OCT. !' --"^DM   TPQ HQ LIBRflRY       •                   NO.573   P.2/19
          906R89102                                 t\150&
F°*^%   '0/^N.iCu «,~,~ ENVIRONMENTAL PROTECTION AGENCY   _ %

 —**- I,- .  ,               OFFICE OF INSPECTOR GENERAL                J "''
 % ««* U ^ FM//£tfU.:.r.             SOUTHERN DIVISION, SUITE 278            REGIONAL OFFICE:
        A/Ste""'»**TOML Mnir/»Tr/U.  1375 P6ACHTRE6 STREET, N.E.            1448 R038 AVENUE, SUITE 1200
       AGCNCY        r"VltmON   ATLANTA, QEORGIA 30309             DALLAS, TEXAS 76202-8733
       ~               .^          (404) 347-3623 AUDIT               (214) 656^621 AUDIT
                    ;^T       (404) 347-2396 INVESTIGATIONS            (214) 66S4610 INVESTIGATIONS

                 7520?
                               December 13, 1989
      MEMORANDUM

      SUBJECT:       Audit  Report No. E5BGL9-06-0134-0100079
                     Interim Audit Sikes'Disposal 'site No.  22
                     Superfund Cooperative Agreement  V006450-01
                     Texas  Water Commission - Austin,  Texas
                     March  l,  1986 through June 30/ 1989
      FROM:           Jack  Carrington
                     Audit Manager (eiq)
                                      \J
      TO:             William B,  Hathaway
                     Assistant Regional Administrator  (6M)


      SCOPE  AND OBJECTIVES

      We have completed an interim audit of Cooperative Agreement
      VQ06450-01 (agreement)  awarded June 28, 1982 to  the Texas
      Department of Water  Resources,  the predecessor agency to the
      Texas  Water Commission (TWC),  Austin, Texas.  The agreement
      provided for performing site investigation, feasibility study and
      remedial design at the Sikes Disposal site in Crosby,  Texas.

      The  purpose of our audit was to determine whether:

           * the costs claimed under the cooperative agreement were
             reasonable, allowable and allocable to the sponsored
             project;

           % the controls  exercised by the TWC through its  financial
             management, accounting,  procurement, contract  administra-
             tion and property management systems were adequate to
             provide assurance that .the costs claimed  were  reasonable,
             allowable and allocable to the cooperative agreement.

      Our  audit was conducted from July 31 to August 18,  1989 for the
      period March 1, 1986 to June 30, 1989.  The results of audit were
      discussed with the grantee's representatives on  August 18,  1989.

      Field  work at the consultant engineer offices was performed
      September 11 through 14,  1989.   We relied on the work of the
      engineer's external  auditors for indirect cost rates  after making
      supplemental tests of the work conducted.  Additionally,  we
      reviewed the external auditors  summary working papers and
      compared their methodology to that used in prior indirect cost
      audits by the Office of Inspector General.
                                                   HEADQUARTERS UBRARY
                                                   ENVIRONMENTAL PROTECTION AGENCY
                                                   WASHINGTON, D.C. 20460

-------

-------
OCT. 5.2000   1:14PM   EPP HQ LIBRfiRY       «                  NO.573   P.3/19
    We performed the audit in accordance with the Ggv^rnment Auditing
    Standards (1988 Revision) issued by the Comptroller General of
    the United states and included tests of the accounting records
    and other audit procedures we considered necessary.  In addition,
    40 CFR Parts 30 and 33, OMB Circular A-87, EPA "Letter of Credit
    Users Manual" and "State Participation In the superfund Remedial
    Program" were used as criteria in evaluating the actions taken
    under the cooperative agreement.

    We did not specifically review TWC's system of internal
    accounting controls.  However, nothing came to our attention that
    indicated the TWC's internal accounting controls were not
    adequate for EPA purposes.

    The Sikes agreement was audited previously.  Audit Report No.
    E5b<36-06-0127-6l257 was issued July 30, 1986.  The prior audit
    reviewed expenditures of $1,000,766 claimed during the period
    July 1, 1982 through February 28, 1986.  Unresolved recommen-
    dations and set aside costs will be identified in the findings of
    this report.

