>EPA
           'Jrtited States
           Environmental Protection
           Agency
            Cffcs =f Water
            iWH-595)
EPA 420 09-89-007
August 1989
                                   BALLAS, TEXAS

                                     LIBRARY
Start-up And Operation*
Chemical Process
Technologies In The
Municipal Sector
The Carver-Greenfield
Process For
Sludge Drying
                                            V

-------
               STARTUP AND OPERATION OF

CHEMICAL PROCESS TECHNOLOGIES IN THE MUNICIPAL SECTOR:

   THE  CARVER-GREENFIELD  PROCESS FOR SLUDGE DRYING
                          by

         A Review Team of Engineers  from  the
       Chemical Process and Petroleum Refinery
                      Industries

                   Manuel Gonzalez
                   Frank Y.W. Liao
                 Kathryn A.  Pluenneke
                     Gilbert Rowe
                   Martin J.  Siecke
                         for

         U.S.  ENVIRONMENTAL PROTECTION AGENCY

           EPA Contract No. 68-03-3470/0-14
           John M. Walker, Project Manager
        Office of Municipal Pollution Control
                Washington,  D.C.  20460

      Harry E. Bostian, Work Assignment Manager
        Risk Reduction Engineering Laboratory
                Cincinnati,  Ohio  45268

-------
                      TABLE OF CONTENTS
          LIST OF FIGURES
          EXECUTIVE SUMMARY
 ill
   v
Section
          INTRODUCTION                       •           1-1
          1.1. Objectives and Scope of Project          1- 3
          1.2. Approach to Task                         1- 4

          SUPPORTING A MUNICIPAL SEWAGE SLUDGE DRYING
             CARVER-GREENFIELD FACILITY                 2- 1
          2.1. Initial Startup                          2- 1
          2.2. Data Collection and Retention            2- 4
          2.3. Pre-Startup Activities                 -  2- 4
          2.4. Plant Staffing for Normal
                  Operation and Maintenance             2- 6
          2.5. Personnel Training                       2- 7
          2.6. Operations Documents                     2- 8
          2.7. Health and Safety Documentation and
                  Procedures                            2-10
          2.8. Technology Acquisition and Retention     2-13

          RECOMMENDATIONS TO THE MERCER COUNTY
             IMPROVEMENT AUTHORITY                      3-1
          3.1. Permanent Staff                          3-3
          3.2. Additional Startup Assistance            3- 7
          3.3. Training Program                         3- 9
          3.4. Startup Planning Considerations          3-10
          3.5. Assuring Continued Operations            3-11
          3.6. Mode of Plant Operation                  3-11

          IMPLEMENTATION OF CHEMICAL PROCESS
             TECHNOLOGIES FOR MANAGEMENT OF
             MUNICIPAL WASTES                           4- 1
          4.1. Factors That Influence Facilities
                  in Municipal Applications             4- 1
          4.2. Making the Transition                    4- 4
          4.3. Obtaining Necessary Skills/Training      4- 5
          4.4. Cost and Operational Expectations        4- 7

          REFERENCES                                    5-1
Appendix

   A      THE CARVER-GREENFIELD PROCESS
A- 1

-------

-------
Appendix                                                Page

   A (con1t.)
          A.I. Heavy and Light Oil Carver-
                  Greenfield Processes                  A- 1
          A.2. Carver-Greenfield Multiple Effect
                  Evaporation                           A- 2
          A.3. Carver-Greenfield Mechanical
                  Vapor Recompression                   A- 4

   B      QUALIFICATIONS OF INDUSTRIAL REVIEW TEAM
             MEMBERS AND EPA PROJECT MANAGEMENT         B- 1

   C      OTHER OBSERVATIONS BY INDUSTRIAL REVIEW
             TEAM MEMBERS                               C- 1

   D      ACKNOWLEDGEMENTS                              D- 1

   E      STATUS OF THE CARVER-GREENFIELD MUNICIPAL
             SEWAGE SLUDGE DRYING FACILITIES:  A
             BRIEF UPDATE                               E- 1
          E.I. The City of Los Angeles Facility         E- 1
          E.2. Facilities Under Construction            E- 4
                             11

-------
                       LIST OF FIGURES
Number                                                  Page

   1      Mercer County Improvement Authority
             Plant Staffing Schedule                    3- 4

   2      Mercer County Improvement Authority
             Normal Operations Organization             3- 5

   3      Mercer County Improvement Authority
             Initial Startup Organization               3- 8

   4      Four-Stage Carver-Greenfield Municipal
             Sewage Sludge Drying System                A- 3

   5      Carver-Greenfield Mechanical Vapor
             Recompression Sewage Sludge
             Drying System                              A- 5

   6      City of Los Angeles Carver-Greenfield
          Facility Production Statistics                E- 3
                             111

-------
                      EXECUTIVE SUMMARY

                  STARTUP AND OPERATION OF
    CHEMICAL PROCESS TECHNOLOGIES  IN THE MUNICIPAL SECTOR:
       THE CARVER-GREENFIELD PROCESS FOR SLUDGE DRYING
Environmental considerations  have  led  to  the  introduction of
more  sophisticated  methods  of treatment  and disposal of
municipal wastes than have been practiced  in the past.   In
many  respects,  these  new techniques are  similar  to those
used  in the  chemical  processing  and  petroleum  refining
industries,  which  have  over  many years  developed  and
implemented complex processes  for  their  own purposes.   For
the  purpose  of  simplifying the  text,  "chemical process
industries" will be  used in this  report  to  refer  to those
industries  involved in  chemical manufacturing  and  petroleum
refining.

The  Carver-Greenfield   Process is  an  example  of  a  more
complex  technology that has  been  adapted  to  the drying of
municipal sewage sludge.    There  are  currently  four
Carver-Greenfield municipal  projects  in  the  United  States,
three under construction and the  fourth  involved in  a  long
and difficult startup.

It  has   become  increasingly  apparent, especially after the
United   States  Environmental  Protection Agency  (EPA)
sponsored  a workshop  in 1987 on  the  Carver-Greenfield
municipal projects, that a number  of  startup problems could
be due  to  difficulties  with  the approach and  experience of
the  startup  personnel  as well  as with  the design  of the
system.    To  further explore  this  area,  EPA  decided to
organize an industrial  review team of  engineers with  startup
and  operations  experience in the  chemical  process
industries.  The designer of  the Carver-Greenfield  municipal
sewage  sludge plants,   Foster  Wheeler USA Corporation,  was
instrumental in making  initial contact with a  number of the
larger chemical processing and  petroleum refining  companies
in  the  United  States,  and  in  assisting  EPA to  screen
potential candidates for the  review team.

A five-person industrial review team was  assembled in June,
1988.  After  studying background information on  the  Carver-
Greenfield Process  and the four municipal   sewage  sludge
drying projects in the  United  States, the  Industrial Review
Team gathered further information  on  these projects  through
a series of meetings with representatives of  three  of the
project  owners:   the Mercer  County (New Jersey)  Improvement
Authority,  the  City of  Los Angeles, and  the Los  Angeles
County Sanitation Districts.
                             v

-------
Based  on  their  professional  experience  with  chemical
processing installations  and  the  information gathered in the
course  of this project,  the Industrial Review Team developed
certain  conclusions  and  recommendations  regarding  the
startup,  operation,  and maintenance  of Carver-Greenfield
municipal sewage sludge  drying  plants.  Recommendations were
also developed for the general  case  of implementing chemical
process technologies in a municipal application.

The Mercer County Improvement Authority  plant,  which was in
construction  at  the  time  of  the  review,  was  chosen  for
specific  case  study,  and  suggestions  were  developed  for
starting  up,  operating, and  maintaining  that  facility.
Because the City  of  Los Angeles  Carver-Greenfield facility
was the  only  plant of  its  type  that was completed  and in
startup at  the  time  of  this review,  it was  of particular
value  in  developing the  material presented  in this report.
A brief update has been included  regarding progress that has
occurred  at  that facility  and  the  facilities under
construction  since  the first  draft  of this  report  was
presented in September, 1988.

The Carver-Greenfield  technology  is substantially different
from traditional  municipal wastewater and  sewage sludge
management systems,  with process  characteristics, equipment,
and  unit  operations  found more frequently in  chemical
processing systems.   This process involves flammable liquid
and  vapor,  operation under  reduced pressure,  and
feedforward/feedback complexity.   Because of  its similarity
to chemical plant  and  petroleum  refinery operations,  it is
to be  expected  that those  practices  that have proven to be
essential in industrial  facilities will prove to be of value
in municipal sewage sludge drying Carver-Greenfield plants.

For the startup of a facility similar to  a Carver-Greenfield
municipal sewage sludge  drying  plant, chemical and petroleum
companies have  found that  a  team of  engineers  with many
years  of specialized  experience  starting up  and operating
the type of equipment  and unit  operations present in the new
facility  are  needed  on a  twenty-four-hour-per-day basis,
seven  days per week.   After  the plant  achieves  normal
operation,  fewer  engineers are  required.   Daily coverage
five  days  per  week  and  on-call  weekends is  normally
adequate.

In  addition to  startup  and/or operations  engineers,  there
are  certain specialized technical  skills and talents that
have proven  to be essential to the  successful  startup,
operation,  and  maintenance  of complex  chemical processing
facilities.   These  include  health  and  safety,
corrosion/materials,  piping  stress,  thermal  expansion,
instrumentation, rotating machinery,  and  electrical/

                             vi

-------
utilities expertise.   There are also certain practices, such
as the development and maintenance  of  detailed documents on
how to  operate  and maintain  the plant  that  are  vital not
only  to  a  successful  startup effort  but for  continued
operations.

Because  the potential  for serious disaster with chemical
processing  systems  is much  greater  than with  typical
publicly-owned  treatment works units,  great emphasis must be
placed  on health  and  safety.   Industrial experience has
proven that risk can be  reduced and controlled  at  acceptable
levels  by planning,  practicing, and  continually reviewing
health   and  safety procedures.   A  health and  safety
specialist  experienced  with chemical  processing systems
should be involved with  the project prior to initial startup
to  assure  that  all  health  and  safety planning,
documentation,  and  training programs are in place.  A member
of  the  plant's  permanent  engineering  staff   should  be
designated safety officer responsible  for  carrying  out and
continually updating the program.

Preparations for  initial  startup  should begin many months
before  the end  of construction,  to  allow  time  for
development of  a startup  plan, hiring and  training
personnel,  developing  operations  documents,  arranging for
maintenance services,  monitoring the  final   phases  of
construction, developing an inventory of spare  equipment and'
parts,  locating  specialty mechanical  service   shops  for
particular jobs,  and  pre-commissioning.    Startup
preparations  should include  planning  for and locating
temporary startup expertise,  in the form of full- or part-
time  personnel  with specialized  background  in starting  up
and  operating chemical  processing  facilities.    These
personnel  are available by  contract from  a   number  of
companies.   One  option  for  municipalities  is to contract
directly  for comprehensive services with  a single  company
that specializes in startup of similar facilities.

The  initial startup of  a chemical  processing facility
frequently  requires  some  modification  to  the  system.
However,  it must be remembered that the primary objective is
to get  the  plant to operate  continuously  as designed,  and
not  to  change,  optimize,  or debottleneck  until  after
continuous  operation is  achieved.   Experience  has proven
that  changes other  than  those  where  design  or equipment
problems  actually  prevent continuous  operation  should  be
postponed.   There  are  a  number of reasons for this approach,
including the fact that  problems  at low  operating rates may
not  be   significant at  high  rates,  and  that continuous
operation is essential to  maintaining  personnel  morale and
gaining  operations experience.
                            VII

-------
For plants that involve process and/or equipment innovations
compared to existing facilities,  chemical/petroleum  industry
experience suggests that process modifications  amounting  to
as  much as  ten percent of  the  capital cost  of the  plant
might  be expected.    In addition to  modifications,  other
startup expenses might run as high  as  another  ten percent  of
the  capital  cost  of  the  plant.    Adequate  funds for  both
startup and modification expenditures should be  included  in
the project budget.   Also,  immediate  access to  funds  should
be  arranged  before   initial  startup  is attempted,  because
many  startup  expenditures  must  be  made  on an  emergency
basis.

In  any  facility where  a technology is being implemented for
the  first time  in a  particular application,  it is  likely
that  the  facility  will not  achieve  one hundred percent  of
design  capacity  as originally installed.   The plant  owner
should have  contingency  arrangements  for  treating and
disposing of  the  feedstock  while modifications are made  on
the new facility.

Through discussions  with  the Carver-Greenfield  municipal
plant owners,  it became apparent that there are  a  number  of
factors inherent in municipal  organizations that  complicate
the implementation of  such complex  technologies.  There has
been  little  opportunity  in  the  past  for the. municipal
facility owner  to   develop startup,  operations,  and
maintenance  expertise  for unfamiliar complex systems.
Restrictions  on  hiring,  wage  scale,  and promotion and
benefit practices may make it difficult  to  hire  and  keep the
more highly  trained and properly experienced  personnel  that
are needed.   This  situation leads  to dependence  on  outside
sources for expertise.   These outside  sources  may not  be
able to provide enough highly trained personnel,  because the
need for such  personnel in  municipal  facilities  is  a  fairly
recent development.   There   are  also  a  number of
institutional obstacles  to  implementing more  complex
technologies in municipal applications,  including
authorization, procurement,  and  purchasing practices  that
are not adapted to  the demands of operating such facilities.

The startup, operation, and maintenance  of  Carver-Greenfield
municipal  sewage  sludge drying  plants require  different
skills  and  procedures than are  required for  traditional
municipal treatment systems.  By way  of general assessment,
the Review Team found  that,  as of July,  1988,  the approaches
for startup  being  used or planned  by the  Carver-Greenfield
municipal  facilities visited during  this  review were not
adequate to successfully perform the task.

Acquiring new skills,  modifying procedures,  and dealing with
the  restrictions  imposed by  municipal  practices present  a

                            viii

-------
significant challenge  to the owner of a  chemical processing
type facility  in  a municipal application.   Flexibility and
innovative  thinking will be  required  to  successfully
accomplish this transition.

The emphasis  of this  report is  on startup,  operation, and
maintenance of  facilities.   This  report  is  not intended to
be  a  review  of   the Carver-Greenfield  technology,  its
appropriateness for  the municipal sewage  sludge  drying
application,  cr the design  of  any of the Carver-Greenfield
facilities mentioned.
                            IX

-------
                         SECTION 1

                        INTRODUCTION
The  Carver-Greenfield Process  is a  patented drying
technology (briefly described  in  Appendix  A)  that has been
applied to a variety  of  feedstocks and has been adapted for
the drying of municipal  sewage sludge.  There are  currently
four major Carver-Greenfield municipal sewage sludge drying
facilities  in  various  stages  of  completion  in  the United
States, three under construction and the fourth involved in
a long and difficult startup.

