ITAV                                                     906R84101
  8605-0042     < ^  „
L.
r
\
                               Environmental Law Institute

                              3346 Connecticut Avenue, N. W.               i ?r>^, c S
                                                                       I u^l'rl^ll
                                  Washington D.C. 20036
COMPENDIUM OF COST OF REMEDIAL TECHNOLOGIES

           AT HAZARDOUS WASTE SITES
                                        DRAFT

                                    FEBRUARY 1984
                  A Report to the Office of Emergency and Remedial Response
                           U.S. Environ mental Protection Agency
                                     Project Officer:
                                    Mr. Bruce Clemens
                                        WH-586
                                    401 M Street, S.W.
                                 Washington, O.C. 20460

-------
                                       DISCLAIMER
L
I
r
      This report has been reviewed by the Office of  Emergency and  Remedial
Response,  U.S.  Environmental  Protection  Agency,  and  approved for  publication.
Approval does not signify that the contents necessarily reflect the views and policies of
the  U.S.  Environmental  Protection  Agency,  nor  does mention of trade names or
com mereial products constitute endorsement orrecom mendation for use.
f

-------
                                   ACKNOWLEDGEMENTS
 L
\
 C
            The Environmental Law Institute (ELI) prepared this report under a subcontract
      with JRB Associates of McLean, Virginia for the US  EPA*s Office of Research and
      Development,  Municipal Environmental Research Laboratory, Solid and Hazardous Waste
      Research Division and the Office of Emergency and Remedial Response.  This report was
      prepared under the  direction of Dr.  Edward C. Yang,  Director of  ELPs Resources
      Program, by James D. Werner, Environmental Scientist for the ELI Resources Program.
      Mrs. Nuran Giampaolo of ELI and Ms. Diane Simmons of JRB Associates provided the
      administrative support for the project.
            The project team greatly appreciates the overall  guidance of the JRB project
      manager, S. Robert Cochran, and the EPA Task Managers, Bruce Clemens and Douglas
      A m mon,  for their assistance and support.

-------
f
                                   TABLE OF CONTENTS


                                                                             Page

      1*0  INTRODUCTION	1

      2JO  Surface Water Controls
            .  2.1 Surface Sealing •«..*	7
              2,2 Grading	17
              2.3 Drainage Ditches	21
(              2.4 Revegetation	.............25

      3JO  Groundwater and Leachate Controls
              3.1 Slurry Wan.	31
              3.2 Grout Curtain (Aspemix)	42
              3.3 Sheet Piling	50
              3.4 Grout Bottom Sealing	54
r             3.5 Permeable Treatment Beds	57
              3.6 WeH Point System	61
t              3.7 Deep  Well System 	64
              3.8 Extraction/Injection Well System  .:	68
f ~             3.9 Extraction Wens/Seepage Basins	74
'              3.10 Subsurface Drain	76

      4dO  Aqueous and Solids Treatment
              4.1 Activated Sludge	86
              4.2 .Anaerobic, Aerobic & Facultative Lagoons	91
              4.3 Rotating Biological Contactors	97
              4.4 Air Stripping'	101
              4.5 Carbon Treatment	 107
i '             4.6 OiVWater Separator	ll4

-------
                                                                           Page
      Table of Contents (continued)
j     SbO  Gas Migration Control
              5.1  Pipe Vents	120
              5.2  Trench Vents	123
              5.3  Gas Barriers	127
              5.4  Carbon Adsorbtion	131
f
      ao   Material Removal
[              6.1  Excavation/Removal, Transportation
                  and Disposal ••••.....••««•••••••••«••••.•«••.«••«.• 137
              6^  Hydraulic Dredging	 160
              6L3  Mechanical Dredging	165
              6.4  Drum Handling	 169

      7.0   Water ft Sewer Line Rehabffltatioa
              7.1  Sewer Line Replacement	175
              7.2  Sewer Line Repair	178
1              7.3  Water Line Repair	182
              7.4  Water Main Repair	1	185
I
      &0   ATtematiye Water Supplies
              8.1  New Water Supply Wells	188
              8.2  Water Distribution System	191

      00   REFERENCES	194

I/    '

-------
                            LOST OF TABLES
Table*   Title                   '                                   Page

1.        Levels of Personal Protection	5
2.        Average Percent Increase for Total Costs
          at four Degrees - of - Hazard Levels	6
3.        Surface Seal Expenditures	.-	10
4.        Surface Seal Cost Estimates	13
5.        Surface Seal Costs:  Material Variations	16
6.        Grading Cost Estimates	20
7.        Diversion Ditch Cost Estimates	.......23
8.        Revegetatlon Cost Estimates	27
9.        Slurry WaH Expenditures	.34
10.       Slurry Wall Cost Estimates	37
11.       Slurry Wall Costs: Depth Effects	40
12.       Grout Curtain Expenditures	45
13.       Grout Curtain Cost Estimates	 46
14.       Sheet Piling Cost Estimates	53
15.       Grout Bottom Sealing Estimates	56
16.       Permeable Treatment Bed Cost Estimates	60
17.       Well Point System Estimates ...I.....	63
18.       Component Cost of Deep WeH Estimates	66
19.       Deep Well Cost Estimates	67
20.       Extraction/Injection Well Cost Estimates	......69
21.       Extraction Wells/Seepage Basin Expenditures	73
22.       Extraction Wells/Seepage Basin Cost Estimates	75
23.    •  Subsurface Drain Expenditures	 79
24.       Subsurface Drain Cost Estimates	33
25.       Activated Sludge Expenditures	39
26.       Activated Sludge Cost Estimates	90
27.       Anaerobic, Aerobic and Facultative Lagoons
          Cost Estimates	.....94
28.       Rotating Biological Contactor Cost Estimates	99
29.       Air Stripping Expenditures	104
30.       Air Stripping Cost Estimates	105

-------
L
      Table*       TltJp                                                     Page

           31.       Carbon Treatment Expenditures	109
           32.       Carbon Treatment Cost Estimates.	Ill
           33.       OH/Water Seperator Capital Expenditures	 116
           34.       CH/ Water Seperator Expenditures	117
           35.       Oil/Water Seperator Cost Estimates	120
,          36.       Pipe Vent Cost Estimates	122
           37.       Trench Vent Cost Estimates	125
f          38.       Gas Barriers Cost Estimates	130
i
           39.       Gas Treatment Expenditures	133
           40.       Gas Treatment Cost Estimates	.,	134
           41.       Excavation Expenditures	141
           42.       PCB Excavation Expenditures	146
           43.       Transportation Expenditures	150
           44.       Excavation Cost Estimates	153
           45.       Estimates from Engineering
                    Construction Manuals	 155
L-          46.       Transportation Cost Estimates	156
*          47.       Average Transportation Costs
                    by Type of Transporter	157
i           48.       Averages of Hazardous Waste Management
                    Quoted Prices for AIL Firms in 1980
                    and for Nine Major Firm sin 1981	159
'           49.       Additional Related Cost Items
                    Estimated for Hydraulic  Dredging	162
i           50.       Hydraulic Dredging Cost Estimates	163
           51.       Additional Costs to Basic
                    Mechanical Dredging	167
           52.       Mechanical Dredging Cost Estimates	168
           53.       Drum  Handling Expenditures	173
V          54.       Sewer Line Replacement Cost Estimates	177
           55.       Sewer Line Repair Expenditures "	„	180
|           56.       Sewer Line Repair Cost Estimates	 181
           57.       Water Line Repair Cost Estimates	184
           58.       Water Line Replacement Cost EstimaTes	187
           59.       New WeH Cost Estimates	 190
           60.       Water Distribution Cost Estimates	193

-------
                                         SECTION 1
                                     U)  INTRODUCTION
i

\      LI   OVERVIEW
(            Response cost Information is critical to several aspects of implementation of the
.-    Comprehensive  Environ mental  Response, Compensation and  Liability  Act of  1980
1      (CERCLA), known as Superfund. These aspects include:

'             o   Selecting cost-effective response alternatives
             o   Documenting reasonable costs for cost recovery
             o   Budgeting for fund balancing

V    The purpose of this Cost Compendium is to sum raarize existing  cost information for
      these uses.  Actual expenditures and. estimated costs are both given to assemble data
      from all available sources into this one data base. The im mediate use of this centralized
      source of cost information is to provide consistency in various site-specific costing tasks
      such as:  remedial alternative  costing called for in the Feasibility Study  Guidance
      Document (FSGD), and budgeting for immediate and planned removals.  This compendium
      should be viewed as the first installment of an ongoing data base, which wfll be updated
      periodically as  more cost information becomes available from completed Superfund
      responses.    Cost data  in  this  compendium  are  organized according  to related
      technologies, such as "Ground Water  Controls" (see Table of  Contents).  The cost given
      are for technologies that have been most com monlv used at uncontrolled hazardous waste
         »
      sites, although some rarely used technologies are given because estimates are frequently
      given.  Com m'only used technologies  may have been excluded because  of the paucity of
      data.   Typically, however,  the number of estimates and  the depth of  background
      information are often proportional to the frequency of use of the technology. In addition
      to the organization of cost data according to technologies, several other features at this
      cost compendium, which merit highlighting are sum marized below.
1
r
                                            -i-

-------
           ACTUAL EXPENDITURES VERSUS ESTIMATES
            Most  available cost Information  is  from  engineering  esti.rr.a-2s.   Few such
<     estimates have been field tested, however.  Preliminary comparison of these estimates
     with  actual  expenditures has shown significant differences in  many cases (ELI/JRB,
<     1983).  Since merging these two types of data would be misleading to the reader, this
1     compendium   separates,  ex  ante,  engineering  estimates  from  actually  observed
     expenditures.  Although actual expenditure data,  which has been "ground truthed", are
     generally more reliable than estimated cost data estimates are useful because they
     broaden the range of site characteristics and technical circumstances for which costs are
I     available.  The factors that were included in deriving the cost estimates  may reflect a
     situation that  more closely parallels the Intended use of the cost data than any of the
     situations for which actual expenditure data are available.

     L3   FOCUS ON UNIT COST
            Data are given in a unit cost form, in terms of dollars per unit operation, such as
.     cost per square foot of slurry wall, or cost per gallon of treated water. Since the units
     used  are important, consideration  was  given to the selection to ensure that they were
     useful and/or standardized throughout the industry.  English measure only are used for
T    simplicity.  These unit costs typically include aH related, costs such as material, labor,
     and equipment and other capital costs.  Operation and labor costs are given when they
i-    are applicable and available.
           INCLUSION OF SUM MART AND RAW DATA
            This compendium organizes cost data Into two levels: (1) sum mazy data, and (2)
      raw data.  On the first level, sum mary data such as range, and when possible, mean and
      standard error are given. This is simply a sum mation of the raw data and should be used
      only for very general  cost screening and  budgeting.  The wide  ranges of these data
      sum maries, and the lack of background explanation on tills level render it unsuitable for
      more specific costing purposes.  Such specific cost estimation should use raw data, on the
I     second level, which provides more detail on the data compilation. This detail can be used
      for matching to the circumstances at the site for which it is to be  used.  The user should
' "•     compare the site circumstances to the  factors given in the raw  data to estimate the
      effect of these factors on the estimated cost.
                                             -2-

-------
      U5  FACTORS FOUND TO AFFECT COSTS
 1            A fundamental concept of estimating technology costs is that a variety of factors
      influence these costs.  This compendium rtlsqgsses these factors for each technology.
 I     This brief discussion of the effects of these factors reflects the descriptive detail given
      for each data source in the tatite of raw data. For actual expenditure data, the essential
      site characteristics  are  typically  described.    For  estimated  costs,  these  site
      characteristics are drawn from a hypothetical site scenario that is usually established for
      the purpose of making necessary assumptions for estimating costs.  The level of detail
      available for actual site characteristics and hypothetical site scenarios varied widely.
1.
L
           CONSTANT 1982 DOLLARS
            Since the source data, on which this compendium is based, originated in different
      years between 1975 and 1982, all costs were indexed to constant 1982 dollars using the
      Engineering News Record construction cost index.  This index relects the weighted cost
      trend of common labor (74%), structural steel (15%), lumber (9%), and portland cement
      (2%).  Data from 1983 documents were not deflated to 1982 dollars for two reasons.
f     First, most of the actual costs for 1983 were actually incurred in 1982 or estimated for
      1982 dollars. Second, the change in the EN R index between 1982 and 1983, is expected
      to be very smalL

      L.7  COST OF HEALTH AND SAFETY PROTECTION
            One of the key factors affecting the costs of responses at uncontrolled sites is the
      level of protection  for health and safety of on-site workers.   The level of hazard
      determines the type of protective measures the workers must take, which ultimately
      affects  the cost of the response.  Many of the data sources used in this compendium,
      however, did not explicity note health and safety concerns.   For actual expenditures, the
j
      cost data already include  whatever protective measures were taken at the site. Often,
|      however, the available information on the response action did not fully describe the
      protective measures.  This defect may be corrected by further research.  For estimates,
I      health and safety assumptions are usually less clear than expenditures. In only one case
      did the estimator explicitly consider the cost effect of various protective measures.
t-           SCS Engineers recently completed  a study on the  cost  of health and 'safety
      protection, for the  U.S.  EPA  Office of Research and Development.   For studv, six
      cleanup firms ^ere asked to bid on six hypothetical uncontrolled site scenarios with .five
      levels of personal protection (see Table l\  The key results are presented in Table 2, and
      more details are given in the SCS report.  In using Table 2, several items should be kept
                                                                              *
                                             -3-

-------
 i
 \     in mind.  First, the results are from a final draft version of the SCS report.  Additional
 i
      changes may be made to the results.  Second, the validity of the result.- depends on how
 ]     seriously  the bidders took  the hypothetical scenarios  and whether che bidders were
      neutral in providing the estimates (Le., free from  motives that  may misrepresent the
I      costs).  And finally, the technologies in Table 2 do  not always  match the ones given in
      this compendium.
I
r
r
                                              -4-

-------
I
r
                                          TABLE 1

                            LEVELS OP PERSONAL PROTECTION
1.    Level A - requires full encapsulation and protection
      from any body contact or exposure to materials (Le.,
      toxic by Inhalation and skin absorption).

2*    Level B - requires self-contained breathing apparatus
      (SCBA),  and cutaneous or  percutaneous exposure to
      unprotected areas of  the body  (Le., below  harmful
      concentration).
          3.     Level C - hazardous constituents known; protection
                 required for low level concentrations In air; exposure of
                 unprotected body areas (Le., head, face, and neck) is not
                 harmfuDL

          4.     Level D - no Identified hazard present, but conditions
                 are   monitored   and  minimal  safety equipment is
                 available.

          5.     No hazard protection - standard base construction costs.
          Source:   "Interim Standard Operating Safety Guides,"

                    EPA, 1982.
                                            -5-

-------
1
                    TABLE 2.

AVERAGE PERCENT INCREASE FOR TOTAL COSTS A7
        POUR DEGREE-OF-HAZARD LEVELS*
L
I
r
Unit Operation
Surface Kiter Controls:
1. Surface Sealing - Sythetic Heabrene
2. Surface Seal ing . Clay
3. Surface Sealing « Aspna It
4. Surface Sealing . Hy Ash
$. Hevegetation
(. Contour Grading
7. Surface Hater Diversion Structures
1. Basins and Ponds
*. Dikes and ler*s
Cround Kiter Controls t
1. Hell Point Systct)
I. Deep Hell System
3. Drain Systen
4. Injection Systea
S. lent on Ue Slurry Trench
I. trout Curtain
7. Sheet Piling Cutoff
1. Crout 8ottOB Sealing
Cas (deration Controls:
1. Passive Trench Vents
2. Passive Trench larrters
3. Active Cas Extraction Systems
Haste Controls:
1 Chentcal risitlon (Solidification)
2 Chr*1ei1 Injection
3 Cicavatlon of Hastcsftontonlnatetf Soil
4 Irachate ftectrculatlon
S Treatwnt of Contaminated Hater
t Prun Processing
7 lulk Tank Processing
8 Transformer Processing • •
•Mn
1141
109S
1171
122S
13SS
12SS
1SOS
not
1287
loss
~
im
3071
1191
2011
ins
UreJC
119S
11 91
1331
1441
1381
1731
1171
1381
mi
^
1291
3371
1211
2281
2481
2931
level 8
1221
1241
1261
1401
1511
1451
176S
1211
1431
1321
•e*
1331
3971
1»S
2(41
4191
teveT X
1241
1271
128S
1461
1541
1501
1861
1281
.1481
13C1
~
1371
7?S1
1281
3171
5491
             *
             •*•
     Values given include 100 percent for base construction costs.
     Tnis unit operation was deemed appropriate for performance
     cnly at Level C. Costs at Levels D, B, and A were not provided.
      Source:   "Worker Health  and Safety Considerations:   Cost of
      Remedial  Actions at Uncontrolled Hazardous Waste Sites",
      Draft  Final Report, 1983.  SCS Engineers  for US EPA,
      Covington, ICY
                                        -6-

-------
                                                                Surface ' ater Controls
                                                                Surface Sealing
L
I
                                          SECTION 2

                               2JO SURFACE WATER CONTROLS
      2.1 SURFACE SEALING

{      2.1.1    Definition
      Surface sealing (capping) involves covering a site with any of a variety of materials,
/
!      including day, asphalt, cement or a  synthethic  membrane, to prevent surface water
      infiltration, control erosion, and/or mitigate volatilization from contaminated waste.

      2.U2    Units of Measurement
      Cost per unit surface area is used, generally, because area best expresses the functional
      attribute of  a cap.   Cost per square yard is used  specifically  because  it is readily
      converted to  acres (X 4,840), sq.ft. (S/9) and cubic yard volume (X depth in yards).

      2.L3    Sum mazy Statistics

      2.1*3.1     Expenditures
      The actual costs of surface seals ranged from:
                 $0.92/yd.2 - 4" thick, loam
                     to
                 $ 15.84/yd.2 - 6" thick, clay

      The surface seals for which actual costs are given reflect site specific characteristics,
      such as design parameters and local material avaflahflity. The highest cost seal involved
      an engineered cap with careful quality control for clav/water content.  The lowest cost
      cap was constructed  with on-sLte  clay  that required only hauling and  compacting
      expenditures.
             Operation  and maintenance  costs  involved ground water monitoring, inspection
      and, possibly, repair  costs. These costs were either accounted for separately or had  not
      yet been encountered in these new caps.
                                             -7-

-------
I

I
                                                                Surface V ater Control
                                                                Surface Sealing
      2.1.3.2     Estimates
            The eight cost estimates for surface seals ranged from:
                 $1.32/yd.2 -        geotextfle, level B protection
                   to
                 $16.88/yd.2-      'sand/hypalon/loam

f-
      Operation and maintenance costs Involving ground water monitoring and cap inspection
i
      were generally not Included in the estimates.  However, the following in 0& M costs were

      Included in the Radian estimate:
           Item                                   Cost
           Annual Inspection                       $500/year
           Mowing/Revegetation                   $600/year/acre
(           Erosion control and drainage
]          maintenance                     '      S200/year/acre
           Repairs resulting from shrink
1           swell or freeze/thaw forces              $200 costs/year
           construction


      The extremes  of the range  of estimated costs are represented  by a  very  simple
      temporary cap  at the low end and a more complex, three element cap, intended to be
«      permanent, at the highest cost end.


I      2.1v4   Factors Found to Affect Costs


i      2.1.4.1     Expenditures

      Generally, the following salient factors affected the surface seal costs:
f           o  Cap material:

                 bentonite/clay
                 asphalt
                 concrete
                 synthetic membrane
                 loam
                                             .8-

-------
                                                                Surface Ya.-*r Control
                                                                Surface Ser
 I
 f
o  Related material costs:
      top gravel
      gravel bed
      curbs
      membrane anchor son
o  Dimensional variations:
      thickness
      area covered
      The factors affecting the actual costs of surface seals, as outlined above and given in
      Table 3 are generally divided into "Material variations" and "Dimensional variations".
      They are presented here only to provide a rough background explanation of the costs for
]     general comparison purposes, and not to specifically delineate the proportional effect of
      particular cost components. It is not possible to determine from the data if there was a
<     significant general cost difference between clay and asphalt caps.  Although the costs at
      the California site suggest no significant cost difference, other sites had significant cost
      differences. These differences, however, may have been due to anomolous local material
i     availability or other factors.  The number of observations were inadequate to make any
      clear conclusions.  Variations  in the costs for related  materials may have affected the
] r    total costs of the various caps. The cost of the bentonite-soil cap at the California site
      included  the cost of the 6-inch (0.15 m) cover of 3/4-4nch (1.9 cm) gravel to prevent
      erosion of the cap. The cost of the curbs for run-off control at the California site was
      not included in the total reported cap cost, but curb installation may have caused a cap
      cost increase not incurred In the other sites lacking this feature, due to delays for sealing
      these seams.'  The use  of a synthetic  membrane required less heavy  construction
I      equipment for deployment, although soil anchors were used.  The cap for the  New
j
<      Hampshire site may also be considered an element of revegetation, but it also had a role
      in snfl stabilization.
                                             -9-

-------
:

             0
             b
             0
O

Q
                                       -10-

-------
         •tl
         Ol

         e
    L    §


•    :
        g
    I.
e-
8
z



M
K
£
8
CO
i
X
o
M
£


J
M
tt
1!
•H

a

K

<
£4
^
A




X
CD
55
e*»
•
tr
e
o
«>
s

4J -H
0 .0
c «

4 -H
Id >
•D «
c
jj
i
u
4J
5
-



1-1
^4 ^«
S3 ^
< o


-------
 L
 r
                                                        Surface Water Control
                                                        Surface Sealing
Finally, the cap dimensions—thickness and area covered—appeared to affect cap unit
costs.  Increased cap thickness and area generally added to cap costs by increasing the
volume of  cap material required and  the amount of grading.   An exact generalized
function for this relationship cannot be determined from the available data. The unit cap
cost, however, is also affected by economies of scale.

2.1.4.2     Estimates
Generally, the following factors affected the estimates:
     o  Component material type:
           clay
           soil
           synthetic liner
          o  Number of components:
                single component
r              composite
          o  Dimensional variations:
?                thickness
                area covered
                                                  *
I    Generally, cost estimate information (see Table 4) was less detailed than the data for
     actual cost; however, salient information usually was available.  Scenarios from generic
     engineering-construction cost manual estimates (JRB,  SCS, Radian) and  feasibility
     studies were unable to predict unexpected changes occurring during the response.

     As in the actual costs, components affecting the costs were generally qualitative and
     quantitative - "Component  material costs" and "Dimensional variation," respectively.
U   Four types of materials were assumed in the various estimates: clay, soil, synthetic liner
     and sand. The more significant consideration, however, was the  number of components
     assumed for the  estimates.  Typically, additional component costs in composites were
     assumed to be additive.  Again, the dimensional variations affected both the volume of
     surface material required and the economies of scale.  Increased cap thickness requires
     more volume per area.  By using  mobilized grading and compacting equipment at a
     relatively small additional marginal cost, caps with a larger area had the advantage of
     greater economies of scale.
                                           -12-

-------

i   ?   <
T   ^   w
 f       0)
          s
         eo
         o\
^
en
fr-
8

t-
w
o




u
u
>
Q
o

CO
s


M


jj
K
P
c

«
O1
CO
o
o
CO
*


a
9 •
JZ t-t 4J
CJ -H Q
c E 6
o
CD 1*1 ^»


h
4)

l|
-H js a






si
M 1 0
sa • CD
tO OS O\


,

>,
*
^
^
CO
*
Si
i
jf
o
o
CO
A


a
4) *
O -H O
C E ^
O
CD **1 ^
-

^
4)
>
l|
ill
•H jc m






< e
eu a
a -H .-M
•O 00
CO CQ O1^
S OS fH


•
CT
CO

fH
•
1
CD
in
S
*
o-
CD
in


-------
p
       •o
       01
       g
       o
       u
a
P
(B
i
M
Z
9



C5
Si
1>
Q
Q


«n
1
Sj
H
E


HI
et

C*
£







U

Q
CO

^
gj
o

x
V
n
ON
vO
i

tr
r-
en
in

in


tt
|
**^

•n




•
O 01
e 4J
|S
3 O
•w e
•H O
ja u






X
4)
a
o- ,_ n
5 2 *
W U O» Ol
a z 
» 5 £ S Z
i
IT

U M
B
•H 4J
O
00 B
14

>
o

•H -H
•fj ^
«H X
£ 0>
JJ 4J
t4 0
0 01
Ol O>
X
•o
3
to

^,
^H xj' ^.
•H -H ."U
•H « £0
B •* U
< ja «
6 «ss»
c/5 s oi en u
3 U h, 
-------
I

Ir
                                                              Surface * ater Control
                                                              Surface S
1    The Radian estimates given  Table 5 are based  on using  the following  list of cost
    components to construct a surface seal, the same specifications were established in the
    JRB-RAM scenario.
                TABLES. SURFACE SEAL COSTS:  MATERIAL VARIATIONS

                                                                  Cost

                                                                  $15/yd.3
          Direct Capital Cost Kerns:
          Topsail (sandy loam), hauling, spreading,
          and grading (within 20 miles)
          Clay hauling, spreading, and compaction

          Sand hauling, spreading, and compaction


          Portland concrete (4 - 6" layer), mixed,
          spread, compacted on-site

          Bituminous concrete (4-6" layer),
          including base layer

          Lime or cement, mixed into 5" cover soil

          Bentonite, material only; 2" layer, spread
          and compacted

          Sprayed asphalt membrane (1/4" layer and
          son cover), installed

          PVC membrane (20 mil), installed

          Chlorinated PE membrane (20-30  mil), installed

          Elasticized polyolefin membrane,  installed

          Hypalon membrane, (30  mil), installed

          Neoprene membrane, installed

          Ethylene propylene rubber membrane, installed

          Butyl .rubber membrane, installed

          Teflon-coated fiberglass CTFS) membrane
          (10 mil), installed

          Fly ash and/or sludge, spreading, grading,
          and rolling
                                                                    $10/yd.3

                                                                    $18/yd.3
                                                                  ($9-12,000/acre)


                                                                  $9 - 15/yd.2


                                                                  $4.50- 7.25/yd.2

                                                                    $2.15-3.00/yd.2


                                                                  $1.90 yd.2


                                                                  $2.00 - 3.40/yd.2

                                                                    $1.75 - 2.70/yd.2

                                                                    $3.25-4.30/yd.2

                                                                    $3.10-4.15/yd.2

                                                                    $7.40/yd.2

                                                                  $7.25/yd.2

                                                                    $3.50-4.70/yd.2

                                                                    $3.60 - 5.10/yd.2


                                                                  $23/yd.2


                                                                  $1.50 - 2.50/yd.2
                                           -15-

-------
f
                                                                 Surface Water Control
                                                                 Jurfacg Sealing
 «     Expenditure Sources
 (
 I-        o  EU/JRB Case Studies, 1983
          o  State and Federal Superfund Work, 1981 -1983
      Estimate Sources
     ~~~~™"~~"""1^^~~
          o  JRB-RAM, 1980
          o 'Radian, 1983
          o  EPA, OERR contractor Feasibility Studies, 1981 -1983
          o  SCS Engineers, 1981
                                          -16-

-------
L
I".
                                                             Surface Watrr Controls
                                                             Grading
2L2  GRADING

2,2.1    Definition
Grading is the general term for the process of reshaping the ground surface to control
surface water run-off and infiltration, as well as to minimize erosion and prepare the site
for revegetation or surface sealing.  The three basic steps in the process are: hauling,
spreading and  compacting.  The  latter two steps are routinely practiced at sanitary
landfills.  The equipment and methods used In grading are essentially the same for aH
landfill surfaces, but applications of grading technology will vary on a site-specific
basis.   Grading is  often performed in conjunction with surface sealing practices and
revegetation as part of an integrated landffllclosure plan.
             Units at Measurement
     The unit cost is given in dollars per acre because grading is usually performed on the
•     scale of acres.

             Sum mary Statistics
                                                   *
     2.2.3.1      Expenditures
     No actual expenditure data were available for grading costs at this time.

     2.2.3.2      Estimates
     The grading cost estimates ranged from :
             $4,000/acre
                 to
             $16,205/acre
                                            -17-

-------
                                                        Surface Water Cor.trol
                                                        Grading
I     Operation and maintenance costs involving ground water monitoring and cap inspection
     were generally not included in the estimates.   The following in O&M  costs,  however,
     were included in the Radian estimate;
r
               Item                                Cost
           Annual Inspection                      $500/year
           Mowing/Revegetation                  $600/year/acre
           Erosion control and drainage
            maintenance                          $200/y ear/acre
           Repairs resulting from shrink/
            swell or freeze/thaw forces
            construction                          $200 costs/year

The lower grading cost estimates ($4,000 - 4,720/acre)  reflected the costs of on-site
      j, spreading and compacting of a one-foot thick soil layer and a 6 inch sand layer.
     These estimates assume no material costs for sand or scdL  The higher grading cost
     estimates by SCS  also exclude material costs, but include the excavation and grading
     cost for on-site sofl.  Additional costs (30%) were included in these estimates to cover
     overhead and a contingency allowance.  The cost for a diversion ditch, included in the
     SCS estimates, was subtracted, for consistency with the other estimates.

     22.4   Factors Found to Affect Costs

     2.2.4.1      Expenditures
     No expenditure data are available at this time.

     2.2.4.2      Estimates
     The Following salient factors affected grading costs:
          -Material-
             Source of  material
             Type of material
          Related or additional costs:
             Soil compaction testing
             Surveying
             Overhead
             Contingencv allowance
                                            -18-

-------
                                                      Surface '•': ater Controils
                                                      Grading
 material costs varied among the estimates detailed in Table 6.  The source of the
erial was either on-slte or off-site, which affected the costs for hauling. The type of
material affected the estimate because sand costs more per unit volume to handle
. sofL  Again, however, this estimated difference excludes material costs, and only
ides hauling, spreading and compacting.

 inclusion of related or additional costs varied among the estimates, and hence
rted the costs. The SCS estimates included the following related or additional costs,
h were not included in the JRB and Radian estimates:
 ted/Additional Costs                 Landfill            Impoundment
                                    (13.4 acres)        (1.16 acres)
 eying (2 days)                          —            $  366-614
 •head allowance (25%)             $17,499-20,402       $2,655-3,469
   gency allowance (15%)          $10.502-12.237       $1.593-2,077
    Total                        $28,001-32,639       $4,614-6,160
 nates Sources

 o JRB-RAM, 1980
 o Radian, 1983
 o SCS, 1981
                                   -19-

-------














a"
5
^M
£
H
C^J jn-S
H -2
- 53 o
* O °
a 0 s
cfi ^^ 5v
^ 0 c
5
^C
A^
PB>|
U

«






41
1 .
1 u
1 ">
E*
§

-
•*
2




*a
M
b
1 ADDED


U
I COVERAG

O
M
a
u
E*




O
w
z
g
u\
0
es
*
\o
fH
1
cn
•^
«M


JJ
0)
ID

CO
01
u





«
JJ
ta -H
1 -H
C 0
0 10

•
e
E
S I
-j a. o
W S 03
en u 1-1 cn
3 w r IH

4)
M
u
(Q
vO

^
00
1 *
00
•
5.


4J
0
0

a
0)
u
U
n
»




0)
jj
CO -H
1 -H
c o
0 CO



Pi
a. «o
to 3 oo
w cj -J eri
9 en 5 IH





0)
u
o
*>v
O
0
o
V

41
>
•H
Oi
JJ
0



>
•H
JJ
0







•H -D
•H C
o 10
CO CO




< c
Q-i nj
«? i
S an ^H '









O
es
gl
-a-

to
41
"S "5
0 C
IM — I
v u:



03 eg
(jj Qj
u u
u o
Id 10
in o
t- CN






:
•H c
- m




— 2±
U I 0
M 00
tn oi o>
3 ^ i-t
-20-

-------
                                                   Surface Water Con*rol
                                                   Drainage Ditches
  23  DRAINAGE DITCHES
          Definition
  Drainage ditches or trenches intercept overland flow or shallow  ground water flow to
  control surface discharge and/or minimize contributions to ground water contamination.
  Ditches usually run around the perimeter of a site and may complement ground water or
'  surface  water control techniques by collecting water from subsurface drains or off of
  caps.  They may be lined with a clay or synthetic membrane to prevent infiltration or
  with stone to prevent erosion.

  2^2    Units of Measurement

  Costs are given in dollars per linear foot (LF) because length provides a single simple
 " trench dimension for performing quick estimates.

  2^3   Sum maxy Statistics

  2.3.3.1     Expenditures
        No actual expenditure data are available at this time.

  2.3.3.1     Estimates
        The cost estimates range from:
         $1.27 - 2.54/LF         (1-foot deep)
             to
         S6.04/LF               (6-feetdeep)
                                        -21-

-------
I.
r
                                                         Surface Water Control
                                                         Draijige Ditches
The cost estimates seemed to be primarily affected by the volume of seal excavated.
The  Radian scenario assumed over six times as much soil as the EPA site-specific
estimates.  The 1 foot deep trench was similar to a shallow french drain since it was
filled with graveL

Operation and maintenance costs such as inspection  and repair  were inconsistently
available. The Radian estimate, however, gave the following estimate:

               Item                              Cost
j                 Annual Inspection                      $500/year
                 Mowing/Revegetation                  $600/year/acre
                 Erosion control and drainage
f                  maintenance                          $200/y ear/acre
*                 Repairs resulting from shrink/
                 swell or freeze/thaw forces
i            '     construction                          $200 costs/year


i      2J2A    Factors Found to Affect Costs

 /    2.3.4.1     Expenditures
      No expenditure data were available at this time.

