vvEPA
          United States
          Environmegtal Protection
          Agency
            Office of
            Policy and Resource Management
            Office of Water
            Washington, DC 20460
                                   June 1982
Streamlining
The Environmental
Permitting Process:
800R82101
          A Survey of State Reforms
          Final Report

-------

            UNITED STATES ENVIRONMENTAL PROTECTION AGENCT

                        WASHINGTON. D.C. 20460            *
                          JAN 5   1983
V£L
                                                    .oeacgL,
                                                POLICY AJMMI
  AGEMENT
Dear EPA Official:
     We are pleased to be able to send you a copy of Streamlining
the Environmental Permitting Process:  A Survey of State Reforms.

     This report produced during 1981 and 1982 describes the
initiatives that all 50 states have taken to streamline and
expedite the environmental permitting process.  Information for
this survey was gathered by our consultants, Temple, Barker, &
Sloane, primarily from telephone interiews with state officials
and from secondary sources of information.  The resulting report
is a state-oy-state description of the environmental permitting
reforms that the officials interviewed considered to be the most
significant.  It is designed to serve as a reference tool for
those interested in learning about the types of environmental
permitting reforms initiated across the country.

     There are several limitations to the study that we would
like to make readers aware of:

     1)  Because of the manner in which, the survey was conducted,
         there is a possibility that we missed an important reform
         within an individual state.  We are encouraging state
         officials to submit to us additional or up-dated informa-
         tion on the: r programs.  We will prepare an addendum of
         changes to the appropriate state summaries and send it
         to everyone on our mailing list.

     2)  It must be emphasized that the report covers a broad
         spectrum of state environmental permits.   It does not
         focus on one specific type of permit such as water or
         hazardous waste.   In some state summaries, it is difficult
         to tell which reforms apply to which permits.   It may
         also be unclear whether a state's program is approved
         by EPA or whether the state is Implementing its own
         authorities which differ from the federal Clean Water
         Act, Clean Air Act, etc.

              Detail that  some readers may want may be lacking.
         For example,  for  those states with a one-stop permitting
         process, our description of the process may not be
         sufficiently detailed to Indicate whether federal permits
         are included in the process or whether applicants must

-------
                              - 2 -
         apply for them separately.  Or where we indicate that a
         state uses general permits, we often do not indicate the
         specific permit programs for which the general permit
         approach is used.

     3)  The purpose of this document is primarily informational.
         The Office of Policy Analysis does not endorse one type
         of state reform over another, nor, in all cases, do we
         believe that whatever is cited as a reform is a success.
         Reforms have been developed to meet the organizational
         and environmental needs of each state and should be
         reviewed with this in mind.  For instance, some reforms
         might be intended by a state not to accelerate permit
         issuance but to afford the state the opportunity to
         simultaneously review all aspects of a project's environ-
         mental impacts.  Such reforms may in fact slow permit
         issuance.

     4)  Some state reforms may be legally acceptable in
         independent state programs but would not be authorized
         under federally approved or delegated programs.  For
         example, automatic issuance of a "default" permit once
         a decision deadline is passed is a reform in use in some
         states.  Such an approach generally would not be accept-
         able in a Federally approved NPDES program.

     5)  Our consultants felt that categorization of the reforms
         that were reported to them required a good deal of
         judgment.  Consequently, the report should be viewed as
         a somewhat subjective account of state permitting initia-
         tives.

     In spite of these limitations, we feel this is a useful study.
As the agency continues to turn responsibility for programs back to
the states, it is important for both state and federal officials to
be aware of the innovations being implemented in various jurisdictions
so that the most promising of these might be given consideration and,
where appropriate, be adopted so as to provide better service.

     Additional copies of this report are available from the National
Technical Information Service (5285 Port Royal Road; Springfield,
Virginia; 22161).  You may order by phone (703-487-4690) and charge
the report to your American Express, Visa or Mastercard.  Please
refer to the report's number PB82-256983 when placing your order.
You may also order by letter by stating the report's number and
including a check in the following amounts.  A paper copy is $18.00
now and $19.00 after January 1; microfiche is $4.00 now and $4.50
after January 1.
                                Sincerely,
                                Joseph A. Cannon  K
                                Associate Administrator
                                  for Policy and Resource Management

-------
         STREAMLINING

     THE ENVIRONMENTAL

     PERMITTING PROCESS:
   A Survey of State Reforms
             Final Report
  U. S. ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF POLICY AND RESOURCE MANAGEMENT
             June 1982 ^ Environmenta, Protection Agency
                    Region V, Library
                    230 South Dearborn Street
                    Chicago, Illinois 60604

-------
                             PREFACE
     This document presents  information  obtained  from tele-
phone interviews with officials  in  all  50  state  governments as
well as from secondary sources of information.   Special  appre-
ciation is given to the many  state  officials  who  contributed
their valuable time and thoughtful  review.  Acknowledgement is
also made to the Southern States Energy  Board,  the  Western
Interstate Energy Board, and  the Regulatory Reform  Institute
for their work in the early  stages  of the  survey.

     The U.S. Environmental  Protection Agency's  Energy
Facilities Branch within the  Office  of  Policy and Resource
Management provided direction throughout the  duration of the
project.  The Office of Water Enforcement  and Permits also
contributed extensively.  Special thanks are  given  to Stu
Sessions and Sue Wilson for  their valuable assistance.

     This document was prepared  by  Temple, Barker & Sloane,
Inc. under contract No. 68-01-5845  to the  U.S.  Environmental
Protection Agency.

-------
                      CONTENTS
PREFACE                                       i


EXECUTIVE SUMMARY                             v



PART I:  INTRODUCTION                         1

  Objectives                                  4

  Methodology                                 5

  Key Reforms                                 5

  Observations Concerning
  State Permit Reforms                       17



PART II:  STATE SUMMARIES                    23



APPENDICES

  A.  EPA Programs Delegated and
      Authorized to States                  225

  B.  Bibliography                          227

-------
                          EXECUTIVE SUMMARY
     As the complex of state,  federal,  and  local  environmental
regulations has multiplied over  the  last  decade,  developers of
energy and industrial projects have  increasingly  faced  prob-
lems of confusing and duplicative permit  requirements  and
delays in receiving permit approval.   In  response,  many states
have initiated procedural permitting  reforms.

     During 1981, the U.S. Environmental  Protection Agency
undertook a survey of the procedural  environmental  permitting
reforms in all 50 states.  Information  for  this survey  was
gathered primarily from  telephone interviews  with state offi-
cials and from secondary sources of  information.   The  result-
ing report is a state-by-state description  of  the environ-
mental permitting reforms that each  state considers the most
significant.

     This survey is designed to  serve as  a  reference tool for
state officials interested in  learning  about  the  types  of
environmental permitting reforms initiated  by  their counter-
parts across the United  States and in exploring alternatives
to implement at home.

     In order to help state officials locate  states where
similar procedures have  been implemented  and  to provide a
structure for analysis,   each state permitting  reform was  cate-
gorized into one of the  following key reforms:

       •  Computer tracking

       •  Decision-making deadlines

       •  General permit

       •  Joint application

       •  Joint hearing

       •  Joint review

       •  One-stop permitting

       •  Over-the-counter processing

       •  Permit/application coordinator

       •  Site inventory/banking

-------
PART I:  INTRODUCTION

-------
                           INTRODUCTION
     State, federal, and  local environmental  laws  and regula-
tions have reduced air, water, and  solid  waste  pollution and
have mitigated many negative  impacts  associated with energy
and industrial projects.  However,  as  these  regulations have
grown in number and complexity,  so  has  the difficulty for
agencies in administering the regulatory  programs  and for
project applicants in understanding and applying for the many
permit requirements associated with them.

     The complex of environmental laws  that  exists today was
formed incrementally over time;  each  new  law  was passed to
address a specific, single purpose  or  need,  and subsequent
laws were passed to fill  in gaps  left  uncovered by the old.
Moreover, organizationally separate agencies  and programs also
developed incrementally at the local,  state,  and federal
levels.  As a result of this  history,  these  agencies frequent-
ly have overlapping, duplicative, or  contradictory regulatory
authority as well as inadequate  communication networks.

     The effect on industrial and energy  project sponsors has
often been burdensome in  terms of money and  time.   Inadequate
and conflicting information,  constantly changing and duplica-
tive application requirements, and  lengthy permit  decision
times are factors that have contributed to added project costs
and delays in commencing  projects.  Government  agencies have
also suffered in terms of their  efficiency,  coordination,  and
quality of decision making.   Just as  regulatory overlaps oc-
cur, there may also be situations where poorly  coordinated
review procedures fail to address environmentally  unsound
aspects of projects.  And ultimately,  of  course,  the public
has paid through inadequate environmental protection,  costly
government services, and  higher  priced  energy or industrial
projects.

     There are numerous examples  of delay and cost due to this
regulatory maze.  One of  the  more extreme cases was the Sohio
pipeline proposal which underwent five  years  of attempting to
meet 715 permit requirements  before the effort  was abandoned.1
The Kaiparowitz coal project  in  Utah  spent 14 years in the
regulatory process before it  was  ultimately  abandoned.   Less
extreme examples occur on a regular basis.
^Tosco Foundation, Siting Major Energy Facilities,  October
t 1979, p. 1.
2D. Linkhart, Western Governors' Policy Office,  "Permitting
 and Siting of Energy Projects," June  1981,  p.  7.

-------
     Naturally, the reasons  for  delay  in  a  project are not all
regulatory.  Projects may be  delayed  for  technical—architec-
tural/engineering—reasons.   In  addition, an  applicant might
postpone a project because it  is  not  economic or does not meet
the company's criterion for  minimum  financial return.  Final-
ly, a project might be delayed because it is  unable to obtain
adequate financing.  Even when the regulatory process is drawn
out, the cause may not be a  duplicative,  cumbersome process,
but legitimate environmental  concerns  or  a  project applicant's
inability or unwillingness to  provide  the necessary informa-
tion.  Nonetheless, the regulatory maze  is  recognized by
industry and government representatives  alike as an important
and controllable factor in the all too frequently lengthy
permitting process.

     Efforts to improve permitting processes  are taking place
at the local, state, and federal  levels.  For many major
projects, the bulk of permitting  requirements occur at the
state level.  This trend will  intensify  with  further delega-
tion of  federal responsibilities  to  states.   Many states have
passed legislation, promulgated  regulations,  or made adminis-
trative  changes to streamline, simplify,  and  coordinate their
environmental permitting processes.
OBJECTIVES

     In order to ensure  that  states  are  aware  of  the success-
ful reforms initiated  by  other  states,  the  Energy Facilities
Branch of the EPA's Office of Policy Analysis  and the Permits
Division of the EPA's  Office  of  Water Enforcement and Permits
undertook a survey of  state environmental permitting reforms.

     Preliminary work  on  the  survey  was  performed by the
Southern States Energy Board, the  Western  Interstate Energy
Board, and the Regulatory Reform Institute.   In  August 1981,
the EPA requested that Temple,  Barker &  Sloane,  Inc. (TBS), a
management and economic  consulting firm  located  in Lexington,
Massachusetts, complete  the survey work  and  prepare a report
summarizing the findings.

     In undertaking this  survey,  the EPA and TBS  concentrated
only on those reforms  that satisfied the following three
criteria:

       •  The reform had  to expedite or  facilitate in a
          significant  way the issuance  of a  permit.

-------
       •  The reform had  to  affect  permits that regulate
          activities that  have  environmental impacts
          (e.g., air,  water,  solid  waste,  and facility
          siting permits).

       •  The reform had  to  affect  some  part of the per-
          mitting process, from initial  permit applica-
          tion  to final administrative approval.
METHODOLOGY

     In conducting  the  survey  TBS  primarily relied on second-
ary sources of  information  and on  telephone interviews with
state officials.  With  respect to  secondary sources of infor-
mation, TBS used numerous recent descriptions or evaluations
of state permitting  reforms  provided  by  either the EPA or the
individual states.   A complete bibliography of the sources
used in the survey  is included at  the end  of this report.

     TBS also held  telephone interviews  with state officials
and asked them  to describe  those reforms they considered the
most important.  Only those  reforms  that were mentioned by
state officials in  the  telephone interviews were included in
the survey.  Not all the reforms,  however,  mentioned by state
officials are included  in Part II  of  this  report; some reforms
did not satisfy the  three screening  criteria mentioned above.
A list of the state  officials  who  may serve as primary con-
tacts for further discussion of  these reforms is included
after each of the state summaries.

     Finally, neither the EPA  nor  TBS undertook an independent
evaluation of the effectiveness  of  the reforms that are in-
cluded in this  report.  Thus,  the  report is a compilation of
those environmental  permitting reforms that the states believe
to be the most  significant,  and  is  not necessarily an evalua-
tion of those that  are  the  most  effective.
KEY REFORMS

     The environmental permitting  reforms  that  have been in-
itiated by the states concern  all  phases  of  the permitting
process, from initial permit application  to  final  administra-
tive approval.  The reforms  include  those  that  have been
adopted pursuant to statutes,  regulations, executive orders,

-------
and informal administrative decisions.   Moreover,  different
states have implemented  variations  of  the same kind of reform
and yet titled it differently.

     In order to help  the  reader  locate  states where similar
procedures have been implemented  and  to  promote consistency in
the state summaries, TBS grouped  the  many permitting reforms
into ten categories of  "key reforms."  These categories are
not intended to exhaustively  define and  differentiate among
the various environmental  permitting  reforms;  new procedures
are constantly being tried and  old  ones  modified.   The cate-
gorization is intended  primarily  as a  reference aid.

     Where relevant, each  state summary  is organized around a
description of the state's implementation of one or more key
reforms.  The key reforms  are  listed  in  the upper righthand
corner of the first page of each  state summary.

     Exhibit 1 presents  a  matrix  of the  ten key reforms imple-
mented by the states and mentioned  in  the survey.   Defini-
tional criteria and relevant  observations about each of the
reforms are set forth  below.
Computer Tracking

       •  The use of a  computer  to  track  a permit appli-
          cation or renewal  or  to monitor compliance with
          a permit that  has  been issued.

     Computerized data  storage  and  retrieval systems are a
recent and rapidly growing management  reform in the public
sector.  Eight states noted  the  significance of systems that
are already in place or  are  currently  being developed.   Typi-
cally these systems are  used as  informational mechanisms to
track permit applications and to monitor  compliance with
existing permits.

     Some states use the computer to  track individual permit
programs, and other states are  developing comprehensive sys-
tems for all their environmental programs.  Kentucky has in-
stituted a Surface Mining Information  System to handle  the
volume of permit applications and to  monitor needs in the
mining area.  Michigan  tracks its dredge  and fill permits to
assure that reviews are  conducted within  special time frames.
Many of the states with  single  permit  programs are examining
the feasibility of adapting  the  system to other programs.

-------
                                                Exhibit 1

                                      MATRIX OF KEY REFORMS
                                      DESCRIBED IN THIS SURVEY

EPA
Region
[y riv
'i ••*% « v%
!>'' #4' $^\
tw;;n>
^ '"«.'
;, $ «? «
'j / < **i
;* * ~iS -~
^ % * ^ M * J&
>,-.>??;
- -'0fA ,
£•' *C- %s ••
r -vk;
- -\v*.
o«- c
\ -f *V.>* v^
- s f ,**
i- , ' ^
A <
?, *:r^.
f r^
> , ••/
k.n - > , v
If ^ 	 J.' 	
Lt
n ,>;,/,
t .. ~ >
L ^;'
,-•
,-••.,
<,' 'X-
% t ~V ffff
'..' •» f
t < f
* ''
> ^
tf-
c
t >
State
Connecticut
Maine
Massachusetts
New Hampshire
Rhode Island
Vermont
New Jersey
New York
Delaware
Maryland
Pennsylvania
Virginia
West Virginia
Alabama
Florida
Georgia
Kentucky
Mississippi
North Carolina
South Carolina
Tennessee
Illinois
Indiana
Michigan
Minnesota
Ohio
Wisconsin
Arkansas
Louisiana
New Mexico
Oklahoma
Texas
Iowa
Kansas
Missouri
Nebraska
Colorado
Montana
North Dakota
South Dakota
Utah
Wyoming
Arizona
California
Hawaii
Nevada
Alaska
Idaho
Oregon
Washington
PERMITTING REFORM
Computer
Tracking























;::::::-:-:'::::::::&::::::x::-







;::::&::::::£:::::::::x:x


















Decision-
Making
Deadlines
!il!lil
8s;3$$ii
mmmM
$Mim?m





:::!:;:;:x:S::iS§:;:?*




g!SSSS?;s$*





lllllii





























Gtmral
Permit







lltlilill










































Joint
Application

«Sfpi$
SSSS^SKS;








mmmm






wSiSg^gjs;


















gSssSSSSSiS





5SSSJS:::¥S?::s
Wmtfmm





Joint
Hearing



%®i$mm&





::x::!:s:::S$S«S$:


































:::::::iv:v:::::::::::::^::::::





Joint
Review*




















•ft'-Vfftifffftttf:
S$5sS$ftW:S
If If III!














Illllllf













One-Stop
Permitting*









SS-sjSwSvS




fj:S;%fl:::j:j:j::^::;:i
SvyixiXxX:::':':^
















5::S:::-¥:¥:©:::::::;x:
xX::::x:::v::::::Xx-::::

















Over-the-
Counter
Processing






11^^











































Permit/
Application
Coordinate

m®8$i%
Piv^sSliSlx::



^
r>



:

















HSSSSSSSS










BJHvx'^x'SSw


l^x^x-vxix-Xv
:|:l:!::x§:-x:x:;:::x;

v.-x:X;:vX;'x ;[x;

jjgxjxfxvxjffil:
X'X'x'x-x'x-xv:':

Site
Inventory/
Banking









,














xSKSS®:

























All joint review and one-stop permitting reforms include joint application and joint hearing.

-------
                               8
More comprehensive computer  systems  are  now being developed in
states such as North Carolina  and  Hawaii.   Hawaii's Permit and
Application Support System  (HPASS) will  include compliance
status data on air, water,  and  waste permits as well as the
state EIS, the A-95 Notification and Review, and other envi-
ronmental requirements.   In  addition,  Hawaii intends to expand
the system to include permit applications  and an environmental
data base.

     Computer systems can also  be  used to  share information
across levels of government.   The  Environmental Protection
Agency's Region II office is arranging with both New York and
New Jersey to share the  EPA  and state  computer data systems.
Decision-Making Deadlines

       •  The use of fixed deadlines  for  administrative action
          or permit application.

          —The deadlines can  be  mandated by  statute,  regu-
            lation, or executive  order.

       •  More strict deadlines than  are  generally re-
          quired by the  state,  usually  by the state's
          administrative procedures act.

          —The intent is to reduce the  total time neces-
            sary to reach a final  decision.

          —Sanctions may or may  not  be  attached  to the
            failure to meet the deadlines.

     Most states have decision-making deadlines  mandated com-
prehensively by a state  administrative  procedures act  or asso-
ciated with individual permits  or  program-specific laws.
However, only 22 states  noted  the  significance of decision-
making deadlines in their environmental  permitting procedures.

     One half of the cases where  deadlines  are described in
this report are for energy siting/permitting  processes.  For
these projects the deadlines to complete  the  decision-making
process range from six months  in  Arizona  to 33 in Montana.

     Typically decision-making  deadlines  date from the time
the application is deemed complete by the permitting agency.
Frequently the deadline  varies, depending on  whether a hearing
is required or not.  In  New York  all  permits  (except for those
for powerplants) must be issued within  60 days of the  last

-------
hearing or, if no hearing  is  requested,  five  days  after a
decision-making conference.   Missouri  has  different deadlines
for "minor" and "major" permits.   Minnesota  is  planning to
require that all permits be issued or  denied  no more than 60
days after the state  EIS has  been  completed.

     In states where  extensions are  readily  available or where
there are  no sanctions attached to failure to meet the dead-
line, the  value of a  decision-making deadline in accelerating
the permitting process may be  compromised.  A few  states, such
as California and Colorado, automatically  grant a  permit if
the agency does not act within a  specified period  of time.
General Permit

       •  The use of one permit  document  for  an  entire
          category of permit applicants.

          —The permit applicants who  are  "covered"  by
            the general permit category are  those  who
            satisfy specified criteria, such  as  certain
            types of dischargers whose rate  of discharge
            is less than a given amount.

       •  The use of a "self-certifying"  permit  in which
          the applicant determines  whether he satisfies
          the specified criteria needed for  issuance of
          the permit.  Such applicants need  not  undergo
          an individual permit review.

          —The self-certification  process imposes legal-
            ly enforceable standards upon  the permit
            applicant.

     Under the EPA's Administrative Guidelines to  the Clean
Water Act, several states have initiated  the  use of  general
permits for certain categories of water dischargers.  This
reform serves both to reduce the burden of administration and
enforcement on the state agencies and  to  relieve small dis-
chargers of time-consuming permit application and  reporting
requirements.  During this survey, Oregon, New York,  and
Wisconsin noted the importance of general permits  for small
dischargers.  All three states issued  their general  permits
during 1981.

     The U.S. Army Corps of Engineers  also issues  "general
permits" for many categories of  projects  requiring dredge and
fill permits under Section 404 of the  Clean Water  Act.   (See

-------
                              10
North Carolina.)  The Corps' general  permit  differs substan-
tially from the general permit  described  above in that Corps
officials determine on a case-by-case basis  whether a project
is covered under the general permit,  and  applicable projects
must still obtain state permits.   Therefore  the key word
"general permit" is not used to describe  the process used by
the Corps of Engineers.
Joint Application

       •  The submission of a  single  application form for
          more than one permit.

       •  The distribution of  the  completed  application
          to more than one agency.

          —The completed application can  be directly
            submitted to all the  relevant  agencies,  or it
            can be submitted to one agency which in  turn
            distributes it to  the  relevant agencies.

          —The agencies that  receive the  completed  ap-
            plication can be federal, state, or local
            agencies.

     Although many states have explored  the  use of joint ap-
plications  for a variety of permits,  they  have later found
certain types of permit combinations  to  be more feasible than
others.  An ever-more-common area  for joint  applications is
the complex of local, state, and  federal (Army Corps of Engi-
neers) coastal and dredge and  fill permits.   Five states noted
the importance of joint applications  in  reducing the duplica-
tive intergovernmental requirements  in this  area.  Joint ap-
plications  are also used for many  energy facility permitting
processes.  Since all one-stop permitting  and joint  review
processes by definition include  the use  of a joint applica-
tion, a separate key word for  joint application is not listed
along with  one-stop permitting and joint review.  However,
many states have instituted energy facility  permit processes
that are not one-stop permitting  but  do  include joint applica-
tions.  In  addition, individual  states have  used joint appli-
cations for specific permit combinations.   For instance,
Alaska uses a joint application  to cover various applications
previously  required by six state  and  three federal agencies to
permit placer mines.  New Jersey  actually  uses one master
permit application for all permits and distributes xeroxed
copies to the different permit programs.

-------
                               11
     Frequently permit coordination  legislation  and descrip-
tions of a permit coordinator's  duties  include  a mandate to
encourage the use of joint applications.   In  most of these
cases joint applications rarely  or never  occurred,  and so a
key word is not listed.  Furthermore,  "joint  application" does
not describe the permit information  forms used  by states such
as Washington and Pennsylvania.   These  forms, often referred
to as master application forms,  are  used  to  identify which
state permits an applicant must  obtain.


Joint Hearing

       •  The participation of more  than  one  permitting
          authority in one hearing.

     Although many states broadly encourage  the  use of joint
hearings, their practice has by  and  large been  limited to
states where agency participation is  mandatory.   Several
states, such as Washington and Maryland,  have established
procedures enabling applicants to request joint  hearings; in
these cases, the practice of joint hearings  has  been limited
only by reluctance on the part of the applicant.   Other states
have routinely incorporated joint hearings into  their permit-
ting processes.

     Several of the states that  mentioned joint  hearings use
this vehicle routinely for energy facility permitting proc-
esses.  As in the case of joint  applications, since all joint
review and one-stop permitting processes  as  defined in this
report include the use of joint  hearings,  a  separate key word
for joint hearing is not listed  along with one-stop permitting
and joint review.  Five states noted  the  use  of  joint hearings
for nearly all their environmental permits.   For  instance,
Washington and Maryland offer applicants  the  option of a joint
hearing for all required permits.  Other  states  use joint
hearings for specific permits or projects.   Illinois,  for
instance, holds joint hearings for major  construction projects
and Michigan holds joint dredge  and  fill  permit  hearings.

     Although many states have attempted  to  institute joint
hearings across governmental levels,  the  reform  has been most
successful at the state level.   In Maryland,  local  agencies
may be invited to participate in hearings with state agencies,
while in Washington local agencies are  required  to  participate
in the coordinated review process and joint  hearing.   Efforts
to combine federal and state agency  hearings  have  not been
widespread.  Except for the state programs categorized under

-------
                               12
"joint review," only the Michigan  dredge  and  fill program
and the Wisconsin mining reclamation  program  were noted as
examples of joint state and  federal hearings.

     Not reflected under the joint hearing  category is an
apparent trend toward  reducing  the total  number of public
hearings required of applicants.   Some  states  noted that they
have successfully streamlined the  permitting  process for small
or noncontroversial projects by  eliminating the public hearing
requirement.  In other situations, the  EPA  and individual
states have coordinated their permitting  process so that only
one agency holds a public  hearing.

     As in the case of joint applications,  permit coordination
legislation or executive orders  often include  a mandate to
encourage the use of joint hearings.   However,  unless agency
participation is mandatory,  combined  hearings  rarely take
place.
Joint Review

       •  An approach  to  coordinating  the  issuance of
          multiple permits  needed  by  a single project.

       •  The involvement of  more  than one government
          agency as  part  of a "team"  in the permitting
          process.

          —The object  is to  include  federal, state,  and
            local agencies  from  which  permits are needed
            on the team.

       •  The coordination  of the  schedule for permit
          applications, permit hearings,  or decisions on
          whether or not  to issue  the  permits.

       •  Written commitment  by  participating agencies  at
          the beginning to  meeting the schedule.

          —There may  or  may  not be sanctions attached  to
            the failure of  an agency  to meet its  written
            commitment  to the schedule.

     Colorado's Joint  Review  Process,  initiated by executive
order in  1978, has served as  the model for subsequent efforts
in three  other states.  State legislatures in Tennessee and
Utah passed joint review  legislation  in 1981, and the governor
of Illinois initiated  a joint review  process through  executive

-------
                               13
order during 1981.  All four programs  apply  to  major projects
in the energy and mineral resources  development area.

     The processes set up in these states  are designed around
the basic concept of a review  team composed  of  representatives
of state, local, and federal agencies  and  the project  appli-
cant.  However, in all these cases local and federal agencies
are not required to participate.  Utah's structure  differs
slightly from that of the other  states  in  that  the  Resource
Development Coordinating Committee,  a  pre-existing  intergov-
ernmental body which conducts  A-95 and  other reviews,  oversees
the process.

     The joint review process  is  designed  to be a  flexible
coordinating reform.  Only applicants  that request  it  and are
designated eligible by the governor  are permitted  under the
joint review process.  The joint  review team is given  consid-
erable planning and enforcement  discretion to arrange  for such
streamlining vehicles as joint hearings, deadlines,  and joint
applications.  Because these reforms are generally  available
under all joint review processes, separate key  words for joint
applications and joint hearings  are  not listed  under joint
review.  The process is intended  to  be  tailored to  individual
project applications.

     Because Tennessee, Utah,  and Illinois initiated their
joint review processes in 1981,  only Colorado has  had  any
experience with the reform.  Seven projects  have applied and
been accepted for consideration  under  Colorado's review proc-
ess.  Utah is the only other state to  have designated  a
project eligible for joint review.
One-Stop Permitting

       •  One administrative process  for all  state  per-
          mits (at the minimum)  involving  both  a  joint
          application and a joint hearing.

       •  One government body that  issues  a permit  or
          permits or that requires  other agencies  to
          issue permits.

          —The government body  can be one agency  or a
            team consisting of a group of  officials from
            several agencies.

          —In some cases, other agencies  can attach
            conditions to the permit  that  is  issued by
            the lead government  body.

-------
                               14
     As defined in this report,  one-stop  permitting processes
exist in eight states.  However,  modifications  of  one-stop
permitting, where many but not  all  of  the criteria described
above are met, occur  in many other  states.   For instance,
Ohio's permitting process for energy  facilities is categorized
under "permit/application coordinator"  and  "joint  applica-
tion," since the process does not include joint hearings and
each agency maintains authority  to  issue  its permit.   Some of
these states may actually label  their  process "one-stop per-
mitting" but fail to  meet the definition  contained in this
report.

     Nearly all one-stop or modified  one-stop permitting proc-
esses apply to major  energy facilities  and  transmission lines.
Specific eligibility  criteria vary  from state to state in
terms of minimum, facility size  and  other  types  of  energy proj-
ect coverage.  A few  states, such as  New  York and  Florida,
have established one-stop permitting  procedures for industrial
facilities.  Connecticut is one  of  the  initiators  of  one-stop
permitting for hazardous waste  facilities.   In  all cases de-
scribed in this report, except  for  Florida's industrial one-
stop permitting process, project  applicants are required to
use the process.

     The decision-making structure  also differs across states.
In many states, such  as Arizona  and New York, a special siting
council composed of state and local agency  representatives
decides whether to grant the applicant  the  requested  permit.
In Florida, the governor and his  cabinet  make the  certifica-
tion decision.  Maryland's Public Service Commission  has final
authority over powerplant permitting.   Local permits  and agen-
cies are typically included in  the  one-stop permitting proc-
ess, although state power to override  local decisions varies
among the states.  Nearly all the states  have deadlines for
their one-stop permitting processes,  but  the time  frames range
from six to 24 months.

     Since nearly all the energy  facility one-stop permitting
programs were first developed in  the  early  1970s,  this reform
has been well tested.  Most states  have certified  at  least
three or four major facilities  under  this reform.

     To generalize, one-stop permitting has not necessarily
resulted in accelerated permitting  of  facilities.   Instead,
the process seems to  have provided  states a forum  for compre-
hensively assessing proposed projects  and integrating these
decisions into long-range plans.

-------
                               15
Qver-the-Counter Processing

       •  Permit application,  permit  review,  and  permit
          approval occurring on  the  same  day  and  at the
          same place.

          —A preapplication discussion  (often  a  tele-
            phone conversation)  between  the applicant and
            the relevant agency  can  occur at  any  time
            before the one-day processing.

          —Over-the-counter processing  applies to  minor
            permits.

     Although only New Jersey  made mention of this  reform,  it
has proved very helpful to small  project  applicants.
Permit/Application Coordinator

       •  Any one of a series of  coordination  functions,
          including the  following:

          —Master application  or  permit  information  form

          —Mediation services

          --Permit directories

          —Permit expediters

          —Permit information  centers

          —Preapplication conferences

     This term covers a  broad range of  reforms  initiated  in
over half the states.  Four states noted  the actual existence
of a predesignated individual titled  "permit coordinator," and
four states assign individual coordinators  on  a project-by-
project basis.  In other states, a department,  committee, or
task force might oversee one or more  of the coordination
mechanisms listed above.

     The permit/application coordinator reform  may apply  to a
variety of permits or projects.  Seventeen  states, including
Connecticut,  Rhode Island, and Michigan,  described procedures
that apply to all their  environmental permits.   The term  is
also used to describe facility permitting processes in  states

-------
                               16
such as Ohio and Massachusetts which  do  not  meet  all  the cri-
teria of one-stop permitting but  are  highly  coordinated.
Hawaii, Maine, and Vermont coordinate their  land-use  permits,
while other states' procedures apply  to  dredge  and  fill  per-
mits, construction projects, or  "priority" projects.   Many
states have attempted to coordinate  the  local or  federal per-
mitting process.  These efforts  have  succeeded  more in the
informational area than in the application,  review,  and
decision-making stages (excluding  the Corps' dredge and  fill
permits).

     Typically the reform is aimed at "coordinating"  the per-
mitting functions of many agencies so that project  sponsors
may submit their applications and  receive  responses in a con-
sistent and timely fashion.  Pennsylvania's  regional  system
and Ohio's energy siting process  are  examples of  coordinated
systems.  Several state reforms  are  aimed  at "expediting"  a
project through the permitting process,  such as Kentucky's
proposed priority application procedure  and  New Jersey's pool
of permit expediters.  Yet, increasingly,  it is the "informa-
tional" reform that states and industry  are  finding most use-
ful.  Washington, Maryland, and  Hawaii have  established  a
variety of mechanisms to help both agencies  and applicants
learn more, earlier, about issues  associated with the project
review and permit application requirements.
Site Inventory/Banking

       •  The identification  of  an  inventory of  sites for
          specific  types  of  facilities  by  a state agency
          using preselected  criteria.

          —The agency  can either  identify the  site or
            actually  purchase ("bank")  it.

     Although several states  have  explored the  concept of site
inventories or banks  for  guiding the  location of new major
energy facilities,  only three states  noted actual use of this
reform.  Minnesota  has  limited  the  scope  of its  inventory to
broad-corridor recommendations  for  powerplant facilities.
Illinois has  issued broad area  maps identifying  suitable areas
for coal gasification and synthetic fuels  facilities.  Mary-
land, however, with separate  financing  from a surcharge on
electricity production, actually "banks"  specific powerplant
sites for future  sale to  utilities.  Although early designa-
tion of site  criteria and areas  for utility development is
intended to facilitate  the permitting process,  this reform has
often proved  too  complex  to  implement.

-------
                               17
OBSERVATIONS CONCERNING STATE  PERMIT  REFORMS

     The primary conclusion  that  can  be  drawn  from the survey
of state environmental permitting reforms  is that there is not
an "ideal" reform which should be adopted  by all  states for
all projects.  Not only do states have  varied  needs and con-
cerns which are the impetus  for permit  reform,  but different
states have had contrasting  experiences  with similar types of
reform.  Outlined below are  some  observations  concerning how
state reforms differ  in terms.of  their  objectives, benefits
and costs, applicability  to  different industries  or projects,
manner of initiation, and flexibility in implementation.  Two
final sections address the issue  of regional differences and
provide examples of intergovernmental coordination.
Objectives of the Reforms

     Procedural permit reforms  are  designed  to  serve a variety
of objectives and are a  result  of many  different  concerns.
Some reforms increase public  involvement  and governmental
oversight, some improve  intergovernmental coordination,  others
reduce duplicative or burdensome requirements,  and  others
improve the information  flow.   Most,  however,  are ultimately
intended to expedite the permitting  process.

     Some reforms are aimed mainly  at improving public in-
volvement and/or governmental oversight of  a project.   With
the fragmentation of regulatory authority across  many  agen-
cies, states have found  that  issues  have  "fallen  between the
cracks" or that project  approvals have  occurred without  regard
for long-term planning needs.   Examples of  reforms  directed at
this problem are the various  types  of energy facility  siting
commissions found throughout  the country.

     Reforms may also be aimed  at improving  the coordination
between state agencies or agencies  across governmental levels.
Problems of inefficiently used  resources,  jurisdictional
ambiguity, or conflicting time  frames may all  be  the impetus
for these kinds of reforms.   To this  end,  permit/application
coordinators serve to clarify requirements  for  an applicant,
improve communication between the applicant  and agencies, and
reduce the amount of overlays and conflicts  between agencies.

     Some reforms are specifically  designed  to  eliminate du-
plicative requirements which  strain  applicants'  resources.
Joint hearings and joint applications are examples  of  this
type of reform.

