United States        Office of
           Environmental Protection    Emergency and
           Agency           Remedial Response
 SEPA    Superfund
        -  Record of Decision

           Crystal Chemical
           (Amendment), TX
EPA/ROD/R06-92/071
June 1992

PB93-964201
o

-------
                                         NOTICE

The appendices listed in the index that are not found in this document have been removed at the request of
the issuing agency. They contain material which supplement, but adds no further applicable information to
the content of the document. All supplemental material is, however, contained in the administrative record
for this site.

-------
50272-101
 REPORT DOCUMENTATION
        PAGE
1. REPORT NO.
   EPA/ROD/RO6-92/071
                                           3. Recipient-* Accession No.
 4. Title and Subtitle
   SUPERFUND  RECORD OF  DECISION
   Crystal Chemical (Amendment), TX
   First Remedial Action  - Final
                                           5. Report Date
                                             06/16/92
                                           6.
 7. Authors)
                                           8. Performing Organization RepL No.
 9. Performing Organization Name and Address
                                                                     10. ProjectTTask/WorkUnltNo.
                                                                     11. Contract(C)orGrant(G)No.

                                                                     (C)

                                                                     (G)
 12. Sponsoring Organization Name and Address
   U.S. Environmental Protection Agency
   401 M Street,  S.W.
   Washington, D.C.   20460
                                            13. Type of Report & Period Covered

                                              800/000
                                                                     14.
 15. Supplementary Note*
    PB93-964201
 16. Abstract (Limit: 200 word*)
   The 24.4-acre  Crystal Chemical site  consists of  a 6.8-acre  abandoned herbicide
   manufacturing  facility  (referred to  as the onsite area) and 17.6 acres  of affected
   surrounding properties  (referred to  as the offsite area)  in Houston, Harris County,
   Texas.  The site,  which  lies within  the 100-year floodplain of an adjacent flood
   control channel,  overlies  a shallow  aquifer system.  Surrounding land use is commercial
   and industrial.   From 1968 to 1981,  herbicides,  including arsenic compounds, were
   manufactured onsite.  During that  time several structures,  four evaporation ponds, and
   many storage tanks were  utilized in  site operations, and  drums of raw and finished
   product were routinely stored in the open.  During transfer of raw materials from rail
   cars, onsite soil  was contaminated by herbicides spilled  from drums.  Contamination  of
   offsite soil and sediment  was a result of periodic flooding,  which caused arsenic-
   contaminated onsite wastewater to  move offsite.   In 1981, the site was  abandoned, and
   approximately  99,000 gallons of chemical liquids in a storage tank and  600,000 gallons
   of wastewater  in the evaporation ponds were left onsite.  Emergency removal actions,
   conducted intermittently by EPA from 1981 to 1988,  included removing chemical liquids
   and wastewater,  temporarily capping  the site, dismantling and decontaminating site

    (See Attached  Page)
 17. Document Analysis a. Descriptors
   Record of Decision - Crystal  Chemical  (Amendment),  TX
   First Remedial Action - Final
   Contaminated Medium: Soil
   Key  Contaminants:  Metals  (arsenic)

   b. Mentffiers/Open-Ended Terms
   c. COSATI Reid/Group
   Availability Statement
                                                      19. Security Class (This Report)
                                                             None
                                                      20. Security das* (This Page)
                                                      	None	
                                                       21. No. of Pages
                                                         34
                                                       22. Price
(SeeANSI-Z39.18)
                                      See Instructions on Reverse
                                                      OPTIONAL FORM 272 (4-77)
                                                      (Formerly NTIS-35)
                                                      Department of Commerce

-------
EPA/ROD/R06-92/071
Crystal Chemical  (Amendment),  TX
First Remedial Action - Final

  Btract  (Continued)

structures, constructing drains and fencing,  and placing fill material onsite.  A 1990
ROD addressed onsite and offsite soil and ground water.  This ROD amends the remedy for
soil and replaces in-situ vitrification with onsite disposal and capping.   The ground
water remedy will not change and will be implemented as called for in the 1990 ROD.  The
primary contaminant of concern affecting the soil is the metal arsenic.

The amended remedial action for this site includes excavating all offsite soil
contaminated with arsenic above 30 mg/1; placing the soil back on the site; construction
of a multi-layer cap and implementing institutional controls to restrict future land use.
The estimated present worth cost for this amended remedial action is $5,803,300.  O&M
costs were provided in the 1990 ROD.

PERFORMANCE STANDARDS OR GOALS:  The cap will comply with RCRA requirements for landfill
closure.  The chemical-specific goal for soil is 30 mg/1.  Onsite surface water must meet
the CWA ambient water quality criteria for arsenic 0.0175 ug/1.  The ground water
remediation goal at the site is 0.05 mg/1.

-------
                                         :9C' N Asard S    Da:.a$ ~e*as "520"   >e:r:"e I'--969-697'   :;x 214-969-7616
July 21,1992
Mava Elliott, Work Assignment Manager
U.S. EPA Region 6
1445 Ross Avenue, Suite 1000
Dallas, TX  75202-2733

RE:   TES X Work Assignment No. C06025
       Crystal Chemical Amended Record of Decision

Dear Ms. Elliott:

As  you requested during our 07/16/92 conversation, I have enclosed the Crystal
Chemical Site  Amended  Record  of Decision (ROD) in which you expressed an
interest.

If you need any further information, please call me with your request.

Sincerely,
Coley Cnaudoin
Research Assistant

Enclosure

cc:      John Shriwise, DPRA, w/o Enclosure
        File/3732.625
                          2" Researc' D- .e  -~. 5:' 71'  Ma-iEata*" Kansas 655C2  Teieonorie9';:-5J9-35£:  FA; 915-539-535;  Teiex 704314

                          Oineronces  Wasnngtc" DC      S; Pat-      Cnicagc      Denser      Oalias     Kansas City

-------
              STATUTORY PREFERENCE FOR TREATMENT AS A
                      PRINCIPAL ELEMENT IS NOT MET
                 AND FIVE-YEAR SITE REVIEW IS REQUIRED
SITE NAME AND LOCATION

Crystal Chemical Company
3502 Rogerdale Road
Houston, Texas

STATEMENT OF BASIS AND PURPOSE

This decision document presents the selected remedial action for the Crystal Chemical
Company site, Houston, Texas, which was chosen in accordance with Comprehensive
Environmental Response, Compensation, and Liability Act, as amended by Superfund
Amendments and Reauthorization Act, 42 U.S.C. Section 9601, etseq., and to the extent
practicable the National Oil and Hazardous Substances Pollution Contingency Plan, 40
CFR Part 300.  This decision is based on the administrative record for this site.

The State  of Texas was given an opportunity to comment on the selected remedy,
however, did not provide any comments.

ASSESSMENT OF THE SITE

Actual or threatened releases of hazardous substances from this site, if not addressed
by implementing the response action selected in this Amended Record of Decision, may
present an imminent and  substantial endangerment  to public health,  welfare, or the
environment.

DESCRIPTION OF THE REMEDY

This Amended Record of Decision addresses the contaminated soils on and off-site. The
ground water remedy selected in the 1990 Record of Decision will be implemented as
it was described in that document  The remedy for the soil contamination addresses the
principal threats at the site by eliminating potential exposure via ingestion, inhalation .or
direct contact with contaminants and by reducing the potential for the soil to act as a
continued source for surface water and ground water contamination.

The major components of the selected remedy include:

            Excavate arsenic-contaminated soil above 30 parts per million (ppm) from
            off-site and place it on the site.
            Install a multi-layer cap over the entire site.

-------
DECLARATION

The selected remedy is protective of public health and welfare and the environment,
complies with Federal and State requirements that are legally applicable or relevant and
appropriate to the remedial action, and is cost-effective.  This remedy utilizes permanent
solutions and alternative treatment technologies to the maximum extent practicable for
this site.  However, because treatment of the principal threat of the site was not found
to be practicable, this remedy does not satisfy the statutory preference for treatment as
a principal element of the remedy.

Because this remedy will result in hazardous substances remaining on site, a review will
be conducted within five years after commencement of remedial action to ensure that
the remedy continues to provide adequate protection of public health and welfare and
the environment.

