United States Region 10 91 0979Ut> I 5711 Environmental Protection 1200 Sixth Avenue Agency Seattle WA 98101 September 1978 Waste water Treatment Plant Design Guidelines For Operability, Flexibility And Maintainability ------- 2 TABLE OF CONTENTS Section Page 1. INTRODUCTION 4 1.1 Design Summary 5 2. GENERAL 7 2.1 Plans 7 2.2 Specifications 7 2.3 Revisions to Approved Plans 10 3. DESIGN CONSIDERATION 11 3.1 Hydraulic Loading 11 3.2 Organic Loading 11 3.3 General 11 4. PROCESS UNIT DESIGN 16 4.1 Reliability 16 4.2 Influent/In-Plant Lift Station 16 4.3 Solids Grinding Equipment 16 4.4 Grit Removal 18 .4.5 Primary Clarifier 19 4.6 Secondary Clarifier 2Q 4.7 Aeration Tanks 22 4.8 Activated Sludge "Package Plants" 25 4.9 Activated Biofliters 25 4.10 Aerobic Digestion 26 4.11 Anaerobic Digestion 27 ------- 3 TABLE OF CONTENTS Section Page 4.12 Disinfection 30 4.13 Lagoon-Oxidation Ponds 30 4.14 Laboratory Facilities 31 4.15 Metering 32 ------- 4 WASTEWATER TREATMENT PLANT DESIGN GUIDELINES for OPERABILITY, FLEXIBILITY AND MAINTAINABILITY 1. INTRODUCTION Many municipal wastewater treatment plants have not met their designed treatment efficiencies. This has been in part due to untrained plant personnel and in part due to designs which can not;" for various reasons, be adequately operated and/or maintained. Operator training programs have been and are being initiated to alleviate the problem of untrained operations personnel. These guidelines are intended to supplement recognized design guidelines"^' such as ASCE-MEP-No. 36 "Sewage Treatment Plant Design," to insure that municipal wastewater treatment plants are designed in a manner which provides for operability, flexibility, and maintainability. These design guidelines will be used by EPA Region 10 and state agencies in the review of plans and specifications for construction of municipal wastewater treatment facilities constructed with the aid of federal funds. DEVIATIONS FROM THESE GUIDELINES WILL BE CONSIDERED ON A CASE-BY- CASE BASIS WHEN IT CAN BE SHOWN THAT THE DEVIATIONS WILL PROVIDE FOR EFFICIENT AND EFFECTIVE OPERABILITY, FLEXIBILITY, AND MAINTAINABILITY. ------- 5 1.1 Design Summary A design summary shall accompany the plans and specifi- cations when submitted for EPA or state agency approval. A preliminary draft design summary should be submitted prior to 10 percent completion of design. The summary shall include, but not be limited to,the following: a. Hydraulic and organic loadings—minimum, average, maximum and effect on each process unit for both dry and wet weather flows and initial start-up. b. Quantity and type of industrial wastes which the plant is designed to treat, and what factors of design are affected by the industrial wastes. c. Process unit dimensions and volumes. d. Flow rates and velocities within process compart- ments and piping at minimum, average, and maximum loading for both dry and wet weather flows and initial start-up. e. Detention time for each process compartment at minimum, average, and maximum flow rates for both dry and wet weather flows and initial start-up. f. Expected ranges of BOD,- and/or COD, and S.S. concentrations of all process side streams. g. Expected mixed liquor suspended solids (MLSS) concentrations, food/mass (F/M) ratios, and mean cell residence time (MCRT). ------- 6 h. Recycle flow rates—minimum, average, and maximum for both dry and wet weather flow conditions and initial start-up. i. List chemical additives and their control. j. List or denote in schematic form physical controls for each process compartment (e.g., gates, valves, weirs, measuring devices, etc.). k. Removals—effluent BODg and/or COD, and S.S. concentrations for each process unit handling solid and liquid fractions. 1. Process diagrams including: 1. Process units. 2. Interconnecting piping with direction of flow. 3. Flexibility including direction of flow. 4. Hydraulic profiles at minimum, average, and maximum flows for both dry and wet weather and initial start-up conditions. m. List of physical and laboratory control tests needed to control each treatment unit. n. Adequate description of any features not otherwise covered by the plans or specifications. o. Estimated staffing requirements, both initial and at design capacity for the entire facility, with a per shift breakdown when applicable. ------- 7 2. GENERAL 2.1 Plans The plans shall be drawn to a scale which will allow all necessary information to be plainly shown. Datum used shall be indicated. Locations and logs of test borings, when made, shall be shown. Detail plans shall contain plan view, elevations, sec- tions, and supplementary views which, in conjunction with the specifications and general layouts, provide sufficient infor- mation for the construction of the treatment facilities. The plans must include dimensions and relative elevations of structures; the location and outline form of equipment; loca- tion and size of valves, clean outs, and piping; water levels; slopes of piping and floors including tank bottoms; sump locations; ground elevations; hydraulic profiles; design parameters; and other information as necessary to fully des- cribe intended works. 