-------
                               18
     There is an increasing awareness  of  the  unfair regulatory
burden placed on small project  applicants,  and  a number of
procedural mechanisms have been  implemented to  address this
issue.  General permits  for classes  of activities and one-day
over-the-counter processes are  good  examples  of this type of
reform.  Many states have also  instituted  ad  hoc procedures to
expedite "minor" projects and/or  have  eliminated their public
hearing requirements for uncontested,  small projects.

     Informational mechanisms directed at  reducing the uncer-
tainty for applicants and agencies alike  are  rapidly increas-
ing in use.  Most states offer  preapplication conferences
where applicants can learn about  permit requirements and ex-
plore issues early on which might arise later in the permit-
ting process.  Permit directories are  published in most states
and several states have  taken advantage of  permit centers and
computer tracking of permits to  serve  both  applicants'  and
agencies' information needs.

     Finally, there are  reforms  that are  solely intended to
expedite the permitting  process.  Decision-making deadlines
are frequently imposed on permitting agencies in order to
ensure that agencies are not dilatory.  Some  states,  anxious
to encourage specific types of  development,  have set up spe-
cial task forces to expedite the  permitting process for these
projects, and certainly  many of  the  reforms described earlier
are intended to ultimately result in a more efficient,  coor-
dinated, and faster permitting  process.
Benefits and Costs of the Reforms

     The benefits and costs of  these  reforms  are  not always
apparent.  While in many cases  the  state  officials  can point
to such records as the  total  reduction  in permitting time or
the smaller number of hearings  required,  in other cases,  where
the benefit is greater  satisfaction on  the part of  the appli-
cant or improved communication,  such  quantification is diffi-
cult.  This is especially true  for  the  informal reforms such
as preapplication conferences and permit  coordinators.

     Moreover, the benefits for  agencies  and  applicants are
not always the ones primarily anticipated.  For instance, the
Colorado joint review process (CJRP), designed  to coordinate
agency and applicant actions  and improve  the  public participa-
tion process, also helps the  state  by explicitly  identifying
the source of delay in  the permit process.  Where previously
the government was normally seen as the scapegoat for permit-
ting delay, under the CJRP, where the responsibilities of all

-------
                               19
parties are specified  in agreements,  the  source of any delay
is clear.  Often, the  project  applicant  is  responsible for the
delay.

     Finally, many of  the permit  reforms  clearly present
tradeoff situations.   A tradeoff  occurs  when  several steps in
a permitting process are eliminated  so  that decisions are
expedited, yet agencies' decision-making  capabilities are
reduced and issues may "fall through  the  cracks."  In other
situations, more agencies are  involved  at more steps in the
process, which may be  more burdensome,  yet  decisions are made
more deliberately.
Industry/Project Differences

     Permitting reforms also differ  in  their  application to
specific projects or  industries.   Over  time,  certain types of
projects have experienced more  attention  in  the  area of permit
reform.  Throughout the 1970s,  many  states  enacted  legislation
governing the permitting of powerplant  facilities.   Emphasis
in this area may have been due  to  such  factors  as  the indus-
try's history of regulatory control,  recognition by the public
and legislatures of the need for comprehensive  energy plan-
ning, and the increased interest of  local communities in de-
termining and understanding the environmental  impact of new
facilities.  Later, as other sorts of energy  projects en-
countered permitting  delays and as concern  for  national energy
self-sufficiency grew, several  states amended  their legisla-
tion to include a broader scope of projects  such as coastal
refineries, pipelines, and mines.  Currently,  in the wake of
federal RCRA legislation, more  states are passing  hazardous
waste facility siting legislation.

     Naturally, the characteristics  of  the  reforms  vary de-
pending on the type of project  affected.  Both  the  powerplant
and hazardous waste facility processes  are  oriented toward the
siting of facilities, although  some  of  the  processes cover all
permits required for  construction  of a  facility,  while others
only address the siting question.  Intergovernmental coordina-
tion between local and state agencies nearly  always character-
izes these reforms.   Frequently, a siting committee,  composed
of representatives from all affected state  and  local agencies,
is responsible for coordinating the  process.  The objective of
long-term planning often supersedes  any objective of expedited
permitting with these kinds of  reforms.

     Permit reforms applicable  to  non-energy  industrial devel-
opment have tended to be implemented less formally  and on a

-------
                               20
voluntary basis.  A few states  have  enacted  siting  legislation
for such development, but  for  the  most  part  these  reforms
cover a range of less formal processes  aimed at  coordinating
agency action, improving the information  flow,  and  expediting
the process.

     In addition to industry distinctions,  many  states have
implemented reforms specifically  for "minor" or  "major" proj-
ects.  Some states have found  that  imposing  the  same require-
ments on projects of all sizes  is  too  burdensome for both the
agencies and  the applicant.  They  have  instituted  reforms to
expedite or eliminate requirements  for  "minor"  projects.
Other states  are developing processes  to  accommodate speci-
fically the numerous permit requirements  of  a "major" project.
Ad hoc permit expediting committees  or  joint review processes
are examples  of this type  of reform.
Statutory, Regulatory, or
Administrative Initiative

     States have initiated  their  permitting  reforms  through a
variety of mechanisms.  Many  states  have  passed  legislation to
implement their processes;  other  states have issued  regula-
tions implementing existing statutes.   In some  states the
governor has issued an executive  order  for a reform,  and in
others the reform has evolved  out of changes in  administrative
practice.  The benefits and drawbacks of  each of these types
of initiatives vary from state  to state.   Some  state  officials
believe that legislation restricts  the  agencies  to cumbersome,
rigid procedures.  In other states  the  legislation is flexible
enough to accomplish regulatory  reform  and additionally pro-
vides the authority to ensure  a  stable  funding  source and to
enforce the reform.
Flexibility of the Reform

     There is a distinct trend  in  the  nature of  permit reforms
toward an  increased  emphasis  on  informal,  flexible procedures.
Whereas much of the  siting  legislation passed during the 1970s
prescribed rigid  procedures  for  permitting,  the  more recent
experiments with  joint  review are  flexible and rely on volun-
tary cooperation.  Several  states  that passed permit coordi-
nation legislation in  the mid-1970s  have  abandoned the formal
procedures laid out  in  the  statutes  and use permit coordina-
tors in a  more informal manner.   State officials cite several
reasons for this  trend, including:   court  challenges to formal

-------
                               21
procedures, evidence  that  new  reforms  are  even  more time-
consuming than the previous  process, and  industry criticism of
formal procedures.

     However, many officials also  commented  on  the problems
associated with the more flexible,  informal  procedures such as
permit coordinators.  There  is a possibility that the success
of many of the reforms  is  dependent  on the abilities of the
individuals in charge.  If the individual  is not  effective,
neither is the reform.
Regional Differences

     Although it is difficult  to  discern  clear  regional  dif-
ferences in permitting reforms, some  regional  differences do
seem to correspond to the  type and  level  of  industrial  devel-
opment.  For instance, many of the  heavily  populated,  indus-
trialized Northeastern and Middle Atlantic  states  have  estab-
lished informal permit coordinators.   These  permit coordina-
tors are very helpful to a large  volume of  not  very compli-
cated projects.  In contrast,  several  of  the western states
with a great deal of new energy development  have created
formal joint review and facility  siting processes  which  are
best applied to only a few major, complicated  projects.
Finally, the sparsely populated states with  little energy or
industrial development presumably have little  need for  envi-
ronmental permitting reforms and, as  a consequence,  have
initiated relatively few reforms.
Intergovernmental Coordination

     A pressing need in the area of permit  reform  today  is  for
more effective intergovernmental coordination.   As  both  the
local and state agencies develop greater analytical  and  deci-
sion-making capabilities and as states assume  a  larger  role in
the environmental review process,  the problem  of jurisdiction-
al conflict has grown.  Moreover,  many state officials  noted
that differing federal and state statutory  deadlines  pose a
major obstacle to their efforts to streamline  the  review proc-
ess.  For the applicant this may mean confusion  over  permit
requirements, duplicative demonstrations of compliance,  and
lengthy review times.  For the agencies this may mean agency
conflicts, wasted efforts, and inadequate environmental
review.

-------
                               22
     State, federal, and local agencies  are  coordinating their
efforts in a wide range of ways.   A  common practice  between
state and federal agencies is to  sign a  Memorandum of  Under-
standing (MOU) or Agreement  (MOA)  which  describes mutually
agreed-upon coordinating procedures  and  jurisdictional bound-
aries.  Several states have  established  state/federal  task
forces to explore new ways to coordinate their  efforts.
Annual state/EPA Agreements  (SEAs) often include  goals for
coordinating state and regional EPA  agency efforts.  The
Department of the Interior has worked with several states to
combine EIS procedures.  The U.S.  Army Corps  of Engineers dis-
trict offices have established an  assortment  of agreements
with state agencies to combine applications,  hearings,  and
review procedures for projects requiring permits  from  both
levels of government.  Many  states have  designed  one-stop and
joint review processes where local and/or federal participa-
tion is encouraged.

     One major distinction between intergovernmental and state
agency coordination processes is  the general  absence of  en-
forceability of the former and therefore its  heavy reliance on
a spirit of cooperation.  This is  especially  true for  state
efforts to include federal review  agencies.   While some  states
have legislatively given themselves  pre-emptive authority over
local siting decisions, they are  generally reluctant to  use
this power.

     The success of these intergovernmental  efforts  varies
from state to state.  While  many  states  cited the federal/
state/local interface as their most  difficult problem,  other
states commented on an excellent  relationship between  the
various governmental levels.

-------
PART H:  STATE SUMMARIES

-------
OVERVIEW

     There is no formal consolidation of state permits in
Alabama.  Separate boards and commissions process state and
federal permits in the categories of air, water, solid waste,
drilling, mining, etc.

     Over the last few years, similar versions of a bill have
been introduced in the state legislature to consolidate envi-
ronmental management and permitting into one agency, the
Department of Environmental Management.  Department of Public
Health staff indicate that they expect passage of the bill
within a couple of legislative sessions.

     Water Improvement Commission staff are considering a
proposal to issue general permits for 11 categories of dis-
chargers.  They believe that the use of general permits will
effect significant savings in personnel time.
STATE CONTACTS

W. T. Willis, Director
Environmental Health Administration
Department of Public Health
State Office Building, Room 328
Montgomery, Alabama  3G130
(205) 832-3176

James W. Warr, Director
Water Improvement Commission
State Office Building
Montgomery, Alabama  3G130
(205) 277-3630

-------
                                           Permit/Application Coordinator
                                                        Joint Hearing
                                               Decision-Making Deadlines
                                                     Joint Application
OVERVIEW

     Alaska has established  permit information centers in
several locations  to  disseminate to interested parties infor-
mation about permits  required,  qualifications for such per-
mits, application  procedures,  and state contacts.  These cen-
ters serve as an initial  intermediary between applicants and
the regulators.  Additionally,  a coordinated review process,
which includes a consolidated  preapplication form, issuance of
joint public notices,  and joint hearings,  is available to any
applicant.  This review,  however,  is limited in scope and
applies only to certain environmental permits.  Finally, a
master application  is  required  for the permitting of placer
mines.
PERMIT/APPLICATION COORDINATOR

     Alaska has established  three  permit information centers—
in Anchorage, Fairbanks,  and Juneau—which offer a variety of
information about local,  state,  and federal permits.  The
centers both provide  potential applicants information on per-
mits required for specific projects and give them the names of
specific regulatory agencies.   The centers function as clear-
inghouses for the master  application and joint review proc-
esses as well.

     The centers were  created  by the Department of Environ-
mental Conservation (DEC) in response to a legislative mandate
to "establish an opportunity for members of the public to
obtain information pertaining  to requirements of federal,
state, and local law  which must  be satisfied before under-
taking a project in this  state"  (Environmental Procedures

-------
Alaska                        28
Coordination Act, A.S. § 46.35).  This legislation was
modeled, with minor adjustments, after the Washington Environ-
mental Coordination Procedures Act.
Permits/Agencies Affected

     The centers provide information on all state and  federal
permits, not solely environmental permits.  Generic  informa-
tion on local permitting is available, but the variation among
local practices makes it impossible to catalog specific
requirements.
Administrative Process

     After the applicant furnishes a description of the pro-
posed project, the center will identify the agencies with
jurisdiction; the federal, state, and local permits that may
be necessary; and the appropriate contacts.  To facilitate
this effort, the DEC has compiled a permit directory and lists
of permits required for specific types of projects.  The
centers also function as the clearinghouse for master applica-
tions and the joint review process.  Toll-free telephone
service with these centers is available throughout the state.
Experience with the Reform

     The permit information centers are heavily used, receiv-
ing hundreds of calls per month.
JOINT HEARING, PERMIT/APPLICATION
COORDINATOR, AND DECISION-MAKING
DEADLINES FOR SPECIFIED STATE PERMITS

     A coordinated review of certain state permits is avail-
able to any project requiring multiple state permits.  The
process includes a master preliminary application, coordinated
notice activities, and joint hearings.  These procedural
measures were authorized in 1977 by the Environmental Proce-
dures Coordination Act (A.S. § 46.35).  The use of this proc-
ess is voluntary, and any project requiring two or more
permits is eligible.

-------
                              29                         Alaska
Permits/Agencies Affected

     The Environmental Procedures  Coordination  Act  specified
34 environmental permits issued  by the  departments  of Environ-
mental Conservation, Fish and Game,  Natural  Resources,  and
Transportation and Public Facilities which must be  considered
in the coordinated review process.   This  list  includes  many  of
the major state environmental permits,  such  as  air  and  water
pollution, land use, and mineral extraction.   All other
permits issued by these as well  as the  other  state  agencies
are included in the process.  Local  and federal authorities
may, at their optidn, be represented at the  hearings.
Administrative Process

     The process is initiated when  the applicant  files  a  sin-
gle preliminary application with the Department of  Environ-
mental Conservation through the permit centers.   The  DEC  cir-
culates the application to the other eligible  agencies, which
must determine within 15 days whether permits  are required.
If an agency has a negative response or  fails  to  respond
promptly, it cannot subsequently require  permits.   When these
determinations are complete, the permit  center distributes the
necessary application forms to the  developer.  Upon filing of
the necessary forms, the participating agencies issue a joint
public notice and hold joint public hearings if any agency
deems hearings necessary.

     Each state agency having an application for a  permit must
be represented at the hearing.  A DEC hearing  officer chairs
the hearing, but representatives from the other agencies  con-
duct the portions of the hearing relevant to their  jurisdic-
tions.  Following the hearing, decision  deadlines (usually 90
days or less) are established by the DEC.  No  state permit may
be issued under the Environmental Procedures Coordination Act
unless the applicant can demonstrate that all  necessary local
permits or certifications, if any, have  been received.  The
individual state permits are then issued  through  the permit
center.

     If an applicant desires,  he or she may use only the  first
stage of this coordinated review process.  In  such  a case the
applicant files the preliminary application.   The DEC then
lets the applicant know what state permits are required and
furnishes him or her with the necessary application forms.
The applicant then follows the standard permitting  procedure
required by each of the various state agencies.

-------
Alaska                         30
Experience with the Reform

     The coordinated review process  has  not  been used exten-
sively since it was instituted  in  1977.   Twenty applicants
have entered the process, but only one has  chosen to partici-
pate in the optional joint hearings.
JOINT APPLICATION FOR PLACER MINES
                                           «
     Alaska has consolidated the  applications  for state per-
mits relating to placer mines  (operations  which collect
minerals from sand or gravel deposits  by washing or dredging).
The use of the master form  is  required of  all  placer mine
applicants.  This practice  was  adopted by  voluntary agreement
among the state agencies.   This form  replaces  the various
forms previously required by the  six  state and three federal
agencies participating in the  program.
Permits/Agencies Affected

     The consolidated application  is  used  for state permits
required for placer mining,  including water permits,  land-use
permits, and mining licenses.   The federal  agencies—EPA,  BLM,
and USFS—accept this application  as  their  annual report and
plan of operation.  The  local  reviews are  independent.
Administrative Process

     The applicant submits a  single  application to the permit
center, which forwards  the application  to  the interested agen-
cies.  The agencies  conduct their  reviews  independently.
Experience with the Reform

     In  1981, over 600  master  applications  were filed and
processed, covering about 2,000  placer  mine claims.   A DEC
official  noted that despite  problems  in 1980—the first season
that master  applications were  used—the program was  well re-
ceived in  1981.

-------
                             31                        Alaska
STATE CONTACT

Woody Angst, Permit Coordinator
Department of Environmental Conservation
Pouch 0
Juneau, Alaska  99811
(907) 465-2670

-------
                                                   One-Stop Permitting
                                               Decision-Making Deadlines
OVERVIEW

     The Arizona Power Plant and  Transmission  Line  Siting
Committee conducts a one-stop  permitting  process  for  all major
electric utility facilities.   The process  includes  a  master
application, joint hearings, and  a review deadline.   If the
committee approves an application for  an  electric utilitv
facility, it issues a Certificate of Environmental  Compati-
bility, which is the only state authorization  required.

     In addition, Arizona has  within the  Office of  Economic
Planning and Development a  liaison service which  aids develop-
ers in identifying the state and  local  regulatory requirements
for projects contemplated around  the state.
ONE-STOP PERMITTING AND DECISION-
MAKING DEADLINES FOR MAJOR
ELECTRIC UTILITY FACILITIES

     The one-stop permitting process of  the  Arizona  Power
Plant and Transmission Line Siting Committee is  mandatory for
all new powerplants with capabilities over 100 megawatts  and
transmission lines over 115,000 volts.   The  committee,  com-
posed of eleven state agency representatives and seven  public
members appointed by the governor, conducts  a joint  review in
which all interested state and local authorities participate.
If the committee approves a project, it  issues a "Certificate
of Environmental Compatibilitv" (Ariz. Rev.  Stat.  Ann.
40-360.01 et seq.).  The certificate is  the  only state
authorization needed by the utility; no  additional approvals
from state agencies are required, though the agencies do
retain authority to attach conditions to the certificate.

-------
Arizona                       34
Permits/Agencies Affected

     Although the certificate is the only  state approval
necessary for eligible projects, and no other  permits  are
required, the committee must ensure that all state  regulatory
requirements are met.  State permit requirements  that  must  be
satisfied include those affecting air pollution,  wastewater
discharge, water use, solid and hazardous  waste,  and  land
use.

     Local authorities may participate in  the  joint proceed-
ings in order to present any objections to a proposal.  Al-
though local ordinances must ordinarily be  met, the committee
can override local restrictions deemed unreasonably restric-
tive.  The ability of local regulators to  halt a  project in
this process has not been tested.  There has been no  signifi-
cant federal participation in the process.
Administrative Process

     In order to initiate the one-stop permitting process,  a
utility files a master application with  the  siting  committee.
The application is forwarded to  the relevant  state  and  local
authorities, and a joint hearing  is scheduled.   At  the  close
of the evidentiary hearings, the  state agencies  with  jurisdic-
tion must inform the committee of any restrictions  or condi-
tions to be attached to the certificate.  The committee's
criteria for reviewing applications are  consistency with
Arizona's environmental and economic goals and compliance with
state and local regulatory requirements.

     Ten favorable votes in the  18-member committee are neces-
sary for a project to be approved.  A decision,  whether favor-
able or unfavorable, must be made within 180 days of  the fil-
ing of the application.  Any of  the participants in the pro-
ceeding may, within 15 days of the decision,  file an  appeal
with the Arizona Corporation Commission.
Experience with the Reform

     The statute was adopted  in August  1971.   There  have  been
57 applications under  this program  in the  past ten years.
Although the great majority of these have  been for transmis-
sion line projects, the applicants  have  included  one nuclear
plant and one coal plant.  None of  these applications  has  been
denied.

-------
                               35                       Arizona
STATE CONTACT

Torn Prose
Assistant Attorney General
Arizona Attorney General
1700 West Washington
Phoenix, Arizona  85007
(G02) 255-3562

-------
OVERVIEW

     There is no consolidation of state permits in Arkansas.
However, all environmental permit programs are administered bv
one agency, the Department of Pollution Control and Ecology.
This organizational structure facilitates communication among
the permitting program staffs.  A Commission of Pollution
Control and Ecology officially makes all permit decisions
(except those concerning water quality, which has been dele-
gated to the department's water division), and department
staff administer the programs.

     In the past, Arkansas has experimented with using a proj-
ect manager to coordinate the environmental permitting of
large projects.  This approach has been dropped because of
insufficient staffing.

     The department may hold preapplication conferences for
large projects requiring multiple permits.  Representatives
from each of the permit programs will get together with the
applicant to discuss permit requirements.
STATE CONTACT

John Ward, Manager
Permits Branch
Department of Pollution Control and Ecology
8001 National Drive
Little Rock, Arkansas  72205
(501) 562-7444

-------
                                            Permit/Application Coordinator
                                                      Joint Application
                                                Decision-Making Deadlines
OVERVIEW

     California's major  reforms  in permitting result from two
state laws, the Warren-Alquist Act passed in 1974, and A.B.
884 passed in  1977.   The Warren-Alquist Act establishes a
coordinated and expedited procedure for the siting of large
powerplants and transmission  lines.  The other law, A.B. 884,
sets deadlines for  permit review and mandates information
exchange among agencies.  A.B. 884 applies to construction and
development projects  of  all  types other than those covered by
the Warren-Alquist  Act.

     To assist in implementing both laws,  California has es-
tablished the Office  of  Permit Assistance (OPA) as part of the
state Office of Planning and  Research.   The OPA provides ap-
plicants with  information such as the California Permit Hand-
book and arranges preapplication conferences and coordinated
reviews.

     Finally, at least one attempt was  made to inventory sites
desirable for  industrial development in the San Francisco Bay
Area.  The Association of Bay Area Governments (ABAC) per-
formed this study in  cooperation with the state.  Although a
report was issued,  it has not had much  impact on development
decisions, according  to  a government official who helped pre-
pare the report.

-------
California                    40
PERMIT/APPLICATION COORDINATOR,
JOINT APPLICATION, AND DECISION-
MAKING DEADLINES FOR MAJOR
ENERGY PROJECTS

     The Warren-Alquist Act establishes  what  may be termed a
modified one-stop siting process  for  thermal  powerplants gen-
erating more than 100 megawatts and  their  associated trans-
mission lines.  The procedure  is  not  described  here as one-
stop because it is a coordination of  individual agencies that
make separate reviews under time  deadlines.
Permits/Agencies Affected

     The process encompasses  all  the  state  air,  water,  and
solid waste permits  issued  for  a  facility.   If federal  agen-
cies' must approve a  project,  their  participation is invited
but cannot be required by the state.   The  state  Energy  Com-
mission issues the final certification,  which incorporates all
the state agency reviews.   However,  an applicant must receive
an additional permit  (the Certificate of Public  Convenience
and Necessity) from  the state Public  Utilities Commission
(PUC), which holds its review separately from the Energy Com-
mission .
Administrative Process

     The California Energy  Resources  and  Conservation Commis-
sion (Energy Commission), created  by  the  Warren-Alquist Act,
oversees a two-stage  process  for applicants  proposing energy
facilities.  First, the  applicant  files a Notice of Intention
(NOI) which provides  the Energy Commission,  other agencies,
and  the public with early information about  a project.   The
Act  specifies that information about  the  size and location of
the  facility be  included, along with  predictions of its econo-
mic, social, and environmental impacts.   The sponsor must
include at least three alternative sites  for the project.  The
Energy Commission acts as the coordinating agency,  sending
copies of  the NOI to  relevant federal,  state, and local agen-
cies and citizen groups. The Energy  Commission holds infor-
mal, nonadjudicatory  hearings on the  NOI  while conducting its
own  researbh on  the proposal. Unless the Energy Commission
and  the sponsor  agree on a  time extension, the commission must
issue its  decision on the NOI within  12 months of its submis-
sion.

-------
                               41                   California
     If the commission approves  the NOI,  the applicant  pro-
ceeds to the second phase, which  is to  file  the  Application
for Certification (AFC).  The AFC is distributed  to  local,
regional, state, and federal agencies interested  in  the
project for their review and input.  At this stage,  specific
sites are identified, and in-depth studies by  the commission
in cooperation with the sponsor  are begun for  the environ-
mental impact statements required by state and federal  law.
The Energy Commission acts as the lead  agency  in  preparing the
environmental impact report (EIR) required under  California's
Environmental Quality Act (CEQA).  Where a federal EIS  is re-
quired, the commission attempts  to coordinate  state  and
federal efforts by consolidating  the information  and  hearings
required for both documents.  Although  the Energy Commission
takes lead responsibility for the EIR,  it sends  out  informa-
tion on the project to other state agencies  like  the  Air
Resources Board and Water Resources Board, which  make their
own independent reviews, just as  they would  if they  were
issuing PSD permits or NPDES permits separately.

     The Energy Commission holds  additional  nonadjudicatory
and evidentiary hearings on the  AFC during this  second  phase.
Other state or federal agencies  may hold their own hearings as
part of their review.  All the agencies must submit  their
findings to the Energy Commission, which then  decides,  within
18 months of the filing of the AFC, whether  to issue  certifi-
cation.  Since geothermal plants  have been given  a priority by
the legislature, the commission  must rule on their AFCs within
12 months of filing.  When the AFC is issued,  it  takes  the
place of individual approvals by  the state agencies.  The
Energy Commission has authority  under the Act  to  override
other state and local ordinances  and decisions,  but  the courts
have construed this to require the commission  to  give substan-
tial deference to local government opinions  and  laws.   The
Energy Commission does not have  the legal authority  to  over-
ride federal requirements, even  in cases where the state has
been delegated the program.  In  practice such  conflicts do not
usually arise, since the process  incorporates  the views of
other state and federal agencies  into the review  process.

     In addition to receiving the AFC,  if the  facility  is in-
vestor-owned (nonmunicipal), the  applicant needs  to  obtain a
Certificate of Public Convenience and Necessity  from  the PUC.
The PUC's review concentrates on  financial,  rate,  and reli-
ability concerns, as opposed to  the Energy Commission's review
which one staff member described  as a "site  review."

-------
California                    42
Experience with the Reform

     Since passage of  the Warren-Alquist  Act eight plants have
been sited through the  process.   Seven  of these were geother-
mal plants and one was  a coal  gasification plant.   Staff from
the Energy Commission  believe  that  the  process works well,
significantly reducing  time  and  paperwork.
DECISION-MAKING DEADLINES
FOR DEVELOPMENT PROJECTS

     A.B. 884 sets  deadlines  for  agency  review and decisions
on development projects.   "Development"  is defined broadly to
include placement or  erection  of  any  structure,  waste dis-
charge or disposal, mining,  grading,  dredging, or changes in
the density or intensity of  land  or water use.
Permits/Agencies Affected

     A.B.  884 applies  to all  state  agencies issuing permits
except the  Energy  Commission,  which falls under the jurisdic-
tion of  the Warren-Alquist  Act.
Administrative  Process

     Under  A.B.  884  the  Office  of  Permit Assistance (OPA) in
the Office  of Planning and  Research (part of the executive
branch) oversees  the deadlines  and reporting requirements of
the law.  The law requires  the  lead agency for a project to
approve or  disapprove the project  within one year of the re-
ceipt of  a  completed application.   The lead agency is the
agency which under the California  Environmental Quality Act
takes primary responsibility  for determining whether an EIR is
necessary or for  issuing a  negative declaration.  Other agen-
cies that also  must  comment or  issue a permit for the project
must act  within 180  days after  the lead agency has made a
decision, or within  180  days  after the application is com-
plete, whichever  is  longer.  Furthermore, the Act specifies
that if a permitting agency fails  to act on the application
within the  given  time limit,  the permit is automatically
approved.

-------
                                                    California
     When requested by an applicant  or  an  agency,  the OPA may
designate lead agencies and assist  in determining  the respon-
sibilities of other agencies.  OPA  staff often  arrange confer-
ences for applicants with agency  personnel and  can informally
mediate disputes that arise.
Experience with the Reform

     OPA staff report that  the procedures  under  A.B.  884 re-
sult in the staff's receiving information  on  several  thousand
projects per year, of which  they actively  participate in about
three to four hundred.  One  staff  member commented  that after
working through some initial start-up  problems,  the procedure
had expedited permitting a  great deal.  He did  not  feel that
requiring more consolidation in the  form of joint  hearings was
time effective or cost effective.  According  to  him it is
difficult to gather decision makers  on  all aspects  of a pro-
ject together in one place,  and their  concerns  are  so varied
as to make one large hearing counterproductive.
STATE CONTACT

Kent Fickett, Permit Coordinator
Office of Permit Assistance
Office of Planning & Research
1400 Tenth St.
Sacramento, California  95814
(916) 322-2318

-------
                                                         Joint Review
                                                Decision-Making Deadlines
OVERVIEW

     Colorado has established  the  Joint Review Process for
Major Energy and Mineral  Resource  Development Projects.  The
joint review process  is a mechanism for coordinating project
review and schedule among local,  state,  and federal regulatory
agencies.  The process was established administratively in
1978 and has served as a  model  for similar efforts in Illinois
and Tennessee.  In a  related effort,  the Colorado Department
of Natural Resources  publishes  the Colorado Permit Directory
for Energy and Mineral Resource  Development,  which is updated
twice a year.

     Colorado law prescribes strict review and decision-making
deadlines for all state air permits,  NPDES wastewater permits,
and regular mining permits.
JOINT REVIEW PROCESS FOR  ENERGY
AND MINERAL DEVELOPMENTS

     Colorado's joint  review  process  is  initiated by the proj-
ect applicant.  It  is  designed  to  bring  the applicant and the
public together at  an  early stage  in  the development of a
project in order to accomplish  four  goals:   (1) to determine
all applicable regulatory  requirements;  (2) to define agency
and applicant responsibilities;  (3)  to specify a schedule for
the various regulatory activities  and proceedings; and (4) to
enhance and improve public participation in governmental
decision making.  The  process does not alter the substantive
requirements or procedures of any  agency.   Rather, the process
fosters early and constructive contact between the regulator
and the applicant.  This  contact  in  turn results in more

-------
Colorado                      46
complete applications at the time of filing and better  agency
understanding of the project at the time of application con-
sideration.  The joint review process was established without
statutory changes.
Permits/Agencies Affected

     The joint review process can accommodate  all  local,
state, and federal permits required for energy or  mineral
development, and therefore may include local land-use  permits
and state and federal permits for resource extraction,  water
use, and air and water pollution control.  Federal,  state,  and
local agencies all participate in the process  on a voluntary
basis, but the governor may direct state agencies  to take
part.  In the first case to use the joint review process,  11
federal agencies were voluntary participants.
Administrative Process

     The joint review process is initiated when  the  applicant
requests the Department of Natural Resources  (DNR) to  under-
take a joint review.  The applicant's proposal and a prelimi-
nary recommendation supplied by  the DNR go first  to  the
governor's cabinet, which (with  input from appropriate local
and federal offices) makes a recommendation to the governor
concerning the project's qualifications for joint review.  The
project must meet  three criteria:  (1) the project must  be "a
major energy or mineral resource development"; (2) the propos-
al must be submitted in an early phase of project development;
and (3) the state  must have sufficient staff  and  resources to
support the joint  review.  The governor issues final approval
for use of the joint review process.  This decision  can  take
up to one month.

     The second stage in the joint review process involves the
designation of a review team and the planning by  the team of
the permit review  processes.  A  state agency  (the DNR  in all
joint reviews thus far) is designated the lead state agency by
the governor.  This agency then  consults with other  agencies
in order to obtain commitments to  participate and to designate
liad local and federal agencies.   The lead local  and federal
agencies are usually those with  the greatest  regulatory  re-
sponsibilities for the project.

     The project team is composed  of the applicant and the
designated lead agencies.  Currently, lead federal agencies
are the U.S. Forest Service, the USGS, the EPA,  and  the  BLM.

-------
                              47
                                                     Colorado
Each lead agency  represents  the  agencies on its level of
government in  the  subsequent  discussions of scheduling and
application requirements.  The  team members sign a joint
agreement which publicly  commits the three levels of govern-
ment and the applicant  to  participate fully in the joint re-
view process.  All  agencies  (in  addition to the team members)
participating  in  the  overall  review process sign a statement
of responsibilities,  which carefully documents the regulatory,
coordination,  and  support  responsibilities of all partici-
pants.  For example,  in the  Rio  Blanco oil shale project, a.
statement of responsibilities was  signed by 4 local, 23 state,
and 9 federal  agencies  as  well  as  by the proponent.   The joint
review team then  develops  a  project decision schedule and
conducts public meetings  in  order  to present the project to
the public and to  define  the  issues of major concern.  This
second stage of the joint  review process typically consumes
about eight months; however,  the process is flexible to accom-
modate the pace at  which  the  proponent intends to pursue its
permits.

     The third stage  is the  implementation of the project
decision schedule.  The schedule melds the regulatory reviews,
preparation of an  Environmental  Impact Statement (if neces-
sary), public  hearings, the  completion of the applicant's
design and feasibility  studies,  and the administrative proc-
esses of joint review into one  logical sequence of events.
The schedule is not legally  binding;  however,  a project deci-
sion schedule  agreement is signed  by all involved government
agencies and the proponent.  The joint review team monitors
any changes made  by the individual  agencies and revises the
decision schedule  accordingly.
Experience with the Reform

     Thus far, seven projects have  been  accepted  into  the
joint review process.  The projects  include  a molybdenum mine
and mill, the nation's first nahcolite mine,  Colorado's  first
coal-to-methanol plant, and four  major oil shale  developments.
AMAX, Inc.'s Mount Emmons molybdenum  mine and mill  was the
first project to utilize the process.  The project  decision
schedule is currently being implemented; however, project
construction has been pushed back for economic reasons.   Rio
Blanco Oil Shale Co.'s surface retorting demonstration project
has also been delayed for economic  reasons.   Despite  these and
other project delays, project proponents have not cited  the
joint review process or other regulatory processes  as  causing
the delays.  None of the projects that have  formally applied

-------
Colorado                       43
to the Department of Natural Resources for use of  the joint
review process have been rejected, but some projects that  have
approached the DNR Informally have been redirected  to the
ordinary state permitting process.  Joint preapplication meet-
ings have been used extensively.  Joint public hearings have
also been held.  In one case thus far, a modified  master
application was used.
DECISION-MAKING DEADLINES FOR
AIR AND WATER PERMITS

     Colorado has established specific administrative  dead-
lines for the review and issuance of all state air  permits
(Colorado Air Quality Control Act, Colo. Rev. Stat.  §  25  (7)
(114)).  All state air permits are issued by  the Colorado
Department of Health, Air Pollution Control Division.   The law
prescribes deadlines for determining if the application is
complete, performing analysis, issuing notice of a  public
comment period, accepting public comments, and reaching a
final decision.  Final decisions on major sources must  be made
within 135 days of the filing of a complete application.
Cases that do not require a public comment period must  be
decided within 95 days.  If the agency fails  to meet  these
deadlines, the permit must be approved, but the agency  can
negotiate with the source to extend the deadlines.   The dead-
lines will apply to PSD permits when that authority  is  dele-
gated as expected in 1982.

     In July 1981, Colorado established administrative  dead-
lines for the delegated NPDES wastewater permits in  the Water
Quality Control Act (25 Colo. Rev. Stat., Art. 8 (1973) (as
amended in July 1981)).  The statute requires that  the  Col-
orado Department of Health's Water Quality Control  Division:
(1) rule on the completeness of applications  within  45  days of
their submittal and (2) either deny or issue  a temporary
permit within 180 days of the submittal of the completed ap-
plication.
ADDITIONAL COMMENTS

     The joint review process was developed by  the  Department
of Natural Resources under  a Department of Energy grant  issued
in 1978.  The Colorado General  Assembly now allots  funds  for
operation of the joint review process on a yearly basis.   A
DNR representative suggested that some sort of  fee  system may
be proposed in the future.