      2.3.4.2     Estimates
i      The three primary components affecting the cost estimates were:
1              Depth
I              Lining
L            Overhead and contingency costs
r      The depth was perhaps the most salient factor affecting cost estimates (Table 7) since it
!      was directly related to the  volume of material excavated.   Excavation is the primary
      task of ditch construction, grading and berm construction  but it  was proportionally
      included in all estimates.
                                             -22-

-------
L
P
          s
          «
^
           w
                             «N
H
C
         w>
         2^*1
O

w
8
M
2
3

§
j
g
*
£
a
8


z
M




O
c
<
s
a


j
^
o
vc

o
o
oT


0)
0)
•w
(0



I
B





^ ^
Cu *
" "fl «
3 K 3
fa

*?
1
m
•*
l
en •-!
en r*.
en 10
2Z

0)

A '*
< W 4)
CL Z >-j
W 1 ON
a r- »
c/3 ec cr\ aj
3 0 -H 2






















*



                                                                                                                                       in
                                                                                                                                       0)
                                                                                                                                       o
                                                                                                                                       us
                                                                                                                                       o
                                                                                                                                       0)
                                                                                                                                       I
                                                                                                                                      •o
                                                                                                                                       10
                                                                                                                                      in
                                                                                                                                      CN
                                                                                                                                      •D
                                                                                                                                       10
                                                                                                                                       01
                                                                                                                                       n
                                                                                                                                       01
                                                                                                                                      TJ
                                                                    -23-

-------
                                                              Surface V ater Control
                                                              Drainage Ditches
I-
Only the EPA-New Jersey site estimate included estimates for the lining subtask. This
cost component could become more significant for deeper ditches.

Finally, an overhead allowance (25%) and a contingency allowance (15%) were included
for the SCS estimate. The other estimates did not Include any surcharges or allowances
for health  and safety considerations,  so these additional costs may be appropriate to
include for some sites.   The SCS estimated only "grubbing" to clear vegetation from
ditches (28,300 sq.ft.) once a year at $378-779.

Estimates Sources

     o  Radian, 1983
     o  SCS, 1981                 	
     o  US EPA, OERR contractor Feasibility Studies
                                           -24-

-------
(
                                                          Surface Water Control
                                                          RevegetatLon
      2.4 REVEGETATION

      2.4.1    Definition
      Establishing a vegetative cover may stabilize the surface of hazardous waste disposal
      sites,  especially when preceded by surface sealing and grading. RevegetatLon decreases
      wind and water erosion, and contributes to the development of a naturally fertile and
      stable surface, and reduces infiltration by enhancing  evapotranspiratLon (Le., increased
      loss of son moisture),   ft also can be  used  to aesthetically upgrade the appearance of
              sites that are being considered for re-use.  Short-term vegetative stabilization
      (Le., on a semiannual or seasonal basis) aiy> can be used during ongoing remedial actions.

      2.4*2   Units of Measurement

      Costs are given In dollars per acre because revegetation is usually given in terms of
      acres.

      2.4^   Sum mary Statistics
                                                    *
      2.4.3.1     Expenditures
      No actual expenditure data are available at this time.

      2.4.3.2     Estimates
      The revegetation cost estimates ranged from :
i
      Capital:        $l,214/acre    (1.76 acre site)
i  •         •                                               •              •
                     38,000/acre    (20 acre site)
i                                                                            •      -
      Operation and Maintenance:
                     S51/acre/year
                        to
                     $l,267/acre/year
                                             -25-

-------
L
r
                                                          Surface Water Control
                                                          Revegetation
      The  range of costs for revegetation reflects the differences in the amount of work
      needed for different site condition assumptions.  The highest cost  estimate was for a
      proposed restoration of a secondary growth temperate deciduous forest, requiring heavy
      liming to neutralize the highly acidic solL   The lowest cost  was estimated for a
      hypothetJcaTly filled and graded on-site fertile srril.

      2:4.4   Factors Found to Affect Costs
!
      2.4.4.1     Expenditures
      No actual expenditure data were available at this time.

 }    2.4.4.2     Estimates
      The following factors were found to affect the revegetation cost estimates:
           o  Scrfi
f             '   New fUl and grading required
                 Terrain impediments (e.g., slope, berms)                      	
f                treatment for fertility
           o  Vegetation:
                                                    »
f                 Grass and/or trees (successional stage), multi-year planting
''                Mulching and/or jute mesh stabilization

      Soil cost was not included in the estimates (see Table 8> However, for the  New Jersey
      Feasibility Study, 65,000 cubic yards of off-site fiH was expected to be necessary for the
      72,600 square yard (15 acre) site (0.9  yards deep).  Also, the SCS "landfill" estimate
      includes excavation, grading and recontouring of the site (27,685 m3) this was about 60%
j      of the total revegetation cost, including the overhead and contingency. The  terrain was
      assumed to be flat except for tae.JRB estimate, which assumed 25% sloped terrain and
,      75%  flat terrain.   The JRB  estimate  also assumed a  three-year staged  planting
                                                                                   *
      schedule. The estimates also vary the type of vegetation assumed. Hydroseeolng was by
      far the least expensive vegetation (S0.37/sq. yd.) since it provides  fertilizer, !ime, and
      seed in mass application of a sprayed liquid.  Trees and shrubbery cost significantly more
      because of higher material and labor costs of individual hand-planted nursery stock.  This
                                             -26-

-------
.  1
  L
  r
                    CM
                    GO
                    ON


•e oi
u
e e
o a
•H C
U 01
eg ti
S.5
<§•£





aj
4J
•H
CL
a
u



01
M
•H
CO





^
•H
O
ca





§
•H
a
•H
^4
U
03
01
0

0>
o
M
3
O
CO
a
(0
o

eg
0)

*^
o>

u
a
\o
CM
tH
01
b
U
CO
o
o
0
•h
00
09
01
u
CO

«n
fH


N
4J 0) ft
03 
U O 0)
eg tH »H
09
O "">
«M «ft fH
^•^





"S
fH e
«H a
«H O
4J fH
00 09
e e
•W 1^
J= 01
O I- CO
fH 004
I « 2
of oi oo
0)
a o o
03 O O
«g o o
(4 • •
00 fH fH





jj
^
^ *
' O
eo pa oo
=3 a: ON


fW
a
o

^^
01

eg
CM
CO
01

U
<0
fH

fH
•O
•• •*
c m J
5r^ *
•J55 S
00 *

^i E
O 3
e co
09
CO

e
0)

•H
00

^
o
C
•u
fH

tf^
U-l
00
C • «
•rt 0) M
•0 E 01
ttJ -rt N
01 fH -H
09 ^ *H
O -> SS 4J t3
•e fH ki oi
>> C 0) 01
j: o «- BB







< e
o. eg
W ^o oo
co as o\
S OS fH

                                                     -27-

-------
L
r
         •o
         01

         c
         o
CO

eg
                        «M
                        00




•0 01
u
o «t
i-l C
B £
h. e
01 -H
&03
oz


a
^
a
a





01
M
M



^
•H
O
CO
§
•H
4J
a
•H
U
CO
&
01
u
3
0
Vi
9
a



«0
01
^%
0)

e

•H
«•



CM
1
CO
«>
01
u _.
« Q
f"H C^
CN 00
fH fH
«&• «>
09
0)

U
a

rH
O
CO
cu cu
•H fJ .
4J CO
M 1
iw O
*
01 60
oi e
0) -H
O JC
hi U
•a fH
>, 3
J= E
"ij
01
•o
^
a. o o
u a. oo
CO E O\
CO CJI-H fH
3 COS
                                                                        01    CU
                                                                        >.    M
                                                                                                 u
                                                                                                 0)
                                                                                                 a
       §
       U

      •o

       CB

O    **.
      §K
      «n
 •    CN
O    ^
                                                                              Q)
                                                                              OI
                                                                             J=
                                                                              IN
                                                                              01
                                                                              >
                                                                              O
                                                                                                a
                                                                                                4)
                                                                                                       a
                                                                                                       at
                                                                       -28-

-------
I
                                                          Surface Water Control
                                                          RevegetatLon
      higher stage of plant succession  wiH also vary  with the type of stock selected.  The
      Radian report provided the following list of various plant costs (in 1982 dollars), which
      included materials and installation:
           Item
                                                        Cost(S)
I-
Topsail, furnish and spread
           4"
           6"
Sodding, 1-1/2" thick

           Level
           Slopes

Ground  Covers
     Pachysandra
     Vinca Minor
     Privits, 15" taH planted in hedge row
     Barberry, 15" taH planted in hedge row
     Boxwood 16", tan planted in hedge
Trees and Shrubs

     Flowering Crab 8' - 10'
     Hawthorn 8' - 10'
     Junipers, spreading 18" - 24"
     Junipers, upright 4' - 51
     Yews, spreading 18" - 24"
     Yews, upright 2' - 3'
     Rhododendron 2*
   - Fir 81- 10'
     Hemlock 8' - 10'
     Beech 8'. - 10'
     Pine 8' - 10'
     Tulip 8' -10'
     Maple 1-1/2" diameter
     Maple 2" diameter
     Maple 3" diameter
     Sycamore 4' -5'
     Gold Locust

        Source: Radian, Inc., 1982
                                                              1.43/sq.yd.
                                                              1.90/sq.yd.
                                                              2.86/sq.yd.
                                                              3.74/sq.yd.
                                                              1.09/sq.ft.
                                                              1.11/sq.ft.
                                                                 2.34/LF
                                                                 3.03/LF
                                                                 2.84/LF
222.12/ea
170.90/ea
 33.22/ea
 58.63/ea
 45.22/ea
 54.63/ea
 71.16/ea
251.16/ea
283.16/ea
222.16/ea
249.16/ea
244.16/ea
167.11/ea
197.15/ea
362.24/ea
 46.22/ea
 69.22/ea
                                             -29-

-------
                                                             Surface Vater Control
                                                             Revegetatlon
r
Estimates Sources

    O JRB-RAM, 1980
    o Radian, 1983
    O SCS, 1981
    o US EPA, OERR contractor Fensihllity Studies
fl
r
                                           -30-

-------
                                                       Ground Water & Leachate Controls
                                                       Impermeable barrier
                                                       Slurry Wall
                                    SECTION 3

                    GROUND WATER AND LEACHATE CONTROLS
3.1  SLDRR7 WALL

3.1.1    Definition
A  slurry waE is one of several types of subsurface cut-off waHs that prevent leachate
formation by redirecting upgradient ground water away from a  contaminated area,
and/or controlling horizontal leachate movement away from  the site.  A slurry wall is
constructed by frmng  a trench with a slurry such as bentonite on bentontte-ecdl-cement
during excavation.  The backfilled trench has a much lower coefficient of permeability
than the surrounding 'soil and thus creates a barrier to ground water flow.

3.1.2    Units of Measurement
Costs are given in dollars per square foot because square feet reflect the functional area
of a cut-off  walL  In estimating the cost of a cut-off wall, the length  and depth (face
area)  requirements are usually fixed by the extent of the waste and the depth of the
aquiclude.  Linear units were not used because they would obscure the effect of thickness
on grout curtain costs.
                                                          •
3.1*3    Sum mazy Statistics

3.1.3.1     Expenditures
       The slurry  w all expenditures ranged fro m:
           $0.25/sq.ft.
               to
           831.96/sq.ft.
                                      -31-

-------
r
                                                       Ground Water & Leachate Controls
                                                       Impermeable barrier
                                                       Slurry Wall
i
j      The lowest cost for a slurry wan was for a privately constructed wall using extensive in-
      house equipment and labor.  The next lowest cost wall was relatLvelv shallow (14 feet
      deep).  The highest cost slurry wall was buHt partly In contaminated -yrfl on a stream
      bank.  Each scoop of soil required analysis with an  organic  vapor analyzer and was
      disposed of at an engineered landfOL  The stream bank restricted and delayed access to
      the construction area.
i
:      Operation and maintenance costs involved groundwater monitoring and, possibly, repair.
      These costs, however, either were accounted for separately or were not yet encountered
      at the new sites.

^    3.1.3.2     Estimates
            Slurry wall cost estimates ranged from:
.                $4.50/sq.ft.        scdl-bentonite
*                     to
I                $13.86/sq.ft.
1
.      The highest slurry  wall cost estimate ($11.56/sq.ft.) was for a Wyoming bentonite slurry
I      walL  The lowest  estimate was for a competitively bid sodl-bentonite slurry  wall,  for
      which another contractor was deemed more reliable.
                                        •
      Operation and maintenance costs such as inspection, ground water monitoring, and repair
      were not included in the estimates.
                                             -32-

-------
r
                                                    Ground Water & Leachare Control
                                                    Impermeable barriers
                                                    Slurry Walls
      3.1.4    Factors Found to Affect Cost

      3.1.4.1     Expenditures
      The following factors primarily affected slimy wall expenditures:
           o  Depth.
           o  Thickness
           o  Wall material
           o  Inclusion of related costs:
                 Staging area set-up
                 Contaminated trench soil disposal

      Perhaps  the  most  salient factor  affecting costs (shown  in Table  9)  was the  wall
      material Cement - sofl/bentonite walls were the most expensive walls; soil bentonite
      was in the middle of the cost range, and local clay was the least expensive.  Much of the
t     local clay used for the $1.80/sq.ft. California slurry wall was dredged from, the adjacent
      bay.  Depth affected costs since a larger excavator (such  as a  CAT 215 or clamshell
      instead  of  a backhoe)  was necessary for digging deeper trenches.  Once mobilized,
      however, larger equipment is capable of increasing  the trench  depth at a reduced
      marginal cost.  Wall thickness was directly proportional to the volume of soil excavated
      and the volume of slurry mixed into the trench.  Since costs are given in terms of dollars
      per square foot, the cost for this added volume is not precisely reflected in the face-area
      cost.  However, most of the walls had very similar thicknesses, at between 30-36 inches,
      with two waUs varying by  two feet.  The different thicknesses generally stem from
      different permeability requirements set forth in a consent  decree, or by a state  or
      federal agency.

      Related costs played a significant role in at least two cut-off walls. At the Pennsylvania
      site, a large volume of contaminated  trench  soil required disposal at an engineered
      landfUL  In addition to these disposal costs, which were included in the operation cost
      total, the trench construction was slowed by the need to test each excavator scoop with
      an organic vapor analyzer.
                                             -33-

-------

8

£"*
§


<
M
MATER
8
b3
u
M
£

DEPTH
•B
1
SOURCE,'
^
2
^
Q




(w
tr
OB
SO
•
5
0
jj
1 -H
JJ C
e o
E "c
O J3


JJ
8

^~


*j
0 jj
0 * 0
•H 0
X 
a -H
< ae >.
flu -5 CO
u >- ^ e
H« ao e
tO J 9> 0)
a u --HO.

jj
.
er
en •
C^
CO
i 0 e
«H JJ 0
*0 ^ 0
BOO
in 0 in
CO & i-
n
0
O
0
en
-
0
0
2 « P
o X iw
in
• o

o

^C pJ S3
CU U M
w >^. tr> o
CE3 f"^ i— t
CO 06 ^ O
s *^ •-< u

"t
2*
^
CO
CO
in
v>
0
<£J
•H
. §

-------
-  i
  L

  r
             •o

             I
             o
             u
             w

             ca
Q

i
X
CO
M

«
                   <   -
                   ^   s

                   g
                  ^

8
JH
M
5

J

I*H
a
£
£
I
o
M
3«
P

DEPTH
j-
§

i
z
s

B


1
jj
«T
a
CD
,

0>
JJ
e
1 O
-H C
0 01
a ,0

_,_,
0)
0)

m

4J

«2 jj

0 X IM
in
• o


g
Is
s a
< •*
aj cu a
M *J ^ •
BO (0 3
S ££,3
IM
tr
o
\D
eg


jj
e
1 O
-H JJ
•H C
0 0)
n ja

jj
«
0)

r>
*
jj
aj
Ol
IM JJ
0
o a»
0 X IM
o
eg eg
<«s
5
_g «o
< S -D
p . CU "H
pa a o
to ni o ^fa
IM
r
s^
eg
^
^




*« >,
O 'H
•H O

JJ
0)
0)
IM
in

jj
3)
01
J^j ^J
01
in a>
* X IM
r-

00
M
iH (8
•M — 1
eo a C
W •< CO «H
tH ON 1-1
M J  ^ c
W •»> O B3
M CO ^
9 W iH <
                                                       -35-

-------
L
r
                                                        Ground Water & Leachate Controls
                                                        Impermeable bamer
                                                        Slurry Wall
At the  Arkansas site  the cost given  may not reflect the full slurry wall costs since
significant in-house labor and equipment were used but not recorded. Other related costs
such as site preparation  and geotechn1r.nl investigations  were inconsistently noted as
separate or included.  Generally, these costs were not included in the slurry waU
expenditures.

3.1.4.2      Estimates
      The following factors affected the estimated costs for slurry walls:
           o   Depth
           o   Thickness
           o   Material
           o   Inclusion of related costs:
               -  Geotechrrical investigation
               -  Overhead and contingencies
       Material costs were again the most clear cost factor in the slurry wan cost estimates
      (Table 10).  The highest cost wall (SlO/sq.ft.) was the cement-bentonite wall at the New
       York site.  Slurry wall depth seemed to be, at best, a secondary factor.  The deepest (130
      foot deep) slurry waU at the New Jersey site was the second to lowest estimate while the
       most shallow (14 foot) slurry wall was the highest estimate.

       However, the construction of the 130 foot deep slurry waU would be greatly facilitated
      by  the unlithlfled  coastal  plain sediment of  New  Jersey for which it was proposed.
       Complete hydrogeological assumptions were not given for all of the estimation scenarios,
      but a 1980 paper by Ressi di Cervia (see Table 11) gave the following depth-soil condition
      cost matrix. The slurry waU thicknesses varied less than did those of the wall studied for
      the actual expenditures.  Only one hypothetical slurry waU was over 3 feet thick.  .
                                             -36-

-------
I
$
                                   -37-

-------
L
r
 r
 f
 r
           §
           O
           U
U
fa
JS

E*
O

£*
M
2
S



^j
M
eg
£

CO
2
U
M
2j
£*


•B
1
1


U
U
a
s
CO

£

a


4J
IM
cf
w
V.
en
•
v>


0)
jj
•H
. §
-H JJ
•H C
O 0)
a ^



•w

•
IM

"

0) 0)
IM d)
X IM
O O










< G
c- a
M -H CM
•a eo
CO 10 ON
S OS iH



^J
IM
*
'v
«O

9
in
0)
^
•M
. §
•H 4J
O 0)
a ^
a
0)
u
•H

O

«
CM
4J*
IM
tf
3)
in
9-


^

01
4J
•H
CO

^H (U
5 SJ
CMOO S
CO S ON U
SS 0 iH Z
cr
IB
\C
in
^
iH
ON

•CO-

CM
1 •-
. A) **
JJ «-
0,-H^
•H O U
O C 4J
> 01 10


0)
0)
IM

CD
CM
rn

jj
0) -U
O) 01
VM (U
X IM
^ en
en ^s-




^
^y
|

•O
< §
& o
U 0.0
eo e oo
CO U M ON
aw- *H
IM
cr
80

o
Wi
O
1
o
\0
CM
1 T-
fll •*
4J v-
•H *•
§ w
c -w
'
^)
$
IM

CD
CM
ro


D
01
IM 4J
0)
CM 01
U3 X IM
» en
CM V


•





i— i
*H
•< tM
CL -o
U CO
CO O OO
CO CJ •-( ON
3 35 r —
                                                   -38-

-------
L
L

r
        1
        o
        u
       u
       J
       BO
             8
             ,J  5
                                             -39-

-------
                                         TABLE 11
                          SLDRRY WALL COSTS:  DEPTH EFFECTS
              Slurry Trench Prices
              In 1982 Dollars
              Soft Bentonite BackfDl
              (Dollars/Square Foot)
Unreinforced Slinry Wall
Prices in 1982 Dollars
    Cement Bentonite Backfill
(Dollars/Square Foot)
r
Depth
30
Feet
S~ft to Medium Son
N 40 3-5
Hard Son
^40-
Occassional
L-Julders
5-9
5-10
f'tt to Medium Rock
N 200 Sandstone,
?vale 8-15
Hard Rock
•• .-unite, Gneiss,
' Schist*
-^-p.
Depth
30-75
Feet
5-10
6-13
6-10
13-25
_»
Depth
75-120
Feet
10-13
13-25
10-32 .
25-64
,^_
Depth
60
Feet
19-25
32-38
25-38
64-76
121-178
Depth
60-150
Feet
25-38
38-51
38-51
76-108
178-222
Depth
150
Feet
38-95
51-121
51-108
108-222
222-298
] 3tes: N « standard penetration value in number of blows of the ham mer per foot of penetration
(ASTM D1586-67)

I formal Penetration Only
     For standard reinforcement add $8.00 per sq. ft.
     For construction in urban environment add 25% to 50% of price
Reference: RessL di Cervia 1980.
                                           -40-

-------
                                                  Ground Water & Leach£.te Controls
                                                  Impermeable barrier
                                                  Slurry Wall
      Additional costs were included in at least two of the estimates.  Both geotechnical
      investigation (impoundment: $11,210-23,010; landfill: $4,543-7,694) costs and overhead
      (25%) and contingency costs (30%)  were included in the SCS estimates.  Geotechnical
      investigation and filter cake permeability testing costs were grouped together ($23,600-
      94,400) in the JRB estimate.
      Expenditure Sources
          o ELI/JRB Case Studies, 1983
          o JRB, 1983
          o State and Federal Superfund Work

      Estimates Sources
!i
O JRB-RAM, 1980
o Radian, 1983
o SCS, 1981
o US EPA, OERR, Feasibility Studies.
                                           -41-

-------
                                                 Ground Water and Lacheate Controls
                                                  Impermeable barrier
                                                  Grout Curtain
           GROUT CURTAINS
      3J2.1   Definition
      Generally, grouting is the pressure injection of one of a variety of special fluids into a
      rock or soil body to seal and strengthen that body.  Once, this fluid gels in the rock or
T     soil voids, it greatly reduces the permeability of, and increases the mechanical strength
      of the grouted mass. When carried out in the proper pattern and sequence, this process
|     can result in a  curtain or  wall that can  be a very effective ground  water barrier.
      Grouting  is  rarely  used when ground  water has to be controlled in soil  or loose
11     overburden.  The major use of curtain grouting is to seal voids in porous or fractured rock
"'     where other methods of ground water control are impractical.  The injection process
 (I     itself involves drilling  holes to the  desired depth and injecting the grout with using
 I     equipment.  In curtain grouting, a line of holes is drilled in single, double, or sometimes
}     tripte staggered  rows (depending on the site  characteristics) and injecting the fLiIri in
]     either descending stages with increasing pressure, or ascending stages with decreasing
      pressure.  The spacing of the injection holes is also site-specific and is determined by the
f     penetration radius of the grout out from the holes.  Ideally, the grout injected in adjacent
      holes should  fuse  between  them.  If this  process is  done properly,  a continuous,
Jj     im pervious barrier (curtain) wiH be f or m ed.
tli
I     2^2   Unit of Measurement
•'     Costs are given in  terms of dollars per unit face-area (square feet) because it best
,,     reflects the functional area of the grout curtain. The effect of other dimensions on costs
      is discussed  in section  3.2.4 (Factors Found to Affect Costs).  Since the units used in
      existing  engineering estimates have  varied  widely,  the effect  of using  different
I     dimensions is an important consideration for comparing estimates.
                                             -42-

-------
F
I
                                                        Ground Water & Leuchate Controls
                                                        Impermeable barrier
                                                        Grout Curtain
        Sum nary Statistics

3.2.3.1      Expenditures
      The cost of grout curtains (alt-ASPEMIX vibrating beam walls) ranged from:
               $ 6.60/sq.ft.
                 to
               $ 14/sq.ft.

The  lowest  cost grout curtain was the  first one installed by a  new company.   The
$14/sq.ft. grout curtain was installed two years later at the same site as the $&26/sq.ft.
waH.  The  cost  differences  may reflect the need to  reccop the potential earnings
foregone for the e*r?JgT- waHs in order to  enter the market. Operation and  maintenance
costs such as inspection,  ground water  monitoring and, possibly, repair either were
accounted for separately or were not yet encountered at the new sites.

3.2.3.2      Estimates
The grout curtain cost estimates ranged from:
        $5.50/sq.ft.          ASPE MIX, vibrating beam installation
           to
        $75.52/ sq.ft.        phenolic resin, standard injection installation

The  order of magnitude difference in cost estimates for grout curtain cost estimates
largely seems to reflect the widely varying thicknesses thickesses.  The highest estimate
was  for a 9 foot thick  wall; while the lowest (group of four) estimate was for an
ASPE MIX wan, which is typically under a foot thick.  Operation and maintenance costs
such as inspection and ground water monitoring costs were not included in the estimates.
                                             -43-

-------
r
i
                                                       Ground Water & Leachate Controls
                                                       Impermeable barrier
                                                       Grout Curtain
3J2A   Factors Found to Affect Costs

3.2.4.1     Expenditures
The following factors seemed to affect expenditures:

     o  Market entry loss
     o  Labor costs

The  cost of grout curtains seemed to be primarily affected by market conditions.  The
Industry contacts who supplied the data in Table 12 noted that, compared to the costs
shown,  the prices wffl decrease and stabilize  in the future now  that the firm has
penetrated the market.  They also noted that the California site cost was significantly
affected by the relatively high local labor costs.  For instance, a privately built grout
curtain  in Dallas, for which no data were available, was said to have been less than half
the cost of the latest California walL

3.2.4.2     Estimates
The following factors affected grout curtain cost estimates:
     o  Thickness
     o  Material composition
     o  Installation technique

     o  Inclusion of related costs:
        -   Geotechnical investigation
        -   Overhead and contingency

The  most significant cost factor affecting grout curtain cost astimates (Table 13) was
                                                                             «
the  waB. thickness.  For single row walls this was assumed to be equal to the center^to-
center  distance of the grout injections, which is equal to  the diameter for adjacent
injections. The nine foot thick  wall, which was expected to be necessary to enclose an
impoundment, was the highest estimate.
                                             -44-

-------
1
I
II


I










1
5

Q
*-»
Z
K
CN
S !
__ ^>i
CM Z ^
i-< fe 0
a 2 "
03 L^ CO
< r^ o>
^j ff^m _j
P* ^^ *H
^•N >-x
U

I
u
.








4J
01
O
u

4J
•H
e


iH
a
•H
k>
41
W
£



1 Thickness




4J
a
V
i3
K
4J
g
•J



4)
U
• .
PH
O
en
a
u
a
a


•
u
IM
' •
er
CD
•*.
*T
iH
O-
^
rH
N— '
X
g
e-
w



w
41
4)
«w
«n
eo
•
0




JJ
4)
(U
IM 4J
0)
en K 4)
CM IM
ON
« r»
CM fH



a
«H
m £
< as o
a, <^ uj
W >v -H CM
M t-l 00
V3 .J flj O>
a w u ^>
X
g
c-
cn



w
01
41
«M
en
CO
•
0

•


4J
V
«
«M AJ
4)
§K 41
>M
• r*
CM «-<



«
^H
« S
< as 3
a, •-) ^
&<. -HO
M ^^ CO
W J Q ON
a u o «H












*
§
ft-
in



JJ
o
o
IW
ff




4J
M
«
IU 4J
01
m x 41
SO «-l
«»
• 0
«-l 
83 •
45
£3
*• 9
<— V
-j
^*

«
                                             -45-

-------
I
              0   i
                    fH
              s   i
                    CM
                    00
                    ON
 I
 »:
 I





4J
CO
0
u
4J
vH
g
D
•-I
0)
1 Materi
(0
CO
01
e
.*
u
^_j
^^
H
4J
a
01
fi
X
4J
00


01
u
fc
9
O
cn
a
u
a
a
•
4J
<44
•
tr
CO
CM
U*t
•
in
r»»
1
•»
o>
•
CO
n
«•

u
•H
iH
o e
§«H
a
^ 01
0. U



44
at
01
*M
Ov

• 4J
01 4J
01 01
vu 41
4
m
4J
0)
01 4J
U4 0)
41
fN. Hrf
t-t

01
4J
CB
U
«H
•H
•H
CO



4J
0)
0)
IM
«n

4J 4J
01 0)
01 01
'•M '-M
0 X O
g «"





 1 »H


•
Jl
U-l
•
O"
a

o
00
>H
CM

01
4J
silica


•
4J
^rf
•
c-
u

o
00
•
rH
f— 1


-------
1
1

IP
i
J
i
|
r
I
I

1

«^
"O
01
. B
^^
4J
O
u

<*>
•H
U
J
03
S



£
c
i


8
Z

<
H
ft!
8
5
O
fig
U




^^\
00
h
• 0
»H
iH
O
Q

CM
00
o\
•H
>^







(^
CO
O
u
u
ft
c
3
•H
C9
•H
M
0)
«J
to
Z

CO
CO
0)
j
u
v>4
H
M
a
0)
o
X
.e
^J
00
j

01
u
1 .
M
o
en
9
±J
fl
Q

•
4J
•
ee! 0)
fid a
«:* S
a. i *5
W ^ C7*
P C* >
V3 ae ON oj
3 O iH 2


•
4J
iw
•
cr
CO
**^
VO
00
•
NO

0
l«
•
m
v>
X
i_i
S
A.
CA
*2
<;
y^>
4J
o
0
t^J
*t"N
§ fH
* I
« 1
s s
c *
" >-»
•
^J
01
4) JJ
IM 01
U
0 ^
m o
-  a;
3 •* ^ 2

-47-

-------
                                                           Ground Water & Leachate Controls
                                                           Impermeable barrier
                                                           Grout Curtain
       Comparing the cost estimates based on dollar per linear foot and a dollar per cubic foot

       basis is useful for discerning the effect of thickness on the estimates.  On a cost per

       Tinaa.r foot basis the following list shows that the cost ranking is aberrant compared to

       the depths.


            Date      Depth             Unit Cost                Cost Ranking ($/sq.ft.)

            1982      60 feet            $ 330- 412/LF                  6
|1           1980      49 feet            $1,908 - 3700/LF                 1
ij           1980      49 feet            $1,619 - 3353/LF                 2
            1979      40 feet            $ 249 - 419/LF                  5
            11982      20 feet            $ 230 - 340/LF                  4 a
            1982      20 feet                $ 420/LF                    3
            1982      20 feet                $ 240/LF                    4b

f:
       On this basis the costs show neither an ordinated ranking according to depth, nor does it

!      show an evenness (X- 81,102/LF; SE*  $365/LF; n*12) that would suggest that simple

"      length was the most significant cost factor.


I      Similarly, the effect of thickness and depth on cost can be elucidated by comparing costs

       on a per volume  basis.  The following list shows that the cost estimates are relatively

       even (X- $5.30/cu.ft.; SD- $2.90/cu.ft.; n- 10).


            Date      Thickness         Unit Cost                 Cost Ranking (S/sq.rt.)

            1980      9 feet            S4.33-8.26/ctuft.                 3
            1980      5 feet            $6.61-13.69/cu.ft.                1
            1982   •   3 feet            $7.30/cu.ft.                     2
            1982      3 feet            $3.80-5.72/cu.ft.                 4a
            1982      3 feet            $3.90/cu.ft.                     4b
            1979      3 feet            $203-3.43/cu.ft.                  5
            1982      Ifoot            S5.50-3.86/cu.ft.                 6
                                              -48-

-------
1
I
I
f
                                                 Ground Water & Leachata Controls
                                                 Impermeable banier
                                                 Grout Curtain
The  mean of the Table 14 costs was $22.60/sq.ft (SD= $20.10;  n*10).  The data are
inadequate to provide any generalization about  the  relative costs of various grout
materials. The scenarios that assumed the use of phenolic resin, however, were the two
highest estimates; two silicate waH scenarios were higher than portland cement, and four
bids to construct an ASPEMIX  wall, composed of an emulsion of asphalt, sand  and
concrete to be installed with  a vibrating beam,  was the lowest cost estimate. Since no
"control" estimate was available to consider the cost of an ASPEMIX wall if installed
with a traditional injection technique, the installation technique cannot be accurately
Judged as a  cost factor.  However, the vibrating beam  method  may be generally  less
expensive than the traditional injection technique.

Finally, the  cost of a geotechnical investigation was included only in the JRB and the
SCS estimates.   The SCS  estimate also  included overhead (25%) and contingency
allowance (30%).
      Expenditure Sources
          o ELI/JRB Case Studies, 1983
      Estimates Sources
           o JRB-RAM, 1980
           o Radian, 1983
           o US EP*A, OERR contractor bids
           o SCS, 1980
                                           .49-

-------
i
r
i
                                                    Ground Water & Leachate Controls
                                                    Impermeable barrier
                                                    Sheet Piling
           SHEET PILING
      3,3.1   .Definition
      Sheet piling can be used to form a continuous ground water bander of driven steel piles.
      Although sheet piles can also be made of wood or precast concrete, steel is the  most
      effective in terms of ground water cut-off and easy installation.  The construction of a
      steel sheet piling cut-off wall involves driving interlocking p*ipq into the ground using a
      pneumatic or steam-driven pQe driver. In some cases, the pfl«»g are pushed into pre-dug
      trenches.  Piles are com monly 4 to 40 feet long and 15 to 20 inches wide.  Because of
      corrosion and "windows" usually present between piles, this method is often considered a
      temporary stop-gap measure.
              Unit of Measurement
      Costs are  given  in terms of dollars per square foot because area  best reflects the
      functional units of a cut-off wall
              Summary Statistics
      3.3.3.1      Expenditures
fii
I     No actual, expenditure data for sheet piling cut-off walls were available at this ttm e.