                                  JUN 1 6 1392
B. U. Wynne
Regional Administrator
Region VI

-------
                   CRYSTAL CHEMICAL COMPANY SITE
                         RECORD OF DECISION
                            CONCURRENCE
                              JUNE 1992
S$n Hitt Section Chief         & - 3
Superfund Enforcement Texas Section (6H-ET)
Sam Becker, Chi
Superfund Enforcement Branch (6H-E)
Michael C. Barr
Assistant Regional Counsel (6C-WT)
Pam Phillipte1'-'7
Assistant Regional/Counsel (6C-WT)
Assistant Regidnal Counsel (6C-W)
Geo/gfe 'Alexander
Regional Counsel (6C)
Allyn M.Davis, Direc
Hazardous Waste Managment Division (6H)

-------
                CRYSTAL CHEMICAL COMPANY SITE
                 AMENDED RECORD OF DECISION
                      TABLE OF CONTENTS
I.    SITE NAME AND LOCATION	  1

II.    SITE HISTORY AND BACKGROUND INFORMATION 	  1

III.   HIGHLIGHTS OF COMMUNITY PARTICIPATION 	  3

IV.   SUMMARY OF .SITE RISKS 	  4

V.    SCOPE AND ROLE OF AMENDED RESPONSE ACTION  	  7

VI.   DESCRIPTION OF ALTERNATIVES  	, .  7

VII.   SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES  	 15

VIII.  SELECTED REMEDY	 21

IX.   STATUTORY DETERMINATIONS  	 22

X.    DOCUMENTATION OF SIGNIFICANT CHANGES	 25

-------
                            DECISION SUMMARY
                                  FOR THE
                          CRYSTAL CHEMICAL SITE
                             HOUSTON, TEXAS
I.  SITE NAME AND LOCATION

The Crystal Chemical Company site ("Crystal Chemical site" or the site") is located at
3502 Rogerdale Road, in southwestern Houston, Harris County, Texas. The company
operated on approximately 6.8 acres.  The acreage is bounded on the west by the
Harris County Rood Control Channel and lies immediately south of Westpark Drive. The
area! extent of contamination covers approximately 24.4 acres. (All further discussions
referring to the "onsite contamination"  refer to the 6.8 acres on which  the Crystal
Chemical Company  operated, and discussions of "offsite contamination11  refer to the
estimated areal extent of contamination off of the site that covers  approximately 17.6
acres.) The site is located east of the area of Harris County known  as Alief (see Figure
1).  While the Crystal Chemical Company was  operating, four evaporation ponds,
several structures, and many storage tanks existed on the site (see Rgure 2).  The site
is now fenced, and all above ground structures have been removed. The site has also
been  capped and graded in  order to  promote drainage  (see  Rgure 3). The land
immediately surrounding the  site is vacant, commercial, and industrial  property.  An
estimated 20,000 people live within a one-mile radius of the site.  Approximately 20
water wells are located within a one-mile radius of the Crystal Chemical site. These
include public drinking water wells, and industrial, irrigation, and observation wells.

The Harris County Rood Control Channel bounds the Crystal Chemical site on the west.
Surface waters that enter the flood control channel flow south and  are discharged into
the Brays Bayou, approximately one mile south of the site.  Brays Bayou eventually
drains into the Houston Ship Channel, which enters Scott Bay and eventually Galveston
Bay.   There  is  no  designated  Texas  significant habitat,  agricultural  land,  or
historic/landmark site directly or potentially effected.  A Preliminary Natural Resource
Survey was conducted by the National  Oceanic and Atmospheric Administration
("NOAA") in February 1989.  To date, NOAA has  not indicated whether there  is direct
impact to NOAA resources.  Additionally, there are no endangered species or critical
habitats within close proximity of the site.
II. SITE HISTORY AND BACKGROUND INFORMATION

Crystal Chemical Company produced arsenical, phenolic and amine-based herbicides
from 1968 to 1981.  Operation  and maintenance problems at the Crystal Chemical
facility during the late 1970s resulted in several violations of the environmental standards
of the  Texas  Department  of Water Resources  ("TDWR"),  now  the Texas  Water


                                      1

-------
    0.
UJ  <
CC  UJ
3  QC

    <
    CO

-------
                        PROPERTY LINE
                                                       40
                                                                      •01
                              FIGURE 2
                         HISTORIC SITE MAP
SOURCE: D'APPOLONIA/ERT/BFI
       SITE INVESTIGATION
       JANUARY, 1984
METCALF &

-------
POOR QUALITY
  ORIGINAL
                  n
                  w
                 i a
               t  I C
                 1
               i S
               I I
               § i
               I

-------
Commission ("TWO"). The primary problem was repeated flooding of the site which
carried arsenic-contaminated wastewater offsite. In 1978 the Crystal Chemical Company
applied to the State of Texas for an onsite deep well injection permit to dispose of the
facility's wastewaters which were being stored in the four onsite wastewater evaporation
ponds. The permit was denied.

In September 1981, Crystal Chemical filed for bankruptcy and abandoned the site,
leaving approximately 99,000  gallons of arsenic  trioxide  in a  storage tank and
approximately 600,000 gallons of wastewater in the evaporation ponds. Arsenic trioxide
is a substance used in the manufacturing of weed killers, enamels, and pesticides.  It
may be highly toxic and a potential cause of cancer.

The United States Environmental Protection Agency ("EPA") initiated an Emergency
Removal Action to stabilize the site in September 1981, and the action was completed
in February 1983.  During the first phase of the EPA emergency cleanup, the wastewater
was removed from the ponds and disposed of at an offsite commercial waste disposal
facility. The top foot of soil was removed, mixed with lime, then deposited back into the
wastewater ponds. A temporary cap, which included a plastic cover topped by a layer
of clay, was placed over the area to limit the infiltration of water into contaminated soil.
The arsenic trioxide was sold,  and the buildings and process equipment were
disassembled,  decontaminated and sold, essentially leaving the site vacant.  The only
remaining structures onsite are two  concrete slabs.  Subsequently, EPA has taken
further measures to control surface runoff and  site access, and to enhance the integrity
of the temporary cap. Steps taken by EPA in  1983 and 1988 included construction of
drains, fencing, and placement of additional fill onsite.

In 1983, the Crystal Chemical property was added to the National Priorities List ("NPL"),
pursuant  to Section  105  of  the  Comprehensive  Environmental    Response,
Compensation,  and Liability Act ("CERCLA"), 42 U.S.C. Section 9605, as amended,
qualifying  the site for investigation and remediation  under CERCLA, more commonly
known as Superfund.

In June 1990, EPA originally proposed a plan for the arsenic-contaminated soils and for
the contaminated ground water, and the Record of Decision ("ROD") documenting the
remedy selection was issued on September 27, 1990. The ground water remedy that
was selected in the 1990 ROD consisted of extraction, treatment, and discharge to a
Publicly Owned Treatment Works ("POTW), to surface water, or reinjection.  The soils
remedy proposed and selected by EPA in  1990  included  excavating offsite soils
contaminated with arsenic greater than 30 parts per million ("ppm"), treating all the soils
contaminated  with arsenic greater  than 300 ppm with a process called In-Situ
Vitrification ("ISV"), and  capping the entire site after the soils treatment  had been
completed.  The ISV technology  is a process which uses electricity to generate heat
which will melt the contaminated soil.  The process destroys many contaminants when
the soil is heated and permanently bonds other contaminants into the glass-like material

-------
 as it cools. The glass-like material is expected to remain stable for thousands of years.
 Soils from the Crystal Chemical site were actually treated using this process, and tests
 conducted on the glass-like material have shown that only a very small amount of
 arsenic is able to leach.

 However, EPA was notified in July 1991 by the only vendor of the ISV technology that
 the technology would be unavailable for an undetermined period of time because of the
 need to do  additional analytical  and experimental work on the technology.  After
 evaluating its options, EPA decided that it is in the best interest of public health, welfare,
 or the environment to  proceed  with  the  selection  of  another remedy for soil
 contamination.

 The remedial alternatives considered for the Crystal Chemical site are described in detail
 in the Supplemental Feasibility Study ("SFS") report. This amended decision document
 presents the selected remedial action for the Crystal Chemical site, Houston, Texas,
-chosen in accordance with CERLCA, as amended by the Superfund Amendments and
 Reauthorization Act of 1986 ("SARA") and, to the extent practicable, the National Oil and
 Hazardous Substances Pollution Contingency Plan ("NCP"), 40 CFR Part 300.  The
 decision for this  site  is based on  the administrative record.   An  index  for the
 administrative record is included as an attachment to this document.
 III. HIGHLIGHTS OF COMMUNITY PARTICIPATION

 The Amended Proposed Plan for the Crystal Chemical site was released to the public
 in early February 1992.  This document as well as all other site related documents are
 available to the public at both the administrative record and the information repository
 locations. A summary of the Amended Proposed Plan and the notice of the availability
 of these documents and the administrative record was published in the Houston Post
 on February 12, 1992.  The public comment period began on  February 24, 1992, and
 ended March 24, 1992.  An informal Open House was held in the area near the site on
 February 20,1992. The Public Meeting was held on March 19,1992, at the Westchase
 Hilton and Tower in Houston, Texas. The purpose of this meeting was to discuss all the
 available alternatives and EPA's preferred alternative for the soil contamination at the
 Crystal  Chemical site.  A  response to  the  comments received during  this period
 including  those  expressed  verbally  at the public meeting  is  included  in the
 Responsiveness Summary, which is included as a part of this Amended  ROD.   This
 decision document presents the selected remedial action for the soil contamination for
 the Crystal Chemical site, Houston, Texas, chosen in accordance with CERCLA, as
 amended by SARA,  and, to the extent practicable, the NCP,  40 CFR Part 300.  The
 decision for  this site is based on the administrative  record.   An index  for the
 administrative  record is included as an attachment to this document.

