United States
Environmental Protection
Agency
Industrial Environmental
Research Laboratory
Research Triangle Park NC 27711
Research and Development
EPA-600/S7-84-090 Sept. 1984
Project  Summary
Homer  City  Multistream  Coal
Cleaning  Demonstration:
A  Progress  Report
D. W. Carey, S. T. Higgins, A. A. Slowik, R. D. Stoessner, C. W. Sypult,
J. H. Tice, M. E. Till, and E. A. Zawadski
  This  report gives  an  overview of
ongoing testing and evaluation of the
Homer City Coal Cleaning Plant, built to
enable the Homer City Power Complex
to meet sulfur dioxide (SO2) emission
levels mandated by the  Pennsylvania
and Federal governments.
  The plant was constructed as a result
of an extensive comparative evaluation
of flue gas desulfurization (FGD) and
physical coal cleaning. The Homer City
System,  The  Multistream  Coal
Cleaning System (MCCS), was chosen
as an economical alternative to FGD.
  The plant contains circuits for clean-
ing coarse, medium, and fine coals and
for recovering fine and very fine coals.
The  dominant type  of  cleaning
equipment used in the plant is the dense
medium cyclone.
  The original "93 plant" configuration
was  never able  to clean coal to the
conditions specified in the plant design.
An extensive  test  and evaluation
program was begun to  identify and
correct the causes of plant operating
problems.  After extensive pilot plant
equipment  tests  and  engineering
studies were completed, recommen-
dations were made for plant modifica-
tions neccessary to correctthe design
and operating deficiencies of the plant.
Extensive modifications were made to
one of two parallel processing trains in
the plant (the "B" circuits), and  a test
program was initiated to evaluate these
corrective measures.
  The recently  modified "B" circuits
have not yet met  design conditions.
Presently,  the fine and medium coal
circuits are undergoing an evaluation to
determine why the cyclones  are not
operating at predicted levels and to test
further proposed corrective actions in
actual operation.
  This Project Summary was developed
by  EPA's  Industrial  Environmental
Research  Laboratory, Research
Triangle Park. NC, to announce key
findings of the research project that is
fully documented in a separate report of
the same title (see Project Report order-
ing information at back).

Introduction
  The  Homer  City  Power  Complex
consists of two 600 MW boiler/turbine/
generator units and one 650 MW unit, fed
primarily from two dedicated mines and
from other sources within 30 mi (48 3 km)
of the plant.
  Units 1 and 2 (600 MW) at the genera-
ting station must meet an SO2 emission
limit of 3 7 lb/106  Btu  (1590 ng/J)
mandated by the Pennsylvania Depart-
ment  of Environmental Resources
(PA.DER). Unit 3 must comply  with an
EPA New Source Performance Standard
(NSPS) limiting  SO2 emission levels to
1.2 lb/106 Btu (51 6 ng/J).
  To meet both emission levels using the
captive   coal  reserves  on-site,  two
compliance  strategies  were  initially
considered- the  first considered a  coal
cleaning system in Units 1 and 2 and a
FGD system  for  Unit 3; the second, the
MCCS,  involved constructing  and
operating a  coal preparation plant to
produce two grades of compliance coal
capable of meeting both emission regula-
tions. Evaluating  both  strategies led to
the conclusion that the MCCS would offer

-------
substantial capital, operating,  mainte-
nance, effluent disposal, and boiler oper-
ating costs savings over FGD.
  This report chronicles the history of the
MCCS coal preparation plant, describes
its design and operating problems, sum-
marizes  corrective  measures,  and
provides some preliminary results of tests
on the modified portion of the plant.

Coal Preparation Technology
Operations and Equipment
  Coal  preparation or benefication is
used to remove mineral matter from coal.
Since  the advent  of  sulfur emission
regulations, many development activities
have focused on coal desulfurization.
  Several different unit operations are
used in coal  preparation, including size
reduction,  size classification,  coal
cleaning, dewatering and drying, and pol-
lution  control/waste  disposal.  Modern
commercial coal preparation plants crush
coal  and separate the  particles into
several size ranges which may be defined
as  coarse, medium, or fine.  Each size
fraction is usually processed in a separate
circuit using  equipment suitable to the
size range and cleaning objectives.
  Size  reduction  liberates  mineral
impurities and produces the range of
sizes  needed in subsequent cleaning
activities. Size reduction  is mechanical:
equipment breaks the coal by impaction,
compression, splitting, shearing, or attri-
tion.  Primary  size  reduction  usually
involves rotary  breakers  or crushers;
second and  third stages,  crushers or
mills
   Size classification is commonly used to
 remove fines prior to size reduction a nd to
 separate  size  ranges prior  to further
 processing  or   sale.  The  major
 classification  technique  is  wet  or  dry
 screening. The  most  common screens
 used in coal  preparation are-

   — Perforated plate and square-opening
     wire screens that shake or vibrate.

