605  )j6
'
                     906R85102
           SUPERFUND REMEDIAL DESIGN AND

             REMEDIAL  ACTION  GUIDANCE
                  February 1985
          Hazardous  Site Control Division
     Office of Emergency and Remedial  Response
       U.S. Environmental  Protection Agency
               Washington, DC  20460

-------

-------
                      TABLE   OF.  CONTENTS
                                                                     Page
                                                                    Number
1.   INTRODUCTION

     1.1   Purpose of the Guidance Document                          1-1
     1.2   Overview of the Guidance Document                         1-1

2.   REMEDIAL DESIGN                                                 2-1

     2.1   Architect/Engineer Selection Activities                   2-1

          --2-r-W-  Federal Lead Remedial Design                       2-1
           2.1.2  State Lead Remedial Design                         2-4

     2.2   Design Initiation                                         2-5

           2.2.1  Remedial Planning Information                      2-5
                  Provided to Lead Design Party

                  2.2.1.1  Record of Decision/Enforcement            2-5
                           Decision Document and Final Remedial
                           Investigation/Feasibility Study Report

                  2.2.1.2  Pre-Design Report                         2-6

                  2.2.1.3  Technical  Transfer Briefing               2-6

-------
       2.2.2   Type  of  Agreement                                   2-6

              2.2.2.1   Federal Lead Remedial  Design              2-6
              2.2.2.2   State lead Remedial  Design                2-9
              2.2.2.3   Responsible Party Remedial Design         2-9

       2.2.3   Architect/Engineer Conflict of  Interest           2-12

 2.3   Elements  To  Be  Included In Statement of Work (SOU)        2-12

       2.3.1   Plans and Specifications                          2-12
       2.3.2   Additional Studies                                2-14
       2.3.3   Operations and Maintenance Plan                   2-15
       2.3.4   Quality  Assurance  Project Plan                     2-15
       2.3.5   Site  Safety Plan                                   2-15
       2.3.6   Architect/Engineer Services During Construction   2-16

J^.4   Design  Reviews  and Approvals                             2-16

       2.4.1   Preliminary Design                                2-17

              2.4.1.1   Environmental Review                     2-17
              2.4.1.2   Technical Review                         2-18

       2.4.2   Intermediate Design                               2-18

       2.4.3   Prefinal Design                 .                  2-18

              2.4.3.1   Environmental Review                     2-18
              2.4.3.2   Technical Review                         2-19

       2.4.4   Final Design                                      2-19

              2.4.4.1   Extent of Review                         2-19
              2.4.4.2   Final Approval                           2-20
              2.4.4.3   Plan-In Hand Review                       2-20
                                 ii

-------
I
I
      2.4.5  Major Design Changes                              2-20
      2.4.6  Value Engineering                                 2-21

2.5   Permits, Approvals and Site Access                       2-21

      2.5.1  Permits and Approvals                             2-22

             2.5.1.1  Requirements                             2-22
             2.5.1.2  Responsibilities                         2-22

      2.5.2  Site Access                                       2-23

             2.5.2.1  Requirements                             2-23
             2.5.2.2  Responsibilities                         2-24

2.6   Community Relations Activities                           2-24
I                   2.6.1   Objectives                                        2-25
                    2.6.2   Implementation Activities and Techniques          2-25
I                   2.6.3   Responsibilities                                  2-26

I             2.7   Cost Estimates for Construction                          2-26

|                   2.7.1   Estimated Cost of Project                         2-27

•                   2.7.2   Supervision and Administration (S&A)  and          2-27
                           Engineering and Design (E&D)  During Construction

                    2.7.3   Contingency Limits                                2-27

                           2.7.3.1  Bid Contingency                          2-28
                           2.7.3.2  Changes Orders  and Claims                 2-28
4
                    2.7.4   Total  Cost Estimate for  Remedial  Action            2-28
                           Agreements
                                             iii

-------
3.   REMEDIAL ACTION                                                 3-1

     3.1   Remedial Action Initiation                                3-1

           3.1.1  Federal Lead Remedial Action                       3-1
           3.1.2  State Lead Remedial Action                         3-1
           3.1.3  Responsible Party Remedial Action                  3-4
           3.1.4  Conflict of Interest                               3-4

     3.2   Procurement Activities                                    3-4

           3.2.1  Advertise for Bids                                 3-4
           3.2.2  Site Inspection      '                              3-6
           3.2.3  Review of Bid Documents                            3-6
           3.2.4  Bid Protests                                       3-7

     3.3   Monitoring and Oversight                                  3-7

           3.3.1  Inspections                                        3-7

                  3.3.1.1  Full Time Inspector                       3-7

                  3.3.1.2  Compliance with Environmental             3-8
                           Requirements

                  3.3.1.3  Compliance with Other Contract            3-8
                           Requirements

                  3.3.1.4  Review of Contractor Reports              3-8

           3.3.2  Progress Reports to EPA                            3-9

           3.3.3  Contingency Fund for Change Orders  and Claims     3-10

                  3.3.3.1  Federal Lead Remedial Action             3-10
                  3.3.3.2  State Lead Remedial Action               3-10

                                     iv

-------
3.4   Final Inspection and Closeout                            3-11

      3.4.1  Prefinal Construction Conference             .     3-11

             3.4.1.1  Participating Parties                    3-11
             3.4.1.2  Suggested Agenda Items                   3-12

      3.4.2  Prefinal Inspection                               3-12

             3.4.2.1  Inspecting Parties                       3-12
             3.4.2.2  Extent of Inspection                     3-12
             3.4.2.3  Prefinal Inspection 'Report               3-13

      3.4.3  Final Inspection and Certification                3-13

             3.4.3.1  Inspecting Parties                       3-13
             3.4.3.2  Extent .of Inspection                     3-13
             3.4.3.3  Final Inspection/Certification Report    3-14

      3.4.4  Acceptance of Completed Project and Beneficial    3-14
             Occupancy

      3.4.5  Operation and Maintenance Assumption              3-14

      3.4.6  Site Closeout ana Post Mortems                    3-15

             3.4.6.1  Final Technical Report                   3-15
             3.4.6.2  Deletion of Site from NPL                3-16

-------
Appendix A - Sample USAGE Work Assignments and  Interagency            A-l
             Agreements

Appendix B - Elements to be Included  in the Remedial  Design           B-l
             Statement of Work

Appendix C - List of Acronyms                                         C-l

Appendix D • Glossary of Terms                                        D-l

REFERENCES
                                      vi

-------
                      INDEX   OF   EXHIBITS
                                                                      Page
                                                                    .Number
EXHIBIT
NUMBER                     TITLE

 1-1       Remedial Process                                           1-2

 2-1       Federal Lead Remedial Design Process                       2-2

 2-2       USAGE Regional Assignments for Superfund Projects          2-3

 2-3       Suggested Outline for Pre-Design Report                    2-7

 2-4       State Lead Remedial Design Process                       2-10

 2-5       Responsible Party Lead Remedial Design Process           2-11

 3-1       Federal Lead Remedial Action Process                       3-2

 3-2       State Lead Remedial Action Process                         3-3

 3-3       Responsible Party Lead Remedial Action Process             3-5

 B-l       Basic Elements of Operation and Maintenance Plan           B-6

 B-Z       Suggested Outline for Site Safety Plan                   3-11
                                     uii

-------
* .-'  V .
1.  INTRODUCTION

-------

-------
                              1.  INTRODUCTION
1.1  Purpose of the Guidance Document

     This guidance document has been developed to assist agencies and
parties who plan, administer, and manage remedial design (RD) and remedial
action (RA) at Superfund sites.  The guidance document pertains to
Fund-financed RD/RA (i.e., Federal lead and State lead) and responsible
party RD/RA, and provides procedural guidance to be followed in order .to
ensure that RD/RA is performed properly, consistently, and expeditiously.

     The guidance document has been developed primarily for use by:

           Environmental Protection Agency Remedial Project Managers (EPA
           RPM)                                   	'

           State Project Officers

           U.S. Army Corps of Engineers (USACE) personnel

           Responsible parties.

Exhibit 1-1 highlights the focus of the document within the context and
sequence of activities required to complete an entire remedial response.

1.2  Overview of the Guidance Document

     This guidance document has been organized to reflect the general
sequence of events that occurs prior to, during, and after -emedial design
and "emedial action at a Superfund site.  Remedial design activities are
presented in Chapter 2, and remedial action activities are presented in
                                     1-1

-------
                                  EXHIBIT 1-1
                              REMEDIAL PROCESS
 MK9VCRV
   MO
Mvtsnunoi
  REMEDIAL

MPUMHTinON
                                                  SUBJECT OF
                                                RDfRA GUIDANCE




CHT
•cswin
icnti

                                         o
                                    1-2

-------
 I
 I
 i
 I
,1
 I
 I
 i
 I
Chapter 3.  The majority of both chapters pertains to Fund-financed and
responsible party projects, however, some sections apply only to
Fund-financed projects and are noted accordingly.  Common information is
consolidated for discussion, and where necessary separate subsections are
provided for Federal lead, State lead, and responsible party RD/RA.
Additional guidance on oversight of responsible party RD/RA activities will
be provided by EPA in the future.

     The discussion on responsible party RD/RA pertains only to those
Superfund sites where EPA has entered into a settlement agreement with the
responsible party(ies), and no trust fund monies are involved in the RD/RA.
If trust fund monies are involved, different procedures to be followed will
be  provided in the future by EPA.

     RD/RA conducted by other Federal agencies is not addressed directly in
this document.  The forthcoming Federal Facilities Program Manual will
tailor the information in this document to address Federal Agency RD/RA
activities.                '                                      -
                                              1-3

-------
                 •**•••
2.  REMEDIAL DESIGN

-------
*.'••"*,*"'•'   •-«"'-  <•'•?..-  ~   •"
   •  •••• J~  •,:•    ..... y.v. or.   -_V
    »

•I
•
    1

-------
                             2.  REMEDIAL DESIGN
2.1.  Architect/Engineer Selection Activities

       Activities Involved in selecting an architect/engineer  (A/E) firm for
remedial design will be dependent on the lead party.  A/E selection
activities pertaining to Fund-financed remedial design are discussed below.

2.1.1  Federal Lead Remedial Design
    \
       Exhibit 2-1 diagrams the Federal lead remedial design process.   In
order to expedite the design phase, A/E selection activities may be
initiated prior to Record-of-Decision (ROD) approval if deemed appropriate
by the EPA RPM and EPA headquarters (HQ).  The EPA Regional office will
issue a work assignment consistent with the standing Interagency Agreement
(IAG) to USAGE Missouri River Division (MRD) to initiate Phase I design
activities based on the draft feasibility study (FS).  The EPA RPM will
forward copies of the executed work'assignment to EPA HQ and USAGE HQ.

       The map in Exhibit 2-2 shows the USAGE Regional assignments for
Superfund Projects.  Under MRD supervision, the appropriate USAGE Design
District (i.e. Kansas City or Omaha) will perform the following Phase I
design activities to retain an A/E firm for the engineering design:

             Synopsize requirements in Commerce Business Daily (CBD)

             Develop A/E pre-selection list

             Contact A/E firms on the pre-selection list to ascertain
             interest in project
                                     2-1

-------
                                                       EXHIBIT 2-1
                                      FEDERAL LEAD REMEDIAL DESIGN PROCESS
                       COPIES TO
                        EN HO
                       USAGE HO
1
ACTIVITIES PRIOR TO
  ROD APPROVAL
 ARE OPTIONAL IN
ORDER TO EXPEDITE
 DESIGN INITIATION
EPA HEGION ISSUES
WA FOR INITIATING
Miiet i DKIRII
ACTIVITIES TO
USAGE MUD
1
EM RPM ft STATE
PROCESS STATE LETTER
Of REQUEST OR
AMEND EXISTING MOU




USACE-MRD |
DESIGN DISTRICT 1

•SVNOPSKE REOMTS. IN CBO
•DEVELOP Art PRESELECTION LIST
•CONTACT A/E FMMS TO ASCERTAIN INTEREST
•DEVELOP AIE SELECTION LIST MIN. 3 FIRMS)
^SELECT AC FMM (TENTATIVELY}
               EPA REGION PREPARES
                DRAFT SITE SPECIFIC
              DESIGN IAG CONCURRENT
                 WITH EPA REGION
               SUBMITTING FINAL ROD
               PACKAGE FOR APPROVAL
                                          SELECTION OF REMEDY BY EPA
                                                 ROD APPROVAL
           COPIES TO
             EPA HO
           USAGE HO
                H
  EPA REGION t
USAGE MUD FINALIZE
    DESIGN IAG
                                      J.
                                  USAGE-MRO
                                •rruns DESIGN
                                 AcnvrmsTww
                                 DESIGN OBTRET
                                                                      I	
REMEDIAL PLANNING
   INFORMATION
   PROVIDED TO
  USAGE MHO BY
     EPA RPM
                                                DESIGN DISTRICT
                                                BSUES SOW FOR
                                               DESIGN TO AIE FMM
    ACRONYMS KEY

    VM       KMOuu. rautrr MAUOH
    KUCt-MO   IU MMT dim OF {KMEHB -
               •UOMI mm omsn*
    IM       HTHMEKT ACKEMEIT
    MO       KOTO OF Of OSIOII
    SOW       niTtMHT OF WORK
    N*       *OM USKMEI7
    CIO       COMHRa WSWfSS DAILY
    Ml       UTNMAt MBOWTHS IIST
    «U       HBHMUiOUM OF iGVf Mf IT
                                            AIE FNtM DEVELOPS
                                             DESIGN PACKAGE
                                             BASED ON SOW
                                        DESIGN REVIEWS SCHEDULED
                                            AT PRE DETERMINED
                                        INTERVALS (I.E., PRELIMINARY.
                                        INTERMEDIATE. PREFIN Al. FINAL!
                                       DVERSffiMT BY EPA RPM
                                             USAGE MRD APPROVES AND
                                              ACCEPTS DESIGN WITH
                                             CONCURRENCE FROM EPA
                                                REGION AND STATE
                                                                 2-2

-------
 I
 I
I
I
I
I
I
I
I
I
             |
i ta
 55

-------
Appendix P of the manual for State Participation 1n the Superfund Remedial
Program (State Manual) for specific information and procedures
(Reference 1).  To be consistent with EPA policy, attention should be given
to the utilization of minority business enterprises and women's business
enterprises.

2.2  Design Initiation

       Following selection of a remedy and Record of Decision
(ROD)/Enforcement Decision Document (EDD) approval by the designated EPA
official, action must be taken to initiate design activities.  The lead
design party shall ensure the design package is developed consistent with
the approved ROD/EDD and applicable CERCLA policy and procedures.  Remedial
planning information to be provided to the lead design party and the type of
agreement used to initiate design are discussed below.

2.2.1  Remedial Planning Information Provided to Lead
       Design Party                                               .

       When the lead design party is different than the lead RI/FS party,
the EPA RPM must provide remedial planning information to the appropriate
design party (i.e. USAGE, State, responsible party) in order to initiate
design.  If the lead party does not change from RI/FS to RD, this is not
required since the lead party should already have the information.

2.2.1.1  Record of Decision/Enforcement Decision Document
         and Final Remedial Investigation/Feasibility Study
         (RI/FS) Report

       Mandatory information to be provided to the lead design party
includes a copy of the approved ROD/EDD and the final RI/FS report(s)..  This
information should be forwarded as soon as possible after ROD/EDD approval
in order to. facilitate initial design activities.
                                     2-5

-------
2.2.1.2  Pre-Des1gn Report

       A Pre-Design Report  shall be  prepared  by the  lead  RI/FS party and
provided to the  lead  design party.   The  objective  of the  Pre-Design  Report
1s to describe the engineering parameters  and Institutional  concerns of the
selected remedy,  and  package all pertinent project Information for
effectively transferring the project to  the lead design party.  The
Pre-Design Report replaces  the conceptual  design task of  the FS.   The
Pre-Design Report should be completed within  2 weeks following remedy
selection, and the cost should be limited  to  approximately 5 percent of the
cost of the feasibilty study.  A suggested outline for the Pre-Design Report
is presented  in  Exhibit 2-3.

2.2.1.3  Technical Transfer Briefing

       The EPA RPM should schedule a technical transfer briefing between
lead design party and the lead RI/FS party.   The purpose  of  this briefing
would be to facilitate project transfer  and resolve  any outstanding  issues
or questions.

2.2.2  Type of Agreement

       The type  of agreement  used to initiate design  is dependent  on  the
party that is responsible for design.  For Federal lead remedial design,
action is initiated through an Interagency Agreement  (IAG) with the  USAGE.
For State lead remedial design, action 1s  initiated  through  a  cooperative
agreement (CA) with the State.  For  responsible party remedial design,
action is initiated  through  a document  of settlement with the responsible
.party(ies) (i.e.  judicial consent decree or administrative order on  consent).