-------
 IV.  SUMMARY OF SITE RISKS

 The following  discusssion is  an excerpt from the Summary  of  Site Risk section
 contained in the  1990 ROD.  It is being  included in this Amended ROD in order to
 provide for continuity and  clarity between  the two documents.

 During the SFS, a Health Assessment was prepared for EPA by the Agency for Toxic
 Substances and Disease Registry ("ATSDR"). This report reviewed  the potential risks
 to human health posed by the Crystal Chemical  site in regards to contaminant sources
 and potential contacts to the population.  The ATSDR determined that arsenic was the
 only contaminant of concern with respect to public health.  Arsenic ranks twentieth
 (20th) in abundance among the natural elements in the Earth's crust and, therefore, is
 found naturally occurring in rocks and soils. It is widely used in herbicides and is found
 in both organic as well as inorganic forms on the Crystal Chemical site.  The arsenic
 found on the  Crystal Chemical site exhibits characteristics of a  substance  that is
 regulated under the  Resource Conservation and Recovery Act ("RCRA"), as amended,
 42 U.S.C. Section 6901, et seq., and a specific type of arsenic (i.e.,  K031  - by-product
 salts generated in  the production  of  monosodium  methylarsenate  ("MSMA") and
 cacodylic acid) that is listed and regulated under RCRA was produced on the site.
 ATSDR determined that the areas of concern where potential exposure to the arsenic
 contamination was most likely to occur would be surface  soil and surface water. The
 susceptible populations were identified as children who may play in the  immediate
 vicinity of the site and workers who may be involved in maintenance and remediation
 activities at the site.  The identified exposure  pathways  include direct skin contact,
 ingestion of contaminated ground water, surface water and surface soil, and inhalation
 of contaminated airborne dusts.

 Also,  during the SFS, an  analysis was  conducted to  estimate  the  health  or
 environmental  problems  that could result  if no action  were taken  on the  soil
 contamination at the Crystal Chemical site. This analysis is commonly referred to as an
 endangerment assessment. The primary purpose of the endangerment assessment is
-to  evaluate  potential health  effects  that could result from direct exposure to the
 contaminant as a result of contaminated soil, surface water or airborne dust coming in
 contact with an individual through direct contact with the skin, ingestion (eating or
 drinking),  or inhalation,-  and to determine appropriate  remediation  levels  of the
 contaminant of concern. Irrthis case, arsenic in its most toxic form (trivalent, inorganic
 arsenic) is the contaminant of concern.  Although phenol has been found onsite, the
 ATSDR Health Assessment determined that phenolic compounds  did not present a
 potential health problem to area residents and workers in the area due to the low levels
 that were detected at the site.  Although phenol has been found onsite at a maximum
 concentration of 157 ppm, the endangerment assessment did not evaluate risk because
 concentrations of this compound were well below any health-based levels of concern.

-------
 With respect to potential health effects, the results of the endangerment assessment
 supported the ATSDR  Health  Assessment and identified the following five specific
 potential ways in which individuals could become exposed at the site:

             ingestion of or direct contact with soil  and sediments,

             ingestion of or direct contact with surface water,

             ingestion of shallow ground water,

             inhalation of wind dispersed dust, or

             ingestion of contaminated fish.

 The contaminated soil was determined to be a principal threat at the site because of
 direct contact, ingestion,  and  inhalation risks and because of the soil's  impact on
 ground water.  The remedial objectives for the soil  are to eliminate potential exposure
 via  ingestion,  inhalation or direct contact with contaminants and  by reducing the
 potential for the soil to act as a continued source for surface water and ground water
 contamination.

 The contaminated shallow ground water was also determined to be a principal problem
 at the site because of the potential exposure of the public to the site contaminants and
 because of the threat of migration of contaminants to deeper zones of ground water.
 The deeper ground water zones are used for industrial, irrigation, and drinking water
 purposes.  The remedial objective is to reduce the amount of contamination to human
 health-based standards in order to eliminate or minimize the risks associated with the
 contaminated shallow ground water.

 Arsenic was  determined by ATSDR to be the contaminant of concern at the Crystal
 Chemical site, therefore, all remediation goals are set for arsenic.  The  only other
'contaminant found at the site which may be of concern was phenol. Remediation levels
 assuming chronic daily exposure in order to protect against noncarcinogenic effects
 were calculated for the phenolic compounds.  The  remediation levels were calculated
 to be 420,000 ppm for an aduit and 50,000 ppm for a child.  The remediation levels for
 phenolics have no significant.effect on the  volumes of soil  or ground  water requiring
 remediation at the site, and because these levels are relatively high compared to
 phenolic levels found at the site (approximately 160  ppm), the remediation levels for the
 phenols are not discussed in the review and evaluation of remedial technologies.

 The selection of an appropriate remediation level for arsenic was based primarily on an
 evaluation of the potential health effects caused by human exposure to the contaminant,
 assuming that the future land use will be residential and commercial/industrial.  The
 reasoning behind designating the future land use as possibly residential is that the City

-------
of Houston does not, at this time, have zoning ordinances, therefore, EPA takes a
conservative approach and calculates risk so that all potential scenarios are taken into
consideration.

To a lesser extent remediation levels for arsenic were based on the naturally occurring
background conditions of arsenic in soils.  Arsenic is a naturally occurring metallic
constituent of soils, derived from the rock or parent materials, from which the soil was
formed.  Background concentrations of metals in soil may vary from region to region.
For example, the United  States Geological Survey  (1975) reports that the mean and
range of background arsenic concentrations in western soils is 6.1 ppm and 0.2-97
ppm, respectively.

A limited number of soil  samples collected from offsite areas within two miles of the
Crystal Chemical site found background arsenic concentrations to be less than 1.6 ppm.
Soil sampling at the site found arsenic concentrations on the order of several hundred
to several thousand ppm. As determined in the endangerment assessment, leaving this
contamination on site without treatment would result in a one in ten thousand  (10"4) risk
of cancer  over the  lifetime of individuals who  may come in contact  with  this
contamination.    This  estimate was developed  by  taking into account various
conservative  assumptions about the  likelihood of a  person being  exposed  to the
contaminated soil, and in consideration of the toxicologicai effects of arsenic exposure.

The national risk of getting some form of cancer over a 70 year life span is very high,
estimated at  one chance in five or 0.2.  The one in  five probability is the baseline
situation or "natural incidence" of cancer.  A one in  ten thousand (10"4) risk is an
increment above the baseline risk (an increase from 0.200 to 0.201).  EPA policy calls
for an  evaluation of remediation levels that range from a cancer risk  of one in ten
thousand to one in one  million (10"* to 10"6), using one in  one million as a point of
departure.

Utilizing conclusions made concerning the public to be protected and the amount and
duration of exposure, the endangerment assessment  calculated health standards for
arsenic in surface soil and sediment.  These goals call for the removal of offsite soils to
a concentration of 30 ppm for arsenic, which represents a one in one hundred thousand
(10'5) cancer risk level. * Since the  average background concentration of arsenic in
western soils (6.1 ppm) exists at a level in excess of EPA's standard point of departure
(one in one million cancer risk - at a 3 ppm concentration of arsenic), 30  ppm  was
determined to represent  a safe health-based action level. These soils will be placed
back on to the'Crystal Chemical site, and a multi-layer cap will be constructed over the
entire site.  Once the soil remedy is complete, the resulting cancer risk will be reduced
to less than one in one million (at or near the original background conditions).

-------
 V.  SCOPE AND ROLE OF AMENDED RESPONSE ACTION

 The studies undertaken at the Crystal Chemical site have identified two principal threats
 (i.e., contaminated soil and shallow ground water), and the remedies to eliminate or
 minimize these threats that are included in the 1990 ROD and this Amended ROD and
 are addressed as one operable unit.

 The contaminated soil was determined to be a principal threat at the site because of
 direct  contact, ingestion, and  inhalation risks and because of the soil's impact on
 ground water. The  remedial objectives for the soil are to eliminate potential exposure
 via ingestion, inhalation  or  direct  contact with contaminants and  by  reducing  the
 potential for the soil to  act as a continued source for surface water  and  ground water
 contamination.

 The contaminated shallow ground water was also determined to be a principal problem
 at the site because of the potential exposure of the public to the site contaminants and
 because of the threat of migration of contaminants to deeper zones of ground water.
 The deeper ground water zones  are used for industrial,  irrigation, and drinking water
 purposes. The remedial objective is to reduce the amount of contamination to human
 health-based standards in order to eliminate or minimize the risks associated  with the
 contaminated shallow ground water.