2.2 Specifications Complete technical construction specifications shall accompany the plans. The specifications shall include, but not be limited to, the following: 2.2.1 All construction information not shown in detail on the plans which is necessary to indicate design requirements such as the quality of materials, workmanship, and fabrication of the project and the type, size, strength, operating ------- 8 characteristics, and rating of equipment, including machinery, valves, piping, and jointing of pipes; electrical apparatus, electronic and pneumatic control apparatus, wiring, and meters; laboratory fixtures and equipment; operating tools; safety equipment; construction materials; miscellaneous appurtenances; chemicals; instructions for testing materials and equipment as necessary to meet design standards; operating tests for the completed facility and/or separate units (wet testing is preferred); and start-up training requirements for the operating personnel for specific units as applicable. 2.2.2 The specifications shall require one (1) set of special tools for each different piece of equipment along with a list by name and part numbers of the special tools. A special tool is defined as a tool necessary to disassemble, assemble, or adjust the piece of equipment and which would not normally- be found in the treatment plant or municipal maintenance shop; duplication of tools must be avoided. 2.2.3 The specifications shall require equipment identifica- tion/specification tags to be composed of materials which will be durable in the environment to which they will be subjected. The tags should have stamped or cut lettering and be screwed, riveted, or bolted to the equipment. 2.2.4 A minimum of two (2) sets of manufacturer's operation and maintenance (O&M) manuals will be provided with each piece of equipment. The manuals will be delivered to the design ------- 9 engineer within sixty (bO) days after the equipment purchase order is signed. Where a manual also contains information on equipment not installed, the extraneous information will be marked out to avoid confusion. 2.2.5 The equipment manufacturer and/or vendor will provide for each piece of equipment a complete maintenance summary which wiII include: a. Name of manufacturer with address and phone number of nearest representative. b. Complete identification/specification tag data including serial number of equipment. c. A list of spare parts including part numbers and other information needed to order parts. . d. A complete listing of routine maintenance, including time intervals for lubrication, adjustments, etc., and a list of acceptable equivalent lubricants from at least three (3) different major manufacturers whose products are locally available. e. Weight of individual components of each piece of equipment weighing over 4b kg (100 pounds). It is recommended that the designer develop a suitable form to obtain the above information. Manufacturer and/or vendor response such as "see instruction manual" will not be acceptable. ------- 10 2.2.6 The specifications shall indicate clear lines of respon- sibility where components of a unit are provided by different manufacturers, vendors, etc. Also guaranteed performance of equipment and instrumentation will be required. 2.2.7 The specifications will indicate the ambient conditions and maintenance acceptable for equipment in storage and in place during construction prior to plant start-up. 2.2.8 The specifications shall provide a written program for meeting the level of treatment required of the owner by the state agency during construction. Treatment plant personnel should have input in developing the program and in approving deviations by the contractor. Deviations by the contractor will need approval by the state agency prior to their initiation. 2.3 Revisions to Approved Plans and Specifications All deviations from the approved plans and specifications affecting capacity, flow, operation of units or compartments, methods of process control, or level of treatment of existing facilities shall be approved in writing by the state agency (and/or EPA where required by regulation) before such changes are made. 2.3.1 At least one set of "As Built" plans and design summary (Section 1.1) will be provided to the state regulatory agency and two sets to the municipality within 30 days of completion of construction. ------- 11 3. DESIGN CONSIDERATION 3.1 Hydraulic Loading Where peak waste flows are expected to be greater than 2h times design flow, some form of flow equalization should .be considered when needed to prevent significant reduction of treatment efficiency. 