2.2.2.1  Federal  Lead Remedial Design

       To initiate design at  a Federal lead site,  the EPA RPM  works  with the
State to process  a new State Letter  of Request or  amends the existing MOU to
include the remedial design  if remedial design was not covered in  the
                                     2-6

-------
                                 EXHIBIT 2-3
                   SUGGESTED OUTLINE FOR PRE-DESIGN REPORT
1.  Site Description

2.  Summary of Selected Remedy

         Description of remedy & rationale for selection
         Performance Expectations
         Site topographic map & preliminary layouts
         Preliminary design criteria & rationale
         Preliminary process diagrams
         General operation and maintenance requirements
         Long-term monitoring requirements

3.  Summary of Remedial Investigation and Impact on Selected Remedy

         Field studies
         (Air, surface water, ground water, geology)

         Laboratory studies
         (Bench scale, Pilot scale)

4.  Design/Implementation Precautions

         Special technical proolems
         Additional engineering data required
         Permits & regulatory requirements
         Access, easements, rights-of-way
         Health & safety requirements
         Community relations activities
                                     2-7

-------
                           EXHIBIT 2-3 (CONTINUED)
                   SUGGESTED OUTLINE FOR PRE-OESIGN REPORT
5.  Cost Estimates & Schedules


         Implementation cost estimate  (Order of Magnitude, +  50%/-  30%)


         Preliminary annual O&M cost estimate and duration


         Project schedule (design, construction, permits & access)


6.  Appendices


         Reports, data summaries, etc.
                                     2-8

-------
 original  MOU.   The RPM and the State officials should refer to Chapter VIII
 of the State Manual for specific Information.

        Once the State Letter or MOU 1s processed,  the RPM shall  coordinate
 with USACE-MRD and establish necessary funding for design.  The EPA Region
 should prepare a draft site-specific design IA6 with USACE-MRD,  concurrent
 with submitting the final  ROD package for approval.   After ROD approval,  the
 EPA Region should finalize the design IA6 with USACE-MRO.  The RPM should
 forward copies of the executed design IAG to EPA HQ and USACE-HQ (DAEN
 ECE-B).  USACE-MRD will initiate design activities through the appropriate
 Design District.  The RPM will monitor all design  activities.   The design
 process is outlined in Exhibit 2-1.  A sample (sample No. 2) site-specific
 design IAG is  Included in  Appendix A.

 2.2.2.2  State Lead Remedial Design

        To Initiate design  at a State lead site, the RPM works  with the State
 either to amend the existing CA or to develop a new CA for RD, or for both
 RD and RA.  The RPM and State should refer to Chapters III amd VIII of the
 State Manual for specific  information and procedures.  Exhibit 2-4
 graphically depicts the State lead remedial design process.

 2.2.2-2  Responsible Party Remedial Design

        To initiate design  for a responsible party  clean-up, EPA enters into
 a settlement agreement (consent decree or administrative order on consent)
 with the responsible party(ies).  The responsible  parties will then proceed
 ahead with the selection of a support contractor as needed to  complete the
 design, according to the schedule and conditions set forth in  the document
 of settlement.  The process for responsible party  lead is shown in Exhibit
'2-5.  This discussion pertains only to settlement  agreements where no trust
 fund monies are involved.   EPA will provide additional guidance on
 responsible party oversight in the future.
                                      2-9

-------
                                          EXHIBIT 2-4
                             STATE LEAD REMEDIAL DESIGN PROCESS
                                                                                                  I
                                        STATE AND EPA-RPM
                                         PREPARE/AMEND
                                       DRAFT CA CONCURRENT
                                         WITH SUBMITTING
                                        FINAL ROD PACKAGE
                                           TO EPA HO
                                       SELECTION OF REMEDY
                                          ROD APPROVAL
                       STATE AND
                        EPARPM
                       FINALIZE CA
                                                     REMEDIAL PLANNING
                                                    •FORMATION PROVIDED
                                                       TO STATE (ONLY
                                                    REQUIRED IF STATE WAS
                                                    NOT LEAD RUFS PARTY)
                                        STATE ISSUES SOW
                                      FOR DESIGN TO AIE FIRM
ACRONYMS KEY
                                              I
                                        AIE FIRM DEVELOPS
                                         DESIGN PACKAGE
                                         BASED ON SOW
SOW
•A
KMEMAL PROJECT MAUSER
man OF KOMI
ttmmu nnffmemimi
 KASMJTY STUDY
STATHKIT OF WOM
                                    DESIGN REVIEWS SCHEDULED
                                    AT INTERVALS (PRELIMINARY.
                                      •TEMEDIATE. PREFINAL.
                                             RIAL)
OVERSIGHT BY EPA RPM
                                        1
                                         STATE APPROVES
                                     AND ACCEPTS DESIGN WfTH
                                     CONCURRENCE FROM EPA
                                              2-10

-------
                              EXHIBIT 2-5
          RESPONSIBLE PARTY LEAD REMEDIAL DESIGN PROCESS
                                          SELECTION OF
                                            REMEDY
                                          EDO APPROVAL
                                         EPA ENTERS INTO
                                      SETTLEMENT AGREEMENT
                                        WITH RESPONSIBLE
                                             PARTY
                                               1
                                        REMEDIAL PLANNING
                                      •FORMATION PROVIDED
                                         TO RESPONSIBLE
                                             PARTY
                                        RESPONSIBLE PARTY
                                         ISSUES SOW FOR
                                        DESIGN TO A/E FIRM
                         OVERSIGHT BY EPA RPM
                                               I
                                        A/E FIRM DEVELOPS
                                         DESIGN PACKAGE
                                          BASED ON SOW
                                               I
                                     DESIGN REVIEWS SCHEDULED
                                     AT INTERVALS (PRELIMINARY.
                                      INTERMEDIATE. PREFINAL.
                                              FINAL)
                         OVERSIGHT BY EPA RPM
ACRONYMS KEY

EDO    EVONCEMEMT DEOSMM DOCUMENT
SOW   STATEMEIIT OF WWW
   RESPONSIBLE PARTY
       APPROVES
AND ACCEPTS DESIGN WITH
 CONCURRENCE FROM EPA

-------
 2.2.3  Architect/Engineer Conflict of Interest

        In the process of selecting an A/E firm for Fund-financed remedial
 design, the State or EPA shall evaluate whether the prospective A/E has a
 potential conflict of Interest based on any potentially responsible party
 (PRP) Involvement at the site.  This could include the situation where a
 current client may be a PRP at the site.  The EPA-Region should include a
 provision in all CAs and lAGs regarding contracts with PRPs.  Appendix F of
 the State Manual suggests specific,language to be included in a CA provision
 and suggests specific clauses to be included by the State in any contract
 for services or construction.  lAGs should contain a provision consistent
 with Appendix F, stating the USAGE will require interested contractors to
 provide information and EPA will evaluate potential conflicts.  The USAGE
 should include a provision equivalent to Appendix F in the contract for RD.

 2.3  Elements To Be Included In Statement Of Work (SOW)

        It is essential that the A/E firm retained to accomplish the design
-for a specific remedial action have a clear understanding of the project
 scope and subsequent required design documents.  The following elements of a
 statement of work are intended as guidance in preparing site-specific A/E
 instructions and apply to Fund-financed and responsible party remedial
 design (RD).  The design Project Officer (PO) shall ensure that the
 appropriate elements are addressed.   Further requirements for preparing the
 A/E statement of work are presented in Appendix B.

 2.3.1  Plans and Specifications

        The SOW for remedial design should require the A/E to prepare the
 final construction plans and specifications to accomplish the remedial
 action alternative as defined in the Record of Decision/Enforcement Decisiorf
 Document (ROD/EDO).   The specifications should include quality assurance
 provisions in all  proposed work.  It should also state that the A/E snail
 conduct the analysis and perform all work as requirea to prepare the
                                     2-12

-------
document package required for the remedial action.  (For further detail see
Appendix B).  In general, the plans and specifications portion of the SOW
should Include the following phases:

             Preliminary Design - The Scope of the preliminary design should
             address not less than 30% of the total design and shall be
             based on data furnished for the project.

             Intermediate Design - Complex project designs may necessitate
             review of the design documents between the preliminary and
             prefinal/final design phases.  At the discretion of the design
             PO a design review may be required at 60X completion of the
             design.

             Prefinal/Final Design - Prefinal/final design documents shall
             be submitted in two parts.  The first submission shall be at
             95X completion of design (i.e., prefinal).  After approval of
             the prefinal submission, the A/E shall execute the required
             revisions and submit the final documents 100X complete with the
             reproducible drawings and specifications ready for bid
             advertisement.  This portion of the document package as
             submitted for prefinal/final design shall include, but not be
             limited to the design analysis, final construction drawings and
             specifications and cost estimate.

             Correlating Plans and Specifications - The coordination between
             drawings and technical specifications is a principal
             requirement of the A/E contract.  The coordination shall be
             consistent with the submission requirements of the drawings and
             specifications through prefinal/final design.

             Selection of Qffsite Resource Conservation and Recovery Act
             (RCRA) Facilities - The A/E shall ansure compliance *nth CERCLA
             procedures for selecting an offsite RCRA facility and the
             requirements specified in the ROD/EDO.  Refer to reference 3
                                    2-13

-------
             for additional Information.  (Additional requirements are
             forthcoming to address RCRA landfills, focusing on the effects
             of the RCRA reauthorization.)

         .   Compliance with the Requirements of other Environmental Laws -
             The A/E shall ensure that the design package submitted Is in
             accordance with CERCLA procedures on compliance with other
             environmental laws.  Refer to reference 2 for additional
             information.  AH applicable or relevant standards and criteria
             identified in the ROD/EDO shall be analyzed and incorporated
             Into the design by the A/E.  The A/E shall identify the
             controlling parameters as required by such standards.

             Equipment startup and Operator Training - The AE shall prepare,
             and include in the technical specifications governing treatment
             systems, contractor requirements for providing:  appropriate
             service visits by experienced personnel to supervise the
             Installation, adjustment, startup and operation of the
             treatment systems, and appropriate operational procedures
             training once the startup has been successfully accomplished.

2.3.2  Additional Studies

       Remedial actions involving the on-site treatment or disposal of
contaminated wastes (i.e., groundwater, lagoon wastes, etc.) may require
additional studies to supplement the technical data available from the RI/FS
activities so that the optimum treatment or disposal methods may be
determined.  Additional studies- could include field work and/or bench and
pilot scale studies.  For futher detail see Appendix B.  The quality
assurance project plan and site safety plan from the RI/FS should be
tailored for any studies, as required.

       The fact that such studies will be performed should be explicitly
addressed in the ROD, and if necessary, the ROD should authorize the Region
to make any necessary choice among treatment or disposal options.
                                    2-14

-------
  2.3.3  Operation and Maintenance Plan

         In most Instances, remedial activities will result  1n  the  requirement
  of a varying degree of operational and maintenance (O&M) activity associated
  with the completion of a project.  The RI/FS and ROD will  Indicate the  types
  of O&M activities required and provide a cost estimate.  The  RD will  provide
  more detail on the specifics and degree of O&M activities  required,  and
  provide a more accurate cost estimate.  To ensure correlation of  the
  separate but related phases of design and O&M, the A/E shall  submit  an
  Initial draft O&M plan simultaneously with the prefinal design document
  submission and the final draft O&M plan with the final design documents.
-. For guidance on developing a comprehensive O&M plan see Appendix  B.   The  O&M
  plan will be finalized and submitted by the A/E or construction contractor
  at the prefinal construction conference.

 ' 2.3.4  Quality Assurance Project Plan

         A site-specific Quality Assurance Project Plan (QAPP)  shall  be
  prepared by the A/E, 1f the project will Involve any sampling or  monitoring
  activities.  The plan will provide guidelines for project  organization  which
  shall outline and Identify quality-control (QC) and quality assurance (QA)
  responsibilities of the construction contractor, lead design  party,  or  other
  applicable agencies during construction.  The QAPP should  be  consistent with
  EPA QA/QC Procedures.  The A/E shall submit a draft QAPP simultaneously with
  the prefinal design documents and the final QAPP with the  final design
  documents submission.  For guidance on the development and applicability  of
  the QAPP see Appendix B.

  2.3.5  Site Safety Plan

         An important aspect of a remedial action project, during both design
  and construction, is the health and safety of the individuals who will  be on
  site and that of the surrounding communities.  The A/E shall  develop,  in
  response to site specific data, specifications to be used  by  the
  Construction Contractor in developing a Site Safety Plan (SSP) that  is
  sufficient to protect on-site personnel and surrounding communities  from  the

                                      2-15

-------
physical, chemical, and/or biological hazards  of  the  site.   The A/E shall
submit draft specifications with the prefinal  design  document  submission  and
the final specifications with the final design documents.   For guidance on
development and compliance requirements of the SSP see  Appendix B.

2.3.6  Architect/Engineer Services During Construction

       The party responsible for accomplishing a  remedial action may deem It
desirable or mandatory that the A/E preparing  the final design package
assume an active role in the on-site remedial  action  (construction)  work.
The use of A/E services during construction 1s encouraged in the following
areas:

             Review construction contractor submittals

             Attend conferences and visit project site

             Provide field representative.

For further information and guidance on possible  services provided by the
A/E within these areas see Appendix B.

2.4  Design Reviews and Approvals

       The concept for a Superfund remedial project is determined when EPA
selects a cleanup alternative based upon the feasibility study  and
supporting documents, and as specified in the  ROD or EDO.  Once  an A/E firm
is contracted to perform the design work necessary to implement  the  selected
remedy, the Government reviewing agencies are  responsible for the review,
approval  and acceptance of the final plans and specifications.   Interim
outputs as well as the final product of the A/E must be reviewed to ensure
that the design is progressing in a manner consistent with the ROD/EDO ana
existing environmental ana construction standards.  The Government design
review and approval responsibilities for all  reviews are dependent on the
                                    2-16

-------
         lead design party and are listed below.  For responsible party RD, the
         responsible party has the primary responsibility for design review and for
         submitting the design documents to EPA for government review.
              RD Lead
I
I
f
I
I
I
r
i
         Federal
         State
                   Government Review
                     Responsibility
                     USAGE
                     State
Responsible Party    EPA
2.4.1  Preliminary Design
Environmental
   Review
 Assistance
EPA and State
EPA


State
Technical
  Review
Assistance
USAGE or EPA
Contractors upon
request
USAGE or EPA
Contractors upon
request
       The preliminary design shall be submitted by the A/E when the design
effort is approximately 30% complete.  The submittal should consist of the
plans and specifications previously described in Section 2.3.1.  If bench
and pilot studies were required, the interim report should be included with
the submittal.  For responsible party RD, the preliminary cost estimate will
be submitted at the discretion of the responsible party.  The preliminary
review is Important to correct or modify any problems areas before extensive
design is completed.

2.4.1.1  Environmental Review

       The preliminary design submittal shall be reviewed from an
environmental quality standpoint for Fund-financed and responsible party RD,
to ensure that all the necessary elements are included in the specifications
to address full compliance with requirements of the applicable or relevant
environmental and public health standards *hich are identified in the
ROD/EDO (refer to reference 2).

-------
2.4.1.2  Technical Review

       The preliminary design shall be reviewed from a technical standpoint '
for compliance with the SOW (refer to Section B.I.I), constructability, and
accuracy of the cost estimate.

2.4.2  Intermediate Design

       At the discretion of the design PO, the intermediate design shall be
submitted for review when the design is approximately 60% complete. The
submittal shall consist of the plans and specifications described in Section
2.3.1.

2.4.3  Prefinal Design

       The prefinal design submittal shall occur when the design is
approximately 95X complete and shall consist of the plans and
specifications, O&M plan, QAPP, and specifications for SSP previously
described in Sections 2.3.1 and, 2.3.3 - 2.3.5.  The Government agencies'
major review should occur at this time.  For responsible party RD, the cost
estimate will be submitted at the design PO's discretion.

2.4.3.1  Environmental Review

       The prefinal design submittal shall be reviewed for:

             Compliance with all applicable or relevant environmental and
             public health standards identified in the ROD/EDD

       . '    Utilization of currently accepted environmental control
             measures and technology

             The adequacy of the O&M plan, QAPP, and SSP specifications

             Consistency with ROD/EDD, and environmental and public impacts.
                                    2-18

-------
 2.4.3.2   Technical  Review

       The prefinal design  submlttal  shall  be reviewed to ensure:

              The bldability and constructability of the design

              The accuracy of the construction cost estimate

              Utilization of currently accepted construction practices and
              techniques
                       /
              The ability of a construction  contractor to submit a fair and
              reasonable bid based upon the  bid schedule included in the
              specifications
»
              The accuracy of any estimated  quantities of materials specified
              in the design

              That the responsibilities and  liabilities of the construction
              contractor and the government  are clearly defined and detailed
              in the design  documents  (fund  financed only).

