United States
            Environmental Protection
            Agency
Office of
Emergency and
Remedial Response
EPA/ROD/R06-87/015
November 1986
&EPA     Superfund
            Record of Decision:
   \
              Mid-South Wood, AR

-------
                                    TECHNICAL REPORT DATA
                             (Please read Instructions on the reverse before completing}
 1. REPORT NO.
[EPA/ROD/R06-86/015
                                                             3. RECIPIENT'S ACCESSION NO.
 14. TITLE AND SUBTITLE
 SUPERFUND RECORD  OF DECISION
 Mid-South Wood  Products,  AR
 First Remedial  Action
                                                            5. REPORT DATE
                                                                      November 14. 1986
                                                            «. PERFORMING ORGANIZATION CODE
 7, AUTHOR(S)
                                                             8. PERFORMING ORGANIZATION REPORT NO
 9. PERFORMING ORGANIZATION NAME AND ADDRESS
                                                             10. PROGRAM ELEMENT NO.
                                                              1. CONTRACT/GRANT NO.
 12. SPONSORING AGENCY NAME AND ADDRESS
 U.S. Environmental  Protection Agency
 401 M Street,  S.W.
 Washington, D.C.   20460
                                                            13. TYPE OF REPORT AND PERIOD COVERED
                                                              	Final ROD Report
                                                            14. SPONSORING AGENCY COOE

                                                                      800/00
 IS. SUPPLEMENTARY NOTES
 16. ABSTRACT                                           	~~~~——	————————.
    The Mid-South  Wood Products site is located  in  Polk County, Arkansas, approximately
 1/2 mile southwest  of Mena, Arkansas.  The 57-acre site includes the following  areas:
 the Old Plant site,  the Small Old Pond and Old  Pond areas, the North and South
 Landfarms, the  landfill, Clear Lake and an existing chromated copper arsenate  (CCA)
 treatment plant.  The Old Plant site was used to treat wood with pentachlorophenol  (PCP)
 and creosote; the Small Old Pond was the original  impoundment for waste PCP and
 creosote.  These  two areas have been covered with  soil.  The Old Pond area  was  used  to
 store PCP and creosote sludge and has since been graded and covered with soil;  materials
 from the Old Pond were spread over the Landfarm areas and mixed into the soil;  the
 Landfill area contains deposits of sawdust, woodchips, and other waste wood products;
 Clear Lake receives  runoff from all the above areas;  the CCA treatment plant contains  an
 ongoing wood treating operation where the surface  drainage from the plant is put  in
 sumps.
    The plant site was originally developed by a lumber company in the late  1930s  as  a
 post and pole production plant.  In 1967, Edward Hines Lumber Company purchased the
 plant and operated  it as a PCP and creosote wood treating plant until 1977  when the  CCA
 treating process  was first introduced at the plant.   In September 1978, Edward  Hines
 Lumber Co. sold the  plant to Mid-South Wood Products,  Inc. Investigation of the
 ISee Attached Sheet)
17.
                                KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.IDENTIFIERS/OPEN ENDED TERMS C.  COSATI Field/Group
 Record of Decision
 Mid-South Wood Products,  AR
 First Remedial Action
 Contaminated Media:  sw,  gw, surface soils,
  surface sediments
 Key contaminants: creosote compunds (PAHs),
  PCP, CCA, arsenic,  chromium
18. DISTRIBUTION STATEMENT
                                               19. SECURITY CLASS (Tins Report/
                                                         None
                                                                          21. NO. OF PAGES
                                                                                    73
                                               20. SECURITY CLASS (Tllispage!

                                                         None
                                                                          22. PRICE
EPA Form 2220-1 (R«v. 4-77)   PREVIOUS COITION i» OBIOLCTE

-------
EPA/ROD/R06-86/015
Mid-South Wood Products, AR
First Remedial Action

16.  ABSTRACT (continued)
Mid-South Wood Product site began in 1976 when several fish kills were
reported in waterways downstream of the site.  The Arkansas Department of
Pollution Control and Ecology (ADPC&E) tested the ground water, surface
water, ponds, and three wells; they found low levels of PCP in the wells and
higher levels in the surface water samples and arsenic and chromium in the
ground water and surface water.  In December 1981, ADPC&E concluded that a
contamination problem existed and recommended initial remedial actions be
taken.  Contaminants were found in the site surface soils, surface
sediments, surface water, and ground water beneath the site. The primary
contaminants of concern include:  creosote compounds (PAHs), PCP, CCA,
arsenic, and chromium.
   The selected remedial action includes:  excavation of onsite contaminated
soils, with the exception of those existing in the Old Pond area, and
consolidation with the contaminated soils in the North Landfarm area;
stabilization of any free oil, liquid, or sludge found in the heavily
contaminated area of the Small Old Pond/Old Plant area and placement of
these wastes in the North Landfarm area; grading and covering the
contaminated soils consolidated in the North Landfarm and RCRA top-soil clay
cap; investigating the Old Pond area to locate any free oil, liquids, or
sludges and in-situ stabilization of these materials; capping the Old Pond
area with a RCRA top-soil clay cap; remedial action at the CCA treatment
facility; completing installation of the french drain system at the site and
pumping water to the treatment system; treating the ground water by removing
organics through carbon filtration (any ground water found to be
contaminated with inorganics will be treated by carbon filtration then used
as makeup water for the CCA treatment facility); disposal of oils and
sludges collected in the french drains in an EPA approved hazardous waste
disposal facility; discharging treated water from the ground water treatment
facility to surface drainage; and installation of a ground water monitoring
system.  The estimated capital cost is approximately $3,500,000 with annual
O&M costs of $153,500.

-------
 j^  '«v
 J* — '*
f A \    UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
        *                             REGION VI
       ?                          12O1 ELM STREET
                                DALLAS, TEXAS 7S27O


                               RECORD OF DECISION
   SITE

   Mid-South  Wood  Products  located in Polk County, Arkansas, approximately
   1/2 mile southwest  of Mena, Arkansas.
   DOCUMENTS  REVIEWED

   I  am basing  my decision on the  following documents describing the analysis
   of cost-effectiveness  of  remedial  alternatives for the Mid-South Wood
   Products site:

   B&F Engineering,  Inc., 1984.  Phase I and II Report Site Investigation,
   Mid-South  Wood Products,  Inc.   Prepared for Edward Nines Lumber Company.

   B&F Engineering,  Inc., 1983.  Phase I Report Site Investigation, Mid-South
   Wood Products, Inc.  Prepared for  Edward Mines Lumber Company.

   Environmental Protection  Agency, 1986.  Feasibility Study Report, Mid-South
   Wood Products Site,  Mena, Arkansas.  Prepared by CH2M Hill Southeast, Inc.

   Environmental Protection  Agency, 1986.  Supplemental Remedial Investigation
   -  CCA Plant, Mid-South Wood Products Site, Mena Arkansas.  Prepared by
        Hill  Southeast, Inc.
   Environmental Protection Agency, 1985.  Endangerment Assessment, Mid-
   South  Wood  Products  Site,  Mena, Arkansas.  Prepared by Q^M Hill Southeast,
   Inc.

   Environmental Protection Agency, 1984.  Remedial Investigation Report,
   Mid-South Wood  Products Site,  Mena,  Arkansas.  Volumes 1, 2, and 3.
   Prepared by  Soil 4 Materials Engineering, Inc. and CH2M Hill Southeast,
   Inc,

   Law Engineering Testing Company, 1984.  Phase II Hydrogeologic Investigation,
   Mid-South Wood  Products Site,  Mena,  Arkansas.  Prepared for Edward Hines
   Lumber Company.

   Law Engineering Testing Company, 1983.  Phase I Hydrogeologic Investigation,
   Mid-South Wood  Products Site,  Mena,  Arkansas.  Prepared for Edward Hines
   Lumber Company.

   0   Summary  of Remedial Altenative Selection.

   0   Public comments received during April 28 - May 19, 1986, on the Feasibility
      Study.

   0   Community Relations Responsiveness Summary, November 1986 (attached).

-------
                Summary of Remedial Alternative Selection
                         Mid-South Wood Products
                              Mena, Arkansas
                               October 1986
                            TABLE OF CONTENTS
Site Location and Layout	 1
Si te Hi story 	4
Site Status 	 5
Nature and Extent of Contamination 	 10
Enforcement 	 19
Alternatives Evaluation Summary	21
Community Relations 	 53
Remedy 	54
Schedule 	57

-------
                       MID-SOUTH WOOD PRODUCTS SITE
                            RECORD OF DECISION
                              NOVEMBER 1986
ERRATA
The figures used in this document to illustrate the  site depict the
site boundaries incorrectly.  Edward Hines  Lumber  Co.,  Inc.  (potentially
responsible party) has recently purchased a tract  of  land that previously
bordered the site along the southwest property  line.  Therefore, contamin-
ated soil  and groundwater considered offsite during  the development of the
feasibility study and located in this southwestern drainageway is now
part of the site (i.e., the site boundaries have been extended to the
southwest to include all offsite contamination  found in that  area during
site investigations).

-------
 SITE LOCATION AND LAYOUT

 The Mid-South Wood Products site is located in western Arkansas,  approximately
 1/2 mile southwest of downtown Mena, in Polk County (Figure 1).   The
 Mid-South site is comprised of approximately 57 acres.  The northeastern
 half of the site contains an ongoing wood treating operation which  is
 using a chromated copper arsenate (CCA) process.  The current site  layout
 is depicted in Figure 2.

 Areas of remedial investigation for the Mid-South  site include the  Old
 Plant site, the Small Old Pond and Old Pond areas, the North and  South
 Landfarms, the Landfill, Clear Lake and the existing CCA treatment  plant.

 The Old Plant site is where the pressure cylinders used for treating wood
 with pentachlorophenol (PCP) and creosote were located.  The Small  Old
 Pond was the original impoundment for waste PCP and creosote and  is
 located adjacent to the Old Plant.  The Old Plant  site and  Small  Old Pond
 areas occupy approximately 10,000 square feet and  have since been covered
 with soil.

 The Old Pond is an area west of the Old Plant site,  approximately 112,500
 square feet in size, where PCP and creosote sludge were stored before the
 pond was filled in.  The landfarm areas are located  on both sides of a
 ridge running through the southwest part of the plant property.   The area
 south of the ridge is approximately 84,000 square  feet and  drains to the
 south and west.  The area north of the ridge is approximately 150,000
 square feet and drains to the north.  These are areas  on  which material
 from the Old Pond was spread over the surface and  mixed into the  soil as
 part of the Old Pond closure.  Some of the mixture was put  back into the
 Old Pond area.  The Old Pond area has been graded  and covered with  soil.
The Landfarm areas have not been covered.

 The Landfill area is the result of depositing sawdust, woodchips  and
other waste wood products in a swale area to the west  of  the Old  Plant
 and north of the Old Pond.  The swale has been filled to  approximately
the surrounding grade and has no vegetative cover.   In 193U,  Mid-South
 constructed a dike across the lower end of the landfill to  contain  runoff
which in turn created a small  area of ponded water called Clear Lake.
 Clear Lake apparently receives runoff from the Landfill,  the Old  Plant
and Small  and Old Pond areas.

The existing CCA treatment plant is  located adjacent  to the Old Plant
 Site.  It consists of a pressure-treating cylinder,  several  elevated
tanks for storage of the treatment solution, a concrete drip  pad  and a
 wood drying kiln.  Thf concrete drip pad is used to  collect excess  CCA
solution which 1s allowed to drip onto the structure  after  treatment.
 Once the lumber has dried, it is stored in an area located  in the
northeastern section of'the site.  Some surface drainage  from the CCA
 plant area  is contained by either concrete-lined sumps at the drip  pad or
an unlined  overflow sump adjacent to the treatiny  cylinder.

-------
             DESCRIPTION OF THE REMEDY

             The Feasibility Study evaluated alternative treatment technologies including
             Incineration and biological treatment.  These technologies were not retained
             due to engineering impracticability (a detailed discussion can be found
             1n the Summary of Remedial Alternative Selection).

             EPA has negotiated a remedy with the potential responsible parties which
             Includes a remedial action plan summarized below.

             0 Excavation of on-site contaminated soils, with the exception of those
               existing in the Old Pond area, and consolidation with the contaminated
               soils in the North Landfarm area.

             0 Stabilization of any free oil, liquid, or sludge found in the heavily
:               contaminated area of the Small Old Pond/Old Plant area and placement
               of these wastes in the North Landfarm area.

             0 The contaminated soils consolidated in the North Landfarm will be graded
               and covered with a RCRA top-soil clay cap.

I           •  ° Field investigation Into the Old Pond area to locate any free oil,
:               liquids or sludges.  Insitu stabilization of these materials.

             0 The Old pond area will be covered with a RCRA top-soil clay cap.

             0 Remedial action at the CCA treatment facility.
9

•             * Complete Installation of the french drain system already partially
>               Installed at the site and pump water to the treatment system.
                                                                              \
             0 Treat the ground water by removing organics through carbon filtration.
               Any groundwater found to be contaminated with Inorganics will be treated
               by carbon filtration then used as makeup water for the CCA treatment
[               facility.

             0 Dispose of oils and sludges collected 1n the french drains 1n an EPA
               approved hazardous waste disposal facility.

             0 Discharge treated water from the groundwater treatment facility to
               surface drainage..
                               i
             0 Installation of a groundwater monitoring system to monitor the effective-
               ness of the remedy.

             Selection of this remedy is contingent upon the responsible parties
             performing bench studies during the remedial design and providing EPA
             with  results that support the use of stabilization as part of the remedy.
             If stabilization proves ineffective, an alternative action will be  required
             for those wastes for which stabilization has been proposed.

-------
DECISION

Consistent with the Comprehesive Environmental  Response, Compensation,
and Liability Act of 1980 (CERCLA) and the National  Oil  and Hazardous
Substance Contingency Plan (40 CFR Part 300),  I select the remedy described
above for the Mid-South Wood Products site.  I have  determined that this
1s cost-effective and is protective of public  health and welfare and the
environment.  The action will require operation and  maintenance to maintain
the effectiveness of the remedy.  Since wastes will  be left on-site, the
remedial action will be reviewed every five years to assure that the remedy
1s still protecting public health and the environment.  The State of
Arkansas has been consulted on EPA's remedy (I.e., Combined Excavation
and Groundwater Recovery/Treatment) which was  the basis  for the negotiated
remedy, and provided verbal concurrence.  I have considered the cleanup
standards of Section 121 of the Superfund Amendments and Reauthorization Act
of 1986 (SARA), Including the cleanup standards thereof, and certify that
the portion of the remedial action covered by  this Record of Decision
complies to the maximum extent practicable with Section 121 of CERCLA
(as amended by Section 121 of SARA).

Negotiations with the potentially responsible  parties have been successful
regarding the selected remedy; however, in the event that negotiations  on
the Consent Decree are unsuccessful, on-going  litigation will  be pursued
by EPA and the Department of Justice in an effort to secure performance
of the remedial action.
                                       V   ^TA^^t^
	                        __^_	'***_ (0
Date                                       Trarices E. Phillips
                                            Acting Regional Administrator

Attachments

-------
SITE HISTORY

The plant site was originally developed by Nebraska Bridge  Supply  and
Lumber Company as a post and pole production plant in the late  1930's.
Nebraska Bridge Supply and Lumber Company, operating under  the  name  of
Three States Lumber Company, installed the first pressure-treating system
1n 1955.

The plant was purchased by Edward Mines Lumber Company 1n 1967.  The
plant was operated as a pentachlorophenol and creosote wood treating
plant by Nines until  1977 when the CCA treating process was first  introduced
at the plant.  Edward Hines Lumber Company sold the plant in September of
1978 and the new owner soon afterwards formed the corporation of Mid-South
Wood Products, Inc.

