Waste

                           Iteatanent
                          Upgrading Poultry-Processing
                           Facilities to Reduce Pollution
PAlechndogy Transfer Seminar Publication
                     .  J

-------
                                       WASTE TREATMENT


                                           Upgrading Existing
                                    Poultry-Processing Facilities
                                           to Reduce Pollution
                     f T-•<':•>  \ P
                               , V
                                 .-- • ULlIONAGENCY
ENVIRONMENTAL PROTECTION AGENCY* Technology Transfer

                           July 1973

-------
                 ACKNOWLEDGMENT
     Tills seminar publication contains materials prepared for the
U.S. Environmental Protection Agency Technology Transfer Program
and presented at industrial pollution-control seminars for the
poultry-processing industry.

     Giffels Associates, Inc., Architects-Engineers-Planners, Detroit,
Mich., prepared this publication.
                             NOTICE
     The mention of trade names or commercial products in this publication is
for illustration purposes, and does not constitute endorsement or recommenda-
tion for use by the U.S. Environmental Protection Agency.

-------
                                      CONTENTS
                                                                                     Page

Introduction	     1
         Why Is Wastewater Treatment Needed?	     1
         Probable Wastewater Quantities and Properties	     1
         Wastewater-Treatment Processes  	     3

Chapter I. Planning for Wastewater Treatment   	     5
         Wastewater Surveys	     5
         Initial Planning for a Wastewater-Treatment System  	     5
         Selection of a Poultry Wastewater-Treatment Process	     6
         Upgrading Existing Lagoons	   10

Chapter II.  Operating a Wastewater-Treatment System  	   13

Chapter III. Case History—the Original Gold Kist Wastewater Facilities	   17
         Site Selection  	   17
         Wastewater Survey and Criteria	   17
         Selection of the Treatment Process  	   19
         The Flow Diagram	   20
         Design Criteria Used	   20
         Future Expansion Provisions   	   23
         Waste-Treatment System Costs   	   24
         Operating Arrangments   	   25

Chapter IV. Case History—Current Expansion at Gold Kist	   27
         Project History   	   27
         Current Wastewater Loads	   27
         Current Operating Difficulties	   28
         Proposed Wastewater-Treatment System Loads	   30
         Review of Component Adequacy	   31
         Proposed Modifications	   35
                                           m

-------
                                   INTRODUCTION
                      WHY ISWASTEWATER TREATMENT NEEDED?
     The discharge of waterborne wastes into a stream may impart turbidity, reduce dissolved oxy-
gen, form sludge deposits, alter salinity, pH, and temperature, produce nutrients that result in
undesirable growths, and impart toxicity to that stream. The introduction of any one of these
factors in a natural body of water may adversely affect the flora and reduce the value of that water
to subsequent users. Increased turbidity in a stream may kill fish, affect the growth of green plants
by scattering light, and result in settleable solids. Settleable solids may fill a body of water and
cover aquatic vegetation so that it will not grow. Where the settleable solids are organic in nature,
they may cause sludge blankets at the stream bottom that degrade anaerobically (in the absence of
oxygen) with the production of gases that buoy up noxious matter causing odors and scum at the
water's surface. A reduction in dissolved oxygen concentration in a stream results from the intro-
duction of oxygen-demanding substances that may be either organic or inorganic in nature. The
organic material reduces dissolved oxygen as a consequence of aerobic (in the presence of dissolved
oxygen) decomposition and inorganic substances may react chemically with the dissolved oxygen of
the stream. Fish require  a dissolved oxygen concentration of 5 milligrams per liter (mg/1) for a
wholesome life. The pH  must be maintained in the range of 6.5 to 8.5 for a well-balanced biological
system in the water course. Acids and alkalis may make the fish susceptible to fungus attack.
Increasing the salinity of a stream may result in alteration of the osmotic pressure in fish. Sub-
stances that produce nutrients will increase plant growth. Rapid growth of algae is a common result
of the excessive discharge of nutrients such as nitrogen and phosphorus. Excessive algae growth
causes tastes and odors in the water supply and also may result in the clogging of water-treatment
plant intake screens. Large concentrations of algae may result in extreme variations in dissolved
oxygen concentration from  daytime high dissolved oxygen levels to nighttime low levels. Increased
water course temperature results in accelerated oxygen depletion and a disruption of aquatic life.
The discharge of toxic substances to a stream may destroy aquatic life and render a stream of no
value as a water supply for downstream water users.

     Wastewater treatment or processing for removal of those adverse constituents described pre-
viously is required to protect the quality of existing water resources. Nearly every lake or stream in
this country today is regulated in terms of the quality and quantity of effluents that may be dis-
charged into it. Either Federal, State, or local agencies have the authority to establish water-quality
standards for the effluents and to enforce those standards. Consequently, one of the best sources of
guidance in terms of the wastewater-treatment needs of a poultry plant is the authority having juris-
diction over discharge into the receiving stream. The authority having jurisdiction shall determine
the quality  of the effluent discharged and can offer experienced guidance on this subject.
                PROBABLE WASTEWATER QUANTITIES AND PROPERTIES
     The quantity of wastewater discharged from processing operations in a poultry plant may
range from 5 to 10 gallons per bird with 7 gallons being a typical value. Poultry-processing wastewater
is typically organic in character, higher than domestic sewage in biochemical oxygen demand (BOD),

-------
                      Table 1 .—Some characteristics of poultry-plant wastewater
Analysis
pH 	
DO 	
BOD 	
Suspended solids 	
Total solids
Volatile solids ...
Fixed solids 	
Settleable solids 	 	
Grease 	

Unit

ppm
ppm
ppm
Dom
DDm
ppm
ml/l
ppm

Range
6.3-7.4
0-2.0
370-620
1 20-296
NA
NA
NA
15-20
170-230

Average
69
.5
473.0
196.0
6500
4860
164.0
17 5
201.0

and high in suspended solids and floating material such as scum and grease. Table 1 shows some
characteristics of wastewater from a poultry plant.

     Since wastewater from poultry-processing plants is typically organic, it responds well to treat-
ment by biological methods. In biological waste-treatment systems, microorganisms use the pollut-
ing constituents of the wastewater as food to provide energy for survival and growth. The primary
microorganisms encountered in wastewater  treatment are bacteria, fungi, algae, protozoa, rotifers,
and crustaceans. Bacteria can only assimilate soluble food and may or may not require oxygen
depending on whether the bacteria are aerobic or anaerobic. Fungi must also have soluble food but
are strictly aerobes; that is, they must have  oxygen to survive. Algae utilize primarily inorganic
compounds and sunlight for energy and growth with oxygen given off as a byproduct. Protozoa are
single-celled animals and use bacteria and algae as their primary source of energy. Rotifers are multi-
cellular animals that use bacteria and algae as a major source of food. Crustaceans are complex
multicelled animals with hard shells. The microscopic forms of crustaceans use the higher forms of
microorganisms as a source of food. Protozoa, rotifers, and crustaceans grow only in an aerobic
environment.

     Microorganisms find their place in the  carbon cycle at the elemental levels of conversion of
residual organic carbon to carbon dioxide. Briefly, the carbon cycle consists of green plants utilizing
inorganic carbon in the form of carbon dioxide and converting it to organic carbon by using sun-
light for energy for photosynthesis. Animals consume the resulting plant tissue and convert part of
it to animal tissue and carbon dioxide. Plant and animal tissue and other residual organic carbon
compounds are then oxidized back to inorganic carbon dioxide by microorganisms.

     Aerobic degradation of wastewater constituents is a biochemical reaction in which living cells
assimilate food for energy and growth in the presence of dissolved oxygen. About one-third of the
organics are oxidized providing the energy to synthesize  the remainder into additional living cells.
The end products of these biochemical reactions are carbon dioxide and water. When oxygen is
absent from the reaction, the degradation is anaerobic and the end products are organic acids, alde-
hydes, ketones, and alcohols. Special bacteria called methane formers metabolize about 80 percent
of the organic matter to form methane and  carbon dioxide with the remaining 20 percent forming
additional living cells. These biochemical principles are used in wastewater-treatment systems to
render wastewater streams resulting from poultry-processing facilities suitable for discharge into a
stream.

-------
                         WASTEWATER-TREATMENT PROCESSES
     Wastewater-treatment systems in the poultry-processing industry usually provide primary and
secondary treatment and may or may not include tertiary treatment. Primary treatment consists of
screening, comminutor and primary sedimentation, or flotation for removal of solid and particu-
late mat,ter. Primary treatment is discussed in more detail in the second paper of this seminar,
"Pretreatment of Poultry-Processing Wastes."

     The secondary treatment required for discharge to a stream may be in the form of an activated
sludge or trickling filter system, a system of lagoons, or an irrigation system. Each of these methods
of biological treatment has been tried with varying degrees of success. Activated sludge systems that
may be applied to poultry plant wastes include conventional activated sludge, activated sludge using
step aeration, high-rate activated sludge, extended aeration activated sludge, and the contact-
stabilization process. Anaerobic lagoons, aerobic lagoons, and a combination of an anaerobic lagoon
followed by an aerobic lagoon may be used for secondary treatment of poultry wastes. All poultry
wastewater effluents should be chlorinated before discharge to the receiving stream.

     All of the above processes are described in chapter I and represent the commonly used waste-
treatment processes. The use of other systems, such as microfiltration and certain chemical proc-
esses, while possible, is generally not prevalent due to high first and operating costs.

-------
                                       Chapter I

                PLANNING  FOR  WASTEWATER TREATMENT


                                 WASTEWATER SURVEYS
     Planning for a wastewater-treatment facility for a poultry plant begins with a survey of the
wastewater sources within the plant. An industrial wastewater survey in an existing poultry-
processing facility would consist of determining the volume and characteristics of the composite
wastewater discharge. The survey may be as simple as measuring flow and taking a composite
sample at a single point or may be as complex as measuring flows and sampling each source of
wastewater discharged. The latter has the advantage that each point within the plant may be studied
to determine the possibilities available for reducing the volume of wastewater and pollution at the
source. A discussion of reducing the waste volume within the poultry-processing plant is given in the
first paper of this seminar, "In-Process Pollution Abatement."

     For a new poultry-processing facility where wastewater flow streams do not exist, the waste-
water for the proposed plant must be synthesized based on the experiences of similar  existing
processing plants. Using this method for determining wastewater quantity and character requires
great care to insure that all waste constituents are included in the synthetic wastewater sample and
that the constituents are included in proportions that will be truly representative of the waste from
the proposed facility. It is suggested that an experienced engineer  be retained to prepare a study
that will determine the properties of the design influent.

     The volume of wastewater, in general, will vary with the bird production, increasing with in-
creased bird production and decreasing with low production.  Figure 22 shows how the volume of
waste discharged varies with time at one poultry plant. Some  of the characteristics of  wastewater
that should be determined include suspended solids, biochemical oxygen demand (BOD5), toxic
substances, grease and fats, dissolved solids, solid matter, temperature, pH, color, and septicity.
             INITIAL PLANNING FOR A WASTEWATER-TREATMENT SYSTEM
     Criteria for the design of the treatment plant are available from the authority having jurisdic-
tion for control of discharge to the receiving stream and must be evaluated by an engineer experi-
enced in the design and engineering of wastewater-treatment plants for poultry-processing facilities.