 2.4.4 Final  Design

       The final design submittal shall consist of the final design plans
 and specifications (100X complete), the A/E firm's final construction cost
 estimate, the final draft 0&.M Plan, final QAPP and SSP specifications.  The
 quality  of the design documents should be such that the government or
 •responsible party is able to include  them in a bid package and invite
 contractors to submit bids  for the construction project.

 2.4.4.1   Extent of Review

       The appropriate agencies from Secton 2.4 shall review this submittal,
 to ensure that the A/E has  adequately addressed all concerns and comments

-------
generated during the preflnal design review process.  If further revisions
to the design are required, the A/E firm shall be so directed.

2.4.4.2  Final Approval

       The agency or party to whom the A/E is under contract shall have the
authority to approve and accept the design, with concurrence from the EPA
and the State on Federal-lead and responsible party projects, and from EPA
alone on State-lead projects.

2.4.4.3  Plan-In-Hand Review

       Plan-In-Hand Review of the final design shall be made by the A/E and
coordinated with the design PO just before the advertisement for
construction of the project.

2.4.5  Major Design Changes

       It is the EPA RPM's responsibility during design reviews and
approvals to ensure that the design package being developed by the USAGE,
State, or responsible party is consistent with the approved ROD/EDO.  If it
appears that major design changes are occurring that would significantly
alter the remedy approved in the ROD/EDO, the RPM should notify the design
PO in writing to temporarily halt design activities and immediately notify
the EPA official delegated ROD responsibility of the situation.  That EPA
official will determine if the design changes warrant .a ROD/EDO amendment
and an additional public comment period.  Minor design changes can be
approved by the design PO, with concurrence from the EPA RPM, consistent
with the approved ROD/EDO.

       Technical scope changes and/or cost changes in the project could
constitute a major design change.  Examples of changes which would
constitute a major change include:

             Change from treatment remedy to disposal remedy or vice versa
                                    2-20

-------
             Proposed remedy will not work due to field conditions

             Implementation cost increases by more than 50%

             Increase in implementation cost results in another alternative
             being potentially less costly.

Examples of changes which would not constitute a major change include:

             Change from one treatment process to another with equivalent
             performance

             Cost savings achieved through value engineering review.

2.4.6  Value Engineering

       For Fund-financed projects, EPA recommends that the USAGE and State
include value engineering screening during the design phase for all remedial
action projects where a potential for substantial cost savings exists.
Value engineering screening shall be limited to project refinements which
would not significantly change or alter the approved remedy, unless
Otherwise approved by EPA.  Value engineering screening will consist of
listing high cost items that have a potential for cost savings.

       Those RA projects which, as a result of the value engineering
screening, show a reasonable promise for significant cost savings will be
recommended to EPA for approval of formal value engineering study by the
USAGE or State.  Potential impacts on the RA project schedule and EPA
funding requirements for a formal value engineering study will be identified
by the USAGE or State.

2.5.  Permits, Approvals and Site Access

       It is important to identify early in the design process all permits,
approvals and site access agreements, if any, required for the project.
Prompt action should be taken to obtain the required permits, approvals, and
                                    2-21

-------
site access agreements 1n order to avoid delays In Implementing the remedial
action.  The following discussion pertains to Fund-financed and responsible
party remedial design.

2.5.1  Permits and Approvals   .

       The permits and approvals which may be required for a project and the
responsibility of obtaining them 1s dependent on the particular project and
the lead design party.  Refer to reference 2 for additional information.

2.5.1.1  Requirements

       EPA has proposed a policy (Reference 2) addressing compliance with
other environmental laws.  Pending final adoption of that policy, the draft
policy should be considered as general guidance.  On-site and off-site
remedial actions shall comply with the substantive requirements of
applicable and relevant laws and standards identified in the ROD/EDO.  For
on-site remedial actions"," environmental permits are not required.  However,
if material is to be taken off site, the receiving facility must possess all
appropriate environmental permits identified in the ROD/EDO.  In general,
the construction contractor shall be responsible for obtaining any necessary
non-environmental construction permits and approvals (i.e., building permit,
electrical permit, etc.)-

2.5.1.2  Responsibilities

       The responsibility for obtaining the required permits and approvals
is dependent on the lead design party and is summarized below.

                                       Environmental Permits
              RD Lead  '                (Off-site RA only)
              Federal                  State
              State                    State
              Responsible Party        Responsible Party
The design PO can request the A/E to provide assistance in obtaining
necessary permits and approvals.
                                    2-22

-------
 2.5.2  Site Access

        At many uncontrolled sites* cleanup actions may have to be taken
 which could require short or long term use of adjoining property or property
 within the site boundaries owned by parties other than the site owner.  In
 addition, the recommended remedial alternative at the site could Include
 actions which might restrict access to or use of both property within the
 site boundaries and adjoining property.  In these situations, it may be
 necessary to obtain access to affected property prior to the initiation of
 remedial actions.

 2.5.2.1  Requirements

        At a site where property access 1s needed, it 1s first desirable to
 obtain voluntary access agreements or rights-of-way from the involved
 property owners.  These access agreements should be obtained prior to the
*completton-of desigiLOf the cleanup alternative.  By obtaining these
 agreements at this time, there will be assurance that the remedial
 construction will not be delayed due to disputes with property owners.

        In some instances, it may be appropriate to acquire easements or
 other interests in property.  Guidance on aquisition will be forthcoming.
 Any purchase of property or easements would be RA activities, requiring
 State cost share for Fund-financed projects.

        For Fund financed RA, if voluntary access cannot be achieved and
 resistance from property owners- is encountered, the State should make all
 efforts to the extent of its legal authority to secure site access.  If
 State efforts fail to secure access, the State should notify EPA in writing,
 and EPA may have to exercise its statutory authority under Section 104 of
 CERCLA and an appropriate access order for entry may have to be secured from
 a court having jurisdiction over the matter.

-------
        For responsible party RA, EPA or the State should assure that
 responsible parties  take all actions needed to obtain access 1n a timely
 manner, and should step in and take legal action if necessary to secure
 access.

        Once again, access agreements, acquisition of interest in property,
 or court orders for  access should occur during the design phase of cleanup,
 prior to the Initiation of remedial construction, so that possible costly
 delays will not be encountered.  Property access should extend for the
 duration of the cleanup and associated operation and maintenance, as
 necessary.

 2.5.2.2  Responsibilities

        The responsibility for obtaining access to the site and adjacent
 properties, as  well  as for all rights-of-way and easements necessary to
 implement the remedial action is dependent on the lead design party and is
 summarized below.  For Federal lead RD, the state or EPA must assure the
•USAGE that site access has been obtained prior to the USAGE initiating
 procurement activities for RA.

              RD Lead                   Responsibility
              Federal                   State
              State                     State
              Responsible Party        Responsible Party
 2.6    Community Relations Activities

        A Community Relations Plan (CRP) should be revised to include any
 changes in the  level of concern or information needs of the community during
 design and construction activities.  Community relations activities during
 design and construction are discussed below, and pertain to Fund-financed
 and private party  projects.
                                    2-24

-------
 2.6.1  Objectives
                                                •
        The basic objectives of the  Superfund  community relations  program
 from remedial  Investigation through construction  are as follows:

              To gather  Information  about  the  community 1n  which a site or
              Incident is  located;

              To inform  the public of  planned  or ongoing actions;

              To give the  public the opportunity to  be involved in decision
              making; and

              To focus and resolve controversy.

' 2.6.2  Implementation Activities and  Techniques

        The implementation of  an effective community relations program as
 outlined  in  the Superfund Community Relations Handbook (Reference 4)
 requires  utilization of two-way communication.  Community  relations
 techniques are selected to fit the  needs  of the site community as determined
 by conducting  on-site discussions.  Small public  meetings, fact sheets,
 press  releases, contact lists, door-to-door visits, local  information
 repositories and comment  periods are  some of  the  most effective techniques,
 especially during  the design  process, to  ensure that the public is involved
 in the decision-making  process.

        Specific activities which must be  conducted  during  the design  stage
 are the following:

              Revise the site  community relations  plan to reflect  knowledge
              of citizen concerns and  involvement  at this stage of the
              process; and

              Prepare  and  distribute a public  notice and an updated fact
              sheet at the completion  of engineering design.

                                     2-25

-------
       Specific activities to be conducted during the construction stage
could be the following:

             Depending on citizen Interest at a site at this point 1n the
             remedial process, community relations activities could range
             from small group meetings to fact sheets on the technical
             status.

             At the end of construction, a final document called a community
             relations review document is prepared.  The purpose of this
             review is to evaluate the overall effectiveness of the
             community relations program throughout the lifetime of the
             project.  (Guidance on this review will be forthcoming.)

2.6.3  Responsibilities

       Responsibility for amending the CRP and implementing community
relation activities is dependent on the lead party for the RD/RA and is
outlined below.

       RD/RA Lead    Amend CRP     Implement CRP   Provide Assistance
       Federal       EPA           EPA  -          State or USACE
       State         State         State           EPA
       Responsible   Responsible   Responsible     EPA, Responsible Party
         Party         Party or      Party or      or State
                       EPA           EPA
2.7.  Cost Estimates For Construction

       The importance of accurately estimating the costs for accomplishing
site-specific construction (i.e., remedial action) can not be over
emphasized.  The development of an accurate total cost estimate is essential
in order to provide adequate funding for a remedial actipn SSC/IAG or CA,
and to determine State cost share.  The following section discusses the
elements included in the total cost estimate for a remedial action, ana
pertains only to Fund-financed remedial actions.
                                    2-26

-------
2.7.1  Estimated Cost of Project

       The preparation of a high quality set of plans and specifications  Is
Inadequate unless the project cost estimate 1s prepared to the same
standards.  The process for developing an accurate project cost estimate  is
discussed in Appendix B.  The project cost estimate becomes more refined  as
the design progresses from the ROD to the preliminary design to the
prefinal/final design.  For most projects, the final project cost estimate
should be within +15X to -10% of the actual cost.  The Importance of the
accuracy of the final project cost estimate 1s magnified since estimates  of
additional costs discussed in Sections 2.7.2 and 2.7.3 are based on the
project cost estimate.

2.7.2  Supervision and Administration (S&A) and Engineering
       and Design (E&D) During Construction

       Supervision and Administration (S&A) and Engineering and Design (E&D)
costs during construction must .be established for each remedial action.
These costs are best represented as percentages of the project cost.  The
following are percentages recommended to be used in estimating costs.
                                *
       8% S&A for contracts up to 52,000,000
       6% S&A for contracts over $2,000,000
       1.5X E&D for contracts up to $2,000,000
       1.0% E&D for contracts over $2,000,000

The percentage used.may vary even more for very small or very large projects,

2.7.3  Contingency Limits

       A contingency fund should be established for each site-specific
remedial action project to cover unforeseen cost variances which may occur
before construction commences or during construction.
                                    2-27

-------
2.7.3.1  Bid Contingency

       The lowest responsive bid submitted during the procurement  process
may exceed the project cost estimate due to complexity of the project,
changes in the bidding climate, etc.  Bid contingencies are best represented
as a percentage of the project cost.  The recommended amount for a bid
contingency is 15X of the project cost.

2.7.3.2  Change Orders and Claims

       During construction, unforeseen site conditions, changes in estimated
quantities, project delays and other problems associated with the  project
are likely to develop and lead to change orders and claims.  A contingency
for change orders and claims is best expressed as a percentage of  the
project cost.  The following percentages are recommended.

       10X contingencies for contracts up to (2,000,000
        8% contingencies for Contracts over $2,000,000

2.7.4  Total Cost Estimate for Remedial Action Agreements

       The total cost estimate to be used In developing SSCs should include
all costs discussed in Sections 2.7.1 - 2.7.3.  The total cost estimate to
be used in obligating funds for CAs and lAGs should be the total cost less
the contingency for change orders and claims.

       Any amount of the bid contingency not needed would be applied towards
the contingency for change orders/claims up to the recommended amount in
section 2.7.3.2.  Any additional amount left in the contingency would be
deobligated or any amount still needed for change orders/claims will be
available from the Region's SCAP.

       Example calculations for estimating the total cost for RA are
presented on the following page.
                                    2-28

-------
          Total Cost Estimate for IA6 or CA
I
1
I
i
i
 i
 i
 i
 i
  a
  i
Estimated cost of project

S&A during construction (.06 x $3,500,000)

E&D during construction (.01 x $3,500,000)

Bid contingency or contingency for change

 orders/claims (.15 x $3,500,00)
                                       Total



           Total  Cost  Estimate  for SSC


 Total cost estimate for IAG

 Contingency for change orders/claims

 (.08 x $3,500,000)
                                        Total
 $3,500.000

    210.000

     35,000


    525,000

 $4,270,000
'•$4,270,000


     280.000

  $4,550,000
                                     9.7Q

-------
                   "-'. V
               • -J- \
3.  IEMEOIAL ACTION

-------
\

-------
                             3.   REMEDIAL ACTION
3.1.  Remedial Action Initiation


        Following completion and approval of the RD package, action must be
taken to Initiate remedial action (RA) activities.  The type of agreement
used to initiate RA is dependent on the party that will implement the RA and
is discussed below.


3.1.1  Federal Lead Remedial Action


        To initiate RA at a Federal lead site, the RPM works with the State
to.prepare and execute a Superfund State Contract (SSC).  The RPM and the
State should refer to Chapters V and VI of the State Manual for specific
information.  Preparation of the SSC should commence during the RD-phase of
the project with SSC execution occurring at the completion of RD.
I

I

I

I

I

I
                 Once the SSC is executed, the EPA Region should prepare and execute
1       a site-specific RA IAG with USACE-MRD.  The RPM should forward copies of the
         executed RA IAG to EPA HQ and USACE-HQ.  Upon completion of procurement
•       activities (Section 3.2), USACE-MRD will initiate RA activities through the
         appropriate USACE Construction District.  The RPM will maintain oversight of
m        all RA activities.  The process is outlined in Exhibit 3-1.  A sample
         site-specific RA IAG is included in Appendix A (Sample No. 3).

         3.1.2  State Lead Remedial Action

                 If the existing CA covers RA, no special action is required.  If
         this is not the case, the RPM should work with the State to amend the
         existing CA for RA in oraer to initiate RA at a State lead site.  The RPM
         and State should refer to Chapters III and VII of the State Manual for
         specific information and procedures.  Exhibit 3-2 graphically depicts the
         State lead remedial action process.

                                              3-1

-------
.•=•-••,!.•   .  .-.•

-------
                                          EXHIBIT 3-1
                         FEDERAL LEAD REMEDIAL ACTION PROCESS
                                                                                                               I
                                         EM HTM ft STATE
                                           PRtMRE SSC
              cants TO
               EMM
              USACf HO
                                           SIC EXECUTED
                                          AT COMPLETION
                                            Of REMEDIAL
                                              DCSIGH
 EM MPM ft USACE MRO
  PREPARE ft EXECUTE
  SITE SPECIFIC RA IAG
                                       OSACE DESIGN DISTRICT
                                      CONOUCTS PROCUREMENT
                                       ACTIVITIES (FIRM FIXED
                                          PRICE CONTRACT)
                                               JL
                                        USACE MHO INITIATES
                                           M ACTIVITIES
                                         TNRU APPROPRIATE
                                                   oisrma
                                        USACE COISTRUaiON
                                         OlSTWa OVERSIGHT
                                          AND MOMITOIIWG
                                          CfliSTRUCTlOII TO
                                         EMSURE COMniAICE
                                         WITH ENVIROI. AMD
                                       COITRACTURAl ftEOMTS.
                       OVERSICHT IT EM IWM
                         ADDITIONAL OVERSIGHT
                             ITEPMMI
                                           comucTon
                                            COMPUTES
                                           COISTRUCTIOH
                                          MfFMAl CONST.
                                         OWFEREICE WITH
                                           CONTRACTOR
                       MMTKVANTS
ACRONYMS KEY
m      taauu nojtcr
at      iumiuMi inn cotnucr
      a  u. tmn cam w IMNHU •
              Ltenm

-------
                                                       EXHIBIT 3-2
                                         STATE LEAD REMEDIAL ACTION PROCESS
                                                     EM WHAM STATE
                                                         AMEND CA
                                                        f NECESSARY
                                                       STATE CONDUCTS
                                                    PROCUREMENT ACTIVITIES
                                                       FIRM FIXED PRICE
                                                         CONTRACT)
 I
1
                     ACRONYMS KEY

                     CA    CMMMTIVt AGKEMtNT
                     IPM   «Mf OUL HWJECT MANAGER
                     m   unouu PWOIBTIES LIST
                     MM   OKMTMM * MAWTEHANCE
STATE OVERSIGHT
AND MONITORING OF
CONSTRUCTION TO
ENSURE COMPLIANCE
WITH ENVIRON. AND
CONTRACTUAL REQMTS.
1
CONTRACTOR 1
COMPLETES
CONSTRUCTION |
1
PREFINAL CONST. 1
CONFERENCE WITH
CONTRACTOR

|
PREFINAl 1
•SPECTION ]

1
STATE PREPARES
PREFINAL INSPECTION
REPORT FOR
SUBMISSION TO
EPA
1
FINAL INSPECTION
AND
CERTIFICATION
|
STATE PREPARES FINAL
•SPECTION REPORT
FOR SUBMISSION
TO EPA
1
EPA ACCEPTANCE
OF COMPUTED
PROJECT

. ADDITIONAL OVERSIGHT
— - BY EPA-RPM
ANOIOR DESIGNEE
PARTICIPANTS »*«"»
1 "j CONTRACTOR
[PARTICIPANTS »*«««»
CONTRACTOR
PARTICIPANTS *****
CONTRACTOR

1



FINAL TECH. REPORT
PREPARED BY
STATE
1
DELETION OF SITE
FROM NPL


1

-------
3.1.3  Responsible Party Remedial Action

        The document of settlement Issued by EPA where  no  trust  fund monies
are Involved will have covered RD and RA, and no special action  1s  required
to Initiate RA at a responsible party site.  The process for  responsible
party lead remedial action is shown in Exhibit 3-3.

