United States
Environmental Protection
Agency
Municipal Environmental Research
Laboratory
Cincinnati OH 45268
Research and Development
EPA-600/S2-82-101 Mar. 1983
Project  Summary
Performance  Characteristics  of
Package  Water Treatment  Plants
James M. Morand and Matthew J. Young
  The quality of water produced by
package water treatment plants was
investigated in a study conducted on-
site at six selected facilities.  These
sites are but a small sample of the more
than 500 package installations identi-
fied by manufacturers and state agen-
cies through a questionnaire.  The list
by no  means includes all  package
plants operating in the United States.
  The six selected plants were in year-
round operation, used surface water
sources, and served small populations.
The plants  were monitored to assess
their performance and ability to supply
water meeting  the  Interim Primary
Drinking Water Regulations.
  At each plant, grab samples of the
raw water, the treated water, and water
from the distribution system were col-
lected  intermittently  over a 2-year
period.  Data  on turbidity, total coli-
forms, and chlorine residuals were re-
corded on all visits.  Standard plate
counts,  chemicals listed in the U.S.
Environmental  Protection Agency Drink-
ing Water Regulations, and trihalome-
thanes were determined intermittently.
  Only  one treated water sample (a
distribution sample) showed any coli-
forms. Sixty-eight percent of the stand-
ard plate counts for  treated water
showed densities of 10 or fewer organ-
isms per milliliter.
  Three of the plants  met the 1-ntu
turbidity standard on  nearly all occa-
sions, whereas the other three plants
met it on fewer than half of the sam-
pling trips.  Failure of the latter plants
to perform  well is  attributed to  the
variability and quality of their raw water
sources and/or  to the lack of skilled
operators with sufficient time to de-
vote to treatment.
  This Project Summary was developed
by EPA's Municipal Environmental Re-
search Laboratory, Cincinnati, OH, to
announce key findings of the research
project that is fully documented in a
separate report of the same title (see
Project Report ordering information at
back).


Introduction
  The problem of providing acceptable
water supplies to the public is particularly
acute for small communities with limited
financial resources and a lack of compe-
tent treatment plant operators.  Isolated
recreational areas also must provide ac-
ceptable drinking water to their visitors
and staff, often without skilled or experi-
enced water treatment personnel.
  During the last 20 years, cost savings
have been achieved in such situations by
using package water treatment plants.  A
package plant generally consists of pre-
fabricated and largely preassembled clari-
fication and filtration  units  (Figure 1).
These plants are reputed to require mini-
mal operational skill and to be a viable and
economical low-flow alternative to the
custom-built facility. Six such plants were
selected for study (Tables 1 and 2). These
plants were monitored to assess their
performance and  ability to supply water
meeting  the  National Interim  Primary
Drinking Water Regulations, particularly
the turbidity 'and microbiological require-
ments.
  The design of a custom-built treatment
plant should depend on an evaluation of
the nature and quality of  the particular
water to be treated. Package plants are
designed with the goal of producing a
satisfactory quality of treated water from a
range of influent waters.  Flow rates for

-------
                                 03=
          Flocculator
                             Backwash
                           Waste Valves
Tube Settlers
                                                         V.
                                                             Filters






r-



;

! i !; 'I In i
1 I 'Ml l'| i
J ii u {-~trrrdi I
{TVMfjj ft '
i i ! i!::ji
NI i i, n 'i
o-oti — r~ tra-a


1
1
Hj
1 — W


r
P
L_

i X

-i ~-^--
1 — "J^-—






\
Effluent and
Backwash Valves
fi
1 — I]L

Figure  1.    Neptune Microfloc AQ-40 Water Treatment Plant (200 gpm capacity).
plants  on the market range from 10 to
2100 gpm.
  The  financial and personnel limitations
faced by small communities  and recrea-
tional areas can be alleviated  by prefab-
ricated plants of this type. The question of
the adequacy of treatment provided by
these  plants as they are managed  and
operated by small communities and recre-
ational  areas  is  not  answered  by data
available in the literature. This study was
undertaken to collect  reliable onsite in-
formation on the quality of treated water
produced by  package  water treatment
plants.

