>A/202/R-93/004
                  Interim Report Of

                  The Federal Facilities

                  Environmental Restoration

                  Dialogue Committee

                          Recommendations For Improving
                          The Federal Facilities Environmental
                          Restoration Decision-Making And
                          Priority-Setting Processes

                          February 1993
                                            Recycled/Recyclable

                                            Printed on paper that contains
                                            al least 50% recycled liber

-------
This document is the result of the work of the Federal  Facilities  Environmental  Restoration Dialogue
Committee, a federal advisory committee chartered by the U.S. Environmental Protection Agency and
facilitated by The Keystone Center.  For additional copies of this report please contact:
Office of Federal Facilities Enforcement
Strategic Planning and Prevention Division
U.S. Environmental Protection Agency
401 M Street, S.W. (OE-2261)
Washington^ D.C.  20460
202-260-9801
or
The Keystone Center
Science and Public Policy Program
P.O. Box 8606
Keystone, Colorado 80435
303-468-5822

-------
                     INTERIM REPORT

                        OF THE

         FEDERAL FACILITIES ENVIRONMENTAL RESTORATION
                   DIALOGUE COMMITTEE
RECOMMENDATIONS FOR IMPROVING THE FEDERAL FACILITY
ENVIRONMENTAL RESTORATION DECISION-MAKING PROCESS
         AND SETTING PRIORITIES IN THE EVENT
                OF FUNDING SHORTFALLS
                      February, 1993

-------
                            TABLE OF CONTENTS

             FEDERAL FACILITIES ENVIRONMENTAL RESTORATION
                           DIALOGUE COMMITTEE

      EXECUTIVE SUMMARY

1.0.   INTRODUCTION

      1.1.   BACKGROUND ON FEDERAL FACILITIES ENVIRC JMENTAL RESTORATION

      1.2.   THE FFER  DIALOGUE COMMITTEE: ITS MEN ERSHIP, PURPOSE, AND
            GOALS, AND THE IMPLICATIONS OF THIS REPO T

            1.2.1. Background on the FFER Committee

            1.2.2. The Goal of the FFER Committee and the Impl itions of this Report

      1.3.   GENERAL PROBLEMS  WITH  THE  CURRENT  TER DECISION-MAKING
            PROCESS

            1.3.1. The Problem of Mutual Distrust

            1.3.2. Ongoing Disputes Over Statutory Authorities

      1.4.   OVERVIEW   OF  THE  RECOMMENDATIONS    MD  SCOPE  OF  ISSUES
            ADDRESSED IN THIS REPORT

            1.4.1. FFER Priority-setting and Decision-making

            1.4.2. Federal Facility Environmental Restoration

            1.4.3. Clarification of Commonly Used Terms

2.0.   RECOMMENDATIONS FOR IMPROVING THE PROCESS 3F DISSEMINATING AND
      EXCHANGING INFORMATION WITH AFFECTED STAKE  3LDERS

      2.1.   BACKGROUND AND STATEMENT OF NEED

      2.2.   DEMONSTRATED   SUCCESSES  AND  PRIN PLES   OF  EFFECTIVE
            INFORMATION DISSEMINATION AND EXCHANG

      2.3.   RECOMMENDATIONS

            2.3.1. Overview and Scope

            2.3.2. Information Dissemination Policy

-------
            2.3.3. Citizen Use of FFER Information

            2.3.4. Central Point of Contact within Agencies

      2.4.   IMPLEMENTATION STRATEGIES


3.0.   RECOMMENDATIONS FOR IMPROVING THE PROCESS OF SOLICITING INPUT FROM
      AFFECTED STAKEHOLDERS

      3.1.   BACKGROUND AND STATEMENT OF NEED

      3.2.   DEMONSTRATED SUCCESSES OF SITE-SPECIFIC ADVISORY BOARDS

      3.3.   RECOMMENDATIONS REGARDING THE ESTABLISHMENT OF SITE-SPECIFIC
            ADVISORY BOARDS

            3.3.1. Overview and Scope

            3.3.2. When Site-Specific Advisory Boards Should Be Established or Restructured

            3.3.3. Model Approach to the Formation of SSABs

                 a)    Charter
                 b)    Scope
                 c)    Role of Regulated and Regulating Agencies
                 d)    Membership and Membership Selection Process
                 e)    Accountability
                 f)    Interaction with the Public
                 g)    Operating Procedures
                 h)    Administrative and Technical Funding

      3.4.   IMPLEMENTATION STRATEGIES


4.0.   RECOMMENDATIONS FOR IMPROVING ACCOUNTABILITY THROUGH ENHANCED
      STAKEHOLDER INVOLVEMENT THROUGHOUT THE FEDERAL BUDGET PROCESS

      4.1.   BACKGROUND

      4.2.   OBJECTIVE

      4.3.   PRINCIPLES

      4.4    OVERVIEW OF THE CONSULTATION AND ALLOCATION PROCESSES


      4.5    CONSULTATION PROCESS

-------
              4.5.1.  Introduction and Scope

              4.5.2.  Consultation During Program Development and Execution

              4.5.3.  Consultation  During  the  Initial  Field-Level  Development of  Site-Level
                      Requirements

              4.5.4.  Notification after the President's Budget Submission

              4.5.5.  Consultation   after  Presidential/Congressional   Appropriation  and  OMB
                      Apportionment

              4.5.6.  Consultation after Budget Execution

       4.6    ALLOCATION PROCESS

              4.6.1.  Introduction and Scope

              4.6.2.  Important Considerations in the Allocation of FFER Funds

              4.6.3.  Fair Share Allocation  Process to Address Insufficient Appropriations  for Sites
                      That Are Subject to Outside Supervision

              4.6.4.  Fair Share Allocation  Process to Address Insufficient Appropriations  for Sites
                      That Are Not Subject to  Outside Supervision

              4.6.5.  Allocation  Process to Address  Funding Shortfalls Caused by  Unanticipated
                      Program Growth

              4.6.6.  Recommendation Against Congressional Earmarking


5.0.    CONCLUSION


Appendices

Appendix A:   List of FFER Dialogue Committee Members and Alternates

Appendix B:   FFER Dialogue Committee Charter and Ground Rules

Appendix C:   History and Description of the Federal Facilities Environmental Restoration Dialogue
              Process

Appendix D:   Statutory Provisions for Technical Review Committees
                                             in

-------
                                        ACRONYMS
A list of acronyms used
that the acronym repres
ATSDR
BRAC
CERCLA

DERP
DOD
DOE
DOI
DOJ
EM
EPA
ER
ERWM
FFA
FFER
FOIA
FUDS
FUSRAP
GAO
IAG
NASA
NCP
NEPA
NOAA
NPL
O&M
OMB
PEIS
PRP
RCRA
REO
RI/FS
ROD
SARA
SSAB
SVTC
TAG
TCE
TKC
TRC
UMTRA
USDA
Agency
BaseR
Compri
as at
Defenj
Depart
Depar
Depar
Depar
DOEt
Envirc
DOEl
DOE<
Federa
Federa
Freedo
Formei
Formei
Genera
Interag
Nation
Nation
Nation
Nation;
Nation;
Operati
Office i
Prograi
Potentii
Resoun '.
Regiom i
Remedi; .1
Record 1
Superfui i ,
Site-Spe fi
Silicon \ ill
Technica A
Trichlorc ;th
The KeyLton
DOD Techni
Uranium Mil
U.S. Departn
hout this document is provided below, along with the full name or term
                             c Substance Disease Registry
                             it and Closure (Act)
                             environmental Response, Compensation, and Liability Act of 1980,

                             mental Restoration Program
                             >efense
                             inergy
                             le Interior
                             ustice
                             Environmental Restoration and Waste Management
                             5rotection Agency
                             Environmental Restoration
                             Environmental Restoration and Waste Management
                             Agreement
                             Environmental Restoration
                             Tmation Act
                             Defense Sites
                            :ed Sites Remedial Action Program
                             iting Office
                             cement
                             wtics and Space Administration
                             gency Plan
                             imental Policy Act of 1969, as amended
                             : and Atmospheric Administration
                              js List
                              aintenance
                              ;ment and Budget
                              ivironmental Impact Statement
                              msible Party
                              vation and Recovery Act of 1976,  as amended
                              imental Officers
                              gation/Feasibility Study
                              ion
                             idments and Reauthorization Act of 1986
                             /isory Board
                             3xics Coalition
                             ant Grant
                             ,e
                             enter
                             Review Committee
                            failings Remedial Act
                                              IV

-------
EXECUTIVE SUMMARY

The federal facility environmental restoration challenge is enormous. The environmental legacy of the
federal  government's  mission-oriented  activities is felt  in  communities  throughout the  country.
Environmental clean-up of the 24,000 sites on federal facilities in the United  States may ultimately cost
as much as $400 billion and will extend well into the next century.  From a technical perspective, these
clean-ups  are likely to be particularly complex and challenging.  Equally challenging is the process by
which federal facility  clean-up decisions are made.  From the perspective  of many participants,  the
current process has been unnecessarily hampered by feelings of mistrust and conflict over the appropriate
roles, responsibilities, and authorities of regulated and regulating agencies and other affected stakeholders.
Reinvigorating the process will require a fundamental change in the way the clean-up process is managed.
The cornerstone of this change must  involve a shift from the decide, announce,  and defend mode of
public involvement to a new partnership between all of the affected stakeholders.

The Federal Facilities Environmental Restoration (FFER)  Dialogue Committee, which  includes forty
representatives of federal agencies, tribal and state governments and associations, and local  and national
environmental, community, and labor organizations (see Appendix A for a list of Committee members
and  alternates),  was  established by  EPA to develop  consensus  policy recommendations aimed at
improving the FFER decision-making process to ensure that clean-up decisions reflect the priorities and
concerns of all stakeholders.

In an era of increasing concern over federal budget deficits, the FFER Dialogue Committee believes that
it is essential for federal facility clean-up decisions to be broadly supported if the nation is to accomplish
its clean-up goals in a timely and  efficient manner.  Technical breakthroughs and scientific models alone,
as important as  they  are to ensuring progress, will not overcome  the  current problems  with  FFER
decision-making.  Indeed, the future viability of federal  facility clean-ups depends on the ability of the
federal government to  incorporate the divergent views of all concerned stakeholders into the decision-
making process  such that all  stakeholders can become true partners in ensuring that clean-ups  are
conducted in the safest, most efficient, and most cost-effective manner possible.

Unless otherwise noted, the recommendations contained in this report reflect the consensus views of the
members of the FFER Dialogue Committee, all of whom participated as individuals rather than as official
spokespersons of their respective agencies, organizations, or associations.

The Committee's recommendations focus on:

        •      improving the dissemination of FFER related information (Section 2);

        •      improving stakeholder involvement in key FFER decisions, with special emphasis on the
              use of site-specific advisory boards (Section 3); and

        •      improving consultation on FFER funding decisions and setting priorities in  the event of
              funding shortfalls (Section 4).
What follows is a brief summary of the detailed recommendations that are found in each major section
of the report.   It should be noted that the language in the report was debated word-by-word by the

-------
Committee.   Due to  the detailed and,  in many instances,  mutually  interdependent nature  of the
recommendations, the  Committee encourages readers to refer to the full text of the recommendations
instead of relying solely on the Executive Summary.
INFORMATION DISSEMINATION AND EXCHANGE

The  Committee makes three  recommendations regarding  the current process for disseminating and
exchanging information to affected stakeholders including:

       •      developing agency-wide information dissemination policies on information that is related
              to environmental restoration;

       •      encouraging public participants to portray accurately the status of documents or other
              information that they receive in draft form;  and

       •      developing a  central point  of contact  within each  agency for assisting in FFER
              information exchange.

To help facilitate the implementation of these recommendations, the Committee recommends that agencies
consider such options as establishing an "800" number for citizens to call for information on
environmental restoration activities, and establishing a mailing list of citizens interested in such activities.
INVOLVING AFFECTED STAKEHOLDERS

The  Committee's  recommendations  for  involving  affected  stakeholders more  directly  in  FFER
decision-making focus on the creation and use of site-specific advisory boards (SSABs). The role of the
SSABs is to actively involve representatives of the local community and others in the clean-up decision-
making process. The Committee recommends that SSABs be used to streamline and complement, rather
than supplant, broader site level FFER public involvement initiatives. The intended scope of the  SSABs
is  to address federal  facility environmental  restoration issues, as well  as  waste management and
technology development issues that are related to  environmental restoration.

The report describes when SSABs should be established and proposes a model approach to implementing
these recommendations,  including:

       •       the appropriate SSAB charter and scope and roles of regulated  and regulating agencies;

       •       a method for determining SSAB membership; and

       •       appropriate operating procedures and methods for ensuring accountability.
The Committee recommends that SSABs should be provided support for administrative needs.  Most
Committee members also agree that regulated agencies should provide funding for technical assistance
to non-governmental SSAB participants to help ensure more effective and meaningful participation. The
                                             VI

-------
report describes  recommended  levels,  appropriate uses,  and implementation options for providing
administrative and technical assistance funding.

The Committee's recommendations for involving affected stakeholders are provided for consideration by
those who will be responsible for implementation at the site level.  The Committee believes that it is
essential for the federal agencies to work closely with local communities to ensure that SSABs reflect and
are responsive  to local  community  needs and  concerns.   The  Committee  recognizes  that  the
recommendations in this Interim Report will need to be tailored to meet the needs of each federal site and
its local stakeholders.
CONSULTATION ON FFER FUNDING MATTERS

In assessing the concern that federal clean-up programs are likely to experience funding constraints, the
Committee believes that extensive and meaningful stakeholder involvement is the key to reducing the
impacts of such conditions. As such, the Committee recommends that federal agencies communicate in
a timely manner site-specific or programmatic decisions affecting the ability of a site to meet its legally
binding clean-up obligations to stakeholders. In addition to such ongoing consultations, the Committee
recommends that information be shared during several discrete points in the FFER funding and decision-
making process, including:

        •      at the time of initial field-level development of site-level requirements;

        •      after submission of the President's budget to Congress;

        •      after Presidential/Congressional appropriation and during agency allocation; and

        •      after budget-year execution.

Such  consultation should  revolve around  what  FFER activities or projects are  being considered for
execution and what FFER  activities or projects have been executed.  The information exchanged should
be at  a sufficient level of detail to enable verification that an agency's budget request package includes
the activities and projects that are necessary to meet budget year obligations and milestones contained in
enforceable  agreements and other documents as  well  as to ensure adequate progress toward  out-year
obligations and milestones.


SETTING PRIORITIES  IN THE EVENT OF FUNDING SHORTFALLS

The Committee agrees that existing milestones describe a set of obligations that  should be honored to the
fullest extent possible. However, given the practical limitations of the federal budget process, even the
most arduous efforts may  not ensure full  funding for  all FFER obligations.  As a result, there may be
times  when  insufficient funds  will prevent full implementation of all FFER obligations.

In light of the growing concern that federal facility clean-up activities may face funding shortfalls, the
Committee recommends a flexible strategy for  applying  "fair  share" principles  to allocating funding
shortfalls. The Committee recommends a detailed process for applying fair share principles in the event
                                              vn

-------
of funding shortfalls caused by insufficient appropriations and a more general set of principles for use
when shortfalls occur due to unanticipated program growth.

The Committee recognizes that it is not appropriate to use health risk as the single criterion to guide the
allocation of FFER resources.  Other factors, such as environmental risk, indigenous peoples' rights, and
environmental equity, must also be considered.  Even though health and environmental risks are not the
sole factors that should determine the allocation of FFER dollars, it is important to obtain more and better
information on environmental  and human health exposure and risk from federal facility contamination.
The Committee strongly supports increased efforts to develop such information.

Where funding shortfalls result from insufficient appropriations, the Committee recommends that, to the
greatest extent possible, all sites subject to outside supervision should share equally in the total amount
of the funding shortfall. This is defined as the "fair share" allocation. The Committee recommends that
a process of consultation between regulated agencies, state and federal regulators, affected tribes, and
other affected stakeholders, take place in an effort to reallocate funds among FFER projects and activities
within a site without missing legally binding obligations. However, if this is not possible or appropriate,
given  the  criteria  summarized above and  specified  in  more detail  in the  report, the  Committee
recommends that  regulating agencies  renegotiate legally binding clean-up  obligations, rather  than
undertake punitive enforcement actions,  so long as:

       •      the fair share allocation is adhered to;

       •      the regulated  agency implements the recommendations contained in  this report  in  a
               responsible and good faith manner; and

       •      the funding requested for that agency's FFER budget represents the Executive Branch's
               best estimate of the amount of funding that is necessary to meet that agency's  legally
               binding clean-up obligations.

Regulated agencies may suggest a reallocation of FFER resources in a manner that is not consistent with
the fair share principles specified in this report.  However, the agency may be subject to punitive
enforcement action if such reallocation causes a legally binding obligation to be missed.

Where the funding shortfall is caused by unanticipated  program growth, the Committee recommends  a
greater emphasis on absorbing the shortfall at those sites where it  arose.  A consultation process would
still occur, but the Committee did not recommend  granting  enforcement relief for program growth
funding shortfalls.

The Committee recognizes that in certain cases an appropriation bill may specify or "earmark" precise
funding levels for particular sites. The Committee strongly recommends that Congress refrain from  such
site-specific earmarking as it will detract from  the principles of fairness that are built into the process
described herein,  as well as diminish the value of stakeholder involvement in FFER programs.
CONCLUSIONS AND NEXT STEPS

This report is  being issued as an Interim Report to  communicate  the  results of the Committee's
deliberations at this  critical stage of transition and to provide an opportunity to begin the process of

                                              viii

-------
implementing the recommendations where consensus exists among Committee members. The Committee
intends for its recommendations to  be implemented with common sense consideration of the needs,
interests, and concerns of those who live near and, therefore, are most directly impacted by site-level
clean-up efforts.  As such, the recommendations contained in this report are intended to serve as a model
that should be utilized and tested at both the field level and the national policy making level.

The  FFER Dialogue  Committee  will be  undertaking a  variety of  efforts  to communicate  its
recommendations and receive feedback from those who did not participate directly in its deliberations.
The Committee will continue to meet to assess the progress that is being made and address concerns that
emerge with the  implementation of its recommendations.

The Committee believes that the recommendations contained in this report represent a new approach for
conducting federal facility clean-ups. It is based on the premise that all stakeholders should participate
in a meaningful manner in the FFER decision-making process.  It is the view of the Committee that only
through such active involvement of all affected stakeholders can a true partnership develop that will lead
to broadly supported clean-up decisions.

It is the sincere hope of the FFER Dialogue Committee that the process it has gone through to develop
its recommendations, as well as the  recommendations themselves, will usher in a new era of trust and
consensus-building that allows all parties to  get on with the  job of cleaning  up  federal facilities in a
manner that reflects the priorities and concerns of all stakeholders.
                                              IX

-------
1.0.   INTRODUCTION

1.1.   BACKGROUND ON FEDERAL FACILITIES ENVIRONMENTAL RESTORATION

Over the past decade it has become increasingly clear that environmental contamination at federally
owned and operated facilities poses a significant challenge for the nation.  Over this period, it has also
become clear that there are many interests that have a stake in and are concerned about what is occurring
at these facilities.

With the passage of statutory provisions under the Resource Conservation and Recovery Act (RCRA) and
the Comprehensive Environmental Response,  Compensation,  and  Liability Act (CERCLA)1 and the
corresponding increased attention that has been placed on identifying environmental contamination  at
federal facilities, the immense magnitude of this problem has become clear. Estimates for clean-up  of
the approximately 24,000 currently identified sites at federal facilities range from $100 billion to upwards
of $400 billion.  Clean-up  efforts are projected to continue well into the 21st Century.2

By  any measure, the cost of cleaning up the environmental contamination that is currently known to  exist
at federal facilities is enormous.  Such costs must be borne by taxpayers because of the public purposes
served by these facilities.   More significantly, these costs must be borne by taxpayers in an era  of
increasing concerns over the growing federal budget deficit.

Many who are involved in  managing federal  facility clean-up  programs, as well as  those who are
regulating or affected by these programs, are becoming increasingly concerned with the ability of the
nation to maintain the necessary level of funding to meet current clean-up goals.  Because of these
concerns, there has been an increasing amount of attention paid to the need to establish publicly supported
priorities as the study and actual  clean-up of these facilities proceed.

As  the sheer  magnitude of federal facility environmental contamination has become clear, so have the
technical complexities of these problems.   In many instances federal facility environmental contamination
problems pose threats to human  health and the environment that are similar to those that are found  at
private sector sites.  However, in numerous other situations, especially those found at the major defense
production facilities owned and operated by the DOE, the technical dimensions of the environmental
contamination problems are perhaps as complex as those found anywhere in the world.

Environmental contamination confronts federal agencies with challenges that are often fundamentally
different from those of their primary missions.  Although clean-up problems exist at facilities owned by
most federal agencies, the number and severity  of these problems are greatest at sites managed by DOD
and DOE.  The facilities that are  owned by these agencies were built and operated primarily to serve the
nation's defense needs.  As in the private sector, many of the environmental contamination problems  at
these facilities had their genesis in an era when there were few laws or regulations to address the disposal
    1  See Section 6001 of RCRA and Section 120 of CERCLA.

    2   Sources include:   Milton Russell, et al., Hazardous  Waste Remediation: The Task  Ahead.
University of Tennessee, Dec. 1991.  pg. 22;  U.S. Department of Defense, Installation Restoration
Program Cost Estimate Sept. 1991; Congressional Budget Office. Federal Liabilities Under Hazardous
Waste Laws. May  1990.

