905R82111
UNITED STATES
ENVIRONMENTAL PROTECTION AGENCY
REGION V
      WATER DIVISION
  230 S. DEARBORN ST.
CHICAGO, ILLINOIS 60604
OCTOBER, 1982
             FINAL
                        vvEPA
                RESPONSIVENESS SUMMARY
                           FOR
          PUBLIC MEETING AND WRITTEN COMMENTS
                    ON THE REPORT ON
      COMBINED SEWER OVERFLOW FACILITIES PLANNING
                         FOR THE
        DETROIT WATER AND SEWERAGE DEPARTMENT

-------
McNichols  Combined  Sewer Overflow  Gates
located  in  the City  of  Detroit, on  the
Rouge  River.   Shown during  dry  weather.
Constructed  in  two  segments  of  three
barrels  each.  Barrels  measure 9  feet,  3
inches square in the left segment, and 11
feet  by  11  feet  9  inches  in the  right
segment -  each.

-------
                                 905R82111
        RESPONSIVENESS SUMMARY
                 FOR
  PUBLIC MEETING & WRITTEN COMMENTS
   ON THE REPORT ON COMBINED SEWER
     OVERFLOW FACILITIES PLANNING
               FOR THE
DETROIT WATER AND SEWERAGE DEPARTMENT
             Prepared By
 U.S. Environmental Protection Agency
      Jim Novak, Project Manager

                 and

              ESEI, inc.
    Peter Swinick, Project Manager
            October,  1982

-------
                     TABLE OF CONTENTS
TOPIC                                             PAGE NO,
Introduction	   1



Public Meeting Notification	   7



Summary of Issues Raised	  13



Comment Letters Received	,	  19



Public Meeting Transcript	  61



List of Public Meeting Attendees	  95

-------
INTRODUCTION

-------
                        INTRODUCTION

One of the major elements being covered by the Detroit Waste-
water Final Facilities Plan was combined sewer overflow  (CSO).
An environmental impact statement  (EIS) was prepared  concurrent-
ly with facilities planning.  A finding of the July 6, 1981  Fed-
eral District Court Order, was that the parties  (DWSD, MDNR, and
U.S. EPA) have agreed to suspend further CSO  facilities  planning,
but that U.S. EPA and MDNR wish to reserve their  rights  to peti-
tion the court in the future  for further relief  on CSO control.
CSO facilities planning was suspended June 25, 1981.  This plan-
ning culminated with the preparation of the Alternative  Facili-
ties Interim Report (AFIR).

Since the AFIR was not comparable  to a Final  Facilities  Plan and
identified no alternative for implementation, there was  techni-
cally no longer a need for the EIS to address CSO.  There was,
however, a need for a detailed overview of the planning  that was
completed.  The Report on Combined Sewer Overflow Facilities
Planning was generated in response to this need  and had  four
major objectives:

     1)  To review and summarize the combined sewer overflow
         planning that was accomplished up to the time of
         suspension,

     2)  To evaluate water quality improvements  estimated for
         the alternatives,

     3)  To independently evaluate the procedures used in
         facilities planning, and

     4)  To provide a basis from which a resumption of the
         CSO planning can proceed.

-------
It should be noted that this document was not intended to
explain or generate any decision or set any policy on the CSO
planning.  Its overall objective is to facilitate future CSO
planning.

The CSO Report covered many technical and non-technical sub-
jects which collectively brought planning accomplishments into
focus.  These subjects included:

     Section 1 - An introduction describing the purpose
                 and scope of the report,

     Section 2 - An historical account of previous planning,

     Section 3 - A description of the existing facilities,

     Section 4 - A description of the sewer system transport
                 model and the model generated CSO flows and
                 loadings,

     Section 5 - A description of the receiving water models,
                 model outputs and model generated "existing"
                 water quality estimates,

     Section 6 - A description of the alternatives development
                 procedure leading to the 25 CSO Alternatives
                 plus the Future-No-Action and Existing Condi-
                 tion Alternatives.  Also, the CSO site selec-
                 tion methodology and results are described.

     Section 7 - A summary of water quality improvements esti-
                 mated from modeling outputs.

     Section 8 - A description of the facilities plan evalua-
                 tion methodology used to rank the 25 CSO
                 Alternatives and identify the "few best".

-------
Section 9  -  A summary of revisions made to the alterna-
              tives between publication of the Preliminary
              and Final AFIR's.

Section 10 -  A critique of the evaluations and the  find-
              ings of the AFIR.

Section 11 -  Recommendations of the report (when CSO
              Facilities Planning resumes):

    1.  Alternatives for consideration should include, but
        not be limited to:  maximization of system storage
        and best management practices; and transfer  of flows
        from the Rouge River Basin to the Detroit River
        Basin.

    2.  Consider how to address CSO planning problems caused
        by upstream pollution sources.  The procedure should
        include a detailed review of "208" data and  all CSO
        planning data developed to date to redetermine if
        sewer overflows are a major problem in the Rouge
        River Basin.  Coordination of present and future CSO
        planning from the headwaters to the mouth would also
        be desirable.

    3.  The concept of spending to the point where marginal
        benefits equal marginal costs (dB/dC = 1)  may be un-
        affordable.  Future CSO control planning should con-
        sider a spending level where the marginal benefits
        exceed the marginal costs (dB/dC > 1).

-------
4.  Several improvements at the System Control Center
    (SCC) will maximize the usage of in-line storage for
    CSO control.

    These include:

a)  Verification of the in-line storage volumes and sub-
    sequent modification of procedures and equipment to
    ensure their utilization.

b)  Evaluation and refurbishment, where necessary, of  the
    SCC computer system hardware and software to ensure
    proper collection, storage, and processing of sewer
    system operational data.

c)  Evaluation, cleaning, replacement (if necessary) and
    recalibration of all field sensors to ensure that
    accurate signals are being transmitted to the SCC  com-
    puter.

d)  Development of a preventive maintenance program to
    increase reliability of the critical components of
    the SCC and the field sensors.

-------
PUBLIC MEETING NOTIFICATION

-------
                  PUBLIC MEETING NOTIFICATION


1.  Notice of the Public Meeting was Published in;

         A.  Detroit News on 7/11/82

         B.  Detroit Free Press on 7/11/82

         C.  Local Newspapers on 7/19/82
2.  Notice of the Public Meeting was mailed to 2700 interested
    parties on 6/21/82.
3.  One photostatic copy of the Document was placed in each
    of ten Detroit area libraries on 6/22/82 and 6/23/82.
4.  One original copy of the Document was placed in each of
    ten Detroit area libraries on 7/8/82.
5.  Over 150 copies of the Document were distributed by request
    between 7/19/82 and 9/1/82.

-------
                                   UNITED STATES
                         ENVIRONMENTAL PROTECTION AGENCY
                                      REGION V
                                230 SOUTH DEARBORN ST
                                CHICAGO ILLINOIS 60604
                             NOTICE  OF  PUBLIC  MEETING
                                                                   REPLY TO ATTENTION OF
                                                                      5WFI
 Region  V of the U. S. Environmental  Protection  Agency  will  hold  a  Public  Meeting
 on Wednesday, July 21 at  7:30 p.m.  at the  Henry Ford Centennial  Library Audito-
 rium, 16301 Michigan Avenue, Dearborn, Michigan to  discuss  the Report  on  Combined
 Sewer Overflow Facilities Planning  for the  Detroit  Water  and  Sewerage  Department.
 This report was prepared to summarize and  review all Combined Sewer  Overflow
 (CSO) facilities planning to date and to provide a  conceptual framework for CSO
 planning when it is resumed.  Copies of this  report are available  for  your in-
 spection at the following locations:
 Baldwin Public Library
 351 Martin
 Birmingham, Michigan  48021
 Attn:   Ms. Lee Tuttle

 Troy Public Library
 510 W.  Big Beaver Roac
 Troy,  Michigan  48084
 Attn:   Mr. Joseph Howey

 Beacon  Memorial  Public Library
 45  Vinewood
 Wyandotte, Michigan  48192
 Attn:   Ms. Tinsley

 Detroit  Public Library,  Main  Library
 5201 Woodward
 Detroit, Michigan   48202
 Attn:   Mr.  Dance

 Henry Ford  Centennial  Library
 16301 Michigan A,venue
 Dearborn,  Michigan   48126
 Attn:   Ms.  Fran Delaney
    erely yours,
 Wayne  State Universtiy,  Purdy Library
 Room 130  •
 Detroit, Michigan   48202
 Attn:   Dr.  Vern  Pings
Bloomfield  Public  Library
1099  Lone Pine  Road
Bloomfield  Township,  Michigan
Attn:  Mrs.  Bamberger
48013
Wayne Oakland  Library Federation
33030 Van Born Road
Wayne, Michigan 48184
Attn:  Ms. Dolores Hayden

Detroit Public Library, Downtown
121 Gratiot
Detroit, Michigan
Attn:  Mr. Dance

SEMCOG Library
800 Book Building
Detroit, Michigan  48226
Charles H. Sutfin
Director, Water Divisiion

If you would like a personal copy please fill  in the  information  requesTelT~D^low,
fold, staple, and mail (no postage is required if mailed in the United States).

     Name
     Street Address
     City,  State & Zip Code
                                          10

-------

»»
SSfcsSM

                      COME TO
                           at the
                 Henry Ford Centennial
                   Library Auditorium,
                   16301 Michigan Avo.
                   Dearborn, Michigan
                         7:30 p.m.
                Come to a discussion of the findings
                of the Combined Sewer Overflow
                Report issued by EPA as part of the
                Detroit Water and Sewerage
                Department's facilities planning
                work. For further information call
                ESEI, inc.; 313-961-3940.
                Please note: This meeting was
                rescheduled from the previous date
                of May 26, 1982.

-------
SUMMARY OF ISSUES RAISED

-------
                 SUMMARY OF  THE  ISSUES  RAISED
                     AT THE  PUBLIC  MEETING
                             ON THE
     REPORT ON COMBINED SEWER OVERFLOW  FACILITIES  PLANNING
         FOR THE DETROIT WATER AND  SEWERAGE  DEPARTMENT
The major issues raised by participants  at  the  special  meeting
on the Report on Combined Sewer Overflow Facilities  Planning
for the Detroit Water and Sewerage  Department are  summarized
below.  The response of USEPA  to  these  issues is also briefly
summarized.  A transcript of the  meeting, including  the presen-
tation, all questions and all  responses  is  included  in  a later
section of this Responsiveness Summary.

Issue:     Why was the recommendation of basin-wide  planning
           made by the Citizen's  Advisory Committee  (CAC)
           omitted from the recommendations  chapter  of  the
           report?

Response:  The Report recommends  coordination of all facil-
           ities planning work completed to  date in  the Rouge
           Basin (a coordinated approach).   The USEPA,  however,
           cannot dictate how  the State  of Michigan  will  con-
           duct its water quality planning or how  it will pri-
           oritize its projects.  Thus,  basin-wide planning  is
           ultimately a state  responsibility.  Also, to imple-
           ment basin-wide planning, some agency would  have  to
           be designated as the "grantee" and currently none  of
           the participants, except the  State, has authority
           over the entire basin.

Issue:     Is the USEPA and the City of  Detroit setting  a pre-
           cedent for future CSO planning by suspending  work  on
           the Detroit Facilities Plan?
                            15

-------
Response:  No precedent was being  set.  The Detroit  Facilities
           Planning was suspended  - not terminated - by  the
           July 6, 1981 Federal Court Order.   (For elaboration
           see Public Meeting Response by Novak on page  70.)

Issue:     Wayne County had commissioned a study of  the  effects
           of CSO's on the Upper,  Middle, and  Lower  Branches of
           the Rouge River.  The preliminary findings  indicate
           that background water quality can be improved.  Can
           the DWSD Rouge River water quality  models be  rerun
           to simulate the impact  of cleaner background  water
           quality on the Rouge River alternatives for the
           Detroit area?

Response:  One of the recommendations in the USEPA report was
           to integrate all of the information that  has  been
           generated by the facilities planners in the Rouge
           Basin.

Issue:     Lake Erie has not improved since USEPA began  to
           implement facilities planning and DWSD has not
           assisted in the lake's  clean up.

Response:  The USEPA has assisted  DWSD to significantly  reduce
           the amount of pollutants from the treatment plant to
           the Detroit River and thus ultimately to  Lake Erie.
           In fact for the past year, for example, the treat-
           ment plant has been reporting an average  concentra-
           tion of phosphorus in the effluent  below  the  1.0 mg
           per liter limit in the  permit.

Issue:     Does the Report on Combined Sewer Overflows consti-
           tute official USEPA policy regarding CSO  planning in
           Detroit?
                             16

-------
Response:  The document  is  not  a  policy  statement  but  simply a
           summary and commentary on  the  facilities  planning to
           date.

Issue:     Shouldn't SEMCOG,  as the regional  planning  agency,
           coordinate all water quality  planning?

Response:  SEMCOG reviews the facilities  plans  after they have
           been completed.  SEMCOG is  not in  the position of
           directing facilities planning.
Issue:
Is the report issued in final version at this time?
Response:  The report  is  a  final  report,  but  a  responsiveness
           summary  (this  summary)  will  be prepared  to  address
           all issues  or  questions raised at  the  public  meeting
           or sent  to  USEPA.

Issue:     There were  serious  omissions of  data and  references
           in the report, (Ph.D.  or Master's  Theses  generated
           in conjunction with  the water  quality  modeling).

Response:  The Responsiveness  Summary can be  expanded.   (Sub-
           sequently,  a bibliography has  been included  in  the
           Responsiveness Summary.)

Issue:     The most serious water  quality problem is in  the
           Detroit  River and not  in the Rouge River  as stated
           in the special report.   Considering  that  there  are
           18 bathing  beaches  and  60 marinas  downstream  of  the
           treatment plant, Lake Erie itself  should  be a major
           concern.

Response:  The Responsiveness Summary will  include any further
           elaborations and commentary  that is contributed.
                             17

-------
Issue:     The City of Allen Park may be  required  to  spend  60  •
           100 million dollars for sewer  separation,  for  the
           same water quality problems  that USEPA  is  recommend-
           ing that the City of Detroit take  no  action.   The
           same methodology and conclusions should  be  applied
           to Allen Park as to Detroit.

Response:  The Report on CSO does not recommend  no  action.
           Facilities planning was suspended  and no conclusion
           on CSO was reached.
                            18

-------
COMMENT LETTERS RECEIVED

-------
                 COMMENT LETTERS RECEIVED
The following section is arranged to show the comment letters
on the left side page and the response to individual comments
directly to the right on the right side page.
                             21

-------
               (Ettg   of   Alirn   Park
                     OFFICE  OF THE  MAYOR
                        FRANK J. LADA
                      16850 SOUTHFIELD ROAD
                     ALLEN PARK, MICHIGAN 48101
                         PHONE: 928-1400
                        July 20, 1982
U.S. Environmental Protection Agency
Office of Grants and Administration
Region 5
230 South Dearborn Street
Chicago, Illinois   60604
        Re:
Gentlemen:
Report on Combined Sewer Overflow Facilities
Planning for the Detroit Water  and Sewerage
Department
        The City of Allen Park appreciates the opportunity to
comment on the "Report on Combined Sewer Overflow Facilities
Planning for the Detroit Water and Sewerage".   We have a  special
interest in this report for two reasons.

        1.  A portion of Allen Park is served  by the  Detroit
system, and, therefore, our residents are affected by any
changes in capital and 0 & M expenditures.

        2.  The remainder of Allen Park is served by  a combined
sewer system, for which a Facilities Plan has  been prepared,
coming to diametrically opposed conclusions to your report.

        Our general comments on the above report are  as follows:

        1.  The conclusion of the report, which is based  on
extensive modeling and analysis, indicates that little or no
activity relative to combined sewer overflows  is warranted at
this time.  Particularly, in regards to the Detroit River over-
flows.  Allen Park agrees with this finding, generally, and has
found, that using nearly the same methodology  of analysis, that
for a similar, but smaller, combined system in Allen  Park that
little or no action will result in the most reasonable solution
there, also.
                             22

-------
                             RESPONSE
As a point of clarification, the Report on CSO does recommend further
evaluation of potential improvement to the System Control Center.   No
other activity is recommended at this time since facilities planning was
suspended, but this in no way should be construed to be equivalent to a
recommendation of No Action.  On the contrary, a recommendation of the
"No Action" alternative would require completion of the Facilities Plan
as would the recommendation of any "Action" alternative.
                              23

-------
U«S. Environmental Protection Agency - July 20, 1982 - Page 2
        2.  We find it ironic and tragic that EPA is encouraging
the expenditure of about $60 million to $100 million for sewer
separation in Allen Park (about $5,000 - $8,500 per household
with all its disruptive and destructive effects)  while the sewer
separation alternatives in the Detroit study area ranked amongst
the poorest choices of the 25 evaluated.  The cost of the high-
est ranking alternatives in the Detroit report are $130-145 per
capita.  How can EPA/DNR justify the extreme disparate treatment
to different portions of the same small City?