The Carver-Greenfield technology is  substantially  different
from  traditional  municipal wastewater and  sewage sludge
treatment systems, with  process  characteristics,  equipment,
and  unit operations  found  in  chemical processing  systems.
The Process involves flammable  liquid and vapor, operating a
vacuum system,  and feedforward/feedback complexity.  For the
purpose  of  simplifying  this  text,  the   phrase   "chemical
processing" will be  used  to  indicate both   chemical
manufacturing and petroleum refining.

It became increasingly apparent,  especially after  a workshop
was sponsored by  the  United  States Environmental  Protection
Agency  (EPA) in 1987  on the  Carver-Greenfield  municipal
projects,  that  a number  of the  startup  problems could be due
to difficulties  with the  approach and experience of the
startup personnel as much as with  the design of the system.
To further  explore  this  area,  EPA decided  to  organize  a
review team with startup and  operations  expertise  in
chemical  and  refinery  processes.   The  designer of  the
Carver-Greenfield municipal  plants, Foster  Wheeler USA, was
instrumental  in making initial  contact with a number of the
larger chemical and petroleum  companies  in  the  United
States, and in assisting EPA to  screen potential  candidates
for the review team.

This  report presents the  findings  and  recommendations  of
that  industrial  review team,  who,  on behalf of EPA, applied
their  professional  expertise  from the  chemical process
industries to the  problems  of starting up,  operating,  and
maintaining  a  Carver-Greenfield  municipal  sewage sludge
drying facility.

The chemical engineers who  served  on the  Industrial Review
Team  are (see also Appendix B):

          Mr.  Manuel Gonzalez  of Mobil  Research and
          Development Corporation  (twenty-four  years  total
          technical experience),

                            1-1

-------
         Mr.  Frank  Y.  W.  Liao  of  Mobil  Research  and
         Development  Corporation  (twenty  years  total
         technical experience),

         Ms.  Kathryn  A.  Pluenneke  of Technical Services;
         previously with Dow Chemical  Company  (eleven years
         total technical experience),

         Mr.  Gilbert  Rowe  of  Environmental Consultants;
         previously  with Exxon Corporation  (thirty-seven
         years total  technical experience),

         Mr. Martin J. Siecke,  P.E.,  of National Starch and
         Chemical Corporation (twenty-five years  total
         technical experience).
EPA Project Management:
         Dr.  Harry  E.  Bostian,  P.E. ,  Chemical Engineer,
         Risk Reduction  Engineering  Laboratory,  EPA,
         Cincinnati,  Ohio;  previously  with  Exxon
         Corporation and Universities  of New Hampshire and
         Mississippi  (thirty  years  total  technical
         experience),

         Dr.  John  M.  Walker,  Physical Scientist, Office of
         Municipal  Pollution Control,  EPA, Washington,
         D.C.;  previously  with  U.S.  Department  of
         Agriculture  (twenty-eight  years total technical
         experience).
The members  of  the  Review  Team wish to  stress  that  the
limited  time  available  for  this review precluded detailed
evaluation  of  startup  problems and  of  operational
solutions.   The Team's  efforts  were  directed at determining
the status of  current  startup,  operations,  and maintenance
activities,  so that  they could provide  information based
upon  their professional  experience by which  the startup,
operations,  and maintenance  personnel, systems,  and
approaches  could  be  modified  to better  meet the needs of a
Carver-Greenfield municipal  sewage  sludge  treatment
facility.

By way of general  assessment,  the Review Team found that, as
of  July,  1988,  the  approaches  for startup being  used or
planned by  the  Carver-Greenfield municipal  facilities
visited during  this review were not adequate to successfully
perform the task.   While conditions  varied  from location to
location,  it was  obvious to  the Team that  there  was in
general  a  lack  of  familiarity with  the  requirements  for
successful  startup and operation  of  chemical  processing

                           1-2

-------
systems.   Problems observed  (see  also  Appendix  C)  included
lack  of  properly  trained and  experienced personnel  for
startup  of  the  relatively complex installations, inadequate
use of  monitoring  and  sampling for documentation and control
of component  performance,  and, as  of July,  1988, not having
run  all  parts  of the  system per  the design  (e.g.,  acid
addition and sewage  oil  separation components).    Lack  of
experience  with  starting up  chemical/refinery  type  systems
had apparently  contributed to the problems  with bringing  a
major  Carver-Greenfield  municipal sewage  sludge  drying
system  into full operation.

As a  basis  for improvement, the Review Team has met with the
several municipalities for  frank and open  discussions  of
problems  and  possible  solutions and  has prepared this short
informational document.   The Team  gained  a great  deal  of
insight  regarding the  problems surrounding  the
implementation of  the  process in  the  municipal environment
and hopes that the  plant  owners   and operators,  the system
developer,  and  the system designer have  also  gained  from
this  exchange of information.   The frankness and cooperation
of all  those  individuals who  met  with the  Team is  greatly
appreciated (see Appendix D).
1.1. Objectives and Scope of  Project

This project was undertaken  to develop suggestions, based on
professional  experience with chemical  processing systems,
for  the  startup,   operation, and maintenance of  Carver-
Greenfield municipal  sewage  sludge drying  facilities.   This
report outlines the staffing, personnel training, operations
documents,  and  other  support  that the  chemical  process
industries  would typically provide  for  the successful
startup  and  operation of  such  a  facility.   As a specific
case,  suggestions  are presented  for the Mercer County (New
Jersey)  Improvement  Authority facility,  which  is  currently
under  construction.   On  a  larger  scale,  general
considerations are  presented for  future municipal projects
involving  technologies of  a  similar  complexity  to  the
Carver-Greenfield Process.

A brief  update of  the status of  the four  Carver-Greenfield
municipal facilities,  particularly the  City of  Los  Angeles
facility, is included in Appendix E.   Many of the activities
which  have  occurred  since   this  review was undertaken  in
July, 1988, are  consistent with  recommendations  made  by the
Review Team.

The  emphasis  of  this  report is  on  startup,  operation,  and
maintenance of facilities.   This report  is  not intended  to
be  a  review  of  the Carver-Greenfield technology,  its

                             1-3

-------
appropriateness for  the municipal  sewage sludge  drying
application,  or the  design  of any of  the  Carver-Greenfield
facilities mentioned.
1.2. Approach to  Task

At  the beginning  of  the project,  documentation  concerning
the  Carver-Greenfield  Process  (see  References)  and the
Piping and  Instrument Diagrams  and Operating Manual of The
Mercer  County Improvement  Authority  (MCIA)  Project were
distributed to and studied by each  member  of  the  Industrial
Review Team.  Additional information was gathered through a
series  of meetings held  in New  Jersey  and California and
from  design  and  operating documents examined  at  the  three
California locations.

The  first  project  meeting  was  held  in   the  MCIA
building  in  Trenton,  New  Jersey,  on July 8,  1988.   The
morning  meeting  was  attended  by the Review  Team  and EPA
Project  Management.   At  noon,  this  group  was  joined by
representatives of:

          MCIA and its  supporting  municipalities  (Trenton,
          Hamilton, and Ewing-Lawrence);

          Clinton Bogert  Associates  (the  prime  contractor on
          the MCIA Project);

          Foster  Wheeler  USA  (subcontractor to  Clinton
          Bogert  and  licensee  of  the Carver-Greenfield
          Process  for the MCIA Project);

          Dehydro-Tech  Corporation (licensor of the  Carver-
          Greenfield Process).

Included in the afternoon session was  an inspection  tour of
the MCIA project  construction site.

Two  days,  July  11 and  12,  were  spent at   the  City of Los
Angeles Hyperion  Energy  Recovery System facility  in  order to
collect  as  much information as  possible  about   the  single
existing  Carver-Greenfield  facility in  a   municipal  sewage
sludge  drying application  that  is  fully constructed and
currently  in   startup.   Meetings  were held  with
representatives of:

          The City of  Los  Angeles Hyperion  Construction
          Division Bureau of Engineering;

          The City of  Los Angeles Department of Public  Works
          Bureau  of Engineering;

                            1-4

-------
          Dehydro-Tech Corporation  (providing  startup
          assistance);

          James M.  Montgomery Consulting Engineers, Inc.
          (providing startup and operations management);

          The Ralph M. Parsons  Company  (providing  startup
          and operations management).

The  visit included  a  tour  of  the  City of  Los  Angeles'
Carver-Greenfield plant.

The third day  of meetings  in  California,  July 13, was held
at  the  Los  Angeles County  Sanitation  Districts'  (LACSD)
Carver-Greenfield  plant  site.    LACSD  project  management
provided background  information  about  their  Carver-
Greenfield  installation and  conducted  a  tour  of  the
construction  site.

The  final meetings  in California took  place  on July 14,
1988, at  FW  Martinez,  Inc.,  a cogeneration  facility  built,
owned,  and   operated  by  Foster  Wheeler that provides the
adjacent  Tosco petroleum  refinery in Martinez,  California
with  steam   and  electricity.   Plant management provided
information  about the  startup  and operation  of  their
Carver-GreenfieId  unit,  which uses  steam  from  the
cogeneration facility  to dry an  alum/clay  sludge  from  a
municipal water treatment  plant operated  by the  Contra Costa
Water District.  This  information  was  used as  a basis of
comparison,  and  to  confirm impressions about  Carver-
Greenfield systems  gained  at  other locations.   FW  Martinez
was the  last  site visited in California.

After  the  California  trip,  the  recommendations  of  the
Industrial Review Team  were assembled and  used as  the basis
for drafting this  report.    A meeting was then  held at the
Nassau Inn in Princeton, New Jersey, on September  15  and 16,
1988, for the purpose  of discussing the  startup,  operation,
and maintenance of  Carver-Greenfield municipal sewage  sludge
drying  facilities.   Those  invited to  attend included the
developers  and designers of the  process,  the  owners and
operators of the four  municipal  facilities, the  architect/
engineering  firms on the  four  projects, consultants,
representatives  of EPA and  state environmental  agencies,
vendors  of equipment used  in the process, and the  Industrial
Review  Team.   Additional material  included in  the final
report  was  gathered   from  this  meeting  and  from  the
documentation listed under  References.
                            1-5

-------
                         SECTION  2

         SUPPORTING A MUNICIPAL  SEWAGE SLUDGE DRYING
                 CARVER-GREENFIELD FACILITY
The  Carver-Greenfield  Process  has  qualified as  an
"Innovative  and Alternative"  approach to municipal sewage
sludge  disposal,  according  to  government  funding
definitions,  which  qualifies installations for  increased
federal funding.   Four major projects  utilizing the process
for drying municipal  sewage  sludge  were  funded under this
incentive.   The  process was  chosen because it was  an
effective,  established technology in other applications, and
because  its  calculated energy consumption  for  the
application  was favorable when  compared  to other drying
technologies.   The  dried  sludge  product  from this process
can be land-applied as fertilizer,  if  the raw sewage sludge
quality is  good, or burned as a fuel, to recover  energy.

Because  of  the differences in  equipment design,  unit
operations,  process  configuration, operating  conditions, and
level  of control  required,  the  Carver-Greenfield Process
requires  a different approach  to  initial  startup and normal
operation  and maintenance and  to  the  financing  of  those
activities  than  is required  by  traditional  municipal
wastewater  treatment/sludge  management systems.   In  fact,
the Carver-Greenfield  Process more nearly  resembles  chemical
processing  or petroleum  refining  installations  than
traditional  municipal  systems  in  many ways.    For  this
reason,  many of the approaches  and procedures  that are
common  in  the  chemical  process  industries  may  be better
suited to a  Carver-Greenfield sewage  sludge  drying  facility
than traditional municipal sector  approaches and  procedures.
2.1. Initial Startup

As  is the  case  with  any  fairly  complex  system,  the
requirements  for initial  startup  of  a  Carver-Greenfield
facility  are significantly  different from the  requirements
for  normal  operation  and  maintenance  of  that facility.
Furthermore, the  initial startup, operation,  and maintenance
requirements of the  Carver-Greenfield system, which  involves
a  volatile,  flammable hydrocarbon  and  a   potentially
explosive dried product,  are very different from  the
startup,  operation, and  maintenance  requirements of  a
typical wastewater treatment facility.

The  startup  and  line-out  of any  new  plant,  municipal or
industrial,  is  much  more difficult  than  the  operation of an
established plant.    Every  piece  of equipment in  a  new

                            2-1

-------
installation  is  a potential  source  of trouble if it is not
properly installed,  operated,  and maintained.  In addition,
there may be shortcomings  in the  basic  process or design if
the plant involves  unproven  technology or equipment or a new
application.   Anticipating problems,  avoiding problems,
recognizing  trouble  symptoms, and applying corrective action
are  all  vital  startup  functions.    To  carry out  such
functions  requires a quite  different,  larger organization
with  more specialized  skills than will be  needed  in the
permanent organization.

During  initial  startup of  chemical  processing  facilities,
there  should  be  twenty-four-hour-a-day  engineering
supervision  in  the  plant.    For  this  reason,  the startup
organization requires many  more  engineers  than  the normal
operations  staff.    These  engineers  are needed to supply
"trouble-shooting"  skills  that  no  other  background  can
provide, specifically, to perform heat and material balances
and evaluate equipment performance  versus design, which may
include determining  heat  exchange  coefficients,  pump
head/capacity  curves,  and  quality  of  liquid-liquid  and
liquid-solid  phase  separations.   Such procedures  are
necessary  to evaluate  and  prioritize  the  need for plant
shutdowns or  changes.

In  a Carver-Greenfield  municipal  sewage sludge  drying
facility, startup engineers  should  have a minimum of three
to five years startup  and  operations experience with systems
similar to  the Carver-Greenfield  Process; engineering
supervisors should have   ten-plus  years  startup  and
operations experience with similar processes.

There are  a number of  technical  disciplines that  are
typically  available  for  a  chemical processing  plant or
petroleum  refinery  startup on  a  system  similar  to  a
Carver-Greenfield installation, including:

          Mechanical  engineering  for  corrosion/materials,
          piping stress,  thermal expansion,  and  other
          problems;

          Instrument systems  engineering;

          Rotating machinery  engineering;

          Electrical/utilities engineering;

          Safety  engineering;

          Startup operations advisers  -  foremen or operators
          who are experienced in the process or in  similar
          processes.    These  personnel will  assist  in

                            2-2

-------
          training and  serve  as additional operating  staff
          during the  startup.

Temporary startup expertise, in  the  form of full- or  part-
time personnel,  is  available by contract  from a number  of
companies.    The most  straightforward arrangement for  a
facility  owner  is to  contract with  a  single company  that
specializes in startup of  similar facilities.

In the  initial  startup  of  a chemical  plant  or  refinery,  the
first objective  is to get  the  plant  to  operate continuously
as designed,  and not to  change,  optimize, or  debottleneck
until  after  continuous operation  is  achieved.   Experience
has  proven that  changes  other than  those  where design  or
equipment  problems  actually  prevent  continuous  operation
should  be  postponed.   There  are  a  number of  reasons  for
postponing  changes if  at  all  possible,  including the  fact
that a  problem that  is significant at  a low feed rate  may
not be  significant at  a high feed rate, and that the  plant
needs  to be  running  continuously as  soon as  possible  to
maintain personnel morale  and gain operations experience.

