903R92007
               U.S. EPA legion III
               Regional Center for Environmental
                Information
               1650 Arch Street (3PM52)
               Philadelphia, PA  19103
     The  ROAD To ROD
Tips for Remedial Project Managers

    Working Together to Get There Faster
              Jointly Prepared by:

     The U.S. Environmental Protection Agency
         The U.S. Department of Defense
                 January 1992

-------

-------
                    CONTENTS









                                              Page




     Acknowledgment                          vii




 I.   Purpose                                    1




 II.   DoD Involvement at NPL Sites                5




III.   The ROD Process                          11




IV.   Tips to Expedite the ROD Process            23




     Conclusions                               39




     Available Resources                        41




     References                                43




     List of Acronyms                          47




     Appendix A.  ROD Summary for DoD Sites   52




     Appendix B.  Summary of Key Requirements  58

-------
                  LIST OF TABLES



                                               Page

1.   Characteristics of DoD Facilities                   6

2.   The Nine Evaluation Criteria for                  13
    Remedy Selection
                 LIST OF FIGURES



1.  The Road to ROD:  A Pyramid to Progress          3

2.  Examples of Post-ROD Changes                  20

3.  Case Study of the ROD Process                   24

4.  Potential Reviewers                             38

-------
                        ACKNOWLEDGMENT

The recommendations presented in this guide were developed by a work group of
representatives from EPA, DoD, and each of the DoD services.  Through effective
communication and a Total Quality Management (TQM) approach to coordination
and analysis, this work group quickly researched opportunities for improving the
current ROD development procedures and for approving NPL site documents,
namely the PP and the ROD. The guide tries to keep a balanced perspective of the
demands and schedules placed on each of the participants in the ROD process, and
to look at the statutory and regulatory guidance as a road map for the process.

The guide was developed over a 7-month period with concentrated effort and
constant commitment from the following individuals:

   EPA

   •  Harry Harbold, Technical Coordinator, Hazardous Waste Management
      Division, EPA Region III

   •  Steve Hirsh, Remedial Project Manager, EPA Region III

   •  Seth Thomas Low, Chief, Virginia RCRA/CERCLA Remedial Section,
      Office of Regional Counsel, EPA Region III

   •  Henry Sokolowski, Chief, Federal Facilities Superfund Program, EPA
      Region III

   •  Kathryri Boyle, Environmental Scientist, Compliance Branch, Office of
      Waste Programs Enforcement, EPA Headquarters

   •  Sherry Milan, Environmental Protection Specialist, Office of Federal
      Facilities Enforcement, EPA Headquarters

   DoD

   •  Vic Wieszek, Environmental Protection Specialist, Office of the Deputy
      Assistant Secretary of Defense ( Environment)

   •  Karl Kneeling, Environmental Restoration Program Manager, Department
      of the Air Force, Office of the Civil Engineer, Environmental Directorate

   •  Rick Newsome, Assistant for Environmental Restoration, Office of the
      Assistant Secretary of the Army for Environment, Safety, and
      Occupational Health

   •  Dave Olson, Installation Restoration Program Manager, Office of the
      Chief of Naval Operations

   PRC Environmental Management, Inc.

   •  Pamela Bellin, Project Manager

   •  Joe Knox, Project Manager

Many other people, in addition to the regular work group  members, participated
in the development of this guide, and their efforts were greatly appreciated at every
ster

-------

-------
                        I. PURPOSE
This guide is designed to provide
Environmental Protection Agency
(EPA) and Department of Defense
(DoD) Project Managers with an
overview of the Record of Decision
(ROD) process, and to identify
opportunities for  expediting the
ROD process at DoD sites on the
National Priorities List (NPL). The
expertise  that has  been gained in
managing the first group of DoD
sites to go  through  the remedial
process under the Comprehensive
Environmental  Response, Com-
pensation, and Liability Act of 1980
(CERCLA) provides  valuable
insights for Project  Managers at
future sites. This document focuses
on one segment of the ROD process,
the  period between completion of
the  Feasibility Study (FS) and
signature of  the  ROD, and  on
opportunities to minimize this time
period.
DoD  sites requiring  CERCLA
response  present  a formidable
management  challenge.  Project
Managers  at EPA,  DoD, and the
States face a large universe of DoD
sites on the NPL and the potential
for many  additional RODs to be
completed during  this decade.
Innovative approaches are needed
to expedite the ROD process.

It is important to  examine the
lessons that  have been learned
already in handling the complex
challenges at DoD sites and apply
these lessons to future NPL sites,
with the ultimate goal of reducing
potential risks to human health and
the environment. Project Managers
who have charted new courses and
directed the first DoD sites through
the ROD process have learned much
from which others can benefit. Their
 COMPLEX SITES
 A MANAGEMENT CHALLENGE
              Waste Piles

-------
lessons are presented in this guide.
Appendix A  summarizes   the
identified threats and  selected
remedies at a variety of DoD sites
for which RODs have been signed.
This list provides Project Managers
with EPA and DoD contacts  who
can share insights as similar sites go
through the ROD process.

This guide is targeted to both new
and experienced Project Managers.
It provides new Project Managers
with a description of DoD's role in
CERCLA response actions at  NPL
sites and a concise explanation of
the ROD  process.  It then provides
tips on improving and expediting
the  ROD  process,  available
resources that can assist Project
Managers, and references others
have found valuable.  The tips are
organized  around  the  four
objectives highlighted in Figure 1.
Readers who are familiar with the
ROD process and  the unique
challenges posed by DoD sites may
want to  proceed immediately to
Chapter 4, "Tips to Expedite the
ROD Process."  The discussions
throughout  this guide  focus on
experiences  at DoD  sites on the
NPL; however,  these  lessons
provide valuable insight that can
be applied to non-DoD  and non-
NPL sites as well.

-------
                 Expediting Document
          (,  Preparation/Review/Approval
                   Feasibility Study
                 Remedial Investigation
         Building Communication and Coordination
             Improving the Planning Process
  Understanding the Role of the Interagency Agreement (IAG)
                     Figure 1.
The Road to ROD:   A Pyramid to Progress
                         -3-

-------

-------
            II.  DoD INVOLVEMENT AT NPL SITES
 Implementation  of environmental
 protection programs at  DoD sites
 poses numerous challenges.   The
 Federal Government's commitment
 to  protect human  health and the
 environment and to  become a model
 for  environmental  compliance  is
 demonstrated by the large efforts
 under way not only at CERCLA sites,
 but also at the thousands of sites being
 addressed by the Defense Environ-
 mental Restoration Program (DERP).
 In  addition  to  the 95 DoD facility
 listings on the NPL, DoD services are
 investigating  or addressing potential
 risks at hundreds  of sites.  DoD and
 EPA Project Managers can obtain a
 broader picture of the number of DoD
 facilities in the CERCLA pipeline and
 progress already accomplished by
 reading  the "Defense Environmental
 Restoration Program Annual Report to
 Congress for  Fiscal Year 1990,"
 February 1991.

 EPA and DoD Project Managers face
 unique challenges, because environ-
 mental priorities must be  integrated
 with the national security missions of
 each DoD service, including the
 Department  of the Air Force, the
 Department  of  the  Army,  the
 Department  of the Navy, and the
Defense  Logistics Agency (DLA).
National  security  is  paramount,
however, it is also important for the
Federal Government to  present  a
unified  picture to the public of a
government     committed     to
environmental   protection   and
restoration at its own facilities to at
least the same extent that it  is
committed to environmental pro-
tection at private sites. (Private sites
here are defined as all non-DoD and
non-Federal facility NPL sites.)  To
achieve this result, EPA and DoD
must  work  closely to  identify
workable  solutions for  integrating
environmental protection priorities
with DoD missions.
This section describes some of the
unique characteristics of DoD  sites
and the pertinent environmental regu-
lations that govern their operations.
Major issues confronting EPA, DoD,
and State Project Managers are high-
lighted.

II.l Characteristics of DoD
    Facilities

Several key differences exist between
DoD and private industry operations
that make remediation  of  DoD
facilities unique. These dissimilarities
include the size of the facility, the

-------
number of  operable  units,1 and  the
types of industrial processes in which
DoD is engaged.  DoD sites on  the
NPL range  in size from a few acres
to tens of  thousands  of  acres and
frequently    contain    multiple
contaminated areas.   DoD sites  on
the NPL presently have from 1 to as
many as 25  operable units.

Many of the problems existing at pri-
vately owned sites on  the NPL also
occur at DoD facilities. DoD facili-
ties often  have many wastes in com-
mon  with private sites,  but face a
cleanup challenge due to  the  large
quantity and variety of wastes.  In
addition, military-unique compounds
such as pyrotechnics, explosives, and
propellants are atypical of private in-
dustry and require special remedial in-
vestigative procedures and responses.
Table 1 provides an overview of DoD
facility characteristics.
AN  OPERABLE UNIT, as
defined in the National Oil and
Hazardous Substances  Pollution
Contingency  Plan (NCP) (40
CFR 300.5), is "a discrete action
that  comprises an incremental
step  toward  comprehensively
addressing site problems.   This
discrete portion  of a  remedial
response  manages  migration, or
eliminates or mitigates  a release,
threat of a release,  or pathway of
exposure.  The cleanup of a site
can be divided into a number of
operable units, depending on the
complexity  of the  problems
associated with the site.  Operable
units may address geographical
portions  of a site, specific site
problems, or initial phases of an
action, or may consist of any set
of actions performed over time or
any actions that are concurrent
but located in  different parts of
a site."
Military Activities
• Explosive ordnance
production and disposal
• Demilitarization
• Ammunition plants
• Weapons systems
development, testing,
and evaluation
• Shipbuilding
• Large industrial
processes
• Training (land, sea,
and air)

t

Unique Military Wastes
• Exotic fuels
• Explosive
compounds (TNT,
DNT, etc )
• Military chemicals
(mustard gas, white
phosphorus, Agent
Orange, etc.)
• Mixed waste
(low-level radiation
and hazardous waste)
'•;


Large Quantity and
Varied Wastes
• Benzene • Arsenic
• Toluene • Zinc
• Xylene • Mercury
• Lead • Acetone
• Trichloroethylene
• Tetrachloroethylene
• Ethyl benzene
• Chloroform
• Chromium (III)
• Methyl chloride
                                 Table 1.
                    Characteristics of DoD Facilities

-------
 II.2 Statutory and Regulatory
     Framework

 The number  of DoD facilities to be
 investigated, the size of these facilities,
 and their types  and  sources of
 contamination combine to create a
 clear  challenge  in  ensuring DoD
 compliance  with  hazardous waste
 laws. This challenge is heightened by
 the potential  at each  site for
 overlapping jurisdictions  among
 Federal agency  programs,  State
 programs, and multiple statutes.
  Overlapping Jurisdictions and
            Programs
DoD facilities are subject to the
requirements of other regulatory
environmental laws and programs in
addition to  CERCLA, such as the
National   Pollution   Discharge
Elimination System (NPDES) program
under the Clean  Water Act (CWA),
the  Resource  Conservation and
Recovery Act (RCRA), and the Toxic
Substances Control Act (TSCA). Most
CERCLA response activities at these
facilities are  the result of a release or
threat  of release   of  hazardous
substances from  hazardous materials
and waste management practices that
occurred before  enactment of  these
statutes  or  that   violate   their
requirements.

