* •
            United States
            Environmental Protection
            Agency
                     Office of
                     Emergency and
                     Remedial Response
EPA/ROD/ROC-90/054
November 1989
PA   Superfund
       Record  of  Decision

       Hardage/Criner, OK
                                               UsJfi.'jiii ?
     x
     \

-------
50272-101
 REPORT DOCUMENTATION
        PAGE
                        1. REPORT NO.
                         EPA/ROD/R06-90/054
                                                                    3. Recipient1* Accession No.
 4. Title and Subtitle
   SUPERFUND RECORD OF DECISION
  pardage/Criner,  OK
   'irst Remedial  Action  (Amendment)
 7. Author(s)
                                                                   S. Report Date
                                                                     11/22/89
                                                                   8. Performing Organization RepL No.
 9. Perionning Organization Name and Addreee
                                                                   10. Project/Taak/Work Unit No.
                                                                    11. Contract(C) or Grant(G) No.

                                                                    (C)

                                                                    (G)
 12. Sponaoring Organization Name and Addree*
  U.S. Environmental Protection Agency
   401 M Street,  S.W.
  Washington,  D.C.   20460
                                                                   13. Type of Report & Period Covered

                                                                       800/000
 15. Supplementary Notea
 16. Abstract (Limit: 200 words)
 The Hardage/Criner site is  in an agricultural area near  Criner, McClain County, in
 central Oklahoma.   The site is situated  in  the North Criner Creek drainage basin,
 approximately  0.8  miles from the confluence of North Criner Creek and Criner Creek.   From
 1972 to 1980 the  site was operated under a  State permit  for the disposal of industrial
 wastes  including  paint sludges and solids,  ink solvents,  tire manufacturing wastes,  oils,
        solvents, cyanides, and plating wastes sludges.  Waste disposal practices have
           in the contamination of approximately 70 acres  of ground water beneath and
 adjacent to the site as well as several  acres of surface soil.  The principal source of
 contamination  is  approximately 278,000 cubic yards of sludges, waste  drums, highly
 contaminated soil,  and waste liquids contained in three  main waste  (source) areas near
 the center of  the  property.   Additional  source areas include scattered mixing ponds,
 spill areas, and  runoff paths in the vicinity of the main source areas.   Dense
 non-aqueous phase  liquids have pooled beneath the disposal areas and  are a continuing
 source  of contamination to  the ground water.   A 1986 Record of Decision addressed source
 control through incineration,  stabilization,  and onsite  disposal; however, the remedial
 action  was never  implemented due to protracted litigation.   The 1989  ROD Amendment
 provides a comprehensive site remedy addressing both source control and ground water
 remediation and takes into  consideration recently enacted land disposal restrictions.
 The primary contaminants of concern affecting soil, debris,  (Continued on next paqe)
                                          OK
17. Document Analysis a. Descriptor*
  Record of Decision -Hardage/Criner,
  First  Remedial  Action  (Amendment)
  Contaminated Media:   soil, gw
  Key Contaminants:   VOCs  (benzene,  PCBs, PCE,  TCE), other  organics  (pesticides),
  metals (arsenic,  chromium, lead)
  b. Identifiers/Open-Ended Terms
   c. COSATI Reid/Group
   Availability Statement
                                                     19. Security Ctas* (This Report)
                                                            None
                                                     20. Security Cla** (This Psge)
                                                            None
                                                                              21. No. of Pages
                                                                                   260
                                                                              22. Price
(See ANSI-Z39.18)
                                      See Inatructiona on Reverse
                                                                              OPTIONAL FORM 272 (4-77)
                                                                              (Formerly NTIS-35)
                                                                              Department of Commerce

-------
	DO NOT PRINT THESE INSTRUCTIONS AS A PAGE IN A REPORT


                                                      INSTRUCTIONS
 Optional Form 272, Report Documentation Pag* la baaed on Guideline* for Format and Production of Scientific and Technical Reports,
 ANSI Z39.18-1974 available from American National Standards Institute, 1430 Broadway, New York, New York 10018.  Each separately
 bound report—for example, each volume in a multlvolume Ml—shall have Its unique Report Documentation Page.

  1.   Report Number.  Each Individually bound report shall carry a unique alphanumeric designation assigned by the performing orga-
      nization or provided by the sponsoring organization in accordance with American National Standard ANSI Z39.23-1974, Technical
      Report Number (STRN). For registration of report code, contact NTIS Report Number Clearinghouse, Springfield, VA 22161.  Use
      uppercase letters, Arabic numerals, slashes, and hyphens only, as in the following examples: FASEB/NS-75/87 and FAA/
      RO-75/09.
  2.   Leave blank.

  3.   Recipient's Accession Number. Reserved for use by each report recipient

  4.   Title and Subtitle. Title should Indicate clearly and briefly the subject coverage of the report, subordinate subtitle to the main
      title. When a report is prepared In more than one volume, repeat the primary title, add volume number and include subtitle for
      the specific volume.

  5.   Report Date. Each report shall carry a date indicating at least month and year. Indicate the basis on which it was selected (e.g.,
      date of issue, date of approval, date of preparation, date published).

  6.   Sponsoring Agency Code. Leave blank.

  7.   Author(s). Give name(s) In conventional order (e.g., John R. Doe, or J. Robert Doe). List author's affiliation If It differs from
      the performing organization.

  8.   Performing organization Report Number. Insert If performing organlzaton wishes to assign this number.

  9.   Performing Organization Name and Mailing Address. Give name, street, city, state, and ZIP code. Ust no more than two levels of
      an organizational hierachy. Display the name of the organization exactly as It should appear in Government indexes such as
      Government Reports Announcements &  Index (GRA & I).

 10.   Project/Task/Work Unit Number. Use the project, task and work unit numbers under which the report was prepared.

 11.   Contract/Grant Number. Insert contract or grant number under which report was prepared.
 12.   Sponsoring Agency Name and Mailing Address. Include ZIP code. Cite main sponsors.

 13.   Type of Report and Period Covered. State Interim, final, etc., and, if applicable, Inclusive dates.

 14.   Performing Organization Code. Leave blank.

 15.   Supplementary Notes.  Enter Information not included elsewhere but useful, such as:  Prepared in cooperation with... Translation
      of... Presented at conference of... To be published in... When a report Is revised, include a statement whether the new
      report supersedes or supplements the older report

 16.   Abstract. Include a brief (200 words or less) factual summary of the most significant information contained in the report. If the
      report contains a significant bibliography or literature survey, mention it here.

 17.   Document Analysis, (a).  Descriptors. Select from the Thesaurus of Engineering and Scientific Terms the proper authorized terms
      that identify the major concept of the research and are sufficiently specific and precise to be used as index entries for cataloging.

      (b). Identifiers and Open-Ended Terms.  Use identifiers for project names, code names, equipment designators, etc. Use open-
      ended terms written in descriptor form for those subjects for which no descriptor exists.

      (c). COSATI Field/Group. Field and Group assignments are to be taken form the 1964 COSATI Subject Category Ust. Since the
      majority of documents are multidisciplinary In nature, the primary Field/Group assignment(s) will be the specific discipline,
      area of human endeavor, or type of physical object  The application(s) will be cross-referenced with secondary Field/Group
      assignments that will follow the primary posting(s).

 18.   Distribution Statement. Denote public releasability, for example "Release unlimited", or limitation for reasons other than
      security. Cite any availability to the public, with address, order number and price, if known.

 19. & 20.  Security Classification. Enter U.S. Security Classification In accordance with U. S. Security Regulations (i.e., UNCLASSIFIED).

 21.   Number of pages.  Insert the total number of pages,  Including introductory pages, but excluding distribution list, if any.

 22.   Price. Enter price in paper copy (PC) and/or microfiche (MF) if known.

    GPO   1983 0 - 381 -526 (8393)                                                                       OPTIONAL FORM 272 BACK
                                                                                                    (4-77)

-------
EPA/ROD/R06-90-054
Hardage/Criner, OK

16.  Abstract  (Continued)

 nd ground water are VOCs including benzene, PCBs, PCE, TCE and other carcinogenic
compounds; other organics including pesticides; and metals including arsenic, chromium,
and lead.

 The selected remedial action for the site includes source control and ground water
components.  Source control remediation includes installation of liquid extraction wells
to pump out free liquids currently pooled in the three waste areas and any liquids
released from drums buried in the mounds, followed by offsite treatment of the removed
organic liquids and onsite treatment of aqueous liquids; excavation of drummed organic
liquids for offsite destruction; excavation and consolidation of contaminated soil
adjacent to the main source areas with placement in the main source areas, followed by
temporary capping; treatment of the main source areas using in-situ soil vapor
extraction with treatment of air used in soil extraction by thermal destruction;
installation of a permanent RCRA-compliant cap once remedial activities are complete.
Ground water components are designed to control the spread of ground water plumes and
protect downgradient areas because of the technical impracticability of restoration of
the bedrock aquifer.  Ground water remediation includes installation of an interceptor
trench downgradient of the source areas to intercept and collect contaminated ground
water migrating in bedrock zones, and a second trench or equally effective system of
extraction wells to intercept and collect contaminated ground water contaminating the
alluvium; design and construction of an onsite ground water treatment system to treat
both organic and inorganic contaminants before discharge of treated water to surface
water.  Contaminants already present in the alluvium will be allowed to dissipate by
natural dilution, natural attenuation,  and flushing; however,  active restoration will be
 .mplemented if contaminant reduction goals are not met.  In addition, institutional
 ontrols, surface water controls, and multimedia monitoring will be implemented, and the
current provision of an alternate water supply will be continued.  The estimated present
worth cost of this remedial action is $62,904,655, which includes an annual O&M cost of
$1,300,000.

-------
    RECORD OF DECISION AMENDMENT
        HARDAGE/CRINER SITE
      McCLAIN COUNTY, OKLAHOMA
           NOVEMBER 1989
U.S. ENVIRONMENTAL PROTECTION AGENCY
       REGION 6, DALLAS, TEXAS

-------
                                 DECLARATION
                                   FOR THE
                         RECORD OF  DECISION AMENDMENT
 SITE  NAME  AND  LOCATION

 Hardage/Criner
 McClain  County,  Oklahoma

 STATEMENT  OF BASIS  AND  PURPOSE

 This  decision  document  represents the selected remedial action for the
 Hardage/Criner site developed in accordance with the Comprehensive
 Environmental  Response, Compensation, and  Liability Act (CERCLA), as
 amended  hy the Superfund Amendments and Reauthorization Act of 1986 (SARA),
 and to the extent practicable, the National Oil and Hazardous Substances
 Pollution  Contingency Plan  (NCP).

 This  decision  is based  on the contents of  the administrative record for the
 Hardage/Criner site.  The attached index (Appendix C)  identifies the items
 which comprise the  administrative record upon which the decision to amend
 the 1986 Record  of  Decision  (ROD), and the selection of the modified remedial
 action is  based.

 The State  of Oklahoma supports a number of the components of the amendment
 but has  not concurred with all elements of the selected remedial action.

 ASSESSMENT OF  THE SITE

 Actual or  threatened releases of hazardous substances  from the site, if not
 addressed  by implementing the response action selected in this ROD, may
 present  an  imminent  and substantial endangerment to public health, welfare,
 or the environment.

 DESCRIPTION OF THE  REMEDY

 The 1989 proposed remedy is  a comprehensive site remedy addressing both
 Source Control  and  Groundwater operable units at the Hardage/Criner site.
 It involves a  modification of the 1986 ROD for Source Control, and
 incorporates new Groundwater response actions.  The major components of
 this remedial  action consist of the following source control and ground-
water components:
        SOURCE CONTROL

        the installation of liquid extraction wells in three main source
        areas to pump out free liquids current y pooled in these areas and
        any liquids released from drums buried in the mounds.  The liquids
        would he collected and shipped offsite for treatment, thereby
        permanently reducing the volume of haz 'dous substances in the
        source areas and the potential for the r migration.

-------
         excavation as per the 1986 ROD for the direct removal  of drummed
         liquids  in the Barrel Mound and Main Pit.  Drum excavation and
         liquids  removal would reduce the volume of hazardous liquids within
         the source areas during the early phases of remedy implementation,
         thereby  reducing the reliance on long-term active controls otherwise
         necessary to address the continued release and migration of hazardous
         liquids, many of which are highly toxic, resulting from gradual  and
         difficult to predict corrosion of drums.

         excavation of contaminated soils in areas adjacent to  the three
         main source areas and transport to the source areas.  These materials
         would be consolidated under a temporary cap in the main source  areas
         where they would be treated using soil vapor extraction.

         use of soil vapor extraction to draw air through the source areas
         after consolidation to evaporate contaminants and permanently
         remove them to the surface through air extraction wells.  The air
         would be treated to destroy the contaminants using the best available
         control technology (BACT) by thermal destruction.

         permanent source area capping once remediation activities are
         complete.  A temporary cap will be installed during remediation
         activities, followed by a permanent RCRA-compliant cap at the end of
         remediation.
        GROUNDWATER

Groundwater components summarized below would be implemented in conjunction
with a substantial reduction of the contaminant source areas thereby reducing
the long-term potential contribution of the sources to groundwater.

     o  the installation of a V-shaped trench located downgradient (west,
        south and east) of the three main source areas to intercept and
        collect contaminated groundwater migrating in all bedrock zones
        existing above Stratum IV.  This trench would capture contaminated
        groundwater onsite and near the source areas minimizing migration
        of contaminants beyond the trench and into the alluvium of North
        Criner Creek.

     o  the installation of an interceptor trench, or equally effective
        system of extraction wells, in the southwestern part of the site to
        contain contaminated groundwater moving into the alluvium from
        bedrock zones above Stratum IV.  This interceptor system would capture
        migrating contaminants between the V-trench and alluvium of North
        Criner Creek.

     o  the design and construction of an onsite ground rater treatment
        system incorporating treatment processes to tre t both organic
        and inorganic contaminants to surface water dis.iarge standards.
        Collected groundwater would he pumped to the treatment unit, and the
        treated water discharged to North Criner Creek.
                                     11

-------
     o  alluvial groundwater restoration.  Contaminants already present  in
        the alluvium would he allowed to dissipate hy natural  dilution,
        natural biodegradation and flushing.  The interceptor  trenches,  in
        conjunction with source control actions, would abate contaminant
        migration into the alluvium of North Criner Creek and  allow natural
        restoration to Maximum Contaminant Levels to occur.  If alluvial
        monitoring reveals that estimated natural restoration  times and
        plume dilution rates are not being met, then active restoration
        of the alluvium would be implemented.  An increase in  contaminant
        concentrations in the alluvium after trench installation and pumping,
        or a decline in the mass of contaminants of less than  40 percent in
        10 years, will trigger active restoration in the alluvium.

In addition to the Source Control  and Groundwater components listed above,
the comprehensive remedy calls for the following monitoring and support
components (further described in Section 6) which are necessary as part  of
remedy implementation:


     o  institutional  controls, including fencing, deed restrictions, and
        maintenance of the availability of an alternate water  supply system.
        These will  be implemented  to restrict access to the site and
        contaminated groundwater.

     o  surface water controls to  collect surface water drainage from the
        source areas during remedy implementation, and to divert
        uncontaminated runoff away from the working area in order to
        minimize the generation of contaminated groundwater.

     o  remedial  monitoring to verify that the migration of contaminants
        has been halted.  This monitoring program includes monitoring of
        surface water in North Criner Creek, monitoring of alluvial and
        bedrock groundwater onsite and offsite, including downgradient of
        the alluvial  contamination plume, and monitoring of the performance
        of the groundwater interceptor trenches (or wells if used in place
        of the southwest interceptor trench) to determine their effectiveness
        in containing and reducing contamination.  The caps proposed as
        part  of the Source Control  will  be monitored for differential
        settlement  or erosion.  Finally, air quality would be  monitored
        during implementation of the remedy both onsite and at the fenceline
        boundary.   Action levels will be set onsite to assure  fiat Maximum
        Ambient Air Concentrations are not exceeded at the fenceline.
                                    m

-------
 DECLARATION

 The  selected  remedy,  if  implemented,  is protective of human health and the
 environment,  attains  Federal and State requirements that are applicable or
 relevant and  appropriate to this remedial action and is cost-effective.

 This remedy satisfies the statutory preference for remedies that employ
 treatment that reduces toxicity, mobility or volume as a principal element
 and  utilizes  permanent solutions and  alternative treatment technologies to
 the  maximum extent practicable.

 Because this  remedy will result in hazardous substances remaining onsite
 above health  based levels, a review will be conducted within five years
 after commencement of remedial action to ensure that the remedy continues
 to provide adequate protection of human health and the environment.
Robert E. Layton Ji^T, P.
                                                     l   I*
Date

-------
               HARDAGE/CRINER - RECORD OF DECISION AMENDMENT
                             TABLE OF CONTENTS
1.0  Site Location and Description

2.0  Site History and Enforcement Activities
     2.1  Disposal Operations
     2.2  Enforcement
     2.3  Site Investigations
     2.4  Highlights of Community Participation

3.0  Scope of Response Action

4.0  Site Characteristics
     4.1  Site Conditions
          4.1.1  Surface Water Hydrology
          4.1.2  Site Geology
          4.1.3  Groundwater Hydrology
     4.2  Site Contamination
          4.2.1  Impact of Disposal  Operations
          4.2.2  Remaining Contaminant Sources
          4.2.3  Pathways and Extent of Contamination
          4.2.4  Future Contaminant  Migration

5.0  Site Risks

6.0  Description of Alternatives
     6.1  Alternative Source Control Components
          6.1.1  No Action
          6.1.2  On-site Landfill (EPA 1986 ROD)
          6.1.3  Containment of Wastes (HSC Proposal)
          6.1.4  Incineration
          6.1.5  Liquid Extraction Wells
          6.1.6  In-Place Drum Lancing
          6.1.7  Drum Excavation
          6.1.8  Excavation of Wastes in Adjacent Areas
          6.1.9  Soil Vapor Extraction and Treatment
          6.1.10 Source Area Capping
     6.2  Groundwater Remediation Objectives and Alternative
          Groundwater Components
          6.2.1  U-shaped Trench
          6.2.2  V-shaped Trench
          6.2.3  Southwest Interceptor Trench
          6.2.4  Groundwater Treatment System
          6.2.5  Alluvial Groundwater Restoration
     6.3  Monitoring and Support Components
          6.3.1  Remedial Support Facilities
          6.3.2  Institutional Controls
          6.3.3  Surface Water Controls
          6.3.4  Remedial Monitoring

-------
     6.4  Comprehensive Alternatives
          -6.4.1  Common Elements
          6.4.2  Revised EPA Remedy
          6.4.3  Partially Revised EPA Remedy
          6.4.4  HSC Remedy

700  Comparative Analysis of Alternatives
     7.1  Overall Protection of Human Health and the Environment
     7.2  Compliance with Applicable or Relevant and Appropriate Requirements
     7.3  Long-term Effectiveness and Permanence
     7.4  Reduction of Toxicity, Mobility, or Volume
     7.5  Short-term Effectiveness
     7.6  Implementabilit-y
     7.7  Cost
     7.8  State and Community Acceptance

8«0  Selected Remedy Description
     8.1  Remediation Goals

9.0  Statutory Determinations
     9.1  Protection of Human Health and the Environment
     9.2  Compliance with ARARs
     9.3  Cost Effectiveness
     9.4  Utilization of Permanent Solutions and Alternative
          Treatment Technologies
     9.5  Preference for Treatment as a Principal Element
     9.6  Documentation of Significant Changes
REFERENCES

APPENDICES

A. Evaluation of Applicable or Relevant and Appropriate Requirements

B. Agency for Toxic Substances and Disease Registry (ATSDR)/Center for
     Disease Control (CDC) Evaluation

C. Administrative Record  Index

D. State of Oklahoma Correspondence

E. Responsiveness Summary

F. 1986 Source Control Record of Decision

G. Detailed Cost Evaluation of the Selected Remedy

-------
                              LIST OF FIGURES
1-1.  Vicinity Map
1-2.  Site and Disposal Operations Map

4-1.  North Criner Creek Drainage Basin Map
4-2.  Surface Water Hydrology
4-3.  Geologic Cross-Section
4-4.  Hydrogeologic Cross-Section
4-5.  Main Pit and Barrel Mound Pit Cross-Section
4-6.  Approximate Extent of Groundwater Contamination
4-7.  Distribution of Total Volatile Organics in Stratum III
      and the Alluvium
6-1.  Conceptual Drum Lancing Diagram
6-2.  Areas Targeted for Drum Excavation
6-3.  Schematic of Soil Vapor Extraction
6-4.  Final Source Area Cap
6-5.  Alternative C Site Schematic, Second Operable Unit
      Feasibility Study
6-6.  Alternative E Site Schematic, Second Operable Unit
      Feasibility Study
6-7.  Site Cross-Section Showing Trenches
8-1.  Schematic of Selected Remedy
                               LIST OF TABLES

2-1.  Summary of Drummed Wastes from Manifests
4-1.  Carcinogens Detected in the Source Area Characterization
      Holes
4-2.  Comparison of Groundwater Data with MCLs.
6-1.  Summary of Alternative Elements, Second Operable Unit
      Feasibility Study
6-2.  Comparison of Alternatives
7-1.  Comparison Summary According to Statutory Criteria
7-2.  Drum Excavations Performed at Other Sites
8-1.  Cost of Selected Remedy

-------
                                     1-1
 1.0  SITE  LOCATION  AND  DESCRIPTION

 The Hardage  site  is located  in  a  rural area of McClain County in central
 Oklahoma,  approximately 25 miles  south-southwest of Oklahoma City
 (Figure  1-1).   The  site is hounded on the South by old Oklahoma State
 Highway  122, on the north by open farmland, on the west by a gravel (County)
 road,  and  on the  east by a series of three small ponds (Figure 1-2).

 The Hardage  site  was operated from 1972 to 1980 under a permit issued by the
 Oklahoma State  Department of Health (OSDH) for the disposal of industrial
 wastes.  In  1983, EPA placed the  site on the "National Priorities List"
 (48 Fed. Reg. 40658) for response under the Comprehensive Environmental
 Response,  Compensation,  and Liability Act of 1980 (CERCLA).  EPA has taken
 the lead in  response to  this site.  OSDH has provided technical support and
 advice to  EPA,  particularly in  the early stages of work on the site, and
 has been consulted  on remedy selection.

 As  a result of waste disposal practices at the site, chemicals have migrated
 vertically and  laterally resulting in the contamination of approximately
 70  acres of groundwater  beneath and adjacent to the site as well as several
 acres of surface  soil in the immediate vicinity of the main disposal areas.
 The principal source of  contamination is some 278,000 cubic yards of
 sludges, waste drums, highly contaminated soils, and waste liquids contained
 in  three waste areas near the center of the property.

 The disposal areas  at the site were a number of permanent and temporary
 impoundments into which  a variety of liquid, sludge, and solid wastes were
 disposed and mixed.  These areas, described more fully in Section 2.1, were
 primarily the Main  Pit,  Sludge Mound, and Barrel Mound, and in addition the
 North Pit, West (mixing) Ponds, and East (mixing) Ponds (see Figure 1-2).
 During 1980 - 1981  the  operator consolidated wastes into the Main Pit,
 Barrel Mound, and Sludge Mound and capped those areas with two to three
 feet of local soil  in an effort to permanently close the site.  Closure
 efforts failed, however, to prevent the migration of hazardous substances
 vertically and laterally into groundwater from the impoundments.  More
 specifically, dense non-aqueous phase liquids have pooled beneath the Main
 Pit, Barrel Mound and to some extent the Sludge Mound and now serve as a
 continuing source of contamination to the groundwater.  Volatile organic
 compounds, many of  them  known or suspected carcinogens, have migrated
 from these areas offsite into the alluvium of North Griner Creek, forming a
 plume of contamination extending a distance of about 2800 feet southwest of
the Main Pit.  Total concentrations of volatile organic compounds in the
plume exceed 25,000 ppb  near the source areas and decrease systematically
 away from the source areas, with concentrations as high as a few hundred
 ppb more than 2500  feet  away from the Main Pit to the southwest.  Volatile
organic compounds are entering  North Criner Creek at sufficient quantities
to cause detectable concentrations in surface water in the Creek.

Present and near-term risks are related primarily to groundwater resources
and any individuals who  might use the contaminated groundwater.  Over the
 long-term, risks will also he posed due to erosion of wastes and their
 gradual surface and subsurface migration across and from the site.

-------
 SCALE IN MILES
               OKLAHOMA
               oClTY
              •PROJECT
               SITE
STATE OF OKLAHOMA
       HARDAGE INDUSTRIAL
          WASTE SITE
   REMEDY COMPARISON REPORT
VICINITY MAP

-------
                 NORTH PIT AREA
            NORTHWEST
            FARM
            POND
                                                        *>EAST
                                                        'I POND
                                                        -' I AREA
                     WEST
                     POND AREA
                     INTERCEPTOR  SLUDGE
                     TRENCHMOUND
              HOMESTEAD
                                OLD STATE HIGHWAY 122
                                (COJNTY ROAD)
NORTH
CRINER
CREEK
          FIGURE 1-2


SITE AND DISPOSAL OPERATIONS MAP
                                          HARDAGE INDUSTRIAL WASTE SITE
                                                   REMEDY REPORT
                                  	GENERAL AREA OF WASTE EXCAVATION

-------
                                     2-1


 2.0  SITE HISTORY AND ENFORCEMENT  ACTIVITIES

 2.1 Disposal  Operations

 In  1972 the site owner and operator  Royal  Hardage,  received a permit from
 the Oklahoma  State Department  of Health  (OSDH) to operate a hazardous and
 industrial  waste landfill  at the site.   This  permit was based on an
 application by  Mr. Hardage that consisted  of  a general outline of planned
 operations  and  limj'ted subsurface  boring data on site geology.

 From September  1972 until  November 1980  the site accepted approximately 21
 million gallons  of hazardous and industrial wastes  including paint sludges
 and solids, ink  solvents,  tire manufacturing  wastes, oils and solvents such
 trichloroethene, corrosives, plating wastes sludges, cyanides, and caustic
 wastes, many  of  which are  now  regulated  as hazardous waste under the Resource
 Conservation  and Recovery  Act  (RCRA).  The liquid portion of this waste was
 initially discharged  into  the  Main Pit.  Early in the operation, problems
 began  to occur  due to slower than  expected evaporation of wastes.  To deal
 with  this problem, the operator began spraying liquids over the Main Pit to
 enhance evaporation and also drained some  of  the liquids into adjacent
 temporary mixing ponds for hulking with  soil. The  soil/waste mixture was
 disposed in a new area called  the  Sludge Mound.  Sludge waste, including
 residue from  oil  recycling and styrene tar production, and some drums of
 solid  material,  were  also  disposed in the  Sludge Mound.

 In  addition to  the bulk waste  liquids disposal described above, drums of
 waste  were  also  received at the site.  These  waste  drums were initially
 opened  and  dumped into the Main Pit. This practice, however, became less
 common  after  about 1974.   During most of the  operations, drums were dumped
 off trucks  into  two areas, the west  side of the Main Pit and the Barrel
 Mound.   The Barrel  Mound area  adjoins the  north end of the Main Pit and
 was built to  a height of 25 to 30  feet by  trucks dumping drums off of the
 south  side  of the mound, filling soil over and around the drums, and dumping
 of  additional drums onto the previously  dumped drums.  Many of the drums at
 the site  were carelessly dumped into the pits, without any attempt to avoid
 rupturing.  Some drums were rolled off trucks down  the face of the Barrel
 Mound.   Other drums dumped  into the  pits were not sealed to begin with.
 As  a result,  a substantial number  of these drums spilled or broke
 open during the  disposal operation resulting  in the direct release of large
 volumes  of  hazardous  and carcinogenic chemicals into soils and eventually
 groundwater.  Many  of  the  drums, however, were disposed intact, as shown
 by accounts of the  site operation  (Hardage, 1987).  Moreover, intact drums
 were excavated and  removed from the  site during exploratory excavations in
 1988 (EPA,  1988).   A  summary of drummed  wastes brought to the site (from
 manifests)  is presented  in Table 2-1.

 In addition to disposal  practices  in the source areas (Barrel Mound, Main
 Pit, and  Sludge  Mound)  waste mixing  and  transfer operations were conducted
 over much of  the  site  in areas known as  the North Pit, East Pond area, and
West Pond area.   The  disposal  areas  and  site  activities described above are
 illustrated in Figure  1-2.

-------
                          Table 2-1
          SUMMARY OF DRUMMED WASTES FROM MANIFESTS

                              No.  of           Estimated
                            Containers     Volume Received(1)
Waste Category               Received          (gallons)

Paint
  Sludge                      5,897             324,047
  Paints and Related Wastes   1,044              57,420
  Solids     -  -   -            451              24,805

Mixed Wastes
  Mixed Wastes                2,557             138,600
  Tire Manufacturing Wastes
     (Carbon Black, Soap,
      Oil, Solvents, Rubber}  1,405              77,275
  Soap, Oil, Solvents           304              16,720

Acid
  Rinse Water                 1,867             102,685
  Sulfuric Acid                 880              48,400
  Sludges                       676              37,180
  Acids                         341              18,755
  Chromic Acid                  248              13,565
  Nitric Acid                   194              10,670
  Acids and solvents             31                1,705
  Muriatic Acid                  13                  715
  Acrylic Acid                   12                  660
  Hydrofluoric                     4                  220

Oils and Solvents (TCE,
 Stoddard)                    3,253             177,815

Asbestos                       1,345              73,975

Oil
  Oils                          660              36,300
  Sludge                        132                5,790

Alumina Silica Slurry           747              41,085

Ink
  Inks                          520              30,425
  Solvent                        57                3,135
  Sludge                         47                2,585

Caustic                         580              31,900
CVOR211/033.50/1

-------
Waste Category
 Table   2-1
(continued)
     No. of
   Containers
    Received
Cupric Ammonium Persulfate
and Toxic Tin
Corrosive
MDI (methylene bisphenyl
isocyanate)
Plastic Wastes
Aromatic Residue
Chemical Wastes
Plating Waste Sludge
Cyanide (Copper, Potassium,
Sodium)
Shopwaste
Nitric Alumina
Glue
Alumina Oxide
Filter Cake
Methanol
Sediment Pit Waste
Zinc, Arsenic
PCBs
Laboratory Chemical Packs
(Phosgene Gas Canister,
Reagents, Waste Chemicals)
Toxaphene
    Estimated
Volume Received(l)
    (gallons)
435
357
299
261
232
229
214
142
111
91
84
80
80
80
62
33
29
27
145
23,925
19,635
16,325
14,355
12,760
12,595
11,770
7,760
6,105
5,005
4,620
4,400
4,400
4,400
3,410
1,782
1,595
1,385
1,375
CVOR211/033.50/2

-------
Waste Category
Polyacrylamide
Sand Filter Sludge
Ammonium Bifloride
Selenium
Emulsion
Trichloroethene and Aluminum
Chromium
Waste Chlorides
Insecticides
Salt Sludge
Ammonium Hydroxide
Chlorine
Sodium Lead Alloy
2,4-Dinitrophenyl Hydrazine
Pesticide with Arsenic
Vaccine
  TOTAL
 Table 2-1
(continued;
     No.  of
   Containers
    Received
         14
         11
         8
         8
         6
         63
         20
        142
         3
         2
         55
         1
         1
         1
         1
         1
    25,593
    Estimated
Volume Received(l)
    (gallons)
         770
         605
         440
         440
         330
         315
         300
         142
         165
         110
          55
          55
          28
    1,437,809
(1)  Unless indicated on manifest,  Hardage (1972-1980)
     containers were assumed  to  be  55-gallon drums.   All
     containers were assumed  to  be  full.
CVOR211/033.50/3

-------
                                     2-5
 2.2  Enforcement

 In  1979,  OSDH  and  EPA inspections  and sampling of the site indicated waste
 management-practices  were  posing potential threats to public health and the
 environment.   In September 1980, the United States, on behalf of EPA, filed
 a complaint  in the U.S.  District Court for the Western District of Oklahoma.
 The  complaint  sought  injunctive relief under Section 7003 of RCRA for the
 proper  cleanup and closure of the  site.  The facility ceased operations in
 early November 1980,  before Interim Status Standards under the RCRA came
 into effect.

 In 1982,  United States amended the existing complaint against the facility
 owner and operator Royal Hardage,  to request relief under Sections 106 and
 107  of  the CERCLA.  In December 1982, the Court found that the site posed
 an "imminent and substantial endangerment to public health and welfare and
 the-environment" as defined by CERCLA Section 106 and RCRA Section 7003.
 In August 1983, the Court  granted  a partial judgment for over $211,000 in
 response  costs, which EPA  had incurred through 1982, against Royal Hardage.
 Hardage filed for  bankruptcy in 1983 and again in 1985, and EPA has to date
 not  recovered its  partial  judgment.

 In December  1984,  EPA mailed letters to 289 Potentially Responsible Parties
 (PRPs)  requesting  information about their waste disposal at the Hardage
 site under authority  of  Section 104(e) of CERCLA and Section 3007 of RCRA
 and  notifying the  PRPs of  their potential liability for site cleanup.  As
 further information was  gained, information request and notice letters were
 sent to additional  PRPs  identified.  At the present time, over 400 PRPs
 have been identified.  Various PRPs have gone out of business or cannot be
 located;  therefore, approximately  340 have been contacted.  A group of
 these parties organized  into the Hardage Steering Committee (HSC) and met
 with EPA  and OSDH  on  numerous occasions concerning the site.  Initial
 meetings  with the  HSC were held in January of 1985.

 In May  1985, EPA released  a report entitled Field Investigation and Data
 Summary Report (DSR) for the Royal Hardage Waste Disposal Site (EPA, 1985)
 documenting investigations  conducted in 1984 and earlier.  This document
 served  as a remedial  investigation (RI) report for the site.

 After completion of the  DSR, EPA determined that sufficient data were
 available to develop a remedy for  the contaminant source areas, but that
 the  information was inadequate to  develop remedial alternatives for the
 contaminants that  had already migrated from the source areas into ground-
water.  Accordingly, selection of  a comprehensive alternative for a complete
 remedial action, addressing surface and subsurface contamination beyond the
 source  areas, was  not possible at  that time.  The need for control of the
 source  areas at the site prompted  EPA to consider alternatives that would
 reduce  or eliminate the  spread of  contaminants off the site.  Therefore,

-------
                                    2-6
EPA decided, in accordance with Section 300.68(c) of the National  Oil  and
Hazardous Substances Pollution Contingency Plan (NCP), to divide the
remedial process of the site into two operable units: 1) Source Control  and
2) Management of Migration (groundwater).

During  1985, EPA began preparing a Feasibility Study (FS) for the Source
Control Operable Unit primarily addressing the three principal waste source
areas:  the Main Pit, the Barrel Mound and the Sludge Mound.

EPA's FS, entitled Feasibility Study - Source Control - Royal Hardage
Industrial Waste Site Nea.r Criner. Oklahoma (EPA. 1986a). presented the
methodology used to develop several remedial action alternatives for the
Source  Control Operable Unit.  The alternatives, further discussed in
Section 6, were evaluated in accordance with the NCP, and four alternatives
were developed in detail.  These four alternatives included onsite waste
stabilization with disposal in a RCRA-compliant landfill, onsite incineration
and disposal, offsite incineration and disposal, and onsite waste stabiliz-
ation and disposal in an offsite RCRA-compliant landfill.

In November 1986, EPA issued its Record of Decision (ROD) outlining the
selected final remedy for the Source Control Operable Unit (see Appendix
F).  This remedy was selected in a manner consistent with CERCLA, as amended,
and the NCP as the most appropriate remedy for source control considering
all relevant selection criteria.  The selected remedy consisted of excavating,
treating, and disposing of solids in a RCRA-compliant onsite landfill;
removal and offsite incineration of free organic liquids; and the onsite
treatment and disposal of other water-based liquid wastes.  After potentially
responsible parties declined to implement the selected remedy,  EPA subse-
quently initiated the remedial design process with the design-related field
activities.  The detailed design was presented in EPA's Design Report - Source
Control Remedial Design - Hardage Industrial Waste Site - Criner Oklahoma
(EPA, 1988).

Prior to EPA's 1986 ROD, additional field studies were initiated by the
HSC.  This work involved the gathering of geologic and hydrologic data at
the Hardage site to assess an in-place containment remedy later proposed by
the HSC.  As a result of this work, the HSC submitted the Final
Confirmatory Bedrock Study in December of 1986 (HSC 1986).  As a part of
the EPA's public comment process for the ROD, the HSC's report also briefly
presented the the HSC's proposed source cortrol remedy.  The HSC remedy
ca'led  for in-place containment of the waste source areas by a cut-off
wa 1 supplemented by groundwater pumping.  Differences between the HSC and
EPA source control proposals were not resolved and resulted  in litigation
ov^r implementation of the selected remedy.  Work by the HSC in support of
tl- ir proposed remedy continued at the site through November 1, 1988.
Ac itional characterization of the source areas was conducted and

-------
                                     2-7
 reported in the HSC's Mound Characterization  Field  Study (HSC,  1988).   From
 these and.other studies performed as  a part of  the  HSC's litigation  efforts,
 the HSC prepared a Recommended Source Control Remedy  design  report  (HSC,
 1988) which provided additional  technical  details of  the HSC's  proposed
 remedy.

 Meanwhile,  in July 1985 the Court administratively  closed the  1980  case
 against Hardage, providing that  the U.S.  could  re-open  the case  for  the
 purpose of  seeking appropriate relief until April 1,  1986, at  which  time
 the case would otherwise he dismissed. The United  States, on  behalf of
 EPA,  filed  a motion on March 27,  1986, to  amend the existing complaint  and
 add newly discovered generators  and transporters to the existing case.  The
 Court ultimately denied the motion and dismissed the  case.   On  June  25,
 1986, the United States filed a  new complaint naming  36 generators  and
 transporters of waste at the site. The complaint asked for  performance of
 the EPA selected source control  remedy, maintenance of  site  security, conduct
 of  a  RI/FS  for the management of  migration (groundwater) operable unit,
 implementation of the groundwater operable unit remedy  to be selected by
 EPA,  and recovery of EPA's past  and future response costs.

 In  1987 the District Court issued a ruling indicating that the  case  would
 be  decided  in a "de-novo"  trial,  as opposed to  a trial  on the  Administrative
 Record.  The Court, in issuing that ruling, cited two factors  peculiar  to
 the case.  First, the case was filed  prior to the enactment  of  the  Superfund
 Amendments  and Reauthorization Act of 1986 (SARA),  which called  for  Admin-
 istrative Record review at trial.  Second, the  case was filed  under  RCRA as
 well  as CERCLA; and RCRA does not mandate  an  Administrative  Record  trial.

 After lengthy negotiations,  a Partial  Consent Decree  between EPA and HSC
 was entered by the Court in  February  1988. Under this  Decree,  HSC  agreed
 to  conduct  a RI/FS addressing management  of contaminant migration at the
 site  under  EPA oversight.   The second operable  unit RI/FS, and  Endangement
 Assessment  reports were submitted to  EPA  in the spring  of 1989,  finalized
 and sent  to repositories in  October of 1989.

 Throughout  1988 both EPA and HSC  took extensive depositions  of  both  fact
 and expert  witnesses.   In  early  1989,  the  Government  initiated  meetings
 with  HSC  to discuss ways of  resolving on-going  litigation.

 On  April  7,  1989 a Consent  Decree was lodged with the U.S. District  Court
 between EPA and  approximately 170 "de minimis"  (small quantity)   PRPs for
 the site.   Under this  agreement,  the  de minimis parties resolved their
 liability for  the  site  by  making  two  cash  payments: one to EPA  to cover
 past  cost   incurred,  and a  second to  a trust  fund to  be supervised  by the
 District  Court.   The  trust  fund will  be used  for site remediation.   This
 Consent Decree  was  entered by the court on September  22, 1989.   The
 de minimi   agreement  was prepared in  accordance with  EPA's Interim  Guidance
 on  Settle, ^nt  with  De Minimis Waste Contributors under  Section  122(g) of
SARA  (Junt  19.  1987)  52  Fed.  Reg.  24333 (June 30. 1987).

-------
                                    2-8
 2.3   Site  Investigations

 Studies o£ the Hardage site have been conducted since 1982.  These studies,
 some  of which were mentioned in Section 2.2, are part of EPA's administrative
 record for the site, and are described below:

 March 1982
 Ecology and Environment (E&E), an EPA contractor, sampled surface soils,
 drainage ways, and existing wells at the site.  E&E also installed and
 sampled ten monitoring wells on and around the site.  These wells are
 designated EW-1 through EW-10.  This investigation is documented in a
 May 7, 1982 letter report from Imre Sekelyhidi of E&E.

 August 1984
 EPA contractor CH2M Hill'and its subcontractors Chen Associates, Wright
 Water Associates, and Davenport-Hadley conducted a site investigation in
 1984 to supplement the 1982 E&E data and allow selection by EPA of a source
 control remedy.  This investigation involved installation and sampling of
 monitoring wells (the "GTW", "BW", "PW", and "AW" series of wells), limited
 coring of  bedrock, sampling of the source areas, and sampling of shallow
 test pits.  This investigation is documented in the the May 1985 report
 "Field Investigation and Data Summary Report" (DSR) prepared by CH2M Hill.

July - November 1986
 HSC contractor ERM-Southwest conducted an investigation centering on
 conditions of the bedrock in the immediate vicinity of the source areas.
This investigation included installation of monitoring wells and well nests
MW-1 through MW-11, sampling of the shallow wells, resampling of some
 existing wells, and drilling vertical and slanted test borings 8-1 through
B-13 and SB-1 through SB-7.  This investigation is documented in the December
 1986 report "Confirmatory Bedrock Study" prepared by ERM-Southwest.

May 1987
 E&E, on behalf of EPA, collected samples from all monitoring wells at the
site.  This work was monitored, and split samples collected by ERM-Southwest
on behalf  of HSC.  HSC also recorded all work under the six week long project
on videotape.  The results of their sampling are documented in an August  31,
 1987 letter repc t from E&E and in the Management of Migration RI.

October 1987 and March 1988
ERM-Southwest, c  behalf of HSC, drilled fourteen cores MB-1 through MB-14
 into the waste «-jrce areas for chemical sampling and observation of physical
conditions.  Thi  activity is documented in the HSC's "Mound Characterization
Field Study" prepared by ERM-Southwest in November of 1988.

-------
                                     2-9
 January - April  1988
 ERM-Southwest,  acting as  litigation  consultants on behalf of HSC, conducted
 a variety of  activities on  the  site,  including drilling of deep core holes
 (the  "DH" holes),  drilling  of slant  cores, photo-linear analysis, geophysical
 logging,  reflection  and cross-hole geophysics, radioisotope dating, and
 sampling  of chloride for  geochemical  modeling.  This activity is documented
 in the  November  1988 report "Hydrogeologic Issues of Relevance to the
 Hardage Site" prepared by S.S.  Papadopulos Associates.

 April 1988 -  October 1988
 CHgM  Hill  and its  subcontractor Chen  Associates, acting on behalf of EPA,
 drilled eight bore holes  into the source  areas to retrieve samples for
 geotechnical  and stabilization  testing and to provide data on air emission
 of VOCs.   Two test pits were also excavated to provide further data on air
 emmissions and on  integrity of  the buried steel drums.  This activity is
 documented in the  November  1988 report "Source Control Remedial Design"
 prepared  by CH2M Hill.

 July  -  October 1988
 ERM-Southwest, on  behalf  of HSC and working under EPA oversight, conducted
 a  comprehensive investigation of the  extent of contamination and physical
 conditions at the  site relative to migration of contaminants.  This activity
 is  documented in the  May  1989 draft  report "Second Operable Unit Remedial
 Investigation" (also  refered to as the Management of Migration RI or
 Groundwater RI).   ERM-Southwest also  prepared and submitted to EPA a May
 1989 draft "Second Operable Unit Feasibility Study Report" (or Groundwater
 FS).  Both of these  reports underwent revision based on EPA comment, were
 then approved by EPA  and  sent to repositories in October of 1989.  HSC
 provided  replacement  pages  to EPA during  the public comment period which
 are addressed in the  responsiveness summary in Appendix E.


 2.4  Highlights of Community Participation

 In  preparation for this ROD amendment, EPA held a public comment period on
 the proposed comprehensive  remedy.  The comment period began October 13,
 1989, and  closed November 2, 1989.  EPA provided notice of the public comment
 period  through announcement in  the newspaper on October 1, 1989, and at
 that time  announced a  public meeting  on the proposed remedy.  A fact sheet
was prepared by EPA summarizing alternatives for both source control and
 groundwater and was sent  to repositories  and addressees on the site mailing
 list on October 12, 1989.   EPA's Remedy Comparison Report and Remedy Report,
 along with the Administrative Record, were also sent to repositories on this
date.  A public meeting on  the  proposed remedy for the site was held on
October 26, 1989,  and  approximately 40 people were in attendance.

EPA has addressed  questions received  during the public comment period,
 includi  g  those received  at the public meeting, in the responsiveness
summary  'Appendix  E).

-------
                                    3-1


 3.0  SCOPE OF RESPONSE ACTION                                                A

 The proposed remedy would address both the Source Control and Groundwater
 (Management of Migration) aspects of the Hardage site in a comprehensive
 remedial action.  This proposed comprehensive remedy would remove a
 substantial portion of the liquid wastes, including many highly toxic and
 mobile volatile organic compounds, from source areas, thereby reducing the
 volume, toxicity, and mobility of the hazardous substances at the site.
 Moreover, this proposed comprehensive remedy would prevent further
 contamination of the alluvial aquifer.

 To date the site has been investigated as two "operable units" - Source
 Control and Management of Migration or Groundwater.  This approach was
 adopted in 1985 in an effort to speed remediation of the site.  On November
 14, 1986, EPA issued a ROD for the Source Control Operable Unit.  This ROD
 selected a remedy, as previously discussed in Section 2.2, consisting of
 waste excavation and segregation followed by incineration of organic liquids
 and stabilization and consolidation of solids into a new landfill to be
 constructed on the site.  Protracted litigation from 1986 through 1989
 delayed implementation of the selected source control remedy.

 In 1987 HSC agreed, pursuant to a partial Consent Decree with EPA, to conduct
 a RI/FS for the Groundwater Operable Unit of the site.  Field studies were
 conducted in 1988 and a draft FS report was completed in May 1989 evaluating
 several remedial alternatives for groundwater at the site.  It was proposed
 that any groundwater actions would be implemented in conjunction with a
 Source Control  remedy.

 Subsequent to the completion of EPA's Remedial Design Report, an issue
 arose concerning the potential impact of the RCRA land disposal
 restrictions on certain elements of the Source Control remedy selected in
 the 1986 ROD.  The Agency's interpretation of the applicability of the land
 disposal restrictions to CERCLA response actions was then still evolving.
 Due to uncertainties over the ultimate resolution of this issue, EPA began
 to consider other alternatives for the Source Control remedy, which could
 unquestionably be implemented consistent with the RCRA requirements.
Because of the timing of the draft Groundwater FS, and the concurrent evaluation
of new Source Control technologies, EPA found it efficient and logical to
combine Groundwater and Source Control alternatives in order to develop
 remedial alternatives that would address the entire site.  As a result,  a
 number of comprehensive remedial alternatives were assembled from source
control and groundwater operable unit alternatives.  Comprehensive alternatives
are addressed in Section 6.4 and involve amendments to the 1986 ROD for
source control  and the selection of a remedial response  actions for contam-
 inated groundwater.  One of those alternatives is presented as the selected
comprehensive -emedy for the site (see Section 7 for remedy selection criteria).

-------
                                    3-2
The proposed  remedy would remove a substantial portion of the liquid wastes
from the source areas.  The Barrel Mound, and those portions of the Main
Pit believed  to contain drums, would he excavated.  Containerized liquids,
and free-phase liquids in the source areas, would be removed for offsite
destruction.  In addition, a relatively new technology, in-situ soil vapor
extraction, would be implemented in the source areas to reduce those
compounds most mobile in the environment.  Soil vapor extraction would be
effective in  removing volatile and semi-volatile compounds, a number of which
are carcinogenic, from the vadose zone, and from the surface of free-phase
liquids in the source areas.

The proposed  remedy would also prevent further contamination of the
alluvial aquifer associated with North Criner Creek.  Groundwater
interceptor trenches (or possibly interceptor wells in the alluvial
recovery area) would be installed to arrest migration of the plume of
contamination from the site, and thereby allow the gradual process of
restoration in the bedrock and alluvial systems to begin.  Groundwater
monitoring, institutional  controls, and controls on the use of groundwater
and surface water would be implemented to assure that humans are not
exposed to contaminants.

-------
                                    4-1
 4.0   SITE CHARACTERISTICS

 4.1 Site Conditions

 The Hardage site  is situated on gently rolling property in a rural area of
 South Central Oklahoma.  The principal disposal operations were conducted
 along a north-south trending ridge at the center of the property.  Relief
 is about 100 feet from the ridge to the adjacent stream valley.  The site
 is hounded on the southwest by the floodplain of a small perennial stream,
 and on the east by a series of three small ponds.  Soil cover on the site
 is thin and subject to erosion.  The underlying bedrock consists of a series
 of interbedded sandstones, siltstones, and mudstone.  These rocks are
 fractured, as is well documented in various published studies including
 observation of cores, rock outcrops, and geophysical logs of borings.

 The waste remaining onsite is primarily located in three source areas, the
 Main Pit, Barrel Mound and Sludge Mound.  These three source areas will
 continue to release contaminants into the environment primarily via ground-
 water flow.  At present, a groundwater plume of volatile organic contamination
 extends some 2800 feet southwest of the Main Pit with concentrations of
 volatile organic compounds exceeding 25,000 ppb.  The plume ranges in width
 from about 1800 feet near the source areas to about 800 feet in the southwest
 corner of the site (see Section 4.2.3, Figure 4-6).  Contaminants have
 migrated vertically and laterally from the source areas into the surround-
 ing and underlying bedrock, both in dissolved form and as non-aqueous phase
 liquids (NAPL).  The present and future migration of contaminants will
 continue via groundwater flow.  Eventually, erosion may also carry wastes
 off the site from the three source areas and adjacent mixing areas.

 4.1.1  Surface Water Hydrology

 The site is situated in the North Criner Creek drainage basin, approximately
 0.8 miles from the confluence of North Criner Creek and Criner Creek  (Figure
 4-1).  The drainage basin drains approximately 5,000 acres, and extends about
 four miles north of the site to the regional drainage divide between the
Washita and Canadian rivers.  The site, as stated above, is disected by a
 north-south trending ridge which controls runoff from the site (see Figure
 4-2).  Runoff from the western side of the site eventually enters a perennial
 stream, North Criner Creek, west and southwest of the site.  Runoff from
 the east side of the site enters a series of three small ponds (the East
 Farm Ponds).  These ponds drain southward through a fourth pond located on
 adjacent property before entering North Criner Creek south of the site.
 Drainage from the east side of the site is diverted from the east farm
 ponds by a berm and enters th~ stream below the southern most pond.

 Drainage on the west side of the site from the source areas and much  of the
 former operation area is channeled around an interceptor trench constructed
by Royal  Hardage to an impou'  lent known as the South Pond at the southwest
 corner of the site.  The sout , pond is constructed such that an open  discharge

-------
AREA - 575 ACHES
          OUTLINE
          NORTH CRIME
          CREEK
          WATER SHED
                                                              RECTIFIED
                                                              CHANNEL
                                                              SECTION
NOTES

1  NORTH CRMER CREEK WATERSHED AREA - MOO ACRES.'

2 RECTFCD NORTH CRMR CREEK CHANNEL SECTION
SOUTHWEST OF SITE COMPETED PRIOR TO If 41

1  SOL CONSERVATION SERVICE RETAMNG POND ft
AREA - 2*02 ACRES
 SOL CONSERVATION SERVICE RETANNG POND
 flfc* - 575 ACRES
                                  »3
 SOURCE QUADRANGLE. COLE. OKLAHOMA H35OO  W»7Mf7 5
                                                           SCALE
                                    toe
                                       1DMS
                          • 0 NO
                                 7661M70
                                                                   NORTH
                                                                            CM«r.
                                                                                                 FIGURE 4-1

-------
o
33
o

b
r5

-------
                                    4-4
 pipe near its  base  releases  water to flow south into a roadside ditch.
 An  unknown fraction of  this  water infiltrates downward from the pond.  Runoff
 from the  westernmost portion of  the site is diverted around the south pond
 and enters-the roadside ditch directly.