3.2 Organic Loading The organic design of the treatment units will be ad- dressed in the same manner as hydraulic loading. Shock loading, industrial wastes, and process unit return streams must be given careful consideration. 3.3 General 3.3.1 Treatment units shall be arranged for operating conven- ience, flexibility and maintainability, and to facilitate installation of planned future units. 3.3.2 Control rooms should be designed and located to afford operators a commanding view of the plant and grounds as is practical. 3.3.3 All large buildings should have man doors on all sides, where practicable. 3.3.4 The prevailing wind should be considered when laying out the process units to prevent aerosols from blowing towards control and office buildings and to direct scum towards scum collection equipment. ------- 12 3.3.5 Process units should be located to provide access by locally available mobile equipment (cranes, front end loaders, trucks, etc.). 3.3.6 Process units should be designed to provide easy access for sampling. 3.3.7 Process tanks should have a minimum free-board of 0.6 m (2 feet). 3.3.8 When the outside of the peripheral wall of process tanks, channels, chambers, etc., is greater than 1.2 m (4 feet) above ground level or above water, a catwalk at least 0.76 m (2% feet) wide should be provided where access is needed. 3.3.9 Treatment compartments shall be designed in such a manner as to allow each individual compartment to be removed from service and/or dewatered without the need of removing other compartments from service. 3.3.10 Inside corners of treatment units should be filleted as needed to enhance circulation, reduce dead areas, and prevent deposition of solids. 3.3.11 Process units designed for parallel operation should have an adjustable method of equalizing or dividing the waste flows entering the units. Splitter boxes, channels, etc., should be designed to avoid creating septic conditions in unused portions or areas. 3.3.12 Process units, channels, etc., shall have dewatering sumps or drains to facilitate complete dewatering and ------- 13 cleaning. The drains must return to a process unit located upstream of the unit being dewatered. Where practicable, dewatering facilities should be capable of dewatering each unit within four (4) to eight (8) hours. 3.3.13 Bottoms (floors) of process units, channels, etc., should slope toward unit sumps or drains to facilitate cleaning when units are dewatered. 3.3.14 Building, gallery, dry well, etc., floors should slope toward floor drains. 3.3.15 Floor drains or sumps with sump pumps should be strate- gically located near sources of spills in buildings, galleries, dry wells, etc. 3.3.16 OSHA safety requirements shall be incorporated into all treatment facility designs. In addition, motor kill switches should be installed adjacent to motors where a breaker or control switch is not within sight of the unit. 3.3.17 Exterior equipment pads, walkways, etc., should be ade- quately sloped to prevent standing water. Surfaces should be slip resistant. Slip resistance will be required where oil may be present. 3.3.18 All piping should be painted according to the standard color code recommended by the Water Pollution Control Federa- tion, except as otherwise required by OSHA. 3.3.19 Large plants should have a loading dock on the plant site for loading and unloading delivery trucks. Overhead ------- 14 clearance must be sufficient to accommodate enclosed transport trucks. 3.3.20 Mechanical treatment plants larger than 189 cu m/day (0.05 MGD) should have storage areas for spare parts, cleaning agents, etc., and a shop area for routine preventive maintenance of the plant equipment. 3.3.21 Every reasonable effort should be made to standardize equipment to minimize confusion and maximize utilization of spare parts. 3.3.22 Valves located higher than 1.8 m (6 feet) above the floor level should have mechanical operators that provide for operation of the valve from an elevation of no higher than 1.5 m (5 feet) from floor level. 3.3.23 Valves should be marked with name or number by permanent tags. 3.3.24 Mechanical equipment (pumps, motors, blowers, etc.) where individual components weigh in excess of 45 kg (100 pounds) should be arranged to allow for a means of mechanically lifting the unit for the purpose of removal, installation, and/or maintenance. Weight of individual components will be listed on the maintenance summary sheet (Section 2.2.5). 