P^^pubtication -^440.2. fati EPA
    and State. Solid. Waa-te. Management Agencies
                                    530SW146C
        A TECHNICAL, ENVIRONMENTAL

    AND ECONOMIC EVALUATION OF THE  GLASS

     RECOVERY  PLANT AT FRANKLIN, OHIO
                (SW-746C)
    t/te FedeAa£ 4o£^i tuaA-te management
         undeA contract KIO. 68-012211
and 
-------
This report as submitted by the grantee or contractor has been
technically reviewed by the U.S. Environmental Protection Agency (EPA).
Publication does not signify that the contents necessarily reflect the
views and policies of EPA, nor does mention of ccnmercial products
constitute endorsement by the U.S. Government.

An environmental protection publication (SW-146C) in the solid waste
management series.

-------
                    TABLE OF CONTENTS


SECTION    	    PAGE

            ILLUSTRATIONS                               V

            LIST OF TABLES                             vi

 1.0        SUMMARY OF EVALUATION                       1

            1.1  Introduction                           1
            1.2  Plant Performance                      2
            1.3  Brief Glass Plant Operational
                      Description                       3
            1.4  Technical Evaluation                   6
            1.5  Environmental Evaluation               9
            1.6  Economic Evaluation                   12

 2.0        INTRODUCTION                               20

            2.1  Program Evaluations                   20
            2.2  History And Background                22
            2.3  Plant Description                     25

 3.0        OPERATIONAL CAPABILITY                     30

            3.1  Equipment Description                 30

 4.0        TECHNICAL EVALUATION OF THE GLASS
               RECOVERY PLANT                          36

            4.1  Evaluation Methods Used               36
            4.2  Results Of The Technical Evaluation   41

 5.0        ENVIRONMENTAL EVALUATION OF THE
                FRANKLIN GLASS PLANT                   56

            5.1  Introduction                          56
            5.2  Environmental Impact On Air Quality   57
            5.3  Environmental Impact On Water Quality 60
            5.4  Environmental Impact On Land          61
            5.5  Noise                                 63
            5.6  Comments on Industrial Hygiene        64
                             111

-------
                    TABLE OF CONTENTS


SECTION	    PAGE

  6.0       ECONOMIC ASSESSMENT                          67

            6.1  Introduction                            67
            6.2  Approach To Developing The
                    Economic Data                        69
            6.3  Development Of Cost Data And
                    Projected Economics                  70
            6.4  Cost Summary Of Franklin Solid
                    Waste Facility                       91
            6.5  Economic Observations                   93

APPENDIX A  PICTORIAL FLOW DIAGRAMS                      96

APPENDIX B  GLASS PROCESSING INDUSTRY SPECIFICATIONS
               FOR GLASS GULLET                         104
                               IV

-------
                      ILLUSTRATIONS


FIGURE    	    PAGE

  1.1      Modified Franklin Glass Recovery System - 1976    4

  1.2      Effect Of Tipping Fee On AROI For A 1000 TPD
               Total Franklin Facility                      18

  2.1      Configuration Of First Prototype Glass Plant
               As Constructed In 1974                       29

  4.1      Glass Recovery System Study Matrix               37

  4.2      Glass Plant Sampling Points                      39

  4.3      Glass Plant Process Flow With Output
               Characteristics                              43

  4.4      Material Balance Diacra-> For Glass And
               Aluminum Recovery System                     48

  5.1      Franklin Solid Waste Gla-s Plant Scrubber -
               Air Evaluations                              59

  5.2      Process Water Characteristics                    62

  6.1      Projected Facility Description For A Franklin
               Glass Plant Sized To Process Feed From A
               500 TPD Plant                                74

  6.2      Projected Facility Description For A Franklin
               Glass Plant Sized To Process Feed From A
               1000 TPD Plant                               75
                                v

-------
                     LIST OF TABLES


NO.	    PAGE

1.1     Glass Plant Cost Balance                            14

1.2     Economic Summary Of Projected Franklin Plant
          With No Fiber Recovery, With Glass Plant, And
          Selling Rejects  As A Fuel                        16

1.3     Before Tax AROI For 500 And 1000 TPD Total
          Facility                                          17

6.1     Income Sources                                      71

6.2     Revenue Factors                                     71

6.3     Operating Labor                                     77

6.4     Maintenance Labor                                   78

6.5     Capital Costs For 500 TPD Franklin Glass Plant
           (Process Described In Figure 6.1)                 84

6.6     Capital Costs For 1000 TPD Franklin Glass Plant
           (Process Described In Figure 6.2)                 85

6.7     Monthly Franklin Glass Plant Costs Projected
          To 500 TPD                                        89

6.8     Monthly Franklin Glass Plant Costs Projected
          To 1000 TPD                                       90

6.9     Economic Summary Of Projected Franklin Plant
          With No Fiber Recovery, With Glass Plant,
          And Selling Rejects As A Fuel                     92
                               VI

-------
1.0       SUMMARY OF EVALUATION

1.1       INTRODUCTION
This report presents an evaluation of the Glass Recovery
Plant in the Franklin Solid Waste and Fiber Recovery Facility.
This evaluation includes technical, economic and environ-
mental assessments of the "Glass Plant" portion of the
Franklin plant.

The Franklin plant is an EPA demonstration project which
incorporates solid waste processing and resource recovery
using wet processing techniques.  These techniques are
extensions of pulp and paper industry technology.  The
operation of this solid waste processing plant begins with
the pulping of incoming refuse to form a liquid slurry with
the concomitant removal of large nonpulpable items, followed
by the further separation of dense materials (cyclone rejects)
from the main process stream.  The cleaned main stream or
light fraction is subsequently processed to recover long
cellulose fibers.  The nonrecoverable portion of the light
stream is ultimately incinerated.

The system of interest to this report is an add-on to the
original solid waste handling plant.   It was intended to
demonstrate the removal and recovery of glass and metals from

-------
the cyclone rejects, i.e., the stream of small dense materials

removed from the fiber recovery stream immediately after

pulping.



A complete evaluation of the main portion of the Franklin

plant was reported previously by Systems Technology Corporation

in "A Technical, Environmental and Economic Evaluation of the

Wet Processing System for the Recovery and Disposal of

Municipal Solid Waste," by Wittmann et al.1  The reader is

advised that much of the present report may be more readily

understood if used in conjunction with the previous st'
1.2       PLANT PERFORMANCE

During its operating history, the glass plant has undergone

several changes and modifications.  These changes involved

both mechanical corrections, major component renovations and

additions.  The data collected for this report was limited

to a six-week period (February to March 1976) after the

system had been sufficiently upgraded to continuously produce

an acceptable product while operating as a production plant.

This evaluation has demonstrated that the separation and

recovery processes operating during the study period offer a
 iT. J. Wittmann, D. J. McCabe, and M. C. Eifert, A Technical
 Environmental and Economic Evaluation of the Wet Processing
 System for the Recovery and Disposal of Municipal Solid Waste,
 EPA Contract 68-01-2211, January 1975.

-------
viable option for the recovery of aluminum and glass from



the cyclone rejects stream.  Since the study period,



additional system changes have improved the product yields



and quality.  However, that data was not available for this



report.







Glass recovery at the Franklin plant can be looked upon as



a two-stage operation.  The first stage is a wet process



subsystem using magnetic separation and density separation



techniques to produce a marketable aluminum fraction plus



a glass rich fraction which is cleaned of magnetic metals,



aluminum and most organics.  The second stage is a dry



process utilizing electrostatic and optical sorting techniques



to produce a clean glass fraction.  During this study, the



glass fraction was separated into flint and mixed color glass



fractions  (flint/amber/green).







1.3       BRIEF GLASS PLANT OPERATIONAL DESCRIPTION



Full descriptions of the theory of operation regarding the



individual separation processes involved in the glass plant



are presented in subsequent sections of this report.  In



this section a brief overview of the plant operation is



given.  A  flow diagram of the glass plant as it was operated



during this evaluation is shown in Figure 1.1.

-------
CO
o
a.
CO
<
cc
Q
O
cc
LL

CC
O
>
UJ
>
z
O
O
     CC
     O
     >
     LJJ
*: CJ U
CD O CC
               CC

               O



               CC
               <
               o.
               UJ
               CO
   ^ CC    ULJ
>  £ 2  »- 5
?£<££

si§|a
"•  '•  uj  5 I
cc
o
>
UJ
>
z
o
o
o

I
CO
<
RATOR


IEDIA RECOVERY
^
ING SCREEN
cc
LUMINUM DEWATE
<


G
ONVEYOR
-> o


cc
UJ
>
cc
Q
3NETIC PULLEY
OT-cMco
                            10  CO
                                            00
                                                o
                                                CM
                               T- CM  CO
                               CVJ 
-------
The glass and aluminum rich fraction of the refuse separated
from the input waste by the liquid cyclone is partially
dewatered and delivered to a surge bin for temporary storage
and feed rate control.  This material is then metered at
a fixed rate into the glass plant.   Since many of the
separation processes are size dependent, the first operation
in the glass and aluminum recovery processing is a washing
and sizing step to remove particles smaller than 1/4 in.
From there the process stream passes a rotating drum magnet
which removes the magnetic materials from the process
stream.  The magnetically cleaned process stream is then
delivered to a heavy media separator where materials with
a specific gravity less than 1.8  (mostly organic materials)
float and are removed for landfill disposal.  Materials with
a specific gravity greater than 1.8 (glass, stones, metals)
sink in the heavy media separator and are carried to a jig
where the aluminum is separated from the glass and stones.
The aluminum rich fraction prepared by the jig can be stored
for market, or upgraded to improve its market value.

The glass rich process stream is dewatered on a vibrating
screen and dried in a kiln dryer.  The dried material is
then conveyed to a high-tension electrostatic separator for
the removal of any remaining conducting materials, such as

-------
metals or any hygroscopic materials which might reabsorb
sufficient moisture to show a high surface conductivity.

The materials passing the electrostatic separator are
conductors which consist mostly of glass.  They enter the
final separation process that utilize differences in optical
properties to segregate glass and stones.  The material first
passes through a transparency sorter.  Here, the opaque
materials are rejected and removed for landfill disposal.
The transparent materials are then color sorted into a flint
and a mixed color glass product.  Both of these final glass
products are commercially salable glass cullets.  If desired,
the mixed color glass product can be further color sorted
into an amber and a green product, both of which have a
higher market value than the mixed color glass cullet.

1.4       TECHNICAL EVALUATION
The Glass Recovery Plant is a major subsystem of the Franklin
Solid Waste and Fiber Recovery  Facility.  The feed to the
glass plant originates in the pulping and separation system
of the solid waste processing facility.  After the solid
waste is pulped, the material is pumped  through a cyclone
where the slurry is separated into heavy and light fractions.
The  light fraction from  the cyclone  is processed  in  the  fiber

-------
recovery system, and the heavy fraction from the cyclone
is fed to the glass plant.

During the evaluation period, 228 pounds of cyclone rejects
were generated for every ton of refuse deposited on the
tipping floor.  These cyclone rejects would normally
constitute the feed to the glass plant.  Because of size
limitations in some glass plant components, the glass plant
did not process all of the cyclone rejects that were available
Instead, the glass plant operated on a slip stream.  The
cyclone rejects have the following composition:

                                      Percent*
            Flint Glass                  38
            Colored Glass                18
            Magnetics                     9
            Aluminum                      5
            Other Metals        .          0.3
            Organics                      8
            Plastic and Rubber            8
            Ceramics and Stones          12
            Miscellaneous                 3
 *Percentages may not add to  100 due to rounding of  individually
 determined values.

-------
The following diagram shows the mass balance for the glass
plant assuming that all the cyclone rejects were processed.
The percentages refer to the ultimate disposition of input
to the glass plant.  The numbers in parentheses are pounds
of material recovered per ton of refuse deposited on the
tipping floor given in pounds per tipping floor ton
(abbreviated to #/TFT).
      INPUT
      100%
  (228#/TFT)
GLASS AND
 ALUMINUM
  RECOVERY
   SYSTEM
                                  MAGNETIC MATERIALS
                 13% (30#/TFT)
                 ALUMINUM RICH MATERIALS
4% (8.5#/TFT)
FLINT GLASS
                                  15% (35#/TFT)
                                  COLORED GLASS
                                  10% (23.5#/TFT)
                                  TO LANDFILL
                                  58% (131#/TFT)
 The  separation  efficiency  of  any unit  operation,  involves
 both the  efficiency of  removal  (the  ratio of removed material
 to available  material)  and the  cleanliness of the product
 in terms  of the fraction of the recovered product that is
 contaminanted.   This data  was obtained for the product streams
 emanating from  the glass plant.

-------
The magnetic separator recovered 86 percent of the magnetic
materials in the glass plant feed, but produced a product
which was 59 percent magnetics and 41 percent contaminant.

The jig separator recovered 50 percent of the aluminum
from the glass plant feed and produced a product which was
62 percent aluminum and 38 percent contaminant.

The optical sorters produce a flint glass product and a
mixed color glass product.  The flint glass product contains
39 percent of the flint glass in the glass plant input
feed and is 96.0 percent flint glass, 2.9 percent green glass,
0.7 percent amber glass, 0.3 percent ceramics and stones and
0.1 percent other contaminants.  The optical sorters recover
58 percent of the colored glass available in the glass plant
feed as a mixed color glass cullet.  This product is 99.2
percent glass, 0.7 percent ceramics and stones and 0.1 percent
other contaminants.

1.5       ENVIRONMENTAL EVALUATION
The glass plant evaluated in this study was designed specifi-
cally as a back-end to the pulping and separation system.
As such, it would be meaningless to discuss the environmental
impact of the Glass Recovery Plant alone.  Therefore, the
evaluation investigated the environmental impact of the total

-------
solid waste plant which was presented in the report of



Wittmann et al.2  However, where possible and meaningful,



independent environmental assessments were made exclusively



on glass plant operations.







1.5.1     Environmental Impact On Air



Those portions of the glass plant which could impact on air



quality include the dryer off-gases and the dust created at



several locations in the plant.  In-plant dust control is



accomplished with a hooding system with the dusty air being



cleaned in a Venturi scrubber prior to atmospheric discharge.



The dryer exhaust is vented through the same Venturi scrubbing



system.  Tests performed indicate that the system exhaust



gas has a composition similar to normal air with a particulate



emission rate equivalent to 3 percent of the allowable



particulate emission in the State of Ohio for such a system



on a process weight basis.







1.5.2     Environmental Impact On Water



There is no water emitted from the glass plant to the environ-



ment.  All water used in the glass plant is returned to a



common sump and pumped to the Whitewater sump in the pulping



and separation system where it is used as dilution water.