 The southwest  corner of the  site abuts the North Criner Creek flood
 plain.  North  Criner Creek is a  perennial stream with a nominal discharge
 of  0.8  to 1.3  cfs.   The stream has been channelized directly south of
 the site.

 The principal  ponds, streams, and surface flow divides and paths
 are shown on Figure 4-2.


 4.1.2   Site Geology

 Bedrock beneath the site consists of a sequence of Permian aged sediments
 which grade from  sandstone to siltstone, and mudstone.  Despite the gradi-
 tional  nature  of  these  deposits, extensive core samples have illustrated
 lateral continuity  of four shallow bedrock zones refered to as Stratum I
 through IV.  Bedding dips at outcrop locations near the site are less than
 one degree to  the west  and southwest.

 Bedrock immediately beneath  the  Main Pit and Barrel Mound is comprised of a
 thin sequence  of  sandstone and siltstone (Stratum  I).  Approximately twenty
 feet beneath the  Main Pit begins a sequence of mudstone/siltstone  (Stratum
 II)  approximately 20 feet thick.  Beneath this is  a sandstone/siltstone
 sequence  (Stratum III)  which is  about 30 feet thick.  Underlying Stratum
 III  is  a  thick sequence of low permeability siltstone and mudstone, the
 upper 20  feet  of which  exhibits  a predominance of  siltstone.  This bedrock
 sequence  is illustrated  in the generalized geologic cross-section  shown in
 Figure  4-3.  Bedrock over the entire site has been subject to natural
 weathering processes.   As a  result, the upper 20 to 40 feet of bedrock has
 been appreciably altered.

 Fracturing has been  observed in  the bedrock layers, both in surface outcrops
 and  in  subsurface drill cores recovered from site  investigations.  Both low
 angle (less than  10  degrees  from horizontal) and high angle (40 degrees on
 up  to vertical) fractures have been reported.  All three primary rock types
 (sandstones, siltstones, and mudstones) have had fractures reported.  In
 addition,  EPA  believes  that  free-phase organic chenrcals released  from the
 source areas may have desiccated materials adjacent to fractures causing
 further opening of  the  fractures.  The irregularity and heterogeneity of
 fracture  distribution,  interconnection and openness contribute to  a relatively
 high degree of uncertainty regarding the large-seal? hydraulic properties of
 the bedrock strata  at the site,  and therefore, high uncertainty regarding
 future waste migration  rates and patterns.

Adjacent  to the site, and associated with North Cri ar Creek, is an uncon-
 solidated  alluvial  deposit with  thicknesses up to  f  feet.  Alluvial borings
 completed  during the second  operable unit RI typicc ly encountered a thin
 silt/clay  zone at a  depth of 10-15 feet, which in  t rn was underlain by
medium to  coarse-grained silty sands.  Bedrock undf lying the alluvium was
 found to  be a  fine-grained silty mudstone, with sor  degree of weathering
 immediately beneath  the alluvium.

-------
                                         BARRCL MOUND/
                                         MAIN PIT-
 1130
1100
10SO-
1000-
950-
HIGHWAY

   SOUTH POND
900
                                                      SANDSTONE
                                 ^''^STRATUM II PREDOMINANTLYMUOSTONC


                                 STRATUM III SANOS70NC, SLTSTONC
                                PKFDOUI,
    SW
                       SCHEMATIC CROSS SECTION
                                                                      NE
                             FIGURE 4-3

                       GEOLOGIC CROSS-SECTION

                         HARDAGE/CRINER SITE
                                                                           •

-------
                                     4-6
 4.1.3  Groundwater Hydrology

 The  geologic  units described  above,  given their fractured and weathered
 conditions, have  combined  to  form  a  hydrogeologic system as illustrated in
 Figure  4-4.   This figure  illustrates  the hydrogeologic units at the site:
 (A)  moderately  permeable  weathered shallow bedrock with general groundwater
 flow to the southwest-into the  alluvium of North Criner Creek (Stratum I-III
 and  the top of  Stratum  IV, especially in the vicinity of the southwest
 alluvium);  (B)  a  sequence  of  variably fractured siltstone and mudstone
 (the lower portions  of  Stratum  IV);  and (C) the North Criner Creek alluvium,
 a  third hydrogeologic unit.   The weathered zone and alluvial aquifer are
 the  most permeable units  at the site  and, consequently, are the units most
 active  in the local  groundwater flow  regime.

 The  water table across  the site forms a continuous surface across Stratum
 I, II,  and III, and  is  roughly  parallel to the land surface as shown in
 Figure  4-4.   The  hydraulic conductivity reported for Stratum I through III
 ranges  from about 2  x 10~'  cm/sec  to  about 1.5 x 10" .  Flow in these
 units has a large horizontal  component with a gradient of about 0.01 to
 0.07.   Lower  and  higher hydraulic  conductivities correspond to an estimated
 average flow  velocity of  18 to  180 feet per year, consistent with the known
 distribution  distances  and patterns of contaminants in groundwater at the
 site.   Stratum  II  has a somewhat lower hydraulic conductivity than Stratum
 I or  III.

 Groundwater flow  in  Stratum I-III  in  the vicinity of the east farm ponds
 varies  seasonally and is affected  by  surface water levels in the ponds and
 recharge to soils.   It  is  generally accepted that the ponds form a discharge
 boundary for  groundwater flow.  However, monitoring during and after any
 remedial action will be required to assure that contaminants are not migrating
 eastward, beneath  the ponds.

 Alluvial deposits  of North Criner  Creek can be separated into upper and
 lower portions that  act as  a  single unit hydraulically.  Nested monitoring
 wells in the  alluvium indicate  a general upward gradient through these
 deposits, implying upward  flow  out of Stratum IV into the alluvium.  Pumping
 tests indicated an overall effective  permeability on the order of 5 x 10
 cm/sec.  Transmissivity values  range  greatly in the alluvium, however, the
 overall  transmissivity  is  about 3200  to 3500 gpd/ft.  Effective porosity
 ranges  between 0.25  and 0.30.

Groundwater flow  in  the alluvium of North Criner Creek is generally toward
 the Creek, though  skewed down-valley.  Contaminants detected in the alluvial
 aquifer are also  found  in  the source  areas of the site.  The concentration
of total volatile organic  compounds (which include toxic substances such as
 1,2-dichloroethene and trichloroethene) are several hundred ppb i  at least
three alluvial aquifer wells.   In  general, North Criner Creek for- 3 the
discharge boundary to groundwater  flow from the site, limiting mi  -ation of
contaminants  across  the Creek.

-------
 1130
900
                                         BARREL MOUND/
                                         MAIN PIT-
                      HIGHWAY 122
                        SOUTH POND
NORTH
CXIHER
                                   A (Stratum I, II,  III and upper

                                      Stratum IV)
                          B (lower Stratum  IV)
                       SCHEMATIC CROSS SECTION
                                 FIGURE 4-4

                        HYDPOGEOLOGIC CROSS-SECTION

                           HARDAGE/CRINER SITE

-------
                                    4-8


4.2  Site Contamination

During the site operations, approximately 21 million gallons of industrial
wastes including acidic, caustic and corrosive wastes, many classified as
carcinogenic, were disposed on the Hardage site.  During and after the
operations, waste liquids migrated downward from several unlined impoundments,
principally the Main Pit, North Pit, and West Pond (mixing) areas and to a
lesser extent from the Sludge Mound, and East Pond (mixing) areas, and
random spills on the site.  Presently, approximately 70 acres of groundwater
on and adjacent to the site is contaminated by organic compounds.  Ground-
water contaminant plumes have migrated east and southwest of the site.
Contamination has entered the North Criner Creek alluvium, and has recently
had a low hut measurable impact on surface water quality (August 7, 1989
sampling).  Surface and shallow subsurface soils at and around the source
areas are contaminated by.low levels of metals.  Approximately 278,000
cubic yards of highly contaminated material exists in the Main Pit, Barrel  Mound
and Sludge Mound which contains soil, sludge, waste liquid, and intact
drummed waste.

4.2.1 Impact of Disposal Operations

During operation of the site, several potential sources of groundwater
contamination existed.  These were:

o  Main pit/Barrel mound
o  Sludge Mound
o  North Pit
o  West Pond (mixing) areas
o  East Pond (mixing) areas
o  Miscellaneous spills, drum leaks, etc.
o  Contaminated runoff paths and south pond

Since liners were not constructed in any of these areas to limit waste
seepage, and since the permeability of the soil profile and shallow bedrock
is relatively uniform across the site, it is believed that those areas
where waste liquids were impounded for the longest periods of time
contributed most to groundwater contamination.  The longer-term liquid
storage and disposal areas were the Main Pit, Barrel Mound, Sludge Mound,
West Pond, North Pit, and to some extent, the East Pond (see Figure 1-2).
The remaining areas contributed lesser amounts of contaminants to groundwater
contamination for reasons as follows:


o  Miscellaneous Spills - these were due to the nature of operations.
   Although drums were occasionally stored on site, the typical practice
   was  to immediately discharge or dump wastes into the pits upon receipt.
   Therefore, spills probably did not release large volumes of waste liquids.

-------
                                    4-9
o  Runoff -.No information exists to indicate any impoundments  were  breached,
   or liquid waste was directly released except for limited seeps.   Rainfall
   presumably contacted wastes, dissolving contaminants and carrying them  down
   slope from the source areas.  However, the contaminants in runoff would be
   highly dilute, as compared to that in waste pits.  In addition, any
   infiltration of runoff would be transient, as compared to the continuous
   release from pooled waste liquids such as those in the main  pit.

4.2.2 Remaining Contaminant Sources

In addition to contaminants which have dissolved into groundwater beneath
and adjacent to the site, .several potent "sources" exist which  will  tend to
release further contamination from the site.  These sources are:

a) Main Pit/Barrel Mound
h) Sludge Mound;
c) Residual  soil contamination in the North pit and immediately west of the
   main pit; and
d) NAPL in bedrock beneath the source areas.

The content and character of these four sources is generally as follows:

a) Main Pit/Barrel Mound:
   The Barrel Mound was built by random dumping of drums and the periodic
   spreading of soil to allow further drum dumping.  As a result, the
   Barrel  Mound is highly variable.  Based on the history of disposal
   operations and data from three exploratory borings done in 1988,  the
   mound consists of a two to three foot cover of native soils  underlain by
   randomly oriented drums mixed with soils and waste sludges.   At a depth
   of 5 to 10 feet, drilling yielded little data other than the depth to
   liquids,  due to minimal core recovery.  The liquids present  at the base
   of the Barrel Mound appear to consist of a 6 inch layer of waste  floating
   on water (L-NAPL or light non-aqueous phase liquids); 4 feet of water;
   and 4 feet of heavier than water wastes (D-NAPL or dense non-aqueous
   phase liquids) on the bedrock surface (see schematic illustration,
   Figure 4-5).   The Barrel Mound would, due to the nature of its construc-
   tion, be expected to have a large number of voids in and around drums.
   This expectation was supported by difficulties encountered in closing
   one boring (high grout take) and the inability to hail down  waste liquid
   levels in two other borings.  The other significant finding in the barrel
   mound borings was the apparent contamination of bedrock immediately
   underlying wastes.

   At its southern end, the Barrel Mound grades into the Main Pit.  The
   Main Pit is predominantly contaminated soil, however, concentrations of
   drums similar to those found in the Barrel Mound are present in about
   1/3 of the main pit, particularly along the west hank.  Locallized pools
   of waste, similar to that in the Barrel Mound, are likely to be present
   in the Main Pit.  While exploratory borings did not encounter such pooled
   liquids,  areas of drum concentrations, those areas where pooled liquids
   would most likely be present, were intentionally avoided in drilling.

-------
                                                           -ion  vauove  MSL)
               o
               o
                                         N)
                                         o
        •— c
        •  O.
        PO fD
        o o
        -i c
         3
                        CO
                       . ft,
                     U1 fD
                     •   3
                     O 0.
                     O)  Ol
                     n  ->-
                     T  3
 CO
 O!
 01
en
03

o
O
O
       tn w ^<
                 O o en
                 O o o
                 o o o
ua
o
3
(/I
Ol
_J
«t
o
3
t/>
<
at
CL
O
i/\
V
ro

N
O
3
ro
a* a, ai

•^ ^^ Md
o o o
333
«/> t« to
•o -•."<*
o 3 a>
0 Q.
— Q. 0
cn
0
c
ft
n
n
>
i-t
n
cu
CO
tw T I/I
CL c a>
3
— * on fvi
-• «_ o
-Q 3
«= fD
                                CL

                                01
H

<-(
(D
(B
                         •o
                          c


• ' ' : ,-, \ s
- 1 1 AS
- -i ... .;• A-
1 ••• :« - .- A
                                    o  a>
                                    co  i-i
                                    ro  i-t
                                    co  ro
                                       i—'
                                    O  CO
                                    3
                                       o <»
                                       >^i n
                                          3-
                                       CT ID
                                       <~\  ro
                                       >-h -a
                                       O  i-l
                                       ^  ro
                                           CO
                                       H-  ro
                                       H-  3
                                       h-1  rr
                                       C  01
                                       CO  rr
                                       rt  H.
                                       1  O
                                       flj  a
z

•a
i—i
H

>
Z
O

CD
                                                                                                                             M
                                                                                                                             O
                                                                                                                             c
                                                                                                                      z
                                                                                                                      o

                                                                                                                      n
                                                                                                                      »
                                                                                                                      o
                                                                                                                      Crt
                                                                                                                      co
                                                                                                                       I
                                                                                                                      w
                                                                                                                      M
                                                                                                                      n
                                                                                                                                 O
                                        o
                                        3

-------
                                    4-11
   Approximately  113,500 gallons of liquid are present in the soils of the
   the Main  Pit/Barrel Bound  (vadose zone) which together total  3.62 acres.
   An estimated 18,000 drums  are buried in these areas representing some
   660,000 gallons of stored  liquids.  (This assumes that two-thirds of the
   drums may be full).

b) Sludge Mound:
   The Sludge Mound consists  of layers of contaminated soil, oil recycling
   residues, and  styrene tar  wastes.  Borings in the Sludge Mound indicated
   pockets of moist "stringy" sludge in addition to the overall  soils cont-
   amination.

   Approximately  58,000 gallons of liquid are present in the Sludge Mound
   (totalling 1.72 acres) weakly held in soil pores under capillary forces.

c) Residual Soil  Contamination:
   The former North Pit is underlain by a number of pockets of contaminated
   soils and 50 to 80 drums buried in shallow trenches.  Sediment in the
   drainage channel along the west side of the Main Pit has been heavily
   contaminated by waste seepage from the Main Pit to a depth of five to
   ten feet.  Contaminated soils are also present in the west pond area.

d) NAPL in Bedrock:
   Pure free-phase (NAPL) has been observed at three locations adjacent to
   the source areas (B-13, MW-6, and MW-2).  These wastes are present both
   at the water table and in  the deeper more competent sandstone (Stratum
   III).  The NAPL tends to be several thousand times as contaminated as
   the surrounding groundwater.  However, similar to an oil layer floating
   on water, the  separate phase waste cannot fully dissolve into the water.
   In the subsurface, clean groundwater tends to pick up dissolved contaminants
   as it flows around and through the NAPL.  In this manner, the NAPL acts
   as a potent source of continuing contamination within the normal ground-
   water flow regime.  Pockets at and beneath the water table are in a
   position to readily contaminate the surrounding groundwater.

   Liquid accumulations have  created a pool of liquids at the bottom of the
   main source areas estimated to he 956,000 gallons (see Figure 4-5).

The Main Pit, Barrel Mound and Sludge Mound are the largest sources of
potential further site contamination.  Exploratory borings have indicated
that these areas  consist of 278,000 cubic yards of wastes.  Chemical sampling
has indicated that some 171,500 gallons (113,500 + 58,000) of volatile
chemicals are suspended in the soil vadose zone.  Pooled liquids and intact
drums are estimated to total  1,616,000 gallons (660,000 + 956,000),
although precise  quantification of the volume is not possible.

Table 4-1 lists a number of EPA classified carcinogens detected in  the
source area characterization  holes.

-------
                          Table  4.-1
             CARCINOGENS1 DETECTED IN THE SOURCE
                AREAS CHARACTERIZATION  HOLES2
      Compound	                 Class
 2,4,6-trichlorophenol                   12
 bis(2-chloroethyl)ether                 B2
 1,4-dichlorobenzene                     B2
 2,6-dinitrotoluene                      B2
 1,2-diphenylhydrazine                   B2
 isophorone                               C
 N-nitrosodiphenylamine                  B2
 bis(2-ethylhexyl)phthalate              B2
 butyl benzyl  phthalate                  C
 beno (a)  anthracene                     B2
 benzene                                  A
 1,2-dichloroethane                      B2
 1,1,2,2-tetrachloroethane               C
 chloroform                               B2
 1,1-dichloroethene                      C
 methylene chloride                      B2
 tetrachloroethene                        B2
 trichloroethene                          B2
 PCB-1260                                 B2
 toxaphene                               B2
vinyl chloride                           A
 1,1,2-trichloroethane                   C
  EPA classifiedcarcinogens
  Reference:  USEPA,  Health Effects Assessments Summary
    Tables, Second  Quarter,  1989.

2 Source USEPA (1985)
CVOR211/034.50/1                                      September 27,  1989

-------
                                    4-13
 4.2.3  Pathways  and Extent of Contamination

 Contaminants  have been transported on and away from the site hy groundwater
 flow.  Additional contaminants have also migrated from the source areas hy
 way of surface  water  runoff; however, sampling data from wells in the alluvial
 aquifer  indicate that groundwater flow, rather than surface water runoff,
 has been the  predominant pathway for migration.  Groundwater containing
 dissolved contaminants migrates vertically and southwestward toward the
 North Criner  Creek alluvium and then upward into the alluvium and into the
 Creek.

 Upward migration of groundwater from Stratum IV into the alluvium of North
 Criner Creek  is documented by upward gradients in water levels of wells
 constructed at  different depths in the alluvium.  If contaminants are
 entering the  alluvium primarily from the underlying bedrock (Stratum IV)
 and moving upward, contaminant concentrations should be higher in the lower
 part of the alluvial aquifer than in the upper portion.  Conversely, if the
 contaminants  are entering the alluvial aquifer primarily by percolating
 downward from the surface runoff water, the concentrations in the upper
 groundwater should be higher than in the lower groundwater.  Sample analyses
 data from two different depths in the aquifer (wells MW-12S, -12M and MW-13S,
 -13M) show that the volatile organic chemical concentrations are greatest
 in the lowest portion of the aquifer, indicating that the contaminants have
 probably migrated through the bedrock from the site and into the lower
 alluvium (as  opposed to the surface water pathway) (Reference, Affidavit of
John B. Robertson).

During site operations, volatilization of chemicals into ambient air resulted
 in the release  and transport chemicals offsite.  This pathway was reduced
with closure  of the pits and capping of wastes.  No residual effects have
been identified, and none are believed to exist from air pathway transport
due to the volatile organic nature of contaminants.  At the present time
 and in the near future, transport of contaminated groundwater and discharge
to surface waters are the only pathways of consequence.  If the site is not
properly remediated, contaminants will also eventually be released from the
site in substantial quantities by erosion and runoff and to a lesser extent
through slow  volatilization to the atmosphere.  As contaminants are exposed
there would be  an additional pathway for risk through direct contact with
contaminated  materials.  The above pathways are discussed in further detail
below.

Groundwater:

The principal pathway of contaminant migration at the Hardage site is through
dissolved phase groundwater flow.  Groundwater contamination emanating from
the source areas extends approximately 600 to 800 feet to the east farm
ponds.  The contamination plume extends offsite to North Criner Creek,
approximately 1600 feet.  The plume in the alluvial aquifer is distorted,
both parallel to and towards North Criner Creek.  Overall, the groundwater
plume underlies approximately 70 acres on and adjacent to the site (Figure
4-6, Area 3).

-------
APPROXIMAT:
GROUNDWATEl
FIGUEF: 4-6
  ra

n PI
o x
2 H
H W
2 O

                                                                        I \ 1 1 \ 1 1
                                                                i a   Sis
                                                                J ;   53?
                                                                is   i

-------
                                    4-15


The groundwater contaminant plume contains a wide variety of volatile
organic chemicals which include toxic compounds such as 1,2-dichloroethene
and trichloroethene.  A summary of contaminants and their concentration for
onsite wells  is presented in Table 4-2.  Beneath and immediately adjacent
to the source areas  (Figure 4-6, Area 1) volatile, semivolatile, and pesticide
compounds are present at their highest levels, in some cases exceeding
25,000 pph for volatile organics.  At three locations NAPL has been encountered
(MW-6, 8-13,  and MW-2).  Additional pockets of NAPL are almost certainly
present in other areas beneath the source areas, particularly at the Barrel
Mound.  A somewhat larger portion of the plume (Figure 4-6, Area 2) contains
both volatile and semivolatile contaminants, but not NAPL.  This, the
"semi-volatile plume", extends over 600 feet eastward to where the plume
discharges into the east farm ponds.  To the southwest, the semi-volatile
plume extends only about 200 feet (to well MW-45).  Contamination by volatile
organic chemicals (VOC) is most widespread and defines the extent of contam-
ination.  The VOC plume extends southeast into the alluvium of North Criner
Creek (see Figures 4-6, Area 3).  Contaminated groundwater flowing southwest
through the onsite bedrock discharges to the alluvial aquifer.  This discharge
constitutes the source of continuing contamination in the alluvium (see
Figures 4-4 and 4-7,.  Average flow rates along this pathway have been
estimated at  110 feet per year (Affidavit of John B. Robertson).

Discharge of Contaminated Groundwater to Surface Water:

Both the east farm ponds and North Criner Creek receive contaminants via
discharge of  groundwater to the surface waters.  The contaminants entering
North Criner Creek are chlorinated ethanes and chlorinated ethenes.  Since
these chemicals are volatile, natural processes rapidly strip volatiles
from the surface waters, and release them to the air.  Sampling of North
Criner Creek has only most recently detected contamination (1-2 dichloro-
ethene, 5 ppb and trichloroethene approximately 2 ppb), and supports the
belief that the discharge of contaminated groundwater can have a measureable
impact on surface water quality in the Creek.

Volatile chemicals also enter the east farm ponds.  Sampling to date has
not indicated the presence of volatiles; however, more persistent
semivolatile chemicals are seeping into the southernmost east farm ponds
and are impacting water quality in the immediate vicinity of the seeps.
These compounds appear to be entering the farm pond due to seepage of  NAPL
along the bedrock surface.  Dilution of this seepage is presently occuring
so that impacts on water quality of the pond have not been measureable.

-------
H
ca

-------

-------
M  O
•Z  M
    C/J
W  H
H  70
30  M
>  CO
H  G
M O
•Z H
a o
    H
H >
3: r1
M
G  H
<  i-(
M  I-1
a  «

So
    so
    n
    en
             a
             »
             PI
             *>
            -\

-------
                                    4-19


Surface Water Runoff and Sediment Transport:

Surface water runoff and sediment transport will constitute substantial
pathways for contaminant transport from the site over the long-term if the
site is left unremediated.  Vegetation over much of the site, including
the source areas, is sparse due to the removal of the topsoil in the course
of site operations.  The lack of vegetation contributes to soil  erosion.
In addition, the final contour of the waste mounds is not conducive to
long-term stability.  Leachate seeps from the western side of the waste
mounds are common in the wet, spring months.  Rainfall runoff tends to
spread this leachate downslope, resulting in visible contamination as far
southwest as the existing interceptor trench.

4.2.4 Future Contaminant-Migration

Left unremediated, contaminants will continue to migrate off of the site and
spread on the site by the following general pathways:

     1. expansion of the plumes of contaminated groundwater;
     2. leakage and spread of waste liquids from the Barrel Mound and
        Main Pit, which will in turn continue to feed the plumes on
        contaminated groundwater;
     3. dissolution of contaminants by groundwater infiltrating through the
        the Sludge Mound, Main Pit, Barrel Mound, and areas of residual
        contamination; and
     4. transport of wastes and contaminated soils from the Main Pit,
        Barrel Mound, Sludge Mound and adjacent mixing areas via erosion
        and runoff.
     5. long-term low-level releases of volatile compounds to the atmosphere

The groundwater contaminant plumes present at the Hardage site have developed
over the 17 years since operations started at the Hardage site.  Left
unremediated, plumes of contamination in the vicinity of both the east
farm ponds and North Criner Creek will expand.  Modelling of the southwest
alluvial  plume in the Remedy Report (EPA, 1989) predicted a gradual expansion
approaching 2000' (with dilution) even with the source of contamination to
the alluvium cut off.  Without source control and groundwater remedial
actions,  the southwest alluvial contaminant plume would certainly continue
to expand southeastward, parallel to the stream.  The plume near the east
farm ponds may expand eastward beneath the ponds, although this is uncertain
due to remaining questions about groundwater and surface water interaction
acting as a barrier to migration around the ponds.

Waste liquids in the Barrel Mound and Main Pit will continue to migrate
into the surrounding bedrock and groundwater in accordance with the
conceptual model illustrated in Figure 4-5.  Liquids  in the Barrel Mound
are released as drums of waste liquid corrode and as  liquids drain from saturated
soils (under gravity and consolidation).  These liquids drain downward through
the permeable mounds and accumulate on the less permeable sandstone and
siltstone bedrock surface at the base of the pit.  This pool of waste  liquids
tends to drain downward under gravity through pores and fractures  in  the
shallow bedrock.  As the liquids move downward  some 10-15 feet below  the
base of these pits, they encounter a less permeable bedrock  horizon and
tend to spread out across the upper surface of  that horizon  and migrate
with a lateral component, as seen at locations  MW-2 and MW-6.

-------
                                    4-20
In their present condition, the source areas are susceptible to infiltration
of rainfall.  As this water percolates downward through the source materials,
it dissolves contaminants and carries them downward to the groundwater
system.  This is a potential continuing source of release on the site.

Over time, erosion of contaminated soils is expected to increase to a point
where substantial offsite releases occur via erosion and runoff.

-------
                                    5-1


5.0  SITE RISKS

The Hardager site received hazardous wastes that are either known or
suspected carcinogens such as vinyl chloride and benzene.  Table 4-1 gives
a more complete list of carcinogens found at the site.  Other compounds
either are or are believed to be acutely toxic or capable of causing damage
to specific organs.  Some of these compounds also bio-accumulate in plant,
animal, and human tissues.  The Hardage Site was permitted to receive all
types of industrial and hazardous wastes except radioactive wastes.
Table 2-1 lists some of the wastes known to have been received at the site.

There are four primary ways humans can be exposed to the hazardous wastes
at the Hardage site.  The first and most important of these is exposure to
contaminated groundwater. -The groundwater at the Hardage site is contami-
nated with waste migrating from the source areas into the bedrock and
alluvial groundwater systems.  Not only is the groundwater under the site
contaminated with these hazardous wastes, hut the contamination has spread
beyond the site to the south and has already forced local residents to stop
using their water wells.

The contaminated water wells are located in the North Criner Creek Alluvium
which lies below the Creek south of the site.  This aquifer is contaminated
with the chemicals exceeding the standards for consumption of drinking water
as set under the Safe Drinking Water Act that are also given under the
column titled MCL in Table 4-2.

As Table 4-2 shows, eight of these contaminants are already above the
limits.  The nearest of the contaminated residential wells is the old
Corley well.  The old Corley well is located approximately 500 feet
southwest of the site.  Estimates of the risk of cancer from lifetime use
of residential water contaminated at the level of the old Corley well range
from 0.0007 (seven per ten thousand) to 0.006 (six per thousand) far above
the one in one million level commonly used as an acceptable risk.  These
estimates were arrived at using average concentrations of contaminants in
the old Corley well and making assumptions about standard ingestion of
water, inhalation exposures and dermal exposures from household use.

-------
                                    5-2
With the North Criner Creek alluvium already contaminated, one of the goals
of the cleanup will be to restore the groundwater to a useable condition.
The standards used to judge the effectiveness of the cleanup alternatives
for groundwater will be the Maximum Contaminant Levels set under the Safe
Drinking Water Act (MCLs).  The effect of the proposed cleanup plans can
be compared through their effects on the concentration of contaminants in the
North Criner Creek alluvium.  The proposed EPA remedies would result in
lower concentrations of contaminants in groundwater in the alluvium of North
Criner Creek through removal and destruction of contaminants at the source
and interception and treatment of groundwater by trenches.  While it is not
possible to accurately assess how long the source areas would continue to
bleed contaminants into the groundwater systems, it does not require and
expert to conclude that if- the HSC remedy leaves 10 or 100 times more of
the most problematic waste liquids in the site than EPA's remedy, then the
long-term duration of the EPA remedy would he shorter.  The EPA remedy would
therefore attain MCLs more quickly than the HSC remedy.

Direct contact with wastes on the surface of the site also poses hazards;
however, the health risk is highly variable depending upon area of exposed
waste and level of human traffic and has not been quantified.  Human
traffic on the site is minimal; but cattle did occasionally graze on the
site.  Contamination of the food-chain (for example beef and milk from cattle
eating contaminated grass) by lead, chromium, pesticides, and PCBs on the
surface of the site poses long-term hazards.  This concern prompted construction
of a fence to keep cattle and people off of the source areas.  Certain
compounds such as pesticides and PCBs have the ability to bioconcentrate
through successively higher levels of the food chain (EPA, 1985a).

Inhalation of volatiles and concentrated airborne particulates on and
possibly adjacent to the site may also pose long-term hazards if the site
remains unremediated, but again this risk is highly variable depending upon
the quantity of exposed contamination.

-------
                                    6-1
6.0  DESCRIPTION OF ALTERNATIVES

A large number of remedial alternatives have been formulated to address part
or all of the Hardage site.  As discussed in Section 3, the site has been
considered as two "operable units".  Source Control measures were considered
by EPA in a  1986 FS.  In November 1986, EPA issued a ROD which selected a
Source Control remedy with incineration of liquid wastes and stabilization
and containment of solids in a new landfill to be built on-site.  HSC objected
to the selection of this Source Control remedy and proposed an alternate
Source Control remedy in December 1986 which called for in-place containment
of the waste source areas by a cut-off wall and groundwater pumping.  HSC
declined to  implement the EPA selected remedy which resulted in litigation
in 1986.  EPA maintained that the remedy selected in the 1986 ROD was
technically  sound and completed the Source Control Remedial Design in 1988.
In 1987, HSC signed a partial Consent Degree with EPA for the conduct of an
RI/FS for groundwater (Management of Migration).  In May 1989 HSC, pursuant
to the Consent Decree, submitted a draft FS on Management of Migration to
EPA for review and approval.

During conduct and preparation of the groundwater RI/FS, uncertainty arose
over the impact of RCRA Land Disposal Restrictions on the EPA selected
Source Control remedy.  To alleviate this uncertainty, EPA undertook considera-
tion of an alternative Source Control remedy based upon the new technology
of in-situ soil vapor extraction.  Evaluation of soil vapor extraction in
conjunction with alternative presented in the groundwater FS resulted in
consideration of alternatives addressing the entire site in contrast to the
original Operable Unit approach.  On June 30, 1989, the United States
advised the District Court of EPA's decision to consider a comprehensive
site remedy.

On July 6th and in greater detail on October 13, 1989 the defendants presented
to the court their plan to further define an additional remedial alternative.
This, the HSC alternative, was similar to EPA's alternative except that the
HSC plan did not include soil vapor extraction, enhanced recovery of container-
ized liquids, or the shallow waste liquid recovery trench proposed by EPA.

Previous and new alternatives for the control of the contaminant sources
are summarized below in Section 6.1.  Alternatives for groundwater as
contained in the groundwater FS are summarized in Section 6.2.  Common
monitoring and support components for Groundwater and Source Control
alternatives are listed in Section 6.3.  Finally, Source Control and
Groundwater alternatives are combined and summarized in Section 6.4.

-------
                                    6-2
6.1  Alternative Source Control Components

A number of alternatives were considered for remediation of the Source
Control areas prior to the 1986 ROD.  These can he seen in more detail  in
the 1986 ROD in Appendix F, along with evaluation criteria for remedy
selection.  Those remedies which were considered fell  into four basic
categories:  no action; disposal onsite in a landfill  (the EPA selected
remedy in the 1986 ROD); containment of wastes in place (the HSC counter
proposal of a cut-off wall); and incineration (also considered in the 1986
ROD).  The following four sections summarize each of these categories.

 6.1.1  No action.  As the title implies, no work would be done to mitigate
        hazards from the site. The alternate water supply, security fence,
        and site stability measures would not be maintained.

 6.1.2  Onsite Landfill (EPA 1986 ROD Remedy).  The source areas would be
        excavated and separated for treatment.  Organic liquids would be
        bulked and shipped offsite for thermal treatment at a permitted
        facility.  Inorganic liquids would be treated and discharged to an
        onsite impoundment for evaporation.  Solids would be stabilized by
        blending with 8-10% cement kiln dust and placed in a new double
        lined landfill cell constructed on-site in accordance with the
        Minimum Technology Requirements (MTR) of RCRA.  The 1986 estimate
        of most probable cost was 70 million dollars.

 6.1.3  Containment of wastes, Cap and Cut-off wall (HSC Proposal).  A
        plastic cement "cut-off" wall would be constructed in panels so as
        to encircle the source areas.  This wall would range from 70 to 130
        feet in depth and, at its base, key 10 to 20 feet into the low
        permeability siltstone and mudstone of Stratum IV.  Wells would be
        drilled through the Source areas and completed in the bedrock within
        the periphery of the wall.  The water and wastes would be pumped
        from these recovery wells in an effort to induce a hydraulic gradient
        inward through the wall and prevent the outward migration of contami-
        nants.  Pumping would be conducted indefinitely.

        Vertical  waste liquid extraction wells would be drilled into the
        Barrel  Mound and pumped in an effort to remove pooled liquid for
        treatment.  In addition, lateral drains would be drilled from the
        west into the base of the Barrel Mound.  These drains would slope
        slightly downward out of the mound to allow free drainage of waste
        liquids  and groundwater from the Barrel Mound over time.

        An  effort would be made to speed consolidation of the Barrel Mound
        by  placing a 20 foot thick soil layer as a surcharge for a period
        of  6 months to a year.  After removal of the surcharge, a MTR cap would
        be  installed over the source areas.  The most probable cost estimate
        was  25 million dollars.

-------
                                    6-3
  6.1.4   Incineration  (EPA Proposal  in  1986 ROD).  The source areas would he
         excavated.  Wastes would he  incinerated in a kiln constructed onsite
         or  at  a commercial incinerator offsite.  The ash would still  contain
         metals and until it could he proven otherwise through de-listing,
         would  require disposal as a hazardous waste.  Estimates in 1986 for
         cost of incineration ranged from 133 to 374 million dollars.


The no action  alternative was eliminated from consideration early as  not
being protective of human health or the environment due to continued  vertical
and lateral migration source area wastes offsite.  Containment of the
contamination  in place was eliminated due concerns over continued migration
of the contamination, doubts that containment techniques such as slurry
walls could be installed effectively, and concerns relating to merely containing
the sources of contamination rather than actively remediating them to achieve
a permanent reduction in their volume, toxicity, or mobility.

The alternatives that remained were onsite disposal and incineration.  The on-
site landfill alternative was eventually selected as providing a degree of
protection to human health and the environment similar to that which  could
be achieved with complete incineration, hut which could he carried out in a
shorter  time and at a reduced cost.  A more detailed comparison is given in
the 1986 ROD in Appendix F.  With this background, onsite disposal was
selected in the 1986 ROD.

The new  alternative for Source Control in the October 1989 Proposed Plan
contained components for a new approach to Source Control.  These
components are as follows:

6.1.5  Liquid Extraction Wells

A system of vertical  extraction wells would he installed throughout the
three main source areas.  The wells would he used for extracting free liquids
that are found in the source areas, and liquids that would be released from
the drums as a result of the lancing procedure described below, should it
be used.  The wells could also he used as part of the soil vapor extraction
process described below.

An estimated approximately 956,000  gallons of aqueous and nonaqueous liquids
presently reside in the saturated portions of the source areas.  The quantity
of residual liquids trapped within the unsaturated portion of the source areas
is estimated as at least 170,000 gallons.

Additional liquids are likely to be found in drums buried in the source  areas.
Assuming that one third of the 18,000 drums estimated to be in the Main  Pit/
Barrel  Mound contain organic liquids, an additional 660,000 gallons of
liquids may be present that require removal and offsite disposal.

The liquids pumping operation is not expected to remove all of the free
fluid found within the source areas due to localized pooling between wells,
nor will it address the liquids residing in the unsaturated zone.

-------
                                     6-4
 The nonaqueous-phase liquids removed from the  extraction wells and trenches
 will he sent to a hazardous waste treatment, storage,  and disposal (ISO)
 facility for incineration.

 6.1.6  In-PTace Drum Lancing

 One method considered to assist in the removal  of  the  liquids  remaining in
 the buried drums was to lance the drums in place.   The lancing process
 would release the liquids for subsequent removal by the wells  or  through
 the soil  vapor extraction process (see Figure  6-1).

 The lancing effort would be accomplished using commercially  available
 construction equipment capable of driving solid spark-resistant Cu-Be
 rods to subsurface depths greater than 40 feet. The lancing would take
 place throughout the Barrel Mound and in areas of  significant  concentration
 of drums  in the Main Pit.  'Magnetometer data highlighting areas of drum
 concentrations would be used to select appropriate areas in  the Main Pit
 for lancing.

 The lances would be advanced to the bottom of  each target area at a nominal
 triangular spacing of 22 inches.   The released liquids would be collected
 and removed via the extraction wells, a U-shaped trench (described
 later), or the soil  vapor extraction system (described later).

 The progress of the lancing operations would be controlled by  monitoring the
 rise of fluid levels in nearby extraction wells.   The  effort would be made
 to prevent the accumulation of fluids to greater levels than those that
 currently  exist in the source mounds.  Non-aqueous phase liquids  (NAPL)
 released by the lancing process and removed in the liquid extraction system
 would  be sent to a TSO facility for treatment  and  disposal.

 While  lancing was  considered as an option for  the  removal of drummed
 liquids, excavation of drums has  several  advantages over lancing  for the
 removal of liquids.   These include the assurance that  all liquids are
 removed and the elimination of the introduction of additional  liquids to
 the vadose zone on the short-term.

 6.1.7   Drum Excavation

 Liquids in  drums from the Barrel  Mound and the west side of  the Main Pit
 can be  removed  from the source areas by excavating the drums as originally
 intended in the 1986 ROD instead  of performing drum lancing.  The
 excavation  option  would remove free liquids directly from the  surface
 and from any drummed liquids in the source areas by direct removal.  It is
 expected that  excavation,  utilized successfully at a number  of other sites,
would he more  efficient than lancing in removing free  and containerized
 liquids in  the  Main  Pit/Barrel  Mound.  Figure  6-2  indicates  areas that
would be targeted  for drum excavation.  Drums  that are removed from the
 source  areas  would  be staged for  sampling and  consolidation  with  similar
wastes.  Drummed organic liquids  would he consolidated for offsite treatment
and disposal.   The  liquids would  he transported to a hazardous waste treat-
ment, storage  and  disposal  (TSD)  facility for  incineration.  Aqueous liquids
would be treated onsite by the groundwater treatment facility.  Any drums
containing  solids,  or having solid residues in them after liquids are removed
would be placed  back  into  the source areas.

-------
                   ****************************
                   *****************************
                   ****************************
                   ****************************
                   ****************************
                   ****************************
                   ****************************
                                                             LANCING MACHINE
BOTTOM OF

SOURCE AREA
      ttfteftt
      xxxxxxxx
      xxxxxxxx
      xxxxxxxx
      xxxxxxxx
      xxxxxxxx
      xxxxxxxx
§	r
77^v
-------
                      FIGURE    6-2

AREAS  TARGETED  FOR  DRUM  EXCAVATION
                                   BARREL  MOUND AREA
                                  LEGEND
                                         EXTENT OF DRUM REMOVAL
                                         DRUM CONCENTRATIONS
                                         SCATTERED DRUMS
                                         AREA OF SIDE SLOPES
                                         EXPECTED TO BE REMOVED
                                         TO FACILITATE DRUM  REMOVAL
                                   MAIN  PIT AREA
                                                100
                                                         20O
                                          1  INCH - 100 FEET

-------
                                    6-7
 6.1.8   Excavation  of  Wastes  in Adjacent Areas

 Contaminated  surface  soils and waste materials located away from the source
 areas  will  be excavated  and  transported to the source areas.  These materials
 will he consolidated  under a temporary cap for soil vapor extraction along
 with trench excavation materials and other materials generated during imple-
 mentation of  the remedy.  The greatest concentration of contaminated soils
 and wastes  away from  the source areas occurs in the North Pit area, where
 up to  80 drums of  wastes as well as contaminated soils are believed to be
 buried, and in the West  and  East Pond Areas (see Figure 1-2).

 If contaminated water or liquid wastes are encountered in these drums, they
 will be treated in the groundwater treatment facility to surface water
 discharge standards,  or  taken offsite for disposal, whichever is appropriate.
 The contaminated solids  and soils will be remediated as part of the overall
 remediation program,  once they are placed within the source areas and capped.

 6.1.9   Soil Vapor  Extraction and Treatment

 Soil vapor  extraction would be conducted in the three main source areas as a
 means to further capture and destroy the liquids present.  Soil vapor
 extraction  is expected to remove a large volume of the highly toxic and mobile
 volatile organic compounds present in the source areas.  The soil vapor
 extraction  systems would consist of a network of extraction wells screened
 in the  contaminated (vadose) zone of the Main Pit/Barrel Mound and Sludge
 Mound.  The dual-purpose extraction wells installed to remove liquids would
 be used  as  part of the vapor extraction system.

 The liquids pumping operation is not expected to remove 100 percent of the
 liquids present.   Numerous field studies have shown that in excess of 40
 percent of  the available liquids may remain trapped in the unsaturated zone
 following gravity  drainage and pumping efforts.  While not readily amenable
 to pumping, these  residual liquids are subject to further removal by vapor
 extraction.

 Soil vapor  extraction works by drawing air through areas containing contami-
 nation  thereby creating a vacuum in the source areas (see Figure 6-3).
 This, in turn results in a high evaporation rate of volatile and semi-volatile
 organic compounds, including significant quantities of toxic and carcinogenic
 contaminants  that  are in contact with groundwater and atmosphere.  Such
 contaminants  evaporate into the air drawn into the mounds.  The contaminated
 air is  then extracted through air extraction wells and is treated o'.site  to
destroy the   ontamination.

 If lancing  -  used, vapor extraction is also expected to remove a
 significant   uantity  of the liquids that remain trapped in the drums.

 If there are  pockets  or  low  spots in the mounds between the liquid
 extraction  v  11s,  the vapor extraction process will further aid in the
 removal of  "  ^uids that  cannot migrate towards the extraction wells.

The air stn  n and vapors removed by the soil vapor extraction system will
be treated    ing the  Best Available Control Technology for thermal destruction

-------
                                              men
                                             m>
  O


  O

-------
                                    6-9
of toxic vapors prior to discharge to the atmosphere.  Vapors generated by
the groundwater treatment system will also he destroyed in this thermal
treatment system.

6.1.10  Source Area Capping

Two types of source area capping are planned for the site.  A temporary
cover would he installed during remediation activities, and a permanent RCRA-
compliant cap would be installed once soil vapor extraction and liquid
extraction activities are complete.  The temporary cover will consist of
compacted, minimum 1-foot thick, low-permeahility soil with vegetation to
minimize erosion.  Repairs will be made as needed to compensate for damage
from settlement and erosipn.

Permanent RCRA-cap installation would he initiated once the drummed liquids
are removed, soil vapor extraction has been completed, and the liquid extrac-
tion wells have been decomissioned.  The cap will be location over the Main
Pit, Barrel Mound and Sludge Mound areas as illustrated in Figure 6-4.

Section 6.2  Groundwater Remediation Objectives and Alternative
Groundwater Components

In addition to the new components considered for Source Control, remedial
alternatives for contaminated groundwater were developed and described in
detail  as part of the Management of Migration Operable Unit RI/FS reports.
All alternatives were developed assuming some form of concurrent Source
Control  remedial action.  The alternatives were developed in light of the
overall  goal of restoring groundwater to its beneficial use within a reason-
able timeframe.

Consideration of the hydrology and contamination of the bedrock aquifer at
the site has led to the conclusion that restoration of bedrock groundwater
underneath the source areas is technically impractical over a reasonable
time period (a few decades).  This conclusion is supported by the fact the
some D-NAPL has escaped from the source areas and will continue to serve as
as source for dissolved contaminants in groundwater.  Also, some contaminants
have diffused into dead-end cracks and fine-grained pores in the rock matrix;
those materials will take a relatively long time to diffuse out of the
pores and cracks during an active or passive restoration program.  In  view
of these facts, the most effective way to address groundwater contamination
onsite is through various -ontainment efforts designed to control the  spread
of groundwater plumes and  ~otect downgradient areas  from future plume
migration.  Such efforts w 11 be significantly aided  by source control
actions that in a timely manner permanently reduce the potent source liquids
which continue to load the groundwater system with contaminants.  Consequently,
component alternatives wer  screened and refined based on their effectiveness
in meeting the following c jectives:

     o intercept and captu  • groundwater that is migrating towards the
       alluvial aquifer an  the east farm ponds, thereby protecting
       offsite areas from   jture contaminant impacts,  and commencing
       the process of natu  tl restoration in the alluvial system;

-------
 on
 o
 G
 TO
 n
33
M


n
>
-a

-------
                                    6-11
     o monitor and control contaminated groundwater discharge to North
       Criner Creek to assure that Oklahoma Water Quality Standards for
       North Criner Creek and Criner Creek are met; and

     o prevent domestic and agricultural use of contaminated groundwater
       through continued supply of alternate water to affected residents.

In view of these objectives, ERM-Southwest, on behalf of the HSC (and
pursuant to a partial Consent Decree with EPA) developed and evaluated  21
remedial action alternatives by combining 6 remedy elements (see Table  6-1).
Details of this analysis is presented in the Management of Migration FS.
All of the initial alternatives developed included groundwater and surface
water monitoring, as well as actions to minimize runoff from the source
areas.  All alternatives relied on institutional controls (such as deed
restrictions) to prevent the use of potentially contaminated groundwater
as a drinking water supply.  The alternatives also included continued
operation of alternate water supplies to nearby residents.

Screening of these alternatives was conducted in the FS based on effectiveness
in containing and capturing contamination, and cost.  Six groundwater alter-
natives were retained after this screening for detailed analysis, and were
summarized below:
   Alternative
Description

No Action

Primary Controls - institutional controls on groundwater
use, maintenance of alternate water supplies, and surface
water controls to limit the discharge of contaminated
groundwater to surface water.

Alternative B and Alluvial Recovery - groundwater recovery
from the North Criner Creek alluvium using a well network
or interceptor trench system (see Figure 6-5)

Alternative B and Alluvial, South Pond and Southeast
Area Recovery - groundwater recovery from the North
Criner Creek alluvium, from bedrock southwest of the
Main Pit, Barrel Mound and Sludge Mound, and from
bedrock east and southeast of these three source areas
(see Figure 6-6) using a well network or interceptor
trench system

Alternative B and South Pond Area Recovery - groundwater
recovery from bedrock   >uthwest of the three main source
areas using a well network or trench system, with the
the option of a local   it-off wall along the site fence
boundary in place of a  umber of recovery wells

Alternative B and Main  Source Area Recovery  - groundwater
recovery associated wi' i source control measures using
a well network.

-------
(A "O
M
•o •<
So
a O
sf
rt a>
Si
(»



x



X











X










r Imary con
loremedlitl
outheasl R<
0 O "
S . 2,
•< 3
a —
3
Ul

C

x



x




x











X





r Imary 'con
loremedlatl
rea and sen

»!;
n v>

2 | *
"*




x




X






X




X




I
r Imary conl
loremedlat I
rea Recovel
•< o •*
3 o
a* w>
i_
Ul 3
Is

e
•o
|
X



X




X






X









O
m TS
i Imary conl
1 or emed 1 a 1 1
Wi
•B
3
a
3

c
x



X




X
















-n
M 13
r Imary conl
nd southea;
sl
g >
< c
<
Q»



-

X


X













X




WI WI *O
r Imary conl
oulh Pond i
outheati Ri
n — ^
I 2r
* a >
c
<
^

X



X


X








x




X




o
JO M "5
r Imary Conl
nd south P(
ecovery
Q. O
it
=
<
E

X



X


x








"









o
o 5
n —
3 S
o. -•
So
It 3
s|
< fl»
ft 3
•^ a
—
1
a*
x



x


X


















09
13
I
O
w*





x



X





















*
NO ACl IOn"






X


























Remedy
I
3
**



!
'o
3
O
° 2
| f
0 -
n —
S|
i:
— ^
» c
— OB>
S 0
* o
It C
o > —
0-3-
< 
-------
en
3
a
n
a*
les element Is in
rt
C
a

a
3
o

i*
3
»
W
i
A

M
i
3
fit
<
n

ft
ft
3
3
(O
C

<*
(9









C
^ (9 O "
<% n £ —
» S ^ -
f controls . At luv
'ond, Southeast
ry and Main sourc
?covery

a*




x






x



x












x



x


x
H
§*7
»,i
i control s . Main
scovery. soulheas
'ond Recovery,

.§
3 ^
a n



x






x
















x



x


x
VI
IS-
S » -
r controls . south
•cover y and Main
Area Recovery
.1 	

I
Q,



X






X
















X






M

S f» O —
n o a*
* S !<
™ IP ^
> o a
 <• — 3
» •< J -
(> 3 O
O M • —
S3 «•
Q. Ul •
2«2-
-< S — 3
3 W<
•o —

t C




X






X








X







X






X
O
i o —
* 3 2
f control s , in si
sdlat Ion. and Mai
Area Recovery
3 — >
C




X


•



x








X














X
T3
<» n O. —
».s?
A _ 2E _^
i controls . Al luv
j|h Pond Area
V and Main sourc
"coverv
<* —
Q»




X






X



X












X






X
O
ft rt ~
- s i
i control s . Al luv
ry and Main sourc
"cover y

M




X






X























X
Z
i -
S ?
1 controls and Ma
Area Recovery

3




X






X
























I
§ -
a -
1 controls and
is) Recovery






X






X




















X



^
88-
f ; \
Y controls
'ond Area and
is I Recovery






X






X
















X



X





JB
fmedy Elements




1
2.

o

3"
 —
O - 3-
< <*
(V » "V
•< 3
Si
n —
Sf
1* »
JO
-• n
3S
  O  V)

  i  i
"5s  =
   —  —  a
   —  r»  —

   -  I
   •<  3

-------
                                                        POND
                                                                             HOMESTEAD
                                                             LEGEND
  WELL LOCATIONS AND NUMBERS ARE
  APPROXIMATE AND ARE SHOWN FOR
  CONCEPT ILLUSTRATION PURPOSES ONLY.

  SOIL REVEGETAT10N AREAS ARE NOT EXACT
  AND ARE SHOWN FOR  CONCEPT ILLUSTRATION
  PURPOSES ONLY.
                                 SURFACE SOIL
                                 REVECCTAT1ON

                                 RECOVERY
                                 TRENCH OR
                                 WELLS
                                                                         MONITORING WELL


                                                                         RECOVERY WELL
ERM-5oothw«st, inc.
NEW ORLEANS, LOUISIANA
         HOUSTON. TEXAS
 DATE   05/24/89
W.Of."  7663A001E89
                FIGUF  6-5

     ALTERNATIVE C  Si : SCHEMATIC
SECOND OPERABLE  UNI"  FEASIBILITY STUDY
          ROYAL HARD 3E SITE
           CRINER,  OK

-------
                                                      PONO
                                                              W


                                                              I

                                                              ?


                                                              I
  WELL LOCATIONS AND NUMBERS ARE
  APPROXIMATE AND ARE SHOWN FOR
  CONCEPT ILLUSTRATION PURPOSES ONLY.
  SOIL REVEGETATION AREAS ARE NOT EXACT
  AND ARE SHOWN FOR CONCEPT ILLUSTRATION
  PURPOSES ONLY.
                                RECOVERY
                                TRENCH OR
                                WELLS
                                                                       MOM TOW NC WELL


                                                                       RKOVEITt  WELL
ERM-Soflthwest. inc.
NEW ORLEANS. LOUISIANA
         HOUSTON, TEXAS
 DATE   05/24/89
W.O.NO.  7663A001E89
               FIGURE 6-6


     ALTERNATIVE  E SITE SCHE  'ATIC
SECOND  OPERABLE  UNIT FEASIE  JTY STUDY
          ROYAL HARDAGE SITE
           CRINER, OKLAHOMA

-------
                                     6-16


 Alternative  E  (illustrated  in  Figure 6-6)  involves the recovery of contaminated
 groundwater  in  the  southwest alluvial area of North Criner Creek and onsite
 groundwater  recovery  west,  south,  and east of the main source areas.  Alter-
 native  E  has been modified  and includes two groundwater components.  The
 onsite  interceptor  system is known  as the  V-Shaped Trench.  The southwest
 interceptor  system  is known as the  Southwest Interceptor Trench.  Both the
 V-shaped  and Southwest interceptor  trenches would he capable, in combination
 with Source  Control components of  the comprehensive remedy, of modifying
 groundwater  gradients at the site  so as to contain and capture groundwater
 and D-NAPL migrating  from the  source areas and off the site.