3.3.25 Mechanical eqi/ipment requiring routine maintenance should have a minimum of 0.6 m (2 feet) clearance on all sides of the equipment where access for maintenance is ------- 15 needed. Take-down couplings should be used for inlet and outlet pipe connections. A convenient method of removing equipment from buildings, tunnels, etc., should be considered. 3.3.26 Oil filled stationary equipment (hydraulic controls, pumps, blower gear drives, etc.) should have built-in catch basins or channel grooves to contain any leaking oil. Units will have drain valves with safety plugs; drains should be piped for access to drain pans. 3.3.27 Exposed water lines, seal water tubing, pneumatic and hydraulic control systems, etc., should be protected from freezing where ambient temperatures are below freezing. 3.3.28 Electrical controls should be protected from splash during wash down operations. 3.3.29 Critical process units should have malfunction alarms and, where possible, the alarms should be incorporated into a central dispatch system that is monitored 24 hours per day. 3.3.30 Portable lighting should be provided to allow for emergency equipment maintenance and repair at night. 3.3.31 Wash water system pressure should be a minimum of 3.5 kg/cm2 (50 PSI) at point of use; 4.9 to 6.3 kg/cm2 (70 - 90 PSI) is preferred. 3.3.32 Hose bibs should be located to allow washdown of process units with no more than 15.24 m (50 feet) of hose. A 2.54 cm (1 inch) diameter hosebib should be considered. ------- 16 4. PROCESS UNIT DESIGN 4.1 Reliability Design guidelines for reliability are provided in the following technical bulletins: 1. Design Criteria for Mechanical, Electric, and Fluid System and Component Reliability, EPA-430-99-74-001. 2. Protection of Shellfish Waters, EPA/9-74-010. 4.2 Influent/In-Plant Lift Stations 4.2.1 Influent and in-plant lift stations should be sized and controlled in such a manner as to prevent adverse hydraulic shock loading of subsequent treatment units. Generally in-plant on-off pumping of plant flow should not precede clarifiers. 4.2.2 Water sealed pumps should be considered where large amounts of grit are present in the waste flow. A method of removing scum and grit from the wet well should be considered. 4.2.3 Pump discharge piping should be designed to preclude settling of solids and grit into discharge riser of pumps not in use. 4.2.4 Dehumidifers or adequate ventilation should be provided in pump rooms to minimize corrosion. 4.3 Solids Grinding and Screening Equipment 4.3.1 When only one grinding device (comminutor, barminutor, etc.) or mechanically cleaned screen is used, it should be designed to carry the maximum expected flow. The design ------- 17 shall incorporate a means of bypassing the grinding/screen- ing device through a bar screen for maintenance purposes and include an emergency overflow weir whereby flows would bypass through the bar screen prior to overtopping or flooding the primary grinding/screening device. Where more than one grinding/screening device is used, the sizing and bypassing capability will be in accordance with reliability requirements (Section 4.1). 4.3.2 Rock traps should be considered in all channels upstream of grinding devices. The trap should be 0.3 m (1 foot) deep and the full width of the channel. Accessibility and method of cleaning should be incorporated into the bypassing scheme (Section 4.3.1.). 4.3.3 All grinding and screening devices will be located to provide easy access for maintenance. Where possible, narrow channels should be avoided; channels must be wide enough to allow personnel to work. 4.3.4 When bar screens are located so that the elevation at which the debris is manually removed is more than 0.9 m (3 feet) below ground level, a mechanical method of lifting the debris should be considered. In all cases, a debris dewatering platform should be provided. 4.3.5 The channel ahead of the bar screen should be designed to assure that equal hydraulic velocity is distributed across the bar screen. ------- 18 4.3.6 Hand cleaned bar screens should have a slope with the horizontal between 30 degrees and 45 degrees. 4.3.7 The design must consider the ultimate disposal of screenings. 4.4 Grit Removal 4.4.1 Grit removal facilities should be provided for mechanical treatment facilities utilizing anaerobic sludge digestion and/or when the collection system is known to have abnormal infiltration/inflow and/or combined sanitary/storm- water systems. 4.4.2 All gravity grit removal chambers will incorporate a method of hydraulic velocity control,' preferably adjustable. 4.4.3 All manually cleaned chambers should incorporate parallel units to facilitate cleaning. When the bottom of the chamber is more than 0.9 m (3 feet) below ground level, a mechanical method of lifting the grit should be considered. A drive or walkway should be provided to facilitate the vehicle used to haul the grit. 4.4.4 Mechanically cleaned chambers will have a bypass or sufficient duplication to allow dewatering of individual units. 