-------
                      DEPARTMENT OF DEFENSE

It is estimated that there are over 15,000 sites where hazardous substances may have been
released at nearly 1,900 facilities owned or operated by the Department of Defense
(DOD). DOD estimates its clean-up cost to be in the range of $25 billion.
                       DEPARTMENT OF ENERGY

The Department of Energy (DOE) has identified 9,000 sites for clean-up.  In
many instances, DOE is in the early stages of site assessment to determine the
nature and extend of the contamination.  As a result, the costs and time to
complete remediation are difficult to ascertain. DOE estimates, however, that
clean-up costs may be in the range of tens of billions of dollars, and has set year
2019 as the goal for cleaning up the inventory of sites identified by 1989. As
DOE  moves from the assessment phase into implementing remedial actions, actual
costs and time frames necessary to clean-up will become more clear.
                   DEPARTMENT OF THE INTERIOR

The Department of the Interior (DOI) currently has 422 sites listed on the Federal
Agency Hazardous Waste Compliance Docket and  two sites that are listed on the
National Priorities list (NPL).  The sites on DOI-managed lands and facilities are
generally not the result of DOI activities, but rather activities conducted on those
lands illegally or under various statutes authorizing use of public lands.  The DOI
has not yet completed inventories of the 440 million acres of land that it manages,
so the total number of clean-up sites on DOI-managed lands is  still unknown.
Thus, the costs  and time frames necessary to clean up these sites are difficult to
determine given the preliminary state of evaluation of DOI-managed lands.

-------
                           U.S. DEPARTMENT OF AGRICULTURE

         The U.S. Department of Agriculture (USDA) currently has 96 sites listed on the
         Federal Agency Hazardous Waste Compliance Docket.  None of these sites are
         identified on the NPL as a USDA responsibility.  However, USDA agencies
         currently are involved with cleanup at two locations listed on the NPL.

         In general, USDA agencies have completed an inventory and discovery process
         for federally owned facilities or managed lands with two notable exceptions. The
         Forest Service has not completed an inventory of potential problems on the 190
         million acres of land it manages with respect to abandoned mining sites or closed
         sanitary landfills.  Most of these sites are the result of third party activities on
         National Forest lands that have occurred in the past under authorizing statutes,
         regulations, or  permits.   Thus, the total estimated cost of the Department's
         hazardous waste cleanup program and the time frame for implementation has not
         been determined at this time.
              NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION

         The National Oceanic and Atmospheric Administration (NOAA), within the
         Department of Commerce, has one site with an estimated clean-up cost of $50
         million and a clean-up time frame of at least 10 years. This site is currently not
         on the NPL. NOAA  is just beginning to do environmental audits, so it may
         discover more sites.  The Department of Commerce has responsibility for more
         clean-up sites which belong to other agencies, via lawsuits, with an estimated
         clean-up cost of approximately $150 million over a 10-20 year period.
of hazardous and radioactive wastes.  Furthermore, the national defense missions of these facilities were
seen as paramount.  Often this mission required a high degree of secrecy (and in some instances still
does) regarding the precise nature of the activities that were taking place at these facilities.

With  increased knowledge of environmental contamination at these facilities, there has been  an ever
increasing level of public demand to clean them up.  DOD and DOE have often tried to deal with rising
public interest and  concerns, as well as increased regulatory oversight, through traditional command and
control approaches that have worked well in the context of their national defense missions.  Although
much progress has been made toward bringing federal facilities into compliance  with state and federal
environmental laws, there  remain significant  management and  public  credibility problems which
jeopardize efforts  to prioritize clean-up  efforts to prioritize clean-up projects and form strategies  for
reaching long term environmental restoration objectives.

-------
Federal agencies other than DOD and DOE also have significant environmental contamination problems,
although most of these agencies do not have a national defense mission and the technical dimensions of
their contamination problems are typically much less complex than DOE's or DOD's.  Nevertheless,
there are management and public credibility problems related to the clean-up programs at these agencies
that are similar to those at DOE  and DOD.

The Committee believes that public involvement is essential for achieving publicly supported priorities
for clean-up.  Federal agencies recognize and support the legitimate and important role the public has in
helping to identify clean-up priorities.  The recommendations of this report,  therefore, are aimed at
creating a more effective public participation process.

1.2.    THE FFER DIALOGUE COMMITTEE: ITS MEMBERSHIP. PURPOSE. AND GOALS.
       AND THE IMPLICATIONS OF THIS REPORT

1.2.1.  Background  on the FFER Dialogue Committee

In April of  1992,  the U.S. Environmental  Protection  Agency established the  Federal Facilities
Environmental Restoration (FFER)  Dialogue Committee as an advisory committee  under the Federal
Advisory Committee  Act.  As stated in its charter, the purpose of the FFER Dialogue Committee is to
provide a forum to identify and refine issues related to environmental restoration activities at federal
facilities. The Committee was intended to be a forum for the exchange of ideas and information among
individuals representing organizations and agencies that have an interest in or responsibility for managing
or overseeing environmental restoration activities at federal  facilities.  The Committee was formed  with
the hope that such diverse parties might reach consensus on how to address issues related to improving
the manner in which decisions are made and priorities are established for the clean-up of federal facilities.
However, at a minimum, EPA,  the chartering agency, wanted to ensure that issues were thoroughly
defined and that differing positions, as well as the reasons for those differences, were identified.

The FFER Dialogue Committee  includes representatives of:

       •      Several federal agencies, including the

                      Environmental Protection Agency (EPA),
                      Department of Defense (DOD),
                      Department of Energy (DOE),
                      U.S. Department of Agriculture (USDA),
                      Department of the Interior (DOI),
                      National  Aeronautics and Space Administration (NASA),
                      National  Oceanic and Atmospheric  Administration (NOAA),  and
                      Agency for Toxic Substance Disease Registry (ATSDR);
       •      National and local environmental, citizen, and labor organizations;

       •      Tribal governments and Native American organizations; and

       •      State government and state government associations.

                                              4

-------
Although each member of the FFER Dialogue Committee is affiliated with an agency, organization, or
association that is either responsible for or actively involved in federal facility environmental restoration
issues, Committee members were not asked  to represent formally, or make binding commitments on
behalf of, their home organizations.

Appendix A includes a complete listing of FFER Dialogue Committee members and alternates.  Appendix
B includes  additional background information on  the Committee, including a copy of the Committee's
charter and its agreed upon ground rules.

The impetus behind the creation of the FFER Dialogue Committee was an informal information exchange
and consensus-building dialogue that was initiated in early 1991. In the beginning, this informal dialogue
focused on exchanging information on the variety of approaches that federal agencies are using to help
set priorities for cleaning up their facilities.  In exchanging such information, the Dialogue Group soon
recognized  that other fora had already been established which were more appropriate for critiquing the
technical attributes of these various priority-setting models.  Furthermore, the Dialogue Group agreed
that there was a much broader set of issues that needed to  be addressed regarding the overall context
within which any particular priority-setting model might be utilized.  These general  agreements helped
form  the basis of the discussions  that  then took place under the auspices of the FFER Dialogue
Committee. (See Appendix C for a detailed description of the  events  that led up to the formation of the
Federal  Facilities Environmental Restoration Dialogue Committee.)

The FFER Dialogue Committee met four times, in April, July, November, and December of 1992.  In
addition, the Committee formed  two separate  work groups,  which met numerous  times between
Committee meetings to produce draft documents for full Committee consideration.

1.2.2. The Goal of the FFER Dialogue Committee and the Implications of this Report

Soon  after the FFER Dialogue Committee was formed, its members agreed upon the following goal
statement:

       The goal  of the  FFER  Dialogue  Committee  is to  develop  consensus   policy
       recommendations  aimed at improving the  process  by which  federal  facility
       environmental restoration decisions are made, such that these decisions reflect the
       priorities and concerns of all stakeholders.

This report describes the outcome of the deliberations of the FFER Dialogue Committee.  The Committee
wishes to emphasize that this report contains recommendations for policy changes rather than official
policy pronouncements. Unless otherwise stated in the report, the recommendations contained herein are
the consensus policy recommendations of the FFER Dialogue Committee. As defined in the Committee's
ground rules, proposals were considered to have achieved consensus when there was no dissent from any
member of the Committee.

In many instances, the language contained in the report was debated word-by-word  and there was
considerable give and take between Committee members.  Thus, some Committee members believe the
recommendations could have gone further or could have been more strongly worded  and others believe
they go further than is necessary to bring  about needed  changes.   In still other  instances, policy
recommendations were proposed and  strongly  advocated, but are not included in this report because they
did not achieve consensus.  Finally, in three instances, each of which is clearly noted, the Committee did

-------
not reach a full consensus.   In  two of these instances, some Committee  members  agreed  with  the
recommendations contained in the report but thought these recommendations did not go far enough to
address their concerns.  In the other instance, an agency  is taking the  recommendation  of other
Committee members under advisement. Because these issues were still considered to be important,  the
outcome of the Committee's efforts are included in this report in order to characterize accurately  the
Committee's deliberations and help inform future efforts that are aimed at resolving these issues.  Even
where consensus was not possible, however, Committee members agree that the language contained in
the report accurately characterizes the outcome of its discussions.

Although the FFER Dialogue Committee process was  not intended to bind any of the organizations,
agencies, or associations with whom Committee  members and alternates are affiliated or employed, all
of the  signatories to this report have agreed to work proactively toward the implementation of  the
consensus policy recommendations within their respective agencies and organizations.3 Furthermore,
Committee members  have agreed  not to  undermine the implementation of the consensus policy
recommendations by others who may or may not have been members of the FFER Dialogue Committee.

As such, this report is intended to serve as a chronicle of the FFER Dialogue Committee's deliberations
and as a set of agreements and milestones that Dialogue participants (and others who read this report and
agree with  its recommendations)  will use to assess the progress that is being made towards "improving
federal facility environmental restoration decision-making processes such that they reflect the priorities
and concerns of all stakeholders."

1.3.    GENERAL PROBLEMS WITH THE CURRENT FFER DECISION-MAKING PROCESS

Committee members  believe there are  two  general problems  that  are currently  preventing  rapid
improvements to the decision-making processes for  federal facility clean-ups - a high level of distrust
among some affected stakeholders and ongoing disputes over the interpretation of critical  statutory
provisions related to the respective authority of state and federal regulators and federal facility program
managers.

These barriers  range from  subjective and  perceptual differences to  more complex  and controversial
distinctions involving legal interpretations of statutes. But, real or imagined, the members of the FFER
Dialogue Committee  believe these barriers must  be  eliminated  in order to improve  the current
inadequacies in site clean-up decision-making and priority-setting.

1.3.1.  The Problem of Mutual Distrust

FFER Dialogue Committee members believe that the most visible and common impediment to effective
FFER decision-making results from  a long history of deep-seated mutual distrust among some affected
stakeholders and some decisionmakers.
    3  In the case of Committee members who are  staff of state associations such as the National
Governors' Association,  National  Association of Attorneys General,  and Association  of State and
Territorial Solid Waste Management Officials, this means that they will bring this report to the attention
of the members of these associations (i.e., Governors, Attorneys General, and Department Heads). Other
Committee members,  who are employed by the members of these state associations, agree to work
proactively within those associations toward implementation of the recommendations of this report.

-------
Some state and tribal government representatives, as well as affected citizens closest to the contaminated
federal sites, feel ignored and overwhelmed by a seemingly insensitive national bureaucratic structure that
appears to be making even the most fundamental decisions in isolation. Facility neighbors in particular
are often suspicious of federal agencies  and feel excluded  from important environmental  restoration
decisions that may affect their future, the health  of their families, and  the value  of their property.
Moreover,  where a  public  involvement  process  is  mandated  by law  -- whether in  the National
Environmental  Policy Act (NEPA) or federal and state clean-up laws — the public often perceives that
the process is used  to defend decisions already made without meaningful dialogue with the affected
public.

Some regulators and citizens also question the sincerity and  commitment of some federal agencies and
their facility managers to rapid and effective clean-ups. These feelings are based on negative experiences
in gaining public access to site information, failures on the part of federal  agencies to deliver results or
meet  agreements, and lack of feedback  about the dynamics  of  initiating and funding clean-up at a
particular site.

Some federal agency representatives, on the other hand, see an apparently insatiable and unorganized mix
of groups and governments with often conflicting and  sometimes unachievable expectations, demanding
action without regard to cost, risk, or priorities. Some federal stakeholders also question the motivations
of other stakeholders.  From experience, they believe that these  motivations can range from political
ambitions on the part of public officials, to the perceived desire to  raise state revenues through fines and
penalties, to agendas moving  beyond environmental restoration, per se, toward broader  national
disarmament issues.

Furthermore, federal agency officials believe that public participation processes, unless carefully designed
and implemented, often are an impediment to efficient, cost-effective, and scientifically sound clean-ups.
Many federal officials stress the importance of balancing the scientific expertise and knowledge of the
government with the desires  of the  local  citizens.  Finally, public officials  have numerous statutory
obligations that  they must fulfill and these responsibilities, by law, cannot be delegated away to local
citizens or other governmental entities.

Through hearings and reports, Congress has registered its concern with the inability of those involved
in federal facility restoration to reach agreement over clean-up priorities. Congress did pass the Federal
Facility Compliance  Act of 1992 (PL 102-386), which was signed  into law by the President on October
6, 1992.  While the focus  of this Act is clarification of EPA and state RCRA enforcement  authorities
regarding federal  facilities,  its long legislative history  is replete with  criticism  of the delays  and
inefficiencies frequently caused by on-site gridlock among federal  agencies, regulators, and the public.
Although Congress has expressed concern and frustration with the  inability of affected parties to resolve
their differences, it has so far stopped short of extensive intervention or preemption.

Obviously, the  effects of such pervasive  mutual distrust  are not  limited to the inhibition of effective
dialogue and decision-making at the local level.  Rather, these dynamics can affect the relationships of
stakeholders at national levels of regulatory review, decision-making and program management as well.

The result of this mistrust is  that the current decision-making process is  often slow, convoluted,  and
inefficient for all involved.  All FFER Dialogue Committee members are concerned that the  increasing
transaction costs of the current FFER decision-making process may jeopardize our  nation's ability to
achieve its collective clean-up objectives.  Even where agreements are  reached, a polarized atmosphere

-------
sometimes remains that leads to a series of conflicts instead of a consultative, cooperative process that
allows for flexibility and promotes efficiencies and, ultimately, the building of public trust.

1,3.2. Ongoing Disputes Over Statutory Authorities

Another significant barrier arises from differing views of the authorities of state and federal government
as they relate to FFER decision-making.  The most fundamental issues in disagreement arise from the
evolutionary dispute over whether or not federal facilities are subject to state authority under RCRA or
other state environmental laws that affect restoration, as well as the relationship of those statutes to
ongoing clean-ups  being conducted under CERCLA.

Without attempting to specify the details  or  merits of these  legal disputes, states and citizen groups
contend that RCRA  and other  state legal  authorities  entitle state  regulators  to impose  specific
informational and procedural requirements, as well as substantive clean-up requirements, where clean-up
agreements or permits are in place.  This includes participation in funding decisions where federal funds
are insufficient  to meet legally binding agreements.  Federal agency decisionmakers dispute such broad
statutory authority.  Further, they contend  that their departmental secretaries are personally responsible
for both the clean-up of facilities and the proper expenditure of appropriated monies (or in not spending
when monies  are  not appropriated).  Consequently, while  others  may be involved  in  advice  and
consultation, only the federal agency in question has the authority to make the final decisions on spending
for environmental restoration activities at a site.

FFER Dialogue Committee members agreed not to attempt to resolve these fundamentally different legal
interpretations.   However, the Committee believes that the recommendations it has developed will  help
to address some of the mistrust and inefficiencies that surround the FFER decision-making process. And,
in particular, the Committee believes that its recommendations on how  to set FFER priorities in the event
of a funding shortfall are an  attempt to balance carefully the legitimate needs, concerns,  and authorities
of all stakeholders.   When  implemented,  these processes  may go a long way toward lessening the
significance of, if not resolving, these legally based disagreements.

1.4.   OVERVIEW OF THE RECOMMENDATIONS AND SCOPE OF ISSUES ADDRESSED IN
       THIS REPORT

1.4.1. FFER Priority-setting and Decision-making

Federal facility environmental restoration priorities are established and refined at numerous stages and
levels  in  the FFER  decision-making process.   Because of this, the  Committee believes  that the
establishment of more  widely supported  federal  facility environmental restoration priorities  can be
accomplished by improving the overall process by  which federal  agencies share information and involve
affected stakeholders in FFER decision-making. Based on these views, the Committee determined that
its discussion of priority-setting issues should focus on improving the overall process by which FFER
decisions are made,  as well  as an explicit  discussion of how  to set FFER priorities in the event  of a
funding shortfall.

Committee members recognize that there is probably only a relatively  narrow window of opportunity to
find some resolution to the inability of FFER stakeholding interests to deal effectively with each other
before future national fiscal  constraints slow down current progress in federal clean-ups.  Agencies in
charge of  federal facility clean-ups are concerned  that while they generally enjoy adequate funding for

-------
 immediate environmental restoration needs, there is no guarantee that adequate funding will be available
 for all necessary future clean-up efforts. Not all participants agree that fiscal constraints should inhibit
 clean-ups rather than affecting other federal priorities, but all agree that eventually these constraints will
 restrict choices and affect clean-up.

 With this limited time  for progress in mind, the FFER Dialogue Committee analyzed and dissected the
 various phases and specific problems that must be addressed in order to improve FFER decision-making.
 In addition to  an  inhibiting aura of distrust, numerous  more specific problems  became apparent as
 Committee members examined the path of decision-making from the individual contaminated site through
 the labyrinth of decisions affecting the selection and implementation of clean-up remedies and the timing
 and  funding of clean-ups that must take place as part of the national authorization and appropriations
 processes.  These more specific  problems are described  below, as they relate to  the particular policy
 recommendations that have been designed to remedy those problems.

 The recommendations  found below  in their totality reflect an  attempt to create an  open,  public,
 consultative process that originates at the "local" or facility level and extends through the entire federal
 hierarchy  of departments,  agencies,  and  offices of  the Executive  Branch.   The  Committee's
 recommendations describe a consultative process and provide an outline of the procedures and ground
 rules necessary to involve all stakeholders equitably in such  a process.

 The Committee also intends that its recommendations for improving the FFER decision-making process
 should be implemented within all agencies that  are responsible for regulating and cleaning up federal
 facilities in as consistent a manner as possible, taking into account the unique structural and organizational
 attributes of each agency, as well as the unique types of environmental restoration problems faced by each
 agency.

 Where  necessary and  appropriate, this document describes the  Committee's  views as  to how  the
 recommendations should be implemented with  specific  departments  and agencies.   In addition,  the
 document contains recommendations that are addressed to stakeholders other than the federal agencies
 responsible for  clean-up,  including state and  federal regulators,  local  and national public interest
 organizations, and the  members of the general public who are concerned about federal facility clean-up
 issues.

 The Committee's recommendations revolve around three  distinct problem areas,  including:

        •      improving the overall process for disseminating and exchanging information with affected
               stakeholders (Section 2);

        •      improving  the process  for soliciting and obtaining input from affected  stakeholders
               (Section 3);

        •      exchanging information  in the context of the  federal budget process and set priorities in
               the event of funding shortfalls (Section 4).

The  recommendations contained in Section 2, which address ways  for improving the process by  which
the general public can stay  informed about the activities at a particular site, are the most broad.   These
recommendations form the foundation for subsequent recommendations.  Section 3 focuses on setting up
fora for stakeholders who want to be actively involved in providing input into the decision-making process

-------
as it relates to environmental restoration at a particular site.  Section 4 contains recommendations that
will ensure that stakeholders who so wish will receive information on FFER funding decisions which are
made in the context of the federal budget process. The last section also describes an approach for setting
priorities in the event of FFER funding shortfalls, which builds upon and makes use of the consultative
mechanisms that flow from the recommendations contained in the previous sections.

1.4.2. Federal Facility Environmental Restoration

The phrase "federal facility environmental restoration" (FFER) is generally used to refer to the clean-up
of contaminated sites at currently and previously used or owned federal facilities.4 Except in Section
4.6,  this includes  clean-up  activities that are  conducted under CERCLA,  as  well as those that  are
conducted pursuant to the corrective action provisions of RCRA, federal facility agreements, and other
state and federal regulatory requirements.  In addition, the Committee believes that sites that are being
cleaned up under  the  Base Realignment  and Closure  (BRAC) Act should  be  subject  to these
recommendations,  once again with the exception of Section 4.6. Although the specific authority under
which a clean-up is conducted may result in significant differences  in emphasis with regard to the needs
and responsibility of the various affected interests, this report addresses federal  facility clean-up issues
in general.  Elsewhere in this document, the term clean-up is used interchangeably with environmental
restoration.

Each  of the major  sections that follow addresses a discreet FFER policy area, including: 1) the general
process by which FFER information is exchanged with affected stakeholders; 2) the general process by
which affected stakeholders can become involved in FFER decision-making; and 3) the manner by which
information should be exchanged and priorities established in relation to FFER funding decisions.  In each
of these sections the  Committee states explicitly the scope of issues that it intended to address.

       NOTE:  The  representatives: of the Yakima Indian Nation support the recommendations
       of the Committee regarding the scope of issues covered by Sections 2,  3 and 4 of the
       report.   However, they believe that the scope of issues that should be  addressed in
       implementing the Committee's recommendations at DOE's Hanford site should include
       all activities conducted under DOE's Environmental Restoration and Waste Management
       Program. Specifically, they believe that the scope should include waste disposal activities
       at Hanford including those that are not traditionally associated with a RCRA corrective
       action or CERCLA remediation.