 A third trench,  known as the U-Shaped Trench, was considered by EPA during
 the development  of  groundwater alternatives in order to prevent uncontaminated
 groundwater  in  the  vicinity of the  Main Pit/Barrel Mound from coming into
 contact with the source waste  materials during remediation, as well as to support
 source  liquids  removal operations  by intercepting lateral seepage that may
 ensue from the  source areas.

 These three  recovery  systems could  be installed at the site to capture
 contaminated groundwater migrating  towards the alluvium and the east farm
 ponds,  provided  Source Control  measures are also instituted.  Collected
 groundwater from any  or all of these systems would be treated onsite
 to discharge standards before  discharge to North Criner Creek.  These
 collection systems  are illustrated  in Figure 6-7 and each is further described
 below:

 6.2.1  U-shaped  Trench

 The first trench, known as  the U-shaped trench, would intercept shallow
 seepage issuing  laterally from the  Barrel Mound and the Main Pit and to
 collect contaminated  groundwater from Stratum I in the vicinity of the
 Barrel Mound and Main  Pit.

 6.2.2  V-shaped  Trench

 The V-shaped trench would intercept  and collect contaminated groundwater
 from all bedrock zones existing above Stratum IV.  The trench will be
 located so that  groundwater contaminants already migrating eastward
 towards the east farm  ponds will be  captured by the trench, negating the
 need for additional  gorundwater recovery measures east and southeast of
 the trench.

6.2.3  Southwest Interceptor Trench

The Southwest Interceptor Trench is  to intercept and collect contaminated
 bedrock system groundwater  prior to  its natural discharge to the offsite
 alluvial aquifer along North Criner  Creek.  The trench will extend to Stratum
 IV and will collect contaminated groundwater from all bedrcx zones above
 Stratum IV.  A system  of extraction  wells could be used as an alternative
to the Southwest Interceptor Trench  provided they are equally effective at
 intercepting and collecting contaminated groundwater.

-------
11 SO
1100-
10SO-
1000-
930-
900
                WOMINANTLY
               SANDSTONE

STRATUM II PHEBOMNAHTLYMUOSTONS
HIGHWAY 122

  SOUTH POA/0
                             STRATUM III SANDSTONE. S1LTSTONE
                  SOUTHWCST 7PfA/CH
                                              FIGURE
                                    SITE CROSS :  £CT!ON
                                    SHOWING TRf  ^CHES

-------
                                     6-18
 6.2.4  Ground Water Treatment  System

 An  onsite_treatment plant  would he  provided to treat collected groundwater
 and surface  water.   The  plant  would he  sized to handle flows from the
 groundwater  collection trenches and the surface water collection system.
 The plant  incorporates appropriate  treatment processes to handle hoth
 organic and  inorganic contaminants  as necessary.

 Following  treatment, the plant would discharge to North Criner Creek.  The
 plant  would  he designed  to meet the applicable discharge requirements set by
 the Oklahoma Water  Resources Board  and  the Oklahoma State Department of
 Health.

 6.2.5   Alluvial  Ground Water Restoration

 Contaminants already present in the alluvial aquifer would he allowed to
 dissipate  hy natural dilution, biodegradation, and flushing.  Future
 contaminant  inputs  to the  aquifer will  he abated hy the trenches and the
 Source Control  elements  presented above to allow restoration to Maximum
 Contaminant  Levels  in the  North Criner  Creek alluvium.  If alluvial
 monitoring reveals  that  estimated natural restoration time and plume
 dilution rates  are  not being met, then  active restoration would be
 implemented.   An  increase  in contaminant concentrations in the alluvium
 after  trench  installation  and  pumping,  or a decline in the mass of
 contaminants  of  less than  40 percent in 10 years, would trigger active
 restoration  in  the  alluvium.

 6.3  Monitoring  and Support Components


 6.3.1  Remedial Support Facilities

 Several components  are needed  to support the implementation of the remedy.
 These  site control  facilities  consist of a command post, medical services
 station, close  support analytical laboratory, sanitary facility, equipment
 maintenance  shop, decontamination facilities for hoth equipment and
 personnel, and a  supply  center, gate guard, and communication center.

 6.3.2   Institutional Controls

 Institutional controls,  including fencing, deed restrictions, and
 maintenance of the  availability of  an alternate water supply system would
 be implemented to restrict access to the site and contaminated groundwater.

 6.3.3   Surface Water Controls

 During  implementation of the remedy, surface water drainage from the sourc
 areas would he collected as needed.  Berms would he constructed to divert
 uncontaminated runoff water away from the working area to minimize the
 generation of contaminated water.   A retention pond would he used to col It .t
 and store surface water  prior  to treatment.  A Treated Water Retention Por
would also he used  to store treated groundwater prior to discharge to the
 surface drainage  system  for North Criner Creek.

-------
                                    6-19
 Once  the  temporary cover  is  in place and the remedy has been implemented,
 surface water control and treatment would not he necessary.  The diversions
 would he  maintained over  the  life of the remedy as a means to control
 erosion of the cover.

 6.3.4 Remedial Monitoring

 A monitoring program would he instituted as part of the remedy to verify
 that  the  migration of contaminants has heen halted.  Streamwater in North
 Criner Creek would he monitored periodically for an indefinite future time
 to provide assurance that surface water discharge limits are not heing
 exceeded  downstream.

 A line of monitoring wells at the downstream end of the alluvial
 contamination plume would-he  used to provide assurance that the plume is not
 expanding downgradient in the alluvial aquifer ahove acceptable levels.

 The quantity and quality  of  liquids collected from the trenches would also
 he monitored.  The effectiveness of the trenches in maintaining the desired
 hydraulic gradients and capture zones will he monitored hy a series of
 piezometers positioned along  lines perpendicular to the orientation of the
 trenches.

 Bedrock groundwater monitoring wells (hoth new and existing) would he used
 to further verify the effectiveness of the trenches in controlling the
 spread of contaminated ground water.

The cap will also he monitored periodically to assure that differential
 settlement or erosion processes are not compromising the integrity of the
caps.

Monitoring would he used  to  verify that the quality of downstream water
 resources is not heing jeopardized during the natural restoration process.

Air quality would he monitored hoth onsite and at the site fenceline to
assure that hoth onsite action levels and Maximum Amhient Air Concentrations
are heing met during remedy  implementation.

6.4 Comprehensive Alternatives

From all  of the components described in Sections 6.1, 6.2  and 6.3,
three comprehensive remedial  alternatives were assembled for consideration.
These three alternatives, the Revised EPA Remedy, the Partially Revised  EPA
Remedy, and the HSC Remedy are described below and in Table 6-2.

-------
                                     6-20
 6.4.1   Common  Elements

 Certain of  the components  from  Section  6.1 are  included in all three of the
 comprehensive  alternatives.  These  are  Institutional Controls (6.3.2),
 Surface Water  Controls  (6.3.3), Remedial Monitoring (6.3.4), and Remedial
 Support Facilities  (6.3.1)

 6.4.2   Revised EPA  Remedy

 The Revised  EPA Remedy  is  a  new source  control  remedy combined with ground-
 water  collection  and  treatment.  This remedy would remove a substantial
 portion of  the liquid wastes, including many highly toxic and mobile
 volatile organic  compounds,  from source areas,  thereby reducing the volume,
 toxicity and mobility of'hazardous  substances at the site.  It calls for:

 - Liquid Extraction  Wells (6.1.5)
 - In-Place  Drum  Lancing (6.1.6)
 - Excavation  of  Wastes in Adjacent Areas (6.1.8)
 - Soil  Vapor  Extraction and Treatment  (6.1.9)
 - Source Area Capping  (6.10)
 - U-shaped  Trench  (6.2.1)
 - V-shaped  Trench  (6.2.2)
 - Southwest Interceptor Trench (6.2.3)
 - Groundwater Treatment (6.2.4)
 - Alluvial  Groundwater Restoration (6.2.5)

 6.4.3   Partially  Revised EPA Remedy

 This remedy  is  essentially the same as  the Revised EPA Remedy except that
 the buried drum concentrations in the Main Pit  and Barrel Mound would be
 excavated (6.1.7) rather than lanced, and the U-shaped trench would not be
 needed.  The use  of excavation assures  that all drummed liquids are removed
 and eliminates  the short-term introduction of additional free liquids to
 the vadose zone resulting form lancing.

 6.3.4   The HSC  Remedy

This remedy  is  described in  the Remedy  Status Report which the HSC filed
with the Federal  District court in Oklahoma City on June 30, 1989 and described
 in greater detail in  the HSC's Preliminary Design Report dated October 12,
 1989, and also  filed  with the Court.  It includes the following elements:

 - Liquid Extraction  Wells (6.1.5)
 - V-shaped Trench (6.2.2)
 - Southwest Interceptor Trench (6.2.3)
 - Excavation  of Wastes in Adjacent Areas (6.1.8)
 - Groundwater Treatment (6.2.4)
 - Alluvial  Ground Water Restoration (6.2.5)

The HSC Remedy also includes capping of the three main source areas, but
with a  less effective cap than that proposed in the EPA remedies.  The HSC
cap does not meet RCRA requirements.

-------
                                   TABLE 6-2
SOURCE CONTROL
Excavation of Drums
Liquid Extraction Wells
Drum Lancing
U-Shaped Trench
Soil Vapor Extraction
Consolidation & Cap-
ping
GROUNDWATER
V-Shaped Trench
Alluvial Recovery
Common Groundwater
     Elements
                               HARDAGE SITE
                      COMPARISON OF ALTERNATIVES
                       HSC REMEDY
X
X
X
            REVISED EPA
              REMEDY
                X
                X
X
X
            PARTIALLY REVISED
               EPA REMEDY  w
                    X
                    X

-------
                                    6-22
The HSC remedy does not contain the following Source Control components
integral to both of the EPA remedies:

 - Drum Excavation (6.1.7)
 - Soil Vapor Extraction and Treatment (6.1.9)
 - In-Place Drum Lancing (6.1.6) & U-shaped Trench (6.2.1)
   (in Revised Remedy)


A comparative analysis of each of these remedies is the subject of Section 7,

-------
                                    7-1


 7.0  Comparative Anaysis

 The  remedial alternatives described in Section 6 have been assessed in
 light of  criteria defined in CERCLA Section 121.  This Section of CERCLA
 specifies that remedial actions must:

  - Be protective of human health and the environment;

  - Attain applicable or relevant and appropriate requirements (ARARs);

  - Be cost-effective;

  - Utilize permanent solutions and alternative treatment technologies or
   resource recovery technologies to the maximum extent practicable;

  - Satisfy the preference for treatment that reduces volume, toxicity, or
   mobility as a principal element or provide an explanation in the ROD as to
   why it does not.

 In addition, CERCLA places an emphasis on evaluating long-term effectiveness
 and  related considerations for each of the alternative remedial actions
 (§121(b)(l)(A)).  These statutory considerations include:

A)  the long-term uncertainties associated with land disposal;

B)  the goals, objectives, and requirements of the Solid Waste Disposal Act
     (i.e., RCRA)

C)  the persistence, toxicity, and mobility of hazardous substances and
    their constituents, and their propensity to bioaccumulate;

D)  short- and long-term potential for adverse health effects from human
    exposure;

E)  long-term maintenance costs;

F)  the potential for future remedial action costs if the alternative
    remedial action in question were to fail; and

G)  the potential threat to human health and the environment associated
    with excavation, transportation, and redisposal or containment.

Nine evaluation criteria have been developed to address the CERCLA
requirements and considerations listed above, and to address the additional
technical and policy considerations that have proven to be important  for
selecting among remedial alternatives.  These nine criteria are discussed
in a memorandum entitled "Interim Guidance on Superfund Selection of  Remedy"
from J. Winston Porter, Assistant Administrator dated December 24,  1986.
The nine criteria are organized into three groups:

Threshold Criteria:

1.  Overall  protection of human health and the environment;

-------
                                    7-2


 2.  Compliance with  applicable or relevant and appropriate requirements (ARARs);

 Primary  Balancing Criteria:

 3.  Long-term effectiveness and permanence;

 4.  Reduction of volume, toxicity and mobility through treatment;

 5.  Short-term effectiveness;

 6.  Implementahility;

 7.  Cost

 Modifying Criteria:

 8.  State acceptance;

 9.  Community acceptance.

 If an alternative satisfies the threshold criteria, it is eligible for
 further analysis under the Primary Balancing criteria.  The comparison of
 alternatives is given below as well as in Table 7-1.  This comparative
 analysis provides the basis for EPA preference for the EPA excavation
 remedy.

 7.1  Overall Protection of Human Health and the Environment:

 The EPA excavation remedy provides the most overall protection of human
 and the environment.  Both the EPA remedies provide short-term protection
 through the provision of alternate water supply the maintenance of site
 security, and land use controls to prevent exposure to contaminated
 groundwater.  Although the EPA excavation remedy involves certain additional
 short-term risks in implementation, these risks can be significantly reduced
 or eliminated, primarily through controls on the emission of vapors and
 dust during excavation.

 The EPA remedies provide long-term protection through the removal of a
 substantial volume the most highly toxic and mobile contaminants present
 in the source areas.  The EPA excavation remedy is more effective in the
 removal of these contaminants than the EPA lancing remedy.  Further long-
 term protection is provided by continued monitoring to assure that the
 remedy components continue to function as expected.

The HSC remedy provides the least overall protection of human health and
 the environment, particularly over the long-term. It would leave a large
 volume of untreated, toxic and mobile compounds, both in buried drums and
 in source area soils. These contaminants would pose a continuing threat
 threat to human health and the environment.  The HSC remedy does not
address the liquids from the source areas until they have migrated to the
 interceptor trenches.  This process will take a long period of time,
 resulting in considerable uncertainty.  The HSC remedy also relies on
 institutional controls to limit exposure to contaminated groundwater and
 surface water.  The long-term maintenance of institutional controls

-------
Sf » 30
IP ^^
• n so
SB
n M
«i
n °
X OB
n =T
S 3
Q 3*
ja
n Si
5. o
3^ »

a.3 3 3 8

»

Reduces the potential
contaminants being released f
sources, migrating away f
sources, and escaping from dc
gradient collection areas
offsite.
w ^ 3 2 _*,
&? 3 3 2
p Mitf m?iiiffis>
§.|* § a. 8 af 1 ^H^'S ? S |.|.iL8
-i8- asr«§» gsi a?-8-, |a
— — o ^-v £? a £• ST. 3 o CL a o 3 » 3 2
85 ? Q 5' ** 3l!-cro_.3oE.Q"33
_ n Soo • « a 9 o ~ 2. 3
is g-"aSS »a-S||l'2s|
2.8. 5 o » jf Q. ™ « ^8 § ffSa
s* 3. « 3 Q9 o 3 =- s; 3. — 2' *> »
MM ^* ^^? ^Me ^S ^^ ^5 **.' !3 *0 SS* ^3
n O^>n3 § ZT n 2 os 3Q.
2JL "^flflQIlB3^ CO S ** Si 3 •••
•" gsisg 2»--.»<'so'?3;aj
3 P"^ 8s»~ eg n-^»,3^nQ.
2 < H o 3. flTa.o<»ri?c/3g
i-o'sr§ » g B g 3 § ^ » i"2
§ 5^§» s, 1 2.1" B 8 1 1.!" 1


on
Q

?3
n
3
o
a





• • •
*es^o^c2 ^t2*^?!"^no/0 S-S1*
92.|§siff 2. •losisf «3«
fi^ias-His F|?g^H| ss|
*l « S. - <3 ««3S§»| 2 a. 8
3^° 3^-^ » 5-S"3.338 i'S.8
o^aBrt-n BB o»asi«::° oSs^.
2- «133^ ««3^Sg» 3~j?
o- -§S? Sg-gl^S. |o«
i-° o §3*5 aS^.§ 5- jfi- 33-3
^-^2^1^ 135s-! i5 ' Ii
UN lSlin i!
»* 2. «« £» 3 2 3SOC«3 a> 5,-n
n3 "o SS2'*>2*11^ w J^
» — Ssej^^,*1 o^
3c7nnv^^ 3D.a:«3'rtS» o.°?

3" «»"



. B

HH1!! P!
HHS 5}tMa« i?
fs-il|lj Uf
1 asti: HSH-l ?il
— s s^ a, o a y s tt 5>-
°8i:3 2, |iess?s =|
33ga«« ^-|g.£-os 3- g-
« ff 1 g 8 § So^^K-g 2^
~|22|8 S|^c£5' 1 Ii
•^^•-••o"^, — • E. «< c. ^ •" "* ai2
3^nrt2§in 5S>rnn5'r»2, a.0?

EPAV Remedy
With Excavation


•
O
£

i
?
»»
s*
a

•^
. 9B
e
•
!
f^
0
B
1 the Environment
















8
1
5
3S
o
z
w
e
Table 7-1
MMARY ACCORDING TO
3
>
»
•<
n
RITERIA



-------
          flip
          &S£§->a
             v>
           g 0
              £§ c I
              a M 3 <
               5? —' '
           rt 2 a —•=
           OB ^ 3 o c
           M  » 2 =/
            3 3 £ S

           llis I
            83 Sg
                      3!" ;*•




                      09 3
                    w*

                    S o

                    g-3
                    £ »
                      Cn

                      C
                        oo

                        n
                        e«*

                        ?3
                        rt


                        n
            1°
            •^
            5*

            i
            ^
                              5
                f?
 o o
s to
3     *• ft £T.
     03 S o


  i^Ilo
   e CX n O
                   |0-
                   Q. 3
                   as 3
                   £ n
                   a«
                   s*
                    ea



                    I


                    i
     3 2
     2.3
3 ™

Ir
   o"£.O>STBSH ^->

   (gQE^gg.? 5
       * e.S
       r*  c«
   '
          -
^ a O » S 5' <'  C
« S _ a 5-£ § if  >
                2.
               -
        ;jl
.  n IS
 OB a =•
 3 M § 5' - - «
 C^3 = = =:OS
  n   - *»


 I'slfSlI
             21

             il
gq A
« 8.
M
g o

frg

3.2
s*
  M
  C
                    0
                    o
                    rt

                     »»•

                     8?
                     S 3
                     * rt

-------
       S° » £<
       o?3 25'2
       §3 &3^

       3 9 50 -
        S X "*» Q
Mil:

Frll
Q.O O —*<•
 •y ^*

if ilf
        «A
          -a,589
          3* 3 ..
          O 0.0.
                 CTJ =r "C 2. 03 _j
                 £ft C/5£2 3
                 >g O^S1™
                 «•i ••• * 5.,
                 2 a -. =n 2
                          oe 5
                          as-
        sagg/S
        *** ^^ *• ^4

        f|i|*
        r- O ~ 9--.
S
V3
Q
6«"

9
n
                                   f
                              M

                              f
                      3 » S2. « •«
                      li^^S
                      a sag.
                      S/ o 3. Q.


                      Ifll8

                      all2?
                      —. «n 09
                      f* fi e*
                 rt&°"s
            SB"  S. 8 o 2 5

           *Kff  mi^
            I If  s-lj^
            M «  r-l  s
                  S'H  3
                  f» 5? 03 3
                             3 rt
                             2 3
                             5' o
                             OQ.Q.
for co
Exca
tech
cont
Pit/
redu
    |S,| 228 S

    » o 5 |  Is
v> ~

     q? c
slSI-aS.
-i ft C. ft 3 U
• The dej
manageme
minimized
are remov<
i> -« w
aS"S3
09 x n
3 M 3
O. C ft
M n
=; rt ft o
« n % ~>
* X 09
«• O -J
«•) «M t\J
J* 3 *< _
P- SB O
i.15
mm *^ 1
i «
09 rt
3 — r "^
•» Z 3
M ft 3
•
3 5,2- 2.^
la|fi.
|>Ifs
*^ "* S
O 9 3 CM O
^» O 5 "i
_ . •* 09
f"^
3** I
2. o o "i ft
a§ o n •«
HI if
— • _. 3 Oq
K* 300^.
• — M f?
3* 3 "•
ft 47 03 3
^^s
-2
m«-
S?
ol 3
•T ^*
o'3-
3 ^^





-------
                  III

                                C/5
                                o
                                n
Reduction
                                rt
                                
ment
                                  SZ
                                  — ft
                                  	, ^i
g-jn
8§

II

Sf

I?

» «
M* **
ST ^
n g

 o'

     II1H? f?f  If  1

       -

               1

as
3

BS
55-0.
                     f!
                     sl

        .M
          2. n

          Is
                   i
                          e ™
                          §3-
                          ||
                              2
                              •^^ v»

                              S'*

-------
-i f> ea
i S-o
S Q
         n =.  5
              is
IEL
2.1
£5
        TO
        ft
        sr
   n
   x

   S
   n
   to

   Q.
3 I.
5\3


l|


 I'
•a rt S
T2. os^
3 -*
OP ~ Ct
•  ars-
   "S
  w n

  ^3.
                    rt 0
                         ^9-
                                9


                                S?
                               I
                               Me

                               ^
V
i'g"
"S-l
3 «
9 ••*
rt *
3
» o
2; 3
i'«
^ 0
il
= 3
ITS
3<*
fa
3 e
£•3-
' S
•
§3?*
09 03 3 ft
CSP S. 3 09
J*83
S »>2 S
fst§
5" 3
2 0 09 <
• S' 3 S.
»* SJ
*• — cr
?3 «
S g-o
3 I 5
u p^
^ "* n
£ n
2. •»
^* or o
3-*ig Q.
                        S?
                        =•>
                        m»'
                        8 »
                        n? ft
                        ~ n
                        s'*

-------
                     s?
             O

             <*>'




             j
                     w
                     w
                    8


                    5'


                    I
g'S

1»
18.
I
et
  I
o 9

i
        BO

        a
            ^
            I?
             -
a
e

2.
    I « <
    SB «i ee

    *•!•§
    «^2 o
    CA O ^
    -. n v>
    3 "
    O Q
    O.OQ 03

    ^•> ft a •

    sai
    65 —


    Si§
    V Q. Q.


     £3

     §•2.
     3*<

-------
               s

               I
               n
               3 I
               - »

               i'a
               n
               3 FT
               s§.
                    on
                    n
                    6»r

                    50
                    n

                    3
             «

             i
 ff»BJ
 3" -n <*
§   89 3
   O O

5*3 I'I?
I*-3*
      I s-r
      I«|

      « a 2.

      S-S*
      n - 3-
      •   ea
 3SS
3 Sip
T3 S =
•* •• s
3 O."
         t» w
         •as

         s&

         08 o


         II
         S3*
  i^-»>

  5I
  £.3
                  ^
                  0?
                             PS
                            B
                            B
    « 2. 2 H
    o *5 S •?

    LIE
SV
con
ope
cha
< c ^

1^1

«sl
n 0)
c. t«

K (t
— v>
        0
        S
S?glm

8SB.
s.ai
••• W  ^M.
P "  2
 £»i
 88.
      •a S =:
       3 * -c
       5 » S
       n 3 Q"
       3 a. w
               01
 I??
8 50
g n

ȣ
ff. ft

-------
= 8
3 -•
E^B

o' 3

= 8
>  3
       QJ
           N) QJ



           IP
           =• v>
           O ~

           3 II
O
                           r

-------






























-

*
oi oi ro oo
3 Q. x rf
Q.C-I. rf 01
at -j rf
(/> o 01 ro
o ro o
-•• 3 rf m
—j rf -•• C
o -o
< Oi 3 T3
Ol -J • O
ra ro -i
O Oi ro rf
•J (/> X 
« o
ro oi — >
X O < -••
n- 01 01 .a
T "O rf c
Oi T3 -i. -•.
O -•• O Q.
rf 3 3
"^ * tf}
O - 0
3 -f.
«


*
ro o ro oo
X Oi X rf
rf ~o n oi
-J -O Ol rf
oi -•• < ro
O 3 Oi
rfto rf (/>
-•.. -— c
O O -0
3 Oi 3 •Q
• 3 O
Q. O T
-*» rf
i/) in
O Oi
-.. Q. — •

Ol r\
< n c
oi ro -••
•o 3 a.
O rf
T ro
Oi X
T rf
ro T
Ctf flu
to n
• rf
o'
3
































*
•0 -» oo oo
C -<• Oi rf
3"  -h ai
— • *• ro rf
-«. rf ro
0 rf«<
• 0 3"
O Oi
f. -ft w>
0
T a. o
7C -J O
ro c 3
-530
t/i ro
— < -j
Oi QI 3
3 3 in
a. n
_.. -j
rf 3 ro
3* (O (Q
ro ai
Qi T
3 Q.
Q. -••
3
(0
*
rf 1/1 oo
O Oi rf
-f, O)
i ro rf
O rf ro
T ^<
?^ 3*
ro o ai
i -h t/>
(/!
ro o
Ol X O
3 n 3
a. oi n
< ro
rf oi -1
3" rf 3
ro -<• 
o
•O 3 T
c ro
C^ Cu tQ
— • 3 Ol
-»• Q. -J
n a.

-" 3
O^lQ


*


ro oo
— •* rf
ro oi
3 rf
ro ro
3
rf in
vn C
. -a
•a
o
-i
rf
in

0
o



3

-J
ro
2
ro
Q.


*
ro oo
— ' rf
ro a>
3 rf
ro ro
3
rf co
in c
« -a
•a
o
-j
rt


o
O



3

-J
ro
S3
ro
Q.
*<
*
ro oo
— ' rf
ro oi
3 rf
ro ro
3
rf in
en C
• -o
•a
0
-J
rf
m

O
O

3[
0
3

•^
ro
fD
a.
^


*


oo o
n- o
ai 3
rf T3
ro o
3
€ ro
0 3
c rf
_4 (/)
CL
Ol
•a -j
T ro
ro
•^ Ol
ro n
-s n
ro
§"^
rf
T Oi
ro or

-s ro
ro -

< c
O) rf
*
3 « oo
ro oi rf
3 rf oi
rf ro rf
-j ro
ro
— ' -5 (/»
ro ro c
33-0
ro o -a
3 < O
rf 0) -j
4/» — ' rf
• in
Ol
3 01
Q. — '

rf
-J CQ
ro i
Ol O
rf C
1 3













^r*
00
o
«
in

•X)
ro
3
ro
a.
^^













3C m
—i. ~&
rf >
3" -
in
I—
01 33
3 ro

^* ro
3 CL
US ^<







Q.



*
ro £ oo
— ' Oi rf
ro rf oi
3 ro rf
ro -j ro
3
rf T in
(/» ro C
§~O
•a
< o
CW T
— « rf
in
at
3 Oi
a. — <

rf
T !£)
ro T
Oi O
rf C
ro a.
3
rf





£
-.. rn
rf -D
3" J»
•
m in
x
O ^3
QI ro
< 3
oi ro
rf QL
— *• *•<
O
3









CO "-" — 1
« f) Q)
O 3-
3 — •
oo rf ro
rf -<•
Ol 3 ^|
rf c I
ro ro i— *
a.
-^ ^_j
o
o
ro
•a
rf
at
3
O
ro








































































-------
~i  o
ro  o
     n
     o
Q)  < C
3  01 3

3     r-r
CD  a/ "•<
3  3
r*  Q.-Q
       -J
oo  a. ro
o  ro -t>
c  oo ro
~i  rr ~t
O  T oo
ro  c
oo  n 3
        o
        3

        O
                                     o
                                     o
                          o —i
                          o  ai
                          3  -3-
                          r-t" —i
                          --• ft)
                          3
                          C  -~J
                          ro   i
                          Q. I—
                           o

                           oo
                           73
                           ro
                          ro
                          a.
                             O
                             n
                             ro
                            •a
                             <-»•
                             O)
                             3
                             n
                             ro
 T Q. r*  O
 ro ro  —  o
 3 oo  o  3
 ro n- 3  3
 Q. -i  fl>  C
<< =  — '  3
 •   O      -••
    rr -J  re
    — ro <<
    O  3
    3  O  l/>
        <  C
    _i. O) "O
    3  — '-a
            o
    el- Qi  T
    3" 3  rt
    ro  o.  oo
           a.
           a.
                 oo
a>
3
n
                 ro
                      3  a.
                     oa <<
    3- ro  o
    ro  3  3
       o  3
    rn <  c
    -a a»  3
    -J  Oi *<
    ro  3
    3  a. 
    ro      c
    a. CL-O
   <<  ro T3
    •   oo  o
       n- -j
       -I  rf
       C  00
       n
       _i. a,
       rr Q.
       O  Q.
       3  -••
       3 O
          3
             m oo
             x
             n  73
             a*  ro
             <  3
             ai  ro
             (-1- Q.

-------
                                    7-13


 results  in  further  uncertainty.

 The EPA  remedies take  a more direct approach to protection of human health
 and the  environment.   The first element of this is the removal of contaminants
 from the source areas  and destroying them.  By removing and destroying the
 contamination at the source, any uncertainties as to their future threat are
 minimized.

 The threat  to human health and the environment is most acute from those wastes
 which migrate the easiest and by those which are known or suspected to cause
 cancer.  The EPA remedies both protect human health and the environment through
 the rapid removal and  destruction of those contaminants that are the most
 mobile and  carcinogenic.  Both minimize contaminant migration through the
 elimination of contaminants at the source not only through removal of
 liquids through extraction wells and either excavation or lancing of drums,
 but have the added protection of soil vapor extraction (SVE).  The SVE
 system is predicted to remove 99% of the volatile, carcinogenic wastes from
 the source  areas.  When they are destroyed following their removal the threat
 from these  contaminants will have been eliminated.  In addition to controlling
the contamination at the source, the EPA remedies also protect against
 those contaminants which remain through the groundwater recovery trenches
and elimination of infiltration with a regulatorily compliant cap.
Therefore,  the EPA remedies have the multiple protection of extensive
 removal and destruction of the contaminant sources combined with a ground-
water collection and treatment system to capture any residual contamination.
The primary element of the HSC remedy, on the other hand, is groundwater
capture and treatment  alone.

In terms of two EPA proposals, the comparison is basically between the
excavation of the buried drums or lancing them in association with the U-
shaped trench.  Both activities have elements of risk associated with
implementation, but the risk associated with excavation of the drums is
less than that of lancing as discussed in Sections 6.1.6 and 6.1.7.  .
Therefore the combined remedy retaining excavation of the drums is overall,
more protective.

-------
                                     7-14
 7.2 Compliance  with  ARARS:

 Section  121  of  CERCLA  provides  that, except under certain narrow
 exemptions.,  remedial actions  shall  comply with Federal and State laws that
 are legally  applicable or  relevant  and  appropriate to the contaminants and
 circumstances of  the site.  The process by which potential ARARs are
 identified,  screened,  and  analyzed  to determine if they actually are ARARs
 is  described in "CERCLA Compliance  with Other Laws Manual" (EPA 1988a).
 The alternatives  described  in Section 6.4 are broken down below into
 remedial elements to facilitate the analysis:

 ARARs may be identified in  three general classes:

 1.   chemical  specific  - for example, a  drinking water "MCL" defines a
                        maximum acceptable concentration for drinking water;

 2.   action specific -  for  example,  a landfill built to accept hazardous
                       wastes would  have to meet RCRA 264, Subpart N regula-
                       tions and associated requirements on design of the
                       landfill;

 3.  location  specific - for  example, the hazardous waste landfill described
                        above could  not  be built on a flood plain.

 Key  among those ARARs,  shown in  more detail in Appendix A, are the chemical
 specific drinking water requirements or Maximum Contaminant Levels (MCLs)
 established  under the  Safe  Drinking Water Act, and the requirements under
 the  Resource Conservation and Recovery Act (RCRA) which relate to the
 construction of hazardous waste facilities and their closure.  Table 4-2
 gives the chemical specific MCLs  that would apply to those contaminants
 that have already migrated  into  the North Criner Creek alluvium.  None of
 the  alternatives  would  result in  rapid  restoration of the groundwater onsite
 to drinking water  standards.  However,  the two EPA remedies would accomplish
 this goal more  rapidly than the  HSC through the elimination of contaminant
 sources.  The HSC  remedy would  also fail to meet the RCRA requirements for
 its  cap.  The RCRA requirements  for the construction of caps are very specific
 and  the HSC cap does not meet them.  The cap proposed under the EPA remedies
would meet these  requirements.

7.3  Long-term Effectiveness and  Permenance

Both of the EPA remedies emphasize  recovery and destruction of the
contamination at  the source.  Through the removal of the liquids still
contained in the  drums, and of  contaminants in the contaminated soils and
sludges through soil vapor  extraction, direct elimination of contaminants

-------
                                    7-15
 at  their source  is  achieved.  These contaminants are then destroyed through
 treatment.   It is through  this early removal of the contaminants at their
 source  that  the  EPA alternatives are superior to the HSC alternative.  Long-
 term effectiveness  is  dependent upon the performance of the alternative
 over time-.   This long-term effectiveness is best enhanced through the
 elimination  of uncertainties associated with an alternative.  The greatest
 uncertainty  with these alternatives is the potential for long-term
 migration of contaminants  out of the source areas.  The uncertainty of the
 capture of migrating contaminants by the groundwater trenches will always
 remain  and will  grow as the time of operation needed for those trenches
 increases.   The  EPA remedies effectively address these uncertainties through
 the  elimination  of  contaminants at the source.  Once the contaminants are
 removed and  destroyed  the  uncertainty is eliminated.  Moreover, the
 uncertainty  as to long-term effectiveness of the groundwater capture and
 treatment systems is also  reduced by the elimination of contaminants at the
 source.  If  the  magnitude  of the sources of the migrating contaminants is
 reduced, then any future risk of their movement through or around the
 capture and  treatment  system is also reduced as is the time of operation of
 the  trenches.

 The  HSC remedy would do considerably less than the EPA remedy to remove
 contaminants at  the source and would allow their continued migration for an
 undetermined amount  of time.  By allowing contaminants to remain in place
 for  a longer period, the HSC remedy is less effective over the long-term
 than either  of the  EPA remedies.  This is shown through the compound
 uncertainties associated with the HSC alternative.  The first of these is
 uncertain length of operation of the HSC alternative due to remaining
 contaminant  sources.  Added to this uncertainty are those of the ability to
 maintain the system over this length of time and the increased opportunity
 for  contaminants to  escape over this period.

 7.4  Reduction of Volume,  Toxicity or Mobility

 CERCLA  states, in section  121(a)(l), a clear preference for remedies which
 reduce  the volume,  toxicity, and mobility of waste.  The EPA remedies
would both reduce the  mobility and volume of the contaminants through their
 removal and  destruction at the source.  The soil vapor extraction, more-
 over, would  remove  the most highly mobile volatile organic compounds from
 the  soils of the source areas.  The HSC remedy allows both greater mobility
and  volumes  of waste since the HSC alternative would only recover the
contaminants that enter the two HSC interceptor trenches.  Waiting for the
wastes  to migrate to the trenches allows for a greater volume of contaminated
material as  the contamination spreads to greater amounts of groundwater
and soils as it migrates.  The mobility of the wastes is also greater in
the HSC remedy than  in  the EPA remedies as it allows the wastes to migrate
and become more dilute  rather than taking the more efficient approach of
capturing them and  destroying them in concentrated form in the source
areas.

-------
                                    7-16
 The  treatment of source areas with soil vapor extraction would remove a
 portion of the carcinogenic compounds in those areas and destroy them
 reducing the toxicity of the contaminants rapidly.  Again, the HSC relies on
 all  contaminants to enter their collection systems.  As for volume of contami
 nants, the EPA remedies, by eliminating contamination at the source, would
 directly reduce contamination through the recovery and destruction of
 contaminants and would reduce the future volume of contaminated material by
 eliminating the migration of these (contaminants and their subsequent
 contamination of soil and groundwater as they spread).  The HSC remedy would
 allow the migration of contaminants out of the source areas not only
 further contaminating the groundwater and soils between the source areas
 and  the collection trenches, but increasing the potential for the escape of
 contamination both vertically and horizontally either under or around the
 control systems.

 7.5  Short-term Effectiveness

 The  short-term effectiveness for the HSC remedy would be higher than that
 for  either EPA remedy as, since nothing would he done about the
 contamination at the source, there would be none of the attendant risks of
 taking action.  It should he noted, however, that the short-term risks of
 taking action can be addressed through use of appropriate safety and
 engineering methods.

 Both EPA remedies pose certain short-term risks.  If the drums in source
 areas are excavated, then the soils around the drums will he disturbed and
 exposed to air.  This creates an opportunity for volatilization of
 contaminants.  The risks associated with excavation and lancing of drums
 have been examined.  The risks to onsite workers are related to the
 excavation and handling of the waste drums and the surrounding materials.
 Drum excavation has been successfully implemented at a number of hazardous
waste sites (see Table 7-2) and the effects are known.  Exposure of site
workers to hazardous substances and situations during the implementation of
 either EPA remedy can be minimized or prevented with well-planned and
 implemented personnel training programs, the supply and utilization of the
 appropriate safety and personal protection equipment and the development
 and use of an effective site safety plan.

The risk to individuals offsite has also been examined.  The primary risk to
those offsite comes from release of volatile chemicals or contaminated dust
 from the site.  This contamination could reach individuals through two primary
pathways, inhalation of volatile chemicals or consumption of beef and milk
 from livestock maintained in the area.  The total extra lifetime human
 cancer risk from ingestion of beef and milk is estimated to be seven in  ten
million.  This also assumes, conservatively, that the ten million
 individuals exposed obtain 100% of their beef and milk from the effected area.
More realistic  stimates of exposure and ingestion would reduce the  seven
 extra cancer ri  ; in ten million exposures even further.

-------
                     M
IS
  (*

H
                    •r
23
  I
  ?
                   I
                   <°

                   I
                          -i
                           I:
                                               9


                                               IB'
                             O
                                                            z
                                        i
                                                               S3
                                                               r*
                                                               i
                                                               lo
  3
  •
  to
                          o
                          S
 a.
                          a.
                                     e
                                     r
                                                          o
                                                          o
                    •r »   f->

-------
Zi
M
M
« w


OF
            I
1

                                                       o
                                                       o
                                                       3
                                                       3



                                                       (0

                                                       Q.
                r
                Us

                fl?'
* 8 to
yaara
                2,-


          f

          r


          i
          B.
          f
          S
            I
            B

-------

-------
                                    7-20


The total extra lifetime human cancer risk from inhalation of chemicals
released during excavation of the Barrel Mound and part of the Main Pit  is
estimated to be one in ten million.  The estimated risk from operating of
the SVE system is six in ten billion.

The opportunity for volatilization can be reduced through using the smallest
possible working face and thereby limiting the contaminated materials exposed
to the air.  Common sense precautions such as excavating during cooler
weather will also reduce volatilization.  The use of volatilization control
techniques such as foam supressants can also be used.

Other short-term risks were also considered.  The intermingling of the
drummed liquids can he limited through the segregation of the drum contents
as they are removed.  The short-term risks associated with the drum lancing
proposal include those associated with the physical puncturing of the drums
and of the mixing of the liquids after they are released by the lancing.
The risks of lancing can be reduced through the use of controlled lancing.
The work would proceed gradually with the removal of liquids released as
rapidly as feasible during the lancing.  The lancing work could also be
done by remote control to protect site workers.  The risks of puncturing
the drums could be reduced through the use of non-sparking materials on  the
lance points and through the use of carbon dioxide to eliminate the oxygen
supply through the lance hole if needed.  It is important to note that there
is already extensive mixing of the source area liquids as evidenced by the
amount of pooled liquids in the Barrel Mound.  This would indicate that  the
risks from further mixing are less than might otherwise he anticipated.

Of these two alternatives, excavation poses less of a short-term risk.  It
allows greater control and observation of the hazardous materials that are
disturbed.

7.6  Implementahility

The majority of all three alternatives use established technologies and
could he implemented.  Only the lancing of drums has not been attempted  at
a hazardous waste site.  The lancing technique has been demonstrated for
the puncturing of buried drums and has been used for other industrial
purposes.  This one point leads to a slight preference for the EPA
excavation alternative and the HSC proposal over lancing for this criteria.

7.7  Cost

Because it is a less extensive remedy, the HSC remedy is cheaper than either
of the EPA remedies.  It is important to remember that the HSC proposal  is
not an equally protective remedy when compared to the two EPA proposals.
The relative estimated costs for the three alternatives are:  HSC $46 million,
EPA with excavation $63 million, and EPA with lancing $59 million.  An
additional consideration is costs associated with remedy failure.

-------
                                    7-21
With greater amounts of waste remaining in the source areas for a longer
period under the HSC remedy, the potential exists for greater costs should
additional- remedial work he required.

7.8  State and Community Acceptance

State comment on the proposed plan for remedial action can he found in the
transcript for the public meeting held on Octoher 26, 1989 and in their
letter of November 13, 1989.  Basically the Oklahoma State Department of
Health as representative of the State of Oklahoma supports elements of
EPA's selected remedy including soil vapor extraction, hut disagrees with
with the excavation or lancing of the drums in the source areas, and with
the use of catalytic oxidation as a thermal treatment.

Public comment expressed at the public meeting showed a preference for
quicker action and for more permanent remediation.  To quote one of the
local residents who spoke at the public meeting,

   "... Personally, I think that the way that some of the basic
    ideas that you have got about addressing the cleanup of this
    is good.  I particularly like the idea of removing the drums.
    When you start taking these materials out, when you remove
    them from the site completely, it's the only way that you are
    going to create any kind of confidence that you have really
    cleaned it up."

-------
                                    8-1


 SECTION  8:  THE SELECTED REMEDY

 Based  upon  consideration of the  requirements of CERCLA as specified in
 Section  7.0 of this document, the detailed analysis of the alternatives,
 and State and public comments, EPA has determined that the Partially Revised
 EPA Remedy  involving the excavation of drums for liquids removal, is the
 most appropriate remedy for the  Hardage/Criner site near Criner, Oklahoma.
 A schematic of the selected remedy is shown in Figure 8-1.

 The first element of the selected remedy is the removal and destruction
 of contaminants in the source areas.  Free liquids within the three major
 source areas, the Barrel Mound,  Sludge Mound and Main Pit, would be removed
 through  extraction wells.  Organic liquids would be transported offsite for
 destruction and aqueous liquids  treated onsite.  Drum concentrations in the
 Barrel Mound and Main Pit would  be excavated.  Liquids in the drums would be
 removed  and taken offsite for destruction.  Solids would be restored to the
 three main  source areas." Contamination from adjacent areas would be consoli-
 dated into  the three main source areas.  These source areas would be treated
 through  soil vapor extraction (SVE) to remove contaminants.  The resulting
 SVE effluent contaminants would  be destroyed onsite using thermal treatment.
 It is this  element of the recovery and destruction of the contamination at
 its source  that is missing from  the HSC remedy and which confers the greatest
 degree of superiority to the selected remedy over that recommended by the
 HSC.  The reduction in the long-term uncertainties associated with leaving
 large portions of the source areas of contamination unremediated, as in the
 HSC alternative, is another area in which the superiority of the selected
 remedy over the HSC alternative  is demonstrated.

The second  element of the selected remedy would be control of residual
 contamination.  The major source areas would be capped first temporarily
 during treatment and removal in  the source areas, and then permanently with
 a regulatorily compliant cap following completion of the main treatment and
 removal  phase.  Groundwater would be collected through interceptor trenches
 and treated onsite.  Surface water controls would be instituted to minimize
 contaminated runoff.

 Finally, institutional controls  would be implemented to prevent use of contam-
 inated groundwater downgradient  of the source areas.  Alternate water supplies
would be continued to replace supplies lost through contamination.  The site
boundaries would he expanded from the original site to the area indicated
 in Figure 4-6 to facilitate the  implementation of the institutional controls.

The estimated cost for the selected remedy is $63 million.  Table 8-1 gives
a breakdown of this estimate and a detailed cost estimate can be found in
Appendix G.

8.1  Remediation Goals

The purpose of this action is to protect human health and the environment
through  control of risks posed by the Hardage/Criner site and minimizing
 further migration of the site contaminants.  Estimates of the risk of cancer
 from lifetime use of residential water contaminated at the level of the Old
Corley well range as high as 0.0007 (seven per ten thousand) to  0.006  (six
per thousand) far above the one  per hundred thousand risk which  is the  upper

-------
                                                                    DRUM STAGING
                                                                    ic CONSC. DAT1CN
             NORTHWEST
             FARM
             POND
                                                      i   DRYING
                                                      \  SHED
                                                                        L'QUIDS STORAGE
                                                                        AND TRANSFER
                                             BARREL
                                             MOUND
                                 EXTENT OF
                                 PERMANENT
                                 CAP
                                                                       DECONTAMINATION
                            STORMWATER
                            DETENTION
                            BASIN
                                                                   LIQUIDS   /
                                                                   EXTRACTION
                                                                 /  CONTROL'/
                                                                 i  BUILDING/
V-SHAPED
TRENCH
                                                                   SOIL/
                                                                   VAPOR
                                                                   EXTRACTION
                                                                   CONTROL
                                                                   8UILDIN
                              WEST
                              FARM1
                              PONC
                                             SLUDGE!
                                             MOUND
                                                    /  TREATMENT
                       INTERCEPTOR \
                       TRENCH
                                                                                EAST FARM
                                                                                POND £2
                     GROUNDWATER
                     TREATMENT
                     PLANT
                                                        - ACCESS
                                                         ROAD
                                                                             EAST FARM
                                                                             POND #3
SOUTHWEST
INTERCEPTOR
TRENCH
                                                       SITE SUPPORT AREA
                HOMESTEAD
                                TREATED WATER
                                RETENTION POND
                                               OLD STATE HIGHWAY 122
                                               (COUNTY ROAD)
                                                    FIGURE 8-1
NORTH
CRINER
CREEK
                                      SCHEMATIC OF SELECTED  REMEDY
                                     w/ excavation in Barrel Mound
                                        and Main Pit)

                                 HARDAGE INDUSTRIAL WASTE SITE
                                   REMEDY COMPARISON REPORT

-------
                                 TABLE 8-1

                    COST SUMMARY FOR THE SELECTED REMEDY1
Liquids Removal anj. .CpntrgJ                           $ 6,449,745
Drummed Waste Staging/Consolidation Area
   and Storage                                       '   2,813,516
Soil Vapor Extraction and Treatment                     3,098,052
Removal of Adjacent Wastes                              2,168,834
Source Area Capping                                     3,722,605
Ground Water Extraction and Treatment                   5,971,286
Remedy Support Facilities-                               3,237,290
Surface Water Controls                                    196,000
Remedial Monitoring                                        41,250
Institutional controls                                    608,250
                                                      $28,306,837

Bid and Scope Contingency                               9,907,393
Implementation Costs                                   10,317,842

Conversion to September 1989 dollars

Operation and Maintenance for 30 Years                 14,309,500
                                            TOTAL     $62,904,655
1  Source:  Remedy Report for the Hardage Industrial Waste Site, Criner,
            Oklahoma, October 13, 1989.

-------
                                     8-4


 boundary of acceptable risk  set  in  the National Contingency Plan.

 To accomplish  this  goal,  the remedy would  permanently  and significantly
 reduce the volume,  toxicity, and  mobility  of  contaminants in the source
 areas.  This is  accomplished through removal  of liquid  contaminants quickly
 and directly through  liquid  extraction wells  and  excavation of drum liquids.
 By following these  steps  with soil  vapor extraction, removal and destruction
 of the most mobile  contaminants,  including most of  the  known and suspected
 human  carcinogens,  will be acheived. The  goal of soil  vapor extraction would
 be a. 99% reduction  of the volatile  organic concentrations found at the
 beginning of soil vapor extraction.

 Beyond reduction of the source,  the goal of this  action is to restore the
 groundwater to levels below  MCLs.   This action is particularly directed at
 the alluvial aquifer  assoicated with North Criner Creek.

 The superiority  of  the selected  remedy is  demonstrated  in the comparison of
 the alternatives through  the use  of the nine  criteria  given in Section 7 of
 this document.   The reduction in  the sources  of the contamination associated
 with the selected remedy  confers  advantage to the selected remedy over the
 remedy recommended  by the HSC.  By  eliminating the  contaminants at their
 source the selected remedy is more  protective of  human  health and the
 environment, has greater  long-term  effectiveness  and permanence and provides
 for greater reduction in  the volume, toxicity and mobility of contaminants
 than provided by the  HSC  remedy.  The selected remedy  can he implemented
 using  existing technologies  and methods.   Its cost  is  greater than that of
 the HSC  proposal, but the selected  remedy  through its  source control elements
 provides  greater and  more efficient levels of remediation.  In this regard,
 the additional costs  associated with the selected remedy are reasonable.
 The selected remedy would also comply with existing ARARs on cap construction,
 which  the  HSC alternative would not do, and would attain the standards for
 drinking water quality in the alluvial aquifer as expressed through the Safe
 Drinking Water Act  MCLs in a shorter period of time than the HSC proposal
 would.  The State of  Oklahoma through its  representatives has expressed
 concerns about the  short-term effectiveness of the  selected alternative,
 and  some short-term risks do exist.  However, these risks have been considered,
 and  they can be  controlled or eliminated through  the application of prudent
 engineering and  safety techniques.   Finally,  the  local  community, through
 the  public  comment  period on the  alternatives expressed a preference for
 removal and  destruction of as  great an amount of  the contamination as possible
 from the source  areas.  The  selected remedy provides for far greater direct
 removal of  the source  area contaminants than  does the HSC proposal.

The selected remedy also  holds advantage over the other EPA alternative
which  included lancing.   The lancing techniques have not been used at a
hazardous waste  site  before  and therefore  their implementability is not as
well known  as the excavation of drums in the  selected  remedy.  There are
also greater uncertainies associated with in-place release of the drummed
liquids through  lancinc that will not exist with  the selected excavation
program with actual  ph; ncal  removal  of the drummed liquids.

-------
                                    9-1


9.0 STATUTORY DETERMINATIONS

Under  its  legal authorities, EPA's primary responsibility at Superfund
sites  is to undertake remedial actions that achieve adequate protection of
human  health and the environment.  In addition, Section 121 of CERCLA
establishes several other statutory requirements and preferences.  These
specify that when complete, the selected remedial action for this site must
comply with applicable or relevant and appropriate environmental laws
unless a statutory waiver is justified.  The selected remedy also must he cost-
eff^tive  and utilize permanent solutions and alternative treatment
technologies or resource recovery technologies to the maximum extent
practicable.  Finally, the statute expresses a preference for remedies which
significantly reduce the volume, toxicity, or mobility of hazardous wastes
as their principal element.  The following sections discuss how the selected
remedy meets these statutory requirements.

9.1  Protection of Human Health and the Environment

The remedy seeks remove liquid contaminants quickly and directly through
liquid extraction wells and excavation of drum concentrations.  By
following  this removal with soil vapor extraction, removal and destruction
of the most mobile contaminants including most of the known and suspected
human carcinogens will be acheived.

Along with effective reduction of contaminant sources, the selected remedy
protects human health and the environment through intercepting and treating
contaminated groundwater with interceptor trenches.  The North Criner
Creek alluvial aquifer is the nearest groundwater used as a residential water
source.  The selected remedy provides better protection of human health and
the environment as it will achieve the goals for groundwater cleanup more
quickly than the HSC proposal.  The selected remedy will eliminate uncer-
tainties associated with the continued presence of toxic and mobile volatile
contaminants in the source areas by recovering and eliminating contaminants,
unlike the HSC alternative which would allow these contaminants to migrate.

-------
                                     9-2


 9.2  Compliance with  Applicable  or Relevant and Appropriate Requirements

 The elements  of the selected  remedy  would all comply with applicable or
 relevant  and  appropriate  requirements  (ARARs) established for this site.  A
 more complete examination of  ARARs can be found in Appendix A.  Key among
 these ARARs are the Safe  Drinking Water Act chemical specific requirements
 known as  MCLs (maximum contaminant limits), and the requirements under the
 Resource  Conservation  and Recovery Act (RCRA) which relate to the
 construction  of hazardous waste  facilities and their closure.