4.4.5 Grit storage-dewatering (draining) facilities should be considered an integral part of all grit removal facilities and be protected from freezing or a means provided to prevent ------- 19 ice build-up where the ambient temperature is below freezing for extended periods. 4.4.6 All facilities not provided with positive hydraulic velocity control should contain grit washing equipment. 4.4.7 All aerated grit removal facilities must have a metered and adjustable air supply. 4.4.8 The design should insure that grit will be removed from all portions of the grit chamber floor. 4.5 Primary Clarifier 4.5.1 The inlet shall be designed to dissipate the inlet hy- draulic velocity and to equally distribute the flow to reduce short-circuiting. 4.5.2 Clarifier walkways, handrails, etc., should provide easy access for maintenance and protection of personnel. 4.5.3 Overflow weirs should be adjustable to allow for future re-leveling. 4.5.4 Clarifiers should have scum baffles ahead of the effluent weirs. Facilities designed for flows of 378.6 m /day (0.1 MGD) and greater should have mechanical scum removal equip- ment. A method of conveying the scum across the water sur- face to the point of removal should be included, such as water or air spray. Baffles should be designed to ensure scum capture at minimum and maximum flow rates. 4.5.5 Provisions should be made to sample the sludge during removal; a 3.81 cm (1 1/2 inch) minimum quick opening valve ------- 20 is recommended. A means of viewing the sludge is also desirable. 4.5.6 Sludge removal lines should be a minimum of 15.24 cm (6 inches) in diameter. Each point of sludge withdrawal should be individually valved. 4.5.7 Scum holding tanks should be provided with a method of removing the excess water. The scum should be premixed with sludge when discharged to anaerobic digesters. Scum piping should be glass lined or equivalent. 4.5.8 Large scum sumps should have a mixing device (pneumatic, hydraulic, or mechanical) to keep the scum mixed when being pumped. 4.5.9 Scum pump start-stop switches should be located adjacent to scum holding tanks. ' 4.5.10 Launders should have flat interior bottoms and be accessible for easy cleaning. 4.5.11 Since closely spaced multiple overflow weirs tend to increase hydraulic velocities, their spacing should be conservative. 4.5.12 Gravity sludge flow systems should have back-up pumping capabilities. 4.6 Secondary Clarifier 4.6.1 Primary clarifier Section 4.5.1 to Section 4.5.11 shall also apply to secondary claritiers except minimum size of sludge piping. ------- 21 4.6.2 Lift stations located immediately upstream of secondary clarifiers shall have flow-paced controls to reduce shock loading. 4.6.3 Activated sludge, including all modifications of the process, should be continuously removed from clarifiers. Provisions for intermittent removal should also be incorporated in small plants. 4.6.4 Provisions should be made to control the rate of sludge withdrawal from each individual point of withdrawal. ' In addition, provisions should be made to isolate each point of withdrawal. 4.6.5 When two or more clarifiers are used, provisions shall be made to control and measure the rate of sludge withdrawal from each clarifier. 4.6.6 The rate of activated sludge withdrawal should be infi- nitely variable from ten percent (10%) of plant average design flow to the maximum designed sludge withdrawal rate without plugging. 4.6.7 Circular clarifiers, 30.48 m (100 feet) in diameter and larger, should have two sets of concentric launder troughs and weirs separated by a distance of approximately 1/10 of the clarifier diameter. 4.6.8 Square clarifiers with circular sludge withdrawal mechanisms shall be designed such that corner hydraulic velocities do not cause sludge carry over. ------- 22 4.6.9 Consideration should be given to removing activated sludge from the effluent end of rectangular clarifiers. 4.6.10 A method of determining the activated sludge blanket level should be available. 4.6.11 The up-flow rate shall not be greater than the surface overflow rate at any location within the solids separation zone of a clarifier. 4.6.12 Overflow weirs should be of the notched type; straight edged weirs are not recommended. 4.6.13 Clarifiers following activated sludge should provide a minimum of 3.65 m (12 feet) side wall water depth. 4.6.14 Designs should consider the possible need for future modifications to add chemicals such as flocculants. 4.6.15 Large circular clarifiers require consideration of hydraulic overloading of leeward weir due to wind action. 4.6.16 A method of foam control should be considered for all inlet channels and feed wells in activated sludge systems. 