3.1.4  Conflict of Interest

        In the process of selecting a contractor for Fund-financed  RA, the
State or EPA shall evaluate whether there 1s a potential conflict of
Interest based on any PRP Involvement at the site.  The EPA Region  should
include a provision in all CAs and lAGs regarding contracts with PRPs.
Appendix F of the State Manual suggests specific language  to  be  included in
a CA provision and suggests specific clauses to be included by the  State in
any contract for services or construction.  lAGs should contain  a provision
consistent with Appendix F, stating the USAGE will require-interested
contractors to provide information and EPA will evaluate potential
conflicts.  The USAGE .should include a provision equivalent to Appendix F in
the contract for construction.

3.2  Procurement Activities

        The responsibility for procurement activities for  Fund-financed
remedial action is dependent on the lead party for the  remedial action
(RA).  For Federal lead RA, the USAGE will conduct procurement activities in
accordance with USAGE procurement procedures.  For State lead RA, the State
will  conduct procurement activities in accordance with  40  CFR Part  33,
Subpart E.

3.2.1  Advertise for Bids

        Procurement for remedial  action should be through  a firm-fixed-price
contract,  and should be by formal  advertising to assure full and free
competition.  Procurement by any means other than formal advertising must be
approved by the award official.  The specifications are rigid and require

-------
                               .   EXHIBIT 3-3
              RESPONSIBLE PARTY LEAD REMEDIAL ACTION PROCESS
 ACRONYMS KEY

 Bfl   UTKUUI. PMOMTCS UST
DIM   OK RATION* MAINTENANCE
                                RESPONSIBLE PARTY
                                  OVERSIGHT AND
                                  MONITORING OF
                                 CONSTRUCTION TO
                                ENSURE COMPLIANCE
                                WITH ENVIRON. AND
                               CONTRACTURAL REMITS.
                                   CONTRACTOR
                                   COMPLETES
                                  CONSTRUCTION
                                  PREFINAl CONST.
                                 CONFERENCE WITH
                                   CONTRACTOR
                                     PREFINAL
                                    •SPECTION
                                        I
                                RESPONSIBLE PARTY
                                PREPARES PREFINAL
                                INSPECTION REPORT
                                FOR SUBMISSION TO
                                       EPA
                                 FINAL INSPECTION
                                       AND
                                   CERTIFICATION
                                 RESPONSIBLE PARTY
                                  PREPARES FINAL
                                 •SPECTION REPORT
                                 FOR SUBMISSION TO
                                       EPA
                                  EPA ACCEPTANCE
                                  OF COMPLETED
                                     PROJECT
FINAL TECH. 3EPORT
   PREPARED 3Y
RESPONSIBLE  PARTY
                        ADDITIONAL OVERSIGHT BY
                        EPA-RPM OR DESIGNEE
                    PARTICIPANTS
                    PARTICIPANTS
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE PARTY
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE PARTY
                     PARTICIPANTS
EPA REGION
STATE
CONTRACTOR
RESPONSIBLE PARTY
                           RESPONSIBLE PARTY
                             ASSUMES O&M
                             RESPONSIBILITY
DELETION OF SITE
FROM NPl
1

-------
absolute conformance.  Sealed bids are required at a certain place, date,
and time and are publicly opened, read, and recorded.  The bidder whose
price 1s low and who 1s otherwise responsive and responsible 1s awarded a
contract.  The solicitation should require all proposals to explain how the
prime contractor would utilize minority business enterprises and women's
business enterprises.

3.2.2 Site Inspection

      The USAGE or State may deem it desirable, or mandatory in some cases,
to conduct a site visit with the bidders in order to answer questions
regarding the design or implementation.  Copies of the RI/FS and the design
document will be made available for review during the procurement phase,
either 1n the USAGE Design District Office or in a local public library.

3.2.3  Review of Bid Documents

      This review shall be limited to determining whether or not the bidders
are both responsive to the requirements of the bid solicitation, (i.e. are
the bid bonds there in the proper form and amount, is the required insurance
binder provided, etc.); and responsible (i.e. does each bidder possess the
capability and experience as required in the solicitation to perform the
remedial action in a safe and timely manner at the price bid, is there any
potential conflict of Interest, if RA involves off-site disposal does the
off-site facility have RCRA compliance inspection, etc.)

      The government bid review responsibility is dependent on the lead
design party and is summarized below.  For responsible party RA, the
responsible party has the primary responsibility for bid review and for
submitting the bid documents for government review.

                        Government Review
      RD Lead             Responsibility         Assistance
      Federal             USAGE               EPA and State
      State               State               EPA (USAGE or EPA Contractors)
                                              upon request)

      Responsible Party   EPA                 State (USAGE or EPA
                                              Contractors uoon request)

-------
I
3.2.4  Bid Protests

      Bid protests have the potential to significantly delay the RA.
Procedures for avoiding bid protests, and lodging and dealing with protests,
should be consistent with 40 CFR Part 33 for State lead projects and with
USAGE procedures for Federal lead projects.  The key 1s often a complete and
well documented bid specification which clearly describes the work to be
performed and the responsive/responsible requirements.

3.3.  Monitoring and Oversight

      Records and reports maintained during these activities must be
adequately documented since they will be used In the final certification of
a remedial action.  Monitoring and oversight of construction activities are
discussed below, and pertain to Fund-financed and responsible party RA
except where noted.

3.3.1  Inspections

      The responsibility for construction inspection is dependent on the
lead party for the RA and is summarized below.

     RA Lead               Inspection            Oversight
     Federal               USAGE                 EPA
     State                 State                 EPA (USAGE or EPA
                                                 Contractors upon request)
     Responsible Party     Responsible Party     EPA (State, USAGE, or EPA
                                                 Contractors upon request)
3.3.1.1  Full Time Inspector

        During all on-site construction activities the party responsible for
inspection will provide a full time on-site inspector with expertise In
federal construction projects and proceedings.  The on-site inspector shall
be authorized to stop all activities not in compliance with 3.3.1.2 and
3.3.1.3 below, or which endanger the health and welfare of on-site personnel
                                             3-7

-------
and surrounding residents.  For large sites or complex  projects,  additional
on-site Inspectors may be required.

        For Fund lead RA, construction oversight will occur at  Intervals
determined by the complexity of the project, by the EPA RPM on  Federal  lead
RA and the EPA RPM or USACE on State lead RA.

        For responsible party RA, construction oversight will be  provided by
the EPA RPM or his designee (i.e. State or USACE) on an ongoing basis.  The
document of settlement will specify the authority of the oversight personnel
in regards to construction activities.

3.3.1.2  ComplianceNwith Environmental Requirements

        Inspections should verify compliance with all environmental
requirements identified in the contract.  These inspections shall include,
but not be limited to air quality and emissions monitoring records, waste
disposal records (e.g., RCRA transportation manifests), etc.  The inspector
also should ensure compliance with all health and safety procedures.

3.3.1.3  Compliance with other Contract Requirements

        The inspector shall review all daily reports and construction
activities to verify that all work is in compliance with all contract
requirements and shall note and resolve all discrepancies immediately.  The
EPA RPM can assist in resolving discrepancies upon request.

3.3.1.4  Review of Contractor Reports

        The on-site inspector shall review all reports  (daily, weekly, and
monthly, etc.) and initial each.  All comments on these reports should be
noted in the inspector's daily log.
I
I
i
                                     3-8

-------
         3.3.2  Progress  Reports to EPA
>
                 Detailed progress reports will  be required throughout the duration
         of the project.   The progress reports will be prepared and submitted to EPA
         Regions and HQ in accordance with the following:

?                RA Lead                 Preparer                Frequency of Report

I                Federal                 USAGE                        Monthly
                 State                  State                        Quarterly
ft                Responsible Party      Responsible Party             Monthly

                 fthe progress reports will be used by EPA  to monitor the remedial
         construction activities.  The content of these reports will be sufficient to
         develop a chronological record of all site activities and should include the
|        following elements:
        i
I                .    Estimate of the percentage of project completed and the total
                      project cost to date

                      Summaries of the following items for the reporting period:
l
m
                      -    Work  performed on  the site
<£                     •    Community relations  activities  Including community
1                          contacts, citizen  concerns,  and efforts to resolve any
                           concerns
                           Change orders  and  claims  made on the contract
                           Problems  or potential problems  encountered

                      Status  of  contingency fund to  date (Fund-financed RA only)

                 .  ^  Projected  \xork for  the  next reporting period

                      Copies  of  contractor daily reports,  change orders, RCRA
                      manifests, and laboratory /monitoring data.
                                             3-9

-------
i            3.3.3  Contingency Fund for Change Orders and Claims

                    This fund 1s available for unforseen site conditions and other
            problems with cleanup, containment, need for alternate disposal sites,
            additional sampling or monitoring which develop and lead to change orders,
            claims, etc.  Problems which would alter ROD decisions -are not subject to
            use of the contingency fund and require HQ and/or Region approval.  A site-
            specific list of Items not applicable to contingency fund use may need to be
            developed as the project progresses.  This section pertains only to
            Fund-financed RA.

            3.3.3.1  Federal Lead Remedial Action

                    The USAGE 1s reponsible for processing change orders and claims In
            accordance with USAGE procurement procedures.

                    The USAGE'S project manager will be delegated authority to approve
            any change order up to 20i of the project contingency fund.  Any change •
            order exceeding 20% of the contingency fund will require approval  of the EPA
            RPM.  If 75X of the total contingency is spent, the USAGE'S project manager
            will formally notify the RPM in writing and state whether additional funding
            may be necessary.  The USAGE'S project manager must receive written approval
            from the EPA RPM in order to exceed 75* of the project contingency fund.  At
            no time will the USAGE exceed 100X of the contingency fund.

            3.3.3.2  State Lead Remedial Action

                    The state is responsible for processing change orders and  claims/
            with assistance and guidance from EPA, and in accordance with 40 GFR 33.

                    The contingency fund is available for change orders.   States must
            obtain the RPM's verbal or written approval  to draw down contingency funds.
            In addition, the State must conduct an administrative and technical  analysis
            of all individual change orders exceeding $100,000 or when the aggregate of
            change orders exceeds 10% of the contractual  funds.  The State must  receive
            EPA's approval  of this analysis before the contingency fund can be used.

                                                3-10

-------
f
        EPA will consider funding claims management costs and claims
allowable to the project via an amendment of the existing CA.

        EPA will provide more detailed Information on change orders and
claims via an addendum to the State Manual in the near future.

3.4  Final Inspection and Closeout

        As the project nears completion, roles and responsibilities of EPA,
the State, and where appropriate the USAGE and responsible parties, must be
clearly defined to ensure proper project completion, approval, and
closeout.  Final Inspection and closeout activities are discussed below.

3.4.1  Prefinal Construction Conference

        Upon preliminary project completion, a prefinal construction
conference with the contractor 1s required for Federal lead remedial action
(RA) and recommended for State lead and responsible party RA.  The objective
of the conference is to discuss procedures and requirements for project
completion and closeout.  The conference will be scheduled and chaired by
the agency that has primary responsibility for construction inspection.

3.4.1.1  Participating Parties

        The parties that participate in the prefinal construction conference
will vary depending on the lead party for the RA.  In general, participants
should include the following:

         Party                RA Lead

         EPA-Region           all leads
         State                all leads
         Contractor           all leads
         USAGE                Federal lead (State and responsible party when
                              requested)
         Responsible Party    Responsible party lead
         Design A/E           when requested

                                    3-11

-------
3.4.1.2  Suggested Agenda Items

        A 11st of suggested Items to be covered at the conference  Includes
but is not limited to:

             Final O&M plan submission
             Cleanup responsibilities
             Demobilization activities
             Security requirements for project transfer
             Prefinal inspection schedule
             Facility startup and testing
             Operator training

3.4.2  Prefinal Inspection

        A prefinal Inspection will be conducted upon preliminary project
completion for Federal lead, State lead, and responsible party RA.

3.4.2.1  Inspecting Parties

        The prefinal inspection will be led by the agency that has primary
responsibility for construction Inspection.  The other parties involved in
the Inspection will vary depending upon the lead party for the RA.  In
general, participants should include all parties from the prefinal
construction conference.

3.4.2.2  Extent of Inspection

        The prefinal inspection will consist of a walk-through inspection of
the entire project site.  The RPM and State should inspect the completed
site work to determine whether the project is complete and consistent with
                       i
the contract documents and the EPA approved remedy.  Any outstanding
construction items discovered doing the inspection should be identified and
noted by the RPM and State.  Additionally, treatment equipment shall nave
been operationally tested by the Contractor.  The Contractor shall have
certified that the equipment has performed to meet the purpose and intent of
                                    3-12

-------
I
I
        the specifications.  Retestlng shall have been successfully completed where
        deficiencies were revealed.

        3.4.2.3  Preflnal Inspection Report

                Upon completion of the prefinal Inspection, a prefinal Inspection
        report will be prepared and processed 1n accordance with the following:

              RA Lead             Preparer             Submitted to
              Federal             USACE                EPA, State
              State               State                EPA
              Responsible Party   Responsible Party    EPA, State
                The prefinal Inspection report should outline the outstanding
        construction Items, actions required to resolve items, completion date for
        these Items, and date for final inspection.
       \
       •3.4.3  Final Inspection and Certification

                Upon completion of any outstanding construction items, a final
        Inspection will be conducted for Federal Lead, State lead, and responsible
       .party RA.

        3.4.3.1  Inspecting Parties

                The final inspection will be led by the agency that has primary
        responsibility for construction Inspection.  The other parties will vary
        depending on the lead p.arty for the RA.  In general, participants should
        include all parties form the prefinal inspection.

        3.4.3.2  Extent of Inspection

                The final inspection will consist of a walk-through inspection of
        the project site.  The prefinal inspection report will be used as a
        checklist by the RPM and the State, with the inspection focusing on the
        outstanding construction items identified in the prefinal inspection.  The
        contractor's demobilization activities should be completed, except for
                                            3-13

-------
equipment and materials required to complete outstanding construction Items,
at the time of Inspection.  The RPM and State Mill confirm that all
outstanding Items have been resolved.  If any Hems are still unresolved,
the Inspection shall be considered a prefinal Inspection requiring another
preflnal Inspection report,

3.4.3.3  Final Inspection/Certification Report

        Upon satisfactory completion of the final Inspection, a final
Inspection/certification report will be prepared and processed In accordance
with Section 3.4.2.3.  The final report will briefly describe the
outstanding construction Items from the preflnal Inspection, Indicate that
the Items are satisfactorily resolved, and certify that the project Is
complete and consistent with the contract documents and the EPA approved RA.

        For responsibility party RA, the document of settlement may specify
different final Inspection/certification conditions.

3.4.4  Acceptance of Completed Project

        The final inspection/certification report will be reviewed by the
RPM for state lead RA and by the RPM and State for federal lead and
responsible party RA.  If the RPM or RPM/State are satisfied that the remedy
1s complete and performing adequately, the Regional Administrator shall
provide written notice to the appropriate party of EPA's acceptance of the
completed project.