   — Curved  stationary  screens  (sieve
     bands)  to  separate  fine  and
     intermediate size particles  in water
     slurries.

   — Classifying cyclones to separate fine
     coal particles from coarser fractions.


   Coal is most  commonly cleaned in
 equipment that relies on differences in
 the size, shape, and specific gravity of
 particles for separating the organic  and
 mineral coal particles.
  Jigs remove mineral matter and mining
refuse from coarse and intermediate size
coal, using hydraulic pressure to stratify a
bed of coal.
  Wet concentrating (Deister) tables use
water to separate or wash intermediate
and fine size coal on a vibrating ribbed
surface.
  Hydrocyclones  process a  slurry  of
medium  or  fine  size  coal  in  large
quantities at relatively low cost.
  Dense medium  separators  include
dense   medium  vessels  and  dense
medium  cyclones.  Both   types  of
separators are fed a slurry of sized coal,
water,  and  magnetite. The  amount of
magnetite can be adjusted to control the
separating  specific  gravity. The vessels
are static baths in which the less dense
clean coal particles float and the heavier
refuse   particles sink.   The  cyclones
separate coal and refuse by centrifugal
force: the  heavier refuse particles are
forced to the outside of the cyclone and
are  removed through  the  underflow
orifice at the cyclone apex; the less dense
coal particles  are  transported  to  the
center  of the cyclone  where they are
removed via the vortex finder as the clean
coal overflow. In addition to the vessel or
cyclones,  the  dense  medium  circuit
contains equipment for  controlling the
slurry density and recovering magnetite
for reuse.

Performance Criteria
   Several criteria are used  to evaluate
the  performance  of   coal  cleaning
equipment  and are classified according
to the degree to which they depend on the
characteristics of the coal being cleaned.
Some   criteria   are  dependent,  either
directly or indirectly, and some are, under
certain  circumstances,  essentially
independent. Dependent criteria include:
weight  yield,  Btu  recovery,  emission
parameter   (of  clean  coal),  emission
reduction, recovery  reduction, misplaced
material,  yield  error,  and  ash  error.
Independent criteria  include: probable
error, error area, and imperfection.

Design of the 93 Plant
   In 1975, owners of the  Homer  City
Power Complex decided to proceed with
the design  and construction of a complex
coal  cleaning  system   using   dense
medium   cyclones as  the  primary
component of deep coal cleaning for Unit
3 NSPS compliance.
   The   basic coal cleaning technology
initially implemented at Homer City was
well established; however, several new
process design features and innovations
were   incorporated  into  the  system
including:

  — Raw coal crushing was controlled to
    minimize  production  of very fine
    coal.

  — Dense medium cyclones, commonly
    used to perform gravitational clean-
    ing  of  sized  coal, were used  to
    separate coal and ash at smaller
    particle sizes  and lower  specific
    gravity than normally used in com-
    mercial practice.

  — Scavenging equipment  was incor-
    porated in  the fine coal processing
    circuits to recover about 95 percent
    of the energy in the coal fed to the
    preparation plant.

  — Efficient pollution  control  devices
    and methods of  residue disposal
    were used  to minimize the environ-
    mental  impact of coal cleaning. The
    process water was recirculated to
    the  coal cleaning  operation to pro-
    vide a closed water circuit.

  The  93 plant contained circuits  for
cleaning coarse, medium, and fine coal as
well as circuits for recovering fine and
very fine coal. The dominant  type of
cleaning equipment used in the plant was
the  dense  medium  cyclone  (DMC).
Hydrocyclones  and  concentrating
(Deister) tables  were used to reclean fine
coal from the underflow of the fine-coal,
low-gravity DMC circuit. Thickeners were
used to close the water circuit and to help
recover fine and very fine coal.
  The coarse coal, 1 % x Vt in. (31.8 x 6.3
mm), was processed through 24 in. (61.0
cm) diameter heavy media cyclones at  1.8
specific gravity  (s.g.). The overflow from
this separation  was screened to remove
water, and  the resultant  material was
used  as a component of the middling
product for Units 1 and 2. The underflow
was discarded as refuse.
  The  medium  coal circuit produced two
products. The 14-in. x 9 mesh (6.3 x  2.0
mm), was processed in 14 in. (35.6 cm)
s.g. The overflowof this separation (deep-
cleaned  product)  was  split;  57 percent
was used in the deep-cleaned product, 43
percent  in  the middling  product.  The
underflow   of   this   separation  was
reprocessed at  1.8 s.g. to recover usable
coal for Units 1 and 2.
  The fine coal, 9x 100 mesh (2.0x0.15
mm),  was processed in 14 in. (35.6 cm)
DMC's after being reclassified to remove
any very fine material to avoid an adverse

-------
effect on product quality. The underflow
was recleaned (using hydrocyclones and
Deister tables) and used in the middling
product. Material  finer than 100 mesh
(0.15  mm) was  not  cleaned, but  by-
passed to the middling product.