Since the CCA plant was designed to be a closed loop, recycling system,
and Mid-South Wood Products, Inc., did not plan to use PCP  or creosote in
their operation, the Old Pond was no longer required after  1978, although
some CCA wastewater apparently was put into the Old Pond  during the  first
year of operation.  The pond was reportedly closed by pumping the  sludye
from the pond, spraying it over the Landfarm area, and mixing the  sludge
into the soil.  A portion of the soil  and sludge mixture  was placed  back
into the pond leaving the remaining waste mixture on the  Landfarm  area.
Use of the CCA wood treating process has continued since  1977,  and is
currently ongoing.

The site has been under investigation since 1976, when it was reported
that Rock Creek and the Mountain Fork River suffered a 100-percent fish
kill for a distance of 8 1/2 miles downstream of the site and a 10 percent
fish kill to a distance of 17 1/2 miles downstream of the site.  An
Arkansas Game and Fish officer traced the kill back to the  site, which
was owned and operated at that time by Hines Lumber.  An  8-inch pipe
existed at that time from the Old Pond to the drainage ditch along the
southern boundary of the property.  The drain valve had apparently been
opened and part of the pond contents released.  There is  some indication
from the records that several fisn kills had previously occurred in
waterways downstream of the site, although it is not stated whether  the
cause was traced to the Hines1 property.

Subsequent to the fishkill, state and federal agencies began testing for
the presence of PCP,  arsenic and chromium on private property west and
northwest of the Mid-South site.  Testing was initiated by  the  Arkansas
Department of Pollution Control and Ecology (ADPC&E) in November 1980
with the collection of groundwater samples and sediment samples at and
adjacent to a nearby pond.  Results from these samples revealed the
presence of low levels of PCP, arsenic and chromium in some groundwater
and surface water samples.  In February 1981, water from  four nearby
wells was analyzed by the EPA which reported finding PCP  (10 ppb)  in
one well.  About this same time, the Arkansas Department  of Health tested
water from a pond, spring, and three wells.  The Department of  Health
found trace levels of PCP in the wells and higher levels  in surface  water
samples.  In December 1981, the ADPC4E performed sampling at the Mid-South
site.  They concluded that a contamination problem existed  and  recommended
that initial remedial actions be taken.

-------
 In 1982, the Mid-South Wood Products site was added to the proposed
 National Priorities List under the Comprehensive Environmental  Response,
 Compensation and Liability Act of 1980 (CERCLA or "Superfund").

 On March 31, 1983, ADPC&E issued an Administrative Order,  requiring that
 Mines and Mid-South, as potentially responsible parties (PRPs), perform
 certain short term remedial actions and that they submit a work plan for
 a full investigation of the site to be conducted on a specified schedule,
 On December 17, 1983, the ADPC&E requested that the EPA implement  a
 remedial investigation/feasibility study  (RI/FS) to develop alternative
 remedial actions for the site.
SITE STATUS

In  late 1983, the EPA issued a work assignment  through  its  Zone  II  Superfund
Contract to perform the RI/FS.  Activities of the remedial  investigation
Included collecting and analyzing surface water, groundwater,  surface
soils, subsurface soils, and sediment samples from onsite and  offsite
locations.  Samples were analyzed for semi-volatile organics  (these
Include PCP and primary creosote compounds) and metals  (including arsenic
and chromium).  Data generated by the responsible parties'  consultants
were utilized to the maximum extent possible.

Results of onsite and offsite sampling conducted during the period  January
through April 1984 are discussed in the Remedial  Investigation Report
(EPA, 1984).  In November 1985, a Supplemental  Remedial Investigation
(SRI) of the operating CCA plant area was performed.  Activities of the
SRI included collecting- and analyzing surface and subsurface soils  and
groundwater from the area immediately adjacent  to the CCA plant.  The
results of the study were presented in the Supplemental Remedial Investigation
Report (EPA, 1986).


Physiography

The Mid-South site and City of Mena are located in the  Ouachita Mountains
physiographic sub-province.  Both lie In the Caddo Basin and are bounded
by the Fourche Mountains to the north and the Caddo and Cossatot Mountains
to the south.  The site is located on the northern flank of a  broad
syncline.  Bedrock onsite dips to the southwest and consists predominantly
of shale with occasional sandstone beds.  Residual soils at the site
consist of clayey silts and sands, silty to sandy clays, and some angular
gravel.  The highest point on the site (elevation 1,146 feet msl) is
found in the north-central -area.  Site relief is  approximately 25 feet.

The site's natural topography has been modified by activities  associated
with the wood-treatment processes.  These include the excavation for
waste storage and later filling of the Small Old Pond and Old  Pond  areas,
filling of the Old Plant area, establishment of the Landfill and two
Landfarms for waste disposal, and creation of Clear Lake.

-------
Surface Water Hydrology

Surface water drainage in the vicinity of the site and surface drainage
patterns at the site are shown in Figures 3 and 4.  A drainage divide
(maximum elevation of 1,146 feet) crosses the eastern half of  the  site
1n a northwest to southeast direction passing through the CCA  plant  area.
Drainage east of this divide is via an unnamed tributary and drainage ditch
Into Prairie Creek, a tributary of the Ouachita River.  West of the
divide, most of the site drainage is through Clear Lake, East  Fork Moon
Creek  (which passes through Pope Pond), Moon Creek, Rock Creek, Mountain
Fork River, and eventually into the Little River.   There is  also a diversion
ditch  around the north end of the landfill which intercepts  surface
runoff from the current Mid-South operation before emptying  into East
Fork Moon Creek.  Along the south border of the site, there  is  some
offsite drainage along an ephemeral stream system  which parallels  the
railroad tracks.  Southwest of the topographic divide this stream  system
intercepts site drainage from the South Landfarm area and the  Old  Pond
area (Figure 4), and apparently received waste from the Old  Pond prior
to 1976 or 1977.  East of the topographic divide the stream  system inter-
cepts  runoff from the drip pad, part of the CCA plant and from treated
wood storage areas.


Groundwater Hydrology

Groundwater at the site occurs primarily in weathered bedrock  and  in
fractured sandstone and shales.  Soils onsite have low hydraulic conducti-
vities and limited capacities to transmit water.  A major fracture zone
onsite is* associated with a fault which trends through the site from  west
to cast along the trace of the East Fork of Moon Creek.  This  fault,
named the "anomolous zone" by the Mines' consultants, is characterized by
highly fractured shales and strikes northwest through the site,  underneath
the Old Pond area.  The depth to water in the bedrock varies from  10  to
30 feet below land surface.

Groundwater flows at the Mid-South site are controlled primarily by
topography and follow a pattern similar to that  described for  surface
water  (see Figure 5).  East of the divide, groundwater flows offsite  to
the east and southeast.  West of the divide, groundwater flows  to  the
west, south, and southwest.  Much of it passes through the Landfill  (an
area with high water level), then radially into East Fork Moon  Creek,
Moon Creek, and the Old Pond area.

Beneath the topographic ridge at the Landfarm is a groundwater  high for
the site.  This appears to be a recharge area and  groundwater  flows
radially from this area.  Groundwater on the north side of the  Landfarm
flows to the north to East Fork Moon Creek.  The water table contours
indicate that groundwater is discharging into the  stream. Groundwater
also flows west and south of this divide toward  the drainage feature
paralleling the railroad track to the south and  ultimately discharges
into Moon Creek within one-half mile west of the Mid-South site.

-------
   --—	—  .~f
 s*- ' 0~ —  '^ J•'
    '        -     '
^Oy   V2/
?&&  
-------

-------
rn -<

-------
                                    10

Water Supply

The City of Mena and several of the smaller towns have developed surface
water supplies.  Mena receives its municipal water supply from Ward Lake
and Irons Fork reservoir located approximately 2.5 miles north and 6
miles northeast of the site, respectively.  The two sources are projected
to give Mena a yield of 8.6 million gallons per day.  The remainder of
the rural water supply comes primarily from groundwater, which occurs in
the Paleozoic age bedrock.  These rocks are not a major aquifer and
groundwater is derived principally from the secondary porosity of the
rock.  The quality of the groundwater is considered only fair due to
elevated concentrations of iron and manganese, and it generally requires
treatment for municipal water supplies.

Several private water wells are located around the site.  Recently, Mines
Lumber Company has extended the city water supply pipeline along County
Road 375 to eight homes located downgradient of the Mid-South site that
were previously on private wells.  This action has effectively removed
all known downgradient groundwater usage between the onsite source areas
and the groundwater discharge area along East Fork of Moon Creek.


Cultural
Polk County is a rural county with approximately 65 percent of its population
in rural areas.  Polk County had a population of about 14,800 people in
1975 with the City of Mena being the largest single population center
with about 4,500 people.  The majority (83 percent) of Polk County is
forested and about 15 percent is agricultural land.  There are approximately
720 farms in Polk County with cattle and chickens as the major agricultural
products.


NATURE AND EXTENT OF CONTAMINATION

The Mid-South site 1s the repository for waste products from three
separate wood-preservative processes.  These wastes contain a suite of
creosote compounds (known as polynuclear aromatic hydrocarbons, PAH);
pentachlorophenol, (PCP); and chromated copper arsenate (CCA).

The most commonly detected organic compounds present in samples collected
during the remedial-investigation are listed below:

        Pentachlorophenol                  Chrysene
        Acenaphthene                       Acenaphthylene
        Fluoranthene                       Anthracene
        Naphthalene                        Fluorene
        Benzo(a)anthracene                 Phenanthrene
        Benzo(a)pyrene                     Pyrene
        Benzo(b)f1uoranthene               Dibenzofuran
        Benzo(k)f1uoranthene               2-Methylnaphthalene

-------
                                     11

 The Inorganic contaminants found on the site are arsenic  and  chromium.
 Eight soil  samples from the site were analyzed for dioxln (2,3,7,8  TCDD)
 and none was detected.  Table 1 presents a summary of mean values of  each
 contaminant found onsite and offsite**, listed by sampling media.   Table
 2 presents  similar data on contaminants from near the CCA plant.  A more
 detailed evaluation of contaminants 1s available In the RI Report (EPA,
 1984), the  Endangerment Assessment Report (EPA, 1985), and the  SRI  Report
 (EPA, 1986) for the Mid-South site.

 **  A majority of the property considered offsite during  the  site investi-
     gation  has been purchased by Edward Mines Lumber Co.   The site  boundaries
     have now been expanded to Include this property.  Additionally, a
     portion of the offsite contamination exhibited in Table 1 may now be
     found in this area.

 The majority of the contaminants are associated with the  surface soil and
 subsurface  contamination in the form of oils, groundwater and soil/sludge
 mixtures.  Since the Old Pond was closed out, as described previously,
 there is an unknown amount of non-absorbed (free)  oil, containing creosote
 compounds and/or PCP,  located in and around the Old Pond/Small  Old  Pond
 and Old Plant/CCA Plant areas.  The. oil  1s primarily located  in fill
.material, weathered bedrock (soil) and bedrock fractures.

 Trenching exploration  by Mines'  consultants also located  free oil near
 Moon  Springs.  It appears that some of the oil  has migrated  from the
 Old Pond area to Moon  Springs via the geologic fault located  during the
 site Investigations.

 Considerable quantities of contaminated soils and  sludges exist primarily
 in the Pond and Landfarm areas.  To evaluate the extent of contaminated
 soil on the site, concentrations of each contaminant were compared with
 depth and location data collected during the site  remedial  investigations.
 Figures 6 to 9 present the areal distribution of the contaminated soil
 for arsenic, chromium, pentachlorophenol  and creosote compounds (sum of
 PAH compounds).  The actual  depths of contaminants vary with  the area.
 The figures showing the extent of contaminant distribution were developed
 utilizing the following assumptions:   the sampling efforts had  adequately
 characterized contamination at the site; and contamination varied uniformly
 between sampling points in both concentration and  distribution.

 As Indicated on Figure 6, the largest amount of contaminated  soil which
 contains over 20 pom of arsenic 1s located within  a 200-foot  radius of
 the current CCA plarit  with a maximum observed concentration of  1435 ppm
 of arsenic.  Chromium  concentrations Indicate a similar pattern.  The CCA
 process area Is the main source of arsenic and chromium contamination at
 the Mid-South site. A RCRA-related Inspection performed.in April 1985
 identified  several  problem areas within the CCA plant that were contributing
 to the release of contaminants.   The Supplemental  Remedial  Investigation
 performed in November  1985 confirmed the release of-CCA solution from the
 plant area.

 Tables 1 and 2 indicate the degree of contamination found in  groundwater
 on the site.  As the mean values illustrate, there is considerable
 contamination onsite,  primarily organic compounds.

-------

-------
          .
; // • -—I --J^^f/*.;-**.
                 ..	{•
                : /•   I'
                ''_/1
{fnf
                                  /i *•--1
                                 /,  /-^N  *

-------
^r^^LU.^-u.-••--,.

-------
: '_.-t:  /f,,->±\;

-------
    i

    ss
    !-•
    (O
 «  M



1"
                &
Onsl
                    i
                                                                                                       in    O    r»   <•«
                                                                                                             -I    CO
                                                                                                                  •W    O    O
                                                                                                                  M    O»    S
                                                                                                                  eo    M    ~
                                 a   s   a    s    s
                                       »*   
-------
B
                                              Table 2 .
                       ARITHMETIC MEANS OF CONTAMINANTS  (ppb),  MID-SOUTH WOOD
                                            PRODUCTS SITE
                                  CCA PLANT SITE AREA, 1985 SAMPLES
                                          Groundwater     Surface Soils     Subsurface
                                       Well 14,15,16,17     (0 - 12")          Soils
              Arsenic                         18                    198             2
If            Chromium, Total                 183                    22           104
U            Fluoranthene                    263                33,513        20,439
              Pentachlorophenol             10,230              187,627        47,387
              EPyrene                          194                29,078        14,545
              Acenaphthene                    437                 5,136        23,511
              Acenaphthylene              .    ND                     ND            ND
              Benzo(a)anthracene              35                  3,372          2,602
              Benzo(b)pyrene                  ND                  1,215           786
              Benzo(b)fluoranthene            ND                 10,579           941
              Benzo (JO fluoranthene            ND                  1,801           770
              Chrysene          •              37                  5,527          2,985
              Dibenzofuran                    300                 3,709        17,410
              Fluorene                        280                 4,845        18,488
            • 2-Methylnaphthalene             730                12,091        33,953
              Naphthalene                    2585                 2,200        44,912
              Phenanthrene                    617                10,007        38,264
,              Anthracene                      127                 1,462          9,187
i
r
c
              ND • Not Detected

-------
                                    18

The present physical condition of the site is unvegetated rolling topography
which is subject to considerable soil erosion during rainfall events.
Some temporary erosion control measures such as hay bale dikes and silt
fences have been implemented by Nines Lumber, but with very limited
success due to the large volume of sediment which erodes from the site.
The presence of PCP (a potent herbicide) in the soil prevents the establish-
ment of a vegetative cover under existing surface conditions.  Given the
present site conditions, there Is ongoing migration of contaminated
sediment and runoff from the site along with movement of contaminated
groundwater and creosote compounds toward Moon Spring and Moon Creek.
There also appears to be migration of surface runoff primarily from the
CCA plant site to the east, toward Prairie Creek.

Pathways of migration from the contaminant sources onsite are by:


        1)   Surface drainage westward Into Moon Creek;

        2)   Surface drainage eastward into Prairie Creek;

        3)   Subsurface (groundwater) movement westward to Moon
             Creek; and

        4)   Subsurface (groundwater) movement southwestward
             and eastward from the CCA plant.

