906R98101
New Source Review

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
                               TABLE OF CONTENTS
                                                                   Page
PART I - PREVENTION OF SIGNIFICANT  DETERIORATION  (PSD)  REVIEW
Chapter A - Applicability
III
. Introduction 	
. New Source PSD Applicability Determination 	
A. Definition of Source 	
B. Potential to Emit 	
1. Basic Requirements 	
2. Enforceabi 1 i ty of Limits 	
3. Fugitive Emissions 	
4. Secondary Emissions 	
5. Regulated Pollutants 	
6. Methods for Determining Potential to Emit . . .
C. Emissions Thresholds for PSD Applicability 	
1. Major Sources 	
2. Significant Emissions 	
D. Local Air Quality Considerations 	
E. Summary of Major New Source Applicability 	
F. New Source Applicability Example 	
. Major Modification Applicability 	
i"^.'*1 *u/flp1:f vi ties That Are Not Modifications 	
•i,1, iC tt,'^ ^ i^ tl, '
'*'B! Vyฃ|T^sions Netting 	
"W&P/Hjyif M'l Accumulation of Emissions 	
2'$ -' '•ฃ. ' Contemporaneous Emissions Changes 	
3. Creditable Contemporaneous Emissions Changes. .
4. Creditable Amount 	
5. Suggested Emissions Netting Procedure 	
6. Netting Example 	
A.I
A. 3
A. 3
A. 5
A. 5
A. 5
A. 9
A. 16
A. 18
A. 19
A. 22
A. 22
A. 24
A. 25
A. 26
A. 28
A. 33
A. 34

A. 34
A. 36
A. 37
A. 38
A. 40
A. 44
A. 51

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                        TABLE OF CONTENTS  -  Continued
                                                                   Page
 IV.   General  Exemptions	A.56
      A.     Sources and Modifications After August 7, 1980. .  .   .  A.56
      B.     Sources Constructed Prior to August 7, 1980 	  A.56

Chapter B - Best Available Control  Technology

  I.   Purpose	B.I
 II.   Introduction	B.4
III.   BACT Applicability	B.4
 IV.   A Step by Step Summary of the Top-Down Process	B.5
      A.     STEP 1--Identify All  Control Technologies 	  B.7
      B.     STEP 2--Eliminate Technically Infeasible Options.  .   .  B.7
      C.     STEP 3--Rank Remaining Control Technologies by Control
           Effectiveness	   B.7
      D.     STEP 4--Evaluate Most Effective Controls and Document
            Results	B.8
      E.     STEP 5--Select BACT	B.9
V.     Top-Down Analysis: Detailed Procedures	B.10
      A.     Identify Alternatives Emission Control Techniques  .   .  B.10
            1.    Demonstrated and Transferable Technologies.  .   .  B.ll
            2.    Innovated Technologies	B.12
            3.    Consideration of Inherently Lower  Polluting
                  Processes	B.13
            4.    Example	B.14

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                        TABLE OF CONTENTS - Continued
                                                                   Page
      B.     Technical  Feasibility Analysis	B.17
      C.     Ranking the Technically Feasible Alternatives to
            Establish  a Control  Hierarchy 	   B.22
            1.     Choice of Units of Emissions Performance to Compare
                  Levels Amongst Control  Options	B.22
            2.     Control  Techniques With a  Wide Range of
                  Emissions Performance Levels	B.23
            3.     Establishment  of the Control Options Hierarchy.   B.25
      D.     The BACT Selection Process	B.26
            1.     Energy Impacts Analysis 	   B.29
            2.     Cost/Economic  Impacts Analysis	B.31
                  a.    Estimating Control  Costs	B.32
                  b.    Cost Effectiveness	B.36
                  c.    Determining an Adverse Economic Impact. .   B.44
            3.     Environmental  Impacts Analysis	B.46
                  a.    Examples (Environmental  Impacts)	B.48
                  b.    Consideration of Emissions of Toxic
                        and Hazardous Pollutants	B.50
      E.     Selecting  BACT	B.53
      F.     Other considerations	B.54
VI.   Enforceability of BACT	B.56
VII.   Example BACT Analyses for  Gas Turbines	B.57
      A.     Example I — Simple Cycle Gas Turbines Firing Natural
            Gas	B.58
            1.     Project Summary	B.58
            2.     BACT Analysis  Summary	B.58
                  a.    Control  Technology Options	B.58
                  b.    Technical  Feasibility Considerations.  . .   B.61
                  c.    Control  Technology Hierarchy	B.62

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                   TABLE OF CONTENTS -  Continued
                                                                   Page
                  d.     Impacts Analysis Summary	B.65
                  e.     Toxics Assessment 	   B.65
                  f.     Rationale for Proposed BACT	B.68
      B.     Example 2--Combined Cycle Gas Turbines Firing
            Natural Gas	B.69
      C.     Example 3--Combined Cycle Gas Turbine Firing Distillate
            Oil	B.73
      D.     Other Considerations	B.74

Chapter C - The  Air Quality Analysis
  I.   Introduction	C.I
 II.   National  Ambient  Air Quality Standards and PSD Increments .   C.3
      A.     Class I,  II and III Areas and Increments	C.3
      B.     Establishing the Baseline Date	C.6
      C.     Establishing the Baseline Area	C.9
      D.     Redefining  Baseline Areas (Area Redesignation).  .  . .   C.9
      E.     Increment Consumption and Expansion 	   C.10
      F.     Baseline Date and Baseline Area Concepts -- Examples.   C.12
III.   Ambient Data Requirements	C.16
      A.     Pre-Appl i cation Air Quality Monitoring	C.16
      B.     Post-Construction Air Quality Monitoring	C.21
      C.     Meteorological Monitoring 	   C.22
 IV.   Dispersion Modeling Analysis	C.24
      A.     Overview of the Dispersion Modeling Analysis	C.24
      B.     Determining the Impact Area	C.26

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                        TABLE OF CONTENTS - Continued
                                                                   Page
      C.     Developing  the  Emissions  Inventories	C.31
            1.     The  NAAQS Inventory	C.32
            2.     The  Increment  Inventory	C.35
            3.     Noncriteria  Pollutants  Inventory	C.37
      D.     Model  Selection	C.37
            1.     Meteorological  Data	C.39
            2.     Receptor  Network	C.39
            3.     Good  Engineering  Practice  (GEP)  Stack Height.  .   C.42
            4.     Source  Data	C.44
      E.     The  Compliance  Demonstration	C.51
  V.   Air  Quality  Analysis--Example 	   C.54
      A.     Determining the Impact  Air	C.54
      B.     Developing  the  Emissions  Inventories	C.58
            1.     The  NAAQS Inventory	C.59
            2.     The  Increment  Inventory	C.62
      C.     The  Full  Impact Analysis	C.66
            1.     NAAQS Analysis	C.67
            2.     PSD  Increment  Analysis	C.69
 VI.   Bibliography	C.71

Chapter D  - Additional  Impacts Analysis
  I.   Introduction	D.I
 II.   Elements  of  the  Additional Impacts  Analysis	D.3
      A.     Growth Analysis	0.3
      B.     Soils  and  Vegetation Analysis	D.4
      C.     Visibility Impairment Analysis 	  D.4
            1.     Screening Procedures:  Level 1   	  D.5
            2.     Screening Procedures:  Level 2   	  D.5
            3.     Screening Procedures:  Level 3   	  D.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                         TABLE  OF  CONTENTS  -  Continued
                                                                  Page
      D.    Conclusions	D.6
III.  Additional Impacts Analysis Example	D.7
      A.    Example Background Information 	  D.7
      B.    Growth Analysis	D.9
            1.    Work Force	D.9
            2.    Housing	D.9
            3.    Industry	D.9
      C.    Soils and Vegetation	D.10
      D.    Visibility Analysis	0.13
      E.    Example Conclusions	D.13
 IV.  Bibliography	D.15

Chapter E - Class I Area Impact Analysis
  I.  Introduction	E.I
 II.  Class I Areas and Their Protection 	  E.2
      A.    Class I Increments	E.8
      B.    Air Quality Related Values (AQRV's)	E.10
      C.    Federal Land Manager	E.12
                                      VI

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                        TABLE OF CONTENTS  - Continued
                                                                  Page
III.   Mandatory Federal  Class I  Area Impact Analysis and Review. .   E.16
      A.     Source Applicability 	   E.16
      B.     Pre-Application Stage	E.17
      C.     Preparation  of Permit Application 	  E.18
      D.     Permit Application Review 	  E.19
 IV.   Visibility Impact  Analysis and Review 	  E.22
      A.     Visibility Analysis  	  E.22
      B.     Procedural Requirements 	  E.23
  V.   Bibliography	E.24

PART  II - NONATTAINMENT AREAS

Chapter F - Nonattainment Area Applicability

  I.   Introduction	F.I
 II.   Definition of Source	F.2
      A.     "Plantwide"  Stationary Source Definition	F.2
      B.     "Dual Source" Definition of Stationary Source  ....  F.3
III.   Pollutants Eligible for Review and Applicability
        Thresholds	F.7
      A.     Pollutants Eligible for Review (Geographic
              Considerations) 	  F.7
      B.     Major Source Threshold	F.7
      C.     Major Modification Thresholds  	  F.8
                                      VI 1

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                        TABLE OF CONTENTS  -  Continued
                                                                  Page
IV.   Nonattainment Applicability Example 	  F.9

Chapter G - Nonattainment Area Requirement
  I.  Introduction	G.I
 II.  Lowest Achievable EMission Rate (LAER)	G.2
III.  Emissions Reductions "Offsets"	G.5
      A.     Criteria  for Evaluating Emissions Offsets 	  G.6
      B.     Available Sources of Offsets	G.7
      C.     Calculation of Offset Baseline	G.7
      D.     Enforceabi 1 ity of Proposed Offsets	G.8
 IV.  Other Requirements	G.9

PART III  - EFFECTIVE  PERMIT WRITING

Chapter H - Elements  of an Effective Permit
  I.  Introduction	H.I
 II.  Typical  Permit  Elements 	  H.3
      A.     Legal  Authority	H.3
      B.     Technical Specifications	H.5
      C.     Emissions Compliance Demonstrations 	  H.6
      D.     Definition  of Excess Emissions	H.7
      E.     Administrative Procedures 	  H.8
      F.     Other  Conditions	H.9
III.  Summary	H.9
                                     Vl

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
                         TABLE  OF  CONTENTS  -  Continued

Chapter I - Permit Drafting
  I.   Recommended Permit Drafting Steps  	
 II.   Permit Worksheets and File Documentation.  .  .  .
III.   Summary 	
Page

 I.I
 1.5
 1.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                         TABLE  OF  CONTENTS  -  Continued
                                                                  Page
TABLES
A.I.  PSD Source Categories With 100 tpy Major Source
        Thresholds	A.11

A-2.  NSPS and National  Emissions Standards for Hazardous Air
        Pollutants Proposed Prior to August 7, 1980 	  A.12

A-3.  Suggested References for Estimating Fugitive Emissions. .   .  A.17

A-4.  Significant Emission Rates of Pollutants Regulated Under
        the Clean Air Act	A.20

A-5.  Procedures for Determining the Net Emissions Change at a
        Source	A.45

B-l   Key Steps in the "Top-Down" BACT Process	B.6

B-2   Sample BACT Control Hierarchy 	  B.27

B-3   Sample Summary of Top-Down BACT Impact Analysis Results .   .  B.28

B-4   Example Control System Design Parameters	B.34

B-5   Example 1 -- Combustion Turbine Design Parameters  	  B.59

B-6   Example 1 -- Summary of Potential  NOX  Control  Technology
        Options	B.60

B-7   Example 1 -- Control Technology Hierarchy 	  B.63

B-8   Example 1 -- Summary of Top-Down BACT Impact Analysis
        Results for NOX	B.66

B-9   Example 2 -- Combustion Turbine Design Parameters  	  B.70

B-10  Example 2 -- Summary of Top-Down BACT Impact Analysis
        Results	B.71

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                         TABLE OF CONTENTS  - Continued

                                                                  Page

TABLES - Continued


B-ll  Example of a Capital Cost Estimate for an Electrostatic
        Precipitator	b.5

B-12  Example of a Annual Cost Estimate for an Electrostatic
        Precipitator Applied to a Coal-Fired Boiler 	  b.9

C-l.  National Ambient Air Quality Standards	C.4

C-2.  PSD Increments	C.7

C-3.  Significant Monitoring Concentrations 	  C.17

C-4.  Significance Levels for Air Quality Impacts in Class II
        Areas	C.28

C-5.  Point Source Model  Input Data (Emissions) for NAAQS
        Compliance Demonstrations 	  C.46

C-6.  Existing Baseline  Dates for S02,  TSP,  and N02  for  Example
        PSD Increment Analysis	C.64

E.I.  Mandatory Class I  Areas	E.3

E.2.  Class I Increments	E.9

E-3.  Examples of Air Quality-Related Values and Potential Air
        Pollution Caused  Changes	E.ll

E-4.  Federal Land Manager	E.14

E-5.  USDA Forest Service Regional Offices and States They Serve.  E.15

H-l.  Suggested Minimum  Contents of Air  Emission Permits	H.4

H-2.  Guidelines for Writing Effective Specific Conditions in
        NSR Permits	H.10

1-1.  Five Steps to Permit  Drafting	1.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                         TABLE  OF  CONTENTS  -  Continued

                                                                  Page


FIGURES


A-l.  Creditable Reductions in Actual Emissions	A.43

A-2.  Establishing "Old" and "New" Representative Actual S02
        Emissions	A.50

B-l   Least-Cost Envelope 	  B.42

B-2   Least-Cost Envelope for Example 1	B.67

B-3   Least-Cost Envelope for Example 2	B.72

B-4   Elements of Total Capital Cost	b.2

B-5   Elements of Total Annual  Cost	b.6

C-l.  Establishing the Baseline Area	C.13

C-2.  Redefining the Baseline Area	C.15

C-3.  Basic Steps in the Air Quality Analysis (NAAQS  and PSD
        Increments)	C.27

C-4.  Determining the Impact Area	C.29

C-5.  Defining the Emissions Inventory Screening Area  	  C.33

C-6.  Examples of Polar and Cartesian Grid Networks  	  C.41

C-7.  Counties Within 100 Kilometers of Proposed Source  	  C.57

C-8.  Point Sources  Within 100 Kilometers of Proposed  Source.  .  .  C.60
                                     XI 1

-------
                         TABLE OF CONTENTS - Continued
APPENDICES


A.    Definition of Selected Terms

B.    Estimating Control Costs

C.    Potential to Emit  	
                                                                   DRAFT
                                                                   OCTOBER  1990
                                                                   Page
a.l

b.l

c.l
                                      XI 1 1

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                   PREFACE
      This document was developed for use in conjunction with new source
review workshops and training, and to guide permitting officials in the
implementation of the new source review (NSR)  program.  It is not intended to
be an official statement of policy and standards and does not establish
binding regulatory requirements; such requirements are contained in the
regulations and approved state implementation  plans.  Rather, the manual  is
designed to (1) describe in general  terms and  examples the requirements of the
new source regulations and pre-existing policy;  and (2)  provide suggested
methods of meeting these requirements, which are illustrated by examples.
Should there be any apparent inconsistency between this  manual  and the
regulations (including any policy decisions made pursuant to those
regulations),  such regulations and policy shall  govern.   This document can be
used to assist those people who may be unfamiliar with the NSR program (and
its implementation) to gain a working understanding of the program.

      The focus of this manual is the prevention of significant deterioration
(PSD) portion  of the NSR program found in the  Federal  Regulations at
40 CFR 52.21.   It does not necessarily describe  the specific requirements in
those areas where the PSD program is conducted under a state implementation
plan (SIP) which has been developed and approved in accordance with 40 CFR
51.166.  The reader is cautioned to keep this  in mind when using this manual
for general program guidance.  In most cases,  portions of an approved SIP that
are different  from those described in this manual will be more restrictive.
Consequently,  it is suggested that the reader  also obtain program information
from a State or local agency to determine all  requirements that may apply in  a
area.

      The examples presented in this manual are  presented for illustration
purposes only.  They are fictitious and are designed to  impart a basic
understanding  of the NSR regulations and requirements.

      A number of terms and acronyms used in this manual have specific
meanings within the context of the NSR program.   Since this  manual  is intended
for use by those persons generally familiar with NSR these terms are used
throughout this document, often without definition.  To  aid  users of the
document who are unfamiliar with these terms,  general  definitions of these
terms can be found in Appendix A.  The specific  regulatory definitions for
most of the terms can be found in 40 CFR 52.21.   Should  there be any apparent
inconsistency  between the definitions contained  in Appendix  A and the
regulatory definitions or requirements found in  Part 40  of the Code of Federal
Regulations (including any policy decisions made pursuant to those
regulations),  the regulations and policy decisions shall govern.

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                             MANUAL ORGANIZATION

      The manual  is organized into three parts.   Part  I  contains  five chapters
(Chapters A - E)  covering the PSD program requirements.   Chapter  A describes
the PSD applicability criteria  and process used  to  determine if  a proposed  new
or modified stationary source is required to obtain a  PSD permit.  Chapter  B
discusses the process by which  best available control  technology  (BACT)  is
determined for new or modified  emissions units.   Chapter C discusses  the PSD
air quality analysis used to demonstrate that the proposed construction  will
not cause or contribute to a violation  of any applicable National Ambient Air
Quality Standard  or PSD increment.  Chapter D discusses  the PSD  additional
impacts analyses  which assess the impact of air,  ground, and water pollution
on soils, vegetation, and visibility caused by an increase in emissions  at  the
subject source.  Chapter E identifies  class I areas,  describes the procedures
involved in preparing and reviewing a  permit application for a proposed  source
with potential class I area air quality impacts.

      Part II of  the manual (Chapters  F and G) covers  the nonattainment  area
(NAA) permit program requirements for  new major  sources  and major
modifications.  Chapter F describes the NAA applicability criteria for new or
modified stationary sources locating in a nonattainment  area.  Chapter G
provides a basic  overview of the NAA preconstruction  review requirements.

      Part III (Chapters H and  I) covers the major  source permit  itself.
Chapter H discusses the elements of an  effective and  enforceable  permit.
Chapter I discusses permit drafting.

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                           INTRODUCTION AND OVERVIEW
      Major stationary sources of air pollution and major modifications to
major stationary sources are required by the Clean Air Act to a obtain an air
pollution permit before commencing construction.   The process is called new
source review (NSR)  and is required whether the major source or modification
is planned for an area where the national  ambient air quality standards
(NAAQS) are exceeded (nonattainment areas) or an  area where air quality is
acceptable (attainment and unclassifiable  areas).  Permits for sources in
attainment areas are referred to as prevention of significant air quality
deterioration (PSD)  permits; while permits for sources located in
nonattainment areas  are referred to as NAA permits.  The entire program,
including both PSD and NAA permit reviews, is referred to as the NSR program.

      The PSD and NAA requirements are pollutant  specific.  For example,  a
facility may emit many air pollutants, however, depending on the magnitude of
the emissions of each pollutant, only one  or a few may be subject to the  PSD
or NAA permit requirements.  Also, a source may have to obtain both PSD and
NAA permits if the source is in  an area where one or more of the pollutants is
designated nonattainment.

      On August 7, 1977, Congress substantially amended the Clean Air Act and
outlined a rather detailed PSD program.  On June  19, 1978, EPA revised the PSD
regulations to comply with the 1977 Amendments.  The June 1978 regulations
were challenged in a lengthy judicial review process.  As a result of the
judicial process on  August 7, 1980, EPA extensively revised both the PSD  and
NAA regulations.  Five sets of regulations resulted from those revisions.
These regulations and subsequent modifications represent the current NSR
regulatory requirements.

      The first set  of regulations, 40 CFR 51.166, specifies the minimum
requirements that a  PSD air quality permit program under Part C of the Act
must contain in order to warrant approval  by EPA  as a revision to a State
implementation plan  (SIP).  The  second set, 40 CFR 52.21, delineates the
federal PSD permit program, which currently applies as part of the SIP, in
approximately one third of States that have not submitted a PSD program
meeting the requirements of 40 CFR 51.166.  In other words, roughly two thirds
of the States are implementing their own PSD program which has been approved
by EPA as meeting the minimal requirements for such a program, while the
remaining States have been delegated the authority to implement the federal
PSD program.

      The basic goals of the PSD regulations are: (1) to ensure that economic
growth will occur in harmony with the preservation of existing clean air
resources to prevent the development of any new nonattainment problems; (2) to
protect the public health and welfare from any adverse effect which might
occur even at air pollution levels better  than the national ambient air
quality standards (NAAQS); and (3) to preserve, protect, and enhance the  air
quality in areas of  special natural recreational, scenic, or historic value,
such as national parks and wilderness areas.  The primary provisions of the

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

PSD regulations require that new major stationary sources  and major
modifications be carefully reviewed prior to construction  to ensure compliance
with the NAAQS, the applicable PSD air quality increments,  and the requirement
to apply the BACT on the project's emissions of air pollutants.

      The third set, 40 CFR 51.165(a)  and (b), specifies the elements of  an
approvable State permit program for preconstruction review for nonattainment
purposes under Part D of the Act.  A major new source or major modification
which would locate in an area designated as nonattainment  and subject to  a NAA
permit must meet stringent conditions  designed to ensure that the new source's
emissions will be controlled to the greatest degree possible; that more than
equivalent offsetting emissions reductions ("emission offsets")  will  be
obtained from existing sources; and that there will be progress  toward
achievement of the NAAQS.

      The forth and fifth sets, 40 CFR Part 51, Appendix S (Offset Ruling) and
40 CFR 52.24 (construction moratorium) respectively,  can apply in certain
circumstances where a nonattainment area SIP has not been  fully  approved  by
EPA as meeting the requirements of Part D of the Act.

      Briefly, the requirements of the PSD regulations apply to  new major
stationary sources and major modifications.  A "major stationary source"  is
any source type belonging to a list of 28 source categories which emits or has
the potential to emit 100 tons per year or more of any pollutant subject  to
regulation under the Act, or any other source type which emits or has the
potential to emit such pollutants in amounts equal to or greater than 250 tons
per year.  A stationary source generally includes all pollutant-emitting
activities which belong to the same industrial grouping, are located on
contiguous or adjacent properties, and are under common control.

      A  "major modification" is generally a physical  change or a change in the
method of operation of a major stationary source which would result in a
contemporaneous significant net emissions increase in the emissions of any
regulated pollutant.  In determining if a proposed increase would cause a
significant net increase to occur, several detailed calculations must be
performed.

      If a source or modification thus qualifies as major, its prospective
location or existing location must also qualify as a PSD area, in order for
PSD review to apply.  A PSD area is one formally designated by the state as
"attainment" or "uncl assifiabl e" for any pollutant for which a national
ambient  air quality standard exists.

      No source or modification subject to PSD review may be constructed
without  a permit.  To obtain a PSD permit an applicant must:

      1. apply  the best available control technology (BACT);
            A BACT analysis is done on a case-by-case basis, and
      considers energy, environmental, and economic  impacts in
      determining the maximum degree of reduction  achievable for the
      proposed  source or modification.  In no  event  can the
                                       4

-------
                                                            DRAFT
                                                            OCTOBER 1990
determination of BACT result in an emission limitation which would
not meet any applicable standard of performance under 40 CFR Parts
60 and 61.

2. conduct an ambient air quality analysis;
      Each PSD source or modification must perform an air quality
analysis to demonstrate that its new pollutant emissions would not
violate either the applicable NAAQS or the applicable PSD
i ncrement.

3. analyze impacts to soils, vegetation,  and visibility;
      An applicant is required to analyze whether its proposed
emissions increases would impair visibility,  or impact on soils or
vegetation.  Not only must the applicant  look at the direct effect
of source emissions on these resources,  but it also must consider
the impacts from general commercial, residential, industrial,  and
other growth associated with the proposed source or modification.
4. not adversely impact a Class I area; and
      If the reviewing authority receives a PSD permit application
for a source that could impact a Class I area,  it notifies the
Federal  Land Manager and the federal  official  charged with direct
responsibility for managing these lands.  These officials are
responsible for protecting the air quality-related values in
Class I  areas and for consulting with the reviewing authority to
determine whether any proposed construction will  adversely affect such
values.   If the Federal Land Manager  demonstrates that emissions from a
proposed source or modification would impair air  quality-related values,
even though the emissions levels would not cause  a violation of the
allowable air quality increment, the  Federal Land Manager may recommend
that the reviewing authority deny the permit.

5. undergo adequate public participation by applicant.
      Specific public notice requirements and  a public comment
period are required before the PSD review agency  takes final
action on a PSD application.

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER A
                               PSD APPLICABILITY
I.   INTRODUCTION
      An applicability determination,  as  discussed  in  this  section,  is  the
process of determining whether a  preconstruction  review  should  be  conducted
by, and a permit issued to,  a  proposed new source or  a modification  of  an
existing source by the reviewing  authority,  pursuant  to  prevention of
significant deterioration (PSD)  requirements.

      There are three basic  criteria  in determining PSD  applicability.   The
first and primary criterion  is whether the proposed project is  sufficiently
large (in terms of its emissions)  to  be a "major" stationary source  or  "major"
modification.   Source size is  defined  in  terms  of "potential  to emit,"  which
is its capability at maximum design  capacity to emit  a pollutant,  except as
constrained by federally-enforceable  conditions (which include  the effect  of
installed air  pollution control  equipment and  restrictions  on the  hours of
operation, or  the type or amount  of  material  combusted,  stored  or  processed).

      A new source is major  if it  has  the potential  to emit any pollutant
regulated under the Act in amounts equal  to or  exceeding specified major
source thresholds [100 or 250  tons per year (tpy)]  which are predicated on the
source's industrial category.   A  major modification is a physical  change or
change in the  method of operation  at  an existing  major source that causes  a
significant "net emissions increase"  at that source of any  pollutant regulated
under the Act.

      The second criterion for PSD applicability  is that a  new  major source
would locate,  or the modified  source  is located,  in a  PSD area.  A PSD  area  is
one formally designated, pursuant  to  section 107  of the  ACT and 40 CFR  81, by
a State as "attainment" or "unclassifiable" for any criteria pollutant, i.e.,
an air pollutant for which a national  ambient  air quality standard exists.


      The third criterion is that  the  pollutants  emitted in, or increased  by,
"significant"  amounts by the project  are subject  to PSD.  A source's location
can be attainment or unclassified  for  some pollutants  and simultaneously
nonattainment  for others.  If  the project would emit only pollutants for which
the area has been designated nonattainment, PSD would  not apply.

      The purposes of a PSD applicability determination  are therefore:
      (1)   to determine whether  a proposed new source is a "major stationary
            source," or if a proposed  modification  to  an existing source is  a
            "major modification;"

      (2)   to determine if proposed conditions and restrictions,  which will
            limit emissions from a new source or  an existing source that is
            proposing modification to  a level  that  avoids preconstruction
            review requirements,  are legitimate and federally-enforceable;  and

                                      A.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

      (3)   to determine for a major new source or a  major modification  to  an
            existing source which pollutants are subject to preconstruction
            review.
      In order to perform a satisfactory applicability determination,  numerous
pieces of information must be compiled and evaluated.   Certain information  and
analyses are common to applicability determinations  for both  new sources  and
modified sources; however, there are several  major differences.   Consequently,
two detailed discussions follow in this section:   PSD  applicability
determinations for major new sources and PSD applicability determinations for
modifications of existing sources.  The common elements will  be  covered in  the
discussion of new source applicability.  They are the  following:

            *     defining the source;
            *     determining the source's potential  to emit;
            *     determining which major source  threshold the source  is
                  subject to; and
            *     assessing the impact on applicability of the local  air
                  quality, i.e., the attainment designation,  in  conjunction
                  with the pollutants emitted by  the source.
II.  NEW SOURCE PSD APPLICABILITY DETERMINATIONS

II.A.  DEFINITION OF SOURCE

      For the purposes of PSD a stationary source is any building,  structure,
facility, or installation which emits or may emit any  air pollutant subject to
regulation under the Clean Air Act (the Act).  "Building, structure,  facility,
or installation" means all the pollutant-emitting activities  which  belong to
the same industrial grouping, are located on one  or  more contiguous or
adjacent properties and are under common ownership or  control.  An  emissions
unit is any part of a stationary source that emits or  has the potential  to
emit any pollutant subject to regulation under the Act.

      The term "same industrial grouping" refers  to  the "major groups"
identified by two-digit codes in the Standard Industrial Classification (SIC)
                                     A.2

-------
                                                                        DRAFT
                                                                        OCTOBER 1990

Manual,  which is  published  by  the Office  of Management and Budget.  The  1972

edition  of the SIC  Manual,  as  amended in  1977, is  cited in the  current  PSD

regulations as the  basis for  classifying  sources.   Sources not  found in  that

edition  or the 1977 supplement may be classified according to  the most  current

edition.
       For   example  a   chemical  complex  under  common   ownership   manufactures
       polyethylene,    ethylene   dichloride,    vinyl    chloride,   and   numerous
       other   chlorinated   organic   compounds.      Each   product   is  made   in
       separate   processing   equipment    with   each    piece    of   equipment
       containing several  emission  units.    All  of  the  operations  fall  under
       SIC  Major  Group  28,   "Chemicals   and  Allied  Products;"   therefore,   the
       complex   and   all   its   associated   emissions   units   constitute   one
       source.
       In most cases,  the  property boundary and ownership are  easily

determined.  A  frequent question, however, particularly at  large industrial

complexes, is how to deal  with multiple emissions  units at  a  single  location

that  do not fall  under the same two-digit SIC code.   In this  situation  the

source is classified according to the  primary activity at the site,  which is

determined by its principal  product  (or group of  products)  produced  or
distributed, or by the services it renders.  Facilities that  convey,  store, or

otherwise assist in the production of  the principal  product are called  support

faci Titles.
       For   example,  a   coal  mining  operation   may   include  a   coal   cleaning
       plant,  which  is   located  at  the  mine.    If   the  sole  purpose  of  the
       cleaning  plant  is  to  process  the  coal  produced  by  the  mine,   then  it
       is  considered  to  be  a   support  facility  for  the  mining   operation.
       If,   however,   the  cleaning   plant   is  collocated   with   a  mine,   but
       accepts  more  than  half  of  its  feedstock  from  other  mines  (indicating
       that  the  activities  of  the  collocated mine  are  incidental)   then  coal
       cleaning   would   be   the   primary   activity   and  the  basis   for   the
       classification.

       Another   common   situation   is  the   collocation  of  power  plants  with
       manufacturing  operations.     An  example would  be  a  silicon  wafer  and
       semiconductor  manufacturing  plant  that  generates   its  own  steam  and
       electricity  with   fossil   fuel-fired  boilers.     The   boilers  would  be
       considered  part  of  the   source  because   the   power  plant  supports  the
       primary activity of the facility.
                                         A.3

-------
                                                                      DRAFT
                                                                      OCTOBER 1990
      An  emissions unit  serving  as a support  facility for two  or more primary

activities  (sources) is  to  be  considered  part of the primary  activity that

relies most  heavily on its  support.


      For  example,   a  steam  boiler  jointly   owned   and   operated  by   two
      sources   would  be   included   with  the  source  that  consumes  the   most
      steam.

      As  a  corollary  to  the  examples  immediately  above,  suppose  a   power
      plant.    is   co-owned   by   the   semiconductor   plant   and   a   chemical
      manufacturing  plant.     The   power  plant   provides  70  percent  of  its
      total   output  (in  Btu's  per  hour)   as  steam  and  electricity  to  the
      semiconductor plant.    It  sells  only  steam to  the  chemical  plant.    In
      the  case of  co-generation,   the    support  facility  should   be  assigned
      to  a  primary  activity based  on  pro rata  fuel  consumption  that  is
      required   to  produce   the  energy   bought  by   each  of   the   support
      facility's  customers,  since  the  emission   rates  in  pounds per  Btu  are
      different  for  steam  and  electricity.     In   this  example   then,   the
      power plant would be considered part of the semiconductor plant.

      It  is  important to note  that if a new support facility would  by itself

be a major  source based  on  its source category classification  and potential to
emit, it  would be subject  to  PSD review even  though the  primary source,  of

which it  is  a  part, is not  major and therefore exempt from  review.   The

conditions  surrounding such  a  determination is discussed further in  the

section on major source  thresholds (see Section II.C.).


II.B.  POTENTIAL TO EMIT


II.B.I.   BASIC REQUIREMENTS


      The potential to emit  of a stationary source is of primary importance in
establishing  whether a new  or  modified source is major.  Potential  to emit is

the maximum  capacity of  a  stationary source to emit a pollutant under its
physical  and  operational design.  Any physical  or operational  limitation on

the capacity  of the source  to  emit a pollutant,  provided the  limitation or its

effect on emissions is federally-enforceable, shall be treated as part of its

design.   Example limitations  include:
                                        A.4

-------
                                                                       DRAFT
                                                                       OCTOBER 1990
      (1)    Requirements  to install and operate air pollution control
             equipment at  prescribed efficiencies;

      (2)    Restrictions  on design capacity utilization [note that  these
             types of limitations are not explicitly mentioned in the
             regulations,  but in certain instances do meet the criteria
             for  limiting  potential to emit];

      (3)    Restrictions  on hours of operation; and

      (4)    Restrictions  on the types or amount of material processed,
             combusted or  stored.
II.B.2.   ENFORCEABILITY  OF LIMITS


       For  any limit or  condition to  be a legitimate restriction on potential

to emit,  that limit or  condition must  be federally-enforceable, which  in  turn

requires  practical enforceability  (see Appendix  A)  [see U.S.  v. Louisiana-

Pacific Corporation.  682 F. Supp.  1122,  Civil Action No. 86-A-1880

(D. Colorado, March 22,  1988).  Practical enforceability means  the source

and/or enforcement authority must  be able to  show continual  compliance  (or

noncompliance) with each limitation  or requirement.  In other words,  adequate

testing,  monitoring,  and record-keeping procedures  must be  included either  in

an applicable federally  issued permit, or in  the applicable federally  approved

SIP or the permit issued under same.


       For example, a permit that limits actual  source emissions on an
       annual basis only (e.g., the facility is  limited solely to 249
       tpy) cannot be considered in determining potential to emit. It
       contains none of the  basic requirements and is therefore not
       capable of ensuring continual compliance,  i.e., it is not
       enforceable as a practical matter.


       The term "federally-enforceable" refers to all limitations and

conditions which are  enforceable by  the Administrator,  including:
             requirements developed pursuant to any new source
             performance standards (NSPS) or national emission standards
             for hazardous air pollutants (NESHAP),
                                        A.5

-------
                                                                          DRAFT
                                                                          OCTOBER 1990

       •     requirements  within any applicable federally-approved State
             implementation plan, and

       •     any requirements contained in  a permit issued pursuant to
             federal PSD regulations (40 CFR 52.21), or pursuant to PSD
             or operating  permit provisions in a SIP which has been
             federally approved  in accordance with 40 CFR 51 Subpart I.


       Federally-enforceable  permit conditions  that may  be  used  to  limit

potential  to  emit can be  expressed in a  variety  of -terms  and usually include a

combination of  two or more of the following four requirements in  conjunction

with  appropriate record-keeping  requirements for verification of  compliance:
       (1)    Installation and  continuous  operation and maintenance of air
              pollution  controls,  usually  expressed as both a required
              abatement  efficiency of the  maximum  uncontrolled emission
              rate and a  maximum  outlet  concentration or  hourly emission
              rate (flow  rate x concentration);

             A   typical  example  might  be  a  255   tpy   limit   on  a   stone   crushing
             operation.      The   enforceable   permit   conditions   could   be  a  maximum
             emission  rate  of  58   Ibs/hr,   a  maximum  concentration   of  0.1   grains
             per  dry  standard  cubic  foot   (gr/dSCF)  and   a   maximum   flow   rate  of
             67,000  dSCFM  based  on  nameplate  capacity  and   8760  hours  per  year.
             In   addition,   the   permit  should  also   stipulate   a  minimum  90  percent
             overall  reduction   of  particulate  matter  (PM)  emissions   on  an  hourly
             basis via capture hoods and a baghouse.
       (2)   Capacity  limitations;

             The  stone  crusher  decides   to   limit  its  potential   to  emit   to
             180   tpy   by   limiting  the   feed   rate   to  70  percent  of   the
             nameplate  capacity.    One   of  the   enforceable  limits  becomes   a
             stone  feed  rate   (tons/hr.)  based   on  70  percent  of  nameplate
             capacity  with  a   federally-enforceable  requirement   for  a  method
             or  device   for  measuring   the   feed   rate   on   an   hourly  basis.
             Another  approach   is  to   limit   the  PM   emissions  rate   to   41
             Ibs/hr.        A   third   alternative   is    to   retain   a   maximum
             concentration  of  0.1  gr./dSCF,   but  limit  the  maximum  exhaust
             rate  to  47,000  dSCFM due  to  the decrease  in  feed  rate.    In  all
             these  cases,  the  90  percent   overall  reduction   of  particulate
             matter  (PM)  emissions on  an  hourly  basis  via  capture  hoods  and
             baghouse would  also be maintained.

             In  another  example,  the potential  to  emit  of a  boiler  with   a
             design  input  capacity  of  200 million  Btu/hour is  limited  to   a
             100-million-Btu/hr   fuel   input   rate   by   the   permit,    which

                                          A.6

-------
                                                                          DRAFT
                                                                          OCTOBER 1990

             requires  that  the  boiler's  heat  input  not  exceed  50  percent  of
             its  rated  capacity.     The   permit  would  further  require  that
             compliance  be  demonstrated   with  a   continuously  recording  fuel
             meter    and  concurrent  monitoring   and  recording  of  fuel  heating
             value  to show  that  the  fuel  input  does  not  exceed  100-million-
             Btu/hr.
       (3)    Restrictions  on   hours   of  operation,   including  seasonal
             operation;  and

             In  the  stone  crusher  example,  the  operator  may  choose  to   limit
             the  hours  of operation  per year  to  keep the  potential  to  emit
             below  the  major  source  threshold  of  250  tpy.     For   example.
             using  the  same  maximum  concentration  and flow  rate  and minimum
             overall   control   efficiency  limitations   as   in    (1)   above,    a
             restriction  on  the   number   of  8-hour  shifts   to   two,   i.e.,  16
             hours    per    day    would   reduce   the   potential    uncontrolled
             emissions by 33 percent to    170 tpy.

             In  another  example,   a  citrus  dryer   that   only   operates  during
             the  growing  season  could have  its  potential  to  emit  limited  by
             a  permit  restriction  on  the  hours  of  operation,  and  further,
             by   prohibiting   the   dryer   from   operating  between   March    and
             November.

       (4)    Limitations on raw materials used (including fuel  combusted)
             and  stored.

             An  example  of this   type of  limit  would  be  a  maximum  1 percent
             sulfur  content  in  the  coal   feed   for  a  power  plant.    Another
             would  be   a  condition   that   a   surface   coater  only   use  water-
             based  or  higher   solids  coatings  with  a  maximum  VOC  content  of
             2.0  pounds   VOC   per  gallon   solids deposited  on   the  substrate
             with    requisite    limits    on   coating   usage    (gallons/hr   or
             gallons/yr on a 12-month rolling time period).
       In addition  to limits in major  source  construction permits  or federally
approved SIP  limits  for major  sources, terms  and  conditions  contained in  State

operating permits  will  be considered  federally-enforceable  under  the following

conditions:
       (1)     the   State's   operating  permit  program  is  approved  by   EPA   and
              incorporated  into  the  applicable  SIP  under  section  110  of  the
              Act;

       (2)     the   operating  permits  are   legally  binding  on  the  source  under
              the   SIP  and  the  SIP  specifically  provides   that   permits   that
                                          A.7

-------
                                                                            DRAFT
                                                                            OCTOBER 1990

              are    not    legally   binding   my   be    deemed   not    " federal ly-
              enforceable:"

       (3)     all    emissions   limitations,   controls,   and   other   requirements
              imposed   by   such   permits   are   no    less   stringent   than  any
              counterpart   limitations   and  requirements   in   the   SIP,   or   in
              standards established under sections 111  and 112 of the ACT;

       (4)     the    limitations,   controls   and  requirements   in  the   operating
              permits   are   permanent,   quantifiable,   and   otherwise  enforceable
              as a practical matter; and

       (5)     the  permits   are   issued  subject   to   public  participation,   i.e.,
              timely notice, opportunity for public cement,  etc.

       (See also, 54 FR 27281,  June 28,  1989. )
       A minor  (i.e.,  a  non-major) source construction permit issued to a  source
by a  State may be  used to  determine the  potential  to  emit  if:

       •      the  State  program  under  which  the  permit  was  issued  has   been
              approved by EPA as meeting  the  requirements of
              40 C.F.R. Parts 51.160 through  51.164, and
                                           A.8

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
•     the  provisions  of  the  permit  are   federally-enforceable   and  enforceable  as
      a practical matter.

      Note,  however,  that  a  permit  condition  that  temporarily restricts
production  to  a  level at which  the source does not intend  to operate for any
extensive  time is not  valid if it appears to  be intended  to circumvent the
preconstruction  review  requirements for major  source by  making  the  source
temporarily minor.   Such permit limits cannot be  used in the determination  of
potential to emit. Another situation that should receive careful scrutiny is the
construction of a manufacturing facility with a physical capacity  far greater
than the limits  specified in a permit condition.   See also 54 FR 27280,  which
specifically discusses  "sham" minor source permits.

      An  example   is  construction  of  an   electric   power  generating  unit,
      which  is  proposed  to be  operated  as  a  peaking unit but  which by  its
      nature can  only be  economical  if  it  is used  as  a base-load  facility.
      Remember,  If the permit  or  SIP  requirements, conditions  or limits  on  a
source are not federally-enforceable (which  includes enforceable as  a  practical
matter), potential  to  emit  is  based on full  capacity and year-round operation.
For additional information on federally enforceabi1ity and limiting potential  to
emit see Appendix  A.

II.B.3.  FUGITIVE  EMISSIONS

      As defined in the federal PSD regulations,  fugitive emissions  are  those
"...which  could  not reasonably  pass  through a  stack,  chimney,  vent,  or  other
functionally equivalent opening."  To the extent they  are quantifiable, fugitive
emissions  are  included in the potential  to  emit (and  increases in  same  due  to
modification), if  they occur at one of the following stationary  sources:
                                      A.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

      •     Any belonging  to one of the 28 named  PSD source categories listed  in
            Table A-l,  which were explicitly identified in Section  169  of the
            Act  as  being  subject   to  a  100-tpy   emissions   threshold  for
            classification of  major  sources;

      •     Any belonging  to a stationary source category  that  as  of August  7,
            1980,  is  regulated  (effective  'date  of  proposal)   by  New  Source
            Performance Standards (NSPS)  pursuant to  Section  111 of the Act
            (listed in  Table A-2); and

      •     Any belonging  to a stationary source category  that  as  of August  7,
            1980,  is regulated  (effective date  of  promulgation)  by  National
            Emissions Standards for  Hazardous  Air Pollutants  (NESHAP)  pursuant
            to Section  112 of  the Act (listed  in Table  A-2).


Note also  that,  if  a source has been  determined to be major, fugitive  emissions,

to the extent they are  quantifiable, are considered  in  any subsequent  analyses
(e.g., air quality impact).
      Fugitive emissions may  vary  widely from  source  to source.  Examples  of
common sources of fugitive  emission  include:

      •     coal  piles - particulate matter  (PM);

      •     road  dust -  PM;

      •     quarries - PM;  and

      •     leaking  valves  and  flanges  at  refineries  and  organic  chemical
            processing equipment -  volatile  organic compounds  (VOC).
                                     A.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                    TABLE A-l.   PSD  SOURCE  CATEGORIES  WITH
                       100 tpy MAJOR SOURCE THRESHOLDS
 1.    Fossil  fuel-fired steam electric plants of more  than  250  million Btu/hr
      heat  input
 2.    Coal  cleaning  plants  (with  thermal  dryers)
 3.    Kraft pulp  mi 11s
 4.    Portland  cement plants
 5.    Primary zinc smelters
 6.    Iron  and  steel  mill  plants
 7.    Primary aluminum ore  reduction  plants
 8.    Primary copper smelters
 9.    Municipal  incinerators capable of charging more  than  250  tons of refuse
      per day
10.    Hydrofluoric acid plants
11.    Sulfuric  acid  plants
12.    Nitric acid plants
13.    Petroleum refineries
14.    Lime  plants
15.    Phosphate rock processing plants
16.    Coke  oven batteries
17.    Sulfur recovery plants
18.    Carbon black plants (furnace plants)
19.    Primary lead smelters
20.    Fuel  conversion plants
21.    Sintering plants
22.    Secondary metal production  plants
23.    Chemical  process plants
24.    Fossil fuel  boilers   (or combinations  thereof)  totaling  more  than  250
      million Btu/hr heat input
25.    Petroleum  storage and  transfer  units  with  a  total  storage  capacity
      exceeding 300,000 barrels
26.    Taconite ore processing plants
27.    Glass fiber processing plants
28.    Charcoal  production plants
                                     A.11

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
            TABLE A-2. NEW SOURCE PERFORMANCE STANDARDS PROPOSED AND
                NATIONAL  EMISSION  STANDARDS  FOR  HAZARDOUS  AIR  POLLUTANTS
                PROMULGATED PRIOR TO August 7, 1980

New Source Performance Standards 40 CFR 60
Source Subpart
Phosphate rock NN
plants
Affected Facility
Grinding, drying and
calcining facilities
Proposed
Date
09/21/79
Ammonium sulfate
manufacture
   Pp
Ammonium sulfate dryer
02/04/80
National  Emission Standards for Hazardous Air Pollutants 40 CFR 61
    Pollutant
Subpart
Affected Facility
Promulgated
    Date
Beryl 1ium
               Extraction plants,
               ceramic plants,
               foundries, incinerators,
               propellant plants,
               machining operations
                                04/06/73
Beryllium, rocket
motor firing
               Rocket motor firing
                                04/06/73
Mercury
               Ore processing,
               chloralkali  manufacturing,
               sludge incinerators
                                04/06/73
Vinyl  chloride
               Ethylene dichloride
               manufacture via 02 HC1,
               vinyl  chloride manufacture,
               polyvinyl  chloride manufacture
                                10/21/76
Asbestos
               Asbestos mills; roadway         04/06/73
               surfacing (asbestos tailings);
               demolition;  spraying, fabri
               cation, waste disposal  and
               insulting
                                   Manufacture of shotgun
                                   shells,  renovation,
                                   fabrication, asphalt concrete,
                                   products containing asbestos
                                               06/19/78
                                     A.12

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
          TABLE A-2.   NEW SOURCE PERFORMANCE STANDARDS PROPOSED AND
                NATIONAL  EMISSION STANDARDS  FOR HAZARDOUS AIR
                POLLUTANTS PROMULGATED PRIOR TO August 7,  1980

New Source Performance Standards 40  CFR 60
     Source
Subpart
Affected Facility
Proposed
 Date
Fossil-fuel  fired
steam generators for
which construction
is commenced after
08/17/71 and before
09/19/78
                  Utility and industrial
                  (coal ,  oi1, gas,  wood,
                         1i gni te)
                              08/17/71
Elect, utility steam  Da
generating units for
which construction
is commenced after
09/18/78
Storage vessels for
petroleum liquids
construction after
06/11/73 and prior
to 05/19/78
                  Utility boilers (solid,
                  liquid, and gaseous fuels)
                              09/19/78
Municipal incineratorsE
(>50 tons/day)
Portland cement pi
Nitric acid plants
antsF
G
Sulfuric acid plants H
Asphalt concrete
pi ants
Petroleum refineri
I
es J
Incinerators
Kiln, clinker cooler
Process equipment
Process equipment
Process equipment
Fuel gas combustion devices
Claus sulfur recovery
08/17/71
08/17/71
08/17/71
08/17/71
06/11/73
06/11/73
                  Gasoline, crude oil, and
                  distillate storage tanks
                  >40,000 gallons capacity
                              06/11/73
Storage vessels for
petroleum liquids
construction after
05/18/78
    Ka
Gasoline, crude oil,  and
distillate storage tanks
>40,000 gallons capacity,
vapor pressure ;>1.5
05/18/78
Secondary lead
smelters and
refineries
                  Blast and reverberatory
                  furnaces, pot furnaces
                              06/11/73
                                     A.13

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
          TABLE A-2.   NEW SOURCE PERFORMANCE STANDARDS PROPOSED AND
                NATIONAL  EMISSION STANDARDS  FOR HAZARDOUS AIR
                POLLUTANTS PROMULGATED PRIOR TO August 7,  1980

New Source Performance Standards 40  CFR 60
Source Subpart
Secondary brass M
and bronze ingot
production plants
Iron and steel mills N
Sewage treatment 0
pi ants
Primary copper P
smelters
Primary zinc Q
smelters
Primary lead R
smelters
Affected Facility
Reverberatory and electric
furnaces and blast furnaces
Basic oxygen process furnaces
(BOPF)
Primary emission sources
Sludge incinerators
Roaster, smelting furnace,
converter dryers
Roaster sintering machine
Proposed
Date
06/11/73
06/11/73
06/11/73
10/16/74
10/16/74
Sintering machine, electric 10/16/74
smelting furnace, converter
Blast or reverberatory furnace,
sintering machine discharge end
Primary aluminum
reduction plants
Primary aluminum
reduction plants
lll(d)
Pot lines and anode bake      10/23/74
plants
Pot lines and anode bake      04/11/79
plants
Phosphate fertilizer  T
industry              U
                      V
                      W
                      X
Wet process phosphoric        10/22/74
Superphosphoric acid
Diammonium phosphate
Triple superphosphate products
Granular triple superphosphate
products
Coal  preparation     Y
pi ants
Air tables and thermal dryers 10/24/74
Ferroalloy           Z
production facilities
Specific furnaces
10/21/74
                                     A.14

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
          TABLE A-2.   NEW SOURCE PERFORMANCE  STANDARDS PROPOSED AND
                NATIONAL  EMISSION STANDARDS FOR HAZARDOUS AIR
                POLLUTANTS PROMULGATED PRIOR  TO August 7,  1980

New Source Performance Standards 40  CFR 60
Source
Subpart
Affected Faci
11 ty
Proposed
Date
Steel  plants:          AA
electric arc furnaces
              Electric arc furnaces
                              10/21/74
Kraft pulp mi 11s
              Digesters,  lime kiln
              recovery furnace,  washer,
              evaporator,  strippers,
              smelt and BLO tanks
              Recovery furnace,  lime,
              kiln, smelt  tank
                              09/24/76
Glass manufacturing   CC
pi ants
              Glass melting furnace
                              06/15/79
Grain elevators
DD
Truck loading and unloading   01/13/77
stations, barge or ship
loading and unloading stations
railcar loading and unloading
stations, and grain handling
operations
Stationary gas
turbines
GG
Each gas turbine
10/03/77
Lime manufacturing
pi ants
HH
Rotary kiln, hydrator
05/03/77
Degreasers (organic
solvent cleaners)
JJ
Cold cleaner, vapor
degreaser, conveyorized
degreaser
06/11/80
Lead acid battery     KK
manufacturing plants
              Lead oxide production grid    01/14/80
              casting, paste mixing, three-
              process operation and lead
              reelamation
Automobile and
light-duty truck
surface coating
operations
              Prime, guide coat, and
              top coat operations at
              assembly plants
                              10/05/79
                                     A.15

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
      Due to  the variability  even  among similar  sources,  fugitive emissions
should be quantified through  a  source-specific engineering analysis.
Suggested (but  by no means all  of  the useful) references  for fugitive
emissions data  and associated analytic techniques  are  listed in Table  A-3.

      Remember,  if emissions  can be "reasonably" captured and vented through a
stack they are  not considered "fugitive" under EPA regulations.  In  such
cases, these  emissions, to the  extent they are quantifiable, would count
toward the potential to emit  regardless of source  or facility type.

      For example, the emissions from a rock crushing operation that
      could reasonably be equipped with a capture hood are not
      considered fugitive and would be  included  in the source's
      potential to emit.
      As another example. VOC emissions, even if in relatively small
      quantities, coming from leaking valves inside a large furniture
      finishing plant, are typically captured and exhausted through the
      building ventilation system.  They are,  therefore, measurable and
      should be included in the potential to emit.
      As a counter example,  however, it may be unreasonable to  expect
      that relatively small quantities of VOC emissions, caused by
      leaking  valves at outside storage tanks of the large furniture
      finishing operation,  could be captured and vented  to a stack.

II.B.4.   SECONDARY EMISSIONS

      Secondary emissions are not  considered  in  the potential emissions
accounting procedure.  Secondary emissions are those emissions which,  although
associated with a source, are not  emitted from the source itself.  Secondary
emissions occur from any  facility  that is not a  part of the source being
reviewed, but which  would not be constructed  or  increase  its emissions except
as a result of  the construction or operation  of  the major stationary  source or
major modification.   Secondary  emissions do not  include any emissions  from any
off-site  facility which would be constructed  or  increase  its emissions for
some reason other than the construction or operation of the major stationary
source or major modification.
                                       A.16

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      TABLE A-3.   SUGGESTED  REFERENCES  FOR  ESTIMATING  FUGITIVE  EMISSIONS
 1.    Emission  Factors  and  Frequency  of  Leak  Occurrence  for  Fittings  in
      Refinery  Process  Units.   Radian  Corporation.   EPA-600/2-79-044.
      February  1979.

 2.    Protocols  for  Generating  Unit  -  Specific  Emission  Estimates  for
      Equipment  Leaks  of  VOC  and  VHAP.   U.S.  Environmental  Protection  Agency.
      EPA-450/3-88-0100.

 3.    Improving  Air  Quality:  Guidance for  Estimating  Fugitive  Emissions  From
      Equipment.   Chemical  Manufacturers  Association.  January  1989.

 4.    Compilation  of Air  Pollutant  Emission  Factors, 3rd ed.   U.S.
      Environmental  Protection  Agency.   AP-42 (including Supplements  1-8).
      May  1978.

 5.    Technical  Guidance  for  Control  of  Industrial  Process  Fugitive
      Participate  Emissions.  Pedco  Environmental,  Inc.   EPA-450/3-77-010.
      March  1977.

 6.    Fugitive  Emissions  From Integrated  Iron and  Steel  Plants.   Midwest
      Research  Institute,  Inc.   EPA-600/2-78-050.   March 1978.

 7.    Survey of  Fugitive  Dust from  Coal  Mines.   Pedco  Environmental,  Inc.
      EPA-908/1-78-003.  February 1978.

 8.    Workbook  on  Estimation  of Emissions and Dispersion Modeling for Fugitive
      Particulate  Sources.   Utility  Air  Regulatory Group.  September  1981.

 9.    Improved  Emission factors for  Fugitive Dust  from Weston Surface Coal
      Mining Sources,  Volumes I and  II.   U.S. Environmental  Protection Agency.
      EPA-600/7-84-048.

10.    Control  of Open  Fugitive  Dust  Sources.   Midwest  Research  Institute.
      EPA-450/3-88-008.  September  1988.
                                     A.17

-------
                                                                    DRAFT
                                                                    OCTOBER 1990
      An example is the emissions from an existing quarry owned by one
      company that doubles its production to supply aggregate to a
      cement plant proposed for construction as a major source on
      adjacent property by another company.   The quarry's increase in
      emissions would be secondary emissions which the cement plant's
      ambient impacts analysis must consider.
      Secondary emissions  do  not include any emissions which  come  directly
from a mobile source,  such  as emissions from the tailpipe of  a motor  vehicle
or from the propulsion  unit of a train or a vessel.  This exclusion  is
limited, however, to only  those mobile sources that are regulated  under  Title
II of the Act (see 43  FR  26403 - note #9).   Most off-road vehicles are not
regulated under Title  II  and  are usually treated as area sources.  [As a
result of a court decision  in NRDC v. EPA.  725 F.2d 761 (D.C. Circuit 1984),
emissions from vessels  at  berth ("dockside") not to be included  in the
determination of secondary  emissions but are considered primary  emissions  for
applicability purposes.]

      Although secondary  emissions are excluded from the potential emissions
estimates used for applicability determinations, they must be considered in
PSD analyses if PSD review  is required.  In order to be considered,  however,
secondary emissions must  be specific, well-defined, quantifiable,  and impact
the same general area  as  the  stationary source or modification undergoing
review.

II.B.5.  REGULATED POLLUTANTS

      The potential to  emit must be determined separately for each pollutant
regulated by the Act and  emitted by the new or modified source.  Twenty-six
compounds, 6 criteria  and  20  noncriteria, are regulated as air pollutants  by
the Act as of December  31,  1989.  They are  listed in Table A-4.  Note that EPA
has designated PM-10 (particulate matter with an aerodynamic  diameter less
than 10 microns) as a  criteria pollutant by promulgating NAAQS for this
                                      A.18

-------
                                                                      DRAFT
                                                                      OCTOBER 1990

pollutant  as  a  replacement  for total PM.   Thus,  the determination of potential
to emit for  PM-10 emissions  as well as total  PM  emissions  (which are still

regulated  by  many NSPS)  is  required in applicability determinations.  Several
halons and  chlorof1uorocarbon  (CFC) compounds have been  added  to the list  of

regulated  pollutants as  a  result of the  ratification of  the  Montreal Protocol
by the United States in  January 1989.


II.B.6.  METHODS FOR DETERMINING POTENTIAL TO EMIT


       In determining a  source's potential  to  emit, two parameters must  be
measured,  calculated, or estimated  in some way.   They are:


       •      the worst case uncontrolled emissions rate, which is based
             on the dirtiest fuels, and/or the highest emitting materials
             and operating  conditions that the source is or will be
             permitted to use under federally-enforceable requirements,
             and

       •      the efficiency of the air pollution control system,  if any,
             in use or contemplated for the worst case conditions, where
             the use of such equipment is federally-enforceable.
                                       A.19

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
             TABLE A-4.   SIGNIFICANT EMISSION RATES OF POLLUTANTS
                      REGULATED UNDER THE CLEAN AIR ACT

  Pollutant                               Emissions rate (tons/year)


Pollutants listed at 40  CFR 52.21(b)(23)

*     Carbon monoxide                           100
*     Nitrogen oxides3                            40
*     Sulfur dioxideb                            40
*     Particulate matter (PM/PM-10)              25/15
*     Ozone (VOC)                                40 (of VOC's)
*     Lead                                        0.6
      Asbestos                                    0.007
      Beryllium                                   0.0004
      Mercury                                     0.1
      Vinyl chloride                              1
      Fluorides                                   3
      Sulfuric acid mist                          7
      Hydrogen sulfide  (H2S)                      10
      Total Reduced sulfur compounds
      (including H2S)                             10
*  Criteria Pollutants
3  Nitrogen dioxide  is the  compound  regulated  as  a  criteria  pollutant;
   however, significant emissions are based on the sum of all  oxides of
   nitrogen.
b  Sulfur  dioxide  is the  measured surrogate for the criteria  pollutant
   sulfur  oxides.   Sulfur oxides have been made  subject to regulation
explicitly through the proposal  of 40 CFR 60 Subpart J as of
   August  17,  1989.
                                     A.20

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
       TABLE A-4.   (Concluded)  SIGNIFICANT EMISSION RATES OF POLLUTANTS
                      REGULATED UNDER THE CLEAN AIR ACT
  Pollutant                               Emissions rate (tons/year)
Other pollutants regulated by the Clean Air Act:cd
      Benzene                        I

      Arsenic                        I

      Radionucl ides                  I         Any emission rate

      Radon-222                      I

      Polonium-210                   I

      CFC's 11,12, 112, 114, 115     I

      Halons 1211, 1301, 2402        I


c  Significant emission rates have not  been promulgated for these pollutants,
   and until such time, any emissions by a new major sources or any increase
   in emissions at an existing major source due to modification, are
   "signi fi cant. "
d  Regulations covering several  pollutants such as cadmium, coke oven
emissions, and municipal waste incinerator emissions have recently been
proposed.  Applicants should, therefore, verify what pollutants have been
regulated under the Act at the time of application.
                                     A.21

-------
                                                                      DRAFT
                                                                      OCTOBER 1990

      Sources  of the worst-case uncontrolled  emissions  and  applicable  control
system efficiencies could  be any of the  following:


      •      Emissions data from compliance tests or other source tests.

      •      Equipment vendor emissions data and guarantees;

      •      Emission limits and test data from EPA  documents, including
             background information documents  for new source performance
             standards, national emissions standards for hazardous air
             pollutants, and Section Hid standards  for designated
             pollutants;
      •      AP-42 emission factors (see Table A-3,  Reference 2);
      •      Emission factors from  technical literature; and
      •      State emission inventory questionnaires for comparable sources.


      The  effect of other  restrictions (federally-enforceable and practically-
enforceable) should also be  factored into  the results.   The potential  to  emit
of each pollutant, including fugitive emissions if applicable,  is estimated
for each individual emissions unit.  The individual estimates are then  summed
by pollutant over all  the  emissions units  at  the stationary source.


II.C.  EMISSIONS THRESHOLDS  FOR PSD APPLICABILITY


11. C.I.  MAJOR SOURCES


      A source is a "major stationary source" or "major emitting facility"  if:
       (1)    It can be classified in one  of the 28 named source
             categories listed in Section 169 of the CM (see Table A-l)
             and it emits  or has the potential to emit 100 tpy or more of
             any pollutant regulated by the Act, or

       (2)    it is any other stationary source that emits or has the
             potential to  emit 250 tons per year or more of any pollutant
             regulated by  the CAA.

             For  example,   one  of  the   28   PSD  source  categories   subject  to
             the   100-tpy   threshold  is  fossil    fuel-fired   steam   generators
             with   a   heat    input   greater   than    250    million   Btu/hr.
             Consequently,  a  300  million Btu/hr boiler  that  is  designed  and

                                       A.22

-------
                                                                         DRAFT
                                                                         OCTOBER 1990

             permitted   to   burn   any   fossil   fuel,   i.e.,   coal,   oil,   natural
             gas  or   lignite,  that  emits  100  tpy  or  more  of  any  regulated
             pollutant,   e.g.,   S02,   is   a   major   stationary   source.      If,
             however,   the   boiler  were  designed  and  permitted  to  burn   wood
             only,  it  would not  be classified as  one  of  the  28  PSD  sources
             and would  instead be  subject to the 250 tpy threshold.

             A  single,   fossil   fuel-fired  boiler  with  a  maximum  heat  input
             capacity   of  300  million  Btu/hr  takes   a   federally-enforceable
             design   limitation   that   restricts   heat    input   to   240   million
             Btu/hr.      Consequently,   this   source  would  not   be  classified
             within  one  of  the  28  categories  and  would  therefore be  subject
             to  the   250-tpy,  rather  than   the  100-tpy.  emissions  threshold.
       A  situation  frequently occurs  in which  an emissions unit  that is
included in the  28 listed  source categories  (and so is  subject  to a 100  tpy
threshold), is located within a parent source whose primary activity is  not on
the list (and is  therefore subject  to a 250  tpy threshold).  A  source which,
when  considered  alone, would be major (and hence subject to PSD)  cannot  "hide"
within a different and less restrictive source category in order  to escape
applicabi1ity.
      As  an  example,   a  proposed  coal  mining  operation  will  use  an  on-site   coal
      cleaning  plant  with a  thermal  dryer.   The  source  will be  defined as  a   coal
      mine  because  the  cleaning plant  will  only   treat  coal  from  the  mine.     The
      mine's  potential   to  emit  (including   emissions  from  the   thermal  dryer)   is
       less   than   250  tpy   for  every  regulated   pollutant;   therefore,  it   is  a
       "minor"  source.     The  estimated  emissions   from   the   thermal  dryer,   however.
      will  be  150  tpy  particulate  matter.    Thermal   dryers  are  included  in   the
       list  of  28  source  categories  that  are subject  to  the  100  tpy  major source
      threshold.      Consequently,    the   thermal   dryer   would   be   considered    an
      emissions  unit  that  by   itself  is  a  major  source  and therefore  is  subject
      to PSD review,  even though the primary activity is not.

       Furthermore, when  a  "minor"  source,  i.e.,  one  that does  not meet the
definition of  "major,"  makes  a physical  change or change in the method of
operation that is by itself a major  source,  that  physical or  operational
change  constitutes a major stationary source that is  subject  to PSD  review.
                                         A.23

-------
                                                                          DRAFT
                                                                          OCTOBER 1990

To   illustrate,   consider   the   following   scenarios   at   an   existing   glass   fiber
processing   plant,   which  proposes  to   add   new  equipment  to   increase  production.
Glass  fiber  processing  plants  are  included  in  the   list of 28   source  categories
that  are  subject  to  the  100-tpy major  source  threshold.    The  existing plant  emits
40  tpy particulate,  which  is  both  its  potential  to  emit  and  permitted  allowable
rate.   It  also  has  a  potential  to  emit  all  other  pollutants  in  less than  major
quantities;  therefore it  is  a minor source.

       Scenario   1   -   The   physical    change   will   increase   the  source's
       potential  to  emit  particulate  matter  by  50  tpy.    Since  the  plant  is
       a minor  source  and  the   increase   is  not  major  by  itself,   the   change
       is not  subject to  PSD review.