Hazardous  waste   management
activities at  DoD  facilities can
encompass a wide range  of practices
and are dependent on the individual
type of facility and its  function.
Because DoD  facilities  are usually
large operations that treat, store, and
dispose of hazardous wastes, situations
may  arise  where   solid  waste
management  units are subject to RCRA
Subtitle C regulations (management,
closure,  or Corrective  Action)
concurrent with a CERCLA response
activity  (non-RCRA hazardous waste
activity).

Project Managers should be aware of
the need to satisfy multiple statutory
requirements  concurrently.   For
example, CERCLA/RCRA interface
issues at NPL sites are addressed in a
site-specific  Interagency  Agreement
(IAG),  also called a Federal Facility
Agreement (FFA), before initiating a
Remedial Investigation (RI).
                                 -7-

-------
     THE ROD:  THE LINK TO CLEANUP
   Pre - ROD
  Post - ROD
• Site Discovery

• Preliminary
  Assessment/ Site
  Investigation

• National Priority
  List
  Remedial
  Investigation/
  Feasibility
  Study
• Remedial Design

• Remedial Action

• Operation and
  Maintenance

-------
 • Documentation of the selected
  remedy in a ROD, with all the
  facts and analyses supporting this
  preference.

 Project Managers are responsible for
 developing these documents and
 guiding the remedy selection pro-
 cess. In this role, they are the keys to
 careful planning, time management,
 coordination, and document prepa-
 ration.  They are the ones who de-
 velop schedules and can take inno-
 vative approaches to expedite the
 ROD process.

 Throughout  the  remedy selection
 process, States may provide support
 to EPA and DoD. In this role, the
 designated lead agency within the
 State   for  CERCLA  activities
 provides a single point of contact for
 communication and oversees State
 involvement  in the review of
 documents or data.

 Early in the process, EPA and DoD
 Project Managers  should assess
 carefully what is needed to complete
 the  three steps  identified above
 (presenting the PP, selecting the
 remedy, and preparing the ROD)
 and  should begin thinking about
 how a dedicated team can proceed
 effectively and efficiently through
the steps. These next two sections of
this guide provide detailed informa-
tion  on the PP and ROD, and the
following chapter describes specific
opportunities  for improving the
overall ROD process.
III.l The Importance of the
     Proposed Plan

The PP identifies and explains the
rationale for the preferred remedial
alternative and addresses  the
threats to human health and the
environment at the site or operable
unit.  It must describe all remedial
alternatives that were evaluated,
explain the nine criteria used to
evaluate   and  compare   the
alternatives, provide the rationale
for the preferred alternative, and
solicit public review and comment
on all alternatives presented.
The evaluation criteria are the
standards  by  which  all  the
alternatives are assessed and are the
basis of  the remedy selection
process. They can be separated into
three levels: threshold, balancing,
and modifying criteria, which must
be  considered in  this order.
Threshold criteria must be evaluated
first and are strict requirements for
the remedy selection process.  In
considering balancing criteria, and
then modifying criteria, there  is
slightly  more subjectivity  and
flexibility. Table 2 briefly describes
each of the nine evaluation criteria.

-------
                  III.  THE ROD PROCESS
 Signing the ROD is the stepping-
 stone between  identifying and
 assessing  CERCLA  sites  and
 beginning on-site remedial activities.
 It is the critical link between site
 identification and cleanup.
Although removal actions can occur
at any point during the CERCLA
process, this guide focuses solely on
remedial activities.  Additional
information on removal actions can
be found in Section 300.415 of the
NCP.

The purpose of the remedy selection
process is to choose remedies that
eliminate, reduce, or control risks.
With the  potential for hundreds of
additional RODs at DoD facilities in
the next few years, expediting the
ROD process can mean earlier
reductions in risk to human health
and the environment. EPA and DoD
Project Managers overseeing  the
remedy selection process for these
sites are  at the  core of decision
making and can have tremendous
influence  over environmental
restoration and cleanup decisions at
these sites. Project Managers must
always be alert to opportunities for
taking   early   action  where
appropriate to contain, treat, or
remove wastes and reduce risk to
human health and the environment.

EPA's  and DoD's goal for  the
remedy selection process is to select
remedies that protect human health
and  the  environment, maintain
protection over time, and minimize
untreated waste. OnceanRI/FShas
been  completed,   the   site
characteristics should be known and
a range of remedial alternatives
should be  identified.  At DoD
facilities,  selection of the remedy
progresses with the following steps:

• Presentation of a summary of the
 information and analyses that
 support the proposed decision in
 a Proposed Plan (PP) for public
 comment.  Through announce-
 ments in  local  newspapers and
 open communication  with  the
 public, EPA and DoD must estab-
 lish at least a 30-day period for
 public comments.
          Proposed  Plan
 1 Joint selection of the remedy by
  EPA  and DoD.   (In  cases of
  disagreement, EPA is ultimately
  responsible  for  the  remedy
  selection.)
   DoD
                        EPA
                               -11-

-------
                 -criteria,art requirements thai each
  alternative imastmeet In order to fee eligible for
  selection;;."-   ",'     :   -,;..'    '    ,     ';  .'
           Overall Protection of Human Health and the
           Environment.  Addresses whether a remedy
           provides adequate protection of human health and
           the environment from unacceptable risks posed
           by  hazardous  substances,  pollutants,  or
           contaminants present at the site by eliminating,
           reducing,  or  controlling exposures through
           treatment, engineering, or institutional controls.
           Compliance with Applicable or Relevant and
           Appropriate  Requirements   (ARARs).
           Addresses whether the alternative attains  all
           ARARs under Federal environmental laws or State
           environment or facility-siting laws or provides the
           grounds for invoking one of the six ARAR waivers
           stated in the NCP.
                   The
NCP
                         Table 2.
        The Nine Evaluation Criteria for Remedy Selection
1 Criteria are established in Section 300.430(e)(9)(iii) and 300.430(f)
 of the NCP.

-------
    BALANCING criteria are  factors with
    trade-offs between alternatives are assessed so
    that the best option will be; chosen, giiren site-
    specific data and conditions,       \
             Long-term Effectiveness and Permanence.
             Refers to the  ability of a remedy  to maintain
             reliable  protection of  human health and the
             environment over time, once remedial action goals
             have been met.  Permanence for this criterion is
             viewed along a continuum, and an alternative can
             be described as offering a greater or lesser degree
             of permanence.

             Reduction of  Toxicity, Mobility, and Volume
             (IMV) Through Treatment. Assesses the relative
             performance  of recycling  or  treatment  tech-
             nologies on the TMV of contaminants.

             Short-term Effectiveness.  Addresses the ad-
             verse impacts on human health and the environ-
             ment that may be posed in the time it takes  to
             implement the remedy  and achieve  the
             remediation goals.

             Implementability.  Looks at the technical and
             administrative feasibility of the remedy, includ-
             ing  the  availability of materials and services
             needed to implement  each  component of the
             option in question.

             Cost.  Includes estimated capital and operation
             and  maintenance costs,  and net present value  of
             capital and operation and maintenance costs.
                     Table 2. (continued)
        The Nine Evaluation Criteria for Remedy Selection '
1  Criteria are established in Section 300.430(e)(9)(iii) and 300.430(0
  of the NCP.	
                            -14-

-------
             State  Acceptance.  Addresses  the  State
             comments and concerns  for each potential
             remedy. Indicates whether the State concurs with
             the preferred or the selected remedy in the PP or
             the ROD.
             Community Acceptance.  Summarizes  the
             public's  general response to the  alternatives
             described in the PP or the FS.
                     Table 2. (continued)
        The Nine Evaluation Criteria for Remedy Selection '
1  Criteria are established in Section 300.430(e)(9)(iii) and 300.430(f)
  of the NCP.

                              -15-

-------
The PP is intended to facilitate
public participation in the remedy
selection process and satisfies the
CERCLA requirements concerning
public participation. The PP can be
written in a fact-sheet format or an
expanded format.  The  fact-sheet
format is  usually 10 to 15 pages
although a longer  PP may  be
necessary, depending on the specific
site conditions. Circumstances that
may warrant an expanded format
include technically complex issues,
multiple operable units that are
being remediated at the same time,
or a  high level  of community
concern.   The  PP is  probably the
most  effective method  of  written
communication targeted to the
public, because the average citizen
is more likely to read a  fact sheet
summary of the site.
The process for developing the PP
and  its basic requirements are
established in CERCLA as follows:

• Section  113(k)(2)(B)  establishes
 minimum procedures for public
 involvement  in  the  remedy
 selection process.   These pro-
 cedures include notice to the
 public, accompanied by a brief
 analysis of all the alternatives that
 were   considered,    and   a
 reasonable  opportunity  to
 comment.

• Section 117(a) requires the lead
 agency to publish a notice and
 brief analysis of the PP and to make
 it available  to the public.  In
 addition,  it requires that  an
 opportunity for a public meeting
 at or near the facility be provided,
 and that a transcript of the meeting
 be made available to the public.

