                NPDES
      Storm Water Sampling
          Guidance Manual
V .
€
                 U.S. EPA
               Office of Water
                C. K. SMOLEY
             U.S. Environmental Protection Agenqf
             Region 5, Library (PL-12J)
             77 West Jackson Boulevard, 12th Floor
             Chicago, IL 60604-3590

-------
                                            As.
Library of Congress Cataloging-in-Publication Data

Catalog record is available from the Library of Congress.


ISBN 0-87371-961-1

© 1993 by C. K.  SMOLEY
Direct all inquiries to CRC Press, Inc.
2000 Corporate Blvd. N.W.
Boca Raton, Florida 33431

PRINTED IN THE UNITED STATES OF AMERICA
1234567890

Printed on acid-free paper

-------
                                     DISCLAIMER
This document was issued in support of EPA regulations and policy initiatives involving  the
development and implementation of a national storm water program. This document is agency
guidance only.  It does not establish or affect legal rights or obligations.  Agency decisions in
any particular case will be made applying the laws and regulations on the basis of specific facts
when permits are issued or regulations promulgated.  Mention of trade names or commercial
products does not constitute endorsement or recommendation for use.

-------
                                     FOREWORD

Pollutants in storm water discharges from many sources are largely uncontrolled.  The National
Water Quality Inventory,  1990 Report to Congress provides a general  assessment  of water
quality based on biennial  reports submitted by  the States  under  Section 305(b) of the Clean
Water Act.  The report  indicates that roughly  30%  of identified cases of water  quality
impairment reported by the States are attributable to storm water discharges.

Sampling data from storm  water discharges is an important tool which provides information on
the types and amounts of pollutants present.  This data can then  be used to identify pollutant
sources and to develop storm water pollution prevention plans and best management practices
priorities to control these sources.

This manual is for operators of facilities that discharge  storm water associated with industrial
activity and operators  of large and medium municipal separate  storm sewer systems.  This
manual describes the basic sampling requirements for NPDES storm water discharge permit
applications and provides  procedural guidance  on  how to conduct sampling.   Many of the
concepts in this guidance may also be applicable to sampling requirements contained in NPDES
storm water permits.

This document was issued in support of EPA regulations and policy initiatives  involving the
development and implementation of a national storm water program. This document is agency
guidance only.  It does not establish or affect legal rights or obligations.  Agency decisions in
any particular case will be made applying the laws and regulations on the basis of specific facts
when permits are issued or regulations promulgated.

-------
                                                   TABLE OF CONTENTS
                         TABLE OF CONTENTS


                                                                Page

1.  INTRODUCTION  	  1

   1.1  PURPOSE OF THIS MANUAL	  2
   1.2  ORGANIZATION OF THIS MANUAL	  2

2.  BACKGROUND FOR STORM WATER SAMPLING	  5

   2.1  BENEFITS OF SAMPLING  	  5
   2.2  INDUSTRIAL FACILITY APPLICATION REQUIREMENTS	  6
   2.3  MUNICIPALITIES' APPLICATION REQUIREMENTS	  7
   2.4  APPLICATION SUBMITTAL DEADLINES	  8
   2.5  WHERE TO SUBMIT APPLICATIONS	  8
   2.6  WHO MUST SAMPLE 	  9
   2.7  WHEN SAMPLING IS REQUIRED 	 15

       2.7.1  STORM EVENT CRITERIA	 15
       2.7.2  OBTAINING RAINFALL DATA	 18
       2.7.3  DETERMINING REPRESENTATIVENESS  	22
       2.7.4  LOGISTICAL PROBLEMS WITH WHEN TO SAMPLE	23
       2.7.5  WHEN INDUSTRIAL FACILITIES MUST SAMPLE	24
       2.7.6  WHEN MUNICIPAL FACILITIES MUST SAMPLE	28
       2.7.7  USE OF HISTORICAL DATA	29

   2.8  WHERE TO SAMPLE STORM WATER DISCHARGES 	29

       2.8.1  INDUSTRIAL FACILITIES 	30
       2.8.2  MUNICIPALITIES	30
       2.8.3  LOGISTICS OF WHERE TO SAMPLE	31

   2.9  STAFFING CONSIDERATIONS  	31

3.  FUNDAMENTALS OF SAMPLING	35

   3.1  TYPES AND TECHNIQUES OF SAMPLING	35

       3.1.1  SAMPLE TYPE VERSUS SAMPLE TECHNIQUE	36
       3.1.2  SAMPLE TYPE: GRAB AND COMPOSITE SAMPLES	36
       3.1.3  SAMPLE TECHNIQUE: MANUAL VERSUS AUTOMATIC
            SAMPLING 	39

-------
TABLE OF CONTENTS
                    TABLE OF CONTENTS (Continued)

                                                               Page

  3.2  OBTAINING FLOW DATA	41

       3.2.1  MEASURING FLOW RATES	41
       3.2.2  ESTIMATING FLOW RATES	49
       3.2.3  MEASURING TOTAL FLOW VOLUMES FOR THE SAMPLED RAIN
            EVENT	58
       3.2.4  ESTIMATING TOTAL FLOW VOLUMES FOR THE SAMPLED RAIN
            EVENT	58
       3.2.5  REPORTING STORM WATER DISCHARGE FLOW RATES AND
            VOLUMES	67
       3.2.6  MEASURING RAINFALL	67

  3.3  GRAB SAMPLE COLLECTION 	68

       3.3.1  HOW TO MANUALLY COLLECT GRAB SAMPLES  	68
       3.3.2  HOW TO COLLECT GRAB SAMPLES BY AUTOMATIC SAMPLER . . 70

  3.4  FLOW-WEIGHTED COMPOSITE SAMPLE COLLECTION	70

       3.4.1  HOW TO MANUALLY COLLECT FLOW-WEIGHTED COMPOSITE
            SAMPLES  	75
       3.4.2  HOW TO COLLECT FLOW-WEIGHTED COMPOSITE SAMPLES BY
            AUTOMATIC SAMPLER 	80

  3.5  SAMPLE HANDLING AND PRESERVATION	81

       3.5.1  DECONTAMINATION OF SAMPLE EQUIPMENT CONTAINERS  .... 82
       3.5.2  SAMPLE PRESERVATION AND HOLDING TIMES	83

  3.6  SAMPLE VOLUMES  	88

  3.7  SAMPLE DOCUMENTATION  	88

  3.8  SAMPLE IDENTIFICATION AND LABELING  	93

  3.9  SAMPLE PACKAGING AND SHIPPING	93

  3.10 CHAIN-OF-CUSTODY PROCEDURES	94

-------
                                                   TABLE OF CONTENTS
                    TABLE OF CONTENTS (Continued)

                                                                Page

4. ANALYTICAL CONSIDERATIONS  	97

  4.1   INDUSTRIAL REQUIREMENTS	97

       4.1.1  INDIVIDUAL APPLICANTS  	98
       4.1.2  GROUP APPLICANTS  	  101

  4.2   MUNICIPAL REQUIREMENTS  	  102

5. FLEXIBILITY IN SAMPLING  	  105

  5.1   PROTOCOL MODIFICATIONS	  105
  5.2   PETITION FOR SUBSTITUTING SUBSTANTIALLY IDENTICAL
       EFFLUENTS  	  105

       5.2.1  OPTION ONE:  NARRATIVE DESCRIPTION/SITE MAP	  106
       5.2.2  OPTION TWO: USE OF MATRICES TO INDICATE IDENTICAL
            OUTFALLS  	  107
       5.2.3  OPTION THREE:  MODEL MATRICES	  107

  5.3   ALTERNATE 40 CFR PART 136 METHOD 	  116

  5.4   LACK OF METHOD IN 40 CFR PART 136	  117

6. HEALTH AND SAFETY	  119

  6.1   GENERAL TRAINING REQUIREMENTS	  119

  6.2   NECESSARY SAFETY EQUIPMENT	  120

  6.3   HAZARDOUS WEATHER CONDITIONS	  120

  6.4   SAMPLING IN CONFINED SPACES	  120

       6.4.1  HAZARDOUS CONDITIONS IN CONFINED SPACES	  121
       6.4.2  SPECIAL TRAINING REQUIREMENTS	  121
       6.4.3  PERMIT SYSTEM	  121

  6.5   CHEMICAL HAZARDS 	  122

  6.6   BIOLOGICAL HAZARDS  	  122

  6.7   PHYSICAL HAZARDS	  122

-------
TABLE OF CONTENTS
                                  LIST OF EXHIBITS
                                                                                   Page

Exhibit 2-1.   Form 2F Application Requirements	   7
Exhibit 2-2.   Part 2 Group Application Sampling Requirements	   8
Exhibit 2-3.   Municipal Application Sampling Requirements	   9
Exhibit 2-4.   Permit Application Submission Deadlines	  10
Exhibit 2-5.   NPDES Storm Water Program Permitting Authorities   	  11
Exhibit 2-6.   Industrial Facilities Which Must Submit Applications for Storm Water
             Permits	  16
Exhibit 2-7.   Decision Chart for Storm Water Sampling   	20
Exhibit 2-8.   Rain Zones of the United States	21
Exhibit 2-9.   Example of 50 Percent Variance From Average Rainfall	22
Exhibit 2-10.  Logistical Problems of Sampling  	25
Exhibit 2-11.  Checklist for Conducting Dry Weather Evaluations	27
Exhibit 2-12.  Solutions to  Sample Location Problems  	32
Exhibit 3-1.   Sample Type vs. Sample Technique   	36
Exhibit 3-2.   Automatic Sampler	40
Exhibit 3-3.   Comparison of Manual and Automatic Sampling Technique	42
Exhibit 3-4.   Weirs	44
Exhibit 3-5.   Suppressed Flow Over the Weir Crest	45
Exhibit 3-6.   Flumes   	46
Exhibit 3-7.   Palmer-Bowlus Flume	47
Exhibit 3-8.   Example Calculation of Float Method for Unimpeded Open Channel Flow ...  51
Exhibit 3-9.   Example Calculation of Float Method for Estimating Drain Flow Rates	52
Exhibit 3-10.  Example Calculation of Bucket and Stopwatch Method for Estimating
             Flows	54
Exhibit 3-11.  Example Calculation of Slope and Depth Method for Estimating Flow
             Rates	55
Exhibit 3-12.  Typical "c"  Coefficients for 5- to 10-Year Frequency Design Storms	57
Exhibit 3-13.  Example Calculation of Runoff Coefficient/Flow Depth Method for
             Estimating Flow Rates	59
Exhibit 3-14.  Example Calculation of Runoff Coefficient Rainfall Depth Method for
             Estimating Flow Rates	61
Exhibit 3-15.  Example Calculation of Total Runoff Volume From Rainfall Data	62
Exhibit 3-16.  Example Calculation of Total Runoff Volume From Flow Rate Data  	63
Exhibit 3-17.  Recommended Operating Procedures for Taking Grab Samples	69
Exhibit 3-18.  Constant Time - Constant Volume  	72
Exhibit 3-19.  Constant Time - Volume Proportional to Flow Increment	72
Exhibit 3-20.  Constant Time - Volume Proportional to Flow Rate	73
Exhibit 3-21.  Constant Volume - Time Proportional to Flow Volume  Increment	73
Exhibit 3-22.  Example of  Sampling Intervals	74
Exhibit 3-23.  Example of  How to Collect  Sample Aliquot  Volumes Based on Flow, and
             Proportion and Composite in the Field	76

-------
                                                                 TABLE OF CONTENTS
                           LIST OF EXHIBITS (Continued)
                                                                                 Page
Exhibit 3-24.  Example of How to Manually Collect Equal Sample Aliquots Which Are
             Later Flow-Proportioned and Composited in the Laboratory	78
Exhibit 3-25.  Volume of Sample Required for Determination of the Various Constituents
             of Industrial Wastewater	89
Exhibit 3-26.  Field Sheet for Sample Documentation	92
Exhibit 3-27.  Example of Chain-of-Custody Form  	96
Exhibit 4-1.   Subchapter N-Effluent Guidelines and Standards	99
Exhibit 4-2.   Parameters Which Must be Analyzed by Municipal Applicants	   103
Exhibit 5-1.   Petition to Sample Substantially Identical Outfalls (Narrative Description/
             Site Map)	   108
Exhibit 5-2.   Site Map	   113
Exhibit 5-3.   Matrices Demonstrating Substantially Identical Outfalls	   114
Exhibit 6-1.   List of Safety Equipment	   120
APPENDDC A
APPENDIX B
APPENDIX C

APPENDDC D
APPENDDC E
APPENDDC F
               LIST OF APPENDICES

Forms 2F and 1
NOAA Weather Radio Information
Required Containers, Preservation Techniques, Holding Times and 40 Code of
Federal Regulations (CFR) Part 136
References
Glossary
Acronyms

-------
                                                              CHAPTER 1 - INTRODUCTION
           NPDES STORM WATER SAMPLING GUIDANCE DOCUMENT
1.  INTRODUCTION
The 1972 Federal Water Pollution Control Act [(FWPCA), also referred to as the Clean Water Act
(CWA)] prohibits the discharge of any pollutant to waters of the U.S. from a point source unless the
discharge is authorized by a National Pollutant Discharge Elimination System (NPDES)  permit.
Efforts to improve water quality under the NPDES program have focused traditionally on reducing
pollutants in industrial process wastewater discharges and from municipal sewage treatment plants.
Past efforts to address storm water discharges, in particular through the NPDES program, have
generally been limited to certain industrial categories, using effluent limitations for storm water as
a permit condition.

Recognizing the need for more comprehensive control of storm waters discharges, Congress amended
the CWA in 1987 and established a two-phase program. In Phase I, Congress required the U.S.
Environmental Protection Agency (EPA) to establish NPDES requirements for certain classes of
storm water discharges.

    • A storm water discharge for which a permit has been issued prior to February 4, 1987
    • A storm water discharge associated with industrial activity
    • A storm water discharge from a municipal separate storm sewer system serving a population
      of 250,000 or more (large system)
    • A storm water discharge from a municipal separate storm sewer system serving a population
      of 100,000 or more, but less than 250,000 (medium system)
    • A discharge  for which  the  Administrator or the State determines  that  the storm water
      discharge contributes to a violation of a water quality standard or is a  significant contributor
      of pollutants to the waters of the United States.

To  implement these requirements, EPA published on November 16, 1990 (55 Fed. Reg.  47990),
permit application requirements that  include storm water  sampling.  EPA and the States will
subsequently issue NPDES storm water permits based on these applications, and many of these

-------
CHAPTER 1 - INTRODUCTION
permits will require storm water sampling. Congress intended for EPA to address all other point
source discharges of storm water in Phase II of the program.

1.1  PURPOSE OF THIS MANUAL
This manual is for operators of facilities that discharge storm water associated with industrial activity
and operators of large and medium municipal separate storm sewer systems. Storm water sampling
is sometimes difficult due to the unpredictability of storm events and the variable nature of storm
water discharges.  This manual is primarily designed to assist operators/owners in planning for and
fulfilling the NPDES storm water discharge sampling requirements for permit applications as well
as for other storm water sampling needs.

It is assumed that applicants already have a basic understanding of the storm water permit application
requirements.  This document is designed to supplement existing storm water application guidance
by focusing on the technical aspects of sampling.  Since many industrial storm water permits and all
municipal  storm water permits will require regular storm water sampling, many of the concepts in
this guidance may be applicable to sampling requirements contained in NPDES  storm water permits.

The information in this manual pertains specifically to individual industrial storm water applications,
group storm water  applications (Part 2), and municipal  Part 2 storm water permit applications  for
storm water discharges. For information on other storm water application requirements for industrial
facilities and large  and medium  municipal separate  storm sewer systems, see EPA's  Guidance
Manual for the Preparation of NPDES Permit Applications for Storm Water Discharges Associated
with Industrial Activity (EPA-505/8-91-002, April 1991), and EPA's Guidance Manual for  the
Preparation of Part  1 of the NPDES Permit Applications for Discharges from Municipal Separate
Storm Sewer Systems  (EPA-505/8-91-003A, April 1991), respectively.  These manuals can be
requested by calling the Storm Water Hotline [(703) 821-4823] or the National Technical Information
Service (NTIS) [(703) 487-4650].  Additional background documents  for further information  are
listed in Technical Appendix D.

1.2  ORGANIZATION OF THIS MANUAL
This manual explains the basic requirements of storm water sampling and provides procedural
guidance on sampling for permit applications.  Chapter 2 discusses background information (i.e., a

-------
                                                               CHAPTER 1 - INTRODUCTION
summary of permit application requirements, who must sample, when and where to sample, and
staffing considerations).  Chapter 3 presents the fundamentals of sampling (i.e., types of sampling,

obtaining flow data, handling samples, and sending them to the laboratory).  Chapter 4 presents
analytical considerations, including the storm water pollutants  that must be  analyzed under the
regulations.  Chapter 5 discusses regulatory flexibility with respect to storm water sampling, and

Chapter 6 includes health and safety considerations.


Technical Appendices provide information as follows:
      Technical Appendix A—Forms 2F and 1
      Technical Appendix B—NOAA Weather Radio Information
      Technical Appendix C—Required Containers, Preservation Techniques, Holding Times and
      40 Code of Federal Regulations (CFR) Part 136
      Technical Appendix D—References
      Technical Appendix E—Glossary
      Technical Appendix F—Acronyms.

-------
                                    CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
2.  BACKGROUND FOR STORM WATER SAMPLING
This chapter presents background information, definitions, and a description of the fundamentals of
sampling. Specifically, it covers the following areas:

    • The benefits of sampling
    • A summary of storm water application regulations
    • Who must sample
    • When  sampling is required
    • Where to sample
    • Staffing considerations

In response to the 1987 Water Quality Act amendments to the CWA, EPA published the storm water
final rule on November 16, 1990.  In this rule, EPA established the initial scope of the storm water
program by defining the phrase "storm water discharge associated with industrial activity" in terms
of 11 categories of industrial activity and the phrase "large and medium municipal  separate storm
sewer systems" to include municipal systems serving a population greater than 100,000. These terms
are discussed in greater detail in Section 2.6, "Who Must Sample."

In addition to defining the initial scope of the storm water  program, the final rule established permit
application requirements, including requirements for storm water sampling.  Sampling data gathered
for the application will be used to characterize storm water discharges, and will serve as a basis for
establishing requirements in NPDES storm water permits.  It is important to note that the applicant
must report data that are representative of the storm water  discharge, and that the intentional
misrepresentation of discharge  characteristics is unlawful.

2.1  BENEFITS OF SAMPLING
Data that characterize storm  water discharges are valuable to permitting  authorities and permittees
for several reasons. First, storm water sampling provides a means for evaluating the environmental
risk of the storm water discharge by  identifying the types  and amounts of pollutants present.
Evaluating these data helps  to determine the  relative potential for the storm water discharge to
contribute to water quality impacts or water quality standard violations. And, storm water sampling

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
data can be used to identify potential sources of pollutants.  These sources can then be either
eliminated or controlled more specifically by the permit.

2.2  INDUSTRIAL FACILITY APPLICATION REQUIREMENTS
The storm water permit application regulations provide operators of facilities (including those owned
by the government) that have storm water discharges associated with industrial activity with three
application options:  (1) submit an individual application; (2) participate in a group application (a
two-part application); or (3) submit a Notice of Intent (NOI) to be covered by a general permit where
general  permits are  available.   This guidance focuses on sampling requirements for  individual
applications and Part 2 of group applications.  Sampling data generally will not be required for an
NOI, however, the general permit may require sampling during the term of the permit.  State
permitting authorities may also require sampling information for an NOI at their discretion, and
should,  therefore, be consulted prior to submittal.

Industrial facilities submitting  individual applications must submit sampling data on a completed
application Form 2F (entitled "Application  for Permit to Discharge  Storm  Water Discharges
Associated with Industrial Activity").   Facilities selected to be part of the sampling subgroup for a
group application must submit sampling data with Part 2 of the application.  Members of the
sampling subgroup must complete only the quantitative data portions of Form 2F, including Sections
VII, VIII, LX,  and the certification in Section X.  Exhibit 2-1 details the types of information
required for each section  of Form 2F.  Exhibit 2-2 describes what sampling information must be
provided in Part 2 of the  group application. It should be noted  that  States may require the use of
different forms  and submittal of additional documentation.

Form 1 must also be submitted with Form 2F by applicants submitting  individual permit applications.
General information about the facility is provided on Form 1 (i.e., addresses, operators, etc.); it does
not request sampling data. Forms 1 and 2F are reproduced in Technical Appendix A.

Facilities  with  unpermitted  combined discharges of  storm water and process or nonprocess
wastewater must submit Form 2C or 2E, respectively, in addition to Forms 1 and 2F.  Facilities with
storm water discharges combined with new sources or new discharges of process wastewater must
submit Form 2D as well as Forms 1 and 2F.

-------
                                    CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
EXHIBIT 2-1. FORM 2F APPLICATION REQUIREMENTS
Section
2F-I
2F-II
2F-III
2F-IVA
2F-IVB
2F-IVC
2F-VA
2F-VB
2F-VI
2F-VH
2F-vm
2F-IX
2F-X
Requirement
Outfall location(s), including longitude and latitude and receiving water(s)
Facility improvements which may affect the discharges described in the
application
Site drainage map
Estimates of impervious area within each outfall drainage area
A narrative description of pollutant sources (i.e., onsite materials which may
come in contact with storm water runoff)
Location and description of existing structural and nonstructural pollutant control
measures
Certification that outfalls have been tested or evaluated for non-storm water
discharges
Description of method used for testing/evaluating presence of non-storm water
discharges
History of significant leaks or spills of toxic or hazardous pollutants at the facility
within the last 3 years
Discharge characterization for all required pollutants
Statement of whether biological testing for acute or chronic toxicity was
performed and list of pollutants it was performed for
Information on contract laboratories or consulting firms
Certification that information supplied is accurate and complete
Note: See Form 2F and the instructions for more detail on application requirements.
2.3  MUNICIPALITIES' APPLICATION REQUIREMENTS
Operators of large and medium municipal separate storm sewer systems are required to submit a two-
part  application.   Both  parts  contain sampling  requirements:   Part 1  requires information
characterizing discharges from the separate storm sewer system, including field screening sample
data for identifying illicit/illegal connections; Part 2 requires sampling at representative locations and
estimates of pollutant loadings for those sites.  These sampling data are to be used to design a long-
term storm water monitoring plan mat will be implemented during the term of the permit.  The
sampling data that must be submitted in  Parts  1  and 2 of municipal applications are listed  in
Exhibit 2-3. There is no standard application form for municipalities.
                                            7

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
      EXHIBIT 2-2.   PART 2 GROUP APPLICATION SAMPLING REQUIREMENTS
  Quantitative Testing Data

     •  For groups with 4 to 20 members, SO percent of the facilities must submit data; for
        groups with 21 to 99 members, a minimum of 10 dischargers must submit quantitative
        data; for groups with 100 to 1,000 members, a minimum of 10 percent of the facilities
        must submit data; for groups with greater than 1,000 members, no more than 100
        facilities must submit data; there must be 2 dischargers from each precipitation zone in
        which 10 or more members of the group are located, or 1 discharger from each
        precipitation zone in which 9 or fewer members are located.

     •  Sampling and  analysis requirements are described in 40 Code of Federal Regulations
        (CFR) 122.26(c)(l)(i)(E) and 40 CFR 122.21(g)(7). Pollutants to be analyzed depend
        on the type(s)  of industries applying as a group.

     •  Sampling subgroup must provide  all quantitative discharge information required in
        Form 2F Sections Vn-EX plus the certification in Section X.

     •  The group application sampling subgroup must collect grab samples during the first 30
        minutes of the storm event and flow-weighted composite samples as required in 40
        CFR 122.21(g)(7).
2.4  APPLICATION SUBMTTTAL DEADLINES

Deadlines for submitting permit applications and associated sampling requirements are presented in

Exhibit 2-4 for individual and group industrial applications and for municipal applications.


2.5  WHERE TO SUBMIT APPLICATIONS

Storm water discharge permit applications are generally  submitted directly to the permit-issuing

authority.  The appropriate authority is the State, where the State has been granted the authority to

issue NPDES  permits, or the EPA Regional office, where the State  does not have NPDES

authorization.  Exhibit 2-5 indicates which States have approved NPDES  permitting programs.  It

also provides contact names and addresses where applications should be submitted for each State or

EPA Regional Office (depending on who the permitting authority is in each  case).  It should be

noted,  however, that both parts  of  a group application must instead be submitted to EPA

Headquarters. Group applications must be sent to:  Director, Office of Wastewater Enforcement and

Compliance, Attention Mr. William Swietlik,  U.S. EPA, EN-336, 401 M Street, SW, Washington,

DC  20640.
                                           8

-------
                                     CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
        EXHIBIT 2-3.    MUNICIPAL APPLICATION SAMPLING REQUIREMENTS
  Parti
      •  Monthly mean rainfall and snowfall estimates
      •  Existing quantitative data on the depth and quality of storm water discharges
      •  A list of receiving water bodies and existing information concerning known water
         quality impacts
      •  Field screening analysis for illicit connections and illegal dumping
      •  Identification of representative outfalls for further sampling in Part 2
  Parti
      •  Quantitative data from 5 to 10 representative locations in approved sampling plans
      •  Estimates of the annual pollutant load and event mean concentration (EMC) of system
         discharges
      •  Proposed schedule to provide estimates of seasonal pollutant loads and the EMC for
         certain detected constituents in a representative storm event during the term of the
         permit
      •  Proposed monitoring program for representative data collection during the term of the
         permit
Applications submitted by industrial facilities must be certified by a responsible corporate officer as
described in 40 CFR 122.22 (e.g., president, secretary, treasurer, vice president of the corporation
in charge of a principal business function).   Applications submitted  by municipalities  must be
certified by a principal executive officer or ranking elected official as described in 40 CFR 122.22.

2.6  WHO MUST SAMPLE
Operators of facilities that have storm  water discharges associated with  industrial activity and
operators of large and medium municipalities are required to conduct storm water sampling as part
of their NPDES permit applications. Specifically, the following types of industries and municipalities
must sample storm water discharges:

-------
CHAPTER 2 . BACKGROUND FOR STORM WATER SAMPLING
EXHIBIT 2-4. PERMIT APPLICATION SUBMISSION DEADLINES |

Date
Sampling Requirement
Industrial
Individual
Group
• Parti
• Part2
October 1, 1992
September 30, 1991
October 1, 1992
Sampling data due
Sampling subgroup identified
Sampling data due
Municipal :
Large Municipalities
• Parti
• Part2
Medium Municipalities
• Parti
• Part2
November 18, 1991
November 16, 1992
May 18, 1992
May 17, 1993
Illicit connection screening due and
identification of sampling points
Effluent characterization due
Monitoring management program identified
Illicit connection screening due and
identification of sampling points
Effluent characterization due
Monitoring management program identified
*NOI under a general permit is due on October 1, 1992 or the date specified in the permit,
whichever comes first.
       Storm Water Discharges Associated With Industrial Activities - Under Phase I, the storm water
       permit application regulations identify, by  Standard  Industrial Classification (SIC) code  and
       narrative description, 11 categories of facilities considered to be "engaging in industrial activity"
       for the purposes of storm water permit application requirements.  Those facilities included in 40
       CFR  122.26(b)(14)(i) through (xi) of the storm water  permit application regulations with storm
       water point source discharges to waters of the U.S. or separate storm sewers and those designated
       under Section 402(p)(2)(E) of the CWA are required to apply for storm water permit coverage
       by October  1, 1992. Industrial facilities include those that are Federally, State, or municipally
       owned or operated.  Exhibit 2-6 lists these industrial facilities.  The Transportation Act of 1991
       provides an  exemption  from storm water permitting requirements for certain  industrial activities
       owned or operated by municipalities with a population  of less than 100,000.  Such municipalities
       must  submit storm  water discharge permit applications for only airports,  power  plants,  and
       uncontrolled sanitary landfills that they own or operate, unless a permit is otherwise required by
       the permitting authority.

       Municipal Separate  Storm Sewer Systems - Under Phase I, those municipalities with separate
       storm sewer systems serving 100,000 people or more are required to  submit an application for
       discharges from the system.  (Only the part of the population served by municipal separate storm
       sewers  is to be  included in the 100,000  count, not the part served  by combined sewers.)
       Regulated municipalities are listed in Appendices F  through I in the November 16, 1990,  final
       rule or have been designated by their permitting authority.
                                               10

-------
                          CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
  EXHIBIT 2-5.   NPDES STORM WATER PROGRAM PERMITTING AUTHORITIES
CM
I
u
cr
LL
O
GO
cc
O
00
LU
Q
Q.
                                11

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
     EXHIBIT 2-5.
   State
          NPDES STORM WATER  PROGRAM PERMITTING AUTHORITIES
          (Continued)
Authority
Contact
                                     State
                                                           Authority
    Contact
 Alabama      yes     Aubrey White
                      Water Division
                      1751 Dickinson Dr.
                      Montgomery, AL 36130
                      (205)271-7811
 Arizona       no
 California     yes
 Connecticut    yes
 Florida        no
 Hawaii
 Illinois
 Iowa
         Eugene Bromley
         U.S. EPA Region 9
         75 Hawthorne St.
         W-5-1
         San Francisco, CA  94105
         (415) 744-1906
         Archie Matthews
         Storm Water Research Control
          Board
         Water Quality
         901 P St.
         Sacramento, CA 95814
         (916)657-1110
         Dick Mason
         Dept. of Environmental
          Protection
         Water Management Bureau
         Water Discharge Management
         165 Capitol Ave.
         Hartford, CT  06106
         (203) 566-7167
         Chris Thomas
         U.S. EPA Region 4
         345 Courtland St. N.E.
         4WM-FP
         Atlanta, GA 30365
         (404) 347-3633
  yes    Steve Chang
         Dept. of Health
         Clean Water Branch
         Five Water Front Plaza
         #500 Ala-Moana Blvd.
         Honolulu, HI 96813
         (808) 586-4309
  yes    Tim Kluge
         EPA Water Pollution Control
         2200 Churchill Rd.
         P.O. Box 19276
         Springfield, IL 62794-9276
         (217) 782-0610
  yes    Monica Wnuk
         Department of Natural
          Resources
         Wallace State Building
         900 E. Grand St.
         DesMoines,IA 50319-0034
         (515) 281-7017   	
                       Alaska      no      Steve Bubnick
                                           U.S. EPA Region 10
                                           1200 6th Ave.
                                           WD-134
                                           Seattle, WA 98101
                                           (206) 553-8399
                       Arkansas    yes     Marysia Jastrzebski
                                           8001 National Dr.
                                           P.O. Box 8913
                                           Little Rock, AR 72219-8913
                                           (501) 562-7444

                       Colorado    yes     Patricia Nelson
                                           Dept. of Health
                                           Water Quality Control
                                           4210 E. llth Ave.
                                           Denver, CO 80220
                                           (303) 331-4590
                       Delaware    yes
Sarah Cooksey
Dept. of Natural Resources
Surface Water Management
89 Kings Highway
P.O. Box 1401
Dover, DE  19903
(302) 739-5731
                       Georgia     yes     Mike Creason
                                           Dept. of Natural Resources
                                           Environmental Protection
                                           205 Butler St. S.E.
                                           Room 1070
                                           Atlanta, GA 30334
                                           (404) 656-4887
                       Idaho       no     Steve Bubnick
                                           U.S. EPA Region 10
                                           1200 6th Ave.
                                           WD-134
                                           Seattle, WA 98101
                                           (206) 553-8399

                       Indiana     yes     Lonnie Brumfield
                                           Dept. of Environmental
                                            Management
                                           NPDES Permits Group
                                           105 S. Meridian St.
                                           P.O. Box 6015
                                           Indianapolis, IN  46206
                                           (317) 232-8705
                       Kansas      yes     Don Carlson
                                           Dept. of Environment
                                           Water Bureau
                                           Forbes Field, Building 740
                                           Topeka, KS 66620
                                           (913) 296-5555
                                                12

-------
                                      CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
   EXHIBIT 2-5.
       NPDES STORM WATER  PROGRAM PERMITTING AUTHORITIES
       (Continued)
   State
Penmttii*
Authority
      Contact
State     Authority
                       Contact
Kentucky
 yes
Maine
               no
Massachusetts   no
Minnesota
               yes
Missouri
               yes
Nebraska
               yes
New
Hampshire
 no
New Mexico    no
 Douglas Allgeier
 Dept. of Environmental Protection
 Water Division
 18 Reilly Road
 Frankfort, KY  40601
 (502) 564-3410
 Shelley Puleo
 U.S. EPA Region 1
 U.S. EPA/JFK Building/WCP
 Boston, MA 02203
 (617) 565-3525

 Shelley Puleo
 U.S. EPA Region 1
 U.S. EPA/JFK Building/WCP
 Boston, MA 02203
 (617) 565-3525

 Scott Thompson
 Pollution Control Agency
 520 Lafayette Rd.
 St. Paul, MN 55155-3898
 (612) 296-7203
Bob Hentges
Dept. of Natural Resources
Water Pollution Control Program
205 Jefferson St.
P.O. Box 176
Jefferson City, MO  65102
(314) 751-6825
Clark Smith
Environmental Control
Water Quality Division
P.O. Box 98922
Lincoln, NE  68509
(402) 471-4239

Shelley Puleo
U.S. EPA Region 1
U.S. EPA/JFK Building/WCP
Boston, MA  02203
(617) 565-3525

Brent Larson
U.S. EPA Region 6
1445 Ross Ave.
6W-PM
Dallas, TX 75202
(214) 655-7175
                                      Louisiana    no
                                      Maryland    yes
                                      Michigan    yes
                                      Mississippi   yes
                                      Montana    yes
                                      Nevada
                                                  yes
New Jersey   yes
                                      New York   yes
                 Brent Larson
                 U.S. EPA Region 6
                 1455 Ross Ave.
                 6W-PM
                 Dallas, TX  75202
                 (214) 655-7175
                 Edward Gertler
                 MD Dept. of Environment
                 Industrial Discharge Program
                 2500 Broening Highway
                 Baltimore, MD 21224
                 (410) 631-3323
                 Gary Boersen
                 Dept. of Natural Resources
                 Surface Water Division
                 P.O. Box 30028
                 Lansing, MI 48909
                 (517) 373-1982
                 Jerry Cain
                 Dept. of Environmental
                   Quality
                 Office of Pollution Control
                 Industrial Waste Water Branch
                 P.O. Box 10385
                 Jackson, MS 39289-0385
                 (601) 961-5171
                 Fred Shewman
                 Water Quality Bureau
                 Cogswell Building
                 Helena, MT 59620
                 (406) 444-2406
                Rob Saunders
                Conservation and Natural
                  Resources
                Environmental Protection
                123 W. Nye Lane
                Carson City, NV 89710
                (702) 687-4670
                Sandra Cohen
                NJDEPE
                Office of Regulatory Policy
                CN029
                Trenton, NJ  08625-0029
                NJ Hotline: (609)633-7021
                Ken Stevens
                Wastewater Facilities Design
                NY State DEC
                50 Wolf Road
                Albany, NY  12233
                (518)457-1157
                                              13

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
     EXHIBIT 2-5.
     NPDES STORM WATER  PROGRAM PERMITTING AUTHORITIES
     (Continued)
    State
                Pwmittiiic
                Authority
             Contact
                             State
              Authority
                            Contact
  North Carolina   yes
  Ohio
                 yes
  Oregon
yes
  Puerto Rico
                 no
  South Carolina   yes
  Tennessee
                 yes
  Utah
                 yes
Coleen Suiting
Environmental Management
Water Quality Planning
P.O. Box 29535
Raleigh, NC  27626-0535
(919) 733-5083


Bob Phelps
OEPA
Water Pollution Control
P.O. Box 1049
1800 Watermark
Columbus, OH 43266
(614) 644-2034

Ranei Nomura
DEQ-Water Quality
811SW6thSt.
Portland, OR 97204
(503) 229-5256


Jose' Rivera
U.S. EPA Region 2
Water Permits & Compliance
 Branch
26 Federal Plaza, Room 845
New York, NY   10278
(212)264-2911

Birgot McDade
Dept. of Health & Env. Ctrl.
Industry and Agriculture
Waste Water Division
2600 Bull St
Columbia, SC 29201
(803) 734-5241

Robert Haley
Dept. of Environment
Water Pollution Control
150 9th Ave.  N., 4th Floor
Nashville, TN 37243-1534
(615) 741-2275

Harry Campbell
Dept. of Environmental
 Quality
P.O. Box 16690
Salt Lake City, UT 84116
(801) 538-6146
Pennsylvania     yes
Norm Dakota     yes   Sheila McClenathan
                      Dept. of Health
                      Water Quality Division
                      1200 Missouri Ave.
                      P.O. Box 5520
                      Bismarck, ND 58502-5520
                      (701) 221-5210

Oklahoma        no    Brent Larson
                      U.S. EPA Region 6
                      1445 Ross Ave.
                      6W-PM
                      Dallas, TX 75202
                      (214) 655-7175


                      R.B. Patel
                      Environmental Resources
                      Water Quality Management
                      P.O. Box 2063
                      Harrisburg, PA  17120
                      (717) 787-8184

Rhode Island     yes   Angela Uberti
                      Division of Water
                       Resources
                      291 Promenade St.
                      Providence, RI 02908
                      (401) 277-6519


South Dakota     no    Vern Berry
                      U.S. EPA Region 8
                      999 18th St.
                      8-WM-C
                      Denver, CO  80202-2466
                      (303) 293-1630


Texas           no    Brent Larson
                      U.S. EPA Region 6
                      1445 Ross Ave.
                      6W-PM
                      Dallas, TX 75202
                      (214) 655-7175

Vermont         yes   Brian Koiker
                      Environmental Conservation
                      Permits and Compliance
                      103 S. Main St.
                      Annex Building
                      Waterbury.VT  05671-0405
                      (802) 244-5674
                                                14

-------
                                     CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
     EXHIBIT 2-5.
    State
NPDES STORM WATER  PROGRAM  PERMITTING AUTHORITIES
(Continued)
              Authority
     Contact
State
                                     Authority
Contact
  Virgin Islands   yes  Marc Pacifico
                    Dept. of Planning & Natural
                     Resources
                    1118 Watergut Project
                    Christiansted
                    SuCroix, VI  00820-5065
                    (809) 773-0565

  Washington    yes  Gary Kroger
                    Dept. of Ecology
                    Water Quality Division
                    P.O. Box 47600
                    Olympia, WA 98504-7600
                    (206) 438-7529

  West Virginia   yes  Jerry Ray
                    Division of Water Resources
                    1201 Greenbriar St.
                    Charleston, WV 25311
                    (304)348-0375


  Wyoming      yes  John Wagner
                    Dept of Environmental Quality
                    Herschler Building, 4th Floor
                    Cheyenne, WY  82002
                    (307) 777-7082
                          Virginia      yes   Burton Tuxford
                                            Water Control Board
                                            Permits Section
                                            P.O. Box 11143
                                            Richmond, VA 23230-1143
                                            (804) 527-5083

                          Washington    no   Kevin Magerr
                          D.C.              U.S. EPA Region 3
                                            841 Chestnut Bldg.
                                            3WM53
                                            Philadelphia, PA  19107
                                            (215) 597-1651

                          Wisconsin     yes   Anne Mauel
                                            Dept. of Natural Resources
                                            Wastewater Management
                                            P.O. Box 7921
                                            Madison, WI  53707
                                            (608) 267-7364
2.7 WHEN SAMPLING IS REQUIRED

Industrial individual and group applicants must include sampling data from at least one representative

storm event. Operators of large or medium municipal separate storm sewer systems must submit

sampling   data   from  three  different  representative  storm  events.     How   to  determine

"representativeness" and other considerations for when to sample are presented below.


2.7.1  STORM EVENT CRITERIA

Storm water discharge permit application requirements establish specific criteria for the type of storm

event that must be sampled:


    •  The depth of the storm must be greater than 0.1 inch accumulation

    •  The storm must be preceded by at least 72 hours of dry weather

    •  Where feasible, the depth of rain and duration of the event should not vary by more than 50
       percent from the average depth and duration.
                                             15

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
     EXHIBIT
    40CFR
  122J6(b)(14)
    Subpart
        INDUSTRIAL FACILITIES WHICH  MUST SUBMIT APPLICATIONS
       FOR STORM WATER PERMITS
                                      Description
       0)
Facilities subject to storm water effluent limitations guidelines, new source performance standards,
or toxic pollutants effluent standards under 40 CFR, Subchapter N [except facilities which are
exempt under category (xi)].	
               Facilities classified as:

               SIC 24 (except 2434)	Lumber and Wood Products
               SIC 26 (except 265 and 267) . Paper and Allied Products
               SIC 28 (except 283 and 285) . Chemicals and Allied Products
               SIC 29	Petroleum and Coal Products
               SIC 311	Leather Tanning and Finishing
               SIC 32 (except 323)  	Stone, Clay and Glass Products
               SIC 33	Primary Metal Industries
               SIC 3441  	Fabricated Structural Metal
               SIC 373	Ship and Boat Building and Repairing
      (ui)
Facilities classified as SIC 10 through 14, including active or inactive mining operations and oil
and gas exploration, production, processing, or treatment operations, or transmission facilities that
discharge storm water contaminated by contact with, or that has come into contact with, any
overburden, raw material, intermediate products, finished products, byproducts, or waste products
located on the site of such operations.