     The type of treatment and the type, number, and size of components may be selected when
the required treatment efficiency, in terms of removal of contaminants, has been established.

     Costs, both capital costs and operating costs, must be determined in the preliminary planning
phase of the project. This phase should result in a report describing the location of the waste-
treatment plant, the nature of the wastes, all the components of the proposed wastewater-treatment
system, the provisions proposed for future expansion, the anticipated removal efficiency, the
character of effluent, and the estimated capital and operating costs. The preliminary report per-
forms three primary functions.

-------
     • It may be used in discussions with the authorities early in the project.

     • It provides the cost data essential to establish the economic feasibility of the project.

     • It serves as a basis for the preparation of working drawings and construction contract
       documents.



            SELECTION OF A POULTRY WASTEWATER-TREATMEIMT PROCESS


     The secondary treatment processes commonly used in the biological treatment of poultry
wastes are: various forms of the activated-sludge process, standard and high-rate trickling filters, and
aerobic and anaerobic lagoons. In the past, aerobic and anaerobic lagoons have been employed in
the majority of private installations with activated-sludge plants as a second choice. Trickling filters
have been used mainly in plants treating both municipal  and poultry wastes. With the exception of
anaerobic lagoons, all of the processes provide complete  treatment and achieve about a 70- to 90-
percent reduction in the influent BOD and an estimated  80 to 95 percent removal of suspended
solids. Each of the systems to be discussed has its advantages and disadvantages, and in general, the
treatment requirements will dictate, to some degree, the  particular system selected. The main differ-
ences between the systems are construction and land costs. The major costs for activated-sludge and
trickling-filter plants are construction  and operating costs; whereas, the major expense for lagoons is
land-utilization costs. The following discussion will limit itself to the unit operations and
treatment-plant equipment associated with each process.


Activated-Sludge Processes

     There are four general types  of activated-sludge processes.

     • Conventional

     • High-rate

     • Extended-aeration

     • Contact-stabilization

All of the above use the activated-sludge theory, previously discussed, whereby aerobic bacteria
assimilate the organic matter  present in the waste stream for cellular growth and in that way provide
for the waste-stream purification. The common elements of all activated-sludge processes are: an
activated sludge floe, a mixing and aeration chamber, and a clarification or separation tank.

     Conventional Activated  Sludge. In the conventional activated-sludge process, the waste stream,
following primary treatment, is mixed with a proportional amount of the returned settled sludge
from the final clarifier and enters the head of the aeration basin. In general, the aeration basin is
designed to provide a detention time of 6 to 8 hours. Mixing and aeration are uniform along the
tank and are provided for by  mechanical mixers and/or pressurized air diffusers. Following aeration,
the mixed liquor is settled in  a clarifier, the clear supernatant being discharged to the receiving
water and the concentrated sludge being proportionately returned and wasted (see fig. 1). One
modification of the conventional process is step aeration, where the waste stream and/or return
sludge enters through a number of inlets along the aeration basin rather than at a common inlet. A

-------
second modification is tapered aeration, where aeration along the tank is varied. The advantages of
the conventional activated-sludge process are

     • Lower capital costs than for equivalent trackling-filter plants

     • Low hydraulic head losses

     • The attainment of high-quality effluent

The disadvantages are

     • There are higher mechanical operating costs than for equivalent trickling-filter plants.

     • It requires skilled operators.

     • It does not respond well to shock loads.

     • It generates a large volume of sludge to be disposed of.

     • Problems in sludge settling are sometimes encountered.

     High-Rate Activated Sludge. The main differences between the high-rate process and the con-
ventional process are the smaller detention period in the aeration basin and a smaller return-sludge
rate (see  fig. 2). The advantages of this system are

     • The capital costs are lower than for the conventional process.

     • The sludge generated is much denser resulting in a less-voluminous sludge to be dispensed
       with.

     • The operating costs are less because of the shorter detention time.

The main disadvantage is the lower quality of the effluent.

     Extended Aeration. In the extended-aeration process,  the aeration basin provides for 24 to 30
hours of  detention time (see fig. 3). The advantages of this  process are

     • The very high quality of the effluent

     • That less manpower time is required to operate the  process

     • That smaller volumes of sludge are generated

The main disadvantages of this process are the high capital investment required and the possibility
of sludge-settling problems.

     Contact Stabilization. In  the contact-stabilization process, the waste stream does not undergo
primary clarification but is mixed with the return sludge and enters the aeration basin directly  (see
fig. 4). Since the mode of treatment is by adsorption and absorption, a detention period of only 30
minutes is provided. After settling, the concentrated sludge is stabilized by separate aeration before
being proportionately returned to the waste stream. The main advantages of this process are

-------
     • Low capital investment

     • Low operating costs

     • The ability to handle shock loads and variations in flow

BOD reductions of plus or minus 90 percent and suspended solids removals of plus or minus 90
percent have been reported.


Trickling Filters

     As mentioned previously, the biological mechanism involved in treating waste water by perco-
lation through trickling filters assimilates organic matter into cellular growth by aerobic bacteria.
Unlike the activated-sludge process, where the biological process takes place in a "fluid bed," the
biological activity in a trickling filter is conducted on the filter medium by a surface fauna. Portions
of the bacterial fauna are continually sloughing off into the wastewater stream and are removed in
the final clarifier. Trickling filters can achieve upwards of plus or minus 90 percent in both reduc-
tion of BOD and removal of suspended solids. There are two types of trickling filters—standard-rate
and high-rate. The number of filters in series determines the "stage" of the filter system. The pri-
mary elements of a trickling filter are the covered or uncovered containing structure, the filter
medium, the waste-flow distribution system, and the subdrain collection system. The typical
mediums used are rocks, slag, and recently, honeycombed cellular modules of synthetic construc-
tion. Distribution systems are spray nozzles attached to fixed or rotating manifolds.  The sub-
drainage system may consist of tile, concrete, or synthetic drainage tile.

     Standard-Rate Trickling Filters. The main distinction of the standard-rate trickling filter is the
low BOD loading rate (see fig. 5). Its main advantages are

     • The production of a high-quality effluent

     • Low operating costs

     • That operating personnel need not be highly skilled

     • That it is resistant to shock loadings and variations in flow

The main disadvantages are high capital costs and that considerable land space is required. Flies  and
insects are sometimes a problem but are usually controllable.

     High-Rate Trickling Filters. The main distinction of the high-rate trickling filter is the high
BOD loadings (see fig. 6). These loadings may be as much as twice as great as those of a standard-
rate filter. Although, for a single pass, BOD reductions are only about 60 to 70 percent, recircula-
tion increases the total reduction. The advantages are

     • Its versatility of treating high-strength wastes

     • Its resistance to shock loads and variations in flow

     • That highly trained personnel are not required

     • That the area required is considerably reduced

     • That problems with flies and insects are usually eliminated
                                               8

-------
The main disadvantage is the high power requirements caused by recirculation.


Lagoons

     As was mentioned previously, lagoons are presently the most common method of treating
poultry waste at private waste-treatment installations. This prevalence is primarily due to the availa-
bility of low-cost land when most of the poultry-processing facilities were constructed, since both
aerobic and anaerobic lagoons require very large allocations of land. Successful operation of these
lagoons depends to a high degree on favorable climatic conditions—warm, clear, and sunny. Depend-
ing on the geological site conditions, the lagoon may require lining of the bottom. In general, the
waste stream is pretreated by  mechanical screens to remove offal and feathers. The biological
mechanisms responsible for the purification process have been discussed previously. Mechanical
aerators and diffused-air systems are used in the aerobic lagoons. A properly designed aerobic
lagoon can be expected to achieve about a 90-percent reduction in BOD and suspended solids
removal. When anaerobic lagoons are used, expected removals are only about 70 to 80 percent.
Odor problems are frequently associated with anaerobic lagoons, although chemical additives can
usually control the problem. In the past, flies, insects, and excessive growth of bordering vegetation
have been a problem. Figure 7 contains some common-flow schematics of lagoon systems.

     As an example of the variety of schemes that may be incorporated into the design of poultry
waste-treatment  systems, one  such plant has combined, as a single-treatment system, the extended
aeration and aerobic lagoon concepts to effect considerable cost savings plus a reduction in land
requirements. This system, which could appropriately be called an "aerated lagoon," has been in use
for about 6 years and reportedly achieves upwards of a 90-percent reduction in influent BOD and
suspended solids removal of better than 80 percent. Since the waste-treatment system has been such
a success and water shortage is also a problem at this plant, the Environmental Protection Agency
(EPA) has supported a pilot plant investigation to determine the feasibility of recycling the
treatment-plant effluent for use as process  water.


Costs

     The costs for waste treatment are difficult to project due, in large part, to their dependency
upon local conditions. Some of the local conditions include design codes, and climatic and geologi-
cal considerations. Table 2 provides a rough approximation of the costs of waste treatment as
applied to the poultry-processing industry. The table was constructed by adjusting average  costs of
similar municipal waste-treatment facilities to fit poultry-processing requirements. The treatment
costs presented do not reflect land-acquisition costs. The values tabulated are 1967 prices and are
based on the present-value method of calculating costs. The selected interest rate is 5 percent and
the expected life of the structure is 25 years. Considering that the actual useful life of the facility
probably will be 40 to  50 years and that the costs are based on equivalent municipal facilities, this
approach can be considered conservative and the resultant values considered "high." Municipal
plants often are required to have parallel facilities and expensive sludge-disposal equipment. Parallel
facilities sometimes increase the costs as much as 100 to 300  percent and sludge-disposal equipment
such as sludge digesters, vacuum filters, and/or sludge incinerators can amount to 30 to 50  percent
of the capital costs. For these reasons, the capital costs shown in table 2 can be reduced as  much as
50 percent or more for poultry-processing waste treatment. The table, therefore, only truly indi-
cates relative costs for the various processes; for example, the "Gold Kist" waste-treatment plant
cost less to construct than shown in the table. This reduction in capital costs was the result of

     • Climatic  conditions which did not require the facility to house air-supply equipment

     • The availability of land and the recycling of byproducts, which minimized sludge-disposal
       costs

-------
                             Table 2.—Poultry-processing waste-treatment costs

Type of treatment


Conventional activated
sludge
High-rate activated
sludge ....
Extended aeration
Contact stabilization ....
Standard-rate trickling
filter ....
High-rate trickling
filter 	
Aerobic lagoons 	
Anaerobic iagoons
Anaerobic/aerobic
lagoons ....

