WATER POLLUTION CONTROL AOMIN I STRATI ON
      NORTHWEST REGION, PAC F1C NORTHWEST WATER LABORATORY
HOUSEBOAT  WASTES:
   METHODS
FOR COLLECTION
AND TREATMENT
                             JUNE 1967

-------
                HOUSEBOAT WASTES

             METHODS FOR COLLECTION
                       AND
                    TREATMENT
                  Prepared by

                  B. D. Clark
           Technical Projects Branch
       U. S. Department of the Interior
Federal Water Pollution Control Administration
               Northwest Region
      Pacific Northwest Water Laboratory
               Corvallis, Oregon
                   June 1967
              LIBRARY
              Oept. of the Interior.

-------
                        TABLE OF CONTENTS

                                                              Page

    I.   INTRODUCTION	    1

        A.  Authority	    1
        8.  Purpose and Scope	    1
        C.  Problem	    1

   II.   SUMMARY	    5

  III.   WASTE CHARACTERISTICS	   11

        A.  Waste Quality	   11
        B.  Waste Quantity	   11

   IV.   PLUMBING REQUIREMENTS  	   17

        A.  Houseboats	   18
        B.  Other Floating Structures 	   29

    V.   MOORAGE COLLECTION   	   33

        A.  Collection System	   33
        B.  Moorage Lift Stations	   40

  VI.   TREATMENT	   47

       A.  Individual Methods  	   47
        B.  Group Methods	   52

 VII.   EXAMPLE DESIGN	   61

       A.  Basic Design Criteria 	   61
       B.  Layout and Cost Estimates	   63

VIII.  BIBLIOGRAPHY	   71

  IX.  APPENDIX	   73

       Appendix A - Plumbing Costs  for Three Houseboats in
                    Seattle, Washington  	   75

       Appendix B - Design Curves for Multiple Pump
                    Systems	   79

-------
                         LIST OF FIGURES
Figure                                                        Page
  No.                         Title                            No.
   1     Houseboat Water Use Pattern 	    14

   2     Houseboat Plumbing Plans  	    20

   3     Centrifugal Sump Design   	    27

   4     Recirculating Toilet and Macerating Pump
         Application	    30

   5     Walkway Connections 	    36

   6     Moorage Collection Costs  	    39

   7     Centrifugal Sump Pump Installation t	    41

   8     Moorage Lift Station	    42

   9     Extended Aeration Treatment Costs  	    55

  10     Floating Restroom & Sewage  Treatment Plant Used  in
         Conjunction with Boating and Other Marine
         Activities	    57

  11     Floating Restroom & Sewage  Treatment Plant Used
         with a  Boat Holding Station Evacuation System  ...    58

  12     Settling Tank and Chlorination Treatment  	    59

  13     System  Design	    62

  14     Design  Curves  for Multiple  Pump System for
         Various Inflow and Pumping  Rates   	    83

  15     Design  Curves  for Multiple  Pump System for
         Various Inflow and Pumping  Rates   	    84

-------
                         LIST OF TABLES
Table                                                         Page
 No.                          Title                            No.
         Average Wastewater Quality from Three
         Individual Homes  	    12
         Quantities of Sewage Flow	    15
         Estimated Costs for Plumbing a  One-Bathroom,
         Single Story Houseboat with Copper,  Cast  Iron,
         and Plastic Materials    	    22
         Houseboat Plumbing and Pumping  Methods  Summary   .  .    32
         Comparison of Feces  and  Urine Waste  Quantities
         to Total  Household Wastes  for a  Family  of  Five
         People	    50
         Soil Absorption Areas  Required  for  Single
         Houseboats  for Various Percolation  Rates   	    53
         Cost  Summary	    69

-------
                              ABSTRACT






     Methods of collection and treatment for houseboat and moorage




wastewaters are reviewed.  Several methods using alternative




materials are considered and approximate installed costs are




given.  Emphasis is on solution of the problem in the State of




Oregon but information developed is applicable in adjacent states




and elsewhere with appropriate adjustments.
                                ii

-------
                              ACKNOWLEDGMENTS


      This study was made possible through  the  assistance  of  the

following State and local agencies and individuals:

                1.   Oregon State Sanitary Authority
                    Portland,  Oregon

                2.   Floating Homes Association
                    Seattle, Washington

                3.   Waterfront Property Owners  Association
                    Portland,  Oregon

                4.   King County Health Department
                    Seattle, Washington

                5.   City of Seattle Engineering Department
                    Seattle, Washington

                6.   Hersey Sparling Meter Co.
                    Seattle, Washington

                7.   City of Portland Water  Bureau
                    Portland,  Oregon

                8.   Parkrose Water District
                    Portland,  Oregon

                9.   Master Equipment Co.
                    Portland,  Oregon

               10.   Cornell Pump Co.
                    Portland,  Oregon

               11.   H.  D.  Fowler Co.
                    Seattle, Washington

               12.   DeFirs Moorage
                    Portland,  Oregon

               13.   Waterly Lane Moorage
                    Portland,  Oregon

               14.   Portland Rowing Club
                    Portland,  Oregon
                                    111

-------
15.  Mr. Terry Pettus
     Floating Homes Association
     Seattle, Washington

16.  Mr. Fred Repp
     Master Equipment Co.
     Portland, Oregon

17.  Dr. Donald Guthrie
     Professor of Math
     Oregon State University
     Corva His, Ore gon
                    iv

-------
                          HOUSEBOAT WASTES
               METHODS  FOR COLLECTION AND TREATMENT


                         I.   INTRODUCTION


      A.,   Authority

      The  Pacific  Northwest Water Laboratory of the Federal Water

 Pollution Control Administration, Northwest Region, was requested

 by the Oregon  State  Sanitary Authority, letter dated January 19,

 1966, to  conduct,

           "A study of  methods and costs of treatment and/or
           disposal of  sewage wastes from houseboats and other
           floating structures."

 The  Federal Water Pollution  Control Act, P,L» 84-660, as amended

 by the Clean Water Restoration Act of 1966, Section 5b, provides

 the  Federal authorization for this study.

     Bo   Purpose and Scope

     The  purpose of  this  study is to develop findings on wastewater

 characteristics,  together with methods and costs of collection and

 treatment  of sewage  wastes from houseboats and other floating

 structures.  The study area  for the report included the States of

Washington, Oregon,  and California with primary emphasis on the

 State of Oregon„

     C.   Problem

     In three Pacific Northwest States, California, Oregon, and

Washington, there are over 1200 houseboats and many other floating

 structures such as boathouses, commercial establishments,  floating

 restaurants, and public restrooms that discharge untreated sewage

-------
wastes directly to waters over which they are moored,,  Few of these




structures have plumbing systems.




     All three states presently have legislation in varying forms,




both local and State, that require houseboats and other floating




structures to treat their sewage before discharge or else require




complete removal to existing shoreside sanitary sewers.




     In California, State law prohibits the discharge, of untreated




sewage to waters of the State and action is being taken by the




California Water Quality Control Board in the form of cease and




desist orders against property owners that have houseboats moored




at their property.  The State has had little success to date in




enforcing these orders.




     In Washington, most houseboats are located in the City of




Seattle and are required by city and county ordinances to connect




to a recently constructed city sewer by June 1967.  Development of




acceptable collection methods and difficulties with local contractors




on construction costs indicate that the June 1967 deadline will not




be met.




     In the State of Oregon, houseboats and other floating structures




will be required specifically by State law (ORS 449.150) to provide




adequate treatment for all wastes discharged to State waters




effective September 1, 1967.  This time limit has recently been




extended by the Sanitary Authority to January 1, 1968, for the




installation of waste treatment facilities for toilet wastes.




Treatment facilities for kitchen, bath, and laundry wastes (not

-------
including garbage or human excreta) were given an extension of




time from September 1, 1967, to January 1, 1971, provided adequate




facilities were installed for toilet wastes and acceptable




progress reports are submitted on January 1, 1969, and January 1,




1970, demonstrating the development of a satisfactory plan




acceptable to the Authority for the disposal of the kitchen,




bath, and laundry wastes.

-------
                       II.  SUMMARY






     Findings  of  this  study on methods  for  the  collection  and  treat-




ment of wastes  from houseboats and other floating  structures are




summarized below:




     1.  The study area  for this report includes the States of




Washington, Oregon, and  California which have over  1200 houseboats




and many other  floating  structures requiring sewage collection




and treatment  facilities.




     2.  With  rare exception, houseboats and other  floating




structures discharge untreated domestic sewage  from toilets,




kitchens, and baths directly to the water in violation of  State




statutes and water quality standards, and this  may  constitute  a




health hazard  to  other water users.




     3.  Average  daily houseboat wastewater quantities are similar




to those for normal land residences with a daily per capita flow




of 75 gpd.  The average  16-hour flow is also similar with  a per




capita flow rate  of 95 gpd.




     4.  The quality of  the houseboat waste is  expected to be




similar to that for a normal land residence.  A separate report




will present data on the quality characteristics of the houseboat




waste.




     5.  The collection and treatment of houseboat wastes will be




more expensive than most land-based installations because of their




location.

-------
     6.  Few houseboats have adequate plumbing systems, requiring




major replumbing to collect and treat wastes.  Several methods are




presented for replumbing.  The range of costs are estimated from




$230 to $800 for a single story, one bathroom houseboat.  Plastic




PVC pipe costs the least.  This material is not approved for use




in Oregon or Washington for interior plumbing but is acceptable in




California.