-------
                              49                   Colorado
STATE CONTACTS

Adam Poe
Joint Review Process Program Director
Department of Natural Resources
1313 Sherman Street, Room 723
Denver, Colorado  80203
(303) 866-3337

John Clouse
Chief, Stationary Sources Section
Air Pollution Control Division
Colorado Department of Health
4210 East llth Avenue
Denver, Colorado  80220
(303) 320-8333

Jeb W. Love
Chief, Permits Section
Water Quality Control Division
Colorado Department of Health
4210 East llth Avenue
Denver, Colorado  80220
(303) 320-8333

-------
                                                   One-Stop Permitting
                                               Decision-Making Deadlines
                                            Permit/Application Coordinator
OVERVIEW

     Connecticut's major  permitting innovation is the Connect-
icut Siting Council,  a  body  with exclusive authority over all
state permitting  for  the  siting  of  energy, telecommunication,
CAT (community antenna  television towers), and hazardous waste
facilities.

     For other industrial  project applicants,  the Department
of Environmental  Protection's  Office of Adjudications performs
informal permit coordination services.
ONE-STOP PERMITTING  AND  DECISION-
MAKING DEADLINES FOR POWERPLANTS
AND HAZARDOUS WASTE  FACILITIES

     In 1971, Connecticut  passed  the Public Utilities Environ-
ment Standards Act (Conn.  Gen.  Stat. Annotated,  §§ 16-50 et
seq.) which established  a  Power Facility  Evaluation Council.
In 1981 the legislature  passed  the  Hazardous Waste Facilities
Siting Act (Public Act 81-369)  which changed the council's
title to Connecticut Siting  Council and added to its jurisdic-
tion the responsibility  for  certifying hazardous waste facil-
ity sites.  The two  laws are very similar in their procedural
elements.  For instance, both laws  gave exclusive jurisdiction
to the council for issuing state  siting permits, imposed pro-
cedural and decision deadlines, and gave  the council override
over all local ordinances  and regulations.

     All energy transmission facilities (minimum capacity
69 kilovolts) and all generation,  telecommunication, CAT, and
future hazardous waste management facilities (where it is the
primary business) must be  certified by the  Siting Council.

-------
Connecticut
Permits/Agencies Affected

     Prior to the construction of energy  and  telecommunication
facilities, the Connecticut Siting  Council  must  issue a Cer-
tificate of Environmental Compatibility and Public  Need.
Before the construction of hazardous  waste  facilities,  the
council must issue a Certificate of Public  Safety  and Neces-
sity.  These certificates replace all other state  and local
permit requirements except for local  zoning approval.

     The Siting Council is composed of seven  permanent mem-
bers , five of whom are appointed by the governor and two by
the  legislature; two commissioners  of state agencies, which
vary depending on whether the council is  reviewing  an ener-
gy/telecommunications site7 (Environmental Protection and
Public Utility Control departments) or a  hazardous  waste site
(Health Services and Public Safety  departments); and in the
case of hazardous waste applications,  four  ad hoc  representa-
tives from the site and neighboring municipalities.

     Prior to the commencement of any hearing,  the  council
must consult with and solicit written comments  from the fol-
lowing state departments:  Environmental  Protection, Health
Services, Public Utility Control, Economic  Development, Public
Safety and Transportation, the Office of  Policy  and Manage-
ment, and the Council on Environmental Quality.
Administrative Process

     Upon receiving an application  for  generating plants and
transmission  lines, the  council  must  set  a hearing to be held
within  150 days  (180  for hazardous  waste).  Prior to the hear-
ing, the council  must  issue  a  public  notice and circulate the
application among  the  state  agencies  named above as well as
among state officials, affected  municipalities, and various
state and local  commissions.

     For each type of  facility,  the council must consider a
variety of environmental,  safety,  proof-of-need, and community
impact  criteria  in deciding  whether to  issue a certificate or
not.  Applicants  for  hazardous waste  facilities must also
demonstrate financial  liability  and community incentive plans.
The council must  render  a decision  within 10 months for generT
ating plants  and  transmission  lines,  one  year for hazardous
waste,  and 120 days for  telecommunication towers and CAT (with
a possible 60-day  extension).

-------
                              53
                                                   Connecticut
     The Connecticut Siting Council  holds  final authority over
the location of facilities and  has override powers over local
zoning decisions.  For powerplants,  override is possible by a
vote of six out of nine members;  for hazardous waste facili-
ties,  eight out of thirteen votes are required.
Experience with the Reform

     In its ten-year  life span,  the  Power  Facility Evaluation
Council has reviewed  twenty-five full  applications.   Only one
application was for a powerplant;  the  remainder were for
transmission lines, CATs, and  telecommunication towers.   All
but two or three applications  were approved.   The new hazar-
dous waste siting  legislation  has  not  yet  been implemented.
PERMIT/APPLICATION COORDINATOR

     For the past three  years,  the  Connecticut  Department of
Environmental Protection  (DEP)  has  had  an  industrial permit
coordinator located  in its Office of  Adjudications.   All ap-
plicants may use the permit  coordinator's  services.
Permits/Agencies Affected

     The permit coordinator will  informally  assist an appli-
cant with any state environmental  permit.   All  state environ-
mental permits, including  those  for  air  and  water quality,
solid and hazardous waste, and wetlands,  are issued by separ-
ate units within the DEP.  The coordinator  does not track
local or federal permits,  except  the NPDES  program delegated
by the federal EPA to  the  DEP.
Administrative Process

     Applicants usually come  in  contact  with  the  permit  coor-
dinator through word of mouth  or  by  writing  to  the  DEP commis-
sioner for permit information.   The  Connecticut Department  of
Economic Development also  forwards requests  for permit infor-
mation.

     The coordinator will  set  up  informal  preapplication meet-
ings for applicants with the  various  state permitting  staffs
and provide applicants with the  Permit Authority  Index.   Ap-
plicants must apply for permits  separately from each unit.

-------
Connecticut                   54
However, if applicants have trouble with particular permits,
they may request that the coordinator informally act as om-
budsman .
Experience with the Reform

     The industrial permit coordinator reports that he gets
inquiries from potential applicants several times a month.
STATE CONTACTS

Raeann Curtis
Connecticut Siting Council
1 Central Park Plaza
New Britain, Connecticut  06115
(203) 827-2604

N. Rex Altomare
Industrial Permit Coordinator
Department of Environmental Protection
State Office Building
Hartford, Connecticut  06115
(203) 566-4018

-------
                                            Permit/Application Coordinator
OVERVIEW

     In 1978, the Delaware  General  Assembly enacted legisla-
tion entitled the Land  Use  Planning Act for purposes of
achieving consistency and coordination  between the various
levels of government and  between  government and private enter-
prise.  The Act also provides  for the examination of regula-
tory and review agencies  for  purposes of improved coordination
and streamlining of such  processes.

     In order to address  the  mandate of the Land Use Planning
Act, the Delaware Department  of Natural Resources and Environ-
mental Control (DNREC)  has  been examining its own permit and
review processes, and during  1981 proposed to establish a
Development Advisory Service  (DAS)  to assist applicants whose
projects require more than  one  state or federal permit.

     Because of reorganization  legislation that was enacted by
the Delaware General Assembly  in  November 1981, the adminis-
tration of the Land Use Planning  Act,  Coastal Zone Act,
Coastal Management Program, and Permit  Simplification was
transferred from the former Office  of Management, Budget, and
Planning to the Department  of  Natural Resources and Environ-
mental Control.

     The DAS has been established since this reorganization
and the DNREC is in the process of  developing a concerted
effort toward making people aware of the DAS and what it can
provide at an early stage in  the  development process (e.g.,
distributing brochures  to banks and  realtors for dissemination
to prospective developers and  giving presentations to local
planning and zoning commissions).

-------
Delaware                      56
PERMIT/APPLICATION COORDINATOR

     The DAS is a pool of public  officials  qualified  to assist
applicants in complying with permit  requirements.   The service
is available to applicants with projects  that  require more
than one permit.
Permits/Agencies Affected

     The DAS coordinates all  state  and  federal  permits in the
areas of air, water,  solid waste, NPDES,  fish and wildlife,
sediment and erosion, state parks and public  lands,  wetlands,
and hazardous waste,  as well  as  permits in  special areas such
as the coastal zone and Land  Use  Planning Act.
Administrative Process

     The advisory service builds  on  informal  policies that
were already in place in the  DNREC.

     The department has assigned  one contact  person in the
Division of Environmental Control to be  responsible for coor-
dinating meetings of the DAS,  reviews  of permit  requests,  and
related activities regarding  assistance  to  the applicant and
streamlining the permit process.   The  contact pers.on for DNREC
works closely with the  liaison  person  from  the Delaware Devel-
opment Office in providing  assistance  to prospective appli-
cants interested in obtaining permits  for industrial and
commercial developments.

     If a project involves  wetlands  or subaqueous lands, the
coordinator may refer the applicant  to the  department's Wet-
lands Section for purposes  of presenting his  proposal to the
Wetlands/Corps of Engineers Section  404  joint processing meet-
ing which is held every month.

     The service is also available to  applicants at any time
during the permit process.   Reasons  for  additional coordina-
tion could include changes  in project  design, new permit
requirements, and discussion  or resolution  of issues or
conflicts.

     Since the service  has  just recently been established, the
department is currently advising  local jurisdictions, appli-
cants, and prospective  applicants of the service through the
Land Use Planning Act and related programs  and activities.

-------
                              57                       Delaware
A guidebook to permit regulations  for  business  locations was
published last year and distributed  throughout  the  state.   The
book is available to new applicants.
Experience with the Reform

     Figures for the number of permits  that  could  utilize the
proposed service each year can be  roughly  estimated  at  50.
The service will provide faster, more efficient  processing  of
permits and might be particularly  useful  for large residential
construction projects.

     Although the service is new,  the department has already
received very favorable responses  from  local jurisdictions,
state agencies, and applicants who have been advised of  it.
ADDITIONAL COMMENTS

     Currently, the total administration  of  the  department  is
not housed under one roof, but  it will  be by  1983.   After
relocating to its new building,  the department proposes  to
centralize its permits and license application points  within
the facility.
STATE CONTACT

Mary L. McKenzie
Permits Coordinator
Department of Natural Resources and Environmental  Control
Division of Environmental Control
Projects and Planning Section
Edward Tatnall Building
P. 0. Box 1401
Dover, Delaware  19901
(302) 736-3079

-------
                                                   One-Stop Permitting
                                               Decision-Making Deadlines
OVERVIEW

     Florida's efforts  to  streamline and coordinate the per-
mitting process  fall  under three separate statutes:  The Power
Plant Siting Act  (PPSA),  the  Industrial Siting Act (ISA), and
the Transmission  Line Siting  Act (TLSA).  Although the three
acts differ in their  applicability,  they provide for the same
general process,  which  can be categorized as one-stop permit-
ting.

     In addition  to this  legislation,  some coordination exists
between the state certification  process and federal permitting
programs through  a Memorandum of Understanding with Region IV
of the Environmental  Protection  Agency.  Wherever possible,
joint permit applications  and joint  hearings between the two
government levels occur  for a major  industrial or energy proj-
ect.  A joint application  between the  state and the Army Corps
of Engineers for  the  404  dredge  and  fill permit is also
employed.

     Because the  Power  Plant  Siting  Act is the most frequently
used of the three legislative processes named above,  it serves
as the model for  the  one-stop permitting process described
below.  Ways in  which the  Industrial Siting Act and the Trans-
mission Line Siting Act  differ from  the PPSA are then high-
lighted separately.
ONE-STOP PERMITTING AND  DECISION-MAKING
DEADLINES FOR POWERPLANTS

     The Power Plant Siting  Act  (Fla.  Stat.  403.501-517; 1973)
sets up a process  to coordinate  long-range planning and permit

-------
Florida                        60
applications for electric utilities.   The  key  procedural ele-
ments in this process are (1) a  single certification hearing
by an independent hearing officer  in  lieu  of  separate permit
applications, (2) specific  review  deadlines,  and (3) a certi-
fication decision by a siting board composed  of  the  governor
and his or her cabinet.  The process  is mandatory for all
powerplants whose size or capacity exceeds 50  megawatts, and
optional for powerplants below that size.
Permits/Agencies Affected

     Nearly all state and  local  air,  water,  and waste permits
required for new powerplant  facilities  are  affected by this
process.  Among these are  water  pollution,  sewage treatment
and disposal, industrial wastewater  treatment and disposal,
consumptive water use,  surface water  management,  air quality,
and coastal construction permits.  On the other hand, local
building permits are excluded and  federal permit  requirements
are not specifically incorporated  into  the  legislation.   How-
ever, by means of the Memorandum of  Understanding described
above, joint federal/state permit  applications and hearings
may occur.

     The Department of  Environmental  Regulation (DER) serves
as coordinator of the process, and the  Public Service Commis-
sion (PSC), the Department of Veteran and Community Affairs
(DVCA), and the local water  management  district (WMD) are
always parties to the proceedings.  Other government agencies
may request participation  in the process.
Administrative  Process

     All Florida  utilities  must  submit  to the DVCA annual ten-
year site plans which estimate  their power generating needs
and the general location  of  proposed powerplant sites.   The
DVCA classifies each plan as suitable or unsuitable and sub-
mits its findings  to the  DER as  a  prerequisite to the certifi-
cation process.

     Once a  utility has  filed an application for a powerplant
site, the legislation calls  for  a  number of procedural  steps
and review deadlines to  accelerate the  certification process.
Some of these are  (from  the  date of application) the follow-
ing:

       •  The DER  must designate the application complete or
          incomplete within  ten  days.

-------
                               61                    Florida
       •  The DER must  commence  all  studies required by
          statute regarding  the  suitability of the site
          within 30 days.  The DER  considers such crite-
          ria as land use, accessibility,  environmental
          impact on air  and  water quality,  and technical
          sufficiency of operational  safeguards.   These
          studies must  be  completed  within  seven  months.

       •  The DER (through a  designated  hearing officer)
          must conduct  a local land-use  hearing within
          90 days.  The  hearing  officer  must submit a
          written order  within 30 days of  the hearing.

       •  The DER must  submit a  final  report to the hear-
          ing officer within  eight  months.   Along with
          the DER's recommendation  on  the  proposal, this
          report includes  findings  from  all studies that
          were conducted,  comments  from  other agencies
          regarding such issues  as  the need for the site
          and its compatibility  with  state  plans,  and any
          other comments submitted  by  interested  parties.

       •  A certification  hearing must commence by the
          tenth month.   The  applicant, the  DER, the PSC,
          the DVCA, and  the  WMD  always participate in
          this hearing.  Other agencies,  local govern-
          ments, and interested  members  of  the public may
          participate if prior approval  is  granted.

       •  The hearing officer must  submit a recommended
          order to the  siting board  within  12 months.

       •  The board must issue an order  to  approve, mod-
          ify, or deny  the site  application within 14 months.
Experience with the Reform

     As of September  1981, twelve  facilities  had  been  permit-
ted under the Power Plant Siting Act  and  two  are  in  process.
ONE-STOP PERMITTING AND DECISION-MAKING
DEADLINES FOR INDUSTRIAL PROJECTS

     The Industrial Siting Act  (Fla.  Stat.  288.501-.518;  1979)
is an effort to expedite permit decisions  for  industrial  proj-
ects.  The process is modeled after  the  PPSA,  although  it

-------
Florida                        62
varies in a few key ways.  Foremost  among  these  is  that the
process is optional for eligible  applicants.   Any  business
that has the potential for creating  50  or  more full-time jobs
and requires more than one permit  is  eligible.

     In addition, the processing  time for  reports,  hearings,
and decisions is shorter under  ISA than under  PPSA.   For in-
stance, the certification hearing  must  occur within  four
months of filing compared with  PPSA's ten-month  deadline,  and
the entire process must be completed  within  six  months versus
PPSA's fourteen-month time frame.

     The ISA addresses the permit  system at  the  state level
only.   Local governmental approvals  are not  included, unlike
in the PPSA.

     Finally, unlike with the PPSA,  no  industrial  facility has
yet applied to the state to  utilize  the procedures  of the ISA.
Instead, project sponsors have  exercised the option  to work
through the old permit-by-permit  system.
ONE-STOP PERMITTING AND
DECISION-MAKING DEADLINES
FOR TRANSMISSION LINES

     The Transmission Line  Siting  Act  (Fla.  Stat.  403.520-
535; 1980) is intended to provide  an  efficient  and centrally
coordinated permitting process  for the  location and mainte-
nance of electrical transmission  line  corridors and the con-
struction of transmission lines.   Most  major transmission
lines that will carry 230 kilovolts or  more  and tnat will
cross a county line are  required  to follow the  certification
process.

     This process  is also modeled  after the  PPSA,  although its
time frame of six  months parallels that of the  ISA.  Current-
ly, one certification has been  approved under the  TLSA.
STATE CONTACT

Hamilton S. Oven
Florida Department  of  Environmental  Regulation
Twin Towers Office  Building
2600 Blair Stone  Road
Tallahassee, Florida   32301
(904) 488-0130

-------
                                                   One-Stop Permitting
OVERVIEW

     Georgia has a one-stop permitting  process  for  environ-
mental permits issued by the Department of  Natural  Resources,
Division of Environmental Protection.
ONE-STOP PERMITTING

     This process enables concurrent processing of air, water,
and solid and hazardous waste permits  issued by the Department
of Natural Resources, Division of Environmental Protection.
Applicants requiring any or all of  these permits  for  an energy
or a construction project are eligible.
Permits/Agencies Affected

     The state issues all the environmental permits  for which
it has authority through its Environmental Protection Divi-
sion.  These include NPDES permits, air permits under the
Clean Air Act, and RCRA (Phase I) permits for hazardous and
solid wastes.
Administrative Process

     For information about a permit, an applicant may contact
any one of the branches of the Environmental Protection Divi-
sion (EPD), such as the Water Protection Branch or Air Protec-
tion Branch.  Within each branch there is a program coordina-
tor who informs the applicant what other permits are necessary

-------
Georgia                       64
and arranges concurrent reviews for those permits.  The pro-
gram coordination branch gathers, analyzes, and combines all
the permit information and recommendations into one package.
The director of the EPD then reviews the information and
approves or denies all the permits at once.  State law speci-
fies that only the director of the Division of Environmental
Protection has the authority to approve permits.

Experience with the Reform

     Staff members from the Department of Natural Resources
believe that a key to Georgia's success in economic develop-
ment programs has been the one-stop permitting process.  They
sav it provides expeditious, predictable administration of
environmental laws.
STATE CONTACTS

Jim Setser, Chief
Program Coordination Branch
Environmental Protection Division
Department of Natural Resources
270 Washington Street S.W.
Atlanta, Georgia  30334
(404) 656-6905

Gibson Johnston, Information Officer
Department of Natural Resources
270 Washington Street S.W.
Atlanta, Georgia  30334
(404) 656-3530

-------
                                            Permit/Application Coordinator
                                                        Joint Hearing
                                                     Joint Application
                                                    Computer Tracking
OVERVIEW

     The Hawaii state  government  has  developed and continues
to explore a variety of  mechanisms aimed at streamlining the
environmental permitting process.   The legislature passed a
bill in 1977 whic'h  established  countywide central coordinating
agencies for land-use  permits.   Currently the state is bring-
ing on-line a comprehensive  computer  tracking system to be
implemented at both the  state and  the county level.

     In addition, Hawaii sponsored the publication of numerous
permit directories.  The Coastal  Zone Management office is in
the process of revising  a directory of local, state,  and
federal permitting  agencies  which  was first prepared by the
Federal Executive Board.

     The Coastal Zone  Management  office is also the lead
agency on an Interagency Task Force for State Permit Simplifi-
cation.  In March 1981 this  committee released a preliminary
report of findings  and recommendations.
PERMIT/APPLICATION COORDINATOR,
JOINT HEARING, AND JOINT  APPLI-
CATION FOR LAND-USE CONTROLS

     The Hawaii Legislature passed  a  bill  in 1977 (Chapter 46,
HRS) which mandated that  each  of  Hawaii's  four county govern-
ments establish a central  coordinating  agency (CCA).   The
CCAs act primarily as  information sources  for land-use rules,
regulations, and permit applications.   In  addition,  they pro-
vide a variety of coordinating services.

-------
Hawaii                        66
     Anyone may request information  from a CCA.   Applicants
requiring more than one permit are encouraged  to  use  the  CCA's
coordinating services.
Permits/Agencies Affected

     The city and county of Honolulu established  its  CCA  in
the Department of Land Utilization.  Because  the  Honolulu CCA
is the largest and most sophisticated of  these agencies,  it
will be the model discussed here.  The CCA provides  informa-
tion on and attempts to coordinate with other local,  state,
and federal permitting agencies which have control or regula-
tory powers over land development projects.
Administrative Process

     According to the enabling legislation,  the CCA  has  the
following three responsibilities:

       •  To maintain and administer a repository of  all
          laws, rules and regulations, procedures, permit
          requirements, and review criteria  of all fed-
          eral, state, and local agencies having any
          control or regulatory powers over  land develop-
          ment

       •  To maintain and administer a master file of
          active applications for building permits and
          subdivisions, petitions for changes in state
          land-use districts, and general plan or devel-
          opment plan amendments within the  county

       •  Upon request by the applicant, to  attempt  to
          schedule and coordinate referrals, public  in-
          formation meetings, or public hearings with
          other federal, state, or county commissions or
          agencies

     In addition to carrying out these duties, the Honolulu
CCA has studied alternative methods for streamlining  the
permit process.  It has developed for the Department  of  Land
Utilization a master application form which  covers seventeen
different kinds of land-use permits.  The Honolulu CCA is  also
bringing on-line a computerized permit register and  monitoring
system which is independent of the HPASS system described
below.  The system, which will be operational in late 1982,
will monitor the status of permit applications and provide a
complete land-use control inventory.

-------
                               67                        Hawaii
Experience with the Reform

     The Honolulu CCA has provided extensive  information  serv-
ices to the general public.   In  1980,  nearly  9,000  people
visited its public information counter, and over  20,000 phone
calls were made to it.  During 1980 the CCA monitored  almost
400 permits to ensure that applicants  satisfied all  permit
conditions.  Where possible,  the CCA has conducted  joint  hear-
ings among different permitting  bodies and has worked  to  coor-
dinate the timing of different regulations.
COMPUTER TRACKING

     The Hawaii Permit and Application Support System  (HPASS)
is currently being brought on-line for the purpose of  moni-
toring environmental permits.
Permits/Agencies Affected

     Each county government and state agency in Hawaii will
have a computer terminal for tracking permits.  The initial
system will include information on the following types of
permits and reviews:  the coastal zone special management area
permit; the land-use conservation district use permit; the
shorewaters use permit; the state air, ground water and waste
permits; the delegated NPDES permits; the state EIS;  the A-95
Notification and Review; and the Coastal Zone Management
Federal Consistency Review.
Administrative Process

     Initially, HPASS will be used to monitor existing permits
and ascertain patterns of noncompliance.  The state plans to
expand the system to include permit applications and an envi-
ronmental data base.
Experience with the Reform

     HPASS will be on-line in late 1981.

-------
Hawaii                        gg
ADDITIONAL COMMENTS

     In June 1980 the governor of Hawaii established  the
Interagency Task Force for State Permit Simplification and
requested that it develop and prepare recommendations for
improving the regulatory efficiency of state land and water
development permits.  The task force consists of a working
committee, which consists of agency staff involved in day-to-
day permit program administration, and a policy committee,
made up of state department and commission directors.

     The task force released a preliminary report in  March
1981 containing short-term and long-term recommendations for
streamlining procedures.

     Over the long run, the task force proposed that  the state
do the following:

       •  Standardize or expand the lists of exceptions
          endemic to individual state-level regulatory
          processes

       •  Distinguish between major and minor development
          and establish procedures to expedite minor
          projects

       •  Develop an interagency system of preapplication
          review for major state development permits

       •  Simplify, streamline, and coordinate public
          hearing requirements between state agencies

     For the short term, the task force recommended numerous
program-specific measures.  These include memoranda of under-
standing between agencies in order to improve coordination,
organizational changes to eliminate confusing and overlapping
jurisdiction, master application forms at a department level,
coordination of time frames, etc.

     The task force is currently collecting feedback  from
state agencies and will incorporate it into a final report.
In the future the task force intends to study the issue of
local, state, and federal coordination.

-------
                              69                       Hawaii
STATE CONTACTS

Dick Poirier, Project Manager
Hawaii Coastal Zone Management Program
P. 0. Box 2359
Honolulu, Hawaii  96804
(808) 548-4609

Ian McDougall, Chief
Central Coordinating Agency
Department of Land Utilization
City and County of Honolulu
650 South King Street
Honolulu, Hawaii  96804
(808) 523-4254

-------
OVERVIEW

     Idaho has not implemented anv programs or passed any
legislation to formally consolidate permitting processes with-
in the state.  However, some informal coordination does occur
in permitting such projects as small hydroelectric facilities
and dredge and placer mining activities.

     In some cases, pro.iect sponsors need only submit one
application to obtain two permits.  For instance, an applicant
proposing to drill for oil or gas may complete one application
for both the oil and gas drilling permit issued by the Depart-
ment of Lands and the injection well permit issued by the
Department of Water Resources.  The same coordination might
occur for an applicant seeking stream alteration permits from
the State Department of Water Resources and the federal Army
Corps of Engineers.

     Occasionally, the Public Utility Commission and the
Department of Water Resources will conduct joint hearings for
proposed hydro projects.
STATE CONTACTS

Phil Welker
Idaho Energy Office
State House
Boise, Idaho  83720
(208) 334-3800

-------
Idaho                         72
A. Kenneth Dunn, Deputy Director
Department of Water Resources
State House
Boise, Idaho  83720
(208) 334-4437

-------
                                                        Joint Review
                                                 Site Inventory/Banking
                                            Permit/Application Coordinator
                                                        Joint Hearing
                                               Decision-Making Deadlines
                                                     Joint Application
OVERVIEW

     Illinois has made  several distinct efforts to streamline
and coordinate  the  permitting process.  The Illinois Depart-
ment of Energy  and  Natural  Resources (ENR) is implementing the
Illinois Coordinated  Review Process (ICRP).  This process,
which is modeled after  the  Colorado Joint Review Process,
facilitates permitting  of major non-nuclear energy projects by
encouraging local,  state, and federal  government agencies to
plan a coordinated  review schedule early in the development of
a project proposal.   In another effort, the ENR has performed
an environmental siting study to identify favorable sites for
coal gasification and synthetic fuels  facilities.  The ENR is
also in the process of  preparing a permit directory for energy
development projects.

     The Illinois Environmental Protection Agency (IEPA) uses
the Coordinated Permit  Review Program  to coordinate and inte-
grate some functions  in the permit reviews of the divisions
within the agency.  The process, available for all significant
construction projects,  incorporates preapplication confer-
ences, joint notification,  integrated  hearings, and a single
IEPA decision on the  total  permit application.  The focuses of
the ENR and IEPA processes  are different:  the ENR joint re-
view includes all permits for non-nuclear energy projects
while the IEPA  program  coordinates state evironmental permits
for all major projects.

     State statute  establishes strict  deadlines for the review
of applications for all state environmental permits.  Failure
to meet these deadlines results In automatic granting of the
permit.

-------
Illinois                      74
     The Illinois Environmental Protection  Agency  has  also
implemented a master application  for construction  projects  in
waterways or flood plains.  The single  form  is processed  by
three state agencies and the U.S. Army  Corps  of  Engineers.
JOINT REVIEW OF NON-NUCLEAR
ENERGY PROJECTS

     In April 1981 Governor James R. Thompson  issued  Executive
Order No. 3, which directed the Department of  Energy  and
Natural Resources to expedite the regulatory process  for  ma.ior
non-nuclear energy projects.  In response to this order,  the
ENR developed the Illinois Coordinated Review  Process.  The
process is designed to coordinate the responsibilities  and
schedules of the federal, state, and local agencies involved
in the review of project applications.  However,  the  process
does not alter either the substantive or the procedural re-
quirements of these agencies.  Streamlining mechanisms  like
joint hearings, master applications, and regulatory deadlines
may be utilized by the review team  in individual  cases, but
such mechanisms are not a mandatory part of the review  pro-
cess.  Use of the Coordinated Review Process by the project
sponsor is voluntary.
Permits/Agencies Affected

     The process can accommodate any permit  that  is  needed  in
order to construct a major energy project  in  Illinois  (includ-
ing air, water, solid waste, etc.).  However,  since  agency
participation is voluntary, local and  federal  agencies  can
choose not to participate in the coordinated  review  process.
State agencies are required by  the governor  to participate.
Administrative Process

     Energy project developers can voluntarily choose  to  par-
ticipate in the coordinated review process.  The developer
first submits a formal letter requesting participation  in the
ICRP, a completed project summary questionnaire, and/or de-
scriptive data on the project to the Department of  Energy and
Natural Resources.  The ENR screens the proposal to determine
that:  (1) the project is a major energy development and  (2)
the proposal is in the beginning stages of  the planning and
regulatory approval process.  The ENR prepares a pre-recom-
mendation report and submits it to the Energy Review Board,

-------
                               75                      Illinois
consisting of the directors of seven key state  agencies.   The
Energy Review Board, in turn, makes a  recommendation  to  the
governor, and if the governor agrees that  the project qual-
ifies for coordinated review status, he specifies  the state
participants.  These steps typically take  about one month.

     The project-specific review team, made up  of  the project
sponsor and one lead agency from each  of the  local, state, and
federal governments, has primary responsibility for the  coor-
dination role.  The review team documents  agencies' commit-
ments to participate, delineates regulatory responsibilities,
and establishes a detailed review schedule which coordinates
the various agency reviews.  The review team also  sponsors
public information meetings and scoping meetings prior to  the
start of the agency reviews.

     The governor assigns the state lead agency, which in  most
cases is expected to be the ENR.  The  federal and  local  lead
agencies are chosen by consensus from  among the agencies at
each level.  The lead agency is generally  the party with the
greatest interest in the project.  The federal  lead is
typically taken by the agency with responsibility  for
preparing the Environmental Impact Statement (EIS) or, if  no
EIS is needed, by the agency with the  greatest  permitting
responsibility.  The local lead agency is  typically the  county
or municipal governmental unit.  Other interested  governmental
units such as regional planning commissions may also  seek  an
active role in the ICRP team activities.   The review  team
members are responsible for determining the needs  of  the
agencies in the government they represent  and assimilating
their requirements into the coordinated review  plan.   Inclu-
sion in or exclusion from the review team  does  not affect
agency authority concerning the review of  the proposed
project.
Experience with the Reform

     The Illinois Coordinated Review Process is being de-
veloped in response to an Executive Order issued in April
1981.  Although the preliminary program design was completed
in June 1981, the final program preparations were not to be
completed until the end of 1981.  Thus far, several projects
have expressed interest in using the program, and one company
has formally applied for consideration.

-------
Illinois                       76
SITE INVENTORY/BANKING

     The Illinois Department of Energy and Natural Resources
has performed an environmental siting study and released a
report identifying areas suitable for construction of coal
gasification and synthetic fuels facilities.  Site areas were
screened on the basis of a number of environmental criteria,
including air quality, water quality, geotechnical suitabil-
ity, and socioeconomic impacts.  The final study includes
broad areas that are designated as favorable, potentially
favorable,  potentially favorable with conditions, or re-
stricted.  The study will be used by ENR staff to help  syn-
thetic fuel developers identify appropriate sites on which to
construct facilities.
PERMIT/APPLICATION COORDINATOR
AND JOINT HEARING FOR CONSTRUCTION
PROJECTS

     Coordinated Permit Review is a process for coordinating
construction project permit reviews conducted by  the  four
permitting offices within the Illinois Environmental  Protec-
tion Agency.  The key to the program is the creation  of a
Coordinated Permit Review Group, consisting of one representa-
tive from each of the lEPA's permitting divisions, which meets
with the project sponsor to establish permit and  application
requirements, resolves internal jurisdictional disputes, and
conducts joint public notice and hearing activities.  The
procedures were developed by the IEP& under the permitting
authority granted in the Environmental Protection Act (111.
Rev. Stat. Ch. 111-1/2 1039).

     The process is available for projects requiring  construc-
tion permits from two or more of the IEPA divisions dealing
with air, water, land, and public water supplies.  The project
must also be "significant," a term which is defined in the
regulations.  A project is significant, for example,  if the
uncontrolled air emissions will be 100 or more tons per year
of any contaminant or if the emissions include hazardous or
toxic pollutants.  Participation by eligible projects is
voluntary.

     This program has broader eligibility than the coordinated
review process described above.  The Coordinated  Permit Review
Program  is open to any significant construction project while
the coordinated review process is open only to non-nuclear
energy developments.  In the case of energy projects, the

-------
                              77                      Illinois
Coordinated Permit Review Program  can be  incorporated  into  the
broader framework of  the coordinated review  process.
Permits/Agencies Affected

     The four permitting divisions within  the  IEPA—Air  Pollu-
tion Control, Water Pollution Control,  Land/Noise Pollution
Control, and Public Water Supplies—are required to partici-
pate in the Coordinated Permit Review  Program.  The procedure
does not include other state agencies,  local regulators,  or
federal regulators.  The process applies to all environmental
permits for construction projects issued by the IEPA,  includ-
ing state air, water, solid waste, and  drinking water, as  well
as PSD, NPDES, and SDWA permits delegated  by the federal  Envi-
ronmental Protection Agency to the IEPA.   The  small number of
environmental permits issued bv other  state agencies,  such as
the departments of Conservation and Transportation, are  not
included in this process.
Administrative Process

     When an eligible project sponsor approaches  the  IEPA  to
use the coordinated review process, one representative  from
each division is chosen for the review group, and a project
coordinator is chosen from this group.  The group first holds
a preapplication meeting with the sponsor to determine which
permits are needed and to outline information requirements for
applications.  A project report is filed, including a descrip-
tion of the project and proposed pollution control systems,
followed by the more detailed "total project application."

     During the review process, in which the application is
reviewed internally by each division, the review group meets
to resolve any jurisdictional conflicts and conducts joint
public notification.  IEPA hearings deal with the full scope
of the project's environmental impacts, rather than focusing
on qualifications for a single permit.

     Unless all requested permits are approved by the individ-
ual divisions, none of the IEPA permits will be issued.  If
all divisions concur on the total permit application, all
permits are granted.

-------
Illinois                      78
Experience with the Reform

     The review process regulations were adopted in November
1979.  Since that time one project, a low Btu coal gasifica-
tion project, has completed the process.  About six other
projects ranging from hazardous waste treatment facilities  to
powerplants are currently at some stage in the process.
DECISION-MAKING DEADLINES

     The Illinois Environmental Protection Act  (111. Rev.
Stat. Ch. 111-1/2 1039) requires the IEPA to either grant or
deny permit applications for any IEPA permits within 90 days
of the filing of a completed application.  For  cases in which
public hearings are necessary, the deadline is  extended to
180 days from the filing of the complete application.  The
permit is automatically granted if the agency fails to act
within these statutory deadlines.
JOINT APPLICATION FOR
CONSTRUCTION IN WATERWAYS
AND FLOOD PLAINS

     The Illinois Environmental Protection Agency has -created
a single permit application form for construction activities
in waterways or flood plains.  The four agencies utilizing  the
application are the Illinois Environmental Protection Agency
(Section 401, Clean Water Act), the Illinois Department of
Transportation (Division of Water Resources waterway regula-
tion under the Rivers, Lakes, and Streams Act,  Illinois Re-
vised Statutes, Chapter 19, §§ 52 et seq.), the Illinois
Department of Conservation (review of fish and  wildlife im-
pacts under the Fish and Wildlife Coordination  Act, 16 U.S.C.
661-664), and the U.S. Army Corps of Engineers  (Section 404,
Clean Water Act).  The single application must  be filed with
all four offices.  The permit reviews are conducted indepen-
dently by each agency, but if the application is submitted  to
each agency at the same time, concurrent review is possible.

