DISCLAIMER

     This report has been reviewed  by  the  Municipal  Environmental Re-
search Laboratory, U.S. Environmental  Protection  Agency,  and  approved
for publication.  Approval does not  signify  that  the contents necessar-
ily reflect the views and policies  of  the  U.S.  Environmental  Protection
Agency, nor does the mention of trade  names  or  commercial products con-
stitute endorsement or recommendation  for  use.
                                 ii

-------
                                      EPA-600/2-80-003
                                      March 1980
       UPGRADING PRIMARY TANKS WITH
      ROTATING BIOLOGICAL CONTACTORS
                    by

             Alonso Gutierrez
              Ivan L.  Bogert
         Clinton Bogert Associates
        Fort Lee, New Jersey  07024

                    and
             0. Karl Scheible
            Thomas J.  Mulligan
       Hydroscience Associates, Inc.
        Westwood, New Jersey  07675
             Grant No. 804854
              Project Officer

             Edward J. Opatken
       Wastewater Research Division
Municipal Environmental Research Laboratory
          Cincinnati, Ohio  45268
MUNICIPAL ENVIRONMENTAL RESEARCH LABORATORY
    OFFICE OF RESEARCH AND DEVELOPMENT
   U.S. ENVIRONMENTAL PROTECTION AGENCY
          CINCINNATI, OHIO  45268

-------
                                ABSTRACT

      A one-year experimental program was conducted  at  Edgewater,  New
 Jersey, to evaluate the concept of upgrading existing  primary  waste-
 water treatment plants to secondary treatment by the installation of
 rotating biological contactors (RBC's)  in the primary  sedimentation
 tanks.  The Edgewater system is a combined sanitary/stormwater treat-
 ment facility,  subject to significant operational variations related to
 stormwater flow.

      The basic  concept was to horizontally divide a primary sedimenta-
 tion tank into  two  zones by installing  an intermediate  floor at mid-
 depth.  Four RBC  shafts (3.65 m diameter)  were placed  in  the upper zone
 above the intermediate floor.  This zone provided separate biological
 contact and treatment of the incoming wastes,  while the lower  zone,  be-
 low the intermediate floor,  functioned  as  a secondary  sedimentation
 zone.  Such a configuration would eliminate,  or minimize, the  need for
 additional tankage  and clarifiers,  and  would  be especially suited  to
 plants with limited space.   The system  was preceded by  grit removal  and
 high rate primary clarification.

      The experimental program was conducted in three phases over  a full
 year.  Three loadings were  studied  during  the  initial phase to deter-
 mine the optimum  system load that conformed with EPA standards.   This
 loading was then  evaluated  under  summer and winter  conditions.  Optimum
 loading conditions  were found to  be in  the range  of 9 to  11 g/d/m2
 (1.8 to 2.2 lb/d/1,000 ft2),  on a TBOD5 basis.   Influent  organ-
 ic  concentrations were on the order of  140 mg/1  TBOD5 and 125 mg/1
 TSS.   The study determined  the  need for pretreatment, whereby primary
 treatment overflow  rates  of  285 to  370  m3/d/m2  (7,000 to  9,000
 gpd/ft2)  were found  to provide  adequate grit,  trash, and  floatables
 removal.

      A steady-state  fixed film  kinetics model was utilized in the anal-
 ysis  of  the RBC data.   Little difference in treatment efficiency was
 noted  between summer  and  winter conditions, due primarily to the inter-
 actions  of  oxygen availability, mass  transfer, and kinetic removal
 rates, and  the impact  of  temperature  on  each.

    An important  consideration  in the design of the RBC/Underflow
Clarifier system  is the maximum utilization of the underflow clarifier
zone.  This may,  in fact, be  the limiting  condition under certain cases
when setting  the  hydraulic capacity of  the unit.  Suggested design cri-
teria, operating  conditions, and costs have been developed and are pre-
sented as an aid  in evaluating  this upgrading technique at other
primary treatment plants.
                                  iv

-------
                                  FOREWORD


     The Environmental Protection Agency was created because of increasing
public and government concern about the dangers of pollution to the health
and welfare of the American people.  Noxious air, foul water, and spoiled
land are tragic testimony to the deterioration of our natural environment.
The complexity of that environment and the interplay between its components
require a concentrated and integrated attack on the problem.