SIC 10	Metal Mining
SIC 11	Anthracite Mining
SIC 12	Coal Mining
SIC 13	Oil and Gas Extraction
SIC 14	Nonmetallic Minerals, except Fuels	
      (iv)
Hazardous waste treatment, storage, or disposal facilities, including those that are operating under
interim status or a permit under Subtitle C of the Resource Conservation and Recovery Act
(RCRA).                                                                   	
      (v)
Landfills, land application sites, and open dumps that receive or have received any industrial wastes
including those that are subject to regulation under subtitle D or RCRA.	
      (vi)
Facilities involved in the recycling of material, including metal scrapyards, battery reclaimers,
salvage yards, and automobile junkyards, including but limited to those classified as:

SIC 5015	Motor Vehicle Parts, Used
SIC 5093	Scrap and Waste Materials	
      (vii)
Steam electric power generating facilities, including coal handling sites.
      (viii)
Transportation facilities which have vehicle maintenance shops, equipment cleaning operations, or
airport de-icing operations. Only those portions of the facility that are either involved in vehicle
maintenance (including vehicle rehabilitation, mechanical repairs, painting, fuelling, and
lubrication), equipment cleaning operations, or airport de-icing operations, or which are otherwise
listed in another category, are included.

SIC 40	Railroad Transportation
SIC 41	Local and Suburban Transit
SIC 42 (except 4221-25)  .... Motor Freight and Warehousing
SIC 43	U.S. Postal Service
SIC 44	Water Transportation
SIC 45	Transportation by Air
SIC 5171  	Petroleum Bulk Stations and Terminals
                                                    16

-------
                                         CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
   EXHIBIT 2-6.
   40CFR
122.26(b)(14)
   Subpart
        INDUSTRIAL FACILITIES WHICH MUST SUBMIT APPLICATIONS
        FOR STORM WATER PERMITS (Continued)
                                     Description
              Treatment works treating domestic sewage or any other sewage sludge or wastewater treatment
              device or system, used in the storage, treatment, recycling, and reclamation of municipal or
              domestic sewage, including lands dedicated to the disposal of the sewage sludge that are located
              within the confines of the facility, with a design flow of 1.0 million gallons per day or more, or
              required to have an approved pretreatment program under 40 CFR Part 403.  Not included are farm
              lands, domestic gardens, or lands used for sludge management where sludge is beneficially reused
              and which are not physically located in the confines of the facility, or areas that are in compliance
              with Section 405 of the CWA.
     (x)
Construction activity including clearing, grading, and excavation activities except operations that
result in the disturbance of less than 5 acres of total land area and those that are not part of a larger
common plan of development or sale.*	
     (xi)
Facilities under the following SICs [which are not otherwise included in categories (ii)-(x)],
including only storm water discharges where material handling equipment or activities, raw
materials, intermediate products, final products, waste materials, byproducts, or industrial
machinery are exposed to storm water.*
              SIC 20	Food and Kindred Products
              SIC 21	Tobacco Products
              SIC 22	Textile Mill Products
              SIC 23	Apparel and Other Textile Products
              SIC 2434	Wood Kitchen Cabinets
              SIC 25	Furniture and Fixtures
              SIC 265	Paperboard Containers and Boxes
              SIC 267	Converted Paper and Paper Board Products
                                           (except containers and boxes)
              SIC 27	Printing and Publishing
              SIC 283	Drugs
              SIC 285	Paints, Varnishes, Lacquer, Enamels
              SIC 30	Rubber and Misc. Plastics Products
              SIC 31 (except 311)  	Leather and Leather Products
              SIC 323	Products of Purchased Glass
              SIC 34 (except 3441)	Fabricated Metal Products
              SIC 35	Industrial Machinery and Equipment, except Electrical
              SIC 36	Electronic and Other Electric Equipment
              SIC 37 (except 373)  	Transportation Equipment
              SIC 38	Instruments and Related Products
              SIC 39	Miscellaneous Manufacturing Industries
              SIC 4221	Farm Products Warehousing and Storage
              SIC 4222	Refrigerated Warehousing and Storage
              SIC 4225	General Warehousing and Storage	

Source: Federal Register, Vol. 55, No. 222, p. 48065, November 16, 1990.
*On June 11, 1992, the U.S. Court of Appeals for the Ninth Circuit remanded the exemption for construction sites
of less than five acres in category (x) and for manufacturing facilities in category (xi) which do not have materials
or activities exposed to storm water to the EPA for further rulemaking.  (Nos. 90-70671 & 91-70200).
                                                 17

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
These criteria were established to: (1) ensure that adequate flow would be discharged; (2) allow some
build-up of pollutants during the dry weather  intervals; and (3) ensure that the storm would be
"representative," (i.e., typical for the area in terms of intensity, depth, and duration).

Collection of samples during a storm event meeting these criteria ensures that the resulting data will
accurately portray the most common conditions for each site.  However, the permitting authority is
authorized to approve modifications of this definition (especially for applicants in arid areas where
there are few representative events).   Section 5.1 of Chapter 5  discusses general protocol for
requesting  modifications  to  application requirements,  including the definition of "representative
storm."

In determining whether a storm is representative, mere are two important steps to take. First, data
on local weather patterns should be collected  and analyzed to determine the range of representative
storms for a particular area. Second, these results should be compared to measurements of duration,
intensity, and depth to ensure that the storm to  be sampled fits the representativeness criteria.

2.7.2  OBTAINING RAINFALL DATA
Several sources provide  accurate local weather  information for both:   (1) determining  what a
representative storm event is for a particular  area; and (2) assessing expected storm events to
determine whether a predicted rainfall will be "representative," and thus, meet the requirements for
storm water sampling.  The National Oceanic and Atmospheric Administration  (NOAA) National
Climatic Data Center's (NCDC's) Climate Services Branch is responsible for collecting precipitation
data. Data on hourly, daily, and monthly precipitation for each measuring station (with latitude and
longitude) are available to the public on computer diskette, microfiche, or hard copy.  Orders can
be placed by calling (704) 259-0682, by fax  at (704) 259-0876, or by writing to NCDC, Climate
Services Branch, The Federal Building, Asheville, Norm Carolina  28071-2733.

The National Weather Service (NWS) of NOAA can also provide information on historic, current,
and future weather conditions. Local NWS telephone numbers can be obtained from the NWS Public
Affairs Office at (301) 713-0622.  Telephone  numbers are also usually in  local phone directory
listings under "National Weather Service" or "Weather." In addition, NOAA runs the NOAA NWS
                                            18

-------
                                      CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
Weather Radio, which provides continuous broadcasts of the most current weather information. This
broadcast can be accessed with a radio that has a weather band feature.  Approximately 90 percent
of the United  States population is within listening range of the 380 NWS stations.  Technical
Appendix B presents additional information on NOAA Weather Radio, including radio frequencies
for specific locations and a listing of weather band radio manufacturers.  Telephone recordings of
weather  conditions are also provided  by most NWS offices.

Cable TV weather stations and local airports  can also provide weather information.   Weather
information provided by the local newspaper or TV stations should be used only  if more accurate
data (as  described above) are unavailable, since weather  forecasts can change drastically within
several hours.

Someone should be designated at the facility to follow current weather conditions by listening to
NOAA Weather Radio, calling  the  local NWS offices, and watching cable TV weather  news.
Exhibit 2-7 presents a  storm water sampling decision chart for mobilizing field personnel for a
probable storm event.

Annual rainfall statistics can also be used to evaluate  representativeness of storm events.  For
example, Exhibit 2-8 presents  fifteen rain  zones  in  the  United States  and related  storm event
statistics. (These rain zones are not those shown in 40 CFR Part 122 Appendix E.) To determine
typical values of annual storm events  for a particular facility, identify the zone in which the facility
is located. The tabulated information lists the annual  average number of storms and  precipitation
as well as the  average duration, intensity, and depth of independent storm events for each zone.
Care must be taken, however, in using annual rainfall statistics for determining representativeness
of storm events, since the  annual rainfall statistic  may not  be  representative of  seasonal rainfall
events.  If rainfall data is available at  or close to a particular facility, it is preferable to  use this data
for determining average  storm event statistics.

Rainfall data tabulated from NOAA precipitation data indicate for Alaska (not shown in Exhibit 2-8)
that average storm events last from 14 to  24  hours in duration and are 0.6 to  l.OS inches in depth.
Average  storm event data for Hawaii are 9 to 11 hours  in duration  and from 0.6 to 1.6 inches in
depth.
                                             19

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
          EXHIBIT 2-7.    DECISION CHART FOR STORM WATER SAMPLING
                               Follow Dally 48 How Foment
                               Evaluations Via:

                                NOAA Weather Radio
                                Local/Cable News
                                Airport Weather Information
                                         i
                                  Spaculata Probability of
                                  "Representative Storm"
       Continue to Evaluate Impending
               Storm Event
Sat Up Auto Sampler* and/or
   Notify Sampling Craw
                                          20

-------
                                   CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
                EXHIBIT 2-8.    RAIN ZONES OF THE UNITED STATES
   RAIN ZONE

NORTHEAST
NORTH EAST-
COASTAL
MTOATLANTIC
CENTRAL
NORTH CENTRAL
SOUTHEAST
EAST GULF
EAST TEXAS
WEST TEXAS
SOUTHWEST
WEST INLAND
PACIFIC SOUTH
NORTHWEST INLAND
PACIFIC CENTRAL
PACIFIC
NORTHWEST
No.ofStonw Prwap.
Aft

70
63
62
68
55
65
68
41
30
20
14
19
31
32
71
cov

0.13
0.12
0.13
0.14
0.16
0.15
0.17
0.22
0.27
0.30
0.38
0.36
0.23
0.25
0.15
Arg
(in)
34.6
41.4
39.5
41.9
29.8
49.0
53.7
31.2
17.3
7.4
4.9
10.2
11.5
18.4
35.7
COV

0.18
0.21
0.18
0.19
0.22
0.20
0.23
0.29
0.33
0.37
0.43
0.42
0.29
0.33
0.19
Dm*. I— rity
Arg

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
The NWS should be consulted for proper procedures for collecting and interpolating rainfall data if

the applicant elects to collect the data rather than use existing data.


2.7.3 DETERMINING REPRESENTATIVENESS

An example of how to determine whether a rainfall event varies by more than 50 percent (i.e., is

not representative) is shown in Exhibit 2-9.
EXHIBIT 2-9. EXAMPLE OF 50 PERCENT VARIANCE FROM AVERAGE
RAINFALL
Event Type
Average event
50 percent average event
150 percent average event
Duration (hrs.)
5.2
" 26 • •
..'- ••"."r.r-".'-- •'••
Depth On.)
0.43
M 0,22
0.65
  Once the information on an average duration and depth storm event is obtained for a specific
  location, multiply these numbers by 0.5 to get the 50 percent average event numbers and
  multiply by 1.5 to get the 150 percent average event numbers.
                                 A representative storm in both duration and depth for a
                                 specific area will fall between the shaded numbers above
                                 (i.e., between 2.6 and 7.8 hours in duration and 0.22
                                 and O.fiS inches in depth).
Snowmelt creates runoff which may result in point source discharges very similar to that from other

storm events.   Pollutants accumulate in snow, and when a thaw occurs, the pollutants will be

discharged to receiving waters much like during a rain storm event.  Snowmelt may be sampled as

long as the applicant works closely with the permitting authority to determine the proper sampling

strategy,  i.e., sampling procedures, techniques, and pollutant analyses.


For snowmelt, the sampling strategy should be developed depending on the drainage area being

monitored for storm flow.  The strategy should consider (1) snow removal or clearing practices,

e.g., direct dumping into water bodies, plowing, and the creation of snow mounds (whether in a line

along a roadway or  in piles on parking lots, etc.), and (2) the melting process.


It is also important to consider what happens to snowmounds as they melt and evaporate, which can

alter the pollutant concentration in the resulting runoff.  In addition, pollutants from the surrounding
                                           22

-------
                                     CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
air and pavement can build up on snow mound surfaces in a crust or cake-like manner eventually
leaving a residue (including previously dissolved solids that become a remaining solids residue)
which is later left to be washed off by rainfall, manual flushing or other mechanisms.

The sampling of snow mounds, undisturbed snow itself, and hard pack requires a carefully thought
out strategy.  Given the  complexities associated with snowmelt sampling, applicants should have
proposed sampling  strategies reviewed  by the permitting authority  before attempting to  conduct
sampling.

2.7.4 LOGISTICAL PROBLEMS WITH WHEN TO SAMPLE
Applicants may encounter weather conditions that may not meet minimum "representative" storm
criteria; these conditions may prevent adequate collection of storm water samples prior to application
submission deadlines.  For instance, sampling may be problematic in parts of the country that
experience drought  or near-drought conditions or areas that are under adverse weather conditions
such as freezing and flooding. Events with false starts and events with stop/start rains can also cause
problems.  Solutions for sampling under these circumstances are discussed below.

Where the timing of storm event sampling poses a problem, it may be appropriate for the applicant
to petition the permitting authority for a sampling protocol/procedure modification either prior to
sampling or after sampling  is conducted (if the storm event is not acceptable).  When the applicant
requests  a sampling protocol/procedure modification, a narrative justification should be attached.
This justification should be  certified by a corporate official (for industrial facilities) or the principle
executive officer or ranking official  (for municipalities),  as per 40  CFR  122.22.  Section 5.1  of
Chapter 5 discusses protocol/procedure modifications.

Arid Areas
For arid or drought-stricken areas where a storm event does not occur prior to the time the applicant
must sample and submit data with the application form, the applicant  should submit the application,
complete to the extent possible, with a detailed explanation of why sampling data are not provided
and an appraisal of when sampling will be conducted.  This explanation must be certified by the
appropriate party (as described above).  The applicant should also contact the permitting authority
                                            23

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
for further direction.  Where the applicant can anticipate such problems, approval for an extension
to submit sampling data should be acquired prior to the deadline.

Adverse Weather Conditions
The applicant should never conduct storm water sampling during unsafe conditions. It is likely that,
in areas that experience flooding, lightening storms, high winds, etc., another representative storm
event will occur for which sampling conditions will be much safer.  (For further information on
safety issues,  see Chapter 6.)  If no other  storm event occurs,  the  applicant should submit a
justification as to  why the event was not sampled.  This information  should be certified by the
appropriate official.

False Starts and Stop/Start Rains
False start and stop/start rains can also cause problems.   False starts may occur when weather
conditions are unpredictable and it appears that a storm event may be representative,  collection
begins, and then the rain stops before an adequate sample volume is obtained.  (Necessary sample
volumes are discussed  in Section 3.6.)  Some latitude may be given for the 0.1-inch  rainfall
requirement as long as the sample volume is adequate; the permitting authority may accept the results
with applicant justification and certification.  Again,  see Chapter 5 for information on requesting
protocol/procedure modifications to storm water sampling requirements.

During stop/start rains (those  in which rainfall is  intermittent), samples should be taken until an
adequate sample volume is obtained.  Exhibit 2-10 summarizes logistical problems of storm water
sampling and presents solutions to the problems identified.

2.7.5 WHEN INDUSTRIAL FACILITIES MUST SAMPLE
Industrial applicants must generally collect two types of storm water samples:  (1) grab samples
collected during the first 30 minutes of discharge; and (2) flow-weighted composite samples collected
during the first 3 hours of discharge (or the entire discharge, if it is less than 3 hours).  Information
from  both types of samples is critical to fully evaluate the types and concentrations of pollutants
present in the  storm water discharge.
                                             24

-------
                                    CHATTER 2 - BACKGROUND FOR STORM WATER SAMPLING
        EXHIBIT 2-10.   LOGISTICAL PROBLEMS OF STORM WATER SAMPLING
  Problem:      Arid/drought areas
  Solution:      Submit a petition requesting a modification to the protocol if problems are
                 anticipated and, if it is approved, submit the application without sampling
                 data by the application due date with a certified explanation.  Provide
                 sampling data to the permitting authority as soon as possible.
  Problem:      Adverse weather conditions such as freezing, flooding, winds, tornadoes,
                 electrical storms, and gully washes
  Solution:      Sample another, less hazardous event or submit a certified justification of
                 why the event was not sampled.  Provide sampling data to the permitting
                 authority as soon as possible.
  Problem:      False starts

  Solution:      Discard the  sample if the volume is inadequate.  If the volume is adequate,
                 submit the sampling data with a certified explanation that the sample is from
                 a non-representative event.  Continue to monitor weather conditions and
                 attempt to resample as soon as possible.
  Problem: :     Stop/start rains

  Solution:      Continue to sample in case the storm event turns out to be representative and
                 adequate sample volumes are obtained.  If sample volumes are inadequate,
                 continue to monitor weather conditions and attempt to resample as soon as
                 possible.
The grab samples taken during the first 30 minutes of a storm event will generally contain higher

concentrations of pollutants, since they pick up pollutants that have accumulated on drainage surfaces

since the last storm event.


Composite samples characterize the average quality of the entire storm water discharge.  Flow-
weighted composite samples provide for the most accurate determination of mass load.  The flow-

weighted composite sample must be taken for either the first 3 hours or for the entire discharge (if
the event is less than 3 hours long). Additional information on how to collect grab and composite
samples is presented in Sections 3.3 and 3.4, respectively.


Industrial applicants are required  at a minimum  to sample only one  storm  event.  However, if
samples from more than one storm are analyzed and the results are representative of the discharge,
the data representing each event must be reported.  The facility must provide  a description of each
storm event tested.  The average of all values within the last year must be determined and  the
                                            25

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
concentration, mass, and total number of storm events sampled must be reported on Form 2F.
Furthermore, sampling should be conducted during normal operating procedures (day or night), and,
not when the facility has been closed for a period of time.

Industrial  applicants must certify, as a separate requirement, that all outfalls have been  tested  or
evaluated to determine whether non-storm water discharges are present (e.g., process wastewater,
sanitary wastes, cooling water, or rinse water) or whether illegal/illicit connections are occurring in
the system.  This testing should be conducted during dry weather to avoid any flows of storm water
through the conveyance.

A checklist that can be used to conduct dry weather evaluations is provided in Exhibit 2-11.  A
narrative description of the method  used to conduct dry weather evaluations and the date and the
drainage points must be included in  Section V.A of Form 2F.  This statement must be certified by
the appropriate party as described in Section 2.7.4.

A dry weather visual inspection is the simplest way to screen for illicit discharges.  If one or more
of the items on the checklist in Exhibit 2-11 are answered affirmatively, or if there are other reasons
to believe that illicit connections exist, more detailed investigations (such as dye tests, smoke tests,
evaluation of piping designs, and TV line  monitoring) may be necessary.  Dye testing involves
releasing fluorescent, nontoxic dye into the suspected source of non-storm water, (e.g., a drain, sink,
toilet, or pipe) and  checking to see  whether the dye shows up in the storm water outfall. Smoke
testing involves pumping  smoke into a storm sewer  and viewing the facility to see if smoke escapes
through unknown openings or storm sewer inlets.  The presence of smoke indicates that storm water
may enter the sewer through these openings or inlets. However, smoke testing may prove ineffective
at finding non-storm water discharges to separate storm sewers. Smoke passage may be blocked due
to line traps that are intended to block sewer gas.

TV line monitoring is a technique whereby  a small video camera is placed in the storm sewer and
a video image of the sewer is viewed on a monitor at the surface to identify illicit connections.  The
camera can be moved through the sewer by remote control.  For more information on smoke and
dye testing and TV line monitoring,  consult  EPA's Guidance Manual for the Preparation of NPDES
                                            26

-------
                                      CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
 EXHIBIT 2-11.   CHECKLIST FOR CONDUCTING DRY WEATHER EVALUATIONS
 1.   Date of inspection:	
 3.   Date of last rain event:	
 4.   Inspector name:	
 5.   Type of outfall
     D  Concrete      D  Pipe
              2.   Facility name and address:
D  Grassed
Rock      D  Other
6.   Is there visible flow from the pipe?  D Yes    D No
     If yes, check all that apply.  If no, go to number 7.
     D  Colored water (describe)	
     D  Odor* (describe)	
     D  Murky
     D  Floating objects (describe)	
     D  Absence of plant life surrounding
        conveyance
     D  Scum
               U Oily
               D Sludge present
               D Clear water
               D Stains on conveyance
               D Notable difference in plant life surrounding
                  conveyance
               D Suds     D  Other	
     "e.g., rotten eggs, earthy, chemical, chlorine, soap, putrescence, gasoline, musty, etc.
     Estimate the flow either visually or by describing the width, height, and shape of the conveyance and
     the approximate percentage  of the conveyance where flow is present or the approximate depth of the
     flow.  Describe your estimate.
7.   Is there standing water present? D  Yes    D  No
     If yes, check all that apply. If no, go to number 8.
     D  Colored water (describe)_
     D  Odor* (describe)	
     D  Murky
     D  Floating objects (describe).
               D Oily sheen
               D Sludge present
               D Clear water
               D Stains on conveyance
               D Notable difference in plant life surrounding
                  conveyance
               D Scum   D  Other:	
     D  Absence of plant life surrounding
        conveyance
     D  Suds
     D  Absence of plant life surrounding conveyance
     *e.g., rotten eggs, earthy, chemical, chlorine, soap, putrescence, gasoline, musty, etc.
8.   From the inspection locations, can you see any unusual piping or ditches that drain to the storm
     water conveyance?  D Yes    D  No
9.  Is there any overland flow visible from the discharge location?
10. Are there dead animals present? D  Yes    D  No	
Signature:
                               Yes    D No
                                              27

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
Permit Applications for Storm Water Discharges Associated with Industrial Activity (EPA-505/8-91-
002, April 1991).

A problem with the dry weather evaluation process is that the presence of a dry weather/non-storm
water discharge may be caused by infiltration of ground or surface waters through cracks in the
storm water drainage system.  In this situation, all other possible sources of the non-storm water
discharge should be examined and ruled out.  If no sources are found, the physical structure of the
conveyance system should be inspected for deterioration.

The applicant should make every attempt to halt non-storm water discharges to the storm sewer
system unless the discharge is covered by an NPDES  permit.   If it is  not feasible  to halt the
discharge of non-storm water to the storm sewer system, and the discharge is not authorized  by a
process wastewater or storm water permit, the applicant must submit either Form 2C (for a process
water discharge) or Form 2E (for a nonprocess water discharge), and check with state officials to
see if alternate forms are required.

2.7.6  WHEN MUNICIPAL FACILITIES MUST SAMPLE
Municipal applicants are required to conduct sampling  for both Parts 1 and 2 of their applications.
In Part 1, municipalities must conduct a field screening analysis  to detect illicit connections and
illegal  dumping into their storm sewer system.  Where flow is observed during  dry weather, two
grab samples  must be collected during a 24-hour period with a minimum of 4 hours between
samples.   These samples must be analyzed for pH, total chlorine, total copper, total phenol, and
detergents (surfactants). Note that these are dry weather samples, rather than storm water samples.
EPA's Guidance  Manual  for the Preparation of Part 1 of the NPDES Permit Applications for
Discharges from Municipal Separate Storm Sewer Systems presents a description of conducting field
screening sampling and provides a data sheet.

For Part 2 of the application, municipalities  must submit grab  (for certain pollutants) and flow-
weighted sampling data from selected sites (5 to 10 outfalls) for 3 representative storm events at least
1 month apart. The flow-weighted composite sample must be taken for either the entire discharge
or the first 3 hours (if the event lasts longer than 3 hours).  Municipal facilities are not required to
collect grab samples within the first 30 minutes of a storm event.

                                            28

-------
                                     CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
 In  addition to submitting quantitative data for  the application,  municipalities must also develop
 programs for future sampling activities that specify sampling locations, frequency, pollutants to be
 analyzed, and sampling equipment.  Where necessary (as  determined  by the municipality or if
 required by the  permitting authority),  responsibilities  may also  include monitoring  industries
 connected  to the municipality's  storm sewers for compliance with their facility-specific NPDES
 permits.  Refer  to EPA's Guidance Manual for the Preparation of Part 1 of the NPDES Permit
 Applications for Discharges from Municipal Separate Storm Sewer Systems for information on how
 to develop municipal sampling programs.

 2.7.7 USE OF HISTORICAL DATA
 Data from storm water samples analyzed in the past can be submitted with applications in lieu of new
 sampling data if:

     • All  data requirements in Form 2F are met
     • Sampling was performed no longer than 3 years prior to submission of the permit application
     • All  water quality data are representative of the present discharge.

 The historical data may be unacceptable if there have been significant changes since the time of that
 storm event in production level,  raw materials,  processes, or final products.  Significant changes
 which may also impact storm water runoff include construction or  installation of treatment or
 sedimentation/erosion control devices, buildings, roadways, or parking lots. Applicants should assess
 any such changes to determine whether they altered storm water runoff since the time of the storm
 event chosen for use in the permit application.  Historical data can be used only in  applications.
 Historical data cannot be used for fulfilling permit requirements.

2.8  WHERE TO SAMPLE STORM WATER DISCHARGES
Storm water samples should be taken at a storm water point source. A "point source" is defined as
any discernible, confined,  and discrete conveyance, including (but not limited to) any pipe,  ditch,
channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding
operation, landfill leachate collection system, vessel, or other floating craft from which pollutants
are  or may be discharged (as per 40 CFR 122.2). Included in the definition of storm water "point

                                           29

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
sources" is storm water from an industrial facility that enters, and is discharged through, a municipal
separate storm sewer.   In short, most storm water discharges can be defined as "point source"
discharges, since they ultimately flow into some kind of conveyance (e.g., a channel or swale).

2.8.1  INDUSTRIAL FACILITIES
Industrial  applicants submitting individual applications must collect and analyze a grab sample taken
within the first 30 minutes of the storm event and flow-weighted  composite samples from each of
the industrial storm water "point source" outfalls identified on the site drainage map submitted for
Section III of Form 2F.  Applicants submitting quantitative data for Part 2 of the group application
must also  collect samples for each outfall discharging storm water associated with industrial activity.
All outfalls should be sampled during the same representative storm event if possible.  If this is not
feasible, outfalls may be sampled during different representative storm events upon approval by the
permitting authority. Descriptions of each storm event and which outfalls were sampled during each
event must be included in the application.   Storm water runoff from  employee  parking lots,
administration buildings, and landscaped areas that is not mixed with storm water associated with
industrial  activity, or storm  water discharges  to municipal sanitary sewers, do not need to be
sampled.

Outfalls With Substantially Identical Effluents—Industrial Facilities
If an  applicant has two or more outfalls with  "substantially identical effluents," the facility  may
petition the permitting authority to sample and analyze only one of the identical outfalls and submit
the results as representative of the other.  "Substantially identical effluents" are defined as discharges
from drainage areas undergoing similar activities where the discharges are expected to be of similar
quantity and quality, and indistinguishable in expected composition. Chapter 5  presents an example
of a petition for substantially  identical effluents and discusses this process in more detail.

2.8.2  MUMCIPALTTIES
Large and medium municipalities are required to sample storm water discharges  from 5 to 10 outfalls
or field screening points that  were proposed in Part 1 of the application.  The  final decision on the
number and location of sampling  points will be determined by the  permitting authority and will
                                             30

-------
                                     CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
depend on site-specific conditions  such as land use or drainage area and results of data collected
during the field screening analysis  process for Part 1 of the application.

2.8.3  LOGISTICS OF WHERE TO SAMPLE
The ideal sampling location would be the lowest point in the drainage area where a conveyance
discharges storm water to waters of the U.S. or to a  municipal separate  storm sewer system.  A
sample point also should be easily accessible on foot in a location that will not cause  hazardous
sampling conditions. Ideally, the sampling site should be on the applicant's property or within the
municipality's easement;  if not, the field personnel should obtain permission from the owner of the
property where the discharge  outfall is located.   Typical  sampling locations  may include the
discharge at the end of a pipe, a ditch, or a channel.

However,  logistical problems  with  sample  locations  may  arise  (e.g., nonpoint discharges,
inaccessibility of discharge point, etc.).  Logistical problems with sample locations and suggested
solutions are described in Exhibit 2-12.  In many cases, it may be necessary to locate a sampling
point further upstream of the discharge point (e.g., in  a manhole or inlet). If the storm water at a
selected location is not representative of a facility's total runoff, the facility may have to sample at
several locations to best  characterize the total runoff from the  site.  In situations where discharge
points are difficult to sample for various  reasons, the applicant should take the best sample possible
and explain the conditions in the application. A discussion on sampling at retention ponds appears
in Section 3.1.2.

2.9  STAFFING CONSIDERATIONS
Staffing  needs for sampling  must be  determined by  the  applicant.   Factors in  making the
determination include the number of sample locations, the size of the area to be sampled, how far
apart the locations  are, the type of sampling required, the technique to  be used, the number of
samples  to  be taken  (depending  on how many  parameters must be analyzed), and safety
considerations.

Training  sampling personnel is important to the success of storm water discharge characterization.
Training can be done using this manual.  Sampling conducted by untrained personnel may result in
                                            31

-------
CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
           EXHIBIT 2-12.   SOLUTIONS TO SAMPLE LOCATION PROBLEMS
  Problem:     Sampling where storm water commingles with process or non-process water

  Solution:     Attempt to sample the storm water discharge before it mixes with the non-storm
               water discharge.  If this is impossible, sample the discharge both during dry
               and wet weather and present both sets of data to the permitting authority.  This
               will provide an indication of the contribution of pollutants from each source.
  Problem:    Numerous small point discharges
  Solution:     Impound channel or join together flow by building a weir or digging a ditch to
               collect discharge at a low point for sampling purposes.  This artificial collection
               point should be lined with plastic to prevent infiltration and/or high levels of
               sediment. Or, sample at several locations to represent total  site runoff.
  Problem;    Inaccessible discharge point [examples include underwater discharges or
     :    h    unreachable discharges (e,g,,; out of ai cliff}]
  Solution:    Coup the pipe to sample (i.e., to the nearest manhole or inspection point).  If
               these are not available, tap into the pipe or sample at several locations to best
               represent total site runoff.
  Problem:    Managing multiple sampling sites to collect grab samples during the first 30
         ;      minutes industrial facilities only)            ;
  Solution:    Have a sampling crew ready for mobilization when forecasts indicate that a
               representative storm will occur or sample several different representative
               events.  Also, for most parameters, automatic samplers may be used to collect
               samples within the first 30 minutes triggered by the amount of rainfall, the
               depth of flow, flow volume or time.
  Problem;:  :  Commingling of parking tot runoff with discharge associated with industrial
   =.-'    ;.":•  • 'activity    :      -.   '     ' \  •'•'-..'  J" ••'.'            '-.      ; .  .
  Solution:     The combined runoff must be sampled at the discharge point as near as possible
               to the receiving water or the parking lot drain inlet if there is one.
  Problem:    Sampling in manholes       ;

  Solution:    Sample in manholes only when necessary.  See Chapter 6 for safety
               information.  Sampling in manholes requires training on confined space entry.
  Problem:     Runon from other property                  ;                :

  Solution:     If possible, estimate the volume of offsite runon contributions and offsite runon
               sources of pollutants to perform a mass balance calculation.  Include this
               information in the permit application.  If this estimation is not possible, provide
               a narrative  discussion of the upstream site (e.g., is it developed, if so the type
               of facility,  the types of pollutants that may be present on the site, etc.).
                                            32

-------
                                    CHAPTER 2 - BACKGROUND FOR STORM WATER SAMPLING
data that is unrepresentative of the facility's storm water discharge.  This data might be rejected by
the permitting authority, who would then require another sampling effort.
                                          33

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.  FUNDAMENTALS OF SAMPLING
Because of the variable nature of storm water flows during a rainfall event and different analytical
considerations for certain pollutants, the storm water regulations establish specific requirements for
sample collection techniques.   The  quality  of storm water discharges and logistical  needs  for
sampling will be different for industrial applicants and municipal applicants.  Therefore, specific
sampling requirements vary.  After a brief review of sampling fundamentals and special sampling
requirements for storm water permit applications, the following  sections are intended to teach
applicants how to sample to meet these requirements.

The applicant should carefully plan his/her sampling strategy prior to the actual sampling event, e.g.,
walk the site to  determine appropriate sampling locations, become familiarized with local rainfall
patterns, train sampling staff in procedures and safety, consult with laboratory, and collect supplies.

3.1  TYPES AND TECHNIQUES OF SAMPLING
There are three basic aspects of sampling:

    • Sample type  (i.e., grab versus composite)
    • Sample technique (i.e., manual versus automatic)
    • Flow measurement methods.

These topics will be  discussed in relation to requirements of an NPDES storm water discharge permit
application.  Once these aspects are addressed, step-by-step instructions on sampling procedures are
presented.  The sections below define and  describe the types of storm water samples that must be
collected and methods or techniques for collecting them.  In addition, special sampling requirements
for certain pollutants are discussed.
                                            35

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.1.1 SAMPLE TYPE VERSUS SAMPLE TECHNIQUE
It is important to understand the difference between sample type and technique. "Sample type" refers
to the kind of sample that must be collected - either a grab or a composite.  "Sample technique"
refers to the method by which a grab or composite sample is actually collected - either manually or
by automatic sampler. A generalized relationship between sample type and  sample technique  is
presented in Exhibit 3-1.   Sections 3.1.2 and 3.1.3 further explain the significance of these terms
as they relate to storm water sampling requirements.
               EXHIBIT 3-1.   SAMPLE TYPE vs. SAMPLE TECHNIQUE
                Sample Type
            Sample Technique
  Grab
Manual
Automatic sampling system
  Composite
Manual with manual compositing
Automatic system or automatic sampling with
manual compositing
3.1.2 SAMPLE TYPE: GRAB AND COMPOSITE SAMPLES
To comply with storm water application requirements, the sample type (grab or composite) must be
collected in  accordance with 40 CFR 122.21(g)(7) and 40  CFR Part  136.   The storm water
application requirements clearly specify which pollutants must be analyzed by grab sample, and
which by composite sample.  Although the requirements in 40 CFR 122.21 (g)(7) do not explicitly
specify either manual or automatic sampling techniques, the approved analytical methods contained
in 40 CFR Part  136 direct that grab samples must be collected manually for certain pollutants.
Sections 3.3 and 3.4 clarify which pollutants must be  grabbed, which ones must be grabbed
manually, and which ones must be flow-weighted composites.
The two types of storm water samples required by the regulations, grab and composite samples, are
described below.

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Grab Samples

A grab sample is a discrete, individual sample taken within a short period of time (usually less than
15 minutes).  Analysis of grab samples characterizes the quality of a storm water discharge at a given

time of the discharge.


Composite Samples

A composite  sample is  a mixed or  combined sample that is  formed  by combining  a  series of
individual and discrete samples of specific volumes at specified  intervals.  Although these intervals

can be time-weighted or flow-weighted, the storm water regulations require the collection of flow-

weighted composite samples.  This means that  discrete  aliquots, or samples, are collected  and
combined in proportion to flow rather than time.   Composite samples characterize the quality of a
storm water discharge over a longer period of time, such as the duration of a storm event.


Application Requirements

Both types of samples must be collected and analyzed for storm water discharge permit applications.

Grab samples must be collected for the following conditions:
    •  For storm water discharges associated with industrial activity, a grab sample must be obtained
       during the first 30 minutes of a discharge. This requirement is in addition to the composite
       sampling requirements.   These samples  are  intended  to characterize  the maximum
       concentration of a pollutant that may occur in the discharge and/or may indicate intermingling
       of non-storm water discharges.

    •  For storm water  discharges from large and  medium municipal separate storm sewers, grab
       samples are required for Part 1 of the application if a discharge is noted during  dry weather
       field screening.  Two grab samples must be  collected during a 24-hour period with a
       minimum of 4 hours  between samples.   These  samples are intended to assist  in  the
       identification of  illicit connections or illegal  dumping.  In Part 2, grab samples may be
       required for the analysis of certain pollutants for which municipalities are required to sample.
Flow-weighted composite samples must be collected during the first 3 hours of discharge or the
entire discharge (if it is less than 3 hours) for both industrial and municipal applicants.
                                            37

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Pollutant-specific Requirements
The  regulations  at 40 CFR 122.21(g)(7)  identify  certain pollutants for which grab sampling is
required:
      Monitoring by grab sample must be conducted for pH, temperature, cyanide, total phenols,
      residual chlorine, oil and grease (O&G), fecal coliform, and fecal streptococcus.  Composite
      samples are  not appropriate for these parameters due to their tendency to transform to
      different  substances  or change in  concentration  after  a short period  of time.    Such
      transformations  may be particularly likely in the presence of other reactive pollutants.
Sampling At Retention Ponds
Retention ponds with greater than a 24-hour holding time for a representative storm event may be
sampled by grab  sample.  Composite sampling  is not necessary.  The rationale for this  is that,
because the water  is held for at least 24  hours, a thorough mixing occurs within  the pond.
Therefore, a  single grab sample of the  effluent  from the discharge point of the pond accurately
represents a composite of the storm water contained in the pond. If the pond does not thoroughly
mix the discharge, thereby compositing the sample, then a regular grab and composite sample should
be taken at the inflow to the pond.  Since each pond may vary in  its capability to "composite" a
sample, applicants must carefully evaluate whether the pond is thoroughly mixing the  discharge.
Such factors as pond design and maintenance are important in making this evaluation.   Poor pond
design, for example, where the outfall and inflow points are too closely situated, may cause short-
circuiting and inadequate mixing. In addition, poor maintenance may lead to excessive re-suspension
of any deposited  silt and sediment during heavy inflows.  Because of factors such as these, the
applicant should determine  the best location  to sample the pond (e.g., at the outfall, at the outfall
structure,  in  the  pond) to  ensure  that a representative  composite  sample is taken.  If adequate
compositing is not occurring within the pond, the applicant should  conduct routine grab and  flow-
weighted composite sampling.

A grab sample and a flow-weighted sample must be taken for storm water discharges collected  in
holding ponds with less than a 24-hour retention  period.  The applicant must sample the discharge
in the same manner as for  any storm water discharge [as described in 40  CFR 122.21(g)(7)].   In
                                            38

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
effect, the applicant must take one grab sample within the first 30 minutes of discharge, or as soon
as possible.  The applicant must also collect a flow-weighted composite sample for at least the first
3 hours of the discharge, or for the event's entire duration (if it is less than 3 hours). The flow-
weighted composite sample may be taken using a continuous sampler or as a combination of at least
three sample aliquots taken  during each hour of the discharge, with a minimum of IS minutes
between each aliquot.  If the applicant does not know what retention period the pond is designed for,
the design engineer of the pond should be consulted.

3.1.3  SAMPLE TECHNIQUE: MANUAL VERSUS AUTOMATIC SAMPLING
As previously discussed, manual and automatic sampling techniques are methods by which both grab
and composite samples can be collected.  Manual samples are simply samples collected by  hand.
Automatic samplers are powered devices that collect samples according to preprogrammed criteria.
A typical  automatic sampler  configuration is shown in Exhibit 3-2.

For most  pollutants, either manual or automatic sample collection will conform with 40 CFR Part
136. However, one case in which automatic samplers cannot be used is for the collection of volatile
organic compound (VOC) samples because VOCs will likely volatilize as a result of agitation during
automatic sampler collection. Samples  collected for VOC  analysis  should be filled until a reverse
meniscus is found over the top of the collection bottle and capped immediately to leave no air space.
Automatic samplers do not perform mis function.  Special  requirements  for VOC  sampling are
discussed  in Section 3.5.2.

Although both collection techniques are available, several other pollutants may not be amenable to
collection  by an automatic sampler, for example fecal streptococcus, fecal coliform and chlorine have
very short holding times (i.e., 6 hours), pH and temperature need to be analyzed immediately and
oil and grease requires teflon coated equipment to prevent adherence to the sampling equipment.

Other restrictions on sample  collection techniques (such as container type and preservation) should
be determined by consulting the approved analytical methods listed in 40 CFR Part 136. Section 3.5
and Technical Appendix C provide additional information on sample handling, holding times, and
preservation methods.
                                           39

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
                   EXHIBIT 3-2.   AUTOMATIC SAMPLER
                         Programming Unit
                                                      Pump
                 Flow Sensor    * Sample Intake
                                                      Distributor
                                                      Sample Aliquot
                                                      Containers
                                 40

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Manual and  automatic techniques have advantages and  disadvantages that  the applicant  should
consider in relation to the sampling program. The main advantage of manual sampling is that it can
be less costly than purchasing or renting automatic samplers. Automatic samplers, however, can be
often more convenient.  Exhibit 3-3 presents a matrix of advantages and disadvantages associated
with each technique.  Ultimately, the best technique to use will depend on each applicant's situation.

3.2  OBTAINING FLOW DATA
In  addition  to  collecting  samples  of storm  water discharges,  applicants must collect  data
characterizing the flow rate and flow volume for each storm water discharge sampled. Flow rate
is the quantity of storm water discharged from an outfall per unit of time.  Total flow is a measure
of the total volume of storm water runoff discharged during a rain event. Flow rates and volumes
can either be measured specifically or can be estimated (based on rainfall measurements, velocities,
and depth of flows).  To collect flow-weighted  composite samples,  flow rate data is necessary to
combine proportional volumes of individually collected aliquots. Applicants  must also report the
mass of pollutants contained in storm water discharges (see Section 3.2.5).  To determine mass
loadings of pollutants, applicants must measure both discharge flow rate  and pollutant concentration.
This section presents methods for obtaining flow data.