        3.  Allen Park believes that the basic recommendation,
that when planning is resumed, that primary consideration be
given to in-line storage and inter-basin transfers is appro-
priate.  Allen Park would like to submit that similar finding
should be applied to that portion of the City of Allen Park
served by the Wayne County system.

        4.  Allen Park requests that the EPA/DNR consider these
findings and bring uniformity to CSO planning in the southeast-
ern Michigan area, or at least Allen Park, before $60 million to
$100 million is wasted on sewer separation in Allen Park.  We
suggest that EPA/DNR take proper action to alleviate this
serious discrepancy.

        5.  Allen Park agrees with  the finding that there is a
need to look at the overall collection and treatment system in
detail before a conclusion can be reached.  This was not done in
the City of Allen Park and has led  to erroneous conclusions.

        Our specific comments on this report will be submitted
in writing in the next few weeks.

        Again, we appreciate this opportunity to comment and
strongly urge EPA/DNR to act to bring about uniformity on CSO
planning in southeastern Michigan,  before a major misappropria-
tion of public funds is made.  Since it currently appears that
                            24

-------
                                RESPONSE
2.  A finding of the July 6, 1981 Federal District Court Order was that the
    parties  (DWSD, MDNR, U.S. EPA) have agreed to suspend further CSO
    facilities planning, but that U.S. EPA and MDNR reserve their rights to
    petition the court in the future for further relief on CSO control.

    The suspension of Detroit's CSO facilities planning effort was primarily
    due to the questionable status of future federal funds to construct CSO
    control facilities.  Further expenditures for facilities planning would
    prove unwarranted if construction never occurred, or if it occurred years
    from now under different conditions.  Under the present situation of
    limited funds, while it is still necessary to meet the requirements of
    the Clean Water Act, the project priority system mandated by the Act
    determines the allocation of funds within the State.  At this time, CSO
    projects generally are not ranked high within the priority system.  On
    the other hand, the decision to obligate funds for the Ecorse Creek pro-
    ject, of which Allen Park is part, was made under different (lesser) fund-
    ing constraints.  The funds have already been made available for the
    Ecorse Creek project, quite a different situation than an evaluation of
    planning in light of the December 1981 amendments to the Clean Water Act
    and corresponding regulations which means a general reduction in funds
    for CSO projects.

    The "disruptive and destructive effects" of sewer separation is a factual
    determination to be made for each project.

    The total cost for the Ecorse Creek project is approximately $65 million,
    of which 75 percent or $48.8 million is funded by a federal grant; 5
    percent, or $3.2 million by a state grant; and the remaining 20 percent,
    or $13 million by apportionment among the four communities within the
    Ecorse Creek basin (Lincoln Park, Taylor, Dearborn Heights, and Allen Park)

3.  The Ecorse Creek project has an approved facilities plan, construction
    in the other communities is substantially complete, and a Federal Court
    has ordered the grantee to complete the remainder of the project within
    Allen Park.   Accordingly, non-final facilities planning in Detroit cannot
    be compared to the project in Allen Park.

4.  See Response for Item 2.

5.  The Allen Park project was evaluated in light of its role in solving the
    water pollution problem within the Ecorse Creek basin along with the other
    communities.   Accordingly, the proposed project was to effect water
    pollution control as an overall system.   The water quality improvements
    by completed work in the other communities cannot be realized until the
    full system is complete.
                                   25

-------
U.S. Environmental Protection Agency - July 20,1982 - Page 3
EPA/DNR intend to pursue the wasteful sewer separation project
in Allen Park, we request that some indication be given now by
these agencies that a rational policy will be pursued.

                        Yours truly,
                        Frank J.  Lada
                        Mayor for the City of Allen Park
cc:  Mr. Richard Hindshon
     Grants Administration
     Department of Natural Resources

     Mr. Charles N. Youngblood
     Wayne County Drain Commissioner

     Mr. John D. Dingell
     Congressman of the 16th District

     Mr. Valdaz Adamkus
     U.S.Environmental Protection Agency
     Region 5

     Ms. Ann Gorsuch,  Director
     U.S.  Environmental Protection Agency

     Ms. Janis Bobrin
     AWQB Coordinator
     SEMCOG
                             26

-------
                                RESPONSE
Again, it should be noted that the federal district court has  ordered the
grantee and the City of Allen Park to complete the project in  Allen  Park.

Thank you for your comments.
                                  27

-------
Giffels/Black& Veatch
 A Joint Venture
                         200 Renaissance Center, Suite 1220, Da*fbit. Michigan 4S243 (313)259-5300
Detroit, Michigan
Facilities Plan
Mr. Charles M. Beckhara, Director
Detroit Water and Sewerage Department
Water Board Building
735 Randolph Street
Detroit, Michigan  48226

Attention:  Mr. John McGrail

Dear Mr. Beckham:
          July 21,  1982
          B&V Project 7889
          GAI ProJ
          File.A.I
                                                                         \
Re:   DWSD
DWSD PM^ect, CS--'806-
EIS Consultant Final,Report
Group 14 C^J" !  If'-!  '
                  ••— -i3., - - •-'
Attached are comments on the Environmental Consultant's  audit  of  the
combined sewer overflow studies conducted by the Joint Venture.   The
comments are intended to be constructive and we trust will  be  accepted  as
such by all parties concerned.   We were surprised to receive on July  16  a
bound copy of the CSO Report marked "Final".  We trust this was an  error
and that these comments can be  incorporated into the report.

In addition to the attached comments,  we feel there are  four primary  points
regarding the combined sewer overflow studies that should be made:

     o    Had the facilities planning effort on combined sewer overflows
          not been stopped short of completion, it is likely that the
          "Future No Action" alternative would have been selected.  This
          would have eliminated the need to try and pick up the work  and
          continue planning at  some future time when funds  become available
          for construction.

     o    The Environmental Consultant's report does not document the 1980
          field data, which are available even if only in unanalyzed  format.
          These were the most important field data of all,  as  they  are
          vital for recalibration and verification of the several complex
          and interrelated system models.

     o    Most importantly, the project was terminated before  the user's
          manuals for the several complex modeling programs were  written.
          Without this documentation,  the immense amount of time  and  effort
          that went into modification and development of these specialized
          models is lost to the City and to the profession. At this  point
          even the subconsultant, who had the major input into developing
          the models, would have some difficulty in reactivating  them.
Giffels Associates. Inc.
Architects Engineers Planners
                                 28
                Black & Veatch Michigan
                Consulting Engineers

-------
                               RESPONSE
The report on CSO is a final report, but as stated in the public meeting of
July 21, 1982 - a responsiveness summary addressing meeting comments and
written comments will be prepared and distributed.
When planning is completed, a selection will then be made.
The Environmental Consultant did not document the 1980 field data since it
was not available to them.  We agree that these data would be very valuable.
We will be formally requesting the submittal of this data from the grantee.
The lack of documentation is also frustrating to the USEPA.   One reason this
report on CSO was completed, was to assess the status of the CSO facilities
planning at the time of suspension.
                                 29

-------
Mr. Charles M. Beckham               2                 July 21,  1982
     o    The model programs and the massive amount of quantity and quality
          data entered into the computer data base has been stored on tape,
          a copy of which was delivered to DWSD at the termination of the
          project.  Every effort should be made by the City to ensure that
          this data bank and the computer programs are not lost.   Any con-
          tinuing charge for storage would be minor compared to the cost
          and effort in reestablishing the programs and the data  base.

We appreciate the opportunity to comment on the Environmental Consultant's
summarizing report.

                                        Very truly yours,
                                        R. 'E. Filardi
                                        Giffels/Black
                                        Project Manager
Giffels/Black^& Veatch'
WEF/MJG/REF/lhj
cc:  J. McGrail   - DWSD
     P. Swinnick  - ESEI
     G. Cottrell  - G/B&V
     C. Sutfin    - EPA
                                  30

-------
                                  RESPONSE
Agreed.
                                    31

-------
                  COMMENTS BY GIFFELS/BLACK & VEATCH




                                ON THE




    "REPORT ON COMBINED OVERFLOW FACILITIES PLANNING FOR THE DWSD"




                             BY ESEI Inc.




                              June 1982
     1.  PAGE i, PARAGRAPH 1.  The statement "Certain methodologies... seem




inappropriate given the data and circumstances" is not supported by the




report.  The text of the CSO Report suggests alternatives but does not




demonstrate or call any methodology inappropriate.  We suggest a re-phrasing




as follows:  "Facilities planning results to date, plus the new or changed




circumstances surrounding the subject matter, indicate that resumption of




planning will probably involve different assumptions and, therefore,  modi-




fied methodologies".




     2.  PAGE i, LIST OF CENTRAL DOCUMENTS.  We recommend the addition of




two reports:  "Flow Management Report", May 1981 and "Existing Preliminary




Treatment Complex Evaluation Report", April 1981.




     3.  PAGE ii, LAST PARAGRAPH.  The phrase "very complex and difficult




to understand" is suggested as a substitute for the word "confusing".




     4.  PAGE 1-1, PARAGRAPH 1.  The phrase "... summarizes much of..." is




suggested instead of "...is their summary of ...".  The AFIR was originally




only a progress report on some of the planning activities, and was never




intended to provide full coverage of all the planning; witness the fact




that modeling was not extensively covered.  Some increase in scope was




attempted when the Federal Court mandated that the planning process cease




with the AFIR, but time and other constraints did not allow full coverage.




                                     1
                                  32

-------
                                RESPONSE
The Summary of Comments on FFP Environmental Analysis by Parameter  (Table
10-10, page 10-43) lists several FFP environmenal analyses which were
considered inappropriate for preliminary and/or final screening of alter-
natives.  The reasons are also listed.  This Table is supported by a complete
discussion of the FFP Environmental Evaluation, Section 10.3, pages 10-33 to
10-42.  For methodologies other than for environmental evaluation, we agree
with your re-phrasing.
We accept this and these reports should be included on our list as 4d and
4e, respectively.
We agree.
We agree.
                                  33

-------
     5.  PAGE 1-1, LIST OF OBJECTIVES.  Two more objectives are considered

to be of prime importance and should be added:



    "5.   To provide documentation for all available water quality data.



     6.   To provide user's manuals for all of the water quality model

          programs developed and used in the Facilities Planning."



Full documentation of the data base should include the Spring 1980 monitor-

ing data.  It was crucial to model recalibration and would prove extremely

useful to future planning.  Project constraints caused DWSD to trade off

full documentation and generation of water quality data in hard copy for

other deliverables, but data are currently (and have been since project

termination) available on magnetic tape at DWSD.

     The recalibrated and verified models, which represent a substantial

investment, would be very useful to future planners, who could immediately

implement them if their use and basis were described in user's manuals.

Project budget and schedule constraints also caused DWSD to trade off

generation of user's manuals for other products.  Although some documenta-

tion is available through Wayne State graduate student dissertations, this

is not enough.  Generation of user's manuals should proceed while the

people involved are available, and they still have some recollection of the

various programs.

     6.  PAGE 1-2, LAST PARAGRAPH.  In line with Comment No. 4 above we

suggest the following rephrasing:

     o    "... AFIR became the final deliverable..." instead of " ... AFIR
          was the..."
                                  34

-------
                                RESPONSE
The four objectives listed on page 1-1 are specific to the subject CSO
Report, June 1982.  The two objectives you have listed are applicable to
the Final Facilities Planning effort.  These were never carried out, as
you have stated, but we believe, would still be a worthwhile endeavor of
the DWSD.
We agree.
                                  35

-------
     o    "Early in 1981 the Federal District Court mandated that it was
          to serve as a stopping point..." instead of "It was mandated...,
          and was to serve as a stopping point...".

     7.  PAGE 3-2, PARAGRAPH 2.  The last two sentences should be expanded

to properly describe the current status of the NI-EA.  We suggest the

following:  "A third major ...(NI-EA) is almost finished, with approximately

2500 ft more required to bring it into the DWWTP.  A pump station would be

required to allow it to convey suburban sanitary sewage and/or to transport

and store combined sewage.  However, work on both the interceptor and the

pump station have been stopped by Court Order, with MDNR concurrence,

because of the lack of construction grants funding."

     8.  PAGE 4-1, PARAGRAPH 1.  The first statement, "The determination of

CSO...rather than direct measurements" could be misinterpreted.  We suggest:

"Current CSO quantity and quality were ascertained through statistical

analysis of direct measurements.  The statistical characteristics and

trends observed were incorporated into the models and utilized to estimate

variation over time and under changed operational conditions." The latter

phrasing expands on the actual sequence of analysis, which is standard

practice, and which led up to the "CSO Quantity and Quality Report", whose

tables and figures represent or were extrapolated from actual collected

data.

     9.  PAGE 4-6, TABLE 4-1.  Most of the Baby Creek East (BCE) watershed

flows are received by the DRI through the Livernois, Morrel and other

sewers, not by the 0-NWI.

     10.  PAGE A-25, PARAGRAPH 1.  Field problems had nothing to do with

the makeup of the calibration set.  The six storms were selected from the

available data because they provided the best representation of total
                                   36

-------
                                RESPONSE
We agree.
We agree.
We agree.
You are correct.  This change should be noted.
                                   37

-------
system and receiving stream operation during storm conditions.  The full 25




storm set was not used because it does not always overflow at all locations




and, due to cost and logistic constraints, Detroit River receiving quality




cruises were not scheduled for all events.  It is suggested that the text




be modifified to "Of the 25 monitored storm events the six providing the




best representation of storm conditions were selected for model calibration."




     11.  PAGE 4-26, PARAGRAPH 2.  "...the 1980 data is unavailable."  See




Comment No. 5 above.  No hard copy or documentation was generated due to




project constraints, but the data was and is available on magnetic tape at




DWSD, as part of the Water Quality Data Base.   To fulfill the purpose of




the CSC Report, both documentation and hard copy production should be




provided.




     12.  PAGE 4-32, PARAGRAPH 3.  We suggest that "While this provides...




or by seasons" be modified to read "This provides information on any one




mean value.  To compare the amount of variation by river, season or among




different parameters at the same site, the investigator must access the




water quality management programs data base and perform the desired sig-




nificance tests."  The programs to operate on the data and the data them-




selves are on magnetic tape at DWSD.  Some such tests were performed but




the results were not included in the hard copy tabulations.  The Joint




Venture believes that direct interpretation of the statistical data is open




to speculation, because of the complexity of the system.




     13.  PAGE 4-46, PARAGRAPH 2.  The criteria cited as used for average




year selection are not totally correct.  They should be replaced by the




ones provided on Page 6-1, last paragraph, of the CSO Report.
                                  38

-------
                                  RESPONSE
 This clarification is quite acceptable.
We agree.
                                   39

-------
     14.  PAGE 5-18, LAST PARAGRAPH.  Current phrasing could be misinter-




preted and thereby mislead the reader.  The fact is that QUAL II was selected




for dry weather flow, steady state condition simulation because stream




flows and input are essentially constant during these conditions and because




extreme flow variations do not happen at these times.  RECEIV II was selected




to model dynamic storm (extreme) conditions.  We suggest rephrasing to




read: "QUAL II was selected to model dry weather flow steady state conditions




because it assumes essentially unvarying stream flows and input waste




loads, conditions which accurately reflect dry weather periods.  Extreme or




dynamic conditions, such as those experienced under storm conditions, were




simulated by another model, described in Section 5.3.2.2 below."




     15.  PAGE 5-24, LAST PARAGRAPH.  The statement "The basic difference...




water quality planning" could easily be misinterpreted.   RECEIV II i^




specifically geared to model storm (high flow) conditions.   It is the




modified version of the SWMM Receiving Water Block, modifications that




enhanced rather than detracted from its urban storm modeling role.  We




suggest that the text be modified to read: "The basic difference between




SWMM Receiving Water block and RECEIV II is one of degree and flexibility;




while both simulate storm (high flow) conditions associated with urban




drainage problems, RECEIV II is better geared toward water quality planning."




     16.  PAGE 5-46, PARAGRAPHS 2 AMD 3.  It is correct that no sampling




data were available for many (in lieu of most) of the 36 data points.




Preliminary investigations of existing sources led us to believe these were




sufficient and therefore no sampling was scheduled.  When in fact some




locations were found to have little or no data, in line with accepted and
                                  40

-------
                                RESPONSE
Your rephrasing is agreed with and should be considered as replacing the
last paragraph of page 5-18.
We agree with your modification.
We could not confirm that sampling data were available for most of the 36
data points, although two staff members spent a day in the Black and Veatch
library searching.  We do not question that accepted methods were used to
derive missing data, but we did wish to call attention to the fact that
sampling data was not the basis of the majority of the 36 data points.
                                  41

-------
standard practice for similar cases, we assumed values satisfying observed




upstream and/or downstream steady state conditions.  We suggest insertion




of a phrase in the CSO Report indicating the procedure used to be accepted




practice.




     17.  PAGE 5-57, PARAGRAPH 3.  To reflect the circumstances more




accurately we suggest that the statement "As with the Rouge River model,




these...contained certain errors..." be rephrased to read "As with the




Rouge River model, in order to meet a stringent deadline, Detroit River




model outputs were distributed as they became available,  without the benefit




of the analysis normally performed before release.  Review indicated the




need for changes and modifications, requiring output to be corrected in




updates."