Experience in the chemical  process industries has been  that
new  plants,  especially  those involving  innovative  design
features or new applications,  such as is the case with  the
Carver-GreenfieId municipal  sewage   sludge  drying
application, may take a relatively  long  time to start  up  and
may  operate  at less  than  one hundred percent of  design
capacity as originally installed.   Some  modifications  should
be expected in  order to achieve continuous  operation  even at
a nominal level  that is less  than  design capacity.   Further
modifications  to bring  the  plant  up  to  design capacity  may
require substantial  capital outlays,  as much as  ten  percent
or more of  the  total  capital cost of the  project.    In
addition  to  the cost  of  modifications,   typical  startup
expenses,  including staff  training,  vendors'  assistance,
additional  engineers,  and  emergency  equipment parts  and
service, may run as  high as another ten  percent of the  total
capital  cost  of the project.   Since  many of  the  startup
expenditures are on  an  emergency basis,  immediate access  to
a contingency  fund is essential.

During  startup,  the job  procedures  and   other  operations
documents  are  used and  modified  continually.   These
documents  must be   upgraded not  only  to achieve  smooth
operation,  but  for  personnel safety.   Other than  crises,
initial  startup  is  the  most dangerous time  in a  plant's
twenty to  thirty year  life.   Subsequent startups are  also
dangerous.
                            2-3

-------
2.2.  Data Collection  and Retention

Complete documentation of  the system's  actual  performance,
to be  compared  to  design  specifications, is  vital to  a
successful startup.   In order to develop this documentation,
it  is   important  that  engineers  who  have  an  intimate
knowledge of  the  operating characteristics of  the  system's
components work closely  with instrument  specialists  during
the final phases of construction and startup,  to assure  that
the  facility has   adequate  sampling  and  instrument
installations to monitor and  control its operation.

Comprehensive, systematic  recording  of operating data  is
critical during startup,  because,  if the  plant  shuts down,
data analysis  is  the  only  method  of tracking  a  developing
problem  and  isolating possible  causes.   Any correction  to
plant design or operating parameters should be  based on  firm
data,  if unwarranted and inappropriate  changes  are to  be
avoided.

Even in  an  established operating plant  with  a  computerized
instrumentation system,  operators should fill  out data
sheets  that  contain  temperatures,  pressures,   levels,   and
flows throughout the  plant at least  once per  shift.   During
startup, data  should be  recorded  several times per  shift.
As well  as providing  a written  record,  this activity causes
the  operators  to  learn  the plant layout and the  normal
operating characteristics  of  the equipment.

Data from laboratory  analyses of samples  are  also  essential
to the  startup and  operations  effort.    Sample  analysis  is
the means by which activity inside  the  system can be tracked
and corrective action can be  taken.  At  least once  per  day,
a  complete   set of  samples  should  be  collected from every
important point in the process  along with a complete  set of
written  data.   This  gives the operations  engineers  a point
in time  when all variables  they  are trying to  control  are
characterized.  More frequent sampling  should  be  performed
as needed during startup  and whenever  an operations problem
is to be evaluated.
2.3. Pre-Startup Activities

Planning for startup should begin very early and should be a
factor in making  the final selection of any  system  that  is
relatively  complex  compared  to  typical wastewater
treatment/sludge  management  operations.   This early
beginning  is  important for  the  municipal  owner  and/or
operating  authority, because  it  allows time  to  understand
and make allowances  for  the  needs  of this  different  type  of
facility.    Early  startup planning  considerations  include

                             2-4

-------
hiring and training staff,  procuring  startup  and maintenance
expertise,  making  arrangements  for  the  treatment  and
disposal  of  the  feedstock while the  system is not  up to
design capacity,  and  procuring  and  making arrangements  for
readily accessible startup  funds.

Plant  management  should  spend  the  year  before  startup on
organizational activities  to  remove foreseeable obstacles as
long in advance as possible.   Because  hiring  and training is
time-consuming,  an important  goal of  these endeavors  is to
phase people  and  talents  into the support organization for
the facility.   Pre-startup  activities  should include:

          Development  of a  detailed startup plan;

          Hiring  and  training plant operations  and
          maintenance  staff;

          Development  of operations documents;

          Development  of emergency  response  plans  and
          documents;

          Development  of contract maintenance  availability;

          Checking  instrumentation  and  adding
          instrumentation   and sample  points  so that
          performance  of   each  piece  of equipment  can be
          tracked;

          Development  of warehouse  parts  and equipment
          inventory  based   on  manufacturers'  recommendations
          and evaluation of breakdown  probability;

          Locating specialty mechanical  service  shops  for
          such services  as  rotor  balancing, motor rewinding,
          hard surfacing, etc.;

          Pre-commissioning  (testing  plant construction at
          operating conditions with water, air, or steam).

A major milestone in  the pre-startup phase  of the project is
mechanical  completion,  the date  when the construction
contractor  has  satisfactorily  finished construction,  with
all components  properly installed,  the  system successfully
pressure  tested, all  motors turning in  the  proper direction,
all instruments properly calibrated,  and all control valves
opening   and closing  as specified.   After mechanical
completion,  operations   personnel  can  begin  pre-
commissioning.

Pre-commissioning usually takes  the  form of  using water,

                            2-5

-------
air,  and  steam  to  simulate  normal  plant operating
conditions.    This allows  equipment  to  be checked  using
non-hazardous materials that can be dumped or vented without
problems.   Regardless  of  the quality  of the  design  work,
this  exercise  uncovers omissions  and problems that  need
correcting.   If the design involves unfamiliar equipment and
concepts,  these are  given  priority for check-out,  to  allow
time  for possible modifications.   Sometimes  the  problems
identified in  pre-commissioning  could  pose a major problem
to startup.
2.4. Plant Staffing for  Normal Operation and Maintenance

Although  the  number  of  personnel  varies  with the  design,
size,  and  layout of  each  particular facility,  there  are
certain talents  and  skills that  are  necessary  for  the
successful  operation  of  any Carver-Greenfield  municipal
sewage  sludge  drying plant.   Because the  light oil  process
and  the municipal sewage sludge  application  are  relatively
recent, the opportunity for sharing staff with other  similar
plants  is limited.  Therefore, it is critical that all plant
requirements be anticipated so that qualified personnel will
be available when  needed.   The  staffing  effort should start
long  in advance  of  startup,  to  allow adequate time  for
recruiting  personnel  with  specialized skills  and  for
training personnel.

It generally takes  two  to five years  in process  operations
for  an engineer  to become  proficient  in field applications
of what he  was exposed  to  in a  college or university.   A
substantial part of this proficiency comes from working with
other  engineers with  substantial  field experience.    In the
case of a  Carver-Greenfield  facility where  there  are only a
handful of  experienced  engineers  available  in the  U.S.
today,  it  would  be advisable to  acquire process  operations
experience from the chemical  and  refining  industries.   This
would  create  an  experience base  for  in-house  technical
personnel development.

In the  experience  of the chemical process  industries,  it is
necessary to have  engineers  working days  and on call nights
and  weekends  to  analyze problems  as  they develop  and to
devise and  implement  solutions  in a  timely fashion.   The
nature  of  the  equipment and  process  steps  require
engineering training  in the unit  operations  present  in a
particular plant,   to perform the  necessary calculations and
devise  and  implement procedures  to  evaluate the performance
of each piece of equipment.

The Carver-Greenfield municipal  sewage  drying control system
is  complex  enough that  an  inexperienced operator  will have

                            ,2-6

-------
difficulty working  with  it until he  gains  experience.   In
addition,  the  hazards of  processing hot flammables bring
significant risks  of  fire,  explosion, and personal  injury.
For these  reasons,  it  is  advisable to have control room and
outside operators with chemical plant  or refinery  experience
in order  to  reduce risks  to an  acceptable level  and  assure
successful operation.

Shift and  operations supervisors  should  have  experience at a
control room  operator or higher ' level  in similar unit
operations and  operations  involving flammable  hydrocarbons.
Related experience that would be of value includes:

          Evaporation  or distillation operations;

          Particular equipment,  such  as oil/water
          separators, coalescers,  devolatilizers,  or
          centrifuges;

          Solids handling;

          Sludge or slurry processes.

If  the engineer,  operator,  or  foreman applicant  has no
experience with unit operations or equipment  similar  to that
in the  Carver-Greenfield Process, almost any chemical plant
or  refinery operations experience is still  of value.   At
least  this would  assure  some familiarity with  nonambient
operating  conditions,  process  control  systems,  heat
exchange,   and  health  and  safety procedures in the presence
of hazardous substances.   In  the absence of chemical plant
or  refinery experience,   background in the  operation of
mechanical equipment  or  systems,  such  as  large  engines or
boilers, would  be beneficial.

In  the  case  of maintenance  personnel,  experience with
similar  equipment is a great  asset.   For maintenance
planning and warehousing of spare parts, lack of  experience
with a  process  of similar  complexity  and equipment is very
difficult to overcome.

Laboratory personnel should have  experience with analyses of
similar complexity, preferably  having  used some of the same
procedures and  types of equipment.
2.5. Personnel Training

It  will take  approximately  six  months to  train  a totally
inexperienced operator  to  work in  a Carver-Greenfield
municipal sewage sludge drying facility and three months to
train  someone with  process  or  equipment  operations

                            2-7

-------
background.   Engineers and  operations  and maintenance
supervisors  should have a minimum of  three  months  to learn
the process  and plant.

The operations documents  are  the most  essential  source  of
training  for  any plant.   Engineers and  operations  and
maintenance  supervision  can  prepare,  use,  correct,  and
expand these documents in  a  self-education procedure.
Sessions for operators  should  be  supervised, and sections of
the documents that  repeatedly  cause  difficulties  should  be
rewritten  or  expanded.

In addition to the operations  documents, video-taped or live
classroom  sessions on  the  basics of  physics and chemistry,
heat transfer, evaporation,  fluid flow,  etc.  give  a broader
picture of why and how  things occur in  the process.

A  very important training  aid  is  a  scale  model  of  the
facility,  especially  when construction is  not  complete
enough  to see physically how  the pieces described  in  the
operations documents fit together in the  field.

Hands-on  training  at  a  pilot-  or  full-scale  facility  is
always a  tremendous  asset.    A  substitute  for  this  is
computer modeling  to simulate hands-on  operating experience.

In-plant trainig  at  other Carver-Greenfield municipal sewage
sludge drying plants  that  are already in  startup  or
operation  would be of  significant value to plant management
and engineers.   Depending  on startup  status,  such visits
could  also be useful to operations and  mechanical personnel.

Vendors of  equipment  and  instrumentation are  usually good
sources  for training  of  instrument,  maintenance,  and
operations supervisors.

An  essential segment  of  employee training for  all plant
personnel  is health  and  safety.   The Carver-Greenfield
Process involves  flammable  liquids and potentially explosive
vapors.   Minimum  health and  safety  training  includes
emergency  procedures  and information on  proper  handling
techniques  for chemicals present  in  the  plant.   Safety
meetings for  reviewing material  and presenting new material
should be  held  on  a monthly  basis after  the  plant  is
operational.
2.6. Operations  Documents

In the experience of the chemical  process  industries, it has
proven to  be essential in both  initial  startup  and normal
operation to  have  certain documents in place, and  to keep

                            2-8

-------
these documents updated:
          Health  and  safety writeups  - These  documents
          include  important health and safety considerations
          for  the  chemicals and operating conditions  present
          in  the  plant.    Material  Safety Data Sheets  and
          other  manufacturers'  bulletins  giving  information
          on  special  handling requirements  and  protective
          equipment  are  included,  as  well  as  the  locations,
          testing,  and  maintenance schedules  for fire
          extinguishers,  pressure relief devices,  eyewash
          and shower  stations,  and  sprinkler  systems.
          Emergency  procedures are covered, plant  evacuation
          routes  listed.   Health and safety writeups must
          comply with state and federal regulations.

          Operating  manual  -  This  document  gives a
          generalized description  of  what the  process  is  and
          how  it works.   It describes how the  plant is to be
          started  up,  shut down,  and operated during  normal
          periods, as well 'as  how  to handle emergencies such
          as  power or steam  failure.  The operating  manual
          should  include manuals from  equipment  suppliers
          which describe  equipment operation.   A  first
          version  of  the operating manual  is  normally
          prepared by the plant designer.   A more complete
          version  should  be  prepared  by  the  technical staff
          prior to startup.

          Operating   or  job  procedures  - A  collection of
          detailed  instructions  which  describe,
          step-by-step, how  to do each particular job that
          has  been  described  in general  in the  operating
          manual.    For  example,  the operating manual  may
          say,  "Pump water  from  Tank 1,  using  Pump 1,  to
          Tank  2,  until  a   50  percent  level  has been
          established."   The  job procedure  for this
          operation  will  give  step-by-step instructions of
          how to  accomplish  the task,  including very
          detailed descriptions,  such  as the  position of
          every valve in  the  system,  what  pressure the pump
          pressure  gauge  will  read,  and  how long  the
          transfer will  take  under  normal conditions.   It
          will also  contain  instructions for  handling minor
          problems,  using appropriate protective  equipment,
          and  responding to  emergencies.    Job  procedures
          also  usually  contain special  instructions  to be
          followed if the  system has  been out  of service  for
          maintenance.    Operating procedures  are very
          specific and  concise,   rarely more  than   two or
          three  pages  in length,  because they  deal with
          simple component  procedures, not complex combined

                            2-9

-------
          component  procedures.   It is  very  desirable  that
          these  procedures  be  prepared  by the new operators
          as part of their training  program.

          Maintenance  procedures  -  These procedures are  as
          specific  and  detailed  as operating procedures.
          They give  step-by-step  descriptions  of how  to
          ready  a  piece  of  equipment for maintenance and how
          to perform the  maintenance, listing the tools  that
          are  required,  and often  listing what  spare  parts
          should be  kept  on  hand  and where  they can  be
          found.   There is  usually  a special  section  on
          instrumentation  maintenance  and calibration.
          These  detailed procedures should  be  prepared  by
          maintenance  personnel, with input from  the
          technical and operations  staff,  during their
          training program.

          Laboratory  procedures -  These are  step-by-step
          written procedures  for  performing  all  analyses
          necessary  for  the control of  the  system.  For  a
          Carver-Greenfield  system,  these  analyses  might
          include  moisture  in  feedstock and  product, oil  in
          product,  oil  in condensate,  oil  in wastewater,
          condensate  pH,  and  heavy and  light  oil
          distillation.   Laboratory procedures  also include
          safety  and health'  information and procedures.
          Plant  analytical  personnel review  and, where
          necessary, revise these procedures  which  are
          initially  prepared by the  designer or licensor.