-------
                              79                     Illinois
STATE CONTACTS

E. Wayne Bahr, Manager
Illinois Energy Review Program
Department of Energy and. Natural Resources
325 W. Adams Street
Springfield, Illinois  62706
(217) 785-2800

George Benda, Manager
Energy Bond Fund Program
Illinois Department of Energy
  and Natural Resources
325 W. Adams Street
Springfield, Illinois  62706
(217) 785-2800

Tom McSwiggin, Manager
Permit Division
Division of Water Pollution Control
Illinois Environmental Protection Agency
2200 Churchill Road
Springfield, Illinois  62706
(217) 782-0610

-------
OVERVIEW

     There is no consolidation  of  state  environmental  permits
in Indiana.  The Stream Pollution  Control  Board,  Air Pollution
Control Board, and Environmental Management  Board are  separ-
ately responsible for approving water, air,  and  solid  waste
permits.  The Indiana State Board  of  Health  provides staff
support to these boards.

     Informal intra-agency coordination  does occur in  several
program areas.  Staff in  the areas of  air, water, and  solid
waste frequently consult  one another  regarding permit  issu-
ance, particularly where  toxic  substances  are involved.   The
State Office of Surface Mining  expects to  coordinate strip-
mine permitting with the  state-delegated NPDES program in the
future.

     The State Board of Health  has hesitated to  institute
formal coordination measures such  as  one-stop permitting out
of fear that such measures would increase  permit  delays.
STATE CONTACTS

Larry Kane, Permit Section Chief
Water Pollution Control Division
Indiana State Board of Health
1330 West Michigan
Indianapolis, Indiana  46206
(317) 633-0761

-------
Indiana                       82
Lonnie Brumfield
Water Pollution Control Division
Indiana State Board of Health
1330 West Michigan
Indianapolis, Indiana  46206
(317) 633-0751

-------
                                                   One-Stop Permitting
OVERVIEW

     The major permitting  reform  in  Iowa has been the estab-
lishment of one-stop  permitting  for  the construction of large
powerplants.  In addition,  state  agencies try to make deci-
sions on permits promptly  after  application, though there is
no formal deadline.   For the  three  utilities that have gone
through the entire one-stop process  and been granted certifi-
cates, the average time was approximately 16 months from
initial partial application to certificate.
ONE-STOP PERMITTING FOR
POWERPLANTS

     Iowa uses one-stop  permitting  in  regulating the construc-
tion of powerplants with capacities greater than 100 mega-
watts.  For such powerplants,  the  state  conducts,  under the
authority of the Iowa  State  Commerce Commission, a unified
application and hearing  process  encompassing all state and
local permit requirements.   This process allows a utility to
submit a single application  and  to  participate in only one
hearing in order to obtain the required  comprehensive con-
struction and operation  permit.  Proposed facilities that meet
the eligibility requirements  must  use  the one-stop process.
The procedures and authorities are  prescribed in Chapter 476A,
Code of Iowa (1981).
Permits/Agencies Affected

     The Commerce Commission's Certificate  of  Public  Use,
Convenience, and Need  functionally  aggregates  all  state and
local permits and licenses  for powerplant construction and

-------
Iowa                          84
operation, although the individual  agencies  do continue to
issue permits as part of  the  certification  process.   The major
permits affected by the commission's  one-stop  permitting are
the following:

       •  Air, water, and solid  waste permits  required by
          the Department  of Environmental Quality (DEQ),
          including RCRA, NPDES,  and  SDWA permits

       •  Permits for water use  and flood plain construc-
          tion issued by  the  Natural  Resources Council

       •  The Conservation Commission's  permit for con-
          struction in a  navigable  stream

       •  Compliance with city or county zoning
          ordinances

     As prescribed in the Iowa Code,  the Commerce Commission
cannot grant a certificate unless all state  and local regula-
tory requirements are met.  However,  agencies  that fail to
participate in the commission's  hearings are assumed to have
no objection to the application  and may  be  ordered by the
commission to issue the relevant permits.   Some state agen-
cies, notably the Bureau  of Labor,  have  chosen not to partici-
pate in the unified hearings  and have thus  lost their author-
ity to deny required permits.  The  Iowa  Code also prohibits
the imposition of further regulatory  requirements by any state
or local agency after the certificate is granted.  Finally,
the commission can overrule city and  county  zoning author-
ities, although the commission has  never utilized this power.
Administrative Process

     The procedures  for processing  applications for construc-
tion of large powerplants  are  outlined  in  Chapter 476A in the
Iowa Administrative  Code.  The process  begins  with the util-
ity's submittal of  its master  application.   The commission
circulates the application to  all  regulatory and interested
agencies and seeks  their  input in  determining  if sufficient
information for commencing a hearing  has been  provided.  The
commission has allowed itself  45  days to determine if an
application is complete.

     After the application is  complete, a  unified hearing is
held.  This hearing  is in  lieu of  any other hearing required
for permits or licenses to construct,  maintain, or operate a

-------
                              85
                                                          Iowa
facility.  The formal hearing is conducted  by a commerce  com-
missioner and a hearing officer from  the  regulatory  agency
concerned with the particular substantive area.   State  and
local officials must present any objections  in these  proceed-
ings, and dissatisfied agencies are required to propose amend-
ments that could bring the application  into  compliance.  The
requirements of agencies which fail to  appear are  presumed  to
be satisfied.

     Following the hearings, the participating agencies render
permit decisions based on the final application.   The commis-
sion then issues the certificate based  on the agency  actions
and its own findings.  When the certificate  is issued,  the
permits issued as a result of this joint  review process are
included in the certificate along with  any  conditions they
might impose.  There are no decision-making  deadlines speci-
fied, although the statute directs the  commission  to  "render  a
decision on the application in an expeditious manner" (Chap-
ter 476A.6, Code of Iowa).  In addition,  the statute  (Chap-
ter 476A.2) signifies that there be one-stop judicial review.
Appeals must be brought against the entire  certificate  and  not
against individual permits.
Experience with the Reform

     Five facilities have used this permitting process.   In
four cases the utilities were issued certificate's; in the
fifth case the certificate was denied because of a failure to
establish public need for the power to be generated.  Three
utilities completed the whole process, which from initial
notification of the commission to the issuance of the certifi-
cate took about one and one-half years.  The fourth utility
requested and received a significant alteration certificate
for an existing facility.

     The interpretation of Chapter 476A was the subject of a
1979 court action between the DEO and the Commerce Commission
(Polk County District Court Docket Nos. CE 11-6046 and CE 11-
6082).  The DEO issued conditional permits in the air pollu-
tion and waste water areas.  The commission used these condi-
tional permits as indications that the DEO's regulatory re-
quirements had been met and issued a certificate.  The court
found that the commission had acted properly and that the DEO
could not require further permits;

-------
Iowa                          86
STATE CONTACT

Tom Houvenagle
Iowa State Commerce Commission
State Capitol
Des Moines, Iowa  50319
(515) 281-5920

-------
OVERVIEW

     Kansas has  taken  no  formal  steps  to  streamline  applica-
tion reviews  for  environmental permits.   However,  informal
mechanisms such  as preapplication meetings  and  project
"managers" are used  for some  projects.  These  informal  prac-
tices are effective  because all  state  environmental  permits
other than pesticide and  coal mining licenses  are  issued  in a
single agency, the Kansas  Department of Health  and Environment
(DHE).  The preapplication meetings are an  opportunity  for the
applicant to  present the  project to DHE officials  and for DHE
officials to  outline the  permit  requirements and distribute
application forms for  the  various permit  programs.   Project
managers serve as the  state contact for the applicant.  These
practices are used whenever practical  to  minimize  application
review time.
STATE CONTACT

Donald Carlson, Chief
Industrial Unit
Water Pollution Control Section
Kansas Department of Health and Environment
Building 740-Forbes Field
Topeka,  Kansas  66620
(913) 862-9360

-------
                                                    Computer Tracking
                                            Permit/Application Coordinator
OVERVIEW

     Kentucky's Department  for  Natural  Rescmrces and Environ-
mental Protection  (DNREP) has  initiated and continues to ex-
plore administrative measures  to  improve the environmental
permitting process.  The department's  Bureau of Surface Mining
Reclamation and Enforcement  has a computerized permit tracking
system, and early  in FY1982  the DNREP  will  implement a coordi-
nated priority application  procedure for certain types of
project applicants.

     In addition to initiating  these measures, in FY1981 the
DNREP consolidated its  water programs,  which had previously
been split between the  Bureau of  Environmental Protection
(BEP) and the Bureau of Natural Resources (BNR), into the BEP.
Also, all the offices of the BEP  were  relocated from three
physically separate sites into  one building.  Although these
actions have not reduced the number of  necessary permits or
applications, they do promote  consistency and better communi-
cation .
COMPUTER TRACKING OF  SURFACE MINING  PERMITS

     The Bureau of Surface Mining  has  implemented a computer-
ized permit tracking  system as  part  of  a Surface Mining In-
formation System.  All applications  for any permit issued by
the Bureau of Surface Mining are  included  in the system.

-------
Kentucky                      90
Permits/Agencies Affected

     The Bureau of Surface Mining issues permits  for  surface
mining and enforces reclamation regulations.   Delegation  of
authority by the federal government will soon  add permit
responsibility for enforcement of surface effects of  under-
ground mining.  The bureau's computer tracking  system  follows
all state mining permits.
Administrative Process

     The tracking system of the Bureau of Surface Mining
serves as an information mechanism for the bureau's  separate
divisions and as a monitoring device to ensure  that  permits
are processed expeditiously.  The computer system tracks  each
project as it moves through the three separate  divisions
responsible for planning, issuing permits, and  enforcement.
Experience with the Reform

     The computer tracking system has been very useful  in
monitoring the high volume of coal permits issued  in Kentucky,
In a sample month, the bureau issued 123 new permits and moni-
tored 6,400 permits.  The feasibility of implementing  this
system in the DNREP's Bureau of Environmental Protection—the
regulatory bureau for water, air, and solid waste  permits—is
currently being evaluated.
PERMIT/APPLICATION COORDINATOR
FOR NEW TECHNOLOGIES

     The DNREP plans to coordinate a priority application pro-
cedure for applicants with multiple permits whose applications
involve new technical processes.  Applicants applying for per-
mits associated with certain kinds of electric power genera-
tion, ethanol production, tar sand, oil shale, coal conver-
sion, and other operations may fall into this category.
Permits/Agencies Affected

     All environmental permits required by an eligible appli-
cant would be expedited by this procedure.  All  bureaus  issu-
ing these permits, such as Surface Mining, Environmental  Pro-
tection, and Natural Resources, would participate  in an  inter-
departmental task force.

-------
                              91                      Kentucky
Administrative Process

     The secretary of the DNREP will have authority  for  desig-
nating a project a priority application.  In order  to  make
this determination, the Secretary will consider  the  project's
investment potential as well as its utilization  of  new tech-
nologies.  The main vehicle for expediting the project will be
the interdepartmental task force, whose members  will work
together to resolve application problems.
Experience with the Reform

     If the priority application program proves successful,
its use will be expanded to other projects  involving major
investments.
ADDITIONAL COMMENTS

     The DNREP is currently planning other improvements de-
signed to reduce the time involved in reviewing permits and  to
increase communication between applicants and the agency.
These improvements include a permit coordinator, a revised
permit information document, greater use of preapplication
conferences, and concurrent permit review.
STATE CONTACT

Richard Shogren
Administrator
Office of Special Projects
Department for Natural Resources
  and Environmental Protection
Capital Plaza Tower
Frankfort, Kentucky  40601
(502) 564-7320

-------
                                                       Joint Hearing
OVERVIEW

     The Louisiana Environmental Affairs Act  (Act 449  of  1979,
L.R.S. 30:1051 et seq.) reorganized the state  regulatory
structure to consolidate most environmental permitting
activities and place them within the Department  of Natural
Resources' newly formed Office of Environmental  Affairs  (OEA).
Act 449 also created the Environmental Control Commission
(ECC), which is composed of the heads of seven state agencies
and is vested with final authority for granting  or denying
environmental permits.  The OEA serves as  the  staff for the
ECC, and its five divisions review applications  for air
quality, water pollution, solid waste, hazardous waste, and
nuclear development permits.  Permitting authority for some
categories has been delegated by the ECC to the  head of the
OEA.
JOINT HEARING

     The ECC holds a single hearing for any project that
requires multiple environmental permits.  However, the  appli-
cations and decisions for these permits are still handled on
an individual basis.

-------
Louisiana                     94
STATE CONTACT

William B. DeVille
Director of Policy Development
Office of Environmental Affairs
Department of Natural Resources
P. 0. Box 44066
Baton Roiige, Louisiana  70804
(504) 342-1254

-------
                                            Permit/Application Coordinator
                                                      Joint Application
                                                Decision-Making Deadlines
OVERVIEW

     Maine has  developed comprehensive land-use programs  under
the jurisdiction  of  several state authorities.  In order  to
minimize the duplication between the land-use regulations  and
administrative  programs,  Maine passed the Environmental
Coordination Procedures  Act.   In addition, Maine has  imposed
decision-making deadlines on  many of its permit procedures.
PERMIT/APPLICATION COORDINATOR AND JOINT
APPLICATION FOR LAND-USE PERMITS

     Maine has instituted a number of administrative proce-
dures to coordinate  the  permit application process.  The  En-
vironmental Coordination Procedures Act, known as the  "One
Stop Law"  (which  is  in  fact a misnomer; it is really a coordi-
nated procedures  bill),  specifically prescribes that,  depend-
ing upon the geographic  location of the project, the Land Use
Regulatory Commission  (LURC)  or the Department of Environ-
mental Protection  (DEP)  act as lead agency to coordinate  the
application and review  of six land-use statutes, and broadly
prescribes coordinating  activities (1977;  amendment to 12 MSRA
§ 685-B).  In addition,  the LURC and the DEP signed a  memoran-
dum of agreement  in  1978 defining the situations in which each
would act as lead agency.

     All applicants  that are  required to obtain a permit  from
both the DEP and  the LURC may benefit from the one-stop law.
In addition,  for  larger  and more complex projects that require
multiple permits, a  project coordinator procedure may  be used.

-------
Maine                          96
Permits/Agencies Affected

     The Maine Board of Environmental  Protection (BEP) has
statewide jurisdiction and  issues  environmental permits for
air, water, and waste as well  as a number of land-use permits.
The Department of Environmental  Protection (DEP) administers
these environmental permitting programs.   The BEP land-use
permits affected by the one-stop law are  site location (for
developments in excess of  three  acres  or  subdivisions of over
20 acres), minimum lot size  (for lots  smaller than 20,000
square feet), great ponds,  and coastal wetlands.  The DEP is
the lead agency in the incorporated and organized areas of the
state.

     The Land Use Regulatory Commission has planning, zoning,
and permitting authority over  land-use development in Maine's
unorganized territories (51  percent of the state) where no
municipal form of government exists.  Its staff is located in
the Maine Department of Conservation.   Applicants seeking
development in the unorganized  territories must obtain a land-
use permit from the LURC and will  probably require at least
one of the land-use permits  issued by  the BEP.   The LURC is
the lead agency in the unorganized portion of the state.

     In addition to these  five permits, the one-stop law
covers the Department of  Inland  Fisheries and Wildlife's
(DIF&W's) stream alteration  permit.  The  DEP and DIF&W have
also signed a memorandum of  agreement  explicitly defining the
procedures to follow under  the one-stop law.

     The lead agency system  may  affect all permits required
by a project, including those  issued by the BEP, the LURC,
and the DIF&W.  Although they  are  not  statutorily included,
air, water, and waste permits  and  licenses may be handled
through the coordination procedures, particularly for larger
projects.
Administrative  Process

     Under  the  one-stop  law,  applicants in the unorganized
portion  of  the  state  are required to submit only one applica-
tion form  to  the  LURC for all six permits.  A master applica-
tion form  has  not been  developed.  Rather, the most detailed
relevant form,  such  as  the one for "site location" or "great
ponds" permits,  is  used.  LURC staff coordinate the distribu-
tion of  information  to  the permitting bureaus and attempt to
ensure consistent responses to the applicant as well as coor-
dinate the  timing of  responses.   However,  individual per-
mitting  bureaus  still issue the  permits.  To date there have

-------
                              97                         Maine
not been any projects  large  enough  to  warrant joint hearings,
although these are envisioned  in  the  law.

     The process is essentially  the  same  in the organized
portion of the state,  with  the DEP  acting  as lead agency.

     As indicated, the LURC  generally  acts as lead agency for
all projects in the unorganized  territories, and the DEP acts
as lead agency in the  other  areas.   However, if a project in
the unorganized territories  poses more technical problems
associated with air, water,  or waste  than  associated with
land use, the DEP, because  of  its expertise, may take the
lead.  When a proposed project is large or controversial, the
lead agency may appoint  a coordinator  to  act as contact point
for both the applicant and  the permitting  bureaus.  The coor-
dinator may arrange preapplication  meetings and consolidated
hearings.  On an informal basis  there  is  always a great deal
of communication between the different agencies.
Experience with the Reform

     The one-stop law has proved  particularly useful to great
ponds and subdivision permit  applicants.   The LCJKC has not yet
permitted any major projects  under  this  authority,  although
several are under way.
DECISION-MAKING DEADLINES

     Maine's Administrative  Procedures  Act  specifies that the
final decision on all permits  should  be made no later than
180 days after acceptance of  the  application.   In addition,
there are a number of permit-specific deadlines.   For
instance, the site location  permit  must be  decided on within
30 days of receiving a  complete application.   If  a public
hearing is held, the final decision should  be  made within
30 days after the hearing.
ADDITIONAL COMMENTS

     Two other efforts aimed  at  simplifying  the  permitting
process are under way.  The governor  has  charged the Land and
Water Resources Council with  devising a one-stop permitting
process for hydroelectric  facilities.  This  proposal is sched-
uled for review in the January  1982  legislative  session.

-------
Maine                          98
     In addition, the governor has established  a  citizen  com-
mittee to study the operations of  the  DEP  and assess  how  they
can be improved.  This report was  scheduled  to  be released  in
November 1981.
STATE CONTACTS

Thomas S. Radsky
Supervisor, Development Review Division
Land Use Regulatory Commission
State House, Station 22
Augusta, Maine  04333
(207) 289-2631

Hollis McGlauflin
Director, Bureau of Land Quality Control
Department of Environmental Protection
State House, Station 17
Augusta, Maine  04333
(207) 289-2111

Steve Groves
Director, Bureau of Water Quality Control
Department of Environmental Protection
State House, Station 17
Augusta, Maine  04333
(207) 289-3365

David Tudor
Director, Bureau of Air Quality Control
Department of Environmental Protection
State House, Station 17
Augusta, Maine  04333
(207) 289-2437

-------
                                                  Site Inventory/Banking
                                                    One-Stop Permitting
                                                Decision-Making Deadlines
                                            Permit/Application Coordinator
                                                         Joint Hearing
OVERVIEW

     Maryland has  one  of the most comprehensive and  sophisti-
cated energy siting  programs.  The Power Plant Siting  Act
(PPSA), passed  in  1971,  includes a state site acquisition
program, ongoing research programs, and a one-stop siting
process for powerplants  throughout the state.  The Coastal
Facilities Review  Act  (CFRA), passed in 1975, is modeled after
the one-stop siting  element of the PPSA and covers oil  and  gas
facilities along Maryland's coast.

     In addition,  in 1975 Maryland passed consolidated  permit
procedure legislation  in an effort to promote coordination
between state and  local  agencies as well as among state
agencies.

     Maryland also has a Governor's Permit Simplification Task
Force, which is charged  with the responsibility of improving
the permitting  process of state and local governments.  The
task force has  circulated,  but not yet proposed, a draft per-
mit simplification bill.
SITE INVENTORY/BANKING FOR
POWERPLANTS

      The Power  Plant  Siting Act (1971;  Md. Nat. Res. Ann.
Code §§ 3-301 et  seq.)  includes provisions for state acquisi-
tion of sites suitable  for major powerplants.  Under the PPSA,
the state has set  up an Environmental Trust Fund, which is
financed by a surcharge on electricity production, to pay for

-------
Maryland
site purchases as well as to conduct  ongoing  research  programs
for site evaluation and related environmental considerations.
The state is required to develop  an inventory of  suitable
sites.  Utilities may then choose to  purchase or  lease sites
from the inventory or to acquire  sites  independently.


Permits/Agencies Affected

     The Maryland Department of Natural  Resources'  (DNR)  Power
Plant Siting Program (PPSP) is the lead  agency for  the site
banking program and for conducting detailed technical  studies
of the environmental impact of existing  and proposed power-
plants.  Other state agencies, such as  State  Planning,  Eco-
nomic and Community Development,  Health  and Mental  Hygiene,
and Agriculture are integrally involved  in the process, but
the PPSP is vested with ultimate  authority to purchase a  new
site.  State acquisition of a site or state approval of a
utility-owned site may pre-empt local zoning.
Administrative Process

     The PPSA requires the PPSP to create an  inventory  of  at
least one site for every major utility  that has  a  peak  demand
of 1,000 megawatts (at present, this covers three  utilities),
up to a maximum of eight sites.  Once purchased, the  site  is
banked and can be sold to utilities at  fair market value or
under 99-year leases.
Experience with the Reform

     Maryland has acquired only one site.  The  PPSP has  iden-
tified a second site but has not been able to complete pur-
chase negotiations.  The PPSP is about halfway  through the
process of identifying the third site.  No utilities  have
sought to acquire a state site.
ONE-STOP PERMITTING AND DECISION-
MAKING DEADLINES FOR POWERPLANTS

     The PPSA also contains provisions for one-stop permitting
of powerplants and transmission lines.  Prior  to  the construc-
tion of any of these facilities (with a minimum capacity of  69
kilovolts) , a utility must receive a Certificate  of Public
Convenience and Necessity from the Public Service Commission

-------
                              101                      Maryland
(PSC).  This certificate replaces a  number  of  other  state  and
local permit requirements.   A  single  public hearing  process
and decision deadlines are important  elements  of  the PPSA.
Permits/Agencies Affected

     The Certificate of Public Convenience  and  Necessity  re-
places most environmental  state  permits,  such as  those  relat-
ing to dredge and fill, air emissions, water appropriations,
and water use, as well as  local  permits and zoning.   However,
the delegated NPDES and solid waste permits are  issued
separately.

     If the proposed facility or  its appurtenances  (e.g.,
water intake channels) involve the dredging or  filling  of
state wetlands, approval by the  State Board of  Public Works  is
required.  While the issues pertinent to  a  recommendation  on
proposed alterations to state wetlands may  be considered  in  a
single public hearing process and within  the same decision
deadlines, a formal authorization must be granted by  the  State
Board of Public Works.

     The PSC is the ultimate decision-making body for issuance
of the permit.  However, the PPSP has a formal  lead advisory
role.  The departments of  State  Planning, Economic and  Commun-
ity Development, Health and Mental Hygiene  (which.ordinarily
issues air, water, and waste pollution permits), Transporta-
tion, and Agriculture issue joint recommendations with  the
PPSP.

     In general, there is  little federal  participation  in  the
proceedings.  However, when Maryland was  considering a  nuclear
power site, the state worked closely with the Nuclear Regula-
tory Commission.
Administrative Process

     The PSC receives and evaluates the annual plans of each
public utility.  These plans, which include ten-year forecasts
of need for proposed sites, are sent to the PPSP.  Within six
months of receipt of the plans, the PPSP must issue a. prelimi-
nary statement regarding the suitability of each site.  If a
site is not initially declared unsuitable, the PPSP will
conduct a detailed environmental investigation that must be
completed within two years.  These studies provide the basis
for the state departments'  recommendations to the PSC on

-------
Maryland                      102
whether to grant, deny, or grant with conditions a  certificate
of public convenience and necessity  for a  powerplant  at  that
site.

     Applications for certification  must be  submitted two
years prior to planned construction.  Upon notification  from
the PSC that an application has been received,  the  PPSP  must
complete its environmental studies of the  site.  The  PPSP  then
makes a preliminary recommendation to the  PSC on whether the
certificate should be granted or denied.   This  recommendation
is presented along with relevant data at a public hearing.
Within 15 days after the hearing, the PPSP must  issue a  final
recommendation to the PSC, which must grant  or  deny certifica-
tion within 90 days of the public hearing.
Experience with the Reform

     Five applications for powerplant certification  have  been
submitted, and three of these have been approved.  A fourth
application concerned a nuclear facility, but  the  utility has
elected to defer the certification process.  A fifth applica-
tion is currently (as of October  1981) in process.   To  date,
no utility has elected to construct  on a state-banked site.

     An official in the powerplant siting program  noted that
it has been impractical to abide  by  the deadlines  in the  PPSA
and that there are proposals to amend them.
ONE-STOP PERMITTING AND DECISION-
MAKING DEADLINES FOR COASTAL
OIL AND GAS FACILITIES

     The Coastal Facilities Review Act  (1975;  Md.  Nat.  Res.
Ann. Code §§ 6-501 et seq.) is  closely  modeled after  the
PPSA's one-stop siting procedures.   It  differs substantively
from the PPSA in that there is  no stable  source  of funding
such as the Environmental Trust  Fund, no  ongoing  research
program, and no state acquisition of  sites.

     The CFRA affects facilities related  to  crude  oil and
natural gas in areas of Maryland adjacent to the  Atlantic
Ocean and Chesapeake Bay.  The  CFRA  procedures apply  to off-
shore pipelines, production terminals and refineries, oil
storage facilities, and assembly areas  for oil and gas
exploration, subject to certain  size  qualifications.

-------
                              103                      Maryland
Permits/Agencies Affected

     The CFRA certificate replaces all  other  state  and  local
permits, except local  zoning.   This  exclusion differentiates
the CFRA from the PPSA.  Again,  the  DNR acts  as  the lead
agency, and the action  taken by the  DNR secretary on the  ap-
plication constitutes  the department's  position  on  all  other
permits or licenses.   In the case of projects involving alter-
ation to state wetlands, the recommendation on that aspect  of
the project is forwarded to the Board of  Public  Works for
final approval.
Administrative Process

     Procedurally, CFRA certification  is  very  similar  to  PPSA
certification.  Public hearings and  time  limits  are  an  inte-
gral part of the process.
Experience with the Reform

     There have been no eligible project applicants  since  the
CFRA's passage.  Therefore, the legislation remains  untested.
PERMIT/APPLICATION COORDINATOR,
JOINT HEARING, AND DECISION-
MAKING DEADLINES

     The "Consolidated Permit Procedures" legislation  passed
in 1975 and modified in 1979 (Ann. Code Md. Art. 78A §  56-67)
established the Office of Coordinator of Development and Con-
struction Permits and provided for coordinated permitting
procedures.  The legislation includes formal procedures for
master application forms, joint and consolidated hearings, and
decision-making deadlines.  However, the office believes that
it is more effective when it works on an informal basis,
acting as ombudsman and information source.

     Any applicant may use the coordinator's informal  serv-
ices, and any applicant requiring more than one permit may use
the formal procedures.  Applicants are required to submit
master application forms but are not required to use joint or
consolidated hearings.

-------
Maryland                      104
Permits/Agencies Affected

     The Office of Coordinator  is  housed  in  the  Board  of Pub-
lic Works, which consists of  the governor,  the  treasurer,  and
the comptroller.  The coordinator  will  provide  information to
the applicant on all construction  and environmental  permits
issued by state and local agencies.  Local  agencies  are in-
vited to participate in joint hearings, but  state  agencies
must participate in joint or  consolidated hearings upon the
coordinator's request.
Administrative Process

     The consolidated permit procedures  legislation specifies
that the coordinator has authority  to:

      1.  Require all applicants  for  any  permit  to complete a
          master application form.  This  document  helps the
          applicant understand  exactly what  permits are needed
          and where he or she can obtain  them.

      2.  Conduct consolidated  hearings  between  state agen-
          cies.  The coordinator  has  complete  discretion to
          enforce a consolidated  hearing  on  state  agencies and
          the applicant.

      3.  Conduct joint hearings  between  state  and local
          government agencies.  Joint hearings  will be held
          only upon the applicant's request  and  if the local
          entity consents.

      4.  Intervene in a project  review  and  enforce a 60-day
          time limit for action by  the agencies.
Experience with the Reform

     The Office of Coordinator  has  rarely  used  its  formal
authority granted by  state  legislation  but rather has worked
more effectively on an  informal  basis.   In the  past seven
years, the office has conducted  consolidated hearings only
five times and has yet  found  it  necessary  to intervene and
enforce the  time limit  on administrative decisions.  Joint
hearings between state  and  local  entities  have  been requested
rarely.  The Office of  Coordinator  received 4,000 master
permit application forms in  1980.

-------
                             105                     Maryland
STATE CONTACTS

Paul Massicot
Administrator
Maryland Energy Administration
Department of Natural Resources
Tawes State Office Building
Annapolis, Maryland  21401
(301) 269-2788

Dr. Sarah Taylor
Coastal Resources Division
Tidewater Administration
Department of Natural Resources
Tawes State Office Building
Annapolis, Maryland  21401
(301) 269-2784

Frances J. Aluisi
Coordinator
Development and Construction Permits
P. 0. Box 1510
Annapolis, Maryland  21404
(301) 269-2666

Thomas Andrews
Director
Water Resource Administration
Department of Natural Resources
Tawes State Office Building
Annapolis, Maryland  21401
(301) 269-3846

-------
                                            Permit/Application Coordinator
                                                     Joint Application
                                               Decision-Making Deadlines
OVERVIEW

     The Massachusetts  Energy  Facility Siting Council (EFSC)
expedites the review  of permit applications for all hydro-
electric facilities of  less  than 100 megawatts by requiring
preapplication conferences and joint applications, and by
imposing decision deadlines.   The EFSC also functions as an
appeal board for state  and local permit decisions on these
projects.

     The EFSC further serves as a forum for appeals of state
and local decisions on  environmental permits for any energy
project that meets the  definition of "facility" set out in
M.G.L.L. 164 § 69G.   If an energy developer is dissatisfied
with an agency decision for  one of a number of specific
reasons, including failure to  make a timely decision, an EFSC
review may be requested.  The  EFSC has the authority (with
certain exceptions) to  overturn agency denials or issue per-
mits if an agency has failed to act.  There have been no
petitions for this review since the law was enacted in 1974.

     The Department of  Environmental Quality Engineering
(DEQE) has instituted a number of additional reforms.  It has
relocated all DEQE offices to  one location, published a permit
directory, and conducted a study to identify possible areas
for permit consolidation and procedural streamlining.
PERMIT/APPLICATION COORDINATOR,
JOINT APPLICATION, AND
DECISION-MAKING DEADLINES
FOR HYDROELECTRIC PROJECTS

     The Energy Facility Siting  Council  is  composed of four
cabinet members and six gubernatorial  appointees.   It serves

-------
Massachusetts                 108
as the lead state agency for hydro-power development and  is
responsible for coordinating the permitting and  licensing of
hydropower generating facilities with capacities smaller than
100 megawatts.  In this role the EFSC makes use  of modified
master applications, prehearing conferences, and decision-
making deadlines.  These procedures, adopted pursuant  to Mass.
Stat. Ch. 164 § 69H1/2, are mandatory for hydroelectric  pro-
jects with capacities less than 100 megawatts.

     In addition, the statute established the EFSC as  an op-
tional appeal board for the permit decisions or  failures to
make permit decisions by state and local agencies concerning
eligible hydroelectric projects.  The applicant  may appeal
decisions to the EFSC or directly to the state courts.
Permits/Agencies Affected

     The EFSC requirements, including a master application,
prehearing conference, and decision deadlines, apply  to  all
state agency and local conservation commission permits and
licenses applicable to hydroelectric developments,  including
wetlands, dredge and fill, dam, and waterways permits.   Al-
though federal agencies are not bound by  the procedures,
application information is forwarded to the Federal Energy
Regulatory Commission and the Army Corps  of Engineers.
Administrative Process

     The process is initiated when the applicant files a pre-
liminary notification form with  the EFSC.  This application  is
subsequently circulated.to all interested local, state, and
federal agencies and the utility in whose service  territory
the site is located.  The state and local permitting agencies
are prohibited from requiring the use of application forms
other than the master application, though they may ask the
developer to supply supplemental information and studies
specific to the project.  Within 30 days the EFSC  must call  a
prelicensing conference at which the interested agencies
inform the applicant what permits are required and what addi-
tional information is needed to  complete the application.
Following this conference and submission by the applicant of
the required information, the EFSC specifies decision-making
deadlines for the individual agencies not more than 90 days
from the completion of  the application.  If an environmental
impact report is required under  the Massachusetts  Environ-
mental Policy Act, the  decision  review periods start when the
report is completed.

-------
                              109                Massachusetts
     The statute also allows any party aggrieved by the action
or inaction of any state or local permitting or licensing
agency in cases involving hydroelectric projects smaller than
100 megawatts to appeal to the EFSC within ten days of the
administrative decision.  The EFSC jointly considers all pend-
ing appeals and must issue a decision, based upon cost, need
for energy, and environmental impact, within 90 days.  This
EFSC decision is equivalent to the final agency action on the
appealed permit or license.  Failure to appeal to the EFSC
does not sacrifice any rights to judicial appeal.
Experience with the Reform

     The statute was enacted in November 1979 and the regu-
lations were adopted in April 1981.  Two projects are current-
ly in the agency decision-making stage.
STATE CONTACTS

Robert Smart, Jr.
Senior Counsel
Energy Facility Siting Council
Room 300
73 Tremont Street
Boston, Massachusetts  02108
(617) 727-1136

Tom McShane
Department of Environmental Quality
  Engineering
1 Winter Street
Boston, Massachusetts  02108
(617) 292-5520

-------
                                            Permit/Application Coordinator
                                                      Joint Application
                                                        Joint Hearing
                                                    Computer Tracking
OVERVIEW

     Within the Michigan  Department of Natural Resources
(MDNR), two major efforts have been undertaken to streamline
the environmental permitting  process for both energy and in-
dustrial projects.   The Environmental Services Division has
designated a permit  coordinator for air quality,  water qual-
ity, and solid and hazardous  waste permits.  The Division of
Land Resource Programs has developed a consolidated applica-
tion and review process for all federal and state land/water
interface permits.   This  latter reform will be tested in the
fiscal year beginning October 1981.
PERMIT/APPLICATION COORDINATOR

     The Environmental  Services  Division has designated an
individual in its Office  of  Environmental Planning to coor-
dinate environmental protection  permits  on a project-by-
project basis.   Although  any applicant may use this service,
it generally applies only to projects  that are large in scope
or that require  multiple  permits.


