SECOND PROGRESS REPORT
LIME/LIMESTONE
WET-SCRUBBING
TEST RESULTS
AT THE
EPA ALKALI
SCRUBBING
TEST FACILITY
U.S. EPA
OFFICE OF
RESEARCH AND
DEVELOPMENT
PROTOTYPE
DEMONSTRATION
FACILITY

-------
[I,
   This capsule report describes a program con-
ducted by The Environmental  Protection Agency
(EPA) to test prototype lime and  limestone  wet-
scrubbing systems for removing sulfur dioxide
(SO2) and particulate matter (fly ash) from  coal-
fired  boiler  flue gases.  The program  is being
carried out  in a test facility which  is integrated
into the flue gas duct-work of  a coal-fired boiler
at the Tennessee Valley Authority  (TVA)
Shawnee Power Station, Paducah,  Kentucky.
Bechtel Corporation of San Francisco is the
major contractor and test director, and TVA is
the constructor and facility operator.  This
report describes a series of lime and limestone
reliability tests conducted from March 1973  to
December 1974. An earlier capsule report
(EPA Technology  Transfer Capsule Report
No. 4) discussed the results of limestone factorial
tests and initial limestone reliability tests.  The
results of an advanced program at the Shawnee
test facility  will be presented in future reports.
   In  a lime/limestone wet-scrubbing system, the
flue gas is contacted (scrubbed) with a slurry of
lime or limestone in water.  SC>2 is absorbed into
the liquor, where it reacts with the dissolved
lime/limestone, forming the waste products of
calcium sulfite and calcium  sulfate  (gypsum).
Particulate is removed  in the scrubber by impact
with the slurry droplets.
   The Shawnee test facility consists of three
parallel  wet-scrubber systems:  a Turbulent
Contact Absorber  (TCA), a  venturi followed  by
a spray tower,  and  a Marble-Bed Absorber.
Each system is capable of treating approximately
10 MW equivalent (30,000 acfm at 300°F) of
flue gas containing 1800 to 4000 ppm of SC>2
and 2 to 5 grains/scf of particulates.  Testing of
the TCA and venturi/spray tower is ongoing;
testing of the Marble-Bed Absorber has been
discontinued.
   The following tests have been conducted:
   •  Limestone factorial tests on all three
     scrubbers  to determine the effects of the
     independent variables (e.g., liquid-to-gas
     ratio, gas velocity,  etc.) on SC>2 and
     particulate removal
  •  Limestone reliability verification tests on
     all three scrubbers to define regions for
     reliable (scale-free) operation of scrubber
     internals
  •  Lime and limestone reliability tests on the
     venturi/spray tower and TCA systems,
     respectively, to demonstrate long-term
     operational reliability

  Test results have shown that scrubber internals
can be kept relatively free of scale  if the sulfate
(gypsum) saturation of the scrubber liquor is
kept below about 135 percent.  This can  be
accomplished by  proper selection of slurry solids
concentration, effluent residence time, and liquid-
to-gas  ratio.
  At the conditions tested, the  mist elimination
configuration presently used in the TCA appears
to be successful  in  handling the  problem of mist
eliminator scaling and  plugging — the most
significant reliability problem encountered during
the test program.  This configuration consists of
a wash tray  (Koch  Flexitray) followed by a
chevron  mist eliminator, both continuously
washed on  the underside with a combination of
clarified  liquor and makeup water.  In a test run
of over 3 months' duration in which the TCA
operated in a closed liquor loop at  a superficial
gas velocity of 8.6  ft/sec and a slurry solids
concentration of  15 percent, the system remained
essentially clean.
  A run of 3 months' duration  is yet to be made
with the venturi/spray tower mist elimination
configuration, which consists of a chevron  mist
eliminator with provision  for both underside and
topside washing.  With the system at  a superficial
gas velocity of 6.7  ft/sec and 8 percent slurry
solids concentration, scale formation on the top
mist eliminator vanes has  been a constant prob-
lem.   Underside washing by itself did not elim-
inate topside  scale formation.  But  when the
underside washing was combined with an  inter-
mittent high-pressure topside wash  of a single
section of the mist  eliminator, that section
remained essentially scale-free.  This procedure
seems promising and will be tested  further.