• Section 121(f)(l)(G) provides the
 requirements for State involve-
 ment in the remedial  decision
 process,  including notice  to the
 State and an  opportunity  to
 comment on the PP.   (See also
' Section 120(0).

The PP should be written in a clear
and concise manner. Use of technical
jargon    and   administrative
nomenclature should be kept to a
minimum to make it understandable
to the general  public. The PP is a
public participation document, not
a technical or legal document. The
information presented in this
document is intended to inform and
educate the local community on past
and future activities at the site. The
document (and subsequent public
meeting)  should emphasize that
community  acceptance is one
criterion in selecting the remedy and
that a  final decision is pending,
awaiting public input.

-------
 The period required for public com-
 ment on the PP is a constraint that
 the Project Manager should antici-
 pate.  The EPA Project  Manager
 should plan on releasing  the PP to
 the public 12 weeks before the date
 targeted in the EPA Superfund Com-
 prehensive Accomplishments Plan
 (SCAP) for ROD signature to allow
 time for a 30-day comment period,
 as required by the NCP.  Time-
 frames and requirements for public
 comment periods are established in
 Section 300.430(f)(3)(C) of the NCP
 and  are  beyond  the   Project
 Manager's control.
Wednesday
  July
    8
              12 Meets to ROD///
Although the NCP requires a mini-
mum of 30 calendar days for public
comment on the PP, Project Manag-
ers should  review the site-specific
timeframes  set forth in the FFA,
since many agreements provide for
a 45-day public comment period.
In addition, if a timely request is
submitted to extend the public com-
ment period, the lead agency must
provide a minimum of 30 additional
days. As a result, this period can
last from a minimum of 30 days to
more than 75 days, which the Project
Manager must take into account in
planning. When the PP is issued,
the public comment period officially
begins.  After the close of the com-
ment period, the Responsiveness
Summary is prepared describing the
comments and how they have been
addressed. During the public com-
ment period, the lead agency must
provide the opportunity for a pub-
lic meeting at or  near the site to
discuss the PP and  supporting
analyses.
                      Q
III.2 The Importance of the
     Record of Decision

The purpose of the ROD is to docu-
ment the remedy selected by DoD
and EPA, provide a rationale for the
selected remedy, and establish per-
formance standards or goals for the
site or the operable unit under con-
sideration.  The ROD provides a
plan for site design and remediation,
and documents the extent of human
health or environmental risks posed
by the site or operable unit.  It also

-------
serves as legal certification that the
remedy was selected in accordance
with the requirements of CERCLA
and the NCP. The ROD is one of the
most  important documents in the
remedy selection process, because it
documents all activities prior to the
selection of remedy and provides a
conceptual plan for all activities sub-
sequent to the ROD.
The ROD consists of three basic
components:  the Declaration, the
Decision Summary, and   the
Responsiveness Summary, which
are described below:

•  The Declaration is an abstract
   of the key information contained
   in the Decision Summary.  This
   section is signed  by  the  EPA
   Regional Administrator and the
   designated  representative on
   behalf of the Assistant Secretary
   of Defense for Production and
   Logistics; once  signed,  this
   section makes  the entire ROD
   legally binding.

•  The Decision Summary is the
   core of the document and de-
   scribes  the site characteristics,
   the  risks posed by the site, the
   remedial alternatives evaluated
   to mitigate those risks,  the se-
   lected remedy and rationale for
  selection, and the performance
  goals of the remedy.

• The Responsiveness Summary
  addresses all  significant ques-
  tions and comments received
  from the public during the des-
  ignated comment period.

Similar to the PP, the contents of the
ROD  are governed by CERCLA.
Section 113(k)(2)(B)(v) of CERCLA
requires a statement of "basis  and
purpose" for the selected remedy at
a site. Section 117(b) requires that a
notice of the final ROD be published
and made available to the public in
the Administrative  Record  (as
provided for in the NCP) before
commencing the remedial action.
The  ROD must document  any
significant changes from the PP and
a response to all comments, written
and oral, that were received during
the public comment period.   The
ROD  is signed after closure of the
public comment period and once all
significant comments or issues are
addressed.

If public comments result in changes
to the remedy, the changes should
be clearly documented in the section
of the ROD  describing significant
changes from the PP.  If a funda-
mental change to  the  remedy is
made between the PP and the ROD
(such as changing a  treatment
remedy to a containment remedy),
then  an  amended  PP  should be
issued and a new public comment
period must be opened.
                               -18-

-------
III.3 Post-ROD Changes

After the ROD is  signed,  new
information may come to light that
may alter the effectiveness, extent,
or implementation of the remedial
action. Three types of changes may
occur:

  • Non-significant or minor
  • Significant
  • Fundamental.

Examples of these  three types of
post-ROD changes are presented in
Figure  2.   EPA  guidance on
addressing pre- and post-ROD
changes is contained in the Office of
Solid  Waste  and  Emergency
Response  (OSWER) Publication
9355.3-02FS-4 (April 1991).
         How big a
           change ?
Non-significant   changes  are
characterized as minor changes that
do not overly affect the scope or the
objectives of the selected remedy.
Non-significant changes generally
do not need formal documentation
and approval. They should be noted
in the post-decision document file.
Non-significant changes can also be
documented in an optional Remedial
Design Fact Sheet.

A significant change does not modify
the overall remedy but could alter a
component of  the remedy.   If a
significant change to a component
of the remedy is needed, then an
Explanation   of   Significant
Differences   (BSD)  must  be
developed, approved, and released
to the public in accordance  with
Section 300.435(c)(2)(i) of the NCP.
A formal public comment period
and Responsiveness Summary are
not required but may be initiated at
the discretion of both EPA and DoD.
It may also be appropriate to prepare
an BSD document when DoD and
EPA decide  to use a contingency
remedy that was not fully described
in the ROD.

An  BSD  document contains the
following:

• Introduction, describing the
  circumstances that gave rise to
  the change

• Summary of the site history and
  the selected remedy
                              -19-

-------
 1. Minor. Testing during Remedial Design shows that the volume of
    soil requiring treatment is 75,000 cubic yards (yd3) rather than the
    60,000 yd3 estimated in the ROD. However, the cost of the remedy
    will only increase by 5 percent because of economies of scale that can
    be realized.

 2. Significant. Residuals from a treatment operation were not expected
    to be hazardous and it was planned to dispose of them on site in a
    Subtitle D unit.  However, testing after treatment determines that the
    residuals are hazardous wastes, and off-site disposal at a  Subtitle C
    facility is required.

 3. Fundamental.  The in-situ soil washing remedy selected in the ROD
    proves to be infeasible to implement after testing during Remedial
    Design. A decision is made to excavate and thermally treat the waste
    instead.

 The Project Manager should consider these categories as  guidance.
 The appropriate approach  to responding to post-ROD changes is
 decided by EPA and DoD based on site-specific circumstances and
 discussion.
                             Figure 2.
                  Examples of Post-ROD Changes
• Description of the significant
  differences and the basis for those
  differences

• Affirmation of the statutory
  determinations

• Public participation activities.

The ESD document should receive
the same concurrences and approval
as the ROD.
subsequent  to  the  ROD is con-
sidered  a  fundamental change to
the remedy  and requires a ROD
Amendment. When such funda-
mental  changes are  made to a
remedy, a repetition of the ROD
process, including  issuance of a
revised PP and a new  public
comment period, is necessary, in
accordance with the requirements
of Section 117  of  CERCLA and
Section 300.435(c)(2)(ii) of the NCP.
At the other end of the spectrum, a
reconsideration of the hazardous
waste management  approach
An amended ROD looks very similar
to an initial ROD and should include
a  Responsiveness  Summary;
                                -20-

-------
however, the introductory sections   The NCP provides the policies for
(such as the site history, community   the remedy selection process under
relations, and site risks) do not need   CERCLA. Interim Final Guidance is
to be readdressed. Rather, the focus   available on developing the PP and
of the discussion should be on the   ROD in a document titled "Guidance
rationale for the ROD Amendment,   on Preparing Superfund  Decision
evaluating the alternatives in terms   Documents" (July 1989). Additional
of the nine criteria, and providing   information can be found  in  the
assurances that the new proposed   quick-reference fact sheet entitled
remedy  satisfies the statutory   "Guide to Addressing Pre-ROD and
requirements.                      Post-ROD Changes" (April 1991).
                               -21-

-------
                           ROD
                     /  Proposed Plan  \

                  f  Expediting Document  A
                 / Preparation/Review/Approval \

               /      Feasibility Study      \


            /       Remedial Investigation      \


         /   Building Communication and CoordinationX


     /        Improving the Planning Process          \


  / Understanding the Role of the Interagency Agreement (IAG) \


GETTING TO THE ROD AT DOD FACILITIES
                            -22-

-------
       IV. TIPS TO EXPEDITE THE ROD PROCESS
This chapter identifies specific
opportunities and methods to
streamline the ROD process at DoD
facilities.  Throughout, special
attention is given to how potential
modifications to the ROD process
at DoD  facilities apply to each
participant (EPA, DoD, other
agencies,  the   State)  and  to
milestones in the process (the PP
and ROD).  When possible, it
includes  references to  actual case
studies  where changes to the
process  have been successful.
Figure 3 presents  a sample case
study in which  many  of the tips
described  in this guide  were
applied and a ROD was prepared
and signed within  six months of
the FS  completion.

Although many opportunities ex-
ist to streamline the ROD process,
they center around  four objectives
for the ROD process, which include
the following:

•  Understanding the role of the
   Interagency Agreement (IAG)

•  Improving the planning process

•  Building communication and
   coordination

•  Expediting document  prep-
   aration,   and   review  and
   approval.
The steps that Project Managers can
take to achieve each of these objec-
tives are presented in the follow-
ing sections.
      This Way to
          ROD
IV.l
       Understanding the Role
       of the IAG
Section  120(e)(2) of  CERCLA
requires DoD services to enter into
an IAG with EPA for "the expedi-
tious completion" of all necessary
remedial actions at facilities on the
NPL.  Although CERCLA requires
an IAG to  be  signed within 180
days of the completion of the RI/
FS, EPA, DoD, and other Federal
agencies have agreed that it is more
appropriate to  enter into  an IAG
before beginning the RI/FS. This
way, all parties agree up front
about the scope, timeframe, and
approach for the RI/FS,  and go
                              -23-

-------
                         CASE STUDY

The following is an actual case study of how a ROD was prepared and signed in
less than six months from  the completion of the FS.  The name of the actual
facility is not presented, but all dates and activities are accurate.