In the case of the Committee's recommendations regarding the dissemination and exchange of information
with  affected stakeholders,  the  Committee uses  the  same  general  definition of federal  facility
environmental restoration that is used above. Thus,  the authority under which clean-ups are conducted
is not particularly important as it relates  to these  recommendations.    In addition, the Committee
recommends that its  recommendations regarding information dissemination and  exchange with affected
stakeholders should cover waste management and technology development issues related to environmental
restoration, as well as environmental restoration issues as defined above.
    4  Within the DOD, previously owned federal facilities are those sites that are managed under the
Formerly  Used Defense Sites (FUDS) program.   Within DOE, previously used or owned sites are
managed under the Uranium  Mill Tailings Remedial Action (UMTRA) program and the Formerly
Utilized Sites Remedial Action Program (FUSRAP).

                                               10

-------
The Committee's recommendations for involving affected stakeholders more directly in FFER decision-
making includes recommendations for the creation and use of site-specific advisory boards (SSABs).  For
a variety of reasons, including practicality and efficiency, the Committee believes that it is important that
such site-specific advisory boards should not only be used to address federal  facility environmental
restoration issues, once again regardless of the authority under  which s.uch clean-ups are conducted, but
waste management  and technology development issues that are related to environmental restoration as
well.

In the final section of the report, the Committee addresses two major issues: 1) consultation with affected
stakeholders in relation to FFER funding decisions; and 2) how to set FFER priorities in the event of a
funding shortfall. In the case of the former, the Committee recommends that its recommendations should
cover waste management and technology development issues related to environmental restoration, as well
as environmental restoration issues as defined above.  However, in the case of the recommended process
for setting allocation priorities in the event of  a  funding shortfall, because of the nature of these
recommendations, the Committee decided it was critical to identify the specific FFER programs within
federal agencies under which these recommendations are intended to be applied.

These distinctions regarding the scope of issues addressed  in  this report are explained in more detail
below as they pertain to each of the major sections of the Report.

1.4.3.  Clarification of Commonly Used Terms

Throughout this document recommendations  are made regarding the  roles and responsibilities of various
affected parties, including the regulated agency, the regulating agencies, affected tribes, other affected
stakeholders.  It may be helpful at the outset to clarify what each of these terms signifies.

Regulated Agency - The term "regulated agency," refers to the agency that has the lead responsibility for
cleaning up the site including such agencies  as DOD, DOE, DOI, USDA,  NASA, NOAA, etc.

Regulating Agency(ies') - The term "regulating agencies," unless otherwise noted, refers to the state and
federal agencies that provide regulatory oversight of clean-up  activities at a site.  Typically, this will
include a combination of the state's hazardous waste agency and/or the office of the attorney general, and
EPA  and the Department of Justice (DOJ).  Two  other governmental entities may also play  regulatory
roles — tribes and local/municipal  governments.  In the case of localities, since local regulations typically
do not relate directly to federal  facility environmental clean-ups, the Committee recommends that local
governments be treated like any other affected stakeholder, rather than as a regulator.  To the extent that
local  regulations do pertain to site-level federal facility  environmental restoration activities, local
governments  should be considered to be subject to the same  recommendations for state and federal
regulators (see especially the discussion  of  model approach to the  formation of site-specific advisory
boards in Section 3  and the allocation process in Section 4).

Affected Tribes - In the case of tribes,  the Committee's recommendations attempt to  account for a
complex set of relationships that includes  at least four distinguishable bases for tribal interests in federal
facility environmental restoration activities.  These include:

1)     Instances where tribes  serve  as regulators of FFER activities that take place on tribal lands
       through their own laws,  which they establish as sovereign nations, or as a result of the delegation
                                               11

-------
        of federal statutory authority to the tribe through such statutes as RCRA, Clean Water Act, Clean
        Air Act, etc.5

2)      Instances where tribes have an interest in FFER activities that is derived from rights that are
        specified in treaties with the U.S. Government.  In some instances, these treaty rights may result
        in legally binding obligations on the part of the  U.S.  Government that must be accounted for
        during the conduct  of federal facility environmental restoration activities.   Typically these
        interests will pertain to hunting, fishing, and  religious freedom rights on ceded lands upon which
        there exists a federal facility.

3)      Instances where the interest of tribes in FFER activities are derived from the rights and privileges
        that  are  specified in such  statutes as the Historic  Preservation  Act,  the Antiquities Act, the
        American Indian Religious Freedom Act, and other aspects of the trust relationship between tribes
        and the U.S. Government.

4)      Instances where tribes do not have any special  interests that  are derived from their status as
        sovereigns, or through treaties, or any federal statute, but nevertheless are still impacted by and
        concerned about federal facility environmental restoration activities. In these instances tribes and
        tribal members have interests that are equivalent to those of any other affected stakeholder.

As discussed in Sections 3 and 4 of the report, if tribes have interests in FFER activities that are derived
from their laws as sovereign nations, the delegation of federal regulatory authority,  or from treaty or trust
relationships, their role in FFER decision-making should reflect the nature of these special relationships.
To the extent that tribes and tribal members interests are not derived from any such special relationship
(as per #4 above), tribes and  tribal members should be treated the same as any other affected stakeholder.

Other Affected Stakeholders - There are a wide variety of other affected stakeholders who are impacted
by or concerned about federal  facility environmental restoration activities. Although such stakeholders
exist at both the national and local levels, this report focuses primarily on those affected stakeholders that
exist at the local, site-specific level (particularly with the recommendation for the establishment of site-
specific advisory boards). These local stakeholders are defined as individual  residents that live in the
communities or regions within which  a site is located or  representatives of citizen, environmental, and
public interest groups whose members live in the  communities or regions  within which a site is located.
It also includes workers or representatives of workers involved in or affected by site clean-up operations
and  elected  and appointed local government officials to the extent that they do not serve as  regulators
of site-level federal facility environmental restoration activities.
    5  Although the delegation of federal  regulatory authorities to tribes for overseeing environmental
restoration activities has not yet occurred, it may occur in the near future.

                                                12

-------
2.0.   RECOMMENDATIONS FOR IMPROVING THE PROCESS OF DISSEMINATING AND
       EXCHANGING INFORMATION WITH AFFECTED STAKEHOLDERS

2.1.   BACKGROUND AND STATEMENT OF NEED

From the public's perspective, there has been some reluctance in the past on the part of federal agencies
to provide information on federal facility environmental contamination problems and restoration efforts.
Issues of access to information, including relevant classified information, the lack of clear ground rules
for gaining access  to information,  and the cumbersome and  time-consuming processes to  retrieve
requested information have all exacerbated the problem.  Additionally, information dissemination and
exchange efforts have sometimes been perceived as more of a one-sided public relations approach rather
than the interactive dialogue that stakeholders in the decision-making process desire.
From the agencies' perspective, the public has sometimes requested such voluminous  quantities of
information that it  would have been difficult, if not impossible,  to  provide  an  adequate  response,
particularly given limited resources.  This desire for information and involvement on  the part of the
public was  often seen as interfering with the agency's ability to meet its mission objectives.

Today, it is generally recognized that  federal  agencies have important  environmental obligations in
addition to their other  missions and that  disregard for these obligations is  shortsighted  and often
expensive in the long run.  In response, these agencies have implemented public  participation and
information dissemination and exchange efforts.  In many cases, these efforts have been successful and
the recommendations in this report attempt to promote and build upon these successes.  In other cases,
there are still improvements to be made in promoting information such efforts.  In particular, stakeholder
concerns regarding current agency information dissemination and exchange efforts fall into three areas:

       •      Stakeholders' opinions are often solicited late in  the  process after the governmental
              entities have concluded their investigatory work;

       •      The extent, timing, and scope of current information dissemination and exchange efforts
              are inconsistent between sites and between agencies; and

       •      Stakeholders perceive that requests for information are treated  by government officials
              as burdensome and an impediment to  management rather than as a right of citizenship.
2.2.    DEMONSTRATED SUCCESSES AND PRINCIPLES OF EFFECTIVE
       INFORMATION DISSEMINATION AND EXCHANGE

In the last several years, many agencies have dramatically changed the way they do business by making
environmental restoration data widely available to the public early  enough to ensure stakeholders the
chance to have an impact on decision-making.  For examples of this, see the box below.

In reviewing the successful use of methods for promoting information dissemination and exchange, the
Committee believes there are several important principles for ensuring the success of these efforts. These
include:

1)     Federal agencies have an obligation to take the initiative in ensuring that information is provided
       to all  interested parties within applicable regulatory, resource,  and budgetary constraints.

                                             13

-------
2)     Well  developed  information dissemination and  exchange processes should ensure the timely
       release of information of interest to stakeholders and provide the basis for informed involvement
       in decision-making.  This should hold true for any environmental restoration site, whether it is
       on the National Priorities List (NPL) or not.

3)     The information dissemination and  exchange  process  must be consistent with  Freedom of
       Information  Act (FOIA)  principles,  providing  full  disclosure  of  available  information.
       Classification of information on the basis of national security concerns should not be used to bar
       the flow of relevant environmental restoration information where security/classification issues no
       longer exist.  Such information should be declassified.

Overall, an open,  free flow of information will enhance the credibility of environmental restoration
actions proposed by federal agencies and may allow the stakeholders to gain a sense of ownership of the
final decisions.
            DOE PROGRAMMATIC ENVIRONMENTAL IMPACT STATEMENT
                      AND THE DOSE RECONSTRUCTION PROJECT

         The public participation program for the DOE Programmatic Environmental Impact
         Statement (PEIS) exceeded the procedural public involvement requirements mandated
         by NEPA. Some of the innovative public participation activities undertaken  in the
         PEIS program included the release of documents not usually distributed for public
         comment (e.g., the Implementation Plan), the distribution of information sheets on
         particular topics, and the use of innovative interactive workshops in addition  to the
         traditional public hearings mandated by NEPA.

         In another case, the director of DOE's Pacific Northwest Laboratory announced an
         open-door policy  for  anyone interested in  information related to  the  Hanford
         Environmental Dose Reconstruction Project.  The decision was made in response to
         stakeholder demands for greater access to preliminary information.  This open door
         policy includes the opportunity for stakeholders to visit laboratory offices in order to
         review environmental computer codes and any other related project information.
2.3.   RECOMMENDATIONS

2.3.1.  Overview and Scope

The Committee recommends three improvements to the current process for disseminating and exchanging
information with affected stakeholders including:

       1)     developing agency information dissemination policies;

       2)     encouraging affected stakeholders to portray accurately the status of documents or other
              information that they receive in draft form; and
                                              14

-------
       3)      establishing  a  central point of contact within agencies for assisting in disseminating
               information.

The recommendations  contained in this section are intended  to apply broadly to all FFER activities,
regardless of the statute under which they are conducted.  For example, the recommendations that are
presented in this section could be applied to clean-ups conducted under CERCLA, RCRA, BRAC, FUDS,
UMTRA, and FUSRAP, as well as other state and federal requirements, as described in Section 1.4.2.

2.3.2. Information Dissemination Policy

To  address deficiencies and inconsistencies in the present process, the Committee agrees that federal
agencies  need to take proactive measures to involve stakeholders and to respond effectively to requests
for information. To this end, the Committee first and foremost recommends that each agency work with
stakeholders to develop policies or procedures delineating the process and timetable for disseminating
environmental  restoration related  information,  including  information prepared  by  contractors and
government employees.

All Committee members agree that  the policies should include, at a minimum, detailed  language to
implement the following provisions:

a)     Make  environmental restoration  documents that are considered deliverables  under
       CERCLA Federal Facility Agreements (FFAs), RCRA corrective action permits, or other
       regulatory instruments available to the public at the same time that the agency submits
       these documents for formal review to  state, tribal, and/or federal regulators.

b)     Regarding the release of all other FFER  related information, define the different types
       of data and information that the agency produces and relies upon in the FFER decision-
       making process and establish definitive time frames for release of each  category of data.

c)     On a timely basis, provide information that federal agencies use in, or that is pertinent
       to,  environmental restoration decision-making.  To the extent that the release of such
       information is restricted because it is classified or exempted from FOIA, the agency will
       either  promptly declassify or reclassify  the material  such  that it  can be released, or
       explain why it cannot be released.

d)     Disseminate information, interpretations, and proposed direction to advisory groups such
       as site-specific  advisory boards (SSABs), Technical Review Committees (TRCs),  and
       recipients of Technical Assistant Grants (TAGs) to ensure effective involvement in the
       evaluation of options.

e)     Inform agency personnel responsible for environmental restoration of the agency policy
       on information flow. The policy should emphasize the importance of public participation
       and the need for timely, substantive responses to maintain public credibility.

The Committee recommends that such guidance be sufficiently detailed to:  1) ensure that individuals at
all levels in the departments clearly  understand the guidance; 2) provide  the public with  the support
necessary to clarify the scope of their information requests in  the event that any conflicts arise; and 3)
include a mechanism to ensure that the established time frames and policy provisions are  met.

                                              15

-------
2.3.3.  Citizen Use of FFER Information

The Committee recommends that public participants should portray accurately the status of documents
or other information that they  receive in draft form.   In particular, the  public has an obligation to
recognize and note the preliminary nature of draft materials and to use and distribute these documents
within this context only.

2.3.4.  Central Point of Contact Within Agencies

The Committee recommends that regulated agencies should designate central points of contact to serve
as visible and accessible advocates of the public's right-to-know.  The role of this contact is  twofold.
The first is to investigate and attempt to  resolve complaints promptly from individuals or groups who
assert that the agency is not responding to their requests for information in a timely or complete manner.
The second purpose is to identify -- through the effort to  resolve citizen grievances  - deficiencies in the
information-handling functions  and policies  of the agency and, when appropriate, suggest changes to
improve both the timeliness and quality of responses.

Agencies may choose to implement this recommendation  in different ways to account for the differences
in the magnitude of clean-up problems and the different structures of the organizations.  Please refer to
the boxes below regarding proposed implementation techniques at various agencies.

        NOTE: Although all Committee members agree that the proposal to establish a central
       point of contact within  agencies is a positive step, several members expressed concern
        that the Interim Report does not go far enough to ensure that this central point of contact
       plays a productive role.  In particular, many participants support the idea that the larger
        agencies instead establish an  independent ombudsperson.  These Committee members
        advocate that an ombudsperson who would serve as an independent public advocate could
        offer  more accountability  to the  agencies  in  a  manner  that  is  quicker, more
        comprehensive, and more credible than having an internal agency official serve this role.
                                DEPARTMENT OF DEFENSE

         DOD is in the process of creating regional environmental coordination offices that
         would serve a number of coordinating functions among all the military services
         and DOD installations within an area that corresponds to the EPA regional offices.
         These "offices" are intended to streamline duplicative functions and improve
         communication on environmental related matters not only among the services, but
         also with environmental regulatory agencies and the public.  They would serve as
         central points of contact to raise and resolve matters related to the inability to gain
         access to relevant data associated with clean-up actions.
                                               16

-------
                        DEPARTMENT OF ENERGY

The Office of Environmental Restoration and Waste Management (EM) has
recently developed a public participation policy to ensure that EM provides
opportunities for meaningful, substantive, and early participation in its activities
by stakeholders and interested members of the public.  To help implement this
policy, assistant managers for EM, or their designees,  are being identified as EM
public participation liaisons.  Their responsibilities include:  coordinating site
public participation activities to ensure a coherent,  comprehensive, coordinated
program so that the public is not confronted  with multiple, overlapping,
disconnected participation opportunities; identifying resource and training needs;
helping to ensure that site public information and education materials support and
are compatible with public participation activities; and  interacting and coordinating
with headquarters on public participation activities.

To respond to the recommendation of the FFER Dialogue Committee, DOE
proposes to expand the role  of the public participation  liaisons to serve as the
central point of contact for EM information requests at the field-level, and be
charged with the responsibility to provide stakeholder groups with requested
information in a timely fashion to facilitate their involvement in EM decision-
making.  Should stakeholder groups experience problems with accessing
information through the field EM public participation liaisons, the director of the
EM  Office of Policy and Program Information should be notified and he or she
would then take the necessary steps to ensure that DOE fulfill all reasonable
information requests given regulatory, budgetary, and policy constraints.
                    DEPARTMENT OF THE INTERIOR

DOI has nine Regional Environmental Officers (REOs) located throughout the
United States who serve to coordinate with field offices of the nine DOI bureaus,
the EPA, state and local governments, and the public.  These REOs serve as field
representatives of the Office of the Secretary of the Interior to help resolve
disputes, including dispute over FFER information dissemination issues, and to
elevate issues to senior DOI management.
                    DEPARTMENT OF AGRICULTURE

The USDA-Forest Service has environmental engineers located at nine Regional Offices
throughout the United States who have designated responsibility for environmental
pollution prevention, control, and abatement.  The Forest Service is in the process of
designating an individual in each Region who will have specific responsibility for
coordinating CERCLA clean-up activities.  Other USDA agencies with smaller programs,
such as the Agricultural Research Service, have designated an individual at their
headquarters level as the contact point for environmental restoration activities.
                                     17

-------
2.4.    IMPLEMENTATION STRATEGIES

To  provide an effective, responsive means of ensuring that public information needs are met, agencies
should consider implementing some combination of the following options:

1)      With regard to providing a  single point of contact at each agency for FFER related
        questions, establish an "800"  number for citizens to call and request information on
        environmental restoration projects may help in this process.

2)      Develop and maintain a mailing list of interested parties for ea:h facility.

3)      Hold meetings  to inform the public  about the  initial discovery  of contamination  at a
        facility.

4)      Where substantial public interest exists, hold meetings at the formative stages of FFA negotiations
        when the first conceptual outline of the technical requirements is developed. Agencies may also
        hold additional meetings  at later stages  in the negotiations when public involvement can still
        provide useful input to the negotiations.  These  meetings should also be used to update citizens
        on negotiations and clean-up activities.  In addition  to announcing public meetings in the local
        paper, individuals on the mailing list  should be notified.

5)      Develop annual bulletins that provide updated information on progress at a site or group
        of sites. Bulletins should be distributed to individuals on the mailing list and in response
        to requests for information  from the public.  Depending upon  the particular  public
        interest at an installation, the facility may  develop special, more in-depth "reports" for
        significant events or milestones. In some cases, a regular newsletter may be appropriate.

6)      Make  technical documents  available on  loan  from  the  agency,  when  possible.
        Administrative records should also be available through public reading rooms in local
        libraries.   If a large number documents exist in  the administrative records for  a  site,
        indices,  along with microfiche and/or computer disk storage  and access, should be
        available  in public reading rooms.

7)      Where  practicable,  have the government  employees  responding to  requests  for
        information contact the requesting parties to facilitate the process.  A direct conversation
        should help refine and focus the request. This will help ensure that the requesting party
        receives the  actual information they are  seeking and may help minimize the disruption
        and demands upon government resources.

The above recommendations are intended to  improve the  current processes for  exchanging information
with interested parties.  The Committee  notes that these measures should ensure that  any citizen or
stakeholder can receive a base level of information at any  site, regardless of its size or potential hazard,
on a timely basis.

The following section focuses on  establishing fora for stakeholders who desire to receive more detailed
information on the events at a site and to be  actively involved in providing input into decision-making.
The Committee intends for these recommendations to be most crucial at large or particularly controversial
or difficult sites where citizens want to be intimately involved with the ongoing clean-up  efforts.

                                                18

-------
3.0.    RECOMMENDATIONS FOR IMPROVING THE PROCESS OF SOLICITING INPUT
        FROM AFFECTED STAKEHOLDERS

3.1.    BACKGROUND AND STATEMENT OF NEED

As federal agencies have instituted massive environmental restoration programs designed to investigate
and remediate contamination at their facilities, there has been a growing desire by those affected by these
clean-up efforts (who are referred to here as affected stakeholders) to have a greater role in the clean-up
decision-making process. This desire for a greater role is a result of many factors, including an  increased
awareness of the environmental and health effects of contamination at federal facilities sites, a recognition
of the complexity and scientific uncertainty surrounding many decisions at sites, and a mistrust of the
government's intentions to consider the concerns of local citizens  sufficiently.

In  response to  this concern for a  greater role in  the  decision-making process, various  statutory,
regulatory, and other mechanisms have been established to help solicit input from affected stakeholders.
Historically, however, these opportunities for citizen involvement have been  inconsistent and have not
necessarily provided for a meaningful dialogue between participants.  Among  the issues of greatest
concern to these stakeholders are:

1)      Affected stakeholders have not been  substantively  consulted  in the early  stages of
        decision-making.  At sites where  FFAs have been  negotiated,  for example,  public
        comment has typically been solicited  only after the  signing agencies have agreed to
        circulate a draft agreement.  The perception is that the public is consulted only after the
        key decisions have been negotiated by the agencies.

2)      The laws governing the generation and disposal of wastes  did not contemplate problems
        of  the complexity and scale that exist at federal facilities.  The public involvement
        mechanisms in these  laws tend to focus on the specific proposal  at  issue, and  do not
        allow  consideration  of how  that proposal may relate to other proposed or existing
        activities.

3)      Compounding the problem of late public involvement in decision-making is the lack of
        opportunity  for meaningful dialogue in the formal comment and response process used
        in the regulatory decision-making process. Some perceive  there is a strong tendency for
        this process to serve the needs of agencies to defend decisions  rather than incorporate
        common or insightful concerns into decision-making.  Likewise, it does not allow for an
        interactive and substantive exchange that promotes better understanding and consensus-
        building.