     18.  PAGE 8-8, PARAGRAPH 1.   In the AFIR report (see Page 1-11), based




on project data and analytical results, the JV recommended that the FNA be




included with the "few best" for future analysis.  This decision was based




on the observation that only minimal incremental benefits accrued from




increased control, a conclusion only made possible by the analytical effort




up to that date.  The statement "Although the FNA..., no assessment was




made of whether any alternative should be chosen over the FNA alternative."




neglects to mention that selection of one preferred alternative was always




scheduled for the last planning phase, which the JV was not allowed to




perform.  There is the strong possibility that the FNA alternative would




have been recommended.  We therefore suggest that the text be changed to:




"Although the FNA alternative was used to calculate benefits and costs of




the 25 specific control alternatives, the planning process was halted by
                                  42

-------
                                  RESPONSE
We agree with this clarification.
We agree with this restatement.
                                      43

-------
Court Order before assessment was made of whether any alternative should be




chosen over the FNA alternative."




     19.  PAGE 8-1A, PARAGRAPH 2.  Three issues require clarification.




First, the revised cost figures were not available until mid-May, but the




results and the support calculations were made available to DWSD at the




project end as part of the back-up calculations; anyone could have accessed




them.  The JV suggests the note be deleted altogether or modified to reflect




cost figure availability.




     Secondly, the FNA was not suddenly assigned a substantial cost; the




May AFIR included a cost within 12% of the final figure.  The reasons for




the cost were amply discussed with DWSD and the EIS consultant and are




clearly explained in the (final) June AFIR.  The sentence "Also, a substan-




tial cost...zero." should be deleted.




     Finally, the JV internally reiterated not only the cost/benefit




analysis, but the total screening and ranking, and saw no reason to change




the report since the same "few best" alternatives resulted.  This is further




explained in Comment No. 20 below.  The statement "However, the facility




planner did not..." would better reflect what happened if rephrased as




follows:  "An internal revision of all the alternative screening and ranking,




including the cost/benefit analysis, did not modify the alternatives included




in the few best."




     20.  PAGES 9-1, PARAGRAPH 1 AND 9-2, PARAGRAPH 2.  The costs of the




FNA was not radically changed (see Comment No. 19 above); thus the statement




"The cost of the FNA alternative also was radically changed," on Page 9-1




should be deleted.  Paragraph 2 of Page 9-2 should also be deleted; it
                                    44

-------
                                  RESPONSE
The EIS Consultant verbally requested the revised cost data twice and was
told that it was not available.  The matter was not pursued further.
Although the May AFIR did include a cost for the FNA, the costs the EIS
Consultant analyzed were obtained in February of 1981 and in this cost data
FNA was assigned a cost of zero.  Since the February cost data are presented
in Tables 8-3 and 8-4, the reader should be forewarned that the costs were
later modified.  We agree that the assignment of costs to the FNA was
amply discussed and we do not disagree with the decision to make such an
assignment.
We agree.
                                      45

-------
apparently results from a misunderstanding.  The costs attributed to the




FNA alternative result from items considered as "givens", such as the NI-EA




and Pump Station No. 2.  This affected all the alternatives in like manner,




making the FNA cost a base cost.  The benefit cost computations were redone,




but were unaffected by this cost increase, since the basis is the difference




in cost between an alternative and the FNA.  The cost difference was only




affecLed by the changes in storage and treatment shown on Table 9-1, and




not by the FNA cost.




     As noted in Comment No. 19 above, the facilities planner did engage in




the rescreening and reranking of the alternatives with the revised costs




and conditions.  The matter was not pursued officially because the same




"few best" alternatives resulted, confirming a prior sensitivity analysis.




While modeling indicated that the reduction of excess storage and the




elimination of unused treatment modules did not affect water quality, it




still affected related elements such as cost, disruption to the environment,




etc.  The rescreened and ranked alternatives mostly maintained their




relative positions with respect to these factors, but the difference between




these and other alternatives was less marked.  The few alternatives that




did change rank did not change enough to be included in the "few best".




Thus the statement on Page 9-1, "These revisions were not used..." should




read:  "The Facility Planner reevaluated the cost/benefit, environmental,




implementability, technical, and economic analyses with these incorporated




revisions; the same "few best" alternatives resulted, confirming prior




sensitivity analyses."
                                   46

-------
                                  RESPONSE
We agree.  The CSO Report should make the reader fully aware of the rescreen-
ing and reranking.
                                      47

-------
     21.  PAGE 10-1, PARAGRAPH 1.  The circumstances mentioned in "The




subject areas covered...without regard to the circumstances..."  are an




integral part of (in many cases the sole reason for) the subject areas.




While objective critique certainly requires that the circumstances be




excluded, more explanation is necessary to do them justice to the subject




area and avoid misrepresentation of the facts and issues.  We suggest




inserting the following sentence before the above quoted statement.  "The




reader should also understand that these circumstances are an integral




part, of the planning techniques used and, in many cases, are the sole




reason for them."




     22.  PAGE 10-3, SECTION 10.1.1.1, REACTION RATES.  While it is true




that the rates were not supported by field data, the JV had indicated that




it considered setting these rates equal to zero reasonable because of the




rapid travel time in the Rouge River.  Flow reaches the Detroit River in a




matter of hours, rendering any effect of the rates negligible.




     As mentioned in Comment No. 5 above, although some calibration and




verification documentation is available, the absence of complete documen-




tation and user's manuals was a conscious DWSD trade-off.  We recommend it




be carried out as soon as possible, enabling a reassessment of the CSO Report




comments with regard to calibration/verification and related issues.




     23.  PAGE 10-7, PARAGRAPH 1 AND 10-8, PARAGRAPH 2.  See Comment No. 22




with respect to calibration/verification.  Furthermore, no claim was ever




made by the modelers of absolute numbers at the current planning stage; the




models were only intended to differentiate relative effects.  The small




observed difference was interpreted by the modelers as having no sigficant




difference between the alternatives or between the alternatives and FNA.




This should be brought out in the CSO Report.




                                     9
                                   48

-------
                                RESPONSE
Agreed.
We agree that lack of complete documentation and users manuals makes inter-
pretation of the models and the supporting data difficult, however, your
recommendation is more appropriately directed to your former client, DWSD.
Agreed.
                                 49

-------
     24.  PAGE 10-17, PARAGRAPH 2 AND PAGE 10-19, PARAGRAPH 2.  See Comments




No. 18 and No. 23.  The JV interpretation was that only minimal differences




exist between the alternatives and the FNA, a conclusion shared by the




CSO Report.




     25.  PAGE 10-20, PARAGRAPHS 2 AM) 3.  The authors of the CSO Report




were able to suggest redefinition of the optimal point after they observed




the results of current definition analysis.  In like manner the CSO Report




suggestion to use dB/dC = maximum could be questioned.  With this differ-




entiation, the public decides whether to spend more money or less, rather




than the more basic question of should any money be spent at all?  The AFIR




addresses this by recommending that FNA be considered as one of the "few




best", and therefore that it be subject to a future analysis that could




result in its selection as the preferred alternative.




     A rough calculation and re-ranking, using the CSO Report's alternate




strategy ranking for cost/benefit, along with the rankings of the other




categories (implementation, environment, etc.), still produced the same




"few best".  The JV suggests modification of Section 10.2.2 - Optimization,




to reflect these comments.




     26.  PAGE 10-29, PARAGRAPH 1.  The assumption that society values the




benefits of pollution in direct proportion to cost was not made in a vacuum.




It was recognized as one value system within the context that other societal




values would be reflected and adequately weighted in the other ranking




categories.  Other value systems were in fact accounted for.  The JV suggests




rewriting of Section 10.2.3, Value Systems, to reflect the above comments.
                                     10
                                  50

-------
                                  RESPONSE
Agreed.
Agreed.  This conclusion should be stated more clearly in the CSO Report.
The CSO Report does not suggest that value system employed by the Facilities
Planner was made in a vacuum.  In fact,  without knowing the results of the
cost benefit analysis, the chosen value  system was the most logical choice.
We simply wish to point out that other value systems  exist,  which could lead
to the selection of different alternatives.
                                    51

-------
     27.  PAGE 11-1, PARAGRAPH 2.   The DWSD, EPA and the EIS consultant




were all knowledgeable about the assumptions referred to as questionable,




and either accepted them or did not question them.   The statement "Facili-




ties planning...now appear questionable" should be  modified as follows:




"Results to date, coupled with changed project related circumstances,




require a change of assumptions before resumption of planning activities."
                                     11
                                  52

-------
                                  RESPONSE
Agreed.
Thank you for your comments.
                                    53

-------
Wayne Sidle University
College of Engineering
                                              Department of Chemical and
                                              rvtetallugical Engineering
                                              Detroit, Michigan 48202

                                                 July 29, 1982
             Mr.  James  Novak
             USEPA  Water  Section
             Environment  Impact  Section
             12th Floor
             230  South  Dearborn  St.
             Chicago, IL   60604

             Dear Mr. Novak:
                   As  a  practicing professional in the area of water resources,  I
             have  reviewed the  EPA Region V Final Report on Combined Sewer Overflow
             Facilities Planning for the  Detroit Water and Sewerage Department.   I
             attended the  public meeting  held on July 21,  1982 and commented on the
             report.  I wish to add the following written comments to the Responsive-
             ness  Report which  I understand will go to all recipients of the Final
             Report as  well as  all future requestors of that report.

                   The major purpose of the CSO report was  to facilitate the resump-
             tion  of  the CSO facilities planning in Detroit.  As it stands, the
             document does not  accomplish that objective as it omits references to
             all professional papers and  Wayne State University thesis and disser-
             tations  which are  in the public domain and which were intended to  docu-
             ment  specific portions of the work.  Not only were the references
             omitted, but  the work was apparently not reviewed and many statements
             made  in  the report are therefore misleading or incorrect.  An Auxilliary
             Bibliography  is attached to  correct this oversight of thousands of pages
             of detailed results, data and interpretation.

                   With  respect  to the recommendations, the oversights could signi-
             ficantly change a  number of  conclusions; a quantitative assessment of
             the impact is beyond the scope of this critique.  Recommendation 11.1
             is questionable as it is based upon ESEI's inability to find all the
             Rouge River initialization data that was used.  The MDNR 73 survey
             alone lists more data than that published in Table 5.5.  11.2 should
             be revised to indicate that  substantial additional quantities of data
             exist in the  present study.

                   The impact of the CSO's upon the Detroit River should be reviewed
             again, as  the ESEI study did not address the  entire river and new
             marinas  and canals with total body contact recreation will be added to
             the river.  The report should have addressed  the environmental impact
             of the existing and future no action conditions.  The Chemical Engi-
             neering  Department of Wayne  State University should be noted to have
             been  a major  subconsultant to the Joint Venture and a considerable
             resource of information.
                                            54

-------
                                  RESPONSE
We appreciate your bibliography which should be very helpful to present and
future planners.
The EIS Consultant made numerous requests for the initialization data to
Black & Veatch and to USA.  All of the information supplied by these two
sources was used.  If you possessed additional information, it would be of
great value to future planners.
Table 5.5 lists the arithmetic means of STORET data and not the individual
samples.  Therefore you are correct in saying that the MDNR 73 survey con-
tains more pieces of data than are displayed in Table 5.5.
The scope of study did not include the entire Detroit River or Lake Erie.
Future basin wide planning should certainly cover the impacts of alternatives
on a larger area than was analyzed for this study.
We agree that the Chemical Engineering Department of Wayne State  University
should be noted as a major subconsultant,  and we apologize for this  omission.
                                     55

-------
Mr. J. Novak
Page 2
July 29, 1982
     There are many additional technical issues raised by the report
which are definitively answered in the attached bibliography.  I would
be pleased to make copies of those papers available in their entirety
for the Responsiveness Summary, if desired.

                                   Sincerely,
                                   Ralph' H.
                                   Chairman
                               56

-------
                                  RESPONSE
Thank you for your comments.
                                     57

-------
                AUXILIARY BIBLIOGRAPHY FOR RIVER MODELING ON THE

                    DETROIT SECTION 201 FINAL FACILITIES PLAN
Alternate Facilities Interim Report, Giffels/Black and Veatch, Report on the
Detroit Section 201 Study, June 1981.

Anderson, H.M., "A Dynamic Simulation Model for Wastewater Renovation Systems,"
Doctor of Philosophy Dissertation, under R.H. Kummler and R.V. Edwards, Department
of Chemical Engineering, Wayne State University, Detroit, Michigan, 1981.

Anderson, H.M., "Combined Sewer Overflow Modeling:  STPSIM2, A Dynamic Model of
the Wastewater Treatment Plant," Symposium on Section 201 Planning; Modeling for
Combined Sewer Overflow Abatement, Paper 7d, 91st National AIChE Meeting, Detroit,
Michigan, August, 1981.

Anderson, J.A., C.D. Harlow and J. Baranec, "Combined Sewer Overflow Modeling in
Detroit 201 Study Using SWMM," Symposium on Section 201 Planning; Modeling for
Combined Sewer Overflow Abatement, Paper 7c, 91st National AIChE Meeting, Detroit,
Michigan, August, 1981.

Anderson, J.A., C.D. Harlow, J. Baranec and H.M. Anderson, "Combined Sewer
Overflow Modeling in the Detroit 201 Study using SWMM," Proceedings of the USEPA
(SWMM) Stormwater Management Model User's Meeting, January 19-20, 1981, Austin,
Texas.

Fl Sharkawy, Alaa, "Water Quality Modeling for One-Dimensional Rivers," Master's
Thesis under R.H. Kummler, Department of Chemical Engineering, Wayne State
University, Detroit, Michigan, 1981.

El Sharkawy, Alaa and Esmail Jamshidi, "A Comparison of an Analytical, One
Dimensional River Simulation with Numerical River Models," Symposium on Section
201 Planning; Modeling for Combined Sewer Overflow Abatement, Paper 8d, 91st
National AIChE Meeting, Detroit, Michigan, August, 1981.

Filardi, Raul and Barbara Harvey-Brayton, "CSO Control Alternatives Analysis,"
Symposium on Section 201 Planning; Modeling for Combined Sewer Overflow Abate-
ment, Paper 8f, 91st National AIChE Meeting, Detroit, Michigan, August, 1981.

Giffels/Black & Veatch, Segmented Facilities Plan prepared under Section 201
Facilities Planning Grant for the Detroit Water and Sewerage Department,
January 31, 1978.

Graham, Malaise, J., "Field Data Collection for Calibration of Models," Sym-
posium on Section 201 Planning; Modeling for Combined Sewer Overflow Abatement,
Paper 7b, 91st National AIChE Meeting, Detroit, Michigan, August 1981.

Harlow, C.D., E. Jamshidi, R.H. Kummler, J.G. Frith and J.A. Anderson, "One
Dimensional Water Quality Models for Dynamic, Small Rivers:  The Rouge River,"
Proceedings of the USEPA  (SWMM) Stormwater Management Model User's Meeting,
January 19-20, 1981, Austin, Texas.
                                       58

-------
Harlow, C.D. and J. Frith, "Numerical Water Quality Models for One Dimensional
Rivers," Symposium on Section 201 Planning; Modeling for Combined Sewer Overflow
Abatement, Paper 8a, 91st National £IChE Meeting, Detroit, Michigan, August 1981.

Harlow, C. and R. Kummler, Detroit Water and Sewerage Department Wastewater
Treatment Plant Flow Analysis for 1974-1979, Report to Black and Veatch,
February 1980.

Harvey-Brayton, Barbara L. and Raul E. Filardi, "Combined Sewer Overflow
Abatement Alternative Development," Symposium on Section 201 Planning; Modeling
for Combined Sewer Overflow Abatement, Paper 7a, 91st National AIChE Meeting,
Detroit, Michigan, August 1981.

International Joint Commission Great Lakes Water Quality Board, Surveillance
Subcommittee Reports Appendix B for 1975, 1976, 1977, 1978 and 1980, available
from the International Joint Commission, 100 Ouelette Street, Windsor, Ontario,
Canada.

Jamshidi, E., A. El Sharkawy, R.H. Kummler and C. Harlow, "An Analytical Model
for a Dynamic, One Dimensional River with Axial Dispersion and Chemical Reaction,"
2nd World Congress of Chemical Engineering, Montreal, October 1981.

Kummler, R.H., J.G, Frith and C-S.  Liang, Final Report on the Planning Level
Model Sensitivity Analysis, Task 1232.1, May 25, 1981.

Kummler, R.H., G. Roginski, C-S.  Liang, S. Winkler and J. A. Anderson, "Two
Dimensional Water Quality Models for Dynamic, Large Rivers:  The Detroit River,"
Proceedings of the USEPA  (SWMM) Stormwater Management Model User's Meeting,
January 19-20, 1981, Austin, Texas.

Kummler, R.H., J.G. Frith, L-S.  Liang and J.A. Anderson, "Uncertainty Analysis
in Stormwater and Water Quality Modelling," Proceedings of the SWMM Users Group
Meeting, USEPA and McMaster University, Hamilton, Ontario, Canada, September,
1981.

Lake Erie Report:  A Plan for Water Pollution Control, U.S. Department of the
Interior, Federal Water Pollution Control Administration, Great Lakes Region,
1968.