There are no known drummed or liquid hazardous wastes on the Mid-South
site other than about 270 drums of Investigation derived wastes (contaminated
waten, disposable clothing and drilling wastes) from the RI  and SRI  field
work.  This material will be Incorporated Into the remedial  action for
the site.
Future Effects of Contaminants

Of the contaminants found on the site, six are recognized as carcinogens
or suspected carcinogens.  These are:  arsenic; benzo(a)pyrene;  benzo(a)
anthracene; benzo(b)f1uoranthene; benzo(k)f1uoranthene; and chrysene.
Additional contaminants of concern for toxic effects are chromium,  naph-
thalene, and pentachlorophenol.  The health and environmental  effects  of
these compounds are addressed In the Endangerment Assessment Report (EPA,
1985).

Without some change<1n the physical  condition of the site, the migration
of contaminants will continue westward Into Moon Creek and eastward
toward Prairie Creek.. Access to the site 1s presently unrestricted and
the current Industrial operation allows worker access to the site on a
daily basis.

The Endangerment Assessment (EPA, 1985} evaluated the potential  public
health impacts of the current site conditions (taking no remedial action)
on individuals under industrial and  residential scenarios.  These scenarios
were established to simulate existing conditions (industrial)  and possible

-------
                                    19

worst case, future conditions (residential) for the site.  Table 3
summarizes the results of the endangerment assessment evaluations.  This
table presents a summary for potential carcinogen impacts (increased
cancer risk) and potential noncarcinogen impacts (exceedence of allowable
daily intake rates) by exposure to contaminated media.  The information
presented in the Endangerment Assessment supported the following objectives
for remedial action.
Objectives for Remedial Action

The potential health risks Identified for the Mid-South site are based
upon contact with or ingestion of the contaminated soil and groundwater
which contain arsenic and creosote compounds.  If the source of contamination
1s removed or controlled, such that ingestion or contact 1s no longer
possible, then the endangerment to human health and the environment 1s
reduced to acceptable levels.  Therefore, the following specific remedial
objectives were selected for the Mid-South site.

     0    Minimize the threat to public health from the Ingestion of or
          contact with onsite contaminated soil;

     0    Minimize the threat to public health from direct Ingestion of
          shallow groundwater, both onsite and downgradient;

     0    Minimize erosion of contaminated soil and offsite migration
          to protect public health and environmental quality;
          •
     0    Minimize leaching of contaminants Into surface water and
          groundwater; and

     0    Identify cost effective alternatives for remediation of the
          site.

Endangerment Assessment (EPA 1985) concluded that the current site conditions
present a potential threat to the public health and the environment.


ENFORCEMENT

EPA has Identified two Potentially Responsible Parties (PRPs) namely,
Edward Mines Lumber Co., Inc. (Mines) and Mid-South Wood Products of
Mena, Inc. (Mid-South).  EPA sent Notice Letters to Mines and Mid-South on
March 18, 1982, offering them an opportunity to conduct the site
Investigations.  EPA negotiated with the parties for voluntary action;
however, no agreement was reached.

On August 8, 1985, EPA sent Notice Letters to Mines and Mid-South
Informing them of the completion of the remedial Investigation/feasi-
bility study (RI/FS) and EPA's Intent to take remedial action at the
site.  However, on August 14, 1985, EPA decided to delay its decision on
a remedy due to potential contamination problems resulting from the
operation of the CCA wood treatment facility (an area which had not been

-------
W   «•«   E
i   ;   i

i   I   i
*   S
S   5
       i
    fn   fl
    r   ^
!   E
5   i
i
       I
                i
     5
     t
               f  i
               f  i
                &  &


                    I
                        j
                        i
                   sr    f
rvi

5

i?
                                      5
                S  I
                J»  5"
                t?  «*
                *  8
                                          f
                f  ?  S3"
                ?  ?
                i  i
                E  £

                I  I
                e  s
                                                il
-I
»s
                •1   1
                ET   tr
                >r   >r
                             ?
                                      ?
                                 I
                        n    i
                        i    S

-------
                                    21

investigated during the original RI/FS activities.  EPA performed a
supplemental investigation during the winter of 1985.  On April 17, 1986,
EPA sent Notice Letters to Mines and Mid-South informing them of the
completion of all RI/FS activities and its intent to take remedial action.

On May 8, 1986, EPA held a Public Hearing in Mena, Arkansas to discuss
with local residents the remedies being considered for the Mid-South
site.

Subsequent to the completion of the RI/FS, EPA has held several meetings
with the PRPs to discuss remedial action.  On April 24, 1986, a meeting was
held in Dallas to discuss the Feasibility Study Report.  On June 5,
1986, EPA met with the PRPs and listened to their proposal for remedial
action.  On September 9, 1986, EPA received a remedial  action work plan
from the PRPs.  EPA and the PRPs met on September 17, 1986, to discuss
this proposal.  Based on the comments provided by EPA during the meeting
and summarized in a letter sent to the PRPs on September 19, 1986, a
revised proposal was received by EPA on October 7, 1986.


ALTERNATIVES EVALUATION SUMMARY

Based on the remedial Investigation and endangerment assessment findings,
remedial action alternatives were developed from a list of applicable
remedial technologies to address the hazards posed by the site.  Contaminants
are found in the site surface soils, surface sediments and surface water
and the groundwater beneath the site.  Alternatives were developed to
address the contaminants in all media.

Table 4 presents a list of the remedial technologies (grouped by response
action) that were considered as potentially viable solutions for the
Mid-South site.  Descriptions of the remedial technologies considered
applicable are summarized below.


                                Table 4
                     POTENTIAL REMEDIAL TECHNOLOGIES
        Response Action              Remedial  Technology

        Containment                  Capping,  containment barrier,
                                     stabilization
                   /

        Source Removal               Excavation and backfill,  on-
                                     site landfill, offsite land-
                                     fill

        Source Treatment             Incineration, leaching/biotreat-
                                     ment, landfarming

        Groundwater Remediation      Groundwater recovery, groundwater
                                     treatment

-------
                                     22

         Other Responses              Fencing, regrading, topsoil
                                      addition and seeding (cover),
                                      deed restrictions, alternate
                                      water supply

 In EPA's Feasibility Study Report cleanup action levels were derived to
 Unit exposure to contaminated soils.  Those contaminants most prevalent
 at the site and of the greatest concern form a public health standpoint
 were the carcinogenic PAHs and arsenic.  Arsenic does not have a cleanup
 standard; therefore, the concentrations found in numerous background
 samples were evaluated and cleanup level was established for arsenic at
 3 ppm (the mean background level).

 Carcinogenic PAHs also do not have a simple concentration promulgated as
 a cleanup standard.  Therefore, EPA must select a cleanup level relative
 to a desired excess lifetime cancer risk level.  Using a model which was
 developed by EPA's Carcinogen Assessment Group, the cancer risk levels
 corresponding to a target range of 1x10-4 to 1x10-8 were generated.  EPA
 selected a 1x10-6 value of 300 ppb as the cleanup level for total  carcin-
 ogenic PAHs.

 Due to the fractured nature of the bedrock below the site, 1t was  deter-
- mined that groundwater cleanup would be best accomplished with'large
 surface area, french-draln type recovery systems.  These systems should
 collect the majority of contaminated groundwater leaving the site.  All
 contaminated surface waters will  be treated prior to discharge.

 Potential alternatives were screened using relative rating scales  based
 on cost estimates, effects on public health and the environment, and
 accepted engineering practices.  A summary of the screening 1s presented
 1n Table 5.  The alternatives retained after the screening process
 Included:

      o    Onsite Landfill
      o    Multi-Layer Cap
      o    Topsoil-Clay Cap
      o    Soil Treatment
      o    Combined Excavation/Capping
      o    Groundwater Recovery/Treatment

 Based on the Information developed during the Mid-South Investigation
 six remedial alternatives were evaluated as being feasible to eliminate
 or minimize the environmental or public health threat posed by the Mid-
 South site.        '

 Each alternative was then developed in more detail  and evaluated based on
 total present worth costs, public health effects, environmental effects,
 technical considerations and Institutional concerns.  Table 6 presents
 a summary of the detailed alternative evaluation.

-------
E
            4V
V^   ^*
8   8

U  I
*§  o


?!  ?
ii  i


^2  «
                  Si
                  ?

                  i
              i   I
ing,

water aupp
                               S 8
                                    2
        |


        I
             g-<    •
            -S    s
            5? Sf  *

            ji i  i



            «! i!
             ** M  4* •
                                               I  2C
                                               8  . i
2



1

V

|
                           2
15

1^
•«*
Eve  «  M
3*1  £  5
for
                                i
                                    •  •
IM • v«  B •  ««

111  it  i

                               t

clay ft aynthe

reatrictiona
                  u
                  **
                  k«
                  h   h  I
             •"  a S
Cap with

reatrict
              •  MO


              i  *!
             * ta  S M
             *3  »!
             ••6  •« 6
             Si  3*
                     '  S
                      ,  «.

                      I  i
                      ? - ?
                      5 S I

                      n.|
                      «- —i
             «<  -  e
                                                     *• «.  e
                                                         2
                      il 3.

                      8"5 2.

                      H fl
«
•P4
i
^
S"
!
1

3
IM
•
W
i
•4
«M
2

S
«
1
»
4rf
i
a
41

J!
                                                         i»
                                                               
-------

i

     i

           M
!ji  J|i   !||   ii!

Ill  i]f   ill
]i;  it!   ii!
ii!
                    !:
                             I  I
                             lil
                        i

                       12
                          i13
                          iii
                          ill
       i
              i
      ji!

                    ii '
           Mf fins  lj.j|
           ill Jllil  iliii
       ill
        • 12 i •
        a 8 « 1 •
        li; i
!
ii
ij
    S
    !
      i
ii
j!
i'
«•

i

!
!
l
        i
           !
    jf

    I

         1
                 5
                 m


                 t

                 I

         i!!!   iH   !
                      ^
                       s
               a

               I

                     I


                     I

                             ||!


                             13!!


                             il
                          I
                          -41
                          Il
                          i
                          a
           i     i     i!    i     !
                          s

-------
i
             J
 j
   «4
   •*



   ii

   a"

                n
| I

Ji
              si
               j s
5i
f!
•M 2

j
J
1
*J
g

1
f
|
M
S
I
s
ii
1
§

i
•*
b I
tooovtrr/1

-------
                                     26

 Development of Remedial Alternatives

 The technologies listed above represent an assemblage of potential  tech-
 nologies that could be implemented in various combinations to remediate
 the hazardous waste problems at the Mid-South site.   Each technology is
 applicable for a specific function as part of a remedy and, as such,
 represents a portion of the overall remedial  action  that is necessary at
 the site.  Where two similar technologies were applicable (and acceptable)
 for a single alternative, the lower cost technology  was selected.

 The Mid-South site presents two media of concern:  contaminated surface
 soil/sediments and contaminated groundwater.   To develop potential  remedial
 alternatives for these media, the screened technologies were combined to
 encompass a range of possible alternatives for this  site.

 Each alternative, except for No Action and Groundwater Recovery/Treatment,
 addresses contaminated soil media (including  the small volumes of contami-
 nated surface water) to varying extents.  The Groundwater Recovery/Treatment
 alternative as modified, was determined to be the  only possible, effective
 alternative for direct groundwater remediation and is presented separately.
 This alternative can be combined with any of  the other alternatives
 depending on the desired level  of remediation and  cost of Implementation.

"For all  alternatives, except for the No Action alternative,  the remedial
 investigation-derived wastes, described previously will  be disposed of by
 batch treatment onsite.  Contaminated fluid will be  treated  in the  ground-
 water treatment unit and solids will  be incorporated with solids being
 disposed of under the chosen site remedy.  Emptied barrels will be  cleaned
 and salvaged.  For the no action alternative, the  barrels will  be left
 onsite.   For this small amount of waste, alternative evaluations will  not
 be made  and the same cost is assumed to be additive  to each  alternatives.
 Based on Initial estimates, the disposal cost has  been estimated to be
 approximately $10,000.

 In addition, remedial actions for the CCA plant will  be necessary to
 control  further releases of arsenic and chromium from the plant via
 runoff.   The drip pad (see Figure 10) has a surface  area of  approximately
 22,000 square feet and during the first hour  of a  25-year, 24-hour  storm
 (0.3 inches/hour 1n Mena) approximately 4,000 gallons of runoff will  be
 produced from the drip pad.  The pad 1s sloped toward the collection
 trench and plant sumps to collect the runoff.  An  open stormwater storage
 tank exists, however, the volume of the plant sumps  and stormwater  storage
 tank are not maintained to contain 4,000 gallons of  runoff in  the event
 of a storm.  Under current operation, the stormwater pump must be turned
 on manually to function.  As a result,  much of the contaminated runoff is
 released to the environment by overflow of the stormwater sump into the
 adjacent ditch and overflow sump.  In addition,  the  pad ,1s not completely
 curbed and open joints and cracks exist in the concrete providing additional
 pathways for migration.

-------
HI
 9
 if

-------
                                    28

To remedy the CCA plant  releases, better stormwater containment must be
installed and properly operated.  The actual volume of stormwater to be
collected will be established based on state or federal regulatory limit-
ations placed on the quality of the water leaving the plant.  For estimation
purposes, the first hour of a 25-year, 24-hour storm (4,000 gallons) is
assumed.  Under average  rainfall conditions this stormwater would be
expected to be heavily contaminated.  A stormwater storage tank could be
connected to the existing stormwater sump by a system composed of a level
actuated pump designed to cutoff when the storage tank becomes filled.
The water in the tank should be used as makeup water for the CCA process
or run through a water treatment system prior to discharge.

To contain runoff on the drip pad, the drip pad should be curbed along
its entire perimeter.  A 6-inch high by 8-inch wide concrete curb will be
substantial enough to remain Intact and provide the needed drainage
control.  Protection against infiltration through the drip pad can be
enhanced by sealing all existing joints and cracks in the concrete.

To implement this alternative for stormwater control at the CCA plant, it
is estimated that the cost would be approximately $12,500.  This cost
will be additive to any selected remedial action undertaken at this site.


Description of Alternatives

Upon completion of the screening process, a set of remedial alternatives
was assembled to address the remedial needs of the Mid-South site.  The
assembled alternatives were selected to demonstrate a reasonable range of
remedial actions which are applicable to the Mid-South site and which are
based upon technical implementability and environmental  suitability
within the limits of the specified objectives.  The Groundwater Recovery/
Treatment alternative addresses only groundwater remediation within the
shallow bedrock, and can be combined with any of the other alternatives,
as deemed necessary by the EPA.

A summary of the results of the detailed evaluation of retained alternatives
1s presented in Table 6.  Brief discussions of these final alternatives
are presented in the following sections of this document.


Alternative 1   No Action

Section 300.68(f) of the NCP specifies that the "No Action" alternative
be evaluated.  Under1 this, alternative, no remedial  action  would be imple-
mented at Mid-South.  Section 300.68(g)(3)  states:

     "Those alternatives that do not effectively contribute to the
      protection of public health and welfare and  the environment  shall
      not be considered further."

-------
                                     29

 The absence of remedial  action would allow for long term erosion of the
 site due to wind and precipitation.   The following threats to public
 health and the environment would be  posed if no remedy was implemented  at
 the site:

      0  Direct contact with surface  soils;
      0  Migration due to surface water runoff;
      0  Fugitive dust emissions;
      0  Migration due to leaching and subsequent groundwater
         contamination.