     7.  Central collection of all wastes is recommended wherever




possible requiring that moorages provide central collection




facilities for houseboat wastes and wastewaters from other floating




structures.  Costs for above water, pressure moorage collection




systems installed were estimated to range from 8% to 83 cents per




houseboat per foot of moorage length using cast iron pipe and 5




to 48 cents per houseboat per foot of moorage length using PVC




plastic pipe for moorages ranging in size from 50 to 5 houseboats,




respectively.  Costs would be significantly higher for gravity




underwater collection systems.




     8.  Houseboats located on rivers or waters with a large tidal




fluctuation may require individual pump units to maintain collection




lines above water.  Individual houseboats on these waters may or




may not require pumps depending on whether they treat their wastes




on shore or on the water with a floating facility.  Several pumping




methods have been considered that range in price from $275 to $1500,




not including installation costs.

-------
     9.  Houseboats  located on lakes or other relatively quiet




bodies of water  could use either gravity underwater systems to a




central  lift station or  individual pumping units for pumping




direct to shore.




     10.  Moorages on widely fluctuating rivers may find it




necessary to install lift stations on auxiliary floats to lift




the  waste to shore-based treatment facilities or public sewers.




These units can  be purchased in a price range of $2500 to $7100.




     11.  Recirculating toilets may find application where the w.aste




volume is significant.  This would be the case for intermittent




waste sources that choose to hold the wastes with periodic cleaning




of the holding facilities.




     12.  Pumping all wastes to a shore sewer is the least expensive




and most practical alternative wherever this is possible.   It has




been estimated that exclusive of city or other municipal group




connection charges, a houseboat could pump all wastes to a city




sewer for a cost ranging from $1000 up.




    13.  Individual treatment devices including macerator-chlorinator




toilets,  incinerator toilets,  septic tanks with soil absorption



fields, and aerobic extended aeration units were considered.




    14.  Macerator-chlorinator units presently available commercially




are not recommended for use in treating wastes from the floating




structures considered in this  report.




    15.  Incinerator toilets provide satisfactory treatment  of




toilet wastes  with proper operation and maintenance.   They are

-------
not satisfactory when considering the entire household waste.  The




estimated costs for these units installed will range from $350 to




$575 per unit.




     16.  For no more than one houseboat, a properly designed and




constructed shore septic tank with soil absorption field would provide




satisfactory treatment in areas where soil conditions and local regu-




lations permit.  Such a system installed would cost from $1100 up.




     17.  Aerobic biological treatment units with disinfection




facilities would provide satisfactory treatment of all wastes in




most waters of the study area.  Packaged units are available




commercially that could be used in either a floating- or shore-




type of installation.  Costs for a floating unit would range from




$1800 to treat the wastes from a single houseboat, to $200 per




houseboat for the wastes from 50 houseboats,




     18.  Commercially available biological treatment units are over-




sized for individual houseboat applications making them bulky and




prohibitively expensive.  There is a need for an economical individual




household secondary treatment device capable of operating satisfactorily




with a minimum of operation and maintenance.




     19.  Primary settling with sludge removal facilities and chlori-




nation of the effluent could be considered as an interim method of




treatment.  This process may find application where sewers are not




presently available but are contemplated in the near future.  The




lower degree of treatment will not interfere with other beneficial




uses of the water.  A system adequate to serve up to 25 to 35 house-




boats could be fabricated for $500 to $700, excluding labor costs.






8

-------
    20.  A system design with three alternatives was made for a




typical, moorage in the Portland, Oregon, area.  The design




considered:  (1) pumping with centrifugal pu;up=i from each house-




boat to a lift station for further lifting to a city sewer,




(2) pumping with centrifugal pumps directly to a city sewer




from each houseboat, and (3) pumping with pneuratic ejectors




to a floating treatment facility.  The cost to r.he individual




houseboat owner for each plan was $935, $1360, and ^1460,




respectively.  The first cost to the moorage owner for each plan




was $7500, $4600,  and $8700, respectively.  These figures do not




include annual costs for financing, operation, and n.aintenance.

-------
                         III.  WASTE CHARACTERISTICS


     Houseboat waste  is  purely domestic in nature and is expected

 to be  similar in both quality and quantity to that of a normal

 land residence.  A  literature search was made to characterize

 the houseboat waste on the basis of normal household character-

 istics but,  the available information is limited particularly on

 an individual household  basis.  That which was found, together with

 field  data collected  to  date, is reported at this time,,

     A.  Waste Quality

     Watson  et al^  '  report on the quality characteristics of

wastewaters  from several individual land residences obtained in

an extensive sampling program of several years.  These data are

expected to be characteristic of houseboat wastes.  Table 1

summarizes data from  this report for three homes.

     B.  Waste Quantity

     The reported average -residential sewage flow per capita is

approximately 75 gallons per day (gpd) with a range from 27 to

200 gpd.(2)(3)  The percent distribution of this flow has been

estimated as follows:

     Waste Source             Reference 2   Reference 3  Average

     Kitchen Wastes              13.3%           6%        107.
     Toilet Wastes               33,4%          41%        38%
     Showers, Washbasins, etc.    33.370          37%        35%
     Laundry Wastes              20.0%           4%        12%

     The  basic design  flow variations  used for small Army

installations are reported on page  13.

                                                              11

-------
                            TABLE 1

             Average Wastewater Quality from Three
                    Homes after Watson(l)
ANALYSIS (mg/1)
Total Solids
Suspended Solids
Total Volatile Solids
COD
BOD5
Detergents
Total Nitrogen
NH3 -Nitrogen
Total P04
Ortho-PC>4
Grease
PH
Flow (gpd)
Family Characteristics
Total People
Children
Home Laundries
Dishwashers
Baths
HOME 1
866
363
468
705
542
5.3
69
53
47
31
95
8.0
388
Home 1
5
2
1
1
5
HOME' 2
788
293
414
540
284
5.2
61
48
70
40
33
8.0
331
Home 2
5
3
1
1
3
HOME 3
1249
473
659
882
479
6.9
121
92
65
40
66
8.3
123
Home 3
5
1
1
1
1
12

-------
                       Basic Design Flow Variations
                       for Small Army Installations

                 Condition            Per Capita Flow, gpd

                 24-hour average               70
                 16-hour average               37.5
                  4-hour maximum              122.5
                 Extreme Peak                 210

At  this writing, limited data have been obtained on the waste

discharge from houseboats.  Assuming that the waste disposal

pattern would parallel the water consumption with a certain time

lag between usage and discharge and a small consumptive loss,

water use was monitored at several moorages.

     The measured average houseboat per capita water consumption

is  78 gpd, based on the use at two moorages in the City of

Portland (Portland Rowing Club and Water Lane Moorage) and one

moorage in the City of Seattle.  This is based on data for 1585

houseboat-months water use.  With a 5 percent consumptive loss,(l)

the average waste discharge is 74 gallons per capita per day (gpcd)

which agrees closely with figures reported previously.

     Data on hourly flow variations were obtained by installing a

continuous recording device on a water meter serving the Waterly

Lane Moorage located on the Willamette River in Portland, Oregon.

Figure 1 averages these data for two weekend periods.   Analysis

of  the data indicates good agreement with those reported previously.

     Waste quantities from other floating structures can be

estimated from Table 2 reproduced in part from the Manual of Septic

Tank Practice.(2)

                                                                13

-------
                    o
                s: 5Jo
                o m >
                o -o £
                a r» *
                > - 2
                C) ^3 *D
                m _i_ m


                StS
                > -I -
                2 l: w
                            o
                           -n «
      Ifl
      OD

      O
                  I O
x «
r m
•< m
r
                   3

                   o
                   o
                   (A
         o
         ft
o
c
m
      m



      C

      m
      m
                            s
                           o
                                     WATER  USE , GALLONS


                                                     8
                                                     O
                   O
                   o
N
o
o
8
u
o
o

-------
                           TABLE 2

                  QUANTITIES OF SEWAGE FLOW


Type of Establishment


Single family dwellings

Restaurants (toilet & kitchen wastes/patron)

Restaurants (kitchen wastes/meal served)

Public restrooms (toilet wastes only)
Sewage Flow*


  75 gpcd

7-10 gallons

2%-3 gallons

   5 gallons/
      patron
Public bathhouses (bathhouse, showers, toilets)    10 gpcd
Stores (per toilet room)
 400 gallons/
      day
*If recirculation toilets are used, the volume of toilet waste
 could be calculated on the basis of four gallons per 80 usages,
                                                                15

-------
                        IV.  PLUMBING REQUIREMENTS






      To  provide  treatment  for wastes from houseboats and other




 floating structures,  the wastes must first be collected and trans-




 ported to a  single point.  In the case of houseboats that treat




 their wastes individually, this point may end at the houseboat.




 For a moorage with a  number of houseboats, boathouses with sanitary




 facilities,  and  other structures with liquid waste discharges, a




 common collection system with a single treatment facility is the




 most  economical  approach.




      The  problem of collection is complicated by flood stage




 fluctuations on  the rivers (as much as 27 feet on the Willamette




 and Columbia Rivers in the vicinity of Portland), river currents,




 floating  and submerged trash, tidal fluctuations, and the fact




 that  few  of  the  existing houseboats and other floating structures




have  plumbing systems.  To overcome these problems, individual




pumping units at each waste source with sufficient capacity to




pump  the waste to a shore-based facility or a facility at the




moorage level were considered.   An alternative to the individual




pumping units would be to retain the waste in a holding tank and




use a portable pump to empty the holding tank periodically.   Gravity




systems could be used on lakes  and other quiet bodies of water but




these were not considered in this report,




     This section is composed of two portions dealing first  with




the individual collection,  holding,  and pumping systems,  and




second with the moorage collection and pumping systems.




                                                               17

-------
     It is expected that the individual will be responsible up to




the point of system connection and the moorage will be responsible




for providing a conveyance system and holding tank emptying facilities,




if necessary.