'     3.3.3.2      Estimates
             The cost estimates for sheet piling cut-off walls ranged from:
 ,                 $8.02/sq.ft.
                   to
                  $17.03/sq.ft.
                                             -50-

-------
I
1
I
I
                                                    Ground Water & Leach*.te Control
                                                    Impermeable banier
                                                    Sheet Effing
The lowest sheet piling cut-off wall estimate was for the largest site involving 116,228
sq.ft. of sheet piling. This larger wall may have helped reduce the cost by using already
mobilized equipment,   This effect  may have counterbalanced the  effect of including
related costs that were not included in the JRB-R A M estimate.

3-3.4    Factors Found to Affect Costs

3.3.4.1      Expenditures
No actual expenditure data are available at this time.

3.3.4.2      Estimates
The following components affected the cost estimates for sheet piling cut-off waHs:
     o  Economies of scale
     o  Piling type
     o  Inclusion of related costs:
            Geotechnical investigation
            Overhead and contingency allowances
                                              •
As noted above In  Com ments on the sum mary statistics, the limited data in Table 14
suggest that economies of  scale  may  be the most significant factor affecting  costs.
Although local costs may vary this effect, the specialized  equipment (pile drivers) and
experienced personnel may be able to Install sheet piling at decreasing marginal costs as
the total area  of Installed waH increases.  This relationship may derive from the fact
that mobilization and set>-up are relatively more significant  elements of the total unit
operation for sheet piling than other remedial technologies.
                                             -51-

-------
I
I
FL

I
                                                    Ground Water & Leach?.te Controls
                                                    Impermeable barrier
                                                    Sheet Pffljig
Among  the estimate scenarios,  the piling  types varied both in composition  and in
thickness.  Galvanized steel ($10.48/sq.ft. installed) which provides.somewhat greater
corrosion  resistance,  was  slightly  more  expensive  than  black steel ($9.41/sq.ft.
installed).  The paucity of data on piling thickness precludes accurate quantification of
its relationship to costs. However, this variable may often be dictated by local material
availability and geological constraints.  Since pflpR are typically withdrawn and reused,
tiie thickness of the piles  may also affect of the reusability and- hence  the rebate
revenue, since a too-thin pile may buckle upon Insertion.  Since materials may be 80% of
the total cost of a sheet piling cutoff wall, the effect of thickness and reusability on the
                   •
cost may be significant.  The cost estimates given Table 14 do not include cost credits
for reuse of the piles, but do include  varying pile types, as indicated.  As noted in Table
14 the cost of a geotechnical investigation ($11,210-23,010) was included only In the SCS
"impoundment"  estimate.   Additional .costs  for overhead  (25%)  and  contingency
allowances (25%) were included in this estimate and the SCS "landfill" estimate.

Estimates Sources
                                              •
     o  JRB-RAM, 1980
     o  Radian, 1983
     o  SCS, 1980
                                              -52-

-------
C  :
i

I;
w
I
       fe  ,
       8S
           CM
           eo
g  -
d  s
    I
    ffi


.u
03
O
U
•H
e

60
-g
fH
•H
CM



4J
^j
60
•H
0)

jr
cu

•o
K

.C
e
0)
u
!^
g
V3
a
a
0

•
tr
m
en
O
fH

O K IM
§ o
• CM
fH


CU ' O
aa eo
U OS C*


IM
fH
ON
fH
0)
(U
CO
•s
CO
iO


•
IM
C1
(0
00
o
alvanlzed
60

a>
^
•H
60

^
0
•

*J
01
01 4J
IM 0)
0>
O K IM
§ 0
•• CM
fH


< e
W -H CM
•Q 00
00 0) O\
3 as «-"
cr
eo
CM
^j
1^^
CM
.3-
eo*

60
CO
60


09
e
o
f£J

^*
00

4J
01
01
IM JJ
01
CM O>
»»* K IM
CM «»
*4J
^^ S
CM E
•o
• e
2C§
W D.O
W S 00
CO O M 0>
SMS ~i
IM
cr
CO
o
oo
fH
fH
CM
O
*
eo
to
CM
CM
a-

n
§
A4

fH
eo
CM
fH

4J
01
01 M
IM 01
01
t?^ i»W
l^ K
CM

•u
^H
fH
< CMIM
ft. *+* -r}
ta no
W 03 00
tn u j o\
s w : <-)
                                                               X
                                                               u

                                                               01
                                                               eo
                                                               c
                                                               c
                                                               o
                                                               V

                                                               13
                                                               C
                                                               a
                                                               in
                                                               CM
                                                               
-------
1
I
n
i
                                                             Ground Water ft Leachate Controls
                                                               Impermeable banters
                                                               Grout bottom sealing
      3.4 GROUT BOTTOM SEALING

      3.4.1       Definition
|     Grout bottom  sealing is a direct  barrier to downward leachate migration.   Grout is
      injected, through the fill material to form a bottom underneath the contaminants.  The
      grout is injected horizontally from  jets at the bottom of a pipe, which is inserted like a
      well point,  with  a pneumatic hammer.   A grid of injected grout ideally  forms a
      contLnguous bottom seaL Grout materials are typically silicate or portland cement.
      2A2       Drifts of Measurement
      Costs are given in terms  of dollars per square foot because area best reflects the
      functional characteristics of bottom sealing.

      3.4^}       Sum mary Statistics

      3.4.3.1     Expenditures
      No actual expenditure data are available at this tune.

      3.4.3.2     Estimates
            The grout bottom sealing costs ranged from:
                        $9/sq.ft.
                        to
                        $116/sq.ft.

      This  wide  range  of estimates seems  to reflect  the varving  thicknesses  given for
      hypothetical seals. The higher estimate was for a 5.25-foot thick seal vs. a 3.25-foot
      thick  seal for the low er estim ate.
                                             -54-

-------
                                                              Ground Water •<* Leachate Controls
                                                              Impermeable barriers
                                                              Grout bottom sealing
       3.4.4
            Factors Found to Affect Costs
       3.4.4.1     Expenditures
       No actual expenditure data are ava.ilable at this time.
I
1
c
I
 3.4.4.2     Estimates
 In the scenarios for the grouting estimates, the following components varied:
      o     Grout thickness
      o     Grout material
      o     Coverage
      o     Son, fill type
 Of these components, the grout thickness appeared to be directly related to the wide
 variation in the cost of the two grout seals shown in Table 15.  The "landfill" seal was 2
 feet  (61%) thicker than the "impoundment" grout.  Thickness appears to  affect the
 estimates more than does the grout material type.  Material costs for phenolic resin are
'significantly higher than for Portland cement grout, but overall, the thicker cement grout
 has a higher unit area, and a higher unit volume cost ($11- 22/cu.ft. vs $2-5/cu.ft.) than
 phenolic resin.

 Economies of scale may have caused the "landfill" grouting to be less expensive than the
 impoundment  grouting since the scenario assumed ten times as  much coverage.  Despite
 this disparity  in task size, the geotechnicalinvestigation  (impoundment: $11,210-23,010;
 landfill: $15,104-25,559) and equipment cost were relatively similar.
 Overhead (25%) and contingency allowances (40%) were the same for both seals.
       Although it is not possible to quantify from the available cost estimates, the effect of
       iAJection through heterogeneous, resistant fill and soil probably is a  significant cost
       factor.  However, the  higher  cost  of the landfill groutestimate cannot be  clearly
       attributed to this factor since co m plete inform atton is unavailable.

       Estimates Source

            SCS 1980
                                             -55-

-------
I
I




m
^.
a
CO
U
z
2
2S
C/2

O


^\
a
(9
rH
O
o
«M
00
i-l
li

i
u.
=>
O
**
3



4J
CO
O
0

u
c
=5
•
V
6C
<0

Q)
*^
o
ej

•c
o
0)
Q
f-l
(0
•H
«•"
4JQO
an

au
Or*
uc

41
o

5
CO
JJ
e
o

vu
•
CO
vO
3

-------
                                                               Ground water & Leachate Controls
                                                               Permeable Treatment Bed
1
i
1
II
1
I
          PERMEABLE TREATMENT BED
3J>.1       Definitioo
A permeable treatment bed is subsurface wall made of a permeable filtering  material.
The intent of these treatment beds is to decontaminate groundwater as it flows through
the bedding  material  The most com mon functions of these beds is to neutralize acidic
ground water, or precipitate metallic ions by using a limestone bed, which increases the
pH of the groundwater, thereby reducing the solubility of the metals.  The six primary
component tasks (generally included in the costs) are:
     o     Trench excavation
     o     Spreading
     o     Well-point dewatering
     o     Sheet piling
   .  o     Walers, connectors, struts.
     o     Bedding (limestone or carbon).

3Jx2       Units of Measurement
                                            *
Costs of permeable treatment beds are given in terms of dollars per square foot because
it best expresses the functional value of the treatment bed.  The width and depth of the
leachate plume to be estimated are usually known,

JL5J3       Sum mazy Statistics

3.5.3.1     Expenditures
No actual expenditure data for permeable treatment was available at this time.

3.5.3.2     Estimates
                                                                          •
The cost estimate for permeable treatment beds ranged from:
                       314/sq.ft.          limestone bedding
                              to
                       $267/sq.ft.  .  activated carbon bedding
                                            -57-

-------
i
E
I
I
*!'
I
                                                             Ground Water % Leachate Controls
                                                             Permeable Treatment Bert
      The lowest cost permeable treatment bed was  for a limestone  bed;  while the high
      estimate was for a bed of granular activated carbon. Operation and maintenance costs,
      when given, consisted of the  following two cost items which depend on site specific
      variables:
                  Operation and maintenance                   Site-specific
                  Cost Items                                  Variables
           (1)    Ground water monitoring              - contaminants
                 cost                                 - hydrogeologoy
           (2)    Replacement cost                    - operational lifetime of
                                                         treatment bed
           Factors Found to Affect Costs
3.5.4.1     Expenditures
No actual expenditure data are available at this time.

3.5.4.2     Estimates
The following factors were found to affect the subsurface drain estimates:

           o     Bedding Material
           o     Size

The estimates made by JHB and Radian shown in Table 16 are very similar except that
17%  was added to most of the Radian costs for inflation.  However, the same unit cost
for limestone and carbon was assumed.  For the carbon treatment bed, the bedding cost
was the most significant (90%) cost out of the total.  For the limestone treatment bed,
the most significant cost (75%) was the cost of sheet piling.   Conversely, the bedding
cost was 7%  of the total for the limestone bed; whereas for the carbon bed, the sheet
piling was 8% of the total cost.
                                             -58-

-------
I
I
1
E
V!
i
f!
                                                                Ground Water & Leachate Controls
                                                                Permeable Treatment Bed
Although all cost estimates are for the same size treatment bed scenario, the influence
of size on unit costs should be noted briefly.  First increases in the dimensions of the
trench generally will proportionally increase total treatment  bed costs.  The effect is
pronounced by increases in width and depth, and for the more expensive carbon bedding
needed to fill the larger trench. A wider carbon trench could potentially be significantly
different than any of the estimates given in Table 16. Second, economies of scale coulrJ
reduce the unit costs of limeston treatment beds over that given in the estimate, since
reusable sheet piling, which has significant one-time set up and mobilization costs, is the
major (75%) component cost.   Also, the marginal unit cost of dewatering  decreases as
trench size increases.
Estimates Sources
           O     JRB-RAM, 1980
           o     Radian, 1983
                                            -59-

-------
f

I

I
i   s
I
               a
               w
               o
               CM

               00
CD
o


.4J
^^
n




vH
n

»^
0)
4J
X
•o
w
to
JS

•o
5


co

0)
u
w
3
w
a
to
O
IM
•
o-
o

^*
\o

o
05
M
(0
U

•O

^
a
•rl
^ t3
U 0)
CO 05
OI
01
IM
**
0)
(U
IM Arf
o x S
^3 ^j
°.
-.


2?
^
^« °"
9. 1 _
£>3 O
tn cs ON
»
«
u"
CD
^^
i-i
o
P>4




V
N

CO 01
^J
01 CO C
CO > O
w iH O5
9 4J W
o u a
u a u
01
01
IM
**

OI
01
0 X 0)
^J (M
0
-,




< c
a -2 »»»
TJ CO
J
v
tr
0]

Os

•co-
ts 0)
c e
a o
CD M
n
^3 0?
C E
0 TH

•H
cu :
a 01
W N
60 -H
r CD
u
u
IM
"*
OI
01
Oi
O X 01
O IM
0
.



_
«c ^
U i O
OS CO
Cft 0£ ^^*
•^ J
• IM
^T ^^»
»H U"
1 CO
*9
iH
V>



J
•O T3
C 01 01
CO N C
•H O
 T3 0)
a c E
W « -H
_00 W iH

4J
01
01
IM
•a-
01
OI
o x oi
O IM
o
o
«M JVJ




< e
c_ «a
a -i c
•u oo
05 (0 ON
=5 OS ^ .
                                                 -60-

-------
                                                                    Ground'vater & Leachate Controls
                                                                    W ell point syste m
1
D
u
I
3.6 WELL POINT SYSTEM

3.6.1        Definition
WeD. points are generally used to lower the water table or extract leachate. They differ
from drilled and  cased  deep wells in that they are driven, instead of drilled, into the
ground to just below the leachate plume. Ground water is then piped to a suction header,
drawn by a centrifugal pump, to a treatment system. In contrast, deep wells typically
use submerisble pumps to pump ground  water to a treatment  system.   For costing
purposes, treatment costs are considered separately.

3.6L2        Units of Measurement
Costs are given in terms of dollars per weH.  The extraction rate (gallons per  minute-
gpm) and depth should »ly> be considered. Since these characteristics vary  with site-
specific hydrology, however, costs given below do not factor in pumping rate.

3A3       Sum mary Statistics

3.6.3.1     Expenditures
                                             «
No actual expenditure data are available at this time.

3.6.3.2     Estimates
The cost estimates ranged from
           $803/well
                 to
           $8,284/well

The  highest  cost estimate  (SCS-"impoundment") included  the  cost of  geotechnical
investigation,  which comprised 50% of the costs.  No related costs were included in the
                                                                           6
lowest estimate (Radian).
                                            -61-

-------
I
F
li
                                                         Ground water & Leachate Controls
                                                         Well point system

3.6.4       Factors Found to Affect Costs

3.6.4.1     Expenditures
No expenditure information are available at this time.

3.6.4.2     Estimates
The following factors affected the cost estimates for the well point systems:
     o     Depth
     o     Pumping rate
     o     Inclusion of related costs:
                 Geotechnical investigation
                 Overhead allowances
                 Contingency allowances

The costs shown in Table 17 are relatively similar.  The effect of depth, which was
expected to be an  important cost factor, did not appear to significantly affect the
estimates.    Although  well  point  installation is often charged by the  depth, well  "
installation was a relatively small cost component compared to pumps  and headers.
Hence depth affected  cost  estimates in proportion to the  importance of well point
installation, which was low compared with  the importance of other  components such as
pumps and  headers. The pumping rate, which  varied with the size of the pumps and the
header  system,  should  affect both  capital  and  operation  and  maintenance costs.
However, no relationship could be identified in  the gross data.

The  most significant cost factors that could be identified was the  inclusion of related
costs.    Over  half  of  the SCS  "Impoundment"  estimate was for  a  geotechnical
investigation, that  was not included  in  either of the  other  estimates.  The SCS
"Impoundment"  and "Landfill" estimates included overhead (25%)  and contingency (25%)
allowances.
                                                                           «

Estimates Sources
            Radian, 1983
            SCS, 1980
                                      -62-

-------











f^
^^
w
gfl
<
S
P
S
H
O3
O
U
2
u
H
172
^
03








^N
CO
a
1-1
1-1
o
c
en
ON
^^
II

i
(0
o
u
4J
•H
e
5
to
_j
^^
o.
eg
u
^M AI
peration 1
aintenanci
OS
01 > J<:
o "o o
vO r- o
^ ON O
^^ ^^ ^^
 <0- ^H


1 1- .






Q.
01
01
*"
CO 4J
fH 0)
•^ .S !
V ^^ 1
»
vO
C
01
"5
wo!
US 00 g
to O ON J;
s w ^ r
1— 1
01 x-\

*>. >-*
" m
00

<-7
J
o
^
^
 (O

&
00
vO
7 !

CN


*

a
01
V
a -o
3 u
O) 01
* 01 1
vw j
en
en so
i-l iH

S^
_,
u o "2
w oo £
W5 U ON .3
3 t/3 iH j






iH
0)
^n
O
00


1
CO
oo
d
«>


e QJ
O> 01
00 M-l
o o
0 iH
m






3)
(0 0)
•H 01 U
4) 01 _C

O m  ec -H




































                                                                                                                                         »•« /^
                                                                                                                                         in »ss
                                                                                                                                          cn  »
                                                                                                                                          o  o
                                                                                                                                          u  u

                                                                                                                                          C  C
                                                                                                                                          o  o
                                                                                                                                         m re
                                                                                                                                         ec ec
                                                                                                                                         CB tfl
                                                                                                                                         o at
                                                                                                                                         > >
                                                                                                                                         C C
 ce  ca
 u  u
•H TH
 C  C

"y "u
 u  ai
4J  U
 o  o
 u  a
 ce  co
 ai  ai
T3 T3
 s  s
                                                                                                                                         C  C
                                                                      -63-

-------
i,
r
                                                                      Permeable treatment beds
                                                                      Deep well system
3.7 DEEP WELL SYSTEM

3.7.1       Definition
Aside from  going deeper,  deep wells are typically drilled and cased, in contrast to
shallower, driven well points.  The deep well systems considered in  this section are
intended to dewater soil at greater depths, for extracting leachate or intercepting ground
water flow upradient of a site.

3.7.2       Units of Measurement
Costs are given in terms of dollars  per welL  Cost per well per foot may also be useful
but available cost estimates assume the same depth scenario.

3.7.3.      Sum raary Data

3.7.3.1     Expenditures
No expenditure data was available at this time.

3.7.3.2     Estimates
Cost estimate ranged from
           $4,862
             to                (both weHs were at 46 feet deep)
           $13,513

These estimates  are the low and  high end  of the ranges of  the lowest and highest
estimates.  It should be noted (see Table 18) that 62% of the lowe estimate and 85% of
the high estimate were for (1) geotechnical investigation, (2) overhead allowance (25*);
and (3) contingency allowance (30%%  On a cost per foot per well basis, the above cost
range would be $106-295/foot/welL
                                             -64-

-------
•
   If
   1
   I
                                                                Permeable treatment beds
                                                                Deeo wellsvstem
3.7.4       Factors Found to Affect Costs

3.7.4.1     Expenditures
No expenditure data are available at this time.

3.7.4.2     Estimates
The following factor affected the cost estimates.
     o     Well depth
     o     Well diameter
     o     Pumping capacity
     o     Inclusion of related costs:
                  geotechnical investigation
                  overhead allowance
                  contingency aHwance


Variations in  well depth are not quantified by the data, but well drilling costs tvp.ic.aHv
vary with depth.   Variations in well diameter  are  also  not given in the data,  and
therefore  are not quantifiable, but costs for larger diameter  wells are generally
proportional because of increases in labor equipment and  material costs.  Submersible
pumping capacity effects  on capital costs  are  difficult  to  quantify  because of the
importance of hydrogeology to well yield.  Increasing the pump size may have no effect
on well yield if the  well does  not recharge quickly enough to justify the larger pump.
Hence,  any  consideration  of  cost  functions  for  pumping capacity  must  regard
hyrogeology, -pump capacity and  well design.  Electricity costs lor pumping comprised
about 5-10% of the operation and maintenance costs. Hence, this cost component, which
varies directly with pumping capacitv has a relatively  small effect on costs compared to
the other operation and maintenance cost items-sampling and analysis.
                                       -65-

-------
                                                                 Permeable treatment beds
                                                                 Deep well system
      Related costs had the greatest discernible effect on cost estimates since they comprise
      the majority of both estimates.  Table 18  shows the proportion of total capital cost
      Involved in these related components for cost estimates given in Table 19.
1
f
E
                                        TABLE 18.
                       COMPONENT COSTS OF DEEP WELL ESTIMATES
Estimate
source
Geotechnical
Investigation
Overhead
Allowance
Contingency
Allowance
Total
      scs
      'Impoundment"
                       30%
25%
30%
85%
      SCS
      "Landffll"
                        7%
25%
30%
62%
I
The reason for the significantly higher proportional and absolute cost estimate for the
smaller impoundment (1.16 acres, 5 wells) compared to the landfill (13.4 acres, 13 wells)
is unclear.
      Estimated Sources
           o     SCS 1980
                                           -66-

-------
I.

I
n


I
               55
               s
               H
     s
O  a
u  «§
               tf
               o






^
ca
U
<-M
a
w
i^
^* i
&^
a
CJ






>40I
U
cc
03
•HC
JJO
(QW
we
O>i
M ••
K£3
oz








sc
c
«^
e.
£

^«
^^

a
^

b
&l
^

!3
*M
•o

»
f
u
&
•j







a
•j
h>
3
O
tfl
O
^j
•^
a

^H
•H ^>s
01 — 1
^ W
^•fc
f^
^^
m
<••>
•H
•
1
f>
•a-
•a*
•
fx



-N.
0
CM
O\
•
o\
4 u
«-H (3
«-l 01
• X
O\
f_f±
v>
a —
0) U
4J 01 C
O T3 01
0 - 1-
« it< n u
1-i
A -9 O V
IH f»> JJ to
05 m i*
W bi Q
01 CO 01 J=
E C.'Q U
js E ra 05
3 3 01 -H
to C.-C -3





u
a >
•u a.
ai
•0 09
01 09
*J jr ^
01 O i-l
0) C V
«-> i-l 3

so so m
•a-






r
^J
 
01
p CO
01 1-
•O «3
• a x:
0) C. 01 U
IH J= £. ca
• J l-t -H
1-1 >H 4J 01 *D
09 O >
b • O «S "O —
o cn MJ w 01 u
E o. OO^H c
J E «T <-l 01
3 S 03 O «H Ui
81 C. CT> U u-i U


•


(J
S. >
u a.
01
•a ca
01 n •
4J JS ^H
o) a  e 01
«M -H 3

\o so m
»» -H








•
7-1
^•4
< *
a. u-
U >
£ U
0 C
•H flj
ji *n
•* C*J
- c
ec —
•H J_l
u c
05 O
ai u
^
e -c
iH CJZ
a
^^
a .-*
U i^
•H LH
C c^J
"o aj
o» -o u
U R C
O OJ S
o ^: 3
to u o
01 -H
01 > r-.
u o c
•a
3 » *•• ^
iH >^ E~?
U 8^S O
C r«- c*i
H« N^ ^^
^^
pg
N-X









•
eu
u
c
to
3
— . O
»S? mm*
f*+ F^
0 r-
tn n
/»s
C *£
0 O
1-1 f-1
4J V*'
ra
eo ^
i-l U
•u c
Cfl 0)
O 00
> c
C -H
1-1 AJ
c
^* o
a u
u
—4 *T^
•I" ^
c c
i r;
0
0) -^
•u »>?
o y^i
a; tN
60 ^'
o) -n
o< TO
•U 0)
^H W

c >
«H O

rf^

-------
                                                                Ground water & Leachate controls
                                                                Extraction-'Injection Well Syste n
I
I
G
1
I
          EXTRACTION/INJECTION  WELL SYSTEM
3.8.1        Definition
Extraction/injection weEs are  usually well points, which are  driven into the ground,
unlike deep weUs which are drilled and cased.  A series of extraction and injection wells
(well  points or cased, drilled weUs) is given as the design basis an which to compare
costs. Costs for a water treatment system, are is not incuded in this system*s cost. This
system  is sometimes referred  to  as  a  leachate recalculation  system  or  plume
containment.  In addition to ground water decontamination, this system may be used to
control leachate migration.

3A2        Units of Measurement
Total capital costs are given instead of  unit costs for two reasons. First, unlike most
other remedial technologies,  extraction injection systems  are composed  of several
components that are not readily sum marized into a simple unit. Extraction, injection and
monitoring weBs all comprise roughly equal parts of the system. Capacity in terms of
gallons per  minute was not used because of its dependence on hydrogeology, and this
information was not usually available.

3&3        Summary Data

3.8.3.1      Expenditure
No expenditure data was available at this time.
*     3.8.3.2     Estimates
      A range of cost estimates cannot be given since the units of the two estimates were not
      comparable. See Table 20.
                                             -68-

-------
If


o
CN
td
(0
Z
o
1
u
*«^
to
1 .
M
a
fH
fH
0
O
CN
00
ON
•H
        O
l-l
CO
^j,
•H
a.
3

fH
a
jj
p
H

•40)
ation
itenanc
wu
4hH
on
OZ





60
e
l>4
Oi
CU




0
•H
JJ
U
41
^-i
B
M

|
JJ
U
0]
hi
4J
X
b£





01
Q
^4
O
en

a
JJ
(8
o




CN
en
«»
»
fH
CN
f*1
<«•


01
•H
60
JJ
i
JJ
tw oi
CU 01
U-l IM
00
o> e o
fH no
j3 WO
•H JJ •
J= 00 iH
U hi J=
e oi oj u •
•H E 0. C 01
JD B «H a
•3-33 ^»
oo aoo a

U 0]
3  J3 ^.
JJ
^s M
l« 3
HS S
^s . «
a> M a u
»H eg 5
• QJ 01 S
1*. J 13 &






3 1
^
<
CU 1
u o
M 00
W 06 CTN
an «-<
 > iw
•H "*.
bo o
m
jj •
0 "^
* ?
%_<•
>,
t? JJ 60
60 -H C
S 0 -H
*^ -H Ul
00 hi O
00 JJ JJ
. CJ -H
O 41 TJ C
r* r-i C o
 O
fH S « m








< e
2. CO
W -H O
•a oo
en tg o>
a ec *H




































































































«









^H
CO
jj
0
jj

^
O.
01
01
•u
JJ
0>
flj
w
u->
o
o o
m m
*
• rv.
en n
fH 
r- i
a n
»
jj
O 03
CN 0
U
CO
C 1-4
•H RJ
E JJ
3 -H
03 e.
03 fO
< u
*-s
CN
*«^









»
fH
tH
1)
3
H
a>
c-
a.
eo_«
o "o
in jj
- -H
Cfl
^* ^.^
0 E
C.
"C CO
a)
CO O
(5 0
oa in
^s
i-H
s,^







                                              -69-

-------
f
I
                                                                   Ground water & Leachate controls
                                                                   Extraction/Injection W ell Svsrtej
   3.8.4 Factors Found to Affect Costs

   3.8.4.1      Expenditure
   No expenditure information is available at this time.

   3.8.4.2      Estimates
   The following factors contributed to the cost estimates of the extraction/injection well
   systems:
              o     number of weDs
              o     depth of weHs
              o     diameter of wells
             *o     casing
              o     submersible pump capacity
              o     transfer pipe length diameter

..  The paucity of data precludes quantification of the effects of these factors.
      Estimate Sources
                 o     U.S. EPA, JRB-RAM, 1980
                 o     U.S. EPA, Radian, 1983
                                            -70-

-------
                                                              Ground water & Leachate Controls
                                                              Extraction Wells/Seepage Basins
    EXTRACTION WELLS/SEEPAGE BASINS
ag.1       Definition
A series of extraction weHs is used to collect ground water, and a seepage basin/trench,
which  is  sometimes  referred to as  "subgrade irrigation" is used  to recharge  the
groundwater.  As with the extraction/injection well system above, this system may have
a treatment system placed on-3ine, or it  may be used simply to control leachate flow.
Treatment costs are not considered in this section. Seepage basins are often applicable
in less permeable soil, such as the glacial till, where injection wells provide inadequate
infiltration.

3A2       Units of Measurement
Total capital cost is given instead of unit costs because, unlike  most other remedial
technologies, extraction wen/seepage basins are composed of several components that
are  not readily summarized  into a simple  unit.   Extraction  and monitoring wells,
teench/basin size and pumping/transfer equipment all comprise roughly equal parts of the
system. Capacity in terms of gallons per minute was not used because of its dependence
on hydrogeology.
T'1
(,
           Sum mazy Data
3.9.3      Expenditures
The one expenditure found was:
     Total capital
     Operation and maintenance
                                             531,269 (as gpm total extraction, two 100-
                                                      foot long seepage trenches)
                                             $27,500/year
The expenditure was for two extraction trench wells (one 80 x 10 x 4 feet, another*4 x 10
?: 16 feet) and two recharge ('injection') trenches (100 x 4 x 10 feet).
                                      -71-

-------
                                                                   Grour.,1 water & Leachate Controls
                                                                   Extraction Wells/Seepage Basisns
1
i
I
I
     3.9.3.2      Estimates
      The range given in the one estimate source found was:
          Total capital:                         $33,618 - 53,360
          Operation and Maintenance:            $10,856 - 11,812/vear
This is actually from a single estimate source that predicts a range for the U.S.

3*9.4       Factors Pound to Affect Costs

3.9.4.1     Expenditures
The following factors affected the expenditure
     o     Number of wells
     o     Size of wells
     o     Depth of weHs
     o     Pu m ping capacity
     o     Seepage basin design

Because  of  inadequate  data and  the lack  of  a comparative site  expenditure,
                                              •
quantification of these factors is not possible (see Table 21).  However, it should be noted
that many of  the  factors affecting this expenditure are similar to those affecting the
subsurface  drain,  especially  the  design of the extraction  well trench using stone of
decreasing size toward the Inside of the trench. This increased  capital,  but probablv
decreased O&M costs.

3.9.4.2     Estimates
The following factors affected cost estimates:

     o     Overhead allowance
                                                                             *
     o     Contingency allowance
     o     Well size and number
     o     Pumping capacity
                                            -72-

-------
i
I
     S
     oa
X
           &   ^
           r^   a
•o c





^•4
09

^4
O.
18
U
fH
to

o
H


O «
U
e c
o n
•H C
4J 01
CQ AJ
H C
0) 
4JW
fc*-'





V
u
^
3
3
CO

a

a
a









/_
*H
S *
CM y

^>4 f»W
CO |^






at
fH
e •*
a a
60 M
0)
•; J^ .
e> s a
09 a
•o
09 0 y"
a) at u
^^ u^
O vp
e o a\
0) »H ^ p>4

*j 
co u a
K 01 W
re *j o<
re c.
>> 3 0
IH a
01 14-1 4J U
> 0 C C
•H 01 S3
*J PO E c
re -^- jj oi
> i— i n j-»
W 0) C
cj at w 11
en ^ u re
c c E
O O 1-1
y u .£ 
— 1
A .
J= U

a. u
— -. U_|
o
C u-i
o .
u CM
w
• 01
C5 4J
"5 0
CJ —
S (fl
-H i— 1
13 .H
= V
Q 2

^-^
»~^
S./




                                             -73-

-------
                                                          Ground* a r,or & Leachate Controls
                                                          Extraction W ells/Seepage Basins
The overhead had contingency allowance comprised 25% and 20%, respectively, of the
total estimated capital cost.  Well size and number would be expected to be proportional
to the cost, but quantification is not possible without other estimates for comparison (see
Table 22).   Pumping capacity would also be expected to be proportional to cost, but
hydrogeological factors affect this on a site specific basis.

Expenditure Sources
     o      ELJ/JRB Case Studies, 1983
                                      •
Estimates Sources
           SCS, 1980
                                       -74-

-------
i

I
F
CM



U
S    i
       H^
       ^^
CD    °

^    S


iH
a
a
u
^
CD
O
H

«4 0)
U
e e
O CQ
•H C
a «
u c
0)-H
CL«B
or

00
c
a
e*




e
0
•H

U
0)

"c"






e
o
•H
^J
u
ce
u
4J
X
U



w
u
3
0
CO
a
u
a
o

o
SO
0
•k
1
00
1— 1
\c
•k
r">

f **
« 2
o> §!
^^ 1 ^^
, > VO IN
§ s ss
^4 * ^5 »^
* ^D *j ^j
^^ ^H .— .—
**•
0)
JD
09
i.
0) 09
JO.
E
•H 3 3
09 09 O.
•O 
-------
I
                                                                Ground water ft Leachate Controls
                                                                Subsurface Drains
     3.10 SUBSURFACE DRAIN

     3.10.1      Definition
     A  subsurface drain is basically a gravel-filled trench  capped with a low permeability
     material.  Often, broken tile or perforated pipe is laid along the botton, running into a
     coHectSon sump or tank.  The backside and bottom of the trench  may be lined with
|    plastic or clay  before being filled with gravel or tile.  Subsurface drains are intended to
     intercept and collect leachate or infiltrating water.

I
     3.10.2      Units of Measurement
     The unit costs  for subsurface drains are given in dollars per unit length for three trench
     depth ranges because it facilitates quick cost estimates from a single trench dimension.
     Trench depth was found to be the greatest single factor affecting costs.  The ranges in
     depth given in  the Sum mazy section 3.10.3.1 were determined by the aggregation found
     for the costs of the different trenches. This may have been  caused by technical factors
     discussed in section 3.10.4, such as type of excavator used and need for sheet piling.

     3.10J3      Sum mary Statistics

     3.10.3.1     Expenditures
     The expenditures for subsurface drains in three groups of depth ranges were:
                                            /
                 Cost per Unit Length                      Depth
                       S24/LF                            3 feet
                 X -   S370/LF (S£-$208/LF, n-4)          8.5-14.5 feet
                       $1,733/LF                          22.5 feet
      The 2 subsurface .drains at the high end of the range involved significant marginal costs
      for false-starts, delays, and overdeslgning.  The lowest cost drain was shallow enough
      that it aid not require sheet piling or wooden shoring during construction.
                                             -76-

-------
I
                                                                Ground Water & Leachate Controls
                                                                Subsurface drain
Operation and maintenance  costs  involve  sampling and replacement costs.  Drains
typically remain undogged for 10-20 years,  but site conditions and drain design affects
this operation period.  No O&M costs were available for expenditures since they were
either accounted for separately, or were not yet encountered and documented.