The  operations  documents are important  tools  for  training
new personnel.   Use  of these documents by the plant manager,
engineers, foremen,  technicians,  operators,  and maintenance
staff  during  pre-startup  and  startup is both  a  training
exercise and  an  excellent method  of identifying inaccuracies
and  omissions  in the  documents.   The  documents  should  be
used and  revised continually,  especially during startup,  so
that they accurately reflect  the most  current expertise for
operating and maintaining the plant.


2.7. Health and  Safety Documentation and Procedures

Introducing  more  complex  technologies,  such  as  the
Carver-Greenfield  Process, into  the  municipal environment
will also, in most  cases,  introduce unfamiliar risks due to
the unfamiliar substances,  equipment,  and procedures in the
new facility.   Although health and  safety documentation and
procedures are mentioned elsewhere  in  this report,  they are
of  such  critical  importance  that  they  merit  special
discussion.

                           2-10

-------
Over  many  years,  the  chemical  process  industries have
experienced  accidents involving  hazardous and  toxic
substances.    In  response  to this  experience,  these
industries  have developed methods  of  minimizing  the risk  of
accidents  that are foreseeable due to  the  nature of  the
substances, equipment,  and  operations  present  in a  plant.
These methods  of minimizing  risk are strictly followed,  not
only to  avoid  injury to employees,  but  to  avoid  financial
injury to  the  corporation  due  to lawsuits,  down-time,  and
costly repairs  to  facilities.

It  is  strongly  recommended  by the  Review  Team that  the
prospective owners  and/or operators  of  chemical  processing
type  facilities  borrow  from the  experiences  of  these
industries  rather  than go through a dangerous learning curve
that involves  repetition of  past chemical plant and refinery
accidents.

In  a  typical  industrial facility,   there  is a health  and
safety officer  or department that  is responsible  for  seeing
that  certain   guidelines are  followed.   It  is  recommended
that  in  any more  complex  municipal  facility,  one of  the
plant  supervisors  be appointed health and  safety  officer,
and  that  certain activities be  included  in the  job
description:

         Train  or oversee  training  of new  personnel  -
         Before  new personnel  can work  in  the  facility  for
         the   first time,   they  must  receive intensive
         indoctrination regarding  potential  risks and  how
         to  avoid  them.    Initial  training  should  include
         "right-to-know"  information  about  the health
         aspects  of exposure  to  materials present in  the
         plant,  discussion  of  the  explosion  and fire
         hazards  specific to each  part of  the plant,
         training  in  safety  procedures  (such  as  proper
         tagging  of equipment  to avoid accidental operation
         during maintenance), and  emergency procedures;

         Conduct  or supervise  continuing employee  training
         program  - All  plant personnel  should attend
         monthly  training sessions (plus emergency sessions
         as  needed),  at  which  new  health and  safety
         developments  are  discussed and  initial  training
         material  is reviewed,  reinforced, and expanded;

         Investigate and report  on  work-related  illnesses
         and   injuries,  including  required OSHA and  NIOSH
         reporting;

         Maintain  and update emergency response plans;


                            2-11

-------
          Review  issued work  permits,  to assure  compliance
          with procedures;

          Review designs and  inspect  completed  work for
          safety  before placing in service.

It  is  advisable to  involve  as  many  plant personnel as
possible,  especially  front-line supervision  and  union
representatives, in  implementing  the  health  and  safety
program.   This helps  assure  compliance  and communication to
all groups of  personnel.

It is necessary  to  have  a designated supervisor on call for
emergencies,  twenty-four  hours  per  day,  seven  days per
week.    The  "on-call" schedule  should  be  posted  at
telephones.

An essential  part  of a  good health and  safety program is
developing  and  drilling personnel in emergency response
procedures.    In  an  emergency,  personnel must be able to act
without  hesitation,  relying  on their response  procedure
training,  in  order  to avoid  injury.  The  Emergency Response
Plan should give  specific answers to questions such as:

          Who  is  in  charge?

          Who  is  the spokesperson?

          Who  calls  the  fire department or other  emergency
          services?

          Who  contacts the regulatory agencies?

          Who  informs the  treatment  works supplying sludge
          to the  plant,  and  how should  they  respond in  their
          own  locations?

          Who  will  ask for  and  who  will  provide  plant
          security  in case of a major incident?

          Who  will  interface with community leaders and the
          media,  and  how and  where  will he meet with  their
          representatives?

Defining specific roles  and  responsibilities  is  essential to
the success of  any health and  safety  plan.   Each employee
should know exactly  what he  must do,  and he must also  know
what other  employees  in the plant will be doing during an
emergency.    The plant  emergency  organization  should be
posted in clear  view in several locations in the plant and
reviewed in monthly safety meetings.   Telephone  numbers  that
may  be  needed  during an  emergency,  including  fire

                            2-12

-------
department,  ambulance,  and  environmental  regulatory
agencies,  should  be posted by telephones.

A great deal of time  and effort  is  required to maintain good
health and safety  practices  in  the typical  chemical
processing  facility.    A similar level of  effort  should  be
anticipated and planned for  by the  prospective owners and/or
operators of municipal  facilities  involving such
technologies.
2.8. Technology Acquisition and Retention

Each plant is  unique, with idiosyncrasies due to individual
pieces  of equipment, plant  design,  and layout.    For  this
reason,  initial  startup of  a  new facility is  a  learning
experience for all personnel, even those with many years of
startup  and  operations background.    Consequently, it  is
important to  collect  as much information  as  possible  from
the  licensor,  designer, and equipment  vendors.    During
startup,  personnel devise methods  of  getting particular  jobs
done,  and learn  to  detect   and  act upon early  signs  of
developing trouble.   In order to assure  continued successful
operation of the plant,  this  accumulated knowledge  needs to
be  retained  in the  facility  in  the  form  of  operations
documents and experienced personnel.

A very important element in  any startup plan is a procedure
for  transfer  of  accumulated  operations  expertise  from
temporary startup personnel.   One  method of  achieving  this
transfer  is  for  permanent  plant personnel to  accompany
temporary startup personnel  and  observe their activities.
When  the permanent  personnel  take  over a  function,  the
startup  personnel  can  accompany  and  supervise.   Acquired
expertise is  also  stored  and  transferred  by continually
updating  operations  documents and bringing any  changes  to
the attention of plant personnel.

There is  a  critical  need to  retain permanent staff members
after  training,  especially  because the  Carver-Greenfield
municipal sewage  sludge drying  application  is  relatively
new.  In  the  case  of any new type of facility,  there is no
existing  pool  of  experienced manpower  from which  to  draw
information  or  new employees,  so  it  is  particularly
important to  retain experienced staff.
                            2-13

-------
                         SECTION 3

                     RECOMMENDATIONS TO
           THE MERCER COUNTY IMPROVEMENT AUTHORITY
The Mercer County  (New Jersey) Improvement Authority (MCIA)
Carver-Greenfield  sewage sludge drying facility was selected
as a specific example of  a chemical process technology being
implemented  in a municipal  application.   The  Industrial
Review Team  developed a  number  of recommendations  for  MCIA
based on their experience of  how  the  startup and operation
of  similar  facilities are handled in  a  chemical  plant  or
petroleum refinery environment.    It  is  expected  that
applying some of  the practices from these  industries will  be
of  value in  implementing relatively complex  processes  in
municipal applications.

Work on  the  MCIA  facility has been  halted since  September,
1987,  with  construction  approximately  eighty  percent
complete, because  of construction  contractor problems.   When
construction is  resumed, it will  take  approximately  ten
months to complete.   The  Plant Manager should take advantage
of  this unexpected  delay  to prepare  for  a challenging
startup.   There are certain actions that can be taken now  to
help minimize foreseeable  problems and assure the  success  of
the initial startup  and operation efforts:

          Hiring  an  Assistant  Plant Manager as  soon  as
          possible  is strongly  recommended.   His  duties
          would  include  serving as  designated  safety
          officer,  filling in  for  the  Plant  Manager  when  he
          is  not  available,  assisting  in employee training,
          assisting  in   the  development  of operations
          documents,  updating  the  operations  documents,  and
          interviewing potential employees and comparing his
          impressions  with the results  of the Plant
          Manager's  interview.   During and  after  startup,
          the  Assistant Plant  Manager  would  perform
          engineering  support  functions,  such as performance
          evaluations of equipment,  and  share  on-call
          supervisory duty.   The Assistant  Plant  Manager
          should be a chemical engineer with  at  least  five
          years  of chemical/refinery  startup  and  operations
          experience, specifically in facilities  with  unit
          operations similar  to those  in  the  Carver-
          Greenfield Process.

          The Plant  Manager  and  Assistant  Plant  Manager
          should  undertake a self-training  program  that
         would  include  studying the piping  and  instrument
          diagrams  and other process  information.   The plant

                            3-1

-------
operations  and health and safety documents should
be  developed and  reviewed through  this  self-
training,  so  that they  will  be  in good condition
for  the  training of  other  personnel.   Extended,
preferably  hands-on, visits  to the City  of  Los
Angeles plant, the  Dehydro-Tech  pilot  plant,  and
the  Burlington  Industries or  other  Carver-
Greenfield  light oil plants are very  strongly
recommended.

As  an extension  of self-training,  the  Plant
Manager  and  Assistant Manager  should investigate
resources to be  used  for training  of  other
personnel,  such as  programmed instruction courses
and  vendor courses.    Contract arrangements  for
training  assistance  should be made as necessary.

The  Plant  Manager  and  Assistant Plant  Manager
should carefully review the talents  and skills
required  for  startup, and decide  how  to satisfy
any  additional  temporary personnel  needs.   It
would probably not  be feasible for MCIA to hire in
employees  with  the specialized skills necessary
because of hiring restrictions  and  the  fact that
many  of  the  positions  would be temporary (less
than  twelve   months).   One  strongly recommended
alternative is to contract out the startup.

Some modifications to the MCIA plant will probably
be  required  during startup,  for  a  number  of
reasons:    the  process application is a relatively
new  one,  feedstock  characteristics  are  unique to
each location in  the   municipal sewage  sludge
application,  and  there are design features of the
MCIA plant that are unique to that facility, such
as  the  the   pelletizing/granulation  operation.
Chemical  plant/refinery  experience with relatively
innovative  plants like the MCIA  facility suggests
that up  to ten percent  of the  total capital cost
of  the plant  may  be required  for modifications
during startup.   In  addition to  the  cost  of
modifications,  other  startup expenses may  run as
high as  another  ten percent  of  the total capital
cost  of  the project.   Funds  to cover both
modification  and other  startup  expenses  must be
accessible  on an  emergency basis,  or  startup
activities  will be delayed.

The  Plant Manager  and  Assistant Plant  Manager
should develop a  comprehensive plan of pre-startup
activities,  to be implemented  as  soon  as
construction  is resumed.

                  3-2

-------
3.1.  Permanent  Staff

The  Plant  Manager and  Assistant  Plant Manager  are  the
nucleus  of the  permanent  operations  staff for  the  MCIA
Carver-Greenfield facility.   One of  their  most important
functions  is  to  interview  and hire  other  permanent  staff
members after construction resumes.   The suggested schedule
for bringing these personnel into the organization  is  shown
in Figure 1 on page 3-4.  The  recommended normal operations
organization  is  shown  in Figure  2  on  page  3-5.    The
suggested organization would include:

          Plant Engineer  - Should join  the  plant staff  six
          months  before  the end  of  construction  and should
          follow  the same  self-training program as the  Plant
          Manager and  Assistant  Plant   Manager.
          Responsibilities  should  include process  and
          project  engineering  functions  such  as  monitoring
          equipment  performance,  designing plant
          modifications,  and  supervising implementation of
          modifications.   Should also  share  on-call  duty.
          B.S.Ch.E.  plus  three  to five  years  chemical/
          refinery  process  and operations experience should
          be required.

          Day Foreman  -  Should  join  the operations staff  six
          months  before  the end  of  construction  and become
          familiar with plant  layout,  equipment,   and
          design.   Should  study operations  documents  and
          assist  in developing operating procedures,  attend
          all  training  sessions,  and assist  in hiring  shift
          foremen  and  operators.   Chemical  processing  plant
          or petroleum refinery experience  at control  room
          operator  or shift foreman level  is recommended.

          Maintenance  Foreman  - Should  join  the  operations
          staff  six months before the  end  of construction.
          Should  study  plant  layout,  equipment,   and
          operations documents,  as well  as  attend  training
          sessions and develop maintenance  procedures  with
          input  from vendor experts.    Should  study
          installations,  recommend modifications   for
          maintenance  accessibility,  and  develop  a  list of
          warehouse spare  parts to be kept  on hand.   Should
          work with plant management to  develop  contract
          resources for  special  maintenance services  and
          develop  plans  for  scheduled and unscheduled
          shutdown  mechanical work.   Experience with similar
          process equipment is very important.

          Instrument Supervisor -  Should join the  operations
          staff four months  before the end  of construction,

                            3-3

-------


s
Q
W
X
U >*
C/J iJ
rrr
o o
M 1-3
P^ 55
EH O
W W
Pi
FA r_-i
r* w
tJJ H
P^ 25
fjj
< Z
M , /•































k X1






























v /•






























V /•






























1, /•














V /














V A A A A
I 1






























CO CO
M C C
O (fl ffl
C W -H -H
(fl -H U O
H £ > -H IM -H
0) QJ )-( C 4-1 C
O1 >H Q) r; frt _r]
 S C C QJ E i -H W -H (1) W -H JQ
rHWrH(ti(tiflX3O
-------

























o
H
PJ
t-4
2;
< <
hH C5
U OS
& o
• to
CN1 *!T
f^l X—
O
O M
H H
3 < .
•H U
In O,
O

, ^
^
y
2
o




















































_ •"




OS
U

1


EH

<
04






—






















































































































_^

os

EH
U
OS
U
U
^
os
u
U



— r
\











































































































































__


Oi
U
<

I
_
5

f-4
to
t/5
C/5
^




— —






















































































































-•H
IX
1

OS
O
ffi

J

U
M
^
,_J
«^
5

~T
_L
































































































































OS
o
>
w
CU
3
M
EH
Z
U
2£
^
OS
f^
M
Z
HI
g
E

OS
O
tu

U
§
Z
U
H
Z
M
E



































to
z
HH
U
z
X
a


£H
Z
Ed
s

os
£H
t/]
Z
M







«
to
EH Z
as in <
W EH < E
H to as
EH M 0 X
M 2 EH
til I-H OS M
U] X W U
a. u x M
n < EH EH
0. E O 3










































Z
!({
E

os
bu

^
^
Q






-^
OS
U
U
z
o
EH
§
iJ































to to
as as
o o
H EH
Z < <
SUM

a: o o
o
r*t 1 1 r*i
O Q
H OS M
U. H W
l-l Z EH
X 0 3
to u o











-^^



3-5
































































Q

as
EH
Z
O
U
PQ
>«
S
«

-------
go  through  the  training  program,  and assist in
hiring instrument  technicians.   Should follow the
final  phase  of  construction,  check  as-installed
instrumentation,  recommend modifications,  and
develop  a  list  of  parts to keep  on  hand.
Experience with similar  instrumentation  and the
same  type of  instrument  control  method  is  very
important.