     A.  Houseboats




     The waste collection may require complete replumbing and indivi-




dual pumping units or simple holding facilities with provision made




for draining periodically.  In areas where gravity systems can be




utilized, replumbing may be all that is required.




     The drainage system of houseboats, boathouses, and other float-




ing structures with few exceptions, is composed of vertical drain




lines from each fixture discharging directly to the water.  Because




all wastes, including kitchen, laundry, and bath, require treatment,




most houseboats will require complete replumbing.  Also, in area's




where necessary to maintain lines above water, each structure will




have to be provided with a pump unit or a holding tank.




          1.  Plumbing Methods




          Methods and materials for plumbing installations on house-




boats and other floating structures must comply with State and/or




local plumbing codes except when alternatives are approved by the




plumbing department with jurisdiction.  It is recognized that there




are structural and financial problems involved unique to the existing




houseboats which may justify relaxation of certain code requirements




to effect a reasonable solution.




          The Floating Homes Association, Seattle, Washington, which




represents about 500 houseboats located on Lake Union within the






18

-------
 City of Seattle,  together with the  City  of  Seattle  Plumbing Depart-


 ment has developed an acceptable  plan for replumbing  existing


 houseboats.   At this time approximately  80  houseboats have been


 plumbed according to this plan.   This basic plan, modified to


 meet the State of Oregon Plumbing Code,  is  presented  in Figure 2.


          This method of  plumbing  for  houseboats  facilitates


 construction and  minimizes the expense involved, yet  provides


 a completely workable system.   In the future, all houseboats


 without exception will be expected  to comply with State or


 local plumbing codes.


          Approved materials for replumbing  are specified by most


 State or local codes.  In Oregon, the  State plumbing  code requires


 that all fixtures be trapped and  that  waste discharge piping be


 either galvanized steel,  galvanized wrought iron, cast iron, brass,


 lead pipe, or copper tube.  Plastic pipes, Acrylonitrile-Butadiene-


 Styrene  (ABS),  or Polyvinyl Chloride  (PVC), that conform to the


 temporary standards  of the U.  S.  Department of Commerce (CS270-65

 for  ABS  pipe  and  CS  272-65 for PVC pipe) are acceptable for use

 in California  but are  not  approved in  Oregon or Washington.  The

 National  Plumbing Code has proposed revisions to include plastic


 pipe and  fittings  for water, sewer,  drain, and waste lines„  When


 and  if  these  revisions are made, Oregon and Washington,  as well,


 may  allow the  use  of plastic materials.


         To provide relative cost estimates for replumbing house-


 boats, a  typical  floor plan for a one bathroom,  single story


houseboat was chosen and cost estimates were made for replumbing
                                            •

                                                                19

-------
                                       " IF OVER 4' FROM  ./TUB SHOWER

                                                         IF OVER 4' FROM MAIN WASTE
                                                          INDIRECT WASTE TO SUMP
                                                          EITHER  DOCK  OR INDIVI-
                                                          DUAL HOUSE SUMP,
                        PLAN 3
NOTE: BASIC PLUMBINO PLANS WHICH MEET
     OREGON CODES.
     CONTACT LOCAL STATE,COUNTY OR CITY
     PLUMBINO DEPT. WHEN DESIGNED FOR
     STRUCTURES OR VARIANCE IS
     NECESSARY.
                                          HOUSEBOAT  PLUMBING  PLANS
                                                      FIGURE  2

-------
with  copper, cast  iron, and plastic materials according to the

plan  illustrated by Figure 2.  The cost of material was based on

an  average  of unit prices at local distributors in the State of

Oregon.  Unit labor costs were estimated at $9.50 per man-hour and

the construction time at 40 man-hours using copper pipe.*  Construc-

tion  time for the other two materials was based on a recent article

by  Pierce using copper material as a reference,(5)  These times are

given as follows?
                                           Relative
                                           Construction
                     Material              Time	

                     Copper                   1.0
                     Plastic (ABS or PVC)     0.35
                     Cast iron                1.83

The estimated cost for replumbing a one-bathroom single story

houseboat is $230 with plastic materials, $560 with copper

materials, and $800 with cast iron.  These costs are summarized

in Table 3.

         The estimated labor costs in Table 3 can be reduced

significantly if the owner assists in the work as indicated by

three examples of houseboat replumbing presented in Appendix A.

The owners did their own carpenter work and assisted the plumber

which reduced the average construction time by a factor of two.

It should be noted that the construction times for cast iron and

plastic materials are hypothetical and may differ significantly in

practice.
*Based on figures provided by University Mechanical Contractors,  Inc.,
 Seattle, Washington, for three houseboats.   See Appendix A for details,

                                                                21

-------
                               TABLE 3

     ESTIMATED COSTS FOR PLUMBING A ONE-BATHROOM, SINGLE STORY
      HOUSEBOAT WITH COPPER, CAST IRON. AND PLASTIC MATERIALS


Type
Copper
Cast Iron
Plastic (PVC
2.
Cost of
Materials
$ 180
$ 110
or ABS) $ 100
Pumping Methods
Labor
Costs
$ 380
$ 690
$ 130

Total
Cost
$ 560
$ 800
$ 230

          Where pump units are required, the houseboat drainage system

should tie into a small sump with a pump or ejector to convey the

waste under pressure to point of treatment or disposal.  The sump

or ejector which could be connected to the houseboat float should

conform to the following design criteria;

               a.  Storage capacity excluding pump of at least 20

gallons.

               b.  Material should be cast iron, fiberglass,

aluminum, PVC, or steel coated with an asphalt or epoxy compound.

The weight of the sump should not be excessive.

               c,  Maximum liquid level in the sump should be 30

inches below the moorage connection, if possible.

               d.  Inlet diameter should be a minimum of 3 inches

and the outlet diameter a minimum of 2 inches.  If suitable

maceration precedes the pump, the outlet can be reduced even more.

               e.  Adequate venting should be provided.  A 2-inch

vent extended above the roof line is suggested.


22

-------
                f.   There must be  no overflow  from  the sump.




                g.   It  should be located or protected in such a




 manner as  to  prevent damage from  boats, swimmers,  floating or




 submerged  debris,  and  to facilitate maintenance and inspection.




         In pump selection, there are a number of  alternatives




 open  to the houseboat  owner depending on his  location and whether




 treatment  is  provided  on shore or on the water.




         If the  waste  is treated  on shore, which is recommended




 wherever feasible,  the pump capacity should be 55  gpm at heads




 varying from  10  to  over 40 feet.  An arbitrary selection of 20




 feet was made  to differentiate between high and medium head pumps




 on  the basis  of  several typical head-capacity curves.  The capacity




 of  55  gpm was  selected on the basis of providing a 2.5 feet per




 second (fps) velocity  in a 3-inch pipe.




         High head  pumps would be required for pumping directly




 to  shore in the  Portland, Oregon,  area.  In nearly all other areas




 where  houseboats are located in the States of Oregon, Washington,



 and California, medium head pumps could be used for pumping wastes




 to  shore.




         If the waste is pumped to a floating treatment facility




 or  to an auxiliary  lift station used in place of individual high




head pumps, a low head pump should be used with a capacity of at




 least 55 gpm at a head of 0 to 10 feet.




         Two types of pumps have been considered;   pneumatic




 ejectors and centrifugal pumps.






                                                              23

-------
          Pneumatic ejectors consist essentially of a closed tank




into which sewage flows by gravity until it reaches a certain depth.




Then air under pressure is admitted into the tank to displace the




sewage through the discharge line until the low water level control




cuts off the air supply.  Ejectors require one-way valves on both




inlet and outlet pipes, venting on the inlet side, level control




mechanisms, and a source of air under pressure.  For individual




houseboat pumping, pneumatic ejector units should provide their




own air supply.  If pneumatic systems were standardized on all




houseboats, perhaps moorages would provide the air supply, but this




possibility is unlikely.




          Pneumatic ejectors have the advantage of operating satis-




factorily over a wide range of heads from a minimal to a high head,




and to pass solids equal in size to the inlet and discharge piping.




Their main disadvantages include problems with check valves seating




properly, air control, and their high initial cost.  While they are




not free from operating problems, they are usually superior to centri-




fugal pumps that handle raw sewage.




          Pneumatic ejectors are ideally suited for houseboats in




principle because of their adaptability to various head requirements




and their nonclog characteristics.  However, few commercially




available units are economically feasible for houseboat application.




          At present, an ejector specific for houseboats for pumping




up to heads of about 20 feet is being developed in Portland.  This




work is aimed primarily at developing a unit that is small, self-







24

-------
contained, that minimizes problems with controls and check valve




clogging on the inlet side, and that has a significantly lower cost.




A test unit has been constructed and will be operated on a




houseboat for several  months to obtain data on its operation.




An approximate cost of this unit exclusive of valves, fittings,




and the small compressor to activate the ejector is $550.  The




additional cost of valves, fittings, etc. and the compressor would




run between $150 and $200 for a total price of approximately $750.




An ejector sufficient to pump against higher heads would be




considerably more expensive--on the order of $1500.




     Radial flow centrifugal pumps, submerged or dry, were




considered as applicable for individual houseboat pumps.  This




type was chosen because it is less expensive than other types of




pumps and is available commercially in packaged sump type




installations.




     Centrifugal pumps are compact and less expensive than




pneumatic ejectors.  Their main disadvantages include: (1) operating




head limitations and (2) clogging problems due to rags, stringy




material, and other solids found in raw sewage.