 The remedy  selected in  the 1990  ROD for the contaminated ground water will  not
 change and will be implemented as it is called for in the 1990 ROD. However, because
 of the unavailablity of  the  treatment technology selected  in the  1990 ROD for the
 arsenic-contaminated soils,  this  Amended  ROD addresses the selection of a new
 remedy to address the arsenic-contaminated soils at the Crystal Chemical site.  The risk
 range  selected in the 1990 ROD  for the contaminated soils will remain the same,  i.e.,
 one in one million excess lifetime cancer risk of 3 ppm to one in ten thousand excess
 lifetime cancer risk of 300 ppm (1  x 10"6 to 1 x 10"4). Furthermore, the remediation goals
 for soils will  fundamentally  remain the same.  Therefore, the remediation  goal for
'removal of offsite soils is 30 ppm, which represents a one in one hundred thousand (1
 x 10"*) cancer risk level.
 VI. DESCRIPTION OF ALTERNATIVES           -

 The alternatives for the soil remediation are the following:

       Alternative A-1: Excavation and Offsite Disposal
       •K«*>K-:wK..vKv;*Kv^^^^
       Alternative A-3: Solidification/Stabilization
       Alternative A-4: Soil Washing
       Alternative A-5: Part'aJ IrvSftu Vtnfication ajTd C^pir^ U^VAIWB!^

-------
       Alternative A-6:  Partial Solidification/Stabilization and Capping
       Alternative A-7:  Partial Soil Washing and Capping
       Alternative A-8:  Capping
       Alternative A-9:  No Action
       Alternative A-10: Umited Action

 Common Elements.  Except for the "No Action" and "Limited Action" alternatives, all of
 the alternatives that were considered  for the site included a number  of common
 elements.  Each of the alternatives, with the exception of Alternative A-1, call for long-
 term monitoring activities that will be conducted to ensure that the remedy remains
 effective and continues to protect public health and the environment.  In addition,
 restrictions will be placed on the site to prohibit certain activities, such as soil removal
 or construction of buildings at the site, and site access will be restricted.

 All  of the alternatives involve the removal of offsite soil and sediments with arsenic
 contamination greater than 30 ppm, EPA's offsite remediation level, and  these offsite
 areas  will be backfilled to previously existing grades.   Alternative A-1 proposes to
 dispose of all contaminated soils at an offsite landfill; all other alternatives involve onsite
 placement of the offsite soil and sediments.   Two concrete slabs remain on the site.
 Soil Alternatives A-1 through A-4 call for removing the slabs and disposing of them off
 site. Alternatives A-6 through A-8 call for removing the slabs, breaking them into smaller
 pieces, and placing them under the multi-layer cap that is to be constructed over the
 site. All costs and time required to implement all of the alternatives are estimates. The
 cost estimates were  originally developed in 1989  based on information from the
 treatment technology vendors.  Because of the rate of inflation since 1989, the originial
 estimates have been increased by 3.5%.

 When remediating a site, there are applicable or relevant and appropriate requirements
 ("ARARs) that the remedy(s) must meet in order to be in compliance with Federal and
 State  laws.  Given that the arsenic found  on  the site exhibits  characteristics of a
 substance that is regulated under RCRA, 40 CFR Subpart C,  and that a type of arsenic
.(i.e., K031 - by-product salts generated  in the production of MSMA and cacodylic acid)
 that is specifically listed and regulated under RCRA, 4O CFR Subpart D, was produced
 on the site, certain ARARs apply. If a waste leaches above 5.0 ppm of arsenic when
 analyzed using the Toxicity Characteristic Leaching Procedure ("TCLP"), 40 CFR 261.25,
 it is considered a hazardous waste and is regulated  under  RCRA.  Furthermore, if a
 RCRA regulated waste is treated, additional ARARs apply.

 On June 1,1990 a regulation identifying vitrification as the best demonstrated available
 treatment technology ("BOAT) for arsenic as a RCRA characteristic waste as well as a
 RCRA listed waste was published (55 Fed. Reg. 106 at 22556 to 22561).  The effective
 date  of this  regulation was August  8,  1990.  Associated  with  the BOAT is  a
 concentration-based treatment standard of 5.6 ppm for K031  nonwastewaters, and the
 BDAT concentration-based treatment standard for arsenic as a characteristic (D004)


                                       8

-------
nonwastewater is  5.0  ppm.   When the  soils treatment  and replacement triggers
placement (Soils Alternatives  A-3, A-4, A-6, and  A-7)  or when  offsite disposal of
contaminated soil is involved which, too, triggers placement (Soil Alternative A-1) under
RCRA's Land  Disposal Restrictions ("LDRs"),  40 CFR 268,  the 5.6 ppm treatment
standard for nonwastewaters is required per 40 CFR 268.9.
Soil Alternative A-1:
EXCAVATION AND OFFSITE DISPOSAL

This alternative calls for excavating all onsite and ail offsite soils and sediments with
arsenic contamination  greater  than  30 ppm.    The  estimated  volume of  soils
contaminated  with  arsenic greater  than 30 ppm is  156,000 cubic yards.  These
excavated soils would then be transported offsite for disposal in a landfill that is allowed
to accept arsenic-contaminated soils.  All excavated areas would be back-filled with soil
to previously existing grades and the area would be revegetated.  The total cost of this
alternative is approximately $84,266,100,  and the estimated time required to implement
this alternative would be 2.5 years.

This alternative  calls for the removal of the contaminated  soils from the site and
disposing of them elsewhere.  The offsite and onsite soils with arsenic contamination
greater than 30 parts per million would be excavated, and transported off site and
disposed  in a landfill  that is allowed to accept arsenic-contaminated  soils.  This
alternative reduces site risk by removing soil that is contaminated at levels which may
pose health or environmental risks.   However, this alternative is not favored by EPA
because CERCLA discourages offsite transportation and disposal  of contaminated
materials.
Soil Alternative A-2:
Soil Alternative A-3:
SOLIDIFICATION/STABILIZATION

Solidification is a process which changes a liquid or a sludge into a solid thus changing
its physical state and characteristics.  Stabilization is a process which mixes chemically
binding materials with contaminated soil to reduce the ability of  the contaminants to
leach out of the soil into the surrounding environment  A treatment rate of 1,000 cubic
yards per day is possible when using this treatment technology. For this alternative, all
offsite and  onsite arsenic-contaminated soils and sediments would be excavated and
then treated using the solidification/stabilization process. The site would be backfilled
with the treated soil.  The volume of offsite soils requiring excavation is estimated to be

-------
55,000 cubic yards, and the total volume of soils requiring treatment with this alternative
is  estimated to be  156,000  cubic yards.  The total  cost of this  alternative is
approximately $32,768,300  and it would take approximately 3  years to implement this
remedy.

Solidification/stabilization has been used successfully many times on hazardous waste
sites and conforms with the CERCLA preference for remedies that involve the treatment
of contaminants. However, tests conducted on the arsenic-contaminated soil from the
Crystal Chemical site treated using the solidification/stabilization process have shown
that a high concentration of the arsenic (78 to 288  parts per million) continues to leach
out of the soil after the treatment has been completed, therefore, the mobility of the
arsenic has only been slightly reduced (See Table 1). The  Superfund Program uses as
a guideline  for effective treatment the range of  90 to 99 percent reduction in the
concentration or mobility of the contaminant of concern. Solidification/stabilization was
able to only reduce the amount of teachable arsenic by 68% and even  this reduction is
not consistent,  therefore, EPA does not  consider this  technology to be an  effective
treatment technology for the Crystal Chemical  site. Furthermore, there is no indication
that solidification/stabilization technology reduces the toxicity of the contaminant.

In addition, this technology will significantly increase the volume (a minimum of 10% to
30%) of the contaminated soil that will need to  be put back on to the site. Furthermore,
the soil volume increase that occurs when the  soils  in this area are excavated is
documented to be approximately 40%. The naturally occurring  volume increase of 40%
coupled with the 10% to 30% increase caused by the treatment would significantly
increase the volume of treated soil that requiring permanent storage on the site, creating
an unacceptably large soil  pile, possibly as  high as  19  feet  Therefore, using this
technology will only serve to create a larger volume of waste that would  need to be
placed on the site and a larger volume of waste that would continue  to leach arsenic
with little or no  reduction in the risks posed  by  the site.   In  conclusion, the
ineffectiveness  of  this treatment technology  coupled  with the drawbacks  (volume
increase) of using this treatment technology far outweigh  the Superfund preference to
use treatment when available.  For these  reasons  EPA does not favor this  alternative.
Soil Alternative A-4:
SOIL WASHING

Soil Washing is a process which  removes contaminants from  soil by mixing the
excavated  contaminated  soils  with  a  liquid.   During  the  mixing  process, the
contaminants are washed from the soil. The liquid containing the contaminants is then
drained from the soil, the contaminant is removed from the liquid, and the contaminants
are disposed in an offsite landfill which is allowed to accept arsenic contamination. The
soil processing rate for this technology is approximately 200 cubic yards per day. This
alternative calls for the excavation of all offsite and onsite arsenic-contaminated soils and


                                       10

-------

CQ CO
UJ
UJ
oo
5s
CD »
      h-
      Ul


      I
      CC
        UJ

        1
        cc
        UJ
        cc
        £
        UJ
        03


1-
z
111
h-
a
or
z
O
H-
a
D
CO
1
g
0
g
o
CO
cc

<•
Q
Z
UJ
cc
o
UJ
CQ
53
0
CO
z
53
UJ
~]
o
UJ
CO
cc
£^
(Q
CQ -"


f
i!








s*
10
il
§





•




o
^
.g

-------
 sediments.  The volume of soils estimated to require treatment with this alternative is
 156,000 cubic yards. After the washing process, the site would be backfilled with the
 washed soil. This alternative would take approximately 6 years to implement and would
 cost an estimated $134,719,000.