       Scenario   2   -   The   physical    change   will   increase   the  source's
       potential  to  emit  particulate  matter  by  65  tpy.    Since  the  plant  is
       a minor  source  and  the   increase   is  not  major  by  itself,   neither  is
       subject  to  PSD  review.      However,   the  source's  potential  to  emit
       after  the  change  will  exceed  the  100-tpy  major  source   threshold,   so
       future    modifications    will    be    scrutinized    under    the   netting
       provisions (see section A.3.2).

       Scenario   3   -   The   physical    change   will   increase   the  source's
       potential  to  emit  particulate  matter  by  110 tpy.    Since   the  existing
       plant  is  a  minor  source  and  the  change  by  itself  results  in   an
       emissions   increase   greater   than   the   major   source   threshold,   that
       change   is   subject   to  PSD   review.     Furthermore,   the  physical   change
       makes  the  entire plant  a  major  source,  so  future physical   changes  or
       changes  in   the   method  of   operation  will   be   scrutinized   against  the
       criteria  for major modifications (see section II.A.3.2).
II.C.2.   SIGNIFICANT  EMISSIONS


       A PSD  review  is  triggered in  certain  instances  when emissions  associated
with  a new major source or  emissions  increases resulting from a major
modification  are "significant."  "Significant" emissions thresholds  are
defined two  ways.   The first  is in  terms of  emission  rates  (tons/year).

Table  A-4 listed the  pollutants for which significant emissions rates have
been  established.


       Significant increases  in emission rates  are subject to  PSD review in two

ci rcumstances:
                                         A.24

-------
                                                                    DRAFT
                                                                    OCTOBER 1990

'.!)   For a new  source  which is major for at least  one  regulated attainment or
      noncriteria  pollutant, i.e., is subject to  PSD  review,  all pollutants
      for which  the  area  is not classified as nonattainment and which are
      emitted  in  amounts  equal  to or greater than those specified in Table A-4
      are also subject  to PSD review for its VOC  emissions.
For  example,  an  automotive  assembly  plant   is  planned  for  an  attainment   area  for
all  criteria  pollutants.    The  plant  has  a  potential  to  emit  350  tpy VOC, 50  tpy
NOK,  60  tpy  S02,and 10 tpy PM  including  5 tpy      PM-10.   The 350 tpy VOC exceeds
the  major  source   threshold,  and  therefore subjects  the  plant  to  PSD  review.    The
"significant"  emissions  thresholds  for NOX and  S02  are   40  tpy:  therefore,  the  NOX
and  SO? emissions,  also,   will  be  subject  to  PSD  review.    The  PM and   PM-10
emissions  will  not  exceed  their  significant   emissions   thresholds;  therefore  they
are not subject to  review.
(2)   For a modification to an existing major  stationary source, if both the
      potential  increase in emissions due to the  modification itself, and the
      resulting  net  emissions increase of any  regulated, attainment or
      noncriteria  pollutants are equal to or greater  than the respective
      pollutants'  significant emissions rates  listed  in Table A-4, the
      modification is  "major," and  subject to  PSD  review.   Modifications are
      discussed  in detail  in Section  II.D.

      The second type  of "significant" emissions  threshold  is defined as any
emissions rate  at  a  new major stationary source (or any net emissions increase
associated with  a  modification to an  existing  major stationary source) that  is
constructed within 10  kilometers of a Class I  area, and which would increase
the 24-hour average  concentration of  any regulated  pollutant in that area by  1

ug/m3  or greater.  Exceedence of  this  threshold triggers PSD  review.


II.D.    LOCAL  AIR QUALITY CONSIDERATIONS FOR CRITERIA  POLLUTANTS


      The air quality, i.e., attainment status, of  the area of a proposed new

source  or modified existing source will impact  the  applicability determination

in regard to  the pollutants that are  subject to PSD review.  As previously

stated,  if a  new source locates in an area designated attainment or

unclassifiable  for any criteria pollutant, PSD  review will  apply to any
                                      A.25

-------
                                                                       DRAFT
                                                                       OCTOBER  1990

pollutant  for which the  potential to  emit is major  (or  significant,  if the
source  is  major) so long as the area  is  not nonattainment for that pollutant.
      For example, a kraft pulp mill is proposed for an attainment area
      for S02, and its potential to emit S02 equals 55 tpy.  Its
      potential to emit  total reduced sulfur (TRS) a noncriteria
      pollutant, equals  295 tpy.   Its potential to emit I/OC will be 45
      tpy and PM/PM-10,  30/5 tpy;  however,  the area is designated
      nonattainment for  ozone and  PM.  Applicability would be assessed
      as follows:

             The source  would be major and subject to PSD review due to
             the noncriteria TRS emissions.

             The S02 emissions  would therefore be subject to PSD because
             they are significant  and the area  is attainment for S02.

             The  VOC emission and  PM emissions would not be subject to
             PSD, even though their emissions are significant, because
             the area is designated nonattainment for those pollutants.

             The PM-10 emissions are neither major nor significant and
             would therefore not be subject to review.


Similarly,  if the modification of an  existing major  source,  which  is located

in an attainment area for  any  criteria pollutant,  results in a significant
increase  in potential  to emit  and a  significant net  emissions increase,  the
modification is subject  to  PSD, unless the location  is  designated  as

nonattainment for that pollutant.


      Note that if the source  is major for a pollutant  for which an  area  is
designated nonattainment,  all  significant emissions  or  significant emissions
increases  of pollutants  for which the area is attainment  or  unclassifiable are
still subject to PSD  review.


II.E.   SUMMARY OF MAJOR  NEW SOURCE APPLICABILITY


      The  elements and associated information necessary  for  determining  PSD

applicability to new  sources are outlined as follows:
                                       A.26

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Element 1  -  Define  the  source
      •     includes  all  related  activities  classified  under  the  same  2-digit
            SIC  Code  number

      •     must have the same  owner  or  operator

      •     must be located  on  contiguous  or adjacent  properties

      •     includes  all  support  facilities
Element 2 -  Define applicability thresholds for major source as a  whole
              (primary activity)
      •     100 tpy for individual  emissions units or groups of units
            that are included in the list of 28 source categories
            identified in Section 169 of the CAA

      •     250 tpy for all  other sources


Element 3 - Define project emissions (potential to emit)


      •     Reflects federally-enforceable air pollution  control  efficiency,
            operating conditions, and permit limitations

      •     Determined for each pollutant by each emissions unit

      •     Summed by pollutant over all emissions units

      •     Includes fugitive emissions for 28 listed source categories
            and sources subject to NSPS or NESHAPS as of  August 7, 1980



Element 4 - Assess local area attainment status
            Area must be attainment or unclassifiable for at least one
            criteria pollutant for PSD to apply
                                     A.27

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

Element 5 -  Determine if source is major by comparing its potential  emissions
              to appropriate major source threshold
            Major if any pollutant emitted by defined source exceeds
            thresholds,  regardless of area designation,  i.e.,
            attainment,  nonattainment,  or noncriteria pollutants

            Individual  unit is major if classified as a  source in  one of
            the 28 regulated source categories and emissions exceed an
            applicable  100-tpy threshold
Element 6 - Determine pollutants subject to PSD review
            Each attainment area and noncriteria pollutant emitted in
            "significant" quantities
            Any emissions or emissions increase from a major source that
            results in an increase of 1 M9/f3  (24  hour  average) or  more
            in a Class I area if the major source is located or
            constructed within 10 kilometers of that Class I area.
II.F.  NEW SOURCE APPLICABILITY EXAMPLE


    The following example provided is for illustration only.  The example source

is fictitious and has been created to highlight many of the aspects of the PSD

applicability process for a new source.


      In this example the proposed  project is a new coal-fired electric plant.

The plant will have two 600-MW lignite-fired boilers.  The proposed location

is near a separately-owned surface  lignite mine, which will  supply the fuel

requirements of the power plant,  and will  therefore,  have to increase its

mining capacity with new equipment.   The lignite coal will be  mined and then

transported to the power plant to be crushed, screened, stored,  pulverized and

fed to the boilers.  The power plant has informed the lignite  coal  mine that

the coal will not have to be cleaned,  so the mine will not expand its coal

cleaning capacity.  The power plant  will have on-site coal and limestone
                                     A.28

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
storage and handling  facilities.   In  addition,  a  comparatively  small  auxiliary
boiler will  be installed  to  provide  steam  for  the facility  when  the  main
boilers are inoperable.   The area  is  designated attainment  for  all criteria
pol1utants.

     The applicant proposes  pollution control  devices  for  the two  600-MW
boilers which include:

      - an electrostatic  precipitator (ESP)  for PM/PM-10 emissions control,
      - a limestone scrubber flue  gas desulfurization  (FGD) system for
        S02  emissions control;
      - low-nitrogen  oxide (NOX) burners and low-excess-air firing for
        NOX  emissions control;  and
      - controlled combustion for  CO emissions control.
     The first step is to determine what constitutes the source (or sources).
A source is defined as all  pollutant-emitting activities associated with the
same industrial  grouping, located on contiguous or adjacent sites,  and under
common control or ownership.  Industrial groupings are generally defined by
two-digit SIC codes.  The power plant is classified as SIC major group 49;  the
nearby mine is SIC major group 12.  They are neither under the same SIC major
group number nor have the same owners, so they constitute separate sources.

      The second step is to establish which major source thresholds are
applicable in this case.  The proposed power plant is a fossil fuel-fired
steam electric plant with more than 250 million Btu/hr of heat input, making
it a source included in one of the 28 PSD-listed categories.  It is therefore
subject to both the 100 ton per year criterion for any regulated pollutant
used to determine whether a source is major and to the requirement that
quantifiable fugitive emissions be included in determining potential  to emit.
                                     A.29

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
     The emissions units at the mine are neither classified within one of  the
28 PSD source categories nor regulated under Sections 111 or 112 of the Act.
Therefore,  the mine is compared against the 250 tpy major source threshold and
fugitive emissions from the mining operations are exempt from consideration in
determining whether the mine is a major stationary source.

      The third step is to define the project emissions.  To arrive at the
potential to emit of the proposed power plant,  the applicant must consider all
quantifiable stack and fugitive emissions of each regulated pollutant (i.e.,
S02,  NOX) PM, PM-10, CO, VOC, lead, and the noncriteria pollutants).
Therefore,  fugitive PM/PM-10 emissions from haul roads,  disturbed areas,  coal
piles, and  other sources must be included in calculating the power plant's
potential to emit.

      All stack and fugitive emissions estimates have been  obtained through
detailed engineering analysis of each emissions unit using  the best available
data or estimating technique.  Fugitive emissions are added to the emissions
from the two main boilers and the auxiliary boiler in order to arrive at  the
total potential to emit of each regulated pollutant.  The auxiliary boiler in
this case is restricted by enforceable limits on operating  hours proposed  to
be included in the source's PSD permit.  If the auxiliary boiler were not
limited in  hours of operation,  its contribution would be based on full,
continuous  operation,  and the resulting potential  emissions estimates would be
higher.

     The potential to  emit S02,  NOX, PM, CO, and sulfuric acid mist each
exceeds 100 tons per year.  From data collected at other lignite fired power
plants it is known that emissions of lead,  beryllium, mercury, fluorides,
sulfuric acid mist and arsenic  should also  be quantified.  It is known that
fluoride compounds are contained in the coal in significant quantities;
however, engineering analyses show fluoride removal  in the  proposed limestone
scrubber will result in insignificant stack emissions.  Similarly, liquid
absorption, absorption of fly ash removed in the ESP, and removal  of bottom
                                     A.30

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
ash have been  shown  to  maintain  emissions  of  lead  and  the  other  regulated
noncriteria  pollutants  below significance  levels.

      The only emissions  at the  existing mine,  and consequently  the  only
emissions increase that will  occur from the expansion  to  serve the power
plant, are fugitive  PM/PM-10 emissions  from mining operations.   The  mine's
potential to emit, for  PSD applicability purposes, is  zero and the mine  is  not
subject to a PSD review.   The increase  in  fugitive emissions  from  the  mine,
however, will  be classified as secondary emissions  with  respect to  the  power
plant and, therefore,  must be considered in the air quality analysis and
additional impacts analysis for  the proposed  power plant  if the  power  plant  is
subject to PSD review.

      The next step  is  to compare the potential emissions  of  the power plant
to the 100 ton per year major source threshold.  If the potential  to emit  of
any regulated  pollutant is 100 tons per year  or more,  the  power  plant  is
classified as  a major  stationary source for PSD purposes.   In this case,  the
plant is classified  as  a  major source because S02,  NOX, PM, CO,  and sulfuric
acid mist emissions  each  exceed  100 tons per  year.  (Note  that emissions  of
any one of these pollutants classifies  the source  as major.)

      Once it  has been  determined that  the proposed source is major, any
regulated pollutant  (for  which the location of the source  is  not classified as
nonattainment) with  significant  emissions  is  subject to a  PSD review.   The
applicant quantified,  through coal and  captured fly ash analyses and through
performance test results  from existing  sources burning equivalent  coals,
emissions of fluorides, beryllium, lead, mercury,  and the  other  regulated
noncriteria pollutants  to determine if  their emissions exceed the  significance
levels  (see Table A-4.).   Pollutants with  less than significant  emissions are
not subject to PSD review requirements  (assuming the proposed controls are
accepted  as BACT for S02,  or the application  of BACT for S02  results in
equivalent or lower noncriteria  pollutant  emissions).
                                     A.31

-------
                                                                  DRAFT
                                                                  OCTOBER 1990


      Note that,  because the proposed construction site is not within 10

kilometers of a Class I area, the source's emissions are not subject to the

Class I  area significance criteria.
                                     A.32

-------
                                                                   DRAFT
                                                                   OCTOBER  19913
III.  MAJOR MODIFICATION APPLICABILITY
      A modification is subject to  PSD  review  only  if (1)  the existing source
that is modified is "major," and  (2)  the  net emissions increase of any
pollutant emitted by the source,  as  a result of  the modification, is
"significant," i.e., equal to or  greater  than  the  emissions rates given on
Table A-4 (unless the source is located in  a nonattainment area for that
pollutant).  Note also that any net  emissions  increase in  a regulated
pollutant at a major stationary source  that is located within 10 kilometers of
a Class I area, and which will cause  an increase of 1 pg/m3 (24  hour average)
or more in the ambient concentration  of that pollutant within that Class I
area, is "significant".

      Typical   examples   of  modifications   include   (but  are   not   limited   to)
      replacing  a   boiler  at  a  chemical  plant,  construction  of  a   new  surface
      coating  line  at  an  assembly  plant,   and  a  switch  from  coal  to gas  requiring
      a physical change to the plant,  e.g., new piping,  etc.

      As discussed earlier, when  a "minor"  source,  i.e., one that does not meet
the definition of  "major,"  makes  a physical change or change in the method of
operation that is by itself a major source, that physical or operational change
constitutes a  ma.ior stationary source that  is  subject to PSD review.  Also, if
an existing minor source becomes  a major source as  a result  of  a SIP  relaxation,
then it becomes subject to PSD requirements just as if construction  had not yet
commenced on the source or the modification.

III.A.  ACTIVITIES THAT ARE NOT MODIFICATIONS

      The regulations do  not define "physical  change" or "change in the method
of  operation"  precisely;  however,  they exclude from  those activities certain
specific types of  events  described below.

       (1)   Routine maintenance,  repair and replacement.
                                      A.33

-------
                                                                   DRAFT
                                                                   OCTOBER 1990

            [Sources   should    discuss    any    project   that   will
            significantly   increase    actual    emissions    to    the
            atmosphere   with   their   respective   permitting  authority,
            as    to   whether   that   project   is  considered   routine
            maintenance, repair or replacement.]

      (2)   A fuel switch due to an order  under  the  Energy  Supply and
            Environmental Coordination Act of  1974  (or  any   superseding
            legislation) or due to a natural gas curtailment  plan under the
            Federal Power Act.

      (3)   A fuel switch due to an order  or rule under section  125 of the
            CAA.

      (4)   A switch at a steam generating unit  to  a  fuel  derived in whole or
            in part from municipal solid waste.

      (5)   A switch to a fuel  or raw material which  (a)  the  source was
            capable of accommodating before January  6,  1975,  so  long as
            the switch would not be prohibited by any federally-
            enforceable permit  condition established  after  that  date
            under a federally approved SIP (including any PSD permit
            condition) or a federal PSD  permit,  or  (b)  the  source is
            approved to make under a PSD permit.

      (6)   Any increase in the hours or rate  of operation  of a  source,
            so long as the increase would  not  be prohibited by any
            federally-enforceable permit condition  established after
            January 6, 1975 under a federally  approved  SIP  (including
            any PSD permit condition) or a federal  PSD  permit.

      (7)   A change in the ownership of a stationary source.

For more details see 40 CFR 52.2Kb) (2) (iii).
      Notwithstanding the above, if  a  significant  increase in actual  emissions
of a regulated pollutant occurs at an  existing  major  source as a  result of a
physical  change or change in the method  of  operation  of  that source,  the "net
emissions increase" of that pollutant  must  be determined.


III.B.  EMISSIONS NETTING


      Emissions netting is a term that refers to the  process of considering
certain previous and prospective emissions  changes  at an existing major source
to determine if a "net emissions increase"  of a pollutant  will result from a

                                     A.34

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
proposed physical  change or change  in  method of operation.   If a net emissions
increase is  shown  to result, PSD  applies to each pollutant's emissions  for
which the  net  increase is "significant", as shown in  Table  A-4.

      The  process  used to determine whether there will  be a net emissions
increase will  result uses the following equation:

                             Net Emissions Change
                                      EQUALS
         Emissions increases associated with the proposed modification
                                      MINUS
           Source-wide creditable  contemporaneous emissions decreases
                                       PLUS
           Source-wide creditable  contemporaneous emissions increases

Consideration  of contemporaneous  emissions changes  is allowed  onlv  in  cases
involving  existing ma.ior sources.   In  other words,  minor sources are not
eligible to  net emissions changes.   As discussed earlier, existing  minor
sources  are  subject to PSD  review only when proposing to increase emissions  by
"major"  (e.g., 100 or 250 tpy,  as applicable)  amounts,  which,  for PSD
purposes,  are  considered and reviewed  as a major new  source.
       For  example,  an  existing  minor  source  (subject  to  the  100  tpy  major  source
       cutoff)   is   proposing  a   modification  which   involves  the   shutdown  and
       removal  of   an   old   emissions  unit  (providing   an   actual   contemporaneous
       reduction   in  A/Ox  emissions  of  75  tpy)   and  the  construction  of  two  new
       units  with  total  potential  NOx  emissions   of 110  tpy.    Since  the  existing
       source   is   minor,   the  75   tpy   reduction   is   not   considered   for  PSD
       applicability  purposes.      Consequently,   PSD  applies   to   the  new   units
       because  the  emissions   increase  of  110  tpy  is   itself  "major".     The  new
       units  are  then  subject  to  a PSD  review  for  NOx   and  for  any  other  regulated
       pollutant  with a  "significant"  potential to emit.

       The consideration of  contemporaneous emissions changes is  also  source
 specific.  Netting must take place  at the  same  stationary  source;  emissions
 reductions cannot  be traded  between stationary  sources.
                                       A.35

-------
                                                                       DRAFT
                                                                       OCTOBER 1990
III.B.I.   ACCUMULATION OF  EMISSIONS
       If  the proposed emissions increase at a major  source is by  itself

(without  considering any  decreases)  less than "significant", EPA  policy does

not require  consideration of previous  contemporaneous  small (i.e.,  less than

significant) emissions  increases at  the  source.   In  other words,  the  netting

equation  (the summation of contemporaneous emissions  increases and  decreases)

is not  triggered unless there will be  a  significant  emissions increase from

the proposed modification.
      For  example,  a  major  source  experienced  less  than  significant   increases   of
      NOX  (30  tpy)  and S02  (15  tpy) 2 years  ago,  and  a  decrease  of S02  (50  tpy)
      3  years  ago.     The  source  now proposes  to  add  a new  process  unit  with   an
      associated  emissions  increase  of 35  tpy  NOX  and  80  tpy S02.    For  S02,   the
      proposed  80  tpy  increase  from  the   modification   by   itself  (before  netting)
      is   significant.     The  contemporaneous   net   emissions   change   is   determined,
      by  taking  the  algebraic  sum  of (-50) and  (+15)  and   (+80),  which  equals  +45
      tpy.    Therefore,  the  proposed  modification  is   a major  modification  and  a
      PSD  review  for  502  is  required.     However,   the   NOX  increase   from   the
      proposed  modification  is  by  itself   less   than   significant.     Consequently,
      netting  for  PSD  applicability  purposes  is  not  performed  for  NOX   (even
      though  the  modification  is  major  for  S02)  and  a  PSD  review  is   not  needed
      for NO,.
It is  important to note  that when any  emissions decrease is claimed  (including

those  associated with the  proposed modification),  al1  source-wide  creditable

and contemporaneous emissions increases  and decreases  of the pollutant subject
to netting  must be included in the PSD applicability  determination.


       A  deliberate decision to split an  otherwise  "significant" project into

two or more smaller projects to avoid  PSD review would be viewed as
circumvention and would  subject the entire project  to  enforcement  action if

construction on any of the small projects commences without a valid  PSD

permit.
For  example,   an  automobile  and  truck   tire  manufacturing  plant,  an  existing  major
source, plans  to increase its production of both types of tires by


                                        A.36

-------
                                                                     DRAFT
                                                                     OCTOBER 1990

      "debottlenecking"  its  production  processes.     For  its   passenger   tire   line,
      the  source  applies   for  and  is  granted  a  "minor"  modification  permit  for  a
      new  extruder that will  increase  VOC  emissions by  39  tons/yr.   A  few  months
      later,   the  source   applies  for  a   "minor"   modification   permit  to  construct
      a   new   tread-end  cementer   on  the  same    line   which   will  increase  VOC
      emissions  by 12  tons/yr.   The  EPA  would  likely consider these proposals  as
      an   attempt   to   circumvent  the   regulations   because  the  two  proposals  are
      related  in terms of an
      overall project to increase source-wide production capacity.  The
      important  point  in   this  example  is   that  the two  proposals  are  sufficiently
      related  that  the PSD  regulations would consider  them a single project.
      Usually,  at least two basic  questions should  be  asked when evaluating
the construction  of multiple minor projects to determine if they should  have
been considered a single project.   First, were the  projects proposed  over  a

relatively  short  period of time?   Second, could the changes be considered  as

part of a single  project?


III.B.2.  CONTEMPORANEOUS EMISSIONS CHANGES


      The PSD definition of a  net  emissions increase [40 CFR 52.2Kb) (3) (i) ]
consists of two additive components as follows:

      (a)    Any increases in actual emissions from  a particular physical
             change or change in method of operation at a stationary  source;
             and

      (b)    Any other increase and decreases j_n actual  emi ssions at  the  source
              that are contemporaneous with the particular change and  are
               otherwise creditable.

      The first component narrowly includes only  the emissions increases
associated  with a particular change at the source.   The second component more

broadly includes  all contemporaneous, source-wide (occurring anywhere at the

entire source), creditable emission increases and decreases.


      To be contemporaneous. changes in actual emissions must have  occurred
after January 6,  1975.  The changes must also occur within a period  beginning

5 years before the date construction is expected  to commence on the  proposed
                                       A.37

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
modification (reviewing agencies may use the date construction is scheduled to
commence provided that it is reasonable considering the time needed to issue a
final  permit)  and ending when the emissions increase from the modification
occurs.   An increase resulting from a physical  change at a source occurs  when
the new  emissions unit becomes operational  and  begins to emit a pollutant.  A
replacement that requires a shakedown period becomes operational  only after a
reasonable shakedown period, not to exceed  180  days.  Since the date
construction actually will  commence is unknown  at the time the applicability
determination  takes place and is simply a scheduled date projected by the
source,  the contemporaneous period may shift if construction does not commence
as scheduled.   Many States  have developed PSD regulations that allow different
time frames for definitions of contemporaneous.  Where approved by EPA,  the
time periods specified in these regulations govern the contemporaneous
timeframe.

III.B.3.  CREDITABLE CONTEMPORANEOUS EMISSIONS  CHANGES

      There are further restrictions on the contemporaneous emissions changes
that can be credited in determining net increases.  To be creditable, a.
contemporaneous reduction must be federally-enforceable on and after the  date
construction on the proposed modification begins.  The actual reduction  must
take place before the date  that the emissions increase from any of the new or
modified emissions units occurs.  In addition,  the reviewing agency must
ensure that the source has  maintained any contemporaneous decrease which  the
source claims  has occurred  in the past.  The source must either demonstrate
that the decrease was federally-enforceable at  the time the source claims it
occurred, or it must otherwise demonstrate  that the decrease was maintained
until  the present time and  will continue until  it becomes federally-
enforceable.  An emissions  decrease cannot  occur at. and therefore, cannot be
credited from  an emissions  unit which was never constructed or operated.
including units that received a PSD permit.

      Reductions must be of the same pollutant  as the emissions increase  from
the proposed modification and must be qualitatively equivalent in their

                                     A.38

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
effects on public health and welfare to the effects  attributable to the
proposed increase.   Current EPA policy is to assume  that  an  emissions  decrease
will  have approximately the same qualitative significance for  public health
and welfare as that attributed to an increase,  unless  the reviewing agency  has
reason to believe that the reduction in ambient concentrations from the
emissions decrease will not be sufficient to prevent the  proposed emissions
increase from causing or contributing to a violation of any  NAAQS or PSD
increment.  In such cases, the applicant must demonstrate that the proposed
netting transaction will not cause or contribute to  an air quality violation
before the emissions reduction may be credited.  Also, in situations where  a
State is implementing an air toxics program, proposed  netting  transactions  may
be subject to additional tests regarding the health  and welfare equivalency
demonstration.  For example, a State may prohibit netting between certain
groups of toxic subspecies or apply netting ratios greater than the normally
required 1:1 between certain groups of toxic pollutants.

      A contemporaneous emissions increase occurs as the  result of a physical
change or change in the method of operation at the source and  is creditable  to
the extent that the new emissions level exceeds the  old emissions level.  The
"old" emissions level for an emissions unit equals the average rate (in tons
per year) at which the unit actually emitted the pollutant during the 2-year
period just prior to the physical or operational change which  resulted in the
emissions increase.  In certain limited situations where the applicant
adequately demonstrates that the prior 2 years is not representative of normal
source operation, a different  (2 year) time period may be used upon a
determination by the reviewing agency that it  is more representative of normal
source operation.  Normal source operations may be affected by strikes,
retooling, major industrial accidents and other catastrophic occurrences.  The
"new" emissions levels for a new or modified emissions unit which has not
begun normal operation  is its  potential to emit.

       An emissions increase or decrease  is creditable only if the  relevant
reviewing authority has not relied  on it  in issuing a PSD permit for the
source,  and the permit  is still in  effect when the increase in actual

                                     A.39

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
emissions from  the proposed modification occurs.  A  reviewing authority  relies
on an increase  or decrease when,  after taking the increase or decrease  into
account, it  concludes that a proposed project would  not cause or contribute to
a violation  of  an increment or  ambient standard.  In  other words, an  emissions
change at an  emissions point which  was considered in  the issuance of  a
previous PSD  permit for the source  is not included in the source's  "net
emissions increase" calculation.  This is done to avoid "double counting"  of
emissions changes.
      For  example,   an   emissions   increase  or  decrease  already  considered  in  a
      source's   PSD   permit   (state   or   federal)   can   not   be   considered   a
      contemporaneous   increase  or  decrease  since  the   increases  or  decrease  was
      obviously  relied  upon  for  the  purpose  of  issuing  the   permit.     Otherwise
      the  increase or  decrease  would  not  have been  specified  in  the permit.    In
      another   example,   a  decrease  in  emissions   from  having   previously  switched
      to  a less  polluting fuel   (e.g.,  oil  to gas)  at  an  existing  emissions  unit
      would not   be   creditable   if  the   source  had,  in   obtaining   a   PSD  permit
      (which  is  still   in  effect)  for a  new  emissions  unit,  modeled the  source's
      ambient impact using the  less polluting  fuel.
      Changes  in PM (PM/PM-10),  S02 and  NOX emissions are a subset  of
creditable  contemporaneous changes  that also affect  the available  increment.
For these pollutants,  emissions  changes which do not affect allowable  PSD
increment consumption  are not  creditable.

III.B.4.  CREDITABLE AMOUNT

      As mentioned above, only contemporaneous and creditable emissions
changes are considered in determining the source-wide net emissions  change.
All contemporaneous and creditable  emissions increases and decreases at  the
source must,  however,  be considered.   The amount of  each contemporaneous and
                                       A.40

-------
                                                                    DRAFT
                                                                    OCTOBER 1990

creditable emissions  increase or decrease involves determining old and new

actual annual emissions  levels for each affected emission  unit.


     The following  basic criteria should be used when  quantifying the increase

or decrease:
      >      For  proposed  new or modified units which  have not begun normal
             operations,  the potential to emit must  be used to determine the
             increase  from the units.

      >•      For  an  existing unit, actual emissions  just prior to either a
             physical  or  operational change are based  on the lower of the
             actual  or allowable emissions levels.   This "old" emissions level
             equals  the average rate (in tons per year)  at which the unit
             actually  emitted the pollutant during the 2-year period just prior
             to the  change which resulted in the emissions increase.  These
             emissions are calculated using the actual  hours of operation,
             capacity, fuel  combusted and other parameters which affected the
             unit's  emissions over the 2-year averaging  period.  In certain
             limited circumstances, where sufficient representative operating
             data do not  exist to determine historic actual emissions and the
             reviewing agency has reason to believe  that the source is
             operating at  or near its allowable emissions level, the reviewing
             agency  may presume that source-specific allowable emissions [or a
             fraction  thereof] are equivalent to  (and  therefore are used in
             place of) actual emissions  at the  unit.  For determining the
             difference in emissions from the change at  the unit, emissions
             after the change are the potential to emit  from the units.

      >•      A  source  cannot receive emission reduction  credit for reducing  any
             portion of actual emissions which  resulted  because the source was
             operating out of compliance.

      >      An emissions  decrease cannot be credited  from a unit that  has not
             been constructed or operated.

      Examples    of    how   to   apply   these   creditability   criteria    for
      prospective   emissions  reductions  is  shown  in Figure  A-l.    As  shown
      in  Case  I  of   Figure  A-l,  the  potential   to  emit   for  an  existing
      emissions   unit  (which   is  based  on   the  existing   allowable  emission
      rate)  is  greater   than  the  actual  emissions,    which  are  based   on
      actual  operating data  (e.g.,   type  and  amount  of   fuel  combusted  at
      the  unit)  for  the  past  2 years.    The  source proposes to  switch to  a
       lower  sulfur  fuel.    The  amount  of the reduction  in  this  case  is  the
      difference   between   the  actual  emissions  and  the   revised  allowable
      emissions.   (Recall  that
                                      A.41

-------
                                                                       DRAFT
                                                                       OCTOBER 1990

for  reductions   to  be  creditable,  the   revised   allowable  emission  rate   must
be ensured with federally-enforceable limits.)

Figure  A-l   also  illustrates  in  Case  _II   that   the  previous  allowable
emissions   were  much   higher   than   the   potential   to   emit.     Common
examples  are  PM  sources   permitted   according  to  process  weight  tables
contained   in   most  SIPs.     Since  process   weight   tables   apply  to   a
range  of   source  types,    they  often   overpredict   actual  emission  rates
for  individual  sources.     In such  cases,  as  in  the  previous  case,  the
only   creditable   contemporaneous   reduction   is   the   difference  between
the  actual  emissions  and  the  revised  allowable  emission  rate   for  the
existing emissions unit.
Case   III   in  Figure  A-l   illustrates  a   potential   violation  situation
where   the   actual   emissions    level   exceeds   allowable   limit.       The
creditable  reduction  in  this  case  is  the  difference  between  what   the
emissions   would   have  been   from   the   unit  had   the  source   been   in
compliance   with    its   old  allowable   limits   (considering   its   actual
operations) and its revised allowable emissions level.
Consider  a   more  specific  example,   where  a  source   has  an  emissions
unit  with   an  annual  allowable   emissions  rate  of  200   tpy  based  on
full   capacity   year-round   operation   and    an   hourly   unit-specific
allowable  emission  rate.     The   source  is,   however,   out  of  compliance
with   the   allowable   hourly   emission   rate  by  a    factor   of   two.
Consequently,   if  the  unit   were  to   be   operated  year-round   at  full
capacity  it  would  emit  400   tpy.    However,   in  this  case,  although   the
unit  operated  at   full  capacity,  it   was  operated   on  the  average  75
percent  of   the  time  for  the  past   2 years.     Consequently,   for   the
past  2 years average  actual  emissions  were   300   tpy.    The unit   is   now
to  be  shutdown.    Assuming       the  reduction   is  otherwise  creditable,
the  reduction  from  the  shutdown  is   its  allowable   emissions  prorated
by its operating factor          (200 tpy x .75  = 150 tpy).
                                     A.42

-------
Case I: Normal Existing Source
  Potential to Emit
  Equals Existing
Allowable Emissions
   Actual
  Emissions
                                                            Creditable
                                                            Reduction
Revised Allowable
   Emissions
Case II: Existing Source Where Allowable Exceeds Potential
     Existing      Potential to Emit       Actual      Revised Allowable
    Allowable   at Maximum Capacity   Emissions       Emissions
    Emissions

Case III: Existing Source in Violation of Permit
                                                            Creditable
                                                            Reduction
     Existing
     Allowable
     Emissions
  (at 70% Capacity)
    Actual
  Emissions
(at 70% Capacity)
Revised Allowable
   Emissions
        Figure A-1.  Creditable Reductions in Actual Emissions
                                A.43

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.B.5.   SUGGESTED EMISSIONS NETTING PROCEDURE
      Through its review of many emissions netting  transactions,  EPA has  found
that,  either because of confusion or misunderstanding,  sources  have  used
various netting procedures, some of which result  in cases  where projects
should have been subjected to PSD but were not.   Some of the  most common
errors include:
            Not including contemporaneous emissions  increases  when  considering
            decreases;

            Improperly  using al1owable emissions  instead  of actual  emissions
            level  for the "old"  emissions level  for  existing units;

            Using  prospective (proposed)  unrelated  emissions decreases  to
            counterbalance proposed emission increases  without also  examining
            all previous contemporaneous  emissions  changes;

            Not considering a contemporaneous increase  creditable because  the
            increase previously  netted out of review by relying on  a past
            decrease which was,  but is no longer,  contemporaneous.   If
            contemporaneous and  otherwise creditable,  the increase  must be
            considered  in the netting  calculus.

            Not properly documenting all  contemporaneous  emissions  changes;
            and

            Not ensuring that emissions decreases  are  covered  by federally-
            enforceable restrictions,  which is a  requirement for
            creditabi1ity.
      For the purpose of minimizing confusion and improper  applicability

determinations,  the six-step procedure shown in Table A-5  and  described  below
is recommended in applying the emissions netting equation.   Already  assumed  in

this procedure is that the existing source has been  defined,  its  major source

status has been  confirmed and the air quality status in the area  is  attainment
for at least one criteria pollutant.
                                     A. 44

-------
                                                            DRAFT
                                                            OCTOBER 1990
              TABLE A-5.  Procedures  for  Determining
               the Net Emissions  Change  at a  Source
Determine the emissions  increases  (but  not any decreases)  from the
proposed project.  If increases  are significant,  proceed;  if  not,  the
sources is not subject to review.

Determine the beginning  and  ending dates  of the  contemporaneous period
as it relates to the proposed modification.

Determine which emissions units at the  source experienced  (or  will
experience,  including any proposed decreases resulting  from  the proposed
project) a creditable increase  or  decrease in emissions during the
contemporaneous period.

Determine which emissions changes  are creditable.

Determine, on a pollutant-by-pol1utant  basis, the  amount of  each
contemporaneous and  creditable  emissions  increase  and decrease.

Sum all contemporaneous  and  creditable  increases and decreases with the
increase from the proposed modification to determine if a  significant
net emissions increase will  occur.
                               A.45

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

Step 1.      Determine the emissions increases from the proposed project.

      First, only the emissions increases  expected to  result  from the  proposed
      project are examined.   This  includes emissions  increases  from  the  new
      and modified emissions  units and  any other  plant-wide emissions
      increases (e.g.,  debottlenecking  increases)  that will occur as a  result
      of the proposed modification.   [Proposed emissions  decreases occurring
      elsewhere at the source are  not considered  at this  point.   Emission
      decreases associated with a  proposed project (such  as a  boiler
      replacement) are contemporaneous  and may be  considered  along with  other
      contemporaneous emissions changes at the source. However,  they  are  not
      considered at this point in  the analysis.]

      A PSD review applies only to those regulated pollutants  with a
      significant emissions  increase from  the proposed modification.  If the
      proposed project will  not result  in  a significant emissions increase of
      any regulated pollutant, the project is exempt  from  PSD review  and  the
      PSD applicability process is completed.  However, if this  is not  the
      case, each regulated pollutant to be emitted in  a significant  amount is
      subject to a PSD review unless the source can demonstrate  (using  steps
      2-6) that the sum of all other source-wide  contemporaneous  and
      creditable emissions increases and decreases would  be less  than
      signifi cant.

Step 2      Determine the beginning and ending dates  of the contemporaneous
            period as it relates to the proposed modification.

      The period begins on the date 5 years (some  States  may  have a  different
      time period) before construction  commences  on the proposed  modification.
      It ends on the date the emissions increase  from  the proposed
      modification occurs.
Step 3      Determine which emissions units at the source have experienced an
            increase or decrease in emissions during the contemporaneous
            period.

      Usually,  creditable emissions increases are associated  with  a  physical
      change or change in the method of operation at a  source which  did  not
      require a PSD  permit.  For example,  creditable emissions increases may
      come from the  construction of a new  unit,  a fuel  switch or  an  increase
      in operation that (a) would have otherwise been subject to  PSD but
      instead netted out of review (per steps 1-6) or (b) resulted in a  less
      than significant emissions increase  (per step 1).

      Decreases are  creditable reductions  in actual  emissions from an
      emissions unit that are, or can be made, federally-enforceable. A
                                     A.46

-------
                                                                 DRAFT
                                                                 OCTOBER 1990

      physical  change  or  change  in the method of operation is also associated
      with  the  types of decreases that are  creditable.  Specifically, in the
      case  of  an  emissions  decrease,  once the decrease has been made
      federally-enforceable,  any proposed increase above the federally-
      enforceable level must  constitute  a physical change or change in the
      method  of operation at  the source  or  the  reduction is not considered
      creditable.   For example,  a source could  only receive an emissions
      decrease  for netting  purposes  from a  unit that  has been taken out of
      operation if,  due to  the imposition of federally-enforceable
      restrictions preventing the use of the unit, a  proposal to reactivate
      the  unit  would constitute  a physical  change or  change in the method of
      operation at the source.   If operating the unit was not considered a
      physical  or operational change, the unit  could  go back to its prior
      level  of  operation  at any  time, thereby producing only a "paper"
      reduction,  which is not creditable.

Step 4      Determine  which emissions changes are creditable.

      The  following basic rules  apply:

      1)  A increase or decrease  is creditable only if the relevant reviewing
      authority has not  relied upon  it in previously  issuing a PSD permit and
      the  permit  is in effect when the increase from  the proposed modification
      occurs.    As stated earlier, a reviewing  authority "relies" on  an
      increase  or decrease when, after taking the increase or decrease  into
      account,  it concludes in issuing a  PSD permit that a project would not
      cause or  contribute to  a violation  of a PSD increment or ambient
      standard.

      2)  For pollutants with  PSD increments (i.e., S02, particulate matter  and
      NOx), an  increase  or decrease  in actual emissions which occurs  before
      the  baseline date  in an area is creditable only if it would be
      considered in calculating  how  much  of an  increment remains available  for
      the  pollutant in question.  An example of this  situation is a 39  tpy  NOX
      emissions increase  resulting from  a  new heater  at a major source  in
      1987, prior to the  NOX  increment baseline date.  Because these  emissions
      do  not affect the  allowable  PSD increment, they need not be considered
      in  1990 when the source proposes another  unrelated project.  The  new
      emissions level  for the heater (up to 39  tpy) would be adjusted downward
      to  the old level (zero) in the accounting exercise.  Likewise,  decreases
      which occurred before the  baseline date was triggered cannot be credited
      after the baseline  date.   Such reductions are  included in the baseline
      concentration and  are not  considered  in calculating PSD increment
      consumpti on.

      3)  A decrease is creditable  only to  the extent  that it is "federally-
      enforceable" from  the moment that  the actual construction begins  on the
      proposed modification to  the source.  The decrease
                                     A.47

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

      must occur  before the proposed  emissions  increase  occurs.   An  increase
      occurs  when the emissions  unit  on  which  construction  occurred  becomes
      operational  and begins to  emit  a  particular  pollutant.   Any replacement
      unit that  requires shakedown  becomes  operational only after a  reasonable
      shakedown  period not to exceed  180 days.

      4)  A decrease is creditable  only  to the  extent  that  it  has  the same
      health  and  welfare significance as the  proposed increase from  the
      source.

      5)  A source cannot take credit  for a  decrease that it has had  to make,
      or  will  have to make, in order  to  bring  an emissions  unit into
      compli ance.

      6)  A source cannot take credit  for an emissions reduction from potential
      emissions  from an emissions  unit  which  was permitted  but never built or
      operated.

Step 5      Determine, on a pollutant-by-pollutant basis,  the amount of each
            contemporaneous and creditable emissions  increase and decrease.

      An  emissions increase is the  amount by  which the new  level  of  "actual
      emissions"  at the emissions  unit  exceeds  the old level.   The old level
      of  "actual  emissions" is that which prevailed just prior (i.e., prior 2
      year average) to the physical or  operational change  at  that unit which
      caused  the  increase.  The  new level  is  that  which  prevails  just after
      the change.   In most cases,  the old level  is calculated from the unit's
      actual  operating data from a  2  year period which directly preceded the
      physical  change.  The new  "actual   emissions" level  us  the  lower of the
      unit's  "potential" or "allowable"  emissions  after  the change.   In  other
      words,  a  contemporaneous emission  increase is calculated as the positive
      difference  between an emissions unit's  potential to  emit just  after a
      physical  or operation change  at that  unit (not  the unit's current  actual
      emissions)  and the unit's  actual  emissions just prior to the change.

      An  emissions decrease is the  amount by  which the old  level  of  actual
      emissions  or the old level  of allowable  emissions,  whichever is lower,
      exceeds  the new level of "actual"  emissions.  Like emissions increases,
      the old  level is calculated  from  the  unit's  actual  operating data  from a
      2 year  period which preceded  the  decrease, and  the new  emissions level
      will be  the lower of the unit's "potential"  or  "allowable"  emissions
      after  the  change.
                                    A. 48

-------
                                                                       DRAFT
                                                                       OCTOBER 1990

      Figure  A-2  shows  a  example  of how  old  and  new  actual  S02  emissions  levels
      are  established for  an existing emissions unit  at a  source.    The  applicant
      met  with   the  reviewing  agency   in   January   1988.   proposing  to   commence
      construction  on  a   new   emissions   unit  in  mid-1988.     The  contemporaneous
      time  frame  in  this  case  is   from  mid-1983  (using  EPA's  5-year  definition)
      to the  expected date of the new boiler start-up, about January 1990.

      In  mid-1984  an  existing  boiler switched  to   a   low  sulfur  fuel   oil.    The
      applicant  wishes  to  use  the  fuel   switch  as  a  netting  credit.     The  time
      period   for  establishing  the  old 502  emissions   level  for  the   fuel  switch  is
      the  2  year   period  preceding  the   change   [mid-1982   to   mid-1984,   when
      emissions  were  600  tpy  (mid-1982  through  mid-1983)  and  500   tpy  (mid-1982
      through mid-1983)].     The  new  502  emissions   level,  300   tpy,  is  established
      by   the   new   allowable   emissions   level   (which   will   be  made   federally-
      enforceable).    The  old  level  of  emissions  is   550 tpy  (the  average  of  600
      tpy  and 500  tpy).    Thus,  if  this  is  the  only  existing  502  emissions  unit
      at  the source,  a  decrease of  250  tpy  502  emissions  (550 tpy  minus  300 tpy)
      is   creditable   towards  the   emissions  proposed   for  the   new  boiler.    This
      example assumes  that   the  reduction  meets  all   other  applicable  criteria  for
      a creditable emissions decrease.

Step 6       Sum all  contemporaneous and creditable  increases and decreases
             with the increase from the proposed  modification to determine if a
             significant net emissions  increase will occur.

      The proposed  project is subject  to PSD review for each regulated
      pollutant for  which the sum  of  all  creditable emissions  increases  and
      decreases results  in a significant net emissions increase.

      If  available,  the  applicant  may  consider proposing additional
      prospective and  creditable emissions reductions sufficient  to  provide
      for a  less than  significant  net  emissions  increase at  the source  and
      thus avoid PSD review.  These reductions can  be achieved  through  either
      application of emissions controls or placing  restrictions on the
      operation of  existing emissions  units.  These additional  reductions
      would  be added to  the sum of all  other creditable increases and
      decreases.  As with all contemporaneous emissions reductions,  these
      additional decreases must be based on  actual  emissions changes,
      federally-enforceable prior  to  the commencement of construction  and
      occur  before  the  new unit begins operation.   They must also affect the
      allowable PSD  increment, where  applicable.
                                        A.49

-------
                                                                                          DRAFT

                                                                                          OCTOBER 1990
 _
CD
Q.
c
O
1
CD
c
g
'
E
LLJ
     800-
     600-
400-
                                                 offUelswteh
                                                 RepesenHwe "otf1 adual enissions tevet 550 Ipy

                                                 (aeage adel errissions fcr rrii82 to rridB4)
                                                                 cUcwebe enissions: 300 Ipy
     200-
            1980   1S81    1962   1983 ,
                                    ^-Dte!
                                                                   ~Ccnstnjcticnto

                                                                     CCnTTETCEOn

                                                                     pcpceed change


                                                                       Biisacns hcrease

                                                                       frcm pcpceed change
                                         19B5   1986   1967   1988   1989


                                         Qteofluelswteh


                                         Ctrterrpraneous f



                                    taeS^eaBpticrtolheoonshJcioncflheptopceed change
      I AtaAetteemscnsicmtiebcfcr
                                    I AtelemssionsfDmlTebaler
                                                              Aid aeage errisacns tan ซ-e boiertr

                                                              the tao yeas per to tieluel swth in rrid 1964
                                                                            Errissions
                                            A.50

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.B.6.   NETTING EXAMPLE
      An existing source has  informed  the  local  air  pollution  control  agency
that they are planning to construct a  new  emissions  unit "G".   The existing
source is a major source and  the construction of unit G will  constitute a
modification to the source.   Unit G will  be capable  of emitting 80 tons per
year (tpy) of the pollutant  after installation of controls.   The PSD
significant emissions level  for the pollutant in question is  40 tpy.  Existing
emissions units "A" and "B"  at the source  are presently permitted at 150 tpy
each.  The applicant has proposed to limit the operation of  units A and B,  in
order to net out of PSD review, to 7056 hours per year (42 weeks) by accepting
federally-enforceable conditions.  The applicant has calculated that there
will be an emissions reduction of -29.2 tpy [150 - 150x(7056/8760)] per unit
for a total reduction of 58.4 tpy.  Thus,  the net emissions  increase,  as
calculated by the applicant,  will be +21.6 tpy (80-58.36).  The applicant
proposes to net out of PSD review citing the +21.6 tpy increase as less than
the applicable 40 tpy PSD significance level for the pollutant.

      The reviewing agency informed the source that  1) the emissions
reductions being claimed from units A and B must be  based on the prior actual
emissions, not their allowable emissions and (2) because the increase from the
modification will be greater than significant, al1 contemporaneous changes
must be accounted for (not just proposed decreases)  in order to determine the
net emission change at the source.

      To verify if, indeed,  the source will be able  to net out of PSD review,
the reviewing agency requested information  on the other emissions points at
the source, including their actual monthly  emissions.  For illustrative
purposes, the actual annual  emissions of the pollutant in question from the
existing emissions points (in this example  all emissions points are associated
with an emissions unit) are given as follows:
                                     A.51

-------
Actual Emissions
Year
1983
1984
1985
1986
1987
1988
1989
Unit A
70
75
80
110
115
105
90
Unit B
130
130
150
90
85
75
90
Unit C
60
75
65
0
0
0
0
(tDV)
Unit D
85
75
80
0
0
0
0
DRAFT
OCTOBER 1990
Unit E
50
60
65
70
75
65
60
Unit F
0
0
0
0
75
70
65
      The applicant's  response indicates  that  units  A and  B  will  not  be
physically modified.   However, the information does  show that the modification
will  result in the removal  of a bottleneck at  the plant and  that  the  proposed
modification will  result in an increase in the operation of  these units.
      The PSD baseline for  the pollutant  was triggered in  1978.   The  history
of the emissions units at the source is as follows:

Emissions
 Unit(s)                         History
A and B           Built in  1972 and still operational
C and D           Built in  1972 and retired from operation 01/86
E           Built  in  1972 and still operational
F           PSD permitted unit; construction  commenced 01/86 and  the  unit
            became operational on 01/87
G           New modification; construction scheduled to commence  01/90    and
            the unit  is expected to be operational  on 01/92

      The contemporaneous period extends  from  01/85  (5 years prior to 01/90,
the projected construction  date of the modification) until 01/92  (the date the
emissions increase from the modification).  The net  emissions change  at  the
source can be formulated in terms of the  sum  of the  unit-by-unit  emissions
changes which are  creditable and contemporaneous with the planned
                                     A.52

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

modification.   Emission changes  that are not  associated  with  physical/

operational  changes are not considered.


      In assessing the creditable  contemporaneous  changes  the permit  agency

considered the following (all  numbers are in  tpy):
            Potential  to emit is used for a new unit.   The new unit will
            receive a  federally-enforceable permit  restricting allowable
            emissions  to 80 tpy, which then becomes its potential  to emit.
            Therefore,  the new unit represents an increase of  +80.

            Even though units A and B will  not be modified,  their  emissions
            are expected to increase as a result of the modification and  the
            anticipated increase must be included as part of the increase from
            the proposed modification.  The emissions  change for these units
            is based on their allowable emissions after the change minus  their
            current actual emissions.  Current actual  emissions are based on
            the average emissions over the last 2 years.   [Note that only the
            operations of exiting units A and B are expected to be affected by
            the modification.]  The emissions changes  at A and B are
            calculated as follows:
      Unit A's change = +23.3

      {new allowable [150x(7056/8760)]  -   old actual  [(105+90)72]}

      Unit B's change = +38.3

      {new allowable [150x(7056/8760)]  -   old actual  [(75+90)72]}

      The federally-enforceable restriction on the hours of operation for
      units A and B act to reduce the amount of the emissions increase at the
      units due to the modification.   However, contrary  to the applicant's
      analysis, the restrictions did  not  restrict the units'  emissions
      sufficiently to prevent an actual  emissions increase.

      ••     The emissions increase from unit F was permitted under PSD.
            Therefore, having been "relied upon" in the issuance of a PSD
            permit which is still in effect, the permitted emissions increase
            is not creditable and cannot be used in the netting equation.

      >     The operation of unit E is not projected to be affected by the
            proposed modification.  It has not undergone any physical or
            operational change during the contemporaneous period which would
            otherwise trigger a creditable emissions change at the unit.
            Consequently, unit E's emissions are not considered for netting
            purposes by the reviewing agency.

                                     A.53

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

      ••      The retirement (a physi cal/operational  change)  of units C and  D
            occurred within the contemporaneous  period and  may provide
            creditable decreases for the applicant.   However, if the
            retirement of the units  was relied upon  in the  issuance of the PSD
            permit for unit F (e.g,  if  the emissions of units C or D were
            modeled at zero in the PSD  application)  then the reductions would
            not be creditable.  If they were not modeled as retired (zero
            emissions),  then the reduction would be  available as an emissions
            reduction.  The reduction credit would  be based on the last 2
            years of actual data prior  to retirement.  As with all  reductions,
            to be creditable the retirement of the  units must be made
            federally-enforceable prior to construction of  the modification to
            and start-up of the source.  Upon checking the  PSD permit
            application  for unit F,  the reviewing agency determined that units
            C and D were not considered  retired and their  emissions were
            included in  the ambient  impact analysis  for unit F.  Consequently,
            the emissions reduction  from the retirement of  unit C and D
            (should the  reductions be made federally-enforceable) was
            determined as followed:

      Unit C's change =  -70

      {its new allowable [0] - its old  actual  [(75+65)72]}

      Unit D's change =  -77.5

      {its new allowable [0] - its old  actual  [(75+80)72]}

      >•      The netting  transaction  would not cause  or contribute to a
            violation of the applicable PSD increment or ambient standards.

      The applicant,  however, is only willing to accept federally-enforceable
conditions on the retirement of unit C.  Unit D  is  to be kept as a  standby
unit and the applicant is unwilling  to  have its  potential  operation limited.
Consequently, the reduction in emissions at unit D  is not creditable.


      The net contemporaneous emissions change at the source is calculated by
the reviewing agency as  follows:
                                     A. 54

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Emissions Change (tpy:
      +80.0 increase from unit  G.
      +23.3 increase at A from  modification  at  source.
      +38.8 increase at B from  modification  at  source.
      -70.0 creditable decrease from retirement of  unit  C
      +72.1 total  contemporaneous  net emissions increase at  the  source.
The +72.1 tpy net increase is greater  than  the  +40  tpy  PSD significance  level;
consequently the proposed modification is subject  to  PSD review for  that
pollutant.

      If the applicant is willing  to  agree  to federally-enforceable  conditions
limiting the allowable emissions from  unit  D (but  not necessarily requiring
the unit's permanent retirement),  a sufficient  reduction may be available to
net unit G out of a PSD review.   For  example, the  applicant could agree  to
accept federally-enforceable conditions limiting the  operation of unit D to
672 hours a year (4 weeks), which  (for illustrative purposes) equates to an
allowable emissions of 15 tpy.  The creditable  reduction from the unit D would
then amount to -62.5 tpy (-77.5  +15).   This brings  the  total contemporaneous
net emissions change for the proposed  modification  to +9.6 tpy (+72.1 -  62.5).
The construction of Unit G would then  not be considered a major modification
subject to PSD review.  It is important to  note, however, that if unit D is
permanently taken out of service after January  1991 and had not operated in
the interim, the source would not be  allowed an emissions reduction  credit
because there would have been no actual emissions  decrease during the
contemporaneous period.  In addition,  if the source later requests removal of
restrictions on units which allowed unit G to net  out of review, unit G then
becomes subject to PSD review as though construction  had not yet commenced.
                                     A.55

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.  GENERAL EXEMPTIONS

IV.A. SOURCES AND MODIFICATIONS AFTER AUGUST 7,1980

      Certain sources may be exempted from PSD review or certain PSD
requirements.  Nonprofit health or educational sources that would otherwise be
subject to PSD review can be exempted if requested by the Governor of the
State in which they are located.   A portable,  major stationary source that has
previously received a PSD permit and is to be  relocated is exempt from a
second PSD review if (1) emissions at the new  location will not exceed
previously allowed emission rates, (2) the emissions at the new location  are
temporary, and (3) the source will not, because of its new location, adversely
affect a Class I  area or contribute to any known increment or national ambient
air quality standard (NAAQS) violation.  However,  the source must provide
reasonable advance notice to the reviewing authority.

IV.B.  SOURCES CONSTRUCTED PRIOR TO AUGUST 7,1980

      The 1980 PSD regulations do not apply to certain sources affected by
previous PSD regulations.  For example, sources for which construction began
before August 7,  1977 are exempt from the 1980 PSD regulations and are instead
reviewed for applicability under the PSD regulations as they existed before
August 7, 1977.   Several exemptions also exist for sources for which
construction began after August 7, 1977, but before the August 7, 1980
promulgation of  the PSD regulations (45 FR 52676).  These exemptions and  the
criteria associated nonapplicabi1ity are detailed  in paragraph (i) of
40 CFR 52.21.
                                     A.56

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

                                  CHAPTER B

                      BEST AVAILABLE CONTROL TECHNOLOGY


I.  INTRODUCTION


Any major stationary source or major modification  subject  to  PSD  must  conduct

an analysis to ensure the application of  best  available  control

technology (BACT).   The  requirement  to conduct a  BACT  analysis  and

determination is set forth in section 165(a)(4)  of the Clean  Air  Act  (Act),  in

federal  regulations at 40 CFR 52.2KJ),  in  regulations setting  forth  the

requirements for State implementation plan  approval  of a State  PSD program at

40 CFR 51.166(j),  and in the SIP's of the various  States at 40  CFR Part  52,

Subpart A - Subpart FFF.  The BACT requirement is  defined  as:
      "an emissions limitation (including a  visible  emission  standard)  based
      on the maximum degree of reduction  for each  pollutant  subject  to
      regulation under the Clean Air Act  which  would be  emitted  from any
      proposed major stationary source  or major modification  which the
      Administrator, on a case-by-case  basis,  taking into  account  energy,
      environmental, and economic impacts and  other  costs,  determines is
      achievable for such source or modification through application of
      production processes or available methods, systems,  and techniques,
      including fuel cleaning or treatment or  innovative fuel  combustion
      techniques for control  of such pollutant. In  no event  shall application
      of best available control technology result  in emissions of  any
      pollutant which would exceed the  emissions allowed by  any  applicable
      standard under 40 CFR Parts 60 and  61.  If the Administrator determines
      that technological or economic limitations on  the  application  of
      measurement methodology to a particular  emissions  unit  would make the
      imposition of an emissions standard infeasible,  a  design,  equipment,
      work practice, operational standard, or  combination  thereof, may  be
      prescribed instead to satisfy the requirement  for  the  application of
      best available control  technology.   Such  standard  shall, to  the degree
      possible, set forth the emissions reduction  achievable  by  implementation
      of such design, equipment, work practice  or  operation,  and shall  provide
      for compliance by means which achieve equivalent results."

      During each BACT  analysis, which  is done on  a  case-by-case basis, the
reviewing authority evaluates the energy, environmental, economic and other
                                       .1

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
costs associated with each alternative technology,  and the benefit of reduced
emissions that the technology would bring.   The reviewing authority then
specifies an emissions limitation for the source that reflects the maximum
degree of reduction achievable for each pollutant regulated under the Act.  In
no event can a technology be recommended which would not meet any applicable
standard of performance under 40 CFR Parts  60 (New  Source Performance
Standards) and 61 (National  Emission Standards for  Hazardous Air Pollutants).

      In addition, if the reviewing authority determines that there is no
economically reasonable or technologically  feasible way to accurately measure
the emissions, and hence to  impose an enforceable emissions standard, it may
require the source to use design, alternative equipment, work practices or
operational standards to reduce emissions of the pollutant to the maximum
extent.

      On December 1,  1987, the EPA Assistant Administrator for Air and
Radiation issued a memorandum that implemented certain program initiatives
designed to improve the effectiveness of the NSR programs within the confines
of existing regulations and  state implementation plans.  Among these was the
"top-down" method for determining best available control technology (BACT).

      In brief, the top-down process provides that  all available control
technologies be ranked in descending order  of control  effectiveness.  The  PSD
applicant first examines the most stringent — or "top"--alternative.  That
alternative is established as BACT unless the applicant demonstrates, and  the
permitting authority  in its  informed judgment agrees,  that technical
considerations, or energy, environmental, or economic impacts justify a
conclusion that the most stringent technology is not "achievable" in that
case.  If the most stringent technology is  eliminated in this fashion, then
the next most stringent alternative is considered,  and so on.
                                     B.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990


The purpose of this chapter is to provide a detailed description of the

top-down method in order to assist permitting authorities and PSD applicants

in conducting BACT analyses.
                                      B.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.  BACT APPLICABILITY
      The BACT requirement applies to each individual  new or modified affected
emissions unit and pollutant emitting activity at which a net emissions
increase would occur.   Individual  BACT determinations  are performed for each
pollutant subject to a PSD review emitted from the same emission unit.
Consequently,  the BACT determination must separately address, for each
regulated pollutant with a significant emissions increase at the source,  air
pollution controls for each emissions unit or pollutant emitting activity
subject to review.
                                     B.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.   A STEP BY STEP SUMMARY  OF THE  TOP-DOWN  PROCESS
      Table B-l  shows  the five  basic  steps  of  the  top-down  procedure,
including some of the  key elements  associated  with each  of  the  individual
steps.   A brief  description  of  each step  follows.

III.A.   STEP 1--IDENTIFY ALL CONTROL  TECHNOLOGIES
      The first  step in a "top-down"  analysis  is  to identify,  for  the
emissions unit in question (the term  "emissions  unit"  should  be read to  mean
emissions unit,  process or activity),  all  "available"  control  options.
Available control options are those air pollution  control  technologies  or
techniques with  a practical  potential  for application  to the  emissions  unit
and the regulated pollutant  under evaluation.   Air pollution  control
technologies and techniques  include the application of production  process  or
available methods, systems,  and techniques,  including  fuel  cleaning  or
treatment or innovative fuel combustion techniques for control  of  the  affected
pollutant.  This includes technologies employed  outside of  the United  States.
As discussed later, in some  circumstances inherently lower-polluting  processes
are appropriate for consideration as  available control alternatives.   The
control alternatives should  include not only existing  controls for the  source
category in question,  but also (through technology transfer)  controls  applied
to similar source categories and gas  streams,  and innovative  control
technologies.  Technologies  required  under lowest achievable  emission  rate
(LAER) determinations are available for BACT purposes  and must also be
included as control alternatives and usually represent the top alternative.

       In the course of the BACT analysis, one or more  of the  options  may be
eliminated from consideration because they are demonstrated to be  technically
infeasible or have unacceptable energy, economic,  and  environmental  impacts on
a case-by-case (or site-specific) basis.   However, at  the outset,  applicants
                                     B.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
            TABLE B-l.  - KEY STEPS IN THE "TOP-DOWN" BACT PROCESS

STEP 1:  IDENTIFY ALL CONTROL TECHNOLOGIES.
                  LIST Is comprehensive  (LAER included).

STEP 2:  ELIMINATE TECHNICALLY INFEASIBLE OPTIONS.
            A demonstration of  technical  infeasibi1ity  should be clearly
            documented and  should show,  based on  physical,  chemical,  and
            engineering principles,  that technical  difficulties would preclude
            the successful  use  of the control  option on the  emissions unit
            under review.

STEP 3:  RANK REMAINING CONTROL  TECHNOLOGIES  BY CONTROL  EFFECTIVENESS.
      Should include:

            control  effectiveness (percent  pollutant removed);
            expected emission rate (tons per year);
            expected emission reduction  (tons per  year);
            energy impacts  (BTU,  kWh);
            environmental impacts (other media and the  emissions of toxic  and
            hazardous  air emissions); and
            economic impacts (total  cost effectiveness, incremental  cost
            effectiveness).

STEP 4:  EVALUATE MOST  EFFECTIVE CONTROLS AND DOCUMENT RESULTS.
            Case-by-case consideration  of energy,  environmental, and  economic
            impacts.
            If top option is not  selected as BACT,  evaluate  next most
            effective  control option.

STEP 5:  SELECT BACT
           Most effective option  not  rejected is  BACT.
                                     B.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
should initially identify all  control  options  with  potential  application  to
the emissions unit under review.

III.B.  STEP 2--ELIMINATE TECHNICALLY  INFEASIBLE OPTIONS

      In the second step, the technical  feasibility of the control  options
identified in step one is evaluated with respect to the source-specific (or
emissions unit-specific) factors.   A demonstration  of technical  infeasibi1ity
should be clearly documented and  should  show,  based on physical,  chemical, and
engineering principles, that technical  difficulties would preclude the
successful use of the control  option on  the emissions unit under  review.
Technically infeasible control  options are then eliminated from further
consideration in the BACT analysis.

      For example, in cases where the  level of control in a permit is not
expected to be achieved in practice (e.g., a source has received  a permit but
the project was cancelled, or every operating  source at that permitted level
has been physically unable to achieve  compliance with the limit), and
supporting documentation showing  why such limits are not technically feasible
is provided, the level of control  (but not necessarily the technology) may be
eliminated from further consideration.  However, a  permit requiring the
application of a certain technology or emission limit to be achieved for such
technology usually is sufficient  justification to assume the technical
feasibility of that technology or emission limit.

III.C.  STEP 3--RANK REMAINING CONTROL TECHNOLOGIES BY CONTROL EFFECTIVENESS

      In step 3, all remaining control alternatives not eliminated in step 2
are ranked and then listed in order of over all control effectiveness for the
pollutant under review, with the most effective control alternative at the
top.  A list should be prepared for each pollutant and for each emissions unit
(or grouping of similar units) subject to a BACT analysis.  The list should
present the array of control technology alternatives and should include the
following types of information:

                                      B.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      •  control  efficiencies (percent pollutant removed);
      •  expected emission rate (tons per year,  pounds per  hour);
      •  expected emissions reduction (tons per  year);
      •  economic impacts (cost effectiveness);
      •  environmental  impacts (includes any significant or unusual  other
         media impacts  (e.g., water or solid waste),  and,  at a  minimum,  the
         impact of each control  alternative on emissions of toxic  or hazardous
         ai r contami nants);
      •  energy impacts.

      However, an applicant proposing the top control  alternative  need not
provide cost and other  detailed information in regard to other control
options.  In such cases the applicant should document that  the control option
chosen is, indeed, the  top, and review for collateral  environmental  impacts.