3.10.3.2    Estimates
Cost estimates for subsurface drains ranged from:
                  Capital-
                              S1.94/LF
                                to
                              S218/LF

                  Operation and maintenance:

                              $10,337/year
                                to
                              $ll,293/year
                                             *
This two order of magnitude cost estimate range resulted from included costs and depth
variations.   The highest  cost  drain included the cost for a geotechnical investigation,
which accounted for 50% ot the estimated cost.  The lowest cost hypothetical drain was
1-2 feet deep. O&M costs were frequently noted but not consistently quantified.
                                             -77-

-------
I
 3.10.4      Factors Found to Affect Costs

 3.10.4,1    Expenditures
 The following significant factors were found  to affect the costs of subsurface drains
 shown in Table 23.
            1.     conta minated soil re m oval
            2.     trench (filter) length and depth
            3.     plumbing complexity
            4.     gravel installation
            5.     storage tank or sump size

 Contaminated  soil, which may  require secure  disposal, may -be  encountered  while
 constructing the trench or the sump. Excavation of contaminated soil, which resulted in
 additional costs for  disposal, occurred  when trenches  were  constructed  within a
 contaminated area, rather than at the site perimeter.  This additional cost was incurred
 at the ELI/JRB Wisconsin  site *1  where hexavalent chromium contaminated soil was
 disposed of from the hole excavated for a sump.   The PC8 contaminated soil at the
 ELI/JRB California site *1, however, was returned to the drain cap because the system
. was considered  an "Im mediate  Correction Plan", not a long term remedy.  This provision
 avoided the cost of off-site disposal of the PCB soil

 The importance of the trench length and depth is 
-------
I

I
            CM
L^
u
£
*>
5
^
S
C/2
                         CO
                         p
                         0
       o
       o
       CM
       ce
       ON

l-l
(S
1-1
a
CO
u
i
CO
o
cj

4W
•H
»
•o
CO 01
u
e c
0 C3
i-l C
4J 01
(0*J
u c
fljil
a. co
OE
*
U
01

t»
^™
a

•a

1




^J
4J
•o
^^


u

01 4-1
via

x"°
^^
JH ^
001
eoi-i
O-H

"^
Ol
u
-
o
M
4.
CO
a





S
£^
en
C1
^
*
tH
V>
§
in
/-s « CO
-^ XI -H C
o ~ 10
0 0 -s
O Wi O «H
• CO O  »-'

i— i
01 CO
> 0)
4j a, c.
Ol i-l i-l
cu a
**4 0)
1-H C
m o. 


/-^
O y-^ .
*-" in 4J
• a/
4U  *U
3 U -H 0






b.
«J

v£>
PO
^^
0-
^
'c'
(g CO C —H
>, -a E iia
P^ f3 « ec°
Q U O O
f»"} X L4 ^^
 iJ ^

^H
01
J

4J Q)
Ol JS
01 U
(41 9
o -°

C^l «ff
f-t
» O n
I-H 00 I-I
3 S i-H U






d.

^^^
^
CM
-cr
to-
-
w*4
^ tt
O J3 60
. Ui  0.1-1
a n
E K T3 «-i
3 00 C 01
CO 3 >
ce o eg
O 01 V. (-
C O. 35 60



^>
a*
Ol
^d

**


^^
u
N-' 4J
Ol
4-1 01
0) w-
ft) X
IM x"v
vO
o ^
CO O
CN iH

X
3)
a ij
< as o
ft. -1 n
"" i-i oo 3
CO J ON O
S U <-4 Z
1




^»
2

ft.

^^.
i/^
00


o;
ec
^j
o
c

e
11
co

•D
4J


11
00

o
c



4J
01
Ol
01
01 X *-*
vu v£

O m

ON 00
«

^
ts re
< as oo
c. -^ —
M ^ 0 J=
l-l 00 U
V) -J ON il
3 td I-H Z

                                                                                                                                   c     °
                                                                                                                                   o     u
                                                                                                                                         o
                                                                                                                                         c
                                                                                                                                         u
                                                                                                                                         V-

                                                                                                                                        •3
                                                                                                                                         C
                                                                                                                                         c
                                                                                                                                   cc    11
                                                                                                                                   0>     U
                                                                                                                                  .C i-l MI
                                                                                                                                   C  C  i.
                                                                                                                                   C  3  O
                                                                                                                of  S
                                                                                                                CJ -i ^~
                                                                                                                w  3  u
                                                                                                               .c     c
                                                                                                                                  O  E.  S
                                                                                                                                 •H  «3  wo
                                                                                                                                  CO     O
                                                                                                                                     o  >.
                                                                                                                                 K ^  ±J'
                                                                                                                                 E  o
                                                                                                                                 ra  c
                                                                                                                                 u  f  w
                                                                                                                                 •8  _C- i

                                                                                                                                 ij  e. r

                                                                                                                                 u  u  o
                                                                                                                                 j=  >  c
                                                                                                                                 r-  C.  —
                                                                     -79-

-------
1!
I:























'continued)
•^^
f>
CM

K>
to
£
^



































C/5
5" ^
3
CM
g
f"*
fi
z
rv^
M
&
ff
Z<^
2
^^ w
™ to
3 3
•M Q
a *
ec
a £
u -
!<
g
^/
• tX
«M*

5*
r^%
C/J









I—
It
4.
"c
IS
u
1
^
CO
c
u
4J
•H
c
=>
•o
C 01
CO U
era
*• (g
0 C
f> O
•U JJ
a c
*--H
O (6
<§-E
•
u
4J
flj
w
•1
f"
4J
a
ai
•o
a
3
CO




X
u
•o
1-1
»



j:
U<£
Cu
Oi C.
I. O
AJ-O
Xx~>
b
J= 01
U JJ
OO-I
c —
Ol'u*
J>^
01
u
k<
o
VJ
«
4J
18
0



u



g
vO
f*^
^f&




»
fH
u S
a~ M
0) «8 O
>,>- §
i: o
CO .
*3" CM
vo rs.
v>


JJ
01
01
«M
«o
tH



4J
01
a
VIM
sr


jy
ai
0)
UH
JJ
41 /-\
01
<4M
X *— '
0
sr
CM CM
iH

CM
^te
^
y>
< ca e
^.2 O
u ~) w
	 ^H 03
OT M ec -*






b-
*^-
CM
V>





e
01

^H
C£
^ j
«J
O


• •
09
& JJ 0-1
E 01 01
3 01 01
0) U. UM '
CM -» \O




U
01
0)
UM
CM


,*J
V
0)
^4
XJ
U^
^N
OJ en
y^ ^NM

o x ^
l/^ ^™^
Ml ^^
p^
f*"l


*fe
^*4
e ca
< sc c
EH ^^ CM CJ
«- oo o:
tn -J CT» JH
Z^»J^ 2 Z3LxJ^H 2
                                                -80-

-------
                                                              Ground Wat;r ±  Leachate Controls
                                                              Subsurface Or.un
      pililng and the New  Jersey, site which used plywood shoring, the cost of shoring was
      perhaps the most important factor in the different case study drain costs.  The available
      cost data breakdowns are inadequate to quantify this relationship, but the cost difference
      among these shown in Table 23 suggests its significance.

      In addition to trench depth, the filter depth varied among the sites.  The depth of the
      filter affects the amount of stone on gravel fill installed, which is much more expensive
      than the same volume of backfilling.

      The plumbing complexity of the collection pipe running the length of the trench ranged
      from a single pipe to multi-level pipes.  At most of the case study sites a single pipe ran
      the length of the trench and either drained into a collection sump or as in .the case of the
     . New Jersey site, was drained by an extraction pump.  At the ELI/JRB California Site-*!,
      three levels of slotted PVC piping were  installed in each  of three trench arms,  with
      valves into the  sump at each level to control the  flow from the different cdl-lense
      depths.  The cost for design, materials and installation of the trench plumbing part of the
Ji     system at the California Site *1, was significantly higher than the other case study sites.
                                                    •
ji     The gravel fill installation procedure affected the costs of the drain at one site where a
      different design  was  used.  At the New Jersey site, an outer layer of 1/4"inch (0.6 cm)
!:'     washed stone was placed around an inner layer of 1 1/2" inch (3.2 cm) stone, which
*•     surrounded the collection pipe.  The purpose of this relatively complex design  was  to
i      provide  filtration by the outer layer and high collection rates from the  coarser inner
      layer.  This added expense was intended  to obviate the need for future operation and
      maintenance  costs for clearing the clogged  pipe.  Reconstruction  of a drain installed in
      1976 that had become clogged was necessary at the Michigan site.  Drains at the other
      case study sites used a single size of stone cr graveL

      The second cost item included in the costs of the subsurface  drains is for storage  of
      collected  water in sumps or tanks.  The New  Jersey site -was the only ate  for wnich
      leachate  storage costs  were  not  included  because the collected  water was.pumped
      directly into the treatment system.  The inclusion of sumps In the other case study site
                                             -81-

-------
                                                         Ground Water & Leiohate Controls
                                                         Subsurface drai .
     cost  assumes that  the size and  cost of sumps and storage t^nks  were generally
     proportional to the size of the collection trench.  The storage svstems differed in types
     as well as size. Large prefabricated concrete sumps were used at the end of some drains;
     whereas steel tanks or pipes were used at others.

     3.10.4.2    Estimates
|    The following factors affected the subsurface drain cost estimates shown in Table 24.

T          o     trench (filter) depth and length
           o     storage tank or sump size
|!          o     inclusion of related costs

 I'    Trench and filter depth  and length had effect on drain estimates similar to that described
 '    .in the expenditure section above.  However, technical details' such as the filter/jacket
.     gravel size and the  depth of the  filter vs. the backfill were less often available for
•     consideration.

11    A wider variety of storage tanks and sump sizes was found for the estimates scenarios
     over the actual expenditure sites.  In most cases'however, no information was available
| :'    about sump and tank sizes.  The influence of this cost factor on total capital costs as
     well  as on  operation and maintenance costs  from varying  storage  capacities may be
 I'    significant.
 1
r    The SCS estimates were significantly affected by the inclusion of related costs such as:

,                -     geotechnical investigation
I                -     overhead allowance
                 -     contingency allowance
                                             -82-

-------
.
                CO
Cs?
u

u.
        a
        t-
        a
                                CM
                                00
                                ON


03
O
U

AJ
•rt
c
3


•o
CO)
CO U
c
en;
OC
•HOI
4J4J
we
1— H
Oi eo
C.E
o
*
u
4J
01
*
f,
•o
1
tn


^
•a
5
"y
C.C
QJ4J
W.D.
4J 0)
•o
X

.e'u'
4-1 (U
Otl-4
-Ju-
01
U
s
0
tn
a
4J
ce
a
CM
u.
ii
eo
fH
CM

1
m
i— i

to
01
^ •

r- eo E
CO ON QH
CO CM 00
CP'IH' o



w e
O -H
01
j: o.
4-1 ft
a o.
0)
•0 C *J C
0) C -H
a > oi a
e ft E *
3 00 0) *O
03 U

01
01
**4
(0
co
tH

4>l
01
4J QJ
Of *w
0)
u- ,-s
X -»
ON \O
fH fH

c
S
13
C
ss §
& a c
so E oo
W O H- ON
3 en r fH


fc.

^.^
00

1

\O
CM
CO
01

1 *"*^ •
f>. co E
CO »^^ ^^
CO H O
tH tH m


c
oi e
^ ^1 ^
•H C «B
00 01 hi
4U 01
O U C
C -H
j: o oi
U CO.
Q. -H 11
0) a
•u sr

01
01
IW
co -
CO
c
^
QJ
OJ
^ t»M
01
01 /^
^ t^l
X fH
00 CM


" ,t
fH
iH
a. "go
tJ C (JQ
CO ^ ON
tn u «J -H
3 C/3 S
j •>







J
*^«fc
CO
CM




oo E
oo a
• *O 00
o oo
r-. z o
 y^



4J rj
2 >
c a.
JS fj
a. 25
oi eo CB
•D CUP
0) o T3
C. > tw
3 OO 01 -H
to a

4J
01
01
Vw
**
C
1-1
.U ^
0) V
(V u*
lu

o o"
§ »< d
0
tH CM




^
c- e
W eo
•H CM
v. fj oo
2? eo ON
02 -H







b.
cj
in


E
e c.
01 00

•H m
00 CM
*-> X
0

•
Q
"o
re
.. 01
03 tH CO -
01 — '
•c co
C U  01
0) 01
tM IM

o ^-^
O X CM
C3
pn fsj

•


y
0. K
W | 0
a oo
to ec ON
•p *^ t~*

                                                                                                                                        a
                                                                                                                                        u /-v
                                                                                                                                        •^ **s
                                                                                                                                        G O
                                                                                                                                        £. m
                                                                                                                                        o «^
                                                                                                                                        01
                                                                                                                                        tn
                                                                                                                                        o
                                                                                                                                        •o
                                                                                                                                           C
                                                                                                                                           0
                                                                                                                                           ec
                                                                                                                                           tn
                                                                                                                                           01
                                                                                                                                           >
                                                                                                                                           c
                                                                                                                                        n

                                                                                                                                        w
                                                                                                                                        u
                                                                                                                                        X  *

                                                                                                                                            i
                                                                                                                                        M fi
                                                                                                                                        3 "i
                                                                                                                                        C  C
                                                                                                                                        f  u
                                                                                                                                        K  cn
                                                                                                                                            c
                                                                                                                                        O. rH
                                                                                                                                        U  O

                                                                                                                                        •3  >
                                                                                                                                        •*     0)
                                                                                                                                        U-  0]  >
                                                                                                                                        >-'  > -rt
                                                                                                                                         w  E  U
                                                                                                                                         CSC.
                                                                           -83-

-------
<»s
•a
01
c
•H
4J
C
o
u
>^
<•
CM
U
*
£
$

O
U
Z
I
a

u
<-
1


/-*
03
W
ca
1H
1-4
O
CM
co
C7»
r-l

C/3

4J
03
O
u
4J
*^4
C

T3
C Ol
a u
e
C CD
o e
_4 m
^^ w
*ju
« C
I--H
Ol CO
O.E
f—J
•
u
J^
Ol
*
X
JJ
a
Ol
•o

a.
3
CO
j=
4J
•c
—i
9
j=
y.s
c «
oi a
d Ol
4JtJ
X^M.
*^
id
X 0)
4J JJ
00-1
C— t
01 u-i
J^-'


V
u
u
3
0
C/3

«
u
a
a



t.
^
in
•
in


01
•H
J3
03
I t ^J
*• f"1
0 -H
e CD
CO



e
4)
•"-" >
O -H
C 00




Z
01
4-1 >
o •*
C 00

4J *J
01 01
Ol 01
U-l Hi
0 X *-*
in e-
CM ^^
«
o in
iH
X
TJ
3
4J
en

>N
^ U
*^ 2
X •«
< £
£ Z 03 0
CM « »
eyj 55 * 2
Z> u b. ^


b.
^y
C7>
•
i— 1


0)
f- (
J3
CO
ii ^_J
•J ^^
O IH
«= a
a


TS
at
4-1
4J
O
1-1
CO

ST

C
Uv
" >
O -H
e co.
4-1
V
4-1 01
U »-l
Ol
U-i /-s
^«
m x *•"
c^
«» CM
• 1
CM fH
>,
•o
4J
CA

>s
•« M >>
iJ CO OJ
— CTi y)
11 ^H t-
< J3 OJ
a. -H —.
u °>
CB 3
M 01 Hi
S b. Z
I
fa.
*J
b. O '— 's- b.
" * -^ i ~^« «
,-j r*- _ M- »—
***^ • **»^ ^*^. **^
CNJ i»i f** iT» <•
^ j ^_
v»-  v> 
«





c
01
*J >
O i-1
B a


e
o
4J >
O ii
B 00

u
0) jj
O> 0)
Ui oi
Ml
0 X
«n <-s
CM C"
•• ^^
cn m
iH

U
U
n

C/5 iH
>• — J -M
3 ;-< 35 ^
*^» —M C3^ ^
< X, o
a. Z >•
" CM^ 3
CO Z ^H 01
a u GQ z
                                  -84-

-------
                                                      Ground Wat=r i Leachate Controls
                                                      Subsurface drdn
The cost of the geotechnical investigation was included only in the "Impoundment" drain
scenario estimate. This element comprised 50% of the total cost of the drain.  Overhead
(25%) and contingency (25%) allowances were added  to both the  "Impoundment" and
"Landfill" estimates.  The variations in the estimated subsurface drain costs from JRB
and SCS were caused by  a combination of two factors.  First, the JRB estimates used
unit costs at the high end of the range used by SCS.  Second, the JRB estimate included
three components not included in the SCS estimates.  However, since these items were
                                                           \
responsible for only $24.70 of the S694/LF difference  (11%) in total unit cost between
JRB and SCS, their influence was relatively insignificant. The influence of component
unit costs that were included was therefore  more significant than the  influence of
component costs that were not included in the JRB estimates.

Expenditure Sources

     o      ELL/'JRB Case Studies, 1983

Estimated Sources
^^^v_^                           •

     o     JRB-RAM, 1980
     o      Radian, 1983
     o      US EPA OERR contractor bids
    . o      SCS 1980
                                      -85-

-------
                                                             Aqueous ft solids Treatment
                                                             Activated cl-: .ge
f
E
                           4.0 AQUEOUS AND SOLIDS TREATMENT
4.1 ACTIVATED SLUDGE

4.1.1       Definition
This treatment technology involves introducing organic-laden wastewater into a reactor
where  an aerobic bacterial culture is  maintained in suspension (mixed liquor).  The
bacteria convert organic materials to carbon dioxide, water, metabolic intermediates and
am monia. Oxygen is supplied to the reactor by mechanical or diffused aeration  with air
or oxygen-enriched stream. Intimate contact between wastewater, sludge, and oxygen is
maintained.   A portion of the mixed liquor is continuously passed  to a settling  tank
(clarifier) where sludge is separated from wastewater. A  portion of the settled sludge is
returned to the  reactor to  maintain the proper  microorganism balance, while the
remainder is removed from  the system.  Typical equipment  includes aeration tanks
hasina, clarifiers,  compressors, aerators (diffused or mechanical), and recycle pumps.

4.L2       Unit of Measurement
Costs are given in terms of dollars per gallon treated. Costs estimates from one source
were  available only in terms of cost per pound of biological oxygen demand (BOD)
reduction.  Also, where available, system volume capacity assumptions  are given, but
cost per unit of mixed organic contaminant reduction estimates were not calculable.

4.1^3.      Sum mary Data

4.1.3.1     Expenditures
The following expenditure was found:

           Capital:              S6.3 miHion/Mgd (887,514/13,880 gpd)
     Operation & Maintenance:       S0.0165/gaL
                                             -86-

-------
                                                       Aqueous or Solids Treatment
                                                       Activated sludge
      This system  was a nutrient-enhanced biodegradation system, constructed with retrofitted
      5,400" gallon milk trailers for aeration and settling tanks.  It was not a standard factory
      constructed  activated sludge system, though the cost components were very similar. The
      operation and maintenance cost includes a relatively small expenditure for nutrient salts
      ($19.20/day; $0.0014/gallon; 8%).   The  use of used  or salvaged  material generally
      produced significant costs savings over the expected cost for new materials.

      4.1.3.2      Estimates

      Cost estimates ranged from:
           Capital;                        $200,000/Mgd
                                             to
                                          $390,000/Mgd

           Operation & Maintenance:       $18,0007Mgd/year
                      *
                                             to
•                                          S25,000/Mgd

F           The compilation of these estimates is unclear from the available data

i     4.1.4        Factors Found to Affect Costs

      4.1.4.1      Expenditures
      The following factors were found to contribute to expenditures.
                  Materials (used and salvaged)
'          -      In- house design and maintenance
           -      In-house power and process steam
                  System flexibility (access holes)
I
I
f
                                             -87-

-------
                                                      Aqueous or Solids T .•«.::-nent
                                                      Activated Sludge
i
i;
I!
t
Although no expenditure data is for a newly constructed system available for comparison,
the cost of this system given in Table 25 may have been significantly lower than if new
equipment and contractor labor had been used.  One cost item that increased the capital
expenditure, possibly unnecessarily,  was the construction of a roller mount and access
ports for the pipe air spargers.  This system was intended to allow the spargers to be
cleaned of bio mass buildup without sending a technician into the tank. This maintenance
has not been necessary in over 2 years of operating the system (as of August 1983).

4.1.4.2     Estimates
The lack of technical detail about the hypothetical systems for which estimates were
given precludes consideration of specific factors affecting the costs (see Table 26).

Expenditure Sources
     o     EU/JRB Case Studies, 1983   .

Estimates Sources
     o     Radian, 1983
     o     SCS,  1981
                                            -88-

-------
I
I
I
in
CN

u

ca
 CO

 to
iH
i-l


<§

CM
OO

1-H
a

o
to
u

u
01

^H
a
<£ 0)
U
e c
o to
•H C
•4J 01
to 4J
»- e
Ol-H
a «
or





e
01
(0
01
o








c
0
•rt
4J
<0
w
4)
<
01
a
.„
^
*j
_j
u
10
CL
a
u
01
u
3
0
CO
(0
to
a
•o
c
o
iH <-»
«-i sr

E Jn
co rT
• 00
NO 

*-* «
•O 60
00 >s -^
X to in
^. TJ vO
C^ ^v ^^
00 NO O
• CN| •
CM CM O
v> 

CD
CD .*
1- C
•o oi a
0) i-l 4J
jj a w e
•H U O 0
O W
W Ji -O 10
4J iH 01 b
oi «H ca oi
u e s as
m
0) U
G 01
O (0
•U 3
CO U-l
lAj
^E .e -H
*U 3 "°
O 01
ova.
 «-j
M 00 »
to j «r> ai
S ttl ^ Z




























































































































•
























































*




u


03

O
                                                                                                                       to
                                                                                                                       30


                                                                                                                       o
                                                                  -89-

-------
  K

  ea
Q   3
•—\   o
      (M

      00
E       ^
1-1
f-l
fr
3
^
u
4)

<<-l
0
*9 41
U
e c
O fQ
•HC
•U 41

hi C
41 •*
aea
OS







gj
60

09
4)
O




e
o
•H

to
hi
4)


11
00


,^
>>
•H
U
(8
o.
(0
u

41
U
hi
3
O
V3
(0

(8
O

•W "O -O
60 60 60
x z x
1 § 1
o o o
• * *
O O O
cr> m o
r"» p>4 CM
  
78 TJ IS
60 60 60
•2E ^ z:

o o o
o o o
00 O
* * *
m «7 oo
f"*J P*4 f^
  -H
hi JJ
4)
(0 C
O
hi 4i -H a
CO •*•* 4J hi
41 -H C 9
>< «H 41 O
O 4)
^ -B vO
Xt -O
^ 41

fM O
0 E
4)
Jl hi
f*^
m
^ O
• o
~4 0


^^
^•4
^^
^ ^ ^3
60 60 60
z z z
o o o
* • •
<-( m o
to
c
o
•H
^
e

< c >
a. to c t*>
U -H 3 OO
^3 rj G^
C/3 CO - i-H
3 OS
•

^^
Ci
•D T3
60 60

^^ ^N»
0 0
«N 00
00 GN
W 









4)
U
•H
hi
4)
(0

hi 41
CO «w
4) -H
>» iH
O
•H


C
41

•H
60

U
0
s:


i— ' E
*-* a.
00
•o
60 O
Z 0
0
ex •
. in
r*. >-•


oo
CTs
tH

^\
hi
•3
S Is

to 4i ey>
C/3 O Bu iH
rs w






























































































































*

^









                                                                                                           O
                                                                                                           a.
                                                                                                           c
                                                                                                           o
                                                                                                          f-l  K
                                                                                                          1-1  l-
                                                   -90-

-------
i,
I;
F
I
                                                          Aqueous & Solids Treatment
                                                          Aerobic, Anaerobic, &
                                                          Facultative Lagoons
       4.2  AEROBIC, ANAEROBIC, AND FACULTATIVE LAGOONS
            Definition
 Aerobic, anaerobic and facultative lagoons are large, usualLv earthen basins, which relv
 primarily on long retention times for hiodegradation of organic wastes.

 Aerated lagoons are 6 to 20 feet deep.  Aeration devices supply supplemental oxygen and
 partial  mixing.  A sludge blanket accumulates on the bottom and undergoes anaerobic
 decomposition,  A non-aerated cell usually follows to allow solids to settle before
 discharge.

 Anaerobic lagoons are deep (20 feet).  High organic loadings and an impervious layer of
 grease promote thermophilic anaerobic digestion.   Wastewater enters near the bottom
 and  exits  below the surface.   Excess  sludge is  washed  out  with effluent;  waste
 recirculation is unnecessary.

 Facultative lagoons are 3  to 8  feet  deep.   Wastewater is stratified into  aerobic,
Intermediate,  and  anaerobic zones because of settling solids and water temperature-
 density  variations.   Oxygen in the surface laver is provided by diffuse  reaeration and
 photosynthesis, not aeration devices.  The aerated layer also reduces odors.
                  Units of Measurement
      Costs are given in dollars per million gallons per day treated.  This cost basis assumes
      similar treatment effectiveness, as well as the use of extrapolation from total costs.
                                            -91-

-------
                                                         Aqueous % Solids Treatment
                                                         Aerobic, Anaerobic, &
                                                         Facultative Lagoons
                 Summary Data

      4.2.3.1      Expenditures
      No actual expenditure data are available at this time.

*     4.2.3.2      Estimates

j     Cost estimates ranged from
ii
•;     Capital;                       $0.08 miUion/Mgd         (7.2 Mgd)
I                                     to
                                    53.4 miUion/Mgd      (0.14 Mgd)
Ii
      Operation ft                   $0.005 mfflion/Mgd        (10 Mgd)
      Maintenance:                    to
                                    SL23 minion/Mgd         (0.14 Mgd)

      The cost estimates reflect widely varying scales^of operation assumptions.  Large (5-10
 I!     Mgd) scale  scenarios were at the-bottom of the unit cost estimate range, while smaller
      operations  (under one  Mgd)  were generally the higher estimates.   Also, the lower
      estimates axcluded certain related components such as land, pumping and liners.
ii
      42.4       Factors Found to Affect Costs

      4.2.4.1     Expenditures

      No actual expenditure data are available at this time.
                                            -92-

-------
r:
r
                                                       Aqueous & Solids Treatment
                                                       Aerobic, Anaerobic, &
                                                       Facultative Lagoons
 4.2.4.2     Estimates
 The following factors appeared to significantly affect the cost estimates:
      o     Scale of operation
                  land, pumping, liner
                  containers and overhead
      o     Removal effectiveness
      o     Aeration extent
      o     Climate
 As noted in section 4.2.3.2, the cost estimates were significantly related to the scale of
 operation of the scenario.  This results partly from  the economies of scale inherent in
 larger  operations,  but it also  reflects  the nature  of  these  papers  for specific
 technologies, and general construction estimating manuals (see Table 27).

 The large hypothetical systems estimated by Radian excluded the costs of pumping, liner
 and land.  These systems were si mil AT in design to those that would be part of a sewage
 or industrial treatment plant,

 A  contingency and engineering cost of  30%  was  included  in  the New  Hampshire
. Feasibility Study estimate. The inclusion of this cost in the other estimates is unclear
 from the available data.

 The  estimates include a variety of contaminant removal effectiveness levels.  These
 levels were generally given in terms of BOD  or COD.  These may not provide accurate
 estimates of removal effectiveness for many refractorv or highly toxic organics but thev
 provide useful standards for comparison.  In cases where removal efficiency information
 was available, no relationship with total unit costs was apparent. However, for similarly
 designed systems,*removal effectiveness would probably be proportional to cost.
                                             -93-

-------
               c«

               C
               O
!
                iS
I
        C/}
        M
        H
         H
         cn
cs

W

83
Q
Z

y


I

<
y
5
o







iH
«

O.
a
cj

fH
U
c e
o re
•H C
4J 01

w e
OJfH
are
OZ




4J
•H
U
a
a
re
cj












e
90
•H
0)
£




0)
u

3
O
OT

JJ
re

•o
60

^N^
e
o
•H
iH
•H
E
-3-
c
n
•
1
iH
rH
•H
E
•a

CM XI
fH


00 -0
oo
g *
O <4T
• «H
•» •
*3P O
fH v-'

•0
O
•H a
1- 0)
4J Q)
o. •a e
0
C •" fH •
Q 9> **
• •HOI a
JJ U-I V
C 0
at CM a
*J fH
'^ 3E
•o • £
U 09 U
M X fH
03 a fH O
O <0 4) O
os y in
W CO •>
<; CM «a* m
3
CO V
M
^% fH
4J _l"
CM iH 00
co fH a.
ON fH E
«< -H .a _3
w at "Z "~
os re s
to a D D
a o b. z
•o -c
00 00
z z
*»N» *^.
e c
0 0
•H -H
fH fH
•H fH
E B

0 O
* *
O 0

c c
0 O
fH tH
fH fH
fH «H
B E
•e -o
r*t 60 t^ 60
0 Z 0 Z
0 0
*"" **"




•o -o
00 00
.z z

fH 6
fH




0) .0)
E fH . UM
fH « fH
»W ^ ^H
Q
e E a)
o u u
fH tH fH
•U 0. >
C Q « h
4) O CU V
jj cj rj a
0) *>.
OT3 Q W »J
M ova
» >> ta v o>
09 <« -X
W "° CO O 0
< r^ co fH «n








•< s
Cu 09
W -H m
•o co
tO O 9>
3 OS fH

fj fj
00 00
Z Z
•^ *««.
e e
0 O
fH fH .
fH fH
E E
m o
* *
o o

•O 0
00 fH
Z «H
-•. fH T3
e fH oo
0 E Z
in fH
CM i-H m — '
fH t-4 O
O fH O
* B •
0 0
w  fH
i c o >
O fH B W
«H D. V V
y *< s ^ 3
M 3
03 >> a n i-
o u o re
BE: fH • « a>
m > -n x
< a c *x
Z 1- O O O
< oo r-t \o in


•





-< "
e. re
W fH (O
TJ CO
CQ re o^
s ec fH

•O T)
00 6C
z z^

e c
0 0
fH i-l
iH 1—1
"e "E
m P*
^ c
fH O
<«• <0-
00 00
z z

c e
0 0
in IH so fH
iH fH O «-H
O fH O fH
si*6* ® "^






•a -c
00 OC
z z

fH O
iH
^.j
-05 QJ
(U C
•0 fH

^H CQ CQ
o -c -a >
X C ^- O
cu a v E
}M ID
• • 00 U h
9 c re
W O fH *>. Q
> fH B. LOO
IH 30^
< :>> a. ea a
H *J O
J fH • J S3
9 > "O -H
owe »•«
< w re o o
&. eo
-------
•o
 0)
 3
• C
 O
 U
CM
CO
          z
          c
          o
I
I

a    s
§    £
          y
          3
          i








l-f
eg
4J
a
CB

^
iH
W
•a u
u
ec
o n
•H C
u ai
>* C

a. eg
or
^
o
a
a.
eg
u










eg
V
0




0)
u
3
O
a
1


•0 TS
60 60

^^- ^^
c c
5 5
•H 1-4
«H f-l
•^ taJ
B E
•n in
»o f>
o o
CM
tN
•a eo
*? *
^ e
m c so o
«H O O-H
O ^| O^
* ^4 '^4
O «_| O-H

"e **

•o -a
60 60


^ 0
n
w
v*H Q CQ
CJ -O -O >
x e *•» »
at a ai -3
h IJ
•« 60 O J-
» c eg
w o -H ^ a
> -< a in O
M IM £ O O
H 3 O •>.
< x a sa a
C-> 4J O
J -H . k. .0 CQ
5 > T3  0
M 1 §.
eo t- o.

SM O
O 0
< rx ^
35
a

o
•o
eo

< 2
eu V
tf i^
co ao "5
w u a>'d
D CO i-t B






























































































•









                                                                                                        tn
                                                                                                        o
                                                                                                        u
                                                                                                                 (b

                                                                                                                 /^
                                                                                                                 n
                                                                                                                  O
                                                                                                                 •c
                                                                                                                  CO

                                                                                                                  o
                                                                                                                  n
                                                                                                                 •60

                                                                                                                  C
                                                                                                                  O
                                                                                                        (6

                                                                                                        C
                                                                                                        C
                                                        -95-

-------
1
I
I
E
i;
i
                                                      Aqueous & Solids Treatment
                                                      Aerobic, Anaerobic &
                                                      Facultative lagoons
Finally, the extent of aeration varied among the estimate scenarios.   The cost of
aeration equipment, in terms of both capital, and operation and maintenance costs, may
be significant. This difference in design and cost also significantly affects
performance.  For example, the hypothetical aerobic system  had a presumed efficiency
of 88%; whereas the anaerobic system achieved only  60%.  This difference suggests the
need to quantify costs in terms of dollars per unit of contaminant removed per unit of
time when comparing systems for the same waste stream.  For facultative systems the
climate affects system performance and hence, costs.  The  system  in a warm climate
was more effective than the cooler climate system.

Estimates Sources
     o     Radian, 1983
     o     SCS, 1983
                                            -96-

-------
                                                       Aqueous & Solids Treatment
                                                       Rotating biological contactors
i
i
          ROTATING BIOLOGICAL CONTACTORS
      4J3.1       Definition
      This system is  a form  of  fixed film  biological treatment.    A slime  layer  of
      microorganisms grows attached to polystyrene or polyvinyl chloride disks 6 to 12 feet in
      diameter.  The disks are mounted vertically on a horizontal rotatable axis in treatment
      tanks.  Rotation of the disks exposes the slime surfaces alternately to both oxygen in the
      atmosphere and  organic matter in the wastewater.  Both oxygen and organic matter are
      adsorbed; the organic material is degraded by aerobic microorganisms. The rotation also
      mixes and  aerates the  contents  of the tank  and causes excess microorganisms to be
      sloughed off as  growth continues.   Excess solids are subsequently separated from the
      effluent in  a clarlfler. A complete  RBC system usually consists of two or more trains of
      disks with each train consisting of several stages.
            Units of Measurement
Costs are given in terms of dollars per million gallons per day treated, when available,
for comparison with other water treatment technologies.