 This alternative does use treatment, and tests conducted on contaminated soils from the
 Crystal Chemical site using the soil washing technology indicate that the treatment has
 been able to remove 90% of the  teachable arsenic (See Table 1).   However, the
 technology cannot be considered appropriate for the Crystal Chemical site because the
 arsenic is only concentrated  at the  completion  of the treatment process.   This
 concentration of arsenic will require onsite or offsite land disposal since arsenic is an
 element and cannot  be  destroyed.   Because state  and Federal  environmental
 regulations restrict certain land disposal practices, the disposal will be difficult or further
 treatment of the arsenic concentration will be required before disposal can occur.   In
 conclusion,  the use of this treatment technology will provide no overall benefit and will
 provide little or no reduction in the risks posed by the site.  For these reasons EPA does
 not favor this  alternative.
 Soil Alternative A-5:
                                                 UNAVAILABLE
                                                 .- v •*•* .v. *.i".s'". •,/•.-..•.    v
 Soil Alternative A-6:
 PARTIAL SOLIDIFICATION/STABILIZATION AND CAPPING

 This alternative is similar to Soil Alternative A-3, however, only those soils with arsenic
 contamination   greater  than   300   ppm   would  be  treated   using  the
 solidification/stabilization process.  The volume of soils requiring treatment is estimated
 to be 16,500 cubic yards.  A multi-layer cap would be constructed over the entire site
 after the soils had been treated. The cap acts as a barrier that restricts the flow of water
. through the soils which are not subjected to water table conditions, prevents the release
 of soil  and residual contaminants into  the air, and  prevents  direct contact with the
 treated soil and the contaminants. This alternative would cost approximately $9,236,800
 and would take an estimated 2.5 years to implement.

 This alternative would somewhat decrease site risk by slightly reducing the mobility of
 contaminants present in the soil, however, there would be no reduction  in the toxicity
 or volume of contaminants.   Furthermore, this technology increases the volume of
 contaminated soil by a minimum of 10% to 30%. The soil volume increase that occurs
 when the soils in this area are excavated is documented to be approximately 40%.  This
 naturally occurring volume increase of 40% coupled with the 10% to 30% increase will
 significantly increase the volume of treated soil that will require permanent storage on
 the site.  Therefore,  this alternative may create an unacceptably large soil stockpile.

                                       12

-------
This alternative also requires that a multi-layer cap be constructed over the treated soils,
therefore,  the  stockpile coupled with the height of the cap constructed (9 to 15 feet
high) will  be environmentally and aesthetically unacceptable.  For these reasons and
other reasons as in the discussion of Soil Alternative A-3, this alternative is ineffective,
impracticable, and has many drawbacks, therefore, it is not favored by EPA.
Alternative A-7:
PARTIAL SOIL WASHING AND CAPPING

This alternative is similar to Soil Alternative A-4, however, only those soils with arsenic
contamination greater than 300 ppm would be treated using the soil washing process.
The volume estimated to require treatment is 16,500 yards. A multi-layer cap consisting
of clay, plastic, sand, topsoil, and vegetation would be constructed over the  entire site
after the soils had been treated.  The cap acts as a barrier that restricts the flow water
through soils which are not subjected to water table conditions, prevents the release of
soil and residual contaminants into the air, and prevents direct contact with the treated
soil and the contaminants. This alternative would cost approximately $21,618,400 and
would take an estimated 3.75 years to implement.

As with Soil Alternative A-4, there are drawbacks to this alternative, the more important
being the need to dispose the concentrated arsenic that will result from the treatment.
Ultimately, this concentrated arsenic may have to be disposed on the site because of
state and Federal environmental regulations that restrict certain land disposal practices.
If offsite  disposal is desired, a pre-treatment step to reduce the teachability of the
arsenic will be required before an offsite facility will accept the arsenic contamination.
For these reasons as well as the reasons associated with alternative A-4, EPA does not
favor this alternative.
Alternative A-8:
CAPPING

The capping alternative calls for all soils and sediments from offsite that have arsenic
contamination greater than 30 ppm to be brought back on to the site.  Then a multi-
layer cap would be constructed over the entire site.  The cap acts as a barrier that
restricts the flow of water through the soils,  prevents the release of soil contaminants
into the  air,  and prevents direct contact with contaminants.  Although a  cap  was
constructed over the site in 1983 during an  EPA Emergency Removal Action and this
cap has eliminated direct contact with the contaminant and has minimized or eliminated
infiltration, this cap was constructed to be  a temporary barrier.  If a cap is to be a
permanent barrier, a more substantial cap design must be constructed. This alternative
would  take approximately 2.25 years to implement and would cost  approximately
$5,803,300.

                                       13

-------
Although no treatment of the soils will be done before the site is capped, the multi-layer
cap  will  ultimately aid in reducing the amount of ground water contamination  by
eliminating the infiltration of water through the arsenic-contaminated soil.  Additionally,
through the ground  water extraction process, the arsenic contamination within and
below  the  ground water table  will  be eliminated.  Therefore, the  mobility of the
contaminants in the soil will be somewhat reduced if a permanent cap were constructed
over the site, however, neither the volume of the contaminated soils nor the toxicity of
the contaminants would be reduced.

Treatment of the source of contamination is always preferable to no treatment, however,
in this case the treatment of the arsenic contaminated soils at the Crystal Chemical site
may cause  more  environmental problems due  to an ineffective and  impracticable
treatment (i.e., solidification/stabilization or soil washing) technology than it would solve.
This alternative provides for the protection of public health and significantly reduces the
risks posed  by the site.  Therefore, this is EPA's preferred alternative.
Alternative A-9:
NO ACTION

The Superfund program requires that a no action alternative be considered at every site
as a basis of comparison when evaluating other alternatives. No action assumes that
nothing would be done to restrict site access, monitor offsite contaminated soil, or to
maintain the existing temporary cap.  Therefore, there would be no costs associated
with  this alternative.  This alternative is not favored by EPA  because  it would not
decrease the toxicity, mobility, or volume of contaminants or reduce public health or
environmental risks.
Alternative A-10:
LIMITED ACTION

This alternative involves site access and land use restrictions that include prohibiting
activities such as soil removal or any type of commercial or residential activity on the
site.  The costs associated with this alternative are approximately $107,100, and the
restrictions would be enforced in perpetuity.

This alternative would somewhat reduce risks to public health and the environment by
restricting site use and access and by maintaining the existing cap. However, the cap
that exists on the site was contructed in 1983 during one of EPA's emergency removal
actions and was not intended to be a permanent barrier to prevent migration of arsenic
from the site or migration  of surface waters through the contaminated soils.  Although
the temporary cap has served its purpose well, this alternative does not provide long-
term protection to public health or the environment, therefore, EPA does not favor it.


                                       14

-------
VII. SUMMARY OF COMPARATIVE ANALYSIS OF ALTERNATIVES

The nine (9) criteria used in evaluating all of the alternatives identified in the SFS are as
follows:

            Overall protection of human health and the environment,
            Compliance with applicable or relevant and appropriate requirements,
            Long-term effectiveness and permanence,
            Reduction of toxicity, mobility, or volume through treatment,
            Short-term effectiveness,
            Implementability,
            Cost,
            State/support agency acceptance, and
            Community acceptance.

Explanation of Evaluation Criteria

      Overall Protection of Human Health and Environment addresses whether or not
      a remedy provides adequate protection and describes how risks posed through
      each  pathway  are eliminated,  reduced, or  controlled  through  treatment,
      engineering controls or institutional controls.

      Compliance with ARARs addresses whether or not a remedy will meet all of the
      applicable or relevant and appropriate requirements of other Federal and State
      environmental statutes and/or provide  grounds for invoking a waiver.

      Long-term effectiveness and permanence refers to the magnitude of residual risk
      and the ability of a remedy to maintain reliable protection of  human health and
      the environment over time once cleanup goals have been met.

      Reduction of toxicity, mobility, or volume through'treatment is the anticipated
      performance of the treatment technologies that may be employed in a remedy.

      Short-term effectiveness  refers to the  speed with which the remedy achieves
      protection, as well as the remedy's potential to create adverse impact on human
      health  and the  environment  that may  result  during  the  construction  and
      implementation period.