Capital costs,
thousands of
dollars


825

660
1,569
473

750

555
740
300

450

Level of
treatment,
percent BOD

reduction

90±

80±
95±
90±

90±

90±
90±
70-80+

90±

Operation and
maintenance
costs, cents

per 1 ,000 gallons

10.63

6.81
13.61
7.44

6.00

12.27
(')
(')

(M

Land
requirements,
acres


3.0

2.0
3.0
2.5

8.5

5.5
74.0
15.0

30.0

Total
treatment
costs, cents

per 1 ,000 gallons

15.0

11.0
25.0
9.4

12.0

13.0
8.0
3.3

4.9

Total
treatment
costs, cents

per bird

0.15

.11
.25
.094

.12

.13
.08
.033

.049

     1 Negligible.

     Note.—Based on a flow of 1.0 mgd having a BOD load of 450 ppm. Values given are calculated by the present-worth method
based on an interest rate of 5 percent and an expected facility life of 25 years. Total treatment costs do not reflect land costs.


    • The retaining lagoon, which permitted a considerable reduction in clarifier sizing

    • The fact that parallel facilities were not required
                             UPGRADING EXISTING LAGOONS
    As discussed previously, the problems associated with the operation of lagoon systems depend
heavily on the local climatic conditions. Odors are a common problem, always present in anaerobic
systems and occurring whenever anaerobic conditions develop in aerobic lagoons. Since there is no
control of the biomass, suspended solids removal and the maintenance of minimum dissolved
oxygen levels are frequently troublesome. Major constituents of the suspended solids present in
lagoon effluents are algae. In the absence of sunlight, algae require molecular oxygen for endog-
enous respiration.  During periods which are characterized by low-intensity sunlight radiation, the
algae may deplete the dissolved oxygen below the minimum requirements resulting in algae degrada-
tion and biochemical oxygen demand. Stricter effluent criteria, perhaps based on total pounds or
maximum concentration rather than a percentage removal of influent loading, should ultimately
force the abandonment of conventional lagoon systems to other alternatives or the upgrading of the
existing lagoons.

     To effect any substantial improvement in the effluent quality, any steps  to upgrade a lagoon
system must be oriented toward control of the biomass. Recent attempts to remove the suspended
solids from lagoon effluents have not met with appreciable success.  Because algae do not form dense
floes, clarification—either alone or combined with chemical flocculation—has not been successful.
Chemical flocculation followed by air flotation has had limited success but the application of this
method to the entire effluent stream would be economically prohibitive. Conversion of an existing
lagoon system to one of the forms of activated-sludge systems previously discussed is both advanta-
geous and economically feasible. In the  activated-sludge process, nutrients present in the waste
                                             10

-------
stream are used in the synthesis of the biomass. Since the biomass is ultimately separated and
removed from the waste stream, the degree of algae synthesis in the effluent stream is limited.

     In order to provide sufficient control of the biomass in converting to an activated-sludge
system, air-supply and solids-removal equipment must be provided. Generally, these will require the
installation of blowers, air-distribution systems, floating aerators, clarifiers, concentrators, and
strainers. As in all of the biological systems, some solids will have to be disposed of and considerable
attention should be given to reclaiming the solids as feed meal or fertilizer. Maximum effort should
be exerted to use existing lagoons as much as possible. In some cases, portions of the  lagoons can be
converted to serve as multipurpose units such as clarifiers or aerobic digesters, as well as aeration
basins. Lagoons  can also be used as "polishing" ponds capable of supporting fish life and providing
the capability  for recycling the treated wastewater.

     Generally, once poultry-processing operations have commenced, more reliable information is
made available—on flows, loadings, temperatures, and waste characteristics—which can be used to
establish good design criteria for the upgrading of lagoon systems. Similarly, it is often found that
changes in existing process procedures can result in reduced flows and loadings, thereby reducing
the need to size  equipment.

     Construction for the upgrading of lagoon systems is best accomplished by a "staged" sequence.
New construction should be scheduled when plant production and the wastewater flow are at a
minimum. In this way the staged concept may allow plant personnel to perform much of the re-
quired construction. Also, present effluent criteria can be satisfied while a future water-use and
waste-treatment program is established. Staged construction allows for distributing the capital costs
for treatment facilities over a period of time resulting in minimization of upgrading costs. Staged
construction could consist of initial installation of improved aeration systems, then later installation
of a clarification device, followed by final installation of a system for recirculation of process water
from a polishing pond.

     The costs for upgrading existing lagoon systems are often significantly less than those which
would be required for equivalent new wastewater-treatment systems. In short, to minimize both
present and future treatment costs, the design for upgrading an existing lagoon system should incor-
porate, wherever possible, the existing facilities, process-water conservation, and the flexibility to
provide for present or future solids reclamation and treated wastewater recycling.  Included are
some typical flow schematics (figs. 8-10) showing various methods of upgrading existing lagoons.
                                             11

-------
                                       Chapter  II

            OPERATING  A  WASTEWATER-TREATMENT  SYSTEM
     When the waste-treatment plant is designed, constructed, and finally placed on stream, it is the
responsibility of the waste-treatment plant operator to insure that the equipment performs as
intended. The intent of the waste-treatment plant is to reduce the pollutional potential of the
wastewater discharge to below specified limits. The operator must control the flow streams within
the plant to achieve optimum efficiency; this may require, as in the case of activated-sludge systems,
that the rate at which sludge is wasted and air and chlorine are applied be adjusted to assimilate the
contaminants emanating from the processing plant. The pollution load or contaminants emanating from
the plant depend upon the particular processes used within the plant, the bird production, and the plant
personnel. The waste-treatment plant operator must learn to anticipate and recognize when the influent
has changed in character and make the necessary adjustments in the waste-treatment plant flow streams
before the quality of the effluent has declined sufficiently to constitute a violation or affect the quality
of the receiving stream. Good indicators from which to judge the operation of the waste-treatment plant
are the appearance, color, and smell of sludge and wastewater in the various components, and the general
odor at the plant. A successfully operating waste-treatment plant has little or no unpleasant odor.

     Maintaining good records of the results of tests and plant operation cannot be overemphasized.
Results of record tests,  as well as  operating tests, indicate how well the plant is functioning. The
authority having jurisdiction over the discharge to the receiving stream is responsible to the public
for the proper functioning of the waste-treatment plant. Where good records are maintained, the
authorities, engineers, and others may have ready access to the history of plant operation. This
history is valuable in providing assistance in evaluating plant performance and analyzing problems
that may occur.

     The successful waste-treatment plant is also a well-maintained waste-treatment plant. Routine
inspection and maintenance procedures must be developed for each waste-treatment plant; however,
a few basic guidelines may be set  forth. A manufacturer's instruction manual and shop drawings
should be furnished for each piece of equipment in the plant. The operator should be intimately
familiar with these manuals and their contents. These manuals give complete information on lubri-
cation, adjustments, and other equipment  maintenance. The waste-treatment plant should be visited
at least once each day. Daily, weekly, monthly, and yearly checklists for inspection and mainte-
nance should be developed and followed to assure proper waste-treatment plant operation and
maintenance. The following checklists were suggested for an activated-sludge waste-treatment plant
treating wastewater from a poultry-processing plant. These checklists are not intended to be com-
plete but to serve as aids for an operator developing his own checklists.


Daily Checklist

      1.  Check the ah-compressors.

         a.    Check lubrication.

         b.   Check motor, bearings,  and compressors for overheating.
                                            13

-------
         c.   Check air filter for fouling.

         d.   Change the compressors "in service." (Set up a rotation schedule to use all of the
              compressors, including the standby, on a daily switchover schedule so that all
              compressors are operated the same amount of time.)

         e.   Check the "cold" compressor to be put into service for lubrication, free rotation,
              clean inlet filter, and so forth.

         f.   Start the cold compressor and put it on the line before shutting down the one(s)
              in service (start-up procedure, lubrication, operation, etc.), so that you can satisfy
              yourself that it is being started and operated properly and is performing satisfactorily.

         g.   Allow the cold compressor to operate while you are at the plant and recheck it before
              leaving.

      2.  Check the chlorinator.

         a.   For operation, setting

         b.   Chlorine supply

      3.  Observe the air pattern in all tanks. Adjust it if necessary.

      4.  Check the final clarifier tank for operation and flow.

      5.  Check return sludge airlift pump for operation.

      6.  Check skimmer and scum remover at final clarifier and byproducts collector for operation,

      7.  Check byproducts collector for operation and flow.

      8.  Check telescoping valve for proper sludge and grease removal.

      9.  Observe sludge appearance in all tanks. Investigate and correct any deficiencies.

     10.  Observe final clarification and byproducts collector tanks. Correct any deficiencies.

     11.  Observe the condition of raw sewage entering the plant.

     12.  Observe the operation of the froth spray system (if used). Clean it if necessary.

     13.  Check the operation of the comminutor, motor, and bearing for overheating.

     14.  Rake screenings from bypass bar screen and remove in covered receptacle for burial
on the site.

     15.  Skim floating solids from final clarifier, byproducts collector, and digester supernatant
decant chamber; place in covered receptacle; bury. (A "bug screen" on a long handle, such as is
used for removing bugs, wrappers, etc., from swimming pools, is suggested.)
                                             14

-------
     16. Hose down tank and compartment walls, weirs, clarifier center well, raw sewage inlet
boxes, and channels to maintain a clean plant. (A large 1- to 1%-inch hose with tapered discharge
nozzle to "blast" surfaces with fresh water, so that the cleanup will take a minimum of time, is
suggested.)

     17. Correct any plant deficiencies noted.

     18. Make tests—DO, sludge, and chlorine residual—as required.

     19. Recheck the operation of the cold compressor.


Weekly Checklist

      1. Use a coarse brush on a handle to brush down accumulation of algae and other foreign
matter that hosing down will not clean up; follow by hosing.

      2. Check the air compressors and sludge collector mechanism for oil level and lubrication.
(Follow the manufacturer's instructions, using the lubrication oils and greases recommended; and
observe and schedule oil changes, bearing lubrication, and other maintenance, as recommended by
the manufacturer.)

      3. Make a test of the sludge solids in the extended aeration tanks and in the aerobic digester.
Make corrections, if necessary, by adjusting the sludge return to the extended aeration tanks and
the aerobic digester.

      4. Make a DO test of the final effluent. Correct the  amount of air, if necessary.

      5. Check the chlorine residual in the plant effluent.  Correct the chlorine feed rate if necessary.

      6. Open and close all plant valves momentarily to be sure they are operating freely.

      7. Maintain the premises (rake, mow, etc.).


Monthly Checklist

      1. Check and observe the raw sewage flow rate through the plant.

      2. Make a settleable solids (Imhoff cone) test of the raw sewage entering the plant; record.

      3. Make an Imhoff cone test of the plant effluent from the chlorine contact chamber;
record.

      4. Collect a sample of the plant influent and a sample of the plant effluent for a BOD
analysis at an independent laboratory.

      5. Remove, inspect, and clean the inlet air filter screens for the air compressor units.

      6. Remove the belt guard from the sludge-collector drive; check belt tension; grease and
service shear pin coupling; and check vent plugs.