Evaluation and Modification
of the 93 Plant
  Because  of  several  design  and
operating  problems,  the  plant  never
produced  the  projected  quality  and
quantity of product coal. The three major
problems  identified with these circuits
were:

  — Poor water feed to the plant and poor
    water distribution  in  the circuits
     made it impossible to run the plant
    for any sustained time and maintain
    conditions needed for proper equip-
     ment operation.

  — The low gravity  DMC circuits failed
     to achieve design performance even
     when design operating  conditions
     were attained.

  — Magnetite losses in the DMC fine
     coal  cleaning  circuits  were
     excessive.

  To  rectify these  problems,  a
cooperative pilot plant test program was
conducted by the Department of Energy
(DOE), EPA, and the Homer City owners.
Thirty-six tests were conducted on an 8
in.  (20.3 cm)  DMC  with  the cyclone
operated at a nominal feed rate, at 1.3s.g.
with 9 x 100 mesh (2.0 x 0.15 mm) coal.
Statistical evaluation  was performed by
Bituminous Coal Research, Inc., and the
following conclusions  characterize
cyclone operation at low gravity with fine
coal:
  — Dense medium cyclone performance
     improves as particle size of the feed
     coal increases.

  — Cyclone performance, as measured
     by the dependent criteria and per-
     cent sulfur reduction, is statistically
     related to flow rate level.

  — Cyclone performance, as measured
     by the dependent criteria, is related to
     the size of the inlet orifice.

  — Dense media cyclone performance
     improves as the percent of coal in the
     slurry decreases.

  — The  cyclone  operating parameters
     investigated  are, in general, more
     highly correlated with independent
     measures of  cyclone  performance
     than with dependent or sulfur-based
     criteria.

   — For the test matrix under investiga-
     tion, cyclone operating  conditions
     corresponding to a 1.5 in. (3.81 cm)
     orifice  size,  120 gpm (454.3 l/s)
     flow rate, and 7:1 media to coal ratio
     produced best overall cyclone per-
     formance.

   In addition  to the  pilot plant tests,
 several cleaning plant consultants and
 engineering  firms were requested to
 survey the  existing plant  and  propose
 corrective measures.
   As a result of these efforts, the "B" side
 of the  93 plant was extensively modified
 and started up in 1982.
   Although   the  coarse  coal  circuit
 cleaning equipment was  not changed, it
 now processes a minimum coal size of Ve-
 in. (3.15 mm) instead of 1/4-in. (6.35 mm).
 The coarse coal is separated at 1.8 s.g. in
 24 in.  (61.0 cm) cyclones into a middling
 product and refuse.
   The  medium coal circuit was changed
 to process coal in the size range of Vs-in. x
 16 mesh (3.15 x 1.0mm) instead of Vi-in.
 x 9 mesh (6.35 x  2.0  mm) and the low
 gravity DMC underflow is  recleaned in
 hydrocyclones and concentrating tables
 instead of only in dense medium cyclones.
  The  major changes in the fine coal
 circuit  involve  redefining the coal size
 from 9 x 100 mesh (2.0x0.15 mm)to 16x
 100 mesh (1.0 x 0.15 mm), the use of
 fifteen 8 in. (20.3 cm) cyclones to replace
 the former bank of eight 14 in. (35.6 cm)
 cyclones, the use of a low head static feed
 tube to stabilize inlet pressure, and the
 use of special screening devices to elimi-
 nate the 100  mesh (0.15 mm) "slimes"
 before processing.