The dilution water contaminant level is lower than that





2 Ibid.
                               10

-------
existing in the Whitewater system and, when so used, does
not degrade the Whitewater quality.  Thus, there is no
significant environmental effect on water quality due to
the operation of the glass plant.

Glass 'plant water usage was 1930 gallons per hour of
operation.  This usage was dependent on equipment size (much
of which is oversized) and does not relate directly to
throughput tonnage.  For example, the jig could process
5 tons of material per hour with no significant increase
in water usage.

1.5.3     Environmental Impact On Land
A result of operating the glass plant is a 24 percent decrease
in the amount of material to be landfilled.  Furthermore,
the solid materials emanating from the glass plant have not
been degraded by that processing; thus, they are equivalent
in composition to the totality of the liquid cyclone effluent
stream which otherwise would be landfilled.  On a dry weight
basis, approximately 6.5 percent of the input to the tipping
floor is landfilled via the glass plant.

1.5.4     Noise Pollution
Noise measurements taken throughout the glass plant indicate
consistent noise levels in excess of  90 dBA which is the OSHA
limit for 8 hour exposure.  A major cause of noise  in the
                                11

-------
glass plant is the operation of vibratory conveyors and
bucket elevators filled with primarily nonresilient solids,
i.e., metal fragments and glass particles.  Any new plant
of this type would require a different type of conveyor
system or enclosures around the bucket elevators and vibratory
conveyors to achieve compliance with present OSHA noise
regulations.

1.5.5     Odor Analysis
No appreciable odor is present in the glass plant since the
material being processed is washed in the first stage of
the processing.  This washing removes the majority of
putrescible matter contained in the process stream.  Thus,
as long as the system continues to operate and large quantities
of cyclone rejects are not retained within the plant, odor
is not expected to be a significant problem.

1.6       ECONOMIC EVALUATION
Economic data presented are based on the operation of the
present glass and aluminum recovery system, scaled to 500 TPD
and  1,000 TPD plants and with system changes indicated for
improved operation.
                                12

-------
Economic data is not given for the present system since it
includes equipment with different throughput capacities.
Some equipment is considerably oversized and others under-
sized for the plant's processing requirements.  Thus, any
economic analysis of the existing glass and aluminum recovery
system shows disproportionately high capital costs for the
oversized equipment, disproportionately low capital costs
for the undersized equipment, and generally disproportionately
high operating costs for the total system because of this
disparity in equipment sizes.  The net operating costs and
income for a glass plant serving 500 and 1,000 TPD solid
waste processing plants are displayed in Table 1.1.  The
costs are normalized per ton of solid waste entering the
plant.  Note that the loss associated with the glass plant
operation indicates that the plant cannot pay for itself
or make a profit for the investor.

The glass plant alone is not a money maker at 500 TPD; but
at 1,000 TPD, it is projected as a break even operation.  It
should be noted that the revenue from the sale of aluminum
is twice that received from the sale of glass.

A glass plant requires a front-end system to provide the
glass plant process stream.  Hence, the total economics of
both the front-end system and the glass plant should be
                              13

-------
    TABLE  1.1    GLASS  PLANT COST BALANCE



                             500 TPD     1,000 TPD

 Capital Costs*             $1,874,000   $3,290,000

 Facility  Expense**           $1.70/T      $1.49/T

 Operating Expense           $2.19/T      $1.48/T

 Income

    Magnetic Sales (125/T)"*"  $0.02/T      $0.02/T

    Aluminum Sales ($300/T)  $1.95/T      $1.95/T

    Glass  Sales

      Flint ($20/T)           $0.60/T      $0.60/T

      Amber ($20/T)           $0.22/T      $0.22/T

      Green ($20/T)           $0.13/T      $0.13/T

              Total  Income   $2.93/T      $2.53/T

 Net Savings (Loss)          ($0.96/T)    ($0.04/T)
 +Assumed Sale Price for each Recovered Product - $/T
 *Includes Financing Costs
**Based on Capital Recovery Factor of .11683  (15 years
    at 8 percent).
                        14

-------
considered.  Table 1.2 summarizes the economics of a Franklin
type facility with a glass recovery subsystem.  Note that
the analysis excludes fiber recovery but it does include the
sale of all the fiber from the system as fuel.  Revenues
from sludge disposal and magnetic and nonmagnetic metal
sales are included.  The glass plant data is separated
from the pulping and separation system economics for easy
assessment of the glass plant's relative contributions.

The net savings for a 500 TPD plant is $1.28 and for 1,000 TPD
the net savings if $3.19/T.  No tipping fee is included in
this analysis.  One can quickly realize that the wet process
is more financially attractive without a glass and aluminum
recovery system.  However, at 1,000 TPD, the analysis shows
that a glass plant becomes less risky.
                               15

-------
   TABLE 1.2  ECONOMIC SUMMARY OF PROJECTED FRANKLIN
               PLANT WITH NO FIBER RECOVERY, WITH GLASS
               PLANT, AND SELLING REJECTS AS A FUEL

                      Franklin Projected   Franklin Projected
Costs	to 500 TPD	to 1,000 TPD

Income*

   Pulping and
    Separation
      Magnetic Metals     $ 2.40/T             $ 2.40/T
      Sludge Disposal .      1.75/T               1.75/T
      Fuel                 10.71/T              10.71/T

   Glass Plant               .02/T                .02/T
      Magnetics             0.25/T               0.25/T
      Aluminum              1.95/T               1.95/T
      Glass                 0.95/T               0.95/T

                          $17.78/T             $17.78/T

Operating Expenses

   Pulping and
    Separation            $ 6.04/T             $ 5.50/T

   Glass Plant              2.19/T               1.48/T

                          $ 8.23/T             $ 6.98/T

Facility Expense

   Pulping and
    Separation            $ 6.57/T             $ 6.12/T

   Glass Plant              1.70/T               1.49/T

                          $ 8.27/T             $ 7.61/T


Net Savings               $ 1.28/T             $ 3.19/T
    *Based on following revenue factors:

       Magnetic metals selling at  $25.00/T.
       Sludge disposal—disposed of at a rate of 0.07/T
          Input—$25.00/T.
       Fuel—$1.25/1,000,000 Btu.
       Aluminum— $ 3 0 0.0 0/T.
       Glass—flint,  amber and green—each  at $20.00/T.
                               16

-------
The annual before-tax return on investments for 500 and

1,000 TPD total facilities, including the operation of the

glass plant, is presented in Table 1.3*.


         TABLE 1.3  BEFORE TAX AROI FOR 500 AND 1000
                     TPD TOTAL FACILITY
                                           $0.0/T Tipping Fee
                                Total         Before-Tax
                Net Savings   Investment	AROI
500 TPD
1,000 TPD
$165,000
$823,000
$ 7,966,000
$14,676,000
2.1%
5.6%
The before-tax AROI does not meet industrial investment

standards.



However, addition of a tipping fee to provide more revenue

changes the picture.  Figure 1.2 illustrates the effect

adding a tipping fee to the revenue side of the balance

sheet and its effect on the before-tax AROI for a 1,000 TPD

facility.



Thus, with a tipping fee of approximately $8.00/T added to

the net income of $3.19/T, a before-tax annual return on

investment of 20 percent can be realized for a 1,000 TPD

plant.  For a capital intensive and high risk business,

industry would require a before-tax AROI of at least 40

percent.
*This analysis assumes that all cash flows remain relatively
constant in time.  This is effectively a "Unicost" assessment.
                              17

-------
10-
        14    15    16    17    18    (9    20   21    22   23

                                             •
                   I


                BEFORE-TAX  AROI (PERCENT)
FIGURE 1.2   EFFECT OF  TIPPING FEE ON AROI FOR A

                  1000 TPD TOTAL FRANKLIN FACILITY
                             13

-------
Industry and municipalities use different techniques to
assess the merit of an investment.  What may not be attractive
to industry could very well be attractive to a municipality
since the community might apply a break even analysis to
solve a pressing waste disposal problem where private
industrial participation (funding) would make the venture
unattractive.
                               19

-------
2.0       INTRODUCTION

2.1       PROGRAM EVALUATIONS
The objective of this study was to perform a technical,
economic, and environmental evaluation of the Franklin Glass
Recovery Plant, which is a subsystem of the Franklin Solid
Waste and Fiber Recovery Facility located in Franklin, Ohio.

The evaluations were performed over a six-month period
(September 1975 to March 1976).  Because of the changing
nature of the facility, the data presented in this technical
evaluation was collected during February and March of 1976.

2.1.1     Technical Evaluation
The technical evaluation included:

     1.  A description of the Franklin Glass Recovery Plant
     2.  Power and water consumption
     3.  Stream characteristics
     4.  Material balances
     5.  Equipment description, theory of operations, and
             efficiencies.

The results of the technical  evaluation are presented  in
Section  4.
                               20

-------
2.1.2     Environmental Evaluation
The environmental evaluation included an analysis of the
potential for polluting the air, land, and water.  It also
evaluated the noise levels in the plant and observations of
odor and industrial hygiene requirements.  Results of the
environmental evaluation are presented in Section 5.

2.1.3     Economic Evaluation
The economic evaluation of the glass recovery subsystem
included a determination of the economic viability of the
technology being used at Franklin.  Cost and performance
data collected at the plant provides a measure of the economics
that would be experienced if the glass plant were to be
incorporated into a different type of solid waste/energy
recovery facility.

The data is presented, where possible, in non-dollar value
terms so that it can be readily used by all interested parties.
Results are projected for facilities scaled up to 500 and
1,000 TPD.  Results of the economic evaluation are presented
in Section 6.
                               21

-------
2.2       HISTORY AND BACKGROUND







2.2.1     Franklin Plant



In 1967 the City of Franklin assessed its solid waste problems



and realized that its landfill would be complete in three to



four years.  At the same time, employees of the Black Clawson



Company, Middletown, Ohio, conceived the idea of using paper



mill machinery to pulp solid waste, eject the nonpulpable



items, separate the finely chopped noncombustibles from the



paper fibers, recover them and burn the organic residual in



a fluidized bed reactor.  The Black Clawson Company investigated



this concept further and, to prove its feasibility, con-



structed a pilot plant at their Middletown facility.  This



pilot plant showed that municipal solid waste could be pulped,



that separation of the inorganic fraction from the organic



material could be accomplished, and that the organic material



could be burned with the remaining material placed into a



landfill.







Based on the results obtained from the pilot plant and the



City of Franklin's need to find an alternate solution to



their solid waste problems, a solid waste processing



demonstration grant was requested from the Public Health



Service under the Solid Waste Act of 1965.
                              22

-------
The City of Franklin made this grant request to design and
construct a full-scale plant which would demonstrate this
new and innovative concept of solid waste disposal recycling
with the recovery of magnetics.  The grant was awarded to
the city on September 24, 1970.  Land was acquired for the
project from the Miami Conservancy District near the new
waste water treatment plant.  The solid waste plant was
completed in May 1971, and the fiber recovery plant was
completed in June 1971.

While the Franklin Solid Waste and Fiber Recovery Facility was
being constructed, the Glass Container Manufacturers Institute
(GCMI) announced that, under their sponsorship, the Sortex
Corporation of North America had completed a series of test
and trial operations using the glass rich fraction separated
from the pulped refuse by the liquid cyclone at Black Clawson's
Middletown pilot plant.  Using a series of screening and
classifying steps to separate the extraneous material, Sortex
was able to recover a stream of color sorted glass cullet
and an aluminum rich stream.  Based upon the laboratory
bench/pilot studies on the glass rich fraction, GCMI proposed
to the City of Franklin that the City apply for a supplemental
grant to add a glass and aluminum recovery line.  GCMI indicated
that they would reimburse the City of Franklin for the matching
funds required for the demonstration grant.  This grant
                               23

-------
request was submitted and approved.  Construction of the
glass plant began in the summer of 1972 and was completed
by the end of 1972.

2.2.2     Contract History
As part of Contract No. 68-01-2211 with the U.S. Environmental
Protection Agency, SYSTECH was to perform a nine-month
evaluation of the Franklin Solid Waste and Fiber Recovery
System including the glass recovery system.  However, during
much of the technical evaluation period (January through
September 1974) of the total plant the glass recovery system
was nonoperational.  In mid 1974 it became apparent that the
glass plant would not be commercially operational during the
remainder of the nine-month evaluation.  The major difficulty
stemmed from the use of air classification as a primary
technique for separating organics from the remainder of the
glass concentrate  stream.

After several modifications to the system, start-up of the
modified glass recovery subsystem and this evaluation began
in November 1974.  However, it became apparent during the
beginning of the evaluation period that the system would
again not meet end product objectives  (yield, quality).
Equipment malfunction, low quality of salable output, and
                              24

-------
relatively high maintenance costs necessitated further



changes in the process.  Hence, the evaluation was postponed



pending these changes.








The Black Clawson Company offered to "turnkey" the modifications



based on technology which they had originated and previously



piloted at the Institute of Minerals Research, Houghton,



Michigan.  The GCMI and the EPA agreed to provide the funding,



and the new technology was integrated into the system during



May and September 1975.  The original concept and the modified



concept of the glass plant are discussed in the following



section.








Other problems (e.g., plugging of lines and screens, etc.)



further delayed the evaluation.  Finally in February 1976,



the glass plant was modified sufficiently to produce an



acceptable color sorted glass product on a continuous basis.



The data presented in this report represent the data collected



during February and March of 1976, e.g., once the plant was



made operational.







2.3       PLANT DESCRIPTION



Before a description of the glass plant is presented, it  is



important that the reader understand the operation of the



front-end system that prepares the feed to the glass plant.
                               25

-------
material.  The cleaned process stream contains mainly
fibrous organic materials and can be directed to a fiber
recovery system which produces a paper pulp marketable for
the manufacturing of roofing shingles and other low
grade fiber applications.  This material can also be disposed
of by first dewatering and then using it in a combustion/
heat recovery system.

The cyclone reject stream (the heavy gritty materials removed
by the liquid cyclone) is the feedstock to the glass recovery
plant.  This fraction of the refuse processing stream is
rich in glass and small pieces of metal, especially aluminum
when the nonmagnetic junk is recycled.  It represents
approximately 11 percent of the original waste stream.

2.3.2     Glass Plant - 1974
Figure 2.1 is a schematic of the glass recovery subsystem
"as built" in 1974.  The outputs from this configuration
were not acceptable and the items encircled in dotted lines
were removed and replaced with newer technology.  Several
of the reasons for renovating this subsystem are as follows:

     1.  Air classifiers did not effectively remove heavy
         organics from the glass rich fraction.
                              27

-------
     2.   Excessive glass breakage was encountered in
         bucket drops, dryers,  etc., resulting in a decrease
         in potentially recoverable materials.