Liang, Chein-Sung, "Use of Multispectral Remote Sensing Data to Predict the
Turbulent Diffusion Coefficient in the Detroit River," Master's Thesis under
R.H. Kummler, Department of Chemical Engineering, Wayne State University,
Detroit, Michigan, 1981.

Liang, Chein-Sung, S. Winkler and R.H. Kummler, "A Guassian Plume Model of a
Two Dimensional River," Symposium on Section 201 Planning; Modeling for Combined
Sewer Overflow Abatement, Paper 8d, 91st National AIChE Meeting, Detroit,
Michigan, August 1981.

Michigan Water Resources Commission, Bureau of Water Management, Department of
Natural Resources, "Rouge River Basin:  General Water Quality Survey and Storm-
water Survey, June-September, 1973, March 1974.
                                        2

                                       59

-------
Roginski, Gregory T., "A Finite Difference Model of Pollutant Concentrations
in the Detroit River from Combined Sewer Overflows," Doctor of Philosophy Disser-
tation under R.H. Jummler, Department of Chemical Engineering, Wayne State
University, Detroit, Michigan, 1981.

Roginski, G. and R.H. Kummler, "A finite Difference Model of a Two Dimensional
River," Symposium on Section 201 Planning; Modeling for Combined Sewer Overflow
Abatement, Paper 8c, 91st National AIChE Meeting, Detroit, Michigan, August 1981.

Roginski, G., C-S.  Liang, S. Winkler and R.H. Kummler, "Simulation of Pollutant
Concentrations in the Detroit River," 2nd World Congress of Chemical Engineering,
Montreal, October 1981.

Upmeyer, D.W., G. Roginski and R.H. Kummler, "Impacts of Detroit's CSO Discharges
on the Detroit River," 54th Annual Water Pollution Control Federation Conference,
October 1981, Detroit.

Upmeyer, D.W., "The Alternative Analysis Procedure," Symposium on Section 201
Planning; Modeling for Combined Sewer Overflow Abatement, Paper 8e, 91st National
AIChE Meeting, Detroit, Michigan, August 1981.
                                       60

-------
PUBLIC MEETING TRANSCRIPT

-------
Edited Transcript  of Public  Meeting Held Wednesday, July 21, 1982 on the "Report
on Combined Sewer  Overflow Facilities Planning for the Detroit Water and Sewerage
Department"
Representing the DWSD   -   Mr.  John McGrail
Representing ESEI       -   Mr.  David Vance
                           Mr.  Peter Swinick
                           Mr.  James Williamson
Representing USEPA      -   Mr.  James Novak
Mr. Novak
Why  did we  do  this  report  on  CSO?    During the  facilities planning  one  of  the
elements being  covered  was  Combined Sewer Overflow (CSO).  That  planning (CSO)  was
suspended  rather abruptly.   While the planning  was  proceeding,  there  was  a  con-
current  Environmental  Impact  Statement  (EIS)  but since  the planning  on  Combined
Sewer  Overflow  was halted,  there was  technically no need for  the USEPA1 s  EIS  to
address Combined Sewer  Overflow.   At  that time, however,  the agency  did not have a
detailed overview  of  what was  done.  Therefore, this  report  was  generated  and  had
the following four  objectives.

           0  To  review  and summarize  the  Combined Sewer  Overflow planning
             that was accomplished to date.

           0  To  evaluate  quality  improvements associated with the alternatives
             that were  determined in  facilities planning.

           0  To  independently  evaluate the procedures used in facilities
             planning,  and

           0  Most importantly,  to provide some basis  from which  a resump-
             tion of CSO planning can proceed.

I should make something very clear, that this is  by  no  means any  kind  of  decision
rlocument.  It was put together  for the previously  mentioned reasons and  is  intended
primarily  to facilitate subsequent planning.

Mrv. SwinLck
We've handed out two things  already.   Two dozen CSO reports were  distributed first
     f.-Irst:  ser\ e  and we are  already  out of  those.   There were  about. 150 of  them
     d otr:  to  individalj who  requested tbein.   It, she eld have  been about 10  days

-------
ago and most people  should have gotten those already  although  I  just got word that
they  haven't  been received.   That  was  the  five  hundred page  report that  was  up
here  that has a  greenish cover  on  it.    We  still have  about  100 copies  of those
available if any  one would like a copy and does not have  one or  does not expect to
get  one  in the mail.  For  anybody who  did  write, you  should get  one  within the
next  2  days or 3 days if  they haven't  already been received.   If  anybody would
like  a  copy,  either Region  V USEPA  or  ESEI  can get you  one.    Everyone  of the
Citizens  Advisory Committee should have  gotten one.   But the place  to write to is
ESEI, you can  write  to my attention, Peter  Swinick,  1  Bank Street,  Rockaway, New
Jersey  07866.  We should be  able to get  it out in a few days.

The second  package  that  was  handed out  is really an  outline  of  today's presenta-
tion  and  since we are  trying to  limit  questions  until  after  the meeting,  if you
have  a question,  just jot it  down and this way we can remember and  call all those
questions together  later.  We are going to  try to present about 45  minutes worth
of information and  then open  it up  for questions. Try to make it  short  and sweet.
I'm going to start with the history of planning for upgrading  of  sewage  treatment.
I'm not going to  go  too far back,  only to 1966.  And then I'm going to turn it over
to Dave Vance  who's  going  to talk about  the work that  was done  by  the  facilities
planners  and the  review done  by ESEI and  the  USEPA.

In 1966 the State of Michigan and the City of Detroit  came to an agreement to limit
discharges  into the  Detroit  River.   At that time,  limits were set  for  those  dis-
charges and Detroit  during that  time tried to  meet those  limits.   Between 1966 and
1972  the  City met  those   limits  and  didn't  meet those  limits in an inconsistent
fashion.   In  the  early 1970's,  studies  came out  of  places like  the International
Joint Commission  and some  of the universities   around Lake  Erie  citing  the City's
publicly owned treatment  plant and many other sources  that were major pollutants of
the lake.  This,  combined with the entrance of  the federal government into regulat-
ing the waste water  discharges in 1972 with the passage  of the  Federal Water Pollu-
tion Control Act, required the City of Detroit, USEPA and the  State  of  Michigan to
put their heads together; forced the  meeting of the minds if you will;  to try and
solve the problems  that  were  occurring  in the City.   In 1974 MDNR, which  is the
Department  of Natural Resources, USEPA and the City agreed to an orderly progres-
sion  of  study  and  upgrading of  the treatment  plant.  They  started an upgrading
process, phosphorus  removal was initiated  or at  least the  construction  was initi-
ated and studies  were begun on the upgrading  of secondary treatment.   Also in 1974,
MDNR issued an interim  permit for the wastewater  treatment  plant  to  operate, again
setting up  some standards for discharge requirements.  In 1975,  a plan was presented
to MDNR and the agencies  on how to  meet  upgraded standards. The  plan was reviewed
by the agencies and  in  certain areas it was  deemed inadequate  to  document the need
of the federal funding.   In 1976,  two things  happened; first the interim permit was
revoked due to continued  violations of the standards  that were set  up and a mori-
torium was  declared  by MDNR on new  connections to the systems.   No  new  collectors
                                      64

-------
were  suppose to be built  and no more  home or  industries  were suppose  to  be con-
nected  to the  system.   The  moritorium was  later suspended  and dropped  when the
City, MDNR and  the  USEPA again agreed to a schedule to study and upgrade the treat-
ment plant and  try  to find solutions to the problems, very complex problems because
of  the  size  and  complexity of  the  treatment  facilities.   It  was  also  agreed  to
develop  a facility  plan which has come  to be  known as the  Segmented  Facility Plan
but at the time was called the Overview Plan with  an  Environmental  Assessment.  In
1976 it  was  agreed  by those parties  to complete a facility plan by August, 1977 and
that facilities plan  was suppose to study upgrading  to  secondary treatment levels.
DWSD also agreed  to meet secondary  treatment  standards  by December of  1979.   They
also agreed  to  study  the Combined Sewer Overflow problem which  was  thought to be a
major contributor of pollution  to Lake Erie and the  Detroit  River.  In  1976, the
Overview Plan with Environmental Assessment was started,  and it was  completed  in
June  of  1977,  on time  and on  schedule.   The  document  studied  the Combined Sewer
Overflow problem  and recommended the  construction  of a West  Arm Interceptor which
was designed to carry sanitary sewage and follow a route along the Rouge River.  It
was  designed to  separate  the  system  carrying pure  sanitary  sewage  down  to the
treatment  plant,  leaving  the  existing system  mostly unmodified  to  handle  storm
water runoff.  That  report  was  then reviewed by MDNR and the USEPA.   The review,
published in the  Environmental  Impact  Statement on the Overview Plan  and Environ-
mental Assessment,  determined that the data presented was  inadequate to justify the
expenditure  of  federal  dollars  on a West Arm Interceptor.   In other  words,  there
wasn't enough information  to make a decision  to spend that much money  to separate
the sewers and  stop or  eliminate to  a great extent the Combined Sewer  Overflows  on
the Rouge River.   Thus, although the  Overview Plan with the  Environmental Assess-
ment was  completed,  it  became  a  Segmented Facilities  Plan  because things were to  be
studied  further.  The Combined Sewer Overflow problems  on  the Rouge River  and the
Detroit  River were not  solved in 1976.   And that more  or less  brings us  to the
start of  this program as we  know it and  are  concluding here  today.  In  1977, the
need  for a  final  facilities  plan  or  for further study  on  a  couple   of  selected
elements  (one of  which  as  the Combined  Sewer  Overflow problem) was recognized and
was  initiated  into  a final  facilities  planning document.    That  kicked off  this
process.   I   will now turn the  meeting over  to Dave Vance who will  tell  us the
technical details of  what happened.
Mr. Vance
Peter gave  you an idea of  what the segmented  facilities  plan did. I'll  start  now
by recapping  the  Final Facilities Plan.   We'll  start  with the problem  definition
on the Final  Facilities Planning process.  The papers  you have in front  of  you go
along with  the  slides  and will help you. The  slides  will  help you write  down your
notes so you  don't forget when  you have  questions.  The goal  of this  portion  of  the
Final Facilities  Planning  effort  was   intended  to  see  if  CSO  in  the  immediate
Detroit area  was a serious problem.  If  so,  how much  of a problem  and, if  it was  a
                                      65

-------
problem,  what  alternatives could you  give  them to correct Combined  Sewer Overflow
problems  into  the  Rouge  River?  Other questions concerning the  treatment plant and
other things were  not  covered  in this  particular facilities planning effort that we
wrote a report on  here today,  such  as  incinerator  improvement, upgrading the treat-
ment plant  for solid handling or site selection for  solids disposal.   Those items
and others  were  covered  in separate reports.  Before we begin in  our evaluation of
that planning process  and  our  recommendations, I want to spend  a  few minutes going
over the  Detroit system  and the  methodology the facilities planners  used in order
to better evaluate our recommendations and  evaluations.  The  Detroit system is com-
posed of  about 3500  miles  of combined sewer and,  as  Peter  said, it  means that one
sewer handles  most of  the  storm water runoff,  domestic  and industrial  waste.   The
next slide  shows the nature of  the combined sewer system  showing both  the runoff
rain and  the  family  sewage going into the  same  pipe.  The  next slide  shows a com-
plete combined sewer system, including a river.  Notice that  again  the runoff goes
into the  same pipe  as  the industrial  and   domestic  waste  and  comes down  here  by
various size  sewers into  an  interceptor which  parallels  the river.   There  is  an
outfall here,  a place  where  overflows  go  into the  river without   being treated.
These combined sewers were originally  constructed  to  prevent  basement  flooding,
street and  parking lot flooding.   However,   in the past  twenty years  they've become
far less  popular because of the water pollution associated  with such  a system.  An
interceptor,  shown in  this slide,  is  a  major sewer  who's  purpose is  to intercept
the flow  of tributary areas  before they transport  it  on  to the treatment plant.
The next  slide should show the  major  interceptors in the Detroit area.   The Oak-
wood Northwest Interceptor parallels  the  Rouge River.    It  runs this  way.   The
Detroit River  Interceptor  is the other  very large one,  which  follows  the Detroit
River and goes  up  this way.  The North  Interceptor,  West  Arm being  referred to in
discussions, would approximately parallel this Oakwood Northwest  Interceptor along
the Rouge River  and  East Arm  Interceptor,  now unconnected generally parallels the
Detroit River Interceptor.    Those are  the four  major interceptors you'll  hear
people talk about.  The  West Arm does  not exist and the East  Arm  is  about 90% com-
plete.   The treatment plant  is  located near the mouth of  the Rouge  River right
where all  these interceptors  come together.   The treatment plant  is one  of  the
largest in  the  country handling more than 800 million gallons of waste  per day so
it's very large.   These  slides  should  give  you an idea of the facility.   For those
of you who  haven't seen  it up close,  these  slides  just  give  you an  idea  of what a
treatment plant  looks  like.    We're  not  going  into detailed  processes  tonight.
That's not  our purpose.

The wastewater which doesn't make it  to  the treatment plant  is  overflowed into the
Rouge River and Detroit Rivers.    That  happens along the  Detroit Interceptor  and
Oakwood Northwest  Interceptor.   This slide  shows,  and your  packet  will show it more
clearly,  the  49  locations  of  the CSO  sites in  the  immediate Detroit  area, within
the City  of Detroit and along  the  Detroit  River.  The  next  slide shows the loca-
tions of  the Rouge River Combined Sewer Overflow  sites.   Again, these  are not all
                                       66

-------
 the  sites on  the Rouge  River, just  the ones  within the  immediate Detroit  area.
 There  are 30  of those along the Rouge River.  There are also two more  outfalls from
 the  plants itself. Combined Sewer Outfalls  vary in size.   Some  are quite  large  as
 indicated by this slide  and the next  slide.   Those  are  very  large, about  10  feet
 square or more; or they may be small as  indicated here.   They  come  in  all  different
 sizes.   Now, needless  to say, the  impact of such  a large overflow may have  very
 harmful effects on water quality and on  any recreation.   To give you a feel for the
 impact it may have,  we'll  show you the  width of the Rouge River  at a  location  of-
 where  one of  those very large interceptors is.   Now  the  river  at this point may  be
 15 to  20 feet wide and about  18  inches  deep, and you saw the  size of the  outfall.
 Combined sewage coming out from the outfall  can totally  dominate the  river at that
 point.  There's  no contest.   For other CSO's  that are  smaller  or where the  river  is
 bigger, the  effect would not be so great.  It's just  interesting to know how  small
 the  river is  at places where  there  are very, very large  outfalls.   It's  important
 to realize here and  as  you read the  document that the study  we are  talking  about
 tonight focused on the  impact of CSO  on only  a portion  of the Detroit River  and
 Rouge  River.   For instance, the  entire Rouge River basin  is shown by the  outline.
 Now  you can see how  big the basin is, being  of  course the area where  all the  water
 flows  into the  Rouge River.   Keep  in mind how  large  that area  is, how far out  it
 goes.   Of this  basin, the Detroit Water  and Sewage District's  service  area  includes
 maybe  one third  of  that area.   Of course,  the Rouge River  basin  is  a very  much
 wider  area. Most of  this  area is served  by combined  sewers. Those  are the  colored-
 in areas here.   Now  for  purposes of  this study,  the planning  area for which  the
 plans  were developed  was  defined as the  immediate  Detroit area shown by the color.
 So out of all that we started with,  out  of the basin  down to the total DWSD service
 area,  we now have  a planning area defined as  just this area.  For planning  purposes
 this area was  further divided into two  watersheds,  the  Rouge River watershed  and
 the  Detroit  River  watershed.    Those were  further subdivided  into subwatersheds.
 Those  were even further  divided.   All this was done with a detailed analysis of  the
 rainfall,  the  runoff  and the  sewer system characteristics.  It  covered such  a  big
 area that the  only  way  to  handle  the problem   is to start breaking  into  smaller
 components.  It gives you just a flavor as to how that process went.

 The  facilities  planners  then  developed  alternatives  to  reduce the volume  of  Com-
 bined  Sewer Overflow. Five control options or methods of  controlling that  Combined
 Sewer  Overflow  were  examined to  reduce  pollution.    These  were:   inline   storage,
 which  is  utilizing the inherent  storage  capacity of  very large  interceptors;  off-
 line storage, which usually means  the  construction of storage tanks below ground  to
 hold the wastewater   until  the treatment  plant  can handle  it;  increased treatment
 Cjapji£ity_ either  at   the  treatment plant or  by  building  remote   treatment  units
wherever  you needed  them; sewer separation,  which was discussed earlier;  and best
manajgemjent_jgrac_tices  such as  street  sweeping, sewer flushing or some of the others.
                                       67

-------
These five control options were  used to develop specific control alternatives.  The
five control options were  examined over four levels  of  pollution  control (i.e. 20,
40, 60 and 75%) and  two  location systems (i.e. 1 facility/basin or  1  facility/2 or
more basins),  to  produce 25  specific  control  alternatives.   So  facility planners
looked at various levels of control  from very little to as much as  possible.   They
looked  at  locating  facilities in  different areas.  They looked  at  the different
control options, and tried out a combination of those to see what turned out  to be
a superior specific  control alternative.  There were some duplications so we end up
with about 25.  There are two  special cases that did not come directly  out of that
process that are important.   The Future No Action  case  that  you'll  see  abbreviated
FNA, Future No  Action,  which  assumed  that  all  the improvements already  under con-
struction were  finished.   And Existing Conditions,  which  you  may  see  abbreviated
EC, which represented the facilities as they existed in 1979.  The Future No Action
alternative was far  more important because  all the alternatives had to  be compared
to something. That base is the Future No Action.  Now there  is  a  slight difference
between what we've used as that  Future No Action and what will  come  to be in a year
or two.  But  when  you look at the  actual data, it doesn't end  up making much dif-
ference.  So,  the  Future No  Action alternative  can be used as a  base  to compare
other alternatives to.