4)      Finally, the burgeoning number of public involvement opportunities — including NEPA,
        those required  by regulators in permitting, FFA processes,  and  other voluntary and
        required facility-sponsored events - is in many instances overwhelming  and dissipates
        the public's ability and interest to participate effectively.  There is  a need to  focus,
        coordinate, and streamline, where possible, the public involvement process especially at
        larger sites involving literally dozens of permitted units.
                                              19

-------
The net result is that many stakeholders consider the current methods for soliciting input to be too late
in the process, inefficient due to overlap with other efforts, and ineffective because the result is often a
one-way communication instead of a two-way dialogue.

3.2.   DEMONSTRATED SUCCESSES OF SITE-SPECIFIC ADVISORY BOARDS

Site-specific advisory boards (SSABs), as the term is used in this report, are independent public bodies
established to provide policy and technical advice to the regulated and regulating agencies with respect
to key clean-up decisions.  The Committee believes that such boards can improve the decision process
by:

1)     Providing a setting for direct,  regular contact between agencies and  a diverse set of
       stakeholders;

2)     Providing a forum for stakeholders and agencies to understand the competing needs and
       requirements of the government and the affected communities;

3)     Providing  a  forum for discussing  citizen  issues and  concerns,  thus enabling the
       development of a more complete and satisfactory plan or decision;

4)     Enabling citizen review and the evaluation of plans and their technical adequacy in more
       depth than is possible in most single opportunity public participation efforts;

5)     Permitting a  more  detailed consideration of issues than is possible as a result of the
       minimal legal requirements identified in various state and federal laws; and

6)     Broadening consideration of issues to include values as well as facts.

For these  reasons, both citizens and federal  agencies will benefit from the creation  of SSABs.  Such
boards provide  unique opportunities for public participation  in the decision-making process  for
environmental restoration, either not found or not fully available in more traditional fora such as public
hearings or public meetings.  There have been some exceptional examples of circumstances where the
public  has been successfully allowed and encouraged to advise the decision-making process.  The
information in the box below provides an example of the effective use of a site advisory board.

3.3.   RECOMMENDATIONS  REGARDING THE ESTABLISHMENT OF
       SITE-SPECIFIC ADVISORY BOARDS

3.3.1.  Overview and  Scope

In order to realize the benefits of citizen/federal agency interaction, the Committee believes a process is
needed that accomplishes the following goals:

       •      consistent opportunity for involvement;

       •      regular, early, and effective public participation in federal clean-up programs;  and

       •      consolidation of the many public involvement initiatives addressing clean-up.

                                              20

-------
                                   THE MOFFETT MODEL

         Moffett Naval Air Station, Pacific headquarters for the Navy's subchasing P-3C
         "Orion" aircraft, sits in the heart of Silicon Valley, at the southern edge of the
         San Francisco Bay. Its 26 Installation Restoration Program sites include a
         massive plume of shallow groundwater contaminated  with TCE and other volatile
         organic compounds. The plume, shared with electronics industry Superfund sites
         just to the south, threatens local drinking water supplies as well  as the Bay and its
         wetlands.

         The Navy first discovered contamination in 1983, and the base was added to the
         NPL in 1987.  In 1989-1990, when Moffett first negotiated its interagency
         agreement with state agencies and the EPA, community groups,  area newspapers,
         and the other Superfund parties called the Moffett timetable too  slow.

         In early 1990, the base commander, Captain Tim Quigley, established  a Technical
         Review Committee (TRC), composed of Navy personnel, regulators, and
         representatives of the local community, including the Silicon Valley Toxics
         Coalition  (SVTC).  Quigley established an active community relations  program,
         disseminated fact sheets, and shared more detailed technical information upon
         request.

         Through the TRC and  other community relations activities, local residents and
         their representatives gained respect for  the Moffett clean-up program, but the
         SVTC  and others remained critical of the remediation schedule.  They  took their
         case to the press, elected representatives, and Defense Department officials.
         Informed  by participation in the TRC, they focused on the so-called "regional"
         TCE plume.

         In late 1991, after Moffett was approved for closure,  the Navy proposed dividing
         Moffett into six distinct operating units. Clean-up of the main plume,  the highest
         priority operating unit, was accelerated three years.  This solution has  won praise
         from all parties.  The SVTC believes that the Moffett experience shows that if you
         give activists a "seat at the table," they can participate effectively in the setting of
         clean-up priorities.  SVTC has applied to EPA for a Technical Assistance Grant to
         aid in its involvement in the clean-up process.
The Committee recommends that, as an important step toward achieving these goals, the agencies should
establish and make use of SSABs, where appropriate and practicable.   The Committee believes that
SSABs will improve the effectiveness and consistency of public involvement at federal facility sites  by
providing focused and timely advice to the regulated and regulating entities on environmental restoration
activities occurring at  the site level.  The recommendation is to have, at most, one SSAB at any facility
or group of facilities to help coordinate advisory efforts and decision-making initiatives.
                                              21

-------
The Committee wishes to make clear that SSABs should be used to complement rather than duplicate or
supplant broader site level FFER public involvement initiatives.  Nor is it the Committee's intent that
SSABs should be established at all federal facilities or sites where clean-up activities are taking place.
Rather, such boards should be established on an as-needed basis, as is described below. In addition, such
boards should in no way hinder or impede the effectiveness of broader public involvement activities,
including those that are required by law and those that are not.  Not every affected stakeholder will have
the time or inclination to participate in SSABs and the Committee believes that it is vitally important that
all members of the public be afforded their full rights  and privileges with respect to public involvement.

The following recommendations detail when SSABs should be established and propose a model approach
to implementing this recommendation. The Committee believes that it is essential for the federal agencies
to work closely with  local  communities  to  ensure  that SSABs reflect and  are responsive to local
community needs and concerns.  The Committee  recognizes that the recommendations in this Interim
Report will need to be tailored to meet the needs of each federal site and its local stakeholders.

The recommendations contained in this section are intended to apply broadly to all FFER activities,
regardless of the statute under  which they are conducted.  For  example, the recommendations that are
presented in this section could be applied to clean-ups under CERCLA, RCRA, BRAC, FUDS, UMTRA,
and FUSRAP, as well as other state and federal requirements, as described earlier in Section 1.4.2.

3.3.2.  When Site-Specific  Advisory Boards Should be Established or Restructured

The Committee recommends that agencies form SSABs at sites  where no advisory committee currently
exists and where there is a need as evidenced by:

        •      an  affected local, state, tribal or federal government entity requesting the establishment
              of an SSAB; or

        •      at least fifty residents of the community or region in which  a  site is located signing a
              petition requesting an SSAB.

Where site advisory boards already exist, the Committee intends for its recommendations  to build upon
existing groups and not to supplant them, particularly where they have proven successful.6

State and federal agencies will need to assess their  existing public participation initiatives addressing
environmental restoration issues to determine the  extent to which they operate according to the model
described  below,  and then implement the recommendations where  needed.  For example, where  an
advisory board, committee, or  group currently exists for addressing clean-up issues,  agencies may need
to increase the scope of issues to be addressed by the group, add members to  ensure representation of
a wider  constituency, change the way in which the  group interacts with the  general public, etc., in order
to be consistent with these recommendations. When more than one group exists, agencies should consider
consolidating their activities.

Regardless of whether or not a site advisory  board currently exists  at a site, the Committee does not
intend for the implementation of SSABs to be a replacement or substitute for current  public involvement
activities such as community relations plans under CERCLA or the legally required  public involvement
in the Record of  Decision (ROD)  process.    SSABs would be  complementary  to  existing public
    6  Currently, only the DOD is required by law to establish site advisory boards. See Appendix D
for more detailed information regarding these statutory requirements.

                                              22

-------
involvement requirements.  As such, they are not intended to hinder the continued ability of citizens to
comment and participate individually or in groups of their own selection.

3.3.3. Model Approach to the Formation of SSABs

The following model approach to the formation of SSABs is  intended to serve as an example for how to
establish SSABs at sites where they do not currently exist and as guiding principles for how existing
advisory groups should be revised to be consistent with these recommendations. These recommendations
build  upon the lessons learned from both the successes and failures of other site advisory boards.  In
addition, the Committee believes that its recommendations are sufficiently broad to permit flexibility for
each agency and the affected communities to adapt them  to their own circumstances.

       a)     Charter

A charter outlining the mission and duties of the SSAB should be developed at each  site.   It should
provide for SSABs to advise both the regulated and regulating agencies on key policy and technical issues
and decisions related to environmental restoration at the site.  The Committee discussed the potential
application of the Federal Advisory Committee Act (FACA) to the recommended SSABs.  The Committee
believes that the approach  that it has taken is consistent with the spirit of FACA  to  create advisory
committees that are balanced and subject to an open and  fair process.  Because of this,  and in order to
facilitate the implementation of these recommendations and  avoid  unnecessary administrative burdens,
the Committee does  not believe that it is  necessary or prudent to charter SSABs as federal advisory
committees. This is consistent with  the current practice with DOD's Technical Review Committees and
numerous other site-level efforts where advice is given to federal agencies.

       b)     Scope

In all  federal  departments, environmental restoration issues are often integrally  linked with  waste
management issues.  Also, the people within the communities surrounding federal facilities that are
concerned about environmental restoration issues are also  likely to be the same people who are concerned
about other  environmental  management issues at that  site.  The  Committee recognizes  there may  be
pressure  to  use  SSABs as a  "sounding board" for site-level environmental issues that  go beyond
environmental restoration.  The Committee believes it is vitally important that SSABs  not become the
general community advisory  board for  any and  all  environmental or  other  issues of concern  to
communities that surround federal facilities. For example, the Committee believes SSABs should not be
used to address land and  wildlife management issues that are not related to environmental restoration.
However, the Committee  does recommend  such Boards be used to  address waste management and
technology development issues that are related to environmental restoration.

In focusing on environmental restoration, the boards should provide advice on issues related to:

       •     identifying clean-up  activities and projects (including those necessary to meet regulatory
              requirements such as milestones in FFAs);

       •     tracking progress on those activities/projects (as per the recommendations contained in
              Section 4);

       •     providing information and perspectives  on clean-up priorities;
                                              23

-------
        •      addressing important  issues related to clean-up, such as land use, level  of clean-up,
               acceptable risk,  and waste management and technology development  issues related to
               environmental restoration; and

        •      developing clean-up strategies.

The SSABs should have the discretion to hear presentations on the social, economic, cultural, aesthetic,
and worker health and safety effects of environmental restoration and waste management and technology
development  issues related to environmental restoration. In addition, the Committee agrees that SSABs
may hear presentations on other environmental  management decisions that SSAB members regard as
relevant and appropriate.

       c)      Role of Regulated and  Regulating Agencies

As stated above, the SSAB is intended  to be a forum through which  advice  can be given to both the
regulated and regulating agencies on environmental restoration and waste management and technology
development  issues related to environmental  restoration.7  As such, senior representatives  of both
regulated and regulating agencies should  serve as "ex-officio" members of the SSAB. The term ex-officio
is used here to imply that  representatives of these agencies should attend  SSAB meetings and  participate
in SSAB discussions.   However,  because the advice to be given by the  SSAB will be directed at their
agencies, these agency representatives should not take part in any decisions about  what  advice should be
given.8

The regulated agency should serve as the host of the SSAB and  should provide administrative  assistance,
meeting facilities, etc.,  as necessary. Also, because of the important role that operations and maintenance
(O&M) and  environmental restoration  contractors often play in actually conducting environmental
restoration activities on behalf of regulated agencies, agencies should include contractor representatives
as part of their team. However, because contractors serve as subordinate agents of the regulated agency,
the Committee agrees that contractor participation in SSAB discussions should never serve as a substitute
for the participation of senior representatives of the regulated agency.  Contractor salaried  employees
(i.e., those in managerial  positions) should not serve as members of SSABs.

       d)     Membership and Membership Selection  Process

The Committee recommends  that SSABs  should  reflect  the  full diversity of views in  the  affected
community and region and be composed primarily of people who are directly affected by site clean-up
activities. Thus, in addition to regulated and regulating  agencies serving as  ex-officio members, the
    7  As used here and elsewhere in this document, the terms regulated and regulating agencies refer to
those agencies that  are  either regulated  or serve as regulators  regarding  site level  environmental
restoration activities.  In the case of regulating agencies, the Committee assumes that this will principally
include state and federal  regulators and, where applicable, tribal regulators.

    8   Similar to the recommended role of state  and federal regulators of environmental restoration
activities, where any other  government agencies  participate on SSABs they should operate  in an ex-
officio capacity (by not taking part in SSAB decisions about what advice should be given) on matters in
which they serve as regulators.

                                               24

-------
Committee recommends the following affected stakeholders be given primary consideration for SSAB
membership:

        •      individual residents that live in the communities or regions in which a site is located;

        •      representatives of citizen, environmental, and public interest groups whose members live
               in the communities or regions in which  a site is located;

        •      workers or representatives of workers involved in or affected by clean-up  operations at
               the site, with a priority for clean-up and production workers who are currently employed
               at the site; and

        •      representatives of Indian Nations and other indigenous people that have treaty or statutory
               rights that are affected  by clean-up activities at the site.

The Committee recommends that in order to address environmental equity concerns, special efforts should
be made to provide notice and opportunity to participate for people who are or have historically been
disproportionately impacted by site contamination.

In some cases, potentially responsible parties (PRPs) from the private sector that are directly involved
in or affected  by site clean-up  activities could be added as  ex-officio (non-voting) members at the
discretion of the SSAB.  The Committee believes that participation on an ex-officio basis is appropriate
because PRPs may stand to benefit or gain financially  from decisions of the SSAB.  For example,  at
Moffett Field  (which is described above) contamination from sites owned by private sector PRPs has
mixed with the ground water plume from Moffett Field.  Because clean-up activities at these private sites,
from  a technical  perspective,  must be  addressed  in conjunction with  Moffett Field clean-up activities,
these PRPs can be said to be "affected by" the federal facility clean-up efforts.  In other cases, companies
have been named as PRPs for  the actions they took on federal facilities,  such as in  the case of Shell Oil
at the Rocky Mountain Arsenal.  In these cases, such PRPs can be said to be "directly involved in" the
clean-up activities at the site.  In both cases, these private sector PRPs should be distinguished from the
O&M and environmental restoration contractors for the regulated agency, whose proper role is described
in Section 3.3.3.c) above.

The Committee recommends that  the size  of the boards should be limited to promote efficiency and
encourage participation, while also ensuring that  the major stakeholders or groups of stakeholders are
adequately represented.  With some exceptions, given the wide variety of circumstances,  the Committee
believes the optimum size for  SSABs will  typically  be 10-20 people,  not  including the ex-officio
members.  Every effort  should  be made to include divergent interests and viewpoints, regardless of
technical expertise. The Committee recommends that appropriate qualities for an SSAB member include:

        •      an ability to focus on environmental restoration issues irrespective  of any interest in or
               concern over other issues that are unrelated to environmental restoration; and

        •      a willingness to devote the time necessary to serve on  a board.
                                               25

-------
In order to ensure confidence and trust in the establishment of SSABs fhat represent the full diversity of
views within a community on FFER issues, the Committee recommends an SSAB membership selection
process that has the following features:

1)      Regulating agencies shall actively and publicly solicit nominations for SSAB  membership from
        interested individuals and organizations, ensuring that ample notification is given to those with
        an  active interest or obvious stake  in environmental restoration activities at the site.9   Such
        notification should also be given to national organizations that have expressed an interest in that
        agency's environmental  restoration  program.10   Interested  organizations  and  individuals,
        including those whose nomination has not been solicited by the regulating agencies, should submit
        nominations  for  SSAB membership to the regulating agencies.  Furthermore, the regulating
        agencies shall solicit nominations from the governor, local congressional representative(s), state
        legislators, and affected county, city,  and tribal governments.

2)      Based on the criteria set forth above, the regulating agencies should review all nominations,
        submit a proposed  list  of SSAB members to the regulated agency, and make this list publicly
        available.  Furthermore,  this list should be mailed to  all who were  nominated or submitted
        nominations.

3)      The regulated agency shall accept the recommended list of SSAB participants unless it determines
        that the list does not ensure a sufficient diversity of viewpoints or an appropriate balance of
        affected interests.  Decisions of the regulated agency to  accept or reject the proposed list must
        be  made and explained openly and publicly.  Once again,  all who have been nominated or
        submitted nominations as per Step 1 should be notified of the decision of the  regulated agency.

4)      If the regulated  agency rejects the proposed list, the regulating agencies, with the advice of
        federal,  state, tribal, and local government representatives,  shall propose, and make publicly
        available, an alternative list that addresses the specified imbalance or lack of diversity.

5)      If SSAB membership selections issues have  not been resolved after step 4, the regulating and
        regulated agencies will refer the matter to higher levels of authority within their agencies for final
        resolution.

SSABs, once established, should develop procedures for adding, replacing, or removing Board members.
In doing so, the SSAB should consider carefully the  need to assure that the Board does not become too
large so as to be unmanageable and that the  full  diversity of views in  the community/region are  fairly
represented.  Procedures for adding new members should give special emphasis to:

        •      interests  that, in the view of the SSAB, are not adequately represented at the time of the
               initial formation of  the SSAB; and
    9   The  Committee believes that ample notification can best be accomplished  by the regulated,
regulating, and affected agencies and institutions jointly pooling their resources to develop a contact list
for purposes of soliciting nominations for SSAB membership.

    10  Notification  of national organizations is for the purpose of allowing those organizations  to
themselves notify any local members who may have an interest in participating on an SSAB.

                                               26

-------
        •      expressions of new interests that may not have existed or were not considered at the time
               of the initial formation of the SSAB.

Notwithstanding the recommended role of the  SSAB on  these matters, it remains the obligation of all
participants — including the regulated and regulating agencies — to ensure the membership of the SSAB
is composed  of a manageable number of people,  is properly balanced, and adequately  represents the
diversity of views within the affected community.

        e)      Interaction with the Public

As noted above, SSABs operate in a larger context in which members of the public, who may not have
the time, resources or inclination to participate on an SSAB, must be kept adequately informed of and
involved in clean-up decisions that affect their lives and their communities.  As such,  SSABs should
conduct their activities in a manner that complements rather than duplicates or supplants broader public
involvement efforts, some of which will be legally required. To this  end, members of the SSAB, along
with the participating regulated and regulating agencies, should make every effort to coordinate the timing
and focus of SSAB activities with the need for broader public involvement activities.  The Committee
encourages regulated and regulating agencies to use the SSAB to obtain advice as to how and when such
broader public involvement activities should  be conducted.  In addition, in order to maintain trust and
accountability, interested members of the public should be notified of SSAB meetings, SSAB meetings
should be open to the public, and some type of record documenting the meetings should be made
available to the public.  Finally, SSABs should provide opportunity for public comment at their meetings
and should make every effort to respond to both written and verbal comments that are submitted to it in
a timely manner.

       0      Operating Procedures

At the establishment of each SSAB, SSAB members as a group should develop appropriate ground rules
and operating procedures to allow for the efficient and productive operation of the group.  Each SSAB
should consider establishing procedures regarding the following:

        •      Determining explicitly  how  the SSAB will  make decisions about what advice and
               recommendations  it should give  and,  in particular, how to  ensure that  minority or
               dissenting views are addressed;

        •      Naming a chairperson, hiring a  coordinator, or appointing an independent facilitator, as
               deemed necessary by the SSAB, whose principal role would be to ensure that:

                      SSAB meetings  are run effectively and in a manner that  is consistent with the
                      SSAB's agreed upon ground rules;

                      the  board maintains  its focus on environmental  restoration issues and waste
                      management  and technology development  issues related  to environmental
                      restoration; and

                      whatever logistical and administrative tasks that the SSAB determines are
                      necessary to play its advisory role effectively  are accomplished.
                                              27

-------
        •      Forming subcommittees where and when it is appropriate;

        •      Providing training to SSAB members regarding relevant regulatory processes;

        •      Determining what type of public record is kept of meetings (video, minutes, general
               summary, etc.);

        •      Establishing procedures for adding, replacing, and removing SSAB members;

        •      Deciding what, if any, terms, rotational schedule, term limits, or use of alternates are
               appropriate to  help ensure a balance of interests and continuing opportunity for  and
               access to SSAB participation; and

        •      Determining when the work  of  the  SSAB  is  comnlete or the overall  interest in
               participating has diminished to such a level that the SSAB should be dissolved.

In addition to the above, the regulated agency shall establish and make public operating procedures that,
to the extent possible,  attempt to ensure continuity in the availability of the staff who  are principally
responsible for  interacting  with the SSAB.

       g)      Accountability

Federal  agencies and regulators should respond to recommendations and advice from SSAB members by
providing information on  which  recommendations or  advice can be implemented, which  need to be
modified in  order to be implemented, and which cannot be implemented. The SSABs may request a
written response to any recommendation or advice made by its members. SSABs and agencies should
maintain a record of recommendations or advice made by the board and  the status and substance of all
responses.  SSABs also have the responsibility to respond to issues raised by the regulated agencies. A
log of such issues and responses should be kept.