     3.   The high tension electrostatic separators did not
         operate effectively because the process stream
         reabsorbed moisture from the atmosphere after
         leaving the dryer.  The moisture caused the
         separators to operate ineffectively.

These three problems caused excessive process losses and
resulted in unacceptable contaminant levels in recovered
products.

Other minor problems also contributed to production of
unmarketable end products.  Hence, the glass recovery sub-
system was modified to the configuration shown in Figure 2.1.

2.3.3     Modified Glass Plant - 1976
Figure 1.1 displays the evaluated glass plant configuration.
A detailed description of this revised configuration follows.
                               28

-------
CO
o

UJ

CD
     UJ

     o

     o
     UJ
     gc

     <

     UJ
                               CO
                               o
                               Z
                               <
                               O
                               cc
                               O
                               00
                               UJ
                            co
                                    CO
                                    cc
     y   coco
        CO CO CO
                         •cozcDco5!55^ J
                          < CD GJ UJ (3 u 3 CD CD
                         • ;£I>Z
<£^
5 < in
05 0 ^







CO
cc
O
CC
Q.
UJ
CO
z z
UJ CO UJ
LU UJ UJ
CC ^ OC
OHO
co x co
CM CO •*
cc
UJ
t .-.-
r"~
cc
o
CO
>• oc
0 LU
UJ CC
cc O
< co
1 §


"• Q
°O LU
Z LU
mC3
LU y
o s
< ^
si
        >
        LU

        _J
        •D
        a.
                          cc. o
                          OP

                          £ m
                          < z
                          > (Tj

                       _^<
                    co > uj 2
cc
LU
QC
LU
                                  LU
                   CD
                                       Z
                                       r>
                       CM co
           LU  s: cc <
           LU  LU UJ >
           OC  CC > Lu
           o  o oc _j
           CO  CO Q LU

           IO  CO N^ 00
                                 2
                                 H

                                 Q
                                 w
                                 £-•
                                 u
                                 D
                                 CO
                                 2
                                 o
                                 u

                                 CO
                                                     LO
                                                     en
                                                     <
                                                     ,4
                                                     o

                                                     w
                                                     cu
                                                     o
                                                     EH
                                                     o
                                                     CO
                                                     2
                                                     o
                                                     M
                                                     Pi
                                                     2
                                                     o
                                                     CN

                                                     w
                                                     Di
                                                     D
                                                     o
29

-------
3.0       OPERATIONAL CAPABILITY



The glass recovery system at Franklin, Ohio demonstrates



the technical feasibility of recovering marketable glass



and aluminum products from the heavy rejects of a "wet



process" resource recovery system.  The glass plant utilizes



a variety of separation techniques to recover a clean,



color-sorted glass product and an aluminum product.  The



separation steps employed include methods utilizing the



magnetic properties, material size and density, electrical



conductivity and optical properties of the various components



of the glass plant feed stock.








3.1       EQUIPMENT DESCRIPTION



This section describes only .the major pieces of equipment



installed in the glass plant.  No attempt will be made to



describe all the conveyors, bucket elevators, and dewatering



conveyors.







3.1.1     Surge Bin



The surge bin is a 10 cubic yard  cylindrical hopper with a



conical bottom.  Cyclone rejects  from the pulping  and



separation system are dropped in  the  top of the hopper.



Material to be processed is removed at the bottom  by  a



rotary  feeder.
                               30

-------
3.1.1     Initial l.izing Ar.-i Cleaning



Many of the separation operations in the glass plant depend



upon having a consistent size for the particles being



processed.  Thus the first step in the glass and aluminum



recovery operation involves screening.  A 48-inch Sweco



Incorporated "Vibroenergy" vibrating screen separator rated



at 3,000 Ib/hr and fitted with screens that will pass



 articles smaller than ;. in. is used.   A rotating wash



removes fines which adhere to larger particles.  Particles



which do not pass the screen are scraped into a feed control



bin which regulates the rate of feed to the following



separation processes.  The +'; in. fraction becomes the



feed stock to the rest of the plant.  The -\ in. fraction



is dewatered and landfilled.








3.1.^     Magnetic Separation



Oversized material from the screen is passed to a drum



magnot which draws off magnetic materials and deposits  them



in a container for recovery and sale.  The rest of the  glass



and aluminum rich fraction  passes on  to the next unit



operation.
                              31

-------
3.1.4     Ht-avy Media Separator



The magnetic free +% in. material enters a heavy media




separator to purge it of residual organic materials.  The



dense media separator is a Wemco HMS laboratory unit with



a rated capacity of up to 500 Ib/hr.  The HMS is a rotating



drum partially filled with a pool of water whose apparent



specific gravity has been adjusted to 1.8 by the addition



of magnetite.  The feed enters one end of the drum just



below the surface of the pool.  Materials with a specific



gravity less than 1.8 will then float to the top and



eventually overflow a circular opening at the discharge



end of the drum.  Particles with a specific gravity greater



than 1.8 sink  to the bottom of the drum and are picked up



by lifters, elevated out of the pool and dropped into a



sinks hopper.  Both  the floats and sinks are spray washed



to remove residual magnetite which is recovered for reuse.







The  floats are mostly heavy organic materials.   These are



collected for  subsequent -landfill disposal.







The  sinks include glass,  nonmagnetic metals,  rocks, dirt



and  ceramic materials.
                              32

-------
3.1.5     Jigging



The dense media sink material is processed in a Wemco-Remer



jig.  In this device, liquid is pulsated vertically through



a horizontal bed of material being processed.  This causes



the heavier material to work its way to the bottom of the



jig bed as the lighter material rises to the top.  The Wemco-



Remer jig uses a double stroke jig mechanism for improved



separation efficiency.








Aluminum rich material comes off the top of the jig and can



be further refined for sale.  The bottoms consisting primarily



of glass are passed on to dewatering and drying.  The



middlings may be reprocessed or rejected to the landfill.








3.1.6     Electrostatic Separator



The sink material from the jig is gravity dewatered then



dried in a rotary drum drier.  It then passes to a Carpco



high tension electrostatic separator.  The electrostatic



separator is a device consisting of rotating, electrically



grounded drums on which the feed material is dropped.  Near



the feed entry point, a high voltage ion source charges



the particles in the process stream.  Conducting materials,



once beyond the influence of the ion source, rapidly dissipate



their charge to the grounded drum.  These conducting



materials then drop from the drum since there is no electrical
                              33

-------
force holding them.  (A charged body creates an "image"



force which causes it to adhere to a grounded surface).



Nonconducting materials, however, do not readily lose their



electrical charge.  Thus they adhere to the drum longer than



the conductors.








Some nonconductors drop off with the conductors in the



electrostatic separator, but they tend to be principally



stones and ceramic materials.  Theories as to why this



occurs are presently in dispute, but for our purposes the



result is fortuitous since it tends to aid in cleaning up



the glass product.  The phenomena does result in contamination



of the mixed non-ferrous concentrate.








3.1.7     Opacity Sorter



The process stream, having been cleansed of conducting



materials and some stones and ceramics, passes to an optical



sorter for the removal of opaque materials.  This is a



Sortex Model 962M Optical Sorter with a rated capacity of



400 Ib/hr per channel.  In the optical sorter, each piece



of material passes through a beam of light.  If the light



beam is cut off  (the particle appears opaque) a small air



jet blows that particle aside and it is rejected.  Transparent



materials are not  subjected  to the air blast and thus report



with accepted material.   It  should be noted that because of
                              34

-------
the irregular surface of the glass materials in the process
stream, transparent materials will be rejected because they
happen to pass through the light beam at such an angle that
their reflectivity makes them appear opaque.  Rejected opaque
materials are removed for landfill disposal.  Transparent
materials are passed on for further sorting into colored
and flint glass products.

3.1.8     Color Sorting
The final step in the glass plant processing is to sort the
glass product into a clear or flint glass cullet and a mixed
color glass cullet.  This sorting is also performed by a
Sortex Model 962M Optical Sorter with colored filters
installed on the optics so that colored glass appears to
be "opaque".  The principle of operation is exactly as
before, with the resultant products being clear glass cullet
and mixed color glass cullet.  The colored glass mixture
could be further sorted into a green and an amber product,
but that is not presently done at the Franklin Glass
Recovery Plant.
                               35

-------
4.0       TECHNICAL EVALUATION OF THE GLASS RECOVERY PLANT








4.1       EVALUATION METHODS USED



This chapter presents the data gathering and analysis method-



ologies used in the evaluation of the glass recovery system.



Results of the data analysis and the overall glass plant



technical evaluation are also presented.  These include:



recovery efficiencies, material balances, power and water



usages and some maintenance history.








4.1.1     Development Of A Study Matrix



To organize the principal areas of evaluation and to aid in



defining the data to be measured, a study matrix was developed.



The study matrix is a graphic representation of all possible



measurements.  This allows the experimenter to rapidly assess



the necessity of any particular measurement, the relationships



between measurables and the completeness of his final experiment.



This study matrix is presented in Figure 4.1.  Along the



horizontal axis, the unit operations of the glass recovery



system are listed.  The vertical axis is divided into the



three evaluation categories.  Each of the evaluation categories



is  subdivided into  its component parameters.  A mark is placed



at  the intersection of each unit process/parameter  relation-



ship that was evaluated during this  effort.
                               36

-------
EVALUATIONS
TECHNICAL
ECONOMIC



>
o J
K <
*H H
> z
2 U)
U) Z

N. UNIT
N. PROCESSES
PARAMETERS N.
DESCRIPTION OF EQUIPMENT
THEORY OF OPERATION
MAINTENANCE HISTORY
POWER REQUIREMENTS
STREAM CHARACTERIZATION
MATERIAL BALANCE
EFFICIENCY
RECOVERED PROD. CHARACT.
OPERATING LABOR COSTS
OPERATING POWER COSTS
MAINTEN. LABOR COSTS
MAINTEN. PARTS COSTS
GENERAL CONSTR. COSTS
EXTENDED CONSTR. COSTS
REVENUES
AIR
WATER
LAND
IN-PLANT NOISE
ODOR
INPUT SYSTEM 1
0
0
0

0
0














WASH SCREEN
0
0
0

0
0
0













MAGNETIC SEP'N I
0
0
0

0
0
0
0












z.
0,
H
V)
<
w
o
u
X
>•
<
u
X
0
0
0

0
0
0






•






u
M
^
0
0
0

0
0
0
0












ce
u
X
a.
o
M
*
0
0
0

0
0
0













SCREEN I
0
0
0

0
0
0













ELECTROSTATIC SEP'N I
0
0
0

0
0
0













TRANSPARENCY SEP'N I
0
0
0

0
0
0
0












Z
a
M
tt
$
o
o
0
0
0

0
0
0
0












SYSTEM
0
0
0
0
0
0
0
0
Q
0
0
0
0
0
0
0
0
0
0.
0
FIGURE 4.1   GLASS RECOVERY SYSTEM STUDY MATRIX
                            37

-------
4.1.2     Sampling And Analysis Methods



Of the parameters listed in Figure 4.1 under technical



evaluation, brief descriptions of the equipment and theory



of operation have already been presented in Section 3.







Since so much of the technical and economic evaluation of



the plant hinges on the separation efficiencies of the unit



processes, the weights of the output streams and the



characterizations of the output and process streams are



of great importance.







Process streams within the plant were sampled daily and



these daily samples were composited for weekly analysis.



Figure 4.2 shows the points at which the process stream



samples were collected and the points at which the output



streams were weighed.







The weekly composite samples were used to characterize



individual process and reject streams within the plant.  The



weekly composites were also used to determine the recovered



product characteristics and individual unit efficiencies.



Analyses of the collected samples were performed by Systech



personnel by hand sorting into the characterization categories



appropriate for the stream under analysis.  Magnetic  metals



were separated from other metals using a small  lab magnet.
                               38

-------
H
MAGNETIC
SEPARATOR
HEAVY
MEDIA
SEPARATOR

sauTj
soTueBao^O'
n
h|m|
VIBRATING
SCREEN
SEPARATOR
i
sauT jp

DE WATER
AND
DRY
$
MAGNETIC
SEPARATOR
$
ELECTRO-
STATIC
SEPARATOR
$
TRANS-
PARENCY
SORTER
!j SAMPLE TYPES
SOT}SU6EWV^/ KS
sauTj td


O- Composition
Q~ Weight
FIGURE 4.2 GLASS PLANT SAMPLING POINTS
C 2
OS H
3 CQ
e/3
            UT9
COLOR
SORTED
                                 39

-------
There are no in line scales for measuring the input to the



glass plant, nor are there any scales on any of the conveyors



within the process.  Therefore, the analysis of material



flows had to be accomplished by network analysis using the



weights of the output streams from the plant and recognizing



that their sum had to be the total input.  Each output



stream was collected in barrels and weighed periodically



and these weights were recorded.  In addition, spillages



and other losses were collected and weighed so that they



might be accounted for.  When all outputs had been measured,



they were appropriately added together to determine total



input weights.  The operating time for the plant was used



to compute average flow values per unit time based on the



assumption that plant operation was quasi steady state.







The maintenance history for the plant was obtained from



operating logs kept by plant operating personnel.  These



logs were verified by SYSTECH personnel who monitored the



operation at the glass plant during the study.







Power requirements were determined for the system as a whole



by using electric power meters.  Power requirements per unit



time were determined by using a timer attached to the power



supply of the washing and  sizing screen.  Since  this unit



was required for all subsequent operations,  it was felt that

-------
its time of operation effectively measured the time of



operation of the whole plant.  There were operations in the



glass plant which did not run as long as the washing and



sizing screen (e.g., the color sorters), but no unit ran



longer.








Section 4.2 of this report presents the results of the



technical evaluation phase of the study.  The data represents



a compilation of six weeks data extending from 3 February 1976



through 12 March 1976.  Findings presented in the following



sections of this report represent average operating and



characteristics data.








4.2       RESULTS OF THE TECHNICAL EVALUATION



The items covered in this section of the technical evaluation



of the glass plant include:   (1) material balance data;



(2) characterization of the input, process and reject streams



and oatput products of the plant;  (3) power and water usage



data; and  (4) efficiencies of the separation equipment used



in the glass plant.  Actual data collected with raw material



balance data, periodic test data, and data collection forms



are too numerous to include in this report.  Hence, only



summaries are presented.
                               41

-------
4.2.1     Mass Balance Data For The Glass Plant



Figure 4.3 is a material balance diagram for the glass



recovery system.  The input is for a typical 5-day operating



week  at the Franklin Solid Waste and Fiber Recovery Facility.