Once the specific  control  alternatives  had been developed,  they were evaluated in
five different  categories.   First was  the cost benefit  category,  second  was the
environmental  analysis, third the  implementability,  fourth technical  and  fifth
economic.  There had to be some  way to evaluate alternatives so it  was  broken down
into these  five categories and  these  five categories were  weighted by  a complex
process.  You can see by the  chart the categories  have just about  equal importance.
Before the  cost benefit analysis  or  the environmental  analysis can  be  performed,
the actual  impact  of the alternatives on  the  water  quality  had to be  determined.
The only way to do that is to  model  water quality  changes.   After  you know what the
water quality  is  (the place  where you begin  to model) you  have  to  know  what the
flow is  up  there.    You need  to know  the  quality and  quantities   of the  Combined
Sewer Overflows coming into  it.   As well  as  any  other discharges  coming  into it.
You  need various  streamflow  characteristics.   So  for  purposes  of this  study,
facility planners had four headwater locations  here near Inkster,  near Garden City,
up here near Farmington and right  over the  line here in Southfield.  Each of  these
points here are where the model  had to start off.  So those  are our four headwater
locations.  I'll come back to  that later.

The water quality model was used to predict concentrations of different parameters.
Some of the parameters in one  model are represented  here.  Each parameter or  vari-
able is used to gauge impact  of  pollution  on a certain  beneficial use.   That  bene-
ficial  use  may be  wildlife  protection, it  may  be  recreation, or  drinking  water
supply;  and  there  are  a  number of  others.  All  of these parameters are  used to
determine  suitability  of  the  water  quality  for  the  designated  beneficial  use.
                                       68

-------
Dissolved  oxygen is used to  measure  the beneficial use  of  propagation and  mainte-
nance  of fish.   Fecal  coliform is a measure  of  the potential for recreation.  After
each  alternative has  been  modeled, the data  (concentrations)  were  then used  for
cost/benefit  analysis  and environmental  analysis.   Cost/benefit analysis is  a tool
which  is used to measure efficiency of  the alternative.   It measures how much more
benefit that  last dollar bill will achieve. For instance, here we have three  cases,
each  with  an equal cost.   Here  this  same  amount of  cost going  from  this  point
brings this much benefit.   Up here, this same amount of cost from this point  brings
this  much  benefit; a  smaller amount  than  down here.   Up  here,  the difference  is
quite  clear,  the same amount  of  cost  brings  a smaller amount of  benefit.  For  any
project, there  comes  a certain point where you  can spend more  and get less  benefit
than  the  last increment  of  expenditure.   The  facility planner  defined  benefit  as
the  improvement  over  the Future  No Action  case  divided  by the  maximum possible
improvement.   Now  this  definition is  right  below.   What  this  basically means  is
that  benefit  is measured  with percent improvement  toward the  maximum possible;
towards the best you  can do  in that part of the  river.   That will be determined  by
looking at the  results of the alternative and using those that did the best  as max-
imum.  Since the  facility planners chose  a  control  level  range  to encompass  all  the
total  control of CSO, you  can  identify the best  one by  looking and use  that  to
determine  the maximum improvement.    The difference  between the Future  No Action
alternative and the best alternative  is the maximum  possible  you  can  improve  the
water  quality.

The environmental analysis has the same importance as the cost/benefit analysis.  In
the environmental analysis  the impact of each alternative  was  examined in 6 areas.
Each of these six areas  had  many,  many sub-categories. It became quite detailed  and
complex.   You can  see by this chart  here  that  the water environment was rated  as
most  important  followed by biological.   The  alternatives  were  also evaluated  for
technical considerations and economic; considerations.   Most of  our  time was  spent
on the two  that  are most  important;  the cost/benefit and  environmental analyses.

After  alternatives  were  ranked in  each of  these  five  categories,  rankings were
combined to produce the few best  alternatives.   Eight few  best  of  the  original  25
were produced.   Of  these eight few best, the top  three  were Alternative  #10,  which
maximized potential inline  storage through using  inflatable dams making better  use
of the space  in  those  very large  interceptors.   That came out to look like it  might
be the most preferred.   Next  was  Alternative  #9  which was increasing treatment cap-
acity at the  plant  itself via  small  amounts.   Third was Alternative #2 using poten-
tial inline storage but  not to the extent that  alternative #10  did.  The Report goes
into great detail on these three  alternatives  as well  as the other alternatives for
anyone who is interested in pursuing the details.
                                      69

-------
It was originally  intended  to  subject these few best alternatives, these top eight,
to  a  more  detailed  evaluation.   This  detailed evaluation  would  have  included
detailed modeling, detailed costing or cost/benefit  analysis,  and detailed environ-
mental analysis.   So view  this  as a  result  of the  first  cut,  not the  final  word
just the first  cut.   It was intended to provide further analysis to select the best
alternative  instead  of  just the  few best.  However, about  this  time  the facilities
plan was halted.  And now we will  turn for a moment  to Jim and  John  to  explain why
facilities planning  was halted.

Mr. Novak
There was  an ongoing consent  judgement that had date  requirements in it.   It was
obvious that  some  of the  dates could  not  be  met.  That meant  that an amended con-
sent judgement  had to be  developed.   At  the  same time, there were  fiscal problems
in  the  State and  the DNR.    The  DNR,  Michigan Department of  Natural  Resources,
expressed  a  desire  to reduce the amount  of dollars  being expended on planning for
Detroit  at  this  time.   The  preliminary  information  (from  facilities  planning)
showed that  there  is  a minimal improvement in water  quality in both Detroit and the
Rouge River; that was the initial  indication.   As far  as  the agency perspective, we
were undergoing a change in administration and a change in  our administrator. There
was an uncertainty of funds.   All  these factors contributed to  the findings of the
July 6, 1981 Federal  Court  Order to suspend CSO facilities  planning.

Mr. McGrail
As you  might imagine,  Detroit sees  it  a bit  differently.   The  facility planning
work began way  back  in  1975 or 1976 and produced  the segmented facility  plan in
early winter 1978.   January 1978  was when it  was published.   Now the  way Detroit
has historically  considered the  two  facility plans,  the  segmented  and  then  the
final  facility  plans,  is   one  building  upon the other.    That  is  the  segmented
facilities plan looked to a large  extent at the entire needs  of  the  department but
ended up considering mostly the  dry  weather  needs;  the sludge handling  related to
dry weather needs,  etc.    In  fact it  has become  the cornerstone  of   our  modern
wastewater capital improvements program.   Many of the  projects that appear today in
Step 3  (in the  construction phases)  can be traced  quite readily back to  the  seg-
mented facilities  plan.   The  second phase of  facility planning came, as  Pete in-
dicated, when EPA  felt that there wasn't  sufficient  analysis to  warrant plunging
forward on the West Arm, on CSO control and on other  facets of  the wastewater pro-
gram.   So  consequently  we  embarked  on the final facilities planning  program.  Now,
originally, back in  August  1980  there was a grant application prepared  which would
have finished the facility  planning program.   The total cost of  facilities planning
work would have been in excess  of  $22  million; just  the  planning.   Now consider
that for  $28 million we're building  two 300  foot diameter clarifiers  and  with
                                   70

-------
 justification MDNR said,  for that kind of money we could build concrete rather  than
 paper.   It  was a convincing and compelling argument in so far as DNR was concerned.
 The  Director  was a little less tenuous about that, but there was feeling within the
 Department  that perhaps we have planned enough.  As Jim pointed out, by February of
 1981  we were beginning  to  get  preliminary  modeling  outputs  that  suggested  that
 water  quality improvement on both rivers; the  Rouge  and  Detroit;  was not that  sig-
 nificant.   Indeed, even  given  the highest  level of CSO control we still would  not
 have  brought  the rivers  into  compliance  with  dry  weather  standards.    In other
 words,  to bring them into compliance, we would  have  had  to  change the law to allow
 for  wet weather standards.  Then perhaps we would have complied.  Because the water
 quality conditions  would not  significantly  improve the  dry weather  standard,  we
 could  not encourage  the development of full body  contact  recreation.   And if some-
 one  in the  audience  could explain to me what  partial  body  contact  recreation  is,
 I'd  be  glad to know.   It  seems to me that either you're all wet or you're not.   The
 fact  of the  matter  is and  I must  admit it came out in  many of  the interagency
 meetings, that there was  a certain weariness on the part of the department in terms
 of  further  facility  planning.    In  fact  that  weariness  not  only  ended  in   the
 termination of final  facilities  planning but  it  also  ended up in the elimination
 of a lot of  other Step  1  work as many  of those  in  the audience can testify  to.
 Also,  a lot of termination of  Step  2  work as  a matter of fact.   It  seemed  to  get
 easy after  a  while.   You  dump one facility planning program and you  can dump 2  and
 3 others and  it gets  fun. You  find  youself accomplishing something.   Now  I'd  like
 to return the presentation to Dave Vance.

 Mr. Vance
 Now  we've  given you  an  idea of what  went  into facilities planning  and  why  it  was
 halted.   For   our  evaluation tonight  we  are  going to  confine  our comments  to  two
 very important areas, water  quality  modeling  and the  cost/benefit  analysis.    The
 water  quality results, as John mentioned, are  very interesting  and begin to answer
 one of  the  original  questions of the study.  We want to  know,  "why the CSO's are a
 problem particularly  in  the  Rouge River?   What  is  the  CSO contribution  to water
 quality problems?  and What can be done about it?"  Now the  water  quality  modeling
 results  give  us some  ideas,  give us  some  direction on  how to answer  those ques-
 tions.   The water  quality modeling results  indicate that  water quality is a problem
 in the  Rouge River.   Dissolved  oxygen,  fecal  coliform and  phosphorus  all   show
 significant hours of  violation of the  state's  standards.   Now  when you  look  at
 this,  this  column has the  standards  set by  the state.   Here  we  have  the average
 concentration and over here  the  hours of  violation.   Now  look at those  hours  of
 violation.  The Rouge River was  modeled  for 6600  hours;  9  months, 24 hours  a  day.
That comes  to a total  of 6600, the most hours you could have.   You  can  see  that
phosphorus  is  very  nearly  a  unanimous  winner.    6584   violates  almost  all  the
possible hours  and you can  see  this  here.
                                   71

-------
Unfortunately,  as John  said  the  alternatives provide only modest improvement in the
water  quality.  Notice  here  the  unresponsiveness of both  the  hours  of violation in
fecal  coliform  and  dissolved oxygen to the reduction in CSO volume.  Now, the alter-
natives can physically  reduce the  amount of CSO that goes  into  the  river,  and this
gives  you  an  idea  of how much.  Remember  our base  is  the Future No  Action here in
this column.  That's what we have  if we don't do anything.  So  you  can see, as the
alternatives  go this way,  the  control gets  a  little  better.   Until  here you've
reduced  the  CSO volume quite substantially  compared  to what  it was  in  the FNA
alternative.  These  lines which  indicate the hours  of  violation, don't drop accord-
ingly.  Alternative 19  shows the most  improvement.  It reduced the  CSO by 80% but
only reduces  the hours  of violation  by 17%  for  dissolved oxygen and 56%  for  fecal
coliform.  This still  leaves 1809 hours of  violation  for fecal coliform.   This is
what the best alternative can do.   Alternative 19 has  a capital cost of 578 million
dollars, that's half a  billion  dollars,  so its a  very  expensive alternative and
disappointing in performance.   There are  less expensive  alternatives which result
in  lower  benefits  as  you  might  imagine.    Alternative  10  is  a   very  efficient
alternative and was listed  by facility planners as perhaps the most desirable at
this tentative  first cut  stage.   Alternative 10  reduces combined  sewer  overflow
volume by  24%,  reduces  the  DO  violations  by 11%  and  reduces  the   hours  of  fecal
coliform violations  by  8%.   This costs only $8.2 million.  So  for $8 million, you
can get  a  more  efficient alternative but unfortunately  it  still doesn't  do much.
We're  only talking  about 10% improvement  for 8  million dollars  still leaving many
hours  of violation  of fecal  coliform and dissolved oxygen.  Now at  this point, you
should be wondering why  even the best alternative,  Alternative 19 at half a billion
dollars, doesn't substantially  improve the  water  quality.   If  you  can  spend $578
million why  don't  you  get  more  for it.  Well,  the answer appears  to lie  in the
background water quality, the incoming water quality.   Even if  DWSD  were  to elimi-
nate all  its  overflows  on   the  Rouge  River,  the  fecal  coliform counts might not
improve  enough  to  substantially reduce  hours of  violation.    During  wet weather
there  are  numerous other   overflows  on  the  lower,  middle  and  upper  branches,
contributing  to the main Rouge  and  the upper Rouge itself. Other  communities have
combined sewer  overflow. Thus during wet  weather you  might expect  that  the water
quality wouldn't  be that  good.    Communities  of  Dearborn,  Inkster,  Garden City,
Farmington  and  Southfield   all  contribute  combined sewer  overflow  to the  Rouge
River.

The alternatives performed better  for  the Detroit  River  than the Rouge River. You
can see that  with  the  CSO volume up here  there  is  great  variability in the amount
of CSO.  Some alternatives  do control  quite a bit of  it  and you do get  some real
reductions  compared to the Future No  Action  in fecal  coliform  concentrations
brought about by the alternatives.   Alternative  12  achieves the highest water  qual-
ity in the Detroit  River  by reducing  overflow 76%.   The  hours  of  violation for
fecal  coliform  are  reduced by 54%  by this alternative. Quality  doesn't change very
much.  Alternative  12 for  the Detroit  River  has a capital  cost of  $229  million.
                                      72

-------
Having  presented a  summary of these  water quality modeling results,  we  will  now
turn  our attention  for  the last  few  minutes to  the  components of  the model  that
produced these  results.   The combined  sewer  overflow  study addressed many  detailed
questions  and provided  many insights  into the problems  produced  by DWSD  and  the
USEPA.   We're not  going to go  into all  those  questions  tonight;  they're  far  too
complex  and would  take  a long  time.  What we are going to  do tonight is  take  one of
those we feel would be  especially important.  And that's the issue of initialization
data, (data used to describe incoming water quality).   It  is important  not  just  be-
cause its  an  academic  study but because those of  you  who are concerned  about  water
quality  in this area  should  keep it  in  mind when  facility planning  is  resumed.

In the Rouge River  there are four headwaters location, again at the end  of  the  blue
model portion. Now  facilities  planners used monthly average, dry weather concentra-
tion  for each parameter  and each  of  those headwaters  to start the  model.   Given
enough  other  information  you  can  generally  tell  what  the water quality  is  along
here.  But at each  starting point you've  got to tell  the model  what to  start  with.
The model  was set  up so  that it needed a concentration for each month.  They  didn't
want  one for  each  day, that would have been  far too  difficult.  And  a year  wasn't
really  enough.   So  we  started with one concentration per month for  each  of  those
parameters at each  of  those points.  So for dissolved oxygen for the month  of  April
you need a concentration here,  here, and here and so on.  Now since the model  is to
run for  9 months and  there are four  headwaters  to model,  you  need a  total  of  36
average  concentrations  to start  up  the  model for  each  of the parameters;  nine
months times the 4  headwaters.  Now ideally,  of course, there would be data;  actual
sample data which you  could use to get these  initializing  concentrations.   However,
that might not be expected to  exist in reality and it didn't.  Often times  in water
quality  modeling, the modelers  are forced to  rely on some  of their own  judgement to
fill in  points that  just don't  exist in sample data.   Unfortunately in this case of
the 36  average  concentrations  required,  for  dissolved  oxygen,  fecal  coliform,  and
phosphorus,  the existing data  gathered  by  others in  the  past  and  stored  in a
retrieval  system supplied  concentrations  for only 5  of  the 36 necessary  points.
Which is 5 out  of  36.    The other 31 had  to  be supplied  with  the  best  engineering
judgement.  In  the  case  of other  water  quality parameters,  it was even  less  en-
couraging  because  there  was only  1 sample, and  that  wasn't even an  average.   That
was just one sample, of  the 36  that were  necessary.  So although some estimates  are
always  necessary and are  expected in  water  modeling,  it  was  unfortunate  in  this
case that  there  was  not  more data  available with which to initialize the model.  Now
fortunately for  the  most  important parameter,  dissolved oxygen, facilities planners
undertook  a very extensive sampling campaign to get good data  of  dissolved oxygen.
They spent 31 days  at  various  locations and  collected quite a bit  of  data  on  dis-
solved oxygen.   So  for dissolved  oxygen there is a high  degree  of  certainty  in  the
accuracy of the  initialized input  data.   For the  other  parameters, unfortunately,
there weren't very many  dry  weather samples to  be  used to start up the model.  Now,
it needs to  be   understood at  this  point  that the modeling was developed  at.  this
                                     73

-------
stage  to rank  alternatives relative  to one  another,  not  to  predict  absolute or
actual  water quality.  To  decide how much  better  or worse Alternative  5  might be
than  Alternative  1,  is  an  example.    For  that purpose,  extensive  use   of  best
engineering  judgement is all  right because  once the model  is calibrated  and the
methodology  is  down correctly,  it won't make  much  difference what values you start
with, the rankings can  still  come out the same.  Alternative  19 will be better than
Alternative  11,  no matter what  you started with.  The difficulty comes in trying to
use the  data  to  describe the  actual water quality.   For that purpose, the extent of
these engineering  judgements  prohibits  us  from placing much confidence  in the re-
sults of the water quality model.   It's important  to  keep in mind  the different
purpose  the  model was developed for.   Remember also that it was originally  intended
in the  next  stage, the  detailed stage, to do more detailed analysis, and perhaps at
the end  of that  be able to  predict absolute water quality. At the stage the process
was stopped,  the information  was not sufficient except dissolved oxygen, to predict
with high confidence  the input  data to initialize the model.