Members of the SSAB have a  responsibility to share information  with and provide feedback from the
constituencies they represent.  In addition, members  have an obligation to attend all SSAB meetings to
the extent possible.  Finally, members of SSABs have a  responsibility to portray accurately data or
information  provided to them as members of the SSAB.  If members distribute documents to others
outside of SSAB, they must indicate the preliminary or draft nature of the document.

       h)      Administrative and Technical  Assistance Funding

       NOTE;    Representatives  of DOD have  indicated that   they  wish  to  take  the
       recommendation of all other  Committee members that are specified in 3.3.3.h)  under
       advisement. For this reason, any references to the "Committee" in this section of the
       report do not include DOD representatives.    When and if DOD accepts the general
       recommendation of other Committee members  to provide administrative and technical
       assistance funding  to SSABs, the Committee agrees that it will revisit the more specific
       question regarding appropriate funding levels for DOD sites and that these funding levels
       should address both the large number of and  greatly varied conditions that are found at
       DOD-managed sites.
                                              28

-------
The Committee  recommends that the regulated  agency  should  provide SSAB  funding for  both
administrative support and technical assistance in order to ensure meaningful public involvement.  The
first two sections that follow outline the general principles the Committee agrees to regarding each type
of funding.  The last section discusses a number of funding implementation issues.

               (i)     Administrative Funding

The Committee recommends that regulated agencies provide funding to cover the routine administrative
needs of SSABs  that will allow them  to operate efficiently and effectively,  such  as  meeting space,
document duplication, mailings, etc.  The Committee agrees that funds should be provided for per diem
and  travel  expenses of local SSAB  members who must travel to  meetings,  hiring a coordinator or
independent facilitator (where deemed necessary by the SSAB), and other similar administrative expenses
necessary for SSAB business.  The Committee does not support providing funding for SSAB members'
salaries or honorariums.

The Committee recommends that regulated agencies should work with SSABs to establish a  limit or
ceiling on administrative costs for each SSAB. SSABs should be responsible for establishing priorities
and allocating the administrative funding provided.

               (ii)     Technical Assistance Funding

Committee  members agree  that neighbors of major hazardous  waste sites  often  lack the technical
resources to monitor and comment effectively on the technical  aspects  of investigation  and  clean-up at
their sites.   Thus,  the Committee supports  providing funding  for technical assistance to the non-
governmental SSAB participants to help ensure more effective and meaningful participation, especially
as it relates to SSAB review and comment on technical reports and  documents being developed by the
federal facility managers and their contractors.  In addition, the Committee recommends that  SSABs'
technical assistance  funding should be used to provide local training courses to educate SSAB members
regarding relevant regulatory processes.

The Committee agrees that it would be appropriate for SSABs to use technical assistance  funding to
provide travel, per  diem, and compensation to technical experts  and researchers from  national public
interest organizations, universities, or private consulting firms to attend one or  more SSAB meetings to
assist the board in discussions and deliberations involving technical issues.

The Committee also agrees that technical assistance funding should be used to complement,  rather than
duplicate, the technical programs  of both the regulated and  regulating agencies.  Therefore, SSAB
technical assistance  funds may not  be used to perform  additional sampling, to  underwrite legal actions
in any way,  including the preparation of testimony or the hiring of expert witnesses.  Also, the work of
any SSAB technical consultants must occur concurrently with the on-going efforts of the regulated and
regulating agencies so as not to slow down or impede the process. It is the responsibility of the regulated
agency to help coordinate this review process and to provide information willingly to expedite the
soliciting of input from the SSAB and SSAB technical consultants.

              (iii)  Funding Implementation

The administrative and technical assistance funding support recommended by the Committee  is intended
to build upon the principles of the existing Technical Assistance Grant (TAG) program under CERCLA

                                              29

-------
by:  1) connecting the use of such funds to the activities of the SSAB and, in particular, to the technical
assistance needs of the citizen participants in the SSAB;11  2) linking funding amounts to the magnitude
and complexity of clean-up at  each site; 3) providing funding for administrative support and technical
assistance; and 4) providing funding for non-NPL sites that have established SSABs, as per the procedures
specified above, as well as at NPL sites with SSABs.

The Committee recommends that individual SSABs and the regulated agency providing the funds should
work together to determine an appropriate mechanism for making administrative and technical assistance
funds available to the citizen members of the SSAB. Whatever approach is selected should ensure that
decisions  regarding the  administration and  use of such funds be made by the citizen members of the
SSAB, in accordance with the guidelines  specified above.  Possible mechanisms  identified  by the
Committee include:

1)     Channeling  the funds through a member of the SSAB that represents a public  interest and/or
       citizen-based organization that has non-profit legal status who  would  administer the funds in a
       timely and accountable manner;

2)     Channeling the funds through a non-profit organization that is or has been created for the explicit
       purpose of serving as a legally responsible fiduciary and  administrator of the  funds;

3)     Channeling the funds through an independent entity, such  as a university or accounting firm, that
       is mutually  agreed upon by the citizen members of  the SSAB  and the regulated agency that is
       providing the funds;  and

4)     Channeling the funds through a state or local government agency that is both capable and  willing
       to administer the funds in a timely and accountable manner.

The above options should not preclude the  possibility of the citizen  members of the  SSAB negotiating
procedures with the regulated agency for direct disbursement of  administrative and technical assistance
funding.  The Committee expects that in some cases, it may be necessary — if only on an interim basis -
- for the  regulated agency to oversee the direct disbursement of  administrative and technical assistance
funds while the SSAB decides on how to  receive funds over the long-term.   For the other long-term
options, the participating, newly created, independent, or local/state governmental entity would serve in
a legally responsible fiduciary capacity, administering the funds in a manner to be decided by the citizen
members of the SSAB, in accordance with the guidelines specified above.

In order to avoid duplication of effort, the Committee recommends that after  an SSAB is established it
will  not be  necessary to award grants under the existing CERCLA TAG  program.  In particular, the
Committee recommends that TAGs should not be awarded to organizations that choose not to participate
in SSABs.  The Committee wishes to make absolutely clear, however, that in situations where  SSABs
are established and organizations have received TAGs in the past, such organizations  would not only be
    11 The Committee does not intend for control over this technical assistance funding to be shared by
private sector responsible parties or contractors who may be participating in the SSAB.  Also, consistent
with the TAG program, no group (other than the SSAB) created or sustained by a PRP or the regulated
federal facility shall benefit  from the technical assistance funding to be provided as a result of these
recommendations.

                                              30

-------
eligible for participation on the SSAB,  they are likely to be prime candidates for SSAB participation
because they have already evidenced  an active interest and involvement in clean-up  issues at the site.
Furthermore, where SSABs have not been established, it is the Committee's view that community groups
would still be eligible to receive TAG awards.

The recommended levels and factors to be considered in providing administrative and technical assistance
funding to SSABs are as follows:

        •      The Committee also anticipates that SSAB technical assistance funding needs will  be
               proportional to the level of environmental restoration assessment activities at a site in a
               given year.

        •      The Committee  believes that  typical funding needs  will be  $50,000 per  year, and
               normally will not exceed $250,000.  Need will be determined  based  on an application
               from  the citizen  members of the SSAB, and on the approval  of the regulated and
               regulating agencies. This approval will be based on criteria developed by the regulated
               agencies in consultation with stakeholders.  To  accelerate the implementation of this
               program, the Committee urges the regulated agencies to begin this process of consultation
               as soon as possible.

        •      Greater amounts of funding should be provided in the early  phases of the FFER clean-up
               process in recognition of the fact that technical assistance  needs will  be greater during
               these early phases of the decision-making process.  Funding levels should be reassessed
               after site remedies have been selected.

        •      Although the Committee anticipates a typical funding need of $50,000 per year, it is
               likely that funding needs will be greater at the larger, more complex DOE sites and, in
               some cases, may exceed $250,000 per year.

        •      It is likely that technical assistance funding at the levels cited above will not be necessary
               at  minor sites with small clean-up  budgets.  The level of  administrative and technical
               assistance funding at such sites, if any, should be determined by the regulated agency in
               consultations with the  regulating agency and the SSAB. The Committee notes that few,
               if any, NPL sites should be considered minor and that many non-NPL sites  are major
               sites.

        •      Agencies are encouraged to group together small sites with similar technical  concerns,
               especially if they are in the same region, to provide common technical assistance funding.

The Committee recommends that the above approach to providing funding for administrative and technical
assistance be reassessed in the early phases of the SSAB program.
                                              31

-------
3.4.   IMPLEMENTATION STRATEGIES

The Committee recommends  that each agency,  working with affected stakeholders, should  develop
agency-wide policies to ensure that administrative and technical assistance funding levels not be arbitrarily
changed or adversely affected  by  whatever advice the SSABs choose to give.

At  agencies where site advisory boards already are mandated  by law,  the Committee recommends
building upon existing structures to implement the recommendations outlined here. Also, the Committee
recognizes that some agencies have efforts underway to implement the use of site advisory boards.  In
either case, the Committee recommends that the provisions outlined above be adopted and grounded in
policy or guidance whenever possible.  Options for  implementing these recommendations are suggested
below:

1)     At DOD sites, the regulations which implement TRCs could be amended to account for
       the additional provisions  outlined above, making it clear that SSABs fulfill the SARA
       Section 211 requirements  for TRCs.

2)     At  non-DOD sites  with  existing  FFAs, the community  relations plans  included  in
       agreements could be amended to provide for the establishment of SSABs upon request
       or petition. Also, any party to the FFA could initiate efforts tc amend each of the FFAs
       pursuant to the procedures outlined in those agreements.

3)     At  non-DOD sites  where FFAs are pending, the establishment of SSABs may be
       incorporated into the community relations plans for these sites.  Negotiations on the FFA
       should not, however, preclude the  earlier establishment of SSABs.  Prior to conclusion
       of the negotiation of the  FFA, EPA and the other parties  to the pending  FFA should
       initiate efforts to notify the public of the option to establish SSABs.

4)     At federal facilities or groups of facilities of significant public concern, but not on the
       NPL, the  Committee  suggests that facility  operators work in coordination with EPA,
       states, and tribal governments to notify the  public regarding the potential establishment
       of SSABs  and designate a contact  at the  regional or local  level for those who may be
       interested  in preparing a petition for establishing a SSAB.
                                             32

-------
 4.0.    RECOMMENDATIONS FOR IMPROVING ACCOUNTABILITY THROUGH ENHANCED
        STAKEHOLDER INVOLVEMENT THROUGHOUT THE FEDERAL BUDGET PROCESS

 4.1.    BACKGROUND

 As federal agencies continue to implement FFER programs at an increasing number of sites, and as these
 sites proceed through the clean-up process, the scope of the federal government's clean-up responsibilities
 will  mount.  As sites proceed into the more costly remedial  construction phase,  the government's total
 clean-up funding needs will also increase.  The ability of each agency to obtain sufficient funds to ensure
 execution of projected environmental restoration activities in  a given year will be an important factor in
 determining the overall success of the federal government's environmental restoration efforts.

 Executive Order 12088 requires federal agencies to request sufficient funds in their budget submission
 to OMB to  meet all  environmental restoration obligations.12 To date, federal agencies have generally
 been successful in obtaining sufficient funds to carry out all such obligations, as well as certain additional
 essential activities.13

 Stakeholder  confidence in each agency's environmental restoration program is contingent upon continued
 progress on  clean-ups and an understanding that the agency has made every effort  to plan for and execute
 its clean-up  obligations.  These obligations are usually expressed in  some form of a legally binding
 obligation, which contains detailed time frames  and milestones for required activities. While federal
 agencies are indeed committed to meeting these time frames, the practical limitations of the federal budget
 process indicate that even the most arduous efforts may not ensure full funding for all FFER obligations.
 As a result,  there  may be times when insufficient funds  will prevent full implementation of all FFER
 obligations or related, but not required, activities.

 The  Committee has developed a process that should ensure that such funding shortfalls  do not create an
 undue burden upon individual  sites or stakeholder expectations.  By building upon the principles of open
 and active involvement described earlier,  the Committee hopes the consultation  and  allocation process
 described below will ameliorate the effects of funding shortfalls on FFER programs.

 4.2.     OBJECTIVE

 The primary objective of this section is to establish a credible process for planning  and undertaking FFER
 activities and dealing with funding shortfalls in an equitable and cost-effective manner. In order to meet
 this objective,  the  Committee  has developed  a set of recommendations for a process whereby affected
 stakeholders are informed of, and to the extent feasible, participate in, important decisions that will affect
 the scope of work to be performed at federal  agency sites.
    12  The term environmental restoration obligations means  all legally enforceable or otherwise
applicable federal, state, tribal, or local requirements as those terms are used in the Interagency Review
of the DOE ERWM Program, April 1992. These are usually expressed in statute, treaties, regulation,
permit, order, or Interagency Agreement.

    13 For example, though generally not legally required, DOD and DOE have initiated extensive RI/FS
investigations at non-NPL sites. These studies have been essential in m?naging a comprehensive clean-up
program.

                                              33

-------
4.3.   PRINCIPLES

In recognition of the important linkage between funding availability and work to  be performed, the
Committee endorses the active engagement of stakeholders in important FFER decisions.  This applies
to all decisions regarding the scope, timing, and priority of activities to be performed, and, to the extent
feasible,  budgetary matters.  Where affected stakeholders cannot actually be involved in the decision-
making process, they should be advised of relevant decisions to the extent practicable so that they retain
confidence in the federal agency's efforts.

Many aspects  of the federal budgetary process are deliberative and are therefore confidential.  These
include many aspects of the budget formulation process. However, the Committee recognizes that there
are essential aspects of establishing budgetary requirements that are not confidential and that are subject
to disclosure.  This includes most of the information relating to the scupe of activities to be performed.
This is fortunate,  as it is  the activities that will  be  performed, and not the amount of funds being
requested,  that are of greatest interest to the stakeholders.  Accordingly,  the process that has  been
developed  is intended  to emphasize communication regarding the scope  of activities that the federal
agencies  expect to  perform.

4.4.   OVERVIEW OF THE CONSULTATION AND ALLOCATION PROCESSES

What follows is an introduction and overview of the consultation and allocation processes that have  been
developed by the Committee. The recommendations and discussion of these two interrelated subjects are
presented in separate  sections of this report,  but each  bears  upon the other and the  Committee's
recommendations with regard to each are intended to operate in conjunction  with one another.

The consultation process provides for extensive input by the affected stakeholders into the FFER process.
By  actively consulting and communicating with stakeholders in the decisions that affect  the scope of
activities to be performed,  federal agencies will enhance their FFER programs.

In  addition to  describing a  process for  timely communication, the Committee  has  developed  a
methodology for allocating funds in the event of FFER funding shortfalls.  Described as  a "fair share"
allocation,  the methodology provides a process for distributing funding shortfalls in an equitable  manner.
There are several important variations and caveats to the process, and these are described in much greater
detail below.

Prior to further discussion of the consultation and allocation processes, there are several important terms
that warrant explanation in order  to provide the  reader  with maximum  clarity.  Terms that are not
described below retain their plain language meaning.

Activity/Project:  In order to ensure  consistency and  accountability for the  consultation and allocation
processes,  it is important to retain a consistent "unit of analysis." The term  "activity/project" is one or
a collection of activities, projects, tasks, or work items that are conducted pursuant to a federal agency's
ER program.  These may range from an individual task to the restoration of a collection of individual
hazardous substance sites that are in close proximity.

It is impossible to  prescribe a size or scope for activities/projects that will be consistent throughout all
FFER programs. However, the term should define units that will enable accurate tracking and sufficient
accountability of FFER programs.  As such, the process  of site-level consultation,  which is described

                                               34

-------
herein, should be utilized to reach consensus on the activities/projects at each site that will meet the goals
of accurate progress tracking and accountability.

Ideally, the identification of appropriate activities/projects at the site level should be at a sufficient level
of detail to enable verification that the agency's budget request package and the President's budget request
to Congress  for that agency  includes the activities/projects that are  necessary  to meet budget year
obligations and milestones (required by FFAs, other regulatory documents or the agency's own planning
documents), as well as to ensure adequate progress toward out-year obligations and milestones. Indeed,
the principal purpose of utilizing a unit of analysis  at the  activity/project level is to enable consistent
evaluation of each facility's ER program progress over time.

Field-Level Manager and National Program Manager: The terms "field-level manager" and "national
program manager"  are used throughout this section of the report to connote two distinct levels or types
of decision-making that  take place within federal  agencies.  It is recognized that for some agencies,
particularly DOD  and  DOI,  this  nomenclature may  vastly oversimplify complexities in  the  FFER
decision-making process related to the multiple organizational layers within such agencies. Nevertheless,
the terms  "field-level manager" and  "field-level decisions" are meant to connote decisions and interactions
that take place at the local site/facility/field office level.  "National program managers" refer to the level
of management and decision-making that relates to the overall management of a FFER program. In some
departments there may be a multitude of such programs and program managers.

Programmatic Versus Site-Specific Decisions: The Committee is aware of the extremely dynamic nature
of the federal facility environmental restoration decision-making process. Sometimes decisions are made
at the local level (i.e., the site/facility/field office level) that could affect the scope or  schedule of an
FFER activity/project. Other times decisions are made within agencies or within  the Executive Branch
that are of a programmatic or policy nature.  When these types of decisions are  made it is  sometimes
possible to ascertain whether they will affect the scope or schedule of a particular FFER activity/project.
However, it is probably more typical, because of the nature of these decisions, that it is  not possible to
ascertain their potential impact on site-specific FFER activities/projects until such time as the President's
budget is  submitted. This is particularly true with programmatic  and policy decisions that are made in
the context of the federal budget cycle.

Affected Stakeholders: The terms  affected stakeholders or stakeholders will be  used  throughout this
section in a manner consistent with the intent of the previous sections of this report. Accordingly, where
stakeholders are affiliated with an SSAB, the terms  should be used interchangeably. Where no SSAB
exists, then the term stakeholders is intended to refer to the federal  agency, regulatory agency,  tribal,
public, and other affected parties who are most interested and concerned with the FFER activities/projects
to be performed.

4.5.     CONSULTATION PROCESS

4.5.1.   Introduction and Scope

Regular and extensive communication and consultation amongst the affected stakeholders is essential to
ensuring that  all parties are active participants in  the FFER process.   Throughout this continuous
consultative process, there are several key points that are important opportunities for the stakeholders to
confer on  matters related to the availability of resources to carry out environmental restoration activities.
                                               35

-------
The Committee has  identified  four  distinct  points within the  FFER process  at  which  enhanced
communication among stakeholders is recommended:

       Point #1:      Initial field-level development of site-level  requirements.

       Point #2:      Submission of the President's budget to Congress.

       Point #3:      Presidential/Congressional appropriation and agency allocation.

       Point #4:      Completion of the budget-year execution.

Additional communication regarding resources  should also occur, to the extent feasible, throughout the
process, but the Committee has not identified distinct times for consultation other than those listed above.
Rather, the principle stated above, timely and continuous communication of important decisions, should
serve as a guideline for use throughout the entire FFER process, as recommended in Section 4.5.2.

The communication process that is  described  in this  report is intended to  enhance stakeholder
understanding and  participation in the FFER decision-making process.   It  is  envisioned that the
consultation and communication that  is described herein will be conducted primarily at the local  level
among representatives of the federal  facility and  affected  stakeholders, such  as  the SSABs and the
regulators.  It is not envisioned  that this  communication will occur often at the national level.

It is noted that the federal budgetary process is both a multi-year and cyclical process. For the sake of
efficiency,  the  Committee  encourages  agencies  to coordinate  their  efforts  to  implement these
recommendations, such that information on two or more separate budget development and implementation
cycles  can  be shared at  the same time, where practicable  and  appropriate.   This suggestion for
coordinated review and consultation of budget-related information is in no way intended to diminish the
importance of the ongoing and continuous consultation between affected stakeholders, regulators, and site
managers that is recommended in Section 4.5.2. and elsewhere  in this report.

The recommendations contained in section  4.5. are intended to apply broadly to  all FFER activities,
regardless of the statute under which they are conducted. For  example,  the recommendations that are
presented in this section could be applied to clean-ups conducted pursuant to CERCLA, RCRA, BRAC,
FUDS, UMTRA, and FUSRAP, as well as other state and federal  requirements, as described  earlier in
Section 1.4.2.  However, as explained below,  the applicable scope of the allocation process, which is
described in Section 4.6., is narrower than  that which applies to the other  recommendations contained
in this report.

4.5.2.  Consultation During Program Development and Execution

Recommendation

The Committee recommends that when site-specific or programmatic decisions are made that affect the
ability of a site to meet its clean-up obligations, federal agencies should communicate these decisions to
stakeholders in a timely  manner.
                                              36

-------
Discussion

The Committee recommends that at any time site-specific or programmatic decisions are made that will
affect the ability of an individual facility to meet its clean-up obligations, these decisions, regardless of
when or in what  context they are made, should be communicated in a timely manner to  affected
stakeholders at the facility.  This recommendation is intended to focus on communicating decisions that
result in changes to the scope or schedule of proposed FFER activities/projects, which in turn affect the
ability of federal facility managers to meet  their FFER  obligations.  The Committee  is especially
concerned that decisions that affect the ability of an individual facility to meet FFER obligations that are
specified in legally enforceable agreements, permits,  orders, etc., be communicated in a timely manner.

This recommendation builds upon the  recommendations and principles contained  in the previous two
sections of this report,  which address information exchange and  the establishment of SSABs.   This
recommendation also forms the broader context within  which the remainder of the recommendations
contained in this "Consultation Process" subsection (all of which focus on consultation at discrete points
in the FFER budget development and implementation process) should be considered.

It is intended  that this recommendation should apply to any  site-specific or programmatic decisions,
including those that are made in the context of the budget process. However, this recommendation does
not apply to the numerous deliberative, predecisional considerations and discussions that occur within the
federal government during the development of the President's Budget.