About 43 percent of the processed input to the glass plant



is recovered; so only 57 percent of the cyclone rejects are



landfilled.







Mass balance data for the glass plant can be related to the



refuse received at the tipping floor by assuming that the



glass plant is appropriately sized to accept all the cyclone



rejects.  For every ton delivered to the tipping floor,



228 pounds of cyclone rejects would be received at the glass



plant in a community with Franklin waste characteristics.



Figure 4.3 shows the different output streams from the glass



plant.  Percentages shown in that figure refer to the fraction



of input to the glass plant recovered, while the weight



numbers refer to pounds of material removed per ton of



refuse at the tipping floor.  Thus, for example, 30 pounds



of magnetic materials are recovered in the glass plant for



every ton of Franklin refuse at the tipping floor.  The  jig



top product, which is the aluminum rich stream, is 8.6



pounds per Franklin tipping floor ton.  The flint glass



product is 35 pounds per Franklin tipping floor ton, while



the mixed color glass product is 23.5 pounds per Franklin
                                42

-------
                                                                                                                                                                    0)
                                                                                                                                                                    s:  01
                                                                                                                                                                    4J '0
                                                                                                                                                                        c
                                                                                                                                                                    O  3  5)
                                                                                                                                                                    VOX

                                                                                                                                                                    V
                                                                                                                                                                    3  01  U
                                                                                                                                                                           1)
                                                                                                                                                                        O  01
4— f- rH
m rH rH
          r^ O n  p^ CD rH

          *r ff* o  i"* r- m
                                                                                               o-riinomoin   ootnm
• ^« in ^r    1—4 '
        (N    00
    IH  (U
•4-1  0  M
C HH
CJ  (U -4J
U  IH  3

01  Ul  C
a u -H
O
M
EI 01
M 01
ui m
O -
s c
O -^
o
—
CM







01 01 £1
01 4) p
in c 01 ix
rH O 3
U JJ 01 0 "»
in £ o u 01
T3 3 --H w O U
0 » C JJ 41 -4 -H
U 



3M> 4k C7O
O 00 cH
O CN CN


I 	
UJ
5 t-O
A\- uj — cO
i x
en <
i

i

^"T
O
m


04

rH




-r O
H"
il 	 uj
5 °
to <


1












ct
o
ct
UJ
(O



















01 01 01 O D^>4H
QJ O 01 4J -H O
01 c c 01 m 4)
3 OO01i-4 Ui5c
01 ooijjvmo do
01£ EOUl r4£U01O3UlrH 14HT3-4J
O3 3 -HO UiS'HO O"O DC-
••HC C 4J -I (UC-U-H^^aO) MftJMrj
CH- -rtQJCOl- h-HOICOl • 4J 14 • (DO
03 E O S C 03 Ul O I6C03U1.CJ.COU M -U a O
O^ 30} 3 CP T* in 01 C 3 ^ (7* fl M t(l IH *H rH Ul CJ C — H
|0<£| < fi 0 3 SB | S < I S 3 iS SEll 0 fc 5 1 1 ra^«H «
3 M Id i O t'l
b. A > U 5 =
O rH Q O
Ul J3 U OS Z <
£ £ W O a,
s j: os cj O
1 (N I-- rH
~l
_
f
in
^t


00



i 1


^-
f*i


&*
rH


1 1 1
afe --,
\O ^*
. v^
00 rH


OP 0*



1
^^
-^
i"O
r-H


cJP
^O


' 03 
< 01
J 01
O EH C
U O
— Q D V
=•» S3 Q 01
in Q* O
30 - O ^4 ^
o m J o. 01
rH 04 O Ul • O
— CJ 03 n 01

Q ^
^0
^ <
UJ LU

rH - — OCC — O~ — -Jrr
CC S^ *^O ^O
UJ ^ O ^^^^ va O  r4 C
                                                                                                                           C (U <1)   •  O
                                                                                                                          •H jQ (3J  Ul  01
                                                                                                                          rH S Ul  OJ -H
                                                                                                                          t. 3 u u £
                                                                                                                                                                                                  2
                                                                                                                                                                                                  O
                                                                                                                                                                                                  H
                                                                                                                                                                                                  W
                                                                                                                                                                                                  EH
                                                                                                                                                                                                  <
                                                                                                                                                                                                  G
                                                                                                                                                                                                 D
                                                                                                                                                                                                 CM
                                                                                                                                                                                                 EH
                                                                                                                                                                                                 O
                                                                                                                                                                                                 O
                                                                                                                                                                                                 EH
                                                                                                                                                                                                 H
                                                                                                                                                                                                 S

                                                                                                                                                                                                 .2
                                                                                                                                                                                                 o
                                                                                                                                                                                                 w
                                                                                                                                                                                                 u
                                                                                                                                                                                                 o
                           "3"

                           W


                           O
                           M
                           &H
                                                                                                                          O  c
                                                                                                                         rH  <0
                                                                                             43

-------
tipping floor ton.  Because some processing equipment in
the glass plant is undersized (especially the heavy media
separator) only a fraction of the available cyclone rejects
were processed by the glass plant.  Total cyclone rejects
were measured at 11.4 percent of the incoming refuse during
the test period.  However, because of this undersizing, the
material handled by the glass plant was only 1.9 percent
of the refuse received at the tipping floor or a slip stream
of approximately 20 percent of the available cyclone rejects
was actually processed.

4.2.2     Glass Plant Stream Characterization
The characteristics of the streams in the glass plant were
developed from composite samples collected at various points
in the process stream and all the output points  (see
Figure 4.2).  The input to the glass plant consists of the
water-saturated cyclone rejects which are rich in glass,
magnetic materials, and aluminum.  The majority of this
material  (70 percent) is -3/4 in. and  +^ in.   in addition
to the fraction of the material entering the glass plant
which is  separated at various points within the process,
Figure 4.3 also shows the characteristics of those output
products.  All the compositions are reported as appropriate
weight percents.
                               44

-------
Magnetic materials comprise approximately 9 percent by weight

of the Franklin cyclone rejects*.  Eighty-six percent of these

magnetic materials are recovered by the magnetic separator.

However, contaminant levels are high (41 percent) in this

product stream.  This contaminant level is caused primarily

by wet materials sticking together; thus, the wet magnetics

carry contaminants along with them on the magnetic drum and

into the recovery bin.  This magnetic material would require

further cleaning for sale.  Once it is dried, it can be

easily processed through another magnetic separator to

achieve a much higher purity and enhance its value.



The cyclone rejects at Franklin are the input to the glass

plant.  They have an aluminum content of 4.7 percent.  Due

to the high economic value of this metal, an attempt is

made to recover this fraction of the cyclone rejects.

Fifty-one percent of the aluminum in the cyclone rejects was

recovered at the jig.  The remainder of the input aluminum

is removed at the magnetic separation step, the heavy media

separation step, and past the jig by the electrostatic

separator.
*The cyclone rejects are a poor fuel with 94 percent ash and
417 Btu/lb higher heating value.  It is evident from this low
Btu content and high ash content that this material is not
considered a useful fuel source and that little fuel value is
lost in the cyclone rejects.  These numbers are consistent with
the characterization data of the input which indicates a total
organic content of 15.5 percent on a dry weight basis.
                               45

-------
The Franklin cyclone rejects have a glass content of about



54 percent, 53 percent of which is recovered as glass cullet.



This is equivalent to approximately 29 percent of the feed



coming into the glass subsystem (i.e., 36 percent of the



glass received on the tipping floor in Franklin).







4.2.3     Utilities Requirements



During the study period the electric power consumption was



recorded for the glass plant.  The average power usage of



the glass plant was 63.3 kilowatt hours per ton.  This is



equivalent to 215 kilowatt hours per ton of material processed



in the glass recovery system, or to 26 kilowatt hours per



ton of solid waste delivered to the tipping floor.  Power



usage for individual unit processes is not available since



no individual units were metered.







There are four areas of water usage in the glass recovery



system:  they are the surge bin conveyor, the washing and



sizing screen, the heavy media separator, and the jig.  Flow



meters were not available to measure water used by the jig



and the heavy media separator.  For the most part they used



their own recycled water and needed only makeup water.  The



surge bin conveyor uses approximately three gallons per



minute and the washing and  sizing  screen uses approximately



30 gallons per minute of operation.   This represents a
                               46

-------
total flow of 1,980 gallons per hour or 6,712 gallons per
ton processed. Water used in the glass plant at Franklin
is "city water", i.e., clean potable water.  At another
installation, non potable process water could be used.

All the water used in the glass plant is collected in a
common drain system and is pumped to the Whitewater sump in
the pulping and separation system of the main solid waste
plant.  Thus, all water in the glass recovery system is used
as makeup water in the Whitewater system.  No Whitewater
(recycled process water from the pulping and separation system)
is used in the glass recovery system.  The primary contamination
of the water used is an increase in total suspended solids.
This results because fine particles are rinsed off the feed
material going to the glass recovery system.

4.2.4     Efficiency Of Equipment
Separation efficiencies for unit operations within the glass
recovery system are calculated  for the following unit
operations:  washing and sizing screen, wet magnetic separator,
heavy media separator, the jig separator, the rotary kiln, the
electrostatic separator, the transparency sorter, and the
color sorter.  The overall material balance for the glass
plant is presented in Figure 4.4.
                               47

-------
  TOTAL
  CYCLONE
  REJECTS
48,868 Ibs.
                   CYCLONE REJECTS BYPASSING GLASS PLANT
                                  41,868 Ibs.
              INPUT
            7,000 Ibs.
                 GLASS AND

                   ALUMINUM

                     RECOVERY

                        SYSTEM
                                OPERATING
                                   TIME

                                 11.9 hrs.
                                                    MAGNETIC MATERIALS
                                                         931.4 Ibs.
                                                     ALUMINUM RICH
                                                        MATERIALS
                                                       T68.2  Ibs.
                                                      FLINT GLASS
                                                      1078.6  Ibs.
                                         COLORED GLASS
                                           719.1 Ibs.
                                                      TO LANDFILL
                                                       4002.7  Ibs.
FIGURE 4.4
                         MATERIAL BALANCE DIAGRAM FOR GLASS AND
                               ALUMINUM RECOVERY SYSTEM*
              *Figures represent operating data for an average week;
                all weights are given on a dry basis.
                                         48

-------
4.2.4.1   Washing And Sizing Operation



The input to the glass plant from the liquid cyclone is



directed to a surge bin having a rotating feed table which



meters the solid flow to the initial separation operation.



This first operation in the separation process is the



vibrating screen separator which rejects materials smaller



than -; in. from the remainder of the process stream.  To



aid this removal, material on the vibrating screen is flushed



with water to remove small particles adhering to the surface



of the large particles.  The rejected material from the



screen separator is fed to an inclined dewatering screw and



landfilled.







Twenty-one percent of the total input to the glass plant



is removed as undersized rejects at this point.  Of the



material passing as process stream, only 3 percent  (equal



to about 2 percent of the input) is less than % in. in



size.  This indicates an efficiency for the washing and



sizing operation of 90 percent.







4.2.4.2   Magnetic Separation



The process stream from the washing and sizing operation  is



fed to an electromagnetic drum separator which scalps off



the easily removable magnetic materials.  The materials



removed by this magnetic scalping of the wet feed are moist
                                49

-------
(12 percent water).   As a result, materials stick together
so that this recovered stream is only 59 percent magnetic
material.  However,  86 percent of the available magnetic
materials are removed at this step.  Even though the removal
efficiency is 86 percent, since the product is 41 percent
contaminants, the market value of this product is questionable
without further cleanup.

4.2.4.3   Heavy Media Separator
After removal of the wet magnetics, the process stream flows
to the heavy media separator.  The function of the heavy
media separator is to remove organic materials from the
glass rich stream.  By blending material with a solution
of water and magnetite, which is held at a specific gravity'
of 1.8, the organic materials are floated off and the heavy
fraction is passed on to the next operation.  Eight percent
of the input to the glass plant is removed at this point
and contains 93 percent of the organic materials remaining
in the process stream at this point.

4.2.4.4   Jig Separator
The primary function of the  jig is to separate the aluminum
fraction from the process stream.  The  jig is fairly  efficient
since it removes  73 percent  of the aluminum  in the jig  feed.
                               50

-------
The jig output product contains only 62 percent aluminum.
Further cleanup of the jig output product can be achieved
by drying the material and then subjecting it to an electro-
static separation process because the contaminants are
primarily organics which bypassed the heavy media separator.

4.2.4.5   Rotary Drum Dryer
After leaving the jig, the process stream passes a dewatering
screen for the removal of excess surface water; then it
passes to a rotary drum dryer.  The moisture content of the
influent material averages 2.9 percent, and the moisture
content of the stream leaving the dryer averages 0.3 percent.
This indicates an average reduction in moisture of approximately
90 percent.

4.2.4.6   Electrostatic Separator
Following the rotary dryer, the process stream is passed
through a magnetic scalping operation to remove any residual
magnetic materials.  It is then fed to the electrostatic
separator which separates materials according to their ability
to hold a static charge.  Removal efficiency for metallic
material is nearly 100 percent.  Also, almost all of the
remaining organics and 66 percent of the ceramics and stones
are removed by this device.  About 6 percent of the available
glass is lost from the process stream at this point.
                               51

-------
4.2.4.7   Transparency Sorter



The process stream from the electrostatic separator is



conveyed to the transparency sorter.  The removal efficiency



of opaque materials was determined to be 90.5 percent.  The



transparency sorter also rejects 17 percent of the incoming



glass.  This results in a glass contamination level of



77 percent in the sorter rejects.  This percentage varies



with the feed rate to the sorter and the quantity of opaque



materials in the feed.  During the evaluation, the feed rate



to the sorter was held at 400 Ib/hr.







4.2.4.8   Color Sorter



The last unit operation in the glass recovery system is the



color sorter.  The function of this device is to separate



the flint glass from the colored glass.  Efficiency in this



operation has been computed as the contaminant content in



the flint glass product, where contaminant means any constituent



which is not flint glass.  The flint glass product was



measured to be 96 percent flint glass,  2.9 percent green



glass and 0.7 percent amber glass.  Other contaminants include



0.2 percent ceramics and stones, and 0.1 percent unidentifiable



tramp fine material.
                                52

-------
The colored glass product was 99.2 percent glass, 0.7 percent



ceramics and stones, and 0.1 percent unidentifiable fine



materials.