III.D.  STEP 4--EVALUATE MOST EFFECTIVE CONTROLS AND  DOCUMENT RESULTS

      After the identification of available and  technically feasible control
technology options,  the energy,  environmental, and economic impacts  are
considered to arrive at the final level of control.   At this point the
analysis presents the associated impacts of the  control option in  the listing.
For each option the  applicant is responsible for presenting an objective
evaluation of each impact.  Both beneficial and  adverse impacts should be
discussed and, where possible, quantified.  In general, the BACT analysis
should focus on the  direct impact of the control alternative.

      If the applicant  accepts the top alternative in the  listing  as BACT, the
applicant proceeds to consider whether impacts of unregulated air  pollutants
or impacts in other  media would justify selection of  an alternative  control
option.   If there are no outstanding issues regarding collateral  environmental
impacts, the analysis is ended and the results proposed as  BACT.   In the  event
that the top candidate  is shown to be inappropriate,  due to energy,
environmental, or economic impacts, the rationale for this  finding should be
                                     B.8

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
documented for the public record.   Then the next most stringent alternative in
the listing becomes the new control  candidate and is similarly evaluated.
This process continues until  the technology under consideration cannot be
eliminated by any source-specific  environmental, energy,  or economic impacts
which demonstrate that alternative to be inappropriate as BACT.

III.E.  STEP 5--SELECT BACT

      The most effective control option not eliminated in step 4 is proposed
as BACT for the pollutant and emission unit under review.
                                      B.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.   TOP-DOWN ANALYSIS DETAILED PROCEDURE

IV.A.  IDENTIFY ALTERNATIVE EMISSION CONTROL TECHNIQUES (STEP 1)

      The objective in step 1 is to identify all  control  options with
potential application to the source and pollutant under evaluation.   Later,
one or more of these options may be eliminated from consideration because they
are determined to be technically infeasible or to have unacceptable  energy,
environmental or economic impacts.

      Each new or modified emission unit (or logical  grouping of new or
modified emission units) subject to PSD is required to undergo BACT  review.
BACT decisions should be made on the information  presented in the BACT
analysis, including the degree to which effective control  alternatives were
identified and evaluated.  Potentially applicable control  alternatives can be
categorized in three ways.
      •  Inherently Lower-Emitting Processes/Practices,  including the use of
         materials and production processes and work practices that prevent
         emissions and result in lower "production-specific" emissions;  and
      •  Add-on Controls, such as scrubbers,  fabric filters, thermal  oxidizers
         and other devices that control  and reduce emissions after they  are
         produced.
      •  Combinations of Inherently Lower Emitting Processes and Add-on
         Controls. For example, the application of combustion and
         post-combustion controls to reduce NOx emissions at a gas-fired
         turbine.
      The top-down BACT analysis should consider potentially applicable
control  techniques from all  three categories.   Lower-polluting processes
should be considered based on demonstrations made on the basis of
manufacturing identical or similar products from identical  or similar raw
materials or; fuels.   Add-on controls,  on the other hand, should be considered
based on the physical and chemical characteristics of the pollutant-bearing
emission stream.   Thus, candidate add-on controls may have  been applied to a
broad range of emission unit types that are similar, insofar as emissions
                                     B.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
characteristics,  to the emissions unit undergoing BACT review.
IV.A.I.   DEMONSTRATED AND TRANSFERABLE TECHNOLOGIES
      Applicants are expected to identify all  demonstrated and potentially
applicable control  technology alternatives.   Information sources to consider
include:
      •  EPA's BACT/LAER Clearinghouse and Control  Technology Center;
      •  Best Available Control  Technology Guideline -  South Coast Air Quality
         Management District;
      •  control technology vendors;
      •  Federal/State/Local  new source review permits  and associated
         inspection/performance test  reports;
      •  environmental consultants;
      •  technical  journals,  reports  and newsletters (e.g., JAPCA and  the
         Mclvaine reports), air pollution control  seminars; and
      •  EPA's New Source Review (NSR) bulletin board.
      The applicant should make a good faith effort to compile appropriate
information from available information sources, including any sources
specified as necessary by the permit agency.  The permit agency should review
the background search and resulting list of control alternatives presented by
the applicant to check that it is complete and comprehensive.

      In identifying control technologies, the applicant needs to survey the
range of potentially available control options.   Opportunities for technology
transfer lie where a control technology has been applied at source categories
other than the source under consideration.  Such opportunities should be
identified.  Also, technologies in application outside the United States to
the extent that the technologies have been successfully demonstrated in
practice on full scale operations.   Technologies which have not yet been
applied to (or permitted for) full scale operations need not be considered
available; an applicant should be able to purchase or construct a process or
control device that has already been demonstrated in practice.
                                     B.ll

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      To satisfy the legislative requirements of BACT,  EPA believes that the
applicant must focus on technologies with a demonstrated potential  to achieve
the highest levels of control.   For example,  control  options incapable of
meeting an applicable New Source Performance  Standard (NSPS) or State
Implementation Plan (SIP) limit would not meet the definition of BACT under
any circumstances.  The applicant does not need to consider them in the BACT
analysis.

      The fact that a NSPS for  a source category does not require a certain
level  of control or particular  control technology does  not preclude its
consideration in the top-down BACT analysis.   For example, post combustion NOx
controls are not required under the Subpart GG of the NSPS for Stationary Gas
Turbines.  However, such controls must still  be considered available
technologies for the BACT selection process and be considered in the BACT
analysis.  An NSPS simply defines the minimal level  of  control to be
considered in the BACT analysis.  The fact that a more  stringent technology
was not selected for a NSPS (or that a pollutant is  not regulated by an NSPS)
does not exclude that control alternative or  technology as a BACT candidate.
When developing a list of possible BACT alternatives, the only reason for
comparing control options to an NSPS is to determine whether the control
option would result in an emissions level less stringent than the NSPS.  If
so, the option is unacceptable.

IV.A.2.  INNOVATIVE TECHNOLOGIES

      Although not required in  step 1, the applicant may also evaluate and
propose innovative technologies as BACT.   To  be considered innovative, a
control technique must meet the provisions of 40 CFR 52.21(b)(19) or, where
appropriate, the applicable SIP definition.  In essence, if a developing
                                     B.12

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
technology has the potential  to achieve a more stringent  emissions level  than
otherwise would constitute BACT or the same level  at  a  lower  cost, it may be
proposed as an innovative control  technology.   Innovative technologies are
distinguished from technology transfer BACT candidates  in that  an  innovative
technology is still  under development and has  not  been  demonstrated in a
commercial application on identical  or similar emission units.   In certain
instances, the distinction between innovative  and  transferable  technology may
not be straightforward.   In these cases,  it is recommended that the permit
agency consult with EPA prior to proceeding with the  issuance of an innovative
control  technology waiver.
      In the past only a limited number of innovative control  technology
waivers for a specific control  technology have been approved.   As  a practical
matter,  if a waiver has been granted to a similar  source  for  the same
technology, granting of additional waivers to  similar sources is highly
unlikely since the subsequent applicants are no longer  "innovative".

IV.A.3.   CONSIDERATION OF INHERENTLY LOWER POLLUTING  PROCESSES/PRACTICES

      Historically, EPA has not considered the BACT requirement as a  means to
redefine the design of the source when considering available  control
alternatives.  For example, applicants proposing to construct a coal-fired
electric generator, have not been required by  EPA as  part of  a  BACT analysis
to consider building a natural  gas-fired electric turbine although the turbine
may be inherently less polluting per unit product (in this case electricity).
However, this is an aspect of the PSD permitting process  in which states  have
the discretion to engage in a broader analysis if they so desire.   Thus,
a gas turbine normally would not be included in the list  of control
alternatives for a coal-fired boiler.  However, there may be  instances where,
in the permit authority's judgment, the consideration of  alternative
production processes is warranted and appropriate for consideration in the
BACT analysis.  A production process is defined in terms  of its physical  and
chemical unit operations used to produce the desired  product  from a specified
                                     B.13

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
set of raw materials.   In such cases,  the permit agency may require the
applicant to include the inherently lower-polluting process in the list of
BACT candidates.

      In many cases, a given production process or emissions unit can be made
to be inherently  less  polluting (e.g;  the use of water-based versus solvent
based paints in a coating operation or a coal-fired boiler designed to have a
low emission factor for NOx).   In such cases the ability of design
considerations to make the process inherently less polluting must be
considered as a control alternative for the source.   Inherently lower-
polluting processes/practice are usually more environmentally effective
because of lower  amounts of solid wastes and waste water than are generated
with add-on controls.   These factors are considered in the cost,  energy and
environmental impacts  analyses in step 4 to determine the appropriateness  of
the additional add-on  option.

      Combinations of  inherently lower-polluting processes/practices (or a
process made to be inherently  less polluting) and add-on controls are likely
to yield more effective means  of emissions control than either approach alone.
Therefore, the option  to utilize a inherently lower-polluting process does
not, in and of itself, mean that no additional  add-on controls need be
included in the BACT analysis.  These  combinations should be identified in
step 1 of the top down process for evaluation in subsequent steps.

IV.A.4.  EXAMPLE

      The process of identifying control technology alternatives  (step 1 in
the top-down BACT process) is  illustrated in the following hypothetical
example.
                                     B.14

-------
                                                                      DRAFT
                                                                      OCTOBER 1990
Description  of Source
      A  PSD  applicant proposes  to install  automated surface  coating process

equipment  consisting of a  dip-tank priming  stage  followed  by  a  two-step spray

application  and bake-on enamel  finish coat.   The  product is  a  specialized

electronics  component (resistor)  with strict  resistance property

specifications that restrict  the  types of  coatings that may  be  employed.


List of  Control Options


      The  source is not covered by an applicable  NSPS.  A  review of the

BACT/LAER  Clearinghouse and  other appropriate references indicates the

following  control  options  may be  applicable:

      Option #1:  water-based primer and finish coat;

      [The water-based coatings have never been used in applications similar
      to this.]

      Option #2: "low-VOC  solvent/high solids  coating for primer and finish
      coat;

      [The high  solids/low VOC solvent coatings have recently been applied
      with success with similar products  (e.g., other types of electrical
      components).]

      Option #3:  electrostatic spray application to enhance coating transfer
      efficiency;  and

      [Electrostatically enhanced coating application has been applied
      elsewhere  on a clearly similar operation.]

      Option #4:  emissions  capture with add-on control  via  incineration  or
      carbon adsorber equipment.

      [The VOC capture and control  option (incineration or carbon adsorber)
      has been used in many cases involving the coating of different  products
      and the emission stream characteristics are similar to  the proposed
      resistor coating process and  is identified  as  an option available
      through technology transfer.]
                                       B.15

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Since the low-solvent coating,  electrostatically  enhanced  application,
and ventilation with add-on control  options  may  reasonably  be  considered  for
use in combination to achieve greater emissions  reduction  efficiency,  a total
of eight control  options are eligible for further  consideration.   The  options
include each of the four options listed above  and  the following  four
combinations of techniques:
      Option #5:   low-solvent coating with electrostatic applications  without
      ventilation and add-on controls;
      Option #6:   low-solvent coating without  electrostatic applications  with
      ventilation and add-on controls;
      Option #7:   electrostatic application  with add-on control;  and
      Option #8:   a combination of all  three technologies.
      A "no control" option also was  identified  but  eliminated because the
applicant's State regulations require at least a 75  percent reduction  in  VOC
emissions for a source of this size.   Because  "no  control"  would  not meet the
State regulations it could not be BACT and,  therefore,  was  not listed  for
consideration in  the BACT analysis.

Summary of Key Points

      The example illustrates several key guidelines for identifying control
options.  These include:

      •  All available control techniques must be  considered in  the BACT
         analysi s.
      •  Technology transfer must be  considered  in identifying control
         options.  The fact that a control option  has never been  applied  to
         process  emission units similar or identical to that  proposed does
         not mean it can be ignored in the BACT  analysis if the  potential for
         its application exists.
      •  Combinations of techniques should be  considered to the  extent they
         result in more effective means of achieving stringent emissions
         levels represented by the "top" alternative,  particularly if the
         "top" alternative is eliminated.
                                     B.16

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.B.   TECHNICAL FEASIBILITY ANALYSIS  (STEP  2)

      In step 2, the technical  feasibility  of  the  control  options  identified
in step 1 is evaluated.   This step should  be straightforward  for  control
technologies that are demonstrated--if the  control  technology has  been
installed and operated successfully  on the  type of source  under  review,  it  is
demonstrated and it is technically feasible.  For  control  technologies  that
are not demonstrated in  the sense indicated  above,  the  analysis  is somewhat
more involved.

      Two key concepts are important in determining whether an undemonstrated
technology is feasible:  "availability" and  "applicability."  As  explained in
more detail  below, a technology is considered  "available"  if  it  can be
obtained by the applicant through commercial channels  or is otherwise
available within the common sense meaning  of the term.   An available
technology is "applicable" if it can reasonably be installed  and  operated on
the source type under consideration.  A technology that is available and
applicable is technically feasible.

      Availability in this context is  further  explained using the following
process commonly used for bringing a control technology concept  to reality as
a commercial product:

      •  concept stage;
      •  research and patenting;
      •  bench scale or laboratory testing;
      •  pilot scale testing;
      •  licensing and commercial demonstration; and
      •  commercial sales.
                                     B.17

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      A control  technique is considered available,  within the context
presented above, if it has reached the licensing and commercial  sales stage of
development.   A source would not be required to experience extended time
delays or resource penalties to allow research to be conducted on a new
technique.   Neither is it expected that an applicant would be required to
experience  extended trials to learn how to apply a  technology on a totally
new and dissimilar source type.  Consequently, technologies in the pilot  scale
testing stages of development would not be considered available  for BACT
review.  An exception would be if the technology were proposed and permitted
under the qualifications of an innovative control  device consistent with  the
provisions  of 40 CFR 52.21(v) or, where appropriate, the applicable SIP.

      Commercial availability by itself,  however,  is not necessarily
sufficient  basis for concluding a technology to be  applicable and therefore
technically feasible.  Technical feasibility,  as determined in Step 2, also
means a control  option may reasonably be  deployed on or "applicable" to the
source type under consideration.

      Technical  judgment on the part of the applicant and the review authority
is to be exercised in determining whether a control  alternative  is applicable
to the source type under consideration.  In general, a commercially available
control option will be presumed applicable if it has been or is  soon to be
deployed (e.g.,  is specified in a permit) on the same or a similar source
type.  Absent a showing of this type, technical feasibility would be based on
examination of the physical and chemical  characteristics of the  pollutant-
bearing gas stream and comparison to the  gas stream characteristics of the
source types  to which the technology had  been applied previously.  Deployment
of the control technology on an existing  source with similar gas stream
characteristics is generally sufficient basis for concluding technical
feasibility barring a demonstration to the contrary.
                                     B.18

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      For process-type control  alternatives  the decision  of whether  or not  it
is applicable to the source in  question  would  have  to  be  based on  an
assessment of the similarities  and differences between the proposed  source  and
other sources to which the process technique had been  applied previously.
Absent an explanation of unusual  circumstances by the  applicant showing why a
particular process cannot be used on the proposed source  the review  authority
may presume it is technically feasible.

      In practice, decisions about technical feasibility  are within  the
purview of the review authority.   Further,  a presumption  of technical
feasibility may be made by the  review authority based  solely on technology
transfer.  For example, in the  case of add-on  controls, decisions  of this  type
would be made by comparing the  physical  and  chemical  characteristics of the
exhaust gas stream from the unit  under review  to those of the unit from which
the technology is to be transferred.  Unless significant  differences between
source types exist that are pertinent to the successful operation  of the
control device, the control option is presumed to be technically feasible
unless the source can present information to the contrary.

      Within the context of the top-down procedure, an applicant addresses  the
issue of technical feasibility  in asserting  that a  control option  identified
in Step 1 is technically infeasible.  In this  instance, the applicant should
make a factual demonstration of infeasibi1ity  based on commercial
unavailability and/or unusual circumstances  which exist with application of
the control to the applicant's  emission  units.  Generally, such a
demonstration would involve an  evaluation of the pollutant-bearing gas stream
characteristics and the capabilities of  the  technology.  Also a showing of
unresolvable technical difficulty with applying the control would  constitute a
showing of technical infeasibility (e.g., size of the unit, location of the
proposed site, and operating problems related to specific circumstances of the
source).  Where the resolution of technical  difficulties  is a matter of cost,
the applicant should consider the technology as technically feasible.  The
economic feasibility of a  control alternative is reviewed in the economic
impacts portion of the BACT selection process.

                                     B.19

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      A demonstration of technical  infeasibi1ity is based on a  technical
assessment considering physical, chemical  and engineering principles and/or
empirical  data showing that the technology  would not work on the emissions
unit under review, or that unresolvable technical  difficulties  would preclude
the successful deployment of the technique.   Physical  modifications needed to
resolve technical  obstacles do not in and  of  themselves provide a
justification for  eliminating the control  technique on the basis of technical
infeasibi1ity.  However, the cost of such  modifications can be  considered  in
estimating cost and economic impacts which,  in  turn, may form the basis for
eliminating  a control technology (see later discussion at V.D.2).

      Vendor guarantees may provide an indication  of commercial  availability
and the technical  feasibility of a control  technique and could  contribute  to  a
determination of technical feasibility or  technical infeasibi1ity,  depending
on circumstances.   However, EPA does not consider  a vendor guarantee alone to
be sufficient justification that a control  option  will work.  Conversely,  lack
of a vendor  guarantee by itself does not present sufficient justification  that
a control  option or an emissions limit is  technically infeasible.  Generally,
decisions  about technical feasibility will  be based on chemical, and
engineering  analyses (as discussed above)  in  conjunction with information
about vendor guarantees.

      A possible outcome of the top-down BACT procedures discussed  in this
document is  the evaluation of multiple control  technology alternatives which
result in  essentially equivalent emissions.   It is not EPA's intent to
encourage  evaluation of unnecessarily large numbers of control  alternatives
for every  emissions unit.  Consequently, judgment  should be used in deciding
what alternatives  will be evaluated in detail  in the impacts analysis (Step 4)
of the top-down procedure discussed in a later  section.  For example, if two
or more control techniques result in control  levels that are essentially
identical  considering the uncertainties of  emissions factors and other
parameters pertinent to estimating performance, the source may  wish to point
this out and make  a case for evaluation and use only of the less costly of
these options.  The scope of the BACT analysis  should be narrowed in this  way

                                     B.20

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
only if there Is a  negligible difference in emissions  and  collateral
environmental  impacts  between control  alternatives.   Such  cases  should  be
discussed with the  reviewing agency before a control  alternative is  dismissed
at this point in the BACT analysis due to such considerations.

      It is encouraged that judgments  of this type be  discussed  during  a
preapplication meeting between the applicant and the  review authority.   In
this way, the applicant can be better  assured that the analysis  to be
conducted will meet BACT requirements.  The appropriate time to  hold such  a
meeting during the  analysis is following the completion of the  control
hierarchy discussed in the next section.

Summary of Key Points

      In summary, important points to  remember in assessing technical
feasibility of control alternatives include:

      •  A control  technology that is  "demonstrated"  for a given type or  class
         of sources is assumed to be technically feasible  unless
         source-specific factors exist and are documented  to justify technical
         i nfeasibility.
      •  Technical  feasibility of technology transfer control candidates
         generally is assessed based on an evaluation of pollutant-bearing gas
         stream characteristics for the proposed source and other source  types
         to which the control had been applied previously.
      •  Innovative controls that have not been demonstrated on any source
         type similar to the proposed source need not be considered in the
         BACT analysis.
      •  The applicant is responsible for providing a basis for assessing
         technical  feasibility or infeasibility and the review authority  is
         responsible for the decision on what is and  is not technically
         feasible.
                                     B.21

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.C. RANKING THE TECHNICALLY FEASIBLE ALTERNATIVES TO ESTABLISH A CONTROL
HIERARCHY (STEP 3)
      Step 3 Involves ranking all  the technically feasible control
alternatives
which have been previously identified in Step 2.   For the regulated pollutant
and emissions unit under review,  the control  alternatives are ranked-ordered
from the most to the least effective in terms of  emission reduction potential
Later, once the control  technology is determined, the focus shifts to the
specific limits to be met by the  source.

      Two key issues that must be addressed in this process include:
         What common units should be used to compare emissions performance
         levels among options?
         How should control techniques that can operate over a wide range of
         emission performance levels (e.g., scrubbers,  etc.) be considered in
         the analysis?
IV.C.I.  CHOICE OF UNITS OF EMISSIONS PERFORMANCE TO COMPARE LEVELS AMONGST
CONTROL OPTIONS
      In general, this issue arises when comparing inherently lower-polluting
processes to one another or to add-on controls.   For example, direct
comparison of powdered (and low-VOC) coatings and vapor recovery and control
systems at a metal  furniture finishing operation is difficult because of the
different units of measure for their effectiveness.  In such cases,  it is
generally most effective to express emissions performance as an average steady
state emissions level  per unit of product produced or processed.  Examples
are:
                                     B.22

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      •  pounds  VOC  emission  per  gallons  of  solids  applied,
      •  pounds  PM emission  per ton  of  cement  produced,
      •  pounds  S02  emissions per million Btu  heat  input,  and
      •  pounds  S02  emission  per  kilowatt of electric  power  produced,

      Calculating annual  emissions levels (tons/yr)  using  these  units  becomes
straightforward  once the  projected annual  production or  processing rates  are
known.  The result is an  estimate of the  annual  pollutant  emissions that  the
source or emissions  unit  will emit.   Annual  "potential"  emission projections
are calculated using the  source's maximum design capacity  and  full  year  round
operation (8760  hours),  unless the final  permit  is  to  include  federally
enforceable conditions restricting the  source's  capacity or  hours of
operation.   However, emissions estimates  used  for the  purpose  of calculating
and comparing the cost effectiveness of a control  option are based on  a
different approach (see section  V.D.2.b.  COST  EFFECTIVENESS).
IV.C.2.  CONTROL TECHNIQUES  WITH  A WIDE RANGE  OF EMISSIONS PERFORMANCE LEVELS

      The objective of the top-down BACT  analysis is to  not  only identify the
best control technology,  but also a corresponding performance  level (or  in
some cases performance range) for that  technology considering  source-specific
factors.  Many control techniques, including both add-on controls and
inherently lower polluting processes can  perform at a  wide range of levels.
Scrubbers,  high and low efficiency electrostatic precipitators (ESPs), and
low-VOC coatings are examples of  just a few.  It is not  the  EPA's intention  to
require analysis of each  possible level of efficiency  for a  control technique,
as such an analysis would result  in a large number of  options.  Rather,  the
applicant should use the most recent regulatory  decisions and performance data
for identifying the emissions performance level(s) to  be evaluated in  all
cases.

      The EPA does not expect an  applicant to  necessarily accept an emission
limit as BACT solely because it was required previously  of a similar source
type.  While the most effective level of control must be considered in the
                                     B.23

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
BACT analysis,  different levels of control  for a given control  alternative can
be considered.1    For  example,  the  consideration  of  a  lower  level  of  control
for a given technology may be warranted in  cases where past  decisions involved
different source types.   The evaluation of  an alternative control  level  can
also be considered where the applicant can  demonstrate to the satisfaction of
the permit agency demonstrate that other considerations show the need to
evaluate the control  alternative at a lower level of effectiveness.

      Manufacturer's  data, engineering estimates and the experience  of other
sources provide the basis for determining achievable limits.  Consequently, in
assessing the capability of the control alternative, latitude exists to
consider any special  circumstances pertinent to the specific source  under
review, or regarding  the prior application  of the control alternative.
However, the basis for choosing the alternate level  (or range)  of  control  in
the BACT analysis must be documented in the application.  In the absence  of a
showing of differences between the proposed source and previously  permitted
sources achieving lower emissions limits, the permit agency  should conclude
that the lower  emissions limit is representative for that control  alternative.

      In summary, when reviewing a control  technology with a wide  range  of
emission performance  levels, it is presumed that the source  can achieve  the
same emission reduction level as another source unless the applicant
demonstrates that there are source-specific factors or other relevant
information that provide a technical, economic, energy or environmental
justification to do otherwise.  Also, a control technology that has  been
eliminated as having  an adverse economic impact at its highest  level  of
performance, may be acceptable at a lesser  level  of performance.  For example,
this can occur  when the cost effectiveness  of a control technology at its
     1  In  reviewing the BACT  submittal by a  source the permit agency may
determine that an applicant should consider a control technology alternative
otherwise eliminated by the applicant,  if  the operation of that control
technology at a lower level of control (but still higher than the next control
alternative.   For example,  while scrubber  operating  at 98% efficiency may be
eliminated as BACT by the applicant due  to source specific economic
considerations, the scrubber operating in  the 90% to 95% efficiency range may
not have an adverse economic impact.
                                     B.24

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
highest level  of performance greatly exceeds  the  cost  of that control
technology at  a  somewhat lower level  (or range)  of  performance.

IV.C.3.  ESTABLISHMENT OF THE CONTROL OPTIONS HIERARCHY

      After determining the emissions performance levels (in common units)  of
each control  technology option identified in  Step 2,  a hierarchy is
established that places at the "top" the control  technology option that
achieves the  lowest emissions level.  Each other  control option  is then placed
after the "top"  in the hierarchy by its respective  emissions performance
level, ranked  from lowest emissions to highest emissions (most effective to
least stringent  effective emissions control  alternative).

      From the hierarchy of control alternatives  the  applicant should develop
a chart (or charts) displaying the control hierarchy  and, where  applicable,:

      •  expected emission rate (tons per year,  pounds per hour);
      •  emissions performance level (e.g.,  percent pollutant removed,
         emissions per unit product, Ib/MMbtu, ppm);
      •  expected emissions reduction (tons per year);
      •  economic impacts (total annualized costs,  cost effectiveness,
         incremental cost effectiveness);
      •  environmental impacts (includes any significant or unusual other
         media impacts (e.g., water or solid waste),  and the relative ability
         of each control alternative to control  emissions of toxic or
         hazardous air contaminants);
      •  energy impacts (indicate any significant energy benefits or
         di sadvantages).
                                     B.25

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      This should be done for each  pollutant  and  for  each  emissions  unit  (or
grouping of similar units)  subject  to  a  BACT  analysis.   The  chart  is used  in
comparing the control  alternatives  during  step  4  of the  BACT selection
process.  Some sample charts are displayed in Table B-2  and  Table  B-3.
Completed sample charts accompany the  example BACT analyses  provided in
section VI.

      At this point, it is  recommended that the applicant  contact  the
reviewing agency to determine whether  the  agency  feels that  any  other
applicable control  alternative should  be evaluated or if any issues  require
special attention in the BACT selection  process.

IV.D.   THE BACT SELECTION PROCESS (STEP  4)

      After identifying and listing the  available control  options  the next
step is the determination of the energy, environmental,  and  economic impacts
of each option and  the selection of the  final level of control.  The applicant
is responsible for  presenting an evaluation of  each impact along with
appropriate supporting information.  Consequently, both  beneficial  and adverse
impacts should be discussed and, where possible,  quantified.  In general,  the
BACT analysis should focus  on the direct impact of the control alternative.

      Step 4 validates the  suitability of  the top control  option in  the
listing for selection as BACT, or provides clear  justification why the top
candidate is inappropriate  as BACT.  If  the applicant accepts the  top
alternative in the  listing  as BACT  from  an economic and  energy standpoint, the
applicant proceeds  to consider whether collateral environmental  impacts  (e.g.,
emissions of unregulated air pollutants  or impacts in other  media)  would
justify selection of an alternative control option.   If  there are  no
outstanding issues  regarding collateral  environmental impacts, the analysis  is
ended  and the results proposed as BACT.  In the event that the top candidate
                                     B.26

-------
                                                 DRAFT
                                                 OCTOBER 1990
TABLE B-2.  SAMPLE  BACT  CONTROL  HIERARCHY




Pollutant Technology
S02 First Alternative
Second Alternative
Thi rd Al ternati ve
Fourth Alternative
Fifth Alternative
Baseline Alternative

Range
of
control
(%)
80-95
80-95
70-85
40-80
50-85
-
Control
level
for BACT
analysi s
(%)
95
90
85
75
70
-



Emi
1
15
30
45
75
90
-



ssions
imi t
ppm
ppm
ppm
ppm
ppm

                   B.27

-------
S
CO

s
s
             C/l
             *-ป
             o
             CO
             o
             s
                       QJ M*

                       Sป — 1
                       -2C7
                    ku  5 CJ	

                    ฃ  g g.8
                          o
                           B
                          ป O
                          — . *->
                    <0  U)
                    k4  O

                    S  w S~
                   e  1 8^
                             Sfi^
                             i*
                             s
                      4->  tO

                      Jฐ
                      3  S3-

                      ฃฃl
                                       .8
                                       ป 2
                                           -
                                          -^ o>     to -H
                                                                   — H  o>     o> -H  a)
                                                                                                          DRAFT

                                                                                                          OCTOBER  1990
S
2
                                                                                    o

                                                                                    CO

                                                                                    o
                                                                                                             •8
                                                                                                             •o

                                                                                                             "3
                                                                                                                       O>  O)

                                                                                                                       •—•  (V
                                                                                                                       •*-*  e=
                                                                                                                       (Q ••*


                                                                                                                       O>  CO

                                                                                                                       a a
                                                             i    jj
                                                             .=, p  S  O
                                                             j-> o  5  G

                                                             B •—* ซ*^  O>

                                                             * ง  0.-S

                                                             —* C ซ-*  C_>
                                                             m *B *j  o>
                                                                   •—* **^

                                                             g ซ3  W  0>

                                                             *J  I   k4 ^ป


                                                             i s  B  i
                                                                wo
                                                             *a cP "^ -*^
                                                             v w •ซ-ป  >c
                                                             to o.  u  o>
                                                             Q _  3  B
                                                             t="<0 ."  o        ฃ  E

                                                            ZJ X 'S Z3        •"• ^J
                                                             <0 "S.     Q.          —i

                                                             cp 3 jc            o

                                                             o to *"* "o     cu ซ a*i     ป  *TJ  1—

                                                             c vi     s     ~  o> "c=


                                                             11"!  8     E ^  8

                                                             g-o-S^     5  งJ3
                                                                                                       CO  O.
                                                                                                      ซซM  o
                                                             3 B 0>  B  U     —•  w
                                                             Q.— .B  B  CP  B =>

                                                             M_ *J ""  "*  W-5 S  "~

                                                                QJ O •**  fc^  TO Q9  Q>
                                                             ~^g ซ—        Sw g  C



                                                             Q>    W  C5 -*^  -*^ S> •ป->



                                                             ^ฎ_^P  R *ฐ ปSป

                                                             ^^•gj-^  ฐ g  g


                                                             •O "TT-^ "O  Oป W W
                                                             es d> —M     .em —• —4
                                                             to *•ป  *-•

                                                          O  t^J    (5     3     ^ 4^


                                                          09  5 eo    >*-^    o •*-*  cs
                                                         *^  .W O> —H     ki  **^    •—*
                                                             ซN k_   u         w
                                                             —> —4 ซ— ซ-•  3  W -^J  OJ



                                                             ซo.wMa>ซwa>cx*M
                                                          *-i  o    a> **-•     w B ts





                                                          c  o —• ^  w "w  w —•





                                                          a  ^M cj ua    CL. c  O. iป^



                                                                                       SO)

                                                                                    *" O-
                                                          B.2S

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
is shown to be inappropriate,  due to energy,  environmental,  or  economic
impacts, the rationale for this finding  needs to  be  fully  documented  for  the
public record.  Then,  the next most effective alternative  in the  listing
becomes the new control  candidate and is similarly evaluated.   This  process
continues until  the control  technology under  consideration cannot be
eliminated by any source-specific environmental,  energy,  or  economic  impacts
which demonstrate that the alternative is inappropriate as BACT.

      The determination that a control alternative to be  inappropriate
involves a demonstration that circumstances exist at the  source which
distinguish it from other sources where  the control  alternative may  have  been
required previously, or that argue against the transfer of technology or
application of new technology.  Alternately,  where a control technique has
been applied to only one or a very limited number of sources,  the applicant
can identify those character!stic(s) unique to those sources that may have
made the application of the control appropriate in those  case(s)  but  not  for
the source under consideration.  In showing unusual  circumstances, objective
factors dealing with the control technology and its application should be the
focus of the consideration.  The specifics of the situation will  determine to
what extent an appropriate demonstration has  been made regarding the
elimination of the more effective alternative(s)  as BACT.   In the absence of
unusual circumstance, the presumption is that sources within the same category
are similar in nature, and that cost and other impacts that have been borne by
one source of a given source category may be borne by another source of the
same source category.

IV.D.I.  ENERGY IMPACTS ANALYSIS
      Applicants should examine the energy requirements of the control
technology and determine whether the use of that technology results in any
significant or unusual energy penalties or benefits.  A source may,  for
example, benefit from the combustion of a concentrated gas stream rich in
volatile organic compounds; on  the other hand, more often extra fuel  or
electricity is required to power a control device or incinerate a dilute gas
stream.  If such benefits or penalties  exist, they should be quantified.
Because  energy penalties  or benefits can usually be quantified in terms of
                                      B.29

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
additional  cost or income to the source,  the energy impacts analysis can,  in
most cases,  simply be factored into the economic impacts analysis.   However,
certain types of control  technologies have inherent energy penalties
associated  with their use.  While these penalties should be quantified,  so
long as they are within the normal  range  for the technology in question,  such
penalties should not, in  general, be considered adequate justification for
nonuse of that technology.

      Energy impacts should consider only direct energy consumption and  not
indirect energy impacts.   For example,  the applicant could estimate the  direct
energy impacts of the control alternative in units of energy consumption  at
the source  ( e.g., Btu, kwh, barrels of oil, tons of coal).  The energy
requirements of the control options should be shown in terms of total  (and in
certain cases also incremental) energy costs per ton of pollutant removed.
These units  can then be converted into dollar costs and, where appropriate,
factored into the economic analysis.

      As noted earlier, indirect energy impacts (such as energy to  produce raw
materials for construction of control equipment) generally are not  considered.
However, if  the permit authority determines, either independently or based on
a showing by the applicant, that the indirect energy impact is unusual or
significant  and that the  impact can be well  quantified, the indirect impact
may be considered.  The energy impact should still focus on the application of
the control  alternative and not a concern over general energy impacts
associated  with the project under review  as  compared to alternative projects
for which a  permit is not being sought, or as compared to a pollution  source
which the project under review would replace (e.g., it would be inappropriate
to argue that a cogeneration project is more efficient in the production  of
electricity  than the powerplant production capacity it would displace  and,
therefore,  should not be  required to spend equivalent costs for the control of
the same pol1utant).

      The energy impact analysis may also address concerns over the use  of
locally scarce fuels.  The designation of a  scarce fuel may vary from  region
to region,  but in general a scarce fuel is one which is in short supply
                                     B.30

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
locally and can be better used for alternative purposes,  or  one which  may  not
be reasonably available to the source either at the  present  time or  in the
near future.

IV.D.2.  COST/ECONOMIC IMPACTS ANALYSIS

      Average and incremental  cost effectiveness are the  two economic  criteria
that are considered in the BACT analysis.   Cost effectiveness,  is the  dollars
per  ton of pollutant emissions reduced.  Incremental  cost is the cost  per  ton
reduced and should be considered in conjunction with total  average
effectiveness.
      In the  economical impacts analysis,  primary consideration should be
given  to quantifying the cost  of control  and not the economic situation of the
individual source.  Consequently,  applicants generally should not propose
elimination of control alternatives on the basis of  economic parameters that
provide an indication of the affordabi1ity of a control  alternative  relative
to the source.   BACT is required by law.   Its costs  are integral to  the
overall cost  of doing business and are not to be considered  an  afterthought.
Consequently, for control alternatives that have been effectively employed in
the  same source category, the  economic impact of such alternatives on  the
particular source under review should be not nearly  as pertinent to  the BACT
decision making process as the average and, where appropriate,  incremental
cost effectiveness of the control  alternative.  Thus, where  a control
technology has been successfully applied to similar  sources  in  a source
category, an  applicant should  concentrate on documenting  significant cost
differences,  if any, between the application of the  control  technology on
those other sources and the particular source under  review.

      Cost effectiveness (dollars per ton of pollutant reduced) values above
the levels experienced by other sources of the same  type  and pollutant, are
taken as an indication that unusual and persuasive differences  exist with
respect to the source under review.   In addition, where the cost of  a  control
alternative for the specific source reviewed is within the range of  normal
costs for that control alternative, the alternative, in certain limited
circumstances, may still be eligible  for elimination.  To justify elimination
                                      B.31

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
of an alternative on these grounds,  the applicant should demonstrate to the
satisfaction of the permitting agency that costs of pollutant removal  for  the
control  alternative are disproportionately high when compared to the cost  of
control  for that particular pollutant and source in recent BACT
determinations.  If the circumstances of the differences are adequately
documented and explained in the application and are acceptable to the
reviewing agency they may provide a  basis for eliminating the control
alternati ve.

      In all cases, economic impacts need to be considered in conjunction  with
energy and environmental impacts (e.g., toxics and hazardous pollutant
considerations) in selecting BACT.   It is possible that the environmental
impacts analysis or other considerations (as described elsewhere) would
override the economic elimination criteria as described in this section.
However, absent overriding environmental impacts concerns or other
considerations, an acceptable demonstration of a adverse economic impact  can
be adequate basis for eliminating the control alternative.
IV.D.2.3.  ESTIMATING THE COSTS OF CONTROL

      Before costs can be estimated, the control system design parameters  must
be specified.   The most important item here is to ensure that the design
parameters used in costing are consistent with emissions estimates used in
other portions of the PSD application (e.g., dispersion modeling inputs and
permit emission limits).  In general, the BACT analysis should present vendor-
supplied design parameters.  Potential sources of other data on design
parameters are BID documents used to support NSPS development, control
technique guidelines documents, cost manuals developed by EPA, or control  data
in trade publications.  Table B-4 presents some example design parameters
which are important in determining system costs.
                                     B.32

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      To begin,  the limits  of the area  or  process  segment  to  be  costed
specified.   This well  defined area  or  process  segment  is  referred  to  as  the
control  system battery limits.   The second step  is to  list and cost  each major
piece of equipment within the battery  limits.  The top-down BACT analysis
should provide this list of costed  equipment.  The basis  for  equipment  cost
estimates also should  be documented,  either with data  supplied by  an  equipment
vendor (i.e.,  budget estimates or bids) or by  a  referenced source  [such  as  the
OAQPS Control  Cost Manual (Fourth Edition), EPA  450/3-90-006,  January 1990,
Table B-4].   Inadequate documentation  of battery limits  is one of  the most
common reasons for confusion in comparison of  costs of the same  controls
applied  to  similar sources.  For control options that  are  defined  as
inherently  lower-polluting processes  (and  not  add-on controls),  the  battery
limits may  be  the entire process or project.

      Design parameters should correspond  to the specified emission  level.
The equipment  vendors  will  usually supply  the  design parameters  to the
applicant,  who in turn should provide  them to  the reviewing agency.   In  order
to determine if the design is reasonable,  the  design parameters  can  be
compared with  those shown in documents such as the OAQPS Control Cost Manual .
Control  Technology for Hazardous Air  Pollutants  (HAPS) Manual  (EPA 625/6-86-
014, September 1986),  and background  information documents for NSPS  and NESHAP
regulations.  If the design specified  does not appear  reasonable,  then the
applicant should be requested to supply performance test data for the control
technology  in  question applied to the  same source, or  a similar  source.
                                     B.33

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
            TABLE B-4.   EXAMPLE  CONTROL  SYSTEM  DESIGN  PARAMETERS
Control
Example Design parameters
Wet Scrubbers
Carbon Absorbers
Condensers
Incineration
Electrostatic Precipitator
Fabric Filter
Selective Catalytic Reduction
Scrubber liquor (water, chemicals, etc.)
Gas pressure drop
Liquid/gas ratio

Specific chemical  species
Gas pressure drop
Ibs carbon/lbs pollutant

Condenser type
Outlet temperature

Residence time
Temperature

Specific collection area (ft2/acfm)
Voltage density

Ai r to cloth ratio
Pressure drop

Space velocity
Ammonia to NOx molar ratio
Pressure drop
Catalyst life
                                     B.34

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Once the control  technology alternatives and achievable emissions  performance
levels have been  identified,  capital  and annual  costs  are developed.   These
costs form the basis of the cost and  economic impacts  (discussed later)  used
to determine and  document if a control  alternative should be eliminated  on
grounds of its economic impacts.

      Consistency in the approach to  decision-making is a primary  objective of
the top-down BACT approach.  In order to maintain  and  improve the  consistency
of BACT decisions made on the basis of cost and  economic considerations,
procedures for estimating control equipment costs  are  based on EPA's  OAQPS
Control cost Manual  and are set forth in Appendix  B of this document.
Applicants should closely follow the  procedures  in the appendix and any
deviations should be clearly presented and justified in the documentation of
the BACT analysis.

      Normally the submittal of very  detailed and  comprehensive project  cost
data is not necessary.  However, where initial control cost projections  on the
part of the applicant appear excessive or unreasonable (in light of recent
cost data) more detailed and comprehensive cost  data may be necessary to
document the applicant's projections.  An applicant proposing the top
alternative usually does not need to  provide cost  data on the other possible
control alternatives.

      Total cost estimates of options developed  for BACT analyses should be on
order of plus or minus 30 percent accuracy.  If  more accurate cost data  are
available  (such as specific bid estimates), these  should be used.   However,
these types of costs may not be available at the time permit applications are
being prepared.  Costs should also be site specific.  Some site specific
factors are costs of raw materials (fuel, water, chemicals) and labor.  For
example, in some remote areas costs  can be unusually high.  For example,
remote  locations in Alaska may  experience a 40-50  percent premium on
installation  costs.  The applicant should document any unusual  costing
assumptions used in the analysis.
                                     B.35

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.D.2.b.   COST EFFECTIVENESS
      Cost effectiveness is the economic criterion used to assess the
potential  for achieving an objective at least cost.   Effectiveness is measured
in terms of tons of pollutant emissions removed.   Cost is measured in terms of
annualized control  costs.

      The Cost effectiveness calculations can be  conducted on an average,  or
incremental basis.   The resultant dollar figures  are sensitive to the number
of alternatives costed as  well  as the underlying  engineering and cost
parameters. There are limits to the use of cost-effectiveness analysis.   For
example, cost-effectiveness analysis should not be used to set the
environmental objective.  Second, cost-effectiveness should, in and of itself,
not be construed as a measure of adverse economic impacts.  There are two
measures of cost-effectiveness  that will be discussed in this section:  (1)
average cost-effectiveness, and  (2) incremental  cost-effectiveness.

Average Cost Effectiveness

      Average cost  effectiveness (total annualized costs of control divided by
annual emission reductions, or  the difference between the baseline emission
rate and the controlled emission rate) is a way to present the costs  of
control.  Average cost effectiveness is calculated as shown by the following
formula:

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
           Average cost Effectiveness (dollars per ton removed) =
                  Control option annualized cost	
            Baseline emissions rate - Control option emissions rate

      Costs are calculated in  (annualized)  dollars  per  year  ($/yr)  and
emi ssi ons
rates are calculated  in  tons per  year  (tons/yr).   The  result is a  cost
effectiveness  number  in  (annualized)  dollars  per  ton  ($/ton) of pollutant
removed.

Calculating Baseline  Emissions

      The baseline emissions rate represents  a realistic  scenario  of upper
boundary  uncontrolled emissions for the  source.   The  NSPS/NESHAP requirements
or the application of controls, including other  controls  necessary to comply
with State or  local  air  pollution regulations, are not  considered  in
calculating the baseline emissions.  In  other words,  baseline emissions are
essentially uncontrolled emissions, calculated using  realistic upper boundary
operating assumptions.   When calculating the  cost effectiveness of adding  post
process emissions controls to certain  inherently  lower  polluting processes,
baseline  emissions may be assumed to be  the emissions  from the lower polluting
process itself.  In other words,  emission reduction credit can be  taken for
use of inherently lower  polluting processes.

      Estimating realistic upper-bound case scenario  does not mean that the
source operates in an absolute worst case manner  all  the  time.  For example,
in
developing a realistic upper boundary case, baseline  emissions calculations
can also  consider inherent physical or operational  constraints on  the source.
Such constraints should  accurately reflect the true upper boundary of the
source's  ability to physically operate and the applicant  should submit
documentation  to verify  these constraints.  If the applicant does  not
adequately verify these  constraints, then the reviewing agency should not  be
compelled to consider these constraints  in calculating baseline emissions.  In
addition, the reviewing  agency may require the applicant  to calculate cost
                                     B.37

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
effectiveness based on values exceeding the upper boundary assumptions to
determine whether or not the assumptions have a deciding role in the BACT
determination.   If the assumptions have a deciding role in the BACT
determination,  the reviewing agency should include enforceable conditions  in
the permit to assure that the upper bound assumptions are not exceeded.

      For example, VOC emissions from a storage tank might vary significantly
with temperature, volatility of liquid stored,  and throughput.  In this  case,
potential emissions would be overestimated if annual  VOC emissions were
estimated by extrapolating over the course of a year VOC emissions based
solely on the hottest summer day.   Instead, the range of expected temperatures
should be considered in determining annual baseline emissions.  Likewise,
potential emissions would be overestimated if one assumed that gasoline  would
be stored in a  storage tank being  built to feed an oil-fired power boiler  or
such a tank will  be continually filled and emptied.  On the other hand,  an
upper bound case for a storage tank being constructed to store and transfer
liquid fuels at a marine terminal  should consider emissions based on the most
volatile liquids at a high annual  throughput level since it would not be
unrealistic for the tank to operate in such a manner.

      In addition, historic upper  bound operating data, typical  for the
source or industry, may be used in defining baseline emissions in evaluating
the cost effectiveness of a control option for  a specific source.   For
example, if for a source or industry, historical upper bound operations
call for two shifts a day, it is not necessary  to assume full time (8760
hours) operation on an annual basis in calculating baseline emissions.  For
comparing cost  effectiveness, the  same realistic upper boundary assumptions
must, however,  be used for both the source in question and other sources  (or
source categories) that will later be compared  during the BACT analysis.
      For example, suppose  (based on verified  historic data regarding the
industry in question) a given source can be expected to utilize numerous
colored inks over the course of a  year.  Each color ink has a different  VOC
content ranging from a high VOC content to a relatively low VOC content.   The
source verifies that its operation will indeed  call for the application  of
numerous color  inks.  In this case, it is more  realistic for the baseline
                                     B.38

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
emission calculation  for the source (and other similar  sources)  to be based  on
the expected mix of inks that would be expected to  result  in  an  upper boundary
case annual  VOC emissions rather than  an assumption that  only one color  (i.e,
the ink with the highest VOC content)  will  be applied  exclusively during  the
who!e year.

      In another example, suppose sources in a particular  industry
historically operate  at most at 85 percent  capacity.   For  BACT cost
effectiveness purposes (but not for applicability), an  applicant may calculate
cost effectiveness using 85 percent capacity.  However,  in comparing costs
with similar sources,  the applicant must consistently  use  an  85  percent
capacity factor for the cost effectiveness  of controls  on  those  other sources.
      Although permit conditions are normally used to make operating
assumptions enforceable,  the use of "standard industry practice" parameters
for cost effectiveness calculations (but not applicability determinations)  can
be acceptable without permit conditions.  However, when a source projects
operating parameters (e.g., limited hours of operation or capacity
utilization, type of fuel, raw materials or product mix or type) that are
lower than standard industry practice or which have a deciding role in the
BACT determination, then  these parameters or assumptions must be made
enforceable with permit conditions.  If the applicant will not accept
enforceable permit conditions, then the reviewing agency should use the
absolute worst case uncontrolled emissions in calculating baseline emissions.
This is necessary to ensure that the permit reflects the conditions under
which the source intends  to operate.

      For example, the baseline emissions calculation for an emergency standby
generator may consider the fact that the source does not intend to operate
more than 2 weeks a year.   On the other hand, baseline emissions associated
with a base-loaded turbine would not consider limited hours of operation.
This produces a significantly higher level of baseline emissions than in the
case of the emergency/standby unit and  results in more cost effective
controls.  As a consequence of the dissimilar baseline emissions, BACT for  the
                                     B.39

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
two cases could be very different.   Therefore,  it is  important that the
applicant confirm that the operational  assumptions used to define the source's
baseline emissions (and BACT)  are genuine.   As  previously mentioned,  this  is
usually done through enforceable permit conditions which reflect limits on the
source's operation which were  used  to calculate baseline emissions.

      In certain cases, such explicit permit conditions may not be necessary.
For example, a source for which continuous  operation  would be a physical
impossibility (by virtue of its design) may consider  this limitation  in
estimating baseline emissions,  without  a direct permit limit on operations.
However, the permit agency has  the  responsibility to  verify that the  source is
constructed and operated consistent with the information and design
specifications contained in the permit  application.

      For some sources it may  be more difficult to define what emissions  level
actually represents uncontrolled emissions  in calculating baseline emissions.
For example, uncontrolled emissions could theoretically be defined for a  spray
coating operation as the maximum VOC content coating  at the highest possible
rate of application that the spray  equipment could physically process, (even
though use of such a coating or application rate would be unrealistic for  the
source).  Assuming use of a coating with a  VOC  content and application rate
greater than expected is unrealistic and would  result in an overestimate  in
the  amount of emissions reductions to  be achieved by the installation of
various control options.  Likewise, the cost effectiveness of the options
could consequently be greatly  underestimated.  To avoid these problems,
uncontrolled emission factors  should be represented by the highest realistic
VOC content of
the types of coatings and highest realistic application rates that would  be
used by the source, rather than by  highest  VOC  based  coating materials or  rate
of application in general.

      Conversely, if uncontrolled emissions are underestimated, emissions
reductions to be achieved by the various control options would also be
underestimated and their cost  effectiveness overestimated.  For example,  this
type of situation occurs in the previous example if the baseline for the  above
                                     B.40

-------
                                                                          DRAFT
                                                                          OCTOBER 1990
        coating operation was based on a VOC content coating or application rate that
        is too low [when the source had the ability and intent to utilize (even
        infrequently) a higher VOC content coating or application rate].
        Incremental Cost Effectiveness

              In addition to the average cost effectiveness of a control option,
        incremental cost effectiveness between control options should also be
        calculated. The incremental cost effectiveness should be examined in
        combination with the total cost effectiveness in order to justify elimination
        of a control option.  The incremental cost effectiveness calculation compares
        the costs and emissions performance level of a control option to those of the
        next most stringent option, as shown in the following formula:

                            Incremental Cost (dollars per incremental ton removed) =
Total  costs  (annualized)  of  control  option  -  Total  costs  (annualized)  of next  control  option
            Next  control  option  emission  rate  -  Control  option emissions rate

              Care should be exercised in deriving incremental costs of candidate
        control options.  Incremental cost-effectiveness comparisons should focus on
        annualized cost and emission  reduction differences between dominant
        alternatives.  Dominant set of control alternatives are determined by
        generating what is  called the envelope of least-cost  alternatives.  This is a
        graphical plot of total annualized costs for a total  emissions  reductions for
        all control alternatives  identified in the BACT analysis (see Figure B-l).

              For example,  assume that eight technically available control options for
        analysis are listed in the BACT hierarchy.  These  are  represented as A through
        H in  Figure B-l.  In calculating incremental costs, the analysis should only
        be conducted for control  options that are dominant among all possible options.
        In Figure  B-l, the  dominant set of control options, A, B, D, F, G, and H,
        represent  the  least-cost  envelope depicted by the  curvilinear line connecting
        them.  Points  C and E are  inferior options and should  not be considered in the
                                              B.41

-------
   I
Dominant controls (A, B, D, F, G, H) lie on envelope
Oco
r-H
rnCO
          Inferior controls (A,C,E)
                                                              DRAFT
                                                              OCTOBER 1990
                                              'delta" Total Annual Costs
                                         J	I	I
             INCREASING EMISSIONS REDUCTION (Tons/yr)
            Figure B-1.  LEAST-COST ENVELOPE
                                 B.42

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
derivation of incremental  cost effectiveness.   Points  A,  C and  E represent
inferior controls because  B will  buy more emissions  reduction  for less money
than A;  and similarly,  D and F will  by more reductions for less money than E,
respectively.

      Consequently, care should be taken in selecting  the dominant set of
controls when calculating  incremental  costs.   First,  the  control options  need
to be rank ordered in ascending order of annualized  total costs.  Then, as
Figure B-l illustrates, the most reasonable smooth curve  of the control
options  is plotted.  The incremental cost effectiveness is then determined by
the difference in total annual costs between  two contiguous options divided by
the difference in emissions reduction.  An example is  illustrated in Figure
B-l for  the incremental cost effectiveness for control option  F.  The vertical
distance, "delta" Total Costs Annualized, divided by the  horizontal distance,
"delta"  Emissions Reduced  (tpy), would be the measure  of  the incremental  cost
effectiveness for option F.

      A comparison of incremental costs can also be  useful in  evaluating the
economic viability of a specific control option over a range of efficiencies.
For example, depending on  the capital  and operational  cost of  a control
device,  total and incremental cost may vary significantly (either increasing
or decreasing) over the operation range of a  control  device.

      As a precaution, differences in incremental costs among  dominant
alternatives cannot be used by itself to argue one dominant alternative is
preferred to another.  For example, suppose dominant alternative is preferred
to another.  For example,  suppose dominant alternatives B, D and F on the
least-cost envelope (see Figure B-l) are identified  as alternatives for a BACT
analysis.  We may observe the incremental cost effectiveness between dominant
alternative B and D is $500 per ton whereas between  dominant alternative D and
F is $1000 per ton.  Alternative D does not dominate alternative F.  Both
alternatives are dominant and hence on the least cost envelope.  Alternative D
cannot  legitimately be preferred to F on grounds of incremental cost
effectiveness.
                                     B.43

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      In addition,  when evaluating the total  or incremental  cost effectiveness
of a control  alternative,  reasonable and supportable assumptions regarding
control  efficiencies should be made.  An unrealistically low assessment of the
emission reduction  potential  of a certain technology could result in inflated
cost effectiveness  figures.

      The final  decision regarding the reasonableness of calculated cost
effectiveness values will  be made by the review authority considering previous
regulatory decisions.  Study cost estimates used  in BACT are typically
accurate to ฑ 20 to 30 percent.  Therefore, control cost options which are
within ฑ 20 to 30 percent  of each other should generally be  considered to  be
indistinguishable when comparing options.

IV.D.2.C.  DETERMINING AN  ADVERSE ECONOMIC IMPACT

      It is important to keep in mind that BACT is primarily a  technology-
based standard.   In essence,  if the cost of reducing emissions  with the top
control  alternative, expressed in dollars per ton, is on the same order as the
cost previously borne by other sources of the same type in applying that
control  alternative, the alternative should initially be considered
economically achievable, and therefore acceptable as BACT.  However, unusual
circumstances may greatly  affect the cost of  controls in a specific
application.   If so they should be documented.  An example of an unusual
circumstance might  be the  unavailability in an arid region of the large
amounts of water needed for a scrubbing system.   Acquiring water from a
distant location might add unreasonable costs to  the alternative, thereby
justifying its elimination on economic grounds.   Consequently,  where unusual
factors exist that  result  in cost/economic impacts beyond the range normally
incurred by other sources  in that category, the technology can  be eliminated
provided the applicant has adequately identified  the circumstances, including
the cost or other analyses, that show what is significantly  different about
the proposed source.

      Where the cost of a  control alternative for the specific  source being
reviewed is within  the range of normal costs  for  that control alternative, the
                                     B.44

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
alternative may also be eligible for elimination in limited circumstances.
This may occur, for example,  where a control  alternative has not  been  required
as BACT (or its application as BACT has been  extremely limited)  and  there  is  a
clear demarcation between recent BACT control  costs in that source category
and the control costs for sources in that source category which  have been
driven by other constraining  factors (e.g.,  need to meet a PSD increment  or a
NAAQS).

      To justify elimination  of an alternative on these grounds,  the applicant
should demonstrate to the satisfaction of the permitting agency  that costs of
pollutant removal (e.g., dollars per total  ton removed) for the  control
alternative are disproportionately high when  compared to the cost of control
for the pollutant in recent BACT determinations.  Specifically,  the applicant
should document that the cost to the applicant of the control alternative is
significantly beyond the range of recent costs normally associated with  BACT
for the type of facility (or  BACT control costs in general) for  the pollutant.
This type of analysis should  demonstrate that a technically and  economically
feasible control option is nevertheless, by virtue of the magnitude of its
associated costs and limited  application, unreasonable or otherwise not
"achievable" as BACT in the particular case.   Total and incremental  cost
effectiveness numbers are factored into this  type of analysis.  However,  such
economic information should be coupled with a comprehensive demonstration,
based on objective factors, that the technology is inappropriate in the
specific circumstance.

      The economic impact portion of the BACT analysis should not focus  on
inappropriate factors or exclude pertinent factors, as the results may be
misleading.  For example, the capital cost of a control option may appear
excessive when presented by itself or as a percentage of the total project
cost.  However, this type of information can be misleading.  If a large
emissions reduction  is projected, low or reasonable cost effectiveness numbers
may validate the option as an appropriate BACT alternative irrespective of the
apparent high  capital costs.   In another example, undue focus on incremental
cost effectiveness can give an impression that the cost of a control
                                     B.45

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
alternative is unreasonably high,  when,  in  fact,  the  total  cost  effectiveness,
in terms of dollars per total  ton  removed,  is  well  within  the normal  range of
acceptable BACT costs.

IV.D.3.   ENVIRONMENTAL  IMPACTS ANALYSIS

      The environmental impacts analysis is not to  be confused with  the air
quality  impact analysis (i.e., ambient  concentrations),  which is an
independent statutory and regulatory requirement  and  is  conducted separately
from the BACT analysis.  The purpose of  the air quality  analysis is  to
demonstrate that the source (using the  level  of control  ultimately determined
to be BACT) will not cause or contribute to a  violation  of any applicable
national ambient air quality standard or PSD increment.  Thus, regardless  of
the level of control proposed as BACT,  a permit cannot be  issued to  a  source
that would cause or contribute to  such  a violation.   In  contrast, the
environmental impacts portion of the BACT
analysis concentrates on impacts other  than impacts  on air quality (i.e.,
ambient  concentrations) due to emissions of the regulated  pollutant  in
question, such as solid or hazardous waste  generation, discharges of polluted
water from a control device, visibility  impacts,  or  emissions of unregulated
pollutants.

      Thus, the fact that a given  control  alternative would result in  only a
slight decrease in ambient concentrations of the  pollutant in question when
compared to a less stringent control alternative  should  not be viewed  as  an
adverse  environmental impact justifying  rejection of  the more stringent
control  alternative.  However, if  the cost  effectiveness of the  more stringent
alternative is exceptionally high, it may (as  provided in  section V.D.2.)  be
considered in determining the existence  of  an  adverse economic impact  that
would justify rejection of the more stringent  alternative.
                                     B.46

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      The applicant should identify any significant  or  unusual  environmental
impacts associated with a control  alternative that  have the  potential  to
affect the selection or elimination of a control  alternative.   Some control
technologies may have potentially  significant secondary (i.e.,  collateral)
environmental  impacts.   Scrubber effluent,  for example, may  affect water
quality and land use.  Similarly,  emissions of water vapor from technologies
using cooling towers may affect local  visibility.   Other examples of secondary
environmental  impacts could include hazardous waste  discharges, such as spent
catalysts or contaminated carbon.   Generally, these  types of environmental
concerns become important when sensitive site-specific  receptors exist or when
the incremental emissions reduction potential of  the top control is only
marginally greater than the next most  effective option.  However, the fact
that a control  device creates liquid and solid waste that must  be disposed of
does not necessarily argue against selection of that technology as BACT,
particularly if the control device has been applied to  similar  facilities
elsewhere and the solid or liquid waste problem under review is similar to
those other applications.  On the other hand, where the applicant can show
that unusual circumstances at the proposed facility create greater problems
than experienced elsewhere, this may provide a basis for the elimination  of
that control alternative as BACT.

      The procedure for conducting an  analysis of environmental impacts should
be made based on a consideration of site-specific circumstances.  In general,
however, the analysis of environmental impacts starts with the  identification
and quantification of the solid, liquid, and gaseous discharges from the
control device or devices under review.  This analysis  of environmental
impacts should be performed for the entire hierarchy of technologies (even if
the applicant proposes to adopt the "top", or most stringent, alternative).
However, the analysis need only address those control alternatives with any
significant or unusual environmental impacts that have the potential to affect
the selection or elimination of a control alternative.   Thus, the relative
environmental  impacts  (both positive and negative) of the various alternatives
can be  compared with each other and the "top" alternative.
                                     B.47

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Initially,  a qualitative or semi-quantitative screening is  performed to
narrow the analysis to discharges with  potential  for causing adverse
environmental  effects.  Next,  the mass  and composition of any such discharges
should be assessed and quantified to the extent possible, based on readily
available information.  Pertinent information  about the public or
environmental  consequences of  releasing these  materials should also be
assembled.

IV.D.S.a.  EXAMPLES (Environmental  Impacts)

      The following paragraphs discuss  some possible factors for
considerations in evaluating the potential for an  adverse other media impact.

      •  Water Impact

      Relative quantities of water used and water  pollutants produced and
discharged as  a result of use  of each alternative  emission control  system
relative to the "top" alternative would be identified.  Where possible,  the
analysis would assess the effect on ground water  and such local  surface  water
quality parameters as ph, turbidity, dissolved oxygen, salinity,  toxic
chemical levels,  temperature,  and any other important considerations. The
analysis should consider whether applicable water  quality standards will be
met and the availability and effectiveness of  various techniques  to reduce
potential adverse effects.

      •  Solid Waste Disposal  Impact

      The quality and quantity of solid waste  (e.g., sludges, solids) that
must be stored and disposed of or recycled as  a result of the application  of
each alternative  emission control system would be  compared with the quality
and quantity of wastes created with the "top"  emission control system.  The
composition and various other  characteristics  of  the solid waste  (such as
permeability,  water retention, rewatering of dried material, compression
strength, Teachability of dissolved ions, bulk density, ability to support
vegetation growth and hazardous characteristics)  which are significant with
                                     B.48

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
regard to potential  surface water pollution or transport into and
contamination of subsurface waters or  aquifers would  be  appropriate  for
consideration.

      •  Irreversible or Irretrievable Commitment of  Resources

      The BACT decision may consider the extent to which the alternative
emission control systems may involve a trade-off between short-term
environmental gains  at the expense of  long-term environmental losses and  the
extent to which the  alternative systems may result in irreversible or
irretrievable commitment of resources  (for example, use  of scarce  water
resources).

      •  Other  Environmental Impacts

      Significant differences in noise levels, radiant heat, or dissipated
static electrical energy may be considered.

      One environmental impact that could be examined is the trade-off
between emissions of the various pollutants resulting from the application of
a specific control technology.  The use of certain control technologies  may
lead to increases in emissions of pollutants other than  those the  technology
was designed to control.  For example, the use of certain volatile organic
compound (VOC)  control technologies can increase nitrogen oxides (NOx)
emissions.   In  this  instance, the reviewing authority may want to  give
consideration to any relevant local air quality concern  relative to the
secondary pollutant (in this case NOx) in the region  of  the proposed source.
For example, if the region in the example were nonattainment for NOx, a
premium could be placed on the potential NOx impact.   This could lead to
elimination  of  the most stringent VOC technology (assuming it generated  high
quantities of NOx) in favor of one having less of an  impact on ambient NOx
concentrations.  Another example is the potential for higher emissions of
toxic and hazardous pollutants from a municipal waste combustor operating at a
low flame temperature to reduce the formation of NOx.   In this case the  real
concern to mitigate the emissions of toxic and hazardous emissions  (via  high
                                     B.49

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
combustion temperatures) may well  take precedent over mitigating NOx emissions
through the use of a low flame temperature.   However, in most cases (unless an
overriding concern over the formation and impact of the secondary pollutant is
clearly present as in the examples given),  it is not expected that this type
impact would affect the outcome of the decision.

      Other examples of collateral environmental impacts would include
hazardous waste discharges such as spent catalysts or contaminated carbon.
Generally these types of environmental concerns become important when site-
specific sensitive receptors exist or when  the incremental  emissions reduction
potential of the top control option is only  marginally greater than the next
most effective option.

IV.D.S.b.  CONSIDERATION OF EMISSIONS OF TOXIC AND HAZARDOUS AIR POLLUTANTS

      The generation or reduction  of toxic  and hazardous emissions, including
compounds not regulated under the  Clean Air  Act, are considered as part of  the
environmental impacts analysis.  Pursuant to the EPA Administrator's decision
in North County Resource Recovery  Associates. PSD Appeal No. 85-2 (Remand
Order, June 3, 1986), a PSD permitting authority should consider the effects
of a given control alternative on  emissions  of toxics or hazardous pollutants
not regulated under the Clean Air  Act.  The  ability of a given control
alternative to control releases of unregulated toxic or hazardous emissions
must be evaluated and may, as appropriate,  affect the BACT  decision.
Conversely, hazardous or toxic emissions resulting from a given control
technology should also be considered and may, as appropriate, also affect  the
BACT decision.

