United States
Environmental Protection
Agency
Municipal Environmental Research -
Laboratory
Cincinnati OH 45268            ,
Research and Development
EPA-600/S2-82-035 Mar. 1983
Project  Summary
Costs  of  Remedial  Response
Actions at Uncontrolled
Hazardous Waste  Sites

Howard L Rishel, Terence M. Boston, Curtis J. Schmidt, and Oscar W. Albrecht
  This study updates previously esti-
mated  costs for remedial response
actions at uncontrolled  and aban-
doned hazardous waste disposal sites.
Costs for 35 remedial action opera-
tions were estimated for the United
States and for the Newark, New Jer-
sey, area. These estimates were based
on mid-1980 price levels.
  Cost components for capital and
operating expenses were estimated
for independent unit operations, and
total and life cycle average costs were
computed. An example is included to
show the user how to estimate costs
for complete  remedial  response
activities.
  This  Project Summary was de-
veloped by EPA's Municipal Environ-
mental Research  Laboratory.
Cincinnati. OH, to announce key find-
ings of the research project that is
fully documented in a separate report
of the same title (see Project Report
ordering information at back).

Introduction
  Past disposal of hazardous wastes is
one of the very serious problems facing
the Nation today. Wastes at uncon-
trolled and abandoned disposal  sites
contain toxic, reactive, ignitable, corro-
sive,  and  persistent  hazardous sub-
stances that pose significant  risks to
public health and the environment.
  To deal with potential risks. Congress
passed  in  1980 the Comprehensive
Environmental Response,  Compensa-
tion and Liability Act (CERCLA), fre-
quently referred to as the "Superfund."
The Act calls for a broad response and
liability mechanism for dealing with
toxic substances pollution and requires
the U.S.  Environmental Protection
Agency (EPA) to identify the hazardous
substances and reportable quantities of
such substances that may escape to the
environment. The Act further provides
for government response to actual and
threatened releases, determination of
the liability of polluters, and a joint
government-industry response fund to
cover costs for cleanup and restoration.
  To assist those involved in estimating
the costs of remedial response actions
(e.g., containment, cleanup, and resto-
ration), EPA sponsored this  study to
review and update engineering designs
and related costs. The tasks included
identification  of appropriate designs
from the available literature and revi-
sion of the associated capital and oper-
ating  costs to reflect recent prices.
Individual costs were estimated for unit
operations (specific types of remedial
actions), and these were then combined
for estimating the costs of complete
remedial  action  responses at uncon-
trolled or abandoned  landfills or
impoundment sites. The  full  report
includes the following.

  • Conceptualized descriptions of the
    uncontrolled landfill  and surface
    impoundment disposal sites;
  • Generalized discussions of the 35
    unit operations (21 for landfills and

-------
Table 1.    Average U.S. Low and High Costs of Unit Operations for Medium-Sized Landfill Sites

                                                      Average U.S. Cost $ Per Unit*
Initial Capital
Unit Operations
1. Contour grading and
surface water diversion
2. Bituminous concrete
surface sealing
3. Revegetation
4. Bentonite slurry trench
5. Grout curtain
6. Sheet piling cutoff wall
7. Grout bottom sealing
8. Drains
9. Well point system

10. Deep well system

11. Injection
12. Leachate recirculation
by subgrade irrigation
13. Chemical fixation
14. Chemical injection
15. Excavation and reburial
16. Ponding
1 7. Trench construction
18. Perimeter gravel
trench vents
19. Treatment of contami-
nated ground water
Unit
Site area, ha

Site area, ha

Site area, ha
Wall face area, m2
Wall face area, m2
Wall face area, m2
Site area, ha
Pipe length, m
Intercept face area, m2

Intercept face area, m2

Intercept face area, m2

Site area, ha
Site area, ha
Landfill volume, m3
Landfill volume, m3
Site area, ha
Trench length, m