3.2.1  MEASURING FLOW RATES
Flow rates for storm water  discharges are most accurately  measured using either primary or
secondary flow measurement devices.   Facilities should use these  devices  to characterize their
discharge  as  precisely as possible. Where flow measurement devices are not already installed,
portable devices  should be considered.  There  are many permanent and portable  types of flow
measurement devices available.  This discussion is limited to the most common flow measurement
devices. To purchase flow measurement devices  and rain gauges, pertinent engineering journals can
be consulted  for equipment vendor listings.  Proper analysis of site  discharge conditions must be
conducted prior to purchase and installment of flow measurement devices.

Primary Flow Measurement Devices
A primary flow measurement device is a man-made flow control structure which, when inserted into
an open channel, creates a geometric relationship between  the depth of the flow and .the rate of the
                                            41

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
       EXHIBIT 3-3.
    Sample
    Method
    COMPARISON OF MANUAL AND AUTOMATIC SAMPLING
    TECHNIQUES
        Advantages
      Disadvantages
  Manual
  Grabs
• Appropriate for all pollutants
• Minimum equipment required
Labor-intensive
Environment possibly dangerous
to field personnel
May be difficult to get personnel
and equipment to the storm water
outfall within the 30 minute
requirement
Possible human error
  Manual
  Flow-
  Weighted
  Composites
  (multiple
  grabs)
  Appropriate for all pollutants
  Minimum equipment required
Labor-intensive
Environment possibly dangerous
to field personnel
Human error may have significant
impact on sample
representativeness
Requires flow measurements taken
during sampling	
  Automatic
  Grabs
  Minimizes labor requirements
  Low risk of human error
  Reduced personnel exposure to
  unsafe conditions
  Sampling may be triggered
  remotely or initiated according
  to present conditions
Samples collected for O&G may
not be representative
Automatic samplers cannot
properly collect samples for VOCs
analysis
Costly if numerous sampling sites
require the purchase of equipment
Requires equipment installation
ana maintenance
Requires operator training
May not be appropriate for pH
and temperature
May not be appropriate for
parameters with short holding
times (e.g., fecal streptococcus,
fecal cohform, chlorine)
Cross-contamination of aliquot if
tubing/bottles not washed	
  Automatic
  Flow-
  Weighted
  Composites
   Minimizes labor requirements
   Low risk of human error
   Reduced personnel exposure to
   unsafe conditions
   May eliminate the need for
   manual compositing of aliquots
   Sampling may be triggered
   remotely or initiated according
   to on-site conditions
Not acceptable for VOCs sampling
Costly if numerous sampling sites
require the purchase of equipment
Requires equipment installation
and maintenance, may malfunction
Requires initial operator training
Requires accurate flow
measurement equipment tied to
sampler
Cross-contamination of aliquot if
tubing/bottles not washed	
                                            42

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
flow.  The depth of the flow, referred to as the head (H), can then be measured at the respective
reference point/area with a ruler or other staff gauge.  When substituted into a formula, which
mathematically describes the relationship between depth and discharge for the primary devices, the
head measurement  can be used  to  calculate a flow rate  (Q).  The most common primary flow
measurement devices  are weirs  and flumes.  Weirs and flumes are flow structures designed to
provide a known, repeatable relationship between flow and depth.

Weirs
Weirs  consist of a crest located across the width of an open channel (at a right angle to the direction
of the  flow).  The flow of water is impeded,  causing water to overflow the crest.   Diagrams and
formulas of some typically found weirs are provided in Exhibit 3-4.  Weirs are inexpensive and
particularly  valuable in measuring flow in natural or man-made  swales because they are easily
installed in irregularly shaped channels.

Weirs  can only provide accurate flow measurements when head measurements are appropriately
taken.  When  flow  exceeds the capacity of the weir and water overtops the weir crest, flow depth
actually diminishes as the water approaches the weir, as shown in Exhibit 3-5.  Therefore, measuring
the depth at the weir crest will result in an inaccurate measurement of the actual head. Under these
circumstances, the head should be measured upstream, at a point determined by the type of weir and
the estimated amount of flow. A staff gauge can be installed at a nonturbulent point upstream of the
weir crest to provide accurate and convenient measurements.

Flumes
Flumes are structures which force water through a narrow channel.  They consist of a converging
section, a throat, and a diverging section.  Exhibit 3-6 portrays the most common type of flume, the
Par shall flume, and also provides formulas for calculating appropriate flow rates.
Parshall flumes have fixed specifications relating  to geometric shape. They vary  only in throat
width.  Due to these geometric constraints, Parshall flumes may be expensive to install.  They are
typically used  in permanent flow measurement points and are  most commonly placed in concrete-
lined channels. However, Parshall flumes can also be used in temporary points.  Parshall flumes
provide accurate measurements for a relatively wide range of flow rates. The flow rate through the
Parshall flume (see Exhibit 3*6) is calculated from the depth (HJ of flow measured in the converging
                                            43

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
                                 EXHIBIT 3-4.   WEIRS
  V-Notch
  Rectangular (without contractions)
  Rectangular (with contractions)
  Cipolleti (trapezoidal)
     Q  = 2.5 H "  (90°)
   Q =  1.443 H "  (60°)
   Q =  1.035 H «  (45°)
   Q =  0.676 H "  (30°)
  Q = 0.497 H " (22V4°)

          Q = Flow Rate

H = Depth of flow (Head)


         Q = 3.33 L H 1J
   Q = 3.33 (L - 0.2 H)1-5
        Q = 3.367 b H lvi
   Source:  Civil Engineering Reference Manual. 5th Edition, by Michael R. Lindeburg, PE,
             with permission from the publisher, Professional Publications, Inc.,
                                Belmont, California, 1989.
                                           44

-------
                                                 CHAPTER 3 - FUNDAMENTALS OF SAMPLING
              EXHIBIT 3-5.    SUPPRESSED FLOW OVER THE WEIR CREST
                                 (H) Real Head
                                                         Nappe
    Source:  Civil Engineering Reference Manual. 5th Edition, by Michael R. Lindeburg, PE,
              with permission from the publisher, Professional Publications, Inc.,
                                Belmont, California, 1989.
section of the flume. The exact location of the depth measurement depends on the specific design
of the Parshall flume.  Exhibit 3-6 indicates the equations used to calculate flow rate through a
typical Parshall flume.  These equations are accurate only when the submergence ratio (Hb/HJ is
greater than 0.7. The manufacturers' information should be consulted for the flow rate equation and
measuring points for a specific Parshall flume.

Palmer-Bowlus flumes, shown in Exhibit 3-7, are also used at some facilities.  Palmer-Bowlus flumes
are designed to be installed in an existing circular channel (such  as a manhole  channel) and are
available as portable measurement devices.  While Palmer-Bowlus flumes are  inexpensive,  self
cleaning, and easy to install, they can only measure flow rates accurately over a narrow range of
flow.

The flow from a Palmer-Bowlus flume is calculated using the height between the floor of the flume
portion and the water level, not the total head of the water level. Head measurements are taken at
                                           45

-------
CHATTER 3 - FUNDAMENTALS OF SAMPLING
  Parshall Flume
                                EXHIBIT 3-6.    FLUMES
                    Q = 0.338 H L5S
                    Q = 0.676 H l K
                    Q = 0.992 H l•547
                    Q = 2.09 H l-58
                    Q = 3.07 H l-53
                    Q =4WH1522W026
                    Q = (3.6875 W + 2.5)H »6
                    Q = Flow rate
                    H = Depth of flow (Head)
(1 inch)
(2 inches)
(3 inches)
(6 inches)
(9 inches)
(1-8 feet)
(10-50 feet)
                                          Throat
                         Converging
                         Section
   Diverging
   Section
                                                                               Top View
                                                                               Side View
    Source:  Civil Engineering Reference Manual. 5th Edition, by Michael R. Lindeburg, PE,
              with permission from the publisher, Professional Publications, Inc.,
                                 Belmont, California, 1989.
                                            46

-------
                                                 CHAPTER 3 - FUNDAMENTALS OF SAMPLING
                      EXHIBIT 3-7.   PALMER-BOWLUS FLUME
                                                            Pakiwr-Bowlui
     Source:  Wastewater Engineering: Treatment. Disposal. Reuse. 2nd Edition, Metcalf &
   Eddy, Inc., with permission from the publisher, McGraw-Hill Book Co., New York, 1979.
a distance from the throat equal to one half the width of the flume.  The dimensions of a Palmer-
Bowlus flume have been standardized in a generic sense, but the flume shape may vary.  Therefore,
there are no formulas that can be applied to ajl Palmer-Bowlus flumes.  Device-specific head-flow
relationships for each device should be obtained from the manufacturer.

There are a number of other, less common, flow measurement devices available which will not be
discussed (see Appendix D for additional references).
                                          47

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Secondary Flow Measurement Device?
Secondary flow measurement devices are automated forms of flow rate and volume measurement.
Typically, a secondary device is used in conjunction with a primary device to automatically measure
the flow depth or head.  This value is then processed, using established mathematical relationships
to relate the depth measurement to a corresponding flow rate. The device also may have the capacity
to convert this flow rate to a volume.  Secondary flow measurement devices include floats, ultrasonic
transducers, pressure transducers, and bubblers.  The output of the  secondary device is transmitted
to a display, recorder, and/or totalizer  to provide flow rate  and volume  information.  The user
manuals for these devices should be consulted for proper usage.

Evaluation of Flow Measurement Devices
To ensure accurate results, facilities should evaluate, via visual observation and routine checks, the
design, installation, and operation of flow measurement devices.  When evaluating design, select a
device which:

    •  Is accurate over the entire range of expected flow rates
    •  Can be installed in the channel to be monitored
    •  Is appropriate to the sampling location (i.e., power setup, submersible, etc.).

When evaluating the installation of flow measurement devices, ensure that:

    •  There are no  leaks and/or bypasses of flow around the measuring device
    •  The primary device is level and squarely installed
    •  The secondary device is calibrated.

When evaluating the operation of flow measurement devices, look for:
    •  Excessive flows which submerge the measuring device
    •  Flows outside the accuracy range of the device
    •  Leaks and/or bypasses around the measuring device
                                            48

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    •  Turbulent flow through the measuring device
    •  Corrosion, scaling, or solids accumulation within the measuring device
    •  Obstructions to the measuring device
    •  Use of the correct factor or formula to convert head readings to actual flow rate.

Other than ensuring appropriate design and installation, accuracy checks are difficult to accomplish
for primary flow measurement devices. Secondary flow measurement devices, on the other hand,
may require evaluation of design,  installation,  and  calibration.  Applicants  should  examine the
secondary recording devices and  their readouts after installation to ensure that they are operating
properly.  Unusual fluctuations or breaks in flow indicate operational or design flaws.

3.2.2  ESTIMATING FLOW RATES
There are a variety  of techniques  for estimating flow rates. These methods are not as accurate as
the methods described in Section  3.2.1 above, but are suitable for those discharges where primary
or secondary devices are not practical or economically feasible.  Each of the following methods is
suitable for certain types of flow situations, as indicated.  For each, the procedure for collecting flow
rate data will be given along with a sample calculation.

Float Methods
Float methods can be used for any  discharge where the flow is exposed and/or easily accessible.
It is particularly useful for overland flows, gutter flows, and open drain or channel flows.  The flow
rate is  calculated in each of the float methods by estimating the velocity of the flow and the cross-
sectional area of the discharge and using the standard flow rate equation:


                      Flow Rate (cfin) = Velocity (ft/min) x Area (ft2)
                                            49

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
The velocity is estimated by measuring the time it takes a float to travel between two points (point
A and point B) along the flow path.  For most accurate results, the two points should be at least 5
feet apart.  The cross-sectional area is estimated by measuring the depth of the water and the width
of the flow, and multiplying the depth by the width. This assumes a uniform cross-section in the
flow path and a geometric cross-section shape.  The float method can also be used for any accessible
pipe or ditch  where the movement of the  float can be traced  downstream for at  least 5 feet.
Subsurface storm water flows can be measured with the float method where there are two accessible
manholes.

If the flow is overland, the water will need to be directed into a narrow  channel or ditch so that the
measurements can be taken.  The initial preparation for this method requires that a shallow channel
or ditch be dug that is 6 feet long or longer  and 4 to 12 inches wide. The channel or ditch should
be shallow enough to easily obtain flow depths but should be deep enough to carry the flow that will
be diverted to it. Boards or other barriers should be placed on the ground above the channel (so that
the flow is diverted into  the channel) and along the edges of the channel or ditch (flush with the
ground surface so that flow does not seep under them).

The procedure for measuring the flow rate by the float method involves  measuring the length of the
channel between chosen points A and B (which must be 5 feet apart or more).  The depth of the
water at point B, in the middle of the channel, must be determined, and  the width of the water flow
must be measured at point B.  A float is men placed in the water and timed as it moves from point
A to point B.  Exhibit 3-8 provides an example of estimating the flow rate using the float method.

For runoff flows from many directions into a drain in a low  or flat area where ponding is  evident,
the float method can also be used.  The total flow rate is calculated by measuring flow rates for
several points  into the drain and adding these values together.  Exhibit  3-9 provides an example of
estimating the flow rate using the float method in this situation.

Bucket and Stopwatch Method
The bucket and stopwatch method of estimating flow rate is the easiest of all the flow rate estimation
procedures. However, it can  only be used under certain conditions. The flow or discharge to be
measured must be flowing from a small pipe or ditch, and it must be free-flowing.  In other words,

                                             50

-------
                                                 CHAPTER 3 - FUNDAMENTALS OF SAMPLING
           EXHIBIT 3-8.
                  EXAMPLE CALCULATION OF FLOAT METHOD
                   FOR UNIMPEDED OPEN CHANNEL FLOW
Step 1:
When each sample or aliquot is taken, record the data for the time the sample was taken and the
length between points A and B (at least 5 feet apart).  See columns A, B, and C.

EXAMPLE DATA:
A


Sample
Nraber
1
2
3
4
5
6
7
8
9
B


ruea
\fintes
0
20
40
60
80
100
120
140
160
C
DfetMce
Between
PaiNtS
A&B
(feet)
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
D
Thneof
TrmI
(AtoB)
(BUD)
0.17
0.18
0.20
0.21
0.18
0.17
0.17
0.16
0.18
E
Depth of
Water at
Point B
(feet)
0.12
0.25
0.29
0.33
0.29
0.25
0.12
0.12
0.12
F
Width of
Flow at
Point B
(feet)
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
G


Calculated Flaw Rate
(eta)
1.8
3.5
3.6
3.9
4.0
3.7
1.8
1.9
1.7
Step 2:   Place a float in the water flow at point A and time it as it moves from point A to point B.
         Record the time in minutes.  See column D.
Step 3:   Measure the depth of the water and the width of the flow at point B. See columns E and F.

Step 4:   Calculate the flow rate for each sample time using the common flow rate formula. See column
         G.
Formulas:
                                                from A to B
                                     nn.
                                     (V) =

                          Ana (A) =  Water Depth x Width of Flow

                                Flow Rate (Q) = (V) x (A)
Example:  For Sample 1
                                V =
                                      5.0ft
                                     = 29.4fl/min
                                     0.17 min

                              A = 0.12ft x 0.5.0 = 0.06 ff

                           Q = 29.4ft/min x  0.06ft2 = 1.8 cfin
                                          51

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
        EXHIBIT 3-9.
EXAMPLE CALCULATION OF FLOAT METHOD FOR
 ESTIMATING DRAIN FLOW RATES
 Step 1:    When each sample or aliquot is taken, record the data for the time the sample was taken.
           Measure the outer perimeter or edge of the drain where the water flows in. See columns B
           andC.
 Step 2:    Designate three evenly spaced points surrounding the drain approximately 3 to 5 feet from
           the drain.  These points will be referred to as points A, B, and C.  Record the distance from
           each point to the edge of the drain. See column D.

           EXAMPLE DATA:  Assume the drain dimensions are 1 ft x 1 ft square, and flow surrounds
           drain.
A
Suple
NaBbcr
1
2
3
4
5
6
7
8
9
B
S»»pfr
T\mt
(mU)
0
20
40
60
80
100
120
140
160
C
Dninace
PeriMeter
(f«t)
4
4
4
4
4
4
4
4
4
D
Dbuaee «T Motto
Dniitfeet)
Pt
A
3
3
3
3
3
3
3
3
3
PL
B
4
4
4
4
4
4
4
4
4
Pt
C
5
5
5
5
5
5
5
5
5
E
Tlae of Travel to
Dnii(Bii)
PL
A
0.2
0.3
0.3
0.4
0.3
0.3
0.3
0.3
0.2
PL
B
0.3
0.4
0.4
0.5
0.4
0.4
0.4
0.4
0.3
PL
C
0.5
0.5
0.5
0.6
0.5
0.5
0.5
0.5
0.5
F
Depth of Water (feet)
PL
A
0.08
0.11
0.11
0.16
0.11
0.11
0.11
0.11
0.08
PLB
0.08
0.12
0.12
0.17
0.12
0.12
0.12
0.12
0.08
PL
C
0.08
0.14
0.14
0.20
0.14
0.14
0.14
0.14
0.08
G
r.i~.i.t~i
Flow Rate
(ef»)
4 cfm
5 cfm
5 cfm
6 cfm
5 cfm
5 cfm
5 cfm
5 cfm
4 cfm
 Step 3:    Place a float at each of the three points and measure the time it takes to reach the drain.
           Record the times in minutes. See column E.
 Step 4:    Determine the depth of flow at each place where the float enters the drain from points A, B,
           and C. Record the depth in feet See column F.
 Step 5:    Calculate the flow rate by adding the individual flow rates for points A, B, and C. Record
           the data in column G.
 Formulas:
                          Velocity (V) -
                                       Distance of Point from Drain
                                            Time of Travel

                        Ana (A) = Water Depth x Drainage Perimeter

                  Flow Rate (Q) = l/riLA,V* where n equals points A, B, and C

 Example:  For Sample 1
                                AA = 0.08ft *4ft = 0.32 ft
                                              52

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
   EXHIBIT 3-9.   EXAMPLE CALCULATION OF FLOAT METHOD FOR ESTIMATING
                    DRAIN FLOW RATES (Continued)
              « W(15ft/min)(0.32fi>) + (13 ft/min)(0.32 ft) + (10 ft/min)(0.32 ff)J
              ~4 cfm
the pipe or ditch must be raised above the ground.  Also, the flow must be small enough to be
captured by a bucket or other suitable container without overflowing.  If these conditions are not
present, another method must be used. The procedure involves recording the time that each sample
is taken, the time it takes for the container to be filled, and the volume of discharge collected. The
flow rate is then calculated in gallons per minute (gpm) or in cubic feet per minute (cfm). The basis
for the bucket and stopwatch method is the collection of a measured amount of flow over a measured
amount of time to determine flow per unit of time (or flow rate) as per the formula below.
                  Flaw Kate Q (g>m) - Vobane *'*«**W> x  6
                                           Time to Fill (sec)       1 min

Exhibit 3-10 provides an example of estimating flow rates with the bucket and stopwatch method.
Slope and Depth Method
The slope and depth method is also a relatively easy method for estimating flow rates in pipes and
ditches.  This procedure requires that the slope of the pipe or ditch be known.  A  survey  or
engineering design data such as sewer or grading plans may provide the slope or grade of the pipe
or ditch. In addition, the flow or effluent to be measured should not fully fill the pipe or ditch from
which it is flowing.  To measure the depth of the flow at the center of the pipe or ditch at the outfall,
the outfall should be accessible.  If these conditions are not present, another method should be used.
The procedure involves recording the time that each sample  is taken and measuring the depth of the
flow in the middle of the pipe or ditch. If the flow is coming from a pipe, the inside diameter  of
the pipe should be recorded. If the effluent is coming from a ditch, the width of the flow in the ditch
should be measured. Also, the modified slope of the ditch  should be calculated.  The flow rate is
calculated in cfm  using the same formulas for  both pipes and ditches.  Exhibit 3-11 provides an
example of estimating the flow rate with the slope and depth method.
                                            53

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
      EXHIBIT 3-10.
EXAMPLE CALCULATION OF BUCKET AND STOPWATCH
METHOD FOR ESTIMATING FLOWS
  Step 1:   When each sample or aliquot is taken, record the data for the time the sample was taken. See
           column B.

           EXAMPLE DATA:
A
SM
NMbcr
1
2
3
4
5
6
7
8
9
B
THM

0
20
40
60
80
100
120
140
160
C
Time to
(MCOMta)
40.0
26.0
24.0
32.0
45.0
31.0
50.0
21.0
28.0
D
VohMeoff
Bwkct
(tallow)
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
E
Calralatad Flow Ratr
    x ,  .
                               '**** '      Time to fill (see)      1mm
                               Qfefin) = Qfgpm) x 0.1337 ft '/gal
  Example: For Sample 1
                             Q(gpm)=
                                       40.0 see   1 min
                         Q (cfm) = 3.0 gpm x 0.1337ft '/gal = 0.4 cfm
                                            54

-------
                                                    CHAPTER 3 - FUNDAMENTALS OF SAMPLING
  EXHIBIT 3-11.
                    EXAMPLE CALCULATION OF SLOPE AND DEPTH METHOD FOR
                    ESTIMATING FLOW RATES
Step 1:   Obtain the pipe or ditch channel percent slope from engineering data.  Determine the inside
         diameter if the flow is from a pipe.

         EXAMPLE DATA:  For purposes of this example, a ditch with a 2 percent slope is assumed.
Step 2:   When each sample or aliquot is taken, record the data for the time the sample was taken.  See
         column B.

         EXAMPLE DATA:
A
SUM*
Noaber
1
2
3
4
5
6
7
8
9
B
TIM
(BJmrteO
0
20
40
60
80
100
120
140
160
C
Depth of
Water fr)
3.6
6.0
7.2
8.4
7.2
6.0
6.0
6.0
4.6
D
Width of Flow
(dteho»|y)
(feet)
2.2
3.2
4.0
4.2
4.0
3.2
3.0
2.9
2.5
E
•M"
MfftflllflMl *&AIM
(ditch oriy)
3.7
3.2
3.3
3.0
3.3
3.2
3.0
2.9
3.3
F
Cafadated Flow
Rate 
-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Runoff Coefficient Methods
Runoff coefficient methods are the least accurate of all the flow rate estimation methods.  These
methods  should only be used for composite flow-weighted  samples if all of the other methods are
inappropriate for the site. Although the least accurate, runoff coefficients are the simplest method
of estimating runoff rates.

Runoff coefficients represent the fraction of total rainfall that will be transmitted as runoff from the
drainage area that flows into the facility outfall.  Runoff coefficients consider the ground surface or
cover material and determine the amount of storm water flow which may infiltrate or runoff as a
discharge.   A simple estimate  of runoff volume assumes that  paved areas and other impervious
structures such as roofs have a runoff coefficient of 0.90 (i.e., 90 percent of the rainfall leaves the
area as runoff).  For unpaved surfaces, a runoff coefficient of 0.50 is normally assumed.  A more
accurate  estimate can be  made by using more specific runoff coefficients for different areas of the
facility, based on the specific type of ground cover.  Commonly used runoff coefficients are listed
in Exhibit 3-12.

The average runoff coefficient can be estimated for drainage areas that have both paved and unpaved
areas by  weighting the coefficients based on their proportion of the total area. An equation for this
would  be:
   Estimated Average Runoff Corf.  =       *><*«*ff <**• # - (Area B) (Runoff Corf. B)
                                                      Area A + Area B
The area of the drainage basin can generally be obtained from land surveys conducted at the time
of facility purchase or site surveys taken from design documents developed as part of construction
planning.   If these are not available,  the  applicant  may estimate the drainage areas from a
topographic map  of the area.   The areas used in this calculation should include only  those areas
drained by the sampled outfall.  When determining the basin  area that drains through the outfall,
some  special considerations should be noted:  (1) storm water from sources outside an industrial
facility's property boundary may contribute to the discharge; and (2) storm water not associated with
industrial  activity may contribute to  the flow volume.   Where these conditions occur, the facility
should accurately quantify and appropriately address these contributions.
                                             56

-------
     CHAPTER 3 - FUNDAMENTALS OF SAMPLING

1 EXHIBIT 3-12. TYPICAL "c" COEFFICIENTS FOR 5- TO 10-YEAR FREQUENCY
DESIGN STORMS
i^^^M^^^^^^^^^Bi^H^^H^^^^^^^^^^^HMVMV^^H^^^^^^^^^HMB*^^^^^^^H^^^HVMi^^^^^^^BBi^^^^^^^^^«B^BBB
Description of Area
Business
• Downtown areas
• Neighborhood areas
Residential
• Single-family areas
• Multiunits (detached)
• Multiunits (attached)
Residential (suburban)
Apartment dwelling areas
Industrial
• Light areas
• Heavy areas
Parks and cemeteries
Playgrounds
Railroad yard areas
Unimproved areas
Streets
• Asphalt
• Concrete
• Brick
Drives and walks
Roofs
Lawns - course textured soil (greater than 85 percent sand)
• Slope: Flat (2 percent)
Average (2-7 percent)
Steep (7 percent)
Lawns - fine textured soil (greater than 40 percent clay)
• Slope: Flat (2 percent)
Average (2-7 percent)
Steep (7 percent)
Runoff Coefficients

0.70-0.95
0.50-0.70

0.30-0.50
0.40-0.60
0.60-0.75
0.25-0.40
0.50-0.70

0.50-0.80
0.60-0.90
0.10-0.25
0.20-0.35
0.20-0.40
0.10-0.30

0.70-0.95
0.80-0.95
0.70-0.85
0.75-0.85
0.75-0.95

0.05-0.10
0.10-0.15
0.15-0.20

0.13-0.17
0.18-0.22
0.25-0.35
Source: Design and Construction of Sanitary and Storm Sewers, with permission from the
publisher, American Society of Civil Engineers, Manual of Practice, page 37, New York,
1960.
57

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
There are two specific methods to estimate flow rate using runoff coefficients. The first method uses
depth of flow in a pipe or ditch and an average runoff rate to estimate each of the sample flow rates
where the slope/pitch of the pipe or ditch is unknown. Exhibit 3-13 provides an example calculation
of estimating flow rates based on depth and runoff coefficients.  The second method uses only
rainfall accumulation and runoff coefficients to estimate a flow associated with the time the sample
was taken.  No actual flows or flow depths are measured.  Exhibit 3-14 provides an example of
estimating the flow rate based on rainfall depth and runoff coefficients.

3.2.3 MEASURING TOTAL FLOW VOLUMES FOR THE SAMPLED RAIN EVENT
Similar to measuring  flow rates, flow volumes may be measured  using automatic flowmeters or
primary/secondary devices as discussed in Section 3.2.1. Measurement of flow volume with these
devices provides a reasonably accurate determination of the total  flow volume for the entire storm
water discharge.  In many  cases, however, primary or secondary devices have not been installed for
storm water flow measurement.  Portable flow measurement devices are often expensive.  Many of
the automatic samplers mat are currently on the market can measure flow volumes as well as perform
sampling.  Where available and when economically feasible, measuring devices should be used to
generate data for calculating  flow.

3.2.4 ESTIMATING TOTAL FLOW VOLUMES FOR THE SAMPLED RAIN EVENT
Since accurate measurement  of total flow volumes is often impracticable due to lack of equipment,
total flow volumes are more commonly estimated.  The two methods provided in this section require
only simple  estimated measurements.  The first  method  is based on rainfall  depths and runoff
coefficients and the second is based on flow rates that can be either measured or estimated.

Runoff Coefficients Methods
Discharge volumes are most  easily estimated using the area of the  drainage basin contributing to the
outfall, the rainfall accumulation,  and a runoff coefficient.  The  total volume of discharge can be
estimated using a simple equation that relates the amount of rainfall to the volume of discharge that
will leave the site as runoff.  The equation is  as follows:
                                          58

-------
                                               CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    EXHIBIT 3-13.
EXAMPLE CALCULATION OF RUNOFF COEFFICIENT/FLOW
DEPTH METHOD FOR ESTIMATING FLOW RATES
Step 1:  Estimate the runoff coefficient for the drainage area that contributes flow to the
        sampled outfall (see Section 3.2.2).

        EXAMPLE: Assume the drainage area to the outfall is 3 acres.  Two of those acres
        are paved with a runoff coefficient of .90, and 1 is unpaved with a runoff coefficient
        of .50. Using the equation for estimated runoff coefficient from the text in Section
        2.2.2.2:
                Est. Run. Coef.  = (2 Ac) (0.90) + (1 Ac} (0.50} = 0.77
                                          2 Ac+ 1 Ac
        The runoff coefficient for the entire drainage area is 0.77.
Step 2:  Measure the rainfall depth. Record the total rainfall of the storm or the rainfall that
        occurred in the first 3 hours (if it lasted more than 3 hours).  Also record the duration
        of the rain event.
        EXAMPLE: Assume the rainfall depth to be 1.0 inches in 3 hours.
Step 3:  Calculate an average runoff rate.
Formula:
        Average Runoff Rate
                               Drainage Area x Runoff Coef. x Rainfall Death
                       Rainfall Duration
Example:
    Average Runoff Rate
      3 Ac x .77 x 1 in
            3hrs
43.560 ff ^   ft  j
 Ac        12in '  Mmin
        When each sample or aliquot is taken, record the data for the time the samples were
        taken and the depth of the water in the center of the ditch or pipe. Record the data in
        columns B and C.

        EXAMPLE DATA:
A
Sample
Numbers
1
2
3
4
5
6
7
8
9
B
Time
(minutes)
0
20
40
60
80
100
120
140
160
C
Channel or Ditch
Water Depth (feet)
1.0
1.1
1.2
1.25
1.3
1.25
1.2
1.7
1.0
D
Calculated Depth-
Weighted Flow Factor
0.82
0.90
0.98
1.02
1.06
1.02
0.98
1.39
0.82
E
Flow Rate
(cfm)
39
42
46
48
50
48
46
65
39
Step 4:  Sum up all the water depths for each sample taken as indicated above in column
        C.
                                Sum =11.0 feet
                                         59

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
     EXHIBIT 3-13.  EXAMPLE CALCULATION OF RUNOFF COEFFICIENT/FLOW
                     DEPTH METHOD FOR ESTIMATING FLOW RATES (Continued)
  Step 5:  Calculate a depth-weight flow factor and record the data in column D.
  Formula:
           Factor = Measured Water Depth   x   Number of Flow Measurements
                                Sum of all Water Depths

  Example: For Sample 1

                               Factor = <^UL5 = OM
                                           11.0

  Step 6:  Calculate the flow rate.  Record the data in column E.

  Formula:
                Flow Rate, Q (cfin) = Average Runoff Rate x Depth Factor

  Example: For Sample 1
                              Q = 47 cfin x 0.82 = 39 cfin
                        V< " Jl

where:   Vt = the total runoff volume in cubic feet
         R, = the total rainfall measured in feet
              = the area (sq ft) within the drainage basin that is paved or roofed
                = the area (sq ft) within the drainage basin that is unpaved
              ~ a specific runoff coefficient (no units) for the drainage area ground cover
Exhibit 3-15 provides an example calculation of total runoff volume from rainfall data.


Discharge Volumes Estimated Based on Measured Flow Rates

Another method of estimating the total volume of a discharge uses a series of measured or estimated
flow rates. The total volume of discharge can be estimated by first multiplying each of the flow rates
by the time interval in between flow measurements.  This time period represents the portion of the
total storm duration that can be associated with the flow rate measurement. Adding all such partial
volumes results in a total flow volume. A procedure for calculating the total runoff volume from
a set of discrete measurements of flow depth and velocity in a ditch during a storm runoff event is
presented in Exhibit 3-16.


                                          60

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
       EXHIBIT 3-14.
                EXAMPLE CALCULATION OF RUNOFF COEFFICIENT
                RAINFALL DEPTH METHOD FOR ESTIMATING FLOW
                RATES
Step 1:   Estimate the ninoff coefficient for the drainage area that contributes flows to the sampled outfall.

         EXAMPLE: See Step 1 in Exhibit 3-14. The site for this example will be similar so a
         coefficient of .77 will be used for the same 3-acre drainage area.

Step 2:   When each sample or aliquot is taken, record the data for the time the sample was taken.
         Record the data in column B.

         EXAMPLE DATA:
A

SMpfe
Nmber
1
2
3
4
5
6
7
8
9
B

TOM
(•motel)
0
20
40
60
80
100
120
140
160
C
Total
RamfaR
Depth
Caches)
0.0
0.2
0.3
0.5
0.6
0.8
0.9
1.0
1.1
D

Tine Sace Lftrt
Sample
0
20
20
20
20
20
20
20
20
E
hero*
RaMaD (mchec)
per 20 mioates
0.0
0.2
0.1
0.2
0.1
0.2
0.1
0.1
0.1
F

Calculated Flow Rate (cftn)
_
84
42
84
42
84
42
42
42
Step 3:



Step 4:



Step 5:


Formula:


Example:


Step 6:

Formula:



Example:
Using a rainfall gauge, measure the total rainfall depth (in inches) and record the data in
column C.

EXAMPLE:  See sample data above.

Calculate the incremental time since the last flow measurement and record the data in column D.

EXAMPLE:  Samples were taken 20 minutes apart so this increment will be 20 minutes for
every sample.

Calculate the additional or incremental rainfall that has occurred since the last measurement.
Record the data in column E.
    Incremental Rainfall - Total Rainfall Sample 2 - Total Rainfall Sample 1
For Sample 2

                  Incremental Rainfall = .2 - 0 - .2 inches
Calculate the flow rate.  Record the data in column F.
   m   D  A  i t—\   (Drainage area)(Runoff coefficient)(1ncnmental rainfall)
   Flow Rate (cfin) =             (Incremental time)          	
Rate =
            20 min
                                                    Ac
                                                     L& .
                                                     12 in
                                                                       cfin
                                            61

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    EXHIBIT 3-15.  EXAMPLE CALCULATION OF TOTAL RUNOFF VOLUME FROM
                    RAINFALL DATA
  Step 1: Determine the area of drainage contributing to die runoff volume at the outfall and
         convert it to square feet.

         Example: Using a land survey, a facility has determined its site encompasses 0.3
         acres (13,068 square feet).  The entire site is used for industrial activities, and
         therefore, any storm water discharges from the site will be associated with industrial
         activity.  A berm surrounds the entire site limiting the drainage area to the site itself
         and preventing any dilution or contamination from other discharges.   (Note:  To
         convert acres to  square feet, multiply the number of acres by 43,560, which is the
         conversion factor).

  Step 2: Determine the rainfall depth during the event that was sampled to the nearest one-
         hundredth of an  inch and convert it to feet.

         Example: From the rain gauge, the rainfall accumulation  is measured at 0.6 inches
         or 0.05 feet (ft). (Note: To convert inches to feet, divide the inches by 12, which is
         the conversion factor).

  Step 3: Determine the runoff coefficients for each area.

         Example: The facility has estimated that Vi of the site,  or 4,356 square feet, is
         covered by impervious surfaces (i.e., roofs or paved roadways) and % of the site, or
         8,712 square feet, is unpaved.

  Step 4: Calculate the volume of flow using the  following formula  and convert the volume to
         liters.

         Formula: Total runoff volume in cubic feet (cuft) =  total rainfall (ft) x (facility
         paved area (sqft) x 0.90 + facility unpaved area  (sqft)  x 0.50]

         Example: Total runoff volume (cuft) = 0.05 x [4,356 x 0.90 + 8,712 x 0.50]

         Total runoff volume = 413.8 cuft or 11,720 liters

         (Note:  To convert cubic feet to liters, multiply  cubic feet by 28.32, which is the
         conversion factor).
                                            62

-------
      CHAPTER 3 - FUNDAMENTALS OF SAMPLING
EXHIBIT 3-16. EXAMPLE CALCULATION OF TOTAL RUNOFF VOLUME
FROM FLOW RATE DATA
Step 1: Measure and tabulate flow depths and velocities every 20 minutes (at the same time
that the sample is collected) during at least the first 3 hours of the runoff event.
EXAMPLE DATA:














A


Sample
Number
1
2
3
4
5
6
7
8
9
B


Time
(minutes)
0
20
40
60
80
100
120
140
160
C
Flow
Velocity
(feet per
minute)
_
4
8
12
8
4
8
4
4
D

Flow
Depth
(feet)
_
0.2
0.4
0.4
0.4
0.2
0.2
0.2
0.2
E


Width
(feet)
.
5
5
5
5
5
5
5
5
F

Calculated
Flow Rate
(cfm)
_
4
16
24
16
4
8
4
4















63

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
       EXHIBIT 3-16.   EXAMPLE CALCULATION OF TOTAL RUNOFF VOLUME
                       FROM FLOW RATE DATA (Continued)
  Step 2:  Calculate and tabulate the cross-sectional area of flow for each of the flow depths
          measured.  Calculate the flow rate for each discrete set of measurements.
  Formula:
Flow Rate Q (cfin)  = Velocity (ft/min) X Area (sqft)
             Area = Depth  x Width
  Example: For Sample 1
                             Area = 0.2ft x 5 ft = 1 sqft
                        Flow Rate = 4ft/min x 1 sqft = 4 cfin
  Step 3:  Plot the flow rate, Q, versus time.  Also, assume that flow drops uniformly from
          the last calculated flow rate (Q9) to zero at the time when Q10 would have been
          taken.

          Example: The flow rates calculated in Step 3 are plotted against the time between
          samples.
            28

            24

            20

   Flowrate  16
      (cfm)
            12

            8

            4

            0
                          40
              60
 80     100    120
Tim* (minutes)
                                                            140    160
                                                       180
                                          64

-------
                                              CHAPTER 3 - FUNDAMENTALS OF SAMPLING
     EXHIBIT 3-16.
EXAMPLE CALCULATION OF TOTAL RUNOFF VOLUME
FROM FLOW RATE DATA (Continued)
Step 4:  The total flow volume (V,) can be calculated by geometrically determining the area
        under the curve.  The summation of the individual volumes per increment of time
        (Vj through V9) is the total flow volume of the event.

        Example:

         28

         24

         20

 Flowrate 16
    (cfm)
         12

          8

          4

          0
                  20     40     60      80    100     120
                                       Time (minutes)
                                        140
160    180
Step 5:  Compute the flow volume associated with each observation (V,, V2, ..., V9) by
        multiplying the measured flow rate by the duration (in this case, 20 minutes).  Be
        sure the units are consistent.  For example, if durations are in minutes and flow
        velocities are in cubic feet per second (cfs), convert the durations to seconds or the
        velocities to feet per minute.
               Example

                  12

          Flowrate  8
             (cfm)
                   4
                                              Time (minutes)
                                        65

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
       EXHIBIT 3-16.  EXAMPLE CALCULATION OF TOTAL RUNOFF VOLUME
                     FROM FLOW RATE DATA (Continued)
         Formula: Volume (V) = Flow Rate (cfm) x Duration (minutes)
         Example:
V, -
                                           (4-0)<20-0) =40 ft3
                         * (16 -4) (40 -20) +4(20)
                                    200 ft3
       V, =40 ft3
       V2 = 200 ft3
       V3 =400 ft3
       V« =400 ft3
       V3 = 200 ft3
       V6 = 120 ft3
       V7 = 120 ft3
       V8 = 80ft3
       V, = 40 ft3

 Step 6:  Total the individual volumes calculated in Step 5 to obtain the total runoff volume.
         Example:
                           Total Storm Runoff = 1,600 f?

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.2.5  REPORTING STORM WATER DISCHARGE FLOW RATES AND VOLUMES
Form 2F requires applicants to provide quantitative data (reported both as concentration and as total
mass) based on flow-weighted samples collected during storm events.   In addition, applicants are
required to provide flow estimates or flow measurements, as well as an estimate of the total volume
of the discharge.   The method of flow estimation or measurement  must be described in  the
application.  Although EPA only requires flow estimates in Form 2F, accurate flow measurement
is necessary for collecting representative flow-weighted composite samples and reporting pollutant
mass loadings.

3.2.6  MEASURING RAINFALL
Many types of instruments have been developed to measure the amount and intensity of precipitation.
All forms of precipitation are measured on the basis of the depth of the water that would accumulate
on a level surface if precipitation remained where it fell. There are two types of rain gauges -
standard and recording gauges. A standard rain gauge collects the rainfall so that the amount of rain
can be easily measured.  The standard gauge for the NWS has a collector which  is 8 inches in
diameter.  Rain flows from the collector  into a cylindrical measuring tube inside the overflow can.
The measuring tube has a cross-sectional area one tenth the size of the collector so that 0.1 inch of
rainfall will fill 1  inch of the measuring tube.  While this standard gauge is both accurate and easy
to use, any open receptacle with vertical sides can be an effective rain gauge.  Standard rain gauges
are simple and inexpensive; however, with a standard gauge, there is no way to record changes in
the  intensity of the rainfall without making frequent observations of the gauge during the storm.

The second type of gauge is the recording rain gauge, which provides a permanent record of the
amount of rainfall which accumulates over time. Three common types of recording gauges are:
    • Tipping Bucket Gauge - Water caught in a collector is funneled into a two-compartment bucket;
      a known quantity of rain fills one compartment, overbalancing the bucket and emptying k into a
      reservoir.  This moves the second bucket into place beneath the funnel. The tipping of the bucket
      engages an electric circuit, which records the event.
    • Weighing Type Gauge - Water is weighed when k falls into a bucket placed on the platform of
      a spring or lever balance.  The weight  of the contents is recorded on a chart, showing the
      accumulation of precipitation.
    • Float Recording Gauge - Water is measured by the rise of a float that is placed in the receiver.
      These gauges may be self-siphoning, or may need to be emptied periodically by hand.