 Because the risks to public health and the environment associated with
 the "No Action" alternative are unacceptable,  this alternative is eliminate
 from consideration.
 Alternative 2  Excavation with  Onsite  Landfill
 This alternative Includes the construction  of an  onsite  landfill that
 complies with provisions of RCRA and  State  of Arkansas regulations  (See
 Figures 12,  13 * 14).  It has been  stated by  Nines  Lumber  Company that
•they own a sufficient amount of  property adjacent to the site for
 construction of a landfill; therefore,  it was assumed that no extra
 property needs to be purchased and  that a sufficient amount of  fill
 material Is  available on the adjacent property.   This alternative
 Includes the following operations:
        Ar
      0  Excavation of onsite and offsite contaminated
         soils;
         Dust control;
         Backfill  and grading of  the site;
         Construction of an onsite landfill;
         Waste placement in the landfill;
         Fencing of landfill  area; and
         Implementation of groundwater monitoring  and deed
         restrictions.

 The  total  volume  to be removed 1s approximately 80,000 cubic yards.
 Figure 11  shows the extent of total contaminated  soils to be excavated
 which would  meet  the above criteria.

-------
  7/:  i*    "^ "•"'•"•  IC\^'  -U'J-' !:;   ->ou r,  .
  //   i     t   »» )!/ "^-x^"'  ^^f-""' >	  V"1'
.-/  st—'^  5«/'  v>^~^"^-  .. .vv^--:--;
 A   ' '   /  \\   M  '   \-'C-<    >*>-^* " " ~.    ^.  '
/.j,_y...,...  .-.., ^^-rr-r^^^i:-:;^";>•, -^:-;i

 ^:. •  1  y# L^H^=;i^^f  riH ^?^? l|j
 ^   U^/-^r-^y^^^|

                    ;   ••Vi'Y ^7 xfTT"^-?^..
                    A   i.*.f ]• \>(x-,-y •».>^- '^r>^:'\")!

                        M/iffif't.-^*  $
   f-'  - -• •  y
   H   .•;,—»  j-
., .JL  ,/,..>4-/
 xrlr-^vrrN /
 tv;  x*i-wr

/>W:I,
/    . ,  •,  L »
/    7   . .5 i .-

-------


-------

-------
SMI
5c°*
^?o.a°
s *< o —
 »cog^

-------
                                     34

 Alternative 3   Multi-Layer Cap

 This alternative includes the excavation of wastes and contaminated soil
 from areas onsite and consolidation onto the main portion of the site.
 An area of 20 acres will be covered by a multi-layer RCRA cap system (See
 Figure 15).  Site security will be Implemented by Including fencing,
 signs, and regular Inspections.  Groundwater monitoring will also be
 performed.  This alternative Includes the following operations:


      *  Excavation of onsite contaminated soils adjacent
         to the CCA plant and in the Moon Creek drainageway;
         Excavation of offsite contaminated soil;
         Site grading;
         Construction of a cap- and cover system;
         Groundwater monitoring;
         Fencing of site and deed restriction.


 Alternative 4   Topsoll-Clay Cap

 This remedial alternative has been Included in the detailed evaluation  as
.an alternative which will meet the remedial objectives of the Mid-South
 site and is a RCRA compliant cap alternative.  The primary difference
 from the multi-layer cap is the deletion of the synthetic membrane.  All
 other components of the alternative will  be the same as discussed  for the
 multi-layer cap.

 This alternative will allow additional  potential  Infiltration through the
 cap and Into the contaminated soil, however,  the calculated reduction of
 Infiltration 1s stm over 70 percent as compared with the present conditions
 at the site.

 This alternative Includes the excavation of wastes and contaminated  soil
 and consolidation onto the main portion of the site as described  for the
 multi-layer cap alternative.  The entire site area of 20 acres will  be
 covered by a topsoll-clay cap system.  Site security will  be Implemented
 by Including fencing, signs, and regular Inspections.  Groundwater monitoring
 will also be performed.  This alternative Includes the following  operations:


      0  Excavation of contaminated soils  adjacent to the CCA plant and
         1n the Moon-Creek and southwest drainageway;
      0  Excavation bf offsite contaminated soils;
      0  Site grading;
      0  Construction of a cap and cover system;
      0  Groundwater monitoring;
      0  Fencing of site and deed restriction.

-------
         \
           \\
                     ^ <. w
                     ~*UJ K ^


                     SS|£
                          -j»>,
  ^^ti:
  J&.
 N
•Nx i /
•  * 5 ,
                 <\-
      ;N

      Xv
:.i»:»r-S#&.
       \*V,
         f  CiT'

 *v^-/'/ / «y •"

:^{ (/,
    A^  s - \
        *2 J ^
 />-—"*—*^
--^ /      «j  ^~*-
T 'W    f ;

0/'^it'	

'/^^
   CT
           «%^iv?«w?^
 ^/
^  //rRrvr/^/:
 i /- /  '////T //v
 !/•••*%? V»T.
                        ?''<§>
                /

-------
                                     36

 Alternative 5   Soil  Treatment

 This  remedial  alternative  (See  Figure 16)  along with  groundwater  recovery
 and treatment was  been  inferred as  the  preferred  alternative of Mines
 Lumber  Company throughout  the preparation  of  the  Feasibility Study  Report.
 As previously mentioned, both alternatives have been  investigated by the
 consultants for Nines.  This combination would include the  following
 operations:

          Excavation of  contaminated  soil;
          Dust control;
          Leaching  of  organic contaminants;
          Biological degradation of  leachate;
          Discharge of effluent  to surface  drainage.


 Alternative 6   Groundwater Recovery/Treatment

 This  alternative 1s designed to recover contaminated  groundwater  from six
 contaminated locations  throughout the site  and treat  the water to acceptable
 levels  so that it  can be discharged.

•The contaminated groundwater would  be recovered by means of six french-drains
 as shown  on Figure 17.  Three of these  systems have been partially  installed
 by Mines  Lumber; however,  RW-1  is improperly  oriented.  Further, RW-2
 needs to  be lengthened, northward to intercept groundwater flowing  around
 this  drain.  French-drains built as  shown  in  Figure 18 should be located
 as Indicated in Figure  17-for RW-1  (new alignment), RW-2 (extension),
 RH-4, RW-5,  and RW-6.   The design pumping  rate of each french-drain would
 need  to be determined after actual  Installation, but  for cost comparison,
 each  system has been  sized for  5 gpm.

 The treatment  system  Incorporates the following unit  operations and
 processes:  flow equalization, batch  chromium  reduction followed by  arsenic
 and chromium oxidation, precipitation,  sedimentation, sand filtration,
 carbon adsorption, and  sludge dewatering.   A  schematic of the treatment
 train 1s  provided  on  Figure 19.


 Alternative 7    Combined Excavation/Capping

 Implementation of  this  alternative Includes:  excavation and onsite
 landfill Ing for contaminated soil and rock  from the Old Pond, Small  Old
 Pond, and  CCA  Plant portion of  the site; and  a topsoil-clay cap for the
 landfarm  area.   This  alternative was developed to utilize source removal
 (excavation)  for the  heavily contaminated areas, which exists over a
 major geologic  fault.  The Landfarm  area, which presents -a primary threat
 through surface runoff contamination would  be capped with a topsoil-clay
 cap.  This  alternative  includes the  following operations:

      0  Excavation of the contaminated  soil and rock as
        noted  above;
      0  Excavation of the contaminated  soils to the southwest and
        northwest  along East Fork Moon  Creek and placement on the  Landfarm
        area to  be capped;

-------
      8
      OB
      S
      m*




      \
"
  I	I
                      o
                      N:

                      s
           w

           3
1
                ;Pl
                ISfil
                *g|l

                 5§5
                 IB*
                  i
i
                            3

-------

'          -

                                '   t

-------
                                                    CO
0

c
I!
                        •^•crf-it 'o'Tr • "><-f


                        :_• ^™ •BIT • . •. ~ts*\ w' ' • 1

                        izmmz
                           &*<>•'£•


                           ^@q

                           i^oS
                           L- *>%»• ^ . **+! . • . .
5S^
s^^afe
                         ;:
                         Pa
                         $*

-------
*•» h* sv

-------
                                     41

      0  Excavation of any contaminated soils
         offsite to the Northeast;
      0  Construction of a RCRA-compliant landfill;
      0  Backfill,  grading and seeding of the  excavated  areas;  •
      0  Construction of topsoil-clay cap over the Landfarm
         area;
      0  Groundwater monitoring;
      0  Fencing of site and deed restriction.

 Elements of this alternative are Identical  to the previously described
 alternatives of excavation, onsite landfill and  topsoil-clay cap  except
 for the specific volumes related to each process.


 Detailed Evaluation of Costs

 This section presents a detailed evaluation of the  cost  for each
 of the previously described alternatives.  The cost estimates presented
 are order-of-magnitude level  estimates.   Examples Include  estimates from
 cost-capacity curves and estimates using scale up or scale down factors
 and/or approximate ratio estimate.  It  1s normally  expected that  an
 estimate of this type would be accurate  to +50%  and -30%.  The cost
'estimates are  presented 1n 1986  dollars.

 The feasibility level cost estimates presented have been prepared for
 guidance in project evaluation and implementation from the information
 available at the time of the estimate.   The actual  cost of the project
 will  depend on the final  scope of  the remedial action as designed by
 others, the schedule of Implementation,  actual labor and material costs
 at the time of bidding, competitive market conditions and  other variable
 factors that may Impact the project costs.  As a result, the final project
 costs will  vary from the estimates presented  herein.


 Alternative 1   No  Action

 No costs associated with this alternative.


 Alternative 2    Excavation with  Onsite Landfill
 Cost

 The excavation  of contaminated soil from the site 1s a common Item for
 several  of  the  alternatives.  The volume of contaminated soil to be
 excavated to  acceptable cleanup levels were discussed previously.  The
 excavation  of 80,000  cubic yards will be required and used for the cost
 estimates.  Table 7 presents the cost elements for this volume.  It is
 also  assumed  that for a variation in excavated volume, the unit prices
 will  remain constant,  (I.e., a 10 percent volume Increase will increase
 cost  by  10  percent).

-------
                                    42

                          Table 7
                COST ESTIMATE FOR EXCAVATION

                                             Construction
     Cost Element                              Cost ($)

1.   Excavation and hauling of
     contaminated soil (80,000 cubic
     yards)                                    $413,000
2.   Dust control (20 acres)                    112,000.
                              Total             $525,000
                              Table 8
                  COST ESTIMATE FOR ONSITE LANDFILL
                                                   Construction
        Cost Element                                 Cost ($)

    1.  Containment Cell (5.5 acres)
        A.  Clear and Grub                              $ 7,000
        B.  Surface Preparation                          13,000

                    Subtotal                             $20,000

    2.  Liner/Leachate Systems
        A.  Synthetic Liner     "                       $122,000
        B.  Sand Cushion                                 58,000
        C.  Leachate System                              87,000
        D.  Leachate Collection Box                      10,000
        E.  Geotextile                                   49,000
        F.  Traffic Layer                                39.000

                    Subtotal    '                        $365,000

    3.  Waste Emplacements (80,000 cubic yards)
        A.  Placement and Compaction                   $712,000

    4.  Cover System
        A.  Earthfill                                  $118,000
        B.  Sand Cushion                                 19,000
        C.  Synthetic Membrane                          208,000
        D.  Drainage Layer                               19,000
        E.  Geotextile.                                  46,000
        F.  Vegetative Layer                            144,000
        G.  Perimeter Fence                              15,000

                    Subtotal                            $569,000

-------
                                43

    Storm Water Runoff Containment
    A.  Haul and Fill                                $1,000
    B.  Grading/Compaction                            2,000
    C.  Ditch and Bern                                7,000

                Subtotal                            $10,000

    Leachate Containment Pond
    A.  Haul and Fill                               $ 1,000
    B.  Grade/Compaction                              1,000
    C.  Piping                                        1,000
    D.  Synthetic Liner                              11,000
    F.  Closure                                       8,000

                Subtotal                            $22,000
7.  Excavation                                     $525,000

8.  Backfill Excavated Area (20 acres)
    A.  Backfill Material                          $565,000
    B.  Grading/Compaction                          320,000
    C.  Seed & Mulch                                 25,000
    D.  Perimeter Fence (2,000 feet)                 19,000
    E.  Groundwater Well Installation                18,000

        Subtotal                                   $947,000

9.  General Requirements
    A.  Mobilization Bond 4 Insurance               126,000
    B.  Health and Safety                           221.000

        Subtotal                                   $347,000

10. Construction Subtotal                        $3,517,000
    A.  Bid Contingencies                           527,000
    B.  Scope Contingencies                         703,000

        Construction Total                       $4,747,000

    C.  Permitting and Legal                        332,000
    D.  Services During Construction                332,000

        Total Implementation Cost                $5,411,000

    E.  Engineering Design Cost                     475,000
                                                   3BSSSZ838
        TOTAL CAPITAL COST                       $5,886,000

-------
                                     44
                               Table  9
                  POST CLOSURE  ANNUAL COST ESTIMATES
                          FOR ONSITE  LANDFILL
               Cost  Element                       Present Worth  ($)

     1.   Long Term Maintenance
         A.   Mowing                                     $  15,000
         B.   Leachate Testing                             9,750
         C.   Leachate Disposal                             50,000
         D.   Annual  Inspection                            10,000
         E.   Groundwater Monitoring                        42,500

                  TOTAL                               $127,250

 Alternative 3   Multi-Layer Cap

 Cost

 Table 10 presents the cost  elements  for  the multi-layer cap alternative.
•The cost estimate is based  on the operations  previously described.
 Capping costs were  based on the  cover  system  as  shown  on  Figure 15.
 The materials used  for the  cap were  assumed to be  hauled  from  adjacent
 property.  Fencing  costs include the construction  of fences around the
 perimeter of the site.  Level  C  protective clothing for all personnel
 onsite  during the construction period  (assumed to  be 6 months) was used
 for estimating purposes.  Decontamination costs  Include the necessary
 equipment and materials needed to decontaminate  the personnel  and equipment
 used.  Installation of five additional groundwater wells  (in addition to
 the existing groundwater monitoring  system) was  assumed to meet the
 needs for groundwater monitoring.