-------
  The test facility consists of three parallel
scrubber systems, each with its own slurry-
handling system.  Scrubbers are of prototype
size, each capable of treating approximately
30,000 acfm (at 300°F) of flue gas from  the
TVA  Shawnee coal  boiler No. 10. This
corresponds to approximately 10 MW of power
plant generating capacity. The equipment
selected was sized for minimum cost, consistent
with the ability to extrapolate  results to com-
mercial scale.  Boiler No. 10  burns a high-sulfur
bituminous coal, leading to SC>2 concentrations
of 1800  to 4000 ppm and particulate inlet
loadings  of about 2 to 5 grains/scf in the  flue
gas.
  The major criterion for scrubber selection was
the potential for removing both SC>2 and  particu-
lates at high efficiencies (SC>2 removal greater
than 80 percent and particulate removal greater
than 99 percent).  Other factors considered in
the selection of the scrubbers were (1) ability
to handle slurries without plugging or excessive
scaling,  (2) reasonable  cost and maintenance,
                                  (3) ease of control,  and (4)  reasonable pressure
                                  drop.
                                     On the basis of information available in the
                                  literature, the following scrubbers were selected:
                                     • Turbulent Contact Absorber (TCA)
                                     • Venturi followed by a spray tower
                                     • Marble-Bed Absorber
                                     The TCA, manufactured by Universal Oil
                                  Products, uses a fluidized bed of low-density
                                  plastic spheres that are free to move between
                                  retaining grids.  The venturi, manufactured by
                                  Chemical  Construction Co., contains an adjust-
                                  able throat that permits control of pressure
                                  drop under  a wide range of flow conditions.
                                  Although a venturi is ordinarily  an effective
                                  particulate removal device, gas absorption is
                                  limited in lime/limestone wet-scrubbing systems
                                  by low slurry residence time. For this reason,
                                  the spray tower was included for additional
                                  absorption capability.  The Marble-Bed Absorber,
                                  manufactured by Combustion Engineering Co.,
                                  uses a packing of 3/4-inch  glass  spheres (marbles).
                                  Because of operating problems with the Marble-
             GASOUT
   WASH LIQUOR
 INLETWASH
 TRAY LIQUOR '

 WASH LIQUOR
   RETAINING
     GRIDS
                     0°0o
 0_ _pC_ c

 n 00 Co
,_£.-£ -0
       G.45 //V I
            CHEVRON MIST
             ELIMINATOR

            WASH TRA Y

             EFFLUENT WASH
              TRAY LIQUOR

              INLET SLURRY
                                                                              GASOUT
     MOBILE
'PACKING SPHERES
                               APPROX. SCALE
               EFFLUENT SLURRY
Figure 1.  Schematic of Three-Bed  TCA
                                                        CHEVRON MIST
                                                         ELIMINATOR
                                                         SPRAY
                                                         TOWER
                                                    INLET
                                                   SLURRY
                                                           WASH LIQUOR

                                                           WASH LIQUOR
                                                    ADJUSTABLE
                                                       PLUG
                                    VENIURI SCRUBBER    ~m~      APPROX. SCALE

                                                   EFFLUENT SLURRY

                                  Figure 2.  Schematic of Venturi/Spray Tower

-------
 Bed Absorber (i.e., nozzle failure and subsequent
 plugging of the  bed), testing was discontinued on
 this system early in the program.  Combustion
 Engineering has since developed an advanced
 Marble-Bed Absorber which has been operating
reliably in  full-scale  commercial service at other
locations.  Figures 1 and  2, drawn roughly to
scale, show the TCA and  the venturi/spray tower,
along with  the mist  eliminators selected for de-
entraining slurry in the gas streams.
                   __gg-_.
                              " t
                      /'  X    Kt HI 1 ff
 Figure 3,  EPA  Test Facility — Typical Process Flow Diagram for TCA System in Limestone Service
                                                                         GASSTRtAM

                                                                         I/QI'OK \IREAV   SETTLIHG TO.VO
Figure 4.  EPA Test Facility -  Typical Process Flow Diagram for Venturi/Spray Tower System
          in Lime Service