3.4.5  Operation and Maintenance Assumption

        The date certified in the final inspection/certification report that
the project is complete and in. accordance with the contract documents, is
the date when O&M commences.

        For fund lead projects this  is the date the State shall assume the
responsibility for O&M.  If necessary, the RPM and State must either amend
the existing CA or develop a new CA  covering 0&M cost sharing.  This CA

                                     3-14

-------
should be processed as soon as reliable cost estimates for O&M  are
available, and need not wait until final project completion.  For
responsible party projects, this .1s the date the responsible party assumes
O&M responsibility.

3.4.6  Site Closeout and Post Mortems

        EPA has Issued Interim procedures to be followed for closing out
sites at the completion of remedial actions and deleting or suspending sites
from the NPL.  For selected sites, EPA may conduct a "post mortem" on the
remedial process Involving the RI/FS contractor, the design contractor,
construction contractor, EPA staff from HQ and multiple Regions, State and
USAGE personnel.  The purpose of such a post construction briefing would be
to learn from the experience of the construction project so as to Improve
future projects.

3.4.6.1  Final Technical Report

        Upon completion of a remedial action, a final technical report is
required to be prepared for state lead RA and recommended for Federal lead
and responsible party RA.  This report will be used to judge the
effectiveness of the remedy and to assess whether criteria for deleting a
site from the NPL have been met.

        The final technical report shall be prepared and submitted to the
RPM within 60 days after the effectiveness of the completed RA has been
confirmed through monitoring.  The responsibility for preparing the final
report is dependent on the lead party for the RA and is summarized below.

        RA Lead             Preparer            Copy to

        Federal             USAGE and State
        State               State
        Responsible Party   Responsible Party   State

-------
        The final technical report will document that the project 1s
consistent with the contract documents, and that the remedy 1s performing
adequately.  Elements to be Included 1n the final technical report are taken
from Appendix F of the State Manual and Include, at a minimum, the following:

             Synopsis of the work defined in the SOW and a certification
             that this work was performed

             Explanation of any modifications to work 1n the SOW and why
             these were necessary for the project

             Listing of the criteria, established before the remedial action
             was Initiated, for judging the functioning of the remedy and
             explanation of any modification to these criteria

             Results of site monitoring, Indicating that the remedy meets
             the performance criteria
             Explanation of the operation and maintenance  (Including
             monitoring) to be undertaken at the site.

        For Federal lead projects, 1t 1s recommended that  the USAGE prepare
the sections of the report concerning the construction project and that the
State prepare the sections of the report concerning performance of the
remedy after O&M has commenced.

3.4.6.2  Deletion of Site from NPL

        The EPA Region can recommend deletion of a site from the  NPL  after
completion of a RA, if one of the following deletion criteria has been met:

             EPA, in consultation with  the State, has determined  that
             responsible parties have completed all appropriate response
             actions
                                     3-16

-------
             EPA, 1n consultation with the State, has determined that all
             appropriate Fund-financed response actions have been completed
             and that no further cleanup by responsible parties 1s
             appropriate.

        For detailed Information on the criteria and mechanism used to
delete sites from the NPl, the RPM should refer to the memorandum entitled
"Interim Procedures for Deleting Sites from National Priorities List."  This
memorandum has been Included in Appendix P of the State Manual.

-------

-------
^                                       APPENDIX A

                                SAMPLE tISACE WORK ASSI6MCNTS
|                               AND INTERA6ENCY AGREEMENTS
   •

I

I

I

I

-------
4-'-

-------
     SAMPLE NO. 1
        IA6 FOR
FIRST PHASE DESIGN WORK

-------
t

-------
   Pit*** rttd instructions on 0«ov* 4 §nd S
         US ENVIRONMENTAL PROTECTION AGENCY
               WASHINGTON. DC 20460
   INTERAGENCY AGREEMENT/AMENDMENT
        Part I - GENERAL INFORMATION
1. IAG Identification Number
3. Type of Action
   New Agreement
2. Funding Location by Region
4. Program Abbreviation
  15. Name and Address of EPA Organisation
               *
6. Nemo and Address of Other Agency
Department of Defense  .
U.S.  Army Corps of Engineers (USAGE)
Engineering Division,  Missouri River
Omaha, Nebraska 68101-0103
  7 Protect Title
  First  Phase Design Work - FT 1985
  8. EPA Project Officer (N»m*. Addrist. ft/ep/wne Numtwl
'i
9. Other Agency Project Officer /Atone. Address. T»lfphon« Numoeri
 William Mulligan        FTS/864-7227
 USAGE,  Engineering Division, Missouri  River
 P. 0. Box 103, Downtown Station
 Omaha,  Nebraska 68101-0103
 I 10. Protect Period
    10/01/84 - 09/30/85
11. Budget Period
     10/01/84 - 09/30/85
   12. Scope of Work (Attten Mttoona/ th»»ts.
   This agreement obligates no more than $   *    and generally no more  than $7,000 per
   project to the USAGE to initiate the  selection of Architectural/Engineering firms for
   the engineering  design phase of Federal lead remedial  action projects.   The USAGE will
   perform all action  necessary to retain an A/E firm for engineering  design, including
   the following:

        Phase I -

           Synopsize requirement in Commerce Business Daily
           Designate A/E. pre-selection and selection boards
           Develop  A/E pre-selection list
           Contact  A/E firms to ascertain interest in project
           Approve  A/E selection list
           Tentatively select A/E firm
13. Statutory Authority for both Transfer of Funds and Protect Activities
1 CERCLA, E.O. 12316 & the Economy Act of 1932, as amended (31USC1535)
* FUNDS
15. EPA Amount
i 16. EPA In-Kind Amount
i 17 C'her Aqencv Amount
18 Otner Aqencv In-Kind Amount
1 9 Total P'oiect COST
PREVIOUS AMOUNT


AMOUNT THIS ACTION
*

i



*

14 Other Agency Type
Federal-
AMENDED TOTAL





| 20 Fiscal Information
Program Eltment
TFAY9A
FY
85
Appropriation
68/20X8145
Doe. Control No.
*
Account Number
*
*
Obiect Class
25.76
Obligation, Decollation Ami
*
   EPA farm

-------
                     PART II - APPROVED BUDGET
                                                                                  IAG IDENTIFICATION NO.
                             J1. ludget Categories
                                                                                         Total Itemisation of
                                                                                       Estimated Cost to Date
  (a> Personnel
  (bl Fnnoe Benefits
  (el Travel
  (•I Supplies
  (ft Procurement/Assistance
  (at Construction
  (ht Other
  (0 Ton) Oiract Charge*
                                                                              $  Breakdown  not  available.
  til indirect CottrJstt
                          »8ase
                                                                          Will  be  provided  as  part of
  
                                                                                 request  for reimbursement.
                                                                                                 *
22. la equipment authorised to be furnished by EPA or acquired with EPA fund*?
  flOfttufv e*eeti«i»riie«» coning 47.000 tr morii
23 Arc any of these funds being used en extramural agreements?    |_J Yn

  O Gram.    LJ CeeeerstrM Agreement or   LJ •toeurement
  Camecter/Mwipiem Name (if urtowni
                                    Total Extramural Amount Under This rHojeet     •ereent Funded by E*A (it known/
                                 •AKT III — PAYMENT METHODS AND BILLING INSTRUCTIONS
24.
  I Disbursement Agreement:
        D Advance
           I Allocation Transfer
                              Request for reimbursement of actual costs will be itemised on SF 1081 or SF 1080 and
                              submitted te the Financial Management Office. Environmental Protection Agency. 26 West St
                              datr. Cincinnati. OH 45268

                                 B Monthly    LJ Quarterly   D Upon Completion of Work

                              Only available for use by Federal agencies en working capital fund or with appropriate iu«if tea •
                              Dpn of need for this type of payment method. Unexpended funds at completion of wore win oe
                              returned to EPA. Quarterly cost reports will be forwarded to the Financial Management Office.
                              Environmental Protection Agency. 26 West St. Claw. Ctnonati. OH 4S268.

                              Used to transfer oMigational authority or transfer of function between Federel agencies Must
                              receive prior approval by the Office of the Comptroller. Budqet Division. Budget formulation mo
                              Control grancn. EPA Headquarters
25
Qp-eim
Aursement Agreement
Other Agency's IAG Identification Number
Billing Address
                                                         tilling instructions and Frequency
 EPA Form 1410-1 (Mew. 8-«4)
                                                                                                            Page 2 of 5

-------
             PART IV - ACCEPTANCE CONDITIONS
                                                                    (AC IDENTIFICATION NO.
26. Goners) Conditions:
   The other agency covenants and agrees that it will expeditioualy initiate and complete th« project work for
   which funds have been awarded under thia agreement.	
27. Spec* Conditions:
Work assignments  for A/E aelectioo will  be initiated via a letter eigned by the
      ..  	   *	 or  hia design**.   The letter will
identify the particular site, provide  the necessary account numbera, and describe  any
adjustments, including Increases in  the  aite dollar ceiling (57,000) and/or changes
to the scope of work.

The DSACE will initiate Phase 1 actions  upon receipt of EPA authorization.  Phase  II
actiona will not  begin until EPA has notified the USAGE of the  aelection and approval
of a remedy and EPA approval of an Interagency Agreement for  Phase II  actions.

EPA acting as manager of the Hazardous Substance  Response Trust Fund,  requires current
information on CERCLA response actiona and related obligations  of CERCLA funds for
these actions.   In addition, CERCLA  authorizea EPA to recover from responsible parties
all government coata incurred during a reaponae action.

                                        • (See Attachment A)
                                        - OFFER AND ACCEPTANCE
 NOTE: 1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
            returned to the Grants Administration Division for Headquarters agreements and to the appropriate
            EPAIAG administration off ice for Regional agreements within 3 calendar weeks after receipt or within
      -.     any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
      ^     the address cited in Item 28 after acceptance signature.

            Receipt of a written refusal or failure to return the properly executed document within the prescribed
            time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other'
            agency subsequent to the document being signed by the EPA Action Official which the Action Off icia I
            determines to  materially  alter  the  agreement/amendment shall  void the agreement/
            amendment

       2)   For reimbursement  actions, the other agency will initiate the action and forward two  original
            agreements/amendments to the appropriate EPA  program office for signature The agreements/
            amendments will then be forwarded to the appropriate EPAIAG administration office for acceptance
            signature on behalf of the Environmental Protection Agency. One original copy will be returned to the
            other agency after acceptance.
 EP*IAC Admm«rmeo Qtftet Her
                                                          EPA Program Offm ffer ttctvuctt uusttncti
21. Organoauon/AdoraM
                                               2*. Organisation/Addran
                   Decision Official on Behalf of tho Environmental Protection Agency Program Offieo
Signnurt
                                       Typed Name and Titla
He
                         Action Official on Bafialf of tha Environmental Protection Agency
   Signature
                                     Typ«d Name and Tula
                                                                                 Oata
                              Authoring
                                     Official on Sonarf of the Other Agency
32.
                                       Typed Name and Title
                                                                             Date
EPA Form 1S1O.1 /••*

-------

-------
                                ATTACHMENT A

27. SPECIAL PROVISIONS (continued)                      :

    In order to help assure successful recovery of CERCU funds, the USACE
shall maintain site-specific accounts and documentation of the following:

         Employee hours and salary (timesheets)          /

         Employee travel and per diem expenses (travel authorizations, paid
         vouchers, and treasury schedules)                \

         Receipts for materials, equipment, and supplies

         Any other costs not included in the above categories

    In order to assist in the development and prosecution of a cost recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (DOJ), the USACE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and DOJ may periodically request updates of the costs and
documentation after the initial request.  The USACE will provide EPA with, a
contact for obtaining such site-specific accounting information and
documentation.  This cost information and documentation must also be
available for audit or verification on request of the Inspector General.

    USACE will provide access to its files concerning the project on an
on-going basis for EPA and DOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USAGE will
provide EPA and DOJ access to the original documentation when requested.
USACE will notify EPA in advance of placing any project files in storage or
archives.

    Reimbursement is contingent upon receipt and approval by EPA of monthly
progress and financial reports by site, containing an accounting of funds
and status of activities.

    The, USACE will provide a letter report summarizing each A/E selection to
the Regional Technical Project Officer.

-------
Mr. William Mulligan
U.S. Army Corp* of Engineers                                ••
Engineering Division, Missouri River
P. 0. Box 103, Downtown Station                           \
Omaha, Nebraska  68101-0103                               '

Dear Mr. Mulligan:                                         \

     This letter serves to initiate a work assignment for the U. S. Army Corps
of Engineers (USAGE) to select an architectural/engineering firm to design the
remedial action at the following superfund site:
     The selected activities must be consistent with the Interagency Agreement
No. DW96******-01-0 between the USAGE and the Environmental Protection Agency
(EPA).  Funding for costs incurred while providing these services to EPA,
authorized under the authority of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980 (CERCLA), is not expected to exceed:
     Enclosed is the Phase I Design Authorization Form.  This document contains
the necessary account numbers that apply specifically to this work assignment.
These numbers must be used on all financial and management reports.

                                      Sincerely yours,
                                      (Title)

Enclosure

cc:  Richard .Ruhe
     Noel Urban
     Paul Nadeau
     Iv-:ry Jacobs

-------
IS PROVIDED FOR COST TRACKING PURPOSES!

SITE NAME                     	

REGION                        	

EPA SITE I.D. *               	

HQ TECHNICAL PROJECT OFFICER  	

REGIONAL SITE MANAGER         	

PERIOD OF PERFORMANCE
                                                                PHONE
                                                                PHONE
                                           FROM
                                                   TO
                             ACCOUNTING INFORMATION
                | DOCUMENT    I
                 CONTROL NO
                      TAG  NO.
I
\
I    SUPERFUND
    ACCOUNT NO.
                                                                          I         I
                                                                          I   6BJECT1
CLASS
CODE
            NOT TO
            EXCEE:.
            AMOUN'
DSOBLIGATE FROM:T~*T* i * 1 *T*T* \ D lW 1.916
                                        olsTrTFlAl*T* 1*1 NToTor2T5T7l6  I$1*1*1*1*
              JJLt'
              **

                             iDiwiiieiijnM
                                    OllllJSlTiFiAiM*.
2i5i7l6_IS±^l*-^
                  (Title)
                                             DATE
               EPA PROJECT OFFICER
                                             DATE
               (individual  who  certifies funds)
                        •   • \
 Original to^  Richard Ruhe,  EPA
               Cincinnati,  QA-,

 ce.           William Mulligan,  USAGE

               Noel Urban,  USACE

               Paul Nadeau, EPA
                                             DATE
               ivery Jacobs,  EPA,  Room 3623M
               Financial Reports and Analysis Branch

-------
      SAMPLE NO. 2
         IAG FOR
DESIGN OF REMEDIAL ACTION

-------
          US ENVIRONMENTAL PROTECTION AGENCY
                WASHINGTON. DC 20460
    INTERAGENCY AGREEMENT/AMENDMENT
          Pert I - GENERAL INFORMATION
                          1. IAG Identification Number
                          3. Type o< Action
                               New Agreement
2. Funding Location by Regior
      *
4. Program Abbreviation
    5. Ntme and Address of EPA Organization
            *
                          6. Name and Address of Otner Agency
                              Department of Defense
                              U.S. Army Corps of  Engineers  (USAGE)
                              Engineering Division,  Missouri  River
                              Ooaha,  Nebraska 68101-0103
   7. Protect Title
        Design of remedial action  at
   8. EPA Protect Officer (Warn*. Addrtss. Tt/tptton* Number)
 f
                          9. Other Agency Protect Officer tftone. AOdrtss. T*t*phon*
                               William Mulligans •      FTS/864-7227
                               USAGE,  Engineering  Division,  Missouri River
                               P. 0. Box 103, Downtown Station
                               Omaha,  Nebraska  68101-0103
    10. Protect Period
                          11. Budget Period
                                  *  (same as project period)
    12. Scope of Work (An»ch •oV/r/o/ia/ */>••«.
      This  Interagency Agreement obligates a  total of $     *   to the  U.S. Army Corps of
      Engineers (USAGE) for .the design of remedial action  at               *	
                     *          	   (ID#      *       ).  These  funds are divided as
       follows:

         1.   $   *
for a contract to design the remedial action.
         2.   $   *      for supervision and execution of  the contract.   Specific USAGE
             responsibilities are  detailed in  the appended  Scope of Work (Attachment  A).
jr
13. Statutory Author ;•• for both Transfer of Funds and Protect Activities ' 14. Other Agency Type j
CERCLA, E.G. 12316 & Economy Act of 1932, as amr ~d (31USC1535) Federal j
FUNCS
1 S EPA Amount
16 EPA In-Kind A- ,jnt
17 C'har Aqene' _'unt
1 8. Other Agencv --"ind Amount
PREVIOUS AMOUNT




AMC ' ' THIS ACTION
*



AMENDED TOTA^




      19 Total Proiec: C. .
    20 Fiscal Informant)-
i
/
!
Program Element
TFAY9A

t

Appropnation
68/20X8145

Doc. Control No.
*

Account Number
V
Obtect Class
25.76

Obligation/ Oeoo: gj,.cr> -

EPA Form 1610-1 (r v. S-84) Previous editions are obsolete . Pac-

-------
                            II - APPROVED BUDGET
                                                                                  IAG IDENTIFICATION NC
                             21. Budoet Categories
                                                                  Total ttamiution at
                                                                 Estimeted Cost jo Date
  'a) Personnel
                                                                                 $
  Ib) Fnnoe Benefits
  lei Tr
  (•I Suooliet
  rtl Procurement/Assistance
  tat Construction
  mi Other
  M Total Direct Charge*
                                                                                 $   (.Breakdown  noc available.
  (it indirect Can*   Rate
   • Base
    Will  b«  provided  prior  to
  
-------
                PAflT IV - ACCEPTANCE CONDITIONS
                                                                     IAG IOC NTIFICAnON NO.
   26. General Caodtoon*
     The other agency covenants and agrt«s that it will expeditiously initiate and complete the project work for
     which funds have been awarded under this agreement.	       	
   Reimburaement is contingent  upon receipt  and approval by EPA of the monthly progress
   and financial reports from the USAGE described below and any other reports  described
   in the appended scope of work.  The monthly progress reports will be submitted to
|  (Regional  P.O.)      in EPA  Region    .(city)   . (state)  .  and    (Hq P.O.)	 In
1 I EPA, Washington, D.C.