                                           67

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
Recording rain gauges provide a permanent record of rainfall, and they can be used to determine
variations in rainfall intensity over time without making frequent observations during the storm.  But
recording gauges are more complicated mechanically than standard gauges, making  them more
costly, less durable, and more difficult to operate.

Although all gauges are subject to error, most errors can be minimized..   To minimize errors, the
gauge should be placed on a level surface that is not windswept and is away from trees or buildings
that might interfere with the path of rainfall.  When taking measurements, other factors contributing
to error should also be considered:  mistakes in reading the scale, dents in the collector rim (which
changes the receiving area), measuring sticks that may retain some of the water, and water lost to
evaporation.  In  the case of tipping bucket gauges, water may not be collected while the bucket is
still tipping. The most common source of inaccuracy is changes in data that are attributable to wind.
It is possible to assess wind errors by comparing measurements of gauges that are protected from
the wind with those that are not.

3.3  GRAB SAMPLE COLLECTION
Section 3.1.2  discussed both the parameters that must be monitored by  grab sample and the
conditions under which grab sampling is required.   This section explains how to collect  grab
samples. The entire sample is collected at an uninterrupted interval (i.e., grabbed at one time).  A
grab sample provides information on the characterization of storm water at a given time  and may be
collected either manually or automatically as discussed below.

3.3.1  HOW TO MANUALLY COLLECT GRAB SAMPLES
A manual grab is collected  by  inserting a container under or downcurrent of a discharge with the
container opening facing upstream.  Generally, simplified equipment and  procedures can be used.
In most cases, the sample container itself may be used to collect the sample. Less accessible outfalls
may require the use of poles and buckets to collect grab samples.  To  ensure that manual grab
samples are representative of the storm water discharged, the procedures  set forth in Exhibit 3-17
should be followed.
                                            68

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
   EXHIBIT 3-17.   RECOMMENDED OPERATING PROCEDURES FOR TAKING GRAB
                    SAMPLES
      • Label sample containers before sampling event

      • Take a cooler with ice to the sampling point

      • Take the grab from the horizontal and vertical center of the channel

      • Avoid stirring up bottom sediments in the channel

      • Hold the container so the opening faces upstream

      • Avoid touching the inside of the container to prevent contamination

      • Keep the sample free from uncharacteristic floating debris

      • Transfer samples into proper containers (e.g.,  from bucket to sample container),
        however, fecal coliform, fecal  streptococcus, phenols and O&G should remain in
        original containers

      • If taking numerous grabs, keep the samples separate and labelled clearly

      • Use safety precautions (see Chapter 6)
Specialized equipment and procedures may be needed, particularly in situations where storm water

discharges are inaccessible or where certain parameters are monitored.  For example:
    •  When sampling for O&G and VOCs, equipment that safely and securely houses O&G bottles
       or VOC vials should be used.  This may be necessary because:  (1) O&G will adhere to
       containers and thus should not be transferred from one container to another; and (2) excessive
       aeration during sampling may result in the partial escape of VOCs.

    •  Since facilities sometimes use sample bottles that already contain preservatives (as provided
       by contract laboratories), extreme care should be taken when filling them  to avoid spills,
       splatters,  or washout of the preservatives.
All equipment and  containers that come into  contact with the sample must  be clean  to avoid
contamination. Additionally, sample collection equipment and container materials should be totally

unreactive to prevent leaching of pollutants.  Cleaning procedures are discussed  in detail in Section
3.5.
                                           69

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.3.2 HOW TO COLLECT GRAB SAMPLES BY AUTOMATIC SAMPLER
Grab samples can also be collected using programmed automatic samplers.  Automatic samplers
come equipped with computers that can be programmed to collect grab samples.  Programming for
grabs is specific to the type of automatic sampler.  Some samplers are portable and have been
developed specifically to sample for storm water discharges. These samplers are frequently attached
to a rain gauge and/or a flow sensor. Such samplers can be programmed to initiate sample collection
by one or more of the following conditions:  (1) depth of flow in a channel; (2) rainfall in inches;
(3) flow rate; (4) time; (5) external signal; and (6) combinations of the first three conditions.  For
example, an automatic sampler could be used to collect  a sample at 15-minute intervals after its
sensors indicate that rainfall has begun.

When using an automatic sampler, planning is very important. First, all equipment must be properly
cleaned, particularly the tubing and the sample containers.  There are several different types of
tubing available, including rubber and Tygon tubing.  Tygon tubing is commonly used since it
generally does not leach contaminants.  Deionized water should be drawn through the sampler to
remove any remaining pollutant residuals prior to taking samples.  Tubing should also be replaced
periodically to avoid algae or bacterial growth.

Sampling personnel should also use adequate and appropriate containers and ensure they are properly
cleaned.  Section 3.5 contains information on cleaning procedures which should be followed for all
equipment.  Additionally, the utilization of blanks (a control used to verify the accuracy of analytical
results) is recommended to determine if cross-contamination of sampling equipment has occurred.
Samplers should also be programmed, set up, and supplied with  a  source of power.  Properly
charged batteries should be readily available for portable samplers in advance of a storm event and,
as a backup power supply in case of power failure. Finally, although automatic samplers may be
useful in some situations, several parameters  are not amenable  to collection by automatic sampler.
These pollutants include fecal streptococcus, fecal conforms, oil and grease and VOCs which  should
be collected manually, not automatically, as discussed in Section 3.1.2.

3.4  FLOW-WEIGHTED  COMPOSITE SAMPLE COLLECTION
Composite samples are samples simply comprised of a series of individual sample aliquots that have
been combined to reflect average pollutant concentrations of the storm water discharge during the
                                           70

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
 sampling period. Composite samples can be developed based on time or flow rate.  There are four
 different types of composite samples, as follows:

     •  Constant Time - Constant Volume - Samples of equal volume are taken at equal increments
       of time and composited to make an average sample (similar to Exhibit 3-18).  This method
       is not acceptable for samples taken for compliance with the storm water permit application
       regulations.
     •  Constant Time  -  Volume Proportional to  Flow Increment - Samples are  taken at equal
       increments of time and are composited proportional to the volume of flow since the last
       sample was taken (see Exhibit 3-19).
     •  Constant Time - Volume Proportional to Flow Rate - Samples are taken at equal increments
       of time and are composited proportional to  the flow rate at the time each sample was taken
       (see Exhibit 3-20).
     •  Constant Volume*- Time Proportional to Flow Volume Increment - Samples of equal volume
       are taken at equal increments of flow volume  and composited (see Exhibit 3-21).

 Generally, flow-weighted composite samples must be collected for most parameters. The methods
 for generating flow-weighted composite samples are discussed in the following sections.

 For storm water discharge permit applications, the aliquots for flow-weighted composite samples
 must be collected during a representative storm for the first 3 hours, or for the duration of the storm
 event if it is less than 3 hours long. The storm water application regulations allow for flow-weighted
 composite samples to be collected  manually or automatically.  For both methods, equal volume
 aliquots may be collected at the time of sampling and then flow-proportioned and composited in the
 laboratory, or the aliquot may be collected based on  the flow rate at the time of sample collection
 and composited in the field.  When composite samples are collected, the regulations require that each
 aliquot collection be  separated by a  minimum  of IS  minutes and that a minimum of three sample
 aliquots be taken within each hour of the discharge.  See Exhibit 3-22 for an example of how this
 requirement may be fulfilled.

The  provisions set forth in 40  CFR 122.21 (g)(7) for collecting flow-weighted composite samples
establish  specific requirements for minimum time duration between sample aliquots. Where these
conditions cannot be met, the permitting authority may allow alternate protocols with respect to the
time duration between sample aliquots (see Chapter 5). However, permission from the permitting
                                            71

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
              EXHIBIT 3-18.   CONSTANT TIME - CONSTANT VOLUME
                              DENOTES SAMPLES OF EQUAL
                            VOLUME (SAME LENGTH ARROWS)
                               AT EQUAL TIME INTERVALS
                                    TIME (t)
          Method of compositing samples on a fixed volume-fixed time interval basis
     Source:  Methodology for the Study of Urban Storm Generated Pollution and Control,
                         U.S. EPA 600/2-76-145, August 1976.
       EXHIBIT 3-19.
            s
            r
            § 5
            "•  k
            Ul
            »
            5  3
            _l

            S  2

               1

               0
CONSTANT TIME - VOLUME PROPORTIONAL TO FLOW
INCREMENT
                                  TIME (t)
      Method of compositing samples proportional to flow volume at constant time interval
     Source:  Methodology for the Study of Urban Storm Generated Pollution and Control,
                         U.S. EPA 600/2-76-145, August 1976.
                                        72

-------
                                         CHAPTER 3 - FUNDAMENTALS OF SAMPLING
  EXHIBIT 3-20.  CONSTANT TIME - VOLUME PROPORTIONAL TO FLOW RATE
        2 3

        2
                      DENOTES COLLECTION OF A SAMPLE
                   WHERE VOLUME IS PROPORTIONAL TO THE
                   RATE OF FLOW.  THE INDIVIDUAL SAMPLES
                     ARE COMPOSITED INTO ONE CONTAINER
                                 TIME(t)
              Method of compositing samples proportional to flow rate
   Source:  Methodology for the Study of Urban Storm Generated Pollution and Control,
    	            U.S. EPA 600/2-76-145, August 1976.	
EXHIBIT 3-21.
        Ul
        §
CONSTANT VOLUME - TIME PROPORTIONAL TO FLOW VOLUME
INCREMENT
                                   t • VAftlABU
                                 DENOTES SAMPLES OF EQUAL VOLUME
                                (SAME LENGTH ARROWS) AT CONSTANT
                                  FLOW INCREMENTS (VARIABLE TIME)
                                 TIME(t)
      Method of compositing samples of equal volume at equal increments of flow
  Source:  Methodology for the Study of Urban Storm Generated Pollution and Control,
  	U.S. EPA 600/2-76-145. August 1976.
                                   73

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
                 EXHIBIT 3-22.    EXAMPLE OF SAMPLING INTERVALS
  Suppose that a storm water discharge began at 2:15 p.m. and lasted until 5:15 p.m. on a
  Friday.  The field staff person wants to collect the samples at regular intervals,  so s/he plans
  to collect an aliquot with a volume that is proportional to the flow every 20 minutes.  After
  the third hour of collection,  the field staff person must deliver the samples to the laboratory
  (which is 10 minutes away).  The laboratory closes at 5:00 p.m.  So, s/he should take the last
  sample at 4:45 p.m. One way of doing mis would be to collect samples (in hour three) at
  4:15, 4:30, and 4:45 p.m.  This would comply with the three-sample minimum in hour three
  (4:15-5:15 p.m.) and the required 15-minute minimum interval between collections.  It would
  also allow the field staff person to get the samples to the lab before it closes for the weekend.
  On the other hand, if s/he missed the sample collection at 4:15 p.m. and instead, collected the
  sample at 4:20 p.m., then s/he would have to collect the next sample at 4:35 p.m. and the
  last sample at 4:50 p.m., and the field staff person would not be able to deliver the sample
  until Monday (by which time the required maximum holding time would be exceeded), and
  the sampling would need to  be repeated.
                                            74

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
authority must be obtained before changes are initiated.  Considerations applicable to the collection
of flow-weighted composites by automatic and manual techniques are discussed  in the following
sections.

3.4.1  HOW TO MANUALLY COLLECT FLOW-WEIGHTED COMPOSITE SAMPLES
Manually collected, flow-weighted composite samples may be appropriate for a facility that prefers not
to invest in automatic equipment. This technique is cost-effective for short-term monitoring programs and
for facilities where few outfalls are being sampled.  The fundamental requirement for facilities that use
these methodologies is mat they should have personnel available to perform the sampling when needed.
Those  facilities where VOCs analysis of storm water discharges are required  should manually collect
composite samples since these parameters may not be amenable to sampling  by automatic samplers.
Compositing of VOC samples should be conducted in the laboratory as discussed in Section 3.5.2.

The manual collection of a flow-weighted sample is performed in the same manner as taking manual grab
samples (see Section 3.3.1). The only difference is mat a series of samples (or aliquots) will be collected.
As discussed in the previous section, there are two ways to manually collect and  combine the aliquots for
a flow-weighted sample:

    •  Collect sample aliquot volumes based on the flow at the time of sampling which can immediately
       be combined to make the composite sample in the field (see Exhibit 3-23)
    •  Collect equal volume sample aliquots  at the time of sampling and  then flow-proportion and
       composite the aliquots in the laboratory (see Exhibit 3-24).

When uniform time intervals are used between the collection of the sample aliquots, the volumes of each
aliquot used in the composite sample can be determined based on either volumes of flow or the flow rate,
as they will result in similar proportions.  However, when there are different  time intervals between the
sample aliquots, the individual sample aliquot volumes should be based on the runoff volume (calculated
from the individual flow rates and durations) associated with each sample aliquot.
Generally, 1,000 ml for each aliquot collected should provide enough sample volume, when composited,
for pollutant analyses of the required parameters contained in Section VILA of Form 2F (see Section 3.6).
More aliquot volume may be required if sampling is conducted for additional parameters. The laboratory
conducting the analyses should always be contacted  prior to a sampling event to  determine how  much
sample volume they will require.

                                            75

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    EXHIBIT 3-23.
EXAMPLE OF HOW TO COLLECT SAMPLE ALIQUOT VOLUMES
BASED ON FLOW, AND  PROPORTION AND COMPOSITE IN THE
FIELD
  Step 1:   Determine the necessary volume for compositing purposes.

           Example: To fulfill analyses for all parameters in Section VILA of Form 2F for which composite
           samples are required [Biochemical Oxygen Demand (BOD3), Chemical Oxygen Demand (COD),
           Total Suspended Solids (TSS), Total Kjeldahl Nitrogen (TKN), nitrate plus nitrite, and
           phosphorous] a total composite sample volume of 5,000 ml is needed by the contract laboratory.

  Step 2:   Determine an appropriate interval for  collection of samples.

           Example: Manually collected flow-weighted composite samples must consist of at least three
           sample aliquots collected per hour and must be gathered at least IS minutes apart.  For this
           example, sample aliquots will be collected exactly  20 minutes apart.

  Step 3:   Estimate or measure the volume of discharge for each sampling event.

           Example: A discharge flow volume of 4.8 cubic feet will be used here.

  Step 4:   Convert the discharge flow volume to liters.

           Example: To convert cubic feet to liters, use the conversion factor of 28.32 liters per 1 cubic
           foot as set forth in the following formula:

           Volume (liters)  - Volume (cubic feet) x  28.32 liters
                                               1 cubic foot
           Volume - 4.8 cubic feet x 28.32 liters = 136 liters
                                   1 cubic foot

  Step 5:   Using Steps 3 and 4, volumes that have been discharged between the collection of each aliquot
           can be calculated.

           (Note that the discharge volumes provided for aliquot numbers  2-9 have already been given for
           me purposes of this  exhibit.)
Example: The procedures set forth in Section 3.2 may be
The following table presents aliquot numbers, time of aliq
Aliquot Number
1
2
3
4
5
6
7
8
9
Tune of Aliquot Collection
2:15 p.m.
2:35 p.m.
2:55 p.m.
3:15 p.m.
3:35 p.m.
3:55 p.m.
4: 15 p.m.
4:30 p.m.
4:45 p.m.
used to calculate discharge volumes.
uot collection, and discharge volumes.
Discharged Volume
136 liters
200 liters
122 liters
178 liters
156 liters
117 liters
94 liters
21 liters
12 liters









                                                76

-------
                                                    CHAPTER 3 - FUNDAMENTALS OF SAMPLING
  EXHIBIT 3-23.
EXAMPLE OF HOW TO COLLECT SAMPLE ALIQUOT VOLUMES
BASED ON FLOW. AND PROPORTION  AND COMPOSITE IN THE
FIELD (Continued)
Step 6:  Determine the appropriate minimum aliquot volume as the basis for collecting other aliquot
        samples which together will provide adequate volume to fulfill the analytic requirements.
        Example:  In Step 1, it was determined that at least 5,000 ml of sample were required for flow-
        weighted composite sample analytical testing. As discussed in Section 3.4.1, basing the sample
        collection on a minimum aliquot volume of 1,000 ml gathered every interval (i.e., every  IS
        minutes) should result in adequate sample volume.
Step 7:  Calculate the volume of the sample aliquot which must be collected during each aliquot sample
        period using the following formula:

       Aliquot volume (ml) = Minimum aliquot volume (ml)  *  Aliauot's discharge volume (liters}
                                                          Initial discharge volume (liters)

                 Step 6 shows that the minimum aliquot volume is 1,000 ml.

                Aliquot n volume (ml) = 1.000 ml x 136 liters =  1,000 ml
                                                 136 liters

                Aliquot #2 volume (ml) = 1,000 ml x 200 liters =  1471 ml
                                                 136 liters

                Aliquot #3 volume (ml) = 1,000 ml x 122MTS =  897ml
                                                 136 liters

                Aliquot *4 volume (ml) = 1.000mix 178 liters =  1,309ml
                                                 136 liters

                Aliquot #5 volume (ml) = 1,000 ml x 156 liters =  1,147 ml
                                                 136 liters
                Aliquot #6 volume (ml) = 1.000 ml x 117 liters =  860ml
                                                 136 liters
                Aliquot H7 volume (ml) = 1.000mix 94 liters = 691 ml
                                                 136 liters
                Aliquot H8 volume (ml) = 1.000 mix 21 liters - 154 ml
                                                 136 liters
                Aliquot #9 volume (ml) = 1.000 mix 12 liters -  88 ml
                                                 136 liters
                A table of these calculations follows:
Aliquot Number
1
2
3
4
5
6
1
8
9
Discharged Volume
136 liters
200 liters
122 liters
178 liters
156 liters
117 liters
94 liters
21 liters
12 liters
Aliquot Volume
1,000ml
1,471 ml
897ml
1,309ml
1,147 ml
860ml
691ml
154ml
88ml
        In conclusion, a combination of the above sample aliquots result in a composite of 7,617 ml.
                                             77

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    EXHIBIT 3-24.
EXAMPLE OF HOW TO MANUALLY COLLECT EQUAL SAMPLE
ALIQUOTS WHICH ARE LATER FLOW-PROPORTIONED AND
COMPOSITED IN THE LABORATORY
  Step 1: Determine the necessary volume for compositing purposes.

         Example: To fulfill analyses for all parameters in Section VILA of Form 2F for which composite
         samples are required (BOD,, COD, TSS, TKN, nitrate plus nitrite, and phosphorous) a total
         composite sample volume of 5,000 ml is needed by the contract laboratory.

  Step 2: Determine an appropriate interval for collection of samples.

         Example: Manually collected flow-weighted composite samples must consist of at least nine
         sample aliquots and must be gathered at least 15 minutes apart; only three or four samples per hour
         may be taken. For convenience, the minimum number of three is chosen.  Sample aliquots will be
         collected every 20 minutes.

  Step 3: Determine the aliquot which should be taken during each sampling event.

         Example: At least 5,000 ml of sample is required for flow-weighted composite sample analytical
         testing. As discussed in Section 3.4.1, a minimum aliquot volume of 1,000 ml garnered every
         interval (i.e., every 15 minutes) should result in adequate sample volume to be used for later flow-
         weighted compositing.

  Step 4: Estimate or measure the volume of discharge for each sampling event while collecting a discrete
         1,000-mI aliquot, as discussed in Step 3, for later compositing.

         Example: Section 3.2 discusses methods to calculate total discharge volumes. A discharge flow
         volume of 4.8 cubic feet will be used here.

  Step 5: Convert the discharge flow volume to liters.

         Example: To convert cubic feet to liters, use the conversion factor of 28.32 liters per 1 cubic foot
         as set forth in the following formula:

         Volume (liters) = Volume (cubic feet) x  28.32  liters
                                            1 cubic foot

         Volume - 4.8 cubic feet x 28.32 liters = 136 liters
                                 1 cubic foot
                                              78

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
  EXHIBIT 3-24.
EXAMPLE OF HOW TO MANUALLY COLLECT EQUAL SAMPLE
ALIQUOTS WHICH ARE LATER FLOW-PROPORTIONED AND
COMPOSITED IN THE LABORATORY (Continued)
Step 6: Using Steps 3 and 4, calculate the volumes that have been discharged between the collection of each
       aliquot.

       Example:  The procedures set forth in Section 3.2 may be used to calculate discharge volumes.
       The following table presents aliquot numbers, time of aliquot collection, and discharge volumes
       (note that the discharge volumes provided for aliquot numbers 2-9 were chosen for purposes of this
       exhibit).
Aliquot Number
1
2
3
4
5
6
7
8
9
Time of Aliquot Collection
2:15 p.m.
2:35 p.m.
2:55 p.m.
3:15 p.m.
3:35 p.m.
3:55 p.m.
4:15 p.m.
4:30 p.m.
4:45 p.m.
Discharged Volume
136 liters
200 liters
122 liters
178 liters
156 liters
117 liters
94 liters
21 liters
12 liters
Step 7: Determine the aliquot sample which is associated with the greatest discharge volume.

       Example:  Aliquot number 2 was taken when the volume was 200 liters.  This is the largest
       discharge volume.

Step 8: Calculate the volume of sample aliquot which must be used subsequent to the sample event to
       comprise a flow-weighted composite sample. The following formula should be used:

       Aliquot volume (ml)  = Minimum aliquot volume (ml) x Aliauot's discharfe  volume (liters}
                                                        Largest discharge volume (liters)

       Step 3 shows that the minimum aliquot volume is 1,000 ml.  Using this value and the data
       determined as part of Steps 6 and 7, the following can be calculated:

       Aliquot HI volume (ml) = LOOP ml x 136 liters =  680ml
                                        200 liters

       Aliquot #2 volume (ml) « 1,000 ml x 200 liters = 1,000 ml
                                        200 liters

       Aliquot »3 volume (ml) = 1,000 ml x 122 liters = 610 ml
                                        200 liters

       Aliquot #4 volume (ml) • LOOP ml x 178 liters = 890ml
                                        200 liters

       Aliquot itS volume (ml) = 1,000 ml x 156 liters = 780 ml
                                        200 liters

       Aliquot H6 volume (ml) = 1,000 ml x 117 liters » 585 ml
                                        200 liters
                                             79

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
   EXHIBIT 3-24.
EXAMPLE OF HOW TO MANUALLY COLLECT EQUAL SAMPLE
ALIQUOTS WHICH ARE LATER FLOW-PROPORTIONED AND
COMPOSITED IN THE LABORATORY (Continued)
In
Aliauot #7 volume (ml) = 1.000 mix 94 liters • 470ml
200 liters
Aliquot US volume (ml) = 1,000 ml x 21 liters = 705 ml
200 liters
Aliauot #9 volume (ml) = 1.000 mix 12 liters = 60ml
200 liters
A table of these calculations follows
Aliquot Number
1
2
3
4
5
6
7
8
9
Discharged Volume
136 liters
200 liters
122 liters
178 liters
156 liters
117 liters
94 liters
21 liters
12 liters
Aliquot Volume
680ml
1,000ml
610ml
890ml
780ml
585ml
470ml
105ml
60ml

conclusion, a combination of the above sample aliquots results in a composite sample of 5,100 ml.
Manually collected flow-weighted composite samples can also be prepared by collecting sample
aliquots of equal volume where the collection times are related to the volume of discharge which has
passed since the last sample aliquot collection.  However, this method is subject to fluctuating flow
rates and volumes which may dictate that samples be taken prior to the 15-minute interval required
by the regulations.  In that case, the alternative sampling protocol would have to be approved by the
permitting authority.
3.4.2 HOW  TO   COLLECT  FLOW-WEIGHTED  COMPOSITE  SAMPLES   BY
      AUTOMATIC SAMPLER
The typical automatic sampler collects sample aliquots after a specific interval. These aliquots can
be flow-weight composited by the automatic sampler; or by hand in the laboratory.  The automatic

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
 sampler may be programmed in one of three ways: (1) to collect a sample at equal time intervals
 and varying aliquot volumes commensurate with the flow (either rate or volume) that has passed;
 (2) to collect equal volume aliquots at varying time intervals commensurate with the flow volume
 that has passed; or (3) to collect equal volume aliquots of sample at equal time intervals.

 The first two methods automatically composite the sample but require that the sampler be connected
 to a flow meter such that the sampler determines either the flow rate or the amount of volume that
 passes.  Since these methods automatically composite  samples, one main sample container may be
 used to receive all aliquots.  The third method  automatically collects the sample aliquots but does
 not automatically flow-weight composite the sample.   As such, discrete sample containers must be
 used, and manual flow-weighted compositing must be conducted after the aliquots are collected.
 Exhibits 3-23 and 3-24 in Section 3.4.1 describe the manual compositing procedures that should be
 followed.

 Manufacturers' instructions  for the use of an automatic sampler provide the best explanation of
 programming options and should be consulted for information on programming samplers for storm
 water collection. Some of the points regarding automatic samplers discussed in Section 3.3.2 should
 also be considered.

 3.5 SAMPLE HANDLING AND PRESERVATION
 Samples must be handled and preserved in accordance with 40 CFR Part 136.  This section describes
 acceptable analytical methods, including requirements  regarding sample holding times,  containers,
 sizes, and preservation requirements. For each pollutant or parameter that may have to be analyzed,
 40  CFR Part 136 includes information on:

    • Container types to be used to store the samples after collection
    • Procedures to correctly preserve the samples
    • The maximum holding time allowed for each parameter.

The following sections present a detailed discussion of  preservation techniques and sample handling
procedures.  Technical Appendix C presents a matrix of required containers, preservation techniques,
                                           81

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
and holding times for each  parameter.  Most laboratories can provide clean sample containers,
preservatives,  sealing,  chain-of-custody forms and  can advise  further on  sample handling and
preservation.

3.5.1  DECONTAMINATION OF SAMPLE EQUIPMENT CONTAINERS
Storm  water sample containers should be cleaned and prepared  for field  use according to the
procedures set forth in 40 CFR Part 136. A summary of the procedures is presented below for
plastic containers, any or all of which may be performed by the laboratory or container distributor:

    •  Nonphosphate detergent and tap water wash
    •  Tap water rinse
    •  10 percent nitric acid rinse (only if the sample is to be analyzed for metals)
    •  Distilled/deionized water rinse
    •  Total air dry.

To clean glass containers, the same steps should be  taken; but, after the distilled/deionized water
rinse, the containers should be rinsed with solvent if appropriate prior to total air drying.  After the
decontamination procedures  have  been  accomplished, the sample containers should be capped or
sealed  with foil, and the  sampling device should be protected and kept clean.  It is a good idea to
label sample containers after  cleaning.  The laboratory should keep a record of the technician
performing the cleaning procedure as well as the date and time. This begins  the required chain-of-
custody procedure for legal custody (see Section 3.10 for more information).  A chain-of-custody
record accompanies each  sample to track all personnel handling the sample. This record is essential
to trace the sample integrity in the event that quality control checks reveal problems.   For this
reason, as well as to avoid problems if contamination issues arise, it is suggested that the laboratory
performing the analysis perform the cleaning.
                                            82

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.5.2  SAMPLE PRESERVATION AND HOLDING TIMES
Preservation techniques ensure that the sample remains representative of the storm water discharge
at the time of collection.  Since many pollutants in the samples collected are unstable (at least to
some extent), the sample should be analyzed immediately or preserved or fixed to minimize changes
between the time of collection and analysis.  Because immediate analysis is not always possible, most
samples are preserved regardless of the time of analysis.

Problems may be encountered when flow-weighted composite samples are collected. Since sample
deterioration can take place during the compositing process, it is necessary to preserve or stabilize
the samples during compositing in addition to preserving aggregate samples before shipment to the
laboratory.  Preservation  techniques vary depending on the pollutant parameter to be measured;
therefore, familiarity with 40 CFR Part 136 (see Technical Appendix C) is essential to ensure
effective preservation.  It  is important to verify that the preservation techniques for one parameter
do not affect the analytical results of another in the same sample.  If this is the case, two discrete
samples should be collected and preserved accordingly.

Sample preservation techniques consist of refrigeration, pH adjustment, and chemical fixation.  pH
adjustment is necessary to stabilize the target analyte (e.g., addition of NaOH stabilizes cyanide);
acidification of total metal samples ensures that metal salts do not precipitate.  Refrigeration is the
most widely used technique because it has  no detrimental  effect on the sample  composition (i.e.,
it does not alter the chemistry of the sample), and it does not interfere with most analytical methods.
Refrigeration requires the  sample to be quickly chilled to a temperature of 4°C. This technique is
used at the beginning of sample collection in the field, and is continued during sample shipment, and
while the sample is in the laboratory. Even though samples taken for compositing purposes are taken
over time each individual sample must be refrigerated.  If taken manually, the samples can be placed
in an ice box.   If  taken by a automatic sampler, the sampler  unit should have refrigeration
capabilities.  The analytical laboratory may provide chemicals necessary for fixation,  or may tell
sampling personnel where they can be purchased.

In addition to  preservation techniques, 40  CFR Part  136 indicates maximum holding times.   A
detailed list of holding times appears in Technical Appendix C.  The holding time is the maximum
                                            83

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
amount of time that samples may be held before analysis and still be considered valid.  Samples
exceeding these holding times are considered suspect and sample collection may have to be repeated.

Although Technical Appendix C provides required sample containers, preservation techniques, and
holding times, some of the more commonly monitored parameters warrant additional discussion. The
following  provides a more detailed discussion  of  considerations pertaining to cyanide, VOCs,
organics and pesticides, O&G, pH, total residual chlorine, fecal coliforrn, fecal streptococcus, and
5-day Biochemical Oxygen Demand (BODS).

Cyanide
Cyanide is very reactive and unstable. If the sample cannot be analyzed immediately, it must be
preserved by pH adjustment after collection.  However, prior to pH adjustment,  procedures to
eliminate residual chlorine and sulfides must be followed  immediately.

Where chlorine has the possibility of being present, the sample should be tested for residual chlorine
by using potassium iodide-starch test paper previously moistened with acetate buffer.  If the sample
contains residual chlorine (a blue color indicates the need for treatment), ascorbic acid must be added
0.6 gram (g) at a time until the tests produce a negative result; then, an additional 0.6 g  of ascorbic
acid should be added to the sample.

Samples containing sulfides may be removed,  in which case the holding time is extended  to 14 days.
Sulfides must be removed as follows:
       Use lead acetate paper moistened with an acetic acid buffer solution to test for the presence
       of sulfide. Darkening of the lead acetate paper indicates sulfide is present in the sample.
       Add cadmium nitrate to be added to the sample in a manner similar to the ascorbic acid until
       the test is negative.
       Filter with a 0.45 micrometer (/im) filter and prefilter combination immediately after.
After chlorine and sulfide residuals have been eliminated, the pH must be adjusted to greater than
12.0 standard units (s.u.) and chilled to 4°C.
                                             84

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
If cyanide is suspected to be present, the sampling personnel should bring all materials mentioned
above to the sampling location.

VOCs
Sampling for VOCs requires the use of a glass vial. The vial should contain a teflon-coated septum
seal.   Volatiles  will escape from the water to the  air if any air is  entrapped in the container.
Therefore, the sample should be collected so that there are no air bubbles in the container after the
screw cap and septum seal are applied.  To ensure that air bubbles are not trapped in the vial, the
following procedures should be followed:

    •  Fill the vial until a reverse meniscus forms above the top of the vial
    •  Screw on the cap (the excess sample will overflow)
    •  Invert the vial to check for the presence of air bubbles
    •  If air bubbles are observed, the vial should be opened, emptied,  men completely refilled, and
       the first three actions should be repeated.

VOC samples should not be composited in the field. To composite a sample, the sampling personnel
would have  to mix it thoroughly.  This mixing action would aerate the sample and cause volatiles
to be lost. Therefore, VOC samples should be sent to the laboratory where they can be immediately,
and carefully, composited and analyzed with minimal volatilization as per method Nos. 502.1,502.2,
524.1, and 524.2 as described at 40 CFR  141.24(f)(14)(iv) and (v).   There are two ways flow-
weighted compositing of VOCs can be  accomplished—mathematical compositing or  procedural
compositing as discussed below.

Mathematical Compositing
In this method,  the grab samples are analyzed  separately.  The sampling  personnel  collect the
requisite number of samples and send them to the laboratory. The laboratory performs the individual
analyses on each sample. Five ml (or 25 ml if greater sensitivity is  required) of each grab sample
are placed into the purge vessel of the GC or GC/MS  for analysis.   Special precautions must be
made  to maintain zero headspace  in the syringe  used to transfer the VOC sample into the purge
vessel of the GC or GC/MS.   These analytical results are mathematically flow-weight composited

                                            85

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
using the  calculation in Exhibit  3-24.  The concentrations  (C) should be adjusted by  using the
following  formula:

                  Adjusted Concentration  = IndMdual AU
-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
 the form of 0.008 percent sodium thiosulfate (Na2S2O3) must be added to organic samples if residual
 chlorine is present. To determine if chlorine is present, a small color indicator test kit can be used.
 Eighty ml of Na2S2O3 per liter of sample must then be added and mixed well until chlorine tests
 indicate a negative result as per methods 604 and 625 of 40 CFR Part 136 Appendix A.  The pH of
 pesticide samples must be adjusted to between 5 and 9 s.u.

 Oil and Grease
 O&G tends to adhere to the surfaces that it contacts. Therefore, it should not be transferred from
 one container to another; rather, a 1-liter container should be used to take the sample.  The container
 used for O&G must be made of glass.  A teflon insert should be included in the glass container's lid.
 However,  if  teflon is not available, aluminum foil extending out from under the lid may be used.
 Samples for  O&G must be preserved by adding sulfuric acid (H2SO4) or hydrochloric acid  (HC1)
 to a pH of less than 2 s.u. and then stored at 4°C.

 Additional Considerations
 Some pollutants have specific analysis requirements due to short holding times that the applicant must
 consider.   For example:

    •  Requirements to analyze immediately (pH, total residual chlorine, temperature, sulfite, and
       dissolved oxygen)
    •  Requirements to preserve immediately and analyze within 6 hours (fecal coliform and fecal
       streptococcus)
    •  Requirements to analyze within 48 hours (BODS).

Because of these requirements, field testing equipment may need to be purchased, borrowed, or
rented for  those parameters that may require field analysis.  If the laboratory is  located nearby,
analysis in the field may not be required.

Laboratories do not always operate in  the evenings or on weekends.  As a result, holding times for
samples taken in the late afternoon or on a Friday may be exceeded. To prevent this from occurring,
close coordination with laboratories is necessary.  The latest date and time of delivery should be
                                            87

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
established to avoid taking samples, only to discover they cannot be accepted by the laboratory and

analyzed in accordance with 40 CFR Part 136 requirements.


3.6  SAMPLE VOLUMES

Exhibit  3-25 presents minimal suggested sample volumes for specific parameters.   This exhibit

should be consulted so that the proper volume is collected for analysis of each pollutant of concern.
This exhibit may not include all parameters; if a particular parameter is not listed, refer to 40 CFR

Part 136.


3.7  SAMPLE DOCUMENTATION

Information should be submitted to the laboratory with the sample to ensure proper handling by the

laboratory.  Exhibit 3-26 is  an  example form  which can be used  to document the following
information.
    • Unique Sample or Log Number - All samples should be assigned a unique identification
      number. If there is a serial number on the transportation case, the sampling personnel should
      add this number to the field records.

    • Date and Time of Sample Collection - Date and time of sample collection (including notation
      of a.m. or p.m.) must be recorded.  In the case of composite samples, the sequence of times
      and aliquot size should be noted.

    • Source of Sample.  Including Facility Name and Address - Use the outfall identification
      number from the site map with a narrative description; a diagram referring to the particular
      site where the sample was taken should be included.

    • Name  of Sampling Personnel - The names and initials of the persons taking the sample must
      be  indicated. For a composite sample, the names of the persons installing the sampler and
      the names of the persons retrieving the sample should be included.

    • Sample Type - Each sample should indicate whether it is a grab or composite sample.  If the
      sample is a composite, the volume and frequency of individual aliquots should be noted.

    • Preservation  Used - Any preservatives (and the amount) added to  the  sample should  be
      recorded. The method of preservation (e.g., refrigeration at 4°C) should be indicated.

    • Analysis Required - All parameters for which the sample must be analyzed at the laboratory
      should be specified.

-------
     CHAPTER 3 - FUNDAMENTALS OF SAMPLING
1 EXHIBIT 3-25. VOLUME OF SAMPLE REQUIRED FOR DETERMINATION OF THE
VARIOUS CONSTITUENTS OF INDUSTRIAL WASTEWATER
Tests
Volume of Sample, ml*
Physical
Color and odor**
Corrosivity**
Electrical conductivity**
pH, electrometric**
Radioactivity
Specific gravity**
Temperature**
Toxiciry**
Turbidity**
100 to 500
flowing sample
100
100
100 to 1,000
100
flowing sample
1,000 to 20,000
100 to 1,000
Chemical
VOCs
Dissolved Gases
Ammonia,*** NH3
Carbon Dioxide,*** free CO2
Chlorine,*** free C12
Hydrogen,*** H2
Hydrogen sulfide,*** H2S
Oxygen,*** Oj
Sulfur dioxide,*** free SOj
Miscellaneous
Acidity and alkalinity
Bacteria (fecal coliform)
Bacteria (fecal streptococcus)
Biochemical oxygen demand (BOD)
Carbon dioxide, total COz (including CO3~, HCO3", and
free)
Chemical oxygen demand (dichr ornate)
Chlorine requirement
Chlorine, total residual C12 (including OC1', HOC1, NH2C1,
NHC12, and free)
Chloroform-extractable matter
Detergents
Hardness
Hydrazine
100

500
200
200
1,000
500
500 to 1,000
100

100
500
100
100 to 500
200

50 to 100
2,000 to 4,000
200

1,000
100 to 200
50 to 100
50 to 100
89

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
  EXHIBIT 3-25.  VOLUME OF SAMPLE REQUIRED FOR DETERMINATION OF THE
                 VARIOUS CONSTITUENTS OF INDUSTRIAL WASTEVVATER
                 (Continued)
                        Tests
   Volume of Sample, ml*
 Miscellaneous (Continued)
 Micro-organisms
 Volatile and filming amines
 Oily matter
 Organic nitrogen
 Phenolic compounds
 Polyphosphates
 Silica
 Solids, dissolved
 Solids, suspended
 Tannin and lignin
100 to 200
500 to 1,000
3,000 to 5,000
500 to 1,000
800 to 4,000
100 to 200
50 to 100
100 to 20,000
50 to 1,000
100 to 200
 Cations
 Aluminum, A1+ + +
 Ammonium,*** NH4+
 Antimony, SD+ + + to Sb+ + + + +
 Arsenic, AS+++ to AS+ +++ +
 Barium, Ba+ +
 Cadmium, Cd++
 Calcium, Ca+ +
 Chromium, Cr+ + + to Cr+ + + + + +
 Copper, Cu+ +
 Iron,*** Fe++ and Fe+ + +
 Lead, Pb+ +
 Magnesium, Mg+ +
 Manganese, Mn++ to Mn+ + + + + + +
 Mercury, Hg+  and Hg+ +
 Potassium, Ni+ +
 Nickel, Ni+ +
 Silver, Ag+
 Sodium, NA+
 Strontium, Sr+ +
 Tin, Sn+ +  and Sn+ + + +
 Zinc, Zn+ +
100 to 1,000
500
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
200 to 4,000
100 to 1,000
100 to 4,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
100 to 1,000
                                       90

-------
                                              CHAPTER 3 - FUNDAMENTALS OF SAMPLING
                 VOLUME OF SAMPLE REQUIRED FOR DETERMINATION OF THE
                 VARIOUS CONSTITUENTS OF INDUSTRIAL WASTEWATER
                 (Continued)
EXHIBIT 3-25.
                        Tests
                                                         Volume of Sample, ml*
Anions
Bicarbonate, HCO3
Bromide, Br
Carbonate, COj"
Chloride, Cl~
Cyanide, Cff
Fluoride, FT
Hydroxide, Off
Iodide, I
Nitrate, NCv
Nitrite, NO,"
Phosphate, Ortho, PO4~, HPO4~, H2PO4"
Sulfate, SO4~, HSCV
Sulfide, S~, HS
Sulfite, SO,", HSOS
                                                      100 to 200
                                                      100
                                                      100 to 200
                                                      25 to 100
                                                      25 to 100
                                                      200
                                                      50 to 100
                                                      100
                                                      10 to 100
                                                      50 to 100
                                                      50 to 100
                                                      100 to 1,000
                                                      100 to 500
                                                      50 to 100
"Volumes specified in this table should be considered as guides for the approximate quantity
of sample necessary for a particular analysis.  The exact quantity used should be consistent
with the volume prescribed in the standard method of analysis, whenever a volume is
specified.
** Aliquot may be used for other determinations.
""""Samples for unstable constituents must be obtained in separate containers, preserved as
prescribed, completely  filled, and sealed against all exposure. 	
Source:  Associated Water and Air Resource Engineers, Inc., 1973, Handbook for Monitoring
Industrial Wastewater, EPA Technology Transfer.
  •  Flow - If flow is measured at the time of sampling, the measurement must be recorded and
     accompanied by a description of the flow measurement method and calculations.

  •  Date. Time, and Documentation of Sample Shipment - The shipment method (e.g., air, rail,
     or bus) as well as the shipping papers or manifest number should be noted.