-------
   The test facility was designed to allow a num-
ber of different scrubber internals and piping con-
figurations to be used  with  each scrubber system.
For example, the TCA can  be operated as a one-,
two-,  or three-bed unit, and solids separation can
be achieved with a clarifier  alone or with a clari-
fier in combination with a filter or a centrifuge.
   A typical TCA system configuration  used dur-
ing limestone testing and a  typical venturi/spray
tower system configuration  used during lime
testing are shown in Figures 3 and 4, respectively.
Process details, such as flue gas cooling sprays,
are not shown.
   For all configurations, gas is withdrawn from
the boiler ahead of the power plant particulate
removal equipment so  that  entrained fly ash can
be introduced into the scrubber.  The gas flow
rate to each scrubber is measured by venturi
flow meters and controlled  by dampers on  the
induced-draft fans.  Concentration of SC>2 in the
inlet and outlet gas is  monitored continuously by
Du Pont photometric analyzers.  Inlet and outlet
gas particulate concentrations are measured
periodically using a modified EPA particulate
train.
   Control of the scrubbing  systems  is carried
out from  a central graphic panelboard.  An elec-
tronic data acquisition system is used to record
the operating data.  The system is hard-wired
for data output directly on  magnetic tape, and
on-site display of selected information is avail-
able.  Important process control variables are
continuously recorded, and  trend recorders are
provided for periodic monitoring of selected data
sources.
   Views of the scrubber structure, TCA, spray
tower, and control room are shown  in Figures
5, 6,  7, and 8, respectively.
                                                  Figure 5.  Scrubber Structure

-------
 Figure 6.  TCA  with View of Fluidized Spheres
          during Air/Water Tests
Figure 7. Inspect/on of Spray Tower
Figure 8. Control Room

-------
  The following sequential test blocks were estab-
lished for the test program:
  (1)  Air/water tests
  (2)  Sodium carbonate tests
  (3)  Limestone wet-scrubbing tests
  (4)  Lime wet-scrubbing tests
  The test program schedule from March 1972
through December 1974 is shown in Figure 9.
Detailed  test results have been presented in EPA
Progress  Reports  EPA-650/2-73-013 and
EPA-650/2-74-010. A third report  will be issued
in mid-1975.

AIR/WATER TESTS

  These  experiments, which used air to simulate
flue gas and water to  simulate alkali slurry, were
designed  to  determine pressure drop model
coefficients  and  to observe fluid hydrodynamics
for  all three scrubbers under clean conditions.

SODIUM CARBONATE TESTS

  These  tests, which  used sodium carbonate
solutions to absorb SO2 from  flue gas, were
designed  to  determine coefficients within mathe-
matical models for predicting SC>2 removal.

LIMESTONE WET-SCRUBBING TESTS

  The objectives of these tests, in which lime-
stone (CaCO3) slurry  was fed  to the scrubber
circuit were:
  (1)  To determine  the effect of important
       variables on particulate and  SO2  removal
  (2)  To identify and resolve operating prob-
       lems, such as scaling and mist eliminator
       plugging
  (3)  To identify regions of reliable operation
       of the  three scrubber systems, consistent
       with reasonable SO2 removal, and to
       choose economically attractive operating
       configurations from  within these  regions
  (4)  To establish long-term operating reliability
       for one or more of the scrubber systems
       and  to develop definitive process econom-
       ics data and scale-up factors
  A large number of  short-term limestone fac-
torial tests,  of about 4 hours each,  were  made  on
each scrubber system  to accomplish the first
objective. The major independent variables were
gas rate,  liquor rate, scrubber inlet liquor  pH, and
number of grids and height of spheres in the TCA.
The results of these tests and of the air/water and
sodium carbonate tests are reported in EPA Tech-
nology Transfer Capsule Report No. 4.
   A relatively small number of longer term lime-
stone reliability verification tests, of about 3
weeks per test, were made on each scrubber sys-
tem to accomplish the second and third objectives.
In these  tests, the dependent variable was the scal-
ing and plugging potential of the scrubber  inter-
nals, and the major independent variables  were
gas rate,  liquor rate, scrubber inlet slurry pH,
effluent residence time, solids concentration  in
the scrubber recirculation  slurry, and  solids
concentration in the discharge sludge.  The results
of these  tests are reported in Section  4.
   Long-term limestone reliability tests, of  up to
3 months in duration, were run  on  the TCA sys-
tem to accomplish the fourth objective.  The
results of these tests are reported in Section  5.