     High head centrifugal pumps are available commercially




and, with minor modification, can satisfactorily pump houseboat




wastes ashore in high head pumping areas.  Modifications include




throttling of the flow to reduce velocities when the total pumping




head requirement is low.  This may also necessitate maceration of




the sewage prior to pumping in order to maintain a system free from




                                                                25

-------
clogging,  It  is estimated  that a high head pump and sump, not.




installed, would cost at  least $450.  With maceration precedio^  the




pump,  the cost  is estimated at $600.




          Low  head centrifugal pumps are also available commercially




and could be used without modification for pumping ashore  in .iteas




with a 10- iv  20-foot head requirement.  A packaged sump and pu>  \-




of this  type is estimated to cost at least $330 not installed




          A. less, expensive  low head centrifugal pump could be us-^sl




for pumping at  the moorage level against heads less than 10 feet




but would require some modifications.  Throttling of the discharge




which may in turn require maceration would be necessary or the static




lift would have to be increased above 3 feet to assure dependable




service.  The cost for this type of pump with sump riot installed




would be at least $275.  To provide adequate maceration prior to




the pump would cost on the order of $150 for a total price of $425.




          A submersible type of centrifugal pump application that




could be used when throttling is required is illustrated schematically




by Figure 3.  This design includes a food grinder on the inlet and




a gate valve on the discharge line for throttling.  The grinder




macerates the sewage solids which reduces pump and valve clogging.




Throttling should be avoided if at all possible since this requires




additional and frequent maintenance.




          The disadvantages to this design should be carefully




considered before actual installation.  These are:
26

-------
            3" Flexible Pipe
            to Houseboat
 2" Vent
to roof lineN
                                       /O-IO, I0-30psi  Pressure Gage

                                                 ,2" Gate Valve
                                                      Union  ^^—Clamped Connection
                                                           2"Flexible Pipe
                                    2* Discharge Pipe
                                        -See State code for
                                         approved material
                                                                                   2'-6"
                                                                                   MINI.
       NOTE: inlet, Outlet and Vent pipes require watertight
              seals.
              Clamped connection can be used as safety
              shear section.
              Food Grinder is optional feature-not
              recommended unless throttling required.
                                                           CENTRIFUGAL  SUMP
                                                                 FIGURE 3

-------
               a.  The use of food grinders on raw sewage has serious



drawbacks, because they were not designed for this type of operation.



Any rags, sanitary napkins, or other long stringy material would



most  likely clog the grinder and require manual cleaning.  The life



of the unit under these conditions is unknown and in most cases



standard warranties would not be applicable.  There is only one



instance reported in the literature of a similar setup using a food


                                         (1)
grinder to precede a pump.  Watson et al.    report using a food



grinder in their waste sampling apparatus for several individual



households for several years with no apparent difficulties.



               b.  The grinder would have to be modified by placing



the manual restart switch outside the sump and the motor would have



to be sealed to water tightness.



               c.  A switching mechanism is also required to start



the grinder when there is flow to the sump.



               d.  Few centrifugal pumps in a feasible price range



for houseboat use will pass rags, sanitary napkins, etc. without



clogging.  The use of these pumps requires either close control



over what is discharged to the sewer or frequent maintenance.



          A unit with the grinder option has been constructed and



is being used in a 6-week houseboat sampling program in Seattle,



Washington.  Data on the installation cost and operation of this



unit will be made available in a separate report.



          An alternative to use of a food grinder would be to install



a macerating type pump in the interior plumbing system of the structure.





28

-------
This  type of pump  is commercially available and is used widely for



draining mobile home holding tanks and other types of sewage hold-



ing  facilities where the pumping head is less than 4 feet.



         This alternative has the advantages over the food grinder



of being a  tried and tested unit and is considerably less expensive.



It is estimated that this unit could be installed for approximately



$100 and would result in additional savings by allowing the use of




plumbing materials no greater than 2 inches.  Figure 4 gives a



schematic layout of this system.



         Table 4 summarizes the various plumbing and pumping methods



with their  associated costs.



     B.  O.ther Floating Structures



     For floating structures other than houseboats, with inter-



mittent, usage, such as boathouses, public restrooms, etc., a



number of commercially available devices could be employed for



the collection and/or treatment of the wastes.
             «


     If the structure has only a toilet such as many of the



public restrooms,  recirculating, chemical,  or incinerator toilets



could be successfuly used.   With the exception of the incinerator



toilet, these methods require facilities for periodical cleaning;



e.g., a portable sewage pump could convey the wastes to a point of



treatment or disposal.




     For structures with waste sources other than toilets such as



certain boathouses, some commercial facilities including floating



restaurants, boat  supply stores,  etc.  with sink and bath or shower




                                                                29

-------
                   METHOD I
Macerating
    Pump
                                       i sv.'MW.^ w.j. i ss sRc-g
                                                  Moorage Collection
                                                      Main
       Recirculating
       Toilet
                                                   Portable Sump
                                                         Pump-
                                      600 Gal Ion
                                      Holding Tank
                     METHOD  E
                                       MACERATING PUMP AND
                                   RECIRCULATING  TOILET APPL.
                                               FIGURE 4

-------
wastes, holding tanks could be used with one of the three toilet




devices mentioned above.  The tanks could be sized to retain the




waste for several weeks or longer on the basis of flow quantities




given previously in Table 2.  Disinfectant chemicals would be




required to inhibit sewage decomposition and offensive odors.




An installation similar to that illustrated by Method II in




Figure 4 could be used.  The estimated cost for holding tanks and




recirculating toilets to accommodate two complete restrooms with




washbasin and shower facilities for a 2-week period would cost




from $700 to $900.
                                                                31

-------
                       o o o
                       CO vO O
                       CN m oo
                    O m m
                    O   u
                •O
                 o
                       o
                      M-l
                       &0
                       C
                       •H
                       -o
                       3  o
                       ^-i  C
                       O  O
                       C  -H
                       •i-l  -U
 &0.-I
 a  co
•i-l  4-1
JD  CO
                                              C
                                              o
                                             •H  cJ
                                             •U  O
                                             Cj  »r-l
                                             Cj  ^jj

                                             a)  cd
                                              U  M
                                             cd  cu



                                          Ul
                                           cu  S  >
                                          •r-l
                                           0) i-l  i-l
                                             cd  cd
                                           O M M
                                          •H  3  3
                                           If II I  11  t
                                           3  4J  4J
                                           0)  C  C
                                           C  9)  0)
                                          CM  u  r_>
                    V
                    oo
                    ctf
                    M
                    o

                    i
                       0)
                    J-J  M-l
                    «
                       O
                    •U  <-l
                    C   I
                    •H  O
                    O
                    Oi'O
                       ctt
                    cd  
 CX  0)
 E -^
                                                              CO
                                                             •O
                                                              cd
                                                              a)
                                                              cd
                                                              4-1
                                                              O
                    4-1

                    cd


                    0)
                                        CO  4-1
                                           0)
                                        o  a»
 eoo
 C CM
•1-1  I
 cxo
 B ^
                                       CO
                                       •o
                                       cd
                                       *
•H  I
O.O

I"
  32

-------
                        V,   MOORAGE  COLLECTION






      This section of the  report  presents  design criteria and cost




 estimates for a moorage collection system,  including design




 capacity,  swells,  waves,  float connections, effects of  temperature,




 selection of materials, and  design of houseboat connections and




 lift stations.




      A.   Collection  System




      The  first  step  in the planning  of a moorage collection system




 is  the overall  plan  or system layout in which both present and




 future sources  of  waste must be  considered,




      The wastes  on a houseboat moorage or marina come from a




 variety of sources other  than houseboats.  These include boat-




 houses with  sanitary facilities, public restrooms, floating




 restaurants,  snack bars,  commercial establishments with sanitary




 facilities,  and  pleasure  craft with toilets.  Wastes of a




 continuous nature  require individual connections to the moorage




 system.  This includes the houseboats,  floating restaurants and




 snack bars,  and  other commercial establishments with a continuing




water use.   Other  intermittent wastes from public restrooms,  boat-




houses, and  pleasure craft,  and certain of the commercial establish-




ments such as boat supply houses, repair shops, etc.,  may not




require individual, connection to the system but instead, could




utilize holding tanks, recirculating ,  chemical,  or incinerator




toilets.
                                                               33

-------
     Provisions should be made for any future expansion of the moorage




for houseboat mooring, boathouses, etc.  The systems should be designed




with capacity to receive wastes expected during the life of the moorage.




     Moorages located on rivers, such as nearly all those in the




State of Oregon, will require pressure collection systems to main-




tain lines above water because of river currents, submerged and




floating trash, and water stage fluctuations.  As discussed previously,




each individual connection to the system will require a pump with




adequate capacity to force the waste to a central point for treatment




or further pumping.  This may be on the water or on the shore.




     In the States of Washington and California, most houseboats




are located on lakes, bays, or other relatively calm bodies of




water with little stage fluctuation.  In these situations, gravity




lines under water to a central lift station could be considered as




well as the individual pump units for a pressure system.




          1.  Design Capacity and Sizes




          A sanitary sewer has two main functions:  (1) to carry




the peak discharge for which it is designed, and (2) to transport




suspended solids so that deposits in the sewer are kept to a minimum.




          The system should be designed to provide scouring velocities




greater than 2.5 fps at least two times a day to prevent corrosive




effects and potential clogging from sludge accumulations.




          For moorage pressure systems, the design peak flow will




be dictated by the number of pumps on the system that operate
34

-------
 simultaneously, the rate of waste flow to the sump,  the pumping




 characteristics,  and the physical layout of the system.  The pipe




 should be sized to pass the peak flow at a velocity  greater than




 2,5 fps but less  than 10 fps,




           The minimum size pipe,  where more than one pump is




 connected,  is 3 inches.  This  size is adequate for peak discharge




 rates up to 220 gpm.   For rates  greater than this, a larger




 diameter pipe is  required.