 1982  Plant Performance
  In 1982 modifications to solve major
operating problems in  the MCCS were
completed on the "B" circuits within the
plant. The program to test the modified
"B" circuits has centered around the
evaluation of  the revised  low  gravity
circuits  for   cleaning   medium  and
fine/very  fine  size  coal. Testing has
included that   needed  for  start-up,
conceptual design  verification, and per-
formance evaluation of the low  gravity
modifications.  Performance evaluations
of  the  1982 plant configuration have
centered on the medium and fine coal
cleaning circuits to improve the  quality
and yield of the Unit 3 product.
 Medium Coal Circuit
  Tests were conducted during the start-
 up period to optimize performance of the
 14-in. (35.6 cm) diameter heavy medium
 cyclones in the medium coal circuit which
 operates  at  low specific  gravity. The
 cyclones fell just short of the targeted
 quantity and   quality  requirements
 necessary to meet design conditions for
 producing compliance coal. In an effort to
 pinpoint the problem areas within this cir-
 cuit, an individual cyclone was modified
 for  further testing.  This single cyclone
 within  the  bank was  sampled  under
 various operating conditions to determine
 the effects of operating parameters on
 performance. To date, the most dramatic
 effects  in cyclone  performance  were
 observed when  the plant medium was
 purged and recharged with fresh E grade
 magnetite.  (Magnetite  grade  is
 determined by the weight percent pass-
 ing a 325 mesh or 0.045 mm screen: B
 grade is 90 percent passing, E grade is 95
 percent  passing, and   F  grade  is  98
 percent passing  the classification point.)
 Under these conditions, the performance
 at 1.34 s.g. separating  gravity  met the
 design sharpness of separation criteria
 (i.e., a probable error of  0.03).


 Fine Coal Circuit
  Optimization testing, including cyclone
 bank  modifications  and  variation  of
 operating conditions, could not achieve
 design conditions. As a result, a detailed
 performance analysis began on a single
 cyclone within a five cyclone bank. As
 with the dense medium  cyclones above,
 the   most  dramatic  performance
 improvement occurred  when the  plant
 medium   was  recharged  with  fresh
 magnetite. However,the  cyclone did not
 achieve design performance using fresh
 magnetite alone. Future testing will be
 performed to define remedial measures
 which  can  be  prescribed  to  achieve
 design separating efficiency.

 Future Testing
  Present and future work is aimed at
 determining why the 8 in. (20.3 cm)
dense medium cyclone at the Homer City
 Coal  Cleaning  Plant  behaves  so
 differently from  the pilot plant  cyclone
tested at the DOE facility. Future  plant
testing  will investigate  the effects of
cyclone geometry, inlet pressure, cyclone
orientation,  finer-sized  magnetite,
 medium-to-coal  ratio,   and coal  size
distribution on the performance of  the 8
 in. (20.3 cm) cyclone.

-------
   Conclusions
    Experience over the past 6 years at the
   Homer  City  Coal Cleaning  Plant  has
   indicated that fine coal cleaning at low
   specific gravity is possible, with a good
   potential  for  recovering  fuel  that  is
   remarkably free of ash and pyritic sulfur.
   To reach full potential, it is necessary to
   control  the feedstock to  the cleaning
   devices, to specially engineer the clean-
   ing devices for their specific coal cleaning
   function,  and  to closely  control  the
   devices in the plant circuits.
    In addition, successful operation of any
   coal cleaning process depends  on the
   characteristics of the coal reserves to be
   cleaned. A system that meets coal quality
   Specifications when operating on  coal
   from one reserve may not perform as well
   when operating with coal from an over- or
   underlying seam or in a distant part of the
   same seam.
    Future application of coal cleaning to
   meet  extremely  low  ash  and  sulfur
   criteria  should  be  proposed  with
   sufficient lead time to extensively sample
   the  reserve   bases  proposed  for the
   operation  and  to  test  the cleaning
   efficiency   of  the  low specific
   gravity  device on  coal  that  is
   representative of  the reserve.   Plant
   design  should  provide  accurate
   classification,  sufficient  separating
   equipment capacity, and a system to effi-
   ciently by-pass fine coal that cannot be
   processed.  Since   it appears   that
   separating efficiency  is enhanced using
   fine  magnetite  in   the   system,  the
   magnetite  recovery equipment must be
   optimized  for  the  applications  and
   slurries being processed.
          D. W. Carey, S. T. Higgins, A. A. Slowik. R. D. Stoessner. C. W. Sypult, J. H. Tice, M.
           E.  Till, and E. A. Zawadzki are with the Pennsylvania Electric Company,
           Johnstown. PA 15907.
          James D. Kilgroe is the EPA Project Officer (see below).
          The complete report, entitled "Homer CityMultistream Coal Cleaning Demonstra-
           tion: A Progress Report," (Order No. PB 84-214 181; Cost: $8.50, subject to
           change) will be available only from:
                  National Technical Information Service
                  5285 Port Royal Road
                  Springfield, VA 22161
                  Telephone:  703-487-4650
          The EPA Project Officer can be contacted at:
                  Industrial Environmental Research Laboratory
                  U.S. Environmental Protection Agency
                  Research Triangle Park. NC 27711
                                           •(r U S GOVERNMENT PRINTING OFFICE, 1984—759-015/7827
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Official Business
Penalty for Private Use $300

-------