    SUMMARY OF FINDINGS

    In our opinion, the costs summarized below and presented in
    Exhibit A present fairly the financial information in accordance
    with the financial provisions of the cooperative agreement and
    generally accepted accounting principles.

                         	COSTS	
                                               Questioned
    Project Phase         Claimed_   Accepted  Ineligible   Unaudited
    Current Audit:
    Remedial Invest./
    Feasibility Study* $  246,073  $ 189,9791  $ (1,608)    $  57,702
    Remedial Design*      915,959     783,360       561       132,038
    Prior Audit:
    Remedial Invest./
    Feasibility Study*  1.000.766     776.9S2     7.730       216.054

      TOTAL            52.162.798  $1.750.321    36.683     S 405.794

    *Federal Share 100%

    Accounting System

    The TWC accounting and financial management system was adequate
    for tracking expenditures as required by 40 CFR 30 and OMB
    Circular A-87.  Generally, we found that the agency was
    accurately reporting allocable and allowable project costs,
    supported by backup documentation.

-------
OCT. 5.2000   1:15PM    EPfl HQ LIBRRRY       •                  NO.573   P.4/19
   Contract Administration

   Prior audit reports  of cooperative  agreements  identified
   contractor labor  cost  documentation as a problem area.   We
   recommended TWC require  the  contractor to  include the employee's
   name, salary, title  and  dates worked on the project to  assure
   costs were supportable by  the books and records  of the
   contractor.

   In response to the recommendation TWC notified the contractors  to
   include the information  on their invoices,  our  review  of
   consultant engineer  invoices found  the problem had been
   corrected.  Contractors  were providing the requiredi information
   and billing in accordance  with contract terms.

   Procurement

   Prior audit reports  of cooperative  agreements  (E5bG7-06-0031-
   71311 BioEcology, June 9,  1987, and E5bG7-06-0033-713l2 Triangle
   Chemical, June 9, 1987)  identified  Record of Negotiation as  a
   problem area.  TWC was provided a draft of these reports for
   review and comments  on March 3r 1987.  We recommended that EPA
   require TWC to prepare a summary record of negotiation.  This
   record was to contain  sufficient detail to reflect the
   significant considerations controlling the establishment of  price
   and other terms of the contract.  On May 20, 1987,  TWC  provided
   comments to our reports  which included as Attachment 2,  A
   "Summary Record of Negotiations".   Our review  determined the
   prior audit recommendation had not  been implemented.

   40 CPR 33.250 states in  part that:

        a) procurement  records  and files for procurement in excess
           of $10,000 shall include the following:  -  - -;  and (5)
           Basis for award  cost or price, including a copy of the
           cost or price  analysis made under 33.290 and
           documentation  of negotiations.

   Review of the project  files  for the Sikes Disposal Pits and  the
   BioEcology Site (both  of which had  prior audits)  showed that  TWC
   had generally maintained documentation as required by 40 CPR
   33.250.  However, we found that a summary record of negotiations
   had not been prepared.   The  files contained memorandums relating
   to the negotiations.   However, these memorandums had not been
   pulled together to provide a summary of the results of
   negotiation.

   As stated in the prior audit reports, a summary  record  of
   negotiations would improve existing documentation  and provide a
   readily assessable means of  demonstrating that a fair and
   reasonable price was obtained.

-------
OCT. 5.2000   irlSPM    EPfl HQ LIBRPRY       •                   NO.573   P.5/19 .
   Recommendation

   We again recommend that EPA require TWC to prepare a summary
   record of negotiations setting forth the principal elements of
   negotiations.  This record should contain sufficient detail to
   reflect the significant considerations controlling the
   establishment of price and other terms of the contract.

   Agency Comment

   The TWC submitted attachments outlining a Summary Record of
   Negotiations.  This record is comprised of:  Record of Selection,
   Cost and Price Consideration, Record of Negotiation, and
   Negotiation Summary.  TWC indicated that the summary record will
   be made a part of the contract files.

   Audit Comment

   As recommended in prior reports,  TWC was requested to provide a
   summary record of negotiations for procurements.   EPA should
   ensure that TWC completes and includes the record of negotiation
   forms in appropriate contract files.

   Property Management

   The TWC's property management system was in compliance with the
   requirements of 40 CFR 30.531.  We found that the agency records
   provided the required information.  Property purchased with
   Federal funds was accounted for in the FY 1988 inventory.