      7. Remove, clean, and check the surge relief valve(s) upon the discharge of each air
compressor.
                                            15

-------
Yearly Checklist

     1.   Clean, touch up, and paint all items requiring attention.

     2.   Inspect, flush, and clean bearings; lubricate and overhaul all items of equipment.

     3.   Proceed with any plant modernization or improvement that needs attention.

     Keep ahead of the waste-treatment plant. Attend it daily. Good housekeeping and maintenance
are a sign of good plant-operation. A dirty, unkempt plant is a poorly operated one. Ninety percent
of plant odors are caused from poor housekeeping.
                                            16

-------
                                        Chapter  III

CASE HISTORY-THE ORIGINAL  GOLD KIST WASTEWATER  FACILITIES
                                     SITE SELECTION
     In 1966, Giffels Associates was retained by the Gold Kist Poultry Processing people, then
 known as the Cotton Producers Association, to undertake a study of waste-treatment problems in
 connection with a proposed new plant to be built in Suwannee County, Fla. The location was predi-
 cated by the fact that the cooperative farm members were experiencing declining returns on
 tobacco farming and the Cotton Producers Association elected to bring new agricultural business
 into the area for the benefit of its farmer members.

     Poultry was considered the most logical choice since the firm wished to expand its poultry-
 processing facilities in any event and the area was suited to the rearing, hatching, and dispatching of
 a large quantity of broilers.

     The site finally selected was adjacent to the Suwannee River, which offered some degree of
 diluting water for the  treated industrial waste and also offered a sandy site, on which facilities could
 be readily built, located over a very adequate ground water supply to furnish the water for poultry
 processing.

     A site of 100 acres was selected for the project giving sufficient room for construction of the
 poultry-processing plant, the hatchery, and the required waste-treatment facilities, while providing a
 buffer zone between the plant and adjoining property owners. In addition, the proximity to the
 interstate highway system offered a ready means for shipment of dressed poultry and nearby rail
 access at the town of Live Oak assured adequate facilities for the receipt of grain and other feed
 materials.
                          WASTEWATER SURVEY AND CRITERIA
     The plant was designed originally to process 50,000 birds per day on one shift. It is currently
 being expanded to a two-shift operation with a capacity of up to 130,000 birds per day, which will
 be described later.

     The original wastewater-treatment system required facilities to treat poultry-processing wastes
 from 50,000 birds, processed over a period of 8 hours, plus wastewaters originating from a second-
 shift cleanup operation. In addition, all facilities had to be designed to accommodate future expan-
 sion up to, or exceeding, twice the then anticipated production rate. In addition to the normal
 poultry-processing wastes, the sanitary wastes from a plant population of about 225 persons and
 wastewater from the condensers on the feed meal cookers had to be included in the total waste-
 waters to be treated.
                                            17

-------
     An investigation was made at the existing Canton, Ga., poultry-processing operation operated
at that time by Gold Kist, and the wastes were examined with respect to what loads could be
expected in the new Florida facility. Flow quantities were measured at Canton and found to be
approximately 12 to 13 gallons per bird; however, operations at that time were considered lax with
respect to water conservation and it was decided that the flow from the new plant would probably
be about 10 gallons per bird. Subsequent operations proved this figure to be correct; however, dili-
gence is always required to maintain water use at that level, with water-consumption practices in the
plant being constantly monitored.

     An analysis of the wastewater being discharged at Canton indicated the following characteristics:

     • pH  ranged from 6.3 to 7.4.

     • Dissolved oxygen ranged from 0 to 2 ppm.

     • BOD ranged from 370 to 620 ppm.

     • Suspended solids ranged  from 120 to 296 ppm.

     • Settleable solids ranged from 15 to 20 ppm.

     • Grease content ranged from 170 to 230 ppm.

Average values for these parameters were:

     • pH,6.9

     • Dissolved oxygen, 0.5 ppm

     • BOD, 473 ppm

     • Suspended solids, 196 ppm

     • Total solids, 650 ppm

     • Volable solids, 486 ppm

     • Fixed solids, 164 ppm

     • Settleable solids, 17.5  ppm

     • Grease, 201 ppm

Since this total load was contained in approximately 20 percent more water than it was assumed
would be used at Live Oak, the figures were increased by one-third for design purposes because of
the expected higher concentration of contaminants in the wastewaters.

     In addition to the poultry-processing loads, about 200 gpm of water was to be run through the
jet condensers on the byproduct cookers. This water collected the grease and vapors from the feed
meal cooking operations and also had to be treated in the industrial waste-treatment facilities.

     When summarized, the daily load on the plant was expected to be, and later proved to be,
about 700,000 gallons per day with a BOD loading of about 2,620 pounds per day. It should be
                                            18

-------
recognized that this waste-treatment plant, therefore, was equivalent to a sewage plant for a town of
approximately 7,000 persons with respect to its hydraulic flow, and to a town of approximately
15,000 to 16,000 persons with respect to its biological load.

     Since the wastewater flow from the plant personnel was so small compared to the process
waste flow, it was completely ignored in the original design, with the only consideration being given
to proper disinfection of the effluent prior to discharge to the Suwannee River.

     Flow variations throughout the day were also measured at Canton with considerable variations
being measured, but a no-flow condition never existed, even during periods of no operations, such
as weekends. In other words, with the plant idle, some flow was experienced due to water consump-
tion that could not be shut off.

     It was determined that the minimum flow rate for the new wastewater stream would be
approximately 150 gpm with a maximum flow rate of about 730 gpm and an average flow rate of
about 490 gpm.

     An important consideration was the fact that a 20-mesh vibrating screen in the processing
plant ahead of the process sewer retained the bird entrails, offal, feathers, heads, flushings, and
other material, so that those byproducts were sent directly  to the feed meal recovery cookers and
the wastewater sent to the process sewer did not contain significant large solids and  was relatively
free of feathers.
                        SELECTION OF THE TREATMENT PROCESS
     Once the wastewater treatment criteria had been established, the decision had to be made as to
what type of waste-treatment process was suitable. The Florida State regulatory agencies said that
lagoons, if built in the area, would have to be fully lined because of earlier problems with ground
water contamination in the area. They would not accept anything except expensively lined lagoons.
Furthermore, the criteria that they set with respect to the discharge to the Suwannee River were
such that a complete lagoon treatment system would be taxed to achieve the desired results unless
the lagoons were made almost ridiculously large. Consideration was therefore given to using a
lagoon merely as a tertiary polishing device. The front end of the system and the primary and
secondary waste-treatment facilities would have to be biological-treatment facilities capable of
achieving pollutant reduction to a point where the subsequent tertiary pond would be minimum in
size and would also assure meeting the strict effluent requirements of the State of Florida. Those
requirements were not over 10 ppm BOD and zero settleable or suspended solids with rather strict
requirements with respect to turbidity and color.

     It cannot be overemphasized, as can be seen from these very strict requirements, that in con-
sidering any industrial waste-treatment process, working closely with State and regulatory agencies is
essential before any design work actually begins.

     Consideration was given to trickling filters and to various modifications of the activated-sludge
process. In the end, considering costs, reliability, and other matters, the extended aeration modifica-
tion  of the activated-sludge process was considered the only possible solution. While this process is
often frowned upon in large municipal work because of its high costs, it must be remembered that
in an industrial waste-treatment facility, the operating expenses are written off for tax purposes,
whereas capitalization costs cannot be.
                                            19

-------
     The extended aeration process, as it evolved, offered the following advantages: The initial
capitalization cost, although high, was not appreciably higher than the cost of other processes con-
sidered when sized to meet the strict effluent criteria. Again, although operating costs were higher,
due to the increased amount of compressed air required for the process, highly skilled operating
techniques are not always required to keep the system operating near peak efficiency. In other
words, exact lab control is not required.

     In addition, the usual 24-hour aeration period required for extended aeration processes was
not conducive to smoothing out the variations in flow and biological loading that were going to be
experienced in this waste-treatment facility. Furthermore, occasional overloads, either hydraulic or
biological, would not cause alarming reduction in waste-treatment efficiencies. The process itself,
when properly sized, is almost foolproof compared to what happens to overloaded trickling filters
in a conventional activated-sludge system with short detention periods. Certain waste-treatment
processes, when overloaded 10 percent, result in waste-treatment efficiency dropping off substan-
tially, maybe as much as 50 percent. A 10-percent overload on an extended aeration system would
cause little reduction in waste-treatment efficiency.

     As a further consideration, the  sludge resulting from this process, being thoroughly degraded,
is easy to dispose of on drying beds, is seldom inclined to cause odor problems, and  is small in
volume compared to what you might expect from a trickling filter or activated-sludge plant
designed and operated by conventional methods.
                                   THE FLOW DIAGRAM
     Accordingly, the system was set up somewhat conservatively consisting of an initial clarifier
and skimming device, which was used as a byproducts collector mechanism, followed by aeration
tanks, a final clarifier, and the tertiary pond. Sludge collected from the final clarifier was pumped
by an airlift and recirculated to the head of the extended aeration tank or to the parallel aerobic
digester. This digester is used for long-term aeration of grease and excess solids returned from the
final clarifier. This aerobic digester should offer the key to successful biological degradation of any
grease remaining from the poultry processing since it aerates its contents for a period of approxi-
mately 10 days prior to discharge  to the clarifier and thence to the final pond.

     Plant sanitary wastes were added downstream from the byproducts collector and were intro-
duced directly into the head end of the aeration tanks, thereby eliminating any possibility of human
wastes contaminating feed meal which is fed to the birds later.

     During subsequent expansion considerations this factor was felt not to be of significant
importance and secondary sludge  also was considered for reclaim.
                                  DESIGN CRITERIA USED
     The primary settling tank was originally sized by somewhat conventional means, with a surface
settling rate of 1,000 gallons per square foot per day being used as criteria for this work. For the
final design we reduced this rate to about 800 gallons per square foot per day by increasing the
byproducts collector size to 40 feet to permit slightly better grease and solids removal.
                                             20

-------
     The criteria for the extended aeration tanks were based on two factors. First, it was believed
necessary to maintain the conventionally accepted basis of 1,000 cubic feet of capacity per 20
pounds of applied BOD per day, and also it was believed necessary to maintain at least the 24-hour
minimum detention period normally used in extended aeration systems. As it turned out, the 24-
hour criterion governed and, in effect, turned out to be somewhat longer than 24 hours because the
hour flow was considered to be the process waste flow plus the recirculated sludge, which was
returned at 50 percent of the total flow rate to the plant. Normally, the 24-hour period is computed
using only the total wastewater flow  and it does not include the recirculated sludge. It was neces-
sary to begin, therefore, with a total of 36 hours of detention based on process flow only. This
period may be considered almost excessive by  some authorities; however, since we were dealing
with the problem of slow biological grease degradation and a need to achieve plus or minus  98 per-
cent of BOD removal, and since we were also looking to expand the plant some time in the  future,
it was felt that this was not an unreasonable criterion to use for the original plant design. Total
aeration-tank capacity, as determined by this method, was 140,000 cubic feet. It was elected to
split this required capacity into two tanks so that one could be operated with a responsible  degree
of treatment while the other was being maintained or cleaned.