The GCMI specifications for recovered glass are presented



in Appendix B of this document.  Although the recovered



glass products do not meet GCMI specifications, they are



marketable glass cullets.  Gullet samples from Franklin



were evaluated by glass users and served as the basis for



long term purchase contracts for the glass to be produced



by a similar plant in Hempstead, New York.







4.2.5     Comments On Maintenance History



Four major unit operations were improved prior to data



collection.  The first change was the replacement of the



vacuum tube electronic systems in the electrostatic separator



with solid state components.  Solid state components improved



the operating life and reliability of the system as well as



enhancing overall operating efficiencies.







The second improvement involved the magnetic separator.  The



unit in use at the beginning of the testing program was not



of sufficient size and strength to give adequate magnetics



recovery.  The heavy media separator output was not sufficiently



free of magnetic materials thus resulting in a lowering of
                              53

-------
the operating efficiency both of the heavy media and jig



separators.  The present magnetic separator resulted in the



reported separation efficiencies and in improved operation



both in the heavy media separator and the jig.







The third item to be improved was the Sortex Optical Sorting



System. During the testing period the Sortex Model 962 Optical



Sorter was replaced with the Sortex Model 962M System which



has an improved, high-speed ejector device.  This has resulted



in an improved quality of output product as well as an increase



in throughput capacity up to 500 Ib/hr.







The fourth item to be improved was the bucket elevators.



Friable materials dropping into the buckets caused flying



chips and dust which accumulated in the bucket pivots and



made the elevators bind at turns.  The resulting stress



increase caused some of the buckets to crack and necessitated



system shutdowns to remove and replace the cracked buckets.



The problem was minimized by replacing exposed drive gears



with enclosed gears.  A maintenance program requiring ongoing



cleaning of the buckets has effectively controlled this



problem.
                              54

-------
There were some minor problems involving the operation of



the heavy media separator due to the fact that it was con-



siderably undersized.  The unit has a throughput rating of



only 500 Ib/hr, whereas a rate of about 1 T/hr is required



to process all the cyclone rejects.  Thus, the unit required



considerable operator attention which would not be necessary



if the unit were sized with a 4-ft. diameter or larger drum.



These problems with the heavy media separator are responsible



for much of the contamination in the aluminum product coming



from the jig.







It should be noted that the glass recovery system in the



Franklin Solid Waste and Fiber Recovery Facility is a large



test operation which represents the first plant of its type



in the world.  As such, many equipment modifications and



changes were incorporated as an ongoing process.  Thus, a



long-term history of the maintenance requirements of the



equipment in the plant is not available.  Based on the



limited knowledge gained at the Franklin plant, routine



maintenance requirements are not excessive.   During the



evaluation, maintenance time never exceeded 10 manhours



per 40 operating hours.
                               55

-------
5.0       ENVIRONMENTAL EVALUATION OF THE FRANKLIN
               GLASS PLANT



5.1       INTRODUCTION

The major environmental impact of the Franklin Glass Recovery

Plant is that it reduces the land required for disposal of

solid waste and recovers valuable resources.  These benefits,

of course, must be weighed against the environmental impact

of various waste streams resulting from the operation of

the plant.



The environmental impact of the Glass Recovery Plant on air

quality can best be characterized by the evaluation of the

particulate emissions from the glass plant.  Particulates

are produced by various operations  (moving of the glass) of

the glass plant.  Tests were conducted to quantify the air

emissions from the glass plant.  The test results are discussed

in Section 5.2.



The environmental impact of any system with respect to water

quality is usually evaluated by characterizing the influent

and effluent flows from the plant.  However, since the glass

plant is  not a  "stand alone" system, it must be  evaluated

in terms  of its additional effect on the environment over

and above the effect of the front-end solid waste plant.
                               56

-------
Finally/ an occupational safety and health evaluation was



also conducted with respect to industrial hygiene and noise.



Sections 5.4 and 5.5 will present the results of this



evaluation.








5.2       ENVIRONMENTAL IMPACT ON AIR QUALITY



The input to the glass recovery subsystem contains friable



material (a material that will fracture and crumble easily).



The separation and handling techniques used in the glass



recovery process tend to fracture the friable materials



so that dust is generated.








Hoods are used at those locations within the glass plant



where dust might be generated.  The collected dust and air



are exhausted through a venturi scrubber located outside



the Glass Recovery Plant.  This exhaust is the only major



source of air emissions to the outside environment.  Thus,



the effect of the glass plant on air quality can be determined



by measuring the particulate emissions from the venturi



scrubber system.








ASME Power Test Code No. 27 type particulate emissions tests



were conducted to measure the emissions from the dust collection



system in the Glass Recovery Plant.  The EPA Method 5 sampling
                               57

-------
procedure was not employed because the ambient stack



temperature and low moisture content did not require a



heated sampling probe.  The results of these tests are



included in Figure 5.1.  It was determined from these tests



that the particulate emission rate is 0.089 pounds per hour.



The stack temperature  (since there is no combustion device



other than the dryer) was approximately room temperature or



74°F.  The flow rate at standard conditions was approximately



8500 dry standard cubic feet per minute.  An Orsat analysis



conducted on the exhaust stack indicated that the gas



composition was similar to air.







At the process weight  rate of 20 pounds per minute, the



allowable emission rate in the State of Ohio is 2.90 pounds



per hour*.  Thus, the  emissions from the glass plant  (0.089



Ib/hr) are only 3 percent of the allowable emission rate.



There are no Federal regulations limiting emission rates



in terms of the process weight rate of an industry or system.



Thus, the Glass Recovery Plant is  in compliance with applicable



regulations.
 *0hio Regulation AP-3-11,  Table  1
                               58

-------

















































O
*
rH



























|
"*" 1
r

en

CN
O
rH
•xl"
r«.
\
CN
CN
O
rH
ri
x^
CN

^_,
rH

en







**




=**




O
"ty*

o
en



r-
r-
CM
CN

r*~
f^
cn
CN

O

rH





0
rH



O
rH






j
j
I






































































































































CO
in
•
rH




00
in

rH




00
in
rH


CO
in
rH


















00
00
irt
in




rH
CN
in


vo
vo
m


















CM
CN

00
















O
^*
r-






rH
00
00


0
rH
CM



o
^*
r~


o
^J*
f*



1
;















o\
rH
_,^
00




rH
r^
00


r-«.
CM
00


|


a
CJ
d


m
CN
in
00




••
4->
•H
TJ
l-l
a
u
•H
•H
O
cu
Q
to








*— *
•
w
£1
\
*
CO
j^
1— 1
>H_I>
1 J
4-*
CO
cu
EH

CT
C
•rH
'H
•3
Q
f
(U
T!
05
0)
cr
aJ
^

TJ
(0
0
E '
TJ E
CU '
•P £
CO
r
CD C
Cn ,
T5 C
CU C
£> )
< c



1
j
1
i

1
s~*>
S
' CU
u*
*•— »>

i CQ
c
o
! -rH
4J
G
O
CJ

y
U
T3
CO
CN 4J
4-* T3
-. — >
^t 4-1
3 TJ -H
CU O
S >-l O
3 < rH
J CU
H .* >
U •
o TJ cr
< 4J >












. — .
2
Cu
CJ
•*— *

CO
c
•H
•H
TJ
C
0
CJ

Stack
14J
CU
TJ
» O
r-H
Cl4






















^~,
CM
o
•— •
CU
>H
3
4J
TJ
r-i
CU
a
cu
EH
U
TJ
4J
to







^^
s
CL<
CJ
CO
~-^

CO
C
O

4-1
d
0
CJ

T)
,_i
TJ
Stand
4J
TJ
CU
4->
TJ
05
0
rH
Qu



















<
EH

Q

Z
0
MISSI
a
w
EH
CJ
05
<;
Oi














Jf^>
D
g
"•-—-i

a
4J
CJ
cu
rH
rH
O
CJ
CU
4J
TJ
rH
3
CJ
•H
4J
nj
rH
TJ
4J
O
EH





t,
CJ
to
»-«

•
TJ
C
O
• CJ
1

T3
» *\
UJ
TJ

T3
CU
rH
a
g
to
cn
5
>
Q
CU
3
rH
O


-—•
CJ
co


. ^-»
TJj pL|
Cj CJ
o] to
rjj * — '

• •
T| T)
•M C
CO| O
CJ

*T5
Tl S
cu to
r-l
CU4J
S tl
TJ
CO CU
. g
VH 3
O rH
CUO
($ ^r*
TJ
iH CU
CU rH
4-» a
TJ g
2 TJ
CO
cu
g rH
rH 4J
o o
> EH




*••— •

1
0
rH

X

P-,
CJ
to
V.

l_l
D
B
C

4J
(TJ
k_l
4J
oncen
u
cu
4->
(TJ
rH
3
CJ
1-1
TJ
a.



^-.
r*.
1
O
rH

X

PM
CJ
to
\

CC
_Q
IrH
C
o
•H
4->
TJ
M
4J
oncen
CJ
cu
TJ
rH
3
O
•rH
4J
TJ

5









^~*
.
i_i
_c
.\
•
CO
j3
rH
CU
4-1
TJ
05

C
O
missi
Cd
TJ
r-H
3
U
4J
T3
Oi
9





*—*
ID
EH
03

VO
O
rH
\

CO
_c
r-
CU
4J
TJ
05

C
0
missi
Cd
CU
4-1
TJ
rH
3
O
•rH
4->
(C
Oi

















^«.
OP
0)
rH
a
g
TJ
CO

netic
•H
X
O
co
M
C
cu
CJ
IH

a,



















X
\
• S
o
EH

a>
4->
TJ
05
4-)
CT
•H
CU
CQ
CQ
CD
CJ
O
rH
PH




i


j








1
rH
hyH
X)
rH

' CU
4J
ed
05

C <
0 E-
•H rt
CO C
cn
•H CO
'e 3
Cd C
cu *z
rH rt
X) r^
rd i-:
o c.
rH V.
rH t-
i^C ZE


























r
tf
C
*




















f]\
us
TJ
Jj
f-1
r*-l
rr
w
.,_!
(1)
VA/
*
ssaoc
^
rH
d.
T)
CU
4-)
g
•H
4-)




























cn
•H
CQ
rH
in
IVJ
s
4J
T5
CQ
O




























dP
in
o
i
0
CJ





























in
Q
CN
1
CM
O





























dP
O
0
1
O
CJ





























dP
O
£
1
f\f
z





































EH
CO
IS

Q
H
rH r-3
K O
\ CO

O £2
O M
CN 1-3
i K^
t-T
II (=£

C fc.
•H
s
=**= rH
O •
CN LO

CU Cd
4J pj
TJ D
05 O
M
4J Cn
CT>
• H
CU
CO
CQ
CU
0
P-I



-------
It should be noted that the moisture content of the exhaust

gases from the wet scrubbing system is only 1.8 percent by
                        j
volume.  This low moisture content is due to the high volume

of air being pulled through the system.




5.3       ENVIRONMENTAL IMPACT ON WATER QUALITY

Water used in the glass plant consists of city water and

process water (firal clarified water from the adjacent waste-

water treatment plant).  The city water is used in the wash

screen for the purpose of washing and separating the various

size fractions of glass and organic material.  This washing

step is necessary because the glass plant feed material is

saturated with lower quality water  (i.e., Whitewater, which

is water that is used and recirculated in the pulping and

dewatering subsystems) containing particulate matter that

needs to be removed.



Process water is used in the glass plant as makeup water

for both the jigging operation and for the heavy media

separator.  All the water used in the glass recovery system

is returned to a common sump and pumped to the Whitewater

sump in the pulping and separation system where it is used

for dilution water  in the Whitewater  system.   There  is  no

direct discharge from the glass plant to a receiving stream
                               60

-------
or wastewater treatment plant.  Thus, the environmental



effect on water quality solely due to the operation of the



glass plant is not significant from a water quality standpoint.



Characteristics of the process water used in the glass plant



are given in Figure 5.2.








5.4       ENVIRONMENTAL IMPACT ON LAND



One of the side benefits of the Franklin Solid Waste and



Fiber Recovery Plant with the Glass Recovery Plant addition



is a reduction in the amount of material that would normally



require landfilling.  The glass plant yields the following



landfillable material:  wet fines, heavy media separator



fines, heavy media separator floats, dry fines, conductors,



opaques, and transparency and color sorter fines.








During the evaluation period, the average input tonnage to



the glass plant was 590 pounds per hour.  Of this amount,



approximately 252 pounds per hour is recovered and is not



landfilled.  This amounts to a 43 percent recovery rate of



the incoming feed to the glass plant.  If the glass plant



were sized to accept all of the cyclone rejects available



(11.4 percent of the tipping floor tonnage at Franklin),



then 43 percent of this material would be recovered.  This



is equivalent to a recovery of an additional 98 pounds from
                              61

-------
               PROCESS WATER CHARACTERISTICS
PARAMETER
Water Temp.
Dissolved
Oxygen
Turbidity
Lab
Conductivity
Lab
oH Lab
\lkalinity
Hardness
Chlorides
Sulfates
Total Solids
Dissolved
Solids
Suspended
Solids
Ammonia
Nitrogen
Organic
Nitrogen
UNITS
°C

rag/1

JTU

Micro-MHO
S.U.
mg/1
rag/1
rag/1
rag/1
mg/1

rag/1

mg/1

rag/1

mg/1
MAXIMUM
28.1

11.4

60.0

2173.0
8.5
544.0
710.0
224.0
220.0
1525.0

1449.0

121.0

44.0

3.1
MINIMUM
6.3

5.1

6.0

1440.0
7.1
142.0
196.0
162.0
70.0
1037.0

987.0

1.0

0.0

0.1
AVERAGE
20.5

8.2

21.4

1603.9
7.8
407.0
451.9
193.0
156.2
1188.4

1138.4

51.0

7.7

2.3
Nitrate
Nitrogen
Total
Phosphorus
C-BOD2
C-BOD5
C-BOD7
C-BOD10
C-BOD15
C-BOD20
N-BOD5
TOC
COD
mg/1
22.0
0.0
5.3
mg/1
rag/1
rag/1
mg/1
rag/1
mg/1
rag/1
rag/1
rag/1
mg/1
3.7
110.0
176.0
182.0
214.0
282.0
292.0
9.8
140.0
431.0
0.1
0.6
2.5
5.0
7.3
9.0
10.2
8.5
25.0
70.0
1.2
8.4
18.4
25.5
35.2
53.7
70.0
9.2
50.9
174.3
        FIGURE  5.2   PROCESS WATER CHARACTERISTICS
                               62

-------
every ton of waste at the tipping floor.  This is a net



reduction of 24 percent of the material to be taken to the



landfill from the Franklin plant.