4^3       Sum mary Data

4.3.3.1      Expenditures
No actual expenditure data are available at this time.

4.3.3.2      Estimates
Therange of cost estimates was:
     Capital:_                        S0.9 million/Mgd           (10 Mgd)
                                       to
                                     $29.6 miHion/Mgd         (0.144 Mgd)

     Operation & Maintenance:        $22,500/Mgd/year         (10 Mgd)
                                       to
                                     34.6 iiilTllnn/Mgd/year       (0.05 Mgd)
                                             -97-

-------
                                                       Aqueous & Solids Treatment
                                                       Rotating biological contactors
I
i
I
I
I
i
I
The range of estimates reflects a widely varying scale of operation assumed for the four
estimates from two sources. The high estimate is derived from dividing the total (capital
or 0 & M) by the treatment rate, in million gallons per day.  Hence this method of scaling
up the smaller system estimates may result in multiplication of some fixed costs.  The
low cost estimates are derived  from estimates for very large sewage treatment scale
systems. The actual costs can be derived by multiplying the unit cost by the treatment
rate.

43.4       Factors Found to Affect Cost

4.3.4.1     Expenditures
No actual expenditure data are available at this time.

4.3.4.2     Estimates
The following factors appeared to have significant effects on cost estimates.

     o     Scale of treatment
     o     Inclusion of related costs
                  overhead allowance
                  contingency allowance
                  settling tanks, etc.
                                            •
As noted  above in section  4.3.3.2,  the scale of treatment operation appeared  to
significantly a±fect costs (see Table 28). For this reason the estimate  may be of limited
comparability since the Radian estimate is for a verv large svstem, compatible with flow
rates at a. sewage treatment, or large industrial 'vaste plant.
                                                                             *
The effect of inclusion of related costs on the estimates is unclear. The New  Hampshire
Feasibility Study assumed an additional 303,  for contractor overhead.   Whether these
costs are included in the Radian  estimate is unclear.
                                             -98-

-------
i

L

I
r
i
eo
CM

W

C8
                        CD
                        la

                        (B
        O
       a
•^    ce
a    s
u
q
k-<
o
S
u
z

I
q








_J
«
4J
T4
a
 «o-
C C TJ
O TJ O 60
•H 60 -HZ
fH Z — 1
.H i-l
1-1 ^4
E E

xO ON
• •
•a- m

TJ
TJ 60
60 Z
z
•a-
m -*
o ^
• *
o o
. Id
• • xj U 01
iH «. ^H -H
 to -H
o TJ u eu
E c *J a eo
01 « C i-l T>
W 0) O 3
. -rt 1-4
03 t- la • 03
(U -J .U "(3
rt 3 3 .* «
•H 01 C C 60
xj e a e
a to u -H 01
i-i a ai >- <— i
O » TJ 60 0) O
> O 3 C u >>
fH I-l tH Cfl O
M iH O X & 01
O O C -H 01 la
tu IM 
TJ TJ
60 60
Z Z

c> ^
o o
in in
«k m
CM CM
en CM
 v>
^"%
r-l
«^
TJ
TJ 60
-.60 Z
z
0
iH ~i-l

to
iH .
T) TJ
U «H C
E i-i  O o
O O E -4
E oi
U 01 la 03 W
IU '-I U V-
« T! 0)
cr o IH s IH
03 U O C ^ W
(w aa o u IH
OR) 6x1-
O J= X E 01 (0
O 03 O CO i-l
.ON JJ CJ
O P 1 X to
O 4) O ON O o
iH 0.00 ON U CM




< C
ft. n
U 1-1 r-i
TJ «
W (0 ON
3 fi£ «H






















































































































*






\
                                                                                                                                   c
                                                                                                                                   c
                                                                                                                   u
                                                                                                                   C TJ
                                                                                                                   v re
                                                                                                                   u u
                                                                                                                   c .=
                                                                                                                   •H I-
                                                                                                                   j_i v
                                                                                                                   c >
                                                                                                                   0 O
                                                                                                                   u
                                                                                                                      to
                                                                                                                   «s -

                                                                                                                   60 O
                                                                                                                   C u
                                                                                                                   •H U
                                                                                                                   * BJ
                                                                                                                   U I*
                                                                                                                   4) .u
                                                                                                                   e c
                                                                                                                   •H O
                                                                                                                   ec u

                                                                                                                   O TJ


                                                                                                                   s g
                                                                                                                   •O  •>
                                                                                                                   u O ui
                                                                                                                   C PI CM
                                                                                                                                   0
                                                                                                                                  •o
                                                                                                                                  u


                                                                                                                                  en

                                                                                                                                  o
                                                                                                                                  oo
                                                                    -99-

-------
                                                       Aquous & Solids Treatment
                                                       Rotating Biological contractors
      Finally, the exclusion of certain system components from the Radian estimate scenario
      may have significantly underestimated the cost estimate, compared to that given in the
      feasibility study. The Radian estimate included only those components strictly used for
      the rotating biological contactor, excluding settling tanks, darifiers and chemical mixing
      unit.  Generally, the  Radian estimate hypothesized a unit to be retrofitted to a larger
      primary treatment plant.
      Estimates Sources
I
o     Radian, 1983
o     US EPA OERR contractor Feasibility Studies
I
•
I
I
                                             -100-

-------
                                                          Aqueous & Solids Treatment
                                                          Air Stripping
      4.4 AIR STRIPPING
      4.4.1       Definition
      The air stripping process enhances volatilization of volatile organic compounds (VOC)
      generally by increasing the liquid surface area and the velocity of the air passing by it.
|     Towers and basins have both been used; only towers are considered here. The typical
      tower is similar in construction and configuration to a water cooling tower.  W aste water
      enters at the top of the tower and flows downward over the packing, which may consist
      of piKgflc beads or piping.  An  induced draft fan draws air in at the lower sides and
      bottom of the tower and out through the top.   Basins,  which consist  of a temporary
      swim ming pool with a series of  spray nozzle across them have been used for leachate
      stripping, but no separate costs were available for them  at this time (August 1983).
B
I
           Units of Measurement
Costs are given in dollars per  million gallons per dav for ready comparison with other
water treatment technologies.

4.4^       Sum mary Data

4.4.3.1     Expenditures
The one source of actual expenditure data indicated the following costs.

     Capital-                         $182,540/Mgd (million gallons per day)
     Operation & Maintenance:        $9,921 - ll,905/Mg<1

No comparison with  other site data, is possible at this time since this is the only actual
expenditure information available (August 1983%  This  expenditure was significantly
                                                                            *
lower than those estimated with engineering/construction costing manuals.
                                            -101-

-------
I
I
I
I
I
I.
                                                        Aqueous & Solids Treatment
                                                        Air Stripping
4.4.3.2     Estimates
The following range cost estimates for air stripping svstems was found:.
     Capital:                    $607,000/Mgd          (1.44 Mgd)
                                    to
                                $7.3 million/Mgd        (0.0504 Mgd)

     Operation & Maintenance:        $89,000/Mgd        (1.44 Mgd)
                                    to
                                $3.2 million/Mgd        (0.0504 Mgd)

The range given is for two out of the three estimate that were available. The third cost
estimate is not shown in the above range because the cost estimate reflects only shipping
and set-up costs for a borrowed tower, not construction costs.  The above range seems to
reflect the economies of scale  for varying size systems.  The lowest cost system on a
unit rate basis ($607,000/Mgd capital; $89,000  O&M) was  the largest (1.44  Mgd);  while
the highest cost system ($7.3 million/Mgd capital; $3.2 million/Mgd) was the  smallest
system estimated (0.0504  Mgd).  Hence, in absolute terms the smallest system had the
lowest cost estimate, but on a relative, per million gallons  per day, basis, the economies
of scale gave a significant cost advantage to the larger systems.

4.4.4.      Factors Found to Affect Costs

4.4.4.1     Expenditures
The following factors appeared to affect the costs:
     o     Capacity (VOC reduction and flow rate)
     o"     Blower size
                                           -102-

-------
1
I
I
E
I
                                                       Aqueous & Solids Treatment
                                                       Air Stripping
For the system considered (see Table 29), the capacity was estimated to bear almost a
straight linear relationship with cost.  Hence, on a relative, per rate basis, the cost for
different sized systems would be expected to be similar. The Feasibility Study estimated
that the cost would increase about the same amount for each of the five towers added.

The VOC reduction was expected to be related to costs, but no quantitative comparison
is possible without more expenditure data.

The blower size significantly affected the operation and maintenance (O&M) since most
O&M  cost was involved In  electrical  power for the fans.  The O&M expenditure was
relatively low since power costs in the northwest U.S. were unusually low during  the
estimation period.
                                                              •
4.4.4.2      Estimates
The following factors seemed to affect the cost estimates

     o      Capacity contaminant (reduction and flow rate)
     o      Blower size
     o     Included costs
     o      Packing  material

Cost estimates varied directly according to flow rate of the treated effluent (see Table
30).   This variation reflected increased tower size, packing volume and  pump capacity.
However, on a per flow  rate  basis, of dollars per minion gallons per day (S/Mgd),  the
costs were inversely related to system size.  This relationship apparently reflected  the
varying economies of scale, which seemed to be the most significant factor affecting
costs. The least cost system  on a  unit rate basis ($607,000/Mgd capital; $89,000 0&?vl)
was the largest (1.44 Mgd); while the highest cost system (S7.3  million/Mgd caital; S3.2
million/Mgd O&M) was the smallest system estimated (0.0504 Mgd).  Hence, in absolute
terms the smallest  system was the lowest cost estimate, but on relative per  million
gallons per  day basis, the economies of scale gave a unit cost  advantage to the larger
system.
                                            -103-

-------
I

I!
  03
r   -fe
i



a
•rl
a.
a
u
i-i
•4 W
u
e c
o  in
in" ^
u
K 5
— — O
-• • JT la JJ

ki 14 •* S E
jj -a .c 5 >5
3 
-------
G
   fj     ^^

I  ta     Z
   "     M
Li 03     A
 CM
•co
 ON








^
«0

•H
B.
CS
U

3
•« Ol
u
e e
o «
•H e
^j 0)
re ±j
w e
cy ^^
a a
or


•H
U
CO

eg
U










£•
00
«H
0)
£






01
u
3
a
5/3
eg
O


•a -a
00 00
.X 3=

c e
O 0
•H «•-(
iH i-H
1-1 iH
E E

CO ^^
• «
r*» pn

1 1
i-l T3 i-l T3
i-l 00 *H 00
i-l X »H X
•H -H
E E

CM C^
i »
f» CM
4O- 
J3 E
.s S
00 S ?D 4)
•••M <^M ^ ^
f U O S3
^
u o o oo
§ S B "S
«-i a a
O J=

CM w m 1-4


3
§tn 01
w
to ir !c
a -^ 7i
3 ^-^ *2"
•H E
< 1 J5 tO
ON iH S
W Be! oo CM
OC CO 00 S
t/J U 01 O^ Ol
3 O b. »^ Z
•o
00

v^.
c
O T)
•H 00
-* 2
i-l O
E O
o
p*. •
O I*-
o


• vC
•a- •
^ii f^k
i-i m
•CO- *>
•O TS
00 00
X X

in IH

1^ vH
• «
O 00
O CM
•CO- •CO-

CO
• ^
•• •* ^3 o
Oi E oo E
00 • 3 X 01
re -a E b
(L^ MA ^H^ ^Q
01 X X ^ «4
> re • in
a «H e  >H
3 0 Cu -H X



                                                                  u

                                                                  o


                                                                  CO*
                                                                  u
                                                                  u
                                                                  c
                                                                  re

                                                                a 5

                                                                o i-
                                                                u 3
                                                                  c.
                                                                •U C_
                                                                c n
                                                                u
                                                                E  •

                                                                re K
                                                                o c.


                                                                  en

                                                                OK
                                                                  c
                                                                eco

                                                               •H e.
                                                                0.3

                                                               i-l U
                                                               ^ u
                                                                CO CO
                                                               •H C
                                                                C R3
                                                                o

                                                                01 C
                                                               •o o
                                                                3u
                                                               iH SC
                                                                u e
                                                                  03
                                                               01 CC
                                                               JJ3
                                                               CO
                                                               c *
                                                               o a
                                                                  E
                                                               r   o
                                                               rl O
                                                               re cs
                                                               e
                                                               u
                                                               c
                                                              <
-105-

-------
I
                                                  Aqueous & Solids Treatment
                                                  Air Stripping

The  contaminant reduction effectiveness of the various  systems estimated  was also
reflected in the costs. Since a variety of factors in turn affect removal effectiveness, it
is difficult to relate these many factors to costs. These factors and components include:
pumping rate (higher rates may create higher dilution resulting in lower percentage
removal but higher molar reductions); climate (effectiveness increases with  ambient
temperature); and  heating of treatment stream (may be  necessary to offset seasonal
cooling or increase effectiveness; significantly increases 0 & M).

The  variation in included costs is especially noteworthv for the system  estimated in the
Minnesota  Feasibility Study;  This cost estimate did not include tower construction, but
rattier only  included shipping  and set-up  of a tower  borrowed  from the Tacoma,
Washington site.  Although this  system was estimated for a four month operation (while
an alternate water was to  be installed),  the cost given are trebled for annualized
comparison.  All of the estimates given include engineering  overhead, at about 25 - 30 %.

Finally, packing types varied among the estimates and had some, unquantifiAble effect on
costs.  The proportion of  costs devoted to tower packing is unclear  but  the costs of
different packing  materials  of varying  effectiveness  was given  in one estimate.
($15/cuft - $95/cuft).  Hence, an optimization is necessary when choosing a  packing type
                                              *
in order to acheive a given level of removal with a certain system size.
      Estimates Sources
           o      Radian, 1983
           o      USEPAOERR contractor Feasibility Studies

      Expenditure Sources
           o      State and Federal Superf'unrt work
                                            -106-

-------
                                                       Aqueous & Solids Treatment
                                                       Carbon Treatment
F
I
          CARBON TREATMENT
4,5.1        Definition
Carton treatment systems generally filter contaminated  water through a carbon bed,
which selectively adsorbs organic compounds with physical and/or chemical action. When
the carbon in the filter reaches breakthrough,  that is, when the rate of desorbtion, equals
the rate of adsorbtion,  the carbon is replaced,  and the old  carbon  is disposed of,
destroyed, or regenerated with heat or solvents.   Carbon adsorbtion is often used in
combination with other treatment technologies such as filtration and flocculatLon.

4A2        Units of Measurement
Costs are given in dollars per million gallons per day, when available.  In some cases,
where no rate information was available, costs are given in dollars per gallon.

4Jx3        Sum mary Data

4.5.3.1      Expenditures
Costs for carbon treatment were found to range from:
            $ 0.10/gaUon
                  to
            $ 0.40/gaHon

These  costs included system  rental,  carbon,  transportation,  and set-up  labor  and
equipment.  The higher cost system includes a greater accounting of all of these related
costs, while the lower cost system was operated for a short period and did not include
carbon disposal or regenerations costs.
                                            -107-

-------
                                                   Aqueous ft Solids Treatment
                                                   Carbon Treatment
     4.5.3.2     Estimates
     The cost estimates range from:

     Capital:                 $643,000/Mgd      (complete construction cost)
                                   to
                             $14,132/ M gd   (set-up of leased system)
j

     Operation and
1    Maintenance:            $ll,786/Mgd/year
*
 I!                           $1.5 million/Mgd/year
 i
_,   The  wide range of cost estimates reflects variety of included costs.  The lowest cost
li   system does not include complete material purchase cost, but rather the rental cost and
     setKip of the  system.  The  highest estimated cost includes complete  material and
i    construction costs.
I
i
4*5.4       Factors Found to Affect Costs

                                              •
4.5.4.1     Expenditures
The following factors affected the expenditures for carbon -filtration:

     o     Inclusion of pretreatment costs
     o     Rental/purchase expenditure

For both expenditures given in Table 31, pretreatment costs are included in the cost
given for the carbon treatment system. Although these costs for pretreatment mayhave
been necessary for efficient carbon use, and may comprises a minoritv of the component
costs, it is important to note that they were included. The  higher cost system included a
                                                                            •
settling pool  for clarifiying out  suspended  solid, and  an  air  stripping system  for
preliminary  removal of methylene chloride before running uhrougn the lour cascade
carbon  towers.   The lower cost svstem  included  only pea-gravel and lime  for
precipitating and filtering out solids.
                                            -108-

-------
1
 [
J u

  03
  <



f


a
^
a
a
u




c c
o o
^H C
±j a
«t
u c
OR
OS

^
^4
u
a
a
«g
u












e
60
•H
00
01
o

V
u
s
o
en
2
a
Q



iH
C
o
fH
Q
00
*•»
-a-
d
i
o
•
o








I
•a oo
60
* S
tr» ^H
C^«! |
d «Q






e oo h<
O C 4) C)
*H ^H ^3 «J
•^ ^IL 13 *• *
03 0. W 
a ui s hi
f-l «H O «8
U <0  01 03 rH
03 hi
hi D. W O
00 CU O
iOI hi ST
e J=
W, 4-i JJ CM
0.1-1
•




•H
ea i-
< ee s
0, <-i o

M f» CO
c/j «J a> -H
3 U fH 2


















•'























1





















































*









                                                                                                           n
                                                                                                           o
                                                                                                           u

                                                                                                           •c
                                                                                                           0)
                                                                                                           AJ
                                                                                                           n
                                                                                                           •a
                                                                                                           o
                                                                                                           ai
                                                        -109-

-------
                                                      Aqueous & Solids Treatment
                                                      Carbon Treatment
I
1
1
I
Both  expenditures  given are  for leased  systems.    The  costs  generally  included
transporting the filter units, set-up, and operating labor.  Also, regeneration costs for the
lower expenditure (Missouri) did not include carbon regeneration.

4.5.4.2      Estimates
The following factors affected the cost estimates.
     o      Size
     o      Inclusion of related costs
                 rental/construction
                 carbon regeneration
                 additional prefiltering or treatment

In absolute  terms, the total system cost estimates varied directly with size (see Table
32). In relative terms, the cost per million gallons per day treated  was relatively more
constant, though it  varied over one order of magnitude for capital,  and three orders of
magnitude  for  operation and maintenance (O&M).  No  economies of scale effect was
apparent since, even from the same  data source, cost per million gallons per day  of
larger systems  was sometimes higher than for smaller systems.

The cost of renting  a system  appeared to be less costly than most construction scenarios
in two instances.  For the feasibility studies at the Illinois and Minnesota sites, quotes for
leased systems were obtained from  vendors.  These costs included set-up and operation
labor, materials and equipment. It is unclear if regeneration costs were included in most
examples.   For rented  systems, it is presumably included in rental costs if  a carbon
change was not necessary during the lease period, such as in the Minnesota scenario.

Costs for additional prefiltering and treatment, aside from carbon, were included only in
two cost estimates.  In the second highest cost system estimate,  for the New Jersey
ieasbUity  study, the costs  of sulfur dioxirie  gas treatment to precipitate  out iron,
airstripping to  remove volatile organics, and neutralization to stabilize the pH were
                                            -110-

-------
If
     CM
     CO

•

fH
«0
•H
a
tfl

-B e,
c
C to
O C
•H O1
« C
b -H
01 (B
O

X
-H
U
a
a.
a
u







e
60
•r4
tn
-*

g .2
E •• •"
•u B3 ffl
u °° 0)
U O C
eo o 33
4J o eo
2 <• H
3 as
•a- m
•O t3 13
60 60 60
O ON O
O CM 0
in •» o
m fH co

•Q* *a* fH

C C
0 O
•H tH
JH -j in 13
•H 00 -H 00
E Z E Z
m en

fH fH
 «V
*E ^
o. E
eo D.
eo
T3 CO 13 fH
eo cn eo o
Z • Z co
tH -a-
CM ^ f*. «-*


fH
en co
»-" eo
J BO
a eo o o
a c -H o
•H ^ »
0) o. a rH
6u C. N
•H -H b
b b rH 01
O 4J eg a.
^4 CO fVrf
CM b 9 fH
O *H 0)
cn co B »H
cn
•
b.
^f
X
•o
3
4J

Bu
&3 l^s
c ;-• x
*• 5 -H 41
Z fH CO
a. -H t-3
(jj oo ^n
Z <0 CO »
cn Q oi ON at
3 CJ Cb fH 2
i i
fH
13 13
60 60
£ £,
ON CM
CM in
-3- 00
vO VO
•a* f^
en «a*
v* 
•a
•a eo
-v. o"
\o »-«. o
CO CM O
• CM
fH CM
fH CM
 ON tH
3 O ^ -H '~i

b
to

^
o

-H
v£3 -^O
^N r^
fH ON
Z Z
U *H
cn E
cn cj •**
3 tn

                                                                                                                                                   tu
                                                                                                                                                  •o
                                                                                                                                                   u  ca  tn
                                                                                                                                                   Cbb
                                                                                                                                                  •H  CO  tO
                                                                                                                                                       01  U
                                                                                                                                                   0!  X  X

                                                                                                                                                   tn in m

                                                                                                                                                   8 -  b
                                                                                                                                                       to  u
                                                                                                                                                  <  u- <

                                                                                                                                                  m  «a* m
 tu
 b


 I
u
 «
 X
cn
                                                                                                                                                          tu
                                                                                                                                                          tn
                                                                                                                                                   O  01
                                                                                                                                                      V  b

                                                                                                                                                       •  C.
                                                                                                                                                  f-l  AJ  O
                                                                                                                                                   TO  T-! Z
                                                                                                                                                   p      ra

                                                                                                                                                   o  oT
                                                                                                                                                  •O fH •«
                                                                                                                                                  *  o  c
                                                                                                                                                   o  b  re
                                                                                                                                                   01 JJ
                                                                                                                                                   b  e  c
                                                                                                                                                  .0  O  O
                                                                                                                                                      U £.
                                                                                                                                                  T)      b
                                                                                                                                                   C   •  15
                                                                                                                                                   n 60  u

                                                                                                                                                   C. -H   »
                                                                                                                                                  -J  C. -,

                                                                                                                                                  U3  • CB

                                                                                                                                                  to  e  b
                                                                                                                                                  D  0)  O
                                                                                                                                                 •O  E  C.
                                                                           -111-

-------
1,

L
   •o
    9)
    O
    U
 I


iH
a
o
a
U
•a «
u
ec
o 0
•H C
AJ 0)
OJJ
hi e
0)1-1
O.0
or

>s
4J
•H
U
0
a
o
u









60

03
91
a




w
u
;S
O
cn

0
4J
0
o
V— '
•o
00
S
*^,
^«r
i-t
•o
to
3u
o
§
*
00
to-

1
TJ 00
X O
o
vo m
t-l «
• fH
CM ^
E J
S 4j
^i C
a *j o
>» o ja
m 0 n
JJ  -H
n u fc. --H r
•




















.











































































































.








                                                                                                                                                 en
                                                                                                                                                i—i
                                                                                                                                                 o
                                                                                                                                                 C  0)
                                                                                                                                                 O  Cfl
                                                                                                                                                 o  re

                                                                                                                                                  • "w
                                                                                                                                                 C  1-
                                                                                                                                                •^  ~
                                                                                                                                                 CL C.
                                                                                                                                                 C.
                                                                                                                                                11  J-J
                                                                                                                                                 C. O
 C   •
 0) "U
 E  C
 C. (3
 CJ  C
    (0
 hi
 o  c
i-> O
 a j=

 6  13
i-*  U
1— (
 10   •
    c
vw  O
 O T,
    ±j
 c  ra
 3  •*•>
 o  u
•o  o
^  c.
 a  en
 0)  C
 i-  a
                                                                                                                                                •o

                                                                                                                                                 ea  c'
                                                                                                                                                 03  •
                                                                                                                                                 0) >>
                                                                                                                                                •O *J
                                                                                                                                                 U  -H
                                                                                                                                                 C  JJ
                                                                            -112-

-------
                                                       Aqueous fc Solids Treatment
                                                       Carbon treatment
    included.   In the  SCS H estimate the costs of neutralization and clarification were
    included.   The  costs of chemicals and power comprised 90% of the O&M costs for this
    system.

    Expenditure Sources
         o     EU/JRB Case Studies, 1983

    Estimated Sources
         o     Radian, 1983
         o     US EPA OERR contractor FeasilalLtv Studies
i'
I
i,
                                          -113-

-------
                                                              Aqueous and SolWs Treatment
                                                                Oil/ W ater separator
      4.6 OIL/WATER SEPARATOR
I
t
¥'
4.6.1        Definition
An oil/water separation skims oil off of water by taking advantage of the im misdhilLtv
of these liquids.  The two  general types of odl/water  separators  are (1) a floating
skimmer-type, and (2) a tank-type coalescing plate separator.  Costs are given in this
section for the second type.   The latter type, which is typically larger, uses a series of
horizontal  and  vertical hydrophilic and  hydropholic plates to  enhance oil globule
flotation. These systems may be used in series with each other and with other treatment
technologies, which may provide "polisking" to remove residual low level contaminants.

4.6L2        Units of Measurement
Costs  are given in dollars per  million  gallons per day when data availability make it
possible.
      4L6L3
            Sum mary Data
      4.6.3.1     Expenditure
      The one expenditure available was:
      Capital-
                  $289,200
(includes hookup and controls)
      Operation and
      Maintenance:"
                  $50,000/year
                  S2.70-4.16/gaBon
(capacity unknown)
(1,000-1,500 gallons/month)
                                             -114-

-------
                                                           Aqueous and Solids Treatment
                                                           Oil/water spjekrator
1
li
The cost per gallon is relatively high because of the low treatment rate.  The oil/water
mixture is collected into a sump from tight soil with a subsurface drain system.

4.6.3.2      Estimates
The single estimate available was:

Capital:             $91,587          5,000 gpm capacity
                    $12,720/Mgd     (7.2 Mgd)

Operation and
Maintenance:        $267,456/lst year
                    ($0.0001/gaHon)

The assumptions for this system suggest that it is intended as an add-on to a larger
treatment system.  Appurtenances and control cost are not included as they are for the
above expenditure.  This causes an underestimate for the capital cost because of the
excluded costs and a low estimate for the 0& M because the maximum capacity flow rate
was assumed for deriving the unit cost.
       4L6L4.      Factors Found to Affect Costs
"!
L
       4.6.4.1     Expenditures
f      The following factors affected estimates:
            o     Flow rate (utilization of capacity)
            o     Inclusion of related costs:
1
                     appurtenances
                     controls
                     tank housing
                                             -115-

-------
                                                            Aqueous and Solids treatment
                                                            Oil/water separation
     Flow rate was probably the  most important factor affecting the expenditure (see Table
     34%  The combination of a locally tight soil with a high organic content, and the natural
     adhesion of oil to such high  organic soil resulted in a very low flow rate of only 1,000-
     1,500 gallons per month for the California case study site.  The effect on operation and
     maintenance unit costs by flow rate is even more clear.  The relatively low flow rate
I    divided into the annual operation and maintenance costs results in a relatively high unit
     O&M cost.
!
I
E
The expenditure data included a variety of related costs that may not be accounted for in
estimates or other expenditures.  These related costs are shown in Table 33.  They
include appurtenance upgrading to connect the lines for the treated effluent to the local
POTW, a building to enclose the storage tanks, and a control system for operating the
separator.  These related fixed costs may be spread among other system components for
a larger system in  which the ofl/water separator is a minor component, such as in a large
POT W or complex industrial waste (pre)treatment operation.
                         •
                TABLE 33. OH/Water Separator Capital Expenditures
                                              *
     o      Treatment system                                  849,200
     o      Plumbing modifications on
            existing tank farm to receive
                 material before treatment to test
*'                for treatment need                                 $ 8,000
.         o     Tank farm building                                 $50,000
          o     Sanitary sewer system modifications
                 to discharge treated effluent to
                 POTW                                             333,000
]         o     Electrical and instrumental oil
                 recovery system                                    8117,000
          o     Monitoring equipment for POTW discharge            812,000
          o     Project management for POTW dishcarge
                 mortifications                                      $ 20,000^
                                          Total                    $289,200
                                           -116-

-------
     u
I;






@

(^K
^^J
V
•Hq
kMri
Q
Z
K
55 '
»

tt
I1
^ i
•< s
3 £
C^
_^
C£
CsQ


^^1
^^C
»^^
M^^
L^^
^^^
^^

•









l-H
to
u
•H
a
a





vfl 01
U
c e
O (3
Operatii
Mainten

AJ
c
to
c
Contaml


><
AJ
^t
u
to
a
a
u

»
e
ec

n
a
O


01
u
9
O
in
2
«B
O

o
0
CM
00
CM

*~*
e
b O
«8 «H
01 «-l
>> to
*». ec
O 1 ^
O O vO
O f- <-•
cTcM «»
m •«*•<«•

o e
U -H
•4- a
«»H U -0
•H «H 01
•H O 4J f
o a u
*«. u 3 c a
03 OJ 6
CJ O C W 3
t. t-( ^ U-l 03

n
a) e o j=
1 1 ** _g^ ^1
*• ^ ^^ *•
a o IH e
iH C <0 O
a ^«E
ec 90
c «- "^
•H 0 X -
y — i u —»
CD tO 11 »
Ol 1- 0 O
iH to 10 O
to a. e. o
O OJ 18 -
U 03 U 
-------
li
I
                                                          Aqueous and Solids Treatment
                                                          Oil/water separation

4.6.4.2     Estimates
The following factors affected the estimate (Table 35):

     o     System capacity
     o     Inclusion of related costs

The unit cost estimate includes only basic material costs and assumes a capacity flow
rate and, therefore,  was probably an underestimate of an actual installed systems cost.
To the extent that this capacity flow rate Js an unrealistic assumption, this unit cost is
an underestimate.

Since this hypothetical system  appears to be intended as an add-on to a large POT W or an
industrial (pre)treatment system certain related fixed costs may be excluded or spread
among the larger system.

Since the bulk of the flow through an oil/water separator is  water rather than oily
contaminant, the flow rate variations may overestimate the actual contaminant removal
range. Therefore, cost estimates may be made more accurate by calculating the cost per
volume of contaminant removed.  As with other.treatment technologies, however, this
contaminant  removal  cost is very difficult to measure because  of the variations in
conta minants and re m oval levels. The re m oval effectiveness of an oil/w ater separator is
affected primarily by  ofl. drop  size;  retention time, density differences between the
aqueous and the organic phases, and the temperature.
      Expenditure Sources
           o     EU/JRB Case Studies, 1983
 !
      Estimate Source
                 US EPA, SCS, 1981
                                            -118-

-------
E
I

t     <
oa     M
       en
       O   7
o
o

CM
00











1-1
a

•H
a
a
w
u
ce
on

4JCU
aw
v-c
CLC3
OZ
e

c
"e
a
c
o
cj
X
4J
•H
u
a
o.
•0
u

*
e
00
^4
to
0)
o
V
u
Id
a
o
CO

3
JJ
«
a


eo eo o)
X o c
-». u o
O ^H
CM  > O
>-* a o
c- a; 1-1
eo ^H >>.
in D.OO
* S ON
iH -H •
ON B -4
V> "**<*•
1

t* VO iH C
a moo
CU -3 O r*
>\ • O fl
r*. . a
jj \O O 00
m CM «>•
i-i •«>•>-'
e
V

00

o
z

0) O*
4J 00
a
•H 0
a o
o
33
C W »r> s-*
«H O -0

ma as
.
CO 00 ON
CO CJ ON ^
S CO i-l ^


































•




























































































































"




























%
                                               -119-

-------
                                                               Gas Migration Control
                                                               Pipe Vents
                               5.0 GAS MIGRATION CONTROL
      5.1 PIPE VENTS

]     5.1.1       Definition
      Pipe vents are vertical or lateral perforated pipe installed in the landfill for controlling
,     gases.  They are usually installed at a landfill perimeter on 30 to 60 foot centers and
1     extend down  to the water table or the landfill base, sometimes in combination with
      trench vents for the control of lateral gas migration. Pipe vents are usually surrounded
I     by a layer of coarse gravel to prevent clogging bv solids or water.  They may discharge
      passively to the atmosphere or be connected to a negative pressure collection system for
      possible treatment.
f:
f
      5.1.2       Unit of Measurement
      Unit cost is given in dollars per pipe vent, Other units 'such as depth and diameter are
      used to describe each pipe vent.

      5.1.3       Sum mary Data

      5.1.3.1     Expenditures
      No actual expenditure data are available at this time.

      5.1.3.2     Estimates
      The estimates ranged from:
                 S445 LS     .(6 feet deep)
                    to
                 $1,310 LS    (30 feet deep)

      No information was avail able about the assumptions for the lowest estimate.  But the
      highest (capital) estimate included additional items such as PVC casing and a blower fan,
      which was not included in the lower estimate.
                                            -120-

-------
                                                                          Gas Migration Control
                                                                          Pipe Vents

      5.1.4 Factors Found to Affect Costs

      5.1.4.1      Expenditure
      No actual expenditure data are available at this time.

      5.1.4.2      Estimates
      The following factors affected the cost estimates for pipe vents:
          o      Depth
          o      Pipe diameter
          o      Casing
          o      Ventilation fan size
      The factors affecting cost estimates are very similar to those affecting well points, deep
      weHs and monitoring well costs, since construction elements are similar.  Well costs are
      typically proportional to their depth, for both well point type installation and drilled
      wells.   Costs also increase with pipe diameter because of affects on both material, and
      installation labor and equipment.  Some estimates for some cost components were given
      in terms of dollars/inch diameter/foot depth, indicating that diameter (in inches) and
      depth (in feet) affect cost at the same function.