These recommendations are not intended to detract from or diminish the importance of the  Committee's
recommendations regarding early and ongoing consultation with affected stakeholders (see Sections 2 and
3). Rather, the focus on communication of decisions in this recommendation is intended to complement
these other recommendations and serve as a means of maintaining trust and credibility, particularly in
those situations where local field-level  managers are not directly involved in decisions that may  affect
their ability to meet FFER milestones.

4.5.3.  Consultation During the Initial Field-Level Developmenf of Site-Level Requirements

Recommendations

The Committee recommends that:

       a)     Field-level managers should work with stakeholders to define the appropriate unit of
              analysis14 and  to  identify  the activities/projects for  inclusion  in  the budget request
              package for the national program manager;

       b)     Field-level managers should share planning cost estimates where practicable; and

       c)     Stakeholders should treat and portray such planning  cost estimates appropriately and
              accurately.
    14   As discussed above,  once an appropriate  unit  of analysis is identified,  the  agreed  upon
activities/projects should be  utilized from that  point forward  as a means of tracking those  same
activities/projects through time.

                                              37

-------
Discussion

These recommendations reflect the Committee's recognition of the important contribution stakeholders
can make in advising federal agencies about proposed clean-up activities/projects and their related scope
and priority.   The first step in this consultation is the establishment of a common unit of analysis.  As
noted, the precise activity/project descriptions that are agreed upon should be at a sufficient level of detail
to enable verification and tracking over time of those activities/projects that are critical to the ability of
the site manager to meet established milestones. The level of detail should also be sufficient to enable
stakeholders to  ensure  that adequate progress  is being made toward meeting out-year obligations and
milestones.

Regarding the type of information that is shared at this time, it is understood that information on the
actual dollar amounts that are included in the activity request package  that is submitted by field-level
managers to national program managers for the purposes of developing the President's budget cannot be
provided. This  is due to restrictions on the availability of federal budget  information prior to submission
to Congress and concerns about providing sensitive information on cost estimates for specific projects not
yet released  for competitive contract bids.   Thus, this  recommendation focuses on  the  sharing  of
information on  FFER activities/projects at  this early  stage of the federal budget cycle rather than the
actual dollar  amounts that are being requested by field-level  managers  as part of their budget request
package.

Although this recommendation focuses on sharing information on the activities/projects that will  be
included in field-level submissions, federal agencies, as part  of the activity/project planning process,
should share planning cost estimates, to the extent possible.  In a number of instances, legislation and
negotiated agreements (particularly pertaining  to DOE and DOD) currently require the sharing of final
planning cost  estimate information.  As noted  above,  it is agreed that there is an affirmative obligation
on the part of those who receive such planning cost estimates, which may not be  of budget quality (i.e.,
the agency has not verified their accuracy), to portray this information as still being in the planning stage.

4.5.4.  Notification after  the President's Budget Submission

Recommendation

        The Committee recommends that as soon as possible after the President submits the budget to
        Congress, federal  agencies  should  provide  information to stakeholders that disaggregates the
        budget to an activity/project level consistent with the level of disaggregation utilized during the
        initial field-level development of requirements.  Information provided at this point should address
        both  the scope and  dollar amount of proposed  activities/projects and  should identify which
        activities/projects  are or  are  not  included in the President's budget  in  comparison to the
        activities/projects specified in the initial field-level consultation.

Discussion

To implement this recommendation, regulated federal agencies should provide information to  affected
stakeholders  that  disaggregates the President's budget  to  an activity/project  level.    Disaggregated
information provided at this point in time will enable stakeholders to understand which activities/projects
are still included in the President's budget, as compared  to the activities/projects that were identified
during the initial field-level consultation (as per Section 4.5.3. above).

                                                38

-------
Information on the proposed funding level for each activity/project that is included in the President's
budget will normally be provided at this  stage.   There may be exceptional circumstances where this
practice  cannot be followed in detail.  For example, concerns about providing information on budget
amounts and cost estimates for specific FFER activities/projects not yet released for competitive contract
bids may limit a federal agency's ability to provide information at the level of disaggregation specified
by the agreed upon site-level FFER activities/projects.  It is also  recognized that it  may be difficult to
provide disaggregated information immediately after the submission of the President's budget, but federal
agencies should make  every effort to do so in a prompt manner which would allow other stakeholders
to participate in the congressional authorization and appropriation  debates.

In addition to providing the information on the activities/projects described above, federal agencies should
provide information to stakeholders, when requested and to the extent such information is available, on
the basis of any changes in the activities/projects that have been requested in the President's budget in
comparison to the  initial field-level requirements identification.  As noted above, the consultation process
described in this  subsection is  intended  to be  performed  primarily at the local level,  and not  in a
centralized manner at the agency headquarters level. However, in order to ensure that the rationale for
changes to the scope or schedule of FFER activities/projects are communicated to affected  stakeholders
in a  timely  manner,  this information  should  be provided by  agency representatives  at  whatever
organizational level within the agency it is available.

4.5.5. Consultation after Presidential/Congressional Appropriation and OMB Apportionment

Recommendation

       Field-level managers should  communicate  the  results  of  agency  allocation  decisions to
       stakeholders.  In cases where there is no funding shortfall, the field-level manager should inform
       stakeholders of the results of agency FFER budget allocation decisions.  In cases where there is
       a funding shortfall, consultations and negotiations, as appropriate and as described in Section 4.6
       below, should occur.

Discussion

After Congress approves and the President signs a bill to appropriate FFER funds,  and the Office of
Management and Budget (OMB)  completes its apportionment of the approved budget, national program
managers should allocate funds to the field-level  in a manner that is as  consistent as possible with the
FFER activities/projects that were included in the President's budget.  If the appropriation from Congress
was  insufficient or there has been significant unanticipated program  growth between  the time the
President's budget was developed and appropriations are finalized,  agencies should allocate FFER funds
in accordance with the recommendations contained in Section 4.6. below.

The agency should inform  affected stakeholders of the  actual funds allocated,  as  well as the projected
scope of activities  the agency expects the allocated funds to achieve at each facility.   As with the other
discrete points  of  consultation process  described  in this  section,  the  information provided  should be
disaggregated to an activity/project level. This should include information about which activities/projects
are included in the facility's budget, as compared to the activities/projects that were identified during the
initial field-level consultation, along with information on the budgeted dollar amounts  associated with
                                               39

-------
these activities/projects. The consultation at this step should be performed in a timely manner to enable
prompt initiation of agreed upon activities/projects.

In the  allocation process described below, the Committee has developed a method for allocating funds
in cases where there are insufficient funds to meet all FFER obligations. The recommendation in this
subsection  is intended to  operate  in  conjunction with the subsequent recommendation on allocation
strategies by ensuring that, as allocation decisions are made that affect the scope or budget of activities
to be performed, stakeholders are informed or consulted with, as appropriate.

4.5.6.  Consultation After Budget Execution

Recommendation

       The Committee recommends that federal agencies should provide stakeholders with a status report
       on  clean-up activities that have been conducted and on funds expended at the end of the fiscal
       year following budget execution.

Discussion

At the end  of the budget year, the federal facility should communicate to the affected stakeholders the
amount of  funds that have been obligated and spent and the work that has  been performed.  This
information should be disaggregated at the same activity/project level as has previously been described
in order to  ensure continuous activity/project tracking. This will ensure a common understanding of the
progress the site is making in meeting its current and future FFER obligations.
4.6    ALLOCATION PROCESS

4.6.1.  Introduction and Scope

Federal facility environmental restoration priorities are established and refined at numerous stages and
levels in the FFER decision-making process.  The Committee believts that the establishment of more
widely supported federal facility environmental restoration priorities can be accomplished by improving
the overall process by which affected stakeholders are involved in FFER decisions.  It is for this reason
that the Committee has included recommendations in  this report related to both improving the exchange
of information and involving affected stakeholders in FFER decision-making.  However, even with these
improvements there is a need to establish an agreed upon approach to setting FFER priorities in the event
of a funding shortfall.

The Committee believes that the recommendations that follow establish a  FFER priority-setting system
that balances the respective interests, responsibilities, and authorities of FFER program managers, state
and federal regulators, tribes, and other affected stakeholders.

The Committee believes that the  allocation process it is recommending will establish a competent,
efficient,  and  cost-effective approach  to  the  allocation of federal  facility environmental restoration
resources in the event of a funding shortfall.  Such an approach should instill congressional and public
confidence in  the  management of FFER  programs  and, thereby, support for these programs.  This
                                               40

-------
confidence will help promote the federal government's overall goal of enhanced environmental protection
and restoration.

What follows is an explanation of certain concepts that are critical to understanding the recommended
approach  to priority-setting and allocation contained in this section.  The reader should note that the
applicable scope of the recommendations contained in this section is, for purposes of practicality, more
narrowly defined than that of the previous sections of this report.

Two Different Types of FFER Funding Shortfalls:  The Committee  identified two different types of
funding shortfalls that warrant different responses.  The first are those shortfalls that are caused by a
failure on the part of Congress to appropriate the amount of FFER funds that were  requested  in the
President's budget for a particular agency's FFER program. This circumstance is referred to below as
an "insufficient appropriations shortfall."

The second are those funding shortfalls that are caused by a variety  of circumstances,  including: a)
unanticipated events, new circumstances, or new data; and b) underestimated FFER costs.  These types
of funding shortfalls are referred to below as "program  growth shortfalls."   Although the Committee
recognized that it will often be difficult to distinguish between these two major types of funding shortfalls
- insufficient appropriations and program growth — as well as between the different causes of program
growth  shortfalls  — unanticipated events and underestimated  costs  — it is  nevertheless important to
maintain these distinctions for reasons that are specified below.

Applicable Scope and Focus of the Allocation Process: In order to understand fully and implement the
Committee's  recommendations regarding a process for making FFER allocation decisions in the event
of a funding shortfall, it is necessary to specify the precise programmatic parameters  within which these
recommendations are intended to be applied.

The "fair share" allocation process, which is described below, focuses primarily, but not exclusively, on
funding shortfalls caused by insufficient appropriations.  This process can only be implemented if all who
are involved  in its implementation are clear about the programmatic  budget from which the  fair share
allocation is to be derived.

The Committee recognizes that some environmental restoration activities take place under the "operation
and maintenance" (O&M) portions of agency budgets. However, the Committee believes that at this time
it would simply be too complicated to include all ER activities that are now funded through O&M budgets
in its recommended allocation process.  Thus,  the Committee recommends that the allocation process
described below should be applied only to the specified ER program budgets within agencies.  In the case
of DOE,  the allocation  system described below would be applied to the  Office of Environmental
Restoration budget15  and  would  not apply to other budget accounts such  as  the Office  of Waste
Management, the Office of Technology Development, and the Office of Facilities Transition; for DOD,
the Defense Environmental Restoration Program budget,  which is under the  managerial control of the
Office of  the  Assistant Secretary of Defense (Environment) and the operational  control  of  the  DOD
components (i.e., the Military Services and the Defense Logistics Agency)16 and would  not apply to
    15  As it existed in December  1992.

    16  As it existed in December  1992.

                                              41

-------
other budget accounts such as BRAC and FUDS; for all other agencies it would be the specific program
or portion of their budget under which environmental restoration activities take place.

The Committee recommends that at some later date, after the allocation process described below has been
tested, agencies should consider using this process to address shortfalls for environmental restoration
activities/projects that are funded  through other  parts of the agency's budget,  as  well  as for  waste
management and technology development activities that are related to environmental  restoration.

The limitation regarding the applicability of the allocation process described  below is not intended to be
determined  by  the authority under  which a clean-up is conducted, but rather by whether the funds for
conducting  the clean-up are  included in the portions of agency-wide budgets that are specified  for
environmental restoration activities. Depending on the agency, these programs typically include clean-up
activities  that  are  conducted pursuant  to a variety  of  laws and  regulatory  requirements including
CERCLA, RCRA corrective action, federal facility compliance agreements,  permits, orders, etc.

Inter- versus Intra-site Allocations:  As  noted in  the introduction to this report,  in grappling with the
perceived need for "national" federal  facility  priority-setting, the Committee agrees that this need should
not result in the establishment of a single, unitary  priority-setting process or system  whereby federal
facilities from  all  departments are considered together.   Rather,  the term "national"  federal facility
priority-setting is used in this report to refer to the question of how best to set clean-up priorities at the
national  level within each  department  (i.e., between sites within  each  federal  department).17   The
allocation of FFER funds between sites but within a department is  referred  to below as  "inter-site
allocations."

Another important level  of priority-setting occurs  between activities/projects within a site.18 This level
of priority-setting and allocation of FFER resources  is referred to below as "intra-site allocations."  See
Figure 1 for a graphic depiction of inter- versus intra-site allocations.

Sites That Are  Subject to Outside Supervision Versus Sites That Are Not:  Federal facilities are subject
to numerous clean-up requirements that are specified under or result from federal, state, and local laws,
and treaties  with Indian Nations. These requirements are generally applied to a facility through a Federal
Facility Agreement (FFA),  order,  permit, or some other legally binding instrument.   In  general,  the
application of external requirements coincides with heightened external interest from regulators, tribes,
and other affected stakeholders. When such  external requirements are applied,  the regulating agencies,
tribes, and other affected stakeholders will become  more actively involved with the  facility, especially
in tracking  whether the regulated  agency is meeting its legally  binding FFER  obligations.  It is in
recognition  of the heightened  concern of stakeholders and the special role that regulating agencies,  and
possibly tribes, will play  under  these  circumstances  that  the  allocation process described below
differentiates between sites that are, versus sites that are not, subject to external supervision.  This
distinction is especially relevant to the parts of the recommended allocation process that are described in
Sections 4.6.3. and 4.6.4. below.
    17 For example, within DOE (Rocky Flats vs. Hanford, etc.).

    18For example, landfill A vs. lagoon B, etc. at "Fort Moosebreath."

                                                42

-------
                                Figure 1
              TWO LEVELS OF FUNDING ALLOCATION
INTRA-SITE ALLOCATION
  (allocation within sites)
                           Landfill
                            Solar
                            Ponds
                            RI/FS
                            Study
                                                INTER-SITE ALLOCATION
                                                  (allocation between sites)
RI/FS
Study
                                          Landfill
                                                          RI/FS
                                                          Study
                                                         Landfill
                                                          Tanks
                             RI/FS
                             Study
                             Ponds
                  SITES:
  B
D
                                    43

-------
4.6.2.  Important Considerations in the Allocation of FFER Funds

The Committee believes that the major consideration in establishing and implementing a system for setting
priorities  in the event  of any  type of  funding shortfall is to adhere to the fair share concept that is
described below and, whenever possible, to the scope and schedule of existing legally binding obligations
(e.g., FFAs, permits, administrative and  court orders, etc.) and the milestones they establish.  Such
obligations, aside from being  legally binding, are the currently recognized  and  agreed upon clean-up
priorities  for a particular site and have often been established at great effort.  These obligations often
reflect consensus agreements among regulated agencies, regulators, tribes, and other affected stakeholders
on the most appropriate approach to clean-up at that site. These agreements are often renegotiated based
on  current site  conditions  and are considered a  reflection  of all of the  affected stakeholders'  best
professional judgement. As such, these obligations should be honored to the fullest extent possible.

The Committee recognizes, however,  that  it may  not always be  possible to  adhere to established
obligations and milestones and has developed a flexible system for distributing funding shortfalls based
on a set of fair  share principles, outlined  in detail below.  This system  relies  on the judgments of the
regulated  and regulating agencies and affected tribes, and the input of other affected stakeholders.

As described in  Section 1.4.3., in the case of tribes, legally binding FFER obligations may derive from
treaty and statutory  rights, including  fishing, hunting, gathering,  and subsistence  rights.  In some
instances, such rights will have a bearing upon FFER related activities and may result in binding agency
or obligations to protect those rights.  It is in these circumstances that this section of the Committee's
report uses  the  term "affected tribe" to indicate that tribes should participate on  an  equal basis with
regulators in any  negotiations which involve potential changes to binding  obligations to tribes.   It is
understood that  this role does not grant tribes  any  rights or justiciable claims that they heretofore have
not had, but simply recognizes existing rights.

The Committee believes that: 1) existing data and science are currently inadequate to determine objective
consensus clean-up priorities;  2) factors other than  environmental and  human  health  risk deserve
consideration in  allocating clean-up resources; 3) broadly acceptable and objective methods for evaluating
some of the criteria relevant to the allocation of clean-up priorities do not currently exist, and, in some
cases, may never exist and may even be inappropriate; and  4) regardless of any party's opinion about the
quality  of available data and  science, it is appropriate in  a democracy  to  allow a variety of affected
interests to provide input on decisions that affect them.

In order to help  guide the collective decision-making of the various participants, the Committee believes
that  certain factors,  in addition to  the need to adhere, to the fullest extent  possible,  to established
obligations and milestones, should be considered by all participants in tue implementation of the flexible,
fair share allocation system described below.  These factors include:

        •      protection of human health, including occupational health considerations  as well as the
               health of the general population;

        •      risk reduction;

        •      cultural and socioeconomic factors, including environmental equity considerations;
                                                44

-------
        •       protection  of  and  trustee/stewardship responsibilities  related  to  significant natural
                resources;19

        •       the degree to which past management practices and/or new requirements imposed by state
                and federal regulators affect the ability to meet established milestones;

        •       the availability of new or innovative technologies or technological constraints that affect
                the ability to meet established milestones; and

        •       other factors that may be unique to  a particular site  or articulated at the site level by
                affected stakeholders.

4.6.3.  Fair Share Allocation Process to Address  Insufficient Appropriations for Sites That Are
        Subject to Outside Supervision

Recommendations

The Committee recommends that:

        a)       If Congress appropriates less than what an agency requested for its FFER program, then
                representatives  from that agency,  regulators,  affected  tribes, and other  affected
                stakeholders should make  every effort to ensure that all sites that are subject to outside
                supervision within that program share equally in the amount of the funding shortfall. For
                example, if Congress only appropriates 90% of what was requested, then all sites subject
                to outside supervision would be expected to receive 90% of what was requested for that
                site.  This is designated the fair share allocation.

        b)       Within  the  constraints of the fair share allocation, and upon  consultation of regulators,
                affected tribes, and other affected  stakeholders, if national or field-level  program
                managers develop an  intra-site allocation scheme that does not affect  the  scope or
                schedule of established, legally binding obligations, they  are free to  implement such a
                decision without further consultation.

        c)       If,  in considering  the  application  of the fair share allocation, national  or  field-level
                program managers believe it  is not possible to develop an intra-site  allocation scheme
                without affecting the scope and schedule of a legally binding obligation, a process of
                negotiation  with state and federal  regulators and affected tribes, and consultation with
               other affected stakeholders, must ensue.  In these circumstances, the Committee strongly
               recommends that  state  and federal regulators and affected  tribes should  renegotiate
               obligations  and milestones, rather than undertake punitive enforcement actions, so long
                as:
    19   "Significant natural resources" are resources of special concern such as wetlands and fish and
wildlife habitat, especially for threatened and endangered species, wilderness areas, park land resources,
cultural resources, and other biological resources.

                                                45

-------
                       a federal agency implements the recommendations contained in this report in a
                       responsible and good faith manner; and

                       the funding requested for that agency's FFER budget represented the Executive
                       Branch's best estimate  at the  time of submission  of the  amount of funding
                       necessary to meet that agency's legally binding clean-up obligations.

               As long as these conditions are met  and the agency adheres to the fair share allocation,
               negotiations with regulators and/or affected tribes for a particular site should be limited
               to the question of which obligations or milestones should be renegotiated, if necessary
               (i.e., how to absorb the fair share cut),  rather than the more basic  question of whether
               any obligations or milestones should be renegotiated.

        d)      If national or field-level program managers, in considering the decision-making factors
               described above in 4.6.2., believe that it would not be good public policy to rely strictly
               on a fair share allocation for a particular site, they can suggest an alternative allocation
               scheme that deviates from the fair share allocation. However, in this circumstance, state
               and federal  regulators and  affected  tribes would  be  free to question whether  that site
               should accept more than its fair share cut, as well as how such a cut might be absorbed
               in relation to established obligations and milestones. In the event a consensual agreement
               cannot  be reached on  an  acceptable reallocation scheme,  existing dispute resolution
               processes (e.g., those specified in FFAs) would be honored.  Where FFAs do not exist
               or are not relevant, a similar process of appeal to progressively higher levels of authority
               to resolve disputes should be used.

Discussion

The system recommended by the Committee for  addressing  funding  shortfalls caused  by insufficient
appropriations at sites that are subject to outside  supervision is  intended to recognize and balance the
legitimate rights, responsibilities, and decision-making authorities of state and federal regulators, affected
tribes, and FFER national program managers, as well as the legitimate consultative role of other affected
stakeholders. The system is intended to be an equitable and efficient system for reallocating funds in the
event of an insufficient appropriation. It is also intended to be a system that has sufficient flexibility to
account for the variety of factors that all key players must consider while making, or participating in the
making of, what are sure to be very difficult decisions.

In implementing this system, the Committee recommends that national program managers who are faced
with  a  funding shortfall caused by insufficient appropriations  should immediately notify  field-level
managers,  who, in turn, should immediately initiate a process of consultation with  regulating agencies,
affected tribes, and other affected stakeholders  about what can be done to absorb that site's fair share
portion of the shortfall.  If this process of consultation reveals that it is possible to absorb the fair share
cut without adversely affecting the scope or schedule of any established, legally binding obligations, then
such a decision should be implemented without further consultation or negotiation.