   Indirect Coats

   The prior audit recommendation to include a contract provision
   for downward adjustments to ceiling rates when actual audited
   rates were determined to be less had been implemented.

   Our review found contract amendments to include the recommended
   provision.

   Better of Qredit Drawdowns

   TWC's letter of credit drawdowns complied with the Letter of
   Credit Users Manual.  Drawdowns were timed closely to the actual
   financial needs of the agency and  withdrawals did not exceed the
   amount of funds needed.

   Questioned Equipment cost

   The prior audit of the Sikes Cooperative Agreement included
   unresolved equipment costs,   our review determined the purchase

-------
OCT. 5.2000   1:16PM   EPfi HQ LIBRRRY       -                  NO. 573   P.6/19
   $9,999 micro  film reader/printer was  ineligible for EPA
   participation under the Sikes Cooperative Agreement.   See Exhibit
   A, Note 2.
               fr

   ACTION REQUIRED

   In accordance with EPA Order 2750f the action official is
   required to provide this office with  a copy of  the  prpposed
   determination on the  findings within  150 days of the audit report
   date.
   BACKGROUND

   The "Superfund" program was established by the  Comprehensive
   Environmental Response, Compensation and Liability  Act  of 1980
   (CERCLA), Public Law 96-510, enacted on December  11,  1980.   The
   Superfund program was created to protect public health  and the
   environment from the release or threat of release,  of hazardous
   substances from abandoned hazardous waste sites and other sources
   where response was not required by other Federal  laws.  A Trust
   Fund was established by CERCLA to provide funding for responses
   ranging from control of emergency situations to provision of
   permanent remedies at uncontrolled sites.  CERCLA authorized a
   $1.6 billion program financed by a five-year environmental tax on
   industry and some general revenues.  CERCLA requires  that
   response, or payment for response, be sought from those
   responsible for the problem, including property owners,
   generators and transporters.

   CERCLA was revised and expanded by the Superfund  Amendments and
   Reauthorization Act of 1986 (SARA), Public Law  99-499,  enacted on
   October 17, 1986.  SARA reinstituted the environmental  tax and
   expanded the taxing mechanisms available for a  five-year  period.
   It authorized an $8.5 billion program for the 1987-1991 period.
   The Trust Fund was renamed the Hazardous Substance  Superfund.

   The basic regulatory blueprint for the Superfund  Program  is the
   National Oil and Hazardous Substances Contingency Plan  (NCP), 40
   CFR Part 300.  The NCP is composed primarily of sites which have
   been ranked on the basis of a standard scoring  system which
   evaluates their potential threat to public health.  In  addition,
   each state was allowed to name its highest priority site  without
   regard to the ranking system.

   CERCLA section 104(c)(3)  provides that no remedial  actions  shall
   be taken unless the state in which the release occurs enters  into
   a contract or cooperative agrement with EPA to provide  certain

-------
OCT. 5.2000   1:17FM    EPfl HQ LIBRRRY        •                  NO.573   P.7/19
   pay ten percent of the costs of remedial action.  Pre-rewedial
   activities (preliminary assessments, site inspections) remedial
   planning (remedial investigations, feasibility studies, remedial
   designs) and'removals may be funded 100 percent by EPA.

   For facilities operated by a state or political subdivision at
   the time of disposal of hazardous substances, the state must pay
   at least 50 percent of all response costs, including removals and
   remedial planning previously conducted.

   The cooperative agreement was entered into by EPA, Region 6 and
   the Texas Department of Water Resources, the predecessor agency
   of the Texas Water commission.  The agreement provided for
   remedial investigation/feasibility study, and remedial design at
   the sikes Disposal Pits site located 4 miles southwest of Crosby,
   Harris County, Texas.  The initial cooperative agreement of
   $476,000 was awarded on June 28, 1982 and provided funds for the
   remedial investigation at the site.  Fourteen amendments were
   made to the initial agreement.  These amendments primarily
   provided for:

     • supplemental sampling
     • funds for design of the remedial action for the site
     • total project costs of $33,457,110 with a state share of
       $3,120,000.