Feb. 14, 1991   EPA, the facility, and the State had a meeting to form a
              work group and find ways to expedite cleanup consistent
              with the existing FFA.  The group focused on measures to
              streamline the process and eliminate unnecessary delay. The
              group agreed  to work  toward completing the  ROD by
              June 30, 1991, versus  the  original scheduled date  of
              October 1991.

Feb. 25, 1991   The facility provided a copy of  its draft ROD to  EPA.

Feb. 28, 1991   Both EPA  and the State provided comments on the Draft
              Final FS and reported early, rather than waiting for the full
              30-business-day  review period  to expire.  These actions
              allowed the FS Report to become final 10 days early.

Mar. 10, 1991  EPA reviewed the draft ROD and provided a revised ver-
              sion to the facility.

Mar. 22, 1991  Joint meeting between EPA, the facility, and the State was
              held over several days to prepare a version of the ROD and
              PP that was acceptable to all parties. Parties literally worked
              out differences in one room and eliminated review times.
              Meeting also enabled resolution of State ARAR issues.

Apr. 25, 1991   Public comment period for the Proposed Plan began.

May 8, 1991   Public hearing for the Proposed Plan was held.

Jun. 10, 1991   Public comment  period ended,  and Responsiveness
              Summary was prepared.

Jun. 15, 1991   ROD was prepared for final Headquarters and State review
              and signature.

Jun. 26, 1991   ROD was signed by all  parties.
                              Figure 3.
                  Case Study of the ROD Process

-------
 through  the process  together
 thereby reducing the chance of
 disagreements about the remedy or
 the data used to support the
 remedy selection.  The agencies
 have also agreed to call the IAG a
 "CERCLA   Federal  Facility
 Agreement (FFA)."

 Although the FFA is primarily a
 legal document, Project Managers
 often rely on the FFA as a plan-
 ning document to initiate and con-
 trol the progress of the  RI/FS.
 Project Managers should remem-
 ber that the FFA usually is not tai-
 lored very specifically to the site,
 but rather identifies the maximum
 timeframes for site activities.  An
 FFA frequently incorporates model
 language  on such items as turn-
 around times for comment periods,
 extensions of comment periods,
 and dispute resolution.

 In many cases,  EPA and DoD
 Project Managers have  assumed
 the maximum times for review and
 comment  on  provisions of the PP
 and  ROD, and in some cases they
 have assumed that dispute resolu-
 tion procedures would be invoked.
 Instead, Project Managers should
 seek to identify site-specific oppor-
 tunities to streamline the process
 and  to minimize review  times.

 "The Model Provisions for CERCLA
Federal Facility Agreements" (June
 1988)1 identifies  the ROD as  a
primary document that is critical to
the RI/FS and RD/RA processes.
Consequently, the ROD is subject
to the provisions for comment
periods, extensions, and other
provisions of the review  and
comment  process.   The legal
language contained in the FFA that
establishes maximum timeframes
is  necessary,  particularly  if
problems  develop,  but Project
Managers should take a positive
approach to planning schedules and
not immediately build in time for
extensions  and disputes.  Project
Managers should view the FFA as
a legal framework and benchmark
for operations and then consider
ways to streamline the process with
aggressive submittal and review
times.
           FFA Establishes
              Maximum
              Timeframes
The following sections of this guide
focus on opportunities and meth-
ods  to streamline the process of
completing  the PP and ROD.
   Porter, J. Winston, Assistant
Administrator for Solid Waste and
Emergency Response,  Memorandum
to Regional Administrator. Agreement
with  the Department  of Defense —
Model Provisions for CERCLA Federal
Facility Agreements, June 17, 1988.

-------
Project Managers should also con-
sider incorporating many of the
opportunities and  methods  de-
scribed below into the FFA during
FFA negotiations. Reviewing these
opportunities will focus the atten-
tion of  Project Managers on the
task of  streamlining the process
and identifying additional oppor-
tunities  for planning meetings to
accelerate progress  through joint
document preparation, and con-
current  ROD review.
IV.2   Improving the Planning
       Process

*  TWn^ attend, anticipate needs,
; , - and;                    " "
Planning may be the most impor-
tant factor for timely completion
of the ROD at Federal facilities.
Effective planning  is conducted
early, monitored   often,  and
focused on elements of the process
that can critically affect progress.
Planning  can  and should begin
even before the FFA is developed
and signed. Project Managers can
improve their planning by focus-
ing on the following issues:

•  Early scoping of the RI/FS

•  Early identification of ARARs
   and To Be  Considered (TBC)
   requirements

•  Early and accurate updates of
   targets tracked  in EPA's SCAP
   and  annual  planning  for
   remedial actions within DoD

•  Sufficient time to circulate the PP
   to the public and for internal and
   external review

•  Plans for contractor support

•  Identification of training needs

•  Use of project management
   tools.

Tips in each of these areas are
described in the following sections.
IV.2.1  Early Scoping of the
       RI/FS

* Assess the site and the risk,

Scoping  is a thorough planning
process for Project Managers that
requires them to look at their site
and determine its overall level of
complexity before  work begins.
Scoping involves an early assess-
ment of the number of migration
pathways at the site, the  most
imminent threats to human health
and  the  environment, and the
projected cost of actions needed at
the site.  The  scoping process is
described in more detail in EPA's
publication, "Scoper's Notes"
(February  1990).     EPA   has
emphasized early scoping of the
RI/FS  for all  sites, private and
Federal. The purpose of scoping is
                               -26-

-------
 to help ensure that important site-
 specific aspects  of the RI/FS are
 identified before work begins at the
 site.

 During this early scoping of the
 site, the Project Manager should
 also  look  ahead  to potential
 remedial actions that  may be
 appropriate at the site. This is an
 important  juncture at which the
 Project Manager should  take the
 following actions:

 •  Contact  EPA  and DoD Project
   Managers for similar sites to
   discuss remedies that  were
   effective

 •  Review guidance that identifies
   ways to streamline remediation,
   such as EPA's "Guidance on
   Remedial Actions for Superfund
   Sites with PCB Contamination"
   (August 1990) and "Conducting
   RI/FS for CERCLA Municipal
   Landfill Sites" (February 1991)

 •  Plan for a treatability  study, if
   one is needed

 •  Identify  an early action or an
   interim remedial measure (IRM)
   for the site.

In ways such as these, proper
scoping will help to expedite the
ROD process and can minimize risk
to  human   health   and  the
environment.
IV.2.2  Early Identification of
       ARARs and TBCs
"' . , saves- time 'aaul eneig^;--:: ''-;".
                 c~ Stair
 • • in -.writ ipg. •„
If all ARARs are not met by the
preferred alternative, the ROD may
be seriously delayed while  the
Project Managers conduct  addi-
tional site investigation activities to
meet  particular ARARs.  Such
delays can be avoided by identify-
ing all ARARs before beginning to
draft the ROD.

Project Managers should  develop
a list of ARARs by asking the State
and other agencies involved with
the site to submit  a list  of their
ARARs.   To anticipate  these
requirements, Project Managers
can examine existing RODs for
similar sites in the same State and
identify which ARARs  are  likely
         All ARARs
           the first
             time
           around.
        WANTED
                               -27-

-------
to apply.  Appendix A contains a
summary of RODs at DoD sites
that provides a starting point to
identify similar  sites;  Project
Managers can identify additional
sites through use of the Records of
Decision System (RODS) database
that is described in Appendix A.

 Project Managers should also refer
to EPA's guidance contained in
"CERCLA Compliance with Other
Laws Manual:   Parts I  and II"
(August 1989).   By requesting
specific State ARARs in writing as
early as possible, reviewing RODs
for similar sites, and referring to
existing   guidance,    Project
Managers can minimize the chance
of surprises  later  in the process,
and the need to address ARARs
that could have been  considered
earlier.

Before releasing the PP, Project
Managers should re-examine
ARARs for the site to ensure that
new requirements have not come
into effect. ARARs are "frozen" at
ROD signature.   Changing an
ARAR requires a ROD amendment
or  an  BSD as   described  in
Section III.3 of this guide.  As part
of the ROD process, ARARs that
are in existence at the time the ROD
is signed may be waived in
situations consistent with the
requirements of the NCP (40 CFR
300.430(f)(l)(ii)(c)).   Therefore,
Project Managers must consider all
statutory and regulatory changes
that can affect the ARARs for the
site until the ROD  is signed.
IV.2.3  Early and Accurate
       Updates of Targets
       Tracked in the SCAP

» Coordinate' in setting  and:
     '             '    "
The SCAP is EPA's primary
planning tool  for setting targets
and measuring progress for  the
CERCLA program. The SCAP is a
computerized database that tracks
the dates for accomplishments
(milestones) at each CERCLA  site
from discovery through operation
of the remedy, and is used for both
forecasting and reporting.  SCAP
reports are typically given to upper
management within EPA, and data
are used in reports to  Congress.
The data also provide input to
funding decisions for specific sites.
Since the SCAP tracks planned, as
well as actual, accomplishments,
DoD and EPA Project  Managers
should agree on the planned dates
for their sites.  By agreeing on these
dates in advance of the site work
and providing accurate updates as
work progresses, Project Managers
can avoid pressures to meet unre-
alistic targets.  Similarly, by shar-
ing these dates with each other,
                              -28-

-------
                                                            A
 Project Managers can ensure that
 DoD's planning systems (such as
 the Army's Fiscal Year (FY) Work
 Plan) and the SCAP are consistent.
 Updates to these systems occur at
 different times of the year for EPA
 and the DoD services. Both groups
 should be alert to these dates and
 coordinate accordingly.
 IV.2.4  Sufficient Time to
        Circulate the PP

 •  Plan on 12 weeks  between
   issuing the PP and the ROD.