Permits/Agencies Affected

     The Environmental  Services  Division coordinates state air
and water quality and solid  and  hazardous waste permits.
These permits are issued  either  by  other divisions in the
Michigan Department of  Natural Resources or by special commis-
sions such as the Water Resources Commission and the Air
Pollution Commission.

-------
Michigan                      112
Administrative Process

     The permit coordinator provides the following  services  to
applicants:

       •  Organizes preapplication conferences

       •  Provides unified department responses advising
          applicants of permit requirements,  potential
          problem areas, etc.

       •  Tracks permits of concern

       •  Distributes permit application packages

       •  Refers potential permit applicants  to appro-
          priate department divisions or to other
          agencies

     The permit coordinator attempts to enter early  into an
applicant's planning process in order to clarify permit re-
quirements and to serve as a focal point for  the applicant
from start to finish.


Experience with the Reform

     The MDNR has performed some type of coordination service
for many years.  The current structure was developed  in the
past year.

     The MDNR estimates that 5 percent of the projects re-
viewed by the agency benefit from this coordination  service.
JOINT APPLICATION AND JOINT HEARING
FOR DREDGE AND FILL PERMITS

     The Division of Land Resource Programs is currently
implementing a consolidated application and review  program  for
all state and federal permits that relate to the  "land/water
interface" (such as flood and erosion risk areas, submerged
lands development, etc.).  This program will apply  to all
industrial and energy projects, regardless of size,  that
require any of these permits.  Joint hearings involving state
and federal, as well as multiple  state authorities,  are
routine.

-------
                              ..-.o                 Michigan
Permits/Agencies Affected

     The land/water  interface  process  currently consolidates
permitting authorities  of  nine  state  statutes and four federal
authorities which involve  the  land/water  interface.   The rele-
vant state statutes  are  the  Great  Lakes  Submerged Lands Act,
the Inland Lakes and Stream  Act,  the  Soil  Erosion and Sedimen-
tation Control Act,  the  Aquatic  Nuisance  Control Act, the
Great Lakes Shorelands  Act,  the  Wetlands  Act, the Floodplain
Control Act, the Dam Construction  Act,  and the Inland Lakes
Level Act.  The relevant federal  statutes  are Sections 401 and
404 of the Clean Water  Act,  Section  10 of  the Rivers and
Harbors Act, and the Coastal Zone  Management  Act.  The Divi-
sion of Land Resource Programs  will  administer the program.
Other participating  agencies include  the  State Division of
Water Management, the U.S. Army  Corps  of  Engineers district
office, the regional office  of  the U.S.  Environmental Protec-
tion Agency, and the Fish  and  Wildlife Service.
Administrative Process

     As a result of  this  program,  applicants  submit a single
application form, receive  joint  reviews,  undergo one hearing
for all relevant permits,  and  receive  a  single  department
response.  A group of division  staff members  functions as a
consolidated permit  processing  unit and  is  the  focal point for
the applicant throughout  the permitting  process.  This group
is responsible for such  tasks  as  receiving  applications,
routing them, tracking their progress,  notifying the public,
compiling all comments,  conducting hearings,  and ensuring
prompt review and action.

     There will be one joint field investigation,  one joint
hearing, and concurrent  reviews  on the  project  application.
The final decision to issue or  deny a  permit  will  generally be
made by the Division of  Land Resource  Programs,  although  other
divisions, such as Water  Management, will occasionally be
responsible if the project falls  more  closely under their
authority.

     Projects will be categorized  as major  or minor,  and  major
projects will require public notification of  hearings.  The
division will expedite the review  of minor  applications—ap-
proximately 75 percent of  all  projects—and hopes  to complete
them within two weeks.

-------
Michigan                      114
Experience with the Reform

     The consolidated application  process  was  just  implemented
in October 1981.  However,  the  Division  of Land  Resource Pro-
grams estimates that upwards of  75  percent of  all  applicants
will incur considerable cost and time  savings  with  the con-
solidated process, in addition  to  avoiding considerable
federal duplication.
COMPUTER TRACKING

     The Division of Land Resource  Programs  employs  a computer
tracking and environmental warning  system  to assist  in assur-
ing both that reviews are conducted within  special  time frames
and that key environmental concerns are  given proper consider-
ation by all viewers.  The system  is further capable of serv-
ing as a list which on a biweekly  basis  notifies  interested
members of the public of pending applications.  The  system
also facilitates the coordination  of both  internal  and exter-
nal reviews at all levels.   (This  system is  being evaluated
for its potential to consolidate almost  all  permitting re-
quests within the department.)
ADDITIONAL COMMENTS

     In the past, coordination  between  the  Environmental Serv-
ices and Land Resource  Programs  divisions has been informal.
Generally one division  took  the  lead  for  shepherding a project
through all environmental permit requirements.   The Division
of Land Resource Programs is  now exploring  mechanisms for
coordinating the two  divisions'  permitting  activities.

     Michigan is currently undergoing a comprehensive regula-
tory review process and  is pursuing  several initiatives to
streamline permit programs.   For example, there are several
pieces of proposed legislation  introduced in the Michigan
legislature that would  streamline the siting and permitting of
powerplant facilities.   In addition,  there  is a proposal to
establish a one-stop  information and  referral service in the
Michigan Department of  Commerce  for  all permits.

-------
                             115                 Michigan
STATE CONTACTS

Tim Ervin
Office of Environmental Planning
Environmental Services Division
Michigan Department of Natural Resources
P. 0. Box 30028
Lansing, Michigan  48909
(517) 373-8542

Karl Hosford, Chief
Division of Land Resource Programs
Michigan Department of Natural Resources
P. 0. Box 30028
Lansing, Michigan  48909
(517) 373-3328

-------
                                           Permit/Application Coordinator
                                                 Site Inventory/Banking
                                               Decision-Making Deadlines
OVERVIEW

     Minnesota  is currently  developing several procedural
mechanisms aimed at  reducing duplication and inconsistency  in
its permitting  programs.   The Business Licensing Group is
preparing procedures for  incorporating the Environmental Qual-
ity Board's (EQB's)  permit coordination unit into its activ-
ities.  The EQB is developing rules to govern the identifica-
tion of appropriate  areas  for a  powerplant site inventory.
Finally, the EOB is  in  the process of revising the state EIS
rules to integrate decision-making deadlines and greater coor-
dination with the permit  information collection process.

     The Minnesota Pollution Control Agency, which is the
state agency responsible  for regulating air quality, water
quality, and waste disposal, is  currently drawing up a set of
permitting rules designed  to make state permit procedures more
uniform.  These rules are  modeled after the EPA's consolidated
regulations and will include a general set of procedural rules
as well as specific  technical rules for all state programs and
federally delegated  programs.  Minnesota currently has author-
ity for the NPDES program  and is seeking interim authorization
for RCRA.  The  agency hopes  to complete the rules by March
1982.
PERMIT/APPLICATION COORDINATOR

     The Environmental  Coordinating Procedures Act (1976;
Minn. Stat. §§  116 c.22 -  116  c.34) provided for a state pro-
cedure for applying  for environmental  permits called the

-------
Minnesota                     118
"Master Application Process" and  the establishment  of  an  envi-
ronmental management information  center.   The Permit Coordina-
tion Unit of the Minnesota Environmental Quality  Board admin-
isters this program.

     In 1981 the legislature passed, the Business  Licensing
Bill (Ch. 342, Minn. Laws), which established a Bureau of
Business Licensing with a mandate to consolidate, simplify,
and expedite the business license procedures of state  agen-
cies.  The EQB's unit will merge  into the  Bureau  of Business
Licensing in late 1981 to form a  coordination unit  for both
environmental and nonenvironmental permits.

     Any applicant may use the bureau's information services
or may elect to use its more comprehensive services.
Permits/Agencies Affected

     Every permit necessary for the initial licensing and
continual operation of a business is affected by  this program.
Examples of these are environmental permits for air quality,
water quality, and solid waste disposal, as well  as nonenvi-
ronmental permits, such as a license to open a restaurant or a
hotel.

     The Business Licensing Group is located in the recently
reorganized Department of Energy, Planning and Development
(EPD).  The EQB is a policy-coordinating board composed of
agency heads and citizen appointees.   Its staff is also
located in the EPD.
Administrative Process

     The Business Licensing Bill gives the bureau authority
for the following functions:

       •  The bureau shall provide to applicants compre-
          hensive information on required licenses.
          Applicants may request preapplication confer-
          ences.  The director of the bureau may request
          that each affected agency provide to the
          applicant written reviews of license require-
          ments within a time frame specified by the
          director.

-------
                             119                     Minnesota
       •  The bureau shall develop a master  application
          procedure.  This process parallels the  current
          one administered by the EQB.  Applicants  may
          complete a master application form describing
          their proposed project.  The bureau  circulates
          the form to all relevant agencies,  which  then
          have 20 days to notify the bureau  that  a  permit
          is needed.  If an agency does not  respond,  it
          loses its authority to require a license.   The
          bureau provides the applicant with application
          forms and related information.  The  applicant
          may submit application forms to each agency
          separately or channel them through the  bureau.

       •  The bureau shall facilitate consolidation of
          hearings among state agencies.  This will be
          done at the consent of participating agencies.

       •  The bureau shall encourage and facilitate the
          participation of federal and local government
          agencies in licensing coordination.   The  bureau
          will advise applicants of federal  and local
          license requirements and will consult with
          local government officials with respect to
          coordination.

       •  The bureau shall make recommendations for
          eliminating, consolidating, simplifying,  expe-
          diting, or otherwise improving licensing
          procedures.
Experience with the Reform

     In the past, the EQB's master application process has
been used rarely, but its information services have been
utilized extensively.  Staff members offer several possible
explanations for this low usage of the master application
process:

       •  Those applicants who could benefit most from
          the process (i.e., large projects needing many
          permits) can afford their own lawyers and con-
          sultants to work as advocates.

-------
Minnesota                     120
       •  The Permit Coordination Unit is  perceived  as
          just another layer of bureaucracy.

       •  Permit writing offices are not supportive  and
          remain protective of individual  jurisdictions.

The head of the Business Licensing Group intends  to  aggres-
sively encourage project applicants to use the master applica-
tion process.
SITE INVENTORY

     The Minnesota Power Plant Siting Act as amended  through
1980 (Minn. Stat. §§ 116 c.51 et seq.) gives the Environmental
Quality Board authority to develop an inventory of  "large
electric generating plant study areas."  The EQB is currently
developing rules identifying the criteria it will use  to
select this inventory.  Powerplant sponsors are not required
to build on sites in the inventory, but if they choose  other-
wise they must provide sufficient rationale.   In addition  to
developing an inventory, the EQB has authority to issue a
certificate of site compatibility for proposed powerplants  in
excess of 50 megawatts.
Permits/Agencies Affected

     The EQB's siting authority pre-empts only  local and
regional zoning authority; all other permits required by  the
facility must be applied for separately, including  the Certif-
icate of Need issued by the Department of Energy, Planning  and
Development.
Administrative Process

     The purpose of the study area inventory is to provide
guidance to the utility for identifying reasonable sites  for
new construction and to ensure that all possible sites are
considered.

     The criteria that the EQB will use to select these areas
will include air quality, transportation, and water quality.
Study areas will not be specific because of the burden of such
a task in a large state, but will cover broad geographic
areas.

-------
                             121                     Minnesota
     The EQB does not purchase sites;  it merely designates
areas as suitable in anticipation of a powerplant  proposal.
Experience with the Reform

     Because the EQB has only recently promulgated  the  rules
to establish selection criteria,  it has not yet put any areas
into the inventory.  The absence  of powerplant construction
proposals has obviated the need for an inventory  to date.
DECISION-MAKING DEADLINES
AND COORDINATION WITH EIS

     The EQB is currently rewriting rules for determining when
and how a state Environmental Impact Statement must be pre-
pared.  As part of these revisions, the EQB is developing
rules for coordinating permit information collection activi-
ties with the preparation of the EIS.  All required environ-
mental permits, including local and federal ones, will be
identified early in the EIS process so that this information
can be easily coordinated.

     In addition, the EQB intends to invoke administrative
decision-making deadlines on permit-issuing agencies.  All
agencies will be required to issue or deny permits no more
than 60 days after the EIS is completed.
STATE CONTACTS

Charles A. Schaffer, Director
Bureau of Business Licensing
Department of Energy, Planning and Development
480 Cedar Street
St. Paul, Minnesota  55101
(612) 296-0617

Nancy Onka
Power Plant Siting Program
Minnesota Environmental Quality Board
100 Capitol Square Building
550 Cedar Street
St. Paul, Minnesota  55101
(612) 296-2169

-------
Minnesota                    122
Tom Rullard, Manager
Policy Analysis and Review
Minnesota Environmental Quality Board
100 Capitol Square Building
550 Cedar Street
St. Paul, Minnesota  55101
(612) 296-2319

Randy Burnyeat
Head of Municipal Unit
Division of Water Quality
Minnesota Pollution Control Agency
1935 West County Road, B-2
Roseville, Minnesota  55113
(612) 296-7228

-------
                                            Permit/Application Coordinator
OVERVIEW

     In 1981, the state of  Mississippi  passed  a  comprehensive
permitting bill which required each  state  agency to develop a
plan for one-stop permitting, to  coordinate  permitting with
other state and federal agencies,  and to design  master appli-
cation forms.  The governor's Executive Order  No.  371
strengthened the bill by designating the Department of Eco-
nomic Development the chief  implementing agency  for the legis-
lation, and by establishing  an advisory council  with reporting
duties to the governor.  Since significant portions of the
bill do not go into effect  until  the spring  of 1982, this
summary necessarily concentrates  on  reforms  outlined in the
Act.  Prior to passage of the permitting bill, the state
Bureau of Pollution Control  made  informal  efforts  to coor-
dinate air and water permits.
PERMIT/APPLICATION COORDINATOR

     The one-stop permitting bill, H.B.  629,  declares  that  the
state's policy is:

    "each agency of the state shall  cooperate  to  the
     greatest extent possible with other  agencies of  the
     state and federal government which  have  separate,
     but similar, related or interrelated  jurisdiction,
     so that the processing and  issuing  of permits,
     licenses and other such instruments  will  be  stream-
     lined to reduce costly delays,  duplication of ef-
     fort, and unnecesary governmental red tape and so
     that state policy will be carried out in  an  effec-
     tive, efficient, predictable, and consistent
     manner."

-------
Mississippi
Permits/Agencies Affected

     The bill is broad in scope, applying  to every  state
agency that issues permits of any kind.  The state  Bureau
of Pollution Control, part of the Department of  Natural
Resources, issues all environmental permits, including those
for NPDES, PSD, and RCRA (Phase  I).

     Executive Order No. 57, which complements H.B.  629,
lodges central authority for permit reform in the state's
Department of Economic Development.  This  department  maintains
information for other agencies and the public on permit re-
quirements.  The executive order authorizes use  of  a  toll-free
phone line for public information.  The director of  the De-
partment of Economic Development chairs the Mississippi Busi-
ness Permitting Advisory Council, which includes representa-
tives from state and federal agencies and  citizens  from busi-
ness, labor, and environmental groups.  This council  is to
assist in implementing the permit reform bill, and  to report
on its progress to the governor.
Administrative Process

     Under the bill each agency must develop a plan  for
achieving one-stop permitting, which takes effect  in  April
1982.  The legislation defines one-stop permitting as  enabling
an applicant to "complete all necessary applications  at  one
time and location, or to supply enough information to  the
agency at one time and location so that each agency  can
process [it] . .  . [and] the applicant .  .  . [can] obtain
authorization."

     In addition,  agencies with "similar, related, or  inter-
related jurisdiction or authority" must develop  a  single
application form which all these agencies can review  "expedi-
tiousiy."  Agencies must also attempt to  use consolidated
hearings and joint permitting procedures  for state and federal
projects.  To enable state agencies to do this,  the  bill
authorizes them to enter into agreements  with other  state and
federal agencies.
Experience with the Reform

     Because the legislation is so  recent, most of  the  work  to
date has been planning.  The advisory council will  issue  an
interim report detailing progress on the  reforms  in  November
1981.

-------
                                                  Mississippi
ADDITIONAL COMMENTS

     Under the bill, the Mississippi Research and Development
Center was directed to design a "single or master application
form for all required permits, licenses, and other instruments
from agencies of the state."  An official from the Department
of Economic Development reported that this effort proved in-
feasible; one cannot design a form that is straightforward and
compact yet comprehensive enough for review bv all state agen-
cies.  Therefore, the current plan is to devise a master per-
mit information form that will enable applicants to find which
permits are necessary for their particular project.
STATE CONTACTS

Francis Geoghegan
Special Projects Officer
Department of Economic Development
P. 0. Box 849
Jackson, Mississippi  39205
(601) 354-6707

Charles Chisholm
Director
Bureau of Pollution Control
Department of Natural Resources
P. 0. Box 10385
Jackson, Mississippi  39209
(601) 961-5171

-------
                                               Decision-Making Deadlines
OVERVIEW

     All of Missouri's environmental  permits are issued within
the Missouri Department  of  Natural  Resources (DNR).   The DNR
is bound to comply with  decision-making  deadlines in reviewing
all air permits.  In  addition,  the  director of the Division of
Environmental Quality acts  as  an  informal  coordinator for
major projects requiring multiple DNR permits.  The  director
instructs the various permitting  branches  to synchronize their
review procedures in  order  to  shorten the  turnaround time.
DECISION-MAKING DEADLINES
FOR AIR PERMITS

     Missouri has adopted  decision-making  deadlines for the
review of all air pollution  permits.   Air  pollution permits
are issued by the Division of  Environmental Quality within the
Missouri Department of  Natural  Resources and include the dele-
gated PSD program.  For minor  permits  the  agency decision nust
be made within 90 days  of  the  filing of a  complete applica-
tion.  Permits for major emission  sources  must  be granted or
denied within 184 days  of  the  filing of a  complete applica-
tion.  These deadlines  have  been mandated  by regulation, not
by legislation.

-------
Missouri
STATE CONTACT

Robert J. Schreiber, Jr., Director
Division of Environmental Quality
Missouri Department of Natural Resources
2010 Missouri Boulevard
Jefferson City, Missouri  65102
(314) 751-3241

-------
                                                     Joint Application
                                                        Joint Hearing
                                               Decision-Making Deadlines
OVERVIEW

     Montana has established a  coordinated  review process for
major energy facilities.   The process  employs a master appli-
cation and joint hearings, and  streamlines  the number of state
and local decision-making  bodies  to  two.   The Department of
Natural Resources serves as coordinator  of  the process,  and
the Board of Natural Resources  serves  as  the  final decision
maker.  The Department of  Health  and Environmental Sciences
retains its authority to make permit decisions, although its
review process is coordinated into the larger process.
JOINT APPLICATION, JOINT  HEARING,
AND DECISION-MAKING DEADLINES  FOR
MAJOR ENERGY FACILITIES

     The Montana Major Facility  Siting  Act  (Mont.  Rev.  Codes
Ann. 75-20-101 et seq.) reduces  the  number  of  applications,
hearings, and decisions needed  to  obtain  the  requisite  state
and local permits for major  energy projects.   However,  the
process cannot properly be categorized  as one-stop because
there are three sets of hearings and two  distinct  decision
points.  An application must be  approved  first by  the Depart-
ment of Health and Environmental Sciences and  then by the
Board of Natural Resources before  the certification is
granted.

     A Certificate of Environmental  Compatibility  and Public
Need is required for construction  of the  following:  power-
plants of 50 megawatts or greater; coal conversion plants with
a capacity of 25 million  cubic  feet  of  gas  per day or greater;
facilities capable of producing  25,000  barrels of  liquid

-------
Montana                       130
hydrocarbons per day or more; any facility capable of utiliz-
ing or converting 500,000 tons of coal or more  per year; any
additions to the preceding categories over $10  million; any
uranium enrichment facility; all transmission lines  greater
than 230 kilovolts and transmission lines greater than 69  kil-
ovolts and over 10 miles long; and synthetic gas, water, or
liquid hydrocarbon product pipelines.  The certificate is  also
required for use of geothermal resources of more than 25 mil-
lion Btu per hour, and underground in situ coal gasification
plants.
Permits/Agencies Affected

     The Board of Natural Resources  (BNR) is the body  respon-
sible for issuing the certificate.   The Department of  Natural
Resources (DNR) serves as the staff  for the BNR and is  respon-
sible for conducting the review process and preparing  recom-
mendations for the BNR.  The Department of Health and  Environ-
mental Sciences (DHES) conducts independent reviews and  ren-
ders decisions on its permits, though the act specifies  review
schedules which coordinate the work  of the DHES and the  DNR.
Also, documentation prepared by the  DHES is included in  re-
ports prepared by the DNR.  The DHES has responsibility  for
air, water, solid waste, and hazardous waste permits.   The
statute requires the DNR to request  input from seven specific
state agencies (the Environmental Quality Council and  the
departments of Public Service Regulation; State Lands;  Com-
merce; Highways; Revenue; and Fish,  Wildlife, and Parks) and
the appropriate local agencies in preparing recommendations
for the board.  The state and local  agencies may participate
as interveners in the BNR hearing, but the board retains final
decision authority and can override  local ordinances.   Federal
agencies receive copies of the application but do not  partici-
pate actively in the review, although joint federal/state
reviews that also satisfy federal requirements may be
conducted.
Administrative Process

     The review process is initiated by the filing of a master
application with the DNR and DHES, which have 90 days to
determine whether it is complete.  Following the completion of
the application, the DHES conducts its reviews, and the DNR
prepares its report concurrently.  This report is also pre-
pared in compliance with the requirements of the Montana Envi-
ronmental Policy Act.  The DHES holds a single set of hearings

-------
                                                       Montana
for all of the permit programs  it  administers.   Permit deci-
sions are made by individual offices  within the DHES and must
be made within one year of  the  acceptance  of the application.
These decisions may be appealed before  the Board of Health.
Such appeals must be decided within  18  months of the date of
the original application.   In the  meantime,  the DNR prepares
the draft environmental assessment and,  if necessary,  the
environmental impact statement,  holds public hearings  to re-
ceive comments, and issues  the  final  report,  including recom-
mendations for the BNR on the application.  The statute re-
quires that these recommendations  be  given to the BNR  within
22 months of the acceptance of  a complete  application.

     After receipt of the DNR recommendations,  the BNR pre-
sides over contested case hearings in which state and  local
agencies as well as other interested  parties may participate.
The BNR must rule on the application  within 11  months  of re-
ceipt of DNR recommendations.
Experience with the Reform

     Since the process was established  in  1975,  Units 3 and 4
of the Colstrip coal-fired powerplant and  about  12  transmis-
sion lines have completed the process and  received  a  Certifi-
cate of Environmental Compatibility  and  Public  Need.   The
Kootenai Falls hydroelectric project is  now  in  the  review
process.
STATE CONTACT

Bob Robinson
Department of Natural Resources
  and Conservation
Facility Siting Division
25 S. Ewing
Helena, Montana  59620
(406) 449-4600

-------
                                                          Sfi
OVERVIEW

     Nebraska neither has a formal consolidated permit  pro-
gram, nor does it formally coordinate  the permitting  process.
Nonetheless, the state has streamlined the permitting process
through a variety of informal mechanisms.

     The Department of Environmental Control  (DEC)  is respon-
sible for issuing all water quality, air quality, and solid
waste disposal permits.  The DEC currently administers  the
federal NPDES program and is in the process of taking over the
federal RCRA program.  Moreover, the Water Pollution  Control
and Solid Waste Pollution Control divisions of the  DEC  were
recently combined into the Water and Waste Management Divi-
sion.  This division keeps a consolidated file for  all  water
and waste permit information and is exploring the possibility
of combining the two applications into one form.

     The DEC is partially constrained by deadlines  for  issuing
these permits.  Both air and water quality permits  must  be
approved or denied within 30 days after public notice has been
filed provided there is no significant amount of public  com-
ment.  When public comments are substantial, however, there
are no decision-making deadlines for issuing permits.

     The Department of Economic Development will arrange pre-
application meetings between the permitting agencies  and
industrial project sponsors who are new to the state.   DEC
staff members may act informally as liaison between an  appli-
cant and the permitting agencies by setting up meetings  and
following up the applicant's request for information.

-------
Nebraska                      134
STATE CONTACTS

Robert B. Wall, Chief
Water and Waste Management Division
Department of Environmental Control
301 Centennial Mall South
Lincoln, Nebraska  68509
(402) 471-2186

Gene Robinson, Chief
Air Pollution Control Division
Department of Environmental Control
301 Centennial Mall South
Lincoln, Nebraska  68509
(402) 471-2186

Dolores Wilson, Director
Industrial Development
Department of Economic Development
P. 0. Box 94666
Lincoln, Nebraska  68509
(402) 471-3774

-------
OVERVIEW

     The Nevada State Clearing House conducts prehearing con-
ferences for major projects at the request of the applicant.
These meetings include the applicant and representatives of
the state permitting agencies in a discussion of the project
characteristics and permit requirements prior to the filing of
an application.  The state has not made any other procedural
reforms in the environmental permit area.

     Most environmental permits, including those for air and
water pollution (NPDES), ground water use, and hazardous and
solid waste disposal, are issued by the Nevada Division of
Environmental Protection in the Department of Conservation and
Natural Resources.  The Clearing House is within the State
Planning Coordinator's office.
STATE CONTACT

Lou Dodgin
Division of Environmental Protection
Nevada Department of Conservation
  and Natural Resources
201 S. Fall St.
Carson City, Nevada  89701
(702) 885-4070

-------
                                                     Joint Application
                                                        Joint Hearing
                                               Decision-Making Deadlines
OVERVIEW

     New Hampshire has consolidated  regulatory proceedings for
major energy facilities.   The  Energy Facility Evaluation Com-
mittee has authority  over  the  required consolidated permit for
nonelectrical energy  facilities.   The Bulk Power Supply Facil-
ity Site Evaluation Committee  has  final authority over the
environmental and siting aspects  of  powerplant and transmis-
sion line permitting.  Both  committees utilize master applica-
tions, joint hearings, decision deadlines, and a comprehensive
state permit.
JOINT APPLICATION, JOINT  HEARING,  AND
DECISION-MAKING DEADLINES FOR  ENERGY
FACILITIES OTHER THAN  BULK POWER  FACILITIES

     The Energy Facility  Evaluation  Committee (EFEC)  is
authorized to conduct  joint reviews  and  issue final state site
permits for nonelectrical energy  facilities (N.H.  Rev.  Stat.
Ann. § 1G2-H).  The EFEC  is made  up  of 13  members  representing
11 different state permitting  agencies.   It includes  represen-
tatives from all agencies issuing  permits  for energy  develop-
ment and representatives  from  other  agencies that  have  an
interest in energy development but do not  have permitting
authority.

     The coordinated review process  incorporates use  of a
master application, joint notice  procedures, joint hearings,
and decision-making deadlines.  Within this coordinated review
process, the applicant must obtain approvals from  state agen-
cies prior to and as a condition  for the  issuance  of  the re-
quired comprehensive construction  and operation permit  by the

-------
New Hampshire                 138
EFEC.  An applicant that wishes to construct a  facility  other
than electrical generating stations and  power lines,  "to
extract, manufacture, or refine sources  of energy," must use
the consolidated review process.
Permits/Agencies Affected

     The coordinated review process coordinates  the  reviews  of
all state permitting agencies with jurisdiction  over an  energy
facility that falls within the statutory definition.   The
state permits involved cover air and water  pollution,  solid
waste, and wetlands protection.  The law requires  that an
applicant secure a permit from the EFEC.  A condition  for
granting of the EFEC certificate is the approval  (possibly
with conditions) of the state regulatory agencies.   The  local
authorities may offer testimony in the joint hearings, but
their approval is independent of the EFEC's decision.  Federal
agencies are not formally involved in the process, although
efforts are made to coordinate state and federal  proceedings.
Administrative Process

     The coordinated review process begins with  the  submittal
to the EFEC of a master application by  the applicant.   This
application is filed in lieu of all other state  agency  forms.
The application is forwarded to all agencies  with  jurisdiction
in the case.  The agencies and the committee  then  evaluate the
application and, if necessary, ask the  applicant to  supply any
omitted material.  Once the EFEC determines that the applica-
tion is complete, it must begin public  hearings  within  60
days.  The first session is strictly a  public  information
meeting, and the subsequent joint hearings are in  lieu  of all
other hearings that would be held by state agencies.  Agencies
that otherwise would conduct hearings are required to partici-
pate, and those that would not ordinarily hold hearings may
not take part.

     Agencies must make permit decisions and  submit  them to
the EFEC within seven months after the  application is deter-
mined complete.  Within 14 months after a completed  applica-
tion is filed, the EFEC must act on the comprehensive permit.
The EFEC can issue a comprehensive permit only if  three condi-
tions are satisfied.  First, no state agency  can have denied
the applicant a required authorization.  Second, the EFEC must
include terms and conditions imposed by other state  agencies
in its comprehensive permit.  Third, the committee must make

-------
                             139                  New Hampshire
findings of its own on  issues outside  the  scope  of  other agen-
cies' reviews, including  the impact  on  the development  of the
region, the environment,  and the  public  health,  and the abil-
ity of the applicant to construct and  operate the facility in
compliance with all permit conditions.
Experience with the Reform

     Since the law establishing  the  EFEC  and  the  coordinated
review process was adopted  in 1974 one  gasohol  plant  in Ports-
mouth has gone through the  entire joint review  procedure.   The
committee has considered a  number of other  energy-related
proposals but subsequently  decided that the proposed  facili-
ties did not fall within the statutory  definition of  an energy
facility.
JOINT APPLICATION AND JOINT
HEARING FOR POWERPLANTS
AND MAJOR TRANSMISSION LINES

     The Bulk Power Supply Facility Site Evaluation  Committee
(SEC) and the corresponding coordinated review  process  were
established in 1971 (N.H. Rev. Stat. Ann.  §  1G2-F).   The  same
state agencies that make up the EFEC are members  of  the SEC.
The SEC site review process is quite similar  to that  used  for
energy facilities other than powerplants and  transmission
lines and includes a master application, joint  hearings,  and a
comprehensive site approval decision by the  SEC.  This  approv-
al is necessary before the New Hampshire Public Utilities
Commission (PUC) can issue a Certificate of  Site  and  Facility.

     Applicants proposing powerplants over 50 megawatts or
transmission lines over 100 kilovolts and  over  10 miles in
length must receive SEC approval prior to  construction.
Permits/Agencies Affected

     The SEC site review process is part of a larger New
Hampshire PUC procedure for certifying electric power facili-
ties.  All state environmental permitting agencies are re-
quired to participate in the SEC coordinated review.  The SEC
will not approve an application unless all state environmental
requirements have been met and must give "due consideration"
to the views of municipal legislative bodies and planning

-------
New Hampshire                140
commissions.  Local governmental agencies are not required  to
participate in the joint review.  There  is no formal  federal
involvement.
Administrative Process

     Applications for a required PUC Certificate of Site and
Facility must be filed with the PUC at  least  two years prior
to construction.  The PUC and the SEC must hold a joint hear-
ing within 60 days of the application.  A single application
and a joint hearing are employed in place of  the independent
state agency procedures.  The SEC, like the EFEC, is bound by
the decisions, terms, and conditions of the state agencies in
its findings.  The SEC decision is conclusive on all issues of
siting, land use, and air and water quality.  These SEC
findings are submitted to the PUC, which must grant or deny
the certificate within sixteen months of application.  In
making its decision, the PUC considers  the SEC result and its
own conclusions on the issues of future demand and system
stability and reliability.
Experience with the Reform

     The Seabrook project is the only major facility to have
completed the full site review process since the joint
review's establishment in 1971.
STATE CONTACT

Russell Nylander
New Hampshire Water Supply
  & Pollution Control Commission
Health and Welfare Building
Hazen Drive
P. 0. Box 95
Concord, New Hampshire  03301
(603) 271-3503

-------
                                  JEW  SIB
                                              Decision-Making Deadlines
                                          Permit/Application Coordinator
                                                    Joint Application
                                             Over-the-Counter Processing
                                                  Computer Tracking
OVERVIEW

     New Jersey's most significant permitting reforms include
review deadlines for certain permits established by a state
"90-Day Review Law" passed by the legislature in 1975,  and
permit coordination under Executive Order No. 57 issued by the
governor in 1977.  In addition, the Department of Environmen-
tal Protection (DEP) has adopted a number of innovative admin-
istrative policies such as the use of a master permit applica-
tion form, a permit directory, and over-the-counter processing
of minor permits.  In 1980 New Jersey's DEP participated in a
task force on permit consolidation with the Region II EPA and
New York's Department of Environmental Conservation which
recommended ways to consolidate permits and to share computer
systems.
DECISION-MAKING DEADLINES

     The intent of the 90-Day Review Law (P.L.  1975 c.232)  and
Executive Order No. 57, which complements the statute,  is to
ensure that the DEP processes permit applications expeditlous-
ly.  Any applicant requiring one or more of the five permits
that the law covers is entitled to receive a decision on  his
or her permits within 90 days of the completed  application.
Permits/Agencies Affected

     The law applies to five categories of  state  permits
issued for construction projects:   Waterfront  Development
permits, Riparian Wetlands permits,  permits under the  Coastal

-------
New Jersey                    142
Area Facility Review Act (CAFRA), Stream Encroachment  permits,
and Sanitary Sewer Facilities permits.  The 90-Day  Law does
not apply to federally issued permits.

     Executive Order No. 57, which complements  the  90-day  Law,
extends the decision-making deadline by requiring that all DEP
construction permit applications deemed complete be acted  on
within the 90-day period.  -iHowever, a process was established
within the framework of the executive order to  exempt  certain
permits from the 90-day provision.  The DEP requested  and
received a number of exemptions:  solid waste registrations,
201 sewer grant discharge permits, and permits  associated  with
projects requiring a federal EIS.
Administrative Process

     For all these state permits except those for CAFRA,  the
DEP must render a decision within 90 days after the applica-
tion is complete.  For CAFRA permits the decision is due  with-
in 60 days of the required public hearing.  Time extensions
are available, however, since there is an exemption procedure
for "good cause."
Experience with the Reform

     The New Jersey DEP processes in excess of 10,000 new
construction permits a year.  Of these, staff estimate that
about 3,000 fall under the 90-Day Review Law.  DEP representa-
tives believe that the law and related reforms have signifi-
cantly reduced time delays and costs in the permitting
process.

     Air permits form a large category not covered by the 90-
Day Review Law.  DEP staff suggest that drafters of the  law
omitted air permits because they thought that the technical
aspects might require additional time.  In practice, however,
DEP officials say that air permits are consistently issued
within 90 days.
PERMIT/APPLICATION COORDINATOR

     A reform related to the 90-Day Review Law, Executive
Order No. 57 (1977), established a Cabinet Committee and a
Citizen Committee on Permit Coordination.  The governor re-
quested the two committees to oversee the implementation of

-------
                             143                     New Jersey
the 90-Day Law and to provide  information  to the public about
the permit process.  The DEP also  provides the assistance of
permit coordination officers within  the  department as a means
of simplifying the permit process.
Permits/Agencies Affected

     The coordination and  information  functions performed by
the DEP permit coordinators and  the  Cabinet  and Citizen Com-
mittees apply not only  to  the  five categories of permits under
the 90-Day Review Law (see discussion  above), but to all per-
mits administered by the DEP.
Administrative Process

     Under the order, state departments  must  report regularly
to the Cabinet Committee what  permit  applications (if any)
consistently miss the deadline,  which ones  require extensions,
and the reasons for  such extensions.   After reviewing this and
other data, the committee  is to  report or  recommend reforms to
the governor.