      Because of the variety of sources and  pollutants that may be considered
in this assessment, it is not feasible for  the EPA to provide highly detailed
national guidance on performing an evaluation of the toxic  impacts as part  of
the BACT determination.  Also, detailed information with respect to the type
and magnitude of emissions of unregulated pollutants for many source
categories is currently limited.   For example, a combustion source emits
hundreds of substances, but knowledge of the magnitude of some of these
                                     B.50

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
emissions or the hazards they produce is  sparse.   The  EPA  believes it  is
appropriate for agencies to proceed  on  a  case-by-case  basis  using  the  best
information available.   Thus, the determination  of whether the  pollutants
would be emitted in amounts sufficient  to be  of  concern  is one  that the
permitting authority has considerable discretion  in making.   However,
reasonable efforts should be made to address  these issues.  For example,  such
efforts might include consultation with the:

      •  EPA Regional Office;
      •  Control Technology Center (CTC);
      •  National  Air Toxics Information  Clearinghouse;

      •  Air Risk Information Support Center  in  the Office of Air  Quality
         Planning and Standards (OAQPS);  and
      •  Review of the literature, such as;  EPA-prepared compilations  of
         emission factors.
Source-specific information supplied by the  permit applicant is often
the best source of information, and it  is important that the applicant be  made
aware of its responsibility to provide  for a  reasonable  accounting of  air
toxics emissions.

      Similarly, once the pollutants of concern  are identified, the permitting
authority has flexibility in determining  the  methods by  which it factors  air
toxics considerations into the BACT determination, subject to the  obligation
to make reasonable efforts to consider  air toxics.  Consultation by the review
authority with  EPA's implementation centers,  particularly  the CTC, is  again
advised.

      It is important to note that several acceptable methods,  including  risk
assessment, exist to incorporate air toxics  concerns into  the BACT decision.
The depth of the toxics assessment will vary  with the circumstances of the
particular source under review, the nature and magnitude of the toxic
pollutants, and the  locality.  Emissions of  toxic or hazardous  pollutant  of
concern to the  permit agency should be identified and, to  the extent possible,
quantified.  In addition, the effectiveness  of the various control
                                     B.51

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
alternatives in the hierarchy at controlling the toxic pollutant  should be
estimated and summarized to assist in making judgements about how potential
emissions of toxic or hazardous pollutants may be mitigated  through  the
selection of one control  option over another.   For example,  the response to
the Administrator made by EPA Region IX in its analysis of the North County
permitting decision illustrates one of several approaches  (for further
information see the September 22,  1987 EPA memorandum from Mr. Gerald Emission
titled "Implementation of North County Resource Recover PSD  Remand"  and July
28, 1988 EPA memorandum from Mr. John Calcagni titled "Supplemental  guidance
on Implementing the North County Prevention of Significant Deterioration (PSD)
Remand").

      Under a top-down BACT analysis, the control alternative selected as BACT
will  most likely reduce toxic emissions as well  as the regulated  pollutant.
An example is the emissions of heavy metals typically associated  with coal
combustion.  The metals generally  are a portion of,  or adsorbed on,  the fine
particulate in the exhaust gas stream.  Collection of the  particulate in a
high efficiency  fabric filter rather than a low efficiency  electrostatic
precipitator reduces  criteria pollutant particulate matter  emissions and
toxic heavy metals emissions.  Because in most instances the interests of
reducing toxics coincide with the  interests of reducing the  pollutants subject
to BACT, consideration of toxics in the BACT analysis generally amounts to
quantifying toxic emission levels  for the various control  options.

      In limited other instances,  though, control of regulated pollutant
emissions may compete with control of toxic compounds, as  in the  case of
certain selective catalytic reduction (SCR) NOx control technologies.  The SCR
technology itself results in emissions of ammonia, which increase,  generally
speaking, with increasing levels of NOx control.  It is the  intent of the
toxics screening in the BACT procedure to identify and quantify this type of
toxic effect.  Generally, toxic effects of this type will  not necessarily be
overriding concerns and will likely not to affect BACT decisions.  Rather, the
intent is to require a screening of toxics emissions effects to ensure that a
possible overriding toxics issue does not escape notice.
                                     B.52

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      On occasion,  consideration of toxics emissions may support the selection
of a control  technology that yields less than the maximum degree of reduction
in emissions  of the regulated pollutant in question.  An example is the
municipal  solid waste combustor and resource recovery facility that was the
subject of the North County remand.  Briefly, BACT for S02 and PM was selected
to be a lime  slurry spray drier followed by a fabric filter.   The combination
yields good S02 control  (approximately 83 percent), good PM  control
(approximately 99.5 percent) and also removes acid gases (approximately 95
percent),  metals, dioxins,  and  other unregulated pollutants.   In this
instance,  the permitting authority determined that good balanced control  of
regulated  and unregulated pollutants took priority over achieving the maximum
degree of  emissions reduction for one or more regulated pollutants.
Specifically, higher levels (up to 95 percent) of S02 control  could have been
obtained by a wet scrubber.

IV.E.  SELECTING BACT (STEP 5)

      The  most effective control alternative not eliminated in Step 4 is
selected as BACT.

      It is important to note that, regardless of the control  level proposed
by the applicant as BACT, the ultimate BACT decision is made by the permit
issuing agency after public review.  The applicant's role is primarily to
provide information on the various control options and, when it proposes a
less stringent control option, provide a detailed rationale and supporting
documentation for eliminating the more stringent options.  It is the
responsibility of the permit agency to review the documentation and rationale
presented  and; (1) ensure that the applicant has addressed all of the most
effective control options that could be applied and; (2) determine that the
applicant has adequately demonstrated that energy, environmental, or economic
impacts justify  any proposal to eliminate the more effective control options.
Where the permit agency does not accept the  basis for the proposed elimination
of  a control  option, the agency may inform the applicant of the need for more
information  regarding the control  option.  However, the BACT selection
essentially  should default to the  highest level of  control for which the
                                     B.53

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
applicant could not adequately justify its elimination based on energy,
environmental  and economic impacts.   If the applicant is unable to provide to
the permit agency's satisfaction an  adequate demonstration for one or more
control  alternatives,  the permit agency should proceed to establish BACT and
prepare  a draft permit based on the  most effective control option for which an
adequate justification for rejection was not provided.

IV.F.   OTHER CONSIDERATIONS

      Once energy,  environmental,  and economic impacts have been considered,
BACT can only  be made  more stringent by other considerations outside the
normal  scope of the BACT analysis  as discussed under the above steps.
Examples include cases where BACT  does not produce a degree of control
stringent enough to prevent exceedances of a national  ambient air quality
standard or PSD increment, or where  the State or local agency will  not  accept
the level of control  selected as BACT and requires more stringent controls to
preserve a greater  amount of the available increment.   A permit cannot  be
issued to a source  that would cause  or contribute to such a violation,
regardless of  the outcome of the BACT analysis.   Also, States which have set
ambient  air quality standards at levels tighter  than the federal standards may
demand a more  stringent level of control at a source to demonstrate compliance
with the State standards.  Another consideration which could override the
selected BACT  are legal constraints  outside of the Clean Air Act requiring the
application of a more  stringent technology (e.g., a consent decree requiring  a
greater  degree of control).  In all  cases, regardless of the rationale  for the
permit requiring a  more stringent  emissions limit than would have otherwise
been chosen as a result of the BACT  selection process, the emission limit  in
the final permit (and  corresponding  control alternative) represents BACT for
the permitted  source on a case-by-case basis.

      The BACT emission limit in a new source permit is not set until the
final  permit is issued.  The final permit is not issued until a draft permit
has gone through public comment and  the permitting agency has had an
opportunity to consider any new information that may have come to light during
the comment period.  Consequently, in setting a  proposed or final BACT  limit,
                                     B.54

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
the permit agency can consider new information it learns,  including recent
permit decisions, subsequent to the submittal  of a  complete application.   This
emphasizes the importance of ensuring that prior to the selection of a
proposed BACT, all  potential sources of information have been reviewed by  the
source to ensure that the list of potentially  applicable control  alternatives
is complete (most importantly as it relates to any  more effective control
options than the one chosen) and that all  considerations relating to economic,
energy and environmental  impacts have been addressed.
                                     B.55

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
V.  ENFORCEABILITY OF BACT
      To complete the BACT process,  the reviewing agency must  establish  an
enforceable emission limit for each  subject emission  unit at the  source  and
for each pollutant subject to review that is emitted  from the  source.   If
technological  or economic limitations in the application of  a  measurement
methodology to a particular emission unit would make  an emissions limit
infeasible, a  design, equipment,  work practice, operation standard,  or
combination thereof, may be prescribed.  Also,  the technology  upon which the
BACT emissions limit is based should be specified in  the permit.   These
requirements should be written in the permit so that  they are  specific to the
individual  emission unit(s) subject  to PSD review.

      The emissions limits must be included in  the proposed  permit submitted
for public comment, as well as the final permit.   BACT emission  limits or
conditions must be met on a continual basis at  all levels of operation (e.g.,
limits written in pounds/MMbtu or percent reduction achieved),  demonstrate
protection of  short term ambient  standards (limits written in  pounds/hour)  and
be enforceable as a practical matter (contain appropriate averaging  times,
compliance verification procedures and recordkeeping  requirements).
Consequently,  the permit must:

      •  be able to show compliance  or noncompliance  (i.e.,  through
         monitoring times of operation, fuel input, or other indices of
         operating conditions and practices); and
      •  specify a reasonable averaging time consistent with established
         reference methods, contain  reference methods for determining
         compliance, and provide  for adequate reporting and  recordkeeping so
         that  the permitting agency  can determine the compliance  status  of
         the source.
                                     B.56

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
VI.  EXAMPLE BACT ANALYSES FOR GAS TURBINES
Note: The following example provided is for illustration only.  The example
source is fictitious and has been created to highlight many of the aspects of the
top-down process.  Finally, it must be noted that the cost data and other numbers
presented in the example are used only to demonstrate the BACT decision making
process.  Cost data are used in a relative  sense to compare control costs among
sources in a source category or for a pollutant.   Determination of appropriate
costs is made on a case-by-case basis.

      In this section a BACT analysis for a stationary gas turbine project is

presented and discussed under three alternative operating scenarios:

      •  Example l--Simple Cycle Gas Turbines Firing Natural  Gas

      •  Example 2--Combined Cycle Gas Turbines Firing Natural Gas

      •  Example 3--Combined Cycle Gas Turbines Firing Distillate Oil


      The purpose of the examples are to illustrate points to be considered in
developing BACT decision criteria for the source under review and selecting

BACT.  They are intended to illustrate the process rather than provide
universal guidance on what constitutes BACT for any particular source
category.  BACT must be determined on a case-by-case basis.


      These examples are not based on any actual  analyses performed for the
purposes of obtaining a PSD permit.  Consequently, the actual emission rates,
costs, and design parameters used are neither representative  of any actual
case nor do they apply to any  particular facility.
                                     B.57

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
VI.A.   EXAMPLE 1--SIMPLE CYCLE GAS TURBINES FIRING NATURAL GAS

VI.A.I  PROJECT SUMMARY

      Table B-5 presents project data,  stationary gas design  parameters,  and
uncontrolled emission estimates for the new source in example 1.   The gas
turbine is designed to provide peaking  service to an  electric utility.   The
planned operating hours are less than 1000 hours per  year.  Natural  gas fuel
will  be fired.  The source will be limited through enforceable  conditions  to
the specified hours of operation and fuel  type.   The  area  where the  source is
to be located is in compliance for all  criteria  pollutants.   No other changes
are proposed at this facility, and therefore the net  emissions  change will  be
equal  to the emissions shown on Table B-5.  Only NOx  emissions  are significant
(i.e., greater than the 40 tpy significance level for NOx) and  a  BACT analysis
is required for NOx emissions only.

VI.A.2.  BACT ANALYSIS SUMMARY

VII.A.2.a.  CONTROL TECHNOLOGY OPTIONS

      The first step in evaluating BACT is identifying all candidate control
technology options for the emissions unit  under  review.   Table  B-6 presents
the list of control technologies selected  as potential  BACT candidates.  The
first three control technologies, water or steam injection and  selective
catalytic reduction, were identified by a  review of existing  gas  turbine
facilities in operation.  Selective noncatalytic reduction was  identified  as  a
potential type of control technology because it  is an add-on  NOx  control  which
has been applied to other types of combustion sources.
                                     B.58

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
         TABLE B-5.   EXAMPLE  1--COMBUSTION  TURBINE  DESIGN  PARAMETERS

Characteristics

Number of emissions units           1
Unit Type                           Gas Turbines
Cycle Type                          Simple-cycle
Output                              75 MW
Exhaust temperature,                1,000 ฐF
Fuel(s)                             Natural  Gas
Heat rate,  Btu/kw hr                11,000
Fuel flow,  Btu/hr                   1,650 million
Fuel flow,  Ib/hr                    83,300
Service Type                        Peaking
Operating Hours (per year)          1,000
Uncontrolled Emissions, tpy(a)
      NOX                     564 (169 ppm)
      S02                     <1
      CO                            4.6 (6  ppm)
      VOC                           1
      PM                            5 (0.0097 gr/dscf)

(a) Based on 1000 hours per year of operation at full load
                                     B.59

-------
                                                                                       DRAFT
                                                                                       OCTOBER 1990
                   TABLE  B-6.   EXAMPLE  1--SUMMARY  OF POTENTIAL NOx CONTROL
                                        TECHNOLOGY OPTIONS




Control technology(a)
Typical
control
efficiency
range
(% reduction)


Simple
cycle
turbines
In Service On:
Combi ned
cycle
gas
turbines


Other
combustion
sources(c)

Technically
feasible on
simple cycle
turbines
Selective Catalytic
  Reductions

Water  Injection

Steam  Injection

Low NOx Burner

Selective Noncatalytic
  Reduction
                             40-90
                                            No
30-70
30-70
30-70
20-50
Yes
No
Yes
No
                                                         Yes
Yes
Yes
Yes
Yes
                                                                     Yes
            Yes
            Yes
            Yes
            Yes
Yes(b)


Yes

No

Yes

No
(a)  Ranked in order  of highest to  lowest stringency.
(b)  Exhaust must be  diluted with air to reduce  its temperature to 600-750ฐF.
(c)  Boiler incinerators, etc.
                                                 B.60

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
In this example,  the control  technologies were identified by the
applicant based on a review of the BACT/LAER Clearinghouse,  and discussions
with State agencies with experience permitting gas turbines  in  NOx
nonattainment areas.  A preliminary meeting with the State permit issuing
agency was held to determine whether the permitting agency felt that any other
applicable control technologies should be evaluated and they agreed on the
proposed control  hierarchy.

VI.A.Z.b.  TECHNICAL FEASIBILITY CONSIDERATIONS

      Once potential control  technologies have been identified, each
technology is evaluated for its technical feasibility based  on  the
characteristics of the source.  Because the gas turbines in  this example are
intended to be used for peaking service, a heat recovery steam  generator
(HRSG) will not be included.  A HRSG recovers heat from the  gas turbine
exhaust to make steam and increase overall energy efficiency.  A portion of
the steam produced can be used for steam injection for NOx control, sometimes
increasing the effectiveness of the net injection control system.  However,
the electrical demands of the grid dictate that the turbine  will be brought on
line only for short periods of time to meet peak demands.  Due  to the lag time
required to bring a heat recovery steam generator on line, it is not
technically feasible to use a HRSG at the facility.  Use of  an  HRSG in this
instance was shown to interfere with the performance of the  unit for peaking
service, which requires immediate response times for the turbine.  Although it
was shown that a  HRSG was not feasible and therefore not available, water and
steam  are readily available for NOx control since the turbine will be located
near an  existing  steam generating powerplant.

       The turbine type and, therefore, the turbine model selection process,
affects  the achievability of  NOx emissions limits.  Factors which the customer
considered in  selecting the proposed turbine model were outlined in the
application as:   the peak demand which must be met, efficiency of the gas
turbine,  reliability requirements, and the experience of the utility with the
operation  and  maintenance  service of the  particular manufacturer and turbine
design.   In this  example, the proposed turbine is equipped with a combustor
                                     B.61

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
designed to achieve an emission level,  at 15 percent 02,  of 25 ppm NOx with
steam injection or 42 ppm with water injection.2

      Selective noncatalytic reduction  (SNCR) was eliminated as technically
infeasible and therefore not available,  because this technology requires  a
flue gas temperature of 1300 to 2100ฐF.   The exhaust from the gas  turbines
will be approximately 1000ฐF,  which is  below the  required temperature  range.

      Selective catalytic reduction (SCR) was evaluated and no basis was  found
to eliminate this technology as technically infeasible.  However,  there are no
known examples where SCR technology has  been applied to a simple-cycle gas
turbine or to a gas turbine in peaking  service.  In all cases where SCR has
been applied, there was an HRSG which served to reduce the exhaust temperature
to the optimum range of 600-750oF and the gas turbine was operated
continuously.  Consequently, application of SCR to a simple cycle  turbine
involves special  circumstances.  For this example, it is  assumed that  dilution
air can be added to the gas turbine exhaust to reduce its temperature.
However, the dilution air will make the  system more costly due to  higher  gas
flows, and may reduce the removal efficiency because the  NOx concentration at
the inlet will be reduced.  Cost considerations are considered later in the
analysi s.

VI.A.2.C.   CONTROL TECHNOLOGY HIERARCHY

      After determining technical feasibility, the applicant selected  the
control levels for evaluation shown in  Table B-7.  Although the applicant
     2  For  some gas  turbine models,  25 ppm  is not achievable with either water
or steam injection.
                                     B.62

-------
                                                             DRAFT
                                                             OCTOBER 1990
        TABLE  B-7.   EXAMPLE  1--CONTROL TECHNOLOGY HIERARCHY
 	Emissions Limits
Control  Technology                         ppm(a)      TRY

Steam Injection plus SCR                   13           44
Steam Injection at maximum(b> design rate   25           84
Water Injection at maximum"" design rate   42           140
Steam Injection to meet NSPS               93           312
(a) Corrected to 15 percent oxygen.
(b) Water to fuel ratio.
                                 B.63

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
reported that some sites in California have achieved levels as low as 9 ppm,
at this facility a 13 ppm level  was determined to be the feasible limit with
SCR.  This decision is based on  the lowest achievable level with steam
injection of 25 ppm and an SCR removal efficiency of 50 percent.  Even though
the reported removal  efficiencies for SCR are up to 90 percent at some
facilities, at this facility the actual  NOx concentration at the inlet to the
SCR system will only  be approximately 17 ppm (at actual conditions)  due to the
dilution air required.  Also the inlet concentrations, flowrates, and
temperatures will  vary due to the high frequency of startups.  These factors
make achieving the optimum 90 percent NOx removal efficiency unrealistic.
Based on discussions  with SCR vendors, the applicant has established a
50 percent removal efficiency as the highest level  achievable, thereby
resulting in a 13  ppm level (i.e., 50 percent of 25 ppm).

      The next most stringent level achievable would be steam injection at the
maximum water-to-fuel ratio achievable by the unit  within its design operating
range.  For this particular gas  turbine model, that level is 25 ppm as
supported by vendor NOx emissions guarantees and unit test data.  The
applicant provided documentation obtained from the  gas turbine manufacturer3
verifying ability  to  achieve this range.

      After steam  injection the  next most stringent level of control would be
water injection at the maximum water-to-fuel ratio  achievable by the unit
within its design  operating range.  For this particular gas turbine model,
that level is 42 ppm  as supported by vendor NOx emissions guarantees and
actual unit test data.  The applicant provided documentation obtained from the
gas turbine manufacturer verifying ability to achieve this range.

      The least stringent level  evaluated by the applicant was the current
NSPS for utility gas  turbines.  For this model, that level is 93 ppm at
15 percent 02.  By definition, BACT can be no less  stringent than NSPS.
     3  It  should be noted  that  achievability  of  the NOX limits is dependent on
the turbine model,  fuel,  type of wet injection  (water or steam), and system
design.  Not all  gas  turbine models or fuels can necessarily achieve these
levels.
                                     B.64

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Therefore,  less stringent levels  are not evaluated.

VI.A.Z.d.   IMPACTS ANALYSIS SUMMARY

      The  next steps completed by the applicant were  the  development  of  the
cost, economic, environmental  and energy impacts of  the different  control
alternatives.  Although the top-down process would  allow  for  the  selection  of
the top alternative without a  cost analysis, the applicant  felt cost/economic
impacts were excessive and that appropriate documentation may justify the
elimination of SCR as BACT and therefore chose to quantify  cost and  economic
impacts.  Because the technologies in this case are  applied in combination,  it
was necessary to quantify impacts for each of the alternatives.   The  impact
estimates  are shown in Table B-8.  Adequate documentation of  the  basis for  the
impacts was determined to be included in the PSD permit application.

      The  incremental cost impacts shown are the cost of  the  alternative
compared to the next most stringent control alternative.   Figure  B-2  is  a  plot
of the least-cost envelope defined by the list of control options.

VI.A.2.6.   TOXICS ASSESSMENT

      If SCR were applied, potential toxic emissions of  ammonia could occur.
Ammonia emissions resulting from application of SCR could be  as large as 20
tons per year.  Application of SCR would reduce NOx by an additional  20 tpy
over steam injection alone (25 ppmHnot including ammonia emissions).

      Another environmental impact considered was the spent catalyst which
would have to be disposed of at certain operating intervals.   The catalyst
contains vanadium pentoxide, which is listed as a hazardous waste under RCRA
regulations  (40 CFR  261.3).  Disposal of this waste creates an additional
economic and environmental burden.  This was considered  in  the applicant's
proposed BACT determination.
                                     B.65

-------
a; 2


































































^
o
8

ซ
0
ft.

0}
H
g
CO
u
K
CO
H
CO
3


2

H
CJ
-a;
Pi
53
H

6
Si

g

g

o.
g

fa
o

iH

g
9

CO

i
H

M
J

Jg
2

H

*
CO
1
a
M
j
9
H

01
JJ
u
to
o
g
M

H
10
JJ
C
OJ
g
c
0
rl
-H
G
H


OJ
01
rl
OJ
>
•a
ซ:













01
JJ
U
10
Q
E
H

ฃ
r4
OJ
C
W


rH
tO
JJ 
G
OJ


01
u
-H
X
O
EH








iH
01
>
O










JJ
01
O
u









01
Dl
OJ
G
OJ
>
•rl
JJ
CJ
OJ
IH
IH
OJ




73
OJ
M
-rl
rH
10

ฃ*
10




rH
10
JJ
-H
ft
tO
CJ




01
G
O
-H
01
01
-H


































, 	
JJ O
0 K
a \
ft 01
g 0)
•H >M





o
JJ "Zt
o -^
to ro
ft OJ
E >H
•rl ~-



~ iH
H-l >i

(1) 3
G JJ
-H m
rH S
OJ g
01 —
10
ft

„
OJ

01
01 ~~
OJ C
C 0
OJ JJ
> \
•H VI-
JJ -~
CJ
OJ
IH
4H
OJ


, 	 .
73

OJ
rl 	 	 	
•H G
rH O
OJ JJ
01 \
10 V>
a —

rl
OJ
>
O




~ rl
0 N

JJ V>
01 —
o
CJ






_
XI ~
— ' VI-
JJ —
Dl
0
CJ



	
10
G U
O ft
-H JJ
JJ ~-
CJ
3
•O
OJ
r4

"N
03 ft
C JJ
O —
-rH
01 ~-
CO rl
-H XI
E \
W XI
rH





OJ
>
-H
JJ
10
g
OJ
JJ
rH
to

rH
0
rl
ฃ
o
u



o
s









w
0)
>*








o
o
o
ซ
^tป
\s>
^f








o
o
CN

\D
in











o
o
^

ซ>







01

o
o
o

r-
rH
r-
H





o
o
0

o
1>
•*

rH
rH




0
ID
CN





CN
CN





•^
•*







-H
JJ
(0
d
rH
Q)
4J
rH
<


a
m
rH



O
&









O
&









o
0
o
,.
o
n








o
VD
^p

CO












0
[^
•^

CN









0
O
0

n
en
in






0
o
o

0
en
r-

in





o
•^
CN





(N
-tf





^f
CO






(U
>
-H
4J
cd
c
.H
0)
4J
rH
<


a
in
CN



O
&









O
g









o
o
m
..
in
H








o
o
CD














o
CO
^o

rH









O
o
o

VD
in
m






o
o
0

^ป
o
n
ป
H





CN
rH
CN





O
r-





0
•*
H





0)
>
-H
.U
ง
rl
OJ
JJ
rH
ft


a
M
^J*



O i
g









O i
z









o
O 1
0
-
CO









1
















in i
CO
CN

CN









o
o
o

CO
CO
CN






o
o
0

r~
CN
en







\ฃ> 1
CN
H





\D CN
in co
rH CN




CN ^i
H U>
ro i/l



OJ
G
-H
rH
OJ
01 01
> CO
•rl CQ
JJ
10 T3
G OJ
iH rH
OJ rH
JJ O
rH !H
< JJ
G
W O
ฃ4 CJ
en c
a o




























































































rH
HI
>
01 •
rH 01
G
rH -H
O rH
rl OJ
JJ 01
C 10
O XI
CJ
O
OJ JJ
-H 01
rH >
0) -H
01 JJ
CO CO
XI rH
OJ
rl r(
OJ
> JJ
o as
0
C cj
O
•rl H
JJ fO
CJ JJ
P -H
•O ft
OJ tct
rl O
01 T3
C OJ
O rH
•H rH
01 10
01 JJ
-H CO
ftl M

15 XI


OJ 4J
XI 0
JJ OJ
0) 4J
S > 4H
rH O -H tO
fO • iH JJ
JJ 01 4H fO 73
•H JJ G 0) C
ft 01 Dl rl > 3
10 O C 0) -H 0
CJ CJ -H 4J JJ 4H
JJ rH fO O
< rH rH tO G iH
10 3 IH ft
3 CO rH 0)
• C OJ O -U tO
OJ C rl rl rH
> 10 JJ tO OJ
-H 01 C >
JJ >, C O rH tO
fO (0 O CJ O rG
G 73 -H H
^4 1 JJ OJ JJ >,
OJ JJ CJ XI G tO
JJ G 3 JJ O g
rH OJ T3 CJ
fO 01 OJ JJ OJ
QJ rl fO OJ 4H
rH r4 X! G -H
O ft CO JJ -H rH
VJ G rH
JJ C O JJ 0) JJ
C -H -H ft 01 01
O 01 OJ tO >,
O CO 01 CJ XI i-l
JJ -H X 10
T3 CO E OJ • OJ JJ
OJ O 0) H) XI tO
CO CJ tO > JJ CJ
0 01 -rl -rH
ft rH XI H OJ T3 G
O 10 JJ 0) to G O
rl JJ JJ G tO
ft -rt >i -H iH 01
ft XI rl OJ 0) 73
OJ fO U JJ > ffl
XI O T3 rH -H E
JJ OJ 01 10 JJ
01 T) Dl 10 Dl
Dl 01 -H OJ rH C C
C OJ > C O rl O
-H rl -H 0) H OJ -H
JJ ft TI > JJ JJ JJ
fO X -H G rH ft
rl OJ C JJ O 10 E
OJ O U O 3
ft O -H OJ rH CO
O JJ JJ 4H OJ O Dl
ft IH G ri <
•O T3 O 0) -H JJ
CO) rH G
fO 01 rH JJ OJ O
3O 01 01 CJ rl
rl O fO fO
Dl CO JJ U X} OJ OJ
G -H C XI >i
-H O rH 0) JJ
rH ~ U fO J3 rl
rH G JJ -JJ X! 0)
tO O 0) O JJ ft
JJ -H XI JJ G -rl
01 JJ JJ 10 S CO
G tO 0) X! in
-H rH ^ XI JJ 01 3
IH o JJ JJ O
- C IH n C XI
Dl -H 01 OJ 0)
C JJ fO XI E 0
-rl JJ 01 JJ OJ O
01 G O 0) (0 rl O
tO 0) O g rl -H H
XI CD to 3
CJ XI 73 CO 0) & >i
W ID CU > CO rH
3 N OJ -H H C
ft - -H XI JJ O
• rH JJ (0 >!
IH 0) fO C Dl CO
O • 3 01 rl rl 0)
-H G -H aj aj jj
~ — G JJ G to
JJ tO 10 rH OJ iH
O CD -H to 0)
Q) JJ rH rl JJ • ft
rICOtO OJJJCJrlO
•H H JJ JJ G 01 10
•d O -H OJ -n OJ 0)
GJJJJ rlOlOSG
•H CO O C rl -rl
OJ O -rl ft IH XI
73 iH JJ CO rl OJ rl
GO) CO JJ rH ft 3
fO JJ rH OJ CO fO JJ
G to C JJ CO
--H3 OJJJO301
JJ O1 > CO JJ JJ -H
O rH 0) -HO ฃ0 XI
0) to JJ g C JJ
rl Q) 01 CJ -H IH
•H rl -H CD JJ O OJ
73 IH X 0) D
to Q) IH OJ U 01 c
G OJ G C G -H
rH Dl-H 0) O CO
10 G rH JJ OJ rl -H
JJ-HOJ COXIOJrHOJ
-HD1CQ OJJ'HrH'H
ft 3 to cj IH -H -H
ffl XI O -H g rH
O XI rH JJ T)
-^ U rl (0 JJ JJ 01
(001 -JJOJOJGOIOI
JJO>0)C>X!OJ>iO)
COrlOGOJ-HJJrHrHG
Oft -HgjJ rdtoo)
CJftCOrHOJtOCU>JJ>
tOCOHJrllHrl-HtO-H
73 ajaicja)(03DjJ
OJ^GtOGrl & CJ
NOCUXl-rl OlOJrlOJ
-rl jj > T3 JJ to IH
rHCJ-HrdrHCUOCOJIH
(OtOiJCUtOrltfl-rH^tl;
3 IH 0 rH C 0) ft
G OJrHO73g73OJJ
G >i MH O -H -H -H OJ rH CO
fOrllHrlJJOl 01 O
0)MjJftG>i0173CJ
rH> GOOD10JO)
COOJJO OrlH3G
JJO01CJOJ OJftOlO
OOJOCXIcoGXcoft
EHrlO3EH-rl&JOJl<3

tj 7? "cu in "m

                                                                                                                                           to
                                                                                                                                           to

-------
                                                            DRAFT

                                                            OCTOBER 1990
  2,000,000
   1,500,000
ro
CD
0

Q.
W
O
O


0
.N

"ro

c
c
   1,000,000
    500,000
                 50     100     150     200    250     300

                   Emissions Reduction (tons per year)



    Figure B-2. Least-Cost Envelope for Example 1
                            B.67

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
VI.A.2.f.   RATIONALE FOR PROPOSED BACT
      Based on these impacts,  the applicant proposed eliminating the 13 ppm
alternative as economically infeasible.   The applicant documented that the
cost effectiveness is high at  6,600 $/ton,  and well  out of the range of recent
BACT NOx control  costs for similar sources.  The incremental  cost
effectiveness of $56,200 also  is high compared to the incremental  cost
effectiveness of the next option.

The applicant documented that  the other  combustion turbine sources which
have applied SCR have much higher operating hours (i.e.,  all  were permitted as
base-loaded units).   Also, these sources had heat recovery steam generators so
that the cost effectiveness of the application of SCR was lower.  For this
source,  dilution air must be added to cool  the flue  gas to the proper
temperature.  This increases the cost of the SCR system relative to the same
gas turbine with a HRSG.  Therefore,  the other sources had much lower cost
impacts  for SCR relative to steam injection alone, and much lower cost
effectiveness numbers.  Application of SCR  would also result  in emission of
ammonia, a toxic chemical, of  possibly 20 tons per year while reducing NOx
emissions by 20 tons per year.  The applicant asserted that,  based on these
circumstances, to apply SCR in this case would be an unreasonable burden
compared to what has been done at other  similar sources.

      Consequently,  the applicant proposed  eliminating the SCR plus steam
injection alternative.  The applicant then  accepted  the next  control
alternative, steam injection to 25 ppmv.  The use of steam injection was shown
by the applicant to  be consistent with recent BACT determinations for similar
sources.  The review authority concurred with the proposed elimination of SCR
and the  selection of a 25 ppmv limit as  BACT.  The use of steam injection was
shown by the applicant to be consistent  with recent  BACT determinations for
similar  sources.   The review authority concurred with the proposed elimination
of SCR and the selection of a  25 ppmv limit as BACT.
                                     B.68

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
VLB.  EXAMPLE 2--COMBINED CYCLE GAS TURBINES FIRING  NATURAL GAS
      Table B-9 presents the design parameters  for  an  alternative  set  of
circumstances.  In this example,  two gas turbines  are  being installed.  Also,
the operating hours are 5000 per  year and the new  turbines  are being  added  to
meet intermediate loads demands.   The source will  be  limited through
enforceable conditions to the specified hours of operation  and fuel  type.   In
this case, HRSG units are installed.  The applicable  control technologies  and
control technology hierarchy are  the same as the previous example  except  that
no dilution is required for the gas turbine exhaust because the HRSG  serves to
reduce the exhaust temperature to the optimum level  for SCR operation.  Also,
since there is no dilution required and fewer startups, the most stringent
control option proposed is 9 ppm  based on performance limits for several  other
natural gas fired baseload combustion turbine facilities.

      Table B-10 presents the results of the cost  and economic impact analysis
for the example and Figure B-3 is a plot of the least-cost  envelope defined by
the list of control options.  The incremental cost impacts  shown are  the  cost
of the alternative compared to the next most stringent control alternative.
Due to the increased operating hours and design changes, the economic impacts
of SCR are much lower for this case.  There does not  appear to be  a persuasive
argument for stating that SCR is  economically infeasible.  Cost effectiveness
numbers are within the range typically required of this and other  similar
source types.

       In this case, there would also be emissions  of ammonia.  However, now
the magnitude of ammonia emissions, approximately 40 tons per year, is much
lower than the additional NOx reduction achieved,  which is 270 tons per year.

      Under these alternative circumstances, PM emissions are also now above
the significance level (i.e., greater than 25 tpy).  The gas turbine
                                     B.69

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
         TABLE  B-9.   EXAMPLE  2--COMBUSTION  TURBINE  DESIGN  PARAMETERS
Characteri sti cs
Number of emission units
Emission units
Cycle Type
Output
   Gas Turbines (2 @ 75 MW each)
   Steam Turbine (no emissions generated)
Fuel(s)
Gas Turbine Heat Rate, Btu/kw-hr
Fuel Flow per gas turbine, Btu/hr
Fuel Flow per gas turbine, Ib/hr
Service Type
Hours per year of operation
Uncontrolled Emissions per gas turbine, tpy (a)(b)
   NOX
   S02
   CO
   VOC
   PM
Gas Turbine
Combi ned-cycle

150 MW
70 MW
Natural Gas
11,000 Btu/kw-hr
1,650 million
83,300
Intermedi ate
5000

1,410 (169 ppm)
<1
23 (6 ppm)
5
25 (0.0097 gr/dscf)
(a) Based on 5000 hours per year of operation.
(b) Total uncontrolled emissions for the proposed project is equal to the
pollutants uncontrolled emission rate multiplied by 2 turbines.  For example,
total NOX = (2  turbines)  x 1410  tpy per turbine)  = 2820 tpy.
                                     B.70

-------















































1— ^
Ol
I i I-H


^C ' ' '
m
rv- O
h-
O
Q o















































































































0
S5

oi
o
b

CO
H

^
CO
a
PJ

CO
H
CO

^

2

H
CJ

PJ
S
H

S

CQ

g
Gj
o
a


o
H

[V,
o

^1

,rf

tjl

™

fs




*gj
Jrf





o
H

n

M

i
E-!




































CO
o
IB

g
M

rH
CO
4-1
C
CU
ฃ
C
0
rl
•H
>
C
H























CO
4J
O
IB


M

ฃ>.
O
n
CD
C
BJ


rH
IB
4J
C
CD
E
D

U
C
VH
























CO
4J
CJ
co
p
ฃ
H

CJ

i
c

c
CJ
w

















































































u
c
-H
XI
n
r



cn
0

CO
C
c

c/
H

E
W












































CU
CO

U
>
TJ
<

















CU
CQ
CO
CU

U
C
-H






rH
IB
4J
C
U
ฃ
11

U
C
M










4J
CO
O
U










,— 1
CO
4J
O








•O
11
rH
rH
CO
4J
01
C
M













































10
4J
C - — •
CU -O O
E 0 2
C IB ^
O ft CO
n E CJ
-H -H >H

C
D


01 4J O
0 CJ g
•rl CO \
X ft 01
O E cu
EH "H >H




tH . —
— rl
cn >,
C -^
Vl -rl 3
U rH 4J
>  0
CO -H 4-1
O 4J \
o o 
cu •—
tH
<4H
CU


. 	 .
•a

CO D
CO C
11 -H
C rH ~
CU CU C
> 01 O
•H CO 4J
4-1 43 ^
CJ Vf
CU rl —
tj cu

CD O




T3 —
CD CJ — .
N — rl
-rt 4J >i

co O 
3O —


CO





rH — -
IB X)
4J -— --~
-rl 4-1 VI-
ft CO ~-
CO O
U O

, 	 ,
i!

CO
01 —
fi C
0 0 ~
-H -H >,
01 4J ft
CQ CJ 4J
•H 3 —
ฃ T3
ta D
ri

s^
CO ft
C 4J
o —
-rl
CO ~
01 rl
•H 43
E ^
fa xi
rH





u

-H
4J
CO
e
a.
4J
rH
to
1— 1
o

4J
c
0
a



o
&









w
cu










o
o
o
„
O
\Q
r-t









O
O
CN)

OJ
t-f










rH
m
in
,.








Dl

o
o
o
,
0
CO
m

ff)





o
0
o
^
o
CO
cr>
ป
o
rH






in
m

rH





in







0
n







0)

•H
4J
(0
C
rH
QJ
4J
rH

e
P4
a

CTป



O










0
!2










O
o
0

l/l
o
H









o
L/l
O

VD











O
•^
„
rH









O
O
o
..
o
n
p*

r-t





o
o
o
v
H
CT)
r-

rH







O
O
CN

H





O
rH
(N





^4
00






0.

-H
JJ
frt
C
0)
4J
rH
E
a
a

in
CN



o










0











o
o
CN

[^
in










rH
CO
rH













f*!
n
CO











o
o
0
,
n
CO
CO







o
0
o
,.
^
o
n
ซ
H







O
O

rH





O
in
ro





0

rH





(D

-H
U
(0
C
V4
0)
4J
rH
e
a
a

IN
*$*



0 i










O i
K










o
O 1
o
..
[^
CN










I















O t
CO
CN
ซ
rH









O
O
O
.. |
in
o
CO







o
o
o
.. i
[*-
CN
a\









O 1
3







o o
CO rH
r*- ^t

rH



CN tj
H ^
m Lf)



(U
-H
rH
(U
a) to
> ft
-H CQ
4J
(Tj *&
C cu
n rH
0) rH
-U O
rH rl
ft, 4J
C
w o
P! u
ra C
2 ?
cu

4J C
cu o
E > -H
rH O -H 4J
IB • rl 4J O
4J CO M-l (0 3
•H 4J C CU -O
ft CO (31 rl > H)
co o c cu -H n
O CJ -H 4J JJ
4J rH IB CU
< rH rH IB C 4i
CO 3 M 4J
3 CO rH D
• C D O -U co
CU C rl rl rH D
> CO 4J CO E
•H CO C -H
4J >l ti O rH 4J
CO CO O O O
C TJ -H rl O
rl 1 4J 0) 4J 3
D 4J O 43 C 4J
4J C 3 4-> O
rH CU 13 O • O
CO CQ CU -U CO 4-1
cu ri IB u co
rH rl 43 C3 CU rH
O ft CO 4J -H C CO
rl fi rH D 3
4J a 0 4J CU > O1
0 -H -H ft CO -H CU
O 01 CU IB 4J
U 01 01 O XI U CU
4J -H X CU XI
T3 01 ฃ 01 • CU •tH
U O CU CU 43 >*H rH
01 U CO > JJ CU H
O CU -H -rl -rl
ftrH43 rl4JT) -US
O CO 4J U CO C CO
rl -0 4J C CO O D
ft-rl >, -rl Wl CJ >
ft X) rl D 0) -H
CU CO O 4J > C 4J
43 U T3 rH -H O CO
4J U 01 CO 4J ft C
01 Tl 01 IB 3 rl
CJ> Cn -rl CD rH ft QJ
COI> COH 4J4J
•rl rl -rl CU rl U CJ rH
4JftTJ >-U4J CUIB
CO X -H C rH I4H
rlCUC JJOCO tHC
CD O CJ CJ IB CO
ft O -H U rH
O4J-U t+HCUO T3rl
ft  D
4J -H 43 4J C -rl IB rl
CO 4J 4J CB S 43
C co CU 43 01
-rlr-Hn 434-101 r*lC3
I4H 0 -U 4J It 0
- c IH n c E -ri
Cn -ri co D cu CQ
C -U CO 43 E CU CQ
-H 4J 01 4J CU 4H -H
coco oicon -Hฃ
COCDO En-H rHCU
43 01 IB 3
OX1T3 CQCUO1 4JD
n CO 0) > D CO T3
3 N U -H JH >, -H
ft - -rl 43 4J rH S
• rH 4J CO >l CO
tH CU CO C 01 4J 4J
o • 3 01 n n co cj
-H C -H CU OJ U OJ
~ ~— C 4J C -n

cj D -H co on
CU 4J rH n 4J ft
ntOcO D4JCJrll)
-Hrl4J 4JCCUCOT3rH
rH T) O -HCU-nUcOtB
CU C4J4J nD10Nฃ3
> -H 01 CJ C n 4J
U- DO -HftncQU
rHUT3n4-J CQrl DCcO
CCD CQ4JrHftO
rH-HCO-Ur-H UCQCO -H-
OrH CtO C 4-1CQ4J01
nU --H3 l)4JO3ftl)

CcOOrHD -HO fflS-H
OXIOJtB 4JฃC 01X1
o ncuco u -H4Hoin
O-nn-H D4J O<3
D 4J T3 IH X 0) 4J
C CO D IH D CJ CQ
•HD- C3 DCCC-O
rH>rHOl-H OJOD3
CU-HCBCrH 4JOJU-HltH4J
C04J4J-HCL1 0143CU'"I-H
tBtB-iHCQCO O-UtHrHrHn
4)rHft3CO O W-rl O
UcO 43 O-HE4J1-I
nnO43 rH4JT3 CQ
u ^un co 4J>,cn
>4J COO) •4JDDCrHrH
O01iJO>0)C>43Dt8rH
OOinOCCl)-H4-)rH4JCO
COOft -Hg4J COtOU
O CJftCOrHl)tOD>O
-rlrH COCnCUiHrHrl-rl 4-1
4JCOT3 DCOODCOprlU
cj4Jcuncc8cn CTCOCU
3 -H N O U XI -H 01 0) D -n
T3ft-r14J!> T3-4J K*lO
DtBrHO-H'drHDCJC n
HOcOcB4JCl)CBrltB-HCNft
3 tH CJ rH C D ft
CQT>C CUrHOTIE'OlBD
C D ti >1 tH O -H -H -rH D 43
OrHCOntHn-UOl CQC04J •
•HrH i01D T3
cncOi-H> COODicnEOJcu
014-1COO4JO unn3O4J
•H014JUCOOD DftCQCCO
ฃCODOC43olc3Xra-H-H



1B43O Tl D tH CD43
-• — - — - — - ~— - — —
CQ

-------
                                                                 DRAFT
                                                                 OCTOBER 1990
     4,000,000
     3,000,000
to

O
O
"ro
c
m
I-
     2,000,000
     1,000,000
              0    200   400   600   800   1,000  1,200  1,400  1,600

                      Emissions Reduction (tons per year)


     Figure B-3. Least-Cost Envelope for Example 2
                               B.72

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
combustors are designed to combust the fuel  as  completely as  possible  and
therefore reduce PM to the lowest possible level.   Natural  gas  contains  no
solids and solids are removed from the injected water.   The PM  emission  rate
without add-on controls is on the same order (0.009 gr/dscf)  as that  for other
particulate matter sources controlled with stringent add-on controls  (e.g.,
fabric filter).  Since the applicant documented that precombustion or  add-on
controls for PM have never been required for natural gas fired  turbines, the
reviewing agency accepted the applicants analysis  that  natural  gas firing  was
BACT for PM emissions and that no additional analysis of PM controls  was
requi red.

VI.C.  EXAMPLE 3--COMBINED CYCLE GAS TURBINE FIRING DISTILLATE  OIL

   In this example, the same combined cycle gas turbines are proposed
except that distillate oil is fired rather than natural  gas.   The reason is
that natural gas is not available on site and there is  no pipeline within  a
reasonable distance.  The fuel change raises two issues; the technical
feasibility of SCR in gas turbines firing sulfur bearing fuel,  and NOx levels
achievable with water injection while firing fuel  oil.

   In this case the applicant proposed to eliminate SCR as technically
infeasible because sulfur present in the fuel,  even at  low levels, will  poison
the  catalyst and quickly render it ineffective.  The applicant  also noted that
there are no cases in the U.S. where SCR has been applied to a  gas turbine
firing distillate oil as the primary fuel.4

   A second issue would be the most stringent NOx control level achievable
with wet injection.   For oil firing the applicant has proposed 42 ppm at
15 percent oxygen.  Due to flame characteristics inherent with  oil firing,  and
limits on the  amount  of water or steam that can be  injected, 42 ppm is the
lowest NOx emission level achievable with distillate oil firing.  Since
     4 Though this argument was considered persuasive in this case,  advances
in catalyst technology have now made SCR with oil firing technically feasible.
                                     B.73

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
natural  gas Is not available and SCR is technically infeasible,  42 ppm is  the
most stringent alternative considered.   Based on the cost effectiveness of wet
injection, approximately 833 $/ton,  there is no economic basis to eliminate
the 42 ppm option since this cost is well within the range of BACT costs for
NOx control.  Therefore, this option is proposed as BACT.

   The switch to oil  from gas would  also result in S02,  CO,  PM,  and
beryllium emissions above significance  levels.   Therefore, BACT  analyses would
also be required for  these pollutants.   These analyses are not shown in this
example,  but would be performed in the  same manner as the BACT analysis for
NOx.

VI.D.  OTHER CONSIDERATIONS

   The previous judgements concerning economic  feasibility were  in an area
meeting NAAQS for both NOx and ozone.  If the natural gas fired  simple cycle
gas turbine example previously presented were sited adjacent to  a Class I
area, or where air quality improvement  poses a  major challenge,  such as next
to a nonattainment area, the results may differ.  In this case,  even though
the region of the actual site location  is achieving the  NAAQS, adherence to a
local or regional NOx or ozone attainment strategy might result  in the
determination that higher costs than usual  are  appropriate.   In  such
situations, higher costs (e.g., 6,600 $/ton) may not necessarily be persuasive
in eliminating SCR as BACT.

   While it is not the intention of  BACT to prevent construction, it is
possible that local or regional air  quality management concerns  regarding  the
need to minimize the  air quality impacts of new sources  would lead the
permitting authority  to require a source to either achieve stringent emission
control  levels or, at a minimum, that control cost expenditures  meet certain
cost levels without consideration of the resultant economic impact to the
source.

   Besides local or regional air quality concerns, other site constraints
may significantly impact costs of particular control technologies.  For the
                                     B.74

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
examples previously presented,  two factors of concern are land and water
avai1abi1ity.

   The cost of the raw water is usually a small  part of the cost of wet
controls.   However, gas turbines are sometimes located in remote locations.
Though water can obviously be trucked to any location, the costs may be very
high.

   Land availability constraints may occur where a new source is being
located at an  existing plant.  In these cases, unusual design and additional
structural requirements could make the costs of  control technologies which are
commonly affordable prohibitively expensive.  Such considerations may be
pertinent to the calculations of impacts and ultimately the selection of BACT.
                                     B.75

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER C

                           THE AIR QUALITY ANALYSIS
I.   INTRODUCTION

   An applicant for a  PSD permit  is  required  to conduct an air quality
analysis of the ambient impacts  associated  with the construction  and  operation
of the proposed new source or modification.   The main purpose of  the  air
quality analysis is to demonstrate that new emissions emitted from a  proposed
major stationary source or major  modification,  in conjunction with other
applicable emissions increases and decreases  from existing sources (including
secondary emissions from growth  associated  with the new project),  will  not
cause or contribute to a violation of any applicable NAAQS or PSD  increment.
Ambient impacts of noncriteria pollutants must  also be evaluated.

   A separate air quality analysis must be  submitted for each regulated
pollutant if the applicant proposes  to emit the pollutant in a significant
amount from a new major stationary source,  or proposes to cause a  significant
net emissions increase from a major  modification (see Table I-A-4,  chapter A
of this part).   [JVote: The air quality analysis requirement also  applies to
any pollutant whose rate of emissions from a proposed new or modified source
is considered to be "significant" because the proposed source would construct
within 10 kilometers of a Class I area and would have an ambient impact on
such area equal to or greater than 1 ug/m3, 24-hour average.]   Regulated
pollutants include (1) pollutants for which a NAAQS exists (criteria
pollutants) and (2) other pollutants, which are regulated by EPA,  for which no
NAAQS exist (noncriteria pollutants).

   Each air quality analysis will be unique,  due to the variety of sources and
meteorological  and topographical  conditions that may be involved.
Nevertheless, the air  quality analysis must be  accomplished in a  manner
consistent with the requirements  set forth  in either EPA's PSD regulations
under 40 CFR 52.21, or a State or local PSD program approved by EPA pursuant
to 40 CFR 51.166.  Generally, the analysis  will involve (1) an assessment of
existing air quality,  which may  include ambient monitoring data and air
                                      C.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
quality dispersion modeling results,  and (2)  predictions,  using dispersion
modeling,  of ambient concentrations that will  result from the applicant's
proposed project and future growth associated  with the project.

   In describing the various concepts and procedures involved with the air
quality analysis in this section,  it is assumed that the reader  has a basic
understanding of the principles involved in collecting and analyzing ambient
monitoring data and in performing  air dispersion modeling.   Considerable
guidance is contained in EPA's Ambient Monitoring Guidelines for Prevention of
Significant Deterioration [Reference 1] and Guideline on Air Quality Models
(Revi sed)  [Reference 2] .  Numerous times throughout this chapter, the reader
will  be referred to these guidance documents,  hereafter referred to as the PSD
Monitoring Guideline and the Modeling Guideline,  respectively.

   In addition, because of the complex character of the air quality analysis
and the site-specific nature of the modeling techniques involved, applicants
are advised to review the details  of their proposed modeling analysis with the
appropriate reviewing agency before a complete PSD application is submitted.
This is best done using a modeling protocol.  The modeling protocol should be
submitted to the reviewing agency  for review and approval prior to commencing
any extensive analysis.  Further description of the modeling protocol is
contained in this chapter.

   The PSD applicant should also be aware that, while this chapter focuses
primarily on compliance with the NAAQS and PSD increments, additional impact
analyses are required under separate provisions of the  PSD regulations for
determining any impairment to visibility, soils and vegetation that might
result, as well as any adverse impacts to Class I areas.  These provisions are
described in the following chapters D and E, respectively.
                                      C.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.  NATIONAL AMBIENT AIR QUALITY STANDARDS AND PSD INCREMENTS
   As described in the introduction to this chapter,  the air quality analysis
is designed to protect the national ambient air quality standards (NAAQS)  and
PSD increments.  The NAAQS are maximum concentration  "ceilings" measured in
terms of the total concentration of a pollutant in the atmosphere (See Table
C-l).   For  a  new  or  modified  source,  compliance with any  NAAQS  is based  upon
the total  estimated air quality, which is the sum of  the ambient estimates
resulting from existing sources of air pollution  (modeled source impacts plus
measured background concentrations, as described  in this section) and the
modeled ambient impact caused by the applicant's  proposed emissions  increase
(or net emissions increase for a modification) and associated growth.
   A PSD increment, on the other hand, is the maximum allowable increase in
concentration that is allowed to occur above a baseline concentration for  a
pollutant (see section II.E).  The baseline concentration is defined for each
pollutant (and relevant averaging time) and, in general, is the ambient
concentration existing at the time that the first complete PSD permit
application affecting the area is submitted.  Significant deterioration is
said to occur when the amount of new pollution would  exceed the applicable PSD
increment.   It is important to note, however, that the air quality  cannot
deteriorate beyond the concentration allowed by the applicable NAAQS, even if
not all of the PSD increment is consumed.

II.A  CLASS I, II, AND III AREAS AND INCREMENTS.

   The PSD requirements provide for a system of area  classifications which
affords States an opportunity to identify local land  use goals.  There are
three area classifications.  Each classification  differs in terms of the
amount of growth it will  permit before significant air quality deterioration
would be deemed to occur.  Class I areas have the smallest increments and  thus
allow only a small degree of air quality deterioration.  Class II areas can
                                     C.3

-------
                                                                      DRAFT
                                                                      OCTOBER 1990
               TABLE C-l.   National Ambient  Air Quality  Standards
                                       Primary             Secondary
   Pollutant/averaging time           Standard            Standard
Particulate  Matter

o PM10> annual3                      50  |jg/m3              50 pg/m3
o PM10',  24-hourb                    150  |jg/m3            150 pg/m3

Sulfur  Dioxide

o S02, annual0                      80  pg/m3  (0.03 ppm)

o S02, 24-hourd
 365  pg/m3 (0.14  ppm)
o S02, 3-hourd                                           1,300 pg/m3  (0.5  ppm)

Nitrogen  Dioxide

o N02i annual0                      0.053 ppm (100  |jg/m30.053 ppm (100  pg/m3)

Ozone

o 03,   l-hourb                     0.12  ppm (235 (jg/m3)0.12 ppm  (235 pg/m3)

Carbon  Monoxide

o CO,   8-hourd                     9  ppm (10 mg/m3)

o CO,   l-hourd                     35  ppm (40 mg/m3)

Lead

o Pb,   calendar quarter0   1.5 pg/m3
                                       3
a Standard is attained when the expected annual arithmetic  mean is less than
  or equal to 50  pg/m3.
b Standard is attained when the expected number of exceedances is  less than or
  equal to 1.
c Never to be exceeded.
d Not to be exceeded more than once per year.
                                        C.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
accommodate normal  well-managed  industrial  growth.   Class  III  areas  have  the
largest increments  and thereby provide for  a  larger amount of  development than
either Class I  or Class  II  areas.

   Congress established  certain  areas, e.g.,  wilderness  areas  and  national
parks, as mandatory Class I areas.   These areas  cannot be  redesignated to any
other area classification.   All  other  areas of the  country were initially
designated as Class II.   Procedures  exist under  the PSD  regulations  to
redesignate the Class  II  areas to  either Class I  or Class  III,  depending  upon
a State's land  management objectives.

   PSD increments for  S02 and  particulate matter—measured  as total suspended
particulate (TSP)--have  existed  in  their present  form since 1978.  On  July  1,
1987, EPA revised the  NAAQS for  particulate matter  and established the new  PM-
10 indicator by which  the NAAQS  are  to be measured.  (Since each State is
required to adopt these  revised  NAAQS  and related implementation requirements
as part of the  approved  implementation plan,  PSD  applicants should check  with
the appropriate permitting  agency  to determine whether such State  action  has
already been taken.  Where  the PM-10 NAAQS  are not  yet being implemented,
compliance with the TSP-based ambient  standards  is  still  required  in
accordance with the currently-approved State  implementation plan.)
Simultaneously  with the  promulgation of the PM-10 NAAQS,  EPA announced that  it
would develop PM-10 increments to  replace the TSP increments.   Such  new
increments have not yet  been promulgated,  however.   Thus  the national  PSD
increment system for particulate matter is  still  based on  the  TSP  indicator.
   The EPA promulgated PSD  increments  for N02  on  October 17, 1988.  These new
increments become effective under  EPA's PSD regulations  (40 CFR 52.21) on
November 19, 1990,  although States  may have revised their  own  PSD  programs  to
incorporate the new increments for  N02 on some earlier date.  Until
November 19, 1990,  PSD applicants  should determine  whether the  N02 increments
are being implemented  in  the area  of concern;  if  so,  they  must  include the
necessary analysis, if applicable,  as  part  of a  complete  permit application.
[NOTE:  the "trigger date"  (described  below in section II.B) for the  N02
increments has  been established  by  regulation as  of February 8, 1988.   This
applies to all  State PSD  programs  as well  as  EPA's  Part  52 PSD  program.  Thus,
                                      C.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
consumption of the N02  increments may actually occur before  the  increments
become effective in any particular  PSD  program.]   The  PSD increments for  S02,
TSP and N02 are  summarized  in Table C-2.

II.B  ESTABLISHING THE BASELINE DATE

   As already described, the baseline concentration is the reference point for
determining air quality deterioration in an area.    The baseline concentration
is essentially the air quality  existing at the time of the first complete PSD
permit application submittal affecting  that area.   In  general, then, the
submittal  date of the first complete PSD application in an area  is the
"baseline date."  On or before  the  date of the first PSD application, most
emissions are considered to be  part of  the baseline concentration, and
emissions changes which occur after that date affect the amount  of available
PSD increment.  However, to fully understand how and when increment is
consumed or expanded, three different dates related to baseline  must be
explained.  In chronological order,  these dates are as follows:

   • the major source baseline  date;
   • the trigger date;  and
   • the minor source baseline  date.

   The major source baseline date is the date after which actual emissions
associated with construction (i.e., physical changes or changes  in the method
of operation) at a major stationary source affect the available  PSD increment.
Other changes in actual emissions occurring at any source after  the major
source baseline date do not affect the increment, but instead (until after the
minor source baseline date is established) contribute to the baseline
concentration.  The trigger date is the date after which the minor source
                                      C.6

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
                          TABLE C-2.   PSD  INCREMENTS
                                    (M9/m3)
                    Class I
              Class  II
                  Class III
Sulfur Dioxide
0
0
0
Parti
0
0
S02
S02
S02
cul
TSP
TSP
, annual3
, 24-hourb
3-hourb
ate Matter
, annual3
, 24-hourb
2
5
25

5
10
20
91
512

19
37
40
182
700

37
75
Nitrogen Dioxide
   o N02,  annual3
2.5
25
50
a Never to be exceeded.
b Not to be exceeded more than once  per  year.
                                      C.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

baseline date (described below)  may be established.   Both the major source
baseline date and the trigger date are fixed  dates,  although  different dates
apply to (1)  S02  and  particulate matter, and  (2) N02, as follows:
   Pol 1 utant	Major Source Baseline Date
   Trigger Date
      PM              January 6, 1975 August 7, 1977
      S02              January 6, 1975 August 7, 1977
      N02              February 8, 1988                     February 8, 1988
   The minor source baseline date is the earliest date after the trigger date
on which a complete PSD application is received by the permit reviewing
agency.  If the application that established the minor source baseline date is
ultimately denied or is voluntarily withdrawn by the applicant, the minor
source baseline date remains in effect nevertheless.  Because the date marks
the point in time after which actual emissions changes from al1 sources affect
the available increment (regardless of whether the emissions changes are a
result of construction), it is often referred to as the "baseline date."

   The minor source baseline date for a particular pollutant is triggered by a
PSD applicant only if the proposed increase in emissions of that pollutant is
significant.  For instance, a PSD application for a major new source or
modification that proposes to increase its emissions in a significant amount
for S02,  but in  an insignificant amount for PM,  will  establish  the  minor
source baseline date for S02 but not for PM.   Thus,  the minor source baseline
dates for different pollutants  (for which increments exist) need not be the
same in a particular area.
                                      C.8

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
II.C   ESTABLISHING THE  BASELINE  AREA
   The area in which the minor  source  baseline date is established by  a  PSD
permit application is known  as  the  baseline area.  The extent of a baseline
area is limited to intrastate areas and may include one or more areas
designated as attainment or  unclassified under Section 107 of the Act.   The
baseline area established  pursuant  to  a specific PSD application is to include
1) all portions of the attainment or unclassifiable area in which the  PSD
applicant would propose to locate,  amd 2)  any attainment or unclassifiable
area in which the proposed emissions would have  a significant ambient  impact.
For this purpose, a significant impact is  defined as at least a 1 pg/m3 annual
increase in the average annual  concentration of  the applicable pollutant.
Again, a PSD applicant's establishment of  a baseline area in one State does
not trigger the minor source baseline  date in, or extend the baseline  area
into, another State.

II.D  REDEFINING BASELINE  AREAS (AREA  REDESIGNATIONS)

   It is possible that the boundaries  of a baseline area may not reasonably
reflect the area affected  by the PSD source which established the baseline
area.  A state may redefine  the boundaries of an existing baseline area  by
redesignating the section  107 areas contained therein.  Section 107(d) of the
Clean Air Act specifically authorizes  states to  submit redesignations  to the
EPA.  Consequently, a State  may submit redefinitions of the boundaries of
attainment or unclassifiable areas  at  any  time,  as long as the following
criteria are met:

   •area redesignations can be no smaller than the 1 uglnf area of
   impact of the triggering source;  and
   • the boundaries of any redesignated  area cannot intersect the
   1 ug/nf area of impact of any  major stationary source that
   established or would have established  a minor  source  baseline date
   for the area proposed for redesignation.
                                      C.9

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
II.E  INCREMENT CONSUMPTION AND EXPANSION
   The amount of PSD increment that has  been  consumed  in  a  PSD area is
determined from the emissions increases  and decreases  which have occurred from
sources since the applicable baseline date.   It  is  useful  to note,  however,
that in order to determine the amount of PSD  increment consumed (or the amount
of available increment), no determination  of  the baseline concentration needs
to be made.  Instead, increment consumption calculations  must reflect only the
ambient pollutant concentration change attributable to increment-affecting
emi ssions.

   Emissions increases that consume a portion of the applicable increment are,
in general, all those not accounted for  in the baseline concentration and
specifically include:

   •  actual emissions  increases  occurring  after  the major  source  baseline date,
   which   are   associated  with   physical   changes   or   changes   in  the  method   of
   operation (i.e., construction) at a  major stationary  source;  and
   •actual emissions  increases at any stationary source,  area source,  or
   mobile source occurring after the minor source  baseline  date.

   The amount of available  increment  may be added to,  or "expanded," in two
ways.  The primary way is through  the reduction  of  actual emissions from any
source after the minor source baseline date.   Any such emissions reduction
would increase the amount of available increment to the extent that ambient
concentrations would be  reduced.

   Increment expansion may  also result from the reduction of actual emissions
after the major source baseline date, but before the minor source baseline
date, if the reduction results from a physical change or change in the method
of operation (i.e.,  construction)  at  a major  stationary source.  Moreover, the
reduction will add to the available increment only  if the reduction is
included in a  federally  enforceable permit or SIP provision.  Thus, for major
stationary sources,  actual  emissions  reductions made prior to the minor source
baseline date  expand the available increment  just as increases before the
minor source baseline date  consume increment.
                                      C.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
   The creditable increase of an existing stack height or the application  of
any other creditable dispersion technique may affect increment consumption or
expansion in the same manner as an actual emissions increase or decrease.
That is,  the effects that a change in the effective stack height would have on
ground level pollutant concentrations generally should be factored into the
increment analysis.   For example, this would apply to a raised stack height
occurring in conjunction with a modification at a major stationary source
prior to the minor source baseline date,  or to any changed stack height
occurring after the minor source baseline date.  It should be noted, however,
that any increase in a stack height,  in order to be creditable, must be
consistent with the EPA's stack height regulations; credit cannot be given for
that portion of the new height which  exceeds the height demonstrated to be the
good engineering practice (GEP) stack height.

   Increment consumption (and expansion)  will generally be based on changes in
actual emissions reflected by the normal  source operation for a period of  2
years.  However, if little or no operating data are available, as in the case
of permitted emission units not yet in operation at the time of the increment
analysis, the potential to emit must  be used instead.  Emissions data
requirements for modeling increment consumption are described in
Section IV.D.4.   Further guidance for identifying increment-consuming sources
(and emissions) is provided in Section IV.C.2.
                                     C.ll

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.F  BASELINE DATE AND BASELINE AREA CONCEPTS --  EXAMPLES
   An example of how a baseline area  is established is illustrated in Figure
C-l.  A major  new  source with the potential to emit significant amounts of  S02
proposes  to locate in County C.  The  applicant submits a  complete PSD
application to the appropriate  reviewing agency  on October 6,  1978.   (The
trigger date for S02  is August  7, 1977.)   A  review of  the  State's S02
attainment designations reveals that  attainment  status is listed  by  individual
counties  in the state.  Since County  C is designated  attainment for  S02,  and
the source proposes to locate there,  October  6,  1978  is established  as the
minor source baseline date for  S02 for  the entire  county.

   Dispersion modeling of  proposed  S02  emissions in accordance  with  approved
methods reveals that the  proposed source's ambient impact will  exceed 1 ug/m3
(annual  average) in Counties A  and  B.   Thus,  the same minor source baseline
date is also established  throughout  Counties  A and B.  Once it is triggered,
the minor source baseline  date  for  Counties  A, B and  C establishes the time
after which all emissions  changes affect the  available increments in those
three counties.