                              Table 10
                          COST ESTIMATE FOR
                          MULTI-LAYER  CAP
                                               Construction
         Cost Element                            Costs  ($)

    1.   Excavation and Hauling                $   66,000

    2.   Capping (20 acres)

         A.   Clay Liner                          546,000
         B.   Sand Drainage Layers                274,000
         C.   Synthetic Membrane                  758,000
         D.   Topsoil                             334,000
         E.   Seeding                              25.000

                   Subtotal                    $1,937,000

-------
                                    45

3.   Fencing (5,000 LF)                        38,000
4.   Groundwater Well Installation (5 wells)   18,000

5.   General Requirements

     A.   Mobilization Bond & Ins.             82,000
     B.   Health & Safety                     144,000

                Subtotal                      $226,000

6.   Construction Subtotal                 $2,285,000

     A.   Bid Contingencies                   343,000
     B.   Slope Contingencies                 457,000

              Construction Total           $3,085,000

     C.   Permitting and Legal                216,000
     D.   Services During Construction        216,000

          Total Implementation Cost        $3,517,000

     E.   Engineering Design Cost             309,000
                                             • JC3S3SS38
                TOTAL CAPITAL COST          $3,826,000
Table 11 presents the post-closure costs which Include groundwater
sampling and analysis for 5 wells, once per quarter for the first year
and once a year thereafter for 30 years, assuming no contamination
occurs, maintenance (I.e., soil replacement and erosion repair,  fence
repair, mowing, and reseeding), and site inspections and security checks,
The costs shown for the post-closure elements are present worth  values
discounted using a rate of 10 percent over a period of 30 years.
                             Table 11
                    POST-CLOSURE COST ESTIMATE
                       FOR MULTI-LAYER CAP

        Cost Element                       Present Worth ($)
   1.   Groundwater'Monitoring                  $ 42,500
   2.   Maintenance      '                         20,740
   3.   Site Inspections & Security               20.000
                  TOTAL PRESENT WORTH           $  83,240

-------
                                    46

Alternative 4  Topsoil-Clay Cap

Cost

Table 12 presents the cost elements for this alternative.  Annual
post-closure costs are the same as Table 11.
                             Table 12
                         COST ESTIMATE FOR
                         TOPSOIL-CLAY CAP

                                              Construction
        Cost Element                            Costs ($)

   1.   Excavation and Hauling                  $ 66,000
   2.   Capping (20 acres)

        A.   Clay Liner                          546,000
        B.   Sand Drainage Layers                274,000
        C.   Topsoil                             334,000
        D.   Seeding                              25.000

                  Subtotal                    $1,179,000

   3.   Fencing (5000 LF)                         38,000
   4.   Groundwater Monitoring Well
        Installation                              18,000

   5.   General Requirements

        A.   Mobilization Bond and Insurance      52,000
        B.   Health and Safety                    91,000

             Subtotal                         $  143,000

   6.   Construction Subtotal                 $1,444,000

        A.   Bid Contingencies                   217,000
        B.   Scope Contingencies                 289,000

             Construction Total               $1,950,000

        C.   Permitting and Legal                137,000
        D.   Service During Construction         137,000

             Total Implementation Cost        $2,224,000-

        E.   Engineering Design Cost             195,000
                                               3833SS83S8
             TOTAL CAPITAL COST               $2,419,000

-------
                                     47

 Alternative 5   Soil  Treatment

 Costs

 The cost of this alternative has  not been  evaluated  because  the  consultants
 for H1nes Lumber Co.  did not furnish any costs  of chemical requirements
 for the pilot demonstration  project  on leaching and  blotreatment of
 organic contaminants  1n soil.  Estimates were made for  screening purposes
 1n the Feasibility Study Report.   A  range  of $4,000,000 to $8,000,000 was
 estimated for the treatment  of an estimated 80,000 cubic yards of contaminated
 soil  (plus excavation costs).

 Alternative 6   Groundwater  Recovery and Treatment

 Costs

 Table 13 presents the costs  for the  groundwater recovery system of six
 french-dralns and a central  water treatment system.  The treatment system
 1s sized for 30  gpm and the  contaminant  concentrations  as previously
 described.  These parameters need to be  accurately tested prior to design
 and Implementation of this alternative.  Table  14  presents the present
.worth post closure costs for this alternative.   Costs for oil/sludge
 disposal  are based on assumptions for recovery  percentages of, 90% for
 the first year and 10% each  year  thereafter for  ten years.


                              Table 13
                          COST ESTIMATE FOR
                 GROUNDWATER  RECOVERY AND TREATMENT
                                              Construction
        Cost Element                             Cost ($)

   1.   French drains and pumps (6 each)      $  209,000

   2.   Pipeline  (12,000 LF)                      60,000

   3.   Power Connection                          20,000

   4.   Controls                                  15,000

   5.   Metal Removal System
        A.   Tanks and reactors                  110,000
        B.   Filter press                         15,000
        C.   Chemical feed system                 55,000

                       Subtotal                 $180,000

   6.   Mixed Media Filter                        20,000

   7.   GAC Carbon Columns                       200,000

   8.   Pumps and Piping                          20,000

-------
                                 48
9.   Electrical and Controls                   30,000
10.  Building and Equipment Installation      100,000
11.  Perimeter Fence (5000 LF)                 38,000
12.  General Requirements
     A.  Mobilization Bond & Insurance         36,000
     B.  Health & Safety                       62,000
                    Subtotal                  $98,000

     A.  Bid Contingencies                    149,000
     B.  Scope Contingencies                  198,000
                    Construction Total     $1,337,000
     C.  Permitting and Legal                   94,000
     D.  Service During Construction           94,000
               Total Implementation Cost    $1,525,000
     E.  Engineering Design Cost               138,000
                                              •S333S3S3
         TOTAL CAPITAL COST                 $1,663,000
                          Table 14
                    ANNUAL OPERATING COST
             GROUNDWATER RECOVERY AND TREATMENT
     Cost Element                          Present Worth ($)
1.   Carbon replacement                      $  950,000
2.   Chemical Cost                               19,000
3.   Sludge/011 Disposal                         94,000
4.   Electricity                                142,000
5.   Manpower    '                               283,000
6.   Chemical Analyses                          377.000
                         TOTAL               $1,865.000

-------
                                     49

 Alternative  7    Combined  Excavation/Capping

 Cost

 Table 15 presents  the  cost elements  and associated  construction costs
 for this alternative.   The cost estimates were based on the construction
 procedures and dimensions described  1n this section for the excavation
 and landfilllng  of 40,750 cubic yards of contaminated soil and rock from
 the Old  Pond, Small Old Pond and the CCA Plant area, and topsoil-clay
 capping  of 12 acres of site area.  Approximately 5,000 cubic yards of
 contaminated soil  from  the various drainage pathways  will  be
 excavated and placed under the cap.

 These costs  Include the backfilling/grading and seeding of the excavated
 area  without the necessity for a complete cover system.  Level C protective
 clothing for all personnel during construction (assumed to be 9 months)
 was used for estimating purposes.  Decontamination costs Include the
 required equipment  and materials needed to effectively decontaminate the
 personnel and construction equipment used.  Groundwater monitoring wells
 are proposed for the excavated and capped area.

 Table 16 presents  the  post-closure costs for the excavation/landfill
.capping  alternative.   The costs include maintenance (soil replacement and
 erosion  repair,  fence  repair and reseeding), leachate removal, Including
 disposal, and site  inspection and security checks.  The post-closure
 costs are present worth values discounted using a rate of 10 percent over
 a period of  30 years.


                          Table 15
               COST FOR COMBINED EXCAVATION/CAPPING

                                                Construction
               Cost Element                       Cost ($)

    1.  Containment  Cell (3 acres)
       A.  Clear ft  Grub                              $  4.000
       B.  Surface  Preparation                           7.000

                 Subtotal                             $ 11,000

    2.  L1ner/Leachate  Systems
       A.  Synthetic Liner                              67,000
       B.  Sand  Cushion  .                              32.000
       C.  Leachate System                              47.000
       D.  Leachate Collection Box                       6.000
       E.  Geotextile                                   27,000

       F.  Traffic  Layer                                16.000

                 Subtotal                             $195,000

    3.  Waste Emplacement (45,750 cubic yards)
       A.  Placement and Compaction                   $407,000

-------
                                 50

4.  Cover System for Containment Cell
    A.  Earthfill                                  $ 65,000
    B.  Sand Cushion                                 10,000
    C.  Synthetic Membrane                          114,000
    D.  Drainage Layer                               10,000
    E.  Geotextile                                   25,000
    F.  Vegetative Layer                             79,000
    G.  Perimeter Fence (500 LF)                      4.000

              Subtotal                             $307,000

5.  Stormwater Runoff Containment
    A.  Haul & Fill                                   1,000
    B.  Grading/Compaction                            1,000
    C.  Ditch & Basin                                 7.000

              Subtotal                             $  9,000

6.  Leachate Containment Pond
    A.  Haul & Fill                                   1,000
    B.  Grade/Compaction                              1,000
    C.  Piping                                        1,000
    D.  Synthetic Liner                               7,000
    E.  Closure                                       5,000

              Subtotal                             $ 15,000
7.  Excavation (45,750 cubic yards)              $  300,000

8.  Backfill Excavated Area (45,750 cubic yards)
    A.  Backfill Material                         $ 323,000
    B.  Grading and Compaction                      183,000
    C.  Seed A Mulch                                 15.000

              Subtotal                           $  521,000

9. Cap (12 acres)
     A.  Clay Liner                               $ 328,000
     B.  Drainage Layer                             164,000
     C.  Topsoll                                    201,000
     D.  Seeding                                     15,000

              Subtotal                           $  708,000

10. Perimeter Fence (5,000 LF)                   $   38,000
11. Groundwater Monitoring Wells                 $   18,000

12. General Requirements
     A.  Mobilization Bond & Insurance           $  101,000
     B.  Health & Safety                         $  177,000

              Subtotal                           $  278,000

-------
                                    51

   13.  Construction  Subtotal                       $2,807,000
        A.  Bid Contingencies                          421,000
        B.  Scope Contingencies                        561,000

                 Construction Total                 $3,789,000

        C.  Permitting and Legal                     $ 265,000
        D.  Service During Construction                265,000

                 Total Implementation Cost          $4,319,000

        E.  Engineering Design Cost                    379,000

                 TOTAL CAPITAL COST                 $4,698,000

                            Table 16
              POST CLOSURE ANNUAL COSTS ESTIMATES FOR
                    COMBINED EXCAVATION/CAPPING


              Cost Element                   Present Worth ($)

   1.  Landfill 0AM
       A.  Mowing                                 $ 8,500
       B.  Leachate Testing                         9,750
       C.  Leachate Disposal                        27,500
       D.  Annual Inspection                       10.000

             Subtotal                             $55,750

   2.  Cap O&M
       A.  Groundwater Monitoring                  42,500
       B.  Maintenance                             12,500
       C.  Inspection                              12.000

             Subtotal                             $67,000

   TOTAL PRESENT WORTH                           $122,750
Alternative 8 Excavation with Offsite Landfill
                   /
While this alternative was screened from detailed excavations, it will  be
used for comparison.   A more detailed cost estimate was developed for
this alternative to provide for a more accurate comparison of costs.
This estimate is presented in Table 17.

-------
                                 52

                              Table 17
                 COST ESTIMATE FOR EXCAVATION WITH
                     OFFSITE LANDFILL DISPOSAL

                                               Construction
         Cost Element                             Cost ($)

1.  Contaminated Soil Removal
    A.  Excavation                              $   209,000
    B.  Loading & Prep. Trucks                      120,000

                 Subtotal                       $   329,000

2.  Transportation (450 m1]es)
    A.  Haul (12 CY Trucks)                       9,600,000
    B.  Oept. of Transportation                      20,000
        Manifest Charges                          	

                 Subtotal                       $ 9,620,000

3.  Offsite Landfill                               8,000,000

4.  Backfill Excavated Area
    A.  Import Backfill Material                     565,000
    B.  Grading/Compaction                          320,000
    C.  Seeding                                      25,000
    D.  Groundwater Well Installation                18.000

                 Subtotal                       $   928,000

5.* General Requirements
    A.  Mobilization Bonds and Insurance             50,000
  * B.  Health and Safety                            88.000

                 Subtotal                       $   138,000

6.  Construction Subtotal                       $19,015,000
    A.  Bid Contingencies                         2,852,000
    B.  Scope Contingencies                       3,803.000

                 Construction Total             $25,670,000
    C.  Permitting and Legal                      1,797,000
  * D.  Service During Construction                 102.000

          Total Implementation Cost               $27',569,000
    * E.  Engineering Design Cost                     814,000
                                                  SSS3SS«3S3S
                   TOTAL CAPITAL COST             $28,383,000


  *Excluding Transportation and Disposal Costs

-------
                                     53

 Community Relations

 Public Interest 1n the Mid-South Wood Products site during the Initial
 phases of the project was minimal.  The interest 1n the site increased
 moderately upon completion of the feasibility study.  The two-week  public
 notice period began on April 14, 1986.  This was followed by a public
 comment period which began on April  28, 1986, and ended on May 19,  1986.
 On May 8, 1986, a public meeting was held 1n Mena. Arkansas.  Approximately
 50 people attended the meeting to express their concern about the potential
 for EPA's plans for remedial action  resulting In the closure of the wood
 treatment facility now actively operating at the site.  Response to the
 comments received during the comment period and public meeting are  outlined
 1n the "Community Relations Responsiveness Summary" attached to this
 Enforcement Decision Document.


 Consistency With Other Environmental  Laws

 As specified in the EPA policy on compliance with environmental  statutes
 other than CERCLA, the alternatives  were developed to correspond to one
 or more of the following categories:

-1. Alternatives specifying offsite storage,  destruction,  treatment, or
    secure disposal of hazardous substances at a facility approved under
    Resource Conservation Conservation and Recovery Act (RCRA).  Such a
    facility must also be in compliance with  all other applicable EPA
    standards (i.e., Clean Water Act,  Clean Air Act, Toxic Substances
    Control Act).

 2. Alternatives that attain all  applicable or relevant Federal  public
    health and environmental standards, guidance,  and advisories.

 3. Alternatives that exceed all  applicable or relevant Federal  public
    health and environmental standards, guidance,  and advisories.

 4. Alternatives that meet the CERCLA goals of preventing or minimizing
    present or future migration of hazardous  substances and protect  human
    health and the environment, but do not attain  the applicable  or  relevant
    standards (this category may Include an alternative that closely approaches
    the level of protection provided  by the applicable or relevant standards).

 5. No action.

 The following alternatives for the Mid-South site correspond to  the above
 categories.  The alternatives corresponding  to categories 1 and  3 failed
 to meet the screening criteria and were not  evaluated in  detail  but are
 presented for comparison purposes only.

-------
                                    54

Alternative                      Category

No Action                           5
Topsoil-Clay Cap                    2
Mult1-Layer Cap                     2
Soil Treatment                      3
Onsite Landfill                     2
Offsite Landfill                    1
Combined Excavation/Capping         2
Groundwater Recovery/Treatment      2
Onsite Incineration                 3

It 1s EPA's policy to select a remedial  action that  attains  or exceeds
applicable or relevant and appropriate Federal environments  and public
health requirements.  Other Federal  criteria and  advisories, and State
standards may be used, with adjustments  for site  specific circumstances.

In the absence of cleanup standards, as  defined by regulations or health
advsories, a risk assessment should derive the concentration of contaminants
that represent an excess lifetime cancer risk that falls  within a target
range of 1x10-4 to 1x10-8 using 1x10-6 as a point of departure.

Standards have not been established for  known or  suspected carcinogens
such  as polynuclear  aromatic  hydrocarbons  (PAHs) which have been
identified as the primary contaminants providing  the "driving force" for
cleanup action at the site.  Therefore,  EPA's Carcinogen  Assessment Group
in Washington, D.C., has developed a model which  has been used to calculate
excess lifetime cancer risks for these contaminants.

Based on the use of this model to develop action  levels,  EPA would be
eliminating any direct contact with these contaminated soils.  This
approach is consistent with the intent of Superfund  to meet  applicable  or
relevant Federal regulations.


Compliance with Section 121 of SARA

Section 121 of the Comprehensive Environmental Response,  Compensation,
and Liability Act of 1980, as amended by the Superfund Amendments and
Reauthorization Act of 1986 (SARA), states that any Record of Decisions
signed within 30 days of enactment fo SARA must comply to the maximum
extent practicable with §121 of CERCLA (§121(g)).

The selected remedy for the Mid-South site includes  a RCRA compliant cap,
solidification of heavily contaminated wastes, groundwater recovery and
treatment, and extensive groundwater monitoring.   In the  process of selecting
the remedial alternative* a number of remedies were examined if accordance
with the National Contingency Plan, 40 CFR 300.68, and either screened  of
retained for final evaluation under 40 CFR 300.68(h).

The following examines the rationale used in screening remedial alternatives
for the site under the NCP, 40 CFR 300.68, and whether this  method resulted
in the selection of an appropriate remedy meeting the Intent of $121 of
CERCLA to the maximum extent practicable.

-------
                                    55

Biological Treatment

As viable treatment alternatives, biotreatment has not been shown to be
effective treatment technology for the wastes onsite and the probability
of failure of this remedy, resulting from wastes not amenable to such
treatments, 1s high.  The potential responsible parties conducted studies
on various forms of biological treatment; however, the results of the work
were Inconclusive.

In light of the lack of data to support the engineering practicability of
biological treatment and the risk of failure of this remedy, the promulga-
tion of §121 would not necessitate additional  scrutiny of this alternative.