LIME WET-SCRUBBING TESTS

   The objectives of this test  sequence, in  which
hydrated lime (Ca(OHJ2) slurry  was fed to the
scrubber  circuit, were identical  to those for the
limestone wet-scrubbing sequence just described.
Originally, the  testing was to be divided into the
same three categories:  (1) short-term factorial
tests,  (2) longer term reliability verification  tests,
and (3)  long-term reliability tests.  Subsequently,
it  was decided  to begin  the lime testing with
long-term reliability tests on the venturi/spray
tower system and to perform the factorial  and
reliability verification tests at a later date  (after
December 1974).  The results of the long-term
reliability tests on the venturi/spray tower system
are reported in Section 6.

ANALYTICAL PROGRAM

   Samples of slurry, flue gas, limestone, and coal
were taken periodically  for chemical analyses,
particulate size sampling, and limestone reactivity
tests.  Locations of slurry and gas sample  points

-------
for the TCA and venturi/spray tower systems
are shown in  Figures 3 and 4.
   To meet the formidable analytical  requirements
of the facility at reasonable costs, equipment was
selected to minimize manpower.  For example,
an X-ray fluorescence unit was used for compre-
hensive slurry analyses.  All analytical computa-
tions and recording of results were handled by
an on-site minicomputer.
   TESTS
     fHfr
     R*bataf»f¥
         w%fettf|fie$j|
 Figure 9. Shawnee Test Schedule

-------
  The primary objectives of the  limestone relia-
bility verification tests were to identify and
resolve operating problems and to identify re-
gions of reliable operation of the three scrubber
systems.   Emphasis,was placed on solving the
problem of scaling of scrubber internals.  The
reliability  verification tests averaged approx-
imately 500 hours (3 weeks) each.

SCALING OF SCRUBBER INTERNALS

  The rate of scaling of the scrubber internals
was found to be sensitive to the  supersaturation
of the calcium sulfate  (gypsum)  in the circulat-
ing scrubber liquor.  Results of the limestone
reliability  verification tests showed that scrub-
ber internals can be  kept relatively free of scale
if the sulfate saturation is kept below about 135
percent at 50°C (i.e., below 35 percent super-
saturation).
  The limestone tests  showed  that, generally,
the sulfate saturation in the scrubber liquor de-
creases (i.e., scaling potential  decreases) with
(1) increasing slurry effluent residence time,
(2) increasing solids  concentration  in the scrub-
ber slurry, (3)  decreasing solids  concentration
in the discharge sludge,  (4) increasing scrubber
slurry pH, and  (5) increasing liquid-to-gas ratio.
   Figure  10 shows the sulfate saturation of the
scrubber liquor  as a function of  slurry solids
concentration and effluent residence  time for
the TCA  reliability verification tests.  All these
tests were operated in closed liquor loop.   In
these tests, the  slurry  pH ranged from 5.2 to
6.1,  tending to  increase with  increasing slurry
effluent residence time.  Included are two data
points from TCA long-term reliability runs at
10 and 15 minutes residence time.
   As seen in Figure 10, the sulfate saturation of
the scrubber slurry was 190 percent  at 4.4 min-
utes effluent residence time and  8 percent slurry
solids concentration.  Severe sulfate  scaling of
the bottommost TCA  grid occurred  under these
conditions after 500 hours of operation.  At 20
minutes residence time and 15 percent slurry
solids concentration, the  sulfate  saturation  was
about 110 percent, and no significant scaling of
 the TCA grids occurred after 500 hours of opera-
 tion.  In the reliability test at 10 minutes resi-
 dence time and 15 percent slurry solids concen-
 tration, sulfate saturation was about 130 percent,
 and less than 15 mils of sulfate  scale formed on
 the bottommost TCA grid after 1200 hours of
 operation.
   The calcium sulfate (gypsum) saturations of
 the scrubber liquors  were obtained with the use
 of a chemical  equilibria computer program.  Using
 laboratory-measured  liquor compositions, the equi-
 libria  program calculates the activities of the cal-
 cium  and sulfate ions. The  degree of saturation
 is equal to  the product of the activities divided
 by the solubility product of calcium sulfate at
 the specified  temperature. Calculations of sulfate
 saturations in  this  report were based on a solu-
 bility  product for CaSO4 • 2H2O of 2.2 x
 TO'5 gmole2/liter2 at 50°C.
          \
                  SPtKCENI SLURRY
                  SOLIDS CONCENTRA TION
        LIQUID-rO-C^AS RAIIO = 60-75 GAI /MCF
        PERCENT SOLIDS DISCHARGED^ ^S
              I
                       I
                               I
              5       10        15       20