Shift Foremen -  Should  join  the operations staff
four  months  before  the end of construction, go
through  the  training  program, study  the plant
layout,  and help develop  job procedures.    Should
also help with  training  operators.   Chemical plant
or  refinery  foreman or  control  room  operator
background is recommended.

Operators -  Should join the operations  staff at
least  three  months  before  the  end  of
construction.    Their  pre-startup  training  should
include  process technology,  plant layout,
equipment,  instrumentation,  and  operating  and
safety procedures.   Control  room operators  should
have  chemical  processing  plant or  petroleum
refinery  experience  or  have  demonstrated
capability in related operations,  such as  boiler
or  engine room.   Inexperienced  operators  require
six months training.

Instrument  Technicians  - Should  join  the
operations staff  three  months  before  the  end of
construction,  go  through  the   training program,
and  study  vendor  information  on  plant
instrumentation.   Vocational  or  practical
experience is recommended.

Maintenance  Staff -  Should join  the  operations
staff a few weeks before the end of construction.
Their training should be  supervised  by  the
maintenance foreman with the  assistance of  vendor
experts on specific equipment and  job  procedures.
Millwright/mechanic,  pipefitter, and utility man
will  be  needed  full-time;  other  crafts  may be
contracted for as needed.

Laboratory  Technicians  - Should  join  the
operations  staff two  to  three  weeks  before
startup,  to  become familiar with  procedures and
sample schedules and  handling.   Should  have
previous  experience with similar analyses,  and may
receive   specific training with  the  licensor.
Permanent staff  laboratory technicians   should

                   3-6

-------
          perform  daily operations  control  testing,  such as
          percent  oil  in  product  and  condensate.
          Supplemental  testing for  heavy metals, pathogens,
          certain toxic organic  compounds,  etc.,  may be
          performed by  an outside laboratory under contract.
3.2.  Additional  Startup Assistance

Because initial startup of  a new facility is substantially
more  demanding than continuing operation  of  an existing
facility,  additional  manpower  and  expertise  is necessary
(Figure 3,  page  3-8).   Experienced  engineering  supervision
is required  twenty-four hours  per  day.   Special  assistance
with  equipment may be provided by vendors  and contract
maintenance services, who  should be  put  on  notice prior to
the startup.  In addition to the permanent plant  staff, the
startup staff should include:

          Startup Team  -  Should include  both  chemical and
          mechanical engineers  selected  and  assigned  to the
          plant  at  least  two months  before  the  end  of
          construction.   The  head  of  the  team should be
          assigned  six  months before  the  end  of construction
          to work  with the permanent  plant personnel on
          pre-commissioning and commissioning  schedules.
          The startup  team  will provide twenty-four-hour-
          per day technical  leadership  until the permanent
          plant staff  develops  sufficient  expertise  and
          confidence  to  assume operation  of   the  plant.
          Extensive  experience  in startup and  operation of
          chemical/refinery type  facilities  as well  as
          understanding  of  process  control  and
          instrumentation systems is  required.

          Startup Maintenance Team  - A group of  maintenance
          specialists,  including a  maintenance  planner,  a
          rotating  equipment   specialist,  and an
          instrumentation  expert,  plus  instrument men and
          craftsmen  to  supplement the permanent  plant staff
          and provide  twenty-four-hour-per-day  coverage.
          The maintenance  specialists should assist  in the
          development  of  the  startup  plan  and schedule.
          This activity  should  take about  three to  four
          weeks, within the three months  before  the  end of
          construction.

          Process  Consultants  -   Expert services  to  be
          provided by the process licensor.

          Vendor Experts  -  Should  be called in as  needed
          when their equipment is started up or tested.

                            3-7

-------






























§
hH
H
<

j_(
M§
CJ O
Z OS
. °
m CU
0) EH
11

•H CO

J
<
(-4

M
2
M





































































-•I




as
u
0


H
z
, •]
cu







—




















































































































































_MI

^4
OS

H
U
OS
CJ
W
CQ
as
u
CJ




^r












































































































































































_j««


OS
Ed
o
1
Vj
^
rt.
EH
CO
(H
CO
CO
<





	












































































«
CJ

ice
£H
CO
k~4
CO
CO
"*
QJ
H
a
EH
CO






















M td CO
EH EH H

(J
•2
2;
1 U < CO
: cj EH EH
0 2 J OS
t-
* < 3 U
EH 2 CO Cu
XI
C U 2 X
OS EH 0 U
CJ 2 CJ
cu M as
O < co O
S CO a
0
j U 2
D CU CJ Ed
EH 3 O >
0
A
S EH OS
c. as a-
EH <
CO EH



























^H
OS
o
£-4
*(
as
O
m
•<

j
^J
CJ
C_|
^4
,_]

1



0
CO




















«
s «
O CO
0
(-
».
a
&
P

i ^
H <.
> hH
S U
J M
u 2
3 X
co o
> EH
0
£
O >*
EH OS
nc
C O
OS EH
C
D
3 -<
Q OS
< 0
kj m



























*£
J

































































_«•
as
o
00
as
u
a.
D
CO
EH
2
U
y
D
as
EH
CO
2
M
	
_••
«c
s
u
as
O
Du

U
2
2
U
H
2
M
*£
2









































«
•K
CO
§
M
CJ
M
2

CJ
EH

EH
2
Cd
2
£3
OS
EH
CO
2
M








«
* CO «
* « EH 2
OS * Eu 5!
Cd EH < S
EH CO OS
EH M CJ >*
M 2 EH
til M OS M
Ed Z Ed iJ
0< CJ Z M
M < EH EH
0* £ O D











































_^^






2
^
2
DL]
(X
Lu

^
Q




































co co
OS OS
o o
Z^" *f
**t *«•
Cd OS OS
S Ed Cd
OS O O
O
In J Ed
O Q
EH OS M
U, EH W
M 2 EH
X O D
CO CJ O





















r\
M-I -a
0)
—^^•i >>^. n-l
























3-8









OS
w
Ed
2
M
O

Ed

EH

15
»j
py




	
v^i \s
M a>
(TJ 0)
SH 2
O
a c
E 0
CU -H
EH 4J
•H
r-l W
CU O •
C PH CU
C Z3
O C 4J
w • o ^
M CX 1)
CU 3 U -P
04 -W D1 CO
M (Tl
•O HJ ^ rH
0) -U CU «)
N CO > -H
•H O -U
IB id C
••H -H (OM
U 4J M
(1) -H 4J M
a c x o
CO M Cd 4-1

-------
3.3. Training Program

A training program should be  developed by  the  Plant  Manager
and  Assistant  Manager, with input  from  the Day Foreman,
Maintenance  Foreman,  the process  licensor,  and the  plant
designer.  The Plant Manager, Assistant Manager,  Maintenance
Foreman, and  Day Foreman should  go  through the course  and
discuss and implement modifications where necessary.

The training program should be tailored to  the needs of  the
operating  staff  of  this  specific  plant.   In order to
accomplish this,  plant  supervision  should first identify
what  these  specific  needs are and  then  participate  in  the
selection  of  training  materials and  their  preparation,
modifiying available  materials  to  fit their  plant.    The
operators should be trained to acquire an  integrated  view of
the process in addition  to the specifics of their  positions.

Suggested operator  training would include:

          Health  and safety training,  including  general
          background as  well as specific procedures;

          Fundamental concepts,  such  as heat,  temperature,
          materials, steam, hydrocarbons,  pressure, vacuum;

          Carver-Greenfield Process  specifics,  sewage sludge
          technology, process chemistry;

          Unit operations basics, such  as  fluid flow,   heat
          transfer,  evaporation,  distillation,  drying,
          solids handling;

          Specific equipment descriptions, functions,  and
          operating  characteristics,  such  as pumps,   heat
          exchangers,  boilers,  centrifuges,  pelletizers,
          filters,  conveyors, hydroextractors;

          Process  instrumentation descriptions   and
          functions;

          Operating procedures;

          Startup procedures.

Experienced operators  should  have a minimum of three months
training prior  to  startup.    Inexperienced  operators should
have up to  six months training.

Training sources include:

          Dehydro-Tech Corporation;

                            3-9

-------
          Foster  Wheeler Management Operations Ltd.  (USA);

          Contract  training companies;

          Programmed instruction supervised by  in-house
          engineering  and operations  personnel,  such as
          those  developed by  Technical Publishing  Company
          for maintenance  and safety skills,  and  E.I. DuPont
          training courses  on topics like  instruments,
          boilers,  chemical  processing  operations,  and  other
          equipment needs;

          Lectures  by operations engineers  from the  City of
          Los  Angeles plant and  Carver-Greenfield pilot
          plants.


3.4. Startup Planning Considerations

The  startup  team  may  be composed  of  members  of  various
organizations or firms but should have  a consistent  nucleus
of  permanent  plant  personnel and  startup personnel assigned
for the duration of  startup.   During  this  period,  personnel
should  report  to  and  follow  directions  from the  startup
operations  manager.   If  startup- arrangements  include  a
startup operations  manager who is not  the  permanent  plant
manager,  the  permanent  plant manager needs  to  remain in
control of his plant, and  work in close conjunction with the
startup operations  manager.

The Carver-Greenfield Process  is  still in  the early stages
of  development  for the drying  of  municipal sewage  sludge.
For this  reason, some process  modifications  may  be required
during  startup  to achieve  continuous  operation.    Further
modifications or debottlenecking, which  may be  required to
achieve  design  capacity,  should  be  postponed until
continuous operation at a  reduced rate is achieved.

Before  any  proposed modifications  are  undertaken, it is
critical  that  the operations, technical,  and  maintenance
teams  agree  on  the  scope  of the modifications and  the
benefits to be derived from them.   In  order to  achieve  this,
a plan to identify and prioritize these modifications should
be developed.  This plan should  include the  following steps:

          Problem identification and documentation;

          Priority  and personnel assignment;

          Trouble-shooting;

          Process and engineering study;

                            3-10

-------
          Evaluation of  alternatives;

          Design;

          Cost estimating;

          Review and approval;

          Implementation/construction;

          Evaluation and documentation.

Process  and  engineering  review  of equipment operating
conditions  during  the  various  stages  of  the  startup  is
necessary  to  assess performance of  the  equipment,  and
mechanical  and process  capabilities.   A first  estimate  is
made, in effect, by the design engineering firm in designing
the equipment.  This  first estimate should be reevaluated in
detail by the  startup team before startup,  to anticipate the
need  for  circulation  lines  and other  temporary arrangements
needed  while  the  plant is  brought  up to design capacity.
The  procedure  is  repeated  again  after  the plant  is
operating.

Operations management and process engineering personnel from
the owner's  staff  should be assigned  as part of  a  project
team  to  follow up  the project throughout all  the stages  of
development.   This  continuity  will  help  prepare  and  achieve
a  smoother  startup.   Another  good  practice is retaining
project  and construction personnel  to continue  working  in
the plant at the end of  construction.


3.5.  Assuring Continued  Operations

Because  it  would   be financially  prohibitive for MCIA  to
develop  in-house all the skills  and  talents  necessary  for
startup  of  the Carver-Greenfield  facility, many  of  the
engineering and  supervisory  people  during the startup will
be temporary  contractors.    It  is important  that  the  Plant
Manager and  Assistant Manager  see that a plan is developed
and carried  out for  the  transfer of technology  from  these
"temporaries" to the permanent  staff.


3.6.  Mode of Plant  Operation

Based on  their previous experience with  systems  containing
solids,  the  members of  the  Industrial Review  Team  would
prefer  to choose  continuous,  seven-day-per-week,  operation
to reduce the  potential  for  difficulties caused  by plugging
of piping  and  equipment  during shutdown  and restart.

                            3-11

-------
Another  problem  caused  by intermittent  operation is  that
repeated  temperature  and pressure  cycles  from  intermittent
operation will result in shorter equipment  life.

It  is recognized  that the  MCIA plant will not  initially
receive enough sewage sludge to  operate  continuously.   Also,
plans are being discussed to allow  for  flushing  of  equipment
with  clean  carrier  oil when the  plant  is  shut down and  for
circulating hot  carrier  oil to  pre-warm equipment  before
startup.   However,  according to  information from  the City of
Los Angeles,  it  may take longer  than  a weekend to turn  the
MCIA  plant  around,  and,  even if the turn-around can be made
over  a weekend,  the high weekend pay rates for  personnel to
shutdown, repair,  and  startup  may make  this approach  very
costly.

An important consideration  in planning  the mode  of  operation
is health and safety.   The highest hazard and  risk periods
in  any plant  operation  occur during  startup and  shutdown.
For  this reason,  continuous operation  is  generally  safer
than  intermittent operation.
                             3-12

-------
                         SECTION 4

     IMPLEMENTATION OF CHEMICAL PROCESS  TECHNOLOGIES FOR
               MANAGEMENT OF MUNICIPAL WASTES
Implementation of  the Carver-Greenfield Process in municipal
sewage  sludge  drying is  one case  of a  broader  movement
toward  seeking new, more  sophisticated  solutions  to  the
management  of wastewater,  sewage sludges,  and  other solid
waste  disposal problems.    Although  the  future  roles  of
federal and  state  agencies  are  uncertain,  it  is inevitable
that the  requirements  for  the management  of  sewage  sludge
and municipal solid waste will become  more stringent.

Pioneering  new applications, even of  proven  technologies,
for managing  these wastes  will  continue  to bring problems.
Some  of the  initial  implementation  problems  of  chemical
process technologies  can be  made  less  troublesome  for  both
the system designer  and municipal owner and operator by  an
increased  awareness of  the  exacting requirements for
starting up,  operating, and  maintaining  these  new  systems,
and the additional restrictions  imposed by  the procurement,
funding,  and  staffing   policies  that  most  municipal
institutions must follow.   This increased  awareness  is
necessary  to plan  for and  adequately  provide  for successful
management  of  chemical processing  systems  in municipal
applications.
4.1. Factors  That Influence Facilities  in Municipal
     Applications

One of the factors  that  makes  a municipal  application  of  a
chemical  process  technology very  different  from an
industrial  application  is that  municipal  facilities  are
non-profit,  public service   operations.   In contrast,
chemical  industry  operations   are  profit  motivated,  and
management  decisions  are  based  primarily  on  economic
considerations.   If  the potential  profit  warrants  the
expenditure,  private  industry  focuses  tremendous  manpower
and capital on  a startup or operations  problem.

In a municipal facility,  guidelines  for management decisions
are not so clear-cut.  Elected officials who influence plant
operations  are very  much  aware  of  public  reaction  to  both
apparent  and  real  increased waste treatment  and  disposal
costs,  and  the  cost has to be  balanced  with complicated
public health and  environmental  considerations.   Under these
circumstances,  the  municipal facility manager  may  well be
criticized  for what would  be  "normal"  expenditures in  a
similar  facility  belonging  to a chemical  or  refining

                            4-1

-------
company.   The  owner of  a new  type  of municipal facility
should  always  consider whether  increased  current
expenditures,  especially during  startup, will  be  offset by
longer term savings.