If federal agency representatives,  in consultation with regulators, affected tribes, and other affected
stakeholders, determine that the fair share cut cannot be absorbed without affecting their ability to meet
established clean-up obligations,  negotiations with state and federal regulators and affected tribes will be
necessary.  An  important feature of the recommended system is that as long as the agency adheres to the

                                                46

-------
fair share allocation, such negotiations would be limited to resolving questions of how to absorb this cut,
rather than whether the presumed fair share cut should be absorbed at that site.

The Committee believes that all who are involved in such negotiations over which  projects/activities
should be changed should make every effort to avoid missing established obligations and milestones,
taking into consideration the balancing factors and considerations identified  in 4.6.2 above.  However,
in the event that it is clear that missing obligations and  milestones cannot be avoided, the Committee
strongly recommends  that state  and federal  regulators renegotiate milestones, rather  than  undertake
punitive enforcement actions.  In the case of  affected  tribes, such "punitive  enforcement action" would
generally be oriented toward protection of treaty and statutory rights, such as those described above, and
would find its application through the courts rather than through administrative orders.

This recommendation for "relief" from punitive enforcement actions is contingent upon federal facility
managers:  1) adhering to the fair share principle; 2) showing that they have attempted to implement the
recommendations contained in this report in a good faith and responsible manner; and 3) snowing that
the funding requested for their agency's FFER budget represented the Executive Branch's best estimate
as of the time of the budget submission of the amount of funding necessary to meet that agency's legally
binding clean-up obligations for that site.

If federal program managers, after  consideration of the factors suggested above and  consultation with
regulators, affected tribes, and other affected stakeholders, suggest an inter-site allocation scheme that
requires a  site to  absorb more than the  presumed  fair share cut,  negotiations with  state and federal
regulators, and consultations with other affected stakeholders, could include whether  such a higher cut
should be absorbed by that site,  as  well as how to  absorb  such  a cut on an intra-site basis.   As  noted
above, existing dispute resolution processes would be utilized if such negotiations do not yield agreements
as to how to proceed with restoration activities at that site.

4.6.4.  Fair Share Allocation Process to Address Insufficient Appropriations for Sites That Are Not
        Subject to Outside Supervision

Recommendations

In the event of a funding shortfall caused by  insufficient appropriations for sites that  are not  subject to
external supervision (i.e., where the federal agency does not have any legally  binding obligations), the
Committee recommends that:

        a)      The funding shortfall for all such sites, taken as a whole, should reflect  the fair share cut.

        b)      Using the factors outlined above in Section 4.6.2,  national  program  managers should
               have discretion to determine how to allocate the overall cut for all such sites on an  inter-
               site basis.

        c)      Federal agency representatives should consult with  affected  stakeholders about how to
               absorb the assigned cut at a particular  site or group of sites.
                                                47

-------
Discussion

The Committee believes that sites that are not subject to external supervision are not likely to have the
same  level of concern and interest on the part of regulators or large numbers of affected stakeholders,
as will sites that are subject to external supervision. However, the Committee also recognizes that many
such sites may have affected stakeholders, even if they are few in number, who are vitally  concerned
about what happens  at these sites. Thus, the Committee recommends  that the fair share principle be
applied to the combined request for all such sites. Furthermore,  the Committee recommends that the
actual site specific (inter-site) distribution would be at the discretion of the national program manager,
using the above referenced decision-making criteria to help guide his/her decisions.  Finally, the manner
in which each facility's (intra-site) funding  would be utilized after the inter-site  allocation has been
determined should be developed in consultation with all affected stakeholders.

4.6.5.  Allocation Process to Address Funding Shortfalls Caused by Unanticipated Program Growth

Recommendations

As is noted  above,  the Committee recognizes  that funding  shortfalls can result  from  unanticipated
program growth that takes place between the time field-level submissions initiate the budget cycle  and
appropriations are finalized, typically a two-year process. In contrast to  shortfalls caused by insufficient
appropriations, the Committee is not recommending any sort of "enforcement protection" when a federal
agency is unable to meet its legally binding obligations due to unanticipated program growth.  However,
the Committee did develop recommendations which it believes will reduce the impact of such funding
shortfalls.

To address funding shortfalls caused by unanticipated program growth,  the Committee  recommends:

        a)      Federal agency representatives should inform affected stakeholders as soon as it is known
               that a funding shortfall has been caused by an unanticipated event,  new circumstances,
               new   information, or  an   underestimation  of  the   costs   of   scheduled  FFER
               activities/projects.

        b)      Program growth funding shortfalls should, to the greatest extent possible, be absorbed
               at the site where the shortfall exists.  This preference  is based on the view that such
               shortfalls arise at the facility  level, so they should  be resolved there.

        c)      Federal agency representatives should consult with regulators, affected tribes, and other
               affected stakeholders to determine how to absorb the shortfall considering the importance
               of legal obligations and milestones and the other decision-making factors outlined above.
               Because of the preference for intra-site reallocation,  federal  agency  representatives,
               regulators,  affected  tribes,  and  other affected   stakeholders  should  give  serious
               consideration to modifying the scope of clean-up activities/projects  or establishing new
               priorities among  clean-up activities/ projects in order  to absorb the program growth
               shortfall within the site.

               The preference for intra-site reallocation of priorities is especially strong if the program
               growth funding shortfall has been caused by new regulatory requirements that are being
               imposed at the  site  in  question  and/or past management  practices  that  may have

                                                48

-------
               contributed to the program growth shortfall. As noted above, however, the Committee
               is not recommending  any sort of "enforcement protection" when a federal agency is
               unable to  meet its legally binding obligations  due to unanticipated program growth,
               especially if the unanticipated program growth funding shortfall is perceived to have been
               caused by past management practices.

        d)      If it is determined that the program growth shortfall cannot  be absorbed at the site
               without causing undue hardship, federal agency representatives should attempt to shift
               discretionary funds from other sites to help absorb the program growth shortfall.

        e)      If shifting discretionary funds from other sites to the site where the program growth
               shortfall exists does not rectify  the shortfall,  federal  agency representatives should
               consider the following options (which are listed  in no particular order of preference):

                (i)     Shift non-discretionary  funds (i.e.,  funds that  are necessary  to meet legally
                       binding obligations and  milestones) from another site or sites to the site where
                       the program growth shortfall exists. This option will  require  renegotiation of
                       legally binding obligations with all sites that are asked to share the burden  of
                       shifting non-discretionary funds.

               (ii)     Petition Congress to  reprogram  appropriated funds to cover  the  cost  of  the
                       unanticipated program growth.

               (iii)     Petition Congress for a supplemental budget  request to cover the cost  of  the
                       unanticipated program growth.

Discussion

Although the Committee hopes that implementation of the recommendations contained throughout this
report will lead to an enhanced process of consultation and communication with affected stakeholders that
will minimize the possibility of funding shortfalls caused  by unanticipated program growth, such shortfalls
may continue to affect FFER programs.

The Committee also recognizes that, in any given year, FFER funding shortfalls are likely to be caused
by a combination of factors, such as insufficient appropriations and unanticipated program growth.  While
the Committee recognizes that it may be difficult to distinguish between the various types of funding
shortfalls, such distinctions are of vital importance if the Committee's recommendations for a fair share
allocation process are to be implemented.  As such,  the recommendations contained in this subsection
should be seen as creating the additional parts of a total system for setting priorities in the event of FFER
funding shortfalls of any type.

The  Committee has an especially strong preference  for absorbing program growth  funding shortfalls
caused by underestimating costs on an  intra-site basis.  If the preference for absorbing cuts  on an intra-
site basis places an undue burden on the site or sites where the shortfall exists, federal program managers
should, in consultation with affected stakeholders, first  attempt to shift funds from discretionary  FFER
activities/projects from other sites to the site or sites that caused the shortfall.
                                               49

-------
If relying on intra-site allocations or shifting discretionary funds from other sites proves to be infeasible,
federal program managers would then have the option of petitioning  Congress either to "reprogram"
appropriated funds or to approve a supplemental budget request to cover the costs associated with the
unanticipated program growth.  Another option would be to attempt to shift funds from non-discretionary
FFER activities/projects at various sites to the site or sites that caused the shortfall.  This option would,
however, require negotiations with state and  federal regulators and consultations  with  other  affected
stakeholders.  The Committee recommends that federal program managers,  in consultation with affected
stakeholders, should attempt to share the burden of covering the costs of a  program growth shortfall on
a "fair share"  basis similar to that described above.  Regulators and affected stakeholders will be more
willing to consider this option if it can be shown  that the  program growth shortfall is truly caused by
unanticipated events and new information rather than underestimated costs without technical justification.

Building on the example posed in the previous section, if  Congress and the President only  appropriate
90% of the funds requested for a particular FFER program, the agreed upon fair share distribution would
be 10%.  If, on top of this there was an additional shortfall  caused by unanticipated program growth that
could not be fully absorbed by the site that caused the shortfall, national and field-level program managers
could suggest  that the remaining  funding shortfall  be distributed amongst all sites on a fair share basis.
However, state and federal regulators and other affected stakeholders would be free to question whether
they should willingly absorb such an additional "fair share" cut on top of the agreed upon fair share of
the shortfall caused by  an insufficient appropriation.  Once again, if it can be shown that the program
growth shortfall is truly  caused  by unanticipated events and new information rather than unjustified
underestimating of costs,  for example, regulators  and citizens will be more likely  to agree to such an
inter-site reallocation of appropriated resources.

The Committee acknowledges that, in many ways, the recommendations in this subsection do not differ
greatly from the existing approach that federal  agencies take to reallocating appropriated resources in the
event of a funding shortfall caused by unanticipated program growth.  The one exception might be the
use of the fair share concept as a way to open up more dialogue and equitable considerations related to
the shifting of program resources at an inter-site level without incurring tremendous transaction costs.

4.6.6.  Recommendation Against Congressional Earmarking

The allocation system recommended  by the Committee is designed only  for those  allocation and/or
reallocation decisions that are within the purview of national  program managers.   The  Committee
recognizes  that in certain cases an appropriation bill may specify or "earmark"  precise  funding levels for
particular sites.  The Committee strongly recommends that Congress refrain from  such site-specific
earmarking as it will detract from the  principles  of fairness that are  built into the process described
herein, as well as diminish the value of stakeholder involvement in FFER programs. If an appropriation
bill does include a specific funding level for an individual site and an aggregate funding level for all other
sites, the Committee recommends that any shortfall be distributed, as described above, among sites for
which there is no site-specific appropriation.
                                               50

-------
5.0.   CONCLUSION

Much has been learned over the past decade or so regarding methods for involving the public and other
stakeholders in the decision-making process of environmental restoration activities.  In part because of
the size and type of sites, DOE and DOD in particular have been at the forefront of these activities. The
recommendations above are intended to institutionalize the effective methods learned at agencies, to advise
agencies  that are just initiating clean-up programs, and to forewarn and prepare agencies that have not
yet realized the extent of their environmental restoration obligations.

These recommendations will require time and resources to implement. In addition, they may not be easy
to  implement  and  will  demand  trust  among  all   parties.    Through   implementation  of  these
recommendations, the Committee hopes that federal agency representatives will come to trust that the
public  and special interest groups will treat draft reports and preliminary  data appropriately and not
misrepresent the information shared with them. The Committee further hopes that, for their part, public
interest groups will come to trust that the agencies will share information willingly, not because they have
to but because they genuinely want the public's input into their decisions.

Over the long run,  the Committee believes that the recommendations set forth  in this document will
reduce the time and money spent developing remediation strategies and will promote efficiency and safety
at sites. The Committee recognizes that some recommendations  may require high-level policy changes,
acts of Congress, or time to implement effectively. The Committee's final recommendation is that each
agency and party to this Dialogue Committee commit to outlining its indentions for acting upon the above
recommendations as a first step in developing the spirit of cooperation that we all seek.

Committee members firmly believe that the types of improvements in the federal facility environmental
restoration decision-making and priority-setting process that are recommended  in this report will have
immediate and  direct benefits in relation to the pace, timing,  reduction in the overall costs, credibility
and effectiveness  of federal facility environmental restoration activities.
                                              51

-------
                                      APPENDIX A

        LIST OF FFER DIALOGUE COMMITTEE MEMBERS AND ALTERNATES



U.S. Environmental Protection Agency

Thomas L. (Tad) McCall, Jr.
Acting Deputy Assistant Administrator
 for Federal Facilities Enforcement
Office of Federal Facility  Enforcement
U.S. Environmental Protection Agency (LE-133)
401 M Street, SW
Washington, DC 20460
202-260-4543
Fax 202-260-0500

George C.  Hofer
Chief, Federal Facilities Superfund Branch
U.S. Environmental Protection Agency
Region X
1200 6th Avenue HW-124
Seattle, WA  98101
206-553-2803
Fax 206-553-0957

Jon D. Johnston
Chief, Federal Facility Branch
U.S. Environmental Protection Agency
Region IV
345 Courtland Street NE
Atlanta, GA  30365
404-347-3016
Fax 404-347-5205
                                           53

-------
EPA Alternates

Gordon M. Davidson
Director
Office of Federal Facilities Enforcement
U.S. Environmental Protection Agency(OE-2261)
401 M Street, S.W.
Washington, DC 20460
202-260-5741
Fax 202-260-9437

Nicholas I. Morgan
Strategic Planning Coordinator
Office of Federal Facilities Enforcement
U.S. Environmental Protection Agency (OE-2261)
401 M Street, S.W.
Washington, DC 20460
202-260-1270
Fax 202-260-9437

Walter Walsh
Environmental Protection Specialist
Waste Analyses  Section
Office of Policy Planning and Evaluation
U.S. Environmental Protection Agency (PM-220)
401 M Street, S.W.  Room 3003
Washington, DC 20460
202-260-2770
Fax 202-260-0174

Martha Walters
(Formerly) Special Assistant
Office of Federal Facilities Enforcement
U.S. Environmental Protection Agency (LE-133)
401 M Street, S.W.
Washington, DC 20460
202-260-3914
Fax 202-260-0500
                                             54

-------
Department of Defense

Thomas Baca
(Formerly) Deputy Assistant Secretary
 of Defense (Environment)
Department of Defense
400 Army Navy Drive, Suite 206
Arlington, VA 22202-2884
703-695-7820
Fax 703-697-7548

POD Alternates

Patrick Meehan
Principal Director
Office of Deputy Assistant Secretary
 of Defense (Environment)
Department of Defense
400 Army Navy Drive, Suite 206
Arlington, VA 22202-2884
703-695-7820
Fax 703-697-7548

Lucy McCrillis
Environmental Protection Specialist
Office of Deputy Assistant Secretary
 of Defense (Environment)
Department of Defense
400 Army Navy Drive, Suite 206
Arlington, VA 22202-2884
703-695-2364
Fax 703-697-7548

Marcia Read
Environmental Protection Specialist
Office of Deputy Assistant Secretary
 of Defense (Environment)
Department of Defense
400 Army Navy Drive, Suite 206
Arlington, VA 22202-2884
703-695-8358
Fax 703-697-7548
                                            55

-------
Department of Energy

Paul Grimm
Principal Deputy Assistant Secretary
Office of Environmental Restoration &
 Waste Management
Department of Energy EM-2
1000 Independence Avenue, SW
Washington, DC  20585
202-586-7709
Fax 202-586-7757

Kitty Taimi
Director
Office of Environmental Compliance (EH-22)
Office of Environmental Safety and Health
Department of Energy
1000 Independence Avenue, S.W.
Washington, DC  20585
202-586-2113
Fax 202-586-0955

R. Pat Whitfield
Deputy Assistant Secretary
 for Environmental Restoration
Office of Environmental Restoration
 and Waste Management
Department of Energy (EM-40)
1000 Independence Avenue, S.W.
Washington, DC 20585
202-586-6331
Fax 202-586-6523

DOE Alternates

Don Beck
Program Manager
Division of Technology Integration
Office of Technology Integration &
 Environmental Education Development
Department of Energy
EM-521, Trevionll
Washington, DC  20585
301-903-7955
Fax 301-903-7238
                                            56

-------
Tom Elsasser
Director
Office of Policy and Program Information
Department of Energy 7A-049, EM-4
1000 Independence Avenue, S.W.
Washington, DC 20585
202-586-2979
Fax: 202-586-7757

Remi Langum
Environmental Protection Specialist
Office of Program Support for
 Environmental Restoration
Department of Energy
EM 43 Trevion II
Washington, DC 20585-0002
301-903-8110
Fax 301-903-8135

Gale P. Turi
Program Integration Branch
Office of Environmental Restoration
Department of Energy
EM433 Trevion II
Washington, DC 20585-0002
301-903-8118
Fax: 301-903-8134

William Wisenbaker
Director
Office of Program Support for
 Environmental Restoration
Department of Energy
EM 43 Trevion II
Washington, DC 20585-0002
301-903-8105
Fax 301-903-8135
                                            57

-------
Other Federal Agencies

Mark M. Bashor
Associate Administrator
Agency for Toxic Substances
 and Disease Registry
1600 Clifton Rd., N.E., Mail Stop F 48
Atlanta, GA 30333
404-639-0730
Fax 404-639-0759

Alternate for M.  Bashor:

       Joe Hughart
       Deputy Director
       Office of Federal Programs
       Agency for Toxic Substances
        and Disease Registry
       1600 Clifton Rd., N.E., Mail Stop F 48
       Atlanta, GA  30333
       404-639-0730
       Fax 404-639-0759

Dr. Jonathan P. Deason
Director
Office of Environmental Affairs
Department of the Interior
1849 C Street, NW Room 2340
Washington, DC  20240
202-208-3891
Fax 202-208-6970

Alternates for J. Deason:

       John Craynon
       Environmental Protection Specialist
       Office of Environmental Affairs
       Department of Interior
       1849 C Street, N.W. (MS 2340)
       Washington, DC 20240
       202-208-7555
       Fax 202-208-6970
                                             58

-------
Sam Higuchi
Environmental Compliance and Safety Officer
U.S. Department of Commerce/NOAA
1325 East West Highway
Silver Spring, MD 20910
301-713-0845
Fax: 301-713-0806

Alternate to S.Higuchi:

       Sharon Lundin
       Chief, Facilities and Logistics Division
       U.S. Department of Commerce/NOAA WC4
       7600 Sand Point Road, NE
       Seattle, WA   98115-0070
       206-526-6191
       Fax: 206-526-6675

Joyce Jatko
Chief, Environmental Management Branch
NASA Headquarters  Code JXG
300 E Street, SW
Washington, DC  20546
202-358-0115
Fax 202-358-3866

Bill Opfer
Hazardous Waste Management Coordinator
U.S. Department of Agriculture
14th & Independence Ave, SW
Washington, DC  20250
202-205-0906
Fax 202-205-0861

Alternate to B. Opfer:

       Karen Solari
       Environmental Engineer
       USDA - Forest Service
       Engineering Division
       14th and Independence Avenue, SW
       Washington, DC 20090
       202-205-0898
       Fax:  202-205-0861
                                           59

-------
Environmental and Citizen Organizations

Tim Connor
Analyst
Energy Research Foundation
South 1016 Buena Vista Drive
Spokane, WA 99204
509-838-4580
Fax:  509-624-9188

Ralph DeGennaro
Senior Appropriations Analysts
Friends of the Earth
218 D Street, SE
Washington, DC 20003
202-544-2600
Fax:  202-543-4710

Alternate to R. DeGennaro:

       Cathy Hinds (NTCF)
       Military Toxics Project
       National Toxics Campaign
       RR 1 Box 2020
       Litchfield, ME 04350
       207-268-4071
       Fax 207-268-9258

Bonnie L. Exner-Rader
President
Citizens Intelligence Network
12600 West Colfax C-310
Lakewood, CO  80215
303-233-1248
Fax 303-233-7634

Ralph Hutchison
Coordinator
Oak Ridge Environmental
 Peace Alliance
P.O.  Box 1101
1817 White Avenue
Knoxville, TN 37901
615-426-9096 (n) or 615-524-4771 (o)
Fax 615-524-4479
                                            60

-------
Melinda Kassen
Environmental Defense Fund
1405 Arapahoe Avenue
Boulder, CO  80302
303-440-4901
Fax: 303-440-8052

Lenny Siegel
Director
Pacific Studies Center
222B View Street
Mountain View, CA 94041
415-961-8918 or 415-969-1545
Fax 415-968-1126

J. Ross Vincent
Sierra Club Representative
P.O. Box 4375
Pueblo, Colorado  81003
719-561-3117
Fax: Same as telephone

James Werner
Senior Environmental Engineer
Natural Resources Defense Council
1350 New York Avenue, N.W., Suite 300
Washington, DC 20005
202-783-7800
Fax 202-783-5917

Alternate to J. Werner:

       Dan Reicher
       Senior Attorney
       Natural Resources Defense Council
       1350 New York  Avenue, Suite 300
       Washington, DC  20005
       202-783-7800
       Fax 202-783-5917
                                            61

-------
Labor Organizations

Richard Miller
Policy Analyst
Oil Chemical Atomic Workers Union (OCAW)
2090 Northhampton Street
Holyoke, MA  01040
413-536-3858
Fax:  413-536-9616
Alternate to R. Miller:

       Charles Barrett
       Industrial Hygienist
       Oil Chemical Atomic Workers Union (OCAW)
       2722 Merrilee Drive
       Fairfax, VA  22031
       703-876-9300
       Fax:  703-876-8952

John B. Moran
Director, Safety and Health
Laborers' Health  and Safety  Fund of
 North America
905 16th Street, NW
Washington,  DC  20006-1765
202-628-5465
Fax: 202-628-2613