 ARARs include:

 1)   RCRA  requirements  for landfill closure in 40 CFR 264.111 Subpart G
     and 264.310 Subpart N which  specify cap requirements for landfills;

 2)   RCRA  requirements  in  40 CFR  264.117 Subpart G dealing with Post-
     closure;

 3)   Requirements under State  of  Oklahoma Air Regulations requiring use of
     Best  Developed Available  Control Technology for treatment of the air
     from  the  SVE system.

 4)   Maximum Contaminant Levels (MCLs) established under the Safe Drinking
     Water Act;

 5)   State of  Oklahoma  maximum acceptable ambient concentrations (MAACs) for
     air contaminants;

 6)   Oklahoma  Water Quality Standards for discharge to a surface stream.

 None  of the alternatives  would result in rapid restoration of the ground-
 water within  the site  to  MCLs.   However, the selected remedy would
 accomplish this goal more rapidly than the HSC remedy through the
 elimination of  contaminant sources.  The selected remedy would also meet
 RCRA  requirements for  the construction of the cap over the source areas;
 the  proposed  HSC alternative  does not meet these requirements.

 9.3  Cost Effectiveness

The  selected  remedy is cost effective and would cost an estimated 63 million
dollars.  It  includes  some 20 million dollars of cost directly related to
contaminant source area reductions, through excavation, soil vapor extraction,
and  liquids extraction.   The  HSC remedy does not include these costs.  This
additonal  cost  is reasonable  considering the added long-term protection of
human health  the environment  provided by direct and permanent reductions to
the  source areas.

-------
                                    9-3


 9.4  Utilization of  Permanent  Solutions and Alternative Treatment
     Technologies.

 The  selected  remedy represents the maximum extent to which permanent solutions
 and  treatment technologies can be utilized in a cost effective manner.  The
 amendment of  the  1986 ROD, which called for land filling and stabilizing the
 source soils  and  sludges, to  the new selected remedy of excavation, liquid
 extraction, soil  vapor extraction and capping provides for a permanent
 solution through  additional recovery and treatment of contaminants.

 The  emphasis  in the  selected  remedy is on the recovery and permanent destruc-
 tion of the contaminants at the source.  This begins with the recovery of
 the  free liquids  and the liquids in the buried drums through excavation and
 liquid extraction,  and the subsequent destruction and treatment of these
 liquids offsite in  a permitted Treatment, Storage, and Disposal facility
 and  in the onsite water treatment system.  It also includes soil vapor
 extraction of the Main Pit, Barrel Mound and Sludge Mound to remove volatile
 organic compounds.

Another aspect of permanence  is the reduction of the mobility, toxicity or
 volume of the wastes.  The selected remedy accomplishes all of these goals
through removal of  contaminants at the source, unlike the HSC alternative
which would allow contaminants to migrate out of the source areas.

Through removal and destruction of contaminants by SVE the amended selected
 remedy provides permanence, particularly when combined with the groundwater
collection and treatment elements of the selected remedy.  The groundwater
portions of the selected remedy utilize permanent solutions through removal
and treatment of contaminated groundwater and the destruction of the organic
contaminants  removed during treatment.

9.5  Preference for Treatment as a Principal Element

Treatment is central to the selected remedy.  Treatment is used extensively
to address each of  the three  primary contaminated media.  Free organic
liquids from the source areas and organic liquids from the excavated drums
will  be taken offsite for destruction or treatment at an appropriate,
permitted Treatment, Storage  and Disposal facility.  Contaminated soils and
sludges that remain  following liquids removal and treatment will be consoli-
dated into the three main source areas for treatment with a soil vapor extrac-
tion (SVE) system.  The goal  of the SVE system will be removal of 99% of
the  volatile organic contaminants from the contaminated soils and sludges.
The  air from the  soil vapor extraction system, and air effluent streams
from other remedy components, will be treated onsite with .\ thermal treatment
system, to treat and destroy  the contaminants within the a^f streams.  The
third major contaminated media is the aqueous liquids including groundwater,

-------
                                    9-4


aqueous liquids from the buried drums, and surface run-off.  All of these
liquids will be treated in an an onsite water treatment plant.  The water
treatment_plant will be designed to treat the influent liquids to standards
for discharge  in accordance with Oklahoma Water Quality Standards.

Additional advantages in the treatment in the selected remedy are gained by
treatment of the contaminants in a more concentrated form.  This is true of
the free and contained liquids in the source areas due to the liquid
extraction wells and collection of the free liquids and the excavation of
the buried drums.  The SVE system will also recover the volatile contaminants
from the soils and sludges in the three source areas allowing them to be
treated in a concentrated air stream rather than diffused through the soils
and sludges.  Treatment of the contaminants at their source will also
improve the effectiveness of the water treatment system through reduction
of contaminant migration to groundwater.  The contaminants will be treated
before they migrate into the groundwater where they would spread and be dilutedc

9.6  Documentation of Significant Changes

The Proposed Plan for the Hardage/Criner site was released for public
comment on October 13, 1989.  The Proposed Plan identified the use of drum
lancing as an option for addressing the buried drums.  Comments received
during the public comment period indicated particularly strong opposition
from the State of Oklahoma to retention of this option.  While EPA feels
that drum lancing could be implemented, the option of drum lancing and
associated U-shaped trench has been deleted from the selected remedy and
only excavation is part of the selected remedy.

-------
                                 REFERENCES
Hardage, Royal N., 1987.  Deposition.
EPA, 1985.  Field Investigation and Data Summary Report, Royal  Hardage
Industrial Hazardous Waste Site, CH2M Hill, May 22, 1985.
EPA, 1985a.  Public Health Assessment Manual, EPA, Office of Solid Waste
and Emergency Response, November 1985.
EPA, 1986a.  Source Control Feasibility Study, Royal N. Hardage Industrial
Waste Site, CH2M Hill, February 20, 1986.
EPA, 1989.  Remedy Report, CH2M Hill, October 12, 1989.
HSC, 1986.  Final Conformatory Bedrock Study, ERM-Southwest, December 31,
1986.
EPA, 1988.  Design Report - Source Control Remedial Design - Hardage
Industrial Waste Site - Criner Oklahoma, November, 1988.
HSC, 1988.  Mound Characterization Field Study, ERM-Southwest, November 7,
1988.
HSC, 1988.  The Hardage Steering Committee's Recommended Source Control
Remedy.
HSC, 1989.  Second Operable Unit Management of Migration Remedial
Investigation Report, ERM-Southwest, May 10, 1989, as amended by EPA
Comments.
HSC, 1989.  Second Operable Unit Management of Migration Feasibility
Report, ERM-Southwest, May 10, 1989, as amended by EPA Comments.

-------
               APPENDIX A

EVALUATION OF APPLICABLE OR RELEVANT AND
        APPROPRIATE REQUIREMENTS

-------
I  ;
 !  in •
 3  511 s  ;
"  -.; $  ?

n
}5
           1!!
             fl
(CM
M
>l
^


II
-I

¥-
ss


}•


'"I
  1
i




ff
•
•*
•

i


f
                        &
                        M
          ?? *!*  5H i:

          -i Hi  Hf -! ?
          i 1 5 a »  •* 3 •  i. lS
          ?• 11 *  ft--  ; [i

          s? "If   «  a i
           i  *l   '-!  Si
                n


                ff

                *
                •^


                5

                *w
                                s
                                s
r

5

f

i

              =5*1
              *«• z
                                8

                                3
                                     2  8
           ;?9

           i!

           ill

           hi
           lit
                        ii
                        ';
                           {lip!  HI
                           if*  "
                                         I
                                          II

                                          §?

                                          5?
lil?
5TJJ5
1 3 » 5
si|5
Z. wT — JT
s^?^
? ° « 3
JgS
H!
!is
« M
< —
3 »

!S5
'I?
!l
^ »»
i ?
:i
!?
(• r*
s:
ii
*» 3
i"
J*


O. ts»
ss
y -»
•• •*
-1 -•
«n
T
1 *
2 c
u
II
w«
»
1*
Hi
1*
&
C
1

1 • • •
|K!

i
s
?
1
•
^
«
2
e
!
I
1*
i
*ft
n
!=
u
u
- 3
9 ?
' )
;*
* T
I
p
J"
ii
I-
-,
HI
ii
It
* ^
•i
f

-------
*
|

1

i
>

I
i
«
i
f
3
J
*
i
I
£
a
















I
n
•j
«9
5





Ivltlaa that affect or •
let enr of the rivera
rifled In Section UTtla

?"?!

li 2
5""™*

Wiat avoid taking or aaslatinf
In action thai vlll have direct
advaraa affert on acenir river.


I
f


iff
rTo.£
i T a"
* «*T>
T —
s> •»
f|
sT
r*
S.
3 <«
^

H ••?
•s> •
li
*


a a • o

*i?l
fi!
= Jo
'iy
SI
* — e.
2 -


Nuat take action to protect flah
or olldllfe


3
!


•o. o
1?
a. -i
wi
X3 O
oE
-* 3"
i-» O
1 f»
i;
a?
O> I1J
^* W
o —
3 M
fit
&
lu
- i

n
-
m'n 52

rratlan of terrain that
patens significant
mtlflc, prehlatorlcal,
torlcal, or archaaoloqlc
i
•
III
sl
s


Must lake action to recover and
preaarve artifacts.


J
1


= 2?
= 73
X* a
• 23
??|
o 3
•«
• rt
at aa»
^ 1
fl
0 ^
|5
\
i







|f
C 1
;
•;
s
i
i
i
!
i
f
*
a
4
a
(
;

lied or bulk liquid hsiarrtous
vaate In a ault dosie formation.
aall bed forvatlon, undernround
•Ine, or cave Is prohibited.


?
S


;:-:|
J ^2 "3
?• jT_
a.:?;
lllll
in if
rj-t
- JH; ?
•• * ^* *3 •
5 * ~ *
jj *
2T
3 0
w *
i


F a?;:?
V--9 *
Z A » A ^
Ion that vlll occur In •
id plain II. a., lovlanda
itlvelf flat areaa ad)ol
ind and coastal vaters,
ft flood-prone areaal
: Hi
' s>!
i *JL
( 3?
> i
a>
i

•hist take action to avoid or
alnlnlie potential hara) tn flood
plalna, and reatora and preaerve
natural and beneflrlal values.


u*
'•


4 s>
tt n
-•» o
o
O r*
O. 3>
— v»
3 19
J
5
3
3"
i
3





1*
is
1 haiardou* Mete, treat
, atoraoe, or disposal
i
S
i
X
«
•
5

Treat ornt, storage, or disposal
facilities vlthln the ITO-vear
flood plain aust be designed,
constructed, operated, and
•alntalned to prevent vashout.


•5
V
;


H
? i
-* o
si
"
-— v*
3 li-
lt



§
If
23
^ o
<« a
a3
•
5
—
| 1
J 5
•» •
e •
^ «*.
s:
:•
i
*
O
0
JJ
c
Cl
•T

— ^« a B
*nf!
!ui
lit*
— a •
— a i i*
a


.
f


2?
n
i •
• *
w
1
F
w
a]
T
3

•V
f





[

n
£
oui. tnrATioH-snrii
^
O
»
w















-------
3 — 99
5 * f 2
S ! -7
^ ' !«
a* 0 ^
:' i!
i i'
H i

o •
• •» 1°
1 |J
5 ' t
Z 92
- I1
I;
Q <*
i f
a ••>
8 1
y fs?f
1 2-1:
i : 1s
i
«
Mist take action t
destruction, loss,
dear adat Ion of vet
proprlate.
i'i
a
m
a
**
9
a

f
?

"?
17.
i-

S"

*•
-1
Yl
A •
i r
„ |
i?
- 1
- •
i
j
•
j

2f5
rti
abltat upon
species or
species de
1 *

SJ2S5
3 3 "l» 1
§1 '


Nust take action t
endangered species
species.
o conserve
or threatened

f


?i?
a w

s,-
u t
If!
lr^ *
^ 1
Iff
^
3 —
a

?? *
* 5 a"
i:|
872
9 W
51
• o



III

jii
r

*ss
31* ^
^
^B»

Must taka act Inn t
historic proprrtle
ront rolled by fedr
Misl plan action 1
hara to National H
landMrks.
o preserve
s ovnrd or
ral earner.
o ejnlalte
Istoric

f
f

5S?
If?

51
.-!
' *-
— s
li
if
~
3
•
*
*
i
f
"
j

s j
a —
• s
1
affectlne,
i
f
i
WM <•»
83
§g
"?
o

a — • <» BI
?!?$!
rt —•.—•»
"S.lft
:S7S!
fU!3
*fi*l
• Sin
a 9 I
5**H
?!K
?a»
9

z
o
W»

1 £ ^
3 1
— . ro 1/1
r» a* r*
03-1
T C
— . — . fl
3 t/t ft
* -0 T
a>
3 O
3 1
(D
0 -1
T 3
3* e
at i
3 -•*
Qi
rD

i*?2
4 So
J"*
«• V
* » w»
5*1



5
!
s,
i
5
f
w
w
;
I
§
5

Must avoM undesir
upon landaarks.
able Impacts

f
f

fW
n
• a
ill

f * t
j ~ »
'«s«
» —


F-f
. | _
?2
n » "^
— i
-'•i
'
§
q

• w
i
I
*
o
f
f
£
* *
0 w
n "

la
*d 1
9t
Art Inn to dispose
•aterlal Into nrea
prohibited vlthout
;I
=!?
•

f
?

•a z
1 O
o
-o a»
o n
Wl f^
n -•
a o
3
CM
r*
m
vt a
n
• I
m
aw
V*

? 2
= 5

S T
rt
I
>

2?
5> 2
M N
1
|
e
f
£
s
o
*
I
1
•
Art Ion to dispose
•aterlal Intn ore*
prohibited vlthout
;iJ
3:1
rl*
«

f


3C
• o
a>
n
,-»•
a
3
o
' Q.
. ta
. 3
at
«-••
O
i
a*
VI

??
I i
1 *
iS1
-



Hi!
•< •» w •»
llsf
Ii]
!r

'rfs
11 i^



nXist conduct actlv
•anner consistent
slate .anaaeavnt f
II;
>t;
0 «
3
a

f
f

*?
•• VI
ii&
»»•<
• •
jj
VI <••
'*
3 -*
* 9
M —
l5
|'
Z


*
i
I





•i
«
i
w
*
H


n
a
7
3


?
Lt
rrlptlon
.1
^ t
O
» •





1*
1
vl




-------
a
I
H
                                                       *  7
                                                       t  f8
                                      S
                                      €
                                             ??
                                      &


                                             I5
                                                      l~ o
                                                       n
                                                      155
                                          m

wtal
(ha
                                                     I < a

                                                     < » f
                                                     i •• ^

                                                      -1
                                                             i
                                         If.''
                                                         LI
                                                         ii
                                                         It •
                                             ?i
                                             f:
                                             • «
                                             ci
                                                     •   >~i
                                                     •"  i
                                                     •?  II
                                                     Ti
                                                     3 •<
                                                     il

-------
I f
8 !
v* «
i
i
tt
1
I
8
7
*
4
ft
3
|
i
i

22 ??T
11
? 'I
S
ru ft?
i ? £ ?? —
* *
3 *


f !
e> •»



II!
m
™**
3 *
I1

ill
*
1


*«>




t Contlnftncf 1
teriqvncr ft<
II

HI
!!l
rtf
** 3
j"


f
a



f!
i

•*!
!i
Is
" 4
*
|
o



o
M Cl
1!
*|
*
<•

il
t{
it
If
y i

1
f&




Esffi
i* il
1 «,'
f
i
i
1
*



s
o
a
1



ill
-i

is
il
II
£*


s
S
x



:f|
Hi
flf
\s

H
I
A
5,
f
•I


S
n
S



W M T
""Is
-I
:s
|i

if
•0
S
I




o
n
I



\ll
M *•
f"

1
f
ft
i



s
ri
I


?y :
?-In '«
«» *• • •*
* — S 2
5~ J

o
f
k
w
*



S :
n "
3 ^
S *
!
1
         3
             :   ?  ?
Ho/Tra


1


f


I!
ss
*»
ft!  5I!"  *!!!? i'
2?i  il :=«  |I ?|f -i
»« I  *• 5e»  t> •> J s -»

?Ii  i: :5i  }l ii: :i
atn   | 5»i  «a »1^ f.
j> e  • 5  yi •  « 9 * a *• < •


;!  l| J|S  -IJll't

» -  s - * » »   . r
    :? 3-!
                   =
f 7«2,<
tS fQ   T
                                                       fir
1
y
?
i
im
!
^
t*
a> sr T — .
r» a* n —
3 is. n n
3 T < V
o -i m
»/i C fD
ft rt) ^. O
3 k/* ^ -«»
c a.' wi

-------
j J
i
^ •
§ '.
I
\
3
-
!
s
2
f
S
r
7
4
i

i
i
i

II
* *
• r
f

M
.5
if
H

if
'•

O
3

5
0


li

ii


H
!|
• J
Hi
•r
•


*
o
3

*



|I}[f

"fffis
"!l*
w ^ ^
}•'

!1
13
11
^r
i
i
*

s
i

x


-
f-f • f I
J * — « 4 ft
i^U;
£ i\H*
5 -*5

'*J
~ • n
* ••
*;
<* •
i*
a «

§
i

X
»


1* j ~f ;
•• O — • ^ ^
fHl;
•?;i|
|sil
• :?
•i








s
3

X
Wi

Q
a
5"

_
i"
f
•

i?
••
li
i)
— .
ft
f
i

|

gg



-
*

[
|

SIT
li
??
*
i
r
•
•«
I

!


9


f




11
3 =
n
i

m
•
^
•

"9 Ul
a, c
i o-
u
ISJ 1

L *
o

J
a
2
I

a
n
n
9
•«
•
n
t
r
•
r
•
!





f

*
4

:f
? I
n
is
2r
H


1





if i
' i
I "
1

pr si
|»J ;}
•:h!
!. 1.
?* r~
:;;;
ir ;r
li i
4

! !





-i
5
[i
1

If
^1
it
•
i;
"r
•
f


M
f





1 •
4 I
;i k
V

*•!
!J!
i S^
* • *•
iii
=ai
•»aj
3"


1




(  13
:->
25
-;*
u
i!
12
;s
»
a








r
f



ii?
I;i
8 —
• •
r j
* •
' »
:'-
u
3 ?
a •
§


mi
ill;
H
'-f!
{!H
hn
J£»s
J •








^
1



If
•• ?
i!
? 1
i
*
•
j



f!ri} !
ISS-i frj
Jl!l*iJ
ih^;1!
SJHfH
•II&MI
?•*•!!-
TiiUf
a:=iii
f 'S
•







I
1



Mill
• a * *
* f IS
:;|l
' 5 —
r 1, 2
? ?
[?}{
i ? *


5 M!
;2 * • }
«=H*
1 » 5"* 3
Hill
1:5!
^ 5 •
IHr
i""
m







I
1



2 •
a ?
i i
?r
i;
i^
^ ~
'"!
;
» ^

r-5i=i|iii
M-^ahn
;i«r=::-:j
=ri.:.iir.
:• 1 ;- ii tl
ISfftilll
?i»*-':!i
Sf 5ilf i
is ;








f
^



i'
~ y
rg
«•
s

T
j
•
c



« a 01 •
5 i.£ »
—i 3-
— 'Ji
V Z"
-^ /.
3 J)
— 1J
3 1
30 O,
yi
n
li -n
•a o
i
i
J3 a
C N
-* to
t 0,
3 O

3 on
'— C
a>
(fl
F : J J
? "i" »_ f
I
I

f M^ ? If
. Is^S 1 *l
* i a M n i _ ^
* 0 ^ — — ^ J2
1 15=5 o J
» sZsC - I
1 "°.3 ;• i
Z J|^ | _
* •* •» !L a
S 5»o ~ -
- Is! -;i
~ 3 ^ 3
*

s
^
9












f
|



-f
V
^»
•
*
£
.
I
C
I
m

; 5 ; ;
» > » »












S ? ? 5
ii t '
iii



S£ jf ;jj
3 — I ' ii
r* -*. ^. < •
T n • - t
El I -1}
:? ! ;:«
°» li
|| .- !$
Q. Q* » 0
n J
a, ^ •
ai 3' e —
Q. O * 5
0 C .1
C 3 * M
i/i Q. ^
3 v
< S
Oi 3


;
o
9
a








1C
fl
- f
J*
• 9
'i




A
1
1





-------
i S
— 1
-•
J
i :
JB a
»
t
I
1 Is ajBl Irani*. It
n
a
S
7
*
7
1
i
1
|
•
i














55! f 1-f
Zll 5 5*!
s-i ^ IE
521 : **
* z S O * r»
•i § 51
f 1
r 2
i i
• •»
*\ «»
i i
r

1
•

s s - =
i« M
" 1 i
i

pi! illl
!*iri l&a?«
»n« • — •» *
Hi} lllii
f bm
l! Kill
1 * n
r ll


» f
1 r

n -i cyi • 2
3 fw o *r
— — 3 r i
i^ r» fO * i
1^ <
— . oi -o •
O 3 O •»
3 r* 1 «
trt r* •
-^ 3 O' ••
-I 0. 3 •
la"1 j
•a o J
™ 3 I »
•a o a
<5 ~* ^^ '
51 "*50 1
3 O ^
*"" 0 0 »

?o«lc Subalancrs Control
(U-t IT5l»(
?



Ss5
iijj
2 1
i

ii
If
ss
|


•*



•» — n
a. f»
f-o OB
•> 1 W>
-» 3 a.
i a.
19 1* r*
< a. i*
— « O r»
•*i a.
- 3
7

H*rlf-« l^rotvrtlofi
•tetearrti •**4 Sanctvarlv*
Art
i

-

z
jj
i
*

i
i
1


|



ll
ll
3

^


Tot l*r PoHutanl
tf fluent Standard
Ii
* •
if

<8 O
a"

s
n
•»

talab(l«n*«
or prnhlbttl
toilc noilul
rfflvrnt atandarda
Ions for c*rtaln
> lit S .


i
i



i!
S|
|


I
•
•*
W •
a ••
• 1
& —
«
v
*
«
1
Pollutants that pai
•r lnt*rf*r* »lth I
prorrasaa In POTIrs

~ a
9i
:•
If
o

S 2
3 %
•a* M

"• » ^
^ *> — •
«' iSS
I?0!?


1


i i 3*' i
rllffM
•« 5 ** * ~ • j
^'•I'i
=iH-
3T7;v}
!!»!--

1 " J** 2 •
_ j - -
UMlr><|rnund Infer (Ion
-«ulj<( <•«•• bu| |» MK>I*
.(|»l |U (01(00, 10)
uu||a|iuWg iiMixtui^




— £
i »


JTSJ7
I'll
2 " at It
mAcr* «ou!4 require
HI ot vol«t 1 le
»slong fro* Prorturt
Vessel.


M



C •
~ •»
^ 9
;j
* «
?i
i
•
1

—
Drwlrrqioontf 5lor4)*ye
i*m** nrrri
f
1
i

i

*
a
n
S

a ?
•i
0 mt
H
ii
w •
£


**.

„

tt
if;
|f
• 1
i -
^ ••
-1
3
B
I

7


n
I
I*

m
5
f
if
a —
If
If



j
•





-------
8

7
1
•
«
4




!




j
i

I
w












HZ » «
- • 5 •
5:3;
<* ** 00

f?!=

ft u
!:
^ S
j* e
"£
3
0
M
|

6
Is

?2
*
If

«*
1
f
IT

?
S
2
I
•
i
W

H

5§
st

*«
a,
i
a
£
n
i
8
"
UB


is

11
5
a
3
f
w
ft
1
3
I
S



||


2f

*
j
0
S
£
i
^
1
~


-3  8
       S  C
    Si


    f!

    8?
    75
    ^ (•

    n
    W *"
    • ft

     3
     O
     M e * u v i* -• w
     l!f H |«
     if? r« "Si
     2*3   "7  "

     &?§   ? !•}
      8» a   *• — — a
      w —   7 o » H
     t 5 J   5  a" a
     3"S   a  !S
     '  -     ^?
            f  !
                          l!
   i ^ ^


   • * 3
   • w a


    • t


    «l
                 • |3   i(
             "    s • •  -
             i"   ?;ii«

-------
    if r°  n
    H 1  =:
    ~°   i   "
    =        o
    t|   =    S
    »*•   "    ?
-i
*«*
a. »
                    - O 3 JO
                    £ J ?• •»
                                            2
                                            i
                                            £
                                            T
                                            I
                          I
a
3 -y
                                      I    I
                                        S?S
                                        3 Ml *
                                                         I!
                                                         ? if
                                                         — «
                                                         s-
                                                         aa
                                                                           •
                                                                                 o
                                                                                 s
                                                                                         0 S

» 1 — a o
« 3 t f*
— »» M e B
Hrll
S5ls*
f 5*??
S-* — -i •
« * **
-»<••*
n° '^3
^^5»«
-2-JS
C » 0. r*
-» **^ *•
MiL'

1 ??§
y * c *
i n-*
J . 0.
0 »e •»
-» y wt t
t-n
?*ss
• j?-
s-s-*^
:==s
^E2
-» 0 3
?;is
? I" 2
•» «• * 3
15J
a 3
f .!
» w» —
— w* rt
« -I »

                                                                                              II
                                                                                              • *
                                 -i t   S
                                                            517
                                                                                        as

-------
             APPENDIX B

AGENCY FOR TOXIC SUBSTANCES DISEASE
        REGRISTRY EVALUATION

-------
                                   Health
                                   Assessment
                                   for
              ROYAL HARDAGE INDUSTRIAL HAZARDOUS WASTE LAND DISPOSAL FACILITY

                            CRINER, OKLAHOMA

                             DECEMBER 1988
I

-------
                                  SUMMARY

The Royal Hardage Industrial Hazardous Waste Land Disposal Facility
(Hardage/Criner) National Priorities List  (NPL) Site is located in Criner,
McClain County, Oklahoma.  The site is located in an agricultural area.
There are volatile organic compounds (VOC's) and several heavy metals
present in the groundwater and soil, and VOC's in surface water and
sediment.  The Record of Decision (ROD) for the first operable unit
(source control) signed November 1986, selected several remedial actions
which included excavation of the primary source material and separation of
the wastes for treatment:  solids to be disposed of in an on-site landfill
which meets Resource Conservation and Recovery Act  (RCRA) requirements,
organic liquids to be incinerated, and inorganic liquids to be treated by
other means as necessary.  This site is currently in the remedial design
phase.

-------
                                 BACKGROUND

A.  SITE DESCRIPTION

The Hardage/Criner NPL Site is located in McClain County,  Oklahoma,  on
60 acres.  Operations began at the facility in 1972.   Several pits were
excavated in the early years to receive wastes from barrels and tank
trucks.  The pits filled rapidly.  The wastes were then transferred to
temporary ponds.  In the west pond, the wastes were slurried with soil and
transferred to the south pond.  The south pond was eventually filled and
the wastes were then stacked to a height of 10 feet above grade.  This
became known as the sludge mound  (see Appendix).

During the mid-1970's, drums were no longer emptied into the pits, instead
they were piled at the north end of the main pit.  This became known as
the drum mound  (see Appendix).  During the late 1970's monitoring wells
were constructed in the southwest corner of the site.  These wells
indicated the presence of contamination.

The wastes received by the facility included:  oil recycling wastes,
chlorinated solvents, styrene tar, acids, caustics, paint sludges, lead,
chromium, cyanide, arsenic, pesticides, inks, polychlorinated biphenyl's
(PCB's) and large quantities of waste from injection wells and other
nearby facilities including two NPL sites, Brio and Bio Ecology.

Operations ceased in November 1980.  Closure activities continued into
1982.  There was an effort made during the closure activities to
consolidate the wastes into major source areas.  These source areas are
identified in the Appendix.

The ROD for the first operable unit signed November 1986, selected several
remedial actions which included excavation of the primary source material
and separation of the wastes for treatment:  solids to be disposed of in
an on-site landfill which meets RCRA requirements, organic liquids to be
incinerated, and inorganic liquids to be treated by other means as
necessary.  This is presently in the design phase.  A second Remedial
Investigation  (RI) was begun in February 1988 to determine what type of
migration control should be implemented at this site.

B.  SITE VISIT

ATSDR has not conducted a site visit at this time.

              ENVIRONMENTAL CONTAMINATION AND PHYSICAL HAZARDS

A.  ON-SITE CONTAMINATION AND OFF-SITE CONTAMINATION

The project site boundary depicted in the Appendix was the basis  for
aefining on-site and off-site in this Health Assessment.  The  values
recorded in the tables below reflect the data presented in the Field
Investigation and Data Summary Report, Volume 1.  Although there  were
other data received by ATSDR, sampling points were not adequately
ident-fied, and therefore, were not utilized in the tables.
                                   Page 1

-------
 The results for the surface water and sediment  sampling  recorded  in
 Appendix H of the Field Investigation and Data  Summary Report were not
 provided to ATSDR for review.   However,  the  discussion provided in the
 text indicated that methylene  chloride and bis  (2-ethylhexyl) phthalate
 (DEHP)  were detected in the surface  water samples  and methylene chloride,
 fluorotrichloromethane,  DEHP,  and chloroform were  detected  in the
 sediment.   (These contaminants may be laboratory artifacts  and not
 site-related.)

                                   Table  1
                            ON-SITE CONTAMINATION
Contaminants
Chloroform
1, 2-Dichloroethane
1, 1-Dichloroethene
Tetrachloroethene
1,1,1-TCA
1,1,2-TCA
Trichloroethene "
trans-l,2-DCE
1,2-DCB
DDT
Chromium
Lead
Methylene Chloride
Xylene (total)
Toxaphene
Aroclor 1260
Soil (mo/Ka)
ND--.0006
ND— .180
ND— 6.2
ND~16,000
ND— 6,000
ND--1,100
ND— 1,500
ND— .009
ND— 150

ND— 937
ND— 5,470
ND— 1,300
ND— 1,500
ND— 160
ND— 19
Groundwater iua/L)
3—40
ND— 1,500
10—5,300
ND— 1,800
33—32,000
ND— 1,200
29—36,000
10—46,000
ND— 4,300
ND— 57
ND— 28
—
24—49,000
—
—
—
                                   Table  2
                           OFF-SITE CONTAMINATION
Contaminants
Chloroform
1, 2-Dichloroethane
1, 1-Dichloroethene
Tetrachloroethene
1,1,1-TCA
1,1,2-TCA
Trichloroethene
trans-l,2-DCE
1,2-DCB
Chromium
Lead
Monitorina (ua/L)
ND— 1,300
ND— 140,000
ND— 4,900
ND— 24,000
ND— 31,000
ND— 50,000
ND— 8,000
ND— 3,600
ND— 40
ND— 223
ND— 23
Residential (ua/L)
—
—
ND— 6.6
ND— 9.2
ND— 29
ND— 120
ND— 63
ND— 79
—
—
ND— 23
Legend

TCA trichloroethane
DCE dichloroethene
DCB dichlorobenzene
DDT dichlorodiphenyltric'- loroethane
    no concentration reported
                                   Page 2

-------
 B.   PHYSICAL  HAZARDS

 There  are  no  reported physical hazards present at this site.

                    DEMOGRAPHICS  OF POPULATION NEAR SITE

 The  area surrounding the site is used to graze cattle.  A chain-link fence
 was  installed in  1987 which eliminated the past problem with cattle
 grazing 6n-site.  There are two buildings located on-site.  One was the
 former sludge drying building located northeast of the drum mound.  The
 other  was  a barn  located between the sludge mound and the main pit, which
 was  used as an office.  The site is located 15 miles southwest of Norman,
 Oklahoma,  and one-half mile east of the community of Criner.   The nearest
 residence  is  located along the southwest site boundary.

                                 EVALUATION

 A.   SITE CHARACTERIZATION  (DATA NEEDS AND EVALUATION)

 1.   Environmental Media"

 The  soil contamination has been well defined.  The groundwater and surface
 water, and the interactions between them, will need to be more completely
 characterized in the future to determine public health implications.  This
 further characterization should be addressed in the second operable unit
 (migration control) RI.  A drinking water survey should be conducted and a
map  developed which indicate the location and population using the
groundwater (public and private wells) or the surface water.

2.   Land Use  and Demographics

The  land use  and demographic data provided to ATSDR were incomplete.
Additional information on the current use of residential wells near the
site would be useful to ATSDR.  If this information does not already exist
it should  be  gathered during the second RI.

3.  Quality Assurance/Quality Control

Conclusions contained in this Health Assessment are based on the
information received by ATSDR.  The accuracy of these conclusions  is
determined by the availability and reliability of the data.

B.  ENVIRONMENTAL PATHWAYS

The bulk of the contamination present on-site is located in the subsurface
soil.  This contamination is the primary source of the contamination in
the other media.  The first operable unit ROD requires the excavation of
all principal source areas and the appropriate treatment and disposal of
such .aaterials.  This action should help to decrease the migration of the
contamination from these source areas.  Additional soil sampling during
the second operable unit RI should identify any additional areas of soil
contamination.
                                   Page 3

-------
 The groundwater at the site is located in two  geologic  formations near the
 site.  One formation which is the primary source  of  drinking water in the
 area, is the alluvium of North Criner Creek, which is 40 to 60  feet deep
 at mid-valley.  The other formation is the Hennesey  Formation which is
 composed of fractured shale,  mudstone,  and sandstone.   The water located
 in the upper sediments is potable,  but deeper  it  becomes salty  and
 brackish.

 The flow of the groundwater has not been well  defined at this time.  It
 appears to flow to the southwest and the east.  Leachate has been detected
 up to 50 feet below the bedrock as  well as 400 to 2,000 feet laterally in
 the bedrock.   This is a result of the strong downward gradient  and the
 fractured Hennesey Formation.  Contamination has  also been detected in the
 alluvium of North Criner Creek 2,000 feet southwest  of  the site.  The
 plume ia estimated to be 1,000 feet long.   The mechanism of this transport
 is unknown and will be the subject  of further  study  during the  second
 operable unit RI.

 The North Criner Creek flows  from the northwest to the  southeast and is
 located south of the site.  Its alluvial valley extends almost  to the
 southwest corner of the site.  North Criner Creek joins Criner  Creek
 approximately 1 mile south of the site.   There is also  a creek  located
 about 400 feet east of the waste disposal areas.  This  stream was
 impounded to  create 3 small lakes which cover  approximately 6 acres,
 total.   There is a 2-acre pond located 1,500 feet west  of the drum mound.
 Surface water and sediment samples  were taken  at  various locations at the
 site.   These  samples indicated the  presence of contamination.   The
 additional sampling planned for the second operable  unit RI should include
 surface water and sediment samples  to better characterize those media.

 There was no  ambient air sampling conducted at this  site.  Without any
 data to the contrary,  air must be considered a potential medium of
 concern.

 Potential environmental pathways at this site  include migration of
 contamination from the primary source areas and the  soil to the
 groundwater,  surface water and sediment,  biota, and  air.  There is also
 the  potential for  the  contamination to migrate between  the various media.

 C.   HUMAN EXPOSURE PATHWAYS

 The  potential human exposure  pathways for this site  are ingestion of
 contaminated  soils,  groundwater,  and surface water;  inhalation  of dusts or
 vapors  from the  source areas,  the contaminated soil, or the contaminated
 groundwater;  and dermal exposure to contaminated  soil,  groundwater,
 surface water,  or  sediment.

 Inhalation  of dusts and vapors generated on-site  from the soils is a
potential exposure pathway for remedial  workers and  trespassers at the
 site.  People may  be exposed  to contamination  while  performing  tasks that
 require disruption of  the  soil,  thereby  causing a release of contaminated
 dust and  vapors.   This potential exposure  will  decrease once remedial work
 requiring excavation of the contaminated  ul  and construction  of the
 on-site landfill is complete.   Off-site  t  >re  is  a potential for exposure
                                   Page 4

-------
 from fugitive dusts and vapors  generated by disrupting the soil at the
 site,  and inhalation of vapors  generated while using the contaminated
 groundwater could occur if water  from  contaminated wells was used for
 showering,  irrigation,  washing  cars, etc.

 Ingestion of contaminated groundwater  is a potential public health
 concern,  off-site.   The maximum concentration of trichloroethylene  (TCE)
 (63  ug/L),  and trans-l,2-DCE  (120 ug/L) reported in Table 2 above, were
 detected'in a residential well  that was no longer in use at the time of
 the  sampling.   However,  the maximum concentration of lead  (23 ug/L)
 reported,  was detected  in a residential well which was still in use.  This
 concentration of  lead is of public health concern.  According to the
 Environmental Protection Agency these  homes have been provided alternate
 water.  There is  no known use of  the groundwater on-site.  The
 concentrations of contaminants  detected in the groundwater monitoring
 wells  located on-site are of public health concern and the water should
 not  be  used for domestic or agricultural purposes.

 Ingestion of soil is a  potential  human exposure pathway on-site.  The
 problem will center around the  workplace  (people eating lunch with dirty
 hands,  wiping dirt  on. their face,  etc,).  Dermal exposure is a potential
 human exposure pathway  from working with the contaminated soils,
 especially in the locations of  the primary source areas.  This potential
 exposure  will decrease  once the contaminated soils are contained within
 the  landfill.

 There is  a  possibility  of incidental ingestion and dermal exposure to
 surface water and sediments at  the site.  The surface water features in
 the  area  may be used for recreational  activities  (e.g., wading, fishing,
 etc.) .

 Human exposure pathways  that are  of public health concern are inhalation
 of fugitive dusts and vapors generated on-site and vapors generated from
 use  of  groundwater  off-site; ingestion of contaminated soils, surface
 water,  and  groundwater;  and dermal absorption of contamination from soil,
 sediments,  ourface  water,  and groundwater.

                         PUBLIC  HEALTH IMPLICATIONS

Much of the contamination detected in  the various media are VOC's.  Some
of these VOC's  may  cause depression of the central nervous system at high
concentrations.   Also,  some VOC's cause liver and kidney toxicity as well
as damage to  the  pulmonary and  hematopoietic systems.  In addition, there
 is evidence that  some VOC's are carcinogenic in laboratory animals.

TCE given orally  in  doses  of 24 or 240 mg/kg/d for a period of 14 days
produced effects  including increased liver weight, decreased hematocrit,
and depressed  cell-mediated immune response  (Tucker et al., 1982, S'nders
et al., 1982).  Based on liver  tumor production in mice, the Environmental
Protection  Agency (EPA)  has designated TCE as a potential human
carcinogen.   It is  unknown how  long residents may have been drinking or
using for domestic  purposes the highly contaminated water present in the
plume.  Long-term exposure to TCE at the maximum contamina ion detected in
residential  wells could  result  in a significant, increased risk of
                                   Page 5

-------
 cancer and other non-carcinogenic  toxic effects such as liver damage and
 depression of immune function.   Therefore the use of this groundwater for
 drinking,  bathing,  and other domestic  uses  is not acceptable.

 Lead is known to cause neurological  effects in gestating fetuses,
 neonates,  and young children.   It  can  also  cause peripheral neuropathy in
 adults. Other adverse health effects  caused by lead include:
 hypertension,  growth retardation,  and  effects on heme synthesis enzymes
 and  the eell  membrane.  The  maximum  concentration of lead detected in the
 soil at this  site was 5,470  mg/Kg  and  in the residential wells, 23 ug/L.
 Ingestion  of  lead at these concentrations is of public health concern.

 Acute PCB-related health effects typically  occur at higher concentrations
 than those detected on-site.   However, for  this site, the primary
 identified potential health  effects, resulting from exposure to PCB's
 through ingestion,  inhalation,  and dermal contact, are carcinogenic
 effects.   PCB's,  have been designated  as Group B2—Probable Human
 Carcinogens (EPA 1987).   This  designation is based on experiments which
 demonstrated  the induction of  hepatocellular carcinomas in laboratory
 animals fed high doses of PCB's in their diet  (Kimbrough et al., 1975;
 Norback and Weltman,  1985).

 The  toxicity  of chromium is  dependent  upon  the valence of the cation
 present (Cr VI or Cr III) and  the  anion to  which it is bound.  The valance
 of the chromium detected at  the site was not established; therefore, this
 assessment is  based on the potential toxic  effects of Cr VI, which is the
 more toxic form.  The cell membrane is penetrated by Cr VI more easily
 than Cr III.   Once  inside the  cell, Cr VI is converted to Cr III, which
 then complexes with deoxyribonucleic acid (DNA) providing an opportunity
 for  cell mutation (EPA 1987).   Dermal  contact with Cr VI may result in
 dermatitis or  skin  ulceration.   Chromium can also cause kidney and liver
 damage.  The maximum concentration found in the soil was 937 mg/Kg.
 Ingestion  of  chromium at this  concentration is of public health concern.

                       CONCLUSIONS  AND  RECOMMENDATIONS

 A. CONCLUSIONS

 This  site  is of potential health concern because of the risk to human
 health  resulting  from possible  exposure to  hazardous substances at
 concentrations that may  result  in  adverse health effects.  As noted in the
 Environmental  Pathways and Human Exposure Pathways Sections, human
 exposure to contaminated soil,  groundwater, surface water, sediment, air,
 and biota may  have occurred  in  the past or  may be occurring now.  The
 actions in the  ROD should reduce the potential exposures to the soil and
 should  reduce  the potential  for the migration of contamination from the
 source.  The second operable unit  RI should provide the additional
 information required  to  determine  what migration controls should be
implemented at  the site.
                                   Page 6

-------
B.  RECOMMENDATIONS

1.  During remediation, measures should be taken to protect people on-site
and off-site  from exposure to any dusts or vapors that may be released.
Workers on-site should be provided adequate protective equipment and
training, in  accordance with 29 CFR 1910.120, and should follow
appropriate National Institute for Occupational Safety and Health and
Occupational  Safety and Health Administration guidelines, when involved in
activities that may result in an exposure.  Workers should implement
optimal dust  control measures.  During working hours, appropriate
monitoring should be utilized at the worksite periphery to protect nearby
workers and residents.

2.  The information requested in the Data Needs and Evaluation Section of
this Health Assessment should be provided to ATSDR.

3.  In accordance with the Comprehensive Environmental Response,
Compensation, and Liability Act as amended, Hardage/Criner NPL Site has
been evaluated for appropriate follow-up with respect to health effects
studies.  Although there are indications that human exposure to on-site or
off-site contamination may have occurred in the past, this site is not
being considered for follow-up health studies at this time because the
level and extent of possible human exposure to site chemicals has nc'c been
defined and it is unclear that current exposure is occurring.  However, if
data become available suggesting that human exposure to significant levels
of hazardous  substances is currently occurring or has occurred in the
past,  ATSDR will reevaluate this site for any indicated follow-up.

                            PREPARERS OF REPORT

Environmental Reviewer:  Susan L. Mueller, Environmental Health
Specialist/ Health Sciences Branch.

Regional Representative:  Carl Hickam, ATSDR Regional Representative,
Region VI.
                                   Page 7

-------
                                 REFERENCES

 1.   Record  of  Decision,  Hardage/Criner, McClain County, Oklahoma, 1986.

 2.   Field Investigation  and Data Summary Report, Volume 1, Royal Hardage
     Industrial Hazardous Waste Site, CH2M  Hill, 1985.

 3.   Hardage/Criner Oklahoma Superfund Site, Partial Summary of Data, 1987.

 4.   Final Preliminary Public Health Evaluation, Technical Memorandum,
     Royal Hardage Industrial Hazardous Waste Site, CH2M Hill, 1986.

 5.   USEPA Drinking Water Criteria Document for Chromium, 1987.

 6.   USEPA Drinking Water Criteria Document for Polychlorinated Biphenyls
     (PCB'S)  ECAO-CIN-414, 1987.

 7.   Kimbrough,  R.D., Squire, T.A., Linder, R.E., Strandberg,
     J.D., Montali, R.J., Burse, V.W., JNCI 55: 1453-1459, 1975.

 8.  Norback, D.H. and Weltman, R.H., Environ. Health Perspect. 60:  97-105,
     1985.

 9.  Tucker A.N., Sanders V.M., Barnes D.W., et al., 1982.  Toxicology of
    trichloroethylene in the mouse.  Toxicol Appl Pharmacol;  62:351-357.

 10. Sanders V.M., Tucker A.N., White K.L., Jr, et al., 1982.  Humoral and
    cell-mediated immune status in mice exposed to trichloroethylene in
    drinking water.  Toxicol Appl Pharmacol; 62:358-368.

11. Casarett and Doull's Toxicology, The Basic Science of Poisons,  Ed. 3,
    Curtis D.  Klaassen,  Ph.D. et al., Macmillan Publishing Company,
    New York,  1986.

12. Environmental and Occupational Medicine, Rom, 1983.

13. ATSDR File.
                                   Page 8

-------
                                 APPENDIX
                                                       LocA-Ti
A/
                                                PURCELL SERIES WELLS
                                                HARDAGE/CR1NER SITE  OK-86

-------
         APPENDIX C

ADMINISTRATIVE RECORD INDEX
      (with Addendum)

-------
           APPENDIX D



STATE OF OKLAHOMA CORRESPONDENCE

-------
SENT SY:CKLA ST DEPT HEALTH   ;n-:3-_WE32:o4PM ENVIRONMENTAL HEALTH-
                                — - /•» r p , |  ' • .
                               •  .I'.-'r:  V;
    JOslH K. LaWfRr M*O«       •' * 7 * i* * \ |  " • 'c* "  »(** X4 T Pi\'
    Commissioner            . .H..M. _j-.< . -^ , •_  , ,^.. i. L/I /
    \**'!ff Sea:
                     .   B.er:J0.                           1000NATBITH
    JomS CjKncrvn. DCS.    9jregf FCntn. M0.                 fWl ftHTIMfl ^^^ ftaf »•<»»
    vce-Presoent          uui M jotwn. M J                wu^«wii« wi«, %M% »IM

    S^-iwy'-tMJw        LwW'aden                          ANaxw.o»»0»njNfTV|M>ioY|»
     November 13,1989

     Allyn M. Davis, Ph.D (8H)
     Director
     Hazardous Waste Management Division
     EPA Region VI
     1445 Ross Ave.
     Dallas TX  75202

     Dear Dr. Davis:
     Criner Proposed Remedial Action Plan. We were awaiting additional information and we
     were given only one working day to formulate a reply.
          Please be advised that trie discussions we have had wtth representatives of your
     agency have not served to eliminate several of our concerns rega/ding your proposed
     plan. As you are aware, the Oklahoma State Department of Health (OSDH) received the
     Remedy Raport for the Hardaga Industrial Waata Sfla on October 13, 1969 and subse-
     quently requested briefings in order to gain an appreciation of your proposal.  During the
     briefings your staff was unable to answer any of our questions relative to risk analysis,
     condition of the barrels and amount of liquids in barrels. Additionally, only some of our
     concerns relative to control of air emissions and other basic information and assump-
     tions upon which the proposed plan is built were answered.
     Your staff promised to forward Information relative to some of these issues; however, the
     information received was either unconvincing or not pertinent to these Issues. The
     important question of relative risk has been left unanswered.
         OSDH believes that several of the remedial action technotoglee proposed for site
    .clean up have merit and in the interest of public health should be Instituted as soon as
     practicable.
          elements of merit:
               Southwest trench or welte - institute Immediately
               V-shaped trench - Institute immediately
               Liquid extraction wells
               Vapor extraction welis - if this element is part of a permanent
                  cap with a vapor control component
         OSDH also believes that there are serious problems with  everal proposed clean up
    technologies presented in the Remedy Report and that these i ?ments of the plan have
    potential for increasing health risks to the public.

-------
      elements of disagreement:
           Drum lancing • not recommended
           Excavation of drums - not recommended
           U-shaped trench - not recommended
           Catalytic thermal treatment - as presented will not meet CAA
             requirements or BACT.
     The Oklahoma State Department of Health does not agree with significant elements
of EPA's Remedial Action plan for the Hardage/Crlner Superfund site as presented and
explained to us, therefor, 08DH cannot concur with the proposed plan based on the
information currently available.
     If you have any questions regarding this matter please call me at (405) 27 1-8056.

Very truly yours,
Mark 8. Coleman
Deputy Commissioner
for Environmental Health

-------
      APPENDIX E






RESPONSIVENESS SUMMARY

-------
                            Hardage/Criner Site
                 Community Relations Responsiveness  Summary
The Community Relations Responsiveness Summary has  been  prepared  to  provide
written responses to comments submitted regarding the proposed  plan  at  the
Hardage/Criner hazardous waste site.  The summary is  divided  into two
sections:
   Section
   section
           I: Background of Community Involvement and Concerns.  This
           provides a brief history of community interest and concerns
   raised during the remedial planning activities at the Hardage/Criner
   site.

   Section II:  Summary of Major Comments Received.  The comments (both
   oral and written) are.summarized and EPA's responses are provided.

I. Background of Community Involvement and Concerns

Individual interest or attention to the site has been moderate since the
signing of the 1986 Record of Decision for source control.  Individual
residents are concerned about their health, food chain impacts, as well as
the economy of the area.  Residents at the public meeting in October of 1989
indicated their desire for more frequent updates on activities and plans
for the site, and for credibility of the remediation through the removal
of wastes from the site.

II. Summary of Major Comments Received

Public notice announcing the public comment period and opportunity for a
public meeting was given on October 1, 1989.  The Proposed Plan fact sheet
was distributed to the site mailing list on October 12, 1989.  Fact sheets
were also sent to site repositories on this date, along with documents
comprising EPA's Administrative Record for the site.  The comment period
began on October 13 and ended on November 2, 1989.  A public meeting was
held on October 26, 1989, at the Grady County Fairgrounds Community Building
in Chickasha.  The purpose of this meeting was to explain the results of
the Remedial Investigation and Feasibility Study for groundwater, and to
explain changes in the source control remedy since the 1986 Record of
Decision for the site.  Approximately 40 people were in attendance, and a
number of questions and comments were received.  Two letters were received
with questions as well.

The comments/ 
-------
 Comments  were  received  from  the  following citizens:  Marvin Lyles, Edwin
 Kessley,  Royce Smith, Eilene Whitehead, Kay Hixon and George (Buddy)
 McKinnon.  Letters  were received from George McKinnon and Lisa Ozment with
 Progressive Environmental  Management, Inc.  Comments received are summarized
 below,  along with EPA responses.

 Question  #1.  Will  there be  any  problems with the roads due to movement of
 equipment?

 Response:   The majority of the activities at the site during remediation will
 take  place  within the site boundaries.  There will be some movement of equipment
 onto  the  site  to perform the work.  The only regular movement will be the
 shipment  of the liquids removed  from the source areas as they are taken offsite
 to be destroyed.  These liquids  will be accumulated until a load is ready for
 shipment.

 Question  #2.  Why weren't the source areas covered during the time of the
 investigations to prevent the infiltration of rainwater?

 Response:   Actions  were taken to eliminate immediate threats at the site,
 such  as erosion of  the  Barrel Mound.  From the end of 1982 when the Hardage
 property  became a Superfund  site it was not anticipated that it would take as
 long  as it  has for  clean-up  to begin.  This is particularly true of the delay
 for litigation  which has taken place since 1986.

 Question  13.   Why are there  differences in the locations shown for the southwest
 trench locations in the fact sheet and the overhead during the presentation?

 Response:   Trench or interceptor well locations shown on overheads during the
 presentation were only  approximate locations specified for the purpose of
 evaluating  alternatives for  groundwater control.  The trench or interceptor
 well  locations  specified in  the  fact sheet are also approximate and based on
 the current  spread  of groundwater contamination.  The exact location of the
 proposed  interceptor system  will  be determined during final design stages of
 the project, and will be based on the following considerations:

 a) the spread  of groundwater contamination immediately upgradient of the
 alluvium;

 b) the hydraulic properties  of the bedrock (these dictate the exact design
 requirements);  and

c) the location of  residential structures and property.

 EPA will make  efforts to install  ~.ne interceptor system so as to minimize
disruption to  homeowners  who may !:e impacted by construction and operation
and maintenance activities.

-------
Question 14.  Did all of the EPA's information come from the Hardage Steering
Committee's  investigation or did EPA do its own studies.

Response:  Much of the information about the Hardage site has come from multiple
sources.  EPA, the Oklahoma State Department of Health (OSDH), and the Hardage
Steering Committee (HSC) have all gathered information about the site.  The
most recent  investigation, that of the area groundwater, was conducted by
the Hardage  Steering Committee under the terms of a formal agreement with
EPA.  Among  the terms of the agreement were provisions for EPA oversight of
the work, split sampling by EPA to check the HSC's sample results, and EPA
review and comment upon the investigation reports, and final EPA approval.
EPA has its  own experts and employees to examine the information gathered and
is not dependent upon the interpretations put on the raw information by the
HSC.