     Compressed air was furnished to the tank on the basis of 15,000 cubic feet  of air per day, per
pound of applied BOD. The job was not unique in that the equipment selected for air diffusion
consisted of conventional swing-out diffusers used with air headers in Y walls between the tanks.
Since the tank was designed based on hydraulic loading rather than BOD loading, it actually turned
out that we had only 13 pounds of BOD applied per 1,000 cubic feet of tank capacity. Again, this
was quite conservative but, as it turned out, quite successful. As a general philosophy in the design
of industrial waste-treatment facilities, it is necessary to be conservative because  there is no assured
means of determining that process loads will not increase once successful production lines are put
into operation. This proved to be the  case at Gold Kist.

     Subsequent to the extended aeration tanks, a final clarifier was provided, which was also
designed somewhat conservatively, although not to the extent used on the aeration tanks because of
the lack of a polishing pond to follow this unit. The final clarifier was designed on the basis of a
surface settling rate of 730 gallons per square foot per day and a weir overflow rate of 360 gallons
per foot per day. Sludge collected by the final  clarifier, which was equipped with a skimming arm as
well as scraping mechanism, was returned by an airlift to the head of the system.

     This minimized maintenance and operation problems because at this point the only motors
needed for the system were those on the blowers and the drive mechanisms for the byproducts
collector and final clarifiers. Additional sludge pumps were not required.

     Again, when it came down to the final design this tank diameter was increased slightly so these
criteria were even less. There was a constant effort to create a system that could  be somewhat over-
loaded without causing a significant reduction  in waste-treatment efficiency.

     It was strongly suspected that it might be possible to process up to 10,000 birds per hour on
occasion which indicated that a one-shift operation could run as high as 70,000 to 80,000 birds per
shift if the processing plant were run at a maximum rate. This actually did happen with production
rates approaching 10,000 birds per hour and the single-shift operation extending  to 9 or 10  hours
per day.

     The aerobic digester, which was provided  adjacent to the aeration tank, had a volume of
46,500 cubic  feet. Air was supplied in exactly the same fashion as to the aeration tanks on the basis
of 20 cubic feet per minute of air per 1,000 feet of digester capacity. A supernatant decant  well was
provided as the end of the digester with clarified liquor rising slowly and very quiescently since the
overflow rate can be controlled by the operator based on the amount of sludge he returns to the
                                           21

-------
aerobic digester, with the remaining amount of return sludge being sent to the aeration tanks. This
supernatant decant well was actually nothing but a timber baffle with a hopper bottom built into
the end of the aerobic digester.

     Sludge from the aerobic digester was directed to the sludge-drying beds by the simple means of
a fire hose, using the head on the aerobic digester to force the sludge to the drying beds. As a
general rule of thumb, the amount of solids generated by the extended aeration system is about
one-half pound  per day per pound of BOD treated in the tanks.

     The sludge-drying beds were perhaps the weak spot in the system. Although north Florida seems
to be entirely made up of deep sand beds, somehow, unwittingly, the only spot of clay in Suwannee
County was picked on which to build the drying beds. Therefore, although subdrainage systems
were provided to dry the sludge, it did not dry as readily as hoped for.  Further complications were
involved in the fact that, at least initially, the outlet from the underdrains in the sludge-drying beds
was completely filled over by some incidental grading operations done  by a contractor. The old
rule—if anything can go wrong on a project it will—seemed to apply here.

     Even though difficulties were experienced with the sludge-drying beds, it was not serious
because the nature of the sludge produced by this waste-treatment process is such that it is inoffen-
sive, dries readily, and in a pinch can just be  spread out on the ground. It is not troublesome  with
respect to odors, and can always be scraped up and hauled away from almost anyplace to store it
temporarily, as  long as it is allowed to dry. The warm Florida weather helped in this matter.

     Sealing the final tertiary pond subsequent to the clarifier was accomplished rather inexpensive-
ly. Asphalt liners, rubber linings, and other membranes were considered and the cost always proved
to be somewhat shocking so the designers ended up with a rather simple system. A thin layer of
Visqueen was placed over the entire bottom  of the lagoon in  small overlapping sections and trucks
full of  sand dumped directly on the Visqueen.  The sand was spread by  hand, making a 1-foot layer
of earth and sand on top of the Visqueen to  protect it.  The system may not have been 100 percent
watertight but the designers were pleased to  note that before any water was added by the waste-
treatment process to the lagoon, it did collect and store rainwater and was ready to go at the time
the poultry-processing facility went onstream.

     The inlet to the square 4-acre pond  was located in its geometric center. This was done so that
any inadvertent solids carryover from the final clarifier would settle out in the central  area of the
pond and if there were an odor problem resulting from this, it would be at least 200 feet from any
point on the shore. The best way to control  an odor is to keep it as far away from people's noses as
possible.

     Effluent from the pond was subjected to 20 minutes of  detention in a chlorination pond. A
chlorinator was provided capable of handling from 20 to 100 pounds of gaseous chlorine per day.
The expected required rate was approximately 42 pounds per day which  left a 0.5-ppm residual in
the effluent.

     New developments in chlorination of effluent by means of electrolytic cells generating sodium
hypochloride have come  into use since that time and in retrospect it would appear wise to install
such a  system in a facility such as this to  eliminate the hazards involved in using gaseous chlorine.

     The air compressor facility for the initial waste-treatment plant consisted of three, 3,000-cubic
feet-per-minute per Spencer turbocompressors, each with a 75-hp motor delivering air  against 96
ounces of pressure (fig. 11). Actually, two compressors were  required to run full time to furnish air
to the aeration tanks and  airlift. The third compressor was merely a standby.
                                           22

-------
     In summary, the wastewater-treatment plant components consisted of the following devices,
which are detailed in figure 12.

     • The system used a byproducts collector tank (fig. 13), a conventional circular settling tank
       with motor-driven sludge collection and skimming mechanisms, 40 feet in diameter with a
       7-foot side water depth and a detention time of approximately one and one-half.

     • Extended aeration tanks (fig. 14) consisted of two concrete tanks each 170 feet long and 26
       feet wide with a water depth of 15 feet and a freeboard of 2 feet. Each tank contained 95
       air diffusers and piping to supply 150 cubic feet per minute of air to the mixed liquor. A
       valve port between the two tanks permitted equalizing loading on each tank if required. The
       detention time was 24 hours based on process flow plus a 50-percent allowance for sludge
       recirculation.

     • The aerobic digester was constructed next to the aeration tanks; therefore, it had an equal
       length of 170 feet but it was only 21 feet wide, again with a water depth of 15 feet. The
       supernatant decant well at the end of the tank, which was used to contain the solids in the
       tank, had a surface settling rate of less than 800 gallons per square foot per day and an over-
       flow rate of 240 gallons per minute to the clarifier.

     • The final settling tank was again a conventional collection mechanism with a motor-driven
       scraper and skimming mechanism. It was made 44 feet in  diameter with an 8-foot side water
       depth and a 9-foot center depth. Detention time in this tank was about 2 hours, which is the
       maximum that could probably be used without running into septicity problems in the
       stored sludge.

     • The final stabilization pond or tertiary device was 4 acres  in size and had a detention time of
       approximately 10 days. The depth was 5 feet, which is about the maximum that can be used
       in an aerobic pond, simply because depths in excess of 5 feet tend to become septic  at the
       bottom due to lack of sunlight and poor oxygen transfer.

     • The chlorination facility was simply  a small building with  a wall-mounted chlorinator,
       scales, and ancillary devices. It was placed at the far end of the ponds, convenient to the
       chlorine detention pond.

     • The air facility used three Spencer turbocompressors rather than positive displacement
       rotary compressors for the simple reason that they were believed less expensive and more
       reliable, and certainly less noisy. Judgment has proved this fact, and turbocompressors, as
       opposed  to positive displacement air compressor devices, have been made standard waste-
       treatment equipment wherever possible. Their one drawback is that the pressure they can
       develop is somewhat limited and they cannot be discharged into  really deep aeration tanks.
       About the best that can be done is to operate with about  13 feet of water pressure and the
       aeration diffuser devices.
                            FUTURE EXPANSION PROVISIONS
     The entire facility was arranged to permit future expansion if necessary, and piping was valved
and placed so that another byproduct collection tank could be added if needed. Another final
settling tank also could be added, if required, as well as more air compressors. All of this was done
for the expansion that took place in 1970.
                                           23

-------
     In addition, there was space onsite to double the stabilization pond and add additional chlori-
nation detention ponds if necessary. It cannot be overemphasized that one must have a site that
is big enough for the waste-treatment facilities and 100 percent of expansion if necessary. It was
possible to accomplish 100 percent of expansion without doubling up on these facilities, as will be
discussed later. At the time, however, doubling of the facilities seemed to be the practical way to
handle the problem.

     No expansion provisions were provided in the original aeration-tank installation since, in
effect, it had been overdesigned and it was felt that in a pinch a conventional activated-sludge opera-
tion could be adopted, which would require less tank volume but more sophisticated control. In
such a case, only 6  or 8 hours of aeration time would be necessary.

     The facility was originally designed to achieve BOD reduction in the following fashion. Of the
2,600 pounds of BOD applied per day, 780 pounds would be removed in the byproducts collec-
tor—30 percent of the applied load. This is a conventional criterion for devices of this type. It was
expected that the subsequent extended-aeration tanks would be able to remove 90 percent of the
remaining 1,820 pounds of applied BOD. Again, this seems to have been a reasonable assumption
since 90-percent removal using long-term aeration is quite feasible.

     The stabilization pond also was capable of removing another 200 pounds of BOD per day. The
rate of 50 pounds per acre per day is allowed in the State of Florida. As one goes farther north colder
temperatures inhibit biological actions in lagoons; therefore, in the Northern States 20 to 30 pounds
of BOD loading per acre per day is all that is allowed.

     This consulting firm  has encountered instances on other Florida jobs where it has been proven
to have removed as much  as 100 pounds of BOD per acre per day, which indicates the State cri-
terion is probably somewhat conservative.

     Totaling up the removal of BOD in all components, it was possible to indicate, in theory at
least, that 100 percent of BOD would be removed. Although it was known that this was impossible,
97 to 98 percent BOD removal was expected, which is very good efficiency. After the plant went
into operation these results were achieved and perhaps even a little better, which justified the selec-
tion of the process  and the conservative design approach.
                           WASTE-TREATMENT SYSTEM COSTS
     The total cost of the wastewater-treatment facility built in 1967 was estimated to be
$252,000. It may have cost somewhat more, however, since the construction costs for the waste-
treatment facilities were lumped in with the construction costs for the onsite hatchery and poultry-
processing plant. The exact cost could not be determined, but in any event, the cost was less than
$300,000.

     Amortizing the costs over a 10-year life expectancy of the facilities, it was found that the orig-
inal investment of $252,000, plus an allowance for interest on that investment, made the total cost
of the facility $327,000. Based on processing 250,000 birds per week at a dressed-out weight of 2*6
pounds per bird, it turned out that the capitalization cost for waste treatment for this plant was
approximately one-tenth of a cent per pound of finished dressed poultry.