, ' EPA acting aa manager of the Hazardous  Substance Response Trust Fund, requires current
'  information on CERCLA response actions  and related obiigatlone of CERCLA funds for
   these actiona.  In addition, CERCLA authorizes EPA to recover from responsible parties
   all government coata incurred during a  response sction.

                                       (See  Attachment B)
1
                                     •art V - OMEH AMD ACCEPTANCE
 I
I NOTE: 1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
       ,     returned to the Grants Administration Division for Headquarters agreements and to the appropriate
             EPA IAG administration office for Regional agreements within 3 calendar weeks after receipt or within
             any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
             the address cited in Item 28 after acceptance signature.

             Receipt of a written refusal or failure to return the properly executed document within the prescribed
             time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other
             agency subsequent to the document being signed by the EPA Action Official which the Action Official
             determines to  materially alter the  agreement/amendment shall void the  agreement/
             amendment

        2)   For reimbursement actions, the other agency will initiate the action and forward two original
             agreements/amendments to the appropriate EPA program office  for signature. TH* agreements/
             amendments will then be forwarded to the aoprooriate EPA TAG administration office for acceptance
             Signature on behalf of the Environmental Protection Agency. One original copy will be returned to me
             other agency after acceptance.
I EPA IAG Admimstrnion W ** ffor •rtTMm*trMnw/marMo*m«iw tssistncH
28. Onjanamn/Addrns
*
EM Program Otfiet Hot r«e/ime«/ isutttncti
21. OnjanoMMn/Addran
*
Oeciiion Official on Behalf
] 30. Sonenir.
(l
i


Typed N*nw and Tide

Oata
.
I Action Official on Behalf of the Environmental Protection Agency
•fit.-' 31. Signature
~
I Authorising
\ 32. Signature
Typed Name and Title
*
Data
;
Official on Behalf of the Other Agency ;
Typed Name and Title
Date <
I

-------

-------
                         REMEDIAL DESIGN

                          Scope of Work

     •
SITE  [Name, City, State]

PURPOSE

     The purpose of this assignment is to obtain assistance from
the U.S. Army Corps of Engineers (USAGE) for the design of a
remedial action at the [site name].

BACKGROUND

     [Briefly summarize the site in 1 or 2 paragraphs to  include]

     o  [Location of site]
     o  [Brief history of operations, releases, response actions,
        etc.]
     o  [Quantity, types, and concentrations of hazardous  substances]
     o  [Extent of contamination]

     A Record of Decision (ROD) was signed by the  [AA-OSWER or
RA] on  [date] selecting  [description of remedy] as the cost
effective remedy for the [site name].

REMEDY

     The remedy selected by EPA and the State of [state-name]
includes the following components:

     [List major components in bullet form]

WORK STATEMENT

     The USAGE will be responsible for:

     1.   Developing the technical statement of work and  awarding
          and managing a contract to a private firm for the
          design of [description of remedy].  The design  package
          will consist of the plans and specifications along with
          [include as necessary -O&M Plan, QAPP, Site Safety
          Plan, etc.).

     2.   Review of the design packa--:    . coordination with the
          EPA-RPM   at .approximately ...  60% (if necessary),
          95%, and 100% completion.  Ap^r^val and acceptance of
          final design, with concurrent    oro EPA.

     3.   Providing other support to include [permit assistance,
          community relations assistance, etc.].

     4.   Reproducing design documents.

     Specific USAGE responsibilities are detailed in the
Suse.vfund Remedial Design and Remedial Action Guidance.

-------
                                                                                      >

27. SPECIAL PROVISIONS (continued)                                                  A

    In order to help assure successful recovery of CERCLA funds, the USAGE            ,
shall maintain site-specific accounts and documentation of the following:

         Employee hours and salary (tlmesheets)                                       ]

         Employee travel and per diem expenses (travel authorizations, paid
         vouchers, and treasury schedules)

         Receipts for materials, equipment, and supplies

         Contract costs (paid Invoices, treasury schedules and copy of the
         contract)  .

         Any other costs not included in the above categories

    In order to assist in the development and prosecution of a cost recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (DOJ), the USAGE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and OOJ may periodically request updates of the costs and
documentation after the initial request.  The USAGE will provide EPA with a
contact for obtaining such site specific accounting Information and
documentation.  This cost information and documentation must also be
available for audit or verification on request of the Inspector General.

    USAGE will provide access to its files concerning the project on an
on-going basis for EPA and OOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USAGE will
provide EPA and OOJ access to the original documentation when requested.
USAGE will notify EPA in advance of placing any project files in storage or
archives.

    Reporting requirments are as follows:

    The USAGE will provide the EPA with a completed signed SF 1080 and
monthly reports containing:

         a.   USAGE estimate of the percentage of project completed.

         b.   USAGE estimate of dollars expended on the project to date.

         c.   Summaries of all change orders and claims made on the contract
              during the reporting period.   Attach copies of all change
              orders as appendix.

         d.   Summaries of all contracts with representatives of the local
              community, public interest groups or State government during
              the reporting period.

         e.  ' Summaries of all problems or potential problems encountered
              during the reporting period.

         f.   Projected work for  the  next reporting period.

-------
          SAMPLE NO. 3
             IAG FOR
IMPLEMENTATION OF REMEDIAL ACTION

-------
Ptittst rrad instructions on peews 4 end 5
US ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON. DC 20460
INTERAGENCY AGREEMENT/ AMENDMENT :
Part 1 - GENERAL INFORMATION
5. Name and Address of EPA Organization
*
(
7. Protect Title
Remedial action at

8. EPA Project Officer (Ntm». Address. Telephone NwnoerJ i
*
10. Project Period
*
12. Scope of Work (Antefi aotf/r/ona/ sheets, ax /w
This agreement obligates a t
(USAGE) for implementation o
*

eded!
otal of $
f the remed;
(EPA ID*
divided as follows:
1. $ for implementation of
2. $ for super
the Invitation for Bi
in the appended Scope

1. 1AG Identification Number
>. Type of Action
New Agreement
2. Funding Location by Region
4. Program Abbreviation
I. Name and Address of Other Agency
Department of Defense
U.S. Army Corps of Engineers (USAGE)
Engineering Division, Missouri River
Omaha, Nebraska 68101-0103
*

>. Other Agency Project Officer (N»me. Address, Telephone Number/
William Mulligan FTS/864-7227
USAGE, Engineering Division, Missouri River
P. 0. Box 103, Downtown Station
Omaha, Nebraska 68101-0103
11. Budget Period
* (same as project
* to the U.S. Army Cor
al action at
} * ).
the remedial action.
period)
ps of Engineers
*

vision and execution of the contract awarded based on
d (IFB). Specific USAGE responsibilities are detailed
of Work (Attachment A).
13. Statutory Authority for both Transfer of Funds and Protect Activities 14. Other Agency Type
CERCLA, E.O. 12316 & Economy Act of 1932, as amended (31DSC1535) Federal
FUNDS PREVIOUS AMOUN'
IS. EPA Amount
16. EPA In-Kind A-nount
17 C'her Aqencv Amount
18. Other Agency- (--''"id Amount
19 Total Proied COST
20 Fiscal Information
Program Element ?v Appropriation
TFAY9A 85 68/20X8145



Doc. Control No.
*
r AMOUNT THIS ACTION
X


I
*
AMENDED TC'AL






Account Number Object Class Obligation/ Deoongsvon Ami
* 25.7* *
EPA Form 1610-1 (R«v. 8-94) Previous editions are obsolete.
Page i  c-

-------
PART !l
i
- APPROVED BUDGET
21. Budget Categories
(•i Personnel
:&) F-moe Benefits
(C) Travel
Id) Eauiement
(a) Sufto"»«
If) Procurement/ Assistance
fat Construction
(h) Other
(0 Total Oiract Charoes
(i) indirect Cost*' Hat* I BaM
W Total
(EPA She** 100 %) (Other Agency Shore 0 %)
22. la equipment authorued to M h

IAG lOENTlPlCATlCN ^C.
Total Itemuution of
Estimated Can 10 Date
9
4
%
1




$ (Breakdown not available.
Will b« provided prior to
reimbursement.)
$ *
jmisfted by EPA or acquired wntn EPA funds? Q Yes ^ No
.000 or mor»y
23. Are any of these funds 6«ng used on extramural agreements? El Yes Q No rSee /c«/r» 27 fl
Q Gram. Q Cooperative Ayeemem. or S^roeurement
ContMtor/Reetpiem Name lit known) Tout Extramural Amount Under Thi* Protect
Unknown - * (estimate)
Percent Funded by EPA tit knovni
TOO*
e>
•ART III — PAYMENT METHODS AND BILLING INSTRUCTIONS

HftertntHirMrnem

Request for reimbursement of actual costs will be itemind on SF 1081 or SF 1080 and
submitted to the financial Management OHice. Environmental Protection Agency. 26-W*st St. • —
O*»r. Cincinnati. OH 45268: 	 •
SMontMy Q Quarterly O Upon Completion of Work \
         D Advance




         LJ Allocation Transfer
Only tveilaWe for use by Federal agencies on working, capital fund or with appropriate justifica-
tion of need for this type of payment method. Unexpenu«d i'urx»» «i u>ci>wi*tior. of «cru .-..:: ic
returned to EPA. Quarterly cost reports will be forwarded to the Financial Management 0«
-------
                •ART IV - ACCEPTANCE CONDITIONS
                                                                      (AC lOiNTIFICATION NO.
   26. Oaooral Conditions:
     The other agency covenants and agrees that it will expeditiously initiate and complete tht projtet work for
     which funds heve been awarded under thia agreement.                 	^_____	
 | 27. Sooosl Conditions:
  Reimbursement  la  contingent  upon receipt and approval by EPA of the monthly progress
1 ireports from USAGE described below and  any other  reports described in  the appended  scope
 I of uork.   The  monthly progress reports  will be submitted to   (Regional P.O.)      in EPA
i  Region   .	.	, and     (Hq P.O.)	 in EPA, Washington, D.C.

 I EPA  acting as  manager of the Hazardous  Substance  Response Trust Fund,  requires current
•  information on CERCLA response actions  and related obligations of CERCLA funds for
  these actions.  In addition, CERCLA authorizes EPA to recover from responsible parties
 fall  government costs Incurred during  a  response action.

i                                       (See  Attachment A)
                                     Part V - QFFEH AND ACCEPTANCE
/  NOTE: 1)   For disbursement actions, the agreement/amendment must be signed in duplicate and one original
 I            returned to the Grants Administration Division for Headquarters agreements and to the appropriate
 '       -    EPA IAG administration office for Regional agreements within 3 calendar weeks after receipt or within
         -    any extension of time as may be granted by EPA. The agreement/amendment must be forwarded to
              the address cited in Item 28 after acceptance signature.

         ,     Receipt of a written refusal or failure to return the properly executed document within the prescribed
         <;.  _ time may result in the withdrawal of the offer by the Agency. Any change to the agreement by the other
              agency subsequent to the document being signed by the EPA Action Official which the Action Off ioa I
              determines  to  materially  alter the agreement/amendment shall  void  the  agreement/
              amendment

          2)   For reimbursement actions,  the other agency will initiate the  action and forward two  original
              agreements/amendments  to the appropriate EPA program office for signature  ~h* agreements/'
              amendments will then be forwarded to the appropriate EPA IAG administration office for acceptance
              signature on behalf of the Environmental Protection Agency. One original copy will be returned to the
              other agency after acceptance.
   6PA 1AC Admmgtf anon Qftict Hot
                                          tuattnttl
                                   EPA Program Off >et /for ntt*ut»t twtuneti
 128. OrganioMn/Addrau
                        29. Onjamaoon/Addrta
                     Doeiaion Official on B«hatf of ttx Environmental Protection Afl«ncy Program Offic*
  30.Sign«urt
              TyporiNMiw and Titte
0«t
Acoon Offtcu* on
                                              of th« envmjnm«m»( Protection Aqvncy
31. Stgn»tur»
Authorizing
32. Signnurt
Typwi N«m« »n4 Title
Official on *•*•«* t>1 th« Ottwr Aa«ncy
Typod Nomo and Till*
Oat* j
i
i
Daw |
  EPA Form 1*10-1 (flrv. t-a4|

-------
                         REMEDIAL ACTION
                          Scope of Work

SITE   (Name, City, State]
PURPOSE
     The purpose of this assignment is to obtain assistance  from
the U.S. Army Corps of Engineers  (USAGE) for  the implementation
of a remedial action at the  [site name].
BACKGROUND
     [Briefly summarize the site in 1 or 2 paragraphs  to  include]
     o  [Location of site]
     o  [Brief history of operations, releases, response actions,
        etc.]
     o  [Quantity, types, and concentrations of hazardous  substances]
     o  (Extent of contamination]
     A Record of Decision (ROD) was signed by the  IAA-OSWER  or
RA] on  [date] selecting (description of remedy] as  the cost
effective remedy for the [site name].
     The remedial design (RD) for the remedy  was performed by the
[USAGE or other party].
REMEDY
     The remedy selected by EPA and the State of [state name]/
and detailed in the IFB includes the following components:
     [List major components in bullet form]
WORK STATEMENT
     The USAGE will be responsible for:
     1.   Conducting procurement activities for remedial  action.
     2.   Managing the contract for remedial  action.
     3.   Providing oversight and monitoring  of construction in
          coordination with the EPA-RPM, to ensure  compli.. ce
          with all contract requirements.
     4.   Conducting final inspection and certification oi
          completed remedial action in coordination with  tne
          SPA-RPM.
        ?cific USAGE responsibilities are detailed in the
Sup-   und Remedial Design and Remedial Action Guidance.

-------
27. SPECIAL PROVISIONS (continued)

    In order to help assure successful recovery of CERCLA funds, the USAGE
shall maintain site-specific accounts and documentation of the following:

         Employee hours and salary (tlmesheets)

         Employee travel and per diem expenses (travel authorizations, paid
         vouchers, and treasury schedules)

         Receipts for materials, equipment, and supplies

         Contract costs (paid Invoices, treasury schedules and copy of the
         contract)

         Any other costs not Included 1n the above categories

    In order to assist 1n the development and prosecution of a cost, recovery
action, within three weeks from the date of a request from EPA or the
Department of Justice (000), the USAGE will provide to EPA or DOJ
site-specific costs and copies of the back-up documentation which supports
those costs.  EPA and DOJ may periodically request updates of the costs and
documentation after the initial request.  The USAGE will provide EPA with a
contact for obtaining such site specific accounting information and
documentation.  This cost Information and documentation must also be
available for audit or verification on request of the Inspector General.

    USAGE will provide access to its files concerning the project on an
on-going basis for EPA and DOJ examination to assist in cost recovery.  As
original documents may be requested for cost recovery actions, USAGE will
provide EPA and DOJ access to the original documentation when requested.
USACE will notify EPA 1n advance of placing any project files in storage or
archives.