     For projects over $500,000  the applicant may request that
the Cabinet Committee coordinate permit  review.   The committee
may appoint a permit expediter from the  Office of Business
Advocacy, Department of Labor  and Industry,  who will set up
preapplication meetings, coordinate contacts,  advise the
applicant on requisite state,  regional,  and federal permits,
and suggest ways to  consolidate  hearings and  forms wherever
possible.

     In consultation with  the  Cabinet and Citizen Committees
on Permit Coordination, the state has published a Detailed
Directory of State Programs for  Regulating  Construction, which
lists all permits required by  the state  for construction proj-
ects, the department that  issues the  permit,  the purpose of
the permit, its statutory  authority,  the type of activity it
regulates, and the titles  and  numbers of staff who can assist
applicants.  The directory also  lists regional permits (such
as those for coastal or critical areas)  and federal permits.
The DEP is required  by law to  publicly distribute at least
monthly a bulletin which lists pending applications for con-
struction permits and the  status of review  of those applica-
tions.  In addition  to indicating application status,  the DEP
Bulletin is used as  the computer tracking document to inform
the public of permit decisions,  public hearing dates,  press
releases, etc.  The  DEP publishes its own Easy Access guide to

-------
New Jersey                   144
the department, which  lists by  subject  area  staff names,
titles, and numbers.   It  names  the  Office  of Cultural and
Environmental Services  in  the DEP a central  information source
on environmental regulations.   Thus if  an  applicant is unsure
about whom to call even after reading  the  directory and guide,
he or she could call the  Office of  Cultural  and Environmental
Services for assistance.
Experience with the Reform

     Although it  is difficult  to  evaluate  specifically the
impact of these reforms,  DEP  staff  state  that better informa-
tion and improved coordination  have  made  the  permit applica-
tion process faster and  more  efficient,  especially for larger
projects.
JOINT APPLICATION

     The DEP has developed  master  forms  for  obtaining informa-
tion from applicants.   The  applicant  or  the  state-appointed
permit expediter uses a "Master  Permit  Information Form" to
clarify features of  the proposal.   The  form  is circulated to
the appropriate permitting  divisions, and  their staffs decide
what permits are required.   Next,  the applicant completes a
Standard Application Form CP-1,  which is used for construction
and discharge permits.   The Standard  Application Form has
taken the place of more than 20  separate application forms and
is included in a booklet which  is  a one-source document of
information on the DEP's permitting process.   It includes
general background information  on  DEP permitting, contact
phone numbers and addresses,  legal citations, and specific
requirements for each permit application.   The CP-1 form is
designed to be xeroxed  and  given to different permit programs
so that processing proceeds concurrently.   DEP staff use hand-
written response forms  for  certain permits as opposed to typed
letters to advise applicants of  the completeness of their
submissions, a practice that has saved  an  average of one week
in response time.
OVER-THE-COUNTER  PROCESSING

     For minor  stream  encroachment,  sewer extension,  and
riparian permits  that  meet specific  criteria,  applicants can

-------
                              145                    New Jersey
receive same-day or 24-hour  service.   Over-the-counter permit
applications are handled by  appointment  only,  and application
requirements are essentially  the  same  for  all  projects.
ADDITIONAL COMMENTS

     DEP and federal agency  staff  meet  regularly  to discuss
projects under joint authority.  The  major  purposes of this
effort are to identify key staff persons, review  procedural
matters, and discuss potential  conflicts.
Federal/State Task Force on
Permit Consolidation and
Computer Tracking

     In 1980 the New Jersey DEP,  the  New  York  Department of
Environmental Protection, and  the  Region  II  EPA established a
task force to recommend ways to  improve state  and  federal
permit processes and to share  environmental  information.  The
task force met more than a dozen  times during  1981 and issued
two interim reports.  The final  report, which  was  due  in late
1981,  will make specific recommendations  for permit consolida-
tion and joint hearings as well  as  suggest ways to share and
expand the computer systems that  the  Region  II  EPA,  New York,
and New Jersey are already using.
STATE CONTACTS

Lawrence Schmidt, Chief
Office of Environmental Review
State of New Jersey
Department of Environmental Protection
Trenton, New Jersey  08625
(609) 292-2662

Fred Schultz
Office of Environmental Review
State of New Jersey
Department of Environmental Protection
Trenton, New Jersey  08625
(609) 292-2662

-------
New Jersey                    146
William McCarthy
Permit Coordination Officer
State of New Jersey
Department of Environmental Protection
88 East State Street
Trenton, New Jersey  08625
(609) 292-4944

-------
                                                Decision-Making Deadlines
                                            Permit/Application Coordinator
OVERVIEW

     Although New Mexico  has  not  implemented a major permit
coordination program,  the state has instituted organizational
and procedural mechanisms which serve to facilitate the per-
mitting processes.  The Health  and Environment Department, for
example, has strict decision-making deadlines for its air and
water permits, and the governor of New Mexico has initiated an
effort to coordinate  the  federal  and state permitting process.

     Coordination among the  state permitting agencies occurs
on an informal basis.  Applicants are encouraged- by each per-
mitting office to participate in  preapplication conferences,
and a handbook describing permit  requirements for natural
resources development  was recently published.

     In addition, several staff members noted that the struc-
ture of the Water Pollution  Control Commission and the Coal
Surface Strip Mining  Commission promotes interdepartmental
coordination.  These  commissions, which are responsible for
setting policy and establishing regulations in their respec-
tive areas, are composed  of  representatives from a cross-
section of state agencies.
DECISION-MAKING DEADLINES
     New Mexico has established  regulatory deadlines for
several of its environmental  permits.   The ground water dis-
charge permit must be approved or  rejected within 60 days from
the time the application  is complete.   The state air quality

-------
New Mexico                    148
permit carries a deadline of  30  days  from the time the com-
plete application is received.   The  Health and Environment
Department does not have a deadline  for  issuing the state
radioactive material permit,  but  the  state aims to complete
the process in half the time  taken by the Nuclear Regulatory
Commission.
PERMIT/APPLICATION COORDINATOR
FOR FEDERAL AND STATE PERMITS

     The governor of New Mexico  recently  established by execu-
tive order a task force to explore  alternatives for coordinat-
ing the "permitting review processes  of  the state and the
various federal agencies to  provide timely, accurate permit
reviews without altering or  impeding  the  authority vested by
the statutes and regulations  in  the various state and federal
agencies."  The task force is composed of the secretaries of
the departments of Health and Environment,  Energy and
Minerals, and Natural Resources,  as well  as the chairman of
the Public Service Commission and an  assistant to the
governor.

     The governor has submitted  a proposal  to the federal
Department of Energy requesting  funds for a staff assistant to
the task force.  The staff assistant  would  work closely with
state permitting agencies to  help them  implement reforms,
develop federal/state permit  review agreements, coordinate the
state's review process, oversee  state permit directory activi-
ties, and act as liaison between the  state  permitting agencies
and industry.

     To date, the state has  not  been  able to obtain the fund-
ing, and therefore the task  force's activities are suspended.
STATE CONTACTS

George Scudella, Chief
Resource  Bureau
Energy and Minerals  Departmen
P. 0. Box 2770
Santa Fe, New Mexico  87501
(505) 827-3326

-------
                              149                   New Mexico
Cubia Clayton, Assistant Director
Environment Improvement Division
Health and Environment Department
P. 0. Box 968
Santa Fe, New Mexico  87504-0968
(505) 827-5271 Ext. 244

-------
                                                   One-Stop Permitting
                                               Decision-Making Deadlines
                                           Permit/Application Coordinator
                                                     Joint Application
                                                      General Permit
                                                    Computer Tracking
OVERVIEW

     New York has  instituted a one-stop permitting process
which the Department  of  Environmental Conservation (DEC) ad-
ministers and which applies  to major projects other than steam
powerplants.  The  New York State Board on Electric Generation
and the Environment (siting  board)  oversees a similar permit
process for steam  powerplants.  Other reforms that New York
has adopted include use  of application coordinators, specific
deadlines for agency  decisions,  joint applications, consolida-
tion of forms, general permits,  and computer tracking of per-
mits.  For energy  projects,  New York has instituted master
energy plans and a public  participation fund.

     Additionally, throughout 1980, representatives from the
New York DEC, the  New Jersey Department of Environmental Pro-
tection, and the Region  II EPA formed a permit consolidation
task force which met  regularly to research and recommend ways
to streamline permitting and to share environmental data and
computer systems.
ONE-STOP PERMITTING  AND  DECISION-
MAKING DEADLINES FOR PROJECTS
OTHER THAN POWERPLANTS

     All construction and  development projects (other than
major steam electric generating facilities) that require more
than one environmental permit fall under New York's Uniform
Procedures Act  (ECL, § 70-0107),  which provides for one-stop
review of applications for regulatory permits.  A similar
review process  applies to  major steam electric generating

-------
New York                     152
facilities under Article VIII of the Public  Service Law.   The
DEC processes all permits concurrently and makes  a single
decision following a public hearing on the proposal.


Permits/Agencies Affected

     The DEC coordinates the 22 environmental permits  that tlae
state issues, except those for major electric generating
facilities, which fall under the jurisdiction of  the Mew York
State Board on Electric Generation and the Environment.  The
one-stop process applies to all categories of state permits
and federal permits that are administered by the  DEC.

     New York issues its own NPDES permits (Clean Water Act),
underground injection control permits (Safe  Drinking Water
Act), and dredge and fill permits (Clean Water  Act), and has
partial authority for permits under the Clean Air Act  and  RCRA
(Phase I).
Administrative Process

     Preliminary screening by the DEC of the applicant's pro-
posal identifies which environmental permits are  necessary.
The New York Uniform Procedures Act sets deadlines  for  the
agency's review and decision on the construction  or develop-
ment project and requires a hearing to be held  if issues
raised by the public cannot be otherwise resolved.  Where the
Act requires a hearing, the DEC must hold it between CO and 90
days after the completed application is filed and must  issue a
decision on major projects within GO days after the close of
the hearing.  For minor projects the DEC has 45 days to rule
on the application after the hearing is completed.

     Where no hearing is necessary, applicants may  request a
less formal decision conference.  After the conference, the
DEC must issue a decision within five days, although an
applicant who is dissatisfied may request a full  hearing.
Experience with the Reform

     By handling all the applicable state and federal permits
in one administrative process and one hearing (where re-
quired) , DEC staff expedite the application process consider-
ably.  According to staff, the DEC processes about 25,000 per-
mits or reapplications each year, of which about 10,000 or

-------
                              153                      New York
fewer are for new facilities.   However, many  of  these  permits
are for minor sources such as wells.   Only  a  small  number (10
percent) of projects require multiple  permits  and planning
under the one-stop siting process,  but these  projects  repre-
sent a large commitment of staff  time.  Because  of  their  size
and complexity, these projects  also tend  to have significant
environmental impacts.
PERM IT/APPLICATION COORDINATOR

     New York has taken two steps beyond  the  Uniform  Proce-
dures Act to further streamline  its permitting  process.   All
major projects are assigned a specific project  coordinator  at
the outset to serve as a contact and  to  try to  expedite  the
review process.  In addition, major projects  are  passed
through a "clearinghouse" review which brings environment-
related agencies outside the DEC into the one-stop  process.
Permits/Agencies Affected

     These coordination efforts apply  to all environmental
permits issued in New York, including  the  22 permits  admin-
istered by the DEC and, when required, approvals  issued  by the
Adirondack Park Agency, Department of  Health, and Office of
Parks and Recreation (historic preservation).
Administrative Process

     A project coordinator is assigned to a project after  the
applicant or potential applicant contacts the DEC.  Each pro-
gram with jurisdiction assigns an individual to review  the
project in order to identify permit requirements and  identify
potential problems.  The project coordinator relavs these
comments and other information between the agencies,  the ap-
plicant, and the interested public.  The coordinator  also
attempts to resolve issues between public objectors and the
applicant before a decision is made about whether or  not a
public hearing is required.  A hearing is held only if  there
is public objection to the project.

     The "clearinghouse" review simply means that all environ-
mental reviews, not only those issued by the DEC, are handled
with one application,  hearing, and decision.

-------
New York                      154
Experience with the Reform

     The DEC began using project coordinators in the middle of
1981.  DEC staff state that these modifications have been  well
received by both applicants and the general public.
ONE-STOP PERMITTING AND
DECISION-MAKING DEADLINES
FOR POWERPLANTS

     Under legislation first passed in 1972 and re-enacted
with procedural changes in 1978 (N.Y. Pub. Service L.  §§  140
et seq.), the New York State Board on Electric Generation and
the Environment (siting board) has complete and overriding
authority for electric generating facilities of 50,000 kilo-
watts or more.  The siting board consists of the Chairman of
the Public Service Commission (PSC); the commissioners of the
state departments of Environmental Conservation, Commerce, and
Energy; and a local representative who is appointed by the
governor and is from the area affected by the proposed plant.
The siting board issues a Certificate of Environmental Compat-
ibility and Public Need.  This certificate differs from certi-
ficates issued by many other states in that it is the  primary
vehicle for evaluating environmental impacts of the project.
Permits/Agencies Affected

     The one-stop siting process for powerplants covers all
the permits that the DEC issues for construction and develop-
ment projects, but in the case of powerplants it is the siting
board, not the DEC, which coordinates  the one-stop procedure
and makes the final decision on the acceptability of the
project.
Administrative Process

     Project sponsors for proposed electric facilities of
50,000 kilowatts or more apply to the siting board  for the
Certificate of Environmental Compatibility and Public Need.
Deadlines in Section 143 of the Public Service Law  require
that within 60 davs of receipt of the application,  the siting
board determine whether the information is complete enough  to
docket.  Within a "reasonable time" after docketing, the board
must hold the prehearing conference and public hearing.  The

-------
                             155                       New York
final decision  is due  from  the  board  no  less  than 24 months
after the application  has been  determined  to  be  complete.

     When reviewing  applications  for  steam  electric  generating
stations, the siting board  is bound by the  latest State Energy
Master Plan  (SEMP) with  respect to its determination of need
for a facility.  The SEMP is developed by  a state energy
board, which is required to consider  economic growth;  techno-
logical change; conservation; the health,  safety,  and  welfare
of the .public;  and the impact of  alternative  energy  sources
and conservation on  the  economy and on the  quality of  the  en-
vironment.   The State  Energy Law  provides  for public partici-
pation in the hearings on the SEMP, including reimbursement of
intervener's costs for expert witnesses  and consultant fees,
but not for  attorney's fees.  The powerplant  siting  law also
makes provision for  reimbursement of  intervener  costs.

     As part of the  powerplant  siting process, the siting
board has also  experimented with  holding /joint hearings and
using joint  forms for  state and federal  environmental  impact
statements with the  Nuclear Regulatory Commission.   A  member
of the Department of Public Service described these  joint
efforts as productive, even though the applications  in the two
cases in which  joint hearings were conducted  were  withdrawn
for other reasons.   Similarly,  the siting board  has  developed
joint state/federal  applications  for  Section  401 and 404 per-
mits under the  Clean Water  Act.
Experience with the Reform

     Since the Power Plant Siting Law's enactment  in  1972,
eight applications have been considered.  The siting  boards
have certified four of these, and four were either withdrawn
or denied.  No applications have been considered under  the act
as amended in 1978.
JOINT APPLICATION

     Although under federal legislation the U.S. Army Corps
of Engineers (COE) has ultimate authority to issue dredge and
fill permits under the Clean Water Act, the DEC and the COE
have developed a joint permit application form and coordinat-
ing procedures for those permits.  Thus an applicant may sub-
mit a form to either agency alone, and that agency will coor-
dinate review with the other agency and channel the applica-
tion into the one-stop siting process.  The DEC has estab-
lished similar procedures with joint forms and review with

-------
New York
156
other state agencies whose jurisdictions  overlap,  such as the
departments of Health and Transportation  and  the  Adirondack
Park Agency.  Thus, as part of  this  process,  the  DEC has
simplified and consolidated a number of different  application
forms.
GENERAL PERMITS

     With general permits,  the  DEC  can  review  and  approve the
environmental impacts of a  class  of  activities as  a whole
instead of conducting permit  reviews  and  issuing  approvals for
each project within a particular  category.   General permits
are issued for projects which are either  caused by extraordi-
nary natural occurrences such as  flooding or ice  damage,  or
which have been demonstrated  to generically  pose  little or no
threat to natural resources.  The latter  category  includes
certain dredging or filling projects, and maintenance or re-
placement, in kind, of docks, bulkheads,  etc.
Permits/Agencies Affected

     The Department of Environmental  Conservation is the only
agency using general permits.
Administrative Process

     The DEC publishes a  notice  of  intent  to issue a general
permit, reviews comments,  and  issues  the  general permit by
notice in newspapers.  In  some cases,  applicants continue to
file a separate application  and  are told  that work proposed
falls under a general permit.  The  project sponsor must notify
the DEC of the proposed project.  No  further action is
necessary.
Experience with  the Reform

     To date, New York  has  issued  54 general  permits.   General
permits have  eliminated  400  to  2,000 permits  each year,  de-
pending on the amount of  flooding  or ice  damage occurring.
Use of this mechanism allows  a  smaller staff  to devote more
time to review of significant projects.

-------
                             157                       New York
ADDITIONAL COMMENTS
Federal/State Task Force
on Permit Consolidation
and Computer Tracking

     Suggestions for sharing of computer  data  and  increased
cooperation in issuing permits were  the main products  of  a
task force formed in 1980 by the New York DEC,  the New Jersey
Department of Environmental Protection, and  the  Region II  EPA.
Representatives from these agencies  met more than  a dozen
times throughout the year to study ways to  improve state  and
federal permit processes.  For example, the  Region II  EPA  is
developing a "SCOPE" system to track NPDES,  RCRA,  UIC  (under-
ground injection), and other permits, while  the  DEC's  system
tracks NPDES and ground water permit issuance  and  compliance.
Region II and the DEC have arranged  to share some  of this
data.  The task force has produced two interim reports on
permit consolidation and information exchange.   One partici-
pant observed that not as much progress was  possible on state/
federal permit consolidation because the  legal deadlines and
procedures for issuing federal permits were  inflexible and did
not allow coordination with state procedures.
STATE CONTACTS

Louis M. Concra, Jr., Director
Division of Regulatory Affairs
New York State Department of
  Environmental Conservation
50 Wolf Road
Albany, New York  12233-0001
(518) 457-7418

John Smolinsky (powerplant siting)
Chief Generating Facilities Analyst
Office of Environmental Planning
Department of Public Service
3 Rockefeller Plaza
Albany, New York  12223
(518) 474-53G8

-------
                                            Permit/Application Coordinator
                                                    Computer Tracking
                                                     Joint Application
OVERVIEW

     The Office  of  Regulatory Relations (ORR) was created in
January 1980  by  the North Carolina Department of Natural Re-
sources and Community  Development (DNR-CD) in order to coordi-
nate the department's  regulatory activities.  In addition, the
ORR also serves  to  provide permit applicants with a central
place to obtain  information.

     The DNR-CD  Office  of Coastal Management, in conjunction
with the Wilmington, North Carolina,  district office of the
U.S. Army Corps  of  Engineers,  has developed a consolidated
coastal permit application process.   Furthermore, the district
Corps office  has  issued a general Section 404 permit.
PERMIT/APPLICATION COORDINATOR

     In addition  to providing information services to appli-
cants, and coordinating  agency  reviews,  the ORR is committed
to assessing and  recommending changes  in regulatory programs
and processes.  Any potential permit  applicant may contact the
ORR and request assistance.
Permits/Agencies Affected

     The DNR-CD issues most  of  North  Carolina's environmental
permits, including  the delegated  NPDES  and PSD permits and the
state's major coastal area management permit.   The Department
of Human Resources  is responsible for issuing  hazardous and
solid waste permits and administering Phase I  of RCRA.  The
Department of Administration  issues  the state  easement to fill

-------
North Carolina                160
in coastal areas.  The ORR provides information on these state
permitting programs and works to coordinate state authorities
as well as, to a more limited extent, federal and local regu-
latory authorities.
Administrative Process

     The ORR is divided into the following four sections:
Permit Information and Assistance, Environmental Assessment,
Economic Assessment, and Administrative Procedures Act Coordi-
nation.  The Permit Information and Assistance section is most
directly involved in permit coordination activities and pro-
vides the following types of services on an informal basis:

       •  A central location and contact for information
          regarding departmental permits and regulatory
          functions.  The office recently published an
          Environmental Permit Directory.

       •  Assistance to applicants in scheduling and
          coordinating the various regulatory processes
          for complex or multi-permit projects.

       •  A forum for the discussion, clarification, and
          resolution of issues and concerns between an
          applicant and regulatory agencies prior to and
          during the permitting process.

       •  Preparation of periodic status and monitoring
          reports regarding departmental permitting and
          regulatory activities.

       •  Establishment of more efficient and effective
          coordination among permit, A-95, and environ-
          mental review processes.

       •  Evaluation and recommendation of improvements
          in regulatory relations and procedures among
          related state and federal permitting agencies.

       •  Review of proposed regulations in regard to
          their relationship and compatibility with
          department-wide permitting and regulatory re-
          sponsibilities and their impact on applicants.

-------
                              161                North Carolina
Experience with  the Reform

     The Office  of Regulatory  Relations  became  fully  function-
al on June 1, 1980, and  responded  in  an  initial  three-month
period to over 100 requests  for  permit information  and  assis-
tance from individuals,  industry,  local  governments,  and  state
agencies.  The office organizes  approximately two  to  three
preliminary permit coordination  meetings for clients  each
month.  Within the last  year the office  has  provided  the  fol-
low-through for  resolving 20 permit  review conflicts  between
applicants and issuing agencies.
COMPUTER TRACKING

     In addition to providing  the  services  described  above,
the ORR is currently assisting in  the  development  of  a
computer-based permit application  tracking  system.  Water  and
air quality permits are  in  the system  now,  and  other  depart-
ment permits will be added  in  the  future.   The  ORR  has also
developed a computer-based  A-95 and  EIS  tracking system which
notifies applicants of required permits.  Both  of  these sys-
tems will be part of an  overall state  automated data  process-
ing (ADP) system.  When  fully  operational,  the  system will be
coordinated through the  Office of  Regulatory  Relations.
PERMIT/APPLICATION COORDINATOR
AND JOINT APPLICATION FOR
DREDGE AND FILL PERMITS

     The DNR-CD Office of Coastal Management and  the  Wilming-
ton District Corps of Engineers have developed  coordinating
procedures for applicants that require permits  from both agen-
cies.  All applicants benefit from joint application  forms and
joint bimonthly coordinating meetings.

     Certain projects may qualify under the Corps' general 404
permit (issued January 27, 1981) and thus  not require  separate
federal permits.  The Corps' general permit differs from
state-issued general permits in that eligibility  for  the per-
mit is not self-certified by the applicant and  the applicant
must still obtain the requisite state permits.

     The Corps has broad discretion to determine  eligibility
under the general permit.  Eligible projects usually  include
maintenance of existing projects as well as new projects such

-------
North Carolina                162
as boat channels and basins, bulkheading and filling, marinas,
canals, and cable and pipeline crossings.   Projects  that  are
not eligible include those which have significant environmen-
tal impacts, involve unresolved state and  federal agency  con-
flicts, adversely affect habitats for endangered species  or
sites in the National Register of Historic  Places, or would
adversely affect wild and scenic rivers.
Permits/Agencies Affected

     Applicants submit only one application for one or more of
the following permits and certificates:  The Army Corps  of
Engineers' permits under Section 404 of the Clean Water  Act
and Section 10 of the Rivers and Harbors Act;  the Office of
Coastal Management's state dredge and fill permit and coastal
area management (CAMA) permit; the Department  of Administra-
tion's easement to fill; and the Division of Environmental
Management's Section 401 water quality certification.  The
following nine state agencies may review the application and
participate in the bimonthly meetings:  the Department of
Transportation; the Department of Human Resources; Archives;
the Department of Administration; and within the DNR-CD,  the
Division of Community Assistance, the Division of Land Qual-
ity, the Division of Environmental Management, the Office of
Coastal Management, and the Division of Wildlife Resources.
At a federal level, the regional offices of the Corps, the
EPA, the Fish and Wildlife Service, and National Marine  Ser-
vices review the application and participate in meetings.
Administrative Process

     Applicants submit copies of the joint application  to  both
the Corps' district office and  the state  field office of
Coastal Management.

     If the Corps determines that an application qualifies  for
the general permit, only the state field  office conducts an
on-site investigation and writes up a report.  If  the general
permit does not apply, the Corps and the  state conduct  either
joint or separate visits and write up reports.  The applica-
tion and report(s) are then circulated  to the nine state
offices and four federal field  offices  named above for
review.

     Applicants receive separate approval for each permit.
Therefore, from one application, an applicant may  receive  up
to four separate permits and one certification.

-------
                              163                North Carolina
     If the general permit  applies,  projects  that  receive
state approval  for CAMA or  state  dredge  and  fill automatically
receive federal approval  for  Sections  404 and 10 permits.  The
Corps reviews state reports and may  submit recommendations to
the state; however, it does not undertake an  independent  in-
vestigation.  In addition to  receiving notification  of permit
approval from the state,  the  applicant receives notice from
the Corps that  the project  is covered  under  the general
permit.

     The district Corps office also  conducts  bimonthly coordi-
nation meetings to which  representatives of  the nine state
agencies and four federal agencies are invited.  These meet-
ings are used to discuss  policy,  regulations,  procedures,
problem permits, and enforcement.
Experience with the Reform

     Both the Corps and the state office of Coastal  Management
feel that these coordinating procedures have  been  very  suc-
cessful in shortening the permitting process.   State officials
estimate that since the general permit was issued, the  average
permitting time has been reduced by three weeks.   This  process
has reduced the number of contacts an applicant must make  and
has made the permitting process less confusing.  In  addition,
the general permit has greatly reduced the burden  on district
Corps staff.
ADDITIONAL COMMENTS

     On a project-specific basis, the DNR-CD has experimented
with an innovative program for coordinating permit activities
and involving the public in the decision-making process.   In
response to a proposal to build an oil refinery, the DNR-CD
set up several committees to expedite the permitting process.
A citizens' advisory committee was created to represent  the
public in the decision-making process and to act as liaison to
the interested public.  A Technical Steering Committee was
established to serve as a state contact for permit coordina-
tion, to act as a technical resource, and to coordinate  with
the project applicant.  Finally, a state government interagen-
cy task force was set up to ensure consideration of the  in-
terests of other state departments.

     In addition, the permitting agencies and the applicant
agreed to lay out a decision schedule for issuance of the nine

-------
North Carolina                164
required permits following completion of the EIS.  The appli-
cant withdrew its application due to the world oil glut;
therefore the process was never completed.  However, the ORR
(which was created during the middle of this process) intends
to use this coordinated process for other industrial projects
wishing to locate in the state.
STATE CONTACTS

Roger Schecter, Chief
Permit Information and Assistance Section
Office of Regulatory Relations
North Carolina Department of Natural
  Resources and Community Development
P. 0. Box 27687
Raleigh, North Carolina  27611
(919) 733-6376
John Parker, Permits Coordinator
Office of Coastal Management
North Carolina Department of Natural
  Resources and Community Development
P. 0. Box 27687
Raleigh, North Carolina  27611
(919) 733-2293

-------
OVERVIEW

     In North Dakota  all  state  environmental permits (except
those for pesticides  and  mining)  are  issued by the Department
of Health.   In addition,  North  Dakota has  pursued delegation
of all possible  federal permitting  programs and now adminis-
ters the NPDES,  PSD,  RCRA Phase I,  and SDWA programs.   As a
result, permit applicants generally work with only one depart-
ment at one  level of  government.

     The Department of Health has attempted to streamline
permitting through procedural mechanisms as well.  The office
administering PSD programs  has  deleted its requirement for a
public hearing on every application.   Effective January 1982,
public hearings  will  be held only on  request.  Department of
Health staff also encourage applicants to  participate  in pre-
application  conferences.   These conferences are generally held
for larger project applicants and conducted informally and
sequentially with each permitting office.

     North Dakota passed  siting legislation in 1975 which gave
the Public Service Commission (PSC) the authority to site
major energy facilities.   Although  it does not prescribe a
one-stop permitting process, the  legislation does provide for
consideration of environmental  criteria and for consultation
with other permitting offices during  the siting process.  The
original legislation  called for the designation of a site
inventory by the PSC, but this  concept was abandoned as im-
practical.   However,  the  PSC does produce  a computerized map
inventory of "avoidance and exclusion areas" for energy facil-
ity sites.

-------
North Dakota                  166
STATE CONTACTS

Gene Christiansen, Acting Administrator
Department of Health
Chief of Environmental Control
State Capitol
Bismarck, North Dakota  58505
(701) 224-2371

Dana Mount, Director
Division of Environmental Engineering (PSD)
Department of Health
State Capitol
Bismarck, North Dakota  53505
(701) 224-2348

Wallace Owen, Chief Engineer
Public Service Commission
State Capitol
Bismarck, North Dakota  58505-0165
(701) 224-2400

Vern Fahy
State Engineer
State Water Commission
900 East Boulevard
Bismarck, North Dakota  58505
(701) 224-2750

-------
                                            Permit/Application Coordinator
                                                     Joint Application
OVERVIEW

     In 1974 Ohio  instituted  a  one-stop siting and coordina-
tion process for powerplants  and transmission lines.  The Ohio
Power Siting Board  has  jurisdiction over the siting of power-
plants and coordinates  extensively with other permitting
agencies.

     The Ohio Environmental Protection Agency (OEPA), which
issues NPDES and PSD  permits  as well as state air, water, and
waste permits, has  also streamlined permit procedures in a
number of informal  ways.   The Water and Land Pollution Control
offices of the OEPA are decentralized into five regional field
offices, and the Air  Pollution  Control Office has sixteen
offices.  Project  sponsors submit their applications directly
to the field offices.   Frequently the field office's recommen-
dation will expedite  the  permit application through the cen-
tral office.

     In addition,  if  a  new project requires both air and water
permits, it may receive combined approval for both permits
in a single document.   Finally,  the Office of Air Pollution
Control uses a computer to track the status of air monitoring
permits.
PERMIT/APPLICATION COORDINATOR
AND JOINT APPLICATION  FOR  PQWERPLANTS

     The Ohio Power  Siting Board  was established by leg-
islation in  1972  (Ohio Rev.  Code  Ann. Ch.  4906) and assumed
jurisdiction over the  siting of  powerplants and transmission

-------
Ohio                            168
lines in 1974.  A utility  that  plans  new  construction submits
only one application for all permits  to  the siting board.
However, each agency issues its  own permit  to  the utility  and
conducts separate administrative  proceedings.   The one permit
that is issued by the board is  the Certificate of Environmen-
tal Compatibility and Public Need.  Electric power generating
plants of 50 megawatts or  more,  gas transmission  lines capable
of operating at 125 pounds per  square inch  or  more,  electric
transmission lines capable of transmitting  125 kilovolts or
more, and associated facilities  must  obtain the certificate
in addition to OEPA permits before commencing  construction.
Any generating plant using solid  waste as fuel is exempted
from the certificate requirement.
Permits/Agencies Affected

     The board consists of  the  directors  of  the departments of
Health, Environmental  Protection,  Economic  and Community
Development, and Natural Resources,  and  the  Public Utility
Commission  (PUC); a representative of  the public who must be
an engineer; and four  nonvoting  legislative  members.  The
chair of the PUC is the chair of  the board.

     The board coordinates  its  reviews and  decisions with nine
other state agencies:  the  OEPA;  the departments of Natural
Resources,  Energy, Economic  and  Community Development,  Health,
Transportation, and Agriculture;  the PUC;  and the Ohio Histor-
ical Society.  Local government  agencies  and officials are
integrally  involved in the  siting  process,  although their
authority can be pre-empted  by  the board.
Administrative Process

     An application  for  the  certificate  must  be filed two
years in advance  for  powerplant  construction  and one year in
advance for  the construction  of  transmission  lines.   Upon
determining  that  the  application is  complete,  board  staff
distribute copies of  it  to all  relevant  state  agencies and
local officials.  A  public hearing  is  scheduled 60 to 90 days
after the application  is  deemed  complete.   Board staff review
the application and  prepare  a report of  recommended  findings.
This report  must  be  filed  15  days prior  to the hearing.   The
hearing, which includes  an adjudicatory  hearing and  a public
hearing, is  held  before  an administrative  law  judge.  The
judge submits a recommendation  to the  board,  which makes its
final decision by majority vote  "within  a  reasonable time."

-------
                             169                          Ohio
     Throughout the certification  process  the  board  works
closely with affected local and  state  agencies.   Affected
local agencies are notified of preapplication  conferences with
the applicant.  These agencies are  also  sent copies  of  the
application, although they must  file a notice  of  intervention
to be made parties to the adjudicatory hearing.   The board's
staff includes five coordinators to the  following state agen-
cies:  the departments of Natural  Resources, Health,  Energy,
and Economic and Community Development;  the OEPA;  and the PUC.
These agencies issue specific permits  as required but receive
the application from and coordinate closely with  the siting
board.  The board is empowered to  pre-empt  local  zoning.

     The legislation encourages  the board  to hold joint pro-
ceedings with other state or federal agencies.  To date,  joint
hearings have not been feasible.
Experience with the Reform

     Since 1974 two nuclear generating  units  have  been  certi-
fied.  An application for two other  nuclear units  was  with-
drawn subsequent to the hearings on  it.  Most  of  the  commis-
sion's activities have involved electric transmission  lines.
STATE CONTACTS

Robert Stamper, Secretary
Ohio Power Siting Board
580 South High Street
Suite 300
Columbus, Ohio  43215
(614) 466-6422

Charles Taylor, Chief
Division of Air Pollution Control
Ohio Environmental Protection Agency
361 East Broad Street
Columbus, Ohio  43216
(614) 466-6116

Ernie Rotering, Chief
Division of Wastewater Pollution Control
Ohio Environmental Protection Agency
361 East Broad Street
Columbus, Ohio  43216
(614) 466-7427

-------
Ohio                          170
Donald Day, Chief
Division of Land Pollution Control
Ohio Environmental Protection Agency
361 East Broad Street
Columbus, Ohio  43216
(614) 466-8934

-------
                                              Decision-Making Deadlines
OVERVIEW

     Permit reform in Oklahoma has been  limited  to  the  infor-
mal coordination of permit applications  among  offices within
the Oklahoma State Department of  Health  and  to the  establish-
ment of regulatory deadlines for  air  quality permits.   The
majority of environmental permits are issued by  the offices  of
the Oklahoma State Department of  Health,  specifically the
Water Facilities Engineering Service  (municipal  treatment),
Air Quality Service (air pollution),  and  Industrial and Solid
Waste Service (solid and toxic wastes).   These offices  issue
permits independently.  For projects  requiring multiple per-
mits from the Department of Health, an informal  meeting is
held with the developer and the appropriate  offices to  deter-
mine which permits are required and to exchange  information.
Four other state agencies issue environmental  permits:   the
State Department of Agriculture (for  pesticide use  or confined
animal feeding), the Corporation  Commission  (for oil- and  gas-
related discharges), the Bureau of Mines  (for  mine-related
permits), and the Water Resources Board  (for stream water
allocation, ground water use, and industrial water  dis-
charges).  There is no formal coordination of  permitting pro-
cesses between state agencies, nor are there mechanisms for
coordinating state and local regulators.
DECISION-MAKING DEADLINES

     State law establishes regulatory  deadlines  for  air  qual-
ity permits.  For all  state air  permits  except PSD,  the
Department of Health must either  grant or  deny the permit
within 90 days of the  filing  of  a completed  permit applica-
tion.  For PSD applications,  the  state complies  with the EPA's

-------
Oklahoma                      172
12-month review deadline.  When Oklahoma assumes respon-
sibility for PSD review in 1982, the state will review an
application within 6 months of the time the application is
completed.
STATE CONTACT

Judy Duncan
Environmental Health Service
Oklahoma Health Department
1000 N. E. 10th Street
P. 0. Box 53551
Oklahoma City, Oklahoma  73152
(405) 271-5204

-------
                                            Permit/Application Coordinator
                                                         Joint Hearing
                                                    One-Stop Permitting
                                                Decision-Making Deadlines
                                                        General Permit
OVERVIEW

     Oregon has taken  three  distinct steps to streamline the
permitting process.  The  Permit  Information and Coordination
Center, established within the  Intergovernmental Relations
Division of the Executive Department, distributes information
about state permit requirements,  offers both formal and in-
formal permit requirement definition services, and can serve
as the convener of joint  hearings.