      Implementability  is the technical and administrative feasibility of a remedy,
      including the availability of materials  and services needed to implement the
      chosen solution.

      Cost includes capital and operation and maintenance costs.
                                     15

-------
      State  Acceptance indicates whether, based on  its  review  of the RI/FS and
      Proposed Plan, the  State concurs with, opposes, or has no comment on the
      preferred alternative.

      Community Acceptance will be assessed in the Record of Decision following a
      review of the public  comments received on the RI/FS report  and the Proposed
      Plan.
Comparative Analysis:

Overall Protection.  All of the alternatives, with the exception of the "no action11 and
"limited action" alternatives, may provide some protection of human health and the
environment by eliminating, reducing, or controlling risk through treatment, capping, or
deed and land use restrictions. The preferred alternative calls for capping all of the
arsenic-contaminated  soils  above  acceptable  health-based  levels, which are soils
contaminated with  arsenic above 30 parts per million.  The cap itself acts as a barrier
that restricts the flow of water through the soils which are not subjected to water table
conditions, prevents  the release of soil and  residual  contaminants into the air, and
prevents direct contact with the arsenic contamination.  Because the  ground water
extraction and treatment remedy selected in the 1990 ROD will be implemented, through
the extraction of the contaminated ground water, this source of arsenic  contamination
will be  eliminated.  Additionally, the arsenic contaminated soils below the ground water
table will be treated during the implementation of the ground water remedy. The arsenic
contaminates adsorped to the soil particles within the ground water saturated zone will
be desorped during the pumping process and extracted for treatment. The desorption
and extraction of the arsenic will make less arsenic available thus eliminating the source
of arsenic contamination within the ground water saturated zone and preventing further
or continued release into the ground water.

Therefore, the remedial objectives achieved through the implementation of the preferred
soil alternative would  be the  elimination of the potential  exposure  via  ingestion,
inhalation or direct contact with the contaminants. The remedial objectives achieved
through the  implementation of the ground water remedy selected in the  1990 ROD will
be the elimination of the potential exposure via ingestion and  direct contact with
contaminants and the elimination the potential for migration of contaminants to deeper
zones  of ground water.

The  Superfund Amendments  and  Reauthorization Act of  1986 ("SARA")  places an
emphasis on the remedies which employ treatment that permanently and significantly
reduces the volume, toxicity or mobility of the hazardous substances, pollutants, and
contaminants over remedies that  do  not employ such treatment.  The Superfund
program uses as  a  guideline  for effective treatment  the range of 90  to 99  percent
reduction in the concentration or mobility of the contaminant of concern.  Therefore,

                                      16

-------
 EPA believes that treatment technologies that cannot achieve this level of performance
 on a consistent basis are not sufficiently effective and generally will not be appropriate.

 The solidification/stabilization treatment technology has not been able to achieve the 90
 to 99 percent reduction in the concentration or mobility of teachable arsenic. In fact, the
 technology  has  only been able to achieve a 68% reduction, and  the percentage  of
 reduction has not been consistent.  The soil washing treatment technology has been
 able to achieve a 90% reduction in the concentration or mobility of teachable arsenic,
 therefore, it can be considered  an effective treatment technology.   However, the
 technology cannot be considered appropriate for the Crystal Chemical site because the
 arsenic is only concentrated at the completion  of the treatment process.   This
 concentration  of arsenic will require onsrte or offsite land disposal since arsenic is an
 element and cannot be destroyed.  Therefore, through the conduct of the soil washing
 treatment technology, no overall benefit has been achieved.

 In conclusion, the treatment technologies available for the Crystal Chemical site are
 either ineffective, do not afford a greater overall benefit, or do not afford a greater overall
 reduction in risks posed by the site.  Therefore, doing treatment for the sake of doing
 treatment using the available technologies does not, in this case, appear to be
 appropriate or beneficial.

 Because 1he "no action* and  "limited action* alternatives are not protective of human
 health and the environment, they will not discussed any further.
 Compliance with Applicable or Relevant and Appropriate Requirements (ARARs).
 ARARs are the Federal and State requirements that a selected remedy must meet.
 Given that the arsenic found on the site exhibits characteristics of a substance that is
 regulated under RCRA, 40 CFR Subpart C, and that a type of arsenic (i.e., K031 - by-
 product  salts generated in the production of MSMA and cacodylic  acid) that is
 specifically listed and regulated under RCRA, 40 CFR Subpart D, was produced on the
.site, certain ARARs apply.  If a waste leaches above 5.0 ppm of arsenic when analyzed
 using TCLP, it is considered a hazardous waste and  is regulated  under  RCRA
 Furthermore, if a RCRA regulated waste is treated, additional ARARs apply.

 On June 1,1990, a regulation identifying vitrification as the best demonstrated available
 treatment technology ("BOAT") for arsenic as a RCRA characteristic waste as well as a
 RCRA listed waste was published (55 Fed. Reg. 106 at 22556 to 22561).  The effective
 date of this regulation was August 8,1990.  The concentration-based treatment standard
 for K031  nonwastewaters  is 5.6 ppm  of arsenic, and the BOAT concentration-based
 treatment standard for arsenic as a characteristic (D004) nonwastewater is 5.0 ppm.
 When the soils treatment and replacement triggers placement  (Soils Alternatives A-3,
 A-4, A-6, and A-7)  or when offsite disposal of contaminated soil is involved which, too,
 triggers  placement (Soil Alternative A-1) under  RCRA's Land Disposal Restrictions


                                       17

-------
 ("LDRs"), 40 CFR 268, the 5.6 ppm treatment standard for nonwastewaters is required
 per 40 CFR 268.9.  Although the vitrification technology alternatives investigated in the
 SFS for the Crystal Chemical site are not available, the concentration-based treatment
 standard associated with the BOAT remains the goal of any treatment technology. None
 of  the  available treatment  technologies have been  able  to  achieve the required
 concentration-based treatment  standard.  However, if one of the available treatment
 technologies were practicable and were chosen as the selected remedy, a treatability
 variance could be sought for this site.

 Alternatives A-3, A-4, A-6, A-7, and A-8 must comply with two federal ARARs. The first
 ARAR regards closure requirements for surface impoundments containing materials that
 migrate out of soil above levels  acceptable to EPA (i.e., TCLP level of 5.6 ppm for
 arsenic).  This ARAR  is relevant and appropriate because the four evaporation ponds
 that existed on the site during Crystal Chemical Company's operation were not closed
 pursuant  to the RCRA regulations during the  EPA Emergency  Removal Actions
'conducted on site.  All of the alternatives that call for leaving arsenic-contaminated  soils
 on the site would have to meet this ARAR. Given that Alternatives A-6, A-7, and A-8 call
 for construction of a multi-layer cap that could satisfy the requirements of this ARAR,
 these alternatives would satisfy this ARAR.  The second ARAR involves performance
 standards   for   redeposited,   treated   soil   regulated  under   the   LDRs.
 Solidification/stabilization and soil washing technologies trigger placement under the
 LDRs thus must meet the LDR treatment standard or a variance to the standard if land
 disposal is desired. Both of the  treatment technologies associated with alternatives A-3,
 A-4, A-6, and A-7 fail to treat the arsenic-contaminated soils to such a degree of success
 that they are no longer regulated  under RCRA or that they meet the performance
 standard set for the contaminant, therefore, alternatives A-3, A-4, A-6, and A-7 would
 fail to meet the LDR ARAR for  the Crystal Chemical site. If the treatment technology
 alternatives were practicable for the Crystal Chemical  site, a  variance to the  LDR
 standard would allow these alternatives to meet the LDR ARAR. However, because they
 are impracticable, no variance will be sought, and the alternatives will fail to meet the
• LDR  ARAR.  Alternative A-T because it involves the offsite land disposal of arsenic-
 contaminated soil would also fail to meet the LDR ARAR.

 The selected remedy A-8 does not trigger placement under the LDRs, and the selected
 remedy calling for construction of a multi-layer cap which will meet the ARARs for the
 site.                                                                       "
 Long-term Effectiveness  and  Permanence.   The  preferred alternative  involves
 excavation of contaminated offsite soil and capping this soil with all the onsite soil
 without  performing any treatment.   This capping  alternative provides long-term
 reductions in the amount of water that otherwise would pass through the contaminated
 soil and would continue to carry the contaminants into surrounding soils and ground
 water, and long-term reductions in the release of arsenic to surrounding soils and into

                                       18

-------
 the air. Although the direct contact risk would be eliminated with this alternative, the
 cap must be maintained to be an effective barrier.

 Alternative A-1 would eliminate the onsite and offsite risks of direct contact and the
 continued  release  of contaminants  into the  air and ground water  because  the
 contaminants would  be removed from the site.   However,  with an offsite disposal
 alternative  the problem is just being shifted  from one  site to another,  therefore,
 Alternative A-1 does not provide a permanent resolution of the problem.