    Reporting requirments are as follows:

    The USACE will provide the EPA with the following reports:

    1.   A completed signed SF 1080.

    2.   A monthly progress report containing:

         a.   USACE estimate of the percentage of project completed.

         b.   USACE estimate of dollars expended on the project to date.

         c.   Summaries of all change orders and claims made on the contract
              during the reporting period.  Attach copies of all change
              orders as appendix.

-------
     d.   Summaries of all contacts with representatives of the local
          community, public interest groups of State government during
          the reporting period.                     :
                                                    \
     e.   Summaries of all problems or potential problems encountered
          during the reporting period.              N-

     f.   Projected work for the next reporting periddK

3.   Weekly telecon construction status update(s) to *_	,
     EPA, Region  * .                                 \

-------
               APPENDIX B

        ELEMENTS TO BE INCLUDED
IN THE REMEDIAL DESIGN STATEMENT OF WORK

-------

-------
                                 APPENDIX  B
                           ELEMENTS TO BE INCLUDED
                  IN THE REMEDIAL DESIGN STATEMENT OF WORK
                                                         v-.
                                                         \
The objective of this Appendix 1s to provide guidance and-clarification  of
submission requirements for the Architect/Engineer (A/E) retained  to  provide
the final document package* which shall Include all the required plans and
specifications, in response to the statement of work (SOW)  issued  for a
remedial design project.

B.I  Plans and Specifications

    The final construction plans and specifications prepared by the A/E  to
accomplish the remedial action proposed in the SOW shall be required  to
comply to certain standards and submissions as outlined herein.

8.1.1  Preliminary Design

    Submission of the preliminary construction plans and specifications
shall reflect the A/E design effort at 30% completion.  At this stage the
A/E shall have field verified the existing conditions of the site.  The
preliminary design shall reflect a level of effort such that the technical
requirements of the project have been addressed and outlined so that  they
may be reviewed to determine if the final design will provide an operable
and usable remedial project.  Supporting data and documentation shall be
provided with the design documents defining the functional aspects of the
project.  The initiation of construction drawings by the A/E shall reflect
organization and clarity.  The scope of the technical specifications  shall
be outlined in a manner reflecting the final specifications.  The A/E shall
include with the preliminary submission desigr ralculations reflecting the
same oe>-ir.tage of comoletion as the designs tfiey -, "oort.

-------
B.I.2  Intermediate Design  .

    Complex project design may necessitate review of the design documents
between the preliminary and the prefinal/final design.  At the discretion of
the design PO, a design review may be required at 60% completion of the
project.  The intermediate design submittal should Include the same elements
as the prefinal design.

B.I.3  Prefinal/Final Design

    The prefinal/final construction plans and specification submission shall
reflect 95* and 100X completion as outlined herein.

    At 95X completion of design and after all checking and coordinating have
been completed by the A/E, prints shall be furnished to the design PO for
review purposes.  Marked prints and/or written comments will be returned to
the A/E for correction of tracings.  After corrections have been
incorporated, the A/E shall furnish new prints of the corrected sheets and
the original tracings.  The A/E shall also return all the marked-up prints
as evidence that the plans have been completely checked.

    Final specifications shall be submitted by the A/E for review when the
overall project is approximately 95X complete.  After making any necessary
corrections, the typed original specifications shall be sent to the design
PO with the complete design.

    The design analysis and design calculations will be furnished for review
of prefinal design. \After making any corrections required, reproducible
sheets shall be submitted.
                     \
B.I.4  Estimated Cost of Project

    An estimate and estimate summary sheet will be required with prefinal
design submittal (95 percent) and the final bid estimate.  One copy of the
quantity take off sheets, including the appropriate items, i.e., treatment
equipment, linear feet of piping, linear feet of wells, quantity of

                                     B-2

-------
hazardous waste to be removed, etc., will be Included with each estimate
submitted.  All work Items (mobilization, excavating, transportation of
hazardous waste, disposal costs, site containment/rehabilitation, etc.) will
be broken down Into labor, material and plant.  The A/E shall provide basis
for development of all unit prices used 1n the estimate.  Unit prices,
overhead, and profit, and other such categories shall be shown as separate
Items.  The final (bid) estimate will be based on the advertised plans and
specifications Including amendments.  It will Include any changes made by
the design PO during final design review, and should reflect current prices
for labor, material, and equipment.  The final estimate must fit the
specifications bid form .and be submitted to arrive not later than 15 days
prior to the scheduled opening of bids.

B.I.5  Correlating Plans and Specifications

    General correlation between drawings and technical specifications, is a
basic requirement of any set of working construction plans and
specifications.  Before submitting the project specifications, the A/E
shall: (1) Coordinate and cross-check the bid form, specifications and
drawings; (2) Complete the proofing of the edited specifications and
required cross-checking of all drawings and specifications.  These
activities shall be completed prior to the 95% prefinal submittal to the
design PO.

B.I.6  Selection of Resource Conservation and Recovery Act (RCRA) F<-  .ities

    The A/E shall write into the remedial action plans and specifications a
requirement that the contractor shall submit certification that all
treatment, storage or disposal facilities proposed to be utilized by the
contractor for acceptance of hazardous substances have an applicable permit
issued by EPA (or an authorized state) or have applicable interim states
unoer : .:fion 3005(e) of RCRA (or the analogous state provision in an
aiKDC-^-ci state).  Additionally, the contractor shall submit certificatior,
that each treatment, storage or disposal facility has received and passed, a
                                     B-3

-------
RCRA compliance Inspection within the past six (6) calendar months.  (Addi-
tional requirements are forthcoming to address RCRA landfills, focusing on
the effect of the RCRA reauthorlzation.)

B.I.7  Compliance With the Requirements of Other Environmental Laws

    All applicable or relevant standards and criteria identified in the
ROD/EDO shall be analyzed and incorporated into the design by the A/E.
Specific A/E responsibility shall include Identifing the following: (1) The
permitting authority(ies); (2) Construction/operating permits required; (3)
Time required by the permitting agency(ies) to process the appHcations(s);
(4) Fee schedule including filing/application fees, emissions fees,
certification testing, etc; (5) Monitoring and/or compliance testing
requirements; and (6) Actual agency regulations governing applications,
exemptions, variances, etc.

    At the design PO's discretion the A/E may obtain all required
applications forms, complete all technical sections, and provide the
partially completed forms to the design PO.  The A/E shall notify the design
PO of any major discrepancies existing between the A/E SOW and the pollution
abatement criteria.  Copies of all correspondence from permitting agencies
which either details permit requirements or indicates that no permits are
necessary, shall be furnished to the design PO by the A/E.

B.I.8  Equipment Start-up and Operator Training

    The A/E shall prepare, and include in the technical specifications
governing treatment systems, contractor requirements for providing:
appropriate service visits by experienced personnel to supervise the
installation, adjustment, startup and operation of the treatment systems,
and appropriate operational procedures training once the startup has been
successfully accomplished.
                                     B-4

-------
 B.2  Additional  Studies

     Remedial  actions may require additional studies to supplement the
 available technical  data.  At the direction of the PO for any such studies
 required, the A/E shall furnish all  services, Including field work as
 required, materials, supplies, plant, labor, equipment, investigations,
 studies and superintendence.  Sufficient sampling, testing\and analyses
 shall be performed to optimize the required treatment and/or disposal
 operations and systems.  There shall be an Initial meeting of all principal
 personnel involved in the development of the project.  The purpose will be
 to discuss objectives, resources, communication channels, role of personnel
 Involved and  orientation of the site, etc.  The Contractor shall submit an
 interim report for the purposes of review when he 1s approximately 90%
 complete with the testing.  The Interim report shall present the results of
 the testing with the recommended treatment or disposal system (including
 options).  The report shall Include  economic analyses of the various
:•alternatives.  A review conference shall be scheduled after the interim
•report has been  reviewed by all interested parties.  The final report of the
-testing shall include all data taken during the testing, a recommendation
 for a facility to most efficiently provide the treatment or disposal system
 and a cost estimate  of such a facility.

 B.3  Operation & Maintenance Plan

     Remedial  actions vary greatly in scope.  However, in most instances,
 there is a requirement for some degree of regular operation and maintenance
 activity associated  with the completed project.  An Appendix to the State
 Manual will be prepared which discusses the basic elements to be includec ;"
 an Operation  and Maintenance (O&M) Plan.  Appropriate elements are listed
 Exhibit B-l and  should be used by the A/E as a guide in preparing the
 site-specific O&M plan.  An initial  draft O&M Plan shall be submitted by thr
 A/E to the design PO for review and  approval with the prefinal design
 documents. After making necessary corrections, the A/E shall submit the
 final c- aft O&M  plan with the final  design documents.  The O&M plan will be
 finalized and submitted by the Construction contractor at the prefinal
 construction  conference.

-------
                                EXHIBIT B-l                                            »

                                                                                       i

                                                                                       i

Basic Elements of Operation and Maintenance Plan



         A.   Description of Normal Operation and Maintenance


                                                                                       f
              1.   Description of tasks for operation



              2.   Description of tasks for maintenance



              3.   Description of prescribed treatment or operating    ^,              *

                   conditions                      .                                    r



              4.   Schedule showing frequency of each O&M task
                                                                      *


         B.   Description of Potential Operating Problems



              1.   Description and analysis of potential operating problems



              2.   Sources of information regarding problems
                                               a


              3.   Common remedies

                                                                                       ^

         C.   Description of Routine Monitoring and Laboratory Testing                 I



              1.   Description of monitoring tasks                                     \



              1.   Description of required laboratory tests and their                  r
                    • \                                                                  I
                   interpretation


                                                                                       I
              3.   Required QA/QC

                                                                                       i

              4,   Schedule of monitoring frequency and when, if so

                   provided, to discontinue.
                                     B-6

-------
                   EXHIBIT B-l (Contrd)

0.   Description of Alternate O&M

     1.   Should systems fall, alternate procedures to prevent
          undue hazard

     2.   Analysis of vulnerability and additional resource
          requirements should a failure occur

E.   Safety Plan

     1.   Description of precautions, of necessary equipment, etc.,
          for site personnel

     2.   Safety tasks required 1n event of systems failure (May be
          linked to site safety plan developed during remedial
          responses)                            .

F.   Description of Equipment

     1.   Equipment Necessary to plan

     2.   Installation of monitoring components

     3.   Maintenance of site equipment

     4.   Replacement schedule for equipment and Installed
          components

G.   A/E also shall prepare an 02M annual  budget which should
     include but not be limited to the following:

     1.   Cost of personnel
                            B-7

-------
                   EXHIBIT B-l  (Cont'd)





     2.   Costs of preventive and corrective maintenance





     3.   Costs of equipment, supplies, etc.





     4.   Costs of any contractual obligation (e.g., lab expenses)





     5.   Costs of operation (e.g., energy costs, etc.)





H.   Records and Reporting Mechanisms Required





     1.   Dally Operating Logs





     2.   Laboratory Records




     3.   Records for.Operating Costs





     4.   Mechanism for reporting emergencies





     5.   Personnel and maintenance records




     6.   Monthly/Annual Reports to State agencies
                            B-8

-------
           B.4   Quality Assurance  Project  Plan
                	                    ,
  i
               The  A/E  shall  prepare  a site-specific Quality Assurance Project Plan
•  [         (QAPP).   The plan  will  include  a precise description  of the project and
           scope of work.   The  QAPP must provide guidelines  for  project organization
           and  responsiblity  including identification of  quality control  and quality
  1         assurance responsibilities for  the construction contractor, lead design
  i         party, and other appropriate agencies during remedial construction.  In
  4         addition, the QAPP will define  quality assurance  objectives and other
           appropriate  elements to be Included  in the plan based on  Information
  I         provided by  the  design  PO.  The plan shall  later  be used  as a guide by the
           contractor to develop a Contractor Quality Control Plan (CQCP) which must be
           approved by  the  design  PO  before Notice to Proceed is given.   More specific
           guidance will be given to  the A/E if more specific information or detailed
           testing  procedures are  known by the  design PO  and are considered necessary.
           A  detailed discussion of elements to be Included  in a State lead QAPP are
  ;         discussed in draft Appendix L of the State Manual.  QAPPs for federal lead
           and  responsible  party projects  should be consistent with  the guidelines of
           Appendix L.   A draft QAPP  shall  be submitted by the A/E to the design PO
           with the' prefinal  design documents.   After making necessary corrections the
           A/E  shall submit the final QAPP  with the final design documents.

           8.5   Site Safety Plan

               An important aspect of this  project, both  during  design and
           construction, 1s the health and  safety of the  individuals who  will  be on
           site.  The A/E responsible for  the design of this project shall  review the
           project  information  provided and develop specifications for a  Site  Safety
           Plan (SSP) that  are  sufficient  to protect on-site personnel  from the
           physical, chemical,  and/or biological  hazards  particular  to the site.  The
           sped' cations will  describe the minimum health,  safety and emergency
                ie requirements for  which  the  construction  contractor will  be made
              Knsible,  and which must be  included in  the SSP developed  by the
           contractor.   EPA is  developing  an outline for  =, SSP which will  be Included
           in Ap.rndlx  M of the State Manual.   In the  interim, the suggested outline
                                               • E-9

-------
presented in Exhibit B-2 should be used as a guide by the A/E 1n developing
specifications for the SSP.  Draft SSP specifications shall be submitted by
the A/E to the design PO with the prefinal design documents.  After making
necessary corrections, the A/E shall submit the final SSP specifications
with the final design document.

    To ensure consistency with appropriate EPA, OSHA and State health and
safety requirements, the following reference list can be used as guidance in
developing the SSP.

         CERCLA sections 104(f) and lll(c)(6)

         EPA Order 1440.2 - Health and Safety Requirements for Employees
         Engaged in Field Activities
                                                                      i
         EPA Order 1440.1 - Respiratiory Protection

         EPA Occupational Health and Safety Manual
                                                       *-

         EPA Interim Standard Operating Safety Guide
         (September 1982)

         Part 1910 of 29 CFR revised 1 July 1982, OSHA Standards for General
         Industry

         MIOSH, (National Institute of Occupational Safety and Health)
         Manual of Analytical Methods, Volumes I-VII
                    \'
         Threshold Limit Values (TVL) for Chemical Substances and Physical
         Agents in tH* Work Environment with Intented Changes Adopted by
         ACGIH (American Conference of Governmental Industrial Hygienists),
         latest edition

         ANSI 2 38.2 - 1980, American National Standard, Practices for
         Respiratory Protection
                                    B-10

-------
'  j                                         EXHIBIT B-2

  =                           Suggested Outline for Site Safety Plan

  •        1.  The purpose of this section 1s to describe the Information that should
              be addressed 1n each SSP and tailored, to the extent Information Is
              available, to each site.
          2.  Describe the site and known hazards and risks
                   [same as existing discussion]
                   Identify general quantities
                   emphasize the Importance of site description
          3.  Delineate work areas
                   designate where work functions occur narratively and with site map
                   define limitation to work areas
                   (i.e. tools, equipment that is not approriate for use in IDLH
                   atmospheres)
          4.  Identify site control procedures .
                   identify procedures to control site access for non-work party
                   members
                   describe (include map) work zones
          5.  Describe air surveillance procedures
                   describe procedures and instrumentation use to monitor for worker
                   safety
                   [air surveillance strictly for site characterization should be
                   described 1n a site study plan]
          6.  Designate levels of protection
                   describe it for each specific work function
                   explain why level selected
                   describe any modifications, supplements to selected levels
          7.  HescriDe decontamination procedures
                   -;or people, sample bottles, field equipment, cars/drill rigs
                   describe what will be done with spent decon solutions
                                              B-11

-------
                            EXHIBIT B-2  (Cont'd)
 8.  Discuss  procedures,  arrangement for  weather-related problems
         discuss  provisions  for  dealing  with  heat,  cold,  storms  etc.
         discuss  provisions  for  shelters,  rest  areas,  fluid  rejuvenation etc.
 9.  Describe action  plan for a site emergency
         persons  to  contact
         location and map, if necessary, to nearest phone
         location and map, If necessary, to nearest hospital  or  doctor
         phone numbers of emergency contacts
         (rescue, police, fire,  explosive  experts,  etc.)
         how to rapidly  evacuate workers,
         how to rapidly  evacuate nearby  residents.
         situation when  emergency procedures  become applicable [include here
         a reference to  the  example in threshold  for response]
10.  Identify responsibilities for implementing  SSP	
         contractor's responsibilities
         construction inspector's responsibilities
                                    B-12

-------
                  A1r Sampling Instruments for Evaluation of Atmospheric
                  Contaminants, 6th edition, 1983, American Conference of
                  Governmental Industrial Hyg1en1sts.
j
                  Appropriate State health and safety statutes

1         B.6  Architect/Engineer Services During Construction

i             The agency responsible for accomplishing a remedial action may deem it
         desirable or perhaps even necessary that the A/E preparing the .plans and
[         specifications take an active role 1n the on-s1te remedial action
         (construction) work.  Following are guidelines for consideration 1n
r
         utilizing A/E services during construction.