Another  factor  that makes the  implementation of chemical
process technologies difficult in municipal applications is
a general  lack  of common  experience  among  the personnel in
the  chemical process  industries  and  municipal  sectors.
These differences start with  educational background and on-
the-job  training  and  continue  through  professional
experience.    For  example,   the majority  of  technical
personnel  in chemical processing  operations are chemical
engineers  by training, while the  majority  of  technical
personnel  in municipal operations  are  civil and sanitary
engineers.   Each  of these engineering disciplines and each
of these sectors  (chemical processing  and municipal) has its
own  vocabulary,   organizational characteristics, priorities,
and standard operating procedures.  After a  few years of on-
the-job experience,  engineers  in  each  sector begin to assume
that the approaches  they use are  typical  and familiar to all
engineers,  even  though practices  and  experience in different
sectors are often quite  different.

The differences  between the chemical  process  industries and
the municipal sector extend to the companies and consultants
that serve  them.   Suppliers  of  technologies,  services, and
equipment to the chemical/refinery industries  have developed
capabilities to  respond to the  needs  and  demands of  their
clientele,  which may  be quite different  than  the  needs and
demands of  a  municipal client.   Suppliers  and clients are
both  inclined  to make certain  assumptions based on  their
previous  experience,  assumptions that  may be unwarranted
when  they deal for  the   first  time  with  a  person  from a
different  type  of  background.   This  situation can make
effective communication very  difficult  in  cases  where full
communication  is critical.   For example,  the past  experience
of  a  system designer that  had traditionally  served a
chemical/refinery  clientele   would  lead  that designer to
assume  that the client  would  have  substantial in-house
resources  for   startup  and  operation of  a new  system
involving  complex  technology.  A  municipal  sector client
dealing for the first  time with a chemical/refinery system
designer  would  probably  assume that  his own  operations
personnel  possessed  adequate  startup  and operations
expertise for a  chemical processing type of system, because
they had been successful starting up  and operating municipal
systems in  the  past.   In this  case,  the  municipal client
would  probably  not  ask  for   startup assistance,  and the
chemical/refinery system designer would  probably  not  offer
it.   A likely  end  result of  this  situation  would  be that
additional startup and  operations resources would be needed

                            4-2

-------
but not provided for when initial startup was attempted.

In addition to personnel and  communications  problems, there
are a number  of  institutional  problems that create  obstacles
to the  successful  implementation  of these  more complex
technologies in the municipal sector:

         Municipalities  and  other  public  sector  entities
         generally  lack the  resources and time to conduct
         detailed  research and development  work to ensure
         the  feasibility  of  a  new  technology.   This  can
         cause  difficulties  during  the  startup  and
         operation of  the new facility;

         Public  bidding requirements  and  time limits on
         contracts for even minor goods and services create
         timing,  continuity,  efficiency,  and  quality
         control problems on municipal projects;

         Municipal project  management  may  have  limited
         control in selecting highly qualified construction
         companies because of  bidding requirements;

         Specifications  on municipal  projects  may  allow for
         "or equivalent" purchasing.   This leads to quality
         control  problems   if the evaluator is  not
         sufficiently  skilled to evaluate equivalency;

         Traditional  municipal sector  authorization  and
         purchasing systems  may  be slow  and  cumbersome
         compared  to those  supporting the  industrial
         chemical  and  refinery  facilities.    Startup,
         especially  of complex  systems,  often  demands
         short-notice or  emergency  expenditures  and
         procurement;

         The  additional  attention to  architecturally
         pleasing  building  design that  may accompany
         municipal projects  may  be at the  expense of
         process  design considerations,  e.g., equipment
         layout  and  sizing  may be  inhibited.   Walls  and
         floors also  inhibit  visibility  in  a plant.    This
         limitation  is more  critical  in  more  complex
         systems, and  extra staff may be  required to cover
         areas that are  blocked from view.  Building design
         can  also cause  accessibility problems that
         increase the  time  required and  cost   for
         maintenance;

         Municipal  facility  owners  may have  limited
         in-house engineering  resources to  perform
         evaluations  and  design work.   Many  have

                           4-3

-------
          traditionally  depended  on outside consultants who
          do  not have  the  responsibility  for  operating and
          maintaining  the  facility  once  it is  built.   Also,
          the  traditional  experience  of municipal technical
          staff and  their  consultants does  not typically
          include management of chemical processing systems;

          Hiring and  keeping  the personnel  necessary to
          operate  and maintain  a complex  facility  may be
          quite difficult because  of hiring restrictions,
          wage  scale,  and  promotion  and  benefit practices
          that have long been established  and  in place in a
          municipal environment;

          Funding  from various sources,  such as  the federal
          government,  brings  other  constraints that  may
          impede the  implementation  of municipal projects.
          For  example,  for many years  regulations governing
          the  use  of  federal funds  allocated  under EPA's
          Clean  Water  Act  prohibited  "turn-key" plants; that
          is,   the  designer  was  not  permitted  to  also
          construct the facility;

          Procurement  is  often  done  by  the construction
          contractor who  is asked to  reconfirm  the system
          design based on the  specific  equipment purchased.
          Few  general contractors have  the  capability to
          make  the process  and  mechanical calculations
          necessary to  accomplish  this  task  where the design
          involves  complex technologies.
4.2. Making the  Transition

Introducing  chemical processing  type  facilities  into
municipal  applications  represents a  major  transition for
municipal owners and operators.   As discussed in  subsection
4.1, the first step is to recognize that  chemical  processing
type  facilities  are different  from  traditional municipal
treatment  and disposal  systems  and that  they  require very
different handling  if  they  are  to  be successfully
implemented.   The  second step in  making  the transition to
more  complex  systems is  to devise  ways  to  meet  these
different  needs  and to  minimize  limitations  imposed by
governmental requirements.

Several key points  should be remembered and provided  for:

          Technical personnel  who  start  up complex systems
          must  possess highly  specialized  skills  and
          training;
                            4-4

-------
          It is essential  for  a  successful startup to follow
          a very comprehensive  specialized  routine  of
          careful performance evaluation of  all components
          of the  system as the startup  proceeds;

          Instrument  specialists are essential in a startup,
          especially  to   install  and maintain monitoring
          systems for performance evaluation;

          Temporary startup personnel should work  very
          closely with  the  permanent  plant  personnel,  so
          that the  acquired  operations expertise will  be
          retained  in  the  plant  and  insure  continued
          successful operation;

          Since  the municipal sector  is  non-profit  and
          service oriented,  the technology used  should  be
          cost competitive for the  degree  of  treatment and
          environmental protection  afforded;

          The  municipal owners  must work  under   many
          governmental  limitations  not  often  found  in
          industrial applications.
4.3. Obtaining Necessary Skills/Training

In order to be able to identify and hire the best qualified
contractors  and/or  permanent  personnel,  the municipal
facility owner should  know  the process, its  specific  unit
operations  and equipment, and  the level of  operations  and
maintenance support  required.   He  should also be aware  that
industrial  backgrounds are  so  specialized  that many
personnel with years of  chemical  processing  experience  may
be  of  limited  assistance  in  starting up or  operating  a
particular  plant.

Specialized and direct assistance is  also  essential  when  a
traditional  municipal  consultant or architect/engineering
firm is  involved in the project.   It would  be advisable  for
the owner  to be  able  to communicate  directly with  specific
technology  consulting and  engineering experts in addition to
his traditional  consultants.   Second  only to the technology
experts,  the owner  should  become the most knowledgeable
person  on  the  project,  because  he  is the  one who  must
ultimately  deal with  the  problems  that  arise.    It  is
essential for the owner and his staff  to have the following
information available and learned  for the new system:

         Basic  theory of the technology  and  unit
         operations;
                            4-5

-------
          Plant  design,  including  the  function of  each piece
          of  equipment;

          Startup,  shutdown,  operations,  and  maintenance
          procedures;

          Hazard,  risk, health,  and safety  considerations
          and procedures;

          Specifics  of  plant  layout,  including  how layout
          affects  personnel  movement  and access  for
          maintenance and cleaning;

          How the  new  system differs  from traditional
          municipal operations  and  what  additional  support
          it  will require.
Key plant  personnel  would  benefit greatly from an  extended
visit, possibly several months, to at  least one plant using
the technology.  This  time would  be well  spent in  observing
and discussing  operations  and maintenance with experienced
plant personnel.

Startup  and  operations personnel  for chemical processing
systems have a  totally different  type  of  background to call
upon than traditional municipal operations personnel.  Since
the startup of  these  complex  systems  is  so specialized,  it
will generally be more efficient  for  the  municipal  owner to
carefully contract for  this  qualified assistance.   For the
municipal  facility  owner  who wishes  to develop  the
capabilities of his  own  operating staff  (the normal case),
qualified contract startup  personnel  should participate  in
the startup  and first few  months of  continuous operation,
and help  train  the owner's  staff  to assume their
responsibilities.

It  is  also  important  to take  special  steps to retain newly
acquired  and  trained personnel.    The  work  in  the  new
facility  is  likely  to be  very demanding, and a  system of
appropriate compensation  should be provided.   If the needed
talents cannot be developed and retained  within the system,
an  important alternative is to contract out these  essential
services.

Training of maintenance personnel  can be done  through vendor
and  other  programs.   Most  vendors  are willing  to  hold
training  sessions on  the  maintenance of  their equipment at
no  cost  or at  some  nominal charge to the customer.   This
same  type  of  program  is  usually  available  for  plant
instrumentation.   Vendors  of  the  main control system
generally have simulators  set up specifically  to demonstrate

                            4-6

-------
their system and train those who have purchased, it.

Engineer, operator, and  maintenance staff  training can  also
be  contracted  out to  a  firm  qualified  to  train  in  the
operation of  the particular process.    Generic training
courses are of assistance in gaining generalized background,
but  personnel  should  be  exposed to  the  specifics  of  the
facility they will be  expected  to operate.   Training  and
experience with a complex technology can  also be gained  from
use of models and pilot  plant operation.

If  a  facility  will be  using  a new  technology  or an
established technology in a  new application, pilot plant
operations  should  be  carefully planned  and  conducted.   In
order  to serve  as a  representative  design  model,  a pilot
plant  should  have the  same feedstock  and  additives  present
and simulate all  the  operations that  are to  be performed in
the full-scale operation.  To  the greatest extent  possible,
the pilot  plant  should have the  same type of  equipment as
the full-scale facility.  Differences  between the  pilot-  and
full-scale  plant  should  be  minimized,  because even minor
changes  in  scale-up are  potential  sources  of problems.
Particular  attention should  be   paid to  duplicating  the
effects of system recycle streams  on overall plant  operation
and  material  balances.   Also,  engineering  evaluation is
needed to determine whether the pilot  scale is sufficient to
allow confident scale-up of critical equipment.
4.4. Cost and Operational  Expectations

In  the  chemical process  industry, typical  startup  expenses
of  an established technology and application run  five  to  ten
percent of  the  total  capital cost of a  project.   If a  new
technology or application is involved, startup is likely to
run  ten  to as  much as  twenty  percent of the total  capital
cost of a project.  This cost of startup includes personnel,
consumables, modifications,  and other  startup expenses.   The
owner  needs to  arrange  for funds  to  be  immediately
accessible, because  many  startup expenditures  are  on an
emergency basis.  Delays lead to a total absence  of  progress
while  capital  and personnel  costs  continue.    One way of
allowing  for  immediately  accessible   funds  would  be  to
include  startup  expenses as part of  project  capital
allocations.

The  owner  of  a  plant  that  involves design  innovations or a
new  application should expect that the  new  facility may  not
reach one  hundred  percent of design  capacity as  originally
installed.    In  the  chemical  process  industries,
modifications  to  achieve design  capacity are  usually
postponed  until after continuous  operation  is  achieved at

                             4-7

-------
the  highest capacity  possible  as  originally  installed.
Postponing  modifications  that do  not actually  prevent
continuous  operation  is  advisable  for several  reasons:
problems  observed  at  low  operating rates  may change or
disappear  at higher  operating rates,  and, in the  worst case,
a modification  that  solves  a problem  at  low operating rates
may actually cause problems  at higher operating rates.

Because  the design and installation of  modifications is
time-consuming,  especially if  long-delivery items  are
involved,  the  owner should  have  an  interim procedure for
treating and  disposing of  the sewage  sludge or  other
feedstock that was scheduled  for  treatment  in  the  new
facility.   Alternative  treatment and disposal plans  are  also
helpful  in   dealing  with  normal startup problems,  such as
unscheduled  down-time and off-specification product.    Some
operational  problems should be  expected for  a  year after
mechanical  completion even  with  facilities  involving
familiar  technologies and applications.   In  the  case  of a
new  application  or  design   innovation,  this problem period
may be considerably  longer than  one year.
                            4-8

-------
                         SECTION 5

                        REFERENCES
1.    Crumm,  C.J.  II,  Pluenneke,  K.A.,  "Development  of  an
     Efficient Bioraass Drying Process  and  its Commercial Use
     for Energy Recovery,"  Institute of  Gas  Technology
     Energy from Biomass  and  Wastes VIII Symposium, 02/84.

2.    Hyde, H.C.,  "Technology Assessment of Carver-Greenfield
     Municipal  Sludge  Drying Process," PB  85-138634,
     EPA-600/2-84-200,  U.S.  Department  of  Commerce, National
     Technical Information Service, 12/84.

3.    Raksit,   S.K.,  Haug,  R.T.,  "LA/OMA  Project
     Carver-Greenfield  Process Evaluation, A Process  for
     Sludge  Drying," LA/OMA Project,   Whittier,  California,
     12/78.

4.    Walker,  J.,  Zirschky,  J.,  "Summary  of  the 1987
     Carver-Greenfield  Sludge Drying Technology Workshop:
     Problems  and  Solutions,"  EPA-430/09-87-010,  U.S.
     Environmental  Protection Agency,  Washington,  D.C.,
     09/87.
                           5-1

-------
APPENDICES

-------
                         APPENDIX A

                THE CARVER-GREENFIELD  PROCESS
The  Carver-Greenfield  Process  is a  patented  drying process
invented by Mr. Charles Greenfield.  "Carver" in the process
name refers to  the  fact  that Mr.  Greenfield did some of his
early process  development  work in  a laboratory supplied by
Fred S.  Carver,  Inc.   The Carver-Greenfield Process patents
are  the  property  of Dehydro-Tech  Corporation of  East
Hanover, New Jersey.

The  first  commercial  application  for  the  Carver-Greenfield
Process was  the processing  of  slaughterhouse  waste,  to
recover tallow and  dry protein-bone meal.   Since the process
was  first  implemented  in  1961,  there  have been a total of
seventy-four full-scale plants put into operation worldwide,
and  three more  major  plants  are  scheduled for  startup by
1990.   These plants have been designed to dry a wide variety
of  feedstocks,  including  sludges  from industrial  and
municipal wastewater treatment  facilities.