Results

Turbidity
  The  six water treatment facilities select-
ed for field research had varied success in
their turbidity removals. Four of the plants
(C, T, W, and P) had uniform,  high-quality
source waters, but only three of these (C,
T, and W)  consistently met the 1-ntu
effluent turbidity standard.   The other
three plants (P, V, and R) met the standard
on fewer than half of the visits  made to
them (Table 3).
  The  performance difficulties of Plants
P, V, and R involved the short detention
times  inherent in the design of the treat-
Table 1.    Facilities Studied
Site
W



T



V



M



P



C


Model
Year
Neptune
Microfloc
AQ-40
1973
Neptune
Microfloc
AQ-40
1973
Neptune
Microfloc
AQ-40
1976
Neptune
Microfloc
AQ-112
1972
Neptune
Microfloc
Water Boy
1972
Permutit
Permujet
1971
Design
Flow Population Served/
Rate No. of Meters
fgpm)
200 1500/552



200 WOO/360



200 ~~/423



560 — -/1 680



100 —-/411



200 State park


Average
Volume
Per Day
(gal)
110,000



78,000



72,000



330,000



82,000



57,000


Group
Served
City



City



PSD*



PSD*



PSD*



State
park

Type of
Distribution
Pipe Used
PVC



PVC cast iron
asbestos cement


PVC



PVC



PVC



Asbestos
cement

Source
Surface
impoundment


Surface
impoundment


River



River



Surface
impoundment


River


*PSD - Public Service District

-------
Table 2. Treatment Process Characteristics
Pre- Rapid Mix Flocculation
Site
W



T


V


M


P



C



Table 3.
Chemical
Addition
Cl, alum.
soda ash


Cl, alum.
soda ash.
poly
Cl, alum.
soda ash.
poly
Cl, alum.
soda ash.
poly
Cl, alum.
soda ash.
carbon
(summer)
Cl, alum.
soda ash.
poly

Type d. t
{sec.)
In pipe 3



In pipe 3


In pipe 3


Chamber 30


Chamber
not used


In pipe



Type
Paddle



Paddle


Paddle


Paddle


Paddle



d.t
(min.j
12.8



12.8


14


10


10



Sedimentation
Type Loading
(gpd/fP)
Tubes



Tubes


Tubes


Tubes


Tubes



100



100


100


100


150



Upflow solids contact
2hr. d.t.
rise rate


- 1 gpm/ft2







Filtration

Media Rate notes
(gpm/ft2j
Mixed 5
anthracite 18 in
silica sand 9 in
garnet sand 3 in
Mixed
same as above 5

Mixed 5
same as above

Mixed 5
same as above

Mixed 5
same as above


Silica sand 24 in 2



Poly added
before
tubes


Post soda
ash
Post sodium
hexameta-
phosphate







Soda ash
added
before
filtration
Plant Turbidity Values (ntu)
Plant C

flaw
8.5
6.2
1.2
1.6
2.2
4.0
12.6
5.2
2.2












Clearwell
Effluent
0.3
0.2
0.3
0.1
0.1
0.1
0.7
0.2
0.2












Plant W
Clearwell
Raw Effluent
0.9
5.0 0.3
4.2 0.4
19.0 0.8
9.2 2.0
1 1.5 0.3
12.0 0.2
1 1.0 0.3
29.7 0.9
12.8 0.2











Plant T

Raw
10.0
8.0
6.0
3.2
3.2
3.2
5.8
10.4
3.4












Clearwell
Effluent
1.9
0.2
0.4
1.1
0.2
0.2
0.2
3.2
0.7












Plant V

Raw
4.0
12.0
* __
35.0
*42.0
"10.0
"90.0
"28.0
"19.0
*47.0
"13.0
* 8.0
* 6.0
*> 100.0
"60.0
24.0
13.0
2.7
1.2
3.3