     The Energy Facility  Siting  Council reviews all major
energy projects with a one-stop  permit process.  The process
includes a master application, joint hearings, and a single
decision maker.

     The Oregon Department of Environmental Quality (DEO)
utilizes general permits  for certain wastewater discharge
permits.  General permits allow  the DEO to develop permit
standards for specific types of  dischargers on a category-wide
basis, leaving case-by-case  review  and most monitoring to the
discharger.
PERMIT/APPLICATION COORDINATOR
AND JOINT HEARING

     The Permit Information  and  Coordination Center offers
information about permits  needed for particular projects, the
procedural process and  substantive  requirements for obtaining
those permits, and appropriate contacts  in the regulatory
agencies (Ore. Rev. Stat.  §  447.805 et  seq.).  The center
maintains a toll-free telephone  number  and publishes a permit
handbook to provide this information service.

-------
Oregon                        174
     The center is also directed by  law  to  organize  optional
master preapplication and joint hearing  processes.   The  master
preapplication process enables an  applicant  to  obtain  a  list
of state permit requirements  in 30 days.  This  list  is
"guaranteed" to contain every permit  applicable  to  the proj-
ect.  Permit requirements can also be identified informally
(and without a guarantee) in a matter of  one  or  two  days.
Joint hearings may be requested by the applicant, but  since
the process has never been used, the  procedural  details  are
not well defined.

     In addition, the center can serve as a  mediator between
applicants and state agencies.  At the request  of an appli-
cant, the center will contact a regulatory  agency to try to
eliminate any problems in the review  process  and, if neces-
sary, set up a meeting between the agency and the applicant.
In 1981, the legislature gave the  permit  center  the  authority
to order state agencies to appear  for mediation  sessions
called by the center.

     These services are available  to  prospective applicants of
any kind, and use of these services  is entirely  voluntary  for
the applicant.  The center handles all state  permits,  not
solely environmental ones.
Permits/Agencies Affected

     The center operates within  the  Intergovernmental  Rela-
tions Division of the Executive  Department.   The  information
mediation and permit requirement identification services
relate to all state permitting agencies.

     If the joint hearing process  is  invoked,  all  state agen-
cies objecting to the filed application must  present their
views at the joint public hearing.   The agencies  retain their
powers to grant or deny individual permits  in  the  joi*nt review
process.
Administrative Process

     In order to use the formal master preapplication  process,
an applicant must file a five-page application  with  the  cen-
ter.  The center then distributes the application  to all
interested agencies, and the agencies determine  which  permits

-------
                                                        Oregon
                              175
must be obtained.  Within 30 days of  receiving  the  applica-
tion, the center must respond to the  applicant  with a defini-
tive list of permits developed from agency  responses.   Agen-
cies that fail to respond within this period  may  not impose
any permit requirements.

     The informal preapplication process, which most small
businesses prefer, involves a meeting between the applicant
and the permit center official.  During  this  meeting the proj-
ect is explained and permit requirements  are  roughly defined.
This informal process takes about one day as  opposed to the 30
days that the formal process requires, but  the  list of permit
requirements is not legally binding.

     The joint hearing process is initiated at  the  request of
an applicant.  If held, the joint hearing replaces  all hear-
ings otherwise required by law.  The  director of  the Depart-
ment of Administration presides over  the  hearing, but repre-
sentatives of the relevant agencies conduct the portions of
the hearing relating to their jurisdictions.   Individual
applications are used, and the agencies make  permit decisions
independently.
Experience with the Reform

     The permit center was established  in  1975.   The  center
receives 400 to GOO calls for information  per  month.   About 30
applicants per year use the formal master  preapplication  pro-
cess, and a similar number participate  in  the  informal permit
identification meetings.  Applicants  with  large  or  complex
projects tend to use the formal option,  while  smaller projects
typically prefer the informal and quick  alternative.   The
center calls 30 to 50 meetings between  applicants and agencies
per year and makes some 200 phone call  resolutions  per year
under its mediation function.  No applicant  has  chosen the
joint hearing option.
ONE-STOP PERMITTING AND DECISION-
MAKING DEADLINES FOR MAJOR
ENERGY FACILITIES

     The Oregon Energy Facility Siting Council  (EFSC)  conducts
a one-stop permitting process for all major  energy  facilities
(Ore. Rev. Stat. § 469.010 et seq.).  The process  includes  a
master application, joint hearings, and a single comprehensive
permit decision process.  The state regulatory  agencies  may
impose conditions on the EFSC certificate, but  the  council

-------
Oregon
                             176
retains the final decision on issuance of the certificate.
State agencies must issue the relevant permits after  the  cer-
tificate has been granted.

     The one-stop process is mandatory for the following  kinds
of facilities:  nuclear powerplants; electric generating  sta-
tions over 25 megawatts; transmission lines over 239  kilovolts
and 10 miles; solar collectors covering over 100 acres; and
pipelines over 5 miles long and, for oil or geothermal energy,
greater than 6 inches in diameter or, for natural or  synthetic
gas, greater than 16 miles in diameter.
Permits/Agencies Affected

     All state and local permitting authorities participate in
the joint hearings.  The state agencies may impose conditions
on the EFSC certificate, but once the certificate has been
issued all state and local approvals must he granted.  The
state permits required for these projects include air, water
(NPDES), solid and hazardous waste, and land-use permits.

     Federal agencies have participated in hearings in several
cases, although their permit decisions are distinct from those
of the EFSC.  The local governments participate in the joint
hearings, but their permitting authority can be overridden by
the EFSC.
Administrative Process

     In most cases, a utility must issue a notice of intent to
file an application one year prior to the actual filing.  This
notice is circulated to the regulatory agencies, which deter-
mine what permits are needed and what standards must be met.
This one-vear period is also used to issue public notice of
the hearing and to allow interested parties to obtain inter-
vener status.  The single application is filed with the coun-
cil.  The joint evidentiary hearing is held before an admini-
strative law judge appointed by the council.  The judge's
findings and the participants' comments on those findings
serve as the basis for the council's decision.  The council
has broad fact-finding powers and may undertake studies
through its staff, the Oregon Department of Energy.

     If the EFSC approves the certificate, it is required to
include conditions recommended by appropriate state regulatory
agencies.  The EFSC is bound by legislatively prescribed

-------
                             177                        Oregon
decision-making deadlines ranging  from  nine  months  to  two
years, depending on the nature of  the project.   Following an
EFSC decision to grant a certificate, all  state  and  local
authorities must issue their permits with  the  same  conditions
recommended to the council.  Although the  statute establishes
this decision-making hierarchy,  the relationship between  the
EFSC and the state and local regulators  has  been cooperative
thus far.  The EFSC has not approved projects  objected to by
other regulators.
Experience with the Reform

     The EFSC and the one-stop process were  created  by  legis-
lation in 1971.  There have been  five applications  in  the  past
ten years.  A coal-fired powerplant, a cogenerator,  and an
underground gas storage facility  were granted  certificates.
There has been no decision on a nuclear plant,  and  an  applica-
tion for a major transmission line was just  received.
GENERAL PERMIT FOR WATER PERMITS

     The Oregon Department of Environmental Quality  is  devel-
oping an array of general permits for a variety of project
categories requiring water discharge permits.  The DEQ  general
permit establishes standards of operation, such as certain
suction dredges, for a type of discharger.  The individual
operator need only check compliance with  those standards  and
notify the DEQ to gain operating authorization.  Monitoring is
also accomplished by self-policing.  The  DEQ intervenes only
in response to complaints.  General permits have been adopted
by the DEQ for seven specific activities  ranging from boiler
blowdown to fish hatchery pond discharge.  The general  permits
were established by changes in regulations and required no
statutory amendments.
Permits/Agencies Affected

     The DEQ issues NPDES permits for direct dischargers and
state wastewater discharge permits for indirect dischargers.
The general permits cover both types of water discharge per-
mits.  The EPA may comment on proposed general permits within
the NPDES program.

-------
Oregon                         178
Administrative Process

     The DEQ initiates the general permit  process  by  proposing
standards for a particular discharging activity.   These
standards are open for public review  through  the customary
public notice, public comment, and public  hearing  process.
Following the agency decision, the NPDES portions  are submit-
ted to the EPA for comment.

     After the general permit has been adopted, the individual
discharger does not need to file an application or undergo
agency review in order to  receive state authorization.   In-
stead, the operator simply notifies the DEQ that the  facility
complies with the standards, at which time the DEQ informs  the
operator of the monitoring requirements.
Experience with the Reform

     The first four general permits were adopted  in  February
1981.  Three more were established in August 1981.   The
general permits are expected to cut by 20  to 30 percent  the
number of permit application reviews handled by Oregon's
wastewater discharge regulators.
STATE CONTACTS

Paul Haugland
Manager of State Regulation Services
Executive Department
Executive Building
Salem, Oregon  97310
(503) 373-1999

Don Godard, Administrator
Siting and Regulation
Oregon Department of Energy
111 Labor and Industries Building
Salem, Oregon  97310
(503) 373-1999

-------
                                          Permit/Application Coordinator
OVERVIEW

     Pennsylvania has initiated a permit coordination  system
through seven regional environmental protection  offices.   In
addition, a Governor's Energy Council, which  has  principal
authority for the development of energy policies  and programs,
was established in 1973.  This council has  no jurisdiction,
however, over energy facility siting.
PERM IT/APPLICATION COORDINATOR

     Pennsylvania's permit coordination system differs  from
those of many other states in its emphasis  on regional  direc-
tors.  Applicants may elect to work either  through  the  region-
al directors or directly with each permitting bureau  in the
regional offices.  Regardless of what an applicant  chooses,
many of the administrative procedures described  under permit
coordination are routine to every application.   All industrial
or energy project applicants may use the regional directors as
permit coordinators.
Permits/Agencies Affected

     The Pennsylvania Department of Environmental Resources
(DER) issues all environmental permits  required  for  industrial
or energy projects.  Separate bureaus exist within the  DER for
such areas as water quality, air quality,  resource management,
and surface mine reclamation.  In addition, there are seven
regional DER offices.  The directors of each  regional office
take the lead for coordinating all environmental permit proc-
essing for applicants in their own areas.  Except for dele-
gated NPDES and RCRA permits, neither federal nor local per-
mits are included in this coordination.

-------
Pennsylvania                  180
Administrative Process

     After the project applicant approaches the DER regional
office, the regional director circulates a brief written proj-
ect description throughout the department.  Regional program
staff then advise the project sponsor through the regional
director of the necessary permits.  A User Guide to DER
Permits is available upon request.  The applicant must com-
plete separate applications for each permit, although these
can be channeled through the regional director.  The regional
director will generally not issue any permits to the applicant
until all permits have been processed.

     The DER attempts to minimize the number of public hear-
ings and will hold them only for controversial projects.
There are no statutory deadlines for application review.
Although the state has a target time frame of 60 days, the DER
finds that federal regulations, especially public participa-
tion requirements, make this goal difficult to attain.
Experience with the Reform

     The regional permit coordination system has existed  for
about two years.  It is extensively used; however, specific
numbers were not provided.
STATE CONTACT

Richard Boardman
Associate Deputy Secretary for
  Environmental Protection
Department of Environmental Resources
P. 0. Box 2063
Harrisburg, Pennsylvania  17120
(717) 787-4686

-------
                                             Permit/Application Coordinator
OVERVIEW

     Rhode Island has not  initiated  major procedural reforms
in the area of environmental  permitting,  but the state does
formally coordinate the permitting process through a permit
coordinator and a permit guidebook.

     In 1974, the Rhode Island General  Assembly granted itself
the power of final approval or denial  over the location and
construction of oil refineries and nuclear powerplants
(General Laws, § 42-64-14.1).  This  authority overrides any
state or local authority that might  have  declared a facility
acceptable or unacceptable.   Since neither type of facility
has been proposed since 1974, the  law  remains untested.

     In addition, in 1979  the governor  established an Energy
Facility Siting Board with a  mandate to expedite existing
permitting procedures for  energy-facility siting.  Although
the board is administratively responsible for setting project
decision schedules, it has no enforcement powers.  No energy
facilities have been proposed since  the board's inception, and
therefore its effectiveness is untested.
PERMIT/APPLICATION COORDINATOR

     The permit coordinator  is  located  in  the Department of
Environmental Management  (DEM),  Division  of  Planning and
Development.  The coordinator handles requests for environ-
mental permit information and sets  up preapplication confer-
ences for applicants with energy  and industrial projects.   Any
applicants requiring multiple permits may  take advantage of
this program.

-------
Rhode Island
Permits/Agencies Affected

     The coordinator is involved  in  all  state  environmental
permits issued by the DEM  for  energy and industrial projects
as well as in the permit issued by the Rhode  Island Coastal
Resources Management Council  (CRMC).  In addition to approving
any development within 200 feet of the shoreline,  the CRMC
must approve the construction  of  any large  power generating
facilities and certain types of industrial  facilities (i.e.,
those that may affect the  groundwater) throughout the state.
Administrative Process

     The permit coordinator arranges  a  preapplication confer-
ence between the applicant and  the  agency's staff.   At the
conference, the permit requirements are reviewed and the
applicant  is given a permit guidebook describing both state
and federal requirements.  Subsequently,  the project sponsor
submits to the coordinator a  strategy for completing its per-
mit applications.  The coordinator  acts as  liaison  between the
applicant  and the permitting  divisions  and  helps monitor the
permit process.  He has no authority  either to make permit
decisions  or to set deadlines for  them.
Experience with the Reform

     The DEM has performed permit  coordination services on an
informal basis for many years.   The  permit  coordinator posi-
tion has been formalized  for  about one  year.   The permit coor-
dinator reports that  he sets  up  from two to four preapplica-
tion conferences per  month.
ADDITIONAL COMMENTS

     During its past  four  sessions,  the  legislature has con-
sidered, but failed to pass,  an  Energy Facilities Siting Bill.
This bill proposes the establishment of  a  separate siting
agency  that would pre-empt  all other authorities for the
siting, licensing, and permitting  of major energy facilities
(not just oil refineries and  nuclear powerplants).

     In addition, the Region  I EPA and the DEM are currently
exploring ways to streamline  the permitting of energy facili-
ties.   In the 1981 State-EPA  agreement,  the DEM agreed to
review  its state permits in terms  of their applicability to 14

-------
                             183
                                               Rhode Island
different types of energy  facilities.   The  DEM will prepare a
description of each permit  it  requires,  review the range of
permit processing times for  the  different  types of facilities,
and determine whether permit reviews  are now handled concur-
rently or sequentially.  The Region I  EPA  will produce a
similar analysis for 26 federal  permits.  Upon completion of
these analyses, regional and state staff will integrate the
information and decide what  streamlining should be imple-
mented.
STATE CONTACTS

Victor Bell
Permit Coordinator
Division of Planning and Development
Department of Environmental Management
Providence, Rhode Island  02903
(401) 277-2777

Mary Kilmarx
Public Utility Commission
100 Orange Street
Providence, Rhode Island  02903
(401) 277-3500

-------
OVERVIEW

     There is no consolidation of  environmental  permits  in
South Carolina, with the exception of  a.  joint  application for
Section 404 Clean Water Act permits developed  by the  State
Coastal Council and the U.S. Army  Corps  of  Engineers.   Certain
provisions of the State Coastal  Act serve  in some  degree to
streamline siting in the "critical areas"  of the coastal zone,
but these provisions do not reduce the number  of required
permits, nor do they amount to one-stop  siting.   Moreover,
they are largely based on directives from  the  federal  Coastal
Zone Management Act.

     In South Carolina the Department  of Health  and  Environ-
mental Control (DHEC) issues NPDES permits, construction per-
mits for air emissions, wastewater system  permits, and sani-
tary landfill permits.  The DHEC also  administers  Phase  I of
RCRA.  Additional permits are issued separately  by other state
agencies.  For example, the Land Resources  Conservation
Commission issues permits for mining operations,  and  the Water
Resource Commission issues permits for oil  and gas facilities
and for projects affecting ground  water  capacity.

     In addition, the Utility Facility Siting  and  Environ-
mental Protection Act governs the  siting of electric  generat-
ing plants.  This act provides for joint investigations,
hearings, and compacts between state and federal agencies.
The language authorizing such joint efforts is broad.   Accord-
ing to Public Service Commission staff,  this provision has  not
been used because there have been  no powerplants sited in the
past several years in South Carolina.

     DHEC personnel have investigated  various  permit  reform
measures.  According to DHEC staff, these measures have  all

-------
South Carolina
been rejected because they either were too costly or added
another layer of bureaucracy.
STATE CONTACTS

Richard P. Wilson
Legal Office
South Carolina Department of Health
  and Environmental Control
2600 Bull Street
Columbia, South Carolina  29201
(803) 758-5409

Duncan Newkirk (coastal permits)
South Carolina Coastal Council
Summerall Center, Suite 802
19 Hagood Avenue
Charleston, South Carolina  29403
(803) 792-5808

-------
OVERVIEW

     In July 1981, South Dakota consolidated all of  Its envi-
ronmental permitting authorities into the Department of Water
and Natural Resources (DWNR).  In addition, most permits
required for energy development and mining, including all air
quality, solid waste, and mining permit programs, have been
placed under the jurisdiction of the Board of Minerals and
Environment within the DWNR.  Water rights permits and permits
for underground injection not related to oil and gas produc-
tion are issued by the Water Management Board within the DWNR.
If a project requires multiple permits from the Board of Min-
erals and Environment, any hearings that are necessary for
these permits are held jointly before the board.  However, the
application and decision for each permit are still handled on
an individual basis.
STATE CONTACT

Robert Neufeld, Secretary
South Dakota Department of
  Water and Natural Resources
Pierre, South Dakota  57501
(605) 773-3151

Patricia DeHueck
Executive Secretary
South Dakota Public Utility Commission
South Capitol Building
Pierre, South Dakota  57501
(605) 773-3201

-------
                                                        Joint Review
                                               Decision-Making Deadlines
OVERVIEW

     Tennessee enacted legislation  in  April  1981  to  coordinate
and streamline the permitting  process  for  major energy  proj-
ects.  This legislation is modeled  after Colorado's  joint
review process.

     In addition, for all environmental programs  (air,  water,
solid waste, and hazardous waste),  Tennessee  conducts  informal
efforts to accelerate the processing of permit applications
for both energy and industrial projects.   Since most of the
environmental permitting departments are housed in  the
Tennessee Department of Public Health, Environmental Manage-
ment and Quality Assurance Administration,  there  is  a  great
deal of internal coordination.   For example,  department staff
help project sponsors effectively time their  multiple  appli-
cations.  Also, the state Department of Economic  and Community
Development will arrange preapplication meetings  between
Tennessee staff and the applicant to review  relevant permits.
JOINT REVIEW AND DECISION-MAKING
DEADLINES FOR MAJOR ENERGY PROJECTS

     The Major Energy Project Act  (Senate Bill  918)  prescribes
procedures for joint review of permits  for  major  energy  proj-
ects.  The key elements of this legislation are  the  establish-
ment of a joint review team, procedural and review deadlines,
and extensive public participation.

     In order to be eligible for joint  review under  the  Major
Energy Project Act, an applicant must apply to  the State  De-
partment of Economic and Community Development  for designation

-------
Tennessee                     190
as a priority energy project.   The  governor has final designa-
tion authority.  Eligibility depends  on  whether the project
has a capital cost of one hundred million  dollars or more and
whether it is likely to reduce  the  state's dependence on im-
ported energy.  Participation  in  the  process is voluntary for
the applicant.
Permits/Agencies Affected

     All state, local, and  federal  permits  that are needed in
order to build a major energy  project  may  be affected by this
legislation.  Examples of these  include  the federally dele-
gated PSD, NPDES, and RCRA  permits  issued  by the Department of
Public Health; the Army Corps  of  Engineers'  404 water permits;
the Tennessee Valley Authority's  26A water  permits; and local
zoning, noise, and construction  permits.

     State and local agencies  are required  to join the proc-
ess.  However, there is no  override of a local agency's inde-
pendent authority to ultimately  approve  or  disapprove the
project.  Federal agencies  whose  approval  is needed for the
project are invited to join  the  process.   If they do so, they
must make every effort to cooperate with the process schedule.
Administrative Process

     The legislation  is  intended  to  be  flexible.   An applicant
may request joint  review for  part  or all  of the regulatory
process.

     Once the governor designates  a  proposed project a major
energy project, he or she  issues  an  executive order approving
the project for joint review  and  providing for a  joint review
staff to assist in the process.   A joint  review team is formed
with state agencies designated  by  the governor,  local agencies
contacted by  the joint review staff, and  federal  agencies who
choose to participate.   The applicant participates as an ex
officio member.  The  joint  review  team  selects a  member to be
team leader.  The  team develops a  project decision schedule
which is monitored by the  team  leader.  The team  leader also
acts to resolve delays and  disputes.

     The legislation  requires a preapplication meeting between
the applicant and  the permitting  agencies in order to clarify
what each expects  from the  other.   The  applicant  is also re-
quired to meet, prior to application, with interested members
of the public to address their  concerns.

-------
                             191                  Tennessee
     The Major Energy Project Act  specifies  a number of dead-
lines to accelerate the  review  process.   The following are
examples of these deadlines:

       •  Approval or disapproval  of  a  request for desig-
          nation as a priority  energy project must occur
          within one month of the  initial request.

       •  The first meeting of  the  joint  review team must
          take place no  later than  six  weeks after this
          approval.

       •  Petitions for  judicial review of any action
          under this legislation must be  brought no later
          than 20 days following notice of such action.

       •  The complete project  decision schedule cannot
          last more than  two years.

     Within this time frame, the joint  review team has the
authority to specify and  modify a  project decision schedule.
If an agency fails to comply with  the project decision sched-
ule, the team leader may  bring  an  enforcement action in chan-
cery court.  The joint review team  may  also  request consoli-
dation of all or several  agencies'  applications and proceed-
ings.  The joint review  team has the  authority to waive any
state or local statute,  regulation, or  requirement if neces-
sary to ensure timely and cost-effective  completion of a
facility without the endangerment  of  public  health or safety.

     After all agency approvals have  been granted or deemed
unnecessary, and if judicial review of  these approvals is
required and completed,  the joint  review  team issues a final
certificate of approval.  This  certificate indicates any con-
ditions and the expiration date of  all  approvals granted to
the project.
Experience with the Reform

     Because the Major Energy Project Act  only  took  effect  on
July 1, 1981, no applicants have  filed  for the  joint  review
process.  The Department of Economic and Community Development
is currently exploring alternative mechanisms  for  implementing
the Act.

-------
Tennessee                     182
STATE CONTACTS

Ted Von Cannon
Department of Economic and Community Development
Suite 1007
Andrew Jackson Building
Nashville, Tennessee  37219
(615) 741-1888

Lee Munz
Executive Director
Tennessee Energy Authority
226 Capitol Boulevard Building
Suite 707
Nashville, Tennessee  37219
(615) 741-2994

Wayne Scharber
Director
Bureau of Environmental Health Administration
349 Cordell Hull Building
Nashville, Tennessee  37219
(615) 741-3657

-------
                                                    Computer Tracking
OVERVIEW

     Although Texas does not have a  formal consolidated  permit
program, it has instituted and continues  to  explore  methods
for streamlining the permitting processes.

     The Texas Department of Water Resources  has a Memorandum
of Agreement with Region VI of the U.S. Environmental  Protec-
tion Agency.  This agreement closely  links the  procedures  for
issuing state water discharge permits and  federal NPDES  per-
mits.  In particular, once the state  has  held hearings and
issued a state water discharge permit,  the EPA  will  usually
issue its permit without requiring a  second  public hearing.
In the last six years, there have been  only  a half dozen cases
where both agencies held public hearings.

     The Department of Water Resources  and the  Division  of
Surface Mining and Reclamation have  signed a  Memorandum  of
Agreement which effectively precludes the  need  for a water
discharge permit for applicants who  obtain a  surface coal  or
uranium mining permit.  Applicants will be required  to comply
with a discharge standard established by  the Department  of
Water Resources.
COMPUTER TRACKING OF
UIC PERMITS

     The Division for Underground Injection Control  is cur-
rentlv developing a computer svstem for tracking  permit appli-
cations and monitoring activities.  This system will be oper-
able in 1982 and will help track the 150 to 200 applications
received each month.

-------
Texas                        124
     During 1979 to 1980, the Texas Legislature's Committee on
Environmental Affairs investigated the potential for consoli-
dating state air quality and water discharge permits.  This
option was rejected as both unfeasible and insufficiently
beneficial.
STATE CONTACTS

Bob Fleming, Executive Assistant
Department of Water Resources
P. 0. Drawer 13087
Capitol Station
Austin, Texas  78711
(512) 475-3187

Jerry Hill, Director
Surface Mining and Reclamation Division
Railroad Commission of Texas
P. 0. Drawer 12967
Capitol Station
Austin, Texas  78711
(512) 475-8751

Jerry Mullican, Director
Underground Injection Control Division
Railroad Commission of Texas
P. 0. Drawer 12967
Austin, Texas  78711
(512) 445-1100

Doyle R. Pendleton, Assistant to Deputy Director
Control and Prevention Program
Texas Air Control Board
6330 Highway 290 East
Austin, Texas  78723
(512) 451-5711 Ext. 204

-------
                                                        Joint Review
                                            Permit/Application Coordinator
OVERVIEW

     Utah is in  the  early  stages of implementing the Utah
Coordinated Review  Process,  which is modeled in part after the
Colorado Joint Review  Process.   According to the legislative
plan, the Resource  Development  Coordinating Committee (RDCC),
an existing body composed  of representatives from 20 state
agencies, will assume  a  significant role in the process.
However, spokespeople  from the  governor's office cautioned
that all these plans are tentative, and untried.  In addition,
the RDCC will act as an  informal permit coordination function
for applicants not  using the joint review.

     Before the  passage  of the  coordinated  review legislation,
the governor from time to  time  formed special task forces made
up of representatives  from government,  industry, public inter-
est groups, and  the  general  public to evaluate sites for
energy projects.  In addition,  the Department of Environmental
Health and the Department  of Oil,  Gas and Mining, the two
agencies that issue  most of  the state's environmental permits,
have extensively utilized  preapplication conferences with
project sponsors.
JOINT REVIEW FOR ENERGY AND
MINERAL DEVELOPMENTS

     Under the Resource Development  Coordinating Committee Act
passed in 1981, the Resource  Development  Coordinating Com-
mittee in the State Planning  Office  will  oversee the coor-
dinated review process.  This  committee  consists of 20 repre-
sentatives from state agencies  and  three  ex officio repre-
sentatives from the U.S. Department  of  the Interior's Bureau

-------
Utah                         19C
of Land Management and National  Park  Service  and  the  U.S.
Department of Agriculture.  Until  now the  committee's function
has been to conduct OMB A-95 and other  economic and  policy
reviews.

     Under the coordinated review  process  the committee  will
assist applicants in identifying the  environmental  permits
necessary for their projects and in consolidating hearings and
application forms whenever feasible.   In order to receive
approval for coordinated  review, the  project  must (1) be a
major energy or mineral resources  development,  (2)  be in the
early planning phase, and (3) have sufficient environmental
impact to justify the commitment of government staff  and
funds.  The coordinated review process  will not change the
substantive permit requirements  for each agency.  Instead  it
will facilitate early information  exchange and establish an
orderly schedule for the  issuance  of  permits.   Finally,  the
coordinated review process will  be voluntary:   both  project
sponsors and government personnel  can choose  whether  or  not to
participate on the review team.
Permits/Agencies Affected

     The joint review process  can  encompass  preparation  of
federal, state, and  local environmental  and  land-use permits
as well as tribal permits.   It  can also  incorporate  state and
federal environmental impact statement preparation.
Administrative Process

     Procedures  for designating  a  project  for  coordinated
review have not  yet been  developed.

     After initial designation of  a  coordinated  review proj-
ect, the governor will  assemble  a  team  that  will generally
include representatives of  the state Natural Resources and
Energy Department and  the Department of  Health,  Division of
Environmental Health.   The  governor,  with  assistance from the
Resource Development Coordinating  Committee, will consult with
state, federal,  and local agencies to select a review team
composed of the  agencies  with  the  greatest regulatory respon-
sibilities.  The team  will  typically include representatives
from local resident and citizen  groups.

-------
                              127                          Utah
     The review team will develop a  statement of specific
responsibilities for the applicant and  agencies, along with a
decision schedule.  The team will also  schedule public meet-
ings and hearings consistent with statutory  requirements.
Experience with the Reform

     Because the legislation  is  so  new,  the  first project to
be subject to coordinated review has  only  recently been desig-
nated.  It is the TOSCO Sand  Wash Oil  Shale  project in Uintah
County, Utah.  The company  volunteered to  be the first appli-
cant to go through the process.   The  team  for the Sand Wash
project includes one  local  representative,  two state agency
representatives who are also  the chairman  and co-chairman of
the Resource Development Coordinating  Committee,  a federal
official from the Bureau of Land Management,  and one Indian
tribe representative.
PERMIT/APPLICATION COORDINATOR

     In addition to its role  in  the  coordinated  review pro-
cess, the RDCC may act as an  informal  coordinator for all
types of projects.  Applicants will  be  encouraged to appear
before the RDCC in a preapplication  meeting.   At these meet-
ings, the RDCC will help applicants  learn  about  permit re-
quirements and identify individual contacts  in each  agency.
This function is still in the development  stages.
STATE CONTACTS

Carolyn Jones, A-95 Coordinator
State Planning Office
116 State Capitol
Salt Lake City, Utah  84114
(801) 533-4971

Juline Christofferson, Physical Resources  Coordinator
Governor's Office
State Capitol
Salt Lake City, Utah  84114
(801) 533-6450

-------
Utah                          198
Kathleen McGinley
Director Intergovernmental Relations
State Planning Office
116 State Capitol
Salt Lake City, Utah  84114
(801) 533-6315

-------
                                           Permit/Application Coordinator
OVERVIEW

     Vermont issues a land-use  permit  for  commercial  or indus-
trial projects (an "Act 250"  permit) and an  environmental
impact and planning certificate  for electrical  generation or
transmission projects (a Certificate of Public  Good).   Al-
though these two permits do not  replace the  need  for  other
permits, they do promote coordination  and  consistency  in the
permitting process.

     In addition, Vermont conducts informal  efforts  to expe-
dite the permitting process for  industrial and  energy  project
applicants.  The Agency for Environmental  Conservation (AEC)
issues most of the state's environmental permits  and  maintains
informal internal communications  on projects that require more
than one permit.  Moreover, AEC  staff  encourage industrial and
energy applicants to participate  in preapplication meetings
and to request written project  reviews which summarize rele-
vant permit requirements.
PERMIT/APPLICATION COORDINATOR

     Vermont's Land Use and Development  Act  (1970;  10  VSA,
Ch. 151) created a mechanism whereby  certain  types  of  develop-
ments must obtain a land-use or  "Act  250"  permit  prior to
commencing construction.  Electric generation  or  transmission
facilities are exempt from Act 250 review, but must  receive  a
Certificate of Public Good instead.

-------
Vermont                       200
Permits/Agencies Affected

     Both the Act 250 permit and  the  Certificate  of  Public
Good are required in addition  to  normally  mandated local,
state, and federal permits.  These  other permits  can be used
as evidence of compliance with  relevant criteria  of  Act 250.

     Nine district environmental  commissions  located in five
regional offices throughout  the state receive and rule on
applications for Act 250 permits.   Each district  commission is
made up of three commissioners  appointed by  the  governor and
is staffed by an environmental  protection  coordinator.  The
Vermont Public Service  Board issues the Certificate  of Public
Good.
Administrative Process

     Although the Act 250 and  certification  procedures are not
examples of one-stop permitting,  they  can  serve to coordinate
some permitting programs.  Any directly  affected state agency,
municipality, planning commission,  or  adjoining property owner
may act as a party at an Act 250  hearing.   In  reviewing a
project application, the district commission looks for evi-
dence that the project will not negatively affect any aspect
of the environment, including  water, air,  soil,  traffic, and
aesthetics.  Upon request, a district  commission will hold
joint hearings with other decision  makers  to reduce duplica-
tive hearings and facilitate coordination.  In addition, a
commission may issue consolidated land-use permits which inte-
grate such requirements as Department  of Health,  subdivision,
and public building regulations.

     The Public Service Board  also  consults  with other agen-
cies during its certification  review.   In  considering an ap-
plication, the PSB looks at the possible adverse effect on all
aspects of the environment.
Experience with  the  Reform

     Both programs have  been  extensively  used.   Nearly 4,000
Act 250 permits  have been  issued  since  the permit's inception
in 1970.  No  specific numbers in  the  use  of the Certificate of
Public Good were provided.

-------
                              201                       Vermont
ADDITIONAL COMMENTS

     The Public Service Board recently adopted General  Order
65, which effectively exempts small power producers  (10 kilo-
watts or less) who sell electricity only at  the  wholesale
level from various regulatory requirements.  The objective  of
this order is to encourage the development of alternative
forms of energy.
STATE CONTACTS

Jan Eastman
Executive Officer for the
  Environmental Board
State Office Building
Montpelier, Vermont  05602
(802) 828-3309

Richard Saudek
Department of Public Service
State Office Building
Montpelier, Vermont  05602
(802) 828-2321

Gary Schultz, Permits Section
Richard Valentienetti, Air and Solid
  Waste Section
Agency of Environmental Conservation
State Office Building
Montpelier, Vermont  05602
(802) 828-3345 (Schultz)
(802) 828-3395 (Valentienetti)

-------
                                            Permit/Application Coordinator
                                                      Joint Application
OVERVIEW

     Virginia established  a  Council on the Environment in  1970
for the purpose of  implementing the state's environmental
policy and coordinating  environmental quality matters.  The
council has statutory  authority to coordinate and consolidate
multiple permit processes, although most of its coordinating
work is informal.

     The Virginia Marine Resources Commission has initiated
several measures, including  joint  application forms and joint
processing meetings, to  promote intergovernmental coordination
of the permitting process  for  marine resource areas.
PERMIT/APPLICATION COORDINATOR

     The administrator  of  Virginia's Council on the Environ-
ment may provide a variety of coordinating services for an
applicant who needs multiple  state permits.   Although the
administrator has statutory authority (Va. Code § 10-184.2) to
formally perform these  services,  he has tended to work on an
informal basis.  Any  applicant  requiring more than one state
permit may request this  service.
Permits/Agencies Affected

     The council administrator  will  provide information on all
relevant state, local,  and  federal permit  requirements to
project applicants.  The council  administrator may also in-
formally work with  the  state  commissions  or boards that issue
environmental permits,  such as  the Air  Pollution Control

-------
Virginia                      204
Board, the Water Control Board, and the Marine Resources Com-
mission.  The administrator also works with relevant  federal
agencies such as the Army Corps of Engineers.