4.7 Aeration Tanks 4.7.1 Aeration tank systems, except extended aeration, should be designed to accommodate at least three (3) modes of opera- tion (such as plug flow, complete mix, contact-stabilization, step aeration, etc.). Two (2) modes of operation for extended aeration systems larger than 1893 m /day (0.5 MGD) should be considered. ------- 23 4.7.2 When two or more tanks are installed, both series and parallel flow schemes should be available. 4.7.3 Where flows (return sludge and/or plant flow) enter aeration tanks through two or more ports, a means of measuring and control ling the flow rate at each entrance port should be provided. 4.7.4 The aeration (mixing) devices used shall provide a mini- mum of one foot per second hydraulic velocity throughout the entire aeration tank at all times. 4.7.5 The air input rate shall be readily controllable and be capable of maintaining the dissolved oxygen concentration between one and three mg/1 in each aeration compartment at all anticipated loadings, including the initial start-up loading. (See EPA 600/2-77-032, "Design Procedures for Dissolved Oxygen Control of Activated Sludge Processes" for additional guidance.) 4.7.6 Air flow rate meters should be provided for each aeration compartment in addition to a total air flow rate meter for each group of blowers, compressors, etc. 4.7.7 A method of control ling the air rate to each aeration tank should be provided. 4.7.8 Diffused air systems will be installed such that the diffusers can be removed, inspected, and cleaned without dewatering the aeration tank, except where the tank can be dewatered without reducing treatment efficiency. A ------- 24 mechanical means of removing the diffuser header must be provided when the procedure would present a safety or equipment hazard. Consideration must be given to the weight of the diffusers plus entrapped debris when being removed. Adequate room must be provided for the mechanical removal equipment. 4.7.9 A method of foam supression should be provided for all aeration tanks. 4.7.10 Mechanical aeration systems should be protected from freezing and a means provided to prevent ice build-up where the ambient temperature is below freezing for extended periods. 4.7.11 Where ambient temperatures are below freezing for ex- tended periods of time, beams, catwalks, etc., should be lo- cated and/or designed to preclude spray and foam from freezing on their surfaces. 4.7.12 All modes of the activated sludge process will have a positive method of measuring the return and waste sludge flow rates. For plants of 378.6 rrr/day (0.1 MGD) and larger the flow rate measuring devices should incorporate totalizing capabilities. 4.7.13 All activated sludge plants will have sludge handling facilities to accommodate waste activated sludge. 4.7.14 Adjustable aeration tank outlet weirs are desirable with mechanical aerators. ------- 25 4.7.15 Aeration devices in small plants should have time clock on-off control available. 4.7.16 Plants with initial flows of less than one-half design should have at least two aeration basins. 4.7.17 Return and waste activitated sludge must be accessable for sampling and should be visible at some point in the system. 4.7.18 Separate return and waste sludge pumps should be provided. 4.8 Activated Sludge "Package Plants" 4.8.1 All guidelines pertaining to activated sludge systems, also apply to package plants. Systems smaller than 378.6 m3/day (0.1 MGD) may be exempt from sections 4.7.1, 4.7.3, 4.7.6, and 4.7.18. 4.8.2 Each process compartment shall be constructed with load bearing walls to allow dewatering each process compartment individually. 4.9 Activated Biofliters 4.9.1 All guidelines pertaining to activated sludge systems will also apply to ABF systems when short term aeration is included, except section 4.7.1. When short term aeration is not included, sections 4.7.12, 4.7.13, 4.7.17 and 4.7.18 will apply. 4.9.2 Fixed nozzle ABF towers should be divided into at least two (2) separate units separated by a solid wall with ------- 26 appropriate valving to allow each unit to be independently removed from service. 4.9.3 Direct recirdilation of the tower should be provided in such a manner as to provide positive control of the recircu- lation rate when the facility is subject to highly varying load rates and/or initial start-up load is less than 50% of design load. 4.9.4 A method of controlling the air flow rate through the ABF tower should be provided. 4.9.5 All ABF systems should include short-term aeration facilities. 4.9.6 Systems treating greater than 10 percent industrial waste should have a means of flushing solids from the tower. 4.10 Aerobic Digestion 4.10.1 All guidelines pertaining to aeration tanks, except sections 4.7.1, 4.7.2, 4.7.3, and 4.7.12, will also apply to aerobic digesters. 