Excavation with Onsite or Offsite Incineration

These alternatives were not selected as the site remedy under 40 CFR
300.68(1). Both would provides permanent remedies for the site.

Offsite incineration is comparable to onsite Incineration, but would
create added risks of exposure while the wastes were being transported
and require an extended treatment period.

Onsite incineration is a proven technology which would permanently destroy
the organic constituents of the wastes and therefore reduce the toxicity
and mobility of the contaminants.  However, considering that method used
for disposal of wastes at the site included mixing contaminants with clean
soil (effectively increasing the waste volume), the remaining ash would
still have considerable volume and may remain a hazardous waste since
metals contamination (i.e., arsenic and chromium) exists at the site.
Additionally, Incineration of the 80,000 cubic yards of wastes would
require a considerable treatment period.  During this period there would
be a significant increase in potontial for adverse health effects from
human exposure to the excavated wastes and possible accidental disruption
of the incineration leading to an increase in the risk of hazardous
emmlslons.

Furthermore, 1t 1s possible that the ash resulting from this form of
treatment could not be delisted and would have to be disposed of as a
hazardous waste.  Therefore, incineration as a treatment alternative for
this site would not be a required alternative under §121 of CERCLA.


Excavation and Offs1te,'D1sposal in a Permitted RCRA Facility

This  alternative was not selected as the site remedy under 40 CFR 300.68(1)
Under §121(b)(l), the offsite transport and disposal of hazardous materials
without [permanent] treatment technologies should be the least favorable
alternative remedeal action where practicable treatment technologies are
available.  This remedy is therefore unacceptible where other alternatives
are available.

-------
                                    56

RCRA Compliant Clay Cap

A RCRA compliant cap with stabilization of heavily contaminated soils,
groundwater recovery and treatment, and an extended monitoring program
was the selected remedy under 40 CFR 300.68(1).   The contaminants  will
remain onsite, and therefore under §121(c) the remedy will  have to be
reviewed "no less often than every 5 years after the Initiation of such
remedial action to assure that human health and  the environment are
being protected by the remedial  action being Implemented".

Wastes onsite will be stabilized and consolidated with lesser contaminated
soils then capped.  This will effectively reduce the mobility of the
wastes and reduced the relative toxidty resulting from direct contact.

A cap would greatly reduce infiltration from rainwater minimizing  offslte
migration of the contamination.  The groundwater recovery and treatment
operations will further reduce the possibility of migration of contaminants
Into the offsite shallow groundwater.  Extensive monitoring associated
with the selected remedy would illuminate problems enabling corrective
action to be taken expediantly.

The remedial  investigation for the site did not  indicate offslte migration
(based on present site boundaries).  Endangerment was associated with the
potential for a release and direct contact with  the wastes.  All applicable
or relevant and appropriate standards, requirements, criteria, or  limitations
shall be complied with as required for a remedy  in which wastes remain
onsite under §121(d).

Permanent remedies for the site were screened during the selection process
outlined 1n the NCP 40 USC 300.68.  However, since the permanant remedies
for the site do not meet the requirements of §121(b), advent of the new
law does not necessitate reevaluating the remedy selection in order to
comply with the congressional Intent of selecting permanent remedies when
it 1s practicable.

A capping remedy with stabilization of heavily contaminated soils, ground-
water recovery and treatment, and extensive groundwater monitoring complies
to the maximum extent practicable with §121 of CERCLA and therefore is  an
appropriate remedy for selection within the 30 day period following
enactment of SARA as required in §121{g).


Remedy
                      i
Section 300.68(1) of the NCP states that "the appropriate extent of
remedy shall be determined by the lead agency's selection of a cost
effective remedial alternative that effectively mitigates and minimizes
threats to and provides adequate protection of public health and the
environment."  To this end EPA has negotiated a remedy with the potential
responsible parties (PRPs) which includes EPA's Groundwater Recovery/
Treatment Alternative in combination with a remedial action plan that
will be summarized below.

-------
                                    57

As stated previously, upon conclusion of the feasibility study, EPA
approached the PRPs offering them an opportunity to conduct remedial
action at the site.  The parties expressed an interest in conducting  the
remedial  work.  Negotiations relative to an appropriate remedy have been
ongoing since June 1986.

EPA's position was that there were several areas of concern namely, the
continued migration of contaminated groundwater from the site; the continued
migration of contaminated soils form the site due to surface water runoff;
the continued contamination of groundwater from the heavily contaminated
areas including the Old Plant, Small Old Pond, CCA Plant and Old  Pond
areas; and the direct contact hazard posed by the site on the workers at
the wood treatment facility.

EPA's recommended remedial action included a combination of Alternative 6
(Groundwater Recovery/Treatment) and Alternative 7 (Combined Excavation/
Capping).

These alternatives would include:

0  Excavation of the heavily contaminated areas comprising the Old Plant,
   Small  Old Pond, CCA Plant, and Old Pond.

°*  Placement of these wastes in an onsite RCRA landfill.
0  Backfill, grade, and seed excavated areas.

0  Excavation of contaminated soils located along several  drainage pathways
   and consolidate with contaminated soil in the Landfarm area.

*  Construction of a RCRA top-soil clay cap over the landfarm area.

0  Completion of the groundwater recovery and treatment system.

0  Installation of a groundwater monitoring system to monitor the
   effectiveness of the remedy.

0  Runoff control at the CCA Plant.

0  Fencing of the site and deed restrictions.

After several negotiating sessions, EPA received a proposal from  the  PRPs
which was derived from a combination of the EPA's recommended remedial
action technologies discussed above.

The proposal calls for the following activities:

0  Excavation of all onsite and offsite contaminated soils, with  the
   exception of those existing in the Old Pond area, and consolidation  of
   the soils in the North Landfarm area.

0  The contaminated soils consolidated in the North Landfarm would
   be graded and covered with a RCRA top-soil clay cap.

-------
                                    58

0  Stabilization of any free oil, liquid, or sludge found in the
   heavily contaminated areas of the  Small  Old Pond and  Old Plant
   area (Stabilized waste from the Small Old Pond will  be consolidated
   with materials in the North Landfarm).

0  Field investigation into the Old Pond area to locate any free
   oils, liquids or sludges.  Insitu stabilization of these materials.

0  The Old Pond area would be covered with a RCRA top-soil  clay
  . cap.

0  Installation of a groundwater monitoring  system to monitor the
   effectiveness of the remedy.
o
   Backfill, grade and seed (or gravel  cover)  all  excavated  areas.
0  Remedial action at the CCA Plant (To be proposed by Mid-South  Wood
   Products of Mena, Inc. but will  be as effective, or more,  than EPA's
   recommended action).

0  Fencing and deed restrictions.

0 Completion of EPA's Alternative 6, Groundwater Recovery/Treatment,
  with the exception of the inorganics treatment system.  Any ground-
  water found to be contaminated with inorganics would be treated by
  the activated carbon system then used as makeup water for the CCA
  treatment process. .

As part of'this remedy the potential responsible parties will  have to
perform bench studies during the remedial design and provide EPA with
results that support the use of stabilization as part of this remedy.
If stabilization proves ineffective, an alternative approach will be
required for those heavily contaminated materials for which stabiliza-
tion has been proposed.

Cleanup Criteria

As stated above, EPA's Feasibility Study Report developed cleanup criteria
for arsenic (3 ppm) and chromium (10 ppm) based on the mean value of
these contaminants found in background samples.  On the other hand, the
action level for carcinogenic PAHs was derived from the EPA's Carcinogenic
Assessment Group lifetime cancer risk model.  EPA selected a 1x10-6
concentration for total carcinogenic PAHs (300 ppb) and entered into
negotiations with this platform.

The cleanup criteria resulting from PRP negotiations called for an action
level for arsenic and chromium to be set at any concentration that exceeds
the range of background concentrations (i.e., arsenic > 5.6 ppm and
chromium > 19.4 ppm).  The cleanup  requirements for total carcinogenic
PAH compounds (benzo (a) pyrene, benzo (a) anthracene, benzo (b)  Fluoranthene,
benzo (k) fluoranthene, and chrysene) will be set at a lifetime cancer
risk of 1x10-5 (3 ppm).

-------
                                    59

The remedial action plan has been thoroughly reviewed by EPA and each of
the technologies incorporated into this proposal  appear applicable for a
specific function as part of the overall remedial objectives to protect
human health and the environment at the site.

EPA policy regarding selection of a remedy that attains or exceeds appli-
cable or relevant and appropriate Federal  environmental  and public health
requirements appear to be satisfied by the negotiated remedy summarized
above.  This remedy will be constructed to meet the design standards for
a RCRA topsoil clay cap.  Additionally, any free liquids, oils, or sludges
will be excavated from the site and solidified prior to consolidation and
capping, to comply with the free liquid land disposal ban.  Also, It is
anticipated that the excavation, consolidation and capping activities can
be completed prior to November 8, 1988, the effective date of the ban on
land disposal of solvents.

The recommended alternative will also include a groundwater monitoring
program to determine if future conditions warrant additional remedial
action.

Costs of Remedy

The estimated capital cost of the remedy is approximately $3.5 million
for soil containment and groundwater recovery and treatment.  These costs
are based on estimates provided by the PRPs in their proposal.

Operations and Maintenance

Post-closure operations and maintenance (0 & M) costs have been estimated
at an annual cost of $153,500 or a present worth cost (based on 30 years
at a 10% discount rate) of $1,404,500.  The 0 4 M activities Include, but
are not necessarily limited to, groundwater monitoring, maintenance, site
Inspection and security, carbon regeneration, sludge and oil disposal from
the groundwater recovery system, electricity, and sampling and analysis.

Schedule

The schedule for the remedial design and construction of the selected
remedy for Mid-South 1s currently dependent upon reauthorization of
Superfund and the successful negotiation of a Consent Decree.  Assuming
Superfund funds are available the design phase will begin once the Consent
Decree 1s signed.  The design phase should take approximately 6 to 8
months to complete.

The balance of the remedial action will begin as soon as the remedial
design 1s completed and approved by EPA.  This phase of construction 1s
estimated to take 6 to 8 months to complete.

-------
Attachment 1

-------
t
                            COMMUNITY  RELATIONS RESPONSIVENESS SUMMARY
                               ON  PREFERRED  REMEDIAL  ALTERNATIVE
                             MID-SOUTH WOOD PRODUCTS,  MENA, ARKANSAS

            This  community  relations responsiveness  summary is divided into the
            following  sections

            I.    Overview -  This section discusses EPA's preferred alternative for
                 remedial action, and  likely  public  reaction to this alternative.

            II.   Background  on Community Involvement and Concerns - This section
                 provides a  brief history  of  site background and community interest
                 and concerns raised during remedial planning activities at the
                 Mid-South  site.

            III.  Summary of  Major Comments Received During the Public Comment Period
                 and the EPA Responses to  Comments

-------
I.  OVERVIEW
    An assessment of possible hazards  posed  to  public  health  or  the
    environment was completed In May 1985.   This  assessment evaluated
    the land use of the site; the types,  location,  and toxicity  of the
    contaminants found at the site, and the  potential  exposure and risk
    associated with these contaminants.  Results  of the  study Indicated
    that remedial action is required to reduce  the  potential  for public
    and environmental  exposure through:
        • ingestlon of contaminated soils;
        - direct contact with contaminated soils;
        - drinking contaminated groundwater;
        • drinking contaminated surface water;
        - Inhaling contaminated dust.
    In the presentation for the public meeting  at the  end of  the Feasi-
    bility Study (FS), the Environmental  Protection Agency  (EPA) dis-
    cussed the remedial alternatives which were examined in the  FS,
    for addressing the contamination at the  site, as follows:
        1.  No Action                              Est.  Cost: $   -  0 -
        2.  Excavation and Onslte Landfill          Est.  Cost: $  5.6  Million
        3.  Top Soil-Clay Cap                      Est.  Cost: $  2.4  Million
        4.  Multi-Layered Cap                      Est.  Cost: $  3.8  Million
        5.  Leaching and Biological  Treatment       Est.  Cost: $  4 to 8 Million
        6.  Excavation and Backfill  with            Est.  Cost: $  28.4 Million
            Offsite Landfill  Disposal
        7.  Groundwater Recovery and               Est.  Cost: $  1.6  Million
            Treatment
        8.  Combined Excavation/Capping            Est.  Cost: $  4.7  Million
    EPA's recommended remedial action  Included  a  combination  of  Alternative
    6 (Groundwater Recovery/Treatment) and Alternative 7 (Combined Excava-
    tion/Capping).  These alternatives would Include:
        - Excavation of the heavily contaminated  areas comprising the
          Old Plant, Small  Old Pond, CCA  Plant  and  Old Pond.
        - Placement of these wastes in an onsite  RCRA  landfill.
        - Backfill, grade, and seed  excavated areas.
        - Excavation of contaminated soils located  along several  drainage
          pathways and consolidate with contaminated soil in  the Landfarm
          area.

-------
                      -  Construction of  a RCRA top-soil clay cap over the landfarm
                        area.

                      -  Completion  of  the groundwater  recovery and treatment system.

                      -  Installation of  a groundwater  monitoring system to monitor
                        the  effectiveness of the remedy.

                      -  Runoff  control at the CCA Plant.

                      -  Fencing of  the site and deed restrictions.

              Subsequent to  several negotiating sessions with the potential responsible
              parties  (PRPs), Edward Hines Lumber Co., Inc., and Mid-South Wood Products
              of Mena, Inc., EPA received a proposal from the PRPs for a remedial action
              which was  derived from a combination of  the EPA's recommended remedial
              action technologies listed above.  This  proposal, in' addition to specific
              requirements made by  EPA,  has been accepted as EPA s preferred remedial
              action.

              The proposal combines the  following activities:

                      o   Excavation of all onsite contaminated soils, with the exception of
                         those  existing  in the Old Pond area, and consolidation of the
                         soils  in the  North Landfarm area.

                      o   Stabilization of any free oil, liquid, or sludge found in the
                         heavily contaminated areas of the Small Old Pond and Old Plant
                         area (Stabilized waste from the Small Old Pond and Old Plant
                         area will  be  consolidated with materials 1n the North Landfarm).

                      o   The contaminated soils consolidated in the North Landfarm would
                         be  graded  and covered with  RCRA topsoil clay cap.

                      o   Field  investigation into the  Old Pond area to locate any free
                         oils,  liquids or sludges.  Insitue stabilization of these
                         materials.

                      o   The Old Pond  area would be covered with a RCRA topsoil clay cap.

                      o   Installation  of a groundwater monitoring system to monitor the
                         effectiveness of the remedy.

                      o   Backfill,  grade and seed (or  gravel cover) all excavated areas.

                      o   Remedial action at the CCA Plant (to be proposed by Mid-South
                         Wood Products of Mena, Inc.,  but will be as effective, or more,
/.                        than EPA's recommended action).

                      o   Fencing and deed restrictions.

                      o   Completion of EPA's Alternative No. 6, Groundwater Recovery/
                         Treatment, with the exception of the inorganics treatment system.

-------
         o  Any groundwater found to be contaminated with inorganics
            would be treated by the activated carbon system and then used
            as makeup water for the CCA treatment process.

As part of this remedy, the potential responsible parties will  have to
perform bench studies during the remedial  design and provide EPA with
results that support the use of stabilization as part of this remedy.  If
stabilization proves ineffective, an alternative approach will  be required
for those heavily contaminated materials for which stabilization has been
proposed.

Additionally, since wastes will be left onsite, the remedial  action will
be reviewed every five years to assure that the remedy is still protect-
ing public health and the environment.