Question #5.  How deep is the underground water in the area of Mrs. Smith's
property?

Response:  Water level measurements in the alluvium in this area indicate
that the groundwater table is about 15 feet below the ground surface.

Question 16.  Is there any threat from eating from pecan trees that have
roots into the contaminated groundwater?

Response:  Wells in the vicinity of the homestead in question (MW-12, 13, and
28, for example) exhibit detectable concentrations of contaminants.  Contami-
nants detected in the alluvium include the following compounds at the
concentrations indicated:

   Compound       Concentration Range    Drinking Water Standard
                  (parts per billion)      (parts per billion)


   Total volatile
    organics (VOC)      39 - 560                  not set

   Arsenic               1-7                   50

   Selenium              6-52                   10

As the table indicates, selenium and VOCs are present at  levels which pose a
concern for  drinking water.  Whether these contaminanats  are taken-up by
pecan tree roots is not known.  EPA will search for information on  exclusion
mechanisms in pecan trees, and further evaluate this question.

-------
 Question #7.   There were noxious  fumes  from  the  site during  its operation.
 What  about  these fumes?

 Response:   During the  time  that the  Hardage  site was open, much of the waste
 that  was brought to the  site  was  exposed  to  the  air.  There  were open ponds
 containing  waste and drums  and piles  of more solid material  were also left
 uncovered.  This allowed the  fumes to escape from these  sources.  The potential
 for escape  of  fumes is dependent  on  the surface  area of  contaminated material
 which is exposed.  During the selected  remedy, the major potential for such
 exposure is during excavation of  the  drums from  the Barrel Mound and the Main
 Pit.   Three direct actions  will be taken  to  control the  formation of fumes.
 First,  the  excavation  will  be done on the smallest practical working face.
 This  means  that  the area disturbed to remove the drums and any one time will
 be kept at  a minimum so  that  as little  contaminated material will be exposed
 to the  air  as  possible.   The  second  step  will be constant monitoring of the
 air both around  the excavations and  at  the fence line.   The  third is would be
 the use of  engineering controls to prevent vapor release problems.  This
 would entail the use of  foam  supressants  to  stop the escape  of the fumes up
 to stopping operations and  recovering the exposed areas  if the fumes cannot
 be controlled.

 Question 8.  Is  EPA aware of  a report by  Kirk Brown from Texas A & M saying
 that  contamination is  worse than  EPA  says?

 Response:   One of the  government's experts for the purposes  of the upcoming
 trial on the Hardage site is  Dr.  Kirk Brown. Mr. Brown  is therefore repre-
 senting the government and  EPA is in  agreement with his  opinions, which
 involve significant measures  to directly  reduce  contamination in the main
 source  areas.

 Question #9.  When will  a final decision  be  made on what will be done to
 clean up the site?

 Response:   The Record  of Decision which was  issued at the same time as this
 Responsiveness Summary completes  the  EPA's administrative process for selecting
 the clean-up method for  the site.  There  is  also a trial on  this issue which
 is scheduled to  begin  on November 27, 1989 in Federal District Court in
 Oklahoma City and which  should last  no  more  than twenty  days.  The Judge will
 then  give his decision on remedy.

 Question #10.  The notice that appeared in the Daily Oklahoman was not
 sufficient to notify the local residents  about the meeting on the sit^.
 Notice  needs to  be provided in papers which  the  local people use.

 Response:  The regulations  governing  the  issuing of public notice require
 that a  daily paper be  used  to give the  notice.   However, that doesn't prevent
 the placing of additional notices in  other papers.  In the future adc tional
 papers  will be used  including the Purcell Register, Chickasha Star, a->d the
Blanch^rd News.

-------
Question #11.  The meeting should have been held in McClain County where the
site is and not in Grady County.

Response:  Euture meetings will be held at a location in Purcell.

Question 112.  Will transcripts of the meeting be available to the public?

Response:  Yes.  A copy of the meeting transcript will be placed in the public
repository for the site in the Purcell Public Library, the offices of OSDH in
Oklahoma City, and at EPA's offices in Dallas.  In addition, copies will be
available on request from either Mr. Underwood or Ms. Price at EPA.

Question 113.  There are carcinogenic compounds in the water that has been
used by the Whiteheads (including children and infants) over the past 14
years.  This contamination is moving to Criner Creek, which in turn runs into
the Washita.  At what rate "is it moving?

The Whiteheads were provided alternate water from the McClain County Rural
Water District No. 7 in 1987.  Prior to this, domestic water supplies came
from wells installed in North Criner Creek.  Groundwater contamination has
migrated to a location in North Criner Creek which is approximately 1600
feet downstream of the North Criner Creek bridge on Old State Highway 122.
Groundwater flow rates for the upper alluvium are estimated to be between 80
and 170 feet per year and that for the lower alluvium between 9 and 19 feet
per year.

Question #14.   How many years until this contamination is contained?

Response:  Groundwater contamination will be removed when the groundwater
interceptor system and source control components (soil vapor extraction,
drum excavation and liquid extraction wells) are installed.  Construction is
expected to take some five months from start to finish.  Construction will
begin as soon as the litigation ends and the trench design is approved by
EPA.

Question #15.  Do we know how much contamination is present in Criner Creek7

Response:  We know there are levels of contaminants in the North Criner
Creek alluvium (see answer to Question #6).  Low levels of contaminants have
also been detected in surface water samples of North Criner Creek.  Contaminants,
however, have not reached Criner Creek.

Question #16.  How much time will be needed from the time a decision is made
to the start of the clean-up?

Response:  Once a decision has been made  (see Response to  Question  #9)  it
normally takes about nine months for clean-up to begin.  Unlike most sites,
much of the preliminary design has been completed for trial, and therefore
work could begin within several months of a final remedy decision.

-------
 Question 17.   Should the Whiteheads  continue  to  farm?

 Response:  Results of the Public Health  and  Environmental  Endangerment
 Assessment (PHEEA) conducted during the  groundwater  investigation  indicate
 that it is safe for the Whiteheads  to farm.  The  PHEEA  evaluated exposure
 scenarios which assumed dermal  contact with  affected water and  injestion of
 affected water, beef and milk for various  age  groups.  The results  of risks
 associated with exposure scenarios  are summarized in the  Second Operable Unit
 Feasibility Study, which indicate risks  below  EPA's  common acceptability
 range for risks associated with Superfund  clean-ups  (1  in  1,000,000 risk).
 Probable scenarios of future land use were developed for  exposure  calculations
 Probable exposure  scenarios for a child  or adult  were a few orders  of mag-
 nitude below EPA's acceptability range,  however,  worst  case scenario results
 showed risks from  exposure to be between 10-  through 10-  .

 Question #18.  Will  appeals be  made to the court  decision?

 Response:  We do not know.  Certainly all  sides in the  case have the legal
 right to do so, but whether or  not  that  right  will be exercised will have to
 be  seen after a ruling has been made.

 Question #19.  Some of the residents  near  the  site have been told  they  will
 have to move for the clean-up.   What  if  they do not  want  to?

 Response:  It is not and has never  been  the  position of EPA that any of the
 area residents would have to move.   Because  of the need to locate  some  of the
 portions of the groundwater portion of the clean-up  off of what was the
 original  Hardage site, access to some area properties may  be needed to
 implement the clean-up.   EPA does not feel that it is necessary to  move for
 the  purpose of institutional  controls, but cannot rule  out the  possibility
 of  temporary re-location during remedy construction. If  no agreement can be
 reached on  allowing access to property for implementation  of the clean  up the
 government  could as  a last resort obtain such  access through the use of emminent
 domain.  However,  the need to resort  to  such a method has  been  rare.

  uestion  #20.  Is  there  water contamination  to the north?   My grandfather
  rilled three wells  in an area  of North  Criner Creek north of the  area  of
 contamination shown  in the fact sheet.

 Response:   Data collect  for and by  EPA does  not indicate  that contamination
 has  migrated to this area.  To  be on  the safe  side,  however, the Oklahoma
 State  Department of Health (OSDH) has sampled  the wells in question. The
 has  indicated that results were sent  to  residents, which  showed no detectable
 contamination.

Question  #21.   Has all  of the seismigraphic  work  in  the area fractured  the
 bedrock?

 Response:   Geologic  studies at  the  site  have revealed details regarding the
 stratigraphy and structure of the site area.  While  fractures were  noted in
 the  local bedrock,  there is no  reason to believe  these  have been caused by
 seismic  testing in  the area.

-------
 Question  #22.  Are  there  faults  in the area?

 Response:   Studies  reported  in the literature have provided evidence for
 deep,  complex  faulting  in the Criner  region.  Depths of over 5000 feet are
 suggested  for  such  complex faulting.  No evidence has been found in the
 literature to  suggest that these faults extend up into the younger (less than
 about  1000 feet deep) bedrock in the  vicinity of the site.

 Question #23.   Something needs to be done quickly to remedy the site problems.

 Response:   EPA agrees with this statement.  Fortunately the upcoming trial is
 set for November 27, 1989.

 Question #24.  The  reputation of the  area has been devastated and property
 values depressed.   These things aren't being addressed.  The only way to
 restore confidence  is to remove the drums from the site completely and highly
 publicize  the  event.

 Response:   The selected remedy calls  for the removal and destruction of
 contaminants contained  in the source  areas through liquid extraction,
 excavation, and soil vapor extraction.  The rapid and permanent destruction
 of contaminants is  one of the primary benefits of the selected remedy over
 other options  that  have been proposed or considered.

 Question #25.  Once remediation of the Hardage/Criner Site is complete and
 for some unforeseen reason the selected means of remediation does not prove
 to be sufficient, will the PRP's be financially responsible for an extended
 remediation?

 Response:   Responsibility remains even after remediation.  Should
 additional  activity beyond that selected in this Record of Decision be needed
 the same parties would still be liable for remediaiton.  Such determinations
 are made on the basis of the 5 year Superfund review process and though re-openers
 in consent  agreements, which provide  for continuing liability if additional
 work becomes necessary.

Question #26.  If material from the site is transported offsite to another
 disposal facility and this facility later becomes a Superfund site will the
 PRP's be financially responsible for  the material transported to the site
 from Hardage/Criner?

Response:   The generators of the material would still be responsible for  it.
This scenario  is not expected to occur as the materials taken offsite should
he destroyed in compliance with EPA regulations.

Question #27.  Can  the  land  be put back like it was?

Response:   No.  The best that can be  done is to remove and destroy as much of
 the contamination as is possible and  to reduce the threat posed by what
contamination  remains by limiting its mobility and by careful maintenance  and
monitoring  of  the site.  Because of the need to maintain a cap on the  site,
 the land will  very  likely lay fallow.

-------
 Question #28.   (OSDH)   The objective  of  Superfund  is  the  protection of public
 health and the environment.  Any release of  contamination  into the water or
 air resulting  from the remedial  action at the  site is  inappropriate and runs
 counter to this objective.

 Response:   The objective of Superfund is the protection of human  health and
 the environment.   This objective includes protection  from both long-term and
 short-term risks.   The short-term risks  posed  by excavation of the drums from
 the source areas  exist, but can  be controlled  as described in the Response to
 Question #7 for releases to air.  The excavation of buried drums  is an
 established technique  which has  been  successful at similar hazardous waste
 sites.  Experience at  such sites has  shown the precautions which  need to be
 taken  to minimize  any  short-term risks to the  site workers or to  the public.

 The long-term  risks associated with the  Hardage site  are  a grave  concern.
 Ultimately this concern can-only be minimized  by the  recovery and destruction
 of  the contaminants.   No one can predict what  will  occur  over time as the
 drums  buried in the source areas corrode and continue  to  release  their contam-
 ination to escape  into the environment.   As  these  wastes  mix and  migrate the
 risks  they pose will continue.   These risks  include chronic, long-term risks
 posed  by carcinogenic  compounds.  With no known time  limit for the release of
 the contamination  from the source areas  a choice is apparent between rapid
 removal  and destruction of contaminants  using  pre-planned engineering and
 safety controls successful  in other similar  excavtions.   The alternative is
 attempts,  with  many uncertainties,  to achieve  long-term containment of
 hazardous  and  carcinogenic contaminants  which  are  mobile  and subject to
 continued  release  into the environment under conditions that are  neither
 known  or controlled.

 Question #29.  (OSDH)   The data provided  does not support  the volume or condition
 of  the drummed  waste that was used  to justify  the  removal  component of the
 proposed plan.

 Response:   It  is true  that assumptions have  been made  about how many of the
 buried drums still  contain liquid waste.  Faced with  the  choice of hoping
 that perhaps all or most of the  drums are empty or making the more conservative
 assumption  that they are not, EPA assumes that they continue to pose a threat.
 Given  the  stakes,  the  health of  local  residents and the environment, we would
 rather take the precaution of making  this assumption  and  then discover that
 the drums  are empty than gamble  that  they are  empty and later be  tragically
 proven  wrong.

 Question #30.  Can  we  be confident  that  all  areas  relating to soil vapor
 extraction  have been addressed?   Can  we  be confident  in the catalytic oxidation
 process  and  that this  in itself  would  not contaminate  the air?

 Response:   Once EPA selects  the  final  remedy for the  site, a detailed remedy
 design will  be  prepared  and  approved.  This  design will necessarily address
 all  areas of concern during  remediation, including refining the areas of
 contamination,  evaluation in detail the  performance of soil  vapor extraction,
 and covering details of  health and  safety during remedial  activities.  As  far
 a catalytic oxidation  is concerned, EPA  is required to utilize the Best
Available Control Technology (BACT) for  the  destruction of contaminated vapors
 resulting from  soil vapor extraction.  This  is a requirement of the Clean

-------
Air Act and State regulations.  If catalytic oxidation does not meet BACT,
then an alternate thermal destruction technology will be used.  Air monitoring
onsite and_at site boundaries will be instituted to assure air quality remains
below action levels desiged to protect human health.

Question #31.  The rural water system should be extended to those concerned
about possible domestic groundwater contamination.

Response:  There are currently no plans to further extend the rural water
system through Superfund.  Conditions which would warrent such an extension,
such as threatened or impacted groundwater in drainages outside North Criner
Creek, do not exist.  Questions about potential groundwater contamination
from the site have been evaluated and indicates that groundwater plumes are
migrating primarily into the alluvium of North Criner Creek where alternate
water has been supplied.  Planned actions in the alluvium would assure that
contamination in the alluvium is geographically controlled and concentrations
reduced.

Question #32.  A park or recreation area should be set up with information
about the site.

Response:  EPA has established a repository at the Purcell Public Library
which contains all such information.
EPA responses to revisions of the Second Operable Unit reports prepared by ERM-
Southwest are found on the following three pages.  These revisions were
submitted to EPA during the public comment period and are treated since EPA
approved the Second Operable Unit RI/FS prior to this time.

-------
                  TECHNICAL REVIEW COMMENTS
                       AMENDMENT NO. 1

                    SECOND OPERABLE UNIT
                REMEDIAL INVESTIGATION REPORT
            REVISION NO. 1 HARDAGE SUPERFUND SITE
                       CRINER, OKLAHOMA
The United States Environmental Protection Agency  (EPA) con-
ducted a technical  review of the Revision No.  1, dated
October 10,  1989, to the Second Operable Unit  (OU) Remedial
Investigation Report (RI) prepared by ERM-Southwest,  Inc.
Users of the RI should be aware that EPA has a number of
comments and technical concerns regarding the  report  and its
Revision No. 1.

Previous EPA review comments were organized to align  with
the Summary  and Conclusions Section (Chapter 6) of the RI
report.  Individual responses were presented for each of
54 conclusions in Chapter 6.  These responses  addressed the
major areas  of concern that EPA has with the RI.

This amendment addresses the October 10, 19S9  major
revisions to the Summary and Conclusions section (Chapter 6)
of the RI report.   The revised conclusion is noted and the
new response is presented beneath it.  Comments could be
raised for each of  the revised technical sections  and sub-
sections of  the report.

Users of the RI should therefore consider EPA's broad
responses and noted data limitations as needed when review-
ing the individual  technical sections or appendixes con-
tained within the RI.

Revised Conclusion
Chapter 6—Introductory Paragraphs

EPA disagrees that  Stratum II is relatively impermeable;
while it may be of  lower overall permeability  than overlying
or underlying units, Stratum II contains fractures and sand-
stone lenses.  The  source mounds are also not  entirely
within the bounds of Stratum II.  Excavation of the source
mounds into  Stratum I sandstones is also suspected.

The presence of irummed solids and liquids in  other portions
of the Main  Pit  besides the west side) is also expected.
                              1 0

DEN/53R/138.50

-------
Data developed by the HSC expert panel investigation was
sponsored by the HSC for their ongoing litigation purposes.
This study, as part of litigation, has not been endorsed by
EPA.

Revised.Conclusion No. 11

EPA does not agree with the characterization of Stratum II
as a low permeability unit.

The hydraulic head measurements alone do not yield informa-
tion on the vertical rate of groundwater movement through
Stratum II.  Hydraulic conductivity and porosity values are
also necessary.

EPA does not agree with ERM's revised groundwater velocities
for Stratum I and Stratum III.  ERM's values were calculated
using median hydraulic conductivity values and the lowest
hydraulic gradient observed during the study.  Recalculating
the velocities using the range of measured hydraulic conduc-
tivities and hydraulic gradients reveals that Stratum I vel-
ocities could range from 1/2 to 1,000 feet per year and
Stratum III velocities could range from 0.003 to 250 feet
per year.

Revised Conclusion No. 15

No comment.

Revised Conclusion No. 21

EPA desires to state that the period of record, while
revised to include a longer period, is still relatively
short and may therefore not be fully representative of the
range of flows that may be encountered in the creek.

Revised Conclusion No. 26

The peak flow measured for the south pond may not be
relevant since it is controlled by discharge through a pipe
rather than site hydrology.

It should be noted that the pe:iod of record, while revised
to include a longer period, is still relatively short and
may therefore not be fully representative of the range of
flow from the south pond or the alluvium.
DEN/53R/138.50

-------
Revised Conclusion No. 43

The modeling performed by SSPA was not conducted as an
approved task under the second OU work plan.  This modeling
is being performed as a result of the ESC litigation effort
and will.be evaluated separately.

As stated in previous responses, EPA does not agree that the
contamination found in the alluvial system is predominantly
the -result of surfical transport.

Revised Conclusion No. 45

See Revised Conclusion No. 43 response.

Revised Conclusion Nos. 54 and 55

The PHEEA does not address the exposure pathway that led to
the provision of an alternative drinking water supply to the
residents previously dependent on well water from the North
Criner Creek alluvium.  The PHEEA also ignores the potential
exposure of humans via the ingestion of aquatic organisms,
at an annual consumption of about 5 pounds per year, which
is possible under a recreational scenario for North Criner
Creek.  This is very important since the 10"* carcinogencic
risk criteria for some volatile organic compounds,  (such as
1,1-Dichloroethene at 1.85 ug/1) relative to the consumption
of aquatic life, is less than CLP contract detection limits.
The PHEEA also does not address a "no action"  alternative
that action alternative risk reductions can be compared  to.

The range of risks developed in the PHEEA are  applicable
only to the exposure scenarios evaluated and are  lacking in
that the ingestion of ground water and/or aquatic life
potential exposure scenarios are conspicuously absent.

The PHEEA also does not use reference doses, Rfds,  nor does
it follow the more recent EPA guidance for the preparation
of Human Health Evaluations 9285.701A dated July  1989.
                              12
DEN/53R/138.50

-------
       APPENDIX F

1986 RECORD OF DECISION
   FOR SOURCE CONTROL

-------
I
I
t
                                     RECORD OF DECISION
                              (ENFORCEMENT DECISION DOCUMENT)

         Site
         Hardage/Criner located in McClain County, Oklahoma

         Documents Reviewed
         I am basing my decision on the following documents which  describe the
         cost-effectiveness of source control remedial alternatives for the
         Hardage/Criner Site:
            0  Field Investigation and Data Summary Report, Royal  Hardage
               Industrial-Hazardous Waste Site near Criner, Oklahoma,  by CH?M Hill,
               dated May  1984.
            0  Source Control Feasibility Study, Royal Hardage Industrial Hazardous
               Waste Site near Criner, Oklahoma, by CH2M Hill, dated February 1985.
            0  Preliminary Public Health Assessment for Groundwater Ingestion for
               the Hardage/Criner site by CH2M Hill, dated August  1985.
            0  Summary of Remedial Alternative Selection, November 1986.
            0  Data gathered prior to and during enforcement actions in 1982 as
               described  in Appendix A to the Summary of Remedial  Alternatives.
            0  August 1986 memo, Bill Langley to Bob Davis descri-bing review and
               confirmation of 1984 data from sludge mound sampling.
H          °  Public comments received March 10 - April 15, 1986 on the Source
<--             Control Feasibility Study.
(.           °  Community  Relations Responsiveness Summary, November 1986.
£
 [
 I
f
             e  Staff summaries  and recommendations.
             0  Reference materials for  the documents listed above.
          Description Of Recommended Final Source  Control Remedy
          Excavate the principal  source  areas  (drum mound, main pit, and
          sludge mound) to bedrock and separate wastes  for treatment as follows:
             0  Solids - treatment and disposal  in an on-s1te landfill cell construe1-»d
                and operated in  compliance with the  Resource Conservation and Recover'
                Act of 1976, as  amended  (RCRA).
                                                                                 AR  00184

-------
i
i
i
 L
r
™

E

I
 L
 I
 I
                                    2

   0 Organic liquids will be incinerated.

   0 Inorganic liquids will be treated and disposed  by other means,
     as appropriate.

Temporarily close areas of residual  contamination  at the  former source
areas until remedial action is selected under the  second  operable unit.


Decision

Consistent with the Comprehensive Environmental  Response,  Compensation,
and Liability Act of 1980 (CERCLA) and the National  Oil and Hazardous
Substances Contingency Plan (40 CFR Part 300), I select the remedy
described above (alternative number seven  from the Source Control Feasi-
bility Study) for the Hardage/CMner site.  I have determined  that  this
remedy 1s cost-effectiv* and is protective of public health and welfare
and the environment.  The action will require operation and maintenance
to maintain the effectiveness of the remedy.  Since  wastes will be  left
on-s1te, the remedial action will be reviewed every  five  years to assure
that the remedy is still protecting public health  and the environment.
The State of Oklahoma has been consulted on the remedy.   I have considered
Section 121 of the Superfund Amendments and Reauthorization Act of  1986
(SARA), Including the cleanup standards thereof, and certify  that the
portion of the remedial action covered by  this Record of  Decision  (ROD)
complies to the maximum extent practicable with Section  121 of CERCLA  (as
amended by Section 121 of SARA).

If negotiations are successful, potentially responsible  parties  (PRPs)
will enter into a Consent Decree with EPA authorizing the PRPs to  Implement
the remedial action.  In the event that negotiations are  unsuccessful,
on-going litigation will be pursued by EPA and the Department of  Justice
in an effort to seo^«-p«cfprmance of the remedial actions.
 /Date
                                      ances E. Phillips
                                    Acting Regional Administrator
                                                                     ARO  '01

-------
                                       HARDAGE/CRINER
                                RECORD OF DECISION CONCURRENCE
 5

 I

 I
 r
  p
Allyn M. Davfs, Director
Hazardous Waste Management Division
           obert E. Hannesschlage/. Chief
            perfund Enforcement/Branch
                                                     >*»
        OJ4L^
/
Paut Seals
Regional  Counsel
                                                Bennett Stokes, Chief
                                                Solid Waste  and Emergency
                                                Response Branch,
                                                Office of Regional Counsel
  r
Larry D. Wright, Chief
Superfund Enforcement Section
 i
 c

f
                                                                                A ,c 0 0 0 I

-------
    e
   i
   f
   r
   
-------
                          SUMMARY OF REMEDIAL  ALTERNATIVE SELECTION
                                        HARDAGE/CRINER
                                   MCCLAIN COUNTY,  OKLAHOMA
J                  -
r        1.0   Site Location and Description
          2.0'  Operating History
|l        3.0   Current Site Status
—        4.0   Risk to Public Health and Welfare and the Environment
F
**        5.0   Alternative Development and Screening
f        6.0   Selected Alternative
          7.0   Compliance of Remedial Action  with  Applicable  or
tt                 Relevant and Appropriate Requirements
          8.0   Operation and Maintenance of the Remedy
I          9.0   Compliance of Source Control Remedy with Section  121 of the Superfund
^                 Amendments and Reauthorization Act of  1986  (SARA) to the Maximum
                   Extent Practicable
         10.0   Other Operable Units
         11.0   Enforcement
         12.0   Community Involvement
         13.0   References
 M
APPENDICES:
      A)  Chronology of EPA Site Investigations  Prior to  1984
      B)  List of Potentially Responsible Parties  Identified for the
          Hardage/Criner Site
T              C)  Community Relations Responsiveness Summary on the Source
L                  Control Feasibility Study
f-
                                                                                 Ar 100 JS

-------
fi

I

f

E
                          SUMMARY OF  REMEDIAL ALTERNATIVE SELECTION
                                        HARDAGE/CRINER
                                   MCCLAIN COUNTY, OKLAHOMA
                                       NOVEMBER  - 1986

          1.0)  SITE LOCATION AND DESCRIPTION

                The Hardage/Criner site Is located in McClaln County, Oklahoma,
                roughly 15 miles  southwest of Norman, Oklahoma and 1/2 mile east of
                the community of  Criner (Fig. 1).  The area is agricultural with
                land on all  sides of  the site used for grazing cattle.  Oklahoma
                Highway 24 forms  the  southern boundary of the site and a gravel
                road runs along the east side of the site (Fig. 2).

          2.0)  OPERATING HISTORY.
                The Royal  Hardage Industrial  - Hazardous Waste Land Disposal Facility
                was issued an operating permit by the  Oklahoma State Department of
E                Health (OSDH) in September 1972 and  commenced construction immedia-
                tely.  Two pits were excavated, the  main pit and the south pit.
                Originally, liquids and sludges from drums and tank trucks were
                discharged directly to these  unlined pits.  The methods of liquid
F               disposal  were evaporation and infiltration; however, the main pit
>-               filled to capacity rapidly.  Waste from the pit was transferred to
                temporary ponds, the "west pond" area, where liquids were slurried
r               with soil, transfered on to the south  pit and disposed concurrently
|               with styrene tar and oil recycling residues.  The  south pit was
                eventually filled in and waste piled to a height of about 10 feet
,               above grade, forming the "sludge mound".  After the first years
I               operation, drums were no longer emptied, but rather piled at the
*-               north end of the main pit beginning  the "drum mound".  The mound
                was extended southward and built to  a  height of about thirty feet.
1$              In all, roughly 18 to 20 million gallons of waste  were disposed at
L               the site during its operation.  The  sequence of operations has been
                compiled from OSDH inspection reports  and a deposition and hearing
C                testimony of the facility owner/operator.   In  1978, the State of
                Oklahoma filed complaints against the  facility for suspected lead
                poisoning of air around the site.  In  September  1979, OSDH began
£                proceedings to revoke the facility permit  for  operating unpermitted
                pits, failure to seal permeable lenses in  the  pits, Improper closure
                of pits, failure to retain runoff, and Improper  storage of wastes.
 •               In September 1980, the U.S. Department of Justice  (DOJ) filed suit
 f              on behalf of the Environmental Protection  Agency (EPA) against the
 E              facility under Section 7003 of the Resource Conservation  and Recovery
                Act  (RCRA).  Operations ceased in November 1980 prior to  the effective
 £              date of RCRA interim status requirements.   Royal  Hardage  then
 r              undertook site decontamination and closure efforts which  extended
                into 1982.   These  efforts consisted of mixing fluids  in  the pits  with
                soil, excavating visibly contaminated soils from mixing areas  and
 I               temporary ponds and capping the  source areas with a layer of soil.
 I               During closure, an effort was made to consolidate wastes  in the
                source areas (sludge mound, main  pit, and drum mound).
                                                                                 AR0001S5

-------
FIGURE  1;



Site location map



 Hardage/Crlner ROD 11/86!
                   II (lit I v-.

-------
                       - -— •- •+r-tr/^

                       BARREL
                       W. rs.i
                       MOUND
SLUDGE MOUND
• ~j  i if»
                                  Site topographic map

-------
          3.0)  CURRENT SITE STATUS:
<

'          3.1)  Site Investigations:

K              The site was inspected frequently by OSDH during  its  operation.
jf              Inspectors reported widely varying conditions,  with problems  Init-
                ially centered around pits filled to capacity and the potential for
m              overflow.  In 1976 OSDH requested that  Hardage  Installed groundwater
•              monitoring wells in the southwest drainage.   Eventually, thirteen
*              monitoring wells were installed by the  operator.   These have  been
                periodically sampled ever since, showing uniformly high levels of
f                contamination.  Some Hardage wells may  have  become contaminated by
                surface runoff entering the well bore during and  Immediately  after
                construction.  However, repeated purging of  these wells has not
p              lowered the levels of contaminants.

(                EPA first inspected the site in July 1979 due to  asbestos disposal.
                EPA contractor Ecology A Environment (FIT) collected  samples  at the
                site in August 1979, August and October 1980, and in  March and
                August 1982.  In 1984, work was begun by EPA contractor CHjM  Hill
                to gather supplemental data to allow preparation  of a Feasibility
                Study (FS) for permanent remedial actions on the  site. This  supple-
                mental data was compiled and field work was  documented In a Data
                Summary Report (DSR) completed in May 1985.   A  chronology of  EPA
                sampling efforts prior to 1984 is given Appendix  1n A.
T
t~
L
5
£
£
          3.2)  Contaminants:

                The site was permitted to accept all  types of Industrial  and  hazardous
                wastes except radioactive materials (OSDH-1972).   A total  18  to  20
                million gallons of waste was logged Into the site.  The resulting
                mixture contains virtually every type of waste produced by industries
                operating In the States of Oklahoma and Texas from 1972 through  1980.
                The general types of waste accepted at the site Included:   oil
                recycling wastes, chlorinated solvents, styrene tars, acids,  caustics,
                paint sludges, lead, chromium, cyanide, arsenic,  pesticides,  Inks,
                PCBs, and large quantities of waste of unknown content from Injection
                wells and other facilities Including what became  the Brio and Bio
                Ecology Superfund sites (Hardage 1972-1980, Eltex 1985). Under each
                of these broad waste types are numerous specific wastes streams
                produced from perhaps hundreds of different Industrial processes,
                each waste having It's own unique characteristics, impurities, and
                inherent hazardous and toxic properties.

                Some of the contaminants which pose an immediate threat through
                groundwater are chlorinated solvents, including:   l,2-d1chloroethane,
                1,1,2-trichloroethane, 1,1-dichloroethene, tetrachloroethene, and
                trichloroethene (CHzM Hill 1986a).  Other compounds such as lead,
                chromium, PCB, and toxaphene are present on the site and will pose
                long term or permanent hazards due to their persistence 1n the
                environment.  This is by no means an exhaustive list of either the
                wastes sent to the site or the contaminants of concern; further
                information is contained in the source control FS.
                                                                                  : (I 0 0

-------
[               3.3)   Remaining Features:

                Source areas  include the main pit, drum mound, and sludge mound
|               (Figure 2).   The  slude mound covers 1.5 acres to a thickness of
(               from  15 to 20 feet  above and within the former south pit.
E
i
I-
The main pit covers about two acres with a 15 to 20 foot thickness
of waste having been slurried with soil  and backfilled  Into the
pit, bringing it to the grade of surrounding land on the east and
forming a steep berm 10 to 20 feet high  on the west. A high concen-
tration of drums is located along the west side of the  pit and in
the barrel mound which covers about 0.8  acres to a thickness of  30
to 40 feet.  Estimates of the number of  unemptied drums remaining
in the source areas ranges from 10,000 to over 20,000,  with knowledge
of site operations and history favoring  the latter (Hardage 1972-80).

Other areas of the site were used as temporary holding  and mixing  "
ponds or may have been incidentally contaminated during site oper-
ations.  These areas are the west ponds, east ponds, north pit,  and
the southwest drainage (Figure 2).

Two buildings are still on-site.  A former sludge drying  building
used during the last year of operations  is located northeast of  the
drum mound.  A barn, used as the office, 1s between the sludge
mound and main pit.
          3.4)  Hydrology:
c
North Criner Creek runs in a northwest to southeast direction south
of the site with the alluvial valley extending nearly to the south-
west corner of the site.  This stream is perennial and joins Criner
Creek roughly one mile south of the site.  Criner Creek empties
into the Washita River thirteen miles south of the site.

A stream runs along the east side of the site, about 400 feet east
of the waste areas.  This stream has been Impounded to form a chain
of three small lakes totalling about 6 acres.  Another two acre
pond lies about 1500 feet west of the drum mound.
          3.5)  Geology:

                The site lies In what are commonly referred to as "redbed" sediments.
                This is a thick sequence of shales, mudstone, and sandstones which
 £             gr- :e back and forth over the space of tens to hundreds of feet.
 T,             The geology was originally described as consisting of the Bison
                sha'e overlying the Purcell sandstone.  Site investigations Indicated
 f              th  e units are not differentiated at the site; so shallow bedrock
                is  -eferred to collectively as the Hennesey formation (Ch^M Hill 1985).
                                                                                4ROOO

-------
                                                                          , 0
L
I
f
L
£
t
f-
      Beds generally dip to the south and southwest  at  less than 5
      No major faults are believed to underlie  the  site.  However, a well
      defined regional joint system is present  with  joint sets observed
      at N 20° W, N 20° E, and N 50° W (Kent  1982).

      The'alluvium of North Criner Creek Is 40  to 60 feet deep at mid
      valley and made up of decomposed bedrock  from adjacent  uplands.


3.6)  Geohydrology:

      The groundwater table beneath the site  generally  follows topography
      and flows are to the southwest and east.   Adjacent monitoring wells
      completed at different depths strongly  Indicate a vertical (downward)
      flow component exists.  Shales and mudstones  underlying the site
      are fractured and provide a secondary  permeability which, coupled
      with horizontal sandstone beds, has allowed migration of leachate
      from 400 to as much 2000 feet laterally through the bedrock and
      over 50 feet beneath the bedrock surface.  Questions exist on the
      method of transport to the southwest, where waste has migrated over
      2000 feet by unconfirmed pathways to enter the alluvium of North
      Criner Creek and apparently form a plume  over 1000 feet long  fn the
      alluvial aquifer.  Further evidence of  the bedrock's Inadequacy as
      a barrier to migration is provided by consideration of  contamination
      in two of the CH2M Hill - 1984 wells (BW-4, GTW-3) and  In a series
      of four FIT - 1982 wells (EW-3.EW-5.EW-6, and EW-7)  located to the
      east and southeast of the sludge mound.  These wells are in areas
      where no site operations occurred and where runoff would not  be
      channeled by topography.  The observed  400 feet of migration  Into
      these wells over the twelve years between 1984 and  1972 Indicates a
      rate of transport greater than 33 feet  per year.


3.7)  Areal Groundwater Supplies:

      Where possible, residents of the area have drilled water supply
      wells into the shallow alluvium of streams such as  North Criner
      Creek.  However, farms not located 1n alluvial valleys  and without
      access to these supplies can and have drilled producing wells Into
      the Hennesey formation within one mile  of the site.  Although not
      formally classified, both the Criner and North Criner  Creek  alluvial
      aquifers and the Hennesey formation would generally be categorized
      as Class lib under the EPA Groundwater Protection Strategy.

      Fresh water in this area is generally contained 1n  the upper sediments,
      with water becoming progressively more  salty or brackish  with depth
      as Indicated 1n F1gur? 3 (USGS -1966).
                                                                               A ^ (1(1(11 S.-.P

-------
       1
      4 .
      E

     r
    L'
S

f-
«•»!   -
      «
      c
      e
      o
      OJ
                                                                                                                      fc 0 0 o i  x H n

-------
I
C
I
r
F
r
c
§
t
E
3.8)  Extent of Contamination:

      Groundwater has been contaminated beneath  and adjacent to the
      source areas, in the southwestern drainage,  and  to the east and
      southeast of the source areas to depths  greater  than  50 feet.  The
      alluvium of Nortn Criner Creek has been  contaminated, as evidenced
      by the presence of from 100 to 300 ppb of  volatile organic chemicals
      In three separate wells,  which indicates a plume over 1000 feet
      long (Figure 4).  The relative contribution  of surface and subsurface
      pathways to alluvial contamination Is  unknown.   However, transport
      rates observed on other parts of the site  Indicate the source areas
      will, over time, continue or begin to  Introduce  contaminants to the
      alluvial aquifer through surface and subsurface  migration routes.

      Soils may be contaminated over several tens  of acres  as a result of
      indiscriminant operations and closure.  Evidence of this is provided
      by both visible surface contamination  and  stressed vegatation.
      Determination of the extent of surface contamination  will require a
      significant sampling effort during the second unit RI to adequately
      define the areas requiring remedial measures.


4.0)  RISK TO PUBLIC HEALTH AND WELFARE AND THE  ENVIRONMENT

      Many of the compounds present at the Hardage site are either known
      or suspected carcinogens.  Other compounds either are or are believed
      to be acutely toxic or capable of causing  damage to  specific organs.
      Some of these compounds also bio-accumulate  in  plant, animal, and
      human tissues.

      The principal routes of exposure for humans  are: Groundwater
      ingestion, direct contact, ingestion resulting  from  contamination
      of the food chain and possibly exposure  to airoorne  contaminants.

      The alluvial aquifer of North Criner Creek represents the most
      readily available source of drinking water in the vicinity  of the
      site.  This aquifer is contaminated with varying amounts of several
      chlorinated solvents, as evidenced by sampling  of water  from the
      abandoned Corley well and three alluvial monitoring  wells.   Since
      several of the compounds detected in these samples  are either known
      or suspected of inducing cancer and/or damage to specific organs
      of the body, chronic consumption of this groundwater would  pose
      unacceptable health risks.

      The Smith and Atkinson/Bearden wells a  » located 200 and 700 feet
      respectively from contaminated monitoring wells.  Domestic  use  of
      water from the abandoned Corley well or the EPA monitoring  well
      AW-S03 would pose lifetime cancer riskr  in excess of 10'4.   Use of
      groundwater from on-site would pose an  xcess lifetime cancer  risk
      averaging 21 and up to 60S (CH£M Hill,  1986a).

-------
£ o 9 s i 0 0 0 d'7

-------
                                             10
I
      Direct contact with  wastes  on  the surface of the site also poses
      hazards; however, the health risk has not been quantified.  Deter-
      mination of acceptable levels  of surface contamination will be a
      primacy concern in the second  unit  FS.  Current  human traffic on
      the" site is minimal; but  cattle do  occasionally graze on the site.
      Contamination of the food-chain by  lead, chromium, pesticides, and
      PCBs, on the surface of the site poses long-term hazards.  This
      concern has prompted construction of a fence to keep cattle off of
      the source areas; however,  there is evidence of continued Intrusion
      by cattle, giving rise to concerns  of food chain contamination.
      Certain compounds such as pesticides and PCBs have the ability to
      bioconcentrate through successively higher levels of the food chain
      (EPA 1985a).

      Inhalation of volatiles and contaminated airborne partlculates on
      and possibly adjacent to  the site may also pose long term hazards;
      however, this has not been  confirmed.
 i

 I

 F

 L
fc
5.0)  ALTERNATIVE DEVELOPMENT AND SCREENING

      In accordance with Section 300.68(f)  of the  NCP and  EPA  guidance
      documents (EPA 1985b), several  alternatives  were developed  for
      source control remedial actions at  the Hardage/Crlner  site.   Scoping
      of general  alternatives and objectives for remedial  action  was  first
      discussed in a 1983 meeting between EPA, OSDH,  and EPA contractors.
      After reconsidering these objectives  and alternatives  1n light  of
      the decision to proceed with a  source control operable unit,
      eleven alternatives were developed  (Table 1), as documented in  the
      FS.  Of these alternatives, four were retained  after screening  and
      developed in further detail (see Section 5.2-5.5 below). Estimated
      cost ranges for the four alternatives retained  are shown in Figure 5.

5.1)  Alternatives eliminated in screening:

      The most notable result of alternative screening was the elimination
      of those plans for containing the wastes In  place.   Several methods
      of isolating the wastes and reducing or eliminating  their release
      were considered.  After screening of technologies, several  1n-situ
      containment plans were developed.  Of these, capping in  conjunction
      with vertical trenches to Intercept shallow  groundwater  (Alternative
      15) would be expected to be the most effective. While this plan
      may be the most effective in-situ containment plan,  It can  by no
      means be considered as an adequate remedy on that basis  alone.
      Consideration of this alternative did, however, serve  as a  test of
      whether or not any form of capping-1n-place  remedy would sufficiently
      contain the source areas.  Technologies such as slurry walls  and
      groundwater injection/withdrawl were eliminated due  to the  presence
      of fractured bedrock, observed vertical migration of contaminants,
      and the absence of any continuous horizontal bedrock layer  at
                                                                               AKOOfJf -  ~

-------
                                          11
E
r
L
I
L
E
L
£
f
TABLE 1  -   Source Control Remedial Alternatives

>    Alternative to. i - ib Action:  no site rs«dial action taten.

>    Alternative No.  2 - Lifted Action:   remedial action consitts  of
     griding,  revegetetion,  fencing and institutional restrictions for
     the site.

>    Alternative No.  3 - Capping:   both source artaj would be left  in
     place and covered with a multi-layered cap.

>    Alternative No.  4 - Gradient Drains:  the scarce areas would  be
     left  in  place,   covered with  a  sulti-layer  cap  and  upgradient
     frcund\*ter drains constructed.

>    Alternative No. 5 - Perimeter Drains:  source areas would be  left  in
     place,  covered   with  a  sulti-layer   cap  and  upgradient  and
     downgradier± ground water drains constructed.

>    Alternative Ite.  6 - Partial tamoval:   a cap and perimeter drains
     would  be  constructed  around  the 'sludge Bound,  the  win  pit and
     barrel Bound would be axcavmted, the wastes treated, as needed, and
     disposed of in an on-sit« compliant RCRA  Undf ill.

>    Alternative No.  7 - On-*ite Disposal!   both source areas would  be
     •xcavated, the wastes treated,  as m«d«d, and disposed of in an en-
     site JOA compliant landfill.

>    Alternative No. 8 - On-site Incineration and Disposal:  both source
     areas  would  be excavated, the wastes  incinerated en-site and dis-
     posed of in an en-site ftCRA ccrpliant landfill.

>    Alternative No. f • On-cite Xncineration/0ff-*ite Disposal:  source
     areas  would  be excavated, the wastes incinerated en  site and dis-
     posed ef in an off«*ite JOA compliant  landfill.

>    Alternative No. 10 • Off-site Disposal:  both source areas would be
     excavated, the wastes treated on-site to s»et landfill criteria and
     transported to an off-site RCRA compliant landfill.

>    Alternative No. 11 • Off-*ite Incineration:  both source areas would
     be excavated and the  avjority  of the wastes transported to an off-
     site Incinerator for incineration and disposal.
 Off-site Incineration was assumed in  some cases for cost-estimating
 purposes.   This does not reflect a final decision to  use off-site
 disposal facilities for any waste  from the Hardage site.
                                                                           • o 001^ f;

-------
• 00 —
^^ . too-
i
C
400-
E f
r ^
I g 100-
E 1
e
L | too-
1 I
^Pp 100-
I— -
0 —
LAITINNATIVE
MO

10t
TO
§§
T

4tl
• It
171
•

• 40
• 74

•

tit
111
74
10
r
             NAME
                 INCIHERAT»OH MCWCMATlONy  OM-ifTl
       DIMOtAL  ANDDlfPOtAl  OFF-im    OM^OtAL
      HUMUM MMttlNTS O^HH-iOUHD COMBmOH,

• IDDLI HUMBIK HIFKItlHTI |Atl COMDITIOH,

lOWll HUMIIK KIFMItlHTI LOWm-IOUHD CQMDITtON.
                                                      H6URE  5;    AROOOJSfi

                                                      Costs and  sensitivity
                                                      ringes  for  source  centre
                                                      remedial alternatives

-------
                                                  13


                 reasonable depth with sufficient integrity to  provide  a  natural base
                 to any engineered containment system.   Further discussion  of these
 f                capping-in-place or in-situ containment technologies and the rationale
 |                for their rejection •s presented in both the Source Control FS  and
                 the Responsiveness Summary (Appendix C).

 r               Consideration of the cap and drain alternative revealed  the presence
 "*               of the same flaws as existed 1n other plans for containing wastes.
                 The drains were first considered to a depth of five feet below  the
 m               present groundwater surface.  However, migration has been  observed
 •               to over thirty feet below the water table, Indicating  that Intercep-
                 tion substantially deeper than five feet would be necessary to
E                 provide meaningful reductions 1n the releases  now occurlng.   In
                 addition, free liquids present 1n the landfill and In  drums which
                 will continue to deteriorate and burst would be released and allowed
 _-               to migrate vertically until the source was exhausted.   The plan
j                Involving shallow (five foot) trenches was estimated  to cost $35-40
 **-    <           million.  Extensive and continous operation and maintanence  (0  &  M)
      '           for the indefinite future would be necessary to maintain the collection
f                 system.  It was estimated that for collection rates greater than
                 0.5 gallons per minute, economics would indicate construction of  an
                 on-site treatment plant.  The problems associated with operating
 p               such a system for the indefinite future, meeting discharge requirements
                 and handling occasional peak flows could be significant.  In  addition,
                 there is no method for assuring the longterm operation of  such  a
                 treatment system.

                'The continued release of hazardous wastes and hazardous substances
                 with only negligible lateral interception and no vertical  intercep-
 r                tion, the need for indefinite 0 4 M when such cannot  be assured,
 ^               the potential for continued off-site Impacts, and the entire
                 "band-aid" type of approach that this, the most viable 1n-situ
                 containment alternative entails 1s wholly Inadequate to meet the
                 objective of CERCLA and the directive of the  NCP to provide a
                 permanent remedy meeting or exceeding applicable or relevant and
                 appropriate Federal public health and environmental  requiremnts.
                -As a result, closure in place was rejected as being Incapable of
                 containing wastes in the immediate  vicinity of the site and unac-
                 ceptable as a permanent source control  remedy.
F
L
£
           5.2)   Alternative 7 - On Site Disposal:

                 The source areas (drum mound, main pit, and sludge mound)  would be
                 excavated.  Solids would be treated and disposed In a landfill  cell
                 constructed on-site.  Liquids would generally be Incinerated.
                 After completion, the landfill would be closed with a multi-layer
                 cap and gas venting system.  The Remedial  Action (RA) would require
                 about 18 months to complete at a present worth cost of $70 million
                 (Table 2).
\                                         * -   «•                                ^- n n i\

-------
                                      TASLE 2:

                         ALTERNATIVE  NO.  7—ON-SITE DISPOSAL

          ITEM                                          COST
          GENERAL                                       $ 1,800,000

          EXCAVATION, SEPARATION,  SAMPLING             $12,979,000

          TREAT AND TRANSPORT  DRUMMED WASTES           $ 5,450,000

          DN-SITE DISPOSAL                              $12,789,000

          SITE RESTORATION                              $   196,000

          EVAPORATION/COLLECTION  POND FOR SURFACE
             WATER  _                                    $   280,000

          SURFACE WATER TRANSPORTATION,  TREATMENT
             AND DISPOSAL                               $ 5,403,000

          OTHER PROVISIONS                              $   249,000

          Construction Subtotal                         $39,146,000

          Bid Contingencies  (15%)                       $ 5,872,000

          Scope Contingencies  (20%)                     $ 7,829,000

          Construction Total                            $52,847,000

          Permitting and Legal  (7%)                     $ 3,699,000

          Services During Construction  (10%)           $ 5,285,000
          Total Implementation Costs                    $61,831,000

          Engineering Design Costs (10%)                $ 6,183,000

          TOTAL CAPITAL COSTS                           $68,014,000

          OPERATION AND MAINTENANCE                     $ 1,690,000
              (Present Worth)

          Bid Contingencies  for Operation and
             Maintenance (15%)                          $   254,000

          Scope Contingencies  for Operation and
              Maintenance (20%)                         $   338,000

          TOTAL OPERATION AND  MAINTENANCE
              (PRESENT WORTH)                           $ 2,282,000

          TOTAL PRESENT WORTH                           $70,296,000
	*:-itc  incineration was  assumed for cost-estimating purposes.
Tnis does not  reflect a final decision to use off-site disposal
facilities for any waste from the Hardage site.                     r jjjj^

-------
                                    15

5.3)  Alternative 8 - On Site Incineration and Disposal:

      The source areas would be excavated.  Hastes  would  be  Incinerated
      in a kiln constructed on-site.  Ash would still  contain  metals  and,
      until  proven otherwise through de-listing, would require disposal  as
      a Hazardous waste.  Disposal would be in a landfill  cell  constructed
      on-site.  This alternative would require four to eight years  to
      implement at an estimated present worth cost  of $326 million  (Table 3)


5.4)  Alternative 9 - On Site Incineration and Off  Site Disposal:

      The source areas would be excavated and wastes Incinerated  as above.
      The difference between this and Alternative 8 would be the  off-site
      disposal of incinerator ash.  This alternative would require  four
      to eight years to implement at a cost of $374 million  (Table  4).
      Future 0 A M for this source control remedy would be non-existent.


5.5)  Alternative 10 - Off Site Disposal:

      The source areas would be excavated; and wastes would  be transported
      off-site to existing Treatment Storage and Disposal (TSD) facilities
      for landfilling, incineration, reuse/recycling, or other treatment
      as appropriate.  This alternative could be Implemented 1n about 2
      years at an estimated present worth cost of $133 million (Table 5).
      As with alternative 9, 0 & M would be non-existent.


6.0)  SELECTED ALTERNATIVE:

      Alternative 7  (On-Site Disposal) 1s selected as the appropriate
      remedy for source control at the Hardage/CMner site.  The process
      by which this alternative was chosen over the other three under
      consideration is outlined below.
6.1)  Remedial alternative selection procedure:

      EPA Is required by Section 300.68(1) of the NCP to determine the
      appropriate extent of remedy by, "Selection of a cost-effective
      remedial alternative that effectively mitigates and minimizes
      threats to and provides adequate protection of public health and
      welfare and the environment".  The NCP goes on to state that the
      selected remedy will attain or exceed applicable or relevant and
      appropriate Federal environmental and public health requirements.
      EPA has c  isldered the cost, technology, reliability, administrative
      and other  concerns 1n selecting Alternative 7 as the appropriate
      remedy, a? documented below.  These considerations have only been
      applied t  alternatives meeting or exceeding the above noted
      requireme- .s.