4.10.2 Aerobic digestion systems in treatment plants designed for flows of 1893 m3/day (0.5 MGD) and greater should contain at least two compartments with provision for alternate feed. A single compartment may be used in conjunction with the extended aeration process. 4.10.3 A means of supernating (solids separation) shall be provided. 4.10.4 Gravity sludge thickener solids and hydraulic design loading criteria should be used for flow through gravity ------- 27 separation supernating facilities located in either a separate compartment or a baffled area within the aerobic digester. 4.10.5 The supernatant draw-off level should be adjustable in either batch or flow through systems. 4.10.6 The supernatant should be returned to the waste stream at the influent to the aeration tank or upstream. 4.11 Anaerobic Digestion 4.11.1 A gas meter with bypass should be provided to meter the gas production from each primary digester. In addition, a gas meter with bypass should be provided to meter the total production and consumption at each point of use; e.g., boiler, waste burner, etc. Only gas meters compatible with digester gas shall be used. 4.11.2 Provisions should be made for gas sampling from each digester. 4.11.3 Thermometers should be provided to show the temperature in each digester. They should be located to show the temperature of the active sludge zone and be removable for checking and calibration without affecting operation of the digester. 4.11.4 A high-low gas pressure alarm device should be incorpo- rated in the gas piping near the digesters and at each vital point of consumption; e.g., boiler, internal combustion engine, etc. ------- 28 4.11.5 Measuring devices should be provided to indicate gas pressure in each digester and at all points of consumption; e.g., boiler, waste burner, etc. Where mechanical gauges are used, diaphram protectors will be installed. 4.11.6 Each digester should have a vacuum/pressure relief valve with flame trap. All gas piping must be sloped with a condensate trap at each low point. 4.11.7 Easy access should be provided to each vacuum/pressure relief valve, condensate trap, and flame trap with sufficient room for maintenance. Drain lines from condensate traps should be piped to floor drains or sumps. 4.11.8 All heated digesters should be provided with mixing facilities. Mechanical or gas mixing is acceptable; generally, mixing by liquid recirculation is inadequate by itself. 4.11.9 Digester heating systems should be automatically con- trolled. 4.11.10 A method of measuring the volume of sludge discharged into each primary digester should be provided. 4.11.11 Adequate piping and valving will be provided to facili- r tate cleaning the digesters. It may be desirable for large installations to permanently install the pumps necessary to facilitate cleaning; whenever portable pumps are used, the availability of such pumps will be indicated prior to approval. ------- 29 4.11.12 All digesters should have side hatches to facilitate cleaning operations. It is recommended that the bottom of the hatch be located 1.52 m (5 feet) above the digester floor, but not below exterior grade, with a minimum opening of 0.91 m by 0.91 m (3 feet by 3 feet). 4.11.13 Digesters should have sufficient sludge withdrawal points to maximize concentration of solids. 4.11.14 Digesters should have sufficient supernatant withdrawal points and elevation control to minimize supernatant solids concentrations. 4.11.15 Sludge handling shall be provided (such as drying beds, holding tanks, lagoons, dewatering equipment and/or incinera- tion equipment, or valves and piping for liquid hauling) so that year-round disposal is available. 4.11.16 Overflow and gas pipes should be positioned to avoid plugging with surface scum. 4.11.17 A means of adding chemical solutions into the digester without opening the digester lid should be provided. 4.11.18 Sludge density must be considered in the selection of pumps. 4.11.19 Timers or variable speed units should be used on raw sludge pumps. 4.11.20 Extreme caution must be used in selecting pumps used for pumping sludge containing significant quantities of grit. ------- 30 4.11.21 Sump pumps in sludge handling areas should be capable of pumping sludge. 4.11.21 Sludge pumps should be positioned to have positive suction head. 4.12 Disinfection Disinfection facilities will be designed in accordance with "Disinfection Chlorination, Design, Operation and Main- tenance Guidelines," June 1977, U.S. EPA Region X. 4.13 Lagoons-Oxidation Ponds 4.13.1 A minimum of three cells should be used. The cells should be interconnected in such a manner to provide for series, parallel, and parallel series operation. 