 •  Account carefully for comment
   periods in setting a target date
   for the ROD.
Project Managers need to carefully
map a schedule of milestones to
the ROD and  to  account for a
potentially lengthy public com-
ment period in response to the PP.
As the Project Managers set target
dates for the  ROD  with their
management, Project  Managers
should estimate approximately 12
weeks for these activities.  The
NCP requires that EPA provide
the opportunity  for a  public
meeting to be held during  the
public  comment  period, and
generally one is held and must be
planned. Project Managers should
also ensure internal and external
coordination in developing the PP
for release to the public to facilitate
its completion.  Section III.l, "The
Importance of the Proposed Plan,"
of this guide describes many of the
regulatory  requirements  that
govern activities during this time.
IV.2.5  Plans for Contractor
       Support

«  Delegate and direct.

Project Managers should evaluate
their support needs, scope of work,
and contract  options well  in
advance of site work.  All the work
to be performed must be within the
scope of work for the contract and
needs to be clearly identified early
in the process to ensure a smooth
procurement process.

Contractors can provide a wide
range of support to the ROD pro-
cess. For  example, they can pro-
vide support in the following tasks:

• Prepare draft site plans

• Perform on-site activities (for
  example, set up and maintain
  Administrative Records)
                               -29-

-------
 •  Review site reports

 •  Assist   in  overseeing  site
   progress

 •  Assist in community relations
   initiatives

 •  Arrange meetings

 •  Assist   in  preparation  of
   preliminary drafts of the PP and
   ROD.

 To  obtain  support,   Project
 Managers need  to define their
 needs  clearly, identify procure-
 ment  options,   and  monitor
 progress  carefully.    Project
 Managers should check with their
 local  contracting office in pre-
 paring a specific scope of work to
 ensure that it is consistent with
 appropriate contracting activities.
IV.2.6  Identification of
       Training Needs

» Stay alert to changing require-
  ments through training.

• Investigate training opportuni-
  ties early in the year.
Many internal training courses are
offered by EPA and DoD, as well
as commercially, that can  help
ensure a more  timely RI/FS and
ROD.   Examples  include  the
courses  offered through the  EPA
CERCLA  Education   Center
implemented by EPA's Technology
Innovation Office  (TIO),  and
commercial courses on  technical
issues such  as boreholes  and
monitoring  well  installation.
Project Managers can obtain details
on available courses from TIO at
(703) 308-8800  and the Superfund
University Training Institutes,
Executive Director, Bruce Potoka,
(513) 569-7537.

Project Managers should note that
each year EPA conducts a ROD
Forum in every Region, usually in
April or May.  This Forum is
intended to provide training on the
proper contents of RODs and to
improve their overall quality. The
ROD Forum  can keep Project
Managers posted on new language
that  is required in RODs; ROD
checklists;  and  national  and
Regional trends, such as utilizing
interim action and no action RODs.

For example, the EPA 1991 ROD
Forum  (which analyzed   1990
RODs) provided participants with
the following:

• A comprehensive analysis of the
  ROD universe, Regional com-
  parisons, and recommendations
  for improving the ROD process
                              -30-

-------
 • An overview of risk assessment
   issues and approaches

 • An  update   on  regulatory
   requirements, such as RCRA
   Land Disposal Restrictions

 • A  summary of key terms and
   definitions

 • A sample ROD

 • Checklists for preparing RODs,
   including interim source actions,
   final source  actions, interim
   groundwater actions,   final
   groundwater actions, and no
   action RODs

 • Numerous  fact sheets on the
   Superfund and ROD processes.
In  addition to  the organized
training, ROD Forums provide a
valuable opportunity to interact
with other Project Managers, hear
their stories, and learn from their
experiences.   For all  of these
reasons, EPA Project Managers
should  contact the ROD Forum
Coordinator in  their Region early
in the calendar year and make a
concerted effort  to participate in
these sessions if possible. DoD
Project Managers should contact
the  EPA Project Manager  for
information on  these  training
opportunities.
IV.2.7  Use of Project
       Management Tools
Project management tools, such as
computer scheduling and tracking
systems, can make it  easier for
Project Managers to monitor major
milestones. Available software can
vary among offices, but both off-
the-shelf and customized systems
designed to project specifications
exist.  EPA and DoD Project Man-
agers should identify the software
available in their respective offices
and coordinate early in the plan-
ning process on the use of compat-
ible project management tools.
One software package used by EPA
is Milestone. Ideally, Project Man-
agers would use the same software
and share computer diskettes con-
taining updates through the mail.
                               -31-

-------
    A
IV.3   Building Communica-
       tion and Coordination

•  Good  communication
   pramot%$N«e££e$tive working
   relationships.

The FFA provides a foundation,
and effective planning identifies
the path for developing a ROD.
Getting there efficiently demands
good    communication    and
coordination to ensure effective
working  relationships.

DoD and EPA  Project Managers
need to  prepare and  organize
individually, but equally impor-
tant, they continually need to work
with each  other toward their
common  goal of signing the ROD.
Project Managers can communicate
and coordinate  effectively by
viewing the ROD process as a team
effort, frequently contacting other
team  members, coordinating
closely with other agencies,  and
using  the  Technical  Review
Committee as a communication
tool. These four opportunities to
improve communication   and
coordination are described in the
following sections.
IV.3.1  A Team Approach

  Abroach &% ROD as one team
       ,6rte/goaL     •;  ' -   ;:
members committed to a common
goal: a high-quality, signed ROD.
For each ROD, EPA and  DoD
Project Managers should take a
fresh approach, realizing that both
are committed to the process and
are not adversaries.  Constraints
and  goals  of  the  individual
organizations  are  now  the
constraints and goals of the whole
team.
DoD and  EPA Project Managers
should approach the RI/FS as team
A team approach can also enhance
the public's  perception of the
project.  The public is eager to see
progress made and potential risks
evaluated.  The public holds the
Federal  Government responsible
and wants to see a commitment to
environmental restoration in its
neighborhoods.     A  unified
approach can enhance the public's
perception of the process and can
defuse further public concerns.
IV.3.2  Frequent Contact and
       Face-to-Face Meetings

• Talk first, type second,

Project Managers should maintain
frequent contact  regarding site
progress and  meet as often as
possible throughout the course of
the RI/FS,  particularly while
preparing the ROD.  Frequent
                               -32-

-------
                                                           A
 contact reinforces a team approach,
 makes it easier to identify concerns,
 and facilitates conversations  that
 can lead to solutions.
Letters and lengthy memoranda
are better suited  to documenting
issues or following up on action
items. They are not substitutes for
telephone calls  and meetings,
where  questions can often be
answered  promptly.   Project
Managers   should   consider
scheduling a biweekly conference
call and a monthly meeting held
in alternating locations to foster
interaction,  communication,  and
good  working  relationships.
During the period in which the PP
and ROD are being prepared, even
more frequent communication can
be beneficial.
IV.3.3   Coordination With Other
        Agencies

*  Consider and coordinate,, with
  * reviewers'I
 Letters to confirm discussions
                                         sf oft ttfe
                                   ,- cm ««« dWdtioit
Good  communication is just as
valuable among agencies as among
Project Managers. Project Managers
will find that their jobs  are easier
when information flows quickly
and smoothly. A few minutes of
communicating can save hours of
clarifying misunderstandings or
coping with surprises.  To this end,
Project Managers should identify
the critical parties and specific
contacts involved in their site in
each agency early in  the ROD
process.

EPA and  DoD Project Managers
may  find that  sharing  these
responsibilities is more efficient.
The DoD Project Manager should
identify the appropriate agencies
and contacts within  the service
responsible for the site, such as
those at the U.S. Army Toxic  and
Hazardous Materials Agency
(USATHAMA), the Naval Facilities
Engineering Command (NAVFAC-
ENGCOM), or the Air  Force Major
Command (MAJCOM).  The NCP
requires each State to  designate a
single agency as the  point of

-------
contact, which is the lead agency
within the State  for Superfund
activities.

If there are potential threats to
natural resources at the site or
migrating off site, the  DoD and
EPA Project Managers  should
notify  the Trustees for  natural
resources as designated in Section
300.600 of the NCP.   Project
Managers need to coordinate with
the Trustees during RI/FS activities
to identify the extent of damage to
natural resources.

Most  EPA  Regions   have  a
Biological  Technical Assistance
Group  (BTAG)  that reviews and
comments on the ROD before it is
signed.   This  group  includes
scientists that advise and  assist
Project Managers in planning,
conducting,   and   evaluating
ecological studies that are needed
in conjunction  with the RI/FS.
BTAG members typically include
representatives from EPA, the U.S.
Fish and  Wildlife  Service, the
National   Oceanographic  and
Atmospheric Administration, State
agencies, and other organizations.
Although DoD  Project  Managers
are not BTAG members, they may
find it helpful to attend these
meetings  and  participate  in
discussions that pertain to their
sites.

As with other participants in the
ROD  process,  EPA  Project
Managers should coordinate with
the BTAG  early and  frequently
during  the  RI/FS process to
provide opportunities for input on
ecological issues at the site before
the BTAG reviews the  ROD.  The
first line of communication for
Project Managers is  the  BTAG
Coordinator in each EPA Region,
who can convene  meetings and
help select appropriate data for
BTAG review. The structure and
function of the BTAG is discussed
in  more detail  in  the  EPA
publication "ECO  Update:  The
Role of  BTAGs  in Ecological
Assessment" (September 1991).
                              -34-

-------
Although State concurrence on a
DoD ROD is not required, it is
required for  a site to be deleted
from the NPL. By actively seeking
State review and comment on work
plans and reports, Project Managers
can promote open communication
and good will. More than one State
agency may  be involved in the
process.  The EPA Project Manager
should review the FFA and speak
with the lead agency in the State to
identify all State offices that should
be kept abreast of activities.  When
a Defense and State Memorandum
of Agreement (DSMOA) is in place
with the State, DoD is funding State
activities and State involvement
should be approached consistent
with the scope of the agreement.
The goals again are  to limit
surprises, obtain the support of the
State agencies early, and pursue a
smooth  path  to  the ROD com-
pletion.
IV.3.4  Use of the Technical
       Review Committee
                       ongoing
Every DoD facility on the NPL has
a Technical Review Committee
(TRC) that consists  of  repre-
sentatives from local communities,
environmental groups, the public,
and other State, Federal, and local
agencies.   The  TRC is  not  a
decision-making body;  rather the
TRC provides Project  Managers
with  an opportunity to meet,
coordinate, and communicate.  The
TRC usually meets quarterly  to
discuss  issues  regarding  site
cleanup.