              SLURRY Et I LUENT RESIDENCE TIME, MIN
Figure 10.   Effect of Effluent Residence Time and
            Slurry Solids Concentration on Sulfate
            Saturation for TCA Limestone Tests

-------
                                                         §
                                                   tf®a
  The  major objective of the limestone reliability
tests was to demonstrate long-term  (2 to 5
months) operability of the TCA system, with
emphasis on mist elimination and scrubber
internals.  This was achieved in TCA Run  535-2,
terminated in December 1974,  which  ran with
little scale and an  essentially clean mist eliminator
over a  3-month operating period (2325 hours on-
stream).  A summary of the operating conditions
for  this run is given in Table 1.

MIST ELIMINATION SYSTEM

  The  TCA mist elimination system consists of a
six-pass, closed-vane,  stainless-steel,  chevron mist
eliminator preceded by  a wash  tray (Koch Flexi-
tray). (See Figure  1.)
  The  underside of the mist eliminator was
sprayed continuously (0.3 gpm/ft^) with clarified
liquor diluted with makeup water.
  A 2-inch depth  of liquor on  the wash tray
(0.5 gpm/ft^ combined  rate from mist eliminator
sprays  and additional clarified liquor)  was used  to
intercept the solids in the entrained mist.  En-
trained droplet solids concentration was reduced
from 15 wt % to less than 0.5 wt %.
  Initially in Run 535-2,  the underside of the
wash tray was intermittently steam  sparged (125
psig, 1  minute/hour).  At  2000 hours, the steam
sparge was replaced by a continuous underside
spray (0.3 gpm/ft^) using wash tray effluent
liquor.
  A view of the  top of the wash tray and under-
side of the mist eliminator after 1350 hours of
TCA Run 535-2  is shown  in  Figure 11.  It ap-
pears that this mist elimination system can  be
operated for a year or more at the  run condi-
tions tested.
  Future plans include testing the TCA mist
elimination system  (1) at increased gas velocity
(10 and 12 ft/sec)  and (2) with the wash tray
removed.


SCRUBBER INTERNALS

  As demonstrated during limestone reliability
verification testing, scrubber internals can be
                                           Table 1
                OPERATING CONDITIONS FOR TCA RELIABILITY RUN 535-2
         Operating Time, hr
         Gas Velocity, ft/sec
         L/G, gal/mcf
         Pressure Drop (including Mist Elimination System), in. H2O
         Slurry Soiids Concentration, percent
         Effluent Tank Residence Time, min
         Inlet SO2 Concentration, ppm
         Percent SO2 Removal (controlled)
         Scrubber InJet Liquor pH
         Percent Limestone Utilization (100 x moles SO2
           absorbed/moles CaCO3 added)
         Percent Sulfate Saturation @ 50°C
         Percent Oxidation of Suffite to Sulfate
         Percent Solids in Discharge Cake
         Dissolved Solids, ppm
                             2325
                              8.6
                               73
                              6.5
                            12-15
                               15
                       2000-4000
                            75-88
                           5.7-6.0

                               65
                              110
                            10-28
                            35-42
                             6000