     Research and development is that necessary first step in problem
solution and it involves defining the problem, measuring its impact, and
searching for solutions.  The Municipal Environmental Research Laboratory
develops new and improved technology and systems for the prevention, treat-
ment, and management of wastewater and solid and hazardous waste pollutant
discharges from municipal and community sources, for the preservation and
treatment of public drinking water supplies, and to minimize the adverse
economic, social, health, and aesthetic effects of pollution.  This publi-
cation is one of the products of that research; a most vital communications
link between the researcher and the user community.

     The study at Edgewater, New Jersey evaluated a novel application of
rotating biological contactors for transforming a primary treatment plant
into a secondary treatment facility.   This project has contributed valuable
technology in the wastewater treatment field.
                                      Francis T. Mayo
                                      Director
                                      Municipal Environmental  Research
                                       Laboratory
                                   iii

-------
                                  FIGURES


Number                                                               Page

  1     Wastewater treatment plant site 	   12

  2     Plant flow scheme	   14

  3     Primary settling tank before installation of RBC	   15

  4     RBC testing unit	   16

  5     Hourly variations of sewage flow	   17

  6     Hydraulic characteristics, high-rate pretreatment sector. .   29

  7     Results of March 2nd hydraulic tracer analysis	   31

  8     Chronological record of raw wastewater characteristics.  . .   36

  9     Diurnal variations of TCOD, TSS and RBC flow.  .  .  .  .  .  . .   38

 10     Example of diurnal dissolved oxygen variations	   39

 11     Performance summary of high-rate pretreatment  sector.  ...   42

 12     Settling test results on raw influent sample	   43

 13     Chronological record of RBC flow,  8005 and hydraulic rates;
        Phase I (3/77 - 6/77) .	„	   44

 14     Chronological record of TBOD^,, SBOD5 and TSS;
        Phase I (3/77 - 6/77)	   45

 15     Chronological record of TCOD,  SCOD and temperature;
        Phase I (3/77 - 6/77)	   46

 16     Summary of Phase I load evaluation performance.  	   49

 17     Chronological record of RBC flow,  BOD5 and hydraulic rates;
        Phase II (7/77 - 9/77).  .  .	   51

 18     Chronological records of TBODs,  SBODs and TSS;
        Phase II (7/77 - 9/77)	   52
                                   vi

-------
                                CONTENTS





                                                                   Page


 Foreword .............................



 Abstract
          .............................   iv


 Figures  .............................



 Tables
          .............................   ix


 Acknowledgements



      1.   Introduction ......................    1



      2.   Summary of Results and  Conclusions ...........    4



      3.   Recommendations  ....................   10



      4.   Description of  Edgewater Treatment Plant

           and Pilot  Facility ...................   H
      5.    Experimental  and  Analytical  Program ...........  19



      6.    Experimental  Results  -  Summary  and Analysis .......  24



      7.    Analysis and  Discussion - Process Design

           Alternatives  Evaluation  ................  81



      8.    Process Design Evaluation of Edgewater System ......  91



      9.    Plant Design  Considerations   .............. 100



    10.    Cost Analysis of Edgewater Modifications  ........ 114


References  ............................ 125



Appendices



     A.   Tabulation of Raw Data  ................  126



     B.   Discussion of Steady State Model  .......... .  .  197
                                  v

-------
                            FIGURES (continued)