   Although S02 impacts due  to  the proposed emissions are above the
significance level of 1 pg/m3 (annual  average) in  the adjoining State,  the
proposed source does not  establish  the minor  source baseline date in that
State.   This is because,  as mentioned in Section II.C of this chapter,
baseline areas are intrastate areas  only.

   The fact that a PSD source's emissions cannot trigger the minor source
baseline date across a State's  boundary should not be interpreted as
precluding the applicant's emissions from consuming increment in another
State.   Such increment-consuming emissions (e.g.,  S02 emissions increases
resulting from a physical  change or a change in the method of operation at a
                                     C.12

-------
                                                        DRAFT
                                                        OCTOBER 1990
                                           County D
                                          Attainment
       Baseline Date Triggered 10/6/78
       State line
       County line
Figure C-1.  Establishing the Baseline Area.
                        C.13

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
major stationary source after January 6,  1975) that affect another State will
consume increment there even though the minor source baseline date has not
been triggered, but are not considered for increment-consuming purposes until
after the minor source baseline date has  been independently established in
that State.             A  second example,  illustrated  in  Figure C-2,
demonstrates how a baseline area may be redefined.   Assume that the State in
the first example decides that it does not want the minor source baseline date
to be established in the western half of  County A where the proposed source
will not have a significant annual  impact (i.e., 1  (jg/m3,  annual  average).
The State, therefore, proposes to redesignate the boundaries of the existing
section 107 attainment area, comprising all of County A, to create two
separate attainment areas in that county.  If EPA agrees that the available
data support the change, the redesignations will be approved.  At that time,
the October 6, 1978 minor source baseline date will no longer apply to the
newly-established attainment area comprising the western portion of County A.

   If the minor source baseline date has  not been triggered by another PSD
application having a significant impact in the redesignated western portion of
County A, the S02 emissions changes occurring after October 6,  1978  from minor
point, area, and mobile sources, and from nonconstruction-related activities
at all major stationary sources in this area will be transferred into the
baseline concentration.  In accordance with the major source baseline date,
construction-related emissions changes at major point sources continue to
consume or expand increment in the westerm poriton of County A which is no
longer part of the original baseline area.
                                     C.14

-------
                                                      DRAFT
   Redesignated Attainment Areas
                          County E   ^
                        Unclassified .•
                                .*.....
   ^^B Baseline Date Triggered 10/6/78

   ~ • ~ • State line
   	 County line
                                        County D
                                        Attainment
Figure C-2.  Redefining the Baseline Area.
                        C.15

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.   AMBIENT DATA REQUIREMENTS
   An applicant should be aware of the  potential  need to establish  and  operate
a site-specific monitoring network for  the collection of certain  ambient data.
With respect to air quality data,  the PSD regulations contain  provisions
requiring an applicant to provide  an ambient air  quality analysis which may
include pre-application monitoring data,  and in some instances post-
construction monitoring data,  for  any pollutant proposed to  be emitted  by the
new source or modification.   In the absence of available monitoring data which
is representative of the area  of concern, this requirement could  involve the
operation of a site-specific air quality  monitoring network  by the  applicant.
Also, the need for meteorological  data,  for any dispersion modeling that must
be performed, could entail the applicant's operation of a site-specific
meteorological network.

   Pre-application data generally  must  be gathered over a period  of at  least 1
year and the data are to represent at least the 12-month period immediately
preceding receipt of the PSD application.  Consequently, it  is important that
the applicant ascertain the need to collect any such data and  proceed with the
required monitoring activities as  soon  as possible in order  to avoid undue
delay in submitting a complete PSD application.

III.A  PRE-APPLICATION AIR QUALITY MONITORING

   For any criteria pollutant that the  applicant proposes to emit in
significant amounts, continuous ambient monitoring data may be required as
part of the air quality analysis.   If,  however, either (1) the predicted
ambient impact, i.e., the highest modeled concentration for the applicable
averaging time, caused by the proposed  significant emissions increase (or
significant net emissions increase), or  (2) the existing ambient pollutant
concentrations are less than the prescribed significant monitoring  value (see
Table C-3),  the permitting agency has  discretionary authority to exempt  an
applicant from this data  requirement.
                                     C.16

-------
                                                                             DRAFT
                                                                             OCTOBER 1990
                 TABLE C-3.   SIGNIFICANT MONITORING CONCENTRATIONS
Pollutant
Air  Quality Concentration  (yg/m3)
       and  Averaging Time
Carbon monoxide
Nitrogen dioxide
Sulfur dioxide
Particulate Matter, TSP
Particulate Matter, PM-10
Ozone
Lead
Asbestos
Beryl 1 ium
Mercury
Vinyl chloride
Fl uorides
Sulfuric acid mist
Total reduced sulfur (including H2S)
Reduced sulfur (including H2S)
Hydrogen sulfide
575
14
13
10
10
a
0.
b
0
0
15
0
b
b
b
0
(8-hour)
(Annual )
(24-hour)
(24-hour)
(24-hour)

1 (3-month)

.001(24-hour)
.25 (24-hour)
(24-hour)
.25 (24-hour)



.2 (1-hour)
a  No significant  air quality  concentration for  ozone monitoring  has been established.  Instead,
applicants with a net emissions increase of 100 tons/year or more of VOC's subject to  PSD  would
be required to perform an ambient impact analysis,  including pre-application monitoring data.
b Acceptable  monitoring techniques may not  be available at  this time.
for this pollutant should be discussed with the permitting  agency.
                      Monitoring  requirements
                                           C.17

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      The determination of the proposed project's  effects  on  air quality  (for
comparison with the significant monitoring value)  is  based on the results  of
the dispersion modeling used for establishing the  impact area (see Section
IV.B of this chapter).   Modeling by itself or in conjunction  with available
monitoring data should  be used to determine whether the existing ambient
concentrations are equal  to or greater than the significant monitoring value.
The applicant may utilize a screening technique for this purpose, or may  elect
to use a refined model.  Consultation with the permitting  agency is advised
before any model is selected.   Ambient impacts from existing  sources are
estimated using the same model input data as are used for  the NAAQS analysis,
as described in section IV.D.4 of this chapter.

      If a potential  threat to the NAAQS is identified by  the modeling
predictions, then continuous ambient monitoring data  should be required,  even
when the predicted impact of the proposed project  is  less  than the significant
monitoring value.  This is especially important when  the modeled impacts  of
existing sources are uncertain due to factors such as complex terrain and
uncertain emissions estimates.

      Also, if the location of the proposed source or modification is not
affected by other major stationary point sources,  the assessment of existing
ambient concentrations  may be done by evaluating available monitoring data.
It is generally preferable to use data collected within the area of concern;
however, the possibility of using measured concentrations  from representative
"regional" sites may be discussed with the permitting agency.  The
PSD Monitoring Guideline provides additional guidance on the  use of  such
regional sites.

      Once a determination is made by the permitting agency that ambient
monitoring data must be submitted as part of the PSD application, the
requirement can be satisfied  in one of two ways.  First,  under certain
conditions, the applicant may use existing ambient data.  To be  acceptable,
such data must  be judged by the permitting agency to be representative of the
air quality for the area in which the proposed project would construct and
operate.  Although a State or local agency may have monitored air quality for
                                     C.18

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
several years, the data collected by such efforts may not necessarily  be
adequate for the preconstruction analysis required under PSD.   In  determining
the representativeness of any existing data, the applicant  and  the permitting
agency must consider the following critical items (described  further  in the
PSD Monitoring Guideline):

      •     monitor location;
      •     quality of the data; and
      •     currentness of the data.

      If existing data are not available, or they are judged  not to be
representative, then the applicant must proceed to establish  a  site-specific
monitoring network.  The EPA strongly recommends that the applicant prepare a
monitoring plan before any actual monitoring begins.  Some  permitting  agencies
may require that such a plan be submitted to them for review  and approval.  In
any case, the applicant will want to avoid any possibility  that the resulting
data are unacceptable because of such things as improperly  located monitors,
or an inadequate number of monitors.  To assure the accuracy  and precision of
the data collected, proper quality assurance procedures pursuant to Appendix B
of 40 CFR Part 58 must  also be  followed.  The  recommended  minimum  contents  of
a monitoring plan, and a discussion of the various considerations  to  be made
in designing a PSD monitoring network, are contained in the PSD Monitoring
Guideline.

      The PSD regulations generally require that the applicant  collect 1  year
of ambient data (EPA recommends 80 percent data recovery for  PSD purposes).
However, the permitting agency has discretion to accept data  collected over a
shorter  period of time (but  in no case less than 4 months)  if a complete  and
adequate analysis can be accomplished with the resulting data.  Any decision
to approve a monitoring period shorter than 1 year should be  based on  a
demonstration by the applicant (through historical data or  dispersion
modeling) that the required  air quality data will be obtained during  a time
period,  or periods, when maximum ambient concentrations can be  expected.
                                     C.19

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
      For a pollutant for which there  Is  no  NAAQS  (i.e.,  a  noncriteria
pollutant), EPA's general position  is  not  require  monitoring  data,  but to base
the air quality analysis on modeled  impacts.   However,  the  permitting agency
may elect to require the submittal  of  air  quality  monitoring  data for
noncriteria pollutants in certain cases,  such  as where:

      •     a State has a standard for a non-cnteria pollutant;
      •     the reliability of emissions data used as input to modeling
            existing sources  is highly questionable;  and
      •     available models  or complex terrain make it difficult to
                  estimate  air   quality  or   the   impact  of   the   proposed  or
            modification.

The applicant will need to confer with the permitting  agency  to determine
whether any ambient  monitoring may  be  required.  Before the agency exercises
its discretion to require  such monitoring, there should be  an acceptable
measurement method approved by EPA  or  the  appropriate  permitting agency.

      With regard to particulate matter,  where two different  indicators of the
pollutant are being  regulated, EPA  considers the PM-10  indicator to represent
the criteria form of the pollutant  (the NAAQS are  now  expressed in terms of
ambient PM-10 concentrations)  and TSP  is  viewed as the  non-criteria form.
Consequently,  EPA intends  to  apply  the pre-application  monitoring requirements
to PM-10 primarily,  while  treating  TSP on  a discretionary basis in light of
its noncriteria status.  Although the  PSD increments for particulate matter
are still based on the TSP indicator,  modeling data, not ambient monitoring
data, are used for increment  analyses.

      Ambient  air quality  data collected  by the applicant must be presented in
the PSD application  as part of the  air quality analysis.  Monitoring data
collected for  a criteria pollutant  may be used in  conjunction with dispersion
modeling results  to  demonstrate  NAAQS  compliance.   Each PSD application
involves its own  unique  set of factors, i.e., the  integration of measured
ambient data and  modeled projections.   Consequently, the amount of data to be
                                      C.20

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
used and the manner of presentation are matters that should be discussed with
the permitting agency.

III.B  POST-CONSTRUCTION AIR QUALITY MONITORING

      The PSD Monitoring Guideline recommends that post-construction
monitoring be done when there is a valid reason,  such as (1) when the NAAQS
are threatened, and (2) when there are uncertainties in the data bases for
modeling.  Any decision to require post-construction monitoring will generally
be made after the PSD application has been thoroughly reviewed.  It should be
noted that the PSD regulations do not require that the significant monitoring
concentrations be considered by the permitting agency in determining the need
for post-construction monitoring.

      Existing monitors can be considered for collecting post-construction
ambient data as long as they have been approved for PSD monitoring purposes.
However, the location of the monitors should be checked to ascertain their
appropriateness if other new sources or modifications have subsequently
occurred, because the new emissions from the more recent projects could alter
the location of points of maximum ambient concentrations where ambient
measurements need to be made.

      Generally, post-construction monitoring should not begin until the
source is operating near intended capacity.   If possible the collection of
data should be delayed until the source is operating at a rate equal to or
greater than 50 percent of design capacity.   The PSD Monitoring Guideline
provides, however, that in no case should post-construction monitoring be
delayed later than 2 years after the start-up of the new source or
modification.

      Post-approval ozone monitoring is an alternative to pre-application
monitoring for applicants proposing to emit  VOC's if they choose to accept
nonattainment preconstruction review requirements, including LAER, emissions
and air quality offsets, and statewide compliance of other sources under the
same ownership.  As indicated in Table C-3,  pre-application monitoring for
                                     C.21

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
ozone is required when the proposed source or modification would emit at least
100 tons per year of volatile organic compounds (VOC).   Note that this
emissions rate for VOC emissions is a surrogate for the significant monitoring
concentration for the pollutant ozone (see Table C-3].   Under
40 CFR 52.21(m)(1)(vi),  post-approval monitoring data for ozone is required
(and cannot be waived) in conjunction with the aforementioned nonattainment
review requirements  when the permitting agency waives the requirement for pre-
application ozone monitoring data.  The post-approval period may begin any
time after the source receives its PSD permit.  In no case should the post-
approval monitoring  be started later than 2 years after the start-up of the
new source or modification.

III.C  METEOROLOGICAL MONITORING

      Meteorological data is generally needed for model input as part of the
air quality analysis.  It is important that such data be representative of the
atmospheric dispersion and climatological conditions at the site of the
proposed source or modification, and at locations where the source may have a
significant impact on air quality.  For this reason, site specific data are
preferable to data collected elsewhere.  On-site meteorological monitoring may
be required, even when on-site air quality monitoring is not.

      The PSD Monitoring Guideline should be used to establish locations  for
any meteorological monitoring network that the applicant may be required to
operate and maintain as part of the preconstruction monitoring requirements.
That guidance specifies the meteorological instrumentation to be used in
measuring meteorological parameters such as wind speed, wind direction, and
temperature.  The PSD Monitoring Guideline also provides  that the retrieval
of valid wind/stability data should not fall below 90 percent on an annual
basis.  The type, quantity, and format of the required data will be influenced
by the  specific input requirements of the dispersion modeling techniques used
in the  air quality  analysis.  Therefore, the applicant will need to consult
with the permitting  agency prior to establishing the required network.
                                     C.22

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
      Additional guidance for the collection and use of on-site  data  is
provided in the PSD Monitoring Guideline.  Also, the EPA documents  entitled
On-Site Meteorological Program Guidance for Regulatory Modeling  Applications
(Reference 3), and Volume IV of the series of reports entitled  Quality
Assurance Handbook for Air Pollution Measurement Systems  (Reference 4),
contain information required to ensure the quality of the meteorological
measurements collected.
                                     C.23

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
IV.   DISPERSION MODELING ANALYSIS
      Dispersion models are the primary  tools  used  in  the air quality
analysis. These models estimate the  ambient  concentrations that will result
from the PSD applicant's proposed emissions  in  combination with emissions from
existing sources.  The estimated total concentrations  are used to demonstrate
compliance with any applicable NAAQS or  PSD  increments.   The applicant should
consult with the permitting agency to determine the particular requirements
for the modeling analysis to assure  acceptability  of any air quality modeling
technique(s) used to perform the air quality analysis  contained in the PSD
applicati on.

IV.A  OVERVIEW OF THE DISPERSION MODELING  ANALYSIS

      The dispersion modeling analysis usually  involves  two distinct phases:
(1) a preliminary analysis and (2) a full  impact analysis.  The preliminary
analysis models only the signifi cant increase  in potential emissions of a
pollutant from a proposed new source, or the significant net emissions
increase of a pollutant from a proposed  modification.   The results of this
preliminary analysis determine whether the applicant must perform a full
impact analysis, involving the estimation  of background  pollutant
concentrations resulting from existing sources  and  growth associated with the
proposed source.  Specifically, the  preliminary analysis:

      •     determines whether the applicant  can forego further  air quality
            analyses for a particular pollutant;
      •     may allow the applicant to be exempted from the ambient monitoring
            data  requirements  (described in section III of  this  chapter);  and
      •     is used to define  the impact area within  which a full impact
            analysis must be carried out.

      The EPA does  not require a full  impact analysis for a particular
pollutant when emissions of that pollutant from a proposed source or
modification would  not increase ambient  concentrations by more than prescribed
significant ambient impact  levels, including special Class I significance

                                      C.24

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
levels.  However, the applicant should  check  any  applicable  State or local  PSD
program requirements in order to determine whether  such  requirements may
contain any different procedures which  may be more  stringent.   In addition,
the applicant must still address the  requirements for  additional  impacts
required under separate PSD requirements, as  described in  Chapters D and E
which follow this chapter.

      A fall impact analysis is required  for  any  pollutant for which the
proposed source's estimated ambient pollutant concentrations exceed prescribed
significant ambient impact levels.  This  analysis expands  the  preliminary
analysis in that it considers emissions from:

      •     the proposed source;
      •     existing sources;
      •     residential, commercial, and industrial growth that accompanies
            the new activity at the new source or modification (i.e..
            secondary emissions).

For S02,  particulate matter,  and N02,  the  full impact analysis actually
consists of separate analyses for the NAAQS and PSD increments.   As described
later in this section, the selection  of background  sources (and  accompanying
emissions) to be modeled for the NAAQS  and increment  components  of the overall
analysis proceeds under somewhat different sets of  criteria.  In  general,
however, the full impact analysis is  used to  project  ambient pollutant
concentrations against which the applicable NAAQS and  PSD  increments are
compared, and to assess the ambient impact of non-criteria pollutants.

      The reviewer's primary role is  to determine whether  the  applicant select
ed the appropriate model(s), used appropriate input data,  and  followed
recommended procedures to complete the  air quality  analysis.  Appendix C in
the Modeling Guideline provides an example checklist which recommends a
standardized set of data to aid the reviewer  in determining  the  completeness
and correctness of an applicant's air quality analysis.
                                      C.25

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Figure C-3 outlines the basic steps for an applicant to follow for a PSD
dispersion modeling analysis to demonstrate compliance with the NAAQS and  PSD
increments.  These steps are described in  further detail  in the sections which
follow.

IV.B  DETERMINING THE IMPACT AREA

      The proposed project's impact area is the geographical  area for which
the required air quality analyses for the  NAAQS and PSD increments are carried
out.  This area includes all locations where the significant increase in  the
potential emissions of a pollutant from a  new source,  or  significant net
emissions increase from a  modification, will cause a significant ambient
impact (i.e., equal or exceed the applicable significant  ambient impact level,
as shown in Table C-4).   The  highest modeled  pollutant  concentration for each
averaging time is used to  determine whether the source will have a significant
ambient impact for that pollutant.

      The impact area is a circular area with a radius extending from the
source to (1) the most distant point where approved dispersion modeling
predicts a significant ambient impact will occur, or (2)  a modeling receptor
distance of 50 km, whichever is less.  Usually the area of modeled significant
impact does not have a continuous, smooth border.  (It may actually be
comprised of pockets of significant impact separated by pockets of
insignificant impact.)   Nevertheless, the required air quality analysis is
carried out within the circle that circumscribes the significant ambient
impacts, as shown in Figure C-4.

       Initially, for each pollutant subject to review an  impact area is
determined for every averaging time.  The impact area used for the air quality
analysis of a particular pollutant is the largest of the areas determined for
that pollutant.  For example, modeling the proposed S02 emissions from a new
source might show that  a significant ambient S02 impact occurs out to a
distance from the source of 2 kilometers  for the annual averaging period;
                                     C.26

-------
                                                                                         DRAFT
                                                                                                    IQQfl
ra   u>
   '
aป  c
   <
         Meteorological Data
          Source Input Data
  a.
  E
 u_
I
                                      Pollutant Emitted in
                                      Significant Amounts
          Meteorological Data
          Source Input Data
                                       Determine Need for
                                         Pre-application
                                           Monitonng
                                             Jf-
                                            Determine
                                          Impact Area
                                             >p Emissio
                                        Develop E
                                       	Inventory
                                         Model Impact of
                                      Proposed, Existing, and
                                       Secondary Emissions
  Add Monitored
Background Levels
(for NAAQS only)
 Demonstration of
   Compliance
    Ambient
  Concentrations
 Above Air Quality
   Significance
      Level
No Further NAAQS or
PSD Increment Analysis
Required for Pollutant
           Figure l-C-3. Basic Steps in the Air Quality Analysis
                             (NAAQS and PSD Increments)
                                        C.27

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                 TABLE C-4.


        SIGNIFICANCE LEVELS FOR AIR QUALITY IMPACTS IN CLASS II AREAS3
Pollutant         Annual       24-hour        8-hour      3-hour      1-hour
S02                  1            5                          25
TSP
PM-10
NO,
CO                  -            -              500      -            2,000
a   This  table  does  not  apply  to  Class  I  areas.   If  a  proposed  source  is
located within 100 kilometers of a Class I area, an impact of 1 pg/m3 on  a
24-hour basis is significant.

-   No significant  ambient impact concentration  has  been  established.   Instead,
  any net emissions increase of 100 tons per year of VOC subject to  PSD would
 be  required to perform an ambient impact analysis.
                                     C.28

-------
                                                  DRAFT
                                                  OCTOBER 1990
                Impact Area
 - • — • State line
      County line
Figure C-4.  Determining the Impact Area.
                      C.29

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
4.3 kilometers for the 24-hour averaging period;  and  3.8 kilometers  for  the  3-
hour period.  Therefore,  an impact area  with  a  radius of 4.3  kilometers  from
the proposed source is selected for the  S02 air quality  analysis.

      In the event that the maximum ambient  impact  of a  proposed emissions
increase is below the appropriate ambient air quality significance level  for
all locations and averaging times, a full impact  analysis for that pollutant
is not required by EPA.  Consequently,  a preliminary  analysis which  predicts
an insignificant ambient impact everywhere is accepted by EPA as the required
air quality analysis (NAAQS and PSD increments)  for that pollutant.   [NOTE:
While it may be shown that no impact area exists for a particular pollutant,
the PSD application (assuming it is the first one in the area) still
establishes the PSD baseline area and minor source baseline date in the
section 107 attainment or unclassifiable area where the source will be
located, regardless of its insignificant ambient impact.]

      For each applicable pollutant, the determination of an  impact area must
include all stack emissions and quantifiable fugitive emissions resulting from
the proposed source.  For a proposed modification,  the determination includes
contemporaneous emissions increases and decreases,  with  emissions decreases
input as negative emissions in the model.  The EPA allows for the exclusion  of
temporary emissions (e.g., emissions occurring during the construction phase
of a project) when establishing the impact area and conducting the subsequent
air quality analysis, if it can be shown that such emissions  do not impact a
Class I area or an area where a PSD increment for that pollutant is known to
be violated.  However, where EPA is not the PSD permitting authority, the
applicant should confer with the appropriate permitting agency to determine
whether it  allows for the exclusion of temporary emissions.
                                     C.30

-------
                                                                   DRAFT
                                                                   OCTOBER 1990

      Once defined for the proposed  PSD  project,  the impact area(s) will
determine the scope of the required  air  quality analysis.  That is, the  impact
area(s) will be used to
            set  the boundaries within which ambient air quality monitoring
            data may need to be collected,
            define the area over which a full impact analysis (one that
            considers the contribution of all sources) must be undertaken, and
            guide the identification of other sources to be included in  the
            modeling analyses.
Again, if no significant ambient  impacts  are predicted for a particular
pollutant, EPA does not require further  NAAQS or PSD increment analysis of
that pollutant.  However, the  applicant  must still  consider any additional
impacts which the proposed  source may  have concerning impairment on
visibility, soils and vegetation,  as well  as any adverse impacts on air
quality related values in Class I  areas  (see Chapters D and E of this part).

IV.C  SELECTING SOURCES FOR THE PSD  EMISSIONS INVENTORIES

      When a full impact analysis is required for any pollutant, the applicant
is responsible for establishing the  necessary inventories of existing sources
and their emissions, which  will be used  to carry out the required NAAQS and
PSD increment analyses.  Such  special  emissions inventories contain the
various source data used as input to an  applicable air quality dispersion
model  to estimate existing  ambient pollutant concentrations.  Requirements for
preparing an emissions inventory  to  support a modeling analysis are described
to a limited extent in the  Modeling Guideline.  In addition, a number of other
EPA documents (e.g., References 5 through 11) contain guidance on the
fundamentals of compiling emissions  inventories.  The discussion which follows
pertains primarily to identifying and  selecting existing sources to be
included in a PSD emissions inventory  as  needed for a full impact analysis.

      The permitting agency may provide  the applicant a list of existing
sources upon request once the  extent of  the impact area(s) is known.  If  the
                                     C.31

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
list includes only sources above a certain emissions threshold,  the applicant
is responsible for identifying additional  sources below that emissions level
which could affect the air quality within the impact area(s).  The permitting
agency should review all  required inventories for completeness and accuracy.

IV.C.I  THE NAAQS INVENTORY

      While air quality data may be used to help identify existing background
air pollutant concentrations, EPA requires that, at a minimum, all nearby
sources be explicitly modeled as part of the NAAQS analysis.  The Modeling
Guideline  defines  a  "nearby"  source as  any  point  source  expected  to cause  a
significant concentration gradient in the vicinity of the proposed new source
or modification.   For PSD purposes, "vicinity" is defined as the impact area.
However,  the location of such nearby sources could be anywhere within the
impact area or an annular area extending 50 kilometers beyond the impact area.
(See Figure C-5.)

      In determining which existing point sources constitute nearby sources,
the Modeling Guideline necessarily provides flexibility and requires judgment
to be exercised by the permitting agency.  Moreover, the screening method for
identifying a nearby source may vary from one permitting agency to another.
To identify the appropriate method, the applicant should confer with the
permitting agency prior to actually modeling any existing sources.
      The Modeling Guideline indicates that the useful distance for  guideline
models is 50 kilometers.  Occasionally, however, when applying the above
source identification criteria, existing stationary sources located in the
annular area beyond the impact area may be more than 50 kilometers from
portions of the impact area.  When this occurs, such sources' modeled impacts
throughout the entire impact area should be calculated.  That is, special
steps should not be taken to cut  off modeled impacts of existing  sources at
receptors within the applicants impact area merely because  the receptors are
                                     C.32

-------
                                                  DRAFT
                                 Screening Area

                                 Impact Area
                                        County D
                                        Attainment
                   Figure C-5
Defining the Emissions Inventory Screening Area.
                       C.33

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
located beyond 50 kilometers from such  sources.   Modeled  impacts  beyond  50
kilometers should be considered as  conservative  estimate  in  that  they  tend to
overestimate the true source impacts.   Consequently,  if  it  is  found  that an
existing source's impact include estimates  at  distances  exceeding the  normal
50-kilometer range,  it may be appropriate to  consider other  techniques,
including long-range transport models.   Applicants  should consult with the
permitting agency prior to the selection of a  model  in such  cases.

      It will  be necessary to include  in the  NAAQS  inventory those sources
which have received  PSD permits but have not  yet not begun  to  operate, as well
as any complete PSD  applications for which  a  permit has  not  yet  been issued.
In the latter case,  it is EPA's policy  to account for emissions  that will
occur at sources whose complete PSD application  was submitted  as  of  thirty
days prior to the date the proposed source  files its PSD application.   Also,
sources from which secondary emissions  will occur as a result  of  the proposed
source should be identified and evaluated for inclusion  in  the NAAQS
inventory.  While existing mobile source emissions  are considered in the
determination of background air quality for the  NAAQS analysis (typically
using existing air quality data), it should be noted that the  applicant need
not model estimates  of future mobile source emissions growth that could result
from the proposed project because the  definition of "secondary emissions"
specifically excludes any emissions coming  directly from mobile sources.

      Air quality data may be used to  establish  background concentrations in
the impact area resulting from existing sources  that are not considered as
nearby sources (e.g., area and mobile  sources, natural sources,  and  distant
point sources).  If, however, adequate air quality data  do not exist  (and the
applicant was not required to conduct  pre-application monitoring), then these
"other" background sources are also included in  the NAAQS inventory so that
their ambient impacts can be estimated by dispersion modeling.
                                     C.34

-------
                                                                    DRAFT
                                                                    OCTOBER 1990
IV.C.2  THE INCREMENT  INVENTORY
      An emissions  inventory for the analysis  of  affected PSD increments must
also be developed.   The  increment inventory  includes  all  increment-affecting
sources located  in  the  impact area of the proposed  new source or modification.
Also, all increment-affecting sources located  within  50 kilometers of the
impact area  (see Figure C-5)  are  included  in  the inventory if  they,  either
individually  or  collectively, affect the amount of  PSD increment consumed.
The applicant  should contact the permitting  agency  to determine what
particular procedures should be followed to  identify  sources for the increment
inventory.

      In general, the stationary sources of  concern for the increment
inventory are  those stationary sources with  actual  emissions changes occurring
since the minor  source  baseline date.  However, it  should be remembered  that
certain actual emissions changes occurring before the minor source baseline
date (i.e.,  at major stationary point sources) also affect the increments.
Consequently,  the types  of stationary point  sources that  are initially
reviewed to  determine the need to include them in the increment inventory  fall
under two specific  time  frames as follows:

      After  the  ma.ior source baseline date-
      •      existing ma.ior stationary sources having undergone a physical
                  change  or change in their method of operation;  and
      •      new ma.ior stationary sources.
      After the minor  source baseline date-
      •     existing stationary sources having undergone a physical
            change or change in their method of operation;
      •     existing stationary sources having increased hours of
            operation or capacity utilization (unless such change was
            considered representative of baseline operating conditions);  and
      •     new stationary sources.
                                      C.35

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      If,  in the impact area  or surrounding  screening  area,  area  or  mobile
source emissions will  affect  increment  consumption,  then  emissions input  data
for such minor sources are also included  in  the  increment inventory.   The
change in  such emissions since the minor  source  baseline  date  (rather  than the
absolute magnitude of  these emissions)  is of concern since this  change is what
may affect a PSD increment.  Specifically,  the  rate  of growth  and the  amount
of elapsed time since  the minor source  baseline  date was  established determine
the extent of the increase in area and  mobile source emissions.   For example,
in an area where the minor source baseline date  was  recently established
(e.g., within the past year or so of the  proposed  PSD  project),  very little
area and mobile source emissions growth may  have occurred.  Also, sufficient
data (particularly mobile source data)  may not  yet be  available  to reflect the
amount of  growth that  has taken place.  As with  the  NAAQS analysis,  applicants
are not required to estimate  future mobile source  emissions  growth that could
result from the proposed project because  they are  excluded from  the  definition
of "secondary emissions."

      The applicant should initially consult with  the  permitting agency to
determine the availability of data for  assessing area  and mobile source growth
since the minor source baseline date.  This  information,  or  the  fact that such
data is not available, should be thoroughly  documented in the  application.
The permitting agency  should  verify and approve  the  basis for  actual area
source emissions estimates and, especially if these  estimates  are considered
by the applicant to have an insignificant impact,  whether it agrees  with  the
applicant's assessment.

      when area and mobile sources are  determined  to affect any  PSD  increment,
their emissions must be reported on a gridded basis.  The grid should  cover
the entire impact area and any areas outside the impact area where area and
mobile source emissions are included in the analysis.   The exact sizing of  an
emissions inventory grid cell generally should be  based on the emissions
density in the area and any computer constraints that may exist.  Techniques
for assigning area source emissions to  grid cells  are provided in
Reference 11.  The grid layout should always be discussed with,  and  approved
by, the permitting agency in advance of its use.
                                     C.36

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.C.3  NONCRITERIA POLLUTANTS INVENTORY
      An inventory of all noncriteria pollutants emitted in significant
amounts is required for estimating the resulting ambient concentrations of
those pollutants.  Significant ambient impact levels have not been established
for non-criteria pollutants.  Thus, an impact area cannot be defined for non-
criteria pollutants in the same way as for criteria pollutants.  Therefore, as
a general rule of thumb, EPA believes that an emissions inventory for non-
criteria pollutants should include sources within 50 kilometers of the
proposed source.  Some judgment will  be exercised in applying this position on
a case-by-case basis.

IV.D  MODEL SELECTION

      Two levels of model sophistication exist: screening and refined
dispersion modeling.  Screening models may be used to eliminate more extensive
modeling for either the preliminary analysis phase or the full impact analysis
phase, or both.  However, the results must demonstrate to the satisfaction of
the permitting agency that all applicable air quality analysis requirements
are met.  Screening models produce conservative estimates of ambient impact in
order to reasonably assure that maximum ambient concentrations will not be
underestimated.  If the resulting estimates from a screening model indicate a
threat to a NAAQS or PSD increment, the applicant uses a refined model to re-
estimate ambient concentrations (of course, the applicant can select other
options, such as reducing emissions,  or to decrease impacts).  Guidance on the
use of screening procedures to estimate the air quality impact of stationary
sources is presented in EPA's Screening Procedures for Estimating Air Qaulity
Impact of Stationary Sources [Reference 123.

      A refined dispersion model provides more accurate estimates of a
source's impact and, consequently, requires more detailed and precise input
data than does a screening model.  The applicant is referred to Appendix A  of
the Modeling Guideline for a list of EPA-preferred models, i.e., guideline
models.  The guideline model selected for a particular application should be
the one which most accurately represents atmospheric transport, dispersion,
                                     C.37

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
and chemical  transformations in the area under analysis.  For example, models
have been developed for both simple and complex terrain situations; some are
designed for urban applications, while others are designed for rural
appli cati ons.

      In many circumstances the guideline models known as Industrial Source
Complex Model  Short- and Long-term (ISCST and ISCLT, respectively) are
acceptable for stationary sources and are preferred for use in the dispersion
modeling analysis.  A brief discussion of options required for regulatory
applications of the ISC model is contained in the Modeling Guideline.  Other
guideline models, such as the Climatological Dispersion Model (COM), may be
needed to estimate the ambient impacts of area and mobile sources.

      Under certain circumstances, refined dispersion models that are not
listed in the Modeling Guideline, i.e., non -guideline models, may be
considered for use in the dispersion modeling analysis.  The use of a non-
guideline model for a PSD permit application must, however, be pre-approved  on
a case-by-case basis by EPA.  The applicant should refer to the EPA documents
entitled Interim Procedures for Evaluating Air Quality Models (Revised)
[Reference 13] and Interim Procedures for Evaluating Air Quality Models:
Experience with  Implementation [Reference 14].  Close coordination with  EPA
and the appropriate State or local permitting agency is essential if a  non-
guideline model  is to be used successfully.
                                     C.38

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.D.I  METEOROLOGICAL DATA
      Meteorological  data used in air quality modeling must be spatially and
climatologically (temporally) representative of the area of interest.
Therefore, an applicant should consult the permitting authority to determine
what data will  be most representative of the location of the applicant's
proposed facility.

      Use of site-specific meteorological  data is preferred for air quality
modeling analyses if 1 or more years of quality-assured data are available.
If at least 1 year of site-specific data is not available,  5 years of
meteorological  data from the nearest National Weather Service (NWS) station
can be used in the modeling analysis.  Alternatively, data  from universities,
the Federal  Aviation Administration, military stations, industry,  and  State or
local air pollution control agencies may be used if such data are  equivalent
in accuracy and detail to the NWS data, and are more representative of the
area of concern.

      The 5 years of data should be the most recent consecutive 5  years of
meteorological  data available.  This 5-year period is used  to ensure that the
model results adequately reflect meteorological conditions  conducive to the
prediction of maximum ambient concentrations.  The NWS data may be obtained
from the National Climatic Data Center (Asheville, North Carolina), which
serves as a clearinghouse to collect and distribute meteorological  data
collected by the NWS.

IV.D.2  RECEPTOR NETWORK

      Polar and Cartesian networks are two types of receptor networks  commonly
used in refined air dispersion models.  A polar network is  comprised of
concentric rings and radial arms extending outward from a center point (e.g.,
the modeled source).   Receptors are located where the concentric rings and
radial arms intersect.  Particular care should be exercised in using a polar
network to identify maximum estimated pollutant concentrations because of the
inherent problem of increased longitudinal spacing of adjacent receptors as
                                     C.39

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
their distance along neighboring radial arms increases.  For example, as
illustrated in Figure C-6, while  the  receptors on  individual  radials,  e.g.,
Al. A2, A3... and Bl, B2,  B3...,  may be  uniformly  spaced  at a  distance of 1
kilometer apart, at greater distances from the proposed source, the
longitudinal distance between the receptors, e.g., A4 and  B4, on neighboring
radials may be several  kilometers.  As a result of the presence of larger and
larger "blind spots" between the radials as the distance from the modeled
source increases, finding the maximum source impact can be somewhat
problematic.  For this reason, using a polar network for anything other than
initial screening is generally discouraged.

      A cartesian network (also referred to as a rectangular network) consists
of north-south and east-west oriented lines forming a  rectangular grid, as
shown in Figure C-6, with  receptors located  at each  intersection  point.   In
most  refined air quality analyses, a cartesian grid with from 300 to 400
receptors (where the distance from the source to the farthest receptor  is   10
kilometers) is usually adequate to identify areas of maximum concentration.
However, the total number of receptors will vary based on the specific  air
quality analysis performed.

      In order to locate the maximum modeled impact, perform multiple model
runs, starting with a relatively coarse receptor grid  (e.g., one  or  two
kilometer spacing) and proceeding to a relatively fine receptor grid (e.g.,
100 meters).  The fine receptor grid should be used to focus on the  area(s) of
higher estimated pollutant concentrations  identified by the coarse grid model
runs.  With such multiple runs the maximum modeled concentration  can be
identified.  It  is the applicant's  responsibility to demonstrate  that the
final receptor network is sufficiently compact to identify the maximum
estimated pollutant concentration for each applicable  averaging period.  This
applies both to  the PSD  increments  and to  the NAAQS.
                                      C.40

-------
                                                            DRAFT
                                                  5 km
                     Polar Grid Network



















































t,







A1
•B11






A2
IB21






A3
IB31






A4
• B41






A5
B5



1 k
i

A6
B6



                   Cartesian Grid Network
Figure C-6. Examples of Polar and Cartesian Grid Networks.
                         C.41

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
      Some air quality models allow the user to  input  discrete  receptors  at
user-specified locations.  The selection of receptor  sites  should  be a  case-
by-case determination, taking into consideration the  topography,  the
climatology, the monitor sites, and the results  of the preliminary analysis.
For example, receptors should be located at:

      •     the fencel'we of a proposed facility;
      •     the boundary of the nearest Class I or nonattainment area;
      •     the location(s) of ambient air monitoring sites;   and
      •     locations where potentially high ambient air concentrations are
            expected to occur.

      In general, modeling receptors  for both  the  NAAQS and the PSD
increment analyses  should  be placed at ground  level points  anywhere
except on the  applicant's  plant property if it is  inaccessible  to the
general public.  Public  access to  plant property is to be  assumed, however,
unless a continuous physical barrier, such as  a  fence or wall,  precludes
entrance onto  that  property.   In cases where the public has access, receptors
should be located on the  applicant's  property.  It  is important to note that
ground level points of receptor placement  could  be  over bodies  of water,
roadways, and  property owned by other sources.  For NAAQS  analyses, modeling
receptors may  also  be placed at elevated  locations, such as on  building
rooftops.   However, for  PSD increments, receptors  are limited to locations at
ground level.

IV.D.3  GOOD ENGINEERING  PRACTICE  (GEP) STACK  HEIGHT

      Section  123 of the  Clean Air Act  limits  the  use of dispersion
techniques, such as merged gas streams, intermittent  controls,  or stack
heights above  GEP,  to meet the NAAQS  or PSD  increments.  The GEP stack height
is defined  under Section  123 as  "the  height  necessary to insure that emissions
from the stack do not result in  excessive  concentrations of any air pollutant
in the immediate vicinity of the  source as a  result of atmospheric downwash,

                                      C.42

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
eddies or wakes which  may be created by  the  source itself, nearby  structures
or nearby terrain  obstacles."   The EPA  has  promulgated stack  height
regulations under  40  CFR Part 51 which help  to determine the GEP stack height
for any stationary source.

      Three methods are available for determining "GEP stack height"  as
defined in 40  CFR  51.100(ii):
            use the 65 meter (213.5 feet) de minimis height as measured from
            the ground-level elevation at the base of the stack;
            calculate the refined formula height using the dimensions of
            nearby structures (this height equals H + 1.5L, where H is the
            height of the nearby structure and L is the lesser dimension of
            the height or projected width of the nearby structure); or
            demonstrate by a fluid model or field study the equivalent GEP
            formula height that is necessary to avoid excessive concentrations
            caused by atmospheric downwash, wakes, or eddy effects by the
            source, nearby structures, or nearby terrain features.
      That  portion  of a stack height  in  excess of the GEP height  is  generally
not creditable  when modeling to develop  source emissions limitations or to
determine source  impacts in a PSD air  quality analysis.  For  a  stack height
less than GEP  height, screening procedures  should be applied  to assess
potential air  quality impacts associated with building downwash.   In some
cases, the  aerodynamic turbulence induced by surrounding buildings will cause
stack emissions to  be mixed rapidly toward  the ground (downwash),  resulting in
higher-than-normal  ground level concentrations in the vicinity  of  the source.
Reference 12 contain screening procedures to estimate downwash  concentrations
in the building wake region.  The Modeling Guideline recommends  using  the
Industrial  Source Complex (ISC) air dispersion model to determine  building
wake effects on maximum estimated pollutant concentrations.

      For additional guidance on creditable stack height and  plume  rise
calculations,  the applicant should consult  with the permitting  agency.  In
addition, several  EPA publications [References 15 through 19] are  available
for the applicant's review.

                                       C.43

-------
                                                                    DRAFT
                                                                    OCTOBER 1990
IV.D.4  SOURCE DATA
      Emissions  rates  and other source-related  data  are needed to estimate  the
ambient concentrations resulting from (1) the proposed new source or
modification,  and  (2)  existing sources contributing  to background pollutant
concentrations  (NAAQS  and PSD increments).  Since  the estimated pollutant
concentrations  can  vary widely depending on the accuracy of such data,  the
most appropriate source data available should always be selected for  use  in a
modeling analysis.   Guidance on the identification and selection of existing
sources for which  source input data must be obtained for a PSD air quality
analysis is provided in section IV.C.  Additional  information on the specific
source input  data  requirements is contained in  EPA's Modeling Guideline  and  in
the users' guide for each dispersion model.

      Source  input  data that must be obtained will depend upon the
categorization  of  the  source(s) to be modeled as either a point, area  or  line
source.  Area  sources  are often collections of  numerous small emissions
sources that  are impractical to consider as separate point or line sources.
Line sources  most  frequently considered are roadways.

      For  each  stationary point source to be modeled, the following minimum
information is  generally necessary:

      •     pollutant emission rate (see discussion below);
      •     stack height (see discussion on GEP stack height);
      •     stack gas exit temperature, stack exit inside diameter, and stack
            gas exit velocity;
      •     dimensions of all structures in the vicinity of the stack in
            question;
             the location of topographic features (e.g., large bodies of water,
             elevated terrain) relative to emissions points;  and
             stack coordinates.
                                       C.44

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      A source's emissions rate as used in a modeling analysis for any
pollutant is determined from the following source parameters  (where MMBtu
means "million Btu's heat input"):

      •     emissions limit (e.g., Ib/MMBtu);
      •     operating level (e.g., MMBtu/hour); and
      •     operating factor (e.g., hours/day, hours/year).

Special  procedures, as described below, apply to the way that each of these
parameters is used in calculating the emissions rate for either the proposed
new source (or modification) or any existing source considered in the NAAQS
and PSD increment analyses.  Table C-5  provides  a summary of the point  source
emissions input data requirements for the NAAQS inventory.

      For both NAAQS and PSD increment compliance demonstrations, the
emissions rate for the proposed new source or modification must reflect the
maximum allowable operating conditions as expressed by  the federally
enforceable emissions limit, operating level, and operating factor for each
applicable pollutant and averaging time.  The applicant should base the
emissions rates on the results of the 8ACT analysis (see Chapter B, Part I).
Operating levels less than 100 percent of capacity may  also need to be modeled
where differences in stack parameters associated with the  lower operating
levels could result in higher ground level concentrations.  A value
representing less than continuous operation (8760 hours per year) should be
used for the operating factor only when a federally enforceable operating
limitation is placed upon the proposed source.  [NOTE:  It is important that
the applicant demonstrate that all modeled emission rates  are consistent with
the applicable permit conditions.]
                                     C.45

-------
                                                                                                                   DRAFT
                                                                                                                   OCTOBER 1990


             TABLE  C-5    POINT SOURCE MODEL INPUT  DATA  (EMISSIONS)  FOR  NAAQS COMPLIANCE  DEMONSTRATIONS
 Averaging  Time
                           Emission Limit

                              WMMBtu)1
                                       Operating Level

                             X           (MMBtu/hr)1
                                                 Operating Factor

                                            (e.g., hr/yr,  hr/day)
                                                     Proposed Major New or Modified Source
Annual and quarterly
Short term
 (24 hours or less)
Maximum allowable emission
limit or Federally enforceable
permit

Maximum allowable emission
limit or Federally enforceable
permit limit
                                                                  Design  capacity or Federally
                                                                  enforceable  permit condition
Design capacity  or  Federally
enforceable permit  condition3
                                                 Continuous operation
                                                 (i.e, 8760 hours)2
          Continuous  operation  (i.e.,
          all  hours of each time
          period  under consideration)
          (for  all hours of the
          meteorological data base)2
                                                         Nearby  Background Source(s)'
Annual and quarterly
Short term
                           Maximum allowable emission
                           limit or Federally enforceable
                           permit
                           Maximum allowable emission
                           limit  or  Federally enforceable
                           permit limit
                                       Actual or design capacity
                                       (whichever is greater),  or
                                       Federally enforceable permit
                                       condition

                                       Actual or design capacity
                                       (whichever is greater),  or
                                       Federally enforceable permit
                                       condition1
                                                 Actual operating factor
                                                 averaged over the most
                                                 recent 2 years*
                                                 Continuous operation (i.e.,
                                                 all hours of each time
                                                 period under consideration)
                                       (for all hours of the
                                                 meteorological  data base)2
                                                          Other  Background  Source(s)6
Annual and quarterly
Short term
Maximum allowable emission
limit or Federally enforceable
permit limit

Maximum allowable emission
limit or Federally enforceable
permit limit
Annual level  when actually
operating, averaged over  the
most recent 2 years5

Annual level  when actually
operating, averaged over  the
most recent 2 years5
          Actual  operating  factor
          averaged over  the most
          recent  2 years*

          Continuous  operation  (i.e.,
          all  hours of each time
period under consideration)

          (for all hours of the
          meteorological  data base)2
Terminology  applicable to fuel burning sources; analogous  terminology  (e.g., #/throughput) may be used for other  types  of sources.
If operation does  not occur for all hours of the time period  of  consideration  (e.g., 3 or 24 hours) and the source  operation  is  constrained
by a Federally enforceable  permit  condition, an appropriate adjustment to the  modeled  emission rate may be made (e.g.,  if operation is only
8:00 a.m. to 4:00 p.m.  each  day, only  these hours will be modeled with emissions  from  the source.  Modeled emissions should not be averaged
across non-operating time periods).
Operating levels  such as 50 percent and 75 percent of capacity  should  also  be  modeled to determine the load causing the highest  concentration.
Includes  existing  facility to which modification is  proposed  if  the  emissions  from the existing facility will  not  be affected  by the
modification,  otherwise use  same  parameters as for major modification.
Unless  it is determined  that this period is not representative.
Generally, the ambient impacts from non-nearby background  sources can  be  represented by air quality data unless adequate data  do not  exist.
                                                                    C.46

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      For those existing point sources that must be explicitly modeled, i.e.,
"nearby" sources (see section IV.C.I  of  this chapter),  the  NAAQS inventory
must contain the maximum allowable values for the emissions limit, and
operating level.  The operating factor may be adjusted to account for
representative, historical  operating conditions only when modeling for the
annual  (or quarterly for lead [Pb]) averaging period.  In such cases, the
appropriate input is the actual operating factor averaged over the most recent
2 years (unless the permitting agency determines that another period is more
representative).  For short-term averaging periods (24 hours or less), the
applicant generally should assume that nearby sources operate continuouslv.
However, the operating factor may be adjusted to take into account any
federally enforceable permit condition which limits the al1owable hours of
operation.  In situations where the actual operating level exceeds the design
capacity (considering any federally enforceable limitations), the actual  level
should be used to calculate the emissions rate.

      If other background sources need to be modeled (i.e.,  adequate air
quality data are not available to represent their impact), the input
requirements for the emissions limit and operating factor are identical to
those for "nearby" sources.  However,  input for the operating level may be
based on the annual  level of actual operation averaged over  the last 2 years
(unless the permitting agency determines that a more representative period
exi sts).

      The applicant must also include any quantifiable fugitive emissions from
the proposed source or any nearby sources.  Fugitive emissions are those
emissions that cannot reasonably be expected to pass through a stack, vent, or
other equivalent opening, such as a chimney or roof vent.  Common quantifiable
fugitive emissions sources of particulate matter include  coal piles, road
dust, quarry emissions,  and aggregate stockpiles.  Quantifiable fugitive
emissions of volatile organic compounds (VOC) often occur at components of
process equipment.  An applicant should consult with the  permitting agency to
determine the proper procedures for characterizing and modeling fugitive
emissions.
                                     C.47

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      When building downwash affects the air quality impact of the proposed
source or any existing source which is modeled for the NAAQS analysis, those
impacts generally should be considered in the analysis.  Consequently, the
appropriate dimensions of all structures around the stack(s) in question also
should be included in the emissions inventory.  Information including building
heights and horizontal building dimensions may be available in the permitting
agency's files; otherwise, it is usually the responsibility of the applicant
to obtain this information from the applicable source(s).

      Sources should not automatically be excluded from downwash
considerations simply because they are located outside the impact area.  Some
sources located just outside the impact area may be located close enough to it
that the immediate downwashing effects directly impact air quality in the
impact area.  In addition, the difference in downwind plume concentrations
caused by the downwash phenomenon may warrant consideration within the impact
area even when the immediate downwash effects do not.  Therefore, any decision
by the applicant to exclude the effects of downwash for a particular source
should be justified in the application, and approved by the permitting agency.

      For a PSD increment analysis, an estimate of the amount of increment
consumed by existing point sources generally is based on increases in actual
emissions occurring since the minor source baseline date.  The exception, of
course, is for major stationary sources whose actual emissions have increased
(as a result of construction) before the minor source baseline date but  on  or
after the major source baseline date.  For any increment-consuming (or
increment-expanding) emissions unit, the actual emissions limit, operating
level, and operating factor may all be determined from source records and
other information (e.g., State emissions files), when available, reflecting
actual source operation.  For the annual averaging period, the change in the
actual emissions rate should be calculated as the difference between:

      •     the current average actual emissions rate, and
      •     the average actual emissions rate as of the minor  source baseline
            date (or major source baseline date for major stationary sources).
                                     C.48

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
In each case, the average rate is calculated  as  the  average  over previous
2-year period (unless the permitting agency determines  that  a  different time
period is more representative of normal  source operation).

      For each short-term averaging period  (24 hours  and  less),  the change in
the actual emissions rate for the particular  averaging  period  is calculated as
the difference between:

      •     the current maximum actual emissions rate, and
      •     the maximum actual emissions rate as of  the minor source baseline
            date  (or major source baseline date for applicable major
            stationary sources undergoing consturction  before the minor source
            baseline date).
In each case, the maximum rate is the highest occurrence  for that averaging
period during the previous 2 years of operation.

      Where appropriate, air quality impacts  from fugitive emissions and
building downwash are also taken into account for the PSD increment analysis.
Of course, they would only be considered  when applicable  to  increment-
consuming emissions.

      If the change in the actual emissions rate at  a particular source
involves a change in stack parameters (e.g.,  stack height, gas  exit
temperature, etc.) then  the stack parameters  and emissions rates associated
with both the baseline case and the current situation must be  used as input to
the dispersion model.  To determine increment consumption (or  expansion)  for
such a source, the baseline case emissions  are input  to  the  model  as negative
emissions, along with the baseline stack  parameters.  In  the same model run,
the current case for the same source is  modeled  as the  total current emissions
associated with the current stack parameters.  This  procedure  effectively
calculates, for each receptor and for each  averaging  time, the  difference
between the baseline concentration and the  current concentration (i.e., the
amount of increment consumed by the source).

      Emissions changes  associated with  area  and mobile  source  growth
occurring since the minor source baseline date are also  accounted for in the
                                     C.49

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Increment analysis by modeling.   In many cases state  emission  files  will
contain information on area  source emissions or such  information  may be
available from EPA's AIRS-NEDS emissions data base.   In  the absence  of this
information,  the applicant should use procedures adopted for developing state
area source emission inventories.  The EPA documents  outlining procedures  for
area source inventory development should be reviewed.

      Mobile source emissions are usually calculated  by  applying  mobile source
emissions factors to transportation data such as vehicle miles travelled
(VMT), trip ends, vehicle fleet characteristics, etc.   Data are also required
on the spatial arrangement of the VMT within the area  being modeled.  Mobile
source emissions factors are available for various vehicle types  and
conditions from an EPA emissions factor model entitled MOBILE4.  The MOBILE4
users manual  [Reference 20]  should be used in developing inputs for   executing
this model.  The permitting  agency can be of assistance  in obtaining the
needed mobile source emissions data.  Oftentimes, these  data are  compiled  by
the permitting agency acting in concert with the local planning agency or
transportation department.

      For both area source and mobile source emissions,  the applicant will
need to collect data for the minor source baseline date  and the current
situation.  Data from these  two dates will be required to calculate  the
increment-affecting emission changes since the minor  source baseline date.
                                     C.50

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.E  THE COMPLIANCE DEMONSTRATION
      An applicant for a PSD permit must demonstrate that the proposed source
will  not cause or contribute to air pollution in violation of any NAAQS or PSD
increment.  This compliance demonstration,  for each affected pollutant, must
result in one of the following:
      •     The proposed new source or modification will not cause a
      significant ambient impact anywhere.
      If the significant net emissions increase from a proposed source would
not result in a significant ambient impact anywhere, the applicant is usually
not required to go beyond a preliminary analysis in order to make the
necessary showing of compliance for a particular pollutant.   In determining
the ambient impact for a pollutant, the highest estimated ambient
concentration of that pollutant for each applicable averaging time is used.
            The proposed new source or modification,  in conjunction with
            existing sources, will not cause or contribute to a violation of
            any NAAQS or PSD increment.
      In general,  compliance is determined by comparing the predicted ground
level concentrations (based on the full  impact analysis and existing air
quality data) at each model receptor to  the applicable NAAQS and PSD
increments.  If the predicted pollutant  concentration increase over  the
baseline concentration is below the applicable increment,  and the predicted
total ground level  concentrations are below the NAAQS, then the applicant has
successfully demonstrated compliance.

      The modeled  concentrations which should be used to determine compliance
with any NAAQS and  PSD increment depend  on 1) the type of  standard,  i.e.,
deterministic or statistical, 2) the available length of record of
meteorological  data, and 3) the averaginign time of the standard being
analyzed.  For example,  when the analysis is based on 5 years of National
Weather Service meteorological data, the following estimates should  be used:
                                     C.51

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
            for deterministically based standards (e.g.,  S02), the  highest,
            second-highest short term estimate and the highest annual
            estimate;  and
            for statistically based standards (e.g.,  PM-10),  the highest,
            sixth-highest  estimate and highest 5-year average estimate.
Further guidance to determine the appropriate estimates to use for the
compliance determination is found in Chapter 8 of the Model ins Guideline  for
S02, TSP,  lead,  N02, and CO; and in EPA's PM-IZ SIP Development Guideline [Reference
21] for PM-10.

      When a violation of any NAAQS or increment is predicted at one or  more
receptors in the impact area, the applicant can determine whether the net
emissions increase from the proposed source will  result in a significant
ambient impact  at the point (receptor) of each predicted violation, and  at the
time the violation is predicted to occur.  The source  will not be considered
to cause or contribute to the violation  if its own impact is not significant
at any violating receptor at the time of each predicted violation.  In such a
case,  the permitting agency, upon verification of  the  demonstration, may
approve the permit.  However, the agency must also take remedial action
through applicable provisions of the state implementation plan to address the
predicted violation(s).

      •     The proposed new source or modification, in conjunction with
            existing sources, will cause or contribute to a violation, but
            will secure sufficient emissions reductions to offset its adverse
            air quality impact.

      If the applicant cannot demonstrate that only insignificant ambient
impacts would occur at violating receptors (at the time of the predicted
violation), then other measures are needed before  a permit can be issued.
Somewhat different procedures apply to NAAQS violations than to PSD increment
violations.  For a NAAQS violation to which an applicant contributes
significantly,  a PSD permit may be granted only if sufficient emissions
reductions are obtained to compensate for the adverse ambient impacts caused
by the proposed source.  Emissions reductions are  considered to compensate for
the proposed source's adverse impact when, at a minimum, (1) the modeled net
                                     C.52

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
concentration,  resulting from the proposed emissions  increase and the
federally enforceable emissions reduction, is less than the applicable
significant ambient impact level  at each affected receptor, and  (2)  no new
violations will  occur.   Moreover, such emissions  reductions must be  made
federally enforceable in order to be acceptable for providing the air quality
offset.   States  may adopt procedures pursuant to  federal  regulations at
40 CFR 51.165(b) to enable the permitting of sources  whose emissions would
cause or contribute to a NAAQS violation anywhere.  The applicant should
determine what  specific provisions exist within the State program to deal  with
this type of situation.

      In situations where a proposed source would cause or contribute to  a PSD
increment violation, a PSD permit cannot be issued until  the increment
violation is entirely corrected.   Thus, when the  proposed source would cause  a
new increment violation, the applicant must obtain emissions reductions that
are sufficient  to offset enough of the source's ambient impact to avoid the
violation.  In  an area where an increment violation already exists,  and the
proposed source  would significantly impact that violation, emissions
reductions must  not only offset the source's adverse  ambient impact, but  must
be sufficient to alleviate the PSD increment violation, as well.
                                     C.53

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
V.  AIR QUALITY ANALYSIS -- EXAMPLE
      This section presents a hypothetical  example of an air quality analysis
for a proposed new PSD source.   In reality, no two analyses are alike,  so an
example that covers all  modeling scenarios  is not possible to present.
However, this example illustrates several  significant elements of the air
quality analysis, using the procedures and  information set forth in this
chapter.

      An applicant is proposing to construct a new coal-fired, steam electric
generating station.  Coal  will  be supplied  by railroad from a distant mine.
The coal-fired plant is a  new major source  which has the potential to emit
significant amounts of S02i PM (particulate matter emissions and  PM-10
emissions), NOX,  and  CO.   Consequently,  an  air quality analysis  must be
carried out for each of these pollutants.   In this analysis, the applicant is
required to demonstrate compliance with respect to -

      •     the NAAQS for S02,  PM-10,  N02,  and CO, and
      •     the PSD increments for S02>  TSP,  and N02.

V.A  DETERMINING THE IMPACT AREA

      The first step in the air quality analysis is to estimate  the ambient
impacts caused by the proposed new source  itself.  This preliminary analysis
establishes the impact area for each pollutant emitted in significant amounts,
and for each averaging period.  The largest impact area for each pollutant is
then selected as the impact area to be used in the full impact analysis.

      To begin, the applicant prepares a modeling protocol describing the
modeling techniques and data bases that will  be applied in the preliminary
analysis.  These modeling procedures are reviewed in  advance by  the permitting
agency  and are determined to be in accordance with the procedures described  in
the Modeling Guideline and the  stack  height regulations.
                                     C.54

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
      Several pollutant-emitting activities  (i.e.,  emissions units) at the
source will emit pollutants subject  to  the  air  quality analysis.  The two main
boilers emit particulate matter  (i.e.,  particulate  matter emissions and PM-10
emissions), S02,  NOX, and CO.   A  standby auxiliary boiler also emits these
pollutants, but will only be permitted  to operate when the main boilers are
not operating.

      Particulate matter emissions and  PM-10 emissions will  also occur at the
coal-handling operations and the limestone  preparation process for the flue
gas desulfurization (FGD) system.  Emissions units  associated with coal and
limestone handling include:

      •     Point sources--the coal  car dump, the fly ash silos,  and the three
            coal baghouse collectors;
      •     Area sources--the active and the inactive coal storage piles and
            the  limestone storage pile;  and
      •     Line sources--the coal and limestone  conveying operation.

      The emissions from all of  the  emissions units  at the proposed source are
then  modeled to estimate the source's area  of significant impact (impact area)
for each pollutant.  The results of  the preliminary  analysis indicate that
significant ambient concentrations of N02 and S02 will  occur out to distances
of 32 and 50 kilometers, respectively,  from  the proposed source.  No
significant concentrations of  CO are predicted  at any  location outside the
fenced-in property of the proposed source.   Thus, an  impact area is not
defined for CO,  and no further CO analysis  is required.

      Particulate matter emissions from the  coal-handling operations and the
limestone preparation process  result in significant  ambient TSP concentrations
out to a distance of 2.2 kilometers.  However,  particulate matter emissions
from  the boiler stacks will cause significant TSP concentrations for a
distance of up to 10 kilometers.  Since the  boiler  emissions of particulate
matter are predominantly PM-10 emissions, the same  impact area is used for
both  TSP and PM-10.
                                      C.55

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      This preliminary analysis further indicates that pre-application
monitoring data may be required for two of the criteria pollutants,  S02 and
N02)  since the  proposed  new  source  will  cause  ambient  concentrations  exceeding
the prescribed significant monitoring concentrations for these two pollutants
(see Tdble C-3).   Estimated concentrations  of  PM-10  are  below  the  significant
monitoring concentration.  The permitting agency informs the applicant that
the requirement for pre-appl ication monitoring data will not be imposed with
regard to PM-10.  However, due to the fact that existing ambient
concentrations of both S02 and  N02 are known to exceed  their  respective
significant monitoring concentrations, the applicant must address the pre-
application monitoring data  requirements for these pollutants.

      Before undertaking a site-specific monitoring program, the applicant
investigates the availability of existing data that is representative of air
quality in the area.  The permitting agency indicates that an agency-operated
S02 network exists  which it  believes would provide  representative data for the
applicant's use.  It remains for the applicant to demonstrate that the
existing air quality data meet the  EPA criteria for data sufficiency,
representativeness, and quality as  provided in the PSD Mom tor ing Guideline.
The applicant proceeds to provide a demonstration which is approved by the
permitting agency.  For N02,  however,  adequate data do not  exist, and it  is
necessary for the applicant to take responsibility for collecting such data.
The applicant consults with the permitting agency in order to develop a
monitoring plan and subsequently undertakes a site-specific  monitoring program
for N02.

      In this example, four intrastate counties are covered  by the applicant's
impact area.  Each of these counties, shown in Figure C-7,  is  designated
attainment for all affected pollutants.   Consequently, a NAAQS and PSD
                                     C.56

-------
                                                           DRAFT
                                                           OCTOBER  1990
Figure I-C- 7.  Counties Within 100 Kilometers of Proposed Source.
                          C.57

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
analysis must be completed in each county.  With the exception  of CO  (for
which no further analysis is required) the applicant proceeds with the  full
impact analysis for each affected pollutant.

V.B  DEVELOPING THE EMISSIONS INVENTORIES

      After the impact area has been determined, the applicant  proceeds to
develop the required emissions inventories.  These inventories  contain  all  of
the source input data that will be used to perform the dispersion modeling for
the required NAAQS and PSD increment analyses.  The applicant contacts  the
permitting agency and requests a listing of all stationary  sources within  a
100-kilometer radius of the proposed new source.  This takes into account  the
50-kilometer impact area for S02 (the largest of the defined impact areas)
plus the requisite 50-kilometer annular area beyond that  impact area.   For N02
and particulate matter, the applicant needs only to consider the identified
sources which fall within the specific screening areas for  those two
pol1utants.

      Source input data (e.g., location, building dimensions, stack
parameters, emissions factors) for the inventories are extracted from the
permitting agency's air permit and emissions inventory files.   Sources  to
consider for these inventories also  include any that might  have recently been
issued a permit to operate, but are  not yet in  operation.    However,  in this
case no such "existing" sources are  identified.  The following  point  sources
are found  to exist within the applicant's  impact area  and screening  area:

      •     Refinery A;
      •     Chemical Plant B;
      •     Petrochemical Complex C;
      •     Rock Crusher D;
      •     Refinery E;
      •     Gas Turbine Cogeneration Facility F; and
      •     Portland Cement Plant G.
                                      C.58

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      A diagram of the general  location of these sources relative to the
location proposed source is shown in Figure C-8.  Because the Portland
Cement Plant G is located 70 kilometers away from the proposed source, its
impact is not considered in the NAAQS or PSD increment analyses for
particulate matter.   (The area  of concern for particulate matter lies within
60 kilometers of the proposed source.)   In this example,  the  applicant first
develops the NAAQS emissions inventory for S02>  particulate matter  (PM-10),
and N02.