The glass plant rejects taken to the landfill are low in



putrescible organics and may not require covering, depending



upon the location.  Nuisance conditions resulting from



landfilling this material are minimal.  Some flies were



detected in warm weather where the material was landfilled



and a slight but unobjectionable odor is detectable.  No



negative environmental impact exists because of landfilling



this material.







5.5       NOISE



Systech performed a noise survey of the plant during normal



operations to determine the noise level in the glass plant.







The Occupational Safety and Health Act requires that no



employee be exposed to noise levels greater than 90 dBA for



a period 8 or more hours a day.  As the noise level increases,



the allowable exposure is reduced.







The glass plant has noise levels in excess of 90 dBA.  The



average noise level was approximately 94 dBA.  Thus, personnel



cannot work in the Glass Recovery Plant full time without



exposure to levels exceeding Federal standards.
                                63

-------
A second generation plant could easily make provision for



reducing the noise levels.  This could be accomplished



through the use of sound-absorbing materials and partial



enclosures about some of the noisy items  (air ejectors and



optical sorters).







A major source of the noise in the glass recovery system is



the operation of the vibratory conveyors and bucket elevators



It would also be necessary in a new plant to enclose the



bucket elevators and the vibratory conveyors to achieve



compliance with Federal noise level standards.  Another



approach to noise control would be to replace the bucket



elevators with another type of conveyor.







5.6       COMMENTS ON INDUSTRIAL HYGIENE







5.6.1     In-Plant Dust



The dust collection system at the Franklin Glass Recovery



Plant appears to function efficiently and, as a result, no



appreciable in-plant dust problem exists.  Dust is removed



from the kiln dryer, electrostatic separator, transparency



sorter and color sorter,  so that dust accumulations do not



occur.  If a less efficient dust collection  system was used,
                               64

-------
dust problems could be significant.  Excess glass dust in
the air could contribute to silicosis and other respiratory
problems.

5.6.2     Bacteriological Comments
In a previous study, samples were taken of several streams
within the pulping and separation system and the Whitewater
system and analyzed for bacterial contamination.  Of these,
only Whitewater passes to the glass plant.  The Whitewater
was found to contain a total coliform count of 2.0 x 108/
100 ml, fecal coliform count of 13 x 108/100 ml, and a total
plate count of 0.28 x 109/100 ml.  The input to the glass
plant coming from the liquid cyclone is saturated with
Whitewater, and thus is highly contaminated from a bacteri-
ological viewpoint.

Water added at the washing/sizing screens is city water.
The water used by the heavy media separator and the jig  is
process water.  Except for the jig  (most of its water is
recycled to the jig), this water is collected in the sump
and used as makeup water for the pulping and separation
system.  Thus, there is no water effluent, per se, from  the
glass plant to the outside environment.
                               65

-------
The process streams within the plant and recovered products



are biologically contaminated and workers who handle this



material should do so only when required.  They should wash



or shower appropriately after handling the material.







5.6.3     In-Plant Odor



No appreciable odor is present in the glass recovery system.



The material processed by the glass plant is washed in the



washing and sizing screen at the front-end of the plant.



This removes the majority of the putrescible matter which



is on the surface of the glass particles.  In addition, the



material down stream of the drying operation is of a



relatively dry nature and does not produce an appreciable



odor.  The wet material input to the glass plant, if allowed



to stand for a length of time, develops  a sharp, rancid odor.



Mold growths will also develop.  This is not a problem with



the drier material in the following sections of the plant



or a plant operating in a continuous manner.  In general,



odor is not a significant problem in the Glass Recovery Plant,
                               66

-------
6.0       ECONOMIC ASSESSMENT








6.1       INTRODUCTION



The Franklin Solid Waste and Fiber Recovery Plant is a



facility designed to demonstrate wet processing of solid



waste for disposal and recovery of some materials.  It must



be remembered that the plant was designed and constructed



for demonstration purposes.  As such, the glass plant module



of the Franklin Solid Waste and Fiber Recovery Plant has



undergone extensive modifications, additions, and changes



during the past 2 years, to improve reliability and product



quality.  Hence, the economics of the glass plant at Franklin



are not truly representative of glass recovery economics.








Many of the changes, additions, and modifications that have



been made at the glass plant, tend to skew the overall



economics of the system.  Since work to accomplish these



changes has been classified as maintenance activities for



accounting purposes, the modification related labor and the



actual maintenance labor are not distinguishable.  Hence,



an assessment of the real economics of the glass plant in



Franklin required definition of a system that would yield



the desired recovered products and then obtaining pertinent



economic data for such a system.  This data was scaled from



the Franklin plant to 500 and 1000 TPD plants.
                               67

-------
Because of the volatile nature of the Franklin glass plant



configuration, most of the subsequently reported economic



projections were developed using engineering cost accounting



procedures.  Considerable effort was expended to assure



that the results are representative of an operating plant and



not simply this developmental experience.  To accomplish



the economic evaluation, it was necessary to develop the



costs associated with both the construction and operation



of the glass plant module.  The glass plant includes the



unit operations discussed in Section 2.0.







The data required to perform the economic evaluation was



derived from information provided by vendors, the U.S. EPA,



Black-Clawson, GCMI, and the City of Franklin.







It must be remembered that the glass plant is indeed a module



that must be attached to a separation system which yields



a heavies  fraction.  When evaluating the economics of the



glass plant, it is important to  simultaneously evaluate  the



economics  of the pulping and separation  system with the  glass



plant module.  This is  appropriate  because the glass plant



requires a specific type of  feed that can be obtained from



the pulping and separation system.   This report presents the



economic analysis of  the glass plant module by itself and



also couples  this data  with  an integrated disposal  facility



producing  refuse derived  fuel  (RDF).
                               68

-------
6.2       APPROACH TO DEVELOPING THE ECONOMIC DATA



The basis of the economic analysis is the operating experience



gained at the Franklin Glass Plant.  Where possible, data



incorporated in the base is representative of the actual



operating experience at Franklin.  The cost factors used to



quantify the Franklin operating experience included the



following:





     a)  revenues - non-magnetic metals, magnetic metals,



         and glass sales.





     b)  operating costs - operating labor, maintenance



         labor, operating supplies, maintenance materials,



         utilities  (fuel, power, water, etc.), and other



         expenses.





     c)  facility expense - amortization and  interest.







The objective of the economic analysis is to  use the data



gathered from the Franklin experience to help project  the



economics of larger commercial plants.  No attempt will be



made to show the economics of the  Franklin facility because



it is  a demonstration plant.  Hence, it has not been operated



to maximize output and minimize cost.  For example, there



has been no continuous sale of glass or aluminum from  the



operation of the Franklin Glass Plant.  Plant changes  have
                               69

-------
been made continuously throughout the last two years to



upgrade the quality of the recovered products.  Hence, to



make an economic evaluation of this facility would be in-



appropriate and misleading since it has inherently no chance



of being economic.  Instead, the technical and economic data



available from the operation of this facility will be used



to project commercial facility configuration and cost for



500 and 1000 TPD plants.







6.3       DEVELOPMENT OF COST DATA AND PROJECTED ECONOMICS



In order to have a complete understanding of all factors



comprising the income and expense for the operation of the



Franklin plant and the projections to 500 and 1000 TPD,



the following sections describe the income and expense



categories used.  The cyclone reject inputs to the glass



plant will be 53.5 TPD and  107 TPD, respectively for  the



500 and 1000 TPD plant size.







6.3.1     Income



Income that can be realized form the operation of the



Franklin Glass Plant are  from the sale of three commodities:



magnetic sales, non-magnetic sales  (aluminum), and glass



 (see Table 6.1).  A potential credit also exists because  the



amount of material taken  to the  landfill for  disposal is



reduced.
                                70

-------
   INCOME SOURCE
TABLE 6.1  INCOME SOURCES

    PERCENT OF MATERIAL
       IN RAW REFUSE
       (TIPPING FLOOR)
             PERCENT RECOVERED
             IN GLASS RECOVERY
                   SYSTEM
Glass
Flint
Amber
Green

6
2
1

.0
.2
.3

50**
50
50
 Magnetic Metals
            1.0 (9.8) *
                     10
 Aluminum
            0.9
                     72
 *Remaining fraction of the magnetics in the solid waste is
 recovered in the pulping and separation system.
**Based on recovering approximately 50% of input glass.  Actual
 operating experience showed this to be lower.  However, it
 is estimated that new operating procedures and equipment
 changes will yield a 50% recovery of input glass or higher.
                TABLE 6.2  REVENUE FACTORS
INCOME
SOURCE
Glass
Flint
Amber
Green
TONS MATERIAL
RECOVERED/
PER TON INPUT
(Tipping Floor)
.03 T/T
.011 T/T
.0065 T/T
ASSUMED MARKET VALUE
IN DOLLARS PER TON
(Early 1976)
$ 20.00/T
$ 20.00
$ 20.00
INCOME PER
TON INPUT
(Tipping
Floor)
$ .60
$ .22
$ .13
 Magnetic
  .001 T/T
$ 25.00
$ .025
 Aluminum
  .0065 T/T
$ 300.00
$1.95
                                71

-------
The assumed market values indicated in Table 6.2 for the

aluminum, magnetics, and glass are based upon quotations

received by Black-Clawson from sources who have agreed to

purchase these materials from their Hempstead  (Long Island)

facility which is currently under construction.  This facility

will include design changes that are expected to improve the

purity of the recovered glass and aluminum compared to the

Franklin products.  These market values were substantiated

by contacts with other sources made by SYSTECH during this

study as well as during a separate study being performed

for the Navy's Civil Engineering Laboratory3.  All commodity

purchase prices are F.O.B. the plant and consequently assume

a user within 500 miles of the plant.



The revenue factors were based on an average percentage  input

of 9.8 percent for magnetics, 0.9 percent for  aluminum,  and

9.5 percent for glass in the  received refuse  (tipping floor).

These fractions are typical of Franklin Refuse and the

procedure outlined  in Tables  6.1 and 6.2 should be followed

to revise the revenue projections for the solid waste

characteristics in  other areas.  By using tonnage based

revenue  factors,  they remain  constant for all  plant  sizes.

Hence, they can be  used directly in the 500  and 1000 TPD

plant economics.
 3Rigo,  H.G.  and Hausfeld,  B.A.,  Development of Alternative
 Approaches to a Small Scale Solid Waste Transfer/Resource
 Recovery Station for Navy  Installations,  Contract No.
 N68305-76-C-0025,  Civil Engineering Laboratory, Port Hueneme,
 California,  1977 (in press).

                               72

-------
6.3.2     Description Of 500 And 1000T/D Glass Plant



Before projecting costs of 500 and 1000 TPD  (Tipping Floor)



glass plants, it is necessary to determine the processing



equipment required by these glass plants.  The required



processing equipment was determined in the following manner:





     1)  unit operations data gathered at Franklin formed



         a basis





     2)  needed improvements were identified and translated



         into hardware changes using literature and vendor



         information





     3)  consultation with Black-Clawson representatives



         was coupled with our observations.







It must be recognized that many components projected to be



installed in large glass plants are bigger than any heretofore



operated.  Hence, cost and performance projections are based



heavily on vendor and Franklin experience.







It is known that several pieces of equipment sized in



Figure 6.1 and 6.2 is used in minerals and minimg industries,



and  is frequently capable of processing tonnages much in



excess of that indicated.  Equipment that is based upon



Franklin performance data includes the jig, color sorter,



and  opacity sorter.
                               73

-------
                  53.5T
         STORAGE
  I.2T
REJECTS r SCREEN
 6.9
      ")  MAGNET
   4.3
                      42.3
                      35.4
HEAVY MEDIA
 SEPARATOR
                                        31.1
J



IG

1





Jl

X

G

>







2ii
B|
                                            29
                                     DRYER
                                                           DRYER
                                                                          2.1
3.7
HTES
"* 3 ROLLS

REJECTS ^
1.6 *
1 k

i ~—
OWCITY
SORTER
1


COLOR
SORTER
1 1
AMBER GRE
5.5T 3.

5"


r

•EN
2T


-25.3
i

OPACITY
SORTER



1 23.7

COL
SON
/•

.
.OR
TER
\


r
i

i
FLINT
i

COLOR
SORTER

5T

                                                                      ALUM  REJECTS
                                                               NOTE: THRUPUT RATES
                                                                    FOR MAJOR EQUIP-
                                                                    MENT ITEMS ARE
                                                                    PRESENTED IN
                                                                    TABLE 6.5
         FIGURE  6.1
         PROJECTED FACILITY DESCRIPTION FOR A FRANKLIN
             GLASS PLANT SIZED TO PROCESS FEED FROH
               500 TPD  PLANT
                              74

-------
       STORAGE
                 I07T
       SCREEN
  22.4       „„ 0
          |  84-6
l3.8rTMA^EFQ
8.6
          J70.8
HEAVY MEDIA
 SEPARATOR
                                                                     ALUM  REJECTS
                 AMBER   GREEN
                 II.OT     6.4T
                                                   NOTE :  THRUPUT RATES
                                                         FOR MAJOR EQUIP-
                                                         MENT ITEMS ARE
                                                         PRESENTED  IN
                                                         TABLE 6.6
           FIGURE 6.2
               PROJECTED FACILITY  DESCRIPTION FOP. A FRANKLIN
                 GLASS PLANT SIZED ^O PROCESS FEED FROM A
                   1000 TPD PLANT
                                          75

-------
The large plants are sized to process the glass plant feed



in two shifts or approximately 12 to 14 hours.








No attempt was made to use the thru-put rates of the Franklin



Glass Plant to size the equipment required for the 500 and



1000 TPD facilities.  The Franklin plant had undersized



equipment early in the processing line that adversely effected



the thru-put of the entire system.  Hence, no meaningful



thru-put rates could be established for many of the components



installed at Franklin.  Hence, manufacturers data and the



literature became a major technique for estimating the equip-



ment for the entire process line.








6.3.3     Operating Expense Items



The following categories were developed and used for deriving



the operating expenses for a Franklin  Glass Plant.