-------
kept relatively free of scale if the sulfate (gyp-
sum) saturation of the scrubber liquor is kept
below about 135  percent.  For TCA Run 535-2,
the sulfate saturation of the scrubber slurry was
110 percent, and  less than 20 mils of sulfate
scale formed on the bottommost TCA grid during
2325 hours of operation.  This scale growth rate
would not interfere with  normal  scrubber opera-
tion over a 1-year operating period.  Figure 12
shows the bottom bed of the TCA after 1350
hours of Run 535-2.
   Until  recently,  the operating life of the 1]/2-
inch-diameter, 5-gram  plastic spheres has been a
significant limiting factor in the long-term relia-
bility  of the TCA scrubber.  High-density
 polyethylene (HOPE) spheres had an operating
 life of about 2000 hours before eroding through
 and filling with slurry.  Thermoplastic rubber
 (TPR) spheres showed a weight loss of only  6
 percent  after 2500 hours.  The TPR spheres  tend
 to dimple, however, and can slip through the
 supporting bar-grids presently used in  the TCA.
 This can be  corrected  by respacing the bar-grids.
   There has been no evidence of significant  ero-
 sion of the bar-grids in the TCA after more than
 5000 hours of operation.  The original wire
 mesh grids deteriorated during approximately
 3000 hours of operation owing to vibrational
 wear at  the points of contact.
Figure 11.  Wash Tray and Mist Eliminator after
           1350 Hours of Operation during TCA
           Reliability Run 535-2
Figure 12.  Internal View of TCA Showing Bottom
           Support Grid and Spheres A fter 1350
           Hours of Operation during TCA
           Reliability Run 535-2

-------
  The major objective of the lime reliability
tests was to demonstrate long-term (2 to 5
months) operability of the venturi/spray tower
system, with  emphasis on mist elimination and
scrubber internals.  A successful run of long-
term duration has not yet been achieved  because
of scale formation on the spray tower mist
eliminator.

MIST ELIMINATION SYSTEM

  The spray  tower  mist elimination system con-
sists of a three-pass, open-vane, stainless-steel,
chevron mist eliminator  which has provision for
underside  and topside washing (see Figure 2).  In
tests of this system  at a superficial gas velocity of
6.7 ft/sec  and 8 percent slurry solids concentra-
tion, scale formation on the top mist eliminator
vanes (of  TOO to  200 mils/month) has been a
constant problem.  A variety of washing configu-
rations have been tried in order to alleviate this
problem.
  Underside washing only, either continuously
with low-pressure water at 0.3 gpm/ft^ or
intermittently  with high-pressure water at 3
gpm/ft^ (9 minutes every  4 hours at 45 psig),
was unsuccessful in eliminating scale formation
on the top vanes.
  A combination of topside and bottomside
washing was studied during venturi/spray tower
Runs 609-1 and  610-1.  A summary  of the oper-
ating conditions  for these  runs is given in Table 2.
The  entire underside of the mist eliminator and a
small area of the topside (14 ft^) were washed
intermittently  (8 minutes  every 4 hours) at high
pressure (45 psig) with makeup water at a rate
of 2.7 gpm/ft^ for the underside and 1.0 gpm/
ft^ for the topside.  At the termination of these
runs, after 530 operating hours, the washed area
was essentially clean, with less than 1 mil of
solids accumulation, compared with an average
of 70 mils scale buildup on the rest of the top-
side  surfaces.  Figure 13 shows the topside  wash
nozzle and the relatively clean mist eliminator
                                             Table 2
                   OPERATING CONDITIONS FOR VENTURI/SPRAY TOWER
                             RELIABILITY RUNS 609-1 AND 610-1

-------
surface  beneath it.  It is anticipated that the
chevron mist eliminator can be operated for a
year or more with underside and topside wash-
ing at the run conditions tested.
   Carryover of water from the topside sprays
caused reheater overloading during the runs.
This problem might be reduced  by a sequential
sectional topside  wash or by the use of a second
mist eliminator to catch  the entrainment from
the topside sprays.  These concepts will be
studied  during  future testing.