V.B.I  THE NAAQS INVENTORY

      For each criteria pollutant undergoing review,  the applicant (in
conjunction with the permitting agency) determines which of the identified
sources will be regarded as "nearby" sources and,  therefore, must be
explicitly modeled.   Accordingly, the applicant classifies the candidate
sources in the following way:
                          Nearby sources        Other Background Sources
      Pol 1utant         (expli citlv model)       (non-modeled background)
      S02                Refinery A              Port. Cement Plant G
                        Chemical Plant B
                        Petro.  Complex C
                        Refinery E
      N02                Refinery A,             Refinery E
                        Chemical Plant B
                        Petro.  Complex C
                        Gas Turbines F
      Particulate       Refinery A              Chemical Plant B
      Matter (PM-10)     Petro.  Complex C        Refinery E
                        Rock Crusher D          Gas Turbines F

      For each nearby source,  the applicant now must obtain emissions input
data for the model  to be used.   As a conservative approach, emissions input
data reflecting the maximum allowable emissions rate of each nearby source
could be used in the  modeling analysis.  However, because of the relatively
                                     C.59

-------
                                                                 DRAFT
                                                                 OCTOBER 1990
            • Portland Cement Plant (
                                           SO2lmpact Area (50 km.)
 Chemical Plar\B  •
   Rock Crushe\D  *
Figure C-8. Point Sources Within 100 Kilometers of Proposed Source.
                              C.60

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
high concentrations anticipated due to the clustering of sources A,  B, C and
D, the applicant decides to consider the actual  operating factor for each of
these sources for the annual  averaging period, in accordance with Table C-5.
For example,  for S02)  the  applicant  may  determine  the actual  operating factor
for sources A,  B, and C, because they are classified as nearby sources for S02
modeling purposes.   On the other hand, the applicant chooses to use  the
maximum allowable emissions rate for Source E in order to save the time and
resources involved  with determining the actual operating factors for the 45
individual  N02  emissions units  comprising  the  source.   If  a  more  refined
analysis is ultimately warranted,  then the actual  hours of operation can be
obtained from Source E for the purposes of the annual averaging period.

      As another example,  for particulate matter (PM-10),  the applicant may
determine the actual annual operating factor for sources A,  C, and D, because
they are nearby sources for PM-10  modeling purposes.  Again, the applicant
chooses to determine the actual hours of annual  operation because of the
relatively high concentrations anticipated due to the clustering of  these
particular sources.

      For each  pollutant,  the applicant must also determine if emissions from
the sources that were not  classified as nearby sources can be adequately
represented by   existing air quality data.  In the case of S02,  for  example,
data from the existing State monitoring network will adequately measure
Source G's ambient  impact  in the impact area.   However, for PM-10, the
monitored impacts of Source B cannot be separated from the impacts of the
other sources (A, C, and D) within the proximity of Source B.  The applicant
therefore must  model this  source but is allowed to determine both the actual
operating factor and the actual operating level  to model the source's annual
impact, in accordance with Table C-5.   For  the  short-term (24-hour) analysis
the applicant may use the  actual operating level,  but continuous operation
must be used  for the operating factor.  The ambient impacts of Source E and
Source F will be represented by ambient monitoring data.

      For the N02 NAAQS  inventory,  the only  source  not  classified as a nearby
source is Refinery  E.  The applicant would have preferred to use ambient data
                                     C.61

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
to represent the ambient impact of this source; however,  adequate  ambient  N02
data is not available for the area.  In order to avoid modeling  this  source
with a refined model for N02,  the  applicant initially agrees to use a
screening technique recommended by the permitting  agency  to  estimate  the
impacts of Source E.

      Air quality impacts caused by building downwash must  be  considered
because several nearby sources (A, B, C, and E) have  stacks  that  are  less  than
GEP stack height.   In consultation with the permitting agency,  the applicant
is instructed to consider downwash for all four sources  in  the S02 NAAQS
analysis, because the sources are all located in the  S02 impact area.  Also,
after consdieration of the expected effect of downwash for  other  pollutants,
the applicant is told that, for N02,  only Source C must be modeled for its air
quality impacts due to downwash, and no modeling for  downwash  needs  to  be  done
with respect to particulate matter.

      The applicant gathers the necessary  building dimension data  for the
NAAQS inventory.  In this case, these data are  available  from  the  permitting
agency through its  permit files for sources A,  B,  and  E.   However, the
applicant must contact Source C to obtain  the data from  that source.
Fortunately, the manager of Source C readily provide  the  applicant this
information for each of the 45 individual  emission units.

V.B.2  THE INCREMENT INVENTORY

      An increment  inventory must be developed  for S02, particulate matter
(TSP), and N02.  This inventory includes all  of the applicable  emissions input
data from:
      •     increment-consuming sources within the impact area;  and
      •     increment-consuming sources outside the impact area that affect
            increment consumption in the impact area.

In considering emissions changes occurring at any  of  the major stationary
sources  identified  earlier  (see Figure C-8), the applicant must consider
actual emissions changes resulting from  a  physical change or a change in the
                                     C.62

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
method of operation since the major source baseline date, and any actual
emissions changes since the applicable minor source baseline date.  To
identify those sources (and emissions) that consume PSD increment, the
applicant should request information from the permitting agency concerning the
baseline area and all  baseline dates (including the existence of any prior
minor source baseline dates) for each applicable pollutant.

      A review of previous PSD applications within the total area of concern
reveals that minor source baseline dates for both S02  and TSP have already be
established in Counties A and B.  For N02,  the  minor source baseline  date  has
already been established in County C.  A summary of the relevant baseline
dates for each pollutant in these three counties is shown in Table C-6.  The
proposed source will,  however, establish the minor source baseline date in
Counties C and D for S02  and TSP,  and in  Counties  A, B and D for  N02.

      For S02,  the  increment-consuming  sources  deemed  to contribute  to
increment consumption in the impact area are sources A, B, C and E.   Source B
underwent a major modification which established the minor source baseline
date (April 21, 1984).  The actual emissions increase  resulting from that
physical change is used in the increment analysis.  Source A underwent a  major
modification and Source E increased its hours of operation after the minor
source baseline date.   The actual emissions increases  resulting from both of
these changes are used in the increment analysis, as well.  Finally, Source C
received a permit to add a new unit, but the new unit  is not yet operational.
Consequently, the applicant must use the potential emissions increase
resulting from that new unit to model the amount of increment consumed.  The
existing units at Source C do not affect the increments because no actual
emissions changes have occurred since the April 21, 1984 minor source baseline
                                     C.63

-------
               TABLE  C-6.   EXISTING  BASELINE DATES FOR S02, TSP,
                   AND  N02 FOR EXAMPLE PSD  INCREMENT ANALYSIS
                                                                  DRAFT
                                                                  OCTOBER 1990
Pollutant
Major Source
Baseline Date
Minor Source
Baseline Date
Affected
Counties
Sulfur dioxide
January 6, 1975
Particulate Matter
    (TSP)             January 6, 1975
Nitrogen Dioxide
February 8, 1988
April  21, 1984


March 14, 1985

June 8, 1988
 A and B
                                             A  and  B
                                     C.64

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
date.  Building dimensions data are needed in the increment inventory for
nearby sources A, B,  and E because each has increment-consuming emissions
which are subject to  downwash problems.  No building dimensions data  are
needed for Source C,  however, because only the emissions from the newly-
permitted unit consume increment and the stack built for that unit was
designed and constructed at GEP stack height.

      For N02,  only the  gas  turbines  located  at Cogeneration  Station  F have
emissions which affect the increment.  The PSD permit application for the
construction of these turbines established the minor source baseline  date
for N02 (June 8, 1988).  Of course, all construction-based actual emissions
changes in NOX  occurring  after  the  major  source baseline  date for  N02
(February 8, 1988),  at any major stationary source affect increment.   However,
no such emissions changes were discovered at the  other existing sources  in the
area.  Thus, only the actual emissions increase resulting from  the gas
turbines is included  in the N02 increment  inventory.

      For TSP, sources A, B, C, and E are found to have units whose emissions
may affect the TSP increment in the impact area.   Source A established the
minor source baseline date with a PSD permit application to modify its
existing facility.  Source B (which established the minor source baseline  date
for S02)  experienced  an  insignificant increase  in  particulate matter  emissions
due to a modification prior to the minor source baseline date for particulate
matter (March 14, 1985).  Even though the emissions increase did not  exceed
the significant emissions rate for particulate matter emissions (i.e., 25  tons
per year), increment  is consumed by the actual  increase nonetheless,  because
the actual emissions  increase resulted from construction (i.e., a physical
change or a change in the method of operation)  at a major stationary  source
occurring after the major source baseline date for particulate  matter.  The
applicant uses the allowable increase as a conservative estimate of the  actual
emissions increase.   As mentioned previously, Source C received a permit  to
construct, but the newly-permitted unit is not yet in operation.  Therefore,
the applicant must use the potential  emissions to model the amount of TSP
increment consumed by that new unit.
                                     C.65

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Finally,  Source E's  actual  emissions  increase  resulting  from an  increase
in its hours of operation  must  be considered  in  the  increment  analysis.   This
source is located far enough  outside  the  impact  area  that  its  effects  on
increment consumption in  the  impact  area  are  estimated  with  a  screening
technique.   Based on  the  conservative results, the permitting  agency
determines  that the source's  emissions  increase  will  not  affect  the amount  of
increment consumed in the  impact  area.

      In compiling the increment  inventory,  increment-consuming  TSP and  S02
emissions occurring at minor  and  area sources located in  Counties  A and  B must
be considered.   Also, increment-consuming NOX emissions occurring  at minor,
area, and mobile sources  located  in  County  C  must be considered.   For  this
example, the applicant proposes that because  of  the  low growth in  population
and vehicle miles traveled in the affected  counties  since the  applicable minor
source baseline dates, emissions  from area  and mobile sources  will not affect
increment (S02,  TSP,  or N02) consumed within the  impact area and, therefore,
do not need to be included in the increment inventory.   After  reviewing  the
documentation submitted by the applicant, the permitting  agency  approves the
applicant's proposal  not  to include  area  and  mobile  source emissions in  the
increment inventory.

V.C  The Full Impact Analysis

      Using the source input  data contained in  the emissions inventories, the
next step is to model existing source impacts for both the NAAQS and PSD
increment analyses.  The  applicant's selection  of models--ISCST, for short-
term modeling, and ISCLT,  for long-term model ing--was made after conferring
with the permitting agency and determining that  the  area  within  three
kilometers  of the proposed source is rural, the  terrain is simple (non-
complex), and there is a  potential for building  downwash  with  some of the
nearby sources.

      No on-site meteorological data are available.    Therefore, the applicant
evaluates the meteorological  data collected at the National  Weather Service
station  located at the regional airport.   The applicant proposes the use of
                                     C.66

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
5 years of hourly observations from 1984 to 1988 for input to the dispersion
model, and the permitting agency approves their use for the modeling analyses.

      The applicant,  in consultation with the permitting agency,  determines
that terrain in the vicinity is essentially flat,  so that it is not necessary
to model  with receptor elevations.   (Consultation  with the reviewing agency
about receptor elevations is important since significantly different
concentration estimates may be obtained between flat terrain and  rolling
terrain modes.)

      A single-source model run for the auxiliary  boiler shows that its
estimated maximum ground-level concentrations of S02  and  N02 will  be less than
the significant air quality impact  levels for these two pollutants (see
Table C-4).   This  boiler  is  modeled  separately  from  the  two  main boilers
because there will  be a permit condition which restricts it from  operating at
the same time as the main boilers.   For particulate matter, the auxiliary
boiler's emissions  are modeled together with the fugitive emissions from the
proposed source to  estimate maximum ground-level PM-10 concentrations.   In
this case, too, the resulting ambient concentrations are less than the
significant ambient impact level for PM-10.  Thus,  operation of the auxiliary
boiler would not be considered to contribute to violations of any NAAQS or PSD
increment for S02,  particulate matter,  or  N02.  The auxiliary boiler is
eliminated from further modeling consideration because it will  not be
permitted to operate when either of the main boilers is in operation.

V.C.I  NAAQS ANALYSIS

      The next step is to estimate  total ground-level concentrations.   For the
S02 NAAQS  compliance  demonstration,  the applicant selects  a  coarse  receptor
grid of one-kilometer grid spacing  to identify the  area(s) of high impact
caused by the combined impact form  the proposed new source and nearby sources.
Through the coarse  grid run, the applicant finds that the area of highest
estimated concentrations will occur in the southwest quadrant.   In order to
determine the highest total concentrations, the applicant performs a second
model run for the southwest quadrant using a 100-meter receptor fine-grid.
                                     C.67

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

The appropriate concentrations from the fine-grid run is added to the
monitored background concentrations (including Source G's impacts) to
establish the total estimated S02  concentrations  for  comparison against the
NAAQS.  The results show maximum S02  concentrations  of:
            600 ug/n?,  3-hour average;
            155 ug/nf,  24-hour average;  and
            27 ug/nf, annual average.
Each of the estimated total impacts is within the concentrations allowed by
the NAAQS.

      For the N02NAAQS analysis, the  sources  identified  as  "nearby"  for  N02
are modeled with the proposed new source in two steps, in the same way as for
the S02  analysis: first,  using the  coarse (1-kilometer) grid network and,
second, using the fine (100-meter) grid network.   Appropriate concentration
estimates from these two modeling runs are then combined with the earlier
screening results for Refinery E and  the monitored background concentrations.
The highest average annual concentration resulting from  this approach  is 85
pg/m3,  which is  less than the N02 NAAQS of  100 |jg/m3> annual average.

      For the PM-10 NAAQS  analysis, the same  two-step  procedure  (coarse  and
fine receptor grid  networks)  is used  to locate the maximum  estimated  PM-10
concentration.   Recognizing that the  PM-10 NAAQS  is a  statistically-based
standard, the applicant  identifies the sixth  highest 24-hour concentration
(based on 5 full years of  24-hour concentration estimates)  for each  receptor
in the network.  For the annual averaging  time, the applicant averages the
5 years of  modeled  PM-10 concentrations at each receptor to determine  the 5-
year average concentration at each receptor.  To  these long- and short-term
results the applicant then added the  monitored background  reflecting  the
impacts of  sources  E and F, as well as surrounding area  and mobile  source
contributions.

      For the receptor network, the highest,  sixth-highest  24-hour
concentration is 127 pg/m3, and the highest 5-year average  concentration is
                                      C.68

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
38 |jg/m3.  These concentrations are  sufficient to demonstrate compliance with
the PM-10 NAAQS.

V.C.2  PSD Increment Analysis

      The applicant starts the increment analysis  by modeling  the increment-
consuming sources  of S02,  including  the  proposed new  source.  As  a
conservative first attempt,  a model  run  is made  using the maximum allowable
S02  emissions  changes  resulting from each  of the increment-consuming
activities identified in the increment inventory.    (Note that  this  is  not  the
same as modeling  the allowable emissions rate  for  each enti re  source.)   Using
a coarse (1-kilometer) receptor grid,  the area  downwind of the  source
conglomeration in  the southwest quadrant was  identified as the  area  where  the
maximum concentration increases have occurred.   The modeling is repeated  for
the southwest quadrant using a fine  (100-meter)  receptor grid  network.

      The results  of the fine-grid model run  show  that, in the  case  of  peak
concentrations downwind of the southwest source  conglomeration, the  allowable
S02  increment  will  be  violated  at  several  receptors  during the  24-hour
averaging period.   The violations  include significant ambient  impacts from  the
proposed power plant.   Further examination reveals  that Source  A in  the
southwest quadrant is the large contributor to  the  receptors where the
increment violations are predicted.   The applicant  therefore decides to refine
the analysis by using actual emissions increases rather than allowable
emissions increases where needed.

      It is  learned, and the permitting  agency  verifies, that  the increment-
consuming boiler  at Source A has  burned  refinery gas rather  than residual  oil
since start-up.  Consequently, the actual  emissions increase at Source  A's

boiler, based upon the use of refinery gas during  the preceding 2 years,  is
substantially less than the allowable  emissions  increase assumed from the  use
of residual  oil.   Thus, the applicant  models  the actual emissions increase  at
Source A and the  allowable emissions increase  for  the other  modeled  sources.
                                     C.69

-------
                                                                   DRAFT
                                                                   OCTOBER 1990

This time the modeling is repeated only  for  the  critical  time periods and
receptors.

      The maximum predicted S02 concentration increases over  the  baseline
concentration are as follows:
            302 yg/n?, 3-hour average;
            72 ug/nf, 24-hour average; and
            12 jjg/m3, annual average.
The revised modeling demonstrates  compliance  with  the S02  increments.   Hence,
no further S02 modeling is required for the increment  analysis.

      The full impact  analysis  for the  N02 increment  is  performed  by  modeling
Source F--the sole existing  N02 increment-consuming source—and the proposed
new source.  The modeled  estimates yield  a  maximum concentration increase of
21 M9/m3>  annual  average.  This increase will not  exceed the  maximum  allowable
increase of 25 pg/m3 for  N02.

      With the S02 and N02 increment portions of the analysis complete, the
only remaining part  is for  the  particulate  matter  (TSP) increments.  The
applicant must consider  the  effects of  the  four existing increment-consuming
sources (A, B, C, and  E)  in  addition  to ambient TSP concentrations caused by
the proposed  source  (including  the fugitive emissions).   The total increase
in TSP concentrations  resulting from  all  of these  sources is as follows:
      •     28 M9/m3>  24-hour average;  and
      •     13 pg/m3,  annual average.

The results demonstrate  that the  proposed source will not cause any violations
of the TSP increments.
VI.  BIBLIOGRAPHY

  1.   U.S. Environmental  Protection Agency.  Ambient Monitoring Guidelines  for
      Prevention of Significant Deterioration (PSD).   Research Triangle Park,
      NC.  EPA Publication  No.  EPA-450/4-87-007.  May 1987.
                                      C.70

-------
                                                                      DRAFT
                                                                      OCTOBER 1990

 2.   U.S.  Environmental Protection  Agency.  Guideline on Air Quality Models
      (Revised).  Office  of  Air Quality  Planning and Standards,  Research
      Triangle Park,  NC.  EPA  Publication No.  EPA-450/2-28-027R.
      July  1986.

 3.   U.S.  Environmental Protection  Agency.  On-Site Meteorological Programs
      Guidance  for Regulatory Modeling Applications.  Office  of Air Quality
      Planning and Standards,  Research Triangle  Park,  North Carolina.   EPA
      Publication  No.  EPA-450/4-87-013.  June  1987.

 4.   Finkelstein, P.L., D.A.  Mazzarella, T.J.  Lockhart, W.J.  King and J.H.
      White.   Quality Assurance Handbook for Air Pollution Measurement
      Systems,  Volume IV:   Meteorological Measurements.   U.S. Environmental
      Protection Agency, Research  Triangle  Park,  NC.   EPA Publication  No.  EPA-
      600/4-82-060.   1983.

 5.   U.S.  Environmental Protection  Agency.  Procedures for Emission Inventory
      Preparation, Volume I: Emission Inventory Fundamentals.   Research
             Triangle  Park, NC.  EPA  Publication  No.  EPA-450/4-81-026a.
      September  1981.

 6.   U.S.  Environmental Protection  Agency.  Procedures for Emission Inventory
      Preparation, Volume II: Point Sources.   Research  Triangle Park,  NC.
      EPA Publication  No. EPA-450/4-81-026b.   September 1981.

 7.   U.S.  Environmental Protection  Agency.  Procedures for Emission Inventory
      Preparation, Volume III: Area Sources.   Research  Triangle Park,  NC.
      EPA Publication  No. EPA-450/4-81-026c.   September 1981.

 8.   U.S.  Environmental Protection  Agency.  Procedures for Emissions
      Inventory Preparation,  Volume IV: Mobile Sources.   Research Triangle
      Park,  NC.  EPA  Publication No. EPA-450/4-81-026d.   September 1981.

 9.   U.S.  Environmental Protection  Agency.  Procedures for Emissions
      Inventory Preparation,  Volume V: Bibliography.  Research  Triangle
      Park,  NC.  EPA  Publication No. EPA-450/4-81-026e.   September 1981.

10.   U.S.  Environmental Protection  Agency.  Example Emission Inventory
      Documentation  For Post-1987 Ozone State Implementation Plans  (SIP's).
      Office of  Air  Quality  Planning and Standards,  Research Triangle  Park,
      NC.   EPA Publication No.  EPA-450/4-89-018.   October 1989.

11.   U.S.  Environmental Protection  Agency.  Procedures for Preparation of
      Emission Inventories  for Volatile Organic Compounds, Volume I: Emission
      Inventory Requirements Photochemeical Air Simulation Models.  Office of
      Air Quality  Planning and  Standards, NC.   EPA Publication  No.
      EPA-450/4-79-018.   September  1979.

12.   U.S.  Environmental Protection  Agency.  Screening Procedures for
      Estimating Air Quality Impact of Stationary Sources.  [Draft for Public
      Comment.]  Office of Air  Quality Planning  and  Standards,  Research
      Triangle Park,  NC.  EPA  Publication No.  EPA 450/4-88-010.   August 1988.

                                       C.71

-------
                                                                     DRAFT
                                                                     OCTOBER 1990

13.   U.S.  Environmental Protection  Agency.  Interim Procedures for Evaluation
      of Air Quality Models (Revised).  Office of Air Quality  Planning and
      Standards,  Research Triangle Park,  NC.  EPA Publication No.
      EPA-450/4-84-023.   September 1984.

14.   U.S.  Environmental Protection  Agency.  Interim Procedures for Evaluation
      of Air Quality Models: Experience with Implementation.   Office  of Air
      Quality  Planning and Standards,  Research Triangle  Park, NC.  EPA
      Publication No.   EPA-450/4-85-006.   July 1985.

15.   U.S.  Environmental Protection  Agency.  Guideline for  Determination of
      Good Engineering Practice Stack Height (Technical Support Document for
      the Stack Height Regulations), Revised.   Office of Air Quality  Planning
      and  Standards,  Research Triangle Park, NC.  EPA  Publication No.
      EPA  450/4-80-023R.  1985.   (NTIS No. PB 85-225241).

16.   U.S.  Environmental Protection  Agency.  Guideline for  Use of Fluid
      Modeling to Determine Good Engineering Practice  (GEP) Stack Height.
      Office  of Air Quality Planning and Standards,  Research Triangle  Park,
      NC.   EPA  Publication No.  EPA-450/4-81-003.  1981.   (NTIS No.
      PB  82-145327).

17.   Lawson,  Jr.,  R.E.  and W.H.  Snyder.   Determination of Good Engineering
      Practice Stack Height:  A Demonstration Study for a Power Plant.   U.S.
      Environmental  Protection  Agency, Research Triangle  Park,  NC.   EPA
      Publication No.  EPA 600/3-83-024.  1983.  (NTIS  No. PB 83-207407).

18.   Snyder,  W.H.,  and R.E.  Lawson, Jr.   Fluid Modeling Demonstration of Good
      Engineering-Practice Stack Height in Complex Terrain.   U.S.
      Environmental  Protection  Agency, Research Triangle  Park,  NC.   EPA
      Publication No.  EPA-600/3-85-022.  1985.  (NTIS  No. PB 85-203107).

19.   U.S.  Environmental Protection  Agency.  Workshop on Implementing the
      Stack Height Regulations (Revised).    U.S.  Environmental  Protection
      Agency,  Research Triangle Park,  NC.  1985.

20.   U.S.  Environmental Protection  Agency.  User's Guide to MOBILE4 (Mobile
      Source Emission Factor Model).  Office  of  Mobile Sources, Ann Arbor,  MI.
      EPA Publication No. EPA-AA-TEB-89-01.  February  1989.

21.   U.S.  Environmental Protection  Agency.  PM-10 SIP Development Guideline.
      Office  of Air Quality Planning and Standards,  Research Triangle  Park,
      NC.   EPA Publication No.  EPA-450/2-86-001.  June 1987.
                                       C.72

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
VII.   INDEX
    	   1-12,  14-26,  29-38,  40-44,  46-71,  73-75
actual  emissions	7,  8,  10,  11,  33,  47,  48,  63,  65,  66,  70
air quality analysis  .  .  .  1-3,  16,  19,  20,  22-24,  26,  29,  36,  38,  41,  43,  53
allowable	10,  44,  60,  61,  65,  66,  69,  70
ambient monitoring data	2,  16,  18-20,  61
area source	10,  34,  48,  49
background	3,  23,  31,  43,  46,  60,  68,  69
compliance demonstration  	  50,  51,  68
emissions inventory	30,  32-35,  46,  58,  60
GEP	11,  41-43,  62,  65,  73
impact area 	  18,  23,  26,  28-31,  33-35,  46,  51,  53-59,  61-63,  65,  66
meteorological  data	16,  22,  37,  38,  51,  67
mobile source	10,  31,  34,  36,  48,  49,  66,  69
modeling   2, 10,  12,  16,  18-24,  26,  29-31,  36,  37,  40-44,  46,  48,  50,  51,  53,
                                                      58,  60-62,  67-70,  73,  74
Modeling Guideline	2,  22,  24,  30,  31,  36,  37,  41,  43,  50,  53
Monitoring Guideline	2,  18,  19,  21,  22,  55
NAAQS .  1, 3-5, 18-21,  23,  24,  29-31,  36,  40,  41,  43,  44,  50,  51,  53,  55,  56,
                                                              58,  60-62,  67-69
nearby source	31,  60,  61
net emissions increase	1,3,  16,  23,  26,  50,  51
non-criteria pollutant  	  20,  24
offset	51,  52
offsets	21
PSD increment  1,  3, 7,  29,  30,  33,  34,  36,  44,  47,  48,  50-52,  55,  58,  60,  63,
                                                                    64,  67,  69
screening area	32,  34,  57-59
secondary emissions	24,  31,  55,  58
significant ambient impact	24,  26,  27,  35,  50,  51,  67
significant monitoring  	   16-18,  21,  55
stack height	11,  41-43,  48,  53,  62,  65,  73,  74
                                     C.73

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER D
                         ADDITIONAL IMPACTS ANALYSIS
I.   INTRODUCTION

      All  PSD permit applicants  must prepare an  additional  impacts analysis
for each pollutant subject  to regulation  under the  Act.   This  analysis
assesses the impacts of air,  ground  and water pollution  on  soils,  vegetation,
and visibility caused by any  increase  in  emissions  of  any regulated pollutant
from the source or modification  under  review, and from associated  growth.

      Other impact analysis requirements  may also be imposed  on  a  permit
applicant  under local,  State  or  Federal laws which  are outside the PSD
permitting process.  Receipt  of  a PSD  permit does not  relieve  an applicant
from the responsibility to  comply fully with such requirements.   For example,
two Federal laws which  may  apply on  occasion are the Endangered Species Act
and the National Historic Preservation Act.   These  regulations may require
additional analyses (although not as part of the PSD permit)  if  any federally-
listed rare or endangered species,  or  any site  that is included  (or is
eligible to be included) in the  National  Register of Historic  Sites, are
identified in the source's  impact area.

      Although each applicant for a  PSD permit  must perform an additional
impacts analysis, the depth of the analysis  generally  will  depend on existing
air quality, the quantity of  emissions, and  the  sensitivity of local soils,
vegetation, and visibility  in the source's impact  area.   It is important  that
the analysis fully document all  sources of information,  underlying
assumptions, and any agreements  made as a part  of  the  analysis.
                                      D.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Generally,  small  emissions increases in most areas will  not have adverse
impacts on soils,  vegetation,  or visibility.   However,  an additional  impacts
analysis still  must be  performed.   Projected  emissions  from both the  new
source or modification  and emissions from associated residential, commercial,
or industrial  growth are combined  and modeled for the impacts  assessment
analysis.  While  this section  offers applicants a general approach to an
additional impacts analysis,  the analysis does not lend itself to a "cookbook"
approach.
                                     D.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.   ELEMENTS OF THE  ADDITIONAL  IMPACTS  ANALYSIS
      The additional  impacts  analysis  generally  has  three  parts,  as  follows:
      (1)   growth;
      (2)   soil  and  vegetation  impacts;  and
      (3)   visibility impairment.

II.A.   GROWTH ANALYSIS

      The elements of the growth analysis include:
      (1)   a projection of the  associated5 industrial, commercial, and
            residential  source growth  that will  occur  in  the  area due  to  the
            source;  and
      (2)   an estimate  of the air  emissions  generated by  the above  associated
            industrial,  commercial,  and residential  growth.

      First, the applicant needs to assess the availability  of residential,
commercial, and industrial services existing  in  the  area.   The next  step  is  to
predict how much new  growth is likely  to occur to support  the source or
modification under review.  The  amount of residential  growth  will depend  on
the size of the available work force,  the number of  new employees, and the
availability of housing  in the area.   Industrial growth is growth in those
industries providing  goods and services,  maintenance faci1ities,and  other
large industries necessary for the  operation  of  the  source or modification
under review.  Excluded  from consideration as associated  sources  are mobile
sources and temporary sources.

      Having completed this portrait of expected growth,  the applicant then
begins developing an  estimate of the secondary air pollutant emissions which
would likely result from this permanent residential, commercial,  and
      5   Associated growth  is growth that comes about as the result of the
construction or modification of a source, but is not a  part of that source.
It does not include the growth projections  addressed by 40 CFR
51.166(n)(3)(ii) and 40 CFR 52.21(n)(2)(ii),  which have been called non-
associated growth.  Emissions attributable  to associated growth are classified
as secondary emissions.
                                      D.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
industrial  growth.   The applicant should generate emissions estimates by
consulting  such sources as manufacturers specifications and guidelines, AP-42,
other PSD applications, and comparisons with existing sources.

      The applicant next combines the secondary air pollutant emissions
estimates for the associated growth with the estimates of emissions that  are
expected to be produced directly by the proposed source or modification.   The
combined estimate serves as the input to the air quality modeling analysis,
and the result is a prediction of the ground-level  concentration of pollutants
generated by the source and any associated growth.

II.B.  AMBIENT AIR QUALITY ANALYSIS

      The ambient air quality analysis projects the air quality which will
exist in the area of the proposed source or modification during construction
and after it begins operation.  The applicant first combines the air pollutant
emissions estimates for the associated growth with  the estimates of emissions
from the proposed source or modification.   Next, the projected  emissions  from
other sources in the area which have been permitted (but are not yet in
operation)  are included as inputs to the modeling analysis.  The applicant
then models the combined emissions estimate and adds the modeling analysis
results to  the background air quality to arrive at  an estimate  of the total
ground-level concentrations of pollutants which can be anticipated as a  result
of the construction and operation of the proposed source.

II.C.  SOILS AND VEGETATION ANALYSIS

      The analysis of soil and vegetation air pollution impacts should be
based on an inventory of the soil and vegetation types found in the impact
area.  This inventory should include all vegetation with any commercial  or
recreational value, and may be available from conservation groups, State
agencies, and universities.

      For most types of soil and vegetation, ambient concentrations of
criteria pollutants below the secondary national ambient air quality standards
                                      D.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
(NAAQS) will  not result in harmful  effects.   However,  there are sensitive
vegetation species (e.g.,  soybeans  and alfalfa)  which  may be harmed by long-
term exposure to low ambient air concentrations  of regulated pollutants for
which are no NAAQS.   For example,  exposure of sensitive plant species to 0.5
micrograms per cubic meter of fluorides (a regulated,  non-criteria pollutant)
for 30 days has resulted in significant foliar necrosis.

      Good references for  applicants and reviewers alike  include the EPA Air
Quality Criteria Documents, a U.S.  Department of the Interior document
entitled Impacts of Coal-Fired Plants on Fish, Wildlife,  and Their Habitats,
and the U.S.  Forest  Service document, A Screening Procedure to Evaluate Air
Pollution Effects on Class I Wilderness Areas.  Another source of reference
material is the National Park Service report, Air Quality in the National
Parks, which lists numerous studies on the biological  effects of air pollution
on vegetation.

II.D.  VISIBILITY IMPAIRMENT ANALYSIS

      In the visibility impairment analysis, the applicant is especially
concerned with impacts that occur within the area affected by applicable
emissions.  Note that the visibility analysis required here is distinct from
the Class I area visibility analysis requirement.  The suggested components of
a good visibility impairment analysis are:
                                      D.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

            a determination of the visual  quality of the area,
            an initial  screening of emission sources to assess  the possibility
            of visibility impairment,  and
            if warranted, a more in-depth  analysis involving computer models.
      To successfully complete a visibility impairments analysis,  the
applicant is referred to an EPA document entitled Workbook for Estimating
Visibility Impairment or its projected replacement,  the Workbook for Flume
Visual Impact Screening and Analysis.   In this workbook,  EPA outlines a
screening procedure designed to expedite the analysis of  emissions impacts on
the visual  quality of an area.  The workbook was designed for Class I area
impacts, but the outlined procedures are generally applicable to other areas
as well.  The following sections are a brief synopsis of  the screening
procedures.

II.D.I.  SCREENING PROCEDURES:  LEVEL 1

      The Level  1 visibility screening analysis is a series of conservative
calculations designed to identify those emission sources  that have little
potential of adversely affecting visibility. The VISCREEN model  is recommended
for this first level  screen.  Calculated values relating  source emissions to
visibility  impacts are compared to a standardized screening value.  Those
sources with calculated values greater than the screening criteria are judged
to have potential visibility impairments.  If potential visibility impairments
are indicated, then the Level  2 analysis is undertaken.

II.D.2.  SCREENING PROCEDURES:  LEVEL 2

      The Level  2 screening procedure is similar to  the Level 1 analysis in
that its purpose is to estimate impacts during worst-case meteorological
conditions;  however,  more specific information regarding  the source,
topography,  regional  visual range, and meteorological conditions is assumed to
be available.  The analysis may be performed with the aid of either hand
                                     D.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
calculations,  reference tables,  and figures,  or a  computer-based visibility
model  called "PLVWE II.

II.D.3.  SCREENING PROCEDURES:   LEVEL 3
      If the Levels 1 and 2 screening analyses indicated the possibility  of
visibility impairment, a  still  more detailed  analysis is undertaken in Level  3
with the aid of the plume visibility model  and meteorological  and other
regional data.  The purpose of  the Level  3  analysis is to provide an accurate
description of the magnitude and frequency  of occurrence of impact.

      The procedures for  utilizing the plume  visibility model  are described in
the document User's Manual for the Plume Visibility Model, which is available
from EPA.

II.E.   CONCLUSIONS

      The additional impacts analysis consists of a growth analysis, a soil
and vegetation analysis,  and a  visibility impairment analysis.  After
carefully examining all data on additional  impacts, the reviewer must decide
whether the analyses performed  by a particular applicant are satisfactory.
General criteria for determining the completeness and adequacy of the analyses
may include the following:

      •     whether the applicant has presented a clear and accurate portrait
            of the soils, vegetation, and visibility in the proposed impacted
            area;
      •     whether the applicant has provided adequate documentation of the
            potential emissions impacts on soils, vegetation, and visibility;
            and
      •     whether the data and conclusions are presented in a logical manner
            understandable by the affected community and  interested public.
                                      D.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.  ADDITIONAL IMPACTS ANALYSIS EXAMPLE
      Sections D.I and D.2 outlined,  in general  terms,  the elements and
considerations found in a successful  additional  impacts analysis.   To
demonstrate how this analytic process would be applied  to a specific
situation, a hypothetical case has been developed for a mine mouth power
plant.  This section will summarize how an additional impacts analysis would
be performed on that facility.

III.A. EXAMPLE BACKGROUND INFORMATION

      The mine mouth power plant consists of a power plant and an  adjoining
lignite mine, which serves as the plant's source of fuel.  The plant is
capable of generating 1,200 megawatts of power,  which is expected  to supply a
utility grid (little is projected to  be consumed locally).   This  project is
located in a sparsely populated agricultural area in the southwestern United
States.  The population center closest to the plant is  the town of
Clarksville, population 2,500, which  is located  20 kilometers from the plant
site.  The next significantly larger  town is Milton, which is 130  kilometers
away and has a population of 20,000.   The nearest Class I area is  more than
200 kilometers away from the proposed construction.  The applicant has
determined that within the area under consideration there are no National or
State forests, no areas which can be  described as scenic vistas, and no points
of special historical  interest.

      The applicant has estimated that construction of  the power plant and
development of the mine would require an average work force of 450 people over
a period of 36 months.  After all construction is completed, about 150 workers
will be needed to operate the facilities.
                                      D.8

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.B.   GROWTH ANALYSIS
      To perform a growth analysis of this project,  the applicant  began  by
projecting the growth associated with the operation  of the project.

III.B.I.  WORK FORCE

      The applicant consulted the State employment office, local  contractors,
trade union officers, and other sources for  information on labor  capability
and availability, and made the following determinations.

      Most of the 450 construction jobs available will be filled  by  workers
commuting to the site, some from as far away as Milton.  Some workers and
their families will move to Clarksville for the duration of the construction.
Of the permanent jobs associated with the project, about 100 will  be filled by
local workers.  The remaining 50 permanent positions will be filled  by
nonlocal employees, most of whom are expected to relocate to the  vicinity of
Clarksville.

III.B.2.  HOUSING

      Contacts with local government housing authorities and realtors, and a
survey of the classified advertisements in the local newspaper indicated that
the predominant housing unit in the area is the single family house  or mobile
home, and the easy availability of mobile homes and lots provides  a  local
capacity for quick expansion.  Although there will be some emissions
associated with the construction of new homes, these emissions will  be
temporary and, because of the limited numbers of new homes expected, are
considered to be insignificant.
                                      D.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.B.3.   INDUSTRY
      Although new industrial  jobs often lead to new support jobs as well
(i.e., grocers, merchants, cleaners,  etc.), the small  number of new people
brought into the community through employment at the plant is not expected to
generate commercial  growth.  For example,  the proposed source will  not require
an increase in small  support industries (i.e., small foundries or rock
crushing operations).

      As a result of the relatively self-contained nature of mine mouth plant
operations, no related industrial  growth is expected to accompany the
operation of the plant.  Emergency and full maintenance capacity is contained
within the power-generating station.   With no associated commercial or
industrial growth projected, it then  follows that there will be no growth-
related air pollution  impacts.
                                     D.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.C.   SOILS AND VEGETATION
      In preparing a soils and vegetation  analysis,  the applicant  acquired  a
list of the soil  and vegetation types  indigenous  to  the impact  area.   The
vegetation is dominated by pine and  hardwood trees  consisting  of  loblolly
pine, blackjack oak, southern red oak,  and sweet  gum.   Smaller  vegetation
consists of sweetbay and holly.  Small  farms are  found west of  the forested
area.  The principal commercial crops  grown in  the  area are soybeans,  corn,
okra, and peas.  The soils range in  texture from  loamy sands to sandy  clays.
The principal soil is sandy loam consisting of  50 percent sand, 15 percent
silt, and 35 percent clay.

      The applicant, through a literature  search  and contacts  with the local
universities and experts on local soil  and vegetation, determined  the
sensitivity of the various soils and vegetation types  to each  of  the
applicable pollutants that will be emitted by the facility in  significant
amounts.  The applicant then correlated this information with  the  estimates of
pollutant concentrations calculated  previously  in the  air quality  modeling
analysi s.

      After comparing the predicted  ambient air concentrations  with soils and
vegetation in the impact area, only  soybeans proved to be potentially
sensitive.  A more careful examination of  soybeans  revealed that  no adverse
effects were expected at the low concentrations of  pollutants  predicted by  the
modeling analysis.  The predicted sulfur dioxide  (S02)  ambient  air
concentration is lower than the level  at which  major S02 impacts on soybeans
have been demonstrated (greater than 0.1 ppm for  a  24-hour period).

       Fugitive emissions emitted from the  mine  and  from coal pile storage will
be deposited on both the soil and leaves of vegetation in the immediate area
of the plant and mine.  Minor leaf necrosis and lower  photosynthetic  activity
is expected, and over a period of time the vegetation's community structure
may  change.  However, this impact occurs only in  an extremely limited,
nonagricultural area very near the emissions site and  therefore is not
considered to be significant.
                                     D.ll

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      The potential  impact of limestone preparation and storage also must  be
considered.   High relative humidity may produce a crusting effect of the
fugitive limestone emissions on nearby vegetation.   However,  because of BACT
on limestone storage piles,  this impact is slight and only occurs very near
the power plant site.   Thus, this impact is judged  insignificant.
                                     D.12

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.D.   VISIBILITY ANALYSIS
      Next, the applicant performed a visibility analysis,  beginning with a
screening procedure similar to that outlined in the EPA document Workbook for
Estimating Visibility Impairment.   The screening procedure  is divided into
three levels. Each level  represents a screening technique for an increasing
possibility of visibility impairment.  The applicant executed a Level 1
analysis involving a series of conservative tests that permitted the analyst
to eliminate sources having little potential for adverse or significant
visibility impairment.  The applicant performed these calculations for various
distances from the power plant.  In all  cases, the results  of the calculations
were numerically below the standardized screening criteria.  In preparing the
suggested visual and aesthetic description of the area under review, the
applicant noted the absence of scenic vistas.  Therefore, the applicant
concluded that no visibility impairment was expected to occur within the
source impact area and that the Level 2 and Level 3 analyses were unnecessary.

III.E.  EXAMPLE CONCLUSIONS

      The applicant completed the additional impacts analysis by documenting
every element of the analysis and preparing the report in straightforward,
concise language.  This step is important, because a primary intention of the
PSD permit process is to generate public information regarding the potential
impacts of pollutants emitted by proposed new sources or modifications on
their impact areas.
                                     D.13

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

NOTE:  This example provides only the highlights of an additional impacts
analysis for a hypothetical mine mouth power plant.   An actual analysis would
contain much more detail, and other types of facilities might produce more
growth and more, or different, kinds of impacts.  For example, the
construction of a large manufacturing plant could easily generate air quality-
related growth impacts, such as a large influx of workers into an area and the
growth of associated industries.  In addition, the existence of particularly
sensitive forms of vegetation, the presence of Class I areas, and the
existence of particular meteorological conditions would require an analysis of
much greater scope.
                                     D.14

-------
IV.   BIBLIOGRAPHY
                                                                  DRAFT
                                                                  OCTOBER  1990
1.
2.
3.
4.
5.
Dvorak, A.J.,  et al,
WiIdlife, and thei r
Illinois.  Fish and
March  1978.
  Impacts of Coal-fired Power Plants on Fish,
Habitats.  Argonne National  Laboratory.  Argonne,
Wildlife Service Publication No.  FWS/OBS-78/29.
A Screening Procedure to Evaluate Air Pollution Effects on Class I
Wilderness Areas, U.S. Forest Service General Technical Report RM-168.
January, 1989.
Latimer, D.A. and R.G. Iveson.
Impairment.  U.S. Environmental
Park, N.C.  EPA Publication No.
            Workbook for Estimating Visibility
            Protection Agency.  Research Triangle
            EPA-450/4-80-031.  November, 1980.
Air Quality in the National Parks.  National Park Service.  Natural
Resources Report 88-1.  July, 1988.

Seigneur, C., et al.  User's Manual for the Plume Visibility Model
(Pluvue II).  U.S. Environmental Protection Agency.  Research Triangle
Park, N.C.  EPA Publication No. 600/8-84-005.  February 1984.
                                     D.15

-------
                                                                  DRAFT
                                                                  OCTOBER  1990
                                  CHAPTER  E
                          CLASS  I AREA  IMPACT ANALYSIS
I.  INTRODUCTION
      Class I areas are areas of special national  or regional  natural, scenic,
recreational, or historic value for which the PSD regulations  provide special
protection.  This section identifies Class I  areas,  describes  the protection
afforded them under the Clean Air Act (CAA),  and discusses the procedures
involved in preparing and reviewing a permit  application for a proposed source
with potential Class I area air quality impacts.
                                      E.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.   CLASS I AREAS AND THEIR PROTECTION
      Under the CAA, three kinds of Class I  areas either have been,  or may be,
designated.  These are:

      •   mandatory Federal Class I areas;
      •   Federal Class I areas; and
      •   non-Federal Class I areas.

Mandatory Federal Class I areas are those specified as Class I by the CAA on
August 7, 1977, and include the following areas in existence on that date:

      •     international parks;
      •     national wilderness areas (including certain national wildlife
            refuges, national  monuments and national  seashores) which exceed
            5,000 acres in size;
      •     national memorial  parks which exceed 5,000 acres in size; and
      •     national parks which exceed 6,000 acres in size.
Mandatory Federal Class I areas, which may not be reelassified, are listed by
State in Table E-l.  They are managed either by the Forest Service (FS),
National Park Service (NPS), or Fish and Wildlife Service (FWS).

      The States and Indian governing bodies have the authority to designate
additional Class I areas.  These Class I areas are not "mandatory" and may be
reclassified if the State or Indian governing body chooses.  States may
reclassify either State or Federal lands as Class I,  while Indian governing
bodies may reclassify only lands within the exterior boundaries of their
respective reservations.
                                      E.2

-------
                                                                    DRAFT
                                                                    OCTOBER 1990
                      TABLE  E-l.   MANDATORY CLASS I AREAS
State/Type/Area    Managing Agency
               State/Type/Area   Managing Agency
Alabama
 National Wilderness Areas
 Sipsey

Alaska
 National Parks
 Oenali

 National Wilderness Areas
 Bering  Sea
 Simeonof
 Tuxedni

Arizona
 National Parks
 Grand Canyon
 Petrified Forest

 National Wilderness Areas
 Chiricahua  Nat. Monu.
 Chi ricahua
 Gali uro
 Mazatzal
 Mt. Baldy
 Pine Mountain
 Saguaro Nat. Monu.
 Sierra  Ancha
 Superstition
 Sycamore Canyon

Arkansas
 National Wilderness Areas
 Caney Creek
 Upper Buffalo

California
 National Parks
 Kings Canyon
 Lassen  Volcanic
 Redwood
 Sequoia
 Yosemite
FS
NPS
FWS
FWS
FWS
NPS
NPS
NPS
FS
FS
FS
FS
FS
NPS
FS
FS
FS
FS
FS
NPS
NPS
NPS
NPS
NPS
   California  -  Continued
National Wilderness Areas
    Agua Tibia                 FS
    Caribou                    FS
    Cucamonga                  FS
  Desolation                   FS
    Dome Land                  FS
    Emigrant                   FS
    Hoover                     FS
    John Muir                  FS
    Joshua Tree                NPS
    Kaiser                     FS
    Lava Beds                  NPS
    Marble Mountain            FS
    Minarets                   FS
    Mokelumne                  FS
    Pinnacles                  NPS
    Point Reyes                NPS
    San Gabriel                FS
    San Gorgonio              FS
    San Jacinto                FS
    San Rafael                 FS
    South Warner              FS
    Thousand Lakes             FS
    Ventana                    FS
    Yolla Bolly-Middle-Eel     FS

   Colorado
    National Parks
    Mesa Verde                 NPS
    Rocky Mountain             NPS

    National Wilderness Areas
    Black Canyon of  the Gunn. NPS
    Eagles Nest                FS
    Flat Tops                  FS
    Great Sand Dunes          NPS
    La Garita                  FS
    Maroon Bells Snowmass     FS
    Mount Zirkel               FS
    Rawah                      FS
    Weminuche                  FS
    West Elk                   FS
                                       E.3

-------
                              TABLE E-l.   Continued
                                                                     DRAFT
                                                                     OCTOBER 1990
State/T.ype/Area    Managing Agency
                      State/Type/Area    Managing Agency
Florida
 National Parks
 Everglades               NPS
 National Wilderness Areas
 Bradwell  Bay             FS
 Chassahowitzka           FWS
 Saint Marks              FWS

Georgia
 National Wilderness Areas
 Cohutta                  FS
 Okefenokee               FWS
 Wolf Island              FWS
Hawaii
 National Parks
 Haleakala
 Hawaii  Volcanoes
NPS
NPS
Idaho
 National Parks
 Yellowstone (See Wyoming)

 National Wilderness Areas
 Craters  of the Moon     NPS
 Hells  Canyon (see Oregon)
 Sawtooth                FS
 Selway-Bitterroot       FS

Kentucky
 National Parks
 Mammoth  Cave            NPS

Louisiana
 National Wilderness Areas
 Breton                  FWS

Maine
 National Parks
 Acadia                  NPS

 National Wilderness Areas
 Moosehorn               FWS
Michigan
 National Parks
 Isle  Royale            NPS
 National Wilderness Areas
 Seney                   FWS

Minnesota
 National Parks
 Voyageurs               NPS

 National Wilderness Areas
 Boundary Waters Canoe Ar.  FS

Missouri
 National Wilderness Areas
 Hercules-Glades        FS
 Mingo                   FWS
                         Montana
                          National Parks
                          Glacier
                          Yellowstone (See
                          NPS
                   Wyoming)
                          National Wilderness Areas
                          Anaconda-Pintlar        FS
                          Bob Marshall             FS
                          Cabinet  Mountains       FS
                          Gates  of the Mountain   FS
                          Medicine Lake           FWS
                          Mission  Mountain        FS
                          Red Rock Lakes          FWS
                          Scapegoat               FS
                          Selway-Bitterroot  (see  Idaho)
                          U.L.  Bend               FWS

                         Nevada
                          National Wilderness Areas
                          Jarbridge               FS

                         New Hampshire
                          National Wilderness Areas
                          Great Gulf              FS
                          Presidential Range-Dry  R.FS
                                        E.4

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
                              TABLE E-l.  Continued
State/Type/Area    Managing Agency
New Jersey
 National Wilderness Areas
 Briganti ne
New Mexico
 National Parks
 Carlsbad Caverns

 National Wilderness Areas
 Bandelier
 Bosque  del  Apache
 Gil a
 Pecos
 Salt Creek
 San Pedro Parks
 Wheeler Peak
 White  Mountain

North Carolina
 National Parks
 Great  Smoky Mountains
 FWS
 NPS
 NPS
 FWS
 FS
 FS
 FWS
 FS
 FS
 FS
(see Tennessee)
 National Wilderness Areas
 Joyce  KiImer-Slickrock FS
 Linville Gorge          FS
 Shining  Rock            FS
 Swanquarter             FWS

North Dakota
 National Parks
 Theodore Roosevelt     NPS

 National Wilderness Areas
 Lostwood                FWS

Oklahoma
 national Wilderness Areas
 Wichita  Mountains       FWS

Oregon
 National Parks
 Crater Lake             NPS
State/Type/Area    Managing Agency

   Oregon  -  Continued
    National Wilderness Areas
    Diamond  Peak            FS
    Eagle  Cap               FS
    Gearhart Mountain       FS
    Hells  Canyon            FS
    Kalmiopsis              FS
    Mountain Lakes         FS
    Mount  Hood              FS
    Mount  Jefferson        FS
    Mount  Washington       FS
    Strawberry Mountain    FS
    Three  Sisters           FS

   South Carolina
    National Wilderness Areas
    Cape Remain             FWS

   South Dakota
    National Parks
    Wind Cave               NPS

    National Wilderness Areas
    Badlands                NPS

   Tennessee
    National Parks
    Great  Smoky Mountains  NPS

    National Wilderness Areas
    Joyce  KiImer-Slickrock
             (see North Carolina)
                          Texas
                           National Parks
                           Big Bend
                           Guadalupe Mountain
                            NPS
                            NPS
                                       E.5

-------
                                                                     DRAFT
                                                                     OCTOBER 1990
                             TABLE  E-l.*  Continued
State/T.ype/Area    Managing Agency
State/Type/Area    Managing Agency
Utah
 National Parks
 Arches                  NPS
 Bryce Canyon            NPS
 Canyonlands             NPS
 Capitol Reef            NPS
Vermont
 National Wilderness Areas
 Lye Brook               FS
Virgin Islands
 National Parks
 Virgin  Islands          NPS

Virginia
 National Parks
 Shenandoah              NPS

 National Wilderness Areas
 James River  Face       FS

Washington
 National Parks
 Mount Rainier          NPS
 North Cascades          NPS
 Olypmic                 NPS

 National Wilderness Areas
 Alpine  Lakes            FS
 Glacier  Peak            FS
 Goat Rocks              FS
 Mount Adams             FS
 Pasayten                FS
          West Virginia
    National Wilderness Areas
    Dolly  Sods               FS
    Otter  Creek             FS

   Wisconsin
    National Wilderness Area
    Rainbow  Lake            FWS

   Wyoming
    National Parks
    Grand  Teton             NPS
    Yellowstone             NPS

    National Wilderness Areas
    Bridger                  FS
    Fitzpatrick             FS
    North  Absaroka          FS
    Teton                    FS
    Washakie                FS

   International Parks
    Roosevelt-Campobello    n/a
                                        E.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Any Federal  lands a State so reelassifies are considered Federal Class I
areas.  In  so  far  as these areas  are  not  mandatory  Federal  Class II  areas,
these areas  may be again reclassified  at some later date,   (there are as  of
the date of  this  manual, no State-designated Federal  Class I  areas.)  However,
in accordance with the CAA the following areas may be redesignated only as
Class I or II.

            an area which as of August 7, 1977, exceeded 10,000 acres in  size
            and was a national monument, a national primitive area, a national
            preserve, a national recreation area,  a national  wild and scenic
            river, a national  wildlife refuge, a national  lakeshore or
            seashore; and

            a national park or national  wilderness area established after
            August 7, 1977, which  exceeds 10,000 acres in size.

      Federal Class I areas are managed by the Forest Service (FS), the
National Park Service (NPS), or the Fish and Wildlife Service (FWS).

      State  or Indian lands reclassified as Class  I are considered non-Federal
Class I areas.  Four Indian Reservations which are non-Federal  Class I  areas
are the Northern  Cheyenne, Fort Peck,  and Flathead Indian Reservations  in
Montana, and the  Spokane Indian Reservation in Washington.

      One way in  which air quality degradation is  limited in  all Class  I  areas
is by stringent limits defined by  the  Class I increments for  sulfur dioxides,
particulate  matter [measured as total  suspended particulate (TSP)], and
nitrogen dioxide.  As explained previously in Chapter C, Section II.A,  PSD
increments are the maximum increases in ambient pollutant concentrations
allowed over the  baseline concentrations.  In addition, the FLM of each Class
I area is charged with the affirmative responsibility to protect that area's
unique attributes, expressed generically as air quality related values
(AQRV's).   The FLM, including the  State or Indian  governing body, where
applicable,  is responsible for defining specific AQRV's for an  area and for
establishing the  criteria to determine an adverse  impact on the AQRV's.
                                      E.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Congress intended the Class  I  increments  to  serve  a  special  function  in
protecting the air quality and other unique  attributes  in  Class  I  areas.   In
Class I  areas, increments are a means of determining  which party,  i.e.,  the
permit applicant or the FLM,  has the burden  of  proof  for demonstrating  whether
the proposed source would not cause  or contribute  to  a  Class  I  increment
violation, the FLM may demonstrate to EPA,  or the  appropriate permitting
authority, that the emissions from a proposed source  would have  an adverse
impact on any AQRV's established for a particular  Class  I  area.

      If, on the other hand,  the proposed source would  cause  or  contribute  to
a Class  I increment violation, the burden of proof is on the  applicant  to
demonstrate to the FLM that the emissions from  the source  would  have  no
adverse  impact on the AQRV's.  These concepts are  further  described in  Section
III.d of this chapter.

II.A.  CLASS I INCREMENTS

      The Class I increments for total suspended particulate  matter (TSP),
S02,  and N02 are listed in Table E-2.  Increments are the maximum increases in
ambient  pollutant concentrations allowed over baseline concentrations.   Thus,
these increments should limit increases in ambient pollutant  concentrations
caused by new major sources or major modifications near Class I  areas.
Increment consumption analyses for Class I areas should include not only
emissions from the proposed source,  but also include increment-consuming
emissions from other sources.
                                      E.l

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
                    TABLE  E-2.   CLASS  I  INCREMENTS (ug/m3)
Pollutant                           Annual             24-hour        3-hour
Sulfur dioxide                        2                   5              25
Particulate matter (TSP)              5                  10              N/A
Nitrogen dioxide                      2.5                N/A            N/A
                                      E.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.B.   AIR QUALITY-RELATED VALUES  (AQRV's)

      The AQRV's are those attributes  of  a  Class  I  area  that  deterioration  of
air  quality may adversely affect.   For example, the Forest  Service  defines
AQRV's as "features or properties  of a Class  I  area that made it  worthy  of
designation as a wilderness and that could  be adversely  affected  by air
pollution."  Table E-3 presents an extensive  (though not exhaustive)  list of
example AQRV's and the parameters  that may  be used  to detect  air  pollution-
caused changes in them.  Adverse impacts  on AQRV's  in Class I areas may  occur
even if pollutant concentrations do not exceed  the  Class I  increments.

      Air quality-related values generally  are  expressed in broad terms.  The
impacts of increased pollutant levels  on  some AQRV's are assessed by measuring
specific parameters that reflect the AQRV's status.  For instance,  the
projected impact on the presence and vitality of  certain species  of animals or
plants may indicate the impact of  pollutants  on AQRV's associated with  species
diversity or with the preservation of  certain endangered species.  Similarly,
an AQRV associated with water quality  may be  measured by the  pH of a water
body or by the level of certain nutrients in  the  water.   The  AQRV's of  various
Class I areas differ, depending on the purpose  and  characteristics of a
particular area and on assessments by  the area's  FLM.  Also,  the  concentration
at which a pollutant adversely impacts an AQRV  can  vary between Class I  areas
because the sensitivity of the same AQRV often  varies between areas.

       When a proposed major source's  or major  modification's modeled
emissions may affect a Class I area, the applicant  analyzes the source's
anticipated impact on visibility and provides the information needed to
determine its effect on the area's other AQRV's.   The FLM's have  established
criteria for determining what constitutes an "adverse" impact.  For example,
the NPS
                                     E.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
TABLE E-3.  EXAMPLES OF AIR QUALITY-RELATED VALUES AND POTENTIAL
                         AIR POLLUTION-CAUSED CHANGES
Air Quality Related Value
Potential Air Pollution-Caused Changes
Flora and Fauna
Growth, Mortality, Reproduction,
Diversity, Visible Injury, Succession,
Productivity, Abundance
Water
Total  Alkalinity, Metals Concentration,
Anion and Cation Concentration, pH,
Dissolved Oxygen
Vi sibi1ity
Contrast, Visual Range, Coloration
Cultural-Archeological
  and Pal eontological
Decomposition Rate
Odor
      Odor
                                     E.ll

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
defines an "adverse impact" as "any impact that:   (1)  diminishes  the area's
national  significance;  (2)  impairs the structure  or  functioning  of ecosystems;
or (3)  impairs the quality  of the visitor experience."  If an  FLM determines,
based on  any information available, that a source will adversely  impact AQRV's
in a Class I area, the  FLM  may recommend that the reviewing agency deny
issuance  of the permit,  even in cases where no applicable increments would be
exceeded.
II.C.  FEDERAL LAND MANAGER

      The FLM of a Class I area has an affirmative responsibility to protect
AQRV's for that area which may be adversely affected by cumulative ambient
pollutant concentrations.  The FLM is responsible for evaluating a source's
projected impact on the AQRV's and recommending that the reviewing agency
either approve or disapprove the source's permit application based on
anticipated impacts.  The FLM also may suggest changes or conditions on a
permit.  However, the reviewing agency makes the final decisions on permit
issuance.  The FLM also advises reviewing agencies and permit applicants about
other FLM concerns, identifies AQRV's and assessment parameters for permit
applicants, and makes ambient monitoring recommendations.

      The U.S. Departments of Interior (USDI) and Agriculture (USDA) are the
FLM's responsible for protecting and enhancing AQRV's in Federal Class I
areas.  Those areas in which the USDI has authority are managed by the NPS and
the  FWS, while the USDA Forest Service separately reviews impacts on Federal
Class I national wildernesses under its jurisdiction.  The PSD regulations
specify that the reviewing authority furnish written notice of any permit
application for a proposed major stationary source or major modification, the
emissions from which may affect a Class I area, to the FLM and the official
charged with direct responsibility for management of any lands within the
area.  Although the Secretaries of Interior and Agriculture are the FLM's for
Federal Class I areas, they have delegated permit review to specific elements
within each department.  In the USDI, the NPS Air Quality Division reviews PSD
permits for both the NPS and FWS.  Hence, for sources that may affect wildlife

                                     E.12

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
refuges,  applicants and reviewing agencies should contact and send
correspondence to both the NPS and the wildlife refuge manager located at the
refuge.   Table E-4 summarizes the types of Federal Class I areas managed by
each FLM.  In the USDA, the Forest Service has delegated to its regional
offices  (listed in Table E-5) the responsibility for PSD permit application
revi ew.
                                     E.13

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                      TABLE E-4.  FEDERAL  LAND MANAGERS
Federal  Land
  Manager
                 Federal  Class  I  Areas
                       Managed
                                     Address
National  Park
Service (USDI)
              National  Memorial  Parks
              National  Monuments1
              National  Parks
              National  Seashores1
                              Air Quality Division
                              National  Park  Service
                              P.O. Box 25287
                              Denver,  CO  80225-0287
                      -  Air
Fish and Wildlife    National
Service (USDI)       Refuges1
                       Wildlife
                              Send to NPS, above,
                              to  Wildlife  Refuge
                              Manager.2
                    and
Forest
(USDA)
Service
National  Wildernesses
Send to Forest Service
         Regional Office
         (See Table E-5)
       those national  monuments,  seashores,  and wildlife refuges which also
were designated wilderness areas as of August 7, 1977 are included as
mandatory Federal Class I areas.

 2The Wildlife Refuge  Manager  is  located  at  or near each refuge.
                                     E.14

-------
               TABLE E-5.  USDA FOREST SERVICE REGIONAL OFFICES
                                  AND STATES THEY SERVE*
                                                                  DRAFT
                                                                  OCTOBER 1990
USDA Forest Service
Northern Region
Federal  Building
P.O. Box 7669
Missoula,  MT  59807
[ID, NO, SD, MT]
USDA Forest Service
Rocky Mountain Region
11177 West 8th Avenue
P.O. Box 25127
Lakewood, CO  80225
[CO, KS, NE, SD, WY]
USDA Forest Service
Southwestern Region
Federal  Building
517 Gold Avenue, SW
Albuquerque, NM  87102
[AZ, NM]
USDA Forest Service
Intermountain Region
Federal Building
324 25th Street
Ogden, UT  84401
[ID, UT, NV, WY]
USDA Forest Service
Pacific Southwest Region
630 Sansome Street
San Francisco, CA  94111
[CA, HI,  GUAM, Trust Terr, of Pacific]
USDA Forest Service
Pacific Northwest Region
P.O. Box 3623
Portland, OR  97208
[WA, OR]
USDA Forest Service
Southern Region
1720 Peachtree Road,  NW
Atlanta, GA  30367
[AL, AR, FL, GA, KY,  LA, MS, NC, OK,
PR, SC, TN, TX, VI, VA]
USDA Forest Service
Alaska Region
P.O. Box 21628
Juneau, AK  99802-1628
[AK]
USDA Forest Service
Eastern Region
310 W.  Wisconsin Avenue, Room 500
Milwaukee, WI  53203
[CT, DE, IL, IN, IA, ME, MD, MA, MI
MN, MO, NH, NY, NJ, OH, PA, RI, VT,
WV, WI]
   Some Regions serve only part of a State.
                                     E.15

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.   CLASS I  AREA IMPACT ANALYSIS  AND  REVIEW
      This section presents the procedures  an  applicant  should  follow  in
preparing an analysis of a proposed source's  impact  on  air quality  and AQRV's
in Class I areas,  including recommended informal  steps.   For  each participant
in the analysis -  the permit applicant, the FLM,  and the permit reviewing
agency - the section summarizes their role  and responsibilities.

III.A.  SOURCE APPLICABILITY

      If a proposed major source or major modification  may affect a Class I
area, the Federal  PSD regulations require the  reviewing  authority to provide
written notification of any such proposed source  to  the FLM (and the USDI and
USDA officials delegated permit review responsibility).   The  meaning of the
term "may affect"  is interpreted by EPA policy to include all  major sources  or
major modifications which propose to locate within 100  kilometers  (km) of a
Class I area.  Also, if a major source proposing  to  locate at a distance
greater than 100 km is of such size that the reviewing  agency or FLM is
concerned about potential emission impacts  on  a Class I  area,  the  reviewing
agency can ask the applicant to perform an  analysis  of  the source's potential
emissions impacts  on the Class I area.  This is because certain meteorological
conditions, or the quantity or type of air  emissions from large sources
locating further than 100 km, may cause adverse impacts on a  Class  I area's.
A reviewing agency should exclude no major  new source or major modification
from performing an analysis of the proposed source's impact if there is some
potential for the  source to affect a Class  I area's.

      The EPA's policy requires, at a minimum, an AQRV  impact analysis of any
PSD  source the emissions from which increase pollutant  concentration by more
than 1 pg/m3 (24-hour average)  in a Class I area.  However, certain AQRV's may
be sensitive to pollutant increases less than 1 pg/m3.   Also,  some  Class  I
areas may be approaching the threshold for  effects by a particular  pollutant
on certain resources and consequently may be sensitive to even small increases
in pollutant concentrations.  For example,  in some cases increases  in sulfate
concentration less than  1 pg/m3 may adversely impact visibility.   Thus,  an
                                     E.16

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
increase of 1 pg/m3  should  not  absolutely  determine whether  an AQRV  impact
analysis is needed.   The reviewing agency should consult the FLM to determine
whether to require all  the information necessary for  a complete  AQRV impact
analysis of a proposed  source.