  •  Comments - All relevant information pertaining to the sample or the sampling site should be
     recorded.   Such  comments  could  include the condition  of the sample site, observed
     characteristics  of  the sample, environmental conditions that may affect the sample,  and
     problems encountered during sampling.
                                        91

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
EXHIBIT 3-26. FIELD SHEET FOR SAMPLE DOCUMENTATION
Sample Source Sample ID # Date:
xx/xx/xx
Facility Name Tune:
XX:XX
a. in. /p.m.
Address
Outfall ID #
Description
Diagram of Site
Flow Description
Flow Calculations
Person Performing Sampling
Signature
Preservation Method
Comments
Ship Via:
Stable Shipping Paper/Manifest
Analysis Required
                                     92

-------
                                                  CHAPTER 3 - FUNDAMENTALS OF SAMPLING
3.8  SAMPLE IDENTIFICATION AND LABELING
Prior to collection of the sample, a waterproof, gummed sample identification label or tag should be
attached to the sample container. This label should contain relevant information for sample analysis,
such as:

    •  Facility name
    •  Name of the sample collector
    •  Sample identification number
    •  Date and time of sample collection
    •  Type of analysis required
    •  Location of sample collection
    •  Preservatives used
    •  Type of sample (grab or composite).

Sample lids should be used to protect the sample's integrity from the time it is collected to the time
it is opened in the laboratory. The lid  should contain the collector's name, the date and time the
sample was collected, and a sample identification number. Information on the seal must be identical
to the  information on the label. In addition, the lid should be taped shut so that the seal must be
broken to open the  sample container.  Caution should be taken to ensure that glue from tape and
label tag wires do not contaminate samples, particularly those containing volatile organics and metals.
Also, waterproof ink should be used to avoid smearing on the label from melted ice used for cooling.

3.9 SAMPLE PACKAGING AND SHIPPING
If the samples are  not hand-delivered to the  laboratory or analyzed in  an onsite laboratory, they
should be placed in a transportation case (e.g., a cooler) along with the chain-of-custody record
form, pertinent field records, and analysis request forms, and shipped to the laboratory.   Glass
bottles should be wrapped in foam rubber, plastic bubble wrap, or other material to prevent breakage
during shipment.  The wrapping can be secured  around the bottle with tape.  The container  lid
should also be sealed with tape. Samples should be placed  in ice or a synthetic ice substitute that
                                           93

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
will maintain the sample temperature at 4°C throughout shipment. Ice should be placed in double-
wrapped watertight bags so the water will not leak from the shipping case. Metal or heavy plastic
ice chests  make good sample transportation cases.  Filament tape wrapped around each end of the
ice chest ensures that it will not open during transport. Sampling records (preferably laminated or
waterproof) can be placed in a waterproof envelope and taped to the inside of the transportation case
to avoid getting them wet in case a sample container or an ice bag leaks.  Shipping containers should
also be sealed to prevent tampering. A copy of all sampling records should be kept onsite in case
they are requested by the permitting authority.

Most  samples will not require any special transportation precautions except careful packaging to
prevent breakage  and/or spillage.  If the sample is shipped by common carrier or sent through the
U.S. mail, it must comply  with Department of Transportation Hazardous Materials Regulations (49
CFR  Parts 171-177).  Air shipment  of hazardous  materials samples may also be  covered  by
requirements of the International Air Transport Association (IATA).  Before shipping a sample, the
facility should be aware of, and follow, any special shipping requirements.  Special packing and
shipping rules apply to substances considered hazardous materials as defined by IATA rules. Storm
water samples are not generally considered hazardous materials, but in the event of a spill, leakage,
etc., at the collection site  hazardous materials may be present in the samples.   Be aware, before
sampling,  of what hazardous materials may be  in the discharge drainage  area.  If the presence of
hazardous materials is suspected, do. not sample unless properly trained.

3.10  CHAIN-OF-CUSTODY PROCEDURES
Once  samples have been obtained  and collection procedures are properly documented, a written
record of the chain of custody of that sample should be made. This is recommended so the applicant
can be confident that the samples have not been tampered with and that the sample once analyzed
is representative of the storm water discharge. "Chain-of-custody" refers to the documented account
of changes in possession that occur  for a particular sample or set of samples.  The chain-of-custody
record allows an accurate step-by-step recreation of the sampling path, from origin through analysis.
Information necessary in chain-of-custody is:

    • Name of the persons collecting the sample
    • Sample ID numbers
                                            94

-------
                                                   CHAPTER 3 - FUNDAMENTALS OF SAMPLING
    •  Date and time of sample collection
    •  Location of sample collection
    •  Names and signatures of all persons handling the samples in the field and in the laboratory.

To ensure that all necessary information  is documented, a  chain-of-custody form should be
developed.  An example of such a form is found in Exhibit 3-27.  Chain-of-custody forms should
be printed on carbonless, multipart paper so all personnel handling the sample receive a copy.  All
sample shipments should be accompanied by the chain-of-custody record and a copy of these forms
should be retained by the originator.  In addition, all receipts associated with the shipment should
be retained. Carriers typically will not sign for samples; therefore, seals must be used to verify that
tampering has not occurred during shipment.

When transferring possession of samples, the transferee should sign and record the date and time on
the chain-of-custody record.   In general, custody transfers are made  for each sample,  although
samples may be transferred as a group. Each person who takes custody should fill in the appropriate
section of the chain-of-custody record.
                                            95

-------
CHAPTER 3 - FUNDAMENTALS OF SAMPLING
             EXHIBIT 3-27.  EXAMPLE OF CHAIN-OF-CUSTODY FORM
                          Source: U.S. EPA, Region 8
                                     96

-------
                                                 CHAPTER 4 - ANALYTICAL CONSIDERATIONS
4. ANALYTICAL CONSIDERATIONS
All storm water discharges must be sampled and analyzed in accordance with the test procedures
provided in 40 CFR Part 136. This section discusses pollutant parameters which must be analyzed
by storm water permit applicants. If the applicant wants to use an alternative test method, the facility
must apply for approval (by submitting a description of the method to the permitting authority for
approval) prior to application submission [see 40 CFR 136.4(d)(3)].  Section 5.4 elaborates on how
to obtain approval for an analytical method for a parameter that is not included in 40 CFR Part 136.
EPA-approved analytical methods at 40 CFR 136.3,  Tables ffl  and 1C are shown in Appendix C of
this document.

When choosing the appropriate 40 CFR Part 136 analytical method, the applicant should consider
sample interferences and potential field sampling error.  Most method detection levels are established
under ideal sample conditions (e.g., with little or no sample matrix interferences or sampling error).
Thus,  for  storm  water samples,  the method  chosen should account  for sampling  error and
interferences.

4.1 INDUSTRIAL REQUIREMENTS
Industrial dischargers must provide information on the following parameters, as required in 40 CFR
    • Any pollutant limited in an effluent guideline to which the facility is subject
    • Any pollutant listed in the facility's NPDES permit for its process wastewater (if the facility
      has an existing NPDES permit)
    • O&G, pH, BOD5, COD, TSS, total phosphorus, TKN, and nitrate plus nitrite nitrogen
    • Any pollutant known or believed to be present [as required in 40 CFR 122.21(g)(7)]
    • Flow measurements or estimates of the flow rate, the total amount of discharge for the storm
      events sampled, and the method of flow measurement or estimation
    • The date and duration (in hours)  of the storm events sampled, rainfall measurements or
      estimates of the storm event (in inches) which generated the sampled runoff, and the time
      between the storm event sampled and the end of the previous measurable (greater than 0.1
      inch rainfall) storm event (in hours).
                                           97

-------
CHAPTER 4 - ANALYTICAL CONSIDERATIONS
4.1.1  INDIVIDUAL APPLICANTS
Industrial facilities submitting an individual permit application must provide sampling data in three
parts of the Form 2F application form as discussed below.  (Form 2F restates requirements listed
in 40 CFR 122.21 and 122.26).

Section VILA Parameters
Section VILA of Form 2F requires the facility to sample (grab and flow-weighted samples) for
O&G,  BOD5, COD, TSS, TKN, nitrate  plus nitrite nitrogen,  total phosphorus, and pH.  These
parameters are to  be monitored by every facility applying for a storm water discharge permit,
regardless of the type of operations that exist at the site.  Sampling for additional parameters may
be required, depending on the type of facility applying for the permit or the pollutants expected to
be present in the discharge.  These additional requirements are discussed in detail below.

Section VII.B Parameters
Section VII-B of Form 2F requires the applicant to identify all pollutants that  are limited in  an
effluent guideline  to which  the facility is  subject,  as well as other  toxic and nonconventional
pollutants listed in the facility's NPDES permit for its process wastewater. EPA  interprets that for
pollutants listed in NPDES process wastewater permits, at a minimum, facilities must sample their
storm water discharge for those pollutants specifically  limited in their  process wastewater permit.
States can be more stringent, however, and  may interpret this  requirement to mean all pollutants
listed in the permit.  Once these parameters  are identified, the applicant will be required to sample
for these parameters by both grab and flow-weighted composite samples, except for the specified
pollutants which must be grab sampled only. Form 2F requires the applicant to  submit maximum
values. The average values column is not compulsory, but should be completed if data are available.
Applicable effluent guidelines  appear in 40 CFR Parts 405-471.  A listing of the  Subchapter
N—Effluent Guidelines and Standards by which the applicant may be regulated appears in Exhibit
4-1.  The applicant must refer to the effluent guidelines and standards for the particular industry, and
should determine which guidelines apply and which parameters should be listed in Section VII.B of
Form 2F.
                                            98

-------
                                                   CHAPTER 4 - ANALYTICAL CONSIDERATIONS
     EXHIBIT 4-1.    SUBCHAPTER N-EFFLUENT GUIDELINES AND STANDARDS
Part
Effluent Guidelines and Standards
Part
Effluent Guidelines and Standards
405


406

407


408


409


410


411


412


413


414


415


416


417


418


419


420


421


422


423


424


425


426


427


428


429


430
Dairy Products Processing Point Source
Category

Grain Mils Point Source Category

Canned and Preserved Fruits and
Vegetables Point Source Category

Canned and Preserved Seafood Point
Source Category

Sugar Processing Point Source Category


Textile Mills Point Source Category


Cement Manufacturing Point Source
Category

Feedlots Point Source Category


Electroplating Point Source Category


Organic Chemicals, Plastics, and Synthetic
Fibers Point Source Category

Inorganic Chemicals Manufacturing Point
Source Category

(Reserved)


Soap and Detergent Manufacturing Point
Source Category

Fertilizer Manufacturing Point Source
Category

Petroleum Refining Manufacturing Point
Source Category

Iron and Steel Manufacturing Point Source
Category

Nonferrous Metals Manufacturing Point
Source Category

Phosphate Manufacturing Point Source
Category

Steam Electric Power Generating Point
Source Category

Ferroalloy Manufacturing Point Source
Category

Leather Tanning and Finishing Point
Source Category

Glass Manufacturing Point Source Category


Asbestos Manufacturing Point Source
Category

Rubber Manufacturing Point Source
Category

Timber Products Processing Point Source
Category

Pulp, Paper and Paperboard Point Source
Category	
431


432

433


434


435


436


439


440


443


446


447


454


455


457


458


459


460


461


463


464


465


466


467


468


469


471
Builder's Paper and Board Mills Point
Source Category

Meat Products Point Source Category

Metal Finishing Point Source Category


Coal Mining Point Source Category


Oil and Gas Extraction Point Source
Category

Mineral Mining and Processing Point
Source Category

Pharmaceutical Manufacturing Point
Source Category

Ore Mining and Dressing Point Source
Category

Paving and Roofing Point Source
Category

Paint Formulating Point Source
Category

Ink Formulating Point Source Category


Gum and Wood Chemicals
Manufacturing Point Source Category

Pesticide Chemicals Manufacturing
Point Source Category

Explosives  Manufacturing Point Source
Category

Carbon Black Manufacturing Point
Source Category

Photographic Point Source Category


Hospital Point Source Category


Battery Manufacturing Point Source
Category

Plastics Molding and Forming Point
Source Category

Metal Molding and Casting Point
Source Category

Coil Coating Point Source Category


Porcelain Enameling Point Source
Category

Aluminum Forming Point Source
Category

Copper Forming Point Source  Category


Electrical and Electronic Components
Point Source Category

Nonferrous Metals Forming and Metal
Powders Point Source Category
                                             99

-------
CHAPTER 4 - ANALYTICAL CONSIDERATIONS
Section VII.C Parameters
Section VII.C requires the applicant to list, for each outfall, each pollutant described in 40 CFR Part
122, Appendix D, Tables II, HI, IV, and V (Tables 2F-2, 2F-3, and 2F-4 of application Form 2F)
that  it knows, or has reason  to believe, may  be present in the storm water  discharge.  These
pollutants consist of conventional and nonconventional pollutants, toxic pollutants and total phenol,
Gas  Chromatography/Mass Spectrometry (GC/MS) fraction volatile compounds, acid compounds,
base/neutral compounds, pesticides, and hazardous substances.  These tables are also provided on
the back of Form 2F.  Tables II and III of 40 CFR Part 122 Appendix D have been combined in
Table 2F-3 of application Form 2F.  Table IV of 40 CFR Part 122 Appendix D is listed as Table
2F-2 of application Form 2F and Table V of 40 CFR Part 122 Appendix D is listed as  Table 2F-4
of application Form 2F.  There are specific requirements associated with each table. If pollutants
in Table IV of 40 CFR Part 122 Appendix D (Table 2F-2 of application Form 2F), are directly or
indirectly limited by an effluent guideline limitation, the applicant must analyze for it and report the
data. For other pollutants listed in Table IV  of 40 CFR Part 122 Appendix D (Table 2F-2 of the
application form), the applicant must either report quantitative data, if available,  or briefly describe
the reasons the pollutant  is expected to be in the discharge.

For every pollutant in Tables II and III of 40 CFR Part 122 Appendix D (Table 2F-3 of application
Form 2F) expected to be discharged in concentrations of 10 parts per billion (ppb) or greater, the
applicant must submit quantitative data. For aerolein, acrylonitrile, 2,4-dinitrophenol, and 2-methyl-
4,6-dinitrophenol, the  applicant must submit quantitative data if any of these four pollutants  is
expected to be discharged in concentrations of 100 ppb or greater.  For every pollutant expected to
be discharged with a concentration less than 10  ppb (or 100 ppb for the four parameters mentioned
above), the applicant must either submit quantitative data or briefly explain why  the pollutant is
expected to be discharged.

For the parameters identified in Table V of 40 CFR Part 122 Appendix D (Table 2F-4 of application
Form 2F) that the applicant believes to be present in the discharge, no sampling  is required.  If
previous analyses of these parameters were conducted, the results must be reported. Otherwise, the
applicant is required to explain why these pollutants are believed to be present.
                                            100

-------
                                                  CHAPTER 4 - ANALYTICAL CONSIDERATIONS
Small Business Exemption
Small businesses are exempted  from the reporting requirements for the organic toxic pollutants
presented in 40 CFR Part 122,  Table II of Appendix D.  Applicants can claim a small business
exemption if:
    •  The facility is a coal mine and the probable annual production is less than 100,000 tons per
       year.   The applicant may submit past production data or estimate future production data
       instead of conducting  analyses for the organic toxic  pollutants  listed  in  Table 2F-3 of
       application Form 2F.
    •  The facility is not a coal mine, and the gross total annual sales for the most recent 3 years
       is, on average, less than $100,000 per year (reflected in second quarter 1980 dollars).  The
       applicant may submit sales data for those years instead of conducting analyses for the organic
       toxic pollutants listed in Table 2F-3 of application Form 2F.
Section VIII
Section VIII of Form 2F requires the applicant to provide biological toxicity testing data for storm
water discharges associated with industrial activity.  Applicants are required to perform biological
toxicity testing  for the storm water application  if the facility's NPDES permit for its process
wastewater lists  biological toxicity (EPA interprets "listed" as limited).  For example, if a facility's
NPDES process wastewater permit has an acute toxicity limit of a lethal concentration (LC^, equal
to 75 percent effluent using ceriodaphnia, then that facility must also test its storm water discharges
associated with industrial activity  and report the results of the tests in Section VIII of Form 2F.

Until whole effluent toxicity methods are promulgated by EPA in 40 CFR Part 136, toxicity testing
should be conducted using the most appropriate methods and species as determined by the permitting
authority.  In the  absence of State acute toxicity testing protocols,  EPA recommends using the
methods described in Methods for Measuring the Acute Toxicitv of Effluents and Receiving Waters
to Fresh Water and Marine Organisms.  EPA/600/4-90-027 (Rev. September 1991)

4.1.2  GROUP APPLICANTS
Industrial  facilities submitting a  group application must also provide sampling  data (from the
sampling subgroup) which is required to be submitted in Sections VII, VIII, and LX along with the
certification in Section X of Form 2F. At a minimum, these parameters include O&G, BOD5, COD,

                                            101

-------
CHAPTER 4 - ANALYTICAL CONSIDERATIONS
TSS, TKN, nitrate plus nitrite nitrogen, total phosphorous, and pH.  Furthermore, all pollutants
listed in an effluent guideline or limited in an NPDES permit applicable to the sampling facilities
within the group must be sampled, as well  as pollutants suspected of being present based  on
significant materials and industrial activities present onsite.

4.2  MUNICIPAL REQUIREMENTS
For Part 1 of the municipal permit application, municipalities must submit samples from the field
screening effort for pH, total chlorine, total copper, phenol, and detergents (or surfactants).  A
narrative description of the color, odor, turbidity, and presence of oil sheen and surface scum must
be included.  For Part 2 of the permit application, municipalities must provide quantitative data for
the organic pollutants listed in Table II of 40 CFR Part 122 Appendix D, and the pollutants listed
in 40 CFR Part 122, Appendix D, Table III, as well as some additional pollutants.  These pollutants
are listed  in Exhibit 4-2.

Furthermore, 40 CFR 122.26(d)(2)(iii)(A)(5) requires  that estimates be provided of the annual
pollutant  load of the  cumulative discharges to waters of the U.S. from all identified municipal
outfalls, and the event mean concentration of the cumulative discharges to waters of the U.S.  from
all identified municipal  outfalls  during  storm events for the parameters listed in Exhibit 4-2.
Estimates of the parameters must be accompanied by a description of the procedures for estimating
constituent loads and concentrations, including any modelling, data analysis, and calculation methods.
                                             102

-------
     CHAPTER 4 - ANALYTICAL CONSIDERATIONS
EXHIBIT 4-2. PARAMETERS WHICH MUST BE ANALYZED BY MUNICIPAL
APPLICANTS
Pollutants Contained in Table m of 40 CFR Part 122, Appendix D
Total antimony
Total arsenic
Total beryllium
Total cadmium
Total chromium
Total copper
Total lead
Total mercury
Total nickel
Total selenium
Total silver
Total thallium
Total zinc
Total cyanide
Total phenols
Pollutants Contained in Table H of 40 CFR Part 122, Appendix D
Acrolein
Acrylonitrile

Benzene
Bromofonn
Carbon Tetrachloride

Chlorobenzene
Chlorodibromo-
methane
Chloroethane

2-Chloroethylvinyl
ether
Chloroform
Dichlorobromo-
methane
1,1-dichloroemane

1,2-dichloroethane
1 , 1-dichloroethylene
1 ,2-dichloropropane

1 ,3-dichloropropylene
Ethylbenzene

Metbyl bromide
Methyl chloride
Methylene chloride
U,2,2-
tetrachloroethane
Tetrachloroethyleue
Toluene
1,2-trans-
dichloroethylene
1 , 1 , 1 -trichloroethane
1 , 1 ,2-trichloroethane
Trichloroethylene

Vinyl chloride
2-chlorophenol

2,4-dichlorophenol

2,4-dimethylphenol

4,6-dinitro-o-cresol
2,4-dinitrophenol

2-nitrophenol

4-nitrophenol
p-chloro-m-cresol
Pentachlorophenol

Phenol
2,4,6-
trichlorophenol
Acenaphthene
Acenaphthylene
Anthracene
Benzidine

Benzo(a)anthracene
Benzo(a)pyreDe
3,4-benzofluoranthene

Benzo(ghi)perylene
Benzo(k)fluoranthene
Bis<2-
chloroethoxy)methane
Bis(2-chloroemyl)emer
Bis(2-
chloroisopropyl)ether
Bis(2-ethylhexyl)phthalate

4-bromophenyl phenyl
ether
Butylbenzyl phthalate
2-chloronaphthalene

4-chlorophenyl phenyl
ether
Chrysene
Dibenzo(a4i)anthracene
1 ,2-dichlorobenzene

1 ,3-dichlorobenzene
1 ,4-dichlorobenzene

3 3-dichlorobenzidine
Diethyl phthalate
Dimethyl phthalate
Di-n-butyl phthalate

2,4-dinitrotoluene
2,6-dinitrotoluene
Di-n-octyl phthalate

1 ,2-diphenylhydrazine
Fluoranmene
Fluorene

Hexachlorobenzene
Hexachlorobutadiene

Hexachlorocyclopen-
tadiene
Hexachloroemane

Indeno(l ,2,3-cd)pyrene
Isophorone

Naphthalene

Nitrobenzene
N-nitrosodimethylamine
N-nitrosodi-n-
propylamine
N-nitrosodiphenylamine
Phenanthrene

Pyrene
1 ,2,4-trichlorobenzene
Aldrin
Alpha-BHC

Beta-BHC
Gamma-BHC
Delta-BHC

Chlordane
4,4'-DDT
4,4'-DDE

4,4'-DDD
Dieldrin

Alpha-endosulfan

Beta-endosulfen

Endosulfen sulfate
Endrin

Endrin aldehyde

Heptachlor
HeptachJor epoxide
PCB-1242

PCB-1254
PCB-1221

PCB-1232
PCB-1248
PCB-1260
PCB-1016

Toxaphene
Additional Pollutants Which Must be Analyzed
TSS O&G
TDS Fecal colifonn
COD Fecal streptococcus
BOD, pH
Total residual chlorine
TKN
Nitrate plus nitrite nitrogen
Total and dissolved phosphorus


Source: 40 CFR Part 122, Appendix D
103

-------
                                                      CHAPTER 5 - FLEXIBILITY IN SAMPLING
5.  FLEXIBILITY IN SAMPLING
The requirements for storm water sampling for permit applications offer some flexibility by the
permitting authority.  The areas of flexibility are discussed below.

5.1  PROTOCOL MODIFICATIONS
The permitting authority may allow sampling protocol modifications for specific requirements on a
case-by-case  basis.   For example, the  permitting  authority may  accept  application forms  with
incomplete sampling data if there was no rainfall at the applicant's  facility prior to the submission
deadline.  However, the permitting authority will require that sampling data be submitted as  soon
as possible.  The reason  for not submitting data must be  certified  by a corporate official (for
industrial facilities) or the principal executive officer or ranking official (for municipalities).

Another area where permitting authorities may allow flexibility in storm water sampling is acceptance
of quantitative data from a storm event that does not meet the representative rainfall criteria of within
50 percent of the volume and duration for the average storm event for the area.  The permitting
authority may decide that the discharge data provided is better than no data at all.

In addition, the permitting authority may establish appropriate site-specific sampling procedures or
requirements, including sampling locations; the season in which  the sampling takes place; the
minimum duration between the previous  measurable storm event and the storm event sampled; the
minimum or maximum level of precipitation required for an appropriate storm event; the form of
precipitation sampled (snow  melt or rainfall); protocols for collecting samples under 40 CFR Part
136; and additional time for submitting data on a case-by-case basis.  The permitting authority should
be  contacted  for preapproval of  any necessary protocol modifications.  In  the case of group
applications, EPA Headquarters should be contacted.

5.2  PETITION FOR SUBSTITUTING SUBSTANTIALLY IDENTICAL EFFLUENTS
As described  at 40 CFR 122.21(g)(7), when an industrial  applicant has two or more outfalls  with
substantially identical effluents,  the permitting authority may allow the applicant to  test only one
outfall and to  report that the quantitative data also apply to the substantially identical outfalls. In the
case of group applications, the petition must be submitted to EPA Headquarters.
                                           105

-------
CHAPTER 5 - FLEXEBIUTY IN SAMPLING
For facilities seeking to demonstrate that storm water outfalls are substantially identical, a variety
of methods can be used as determined by the permitting authority.  Three possible petition options
are discussed here:   (1) submission of a narrative description and a site map; (2) submission of
matrices; or (3) submission of model matrices. Detailed guidance on each of the three options for
demonstrating substantially identical outfalls is provided below.   An owner/operator certification
should be submitted with each option. See Section 5.2.3 for an example of this certification.

5.2.1  OPTION ONE:  NARRATIVE DESCRIPTION/SITE MAP
Facilities demonstrating that storm water outfalls are substantially identical may submit a narrative
description of the facility  and a site map to the permitting authority .  The narrative portion must
include a description of why the outfalls are substantially identical.  Petitioners may demonstrate that
these outfalls contain storm water discharges associated with:

    •  Substantially identical industrial activities and processes;
    •  Substantially  identical  significant  materials that may be  exposed to storm water
       [including,  but not  limited  to, raw  materials, fuels, materials such as  solvents,
       detergents,  and plastic pellets; finished materials  such as metallic  products;  raw
       materials used in food processing or production; hazardous substances designated
       under Section 101(14) of the Comprehensive Environmental Response, Compensation,
       and Liability Act (CERCLA); any chemical the facility is required to report pursuant
       to Section 313 of Title HI of the  Superfund Amendments and Reauthorization Act
       (SARA); fertilizers; pesticides; and waste products such as ashes, slag, and sludge that
       have the potential  to  be released with  storm water discharges as  per 40 CFR
       122.26(b)(12)];
    •  Substantially  identical  storm water management practices (such as  retention ponds,
       enclosed  areas,  diversion dikes,  gutters, and swales)  and material management
       practices (such as protective coverings and secondary containment);  and
    •  Substantially  identical  flows, as determined by the estimated runoff coefficient and
       approximate drainage area at each outfall.

The  site map should include  an  indication of the facility's topography; each of the drainage and
discharge structures; the drainage area of each storm water outfall; paved areas and buildings within
the drainage area for each storm water outfall; all past or present areas used for outdoor storage or
disposal of significant materials; identification of the significant materials in each drainage area; and
identification of each existing structural control measures used to reduce pollutants in storm water

                                             106

-------
                                                       CHAPTER 5 - FLEXIBILITY IN SAMPLING
runoff, materials loading and access areas, and areas where pesticides, herbicides, soil conditioners,
and fertilizers are applied.

Exhibit  5-1  offers  an example  of a  narrative description/site  map  petition that sufficiently
demonstrates identical outfalls.  A demonstration of how to determine runoff coefficient estimates
was presented in Section 3.2.2.  Exhibit 5-2 presents an example of a site map to be included with
the narrative description.

5.2.2  OPTION TWO:  USE OF MATRICES TO  INDICATE IDENTICAL OUTFALLS
Facilities attempting to demonstrate that storm water outfalls are substantially identical may submit
matrices and an  owner/operator certification describing specific information associated with each
outfall to the permitting authority. Matrix information is required only  for those outfalls that the
permit applicant  is attempting to demonstrate are identical, not for all outfalls.  Petitioners must
demonstrate, using the matrices, that the outfalls have storm water discharges that meet the criteria
listed in  Section 5.2.1. Refer to Exhibit 5-3 for examples of matrices that demonstrate substantially
identical outfalls  and Section 3.2.2 for guidance on determining runoff coefficient estimates.

5.2.3  OPTION THREE:  MODEL MATRICES
Facilities attempting to demonstrate that storm water outfalls are substantially identical may submit
model matrices  and an owner/operator certification to the permitting authority.  This  option  is
particularly appropriate for facilities with a large number of storm water outfalls and the potential
for numerous groupings of identical outfalls.   In addition, this option may be useful  in  group
applications that have a large sampling subgroup.

Model matrices should contain information for one grouping of substantially identical outfalls. For
example, if a facility has 150 outfalls and several groupings of identical outfalls, the facility would
choose one of the groupings of identical outfalls to provide information in  the model matrices.  The
petitioner must demonstrate, using these matrices, that all outfalls within this grouping have storm
water discharges  that meet the criteria listed in Section 5.2.1.

The facility should provide an owner  certification that all other groupings of outfalls have been
examined and certified as  substantially identical outfalls according to the  criteria established  in the
                                            107

-------
CHAPTER 5 - FLEXIBILITY IN SAMPLING
    EXHIBIT 5-1.   PETITION TO SAMPLE SUBSTANTIALLY IDENTICAL OUTFALLS
                    (NARRATIVE DESCRIPTION/SITE MAP)
                                         Examples

  I.   The Pepper Company of Philadelphia, Pennsylvania, is primarily engaged in
      manufacturing paperboard, including paperboard coated on the paperboard machine
      (from wood pulp and other fiber pulp).  This establishment is classified under SIC
      code 2631. Pursuant to the November 16, 1990, NPDES storm water permit
      application regulations, this facility is considered to be  "engaging in industrial
      activity" for the purposes of storm water permit application requirements in 40 CFR
      122.26(b)(14)(i) and (ii).

  II.  "When an applicant has two or more outfalls with substantially identical effluents,
      the Director may allow the applicant to test only one outfall and report that the
      quantitative data also apply to the substantially identical outfalls."
      [40 CFR 122.21(g)(7)]

      In accordance with 40 CFR 122.21 (g)(7) of the NPDES regulations, The Pepper
      Company hereby petitions the State of Pennsylvania (the permitting authority) for
      approval to sample certain representative storm water outfalls in groupings of storm
      water outfalls that are substantially identical.  The Pepper Company will demonstrate
      that of the ten (10) outfalls discharging storm water from our paperboard
      manufacturing plant, there are two pairs of substantially identical outfalls. Outfalls 3
      and 4 are substantially identical and should be grouped  together. Outfalls 8 and 9
      are substantially identical and should be grouped together.  Outfalls 1, 2, 5, 6, 7,
      and 10 have distinct characteristics and, therefore, will  not be grouped together with
      other outfalls  for the purposes of storm water discharge sampling.


  III.  The Pepper Company will demonstrate that the substantially identical outfalls that
      have been grouped together contain storm water discharges  associated with:  (1)
      substantially identical industrial activities and processes that are occurring outdoors;
      (2) substantially identical significant materials (including raw materials, fuels,
      finished materials, waste products, and material handling equipment) that may be
      exposed to storm water; (3) substantially identical material management practices
      (such as runoff diversions, gutters and swales,  protective coverings, and structural
      enclosures); and (4) substantially identical  flows, as determined by the estimated
      runoff coefficient and  approximate drainage area at each outfall.
                                            108

-------
                                                    CHAPTER 5 - FLEXIBILITY IN SAMPLING
  EXHIBIT 5-1.   PETITION TO SAMPLE SUBSTANTIALLY IDENTICAL OUTFALLS
                  (NARRATIVE DESCRIPTION/SITE MAP) (Continued)
1.  Industrial Activities

    A.   Description of Industrial Activities at the Pepper Company

    The Pepper Company receives wastepaper in bales. This baled wastepaper is sent
    through a hydropulper and converted to pulp.  The fiber material is concentrated,
    stored, and then drawn through refiners to die paper machines.  Wires, plastics, and
    miscellaneous material are removed during the pulping.

    Three systems are used to produce top liner, back paper, and filler. The highest
    quality fiber is used for the top liner, the medium quality is used for the back paper,
    and the poorest quality is used for the filler paper.  Wireforming or conventional
    boxboard processes are employed to produce clay-coated boxboard, using a water-
    based clay-coating material.  Additional materials may be used as binders. These are
    stored indoors and  are not exposed to precipitation. Ammonia is used in the clay-
    coating process. Off-grade fiber and trim material are ground up and returned to the
    liquid process stream. Slime control agents, consisting of bactericides, are used in
    association with this process. These agents  are organic  materials used to prevent
    souring of mill  operations. They are received in drums  and stored indoors.  Empty
    drums are returned to the supplier to reuse.  In addition, the Pepper Company
    operates an onsite landfill for the disposal of miscellaneous  waste materials removed
    during pulping and paper cuttings operations.

    B.   Demonstration of Why Outfalls Are Substantially Identical in Terms of
         Industrial Activities Conducted Outdoors.

    Outfalls 3 and 4

    Outfalls 3 and 4 are substantially identical in terms of industrial activities conducted
    outdoors. Bom outfalls contain storm water discharges associated with  the outdoor
    storage of baled wastepaper.  The  wastepaper, which consists of old corrugated
    containers, mixed paper, and other types of wastepaper, is received weekly and
    stored for up to 3 weeks in Storage Areas #1 and #2.  These uncovered storage areas
    are enclosed by chain-link fencing.
    Outfalls 8 and 9

    Outfalls 8 and 9 drain storm  water runoff from areas where  all industrial activities
    occur indoors.   The industrial activities occurring under roof cover at these two
    outfalls include  hydropulping, storage of concentrated fiber  material, refining, and
    paperboard production.  These industrial processes have no  potential for contact with
    precipitation.
                                         109

-------
CHAPTER 5 - FLEXIBILITY IN SAMPLING
    EXHIBIT 5-1.  PETITION TO SAMPLE SUBSTANTIALLY IDENTICAL OUTFALLS
                   (NARRATIVE DESCRIPTION/SITE MAP) (Continued)
  2.   Significant Materials

      A.  Description of Significant Materials at the Pepper Company

      The significant materials listed below are used by the Pepper Company to
      manufacture paperboard.  These materials are stored indoors, unless otherwise
      indicated.

      (i) Raw materials, including baled wastepaper (off-spec damaged paper stock or
      recycled paper) [wastepaper is stored outdoors at Storage Areas #1 and #2];
      clays,  ammonias, sizings, and slime control agents (chlorine dioxide); caustic;
      ammonia, which is stored in two tanks. [See Storage Area #3].

      (ii) Waste Materials, including miscellaneous materials removed during pulping and
      paper  cuttings (such as staples,  rubber bands, styrofoam, etc.).   These waste
      materials are stored indoors in open dumpsters.   However, prior to disposing of the
      waste  in the onsite  landfill, these dumpsters are  moved outdoors where they are
      potentially exposed to precipitation for 12 hours or less. [See Storage Area #3].

      (iii) Finished Products, including paperboard and molded fiber products.  These are
      always stored indoors.

      (iv) Others, including wood pallets (which are used to transport and haul raw
      materials, waste materials, and  finished products) are stored both indoors and
      outdoors.  [See Storage Area #3].  The Pepper Company has an above-ground fuel
      tank with a pump. [See Storage Area
      B.  Demonstration of Why Outfalls are Substantially Identical in Terms of
          Significant Materials that Potentially May be Exposed to Storm Water

      Outfalls 3 and 4

      Outfalls 3 and 4 are substantially identical in terms of significant materials that may
      be exposed to storm water.  Bom outfalls contain storm water discharges associated
      with the outdoor storage of baled wastepaper.  The wastepaper, which consists of old
      corrugated containers, mixed paper, and other types of wastepaper, is received
      weekly and stored for up to  3 weeks in Storage Areas #1 and #2.  These uncovered
      storage areas are enclosed by chain-link fencing.

      Outfalls 8 and 9

      Outfalls 8 and 9 are substantially identical in terms of significant materials.  Both
      outfalls contain  storm water  runoff from areas that have  no significant materials
      potentially exposed to storm water.  All industrial activities occurring in the areas
      drained by Outfalls 8 and 9 occur completely  indoors.
                                           110

-------
                                                    CHAPTER 5 - FLEXIBILITY IN SAMPLING
  EXHIBIT 5-1.  PETITION TO SAMPLE SUBSTANTIALLY IDENTICAL OUTFALLS
                 (NARRATIVE DESCRIPTION/SITE MAP) (Continued)
3.  Material Management Practices

    A.   Description of Material Management Practices at the Pepper Company

    The Pepper Company uses a wide range of storm water management practices and
    material management practices to limit the contact of significant materials with
    precipitation.  Non-structural storm water management practices include employee
    training, spill reporting and clean-up, and spill prevention techniques.  Structural
    storm water management practices include:

    (i) Diversion Devices (both above-ground trenches and subterranean drains) are used
    to divert surface water from entering a potentially contaminated area.

    (ii) Gutters/Swales (constructed of concrete or grass) channel storm water runoff to
    drainage systems leading to separate storm sewers.

    (iv) Overland Flow (which is the flow of storm water over vegetative areas prior to
    entrance into a storm water conveyance) allows much of the storm water to infiltrate
    into the ground.  The remainder is naturally filtered prior to reaching the storm
    water conveyance.  This is not considered  sheet flow since natural drainage channels
    may be carved out during a heavy storm event.

    B.   Demonstration of Why Outfalls Are Substantially Identical in Terms of
         Storm Water Management Practices Used

    Outfalls 3 and 4

    Outfalls 3 and 4 are substantially identical  in terms of storm water management
    practices used.  Both outfalls contain storm water discharges associated with the
    outdoor storage of baled wastepaper, located in Storage Areas #1 and #2.  Concrete
    gutters at both sites channel storm water away from the storage areas down to the
    respective outfalls.

    Outfalls 8 and 9

    Outfalls 8 and 9 are substantially identical in terms of storm water management
    practices used.  Both outfalls contain storm water runoff from areas that have no.
    significant materials potentially exposed to storm water.  All industrial activities
    occurring in the areas drained by Outfalls 8 and 9 occur completely indoors.  Both
    outfalls receive overland flow  storm water.  From roof drains, the storm water in
    both drainage areas is then conveyed over similarly graded vegetative  areas prior to
    entrance into the respective outfalls.
                                         Ill

-------
CHAPTER 5 - FLEXranjTY IN SAMPLING
    EXHIBIT 5-1.   PETITION TO SAMPLE SUBSTANTIALLY IDENTICAL OUTFALLS
                   (NARRATIVE DESCRIPTION/SITE MAP) (Continued)
  4.  Flow Characteristics

     A.  Demonstration of Why Outfalls Are Substantially Identical in Terms of
          Flow, as Determined by The Estimated Runoff Coefficient and
          Approximate Drainage Area at Each Outfall

     Outfalls 3 and 4

     Outfalls 3 and 4 are substantially identical in terms of flow. Both drainage areas
     have a 2 to 7 percent grade and contain fine textured soil (greater than 40 percent
     clay) with a vegetative cover.  The estimated runoff coefficient for both outfalls is
     .2.  The approximate drainage area for each outfall is similar.  Outfall  3 has an
     approximate drainage area of 3,500 square feet.  Outfall 4 has an approximate
     drainage area of 2,900 square feet.

     Outfalls 8 and 9

     Outfalls 8 and 9 are substantially identical in terms of flow. Both drainage areas
     have a 2 to 7 percent grade and contain fine textured soil (greater than 40 percent
     clay) with a vegetative cover.  The estimated runoff coefficient for both outfalls is
     .2.  The approximate drainage area for each outfall is similar.  Outfall  8 has an
     approximate drainage area of 7,600 square feet.  Outfall 9 has an approximate
     drainage area of 8,700 square feet.
                                           112

-------
                   CHAPTER 5 - FLEXIBILITY IN SAMPLING
EXHIBIT 5-2.   SITE MAP
          113

-------
CHAPTER 5 - FLEXIBILITY IN SAMPLING
      EXHIBIT 5.3 MATRICES DEMONSTRATING SUBSTANTIALLY IDENTICAL
                   OUTFALLS
                               Industrial Activities
OUTFALL
3
4
A
X
X
B
—
—
C
—
—
D
X
X
E
—
—
             8
        Key:

        A  =  Outdoor storage of raw materials and material-handling equipment
        B  =  Fueling
        C  =  Waste materials storage (dumpster)
        D  =  Loading/unloading of raw materials, intermediate products, and final
               products
        E  =  Landfill activity
                  Significant Materials That May Be Exposed to Storm Water
OUTFALL
3
4
A
-
—
B
—
—
C
—
—
D
—
—
E " '
X
X
F
—
—
             8
        Key:

        A  =  Outdoor ammonia tank
        B  =  Wood pallets
        C  =  Above ground gas tank
        D  =  Waste materials
        E  =  Baled wastepaper
        F  =  Finished products
                                         114

-------
                                           CHAPTER 5 - FLEXIBILITY IN SAMPLING
EXHIBIT 5.3   MATRICES DEMONSTRATING SUBSTANTIALLY IDENTICAL
              OUTFALLS (Continued)
                   Storm Water Management Practices
OUTFALL
3
4
A
—
—
B
X
X
c
—
—
8
9
—
—
—
~
X
X
               Key:

               A   =
               B   =
               C   =
Runoff diversions
Gutters/swales
Overland flow (not sheet flow; flow through
vegetative areas)
                          Flow Characteristics
OUTFALL
3
4
A
0.2
0.2
B
3,500
2,900
8
9
0.2
0.2
7,600
8,700
               Key:

               A   =
               B   =
Estimated runoff coefficient
Approximate drainage area of outfall (square feet)
                                  115

-------
CHAPTER 5 - FLEXIBILITY IN SAMPLING
model matrices described in Exhibit 5-3.  The owner/operator who signs documents in this section
should include the following certification:
       "I certify under penalty of law that this document and all attachments were prepared
       under my direction or supervision in accordance with a system designed to assure that
       qualified personnel properly gather and evaluate the information submitted.  Based on
       my inquiry of the person or persons who manage the system, or those persons directly
       responsible for gathering the information, the information submitted is, to the best of
       my knowledge and belief, true, accurate and complete.  I am aware that there are
       significant penalties for submitting false information, including the possibility of fine
       and imprisonment for knowing violations" [as per 40 CFR 122.22(d)].
5.3  ALTERNATE 40 CFR PART 136 METHOD

As required in 40 CFR 136.4, the applicant must request the approval of an alternate test procedure
in writing (in triplicate)  prior to testing.    The request must be  submitted  to the Regional
Administrator through the Director of the State agency responsible for issuing NPDES permits.  The
applicant must:
    • Provide the name and address of the responsible person or firm making the discharge (if not
      the applicant), the  applicable identification number of the existing or pending permit, the
      issuing agency, the type of permit for which the alternate test procedure is requested, and the
      discharge serial number;

    • Identify the pollutant or parameter for which approval of an alternate testing procedure is
      being requested;

    • Provide justification for using testing procedures other than those specified in 40 CFR Part
      136;

    • Provide a detailed description of the proposed  alternate test procedure,  together  with
      references to published  studies of the applicability  of the  alternate test procedure to the
      effluents in question;

    • Provide comparability data (for applicants applying for nation wide approval of an alternative
      test procedures).
The  permitting authority will notify the applicant within 90 days regarding the approval of the

alternate method.
                                            116

-------
                                                     CHAPTER 5 - FLEXIBILITY IN SAMPLING
5.4  LACK OF METHOD IN 40 CFR PART 136
If a specific pollutant that must be tested does not have a corresponding analytical method listed in
40 CFR Part 136, the applicant must submit information on an appropriate method to be used. The
permitting authority must approve its use prior to collection and analysis  of sampling data.  The
laboratory should be consulted for suggestions and information about analytical methods that can be
used. All information justifying the  alternative method should be sent to the permitting authority
prior to use.
                                          117

-------
                                                           CHAPTER 6 - HEALTH AND SAFETY
6.  HEALTH AND SAFETY
Storm water sampling activities  may  occur when the sampling environment and/or storm water
discharges create hazardous conditions.  Hazardous conditions associated with sampling include:

    •  Hazardous weather conditions (e.g., wind, lightning, flooding, etc.)
    •  Sampling in confined spaces (e.g., manholes)
    •  Hazards associated with chemicals
    •  Biological hazards (e.g., rodents and snakes)
    •  Physical hazards (e.g., traffic, falling objects, sharp edges, slippery footing, and the potential
       for lifting injuries from opening or removing access panels and manhole covers, etc.)