 During bench scale treatability tests using actual contaminated soils from the site, the
 solidification/stabilization technology  (A-3 and A-6) failed to produce a  significant
 decrease in the amount of arsenic that is able to leach out of the treated soil or any
 decrease in  the contaminant's  volume or toxicity, therefore, use of this treatment
 technology does not provide long-term protection or a permanent solution to the arsenic
 contamination.   The soil washing technology  (A-4  and A-7)  has been able  to
 demonstrate that effective treatment can be achieved, however, the permanence of this
 technology is in serious doubt because the arsenic is just concentrated, not destroyed.
 Given that arsenic  cannot be destroyed,  the concentrated arsenic will require  land.
 disposal. Therefore, Alternative A-4 and A-7 do not provide a permanent solution to the
 contamination problem.

 The addition of a multi-layer cap to the treatment methods (A-6 and A-7) would provide
 no added long-term protection from the arsenic nor permanent solution to the arsenic
 contamination when using treatment technologies.
 Reduction of Toxicity, Mobility, or Volume of the Contaminants Through Treatment
 Two methods of treatment are proposed in this Amended Plan, alone and in conjunction
 with capping.  Alternatives A-3 and A-6 involve treatment by solidification/stabilization
 which physically and/or chemically bonds contaminants.  The site's treatability studies
.produced a treated mixture with reduced arsenic mobility (in one case, from 243 parts
 per million before treatment to 78 parts per million after treatment), but the reduction by
 only 68% of the  teachable amount of arsenic is not considered acceptable to EPA.
 Additionally, there is no evidence that the solidification/stabilization treatment process
 reduces the  toxicity  of  the  contaminants or  the volume of the  contaminants.
 Furthermore, this treatment  process increases the contaminated  soil volume  after
 treatment by approximately 10% to 30% at a minimum.

 Alternatives A-4 and  A-7 involve treatment by soil washing which concentrates the
 contaminants into the wash liquid.  The site's treatability study did produce a washed
 soil with reduced arsenic (from 243 parts per million before treatment to 23 parts per
 million after treatment). However,  the arsenic is just concentrated after treatment, not
 destroyed. Therefore, there is no reduction in the volume or toxicity of the contaminant.
                                       19

-------
The preferred alternative, A-8, does not involve treatment therefore, there is no reduction
in the toxicity, mobility or volume through the use of treatment.
Short-term Effectiveness. The construction and/or implementation of the treatment
technologies for most of the alternatives could be completed within a short time period,
that is between 2 to 4 years.  The  short-term risks for all alternatives involve dust
emission due to  the excavation of offsite soils contaminated with arsenic in  levels
greater than 30 parts per million.

Alternative A-8, the preferred alternative, would contain the contaminated soil within an
estimated 2.25 years, with the least potential for short-term community risk involving
fugitive dust emissions during excavation and construction of the multi-layer cap than
any of the other alternatives.  Two  alternatives,  A-1 and A-6, are estimated  to be
implemented in 2.5 years. Alternative A-6 also includes the  risk of dust production
during excavation and also during the treatment of the soil.  Alternative A-7 is estimated
to require 3.75 years for implementation.  It involves the risk of dust production during
soil excavation and during treatment.  Additionally, Alternatives A-3, A-4, A-6, and A-7
would involve  excavating onsite contaminated soils prior to their treatment  which
increases the potential risk to the community.
Implementability.  There  are  problems  with  both  Alternatives A-1  and  A-8 when
considering the technical and administrative issues to implementing them.  Alternative
A-1 calls for all contaminated soils both offsite and onsite to be excavated and disposed
off site.  Not  only does CERCLA discourage offsite transportation and disposal of
contaminated  materials, as in the  case of Alternative  A-1,  but also the Federal
environmental regulations discourage just capping contamination without any treatment
as with EPA's preferred alternative, Alternative A-8. CERCLA has a preference for the
use of practicable treatment technologies where  available.   However, there are
implementation problems  associated with the treatment  technology alternatives and
there are serious doubts about the effectiveness and overall benefits provided by the
technologies that  make  them impracticable  and/or inappropriate for  the  Crystal
Chemical site.

The Crystal Chemical  site  is 5  acres,  the shallow ground water (water table)  is
encountered at 15 feet, and the site is located in a part  of Houston that is prone to
flooding. In fact, the Harris County Rood Control Channel forms the western boundary
of the site.  The  most heavily contaminated  soils  which would be  excavated  for
treatment are located at the northern boundary of the site, immediately adjacent to the
soon-to-be  constructed Westpark  Drive extension, therefore, the excavation and
treatment of the contaminated soils would have to carefully coordinated. Additionally,
the solidification/stabilization treatment technology (soil alternatives A-3 and A-6), as
previously  identified, increases the volume of contaminated soil by 10% to 30% at a


                                       20

-------
 minimum.   The soil volume increase that occurs when the soils  in this  area are
 excavated is documented to be approximately 40%. This naturally occurring soil volume
 increase of 40% coupled with the 10% to 30% increase will significantly  increase the
 volume of treated soil that will require permanent storage on the site thus creating a 19
 foot high pile with alternative A-3.  Furthermore, because untreated soils will remain on
 the site, the multi-layer cap that must be constructed will add approximately 5 feet to
 the treated soil pile with alternative A-€.  Therefore, the end result could be a 9 to 15
 foot stockpile and cap.  The use of the available treatment technologies at the Crystal
 Chemical site, consequently, is impracticable and inappropriate.
Cost  The cost of the preferred alternative is $5,803,300, the lowest-cost alternative.
The highest-cost alternative is Alternative A-4 at $134,719,000.  The other alternatives
range in cost from $84,266,100 for Alternative A-1 (offsite disposal) to $9,236,800 for
Alternative A-6 (solidification/stabilization and capping).
State Acceptance.  The State of Texas, through the Texas Water Commission, was
given an opportunity to comment on the Amended ROD, however, they did not provide
any comments to EPA.
Community Acceptance. The community has voiced limited support for the Capping
remedy for the soil contamination at the Crystal Chemical site.
VIII. SELECTED REMEDY

Based on consideration of the requirements of CERCLA, the detailed analysis of the
alternatives, and public  comments, EPA has determined that soil alternative  A-8
(Capping) is the most appropriate  remedy for the arsenic-contaminated soils at the
'Crystal Chemical site in Houston, Texas.

The remediation goal selected for the offsite arsenic-contaminated soils and sediments
is protective of human health and welfare and the environment  The goal was selected
to eliminate or reduce risks associated with potential exposure to the contaminants via
ingestion or direct contact with soil, sediments and surface water, and inhalation of wind
dispersed dust.  The goals for the soil contamination call for the removal of offsite soils
and sediments to a concentration of 30 ppm for arsenic, which represents a one in one
hundred thousand (10*9)  excess cancer risk level. These soils will be placed back on
to the Crystal  Chemical site.

Approximately 55,000  cubic yards  of offsite soils and sediments contaminated with
arsenic above 30 ppm will be excavated and brought back on to the site. In order to


                                       21

-------
ensure that all offsite soils and sediments contaminated with arsenic greater than 30
ppm from the Crystal Chemical site are identified, offsite areas previously identified as
contaminated will be resampled to verify the need for excavation. This will include, but
will not be limited to, adjacent properties, the Harris County Rood Control Channel, and
all properties potentially affected by drainage from the site by way of the flood control
channel.

During the design phase of the remedial action for the  Crystal Chemical site, an
evaluation defining the relationship between the contaminated soils and the ground
water will be conducted.  From this evaluation a determination will be made by EPA
regarding the potential success of achieving the remediation goal of 0.05 ppm of arsenic
given no  source control at or below the ground water table. Given that there  is heavily
contaminated arsenic-contaminated soils  at or near the shallow  ground water, the
necessity of the excavation of these soils during remediation will be evaluated.
IX.  STATUTORY DETERMINATIONS

Under its legal  authorities,  EPA's primary responsibility at Superfund sites is to
undertake remedial actions that achieve adequate protection of human health and the
environment. In addition,  Section 121  of CERCLA establishes several other statutory
requirements and preferences that the selected remedy must meet.  Section 121 of
CERCLA specifies that when complete, the selected remedial  action for this site must
comply with ARARs established under Federal and State environmental laws unless a
statutory waiver is justified. The selected remedy, also, must be cost-effective and utilize
permanent solutions and alternative treatment technologies or resource recovery
technologies to  the  maximum extent practicable.  Finally,  the statute includes  a
preference for remedies that employ treatment that permanently and significantly reduce
the volume, toxicity, or mobility of hazardous wastes as their principal element.  The
following  sections discuss  how  the  selected soil  remedy  meets  these statutory
requirements.
Protection of Human Health and the Environment

The selected soil remedy protects human health and the environment by excavating all
offsite soils contaminated with arsenic above 30 ppm, placing these soils back on to the
site, and by capping the entire site.  The site will be covered with a multi-layer cap to
act as a barrier that restricts the flow of water through the soils, prevents the release of
soil and contaminants into the air, and prevents direct contact with the contaminants.
Site access and land use restrictions prohibiting soil removal and any commercial or
residential activity will be implemented.
                                      22