     Operating costs were estimated to be approximately 7 man-hours per week of labor, 7 days of
power for the two blowers running continuously, and 7 days' worth of chlorine which was estimated
                                           24

-------
to cost about $6 per day. Total weekly operating costs came out to be about $370, which indicated
an operating cost of about 0.06 cent per pound of finished product. Therefore, the total waste-
treatment costs per pound of dressed poultry appeared to be in the neighborhood of 162 mils per
pound of finished dressed poultry.
                              OPERATING ARRANGEMENTS
     In addition to an adequate design for wastewater-treatment facilities, another important
matter must be mentioned. The true success of any waste-treatment operation is based as much on
operating skill as on the design and capacity of the system. As engineers responsible for the design
of this system, the consultants were most fortunate to have an owner who elected to go out and
hire a skilled, competent man to run these facilities. He was also assigned the job of running the
byproduct reclaim system and cookers. He was assigned a job in which if he reclaimed his byprod-
ucts effectively, his wastewater loads were less and he was, therefore, in complete control of his
own destiny. If he messed up on one job, he would not be able to straighten it out  on the other.

     A licensed certified wastewater treatment plant operator in the State of Florida, Mr. Ronald
Lanier, was hired to operate these facilities and their success is due to, in a great part, to his careful
attention to facilities operations.

     To help him in his job, an operating manual was prepared which  described the plant, its flow
stream and theory, its initial startup procedures, and its normal operating procedures. It also con-
tained a checklist for maintenance and a checklist for equipment operation. The importance of an
operating manual prepared by the design engineer cannot be minimized.

     Before describing the waste-treatment plant modifications now being made to accommodate
increased poultry processing, figures 11 and 13-21 have been  included to illustrate the components
in detail.
                                           25

-------
                                     Chapter  IV

         CASE  HISTORY-CURRENT EXPANSION  AT  GOLD  KIST
                                   PROJECT HISTORY
     The original facility was designed to treat waste waters resulting from the processing of 50,000
birds per day plus a nearly insignificant sanitary wastewater flow from the plant personnel facilities.
The rationale by which hydraulic, biological, and solids loadings were determined has been described
previously.

     Also described are the basic criteria used for determining facility component sizes and the pro-
visions for future expansion as foreseen at that time. During final design, however, the sedimenta-
tion  facilities were increased in size.

     This somewhat arbitrary increase in the size of the byproducts-collector tank (primary settling)
to 40 feet in diameter and the final clarifier (secondary settling) to 44 feet in diameter is the princi-
pal reason, along with a conservative original design, why the system has continued to function well
under recent substantial overloads. For these same reasons, the modifications now required are
minimal.
                            CURRENT WASTEWATER LOADS
     Once poultry-processing startup difficulties had been overcome, it was economically practical
to increase hourly production rates and the one-shift processing time to 9 or 10 hours. This resulted
in daily processing rates of 72,000 to 80,000 birds and measured hydraulic loads of about 1 mgd.
This roughly 50-percent increase in production caused flow rates ranging from 1.7 mgd to 0.4 mgd
on processing days. During weekends (supposedly no-flow conditions) 0.2-mgd flows were recorded
(see figs. 22-24).

     Original flows were expected to be 10 gallons per bird (processing and cleanup) plus 4 gallons
per bird for byproducts cooker-condenser cooling waters, for a total flow of 700,000 gallons per
day.

     Actual measured wastewater flows have averaged 13 gallons per bird and totaled over 1 million
gallons per day.

     In addition, laboratory tests showed the properties of the wastewaters to be  above average
during processing hours (see table 3).
                                          27

-------
                                  Table 3.—Wastewater properties

Item
Total solids 	
Suspended solids 	
BOD 	

Original
assumptions,
ppm
650
200
470

Measured
properties,
ppm1
910
300
420

                        A large part of the increase in solids is due to the fact that the byproducts-
                  collector sludge has often contained too much water for consistently economical
                  reclaim. When pumped back over the byproducts reclaim screens in the processing
                  plant, many fine solids pass through back into the process waste sewer.
                           CURRENT OPERATING DIFFICULTIES


     As the loading on the wastewater treatment passed the design criteria, problems arose in the
operation of the facility. These problems were met as they arose by Mr. Ronald Lanier, the certified
wastewater plant operator hired by the owner. By skillful operation of the facility, consistent
results were obtained. The proposed revisions include measures to correct system deficiencies now
apparent and include a new package laboratory permitting the operator to exercise better control.


Condenser-Cooling Water

     While an allowance of 0.2 mgd was made in the original design for use of process water to con-
dense feed meal cooker vapors, even more water has been required. Problems were encountered
from the very beginning with feathers in the process waste stream clogging the condenser-cooling
water pumps. Although it was  originally intended that the recirculation well be located downstream
of the secondary sedimentation device (clarifier), as shown in figure 11, it was installed between the
roughing screens and the byproducts recovery tank (primary settling). This decision was based on
terrain and plant configuration and in hindsight  was unwise.

     Although ample process wastewater was available during processing hours to meet the antici-
pated 140-gpm demand of the  feed meal cooker condensers, the demand proved even higher and the
ensuing difficulties precluded the use of any process wastewater. In addition, the low-process
waste-discharge flows during cleanup and no-processing hours caused the wastewater stream to heat
up to an unacceptable temperature (120° F plus) even when condenser-cooker water pumps were
operable. At these temperatures, successful condensing of the odorous cooker vapors was incomplete.

     As a result, it was necessary to connect an additional unmetered process waterline into the
cooker vapor condensers with a nearly 24-hour constant water flow and resulting discharge to the
process sewer. This flow is believed to be almost entirely responsible for the increases in flow above
the metered process water consumptions of 10 gallons per bird. In other words, about a 0.30-mgd
increase (3Vz gallons per bird) in process wastewater flow above that expected (10 gallons per bird)
has occurred due to this processing complication. When added to the average daily metered process-
water consumptions of 740,000 gallons per day (processing and cleanup for approximately 75,000
birds per day), the approximate 1-mgd flow which was measured was confirmed.
                                            28

-------
     During late May 1970, condenser water pumps were successfully relocated from their original
location to the process waste sump in the waste-treatment facility. Several days of clog-free opera-
tion were then possible. During these periods, metered process water demands dropped by 0.1 mgd
to 640,000 gallons per day, or only an average of 8V2 gallons per bird.

     Such examples prove that a wastewater estimate of 10-gallons per bird processed is ample pro-
viding all byproduct cooker-condenser cooling water can be taken from the process wastewater
stream. The successful  operation of the wastewater-treatment facilities under the proposed two-
shift, 115,000-bird load is predicated on this assumption and will be discussed further herein.


Hydraulic Overflows

     At times of peak processing, slight overflows have spilled onto the ground from the aeration
tank effluent troughs, and aeration-tank weirs have flooded out.

     The original anticipated design flow rate between the aeration tanks and final clarifier was 0.7
mgd (490 gpm), plus 50 percent (peak flow allowance), plus 0.5 mgd (350 gpm) sludge recircula-
tion, or approximately 1.55 mgd (980 gpm).

     A system head curve for the gravity flow line (C = 100) between the aeration tanks and the
final clarifier revealed only 1.2 feet of the elevation differential required. Effluent trough overflow
was considered, at that time  (original design), to be unlikely.

     However, recent peak flow rates of nearly 1.7 mgd plus sludge recirculation have caused a flow
rate of over 2 mgd in the aeration-tank discharge line. At this flow, about 2.5 feet of elevation
differential is required. Since the design provided for 3.5 feet of elevation between the aeration-tank
water surface and the final clarifier water surface, recent overflows seemed unexplainable.

     Recent checking of "as built" elevations, however, reveal only about a 2.5-foot difference in
elevation; apparently a construction error was made. Later discussion contained herein will describe
the corrective work required.


Solids Control

     The plant operator has been plagued by problems relating to solids control. Not only has he
had difficulty with maintaining optimum MLSS (mixed-liquor suspended solids) ratios, but also
with removing sludge from the aerobic digester to the sludge-drying beds. These problems have
generally been caused by the following complications:

     • Uncanny intuition on the part of the designers placed the sludge-drying beds in the only
       pocket of clay in an otherwise all sand site. This resulted in poor performance.

     • Earth spoil from construction done subsequent to startup was placed in the only available
       low spot on the site.  Unfortunately, this also buried the outlet e»d of the sludge bed sub-
       drainage system.

     • The sludge drawoff pipe from the aerobic digester was placed on the wrong side of the
       decant baffle. Instead of being able to draw a concentrated liquor from the quiescent side  of
       the baffle in a steady stream, it was necessary  to shut off the digester air supply and draw
       only whatever sludge settled in the vicinity of the outlet pipe. Time for this was limited due
       to a rapid decrease in the digester content dissolved oxygen residuals.
                                            29

-------
Proposals for correction of these deficiencies follow herein.


Odor Problems

    During weekend periods of low or near zero flows, oxygen levels in the byproducts collector
(primary settling tank) and lift station sumps often disappear and septicity, with its resulting odors,
occurs. Proposed revisions (described later) have corrected these conditions.

    In addition, frequent power outages (three to four times a year) have presented problems with
the air compressors which require a manual restart sequence. Aeration-tank contents have become
offensive by Monday morning when such outages occur on Friday night or Saturday. System
improvements have provided for automatic air compressor restart.
                 PROPOSED WASTE WATER-TREATMENT SYSTEM LOADS
Hydraulic Loads

     Actual process water flows recently measured during processing periods have ranged from
51,000 to 40,000 gallons per hour. Therefore, during these times we have had an average flow rate
(metered process water) of about 45,500 gallons per hour or a 1.1-mgd rate. The average bird-proc-
essing rate during these times has been 9,400 birds per hour; so processing seems to require an
average of 5 gallons per bird.

     Assuming the  actual use to be 6 gallons per bird for the sake of conservative design, and based
on occasionally reached processing rates of 10,000 birds per hour, the  maximum process waste-
water-flow rates expected may reach 10,000 birds X 6 gallons per bird -=- 60 = 1,000 gpm, or about a
1.4-mgd rate.

     Recently measured cleanup water consumptions have ranged from 239,000 to 294 gallons per
day, or an average of 266,000 gallons per day. The average daily number of birds processed during
this time has been 76,000 birds per day with a range of from 72,000 to 80,000 birds per day. This
indicates cleanup water demands of about 3.5 gallons per bird. This  flow generally occurs in the 6
hours following the end of the poultry-processing work, the initial flow roughly equaling the
process flow, and gradually decreasing thereafter to supposedly near zero  flow about 6 hours later.
Hence, the average  flow during the 6-hour cleanup period is about 500 gpm, or about a 0.7-mgd
rate.