-------
                                           TABLE  3:


                    ALTERNATIVE NO. 8—ON-SITE  INCINERATION AND DISPOSAl
              ITEM
              GENERAL

              EXCAVATION,  SEPARATION, SAMPLING

              ON-SITE  INCINERATION OF WASTE PILL

              TR£AT  AND  TRANSPORT DRUMMED WASTES
             «

              ON-SITE  DISPOSAL

              SITE RESTORATION

              EVAPORATION/COLLECTION POND POR
                 SURFACE WATER

              SURFACE  WATER TRANSPORTATION, TREATMENT
                 AND DISPOSAL

              OTHER  PROVISIONS
              Construction Subtotal

              Bid Contingencies (15%)
              Scope  Contingencies (20%)

              Construction Total
              Permitting and Legal (7%)
              Services During Construction (10%)
              Total  Implementation Costs

              Engineering  Design Costs (10%)
              TOTAL  CAPITAL COSTS

              OPERATION  AMD MAINTENANCE
                 (Present  Worth)

              Bid Contingencies for Operation
                 and Maintenance (15%)
              Scope  Contingencies for Operation
                 and Maintenance (20%)

              TOTAL  OPERATION HD MAINTENANCE COSTS
                 (PRESENT  WORTH;

              TOTAL  PRESENT WOP^H

*  Off-site incineration was assumed  or cost-estimating purposes.
   This does not reflect a final deci ion to use off-site disposal
   facilities for any waste  from the  ardage site.
COST
1T,352,000

$  12,979,000

$130,500,000

$  2,916,000

$  10,175,000

$     196,000

$     310,000


$  21,611,000


$     249,000
$186,288,000

$  27,943,000
$  37,258,000

$251,489,000
$  17,604,000
$  25,149,000
$294,242,000

$  29,424,000
$323,666,000

$  1,384,000
$

$
208,000

277,000
 $   1,869,000
 $325,535,000

-------
                             TABLE A:

    ALTERNATIVE NO. 9--ON-SITE INCINERATION/OFF-SITE DISPC

ITEM                                         COST

GENERAL                                      $  7,928,000

EXCAVATION, SEPARATION, SAMPLING             $ 12,979,000

ON-SITE INCINERATION OF WASTE PILL—         $130,500,000
   Design, Construction and Operation

TREAT AND TRANSPORT DRUMMED WASTES           $  3,788,000

WASTE FILL REMOVAL TO OFF-SITE LANDFILL      $ 16,958,000

OFF-SITE LANDFILL DISPOSAL CHARGES           $ 20,850,000

SITE RESTORATION                             $    196,000

EVAPORATION/COLLECTION POND FOR
   SURFACE WATER                             $    310,000

SURFACE WATER TRANSPORTATION, TREATMENT
   AND DISPOSAL                              $ 21,611,000
Construction Subtotal                        $215,120,000

Bid Contingencies (15%)                      $ 32,268,000

Scope Contingencies (201)                    $ 43,024,000

Construction Total                           $290,412,000
Permitting and Legal (71)                    $ 20,329,000
Services During Construction  (10%)           $29,041,000
Total Implementation Costs                   $339,782,000
Engineering Design Costs (10%)               $33,978,000
TOTAL CAPITAL COSTS                          $373,760,000

OPERATION AND MAINTENANCE                    $0
   .  (Present Worth)
Bid Contingencies for  Operation  and
   Maintenance (15%)                         $0
Scope Contingencies for  Operation  and
   Maintenance (20%)                         .$0	
TOTAL OPERATION AND MAINTENANCE  COSTS        .$0	
     (PRESENT WORTH)
TOTAL PRESENT WORTH                          $373,760,000

-------
                             TABLE 5:


              ALTERNATIVE NO. 10—OFF-SITE DISPOSAL

ITEM                                         COST
GENERAL                                      °^~2,538,000

EXCAVATION, SEPARATION, SAMPLING             $ 12,979,000

TREAT AND TRANSPORT DRUMMED WASTES           $  7,584,000

HASTE FILL REMOVAL TO OFF-SITE LANDFILL      $ 21,228,000

OFF-SITE LANDFILL DISPOSAL CHARGES           $ 26,100,000

SITE RESTORATION                             $    196,000

EVAPORATION/COLLECTION POND FOR
   SURFACE WATER                             $    280,000

SURFACE WATER TRANSPORTATION, TREATMENT
 AND DISPOSAL                                $  5,403,000
Construction Subtotal                        $ 76,308,000

Bid Contingencies (15%)                      $ 11,446,000
Scope Contingencies (20%)                    $ 15,262,000
Construction Total                           $103,016,000
Permitting and Legal (7%)                    $  7,211,000
Services During Construction (10%)           $ 10,302,000
Total Implementation Costs                   $120,529,000

Engineering Design Costs (10%)               $ 12,053,000
TOTAL CAPITAL COSTS                          $132,582,000
OPERATION AND MAINTENANCE                    $0
    (Present Worth)
Bid Contingencies for Operation
 and Maintenance (15%)                       $0
Scope Contingencies for Operation and
 Maintenance (20%)                           $0	
TOTAL OPERATION AND MAINTENANCE COSTS
 (PRESENT WORTH)                             $0
TOTAL PRESENT WORTH                          $'32,582,000
                                                 (Mi

-------
                                              19
fc

I
£
r
r
t
I
I
6cl.l)  Comparison of on-site versus  off-site  remedial action alternatives:

        Two alternatives, 7 and 8,  involve  on-site disposal of wastes excavated
        from source areas.   Alternatives  9  and 10 entail complete off-site
        disposal  of wastes.  The alternatives  7 and  10 Involve essentially
        the same  operations (i.e. excavation with limited Incineration and
        landfilling for the bulk of wastes), except  that they are on and
        off-site  variations of basically  the same alternative.  Similarly,
        alternatives 8 and  9 are basically  on  and off-site disposal options
        for residue from the on-site  Incinerator.  Based on this point, the
        analysis  below compares on-s1te to  off-site  disposal.

        Cost:  The cost of  .off-site landfilling and  Incineration alternatives
        exceed their on-site counterparts by 90%  (J63 million) and  15% ($48
        million)  respectively.

        Technology:  The on and off-site  options will be virtually  Identical
        in the treatment and disposal  technologies employed.  Control of
        the quality of work done under the  on-site alternatives may be
        somewhat  superior in this respect however, since these actions
        would be  conducted  under EPA  oversight and off-site treatment or
        disposal  would not.

        Reliability:  The off-site  disposal options  will provide reliability
        In preventing releases from this  site, simply because wastes would
        not remain on-site.  However, off-site disposal has the potential
        to increase health  risks at other sites.   It is not certain that any
        significant advantage exists  in reliability  of off-site over on-site
        disposal  locations.  The Hardage/CMne'" facility 1s 1n compliance
        with the  siting requirements  currently governing location  of
        commercial disposal facilities.  For this  reason,  any particular
        vulnerabilities which are present on the  Hardage site would not
        necessarily be absent at off-site facilities.

        Administrative:  Each alternative will comply  with RCRA  Part 264
        requirements, long-term objectives of  CERCLA as  amended, and all
        applicable or relevant and appropriate requirements  for  protection
        of public health and welfare and the environment.   Since wastes
        will be left on-site, the remedial  action will  be  reviewed every
        five years after it's completion, as required  by the  Superfund
        Amendments and Reauthoriration Act of  1986  (SARA), to assure that
        the  remedy 1s still protecting public  health and the  environment.

        Other concerns;  (Safety  during Implementation)   Both on and
        off-site alternatives carry Inherent  risks during  excavation.
        As discussed later, these  impacts  can  be controlled.   The primary
        difference between the on  and  off-site alternatives with respect
        to safety  during implementation  is the potential for accidents
                                                                               AROOO

-------
c
c
E
r

t
L
F
                                      20


        or spills during off-site  transport  of the wastes.  For example,
        an estimated 11,000 loads  would be required to transport the
        entire 180,000 cubic yards of  waste  off-site.  For the 400 to
        800 mile transport distance assumed  in the FS, trucks carrying
        waste from the Hardage site would be on the road  from four to
        eight million miles.

        Consideration of the components of the four remedial action alterna-
        tives evaluated shows that the key difference is  the presence of
        an on-site landfill  under  the  two on-s1te alternatives.  Information
        collected to date indicates that an  adequate landfill cell could be
        constructed on-site and successfully maintained.  The site meets
        RCRA Section 264.18 siting requirements for seismic stability and
        flooding potential.  Due to the hazards and costs arising from
        off-site disposal and transport, clear and significant benefits
        should be present before off-site disposal 1s selected.  Those
        benefits are not significant or certain 1n this case.  While such
        benefits may exist in the  off-site treatment of small to moderate
        quantities of specific wastes, organic liquids may be an example,
        off-site disposal for the  entire waste quantity is not preferred
        over on-site management of wastes in this case.   Therefore, the
        off-site alternatives are  eliminated from consideration, and the
        on-site disposal alternatives  (7 - On-site disposal; 8 - On-site
        incineration and disposal) will be carried on for further evaluation.

6.1.2)  Comparison of the two on-site  alternatives:

        Cost:  Alternative 7 would cost  $39-109 million to implement, with
        the most likely cost being $70 million.  Alternative 8 would cost
        $171-495 million, the likely figure  being  $326 million.  Therefore,
        the benefits to be derived from incineration of all waste would
        come at a cost of 470% ($256 million) greater than landfilling.

        Technology:  Incineration  is a key component of both alternatives  7
        and 8.Since some wastes  are  liquids which  cannot be landfilled,
        the decision to incinerate organic liquids  is appropriate.

        Incineration of all wastes will  have the net benefit of destroying
        virtually all organic materials.   Even with  incineration  however,
        heavy metals will still be present  in the  residue.  These materials
        simply cannot be destroyed.  The mobility  can be  reduced  by treating
        the waste to reduce it's acidity;  this would be done under either
        alternative.

        Reliability:  By incineration, virtually  all organics are destroyed,
        leaving an ash with varying contents of  heavy metals  requiring
        stabilization and disposal as a "characteristic"  hazardous waste.
        The landfilling alternative, with  limited  incineration,  removes
        only the free organic liquids with  the greatest  potential  for
        penetrating a landfill liner and  moving  into the  environment.

-------
E
I
I
r
c
[

P
L
C
 P
                                       21


      Landfilling and incineration of liquids  are  established technologies,
      with a demonstrated ability to perform under similar conditions.
      Incineration of soils contaminated  by a  heterogenous mixture of
      wastes, while feasible, has not yet  been attempted  on  a scale such
      as would be required for complete Incineration  at the  Hardage site.

      Administrative:  Both alternatives would meet all apHcable or
      relevant and appropriate requirements for protection of public
      health and welfare and the environment.   Since  wastes  would be
      left on-site, the remedial actions would have to be reviewed
      every five years as required under  Section 121  of SARA.

      Other concerns: (time to Implement)  Landfilling can be accomplished
      1n 12 to 18 months.  Incineration will  take  four to eight years.

      Based on the factors considered above,  Alternative  7 (On-site
      landfill with liquids incineration)  is  selected as  the appropriate
      remedy for the Hardage/Criner site.   This alternative  will provide
      a degree of protection to public health  and  welfare and the environ-
      ment similar to that which could be  achieved with complete Inciner-
      ation.  This remedy can also be carried  out  1n  a shorter time using
      proven technologies which are currently 1n wide-spread application.


6.2)  Detailed Description of the Recommended  Alternative:

      The following is a general sequence of operations and  construction
      activities required to implement on-site disposal for  a source
      control remedy at the Hardage/Criner site.  The timing and spec-
      ifications will be developed in detail  during the Remedial Design
      (RD) phase of response.

      A landfill cell will be constructed to meet  the minimum technology
      requirements for hazardous waste landfills as set forth 1n RCRA
      Section 264.301.  The key feature of such a  landfill cell  1s  a
      double liner system with interior leachate monitoring  and  collection
      (Figure 6).  The landfill will be constructed above grade  on  the
      high ground west and north of the present source  areas, as  Indicated
      1n the FS.  If at all possible, construction of the landfill  cell
      over significant residual contamination will be avoided. The  exact
      siting of the landfill cell will be based on the  results of  surface
      soil sampling during the second unit RI, consideration of  topography
      and hydrology of the site, and possibly additional  geotechnical
      data collected during the RD.  Sufficient land Is available  on
      which to siie a landfill cell.

      The sludge mound, main pit, and drum mound will be excavated.  This
      represents a volume of approximately 180,000 cubic yards,  and Includes
      in excess of 10,000 to 20,000  unemptled drums.  For this operable
      unit, the vertical extent of waste excavation  will  be to the upper
      surface of undisturbed bedrock  (see  Section  6.3 -  Clean-up levels).
                                                                                 A K 0 0 0 1 S

-------
       i
      £
     f
     r
    i
  i
f-
ty
      c
      3
     H

-------
                                  23
After waste excavation, feafnent,  and disposal  (described below),
tne e"ipty waste pits  and bedrock  now  underlying  the waste piles
will still regain.  This upper bedrock surface  1s  believed to be
satjratec witn waste  seepage to an  unknown  depth.  Such  residual
conti-^nation will generally not  be removed during the source control
remedial  action, since the appropriate extent of vertical excavation
cannot yet be defined.  In order  to prevent contamination of surface
runoff waters and to  eliminate direct contact exposure hazards  from
open areas of residual waste, 1t  will be necessary to construct a
protective temporary  cap over the former source  areas.   This temporary
cap will  serve the dual purposes  of preventing  direct rainfall  from
leaching the contaminated bedrock and eliminating  direct contact
hazards.  The cap will be constructed so as to  achieve these goals
and at the same time  be of a design to allow upgrading to meet  rele-
vant and appropriate RCRA closure standards should 1t be determined
by the second operable unit RI/FS that closure  in-place  1s an
appropriate permanent remedy for residual contamination  beneath the
former source areas.   Considering the relative  times  required for
design of the source control remedy and conduct of the management
of migration RI/FS, it is possible that final clean-up levels will
have been developed for the site prior to waste excavation.   If
such clean-up levels are available, the interim cap would be unneces-
sary and remedial action for residual contamination  1n the bedrock
beneath the former source areas can proceed directly  from excavation
of the source areas.

Since wastes excavated in the source areas will  range in consistency
from dry solids to relatively pure liquids, and since the appropriate
means of waste treatment and disposal is in large part determined  by
the physical consistency of the material,  1t 1s clear that  criteria
will have to be developed during the RD which allow  segregation of:
liquids  for  incineration or other treatment, solids  whose moisture
content  is appropriate for  landfilling, and solids requiring  moisture
reduction  prior  to landfilling.

Liquids  will be defined by  the relevant and appropriate  RCRA testing
procedures  (currently  the Paint  Filter  Test) which are  effective at
the time the remedial  design is  approved.  Liquds will be segragated
based  on their  chemical make-up  (i.e. organic versus Inorganic as
described  in the  FS).  The RD will  develop criteria for making this
distinc* on.

Solids,  as defined by  testing procedures noted  1n the above paragraph,
will  be  Dandled in a  manner based  on decisions  made 1n  a moisture
content   valuation, described below  under  Section 6.2.3.  Based on
the crit-ria developed there, wastes will  have  to have  to fall below
an upper limit on moisture  content,  after  treatment, before they can
be dispo ed  in the  landfill,  provided other requirements, such as land

-------
                                                   24
 k
 C
 i
 F
 L
 C

disposal bans, do not preclude their placement  in  the  landfill.
Based on the determinations and criteria from the  RD,  the  wastes  will
be treated and disposed as indicated in the general  schematic  shown
in "Figure 7.  Discussion of waste treatment and disposal  is  provided
below.

Treatment of organic liquids:  These liquids will  be incinerated.
Based on the economics of the volume of materials  encountered, this
would be done either at an off-site facility or on-site with a
portable or modular incinerator.

Treatment of inorganic liquids:  Based on the economics of the
volume and character of the liquids encountered, treatment and
disposal may be done either on or off-site.  On site treatment
would generally be'through physiochemical methods  capable  of removing
both organics and metals, to allow discharge under an  NPDES  permit
or transport to a publicly owned treatment works.   If off-site
treatment is selected, either deep well injection  or treatment at a
commercial facility would be available.

Treatment of Solids: Solids will ultimately be  placed  in  the landfill
cell constructed on-site.  Prior to disposal, the  wastes  will  be
subjected to treatment aimed at reducing their  toxicity and  mobility.
Since a large volume of contaminated soil is present,  significant
volume reduction would not be possible.  Such treatment may  include
addition of materials to stabilize the fill or  physiochemical
treatment designed to remove or alter specific  hazardous  constituents
or classes of compounds.  Treatment technologies identified  are:

       chemical neutralization (pH adjustment),
       solic,fication by addition of lime, cement, fly ash,  or
       other proprietary agents,
       reduction of liquid content,
       chemical oxidation or reduction, and
       air stripping to remove volatiles.

Other a'ternative treatment technologies identified during the
remedial design will also be considered for application,  and those
technol-gies showing promise for the specific wastes and  situations
at the rardage site will be evaluated further through bench  tests or
pilot studies as appropriate

During * ie remedial design, an evaluation Including bench testing
will be :onducted to determine an appropriate upper limit on the
moistur  content of fill which could be placed  in  the on-site land-
fill.  "M'S evaluation will consider the potential composition of
pore fl'. ds in the waste, the reaction of various  soil/fluid combin-
ations   der the type of triaxial stresses to be expected within the
f
                                                                                 R n 0 f) 1 's ~ 7

-------
                                     25
                        WASTE FILL FROM EXCAVATION
                                   I
                          |RCRA test for liquids
                 Liquid
          Criteria developed
          1n remedial design
Inorganic  liquids

      I
(Economics of
 volume
                                 Organic liquids
 (high
  volume)
  A	
  On-sue
  physlochemical
  treatment
Sol
   ds
                                                            Solid

                                                           -X
                                                           ent Dy:
                                            Treatment Dy: neutralization,
                                            fixation, or other methods
                                            determined during remedial
                                            design	
                                                               |On-Site Landfill
                                                   I Economics of
                                                   volume
Liquids
     Surface Discharge
     Under NPDES  Permit
On-site
Landfill
Dlume)
\
Off-site
physiochemical
treatment or
deep well
Injection
(high \ (low
volume \vo1ume)
1 \
|un-5ite
Incineration
with mobile
or modular
unit
/
Solid Liquid
Residues Residu
\
Un
La
i
-site
ndflll
uTT-site
incineration
at an existing
facility
l
Residues
es
1
Off-s te|
disposal j
>
Recycle or treat
and discharge under
NPDES permit
                                                              FIGURE 7;_A p Q 0 0 J  x

                                                              Treatment  schematic  for
                                                              alternative  number 7 -
                                                              on-site landfill with
                                                              liquids incineration

-------
fc
I
C
r
                                             26


               landfill, the potential  for long and short-term  leachate generation,
               and the effects of such leachate on various  liner  systems proposed
               for the landfill cell.  Based on the results of  this evaluation, an
               upper limit will be imposed on the moisture  content of  wastes which
               can.be disposed in the landfill.  Wastes  placed  in the  landfill will
               in no case be of the type which:

                  a) would be classified as "liquids"  by applicable or relevant and
                     appropriate testing procedures pursuant to the RCRA prohibition
                     on the disposal of liquids in landfills; or

                  b) are the subject of any land disposal bans  under the Hazardous
                     and Solid Waste Amendments to RCRA  or  the  Toxic Substances
                     Control Act which are determined  to be applicable or  relevant
                     and appropriate.

               Treatment technologies will be further  refined during the RD phase;
               and additional design data may be required.   The variability of
               wastes present in the source areas precludes any extensive  character-
               ization of wastes prior to excavation.  For  this reason, final
               determinations on appropriate treatment will 1n  some cases  have to
               be made during the RA itself.


         6.3)  Clean-up Levels for the Source Control  Operable  Unit:

               Selection of clean-up levels will be a  concern of the second operable
               unit (Management of Migration).  Ultimately, clean-up levels will
               have to be selected for the base of the pits and for surface soils
               on-site.  In the pit areas, the criteria  will generally Include
               potential for migration of metals and organics which have already
               migrated out of the pits.  The surface soil  criteria will focus on
               metals, PCBs, and pesticides due to their persistence 1n the
               environment, direct contact exposure hazards, and potential to
               contaminate surface runoff.

               LThe Source Control operable unit deals exclusively with the concen-
               trated pits and piles of wastes.  In this case, selections  of
               compounds of concern and selection of clean-up levels based on  soil
               concentrations of these compounds 1s not  appropriate.   The  criteria
               to be used for determining the extent of clean-up will  be  the
               surface of undisturbed bedrock.  If, at that point In  the  RA,
               additional data from the second operable un   RI/FS or  the  Source
r               Control RD has allowed determination of a f   il  clean-up level,
               then excavation, in-situ treatment, or permanent capping may be
               Implemented for the residual contaminants.   If such data  1s not
r              available, a temporary cap will be Installed  iver the excavated
[-             areas pending second operable unit remedy d€  >rm1nat1on.
                                                                               AROIHI I
                                                                                            ~; c

-------
G
I
r-
L
f
P
                                    27

6.4)  Health and Safety Concerns During Implementation

      Excavation of the waste piles and pits will  pose  hazards to workers
      via air and direct contact in addition to the  physical hazards
      normally associated with such construction.   In many cases the
      waste excavation and handling will  have to be  conducted under Level
      B protection (containerized air and protective clothing) to mimize
      hazards to the workers.  Air release of volatile  organics will
      likely increase during waste excavation.  Continuous monitoring of
      air around working areas, at the site perimeter,  and near offsite
      homes will allow identification of health threats to off-site
      residents and prevent problems from going undetected.  Dust and
      vapor suppression measures, maintenance of a small working face of
      exposed waste, and possible use of a temporary structure over the
      excavation will help to minimize air releases.

      Runoff retention structures and emergency holding ponds will be
      used to prevent chronic or sudden releases during construction.


7.0)  COMPLIANCE OF REMEDIAL ACTION WITH APPLICABLE OR  RELEVANT AND
      APPROPRIATE REQUIREMENTS FOR PROTECTION OF PUBLIC HEALTH AND THE
      ENVIRONMENT

      Section 300.68(i) of the NCP directs that EPA will, except in narrow
      cases such as "fund-balancing", select a remedy that  "attains or
      exceeds applicable or relevant and appropriate Federal public health
      and environmental requirements that have been identified for the
      specific site."  These applicable or relevant and appropriate
      requirements (hereinafter "Requirements") are discussed 1n an
      October 2, 1935 memorandum from Winston Porter, Assistant Adminis-
      trator for EPA's Office of Solid Waste and Emergency  Response,
      "CERCLA Compliance with Other Environmental  Statutes", which is set
      forth in the preamble to the NCP at 50 Fed.  Reg.  47912, 47946
      (November 20, 1985).

      The principal requirements and policies to be considered during
      conduct of the RA will be as follows:
7.1)  3CRA Subtitle C Permit Requirements, 40 CFR Part 264:

      While not deemed applicable to the site since It closed prior to
      November 19, 1980, these requirements are considered to be relevant
      and appropriate to this CERCLA response action to the extent Indicated
      below.  Leaving engineering considerations aside, the Part 264
      permit requirements are considered appropriate rather than che Part
      265 interim status requirements.  The facility closed prior to the
      effective date of interim status, rather than attempt to cciply
      witn these standards.  Royal Hardage notified EPA of hazarous
      waste activity under RCRA in August 1980, but withdrew the iotifi-
      cation in November 1980 and did not file Part A of the RCRA permit
      application, most likely because the site could not have me' those

-------
fc
C
•

§
                                              28

                standards without bankrupting the facility.   As Indicated previously,
                wastes were disposed haphazardly in unlined  pits and  the treatment,
                storage, and disposal of hazardous wastes at the facility as  far
                below the standards required for interim status facilities.   Indeed,
                EPA filed a lawsuit seeking clean up and closure of the facility
                under RCRA, Section 7003 in U.S. District Court in Oklahoma  City on
                September 8, 1980.  EPA has conclusive and demonstrable evidence of
                releases of hazardous wastes and hazardous substances from the
                disposal units of the Hardage site.  Given this situation, the most
                appropriate Federal environmental requirements to apply to the
                source control action, which is consistent with and forms a
                substantial increment of a permanent site remedy, would be the Part
                264 requirements, applicable to new facilities, along with their
                more stringent closure requirements.

                Additionally, EPA-believes that the physical nature of the site,
                It's hydrology, and underlying geologic conditions dictate that the
                waste materials not be left in-place.  Accordingly, 1t Is clear
                that the Part 264 permitting and closure requirements should be
                applied to the construction and closure of new disposal units
                necessary for this facility.

                Finally, it should be noted that, as the preamble to  the NCP states,
                "...  although the Subtitle C regulations differ as to whether a
                hazardous waste facility has a RCRA permit (40 CFR Part 264) or 1s
                operating under interim status (40 CFR Part  265), remedies will
                generally have to be consistent with the more stringent Part 264
                standards, even though a permitted facility 1s not Involved.  The
                Part 264 standards represent the ultimate RCRA compliance standards
                and are consistent with CErtCLA's goals of long term protection of
                public health and welfare and environment."   50 Fed Reg at 47918.
        7.1.1)  Subpart B - Siting Requirements:
                 This  will  govern  placement  of  the  landfill  cell on-site.  The
 '                principal  concerns  stated in this  subpart are  seismic stability and
 L               flooding potential.  Neither factor  appears to be a major concern
                 at  the Hardage site;  therefore,  compliance  does not seem to pose
                 problems.
C
it
        7.1.2)    Subpart  F - Groundwater:

                 This  subpart will  determine the extent  to which  the on-site
                 landfill will  be monitored.  It will  have a  much wider application
                 under the second operable unit.

-------
I

I

E
                                              29

        7.1.3)  Subpart G  - Closure and Post-Closure:

                These standards will apply to closure of  the landfill  cell(s)  after
                completion of the source control  RA.   The remedy will  comply with
                this subpart.

        7.1.4)  Subpart K  - Surface Impoundments:

                This will apply to any temporary Impoundments constructed during
                the RA that treat, store,or dispose hazardous wastes.   Impoundments
                will be lined, opearted, closed, and  1f necessary monitored in
                compliance with this subpart.

        7.1.5)  Subpart N  - Landfills:

                This subpart will govern construction and operation  of the landfill
                cell.  The landfill will
                meet requirements set forth for new landfills.


          7.2)  Toxic Substances Control Act:

                This would come into application if PCBs  are encountered  at levels
                greater than 50 ppm, since such materials are banned from land
                disposal.  In that case, alternative treatment would be required
                and implemented in order to comply with the Act.


          7.3)  EPA CERCLA Off-Site Policy (memorandum dated May 5,  1985; "Procedures  for
                Planning and Implementing Off-site Response Actions"):

                This policy will determine which TSD facilities are  eligible  for  receipt
                of hazardous substances from the site.  The policy generally  requires  a
                facility to be permitted and have no significant RCRA violations  or
                conditions affecting it's satisfactory operation.  Prior to disposing
                or authorizing disposal of wastes from this site the Region will
                contact the State in which the facility Is located,  review the
                facility's record of operation, and if appropriate contact other
                Regional offices of EPA where the facilities may be located to
                evaluate compliance with this policy.  No wastes will be disposed at
                any site not meeting the criteria set forth 1n the policy.


t         7.4)  Occupational Safety and Health Standards  (29 CFR Part 1910):

                These  standards will be applied during remedial actions to protect
                workers  from exposure  to hazardous substances and other physical
h-              hazards  associated  with  Implementation of the RA.  Methods for
'                assuring the safety of workers  Involved  1n  the  RA will be devloped
                and described  in  a  "Site Safety Plan" developed as part of the
I                Remedial Design.
r
c
 C
 "
 f
                                                                                HUH! !

-------
 C
  t
  L

  L
                                    30

7.4)  Hazardous and Solid Waste Amendments  to RCRA of  1984:

      The Hazardous and Solid Waste Amendments to  RCRA of  November 1984
      (HSWA), 42 U.S.C. 6901 et seq. contain  provisions setting several
      statutory dates for banning land disposal  of hazardous wastes The
      provisions discussed here are RCRA Section 3004  (d)(e) and  (g), due
      to the possible intersection of their statutory  deadlines with the
      construction schedule for a source control remedy at the Hardage
   •   site.

      The HSWA land disposal amendments are In fact not yet applicable or
      effective Federal requirements with respect  to CERCLA Section 104
      or 106 response actions, since their Implementation  dates are still
      some time off in the future.  The bans  found 1n  subsection  (g) are
      to be implemented during three periods  over  21 months for 1/3, 2/3,
      and finally all of the RCRA subtitle C "listed"  hazardous wastes
      commencing August 8, 1988, as determined by  EPA.  Those determinations
      will be made by rulemaking.  See 50 Fed. Reg. 19300  (May 28, 1986)
      for the list of wastes to be considered.

      The statutory ban on the "California List" wastes and solvents 1n
      subsections (d) and (e) and the prospective  bans laws of subsection
      (g) are not considered relevant and appropriate  at this time, since
      their applicability to CERCLA waste disposal is  1n the future.  The
      effect of the bans in subsection (g) on the  remedy 1s speculative
      at best, since EPA is required to engage 1n  rulemaking for  methods
      of land disposal and pretreatment for such disposal, 42  U.S.C. 6924
      (g)(5) and (m).  Futhermore, it must be emphasized that CERCLA
      requires the selection of cost-effective remedies and does  not
      require EPA to implement standards that are  not  1n effect.

      During the course of remedial action and construction, EPA  intends
      to further review the effect of land disposal bans on waste disposal
      at the site and the issues of how such laws  will be  Implemented
      should they intersect the construction schedule.  Additionally,
      bench tests and/or pilot studies may be performed with  respect to
      pre-treatment methods for solvents and other organics potentially
      impacted by such bans.


8.0)  OPERATION AND MAINTENANCE

      The on-site landfill will require little routine operation  and
      maintenance (0AM).  Monitoring of the Interior leachate detection
      system will be required, as will periodic Inspections of the cap
      and monitoring of gases leaving the venting system.   Development
      and routine sampling of a groundwater monitoring network  will  also
      be necessary for 30 years, at which time the need for additional
      monitoring will be reevaluated.
f

-------
E
I
r
i
i
E
£
                                     31

       To provide a contingency  in  project  cost  estimates, it was assumed
       that at 30 years after construction  replacement of the landfill
       liner and cap might be necessary.  The  cost  1s reflected  in the
       present worth cost estimate  of $70 million.   Operation and maintanence
       costs on a present worth  basis are estimated as $2,282,000 in  1985
       dollars.

 9.0)  COMPLIANCE OF SOURCE CONTROL REMEDIAL ACTION WITH SECTION 121  OF
       THE SUPERFUND AMENDMENTS  AND REAUTHORIZATION ACT OF 1986  (SARA) TO
       THE MAXIMUM EXTENT PRACTICABLE

 9.1)  Basic Certification:

       The selected remedy will  comply with Section 121 of the Comprehensive
       Environmental Response, Compensation and  Liability Act of 1980 (CERCLA),
       as amended by SARA, including the  cleanup standards thereof, to the
       maximum extent practicable.   The  selected remedy is considered to
       be cost effective and protective  of  human health and  the  environment
       as well, in accordance with  the NCP.

9.2)   Permanent Solutions and Technologies

       In selecting this remedy, EPA has  considered a full range of alterna-
       tives and solutions and alternative  treatment technologies that
       will result in a permanent and significant decrease in toxicity,
       mobility, or volume of the hazardous substances present.   In conduct-
       ing its assessments of remedial alternatives and treatment technol-
       ogies, EPA has considered:

         1) The long term uncertainties  of  land  disposal;

         2) goals and requirements of the Solid  Waste  Disposal  Act  ("RCRA");

         3) persistence, toxicity, mobility and  bloaccumulation potential
            of the wastes;

         4) short and long term potential for adverse  human  health  effects;

         5) long term maintenance costs of the remedy;

         6) potential for  future remedial actions costs  1f the  remedy fails;

         7) potential threat to human health and the environment from the
            excavation,  transportation, and redisposal,  or containment of
            hazardous substances.

 9.3)  Remedy Analysis:

       The  selected  remedy  is a  remedy for the  first operable unit of
       remediation  -  source  control.  It is a significant part  of overall
       remediation  at the  Hardage  site and is consistent with a permanent
       remedy  for the site.   The second  operable unit, "management of
       migration",  is now  under  development.

-------
                                     32

       This remedy will employ treatment through  incineration  of  all  free
       liquid organics in the estimated 175,000 cubic  yards  of waste  fill,
       as well as the more than 18,000 estimated  drums of  waste buried
       on-site.  Remaining waste fill  and inorganic  solid  drum contents
       wi-11 be treated through stabilization measures  prior  to redisposal
       1n a double lined on-site RCRA compliant landfill cell. In  carrying
       out these measures, EPA will  be permanently and significantly
       reducing the volume, toxicity,  and mobility of  the  hazardous sub-
       stances present at the Hardage  site.   Further,  EPA  will  avoid  in
       large measure the potential dangers and uncertainties of transport
       and disposal off-site, with  its on-s1te approach for  the bulk  of
       wastes.  EPA requires that this source control  remedy be reviewed
       not less than every five years  to assure that human health and the
       environment are being protected.

       As noted previously, in Section 7 herein,  EPA has scrupulously
       considered the applicable or  relevant and  appropriate federal
       requirements for protection  of  public health  and the  environment  in
       accordance with the NCP.  EPA has also looked into  the  Issue of
       applicable or relevant and appropriate state  environmental laws  and
       has determined that the "RCRA analogous" regulatory requirements  of
       the Oklahoma Controlled Industrial Waste Disposal Act,  as  amended,
       authorized by EPA under RCRA  to operate in lieu of  the  EPA regulations,
       are met or exceeded by the selected remedy.  In a nutshell,  EPA  has
       complied with the SARA Section  121 cleanup standards  to the  maximum
       extent practicable.


10.0)   OTHER OPERABLE UNITS

       EPA's response actions on the Hardage/Criner  have been  d'vided into  two
       ope-rable units:  Source Control (the remedy discussed in this  document)
       and Management of Migration  (also referred to as the  groundwater/off-site
       operable unit).

       The source control response  is  limited to  the source  areas of  the  site
       (sludge mound, main pit, and  drum mound).   The  bases  of the  main  pit  and
       southern pit (beneath the sludge mound) at approximate  elevations  of  1109
       and 1093 feet MSL respectively  form the lower bound of  the source  areas.
       The lateral bounds of the source areas are described  by the  base  of  the
       slopes on the north, south,  and west faces of the waste piles  and  pits,
       and as the lateral extent of  the excavated pits on  those sides of  the
       source areas where wastes and cover have been backfilled to  ground  level.

       The management of migration  RI/FS will Include  the  following:

           0  Definition of the extent and levels of contamination  present
              in soils and rock outside the source area;

           0  determination of the  extent and fate of  groundwater contamination
              in the alluvium of North Criner Creek  and the  feasibility
              and need for remedial  actions in the alluvial  valley;
                                                                          0 0 0

-------
                                               33

                        determination of permanent surface clean-up  levels on-site to
                        prevent or minimize further degradation of potential surface
                        and ground water supplies, direct contact  hazards to the
                        puDlic, and other long term hazards.
L
          11.0)   ENFORCEMENT

           11.1)  Hardage  I:
r
r
c;
L
r
                 In  1979, EPA inspections of the site Indicated poor waste management
                 practices  posing potential threats to public health and welfare and the
                 environment.   In September 1980, the U.S. Department of Justice (DOJ)
                 filed  a complaint on behalf of EPA in U.S. District Court in Oklahoma
                 City,  Oklahoma.  The complaint alleged violations of Section 7003 of RCRA
                 and sought proper cleanup and closure of the site.  The facility
                 had ceased operations in early November 1980, before RCRA Interim
                 Status Standards came into effect.

                 In  1982, DOJ and EPA amended the existing complaint against the
                 facility owner and  operator Royal Hardage.  The complaint was
                 changed to include  allegations and requested relief under Sections
                 106 and 107 of the  Comprehensive Environmental Response Compensation
                 and Liability  Act (CERCLA).  In December 1982, the Court found that
                 the site posed an imminent and substantial endangerment to public
                 health and welfare  and the environment as defined by CERCLA Section
                 106 and RCRA Section 7003.  In August 1983, the Court granted a
                 partial judgment for over $211,000 in response costs, which EPA had
                 incurred through 1982, against Royal Hardage.

                 Hardage filed  for bankruptcy in 1983 and again in 1985, and EPA has
                 never  recovered  its partial judgment.

           11.2)  Hardage II

                 EPA compiled available records from the sites operations Including
                 daily  and  monthly site logs of wastes received, waste manifests,
                 and disposal plans  and records filed with the State of Oklahoma by
                 generators and transporters of waste to the  site.

                 As  a result  numerous Potentially Responsible Parties (PRPs) were
                 identified.   ' i  December 1984,  EPA mailed letters to 289 of these
r                PRPs requesti'   Information about  their waste disposal at the
[                Hardage  site   der  authority  of Section  104(e) of CErtCLA and  Section
fe                3007 of RCRA   i notifying the  PRPs of their potential liability
                 for site  clear p.   As  further Information was gained,  Information
L,                request  and nr ice  letters were  sent to additional  PRPs Identified.
                 At  the presen- time,  over 400 PRPs have  been Identified.   Various
                 PRPs have gon   jut  of  business  or  cannot be  located; therefore,
                 approximately   iO have been  contacted.   A number of these  parties,
                 have organizec  nto the  Hardage Steering Committee  (HSC).   The HSC
                 has met  with [ \ and  OSDH on  numerous  occasions  since  EPA's first PRP
                 meeting concer  ng  the site  in  January  1985.


                                                                               AK 0001
 L
 r

-------
fr

I

i
                Since  the  FS was on going at the time the PRPs were notified  and
                CERCLA progam policy previously did not allow PRP conduct  of  RI/FS
                studies without a  signed agreement to also implement the EPA  selected
                remedy, the PRPs were not involved in preparation of the FS.   In
                May  1985,  EPA released the DSR documenting 1984 site Investigations:
                and  HSC also obtained all EPA files on the site.  The HSC  has retained
                Dames  A Moore and  more recently ERM-Southwest to provide technical
                support in their dealings with EPA.

                In July 1985 the Court administratively closed the 1980 case  against
                Hardage, providing that the U.S. could re-open the case for the
                purpose of seeking appropriate relief until April 1, 1986, at which
                time the case would otherwise be dismissed.  OOJ, on behalf of EPA,
                filed  a motion on  March 27, 1986, to amend the existing complaint
                and  add generators and transporters to the existing case.  The Court
                ultimately denied  the motion and dismissed the case, providing that
                Royal  Hardage could be named for limited purposes 1n a subsequent
                case.

                On June 25, 1986,  DOJ filed a new complaint naming 36 generators
                and  transporters of waste at the site.  The complaint asks for
                performance of the EPA selected source control remedy, maintenance
                of site security,  conduct of a RI/FS for the management of migration
                operable unit and  any subsequent EPA selected remedy, and recovery
                of EPAs' past and  future response costs.  A status conference was
                held on September  3, 1986, and a second status conference has been
                set  for January 7, 1987.


         12.0)   COMMUNITY  INVOLVEMENT

                Due  to the large number of PRPs for this site, the majority of
                meetings,  comments on the FS, and other external communication has
„                been with  these parties, However, attention has been given to the
,                concerns of near site residents and other  Interested parties.

                When the draft FS  was completed on February 20, 1986, a press release
*                was  issued announcing this fact, copies of the  FS  were  placed in
i                repositories, and  a copy was provided directly  to  the Hardage
                Steering Committee.   The public comment period  was from March 10-
                April  15,  1986.  A public meeting was held in Chickasha, Oklahoma
i                to  answer  questions  and  receive comments  on  the FS on March  20.  The
1                response to questions, comments, and concerns raised during  this
                period is  contained  in the Responsiveness  Summary, Appendix  C.

-------
                                               35


           13.0  REFERENCES
           CH2M Hill   1985
                   Field  Investigation  and  Data  Summary Report, Royal Hardage
                   Industrial  Hazardous Waste Site.  CH?M  Hill.  May 22, 1965

           CH2M Hill  1986a
                   Preliminary Public Health  Assessment,  CH^ Hill. August 1986
T         CH?M Hill  19865
fc*                 Source Control  Feasi5ility  Study, Royal Hardage  Industrial
                   Hazardous Waste Site, CH?M  Hill.  February 20.  1986

B         EPA 1985a
                   Public Health Assessment  Manual.  EPA  - Office  of Solid Waste
.jj                 and Emergency Response, November  1985

' :         EPA 19855
                   Guidance on Feasibility Studies Under CERCLA,  EPA, June  1985

|         EPA 1986
                   Superfund Remedial  Design and Remedial Action  Guidance,  EPA,
f                  June 1986

^         Eltex 1985
                   Letter from Eltex Chemical  and Supply (Houston,  Texas) to
                   Stephen Phillips (EPA-Dallas), August 1985

           Hardage 1972-80
f                  Monthly waste site log of materials received at  the  Hardage site

           Kent  1982
rt                 Evaluation of Hydrogeoloqy  at Royal Hardage Industrial Waste
                                  lUahoma, Douglas C. Kent, Ma
        site; Criner, (Jklanoma, Douglas C. Kent. May 1983

OSDH  1972
        In
        1972 to Royal HJartdage 5y OSDH

USGS  1966
 f"                 Industrial-Hazardous waste landfill permit issued September 12,
f*         USlai  1*00
L                 Base of Fresh Groundwater in Southern Oklahoffla, D.L. Hart,
                   United States Geological Survey Hydrologic Atlas - 223, 1974

t

 r

-------
 c
 t
L                             "      APPENDIX  A
                       CHRONOL06-, OF EPA SHE mEST,MT,0«

^                                  PRIOR TO 1984

-------
r

f*

\»
                               APPENDIX   A

EPA Sampling and Inspections  of Hardage/Criner  prior to 1984:
June 27. 1979
Inspector:        Ralph Hawkins  (EPA-Ada  Branch) accompanied by Oklahoma
                 State and County Health Department personnel
Purpose:         NESHAPS inspection due  to  asbestos disposal
Result:          Recommended  Sampling of site
Documentation:   7/3/79 memo, Hawkins to Charles Gazda (EPA-Dallas)
August 15. 1979
Inspector:        S.C. Yin (EPA - Ada Branch) with  other EPA and State
                 Health Department personnel
Purpose:         Obtain samples and inspect site
Result:          Nine soil, water, and waste samples taken, analyzed  for
                 metals and organics; photos taken
Documentation:   9/10/79 memo, Yin to Charles Gazda  (EPA-Dallas)
                 10/26/79 memo William Langley  (EPA-Houstpn Lab)  to Oscar
                 Ramirez (EPA-Dallas) transmitting analytical  results.
August 14, 1980
Inspector:        Thomas Smith of Ecology &  Environment  (FIT)  for  EPA
Purpose:         Off-Site sampling
Result:          Three samples taken from off-site drainage pathways;
                 analyzed for metals and organis; photos taken
Documentation:   8/21/80 memo T. Smith to Charles Gazda (EPA-Oallas);
                 9/23/80 memo William Langley (EPA-Houston Lab)  to William
                ' Librizzi  (EPA-Dallas) transmitting analytical results
October  1. 1980
Inspector:       S.C.  Yin  (EPA-Ada  Branch) with FIT personnel
Purpose:         Off-site  sampling
Result:          Thirteen  (13)  samples  taken from off-site drainage  and
                 domestic  water wells,  analysis for metals and organics,
                 photos  taken
                                                                                 - r, IJ 0

-------
k
c
E
r
s
r
i
c
 F
                                              A-2
Documentation:   1U/23/80 memo, Yin to Wi11iam Librizzi  (EPA-Dallas);
                 10/15/80 memo William Langley (EPA-Houston  Lab)  to
                 Librizzi transmitting analytical  results

March 23 - April 8. 1982

Inspector:        Imre Sekelyhidi  (FIT) personnel  and  other FIT employees
                 for EPA

Purpose:         Detailed on and off-site sampling of the site

Result:          3/23-24/82, 29 samples collected;
                 3/30-4/1/82, 6 domestic wells sampled
                 3/30-4/2/82, 10 monitoring wells  drilled, by Shepard
                 Testing and Engineering Co., Inc. of Norman, Oklahoma
                 at locations directed by Jerry Tnornhill (Hydrogeologist,
                 EPA-Ada" Branch)
                 soil borings and monitoring well  samples collected  from
                 each new monitoring well

August  16, 1982

Inspector:        Ecology 4 Environment (FIT) for EPA

Purpose:         Second  sampling round for the wells drilled by FIT
                 in March 1982

Result:          10 groundwater samples collected
                                                                                A r 0 0 0 1 s:»

-------
     i

     I

    M                                 APPENDIX  B

                         LIST  OF.POTENTIALLY  RESPONSIBLE PARTIES
    £                     IDENTIFIED FOR THE HARDAGE/CRINER SITE
   £
  c
  F
  I
 t
 E
 F
I

-------
 I
k
F
 71O   A  BETTER SANITATION
 711   ABLE  LIMT
-------
770  DOu&.E EAGi_E  REFINING LUBRICANTS,  INC.
771  DOVE 9 COMPOSITION
772  DO-' C^EMICA.  COMPANY
773  DOWNTOWN  ft! SPARK,  INCORPORATED
774  DRILLERS  EN3INE  * SUPPLY
775  DURA-CHROME  INDUSTRY
77£  EASON' 4 £»TT>-, WASTE HAULERS
777  EASO.N ENTERPRISES
77S  EA&ON OIL
773  E. I. DUPONT  DE NEMOURS
780  ELTEX CHEMICAL AND SUPPLY COMPANY
781  ENGINEERING  ENTERPRISES
782  EQUIPMENT REMEWfiu. COMPANY
783  ERNEST ST.  CLAIR
784  EUREKA TOO-  COMPANY
785  EVAN'S ELECTRIC  -SERVICE CENTER
78£  FAA AERONAUTICAL. CENTER
787  FIBERCAST CORPORATION
768  FINE CANDY COMPANY
783  FIRST NATIONAL MANAGEMENT CORPORATION
790  FLINT STEEL  CORPORATION
73:  FORD GLASS P.ANT
792  FOSTER FEED  ft SEED
733  FOSTER SEPTIC TANK CLEANING
794  FRED JONES MANUFACTURING
795  FREuirALJF  CORPORATION
796  GARDNER-DENVER COMPANY
737  GENERA. ELECTRIC
798  GENERA. ELECTRIC
793  GENERA. TIRE &  RUBBER
800  GEOPHYSICAL RESEARCH
801  GLlDDEN COATINGS ft RESINS COMPANY
602  GLO*-LITE DIVISION OF DUTCH BOY, INC.
803  GOODYEAR  TIRE ft  RUBBER COrPA>JY
804  GOVERNAIR CORPORATION
805  GROEVDYKE -RANSPOR", INCORPORATED
806  HALLIBURTON SERVICES
807  ROYAw M.  HARDAGE
808  HART  INDUSTRIAL  DISPOSAL
809  HATHAWAY  INDUSTRIES
810  HELfr  ft WEAVER
811  HERMETIC  SWITCH, INCORPORATED
812  HOLLEY CARBURETOR
813  INDUSTRIAL UNIFORM
814  INDUSTRIAL DISPOSAL SUPPLY, INCORPORATED
815  INTERNATIONAL CRYSTAL MANUFACTURING
816  JOHN  ZINK COMPANY
817  JONES-BLAIR PAINT COMPANY
818  KELSIY-HAYE?
819  KELT^ONICS CORPORATION
610  KERR  Me GEE,  PRESIDENT
821  KITB^-L  CHEMICAL COMPANY
823  KOBE   INCORPORATED
B23  KOCO  TV
824  LAWT  4  PLATING COMPANY
825  LEAc  JiEGLER, INCORPORATED
THIS  LIST F   RESENTS EPA'S  PRELIMINARY FINDINGS ON THE IDENTITIES OF
POTENTIALLY   ESPONSIBLE PARTIES.   INCLUSION ON THIS LIST DOES NOT       A PfUin I
CONSTITUTE   rlNAL DETEMINATION CONCERNING THE LIABILITY OF ANY PARTY   £ MJ U Ui
FOR THE HA2   D OR CONTAMINATION^; TH£ HARDAGE SITE

-------
 8£6  L.  A S. BEPRIN3
 817  LEEWQY P-OTCR  FR£I3-«T (C. L.  MOTOR FREIGHT)
 813  MAREMGNT CORPORATION
 830  MASTER MOTORS
 831  MATERIALS  RECOVERY ENTERPRISES
 822  MCDONNELL  DOUGLAS
V833  MCKESSON CHEMICAL COMPANY
'834  MANUFACTURING MERCURY MARINE
 835  METROPLEX  SANITATION
 82£  MIKE MON30NEY AERONAUTICAL
 837  MOBIL CHEMICAL COMPANY
 838  NAMEPLATES,  INCORPORATED
 839  NATIONAL CAN  CORPORATION
 840  NATIONAL PACKAGING COMPANY
 841  NELSON ELECTRIC  COMPANY
 84£  NEWSPAPER  PRINTING CORPORATION
 843  NICK_£S MACHINE  CORPORATION
 844  NORD»-A»1, INCORPORATED
 64*,  KiQ»T»-3pP WOR'_OW!DE PTRCRP^T S£°VICE  INC.
 64£  \U CHR'j.lE  wi_ATING
 647  O'BRIEN PAINT CORPORATION
 Q<8  OCCIDEN-ftw CHEMICAL
 649  OKLA-C'^p CITY DISPOSAL.
 650  OK.AHOr-A GAS  « E_EC~R!C
 851  0-S OS-RQ-.TU^I
 6£7  PCuE_'_ SAN:*AT:ON SERVICE
 8£8  PO^^	SERVICE CC'T^ANY
 8£9  PRE = 5VTER1A\  HOSPITAL.
 670,  PRES'r
 671  PRVOR CDU\DRY,
 675  PUBLIC SERVICE Cur^
 673  RA NBj CIRCUITS,  INCORPORATED
 S74  RANDY P_i_IO
 675  REAGENT CHE^ICPu & RESEARC-i,  INC.
 876  RED E-.L ^DTC^ FREIGHT
 877  ROCKW'.L INTERNCTICNAu
 678  RQCKW '.L INTERvJATICNA,.
 879  RCDCC
 660  ROTZX  :
 881  ST. A  -KCNY HOSPITAL
 382  S.»S.  BATING CQr?«\Y
 883  SANTA  -E RAILROAD

 THIS LIST RE  ESENTS  EPA'S PRELIMINARY FINDINGS ON THE IDENTITIES OF
 POTENTIALLY   SPONSIBlE PARTIES.  INCLUSION ON THIS  LIST DOES NOT
 CONSTITUTE  A  INAL DETEHINATION CONCERNING THE LIABILITY OF ANY PARTY
 FOR THE HA2A   OR  CONTAMINATION At -?riE YARDAGE SITE

-------
  837  SER*-ETEL,  INCORPORATED
  836  SERVICE PPIN7 "-AvuFACTuRINS COr=>A\Y
  883  St-AKLEE CORPORATION
  890  SrtE^lM-Wl.LlAM COMPANY
  831  SKY  WITC^
  8si  SCwVI.V rpNLFACTURlNG COMPA\Y,  IMC.
  832  SOONER  FORD
  834  SSCNER  OIL PA'CH SERVICES,
  835  SOUTHERN HILLS COUNTRY CLUB
  896  SUL.TH  PRAIRIE CONSTRUC-ION
  837  SOUTHU'SST ELECTRIC CC^PftNY
  838  SCJ^r-WSSTERiM STEEL ROLLI\G DOCS
  839  SOL'THWEST UMTED INDUSTRIES
  900  S^ER^Y  VICHER CO^PQVY
  901  S^AN! RAMSEY COMPANY,  INCORPORATED
  902  S'A.vDARD CHEMICAL COMPANY
  903  STAR MANUFACTURING COMPANY
  90A  STEELCRAFT, INCORPORATED
  905  STORI  PLASTICS,  INCORPORATED
  906  SL'E'-ETT ft ASSOCIATES
  907  SUN  GAS
  90S  TEXACO, INCORPORATED
  909  TEXAS  INSTRUMENTS
  910  TEX  PRODUCTS,  INCORPORATED
  9ii  THE  BUCKET SHOP,  INCORPORATED
  912  SAMUEL  RC&ERTS NOBLE FOUNDATION,  INC.
  913  THOMAS  & BETTS
  SI4  THCTPSCN HAYWA9D CHEMICAL COMPANY
  913  UNITED  S'ATES AIR FORCE
  916  TRIBONETICS COMPANY
  9l7  TOV  BROWN'S OPTICAL
  918  TOX
  919  TRIGS  DRILLING
  9iO  TUFTS  & SON OF OKLAHOMA
  921  UNflRCO  COMMERCIAL PRODUCT
  9ic:  UNI ROYAL TIRE CCMPANY
  9^:3  UNIT PARTS, BORG-UARNER COMPANY
  9iA  UNITED  FOAM
  325  UNITED  PuATING WORKS, INCORPORATED
  9£6  UNIVERSAL OIL PRODUCTS
  927  UNIVERSITY OF OKLAHOMA
  929  UNIVERSITY OF OKLAHOMA
  9£9  UNIV.  OF OKLAHOMA HEALTH  SCIENCE CENTER
  930  UNIVERSITY OF OKLAHOMA
  931  CCLONEL MARY FELTS
  922  U.S. CORPS OF ENGINEERS
  933  U.S. DEPARTMENT OF ENERGY
  934  U.S. PO-LUTION CONTROL
  935  U.S. POLLUTION COr TROL
  936  VETERANS ADMINIS""  3TION
  937  WAYNE  CIRCUIT
  938  WE_CU OIL  COMPANY
  939  WESTERN ELECTRIC t jvpp\Y
  940  WESTERN EXTRACT ri- ,UFACTURING
THIS LIST REPRESENTS ERA'S PRF BINARY FINDINGS ON THE IDENTITIES OF
POTENTIALLY RESPONSIBLE PARTIE .   INCLUSION ON THIS LIST  DOES NOT
CONSTITUTE A FINAL DETEMINATIC  CONCERNING THE LIABILITY  OF ANY PARTY
FOR THE HAZARD OR COMAT.NATK  AT THE HARDAGE SITE
                            <»   «*

-------
t
I
£
f
0
L
•P
  1
  r
941
94£
943
544
945
946
947
948
949
950
951
952
953
954
955
95S
957
958
959
960
961

963
9£4
965
966
967
968
969
570
971
972
573
974
975
97£
977
978
573
98O
981
              WJ:_SO\'
              W. J.  LP.'"BI.RTQN
              WC-VERINE PIPE
                *E5TIN3-TJSE  ELEC-RIC COR30RA-ION
                                 SERVICES
                         GRflPHICS
                U.S. S",AL_L BUSINESS
                SENERQL MOTORS
                SUPERIOR LIN-EN
                O.K. KEMORIfiL. HOSPITfiL
                JIM'S SEPTIC SERVICES
                O-« EMERGENCY PLUMBING
                RIVERSIDE INDUSTRIES
                UflSTE MflNOGEMENT
                IN-E.RNQTIONfli_ SYSTEM & CONTROL
                P.fi. INDUSTRJES-POLP3 MftNUFflCTURINiG
                flMAX, iNCORPOSflTED
                W'flSTE r^P.XflGEME\Tf  INCORPORATED
                S«\DTRft? SERVICE
                COSTER FEED t, SEED COMPANY
                JOC OIL EXPLORATION COMPANY,  INC.
                ALLIED PAIN^ CORPORATION
                BOSS-waRMER CORPORATION
                CLI=-TCO, INCORPORATED
                CODK PAINT AND VARNISH COMPANY
                CH£rlCAi_ LEA^AN TANK LINES,  INCORPORATED
                DIAMOND PAINT  COMPANY
                EXXON C.-:E*!lCft_ COMPANY
                W. R. GRACE 4 COMPANY
                GULF STATES  PAINT COMPANY
                RA^PH LOWE
                MQ3NA CORPORATION
                NPuCO CHEMICAL COMPANY
                T-fE O'BRIEN  CORPORATION
                P. P.G.  INDUSTRIES
                RELIANCE UNIVERSAL, INCORPORATED
                RO--M A\D HAAS  TEXAS, INCORPORATED
                WITCO CHEMICAL COMPANY
                TRIANGLE ENGINEERING COMPANY
          THIS LIST REPRESENTS ERA'S PRELIMINARY FINDINGS  * THE IDENTITIES OF
          POTENTIALLY RESPONSIBLE PARTIES.  INCLUSION ON ">  IS LIST DOES NOT
          CONSTITUTE A FINAL DETEMINATION CONCERNING THE I  ABILITY OF ANY PARTY
          FOR THE  HAZARD OR CONTAMINATIONS! THt HARDAGE 5  'E

-------
     I
    i
    I
    f
   c
                                      APPENDIX^  C
  L                  COMMUNITY
                       "
 c
 i
c

-------
I                -  COMMUNITY  RELATIONS RESPONSIVENESS  SUMMARY



b                 ON THE  SOURCE  CONTROL FEASIBILITY  STUDY




c

                        HARDAGE/CRINER SUPERFUND SITE

f?                      	
L                        MCCLAIN COUNTY. OKLAHOMA




f




S                              NOVEMBER 1986



L
L
 E
                                                                 AR0001?.'