The Carver-Greenfield  Process was chosen for the purposes of
this review as  an example  of a more complex technology that
has  been  adapted  to  a municipal  sector  application,  the
drying  of municipal sewage sludge.  There are currently four
federal/state  jointly  funded  Carver-Greenfield  projects in
the United States,  one is involved  in  a  long and difficult
startup and three more  are  under construction.
A.I. Heavy and Light Oil Carver-Greenfield Processes

The  characteristics  of the  Carver-Greenfield  Process  that
give it  an  advantage over other  technologies  in  many
difficult drying  applications  are  energy-efficiency  and the
introduction of  a "carrier"  or  "f luidizing" oil  into the
feedstock.   The  most essential function of  the  carrier oil
is  that  it  keeps  the  material  fluid, so  that it  can  be
pumped  through the  process  equipment  even  after virtually
all  of  the  water  has  been removed.   This  carrier  oil  also
enhances  mixing  and  heat transfer,   and,  in  some
applications, acts as a  solvent for indigenous oils that are
recovered as a by-product.

In  the  original  slaughterhouse  waste application,  the
carrier oil  is tallow,  which is relatively  nonvolatile  or
"heavy."  A  major  process  innovation, which was developed in
the mid-1970's, is  the  use of a volatile or "light" carrier
oil.   A  light  carrier  oil  is easier to separate  from the
dried  solids  than a  heavy  oil,  but  it does  require  more

                             A-l

-------
stringent safety procedures than a heavy oil, to avoid fires
and explosions.   A  total  of  seven  Carver-Greenfield  light
oil  plants have been built,  in addition  to  the  four
municipal sewage  sludge facilities that  are in startup  or
under construction in California and New Jersey.
A.2. Carver-Greenfield Multiple-Effect Evaporation

Three of the  four  U.S.  municipal  sewage  plants,  The City of
Los Angeles  (California)  Hyperion  facility,  The  Los Angeles
County  (California)  Sanitation  Districts facility,  and  The
Mercer  County  (New Jersey)  Improvement  Authority facility
share  the  same basic  process  configuration:   four-stage
multiple-effect evaporation.

Multiple-effect evaporation was  already  a well-established,
proven technology when Mr. Charles Greenfield adapted it for
use  in his  original process application.   Multiple-effect
evaporation  is  very  energy-efficient  compared  to  other
drying technologies, because it recovers heat from the water
vapor that is driven off  during the drying process.

A  process  flow diagram  for  a  municipal  sewage  sludge
four-stage multiple-effect Carver-Greenfield system is shown
in Figure 4 on page A-3.  In this process configuration, the
feedstock or  material to be  dried (indicated by  the heavy
line, moving  from  left  to  right)  passes through  a grinder
and into a  "fluidizing"  tank  where  it  is mixed with carrier
oil and dried solids recycled from the  process.  Some of the
dried  solids  must  be  "added  back"  to the  feedstock  to
increase the  solids concentration  in the mixture  and avoid
an  undesirable  phenomenon  called "gummy phase."    Acid  to
control  the  formation  of  "soaps" is  also mixed  with  the
feedstock in the fluidizing  tank.

From the fluidizing tank, the process stream passes into the
first stage  vaporizer,  where it  is  heated  under  vacuum  to
evaporate a  portion of the water.  The  process  stream then
passes  through the second,   third,  and  fourth stage
vaporizers  in sequence.   Virtually 100% of the  water  has
been evaporated  out of  the process stream  by the  time  it
leaves  the  fourth  stage vaporizer.    Most of  the process
stream  from  the fourth stage vaporizer is pumped  to  the
centrifuge,  but  a  portion  is  added back to the fluidizing
tank to raise the solids  concentration.

In  the  centrifuge,  most  of  the carrier  oil  and  the
indigenous sewage oil are separated from the dried solids in
the process stream.  The  process stream then passes into the
first of two  "hydroextractors" or devolatilizers, where heat
is  used  to  drive off  the remaining oils as  oil  vapor from

                            A-2

-------
3

-------
the dried solids.  The hot, dried solids then pass through a
cooler  before  being  sent to  storage.   This  dried sewage
sludge may  be  used as a  fuel  or as  a  fertilizer,  if heavy
metals or other contaminants  are not  a problem.

In  the upper  right corner  of  Figure  4  are a  "sewage  oil
stripper"  and  a  "flash still," where  the carrier  oil is
separated from  the  sewage  oil.   The carrier oil is recycled
into the system.  The sewage  oil can  be  burned as a fuel.

The energy-efficiency  of  this  multiple-effect  system is due
to the  fact  that an external heat source,  steam,  is used to
heat only the  fourth stage vaporizer (by means of the flash
still).   The third  stage  vaporizer  is heated  by the water
vapor  that  is  driven  off  in  the fourth stage;  the second
stage, by  the water vapor  from the  third  stage;  the first
stage, by the water vapor from  the second stage.
A.3. Carver-Greenfield Mechanical  Vapor  Recompression

The  fourth  U.S.  municipal  sewage sludge plant,  located in
Ocean County,  New  Jersey,  will have a  new  feature,
mechanical  vapor  recompression  (MVR).    MVR is  a proven
technology  that has  recently  been  adapted  for use  in the
Carver-Greenfield Process.   Carver-Greenfield  MVR  has  been
demonstrated in  a commercial facility  in Holland since 1983
and in pilot facilities in Italy  and Holland.

Referring to  Figure  5,  page  A-5,  which shows  the Ocean
County  facility,  the  water vapor evaporated out  of the
process stream  in  the vapor recompression evaporator, along
with the  vapor  from  the first  of two non-MVR drying  stages,
passes through  a powerful  compressor  and then back  to the
heat exchangers  that  supply heat  to the vapor  recompression
evaporator.   The process  stream  then passes  from  the vapor
recompression evaporator  through  two multiple-effect drying
stages  that  do  not utilize  MVR.   The  centrifuge,
hydroextractor, and  sewage  oil  systems serve  the  same
functions described in subsection  A.2.

One advantage of using MVR in  a  Carver-Greenfield system is
that it  simplifies  the process.    In the four-effect system
described in subsection  A. 2,  it  is necessary to  add  back
some  of  the dried  solids  in order to  avoid  problems  with
"gummy phase."   With  MVR,  the solids  concentration  in the
process  stream  entering  the vapor recompression evaporator
is  below  the solids  concentration where gummy phase  occurs,
and the  solids  concentration out  of the MVR stage is higher
than the  level  where gummy phase  occurs.   This undesirable
phenomenon  is  therefore  contained  and  effectively bypassed
in the MVR drying stage.

                             A-4

-------

-------
A  second advantage  of  MVR is  increased  energy-efficiency.
The Carver-Greenfield MVR system at Ocean  County is  expected
to use approximately the same amount of energy  as the  four-
effect  Carver-Greenfield  municipal  sewage  sludge drying
systems to produce one ton  of  dried product,  even though  the
feedstock  at  Ocean County  will  contain  6%  -  8% solids
compared to  18% -  22% solids at  the other facilities.
                            A-6

-------
                         APPENDIX B

      QUALIFICATIONS OF INDUSTRIAL REVIEW TEAM MEMBERS
                 AND EPA PROJECT MANAGEMENT
Manuel Gonzalez
Associate Engineer
Mobil Research and Development Corporation
Pennington,  New Jersey 08534
(609)737-5261
Bachelor  of  Science  in  Chemical  Engineering  from  the
University  of Puerto  Rico  (1964).   Twenty-four years
industrial experience  with Caribe  Nitrogen  Corporation,
Commonwealth  Oil Refining Company, Davy  McKee  Corporation,
and  Mobil Research  and Development Corporation.    Special
expertise in design,  process development,  startup,  trouble-
shooting,  and  other  support  functions  for  refinery  and
petrochemical  manufacturing  facilities.    Background  also
includes petrochemical plant operations and management,  plus
technical support  for  a  multiple-effect evaporation  system.
Currently provides  technical  services  and operations
assistance to Mobil facilities worldwide.
Frank Y.  W.  Liao
Senior Associate Engineer
Mobil Research  and Development Corporation
Pennington,  New Jersey 08534
(609)737-4955
Bachelor of Science in Chemical Engineering  from  Chung  Yuan
College (1965)  and Master  of  Science in Chemical Engineering
from  the  University  of  Mississippi  (1968).    Twenty years
industrial  experience  with the Mobil Corporation, ANG  Coal
Gasification  Company,  and  ITT Rayonier,  Inc., including  nine
years  experince  in  refinery  and petrochemical plant
operations  support.  Special  expertise  in  multiple-effect
evaporative  and  fluidized-bed  incineration  systems.
Designed,  started  up,  provided  trouble-shooting  services,
and developed training  manual  and job  procedures for  a
six-effect  evaporation  system.    Current responsibilities
include environmental  engineering  support  for capital
projects and  solving  pollution control problems  for Mobil
facilities  worldwide.   Member  of  the American  Institute of
Chemical  Engineers  and the Water  Pollution Control
Federation.

                            B-l

-------
Kathryn A.  Pluenneke
Proprietor
Technical Services
590 Mountain Avenue
Gillette, New Jersey 07933
(201)647-7424
Bachelor of  Science in  Chemical  Engineering  from  the
University of Houston  (1978).   Four years experience with
the Dow Chemical  Company, plus seven years as  an independent
consultant.    Dow experience in chemical  and  petrochemical
plant  operations  and support services.    Previously  a
licensed  water   and  wastewater treatment operator  in  the
state  of Texas.   Currently  proprietor  of  business that
provides  support  services to companies involved in  technical
consulting,  engineering, and  engineered  products.  Services
offered include research of  technical subjects  and  technical
markets,  and technical  writing.    Member of   the American
Institute of  Chemical Engineers.
Gilbert Rowe
Environmental Consultants
110 Hillcrest Avenue
Morristown, New Jersey "07960
(201)267-2920
Bachelor of  Science  in  Chemical  Engineering  from  City
College  of New  York.   Thirty-five  years  industrial
experience  with Exxon,  plus  two  years  as an  independent
consultant.   Exxon  experience covered all phases  of  refinery
and  petrochemical plant  design,  startup assistance, and
technical and operations management; as well as  developement
of  wastewater  and  solid waste  treatment  technology and
design  of  treatment  plants.   Responsibilities  included
personnel  and  organizational  development,  in  addition to
startup, and  after  startup  technical  and  operations
supervision.    Currently  provides  consulting  services in
hazardous  waste and wastewater  management;   problem
assessment  and mitigation;  and  planning,  study,  and
evaluation  of  other  environmental  problems.    Author of
"Evaluation  of  Treatment Technologies for  Listed Petroleum
Refinery Wastes,"  a major  report  for the  American Petroleum
Institute, May,  1988.
                            B-2

-------
Martin J.  Siecke, P.E.
Safety Manager
Safety and Environmental Affairs
National Starch  and Chemical Corporation
10 Finderne Avenue
Bridgewater,  New Jersey 08807
(201)685-5119
Licensed Professional Engineer with Bachelor of  Science  in
Chemical  Engineering  from Newark College  of Engineering
(1963).   Twenty-five  years  experience with  the  National
Starch  and  Chemical  Corporation,  including  seventeen  years
in all  phases  of chemical and petrochemical plant  startup,
operations,  and  maintenance.   Responsibilities  involved
staffing,  training,  and organizational development.
Previously a licensed industrial wastewater  operator  in the
state of Illinois and Chairman of  the Supervisory Committee
for  the  Plainfield Joint  Meeting Sewerage Authority.
Currently  responsible  for National  Starch's  health  and
safety  concerns,  including personnel training  for  risk and
crisis management.   Member of  the  American Society of  Safety
Engineers,  National  Fire  Protection  Association,  and
National Society of Professional Engineers.
John M.  Walker,  Ph.D.
Physical Scientist
U.S. Environmental Protection Agency,  WH-595
Office of Municipal Pollution Control
Washington,  D.C.  20460
(202)382-7283

Bachelor of Science from Rutgers University (1957);  Masters
(1959)  and Doctors (1961)  degrees from  Purdue University.
North  Atlantic  Treaty  Organization  Postdoctoral  Fellow  in
Rothamsted Experiment  Station in England.   Twelve years with
the  U.S. Department  of Agriculture  in  environmental  and
agricultural  research,  including  development  of techniques
for  composting and  land  application of  sewage sludge.
Twelve  years with  EPA.   Current responsibilities  include
evaluation  and improvement  of  design  and  operation  of
technologies  for sludge  management  and  development  of
guidelines for safe use and disposal of  sludge.   Fellow  of
American Association  for the Advancement  of Science;  member
of  Water  Pollution  Control Federation and  many  other
professional  organizations.   Author  of more  than 150
publications.
                            B-3

-------
Harry E.  Bostian, Ph.D., P.E.
Chemical  Engineer
Water and Hazardous Waste Treatment Research Division
Risk Reduction  Engineering Laboratory
U.S. Environmental Protection Agency
Cincinnati,  Ohio 45268
(513)569-7619,  FTS-684-7619
Bachelor  of  Science in  Chemical  Engineering  from Bucknell
University  (1954),  Masters  in  Chemical  Engineering  from
Rensselaer  Polytechnic  Institute  (1956), and  Doctor  of
Philosophy in  Chemical Engineering (1959) from  Iowa  State
University.   Thirty years  technical  experience  with  EPA,
Universities  of  New Hampshire and Mississippi,  and  Exxon
Corporation.    Experience  in  distillation,  solvent
extraction,  fluidization,  computer applications,  operations
research, municipal  and  industrial  pollution control
including  sludge  management,  energy-environmental
considerations.   Teaching  of  almost  entire  undergraduate and
graduate  chemical  engineering currricula.    Advisor  for
masters and doctoral candidates.   Over 70 papers, reports,
and  theses,  including  presentations  at  meetings  and
publications  in journals that are of international stature.
Contributed  to  "Technology  Assessment  of  Carver-Greenfield
Municipal  Sludge Drying  Process"  (Reference  2,  p 5-1)  as
Technical  Manager for  EPA  during  final editing and review.
Member  of American  Institute of  Chemical  Engineers,  Water
Pollution Control  Federation,  American  Association  for
Advancement  of  Science,  Sigma Xi,  Tau Beta  Pi,  and  other
honoraries.
                            B-4

-------
                         APPENDIX C

                    OTHER OBSERVATIONS BY
               INDUSTRIAL REVIEW TEAM MEMBERS
Note to reader:  The observations in this appendix are  based
    solely on information available to the Industrial Review
    Team   in July,  1988.    Some  of  the  changes  and
    developments that have occurred since July,  1988, at  the
    Los  Angeles City  (LAC)   and other  facilities are
    discussed  in  Appendix  E,  "Status  of  the  Carver-
    Greenfield Municipal Sewage  Sludge Drying  Facilities:  A
    Brief  Update."
As  of July  12,  1988,  the  LAC plant  had  not yet  operated
continuously for  a period of  time sufficient to  determine
whether design  modifications may be required.