6.3.3.1   Operating Labor



This category includes the personnel required  for the operation



of a Glass Recovery Plant and projects the operating labor



force needed at a glass plant coupled  to  a facility receiving



500 and  1000 TPD  (Tipping Floor)  of  solid waste.  Table  6.3



summarizes the development of this data.  The  total operating



man-hours  (MH) required per day  by each of the facilities



are:
                               76

-------
               Franklin 50 TPD - 26 MH

               Franklin 500 TPD - 68 MH

               Franklin 1000 TPD - 68 MH


These man-hour projections and appropriate salary rates can

be used to project operating labor costs for each size

facility.  It should be noted that the proposed facilities

for 500 or 1000 TPD operations will require two shifts to

process the material.  As can be seen in Table 6.3, the

operating labor force for the 500 and 1000 TPD plant is

identical.  The reason for this is that operational tasks

are identical for both size facilities and there is not a

significant difference in the amount of equipment that must

be operated for the processing of the material.  The data

for the 50 TPD plant was the actual operating experience at

Franklin.



               TABLE 6.3   OPERATING LABOR
                                  2 Shift Total   2 Shift  Total
                Franklin 50 TPD       500 TPD       1000 TPD
Supervision
Chief Operator
Assistant Operator
General Labor
Office
\
1
1
1
0
%
1
2
4
1
h
l
2
4
1
                               77

-------
6.3.3.2   Maintenance Labor



Very little data has been recorded for the maintenance



requirements of the Glass Plant as it exists at Franklin.



The reason for this is that the plant has been significantly



modified many times over the last two years and it is



impossible to separate actual maintenance costs from the



cost of changes in equipment that have been performed by



maintenance personnel.  Table 6.4 presents an estimate of



the maintenance man-hours associated with the operation of



the Franklin plant in the evaluated configuration and also



projects the maintenance labor requirement to 500 and 1000 TPD



plants  (Tipping Floor).  Table 6.4 is a projection of the



maintenance hours required to maintain these facilities



based upon equipment similar to that being used at Franklin



and assuming that the maintenance problems observed for this



equipment will continue but that obvious improvements will



have been made.







              TABLE 6.4   MAINTENANCE LABOR

Chief Mechanic
Helper
FRANKLIN
50 TPD
\
\
FRANKLIN
500 TPD
h
l
FRANKLIN
1000 TPD
1
1
                               78

-------
6.3.3.3   Operating Supplies



This category reflects all the cost for the operating supplies



and includes all consumables required to operate the Glass



Plant.  Since no record for the Franklin Glass Plant has



been maintained at Franklin, this factor had to be estimated



($.03/T).








6.3.3.4   Maintenance Supplies



Again, no records exist at Franklin that adequately describe



the glass plant maintenance supply cost.  However, during the



evaluation period, it was observed that little maintenance



was actually required in the glass plant.








Maintenance supplies are often estimated at 3 to 6 percent



of the installed equipment costs.  It is believed that a



5 percent factor would conservatively indicate the appropriate



maintenance supply costs.







6.3.3.5   Utilities



     Power - In Section 4.2.3 it was shown that approximately



     26 Kwh are required to operate the glass plant per ton



     input to the tipping floor.  This cost factor can be



     applied directly to the power costs required for larger



     plant sizes.
                               79

-------
    Fuel - Fuel oil is used to heat the building housing



    the glass plant facility.  No technique was available



    for making a direct measurement of the building heat



    fuel requirements.  Since the plant area approximates



    that of the fiber recovery module, the cost factor



    derived for the fiber recovery module  (.09 gallon/ton)



    will be used. **








    Additional fuel oil is required to operate the dryers.



    The type and size of the dryer can vary depending upon



    the material and thru-put desired.








    The type used  for this analysis was the rotary drum



     (same as used  at Franklin).   The  fuel  estimates were



    based upon vendor information supported by literature



    describing the operational  requirements for rotary



    drums.








    Water - Although  some water is consumed in the washing



    and screening  operations within the glass plant,  it



    becomes part of the Whitewater system which  is used



    as a  feed  to the  pulper.   Hence,  no charge will  be



    levied  against the  glass plant for water  consumption.



     If the  user  of the  data  wants to  estimate  the charge
"Wittmann,  T.J.,  et al,  ibid.
                               30

-------
     for water usage, if the plant were attached to another



     process, he should refer to Section 4.2.3 for water



     consumption data and use his local water supply and



     treatment costs to estimate this operating cost factor.








6.3.3.6   Land Disposal



With the glass plant module, some material that would normally



be landfilled is recovered.  That is, approximately 43 percent



of the cyclone reject stream is recovered as magnetics,



aluminum, and glass.








Hence, the rejects from the glass plant that require land-



filling will not be defined as an operating costs to the



glass plant, but for purposes of this evaluation will be



assumed as part of the operating cost of the pulping and



separation system.  However, if a potential user desires



to levy a charge against the landfilled material from the



glass plant, it can be based upon the fact that 6.5 percent



of the refuse received at the tipping floor is landfilled



from the glass plant.  A credit for reduced landfill require-



ments could also be developed if residue disposal were a



significant total cost element.
                              81

-------
6.3.3.7   Miscellaneous Expenses



This category includes all other expenses that are required



for operating the plant.  They include insurance, accounting,



taxes, security, etc.   Since records at Franklin do not



separate the miscellaneous expenses for the glass plant from



the total plant account, it is estimated that the expense



will be approximately $20,000/year, e.g., a proportional



amount of the total facility expense.








6.3.4     Facility Expense Charge



In order to develop a full economic evaluation, costs for



each of the two larger facilities must be determined so



that appropriate amortization and interest charges, depreciation



or other related facility expenses can be derived.








No attempt will be made to present the total capital costs



of the Franklin Glass Plant because,  for the reasons detailed



previously, no economic evaluation of the Franklin operation



was made.  If the reader desires to know more about the costs



of the Franklin Glass Plant, he should refer to  the report,



"Glass and Aluminum Recovery Demonstration Subsystem for



the City of Franklin, Ohio", prepared by John P.  Cummings,



dated November  22, 1976, Owens - Illinois, Glass  Container



Division, Toledo, Ohio.
                              82

-------
The cost for the 500 and 1000 TPD (Tipping Floor) glass

plant module was based on the process as modeled in Franklin

and displayed in Figures 6.1 and 6.2.  Equipment costs were

developed from manufacturers literature and construction

costs were estimated using Mean's5 and Richardson6 construction

cost estimating handbooks.  Tables 6.5 and 6.6 tabulate the

estimated costs for 500 and 1000 TPD glass plant modules.



The total facility costs for the 500 and 1000 TPD  (Tipping

Floor) Franklin Glass Plant are $1,442,000 and $2,531,000,

respectively.  However, there are other factors that contribute

to the total cost of the facility.  For purposes of the

analysis, it will be assumed that the facility will be owned

by a municipality and that 15 year bonds at 8 percent interest

would be issued to finance the facility.  Furthermore, it

is known that the total cost of the facility must  include

monies to cover a "Debt Service Fund", a "Debt Revenue Fund",

and the "Bond Finance Charges".  These items cause the total

bond issue to be approximately 30 percent higher than the

actual facility cost.7  Hence, the total capital and bond

costs are as follows for the 500 and 1000 TPD  (Tipping Floor)

Glass Plant Facilities.


5Building Construction Cost Data, 35th Annual Edition
Robert: Snow Means Company, Inc., Duxbury, Mass.
^Process Plant Construction Estimating Standards,  1976,
Richardson Engineering Services, Inc., Solena Beach, California,
7Wittmann, T.J., et al, ibid.
                               83

-------
          TABLE 6.5   CAPITAL COSTS FOR 500 T/D
                      FRANKLIN GLASS PLANT
                      (PROCESS DESCRIBED IN FIGURE 6.1)
Major Equipment Items and Cost for Processing Input To Glass
Plant From 500 T/D (Tipping Floor) Facility


1 - Screen - Vibro Energy Separator
           - 8' D - Est. Capacity  5T/HR --------   40,000

1 - Magnetic Separator                   ________   12,000

1 - Heavy Media Separator 4'D x 4'L
           - Est. Capacity   4T/HR       	 ______  100,000

2. - Jig  2 Section Jig - 26" x 26"
             .5T/HR/sq.ft.               ________   40,000

1 - Dryer  Rotary Kiln 4'0 x 30'
           - Est. Capacity 3T/HR         ________  100,000

1 - Dryer  Rotary Kiln 2'0 x 8'
           - Est. Capacity 0.4T/HR       - 	 _____   50,000

1 - HTES   - 3 Rolls  1.75D Roll
           - CAP.    1500#/HR/FT Of Rotor Length - - 	  120,000

1 - HTES   - 1 Roll  I'D Roll
           - Cap   300#/HR/FT of Rotor Length- -----   40,000

2 - Opacity Sorters - 6 Channel-400#/HR/Channel- - - - -   60,000

3 - Color Sorters - 6 Channel-400#/HR/Channel- _____   90,000

  - Conveyors, Silo's for Storage of Recovered
    Products,  Input Storage, etc.  (Estimated)- -----  200,000

  - Building-5000 sq.ft. x 30 Ft. Hight, including building
    electrical and plumbing  (16.00/ft2)  --------   80,000

  - Electrical and Plumbing for Process Equipment- - - -   60,000

  - Installation of Above Equipment
    Estimated  Cost                       ________  200,000
                                                       $1,192,000

Engineering Costs  10% of facility
                                   Cost  	 _____  119,000
                                                        1,311,000
Start-Up Costs 10% of Total              _______    131,00
                                                       $1,442,000

Note - No Land Cost Included
                                    84

-------
          TABLE 6.6   CAPITAL COSTS FOR 1000 T/D FRANKLIN
                      GLASS PLANT  (PROC2SS DESCRIBED IN FIGURE 6.2)
Major Equipment Items and Cost for Processing Input to Glass Plant
From 1000 T/D (Tipping Floor) Facility


2 - Screen - Vibro Energy Separator
           - 8'D Est. Capacity   5T/HR   --------    80,000

1 - Magnetic Separator                   _---____    12,000

1 - Heavy Media Separator 6'D x 5" Long
           - Est. Capacity   6T/HR       _-____-_   150,000

2 - Jig    - 2 Section 36" x 36"  5T/HR/ft2  	 - 	    80,000

2 - Dryers - Rotary Kiln 4'D x 30'
           - Est. Capacity 3T/HR         ___--___   200,000

1 - Dryer  - Rotary Kiln 2'D x 81
           - Est. Capacity 0.4T/HR       --____--    50,000

1 - HTES   - 3 Roll - 2.5'D Roll - 1500#/HR/ft of
             Rotor Length                ________   160,000

1 - HTES   - 1 Roll - I'D Roll - 300#/HR/ft of
             Rotor Length                ________    40,000

3 - Opacity Sorters - 6 Channel-400#/HR/Channel- - - - -    90,000

5 - Color Sorters - 6 Channel-400#/HR/Channel- -----   150,000

  - Conveyors, Silos for Storage of Recovered Products,
    Input Storage, etc.  (Estimated)      ________   400,000

  - Building - 10,000 sq.ft. x 30 FT High including
    building electrical and plumbing  (16.00/ftz) - - - -   160,000

  - Electrical and Plumbing for Process Equipment- - - -   120,000

  - Installion of Above Equipment  (Estimated)- -----   400,OOP
                                                         $2,092,000

     Engineering Costs 10% of Facility   --______   209,OOP
                                                         $2,301,000
     Start-up Costs  10% of Total        ________   230,000


                    TOTAL CAPITAL COSTS  ------- -$2,531,000


     NOTE:   No  land  cost  included.
                                    85

-------
                 CAPITAL AND BOND COSTS

                                 500 TPD      1000 TPD
Project Cost                   $1,442,000   $2,531,000

Total Bond Issue               $1,874,000   $3,290,000

Annual A & I (11.683 percent)* $  218,900   $  384,300

  *Based upon 15 years and 8 percent  (a Capital Recovery
   Factor of .11683) .



6.3.5     Estimated Economics For A Franklin Glass Plant To
          Service 500 and 1000 TPD  (Tipping Floor) Facilities



6.3.5.1   introduction

Before presenting the estimated operating costs for the glass

plant modules servicing a 500 and 1000 TPD  (Tipping Floor)

facility, some discussion about the facilities and its

operation is necessary.



Each of the facilities are to be operated such that all

received products and/or landfilled material will be  conveyed

to storage bins for easy removal by a contractor.  This is

done to reduce the labor required for material handling.



Each of the facilities will operate two  shifts with maintenance

being performed on the third shift.   The glass plant  modules

for the 500 and 1000 TPD facilities will require  approximately

5000 and 10,000 sq. ft. of building space,  respectively.
                               86

-------
Much information has been gained from the operation of the



Franklin Glass Plant regarding the processing of material



to achieve a better quality product.  This information will



be used extensively in the design of the larger glass plants.







The recovered aluminum at Franklin has too high a contaminant



level to be of much commercial interest.  It was determined



that by drying the aluminum rich fraction from the jigging



operation and running the material through an electrostatic



separator, a higher quality aluminum product could be



achieved.  Hence, new facilities should incorporate an



additional dryer and electrostatic separator for the aluminum



recovery operation.







Recent changes, made after our evaluation, have included



new optics in the color sorters to allow color sorting of



smaller glass particles.  The glass sorters during the



evaluation required particles to be \ in.  The new optics



will permit sorting of particles down to 1/8 in.  This



modification will increase the glass yield; however, no



yield estimate can be made until performance tests are



conducted.  The revenues from glass in this analysis were



based upon a 50 percent yield (a 4 percent improvement),



although Black-Claeson anticipates even higher yields.
                              87

-------
The cost estimates presented for the 500 and 1000 TPD plants

do not reflect the cost of land.  This value varies con-

siderably and, hence, was not considered in this analysis.

All labor rates and other schedules for determining the total

category costs are presented in the notes for each projected

facility cost.



6.3.5.2   Estimated Economics For 500 TPD Franklin
              Glass Plant

Table 6.7 summarizes the estimated costs for the operation

of a 500 TPD Franklin Glass Plant.



Income from the sale of recovered material amounts to

$2.93/T  (Tipping Floor).  Operating expenses are 2.19/T

and the  facility expense is $1.70/T.  Hence, the net loss

from the operation is $.96/T).  An analysis for the recovery

of magnetics and aluminum only  also show a non-profitable

operation.