-------
t
r.
 Js

 r
                                     C-2

              COMMUNITY  RELATIONS  RESPONSIVENESS  SUMMARY ON THE
                       SOURCE  CONTROL FEASIBILITY  STUDY

                             HARDAGE/CRINER  SITE
                           MCCLAIN COUNTY,  OKLAHOMA


  This  document  summarizes  public  comments  and  Environmental  Protection
  Agency (EPA)  responses to questions and concerns raised  during  the  public
  comment  period.   The responsiveness summary  Is  divided into four  sections:

  I.  Overview

 II.  Activities to illicit input  and address  concerns

III.  Summary of public comments and EPA response, and

 IV.  Remaining  concerns

-------
  c
  I
  c
  p
  r
  V.
f
  r

  F
   r
  I
  C
  I
                                   C-3

I.  OVERVIEW

At this time, the Environmental  Protection Agency (EPA)  is  presenting  its
response to comments on the Source Control Feasibility Study (FS)  prepared
for the Hardage/Criner site.  EPA has not yet selected its  preferred
remedy but has developed four remedial alternatives which it believes  to
be cost-effective plans, meeting all  applicable or relevant and  appropriate
Federal requirements for protection of public health and welfare and  the
environment.

This site is being managed through the EPA enforcement program.   As such,
EPA will make a decision on the "baseline" remedy which 1t  feels to be
acceptable.  EPA will then negotiate with private parties believed liable
for the site in an effort to achieve voluntary cleanup of the site.  In a
parallel manner, EPA is pursuing direct enforcement action  under Section
106 of the Comprehensive Environmental Response Compensation and Liability
Act of 1980 (CERCLA) and under Section 7003 of the Resource Conservation
and Recovery Act of  1976 as amended (RCRA).

When a remedy is proposed, EPA will be seeking public comment.  Only
after this comment period will EPA make it's final remedy selection.

-------
                                            C-4
B
E
C
f
s...
L
 c
 G
 I
 P
II.  BACKGROUND ON COMMUNITY INVOLVEMENT  AND  CONCERNS

Major Concerns and Issues

One of the major concerns  at the Hardage  (Criner)  hazardous waste site is
evidence from monitoring wells of migration of contaminants from the site
and contamination of residential  welfs  offsite.   The North Criner Creek
alluvium is. the primary aquifer of concern.

Deteriorating conditions at the site (i.e., continuous  seepage from the
pits, exposed barrels from the mound, etc.) and inadequate barriers to
retard migration, have given rise to concern  for potential surface and
groundwater contamination.

Activities to Elicit Public Input and Address Concerns

EPA has kept members of Congress, as well as other elected officials and
citizens informed of meetings, plans, and alternatives  under
consideration.  Elected officials and citizens were notified  prior to
start of the Remedial Investigation and Feasibility Study (RI/FS) process.

Ten families live in the immediate vicinity of the site.  Each  family was
interviewed by representatives of the Oklahoma State Department  of Health
(OSDH) and the EPA to ascertain their concerns and feelings  about the
site.  Primarily, these citizens' concerns centered around contamination
of the groundwater, which was originally discovered in the mid  1970s  by
the State of Oklahoma in onsite monitoring wells.  Since that time,  EPA
and OSDH have expended  considerable joint effort and resources  to determine
the nature and extent of the contamination.  Royal N.  Hardage,  owner and
operator of the site, was  sued by the United States in September 1980,
seeking investigation and clean up of the site.  Although the United
States established  it's case and won a partial judgement against Royal
Hardage, it was unsuccessful in obtaining site clean up, in  large part  due
to Mr. Hardage's  bankruptcy.  The U.S. Government filed suit in June 1986
against 36 companies believed to be responsible for public health  threats
posed by the  site,  seeking  performance of  remedial actions and further
studies as directed by  EPA  as well as reimbursement of all  Superfund
costs incurred, which  is more than $1.4  million.

A press release announcing  the end of the Feasibility Study, start of the
public comment  period,  and a  public meeting, was  issued by EPA on February
24, 1986.  Copies of  all  formal documents  concerning the site were placed
in five strategic repositories  for  the public  to review preparatory to
making their  comments.  Preceding the public meeting held on March 20,
1986,  EPA briefed the mayors  and  other city  officials  of both Chickasha,
Oklahoma  and  Purcell,  Oklahoma.   At  this briefing, EPA reviewed past
ac*. ions and  ongoing and future planned  site activities.

-------
                                   C-5

                  SUMMARY OF PUBLIC COMMENTS RECEIVED DURING
                     THE COMMENT PERIOD AND  EPA  RESPONSE


The public comment period on this FS was  from March  10 through April 15, 1986.
The FS was placed in repositories and provided to  the Hardage  Steering Committee
(HSC)  on February 25, the day after a press  release  announced  the end of
FS activities.  A March 20, 1986, public  meeting was attended  by approximately
seventy people, nine of whom made statements.  Fourteen sets of written comments
were received, consisting of over 200 pages.  These  comments were received
from:

 1)  B&F Engineering - for Weyerhauser
 2)  Gardere & Wynne - for L&S Bearings,  Rotex,  and  Tribonetics
 3) Yardage Steering Committee - a PRP group representing  135 parties,
     submitted their own comments as well as  those of three consulting firms
     retained by the HSC:  Dames & Moore, ERM-Southwest,  and MDK Consultants
 4)  Hildebrandt Tank Service
 5)  Hill 4 Roobins - representing U.S. Pollution  Control,  Inc.
 6)  The Hardy Horton Family
 7)  Hunton & Williams - representing Oklahoma Gas & Electric, comments
     endorsed by AT&T
 8}  Kerr McGee
 9)  League of Women Voters
10)  Rajeanna Mayo
11)  Oklahoma Center for Veterans Rights
12)  Pat Shepherd
13)  Thompson & Knight - representing Firestone
14)  Glenn Webb

Comments were also received during the public meeting  from the following
parties:  Glenn Webb, Kinnan Goleraan (for HSC),  Neal Garrett,  Tom  Smith,
Roberta .Olefield, Linda Wall, Faith Hurley, Ben  Kalas  (for tCWCL  news)  and
Mark Fox.

After analysis of the comments,  it was decided  to  organize the responsiveness
summary  into  seven sections, each  dealing with comments on a  specific
subject.  These seven categories are:

A)  Adequacy  of data,
B)  Operable  unit approach,
C)  Compliance with  the  NCP,
D)  Feasibility Study process,
E)  Opportunity for  public  participation,
F)  Recommendation for additional  study  or interim  remedial measures;  and
G)  Other comments

-------
f-
                                              C-6

                   A)  ADEQUACY OF EXISTING DATA ON THE  HARDAGE/CRINER SITE

             Several commenters suggested that existing  data  is  inadequate to fully
          characterize the site and develope a permanent and  cost effective remedy.
          Based on the volume of comments, it appears that either the consultants
          which these individuals employed are not fully aware of the amount of
          existing'data or that a substantial difference of opinion  exists between
          EPA and the Hardage Steering Committee (HSC) as to  what would constitute
          "adequate data".  EPAs "Guidance on Remedial  Investigation under CERCLA"
          Indicates in Section 7.2.3 that the extent of  Investigation should not be
          more than is "necessary and sufficient" to satisfy  site-specific objectives.
          Such objectives were defined early  by EPA and are  documented 1n the November
          1983 work plan prepared by CH^M Hill.  In the  case  of  a source  control
          action data must be, and in this case 1s, adequate  to  establish the degree
          of containment of the waste materials with reasonable  certainty.  The data
          must also allow development of feasible alternatives  for  remediation of
          the site, screening of these alternatives, and ultimately  selection of an
          appropriate cost-effective alternative for remedial  action.  As 1n any
          engineering or scientific study, 100% of the a-'ailable data could never be
          gathered.  As more and more is learned about the site, further  data gathering
          efforts will become less productive and of less value  in  providing new
          Information and more auplicative of previous  studies.  At  this  point, the
          Agency believes that sufficient knowledge of the source  areas  of waste and
          their current state of containment does exist  to allow decisions based on
          fact and sound engineering principles  (not on  assumptions  or  conjecture)
          to be made as to the appropriateness, feasibility,  and cost effectiveness
          of a range of source control remedial alternatives as  required by  the
          National Oil and Hazardous Substances Contingency Plan (NCP),  50  Fed.  Reg.
          47950, November 20, 1985.

          The level of data gathering suggested by some  commenters  indicates  confusion
          about the purpose of an FS and the preceding  investigative efforts.   The
          data gathered prior to remedy selection on a Superfund site  is not  intended
          to be so complete as to allow preparation of  detailed design  for each
          remedial alternative or even for the  remedy selected.   For example,  it
          would make no sense to collect the extensive  data required to design  four
          remedies when only one will be selected.  The data only  needs to be sufficient
          to determine the most  cost-effective  feasible remedy  protective of public
          health and welfare and the environment, not inconsistent with the NCP.

          Several  commenters pointed out what they  believed to  be data gaps in EPA's
          characterization of groundwater  hydraulics and  other  contamination outside
          the source areas.  Since  a separate RI/FS  is  planned  to specifically address
          this, the  second operable unit,  the  comments  are noted for future reference
          in development  of the  workplan  for the second operable unit (Management of
          Migration) RI/FS.
                                                                                 A;  UU

-------
                                       C-7

Response to specific questions and comments  regarding  the  adequacy of
data is provided below:

Comment:    Certain data indicate that  the bedrock may be  fairly impermeable
            and caple of preventing waste migration,  specifically: the
            yield of water from interceptor  wells installed by the operator
            are low, as  reported 1n the FS;  the packer permeability tests
            conducted by EPA contractors 1n  1984 Indicate  the permeability
            of bedrock is very low, less than  10'7 cm/sec.

Response:   It should be noted that the packer tests  Indicated permeabilities
            were less than 8 x 10*7 cm/sec.  Packer tests, when conducted
            properly and under favorable conditions, can provide an Indication
            of the permeability around  the well bore.  This does not
            necessarily  reflect overall  permeability of the bedrock or
            the ability  .of seepage to move  rapidly through joints.  The
            intact bedrock, especially  shales, at this site may have
            hydraulic conductivities on the  order of 10*7  cm/sec, or
            less.  However, EPA believes secondary permeability (fractures/
            joints) rather than porosity, characteristics  have allowed
            existing contaminant transport.  As stated in  the FS, the
            results of site packer permeability tests  would not have been
            significantly affected by thin,  occasional layers with hydraulic
            conductivities on the order of 10-1 to 10-3 cm/sec or an
            occasional tnin fracture.  This  statement  is based on estimations
            of the water loss through a thin pervious  layer within the
            packer test  sections.  Based on  the tests  conducted at the
            site, such a layer would not result in  sufficient water  loss
            during the test to result in an  overall  hydraulic conductivity
            of greater than 10*7 cm/sec, but would allow contaminant
            migration at relatively high velocities  in these  secondary
            channels.

            As discussed in the FS, difficulties are  inherent in monitoring
            groundwater  quality in a fractured aquifer.   The  absence of
            contamination in a single well,  for example, cannot be taken
            with any confidence to mean that contaminants  have  not  reached
            that general area.  This is apparent when  one  considers  the
            relatively minor area intersected  by a  well  bore  as compared
            to the area! and vertical extent of the  aquifer which  this
            well would be intended to monitor  (a six Inch  well  bore  with
            a twenty foot long screened-sampling-section might  be  placed
            hundreds to thousands of feet from other wells and  represent
            the only data on this section of the aquifer).  When  groundwater
            flow occurs through preferential channels, as  at Hardage,  the
                                                                          II (I II ! M .»

-------
V
E
r
te
F
t
c
                                       C-8

            interception of contaminated  flow pathways is largely reduced
            to a matter of chance.   The consistent  presence of contamination
            in the majority of wells  spaced over  a  wide area carries
            great weight in proving the aquifer to  be contaminated; and
            such a situation is correctly taken to  represent contamination
            of the entire area monitored  by the contaminated wells.

            The yield of the Hardage  Wells was reported Incorrectly 1n the FS as
            one barrel per day.  The yield, as stated by Royal Hardage in a 1980
            deposition was in fact  25 barrels per day for each of two wells.

Comment:    The groundwater contour map presented 1n the FS was developed
            with data from different  zones.  This Is not a correct
            procedure since deeper  bedrock may be hydraulically confined or
            vertical gradients may  exist, making  contours developed in this
            manner deceiving.

Response:   The Bison and Purcell Formations are  undifferentiated at the
            site, comprising a single unconfined  hydrogeologic unit; and
            present data indicates  the bedrock is hydraulically connected
            in the vertical direction and in  communication with the  alluvium.
            Therefore, the use of all water level measurements at the  site
            in preparing the ground-water contour map  presented  in the
            FS is only subject to errors  caused by  vertical gradients.
            Vertical gradients in ground-water  do exist  and do  influence
            the phreatic surface obtained from monitoring wells  installed
            to various depths.  During the investigation for  the  second
            operable unit, nested wells will  likely be  installed  to  further
            evaluate vertical gradients at the  site.  Based  on  this  information,
            a refined contour map may be developed.  Overall, this only  has an
            impact on the second (management  of migration)  operable  unit.

Comment:    Data from waste characterization  holes  drilled  through the
            sludge mound and main pit suggest that vertical  barriers to
            seepage exist beneath these areas.

Response:   Some data, when analyzed in a cursory manner, could indicate
            barriers to  seepage exist below source areas.  However,  the
            observed vertical migration of contaminants and their lateral
            spread  into  areas where  no other pathway could exist but
            through  groundwater transport overwhelmingly indicates that
            vertical barriers do not prevent susbstantial  releases of
            contaminants from  the  shallow to the deeper groundwater.

-------
                                                 C-9
  L
  E
  r
•  c
  to*fe
  r~

 I
i
  r

 •p
Ccxnment:    The vertical  extent  of contaminant migration has not been
            defined, neither have  the  vertical flow gradients that would
            induce such migration.  Such  information  is needed to fully
            characterize  site hydrogeology  and adequately develope and
            evaluate remedies.

Response:   Vertical migration of  contaminants through the bedrock to depths
            greater than  40 feet has been documented  to the east, southwest,
            and directly  beneath the source areas.  The Information obtained
            from the waste characterization (WT)  holes does Indicate vertical
            contaminant migration  beneath the source  areas, as discussed in
            the response  to latter comments.   In  addition, ground-water
            contamination found  in wells  EW-01, BH-01. BW-04 and GTW-03
            indicates contaminants in  ground water at deptn.  In each of
            these wells,  the well  screen  interval was placed beneath the
            phreatic surface measured  at  the well location, thus contam-
            ination found at these well locations are beneath the surface
            of the ground-water  table  and confirm vertical migration.   In
            addition, several wells and exploratory boring locations were
            installed adjacent to deeper  wells.   Although these were not
            specifically  intended  to constitute nested wells, Information
            obtained from these  locations indicates a gradient from shallow
            to deep groundwater.

Comment:    Piezometric levels of groundwater were measured 1n January
            and aren't representative  of  the entire year due to seasonal
            fluctuations.  This  limited data cannot indicate to what degree
            wastes in the source areas are  beneath the water table.

Response:   EPA agrees that the  levels may  represent  a low as compared
            to the rest of the year.  However,  relative levels and the
            shape of groundwater contours and  flow directions likely
            represent an annual  average and are consistent with those
            developed by earlier investigators  (Baker & Burns, 1980;  Kent,
            1982).  Seasonal fluctuations could be  better defined  in
            further studies.

Comment:    Geologic cross-sections were  not compiled.  Such  sections
            could aid in analyzing site geohydrology, and are a tool
            commonly used to perform such analyses.

Response:   The bedrock consists of shales, mudstones,  and  sandstones
            which are deposited in discontinous layers.   These  layers
            grade gradually  back and forth from one  rock  type to  another.
            Since this gradation occurs 1n three dimensions,  the  classical
            concept of a well defined sequence of horizontal  or consistently
            dipping beds which allows tracing Individual  layers  of the
  i
                                                                                   A
                                                                                   h
                                                                           U019

-------
                                           C-10
e
t

c
t
ft.
f-
\
L
            sequence from one borehole to the  next  Is not applicable.
            As a result of this graded lithology,  EPA could make only
            limited interpretations and would  have  had virtually no
            confidence in cross-sections compiled  with data from these
            or any other bedrock borings.  For this reason, cross-sections
            were not refined or published.

Comment:    The sitt may not be suitable for locating a  landfill cell in
            compliance with RCRA Part 264 regulations; and data 1s
            inadequate to make this determination.   This should have been
            considered before retaining the On-site Disposal  Alternative
            through final screening.

Response:   EPA believes the existing data Indicates that the site  1s
            suitable for placement of a RCRA vault; and  further study
            will be conducted for design should this alternative be
            selected.  Due to the widespread contamination on-site, low
            levels of residual contamination will  remain in the soils
            over which the landfill would be constructed. A questions
            was raised by one commenter as to the potential problems of
            monitoring for leaks from the landfill  cells, that is,  if
            contamination were seen in monitoring wells  questions  could
            arise as to whether it is coming from trace  landfill's  liner
            systems.  It is EPA belief that monitoring 1n a  possibly
            contaminated environment will not present  insurmountable
            technical problems since:  (1)  The vault will have an  interior
            detection system capable of detecting any  leaks  before they
            enter a contaminated zone;  (2)  the vault will  be above the
            groundwater table, eliminating potential up-flow of contam-
            inants  into the interior detection system;  (3)   regular
            monitoring will likely be  required for any remedy, and long
            term water quality trends  could be established, allowing
            significant  leaks from the exterior liner to be detected.
            The site  is  located over  several  thousand feet of sediments
            and is  not prone to earthquakes.  The  area of the site considered
            for locating a  landfill cell  is far above the 100 year flood
            and also  above  the  probable maximum flood.  Thus, the  site
            meets  the  requirements  set forth  in 40 CFR  Section 264.18.

 Comment:    The geometry of waste  fill  is  not defined.   Without such
            data,  "it  is  not possible  to adequately evaluate  any alternatives
            or determine either the Feaibility 1n  in-s.itu containment or
            the need  for excavation of the source  areas.
                                                                                  .< ~ o o o i

-------
E
I
B
I
I
C
E
r
                                   C-ll

Response:   The base of pits excavated during site operations  and later
            backfilled is defined by depositions  of the  operator Royal
            Hardage and confirmed by test holes  in these source areas.
            The borings show bedrock at  consistent elevations  of about
         '   1109 and 1093 feet mean sea  level (MSL) beneath  the
            main pit and sludge mound respectively, thus defining the
            base of the pits.  Magnetometer surveys have located substantial
            drum concentrations in the drum mound and  along  the west side
            of the main pit, also confirming early site  inspections and
            the Hardage depositions.

Comment:    A Quality Assurance plan was not prepared  1n accordance with
            the NCP.  As such, the accuracy of the data  and  the methods
            of data collection are questionable.

Response:   The Quality Assurance Project Plan (QAPP)  1s included as
            Appendix A to the May 1985 Data Summary Report.   This
            QAPP meets all the requirements of the NCP (1982 edition),
            including concurrence on the plan by  the Regional  QA officer.

Comment:    Sampling from three test holes in the sludge mound failed
            EPA's requirements for QA/QC.  This  lack of  data prevents EPA
            from making decisions on the disposition of the  materials
            since it can make no judgement on it's potential  threats.

Response:   After completion of the Feasibility Study, EPA's Houston  Lab was
            asked to review the data.  The principal problem was that lab
            reporting sheets indicated the units to be parts per million
            (ppm).  Summing the various  constituents indicated certain
            samples with a sum greater than a million ppm, Indicating
            an obvious error.  The Houston Lab's  review showed that the
            units were incorrectly reported and in reality should  have
            been parts per billion (ppb) rather  than ppm. This has
            corrected virtually all problems with thfsdata  set.
            The Houston Lab review is documented in an August 1986  letter
            from Bill Langley  (EPA-Houston) to Bob Davis (CH2M Hill-
            Dallas).

            Data also exists from previous sampling of the sludge  mound
            and in. some cases  for wastes disposed there.  In addition,
            the types of wastes disposed in the sludge mound are  known
            for the most part to be:  styrene tars; drummed aresenic  and
            cyanide; PCB contaminated equipment; and sludges from  oil
            recycling, the analysis of which showed extremely high levels
            of lead and phenol as well as over 50 ppm of PCBs; and a
            composite of all other wastes disposed  at the site as a
            result of clean-out of the main pit.  Samples taken in 1982

-------
C
I

L
r

E

B
                                   C-12

            from the surface  of the sludge mound indicated PCB-1260,
            lead, chromium, anthracene/phenanthrene, dichloropheonol', and
            other heavy metals and  synthetic organics.

Comment:    Poor well  drilling techniques may have resulted in cross-con-
            tamination of some monitoring wells and waste characterization
            holes; thus the results may not indicate deep contamination
            of soil and/on groundwater.

Responses:  Discussion 1s made regarding the contamination found in the
            waste characterization  holes (WT) beneath the source areas.
            It is suggested by the  commenter that only trace levels of
            contaminants were detected in bedrock samples beneath the
            pits and that they are  "probably associated with inadequate
            sampler decontamination... or laboratory contaminants".  As
            presented in the  Data Summary Report, EPA (1985), rinsate
            samples tak'en from the  sampler after decontamination did
            indicate a few contaminants  at parts per billion levels in
            addition to laboratory  contaminants.  The contention by some
            commenters is that bedrock contamination beneath source areas
            was mainly the result of  sampler and laboratory contamination;
            however, this is  not  substantiated  by overall sample analyses.
            Consistently, compounds other than  those found in the rinsate
            and laboratory blank  samples were  found in bedrock samples
            beneath the sources.   In  many instances, these compounds had
            concentrations in the parts  per million range (orders of
            magnitude higher  than that shown in blanks).  In addition, in
            several holes, compounds  were  found in the underlying bedrock
            samples which were not  found in samples taken within the
            source area nor  in  rinsate or  laboratory blank samples.
            These compounds  are  however  components of wastes known to
            have been disposed  at the site.   The obvious  conclusion  here
            is that the wastes  were not, as the commenter suggested,
            carried down the borehole by careless  sampling procedures,
            nor were the compounds  introducted  at the lab or at  any  time
            after the  samples were collected;  rather the  contaminants  are
            in fact, as EPA has  previously stated,  at depth beneath  the
            source  areas and represent the result of  actual waste migration
            vertically out of the waste pits  and into underlying sediments.
            In  waste  characterization hole (WT-006), the results  of the
            analysis of the composite sample comprised of samples  from
            28,33  and  38  feet showed very few volatile  compounds;  however,
            the  sample taken at 43 feet showed many more volatile  compounds
            present.   EPA believes this pattern of contamination is more
            indicative of vertical migration through  the bedrock along
            secondary  permeability features than the result of trace
                                                                                AR00019

-------
                                              C-13
I
F
r
r
[
            contamination on  sampling tools.  Well GTW-03 showed contamination
            in groundwater as did  the nearby BW-04 well; however, analysis
            of borings taken  from  GTW-03 showed no contamination of the
         -  overburden, thus  precluding contamination of this well during
            construction.

            (For further discussion, refer to a previous comment
            on vertical migration  of waste page C-8).

Comment:    No data exists to support EPA's contention that a hazard exists
            from air on the site.

Response:   EPA recently sent its  Emergency Response Branch (ERB) to the
            site for purposes other than air monitoring; however, this
            was also done while on-site, sampling with a photoionization
            unit showed readings less than 1 ppm  in air.   It has been
            observed that odors are much worse on-site in wet weather
            than dry wheather-when ERB  visited the site.  At this time,
            EPA must reply that it has  no data which indicates an air
            hazard from organic vapors  exists on-site at this time.  It
            is entirely possible however, that deteriorating site conditions
            could pose threats by this  exposure pathway.

Comment:    Use of area groundwater is  not adequately assessed to determine
            the need for remedial  actions.

Response:   Those groundwater supplies  with the potential to be  immediately
            affected have been considered.  Other supplies which  could
            ultimately be impacted as wastes migrate farther from the
            site will be assessed in detail during groundwater/off-site
            studies.

Comment:    The groundwater pathway of  contamination transport off-site
            has not been sufficiently  defined.   The potential for
            groundwater contamination  has been cited as  one factor
            requiring  remedial action,  yet  it's  potential  impact have  not
            been adequately assessed.

Response:   Pathways of groundwater contamination transport were only
            considered insofar as they indicate  a general  Inability of
            the bedrock to provide a  reasonable  degree  of  containment  of
            wastes in  the source areas.  The  presence of contamination in
            the alluvial aquifer of North Criner Creek  and the  route of
            transportation from the source  areas  are by and large irrelevant
            to the question  of the adequacy of barriers beneath these
                                                                                AR00019J

-------
                                              C-14
;
G
r
r

            source areas  several  thousand feet away.  EPA still believes
            that contamination  of this  aquifer has resulted from combined
            runoff and sub-surface transport.  The question of which
            pathway has contributed what to current contamination is of
            only academic importance, since significant subsurface migration
            has occurred  in this  and other directions, and contamination
            of the alluvium by  this method will continue or began to occur
            until the sources are exhausted.

Comment:    Source areas  may exist which have not yet been identified.
            If this is the case,  then the source control FS is incomplete.

Response:   Sufficient information on the operating history of the site
            is available from Oklahoma  State Department of Health (OSDH)
            inspections from 1972-1980  and from the operators depositions
            to confirm that Mr. Hardage made efforts to consolidate wastes
            in the main pit/drum  mound  and sludge mound.  Site samplings
            and recent inspections give no  reason to doubt the belief
            that the major concentrations of solids, sludges, and drummed
            wastes are located in the three principal  source areas
            addressed by EPA in its FS.

            Even if other major source  areas did exist, it would not
            preclude EPA from addressing  the drummond, main pit, and
            sludge mound as a single operable unit.  The NCP provides
            no such constrainst on what must be  included in an operable
            unit or on how many operable  units a site  may be divided
            into,

Comment:    Background quality of groundwater has not  been determined.
            Without knowledge of background concentrations of  chemicals
            or elements, it is impossible to determine if the  site  is
            contributing the compounds  or if the levels  are naturally
            elevated and unrelated to the site.

Response:   The  background  levels of synthetic  organics (such  as solvents)
            in this rural area is essentially  zero  with  the possible
            exception  of pesticides from agricultural  application,  and
            trace  levels of natural phenol  in  groundwater.  The  background
            levels of  inorganics will  be fully addressed in the  Management
            of Migration RI.

Comment:    The  extent of groundwater  contamination has not been adequately
            defined;  and no plume  has  been shown to emanate from the
            source areas.   As  a  result, it is premature to determine that
            groundwater  contamination  requires any remedial  action.
                                                                                  AR00019

-------
                                   C-15

Response:   Great difficulties exist in  monitoring  a  fractured aquifer
            where migration is along preferential channels, and where a
            heavily contaminated zone might lie within  a  few  feet of an
            apparently clean monitoring  well.   This characteristic makes
            the classical  concept of a contaminant  "plume" misleading and
            inappropriate  for describing migration  patterns at this site.
            In future studies, EPA will  undertake to  delineate the plume
            present in alluvium of North Criner Creek,  further define the
            lateral extent of groundwater contamination 1n the bedrock,
            and evaluate the potential for contaminants to migrate beneath
            stream drainage divides near the site.  Such investigative
            activities properly fall within the scope of the  second
            operable unit.

Comment:    Trends show water quality 1s Improving  with time.  This could
            Indicate that  the situation  1s not worsening, but rather that
            the groundwater system is recovering by natural processes.

Response:   The historica'l water quality data Is indicative of the presence
            of off-site contamination.  It is not felt  that trends in
            contaminant concentrations can be drawn from the  Information,
            since the samples were taken by various parties using widely
            varying sampling procedures.  Specifically, some  samples were
            obtained from  taps at the residences rather than  directly
            from the well, thus subjecting the water  to aeration during
            pumping and stripping of some volatiles.

            If off-site sampling results from various sources were comparable,
            the well with  the largest historical data base  (the  old
            Corley well),  does not show any trend whatsoever.  Contamination
            is similar to  the levels first seen in  late 1982, two years
            after the site closed.
                                                                        ^ 0 0 0  ! 9 I  3

-------
                                     C-16

B)  EPA's OPERABLE UNIT APPROACH TO THE  HARDAfiE/CRINER  SITE

Comments were received which questioned  the technical  and  legal justification
for EPA's decision to divide the site remediation  of groundwater/off-site
contamination as discrete and separable  problems.

EPA has addressed a substantial  number of NPL  sites, including  several in
Region 6 (Bayou Bonfuca, Gurley Pit, Vertac, Motco,  Highlands Acid  Pits,
Odessa Chromium I, and Odessa Chromium II), by dividing the  response  into
operable units.  These divisions are made based on technical information for
the site and the criteria presented in the NCP. As  noted  in the FS,  EPA
believed at the time the division was made, and continues  to believe, that a
substantial quantity of wastes remain in or near their  original location and
are not contained by adequate barriers and that a  remedy for source control
will be cost-effective and consistent with a premanent  overall  remedy for the
site, thus meeting criteria set forth in the NCP for operable unit  remedial
response.  The best enyineering judgement of the Remedial  Site  Project Officer
(RSPO), EPA Regional and Headquarters managers, and  EPA contractors was that
the vast majority of releases of hazardous substances  to the environment
could be abated by controlling these source areas  which comprise  less than
10% of the site area.  Strategies for cleanup of existing  groundwater contam-
ination or knowledge cf the necessity of such actions  is  not necessary  in
order to determine the best method of containing the wastes.  Source  control
and management of migration are in this  case clearly seperable; therefore,
further delays are unnecessary and would be inconsistent with provision of  a
timely response to a situation posing an imminent  and  substantial  endangerment
to public health and welfare and the environment.

Response is provided below to specific comments on the operable unit  approach
taken on the Hardage site.

Comment:  No technical justification exists for an operable  unit  approach  to
          the Hardage site; the decision to address the site in this  manner
          was driven by budgetary problems and previous delays  in completion
          of the FS.

Response: The technical justification for splitting the site into operable
          units  is strong, as discussed  above.  The questions  about  pathways
          of contaminant transport to offsite  alluvium and the extent of
           surface contamination  away  from the  source areas are not mandatory
          considerations in the question of source control and the existence
           of barriers to migration.   Since  all  proposed source control  alter-
           natives involve waste excavation  and  stabilization,  which  remedy is
           finally selected  is  not  a  concern ^n relation to the Management of
          Migration  operable  unit, therefore  delays to determine the ground-
           water/offsite  remedy  are unnecessary.   The criteria set  forth in
           the  NCP for  use  of  operable units has been met; and no strong
           justification  exists  for not  using  the  approach and further postponing
           cleanup  of the site.   The  comment • -;at  EPA  employed  operable units
           due  to budgetary  problems  is  unfour:ed; the  cost of the  DSR/FS
           project  was  slightly over  $800,000  less than is sometimes  spent or
           far  less  complicated  sites.
                                                                        :: 0 0 0 i

-------
                                               C-17
t
I
c
r
f
F
i.
r
Comment:  EPA has worked on the site  for three to five years; so expediting
          the remedy makes  no  sense at this point.  Further studies should
          be conducted and  a new FS prepared to address the site as a whole
          rather than as operable units.

Response:-EPA first inspected  the Hardage  site in July 1979; and a complaint
          was filed against the operator in September 1980 under Section 7003
          of RCRA.  While EPA  has been involved with the Hardage site for nearly
          seven years now,  active Superfund involvement did no begin until  1984.
          Field work was commenced by EPA  in July 1984 and the FS was released
          in February 1986, twenty months  later; the normal period of time in
          which EPA attempts to complete its investigations and FS on Superfund
          sites is eighteen months.   Delays on this site under Superfund have
          have not been exceptional;  and any delays which have occurred do
          not provide a justification for  further unnecessary delays.

Comment:  A cost effective  remedy can't be selected without knowing the final
          remedy for other  parts of the site.

Response: The situation at  Hardage is such that excavation and treatment of
          the waste piles and  pits is required (FS, pages 3-22 through 3-36).
          Therefore, the cost-effectiveness consideration is reduced to a
          comparison of various treatment  technologies and their relative
          feasibility, benefits, and  permanence.  Cost-effectiveness
          considerations are only to  be applied in comparisons between
          acceptable remedies  in accordance with  Section 300.68 of the NCP.

Comment:  A remedy for source  control should not  have to meet applicable or
          relevant and appropriate requirements since  it is not the  final
          remedy [(NCP, Section 300.68  (1)(5)(1)j.

Response: The remedies which EPA has  developed and evaluated, while  not
          addressing the entire site, are  permanent for the source control
          operable unit.  As such, response actions must be  in  accordance
          with these requirements just  as  if this remedy were for  all aspects
          of the site.  The passage  cited  in the  NCP  refers to  interim  remedial
          measures (such as a temporary cap) which may be  implemented while
          further study or planning  is  conducted  for  the permanent  remedy.

Comment:  The lack of data needed to  complete  a FS for the entire  site  prompted
          EPA to divide the site into operable units;  and  these same data
          gaps also plague the source control  FS. This prevents EPA from
          determining the  nature and  extent of the  threat  posed or evaluating
          proposed remedies.

Response: The "data gaps" are of a quite  different  nature  than  the commentor
          has implied.  Data indicates that releases  from  the site are
          uncontrolled; and knowledge to  site  conditions  Indicates the
          situation wil1 worsen.
                                                                             AR000191

-------
1
fi
I
E
C
0
I
 L
 E
 b
 P
 F
                           C-18
 Data  is  inadequate to determine the  appropriate remedy for  contaminant
 that  have already left the site or the extent of cleanup required
 for surface mixing areas which may remain contaminated.  However,
 it is EPAs opinion that the existing data is adequate to allow
 development of a source control Feasibility Study.  The blanket
 statement that these inadequacies plague the FS was not supported
-with  examples by the commentor.  And 1n the conduct of the  FS, EPA
 has certainly not felt Itself to be  "plagued" by this or any other
 lack  of  information.
                                                                                 AR00019H

-------
                                                C-19


               C) EPA COMPLIANCE WITH THE NATIONAL OIL AND HAZARDOUS SUBSTANCES
                         POLLUTION CONTINGENCY PLAN (NCP), 40 CFR PART 300*


            Several commenters questioned EPAs compliance with the NCP during conduct
            of response action at Hardage.  The comments ranged over many points of the
            NCP, but were centered on Subpart F - Hazardous Substances Response.

            General comments were that EPA had not adequately characterized the site;
            the screening of remedial alternatives was flawed or biased; an operable
            unit approach is not valid for Hardage; applicable or relevant and appropriate
            requirements for protection of public health or welfare or the envlronemnt
            were Incorrectly applied or should not have been applied at all;  EPA should
            have further considered waivers provided 1n the NCP and further evaluated
            those alternatives providing less than adequate protection of public health
            and welfare and the environment; and cost-effectiveness was not given adequate
            consideration.

            One important purpose served by the NCP is to provide consistency in appli-
            cation of CERCLA from one site to another and from one Regional program to
            another; and deviations from the NCP could possibly reduce this consistency.
            The current NCP was followed at all points through the FS process; and
            compliance with the NCP was a major factor in review of drafts of the FS.
            Where formal guidance documents and memos covering compliance with the NCP
            existed, the material was used.  As a result, EPA believes that the FS is
            entirely consistent with the NCP.

            Response to specific comments is given below.

            Comment:   EPAs failure to perform a formal RI is Inconsistent with the
                      NCP since: 1) the NCP does not suggest EPA may decide not to
L_                    conduct an RI when one is clearly appropriate; and 2} the data
                      collected does not serve the purpose of a RI.

[           Response:  The NCP directs that EPA shall "as appropriate" -erform an RI/FS.
                      This passage does not bind EOA to do an RI if  u  is not appropriate,
r                     EPA determined that a discrete RI was not appropriate in light
•                      of the already extensive data compiled on the  site.  The purpose
*-                    of an RI/FS, as explained in the nature and extent of the threat
                      presented by the  release and to evaluate proposed  remedies  (50  Fed
r                    Reg).  This purpose has been met.
I
*The NCP was promulgated, and is periodically revised, as required by CERCLA,
Section 105.  The NCP sets forth the approach to be used in implementing
CERCLA.  The most recent revision of the NCP was February 18, 1986 (50 Fed.
Reg. 47912-47968.

-------
                                     C-20

           On the other hand, EPA believes that  the  aggregate of prior
           studies and data on the site,  when  combined with its "Field
           Investigation and Data Summary Report", would  in fact constitute
           a record of substantial  equivalence to a  discrete RI.
           Therefore, the decision was made to move  directly to the FS.

           EPA must make decisions on how to proceed in cases such as
           this based on the best judgement of the RSPO and EPA managers,
           and it has acted in a manner not Inconsistent  with the NCP in
           deciding against the additional investment in  time and effort
           an RI would have involved.  The commenter does not elaborate on
           why a descrete RI was "clearly appropriate" on this site.

Comment;   The FS is not the functional equivalent of an  Environmental Impact
           Statement (EIS) as required by the  National Environmental  Policy
           Act of 1969 since the FS does  not contain a cost/benefit analysis.

Response:  Conduct of a cost-benefit analysis  is not required under CERCLA;
           this is confirmed by the Act's legislative history (136 Cong. Rec.
           §16427 (1980).)  Furthermore,  the public  comment period on the FS
           serves the opportunity for comments required under NEPA prior to
           expenditure of public funds.

Comment:  The five waivers applying to remedy  selection as set forth  in the
          NCP Section 300.68 (i)(5) should be  applied and a remedy selected
          which does not meet or exceed applicable or relevant and appropriate
          requirements tor protection of  public  health or welfare or  the
          environment, due to the high cost of remedial actions meeting these
          requirements or due to other circumstances set  out  in the NCP.

Response:  The five waivers are stated below along with the reasons they
           cannot be applied to the Hardage site.

1)  Remedy will  become part of a more comprehensive  remedy  -  This is  the
    final remedy for source control.

2)  Fund-Balancing - This test is normally applied where  there  is a  fund-
    financed response.  This is an enforcement lead  site; but there  is
    notniny to indicate fund balancing would be  involved  even if  this were
    a fund-financed
    response.

3)  Technical Inpracticality - Remedies meeting  requirements  are  technically
    feasible and can be implemented.

4)  Unacceptable Environmental  Impacts - This  1s not anticipated  since  the
    impacts of continued  release  out  weigh  those associated with remedial
    action.
                                                                       r 0 0 0 I \)

-------
                                                C-21
 I
 i
5)  Enforcement action where the fund is not available,  public desire for
    cleanup is strong, and  litigation would  probably  not  result  in" a better
    remedy - EPA believes that, if necessary, litigation  will produce the
    desired result and fund may be available.   It  should  be  noted  that
    Hardage/Criner j_s_ a National  Priority List (NPL)  site, so the  Superfund
    may be applied to remedy the site if the Agency chooses.

For the above reasons, the waivers will  not  be applied;  and  the  selected
emedy will comply with all  applicable or relevant  and appropriate  requirements.

Comment:  Consideration of incineration as a disposal  option violates the
          cost-effectiveness requirement of the NCP.

Response:  Incineration was  retained for consideration  since the  environ-
           mental benefits of organics destruction compared  to waste treatment
           and landfilling      are significant.  EPA believes consideration
           of waste destruction alternatives, such as incineration,  is  warranted
           and that the failure to consider waste  destruction would  be  contrary
           to the Agencies commitment to consider permanent  remedies including  .
           those which exceed applicable or relevant and appropriate requirements

Comment:   Scoping of  response actions was not conducted in accordance with
           Section 3U0.68(e) of the NCP.

Response:  EPA believes that it in  fact  has  properly considered all of the
           scoping factors  required by Section 300.68 of the current and
           former  NCP,  as appropriate.   Other  comments on compliance of the
           FS with the  NCP  are addressed  in  the following section.
I
r—
i
                                                                                  £ •-. 0

-------
fc
I
r
1
L
                                   C-22

                  D) The FEASIBILITY STUDY  (FS)  PROCESS

Comments were received to the effect that the  technology screening,
alternative development and screening, and  other components of the
Feasibility Study process were flawed due to a lack  of data or non-
compliance with the NCR.

While it is true that a lack of adequate data  could  bias the  results of
the FS by forcing the preparers into unwarranted assumptions, the discussion
provided in Section A of this summary regarding  what constitutes "adequate
data" is referenced.  And, as in response to comments 1n that previous
section, it is again stated that EPA believes  the data is adequate for
the purpose of a FS on Source Control.  The data may not be adequate for
detailed design; but that is not the present objective.  The  purpose of
this FS is merely to present analysis and discussion sufficient  for
selection of a permanent remedy for source  control.

Comment:

"(EPA) has rejected alternatives found to be protective of public health
and welfare and cost-effective at numerous  other Superfund sites".   This
commenter expressed the opinion that EPA had inappropriately  rejected  in-
place containment alternatives.  The commenter went  on to  cite  15 Superfund
sites in other Regions which they felt were in conflict with  the remedies
considered at Hardage.  These sites are:

Region tl                        Beacon Heights Lanfill, Connecticut;
                                 McKin County  (Landfill),  Maine;

Region #2                        Love Canal, New York;
                                 GEMS Landfill, New Jersey;
                                 Sinclair Refinery,  New York;
                                 Helen Kramer Landfill,  New Jersey

Region 13                        Heleva Landfill, Pennsylvania;
                                 Lackawana Refuse, Pennsylvania;
                                 Taylor Borough  Dump, Pennsylvania
                                 Douglasville Disposal, Pennsylvania

Region *4                        White House  Waste  Oil Pits, Florida

Region 15                        Wanconda Sand ft Gravel, Illinois
                                 New Lyme Landfill, Ohio

Region 110                       Ponders Corner, Washington
                                 South Tacoma Channel, Washington
 L

 E
 L
 f-          (No sites were  referenced  in Region 16, where Hardage/Criner 1s located.)
                                                                                    R 0 0 0 )

-------
  k
  C
   i
   I
   P
   P

4
                                   C-23

Response:

At this time, there are hundreds  of sites  on the  Superfund National
Priority List.  These sites present unique combinations  of factors
involving geology and hydrology,  as well as the age, quantity, and
chemistry of contaminants, among  other things.  For this and  other
reason, neither Congress nor EPA  has ever  taken the position  that
consistency between or among Superfund sites  is the measure of the
appropriateness of Superfund remedial  action at any given site.
The specific test upon which basis Superfund  remedial  actions are
judged is their consistency with  the NCP.   In numerous policy
promulgations, EPA has attempted  to further clarify those principles
which guide Superfund response efforts. The policy and  guidance
documents have changed during the past six years  of Superfund implemen-
tation; and they will continue to evolve and expand their scope in the
future, reflecting a predicted increase in the  body of knowledge concerning
contaminant chemistry, health and environmental effects, contaminant  fate
and transport, and waste control, treatment,  and  destruction  technology,
among other things.  As addressed elsewhere within  this  responsiveness
summary, as well as within the FS Itself,  EPA believes that  its remedial
action proposals are not inconsistent with the  NCP  as  discussed in the
previous section of this Responsiveness Summary.

For informational purposes, a brief summary of  characteristics, differences,
and similarities of the 15 indicated sites vis-a-vis the Hardage site is
presented below, along with a summary comparison  of their respective
remedies. As the information presented suggests,  the commentator's point
is at best overly simplistic and  factually inaccurate.  Review of  these
sites readily shows why capping may be an  acceptable component of  the
remedies (just as capping may be  included  in  the  second  operable unit at
Hardage).  The 15 sites referenced can generally be broken  into four
categories as discussed below:

Contaminated Municipal Landfills:

Beacons Heights, Heleva, Lackawana, Taylor Borough, New  Lyme, and  Wauconda
fall into this category.   Such sites are characterized by relatively
minor amounts of hazardous materials co-mingled with large  volumes of
municipal trash.  In this  type of  situation, wastes are of a far different
nature than the highly concentrated wastes at Hardage.

-------
I
c
f!
r
c
i.
E
E
L
C
I
f-
                                   C-24

Capping of wastes in-places was used  only  on two sites, Beacon and New
Lyme.  At New Lyme, little or no groundwater contamination has occured or
is likely due to hydrogeology.  At Beacon  Heights, contaminants are
dispersed and removal  is not feasible.  Two other sites, Lackawana and
Taylor, utilized capping only after partial waste removal.  In both cases,
well defined concentrations of drums  were  present and were removed; the
wastes capped were almost exclusively municipal in nature.  One site,
Wauconda, used a cap as an interim measure.  The purpose of the cap was
to control surface seepage to a stream.
                                     s
Waste. Oil Recycling/Refining Operations:

The McKin, Sinclair, Douglasville, White House, and South Tacoma sites fall
Into this category.  At such sites, the principal concerns are open pits
of liquid waste and waste spills.  Spills  represent dispersed waste for
which removal would rarely be a feasible option.  Pits are drained on
most such sites, resulting in almost  total  source removal.  At all five
sites noted above, emergency or remedial actions Included partial or
complete source removal followed by capping of contaminated soils in
former source areas.  This is analogous to the proposed removal of source
areas and possible capping of the former pits at Hardage.

Hazardous Waste Landfills:

The Love Canal, GEMS, and Helen Kramer  sites are in this category.
Hardage is similar to these sites only  in  the  respect  that similar waste
types were disposed.  At Helen Kramer and  Love Canal,  barriers to vertical
migration exist.  The layers make slurry wall  cut-off  feasible; sands
overlying the aquitards lend themselves to easy construction  of the wall
and simple and effective groundwater management.   At the GEMS site, no
shallow layer is present; however, a thick sand layer  allows  effective
groundwater management.   In addition, drummed  liquids  are  not present  as
they are at Hardage.

Presented below is a brief summary of site characteristics, differences
and similarities between the  site and Hardage.

Beacon Heights Landfill    Region II      1203  on  NPL

Beacon Falls, Connecticut

0  municipal/industrial waste landfill  operated 1920-78

0   little drummed  or other waste  remains; most waste was  burned  as 1t was
    received  and only Its  residues  remain

0   groundwater  is  contaminated  in fractured bedrock

Remedy-Upgrade  cap; groundwater decisions deferred
                                                                                  AROOOIO:

-------
  i
  f
  E
  t
  §
  fe
  C
  t
  I
4
                                                C-25
             Comparison to Hardage:
                Similarities - fractured bedrock underlies  both  sites
                Differences - The majority of waste once disposed at  Beacon  Heights is
                              municipal.  Little waste remains  in its  original  location,
                              most has been burned or already released to the  groundwater
                              system.
Remedial Elements:
The sites are not comparable since a well-defined  source 1s  present  at
Hardage; and the sources at Beacon Heights are dispersed, making  source
control inappropriate.
McKin County (landfill)    Region #1       133 on  NPL
Gray, Haine
0  waste oil recycling site operated 1n the late 1970s
0  soils are heavily contaminated by spills of solvents
0  all surface tanks and drums have been removed;
Remedy:
Soil contaminated above the clean-up level (11,000 cubic yards) will be
excavated; soil will be aerated and the off-gas burned; capping will be
over areas below the clean-up level
Comparison to Hardage:
   Similarities - solvents contaminate both sites
   Differences - McKin was a  recycling as  opposed to disposal facility;
                 no drummed wastes  remain  on-site
Consistency with removal at Hardage:
   In  both cases wastes will  be excavated  and properly disposed.  McKin
   is  farther along in  remedial process  (cleanup  levels  selected already)
   but the  remedies appear entirely consistent.

-------
C
f
L
 L
 F
                                              C-26
           GEMS Landfill              Region #2      112 on  NPL
           Gloucester Township, New Jersey
           0  Industrial waste landfill operated from 1970 to 1974
           0  solid and liquid waste was mixed in pits;  few  or no drums were disposed
fc
           e  6 million cubic yards of contaminated fill  present
           0  150 feet of permeable sands underlie site, making  groundwater recovery
              feasibile
           Remedy:
           Cap site; pump and treat groundwater to remove leachate  and lower water
r         table below wastes
           Comparison to Hardage:
              Similarities - similar wastes present
              Differences - No drums are in the fill  at GEMS.  Geology makes groundwater
                            management a feasible and effective method for intercepting
                            seepage near the source,  unlike at Hardage.
           Remedial Elements:
           At Hardage, drummed liquids are present in the fill and the underlying
           interbeded and fractured bedrock does not lend itself to groundwater
           management.  These complicating factors make the remedy used  at GEMS
           inappropriate for Hardage.
           Helen Kramer Landfill      Region #2      14 on NPL
           Mantua  Township, New  Jersey
           0  industrial waste landfill operated from 1970 to 1980
           0  2 million cubic yards of waste
           e  all  types of waste are present including drummed wastes
           c  the  site  is  underlain by a  shallow  sand  aquifer and a deeper aquitard.
                                                                                  M-OIM)!0

-------
I
                                   C-27
Remedy:
Cap the fill; Install  a slurry wall  upgradient  and  a  collection trench
downgradient, both with their base tied into the  aqultard.
Comparison to Hardage:
   Similarities - drummed and bulk wastes 1n Industrial  type  fill
   Differences   Containment of the wastes directly beneath the site  1s
                 feasible due to the presence of  a  barrier to vertical
                 migration at Helen Kramer.
Remedial Elements:
The lack of a barrier to vertical migration at  Hardage prevents effective
containment 1n place as 1s possible at Helen Kramer.
Ponders Corner             Region
Tacoma, Washington
*  dry cleaner dumped sludges on the companies property
0  solvents have contaminated groundwater
8  sludge piles (sources) were previously removed by the State  of  Washington
Remedy:
A1r stripping towers are 1n-place on municipal wells and are serving the
dual purposes of groundwater collection and treatment; limited  excavation
with off-site is disposal planned for the most heavily contaminated  soils.
Comparison to Hardage:
   Similarities - solvent contaminated groundwater
   Differences - Little of the source remains, most 1s dispersed Into
                 groundwater system or previously removed; collection
                 and treatment of groundwater 1s feasible;
Remedial Elements:
The contaminant source at Ponders Corner has dispersed from It's original
location, making source control Inappropriate.  For this reason the
sites are not comparable.