Clearwell
Effluent
1.8
2.8
9.6
1.5
2.0
2.4
8.5
5.4
0.3
1.2
0.8
0.3
0.3
0.5
0.5
1.2
0.3
1.2
1.0
0.5

Plant R
Clearwell
Raw Effluent
0.2
39.0 3.8
40.0 2.6
27.0 2.4
6.0 1-2
3.8 0. 1
73.0 1 1.0
* 3.6 0.1
3.8 0.3
6.0 0.5
*70.0 16.0
*25.0 3.4
*> 100.0 55.0
*>100.0 31.0
* 8.5 2.2
4.3 0.4
* 4.0 1.0
* 9.6 1.9
19.1 1.1
64.0 6.9
8.2 1.0
Plant P
Clearwell
Raw Effluent
12.0 0.8
4.4 2.4
7.0
3.5 1.5
2.0 0. 1
1.2 0.5
15.6 9.7
3. 1 2.2
17.2 1.9












*Averaged Values for Day

ment units, the lack of skilled operators
with sufficient time to devote to treatment,
and (in the cases of V and R) the variability
and quality of the source water.
  The stream source quality at Plant V was
quite variable with the turbidity often ex-
ceeding  100 ntu.  The first eight daily
values obtained at this site over a 4-month
period did  not  comply with  the 1-ntu
standard.   But data  indicated much im-
provement after operational methods were
upgraded  and needed maintenance was
performed.  Daily average turbidities for
the last 12 sampling days  over  an  8-
month period  met the turbidity MCL,  al-
though some values exceeded the limit
Before the changes  in maintenance and
operation, this plant  did not consistently
reduce influent turbidities of 35 to 50 ntu
to adequate levels.  But afterwards,  ef-
fluent turbidities were less than 1 ntu even
when influent turbidities increased from
17 to 100 ntu within a 2-hour period.
  Plant R difficulties in turbidity removal
were also caused by highly variable source
water turbidities and inadequate staff time.
This site had influent turbidity levels that

-------
ranged from 3.5 to> 500 ntu. According
to product literature and a manufacturer's
representative, these peaks could not be
adequately treated at the design capacity
of the unit In fact both  Plants V and R
caused State health department engineers
to voice reluctance about approving plans
for future installations of similarly designed
units with such  highly  variable stream
sources. Nonetheless, even with influent
turbidities of less than 30 ntu, the plant
did not  produce an effluent below 1  ntu
because of inadequate operator skill.
  Though Plant P had a  reservoir as its
source and thus showed consistently low
influent turbidities (1 7.2 ntu maximum),
effluents exceeded the 1  ntu limit in six
out of the nine samples taken.  This poor
record was traceable to lack of operator
attention.  Though the plant operated an
average of nearly 14 hours per day, the
operator was present for no more than 2
hours.
  Plants C, W, and T met the turbidity
requirements on nearly  all occasions:
Plant C effluents measured 1 ntu at every
sampling. Plant  W exceeded the  limit
once, and Plant T failed to meet the MCL
twice. At Plant T, two high effluent turbid-
ities of 1.9 and 3.2 ntu  were measured
and found to be caused by a pump failure
and a distribution system problem requir-
ing extensive operator attention.  All three
facilities had low-turbidity sources (1.2 to
29.7 ntu) and high-quality operators.
Total Coliforms and Standard
Plant Counts
  Total coliform determinations for treat-
ed water from all six  plants showed no
coliforms, with the exception of one distri-
bution system sample taken at a residence.
Total coliforms in raw water samples from
the six water treatment plants varied up to
10,000/100 mL. Two of the three facili-
ties using river sources  had the highest
total coliform densities, with typical raw
water levels between 1,000 and 10,0007
100 mL  The plants using impoundments
for  their sources had raw  water total
coliform densities approximately one or-
der of magnitude lower than this range.
  The standard plate counts for treated
water from all six facilities were low: 30
percent of the samples had  counts that
were  lower than 1/mL,  and 68 percent
showed densities of 10/mL or lower. The
highest standard plate count was 2700/
ml.
  The low standard  plate counts and the
absence of coliforms in the treated water
examined indicate that all six water treat-
ment facilities produced adequately disin-
fected water.