     Data gathered indicate minimum weekend flows of about a 0.2-mgd  (140 gpm) rate. This is
presumed to be a completely shutdown flow rate and is due to sanitary flows, infiltrations, and
other miscellaneous water consumption that cannot be reduced further. These data plus the un-
metered cooker-condenser flow estimate have been used to produce the hourly flow rates shown in
figure 22. Figures 23 and 24 indicate expected average and maximum daily flows expected from the
increased poultry processing. These future hourly flow rates and total daily flows are based on the
following premises:

     • The processing of 115,000 birds per day in 16 hours will result in  an average production rate
       of 7,200 birds per hour. This rate is somewhat lower than at present when an average of
       75,000 birds are processed in 8 hours (9,400 birds per hour).
                                            30

-------
     • Peak hourly processing rates of 10,000 birds per hour will again be possible and will occur
       on days when production reaches the proposed maximum of 130,000 birds per day; peak
       flow rates of 1,000 gpm of process waste water will be generated at such times.

     • Process water demands will not exceed 6 gallons per bird and cleanup demands will not
       exceed 4 gallons per bird. This rate seems readily obtained based on present operating
       experience.

     • Wastewater flows will be minimized by discontinuing the use of unmetered process water
       for byproducts cooker vapor condensing. All condenser water demands will be met by using
       untreated process waste supplemented when required by recirculation of byproducts
       collector-tank (primary settling) contents and aeration-tank contents. At these times, those
       waste-treatment system components will be, in effect, heat exchanger devices. Anticipated
       maximum water temperatures in those components will not exceed 120° F and should not,
       therefore, be detrimental to biological processes.

     It was demonstrated by figures 22 through 24 that although total wastewater flows will
increase by 5 to 12 percent, peak flow rates will actually be  reduced by 16 percent.


Biological Loads

     The original design anticipated a BOD load of 2,600 pounds per day while processing 50,000
birds per day, or 0.052  pound of BOD per bird.

     If cooker-condenser water recirculation had been continuously practiced instead of using fresh
unmetered water, this BOD load should have been contained in 50,000 gallons  (4,170,000 pounds)
of water per day, which would then have had an average BOD concentration of 624 ppm.  With addi-
tional water for cooker  vapor condensation, the flow was estimated to be 700,000 gallons per day.
At this time, the average BOD concentration in the raw waste would have been 446 ppm.

     Laboratory tests made on wastewater flows found an average influent BOD of 350 ppm and
397 ppm. These tests indicate that the originally anticipated BOD assumptions  were quite adequate.

     Influent grab samples  during processing hours (Apr. 22, 1969) had a peak  influent BOD of 550
ppm. This increased to 650 ppm during those hours when wastage of byproducts collector sludge
through byproducts area screens was practiced instead of being sent to the cookers for reclaim.
These figures are similar to those BOD concentrations assumed during the original  design work.

     The monthly operating reports for the year 1966 indicate gradually increasing loads on the
waste-treatment facilities as production increased. Near the end of 1969, it became necessary to run
the third standby blower continuously to satisfy oxygen  demands.
                          REVIEW OF COMPONENT ADEQUACY
Lift Station

     The existing lift station contains three separate sumps, e.g., process water, sanitary sewage, and
byproducts. Although total flows are expected to increase slightly, maximum flow rates should
decrease so that no changes are required in this facility. However, to insure an ample cooker vapor
                                           31

-------
condenser cooling water supply, a new 1,000-gpm nonclog pump will be installed where space was
reserved for the future third-process waste pump. The discharge for this pump will run by means of
a new 6-inch force main back to the byproducts area.


Byproducts Collector

     Under present conditions this 40-foot-diameter tank has an average surface settling rate of 765
gallons per square foot per day and an average weir loading rate of 7,650 gallons per foot per day.
Short-term peak flow rates have probably reached twice these values.

     With the increased production on a two-shift basis, the average surface settling rate is expected
to increase to 805 gallons per square foot per day, and the average weir loading rate to 8,050 gallons
per foot per day. Since peak flow rates will be reduced by about 200 gpm, and since this facility has
averaged a 39-percent reduction in BOD, it is believed the increased loads can be handled without
modifications. The BOD removal rate is undoubtedly enhanced by the  substantial grease removal in
this tank.
Aeration Tanks

     The extended aeration process utilized in these tanks has been very successful in meeting the
present system overloads. With an assumed average BOD influent concentration of 450 ppm, a 35-
percent reduction of BOD in the byproducts collector, and a 0.93-mgd flow, the present loading on
the aeration tank is probably 2,260 pounds of BOD per day, more or less. The present detention
time in the aeration tank is 27 hours (2 X 525,000 gallons ^ 930,000 gallons per day = 1.13 days).
With the standby blower presently on at all times, the air supply to the tanks has been increased by
about 50 percent over the original design, and it is now about 1,425 cfm to each tank, or a total of
2,850 cfm.

     Based on these figures, current aeration-tank operating data are illustrated in table 4.

     Proposed modifications to the aeration tanks will consist of approximately  doubling the
number of Walker Process Sparjers on each header and increasing the air supply to 1,900 cfm of air
to each aeration tank.

     With 100-percent condenser cooling using process waste and at peak processing rates (130,000
birds per day), and once again assuming 0.052 pound of BOD per bird, tank data are developed as
shown in table 5. (This is again predicated on 35 percent of BOD removal in the  byproducts
collector.)
                               Table 4.—Aeration-tank operation data
             Applied BOD per day  	
             Daily flow	
             Detention time	
             Tank volume per pound of applied
               BOD per day 	
             Air supply per pound of applied
               BOD per day	
             Air supply per 1,000 cubic feet of
               tank capacity	
2,260 pounds
0.93 mgd
27 hours

62 cubic feet or 16.2 pounds of BOD

1,830 cubic feet

20 cfm
                                           32

-------
                                    Table 5.—Aeration-tank data
             Applied BOD per day  	
             Daily flow	
             Detention time	
             Tank volume per pound of applied
               BOD per day  	
             Air supply per pound of applied
               BOD per day  	
             Air supply per 1,000 cubic feet of
               tank capacity	
4,400 pounds
1.04 mgd
24 hours

32 cubic feet or 31.5 pounds of BOD
  per 1,000 cubic feet of tank capacity

1,250 cubic feet

27cfm
     If this were a conventional activated-sludge application, certain of the preceding data would
tend to indicate that the aeration system had been pushed to a practical limit; however, the long
detention time and ample air supply should assure continued operation as an extended aeration
system. Under these conditions, however, the settling properties of the sludge in the final clarifier
should be improved (less light, endogenous cellular material). But waste-sludge volumes may
increase by several times over what has been encountered up to this time. Improved sludge-wastage
facilities are described later herein.
Final Clarifier

     The performance of this unit will probably actually improve under the additional loading.
Settlmg properties of the sludge contained in the mixed liquor received from the aeration tanks
should be improved and the 24-hour aeration period almost precludes sludge bulking under normal
operation. This 44-foot-diameter unit is currently operating with an average surface settling rate of
612 gallons per square foot per day, and a weir loading rate of 680 gallons per foot per day. These
will increase to 645 and 710, respectively, but again, as in the case of the byproducts collector, peak
flow rates will be less.

     The return sludge airlift that forms a part of this component was originally designed to return
over 350 gpm of sludge to the head end of the aeration tanks and/or aerobic digester.  This
amounted to 70 percent of the anticipated average hydraulic load (700,000 gallons per day = 490
gpm). Under present conditions (0.93 mgd), it is returning sludge at a rate of plus or minus 50 per-
cent of the total flow through the facility. Since the new average hydraulic load is only slightly
greater, the airlift should still be adequate.


Aerobic Digester

     The aerobic  digester, as originally designed, was sized on the basis of 4.5 cubic feet per capita
based on an average of the hydraulic and biological population equivalents. A research of the litera-
ture at that time did not disclose much precedent for sludge designs. The resulting capacity of
46,500 cubic feet was supplied with 20 cfm of air per 1,000 feet of capacity to assure adequate
mixing and dissolved oxygen residuals. The decant well surface area (256 square feet)  was consid-
ered capable of retaining all solids in the system if sludge were wasted to the digester at a rate not
in excess of 10,000 gallons per day (375 gallons per square  foot per day). Actually, required sludge
wastage flow rates were considered as probably being considerably less.
                                             33

-------
     Furthermore, recent research on this matter had disclosed that the extended aeration system
generates about 0.5 pound of solids for every pound of applied BOD. These data are developed and
set forth in the paper "Design Criteria for Extended Aeration" by John T. Pfeffer, Assistant Profes-
sor of Civil Engineering, University of Kansas (published in the Transactions of the 13th Annual
Conference on Sanitary Engineering, at that university).

     With the future applied load of 4,400 pounds of BOD per day on the aeration facilities, about
2,200 pounds per day of solids may be generated. If these were contained in a sludge having a water
content of 99.8 percent, about 1.1 million pounds or 132,000 gallons per day would have to be
wasted to the aerobic digester. Under these flow conditions (92 gpm), the surface settling rate on
the decant well of the aerobic digester would be only 515 gallons per square foot per day; the weir
loading rate would be 8,200 gallons per foot per day; and the digester detention time would be
approximately 3 days. With a regular daily sludge drawoff, the aerobic digester is still believed to be
quite adequate.


Sludge-Drying Beds

     The original sludge-drying beds provided had a total area of approximately 20,000 square feet.
On the basis of the original biological population equivalent, this area amounted to 1.33 square feet
per capita.

     Although the plant has been operating under a plus or minus 50-percent overload condition,
the area has still  proved ample; however, the method by which digester sludge is conveyed to the
beds has been less than satisfactory.

     The fact that the sludge is the end product of an extended aeration process and has been
further subjected to several days of additional aerobic digestion has resulted in small quantities of a
readily dried product with no offensive odors.

     One additional 10,000-square-foot drying  bed with underdrains will be constructed, and the
existing beds and underdrainage system improved to provide more capacity and eliminate previously
discussed operating problems.


Stabilization Pond

     The stabilization or polishing pond has an area of 193,000 square  feet, or 4.4 acres. A high
dissolved oxygen content in the pond has enabled bass and bream to flourish and the pond has been
the site of company fishing contests. When power failures have occurred and septic conditions have
arisen in the aeration tanks, the pond has prevented such conditions from reaching the Suwannee
River until the treatment processes were again in order.

     Although, at this time, no change is contemplated in the pond, aeration may have to be added
to the pond if the increased wastewater load caused anaerobic conditions to develop. This could be
accomplished by means of submerged perforated polyethylene air headers or floating surface
aerators placed near the central inlet.


Outfall Sewer and CI2 Facilities

     Since total  flows are only expected to increase by 9-12 percent and peak flows will actually be
reduced, the existing facilities should still be adequate.
                                            34

-------
                               PROPOSED MODIFICATIONS
Air Supply

     The number of aeration sparjers in the aeration tanks will be approximately doubled. To
furnish the additional air required, two more 75-hp Spencer turbocompressors will be added. During
operations, four will be running and one will be kept as a standby. The motor control center near
the lift station was originally designed to accommodate two more future blowers, so only power
connections from the motor control center to the blower motors are needed. The motor control
center will also have a "Motor Minder" added to it, which will provide automatic sequential blower
restarts in the event of a power failure. This device will also protect the 75-hp motors against low
voltage and single phasing.