Trench length, m

Contaminated water.
Low
15,300

67,300

3,450
54.5
600
73
5,282,000
72.7
62.5

11.6

77

5.270
69, 100
1.67
116
647
12.2

99.2


High
17,900

92,700

16,500
96.1
1,209
108
10,209,000
106
105

18.3

90

8.360
130,000
3.28
120
1,028
14.34

144


Life Cycle Costs
Low
16,300

67,300

14.300
61.2
937
73
5,296,000
357
107

28.6

1,760

19,700
82,500
2.16
116
647
15.11

100


High
19,900

92,700

18,100
103
1.880
108
10,224,OOO
416
153

37.2

1.785

24,000
145,000
3.81
120
1,028
20.32

146


Total Units Used**
5.4 ha site area

5.4 ha site area

5.4 ha site area
10,800 m2 wall face area
10,800 m2 wall face area
10,800 m2 wall face area
5.4 ha site area
260 m pipe length
2,000 m2 intercept face
area
4,800 m2 intercept face
area
550 m2 intercept face area

5.4 ha site area
5.4 ha site area
150,000 m3 landfill volume
596,000 m3 landfill volume
5.4 ha site area
930 m trench length

935 m trench length


                          L/d

20. Gas migration control -
    passive                Site perimeter, m
21. Gas migration control -
    active                 Site perimeter, m
             1.52       2.57       2.52       4.38  440,740 L/d
                                                     contaminated water

             161        241       168       256  935 m site perimeter

             113        173       167       279  935 m site perimeter
 * Mid-1980 dollars, 10-year life cycle, 0 & M costs are discounted at 11.4% to present value, capital costs are not amortized.
** For 5.4 ha site.
    14 for surface impoundments), and
    the   methodology  for  cost
    estimation;
  • Detailed cost information for each
    of the 35 unit operations and their
    components;
  • Cost estimation examples for com-
    plete remedial/response  scena-
    rios;
  • Evaluation of scale economies and
    regional variation of costs; and
  • Unit  costs for all capital and O&M
    components.

Findings
  The updated cost estimates are use-
ful for preliminary comparisons of costs
for alternative unit operations that per-
form the same function. The unit opera-
tion costs can be combined to estimate
total  costs  of complete  remedial
response actions. The user is cautioned
however, that  the  approach  is only a
first  approximation  of total costs,  as
many components are affected by site-
specific considerations.  Considerable
additional research in evaluating tech-
nical  cost differences is needed. As
more remedial  response activities at
uncontrolled and abandoned sites are
undertaken, the cost estimates should
be modified to reflect more nearly the
actual conditions. Average cost  esti-
mates for medium-sized sites are pre-
sented in Tables 1 and 2for landfills and
surface impoundments, respectively.

Conclusions and
Recommendations
  Little is known about the actual costs
involved in cleanup at uncontrolled and
abandoned  hazardous waste  disposal
sites.  The  literature   on  remedial
response activities refers mostly to a
national  and industrywide approach.
Cost information, where available,  is
highly aggregated. Critical components
of cost are frequently  omitted. This
study attempts to  overcome  some of
these deficiencies.
  The primary product of this study is a
cost estimating methodology  that can
be consistently applied to each of the
identified unit operations. The resulting
cost estimates can be used to compare
costs for alternative remedial response
actions that perform the same function
(e.g., prevent infiltration) and to com-
pute combined cost estimates for oper-
ations   that  constitute   a   complete
remedial response scenario. The user is
cautioned, however, that a simple com-
parison of these costs does not address
the many technical differences in the
capabilities or efficiencies of alternative
operations  under  site-specific  condi-
tions. The  site profiles  used for this
study were conceptualizations of gen-
eral environmental settings; thus they