Compared  to  the  full-scale  Carver-Greenfield  municipal
sewage sludge  drying  facilities,   the  Los  Angeles -  Orange
County Metropolitan Area  (LA/OMA)  pilot  plant  work  involved
a different carrier oil, different feedstock,  a single-stage
system, and no  sewage  oil/carrier oil separation.

The  abrasive  characteristics  of  the  LAC sludge were
unexpected, and it is uncertain whether erosion problems  are
now under control.

LAC had  not yet  attempted  acid addition  as  per  design  to
control formation of soaps.

The  unsolved  problem  of  carryover of  solids  into the
oil/water separation system inhibits plant  function at LAC.
Much  of  the  solids  carryover  appears  to  be  from the
hydroextractor  overhead.

LAC  had  not  yet operated  the  sewage  oil/carrier oil
separation system  as  of  July  12,   1988.  The  separation  has
not been  attempted in the absence  of  the facilities to burn
the product sewage  oil.

There were still unresolved  startup and shutdown problems  at
LAC as of July  12,  1988,  including:

    Line  plugging and  exchanger fouling at low flow rates;

    Formation of  clinkers during hydroextractor warm-up.

The fire  and explosion  hazards associated with the process
were  not  fully  appreciated  until after  the  fact  at LAC.

                            C-l

-------
Health and safety procedures and training were inadequate by
chemical or refining industry standards.

If  the Mercer  County  Improvement Authority  (MCIA)  milling
operation  is  not effective, the  fouling problems with  the
spiral  heat  exchangers  due  to  human  hair that  LAC  has
experienced  may  be  more  frequent at  MCIA,  where  the
undigested sludge feedstock is more  inclined  to  have  intact
fibers than digested sludge.

A startup  team  with the  types  of  skills  and experience that
a chemical  processor or  petroleum refiner  would concentrate
on  an  initial  startup was  lacking at the  LAC  plant  as  of
July 12, 1988.

The  Industrial  Review  Team  recommends that  startup  and
operations personnel at  LAC have  chemical plant  or  refinery
experience  because  of the  similarity of the  plant  to
industrial facilities.

At  LAC,  the  carrier  oil  concentration  in the  product  is
still higher  than the  design level of  1  to  2 percent.   High
carrier  oil  concentration  occurs  during  cold startups.
Similar carrier oil  levels  at  MCIA could cause  problems  for
using the dried product as a soil  conditioner.

On-line analyzers  at  LAC were  not functioning  as  designed
when  the  Review Team visited  the plant.   The  control  of
oil/sludge ratio  was based  on  a daily material  balance,
which  is  not  adequate  to maintain  product  quality  control.
However, there is optimism regarding new on-line analyzers.

Regular shutdown and startup at LAC  takes  about three days,
to  allow  time for cool-down,  draining, and  clean-out.   The
tentative MCIA plan  to operate five  days and shut down
weekends  may not  be  feasible in view of  this  turn-around
time.

Equipment  layout  in the  LAC  plant  makes  maintenance
difficult.   For example, the  tube-bundle  in the condenser
unit cannot be  pulled  out because there is  not  enough head
space.

The  LAC  plant suffers  from high  personnel  turn-over  due to
wage scale and job classification  problems.

The  Los  Angeles  County  Sanitation Districts  (LACSD)  plant
has  incorporated  modifications  to their  system  in  order to
avoid some of the LAC problems.

The  LACSD  plant has a central control room  with three sets
of  CRT  stations to monitor and control  the  process.   There

                            C-2

-------
is also  a  supervisor CRT station  to  back up the operator's
control unit.

LACSD  plans  to use an  engineering  contractor  to provide
technical assistance during  initial startup.

Training materials  prepared at  LAC could probably  be made
available and would be of value  to  others.

LAC  has had  far  too  little  continuous  operating  time to
experience expected  system  problems  resulting  from buildup
of impurities in the system, such as sewage oils and fines.

Tungsten carbide has  been  the  most  successful hard-facing
material used at the LAC facility.

The  inertia  of the LAC municipal  purchasing  system has
required building  the spare parts inventory to  four  times
the manufacturer's  recommended level.

Based on  their  most recent experience,  LAC  expects  a train
of spiral heat exchangers to plug every six to eight weeks.

Based  on pilot plant  experience,  LACSD anticipates some
problems with odor.
                             C-3

-------
                         APPENDIX D

                      ACKNOWLEDGEMENTS


The Review Team  and EPA wish to express their gratitude  for
the  excellent cooperation  and assistance  of  those  parties
involved with  the  Carver-Greenfield  Process  who  provided
information,  plant  visits,  and meeting facilities.   Special
thanks to:

          The City of Los Angeles Department of  Public  Works
          Bureau of Engineering;

          The  City  of  Los  Angeles  Hyperion  Construction
          Division Bureau of Engineering;

          Clinton Bogert Associates;

          Dehydro-Tech Corporation;

          Foster Wheeler Martinez,  Inc.;

          Foster Wheeler USA Corporation;

          James M. Montgomery Consulting Engineers,  Inc.;

          The Los Angeles County  Sanitation Districts;

          The  Mercer County Improvement  Authority and  its
          supporting municipalities,  Trenton,  Hamilton,  and
          Ewing-Lawrence;

          Mobil Research and Development Corporation;

          The Ralph M.  Parsons Company.
                             D-l

-------
                         APPENDIX E

               STATUS  OF THE CARVER-GREENFIELD
         MUNICIPAL SEWAGE SLUDGE DRYING  FACILITIES:
                       A BRIEF UPDATE
The purpose of  this  appendix is to provide the  reader with
information on  developments  that  have occurred in the four
Carver-Greenfield  municipal  projects  (the  City  of  Los
Angeles,  Los  Angeles  County,  Mercer  County  Improvement
Authority,  and  Ocean County)   since  this  review  was
undertaken in July of  1988.   The  owners  of  these facilities
were  of  great  assistance in  providing  information  to the
Industrial Review Team  and were further  involved with this
review  project  as  recipients of  the  Drafts of  this  report
issued  for  comments  on September  9,  1988,  and  on  May 18,
1989.    Their  representatives  also participated  in  the
meeting held in Princeton, New  Jersey,  on  September  15 and
16, 1988,  for  the purpose of  the Industrial Review  Team's
discussing their findings  and making  recommendations  to each
municipality and to the  system designer and developer.
E.I. The City of  Los  Angeles Facility

When  this review  project  was undertaken, the  City of  Los
Angeles  Hyperion  Energy  Recovery  System  (HERS)  Carver-
Greenfield municipal  sewage  sludge  drying facility was  the
only one  of  the  four EPA-funded  Carver-Greenfield  municipal
facilities that was  fully  constructed  and in startup.    For
this reason,  the  HERS Carver-Greenfield plant was  extremely
important to  this project and was the basis  for many of  the
comments  and  recommendations  made  by the  Industrial Review
Team.

A number  of  changes  have occurred at the  HERS  facility  and
in  the Carver-Greenfield  operation  since  the  Industrial
Review  Team  visited in July, 1988.   At  an August,  1988,
meeting  at  Los  Angeles  City Hall, the  President of  the
City's  Board  of  Public  Works  requested that  all of  the
engineering companies involved in the project redouble  their
efforts  to achieve  consistent and  continuous operation of
the  Carver-Greenfield  and sludge  combustion  systems.   At
this  meeting,  it  was  also announced  that the system
designer,  Foster  Wheeler,  would  supply four  petrochemical/
petroleum refinery  startup/operations experts  to  serve as
twenty-four-hour-per-day  shift advisers.    In addition,  the
overall  management  responsibility  for  HERS  operations  was
shifted  from  the  City's  construction to  the  City's
operations department.   This  change recognized the need to
proceed  forward  into the  operations  phase, following  the

                            E-l

-------
 substantial  construction  phase  effort  that had successfully
 improved  the quality and  reliability  of equipment supplied
 under various construction contracts.

 A  great  deal of  progress  has been  associated  with these
 changes  since July,  1988.    Even  though  an unfortunate
 maintenance  accident, which  occurred in  early  October,
 slowed  progress by keeping the combustion  and sludge drying
 systems  shut down  until  the  end  of the year,  the plant
 underwent  comprehensive cleaning,  vacuum  testing,  and
 equipment  and instrumentation  review  as a preliminary step
 to  continued full-scale  startup activities.   All operations
 and  maintenance  manuals  (including  safety procedures)  were
 updated.   Also, during  the  last quarter  of  1988,  in-plant
 studies  revealed  that  some of  the slurry pumps  had been
 installed with  undersized  motors.    Corrections  were made
 where   possible  to  achieve  near design  velocities  in  the
 spiral  heat  exchangers.

.Following this  shutdown period,  the  improvements  in  the
 operation  of the  sludge drying system  were  dramatic.   This
 improvement  was achieved  by  attempting to  operate two of the
 three  trains at  all times, per the original design concept.
 During  the first 69  days  of  1989, more sludge was dried than
 during  the  entire year  of  1988  (see  Figure  6,  page E-3).
 Continuous  operation was achieved with dry  sludge being
 produced  83  days out of  the 90 'days  in the first quarter of
 1989.    Between February  3  and  March  31,  dry  sludge  was
 produced  on  57 consecutive days,  a facility record.  Most of
 this dry  sludge  powder  was burned to generate  steam  and
 electricity.

 According to plan, the  operating  level of  the  Carver-
 Greenfield  system  was  increased  incrementally  during  the
 first   quarter of  1989  to   somewhat  below  50% of  design
 capacity, as the  operators gained  familiarity  with  the
 system  and as the  comprehensive performance  testing of each
 of  the  various components  continued.   All  parts of  the plant
 were operated,  including  the flash  still to  remove sewage
 oil and  acid addition to inhibit the  formation  of soaps.
 With continuous operation,  many parts  of the plant that did
 not  operate  well  in an "up  and down"  mode began to operate
 as  designed.   Such previously troublesome  operating areas as
 the spiral  heat  exchangers,  the centrifuges,  and  the
 evaporator non-condensable  over-pressuring began to operate
 acceptably.

 On  March 23, 1989,  the six-month scheduled participation of
 the four-member  Foster  Wheeeler  startup team came  to an
 end.   Referring again to  Figure  6,  during April,  the plant
 was  shut down most  of the month,  and  little dry sludge was
 produced.  In May,  the plant performed close to its February

                             E-2

-------
 >-QJ«i- — >,   Q. >-


        H O C »   X



)
         CO         CO
                                                              ao — — oc


                                                             OOO
                                                                                                                   O CT

                                                                                                                   •o >,
                                                                                                                   o —
 CO


 £,    "o
 O> CO •*-
 C  o  «3
<  ^ Q

 co  .52  o
 o  ** I—
"™"  4^
*-  C/5 O)
 O  ^ CD

 >o2
                                                                                                          OS
                                                                                                          CO
                                                                                                          en
                                                                   -   5
                                                                                                         CO
                                                                                                         CO
                                                                                                         0>
                                                                                           <0

                                                  h- O c »


                                                    Q.1-OT33O*-— OC
                                                         E-3

-------
level.   However,  in  June, production dropped  off,  and
twenty-four-hour-per-day engineering supervision  was
reinstituted  at the end of  the  month.   Under  this
supervision,  there  was  a dramatic improvement  in  July,  when
a record 2,407 tons of dry sludge was produced.

It is  important  to note that,   to  date,  no  specific design
problems have been  identified  that would limit  dry sludge
production  to  50%  of  design capacity.   It is  hoped  that
progress  will  continue in  increasing  the output of  the
system incrementally toward design capacity.

Many of the observations and/or recommendations made by the
Industrial  Review Team  for  EPA have  been addressed  in  Los
Angeles.   Persons  highly  skilled  in startup  of  complex
technologies  that  involve equipment and  unit  operations
similar  to  Carver-Greenfield  were present  and  working  as
advisers on every  shift.   Startup  procedures  that  had been
developed through many  years of experience  in  the  chemical
manufacturing  and  petroleum  refining industries  were
followed.   This may have occurred coincidentally  as  the Los
Angeles startup  progressed,  and,  to  some degree,  it  may also
be a  positive result of  the Industrial Team's  review.   For
whatever  reason,  the  operational improvements have  been
dramatic.

These operational  improvements  strongly  emphasize  the
necessity for specialized petrochemical engineering  startup
expertise and techniques  in  a municipal sewage sludge drying
Carver-Greenf ie Id  system.    It  is hoped  that these
specialized  skills  will continue to  be  available during
startup at Los  Angeles and the other municipal  facilities
using the Carver-Greenfield technology until the  functional
capabilities  of  the  system  can  be  fully tested.    This  is
very important in determining the suitability of the current
design, the  need for any  possible  further  modification  of
design  and  operating  procedures, and  the ultimate
cost-effectiveness  of this  technology  for  drying municipal
sewage sludge.
E.2. Facilities  Under Construction

At  the expanded  Los  Angeles County  Sanitation Districts
(LACSD)  sludge management  facility,  construction  of  the
Carver-Greenfield  system  is 98%  complete,  and  the
incineration system where  the  dried  sludge  product  will be
burned  is  50%  complete.   Key  technical  and maintenance
personnel  have been  present  during the latter  stages of
construction.   Contractual arrangements  have  been  made by
LACSD  for  startup assistance by  technical personnel with
specialized knowledge of the Carver-Greenfield system.

                            E-4

-------
Construction  of the  Ocean  County,  New  Jersey,  Carver-
Greenfield  facility  is due  to  be completed  in  May,  1990.
Ocean County has  budgeted  substantial funds for engineering
review and  startup of  the  facility,  including funds to pay
for  contract  engineering  supervision from  a specilized
startup  and  operations  firm  that  has  experience  with
Carver-Greenfield sludge drying  systems.  After construction
is  completed,  there will  be a  nine-month  period  for
commissioning,  trial runs,  and  acceptance  testing.   During
this period, permanent  plant personnel will be trained under
the  direction  of  the  contracted startup engineers,  so that
they will be able to take over operation of the plant.   The
construction contractor  will not  be  released  from
responsibility  until after  the  nine-month  system check-out
is successfully completed.

Construction of  the  Mercer  County  Improvement  Authority
(MCIA) Carver-Greenfield  facility was halted  in September,
1987,  because of  construction  contractor  default.    As  of
August,  1989, bidding  for  the completion of the facility was
underway.    However,  since  the  first  bid  responses  were
rejected as high, it  is difficult  to estimate a date a which
construction may  resume.   There is approximately ten months
of  construction  work  remaining to complete  the  facility.
While construction work has been halted, MCIA  has authorized
considerable engineering  assessment and  design modifications
for  the  facility.    MCIA  is currently  exploring the
possibility  of  contracting for  specialized  startup
engineering assistance.
                            E-5

-------

-------