EPA and DoD Project Managers
should meet before the TRC so that
they can agree on the progress and
any concerns. Presentations to the
TRC should represent the views of
both EPA and DoD; this should not
be a time for surprises. It is critical
that EPA and DoD appear as a
unified body at  the TRC  with a
common  goal of cleanup.  Before
developing  and signing the ROD,
the TRC can be used as a sounding
board for issues to anticipate how
the public may react to provisions
in the ROD. Thus, the TRC offers
opportunities to inform the public
of site activities, obtain early
feedback, and build consensus
among public groups before the PP
and the ROD are issued.
IV.4   Expediting Document
       Preparation and Review/
       Approval
    ie! final; -ste:
    you
                                                           iaster-
The goal of the opportunities and
methods described above, and the
goal of this  entire guide, is  to
expedite document preparation
and review en  route to a signed
ROD.   Project Managers can
streamline the writing of the PP
                               -35-

-------
     A
 and ROD by encouraging EPA and
 DoD team members to work closely
 in the preparation and review of
 these documents. Project Managers
 can accomplish this final step in the
 ROD   process  by  pursuing
 concurrent preparation of the two
 documents, joint preparation by the
 EPA and DoD Project Managers,
 and concurrent reviews of the
 documents.  Specific suggestions
 for implementing these approaches
 are presented in  the following
 sections.
IV.4.1  Joint DoD and EPA
        Preparation of the PP
        and ROD
                    : -to-' pirogjress:
                               "
Once the draft FS is available, joint
preparation of the PP and ROD can
start.  Rather than waiting for
DoD's first submittal of the PP and
ROD to  EPA for review and
approval, the DoD and EPA Project
Managers can write the PP and the
ROD together.  This approach
allows the Project Managers to
respond  immediately  to specific
language,  format,  or  other com-
ponents of the PP  that they know
their agencies or  other agencies
may not  approve.
Project Managers should always
begin by looking at other sites that
have posed similar issues. The list
of RODs contained in Appendix A
provides  information with which
Project Managers can target exist-
ing RODs that may be helpful. It
is a good idea to call the Project
Manager  for similar sites, find out
what lessons were learned, and lis-
ten for similar problems that may
arise.

When it comes to putting pen to
paper,  Project Managers can take
several approaches. For example,
the Project Managers can meet for
as long as necessary in the same
room to write the sections of the
PP and ROD.  Similarly, the Project
Managers  can jointly  write the
documents by sending draft copies
(hard copy or computer diskettes)
via facsimile or overnight mail.  In
actual case studies, both of these
approaches have been successful in
streamlining the ROD process.
                               -36-

-------
                                                           A
 IV.4.2  Concurrent Preparation
        of the PP and the ROD
 ' ',neede«j,:'
                            are
 Although the PP is released  for
 public comment before the ROD is
 finalized and signed, Project Man-
 agers can prepare both documents
 nearly simultaneously.  Time can
 be saved by submitting both docu-
 ments for internal DoD and EPA
 review and approval if Project
 Managers follow three basic steps.
 First, develop a draft PP. Second,
 prepare a draft of the ROD.  Third,
 submit both documents for inter-
 nal review.

 A draft ROD can be developed at
 the same time  the PP is being
 prepared by beginning with topics
 that are not dependent on the
 remedy, such as background on the
 site and  extent of contamination.
 Since the ROD contains many more
 details than the  PP for  legal
 purposes, a  summary of the issues
 can  be  developed  in  the  PP
 simultaneously in nearly all cases.
Project Managers can  often save
substantial  amounts  of  time  by
coordinating preparation of these
documents, as  long  as  they
maintain an open mind to changes
that may be needed once the PP is
issued. By proceeding in this way,
both documents can go through the
internal review process once. Thus,
the overall time for preparation and
internal review of the documents
is compressed.
IV.4.3  Concurrent Reviews of
       the PP and ROD

*  Develop a complete list of
'                      '     "   '
                            to;
   eliminate .unftecesSarf 'delays.* '•

Once the Project Managers have
prepared the PP and ROD, the for-
mal reviews  can  also  be ap-
proached concurrently.  Early in the
process, DoD and  EPA Project
Managers  should identify all the
agencies that will need to review
the PP and the ROD. For example,
each of the services have health
agencies that need to be included.
These are as follows, by service:

•  Army:   Army Environmental
   Hygiene Agency

•  Navy:  Navy Environmental
   Health Center

•  Air Force: Office of the Surgeon
   General

•  Defense  Logistics Agency:
   ATSDR.

Project Managers should develop a
complete list of required reviewers
                               -37-

-------
through discussions  with their
management. Figure 4 presents an
initial list of reviewers as a starting
point for Project Managers.

Project Managers will submit the PP
or the ROD for  formal review by
EPA, the State, other agencies,  and
each office  within  the  Project
Managers'  chain  of command
simultaneously. This way,  Project
Managers  do not have to wait for
EPA's review and concurrence, then
seek the State's review and comment,
and  then  repeat the process with
other agencies. If a reviewing agency
           does have comments or changes, the
           Project Managers must ensure that
           the changes are conveyed to each
           party reviewing the document
           simultaneously.  The  ROD process
           is complete once the document  has
           been signed by each  required
           signatory, culminating with  the
           signatures of the  EPA Regional
           Administrator  and his  or  her
           counterpart  in  the DoD service
           responsible for the site. Once signed,
           the DoD  Project Manager should
           ensure that a copy of the ROD is
           included in the Administrative
           Record for the site.
         EPA
  1 Project Manager
   and Management
  ' Underground
   Injection Control
   Staff
  • RCRA Technical
   Support Staff
  • CERCLA Technical
   Support Staff *
  • BTAG Staff *
  • Air Staff
  • Water Staff
  1 Regional Counsel
   and Management
  > Headquarters Staff,
   as Needed
   Review only
      Army
1 Army Secretariat
1 Army Staff (Army
 Environmental Office)
1 Major Command
• USATHAMA
1 Installation Staff
1 Army Environmental
 Hygiene Agency

    Air Force
• Installation
 Commander
• Installation Staff
1 Major Command
 Environmental Office
 with copies for the
 Office of the  Surgeon
 General, the Judge
 Advocate General,
 and the Office of
 Public Affairs
     Navy
• Commanding Officer
 of the Engineering
 Field Division
• Installation
 Commanding Officer
• Naval Facilities
 Engineering
 Command
 Headquarters

      DLA
• Director, Installation
 Services and Environ-
 mental Protection
• Chief, Environmental
 Division
• U.S. Army Corps of
 Engineers-Huntsville
 Division
• Installation
 Commanding Officer
                             Figure 4.
                        Potential Reviewers
                                -38-

-------
                    CONCLUSIONS

Project Managers can influence the pace of the ROD process
in many ways.  The lessons presented  in this guide are
approaches that have proven effective at other DoD facilities
on the NPL. EPA and DoD Project Managers are encouraged
to consider each of the opportunities for expediting the ROD
process that are presented in this guide and to share other
innovative approaches they find successful along their road
to ROD.

                 * •:» * * * «:• * * * »:• •:» * ***
                          -39-

-------

-------
                 AVAILABLE RESOURCES
   Hot Lines
•The Federal Facilities Docket
  Hotline (1-800-548-1016).

•The RCRA/Superfund Hotline
  (1-800-424-9346).
   Databases
These may only  be  accessible to
operating agency personnel.

• EPA: Superfund Comprehensive
  Accomplishments Plan (SCAP),
  Robin Richardson
  (202) 260-9367.

• EPA: The Records of Decision
  System (RODS) Database.
  Thomas Batts
  (202) 260-3770.

• EPA: The Cleanup Information
  Bulletin Board (CLU-IN).
  Dan Powell
  (703) 308-8827.
• EPA: Vendor Information System
  for   Innovative   Treatment
  Technologies (VISITT)
  Linda Fiedler
  (703) 308-8799.

• DoD:  Defense Environmental
  Restoration Program Manage-
  ment   Information   System
  (DERPMIS). Patricia Janssen
  (703) 695-8360.

• Department of the Navy:  The
  Navy Pollution Control Report
  (PCR), Contact:
  NAVFACENGCOM (code 18)
  Alexandria, VA 22332
  (703) 325-8538.

• Department of the Air Force:
  Work Information  Management
  System-Environmental Subsystem
  (WIMS-ES), DERA Module.
  R.J. Furlong, HQUSAF/CEVR
  (202) 767-4616

• Department of the Air Force:
  Installation Restoration Program
  Information Management System
  (IRPIMS)
  Phil Hunter
  AFCEE/ESRD, Brooks AFB, TX
  (800) 821-4528 ext. 281.

-------
 EPA Dockets
• Superfund Docket
  (202) 260-3046.

• RCRA Docket
  (202) 260-9327.

• Toxic Substances Docket
  (202) 260-3587.

• Air Docket
  (202) 260-7548.

• Drinking Water Docket
  (202) 260-9598.
                              -42-

-------
                        REFERENCES
  Statutes
 • The  Comprehensive Environ-
  mental Response, Compensation,
  and  Liability  Act  of  1980
  (CERCLA), 42 U.S.C. §§ 9601-
  9675 (1982 & Supp. IV 1986).

 • The Resource Conservation and
  Recovery Act (RCRA), 42 U.S.C.
  §§ 6921- 6939b (1982 and Supp.
  IV 1986).
  Regulations
• The National Oil and Hazardous
  Substances Contingency Plan (40
  CFR Part 300), March 8, 1990.

• Army Regulation (AR) 200-1,
  "Environmental  Protection and
  Enhancement," Chapter 9, April
  1990.
  Guidance
EPA Guidance

• "ECO Update: The Role of BTAGs
  in  Ecological Assessment," U.S.
  Environmental    Protection
  Agency, Off ice of Emergency and
  Remedial Response, Hazardous
  Site Evaluation Division (OS-230),
  OSWER Publication 9345.0-051,
  September 1991.

• "ROD Annual Report FY  1990,"
  EPA/540/8-91/067, Publication
  9355.6-04, July 1991.