-------
Table 2.    Average U.S. Low and High Costs of Unit Operations for Medium-Sized Surface Impoundment Sites
                                                      Average U.S. Cost $ Per Unit*
                                                   Initial Capital
                                                                       Life Cycle Costs
      Unit Operations
                                Unit
    Low
     High
            Low
High
Total Units Used**
22. Pond closure and contour
    grading of surface
23. Bituminous concrete
    surface
24. Revegetation
25. Slurry trench cutoff wall
26. Grout curtain
27. Sheet piling cutoff wall
28. Grout bottom seal
29. Toe and underdrains
30. Well point system
                           Site area, ha

                           Site area, ha
                           Site area, ha
                           Wall face area, m2
                           Wall face area, m2
                           Wall face area, m2
                           Site area, ha
                           Pipe Length, m
                           Intercept face area, m2
 26.900     35,100    35,900    53,500  0.47 ha site area
31. Deep well system       Intercept face area, m2

32. Well injection system    Intercept face area, m2
33. Leachate treatment
34. Berm reconstruction
35. Excavation and disposal
    at secure landfill
                           Contaminated water,
                          L/d

                           Replaced berm, m3

                           Impoundment
                           volume, m3
 48.500
  2,540
   60.1
    326
   76.8
868,000
    316
   62.3

   33.2

   31.3
    1.16

    2.98


    260
   70
1.621
  700    48,500     70,700  0.47 ha site area
3\820     3,970      5,450  0.47 ha site area
  106      60.1        106  4,165 m2 wall face area
  631       343        649  4.104 m2 wall face area
  115      94.6        135  4,100m2 wall face area
  000  1,024,000   1,792,000  0.47 ha site area
  609     1.550      1,960  60 m pipe length
  117       321        398  300 m2 intercept
                            face area
 60.3     114.4        149  950 m2 intercept
                            face area
 55.5       109        141  950 m2 intercept
                            face area

  1.96      4.49       8.14  51,870 L/d
                            contaminated water
 3.80      4.00       5.85  410 m3 berm
                                                                268       260       268  5,000 impoundment volume
                                                                11.4% to present value, capital costs are not amortized.
 * Mid-1980 dollars, 10-year life cycle, 0 & M costs are discounted a
** For 0.47 ha impoundment.
do not necessarily represent actual site
conditions.
  Complete  remedial response action
for uncontrolled or abandoned hazard-
ous waste disposal sites typically con-
sists of at least several unit operations.
Scale economies may exist when multi-
ple unit operations requiring  similar
component inputs  are performed, but
the  extent  of  these  economies is
unknown and needs to be researched.
Furthermore, additional  research is
needed  on short- and long-term reme-
dial response actions to address the net
benefits as well as the costs to society.
  The full report was submitted in ful-
fillment of Contract No. 68-01-4885 by
SCS Engineers under the sponsorship
of the U.S.  Environmental  Protection
Agency.
                                         Howard L. Rishel, Terence M.  Boston, and Curtis J.  Schmidt are with SCS
                                           Engineers, LongBeac
                                           EPA Project Officer, s
                                           mental Research Lab
                                         The complete report, er
                                           trolled Hazardous W,
                                           subject to change) wi
                                                 National Techn
                                                 5285 Port Roya
                                                 Springfield, VA
                                                 Telephone: 70c
              , CA 90807; the EPA author Oscar W. Albrecht {also the
              ee below for contact) was with the Municipal Environ-
              •atory, Cincinnati. OH 45268.
              titled "Costs of Remedial Response Actions at Uncon-
              ste Sites," (Order No. PB  83-164 830; Cost: $16.00,
              be available only from:
              cal Information Service
              Road
              22161
              487-4650
                                         For information contact Donald E. Banning at:
                                                 Municipal Envi,
              onmental Research Laboratory
                                                 U.S. Environmental Protection Agency
                                                 Cincinnati, OH 45268
                                                          AU.S. GOVERNMENT PRINTING OFFICE.  1983-659-017/7008

-------
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Postage and
Fees Paid
Environmental
Protection
Agency
EPA 335
Official Business
Penalty for Private Use $300

RETURN POSTAGE GUARANTEED

-------