Plant Hydraulics

     Although peak flow rates will be reduced, the possibility of aeration-tank effluent trough over-
flows may still exist. A new head box and an increase in the aeration-tank discharge line size to 18
inches from 14 inches should prevent any further problem.


Byproducts Reclaim System

     The original system consisted of a collection sump in the facility lift station and a pump which
returned the sludge and grease collected by the primary-settling (byproducts) tank to the cookers in
the plant. Considerable sand and grit in the sludge caused clogging in the return line, which was
sized for future flows but in which present velocities failed to keep the grit and sand in suspension.
In addition, the byproducts reclaimed often contained too much water for economical recovery.
Some system improvements follow.

     • Replace the present byproducts pump with a 200-gpm, 35-foot head-float-actuated nonclog
       centrifugal  pump. This will return byproducts to the cookers with sufficient velocity to
       prevent clogging  of the return line.

     • Install a secondary grease tank in the byproducts area of the plant. This tank will receive
       grease from the byproducts tank skimmer box. This tank will permit reutilization of the
       Moyno pump to  draw grease from the bottom of the tank and discharge to a separate grease
       cooker for  separate rendering.

     • As an alternative to this scheme, possible use of a centrifuge  to thicken the sludge (20
       percent solids) before discharge to the cookers is being considered. If it proves practical to
       reclaim secondary as well as primary sludge, this alternative will appear to be more
       attractive.
Sludge-Drying Facilities

     A modification to the sludge-withdrawal system in the decant well of the aerobic digester is
required. An adjustable sludge drawoff pipe should permit the operator to withdraw sludge from
that level in the decant well which contains the thickest sludge.
                                           35

-------
     A new 100-gpm sludge drawoff pump on brackets secured to the side of the aerobic digester
will discharge to either one of the existing drying beds or to the new third sludge-drying bed. As an
alternative, the discharge can be sent to the byproducts sump. Should the secondary sludge be
amenable for reuse as poultry food, there will be no need for sludge-drying beds. Since secondary
sludge is low in protein compared to primary sludge, its reclaim value is not yet proven.


Condenser Cooling Water

     The success of the waste-treatment facility operation under the increased loading anticipated is
dependent on 100-percent reuse of process wastewater for byproduct cooker vapor condenser cool-
ing. To assure an ample water supply, an 800- to 1,000-gpm, 50-psi, 75-hp pump will be installed in
the facility lift station. Taking its suction from the process sump, it will discharge back through a
new force main to the byproducts cooker vapor condensers.

     During periods of low process waste flow, the drain valves from the aeration tanks and aerobic
digesters will be opened sufficiently to maintain an adequate water supply to the condenser cool-
ing water pump. This will, in effect, convert the primary settling tank (byproducts collector) and
aeration tanks to heat exchangers. Since some process waste (200-gpm minimum) always flows, it is
felt that the over 1 million gallons of aerated mixed liquor in the aeration tanks will not become
heated to a point detrimental to biological processes. Calculations indicate cooling water tempera-
tures will remain below 120° F for successful cooker vapor condensation and such temperatures are
not expected to injure biological process.


Grease Removal

     Byproducts handling is, on occasion, hampered by excessive grease in the reclaimed feed meal
(conveyor fouling, clogging, etc.). At the option of the poultry processor, a grease-receiving tank
will be installed next to the byproducts collector. Scum and grease from this tank will be collected
separately and pumped to a separate cooker.
                                            36

-------
          PRIMARY
          TREATMENT
                                                CLARIFIER
         WASTE
  AERATION
  6-8 HOURS
  DETENTION
                  RETURN SLUDGE
                    Figure 1. Conventional activated-sludge process.
          PRIMARY
          TREATMENT
                      CLARIFIER
          WASTE
                             AERATION
                             2-3 HOURS
                             DETENTION
                   RETURN SLUDGE
                      Figure 2. High-rate activated-sludge process.
          PRIMARY
          TREATMENT
         WASTE
                      CLARIFIER
                            AERATION
                            24-30 HOURS
                            DETENTION
                   RETURN SLUDGE
                        Figure 3.  Extended-aeration process.
WASTE
    WASTE
AERATION
30 MINUTES
DETENTION
                                             CLARIFIER
    SLUDGE STABILIZER
    AERATION
    2 HOURS DETENTION
RETURN
SLUDGE
                       Figure 4. Contact-stabilization process.
                                    37

-------
          PRIMARY
          TREATMENT
                CLARIFIERS
 WASTE
FILTERS
                                                    HUMUS
                          Figure 5. Standard-rate trickling filters.
WASTE
                 PRIMARY
                 TREATMENT
         CLARIFIER
CLARIFIER
                        TWO STAGE, HIGH RATE
                            Figure 6.  High-rate trickling filters.
  WASTE
  WASTE
  WASTE
  WASTE
                           Figure 7. Lagoon-system schematics.
                                         38

-------
      ANAEROBIC

        LAGOON
         EXISTING
                            AEROBIC
                            LAGOON
         AIR
       UPGRADED
                                 RECYCLED,
                                  WATER
fc.
w
4
^
SCREENS

^
W
FLOTATION
_| 1
t T
AERATION
BASIN

^
BAFFLE Ari
WEIR
^
)
POLISHING
POND

.^

\
1
1
1 fc
W
\
1
                                CHLORINATION'
Figure 8. A method for upgrading a lagoon.
             39

-------
                               ANAERORBIC
                                 LAGOON
                   EXISTING
RECIRCULATION

                                                 SOLIDS
                                              RECLAMATION
                                                  DISPOSAL
                                         CLARIFIER
                                       CHLORINATION
                 UPGRADED
          Figure 9. A method for upgrading a lagoon.
                       40

-------
                                   AEROBIC
                                   LAGOON
    SOLIDS RECLAMATION
        OR DISPOSAL
RECIRCULATION
                                     CLARIFIER
                          AERATION

                            BASIN
                             J
                     UPGRADED
                                          I
POLISHING
   POND
CHLORINATION
             Figure 10. A method for upgrading a lagoon.
                           41

-------
 Figure 11.  Air compressors serving return air lifts, aeration tanks, and
 aerobic digester.  (Cotton Producers Association, Gold Kist Division,
                                 Live Oak, Fla.)
                             LIVE , POULTRY
           ENTRAILS.  OFFAL,  HEADS. AND OTHER WASTE MATERIAL
                     SLUDGE-IP.OOP GPD.I.MAX RATE-50 CPM, MIN RATE - 0
                         AVE RATE-IS 0PM
                         MIN RATE- 5 SPM
            MAX RATE  730 GPM   10,000 GPD
SANITARY SEWAGE         200,000 GPD

t	LIMITS OF WASTE TREATMENT SYSTEM
 roo,ooo GPD
AVERATE-487GPM MIN RATE-I46GPM
                            MAX RATE-50 GPM
                                       "7r
MAX RATE-
MIN RATE-0
^- 	 »-
240 GPM
AEROBIC
DIGESTER
0-200
GPM

SLUDGE
DRYING
BEDS
   Figure 12. Waste-treatment process flow diagram. (Cotton Producers
              Association, Gold Kist Division, Live Oak, Fla.)
                                   42

-------
                                                              Figure 13.  Byproducts
                                                              collector—primary
                                                              clarifier. (Cotton Pro-
                                                              ducers Association,
                                                              Gold Kist Division,
                                                              Live Oak, Fla.)
                                 :
Figure 14.  Aeration
tanks. (Cotton Pro-
ducers Association,
Gold Kist Division,
Live Oak, Fla.)
                            V**"Sf >\\
                            OT
                            v\>--%

                             \   *-
                                      43

-------
Figure 15. Process waste entering sump.  (Cotton Producers Association, Gold Kist Division,
                                   Live Oak, Fla.)
 Figure 16. Feed meal recovery from primary sludge.  (Cotton Producers Association, Gold
                            Kist Division, Live Oak, Fla.)
                                        44

-------
                                                              Figure 17. Air header lifting mech-
                                                              anism—aeration tanks.  (Cotton
                                                              Producers Association, Gold Kist
                                                              Division, Live Oak, Fla.)
Figure 18.  Final effluent from
pond.  (Cotton Producers
Association, Gold Kist Division,
Live Oak, Fla.)
                                            45

-------
Figure 19. Final clarifier.  (Cotton Producers Association, Gold Kist Divi-
                         sion, Live Oak, Fla.)
Figure 20.  Atypical large trickling filter.  (Cotton Producers Association,
                  Gold Kist Division, Live Oak, Fla.)
                                  46

-------
  Figure 21. Final Lagoon—tertiary pond. (Cotton Producers Association, Gold Kist Divi-

                                 sion, Live Oak, Fla.)
                                                                            2.0
O
_1
u.

IE
LxJ
UJ
I-
(O
                                           75,000 BIRD DAY (NO CONDENSER
                                            COOLING WATER  RECYCLE )
         12 I
               234

              PLANT
                IDLE
7  8 9  10  II 12 I   2  3  4  5  6 7  8 9  10 II  12

 1ST PROCESSING  ,|_   CLEANUP
      CMJICTP              ^   ^^
                                  SHIFT
                                                      SHIFT
                               A.M.
                      RM.
          Figure 22.  Present daily hydraulic loads on Gold Kist IWT facilities.
                                         47

-------
S
CL
                                                                            2.0
                                                                       1.75
                                                                            1.50
                                                                             1.25
?
UJ
V)
I
                                                   115,000 BIRD DAY   0.98
                                                   M.G.D.   100%  CONDENSER
                                                   WATER  RECYCLE
                                                                                   q
                                                                                   C)
                                                                                   S
                                                                                   O
          12 I
                2  3  4  5 6  7  8  9  10 II  12  I

                CLEAN UP I    I ST  PROCESSING
                                          2  3 4  5  6 7  8 9  10 II 12

                                             2ND  PROCESSING   I
                 SHIFT
                                  SHIFT
                              A.M.
                                                SHIFT

                                             P.M.
        Figure 23. Future average daily hydraulic loads on Gold Kist IWT facilities.
z

o
IT
UJ
9
UJ
I-
tfl
<
1400

1300

1200

1100

IQOO

900

800

700

600

500

400

300

200

100

0
                                                  130,000 BIRD DAY    1.04
                                                  M.G.D. 100% CONDENSER
                                                  WATER   RECYCLE
                                                                           2.0
                                                                           175
                                                                           1.50
                                                                           1.25
                                                                            10
                                                                           0.75
                                                                           0.50
                                                                           0.25
          12  I  2  3 4  5  6 7  8  9  10 II 12 I

              CLEAN UP   i  I ST PROCESSING
                                         2  3  4  5 6  7  8  9  10 II  12

                                         I . 2ND PROCESSING  _i ,
                SHIFT
                           SHIFT

                        A.M.  -»
                                                     SHIFT

                                                  P.M.
       Figure 24. Future maximum daily hydraulic loads on Gold Kist IWT facilities.
                                         48
                                                                                  o
                                                                                  e>
                                                                                  2
                                                                                  O
                                                                                  §
                                         * U.S. GOVERNMENT PRINTING OFFICE  1973 O - 527-778

-------