• "Conducting RI/FS for CERCLA
  Municipal Landfill Sites," EPA
  Publication    540/P-91/001,
  February 1991.

• "Guidance on Remedial Actions
  for Superfund  Sites With PCB
  Contamination," EPA Publication
  540/G-90/007, August 1990.

• "Scoper's Notes," Publication No.
  EPA/540/G-90/002, OS-240,
  February 1990.

• "Guidance on Oversight of Poten-
  tially Responsible Party RI/FS,"
                              -43-

-------
 EPA Publication 540/2-90-011,
 OSWER Directive 9835.1 (c)(d),
 Volumes 1 and 2.

 "The Federal Facilities Hazardous
 Waste  Compliance Manual,"
 U.S. Environmental Protection
 Agency, Office of  Waste  Pro-
 grams Enforcement, Publication
 9992.4, January 1990. This docu-
 ment contains multiple guidance
 documents issued by both  EPA
 and DoD, which include the fol-
 lowing:

- Executive Order  12580  of
  January 23, 1987.

- "Agreement with the Depart-
  ment  of Defense — Model
  Provisions for CERCLA Federal
  Facility Agreements":  Memo-
  randum from J. Winston Porter,
  U.S. EPA to  Regional Admin-
  istrators, June 17,  1988.

- "Management  Guidance for
  Execution of the FY  1990/91
  Defense Environmental Resto-
  ration Program," Memorandum
  from the Office of the Assistant
  Secretary of Defense, September
  29,1989.  (Please note this has
  been   superseded  by   the
  November 15, 1991 document
  issued by DoD and identified
  under "DoD Guidance" below.)

- "Defense  Priority  Model:
  Defense Environmental Restor-
  ation  Program,"  54  Federal
  Register 43104, October 20,1989.
• "CERCLA Compliance  With
  Other Laws  Manual:  Parts I
  and  II,  "  EPA Publications
  9234.1-01  August  1988,  and
  9234.1-02,  August 1989.

DoD Guidance

• ODASD(E) "Management  Guid-
  ance for Execution of the FY
  1992/93 Defense Environmental
  Restoration Program," Memo-
  randum from the Office of the
  Assistant Secretary  of Defense,
  November  15, 1991.
• DA Pamphlet 40-578, "Health
  Risk Assessment Guidance for
  the Installation  Restoration
  Program and Formerly Used
  Defense    Sites,"    AEHA,
  February 25, 1991.

• "U.S. Army Installation Restor-
  ation Program  Guidance and
  Procedure,"    USATHAMA,
  December 1990.

• "Commander's Guide to Public
  Involvement in  the Army's In-
  stallation Restoration Program,"
  USATHAMA, November 1990.

• "Commander's    Guide    to
  Environmental  Management,"
  USATHAMA, October 1990.

• Technical  Note No.  420-10-2,
  "Work Classification Guidance
  for Defense  Environmental
                             -44-

-------
  Restoration Program  (DERP),"
  U.S.  Army Engineering and
  Housing Support Center, Fort
  Belvoir, VA, April 6, 1990.

  Navy

• OPNAVINST5090.1A, "Environ-
  mental and Natural  Resources
  Program Plan," October 1990.

  Air Force

• "U.S.  Air Force Installation
  Restoration Program  Manage-
  ment Guidance," 1989.

  DLA

• "Environmental Protection Man-
  ual,"  Defense Logistics Agency
  Manual (DLAM) 6050.1, July
  1991.
     Report
       and
   Fact Sheets
2 +
4 x
FACTS
2 = 4 2+2=4
3 = 9 3x3=9
2 = 8 4x2 = 8
 "ARARs-Assist System, Avail-
 ability  of  [Computer-aided
 Environmental Legislative Data
 System] CELDS Computerized
 Database for the Identification of
 ARARs," OSWER Publication
 9234.2-19FS, September 1991.
"Guide to Addressing Pre-ROD
and  Post-ROD   Changes,"
OSWER  Publication 9355.3-
02FS-4, April 1991.

"Guide to Developing Superfund
No Action, Interim Action, and
Contingency Remedy RODs,"
OSWER  Publication 9355.3-
02FS-3, April 1991.

"Defense  Environmental  Resto-
ration Program Annual Report to
Congress for Fiscal Year 1990,"
February 1991.

"A Guide to Developing  Super-
fund  Records  of  Decision,"
OSWER  Publication 9335.3-
02FS-1, May 1990.

"A Guide to Developing  Super-
fund Proposed Plans," OSWER
Publication 9335.43-02FS-2, May
1990.

"A Guide to Selecting Superfund
Remedial Actions," OSWER Pub-
lication 9355.0-27FS, April 1990.

Additional fact sheets on ARARs
(OSWER Publications 9234.1-
01FS to -07FS); on Land Disposal
Restrictions (OSWER Publica-
tions 9347.3-01FS to -08FS); and
on the RI/FS (OSWER Publica-
tions 9355.3-01FS to  -01FS4 and
9380.3-02FS).
                             -45-

-------
• "Superfund Records of Decision
  Update,"  OSWER  Publica-
  tion 9200.5-2161,  Intermittent
  Bulletins.

• Additional  fact   sheets  on
  remediation  and treatment
  technologies can  be obtained
  from the Superfund Documents
  Coordinator, EPA Headquarters,
  (202) 260-9760.
                              -46-

-------
AEHA

AFB

ARAR


ATSDR

BTAG

CERCLA


CFR

CWA

DA

DBCP

DERP

DLA

DLAM

DNT

DoD

DOE

DSMOA

EPA

ESD

FFA

FY
 LIST OF ACRONYMS

Army Environmental Hygiene Agency

Air Force Base

Applicable and Relevant or Appropriate
Requirements

Agency for Toxic Substances and Disease Registry

Biological Technical Assistance Group

Comprehensive Environmental Response, Compen-
sation, and Liability Act of 1980

Code of Federal Regulations

Clean Water Act

Department of the Army

Dibromochloropropane

Defense Environmental Restoration Program

Defense Logistics Agency

Defense Logistics Agency Manual

Dinitrotoluene

Department of Defense

Department of Energy

Defense and State Memorandum of Agreement

Environmental Protection Agency

Explanation of Significant Differences

Federal Facility Agreement

Fiscal Year

-------
             LIST OF ACRONYMS (continued)

FS                 Feasibility Study

GAC               Granulated Activated Carbon

GB                German Brown

GW               Ground Water

IAG               Interagency Agreement

IRM               Interim Remedial Measure

MAJCOM          Major Command

NAVFACENGCOM  Naval Facilities Engineering Command

NCP               National Oil and Hazardous Substances Pollution
                   Contingency Plan

NPDES            National Pollutant Discharge Elimination System

NPL               National Priorities List

OERR              Office of Emergency and Remedial Response

OFFE              Office of Federal Facilities Enforcement

OSWER            Office of Solid Waste and Emergency Response

OU                Operable Unit

OWPE             Office of Waste Programs Enforcement

PA                Preliminary Assessment

PCB               Polychlorinated Biphenyl

PCE               Perchloroethylene

PP                 Proposed Plan

RA                Remedial Action


                             -48-

-------
             LIST OF ACRONYMS (continued)




 RCRA             Resource Conservation and Recovery Act




 RD                Remedial Design




 RI                 Remedial Investigation




 ROD              Record of Decision




 RODS             Records of Decision System




 RDX              Hexohydro-lAS-Trinitro-lAS-Triazine




 RPM              Remedial Project Manager




 SARA             Superfund Amendments and Reauthorization Act




 SCAP             Superfund Comprehensive Accomplishments Plan




 SI                 Site Investigation




 SW                Surface Water




 TBC               To Be Considered




 TCE               Trichloroethylene




 TMV              Toxicity, Mobility, and Volume




 TNT               Trinitrotoluene




 TRC               Technical Review Committee




 TQM              Total Quality Management




 TSCA              Toxic Substances Control Act




USATHAMA       U.S. Army Toxic and Hazardous Materials Agency




UV                Ultraviolet




VOC               Volatile Organic Compound
                              -49-

-------
Appendix A.
ROD Summary for DoD Sitesl> 2
    Site Name,                 Signed                    Threat
    State                      ROD Date
  West Virginia                 3/27/87              Organics and asbestos
  Ordnance,                                          in soil, sediments, and
  WV                                                SW line
  Rocky Mountain               6/4/87               VOCs, TCE, and
  Arsenal,                                            inorganics in GW
  CO
  West Virginia                 9/30/88              Nitroaromatics and lead
  Ordnance,                                          in soil, sediments, and
  WV                                                GW

  Twin Cities Army             8/11/89              VOCs, TCE, PCE, PCBs,
  Ammunition  Plant,                                 and metals in soil
  New Brighton/Arden Hills,
  MN

  Pica tinny                      9/28/89              VOCs, TCE, and metals
  Arsenal,                                            in GW
  NJ

  Sacramento                    9/29/89              VOCs, PCE, and TCE
  Army Depot,                                       in GW
  CA

  Rocky Mountain               2/26/90              Organics, arsenic, mer-
  Arsenal (O.U. 23),                                  cury, pesticides, TCE,
  CO                                                DBCP, organosulfur
                                                     compounds
   Much of the information presented in Appendix A is available from the Records of De-
   cision System  (RODS) database, which is stored on EPA's IBM mainframe in Research
   Triangle Park, North Carolina. The RODS database tracks information on each ROD
   such as signature date, site name, remedy, key contaminants, and a full text of the ROD.
   The database is menu-driven and allows rapid searches on these data.  Direct access to
   the RODS database is available to EPA staff, EPA contractors,  State personnel,  and
   Federal facility representatives who can register for a user account established by EPA 's
   Office of Emergency and Remedial Response.  Information on accessing the RODS data-
   base is available from the RODS staff at (202)260-3770.
                                   -52-

-------
      Selected
      Remedy
EPA Contact
DoD Contact
In-situ flaming treat-
ment; cap; excavation,
flushing, and back-
filling; off-site disposal

Construction of GAG
water treatment; re-
placement of well pumps
and motors; installation
of transmission piping

GW treat and pump
with discharge to
SW; cap

On-site mobile infrared
thermal  treatment
 Robert Thomson
 FTS 597-7858
 (215)597-7858
 Connally Mears
 FTS 330-1528
 (303)293-1528
 Robert Thomson
 FTS 597-7858
 (215)597-7858