Alternate to J. Moran:

       Donald Elisburg
       Attorney  at Law
       Laborers' Health and Safety Fund
       11713 Rosalinda Drive
       Potomac, MD 20854-3531
       301-299-2950
       Fax:  301-299-8752
                                            62

-------
Native American Organizations and Tribal Representatives

William H. Burke
Board of Trustees
Confederate Tribes of the
 Umatilla Reservation
Old Mission Highway
P.O. Box 638
Pendleton, OR 97801
503-276-3165
Fax 503-276-3095

Alternate to W. Burke:

       J.R. Wilkinson
       Environmental Restoration Projects Leader
       Confederate Tribes of the
        Umatilla Reservation
       P.O. Box 638
       Pendleton, OR 97801
       503-276-3165
       Fax 503-276-3095

Russell Jim
Manager, Environmental Restoration and
  Waste Management Program
Yakima Indian Nation
622 West 1st Street
Watato, WA 98951
P.O. Box 151
Toppenish, WA 98948
509-865-5121 ext. 618 or 877-4151
Fax 509-877-4101

Alternates to R. Jim:

       F. Robert Cook
       Technical Analysts
       Yakima Indian Nation
       1933 Jadwin Avenue, Suite 110
       Richland, WA  99352
       509-946-0101
       Fax 509-943-8555
                                            63

-------
Stanley Paytiamo
Tribal Planner
Pueblo of Acoma - Governor's Office
1-40 Exit 102, South
P.O.  Box 309
Acomita, NM 87034
505-552-6604
Fax  505-552-6600

Merv Tano
General  Counsel
Council  of Energy Resource Tribes
1999 Broadway, Suite 2600
Denver,  CO  80202
303-297-2378
Fax 303-296-5690

Gayle Townley
Grants Program Coordinator
Cherokee Nation of Oklahoma
Junction of Hwy 62 and 82
P.O.  Box 948
Tahlequah, OK  74465
918-458-5498
Fax 918-458-5499

       Alternate to G. Townley:

       Curtis Canard
       Program Manager
       Office of Environmental Services (OES)
       Cherokee Nation of Oklahoma
       Junction of Hwy 62 and 82
       P.O.  Box 948
       Tahlequah, OK  74465
       918-458-5498
       Fax 918-458-5499
                                           64

-------
State Government Representatives

Jeff Breckel
Washington\Oregon Interstate Liaison
Washington Department of Ecology
Nuclear and Mixed Waste Program
P.O. Box 47600
Olympia, WA  98504-7600
719 Sleater-Kinney Road, SE
Suite 200
Lacey, WA 98503
206-438-7613
Fax 206-459-6859

Thomas Curtis
Director
Natural Resources Group
National Governors Association
444 North Capitol Street,  Suite 250
Washington, DC  20001
202-624-5389
Fax 202-624-5313

Sam Goodhope
Special Assistant/Attorney General
Office of the Attorney General
Administration
Price Building, 8th Floor
14th and Colorado
Austin, TX 78711-2548
512-463-2191
Fax 512-463-2063

Thomas Kennedy
Executive Director
Association of State and Territorial Solid
 Waste Management Officials
444 N. Capitol Street, N.W., Suite 388
Washington, DC  20001
202-624-5828
Fax 202-624-7875

Robert W. King
Assistant Deputy  Commissioner
South Carolina Department of Health and
 Environmental Quality Control
2600 Bull Street
Columbia, SC  29201
803-734-5360
                                            65

-------
\lternate to R.W. King:

       Lewis R. Bedenbaugh
       Director, Site Engineering & Screening Division
       South Carolina Department of Health and
        Environmental Quality Control
       2600 Bull Street
       Columbia, SC 29201
       803-734-5211
       Fax 803-734-5199

Dan Miller
First Assistant Attorney General
Office of the Attorney General
Natural Resources Section
1525 Sherman Street, 5th Floor
Denver, CO 80203
303-866-5110
Fax 303-866-3558

Lynne M.  Ross
Deputy Director and Legislative Director
National Association of Attorneys General
444 N. Capitol Street, Ste. 339
Washington, DC 20001
202-434-8054
Fax 202-434-8056

Alternate to L. Ross:

       Brian Zwit
       Environment Counsel
       National Association of Attorneys General
       444 N. Capitol Street,  Ste. 339
       Washington, DC 20001
       202-434-8041
       Fax 202-434-8056

David Shelton
Director
Hazardous Material and Waste Management Division
Colorado Department of Health, HMWMD-ADM-B2
4300 Cherry Creek Drive South
Denver, CO 80222-1530
303-692-3313
Fax 303-759-5355
                                             66

-------
Jack Allen Van Kley
Assistant Attorney General
Ohio Attorney General
Environmental Enforcement Section
30 East Broad Street, 25th Floor
Columbus, OH 43266-0410
614-466-2766
Fax 614-466-8898

Designated Federal Official

Nicholas  I. Morgan
Strategic  Planning Coordinator
Office of Federal Facilities Enforcement
U.S. Environmental Protection Agency (OE-2261)
401 M Street, S.W.
Washington,  DC 20460
202-260-1270
Fax 202-260-9437
                                            67

-------
                            THE KEYSTONE CENTER STAFF
Timothy J. Mealey - Project Director
Associate Director
The Keystone Center
P.O. Box 8606
Keystone, CO  80435
303-468-5822
Fax 303-262-0152

Kristi L. Parker
Associate
The Keystone Center
P.O. Box 8606
Keystone, CO  80435
303-468-5822
Fax 303-262-0152

John R. Ehrmann
Senior Vice President
The Keystone Center
P.O. Box 8606
Keystone, CO  80435
303-468-5822
Fax 303-262-0152

Denise A. Siebert
Administrative Assistant
The Keystone Center
P.O. Box 8606
Keystone, CO  80435
303-468-5822
Fax 303-262-0152
                                           68

-------
                    APPENDIX B
FFER DIALOGUE COMMITTEE CHARTER AND GROUND RULES
                       69

-------
               UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                           ADVISORY COMMITTEE CHARTER

   FEDERAL FACILITIES ENVIRONMENTAL RESTORATION DIALOGUE COMMITTEE

1-     PURPOSE.  This charter establishes the Federal Facilities Environmental Restoration Dialogue
       Commitee, in accordance with the provisions of the Federal Advisory Committee (FACA), 5
       U.S.C. App. II  § 9(c).

2.     AUTHORITY.  It is determined that establishment of this Cormiittee is in the public interest and
       supports EPA  in performing  its duties  and  responsibilities under Section  120  of the
       Comprehensive  Environmental Response Compensation and Liability Act (CERCLA),  Section
       6001 of the Resource Conservation and Recovery Act (RCRA),  and other authorities pertaining
       to the environmental restoration of Federal facilities.

3.     OBJECTIVE AND SCOPE OF ACTIVITY.  The Committee will provide a forum to refine and
       further develop  issues related to environmental restoration activities at Federal facilities.  The
       forum will facilitate the exchange of ideas and information among interested parties. It is hoped
       that consensus may be possible on these issues, but at a minimum, EPA would like to ensure that
       issues  are thoroughly refined and that  differing positions, as  well as the reasons  for those
       differences, are  identified. A final  report describing the results of the dialogue will be prepared.

4.     FUNCTIONS.   As  indicated above, the Committee's  function is  to assist  directly  in the
       development of EPA and Federal agency  efforts  to  address  Federal facility environmental
       restoration programs. With the participation of knowledgeable, affected parties, EPA expects to
       develop a practical approach to Federal agency environmental restoration efforts which will best
       protect human health and the environment within guidelines and principles that have broad public
       support and national applicability.

5.     COMPOSITION. The Committee  will consist of not more than forty (40) members, appointed
       by the EPA Deputy Administrator, plus a facilitator who wih serve as Chair.  Members will
       represent the following interests in  an  appropriate mix and balance:

       Categories of Members:

              Public interest/environmental groups
              Tribal Government and Native American representatives
              State Government representatives
              Federal  Agency representatives
              Other Interested and Affected  Parties

       Appropriate members shall be selected  and appointed for the duration of the Committee's charter.
       A full-time salaried official or regular employee of the Agency will serve as  the Designated
       Federal Officer and will be present at all meetings. The Designated Federal Officer is authorized
       to adjourn any meeting whenever  it is determined to be  in the public interest to do so.  The
       Committee is authorized to form work groups for any purpose consistent with this Charter.  Such
       work groups shall report back to the full Commitee. Work groups have no authority to make
       decisions on behalf of the full Committee not can  they report directly to the Agency.
                                             71

-------
       Under the Federal Advisory Committee Act, EPA may pay travel and per diem expenses when
       necessary and appropriate.  The Committee's estimated annual operating cost is approximately
       $200,000, which includes .5 work years of staff support.  EPA's Office of Enforcement will
       provide administrative and process support to the Committee.

6.     MEETINGS. Meetings shall be held as necessary, at the call of the Chair, with an agenda for
       each meeting approved in advance by the Designated Federal Officer.  Committee meetings will
       be called, announced,  and held in accordance with the EPA Committee  Management Manual.
       This manual contains the Agency's policies and procedures for implementing FACA.  Among
       other things, FACA requires open meetings and an  opportunity for interested persons to  file
       comments before or after meetings, or to  make statements to the extent that time permits.

7.     DURATION. The Committee will terminate by June 30, 1993, unless the Deputy Administrator
       determines that the Committee will finish its work within 30 days of the original termination date.
       If the Deputy Administrator  makes such a determination, he may extend the termination date by
       30 days without further consultation with GSA.  In the event more time is needed, EPA may seek
       an extension under Section 14 of FACA.

March 13. 1992                                           F. Henry Habicht II
Agency Approval Date                                     Deputy Administrator
April 29. 1992
GSA Consultation Date
April 29. 1992
Date Filed with Congress
                                             72

-------
                                      GROUND RULES

                 FEDERAL FACILITIES ENVIRONMENTAL RESTORATION
                                 DIALOGUE COMMITTEE

 I.      Objective of the FFER Dialogue Committee

 As stated in its charter, the FFER Dialogue Committee will provide a forum to refine and further develop
 issues related to environmental restoration activities at Federal facilities. The forum will facilitate the
 exchange of ideas and information among interested parties.  The goal of the FFER Dialogue Committee
 is to develop consensus policy recommendations aimed at improving the process by which federal facility
 environmental restoration decisions are made such that federal facility cleanups better reflect the priorities
 and  concerns of all stakeholders.

 It is  hoped that consensus may be possible on how to address these issues, but at a minimum, EPA would
 like  to ensure that issues are thoroughly refined and that differing positions, as well as the reasons for
 those differences, are identified.  A final report describing the results  of the dialogue will be prepared.
 The  output of the FFER  Dialogue Committee will be made available to various decision-makers who are
 concerned with  federal facility environmental restoration issues.

 II.     Membership in  the FFER Dialogue Committee

 Membership on the FFER  Dialogue Committee will be limited to:

        •       three each  from the U.S.  Environmental Protection Agency, the Department of Defense
               and the Department of Energy;

        •       one  each  from   the Department  of Interior,  Department  of Agriculture,  National
               Aeronautics and  Space Administration and  the Agency  for  Toxic Substances Disease
               Registry;

        •      ten state  government and/or state government association representatives;

        •       six Native  American/Tribal government representatives;  and

        •      ten environmental/citizen/labor representatives.

 Committee members may identify alternates who may participate in Committee meetings in their absence
or in work groups that  are  established by  the full Committee.  To the degree possible Committee
membership should  not change  once it  has  been announced.  A  representative of the Office of
Management and Budget will participate as an ex-officio  member of the  Committee.

III.    Decision-making

The  Committee will operate  by  consensus with regard to any recommendations that are made by the
Committee on substantive policy issues.  However,  if consensus on specific substantive proposals is not
possible, the Committee  will  make every effort to articulate in writing in its  final report both the areas
of agreement and disagreement  and the reasons why there continues  to be  differences.  The  term
consensus means that a proposal can be considered to have achieved consensus if there is no dissent by


                                             73

-------
any member of the Committee.  Major procedural issues, including but not limited to whether to add new
members to the Committee and whether to issue a final  report,  will also be made by consensus.  For
routine procedural matters, the Committee's facilitator  will make every effort to find a consensus
solution.

IV.    Meetings  of the FFER Dialogue Committee

The FFER Dialogue Committee will operate as a federal advisory committee under the provisions of the
Federal Advisory  Committee Act.  Accordingly, all meetings of the FFER Dialogue Committee will be
open to the public, subject to the exemptions granted in the Government in the Sunshine Act.  Adequate
notice of the time and location of future PDC meetings  will be  published in the Federal Register  and
meeting summaries will be kept and made available to the public. At the very least, at each Committee
meeting,  a half-hour at the end of the meeting and, if possible, at the end of each  meeting  day, will be
reserved  to provide  an opportunity for members of the public to comment on the deliberations of the
Committee.

V.     Use of Work Groups. Subcommittees and Caucuses

The FFER Committee will generally operate as a committee  of the whole.  When necessary  and
appropriate, the Committee may create work  groups and subcommittees to  pursue certain  topics.
Decisions on the creation of work groups and subcommittees will be made by consensus.  Every effort
will be made to ensure that all work groups that are officially formed by the Committee reflect roughly
the same  balance that has been achieved in the Committee as  a whole. When necessary and appropriate,
Committee members may request a break in the deliberations in the Committee to meet for a reasonable
period of time in a private caucus with other Committee members.

VI.    Issuance of  a Final Report

Subject to final consideration by the FFER Committee, it is  envisioned that the Committee will issue a
report separate from the individual meeting summaries that will be prepared to summarize the outcome
of the Committee's deliberations at each full Committee meeting.  This report will include any consensus
agreements that are reached by the group and their associated  recommendations, as well as any remaining
areas of disagreement and the substantive reasons for these disagreements.  This report will  be prepared
by the  facilitator  with assistance from  Committee members and will  be  issued in  draft form  to the
Committee,  with ample  time for comments and revisions, prior to being issued as a final  report.   As
noted above, the  decision of the  Committee as to whether to  issue a final  report will be made by
consensus.
                                             74

-------
                                         APPENDIX C

               HISTORY AND DESCRIPTION OF THE FEDERAL FACILITIES
                 ENVIRONMENTAL RESTORATION DIALOGUE PROCESS

In February, 1989, the House Armed Services Committee's Subcommittee on Procurement and Military
Nuclear  Systems conducted a hearing on the process  used by DOE to set priorities for conducting
environmental  restoration activities at its nuclear weapons facilities.   The hearing, which included
testimony by DOE, the General Accounting Office (GAO), and the Natural Resources Defense Council,
addressed many aspects of DOE's priority setting methodologies.

In April  1989, the Governors often states sent the Secretary of Energy a letter calling for decisive federal
action on the establishment of a comprehensive national program for the clean-up of all DOE defense and
research facilities.  The proposal  put  forth by the Governors contained a discussion of several  key
elements for a  national program.  One element was the need to develop a national priority system for
ensuring that appropriate priorities for DOE clean-ups were established.

Shortly thereafter, the Administrator of the U.S. Environmental Protection Agency (EPA), sent to the
Director of the Office of Management and Budget (OMB) a letter summarizing the concerns of several
federal departments regarding the need to establish national environmental and funding priorities for the
clean-up  of federal facilities.  In this letter, the Administrator proposed that EPA convene a conference
with representatives of other federal and state agencies to begin discussing the issue. Subsequently, EPA
proposed convening a formal dialogue on the issues related to the establishment of federal facility clean-
up priorities.  Further support for a national dialogue on priority-setting for federal facility clean-ups
came in July, 1989 when 49 Attorneys General sent an open letter to the U.S. House of Representatives.
This letter expressed support for a dialogue on federal facility clean-up issues as a means of strengthening
state-federal relationships.

Based on these public indications of support for a dialogue,  EPA asked The Keystone Center (TKC), a
non-profit  environmental conflict management group located  in Keystone, Colorado, in late  1990 to
convene  a  national policy dialogue on federal facility environmental restoration priority-setting.  As is
typically done  in such  circumstances, Keystone  Center staff conducted a  series of interviews  and
discussions with key stakeholders to confirm support for  the idea  of a national policy dialogue and to
determine what specific policy issues should be the focus of the proposed dialogue and who should
participate.

These convening assessment activities led to the formation of a small ad hoc panning group that consisted
of representatives of several federal agencies, state agencies and state governmental associations, national
environmental groups, and others.  This ad hoc planning group, which met in January 1991, was
designed to give The Keystone Center advice as to whether and, if so, how to proceed with the proposed
dialogue.  At the time that The Keystone Center was asked to convene a dialogue to address  federal
facility priority-setting, an important issue was  congressional debate over the proposed Federal Facility
Compliance Act. This Act would authorize states to impose fines and penalties on federal  agencies for
violations under the Resource  Conservation and Recovery Act.  Federal agencies were concerned that
they would now be subject to fines for failure to meet schedules in enforcement agreements for clean-up
where insufficient funds were appropriated. Federal agency representatives believed that there was a need
for a "system" that would establish how to set priorities in the event insufficient funds are appropriated
to meet all federal clean-up obligations.
                                              75

-------
After addressing concerns about any links that might be created between the proposed dialogue and
pending federal facility environmental compliance legislation, the diverse interests attending the January
1991  meeting agreed that a dialogue on federal facility environmental restoration decision-making and
priority-setting issues would be worthwhile.  They agreed that the proposed dialogue should not be linked
to pending legislation or be used by any dialogue participant as a reason to delay congressional debate
on pending federal facility legislation.

The assembled advisory/planning group  agreed that the dialogue should, at the  outset, have as its
objective the exchange of information and perspectives on federal facility environmental management and
priority-setting issues rather than the development of consensus agreements on these issues. Furthermore,
the group agreed that the initial focus of the dialogue should be issues related to the need to  set priorities
for the clean-up  of  federal facilities, with the possibility of addressing  other critical federal facility
environmental management issues in the future.

The first  meeting of the  National Policy Dialogue on Federal Facility Environmental Management
occurred on June 12-13, 1991 in Washington, D.C.  This meeting  included representatives of tribal
governments and Native American organizations and local citizen groups, as well  as the interests that
were represented at the January,  1991 planning meeting.  The June 1991 meeting included presentations
from  DOD, DOE and EPA officials on a variety of environmental remediation related priority-setting
mechanisms, models, systems, and processes that are currently being used by these agencies. The group
then had  a general discussion of federal facility priority-setting issues and  identified  some topics to
address at its next meeting.

In October,  1991 the Dialogue Group met again  to discuss the role of health assessments  and the
consideration of risk  in setting priorities for federal facility clean-up; how Native American cultural issues
should be factored into the priority-setting process; and the role that various governmental and  non-
governmental entities should play in setting priorities for federal facility clean-ups.  At its October  1991
meeting the Dialogue Group agreed that if they were to continue meeting they should not simply exchange
information and perspectives but adopt an  objective of developing consensus policy recommendations on
how to improve upon the federal facility environmental restoration decision-making process.

The Dialogue Group, met again in December, 1991 and February, 1992 operating with its new consensus
objective.   At these  meetings,  the  group identified several distinct phases in  the  federal facility
environmental restoration decision-making process that could be used as specific references to help focus
their discussions. Based on these distinctions, work groups were formed to developed recommendations
for consideration by  the larger plenary group.

During the course of its discussions, the Dialogue Group noted that:  1) existing data and science are
currently  inadequate to  determine  objective consensus clean-up  priorities; 2)  factors  other  than
environmental and human health risk deserve consideration in allocating clean-up resources; 3) broadly
acceptable and objective methods for evaluating some of the criteria relevant to the allocation of clean-up
priorities do not currently exist, and, in some cases, may never exist and may even be inappropriate; and
4) regardless of any  party's opinion about the quality of available dat? and science, it is appropriate in
a democracy to allow a variety of affected interests to provide input on decisions that affect them.

At the February 1992 meeting of the Federal Facility Environmental Management Policy Dialogue Group,
representatives of EPA, the lead federal  agency for the project, suggested that the entire effort should be
chartered  as an advisory committee under  the auspices of the Federal  Advisory Committee Act (FACA).
The dialogue group agreed and EPA began taking steps towards this end.


                                               76

-------
                                       APPENDIX D
          STATUTORY PROVISIONS FOR TECHNICAL REVIEW COMMITTEES
DOD is  required by  law to  establish site-specific advisory  boards.   The Defense Environmental
Restoration Program (DERP),  which has been in existence since the late 1970s, was codified  by the
Superfund Amendments and Reauthorization Act of 1986 (SARA).  SARA Section 211 amended Title
10 of the United States Code by creating a new Chapter 160. These amendments contain Section 2705
(c) which reads, in its  entirety:

       Technical  Review Committees - Whenever possible and practical, The Secretary shall
       establish a technical review committee to review and  comment on DOD actions and
       proposed actions with respect to releases or threatened releases of hazardous substances
       at installations.  Members of any such committee shall include at lease one representative
       of the Secretary, the Administrator, and appropriate state and local authorities and shall
       include a public representative of the community involved.

While the law only requires that other federal agencies meet the community relations requirements that
are spelled out in the National Contingency  Plan (NCP) and EPA guidance (i.e., preparation of
Community Relations Plans, public comment periods on proposed plans, and availability of TAGs), DOD
must additionally  meet the requirements  of SARA  Section 211.   This  section provides for DOD to
establish TRCs at both NPL and non-NPL sites. At this time, there does not appear to be any national
guidance by DOD  or EPA on the establishment of TRCs.
                                            77

-------