The other area  of  comment  tonight is  the cost/benefit  analysis.   Although  the def-
inition  of  benefit is  quite  reasonable,  the  alternatives  did not  produce suffi-
ciently  different  water quality results to  permit  meaningful  calculations   of bene-
fit.   As it  turned  out, this  definition  did not  allow  a very  good idea of the
alternative.  Look at how  the  numerator  and the denominator are  calculated in the
definition of benefit.  The denominator is  the difference  between the concentration
in the  Future No  Action  and  the  concentration  of  the best   alternative  and that
makes up the  maximum  possible  improvement of the river in terms of quality.

Now we'll  look  at these differences in that  slide,  also  included  in  your packet.
Looking  at  these  differences,  we  can  see  that only  for  fecal  coliform  is  this
difference greater  than 10%.    Here's  the concentration  for the  Future  No Action,
and here's the  best  alternative.   Subtracting those two  gives  you  the difference.
Now how  great is that difference  compared  to Future No Action. In  most  cases, the
difference turned  out to  be  very  small.  Now  the  small  difference  is not only a
problem  itself,  because  it's  so small you're  not quite sure how  much  faith to put
in it, but it masks the meaning of benefit  value itself.  Consider a case where the
denominator  is 4%.  If  the  particular  alternative offered an improvement of 2%, and
the next slide  will  show this, the benefit  would  be calculated  as  50%.   So let's
say the  denominator was 4%, the numerator was 2%, the benefit  turns out  to be 50%.
Now as you're reading the report if you just  opened  to  this page  you might think a
50% improvement  is quite sensational.   That's quite good unless you realize that it
was based on  just a 2% difference.   Such a  small difference may not even be statis-
tically  different.    Now again, for  simply  ranking  alternatives  this  system will
work.
                                       74

-------
The  other important point  that needs to  be  considered about  evaluating the  cost/
benefit  analysis is that  of  choosing which project  or which  level  of spending  is
the  most  desirable.  We mention this tonight because  this is a tactic that's  going
to concern  all of us,  not  only in  this  project, but  in the  future when  government
or any one  else  wants  to spend money.  The question though is, "How far should they
go?"  When  the project is  driving,  you're basically in favor of how much  should you
spend.  Should you  buy a Cadillac or an electric powered  car.   Just how  far should
you  go?   In cost/benefit  analysis, you  move  up this  curve  you  get  less and  less
benefit  for each additional  dollar you invest.  That's  the way  most things  work.
The  question  to  be  answered  then  is where along  the curve  do  you  want to  stop.
Traditionally  in economics,  resources  have been  assumed  to be  unlimited,  and  if
that's the  case  and if both  benefit  and cost  are  in  the  same  terms  (dollars)  then
you  usually  want to  stop spending money at a point  some where  about right in  here.
Up to  that  point, you were getting more than  $1 benefit  for  each additional  $1  it
cost.  Maybe you spent $1  and you go an additional $3 in  benefits.  You  were  doing
real well.   Then some  point,  in here,  you spend the  next $1  and you get $1  back.
Beyond that  you  spend  $1 but  you get  less than $1  in benefit  back.  So the  logical
place to  stop  is where that additional  benefit equals the additional  cost.  That  is
a traditional  stopping point.

However,  when  there  are scarce  resources  as we face  today,  the  question we should
all  ask ourselves in the  future is  "might it  be better, if we  still have  the scarce
resources,  to  choose a point  some place  down  here  where we clearly get more than  $ 1
worth of  benefits for  the  dollar it costs?"  Now you  don't want  to take  that  to  an
extreme  because  if  the  curve  looks  like  this,  you'll never  get off  the ground.
You'll stay  right down here  at  the  origin. But some place in  between here and the
origin is a place  future   facility  planners  might want  to  consider  targeting for
their  level  of  spending  for   the project, not  carrying  all the  way  to  the  point-
where you only get $1  worth of benefits  for the last dollar it costs, but, stopping
at some point  where  you  get $2 or $3 of  benefits for  the  last  $1  it  costs.  As you
might  expect  the method of  trying to  maximize additional  benefits  for  the   last
dollar you  spend and  the method   used  by  facility  planners produces   different
results.   You're going to select different alternatives based just on cost/benefit
analysis.   So  it's not  just  an academic  point, it  will  produce  different results
for you.

That concludes our most  important  comments like  I  say,  in  your  documents  you'll
find these  more  fully  explained, we simplified a  great  deal  tonight.  You'll   find
these subjects fully explained as well as  many other  topics  which we did not  have
time to touch  on  tonicrht.
                                      75

-------
Mr. Swinick
The  final  chapter in  any study,  of  course, is  recommendations  and that's  what  I
want  to cover  briefly.   It's  Chapter 11  in the  volume.  It's  four pages  long.
Before  I  get into specific  recommendations, let me set  the  background.  This  is  a
USEPA document  and USEPA  works  within a specific system.  It  was  given a situation
where  facilities  had been  suspended.   It  was given  a  situation where  there  were
basically no recommendations from the grantee, the City  of Detroit  to  the  USEPA on
what to do about  the  combined sewer overflow.  The City  provided  an interim report
which  was  supposed to  identify the  few best alternatives.   It  didn't  choose  any
alternative  for funding.  As such and because of its  role, the USEPA had basically
no  request   to  act upon.    So  this  document doesn't  recommend  a   combined  sewer
overflow action alternative.  The document  as stated by  David and Jim Novak before,
is the  USEPA's  attempt to briefly  review and summarize  the efforts  that have  been
made  to date.    The  report  also  raises some  questions and  suggests areas  where
further information may assist  greatly in  the future evaluations.

There are four  major  areas on Chapter 11. The first  is alternatives  for evaluation.
Because of many uncertainties,  the evaluation of alternatives in  the future should
not be  limited to  the few  best  that  were chosen  in the Alternatives  Facilities
Interim Report  as it is  known.   Those  uncertainties  include  the use  of  the North
Interceptor  East  Arm, the size  of pump station #2 which is  the  pump  station  that
would connect the North Interceptor East Arm to  the  existing  treatment plant. (It's
not as yet known what size that  would be or what would be done with that intercep-
tor. )  Also, uncertain  is the participation by communities within the  DWSD system.
That's  quite a  hot issue right  now and that  will  affect alternatives in  terms of
their size and  flexibility of the DWSD system to handle   flow  in the future.   Thus,
when all of  that  is  settled and when  facilities  planning is  resumed,  it is recom-
mended that  the development  of  alternatives take those  new situations  into consid-
eration.

The second area is in the area  of modeling  considerations.  As Dave  just  explained,
there is some unresponsiveness  in the alternatives.   The report  concludes that this
should be analyzed to determine  how to structure the  future analysis to  avoid this
problem.

In the area of benefit  analysis,  it is recommended that  rather than using  a single
point on the curve  to choose the  optimum alternative, (be  that  the  area where  one
more dollar  of  expenditure  gets  you  one more dollar  worth of benefit or  the  area
where the technician would say  that the change in benefit compared to the change in
cost is  maximized), that  somewhere between  those  two points on  the  curve  is  the
area where one  would consider  potentially   funding  an alternative  that  would  deal
with Combined Sewer Overflow problems.
                                     76

-------
 The  fourth  area is systems control and this is the  area  where  there is quite a bit
 of  discussion.    There  are  four major  areas under  systems  control:   operating
 philosophy;  computer systems;  instrumentation survey;  and a  preventative mainte-
 nance  program  which are  discussed  in  the  recommendations  section.    Given  the
 circumstances  where we  have  basically  a hold on  combined  sewer overflow planning,
 the  system  control center presently  provides  the best opportunity  to maximize the
 ability  of  the treatment plant,  interceptors  and collection  system,  to reduce
 combined  sewer overflow pollution.  The existing  system  should be  utilized to its
 maximum  capacity.   The   system  holds  opportunities  to  do that.    To  start,  an
 explanation  and a further evaluation  of  the  operating philosophy of  the entire
 system should  be presented.   Also,  verification   of the  potential  storage  volumes,
 that  have been  reported,  within the  system  would  be helpful.    In terms  of  the
 computer  system itself,  it  has  been  reported that  the  computer  system currently
 doesn't reliably perform  its  function  all  the time, and  that  major components such
 as the central  processing  unit, memory and disc  drive are  also unreliable.   It has
 been  recommended that they be reevaluated and if they  are unreliable,  then those
 findings  should be presented  to the  agencies.   In addition, it has been stated that
 the  software program which has been built  into  the  system, that  takes in  informa-
 mation from the  various sensors,  was developed some time ago,  and  that it has been
 modified  maybe on  an  annual   basis,  and that an  overhaul  of  that  entire  software
 program might  result  in  considerable benefit to  the system.   Documentation of this
 situation should be presented.   An  instrumentation  survey might  be required since
 it has also been reported, although  we don't have significant data to back  up these
 details,  that  the  sensors in the field might not be  operating properly.  There is
 not thorough documentation regarding the status  of  level  sensors  in the intercept-
 ors and proximity  sensors. It is, therefore,  recommended that a thorough survey of
 that equipment  be  done  to determine: what  the  remaining sensor life  might  be;  how
 sensors might  be protected from  damage  (what procedures might be  necessary),  and
 whether to  replace or  upgrade  those  devices  to  help maximize  the  system's ability
 to store  combined  sewage  and minimize  overflow.   The  final  recommendation  was  a
 preventative maintenance  program  consisting of  all the  elements  that I  just des-
 cribed.  These  together would be  designed to minimize  the reported quick erosion of
 the sensor reliability and provide a method whereby the  City  can  minimize  combined
 sewer overflow  problems  by efficiently using  the facilities  that  it  has  in place
 with a minimal  amount of capital  expenditure.

 Those then, are  the recommendations  of  this CSO report.

 Mr. Novak
 And  keep  in mind  these  are  recommendations.   Since  facilities planning was  sus-
pended on CSO,  it  is the best we  can  offer  at  this time.   Now  I guess it would be a
 good time to open  it up for questions,  if  anybody has  any questions.
                                     77

-------
Mr. Dean Elworth -   (City  Engineer,  Dearborn)
We were told by EPA  we  were  not in compliance with PL  92-500,  that we should clean
up our  overflow.   We applied  for a  permit to discharge  into  the Rouge  River  our
combined sewer overflow and  we  were  told that by a certain  date,  we  have to submit
a plan  on how to  comply  with  EPA standards,  which  was  plainly   speaking  to  have
fishable,  swimmable  waters.  We hired a firm, completed  our plan, submitted  it to
MDNR where  it's  been sitting.   Why  did we waste our  time doing it?   What  are  the
standards  now?   Is  someone  going to come and pick  up our  mayor and  council  and
throw him  in Jackson because we haven't  complied with those standards and  violat-
ing permit?  What are we doing?

Mr. Novak
First of all, I wish there was  a  representative from  the State  at  this time to ans-
wer your questions.  As far  as  how you completed Step 1, I don't know where you are
on the priority list and the possibility of getting funding.   But in exploring the
problems within  the  U.S.  or just  the problems within  this  State, just  the higher
priority projects  are  the ones that go forward.   As  far as the   standards  of  the
State, the  standards to meet,  there  is and will  be  a  continuing  program to permit
discharges we refer  to  the NPDES permit program.   There is  no  more Step 1 and Step
2 funding  per  se,  as of the latest  amendments to the  construction grants program.
But there  is funding for  construction  and combined  sewer overflow is eligible  for
funding through fiscal  year  1984 and then in fiscal year  1985  there  is a set aside
which  is  under  the  discretion of  the governor  which would  take  care of  those
projects which would no longer be eligible.   Combined sewer overflows  are  in that
category.  If the State determines that a particular problem is such that it is of
high priority, then  that project will go  forward.

Mr. Elworth
I realize  that,  but  does  this  decision mean  that you're  going to amend  or reduce
your standards and requirements.   We're in the same boat you guys   (City of Detroit)
are, we can't do anything  with  combined sewer overflow before anybody else does.

Mr. McGrail
The standards of  course are set by  DNR.    They have  to be more or less consistent
with what EPA desires or at  least  as  stringent.   But  generally  they are set by DNR.
The problem we have, the problem that you have, is that if you have  one CSO a year
during a low flow period which  is  perfectly possible;  a July thunderstorm during a
low flow period; you're  going to have contamination of the streams, or violation of
the water  quality  standards.   So  you  never,  with  CSO, so  long as  you  still  have
CSO, are you going to be able to control  the  quality  of the stream.  That's  a fact.
So you're running up into  a  catch-22  situation.   We propose facilities that we know
are doomed to  a  modest level of failure  at the instant  that  they're put  into
operation.
                                     78

-------
Now  in  a situation like this you  have  to  play the part of Cheshire cat.   You have
to ask  the question where you want  to  go  depends on what  you want to  do.   If the
City  of  Dearborn  feels  that  water quality and the public  good will be preserved by
improving  the Rouge River,  installing the CSO control  facilities,  I think that has
to be said as a high agenda  item.   You have to essentially go to  the  State and de-
mand  money for it.   On  the other hand,  you might say,  "Look,  if you're not going to
do anything,  you're going to put  it  so  low  on the priority  list  that you'll never
get  funded, then  why not just  tell  us  to  go away  and  don't  waste  your  time."
Essentially, that's what  we  ended up doing.   That's  about all I can say.  Go to the
State and  demand  money  or demand to get off  the priority list.

Mr. Elworth
Nobody  is  going to  spend  that kind of money  if nobody  else does.

Mr. MeGrail
I agree. Absolutely!

Mr. Novak
I don't  know how  to really address your problem.  It has  to  do with the prioritiz-
ing  of  projects based on the limited amount  of  dollars.  I think  that  it is going
away  from  the  report  on the   CSO  which  was  the  purpose  of  this   meeting.    I
appreciate your concern.

Mr. Makinerny - Resident  (City of  Dearborn)
From  the City of  Dearborn.   Just  as  a  point  of information,   the  suspension  of the
facilities  planner,  what's the date that that happened, approximately?

Mr. McGrail
DWSD  officially terminated Giffels/Black & Veatch  -  a  joint venture, the facilities
planning consultant on  June   25,  1981.   I  think that's right.  Some  people  in the
audience might remember that.  But somewhere  right around that date, June 25, 1981.
Now the  decision  to terminate on  or about that  date came a good  deal  earlier than
June 25, 1981.

Mr. Kevin  Tourneur  -  (Southeast  Michigan Council  of  Governments)
Just to  clarify a point,  we  should understand the  USEPA and the City of Detroit are
not setting a precedent  for  CSO  planning  within a region by  suspending their work
or their future plans, etc.

Mr. Novak
That  is  correct,  there  has  been no decision to terminate  the planning.   It  was  a
matter of  suspension. (The Federal District Court  decided to  suspend CSO planning).
I again disagree  with  John on  some  of  the major reasons  why  the  planning  was
terminated, but  if  you  look at  the total  dollars at this  time that  would  be
required   to  complete   planning  for   construction,   with  capital   costs   esti-
                                  79

-------
mated over a billion  dollars  in the  more costly alternatives, it is questionable if
those dollars will be available in the near future.   A good question would be, "Why
spend the dollars to  complete the  planning portion now when we aren't sure that the
dollars will be  available in the  future  for  construction?"   That  kind of  picks up
on the earlier question,  perhaps one of the reasons  why CSO planning was  suspended.

Mr^ Swinick
Let me interject, I think that's  a fairly critical point.   The law is on the books,
the Water  Pollution Act has  been amended by the  Clean  Water Act and  then  amended
again  this past  year.   Fishable, swimable  waters  is  still  the  intent  of  the
Congress.  The State still  sets standards,  the  EPA still  funds combined sewer over-
flow planning.  In the City of  Detroit's case, it has been  suspended,  not stopped.
A decision hasn't been made to  quit and not do it again.   It's  just  been suspended
because of circumstances.