 Tom Baroonis
 (312)353-5575
  Joseph Turner
  (304)529-5282
  Kevin Blose
  (303)289-0201
 Joseph Turner
 (304)529-5282
  Martin Cleary
  (612)633-2301
  Extension 662
GW pump and treat
with discharge to SW
GW pump and treat
In-situ vitrification;
vapor extraction; GW
extraction and treat-
ment with GAG; slurry
wall; vegetative  cap
 Bill Roach
 FTS 264-8775
 (212)264-8775

 Marlin Mezquita
 FTS 484-2393
 (415)744-2393

 Connally Mears
 FTS 330-1528
 (303)293-1528
 Ted Gabel
 (201)724-6748
 Thomas Baker
 (209)726-4841
 Kevin Blose
 (303)289-0201
All acronyms used in this appendix are defined in the "List of Acronyms" section
of this guide.
                                     -53-

-------
Appendix A.
ROD Summary for DoD Sites (continued)
Site Name,
State
Rocky Mountain
Arsenal (O.U. 20),
CO
Tinker AFB,
OK
Ogden Defense
Depot,
UT
Dover AFB,
DE
Naval Industrial
Reserve Ordnance,
Plant,
MN
Naval Air Engineering
Center (Area C),
NJ
Naval Air Engineering
Center (Area H),
NJ
Rocky Mountain Arsenal,
South Tank Plume Farm,
CO
Robins AFB,
GA
Signed
ROD Date
3/20/90
8/15/90
9/27/90
9/28/90
9/28/90
2/4/91
2/4/91
6/6/91
6/26/91
Threat
Pesticides, heavy metals,
organics
VOCs including benzene,
PCE, TCE, toluene and
xylenes; other organics,
and metals in GW
and soil
Solvents and pesticides
inGW
Petroleum
hydrocarbons in soil
VOCs including PCE,
TCE, toluene, and
xylene in GW
GW contamination,
petroleum hydrocarbons
GW contamination,
petroleum hydrocarbons
Benzene, toluene,
xylene, and
bicycloheptadiene
GW contamination, or-
ganics, metals (primarily
arsenic, cadmium, lead),
tetrachloroethylene,
trichloroethylene
                             -54-

-------
Treat wastewater using
physical/chemical
methods, including UV
oxidation and GAC

GW pump and  treat;
off-site disposal; cap;
vapor extraction; GW
monitoring
Pump and treat GW;
dispose of soils off site
Remove underground
storage tanks and pipes

GW pump and treat;
off-site disposal
GW pump and treat; on-site
treatment; off-site disposal of
residuals

GW pump and treat; on-site
treatment; off-site disposal of
residuals
Monitoring and reeval-
uation of contaminated
GW plume
"Source Control" to min-
imize release of contaminants;
soil vapor extraction, solid-
ification/stabilization;
leachate collection
Connally Mears
FTS 330-1528
(303)293-1528
Susan Webster
(214)655-6730
Sandra Bourgeois
FTS 330-1975
(303)294-1975

Bruce Beach
(215)597-2317

Thomas Bloom
(312)886-7254
Jeff Gratz
(212)264-6667
Jeff Gratz
(212)264-6667
Connally Mears
(303)293-1528
Rosanne Rudd
(404)347-3016
Kevin Blose
(303)289-0201
Cpt. Dan Welch
(405)736-5102
Dale Fredde
(801)399-7848
Matt Parker
(302)677-6817

Jim Shafer
(215)897-6432
Lucy Bottomley
(908)323-2612
Lucy Bottomley
(908)323-2612
Daryl Smith
(303)289-0239
Bill Downs
(912)926-0983
                                      -55-

-------
Appendix A.
ROD Summary for DoD Sites (continued)
    Site Name,
    State
  Signed
ROD Date
       Threat

 Letterkenny Army Depot,
 Southwest Area,
 PA
 8/2/91
 Rocky Mountain Arsenal,
 RMA Chem-Process,
 CO
 Bangor Naval Marine
 Base (Site F),
 WA
 McCord AFB,
 WA
Aberdeen Proving
Ground/Michaelsville
(O.U. 4), White
Phosphorous Underwater
Munitions Burial Area,
MD
Aberdeen Proving
Ground/Edgewood
(O.U. 5), Old "O"
Field Groundwater,
MD
Hill AFB,
UT
9/5/91
9/19/91
9/19/91
9/27/91
9/27/91
9/30/91
Soil contaminated
with organic compounds,
xylene, trans-1-2 dichloro-
ethylene, ethylbenzene,
trichoroethylene
Nerve agents, blister
agents (mustard gas,
GB, lewisite)
Ordnances, TNT, RDX
GW contamination,
trichloroethylene,
dichloroethylene
Environmental threat of
white phosphorous in
water
Metals, volatiles, and
military-unique
chemicals discharged
to Chesapeake Bay
Dense nonaqueous
phase liquid solvents,
TCE, other solvents

                                -56-

-------
      Selected
      Remedy
 EPA Contact
 DoD Contact
 Low-temperature
 thermal stripping
Dennis Orenshaw
(215)597-7858
Decontamination and
neutralization technique
using sodium hydroxide
and water
GW pump and treat;
treatability study with
UV oxidation technology
GW pump and treat;
GW extraction; carbon
absorption treatment
No effective action;
monitoring during storm
events or dredging
GW extraction and
treatment with chemical
precipitation and
UV oxidation
Pump and treat dense
nonaqueous phase liquid
Connally Mears
(303)293-1528
Howard Blood
(206)553-1172
Marie Jennings
(206)553-6637
Steve Hirsh
(215)597-0549
Steve Hirsh
(215)597-0549
Robert Stites
(303)294-1974
Peg Geiseking
(717)267-9690
Gerald Barbieri
(303)289-0125
Bela Varga
(206)476-5775
Michael J. Gremko
(206)984-3913
John Wroble
(301)671-3320
Cindy Powell
(301)671-3320
Bob James
(801)777-8790
                                      -57-

-------
                         Appendix B.
              Summary of Key Requirements
Section 120 of CERCLA

Upon  the  enactment of  the
Superfund  Amendments and
Reauthorization Act (SARA) in 1986,
Federal facility involvement and
compliance   with    CERCLA
requirements became mandatory.
Since then, DoD has been defining
its role in the CERCLA process.

Section 120 clearly states that "each
department, agency  ... of the
United States shall be subject to,
and comply with [CERCLA], in the
same manner and to  the same
extent, both procedurally and
substantively, as any nongovern-
mental entity."  In particular,
Federal facilities are subject to EPA
enforcement   actions,  public
participation requirements, and
citizen suits. The statute provides
for joint selection of the remedy on
NFL sites by EPA and the Federal
agency; however, if no agreement
can be reached, EPA will select the
remedy.  Section 120 does exempt
Federal facilities from provisions in
the  law concerning  financial
assurances and contracts with State
governments.   In addition,  the
President can exempt DoD and the
Department of Energy (DOE)
facilities  from any  statutory
requirements to protect national
security interests.

One important provision of Section
120   of   CERCLA   was  the
requirement to establish a special
Federal Agency Hazardous Waste
Compliance   Docket  (Federal
facilities  Docket  or the Docket).
This Docket is an inventory of
Federal facilities that generated,
treated, stored,  or disposed of
hazardous waste or reported a
release or potential  release of
hazardous substances. Of the 1,654
facilities listed on the Docket, DoD
accounts  for approximately 50
percent.    Generally,  any  Federal
facility that submitted information
to EPA  under  Section  103 of
CERCLA  or Sections 3005, 3010, or
3016 of RCRA is  added  to the
Docket.  Once  on the Docket, the
Federal agency must conduct a
Preliminary Assessment  and, if
warranted, a Site  Investigation.
Facilities will be evaluated with the
Hazard  Ranking  System  and
possibly added to the NPL,  thereby
increasing  the  scope   and
requirements  of  the remedial
response.

Section   120  of  CERCLA  also
establishes strict  scheduling
requirements for the administrative
process in evaluating and miti-
gating hazardous threats at Federal
facilities.   In addition, it specifies
schedules for commencement of
RI/FSs, negotiation of IAGs, and
implementation and completion of
Remedial Actions.
                              -58-

-------
Section 211 of CERCLA

Section 211  of CERCLA amends
Title 10 of the U.S. Code (Armed
Forces), inserting a chapter on
Environmental  Restoration.  This
chapter requires the Secretary of
Defense to carry out a program of
environmental restoration  at
facilities under his jurisdiction.
This program  is known as the
Defense Environmental Restoration
Program (DERP).  In establishing
such a program  in  the statute,
Congress  required DoD  to plan,
budget for, and  implement an
environmental program to address
threats to human health and the
environment   posed  by  DoD
facilities.

Executive Order 12580

Executive Order 12580, signed by
President  Reagan on January 23,
1987, delegated authority to Federal
agencies  to implement certain
provisions of CERCLA.  Specif-
ically, Section 2(d) of the Executive
Order delegates to the Secretaries of
Defense and Energy the functions of
CERCLA Sections 104(a) and (b) and
c(4) [Investigations, Coordination,
and Selection of Remedy]; Section
113(k)  [Administrative Record];
Section 117(a) and (c) [Proposed Plan
and  Explanation of Differences];
Section 119  [Response  Action
Contractors]; and Section 121 [Clean-
Up Standards] consistent with
Section 120 of CERCLA.

What this order means is that instead
of EPA having responsibility to
implement the above provisions of
CERCLA, DoD is responsible for its
own sites.  DoD will be held
accountable by Congress  for the
meeting the requirements  of these
provisions.

Subpart K of the NCP

The  regulations  that interpret,
clarify,  and   implement  the
provisions of CERCLA are found in
the NCP (40 CFR Part 300, March 8,
1990).  However,  the  regulations
governing  CERCLA  activity at
Federal facilities (Subpart K of the
NCP) were reserved at that time.

Subpart K of the NCP will codify the
requirements of  Section  120 of
CERCLA and provide a road map of
the entire NCP by identifying the
requirements of the NCP  that are
applicable to Federal agencies
conducting CERCLA response
actions.
                              -59-

-------

-------