      Casing  (pvc) was included in the  JRB  and Radian cost  estimates, but not the  more
      shallow  New Jersey  Feasibility  Study estimates (see  Table 36).   This element added
»•     S4.5Q- - 6.50 /LF for 4 - and 6 - inch casings, respectively.
i
      The Jan affects both capital and  operation and maintenance costs.  The fan size, and its
      capital cost estimate was identical for the two sites that included it. The reason for the
      differing operation  and  maintenance cost from these sources is unclear.

         .mates Sources
u
           O     JRB-RAM.1980
           o     Radian, 1983
           o     US SPA OERR contractor Feasibility Studies
           o     US EPA OERR contractor bids
                                            -121-

-------
  vO

la
  n


^

f
i,


v
H   •

O   1
      eo
£   £
ti
.u
to
o
u
9
0
JJ
a
a
u
u
E e
O (0
•H e
10 JJ
H C
01 -^
Q. CO
oz


E
O
•H
^
a

•H
^
C






^
V

V
E
a
•H
a








JS

a
CU
O

y
3
0
tn
(0
(0
o




u
a
0)
o
S





1*
co
>s
oo
*"^


w
a
•H CO
C. E O)
^^ ^4 £>
c u u
a> e
«W \O iH
cn o
a> l «-
o §
cn g


z
2
fe ' 0
pa oo
en oc o«
3 -1 -H



U
a
cu
tc
ON




CO

in
00
 -H O
M CM
o> .-1 m s
C 1
O ^5 PQj
to
cu
^^
u ••
B 60
•H e- ca
•H 01
cn .co ji
CO CJ
•• u e
CU -H
a u
•H > *f
a a

u a
C a
•H CJ

E
4J O
CU 0
CU hi
(M «C
n
O 3
cn E




63 _S cn
5 ^
«° « «*
i



OSS
CO
000
CN O O
in m in
<«• 
0 -H
B 60






cu
c
o


X





e
V
^
•p>4
60

4J
O




B
0)

•H
60

^
O
z
4J
a "a>
w -j
s ^H "55
Z -H 0.
< S CO
tn x -1 2 «
= y 35 2




o


^2
£ U
U CO
B
. -H •
u
sr >
a

H
^

3
O

^ ^H
01 V
cu
^•1 O
o
vO C7N
-

•H 01
i-t eo
< B 01
M =F5" s
3 w »ee *"* z
                                                                                                 u
                                                                                                 e
                                                                                                 o
                                                                                                 eo
                                                                                                 C
                                                                                                 e
                                                                                                 o
                                                                                                 u
O
i-(


+

• «•
6C
E
-H
C.

c.

u
c

>
b.


o
o
00

cn
0)
ts
                                              -122-

-------
                                                                  Gas Migration Control
                                                                  Trench vents
I
•ff
           TRENCH VENTS

       «x2.i       Definition
       Trench vents are deep, narrow trenches backfilled with gravel, forming a path of least
       resistance through which gases  migrate  upward to the atmosphere or to a collection
       manifold.  They are typically constructed around the perimeter of a waste area, or across
       a section of the site to form a barrier against lateral migration of methane (flam mable)
       or toxic vapors.  Trenches can be open,  or capped  with clay and fitted with collection
       laterals and riser pipes, venting to the atmosphere or connecting to a negative pressure
       fan or blower.

       5.?-2       Unit of Measurement
       Unit cost is given in terms of dollars per linear foot because it reflects the functional
       value of mitigating gas  migration across an area.

       15.23       Sum mary Data
 .,

f|      5.2.3.1     Expenditures
       No actual expenditure data are available at this time.

*      5.2.3.2     Estimates
*      The cost estimates for trench vents ranged from:

                         S35/LF  (20 feet deep)
                           to
                         3646/LF (20 ~eet deep)
                                             -123-

-------
•4
I
                                                                      Gas Migration Control
                                                                      Trench vents
The highest cost estimate included significant costs for sheet piling, geotextile trench
lining and well point dewatering of the excavated trench, none of which were included in
any of the other three estimates.  The lowest estimate was a simple passive trench vent
with no piping or fan ventilation.

SL2.4        Factors to Affect Costs

5.2.4.1      Expenditures
No expenditure data are available at this time.

5.2.4.2      Estimates
The following factors were found to affect the trench vent cost estimates:
     o      Trench size
     o      Ripe vent size
     o      Ventilation for size
     o      Inclusion of related costs:
              sheet piling
              geotextile lining
              overhead allowances
              contingency allowances
              well point dewatering

Trench depth seemed to have the most significant effect on costs (see Table 37). The 20-
foot deep scenario used for the  JRB-R A M estimate required sheet piling, which, despite
reuse assumptions, comprised 81% of the total capital cost. Also, wellpoint dewatering
(14% of total capital cost) was considered necessary for this deep trench vent.

Pipe vents  which  were added to the trench vent designs estimates.  Varied among the
estimates given.  The pipe vents for the highest and lowest estimates were not specified,
and not included, respectively.   However, length of the laterals and risers for the two
SCS "Landfill" estimates was congruent; onlv the pipe diameter varied. This did not
appear significantly affect costs.
                                            -124-

-------
I
        CO
f I
      GO
 li
u
a
u
09
O
U
u
^j
G
S
«H
eg
^J
_J
a
eg
cj
»dH (U
hO w
U
cc
O 03
w "**
•ne
4JO>
fM 11
*¥*•
MC
OHH
CiC3
or
e
a
Ud
C
o
•H
4J
eg
iH
•H
1 1
*•
e
01



09
4J
C
a
>

IV
a.

id
eg
w
>,
I >>»
i^
in r^
^H r«
O
» cn
f>- i-H
 w
•H *J r
u e <-<
a* • ' ^ — i
•**. -* * ^™"
ON tO U >H
U 1 Ud
en •« O
cn u e oo
3 to eg ON
|J «H




fc

r»
00
I

O
•8-

Id
eg
01
j>->
1 S
r» eo
ON «
eo *H
v> .««•





0)
c
o



n
0) 00 JC
j: vo o
u o e
i-i e * *H
m -H cn
ON 1 CM
NO CO r*
1 <^
n X eg x
Id >-
0) M 01 *J
09 01 *J 0)
•H oi eg oi
Id Ud |H Ud
(^
I-I
/— \
jj -o *~»
4) N^ S
£ ^
Ud  c •*
a «j IH


id
eg
01
1 >N
^,
0 cn
en oo
«-l CM
 





OI
e
o
c










01
c
o


*"V
— *
•w
x"^ ^^
*J -0 5
4) s>^ N— '
01
U_l 4_l J_|
OI 01
00 X 01 X 01
SO Ud Ud
. O «ff
tn CM

u
c •
01
Id
4J

•H S
OI «-l
> — '
a <<-i
< b Ud
a, aoij -o
w i e c o
cn oi eg co
w o > ,j ON
s cn : 1-1
%
                                                                                                                                c
                                                                                                                                o
                                                                                                                   u
                                                                                                                   a
                                                                                                                                en
                                                                                                                                c
                                                                                                                                o
                                                                                                                                u
                                                                                                                                   00
                                                                                                                                60 C
                                                                                                                                C -H
                                                                                                                                •H C
                                                                                                                                   41
J=  X
 cn  v
    u
 co  o
 01  OJ
•o  so
 a
«-• -s
 u  c
 C  TO
                                                                 -125-

-------
i
I
                                                                  Gas Migration Control
                                                                  Trench vents
For the  one estimate for which a ventilation  fan was included,  the operation and
maintenance costs were significantly higher by  an  order of magnitude than the other
estimates for  which these costs were estimated, presumanly to cover electricity and
maintenance costs.

Geotextile trench lining (12% of total capital costs) was included only in the JRB-RA M
estimate, which assumed $2.38/sq ft for hypalon.

The SCS estimates included allowances for overhead and contingencies as follows:

     Estimate Scenario               Overhead           Contingency
     A ctive control                     25 %                   30 %
     Passive control                    25%                   20%.
     Gravel trench                      .25%
      Estimates Sources
          O     JRB-RAM.1980
          o     SCS, 1980
                                           -126-

-------
                                                                         Gas Migration Controls
                                                                         Gas Barriers
1
      &3  GAS BARRIERS
      &3.1       DeflnltiDQ
      Typically, a synthetic membrane is used in combination with other technologies to form a
      barrier against horizontal or vertical gas migration.  Clay or concrete slurry walls and
      grout curtains  may also perform  a similar function, but at a  higher  cost; these
      technologies are usually reserved for ground water barriers.  Synthetic membranes may
      be installed during construction of a trench vent or a subsurface drain,  which both
      involve digging a trench.  The cost of the trench and other tasks may be derived from the
      section on that conjunctive technology. Similar barriers to vertical migration  may be
      taken from  the surface sealing  section.   For material costing purposes,  synthetic
      membranes may  need to be doubled to prevent punctures from gravel and stones. Also,
      an additional several feet should be allowed for the  membrane at the top of the trench to
      allow for proper anchoring.  Trench bottoms should also be lined.

      5A2       Unit of Measurement                                          	
      Costs are given in terms  of  dollars per square  foot because it best  expresses the
      functional value of gas barriers.
ill
      &3U3       Sum raary Data
*!'
li:
     . 5.3.3.1     Expenditures
^     No expenditure data are available at this time.


i    '
                                           -127-

-------
                                                                           Gas Migration Control
                                                                           Gas Barriers
      5.3.3.2      Estimates
      The cost estimates ranged from:

           Capital      $0.39/sq.ft.                 asphaltic concrete
                           to
                        $3.00/sq.f.t                 hypalon (36 mil)
      Operation and
      Maintenance      S900/year                 (24 four hour inspections/year)
i;     The information source does not explicitly state whether installation as well as material
      costs are included in these estimates.
E
      &3.4       Factors Found to Affect Costs

      5.3.4.1      Expenditure                                   ~
      No expenditure data are available at this time.

,r,     5.3.4^      Estimates
111     The following factor primarily affected gas barrier cost estimates:
a1
jjj           o      Installation
            o      Material type
i           o      Material a mount

|     The inclusion of installation costs is  the most important factor affecting these cost
      estimates.  Although the estimates references drew data from  the same sources. Table
      38 shows  that  there are significant differences that may  have been caused  by the
      inclusion/exclusion of installation costs.
                                             -128-

-------
                                                                        Gas Migration Control
                                                                        Gas Barriers
      The material types and amount affected cost estimates,  but inadequate data  was
      available to quantify these effects.
      Estimates Sources
          O     JRB-RAM,1980
          o     Radian, 1983
n
(i
                                           -129-

-------
i   i
r   ^
 u
 ._}

 i
    i.
    U 5
    ^ fH
    




4J 4J
VM «u
cr «w o-
eo a
*»» tr «*.
O 01 CM
2 a s
CM CM fH
*
JJ
vw . •
^^* * ^J ^^* ^J

^^ 09 • f^ •
• o* • ^T
O 01 CM 03
| ^^ |
rt CM l*»
r« vo r^
* • •
O  -v>

CO
^4
01
CD 0) ,
o eg
^D C3 V
f^ i*H ^C
*• ^Q
'33 C
W ^H
0) ^
C U
•rt eg
•H ^

U 01
«H e -<
-• O ,3—1
01 ft O 4J
X eg tH x
^ Q. VW 0)
C >, 0) *J
x s: Ho
tn 01
u
o

• U<4
O
•H 0-
O
m
£

4
••^ 4J
ON "t
• tr
i^K CO
|
4«O
**
«
«n
.


fm •
»
U
V
fl i
»-< 3)
V
*5 *
> o y ju
X "PI 4)
a fH o vo
•H -H u j:
tJ IM «J >, U
Ul J^ 1- 1- C
^* CJ JD Ol fl)
« eo -H > >-
X JO > 01 *J




^








x
eg
^

                                                o

                                                c
                                                9
                                                •v-l
                                                •o
                                                a
                                                n
                                                05

                                                V
                                                05
                                                O
                                                U
                                                U
                                                C
                                                n

                                                o
                                                 s


                                                 •a
                                                 c
                                                 Q


                                                 O
                                                 OJ
                                                 a
                                                 o
                        -130-

-------
                                                                     Gas Migration Control
                                                                     Carbon Adsorption
 1
 r
w
 I,
 e
       5.4 CARBON ADSORPTION (GAS)
5,4.1       Definition
Carbon filters are added to vents to collect gaseous contaminants (typically volatile
organics) from the vent gases.  Large gas filtration systems (10,000 and 100,000 cf m -
roughlv 1,000 cu.ft. of carbon) used in manufacturing processes are available, but this
section includes information on relatively small svstems (7 cu. ft. of carbon) for passive
venting systems.

5.4.2       Units of Measurement
Costs are given in terms of dollars per filter.  Units such as carbon filter volume of air
filtered or amount of contaminant collected are important for describing a given filter
unit, when available.

5.43       Sum tnary Data       	

5.4.3.1      Expenditures
One expenditure for carbon gas filtration was available:

            $188/Slter
                                  •
This cost does not include the cost of the used 55 - gallon drums that were retrofitted, or
the labor cost of filling these drums with carbon.  Only the material cost for the granular
activated  carbon is included. Each of four improvised filters was saddled over the vents
to the 5,400 gallon activation and settling tanks used to biodegrade butanol and acetone
from contaminated ground water. "isLng a -vooden pallet.
                                                                   ,          *
Operation and maintenance costs include carbon testing and regeneration/replacement
COSTS.
                                             -131-

-------
                                                                           Gas Migration Contronl
                                                                           Carbon Adsorption

     5.4.3.2      Estimates
     One estimate was available from price quote sheets (this may be considered similar to
     expenditures except that no record of an expenditure is available).

                 S635/vent sorb (for orders of 1-3)

 *    This cost is for a com mercial carbon filter, which is very similar to the improvised filter
     for which costs are given above.  Related costs of construction (drum  cutting, filling.
-I    painting) are included in the delivered cost.

 •    &4.4       Factors Found to Affect Costs
I
I
The following factors affected the cost of the carbon vent adsorber (see Tables 39 and
40):

     o      Size
     o      Related costs_
     o      Flow rate
                                               •
The size of the filters affected only the cost of the activated carbon filler, since the
drums used were reconditioned  waste barrels. The containment structure  would affect
costs at a relatively smaH Incremental proportion of the cost, since the  carbon costs
(roughly $1.00/lb) is a more significant cost factor.

 As noted above,  and in the comments section,  the expenditure includes only material
costs for the carbon.  The vent filters were  mounted on  the cylindrical-tanks using
wooden pallets, and in-house labor was used to. retrofit and fiH the drum  canisters.
 Hence,  the cost of tftese relatad components would be expected to increase the cost of a
factory-built carbon filter, as noted below.
                                            -132-

-------
i


I
        H
        S
        z
        H   «
        £_   
C eg



^H 01
O C
e o
eg ij
4J 4)
3 U
jo eg


<— i
E
S
•v

e
ce

S

-
*>^
GO Ol
ec m
•-3 w
— 1 "3

M »oo
tt -J OlOv
a u z--i

























•








•


















*
























































—


















                                                                                                                    X

                                                                                                                    c
                                                                                                                    CR
                                                                                                                    O
                                                                                                                    u

                                                                                                                    c
                                                                                                                    o

                                                                                                                   ~

                                                                                                                    CJ

                                                                                                                    35
                                                                                                                    U
                                                                                                                    C
                                                          -133-

-------
O
••3-
o
o

CM
00
      g  ,
      r™  •-*
      5  "


CO
o
u
f-4
«3

O
H
•a v
u
e c
O «3
•H C
AJ U
CQ U
j- e

&«C3
os
c
(3
C
*E
n
c
o

4)
N
sn
t .
M
01
4J
oH
U.


0)
u
^4
a
o
en
-2
^
(3
O

J=
U
(3
V
r-!
vO
•M-

C*^^
u u e «
> -H «D (8
00 1H U
03 E C
tl oi CO 01
O -H JJ U
e i- e c
(0 O O
> u u
e
0)
>
CO

o
c
E
}^
•o
—
o
l-H
n
60
in
in
0)
•o /-.
c ^
u eo
^ ^^
fH
u" *^






















- . 	 .

-
















-I J
CO iJ
a o
•a a
c o*














-












- 	 	







































10



















*








                                                  -134-

-------
li.
                                                                      Gas Migration Control
                                                                      Carbon Adsorption
      The flow rate affects costs in general, because of the specific costs of a fan and the
      higher rate of adsorbtion. The fan would not only add to the capital cost but would add
      to the operation and  maintenance costs in  two important ways.  First, the fan itself
      would require electricity and maintenance to keep running.  Secondk the higher rate of
      adsorbtion would increse the necessary frequency of replacement for the filter.   The
      paucity  and similarity of available data obviates contrast of factors between sources.
      However, the following brief listing of factors is appropriate.
                                                                  s
           o     Filter size
           o     Flow rate (use of ventilation fan)
           o     Contaminant concentration

      Of these, flow rate is probably the most important independent factor.
      Neither of the passive-type vent filters for which costs are given above included costs
      for a fan,  which would significantly increase operation and maintenance costs.  JRB
      Remedial Action Manual (Rogoshewski, et aL,  1980) included the relationship shown in
      Figure 1.  The hypothetical  system for  which these costs were estimated is a large
      carbon filtration unit, several  orders  of magnitude larger  than the vent-sorbs noted
      above.
      Expenditure Sources

           o     ELI/JRB Case Studies, 1983

      Estimates Sources

           o     US EPA OERR contractor bids
                                            -135-

-------
I
I
D
         100
          90
O
O

B.
O
80
70
w
g  60
H  SO
CO
o
u

o  40
tu
-a


?  30
to
       o
          20
          10
                  FIGURE 1. CAPITAL AND OPERATING COSTS


                 FOR NONREGENERATIVE CARBON GAS VENT  FILTER
                             Total
                             Installed
                       Annual
                       Operating
                                                                 000
                                                                 900 >
                                                       800
                                                       700
                                                           O
                                                           •c
                                                           m
                                                      '600 «
                                                           n
                                                           o
                                                           Cft
                                                                 500

                                                                     H

                                                                 400 5
                                                                 300
                                                                 200
                                                                 100
                                                           o
                                                           *n
                                                                     fa
                                                                     en
                                                      8
                    FLOW RATE  (X1000 CUBIC FEET  PER  MINUTE)

                OF VENT GAS CONTAINING  50 PPM TRICHLOROETHYLENE
      SOURCE: CALGON, 1980
                                    -136-

-------
                                                       Material Removal
                                                       Excavation/transportatlon/dlsposal
                             6.0 MATERIAL REMOVAL
&1 EXCAVATION/REMOVAL TRANSPORTATION AND DISPOSAL/TREATMENT
6L1.1       Definition
Excavation, transportation and  disposal costs are grouped here  because,  (1) similar
factors affect all three tasks, and (2) some actual expenditure data are available only in
terms of the three aggregated tasks,  Excavation refers to the work necessary to load the
hazardous  material,  ready for transport from its found position. (This may involve
significant digging and waste  classification, or onlv surface scraping.)  Transportation
involves hauling loaded materials off-site to a disposal/treatment facility.  Disposal
treatment may include land-filling, incineration or treatment.

6.1.2       Units of Measurement
Cost are given in dollars per cubic yard (cuyd) because it serves as a standard soU
excavation measure.  A' cubic yard is assumed to  weigh one ton, which is a common
assumption at landfills. In several cases disposal and transportation costs are given in
terms of dollars/ton because haulers and landfills used weight measures.

6.1.3       Sum raary Statistics

6.1.3.1     Expenditures
       The   'following   ranges    of   excavation/re movaX    transportation    and
disposal/treatment expenditures were found:

     Excavation/Removal:      $15 - $460/cuyd
     Transportation:           $29 - $145/cuyd
     Disposal Treatment:       $17 - S356/cuvd
                                      -137-

-------
t
I!
I
                                                      Material Removal
                                                      Excavation/Transportation/disposal
These cost elements cannot necessarily be sum med, since the extremes of the ranges are
derived from  different  sources  with different  scenarios and assumptions.   Hence,
sum raing the three unit operations from the highest and lowest cost sites, results in the
following site total

     Excavation, Transportation and Disposal:
                 $4.70 - $884/cuyd

For excavation/removal, the lowest cost site (Texas-S6.06/cuyd) required only pumping a
liquid into a tank truck, while the highest cost site reflected the use of boats and level A
protective gear to retrieve floating palls from a  canaL For transportation, the salient
reasons for the lowest cost site were unclear, but at the highest .cost site (Massachusetts
-3145/cuyd), a relatively high demurrage (compensation for delay) was charged because
of sample analysis delays.   The disposal/treatment cost varied greatly with the waste
compatibility.   The lowest disposal cost (New York City - $17/cuyd) was charged for oil
heavfly contaminated with highly volatile solvents, which facilitated incineration.  The
highest disposal cost (Florida - $356/cuyd) was for disposal of extremelv caustic "super
tropical  bleach" (calcium  oxide-chlorinated lime),  which   required  treatment  and
neutralization  prior to disposal.  Operation  and  maintenance costs may involve ground
water  monitoring and, possibly, site inspections or security  to  prevent  future illegal
dumping, which is often repeated at former sites. These costs  vers richer accounted for
separately, or were not encountered for the sites.

6.3.1.2      Estimates
       The following ranges of cost estimates for excavation/removal, traasportation,
and disposal/treatment were found:

            Excavation/removal:      $0.85- 4.09/cuvd
            Transportation:           $1.67 - 94.40/cuyd
            Disposal/treatment:       £ 12 - 283.20/cuyd
            Site Total               $222.87 -379.37/cuyd
                                           -138-

-------
                                                        Material Removal
                                                        Excavation /transportation /disposal
For excavation/removal, the lowest estimates (SCS "impoundment" - $0.85 - 1.27/cuyd) a
front-end loader was  assumed  to be  feasible,  while for the  highest  estimate (SCS
"landfill11 - $3.42-4.09/cuyd) assumed an excavator scenario for the  deeper excavation.
The low  transportation estimate was an extrapolation from a construction-engineering
manual, while the high estimate reflected actual biris from  different types of hauling
firms.  Disposal costs varied from $12/cu.yd.  at a sanitary landfill, to $283.20/cu.vd. for
contaminated sediment at an engineered landfill.

No operation  and   maintenance  costs were  assumed  for the excavation/removal,
transportation and disposal/treatment cost estimates.

6.1.4  Factors Found to Affect Costs .

6.1.4.1     Expenditures
The following technical factors  were found to affect the costs of excavation/removal,
transportation and disposal/treatment:

     Excavation or On-site Transfer
           1.    Excavation depth
           2.    Site surface characteristics
           3.    Health and Safety requirements
           4.     Material - liquid/son" ct/drums
           5.    Waste quantity

     Transportation:
           1.     Distance to disposal facility
           2.    Accessibility to road
           3.     Material-liquid vs. solid
           4.     Waste quantity
                                      -139-

-------
1
                                                       Material Removal
                                                       Excavation/transportation /disposal    ^

     Disposal:
           1.     PCB Waste
              (a)    Concentration-over/under 500 ppm
              (b)    Mateiial-solid vs. liquid

           2.     Non-PCB RCRA  Hazardous Waste
              (a)    Solid vs. liquid
              (b)    Aqueous vs. organic
                   i

In addition, the following primary non-technical factors affected costs:
     A.    Com munity relations
     B.    Interstate relations
     C.   . Inflation and regulatory factors.

The effect of excavation depth on the costs shown  In Tables 41 and 42 is probably non-
linear, since the most significant cost changes resulted from equipment differences.  For
example, the depth of  excavation  at the Case Study sites  in Idaho, New Jersey and         ^P
Massachussetts $1 necessitated  the use of a Caterpillar 235, which is a large, treaded
backhoe, with a 30 foot (10  m)  arm,  which rents for about $70/hour  without crew.  At
other sites where the excavation depth was shallower, a smaller, less expensive backhoe
such as a Case 580C was used.  At sites where only surface  scraping was performed, a
front loader,  which is generally even less expensive,  was used.

Excavation was performed  at a relatively quicker pace, which reduced labor and rental
costs,  at sites with sandy and unconsolidated  soil.  At the  New  York  City  #1 and
California  $2 Case Study Sites no  excavation costs were  incurred because removal
involved pumping  liquid  waste into trucks from tanks and  ponds, respectively.   Site
surface characteristics probably had a relatively small affect on the excavation costs at
most of the case study sites. At Case Study Massachussetts *1 the waste was excavated
from  a steep embankment.  Clean fill was removed from the top of the embankment to
prevent .ts cross-contaminaucn  -vita the Bastes that were 'ouried  at the toe of the slope
during the excavation. This process added slightly to the labor and rental charges.
                                            -140-

-------
                 ^-^

-       Z    -3
ea
                 CM
                 eo
         U
         X


fH
CO
O
H


l-H
I-H e
CB 01
CO E
O u
a a
ca 01
•H Wl
a H

— s
4)
U
. a
or u
e ca

w a
H ^
e
0
^4
^ rH
a a
a o
u E
X 0>
U OS
e
o
•H
4J
CO
(9 4J
U &
X 01
u o
a
^4
a
4J
6

.£
^H
e
a
3
j--
CO
' hi
at
1
u
(0 M
U 3
n o
O VJ
•o
^^ ^^
S~ 3
_r . •*
S 



(U
u
a
lu
bl
3
CO
4) tO
* a 91
3 35
4s
3s
0 o>
I*. -H
^ ^^ *rt
« 1C 2.

•o •
"3 "n .5
jj» 00 "^
^ in a.
a
u S^ u
S oo o
tn g 2 ^
2 O ^^ Cb
•0
^v
u
vO
r^
*N





^^»
•O CO
is 01
3 iH
•^ E
i-l O
^H *^
 »H





•o
X
3
u
00
in
^H
«>
•


• u
01
ai
Ifc4

in
1-1
CD U
0) M
•Q 01
HH
u -
•H b.
9} S3
g. £
•D
X
U
O

•*
X X
01 U
1-H 01
^J ^
O 01
ja a
ea
< te.
&. n «j-
M 00 l-H
CO pJ CT\ (Q
3 U iH O

C
o
m
CO
CM

c
0

^^
o





^^
§ M
•tl e
IO ^^
^r ^^
•H in

•o

M
u
in

•

4J
0)
V •
IM

^1
A
01
C ^J
o ^
11
"x w

CM C ^ C
in to
O •— I
• in
i— i 1-4

01
60
•H 3
0 ^
CO CO
PD
< K
0- -i
W -...-I CO
H4 00 CO
C/3 J ON tD
=s u -* s:
•o
X
3
U
o
CM










•a
3>'^
CJ *
^"E


53 o
tt) rrt
a

•o
u
•^
• iH
CO

Ol
00
•H *°
3 3
o r!
CO »
CO
< Bi
wC^ 2
M CO 15
C/3 «J ^ "Q
                                                                                                                                                   OJ

                                                                                                                                                   a
                                                                                                                                                   en
                                                                                                                                                   en
                                                                                                                                                   n
                                                                                                                                                   01 •
                                                                                                                                                  o
                                                                                                                                                  o
                                                                                                                                                   O  3
                                                                                                                                                  i-(  U
                                                                                                                                                   u
                                                                                                                                                   re vo
                                                                                                                                                   U r-
                                                                                                                                                      Pvl

                                                                                                                                                   o  •»
                                                                                                                                                  •O  fH
                                                                                                                                                   ?S ••
                                                                                                                                                   3  —I
                                                                                                                                                   U
                                                                                                                                                      n
                                                                                                                                                   — t-
                                                                                                                                                  •o  o
                                                                                                                                                   01  U
                                                                                                                                                   05  O  0)
                                                                                                                                                   o  re  u
                                                                                                                                                   C. I- -H
                                                                                                                                                   03  j-i  tn
                                                                                                                                                  •H  C  I
                                                                                                                                                  •o  o  c
                                                                                                                                                      U  O
                                                                                                                                                   3 .C  0)
                                                                                                                                                   U      U
                                                                                                                                                     •u  n
                                                                                                                                                  in  o>  >-i
                                                                                                                                                  «-H  0)  01
                                                                                                                                                  vo  s  ca
                                                                                                                                                   o  en
                                                                                                                                                   c .*
                                                                                                                                                       cr.
                                                                                                                                                   oj  a
                                                                                                                                                   en JJ

                                                                                                                                                  "5  u
                                                                                                                                                   01  U
                                                                                                                                                  f  O
                                                                                                                                                  JJ
                                                                                                                                                   0  Cfl
                                                                                                                                                      ai
                                                                                                                                                   CO  -O
                                                                                                                                                   tn  3

                                                                                                                                                  >-i  u
                                                                                                                                                  c  c
                                                                                                                                                  •a  AJ
                                                                                                                                                  w  to
                                                                                                                                                  *-  u
                                                                                                                                                  "3  re
                                                                                                                                                  C  u
                                                                                                                                                  CD  C
                                                                                                                                                  — H
                                                                    -141-

-------
f:
r   *

1!   ?

[

^^
*s
3
•H
^
e
o
u
^
Q
z
t:
• c-
X
ti
z
o




***
to
(-1

> 0
to E
u o
x ae
O
JJ
(3
a u
u c.
x u
[i] C

U
e
to
c
•H
(0
1
u

^^
4J
•rt
4J
n
3
o-

a
^4
^4
0)
4J
01
u
a u
^J 3
n o
3 V3




1


O
ON


01
•a u
>L ••*
3 n
£ !
01
.0
es
*J OJ
o >
z <
41
. U
tfl
Ifcrf
3
a




09
e
1
o

•o
^s
3
V

CO
^f



0)
e ^
3 ^*
b 0
•o «
00
< C£
SS si
"^ t*j z
•o
X
3
U
O ON
•H in
£rt
4J
NO


91
T3 . j
X C
O B
a s


^ *x
1 U
u
a
iw
3
0)


6
u
o
fH
U O
a c
w a
c —
01 C.
a

•=
s
u
^^
f<
^.
Psl




rH
^•4
o
ID
•H
so h
< a: 3
B, -5 0
Bu ^*» ON CO
i— i rv o)
CO J ON 

! 5
I 1

•o
3
U
in
u
0)
4fc4

d
*T*
fM




CQ
e tn
> "3
o 'u
CQ E

•a
a
u

e
P;
*
**


01

2 
r*.
^.j
^^


e -H
O E
^j
-»- 00
ON iH
00 00
0)
*2
C3
to
W >
0 <
01
a

i;
01




CO
01
I—I
«

•a
>s
3
u

ON
«N




«
^^
.
0
05
22;
W »^ CN
1-4 00 U
en -3 ON »-
3 UJ.-H 2
                                                                                                             c
                                                                                                             o
                                                                                                             u
                                                                                                             u
                                                                                                             c
                                                                                                             V)

                                                                                                             "5


                                                                                                             ^j
                                                                                                             o

                                                                                                             w
                                                                                                            •3
                                                                                                            C

                                                                                                            t!
                                                      -142-

-------
G


<^v
*o
V
3
«H
4J
O
u
%••
•H
«»

ta
co.
H




H
5
Z
.U
• &
S
z
c
*•!
H
<
>
<
ro
X
w





^^s
03
Id
03
rH
•— 1
O

o
H
i-H
tH O
IB e
a o>
o e
o. *->
05 a
•H 0)
o w
H

0)
y
• e
09 (8
C M
(0 09
U i-l
H C
«IM^
cavation
Removal
x ^*»
M
e
o
i*
' *j
(3
> .2
13 J->
y c.
X 0
a c
4J
c
e)
C
•V*
IB
u
^
0
U

>
ftj
•p*
4J
C
re
c

^^
a
1H
k<
«
JB

1 Data
1 Source

«M
VO
<-> <-N
* f^
O »—
»-*

i-i <•—.
T3 -H 0)
>>> «H f-4
9 uw y
0 *-N -0 >N
^«. c>j e y
00 >-' (B 01
 >-"


0)
1— 1
JD
13
(H
•H
13
4J >
O <
•o
>>
y
ON
CO
v>



01
y
(3
^4
b
09
09
U
09 09 >
U E •"•! *•».
e o m 09 «T
01 1-4 U OI-- *-*
> -^ " -= «
-i -» 3 -3 — J!
O JJ J3 (3 0 U
CD 09 g C.
•
•H -D
IB • X
60-0 3
X my
o 3 m
o y B
m •
> r^ jj
Pvl 
«<


U
«-H
^
a
•H
v4
O
•J >
0 <
•
1-t
13
ea
^ E .*
o 3 y
O 33
• u u
o a  ^


CU
y
i;
l*rf
tl
3
ca



V
c
V
^4
>»
• M

09
O C
0 0
0 -H
ft ^^
O« 13
ON 60


•C
iH
3
O1
^H
•-t
S
u
«M .., 09
S Sll
•o
r
u
in
o\
f— t
v>






•o
3 ~
„« S
crt ^H
2 £
m ^
50- E
O
*y
1-4
«^
•O
>»
U
CO
in
^j
^^
•CO-


u
cu
U
1*4
in
r**
m
0)
•o
•H
,
00 3
•H U
ft
PI





•H
i^
O
09
BO
< Ct
0- I-J IM
U •». tH ^
M CD <-l
W J ON CO
s ta ~* y
•o
^
y
1 -s.
•«• 1-t
«M r^
r-l r-t
V>
0
~ >s
«ff 3
f«- y
f-
C"i
«5-
u
0)
(U
U-l '

VO
Csl
I
1
m
VM


n
u
C 09
CU t-1
> 5 !
^i *j
O U
01 E


•^
•^ >s
O 3
i— i y
•
m



• • *
OB
1 2
P t*
* 0
•rs -n

to >,
< (Jg OJ
CU "•} CO
W -v. i-l I-
t- CD 3 CJ
t/5 _: ON 0) -5
=) U -1 2
                                                                                                                                                95
                                                                                                                                               _*
                                                                                                                                                x
                                                                                                                                                S3
                                                                                                                                                O

                                                                                                                                                co
                                                                                                                                               o
                                                                                                                                               y
                                                                                                                                               r-i  >
 c  u
 ~  n

 •u
     >,
     I—I
     I—I
     IB
     «-*.
•U   u
                                                                        -143-

-------
 [*s
i!
  o
  u
  •a-

  u
X  £
Pjy  CD


    Z'o
~  O
O  CN
    CO
I
      X

fH
a
Q
H
l-t U

> 0
a E
u at
x ee
e
o

^
Excava
Depth
jj
(0
e
a
f*
J


^^
4J
C
co
3
o*
k.
Ol

z

u
u
^ 3
35

•o
X
^». 3
^D U

«.