Mr . Kevin Tpurneur
There's a  number  of other  projects currently being worked on, and  studied within
the region that are  considering  abatement  alternatives  and it's  important  to know
where they should focus their efforts.

Mr. Ken Bonner - (Wayne County Department of  Public  Works)
To add to  what  the  gentlemen from  SEMCOG just  said,  one  of the problems  you indi-
cated for  being unable  to   improve the  main branch is because  of  the  background
water quality of the  branches.   We  are  undertaking,  we have  just  completed essen-
tially, the study  of  those  three branches.  Looking  at some  63  CSO sites  on  the
three branches, our Alternatives  indicate that we can improve  the background water
quality and it would seem most  unfortunate  if you could  not pick up on  the improved
background water quality  and rerun your  model  with  those improvements built  in to
finally  get  a  coordinated  study.  This  study  has  been  proceeding  apparently
concurrent with yours but never together.

Mr . Novak
The study  that  has  been going  on  has  been a facilities planning study.   This  is
just the review of the work that  was  done.   We  are aware that  there  have been many
efforts to coordinate  the  facilities planning  in this area.   That is  also  one  of
the recommendations in this report, to  make sure that you have a  combined look,  so
you have a better idea of the quality  of the water upstream,  and  a basis for vali-
dation of the models.

Ms . Mary Richardson - (League of  Women's  Voters,  Citizen Advisory Committee  - DWSD)
Was there  anything  put  in  there  about  the recommendations  that came  through from
the Combined Sewer Overflow Committee on DWSD?   Were those incorporated  in there?
                                     80

-------
Mr. Novak
There  is.   I think the  best person to answer that would be Peter Swinick because he
most intimately  worked  with them.   But there is the section on public participation
recommendations.

Mr. Swinick
It's fair  to say that  the recommendations of the CAC  were considered in detail. As
you  know,  we have  a very good "give  and  take" between the Citizens  Advisory Com-
mittee  and the  consultants, the  City and  USEPA.   Are  you speaking  of something
specific that you feel  is missing?

Ms. Richardson
Yes, coordinated approach  that was  right on from  the very beginning  for  the need
for a  coordinated approach and the fact that this is a piece meal approach to split
off DWSD,  our  feeling on that committee  was right  from the beginning  to split off
from to put DWSD through that kind  of thing when it's just a portion  of the total
watershed  and that's the  same thing we're telling  them that the Rouge Valley sewer
service area.

Mr. Swinick
Can you touch upon basin  planning?  -  John/Jim

Ms. Ri chardson
You need basin wide planning on  something like this.  This was a strong recommenda-
tion of the CAC.   I don't see how  you can do it any other way. And you left another
big  fat  hole in  there, its  storm water management  apart from  the  combined sewer
overflow and its  structural consideration you're thinking about having it (storage)
in a floodplain  area and  if you  don't control the storm water or have some plan for
that coming in,  you're  going to  be in wet water more ways than one.

Mr. Novak
The recommendation of the report is  to coordinate the effort of facilities planning
that  is  going  on, to  use  the information  that is  developed  so  that you  get an
approach which is  taking  into account other planning  done  in  the area.  Facilities
planning requirements  require you  to  look at the effect of whatever  action you're
doing on the receiving  stream.  But  in  looking at  the effect of what  you're doing
on the receiving  stream,  you have  to take into account the  effect  on other things,
other facilities,  other discharges,  to the streams.   So it  should  be a coordinated
effort that way.   As  far  as  the  basin approach,  that would best  be  left  to  the
State to propose  as a project to go  ahead if its presumed  to  be the  high priority.
It would not be appropriate for the  DWSD to get into  the  planning  of all stretches
of the Rouge and Detroit  Rivers  to do facilities planning  for areas  which  are out-
side of their  service  area.   To  get  information from these areas, yes, but to do
the facilities planning for these  areas  would be inappropriate.
                                        81

-------
Ms. Richardson
You're  dumping your  responsibilities right here.

Mr. McGrai1
Mary, we  recognize that  there  is  a problem with the lack of coordinated approaches.
Between,  for  example,  Wayne  County and Oakland County and ourselves.

Ms. Richardson
That intercounty  coordinating  committee hasn't worked out at all.

Mr. McGrai1
The  so-called Act 200 committee  has come  to some  reasonable  conclusions  on  the
subject which sort of  indirectly  relates to CSO.   For  example,  Oakland County,  the
Evergreen-Farmington District  of  Oakland County,  wanted service through the Depart-
ment's  sewer  system.   Well,  as  you  know,  the Hubbell  and Southfield  sewers  are
strained  under wet weather conditions,  they've been  strained for years.   In fact,
the West  Arm Interceptor  was  partly  to relieve those  two sewers.   Take  the  dry
weather flow  out.  Well, we're not  going to have the West Arm.  But we  still have
the relief problems  in the Hubbell and Southfield sewers and the CSO to go with it.
One of the approaches  that we  are considering now is to  divert  flows from the Hub-
bell Southfield  system  over  to the  First  Hamilton  relief  sewer  which  is  quite  a
large sewer but relatively unutilized.  Now, what  that will  do  is  provide adequate
service  for  Evergreen-Farmington but  at the  same  time it  relieves  the  Oakwood
Northwest Interceptor  system  sort of indirectly.   If we  can relieve the  Oakwood
Northwest Interceptor  all the  way down the line,  down  towards  the plant,  we also
will be able  to relieve  some  of the combined  sewer overflow  problem. But that's an
example of a  coordinated effort because what that will require is the connection of
a  linkage between the  Hubbell-Southfield and  the First Hamilton.   Money from that
will come from Oakland County.  Oakland County may see it a little  differently,  but
it's a  question  of negotiation.   The fact  of the matter  remains  that  this  is an
example of  regional cooperation.   Now that  also  provides  some  benefit to  Wayne
County, because Wayne  County has   some,  we have  some  capacity problems in the face
of  Wayne  County.   If we  could  relieve the  Oakwood Northwest Interceptors,  then
Wayne County  would have  more spaces  in the  system which would also  be relieved.

Ms. Richardson
But historically  speaking from the League's  standpoint, Detroit and  Wayne County
haven't even  talked to each  other which is not very  good from the  citizens' stand-
point.  Everybody gets  shortchanged on  that.    I  didn't know  whether this  was  a
meeting, whether  we  could make a  recommendation,  that  some group could  be  able to
do that for the citizens, because everything has come to  an  impasse up till now.  I
do  think  that the facilities  planning has opened  up the process so that we got  a
real good start  on  getting something  going  and I  hate to  see that  go down  the
drain.  Speaking of drains.  Either through SEMCOG or particularly  on  the Rouge or
                                        82

-------
a beefed-up  Rouge watershed council  get  some coordination. There  are things going
right  now.   Maybe you  could get talking  together  again but I  know  it's a problem
but  I  think it  deserves something more  than having  these things just  pulled  out
from the shelf and not  being handled  any  further because some of these things could
be addressed.

Mr. Swinick
I think your point is very,  very well taken.  It runs  into a  very interesting sit-
uation  in  that  its  one of  the  few situations  across  the  country  that I  know of
where  the  problems extend into  many  many  jurisdictions,  three counties,  you have
such a large utility agency  that still  doesn't cover the whole area.

You  also have  situations where  the federal  law,  the  construction  grants  program,
doesn't necessarily  lend itself easily to solving the problem  either.  Because, to
fund it under  what we  knew  as  Step 1 , requires  a  grantee or an  agency, and there
doesn't seem to  be  any convenient agency around  to  fund  it  under.   That leaves
other  sections of the law, and  as  Jim said, it appears to be best left in the hands
of the State to  make the decision on.  Maybe a basin-wide  planning  analysis needs
to be  done,  but  that's not something  that the  federal  agency can  recommend for-
mally.  It's  really  a  state  decision.   Maybe they can talk in the  back room with
the State on it.

Ms. Richardson
But where do our recommendations go?  They don't  go to the EPA, do  they go to  the
State?  Does EPA want  a copy of this?  It used to be  a public  hearing  on  what  you
did.  Now is this the whole  thing?

Mr. Swini c k
Well,  one  subtlety,  this is  not a public hearing, this  is a meeting.   (Audience
breaks out in  hysterical laughter)   I  knew I shouldn't  have said that.   Somebody
had  to  say it and  I guess  I  was the  goat.  That's   another  one  of those little
federal regulations. They mean  different  things.   Jim that's  a question  for you.
How to they get  that recommendation to  the state?   Copy you?

Mr^Novak
Okay, you're talking about a basin-wide approach.

Ms.Richardson
Any river that needs it.

Mr. Novak
The State has the responsibility for  water quality within  the  confines  of  a basin.
So your recommendation  should go  to  the  State agency.   As far as your  input into
the  public  participation  program,  the concept  of  the  basin  wide  study  didn't
                                     83

-------
make  it into  the final  document.   Coordinated facilities planning,  reemphasized
that  it needs to  be  done,  was  included.   Basin-wide  planning  itself  was  not
recommended  because of  the  limitation that  was alluded to before  about  the  need
for  a singular grantee  to take  on that  responsibility.  The  "coordinated effort,
working together" type  of approach  is  necessary or a lot of money will  be  spent in
a  direction  where we're only dealing with  pieces  and parts and not the  whole.   So
that  recommendation,  the concept of that part of  your  recommendation,  was  put  into
the report.

Mr. John Chasesa  -  (Lake Erie Clean-Up Committee)
Talked  about  solving problems  at  a   local  level,  claimed  no benefit  from  EPA
involvement  and wants DWSD to assist in clean up of Lake Erie.

Mr. No vak
The concept  of looking at these things  locally  as opposed to  the regional concept
illustrates  a  philosophical change  or  redirection nationally.  Initially,  when  the
program started  from a EPA perspective,  one looked at  the megopolis.  You look at
the large project because there was an  economy of scale, you built one  plant to
take  the  waste  of  the  surrounding communities,  and  that plant,  by  building it
larger, is going  to have  a lower unit  cost.  That was the  philosophy at  that time,
but that  has  changed.    There  has  been  a redirection  or  reemphasis.   The  great
example of  that  is  when  you  look at your  rural or almost rural communities  where
the emphasis today  is  on innovative and alternative methods of  treating  waste.   It
gets  back  to  on-site  systems,  mound  systems,  cluster  systems,  cluster-mound
systems.  It's a redirection of how to solve problems.   You have  to  identify  the
problem,  you  have  to  define  the  problem  and you  have to  look at  reasonable
solutions to address  it.   So from an agency perspective, we have contributed on  the
Detroit project.  We've provided money,  we've  done an  environmental impact  state-
ment  on the  segmented facilities plan,  we were doing one  on  the final  facilities
plan.   We have provided  input  throughout.   Our input   on  the EIS  has changed  and
redirected the planning for  Detroit and has  limited  expenditures.   We can go  into
cost  savings in dollars  saved by not doing some  construction.   There has  been quite
a bit of benefit  derived  from our participation.

You're talking about Lake Erie  clean up?   There  has  been a  remarkable reduction  and
I don't have numbers  in  front of me and I'm not  a  number quoter anyway.  But there's
been  a  remarkable  reduction in the  amount  of  phosphorus,   which  was  originally
attributed to  the  wastewater  treatment  plant,  which  now  is  treated  because  the
plant has been providing  secondary  treatment  since June  of  last year.   The  limit in
the permit is  1 milligram per liter and from, this is off  the  top of my  head,  from
looking in the past monitoring  reports  for  the year,  it's averaging  somewhere in
the neighborhood  of .6,  .5.  So there have  been  improvements.  While the goal of
our agency  is  pure water, you  have to work at it  over a time,  with  the limited
                                     84

-------
amount  of dollars  that  are available  and you  have to  do  it  by  prioritizing  and
approaching  the  problems the best way you can.  I don't  mean to jump back at you or
anything  like that but  it's just that there  have  been improvements.   This is  the
system  that  we have now, this  is what we're trying to work with and we're doing  the
best we can.

Mr. Chascsa
I'm not up here  to  pick  an argument with anybody.  But I am very disappointed, very
disgusted.   Since  1962 when Jerry Reeves made the  statement that we would want  the
people  in Detroit  to put  diapers on ducks  before they  flew over our  part of  the
community in Lake Erie  and I  have to  tell  him to try  some of the  samples that  I
presented at the first conference in 1962.  Drink the sample water.  For all of  the
specialists  to  taste the  water  and use it  for  anything to  dampen  their  hair,  but
they wouldn't even  do that and the water was  supposedly cleaner than it was in  the
past 40 years.   You're having  the same problem  now  on  the  Rouge River and the only
solution  is  for  the industries  to treat their  own waste.    You can't  take all  the
waste  and put  it  together and  expect Detroit to  be  able  to take  care  of  it.
Because I don't  believe  that's a  matrix plant.  If  it's a matrix  system you may  be
able to do  it.   You would  have  to have the facilities  to  do it.   It  might cost  a
little  bit more  money,  but  it would  be something that would be workable.   If each
industry  took care  of their own  waste,  and I know this can be done, because Detroit
Diesel  did it.   They were  dumping in the Rouge  River and we contacted Detroit Die-
sel plant and we  suggested different  things  to them.   They put  in treatment  and
they were a very good neighbor  in that part of the Rouge River.  They cleaned  up
their water  and  put in better  water than you can find in the Rouge River.

Mr. Novak
You're  opening  up a lot of questions,  things  like  pretreatment  requirements,  and
other areas  which are really going beyond  the intent of this meeting.

Mr. Chascsa
I realize that,  but if you intend to  clean up anything  or  to make  it any easier  to
clean up, this is what will have to be  done. You can't just push it off on the tax-
payers.   The taxpayers  are  the  people that are going to pay  the bill and try  to
pay it.   Some of them will  probably  do without their  cup  of tea.   I'm sorry that
I'm not in better condition because I  had  a heart attack.   But  I  certainly thought
that I  would hear  something encouraging that would  make me  feel  a heck  of  a  lot
better  than  I have been feeling  in the past  three  years.  I know  that  this can  be
done.   I've  seen  it happen.  I've seen the  lake  clean up. I've  seen the time when  I
couldn't  eat the fish out  of  the lake and  today I'm not  afraid to eat  them,  be-
cause they do taste like fish not  like fish full of dirt and oil  or something  and
they don't smell bad.   But  anyway  I thank  you for the opportunity  to  get  a little
bit off my chest.   But I have  some pamphlets here if you would like to take it with
you.  You'll  find them quite interesting.
                                        85

-------
Mr. Cruz
(For the record, Kenneth  B.  Cruz  representing the City of Allen Park)
Mayor Latta  asked me to  read  this statement  into  record and also submit  it  as an
exhibit of this  meeting.   The City appreciates  the opportunity to comment  on this
report.  We've got  a  special interest in this report  for  two  reasons.  First a por-
tion of  Allen Park  is  served by  the Detroit System.  Therefore our residents  are
affected by  these  changes in capital and O&M expenditures.   Secondly,  the  City is
served by  a  combined sewer  system for which  a  facilities plan has been  prepared,
which  comes  to  diametrically opposed conclusions  to your  report.    Our  general
comments are  as  follows:   First, the  conclusion of  the  report which  is  based on
modeling  and analysis  indicates  that little  or  no  activity  relative  to CSO  is
warranted  at  this time,  particularly  in  regards to  the Detroit River overflows.
The City of Allen Park agrees  with this finding in general and has found that using
the same methodology  of  analysis that  for  a  similar but  a smaller combined system
in Allen Park that  little  or no  action would  result in the most reasonable solution
there.   Second, we  find it  ironic  and tragic  that the EPA is  encouraging the expen-
diture of  approximately $60  to  $100 million for sewer  separation  in  Allen  Park,
which comes to about  $5,000  -  $8,500  per  household with all  its disruptive effects,
while sewer separation  alternatives  in the Detroit study ranked  among the poorest
choices of the 25 evaluated.   The costs of the highest ranking alternatives in the
Detroit report  are $130  to $145  per  capita.   How  can  EPA  and DNR  justify  the
extreme disparate treatment  to the different  portions of  the  same small city.  We of
the City  of  Allen Park  believe  that the basic recommendation  when  planning  is
resumed,  that primary  consideration be  given   to  inline storage  and  interbasin
transfer is appropriate.  Allen Park  would  like  to submit that this  similar finding
should be applied to  that part of  the City  of Allen Park  served by the Wayne County
system.   Allen  Park's  request that  the  EPA  and DNR  consider these  findings  and
bring uniformity  to CSO planning  in  the  Southeastern Michigan or at  least  to  the
City of Allen Park, before  $60 to $100 million dollars are wasted on  sewer separa-
tion.   We  suggest that EPA and DNR  take proper  action  to alleviate  this  serious
discrepancy.   Finally, Allen Park  agrees  with the findings that there  is  a need to
look at the overall  collection and treatment  system in detail  before  a conclusion
should be reached.  This  was not  done  to the City  of Allen  Park which has  led to
erroneous conclusions.