6.3.5.3   Estimated  Economics For 1000  TPD Franklin
              Glass  Plant

Table 6.8 summarizes an estimated cost  summary  for the operation

of a upgraded 1000 TPD Franklin Glass Plant.
                               88

-------
Q
CU
EH

O
O
                         Q
                         W

                         U
                         §
                                      O O     0  O  O

                                      fl> 0)     0)  Hi  4)
                                      33     333
                                      IT) (0
                                                (0  (0  «
                                      0) 0)     
O
IH

C
0
u

c
0

•a
0)
0)

as

E
O

(4H

01
Ul
10
rH
O

f]
4J
• rH
3

4J
O
(0

4-1
c
0
u

• c
~ 0
4-1
CJ 'O
10 CU
rH 01
Cu (0
CQ

^
o
<+H

c
o
•H
4-1
(0

a
u
o
u

r4
(I)
C
•rH
ID

C
O



o
o
CK
"- —

•0
ro
01
4J
0)
cu
0)
33

E
0

MH .
.— .
01 4-1
01 C
ffl 10
rH rH
O CU



J>,
V-i
CD

O
U

y
(0
fa



















•
^-^,
C*P
00

4-)
rd

                                                                                                   CO
                                                                                                             CQ  OQ
                                                                                                                                 O
                                                                                                                                 Z
                         w
                         EH
                         tn
                         o
                         CJ
                         w
                         cn
                                                                                                                                                      EH EH EH
                                                                                                                                     EH EH O
                                                                                                            n p- '
                                                                                                            rH rH
                                                                                                            CO- 
                         Z
                         O
o o
o o
             Cfl CN
             VO V£
             CN ON


                O
                (N
                                                O O O
                                                o o o
                                                o m r-
                                                U1 VO O\
                                               ooooooooo
                                               ooooooooo
                                                                             I 

                        U

                        CQ

                        EH
ui m
0) 01
rH rH
(0 ro Ul
cn w cu
rH
U E fl
H 3 CO 4J in C
4J C COO)
0) -H 01 -H X) 01
M C E 01 -H E M
£ CJ* 3 iD Urf  C
IH O'HOUO) rHlOrH
ai v-i ja rH a 3 cuai-H
&0 rOa3O 3Sr<
o £> t-5 a.tn a. b
<0 3
4J rj cu cn oi i i
c ou
10 rH C CT C 01
4-1 rg 01 (0 C ID 0)
01 rH O C -H C -
-------
                                                                                              O
                                                                                              in
o
o
o
 O
 K
 &4
                       EH
                    EH\
O  O
O   •
  •  o
in  o
CM  n
«>••

<4H  <4-l
 0  0

 0)  01
 3  3
r-l  r-l
 m  10
>  >

 0)  0)
rH  rH
 10  fO
to  to

 c  c
 0  O

•c  n
 o>  oi
 Ul  (A
 10  (0
 03  03
           EH EH EH
 Ul
 o>  i« tn  tn in tn
 c^ ^y d)  0} o) o
 c  o^ o^ tr* CT* CP
•H  C C  C C C
 !_,  .H -^ -H -H -H

    fit, fi^ [|i^ Jj^ Q^
 ON
 C  &* c^ D^ o^ Cr*
•H  C C  C C C
*0  -H 'H 'H !H *H

rH  3 3  3 3 3
 (J  rH rH i-H i-l i-H
 C  U O  U CJ U
M  c e  c c c
                                                     in o o o o o
                                                       • in m o o o
                                                     o	
                                                     rH ON oo r- vo ON
 c  c  c  c c  c
 O  O  O  0 O  0

^0  ^3 *O *O f-0 *O
   ON
ui  c
0 -H
O  4J
    «S
4J  IH
C  01
                                                                              a

                                                                              3  M
                                                                              crx:
                        •o  3
                        oi is
                        rH
                        rH O
                        (0 <0
                        4J i-H
                        (0
                        C  0)  JC
                        H  O> 3
                                                                             *P  IA V.
                                                                             m  3 o
                                                                                    m
                                                                              C  fi   •
                                                                              0  0 *H TJ
M 10
4-> (0 0)
C T) 4J
O r-l (0
CJ 0 0.
C E
C >i 01
O 0> X

•0 E
01 T3 0
Ul C IH
Ifl (0 tH
OQ


V)
W
fT3 M CD
rH 0 O
O 
01 CO
^
O s>
U

i-H U) l»H
04 (0 O
OQ
                                                                                                                to
                                                                                                                H
 CO
 O
 CJ
                                                                                            EH EH EH
                                                                                                                           EH
                                                                                                                           \

                                                                                                                           O
 CO
 C/l

 3
 2
 M
 2:
 o
 a
 00
   •
 vo


 U
 J
 CQ
O O O O O
o o o o o
r^ in o o m
p"i (N O ro ON
in ON cr> i** f^*
rH tS V CM
^* rH
CO-











Ul Ul
01 01
rH rH
(0 iO Ul
to to o)
rH
O E * 4J W C
•rl 3 tO C 01 0)
4J C -H fl 0)
01 -H tn rH E >H
u c E tn &-• < cj
Z ON 3 <0
O TJ ^H ^^
U Z < 0
2
M
O OOOOOOOOO OOO
O OOOOOOOOO OOO
r-- oinoomomoo om^n
CO VOOrHr^it^rHTTinCM 'gOtN'N
oo oomot^oovoor- OOOM^S
CM rHn^trHCIOOrH POrO
V£



1
Vl Ul rH O>
O 0) -H C
4-i tn -H o -IH in
>0 IH 01 rH IH 4-i C
InkH O-rlCUO) rHIOrH
kj OOllH flr-4Q,3 OlOI'iH
0 4J£XiO lOOiaO 3Z«U1
COflCfOOfl t-4CUtOCU EIH 01
W <0 0 IH fl 3 Ul
tO>J-HO)4JrJ OICA01I 1 C
z in a. c u u oi
WCT>"HOlOrH CO">CU1 £1
04C> 4JiOOIiOCn30) X
X-iHlH>»HUlUCJC-rlC-r4 U
U4-IOI01--HOI-HOI4JOI4-I
(0 CU--H U1C«H4-»I04J-H IH
cj)u3x:tnoil*HCiHCrH oi
20)tOCJi
>4 O rH
EH 01 r-* A
M -p-l «3 4-1
r3 O 4-1 C
M In O O
CJ O< EH Z
1^
fcj
OOO
OOO
r- in o
OO i-H O
00 ON O
i— 1 rH CM
^O fl fl
CO-










01
Ul
c
0)
a
X
X W
IX
< in >
Z 01 4-1
Z 0) Ul --H
3 e C rH
to O 0) -H
u cu o
EH C X (0
O3 M a &u
o
o
._
o
.
CO

-------
Income from recovered materials are the same as in the



500 TPD case and amount to $2.93 (Tipping Floor).  Operating



expenses are lower, however, due to no increase in labor



and amount to $1.48/T.  The facility expense also falls on



a per ton basis to $1.49/T.  Hence, the net loss from



operation of the plant is  ($.04/T).








The recovery of aluminum accounts for 67 percent of the



total revenue.  By installing only the equipment necessary



to recovery the magnetics and aluminum, it can be shown



that an aluminum recovery plant servicing a 1000 TPD facility



can yield a pre tax profit of $.44/T.  Hence, it appears



that magnetic and aluminum recovery would be more attractive



than adding glass recovery.








6.4       COST SUMMARY OF FRANKLIN SOLID WASTE FACILITY



Table 6.9 presents an economic summary of the operation of



a Franklin Solid Waste Plant projected to 500 and 1000 TPD.



The facility costs have been adjusted to reflect early 1976



prices.  This summary sheet is presented to show the complete



operation of a Franklin type facility.  The summary is



presented for a plant that does not recover fiber but rather



it sells the rejects as a fuel.  The projection includes  the



recovery of magnetics, glass, and aluminum.  This assessment
                               91

-------
        TABLE 6.9   ECONOMIC SUMMARY OF PROJECTED FRANKLIN
                     PLANT WITH NO FIBER RECOVERY, WITH GLASS
                     PLANT, AND SELLING REJECTS AS A FUEL
                              FRANKLIN PROJECTED  FRANKLIN PROJECTED
       COSTS                     TO 500 TPD         TO 1000 TPD
INCOME*
Pulping And Separation
Magnetic Metals
Sludge Disposal
Fuel
Glass Plant
Magnetics
Aluminum
Glass
Total Income
OPERATING EXPENSES
Pulping And Separation
Glass Plant

FACILITY EXPENSE**
Pulping And Separation
Glass Plant



$ 2.40/T
1.75/T
10.71/T

.02/T
1.95/T
.95/T
$17.78/T

$ 6.04/T
2.19/T
$ 8.23/T

$ 6.57/T
1.70/T
$ 8.27/T


$ 2.40/T
1.75/T
10.71/T

.02/T
1.95/T
.95/T
$17

$ 5.50/T
1.48/T
$ 6.98/T

$ 6.12/T
1.49/T
$ 7.61/T
 Total Expenses                              $16.50/T

NET SAVINGS                                  $ 1.28/T             $  3.19/T

*Based On Following Revenue Factors
   Magnetic Metals - $25.00/T
   Sludge Disposal At A Rate Of  .07/T Input - $25.00/T
   Fuel - $1.25/MBtu
   Aluminum - $300.00/T
   Glass - Flint, Amber And Green - Each At $20.00/T

**Based On Following Facility Costs Projected To 1976 Prices.


                                   500 TPD          1000  TPD

Weighing & Receiving, Pulping,
 Separation And Dewatering       $6,524,000        $12,145,000

Glass Plant                       1,442,000         2,531,000

TOTAL PLANT COST                 $7,966,000        $14,676,000
                                    92

-------
is presented because the glass plant cannot exist without



some front-end system preparing the feed to the glass plant.



The economic data for the front-end system was taken from



the data reported and collected in Wittmann, et al.8








The net savings for this type of operation is $1.28/T for



a 500 TPD plant and $3.19/T for a 1000 TPD plant.  The use



of the fiber as a fuel is necessary for a facility of this



type to be financially sound.  Sixty percent  (60 percent)



of the income is derived from the sale of the fuel product.








The data presented in Table 6.9 includes no tipping fee,



hence, the net operating costs can be compared directly to



existing disposal costs with the following exception.  It



should be noted that for these examples, no charge is made



for the land on which the facility is to be established.



Individual communities may readily approximate the cost of



land locally and add the appropriate amortized capital cost



of the land to the facility expense charge to obtain a



specific projection for their community.








6.5       ECONOMIC OBSERVATIONS



Industry and municipalities use different techniques to



assess the merits of an investment.  What may not be



attractive to industry could be attractive to a municipality,
 Wittmann, et al, ibid.
                               93

-------
The following discussion presents an appraisal concept used

by industry to determine the merits of a potential investment.

This approach was used because it is our opinion that most

municipalities are looking for turn-key operation of an energy/

resource recovery system with industries providing the capital

to protect municipal banding limits.


One of the techniques used by industry to determine the merit

of an investment is to use a term called Annual Return On

Investment (AROI).  This term, depending upon the industry,

can be defined in many different ways.  For purposes of

our discussion here, AROI will be defined as follows:
                            Gross Profit  (Year)
                             Total Investment
Analyzing a complete Franklin type facility projected to

500 and 1000 TPD with a glass plant and the sale of the

fiber as a fuel  (RDF), the following table was derived.
TIPPING
FEE
500
1000
TPD
TPD
0
0
.0
.0
GROSS
SAVINGS
$165,
$823,
000
000
TOTAL BEFORE TAX
INVESTMENT AROI
$ 7
$14
,966
,676
,000
,000
2
5
.1%
.6%
                               94

-------
As indicated, an AROI for the 1000 TPD plant size is only



5.6% before tax, a very unacceptable AROI for industry.  It



should be remembered that the data is based on net savings



which does not include a tipping fee.  As an illustration,



if a $10.00 tipping fee were included in the above analysis,



a before tax AROI of 23% is realized.  The AROI now approaches



a level where industry would become interested if the risks



are small.
                              95

-------
                       APPENDIX A

                 PICTORIAL FLOW DIAGRAMS
This section presents a pictorial flow diagram with which
the reader can visualize the various equipments used in the
Franklin Glass Plant.  Section 3, Operational Capability
describes the process flow and can be used to supplement
this pictorial presentation.
                              96

-------
                                          '!)  Storage  Vessel  For
                                               Feed  To Glass  Plant
(2)   Rotary  Screen,
      Metering  Hopper,
      And  Bucket  Elevator

-------
     [3)   Side  View  Of  Heavy Media Separator
(4)   End  View Of Heavy Media Separator
                      98

-------
                                 (b)   Vibrating Conveyor From
                                       Heavy Media Separator
                                         To Jig
(6)  Aluminum  Recovery  Jig
                                  99

-------
                            Close-up Of Jig
                             Separator
Dewatering Conveyor (Electrostatic
 Separators Shown In Background)
                100

-------
Druiii  Dryej.
[ID)   Outfrai:  ..r  Elect-roritdt ic :



                           ] 0 i
                     [ -^ ra t ors

-------
(11)   Close-up  Of  Electrostatic Separator
  ;i2)   Close-up  Of  Optical  Sorters
                       102

-------
(13)   Front  View Of  Optical Sorter

-------
                        APPENDIX B

         GLASS PROCESSING INDUSTRY  SPECIFICATIONS
                     FOR GLASS  GULLET*
    Parameter
                      Original GPI
                      Specificat ion
 Liquid Content
 Organic Materials
 Magnetic Metals
 Non-Magnetic Inorganics
 Non-Magnetic Metals
 Flint Glass
 Colored Glass
                         10%
                         0.1%
                         0.05%
                         0.1%
                         0.015%
                      Min. 95%
                      Max. 5%
                     Revised GPI
                    Specification
                     (11-9-76)
                     Do Drainage
                        0.2%
                        0.05%
                        0.1%
                   No Particles +\ in.
                  1 (one)  -\ in +20 Mesh/
                        40 Ib.
                     Min.  90%
                     Max.  5.0%  Amber
                     Max.  1.0%  Green
                     Max.  0.5%  Other
 Refractory

  +20 Mesh
 -20
 -40
+40 Mesh
+60 Mesh
 No Specification

 2 Particles/lb.
20 Particles/lb.
1 Particle/40 Ibs.
(no Particle +nt; in.
2 Particles/lb.
20 Particles/lb.,
 NOTES

 1.  Flint glass containing over 0.1% Fe2O3 and/or 0.002%
     Cr203/ by chemical analysis, shall be considered mixed
     color glass.

 2.  Flint glass can contain up to 1% emerald green or 10%
     georgia green, or a combination within these limits  (1%
     georgia green = 0.1% emerald green).
* REFERENCE:
       Glass and Aluminum Recovery Demonstration Plant
       Subsystem for the City of Franklin, Ohio, Report
       by Dr. John P. Cummings, Owens-Illinois, Glass
       Container Division, Toledo, Ohio.  Extensive cullet
       analysis was performed by Dr. Cummings and it is
       recommended that if further information is desired
       about the composition of the glass cullet produced
       at Franklin, a copy of the above referenced report
       be obtained.
                               104

-------