          Appendix B presents design curves to indicate  number of




 pumps operating simultaneously for 99.9% of the time for multiple




 pump systems  on the basis of number of pumps connected  to the




 system,  rate  of inflow to the  pump sump,  and pump discharge rate.




 For example,  a system with 50  pumps connected,  a waste  discharge




 of  100 gallons in an  hour,  and a  pump discharge rate of 60  gpm




 would have  no more than six pumps  operating simultaneously  for




 99.9% of  the  time.




          2.   Swells,  Waves, and  Float  Connections




          To  allow for unequal movements  of one portion of  the




 moorage walkway relative  to the next,  caused by swells,  waves,  or




 unequal loadings,  lengths  of flexible  pipe  should be used wherever




 one walkway joins another.  This  is  illustrated by Figure 5.




          The  length of flexible pipe  should  allow for  an elevation




difference of 3 to 4 feet between adjoining walkways.  There  should




also be no sags with the additional  length made  up in the form of




a horizontal bend.




                                                               35

-------
             MOORAGE
                  WALKWAY
                                      FLEXIBLE PIPING
                                            -CLAMPED
                                              CONNECTION
FLEXIBLE PIPING
                            MOORAGE  WALKWAY^
                                   WALKWAY CONNECTIONS

-------
           3.   Temperature  Effects

           Provision should be  made  to  prevent  freezing  of  the

 lines  and  to  provide for expansion-contraction.  The  lowest  one-

 day average temperature noted  during 25 years  of record at the

 U.  S.  Weather Bureau Portland  Airport  Station  was  -3  degrees F  on

 February 2, 1950.   The maximum recorded for  this station was

 107 degrees F on July 30,  1950.

           The minimum temperature value should be  used  to  calcu-

 late the amount  of  insulation  necessary.  Flexible connections

 between separate floats as described above will provide sufficient

 allowance  for expansion and contraction if connection of the pipe

 to  the moorage is such that the pipe can move  within  the connection.

           4.   Materials

           The following materials have been  accepted  for use on

 houseboat  moorages  by the  City of Seattle and  would most likely

 be  acceptable in Oregon and California as well:

               a.  Hewitt Robbins Flexible Pipes F55,  F66*

               b.  White National Rubber Flexible Pipes  CH22A,
                  CH64A (Neoprene)*

               c.  Plastic  (PVC) 160# Test (Solvent joint or
                  rubber joint)

               d.  Cast Iron and Ductile Iron

               e.  Copper Class L

               f.  Transite  (Water Pressure Type)
*Mention of products and manufacturers is for identification only
and does not imply endorsement by the Federal Water Pollution
Control Administration or the U.S. Department of the Interior.

                                                                37

-------
Cost of material, labor for installation, and expected life will all




vary considerabl}1 for these materials.  Generally, plastic and cast




iron are the cheaper with flexible pipes the more expensive.  Concern-




ing labor costs, flexible and plastic pipes would be cheapest with




cast iron the most expensive; however, cast iron, pipe is the most




durable with plastic possibly the least.




          The specific situation, which will vary considerably from




moorage to moorage, will dictate the most economical choice of




material.  However, as a rough guide for estimating the cost of




moorage collection systems installed, Figure 6 indicates the cost




per houseboat per foot of moorage length for plastic and cast iron




materials.  An example on use of Figure 6 is given later in the




report.




          5=  Houseboat Connection




          A standard form of connection should be adopted by all




morrages because of the mobility of the houseboats.  It is suggested




that where above water pressure systems are required, a standard




3"x3" 2-inch Tee or Wye with a 2-inch check valve be provided for




each waste connection,,  A 2-inch stub from the check valve should




be provided for a clamped flexible pipe connection to the houseboat




sump.  The clamped connection can be designed to provide a point




of failure in the event the houseboat breaks loose from its mooring.




          A minimum grade of 0.25 inch per foot should be maintained




between the check valve and the 90 degree elbow on the discharge pipe




of the sump with no sags or low spots in the connection.  This method







38

-------
o
z
O

at
O

O
o
o
3
o
TOO



90



SO



70



60



50



40



30



20



10
         PVC PLASTIC
             10     20     30


          NO. Of HOUSftOATS
                              40
50
                              MOORAGE COLLECTION  COSTS
                                          FIGURE 6

-------
of connection is illustrated by Figure 7 for a centrifugal-type




sump.  The same type of connection could be utilized for a pneumatic




system.




     B.  Moorage Lift Stations




     Central lift stations may be used in lieu of high head individual




pumps at moorages that treat their wastes on shore in areas with




water stage fluctuations greater than about 20 feet.  If treatment




is provided on the water or where water stage fluctuations are not




as severe with maximum ranges between 10 and 20 feet, it will be




possible to pump directly from the houseboat sump to a treatment




facility or public sewer.




     The following design criteria for moorage lift stations are




suggested regarding location, construction, pump capacity, wetwell




design, and estimated costs.  An illustration of a typical installation




is also presented.




          1.  Construction




          The station should be located near the shore ramp to mini-




mize piping and to be convenient for maintenance, operation, and




electrical service.   It should be firmly secured to the moorage




walkway to reduce damage from float movement and be completely




above water.




          Figure 8 suggests a plan which would be applicable at




most moorages.  The station is supported by an auxiliary float and




connected to the houseboat line and shore discharge line with flexible




pipe.  The shore discharge line could be a tubular hand rail along




the ramp.




40

-------
          Moorage Walkwoy
Shore  Ramp
                                             Jl
     3" Pipe
                                         //  Flexible Pipe
                                         /    3"-C.J,Wye

                                         ^Flexible  Connection
                                              M
Wet Well
Flexible
 Connection
                   SECTION  A-A
                                         MOORAGE  LIFT  STATION
                                                FIGURE 8

-------
       RESTART BUTTON
         PUMP  SWITCH
                         OATE VALVE
                            CLAMPED CONNECTION

                          SHEAR CONNECTION
                                            2" FLEXIBLE HOSE
                                              2"r«ECK VALVE
                                         3? MAIN WYE CONNECTOR
                                             MOORAGE WALKWAY
FOOD WINDER,
(IF NECESlAftYi
                                 "0X30"
                               SUMP PUMP
                                    VARABLE DISTANCE  L FT.
                \
            -TV-
                           Vent to
                           Roofline
                             "^7?
^
^
                                            CENTRIFUGAL   SUMP
                                            PUMP INSTALLATION

-------
          Note  that  the  inlet  to  the wetwell  for the illustrated

 station  is approximately 6  feet above the houseboat discharge main

 and  8^ feet above  the maximum  water level in  the houseboat sump.

 With this static head, little  or  no throttling of the sump pump

 would be required.   The  float  should be sufficiently large to

 support  the weight of the station and provide stability against.

 overturning.

          2.  Capacity

          The minimum size  discharge line from the pumps is 2 inches

 for  a macerated or ground sewage  and 3 inches for a raw sewage.

 Since the velocity of flow  in  the discharge pipe should be main-

 tained between 2.5 and 10 fps, it follows that the pump capacity

 for  a 2-inch discharge line should be at least 25 gpm at low river

 stage and a maximum  of 98 gpm  at  minimum head or high river stage.

 For  a 3-inch line the minimum  is  55 and maximum 220 gpm.

          Centrifugal pumps should be able to pass the maximum size

 solids expected for  the  system or severe clogging will result.  For

 a raw uncomminuted sewage they should have a 3-inch solids handling

 capacity.  However,  solids would  not be, a major consideration and

 a less expensive pump could be used if the grinder, sump-pump

 combination, or toilets with macerator pumps are used.

          3.  Wetwell Design

          Design criteria for construction of wetwelLs  are available

 in a number of documents  and are  specified in state regulations.

Essentially the only variable  is  the volume and this is considered

below.
                                                               43

-------
          The selection of proper storage capacity is critical

because it affects the time the sewage is retained in the station

and the frequency of operation of the pumping equipment.  ASCE

Design Manual No. 37^ ' suggests a wetwell size that, with any

combination of inflow and pumping, the cycle of operation for each

pump will not be less than 5 minutes and the maximum detention time

in the wetwell will not exceed 30 minutes.  Based on these criteria,

a pump capacity of 75 to 125 gpm, and a rate of inflow varying from

200 to 900 gpd per houseboat, the following volumes are suggested

for the lift station wetwell serving houseboats.

             No. of                    Capacity
           Houseboats             Wetwell Storage, Gal.

                 1                         20
                 2                         30
               3-7                         50
              8-15                        100
             16-30                        150

The above figures are for total storage which is composed of the

volume between high and low water levels, the dead storage or

storage below low water, and freeboard volume.

          4.  Materials

          The moorage owner has three alternatives in providing a

lift station.  He can purchase the components and fabricate the unit

himself, have it built, or he can purchase a small package lift  •

station ready for installation*  Possibly with exception of the

small moorages, the prefabricated package unit would be the most

practical approach.
44

-------
          There are a number of package units on the market for




both centrifugal and pneumatic systems that would find application




as moorage lift stations.  The prices vary significantly depending




on the specific application, equipment needed, and manufacturer




with an estimated price range from $2.500 to $7000»  Again, this




is based on pumping uncomminuted sewage„  If the waste is




comminuted or solids removed by an incinerator toilet or other




means, this price range could be reduced,




          Additional details can be obtained directly from the




manufacturers or their representatives regarding specific




applications.
                                                             45

-------
                       VI.  TREATMENT






     Wastes from all sources can be treated individually or on a




group basis.  With few exceptions it will be more economical to




treat on a group basis.