It is essential that sampling personnel be aware of these hazards.   Sampling personnel should be
trained to evaluate potentially hazardous situations and develop ways for handling them.  Since
sampling hazards can be life threatening, safety must be the highest priority for all personnel.  This
chapter outlines general health and safety issues and concerns. Additional references discussed below
should be consulted for more specific guidance to avoid adverse health and safety situations.

6.1  GENERAL TRAINING REQUIREMENTS
Preparation  and training of all  sampling  personnel  should be completed before beginning any
sampling task.   Extreme care should be taken to allow  for safety precautions  including proper
equipment and appropriate operational techniques, sufficient time to accomplish the task, training on
potential hazards, and emergency procedures.   EPA's  Order  1440.2 sets  out the  policy,
responsibilities,  and  mandatory  requirements  for the safety  of personnel who are involved in
sampling activities.  This order,  which is found within the EPA NPDES Compliance Monitoring
Inspector Training: Sampling manual, provides further guidance to applicants' storm water sampling
personnel.   Basic emergency precautions  include having access to both local emergency phone
numbers and communication equipment  (i.e., phones or radios), and ensuring that personnel are
trained in first aid and  carry first aid equipment.
                                           119

-------
CHAPTER 6 - HEALTH AND SAFETY
6.2 NECESSARY SAFETY EQUIPMENT
Exhibit 6-1 contains a  list of safety equipment that  may be  appropriate depending on  the
characteristics of the sampling site.
EXHIBIT 6-1. LIST OF SAFETY EQUIPMENT |
Flashlight
Meters (for oxygen, explosivity, toxic gases)
Ladder
Safety harness
Hard hat
Safety goggles
Coveralls
Respirator
Reflective vests
18-inch traffic cones
Insect/rodent repellant
Ventilation equipment
50 feet of 1/2-inch nylon rope
Safety shoes
Rain wear
Gloves (rubber)
First aid kit
Self-contained breathing apparatus
Source: Adapted from NPDES Compliance Monitoring Inspector Training: Sampling,
U.S. EPA, August 1990.
6.3 HAZARDOUS WEATHER CONDITIONS
Common sense should dictate whether sampling be conducted during adverse weather conditions.
No sampling personnel should place themselves in danger during high winds, lightning storms, or
flooding conditions which might be unsafe. Under extreme conditions, a less hazardous storm event
should be sampled.

6.4 SAMPLING IN CONFINED SPACES
Confined spaces encountered by  storm water  sampling personnel typically include manholes and
deep, unventilated ditches.  A confined  space is generally defined as a space that  is somewhat
enclosed with limited access and inadequate ventilation.
                                        120

-------
                                                          CHAPTER 6 - HEALTH AND SAFETY
The National Institute of Occupational Safety and Health (NIOSH) has developed a manual entitled
"Working in Confined  Spaces"  which should be consulted prior to confined space entry.  Also,
several States have developed specific procedures which should also be consulted.  Unless they have
been  trained  for  confined  space  entry, sampling  personnel  should avoid  entry  under all
circumstances.

6.4.1 HAZARDOUS CONDITIONS IN CONFINED SPACES
Confined spaces pose a safety threat to sampling personnel because of low oxygen, explosivity, and
toxic gases.  When entering a confined space, a qualified person should ensure that the atmosphere
is safe by sampling to test for oxygen levels, potential flammable hazards, and toxic materials known
or suspected to be present.  If atmospheric conditions are detected, the confined space should be
ventilated or sampling personnel should use a self-contained air supply and wear a life line.  At least
one person  should remain outside of the confined space in the event that problems arise.  If
atmospheric testing has not been properly conducted, the confined space should not be entered.
Manholes can also pose a threat to safety because of the small confined area, slippery surfaces, sharp
objects, unsafe ladders, etc.

6.4.2 SPECIAL TRAINING  REQUIREMENTS
Personnel should not enter into a confined space unless trained in confined space entry techniques.
Such training covers hazard recognition, the use of respiratory equipment and atmospheric testing
devices, use of special equipment and tools, and emergency and rescue procedures.  In addition, at
least one member of the sampling crew should be certified in basic  first aid and Cardiopulmonary
Resuscitation (CPR).  Sampling personnel should,  on an annual basis, practice confined  space
rescues.

6.4.3 PERMIT SYSTEM
If entry into a confined space is necessary, an entry permit system should be  developed which
includes a written procedure. This permit should include, at a minimum:

    •  Description of type of work to be done
    •  Hazards that may be encountered
                                           121

-------
CHAPTER 6 - HEALTH AND SAFETY
    • Location and description of the confined space
    • Information on atmospheric conditions at confined space
    • Personnel training and emergency procedures
    • Names of sampling personnel.
The manual developed by NIOSH discusses this permit system in more detail.  Furthermore, the
Occupational Safety and Health Administration  (OSHA) proposed a rule on June 5, 1989 (54 FR
24080) that would implement a permit system.  The rule is expected to be finalized and published
late in 1992.

6.5 CHEMICAL HAZARDS
Sampling personnel can also be at risk of exposure to hazardous chemicals—either chemicals in the
actual storm water discharge or the chemicals that have been  placed in the  sample collection
containers for sample preservation.  Therefore,  direct contact with the preservatives and the storm
water (if hazardous chemicals are suspected to be present) should be avoided.  Sampling personnel
should wear gloves and safety glasses to avoid skin and eye exposure to harmful chemicals.
Sampling personnel should be trained to avoid exposure and instructed as to what to do if exposure
occurs (e.g., flush the eyes, rinse the skin, ventilate the area, etc.).

6.6 BIOLOGICAL HAZARDS
Storm water sampling personnel may also encounter biological hazards such as rodents, snakes, and
insects.  The sampling crew should  remain alert to these hazards.  As mentioned in Section 6.2,
necessary sampling equipment, for certain locations, should include insect/rodent repellant and a first
aid kit.

6.7 PHYSICAL HAZARDS
The sampling crew should be aware  of a number of physical hazards that could  cause accidents at
the sampling site.  These  hazards include traffic hazards, sharp  edges, falling objects, slippery
footing, and lifting injuries from removing manhole covers. Sampling personnel should pay close
attention in order to prevent these safety hazards at all times.
                                           122

-------
                                                           CHAPTER 6 - HEALTH AND SAFETY
If the sample point is in a manhole, a street gutter, or ditch near the street, particular attention must
be given to marking off the work area to warn oncoming traffic  of the presence of the sampling
crew.  Traffic cones, warning signs, and barricades should be placed in appropriate places around
the sampling point.
                                           123

-------
                         TECHNICAL APPENDIX A
TECHNICAL APPENDIX A




   FORMS 2F AND 1

-------
                                                                                       TECHNICAL APPENDIX A
PteaM print or type in the unahededafeM only
                                         EPA ID Numb*  (copy from Mm I of form
                                                                              Form Approved. OMB No. 20400066

                                                                                            Approval expire   5-31-92
  Form

  2F
 NPOES
    S-/EPA
                         •a cnvironmantai riuieumn Agency
                          Weahington, DC 20460
Application for Permit to Discharge Storm Water
  Discharges Associated with Industrial Activity
   Public
   Marching
                                              Pap
                                                                 i Act Notice
           burdan tor tNe application it estimated to avaraga 28* noun par
            data aouroM. gatharinB and maintaining lha data naadad, and
                                          including tima for reviewing instruction*,
                                     and raviawing ma oollactkx) of information. Sand
   oommanta regarding the burdan estimate, any othar aapaet of thia collection of information, or suggestion* for improving this form, including
   auggaatJona which may IncraaM or raduca thia burdan to: CMaf. Information Policy Branch, PM-223, U.S. Environmantal Protection Agency, 401
   M S, SW, Washington, DC 20460. or Oiraetor. Office of Information and Hagulatory Affair*, Otflca of Managamant and Budget, Washington, DC
   20503.
 I. Outfall Location
   For Mch outfall. list tha latitude and longitude of Ha toeation to ttar>aara*t15 aaconda and tha name of the receiving water.
     A. Outfall Number

           flltt)
                          B. Latitude
             C. Longitude
 0. Receiving Watar

	(name)
 II. Improvt     	
   A.  Ara you now raquirad by any Fadaral, Stata, or local authority to maat any tmplamantalton aohadula tor tha construction, upgrading or
      operation of waatawatar traatmant aquipmant or praottOM or any othar environmental programa which may affact tha diachargM described
      in thia application? Thia inductaa, but la not limited to, permit oondlUona. adminlatrativa or antoroamant orders, anforoamant complianca
      achadula (attan, atlpulatlona, court ordara, and grant or loan condittona.
    1. Uwittficatlon of CondHtona,
                                   ^Affactad Outfall*
                                 numbar

                                                                   3.BrtafDaaortpUonofPro)act
                                                                    4. Final

                                                                Compllanca Data
                                                                                                           a. rag,   b.prqi.
You may attach additional sheet* describing any additional watar pollution  (or othar environmental protect* which may affect
diachargM) you now have under way or which you plan. Indicate whether each program la now under way or planned, and indicate
      actual or plan
                                                                                                                   your
                                                                                                                   your
 HI. Site Dralnaoa M
   Attach a aMa map ahowing topography (or indicating tha outJina of drainage area* aarvad by the outfall(a) covered in the application if *
   topographic map ia unavailable) depicting the facility Including: each of It* intake and diaoharga atructurM; tha drainage area of each norm
   water outfall; paved area* and building* within tha drainage area of each etorm watar outfall, each known pact or praaant area* uaed for outdoor
   storage or diapoaal of aignrRcant material*, each axiattng atructural control measure to reduce pollutant* in storm watar runoff, material* loading
   and aooasa area*, area* where pesticide*, herbtoidM, eoH conditioner* and fertilizer* are applied; each of It* hazardoue waste treatment.
   storage or di*po»al unit* (including each anta not required to have a RCRA permit which t» uaad for accumulating hazardou* waste under 40
   CFR 262.34); each well where fluid* from tha facility are injected underground; aprlnga, and othar turface watar bodiM which receive storm
   water discharges from tha facility.	
EPA Form 3510-2F (Rev. 1-82)
                                                  Page 1 of 3
                                                             Continue on Page 2
                                                         A-l

-------
 TECHNICAL APPENDIX A
Continued from tha Front
 IV. Narrative Dascrlptlon of Pnllirtant Sou
      For aach outfall, provida an aatimata of tha «IM (Inctuda unta) of imparvtou*
      tha outfall, ami an aatiTMla of tha total *urfaoaaraaoVainad by tha outfall.
                                                                               (Including pavad araaa and building roof*) draiMd to
 Outfall

 Mumb«r
         Araa of Imparvioua Surfaoa
                torovidt unit*}
                                         Total Araa Drainad
                                                               Outfall
                                                ATM of Imparvioua Surfaoa

                                                             tfflftl)
                                                      Total ATM Orainad
                                                        loravid* tinftnl
   B.  Provio*anarratrvada*criptionof*Wificammatan^thataracun«ntryorlnto
       mannar to allow axpoaura to •torm watar; mathod of traatmant, atoraga, or diapoaal; pact and praaant matariala managamant practica*
       amployad to minimiza contact by thaaa matariala wrth alorm »»atar runoff; matariala loading ana aooasa i
       andtraquancy in which paaticidaa. hafbicidaa. aoil conditionara, and farUlteara am appllad.
                                                                                              i VMS; and tha location, mannar,
   C.  For aach outfall, provhja lha location and a daacription of axiating atructural and nonattuctural control maaauraa to raduoa pollutant* In
       *tormwawrunof?;aixJadaaeriptkxioftriatraatrnam«hai	
                                                                        a. Including tha aohadida and typa of maintananca for control
  Outfall

 Nu
                                                                                                               Liat Coda* from
  V. Nonstormwater Discharge*
   A.  I eartify undar panatty of law that tha outfallM covarad by thia application hava baan taatad or avaluatad for tha praaanoa of nonatormwatar
       dlacharqaa, and that all nonatormwatar dtacnarga* from thaaa outfall(a) am idantifiad hi arthar an aooompanying Form 2C or Form 2E
       application fof tha out
      andOfficialTitoijiypa
N«m«
or print;
Sgnatur*
Oat* Signed
   a  Provide a dMCription of tha mathod uaad, tha data of any taatlng, and tha onatta dralnaga point* that wara diractty obaarvad during a ta«t
  VI. Slanffleant Leaks or Sofllt
    Provida axlstlng InforrraUon ragardlng tha hMory of *ignrficant taaka or *plU* of toxte or hazardou* pdlutanta at tha facility In tha laat thraa
    yaara, including tha approximata data and location of tha «pfU or laak, and tha typa and amount of malarial ralaaaad.	
 EPA Form 3510-2F (R«v. 1-B2)
                                                          Paga2of3


                                                           A-2
                                                                               Contlnua on Paga 3

-------
                                                                         TECHNICAL APPENDIX A
ConMntud from Pag« 2
                                  BPA D Numew popp mm Mm /orflorm 1)
 E. Po«nt4e«criai^ net eovOTd by «!•*•«-it any lone petulant kiM m taw* 2F-2.2F-3 or 2F-4. a tubuanoa or • componant of • subttanca
   which you curranly UM or manutactm as an mamaolaia or feaJ product or byproduct?

   I  I Yoa fltonnueftaoiuanaoabiy)	 FT He (goto
                                                                                          SO
Do you nava any to>o»ndaa or riaion jo bijlya tjail any blolpglaal laat tor aou» or chrome tertoHy haa baan mad* on any o< your diachanjaa or
on t% fMftMnQ Wattof In nMatton to j^ur OioolMnjo wNhn vw MM 3 yowvr

   I  1  Y*a(ii»«fmcBgB«ua>HioXBw»	  f  I  No
 WmanyottwmlyMraporMinMiiVII ovtamwdbyaconnot WbefMryoreamtMnoInn?

   I	I  Yo* (M tfw /MAW, aottMi, •no' MMAOM M*nbw at •nrf i

              A.NHIH
                    I   I No
/ ctttlty undtf ptnttoy or
«jp«Yvwon
tfw /ntormttton •ubmtttd.
oY/*cty nMponstt)/* for
      ffu»\ tccunn, and
                             tfw (Wt document tnd ft ttttchnttmt MWV pnptnd undtf ny dlnction or
                                                      tfitf qu&hd ptnanml property yUhtr »na tmlu»t»
                                 «w *>qu«fy ol tfw pwwn or pw»om who /nintgvtfwiyMm or tfx>M persons
                               tfw MomrnOon, tfw Wtammtoft suomMsd /t, to tfw OMf of /ny Jcnowtedpe tnd
/ am CMW* tfur Men *y*
* vgnfficv*
vloltitom.
                                                                pimta** for submitting fe/s* information,
f^ NMIW • OIMMI TiHo (qipo orprtflo,
                                                                          B. ATM Cod* and Plwn* No.
                                                                          O.OMSlgnod
EPA Form 3510-2F (R*v. 1-92)
                                               P*Q03of3
                                              A-3

-------
TECHNICAL APPENDIX A
                                          6rA >0 Numecr ,cepy Dem inn '
                                  '»" «00n>v«a CMS No
                                -.ominuid from MQ« 3 of
                                ratuW o( « Matt one aflatyM «or every pollutant « m.« tuw Complete en* :iei« '«K «ien :un»ii
                       MinutM
                                     Comootit*
                                                    Taken Ounng
                                                      F!rd»
                                                      MinutM
                Comeotit*
                                                                                 Numecr
                                                                                   of
                                                                                  Stonn
                                                                                               Seu'eti at 3;iiuianti
   Oil and &*•*•
   Bwjiogie* Oiygtn
   Otmand (BOOS)
   0*m«nd (COO)
   Tot*
   Nitrogtn
   Nrtrtw plut
   Nitntt Nitrootn
   Total
   OH
                   Minimum
                                                  Minimum
      f»n m' u»t tacn eonuunt mat if umitM m an •mucnt guiovin* «nien n>« iae«.T> x tuCjMt to or any pollutant i
-------
                                                              TECHNICAL APPENDIX A
Continued from ttw Front
Part C Lift eaoft pollutant ihown
additional detalto and requ
Pollutant
and
CAS Numb*
(If avallatotoj






























in Tabiaa 2F-2, 2F-0, and 2F-4 that you know or rtav* raaaon » baltov* w praaant. S*a tha mctrunoni for
kamama. CompMa ona tat* for each outfal.
Maximum Valuaa
QrabSampla
TafcwiOurtnfl
r«m»
MinuM*






























How walghlad
Compoatta






























Awaraga Valuaa
(IncKidaiinMi;
GrabSampla
Takan During
Fkat»
Mnutaa






























D«MM^*^klMl^M«4
rfowmvaigniaa
Compoana






























Numoar
of
Stofvn
Events
Samplad






























Souraaa of Pollutanti































1. 2. 3.
Dataof Duration TotalraMal
Storm of Storm Event during atorm evant
Event (In minutM) On Jncrteaj

4. 5. 6.
NufTKMT Of NOUfB DOTWW1 MVOfTNaVn nOW fttV QUnHQ TOtU flOW ffOfTl
•MQifminQ of •tofiH fTMflaV vwn wwit *•*•*•«•«*
uradandandotpravtoua fealona/minuBtor rammwn
rrwMurabta rain •vvnt ipvcrryuntt* baAonaorap«o)fyunM>;

7. Provide a oeecrlpuort of tne metnod of flow nMaaurtmefit or aaliniata*

EPA Form 3S10-2F (Ftev. 1-02) PagaW*
A-5

-------
TECHNICAL APPENDIX A
                                     Instructions - Form 2F

                    Application for Permit to Discharge Storm Water

                             Associated with Industrial Activity

     Who Must File Form 2F

     Form 2F must be completed by operators of facilities which discharge storm water associated with industrial
     activity or by operators of storm water discharges that EPA is evaluating for designation as a significant
     contributor of pollutants to waters of the United States, or as contributing to a violation of a water quality
     standard.
     Operators of discharges which are composed entirely of storm water must complete Form 2F (EPA Form
     3510-2F) in conjunction with Form 1 (EPA Form 3510-1).

     Operators of discharges of storm water which are combined with process wastewater (process wastewater
     is water that comes into direct contact with or results from the production or use of any raw material, interme-
     diate product, finished product, byproduct, waste product, or wastewater) must complete and submit Form
     2F, Form 1, and Form 2C (EPA Form 3510-2C).

     Operators of discharges of storm  water which are combined with nonprocess wastewater (nonprocess
     wastewater includes noncontact cooling water and sanitary wastes which are not regulated by effluent guide-
     lines or a new source performance standard, except discharges by educational, medical, or commercial
     chemical laboratories) must complete Form 1, Form 2F, and  Fqrm 2E (EPA Form 3510-2E).
     Operators of new sources or new discharges of storm water  associated with industrial activity which will be
     combined with other nonstormwater new sources or new discharges must submit Form 1, Form 2F, and
     Form 20 (EPA Form 3510-20).

     Where to File Applications

     The application forms should be sent to the EPA Regional Office which covers the State in which the facility
     is located.  Form 2F must be used only when applying for permits in  States where the  NPDES permits
     program is administered by EPA. For facilities located in States which are approved to administer the NPOES
     permits program, the State environmental agency should be contacted for proper permit application forms
     and instructions.
     Information on whether a particular program is administered by EPA or by a State agency can be obtained
     from your EPA  Regional Office. Form 1, Table 1 of the "General Instructions" lists the addresses of EPA
     Regional Offices and the States within the jurisdiction of each Office.
     Completeness

     Your application will not be considered complete unless you answer every question on this form and on Form
     i. If an item does not apply to you, enter "NA* (for not applicable) to show that you considered the question
     Public Availability of Submitted Information
     You may not claim as confidential any information required by this form or Form 1, whether the information
     is reported on the forms or in an attachment. Section 402(j)  of the Clean Water Act requires that all permit
     applications wHI be available to the public. This information will be made available to the public upon request
     Any information you submit to EPA which goes beyond that required by this form, Form 1, or Form 2C you
     may claim as confidential,  but claims for information which are effluent data will be denied.

     If you do not assert a claim of confidentiality at the time of submitting the information, EPA may make the
     information public without further notice to you. Claims of confidentiality will be handled in accordance with
     EPA's business confidentiality regulations at 40 CFR Part 2.

     Definitions

     All significant terms used in these instructions and in the form  are defined in the glossary found in the Genera!
     Instructions which accompany Form 1.
     EPA 10 Number
     Fill in your EPA Identification Number at the top of each odd-numbered page of Form 2F You may copy this
     number directly from item  I of Form 1.

     EPA Form 3510-2F (Rev. 1-92)                       I • 1


                                                 A-6

-------
                                                                          TECHNICAL APPENDIX A
Item I

You may use the map you provided for item XI of Form 1 to determine the latitude and longitude of each of
your outfalls and the name of the receiving water.

Item II-A
If you check "yes" to this question, complete alt parts of the chart, or attach a copy of any previous submission
you have made to EPA containing the same information.

Hem 11-8
You are not required to submit a description of future pollution control projects if you do not wish to or if none
is planned.

Kern III

Attach a site map showing topography (or indicating the outline of drainage areas served by the outfall(s)
covered in the application if a topographic map is unavailable) depicting the facility including:

    each of its drainage and discharge structures;

    the drainage area of each storm water outfall;

    paved areas and  building within the  drainage area of each storm water outfall, each known  past or
    present areas used for outdoor storage or disposal of significant materials, each existing structural con-
    trol measure to reduce pollutants in storm water runoff, materials loading and access areas, areas where
    pesticides, herbicides, soil conditioners and fertilizers are applied:

    each of its hazardous waste treatment, storage or disposal facilities (including each area not required to
    have a RCRA permit which is used for accumulating hazardous waste for less than 90 days under 40 CFR
    262.34);

    each well where fluids from the facility are injected underground; and

    springs, and other surface water bodies which receive storm water discharges from the facility,

Item IV-A

For each  outfall, provide an estimate  of  the area drained  by the outfall which is covered by impervious
surfaces.  For the purpose of this application, impervious surfaces are surfaces where storm water runs off at
rates that are significantly higher than background rates (e.g., predevelopment levels) and include paved
areas,  building roofs, parking lots, and  roadways. Include an estimate of the total area (including all impervi-
ous and pervious areas) drained by each outfall. The site map required under item III can be used to estimate
the total area drained by each outfall.

Item IV-B

Provide a  narrative description of significant materials that are currently or in the past three years have been
treated, stored, or disposed in a manner to allow exposure to storm water method of treatment, storage or
disposal of these materials; past and present materials management practices employed, in the last three
years, to minimize contact by these materials with storm water runoff; materials loading and access areas:
and the location, manner, and frequency in which pesticides, herbicides, soi conditioners, and fertilizers are
applied. Significant  materials should be identified by chemical name, form  (e.g.. powder, liquid, etc.). and
type of container or treatment unit  Indicate any materials treated, stored, or disposed of together. "Signifi-
cant materials' includes, but is not limited to:  raw materials; fuels; materials such as solvents, detergents, and
plastic pellets: finished materials such as metallic products: raw materials used in food processing or produc-
tion; hazardous substances designated under Section 101 (14) of CERCLA; any chemical the facility is re-
quired to report pursuant to Section 313 of Title III of SARA; fertilizers; pesticides; and waste products such
as ashes,  slag and sludge that have the potential to be released with storm water discharges.

Item IV-C

For each  outfall, structural controls Include structures which enclose material handling or storage areas.
covering materials, berms, dikes, or diversion ditches around manufacturing, production, storage or treat
ment units, retention ponds, etc. Nonstructural controls include practices  such as spill prevention plans
employee training, visual inspections, preventive maintenance, and housekeeping measures that are used to
prevent or minimize the potential for releases of pollutants.

EPA Form 3510-2F (R»v. 1-92)                       I -  2



                                              A-7

-------
TECHNICAL APPENDIX A
     ItemV

     Provide a certification that all outfalls that should contain storm water discharges associated with industrial
     activity have been tested or evaluated for the presence of non-storm water discharges which are not covered
     by an NPDES permit. Tests for such non-storm water discharges may include smoke tests, fluorometnc dye
     tests, analysis of accurate schematics'as well as other appropriate tests. Part B must include a description
     of the method used, the date of any testing, and the onsite drainage points that were directly observed during
     a test. All non-storm water discharges must be identified in a Form 2C or Form 2E which must accompany
     this application (see beginning of instructions under section titled "Who Must File Form 2F" for a description
     of when Form 2C and Form 2E must be submitted).

     Item VI

     Provide a description of existing information regarding the history of significant leaks or spills of toxic or
     hazardous pollutants at the facility in the last three years.
     Item VII-A, B, and C

     These items require you to collect and report data on the pollutants discharged for each of your outfalls. Each
     part of this item addresses a different set of pollutants and must be completed in accordance with the specific
     instructions for that part. The following general instructions apply to the entire item.
     General Instructions

     Part A requires you to report at least one analysis for each pollutant listed. Parts B and C require you to report
     analytical data in two ways. For some pollutants addressed in Parts B and C, if you know or have reason to
     know that the pollutant is present in your discharge, you may be required to list the pollutant and test (sample
     and analyze) and report the levels of the pollutants in your discharge. For all other pollutants addressed in
     Parts 8 and C. you must list the pollutant if you know or have reason to know that the pollutant is present in
     the discharge, and either report quantitative data for the pollutant or briefly describe the reasons the pollutant
     is expected to be discharged. (See specific instructions on the form and below for Parts A through C.) Base
     your determination that a pollutant is present in or absent from your  discharge on your knowledge of your
     raw materials, material management practices, maintenance chemicals, history of spills and releases, inter-
     mediate and final products and byproducts, and any previous analyses known to you of your effluent or
     similar effluent.

     A. Sampling:  The collection of the samples for the reported analyses should be supervised by a person
        experienced in performing sampling of  industrial wastewater or storm water discharges. You may con-
        tact EPA or your State permitting authority for detailed guidance on sampling techniques and for answers
        to specific questions. Any specific requirements contained in the applicable analytical methods should
        be followed for  sample containers, sample preservation, holding times, the collection of duplicate sam-
        ples, etc. The time when you sample should be representative, to the extent feasible, of your treatment
        system operating properly with no system upsets. Samples should be collected from the center of the
        flow channel, where turbulence is at a maximum, at a site specified in your present permit, or at any site
        adequate for the collection of a representative sample.
        For pH, temperature, cyanide, total phenols, residual  chlorine, oil and  grease, and fecal coliform.  grab
        samples taken during the first 30 minutes (or as soon thereafter as practicable) of the discharge must be
        used  (you are not required to analyze a flow-weighted composite for these parameters). For all other
        pollutants both a grab sample collected during the first 30 minutes (or as soon thereafter as practicable)
        of the discharge and a flow-weighted composite sampfe must be analyzed. However, a minimum of one
        grab sample may be taken for effluents from holding ponds or  other impoundments with  a retention
        period of greater than 24 hours.
        All samples shall be collected from the discharge resulting from  a storm event that is greater than 0  i
        inches and at least 72 hours from the previously measurable (greater than O.i inch rainfall) storm event
        Where feasible, the variance in the duration of the event and the total rainfall of the event should not
        exceed 50 percent from the average or median rainfall event in that area

        A grab sample  shall be taken during the first thirty minutes of the discharge (or as soon thereafter as
        practicable), and a flow-weighted composite shall be taken for the entire event or for the first three hours
        of the event.
        Grab and composite samples are defined as follows:


     EPA Form 3510-2F (Rev 1-92)                        I-3
                                                  A-8

-------
                                                                       TECHNICAL APPENDIX A
       Grab sample: An individual sample of at least 100 milliners collected during the first thirty minutes
       (or as soon thereafter as practicable) of the discharge. This sample is to be analyzed separately from
       the composite sample.

       Flow-Weighted Composite sample: A flow-weighted composite sample may be taken with a con-
       tinuous sampler that proportions the amount of sample collected with the flow rate or as a combina-
       tion of a minimum of three sample aliquots taken in each hour of discharge for the entire event or for
       the first three hours of the event, with each aliquot being at least 100 milliliters and collected with a
       minimum period of fifteen minutes between aliquot collections. The composite must be flow propor-
       tional; either the time interval between each aliquot or the volume of each aliquot must be propor-
       tional to either the stream flow at the time of sampling or the total stream flow since the collection of
       the previous aliquot. Aliquots may  be collected manually or automatically. Where GC/MS Volatile
       Organic Analysis (VOA) is required, aliquots must be combined in the laboratory immediately before
       analysis. Only one analysis for the composite sample is required.

    Data from samples taken in the past may be used, provided  that:

       All data requirements are met;
       Sampling was done no more than three years before submission; and
       All data are representative of the present discharge.
    Among the factors which would cause the data to be unrepresentative are significant changes in produc-
    tion level, changes in raw materials, processes, or final products, and changes in storm water treatment
    When the Agency promulgates new analytical methods in 40 CFR Part 136, EPA wll provide information
    as to when you should  use the new methods to generate data on your discharges. Of course, the
    Director may request additional information, including current quantitative data, if they determine it to be
    necessary to assess your discharges. The Director may allow or establish appropriate site-specific sam-
    pling procedures or requirements, including sampling locations, the season in which the sampling takes
    place, the minimum duration between the previous measurable  storm event and  the storm event sam-
    pled, the minimum or maximum level of precipitation required for an appropriate storm event, the form
    of precipitation sampled (snow melt or rainfall), protocols for collecting samples under 40 CFR Pan 136.
    and additional time for submitting data on a case-by-case basis.
B. Reporting:  All levels must be reported as concentration and mass (note: grab samples are  reported
    in terms of concentration).  You may report some or all of the required data by attaching separate
    sheets of paper instead of filfing out pages VIM and VII-2 if the separate sheets contain all the required
    information in a format which is constant with pages VIM and VII-2 in spacing and identification of
    pollutants and columns. Use the following abbreviations in the columns headed "Units."

                    Concentration                                    Mass

     ppm     parts per million                      IDS      pounds
     mg/1     milligrams per liter                    ton      tons (English tons)
     ppb      parts per billion                       mg      milligrams
     ug/l     micrograms per liter                  g        grams
     kg       klograms                           T        tonnes (metric tons)

    All reporting of values for metals must be in terms of "total recoverable metal,'' unless:
       (1) An applicable, promulgated effluent limitation or standard specifies the limitation for the metal in
       dissolved,  valent, or total form; or
       (2) All approved analytical methods for the metal inherently measure only its dissolved form (e.g..
       hexavalent chromium); or

       (3) The permitting authority has determined that in establishing case-by-case limitations it is neces-
       sary to express the limitations on the metal in dissolved, valent. or total form to carry out the provi-
       sions of the CWA. If you measure only one grab sample and one flow-weighted composite sample
       for a  given outfall, complete only the "Maximum Values*  columns and insert "1" into the "Number of
       Storm Events Sampled" column. The permitting authority may require  you to conduct additional
       analyses to further characterize your discharges.

 EPA Form 3510-2F (H«v. 1-92)                      ( , 4


                                             A-9

-------
TECHNICAL APPENDIX A
         If you measure more than one value for a grab sample or a flow-weighted composite sample for a given
         outfall and those values are representative of your discharge, you must report them. You must describe
         your method of testing and data analysis.  You also must determine the average of all values within the
         last year and report the concentration and mass under the "Average Values" columns,  and the total
         number of storm events sampled under the "Number ot Storm Events Sampled" columns.

     C.  Analysis: You must use test methods promulgated in 40 CFR Part  136; however, if none has been
         oromulgated for a particular pollutant, you may use any suitable method for measuring the level of the
         pollutant in your discharge provided that you submit a description of the method or a reference to a
         published method. Your description should include the sample holding time, preservation techniques,
         and the quality control measures which you used. If you have two or more substantially identical outfalls,
         you may request permission from your permitting authority to sample and analyze only one outfall and
         submit the results of the analysis for other substantially identical outfalls. If your request is granted by the
         permitting authority, on a separate sheet attached to the application form, identify which outfall you did
         test, and describe why the outfalls which you did not test are substantially identical to the outfall which
         you did test.
     Part VILA
     Part VII-A must be completed by all applicants for all outfalls who must complete Form 2F.
     Analyze a grab sample collected during the first thirty minutes (or as soon thereafter as practicable) of the
     discharge and flow-weighted composite samples for all pollutants in this Part, and report the results except
     use only  grab samples for pH and oil and grease. See discussion in  General Instructions to Item VII for
     definitions of grab sample collected during the First thirty minutes of discharge and flow-weighted composite
     sample. The "Average Values" column is not compulsory but should be filled out if data are available

     Part Vll-B
     List all pollutants that are limited in an effluent guideline which the facility is subject to (see 40 CFR Subchap-
     ter N to determine which pollutants are limited in effluent guidelines) or any pollutant listed in the facility's
     NPDES permit for its process wastewater (if the facility is operating under an existing NPDES permit) Com-
     plete one table for each outfall. See discussion  in General instructions to item VII for definitions of grab
     sample collected during the first thirty minutes  (or as soon thereafter as practicable) of discharge and flow-
     weighted composite sample. The "Average Values' column is not compulsory but should be filled out if data
     are available.

     Analyze a grab sample collected during the first thirty minutes of the discharge and flow-weighted composite
     samples for all pollutants in this Part, and report the results, except as provided in the General Instructions

     PartVII-C
     Part VII-C must be completed by all applicants for all outfalls which discharge storm water associated with
     industrial activity, or that EPA is evaluating for designation as a significant contributor of pollutants to waters
     of the United States, or as contributing to a violation of a water quality standard. Use both a grab sample and
     a composite sample for all pollutants you analyze for in this pan except use grab samples for residual chlorine
     and fecal coliform.  The "Average Values" column is not compulsory  but should be filled out if data  are
     available. Part C requires you to address the pollutants in Table 2F-2, 2F-3, and 2F-4 for each outfall Pollu-
     tants in each of these Tables are addressed differently.
     Table 2F-2:  For each outfall, list all pollutants in Table 2F-2 that you know or have reason to believe are
     discharged (except pollutants previously listed in Part Vll-B). If a pollutant is limited in an effluent guideline
     limitation which the facility is subject to,  the pollutant must be analyzed and reported in Part Vll-B. If a
     pollutant in Table 2F-2 is indirectly limited by an effluent guideline limitation through an indicator (e.g., use
     ot TSS as an indicator to control the discharge of iron and aluminum),  you must analyze for it and report
     the data  in Part Vll-B. For other pollutants listed in Table 2F-2 (those not limited directly or indirectly by an
     effluent limitation guideline),  that you know or have reason to believe are discharged, you must either report
     quantitative data or briefly describe the reasons the pollutant is expected to be discharged.
     Table 2F-3: For each outfall, list all pollutants in Table 2F-3 that you know or have reason to believe are
     discharged.  For every pollutant in Table 2F-3 expected to be  discharged in concentrations  of 10 ppb or
     greater, you must submit quantitative data.  For acroiein, acrylonitrile, 2,4 dinitrophenol,  and 2-methyi-4 6
     dinitrophend, you must submit quantitative data if any of these four pollutants is expected to be discharged
     EPA Form 3510-2F (Rev  1-92)                        |-5

                                                   A-10

-------
                                                                         TECHNICAL APPENDIX A
 m concentrations of 100 ppb or greater. For every pollutant expected to be discharged in concentrations less
 than 10 ppb (or 100 ppb for the four pollutants listed above), then you must either submit quantitative data
 or briefly describe the reasons the pollutant is expected to be discharged.

 Small Business Exemption - If you are a 'small business,* you are exempt from the reporting requirements
 for the organic toxic pollutants listed in Table 2F-3. There are two ways in which you  can qualify as a 'small
 business'. If your facility is a coal mine, and if your probable total annual production is less than 100.000 tons
 per year, you may submit past production data or estimated future production (such as a schedule of esti-
 mated total production under 30 CFR 795.14(c)) instead of conducting analyses for the organic toxic pollu-
 tants. If your facility is not a coal mine, and if your gross total annual sales for the most recent three years
 average less than $100,000 per year (in second quarter 1980 dollars),  you may submit sales data for those
 years instead of conducting analyses for the organic toxic pollutants. The production or sales data must be
 for the facility which is the source of the discharge. The data should not be limited to production or sales for
 the process or processes which contribute to the discharge, unless those are the only processes at your
 facility. For sales data, in situations involving intracorporate transfer of goods and services, the transfer price
 per unit should approximate market prices for those goods and services as closely as possible. Sales figures
 for years after 1980 should  be indexed to the second quarter of 1980 by using the gross national product
 price deflator (second quarter of 1980*100). This index is available in National Income and Product Ac-
 counts of the United States  (Department of Commerce. Bureau of Economic Analysis).

 Table 2F-4: For each outfall, list any pollutant in Table 2F-4 that you know or believe to be present in the
 discharge and explain why  you believe it to be present  No analysis is required, but if you have analytical
 data, you must report them. Not*: Under 40 CFR 117.l2(a)(2), certain discharges of hazardous substances
 (listed at 40 CFR 177.21 or 40 CFR 302.4) may be exempted from the requirements of section 311 of CWA.
 which establishes reporting requirements, crvfl penalties, and liability for cleanup costs for spills of oil and
 hazardous substances. A discharge of a particular substance may be exempted if the origin, source, and
 amount of the discharged substances are identified in the NPDES permit application or in the permit,  if the
 permit contains a requirement for treatment of the discharge, and if the treatment is in place. To apply for an
 exclusion of the discharge of any hazardous substance from the requirements of section 311, attach addi-
 tional sheets of paper to your form, setting forth the following information:

   1. The substance and the amount of each substance which may be discharged.

   2. The origin and source of the discharge of the substance.

   3. The treatment which is to be provided for the discharge by:

         a. An onsrte treatment system separate from any treatment system treating  your normal dis-
            charge;

         b. A treatment system designed to treat your normal discharge and which is additionally capable
            of treating the amount of the substance identified under paragraph i above; or

         c. Any combination of the above.

 See 40 CFR 117.l2(a)(2) and (c). published on August 29. 1979. in 44 FR 50766, or contact your Regional
 Office (Table 1 on Form 1, Instructions), for further information on exclusions from section 311
 Part VII-D

 If sampling is conducted during more than one storm event, you only need to report the information re-
 quested in Part V1I-0 for the storm event(s) which resulted in any maximum pollutant concentration reported
 inPartVII-A, Vll-B. orVII-C.

 Provide flow measurements or estimates of the flow rate, and the total amount of discharge for the storm
 event(s) sampled, the method of flow measurement, or estimation. Provide the data and duration of the storm
 event(s) sampled, rainfall measurements, or estimates of the storm event which generated the sampled runoff
 and the duration between the storm event sampled and the end of the previous measurable (greater than 0 i
 inch rainfall) storm event.