-------
Removing all offsite soils and sediments contaminated with arsenic greater than 30 ppm
will eliminate the threat of exposure from direct contact with the contaminated soils
outside of the current boundaries of the site. The current risks associated with these
exposure  pathways from the contaminated soils are unacceptable.   Therefore, the
residual contamination  outside the current boundaries of the site after the completion
of the offsite portion of this  remedial action  will constitute a one in  one hundred
thousand (10'*)  cancer  risk  level. The construction of the cap over the  entire site will
eliminate all  threats relating  to direct  contact with and inhalation  of the  residual
contamination, and will act  as a barrier restricting the flow of water through the soils.
This will reduce the risk posed by this site to less than one in one million  (10"*).  EPA
policy calls for remediation levels that range from a cancer risk of one in ten ttiousand
to one in one million (10"4 to 10"^.  There are no short-term threats associated with the
selected remedy that cannot be readily controlled.  Further,  no adverse cross-media
impacts are expected from the soil remedy.
Compliance with Applicable or Relevant and Appropriate Requirements:

The selected soil remedy of excavation of offsite arsenic-contaminated soils greater than
30 ppm, placing these soils back on to the site, and capping the entire site will comply
with  all applicable relevant and appropriate action-, chemical-, and location-specific
requirements ("ARARs"). The ARARs are presented as follows:

Action-specific Soil Remediation ARARs:
      Applicable Resource Conservation and  Recovery Act ("RCRA") requirements for
      landfill closure,  40 CFR 264.111  Subpart G,  which  specify  a cap with a
      permeability less than  or equal to the permeability of any bottom liner or natural
      sub-soils  present at  the  site.    In  addition,   applicable  specific closure
      requirements which are provided for surface impoundments, 40 CFR 264.228
      Subpart K, and applicable requirements for landfills. 40 CFR 264.310 Subpart N,
      may also apply.

      Post-closure and monitoring applicable requirements for 30 years or another
      period determinedly  the Regional Administrator, 40  CFR 264.117 (a)(1).

      Applicable ambient air quality standards per 40 CFR  50 to protect the quality of
      the air during the implementation of the remedial action.

Chemical-specific Soil Remediation ARARs:
      As required by the Clean Water Act ("CWA") (33 CFR 303), onsite surface water
      must meet applicable ambient water qualify criteria for arsenic (0.0175
                                      23

-------
 Location-specific Soil Remediation ARARs:
       Applicable RCRA requirements, 40 CFR 264.18, for location of a Transportation,
       Storage or Disposal  ("TSD") facility in a 100-year floodplain, and also general
       applicable requirements for protection of floodplains, 40 CFR 6, Appendix A.
 Cost-Effectiveness:

 The selected soil remedy is cost-effective because it has been determined to provide
 overall  effectiveness proportional to its  costs,  the net present  worth  value  being
 $5,803,300.  While the selected soil remedy effectively reduces the hazards posed by
 contaminants at the site, its costs are only 7 percent of the alternative involving total
 excavation and offsite disposal, $84,266,100.
 Utilization  of   Permanent   Solutions   and   Alternative   Treatment
 Technologies  (or  Resource Recovery Technologies) to the  Maximum  Extent
 Practical:

 EPA has determined that the selected soil remedy in conjunction with the ground water
 remedy selected in the 1990 ROD represent the maximum extent to which permanent
 solution  and treatment technologies can be utilized in a cost-effective manner for the
 source control and remediation at the Crystal Chemical site.  The soil remedy selected
 in the  1990 ROD which consisted of using the ISV treatment technology remains to be
 the best alternative to address the arsenic contamination at the site.  However, the ISV
 technology is not available at this time, and it is not known  when the technology will
 again  become available for use at the Crystal Chemical site.  Therefore, of those
 alternatives that are available, protective of human health and the environment, and
 comply with ARARs, EPA has determined that the selected soil remedy in conjunction
 with the ground water remedy selected in the 1990 ROD provide the best balance of
 trade  offs  in terms  of long-term effectiveness and permanence,  reduction in toxicity,
-mobility,   or  volume   achieved   through  treatment,  short-term  effectiveness,
 implementability, costs, also considering the  statutory preference  for treatment as a
 principal element and considering State and community acceptance.

 The selected remedy calls for capping all of the  arsenic-contaminated soils above
 acceptable health-based levels, which is soils contaminated with arsenic above 30 ppm.
 The cap itself acts as a barrier that restricts the flow of water through the soils which  are
 not  subjectecMo water table conditions,  prevents the release  of soil  and residual
 contaminants into the air, and prevents direct contact with the arsenic contamination.
 Because the ground water extraction and treatment remedy selected in the 1990 ROD
 will  be implemented, the arsenic contaminated soils below the ground water table  will
 be treated. Through the extraction of the contaminated  ground water, this source of
 arsenic contamination will be eliminated. The arsenic contaminates adsorped to the  soil


                                       24

-------
process and extracted for treatment.  The desorption and extraction of the arsenic will
make less arsenic available thus eliminating the source of arsenic contamination within
the ground water saturated zone and thus preventing further or continued release into
the ground water.

Although the capping remedy provides long-term reductions in the amount of water that
otherwise would pass through the contaminated soil thus creating long-term reductions
in the release of arsenic into the environment, the cap must be maintained to be an
effective barrier.  The selected remedy will meet the ARARs for the site and is easily
implemented, but will not provide in reduction of toxicity,  mobility,  or volume  of
contaminants through treatment. It is a cost-effective remedy, and it has been accepted
by the community. The State of Texas, through the Texas Water Commission, however,
did not provide any comments to EPA on the Amended ROD.
Preference for Treatment as a Principal Element:

EPA's selected soil remedy does not use treatment, however, the ground water remedy
selected in the 1990 ROD does utilize treatment to address the arsenic contamination
at the site at and near the ground water zones. The alternatives investigated for this site
that employ treatment would satisfy CERCLA's preference for remedies that employ
treatment that permanently and significantly reduces the volume, toxicity or mobility of
the hazardous substances,  pollutants,  and contaminants  over  remedies that do not
employ such treatment.  However, the treatment technologies available for the Crystal
Chemical site do not afford a greater overall benefit because of the problems associated
with implementing them thus making them impracticable for the Crystal Chemical site.
Therefore, doing  treatment  for the sake  of  doing  treatment using the  available
technologies does not, in this case, appear to be appropriate or beneficial.
X. DOCUMENTATION OF SIGNIFICANT CHANGES

The Amended Proposed Plan for the Crystal Chemical site was released for public
comment in February 1992. The Amended Proposed Plan identified soils alternative A-8
(Capping) as the preferred alternative for the site. EPA reviewed all written and verbal
comments submitted  during the public comment  period.  Upon review of  these
comments, it was determined that no significant changes to the remedy, as it was
originally identified in the Amended Proposed Plan, were necessary.
                                      25

-------
                   CRYSTAL CHEMICAL COMPANY SITE
                       RESPONSIVENESS SUMMARY

The Community Relations Responsiveness Summary has been prepared to provide
written responses to comments submitted regarding the Amended Proposed Plan at the
Crystal Chemical Company site.  The summary is divided into two sections.

Section I.    Background of Community Involvement and Concerns.   This section
provides a brief history of community interest and concerns raised during the remedial
planning activities at the Crystal Chemical Company site.

Section II.  Summary of Maior Comments Received.  The comments (both oral and
written) are presented and EPA's responses are provided.
I. Background of Community Involvement and Concerns

The community  has been involved on a iimited basis with activities at the Crystal
Chemical Company site. Members of the community attended the open house and the
public meeting in limited numbers, however, approximately 300 people receive mailings
from EPA on Crystal Chemical  Company site activities.  The comments that were
received from the local community concentrated on possible inconveniences that might
be experienced during and following the completion of the remedial action.
II.     Summary of Maior Comments

Public notice announcing  the public comment period  and the public  meeting was
published in the Houston Post on February 12, 1992. The Amended Proposed Plan
was distributed through the mail in early February 1992, and the public comment period
began on February 24, 1992 and ended on March 24, 1992.  An informal Open House
was held in the area near the site on February 20,1992.  The public meeting was held
on March 19, 1992 at the Westchase Hilton and Tower Hotel in Houston, Texas. The
purpose of this meeting was to discuss all the available alternatives and EPA's preferred
alternative for the soil contamination at the Crystal Chemical Company site.

Approximately 15 people attended the public meeting and three (3)  people asked
questions or made comments. Four (4) sets of written comments were received during
the public comment period.

A. Comments and Questions received during the Public Meeting.

EPA received oral comments during a public meeting held at the Westchase Hilton and
Tower Hotel on March 19, 1992.   Comments pertinent  to EPA's Amended  Proposed


                         Responsiveness Summary  1

-------

-------