Inorganic Contaminant
  The chemical analyses performed by the
U.S.  Environmental Protection Agency
(EPA) for inorganic contaminants listed in
its drinking water regulations show  that
no maximum contaminants levels (MCL)
listed in the primary regulations were
exceeded in  any influent and effluent
samples.   Five effluent  samples  had
manganese concentrations greater than
the secondary  MCL's,  and two treated
water samples exceeded the recommend-
ed secondary MCL for iron. Results of the
effluent  and distribution system analyses
revealed that 15 of 18 treated  water
samples exceeded sodium levels of 20
mg/L
  Note that the operators of these facili-
ties were not trying to control sodium,
manganese,  or  iron at  the  time  these
samples were collected. Their major con-
cerns were  turbidity removal  and ade-
quate disinfection.

Trihalomethanes
  Four of the six plants  studied had at
least one treated water instantaneous tri-
halomethane (THM) sample with a total
THM concentration greater  than 0.10
mg/L.   The small size of these  water
systems precludes them  from having to
comply with any present THM regulations.
The point of chlorination and  often  the
large free chlorine residuals (>2. mg/L)
detected in the treated water contribute to
these high THM levels. All six of the plants
were originally  equipped with pre-  and
post-chlorination capabilities, but all of the
plants practiced prechlorination during
the study.

General Observations
  The three facilities that were most suc-
cessful (sites C,  T, and W) had competent
operational staffs who devoted sufficient
time to water treatment All had knowledge
of water treatment or great familiarity with
their plants and dedication to their work.
These plants  were characterized by fre-
quent monitoring of the influent and ef-
fluent quality.  Improvement of the water
quality at site V came from  increased
maintenance and more frequent sampling
of water through the plant The staff at site
R lacked adequate knowledge and time to
devote to water  treatment  Distribution
system maintenance requirements kept
this staff from properly maintaining and
monitoring their plant  The small  per-
centage of time spent by the operators at
site P resulted in  poor effluent quality,
even though  the influent turbidity  was
quite low.
Conclusions
  Package water treatment plants manned
by competent operators can readily treat
the turbidity and bacteria of surface waters
that have fairly consistent quality. Reser-
voirs have proved satisfactory for provid-
ing acceptable influent waters.
  Package plants using variable sources
(e.g., streams) require  a high  degree of
operational skill  and near constant  vigi-
lance by the operators.  But regardless of
their source  quality, all package plants
require a minimum level of maintenance
and operational skill.  Lack of this mini-
mum skill and attention precludes  con-
sistently   successful turbidity  removal,
regardless of the influent quality.
  Most package plants are located in rural
or remote areas where it may be difficult to
hire well trained operators.  Small com-
munities  may have to  greatly increase
salaries to attract well qualified operators.
  The full report was  submitted in  ful-
fillment of Cooperative Agreement CR-
806449  by the University of Cincinnati
underthesponsorshipoftheU.S. Environ-
mental Protection Agency.
   James M. Morand and Matthew J. Young are with the University of Cincinnati,
     Cincinnati, OH 45221.
   Thomas J. Sorg is the EPA Project Officer (see below).
   The complete report, entitled "Performance Characteristics of Package Water
     Treatment Plants," (Order No. PB 83-161 018; Cost: $11.50, subject to change)
     will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA 22161
           Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
           Municipal Environmental Research Laboratory
           U.S. Environmental Protection Agency
           Cincinnati, OH 45268
                                                                                . S. GOVERNMENT PRINTING OFFICE: 1983/659-095/1905

-------
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268
Postage and
Fees Paid
Environmental
Protection
Agency
EPA 335
Official Business
Penalty for Private Use $300

RETURN POSTAGE GUARANTEED
                                   U^S  ENViR2PR
-------