III.B.  PRE-APPLICATION STAGE

      A pre-application meeting between the applicant, the FLM,  and the
reviewing agency to  discuss the information required  of the source is highly
recommended.   The applicant should contact the appropriate FLM as soon as
plans are begun for  a major new source or modification near a Class I area
(i.e., generally within 100 km  of the Class I  area).   A preapplication
meeting, while not required by  regulation-, helps the  permit applicant
understand the data  and analyses needed by the FLM.   At this point,  given
preliminary information such as the source's location and the type and
quantity of projected air emissions,  the FLM can:

      •     agree on which Class I areas are potentially affected by the
            source;
      •     discuss  AQRV's for  each of the areas(s)  and the indicators that
            may be used to measure the source's impact on those  AQRV's;
      •     advise the  source about the scope  of the  analysis for determining
            whether  the source  potentially impacts the Class I area(s);
      •     discuss  which Class I area impact  analyses the applicant should
            include  in  the permit application; and
      •     discuss  all pre-application monitoring in the Class  I area that
            may be necessary to assess the current status of, and effects  on,
            AQRV's (this monitoring usually is done  by the applicant).
                                     E.17

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.C.   PREPARATION  OF PERMIT APPLICATION
      For  each  proposed  major  new  source  or  major  modification  that  may  affect

a Class I  area,  the applicant  is  responsible for:


      •     identifying  all  Class  I  areas within  100  km of  the  proposed  source
            and  any other Class  I  areas  potentially  affected;

      •     performing  all  necessary Class I increment  analyses (including  any
            necessary cumulative  impact  analyses);

      •     performing  for each  Class I  area any  preliminary  analysis  required
            by  a reviewing agency  to find whether  the source  may increase  the
            ambient concentration  of any  pollutant by 1 M9/m3 (24-hour
            average) or  more;

      •     performing  for each  Class I  area an  AQRV  impact analysis for
            vi si bil i ty;

      •     providing all information necessary  to conduct  the  AQRV  impact
            analyses (including  any  necessary cumulative impact analyses);

      •     performing  any monitoring within the  Class  I area required by  the
            reviewing agency;  and

      •     providing the reviewing  agency with  any  additional  relevant
            information  the agency requests  to "complete" the Class  I  area
            impacts analysis.

By involving the FLM early in  preparation of the  Class  I area analysis,  the
applicant  can identify  and address FLM concerns,  avoiding delays later during
permit review.
      The FLM is the AQRV expert for Class I  areas.   As such,  the FLM can

recommend to the applicant:
      •     the AQRV's the applicant should address in the PSD permit
            application's Class I area impact analysis;

      •     techniques for analyzing pollutant effects on AQRV's;

      •     the criteria the FLM will  use to determine whether the emissions
            from the proposed source would have an adverse impact  on any AQRV;
                                     E.18

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

            the pre-construction and post-construction AQRV monitoring the FLM
            will  request that the reviewing agency require of the applicant;
            and

            the monitoring,  analysis,  and quality assurance/quality control
            techniques the permit applicant should use in conducting the  AQRV
            monitoring.
The permit applicant and the FLM also should keep the reviewing agency
apprised of all  discussions concerning a proposed source.


III.D.   PERMIT APPLICATION REVIEW
      Where a reviewing agency anticipates that a  proposed source may affect a
Class I  area, the reviewing agency is responsible  for:


      •     sending the FLM a copy of any advance  notification  that  an
            applicant submits within 30 days of receiving such  notification;

      •     sending EPA a copy of each permit application and a copy of any
            action relating to the source;

      •     sending the FLM a complete copy of all  information  relevant to the
            permit application,  including the Class I  visibility impacts
            analysis, within 30  days of receiving  it and at least 60 days
            before any public hearing on the proposed  source (the reviewing
            agency may wish to request that the applicant furnish 2  copies of
            the permit application);

      •     providing the FLM a  copy of the preliminary determination
            document; and

      •     making a final  determination whether construction should be
            approved, approved with conditions, or disapproved.
      A reviewing agency's policy regarding Class I  area impact analyses can
ensure FLM involvement as well  as aid permit applicants.  Some recommended
policies for reviewing agencies are:
            not considering a permit application complete until  the FLM
            certifies that it is "complete" in the sense that it contains
            adequate information to assess adverse impacts on AQRV's;

                                     E.19

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
            recommending  that  the  applicant  agree  with  the  FLM  (usually  well
            before  the  application  is  received)  on the  type  and  scope  of AQRV
            analyses  to be  done;
            deferring to  the  FLM's  adverse  impact  determination,  i.e., denying
            permits based on  FLM adverse  impact  certifications;  and
            where  appropriate,  incorporating permit conditions  (e.g.,
            monitoring  program) which  will  assure  protection of  AQRV's.   Such
            conditions  may  be  most  appropriate when the full  extent  of the
            AQRV  impacts  is uncertain.
In addition,  the reviewing  agency  can  serve as  an  arbitrator  and  advisor in
FLM/applicant agreements,  especially  at meetings  and  in  drafting  any written
agreements.

      While  the FLM's  review of a  permit application  focuses  on  emissions
impacts on visibility  and  other AQRV's, the FLM may  comment on  all  other
aspects of the permit  application.  The FLM should be given sufficient time
(at least  30  days)  to  thoroughly perform or review a  Class  I  area impact
analysis and  should receive a copy  of  the permit  application  either at the
same time  as  the reviewing  agency  or  as soon after the reviewing  agency as
possible.
                                     E.20

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      The FLM can make one of two decisions on a permit application:  (1)  no
adverse impacts;  or (2) adverse impact based on any available information.
Where a proposed  major source or major modification adversely impacts a
Class I area's AQRV's, the FLM can recommend that the reviewing agency deny
the permit request based on the source's projected adverse impact on  the
area's AQRV's.  However, rather than recommending denial  at this point, the
FLM may work with the reviewing agency to identify possible permit conditions
that, if agreed to by the applicant, would make the source's effect on AQRV's
acceptable.   In cases where the permit application contains insufficient
information  for the FLM to determine AQRV impacts, the FLM should notify  the
reviewing agency  that the application is incomplete.

      During the  public comment period, the FLM can have two roles: 1) final
determination on  the source's impact on AQRV's with a formal recommendation to
the reviewing agency; and 2) a commenter on other aspects of the permit
application  (best available control  technology, modeling, etc.).  Even for  PSD
permit applications where a proposed source's emissions clearly would not
cause or contribute to exceedances of any Class I increment, the FLM  may
demonstrate  to the reviewing agency that emissions from the proposed  source or
modification would adversely impact AQRV's of a mandatory Federal Class I area
and recommend denial.  Conversely, a permit applicant may demonstrate to  the
FLM that a proposed source's emissions do not adversely affect a mandatory
Federal Class I area's AQRV's even though the modeled emissions would cause an
      exceedance of a Class I increment.   Where a Class I  increment is
exceeded, the burden of proving no adverse impact on AQRV's is on the
applicant.  If the FLM concurs with this  demonstration, the FLM may recommend
approval  of the permit to the reviewing agency and such a  permit may be issued
despite projected Class I increment exceedances.
                                     E.21

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.   VISIBILITY IMPACT  ANALYSIS AND REVIEW
      Visibility is  singled out in the  regulations  for  special  protection  and
enhancement in accordance with the national  goal  of preventing  any  future,  and
remedying any existing,  impairment of visibility  in Class  I  areas  caused  by
man-made air pollution.   The visibility regulations for new  source  review
(40 CFR 51.307 and 52.27) require visibility impact analysis in PSD areas  for
major new sources or major modifications that have  the  potential  to impair
visibility in any Federal Class I area.  Information on screening  models
available for visibility analysis can be found in the manual  "Workbook for
Plume Visual Impact  Screening and Analysis," EPA-450/4-88-015 (9/88).

IV.A  VISIBILITY ANALYSIS
      An "adverse impact on visibility" means visibility impairment which
interferes with the management,  protection,  preservation,  or enjoyment of a
visitor's visual  experience of the Federal  Class I  area.  The FLM makes the
determination of an adverse impact on a case-by-case basis taking into account
the geographic extent,  duration, intensity,  frequency and  time of visibility
impairment, and how these factors correlate  with (1) times of visitor use of
the Federal Class I area, and (2) the frequency and timing of natural
conditions that reduce  visibility.  Visibility perception  research indicates
that the visual effects of a change in air quality requires consideration of
the features of the particular vista as well as what is in the air, and that
measurement of visibility usually reflects the change in color, texture, and
form of a scene.  The reviewing agency may require visibility monitoring in
any Federal Class I area near a proposed new major source or modification as
the agency deems appropriate.

      An integral vista is a view perceived from within a mandatory Class I
Federal area of a specific landmark or panorama located outside of the
mandatory Class I Federal area.  A visibility impact analysis is required for
the integral vistas identified at 40 CFR 81, Subpart D, and for any other
integral vista identified in a SIP.
                                     E.22

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.B  PROCEDURAL REQUIREMENTS
      When the reviewing agency receives advance notification (e.g.,  early
consultation with the source prior to submission of the application)  of a
permit application for a source that may affect visibility in a Federal
Class I  area, the agency must notify the appropriate FLM within 30 days of
receiving the notification.   The reviewing agency must, upon receiving a
permit application for a source that may affect Federal Class I area
visibility,  notify the FLM in writing within 30 days of receiving it  and at
least 60 days prior to the public hearing on the permit application.   This
written  notification must include an analysis of the source's anticipated
impact on visibility in any  Federal  Class I  area and all other information
relevant to  the permit application.   The FLM has 30 days after receipt of the
visibility impact analysis and other relevant information to submit to the
reviewing agency a finding that the  source will adversely impact visibility in
a Federal Class I area.

      If the FLM determines  that a proposed  source will adversely impact
visibility in a Federal Class I area and the reviewing agency concurs, the
permit may not be issued.  Where the reviewing agency does not agree  with the
FLM's finding of an adverse  impact on visibility the agency must, in  the
notice of public hearing, either explain its decision or indicate where the
explanation  can be obtained.
                                     E.23

-------
V.  BIBLIOGRAPHY
                                                                  DRAFT
                                                                  OCTOBER 1990
 1.
 2.
 4.
 5.
 6.
 7.
Workbook for Plume Visual  Impact Screening and Analysis.  U.S.
Environmental  Protection Agency, Research Triangle Park, NC.
EPA-450/4-88-015.   September 1988.
Workbook for Estimating Visibility Impairment.
Protection Agency.   Research Triangle Park, NC.
November 1980.   (NTIS No. PB 81-157885).
                   U.S.  Environmental
                    EPA-450/4-80-031.
 3.   USDA Forest Service (1987a) Air Resource Management Handbook.
      2509.19.
                                                              FSH
USDA Forest Service (1987b) Protocols for Establishing Current Physical
Chemical, and Biological Conditions of Remote Alpine and Subalpine
Ecosystems. Rocky Mountain Forest and Range Experiment Station General
Technical Report No. 46, Fort Collins, Colorado.
USDA Forest Service (1987c).
Pollution Effects on Class I
and Range Experiment Station
 A Screening Procedure to Evaluate Air
Wilderness Areas.  Rocky Mountain Forest
GTR 168.  Fort Collins, Colorado.
 8.
USDI (1982) "Internal Procedures for Determinations of Adverse Impact
Under Section 165(d) (2)(C) (ii) and (iii) of the Clean Air Act"  47 FR
30226, July 12, 1982.

USDI National Park Service (1985) Permit Application Guidance for New
Air Pollution Sources. Natural Resources Report Series 85-2, National
Park Service, Air Quality Division, Permit Review and Technical Support
Branch, Denver, Colorado.

USDI National Park Service, Air Resource Management Manual. National
Park Service, Air Quality Division, Permit Review and Technical Support
Branch, Denver, Colorado.
                                   CHAPTER F

                                     E.24

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER  F
                        NONATTAINMENT AREA  APPLICABILITY
I.  INTRODUCTION
      Many of the elements and procedures for source applicability under  the
nonattainment area NSR applicability provisions are similar to those of PSD
applicability.   The reader is therefore encouraged to become familiar with the
terms, definitions and procedures from Part I.A.,  "PSD Applicability," in  this
manual.   Important differences occur,  however,  in  three key elements that  are
common to applicability determinations for new sources or modifications of
existing  sources located in attainment (PSD)  and nonattainment areas. Those
elements  are:

      •  Definition of "source,"
      •  Pollutants that must be evaluated  (geographic effects); and
      •  Applicability thresholds

Consequently, this section will  focus  on these three elements in the context
of a nonattaiment area NSR program.   Note that the two latter elements,
pollutants that must be evaluated for  nonattainment NSR due to the location of
the source in designated nonattainment areas  (geographic effects) and
applicability thresholds, are not independent.   They will, therefore, be
discussed in section III.
                                      F.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.    DEFINITION OF SOURCE
      The original  NSR regulations  required  that  a  source  be  evaluated
according to a  dual source definition.   On October  14,  1981,  however, the  EPA
revised the new source review regulations  to give a  State  the option  of
adopting a plantwide definition  of  stationary source in  nonattainment areas,
if the State's  SIP  did not rely  on  the  more  stringent "dual"  definition  in  its
attainment demonstration.   Consequently,  there are  two  stationary  source
definitions for nonattainment major source permitting:   a  "plantwide"
definition and  a "dual"  source definition.   The permit  application  must  use.
and be reviewed according  to. whichever of the two  definitions is  used to
define a stationary source in the applicable SIP.

II.A.  "PLANTWIDE"  STATIONARY SOURCE DEFINITION

      The EPA definition of stationary  source for nonattainment major source
permitting uses the "plantwide"  definition,  which is the same as that used  in
PSD.  A complete discussion of the  concepts  associated  with  the plantwide
definition of source are presented  in the PSD part  of this manual  (see
section II).  In essence,  this definition provides  that only  physical or
operation changes that result in a  significant net  emissions  increase at the
entire plant are considered a major modification  to an  existing major source
(see sections II and III).

      For example,  if an existing major source proposes to increase
      emissions by constructing a new emissions unit but plans to reduce
      actual emissions by the same amount at another emissions unit at
      the plant (assuming the reduction is federally enforceable and is
      the only contemporaneous and creditable emissions change at the
      source),  then there would be no net increase in emissions at the
      plant and therefore no "major" modification to the stationary
      source.
                                      F.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.B.   "DUAL SOURCE"  DEFINITION OF STATIONARY SOURCE
      The "dual"  definition of stationary source defines  the term stationary
source as ".  .  .  any building, structure, facility,  or installation  which
emits or has  the  potential  to emit any air pollutant subject to regulation
under the Clean Air Act."   Under this  definition,  the three terms building,
structure,  or facility are  defined as  a single term  meaning all of the
pollutant-emitting activities which belong to the  same industrial grouping
(i.e.,same  two-digit SIC code),  are located on one or more adjacent
properties,  and are under  the control  of the same  owner or operator.   The
fourth term,  installation,  means an identifiable piece of process equipment.
Therefore,  a  stationary source is both:

      •     a building, structure, or  facility (plantwide); and
      •     an  installation (individual piece of equipment).

      In other  words,  the  "dual  source" definition of stationary source treats
each emissions  unit as (1)  a separate, independent stationary source,  and (2)
a component of  the entire  stationary source.
      For example,  in the case of a power plant with three large boilers
      each emitting major amounts (i.e., >100 tpy) of NOX, each  of the
      three boilers is an individual stationary source and all three
      boilers together constitute a stationary source.   [Note that the
      power plant would be seen only as a single stationary source under
      the plantwide definition (all three boilers together as one
      stationary source)].
Consequently,  under the dual  source definition,  the emissions from each
physical  or operational change at a plant are reviewed both with and without
regard to reductions elsewhere at the plant.
      For example,  a power plant is an existing major S02 source in an
      S02 nonattainment area.   The power plant proposes  to 1) install
      SO2 scrubbers  on an  existing boiler and 2) construct a new boiler
      at the same facility.  Under the "plantwide" definition,  the S02
      reductions from the scrubber installation could be considered,
      along with other contemporaneous emissions changes at the plant
      and the new emissions increase of the new boiler to arrive  at the
      source's net emission increase.   This might result in a net
                                      F.3

-------
                                                                           DRAFT
                                                                           OCTOBER 1990

               emissions change which would be below the S02 significance level
               and the new boiler would "net" out of review as major
               modification.   Under the dual source definition, however,  the new
               boiler would be regarded as a individual source and would be
               subject to nonattainment NSR requirements if its potential
               emissions exceed the 100 tpy threshold.   The emissions reduction
               from the scrubber could not be used to reduce net source
               emissions, but would instead be regarded as an  S02  emissions
               reduction from a separate source.


               The following examples are provided to further  clarify the application

         of the dual  source definition to determine if a modification to an existing

         major source is major and, therefore, subject to major source NSR permitting

         requi rements.


Example 1              An existing major stationary source is located in a
                     nonattainment area for NOX where the "dual source"
                     definition applies, and has the following emissions units:

               Unit #1 with a potential to emit of 120 tpy of NOX

               Unit #2 with a potential to emit of 80 tpy of NOX

               Unit #3 with a potential to emit of 120 tpy of NOX

               Unit #4 with a potential to emit of 130 tpy ofNOx


   Case 1      A modification planned for Unit #1 will result in an emissions
               increase of 45 tpy of NOX.   The following emissions changes are
               contemporaneous with the proposed modification  (all case examples
               assume that increases and decreases are creditable and will be
               made federally enforceable by the reviewing authority when the
               modification is permitted and will occur before construction of
               the modification):

               Unit #3 had an actual decrease of 10 tpy NOX

               Vnit #4 had an actual decrease of 10 tpy NOX
                                               F.4

-------
                                                                        DRAFT
                                                                        OCTOBER 1990

      Only contemporaneous emissions changes at Unit #1 are considered because Unit
      #1 is a major source of NOX by itself (i.e., potential emissions  of NOX are
      greater than 100 tpy).   The proposed increase at unit #1 of 45 tpy is greater
      than the 40 tpy
            NOX  significant emissions rate  since  the  emissions changes  at the other
            units are not considered.  Consequently,  the proposed modification to
            Unit #1 is major under the dual source definition.


Case 2      A modification to unit #2 is planned which will result in an emissions
            increase of 45 tpy of NOX .   The following emissions changes are
            contemporaneous with the proposed modification:

            Unit #1 had an actual decrease of 10 tpy

            Unit #3 bad an actual decrease of 10 tpy

            Unit #2 is not a major stationary source in and of itself  (i.e.,
            its potential to emission of 80 tpy NOX is less than the  100 tpy
            major source threshold).  Therefore,  the major stationary source
            being modified is the whole plant and the emissions decreases at
            units #1 and #3 are considered in calculating the net emissions
            change at the source.   The net emissions change of 25 tpy (the  sum
            of +45, -10,  and -10) at the source is less than the applicable 40
            tpy fiOx significant emissions rate.   Consequently,  the proposed
            modification is not major.


Case 3      A brand new unit #5 with a potential to emission of 45 tpy of NOX
            (note that potential emissions are less than the 100 tpy major
            source cutoff) is being added to the plant.  The following
            emissions changes are contemporaneous with the proposed
            modification:

            Unit #1 had an actual decrease of 15 tpy

            Unit #2 had an actual increase of 25 tpy

            Unit #3 had an actual decrease of 20 tpy

            The new unit #5 is not a major stationary source in and of itself.
            Therefore, the major stationary source being modified is the whole
            plant and the emissions decreases at units #1,  #2 and #3 are
            considered in calculating the net emissions change at the source.
            The net emissions change of 35 tpy (the sum of + 45,  -15, +25,  and
            -20) at the source is less than the applicable 40 tpy NOX
            significance level.  Therefore, the proposed unit #5 is not a
            major modification.


Case 4      A brand new unit #6 with a potential to emit of NOX of 120  tpy  is
            being added to the plant.  Because the new unit is, by itself,  a
            new major source (i.e., potential NOX emissions are greater than
                                            F.5

-------
                                                                        DRAFT
                                                                        OCTOBER 1990

            the 100 tpy major source cutoff), it cannot net out of review
            (using emissions reductions achieved at other emissions units at
            the plant) under the dual source definition.


Example 2   An existing plant has only two emissions units.  The units have a
            potential to emit of 25 tpy and 40 tpy.  Here, any modification to
            the plant would have to have a potential to emit greater than 100
            tpy before the modification is major and subject to review.  This
            is because neither of the two existing emissions units (at 25 tpy
            and 40 tpy), nor the total plant (at 65 tpy) are considered to be
            a major source (i.e.,  existing potential emissions do not exceed
            100 tpy).  If, however, a third unit with potential emissions of
            110 tpy were added, that unit would be subject to review
            regardless of any emissions reductions from the two existing
            units.
                                            F.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.   POLLUTANTS ELIGIBLE FOR REVIEW AND APPLICABILITY THRESHOLDS


III.A.   POLLUTANTS ELIGIBLE FOR REVIEW (GEOGRAPHIC CONSIDERATIONS)


      A new source will  be subject to nonattainment area preconstruction

review requirements only if it will  emit, or will  have the potential  to emit,

in major amounts any criteria pollutant for which  the area has been designated

nonattainment.   Similarly, only if a modification  results in a significant

increase (and significant net emissions increase under the plantwide source

definition) of  a pollutant, for which the source is major and for which the

area  is designated nonattainment,  do nonattainment requirements apply.


III.B.   MAJOR SOURCE THRESHOLD


      For the purposes of nonattainment NSR, a major stationary source  is
            any stationary source which emits or has the potential
            to emit 100 tpy of any [criteria] pollutant subject to
            regulation under the CAA,  or

            any physical  change or change in method of operation at an
            existing non-major source  that constitutes a major
            stationary source by itself.
      Note that the 100 tpy threshold applies to all  sources.   The alternate
250 tpy major source threshold [for PSD sources not classified under one of

the 28 regulated source categories identified in Section 169 of the CAA (See
Section I.A.2.3 and Table I-A-1)  as being subject to  a 100 tpy threshold]  does

not exist for nonattainment area  sources.
                                     F.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.C.    MAJOR MODIFICATION THRESHOLDS
      Major modification thresholds for nonattainment areas are those same
significant emissions values used to determine if a modification is major for
PSD.   Remember,  however, that only criteria pollutants for which the location
of the source has been designated nonattainment are eligible for evaluation.
                                      F.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

IV.    NONATTAINMENT APPLICABILITY EXAMPLE

      The following example illustrates the criteria presented in sections II

and  III above.
      Construction of a new plant with potential emissions of 500 tpy S02,  50
      tpy VOC and 30 tpy NOX is proposed for an  area  designated nonattainment
      for SO2  and ozone and attainment for NOX.  (Recall that VOC is the
      regulated surrogate pollutant for ozone.)   The new plant is major for
      S02  and  therefore would be  subject to nonattainment  requirements for  SOZ
      only.   Even though the VOC emissions are significant, the source is
      minor for VOC, and according to nonattainment regulations,  is not
      subject to major source review.  For purposes of PSD, the NOX emissions
      are neither major nor significant and are, therefore, not subject to PSD
      review.

      Two years after construction on the new plant commences,  a modification
      of this plant is proposed that will  result in an emissions increase of
      60 tpy VOC and 35 tpy NOX without any creditable contemporaneous
      emissions reductions.  Again, the VOC emissions increase would not be
      subject, because the existing source is not major for VOC.   The
      emissions increase of 35 tpy NOX is  not  significant  and again,  is not
      subject to PSD review.  Note, however,  that the plant would be
      considered a major source of VOC in subsequent applicability
      determinations.
      One year later,  the plant proposes another increase in VOC emissions by
      75 tpy and NOX by another 45  tpy,  again  with no contemporaneous
      emissions reductions.  Because the existing plant is now major for VOC
      and will experience a significant net emissions increase of that
      pollutant, it will be subject to nonattainment NSR for VOC.  Because the
      source is major for a regulated pollutant (VOC) and will experience a
      significant net emissions increase of an attainment pollutant (NO,),  it
      will also be subject to PSD review.
                                      F.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER G
                        NONATTAINMENT AREA REQUIREMENTS
I.   INTRODUCTION

      The preconstruction review requirements for major new sources or major
modifications locating in designated nonattainment areas differ from
prevention of significant deterioration (PSD) requirements.  First, the
emissions control  requirement for nonattainment areas,  lowest achievable
emission rate (LAER),  is defined differently than the best available control
technology (BACT)  emissions control  requirement.   Second, before construction
of a nonattainment area  source can be approved, the source must obtain
emissions reductions (offsets) of the nonattainment pollutant from other
sources which impact the same area as the proposed source.  Third, the
applicant must certify that all  other sources owned by the applicant in the
State are complying with all applicable requirements of the CAA, including all
applicable requirements  in the State implementation plan (SIP).  Fourth, such
sources impacting visibility in mandatory class I Federal areas must be
reviewed by the appropriate Federal  land manager (FLM).
                                      G.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.  LOWEST ACHIEVABLE EMISSION RATE (LAER)
      For major new sources and major modifications  in  nonattainment  areas,
LAER is the most stringent emission limitation derived  from either  of the
fol1owi ng:
            the most stringent emission limitation  contained  in  the
            implementation plan of any State for such  class or category  of
            source;  or
            the most stringent emission limitation  achieved in practice  by
            such class or category of source.
The most stringent emissions limitation contained  in  a  SIP for  a  class  or
category of source must be considered LAER,  unless (1)  a  more  stringent
emissions limitation has been achieved in practice, or  (2) the  SIP  limitation
is demonstrated by the applicant to be unachievable.   By  definition LAER can
not be less stringent than any applicable new source  performance  standard
(NSPS).
      There is, of course, a range of certainty in such a definition.   The
greatest certainty for a proposed LAER limit exists when  that  limit is
actually being achieved by a source.   However,  a SIP  limit,  even  if it  has  not
yet been applied to a source, should  be considered initially to be  the  product
of careful  investigation and, therefore,  achievable.   A SIP limit's
credibility diminishes if a) no sources exist to which  it applies;  b)  it is
generally acknowledged that sources are unable to  comply  with  the limit and
the State is in the process of changing the  limit; or c)  the State  has  relaxed
the original SIP limit.  Case-by-case evaluations  need  to be made in these
situations  to determine the SIP limit's achievabi1ity.

      The same logic applies to SIP limits to which  sources are subject but
with which  they are not in compliance.  Noncompliance by  a source with  a SIP
limit, even if it is the only source  subject to that  specific  limit, does  not
automatically constitute a demonstration  that the  limit is unachievable.   The
specific reasons for noncompliance must be determined,  and the  ability  of  the
source to comply assessed.  However,  such noncompliance may prove to be an
                                      G.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
indication of nonachievabi1ity,  so the  achievabi1ity  of  such  a  SIP limitation
should be carefully studied  before it  is  used  as  the  basis  of a  LAER
determination.   Some recommended sources  of information  for determining  LAER
are:
      •     SIP limits for  that  particular class  or  category  of  sources;
      •     preconstruction  or operating   permits issued in other
            nonattainment areas; and
      •     the BACT/LAER Clearinghouse.
      Several technological  considerations are involved  in  selecting LAER.
The LAER is an  emissions rate specific  to each emissions unit including
fugitive emissions sources.   The emissions rate may  result  from a  combination
of emissions-limiting measures such as  (1) a change  in the  raw material
processed, (2)  a process modification,  and (3) add-on controls.    The
reviewing agency determines  for  each new  source whether  a single control
measure is appropriate for  LAER or whether a combination of emissions-limiting
techniques should be considered.

      The reviewing agency  also  can require consideration of technology
transfer.  There are two types of potentially  transferable  control
technologies: (1) gas stream controls,  and (2) process controls and
modifications.   For the first type of transfer, classes  or  categories of
sources to consider are those producing similar gas  streams that could be
controlled by the same or similar technology.   For the second type of
transfer, process similarity governs the  decision.

      Unlike BACT, the LAER requirement does not consider economic, energy,  or
other environmental factors.  A LAER is not considered achievable if the cost
of control is so great that a major new source could not be built or operated.
This applies generically, i.e.,  if no new plants could be built in that
industry if emission limits were based on a particular control  technology.   If
some other plant in the same (or comparable) industry uses  that control
technology, then such use constitutes evidence that  the cost to the industry
of that control is not prohibitive.  Thus, for a new source, LAER costs  are
considered only to the degree that they reflect unusual  circumstances which in

                                     G.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
some manner differentiate the cost of control  for that source from control
costs for the rest of the industry.   When discussing costs, therefore,
applicants should compare control  costs for the proposed source to the  costs
for sources already using that control.

      Where technically feasible,  LAER generally is specified as both a
numerical emissions limit (e.g.,  Ib/MMBtu) and an emissions rate (e.g.,
Ib/hr).   Where numerical  levels reflect assumptions about the performance  of  a
control  technology, the permit should specify  both the numerical emissions
rate and limitation and the control  technology.  In some cases where
enforcement of a numerical  limitation is judged to be technically infeasible,
the permit may specify a  design,  operational,  or equipment standard; however,
such standards must be clearly enforceable, and the reviewing agency must
still make an estimate of the resulting emissions for offset purposes.
                                     G.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.   EMISSIONS REDUCTIONS "OFFSETS"
      A major source or major modification planned in a nonattainment area
must obtain emissions reductions as a condition for approval.   These
emissions reductions, generally obtained from existing sources located in  the
vicinity of a proposed source, must (1) offset the emissions increase from the
new source or modification and (2)  provide a net air quality benefit.  The
obvious purpose of acquiring offsetting emissions decreases is to allow an
area to move towards attainment of  the NAAQS while still  allowing some
industrial growth.  Air quality improvement may not be realized if all
emissions increases are not accounted for and if emissions offsets are not
real .

      In evaluating a nonattainment NSR permit, the reviewing agency ensures
that offsets are developed in accordance with the provisions of the applicable
State or local nonattainment NSR rules.  The following factors are considered
in reviewing offsets :

            the pollutants requiring offsets and amount of offset required;
            the location of offsets relative to the proposed source;
            the allowable sources for offsets;
            the "baseline" for calculating emissions reduction credits; and
            the enforceabi1ity of proposed offsets.

Each of these factors should be discussed with the reviewing agency to ensure
that the specific requirements of that agency are met.

      The offset  requirement applies to each pollutant which triggered
nonattainment NSR applicability.  For example, a permit for a proposed
petroleum refinery which will emit more than 100 tpy of sulfur dioxide (S02)
and particulate matter in a S02  and particulate matter nonattainment area  is
required to obtain offsetting emissions reductions of S02  and  particulate
matter.
                                      G.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.A.   CRITERIA FOR EVALUATING EMISSIONS OFFSETS

      Emissions reductions obtained to offset new source emissions in a
nonattainment area must meet two important objectives:

      •  ensure reasonable progress toward attainment of the NAAQS; and
      •  provide a positive net air quality benefit in  the area affected by
         the proposed source.

States  have latitude in determining what requirements offsets  must meet  to
achieve these NAA program objectives.   The EPA has set  forth minimum
considerations under the Interpretive  Ruling (40 CFR 51, Appendix S).
Acceptable offsets also must be creditable, quantifiable,  federally
enforceable, and permanent.

      While an emissions offset must always result in reasonable progress
toward  attainment of the NAAQS, it need not show that the  area will attain  the
NAAQS.   Therefore, the ratio of required emissions offset  to the proposed
source's emissions must be greater than one.  The State determines what  offset
ratio is appropriate for a proposed source, taking into account the location
of the  offsets, i.e., how close the offsets are to the  proposed source.

      To satisfy the criterion of a net air quality benefit does not mean that
the applicant must show an air quality improvement at every location affected
by the  proposed source.  Sources involved in an offset  situation should  impact
air quality in the same general area as the proposed source, but the net air
quality benefit test should be made "on balance" for the area  affected by the
new source.  Generally, offsets for VOC's are acceptable if obtained from
within  the same air quality control region as the new source or from other
nearby  areas which may be contributing to an ozone nonattainment problem.  For
all pollutants, offsets should be located as close to the  proposed site  as
possible.  Applicants should always discuss the location of potential offsets
with the reviewing agency to determine whether the offsets are acceptable.
                                     G.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.B.   AVAILABLE SOURCES OF OFFSETS

      In general, emissions reductions  which  have  resulted  from some other
regulatory action are not available as  offsets.   For  example,  emissions
reductions already required by a  SIP  cannot be counted as  offsets.   Also,
sources subject to an NSPS in an  area with less  stringent  SIP  limits cannot
use the difference between the SIP and  NSPS limits as an offset.   In addition,
any emissions reductions already  counted in major  modification "netting"  may
not be  used as offsets.   However,  emissions reductions validly "banked"  under
an approved SIP may be used as offsets.

III.C.   CALCULATION OF OFFSET BASELINE

      A critical element in the development or review of nonattainment area
new source permits is to determine the  appropriate baseline of the source from
which offsetting emissions reductions are obtained.  In most cases the SIP
emissions limit in effect at the  time that the permit application  is filed  may
be used.  This means that offsets will  be based  on emissions reductions  below
these SIP limits.  Where there is no meaningful  or applicable  SIP  requirement,
the applicant be required to use  actual  emissions  as  the  baseline  emissions
1evel .
                                      G.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
III.D.   ENFORCEABILITY OF PROPOSED OFFSETS
      The reviewing agency ensures that all offsets are federally enforceable.
Offsets should be specifically stated and appear in the permit, regulation or
other document which establishes a Federal enforceabi1ity requirement for the
emissions reduction.  External offsets must be established by conditions in
the operating permit of the other plant or in a SIP revision.
                                       Go
                                       . o

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
IV.   OTHER REQUIREMENTS
      An applicant proposing a major new source or major modification in a
nonattainment area must certify that all major stationary sources owned or
operated by the applicant (or by any entity controlling, controlled by, or
under common control  with the applicant) in that State are in compliance with
all  applicable emissions limitations and standards under the CAA.  This
includes all regulations in an EPA-approved SIP, including those more
stringent than Federal  requirements.

      Any major new source or major modification proposed for a nonattainment
area that may impact visibility in a mandatory class I Federal  area is subject
to review by the appropriate Federal land manager (FLM).  The reviewing agency
for any nonattainment area should ensure that the FLM of such mandatory class
I Federal area receives appropriate notification and copies of all documents
relating to the permit application received by the agency.
                                      G.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER H

                       ELEMENTS OF AN EFFECTIVE PERMIT

I.  INTRODUCTION

      An effective permit is the legal  tool  used to establish all  the source
limitations deemed necessary by the reviewing agency during review of the
permit application,  as described in Parts I  and II  of this manual, and is  the
primary basis for enforcement of NSR requirements.   In essence,  the permit may
be viewed as an extension of the regulations.  It defines as clearly as
possible what is expected of the source and  reflects the outcome of the permit
review process.  A permit may limit the emissions rate from various emissions
units or limit operating parameters such as  hours of operation and amount  or
type of materials processed, stored, or combusted.   Operational  limitations
frequently are used  to establish a new potential  to emit or to implement  a
desired emissions rate.   The permit must be  a "stand-alone" document that:

      •  identifies  the emissions units to be regulated;
      •  establishes emissions standards or  other operational limits to be
met;
      •  specifies methods for determining compliance and/or excess
emi ssions,
         including reporting and recordkeeping requirements; and
      •  outlines the procedures necessary to maintain continuous compliance
         with the emission limits.

To achieve these goals,  the permit,  which is in effect a contract between  the
source and the regulatory agency, must contain specific, clear,  concise,  and
enforceable conditions.

      This part of the manual gives a brief  overview of the development of a
permit, which ensures that major new sources and modifications will be
constructed and operated in compliance with  the applicable new source review
(NSR) regulations [including prevention of signification deterioration (PSD)
                                     H.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
and nonattainment area (NAA) review],  new source performance standards (NSPS),
national  emissions standards for hazardous air pollutants  (NESHAP),  and
applicable state implementation plan (SIP) requirements.   In particular,  a
permit contains the specific conditions and limitations which ensure that:

      •  an otherwise major source will remain minor;
      •  all  contemporaneous emissions increases and decreases are creditable
         and  federally-enforceable;  and
      •  where appropriate, emissions offset transactions  are documented
         clearly and offsets are real, creditable,  quantifiable,
         permanent and federally-enforceable.

For a more in-depth study, refer to  the Air Pollution  Training Institute
(APTI) course SI 454 (or Workshop course 454 given  by  APTI)  entitled
"Effective Permit Writing."  This course is highly  recommended for all permit
writers and reviewers.
                                      H.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.   TYPICAL CONSTRUCTION PERMIT ELEMENTS
      While each final  permit is unique to a  particular source due to varying
emission limits and specific special  terms and conditions,  every permit must
also contain certain basic elements:

      •     legal  authority;
      •     technical  specifications;
      •     emissions  compliance demonstration;
      •     definition  of excess emissions;
      •     administrative procedures;  and
      •     other specific conditions.

Although many of these  elements are inherent  in  the authority to issue permits
under the SIP,  they must be explicit  within  the  construction of a NSR permit.
Table H-l lists a few  typical subelements found  in  each of  the above.  Some
permit conditions included in each of  these  elements can be considered
standard permit conditions, i.e.,  they  would  be  included in nearly every
permit.  Others are more specific and  vary depending on the individual source.

II.A.  LEGAL AUTHORITY

      In general,  the  first provision  of a permit is the specification of  the
legal authority to issue the permit.   This should include a reference to the
enabling legislation and to the legal  authority  to  issue and enforce the
conditions contained in the permit and  should specify that  the application is,
in essence, a part of  the permit.   These provisions are common to nearly all
permits and usually are expressed in  standard language included in every
permit issued by an agency.  These provisions articulate the contract-like
nature of a permit in  that the permit  allows  a source to emit air pollution
only if certain conditions are met.  A  specific  citation of any applicable
                                     H.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
        TABLE H.I.   SUGGESTED MINIMUM CONTENTS OF AIR EMISSION PERMITS
Permit Category
      Typical  Elements
Legal  Authority
Technical  Specifications
Emission Compliance Demonstration
Definition of Excess Emissions
Admini strati ve
Other Conditions
Basis — statute,  regulation, etc.
Conditional  Provisions
Effective and expiration dates

Unit operations  covered
Identification of emission units
Control equipment efficiency
Design/operation parameters
Equipment design
Process specifications
Operating/maintenance procedures
Emission limits

Initial performance test and methods
Continuous emission monitoring and
  methods
Surrogate compliance measures
       - process  monitoring
       - equipment design/operations
       - work practice

Emission limit and averaging time
Surrogate measures
Malfunctions and upsets
Follow-up requirements

Recordkeeping and reporting
procedures
Commence/delay construction
Entry  and inspections
Transfer and severability

Post construction monitoring
Emissions offset
                                      H.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
permit effective date and/or expiration date is usually included under the
legal  authority as well.

II.B.   TECHNICAL SPECIFICATIONS

      Overall, the technical specifications may be considered the core of  the
permit in that they specifically identify the emissions unit(s)  covered by the
permit and the corresponding emission limits with  which the source must
comply.  Properly identifying each emissions unit  is  important so that (1)
inspectors can easily identify the unit in the field  and (2)  the permit leaves
no question as to which unit the various permit limitations and  conditions
apply.  Identification usually includes a brief description of the source  or
type of equipment, size or capacity,  model number  or  serial number,  and the
source's identification of the unit.

      Emissions and operational limitations are included in the  technical
specifications and must be clearly expressed, easily  measurable, and allow no
subjectivity in their compliance determinations.   All  limits  also must be
indicated precisely for each emissions point or operation.   For  clarity, these
limits are often best expressed in tabular rather  than textual  form.  In
general, it is best to express the emission limits in two different  ways,  with
one value serving as an emissions cap (e.g., Ibs/hr.)  and the other  ensuring
continuous compliance at  any operating capacity (e.g., Ibs/MMBtu).  The permit
writer should keep in mind that the source must comply with both values to
demonstrate compliance.  Such limits  should be of  a short term nature,
continuous and enforceable.   In addition, the limits  should be consistent  with
the averaging times used  for dispersion modeling  and  the averaging times for
compliance testing.  Since emissions  limitation values incorporated  into a
permit are based on a regulation (SIP, NSPS, NESHAP)  or resulting from new
source review, (i.e., BACT or LAER requirements),  a reference to the
applicable portion of the regulation  should be included.
                                     H.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.C.   EMISSIONS COMPLIANCE DEMONSTRATION
      The permit should state how compliance with each limitation will  be
determined,  and include,  but is not limited to,  the test method(s) approved
for demonstrating compliance.  These permit compliance conditions must  be very
clear and enforceable as  a practical  matter (see Appendix C).   The conditions
must specify:

      •     when and what tests should be performed;
      •     under what conditions tests should be performed;
      •     the frequency of testing;
      •     the responsibility for performing the test;
      •     that the source be constructed to accommodate such testing;
      •     procedures for establishing exact testing protocol; and
      •     requirements  for regulatory personnel to witness  the testing.
      Where continuous, quantitative measurements are infeasible, surrogate
parameters must be expressed in the permit.  Examples of surrogate parameters
include:  mass emissions/opacity correlations, maintaining pressure drop
across a control (e.g., venturi throat of a scrubber), raw material input/mass
emissions output ratios, and engineering correlations associated with specific
work practices.  These alternate compliance parameters may be used in
conjunction with measured test data to monitor continuous compliance or may be
independent compliance measures where source testing is not an option and work
practice or equipment parameters are specified.  Only those parameters that
exhibit a correlation with source emissions should be used.  Identifying and
quantifying surrogate process or control equipment parameters (such as
pressure drop) may require initial  source testing or may be extracted from
confirmed design characteristics contained in the permit application.

      Parameters that must be monitored either continuously or periodically
should be specified in the permit,  including averaging time for continuously
monitored data, and data recording frequency for periodically (continually)
monitored data.  The averaging times should be of a short term nature

                                      H.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
consistent with the time periods for which dispersion modeling of the
respective emissions rate demonstrated compliance with air quality standards,
and consistent with averaging times used in compliance testing.   This
requirement also applies to surrogate parameters where compliance may be  time-
based, such as weekly or monthly leak detection and repair programs (also  see
Appendix C).  Whenever possible, "never to be exceeded" values should be
specified for surrogate compliance parameters.  Also, operating  and
maintenance (O&M) procedures should be specified for the monitoring
instruments (such as zero, span, and other periodic checks) to ensure that
valid data are obtained.  Parameters which must be monitored continuously  or
continually are those used by inspectors to determine compliance on a real-
time basis and by source personnel to maintain process operations in
compliance with source emissions limits.

II.D.  DEFINITION OF EXCESS EMISSIONS

      The purpose of defining excess emissions is to prevent a malfunction
condition from becoming a standard operating condition by requiring the source
to report and remedy the malfunction.  Conditions in this part of the permit:
      •     precisely define excess emissions;
      •     outline reporting requirements;
      •     specify actions the source must take; and
      •     indicate time limits for correction by the source.
                                     H.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Permit conditions defining excess emissions may include alternate conditions
for startup,  shutdown,  and malfunctions such as maximum emission  limits  and
operational  practices and limits.  These must be as  specific  as  possible since
such exemptions can be misused.   Every effort should be made  to  include
adequate definitions of both preventable and nonpreventable malfunctions.
Preventable malfunctions usually are those which cause excess emissions  due to
negligent maintenance practices.   Examples of preventable malfunctions  may
include: leakage or breakage of  fabric filter bags;  baghouse  seal  ruptures;
fires in electrostatic precipitators due to excessive build up of oils or
other flammable materials; and failure to monitor and replace spent activated
carbon beds in carbon absorption units.  These examples reinforce the need for
good O&M plans and keeping records of all repairs.   Permit requirements
concerning malfunctions may include:  timely reporting of the malfunction
duration, severity, and cause; taking interim and corrective  actions; and
taking actions to prevent recurrence.

II.E.  ADMINISTRATIVE PROCEDURES

      The administrative elements of permits are usually standard conditions
informing the source of certain  responsibilities.  These administrative
procedures may include:

      •     recordkeeping and reporting requirements, including all continuous
            monitoring data, excess emission reports, malfunctions, and
            surrogate compliance data;
      •     notification requirements for performance tests,  malfunctions,
            commencing or delay of construction;
      •     entry and inspection procedures;
      •     the need to obtain a permit to operate;  and
      •     specification of procedures to revoke,  suspend, or modify the
            permit.

Though many of these conditions will be entered into the permit via standard
permit conditions, the reviewer must ensure the language is adequate to
establish precisely what is expected or needed from the source, particularly
the  recordkeeping requirements.
                                      H.8

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.F.   OTHER CONDITIONS
      In some cases,  specific permit conditions which do not fit into the
above elements may need to be outlined.   Examples of these are conditions
requiring:   the permanent shutdown of (or reduced emissions rates for) other
emissions units to create offsets or netting credits; post-construction
monitoring; continued Statewide compliance;  and a water truck to be dedicated
solely to a haul  road.   In the case of a portable source,  a condition may be
included to require a copy of the effective  permit to be on-site at all times.
Some O&M procedures,  such as requiring a 10  minute warmup for an incinerator,
would be included in  this category, as well  as conditions requiring that
replacement fabric filters and baghouse seals be kept available at all times.
Any source-specific condition which needs to be included in the permit to
ensure compliance should be listed here.

III.  SUMMARY
      Assuming a  comprehensive review, a permit is only as clear, specific,
and effective as  the  conditions it contains.  As such,  Table H-2 on the
following page lists  guidelines for drafting actual  permit conditions.  The
listing specifies how typical permit elements should be written.  For further
discussion  on drafting  "federally enforceable" permit conditions as a
practical matter, please refer to Appendix C - "Potential  to Emit."
                                     H.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

   TABLE H.2.  GUIDELINES FOR WRITING EFFECTIVE SPECIFIC CONDITIONS IN NSR

PERMITS


 1.    Make  each permit condition  simple,  clear,  and  specific such  that  it
      "stands alone."

 2.    Make  certain legal authority exists to  specify conditions.

 3.    Permit conditions should  be objective and  meaningful.

 4.    Provide description of processes,  emissions units and  control equipment
      covered by the permit, including  operating rates  and periods.

 5.    Clearly identify each permitted emissions  unit such  that  it  can  be
      located in the field.

 6.    Specify allowable emissions (or concentration, etc.) rates  for each
      pollutant and emissions unit permitted,  and specify  each  applicable
      emissions standard by name  in the permit.

 7.    Allowable emissions rates should  reflect the conditions of  BACT/LAER and
      Air Quality Analyses (e.g., specify limits two ways:   maximum mass/unit
      of process and maximum mass/unit  time)

 8.    Specify for all  emissions units (especially fugitive sources) permit
      conditions that require continuous application of BACT/LAER to achieve
      maximum degree of emissions reduction.

 9.    Initial and subsequent performance tests should be conducted at worst
      case operating (non-malfunction)  conditions for all  emissions units.
      Performance tests should determine both emissions and  control equipment
      efficiency.

10.    Continual and continuous emissions performance monitoring and
      recordkeeping (direct and/or surrogate)  should be specified where
      feasible.

11.    Specify test method (citation) and averaging period by which all
      compliance demonstrations  (initial and continuous) are to be made.

12.    Specify what conditions constitute "excess emissions," and  what is  to be
      done in those cases.
                                     H.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                  CHAPTER I
                                PERMIT DRAFTING

I.  RECOMMENDED PERMIT DRAFTING STEPS

      This section outlines a recommended five-step permit drafting process
(see Table 1-1).  These steps can assist the writer in the orderly preparation
of air emissions permits following technical review.

      Step 1 concerns the emissions  units and requires the listing and
specification of three things.   First, list  each new  or modified emissions
unit.  Second, specify each associated emissions point.  This includes
fugitive emissions points (e.g.,  seals,  open containers,  inefficient capture
areas, etc.) and fugitive emissions  units (e.g., storage piles,  materials
handling,  etc.).  Be sure also  to note emissions units with more than one
ultimate exhaust and units sharing common exhausts.  Third, the  writer must
describe each emissions unit as it may appear in the  permit and  identify,  as
well as describe,  each emissions  control unit.   Each  new or modified emissions
unit identified in Step 1 that  will  emit or  increase  emissions of any
pollutant  is considered in Step 2.

      Step 2 requires the writer  to  specify  each pollutant that  will be
emitted from the new or modified  source.  Some  pollutants may not be subject
to regulation or are of de minimis amounts such that  they do not require major
source review.  All  pollutants  should be identified in this step and reviewed
for applicability.  Federally enforceable conditions  must be identified for
de minimis pollutants to ensure they do not  become significant (see
Appendix C - Potential to Emit).   An understanding of "potential to emit"  is
pertinent  to permit  review and  especially to the drafting process.
                                      I.I

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                         TABLE 1-1.   FIVE STEPS  TO  PERMIT  DRAFTING
STEP 1.   SPECIFY EMISSIONS UNITS

      •     Identify each new (or modified)  emissions  unit that  will  emit (or
            increase) any pollutant.

      •     Identify any pollutant and emissions units involved  in  a  netting
            or emissions reduction proposal  (i.e.,  all  contemporaneous
            emissions increases and decreases).

      •     Include point and fugitive emissions units.

      •     Identify and describe emissions  unit and emissions control
            equipment.

STEP 2.   SPECIFY POLLUTANTS

      •     Pollutants subject to NSR/PSD.

      •     Pollutants not subject to NSR/PSD but could  reasonably  be expected
            to exceed significant emissions  levels.  Identify conditions that
            ensure de minimis (e.g.,  shutdowns,  operating modes, etc..).

STEP 3.   SPECIFY ALLOWABLE EMISSION RATES AND BACT/LAER REQUIREMENTS

      •     Minimum number of allowable emissions rates  specified is  equal  to
            at least two limits per pollutant per emissions unit.

      •     One of two allowable limits is unit  mass per unit time  (Ibs/hr)
            which reflects application of emissions controls at maximum
            capacity.

      •     Maximum hourly emissions rate must correspond to that used in air
            quality analysis.

      •     Specify BACT/LAER emissions control  requirements for each
            pollutant/emissions unit pair.
                                      1.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                            TABLE 1-1.  -  Continued
STEP 4.   SPECIFY COMPLIANCE DEMONSTRATION METHODS

      •     Continuous,  direct emission measurement is preferable.

      •     Specify initial and periodic emissions testing where necessary.

      •     Specify surrogate (indirect) parameter monitoring and
            recordkeeping where direct monitoring is impractical or in
            conjunction  with tested data.

      •     Equipment and work practice standards should complement other
            compliance monitoring.

STEP 5.   OTHER PERMIT CONDITIONS

      •     Establish the basis upon which permit is granted (legal
authority).

      •     Should be used to minimize "paper" allowable emissions.

      •     Federally enforceable permit conditions limiting potential to
            emi t.
                                     1.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Step 3 pools the data collected  In  the two  previous  steps.   The  writer
should specify the pollutants that will  be emitted  from each  emission  unit  and
identify associated emission controls  for each  pollutant and/or  emission  unit.
(Indicate if the control  has been determined to be  BACT.)   The writer  also
must assess the minimum number of allowable emissions  rates to be  specified  in
the permit.  Each emissions unit should  have at least  two  allowable  emissions
rates for each pollutant to be emitted.   This is  the most  concise  manner  in
which to present permit allowables and should be  consistent with the averaging
times and emissions ratio used in the  air quality analysis.  As  discussed
earlier in Section H,  the applicable regulation should also be cited as well
as whether BACT, LAER, or other SIP requirements  apply to  each pollutant  to  be
regulated.

      Step 4 essentially mirrors the items discussed in the previous Chapter
H, Section IV., Emissions Compliance Demonstration. At this  point the writer
enters into the permit any performance testing  required of the  source. The
conditions should specify what emissions  test is  to be performed and the
frequency of testing.   Any surrogate parameter  monitoring  must  be  specified.
Recordkeeping requirements and any equipment and  work  practice  standards
needed to monitor the source's compliance should  be written into the permit
in Step 4.  Any remaining or additional  permit conditions, such  as legal
authority and conditions limiting potential to emit can be identified in
Step 5.   (Other Permit Conditions, see Table 1-1.)   At this point, the permit
should be complete.  The writer should review the draft to ensure  that the
resultant permit is an effective tool  to monitor  and enforce source
compliance.  Also, the compliance inspector should review the permit to ensure
that the  permit conditions are enforceable as a practical  matter.
                                      1.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
II.   PERMIT WORKSHEETS AND FILE DOCUMENTATION
      Some agencies use permit drafting worksheets  to  store all  the  required
information that will  be incorporated into the permit.   The worksheets  may  be
helpful  and are available at various agencies  and  in  other EPA guidance
documents.  The worksheets serve as a summary  of the  review process,  though
this summation should  appear in the permit file with  or without a  worksheet.
Documenting the permit review process in the file  cannot be overemphasized.
The decision-making process which leads to the final  permit for a  source must
be clearly traceable through the file.   When filing documentation,  the
reviewer must also be  aware of any confidential materials.  Many agencies have
special  procedures for including confidential  information in the permit file.
The permit reviewer should follow any special  procedures and ensure  the permit
file is  documented appropriately.

III.  SUMMARY

      Listed below are summary "helpful hints" for  the  permit writer, which
should be kept in mind when reviewing and drafting  the  permit.  Many  of these
have been touched on throughout Part III, but  are  summarized here  to  help
ensure that they are not overlooked:

      •     Document the review process throughout  the  file.
      •     Be aware of confidentiality items, procedures, and the
            consequences of the release of such information.
      •     Ensure the application includes all pertinent review information
            (e.g., has the applicant identified solvents used in some
            coatings;  are solvents used, then  later recovered; ultimate
            disposal of collected wastes identified;  and applicable  monitoring
            and modeling results included).
      •     Address secondary pollutant formation.
      •     Ensure that all applicable regulations  and  concerns have  been
            addressed  (e.g., BACT, LAER, NSPS, NESHAP,  non-regulated  toxics,
            SIP, and visibility).
                                      1.5

-------
                                                      DRAFT
                                                      OCTOBER 1990

Ensure the permit is organized well,  e.g.,  conditions  are
independent of one another,  and conditions  are grouped so as  not
be cover more than one area  at a time.

Surrogate parameters listed  are clear and obtainable.

Emissions limits are clear.   In cases of multiple or common
exhaust, limits should specify if per emissions unit or per
exhaust.

Every permit condition is 1) reasonable, 2) meaningful,
3) monitorable, and 4) always enforceable as a practical  matter.
                          1.6

-------





























CS)
o^
Ol W
1—1 Iy
Cฃ M
g "

*~ w
zr lป
O f*

Q
H



H
CO
IT.
1*4

17
*H
2
ฃj
t^
H
ง
H




1
j
™"
bd
PS
H
M
M
ซ
CM






























0)
rH
E 43
O -rl
ri ra
b. -H

• ifl
Q
W 01
Oi fl
•rl
O 73

rH
4-1 U
0 fl
0) -rl
•I—I • —
43
P fl
m o
•H
ra 4->
0) It
U 4-1
rl -H
P S
0 -rl
ra rH

ri ra
o c
IH O
•H
73 01
0) 01
rl -rl
•H E
g,ซ
(U fl
rl (0
S
rH
0) ra
> fl
0) (fl
rH 0)
E
rH
0 H
rl U
4-1 ril
C ffl
o
O *-~
^^
0 45
-H .. 	
4-> H
(N
ra •
•H  01
ril 0)
SH
^J
01 0)
(U X
PP -1-1








[H
U
irf
n
o
•H
4-1 rl
(0 O
rH "1 I
p nj
01 ฃ
0
O -
0 >,
4-> 0) 0)
O rl
J_) J-) Q)
o p fl
0) O 0)
•n M
43 4-1
p >, C
01 rl P
(fl O
4-1 fl U
fl O U
(fl -H (fl
4-) 4-)
rH 4-1 4-1
i-H 01 fl
0 -H
ft rl

43 •!-! C
O (fl -rl
(fl ฃ A!
0) (fl
73 4->
rl 0)
O ra -
IH O ra
ft "rl
fl O ra
O rl (fl
-rH ft 43
4J
U >1 0
P fl 01
73 (fl (0
0) O
rH E 1

IH SH 43
O IH 1
0)
a) 73 ra
0) I) ifi
H 4-1 O
01 4-1
0) T-l (fl
73 E
0) fl
E o
p 0)
ฃ 43 -
•H rl
X 73 O
(fl rH 4-1
ฃ P (0
O rH
0) 3 4->
43 ra
4-1 X -H
0 fl
fl -H -H
0 43 E
3 73
73 ril
0) 4-1
ra u a)
(fl <: 43
43 4J
rl
~ -H 43
73 < U
SH -H
Ifl fl 43
73 tfl 3
fl 0)
(fl rH C
4-1 U O
01 -rl
0 4-1
fl 43 (0
O 4-1 O
•H -H
0) rl IH
01 /U -rl
•H 73 73
ฃ ฃH O
OPE















rl
o

0) rl
O O
rl 73 IH
P fl
O to ra
ra o
- P
43 ra Cr
o ฃ -H
P (1) C
ra 4-i 43
SH >i 0
O ra 4J
IH
- fl
 5 p
D CJ rQ
-H E E
43 0

tfl rH
43 r-l

-rl r— 1 P
•rl IH
ra (fl
0 [> 0
fl to >
•H -H
E rl 4-1
rl O tO
0 K>
4-i ra o
0) 0) fl
73 ra fl
ra -H
- 0)

4-1 O O
ra rH
O ft 4-1
U fl
fl 0)
rH O E
4) -rl 4J
43 4-1 (fl
4J rj 0)
O P rl

73 O
fl rl rl
tfl ft O

ra IH 01
4-> 0 fl
U -H
(fl fl fl
ft O tfl
E -H 0)
•rl 4J 1— 1
tfl U
O O
-H -H rH
E rH 0)

fl ft IH
O (0
CJ 0)
0) 43 fl
01 -H
73 P 73
fl 0 P
(0 rl rH
43 U
- 4-1 fl
rH -rl
tfl fl
4-10-
fl -H ra
0) 4->  73 0
CH O U)
0E4,
















D
NrH
01 43 SH
O to O
rH O
O -H rH
fl rH (8
O ft -H
(U nj Q"
4J O
XrH
O ftj G
rl 43
4-1 >, O
C 43 0)
O 4-1
O 73
(0 4-1
0) 3 (0
43 M 5
fl3 r— 1
•H Cfl W
•H D
fO W CJ
> C -H
(0 O E
•H rH
4-1 W Q)
ra ra 4J
0 -H 01
43 E 73
o
IH rl
O 0 O
43 4-1
fl 4-1 (0
O rl
•H 73 4-1
4-i d) ra
(fl 0 -H
U 0 13

rH 0 E
ft 73
ft 73 ril
(S rH
P 0
rH 0 43
rH 3 4-1
(fl
43 43 1-1
ra O M
•H
4J 43
C 3 •
0 H
ฃ> 4J ^D
0 fl
fO 73
0 4J fl
fl P (B
rH
fl rH 0

ft
ra
• rX ฑJ
4-1 fl SH

(0 a,
4J IH
P O K
i— i &,
rH 0) O
O C
ft 0 0
•H ^
43 01
O ซ1 SH
p -H 0
ra E 73
0 H
IH p
O C
•H 73
rH SH
O 4J (0
rl H 73
4-> P C
fl ra (fl
O 0 4-1















4-1
-H
fl
P

ra
o
-H
01
•H
E
0
10
rH
P
O
•H
4J
1

O
rH
o
'O
0
4-)
1
D M tn
MH P| O
ฃ rH
-H D O
Q rj
T3 4U
rl ^i U
fi5 nJ D
73 E 4-1
(fl - rH
4J IH O
01 O SH
0 4-1
ra rl fl

O 43 o
•rl 4-1
01 0
01 fl rH
-H O 43
E -H (fl
0 4J rH
tO -rl
fl fl ffl
Ifl -H >
43 (fl
u j!
O O 4->
o 01
c 
0
X -H
0 X
P U
ra (0

IH X
O U
-H
fl X
0 3
•H
4J ra
tfl fl
4J (fl
fl 0
d) E
E

rH 43
ft
E 0)
•H O
>< tfl
43 -H
rH
0 ft
rH E
43 0
(fl L>
ฃ>
0 SH
•H O
X 1-1
O
(tf 0
73
fl -H

•H O
J_l ^1
0 ft
p
73 rH
0 rH
SH (fl
X
ra ra
fl
O 73
•H a
ra ITS
ra
•H
E fl
0 O
-H
(D 4J
X Ifl
4-1 SH
V
X ft
4J O
rl
O SH
1H O

4-1 0)
0 O
ra -H
4-1
- U =
0) tfl •
rH rl 0)
43 ft 4-)
•r( rH
ra A; p
ra SH ra
000
ft 3 rl



















0
X
4J
E
0

fo

0
o
SH
p
O
ra

0
X


ft
p

0
y
(fl
g

SH
0
X
4-1
0
01
0
4-1

4-1
tO
X
4J

fl
O
-H
4-1
tfl
o
o
rH

Ifl

4-1
tfl

ra
0
-H
4J
•H
rH
•H
O
(fl
IH

01
fl
•H
4->
4-1
•H
E
0

rH
(fl
P
73
•H
[>
-H
73

•rl

0)

^
m
4J
•H
fl
S
fl
o
-H
m
m

g
W



SH
O

m
4-1
•rl
ฃ
0
X
O
•H
X =
4-1
0 U
O ril
SH
p 0
O X
01 4-1

>1 rl
rl 0
(0 73
C fl
O P
•rl
4J fl
(0 O
4-1 -H
m 4-1
tfl
Ifl rH
P
IH 0)
0 0
rl
4J
rl O
(fl 4J
ft
4-1
>i U
C 0
(fl T"1
= 43
P
ra ra
C
tfl 4-1
0 fl
E to
4-1
4-1 P
•H rH
rH
- O
— ft

43 >>
— fl
H Ifl
OJ
• 4-1
CN -H
m E
0

Pn O
C_) 4->

O rH
^ tO
•rt
0 4J
0 fl
C 0
0 4-)
rl O
0 ft
IH
0 0
rl X
— ' 4-1

fl 0
0 >
•H tO
4-> X
(0
rH 73
P rH
01 P
0 O
SH 3













_
^1 ~!
•H _j
rt ^
IU
i SH
(0 O
E IM

4-) ra
(fl ra
X 0
4-1 SH
0)
C C
0 O
•rH 0
4-1
(0 >i
SH 43
O
•rl >,
rl rH
0 -rH
4-1 rl
0 O
73 4-1
P
>i 4-1
4-1 (fl
•H 4J
rH ra
(fl
P 73
(31 0
fl
rl -H
•rH IH
(fl 0
73
IH
O 0
(H
rH 0
0 3
>
0 ra
rH 4-1
fl
0 0
rH E
43 0
•H rl
ra u
ra fl
•H M
E
SH
0 •
ftrH
0
ฃ >
P 0
E rH
-H
(fl 4-1

i-H
0 (fl

H &



in
fl
01


S4
u
fl
H

ra

rn 01
g1 C
i-H [_j
rrt -r*
43 M
•gy
ra ฐ
2 0
n 0
U
rn tQ
ra "U

0 _g
r~J
to
P cj
u 0 •
w , S^
frt *f~' r^
10 01 r-l
^•rl >
*> e -H
"O ^ o

rrt rH 0)
?! (0 ft
5p™
J-: 4-1 0
fi1 0 rl
0 *

ri "0 r?
0 <" ง
0 4J H
73 ^ 73
0 •— ' fl

ง SH ^

3 fl 0
o ฐ w
g -H -v.
ฐ 4J S
m 0 0,

"H rl rl
jj 4-1 O
fi ra IH
d
c: O 00
g O 00
rl ฐ^

fl 43"H

H 73 00
fl
. (fl >1
X rl
O 0 tO
S 4-1 P
(0 SH
M 73 43
O 0
IH 0 PL,
fl
ra -H 73
4-1 rH fl
c 0 (0
0 ra
E (0 -
0 43 in
SH r-
U 0 m
C X H
-rl 4-1
^
73 SH yp
0 0
4J 4-1 >i
(fl IH SH
01 (fl (0
rH P
P 01 fl
E fl (fl
0 -H h3
rl SH
ft SH SH
P 0)
ra u 4J
tfl U IH
x o ifl













-------
































frt
m
2^
3
SI "
0. 'H
2 ฃ
r-H K
a: g
1 i 1 ^_,
03
o w

o ;ง
O K
E-]
"



ง
A

Q


CJ


W
CO

S
o
.
ง
o
H

H
M
H
M
w
ซ

1

"i

?s
H
H
3
r?
ft
S
ซi























g
OJ
4-1
01
^
to

X
fl
IB

01
C
18
ID
g

=
r"i
Ol
o
rH
O
G

O
OJ
4-1

rH
0

4-1
fl
O
U

OJ

•H
4J
(8
ฃ
ฃ
rl
M
E

^-^
^-^
0\
T-H
- —
^^
ฃ

H
CN

fNJ
in

Cฃ
pt4
U

o


OJ
o
fl
OJ
SH
OJ
n [
ID

—

G
0
-H
4J
(B
rH
3
Ol
OJ


OJ
43
4-1

E
0
to
H
0
SH
4J
a
o
m o
> H
-H 0
> 0
O 01
a H
H


E
OJ
18 4J
01
OJ >-,
> 01
(0
43 rH
0
T) to
rH 4-1
3 fl
0 0
3 0

-U >,
3 C
43 Ifl

- G
OJ (fl
U fl
•H 4-1
J_)
U fl
ttf O
lM -H
p, Jj
u
G 3
•H T)
OJ
•a vi
OJ
4J 01
(0 fl
rl O
4J -H
01 01
C 01
O -H
E E
OJ OJ
Tl
01
>>i 3
rH O
01 3
4J fl
(0 -rl
&| 1
rl
0 O
Tl U
(0

C OJ
OJ 4-1
OJ IB
43 
43 OJ
-rl
4-1 43
m o
43 m
4-1

rH O
o
SH 73
4J O
fl O
O 43
O -rl
rH
fl OJ
o ^i
-rl -rl
4-1 rH
3
rH rH
rH (8
O -H
ft 4J
G
SH (8
•H 4J
(8 01
Q
O 01