   The Sikes Disposal Pits site is located on a 185 acre site,
   approximately 2 miles southwest of Crosby, Texas.  It is bordered
   by the San Jacinto River on the west,  Jackson Bayou on the north,
   and U.S. Highway 90 on the south.   The area immediately
   surrounding the site is largely undeveloped with numerous active
   and abandoned sand pits and low-lying swampy areas.

   Some commercial timber operations and mineral exploration have
   been conducted in the past.  The area plays host to sport
   fishermen as well as water sport enthusiasts on nearby San
   Jacinto River and Jackson Bayou.

   One family lives on site.  The Riverdale Subdivision, 500 feet
   southwest of the site, is the only residential development in
   close proximity of the site.

   The site completely lies in the 100 year flood plain of the San
   Jacinto River, while portions lie within the 10 year and 50 year
   flood plains.  The site has been flooded four times since 1969.

   Alluvial sand deposits, ranging from 0,7 to 34 feet thick,
   underlie the site and form a shallow aquifer.  Many of the local
   inhabitants rely on this aquifer for drinking water.  The Sikes
   Disposal Pits site began operation as a waste depository in the
   early 1960's and closed in 1967.  During this period, a variety

                                   6

-------
OCT. 5.2000   1:17PM   EPfl HQ LIBRfiRY       •                  NO. 573   P.8/19
    of chemical wastes from area petrochemical industries were
    deposited on. site in several old sand pits.  Numerous drums of
    wastes were also left on the property.
                f
    The dike around the unlined main waste pit was not adequate to
    withstandthe periodic flooding of the site,  rioodwaters have
    breached the dike and transported wastes across a large, low
    lying area east of the main waste pit.

    Preliminary sampling at the site in 1982 indicated the presence
    of phenolic compounds, xylene, benzene, creosote, toluene and
    other organics.  Approximately 440 cubic yards of phenolic tars
    were removed from a partially buried pit in June 1983.

    Following completion of the original RI activities and prior to
    submission of the final RI document, work began on the
    Feasibility Study (FS) (October 1984).  Several data gaps were
    identified in the RI that were essential for the development of
    the FS.   The decision was to finalize the RI Report and conduct a
    supplemental sampling program.  Field work for the supplemental
    sampling activities began in July 1985.  The final Addendum RI
    Report for these field activities was submitted in June 1986.
    The FS was received in June 1986.

    Several  waste areas have been identified as being sources of
    contamination.   The contamination is broken down as waste or
    sludges  and underlying contaminated soils.

    Sludges  on site are composed of the wide variety of organics.
    Soils underlying the waste areas appear to be significantly
    contaminated to depths ranging from 3  to 18 feet beneath the
    sludge/water/soil interface.   Contaminants found in the
    underlying soils are similar to those found in the overlying
    sludges.

    A  summary of the general definitions utilized in our report is:

         Cost Audited:  The TWC's total claimed cost for the subject
                       agreement submitted to us for our review.   The
                       auditee's total claimed cost was $1,162,032
                       for the period covered by this audit.

         Questioned Cost:  A cost that is questioned because of:

            1.  Ineligible cost—an alleged violation of a provision
                             of a law,  regulation,  contract,
                             grant,  cooperative agreement,  or
                             other agreement or document
                             governing the expenditure of
                             funds.

-------
OCT. 5.2000  1:18PM   EPS HQ LIBRPRY       •                  NO.573   P.9/19
           2,  Unaudited cost—a finding that, at  the time of the
                              audit, the cost is  not supported
                              by adequate documentation and/or
                              has not been approved by responsible
                              program officials.

           3.  unnecessary/unreasonable cost—a  finding that an
                                             expenditure of funds
                                             resulted in an
                                             expenditure that was
                                             not  necessary or was
                                             not  reasonable.
                                   8

-------
  OCT.  5.2000   1:18PM
     EPfl HQ LIBRflRY
NO.573
                                                                 P.10/19 .
                                 Exhibit A

             Summary of Costs Claimed, Accepted  and  Questioned
                 *• Superfund Cooperative Agreement V006450-01
                          Sikes Disposal Pits Site
                    March 1, 1986 through June 30, 1989
                           Texas Water Commission
                               Austin, Texas

                                      COSTS

Personnel
Fringe Benefits
Travel
Supplies
Contractual
Other
Indirect Costs
Total Current $1
Prior Audit $1
Current Review
Total $2
Claimed
$ 88,745
20,147
27,899
246
979,203
756
45f 036
,162,032
,000,766