SCRUBBER INTERNALS

   As with limestone, the lime reliability tests
ha-ve shown  that scrubber internals can be kept
relatively free of scale if the sulfate (gypsum)
saturation of the scrubber liquor is kept below
about 135 percent.  Again, this  can  be accom-
plished  with increased slurry solids concentra-
tion and/or with  increased  effluent residence
time.  The lime system  was found to  differ
 from limestone, however, in that sulfate satura-
 tion of the scrubber liquor is a strong function
 of inlet gas SC>2 concentration  (i.e., SC>2 ab-
 sorption  rate).
   The lime reliability tests have also shown that
 severe scale formation within the spray  tower
 does not necessarily limit scrubber operability.
 Figure 14 shows a view  of the spray tower
 internals (looking upward) after approximately
 1 month of operation at a scrubber liquor sulfate
 saturation of 180 percent. The  white gypsum
 scale on the scrubber internals did not noticeably
 interfere  with the spray  tower operation.
   Initially, nozzles  in the spray  tower frequently
 plugged,  but dual strainers installed in the circu-
 lating slurry lines greatly reduced this problem.
 Stainless-steel spiral-tip nozzles  were badly eroded
 after about 4300 hours  in service. Stellite-tipped
 nozzles have shown no measurable signs of erosion
 after approximately 4000 hours in service.
Figure 13.  Topside of Spray Tower Mist Eliminator
           at Conclusion of Runs 609-1 and 610-1
Figure 14.  Spray Tower Internals Showing Gypsum
           Scale after One Month of Operation at
           180 Percent Sulfate Saturation

-------
   This section  highlights the operating experience
during both lime and limestone  wet-scrubbing
tests at the Shawnee facility.  Mist elimination
systems and scrubber internals have been dis-
cussed previously and will not be described in
this section.

CLOSED  LIQUOR LOOP OPERATION

   Most commercial scrubber systems are required
to maintain a closed liquor loop.  A closed
liquor loop is achieved when the raw water input
to the system  is equal  to the water normally
exiting the system in the settled sludge and in
the humidified  flue gas.  For lime/limestone wet-
scrubbing systems, the solids concentration in the
settled sludge is normally equal to or greater than
38 percent by weight.
   Scaling potential is significantly affected by the
quantity of raw water  makeup, and meaningful
reliability data  can be obtained only by  operating
with a closed liquor  loop.  Because of excess
water input, closed liquor loop operation was
not achieved early in the test  program during
limestone factorial testing.  Sources of excessive
water included  pump seal water, flue gas
presaturation sprays, and water in the 10 to 20
wt % limestone slurry feed.  To reduce water
input, water seals were converted to air  purge,
slurry was substituted for water on the pre-
saturation sprays, and the slurry feed concentra-
tion  was increased to 60 wt % solids.  As a
result of these modifications, all testing  in both
lime and limestone systems has been in closed
liquor loop operation since March 1973.

HOT-GAS/LIQUID INTERFACE

   During  the limestone reliability verification
testing,  there was a continual  problem of soft
solids buildup  at the hot-gas/liquid  interface in
the TCA scrubber inlet duct, where the hot flue
gas is cooled by slurry  sprays  to protect the
vessel's rubber linings.  The  problem was solved
by selecting the proper size, location, and
orientation of the slurry spray nozzles and by
soot blowing in the direction of the flue gas
flow only.
  The venturi scrubber is an extremely reliable
gas-cooling device and does not require  presatu-
ration sprays.
REHEATERS

   Fuel-oil-fired reheaters with external air supply
and direct combustion in the flue gas stream were
originally installed on the scrubber systems.  They
were hard to start, had frequent flame-outs, and
generated considerable soot.  Field modifications
to provide an isolated combustion zone and instal-
lation of mechanical atomizing nozzles improved
combustion,  but burner flame-out continued to
be a problem.
   A fuel-oil-fired external combustion reheat sys-
tem was installed on the venturi/spray tower sys-
tem in March 1974.  This unit has performed
satisfactorily with high reliability for  over 4000
operating hours.

FANS

   Erosion, corrosion, pitting, scaling, etc., have
been negligible on all three fans.  Operation has
been with 125°F flue gas reheat  to give a fan
inlet temperature of 250°F.