     Since most floating structures can travel through and/or




reside on various classes of water, a minimum of secondary treat-




ment or connection to a shore sewer is preferable and is generally




required.  Connection to shore sewers, wherevfer possible, should




be required to consolidate waste treatment responsibility and




regulatory control.




     The remainder of this section discusses available treatment




methods and estimated costs on both an individual and group basis.




     A.  Individual Methods




     Individual treatment should be considered only when the source




is isolated and would cause great expense to connect to a central




system.




          1.  Macerator-Disinfecter Toilets




          This method, as the name implies, macerates and disinfects




the toilet waste before discharge.  Operation of the macerator and




addition of the disinfectant solution are generally automatically




triggered by the flushing action of the toilet.  These toilets




can be either marine or standard type.




          They have been shown''' to effectively reduce coliform




concentrations and provide some measure of organic removals when




                                                                47

-------
operated properly.  There is sone question, at present unanswered,




as to the bacterial efficiency of these units due to the presence




of sewage solids.




          The average cost of these units, based on prices quoted




from three different manufacturers, is approximately $100.  Assuming




an installation cost of $50, the total installed cost would be on




the order of $150.




          Macerator-disinfecter units have several disadvantages:




               a.  They do not provide secondary treatment.




               b.  These units are difficult to police to insure




adequate operation and maintenance.




               c.  Use on board government vessels has demonstrated




short life and periodic equipment repairs and replacement.




               d.  They do not significantly reduce solids concen-




trations nor provide a reduction in the degradable organic matter,




and the bactericidal efficiency is questionable, and generally,




unreliable.




               e.  Treatment is provided only for toilet wastes.




          These units have received approval in a number of states




for use on pleasure craft.  However, for reasons mentioned above,




they are not recommended for use in the houseboat problem.




          2.  Incinerator Toilets




          These units provide complete gas incineration of toilet




wastes to an inert ash.  They use no water for flushing but can






48

-------
handle  up  to  a  quart  of  liquid material.  The  combustion time  is




 from 14 to 18 minutes, but  the combustion cycle  can be  interrupted




 at  any  point  for  subsequent usage of  the unit.   Combustion vapors




 are vented to the atmosphere.  Operation is completely  automatic




 and the toilet  becomes nonusable when it is not  functioning




properly.   They use natural or LP gas  and are  ignited by 110 volts




AC  or a 12-volt DC battery.




           The treatment  efficiency of  these units  is complete  with




 100 percent removal of the sanitary waste.  Like the macerator-




disinfecter toilet, though, they provide treatment only for the




toilet  wastes or  based on figures presented previously, only




33  percent of the total  waste volume.  Table 5 indicates the




percent of the  total  household waste represented by the toilet




wastes.  This also would represent the percent efficiency of the




incinerator toilets in removal of these parameters.  This varies




from a  low of 23  percent total phosphate removal to a high of  100




percent NH^-nitrogen  removal.  While  this comparison is at best




a gross  one,  it does  indicate that incinerator toilets do not




provide  adequate  treatment on a total household waste basis when




secondary  treatment is the desired standard.




          The first cost of these units, not installed, runs from




$300 to  $500 depending on the type purchased and the extra features




desired.  There would also be the cost for gas and electricity but




these operating costs are minimal.   Installation of these units




could be estimated at approximately $50 to $75.




                                                                49

-------
                                  TABLE 5

          Comparison of Faces and Urine Waste Quantities to Total
                 Household Wastes for a Family of 5 People
Parameter
 Urine & Feces
Contribution (8)
     gm/day
Total Household
Contribution (1)
     gm/day
   Percent
Urine & Feces
Contribution
  of Total
NH3-Nitrogen
Total Nitrogen
Total P04
Grease or Total
Total Solids
62.0
65.0
14.5
Fat 22
360
60
76.5
62.0
30.7
950
100
85
23
71
38
          The primary advantages of these devices include:  (1) com-

plete removal of fecal and urine wastes, and elimination of most of

the public health hazard from houseboat wastes; (2) low first cost

and operation costs; (3) easy installation and maintenance, and

(4) assured quality control if properly installed since there is

no place for the waste to go if the unit is not operating.  Adequate

maintenance and operation are essential.

          The primary disadvantages of the units, and it should be

noted that these are undocumented, include:  (1) odor problems,

(2) questionable durability under continued long-term usage, and

(3) less than secondary treatment is provided  for the total household

waste.  Also, a relatively high cost is involved considering the

degree of treatment provided.


50

-------
          It is expected that these units may find application on




facilities with only toilet wastes such as certain boathouses, *




public restrooms, and certain commercial establishments or they




may be used for interim treatment.




          3.  Individual Aerobic Treatment: with Disinfection




          This method consists essentially of a tank with 24 hours




retention time, artificial aeration, solids settling and return,




and chlorination of the effluent before discharge.  It is a simple




system in principle but like any biological system, sensitive to




proper operation.




          There is only one unit presently known .£0 be on the




market suitable for individual application.  This  varies in size




from 750 gpd to 1,250 gpd.




          The efficiency of this unit with proper^installation and




maintenance is on the order of 75 to 85 percent organic removal and




would be acceptable as secondary treatment.




          For the individual houseboat the smallest unit is actually




oversized,  providing 750-gpd capacity when 200 to  400 gpd would be




sufficient.   This would not impair its efficiency  but does suggest




the need for a smaller sized unit.




          The cost of a 750-gpd unit is approximately $1000 delivered




to Portland,  Oregon.   To this would be added cost  of chlorinator,




flotation,  corrosion protection,  and installation  estimated at




$800,  and the total cost would be on the order of  $1800.







                                                                   51

-------
          Operation and maintenance of the unit relative to non-




biological forms of treatment are considerably greater both from a




time and money standpoint.




          4.  Shore Treatment




          If the wastewater from the individual houseboat is pumped




to shore for treatment, there are two alternatives.  These include




connection to a public sewer or to a septic tank with absorption




field, provided soil conditions permit.  Other methods such as hold-




ing tanks and extended aeration units are cheaper to use on the




water.




          Each of these alternatives has been investigated and it




appears that the most practical is to pump the wastes to a public




sewer.  This would cost approximately $800 to $1000.  If no public




sewer is available, the next approach would be to pump the wastes to




a septic tank with absorption field or seepage pit on shore.  The




area required for the field or pit can be determined from Table 6.




It is estimated that a system such as this would cost on the order




of $1100, installed.  If land is unavailable or if soil characteristics




do not permit the use of an absorption field, an extended aeration




type plant would be necessary for treatment on the water (a shore-




based facility would be more expensive than providing a floating unit).




     B.  Group Methods




     In instances where connection to a public sewer cannot be made,




moorages and houseboat owners will have to provide their own treatment,
52

-------
The alternative process discussed here meet State requirements.

They include a floating or shore-based extended aeration unit or

a settling unit with chlorination to be replaced by sewer connection

or secondary process at some designated date in the future.  Each

of these methods with illustrated applications is presented.

                           TABLE 6

    Soil Absorption Areas Required for Single Houseboats
             for Various Percolation Rates(l)
Percolation
Rate
min.
1 or less
2
3
4
5
10
15
30 W
Absorption Area'^)
Using Recirculating
Toilet, ft.
20
30
35
40
45
65
80
115
Absorption Area'^)
For Total Houseboat Waste
ft.2
45
70
80
90
100
150
180
260








(1)  Table based on allowable sewage loadings presented in Manual of
     Septic Tank Practice, U.S.P.H.S., No. 562, 1957.

(2)  Based on flow of 100 gpd per houseboat

(3)  Based on flow of 225 gpd per houseboat

(4)  Not suitable for seepage pit
                                                                53

-------
          !„  Extended Aeration




          Packaged extended aeration units are available from a




number of manufacturers in a size range suitable for a moorage




treatment system.  Information on facilities which can be modified




at a reasonable cost for flotation if desired, can best be obtained




through direct contact with a manufacturer.




          Figure 9 illustrates the estimated installed costs of a




floating extended aeration treatment facility for various sized




moorages on a per houseboat basis.  The cost per houseboat decreases




significantly as the size of moorage or number of houseboats served




increases.  For example, the cost per houseboat for serving one




houseboat is $1800 while the cost per houseboat for serving 50




houseboats is $200.  This curve is based on typical prices for a




floating treatment facility.  The cost for a unit installed on shore




would be less and would be recommended in areas with pumping heads




on the order of 10 to 20 feet.  In high head areas such as the




Portland, Oregon, area, it would be more economical to float the




treatment facility with the moorage.




          The major disadvantage to the packaged extended aeration




unit is the degree of competence required for efficient operation.




Like any biological system it is sensitive to a number of parameters




and unless these are understood by the operator, changes can upset




the balance in operation considerably„  Also, the annual costs of




operation are high due to power requirements, and maintenance labor.
54

-------
   !2,OOQr
    ! 1,506
UJ
(O
3
O
X

K
bl
0.
8
!l,000
                        FIRST COST INSTALLED WITH
                        CHLORINATION AND FLOTATION
               10     20      30      40
               NO. OF HOUSEBOATS SERVED
                                         50
                                  EXTENDED AERATION
                                 TREATMENT COSTS
                                             FIGURE 9

-------
          If these units are used, it is recommended that a service


agreement from the manufacturer or other reputable servicing firm


be obtained.


          Figures 10 and 11 illustrate typical examples of how and


where floating extended aeration facilities could be used.


          2.  Settling Tank and Chlorination


          This method of treatment will not provide the degree of


efficiency normally required but might be adequate as the first


step in a stage treatment scheme which would lead to secondary


treatment.


          For the raw houseboat waste, the process would include a


settling tank constructed with a sludge draw off standpipe.  The


effluent would be chlorinated before discharge.