-------
i
E-
r
j
(
f-
                                  C-28

Love Canal                  Region  #2      #136 on NPL

Niagra Falls,  New York

0  abandoned canal  was  backfilled  with industrial wastes and closed  in
   tons of wastes including drums  are in the fill

0  low-level contamination  is  present in several media

0  canal  excavated in sand  overlying plastic clay and till; situation allows
   containment in place

Remedy:

Cap was upgraded; slurry  walls installed, tied into clay layer; groundwater
collection and on-site treatment  system in-place; further studies are
under way due to concern  over  vertical migration of leachate to bedrock
and the possible inadequacy of in-situ containment.

Comparison to Hardage:-

   Similarites - drums  in fill; similar contaminants

   Differences - low-level  contamination outside the canal as compared to
                 Hardage; containment is feasible due to geology

Remedial  Elements:

The shallow clay layer beneath Love Canal is thought to allow wastes to be
contained beneath their original  location;  however, the adequacy of this l
is still  being evaluated.  The lack of such a layer at Hardage prevents
consideration of such containment.


Sinclair Refinery          Region #2             1117 on NPL

Wellsville, New  York

0  former refinery operation with two  on-site landfills; soil was contaminated
   by  spills

0  fill contains principally bulk wastes

e  small fill area  (2 acres and 10-15 feet thick)  1s adjacent  to a  river  and
   Is  being eroded; larger fill has a clay liner

*  groundwater  contamination  is present but believed to result from spills
   on  the site  rather than releases from the landfills
                                                                                AROOOi

-------
  I
  c
  c
  c
,t
  I
                                            C-29
          Remedy:
          Excavate the small fill areas, consolidate with  the  larger landfills and cap;
          groundwater will  be addressed in other operable  units
          Comparison to Hardage:
            Similarities - Removal is part of the EPA remedy  on both sites.
            Differences -  Groundwater contamination 1s primarily from spills and
                           already dispersed contaminants  rather than the fill or
                           concentrated source areas.
          Remedial Elements:
          The  landfills at  Sinclair are not leaking; at Hardage they are.  For this
          reason, source control at Sinclair only needs to stabilize wastes against
  r        flooding and  erosion.   If necessary, groundwater management  would  likely
          be  feasible  in the river aquifer.
          Heleva  Landfill            Region 13      1162 on NPL
          North  Whitehall  Township, Pennsylvania
          0   low level solvents coming!ed with sanitary waste
          6   "source"  of off-site contamination appears to be contaminated  groundwater
             beneath the landfill itself
          0   little  or  no drummed waste is believed present
I
          Comparison to Hardage:
terf
             Similarities - Similar contaminants observed off-site
B
             Differences -  Little free liquid appears present 1n the fill  at
                           Heleva, while a large source 1s present at Hardage.
r                           Since contaminants have generally left the Heleva  fill,
(                           Source control is not appropriate
w
          Remedy:
          Capping  with  groundwater pumping and treatment
          Remedial Elements:
            At Heleva, the "source" of contamination has generally entered the
  ,          groundwater system.  This type of situation  1s best remedied by removing
  f~~        the contaminated groundwater.   Since  a  large volume of free liquids Is
  1          not present in the fill at Helelva, capping  was  assumed adequate to
            prevent further contamination  of the  groundwater.  Such a system is not
  i          adequate at Hardage due to the physical differences between the sites
  1          noted above.
                                                                                   P00019

-------
                                   C-30
lackawana Refuse           Region 13             1453 on NPL
Old Forge Borough, Pennsylvania
0  sa'nltary landfill  operated through 1976; fill  Mas 1n old coal  pits
•  10,000 drums dumped 1n one pit over 4 months 1n 1976
*  geology makes the groundwater contamination threat to the public m1m1nal
Remedy:
Remove all drums from pit and dispose off-site; cap former pit area
Comparison to Hardage:
   Similarities - drummed wastes present; removal 1s part of the EPA remedy
   Differences - groundwater contamination 1s less extensive than at Hardage
Remedial Elements:
Hazardous materials will be removed from both sites; at Lackawana the
municipal wastes will be capped. The remedies are consistent since, in
both cases, the wastes will be excavated and properly disposed.
Taylor Borough Dump        Region 3              1635 on NPL
Taylor Borough, Pennsylvania
0  municipal/industrial landfill
0  site consists of six distinct areas with varying degrees of contamination
0  drums are present in some parts of the  fill
0  the decision on groundwater issues has  been deferred to  a later operable
   unit
Remedy:
Remove all drums; cap areas of surface contamination  and municipal fill
Comparison to  Hardage:
   Similarities - drummed  waste  present;  removal  1s  part of the  EPA remedy
   Differences  -  surface  contamination  will  be  capped  at  Taylor,  while
                  its disposition  at  Hardage  has not  yet been  determined.
                                                                      A \- 0 0 0 i

-------
c
r
c
                                   C-31

Remedial Elements:

Concentrated areas of source materials have been or will  be removed  on
both sites.  The hazardous wastes at Hardage will be dealt with in the
same general manner as were similar wastes at Taylor.  For this reason,
the remedies at both sites appears consistent.

Wauconda Sand I Gravel           Region #5      1126 on NPL

Wauconda, Illinois

* municipal landfill operated from 1940s to 1979

* less than 3X of the 5 million cubic yards of waste 1s hazardous/Industrial

"fill is in abandoned 'sand and gravel pit

0 groundwater contamination is negligible

Remedy:

Interim remedy is a cap to prevent surface seepage Into a nearby stream.
Further study will be done on the groundwater operable unit.

Comparison to Hardage:

   Similarities - Both sites have been split into operable units.

   Differences - Hardage accepted almost exclusively Industrial and
                 hazardous wastes; Wauconda has only a very small percentage
                 of this type waste.  Groundwater has been contaminated
                 at Hardage, unlike Wanconda.
f*          Remedial Elements:

            Factors making waste excavation necessary at Hardage are not present at

L
Wauconda.  Specifically, Hardage contains a large volume of hazardous
substances which have been and continue to be released and extensive
groundwater contamination is not a driving force behind remedial action
at Wauconda.  Source control and the cap are prlnlcpally directed at
controlling surface seepage.  Such differences make comparison of the
sites difficult.

New Lyme Landfill                Region 15       1626 on NPL

Ashtabula County, Ohio

0  municipal landfill which accepted industrial waste

0  little 1s known on volume or types of waste

•  little groundwater contamination

0  if necessary, groundwater management 1s probably feasible

-------
                                   C-32
0  groundwater discharge (up-flow) controls local  hydrogeology  and
   protects groundwater below fill
Remedy:
Construction of a RCRA compliant cap over the fill.
Comparison to Hardage:
   Similarities - Relatively small amounts of some wastes disposed  at
                  Hardage are present at New lyme
   Oiffences - Little groundwater contamination compared to Hardage site.
               No significant amounts of Industrial waste was disposed at
               New Lyme.
Remedial Elements:
The groundwater flow system at New Lyme acts to prevent seepage out of
the landfill.  Since such a natural system is present, groundwater  1s  not
extensively contaminated and a large liquid/sludge source of contaminants  1s
not present, source control 1s relatively straightforward. If necessary,
groundwater management would likely be feasible unlike at Hardage.   The
sites are generally not comparable.
White House Waste Oil Pits       Region |4      1132 on NPL
Hhitehouse, Florida
0  waste oil recycling facility
0  Emergency Response cleaned out pits and capped the pit areas
0  groundwater contamination present
Remedy:
Repair caps; install slurry wall and pump and treat groundwater.
Comparison to Hardage:
   Similarities - groundwater contamination; waste removal was  Integral
                  to remedy
   Differences - waste source areas  have  already  been  removed  at White
                  House; and geology  makes  groundwater  management feasible
R  Tiedial Elements:
I  : site remedies are quite similar.  In  both cases, the  source areas  were
r  ioved.   The capping and  slurry  wall  at  White  House  are similar to
IT*  :sures which could be considered,  for  the  second operable  unit after
t  ' sources  have  been removed.

-------
                                  C-33
Douglasville Disposal       Region  #3      1103 on NPL
Douglasville, Pennsylvania
0  oil recycling facility;
0  site is located  adjacent to  river and subject to flooding
0  in previous actions,  drums were removed; lagoons cleaned out and sludges
   land fanned on-site;  spills  have contaminated site
0  groundwater and  soils are contaminated
0  river alluvium underlies site;  slurry walls are feasibile to cut off
   lateral flows
Remedy:
Cap site; and build flood control  levee; a slurry wall may be part of the
groundwater remedy
Comparison to Hardage:
   Similarity - groundwater and soil contaminated
   Differences - former  oil recycling  facility;  source areas have already
                 been  removed;  groundwater management is feasible
Remedial Elements:
Source areas have been or will  be  removed on both sites; the remedies
are consistent in that  similar  wastes  are handled in  a similar manner-
(i.e. excavate and  treat hazardous wastes).
South Tacoma Channel (Commencement Bay)        Region  #10    #11 on NPL
Tacoma, Washington
0  waste oil recycling  and  tank clean-out facility operated in 1960s
0  filter cake containing tetrachloroethylene  (PCE) was used as fill  soil
0  contaminants from spills are dispersed in the soil and  underlying
   aquifer
Remedy:
Excavate hot spots  of  CE and  install  vapor  extraction points  in  the
ground.  Continue air-stripping water in a  nearby  municipal well.
Comparison to Hardage:
   Similarites - groun'water contamination
   Difference - sourc •  of  contamination is spill  areas  which  have already
                 dispe  sed  into the groundwater system;  groundwater
                 manag  ent  is  feasible.
                                                                       AFOUUilK!

-------
                                               C-34
k
L

E
r
f


L

C
Remedial Elements:

   At South Tacoma, the waste is dispersed  and  source control is not
   applicable.  The cap in this case has  a  very specific and  limited
   purpose, to allow solvent vapor extraction.

Other comments related to the Feasibility Study process are as follows.

Comment:  "A rotary kiln incinerator has  the  potential for Incinerating
          the site wastes, but Its feasibility  has not seen demonstrated."
          Process upset could result In the emission of dioxins and
          furans.  The mixture of wastes  present would pose problems over
          and above those associated with a costant waste stream.

Response: Incineration of the specific mixture  of wastes present at Hardage
          has not yet been demonstrated.However, the types  of waste
          present have generally been destroyed In this manner.  The
          problems cited contribute to the  cost of over $300  million
          estimated for incineration alternatives.  Bench tests and
          possibly pilot studies would be essential to the remedial
          design as would be emissions testing.

          EPA considers Incineration on virtually all Superfund sites
          where organic contamination exists.  It 1s never stated  that
          the construction and operation  of an  Incinerator would be
          simple, only that at this point it  appears feasible, and warrant
          consideration due to It's benefits.

Comment:  Incinerator ash may be eligible for de-listing as  a RCRA
          hazardous waste on a site specific  basis.

Response: If treatment of ash removes the characteristics of  a hazardous
          waste (primarilly EP Toxicity  1n  this case), the ash may be
          eligible for delistlng.  Based  on a rlsk-assesment, delisting
          could be considered after it  Is demonstrated that  the above
          criteria could be met.

Comment:  On-site incineration provides  no time advantage over off-site
          incineration, since the off-site treatment won't take  10 years
          as assumed 1n the FS.

Response: The 10 year figure was based  on current backlogs for existing
          units.  While capacity may increase 1n the  future  demand will
          also Increase.  Reduction of  the 10 year figure  Is not warranted
          at this time.

Comment;  Groundwater recovery  (pumping) would be feasible  1n the  bedrock
          and should not have been el minated from consideration.

Response: The commenter has ignored t'e extensive data collected Indicating
           fracture  zones, uniformly  1 v yield,  and the fact that wells
          pumping from fractured  bedr ck will produce a small cone of
          depression.  For  this  reaso , withdrawl wells would have to be
          closely spaced and  very  dee , creating an large quantity of
                                                                                AhUOUll

-------
   c
   I
   r
   £-
 if
   c
   r
   L
  f
                                                     C-35
          Although the system would  still allow substantial releases as
          described in the FS, groundwater recovery by withdrawl from a
          collection trench system as described 1n Alternatives 4 and 5,
       -  was deemed feasible.

Comment:   Technologies for reuse  or  recycling of waste should have been
          considered, particularly  "Basic Extraction Solvent Technology"
          (BEST) as employed on the  Savanaha site 1n Georgia.

Response; As noted 1n the FS, the extreme variability of the wastes at
          Hardage virtually eliminates the use of known reuse/recycle
          alternatives.  Solvents Extraction Is quite useful where wastes
          are homogenous liquids. However, the waste stream at Hardage
          1s highly varied and much  Is a high density sludge.  The application
          of solvent extraction to high sol Ids content wastes will only
          result 1n a minimal reduction 1n volume to be dealt with.
          Reuse/recycle treatments will be considered for certain wastes
          if technologies become  apparent 01 are developed.

Comment:   If the site had been operated after 1980 then capping would have
          been an acceptable measure for closure under RCRA.  Yet EPA
          states that capping 1s  not viable enough to even consider as an
          acceptable remedy.

Response: The site was not operated  after November 1980, partially due
          to the operators Inability to meet new requirements for hazardous
          waste land disposal facilities which went Into effect at that
          time.  Facilities which legally operated after November 1980
          presumably were better  managed with at least some safeguards
          built in. In some cases this may make capping adequate for
          containing the wastes.  The Hardage facility had no such safeguards
          and bedrock has been found to provide Inadequate barriers;
          therefore, simple closure  1n-place Is not acceptable.  (Note:
          The commenter went on to argue against the application of other
          provisions of RCRA as applicable or relevant and appropriate
          requirements).

Comment:   The factors used to screen all alternatives and eliminate several
          were Inconsistent with  those dictated by the NCR.  If the
          appropriate factors had been applied, then the FS night have
          reached different conclusions.

Response: Section 300.68(g) of the NCP states that, "Three broad criteria
          shall, as appropriate,  be  used 1n the Initial  .creening of
          alternatives." The three "broad" factors to be used are cost,
          acceptable engineering  practice, and effect1vp'.-ss.  The ranking
          factors used 1n screening  of alternatives 1n t e FS were:
4
                                                                                   AROOOJH

-------
G
r
S
L
F
i
r
                                   C-36

          reliability, implementability,  safety,  environmental, institutid^B
          and cost.  The factors considered fell  in  the  broad  categories  ^^
          listed in the NCP and are consistent  with  the  screening factors
          listed in EPA's FS guidance.

Comment:  The alternatives which should have been retained  for further
          consideration in the FS were Alternatives:  *3-Capping. 05-capping
          with perimeter drains, |7-0n-s1te landfill,  and 110  Off-site
          disposal.

Response: The commenter suggest considering two alternatives which EPA
          rejected (13-Capping and 15- Capping  with  Perimeter  Drains).
          Documentation for rejection of  alternatives  numbered 3 and  5  is
          provided In the FS on page 3-27,28 and  3-29,30 respectively.
          The principal reason for rejecting these alternatives 1s their
          inability to significantly reduce the^release  of  leachate Into
          the groundwater system.

          The commenter also suggest rejecting  two alternatives which EPA
          retained (18- On-Site Incineration and  Disposal and  19-On-Site
          Incineration/Offsite Disposal).  EPA  disagrees with  the commentert
          Congress, in the 1984 ammendments to  RCRA, has determined that
          land disposal of soils contaminated with certain  wastes, Including
          many solvents, should be banned, although  a two year extension
          is provided for CERCLA response actions.  Prior to such
          some facilities may be hesitant to accept  a large volume of
          waste with bans pending on it.   Destruction of organics is  an
          enormous benefit, in that the destroyed compounds will  no
          longer be capable of posing threats to  the public or environment.

          EPA is specifically directed by the NCP to consider alternatives
          exceeding requirements.  Incineration falls Into  this  category
          and the benefits may prove commensurate with the  costs; therefore
          consideration of Incineration 1s appropriate.

Comment:  The adverse effects of waste excavation were not  considered.
          These may pose unacceptable environmental  Impacts and  be  grounds
          for selecting an in-sltu alternative not meeting  requirements.

Response; The hazards associated with excavating the site were recognized
          in the FS.  It 1s believed that releases to all «ed1a except
          air, can be readily controlled.  Releases to air  will  be  minimized
          by dust control measures, handling and excavation techniques
          aimed at minimizing the volume of waste 1n the open at any
          given time, and possibly placement of a temporary structure
          over the waste excavation.  A1r aonltorlng will  be performed
          and the potential threat to adjacent residents will be monitored
          throughout operations as will be the potential need for their
          Immediate evacuation.  Threats to workers are  ?al; but this 1s
          the reason for extensive safety precautions an  health monitoring.

-------
                                                   C-37
            Comment:  A  risk assesment should have been performed  on  the  Hardage site.

            Response: A  preliminary Public Health Assessment has been prepared and
                     Mill be supplemented as further data 1s obtained.

            Comment:  The detailed developement and analysis of alternatives presented
                     1n the FS 1s Inadequate and may not allow selection of the most
                     appropriate remedy from the four finalists.

            Response: Section 300.63(h)(2) of the NCP sets out the factors to be
                     Included, as appropriate, 1n the detailed analysis.  These
                     factors are: 1) refinement and specification of alternatives;
                     2} detailed cost estimate; 3) engineering evaluation of effect-
                     Ivness, 1mplementabil1ty, and constructability; 4)  assessment
                     of effectiveness of remedy 1n meeting remedial  objectives;
                     5) analysis of alternate technologies; 6) analysis  of costs of
                     adverse Impacts and their mitigation.

                     These factors were addressed, as appropriate, and alternatives
                     were refined in sufficient detail to allow selection of an
                     appropriate remedy.  The development 1s not  to  a design level,
                     but it is not intended to be.

            Comment:  The findings of fact and conclusions of law  arrived 1n  1982 by
                     the U.S. District Court in Oklahoma City concerning the site
                     should not have beer, relied upon to d eve lope a  remedy.

            Response: The findings and conclusions were not used  1n the FS 1n the
                     manner that the commenter suggested was the  case.   The  facts
                     which led to development of these findings  and  conclusions have
                     for the most part been supported by data obtained since  1982,
                     and have therefore been properly considered, along  with other
                     relevant investigative and factual Information  concerning the
                     site.  EPA did not mean to Imply that these  findings and
                     conclusions had to be taken at face value,  as they  certainly
                     were not during the FS but were re-examined  as  appropriate.
F
                                                                              £-0001935

-------
                                              C-38
6

E
E
F
E
L
[

                 E) OPPORTUNITY FOR PUBLIC PARTICIPATION

Comments were received which Indicate some parties feel  EPA should  have
made a "greater effort to Involve those parties potentially liable for  the
site 1n development of the FS and should have allowed more extensive
comments on the FS.  The NCP as well as current EPA policy 1s cited as
support for this argument.

Where appropriate, EPA will generally Involve PRPs 1n studies and development
of response actions.  The reasons for this are numerous, not the least of
which 1s the previous experience of the Agency which suggests that  those
parties most directly Involved 1n studies and most familiar with the
rationale for EPA decisions will be most willing to participate 1n voluntary
clean up.  At the Harda.ge/CHner site, the enforcement policy documents
which recommend PRP participation 1n the RI/FS were appropriate, had not
been promulgated by EPA at the time the FS was committed.  In addition,  a
PRP search had not yet been completed.  For this reason, PRPs were not
Involved from the outset.  In December 1984, an Initial  group of nearly
300 PRPs was notified of their potential liability on the site.  Since
that time, approximately 135 parties have formed the Hardage Steering
Committee (HSC).

EPA has met with HSC often since its formation.  Final documents have
been provided in a timely manner; and over 200 requests for documents  and
information have been answered in writing under the Freedom of Information
Act since early 1985.  Communication has been frequent between both the
technical and legal staffs and have been as open as the enforcement nature
of the site allows.

Comment:  EPA refused to afford HSC the opportunity to participate 1n
          development of the RI/FS.  These actions violated EPAs own
          guidelines including the March 20, 1984 **mo from Lee Thorns,
          "Participation of PRPs in development of .U/FS under CERCLA
          and the draft CERCLA Settlement Policy".

Response: The March 20, 1984 memo Indicates that PRPs may be allowed,  to
          where appropriate, to conduct the RI/FS under an EPA approved
          scope of work and under a formalized agreement such as a Consent
          Decree.  This policy  1n no way requires or  Indicates that EPA
          will abandon on-going studies merely to allow PRP conduct of
          an RI/FS.  Regional experience has been that when conduct of
          an RI/FS has been switched  from one EPA contractor to another,
          significant delays result.   Even  greater delays would be expected
          in transfer of the RI/FS  to  a party out-side the Agency.  In
          addition, previous activities of  HSC have  not  indicated  that
          an FS could have been completed by them more  rapidly than by
          EPA.  The Hardage Steering  Committee had not  been  organized at
          the time the FS  was  Initiated in  January  1984;  aside  from this
          purley  practical  reason  for not allowing  HSC  to  conduct  an
          RI/FS,  other factors  enter  Into this  situation.
                                                                                A: 0 0 0 19

-------
                                   C-39

          The draft "CERCLA Settlement Policy" referenced  to  1n  the
          comment was issued October 4, 1985, and  does  not constitute  EPA
          policy. Instead, EPA's settlement policy is contained  in the
          Interim CERCLA Settlement Policy as set  forth in the Federal
          Register on January 5, 1986.  At this time the FS was  in its
          later stages of development.

Comment:   Insufficient time was allowed for comment on  the FS.   The  document
          is extensive and detailed, thus a comment period substantially
          longer than the minimum three weeks required  by  the NCP would
          have been appropriate.

Response: There was a 5 week comment period on the FS;  this Included a 15
          day extension requested by HSC.  addition, the FS was  placed 1n
          repositories and provided to the HSC two weeks before  the
          formal comment period began, providing a total of approximately
          seven weeks" for Interested parties to review  and comment on the
          FS.  While EPA and Its contractor did spend approximately  eight
          months compiling the 200 page FS, all data from which  this FS
          was compiled has been available to the public from  the time EPA
          began the FS in mid-1985.

Comment:   EPA must afford the HSC an opportunity to finalize  and present
          its own response plan before selecting a remedy.

Response: EPA has repeatedly been told that HSC Is or will be preparing
          some type of response plan.  Unfortunantely this work  has  never
          been produced, forcing EPA Into the conclusion that such  work
          may not be done even 1f EPA were to wait.  Any response plan
          submitted to EPA will be considered, as have all proposals.
          documents, advice, and comments In the past, provided  such a
          plan is received in a timely fashion.  EPA guidlines and
          regulations do not, as the commenter states, require EPA to
          afford the HSC an opportunity to finalize and present  this plan.

-------
                                            C-40
L
I
I
r
t
F)  RECOMMENDATION FOR  ADDITIONAL STUDY AND/OR INITIAL REMEDIAL  MEASURES

The commenters have proposed  a  general plan for additional studies which
in their.opinion,  should  be conducted prior to selection of a remedy  for
the site.   These studies  would  supplement EPA work and be aimed at developing
a RI/FS for both operable units  of the site.

These commenters have also proposed  to conduct initial measures aimed at
site stabilization.  These measures  would mainly included:

  1)  fencing of the entire property,

  2)  construction of a temporary cap and collection system for surface
      seeps

  3)  monitoring of drinking  water  supplies and construction of alternate
      water supplies if necessary.

EPA feels that some of the study items suggested by the commenters are
appropriate.  Some of the additional study  items and  are  being considered
by EPA as necessary components  of studies for the  second  operable unit.
EPA sees no purpose in rethinking its previous decision to split the site
into operable units.

The proposed "removal" actions  have also been considered  by EPA.  An EPA
site assessment team was dispatched to the  site  in June 1986 and, following
the teams report, action will be taken  as necessary.
•r
 L
 L
                                                                               AR000193

-------
                                               C-41
L
r
t
c
•

L
p
L
f
f
             G)   OTHER  COMMENTS
Comment:  Has EPA considered incineration  and disposal of the entire
          waste volume at Hardage  through  underground  injection. In this
          area, formations below 3000 feet often  show  caverns which take
          enormous amounts of fluids  and cannot be  plugged by addition of
          sealant or bridging materials.

Response: Two problems would be presented  by disposing wastes 1n the
          fashion suggested:  the  actual ability  to do this and the legal
          and permitting constraints.

          The physical problems with  Injection would be significant.  The
          volume of waste considered  for disposal Is roughly 179,000
          cubic yards, or 36 million  gallons, of  soils and sludge.  To
          allow Injection, the waste  would have to  be  slurrled with
          water, forming a volume  In  exess of 100 million gallons of
          waste slurry.  While this volume could  theoretically be Injected
          in the space of a few weeks, the enormous volume of solids
          would likely clog cavities  rapidly, requiring construction of
          several wells over an area  significantly  larger than the site.

          Considering the type of waste found at  Hardage, 1t 1s unlikely
          such injection wells would  be permitted by EPA or the State of
          Oklahoma.

Comment:  EPA should select the On-site Incineration/Off-Site Disposal
          Alternative.  This 1s the only way to achieve a permanent
          remedy for the Hardage site.  Several commentors expressed this
          sentiment; one felt that the On-s1te  Incineration and disposal
          plan would also be adequate.

Response: EPA favors an on-site disposal plan due to several factors Including:
          1)  the volume of waste present;
          2)  hazards associated with off-site  transport;
          3)  questionable availability of an off-site disposal facility; and
          4)  the fact that an off-site plan merely shifts hazards to
              another location and population.

          EPA will give appropriate consideration to the  Incineration
          options.  The decision will be available  for public comment
          before being finalized as a Record of Decision.

Comment:  Incinceration should not be selected  since  100% destruction of
          compounds such as 2,3,7,8 - tetrachlorodlbenzo  -p-diox1n  (TCOD)
          cannot be achieved.  In addition, partlculates  should be sampled
          prior to emmission to the air.
                                                                               AROOOIO

-------
                                               C-42
  k
  I
  c
  r
  r
'•I
  I
!L
-.P
Response: 100% destruction  of  anything can never be achieved.  Incinerator
          testing by EPA  in Missouri has in all cases achieved  greater
          than 99.9999% destruction of TCDD and has effectively destroyed
        . even hard to  burn compounds such as carbon tetrachloride.   EPA
          sets limits on  particulate emissions by incinerators  and these
          solids  would  be analyzed in test burns and periodically throughout
          the operations.

Comment:   The waste could be disposed as follows:

             seperate water/solids by settling
             dispose the  water 1n an injection well
             heat the solids to dry them
             seal the solids in a plastic/cement "casket" and bury
             dispose the  dirt  in another manner

          This plan is, in  some ways, similar to the on-site disposal option,
          The waste treatment  and handling techniques have not yet  been
          finalized. These comments  and plans will be considered  in the
          design  phase  of remedial planning.

Comment;   Do provisions exist  for indemnifying contractors involved  in
          remedial  work on  Superfund sites from possible future liability
          under CERCLA  for  hazards arising from the site at some time
          after this work is completed.

Response: Under current law, the contractor cannot be indemnified even
          for actions carried  out at EPAs direction.  Provisions for
          contractor indemnification will likely be in revised CERCLA
          statutes being  developed Congress.

Comment:   EPA should have more thoroughly investigated deep bedrock to
          identify existing contamination and  evaluate the potential for
          contamination in  the future.  This needs to be done since it is
          contamination of deeper  ground water and transport through that
          flow regime which has the  potential  to affect populations not
          in the  immediate vicinity  on  the site.

Response: One of  the key  purposes  of the Management of Migration RI/FS
          will be to define the long-term  potential  for migration along
          pathways such as the deeper groundwater.  Three wells  drilled
          on-site to depths of 200 feet or more showed no contaminants at
          detectable leve's.

-------
          APPENDIX G

DETAILED COST ESTIMATE FOR THE
       SELECTED REMEDY

-------
                          iUMINARY
                             .-MftQAGE INXfiTRIAL -ASTE SITE
                             CSI.€S, GKUIHGflA
                             EPA *)€DY WITH EXCAVATION OPTION
ITE»
         UNIT    UNIT     EXTENDED
QUANTITY  £ASUflE   COST       COST
Section 3 - DETAILED SEJCDY DESCRIPTION
  3.1  Source ftooval I Control
  3.:.1 Liquids ftesoval and Disposal
      DfllH SMOVAL
       rquapaent
         Traexed Excavator (1-CY)
         Tracked Excavator (2-CY)
         vacuum Truck
         Forklift (2 units)
         Backnoe (2 units)
         Duap Trucks (6 units)
         Flat Bed Truck (2 units)
         Pickup Truck (2 units)
       Support Equipeant
       Air Emissions Control
        Material
       Labor
        Formn (Ifihr/day i Z wn)
        Equip Optrators (16 hr/day
           x 6 vn)
        Truck Drivtrs (16 hr/day x
           6 MA)
        Labortr (16hr/day x 2 «n)
        Industrial Hygient Tfdi
           (16 hr/day x 2 «n)
        HMlth/Safrty Equipwvt
           - Class A
           - Class B
     Total
16
16
16
32
32
96
32
32
1
32
366
11,776
35,328
35,328
35,32*
MB
MS
KB
MOS
KB
MB
MB
MB
LS
MB
DAYS
MS
MS
MB
HRS
«S,650
8,000
11,040
1,517
2,725
3,050
755
510
112, 000
1,000
300
35,00
31.50
25.60
24.60
WO, 400
128,000
176,640
48,544
87,200
292,800
24,160
16,320
112,000
32,000
110,400
412,160
1,112,832
904,397
869,069
11,776   HRS
                  32.00    376,832
  7,360
  8,832
       MHW
       m-m
135.00
 75.00
     OM9O HASTE STASINB/COeOLIOATiaN AEA
      Sitt Grading                2,047
      Building
        Concrttt Slab               185
        On* Opvninf Am             1
        toof Cove-ing             10,000
        Stum ATMS                   1
        Conwyor Racks              210
      Equiownt                      1
         CY
993,600
662,400
                                  16,449,754
                 M.96    f 1,965
CY
LS
SF
LS
LF
LS
180
14,000
5.15
30,000
48
182,800
33,300
14,000
51,500
30,000
10,080
182,800

-------
                                    HWMflE INDUSTRIAL KftSTE SITE
                                    CRINER,  CXLflHOMfl
                                    EPA R0CDY rflTH EICflVATIQN OPTION
ITffl
           UNIT      'KIT      DTEMDED
QUANTITY  ICASURE    OBT        COST
Section 3 - DETAILED SEJEDY DESCRIPTION
  3.1   Source ftewval t Control
  3.1.1  Liquids  taoval and Disposal
       ORUWED WASTE STflBIIS/CONSOLIDATION AREA - Continued
         .-oreean
         Teen - Level 1  (16 ftrs)
         Teen - Level 1  (8 hrs)
         Health/Safety Eouipecnt
       Maintenance
       Disposal of Organic*
         Transportation (150 trips)
         Incineration
       Disposal of Oruvs
       Closure

     Total

     REMOTE STORAGE AREA
       Rente Storage Area

3.1.4  Soil Vaoor Extraction
     SOIL VAPOR EXTRACTION
       Sitem*
       Buildine*
         Blower Building.
       Eauipemt
         Blower - 9,000cfs
         Tank - 2,OOOgaJ
         Pipmq
         Monitoring  Probes
a, ass
a,a£
4,416
i
i
75,000
300,000
1
1
HRS
HRS
HRS
LS
IS
HI
OILS
LS
LS
35.00
£4.60
34.60
289,800
11,400
3.75
4.04
1,300
39,300
309,120
217,267
108,634
289,800
11,400
281,250
1,212,000
1,300
39,200
                                            1    LS
                    f 19,900     t!9,900
1
2,160
5
1
1
100
LS
SF
£fl
EA
LS
EA
«10,000

41,000
6,000

900
«10,000
90,000
206,000
6,000
600,000
90,000
                                                                                2,733,616
19,900

-------
                               ILIMINARY
                                     INDUSTRIAL 4STE SITE
                              CHINES, OKLflhOMfl
                              cPfl REMEDY WITH EXCAVATION OPTION
ITEM
         UNIT     JUT
QUANTITY MEASUfE   COST
                                                         EXTENDED
                                                          COST
Section 3 - DETAILED REMEDY DESCRIPTION
  3. :  Sourct Rnoval I Control
  3.2.4 Soil Vaoor Extraction
      SOIL VAPOR EXTRACTION - Continued

       SUBTOTAL - Know Costs Only
         General Conditions »        » of SUBTOTAL
         Finishes t                1* of SUBTOTflL
         ElKtrical t             1« of SUBTOTflL
         Instrumentation I Controls I 5* of SUBTOTflL
         yard Piping t             5* of SUBTOTflL
       SUBTOTflL - Pwctntag* Costs Only « 26* of SUBTOTAL
       SUBTOTAL - Known and Ptrctntao* Costs Only
         Mobilization I M of SUBTOTAL - Knows + *
         Pilot Studin                 1   IS      550,000
         SVE Start-tip Strncw           1   LS      30,000

     Subtotal
                                                        «1,001, 000
                                                           67,635
                                                           13,527
                                                          135,270
                                                           67,635
                                                           67,635

                                                        tl, 352, 703
                                                           67,635
                                                          550,000
                                                           30,000
                                                                   12,000,338
     AIR TREPJWff
       Sitawrh
       Concrete
         Slab on Grade
       Eqvipemt
         LP Tank - 18,000pl
         BlOMer
         ThenHl Oxidation Unit

       SUBTOTAL - Know Costs Only
         Seneril Conditions 9
         Electrical t
         Instrumentation I Controls
         Yard Piping            t
       SUBTOTAL - Percentage Costs Only - 70* of SUBTOTflL
       SUBTOTflL - Known and Percentage Costs Only

     Subtotal
1 LS
267 CY
1 Efl
£ Eft
1 EA

of SUBTOTflL
of SUBTOTAL
of SUBTOTAL
of ^UBTOTAL
. tftt ~* anrnr

200
16,000
38,500
612,000




ra
»10,000
53,400
16,000
77,000
612,000
1768,400
54,886
109,771
54,886
109,771
                                                        11,097,714
                                                                    1,097,714

-------
                                   tfftOAGE INDUSTRIAL 4STE SITE
                                   CSifCR,  QKLAHOW
                                   EPfl REKEDY WITH EXCAVATION  OPTION
ITB
          UNIT      WIT      EXTENDED
QUANTITY  NEASUflE    COST        COST
Section 3 - DETAILED REfflJY DESCRIPTION
  3.1  Source Reeoval t Control
  3.1.5  Adjacent Source flMoval
       REWVAL Cf ADJACENT WASTES
         North ^ond Area
          Excavation
          Pltctmnt under cap
          Onn rtMdiation
            Transport
            Incineration
        West Pond Area
          Exc/Haul/Placee*nt
        U trench
          Exc/HMl/Planecnt
        V trench
          Exc/Ha«l/Placeamt
        SU trend)
      East Far* Pond tt  (HSC)
      East Far* Pond 12  
      RDOY TOTAL
5,800
5,300
730
lt4flB
63,200
2,704
11,015
1,275
1
1
CY
cy
Ml
GAL
CY
CY
CY
CY
IS
15
MS. 15
11.77
3.75
4.04
17.23
16.54
16.54
16.54
171,000
317,000
«26i,B70
6B,266
2,813
5,999
1, 092.72S
44,724
183,346
21,089
171,000
317,000
                                         12,168,834

-------
                                          1MXJSTRIAL HASTE  SITE
                                  CR!:€R,  OKLAHOMA
                                  EPfl REJCDV «ITH EXCAVATION OPTION
ITEM

Strtion 3 - DETAILED (BOY DESCRIPTION
  3.1   Sourct ftawval  t Control
  11. S Sourer Area doping
       SITE OPS
        Storautcr Btra
        Sttmticn Basin
        Clean Soil Placwnt
        Ptriamnt Cap
          RMovt Mill
          AHOVW Pipiiq f Mills
          Scale a*ass
          DiK 6'
          24' Clay
          Will  OPE
          12* Sand
          Strip Drains
          Colliction  Plot
          Scotntili
          12*  Granular tetmal
          GMtntilt
          18*  Nativt Soil
          6* Topsoil
          GNMtrii
                    Covtr
 UNIT      UNIT
MEASUfE    COST
COST
4,000
1
5,800
400
400
33.10
72,957
59,160
88,777
29,580
1
1
88,737
29,580
88,777
44,369
14,790
58,670
88,737
LF
LS
CCY
EA
Eft
A£
SY
CCY
SY
CCY
LS
LS
SY
CCY
SY
CCY
CCY
LS
LS
«4.00
10,000
14.84
100.00
20.00
50.00
0.19
14.84
7.20
15.84
38,830.00
1,680.00
1.20
25.00
1.20
5.13
14.81
1.55
0.33
«6,000
10,000
86,072
40,000
8,000
1,655
13,862
877,934
638,906
468,547
38,830
1,680
106,484
739,500
106,484
227,613
219,040
90,939
31,058
      flEHEDY TOTAL
          «3,722,605

-------
ITEM
                                   HMMQE 1MXJSTRIAL WASTE SIT
                                   MINER, OKLPHOW
                                   EPA (OEDY WITH EXCflVflTION OPTION
          UNIT     WIT      EXTENDED
QUANTITY  MEASURE   COST        COST
Section 3 - DETAILED KKDY DESCRIPTION
  3.2  SroundMatir Extraction t Treatsint
  3.2.1  BroundMter Trtncnts
       SROUNWATER COLLECTION TRETOES - Continued
         V-SHAPED TRENCH
     Soil Excavation
     Borehole dia  13') 77 holts
     Borenole dia<2"> 836 holes
     flesove Rita
     Irwrt tnd pipt* (77 holts
        x 33.5 FT/holt)
     Plan coant gravtl
     Plact wdiw sand
     Plan soil limr
     fttplan M^gradt to gradt
     yithdraMl Mils (6 *tdi)
       Pwps
       ElKtric cabin
       Ttflon disctMryi  howt
         to piping
     Colltction LiflM
       Trtncti HIM
       Lattrtl to Plant
       Trtncniiq coit  (Excava-
         tion ft Btcfcfill)
     Pu? control Itrs
     Withdrawal wlls
       P.L Scrnn <6 iich dia)
       P.L Casing (6 indi dia)
       Protective casinq
      Count Sand Backfill
      Low Ptr» Soil Backfill
      Labor
    Observation Wells  (71 eacfl)
      P.E. Screen (4  inch dia
         x 10 If /mil)
      P.E. Casing (4  inch dia
         x SO LF/Mll)
      Gravel Fill  (71 wlls)
      Lou Oer> Soil Backfill
      Protective  casing
      Lricr

Sub Subtotal
                                        330    LF
  2,900
    100

  3,000
      1

     60
    303
      6
     77
      5
      1
    710

  3,386
    970
     36
     71
      1
                                               LF
                                               LF

                                               LF
                                               LS

                                               FT
                                               LF
                                               EA
                                               CY
                                               CY
                                               LS
                                               LF
                                               CY
                                               CY
                                               EA
                                               LS
161.06
35.00
15.92
16.30
2.48
1,265.00
2.00
3.00
5.83
9.89
1.73
3,000
20.00
16.50
250.00
15.92
20.00
6,780.00
6.10
4.17
15.92
20.00
150.00
8,970.00
663,526
22,135
156,318
10,445
28,272
7,590
6,660
990
16,907
989
5,250
5,000
1,200
5,000
1,300
1,226
100
6,780
4,331
14,954
15,442
1,120
10,650
8,970
                                                                 3,037,3%

-------
                                    HARMGE  IttUSTRIflL i*STI SITE
                                    C3INER,  QKUVOft
                                    EPfl SS€DY Him EJCflVflTIQN OPTION
ITS!
           UNIT
QUANTITY  CASUflE
JUT
COST
                                                                  EXTENDED
                                                                    COST
Section 3 - DETAILED RENEOY DESW1PTICN
  3.2  SroundMater Extraction t Treateent
  3.2.1  Sroundiiater Trencnes
       SROWOMflTER COLLECTION TRENCHES - Continued
         SX7MEST TRENCH
           Mobilization
           Soil Excavation
           Borenole dia (3')- 17 ea
           Borehole dia (2*)- 176 ea
           Reeovw Rita
           Insert end pipes (17 t 30*
           Plan coarse gravtl
           Plan eediui sand
           Plan soil liner
           Replace subgrade to grade
           Withdrawal Mils
            Puapt
            Electric cables
            Teflon discharge hoses
               to piping
          Collection Lines
            Trench Lines
            Lateral to Plant
            Trenching Cost (Excava-
               tion t Backfill)
          MMep control lers
          In-line PUB? to transport
             over 8* line
          VithdraMl Mils
            P.E.  Screen (6 inch  dia)
            P.E.  Casing (6 inch  dia)
            Protective casing
            Course Sand Fill
            LOM Per* Soil Backfill
            Labo-
          Observation Mils  (15 etch)
            P.E.    -een<4* x  10'/ea)
            P.E.  &»ing<4* x  27*/ea)
            C Sand Fill (15 Mils)
            LOM P~i Soil Backfill
            Prott  ivt casing
            Labor

      Sub Subtota.
1
2,400
486
5,051
599
510
134
1,008
134
2,400
2
760
60
600
1,200
1,800
1
1
20
74
2
13
2
1
150
400
101
12
IS
1
LS
CY
FT
FT
CY
FT
CY
CY
CY
CY
Eft
LF
LF
LF
LF
LF
LS
LS
FT
LF
EA
CY
CY
LS
LF
LF
CY
CY
EA
LS
•20,000
2.07
66.40
36.95
20.25
161.05
35.00
15.92
16.50
2.48
1265.00
2.00
100
5.83
9.89
1.75
5,000.00
5,000.00
20.00
16.50
250.00
1192
20.00
1,620.00
6.10
4.17
15.92
20.00
150.00
2,000.00
«20,000
4,968
32,403
186,634
12,130
82,136
4,690
16,047
2,211
5,932
2,530
1,520
180
3,498
11,868
3,150
5,000
5,000
400
1,221
500
207
40
1,620
915
1,668
1,608
240
2,250
2,000
                                                                     387,618

-------
                                             1NARY
                               -*WDflfiE INDUSTRIAL HASTE SITE
                               GAINER,  OXWHCH1
                               EPfl 30€DY yiTH EJtCflVflTION OPTION
ITB
                                         UNIT
                                QUftNTITY  CASUAE
WIT
COST
EXTEWED
  COST
 3. i^-
Sert ion 3 - DETAILED R£!QY DESCRIPTION
  3.2  SroundMttr Extract ion I Treitnnt
        GroundiMter Trtncnes
      SROUMWATER COLLECTION TROCHES - Continued
        WSCEUA-COUS ITEMS
         Reserve Pi«ps, cables,
             Discharge hows -           1    LS
         Gtmrators                    5    Efl

      Suft SuMotai

      SufltotaJ
 3.2.2  Brountetv- TrtatMit
     6MUOMTER TREATKNT
       Effluwit Pent
        Excavation
        Bacfcfill
        Spillway
        Utir 3* high
       fecyclt Lint
        V HDPEPip*
       Equipon*
        Tanks - lS,000|tJ
        Nimn - 1 Hp
        P«p» - Oiaphrag* l/2hp
        Oil/Watir Siparators
        Oil Pivp
        Solids PIMP
        Paduat TrMtHnt Systa
        LIM Fttd Systaa
        Stttlfr - Sacond
             Filter
        Effluntt Pum
        Effluent Tank
        Acid Uttering Systoi
        SackMsO Puae
        Badniasft Storage Tank
        Decant Pu»p
        Sludge Puw - BW
        Stripper Puip
                                                   5,000     25,000
                                                            2fl,oao
                                                                   13,453,294
                                  5,000    CY
                                  5,000    CY
                                     1    LS
                                     1    LS

                                  1,000    LF
    t3
     5
 10,000
  5,000

    15
  115,000
   25,000
   10,000
    5,000

   15,000
1
4
2
2
2
2
EflCH
EACH
EACH
EACH
EACH
EACH
130,000
12,000
600
10,000
1,200
7, WO
130,000
46,000
1,200
20,000
2,400
15,600
2
3
6
3
2
2
2
2
2
1
1
2
2
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
EACH
83,000
4,630
20,000
1,200
28,000
600
25,000
4,630
000
20,000
600
1,200
800
170,000
13,890
120,000
3,600
36,000
1,200
50,000
9,260
1,600
20,000
600
2,400
1,600

-------
                                         IMXjSTRIflL «flSTE SITE
                                  C.9L*€R, OXLfrtitf)
                                  EPA  REMEDV KITH EXCflVfiTIQN OPTION
ITEM
          UNIT     JUT     EXTENDED
QUANTITY  KASURE    COST       COST
Stction 3 - DETAILED (BOY DESCRIPTION
  3.2 GroundMitir Extraction  & Tr»at«nt
  3.2.2  SrouHjwater Trcatnnt
      SROUMDMflTER TSEATWff - Continued
        equipment - Continued
          flir Strippers
          Air BlOMr
          SAC - Mittr
          Str. Effl.  Pun
          Sludgt Storage Tank
          Sludgt Hixtr
          Fiitw Prtw
          Filter Pmc Pwp
          Tarti - 0. E.
          0. E. Nixir
          Filtrttt Tank
          Filtratt Pwp
          Enrpncy Smritor - 60KV
          Stup PMP
         Air Comrffwor
         Piping to Pond
         Enrgwcy SMMT t EyMMh
         Opmtiom/Nunt Nmul
         Bitch TrtttMnt Eqvipvfit
       Labor
         Opwator  (16 hrs)
         Operator  (8 hrs)
         HMlth  ( Saftty EqviDMDt
       Clowr*

       SUBTOTAL  - Know Costs Only
         3mral Cant 'ion* 9
         Finishn 9
         Elictrical 9
         IiwtnMRtati jn t Controls
         Yard Piping f
       SUBTDTflL  - Pimntaat Costs (
       SUBTOTAL  - Known and Ptrtsntap Costs Only
         feoihzation I » of SUBTOTAL - Knom

     Subtotal
3.2.3  Alluvial SroundMtir Aavdiition
     ALLUVIAL  SROUMMATER PROGRAM
          COST INCLUDED IN Section 3.3.3
2 EACH
2 EAOt
4 EACH
2 EAD4
1 EACH
1 EACH
2 EACH
2 EACH
1 EACH
1 EACH
1 EACH
EACH
EACH
EACH
EACH
LS
Era
EACH
1 EACH
5,336 MS
5,336 HRS
1 LS
1 LS

i*of SUBTOTAL
S of SUBTOTAL
ttof SUBTOTAL
i* of SUBTOTAL
* of SUBTOTAL
50,000
2,000
20,000
800
10,000
12,000
35,000
1,200
3,000
1,200
3,000
600
23,000
1,200
12,500
15,000
1,000
10,000
100,000
31.50
31.50
143,420
10,900






r • 54* of SUBTOTAL
Costs Only
-Knom * *


100,000
4,000
80,000
1,600
10,000
12,000
70,000
2,400
3,000
1,200
3,000
600
25,000
3,600
12,500
15,000
1,000
10,000
100,000
168,064
168,084
143,420
10,900
« 1,582, 738
119,904
47,962
239,809
119,904
287,771


«, 398,088
119,904
                                        2,317,992
             Monitoring

-------
                                           INDUSTRIAL
                                   MlAEfl,  OKUKMfl
                                   EPA RE!€DY WITH EXCflVRTlON OPTION
ITEM
QUANTITY  KASURE
        LWIT
        COST
EXTENDED
  COST
Stction 3 - DETAILS) JBOY DESCRIPTION
  3.3  Othw ftmdial Ftatum
  3.3.1  RtMdial Support ricihtits
       GENERAL
         Bonds and Insurant (29 of
          Construction Subtotal)
         Equipmt Mob/Dnob (0.5*
          of Construction Suototal)
         CoBNnity Rtlatiom
          Labor
          Materials
         Utility Strviet
          Tiltqnont,  Mtnr, eltctric

      Subtotal

      SITE SUPPORT
        HMlth/Safity Progra*
        Air Monitoring
        Projtct Adnnistration

      Subtotal

      SUPPORT  FACILITIES
        Construction  Offict
        Antrooi Trailer
        Guard  Station
        Suart  Strvict
        EquipMnt Naint. Shop
        StoragtShtd
        On Sitt Laooratory
        iMical  Sarvicts Stat m
        Hitirolofical  Station
        DKontannation Stations
        Roadways

      Subtotal
       i    IS
       1    LS
     216
       1

       1
HRS
LS

LS
       1    LS
       1    LS
       1    LS
           LS
           LS
           LS
           LS
           LS
           LS
           LS
           LS
           LS
           LS
           LS
1600,000
150,000
45.00
10,000
54,800
209,000
171,100
65,000
«20,000
21,800
10,000
101,430
136,240
9,000
809,300
155,400
6,700
489,100
204,700
«600,000
150,000
9,720
10,000
SB, BOO
209,000
171, 100
65,000
tao,ooo
21,800
10,000
101,430
136,240
9,000
809,300
155,400
6,700
489,100
204,700
                                          *B2B,520
                                           US, 100
                                          1,963,670

-------
                              :1""1NARY
                                  IfCUSTSIflL «flS7E SITE
                            C3IJCR, OKLflhCWJ
                            EPA ROCDY WITH OCflVftTIQN OPTION
                                     UNIT    U»IT     EXTBOED
ITEM                          QUHTITY «SURE   COST      COST

SKtion 3 - DETAILS) SEJQY DESCRIPTION
 3.3 Other Rntdia! Featurts
 3.3.2  Surface Hater Controls
     S70&MOTE3 CONTROL
       Detention Pond
        Excavation       -        4,000   CY       13.00   $12,000
        Backfill                 4,000   CY        5.00    20,000
        SaiJloay                    i   LS      10,000    10,000
       Lirwr                   142,000   CY        1.00   142,000
       Disctiargt Lin*
        4* WPf Lin*               800   Lf       15.00    12,000
     Subtotal                                                    *!%,000
 3.13 RmdiaJ
     «NITOflIf€ PWGMN
      Homtonng Mill Installation      6   ER      13,000    *1A,000
      Monitoring fintmim          31   ED         750    23,250
     Subtotal

 3.3.4 Institutional Controls
     iNSTiTUTiott. comas
      Octd flMtrictions
        Lc«al Fm                   1    LS     150,000    160,000
        Fitlrf Karton               23    EA         250     6,250
      Easocnts I Prrmrty Pwcnasn                         552,000
    Subtotal                                                     608,250

-------

-------
                     PR!UM!NARY
                             HAWAflE IHUSTRIAL HASTE SIT!
                             CftllCR,  OKLAHOW
                             EPA REJOY WITH EXCAVATION OPTION
 ITB
                                      UNIT     UNIT     EJTQCED
                              QURNTITY KftSUJE   COST       COST
 Section 3 - DETAILED «BCDV DESCRIPTION
CONSTRUCTION SUBTOTAL

CONTINGENCIES
      Bid Contingency
      Scope Contingmy

      Subtotal

          TOTAL
                                                             128,306.838
INPUNTATION COSTS
     Engiiwring Onign
     Pwmtting and Lqal
     Sirvicn Ouriiq Cowtnction

     Subtotal
                                  1»
                                  20X
                                  1W
                                   7t
                                  10*
TOTAL CAPITAL COST Bastd on Octotar 19M Dollar*
     Engineering **• AKord Contraction Coct Indn
         Dallas Smtntar 1989   318S
         Dallas October 1988     3185
             Multiplier to change bast to Septe^er

TOTAL CAPITAL COST Baud on September 1989 Dollars
                                                     4,246,026
                                                     5,661,368
                                                               9,907,393

                                                              «3B,ai4,23i
                                                     3,821,4£3
                                                     2,674,9%
                                                     3,821,423
                                                              10,317,842

                                                              «4«,532,073
                                            1989 • 1.0013
                                                              146,595,165
OPERATIONS t HAINTENAJCE COSTS
    Present Uortft of $661,900 Annual OM Costs assailing
        5* Interest Rate ovtr 30 years and 1639,700
        Annual OM Costs assuring 5* over B years

TOTAL CAPITAL COST Including Operations I Haintenanct
                                                               14,309,500
                                                              162,904,665

-------