         B.6.1  Review Construction Contractor Submittals
        «*
             The A/E shall check all shop drawings and calculations submitted by the
         Construction Contractor.  The A/E is responsible" for complete review and
         check of the construction shop drawings submitted by the Construction
         contractor for compliance with the requirements of the contract plans and
         specifications.  The preparation of all shop drawings is the responsibility
         of the Construction Contractor.  If submlttals are Incomplete or are
         Insufficient to perform review, the construction PO shall be notified
         Immediately for Instructions.  If deficiencies or errors in the plans and
         specifications become evident in the process of review and checking of the
         submittals, the A/E shall notify the construction PO who will determine the
         course of action to be taken.

         B.7.2  Attend Conferences and Visit Project Site

             The A/E as and when requested in wri*-'ng by the construction PO,  snail
         furnish technically qualified Architects and/or Engineers to attend
         conferenc-s and/or visit the project site before or during construction.
         These services will include writing of reports and/or preparation of
         requirea cost estimates upon return to the A/E office.
                                             B-13

-------
B.7.3  Provide Field Representative

    The A/E shall provide a Field Representative to perform 1n general  the
following:

         Advise the contraction PO on engineering Interpretation of the
         Facility plans and specifications

         Assist the construction PO 1n Interpreting Impact on the design of
         proposed changes and preparing sketches and/or revised drawings 1n
         a timely manner to aid 1n the preparation of construction contract
         modifications.

         Assist the construction PO and A/E's main office staff 1n resolving
         design problems associated with Interpretation of contract plans
        'and specifications.

         Document design field changes tht occur during construction.

         Facility start-up testing shake-down

         Operator training
                                    B-14

-------
   APPENDIX C





LIST OF ACRONYMS

-------
                              LIST OF ACRONYMS

AA                 Assistant Administrator
A/E                Architect/Engineer
CA                 Cooperative Agreement
CQCP               Contractor Quality Control  Plan
CRP                Community Relations Plan
E&O                Engineering and Design
EDO                Enforcement Decision Document
EPA                Environmental Protection Agency
EPA-HQ             EPA Headquarters
FS           •      Feasibility Study
IA6                Interagency Agreement
MOD                Memorandum of Understanding
NPL                National Priorities List
O&M                Operation and Maintenance
OSHA               Occupational Safety and Health Administration
OSWER              Office of Solid Waste and Emergency Response
PO                 Project Officer
PRP                Potentially Responsible Party
QAPP               Quality Assurance Project Plan
RA                 Remedial Action
RCRA               Resource Conservation and Recovery Act of 1976  (PL-94-580)
RD                 Remedial Design
RD/RA              Remedial Design/Remedial Action
RI                 Remedial Investigation
RI/FS              Remedial Investigation/Feasibility Study
RPM                Regional Project Manager (EPA)
ROD                Record of Decision
S&A                Supervision and Administration
SCAP               Superfund Comprehensive Accomplishments Plan
SSC                Suoerfund State Contract
SSP                Site Safety Plan
SOW                Statement of Work
TLV                Threshold Limit Value
TSD                Treatment, Storage and Disposal Facility
USAGE              U.S. Army Corps of Engineers
USACE-MRO          USACE-Missouri River Division

-------
i                                          APPENDIX 0

I                                      GLOSSARY OF TERMS
i

-------
                                  APPENDIX D
                              GLOSSARY OF TERMS
    This  appendix  pr^ides  definitions  of selected  terms  used throughout the
 text.   It 1s  not Intended to  be comprehensive 1n  nature;  rather,  1t attempts
 to  highlight  some  of the terms  commonly used  1n the Superfund remedial
 program.   Statutory definitions have  been quoted  for those terms  defined In
 CERCLA, while other definitions have  been taken from appropriate  EPA
 regulations,  guidance,  and  publications.

 Bidability;   Refers to  the  Inclusion  of all necessary elements and
 specifications of  a design  package  to enable  solicitation and procurement of
 a construction contractor.

 Change  Orders;  A  change order  1s a written order Issued  by the State or
 USAGE to  its  contractor authorizing an  addition,  deletion,  or revision.
 Change  orders are  appropriate when  the  terms  of the contract between the
 recipient and one  of its contractors  must be  altered to make a change in the
 work within the general scope of the  contract as  a  result of changes in
 specifications, time, method  or manner  of performance of  the work,  services,
 site or recipient-furnished facilities,  equipment or materials.

 iuch changes  must  be within the general  scope of  the contract.  The goal  of
•a change  order is  to leave  the  contractor in  the  same relative profit/loss
 situation it  would have encountered under the original contract award.
 Cardir,:   changes or changes which substantially alter the scope of  the work
 under ihe contract may  not  be appropriate for change order  but may  require
 readver;ising for  new bids  or proposals.
                                     D-l

-------
Claims;  A claim Is a request by a contractor for additional time and/or
fees that has been rejected by the State or USAGE.  Rejection of a change
order may lead to a contractor claim 1n which the contractor asserts that,
by either action or Inaction on the part of the recipient, a change was made
In the contract requirements which affected the contract time and/or price
and caused the contractor to perform in a manner different form that
required by the existing contract.  Significant changes which may alter the
remedy approved 1n the ROD require EPA headquarters approval.

Community Relations Plan (CRP); A plan for addressing local citizens' and
officials' concerns about a hazardous waste site and for integrating
community relations activities Into the technical response at a site.  The
CRP should help prevent disruptions and delays in response actions and
partially fulfill the NEPA requirement for public notification and
participation.  Each CRP should Include a description of the background and
history of the site and community concerns about the site; objectives of the
site-specific community relations .program; specific techniques to be used to
achieve those objectives; and a work plan, schedule, budget, and designation
of staff who will be responsible for the program.

Constructability;  Refers to the technical feasibility of a design from an
engineering perspective.

Cooperative Agreement (C/A);  An assistance agreement whereby EPA transfers
money, property, services, or anything of value to a State for the
accomplishment of certain remedial activities, subactivities, or tasks, as
authorized by CERCLA.  It assumes a significant Federal involvement in the
State's performance of these activities.  The remedial Cooperative Agreement
provides general information about the project, such as the approved budget,
and any specific conditions applicable to the project.  It also documents
any required CERCLA section 104(c)(3) assurances.

Deviation Request:  An official written request to allow a deviation from
EPA's General Regulation for Assistance Programs (40 CFR 30).  One example
of a situation requiring a deviation request would be the need to incur
costs at a site prior to the execution of a Cooperative Agreement.

                                     D-2

-------
.,  ,         Enforcement Decision Document (EDO);   Refers to the documentation of the
  i         Agency's  decison-making process for approving remedial actions to be
           Implemented by responsible parties, showing consistency with CERCLA and the
  *         NCP and supplementing the feasibility study if necessary.

  j         Engineering and Design (E&D)  after Contract Award;   EtD after contract award
           1s engineering and design support during the construction/cleanup phase of
  j         the project.  This support 1s provided by the design Architect-Engineering
           or In-house USACE  or State personnel  and can consist of the following:

                    Preparation of design modifications due to design deficiencies,
                    unforeseen site conditions,  client request, or changed criteria.

                    Site  visits and attendance at meetings or  conferences.
  I.
         "Federal Lead;   Means that the EPA has primary responsibility for planning
         * and conducting either part of or an entire removal  or remedial action.

           Feasibility Study;   A study intended  to 1) evaluate alternative remedial
           actions from a technical, environmental, and cost-effectiveness perspective,
           2) recommend the cost-effective remedial action,  3) prepare a cost estimate
           for budgetary  purposes,  and a preliminary construction schedule.

           Interagency Agreement (IAG);   A written agreement,  enforceable by law,
           between EPA and another agency (Federal, State, or  local) where goods  and/or
           services  are provided,  whether or not in exchange for monetary
           reimbursement, or  where policy agreements are delineated.  lAGs for CERCLA
           activities  may function both  as obligating documents and as reporting
           documents necessary for EPA financial and program management.

           Memorandum  of  Understanding (MOU);  An agreement  between EPA and another
           agency  (Federal, State,  or locai)  that sets forth basic policies and
           procedures  governing their relationship on mat"~-s  of mutual  interest  and
           responsibility.  There  is no  exchange of funds * .:ier this type of
           agreement.   In the  context of this  document,  an MOD usually refers to  one
                                               D-3

-------
type of agreement which may  be negotiated between  EPA and a State to
undertake EPA-lead remedial  planning  subact1v1t1es.

National Contingency Plan  (NCP) 40  CFR  Part  300:   Officially known as the
National Oil  and Hazardous Substances Pollution  Contingency Plan, outlines
the responsibilities and authorities  for  responding  to releases  into the
environment of  hazardous substances and other  pollutants  and contaminants
under the statutory authority of  CERCLA and  section  311 of the Clean Water
Act CCWA),

National Priority list:  A list of  the  highest priority releases or
potential releases of hazardous substances,  based  upon State and EPA
regional submissions of candidate sites and  the  criteria  and methodology
contained in  the Hazard Ranking System  (HRS),  in order to allocate funds for
remedial and  planned removal actions.

Operation and Maintenance  (O&M);  Refers  to  the  requirement for  continued
performance of  activities, as necessary,  at  a  site, after  the completion of
remedial action or construction to  ensure the  sustained effectiveness of the
.applied remedy.

Project Officer (PO):  The official designated by  the lead party for RD or
RA who coordinates, monitors and  manages  RD  or RA  activities for the site.

Record of Decision (ROD);  .Refers to  the  documentation of the Agency's
decision-making process for  approving Fund-financed  remedial actions,
showing consistency with CERCLA and the NCP  and  supplementing the
feasibility study if necessary.   The  ROD  supports  future  cost recovery
actions at the  site.

Remedial Action (RA);  A subactivity  in remedial response involving actual
 implementation, following  design, of  the  selected  source  control and/or
off-site remedial measure.
                                     0-4

-------
Remedial Design (RD);  A subactivity 1n remedial response where the selected
remedy 1s clearly defined and/or specified 1n accordance with engineering
criteria (I.e., a site action plan, a relocation plan, or engineering
drawings and specifications) In a bid package, enabling Immediate
Implementation of the remedy.

Remedial Investigation (RI);  The portion of a subactivity 1n remedial
response Involving an investigation to gather the data necessary to:  (a)
determine the nature and extent of problems at the site; (b) establish
remedial response criteria for the site; (c) identify preliminary
alternative remedial actions; and (d) support the technical and cost
analyses of the alternatives.  (The entire subactivity is known as "remedial
investigation/ feasibility study.")

Remedial Project Manager (RPM);  The designated EPA Regional official who
coordinates, manages, and monitors site activities covered in both EPA and
State-lead remedial response agreements.

Remedial Response;  A series of activities and subactivities intended to
provide permanent resolution of a release or potential release of a
hazardous substance from a site.  Remedial response generally Includes the
following sequence of subactivities:  remedial investigation/feasibility
study, remedial design, remedial action, and operation and maintenance.

Remedy (statutory definition):  [An action] consistent with permanent remedy
taken ... in the event of a release or threatened release of a hazardous
substance into the environment, to prevent or minimize the release of
hazs"-1  "i substances so that they do not migrate to cause substantial danger
to present or future public health or welfare or the.environment.  The term
indue    but is not limited to, such actions ... as storage, confineme t,
:,r.-_     protection using dikes, trenches, or ditches, clay cover,
---> •   •    lion, cleanup of released hazardous substances or contaminated
••.  -         •ecycling or reuse, diversion, destruction, segregation of
re     _ Bastes, dredging or excavations, repair or replacement of leaking
                                     D-5

-------
containers, collection of leachate and runoff, on-s1te treatment or
Incineration, provision of alternative water supplies, and any monitoring
reasonably required to assure that such actions protect the public health
and welfare and the environment.

Responsible Party (statutory definition):  [Includes] (1) the owner or
operator of a vessel (otherwise subject to the jurisdiction of the United
States) or a facility, (2) any person who at the time of disposal of any
hazardous substance owned or operated any facility at which(such hazardous
substances were disposed of, (3) any person who by contract, agreement, or
otherwise arranged for disposal or treatment, or arranged with a transporter
for transport for disposal or treatment, of hazardous substances owned or
possessed by such person, by any other party or entity, at any facility
owned or operated by another party or entity and containing such hazardous
substances, and (4) any person who accepts or accepted any hazardous
substance for transport to disposal or treatment facilities or sites
selected by such person, from which there is a release, or a threatened
release which causes the Incurrence of response costs, of * hazardous
substance, [the responsible party] shall be liable for — (A) all costs of
removal or remedial action Incurred by the United States Government or a
State not inconsistent with the National Contingency Plan; (B) any other
necessary costs of response Incurred by any other person consistent with the
National Contingency Plan; and (C) damages for injury to, destruction of, or
loss of natural resources, including the reasonable costs of assessing such
Injury, destruction, or loss resulting from such a release.

Responsible Party Lead;  Means a private party (owner, operator) has primary
responsibility for planning and conducting a remedial action.

Scope of Work;  The element of a Federal lead remedial planning agreement
which generally outlines the subactivities, tasks, and subtasks to be
undertaken at the site.  The scope of work also provides general information
on the objectives of the project.
                                     D-6

-------
         Site (also refers to a hazardous substance site or a hazardous waste site):
         An area or a location at which hazardous substances have been stored,
         treated, disposed, placed, or otherwise came to be located.  This Includes
         all contiguous land, structures, other appurtenances, and Improvements on
         the land used for treatment, storage, or disposal of hazardous substances.
         A site may consist of several treatment, storage, or disposal facilities
         (e.g., Impoundments, containers, buildings, or equipment).

         State Lead;  Means the State has primary responsibility for planning an
         conducting a remedial action.

         State Letter of Request;  The letter, sent from the administrator of the
         State pollution control agency to an EPA Regional Administrator, requesting
         EPA action at a waste site.  A letter of request can initiate only EPA lead
         remedial planning activities.  The letter must refer to and generically
        'approve the required remedial subactivities, agree to participate in
        ••implementing the Community Relations PI an Design ate a State Project Officer
        •for the project, and state that State officiaUjtiVLmeet with EPA personnel
         to exchange site and project information.

         State Project Officer (SPO);  The designated State official responsible for
I         direct management of the activities covered in a Cooperative Agreement or
         for ensuring that the State carries out responsibilities defined in an EPA
I         lead remedial response agreement.

j         Statement of Work (SOW);  The element of a remedial response agreement that
         specifies in detail the subactivities, tasks, subtasks, and objectives to be
j         performed pursuant to that agreement.  The SOW should contain salient points
'         regard- r,g the background of the release or potential release, problem
i         definition, purpose of the work, and a description of the services to be
         performed.
\
I         SHcr; W.- * Order:  A form prepared by an Ordering Officer, OSC, or
         Cor:  - :t -
-------
Super-fund State Contract (SSC);  A bilateral contract between EPA and a
State that 1s legally binding on both parties.  The SSC 1s not a procurement
contract, but 1s used to document EPA and State responsibilities and to
obtain any necessary State assurances for EPA-managed remedial responses.
An SSC 1s appropriate for any EPA lead remedial Implementation subactivities
which require State cost-sharing.

Supervision and Administration (S&A);  S&A consists of supervision and
administration of the construction/clean up contract.  This is primarily
accomplished by USAGE or State In-house personnel, but assistance from the
design Architect/Engineer may be required.  Specifically S&A includes the
following:

         Contract Administration

         Site inspection and construction management performed by on-site
         personnel

         Shop drawing review

         Preparation of as-built drawings reflecting final completed project
         conditions.
                                     D-8

-------
REFERENCES

-------
\
                                             REFERENCES

V
   <•
            1.  U.S. EPA, "State Participation in Superfund Remedial Program," February
   r            1984.

            2.  "Draft Policy on CERCLA Compliance with the Requirements of Other
                Environmental Statutes," Appendix to National Oil and Hazardous
                Substances Pollution Contingency Plan, Proposed Rule, (50 FR 5928),
                February 12, 1985.

            3.  Hedeman, William N., "Requirements for Selecting An Off-Site Option in a
                Superfund Response Action," U.S. EPA Memorandum, January 28, 1983.

            4.  U.S. EPA, "Superfund Community Relations Handbook," September 1983.

-------