,162,798
Questioned
Accepted Ineligible
$ 88,745 $
13,829
27,899
246
811,402
756
30.462
$973,339
$691,597
$ 85.385
$1,750.321

(258)




f789)
$(1,047)

$7.730
$6.683
Prior
Unaudited Set Aside
$
6,576


67,801

15.363
$189,740
$309,169
$216.054 f309r!69>
$405.794
100% Federal

Federal Funds
  Received
  6/30/89

Balance Unpaid
     Notes
$2.082.363

   $80.435
      1.  Increase in accepted costs resulted from the use of
          audited and/or negotiated fringe and Indirect cost rates
          for the periods 1986 through 1988.

      2.  Questioned costs represent fringe benefits and indirect
          cost for TWC's Fiscal Year 1989.  These costs of $6,576
          and $15,363 are classified as unaudited until an audit
          and/or negotiation is completed of TWC's FY 89 fringe and
          indirect cost rates.

      3.  Current audit contractual costs of $167,801 and prior
          audit set aside contractual costs of $216,054 were not
          audited.  These subcontractor costs require audit by the
          Defense Contract Audit Agency as the cognizant Federal
          agency.
                                                                      1  &  2



                                                                        3

                                                                      1  &  2
                                                                      1,3&4

-------
OCT. 5.2000   1:19PM    EFfl HQ LIBRflRY       •                  NO.573   P.11/19
    4,  Equipment costs set aside of $9,999 in our prior audit
        were questioned as ineligible.  The justification for
        purchase did not demonstrate a site specific need.
        Region 6 did not approve the purchase.  This equipment
        provided limited site specific benefit.

        A micrographic reader/printer was purchased by TWO as
        an upgrade to their micrographic capabilities.  The
        equipment was located in the Central Records Office and
        has been there since it was received.  Superfund records
        made up only ten percent of Central Records files and
        microform.  A summary of net ineligible costs is:

        Questioned equipment cost                     $9,999
        Increase in prior audit fringe, indirect cost (2.269)
           Net ineligible cost                        $7.730

        Total TWC costs of $85,385 from the prior audit were
        accepted based on our current review.

   Agency Comment

   The TWC did not provide comments on the questioned cost.
                                  10

-------
  OCT. 5.2000   1:19FM    EPS HQ LIBRflRY       -                   NQ 5?3   p



                     TEXAS WATER COMMISSION         '"'"     *

                                                             APPENDIX A
B. J. Wynne, HI, Chairman  -              ,'~ ; ~^fffit          John J. Vay, General Counsel
John E, Birdwell, Commissioner              \j'.-ia*r,':j/          Michael E. Field, Chief Hearings
Cliff Johnson, Commissioner                 "**=*£=*r           Brenda W. Foster, Chiel Clerk

                           Allen Beinke, Executive Director

                            December 4, 1989
   United States Environmental Protection Agency
   Mr.  Jack Carrington,  Audit Manager
   Office o£ Inspector  General
   1445 Ross Avenue,  Suite 1200
   Dallas, Texas  75202-2733

   Re:   Reply to Draft  Interim Audit
        (A) Superfund Cooperative Agreement V-006452-01
        Bio Ecology System Site Draft Audit
        Report No.'ESBGL-9-06-0133

        (B) Superfund Cooperative Agreement v-006450-01
        Sikes Disposal  Pit Site Draft Audit
        Report No. ESBGL-9999-06-0134

   Dear Mr. Carrington:

   The  Superfund section of the Texas Water Commission offers the
   following comments in reply to your letter of  October 25, 1989,
   advising us of the draft reports on the above  referenced audits.

   A.    Summary of findings/costs;
        No Comment

   B.    Accounting System:
        No Comment

   C.    Contract Administration;
        No Comment

   D,    Procurement;
        Enclosed is attachment 1  outlining the Summary Record of
        negotiations.  This record is comprised of:

        1.   Record of Selection
        2.   Cost and Price Consideration
        3.   Record of Negotiation
        4.   Negotiation Summary  # 	.
  The  summary record of negotiations will be made  a part of the
  contract files.