II.  BACKGROUND ON COMMUNITY INVOLVEMENT AND CONCERNS

     Site Background

     The Mid-South Wood Products site 1s a 57-acre wood treating facility
     located in western Arkansas, approximately 0.5 miles southwest of the
     City of Mena.  The site was operated as a pentachlorophenol (PCP) and
     creosote wood treating facility from the late 1930s to 1977, when a
     new wood treating facility, using a chromated copper arsenate (CCA)
     process, was built adjacent to the old site.  The CCA facility is
     currently being operated by Mid-South Wood Products of Mena, Inc.

     During early operations, waste products from wood treating were stored
     1n two old pond areas onsite.  In 1978, when the onsite waste ponds
     were closed, the pond liquid and sludge materials were pumped onto
     adjacent land to the west (landfarm areas) and mixed with the existing
     soils.  Some of the mixture was placed back in the ponds.

     The site has been under Investigation since 1976, when 1t was reported
     that Rock Creek and the Mountain Fork River suffered a fish kill
     8-1/2 miles downstream.  Subsequent to the fish kill, state and federal
     agencies began testing for the presence of chemicals in the ground-
     water, surface water, and soil.  Low levels of PCP, arsenic, and
     chromium were found in some groundwater and surface soil samples.  In
     1982, the site was placed on the National Priorities List (NPL) for
     hazardous waste sites remedial action under the U.S. Environmental
     Protection Agency Superfund Program.
                     i
     Major Concerns and Issues

     City and county officials, agency staff, and local residents Indicate
     that concern about the site is for the most part focused  1n the
     Immediate vicinity of the site.  Concern 1s also primarily related
     to  economics in the area  which would be greatly affected,  should the
     Mid-South Wood Products facility be shut down.  Although Mena and
     Hatfleld residents are generally aware of the site, remedial action
     is  not seen as a community-wide issue in either city.

-------
                                           12

          Most carcinogens do not have a simple concentration promulgated as a
          standard.  Therefore, EPA must select a cleanup level  relative to a
          desired excess lifetime cancer risk level.  When assessing an appropriate
          risk level for a particular site, to serve as the basis for remedial
          action, EPA uses 1x10-4 to 1x10-7 as the target range and 1x10-6 as a
          point of departure.

          In the Feasibility Study Report EPA derived an action  level  to limit  human
          exposure to contaminated soils.  This derived value is based upon
          extrapolations from animal toxicity experiments to human health effects
          1n order to estimate a reasonable level of risk for the contaminants
          present onsite.  The FS Report uses a 1 x 10-6 excess  lifetime cancer
          risk as Its action level.  However, a 1x10-5 risk level can be considered
          for use as the cleanup criteria based no the conditions Inherent to the
          site.

          EPA's Carcinogen Assessment Group has a desired model  which 1s used to
          calculate excess lifetime cancer risks.  EPA acknowledges the fact that
          their may be uncertainties inherent in the calculation of these risk
          values.  These uncertainties may act to either Increase or decrease risk,
          depending on the source of the uncertainty.  The uncertanties were taken
          Into account when the Endangerment Assessment was prepared for the Mid-
          South site.  In assessing all available information EPA established a
          cl-eanup level for the Mid-South site that 1s unlikely to result in a
          public health or environmental problems.

          8)  HINES LUMBER COMPANY

          The FS proposes to apply the risk level for BaP'to the aggregate of the 5
          carcinogenic PAHs, being, in addition to BaP, benzo(a)anthracene,
          benzo(b)fluoranthene, benzo(k)fluoranthene, and chrysene.  To date, BaP
          is the only carcinogenic PAH for which the toxicological data have been
          adequate, In the judgment of EPA, to allow the agency  to derive a quantitative
          criterion.  The quality of scientific data for the remaining four carcinogenic
          PAHs has been deemed as inadequate to promulgate official agency criteria.
          Nevertheless, there 1s sufficient data to determine that these compounds
          are, for the most part, substantially less potent carcinogens than BaP.

          For example a recent review by the EPA Environmental Criteria and Assessment
          Office showed that benzo(b)fluoranthene was about 10%  as potent as BaP,
          and chrysene was about 1% as potent.  (EPA 1982 Errata: PAH Ambient Water
          Quality Criterion for the Protection of Human Health,  page 24).

          A reasonable approach for the Mid-South site would be  to accept the fact
          that BaP 1s the most potent of the 5 carcinogenic PAHs, that chrysene 1s
          the least potent and to establish a separate cleanup criterion for BaP.
          In the particular situation at the Mena site, using a  10-5 risk level,
          this would mean 3 ppm for BaP, and 30 ppm for the total of the 5 carcinogenic
          PAH.
t

-------
                                  13

 EPA RESPONSE:

 EPA acknowledges  that  benzo(a)  pyrene may be the most potent carcinogen
 of the PAH family of compounds.  However, as indicated  in the above comments,
 there 1s a lack of promulgated  regulations pertaining to the remaining four
 carcinogenic PAHs.  In light  of this fact, the  Agency is reluctant to con-
 sider your recommendation  and is more Inclined  to adopt an action level
 that assures adequate  protection of public health and the environment.

 9)  HINES LUMBER  COMPANY

 The estimates  of  contaminated yardage associated with the various areas
 on the Mid-South  property  are shown 1n  numbers  that Indicate a far higher
 degree of precision and accuracy than 1s warranted.  These estimates
 should be expressed in round  numbers with the likely upper and lower
 range.  A more reliable estimate will be developed during the preparation
 of the remedial action plan and engineering specifications.

 EPA RESPONSE:

 The Feasibility Study  may  not present an upper  and lower range; however,
 the excavation volumes are presented as estimates (e.g.., 80,000 cubic
 yards for the  Excavation and  Offsite Disposal alternative).

10)  HINES LUMBER  COMPANY

 According to the  FS, a soil-clay cap is calculated to reduce infiltration
 by "over 70 percent" as compared with the present conditions at the site
 (FS page 5-17).   For a combination of synthetic membrane and soil-clay
 cap, the reduction in  Infiltration is estimated to be greater than 90
 percent (FS page  5-15). Unfortunately, no substantiation 1s provided to
 allow a review of these two infiltration estimates.  However, 1t 1s clear
 that both values  are far too  low, probably by at least 4 orders of magnitude,
 i.e. 10,000.  In  other words, the reduction 1n  Infiltration achieved by a
 cap Installed  in  accordance with the specifications outlined in the FS
 (FS page 5-11), over the present situation, 1s  almost certainly greater
 than 99% under either  the  synthetic membrane or soil-clay cap option.

 There are two  major factors responsible for the reduction of Infiltration:

 a.  The low permeability (10-7  cm/sec)  of the final engineered cap as
 compared with  the present  situation, which consists of  unconsolidated
 native soils with a permeability estimated at between 10-4 and 10-5
 cm/sec   The engineered cap would thus  have a permeability at least 100
 times less than the present, situation;  and

 b.  The FS stipulates  that the  cap must be graded with  positive slopes of
 between 3 and  5%  at the top and less than 20% on the sides.  The permeability
 values used above refer to a  static situation where water would be ponded
 on the soil.  Under that condition, a 10-7 cm/sec would allow the water
 to penetrate the  cap at the rate of about one inch per  year.  However,
 because of the positive slopes  of the cap, there will be no situation

-------
                                 14

whereby water could remain ponded on the surface of the cap.  The slopes
of the cap are designed to cause all water to promptly run off.   It is
conservatively estimated that the fact that the water will  not be able to
penetrate the cap at even the one inch per year rate implied by  the
static permeability test, will further reduce the potential  infiltration
by at least another two orders of magnitude, i.e., 99%.

EPA RESPONSE:

The.Feasibility Study is not a design document.  This report was developed
based upon the results of the site investigations and it presents the
development and evaluation of remedial action alternatives  that  could
be implemented to eliminate or minimize the threat to public health and
the environment.  If capping is a part of the remedy selected for the
site, then a more precise infiltration rate will be calculated as part of
the Remedial Design.

11) MINES LUMBER COMPANY

According to the FS, both the engineered soil-clay cap (page 5-17) and
the combination synthetic membrane and soil-clay cap offer similar improvements
over the present situation, i.e. a reduction of infiltration because of
the very low permeability (10-7 cm/sec) of the sloped final  cover.  The
difference between the two materials in effectively reducing infiltration,
i.e. 70% for the soil-clay compared to 90% for the synthetic liner is not
explained, and, as discussed above does not appear to be justified.  In
any case, the clay and the synthetic membrane will achieve a similar
reduction.  It is likely that the synthetic membrane will  be both more
costly and shorter lived than the clay which is a natural  material, less
susceptible to failure and far easier tc repair, should that be  required.

EPA RESPONSE:

The 70% and 90% figures were determined by EPA's contractor.  These
values were based upon their experience with the actual operation of such
structures as opposed to a theoretical derivation.

The synthetic membrane liner is a proven technology.  If adequate operation
and maintenance is provided, then it should provide greater protection
from infiltration than the top-soil clay cap alternative.

12)  NINES LUMBER COMPANY

The advantages, 1f any of Alternative 3, Multi-Layer cap over Alternative
2, Topsoil-Clay cap, are not documented in the FS.   It is unlikely that a
convincing demonstration can be made of incremental reductions in risk
commensurate with the $1.4 million additional cost for the synthetic
membrane.

-------
                                 15

13)  HINES LUMBER COMPANY

By the same token, the FS does not demonstrate the additional  advantages,
if any, of Alternative 6, Combined Excavation/Capping as  compared  with
Alternative 2, Topsoil-Clay cap.  The additional  cost would be $2.2 million.

EPA RESPONSE:

The Feasibility Study does in fact compare the alternatives in Chapter  6,
entitled "Comparative Evaluation of Alternatives."


WRITTEN COMMENTS PROVIDED TO EPA DURING THE PUBLIC MEETINGS (MAY 8, 1986)

EPA's response follows each question, comment, or concern raised in each
written statement or group of similar statements.

The major Issues of concern that were raised during the public meeting
and provided in written statements to EPA during  the meeting are summa-
rized below:

(1)  Alderman, Position 12, Waldron, Arkansas, Mr. Butch  Johnston

     "Many people in this area are dependent on Mid-South in Mena  for
     their jobs ... When considering alternatives to the  problem at the
     Old Mid-South location please don't jeopardize the jobs currently
     provided..."

(2)  Resident of Waldron, Arkansas, Ms. Regina Oliver

     "When considering a solution for the cleanup at the  old Mid-South,
     please help keep the current Mid-South facility in operation".

(3)  Resident of Waldron, Arkansas, Ms. Sherry Johnston

     "... any solution that Inhibits the operations at the current Mid-
     south location would create a long reaching economical problem in
     this area".

(4)  Resident of Waldron, Arkansas, Mr. L. J. Watkins

     "... your consideration of a remedial altaernative that will  allow
     the continued day-to-day operation of Mid-South Wood Products, Inc.
     and that will minimize its economic and financial Impact upon all  of
     as involved is expected and will be greatly  appreciated".

(5)  President and Chief Executive Officer, First National Bank, Mena,
     Arkansas , Mr. Bert Hensley
     "In considering an alternative to this problem, I would hope  that
     you could find a remedy which would not affect the normal business of
    •the company or the employee job secruity.  A change  would tremendously
     affect our community and its economy."

-------
                                    16
(6)  Written statement signed by approximately 346 residents  provided
     by Mr.  Phillip Clay,  attorney  for Mid-South  Wood  Products,  Inc.
     M
      Please consider when choosing a remedial  alternative,  to  this
      problem, a solution that  will  not  interrupt the  normal business  of
      Mid-South so that jobs will  not be temporarily or  permanently  lost."

EPA RESPONSE:

     It Is not the intent of EPA to close the current  facility.  What
     we are interested in is taking remedial action  primarily in the
     Inactive areas which exist around the present treatment facility.
     There are two potentially  responsible parties,  Mid-South Wood
     Products, Inc. and Edward  Hines Lumber Co., who share potential
     liability and cost of any  such cleanups.

     With respect to the active facility, there are  certain  remedial
     measures which must be taken  to address the problem of  storm water
     runoff.  We believe that there are  contaminants migrating  from  the
     current facility and contributing to an existing  groundwater
     contamination and surface  water runoff problem.

(7)  Resident of Mena, Mr. David Stewman

     "I own four acres bordered on three sites  by Mid-South  and I have
     never been contacted by the EPA. Why?"

     "My property has a well about 75 feet from Mid-South property.  Has
     it been tested?  If not why?"

     "If work 1s done on Mid-South property by  the EPA or their con-
     tractor(s) will the EPA be responsible 1f  my property 1s adversely
     affected?  If not why?"

     "Does the EPA have the name(s) af anyone who has  been harmed by the
     Edward Hines Lumber Co. or Mid-South operation?"

EPA RESPONSE:

0 Mr. Stewman was never contacted  because there was  never a  need to
  contact him.  The Mid-South site does  not pose  as  a  threat of contam-
  ination to Mr. Stewman's property since it 1s located  to the  northeast
  or upgradient of areas of contamination found during the site Invest-
  igation.

0 No, Mr. Stewman's property has never been sampled.  Sampling  was done
  onslte that Indicates no contamination in areas  adjacent to  his property,

-------
                                    17
          w

0 Yes, EPA 1s responsible for work done by its contractors.   Also,  the
  Potential  Responsible Parties are responsible for work  performed  by
  their contractors.

0 EPA has no names of individuals who have been harmed  by the site  other
  than the problems associated with those properties to the  northwest  of
  the site which were eventually provided with alternate  water supplies.
  (See page 2 of the Responsiveness Summary)

CONCERNS RAISED DURING THE PUBLIC MEETING (MAY 8,  1986)
The major issues of concern that were raised  during the public meeting
are summarized below:

0 Will the Mid-South facility be closed as a  result of  this  action?

0 The people are not against cleaning up the  environment; however,  they
  are worried about losing the jobs provided  by Mid-South, and the  potential
  economic impacts on the City of Mena and Mr. Jim Huff (President  of  Mid-
  South).

0 Who will pay for the remedy?

0 How will the cleanup affect the surrounding property?

0 What has the study cost?

0 Why is Mid-South responsible for something  ft had nothing  to do with?

0 What happens after the public meeting?


EPA RESPONSE (presented in the same order as  indicated  above):

0 It 1s not the intent of EPA to put Mid-South out of business.  It is
  our intent, however, to take those actions  deemed necessary to  protect
  public health and the environment.

0 The apportionment of cost for any remedy that may be  selected for the
  site will  have to be worked out between the two Potential  Responsible
  Parties, Mid-South Wood Products, Inc., and Mines Lumber Company.

0 Any remedial alternative that is selected,  with the exception of  the No
  Action Alternative, will include the excavation  of contaminated soils
  located to the southwest of the site in an  Isolated,  non residential,
  area.  During any remedial activities sufficient measures  will  be taken
  to insure that there is no negative impact  on adjoining properties.

-------
The level of concern about the site was higher in the 1970s than it is
today.  However, there is still  concern about the groundwater and harmful
dust. As stated previously, however, the biggest concern is economics in
the area.

Activities to Elicit Input and Address Concerns

The Arkansas Department of Pollution Control  and Ecology (ADPC4E) is the
lead state agency for hazardous waste issues  in Arkansas.   The ADPC&E
became involved at the site 1n 1976 during its Investigation of the fish
kill in Mountain Fork.  ADPC&E was again involved in  1978.   The ADPC&E
established requirements to be met, including dismantling of an illegal
valve used for discharging holding pond liquids into  a tributary of Rock
Creek and development of a "closed system" for waste  management.  Between
1978 and 1984, the ADPC&E conducted a series  of onsite inspections,
tested soil and water samples, and worked with the USEPA and site owners
in identifying addditional investigative activities to be conducted.