•o
X
u
^J-
\O — i
v> w
V
wd
E
£
«M

•a
x

u

in
^4





4J
U
o
tw
w
S e
•H 3
a -H
g §
X U
-i u

•o
^
U
o
o
rH


•P4
O
u
0
< ee
a. •-) .
H4 CO 0]
CO U ON v4

in -o
r» X
• 3
in u
PO
0-





•o
3
^ ^^
R S
• 2
S g
*"• m
.— i
*^









§
vw
0)
• «o e
o o
§• ?
3 t
OJ f^
a <-x
•o
•r* V*
U
•*« n
01 (3
a. *u
•o
X «O ^
3 0 «3
r*. u <_i eo
O X
•

^r •
^
JJ 01
01 ^
S S
63
< ee
a. -5 u
w -^ o -H
M CO t-l
W *J ON CO
3 U ~4 O

|
GO
CN







•o __
3 ^
y 0)
^^^ ^^
00 g
in










o
^4
^«
0)
•a c
tt) o
g- 0
'! I

a a* i <-s
C9 *^ PH ^^
13 •« ' 01
.n co »
•- C Q
u «** u
VD
• • O
•o ^
.ox -•
>n 3 x td
ON U CO
o" "°.
ON CO
1-1 • n
_
1
O Lj
" u

55
ea
< ee
a. _i u-
.U ^ O -H
l-i 00 iH
CO kJ ON CD
3 U -H CJ
•o
•^ x
r- s
9
•&





' £
3 -^
U

r^ ^
t^» *^
«*^

-------
I'i    _
li    ?
      3
      e
      o
      u
     tri


     tQ

fft
te
c
H

ce
03
0
a
w
^H
a

at
u
• c
w to
C ^
to 0)
1* -H
H a
0
•H iH
^ to
to >
> 0
CO E
U (U
X eg
ex] -».
e
o
_J

a
> X
63 ^
u a
X V
u o
u
c
to
e
"B
to
c
0
u

>
•H

c
co
3
0
a
"2
0)
eg
u
a i-
JJ 3
(0 O
Q W5

O
o
0 *-•
IsT d
£
a *a IH
60 ^s ^^
«** 3 lu
OUT:
•ff *•«. B
• o to
o eo fH

V
** "0
•H ffl
E 0
*«. »H
vO •)£
«r> y
• 3
(N ki
«/> 4J
tH
to -o
60 X
3
**^ tV £
0 *-. 3 Jt
T*~ «H 3O
• «3- W 3
O *-l 10 b
«> <0- > 4J


60
B
•H
^^ ^^
a c
0) CO
iH 4J


U
•H
3
•W ^3
3 U
CO Q
f-H
eo
60
0
o
o
•
o
f-H
•o
3
cr
eg
s « ~ §

fy; 00 «^4
V5 C±3 ^^ W
=J 0 -* <







































*



















































































.
















-











































«






•







































CR
,££
tn
a

^
£
o
03
3
U
C
•H

i-l
to
r-
«^







                                                     -145-

-------
     CM
     sr
      ta


*    o   3
fH    P^   P
     •s
                 CM

                 00
I;



CO
•W
0
**
~
fH C
a o
CO £
O u
e. Q
tfl U
i-l U
0 t-


V
u
c
• a
n w
e x
IB -H
£S
0
« *n
> 0
10 E
U 0
x ee.
e
o
^
a
> .c
a w
u c.
x a;
u o
e
a
e
"E
C3
c
o
u


x
AJ
^4
^
c
to
o-
fH
a
•H
0)
JO
Source

o
••^
eo
o\
sr

0
4J
•>» CM
CM ^

~

0
*•> O
eo i>.
•3- •
V> >^
5
a
2
jj a
0 >
z <


V
u
eg tu
1- S
3 (3
90 4J





ea ^>
BU 'i-'





0)
««» c
SO O
^^ 4^



J
O


O
^.^
r^
pv
£

o

<"> O CM
CM

-

0 O
U CM
CM *^
£
•§
fH
^ CO
O >
z <


~4>
U
a a
fcri C
3 a
0) U

"



<^
s *-•
o.

a
§
^

o

CM

01
i"H
a eo
a. -o
§3
i— I
a. co
ea
< «
Cu "^ CM O
M ^-CO
OT -J — t
3lu iy
^^ *^
c
0
JJ
«n
CM

««•
e
0
^^
fH
CM
CM

GO
41
e «H
s -g
s * S
0 "^

^
u
fH

01
V
in
en





*-s
03 ^^
a.


09
O
4J

CM
00


0)
eo
•H 3
O fH
CO 0)
O3
£2;
U -^ fH 01
M CO CO
w J as 



a
u
13
i
55




.—.
ea >-'
a.
01
c
0
u

("•I

•^
A
CM

f^^
£
01
01 • fH
fH -H O
*. O a
S3
< J£
a. n u
u •••» o .
(H CO >•
V3 nJ O> .
3 W«-H Z
                                                                                                                         £
                                                                                                                         o.

                                                                                                                         o
                                                                                                                         o
                                                                                                                         ul

                                                                                                                         O
                                                                                                                         in
                                                                                                                         O
u
c
                                                                                                                         en
                                                                                                                        •H


                                                                                                                         1^

                                                                                                                         U
                                                                                                                        03

                                                                                                                        Ifl

                                                                                                                        0)
                                                                                                                        eo
                                                                                                                        c
                                                            -146-

-------
t
1
I


a

o
t-
•V. 4J
<-i e
a 01
03 E
0 >>
O. CO
CO 0)
•H Ui
O H

/_s
01
u
c
• cd
03 U
e as
eg •*
b a
H ^
C
o
^4 ^H
u a
ca >
> 0
ca E
u 0)
x a:
w --
e
o
*f4
U
a
> f
CQ 4J
U C.
X CU
M O
4J
e
a
e
•H
to
c
o
«^
00


c m


0)
u
« n
iu j«:
w c
3 eg
03 W



































.





f











« a
e
0
•H
^j
B
(0
3
C'

W
Md
U
0)
u
co
^

Data
Source
U
Q. •
03
e
0


r-
i
U-l
T3 60
•H T3
»-l t) 3
O 01 iH
a) M
S3
< ee
S3^ M »
M GO >-
W ^J &\ •
3 M ^- S
















•






































*



































,





















t















•

















t
                                            -147-

-------
II
                                                        Material Removal
                                                        Excavation/transportation/disposal
Muddy conditions at the Missouri  Case Study site caused some delays in excavation
work.  However, at the US EPA, OERR cleanup in Florida, the palls were in a canal,
which required that technicians retrieve them by boat, while in full level A protective
gear.

Health and safety requirements and costs were rarelv  documented  and hence, their
actual effects on costs are not accurately quantifiable.  Since the relative effects of
these requirements are potentially greater for excavation/removal  than from  other
technologies, their approximate effect warrants brief recapitulation here.
Given the following level of personal protection:
                                                     t
     1.    Level A - requires full encapsulation and protection from  any
           body contact or exposure to materials (Le., toxic by inhalation
           and skin absorption).
     2.    Level B -requires self-contained breathing apparatus (SCBA),
           and cutaneous or percutaneous exposure to unprotected areas
           of the body (Le., neck  and  back of head) is within acceptable
           exposure standards (Le., below harmful concentrations).
     3.    Level C  - hazardous constituents known; protection required
           for low level concentrations in air, ^ exposure of unprotected
           body areas (Le., head, face,  and neck) is not harmful.
     4.    Level D  - no Identified hazard present,  but  conditions are
           monitored and minimal safety equip mentis available.
     5.    No hazard - standard base construction costs.
     Source:      "Interim Standard Operating Safetv Guides," EPA 1982
      The following levels of productivity have been assumed for other estimates:
           Site Level                Productivity          Equipment
                 A                 10% - 15%               50%
                 B                 25% - 50%               60%
                 C                 25% - 50%               75%  .
                 D                 50%- 70%
                 E                 70%-100%
      Source: CH2 M Hill, Inc.


                                           -148-

-------
1
I
F:
I
I
                                                        M aterial Rem oval
                                                        Excavation/transportation/disposal

This productivity effect Is already reflected In the expenditure data, but inadequate
technical data was available to detail the protection levels for each site.

The loading costs for liquids were lower than for solid, and were generally too low to be
significant.  But solidification costs for transportation or incineration costs for disposal
may have negated this lower cost.  Liquid wastes at the New York City *1 and California
?2 Case Study sites were quickly and continuously pumped into trucks or trains instead of
by the bucket load as  with contaminated  sofl. and sludge.   Drum handling was most
efficiently  performed with a hydraulic drum grappler at the Case Study Massachusetts
$1 and New Jersey sites.   This backhoe  attachment rented for  over $200/day,  but
reduced labor costs and other equipment charges by speeding up the loading process. The
net cost effect is unclear from  the available case  study data,  but the  use of this
apparatus by experienced removal contractors suggests an economizing value.

Finally,  waste quantity  may have affected excavation costs through unquantifiable
economies of scale. Larger sites such as the Maryland and California 41 Case Study sites
could maximize the use of  daily rental charges of backhoes because of  the greater
amount of  waste  present.  However, this effect does not appear to be significant since
waste quantity and  unit excavation cost among the case study sites does not appear to be
related.

Transportation-
The distance between the removal and disposal sites appeared  to be the most significant
factor affecting  transportation  costs.   Since  PCB  waste transportation costs did  not
appear to vary significantly  from  non-PCB  RCRA  waste, transportation costs for both
waste types are listed together in Table 43. The average cost for the twelve sites for
which  separate  transportation  costs  were   available  was  S0.17/ton/mile (SD =»
30.34/ton/ mile).
                                            -149-

-------
                     TABLE 43.  TRANSPORTATION EXPENDITURES
]
I
I
f! '
i
f;
I!
i:
j
CD
Data Source
ELJ/JRB-Massachussetts 41
ELI/JRS-New Jersey
ELJ/JRB-Massachussetts 42
ELI/JRB-Missouri
ELJ/JR B-Connecticut
ELI/JRB-N.Y. City 41
ELI/JR B-Minnesota
ELI/JRB-N.Y. City 41
ELI/JRB-N.Y. City 41
ELI/JRB-N.Y. City 42
EPA,OERR-Ftarida
EPA.OERR-Arizona
Unit
Weight Cost
(divided by)
$135/ton
$ 57/ton
$ 72/ton
$ 24/ton
$67/ton
$90/ton
$ 34/ton
$250/ton
$242/ton
$94/ton
$68/ton
$ 38/ton
Distance •
513 miles
• 440 miles
480 miles
170 miles
497 miles
818 miles
140 miles
1,740 miles
1,420 miles
400 miles
400 miles
(2)
400 miles
(2,3)
Unit
Distance Cost
$0.26/ton/m£Le
S0.13/ton/mile
S0.15/ton/mile
S0.14/ton/mile
$0.13/ton/mile
S0.ll/ton/ mile
S0.24/ton/mile
S0.14/ton/mile
SO.I7/ton/mILe
S0.19/ton/mile
S0.10/ton/mile
$0.17/ton/mile
*
(1)    assume i cuvd * 1 ten unless specified other wise by contractor or hauler.
(2)    assumed; actual distance unknown
(3)    15 cu yd/3,000 gallon truckload assumed
                               -150-

-------
                                                                 Material Removal
                                                                 Excavation/transportation/disposal
      The accessibility of the site to major roads was found to affect transportation costs at
      the California Case Study site *1. The contractor stated that a relatively lower price
      was charged because the site was near a  major interstate highway which led to the
      disposal site.   This proximity  to the  highway minimized the distance travelled on
      secondary roads and was said to cause less wear and tear on the trucks. This factor  may
T     have affected transportation costs at other sites where it was not stated explicitly.
i
I
n
r
i
The type of waste material affected transportation costs by dictating the transportation
method.  Liquid wastes were most economically transported in bulk using truck or train
tankers.  Solid waste was generally transported via truck, which required extra costs for
plastic lining and tailgate sealing.  Sealing of bulk liquid tanks was quicker because it
only required  closing and checking  valves, instead of silicon foam or asphalt sealing
necessary on dump truck tailgates. Relative costs of transporting roll off dumpsters was
not distinguishable.  The cost of transportation was also affected by the waste quantity
by influencing the type of transportation used.  Economies of scale were achieved by
using bulk tank trucks and rail cars for large quantttites of liquid waste at sites New
York City $1  and California. *2 Case Study sites.  Rail tankers, which carried several
times as much as trucks, provided the lowest unit transportation cost, as shown by the
New York City *1 Case Study  site.  Economies of scale with solids transportation costs
were generally limited by state laws regarding weight per axle.  Hence, the five axle, 20
cubic yard (15 m^) tractor-trailer dump truck was generally used.

Disposal/treatment -
The  most significant factor affecting disposal costs was whether the wastes were PCB
contaminated.  The disposal of cost for PCB waste was roughly double the disposal cost
for non-PCB RCRA hazardous  waste.  Among the PCB wastes, waste oil with over 500
mg/1 PCB at the New York City Case Study Site *1 was disposed of separately from PCB
oil with between 50-500 mg/1.  The disposal cost alone *as the same for waste oil above
and below  500 mg/1, but the required separate handling affected other costs because of
economies of scale.  Liquids from  this site were disposed of bv incineration, at a slightly
higher unit cost chan gniins, wnich  were iandfuleti.
A wide variation in disposal costs for non-PCB RCRA hazardous waste Is shown in Table
41. Ldq\iid wastes that were solidified prior to landfJUing, such as the ELI/JRB Missouri
                                            -151-

-------
I
I
I
                                                              Material Removal
                                                              Excavation/transportation/disposal
case study site, cost more perexcavated weight because the weight and buUc Increased
due to the added solidification material such as sawdust orlLme.  Aqueous wastes such as
those at Case Study California site *2 had lower tipping rates than the organic wastes at
other sites.  The non-technical factors affecting costs are difficult to quantify fully.  An
increase in disposal cost was encountered at Case Study Minnessota site when com munity
opposition blocked five i^-Hai proposals, which required a more expensive disposal option
to be used.  At the Case Study New York City site *1 delays and  more expensive disposal
options were encountered  when an out-of-state landfill refused to accept wastes.
The cityfe consultant stated that this problem "had less to do with waste characterization
data discrepancies as  with inter-state regulatory political factors" (CH2  M Hill, 1982).
Pre-1981 costs were significantly lower than the post-1981 costs.  This may have been
primarily due to the anticipated R C R A landfill regulations, and secondarily to inflation.

6.1.4.2      Estimates
The   following  factors   affected  the   cost  estimates  for   excavation/removal,
transportation, transportation and disposal/treatment:
     o      Excavation:
              depth
               method
     o      Transportation:
              distance
              contractor
     o      Disposal:
               Method
Generally, the factors affecting estimates (Table 44) were similar to those the affecting
the expenditures,  which was of significantly  less technical detail was available for the
estimates scenarios.

Excavation -                                                               ' *
Excavation  cost  estimates  seemed  to  reflect  primarilv  varying depths.   The SC3
"impoundment" estimate and the New Jersey  RI/FS assumed that a  frontloader would be
adequate to scrape up the contaminated soil and topsail, respectively. In the analgous
estimates scenarios, however, the need for a shovel excavator to dig deeper caused
                                            -152-

-------
      01

II
I


—^
09
^

t^

OS
a ai
to E
O 4J
B. a
09 01
•H Wl
O H


0)
u
• £J
a a
a n
h -H
HS
O
•H ^H
J-l IB
xcaval
Removi
w-w
e
o
•H
U
<8
> X
Q ^J
u a
X 01
w o
4J
e
a
e
^H
s
to
4J
I
X
4J
C
. a
£

a)
•H
^
0)
4J
2



01
u
n w
•u 3
n o
O V)
^
^^
m *o

^^ 3
P- U
CO

-•* "9
O >%
CM 3
• U
co
00
CM
<0-

•o IB
X 01
**» H
0 B
•» 0
• o
S CM
O* v-x
•0
u

o-

e
01 •
^
•H
00


o
c

01
_J
fcrt

^
o
e
•o
3
u

o
iH
a
e

C
^^
•o
0)
a

^ 2
W 1 0
to oo
3 S^ rt

1 -^

VO CM
. . c /-«.
vO ON O CM
tH 1-1 JJ N-'
CM CM

^
•* e
• o
*^ ^
i-t
CM

^^
CO 0)
• Ol
«ff C «H
•1. 0 -rt
IS •" B
vO
O
iH CM
p*.
CM .«-
iH ">, I
IS -» vO
«n u oo CM
00 • •
^5 ^^ ^D
,
^) 3
r^ y
*


0)
• CO
«H "O
? 5
A a
*
•a
e
w a oo
u s o\
w -5 
vO
^^ T3
•H U 01
CM e
•n o
,
3 3
u u
ON 00
CM iH


C
01

—^
CO

4J
o
c

09
e o;

0) > ~"
e IH .
O O CO
C 09 S
•o -a
>> x
3 VO 3
U P» U
00
O
O 1-4
.H in

1-1

Q *
09 f*H
a «H
O --1
^ U-l
s
^^ *v*4 Q
a. z CQ
5 * 3 "
3 U, ^ Z ^
                                                                                                                             en
                                                                                                                             c
                                                                                                                             o
                                                                                                                            00
     3
     U


     0)


     O

     en
•O   0)
 ^   C


IH   tn

">   W
>^   c
                                                            -153-

-------
1
[11
lt    4J
•o
 01


 E
       O
       U
       eg
      H
 D

 C
 I
iH
eg
4J
o
H
i-i
"•«. 4-1
fH C
n oi
SB
O. eg
09 01
•H fc.
O £-"

*t)
U
B
• a
09 4J
E 05
eg -H
ne
f-i«-'
s
o

4-1 eg
eg >
> o
a E
O flJ
xos

s
0
•H
Jj
eg
>x;
CO 4J
U &
X 01
W Q
4J
S
eg
B
•H
e
!fl
4U
B
0

X
4J
•H
4J
B
CQ
o-
fH
a
•H
Iri
01
U
53
Z
IData
Source
i
i
i




>> «H

O •• B) «H
CM T3 4J U-i
1 >, -H -0
CM 9 E E
 CO iH
S -H ^
OS oo
u -s. 01
•V. C IH
O O -H
in 4J E
r«! CM in
«H n m
 . +~*
9)
^4
XI
eg
i— i
«^
u eg
O >
B eg
0)
fH
^t
eg
T-t
•H
u a
o >
B eg



CO

B
4)
^
«H
O
00
CU
.0
es
t^H
^4
u tg
0 >

B
01
• E
•H -H
•H -0
O 0)
^0 09

< e- en
Cu W 01 0)
WOE 1- pg .
to O ao ^

I
1



.
 *— '
01
f^
Xi
eg
l-H
•H
4J CO
O >
B 09
Ol
• fH
Xi
Q

•H
u eg
O >
B eg


•
(0

B
01

t-4
O
00
0)
Xi
CB
fH
•H
4J eg
0 >
B eg
B
0)
• E
fH *H
•H t)
O Ol
99 CO

"•» 16 01
< Cu CO CO
cu S3 oi at w
w Q E WCM o)
(Q O QO ^
W n Q OON •
=> 2 Z -H Z

1
I



O)
^ Wi «-<
O 01 fH
00 -O CU -H
1 >. E «-i
OS -H t3
vO U 00 B
 6 »
0) fH
CO
CU
tH
B -H
2 ,6
•*^ o
o o

«> x^
0)
fH
XI
a
fH
•H
4u eg
O >
B to
0)
fH
x>
a
fH
•H
u eg
0 >
B a



a

B

^
fH
0
«°
0)
XI
eg

B 0}
E
01
• E
fH -H
T< T)
O 11
VJ 3J

o« §3 oi oi fsj
'
i
t
i

E
01
^
•H
00
4-1
o
E

CM <"s
^^ *«-x jj
O^ X
fH •, .U
P*. n 3
1 fi 0 O
CM « 01
mo ta
«> v> *-*



B
01

O 
O -H
B 60





E
OJ
•u >
O «H
c u




E
01

O -H
• E eo


E
at •
4J >
0 -H
C iO

a.
to co
in U a\
S to fH
                                                                                                               •o
                                                                                                                CO
                                                                                                                o
                                                                                                                      u
                                                                                                                        W
                                                                                                                E —

                                                                                                                O E
                                                                                                                4-1


                                                                                                               0§
                                                                                                                      C
                                                                                                                      o
                                                                                                                      c.
                                                             -154-

-------
                                                            Material Removal
                                                            Excavation/transportatiDn/disposal
I
I
I
e
higher estimates.  In all cases the excavation  cost estimates were about an order of
magnitude lower than the expenditures given above.  The reason for this difference may
be that excavation of hazardous material does not simply add costs to the estimate for
additional tasks such as health and  safety protection  requirements.   But, rather it
necessarily affects all tasks involved  in excavation such as reduced labor productivitv
while to of encumberances from protective gear and delays due to waiting for analyses.
Standard Construction-Engineering  manual estimates  (see examples Table 45)  fail to
consider adequatelv the effect of these factors.

                                    TABLE 45.
           ESTIMATES FROM ENGINEERING CONSTRUCTION MANUALS
     Item
Design Basis:
Cost
I;
I
1
           Excavation with
           dragline
                                3/4 yd bucket, 90 swing,
                                rating 33 yd/hr
                                1.5 yd bucket, 90 swing,
                                rating 65 yd/hr
                                        $2.47/cuyd

                                        $1.76/cuyd
Excavation with Hydraulic, crawler mounted
backhoe 1 yd bucket, rating 45 yd/hr
1.5 yd bucket, rating
60 yd/hr
2 yd bucket, rating
75 yd/hr
3.5 yd bucket, rating
150 yd/hr
Wheel Mounted
0.5 yd bucket, rating
20 yd/hr
0.75 yd bupket, rating
30 vd/hr
Excavation with 0.5 yd bucket, rating
clamshell 20 yd/hr
1 vd bucket, rating
35 yd/hr
S2.17/cuyd
S1.96/cuyd
$1.93/cuyd
$1.48/cuvd
33.95/cuvd
$2.92/cuyd
$4.34/cuyd
S2.93/cuvd
%
           Source:  Radian, Inc., 1983
                                           -155-

-------
                                                               Material Removal
                                                               Excavation/transportation /disposal
1
Transportation -
The transportation cost estimates ranged from S1.42 - 94/ton as shown in Table 46 .  The
distance strongly affected the cost of transportation  for a  ton of waste.  The cost
estimates per  ton per  mfle are  given in  Table 46.   They  ranged from  S0.07 -
0.51/ton/mile.   The mean was $0.25/ton/mfle (SE«$0.04/ton/mile,  n=10), which  was
almost twice the average expenditures found for transportation.  However, the distances
assumed for the estimates were significantly lower (3.6 times)  than those found to be
necessary for actual sites, (average distance found for transportation expenditures = 618
miles, SD«485 miles; average distance assu ration given for transportation estimates = 168
miles, SE-65, n - 7).
IE
                             TABLE 46. TRANSPORTATION COST ESTIMATES
Data Source
Unit Weight
Cost        (divided by)
                                                         Distance
Unit Weight
Distance Cost
      JRB-RAM
                    $94/ton
                               200 miles'
$0.47/ton/mile
(I
scs
'!im pound ment"
      New Jersey $ 2
      RI/FS *2
      SCS 1983
$1.42-3.27/ton
                    $17.50/ton
                    $52-76/ton
                                                         20 miles
                                35 miles
$0.07-0.19/ton/mile
SCS
"landfflT
$4.47-10.14/ton
20 miles $0.22-0.51 /ton/ mile
S0.32/ton/mile
New Jersey
RI/FS *2
New Jersey
RI/FS *2
$17.50/ton
$70/ton
100 miles $0.18/ton/mile
400 miles $0.18/ton/mile
                               400 miles(l)      S0.13-0.19/ton/mfle
      (1) Assumed: 400 miles, see text.
                                           -156-

-------
                                                            Material Removal
                                                            Excavation /Transportation / Disposal
     The hauling cost estimates were also found to depend on the type of transporter as shown
     Table 47. These specific costs are not necessarily representative but do show a pattern
     of relative costs.

                                         TABLE 47
                 AVERAGE TRANSPORTATION  COSTS BY TYPE OF TRANSPORTER
I
I
P
I
t
Type of Transporter
Unit distance
cost/'trucUQad"
Unit weight
distance cost (1)
Treatment, Storage, and Disposal
Facilities Providing Service
to Customers
General Freight Transportation
Companies Which May Haul
Hazardous Waste on Request
Hazardous Waste Transportation
Companies Specializing in
Hazardous Waste
$2.67/mfle
($1.66/km) .
33.60/ mile
($2.24/km)
$3.70/mile
($2."30/km)
$0.13/ton/mILe
(SQ.09/Mt/km)
•
$0.18/ton/mile
(S0.12/Mt/km)
S0.19/ton/mile
(S0.13/Mt/Km)
Source: SCS Engineers, 1983.
(1) Assume 20 tons (18 Mt)/truckload
     Disposal/Treat m ent
     The most salient factors affecting disposal cost estimates was the method used in the
     disposal cost estimates from the RI/FS from the New Jersey site shown a doubling of
     disposal cost  for each increase in landfill security.  However, since hazardous waste
     cannot be safely or legally disposed of in a sanitarv landfill, this cost is inappropriate to
     compare with other estimates  for engineered landfills.  Also, the other estimates are
     significantly higher than the actual costs found. Table  48 shows price quotes from a
     sample of disposal/treatment firms.
                                           -157-

-------
                                                              Material Removal
                                                              Excavation/transportation/disposal
      Expenditure Sources

           o     ELJ/JRB Case Studies, 1983
           o     State and Federal Super-fund work
      Estimates Sources
I
           O     JRB-RAM, 1980
I          o     Radian, 1983
m.
           o     US EPA OERR contractor Feasibility Studies
           o     SCS1980
                                           -158-

-------
                                     Table 48

              AVERAGES OF HAZARDOUS WASTE MANAGEMENT QUOTED PRICES FOR ALL     ;

              FIRMS IN 1980 AND FOR NINE MAJOR FIRMS IN 1981*  (in 1982 Dollars)
TYPE OF WASTE
MANAGEMENT
INCINERATION
CHEMICAL TREATMENT
DEEP WELL INJECTION
LANDFILL
LAND TREATMENT
TYPE OF FORM OF
WASTE
clean liquids
high BTU value
liquids
solids; heavy
toxic liquids
acids/
alkalines
cyanides, heavy
metals (2)
oily
waste water
toxic
waste water
Drum
Bulk
All
UNIT COST
1980 1981
$0.65/gal
$131/cuyd
s
$2.12/gal
$429.50/cuyd
$0.21/gal
$42.50/cuyd
$1.30/gal
$262/cuyd
$0.13/gal (1)
$26/cuyd
$0.59/gal
$119.90/cuyd
$2.43/gal
$490/cuyd
$0.24/gal
$47.50/cuyd
$1.76/gal
$355/cuyd
$0.13/gal
$26/cuyd
$0.88/gal
$179/cuyd
$35. 40/55' sal.
drum
$53/ton
$45.90/55 gal.
drum
$67.50/ton
$0.07/gal
$14/cuyd
1
I
D
      Source:
    (1)  Some cement kilns and light aggregate
          manufacturers are now paying for waste

    (2)  Highly toxic waste

U.S. Environmental Protection Agency.
"Review of Activities of Major Firms in the
Commercial Hazardous Waste Management Industry:
1981 Update".  SW-894.1.  May 1982.
                                           -159-

-------
                                                                      Material Removal
                                                                                Dredging
      6L2 HYDRAULIC DREDGING
      6L2.1       Defixritioa
      Hydraulic dredges are used to remove liquid, slurry, or semi-soliri (sludge) wastes from
|     improperly constructed or improperly sited disposal sites.  Once removed, the wastes can
      be pumped to treatment and dewatering facilities, or transported to acceptable nearbv
J      land disposal sites.
 i
-,     6.2.2       Units of Measurement
I,     Costs are given in dollars  per cubic yard  because it  provides  a useful standard
      measurement that is comparable to excavation.

[
      6L23       Sum mazy Statistics
c.
                                                                             t
      6.2.3.1     Expenditure
f>*     No expenditure data are available at this time.

IM     6.2.3.2     Estimates
li     The hydraulic dredging cost estimates ranged from:

IL                $3.54/yd3    Contractor dredging only
                    to
                 S1.25/yd3    Includes related fixed costs: sheet piling, sELt curtain, coffer
                              dam etc.
i
      The lowest cost estimate includes only contractor prices for the oredging ana pun ping
      phases of the operation.
                                            -160-

-------
I
I
I
B
I
                                                                           Material Removal
                                                                           Hydraulic Dredging
6L2.4        Factors Found to Affect Costs

6.2.4.1      Expenditures
No data was available at this time.

6.2.4.2      Estimates
     o      Equipment type
     o      Pumping system capacity
     o      Sludge density
     o      Transportation of slurry
     o      Inclusion of related costs
                                     •
The  most important  factor affecting costs was the inclusion of related tasks.   The
Feasibility Study for the Illinois site included a variety of necessarily related tasks that
are listed in Table 49. These tasks accounted for $119 cuyd of the total $125/cu.yd. unit
price (see Table 50).  Assuming similar included  costs, other site specific and equipped
factors also affect costs.
                                               *
The equipment assumptions varied with the site condition scenario. Land based, floating
and barge-mounted hydraulic dredges represent increasing costs for varying depths and
waterway sLzes.  The JRS-R AM and Radian  estimates did  not specify the dredger tvpe,
but the minoifi feasibility study assumed a barge-mounted dredger..
                                            -161-

-------
I
                                          TABLE 49.

           ADDITIONAL RELATED COST ITEMS ESTIMATED FOR HYDRAULIC DREJTGING-
                             EPA OERR, CH2 M HILL, ILLINOIS, 1983.
      Task/Cost Item
Quantity
Unit Cost
      $855,138/7,200 cuyd » $119/cuyd related costs + hydraulic
      dredging ($6.12/cuyd) - $125/cuyd
Total
Pipeline to lagoon
Sheet pile caisson -
douhLerlng-13400SF
PS 27
Remove sheet -
pile cofferdam
Replace existing pites
ft floating docks
New boat hoisting
facility
Sedim ent control -
2 x silt curtain
1,200 LF S11.97/LF
181 tons S23.36/ton
181 tons $11.68/ton
690 LF S195/LF
1LS • $15,000
600 LF $ 95/LF
$14,364
$422,816
$211,408
$134,550
$15,000
$ 57,000
$855,138
                                         -162-

-------
 f

I
     o
     in
               09

               M
n   t-5
o>   S   3
2   P   <§
a
H
s
    .Q   £











09
0
U

01
ecu
cc
•HflJ
CLU
§2
0.0

4J
a
B
1
O
o


I
a
01
X
JJ
•H
4J
|

°"


01
9
O
co
0)
u
s






n
•a
>%
^
°\
\
,3,
\f\
•


IM
§
O
fH


01
•H
^1 '
O
4J 0)
o a
Z 09

CO
X
X S
a u
"3 3
•»- o
TJ Iri
X O
«» e
ON O
%O *f4
U
3
09




*ln
CO QC ^^

09
«J
4J CB
C 0
C8 U
U
•fH ^3
IM U

e a
60 iH
•H 0)
09 M
CO 03 "O
•o oi e
X -O fl
^* 3
fH U 01
X X .
NO 01 -H

*M
o
o

•o
0)
^J
09
"B oi
a eo
aa e "i
U 0 fH
a. u OB

.
-3
*»%
•O
tn
fM
w»



3
CO
- - X
" s 2 *
I _ ja o

-------
            The  system capacity likely affected unit costs  through economies of scale.
      Inadequate data were available to quantify or confirm this effect.
            The sludge density affects unit costs because, after dewatering, low density sludge
      may yield less contaminated sediment volume than a higher density sludge.  This effect
      must be  considered in light of the higher suction rate  possible with a lower density
      sludge, however.
            Sludge transportation variations affected costs, since the JRB-RAM  and Radian
      scenarios assumed that only piping would be necessary; whereas the Illinois feasibility
i      study assumed the need for a barge-mounted hopper as well as a pipeline.

      Estimated Sources
           O     JRB-RAM, 1980
           o     Radian, 1983
           o     US EPA, OEHR contractor Feasibility Studies
                                            -164-

-------
                                                                         Material Removal
                                                                         Mechanical Dredging
j
 1
 I
i
      &3 MECHANICAL DREDGING
6L3.1       Definition
Mechanical  dredging  with  draglines,  damsheels,  or backhoes is used  to remove
contaminated sediments from shallow streams, rivers, lakes, and other basins of water.
The stream is usually diverted with temporary cofferdams; the sediments are dewatered,
excavated, then loaded onto haul vehicles for transport to a disposal site.