 Part VII-E

 List any toxic pollutant listed in Tables 2F-2, 2F-3, or 2F-4 which you currently use  or manufacture as an
 intermediate or final product or byproduct. In addition, if you know or have reason to  believe that 2,3,7,8-te-
 trachlorodibenzo-p-dioxin (TCDD)  is discharged or if you use or manufacture 2,4,5-trichlorophenoxy acetic


EPA Form 3510-2F (fl«v. 1-92)                         I - 6

                                             A-11

-------
TECHNICAL APPENDIX A
       acid (2,4,5,-T); 2-(2,4,5-trichlorophenoxy) propanoicacid (Silvex, 2,4,S.-TP). 2-(2,4.5-trichlorophenoxy) ethyl
       2.2-dichloropropionate (Erbon); 0.0-dimethyl 0-(2,4,5-trichlorphenyl) phosphorothioate (Ronnel); 2.4.5-
       trichlorophenol (TCP); or hexachlorophene (HCP); then list TCDD. The Director may waive or modify the
       requirement if you demonstrate that it would be unduly burdensome to identify each toxic pollutant and the
       Director has adequate information to issue your permit. You may not claim this information as confidential.
       however, you do not have to distinguish between use or production of the pollutants or list the amounts
       Item VIII

       Self explanatory. The permitting authority may ask you to provide additional details after your application is
       received.
       ItemX

       The Clean Water Act provides for severe penalties for submitting false information on this application form.
       Section 309(c)(4) of the Clean Water Act provides that 'Any person who knowingly makes any false material
       statement, representation, or certification in any application.... shall upon conviction, be punished by a fine
       of not more than S10.000 or by imprisonment for not more than 2 years, or by both. If a conviction of such
       person is for a violation committed after a first conviction of such person under this paragraph, punishment
       shall be by a fine of not more than $20,000 per day of violation, or by imprisonment of not more than 4 years.
       or by both.' 40 CFR Part 122.22 requires the certification to be signed as follows:
           (A) For a corporation: by a responsible corporate official. For purposes of this section, a responsible
          corporate official means (I) a president,  secretary, treasurer, or vice-president of the corporation m
          charge of a  principal business function, or any other person who performs similar policy- or decision-
          making functions for the corporation, or (ii) the manager of one or more manufacturing, production, or
          operating facilities employing more than 250 persons or  having gross annual sales or expenditures
          exceeding $25.000.000 (in second-quarter 1980 dollars), if authority to sign documents has been as-
          signed or delegated to the manager in accordance with corporate procedures.

           Note: EPA does not require specific  assignments or delegation of authority to responsible corporate
          officers identified in I22.22(a)(1)(i). The Agency will presume that these responsible corporate officers
          have the requisite authority to sign permit applications unless the corporation has notified the Director to
          the contrary. Corporate procedures  governing authority to  sign  permit applications may provide for
          assignment  or delegation to applicable corporate position under 122.22(a)(l)(ii) rather than to specific
          individuals.
           (B) For a partnership or sole proprietorship: by a general partner or the proprietor, respectively; or
           (C) For a municipality, State, Federal, or other public agency: by either a principal executive officer
          or ranking elected official. For purposes of this section, a principaT executive officer of a Federal agency
           includes (i) the chief executive officer of the agency, or (ii) a senior executive officer having responsibility
          for the overall operations of a principal geographic unit of the agency (e.g.. Regional Administrators of
           EPA).
        EPA Form 3510-2F (Rev 1-92)                       | . 7


                                                    A-12

-------
                                                          TECHNICAL APPENDIX A
1-A
1-8
1-C
1-D
1-E
1-F
1-G
1-H
1-1
1-J
1-K
1-L
2-A
2-B
2-C
2-0
2-E
2-F
3-A
3-B
3-C
3-0
4-A
4-B
5-A
5-B
5-C
5-0
5-E
5-F
5-G
5-H
5-1
5-J
5-K
5-L
Ammonia Stripping
Dialysis
Diatomaceous Earth Filtration
Distillation
Sectrodialysis
Evaporation
Ftocculation
Flotation
Foam Fractionatkxi
Freezing
Gas-Phase Separation
Grinding (Comminutors)
Carbon Adsorption
Chemical Oxidation
Chemical Precipitation
Coagulation
Dechlorination
Disinfection (CWonne)
Activated Sludge
Aerated Lagoons
Anaerobic Treatment
Nitrilication-Denitriftcation
Discharge to Surface Water
Ocean Discharge Through Out
Stud
Aerobic Digestion
Anaerobic Digestion
Belt Filtration
Centrifugation
Chemical Conditioning
Chlorine Treatment
Composting
Drying Beds
Elutnation
Flotation Thickening
Freezing
Gravity Thickening
Table 2F-1
Codes for Treatment
Units
1-M Grit Removal
1-N Microstraining
1-O Mixing
1-P Moving Bed Filters
1-Q Multimedia Filtration
1-R Rapid Sand filtration
1-S Reverse Osmosis (Hyperfiltration)
1-T Screening
1-U Sedimentation (Setting)
1-V Slow Sand Filtration
1-W Solvent Extraction
1-X Sorption
Chemical Treatreent Processes
2-G Disinfection (Ozone)
2-H Disinfection (Other)
2-1 Electrochemical Treatment
2-J Ion Exchange
2-K Neutralization
2-L Reduction
Biological Treatment Processes
3-E Pre-Aeration
3-F Spray Irrigation/Land Application
3-G Stabilization Ponds
3-H Trickling Filtration
Other Processes
4-C Reuse/Recyde of Treated Effluent
fan 44) Underground Injection
5-M
^N
SO
5-P
SO
5^
5-S
5-T
S-U
5-V
5-W
Heat Drying
Heat Treatment
Incineration
Land Application
Landfill
Pressure Filtration
Pyrolysis
Sludge Lagoons
Vacuum Filtration
Vibration
Wet Oxidation
EPA Form 3510-2F (Rev. 1-92)                   | . 9





                                    A-13

-------
TECHNICAL APPENDIX A
                                              Table 2F-2

                            Conventional and Nonconventlonal Pollutants
            Bromide
            Chlorine, Total Residual
            Color
            Fecal Coliform
            Fluoride
            Nitrate-Nitrite
            Nitrogen, Total Organic
            Oil and Grease
            Phosphorus, Total
            Radioactivity
            Sulfate
            Sulfite
            Surfactants
            Aluminum, Total
            Barium, Total
            Boron, Total
            Cobalt Total
            Iron. Total
            Magnesium, Total
            Molybdenum, Total
            Manganese, Total
            Tin. Total
            Titanium. Total
     EPA Form 3510-2F (Rev 1-92)                          ' ' 9


                                                       A-14

-------
                                                                                       TECHNICAL APPENDIX A
      Antimony, Total
      Arsenic. Total
      Beryllium. Total
      Cadmium, Total
      Chromium, Total
      Acrolein
      Acrylonitrile
      Benzene
      Bromoform
      Carbon Tetrachlonde
      Chlorobenzene
      Chlorodibromomethane
      Chloroethane
      2-Chloroethyrvinyl Ether
      Chloroform
      2-Chtofophenol
      2.4-Dichlorophenol
      2.4-Dimethylphenol
      4.6-Dinitro-O-Cresol
      Acenaphthene
      Acenaphthylene
      Anthraotna
      Benzidine
      Benzo(a)anthracene
      Btnzo(a)pyr«n«
      3,4-Benzofluoranthene
      Benzo(ghi)perylene
      B»nzo(k)fluoramhene
      Bis(2-chloroethoxy)methane
      Bis(2-chloroethyl)ether
      Bi*(2-chloro
-------
TECHNICAL APPENDIX A
                                                         Table 2F-4
                                                     Hazardous Substances
            Asbestos


            Acetaldehyde
            Atlyl alcohol
            AJIyl chloride
            Arnyl acetate
            Aniline
            Benzonitrile
            Benzyl chloride
            Butyl acetate
            Butylamme
            Carbaryl
            Carbofuran
            Carbon disuldde
            Chlorpynfos
            Coumaphos

            Cresol
            Crotonaldehyde

            Cyclohexane
            2.4-0 (2.4-Oichlorophenoxyacetic
            acid)
            Oiazmon
            Oicamba
            Dichlobenil
            Oichlone
            2.2-Oichloropropionic acid
            Oichlorvos
            Diethyl amine
            Dimethyl amine
          Toxic Pollutant


      Hazardous Substances
Oinitrobenzene
Diquat
Oisulfoton
Oiuron
Epichlorohydnn
Ethion
Ethylene diamine
Emyiene dibromide
Formaldehyde
Furfural
Guthion
Isoprene
isopropanolamine
Kelthane

Kapone
Maiathion

Mercaptodimethur
Methoxychlor

Methyl mercaptan
Methyl meihacrylate
Methyl parathion
Mevmphos
Mexacarbate
Monoethyl amine
Monomethyl amine
Naled
Napthenic acid
Nitroioiuene
Parathion
Phenolsulfonate
Phosgene
Propargite
Propytene oxide
Pyrethrins
Ouinolme
Resorcmol
Stronthium
Strychnine
Styrene
2,4,5-T (2.4,5-Tnchloropheno«yacetic
acid)
TOE (Tetrachlorodiphenyt ethane)
2.4,5-TP(2-(2.4.5-Trichlorophenoxy)
propanoic acid]
Trichlorofan
Triethytamme

Tn methyl amine
Uranium
Vanadium
Vinyl acetate
Xylene
Xylenol
Zirconium
                                                                  it  U. S. Government Printing Office: 1992 - 617-003 I47058I
      EPA Form 3510-2F (Hev. 1-92)
            1-11
           A-16

-------
                                                                                              TECHNICAL APPENDIX A
 P eaie
  ' -• s- !VD« iri me unsnaoeo »'eai on'v
  i^fi! t't tptree ,*. I3ch*nct*n/inchl
                                                                         Fonn Approved  OMB No 2040-0086  Approval tip.r»s 5-31-92
                                                                                       t fFA I.O. NUMKR
                                          GENERAL INFORMATION
                                             CtomwlM
     FACILITY NAME N
   \   \   \  \  \  \
    F'ACILITV
_   MAILING ADDRESS
f\ \ \  \ \ \
      \v
   X FACILITY
 II. POLLUTANT CHARACTERISTICS
  INSTRUCTIONS: Compittt A ftiM|k J »
  quntiom, you mutt Mbmit *• ton* •< tkt
  H tin wppttmrniil torn • ime
  ii txcludtd tram ptrmit ra«uimMfc; M
                                                                                         •• PA. H you MMW "y«" to any
                                                                          _ Ski sjsjsfls*. Us* "X" to tht box MI tht third column
                                                         yss tmt ml sisaalt o»y si ISSIS Istm Vs> msy onmur "no* H your attrvity
                                                                  0 Sf fJK) iHtVCSfSSf for SarlJailaJfli Or S0M~foVOI Sttn4
                                                   UM 3t'i_
                                                    •• .mm
  A. Ii ttiM Mcilny  •
     which r«tutu in a
     If OHM 2A)
  C  It tho • iKiinv which eurroiiiv rawlti Mi I
     to «mn o< MM U.S. otMr than than Om
     A or B Uiavt' IFORM 2C)
                                                                F. Do you V «M y«v «|oei «t IMi tacilrty
  E  Doti or will  thu  facility treat, nor*, or i
     haiardout waBea' (FORM 3)
water or other fluids which are oroufM to tha lurteea
m connection with conventional oil or natural *M pro-
duction, miect fluidi uMd tor aiihaimd i»a»»r» ol
                                                                M. O* VM V «W ytw
     oil or natural to. or intact ttvMi for
     hydroearbeni? (FORM 41	
                                        of liquid
                                                                                  tapM « fMi tRUity llwditor IP*
                                                                                  Ii mlritm of turlur by tht Fruch
                                                                                      OT ninOTlt, ifi titu
                                                                                           o( t»o«h»rrn»l
     Ii this facility a i
     one of the 28 indunriai
     itructione and which will potemidry omN 100 tato
     pe> year  of  any air pollutant  refuMMd iu*tr Ida
     Clean Air Act and may effect  or be axoiad In on
     attainment aree> (FORM 81
                                                                           pVQVOMO MHMMM^f §MMW WhtCh IS
                                                                           IS IXtaatlol cate«or« Imad in tha
                                                                      i Md wnWi w* pnamWty amrt 280 ton.
                                                              par ytwutojyo* polluam reiulned under the Ctoen
                                                              Air Aat an* new oH>« or b» HoMid in an analnmem
 V. FACILITY MAILING ADDRESS
EPA  Form 3510-1  (t-90)
                                                                                                       CONTINUE OS REVERSE
                                                           A-17

-------
TECHNICAL APPENDIX A
             »HOM THE
  VII. SIC CODES ' O't't. '" f'O»' at priority
  VIII. OMNATOM INFOftMATION
                                                                                                       I.  !• Ow turn* ittuo in
                                                                                                          lorn VMI-* CUP MM
                                                                                                            YES HI NO
                                                                                             O PMONC torra ruUf 4 no i
                              I. «T*«IT OK ».O «OX
                                                                                      li nw iKilitv IOOIM on Indian lands>

                                                                                          CD YES     C NO
   X. EXISTING INVIMONMINTAL PIMII
                                             D. ^so M^ ffnianonf/rvm Propojrd Sonnet
    f•FEDERAL
    S"STATE
     > « PRIVATE
M • PUBLIC laixtr thin ftdtnl or tniti
0 • OTHER upnihi
       A NFDIS IDUdurtn to Sartmct Wtttrl
          ll_
       • UlC fVitOfrfround llneeUOH o
                                                                                  liftclfyt
                                                                                 (iptcifyj
   Attach to thi* tpplieation • topographic m«p of tht MM urtinding to it Itwt on* milt b*yond property boundwin. The m»p mun *ow
   tht outliiw of tht tadlity, tht location of Mch of to wcMng Mid propowd inttk* and dtoehMft MructtMt, *»d« of it» hmrdoui «wtt
   tTHtmtnt. noragt. or disposal fadlitm, and MCh wall whara K Iniacts Hukh underground, Induda aM iprkigi. rr*ar» and othar aurfaoa
   watir bodix in the map area. Sea imtructiom tar predte raquiremanti.
   XII. NATURE OF MJSINEtt larondf • on* omcnfUonT
   XIII. CERTIFICATION lift nouctioml
    I ctrtify undtr ptnttty of to* ttift IA
    uuehmtnn met thtt, tumd en my inquiry of tr*
                                                                Mr)
    •pp/fcerfen, / 0eArM thtt tht informttion «true, jeeurMe eno* comp«jBj. / «m ^
    f»lm information, including tht pamtattttf afflmindi
                                                        for oHdnlht 9m tttommtion eenuintd in
                                                       Met mere eft afctMcMpenartNe ror auom/nina
  EPA Form  3510-1
                                                          A-18

-------
                              TECHNICAL APPENDIX B
           APPENDIX B




NOAA WEATHER RADIO INFORMATION

-------
                                                                TECHNICAL APPENDIX B
                     NOAA WEATHER RADIO MANUFACTURERS LIST
               RADIO SHACK
               Weather Radio
               2617 West Seventh St.
               Fort Worth, TX 76107
               (817) 390-3011
               GENERAL ELECTRIC
               Model 7-2934
               (800) 626-2000
               UNIDEN BEARCAT
               Bearcat Weather Alert
               6345 Castleway Court
               Indianapolis, IN 46250
               (800) 722-6637
               ELECTROLERT
               Weatheralert Forecaster
               4949 South 25A
               TippCity, OH  45371
               (513) 667-2461
               SPRINGFIELD INSTRUMENTS
               Talking Weather Center/Station
               76 Paccaic St.
               Wood-Ridge, NJ 07075
               (201) 777-2900
               WOODSON ELECTRONICS
               Plectron
               505 Lincoln St.
               Overton, NE 68863
               (308) 987-2404
               GORMAN - REDUCH MANUFACTURING
               James T. Gorman
               257 West Union St.
               Athens, OH 45701
               (617) 593-3150
PRICE RANGE:

 J  Under $50
 •  $50 to $100
 X  Over $100
 •  Features AM/FM model radios with weather band

PLEASE NOTE, THIS LIST is NOT  ALL-INCLUSIVE, AND INCLUSION ON THIS LIST DOES NOT CONSTITUTE
ENDORSEMENT OF ANY COMPANY BY EPA OR THE U.S. GOVERNMENT.
                                          B-l

-------
TECHNICAL APPENDIX B
        !ii
                             !iiifi ill

                                 Up
                                 • 5. _ S* •
                                - .*£3*!
                             •?-** 5l!isl
                       nm jiiHii 111
                       liihiilitiipliii
                        B-2

-------
                                TECHNICAL APPENDIX B

 l! ,i!s!
iijiiiiiiliiiiiiiiiiiipiii

                                         jjjjn
                                   I lljjli
                                   !   H
                                     fjl
!il!]iislsiiilililillii$yi
               iii
                                      ii.il
 iiliiii
mar
                B-3

-------
                                             TECHNICAL APPENDIX C
                     TECHNICAL APPENDIX C

REQUIRED CONTAINERS, PRESERVATION TECHNIQUES, HOLDING TIMES AND
          40 CODE OF FEDERAL REGULATIONS (CFR) PART 136

-------
                  TECHNICAL APPENDIX C
REQUIRED CONTAINERS, PRESERVATION TECHNIQUES, AND HOLDING TIMES
Parameter
Bacterial Tests
Coliform, fecal and total
Fecal streptococci
Inorganic Tests
Acidity
Alkalinity
Ammonia
Biochemical oxygen
demand
Biochemical oxygen
demand, carbonaceous
Bromide
Chemical oxygen
demand
Chloride
Chlorine, total residual
Color
Cyanide, total and
amenable to chlorination
Fluoride
Hardness
Hydrogen ion (pH)
Kjeldahl and organic
Nitrogen
Metals (7)
Chromium VI
Mercury
Metals, except above
Nitrate
Container(l)

P, G
P, G

P,G
P,G
P, G
P, G
P, G
P,G
P,G
P,G
P, G
P, G
P,G
P
P,G
P,G
P, G

P,G
P, G
P, G
P, G
Preservative (2), (3)

Cool, 4°C
0.008% NazSjOj (5)
Cool, 4°C
0.008% NajS2O3 (5)

Cool, 4°C
Cool, 4°C
Cool, 4°C
H2S04topH<2
Cool, 4°C
Cool, 4°C
None required
Cool, 4°C
HjSO4topH<2
None required
None required
Cool, 4°C
Cool, 4°C
NaOH to pH> 12
0.6g ascorbic acid (5)
None required
HN03topH<2
HjSO4topH<2
None required
Cool, 4°C
HjSO< topH<2

Cool, 4°C
HN03topH<2
HN03topH<2
Cool, 4°C
Maximum Holding
Time (4)

6 hours
6 hours

14 days
14 days
28 days
48 hours
48 hours
28 days
28 days
28 days
Analyze immediately
48 hours
14 days (6)
28 days
6 months
Analyze immediately
28 days

28 hours
28 hours
6 months
48 hours
C-l

-------
TECHNICAL APPENDIX C
REQUIRED CONTAINERS, PRESERVATION TECHNIQUES, AND HOLDING TIMES
Parameter
Nitrate-nitrite
Nitrite
O&G
Organic carbon
Orthophosphate
Oxygen, Dissolved
Probe
Dissolved oxygen,
Winkler method
Phenols
Phosphorus (elemental)
Phosphorus, total
Residue, total
Residue, filterable
Residue, nonfilterable
(TSS)
Residue, settleable
Residue, volatile
Silica
Specific conductance
Sulfate
Sulfide
Sulfite
Surfactants
Temperature
Turbidity
: Containerfl)
P,G
P,G
G
P,G
P,G
G bottle and top
G bottle and top
G only
G
P,G
P, G
P, G
P,G
P, G
P, G
P
P, G
P, G
P, G
P, G
P, G
P, G
P, G
Preservative (2), (3)
Cool, 4°C
Cool, 4°C
Cool, 4°C
HjSO4orHCltopH<2
Cool, 4°C
HClorH2SO4 topH<2
Filter immediately
Cool, 4°C
None required
Fix on site and store in
dark
Cool, 4°C
HjS04topH<2
Cool, 4°C
Cool, 4°C
HjSO4topH<2
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C
Cool, 4°C, add zinc
acetate plus sodium
hydroxide to pH> 9
None required
Cool, 4°C
None required
Cool, 4°C
Maximum Holding
Tune (4)
28 days
48 hours
28 days
28 days
48 hours
Analyze immediately
8 hours
28 days
48 hours
28 days
7 days
7 days
7 days
48 hours
7 days
28 days
28 days
28 days
7 days
Analyze immediately
48 hours
Analyze
48 hours
                                   C-2

-------
                  TECHNICAL APPENDIX C
REQUIRED CONTAINERS, PRESERVATION TECHNIQUES, AND HOLDING TIMES
Parameter
Organic Tests (8)
Purgeable halocarbons
Purgeable aromatics

Acrolein and
acrylonitrile

Phenols (11)
Benzidines(ll)
Pbthalate esters (11)
Nitrosamines(ll), (14)
PCBs (11) acrylonitrite
Nitroaromatics and
isopborone (11)
Polynuclear aromatic
hydrocarbons (11)
Haloethers(ll)
Chlorinated
hydrocarbons (11)
TCDD (11)
Pesticides Tests
Pesticides (11)
Radiological Tests
Alpha, beta, and radium
Container^)

G, Teflon-lined septum
G, Teflon-lined septum

G, Teflon-lined septum

G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap
G, Teflon-lined cap

G, Teflon-lined cap

P, G
Preservative (2), (3)

Cool, 4°C
0.008% NajSA (5)
Cool, 4°C
0.008% Na,SA (5)
HCltopH<2(9)
Cool, 4°C
0.008% NajSA (5)
Adjust pH to 4-5 (10)
Cool, 4°C
0.008% NajSA (5)
Cool, 4°C
0.008% NajSjO, (5)
Cool, 4°C
Cool, 4°C
store in dark
0.008% NajSjOj
Cool, 4°C
Cool, 4°C
store in dark
0.008%NA2S2O3(5)
Cool, 4°C
store in dark
0.008% NajSA (5)
Cool, 4°C
0.008% NajSA (5)
Cool, 4°C
Cool, 4°C
0.008% NajSA (5)

Cool, 4°C
PH 5-9 (15)

HN03topH<2
Maximum Holding
Time (4)

14 days
14 days

14 days

7 days until extraction,
40 days after extraction
7 days until extraction
(13)
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction
7 days until extraction,
40 days after extraction

7 days until extraction,
40 days after extraction

6 months
C-3

-------
TECHNICAL APPENDIX C
                                   40 CFR 136.3 TABLE II NOTES
  (1)    Polyethylene (P) or Glass (G).

  (2)    Sample  preservation  should be performed  immediately  upon sample  collection.   For composite
        chemical samples each aliquot should be preserved at the time of collection.   When use of an
        automated sampler makes  it impossible  to  preserve each aliquot, then chemical samples may be
        preserved by maintaining at 4°C until compositing and sample splitting is completed.

  (3)    When any sample is to be shipped by common carrier or sent through the United States Mails, it must
        comply with the Department of Transportation Hazardous Materials Regulations (49 CFR Part 172).
        The person offering such material for transportation is responsible for ensuring such compliance.  For
        the preservation requirements of Table n, the Office of Hazardous Materials, Materials Transportation
        Bureau, Department of Transportation has determined that the Hazardous Materials Regulations do not
        apply to the following materials:   Hydrochloric acid (HC1) in water solutions at concentrations of
        0.04% by  weight  or  less  (pH about  1.%  or  greater); Nitric acid (HNO3)  in  water  solutions at
        concentrations of 0.15% by weight or less (pH about 1.62 or greater); Sulfuric acid (HjSOJ in water
        solutions at concentrations  of 0.35% by weight or less  (pH about 1.1.5  or  greater);  and  Sodium
        hydroxide (NaOH)  in water solutions at concentrations of 0.080%  by weights or less (pH about 12.30
        or less).

  (4)    Samples should be analyzed as soon as possible after collection.  The times listed are the maximum
        times that samples may be held before analysis and still be considered valid.  Samples may be held for
        longer periods only if the  permittee, or monitoring laboratory,  has data  on  file to show that the
        specific types of samples under study are stable  for the longer time, and has received a variance from
        the Regional Administrator under § 136.3(e).  Some samples may not be stable for the maximum time
        period given in the table. A permittee,  or monitoring laboratory, is obligated to hold the sample for a
        shorter time if knowledge exists to show that this is necessary to maintain sample stability. See
        § 136.3(e) for details.

  (5)    Should only be used in the presence of residual chlorine.

  (6)    Maximum holding time is 24 hours when sulfide is present. Optionally all samples may be tested with
        lead acetate paper  before pH adjustments in order  to determine  if sulfide is present.   If sulfide is
        present, it can be removed by the addition  of  cadmium nitrate powder until a negative spot test is
        obtained.  The sample is filtered and then NaOH is added to pH 12.

  (7)    Samples should be filtered immediately on-site before adding preservative for dissolved metals.

  (8)    Guidance applies to samples to be analyzed by GC, LC, or GC/MS for specific compounds.

  (9)    Sample receiving no pH adjustment must be analyzed within seven days of sampling.

  (10)  The pH adjustment is not required if acrolein will not be measured. Samples for acrolein receiving no
        pH adjustment must be analyzed within 3  days of sampling.
                                                 C-4

-------
                                                                         TECHNICAL APPENDIX C
                                 40 CFR 136.3 TABLE H NOTES
(11)  When  the  extractable  analytes of concern  foil within a single  chemical  category,  the  specified
      preservative and  maximum holding  times  should be observed for optimum safeguard of sample
      integrity.  When the analytes of concern fall within two or more chemical categories, the sample may
      be preserved by cooling to 4°C, reducing residual chlorine with 0.008% sodium thiosulfate, storing in
      the dark,and adjusting the pH to 6-9; samples preserved in this manner may be held for seven days
      before extraction and for forty days after extraction.   Exceptions to this optional preservation and
      holding time procedure are noted in footnote 5 (re the requirement for thiosulfate reduction of residual
      chlorine), and footnotes 12, 13 (re the analysis of benzidine).

(12)  If 1,2-diphenylhydrazine is likely to be present,  adjust the pH of the sample to 4.0 ±_ 0.2 to prevent
      rearrangement to benzidine.

(13)  Extracts may be stored up to 7 days  before analysis if storage is conducted under an inert  (oxidant-
      free) atmosphere.

(14)  For the analysis of diphenylnitrosamine, add 0.008%  NajS2O3 and adjust pH to 7-10 with NaOH
      within 24 hours of sampling.

(IS)  The pH adjustment may be performed upon receipt at the  laboratory and  may be omitted if the
      samples are extracted within 72 hours of collection. For the analysis of aldrin, add 0.008%
                                  Source: 40 CFR 136.3 Table H
                                               C-5

-------
TECHNICAL APPENDIX C
                                  TABLE IA—LIST OF APPROVED BIOLOGICAL TEST PROCEDURES

Parameter and untts
Bacteria:
1 CoMorm (fecal) number per
lOOmL
2. GoKorm (fecal) in praaance
of cNarint number per 100
ml
3 CoNtorm (total number per
100 ml
4 CoMonn noM In rjrseenre
Ot chlorine, number per 100
ml

par lOOnt



Method1
MPN, 5 tub*. 3 deuBon; or.
membrane inter (MF)4. angle
(tap.
MPN, 5 tub*. 3 dMon; or,
MF«. single stop.-.
MPN 5 tub* 3 OHution; or MF 4
•not* step or two stop.
MPN 6 Mb* dMon; or MF*
vMh enrichment.
MPN, S tub* 3 oVutton; MF4:
or. plate count
p 138 	 , 	 - 	 	
p 143 	 ,. 	


EPA>
Page
132.
p. 124 „
p. 114
p. 108 .
p. 114
p. 111
p. 138-



Reference (1
Standard
Methods 15th
Ed
»n«c
009
DQ8A ,. ......
gnoA
OMA
80B(A+A.5c)
010A
91 OB
B1OC

Mmoo Nimbi
ASTM










rorP«o«)
USGS

B-0060-77.





80055-77 •


  Table IA Notes
  'The method used must be specified when results are reported.
  'jmrobkHugcsl Methods for Mentoring the Environment, Water and Waste, 1978", EPA-600/6-7B-017. US. Cmironmen.
tal Protoceon Agency.
  •Qreaaon. P£,  ef at. "Method*, tor Ceaactton and Analysis of Aquatic  Biological and Microbiological Samples,  "US.
Qeotogteal Survey. Techniques of Wster-fleeources tnvesBgations, Book 5. Chapter A4. Laboratory Analysis. 1977.
  •0.45 pm membrane fitter or other pore soe certtfied by the manufacturer to My retain orgaraeme to be cuMvated. and free
 	  uUMerMrawimtherg/oVrlhanddeMtopmanL
                            hraque usually yields tow   '
                  ••Since the inembrane fitter technique usual* yieUa
                method wM be required to reaotve any conBweniaa.
> and variable recovery from i
                   Approned orty it ctaaolutjon of the KF Streptococcus Ager (Sectan S.1. USGS Method 6-0055-77) is made in • ooibng
                    bcth to Bvotd KOfcNnQ
                                  TABLE IB—LIST OF APPROVED INORGANIC TEST PROCEDURES

PsWMtaf ( unto •nd fiMrthoti

•nd point or ptMnoaphttDitasn •nd point.
2. Akaknty. at CfXX), mg/L
to pH 4.5, manual, or.
Automated
3. Akimnum— Total.* mg/U Ogeetion'
tolowedby:
AA owed aspratton
AA furnace 	


4 Ammoria (as N), mg/U Manuel distil-
Mtton (at pH 9.5) > fokowed by:
TlfeMiqn
FJMim)* 	


5. Andmony-Tot.il*. mo/L OioMflon*
fafcxmdby:
AA dract MT^****1
AA fumaosi of 	 < 	 	

0 Arwnp Total" mg/L ntpttion'
toiovMdby
AA QsiMout nyrfcidt
AA Iwnao*

CfilOnmtmc (STX1Q
7. Barium-Total.' mg/U Ogeslton ' fol-
lowed by:
AA furnace
(CP or 	 	
DCP
a. Barykun-Total.* mg/U Dtosstton'
toMowed by:
AA drect aepiratton
AA furnace 	

EPA
1979"
305 1
310 1
3102 ...-„-
202.1



390?
3SO? , 	
350i__. 	
350 J.
350.1

TfM1
?04 2

2M$
206.3
20&2.

206.4 	
2081
20*2


210 1

Rl
f^i^
flMflnooK
iemED
402(4 a)
jng

303C
304


*17A , ,..--,
41TB
417O
417 E or F...
417G

303A
W


303E
304

307B 	
303C 	
304


303C
304 	
iterance (method
ASTM
1087-82(E)
D1 007-82(6)






D1428-79(A). .

O1426-79(D) 	
D1426-79(C). .





02972-84(8)


D2972-84(A) —




03845-84(A)

No. or page)
USOS'

M 030-84
1-2030-84
1-3051-85




1-3520-84..


M523-84





1-3082-84


1-3060-84
1-3064-85 	



1-3095-85


OVier

33.014'



200.7.4
Note 33.

33.057.'
33.057*



Mots 6


20074



20074



200.7.'
Note 33.


                                                                C-6

-------
                                              TECHNICAL APPENDIX C
TABLE IB—LIST OF APPROVED INORGANIC TEST PROCEDURES—Continued
Parameter, unto end method
K5P 	 „ 	 	
OCR V ----- -, 	 - 	

9. Biocheirncel oxygen demind (BOD.).
mg/L
DneotyeO' Oxygen Depletion 	
10. Boron— Total. mg/L
Cotonrnvtnc (OFcmmfl)..— 	 ...
ICP or-.™-— "«—." 	 .— 	 T 	 mt
OCP
11. Bromida, mg/U TUnmrtic 	
12. Cadmiunv— Total.* mg/L, Digatfion "
toNowadby:

ICp 	
pTP
Vottamatry ** or

13. Ctfctam-TMI.* mg/L DigeMon*
toMowed byt
AA dvecl eit'^l''!"
ICP 	
OC^ C 	 	
Tt>jtnt*'h. (FPTA) ,
•4. CafDOfiaoaOUB OlOCnamicai OKypan
demand (CBOO.), mg/L »: Diaiohad
Oxygen DeplKon wtth iitfcjlimi in-
NbNor.
15 Chemnl ooiygtn demnd (COD).
mg/L:
THiHiiHiL. or 	

meted
16. Chloride. mg/L
iff (Mtrure nHritt), or
CntorimttrtG manual 0r 	

17. Chtorina Total fMdual, mg/U

Starch and pont dract
Back iMvaon awwr ano
poM '«. or.
DPfi-fAS , 	 - -
T^JLMJItJJU JlTltj UULAII u' f^Bfl
apvcvopnnDnieinCi I^T^ 	 _
Or Eleetood*
18. Chramum VI daeolved. mg/L 0.45
AA eheliliuii emucllon. or 	
19. Chromum— ToM.» mg/L Digerton •
Wkmedby:
AA rtvtcl a^iiniiiBi

AA fumm
•£•„,.
OCP Of
Cofonniatnc (PipnanylcaroaeBoai^.^ 	
20. Cobett— Total," mg/L Digeieon*
Mowed by:
AA direct tnpntion 	
AA furnace 	
ICP. or 	
OOP 	
21. Color pIMmum cobett unto or dom-
nm wBvelenolti, hue. (ummerioe
purity:
Cotonmetnc (AOMI), or 	
SpectrophotorneMc 	

EPA
1979"

	
405.1 	
320.1 	
213.1 	 	
213.2. 	



»1«1


21&2 	
410.1,
410.2. or 	
AinA

3253

3251 or
afS _g _.,.,..,.
330 1
330.3
run
330.4-
330A-__~_.
210.4 	
91*^


219.1 	
219.2.
	
110.1 	
110.2 	
110J 	


Std
metnods
letfiED
309B
507 	
404^,™^ 	
303 A or B...
304 	


310B
303A

31 1C 	
507(5.e.6»_
508A

407B 	 _
407D
408C 	
408A

*o«n
At»f

3038 	

303A

904


312B 	
303 A or B_
304 	

204D 	
204A.._
204B 	
ASTM
	
	
D124e42(C).....
D3557-84(A
or 8).


D3657-84(C) —
D511~64(B)


D511-84(A)

D1 252-83 	

DS12-81(A) 	
D512-81(C) .
D1253-76(A)
01253-76(8) —
Pert 18.3 	





D1687-84CD)




Ot687^4(A) 	
D3S5B-84(A
orB).
	



No. or peg*)
USGS'
	
1-1578-78 ' 	
(-3112-85 	
M 125-84 	
1-3135-85 or
(-3136-45.



1-3152-85




1-3580-84 or
1-3562-84.
(-3561-64
M183-84
1-1184-84 	
M 187-64 	
1-2187-64


	

M 232-84 	
1-3236-85




(-3238-85 or
(-3240-850.
	

1-1250-84 	
Other
200.7"
Note 33.
33.019 '. p. 17."
200.7.«
Note 33.
p. S44.«
33.069.*
p. 37.«
200.7.«
Note 33.
200.7.«
Note 33.
33.034 ». p. 17.«
Notei 12 or 13.
33.067.*
Note 15.
307B."
33.089.*
200.7.'
Note 33.
p. 37."
200.7.'
Note 33.
Note 17.
                        C-7

-------
TECHNICAL APPENDIX C
                  TABLE IB—LIST OF APPROVED INORGANIC TEST PROCEDURES—Continued


Parameter, untts and method
22. Copper— Total.' mg/U DigeaMn'
Mowed by:
AA dkvct itanHon
AAhimew
ICP -- 	 - 	 	 - 	
DCP or
Cotomwtric (Ncocuprom*). or (Bt-
Cvn*Momnata).
23. Cyanida— Total mg.L Manual diatif-


Automatad1*

mg/U Manual d-ettUatnn with MgO,
foNowad by trtnmainc or ipactrophoto-
fiiatnc.
25. Fluonda— Total. mg/L Manual otott-
Wwn* tottowad by:

Cokmrnetic (SPAONS) 	
28. GoW— Total,* mg/U Digaation • (o»-
towadby:
AA drat Mention 	
AA furnace, or 	 	
npp
27. Hardneaa— Total, u CaCOi mg/U
TNflmatric (EDTA). or C* ptut Mg aa
the* carbonate*,- by inductively
raton. (See Parameter* 13 and
33.).
28. Hydragan ion (pH). pH untK
Bacbojnatnc, fnaaauratfiant, of ........
Automatad alaelioda 	 	 -.
29. Mdkjm— Total", mg/U Digaanon* tol-
lowad By*.
AA kvnaca 	
30. Iran- Total,' mg/U Dig-Mon' tol-
kMMdby:

tfyp
pfj» nr

31. Kialdahl ntrogan— Total, (u N). mg/
U Oigettion and d«tillation foNowad
by:
Turation 	 	 	
NasaMnzation. 	
Electrode 	
Automatad phanate 	
Sam-automated block dtgastor. or 	
PoMntnmetnc.. 	
32. Laad— Total," mg/U Digestion ' M-
loi-Mdby:
AA direct aaprabon 	
AA lumaca
tCP._ 	 	
DCP 	
Vonametry." or 	 	 	
Color-metric (Drthoone) 	
33. Magnet-urn- Total,' mg/U Oga»-
«on > followed by:
AA direct atpntion 	
ICP ... .
DCP. or 	 _.
Gravimetric — 	
34 Manganese— Total.' mg/L. Diges-
tion « toUowed by:
AA direct aapnlnn 	 	
AAfumaoe ,
ICP 	
DCP. or 	 	
Colonmetnc (PerauMata) or 	 	
iPenodnte).... .._ 	



EPA
1979 •«
7901
?20Z


	

3352
335 3 	
335 1
3442 ,

340.1 	
340.3— __
231 2 	
231^ 	 .

i?)1
1302 	
150.1 	
2351
235.2 	
2361
2342



351.3 	
351.3 	
351.3 	
351.3 	
351.1 	
351.2 	
351 4
239.1 	
239.2 ...




242.1 	

243.1 	
243.2 	







SJd.
mattKxte
18th ED
303 A or B
304 .._


313B 	
412B

412C 	
412D

412F
413A 	
413B

413C 	
413E
303A 	
304 	


314B 	
423 	 __.
303A
304 	
303 A or B
304 ...


315B __
420 A or B..
41 7D.
417B..
417 E or F..



303 A or B
304



316B
303A 	

318B 	
304 A or B..
304


319B

C-8


ASTM
01888-84 (D
orE).


D1688-84(A) 	

D2036-82(A)
D2036-82(A). 	
D2036-82(B)
D1179-80IB) 	

D1179-«0(A) 	
	


01128-80 	
D1293-84(A
orB).
D1088-84 (C
orD).


D106B-84(A)
D35BO-«4(A) ._.
D3S90-84(A)
D3590-84(A)


D3590-84(A) 	
D3590-84(AX
D3559-84 (A
orB).


D3559-85(C)

D§11>84(B) 	

D511-77(A) 	
0858-84 (B or
C)


0858-84(A)


.

USGS1
1-3270-85 or
1-3271 -85.




1-3300-84


	 	 --•
M327-84

	 	 _.


1-1338-84 	 	
1-1588-84 	
1-3381-85




	 	


M551-78 '


1-3399-85





1-3447-85 	

1-3454-85 	







Oner
33 089 * p 37 •

200.7.«
Note 33
Note 18.

p. 22.'






Note 33.

33.082.'
33.006.'
Note 20.
33089'

200.7 «
Note 33.
Note 21
33051 «





33089 '

2007«
Note 33


33.089 '
2007*
Note 33
33 089 '
2007*
Note 33
33 126 '
Note 22


-------
                                              TECHNICAL APPENDIX C
TABLE IB—LIST OF APPROVED INORGANIC TEST PROCEDURES—Continued
Parameter, unfa and method
35. Mercury— Total '. mg/L
Cold vapor, manual or 	 — 	
Automated
36. Molybdenum— Total.* mg/L Diges-
tion * followed by:
AA direct atpntaon 	
AA fumac*
)QP Qf
DCP
37. Nickel— Total,* mg/L: Digestion ' fol-
lowed by:
AA direct aspiration 	 	 	 	
AA furnace 	 	
ICP
DCP or

38. Nitrate (as N), mg/L Cotonmetnc
(Bruone sutfate}. or Nitrate-nitnte N
mnus Nitnw N (See parameters 39
and 40).
39. Nftrate-nttme (as N), mg/L Cadmium
reduction, Manual or
Automated or

40. Nitnte (as N). mg/L Spectrophoto-
matnc.
Manuiri or »™««.».... 	 	 	
41. CM and graaia Total racovarabie,
mg/L: Gravtmatnc (axtracton).
42. Organic carbon— Total (TOC), mg/L
Combustion or oxidation.
43 Organic nflrogtn (at N) mg/L' Total
Kj*ldaN N (Paramatar 31) mn» am-
monia N (Paramatar 4.).
44. Orthophoaphate (as P), mg/L Ascor-
bic acid method:
Automated or 	
or Manuil two reagent 	
45. Osmium— Total *. mg/L: Digestion «
followed by:
AA dUet aspialion, •*•
AA furnace
40. Oxygen di solved. mg/L WMder
(Azide: modification), or
47. Paltadun— Total.* mg/L Digestion *
followed by:
AA drect aspiration .. 	
AA furnace 	
DCP 	 _ ..
48. Phenol*. mg/L
Manual disttHatton *• 	
Followed by:
Colonmenc (4AAP) manual, or....
Automated " 	
49. Phospnorus (etemental) mg/l_ Gas-
SO. Phosphorus— Total. mg/L Persulfate
o!>gastion foHowad by
Manual or 	
Automated ascorbic acid reduction,
or.
Semi-automated block digester 	 _.
51. Platinum— Total.' mg/L Digestion*
followed by
AA dvect aspration 	 	
AA tumace 	
DCP

followed by:
AA direct aspration 	
Inductively coupled plasma 	
Flame photometric, or 	 	 ..
Cokxtmetnc (Cobaltmitrate) 	 	
53. Residue— Total. mg/L Gravimetric.
103-105'C.
54. Residue— filterable. mg/L Grawne-
tnc. 180-C.
55. Rewdue— nonMterable, (TSS). mg/L
Qranmetnc. 1 03-1 OS 'C post waahng
of residue.
Reference (method No or page)
EPA
1979"
245.1 	 	
245.2....
246.1 	
2462 .