PUMPS

   The major pumps used  in alkali slurry service
at the Shawnee test facility are rubber-lined
variable-speed centrifugal pumps.   In general, the
rubber linings have shown excellent erosion-
corrosion resistance and have remained in good
condition.  The original pumps had water-sealed
packing, but were converted to air-purged pack-
ing during a boiler outage in  February 1973.

LININGS

   The neoprene rubber linings on the agitator
blades and in the spray tower, TCA, process water
hold tanks, pumps,  and circulating slurry piping
have usually  been found to be in  excellent con-
dition, except for slight wear on some of  the
rubber-coated agitator blades.  Hairline cracks
have been noted in  the glass flake lining on the
effluent hold tanks  and clarifiers, but the  cracks
did not appear to penetrate the entire thickness
of the lining.

WASTE SOLIDS HANDLING

   The  test facility is equipped to study alterna-
tive methods of waste solids dewatering and dis-

-------
posal.  Separate clarifiers are provided for each
scrubber system. A belt-type rotary-drum  vacuum
filter and a horizontal solid-bowl centrifuge are
common to  the three systems.
  The venturi/spray tower system has a 20-foot-
diameter clarifier, while the TCA unit is 30 feet
in diameter.  The solids concentration in the
underflow of the larger TCA unit has approached
the  expected final settled  sludge concentration
(approximately 38 wt %), but the underflow
from the smaller unit has  averaged only about
25 wt  %.  To achieve closed  liquor loop opera-
tion, the smaller clarifier has to be  used in series
with the filter or centrifuge.
  Under normal operations,  the belt-type rotary-
drum  vacuum filter produces a filter cake con-
taining 50 to 55 wt % solids from limestone and
45 to 50 wt %  solids from lime slurries. Filter
operation has been  significantly hampered  by
the  short life (usually less than 260 hours) of
the  filter cloth.
  The continuous solid-bowl centrifuge produced
a cake with  55  to 65 wt % solids from limestone
slurry, and the  centrate solids averaged 0.5 to 1.0
wt %.  However, erosion made a major repair of
the  unit necessary after about  1400 hours  of
operation.  It was concluded that the centrifuge
was not an acceptable  solids  dewatering device
for  the Shawnee test conditions.

INSTRUMENTS

  Two types of pH meters have been  used in
slurry service:  (1)  in-line  flow-through meters
and (2) submersible electrode meters.  The
performance of the in-line flow-through meters
has been unsatisfactory because of the erosion
and high rate of failure of the  glass cells and the
frequent plugging of the sample lines.  The
submersible electrode meters have been free  of
such problems  during approximately 9000 hours
of operation.
  Operating experience has been obtained with
three  types  of density  meters in slurry service:
(1)  radiation meters, (2)  differential  pressure
(bubbling tube) meters,  and (3) vibrating  U-tube
meters.  The radiation meter has a continual
calibration shift which is accelerated by scale
formation.  The gas line on the differential
pressure meter  plugs frequently and requires
significant maintenance, but the meter is accurate
when clean.  The vibrating U-tube meters were
installed  in September 1973 in two locations.
The  performance of this type  of density meter
has thus  far been encouraging.
   Slurry flow rates have been measured by both
magnetic and differential pressure  (both orifice
and  Annubar) flowmeters.  Performance of the
magnetic flowmeters and the orifice flowmeters
has generally been adequate.   Annubar meters
plugged frequently and  required excessive
maintenance.
   Operating experience with  control valves in
slurry service has generally been unsatisfactory.
Severe erosion and frequent plugging result from
the throttling operation. This has been observed
with stainless-steel plug valves, stainless-steel
globe valves, and rubber pinch valves.  Satisfac-
tory and trouble-free flow control has  been
experienced only with variable-speed pumps.
 For further information:

   Detailed progress reports, EPA-650/2-73-013
 and EPA-650/2-74-010, are available from the
 National Technical Information Service,
 Springfield, Va. 22151.

   A third detailed report is currently being
 prepared.  If you wish to be notified when this
 report is available write:

 Technology Transfer
 Environmental Protection Agency
 Washington, D.C. 20460

-------