6L3.2       Units of Measurement
Costs are given in dollars  per  cubic yard  because  it  provides  a useful standard
measurement that is comparable to excavation.

6&3       Sum mary Statistics

6.3.3.1     Expenditures
No expenditure data are available at this time.

6.3.3,2     Estimates
Mechanical dredging cost estimates ranged from
           31,37
              to
           4.09/yd3
                                                                    •
The  range reflects varying  equipment assumptions derived from  a single estimate
source.   The  low end Involves a simple backhoe, while the  high end  a  clam shelL
Mobilization and demobilization costs for the backhoe added 31.50. Hauling and disposal
costs of  the  dredge  material was not included (see  excavation,  transportation  and
disposal).
                                            -165-

-------
                                                                              Material Removal
                                                                              Mechanical Dredging
       &S.4       FactOKS Found to Affect Costs

       6.3.4.1     Expenditures
       No expenditure data are available at this time.

 *     6.3.4.2     Estimates
       The foliowjtag factors appeared to affect the cost estimates from mechanical dredging:
 1.
 I
I
           o  Equipment
                  Use of Barge
                  Excavation method (backhoe, clam shell, or dragline)
           o  Site condition
                  Depth of sediment
                  Water table

                  Additional costs:  Barge
                  Sheet piling (pile driver)

Since mechanical dredging is most suited to dredging shallow water, the cost will rise in
                                              *
proportion to the depth of the water and the size of the dredging surface.  The use of a
barge  would  double or triple the unit cost for mechanical dredging;  hence, the
accessibility of the sediments has a significant effect on costs.  Also, wet excavation
may require sheetpfling or a cofferdam to support the dredging.

Table 51 shows the estimated cost for these additional tasks and the pile driver is shown
to be significant.

The basic dredging sqidpment costs varied 
-------
                                    TABLE 51

             ADDITIONAL COSTS TO BASIC MECHANICAL DREDGING
Barge-mounted dragline or clamshell,                              $5.31-7.67/yd3
hopper dumped, pumped 1000' to shore dump


Sheet piling, steel, high strength
(55,000 pel); temporary installation
(pull and salvage):
                                    20' deep                    S9.72/f t2
                                    25' deep                '    $7.82/ft2
Pile driver; mobilize and
demobilize:
                                    50 mile radius               £ 6,726 total
                                    100 mile radius              $11,151 total
     Source:      EPA. Manual for Remedial Actions at Waste Disposal Sites

                       625/6-82-006


Estimate Source
           JRB-RAM, 1980
                                     -167-

-------
1
 CM
 ID
  CO
U    jj
Q    -3
          0    I
   O
  «H
   09


0) 01

« E
                                     we
                                       c
                                       ca

                                      •H

                                       a
                                       4J

                                       o
                                      u
                                                  •o
                                                   >s

                                                  ff*
                                                  O
                                                   •
                                                  «»•




                                                  r«.
                                                  en
                                                            •a
                                                             Q)
                                                  01     01   E
                                                 IM     oi   a
                                                     X MM   V
                                                 tf\          U
                                                   •     O   4J
                                                 r«.     »n   OQ
            •o
             01
             u
             01
             a.
             CB
             e
                                                  •o
                                                  ^»

                                                  o
                                       01
                                       u
                                       w

                                       o
                                       V}
        a.
               i
                                                o
                                                00
                                          ec    os
                                          "->    *4
                                                                       -168-

-------
                                                                   Material Removal
                                                                   Drum removal/transportation/
                                                                   disposal
1
I
                                                    4
      6.4 DRUM REMOVAL, TRANSPORTATION AND DISPOSAL/TREATMENT
6L4.1       Definition
Drum handling Includes excavation in cases where the drums (bucket, pails, containers
etc.)  were  buried;  or,  simply staging,   overpacking  and  loading  for  transport.
Transportation involves hauling loaded material to an off-site disposal treatment f adUtv.
Disposal/treatment   may  include  landfiHing  and/or  other technologies  such  as
neutralization, sottrflftoation or treatment.   These are combined here because the cost
for aH three tasks are often combined into a unit price.

6.4L2       Units of  Measurement
Costs are usually given in terms of dollars  per drum (bucket, paH, containers, etc.) for
comparison purposes. However, these costs may include other component tasks such as
overpacking and adjacent contaminated soil, as noted.

6.4^3       Sum mary Statistics
                                             »
6.4.3.1     Expenditures
The following ranges of expenditures were found from drum removal, transportation and
disposal/treat m ent:
           Drum, removal:           $60-l,168/drum
           Transportation:           $15-261/drura (30-480  miles)
           Disposal/treatment:       $36-360/drum

These cost elements  cannot necessarily be sum med, since the extremes of the ranges are
derived from different sources with different scenarios and assumptions.
                                                                           *
              Site Total:         $60-l,528/drum
                                            -169-

-------
                                                                Material Removal
                                                                Drum removal/transportation/
                                                                disposal
1
Some of the costs for the above three tasks may have been combined in the new data.
For the removal costs, the high  expenditures  may reflect the use of overpacking and
containerization. Transportation cost of a drum likely varied with distance, but distance
information was rarely available.   Some of the  disposal costs given  also include
contaminated  soil disposal expenditures  for bulk soil disposal.    Operation  and
maintenance costs may include ground water monitoring and, possibly, site inspections or
security  to prevent future  illegal dumping, which is often repeated at  former sites.
These costs were either accounted for separately, or were not encountered for the sites.
      6.4.3.2     Estimates
      No handling cost estimates data are available at this time.
      6.4.4
            Factoxs Found to Affect Costs
      6.4.4.1
            Expenditures

      The following factors were found to affect drum removal expenditures given in Table 53
                                                    *
      in the Raw Data section.
                 Removal-            Waste type
                                       Drum condition
                                       Drum size
                                       Drum situation, depth
                                       Adjacent soil contaminant
                                       Demurrage
                                       Economies of scale  •
                 Transportation
                 Disposal -
                                 Distance
                                 Waste type.
                                            -170-

-------
I
i;
                                                          Material Removal
                                                          Drum removal/transportation/
                                                          disposal

Removal - The waste types found at the Michigan,  California *2,  Florida, Vermont and
Philadelphia sites seemed to have had a significant effect on the removal costs.  In all
cases, the cyanide, caustic soda, ethyl ether (highly flam mable), aromatic hydrocarbons
and super tropical bleach (calcium  oxide-chlorinated lime),  required that Level A or B
protective  gear, treatment (solidification or neutralization) and recontainerization be
added to the removal costs.  In addition, careful management of these more hazardous
waste generally increased the time necessary for the various elements of the operation
such as labor and  equipment.  In adequate  technical detail was available, however, to
quantify its effect.

Poor drum  condition increased removal costs because it necessitated overpacking.  In
cases where  waste had leaked  out increased costs were incurred  for transferring the
         *
waste and emptying and crushing the drums. A variety of drum sizes are given in Table
16.  Overpacking 30 and 55  gallon drums required 55 and  80 and gallon overpacks at
increased costs.
-.                   "                                                  *

Most drums were removed from  the surface.  The drum removals requiring excavation did
not cost significantly more than the surface drums suggesting that the added costs of
                                              »
backhoes and  drum  grapplers  were  less significant than  other  cost items  such as
treatment  or protective gear  necessary for high risk waste.   Also, a drum  of an
unidentified liquid floating in a Los Angeles.  California river required additional costs for
a boat, but was not significantly more expensive than other surface removal.

The extent of adjacent soil contamination varied among  the sites given.  In some cases
the total cost included removal of bulk soil, but the unit cost is derived by dividing onlv
this total hy  the intact or overpacked drums. Hence, the removal.cost per drum mav be
in overestimate in some cases.  For the  ZLJ-JR3 sites in New Jersey,  Connecticut, and
Massachusetts, the drums were  emptied, crushed and bulked along with contaminated soil
necessitating a bulk volume unit cost.  More analysis of technical details is necessary to
reaggragate these costs.
                                            -171-

-------
I
1
                                                              Material Removal
                                                              Drum removal/transportation/
                                                              disposal

      Based on two observations the economies of scale appeared to affect the unit costs of
      removal.  First, there was a general inverse relationship between the total site costs and
      the unit cost per drum.  Second, certain  minimum  costs  were charged for component
      tasks such as mobilization of technicians and equipment.  M minimum charges also apply
      to transportation as noted in the discussion of Excavation cost factors in the previous
      section.   However, the Michigan site cost for transportation  ($2/truck/mile; $60  one
      truck, 30 miles) was lower than many minimum hauling charges.

      Transportation - Inadequate Information  was available to compare cost  per mile of
      transportation, but the effect of distance, as well as the rates can be expected to be
1     similar to  those found  in the above Excavation section.   Demurrage was not found to
      significantly affect the costs since it was explicitly charged only at the Philadelphia site
[|     ($50 out of $1,410-4% X

      Disposal -  Although  the reasons for the widely varying disposal costs were unclear
      because of inadequate technical detail availability, they parallel these given In the
      m aterial re m oval section.

      6.4.4.2      Estimates
jj     No cost estimate data are available at this time.

|!    ' Expenditure Sources
L
T        -o     ELI/JRB Case Studies, 1983
*          o     State and Federal Super-fund work.
                                             -172-

-------
i


I


r
       m

        «
        co
       H
f-4
(B

O
H
<-l E
CO V
O 4J
o. a
10 A)
•H hi
Q H



XK
01
U
B
(0
• 4J
CB 0
B It
CO Q
H «•*
0
•H ^
U CO
> 0
CO E
U 01
x ee
tti *^^
B
O
*H
^
(9
> JE
co JJ
U 0.
X 
hi
*C3
*n
t1^
w




E
3
hi

^^
O

CM

§ ' *
1- *- 3
•U 00 U x-s
O -3- •
O • CN
^T pH ^^
 «/>
•

0)
u
eg
 -3


S
hi
•o

o


4fo








§
hi
«n "°
vO

«>•
w
0)
01
01 AJ ifj
. 60 41
co oi m
hi U- <"1
01 I
^ o o
CO CM "**


CO
^
B
0)
^
(^
O
CO




§
§ B
m .*
• E
«*• 3


ca
§ a
U 0
•Q ca



i a i|i
t* vi — a
as 3 ctf M
f^ " ^^
tA ^1
^y w^
«•
•o
^^^
o
o
c^
w


4)
i-t

"B

o
CN

O
r-t

B
u
T3
C^
CM
r- 1


41
U
CO
Vkt
hi
3
ca




I
B
3
^*4
U

CO
u

.g
>\
U
in
^^
«
a

o ^
pn co
eo •
• 1-1
OI 14
B <0
o a

§ m
< o -a
a, E -H
u ac 01 ^ u
0£ u B O
C/J U CO 3 iH
300 fa





*J
o
E
o
c.
o
u

hi
o *c
E >
•H 3
E u

• * r<*
B CM
a. •
D.O
SI
i n
*n -^

^^ ^^
CcS

.














flf!
^^
t;
e?
**
hi
4)
U
0
01
•Q
3
»^
U
e
X
2
CO
4J C
CO -H
0 J^
y -j
CO
H a
CO M
u &
0 >
H 0
>H CN
                                                                                                                                     CO
                                                                                                                                     03
                                                                                                                                     O
                                                                                                                                     C.
                                                                                                                                     m
                                                                                                                                    •o
                                                                                                                                     o
                                                                                                                                     o
                                                                                                                                     a
                                                                                                                                     en
                                                                                                                                     c
                                                                                                                                     CO
                                                                                                                                     hi
 (U
•a

iH
 u
 CB
 CO
 o
 u
in
                                                                   -173-

-------
   1
   (1
•  P
.   11!



1-1
C9
XI
O
H
fH
"•>»>—
iHXI
w
0
*-li-t
W (0

> 0
a E
u 5
MS:
U -v.
e
o
•H
XI
C9
> J=
a xi
y a
X Ol
ca a

u
e
a
«H
e
a
^
o
u


X
u
•H
XI
e
CO
S-
J^
eg
^
b
01
XI
a
X
(Data
Source
•o
i-l X
m -H 3
in x-. CB u
IH <• a **»
• • -* •*
00 (M >3- 00
«-• *<* «>«>•
^M'
•o
X
3
y
vO
in
m

m
8 .->
*-w ^«i
^^ *W
•O *+. •»*
x a
3 ^ -O
,0 y x
r-. w o
•H *«.
. CM 00
O >-* \D
v>  >-<
•a
*». x
o* s
«e y
i
•*
m
«v
u
0»
w
u*
0 " '
CN
1
in
•-i

•


m
xi
e ca
0) i-l
> o
*-* XI
0 4J
CO S




•o
»- X
O 3
*H y
•
m

*
09
E iH
3 -H
1- O
•D CO
S £
n co
•»• »H j u
M 00 01 01
-J ON Z<-)
W -J

e
o
XI
**^
O\
•H
iH
«>


O
XI

O
<•
•O

/*s
•
^H
e e
0
XI •»
•«*. O\
r^. •»
\o ^
•CA-
TJ
x

y

iH
i-l
V>
XI
Ol
01
U-l
n
iH
I
tn




ca
XI
e a
01 i— 1
> eg
WH u
0 U
a g

•a
x
3
y

o
r^
r^
»
«T


CO
§^
•H
k> O
•o to
to
at
n -ao
*•*> e •*•
M C O\
J O >H
Cd U




1




0
XI

»y
00
v>

f^
CO
Ol
"O ^4
W ^^
>s «H
3 6
y
^ o
iH GO
r^ 'C-
<^- ^^
0)
^-t
^
Q
^
•H
JJ CO
O ^
z<


w
y
es
IH
p
g
CO

'


0)
4J
(U

^H
o
CO


•a
x
g
y s"*t
•n
*H ^«^
00
T


I '
Jj
•o
•
ca j=
06 U
•-) (8 00
-•» 03 r»
M CO CTS
J « -H
u r
                                                                                                                                                            .O  CO
                                                                                                                                                                 I
                                                                                                                                                            T3  C
                                                                                                                                                             s

                                                                                                                                                           §  i

                                                                                                                                                           T3 *J
                                                                                                                                                           01  CO
                                                                                                                                                           —I  O
                                                                                                                                                           •H  U
                                                                                                                                                          •a   to
                                                                                                                                                           e  u
                                                                                                                                                           to   o
                                                                                 -174-

-------
                                                                   Sewer & Water Line Rehabilitation
                                                                   Sewer Line Replacement
I
D
I!
I
7.1.4       Factor Found to Affect Cost

7.1.4.1     Expenditures
No actual cost data available at this time.

7.1.4.2     Estimation
The following factors affected sewer line replacement cost estimates:

     o     Pipe size
     o     Pipe composition
     o     Depth of excavation

Pipe size and depth  seemed to  be most directly related  to the cost of sewer line
replacement costs.  The cost of excavation, which is a major component of sewer line
replacement, was affected by the depth and size of the pipe. The cost of the new pipe,
which is the major material  cost factor, was largely a function of the pipe size and
composition.   Since reinforced concrete pipe was assumed for both estimates,  cost
estimates vary mostly with size.
                                             «

Estimates Sources
     o     JRB-RAM, 1980
     o     Radian, 1983
                                            -176-

-------
I
              H
              O
              H
              Z
        in
                   09
                   eg
                  ON
             Cu  ~

             z
             tt
             Cfl

CO
0
cj
4J
•H
e
ca
•H
a
01
o.
•H
a.
Q.
X
H
CU
a
 U
j- g « s
5 h -5
u c *o «H
0 0 0) •*
01 1-1 .O «M
0. W J^
09 U -O O
e cu e a
M CO S .O

<
••5
^ ' %
6Q ^^
6/3 ^ ^^

•J Nw *J J
^.^» O 0
O O CK iA O>
ON NO »J • •
cn vo i/> o en
m NO oo »H  T3 US S
0 -0 «^J
• 8 0) « u
C a -3 5 y
0 W § eg
w c c S §•
u o eg u 5
0) -H eg y
0. *J 01 ^H
ca o a. o.
-------
                                                            Sewer &  Water Line Rehabilitation
                                                            Sever Line Repair
I
I
r
      7.2 SEWER LINE REPAIR
7.2.1       Definition
Sewer lines contaminated by  migrating leachate  may be reconditioned in place if pipe
damage is limited.   The procedure includes interior Inspection, cleaning (mechanical,
hydraulic or chemical means)  and repair of damaged sections.  The upgradient source of
contamination is assumed to have been removed or encapsulated for the purpose of this
section.

7JL2       Units of Measurement
Costs  are  given in  dollars per linear foot (LF) because it provides  a simple and
standardized measure of sewer lines.
         *
7.23       Sum mazy Statistics

7.2.3.1     Expenditures
The only expenditure for cleaning and flushing contaminated sewer lines was:
           $15/LF. •

The cost tser foot for cleaning sewer lines was the same for all pirdng sizes, which ranged
In diameter from 10-21 inches.  No cost comparison was possible since only one actual
expenditures was.

7.2.3.2     Estimates
Sewer Line recondition cost estimates for 12 - inch diameter pipe ranged from:

           $5.75
              to
            S15.30/L?
                                           -178-

-------
i
E
I
                                                                Sewer & Water line Rehabilitation
                                                                Sewer Line Repair
Cost estimates for repair included  cleaning, interior inspection and internal grouting
repairs for 12 inch diameter pipe in average condition.  Higher estimates were expected
for larger diameters  and/or more extensive grouting.   Disposal costs of removed
contaminated material were not included in these estimates.

7.2.4        Factors Found to Affect Cost

7.2.4.1      Expenditures
The paucity  of expenditure data precludes quantification of component costs and the
factors affecting total unit costs (see Table 55).

7.2.4.2      Estimates
The following factors affected cost estimates for sewer line reconditioning  (see Table
56):

     o      Diameter of piping
     o      Extent of damage

Although the paucity of data hinders quantification of the cost factors, the  above two
factors appeared to directly affect the level of effort required for repair, and  hence, the
cost. The extent of the damage was probably the primary factor affecting costs since it
was directly related to the amount of repair that was required.  The size of the pipe was
less directly related to costs, but still affected the area to be repaired.

These costs of contaminant handling and disposal were not included in the estimates and
 must be  considered as a site specific factor.

 Estimates Sources
            O     JRB- RAM, 1980
            o     Radian. 1983
                                             -179-

-------
  f
          in
          i/t

           v
          
-------
 1

 0
    4>
  , £
 r
 D


r
L
                                           -181-

-------
                                                               Sewer & Water Line Rehabilitation
                                                               Water Line Repair
        7.3  WATER LINE REPAIR
        7.3.1       Definition
        Municipal water lines, contaminated by infiltration of contaminated ground water, may be
        repaired and reconditioned if  damage and potential health hazards'are limited.  Upon
        inspection and location of faulty sections, cleaning procedures,  followed, in more
        complicated instances, by pipe relining, can rehabilitate an effected system.  This work
  |j    may be done in place, withour costly excavation.
  1
7A2       Units of Measurement
Costs are  given in dollars per linear foot (LF) because if provides a simple and
standardized measure of water main lines.
   ;     7.3.3.      Sum max? Statistics
•                                                           .               '
        7.3.3.1     Expenditures
   |     No actual cost data was available at this time
 i                                                    •
 '  |    7.3.3.2     Estimates
        Cost estimates for water main repair ranged from:

 i  '               $26/LF       8" diameter
                      to
                   $35.50/LF    24" diameter
   3                                                  •
        Restoration of 24 inch diameter concrete tiipe was in the same range as smaller diameter-
 1'      iron pipe. Included in the cost per linear foor estimate was provision for preliminary T.V.
 '       inspection.
                                              -182-

-------
I
                                                               Sewer & Water Line Rehabilitation
                                                                Water Line Repair
7.3.4       Factors Found to Affect Costs

7.3.4.1     Expenditure
No actual cost data are available for water main repair.

7.3.4.2     Estimates
The following factors affected cost estimates for water main rapair:

     o     Pipe size
     o     Extent of da m age and conta mination
     o     Accessibility

Pipe size was the primary factor which directly affected the cost estimates for repair
(see Table 58).  Site specific factors such as accessibility of damaged sections and degree
of contamination and damage would  directly affect costs, but the cost estimate data
were inadequate to quantify these factors.

Estimates Sources
           O      JRB-RAM, 1980
|          o      Radian, la83

I
                                             -133-

-------
     fe
     8   -
     B   ?
ID
-    fi-
          ts
          CO


CO
o
cj
. u
1-1
e
a
<8
0
a
ft.

0)
a
H
0>



00
•H
CB
at
a
01
u
V
o
en
4.1
5
fa
o
fa fa «n
o o o
m .» m
Ox in ON
 a
u BO)
jp W O«
•H CJ i-(
Cu D.
1 -0
e e >M
l-i CO O

< e
CM a
U -H fO
•O 00
9 oe «H




s














-










*
. 1
                                          -184-

-------
                                                              Sewer ft Water Line Rehabilitation
                                                              Water Line Replacement
1
I
      7.4  WATER MAIN REPLACEMENT
7.4.1       Definition
Water  main replacement involves the excavation and removal of extensively damaged
and  contaminated  water pipe  sections  and bedding, sleeving  new sections with
Polvethelene sheet and relaying them. This Is followed by backfilling and compaction of
the trench. Preliminary investigation by inspection and analysis is required prior to the
replacement procedure.

7.4^       Units of Measurement
Costs  are  given in dollars per linear foot (LF)  because it provides a simple and
standardize measure of water lines.

7.4J       Sum mary Statistics

7.4.3.1     Expenditures
No actual cost data are available at this time.

7.4.3.2     Estimates
Water line replacement cost estimates ranged from:

           $ 58.50/LF          8" diameter
              to
           S119.18/LF         24" diameter

These  estimates  covered all basic pipe  replacement costs including preliminary
inspection procedures.  Costs were generally proportional to pipe size.
                                           -185-

-------
1
i
                                                               Sewer &  Water line Rehabilitation
                                                               Water Line Replacement
7.4.4       Factor Found to Affect Cost

7.4.4.1     Expenditures
No actual cost data are available for water line replacement.

7.4.4.2     Estimation
The following factors affected water Une replacement cost estimates (see Table 59):

           o  Pipe size
           o  Depth of excavation

Pipe size and depth  seemed to  be  most  directly related to  the cost  of  water line
replacement costs.  The cost of excavation, which is a major component of 'water line
replacement, was affected by the depth and size of the pipe.  The cost of the new pipe,
which is the major material  cost factor, was largely a function of the pipe size.  No
significant cost difference between iron and concrete pipe was shown by the limited
available data.

Estimates Sources
           O  JHB-RAM, 1980
           o  Radian, 1983
                                            -186-

-------
I

I

I:
fis
8
H
Z
       00
       m
             u    s
                   o
                   o

                   CM
                   00
i
4J
09
O
CJ
JJ
•H
B
•H
C^
01
N
t/J



a
•H
b
01
^
s


00
•H
m
01
Q
0)
U
Id
3
O
M
4
U
a
a


Ph f*. *J
*s f3 r1 7^
iJ *•». «•«. CO
•^ 00 00 i-l
co ON m •
• • • ON
o 1-1 in i-i
vo r* ON i-t
U U U U
B B B B

oo CM \o  «d
> • 01 .*
a i-i 01 u
u ca >H a
X > 08 4 6
0) O O
B 01 «« >% O.
u B £ a a
U -H 4J % o)
S-o IH a-o
*3 -8 ^ S
M 0 i, O. fl




Jg
<
<
Cu |
M O
as oo
en as ON
S "I iH
5 a a s
-•. *^. o
o o o o
in o o •

00 O PI iH
in r^ o« I-H
U U U U
B B B B

00 CM \O <•
iH iH CM
01
01
U
B B B U
O O O B
U Id V- o
M M M O
01 00
01 B B
6 0) -H. .
•H M X 1
M J: IH 5
3 « o> __
O X O. ^
. 0 0. •
S i.
0 - *
•H • 00 2 e
" ^ e 2 a
0 * ^ £ .2
fll •> ^ **
£.00)-^"
co 8 V i!
e aj «j to to
M 2 a ^ o,






< £
a. a

T3 00
en a ON
=> OS ^














"















-






(




r

















                                                -187-

-------
                                                               Alternative Water Supply
                                                               New Supply Wells
                             &0  ALTERNATIVE WATER SUPPLIES
      8,1 NEW WATER SUPPLY WELLS

      8.1.1       Definition
      New water wells usually Involve drilled rather than driven wells, and are cased with a pvc
      sleeve.  The cost of providing and operating a pump, and the cost of storage tanks may
      also be included in the operation.

      8.L2       Units of Measurement
      Costs are given In dollars per linear foot depth because it provides a standard unit for
      comparison within the water well industry.

      8.1*3       Sum mazy Data

      8.1.3.1     Expenditures
I     No expenditure data was available at this time.
                                                   *
I     8.1.3.2     Estimates
      The single cost estimate found for new well installation was:

      Capital:          $462/LF

      Operation and
      Maintenance:     $265/year

      The capital cost estimate covers labor, equipment and materials.  However, preliminary
      geologic investigation costs required for weU siting were not included.  The operation and
      m aintenance figure has been calculated for a well 200 feet deep.
                                            -188-

-------
f!
                                                                  Alternative Water Supply
                                                                  New Supply Wells
      8.1.4       Factors Found to Affect Costs

      8,1.4.1      Expenditures
      No data was available at this time.

i     8.1.4.2      Estimates
      Due to  the limitations of weU cost estimation data (see Table 59), no comparison of cost
|i     factors can be made.   As noted above, however, well depth arid diameter as well as
      hydrbgeologic site conditions are general determinants In total costs for weH installation.
I
      Estimates Sources
f     US EPA, OERR contractor Feasibility Studies.
                                            -189-

-------
1
E
                                      S1
                                     u
o
T4
JJ 0)1
a v

in
v£)
CM
evi
                                       60
                                       «H
                                       \eo
 H     I"
 0)     3
 *J     O.

 g     0.
 a  SO'-4
 •r*  e  .a
 •e  -^  IH
    a  to
 ^  a  u>
 o  u  u

 5  «!!
    >  3  00
 -»  a. a  m


0)
u
w
5
tn
a
4J
a
a

^*
n
u
a
rH
iH
O
a. a oo
It) ^ m rs
^O f*» O\
CO « ON ^H
p oe ^ ^





















•






                                                                  -190-

-------
                                                               Alternative Water Supply
                                                               Water Distribution
I
I
      &2  WATER DISTRIBUTION SYSTEM
           Deflnttioo:
Water distribution systems consist of network of pressurized pipes connecting individual
households with  existing  water sources such  as mains  or reservoirs and  municipal
hydrants to a common water source.   For this section  no source costs for wells or
reservoirs are assumed, only connection costs are given.
           Units of Measurement
Costs are given in dollars per household connected as this is a com mon factor in the
available data and allows an approximation of the numbers of people sewed by a new
water system.

&&3      Sum mazy Data

8.2,3.1     Expenditures  •
The range of expenditures was:
           $l,091/household
              to
           $10,714/household

The  costs  components of  the  higher expenditure include fire  hydrants  and  all
appurtenances; while the lower cost system did not include these costs,  operation and
maintenance costs, which may be significant, were not available.

8.2.3.2      Estimates
 No estimates data are available at this time.
                                            -191-

-------
                                                                         Alternative Water Supply
                                                                         Water Distribution
  1
  r
i
&2.4       Factors Found to Affect Costs

8.2.4.1      Expenditures

The following factors were found to affect the costs of new water distribution systems
(see Table 60):

            o Size (pipe length/diameter)
            o Inclusion of related costs

The  inclusion of related  costs was probably the  most important factor that affected
costs.  The higher cost system included design work and fire hydrants along all streets
connected.   The lower cost system  included only the  basic  domestic water  supply
connection construction costs.  The two systems shown vary somewhat in size, in terms
                                                                      ?
of both length and diameter.   The lower cost Minnesota  system connected houses that
were closer together than the California system. Also the California system was built to
allow for  connection  of more houses in the future, by using oversized mains  that
                                              *
exceeded present system  needs.   Operation  and maintenance costs,  which may be
significant, are not included. Also excluded is the fee usually charged by a municipality
for a connection.

8.2.4.2      Estimates
No estimates data are available at this time.
                                              -192-

-------
I
              8

              5   ~
        o    O    S
 F
        2
              I







JJ
0)
O
u
JJ
TH
e
p
4J
OB
5
^^
<-(
a
^
o
H
•C
0>
£
41
0)
09
^J
^4
e
9







^j
T*
09
01
O
a
u
I*
0
CO
«





0)
a
3
0
£
^J
P1^
cr.
o
*
iH
«>
O
O
o
CM
*-t
 i- «
§«° ai ca
4J X
a a
•o >


a
4J
03 O
< as w
O< ») 0)
u -^^ en c
0)
09
3
O

«»
*4
r*
*
C
iH
1
£f^
C*i
•»
l-H
•
r»
 «>
4J
a) a
w w
09 >Q
§ ^§
£ u
3) 09
00 trf >»
CM iH 09
14-1
e
o
v<
4J
U
^
4J V
09 1-
§«H
IW
U
OS oT 00
*-
U -i fS -H













-

























*
» •



















p










^

-
                                 
-------
                                 ANNOTATED REFERENCES
1
I
r
CH2  M  Hffl,  December 1982.   "Draft  Engineering  Services  Report/Quanta
Resources Clean-up" Reston, Va. For New York City Department of Environmental
Protection.   Invoices  and  dally logs were used to assemble  actual removal
expenditures.

ELI/JRB Environmental  Law  Institute, Washington, D.C.  and JRB  Associates,
McLean, Va. Case Studies of Remedial Responses at Hazardous Waste Sites. 1983.
Invoices, corresponddence,  reports  and vouchers  were used  as  part  of this
compilation of 23 case studies around the U.S.

JRB -  RAM,  1980.  These cost  estimates were drawn from  the "Manual for
Remedial Actions  at  Hazardous  Disposal Sites"  Draft final  report by  JRB
Associates, McLean, Va. June 20, 1980. This manual was subsequently published by
U.S. EPA as the "Manual for Remedial Actions at Hazardous Wastes Sites."  EPA
625/6-82-006.   Cincinnati,  Ohio, 1982, and again by Noyes Publishing Company,
Englewood Cliffs, New Jersey, 1983. The initial draft final report was used because
it contained the greatest cost detail.  These estimates were drawn principaHy from
construction estimation manuals such as (1)  the Means Manual (Godfrey, R.R. (Ed.),
1980,   Building Construction Cost Data 1980,  38th Annual Edition,  R.S. Means
Company, Inc.; (2) Dodge Manual (McMahon, L.; Pereira, P. (Ed.) 1979.  1980 Dodge
Guide to Public Works and  Heavy  Construction Costs.   McGraw-Hill Information
Systems Co.,  New York, N.Y.;  (3) Richardson Rapid  Construction Cost Estimaong
System  (Richardson Engineering Services,  1980); and supplemented with a large
number of price quotes drawn directly from industry  and commercial sources.
Hypothetical site scenarios are given for many of the technologies.
                                             .                    -
Radian,  1983.  These estimates are drawn from the last section of  "Evaluating
Cost-effectiveness of Remedial Actions at  Uncontrolled  Hazardous Waste Sites" -
                                                                      «
Draft Methodology  Manual by the Radian Corporation, Austin, Texas, January 10,
1983.  These  estimates were indexed to constant dollars  for March 1982.  Many of
the  estimates were derived  from  EPA*s  "Handbook   for Remedial  Action  at
Hazardous  Waste Sites."  EPA  625/6-82-006.  Cincinnati, Ohio, 1982.  This source
                                           -194-

-------
i
r
was always supplemented or supplanted by many other estimation sources, including
specialized papers for specific technologies, and  general construction estimating
manuals.                                                              . '.

SCS  (Engineers), 1980.   These cost estimates came  from "Costs of  Remedial
Response  Action at Uncontrolled Hazardous Waste Sites" by SCS Engineers, Long
Beach California, April 1981.  According to this methodology:  "For the  most part
the 1980  Means (Godfrey,  R.  (Ed.) 1979.   Building construction cost data: 1980.
Robert Snow Means Company, Inc. Kingston, MA. and Dodge Guides McMahon, L.,
Pereira, P. (Ed.) 1979.  1980 Dodge Guide to Public Works and Heavy Construction
Costs.; McGraw-Hill Information Systems Co. New York, N.Y. were used to obtain
tiie costs needed."

SCS  (Engineers), 1981. These cost estimates are derived from Cost Comparison of
Treatment and Disposal  Alternatives for Hazardous Materials  (EPA - 600/52-80-
188) published in February  1981 by the US EPA Municipal Environmental Research
Laboratory.  The estimate compilation was performed by SCS Engineers for a
greater Chicago area scenario using the 1978 Means  Construction Cost  Manual.
Hence, mid-1978 costs were originally estimated.  For comparison purposes these
cost estimates were converted  from simple average costs, and the raw data on
capital and operation and maintenance costs were used in stead.
           US EPA, OERR contractor RIA^T  Losing Mri«i for Superfund work are used here as
           estimated costs since they did not serve as the basis for  actual construction.
           However, these estimates  reflects a higher jsvel of  detail than  -nanv other
           estimates since specific  local capabilities are considered.    Most of the  cost
           estimates are from 1982 and 1983 estimates.

           US EPA, OERR contractor Feasibility Studies.   Cost estimates from feasibility
           studies are  generally drawn from norv-bid estimates from contractors.  Most of
           these cost estimates are trora 1982 and 1983.
                                                                                 «
           US EPA, OERR State and Federal Superfund Work. Records from initial Superfund
           wont,  such as bid  and change order reports, anct spread sneet printouts.  4H  sites
           are numbered for anonymity, but state locations are given because of its relevance
           to cost factors such as labor and materials, and site characteristics such as climate.
                                            -195-

-------