Our more specific  comments will be  submitted in writing  in  the next  few  weeks  on
this report.  Again we appreciate the opportunity  to  comment  and we  urge  the  EPA
again to act on bringing uniformity to  CSO  planning in Southeastern Michigan before
a major misappropriation of  public funds  is made. As  it  currently appears,  EPA and
DNR intend to pursue  a wasteful  sewer separation project  in Allen Park.  We request
some indication from  these agencies on these  comments and their policies.
                                       86

-------
 Mr. Novak
 The effects of concerns that are  raised  are  really very difficult to handle  one  by
 one at this time.  That will best be handled in the responsiveness summary.   As  far
 as consistency on how the citizens  of  Allen  Park are  treated, since you're talking
 about a portion of Allen Park being served by Detroit versus  the  remainder of Allen
 Park by  another  grantee, in  the  planning there  is  a  cost  effectiveness analysis
 which determines the most cost-effective  way  of  addressing the problems in an area
 as defined within the facilities plan.   I am not  familiar with the planning  effort
 going on in Allen Park.  Again,  your comments will be  addressed  in the  responsive-
 ness summary as  would  your  subsequent followup  comments if  they're  received in  a
 reasonable amount of time.

 Mr. Robert Pierce - (Consulting Engineer, Black & Veatch)
 I  just want to be sure  we thoroughly understand the EPA position which evidently  is
 distributed here as  a  final document  and has  been received by the  public  some  10
 days ago.  Does this actually constitute  the official EPA policy regarding combined
 sewer overflow planning in Detroit in conjunction to the planning process?

 Mr. Novak
 First of all,  it's not  really policy.  It's  just  a recapitulation of planning that
 was done with  our concerns about that planning.  In other words, a way of approach-
 the problem when it is  picked again, and  some  areas that we  think should be  looked
 at a little differently.   Again, this is  not a decision  document.   It is a comment
 on planning that was suspended abruptly,   so that we know what was done and we know
 limitations, how good,  how bad the product was and where  we  can  go  when we pick  it
 up again.  That  was  the  intent and why the report was generated.

 Mr.  Rama Cherukuri  - (Consulting Engineer, Rama Rao &  Alfred, Inc.)
 (Paraphrased)  - Isn't SEMCOG the regional planning agency,  and shouldn't all plan-
 ning be  coordinated through  them?

 Mr.  Novak
 Facilities  plans are reviewed by  SEMCOG's A-95  review board.   (The A-95  review
 process  was recently revoked by  Executive Order  12372.   SEMCOG's Water  Quality
 Board  does  review  facility  plans  for  consistency with  the  State  Water  Quality
 Management  Plan.)   That is,  after  facilities  plans have been  generated.   As  far  as
 the  input  into  processes, it  comes  after the  fact.    It would  be  better if the
 system was  set  up such that  before  the  plans  were  generated there  were some overall
 coordination which  is part of  the  problem that  has plagued this project, too.   Yes,
 they are  responsible  for  review  of  sewerage planning in this  area.   They're  not  in
 the  position of  directing the  planning.   The  overall  water  quality  responsibility
 relies with  the State.

Mr. Cherukuri
The law does not  say what  time they  should become  involved?
                                      87

-------
Mr. Novak
It  does,  it  specifies when A-95 review  takes  place.   (The A-95 review  process was
recently revoked, but U.S.  EPA Region V  is developing a regional policy for consis-
tency with the State  Water Quality Management Plan.)  Reality  is  that the planning
conceptionally  should have  been  statewide, then  regionwide  and  then countrywide.
Realistically  the  way the  program has developed  is  at  a specific  facility level,
working  up  the  wrong way.    Let  me  explain the  way the  system  had  worked  and
generated.   When the program  started, the problems  were  identified.   There  was  a
priority put on the  problems.   The planning  was  started.   But realistically,  the
State should have identified the  problems and then should have  looked at  them from
the State to the region,  then  to  facilities planning.  Unfortunately,  it is not the
way things have  generally gone.

Ms. Richardson
I hope  I  made it clear,  I have served  on the CAC for both  studies.   We  got some
really  good  information  out  of  both  of  those studies and if  they could  just  get
that coordinated we'd be  definitely along the way for getting cleaner  water.

Mr. Bheam -  (DWSD)
How does this  report  differ from  the  Facilities  Interim  Report put out by another
consultant for the Department  for  the City of Giffels/Black & Veatch-joint venture?

Mr. Novak
The interim  report  put out  by Gif fels/Black  & Veatch was  just as  inferred by  the
title,  an  interim  report.   It looked at  and  identified  problems,  looked  at  water
quality of  different  alternatives  and it got down to a  reasonable number, but  it
didn't do the last reiteration and go into the detail necessary to  complete facil-
ities planning  on  CSO.    There was an ongoing environmental  impact statement,  and
we  had  intended  to   have combined  sewer overflow  included  in  the  environmental
impact  statement.   Since  the  facilities planning was  suspended on combined  sewer
overflow, we would have no  document in which to  include this.   We  invested time and
money in EIS process. Since the  facilities planning was suspended,  we as  an agency
could review the  AFIR  (Alternate Facilities  Interim Report),  but  we  wanted  to
evaluate it  technically and we wanted to see where  we were at,  so  that  when  CSO
finally was  picked up again, we would know where  to  go.   This report does  reference
throughout the  work  done by Giffels/Black & Veatch.  It  doesn't  redo their  work,
but it  provides an audit type of  approach and  it  makes  suggestions and  provides
some guidance for our future work.   It's not  intended to be  a  decision  document  as
was said before, but  it provides a critique and  some  basis to proceed.  Our agency,
and I hope Detroit,  feels a little more  comfortable  in the work that was  done  and
we have  a good  idea  of  how  useful  the  information is  and  where  we can  go from
there.  That was the  intent.

Dr. RaIph Kummler - (Wayne  State University)
Is this report issued in  its final version at  this time?
                                    88

-------
Mr. Novak
I  don't  want  to give  you a  bureaucratic  answer,  like  the  difference  between a.
public  meeting,  public  hearing, and suspended and terminating and things like that.
There  are different meanings.   This is a  bastard report	(Laughter).

Dr. Kummler
Yes, I  believe we've  stated that for the record.

Mr. Novak
	Meaning  a non-standard report.  The requirement  for  this  report does not fall
into any nice little neat category.   There are  public  participation requirements
for  both  facilities  planning and  environmental  impact  statement.    There is  a
hearing requirement  at the  end of  the EIS  process.   There  are  public  meeting
requirements  throughout  the  process.    There  is  public  input provided  through
Citizens  Advisory Committee.   This, today,  is  a meeting on this  report which does
appear  in final  form.  What will be prepared subsequent to this  meeting  and which
will address  comments  received  within  a reasonable amount  of  time  is  the respon-
siveness  summary.   The  responsiveness summary will  address  all  comments.   This re-
port does not fall into a category of an  EIS,  it doesn't carry  the weight to the
decision  makers  that  an EIS would.  It  doesn't  carry the weight  of facility plan.
It is  just a  recommendation and it's to be used as a tool and nothing else.

Dr. Kyrnmler
There  are serious omissions in terms of data that  was taken  that was not addressed
in this  report.   For  example,  Wayne State University  is  not  mentioned as  a subcon-
tractor  despite  the fact that we generated over 1,000 pages (  2 PhD dissertations
and two master theses)  and also put together some  dozen  or  20  technical reports in
the professional literature.   I've submitted  a  list of  omitted  references which
bear heavily  on  the findings  in this report.

Mr. Novak
Was this  information  made  available to  EIS consultants in preparation of this docu-
ment?

Dr. Kummler
No one's  ever asked for it.   It is  saddening to  see that the report was done in the
absence  of  substantial   amounts  of  information  that was  gathered by  the  original
contractors.

Mr.Novak
Do you  disagree  with  any of the  recommendations as outlined in  this presentation?

Dr. Kummler
Yes.
                                        89

-------
Mr. Novak
Specifically, which  things  do you disagree with?

Dr. Kummler
There are a  number of  them.   We have put them in writing already and I can still do
so.

Mr. Swinick
I  think it  fair to say that a  responsiveness  summary  will  be  created  on this
report.  It's not the  intention to redo the  entire volume with the  responsiveness
summary  attached.   But there  is  no problem  if  in answering  questions  the respon-
siveness summary has to go  into  significant detail  and  be 150 or 300  pages long.
That won't be the first time.   So all questions  and  comments, new  data that wasn't
provided previously  or 1,000  pages  of information that's  on a  computer  disc that
never got printed out  should be submitted if it  bears on  this report!   Whatever it
is it can be included if we are  made  aware of it. If we  can  get the comments, the
questions, the  information   provided  to us,  it  will  be incorporated within in the
document.  And  if  it is that  significant  and there are resulting  major changes in
recommendations, then  that  can be  done  within the responsiveness  summary as well.

Dr. Kummler
One of  the   major points  of  information  that probably  should  be  said here  is  in
relation to  what the gentlemen spoke of Lake Erie.   Of the problems  in the Detroit
River, all  of the numbers  that you quoted deal  only with a  small fraction of the
Detroit River and  there  was a  lot more  of that  river that flows down  to  Lake Erie
and which was being modelled,  and those  calculations  are available,  and were not
presented in the bar charts that you  presented.   The impression that  we  gain from
your report  is  that there  are not  significant  problems  in  the Detroit  River.   I
think that there are crucial problems on the Detroit River.  The impact of CSO cer-
tainly deals more specifically with the Detroit  River because there  is nothing else
there to be  a major  factor.   CSO is  a major problem by itself  and  when  the Mayor
dedicates parks, plans come  out for part or  full  exposure  depending  where you fall
out of your  canoe or  you dabble with your  hand on  the  outside in  that  area some
1,000 feet below Leib  (overflow discharge) I  think you have to take  that  seriously.
When you plan a  marina, it's not  going to be real  easy to  convince the kids not to
hop off the  back of  the boat after a  rain storm.  And, there  will be  serious health
problems that will be  associated  with the future  development  of the  City.  I think
that will be another problem for  development  along the Detroit River. Of  course, no
one mentioned the some  18  bathing  beaches  down  river with  some 60 marinas, down
river which  are  all  impacted by what we do up here.  None  of that  was mentioned in
your analysis.   But  again  if  you  read Dr.  Razinski's  dissertation, you will see
some of the  information that pertains to the  entire river.
                                        90

-------
Mr. Swinick
I thank you  for  that  and I do hope that when the questions and the comments and the
data  does  come in  that  everyone recognizes that this report is not going to pick up
where  the  interim  report left off.  At that it is again a summary of what occurred.
It is  not  a  decision  document to pick and choose a combined sewer overflow alterna-
tive,  and  to fund one.   It  is  a rehash, a summary  of  that  background information,
and we'll  be happy to receive more of it then we have had in the past. Thank you.

Mr. Steve  Ode n - (East  Lansing)
I'd  like  to get  a definition  of the  amount  of  rainfall  which constitutes  wet
weather?

Mr. Vance
I think  the  Rouge  River,  for the  wet weather conditions, it was  assumed - because
the flow would carry  pollutants out in about 24 hours  from  the planning area, (the
model  planning portion)  that essentially for the 6600 hours (April - December) that
it was continually a  mixed state of wet and dry weather.  While earlier there might
have been  attempts to separate  dry weather out from wet weather in the Rouge River,
as far as  running the model  goes,  I  think that in the end it  was  assumed that wet
weather would always  be masking the  dry weather.   So  as far  as  running the model
for the  Rouge River,  it was assumed basically  to  be in mixed  state.   The Detroit
River  was  a  different story. I  don't  remember  right off hand  how  many hours might
have  been  used.   Maybe  someone  from  Black &  Veatch can help me.   1634 wet weather
hours  out  of a potential 6600 for the nine months.   For  purposes  of  the initializ-
ing data,  if that's what  you're referring to,  I  think at least as  we checked the
data  that  they  used,  that the  dry weather data was  defined as for  those periods
where  it did not rain for at least 24  hours  before hand.  And  most  often the data
went  well  beyond that  to  48 or 72 hours  of  no previous  rainfall  if  it  was  to  be
counted as dry weather.

Mr. Oden
Some of the  data I  have  read seemed to indicate that after a couple of tenths of an
inch of rain, real  problems  existed.   And it  seems to me that this system shouldn't
have been  designed to carry  only a couple of  tenths of  inches of rain.

Mr. McGrail
Unless I'm mistaken you have to decide what  constitutes  a rainfall  of  measurable
significance.  In  Detroit  area  you have pretty much distributed rain throughout the
year,  or distributed precipitation.   There was  a figure arrived at that constituted
the beginning of a wet weather condition and I think  if was  like .0095  inches  of
rain an hour.  Something of  that nature.
                                       91

-------
Mr. Devanso  (DWSD)
I  don't know John,  but a  couple of  tenths of  an inch  of  rain is  a significant
amount  of  rain.  If  a quarter of inch of rain falls and you have a catch basin area
of  140  square  miles,  if  you just consider  a runoff factor of  just  50%,  you start
multiplying  out  the  number  of gallons coming into the sewer system, a quarter of an
inch  of rain or even  a tenth of  ar  inch of rain  is  very, very  significant.   The
system  is  designed to  tak°  (drain)  1.95  inches  per hour.   That was  based on the
rainfall curve from  all the  way  up through the 1940's when those design curves were
established. But let's say  a tenth of an inch  of rain  over  this area would  be a
significant  amount of  rain.   And you have 70 some overflow points, which means that
you have 70  some drainage districts.   And some of  those  are very small.   If you go
back  and look  at some of the data that  was  done a number  of  years  ago,  some drain
districts  hardly every overflow.   Thev were  way  over-built and  other ones will tip
at the  drop  of a hat.   What  we  established way back in  the early 70's was that the
system  fell  within the textbook  analysis; they  overflow 2%  of  the  time,  but  some
overflow a lot more  than  2%  and  some  are a lot less.

Mr. Oden
Does  the City  of Detroit have  a plan for  requiring site  retention  of  drainage on
new large  projects such as parking lots, shopping malls?

Mr. McGrail
Let me  say this.  I  suppose  that  they do.  However, as you well know, there isn't a
great deal of large  construction  going on.  I do know for  a  fact that the new Cad-
illac facility  auto  assembly plant,  it's up in  the controversial Pole  town area,
has some storm attenuation  facilities associated with that.   Of course,  that's 465
acres of virtually all paved territory which at one time probably had a run-off co-
efficient  of 50%.  But in that facility  they do  have  some storm water attenuation.
Basically, I think it's just parking lots and  roof  retention,  but  insofar as the
rest  of the  city is  concerned,  there isn't  a  lot  of brand new major construction
going on in the  city.  There  is no attempt to go  back  and correct.   For example, we
don't eliminate  obvious  inflow sources such  as  the footing drains around buildings,
we just live with them because  there is  no  functional purpose for removal since it
flows into the same  system anyway.

Mr. Steve  Williams -  (Consulting  Engineer, Williams & Works)
In reading the Alternatives  Facilities Interim Report,  another  aspect of  the prob-
lem which  may  help  address this  gentleman's   questions  is  that the  Alternative
Facilities Interim Report states  that  there's relatively little difference in qual-
ity between  urban  storm runoff and combined  sewer  overflow.  Some  of the effected
stream  quality parameters may not be  from the combined sewer overflow but the urban
storm runoff.
                                       92

-------
Mr. Novak
If there  aran't any more  questions,  I'll close the  meeting.   I thank  you  all for
your comments  and for coming.   Does  anybody  know  where the  signup sheet  is?   If
anyone wants a  copy of the  document  let us check  your  name off and we'll  get you
one within a week.  Thank  you  again.
                                    93

-------
LIST OF PUBLIC MEETING ATTENDEES

-------
         Name
                J
   Address
/
.-tfo
3 -Z 3
                                     /_J) v- Y'f c i /
M/M
Would  like responseness
suirjTiary
Yes
                                                                                    No
              0 0 <"'
                                                                            V 6
                                             97

-------
   Name                     Address                   Would like responseness
                                                    s uiTima ry
                                                    Yes        No
                              U44-1 w-  B  HiUa     X
s  n*-    o  v/'    '         Per £,rr t^.^4?2-/^
^QPAL   ROV              qftU  VORKSH^
                                        MI  46114     X
                                 r/^). "
        L  ^  Oruso/y        ^J*f LO. GcL-di»c~ATe SV
                                              T £??  __
                               ~98

-------
   Name
? / (' //
                        Address
>J
                                            U-f
                                  Would like responseness

                                  s umrna ry
                                                   Yes
                                                         'No
     "•  4i>

          (/   ^


        '
^-' --~~i*.'~ —  /vj: '«•>'-?}
                         f
          f—*
          r^ru
           &RC»1
                              a
                           ,-r A-/ c
                                            2 6»
                                   Mr
                                               Q!_E^
                                                7
                                99

-------
Name
Address

                   "?¥^   ^-<=--,
Would  like  responseness
suinmary
                           Yes
                                                                  No
                     J

                                  I  it "*
                                 V"H*::t
                                              ff"~

                         / 5 O '7 '"v'  C" /' Z -1- •- c ' '«.
                                100

-------
    Address                       Would like respcnseness
                                  s u/7vna ry
/W ft fi-c&UtJ               Ys^       No
         101

-------