          The settling tank should be designed on the basis of less

               2
than 600 gpd/ft  of surface area and provide a minimum of 2 hours


retention of the design flow.  The design flow should be the 16-hour


daily average or 95 gpcd.  The bottom of the tank should be sloped


at least 2:1 to the sludge draw off pit, and the chlorine contact


chamber should provide a 15 minute contact time on the basis of the


design flow.  If recirculating or incineration toilets are used on


the houseboats, the design flow can be reduced to 70 gpcd and if no


laundry facilities are permitted it can be further reduced to 50 gpcd.


          Figure 12 illustrates a typical design which utilizes a


500 gallon septic tank modified as shown, a 55-gallon barrel with


portable chlorinator, all supported by a wood float over styrofoam



56

-------

   uu
   o:
o
LJ
K- S
z <
< u
p
bit*
*s
ifE
§1
cc
_i o
U. U

-------
u.
   tf)
                                                                         oc
                                                                         i
                                                                         u.

-------
             SCUM .BAFFLE
                      CHLORINE
                      CONTACT
                      CHAMBER
SETTLING
  TANK
                                   2 DISCHARGE
                                         PIPE
4'-6"
      -3 SLUDGE D^AWOFF TO
        COMMERCIAL SEPTIC
        TANK PUMPER
                                     2"GATE
                                      VALVE
                        SETTLING  TANK ft
                    CHLORINATION  TREATMENT

-------
cylinders.  All metal surfaces would be covered with an asphalt,




epoxy, or other approved coating.  This design uses standard,  off-




the-shelf equipment and could be fabricated, excluding labor,  for




approximately $500 to $700.  It would be sufficient in size to




handle up to 35 houseboats using recirculating toilets.  Without




recirculating toilets, 25 houseboats could be connected.  This




unit could later be salvaged for use in construction of a lift




station when sewers become available.  The use of plastic or




fiberglass materials for the settling tank and contact chamber




could be weight saving.  The cost of this material would be some-




what higher but this may be off-set by savings in float requirements




and installation time.
60

-------
                     VII.  EXAMPLE DESIGN






     The  following  design is  presented  to  illustrate method  of




design, equipment application,  alternatives  for  treatment, and




cost estimates.  It should be emphasized that  these costs  are




only estimates  and  could change significantly  with different




equipment  and labor costs.




    In  the design of this system, three alternatives are




considered:




          1.  Centrifugal pumps  at each houseboat  that pump to a




central lift station on the moorage which  in turn lifts the




waste to a Portland city sewer.




         2.  Centrifugal pumps  at each houseboat  with capacity




to pump directly to shore to  a  Portland city sewer.




         3.  Pneumatic ejectors  at each houseboat that pump  to




a floating package  plant.




    Each alternative  is discussed below.   The  basic scheme for




the system design in  plan and profile is shown on Figure 13.




    A.  Basic Design  Criteria




    The moorage is  assumed to accommodate  18 houseboats with no




future expansion considered.    A total of  35 people live on  the




houseboats.




    The average 24-hour flow  is  75 gpcd, and the  average 16-hour




flow is 95 gpcd.  The maximum rate of waste flow  expected from a




houseboat is 50 gallons in an hour.

-------
                                                            PORTLAND CITY SEWER
                                                            MANHOLE SMH INV EL 31.9-
     FLOATINO LIFT STATION
     LOCATED  ALONG MOORAOE
     WALKWAY
MAX WS EL. 26.8
MEAN WSEL.&9

MIN.Wt EL.0.0
                              4"FORCE MAIN, ATTACHED TO
                                MOORAQE WALKWAY
                                                        NOTE: ELEVATIONS ON DATUM  1.95FT. ABOVE
                                                             M.S.Li  PIPING LAVED  LENGTHS
                                                             BASED  ON  AERIAL PHOTOS »ELEV.
                                                             DIFFERENCES
                                 EXISTING PORTLAND CITY
                                 SEWER-MH. S.E.I84
                                     AIR
                                  STATION
                                   AIR  LINE X

                        FLEXIBLE CONNECTION
                        COLLECTION MAIN
                                     325'
                                                                 BAFFLE BOX
                                                   FLOATING LIFT STATION OR(CENTRIFUGAL OR
                                                   PNEUMATlOFLOATING PACKAGE TREATMENT
                                                   PLANT.
4V
          260'
                     : HOUSEBOATS WILL DISCHARGE WASTE
                     INTO COLLECTION MAIN BY PUMPING
             WILLAMETTE  RIVER
              SYSTEM DESIGN
                                                                     FIGURE 13

-------
      The average organic loading per person is CL25 pound of 5-




 da.y biochemical  oxygen demand (BOD)  per  day on the basis of data




 presented in Table I.,




      A minimum velocity of 2 ,,5 fps and a maximum velocity of 10




 fps will, be used to size the force mains.




      A wetwell capacity of 1.50 gallons will  be used as  indicated
      B.   Layout and Cost. Estimates




      Each of the three alternatives  is  discussed  in two  schedules




 on the basis of financial responsibility—that  of the  houseboat




 owner and that  of the  moorage  owner.  Cost  estimates are given for




 each  alternative,




           1 ,  Alternate A




           This  alternate calls  for houseboat  plumbing, centrifugal




 pumps at  each houseboat,  a moorage collection system,  a  lift  station,




 and a discharge force  main with baffle  box  for  connection to  a city




 sewer „




                a0   Schedule_l




                This  schedule is composed of plumbing,  provision of




houseboat  pump  units,  and connection to the moorage system.   It




will be the  responsibility of the houseboat owner.




                Houseboats were assumed  to be plumbed with  copper




materials by a  licensed plumber in accordance with  the plan presented




by Figure 2,
                                                                63

-------
               Packaged submersible centrifugal pumps in 18"x30"




cast iron sumps were used at each houseboat and attached in a manner




similar to that illustrated by Figure 3.




               The grinder mechanism for macerating sewage solids




was not considered necessary as the total lift between the high




water level in the sump and the discharge point to the wetwell was




in excess of 5 feet which is the minimum operating head for the pump.




               The normal operating range of the houseboat pumps




would vary, depending on the number of pumps operating simultaneously,




from 110 to 90 gpm.  The corresponding maximum flow in the collection




system which may be exceeded 0.1 percent of the time, would be 270 gpm.




               Each houseboat pump unit will be connected to the




moorage system with a length of 2-inch flexible hose of a type




mentioned previously.  The hose will be clamped on both ends with




sufficient strength to hold under normal stresses but such that it




will fail first in the event the houseboat breaks from its mooring.




               Estimated costs for plumbing and the pump units are




based on figures reported previously, plumbing at $560 per houseboat




and the pump units including installation at $325 per houseboat.




The cost for making the moorage connection is estimated at $50 per




houseboat.  The total first cost then to each houseboat owner would




be $935.




               b.  Schedule 2




               This schedule includes the moorage collection system,




the lift station, and the shore discharge line with baffle box.  It





64

-------
would be  the  responsibility  of  the moorage owner  to provide  this




system*




                The moorage collection  systeir  to the wetwell  of  the




lift  station  was  designed of 3-inch Schedule  ^.0 PVC pipe.  This




size  pipe requires an average flow of  55  gpn?  and  is adequate, for




flows up  to 240 gpm«   The peak  flow would actually be 270  gpm but




the difference  was not considered significant enough to warrant




the. use of 4-inch pipe.  The line, is supported at 5 foot intervals




with  devices  that allow  the  pipe to contract  and  expand»   A.  5-foot




long,  3-inch  flexible hose connection  was made every 100 feet and/or




at every  walkway  division,   A standard connection with 3"x3"x2"




tees  and  a 2-inch check valve was provided for every houseboat.




Insulation of the pipe was not  considered necessary on the basis




of heat transfer  calculations for extreme temperatures.  The




weight of the collection system is less than  2 pounds per  foot and




no additional flotation was  considered necessary.




               A  package lift station built in accordance  with




State  requirements was selected with dual nonclog sewage pumps.




To reduce  head  loss and pump  capacity, a. 4-inch .PVC Schedule  40




discharge  line was used.  Pumps with a capacity of 100 gpm at a




head  of 50 feet were  satisfactory for use in the  lift station,,




               It was calculated that the station would support




itself with no additional buoyancy at a depth of 3.5 feet when




empty.  The auxiliary float was designed only to support the




weight of sewage  in the wetwell before pumping and the, weight of






                                                               65:

-------
two men.  The float will also give the station stability against




overturning.




               The force main from the lift station to the shore




sewer is of 4-inch Schedule 40 FVC pipe,,  The shore connection is




similar to that indicated by Figure 8 with a 5-foot length of 4-




inch flexible hose connecting the lift station to 4-inch PVC pipe




attached to the. 60-foot, long ramp,  A 10-foot length of 4-inch




flexible hose is used to connect the shore side of the ramp to the




4-inch PVC main on shore.  The line on shore is laid in trench and




backfilled.  A baffle box is used to dissipate the velocity head




before discharge to the sewer manhole.




               The estimated cost of the moorage collection system




is based on data presented in Figure 6 for the PVC system.  This




cost, for 18 houseboats, is $0,138 per houseboat per foot of




moorage length.  For the example moorage with a total length of




680 feet to the lift station the cost would be $1700.




               The lift station cost with auxiliary float is




estimated at $3600 installed.  This cost is based on typical




material and labor costs for the Portland, Oregon, area.




               The discharge force main of 4-inch PVC Schedule 40




pipe with an energy dissipating baffle box is estimated to cost




$1500 for materials and $700 for labor for a total cost of $2200.