4.13.2 Grit removal facilities should be considered when the collection system is known to have abnormal infiltra- , tion/inflow and/or combined sanitary/stormwater systems,, 4.13.3 Comminutors and/or bar screens should be provided when the facility is serving dischargers that characteristically contribute large volumes of debris, such as penal and mental institutions, hospitals, resident schools, etc. 4.13.4 The liquid depth should be controllable, no greater than 15.24 cm (6-inch) increments, from 0.6 m (2 feet) to maximum design depth, and provide for a maximum liquid elevation reduction in the last cell of 5.08 cm (2 inches) per day. 4.13.5 All transfer structures should have submerged inlets. ------- 31 4.13.6 Cell inlets should be located down-wind from the outlet structure, according to the prevailing wind direction. 4.13.7 Adequate piping and valving should be provided to allow isolating and completely dewatering any individual cell without draining into the receiving waters. Portable Dumps and piping may be acceptable. 4.13.8 Effluent structures should provide for multi-level draw- off from the final cell(s). The lowest draw-off at 30.48 cm (12 inches) from the cell bottom with additional draw-offs at 30.48 cm (12-inch) increments up to 45.72 cm (18 inches) below the highest operational level anticipated. 4.13.9 The space between dikes and fences should have sufficient width to accommodate mowing equipment. 4.13.10 Nonfloating rip rap material should extend to the toe of the inner dike. 4.13.11 Short circuiting should be reduced as practical by cell shape or non-load bearing baffles. 4.13.12 Piping and valving-should be considered for recircula- tion between ce-lls. Portable pumps and pipe may be acceptable. 4.11.13 All cells should have staff gauges for liquid depth measurement. 4.14 Laboratory Faci1it ies 4.14.1 All mechanical treatment plants will have laboratory facilities with sufficient equipment to conduct operational ------- 32 control tests indicated in the design summary (Section 1.1). Coliform testing by an off-site laboratory may be allowed on a case-by-case basis. Laboratory facilities must be avail- able to non-mechanical plants; on-site facilities are recommended. 4.14.2 EPA-430/9-74-002, "Estimating Laboratory Needs for Municipal Wastewater Treatment Facilities," June 1973, should be used to determine the physical size, layout and ancillary equipment (water, sinks, power, etc.) of the laboratory - — facilities. 4.14.3 Safety equipment, such as eye wash stations, emergency showers, first aid kits, and fire extinguishers, will be required. 4.14.4 Storage of tools, lubricants, spare parts, etc., in laboratories will not be allowed. 4.14.5 The laboratory should not be located in the same building with mechanical equipment which may cause vibration or excessive noise, such as blowers, pumps, etc., unless adequate sound and vibration isolation is provided. 4.15 Metering 4.15.1 Mechanical plants greater than 378.6 m /day (0.1 MGD) should have a flow measuring device incorporating a recording chart and totalizer. 4.15.2 Mechanical plants 378.6 m3/day (0.1 MGD) and smaller should have a flow measuring device incorporating a ------- 33 totalizer. Pump hour meters may be acceptable in some cases if calibrated after installation. 4.15.3 Lagoons, ponds, etc., should have as minimum influent and effluent flow measuring weirs; effluent flow totalizer -capabilities are preferred. ,f.l5v4-;. The following side streams should have flow rate indicators with totalizers (See Sections 4.7, 4.8, 4.9, 4.10, and 4,11): a. Return activated sludge. b. Waste activated sludge. c. Sludge to anaerobic digesters. d. ABF recirculation streams. 4.15.5 The following side streams should have flow rate indicators: a. Flows to parallel units. b. Sludge thickeners—influent and supernatant. c. Mechanical sludge dewatering units. d. Air supply to each aeration basin. 4.15.6 Flow and air rate indicators should be located within visual contact of flow and air rate controls. 4.15.7 Hydraulic velocities should be considered in the location of flow measuring devices to assure calibration curves match field conditions. 4.15.8 A method of calibration should be considered when locating flow measuring devices. ------- 34 4.15.9 All lift station pumps should have hour meters. 4.15.10 Suction and discharge pressure gauge taps should be considered for all pumps. 4.15.11 Process air systems should have a pressure indicator. 4.15.12 Large electric motors should have ampere meters. 4.15.13 All motors shall have ampere meters when the motor can be overloaded by control changes. The ampere meter will be located within visual contact of the controller. 4.15.14 Portable dissolved oxygen meters should be provided for activated sludge plants and are recommended for all other aerobic treatment plants. Two probes are recommended, one for measuring D.O. in. process tanks and a separate probe with attached stirring device for laboratory use. ------- |