  B.    Property Management:
        No Comment
                                  11

-------
OCT. 5.2000   l:20PM   EPP HQ LIBRRRY       •    .               NO.573   P.13/19
  Mr.  Jack Carrington
  December 4,  1989
  Page Two                                         APPENDIX A
  F.    indirect Costs;
       No  Comment

  G.    Letter  of Credit drawdowns;
       No  Comment

  H.    Questioned Equipment Costs;
       No  Comment

  Thank you  for the  opportunity to  offer our comments to the draft
  report on  the tentative report material of your audit review dated
  October  25,  1989.   The Superfund  Section feels that the changes
  outlined above will effectively address the draft report
  concerns regarding the TWC Procurement Process.

  Sincerely,
 stemes A. Feeley,  Chief
 Superfund and Emergency  Response  Section
 Hazardous and Solid Waste Division

 DE/jf

 attachments

 cc:  James Fowler, Internal Auditor,  TWC
                                  12

-------
OCT. 5.2000   l:£0PM   EFR HQ LIBRfiRY       '                    NO.573   P.14/19


                                                        APPENDIX A

                                                        APPENDIX 1
                                                        Page 3  of 7
                              ATTACHMENT  1

                     SUMMARY RECORD OF NEGOTIATIONS
                                     13

-------
OCT. 5.2000  l:20PM   EPfl HQ LIBRflRY
                                                        NO.573   P.15/19

                                                      APPENDIX A
                                                      APPENDIX 1
                                                      Page 4 of 7
                          RECORD  OF SELECTION

             Copy of LOED approval
             Copy of Affidavit of Publication
             List of firms requesting  of  RFP
             Site visit attendance  list
             List of proposals disqualified;  justification for
             disqualification
             Score sheets from all  members  of review committee for
             all proposals
             Firms.on Short List  identified
             Copy of letter requesting Executive Summary
             Copy of Executive Summaries
             Copy of Commission agenda request
             Copy of Commission meeting agenda
             Copy of RFP from firm  selected
                                    14

-------
OCT. 5.2000   l:21PM   EPA HQ LIBRflRY
                    COST  AND  PRICE'CONSIDERATION
                                                        HO.573
                                     P.IS/19
                                                     APPENDIX A
                                                     APPENDIX 1
                                                     Page 5 of 7
  Project
  A/E Firm
  Types of Services
  Total Contract Amount
  Type of Contract.  	
CPFF
LUMP SUM
OTHER
  The following items have been  reviewed for administrative
  completeness and for reasonableness:
       	  5700-41 Form for prime  is  provided
       	  5700-41 for subcontractors $10,000
       	  Total manhours
       	  Distribution of manhours
       	  Profit (attach Profit Analysis Forms)
              Travel  (mileage  rates,  rooms,  meals,  etc,  are in
              conformance with TWC policy
              Equipment & supplies
              Laboratory fees
              Costs identified in 5700-41 forms  are consistent with
              the contract
              Project schedule
                                 15

-------
OCT. 5.2000  l:21FM   EPfl HQ LIBRPRV
                                                          NO.573    P.17/19
                         RECORD OF NEGOTIATION
                                                       APPENDIX A

                                                       APPENDIX  1
                                                       Page 6  of 7
              Copy of original  draft contract

              Summary of changes
              (Separate attachment each revision)

              Copy of final  contract
                                   16

-------
  OCT. 5.2000   l:21PM    EPfl HQ LIBRRRY
                                                            NO.573    P.18/19
                   NEGOTIATION SUMMARY NO.
                                                     APPENDIX A
                                                     APPENDIX 1
                                                     Page 7 of 7
                                                                               &*•
                                                                               *„>:=;
                                                                               *•*»<
Project
A/E Firm
Project Officer
                                                                               •'.«««
Date  revision requested          	
Date  revision received 	
	 Copy of changes
	 Copy of correspondence concerning change

                                  17

-------
 OCT. 5.2000  I.'SIPM   EPfl HQ LIBRflRY        •                  NO. 573   P. 19/19
                                                         APPENDIX B
                           Distribution
                 «•
Region
Assistant Administrator for Planning and Management  (6M)
Hazardous Waste Managment Division Director
Audit Followup  Coordinator

Headquarters
Director, Grants Administration Division (PM-216)
Anditea
SuperFund and Emergency Response Section,
  Texas Water Commission
                                                                           ... J
                                                                            I
                                 IB

-------