     The Council on the Environment is composed of  the chair-
people or commissioners of eight state agencies primarily
responsible for environmental protection,  two gubernatorial
appointees, a chairman, and an administrator.


Administrative Process

     Applicants generally learn about the  permit coordination
services through referral from the governor's office  or other
state agencies.  Depending on the applicant's preferences, the
council administrator's assistance may range from simply noti-
fying the applicant of relevant permit requirements to actu-
ally working with the applicant and various permitting agen-
cies to modify the project, if necessary,  so that it  will  be
environmentally acceptable.  In the case of extensive coor-
dination, the administrator might serve as the channel for all
permit applications and communications with the permitting
agencies.  At a minimum, A Guide for Permit Applicants is
provided to the applicant.  The degree of  council involvement
is entirely voluntary on the part of the applicant.
Experience with the Reform

     As a result of an adverse opinion on the permit coordina-
tion statute released by the State Office of the Attorney
General, the council has been advising permit applicants not
to request formal permit coordination.  The most popular of
the informal services offered by the council are preapplica-
tion meetings between developers and agency staff.

     The council administrator reports that he provides in-
formational services to about ten or twelve applicants per
month, and more involved assistance to eight or ten per year.
JOINT APPLICATION AND PERMIT/APPLICATION
COORDINATOR FOR MARINE RESOURCES PERMITS

     The Virginia Marine Resources Commission has formally
introduced state/federal joint permit procedures for projects
in, on, and over state-owned submerged land and vegetated

-------
                              205                      Virginia
tidal wetlands.  These include consolidation  of  four state and
federal permit applications  into  one  joint  application,  prom-
ulgation of a joint federal/state public  notice,  and monthly
coordinated permit processing meetings  between federal and
state agencies.
Permits/Agencies Affected

     Applications for  the  following  permits  are  consolidated
into one application form:   the  Virginia  Marine  Resources
Commission's permit to encroach  in,  on, or over  state-owned
submerged land, the U.S. Army  Corps  of  Engineers'  permit under
Section 404 of the Clean Water Act,  the Corps' permit under
Section 10 of the Rivers and Harbors Act, and  the  local wet-
lands permit.  In addition,  the  State Water  Control  Board uses
the information from the application in processing its certi-
fication required by the Clean Water Act, Section  401.

    In addition to the district  office  representatives of the
Army Corps of Engineers and  the  State Marine Resources Commis-
sion, other federal agencies and state  commissions participate
in the monthly joint meetings.   These participants include
representatives from the Region-  III  EPA,  the regional Fish and
Wildlife Service (U.S. Department  of the  Interior),  the
National Marine Fisheries  Service  (U.S. Department of
Commerce), the State Health  Department, the  State  Water
Control Board (which issues  Section  401 certification),, and
the Virginia Institute of  Marine Science.
Administrative Process

     The Marine Resources Commission  assigns  a  single proces-
sor to follow each project application  through  all  its proce-
dural steps.  The processor prepares  the  necessary  copies of
the application for  the  federal,  state, and  local agencies,
makes the initial site visit, presents  the project  formally  to
the Marine Resources Commission,  and  performs any necessary
follow-up activities.

     The Marine Resources Commission  and  the  Army Corps of
Engineers issue joint public  notice  for project applications,
but they do not hold joint public hearings.   State  and federal
agencies, however, are exploring  the  possibility.   The local
wetlands board must  hold a public hearing prior to  any state
or federal hearing and process  the application  within pre-
scribed time frames.

-------
Virginia                      206
     The commission tries to  rule  on  state  permits  within 45
to 60 days.  It holds public  hearings  monthly  and considers
all projects against which a  formal protest has  been lodged.
In the federal permitting process, complex  projects generally
take longer to resolve.

     Joint monthly processing  meetings are  held  to  help coor-
dinate the applicant through  the  federal  permitting process.
At these meetings state and federal representatives discuss
and resolve problems on individual applications  with the
assistance of ground and aerial photographs of project sites.
Experience with the Reform

     The Marine Resources Commission  processes  about 800 to
1,000 applications per year,  all  of which  go  through the coor-
dinative process.  The program  has been  effective  in reducing
conflict among agencies,  improving enforcement,  and reducing
permit processing time.   The  commission  continues  to be a
strong advocate for delegation  by the Army Corps of Engineers
of its Section 404 dredge and fill permit  authority in order
to provide a true one-step  process.
STATE CONTACTS

Keith Buttleman
Assistant Administrator
Virginia Council on  the Environment
903 Ninth Street Office Building
Richmond, Virginia   23219
(804) 786-4500

Norman E. Larsen
Assistant Commissioner  for  Environmental  Affairs
Virginia Marine Resources Commission
P. 0. Box 756
Newport News, Virginia  23607
(804) 245-2811

-------
                                                   One-Stop Permitting
                                               Decision-Making Deadlines
                                           Permit/Application Coordinator
                                                        Joint Hearing
OVERVIEW

     Washington State  has  aggressively pursued new ways of
streamlining permit  procedures.   In 1970 Washington became the
first state to pass  energy facility siting legislation.  In
1973 Washington established procedures to coordinate environ-
mental permitting  for  projects  not included under the siting
legislation.  More recently,  state environmental staff have
developed administrative procedures to coordinate with federal
officials in applications  for "low-head" hydroelectric
projects.
ONE-STOP PERMITTING  AND
DECISION-MAKING DEADLINES
FOR MAJOR ENERGY PROJECTS

     Washington's Siting Legislation (1970;  Ch.  80.50 RCW)
established the Energy Facility  Site Evaluation  Council
(EFSEC) and a true one-stop  permitting process.   The following
energy plants and transmission  facilities are required to use
this process:  oil and gas pipelines of 15 miles or more;
stationary energy plants with capacity of 250,000 kilowatts or
more; floating powerplants with  capacity of 50,000 kilowatts
or more; receiving facilities for  liquified gas  or petroleum;
underground reservoirs for natural gas with capacity of 100
million cubic feet;  petroleum processing facilities processing
25,000 barrels per day; and  associated facilities.
Permits/Agencies Affected

     The siting council  issues  an  Energy  Site Facility Certi-
fication Agreement which is  in  lieu of  all state and local
permits  that  would  otherwise be required.  Preparation of

-------
Washington                   208
state and federal environmental impact statements  is  inte-
grated into the review process, but these documents must  be
prepared separately from the certificate agreement.   Occasion-
ally, the state and federal governments will publish  one  EIS
jointly.

     The members of the EFSEC consist of a chairperson  ap-
pointed by the governor, the directors of 14 state agencies,
and representatives from each local government unit that  may
be affected by the project.
Administrative Process

     The project sponsor must submit a detailed application  to
the siting council describing the proposed project and  site;
analysis of alternatives; compliance with local,  state,  and
federal standards; socio-economic and environmental  impacts;
schedules for environmental studies; etc.  Although  there  is
no check-off list for individual permit  requirements, most
agencies that issued permits for siting  approval  prior  to  the
EFSEC legislation are members on the council.  Certification
by the EFSEC replaces all state and local permit  requirements.
The council may hire independent consultants  to review  the
application and, if required, write the  EIS.

     Within 60 days of receiving the application, a  public
hearing is held in the affected county for the purpose  of
determining consistency with local land-use ordinances.  After
the draft EIS is completed, quasi-judicial public hearings are
held.  There is ample opportunity for public  comment  through-
out the process.

     Within 12 months after receipt of the application  (or
longer if the EFSEC and the applicant mutually agree  to extend
the deadline), the council makes its recommendation  to  the
governor on whether to approve or deny the project and  under
what conditions.  The governor must approve,  reject,  or direct
reconsideration of the project within 60 days of  receiving the
recommendation.  The governor has ultimate approval  but may
not override a negative recommendation by the council.

     The EFSEC is required by its enabling statute to coordi-
nate activities as much as possible with federal  regulatory
agencies.  In order to further this goal the  council  has often
adopted federal environmental impact statements for  state
purposes, conducted joint hearings with  federal agencies,  and
arranged for cooperative environmental impact studies with the
Department of the Interior.

-------
                              i09                     Washington
Experience with the Reform

     To date, the council has  issued  four  certificates for
seven nuclear powerplants (three  twin  projects).   In addition,
the council is currently considering  three applications (two
oil port/crude oil transshipment  systems and  one  coal-fired
powerplant).
PERMIT/APPLICATION COORDINATOR,
JOINT HEARING, AND DECISION-
MAKING DEADLINES

     The Environmental Coordination  Procedures  Act  (1973;
Ch. 90.62 RCW) set up permit  information  centers  throughout
the state as well as a procedural  coordinating  mechanism for
securing permits.  Any applicant for a  new  or  an  expanding
activity requiring two or more permits  may  elect  to use the
process.
Permits/Agencies Affected

     Both state and local agencies are  required  to  participate
in the coordinating process.  Examples  of  agencies  and  permits
that may be affected include the Department  of Natural  Re-
sources' surface mine and drilling permit,  the Department  of
Ecology's water quality permits, regional  air pollution con-
trol permits, and local governments'  shoreline management
permit.  The Department of Ecology,  which  issues  about  80
percent of all state environmental permits,  administers the
program.
Administrative Process

     An applicant may pick up a master application  form  at  any
one of the 39 county planning departments  or  four  regional
Washington Department of Ecology's offices, or  at  the  Depart-
ment of Ecology's Master Application Center.  The  applicant
submits the six-page form as well as an environmental  check-
list (to determine if a state EIS is needed)  to the  Master
Application Center.  The Department of Ecology  circulates
copies of the application among the state  agencies,  each of
which must comment within 15 days on whether  a  permit  is re-
quired and, if so, whether a public hearing is  needed.   After
receiving a response coordinated by the Department of  Ecology,

-------
Washington                    210
the applicant may elect either to withdraw  from  the process
and approach agencies separately or to continue  working
through the department.

     If an applicant elects to use the process,  he or  she  will
submit all forms and receive all information  through the De-
partment of Ecology.  The applicant must still complete separ-
ate application forms for each required permit,  dnd each agen-
cy will reach its own decision.  However, the Department of
Ecology will arrange for a joint public hearing  .(if a  hearing
is needed), which all permitting agencies must attend.  The
department and the other agencies will establish a deadline
for making their decisions.

     In addition, applicants may use the regional permit in-
formation centers to obtain preliminary information about  how
many and which state permits may be required  for their proj-
ect .
Experience with the Reform

     Department of Ecology staff commented  that  the environ-
mental coordination procedures have produced  tangible  time  and
cost savings for both industry and government.   The element
most used by project sponsors is the  initial  stage, in which
agencies must identify which permits  will be  required  based on
information contained in the master application.  Through June
1981, 307 applications were submitted and 53  went through the
entire process.  Recent interest in small-scale  hydroelectric
projects, whose sponsors tend to be unfamiliar with the  intri-
cacies of government, has greatly intensified the level  of
use.
PERMIT/APPLICATION COORDINATOR
FOR HYDROELECTRIC PROJECTS

     Because of the tremendous  increase in small-scale  hydro-
power applications resulting from  the Public Utility Regula-
tory Policies Act, the Department  of Ecology's  Environmental
Review Section has instituted a number of procedures aimed ..it
expediting the permitting process.  At present  20 new applica-
tions are submitted each month.

     The Department of Ecology and  the Federal  Energy Regula-
tory Commission (FERC) have agreed  that the environmental
analysis required under the state  environmental policy  act may

-------
                              211                   Washington
be used to complete the environmental sections of  the  FERC
application.  In some cases the state and federal  agencies
will prepare a joint EIS.

     The Department of Ecology has written a handbook  for
hydropower applicants explaining step by step the  process for
complying with state and federal requirements.   In addition,
the department has conducted informational workshops around
the state.

     The Department of Ecology is in the process of computer-
izing a tracking system for all hydropower projects.   The
department keeps a master list of all hydro projects.   It also
conducts special meetings with other agencies, such as  the
Department of Fish and Game, in order to work out  application
problems.
STATE CONTACTS

Nick Lewis, Chairman
Energy Facility Site Evaluation Council
Mail Stop PY11
Olympia, Washington  98504
(206) 459-6495

Greg Sorlie
Environmental Review Section
Department of Ecology
Mail Stop PY11
Olympia, Washington  98504
(206) 459-6016

-------
                                          Permit/Application Coordinator
OVERVIEW

     In *Vest Virginia,  the Governor's  Office of Economic and
Community Development  helps  expedite  the permitting process'
for industrial and energv projects  by  acting as an informal
permit coordinator.
PERMIT/APPLICATION COORDINATOR

     Upon request, and on a case-by-case  basis,  the Economic
and Community Development Office  assists  developers as they
seek multiple permit approval.  Projects  for which the office
provides permit coordination  include  energy-related facilities
(such as coal mines, oil and  gas  wells, coke plants,  and syn-
thetic fuel plants) and  industrial  facilities (primarily manu-
facturing ).
Permits/Agencies Affected

     The coordination service  performed  by  the Economic and
Community Development Office covers  all  state  environmental
permits needed for a facility  but does not  cover federal or
local permits.  Although the office  coordinates these permits,
applicants must still apply to each  department for individual
permits.  For example,  the Department of  Health issues permits
relating to nonhazardous waste disposal  and  drinking  water;
the Department of Natural Resources  has  authority over water
quality, surface mining and reclamation,  and hazardous waste;
and the Air Pollution Control  Commission  is  concerned with  air
pollution discharge.

-------
West Virginia                 214
Administrative Process

     The  Economic and Community  Development  Office  assists
industrial  and energy applicants by  doing  the following:

       •  Actively  encouraging and arranging for pre-
          application conferences with  the relevant state
          permitting agencies

       •  Tracking  permit  applications  for individual
          projects

       •  Intervening where  appropriate to resolve  con-
          flicts between a developer and a permitting
          agency.
Experience with the  Reform

     The Economic and Community Development Office has as-
sisted industrial project applicants for many vears and energy
project applicants for one year.  In this past year, the of-
fice has helped approximately six developers of energy proj-
ects with their permit applications.  Energy and industrial
projects currently under development in the state are being
monitored in order to track permit applications.
ADDITIONAL COMMENTS

     Permit catalogs covering coal mining and general indus-
trial facilities are currently being prepared by the Economic
and Community Development Office.
STATE CONTACT

Mark A. Scott
Energy Development Division
Governor's Office of Economic
  and Community Development
Building 6, Room B-531
State Capitol
Charleston, West Virginia  25305
(304) 348-0400

-------
                                            Permit/Application Coordinator
                                                         Joint Hearing
                                                Decision-Making Deadlines
                                                        General Permit
                                                     Computer Tracking
OVERVIEW

     Wisconsin's  innovations in permitting result  from  the
Power Plant Siting  Act  of 1975, the Metallic Mining  Reclama-
tion Law of 1978, and  administrative policies of the  state's
Department of  Natural  Resources (DNR).  The reforms  include
joint and master  hearings,  issuance of general permits,  and  a
computer tracking system for permits.

     Rather than  review and issue all permits from DNR  head-
quarters, the  DNR is  developing a program that will  delegate
noncomplex NPDES  permits and most solid waste permits to six
field offices  by  mid-1983.   The director of the Environmental
Standards Division  of  the DNR reports that decentralization
should result  in  greater responsiveness to the discharger and
the public when dealing with localized problems.  The DNR
hopes to decentralize  other environmental permits, but  it
recognizes that decentralization may not be desirable for
permits that involve  complex environmental factors,  such as
permits for water discharges.  DNR staff have proposed  the
appointment of a  permit expediter who would supervise decen-
tralized permits, reviewing their regional and state  impacts.
PERMIT APPLICATION  COORDINATOR,
JOINT HEARING, AND  DECISION-
MAKING DEADLINES  FOR  POWER
FACILITIES AND RAILROAD LINES

     Under the Power  Plant Siting Act of 1975 (196.491(3)
Wise. Stats, and  P.S.C.  111.42 and 2.90-2.95, Wise. Adm.
Code), the DNR and  the  Public Service Commission (PSC) have
established procedures  to  coordinate the review of powerplant

-------
Wisconsin                     216
(over 12 megawatts) and  transmission-line (over 100 kilovolts)
proposals.  The two agencies  hold  a  single joint hearing on
the state environmental  impact  statement  and the major permits
for these facilities.
Permits/Agencies Affected

     The joint hearing  covers  all  environmental permits that
the DNR oversees,  including  those  for NPDES,  underground in-
jection control, dredge  and  fill,  and solid waste.  The joint
hearing also applies  to  those  permits for which the state has
only partial authority:  hazardous waste  and  PSD permits.  In
some cases separate hearings may be necessary for NPDES per-
mits, where DNR staff require  additional  data or extended
review of data.
Administrative Process

     From the time  the  project  sponsor's  application for a
certificate of public convenience  and necessity and the envi-
ronmental report  (ER) required  under  Wisconsin's state envi-
ronmental policy  act  (§ 150,  Wise.  N.R.C.)  are accepted as
complete, the coordinated  review process  should take no more
than 18 months for  powerplants  over 300 megawatts.   For power-
plants of 12 to 300 megawatts  and  transmission lines,  the DNR
has five months to  act,  and  the coordinated review is  sched-
uled to take six  months.   The  DNR  must approve the major envi-
ronmental permits under its  jurisdiction  within 16 months,
before the PSC can  grant  the  certificate.   The utility cannot
condemn land until  the  PSC issues  the certificate.   Once the
DNR and the PSC issue permits  and  approvals,  no local  regula-
tions can prevent construction.

     The definition of  issues  that  the environmental report
will address, known as  "scoping,"  usually begins a year before
the ER is submitted and continues  during  the  draft ER  period
as part of the coordinated review  process.
Experience with  the  Reform

     The powerplant  siting  procedure has been used in three
different forms  since  its  inception in 1975.   At the time the
statute became effective,  three  applications  were in the proc-
ess of being  reviewed.   The PSC  and the DNR signed a memoran-
dum of agreement  to  employ  the  basic principles of the Siting
Act process  for  these  applications, though the deadlines were

-------
                              217                    Wisconsin
not applied.  All three plants  were  successfully permitted
under these ad hoc procedures.   One  plant completed the entire
coordinated siting process  under the 1975 Act.   As a result of
that case, modifications  to the original  process were made to
include a "scoping"  meeting for the  ER and public participa-
tion opportunities early  in the review process.   Two applica-
tions began this modified process  but  were withdrawn because
of financial reasons  before completing it.
GENERAL PERMIT

     Rather than give  individual  environmental reviews and
permits to small sources  on  a  case-by-case basis,  the DNR
issues a general permit  for  the entire  state or for a region.
This eliminates the  need  to  prepare  an  individual  document for
each source.
Permits/Agencies Affected

     So far, the DNR has used  the  general  permit system only
for small, noncontact,  cooling  water  discharge permits but
plans to extend it  to other  permits  such  as  those for sand and
gravel quarry settling  ponds,  monuments and  cut-stone opera-
tions, ready-mix concrete  plants,  potable  water treatment
(ion-exchange), and construction site runoff basins.
Administrative Process

     If the applicant meets  the  overall  criteria established
in the general permit,  the applicant  automatically qualifies
as a general permittee.  Aside  from obligations  by the per-
mittee to maintain  its  facility  in good  working  order and to
internally monitor  its  discharges, no special  reporting re-
quirements or site  inspections  are necessary.  The general
permit is nevertheless  authorized by  the  Clean Water  Act and
legally enforceable should the  DNR receive  a  complaint on the
facility or wish to inspect  it  later.
Experience with the Reform

     DNR staff report that general  permits  have  eliminated
300 to 400 permits for small plant  water  cooling discharges
alone.  According to the department,  estimates show  that  the
average permit costs the state approximately  $200 to process,

-------
Wisconsin                     218
so that if 500 industrial permits  are  converted to a general
permit, a savings of $100,000  results  over the normal five-
year permit cycle.  The approach  frees  staff  time formerly
devoted to supervision and  duplicative  individual contact.
JOINT HEARING FOR MINING PROJECTS

     Under the Metallic Mining  Reclamation  Law of 1978
(§§ 144.80 to 144.94  Wise.  Stats.),  exploration and mining
projects can make use of a  "master  hearing" similar to the
joint hearing for powerplants.   This would  consolidate review
of all required state and federal environmental permits into
one hearing held by the DNR.  The state  has not used this
provision because there are  no  mining applicants far enough
along in a project to qualify.   The Metallic Mining Reclama-
tion Law was under review by  the legislature in 1981.  Amend-
ments are expected.
COMPUTER TRACKING

     The DNR employs a  computer  tracking system to assist
internally with permits.   At  present  the system applies to all
the DNR's municipal and industrial  waste discharge permits.
ADDITIONAL COMMENTS

     In addition  to  assigning  permits  to categories routinely
used by state  agencies  and  the EPA to  classify permits,  such
as major/minor and primary/secondary,  the DNR divides permits
into complex/  noncomplex, and  uses this categorization to
determine overall permit  priority.

     To determine whether a  discharge  is complex or noncom-
plex, the DNR  staff  asks  three questions:  (1) Is the source a
major discharge?  (2) What  are the applicable effluent limita-
tion guidelines?  (3)  If  the EPA has not issued guidelines,
what is the  staff's  best  professional  judgment?  In the  case
of land disposal  permits, a  discharger is complex if its sys-
tem includes pretreatment before irrigation and requires a
ground water monitoring system.

     Complexity  is one  factor  that the DNR considers in  set-
ting overall permit  priorities.   DNR staff analyze in depth

-------
                             219                     Wisconsin
such factors as industry type, waste  type,  treatments  em-
ployed, and a point value system  to determine  a  permit's  com-
plexity, time demands, and environmental  significance.  The
system assists the DNR in setting  future  program priorities,
assigning staff workloads, and setting  assessments  for  dis-
charges.

     By relatively ranking the permits, the  point  system  helps
the DNR in its program planning.   The most  recent  analysis  of
approximately 1,500 permits resulted  in about  25 percent  being
classified as complex.  Initially, the  DNR  has decided  only to
delegate noncomplex discharge permits to  the  field  offices.
STATE CONTACTS

Tom Kroehn, Administrator
Environmental Standards Division
Wisconsin Department of Natural Resources
P. 0. Box 7921
Madison, Wisconsin  53703
(608) 266-1099

Paul P. Didier, Chief
(General Permits and Permit Priorities)
Industrial Wastewater Section
Environmental Standards Division
Wisconsin Department of Natural Resources
P. 0. Box 7921
Madison, Wisconsin  53703
(608) 266-0289

Roy Christiansen, Director
Systems Bureau of Environmental Analysis
Planning, Environmental Review, and
  Consumer Analysis Division
Public Service Commission
P. 0. Box 7854
Madison, Wisconsin  53703
(608) 266-5990

Jerry Mendl, Administrator
Systems Planning, Environmental Review,
  and Consumer Analysis Division
P. 0. Box 7854
Madison, Wisconsin  53703
(608) 266-5990            ;

-------
OVERVIEW

     Most of the efforts at expediting issuance of environ-
mental permits in Wyoming are informal in  nature, designed  to
foster cooperation among state agencies and departments  that
issue permits separately.  Preapplication  conferences  and
memoranda of understanding between state agencies and  between
state and federal agencies help define permit  responsibili-
ties.  Decision-making deadlines found in  administrative regu-
lations set time requirements for permit review and  issuance
by the Department of Environmental Quality and the Industrial
Siting Council.

     The Air Quality, Water Quality, and Land  Quality  divi-
sions of the state Department of Environmental Quality issue
air, water, dredge and fill, and solid and hazardous waste
permits.  Large-scale energy pro.jects must obtain an addition-
al siting permit from the Industrial Siting Council.   Appli-
cants proposing to drill oil or gas wells  must receive a per-
mit from the state oil and gas supervisor.  Those project
sponsors with plans for coal gasification  plants, pipelines,
utility plants, and similar facilities must apply for  a cer-
tificate from the Public Service Commission.
     The Land Quality Division has made cooperative agreements
with boards of county commissioners throughout the state.
These agreements enable the division to coordinate its review
with local ordinances and requirements established by individ-
ual counties.

     Staff at the Industrial Siting Administration noted that
efforts have been made in the past to hold joint hearings with
the state Public Service Commission and federal Bureau of Land

-------
Wyoming                      222
Management.  These attempts were halted when the projects were
withdrawn or rescheduled.  The Industrial Siting Administra-
tion has a memorandum of understanding with the federal Office
of Surface Mining.  This agreement makes the Siting Adminis-
tration responsible for the social and economic review of
proposals coming under the jurisdiction of both agencies.
STATE CONTACTS

Bob Sundin, Director
Department of Environmental Quality
401 W. 19th St.
Cheyenne, Wyoming  82002
(307) 777-7937

Dick Hartman, State Planning Coordinator
State of Wyoming
2320 Capitol Avenue
Cheyenne, Wyoming  82002
(307) 777-7574

Richard Moore, Director
Industrial Siting Administration
Suite 500
Boyd Building
Cheyenne, Wyoming  82002
(307) 777-7368

-------
APPENDICES

-------
                                                  Appendix A

                  EPA PROGRAMS DELEGATED AND AUTHORIZED TO STATES

                                                  MAY 15, 1982

iEPA
Region
:
i;. /"
I? ... .
*b
\ •• *""*
r, <
•£•>
So- -.
F ' , '
*
*-••
«?
^
*
&* . „..,..., 	
&
h
i • "
x 	
1 '• • •
|>« j -.
r;'&
|l|f^X £. , j ,S,/ ,
State
Connecticut
Maine
Massachusetts
New Hampshire
Rhode Island
Vermont
New Jersey
New York
Delaware
Maryland
Pennsylvania
Virginia
West Virginia
Alabama
Florida
Georgia
Kentucky
Mississippi
Morth Carolina
South Carolina
Tennessee
Illinois
Indiana
Michigan
Minnesota
Ohio
Wisconsin
Arkansas
Louisiana
New Mexico
Oklahoma
Texas
Iowa
Kansas
Missouri
Nebraska
Colorado
Montana
North Dakota
South Dakota
Utah
Wyoming
Arizona
California
Hawaii
Nevada
Alaska
Idaho
Oregon
Washington
EPA PROGRAM
PSD
SIP1

'$$$&'$t$88&.






































SfeB!5:S-:SSiS-S-^
^S^^:::^S$:S








Full2


















































Partial3



Si&iSS














































NPDES
Delegated4


















































RCRA
Phase I5










'







































Phase II6
Application


















































^Indicates that the state has received full authority for the PSD program through a state implementation plan. The state
 promulgates its own regulations subject to EPA approval.
^Indicates that the state has received full delegation of the PSD program from the EPA; the state handles the technical and
 administrative aspects of permit issuance and implements the ERA'S regulations.
•^Indicates that the state has received partial delegation of the PSD program from the EPA. Usually the state performs the
 technical work and  the EPA actually issues the permit.
^Indicates that the state has been delegated the NPDES program.
^Indicates that the state has received authorization for Phase I of RCRA. Under Phase I, states enforce regulations
 applicable to generators and transporters of hazardous wastes, and facilities granted interim status.
^Indicates that the state has submitted final application to receive authorization for Phase II of RCRA. Under Phase II,
 states will permit treatment, storage, and disposal facilities under permanent status standards.

-------
                            Appendix B

                          BIBLIOGRAPHY
American Bar Associations.  The Need  for  Power  and  the  Choice
  of Technologies:  State Decisions on  Electric Power Facil-
  ities.  U.S. Department of Energy.  DOE/EP/10004-1, June
  1981.

City and County of Honolulu Department  of Land  Utilization.
  Guide to Land Use Laws in Honolulu.   1981.

Colorado Department of Natural Resources.  Colorado's Joint
  Review Process for Major Energy and Mineral Resource  Devel-
  opment Projects.  December 1980.

Connecticut Council on Environmental Quality.   Citizen's  Guide
  to the Permit Process.  1979.

Connecticut Department of Environmental Protection.  Permit
  Authority Index.  March 1981.

The Council of State Governments.  Untangling the Permit  Web:
  Washington's Environmental Coordination Procedures Act.
  June 1978.

Florida Department of Environmental Regulation.  Manual of
  State Regulatory and Review Procedures  for Land Development
  in Florida.  January 1981.

Greenwood, Richard.  "Energy Facility Siting in  North Dakota."
  North Dakota Law Review, Vol. 52, No. 4 (1976), pp. 703-
  728.

Hamilton, Michael S.  "The Permit Explosion:  Siting New
  Energy Facilities in the Western United States."  Colorado
  State University, Fort Collins, Colorado.  December 1980.

Hamilton, Michael S., and Wengert, Norman. "Environmental,
  Legal and Political Constraints on Power Plant Siting in the
  Southwestern United States."  Report  to the Los Alamos
  Scientific Laboratory, March 1980, at Colorado State  Univer-
  sity.

Hawaii Interagency Task Force for State Permit  Simplification.
  Preliminary Report of Findings and Recommendations.  March
  1981.

-------
                             228
Hopping, Wade L., and Raepple, Carolyn Songer.  "A Solution  to
  the Regulatory Maze:  The Transmission Line  Siting  Act."
  Florida State University Law Review, Vol. 8,  No. 3  (1980),
  pp. 441-461.

Illinois Environmental Protection Agency.  Procedures for
  Coordinated Permit Review.  November 1979.

Illinois Environmental Protection Agency.  Protecting Illinois
  Waters, A Cooperative Effort by You and  Illinois EPA,  Illi-
  nois Department of Transportation, Division  of Water
  Resources, Illinois Department of Conservation, U.S.  Army
  Corps of Engineers.  June 1981.

Illinois Institute of Natural Resources.   The  Illinois Coordi-
  nated Review Process for Major Energy Development Projects
  Program Design.  June 1981.

Illinois Institute of Natural Resources.   Interim Report—
  Synfuels Facilities Siting  Permits.  May 1981.

Kentucky Department for Natural Resources  and  Environmental
  Protection.  Report of the  Permitting and Facility  Siting
  Task Force, Phase 1—Permit Coordination.  April 1979.

Massachusetts Department of Environmental  Quality Engineering.
  Permit Directory—A Guide to Programs and Procedures.
  January 1980.

Minnesota Department of Economic Development.   Business
  Licensing Study.  Minnesota State Legislature, January
  1981.

Morell, David, and Singer, Grace, Center for Environmental
  Studies, with  the support of the  Division of Technology
  Overview, U.S. Energy Research and Development Administra-
  tion.  State Legislature and Energy Policy in the Northeast:
  Energy Facility Siting and  Legislative Action.  Brookhaven
  National Laboratory Regional Energy Studies  Program.   BNL
  50679, P4/CES  Report No. 40, June 1977.

National Governors' Association, Edward L. Helminski,  Direc-
  tor,  Energy and Natural Resources Program, Ned Helme,  Assoc.
  Director, David W. Stevens, Consultant.  "State Initiatives
  in  Expediting  Energy Facility Siting Review  Procedures."
  NGA White Paper, Washington, D.C., August 1,  1979.

-------
                              229
New Jersey Department of Environmental Protection.   A  Guide
  Through the New Jersey Department of Environmental Protec-
  tion.  January 1980.

New Jersey Office of Business Advocacy.  Directory  of  State
  Programs for Regulating Construction.  March  1979.

New York, New Jersey, and EPA Region  II Joint Task  Force  on
  Permit Consolidation.  Draft of Final Report  of the  Informa-
  tion Management Committee.  June  12, 1980.

New York, New Jersey, and EPA Region  II Joint Task  Force  on
  Permit Consolidation.  Report of  the Permit Administration
  Committee.  August 1, 1980.

North Carolina Department of Natural  Resources  and  Community
  Development Office of Regulatory  Relations.   North Carolina
  Environmental Permit Directory.   1981.

Ohio Power Siting Commission.  Citizen Participation.   May
  1978.

Rhode Island Department of Environmental Management, Division
  of Planning and Development.  Permitting Process—Major In-
  dustrial and Energy Facilities.   July 1981.

Rhodes, Robert M.  "Streamlining State Environmental Permit-
  ting—The Florida  Experience."  Natural Resources Lawyer,
  Vol. XII, No. 4, pp. 727-734.

South Carolina Coastal Council.  State Of South Carolina
  Coastal Management Program and Final Environmental Impact
  Statement.  1979.

Southern States Energy Board in cooperation with DOE Region
  IV.  "Energy Projects Proposed in Federal Region  IV  (1980-
  2000) Including Specific State/Federal Permit Requirements."
  Unpublished Report, Atlanta, Georgia, August  1980.

Southern States Energy Board in cooperation with Western
  Interstate Energy  Board and DOE Region VI (Dallas, Texas).
  "Energy Projects Proposed in Federal Region VI (1981-2000)
  Including Specific State/Federal  Permit Requirements."
  Unpublished Report, Atlanta, Georgia, February 1981.

Southern States Energy Board, Western Interstate Energy Board,
  Regulatory Reform  Institute.  Survey of State Permit  Consol-
  idation Initiatives—Draft Report.  U.S. Environmental  Pro-
  tection Agency.  Contract #68-01-5052, June 1981.

-------
                               230
  Texas House of Representatives, Committee  on  Environmental
    Affairs.   Subcommittee Report on Joint Permitting  Air  and
    Water Quality.  October 1980.

  Tosco Foundation.  Siting Major Energy Facilities:   A Process
    in Transition—Executive Summary.  Rockefeller  Foundation,
    State of  Delaware, State of New Mexico,  Tosco Corporation.
    October 1979.

  U.S. Geological Survey.  Permit Requirements  for  Development
    of Energy and Other Selected Natural Resources.  Series  of
    reports prepared for the U.S. Geological  Survey  and the
    following regional commissions:  Appalachian, Coastal
    Plains, Four Corners, Old West, Ozarks,  Pacific  Northwest,
    and Upper Great Lakes.  1981.

  Virginia Council on the Environment.  Environmental  Regulation
    in Virginia, A Guide for Permit Applicants.  November  1978.

  Virginia Council on the Environment.  Virginia's  Environment,
    Annual Report 1980.

  Western Governors' Policy Office, Linkhart, Doug.  "Permitting
    and Siting of Energy Projects:  Causes of Delay, State Solu-
    tions."  Study Report, June 1981.

  Western Interstate Nuclear Board.  Regional Factors  in Plan-
    ning and  Siting Electrical Energy Facilities in  the Western
    States.  U.S. Nuclear Regulatory Commission.  Contract
    #(49-24)-0249, April 5, 1977.

  Wisconsin Office of State Planning and Energy.  A  Citizens
    Guide to  the Wisconsin Environmental Policy Act.   May  1977.

  Wisconsin Public Service Commission and Wisconsin  Department
    of Natural Resources.  Docket 05-E1-13.   Background material
    for discussion at prehearing conference  re  the  Joint In-
    vestigation on the Effectiveness of Power Plant  Siting
    Procedures.  January 1981.
* F.S. GOVERNMENT PRINTING OFFICE: 1982 361-082/313

-------
U.S.  Environmental  Protection Agency
Region V, Library
230  South Dearborn Street
Chicago,  Illinois  60604

-------
United States
Environmental Protection
Agency
Official Business
Penalty for Private Use
$300
Special Fourth-Class Rate
Book
Postage and Fees Paid
EPA
Permit No. G-35
Washington DC 20460

-------