249.1 	
249.2 	


352.1 	
3533 	
353.2 	
353 t ..
354.1 	
413.1 	
4151 	 	

365.1 	
365J 	
365-3
fSfl 	
?922
360.2 	
360.1 	
253.1 	
253.2. 	
420.t 	
420.1 	
420.2 	
365.2 	
365.2 or
365.3.
365.1 	
365.4 	
255.1 	
255 2. 	

258.1 	
	
160.3-.... 	
160.1 	
160.2 	
Sid
nwtfiods
16th ED
303F 	
303C 	
304


303 A or B..
304 	

321B
418C 	
418F 	
419 	 -.
503A 	
505 _. _.
424G 	
424F 	
303C 	
304
421B 	
421 F 	
	
424C(III) 	
424F 	
424G ..

303A 	
304

303A 	
322B 	
209A 	
209B 	 	
209C 	 	
ASTM
03223-60 	
	


D1686-84(C
orD)


DB92-71 	
D3867-85(B) 	
D3867-8S(A).....
D1254-67 	
02579.65 (A or
B).
D515-82(A) 	

0888-81(0) 	
Dt 763-60 (A
orB).
D515-82(A).. 	




	
D1 428-821 A)

	
USGS '
1-3462-84 	
(-3490-85 	 	


1-3499-65 	


1-4545-64 	
1-4540-64 	 	
1-4601-64 	

M575-78 ' 	
M576-78 ' 	
1-4600-64 	



1-3630-64 	


1-3750-84 	
1-1750-84 	
-3765-64 	 „
Other
33.095'
200.7'
Note 33
200.7*
Note 33.
33.063 '. 419D ".
p. 28.*
Note 24.
33.044 ', p. 4.**
33.116. •
33.1H. «
33.028.*
p. S27.*
p. S28.«
Note 33.
Note 26.
Note 26.
Note 27.
33.111.'
33.116.'
Note 33.
33.103.'
200.7.«
3178."
                        C-9

-------
TECHNICAL APPENDIX C
                TABLE IB—UST OF APPROVED INORGANIC TEST PROCEDURES—Continued


Parameter, unMs and method
56. nsurtie Kllleefilii mg/L Volumet-
ric, (Imhotl cone) or grawnssnc.
57 Residue VrtsMe mg/L Grsvwne
trtc, 55CTC.
56. Rhoojum— Total ', mg/L Digestion '
Mowed by:.
AA direct aspiration, or 	

SB. Ruthenium— Total *. mg/L Diges-
tion * Mowed by:
AA furnace 	 - 	 	
60. Selenium— Total '. mg/L Digestion '
followed by:
AA furnace
Inductively coupled plasma, or 	
AA gaseous hydride 	
61. S*ca— Dissolved, mg/L 0.45 micron
filtration fonowad tojr
Cotonmetnc. Manual or 	
Automated (Molybdosilicate), or 	 	
Inductively coupled plasms 	
62 Sever— Total," mg/L Digestion'
followed by:
AA direct aspration 	
AA furnace 	

ICP, or 	
DCP .. 	
63. Sodwm— Total.' mg/L Digestion'
followed by:
AA direct aspration 	 „ 	 „ 	

DCP or.... 	 	
Flame pholomeliic ...

r* «_.«* .. ^ . .
65. SuHate (as SO.), mg/L
chtoranrfate).
Gravimetric, or 	 	
66. SufMe (as S), mg/L
Trtnmetnc (ndms) or 	
Cotonmetne (methytene blue) 	
67 Sultite (as SOj) mg/L Titnmetnc
(ndme-iodate).
68. Surfactants, mg/L Cotonmetnc
(metnytene Woe)
70. Thallium— Total », mg/L Digestion'
followed by:
AA lumaee or 	

71. Tin— Total', mg/L Digestion9 fol-
lowed by:
AA direct aspration. or 	
AA fumac*
72. Titanium— Total,9 mg/L Digestion9
followed by:
AA furnace
DCP 	
73 TurtKkty, NTU Nephelometnc 	
74 Vanadium— Total.9 mg/L Digestion '
AA furnace 	
ICP 	
DCP. or 	
Cotonmetne (Gallic acid)
75. Zinc— Total,9 mg/L Digestion' fol-
lowed by:
AA direct aspration 	
AA furnace

DCP or ~
Culorinistffc (DlUiiimie) or 	 m-




EPA
1879"
1605
1604
265 1
?**?
267 1

270.2 ... .

270.3 	
370.1 	

272.1 	
272.2 	



273.1 	



120.1 	

375.1 _ ..
375.3 	
375.4 	
376.1 	
376.2 	
377.1 	
425.1 	
170.1 	
279.1 	
279.2 	 _...

282.1 	
282.2
2631
283.2 . .

180.1 	
2861
286.2 	



289.1..... 	
289.2





a*

Std.
nietliuds
16th ED
208E 	
2090
303A 	 	
304.
303A
304 	 	
304

303E 	
425C 	

303 A or B. .
304 	 „ .



303A 	


325B
205....


426 A or B...
427D 	
427C 	
428A
512B 	
212 	
303A...
304 	

303A 	
304 	
303C
304 ..

21 4A 	
303C.
304 	


327B
303 A or B...
304


3260




ASTM





"


D3859-*4(A| 	
D659-80(B) 	









D1428-82(A)
D1125-82(A) ..


D616-82(A) 	
D516-82(B) ...
D1339-84(C) ..
D2330-82(A) 	



	



D1 889-81 	




D3373-84(A)
D1691-84 (C
orD)







USGS'
1
1-3753-84



«—•——••.•—......—.-...


1-3667-64 	
1-1 700-84 	
1-2700-84 ...

1-3720-85 -




1-3735-85 ....



1-1780-64 ....


	 	
1-3840-84 	
	 — 	 — -



1-3850-78' 	



1-3660-84 	





1-3900-65 	







Other







2007*

200 7 4
33 089 * p 37 •

319B '•
20074
Note 33
33107*
20074
Note 33

33 002 '


33.124.'
426C'"
228A.'°
Note 31.


20074



Note 33.



200 7.4
Note 33.

33.089 « p. 37."
200.7 *
Note 33.

Note 32.

                                            C-10

-------
                                                                                        TECHNICAL APPENDIX C
              TABLE IB—LIST OF APPROVED INORGANIC TEST PROCEDURES—Continued


   1 "Methods for Analys* of Inorgane Substance* in Watar and Fluvial Sediments," U.S. Department of the Manor. U.S.
 OaotagKal Survey. Optn-Fae Report 85-485. 1886. unless otherwise stated.
   '"Official  Methods of  Analysis  ol DM Asaooatxxi  of Offtaal  Analytical Chamsts."  methods manual.  14«h ed. (1885).
    For th» datarminalien of total metals Ihe sample it  not NMrad before processing. A digestion procedure • requred to
 sokjbttze suspended malarial and to destroy posacxe  organic-metal complexes. Two digestion  procedures ere given n
 "	   ~    		J	, 1878." On* (Mction 4.1 J), a • vigoraut digeston using ratnc aad. A
                                                          1.4) it preleiied; however, the analyst should ba cautioned
"Methods tor Chameal Analysis of Watar and Wastes, 1878." Ona ((action 4.1 J), • a vigoraut digeston uamg ratnc aod. A
                                                                                   uraii to be employed, it it
                                                                matt! it in a reactive ante. In thoaa amiaoont, the
                                                          doat tha aampl* go to drynaa*. SampMt oontanng larga
 _ 	   	             ld alao banadt by thit vlgorout dgeabon. Uaa of tha graphite tumaoa technique, nductvely
 coupled plasma, at we« at determinatione for oartain alainanii men at araarac. tha noble metals, marcury, islsraum, and
 Wanum no/an a modified digaation and in all caaaa tha mathod wnta-up ahouM bt conaultad for apaojfie nefcucbon and/or
  MOTE «tha djgtttnn nckidad in ona of tha olhar approved references is cJffarent than the above, the EPA procedure mutt
 be used

  Olaaolvad malala ara dafinad a* thoaa conttKuant* which  wiN pan through t 0.45 micron membrane War. Foaowng
 tWaaon of tha sample, tha rafaranoad procedure for total matalt mutt ba followed. StmpM digestion for okssotved metals may
 ba omttlad for AA (diract aapranon or gnpMta tumaoa) and tCP analyaaa providad  tha aampla solution to ba analyzed maalt
 tha fallowing criteria:
  a. hat a tow COO (<20)
  b. • viajbly transparent with a turbid*y maaaunMMnt of 1 NTU or lees.
  c. it cotorieet with no perceptable1 odof, and
  d. it of ona fcqud pnata and fnw of particulata or auapandad  matlar toltowng adaWcatnn.

  « The tul laxt of Mathod 200.7. "Induettvaly Couplad Plaama Atomic Eiriaalon  SpauromaBic Mamod for Ttaoa Elaniant
 Analyala of Wttar and Watlaa." la givan at Apoandix C of thit Part 136.
  • Manual dMMion • not raqurad M uomparabBty data on nyaaaiilili»a atHuant  tampfat ara on company Ma to thow that
 this  pralimlnary dotMMon ttap » not naoaaaary; howavar. manual dMNalton will ba raqurad to naolm any controvamat.
  •Ammonia. Automalad ElacMd* Mathod. Indutlrial Mathod Numbar 378-75 WE  datad  Fabruary 18.  1876, Tachnoon
 AutoAnalyzar II. Tachnioon InduaMal Sytlama. Tanytown, NY. 10581.
  'Tha approvad mathod it that  cnad in "Mathodi for  Dalaiimmiiuii of Imganic Subataneaa n Watar and  Fluvial
 Saolmantt". USGS TWRI, Book 5. Chaptar At (1978).
  • Amancan  Natontl Standard on Prmtographic Pnxaaalng Effluantt. Apr. 2. 1875. AvadaUa from ANSI, 1430 Broadway.
 Naw York. NY 10018.
  • "Salaeitd AnHyttcal Malhedt Approvad and CHad by tha UnHad Statat Envnnmantal Pro«a<.Uun Agancy." Supplaniant to
   • Tha uaa of normal and oWarantial putaa vonaoa rampt to mcnaaa MnaMivity and raaokition it arrantaula.
                          J oxygan damand (CBOD.) i
 total BOO." Tha adoWon of tha ifuilkalion inhibitor la not a procadural option, but mutt ba mdudad to raport tha CBOD.
  11 Carbonaceous tuocnaiistal oxygan damand (CBOD.) must not ba oonfuaad with tta traditional BOO. laat wMeh maaturat
paranatar. A dttcha/gar whoaa panrct raquraa raporttno tha tradittonal BOOi  may not uaa a nitrification inhiullui' i
pmoadura tor raporang tha raauNa. Onty whan a dachargafs ptmt spacrtcaKy atataa CBOD, • raqund. can ma parmtMa
raport data using tha nitrification nnfcnor.
  >• OfC CMmcal Oxygtn Damand Malhod. Ooaanography totamatiooal Corporation. 512 Waal Loop. P.O. Bex 2880. Coasga
Station, TX 77840.
  '• Chameal Oxygan Damand. MMtnd 8000. Hach Handbook of Walar Anatyn. 1878. Hach chamcal Company, P.O. Box
388. Lovaland. CO 80537.
  '• Tha back wraoon mattnd wM ba uaad to raaotva caiauvarsy.
  "Orion Raaaareh tnstrucMn Manual Raaahal CMorina Etoctroda Modal 87-70. 1877, Orion nniarcn Inoorpuislad. 840
Mamorial Drtva. Cambndga. MA 02138.
  •• Tha apprevad mathod ia that crtad.m Stsnotn/ Mafnoi* Dor In* Ecamnaabn of Wmltr ana Wttt,mmHr. 14th EdWon.
1878.
  " National Council of tha Papar tnouttry tor Air and Straam Improvamam. (Inc.) Tachnical Buaattn 253. Dacambar 1871.
  " Coppar. Biocmcnoinata Mated, Malhod 8508. Hach Handbook of Walar Analysis. 1878. Hach Chameal Company. P.O.
Box SaTlovaland. CO 80537.
  '• Attar tha manual dMMatkm ia eomplalad. tha auloanalyxar manifolds in EPA Mathods 335.3 (cyanida) or 42CL2 (phanolt)
am asnpMad by connacting t
GC/MS
62S. 1625
625. 1625
•624. 1624
HPLC
610
610
Other

                                                    C-ll

-------
TECHNICAL APPENDIX C
          TABLE 1C—LIST OF APPROVED TEST PROCEDURES FOR NON-PESTICIDE ORGANIC COMPOUNDS—
                                        Continued


4. Acrytonrtrite — 	 	 „ ..
5 Anthracene- 	
6 &arg*m
7 DiiiiiJim
8. Benzo(a)anthracene 	
9. Benzo(a)pyrene ...___ «^.....™«.™ 	 „._ 	
10. BenzcXb)fluoramhene 	 	
11. Benzo(g.hJ)perylene 	 	 « 	
12. Benzo(K)f!uoranthertt 	 	 	 	
13. Benzyl chloride 	
14. Benzyl butyl phthalate 	 	 	 -.
15 Bi^2-chtoroethoxy) methane 	
16 Bia(2-chloroethy1) ether 	 „ 	 „ 	
17. Bis(2-ethylhexyl) phthalate 	
1 9. Bromotorm..™-^™.- — „.....„... 	
21 4-Brofnophenytphenyl ether 	
22. Carbon tetrachlonde 	 _ 	
24 ChtotubeonHMi
25 Chloroethane 	
26 2-Chtoroethy»viriy1 ether 	
28 Chlorornethane 	 	


31. 4-CMcfOPr.eny.phenyt ether 	
32. Chryaene 	 	 	
33. Dtoenzc4fch)onthracene 	 	 ~ 	 	 	
35. 1 ^-DtcritofObenzene. 	 ™ 	 	
36 1 3-Dtchterofr*n?y*

36 3 3 -DtchtoropefgMtnB
39 DichlorodrthioforiMrthang
40 1 1 -Oichtofoetfiane
41 1,2-Dichloroethane
42 1 1-dchloroethene 	 	 	 	 	 	 „.
43 trana-1^-0ichloroeth*ne

45 1^-Oicntoropropane 	
46 tft 1 ,3-QicMflfqf*qp*>iy




51 O^n-bulyf phthalate - 	
52. D*-n-octyl phthalate „..„.
53 2.4-DMtrophenol... 	 	 	 «~ 	
54 2,4-Dtnrtrototuene „. 	
55. 2.6-Oinrtrotolueoe 	 	 	 ..
56 Epfehtomtrydnn - .-


60. Hexachtorobenzene 	

*5 IJHHrfVQfQftf
66 Methylene chloride

68. Naphthalene ....._™™..™...w™...........™™.. 	 .—
99 Nrtrobenezene 	
70 2-Nftrophenol

72. N-NttroaooVnethylarnine - .... 	
73. N-Nttroeodto-propytarnine ....„„.«.»».....„ 	

76 PCS- 101 6
77 PCB-1221 _ 	 	 	
73. PCS- 1232. 	 . 	
79 PCB-1242

61 . PCB-1 254 	 	
62 PCS- 1260 i r



•Ml iTienana
EPAI
GC
603
610
602

610
610
610
610
610

606
611
611
606
601
601
611
601
604
601.602
601
601
601
601

604
611
610
610
601,602,612
601. 602, 612
601 602 612

601
601
601
601
601
804
601
601
601
808
604
606
608
606
604
600
600
602
610
610
612
612
612
612
610
60S
601
604
610
608
604
604
607
607
607
611
808
608
608
608
608
608
606
604
610
604
610
Mlhod Nunber » '
QC/MS
•624 1624
625. 1625
824 1624
•625, 1625
625 1625
625. 1625
625 1625
625. 1625
625, 1625

625. 1625
625, 1625
625. 1625
625. 1625
624, 1624
624 1624
625. 1625
624, 1624
625 1625
624, 1624
624, 1624
624, 1624
624. 1824
624, 1624
625 1625
625 1625
625, 1625
825, 1625
625, 1825
624, 625, 1625
624, 625, 1625
625 1624 1625
625. 1625

624. 1624
624 1624
624, 1624
624 1624
825 1825
624, 1624
624 1624
824 1624
625 1625
625 1625
625 1825
625, 1625
625, 1625
625. 1625
825.1625
625. 1625
624 1624
625. 1625
625, 1625
625. 1625
625. 1625
•625. 1625
625, 1625
625. 1625
625.1825
624, 1624
625, 1625
625.1625
625. 1625
625, 1625
625 1625
625. 1625
•625. 1625
•625, 1625
625 1625
625
625
625
625
625
625
625
825 1825
625. 1625
625. 1825
625. 1625

HPLC

610

605
610
610
610
610
610

	 	 „ 	




	



	


610
610
	

605





•'" '" ~








	
	

610
610

610~



610



	





	

610

610

Other



Note 3 p V



Note 3 p 130
Note 6. p.
S102.




Note 3, p. 130;
Note 3 p. 130


Note 3, p. 130.





















Note 3 p. 130-
Note 6. p.
S102.




Note 3. p. 130;







Note 3, p. 43;
Note 3. p. 43:
Note 3. p. 43:
Note 3. p. 43.
Note 3 p. 43:
Note 3, p. 43;
Note 3. p. 43;
NoteS p 140-



                                            C-12

-------
                                                                                  TECHNICAL APPENDIX C
 TABLE 1C—LIST OF APPROVED TEST PROCEDURES FOR NON-PESTICIDE ORGANIC COMPOUNDS—
                                             Continued

PtYeVTWttT '
•7. 2A7^-T«tf«uhkiio<CMn 	
•8 1 l.?.y Trtrahtofotthirtit
M TcfraeMoroftft^^

91 1 ^ VTrtcWoiub+fMna
92 1 1 1-TricMore*tfw^
93 1 1 ,2-TricNjT ottfw>t
94 Trichtofotttttn*
95 TricMorafluorafTftthint
96 2 4 VrricNwophfnQ*


EPAH
GC
601
aoi
602
612
601
601
601
601
604
601

lethod Number » '
GC/MS
624 1624
624 1624
624 1624
625, 1625
624 1624
624 1624
624 1624
624
625 1625
624 1624


HPLC
	













Not* 3 p. 130-

Note 3 p. 130*

Note 3 p. 130-





  Tata* 1C Note*
  1 All parameters are iipreessd in nBcrogram* per »ter (|ig/L).
  'The (lid text of Method* 601-«13. 624. 625.  1624. and 1625, are given it Appendix A. Test Procedure* (or Analy** of
Organic PoMutants," of this Part 136. Th* standardaed te«t procedure to be ut*d to determm* the method detection Imit
(MDL) tor these MM procedures « grven at Appendix B. "Definition and Procedure tor the Determination of th* Method
Detection Unit," of ttw P»n 136.
  '••Method* tor Benzrtne; Chtonrated Organic Compound*. Periteehtoropnenol and Peioaoes in Water and Wastewater,"
U.S. Environmental Protection Agency. September. 1978,
  'Method 624 may b* extended to tcrern samples for Acratem and Aerytontnle.  However,  when they are known to be
pomnt the preferred method for thaw two compound* • Method 603 or Method 1624.
  'Method 625 may b* extended to delude berurtne. hexaditoroeyctopanteAene, rtntrosodrumethyamne. and N-ntrosoov
phenylamn*. However, when they are known M b* pieaent Method* 60S, 607. and 612. or Method 1625. are preferred
method* tor these compounds.
  • 625. Screening only.
  *"j»liCted Analytical Method* Approved and OMd by the Un
  'Each analyst must make an initial, one-erne, demonstration
                                                    I the* abrMy to generate i
                                                    : A of ttw Part 136) m ac
                                                                                         Sopptemera to

     -      .             -     - .        .       -  -     -          ._           .      .    "on and accuracy
•Hh Mameds 601-613, 624. 625, 1624, and 1625 (See Appendix A of ttw Part 136) m accordance with procedures each m
section  6X2 of each of these Methodi.  AddNnnally. each laboratory, on an on-going bases must spike and analyze 10% (5%
tor Method* 624 and 625 and 100% tor methods 1624, and 1625) of all sample*  to monitor and evaluate laboratory data
quatty in accoidance with sections 6J and 8.4 of these Method*. Whan th* recovery of any parameter faKs outside the
          its,  ths analytiCBl remits tor that parametei  in the unspiked sample are suspect and cannot b* reported to
          i regulatory compliance.
  NOTE These wammg tents are promulgated as an "Interim final action with a request tor comments."
               TABLE ID—LIST OF APPROVED TEST PROCEDURES FOR PESTICIDES '
PMmstw no/L)
t iMdrin


3 AmtWrfiaWh ,-, ,, -, , 	
4 Atrtton -..« „ . —
6 Atnant


9 -r-QMr L1, , 	 	 u 	 — 	 -
9 £-BHC 	 , 	 , ..... , 	 	
m *&**.
11 01 1C (Unctant)

1? CntaVi
19 Cwtoivy1
14 GMbMrtwitMhiofi


16 CHorapfTiphiVn
IT ?L^p
te, 4,4'-ODD 	
19, 4.4'-O06 	

jn AA'-pnr

21 Dtnnlon-O
22. Dtmtnton-S 	 « «. 	 — 	 	
23. Didnon...............i.,Tr .................... 	 ....................
?A fv^fiTtn ,,.

OT OchtOfftn 	 , , 	 	
27 Dtooferi 	


29 Ptoratttion
no DtmHmLifi
31 Dtunn
9a? Cl.tllMUlf.W11

H-ji, i. .1
••wioo
GC__ _„
QC/MS
QC
TLC
GC
QC
QC
TLC
GC_ ......
QC/MS 	
QC_.
QC/MS 	
QC
QC/MS 	
GC
QC/MS
QC
TLC
QC
QC
OC-MS
TLC
ac
GC.
GC-MS 	
QC
GC/MS .
GC 	 .
GC/MS 	
GC. 	
GC..
QC 	
GC
QC
GC
OC
GC
GC/MS
GC
QC
TLC
GC
QC/MS 	
EPA»-'
606
625






606
•625
688
62S
606
•625
608
625




625


606
625
606
625
606
625


	



608
625



608
•625
Stand-
ard
Meth-
ods
ism
Ed 1
508A







508A

	
509A

509A





sose
509A
509A

509A



	

JS08A

50BA




SOSA

ASTM
D3086







O3086
03086
D3066
D3066



"




D3066


D3086



	


D3066





03086

Other
Note 3, p 7; Note 4 p 30

Note 3 p 83* Note 6 p S66
Note 3 p 94' Note 6 p 816
Note 3. p. 83; Note 6. p. 808.
Note 3, p. 63; Note 6, p. S66
Note 3 p 25' Note 6 p S51
Note 3 p 104* Note 6 p 864
Note 3, p. 7.




Note 3 p 7
Note 3 p 94* Note 6, p 860
frpn 4 p. 30- f4ota 6, p 873


fjpla 3 p 104* Note 6, p 864
Note 3, p. 115; Note 4, p. 36.
Note 3, p. 7; Note 4, p. 30.
Note 3, p. 7; Note 4 p. 30.

Note 3. p. 7; Note 4, p. 30.

Note 3, p. 25; Note 6, p. SS1.
Note 3, p. 25: Note 6, p. S51.
Nate 3. p. 25; Now 4. p. 30;
Note 6. p. S51.
Note 3, p. 115.
Note 4 p 30' Note 6 p S73
Note 3. p. 7.

Note 3. p. 7: Note 4. p. 30.

Note 4 p 3O Note 6 p S73
Note 3 p • Note 6 p 851
Note 3. p 104; Note 6 p S64
Note 3. p. 7.

                                               C-13

-------
TECHNICAL APPENDIX C
                        TABLE ID—LIST OF APPROVED TEST PROCEDURES FOR PESTICIDES >—Continued
Parameter (tq/L)
33 Endmutten •

14 Fnrtnsiftan Wfat-




37 FJhton. - 	 	 -.,--.
yt rjnunyi.
90 Fenuror>-TCA 	
40 tttijIatr^K

41 Heptechtor +|MHIH^

42, Itodhn 	 	 , 	 , , , 	 	 -
43 UnVfl0n 	 , 	 	
44 Malalhion.
4S. Methiocerb 	 	
46. Methoxyehlor 	 	 _..
47 Mexacafbate . 	
40 Ms ex
4B* Monuron....
SO. Monuron-TCA 	 „ -. 	 	 .
51, Naburon 	 	 	 _. 	
52. Paralhion methyl 	 _. 	 	
53, Paralhion 9111x1 	 • 	 • 	 — 	
f4 PCNB ----- — - 	


57 Pitun+fryn
ft Ptppmnr
$a Pmphtni
60 P^pmnr
61 Secbunieton
62.Siduron 	 	 .. 	

64 Slroban*
4$ SliMp,,, ... 	 , ..,., 	 ,. 	
44 2,4,5-T
?7 2.4,5-Tp (SilueX) ... 	
66 Ttrbuthyiarine 	

TO TlMI»«%l

Method
or.
OC/US
or
GC/MS 	
oc
GC/MS -
QC
GC/MS
QC
TLC
TIC „ ,
QC
GC/MS
GC____L_J
GC/MS
GC
TLC 	
GC
TLC 	
GC 	 	
TLC_.
GC
TLC 	
TLC... ...
TLC
GC 	 _
GC 	
GC.. 	
GC
GC
GC._- .„
GC 	
TLC
TLC _.. _
TLC
TLC 	
GC
GC 	
Tic
GC 	
GC. _.. „..
GC 	
GC
GC/MS 	
GC..

EPA"
006
•625
606
625
606
•625

625



606
625
606
625




	





	














606
625

Stand-
ard
Meth-
odi
IStti
Ed
60BA


SOBA


~ 	 """'''



SOBA

500A



S09A

SOBA
SOBA



SOBA
SOBA
SOBA









SOBA

5086
SOBB

SOBA
SOBA

ASTM
DQ066


D3066






03066

D3066





D3066





	
D3066













03066


Other
tensi In?






Not* 4, p. 30- Not* 6 p. S73
Not* 3. p. 104' Not* 6 p S64
Note 3 p. 104- Note 6 p S64
Note 5. p 7' Note 4 p 30


6. p. S73.
Note 4 p. 30- Note 6 p S73
Note 3, p. 104' Note 6 p. S64
Note 3 p 25' Note 4 p 30*
Note 6. p. S51.
Note 3, p. B4; NOW 6. p. S60
Note 3, p. 7; Note 4. p. 30.
Note 3, p. B4' Note 6 p. S60
Note 3 p 7
Note 3. p 104- Note 6 p S64
Note 3 p. 104' Note 6 p S64
Note 3 p 104 Note 6 p S64
Note 3 p. 25 Note 4 p. 30
Note 3, p. 2S.
NoteS p. 7

Note 3. p. 83; Note 6. p. S68
Note 3 p 63' Note 6 p S68
Note 3 p. 83 Note 6 p See
Note 3. p. 104- Note 6 p. S64.
Note 3, p. 64; Note 6. p. S60.
Note 3 p 63* Note 6 p S68
Note 3. p. 104; Note 6. p. S64.
Note 3 p 63* Note 6 p S68
Note 3, p. 7.
Note 3, p. 104- Note 6 p. S64
Note 3, p. 115; Note 4. p. 35.
NoteS. p. 115.
Note 3. p. 83; Note 6. p. S6B.
Note 3 p 7' Note 4 p 30
Note 3, p. 7

                 TtbtelDNote*
                 > PetlicidM «r» lisWd m thte tetato by common rwnw for trw comwiteno* of the reader. Additional pettKidei may be found
               under Table 1C. where entries are Med by chemical name.
                 ' The lull text of methods 608 and 625 are given at Appendix A. "Teat Procedures tor Analysis of Orgarac Pollutants." of
               this Part 136.  The standardized test procedure to be used to determne the method detoctxw kmtt (MOD tor these test
               procedures a gwen at Appendix  B. "Definition and Procedure tor the DMermmation of the Method Detection Unit", of this Part
               136.
                 • "Method* tor Benndne. Chlorinated Organic Compounds. Pentachtorophenol and PeModes in Water and Wastemter."
               U.S.  Environmental  Protection Agency, September. 1B78.  This EPA pubeeanon include* thwlayer chromatography (TLC)
               methodi.
                 '"Methods  tor Analysts of Organic Substances in Water," U.S. Geotogcel Survey. Techniques  of  Water-Resources
               Investigation*. Book 5. Chapter A3 (1872).
                 • The method may be extended to include a-8HC. S-BHC, endoeuffen I, endosuHan II, and endna However, when they are
               known to exist Method 606 is the preferred method.
                 • "Selected Analytical Methods Approved, and Cited by (he United States Environmental Protection Agency," Supplement to
                 ' Each antlyst must make an initial, one-time, demonstration of the* ability to generate acceptable precision and accuracy
               with Methods 608 and 625 (See Appendix A of this Part 136) in accordance with procedures oven m section 6.2 ol each ol
               these methods. AdoWonaNy, each labomtoiy, on an orvgong bat*, must spike and analyze 10% of all samples analyzed with
               Method 608 or 5% of HI sample* analyzed with Method 625 to monitor and evaluate laboratory date quafcty in accordance
               with Sections 6.3 and 6.4 of these methods.  When the recovery of any parameter fat* outexJe the warning kmits. the analytical
               results for that parameter in the unapeied sample are suspect and cannot be reported to demonsuate regulatory compliance.
                 NOTE: Thee* wamng *mH> em promulgated as an "Interim final eclton with a request tor comment*."
                                                                   C-14

-------
                                                                              TECHNICAL APPENDIX C
                TABLE IE—LIST OF APPROVED RADIOLOGICAL TEST PROCEDURES

Parameter and units
1 Alpha-Total pO per Mar 	
2 Alpha-Counting error, pO
per Mer.
3 Beta-Total pO per Met .. .
4. Beta-Counting error, pO 	
5. (a) Radium-Total, pd per
Mer
(b)"*Ra. pO per Mer 	


Methods
Proportional or scintillation
counter.
Proportional or sonMatnn
counter.
Proportional counter.—. 	
Scintillation counter 	


EPA'
9000 	
Append* B....
9000
Appendix B ....
9030 ».
903 1

Rde
Standard
methods
16th ed
703
703
703
703
705
706

rvnco (nMttw
ASTM
D1943-81
D1 943-81
01890-61
D1890-S1
D2460-70
03454-79

a No or page)
USGS>
pp 75 and 78 '
p. 79
pp 75 and 78 '
p. 79
p 81

  T*au IE NOTES:
  1 "Prescribed Procedures tor Measurement ol Raduactmty n Drafting Water," EPA-600/4-80-032 (1980 update). U.S.
EnwronmerWal Protection Agency, August I960.
  * Fahrnen, MJ. and Brown. Eugene, "Selected Methods of the U.S. Qeotogwal Survey ol Analysis ol Wastewaters." U.S.
Oeotcoxal Survey. Open-File Report 76-177 (1976).
  ' The method found on p. 75 measures only the dworyed portion while the method on p. 78 measures only the suspended
portion. Therefore, the two results mutt be added to obtain me "Wai."
                                              C-15

-------
                         TECHNICAL APPENDIX D
TECHNICAL APPENDIX D




     REFERENCES

-------
                                                               TECHNICAL APPENDIX D
                                    REFERENCES
APHA, AWWA, WPCF, "Standard Methods for the Examination of Water and Wastewater,"
           17th Edition, 1989.

America Society of Civil Engineers, "Design and Construction of Sanitary and Storm Sewers,
           Manual of Practice," New York, 1960.

Associated Water and Air Resource Engineers, Inc., "Handbook for Monitoring Industrial
           Wastewater," EPA Technology Transfer, 1973.

Federal Register, Vol. 55, No. 222, p. 48065, November 16, 1990.

Federal Register, Vol. 56, No. 195, p. 50759-50770, October 8, 1991.

Professional Publications, Inc., (Michael R. Lindeburg, PE), "Civil Engineering Reference
           Manual," 5th edition, Belmont, California, 1989.

Metcalf & Eddy, "Wastewater Engineering: Treatment, Disposal, Reuse," 2nd edition, McGraw-
           Hill Book Co., New  York, 1979.

National Institute of Occupational Safety  and Health, "Criteria for a Recommended Standard ...
           Working in Confined Spaces," U.S. Department of Health, Education, and Welfare,
           Public Health Service, Center for Disease Control, NIOSH, December 1979.

Occupational Safety and Health Administration, 54 FR 2408, June 5, 1989.

Ogden Environmental and Energy Services,  "Storm Water Sampling Protocol Manual,
           Procedures and Protocols for Facility Data Collection and Storm Water Sampling,"
           February 1992.

U.S. EPA, 40 CFR Parts 122, 123, and 124; National Pollutant Discharge Elimination System
           Permit Application Regulations  for Storm Water Discharges; Final Rule, November
           16, 1990.

U.S. EPA,  "Guidance Manual for the Preparation of NPDES Permit Applications for Storm
           Water Discharges Associated With Industrial Activity," EPA-505/8-91-002, April
           1991.

U.S. EPA,  "Guidance Manual For The Preparation of Part I of the NPDES Permit Applications
           for Discharges From  Municipal Separate Storm Sewer Systems," EPA-505/8-91-
           003A, April 1991.

U.S. EPA,  "Methodology for the Study of Urban Storm Generated Pollution and Control," EPA-
           600/2-76-145, NTIS No. PB258743, August 1976.
                                         D-l

-------
TECHNICAL APPENDIX D
U.S. EPA, "Methods for Measuring the Acute Toxicity of Effluents and Receiving
          Waters to Fresh Water and Marine Organisms," EPA/600/4-90-027,
          September 1991.

U.S. EPA, "NPDES Compliance Inspection Manual," May 1988.

U.S. EPA, "NPDES Compliance Monitoring Inspector Training:  Sampling," August 1990.

U.S. EPA, Region V, "Urban Targeting and BMP Selection," November 1990.

Woodward-Clyde Consultants and Ted Friel Associates,  "Guide for Industrial Storm Water
          Sampling," January 1992.
                                        D-2

-------
                         TECHNICAL APPENDIX E
TECHNICAL APPENDIX E



      GLOSSARY

-------
                                                                 TECHNICAL APPENDIX E
                                      GLOSSARY
Aliquot: A discrete sample used for analysis.

Biochemical Oxygen Demand (BOD): The quantity of oxygen consumed during the biochemical
    oxidation of matter over a specified period of time, usually 5 days (BOD5).

Chain-of-Custody:  Procedures used to minimize the possibility of tampering with samples.

Chemical Oxygen Demand (COD):  Measurement of all the oxidizable matter found in a runoff
    sample, a portion of which could deplete dissolved oxygen in receiving waters.

Composite Sample: Used to determine "average" loadings or concentrations  of pollutants, such
    samples are collected at regular time intervals, and pooled  into one  large sample, can be
    developed on time or flow rate.

Confined Space:  Enclosed space that an employee can bodily enter and perform assigned work, that
    has limited  means of exit and entry, that is not designed for continuous employee occupancy,
    and has one of the following characteristics:

       •  Contains or has a known potential to contain a hazardous atmosphere
       •  Contains a material with  the potential for engulfment of an entrant
       •  Has  an internal configuration such that an entrant could be trapped or asphyxiated by
          inwardly converging walls or a floor that slopes downward and tapers to a smaller cross
          section
       •  Contains any other recognized serious  safety or health hazard.

Conveyance:  A  channel or passage which conducts or carries water including any pipe, ditch,
    channel, tunnel, conduit, well, or container.

Detention Ponds:  A surface water impoundment constructed to  hold and manage storm water
    runoff.

Discharge:  Any addition of any pollutant to waters of the U.S. from any conveyance.

Effluent:  Any  discharge flowing from a conveyance.

Flumes:  A specially shaped open channel flow section providing a change in the channel area and/
    or slope which  results in an increased velocity and change in  the level of the liquid flowing
    through the flume.  A flume normally consists of three sections: (1) a converging section; (2)
    a throat  section; and (3) a diverging section.  The flow rate through the flume is a function of
    the liquid level at some point in  the flume.

Flow-Weighted Composite Sample: Means a composite sample consisting of a mixture of aliquots
    collected at  a constant time interval, where the  volume of each aliquot is proportional to the flow
    rate of the discharge.
                                           E-l

-------
TECHNICAL APPENDIX E
Flow-Proportional Composite Sample: Combines discrete aliquots of a sample collected over time,
    based on the flow of the wastestream being sampled.  There are two methods used to collect this
    type of sample.  One collects a constant sample volume at time intervals which  vary based on
    stream flow.  The other collects aliquots at varying volumes based on stream flow, at constant
    time intervals.

First Flush:  Individual sample taken during the first 30 minutes of a storm event.  The pollutants
    in this sample can often be used as a screen for non-storm water discharges since such pollutants
    are flushed out of the system during the initial portion of the discharge.

Grab Sample: A discrete  sample which is taken from a wastestream on a one-time basis with no
    regard to flow or time; instantaneous sample that is analyzed separately.

Head of Liquid: Depth of flow.

Illicit Discharge:  Any discharge to a municipal separate storm sewer that is not composed entirely
    of storm water except discharges pursuant to an NPDES permit and discharges from fire fighting
    activities.

Materials Management Practices:  Practices used to limit the contact between significant materials
    and precipitation. These may include structural or nonstructural controls such as dikes, berms,
    sedimentation ponds, vegetation strips, spill response plans, etc.

Municipal Separate Storm Sewer Systems:  A conveyance or system of conveyances including
    roads with drainage systems, storm drains, gutters, ditches under the jurisdiction of a city, town,
    borough, county, parish, or other public body.

Outfall: Point source where an effluent is discharged into receiving waters.

Point Source: Any discernible, confined, and discrete conveyance from which pollutants are or may
    be discharged. This term does not include return flows from irrigated agriculture or agricultural
    storm water runoff (see 40 CFR 122.3).

Reverse Meniscus:  The curved upper surface of a liquid in a container.

Runoff Coefficient:  Means the fraction of total rainfall that will appear at the conveyance as runoff.

Significant Materials: Include, but are not limited to, raw materials, fuels, solvents, detergents,
    metallic products, CERCLA hazardous substances, fertilizers, pesticides, and wastes such as
    ashes, slag, and sludge  that have potential for release  with storm water discharges [see 40 CFR
    122.26(b)(12)].

Storm Water:  Storm water runoff,  snow melt runoff, and surface runoff, and drainage.

Storm Water Discharge Associated with Industrial Activity:  Discharge  from  any conveyance
    which  is  used  for  collecting and  conveying  storm water which  is directly  related to
    manufacturing processing  or raw materials storage  areas at an industrial plant [see 40 CFR
    122.26(b)(14)].


                                            E-2

-------
                                                                 TECHNICAL APPENDIX E
Time Composite Sample: Prepared by collecting fixed volume aliquots at specified time intervals
    and combining into a single sample for analysis.

Turbidity: Describes the capability of light to pass through water.

Weir:  A device used to gauge the flow rate of liquid through a channel; is essentially a dam built
    across an open channel over which the liquid flows, usually through some type of notch.
                                           E-3

-------
                         TECHNICAL APPENDIX F
TECHNICAL APPENDIX F



     ACRONYMS

-------
                                                              TECHNICAL APPENDIX F
                                    ACRONYMS

BODj     Biochemical Oxygen Demand (5-day)
CERCLA  Comprehensive Environmental Response Compensation and Liability Act
cfm       cubic feet per minute
CFR      Code of Federal Regulations
cfs       cubic feet per second
COD      Chemical Oxygen Demand
COV      Coefficient of Variation
CPR      Cardiopulmonary Resuscitation
CWA     Clean Water Act
DOT      Department of Transportation
ECD      Electron Capture Detector
EMC      Event Mean Concentration
EPA      Environmental Protection Agency
ESE      Environmental Science & Engineering, Inc.
FWPCA   Federal Water Pollution Control Act
FID       Flame lonization Detector
FR       Federal Register
GC/MS   Gas Chromatography/Mass Spectometry
gpm      gallons per minute
H        Head
HC1       Hydrochloric Acid
HNO,     Nitric Acid
HPLC     High  Pressure  Liquid Cnromatography
H2SO4     Sulfuric Acid
IATA     International Air Transport Association
LCjo      Lethal Concentration
NaOH     Sodium Hydroxide
Na2S2O3   Sodium Thiosulfate
NCDC    National Climate Data Center
NIOSH   National Institute of Occupational Safety and  Health
NOAA    National Oceanic and Atmospheric Agency
NOI       Notice of Intent
NPDES   National Pollutant Discharge Elimination System
NWS      National Weather Service
O&G      Oil and Grease
OSHA     Occupational Safety and Health Administration
PCB      Polychlorinated Biphenyl
PE       Professional Engineer
ppb       parts  per billion
Q        Flow  Rate
RCRA     Resource Conservation and Recovery Act
SARA     Superfund Amendments and Reauthorization Act
SIC       Standard Industrial Classification
s.u.       standard units
TKN      Total  Kjeldahl  Nitrogen
TSS       Total  Suspended Solids
VOC      Volatile Organic Compound
                                         F-l

-------