               The total cost to the moorage owner for Alternate A




is $7500.
66

-------
           2 „  Alternate B




           This alternate calls  for individual, centrifugal pumps




at each houseboat with capacity to pump directly through a moorage




system to  a shore sewer,




               a „  Scheduj,e_j_




               Under  this schedule are the houseboat plumbing and




the  individual, pump units,




               Plumbing would be the same as discussed previously




and  the estimated cost would be $560 per houseboat.




               Each pump unit to pump ashore will require capacity




to pump against a 51,9 foot head plus system losses.  To minimize




head losses and reduce the pump size, a 4-inch collection system




is required,  With a 4-inch collection system and discharge main,




a 1-hp pump with a capacity of 100 gpm at a head of 50 feet can




be used.  Each unit would be connected as discussed previously.




               The estimated cost for each pump unit is $950,




installed, plus an additional $50 for the moorage connection.




The total cost for each houseboat would be $1560 for this alternate.




               bo  Schedule 2




               This schedule would be the same as that discussed




under Schedule 1 with the exception that a lift station would not




be required and a 4-inch collection system would be required rather




than a 3-inch system,   The total estimated cost to the moorage




owner for this schedule would be $4600,  installed.







                                                              67

-------
          3.  Alternate C




           This alternate calls for pneumatic ejectors at each house-




boat  that pump to a central floating treatment plant.




               a.  Schedule 1




               Plumbing is the same as discussed earlier with an




estimated cost of $560 per houseboat.




               The pneumatic ejector units are complete packaged




units sized for an individual household.  The total pumping head is




less  than 10 feet and a low pressure ejector is utilized.  The




estimated cost for the ejector is $800 installed.  There would be




an additional charge of $50 for the connection to the moorage system.




               The total cost to the houseboat owner for this schedule




is $1410.




               b.  Schedule 2




               For this alternate the moorage owner would have to




provide a moorage collection system and a floating treatment facility.




               The moorage collection system would be the same as




that discussed under Schedule 2, Alternate A, with an estimated




cost of $1700.




               The cost for the floating treatment facility was




estimated on the basis of data provided in Figure 9.  This estimates




a cost of $7000 or $390 per houseboat.




               The total cost to the moorage owner for Alternate C




is $8700.




          4.  Summary




          Costs for the three alternatives are summarized in Table 7.





68

-------
Alternate A  is  the  least expensive method for the houseboat owner

but  involves a  greater cost for the moorage owner.  Centrifugal

pumps,  with  their inherent difficulties in pumping raw sewage

are  also a disadvantage,  Alternate B is the least expensive for

the  moorage  owner but the most expensive for the houseboat owner.

It also involves the use of centrifugal pumps for raw sewage and

large expensive pump installations at each houseboat.  Alternate C

is expensive for both the houseboat owners and the. moorage owners.

Pneumatic ejectors, though, would provide dependable none log

service and possibly in the long run be more economical.

         The floating treatment facility on the other hand may

prove to be much more expensive than the first cost indicates

because of annual operation and maintenance, costs.

         It should also be remembered that the costs presented in

Table 7 do not represent annual costs but simply the first cost

for  capital investment.  Annual operation, maintenance, replacement,

and  financing costs may present an entirely different outlook and

should  be considered before deciding on any one method.

                              TABLE 1

                           COST SUMMARY

Schedule                 Alternate A    Alternate B    Alternate C

1--Houseboat Cost
    Plumbing               $  560         $  560         $  560
    Sump,  pump & connection   375           1000            850
   TOTAL COSTS             $  935         $ 1560         $ 1410

2--Moorage Cost
    Collection System      $ 1700         $ 2400         $ 1700
    Lift Station             3600
    Force  Main & Baffle Box  2200           2200
    Floating Treatment        	-           	-           7000
   TOTAL COSTS             $ 7500         $ 4600         $ 8700

                                                                69

-------
                         VIII.  BIBLIOGRAPHY
  1.  Watson,  K. S., Farrell, R. P,, and Anderson, J. S „  "The
          Contribution  from the Individual Home to the Sewer
          System."  Paper presented before annual WPCF Meeting,
          September 1966,,
  2.  Manual of Septic Tank Practices.  Public Health Service
          Publication No. 526, 1957.
 3.   "The Effect of Industrial Wastes on Sewage Treatment."  New
          England Interstate Water Pollution Control Commission,
          June 1965.
 4.  Babbitt, R. E.  Sewerage and Sewerage Treatment.,  6th ed.
          John Wiley and Sons, Inc., 1949„


 5.  Pierce, J. W.  "Plastic Pipe—A Progress Report/1  Civil
          Engineering, ASCE, February 1967.
 6.  Design and Construction of Sanitary and Stcjrm Sewers.  ASCE
          Manual of Practice No. 37, 1960.
 7.  "Evaluation of Marine Toilet Chlorinator Units."  by Syracuse
          University Research Corporation for New York State
          Health Department.  Report No, 9, May 1962.


 8.  Sunderman, F. W. and Bociner, F.  "Nutritional Values in
          Clinical Medicine." p. 260.  W. B, Saunders and Co,,
          1959.

 9.  Personal communication with Dr. Donald Guthrie, Associate
          Professor of Mathematics at Oregon State University,
          Corvallis, Oregon.
10.  Cox,  D.  R.  and Smith,  W.  L.   Queues.   John Wiley and Sons,
          Inc.,  1961.
                                                              71

-------
IX.  APPEND IK

-------
              APPENDIX A

Plumbing Costs for Three Houseboats in
          Seattle, Washington

-------
           UNIVERSITY PLUMBING 6- HEATING CO.
                           CONTRACTOR*

                    iaiTVWAVN.fi • 9. O. • O X •• • PMQMC

                     • CATTLE, WABHINOTON 9B1OB
•OLD TO
        Terry Pattut
        2039 Falrvlaw Ave. East
        Saa-HU. Washington 98102
                                                        -46-
   CAIN Upon COWUTIM «r w«««
                                            f. a. NO.
        2339 PalrvlM Ay*, b.
        Rorough waitat, vwitt and watar for houcaboat
                   9/14   9/21
        Wtlaman

        Paterton
II

 7
IQTAI >
-------
           UNIVERSITY PLUMBING 6- HEATING CO. |
                           CO NTHACTORS
                     BCATTLE. WASH INOTON 9B1OS
                                             DAT!
                                                 October 11,
•OLD TO .
       Dan Brackett
      .2818 Boyer East
       Seattle, Washington
                                                               -1»-
Timid C««H UMK coupumoM OF wonn 0ur JOB NO. |9|9
Rcrough wastes, vonts and »at«r for hous* boat
LABOR 9/14 RATE TOTAL
Kattleman 16 7.30 131.40
Labor
Material
Porni It

Overhead I5£

Foe 10*

Sales Tax

P. O. NO.



131.40
191.57
3.75
326.72
49.01
375.73
37.57
413.30
17.36
430.66

-------
          UNIVERSITY PLUMBING 6- HEATING CO.
                          CONTRACTOR*

                    • CATTLE, WA1MINOTON ••IDS
       Simons
KH.OTO .  281 A Boynr Avenue Ea§t
       Seattle, Washington 96108
                                          DAT. October  7
.ie«?_
'. • run* C*«H un» eemunm or won Our
Rough In
LABOR Q/21,
Kettleman 7
Petereon 7









MB NO. 2047

aia TOTAL BAJK
U 84 7.30
II 6* 7.30
Labor
Material
Perwlt

Overhead 15*

Fee 10*

Sales Tax
9. O. MO.

TOTAL
60.23
60.23
'20.46
172.17
3.00
295.63
44.34
339.97
34.00
375757
389768

-------
        APPENDIX B

Design Curves for Multiple
       Pump Systems

-------
          DESIGN CRITERIA FOR MULTIPLE PUMP SYSTEMS

     Moorage collection systems with a number of pumps connected
in parallel should have adequate capacity for the maximum probable
number of pumps operating simultaneously.  To determine the
probable maximum number for various size moorages, queuing theory
was employed to relate pertinent design parameters which include:
          1.  Number of pumps connected to system.
          2.  System head characteristics.
          3.  Rate of sewage inflow.
          4.  Pump head-capacity characteristics.
          5.  Rate of pumping.
     A relationship developed by Guthrie^'and Cox'  ' for
indicating the proportion of time or probability that any number
of pumps in various sized systems operate simultaneously is given
by equation 1.
                Pj - P0rj     (D
              where

                rj • 1 for j»o
                       and
                                         ™  JJ for 1*- j *N  (3)
                     (       j!          (o)  )
             N = number of pumps connected to the system
             I • rate of inflow to the pump sump, gallons per minutes (gpm)
             0 - pumping rate, gpm
                                                                81

-------
          Pj * proportion of time or probability that j pumps are




in operation where j varies fron o  N




     For general use a family of curves was prepared for Pj by vary-




ing the number of pumps connected to the system from 0 to 50, the




rate of inflow from 50 gallons per hour (gph) to 200 gph and the




pumping rate from 120 to 30 gpm,  These curves are given in Figures




14 and 15.  The indicated number of pumps operating simultaneously




would cover over 99.9 percent of the time; i.e., there would be a




0.1 percent chance that the indicated number of pumps operating




would be exceeded.




     It should be remembered when using the curves that the average




24-hour houseboat waste flow is less than 200 gallons and the




average pumping rate would be on the order of 60 to 100 gpm.
 82

-------
                     INFLOW RATE -   50 GPH
   2
   c
II
I  i
10
9
8
7
6
5
4
3
2
 I
0
           30GPM
           40GPM
      606PM
           1206PM
                        I
I
                  10   15    20   25   30   35   40
                       Number of Pumps Connected to System
                                              45   50
                     INFLOW RATE =   100 GPH
Q- -3
*o 
-------
                     INFLOW  RATE *   150 GPH
I!
"5  
-------