^
^,
Ol 4J
SH 01
OJ -H
G X
OJ OJ

IH CO
O fl
O
01 -rl
E 01

ID '>
4-1 O
SH
fl ft
•H
 OJ
(8 >i
(8
01 rH
c oj
O Tl
•rl
4-1 rH
CJ Ifl
3 -H
T3 O
Ol OJ
^1 ft
W
OJ
rH
Q
(fl
SH •
(C 01
ft 4-1
E o
O (fl
CJ ft
E
4-1 -H
01
(fl rH
OJ (8
rH 4-1
ฃj
4-1 OJ
(fl E
fl
Ol O
G SH
-H -H

OJ G
•H OJ
43
CJ N
(fl 4-1
•H
IH rH
O (fl
3

o
SH
OJ -rl
U (fl
•H fl
4J O
0 G
(fl

ft 0

4-1 -
G 01
OJ CJ

to 'g
3 O
0 C
0
G U
•H OJ








































tn
OJ
3
O1
•H
G
43
O
OJ
4-1

rH
O
to
4-1
0
O

OJ
ฃ>
•H
4-1
(0
[>
0
G
C
-H

OJ
CO
O
ft
O
rl
ft

01
4-1
G
(fl
U
-rl
rH
ft
ft
(fl

G
ID
43
3

TJ
OJ
-rl
rH
ft
ft
10

OJ
43

X
m
E

4-1
(B
4-1














4-1
G
OJ

G
-H
IB OJ
4J to
4J 0
Ifl E
G
O OJ
G 43
4-1
O =
4J
OJ
4-1 O
0 SH
01 3
•n 0
43 to
3
01 X
C
OJ (fl
U
to S-l
3 0
0 IH
01
to
(B fl
(B
1-1 O>
0 E

Tl 4J
OJ -rt
to
•H -
o1"
01 (B

in
rH ID
OJ rH
ฃ>
OJ rH
rH in

rH K
O PK

4-1
fl 0
O M"
O
OJ
D o
fi a
4-> OJ
rl
01 OJ
-rl 1-1
ID
OJ rl
JJ —
IB
erf m
c
01 O
fl -H
O 4J
-rl 18
in i-t
tn 3
-H 01
g OJ
w to

OJ 0)
rH 43
Q 4J
Ifl
> E
OJ O
•H SH

O
rt

4-1 3
01 OJ
0) -rl
3 >
SO)
to










CA
W
j

















































01
G
•H
3
0
rH
rH
0
IH

Ol
rj
4J

G
0

•a
01
CO
(0


01
G
0
•H
TO
to
•ปH
E
OJ

IH
O

OJ
4J
(fl
SH

4J
G
OJ
Ol
G
•rl
^
4-1
to














•a
OJ
tn
>-. 0
G ft
(C O

u ft
0

G J3
(fl 4-1
rH
ftlH
0
G
O rl
•H O
4-1 4-1
(8 (fl

G OJ
OJ ft
E 0
OJ

ft O
E
•H to
OJ
Ol G
43 3
4-> O

G Oi
•rl 43
4J

oj 01
fl 01
•H OJ
10 rH
4-1 G
G 3
O
O -
OJ
to o
•H SH
3
43 O
U 01
-H
43 >,
3 SH
fd
G G
0 0
•rl -H
4-1 4-1
Ifl Ifl
4J 4J
•H 01
E

rH O

01 >,
fl to
O O
•H 01
01 oj
0] 4-1
-H (fl
E U
OJ

4-1 O
fl
OJ 01
Ol 01
G (fl
•H rH
rl O
4->
01 43
O
4-1 3
01 01
O

O
OJ IH
43
frt OJ
4-1
— (0
(B 4-1
— CO






































SH
O

• ~
OJ
H
43
(0

OJ
•rl
fl
O
(B

4-1
O
fl
OJ

(8

tn
fl
o
-H
4J
(fl
4-1
•H
E
•H
rH

43
O
3
tn

4-1
(5
43
4-1

01
OJ

(fl
^J
4-1
tn
fl
o
E
OJ
Tl

01
u

3
0
01

X
^
(8
fl
o
•rl
4J
(8
4-1
0]














>,
to
O
01
OJ
4J
(6
O

SH
0

01
tn
18
rH
CJ

43
CJ
3
01

>,
43

OJ
O
•H
4J
O
(8
SH
ft

fl
-H

T3
0)

OJ
-H
43
0
Ifl

to
•H

43
CJ
-H
43
3

H
0
•H
4-1
m
4J
•H
E
-H
rH

CO
fl
O
-H
01
0]
•H
E
OJ

4J
fl
OJ
O)
G
-H
to
4->
01

4J
01
O
E

OJ
43


,-^
ฃ













OJ rH
r-H rH
43 Ifl
10 43
> tn
OJ
•H 4-1
43 fl
CJ OJ
(0 >
0)
4-1
01 O
OJ fl
3
O C
rH M

0)
fl •
4J 01
CJ
CO SH
fl 3
(fl O
OJ 01
E
X
- SH
G (fl
O C
•H O
4J -H
(0 4->
O (fl
•H 4->
IH 01
•H
Tl 1C
O
E fl
•H
IB 43
4-1
O -H
4-1 3

T) 01
01 4J
•rl -H
rH G
ft 3
ft
(fl tn
G
G O
01 -H
43 tn
3 01
•rl
- E
G 0)
o
•H Tl
4-1 0)
Ifl -H
4-1 M 1
•H -H
E Tl
•H O
rH E

01 to
•H O
43
H 3
OJ
fl

tn oj
OJ 43
CJ 4-1
V-l
3 4-1
o o
01
OJ
>i 4-1
to ifl
ifl SH
fl
O 01
•rl G
4-1 O
(fl -H
4-1 01
CO CO
•rl
4-1 g
O 0)













rr

OJ
o
G
(tf
E

0

C to
(D OJ
ft
4-1
•H IH
E 0
OJ
T)
0 to
4-> IB
•a
OJ fl
CJ (0
SH 4-1
3 tn
O
01 oj
o
X to

(fl O
C to
O
-H 3
4-1 OJ
(8 G
4-1
01 oj
rH
•d 43
a) (fl
•rl O
IH -rl
•rl rH
T) ft
O ft
E (C

SH G
O (8

3 SH
OJ OJ
G Tl
G
T) 3
OJ
to ID
0 rH
ft 43
0 18
to 3
ft O
rH
(B rH
(8
4-1
•rl 4-1
E G
M 3
ID O
ft E
18
g
to 01
0) 43
4J 4-1

OJ 1-1
43 0
4J
tn
1H 01
O OJ
u
G X
O OJ
-H
4-1 fl
IB -H
CJ
•H 4->
rH fl
ft 1C
ft 4J
1C 3
rH
(D r-H
43 O
4J ft













C\J

-------































rrt
fM
•-1
2
ta ^
1 — o"ป *r"'
O"> -^
U_ rH R
U
^ UJ —
CO

^ i_ w
o *5
do ซ
w


OS
2
&

o
H



ซ
w
W

w
o
.
ซ
CJ
H
t-1
H
ง
M
?i
W
H

1
^
^i

r^
H
p
M
n
S
3
"ซ


















O
4-1

4-1
O
0)

rfl 43
3
R ra
•rH
01
01 -H
R
-H -
4-1 Ol
rH SH
3 O
01 IH
Ol 01
SH SH
01
0) 43
U 4J
SH

0 4-T
w ra
43
>< 4-1
fa
rt —
R 01
O H
-rH 43
4J ra ••
rt 4-i —
4-1 — -
01 01 CN
•H • —
SH 43 —
O 4-1 43
•n • —
n) R rH
E -H CN
01 Ol CN
R SH in
•H 0)
4-i 43 r*^
01 3 h
•H Ol CJ
X 01
d) rH 0
0) <*
R
n) 73 0)
0) CJ
0 R R
4-1 -H 01
4-1 rH
R 01 01
O 73 4-1
•H -— 0)
4J SH
rt a) "
CJ ra
•H ra R
14-1 0) O
•H rH -r-l
73 O 4J
O R rt
E -H rH

rt ra 01
R 0)
ra o SH
•H -H
01 0)
R ra 43
O -H 4J
•H E
4J 0) g
rt o
cj 4-1 SH
•H HI fa
IH R
-H
73 4-1 •
0 R 3
g rt 0)
O -iH
SH -rH >
O 4J Ol
•n -H rH
rt R
E 01 Q
-H U)
 >i
rt R
SH n)
Ol
ft 4H
0 0

4-1 O)
O 0]
rt
73 0)
0 SH
43 CJ
4-1 R
0) -H
E
01
01 R
43 O
4-1 -H
01
R 01
•H -H
e
01 01
01
R 1 1
rt Q)
43 R
u
4J
S-l H
O co
U
R -H
-H 4H
•H
Ol R
01 01
R -H
rt ra
r;
o ซ

rH R
rt -H
CJ
•H 4J
ra rH
N 3
43 01
a 01
SH •
>i 4J
R 73 0
rt rH rfj
3
ra o cu
R 3 43
rt 4-1
0) 4J
E ra rH
43 0)

R u "R
O Ol 3
-H U
4-1 SH R
rt 3 0
CJ O -H
•rH ra 4J
4-1 rt
•H >, rH
73 SH 3
o rt 0i
g R 0)
O SH
SH -H
O 4J O
•r-i ซ 4J
rt 4J
S 01 4J
' CJ
rH 0)
— 0 -n
•H -I-, 43
— ซ 3
= E 01


















cu
43

rH
rH
ra
43
01

01
73
R
3
O
a
E
o
O

U
•H
R
a
01

o

Ol
r-l
•rH
4-1
rt
rH
O


O
4H

J-l
R
ra
CJ
•H
4H
-H
R
01
•H
ra

01
-H

4-1
rt

4J •
01
O) R
o] O
ra N
0) O
^|
CJ SH
R 0
•H 4-1

ra 4-i
R R
o ra
•rH CJ
01 -H
01 4-1
-H -H
g R
Ol 01
•H
4-1 M
01
R 73
0)

•H
— ra
-H R
-H O
*- cj































D
73
3
rH
o
R
•H

4J
0
R

rH
rH
ra
43
ra

R
0
-H
4J
rt
SH
0)
a
O

4H
0

73
O
43
4-1
01
g

01

4J

R
-H

Ol
01
R
rt
43
u

M
O

Oi
01
R
rt
43
CJ

rH
rt
O
-H
ra
^
a

~
-H
-H
•rH
~




























































• *
4-1
R
01
g
0)
CJ
rt
rH
a
i)
SH

73
R
rt

SH
-H
ra
a
o>
SH

^
0)
o
R
rt
R
O)
4-1
R
•H
ra
g

0)
H
-H
4-1
O
SH

, 	 .
rt




















•-
4-1
O


Ol
43
4-1

4-4
O

in
CN
H

R
O
-H
4-1
O
0)


SH
0)
73
R
3

0)
rH
3
SH

SH
O

SH
cu
73
SH
0

R
rt

4-1
0

R
0
ra
ra
0)
SH

^y,
Q

rH
OJ
3
4-1

CU
[>
•H
4-1
rt
R
SH
CU
4-1
rH
ra

R
rt

4-1
0

ra
3

^-^
u
~











73
0)
4-1
ra
fa
01
R
0)
01

ra
•H

rH
01
3
4-1

Ol
43
4-1

4-1
ra
43
4-1

4-1
R
0)
4-1
X
01

Ol
43
4-1

O
4J

4-1
•r-l
R
3

01
R
•rH
4-1
rt
SH
01
R

01

E
ra
01
4-1
01

rt

4-1
ra

rH
0)
3
4H •-
0)
01 4-1
> ra
•H rt
4-1 3
fO
R 73
SH -H
01 iH
4J O
rH ra
re
rH
R rt
ra ft
-H
4H CJ
O -H
R
CD 3
e6
E
~ 0
73 SH
— 4-1


































43
O
•H
43


0)
0
SH
3
O
01

^
SH
rt
R
0
-H
4J
rt
4J
01

rt

^K,
43

rH
rt
•H
SH
0)
4-1
rt
E

3
rt


^
0

rH
0)
3
4H

01

•rH
4-1
rt
R

CU
4-1
rH
rt

R
rt

4H
O

01
01

^^
0)











M
4J
S-l
rt
CD ft
Q ^Q
3
73 W
rH
3 K
O Cij
3 U
SH
0) 0) 0
rji 4-i *iป
R 4J
rt rt o
43 4J
CJ 73
01 4-1
43 43 R
u ra rt
3 -H 3
01 rH U]
43 SH
ra ra 3
ra 4-1 ft
O) ra
rH 01 73
R 0)
3 ra >
ra o
- 3 SH
in ft
r- 43 a
cr> cj rt
H -H
43 ra
- 3 H
(s> O
R -H
>, O 4J
SH -H ra
rt 4-1 rH
R 73 01
rt R 0)
1-3 O SH
O

S-l 4-1 0)
0 -H 73
4-1 E R
0) SH 3
43 0)
a SH
01 O
R cu
•H rH H
4-1 43 CN
rt rt •
73 0) rป
0 U in

E O ซ
O 4H fn
0 R CJ
O 0)
rt o
t>* ^*
4-1 rH
O rH O
ra 4-i
0) SH
rH 0) 4-i
43 73 R
ra 01 ra
a fa 3
rt ra
o N SH SH
R 3 O
01 rt a
rt
3 SH - ID
01 in u>
0) 73 r- rH
u R en .
SH 3 H rH
3 in
O 73 -
ra 01 u> di
4-1 pM
0) -H >, CJ
43 43 SH
EH -H rt O
43 3 ^f
— OR
rH rH rt rH
" ft 4 O












ra
R
0
•H
4-1
ra
i— i
3
01
0)
SH

SH
01
73
R
3

SH
O

iH
CN

01
in

A
fn
CJ

0
^

rH
0)
73
R
3

73
4)
ra
ra
•H

4J
-H
E
M
01
ft

^
R
ra

fa
0)
73
R
3 •-
145
CU 145
ra rH
3 •
rH
O in
4J
PH
73 fa
CD CJ
ฃ>
O 0
SH ^
ft
ft 0
ra 4-i

ra 4-1
•rH R
rt
0) 3
u ra
rH M
3 3
O ft
ra
73
H 0
SH
— ft
CN ft
— rt













0)
43

73

3
O
3

Ol SH
01 CU
R 4-1
rt 4-1
43 rt
u
73
43 cu
U 43
3 ra
ra -H
rH
ra 43
01 rt
CO 4J
rH ra
งcu

01
- rt
0) 3

rt 43
rH O
•H
R 43
0 3
•H
4-1 R
U O
3 -rH
73 4-i
O -H
SH 73
ft R
O
cu O
43
4-1 4-1
-H
R E
•H SH
(U
SH ft
0
01
R rH
O 43
-H rt
4-1 0)
rt o
SH SH
0) O
a 4-1
0 R
0)
4H
0 >.
rH
m rH
SH rt
3 SH
O cu
43 73
0)
0) 4-1
43

^ R
R rt
•H
SH
01 (U
ra 73
rt R
cu 3

CJ 73
R 0)
•H 4-1
•H
R 43
rt -H
43
~ o
4-i SH
— a










M
4-1
^1
ra
a
43
3
C/3

K

CJ

o
^

O
4-1

4J
R
rt
3
01

3
a

73
01
>
o
rH
a
a


01
R
o
-rH
4-1
rt
rH
0)
CU
rH

SH

> H
01 •
rH iH
in

fa
&u
rt o
3 M-
R
rt SH
fo O
























































—

01
u
SH
3
0
ra

j>,
SH
rt
R
O
-H
4-1
rt
4J
01

rt

4-1
rt

ft
•H
X
ra
SH
0)

ง
O

R
•rH

01
01
R
rt
43
CJ

rt

, —
01











ro
 ra

-------
    m
oc ฐ
   E
 0  Q   O
JJ  W   rl
    ft   3
 0)       O
 N  O   CO
•rl  JJ
 co       >-,
    JJ   rt
jj  u   id
 c  <  G   S
 rl   O   >H
 id  -H   ID
 G   JJ  1H
 O   id   0)
•H   O   rl
 Jj  -rl  -—
 id   IH
 JJ  -H   C
 CO  73   O
     O  -H
 rl   g  JJ
 O       id
•O  rl  rH
 id  O   3
 E -n  01
     id   (D
                 o
                CO
                 id
                 a
                 o
                -H
                JJ
                 id
                                     i   id
                                O rH  O
                                JJ  O  O

                                rH IH   -
                                id      jJ
                                                           G
                                                         - o
                                                        co  X)
                                                                                     a)
                                                                                     oi  m
                                                                                     id  G
                                                                                     SH -H
                                                                                 co  O  tn
                                4->O
                                        IdrlrHErlldGErlrl

                                        0>  Id   Id          r-H-HOJJO
                                                                !  JJ  H       JJ
                                                            M  C  O    - -H
                                                            oi -H —-   jj  a
                                                            >  tn      30
                                                     o
                                                     X!   -
                                                         co
                                                     rl  JJ
                                                     (D  PI
                                                        a  a)   co   a)  -H  jj
                                                            ^1  JJ  rH
                                (D  O
                                   •H rH
                               X! JJ  id
                                o  id  E
                                                            ID   co  G
                                                                   JJ  3
                                                SH-Hfi      3
                                              ~OO      CM-I
                                OOJCQrHE-Hc;>
                                 rl   3   O
                                •H   CO  -H
                                 Id      rH
                                    JJ  rH
                                IH   G  -H
                                 O   id   E
                                    Jj
                                 O  rH  (N
                                 rl   O
                                o
                                to
                                            g-HId   ~  (1)  CJ   CO   (U
                                                         rH  rH   O   rl  O  0)
                                                          3   Id  -H   3      E
                                                          a      G  IH   ~  CO
O
O X!
S-l  10
                                                          id   g    -      id  (D
                                                          rl  -H   CO    - rH  rH
Id  rl
O  ซ
                                                ai  O
U X!
id  o
a
id 73
U  G
    id
                                        IUrl4JErHW-H
                                •H   (D
                                JJ   rl  IH
                                 id   o   o
                                JJ   E
                                 co       tn
                                     H  JJ
                                 tn  o   H
                                 G       id
                                •H   H  rH
                                 3   id   a
                                 O   0)
                                     au
                                0)      OJ
                                                         rH  rH   ax;   a  co
                                                          id  i—i   o           to
                                                          E  -H   o    - ,y   ID
                                                          HE       >i  O   O
                                                          0)       >i  id   o   o
                                                         X!  rH   rl  73   SH   M
                                                         jj   a)   id           n
                                                            x!  (d
                                                         MHj3MH
                                            fSrlrH
                                 id  -H
                                                        O  JJ  G
                                                            C  id
                                            -H,
                                                                       jj  a
                                                                        o  id
                                                                        (D
                                                                        co IH
                                                                            O
                                                                        tn
                                                                       •rH  ID
                                                                       x:  in
                                                                       JJ  O

                                                                       in
                                                                        O  rl
                                                                            O
                                                                                       —  id
                                                                                       -.  ai
                                                                                       H  >,
           X!  (U
           —  a

           x:  to
            a  G
            id  o
            rl  JJ
            tn
            id  o
            M  in
            id  oi
            a
                                                                                       T3
                                                                                        0)
 O  rH
 (D   Id
 a -H   s-i
 tn  jj   o

 (D   (D   -
 N  JJ  JJ
•H   O   U
 en   a <
                                                                                                     HI  ID  01
                                                                                                     o  xl  x!
                                                                                                     rl  JJ  JJ
                                                                                                     3
                                                                                                     O  CO  rl
                                                                                                             (D
                                                                                                             73

                                                                                                     &SH  ง
                                                                                                     id  o
                                                                                                     G      d
                                                                                                     0-0
                                                                                                     •H  tn
                                                                                        co
                   -H
                   jj
               •H  id
                g rH
                ,
rl
id
G
0
•rl
JJ
id
JJ
CO

id

jj
id

H
3
o
u
o

73
rH
3
O
3

jj
id
XI
jj

0)
tn
G
id
X!
o
rH
18
O
•H
to
>,
XI
a

>,
S

^^.
0

CO
id

	 	 	
rH
• —
	
XI


X!
a
id
JH
tn
id
SH
id
a

rl
,
1-1
•rH
rH
id
3
tr

(U
CO
-H
3
rH
ID
X
JJ
O

JJ
o
G

0)
O
rl
3
O
CO

>,
SH
id
G
O
•H
jj
id
jj
tn

in
0
-n
id
E
id

CO
id
tH
• — •
__
Xl


XI
a
id
H
tn
id
SH
id
a




in
rH
(D
cn
jj
•H

>,
Xl

o
o
!H
3
O
CO

>,
S-l
id
G
o
•H
JJ
id
jj
CO

SH
O
•r— 1
Id
g

id

(a
jj
3
jj
•H
JJ
CO
G
O
u

73
rH
3
O
3

tn
(1)
tn

id
X!
0

(D
XI
JJ

1H
-H

^
(D
O
SH
3
O
CO
>>
S-l
(d
G
O
•H
JJ
id
jj
tn
SH
O
•n
Id
g

T3
O
SH
(U
73
•H
CO
G
O
O



S-l
O
MH

SH
O
•r— I
id
g

co
•H

JJ
id
X!
jj

ID
U
rl
3
0
CO

>,
rl
id
G
O
•H
JJ
id
jj
CO

H
O
•n

E

<
. — .
-H
•H
— '













































































=
(D
G
0
N
O

rH
O
in
H
O
•n
Id
E
>,
jj
•H
rH
id
3
W

rl
•H
id

jj
G
(D
•H
n
g
id

E
3
E
•H
G
•H
S
(D
XI
JJ

SH
O
1H

CO
73
•H
id
73
G
id
jj
tn

rH
id
•H
0)
73
(U
fn

(D
rl
id

co
73
SH
id
73
G
id
jj
w

><
jj
•H
rH
id
3
CX

SH
-H
<
JJ
G
(D
-H
Q
ฃ
<

rH
id
O
•H
JJ
(d
S




CO
JJ
G
id
jj
3
rH
rH
O
a

id
•rt
SH

id
XI

S
(U
XI
EH



(D
M
Id
1H
t-H
(D
3

73
G
id

XI
jj
rH
id
(D
X!

0
•H
rH
XI
3
a

jj
o
(D
JJ
O
H
a

0
jj

73
(D
73
I)
(D
G
















































XI
O4

73
G
id

ป
, 	 .
U
O
>


m
O

-
o
CJ

*
o
^

o

pj

DJ

M
o
co

tn
G
-H
73
3
rH
U
G
-H
                 id
                 S
                                                                                                                                    OI
                                                                                                                                    i

-------




























, ta
1— en
en
U_ ^H
_. o:

S3
rd
4J
03

T)
4!
01
(0
42
i
>.
Dl
O
rH
0
(3
U
41
4J
rd

us Air Pollutants, is
o
•d
Hazar
SH
o
4H

•d
rl
rd
•d
B
fd
4J
CO
B
r National Emissio
o

ป.
a
X
co
W
S5










ft
^t
g
01
W
%




01
0)
• H
r<
0 g
Ol P
4> g
4-1 -H
rd B
U -H
g
01
U 01
rl 4J
P P
0 rH
01 O
01
>.43
SH rd
rd
B 4-1
0 B
•H 01
4J 01
rd 41
tants from certain st
ey apply, NESHAP repr
P 43
rH 4-1
rH
O 01
a SH
41
SH 43
•H IS
rd

01 •
P 4J
0 0
•d <;
rl
rd SH
N -H
n) <;
43
B
rl Id
O 01
mance prescribed f
tion 112 of the Cl
nts for BACT.
SH U 41
O 01 g
IH CO 4)
SH SH
4) SH -H
a 4) P
•d rj
IH B 0)
O P SH














01 -
4-1 IX
B rH
rd a
4-1 a
P rd
rH
rH >,
O 01
a43
4-1
rO
•H 41
SH SH
41 01
4-1 43
•H 5
SH
O

SH 4-1
0 9
UH  ro rO
B (3
Ol O -
-H -H B
01 iH 4J O
4) rd ro -H
•d 4-1 4-1 4-1
C to rd
g 01 4-1
rd g SH 0)
SH 41 O Ol
Ol rl -n 01
O U ro >
SH B g
a -in
O 01
01 T! 4-i rH
BO) -H
-rH -H EH O
4-> IH CJ 01
4J -H  01
01 >, • rd 4)
•H 0) rH rH U
43 41 P O
B > Ol SH
O 01 41 41 a
-H Tl H SH
4-1 id Ol
ro SH 0) SH B
SH Ol B O -H
O 01 -H IH 4-1
-H T) rH 4-1
SH 01 01 -H
01 4J 01 B g
4J O ro O SH
01 B 43 -H 01
n of significant d
air quality does
bove a prescribed
nd major modificat
y impacts in the p
O 01 rd rd 4-1
•H SH -H
4-1 P W 01 rH
B W 4-1 01 -H
0) B B U 43
> 01 P rl -H
4) O P 0]
SH O g O -H
ft 4-1 rd 01 >











Q
CO
Pi







J 1
u
<<*

^_l
-H
f-f
f^t
^
ni
<1)
i — i
ฃ_j

(U
Jj

M-l
0
>1
1 I
:ed under the authoril
fO
r— 1
3
01

X M
<•> O O
o a co




























•—*
CO
K

m
B
>r^
T)
P
, — |
rj
rj
-H

LJ
metric diameter
- Total reduced sulfui
o
SH
0)
rd
ss 1
4-> 0
rd -H
g 6

0) O
4J H
rO V|
rH
P •ฃ
0 4-1
•H -H
4J 3
SH ,
to SH
Total suspended p
Particulate matte
Carbon monoxide
Lead
i i
^-^ — '
ft S
CO S
EH ft
S S O 43
ft ft L> ft
























• — >
CO
D?

0)
^
-H
13
P
,__!
fj
q
-H

Uj
TJ
P
3
n
- Reduced Sulfur Comp<


co
Q
rt












Asbestos
I




01
<










































- Benzene
- Radionuclides
- Arsenic


N Tl 01
m P4 <












Beryllium
Mercury
Vinyl chloride





01 Ol U
m x >










































- Chlorof luorocarbons
- Radon-222

0*3 W
01 (N B
- cs O
U 1 rH
fe B rd
U K X











1 \
Fluorides
Sulfuric acid mist
Hydrogen sulfide




ซ
O
ฐi ฐ?.
CM S3* P?














 o
 a
 rd

 o
-H
 4-1
-H
•d
•d
 rO
4-1
 a
 (U
 01
 OJ
 SH
ft
en
oo
en
 (U


I
 01
-H   SH
    -H
 01     S3
 SH   O
    •H
IH  4J
 O   ro
    rH

 ra   Oi
T!   O
 0)   4-1
 O
 (3   4J
 S   U
 SH   01
 (U  T-l
in  X!
 0)   P
 SH   01
     o
     01

-------






























* *
T?
d)
3
._ ^ s
1— CT> 'rt
m e
^ 0
< ฃ H
CO
rv* O rn
t-L- | 	 C/J
O "
do ซ
W
EH

K
01
53

Q
W
B
H
i-3
H
CO
b
O
DEFINITION

1
rt!

W
H
M
Oi
Pi



























_jj
ฃj

co "I
d t; cu
O jr o
•H ^ d
to TJ cu
co " SH
•H ^ CU
E - IH
v u ?
, rd ^
t^ S ""
d "
rrj d
^ 0 ฐ
'H OH 'H
14^ 4H jj
•H jj ">
S. u d
S1 e S,
•H ^ Ol
m cu i"
^ ^ SH
td •"
rlT Cfl 1
CO ™ 4J
d 3
2 N
"1 CO P
4J "' SH
S d fc
S8
iw t-
•H ^ O
73 ^ co
o -g to
e g, cu
. (ii J^
SH JJ 0
o " d
-n ^ -H
c CU n
g ^ ra
'S d
T3 > 0
d ซ -H
id K ra
ra
CO -rl
0) 6
u cu
rl •
P 3 4J
o cu cu
CO -H d
>-i 0) 4J
SH rl d
or stationa
•iggers PSD
a significa
•n M
ni -u en
E d
CU -H
3 co O
cu to O)
d cu SH
V-i cu
SH O 73
odd
ftl -H p


01
m
id
CO
k
o
a
H

m
a
o
m
ra
•H
1
w
4J
a
10
U
•rl
M-l
•rf
C
Ol
•rl
01



















































m
01
2
H
Ol

01
l/l

Q4
Cb
U

O
^C



























y<
O ra
d
cu o
U -H
ri ra
P ra
O -rl
co E
cu
M
O *J
-n O
m
E 0)
4-1
73 ro
0) M
•H
MH Id
•H
73 -
o m
E 4-1
d
to id
4J
E P
O rH
SH rH
IH O
ft
0)
ra O)
rd d
0) -H
V4 3
0 0
d rH
-H iH
O
ra MH
f3
O 0) "
-H xl ra
ra 4J 0)
ra 4-i
-H m id
E 0 SH
0)
>i Ol
4J d d
cu id -H
d 3
4-> O
Id -H rH
E rH
O 0) O
4J 4H
O
CU 4J 0)
0 XI
in referen
ajor source
ed any of t
-go)
CO U
d 3 X
id cu cu
cu d
E rl
id O
4J MH rH
d o id
td P
CJ rH O"
•H rd 0)
IH -rl
•H 4-1 73
d fi rH
O) 0) P
•rl 4-> O
CO O 3
= PJ
4-1
— cu id
•H XI X!
— - 4-1 4-1
































































&
4J
SH
id
0)
>*
rl
CU
^ >,
s &
0 N
4-> ft >* in
4J ft 01
O 4-1
0 O
H ^ 0 ••
•* in
CU
.. .. jj
CU CO •• 4J
T3 CU CU Id
•rl T) T! E
X -H -H
O X X cu
d o o 4-1
o -H id
g d 73 rH
CD p
d Oi ^ o
0 0 P -H
J3 rl >4H 4-1
rl 4J iH rl
td -rl P 
IH
O
>,ฃ
ft 4J
4J
O
IX) <3ซ
rH

-. CU
0 d
H O
S N
ft O


































































><
ft
4->
&s
4-1

>• >- > ~
ft ft rn
>, 4J 4J "?.
ft •• W
4-1 <3< rH 4-1 —
0 >i >, CO
r- o ft ft -H cu
O 0 4-1 •• 4-1 E T3
>i 0 • 0) -H
ft • 0 H 73 m 73 IH
4-> O • -H -H rH
0 S-i Up
U3 •• O •• Id CO
• •• E rH ra
orap • • xl cu cj d
O -H >, U 73 -H CU
4J rH SH -H SH Ol
••C/lrH P rH SH P O
'dCUNUSOIHSH
Id.QSHrldPrH73
CUCO-i
J&)CQK






























































ft
>-i|
J_)
>,0
ft H
4-1
O ••
CO
0)
.. K
eluding H2S]
(including
d co
-H 73
— d
SH O
P ft
u E
rH O
P CJ
CO
SH
73 P
0) IH
O rH
P P
•d co
0)
M 73
cu
rH U
rO P
4J 73
O CD
H K
















O
1-1 CO
d
CU 0
U -H
SH ra
p ra
O -H
to E
cu
rd
>i
•w d
O id

i-H -
td 4-i
-H ra
4J -H
d rH
0)
4-1 4-1
O 0
ft d

a; co
XI 0)
4-> O
73
M
o cu

0) 0
CO XI
rd td
cu
SH — -
U -H
-H
4-1
co id
d xl
O 4-1
•rl
CO -
CO 4-1
•H O
e. <
0)
0)
4J X!
CU 4-1
PI
n
rd cu
73
O d
4J P
a) a
o o
d -H
, in refere
to regulat
CO 4J
d O
ro cu
CU -n
ฃ XI
P
= CO
4-1
G 4J
td d
O rd
•H 4-1
IH P
•H rH
fi rH
Ol O
•H ft
W
= id

— 4J CU
•H -H 4J
-rl ฃ Iti
— CU M






















=
CU
4-1
rd
^

ra
d
0
-H
CO
10
-H
E
0)

>i
d
ro
s

CU
X!
4J

O
4-1
d
•H
O)
d
•H
rH
rH
id
IH

CO
4-1
d
id
4-1
iH
rH
O
ft
CU
^4
id
ro
CU
73
•H
d radionucl
d
id
(U
d
cu
N
d
cu
X!
CU
iH
ft
6
id
X
(U

^
0
[t.
• —






^~.

>1
^1
o
Ol
cu
4-1
id
u
XI 0
CU U 4-1
4-1 -rl
10 XI rH
^4 3 10
p
co d ti1
d o cu
0 -H
•H 4-1 10
ra rd • O
d E XI
id u
SH p
CO O CO
d -i-i
id id d
a> 6 o
E
rl 4J
4J O CJ
d m
to cu ft
o u e
•H ^ -rl
IH p
•rl O d
d ra ro
Ol
•H >, 0)
ra JH >
= id id
d x!
d" -H 73
o 4-1 d
•H tO tO
4J 4J
u ra -
cu to
ra M cu
O ^
ra T-i id
-rl Id
XI g H
4-1
id co
i4H ra
0 xl id
4J rH
~ -rl U
•H S
— id
— 73
m CD IH
CN 4J O
— id
—~ -H CO
aragraph (b
rease assoc
0 kilometer
ft CJ iH
d
- -H d
Ol -H
d ra xl
•rl d 4-1
73 O -H
d -H s
rd co
4J CO 4J
ra -ri o
XI E P
4-> CU ^
-H 4-1
3 4-1 ra
4-1 cu d
o d o
•z, o
>1
— d-d
•H 10 rH
•H P
•rl Vl 0
— 0 3
































































"cU
Ol
(C
fc
(U
ro
SH
P
O
i
^<
01

m ""
E
Oi
P
H

d
10
X!
4J

rl
cu
4J
td
cu
SH
Ol
•H
0
















-------





























frt
a\
CD
[-(
i-<
•rH
•y
ซ
o



~*
3
P5
W
EH

K
CQ
55

Q
s
C"J
W
W
^
ซ
C/J

ซ
O
.
tt
o
H

H
g
H

p

'
<

PS
^
B
r\
Oi
i-M
P.
*^





















n
0
U 13
X! D
4J 73
•H
0 >
4J <1J

4J Kl 01
G rl Id
01 0)
g 14 |<
0) D ft
01 rl W
id
G 01 >,
id -H xi
g x;
4J 73
>, 11
jj , JJ
•rl >, ft
rH rH 11
Id rH O
D1 &4 id
u
V4 G G
•HUH
id O u
XI

r7 • 01
id co >
o a id
O f-Q .*"!
rH r5]
S 4J
&4 Id
O 0) XI
— X! 4J
4J
0) 01
4J 01 4J
id G G
4J -H D

-H 01
73 Id rl
H 4J -H
r> G 3
O -H O"
^4 id u
ft g rl

Id 73 01
G G
>i id -H
H 4J
rH Ol 4J
id C -H

,
H id G 0)
Xi n) 11
4J rl 4J
o 01 m
01 1-1 U rl
-H rH 4J
G 3 CQ
G id JH

rH ft >i O
ft 4J in
>i -rl 4J
G rl rH K
O O id 0
•H 4J 3 CJ
4J 3 cr
id u u
4J Id rl rH
G 4J -H XI
0 01 id id
g 4J
11 01 rH ft
rH - Id 0)
ft >1 U 0
g 4J O 0
M -H rH rd
rl \
0) 0 01 G
4J Xi 4J fd
id 4J id
4J 3 4J 1-1
co rd CO O








a.
H
CQ
G
o
-H
rH 4J
O Id
rl rH
S Si
O - 0)
O 0) S-l

rl -H O
O 73 4J
rH
ft-rl 4J
•H 3 U
X! X! 01
01 -n
rl ^1 XI
0) G 3
G id 01
O " 4J
01 G
G G id
O id 4J
g H 3
g g rH
O rH
U 4J O
-rl ft

D - rl
73 ~ -H
G — rt
3 in
	 K*1
rj 	 , rj
O XI id
•H —
4J ID 4J
Id VXi -H
O H g
O • 0)
r-H r-<
in >,

G 73 g
O G
rd ri
4J O
id —
in 01
01 *" 4J
4J ^- -H
•H XI g
G — D
3 H
CN Xi
01 • o
G CN -H
O in xi
•H 3
01 Pi
01 CK G
-H U 0
g -H
U 0 4J
^ id
rH rH
r-l 11 rH
id u id
G 4J
O 0) 01
4J rl G
01 -H
01 1-1
rl 01 rl
01 rl O
01
rl G >1
O 4J
- -H -H
01 4J rH
01 Id -H E
01 rH U •
O 3 id 4J
ft Ol . G
01 -H
01 4J XI
0) G 4J 73
•HI) 0)
4J O 1-1 XI
-H rd -H -H -—
> -n • rl >,
•rl 73 ^~ 01 U rH
4J Id rH G 01 D
O O -H 0) >
Id V4 rl ft 73 4J -H
O 4J 3 G 4J
0) G O 01 01 O
C 01 o ri rd g 0)
•rl 3 O 0) (U ft
4J O — - i-H 01
4J 3 G rH 0) ft U
•H 01 O Id 73 ft rl
g -H g -H O 3
U 4J g rl U CO -
1 C O 4J 0
4J O u oi 4J r- i
GO 3 -H r-- u>
id M 73 01 cri r~
4J U U G -H rH H
3 rl 73 -H 73 0
rH O G 0) O
H e 3 D o x; i
O 6 3 4J in
ft rl G Id 4J 0
O O 01 >, 0
0) 01 jJ XI i
Xi U rl U 01 f>
4J G U Xi rl 73 0
O ft 4J -H 01 O
1-1 1-4 73
o G ri 1-1 n 73
O O O D D G
rH " g 6 10
rH 73 4J Id 10
id 01 G ri w u>
4J O Id 01 kO
01 id 01 ft D 10 o
C U rl Xi 0
id o oi 01 4J ~i
01 rH ft Id IN H
g u r- o
0) H 73 > CTi H
= ^4 g 01 Id rH Tj*
G id id M XJ
O 01 0) -01
-H - 73 Xi i-H ^4
4J 01 u -H u m u
id G Xi 01 -H 3 xi
rH -H 4J G Xi H g
rH ft O 3 10 3
id 3 i-i o S G
4J O O
01 rl U • C X
G 01rH XI 01 O U
•H O • -H O
i— 1 ^4 rH -H 4J 4J
^ Id 4J r-l " 10 01
O -H G Id O
H O X! = -HO)
- jj u m ft 4-1 u
>, 01 3 -H -H
4J 3 U 01 O 01 lU
-H 73 Xi 11 rl 01 U-l
rH G 4J -H O 10 O
•H -H 4J rH
O rl -H V4 U Ol
id u o) > o G
4-1 g 73 -H -m rH -H
10 G 4J Id IB 4J
- 01 3 0 S -H G
u id = h -H
rl 01 11 4-1 M
3 xi ri Ol 
G 0) -H G 4J H O
•H XI 4J Id IB O
73 ^4 4J 01 4J
rH Xi U 3 G CO •
-H O ft rH O CO
3 -H O rH rH HI •
m Xi rl 0 D X! t>
= 3 ft ft XI 4-1 —












-------
                                        DRAFT
                                        OCTOBER 1990
       APPENDIX  B

ESTIMATING CONTROL  COSTS

-------
                                                                  DRAFT
                                                                  OCTOBER 1990

                    APPENDIX B - ESTIMATING CONTROL COSTS

I.  CAPITAL COSTS

     Capital  costs include equipment costs,  installation costs,  indirect
costs,  and working capital (if  appropriate).    Figure  B-4 presents the
elements of total  capital  cost  and  represents  a  building block approach that
focuses on the control  device as  the basic unit  of analysis  for  estimating
total  capital  investment.   The  total capital  investment has  a  role in the
determination  of total  annual  costs and cost  effectiveness.

     One of the most common problems which occurs  when comparing costs at
different facilities is that the  battery limits  are different.  For example,
the battery limit of the cost of  a  electrostatic precipitation might be the
precipitator  itself (housing,  plates,  voltage  regulators, transformers, etc.),
ducting from  the source to the  precipitator,  and the solids  handling system.
The stack would not be  included because a stack  will  be required regardless of
whether or not controls are applied.  Therefore, it should be  outside the
battery limits of the control  system.

     Direct installation costs  are  the costs  for the labor and materials  to
install the equipment and  includes  site preparation,  foundations,  supports,
erection and  handling of equipment, electrical work,  piping,  insulation and
painting.  The equipment vendor can usually  supply direct installation costs.

     The equipment vendor  should  be able to  supply direct installation costs
estimates or  general installation costs factors.  In addition, typical
installation  cost factors  for various  types  of equipment are available in  the
following references.
                                      b.l

-------
                                                      DRAFT
                                                      OCTOBER 1990
   w
— 4 a>





J5
J3
li .

-* w
•*->ฃ=>
ฃg,S



"5"
—4
5
o,
_ S
i g* cr
-S3 S
•o -w -*3
C U 4-*
3 ฃ ฃ

•— i o on
s at!
fiSS








^
ง
g 2

•o •*-> •ซ-> ^— S.
S m -H ^— ' k4
•ง ^" -._> an ^S J3 o>
ฃ ง•ง ฑ3 g S i:
ฃ w <_ป o 1-4 ซj ซo





i.
"3
to ^ 13
O h4 "C C
"3 -4-ป 3?-ฃ — - S.— <
illl*_ *I
p -* o +3 o -=" -3 CO ซ0 (3 ซ — 1 B
O PI B •*-ป B X —— O a O
W **H fO C9 ICT •** O* O ป•< C7^
ป-•  -4->B— 4 *J C
t_i — < 9 — < 9 J3 ซJ — ' ป-l CT> ซJ -^
J^H ^-4 ••-• M CO C7^ "O •-* *^ B ^H 4^
_4CJ— 44->CO— H G -O O — 4 S B
x c -c> ซo •— ซ a> 3 c ^ 3 -S S c 

a> c= S3 t> S" S C7> O O >-ซ VI — * C jo i E c: ^*^S!2r: cr 4-> i-ซ *^ o **H aj (l> ^H ฃG j; tACOfO-^OE C7* C C


-------
                                                                  DRAFT
                                                                  OCTOBER 1990
     •    OAQPS Control  Cost Manual  (Fourth Edition), January 1990,
          EPA 450/3-90-006
     •    Control  Technology for Hazardous Air Pollutants (HAPS) Manual.
          September 1986,  EPA 625/6-86-014
     •    Standards Support Documents
               Background  Information Documents
               Control  Techniques Guidelines Documents
     •    Other EPA sponsored costing studies
     •    Engineering Cost and Economics Textbooks
     •    Other engineering cost publications

These references should  also be used to validate any installation cost factors
supplied from equipment  vendors.

     If standard costing factors are used, they may need to be adjusted due to
site specific conditions.   For example, in Alaska installation costs are on
the order of 40-50 percent higher than in the contiguous 48 states due to
higher labor prices,  shipping costs, and climate.

     Indirect installation costs include (but are not limited to) engineering,
construction, start-up,  performance  tests, and contingency.  Estimates of
these costs may be developed by the  applicant for the specific project under
evaluation.  However, if site-specific values are not available, typical
estimates for these costs  or cost factors are available in:
     •    OAQPS Control Cost Manual (Fourth Edition), EPA 450/3-90-006
     •    Cost Analysis Manual  for Standards Support Documents, April 1979

     These references can be used by applicants if they do not have
site-specific estimates already prepared, and should also be used by the
reviewing agency to determine if the applicant's estimates are reasonable.

                                      b.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
Where an applicant uses different procedures or assumptions for estimating
control  costs than contained in the referenced material  or outlined in this
document,  the nature and reason for the differences are  to be documented in
the BACT analysis.

      Working capital  is a fund set aside to cover initial costs of fuel,
chemicals, and other materials and other contingencies.   Working capital  costs
for add on control systems are usually relatively small  and, therefore, are
usually not included in cost estimates.

     Table B-ll presents an illustrative example of a capital cost estimate
developed for an ESP applied to a spreader-stoker coal-fired boiler.   This
estimate shows the minimum level  of detail  required for  these types of
estimates.  If bid costs are available, these can be used rather than study
cost estimates.

II. TOTAL ANNUAL COST

     The permit applicant should use the levelized annual cost approach for
consistency in BACT cost analysis.  This approach is also called the
"Equivalent Uniform Annual Cost" method, or simply "Total Annual Cost" (TAC).
The components of total annual costs are their relationships are shown in
Figure B-5.  The total annual costs for control systems is comprised of three
elements:  "direct" costs  (DC), "indirect costs" (1C),  and  "recovery credit"
(RC), which are related by  the following equation:

                          TAC = DC + 1C - RC
                                      b.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
           TABLE B-ll.   EXAMPLE OF A  CAPITAL  COST  ESTIMATE  FOR AN

                          ELECTROSTATIC  PRECIPITATOR
                                                                     Capital
                                                                       cost
                                                                        ($)

Direct Investment

     Equipment cost
        ESP unit                                                    175,800
        Ducting                                                      64,100
        Ash handling system                                          97,200
        Total  equipment cost                                        337,100

     Installation costs
        ESP unit                                                    175,800
        Ducting                                                     102,600
        Ash handling system                                          97,200

        Total  installation costs                                    375,600
        Total  direct investment (TDI)                               712,700
        (equipment + installation)

Indirect Investment                                                    71,300
   Engineering (10% of TDI)                                          71,300
   Construction and field expenses (10% of TDI)                      71,300
   Construction fees (10% of TDI)                                    71,300
   Start-up (2% of TDI)                                              14,300
   Performance tests (minimum $2000)                                   3,000

   Total indirect investment (Til)                                  231,200
Contingencies  (20% of TDI + Til)                                    188,800

TOTAL TURNKEY  COSTS (TDI + Til)                                   1,132,700

Working Capital (25% of total direct  operating costs)a               21,100

GRAND TOTAL                                                       1,153,800
                                      b.5

-------
                                                                    DRAFT
                                                                    OCTOBER 1990
 o Raw Materials
 o Utilities
   -  Electricity
   -  Steam
   -  Water
   -  Others
o Labor
  -  Operating
  -  Supervisory
  -  Maintenance
o Maintenance materials
o Replacement parts
Vari able
Semi vari able
                            o Overhead
                            o Property Taxes
                            o Insurance
                            o Capital Recovery
                            o  Recovered  Product
                            o  Recovered  Energy
                            o  Useful  byproduct
                            o  Energy  Gain
                                                          Di rect
                                                          Annual
                                                          Costs
                     Indi rect
                     Annual
                     Costs
                     Recovery
                     Credits
                                      Total
                                   =  Annual
                                      Costs
                   FIGURE  B-5.  Elements  of Total  Annual  Costs
                                       b.6

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Direct costs are those which tend to be proportional  or partially
proportional to the quantity of exhaust gas processed by the control  system
or, in the case of inherently lower polluting processes, the amount of
material  processed or product manufactured per unit time.   These include costs
for raw materials, utilities (steam, electricity,  process  and cooling water,
etc.), and waste treatment and disposal.  Semivariable direct costs are only
partly dependent upon the exhaust or material flowrate.   These include all
associated labor, maintenance materials, and replacement parts.   Although
these costs are a function of the operating rate,  they are not linear
functions.  Even while the control system is not operating, some of the
semivariable costs continue to be incurred.

     Indirect, or "fixed", annual costs are those  whose  values are relatively
independent of the exhaust or material  flowrate and,  in  fact, would be
incurred  even if the control system were shut down.  They  include such
categories as overhead, property taxes, insurance, and capital recovery.

     Direct and indirect annual costs are offset by recovery credits, taken
for materials or energy recovered by the control system, which may be sold,
recycled  to the process, or reused elsewhere at the site.   These credits,  in
turn, may be offset by the costs necessary for their  purification, storage,
transportation, and any associated costs required  to  make  then reusable or
resalable.  For example, in auto refinishing, a source through the use of
certain control technologies can save on raw materials (i.e., paint)  in
addition  to recovered solvents.  A common oversight in BACT analyses  is the
omission  of recovery credits where the pollutant itself  has some product or
process value.  Examples of control techniques which  may produce recovery
credits are equipment leak detection and repair programs,  carbon absorption
systems,  baghouse and electrostatic precipitators  for recovery of reusable  or
saleable  solids and many inherently lower polluting processes.
                                      b.7

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
     Table B-12 presents an example of total  annual  costs for the control
system previously discussed.   Direct annual  costs are estimated based on
system design power requirements,  energy balances,  labor requirements,  etc.,
and raw materials and fuel  costs.   Raw materials and other consumable costs
should be carefully reviewed.   The applicant generally should have documented
delivered costs for most consumables or will  be able to provide documented
estimates.  The direct costs  should be checked to be sure they are based on
the same number of hours as the emission estimates  and the proposed operating
schedule.

            Maintenance costs  in some cases  are estimated as a percentage of
the total capital investment.   Maintenance costs include actual costs to
repair equipment and also other costs potentially incurred due to any
increased system downtime which occurs as a  result  of pollution control  system
maintenance.

      Fixed annual costs include plant overhead, taxes, insurance, and capital
recovery charges.  In the example shown, total plant overhead is calculated as
the sum of 30 percent of direct labor plus 26 percent of all labor and
maintenance materials.  The OAQPS Control Cost Manual combines payroll  and
plant overhead into a single indirect cost.   Consequently, for "study"
estimates, it is sufficiently accurate to combine payroll and plant overhead
into a single indirect cost.   Total overhead is then calculated as 60 percent
of the sum of all labor (operating, supervisory, and maintenance) plus
maintenance materials.

     Property taxes are a percentage of the fixed capital investment.  Note
that some jurisdictions exempt pollution control systems from property taxes.
Ad valorem tax data are available from local governments.  Annual insurance
charges can be calculated by multiplying the insurance rate for the facility
by the total capital costs.  The typical values used to calculate taxes and
                                      b.8

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
     TABLE B-12.  EXAMPLE OF A ANNUAL COST  ESTIMATE  FOR  AN  ELECTROSTATIC
                 PRECIPITATOR APPLIED TO A COAL-FIRED BOILER

                                                               Annual  costs
                                                                  ($/yr)

Direct  Costs
     Direct labor at $12.02/man-hour                                   26,300
     Supervision at  $15.63/man-hour                                         0
     Maintenance labor at $14.63/man-hour                              16,000
     Replacement parts                                                  5,200
     Electricity at  $0.0258/kWh                                         3,700
     Water at $0.18/1000 gal                                               300
     Waste disposal  at $15/ton (dry basis)                             33,000
          Total  direct costs                                            84,500
Indirect Costs
     Overhead
          Payroll (30% of direct labor)                                  7,900
          Plant  (26% of all  labor and replacement parts)                12,400
          Total  overhead costs                                         20,300
Capital  charges
     G&A taxes and insurance                                            45,300
     (4% of total turnkey costs)
     Capital  recovery factor                                           133,100
     (11.75%  of  total turnkey costs)
     Interest on working capital                                         2,100
     (10% of  working capital)
          Total  capital charges                                       180,500
          TOTAL  ANNUALIZED COSTS                                      285,300
                                      b.9

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
insurance is four percent of the total  capital  investment if specific facility
data are not readily available.

     The annual  costs previously discussed do not account for recovery of the
capital  cost incurred.   The capital  cost shown  in Table B-2 is annualized
using a  capital  recovery factor  of 11.75 percent.  When the capital  recovery
factor is multiplied by the total  capital  investment the resulting product
represents the uniform end of year payment necessary to repay the investment
in "n" years with an interest rate "i".

     The formula for the capital recovery factor is:

          CRF = i (1 + 1)"
where:
     CPF = capital recovery factor
       n = economic life of equipment
       i = real interest rate

     The economic life of a control system typically varies between 10 to 20
years and longer and should be determined consistent with data from EPA cost
support documents and the IRS Class Life Asset Depreciation Range System.

      From the example shown in Table B-12 the interest rate is 10 percent and
the equipment life is 20 years.-  The resulting capital recovery factor is
11.75 percent.  Also shown is interest on working capital, calculated as the
product of interest rate and the working capital.

      It is important to insure that the labor and materials costs of parts of
the control system (such as catalyst beds, etc.) that must be replaced before
the end of the useful life are subtracted from the total capital investment

                                     b.10

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
before it is multiplied by the capital  recovery factor.   Costs of these parts
should be accounted for in the maintenance costs.   To include the cost of
those parts in the capital charges would be double counting.   The interest
rate used is a real interest rate (i.e., it does not consider inflation).   The
value used in most control costs analyses is 10 percent  in keeping with
current EPA guidelines and Office of Management and Budget recommendations for
regulatory analyses.

     It is also recommended that income tax considerations be excluded from
cost analyses.  This  simplifies the analysis.   Income taxes generally
represent transfer payments from one segment of society  to another and as  such
are not properly part of economic costs.

III. OTHER COST ITEMS

     Lost production  costs are not included in the cost  estimate for a new or
modified source.  Other economic parameters (equipment life,  cost of capital,
etc.) should be consistent with estimates for  other parts of  the project.
                                     b.ll

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
                                 APPENDIX C7


                              POTENTIAL TO EMIT
      Upon commencing review of a  permit application,  a  reviewer  must  define

the source and then determine how  much  of each  regulated pollutant  the source

potentially can emit and whether the source is  major  or  minor  (nonmajor).   A

new source is major if its potential  to emit exceeds  the appropriate major

emissions threshold, and a change  at an existing major source  is  a  major

modification if the source's net emissions increase is "significant."   This

determination not only quantifies  the source's  emissions but dictates  the

level  of review and applicability  of various regulations and new  source review

requirements.  The federal regulations, 40 CFR  52.21(b)(4),  51.165(a) (1) (iii),
and 51.166(b)(4), define the "potential to emit" as:
"the maximum  capacity  of a  stationary  source to  emit  a  pollutant  under  its
physical  and operational  design.  Any physical or operational limitation on the
capacity  of  the  source to emit  a  pollutant,  including air  pollution  control
equipment and restrictions on  hours  of  operation or on the  type  or  amount of
material  combusted,  stored or processed,  shall be treated as part of its design
if  the  limitation  or  the  effect  it  would  have  on  emissions   is  federally
enforceable."
In the absence of federally enforceable restrictions,  the potential  to emit

calculations should be based on uncontrolled emissions at maximum design or

achievable capacity (whichever is higher) and year-round continuous  operation

(8760 hours per year).
      7  This Appendix  is based largely on an EPA memorandum "Guidance on
Limiting Potential to Emit in New Source Permitting," from Terrell  E. Hunt,
Office of Enforcement and Compliance Monitoring, and John S.  Seitz,  Office of
Air Quality Planning and Standards, June 13, 1989.

                                      c.l

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      When determining the potential  to emit for a source, emissions should be
estimated for individual  emissions units using an engineering approach.  These
individual values should  then be summed to arrive at the potential  emissions
for the source.   For each emissions unit,  the estimate should be based on  the
most representative data  available.  Methods of estimating potential to emit
may include:

      •     Federally enforceable operational limits, including the effect of
            pollution control equipment;
      •     performance test data on  similar units;
      •     equipment vendor emissions data and guarantees;
      •     test data from EPA documents,  including  background information
            documents for new source  performance standards,  national emissions
            standards for hazardous air pollutants,  and Section lll(d)
            standards for designated  pollutants;
      •     AP-42 emission factors;
      •     emission factors from technical literature; and
      •     State emission inventory  questionnaires  for comparable  sources.

NOTE:  Potential to emit  values reflecting the use of pollution control
equipment or operational  restrictions are  usable only to the extent that the
unit/process under review utilizes the same control  equipment or operational
constraints and  makes them federally  enforceable in  the permit.

Calculated emissions will embrace all potential, not actual, emissions
expected to occur from a  source on a  continuous or regular basis, including
fugitive emissions where  quantifiable.  Where raw materials  or fuel vary in
their pollutant-generating capacity,  the most pollutant-generating  substance
must be used in  the potential-to-emit calculations unless such materials are
restricted by federally enforceable operational or usage limits.  Historic
usage rates alone are not sufficient  to establish potential-to-emit.
                                      c.2

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      Permit limitations are significant in determining a  source's potential
to emit and, therefore,  whether the source is "major"  and  subject to new
source review.   Permit limitations are the easiest and most common way for a
source to restrict its potential  to emit.   A source considered major,  based on
emission calculations assuming 8760 hours  per year of  operation,  can often be
considered minor simply  by accepting a federally enforceable limitation
restricting hours of operation to an actual schedule of,  for example,  8 hours
per day.  A permit does  not have to be a major source  permit to legally
restrict potential emissions.  Minor source construction  permits  are often
federally enforceable.  Any limitation can legally restrict potential  to  emit
if it meets three criteria: 1) it is federally enforceable as defined by
40 CFR 52.21(b)(17), 52.24(f)(12), 51.165(a)(1)(xiv),  and  51.166(b)(17),  i.e.,
contained in a permit issued pursuant to an EPA-approved  permitting program or
a permit directly issued by EPA, or has been submitted to  EPA as  a revision to
a State Implementation Plan and approved as such by EPA;   2) it is enforceable
as a practical  matter; and (3) it meets the specific criteria in  the
definition of "potential to emit," (i.e.,  any physical or  operational
limitation on capacity,  including control  equipment and restrictions on hours
of operation or type or amount of material combusted,  stored, or  processed).
The second criterion is an implied requirement of the first.  A requirement
may purport to be federally enforceable, but in reality cannot be federally
enforceable if it cannot be enforced as a practical matter.

       In the absence of dissecting the legal aspects of "federal
enforceabi1ity," the permit writer should always assess the enforceabi1ity of
a permit restriction based upon its practicability.  Compliance with any
limitation must be  able to be established at any given time.  When drafting
permit  limitations, the writer must always ensure that restrictions are
written in such a manner that an inspector could verify instantly whether the
source  is or was  complying with the permit conditions.  Therefore, short-term
averaging times on  limitations are essential.  If the writer does this, he or
she can feel comfortable that limitations  incorporated into a permit will be
federally enforceable, both legally and practically.
                                      c.3

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
      The types of limitations that restrict potential  to emit are emission
limits,  production limits,  and operational  limits.   Emissions limits should
reflect  operation of the control  equipment,  be short term,  and,  where
feasible, the permit should require a continuous emissions  monitor.   Blanket
emissions limits alone (e.g.,  tons/yr,  Ib/hr)  are virtually impossible to
verify or enforce, and are  therefore not enforceable as a practical  matter.
Production limits restrict  the amount of final product  which can be
manufactured or produced at a  source.  Operational  limits include all
restrictions on the manner  in  which a source is run, e.g.,  hours of  operation,
amount of raw material consumed,  fuel combusted or  stored,  or specifications
for the  installation,  maintenance and operation of  add-on controls operating
at a specific emission rate or efficiency.   All production  and operational
limits except for hours of  operation are limits on  a source's capacity
utilization.  To appropriately limit potential to emit  consistent with a
previous Court decision [United States  v.  Louisiana-Pacific Corporation.
682 F. Supp. 1122 (D.  Colo. Oct.  30, 1987)  and 682  F.  Supp. 1141 (D. Colo.
March 22, 1988)], all  permits  issued must  contain a production or operational
limitation in addition to the  emissions limitation  and  emissions averaging
time in  cases where the emission  limitation  does not reflect the maximum
emissions of the source operating at full  design capacity without pollution
control  equipment.  In the  permit,  these limits must be stated as conditions
that can be enforced independently  of one  another.   This emphasizes  the idea
of good  organization when drafting  permit  conditions and is discussed in  more
detail in the Part III text.  The permit conditions must be clear, concise,
and independent of one another such that enforceability is  never questionable.

      When permits contain  production or operational limits, they must also
have requirements that allow a permitting  agency to verify  a source's
compliance with its limits.  These  additional  conditions dictate
enforceabi1ity and usually  take the form of  recordkeeping requirements.  For
example, permits that contain  limits on hours  of operation  or amount of final
product  should require use  of  an  operating  log for  recording the hours of
operation and the amount of final product  produced.  For organizational
                                      c.4

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
purposes,  these limitations  would  be  listed  in  the  permit  separately  and
records should be kept on a  frequency consistent  with  that of  the  emission
limits.  It should be specified that  these logs be  available  for  inspection
should a permitting agency wish to check a source's compliance with the  terms
of its permit.

      When permits require add-on  controls operated at a  specified efficiency
level, the writer should include those operating  parameters and assumptions
upon which the permitting agency depended to determine that controls  would
achieve a  given efficiency.   To be enforceable, the permit must also  specify
that the controls be equipped with monitors  and/or  recorders  measuring  the
specific parameters cited in the permit or those  which ensure  the  efficiency
of the unit as required in the permit.  Only through these monitors could  an
inspector  instantaneously measure whether a  control was operating  within its
permit requirements and thus determine an emissions unit's compliance.   It  is
these types of additional permit conditions  that  render other  permit
limitations practically and federally enforceable.

      Every permit also should contain emissions  limits,  but  production  and
operational limits are used to ensure that emissions limits expressed in the
permit are not exceeded.  Production  limits  are most appropriately expressed
in the shortest time periods as possible and generally should  not exceed
1 month (i.e., pounds per hour or tons per day),  because compliance with
emission limits is most easily established on a short term basis.   An
inspector, for example, could not verify compliance for an emissions  unit with
only monthly  and annual production, operational or emission limits if the
inspection occurred anytime except at the end of a month.   In  some rare
situations a  1-month averaging time may not be reasonable.  In these  cases,  a
limit  spanning a longer period is appropriate if it is a rolling average
limit.  However, the limit should not exceed an annual limit rolled on  a
monthly basis.  Note also that production and operational  recordkeeping
requirements  should be written consistent with the emissions limits.   Thus,  if
an emissions  unit was limited to a particular tons per day emissions  rate,
                                      c.5

-------
                                                                  DRAFT
                                                                  OCTOBER 1990
then production records which monitor compliance with this limit should be
kept on a daily basis rather than weekly.

      One final matter to be aware of when calculating potential to emit
involves identifying "sham" permits.   A sham permit is a  federally enforceable
permit with operating restrictions limiting a source's potential to emit  such
that potential  emissions do not exceed the major or de minimis levels for  the
purpose of allowing construction to commence prior to applying for a major
source permit.   Permits with conditions that do not reflect a source's planned
mode of operation may be considered void and cannot shield the source from the
requirement to  undergo major source preconstruction review.  In other words,
if a source accepts operational limits to obtain a minor  source construction
permit but intends to operate the source in excess of those limitations once
the unit is built, the permit is considered a sham.  If the source originally
intended or planned to operate at a production level  that would make it a
major source, and if this can be proven, EPA will  seek enforcement action  and
the application of BACT and other requirements of the PSD program.
Additionally, a permit may be considered a sham permit if it is issued for a
number of pollution-emitting modules  that keep the source minor, but within a
short period of time an application is submitted for additional modules which
will make the total source major.  The permit writer must be aware of such
sham permits.  If an application for  a source is suspected to be a sham,  EPA
enforcement and source personnel should be alerted so details may be worked
out in the initial review steps such  that a sham permit is not issued.  The
possibility of  sham permits emphasizes the need, as discussed in the Part  III
text, to organize and document the review process throughout the file.  This
documentation may later prove to be evidence that a sham  permit was issued, or
may serve to refute the notion that a source was seeking  a sham permit.

      Overall,  the permit writer should understand the extreme importance  of
potential to emit calculations.  It must be considered in the initial review
and continually throughout the review process to ensure accurate emission
                                      c.6

-------
                                                                   DRAFT
                                                                   OCTOBER 1990
limits that are consistent with  federally  enforceable production and

operational restrictions.
                                       c.l

-------

B ->c7Sfiu tuaebiixi-io. oo o o o o oooooo **^ t * JQ C ซ* a? •r-4 E *** fl5 ^ ซo G o ess . — . s 9 •*•• a; ฃ Zป *J . ^ O) —4 — ^ CO •*-* * -*^5 (A CO ^H •*-* 51 Sฃ ^ i i l .=• 3 •*-> 3 tJ t> &• fl3 — . p -^ ฎ *" *-H b CO 3 -S CO 1— O O C O rO C >ป ง ™ E M C *O QJ ^ A> V — 4 o. ai co ^ c= 1=58 *_* o W • *-• "O -M — < CO O ฃ= CA ^-ป ^~>* O *^ C ^*-ซ *O CTV ^-> •— < ป— - -*-^ >M -*^ w -o w .— H ab ^-i ^ •*-* •*-• -ซ-ป a> e *o w 10 us p i= m to M cu -^ซ *OCOU3 O — ^ t> tO tO 3 es e o -* 04 I-H ป-ป t-t ^-0*^vO>W ••-J & to IO i-i W = ^-* *tJ — ซ O J2 * p >^ k-ซ Sfci "io ^ "e =3 —* -*-J *-> O W CU 0 0 U O Qi *• ^ .C -^ aj p (P t/1 C -4-> *O ca E E *o "^ 'O "^? f O O i- ex: ft* •a "O 4fc^ 4^ ป^4 d> w (O •*— * (O 3C 13 W C O p ^-i o o >- aป o -p a> *j *j -^ u. 2i — * CJ O C ••-ซ -ป-> U4 •o 4_* np i-* g er <5 4D CD k-t i-t i-< .C >-H krf