Subsequent to each of the formal studies conducted by the EPA, the Remedial
Investigation and the Feasibility Study, copies of the documents outlining
these studies were placed in strategically located repositories for
review and comments from the public.  A public comment period was held at
the end of the Feasibility Study, from April  28, 1986, through May 19,
1986.  During this public comment period, a public meeting  was held on
May 8, 1986, to explain results of the Feasibility Study and to hear
comments on the remedial alternatives.
III.  SUMMARY OF PUBLIC COMMENTS RECEIVED DURING PUBLIC COMMENT PERIOD
      AND AGENCY RESPONSES

CONCERNS RAISED DURING THE PUBLIC COMMENT PERIOD
(April 28 - May 19, 1986)

The following summarizes the major issues raised in  written  statements
provided to EPA during the public comment period.

EPA's response follows each comment or group of similar comments.

1)  HINES LUMBER COMPANY

It 1s most Important that all discussion and diagramatic representations
that pertain to the present configuration and alignment of the site
boundaries be checked to ensure that they accurately reflect the property
acquired by the Edward Hines Lumber Company ("Hines").   For  example,
figure 1-2 gives the false impression that Pope Pond  and Moon Springs
are offsite locations, whereas they are both within  the present boundaries
of the site.

-------
EPA RESPONSE:

EPA acknowledges the comment and will  make every effort  to  represent  the
site in its present configuration and alignment of property boundaries  in
any future EPA documents.

2)  HINES LUMBER COMPANY

Since Hines took title to the former Pope and Moon properties,  no
location has been identified where there is contamination that  has  been
transported via the groundwater route.  Neither the Remedial  Investigation
(RI) nor the sampling by B & F Engineering, consultants  for Hines,  has
detected any groundwater contamination beyond Moon Spring,  a location
which 1s on property owned and controlled by the Potentially Responsible
Parties (PRPs).  The only location beyond the present  property  boundaries
where some contamination has been detected 1s a small  area  near the
railroad tracks to the southwest of the site.  That contamination was
transported by a surface flow as the result of an Inadvertent release
from the former pond (RI page 8.0-8).  That pond, along  with all other
former impoundments has since been closed.

EPA RESPONSE:

At the request of Mr. Pope, ADPC&E obtained water samples 1n November,
1980, from the Pope's well and sediment samples from near Pope  Pond.  The
results of these test were reported as:

                           Results of Analyses*

                                                                     Soil
              Water            Water        Soil        Soil     Drainage
              Kitchen          Pump       West of       Pope       from
              Faucet           House      Mid-South     Pond     Mid-South

PCP            0.036 ppb        0.063 ppb   118 ppb      232 ppb     1335 ppm
Arsenic       14 ppb          < 5 ppb      1086 ppb      115 ppb
Chromium       8 ppb          < 5 ppb        60 ppb        46 ppb

* ppb - parts per billion; ppm - parts per million

Subsequent to receiving these results, the Popes connected  to City  of
Mena water system.

In February, 1981, the U.S. EPA sent a two-man team to the  site. Water
samples were taken by the team from the Pope, Hilton, McMellon, and
Melrose wells (Figure 2.2-2).  With the exception of the Hilton well
which had a  PCP concentration of 10 ppb, chrome, arsenic, and PCP were
not detected.  About the same time, the Arkansas Health  Department  obtained
water samples from Pope Pond, Moon Spring  (west of the Pope property) and
Frost, Hilton, and Melrose wells.  The results of analysis  on these
water samples are:

-------
                            Moon         Frost     Hilton       Mel rose
                            Spring       Well       Well          Well

PCP           47 ppb     1,400 ppb       Trace     Trace        Trace
Arsenic       37 ppb         5 ppb     < 5 ppb   < 5 ppb      < 5 ppb
Chromium      85 ppb       < 5 ppb     < 5 ppb   < 5 ppb      < 5 ppb

In 1984 several private wells along Hghway 375 were sampled by EPA;
however no groundwater contamination was found (RI, page 2.0-6).

Regardless of the comments made by Hines there 1s a significant ground-
water contamination problem onsite.  Furthermore, field  Investigations
referenced above do Indicate that groundwater  contamination has been
found beyond Moon Spring.   In light of this fact, EPA developed  a ground-
water remediation strategy which is addressed, as proposed by alternative
7, in the Feasibility Study Report.

In reference to the statement concerning contamination found offsite
along the railroad tracks to the southwest of  the site.   The Remedial
Investigation Report identifies groundwater and surface  water routes  to
the southwest from the highly contaminated areas onsite.  Therefore,  the
past release may not be the sole contributor to contamination in  this area.

3)  HINES LUMBER COMPANY

The Feasibility Study ("FS") should give more  recognition to the  crucial
fact that the hydrogeology at the site makes 1t highly unlikely that
contaminants could migrate off the site via the groundwater.  The FS
confirms that M. . . the soils onsite have low hydraulic conductivities
and limited capacities to transmit water."  (FS page 1-12 and RI  page
8.0-11).  With the purchase of adjoining downgradient properties  by
Hines, the sole identified groundwater pathway, represented by the fault/
fracture zone, has been contained totally onsite.  Any groundwater in the
fracture zone 1s now recovered and treated by  an engineered system that
has been operating since October 1985.  Furthermore, as  mentioned in  the
FS, voluntary action by Hines "... has effectively removed all  known
downgradient groundwater usage ..." (FS page 115).

EPA RESPONSE:

The statement "... the soils onsite have low hydraulic conductivities and
limited capacities to transmit water" 1s a correct statement; however,
the surface soils should not be used to describe the potential  for ground
water migration at the Mid-South site.  The Remedial Investigation Indicates
"The residual soils in the valley area are up  to 6 feet  thick and average
2 to 3 feet thick in most areas" (RI, page 5.0-11); however, the  primary water
bearing zone 1s found at a depth of 10 - 30 feet beneath the surface  in
the fractured rock regime (RI, page 7.0-16).  The primary impact  of surface
soil on groundwater flow is with respect to recharge of  the water bearing
zone.

-------
                                 8

Furthermore, the groundwater migration pathway along the fault/fracture
zone is not the "sole" groundwater pathway as indicated in the Hines comment
EPA found potential groundwater migration pathways to exist to the south
- southwest along the railroad tracks and to the east from the CCA plant.

4)  HINES LUMBER COMPANY

The statement "the proposed float or liquid level  controlled pump  switches
are not being used and the liquid levels in the trenches are not being
kept below the lateral collector pipe inverts" (FS page 3-22)  is not
correct.  Also, the oils & sludges are removed from the wells.

The statement "free oils and sludge from the existing french drains were
found to quickly clog the activated carbon system during the demonstration
project" is not correct.  There was a problem with silt from the wells
clogging the cloth filter ahead of the activated carbon system during the
first few weeks of operation.  A second filter has been added in parallel
and this is no longer a problem.

EPA RESPONSE:

The statement made in the Feasibility Study Report is based upon an
inspection of the existing groundwater recovery system which was conducted
in November 1985.  At the time of the inspection the groundwater recovery
system was not operating correctly.

5)  HINES LUMBER COMPANY

Concentrations of heavy metals in the native soils of the Caddo Basin,
Ouachita Mountain region, in the general vicinity of Mena, have been
inadequately characterized in the RI.  As a consequence neither the
Endangerment Assessment ("EA") nor the FS give sufficient attention to
the fact that relatively high concentrations of chromium (Cr)  and  arsenic
(As) are present in the native soils around the Mid-South site. The RI
report documented the fact that Cr levels as high as 18.4 ppm and  19.4
ppm, and As levels of up to 5.6 ppm were measured in the background
samples collected 3 inches beneath the surface (RI page 7.0-22).   However,
the EA and FS derive a median value for Cr of 11.4 ppm and for As, 3 ppm
(FS table 2-1 and page 3-10).

The use of median or average values to represent background (uncontaminated)
levels, and certainly their extrapolation into target levels for cleanup,
1s Inappropriate.  As 1s evident from the limited data, natural background
levels for these metals considerably exceed the median values.  Furthermore,
total metal concentrations should be considered only for the hazard
associated with the ingestion of wind-blown dusts, I.e. surface soils
(whereas background samples were collected 3 Inches below the surface).
For considering the potential risk to groundwater off the property, the
relevant unit of measure should be the concentration of Teachable  Cr and
As, as determined  by the EPA stipulated EP toxicity test.

-------
Figures 2-1 and 2-2 which show As and Cr levels in the soil  are
seriously misleading for several  reasons:

a.  they are based on the use of median values for background
concentrations in the native soils and do  not take into account the
variation in these naturally-occurring concentrations; and

b.  they are based on samples collected at depths  on the site
that were different from the depths used offsite.

For the above reasons, only the areas of higher concentrations than
background should be considered as posing an incremental risk, and therefore
as candidate areas for remedial action.  Concentrations of As and Cr that
fall within the range of natural  background should not be considered as
posing a significant additional risk to human health or the  environment.

EPA RESPONSE:

The use of an average background concentration for arsenic and chromium
for cleanup criteria may be inappropriate due to the small number of
background samples collected and the wide  range of results.   Therefore,
EPA will consider using an action level of any concentration above the
range of background concentrations found during the remedial  investigation
(I.e., arsenic > 5.6 ppm and chromium > 19.4 ppm ).

Regarding soil collection procedures, surface-soil  samples are collected
by extracting soil from the 0-3 inch depth, not at a depth of 3 inches
beneath, the surface of the siol,  as indicated in your comment.

In response to the comment suggesting that the EP Toxicity procedure
be used for "considering the potential risk to groundwater...", the
EP Toxicity procedure was not developed to aid in the development of
cleanup standards.  This is an extraction  procedure which is used to
characterize wastes (with the understanding that any waste material
that does not exhibit the characteristic 1s not necesarily non-hazardous.

Based upon a comparison of the areal distribution of soils contaminated
with arsenic to those contaminated with total PAHs at a concentration
greater than 300 ppb (soil cleanup criteria described 1n the FS Report)
the above recommendation would not significantly affect the  total surface
area which would require excavation under any given remedial alternative.
Furthermore, preliminary calculations Indicate that Increasing the cleanup
criteria for arsenic to 5.6 ppm would not  significantly affect the amount
of soil requiring excavation.

6)  NINES LUMBER COMPANY.

The FS report states that "... organic carcinogens [PAH group] are not
present in natural soils, therefore the 10-6 Increased cancer risk level
will be applied to the carcinogenic PAH's."  (page 3-10).

-------
                                 10

The premise that the carcinogenic Polynuclear Aromatic Hyrdocarbons
(PAHs) do not occur in natural  soils is not correct.   In  fact,  the situation
is exactly the opposite, as has been thoroughly documented.   For example,
a recent EPA report has the following introduction  with regard  to benzo(a)
pyrene (BaP), the most potent carcinogenic member of  the PAH family  of
compounds:

     "The ubiquitous presence of BaP in the environment has  been docu-
      mented in U.S. EPA (1980)...  Human exposure occurs primarily
      through ingestion of food, followed by inhalation and  the consump-
      tion of water.  From the data presently available,  it  should be
      assumed that a large prtion, if not all,  of the human  population
      will be exposed to BaP in their daily activities."

(U.S. EPA 1982.  Errata:  PAH Ambient Water Quality Criterion for the
Protection of Human Health.)  PAHs are products of combustion,  and are
therefore present in the environment as a result of vehicle  emissions,
agricultural burning, forest fires, wood stove smoke, cigarette smoke,
to mention just a few sources.  PAHs identical  to those found in creosote,
are also common in asphalt used for highway paving, roofing  tars, tire
rubber, and municipal sewage sludge and effluent from treatment plants.

Because the PAHs are typically released in the form of particulate
matter 1n the atmosphere, and because they absorb very effectively to
soil, they will tend to be found in the upper layers  of surface soils.
One reason that these PAHs were not detected in the few background soil
samples that were analyzed may lie in the fact that the samples were
collected under the top 3 Inches, whereas the PAHs  would  tend to concentrate
at or near the surface of the soil.  In fact, according to the  EA (page
218), significantly higher levels of BaP were found offsite  than onsite,
namely up to 1,700 ppb as compared to only trace.  The level  confirmed by
this one PAH compound offsite is 600% higher than the cleanup criterion
proposed in the FS for the combined total of 5 PAHs.

EPA RESPONSE:

The statement in the Feasibility Study "... organic carcinogens (PAH
group) are not present in natural soil." 1s a correct statement in the
context 1n which 1t 1s presented.  The Feasibility Study does not Infer
that PAHs do not or may not occur naturally in the environment.  What  it
does Indicate 1s that background samples were collected and  analyzed and
no PAHs were found in these samples.  Furthermore, as Indicated in the
above comment by Hines, the Endangerment Assessment does reference an
offsite location wherje benzo (a) pyrene  (the most potent carcinogen
member of the PAH family) was found at a level  of 1700 ppb which 1s, as
stated above, 600% higher than the cleanup criterion  proposed in the
Feasibility Study for total PAHs.  However, it should also be pointed
out that the location of this extremely  high level of contamination  was
1n the area offsite, to the southwest of the site, which is  considered
contaminated and is thought to  receive surface and ground water drainage
from the site.  Additionally, the soil sample (representative of the

-------
                                 11

1,700 ppb benzo(a)pyrene)  was collected at a depth of 1.3  feet  below the
surface; therefore, any inference that the presence of benzo(a)pyrene is
naturally occuring, based  upon comments presented  by Hines,  would  be
difficult to substantiate.  This area is considered contaminated and is
included 1n all remedial  alternatives outlined  in  the Feasibility  Study.

7)  HINES LUMBER COMPANY

The risk level that is proposed in the FS for the  carcinogenic  PAHs,
namely 1x10-6 is excessively conservative for the  particular situation
encountered at the Mena site and a 1x10-5 risk  level  would be more
reasonable based on the facts documented in the EA report, in particular:

a.  There 1s essentially no risk to the community  from potential exposure
to contaminated drinking water, because the town and all  of  the proximate
downgradient dwellings are served by a municipal utility  system that
draws on a surface reservoir upstream of the site.  The EA states  "...
there are no nearby domestic groundwater users",   (page 3-6);

b.  The principal risk pathway .Identified in the EA 1s exposure to windblown
dust, however, despite the fact that far higher levels of  BaP,  the most
potent carcinogen, were found offsite as compared  to onsite  (EA page
2-18) no evaluation was made of the background  risk associated  with BaP
and similar PAH compounds; and

c.  The assumption made in the EA that 100% of  the contaminant  present on
the soil would be biologically available and the estimated rate of ingestion
by humans, are extremely conservative (EA page  5-25).

In a recently proposed regulation on the subject of the appropriate risk
level at a particular site that should serve as the basis  for a remedial
action, EPA outlined a framework for determining the level of risk to
be permitted post cleanup.  (U.S. EPA Hazardous Waste Management System;
Land Disposal Restrictions; Proposed Rule.  Federal Register, January 14,
1986, pages 1602-1766.  Refer to page 1635.)
Applying the procedure proposed by EPA in conjunction with the  site-specific
conditions prevailing at the Mid-South site and the facts  described in
the EA, it seems reasonable to base the cleanup criteria  for the protection
of human health in Mena on a 1x10-5 risk level.

EPA RESPONSE:

The Endangerment Assessment was designed to address two scenarios, Indus-
trial and residential,'  The Industrial scenario essentially  leaves the
site in Its current state and workers are exposed  to contaminated
surface waters and surface soils through Ingestion, Inhalation  of  dusts,
or dermal contact with soil or water on a dally basis. The  other  scenario
1s represented as a "worst case" scenario and it assumes  that the  site 1s
developed for residential  use and residents would  be exposed through
ingestion of groundwater, surface soils, subsurface soils  or sediments,
or by dermal contact with groundwater, surface  water, surface soils or
sediments.

-------