Number

 36     Correlation of net solids production to SBOD5 removal
        rate	   80

 37     Process design curves relating BOD5 loading rates to
        BOD5 removal rates	   83

 38     Single stage process designs relating effluent SBOD^ to
        influent SBOD5 and hydraulic loading	   85

 39     Process design curves relating the effect of dissolved
        oxygen on SBOD5 removal 	 87

 40     Process design at Edgewater 	   96

 41     Process design at Edgewater with aeration and chemical
        treatment	   99

 42     RBC bottom configurations	103

 43     Layout:  example No. 1	104

 44     Layout:  example No. 1 (cross-section)	105

 45     Layout examples in small tanks	107

 46     Layout and dividing wall detail for adjacent tanks	108

 47     RBC Layouts in large tanks (example No. 6)	109

 48     RBC Layout in medium-size square tank	110

 49     Mechanical drives - schematic layout	119

 50     Air drives and chemical treatment - schematic layout. .  .  .  123

B-l     Sketch of sectors in the RBC model	198

B-2     Biofilm schematic diagram 	  199

B-3     Mass flux through infinitesimal slice of biofilm	200
                                  viii

-------
30     Correlation of effluent TSS with effective clarifier
       overflow rate	
                             FIGURES  (continued)

 Number

  19     Chronological record of TCOD, SCOD  and temperature-
        Phase  II  (7/77  - 9/77) ..........        / .....   53

  20     Chronological record of RBC  flow, BOD5 and hydraulic rates-
        Phase  III  (12/77 - 2/78)  ......  . .........   '    55

  21     Chronological record of TBOD5, SBODc and TSS-
        Phase  III  (12/77 - 2/78)  .....  .....' ........   55

  22     Chronological record of TCOD, SCOD and temperature-
        Phase  III  (12/77 - 2/78)   .........        / .....   57

 23     RBC kinetic model verification based on interstage
        SBOD5 and DO Data  .  .  .   . ...........  .....    62

 24     RBS kinetic model verification based on interstage
        SBOD5 and DO data .......... ......  ......  63

 25     RBC kinetic model verification based on in-1 erstaee
        COD data ........                         6             ,.
                     ........................  64

 26     Estimate of RBC  oxygen  utilization rates  ..........  66

 27     Predicted substrate and oxygen profiles in biofilm .....  67

 28     Biofilm concentrations  of  substrate  and dissolved oxygen
        in  successive stages  ...............
 29     Evaluation of  impact of dissolved  oxygen  gradients on
       substrate removal   .................           71
                                                                     73
31     Evaluation of chemical treatment for improved solids
       capture	                  „,.


32     Correlation of organic fixed hydraulic loading rate
       to effluent TSS. ...                                        -,,
                                	/D

33     Correlation of organic and hydraulic loading rate to
       organic removal rate	            77

34     Influent, effluent and waste solids.
                                                                     78
35     Correlation of total suspended solids wastage and
       TBOD5 removal	               7g
                                 vii

-------
                            TABLES  (continued)




Number                                                               page




 21     Cost Estimate:  Air Drives, Case 4	122




 22     Comparison of Alternatives  	  124




A-l     Edgewater Raw Data Summary	125




A-2     Edgewater Nitrogen Data Summary	171




A-3     Edgewater Sulfur Data Summary	181




A-4     Edgewater Grease and Oil Summary	183




A-5     Edgewater Phosphate Data Summary 	  184




A-6     Analysis of Interstage Samples 	  185

-------
                                   TABLES


Number

  1     Raw Wastewater Composition	11

  2     Analytical Schedule 	  	   21

  3     Summary of Monitoring Data	25

  4     RBC/Underflow Clarifier Nominal and Actual Volumes	32

  5     Effective Clarifier Volume Analysis 	   33

  6     Wastewater Characterization Summary -  3/77 -  2/78 	   35

  7     Correlation of Major Water Quality Parameters 	   41

  8     Summary of RBC Interstage Data	59

  9     Comparison of Summer and Winter Performance 	   69

 10     Comparison of Observed and Predicted RBC  Effluents	86

 11     Evaluation of Pre-Aeration	89

 12     Edgewater Waste Characterization:   Present Conditions  ....   92

 13     Estimate of Effluent Criteria  	   92

 14     Underflow Clarifier Process  Design Requirements at Edgewater.   93

 15     Preliminary Design  of Edgewater Modification  Using
        Existing Tankage	95

 16     Process  Design Summary at  Edgewater Under Present  Conditions.   97

 17     Generalized Power Comsumption  	 113

 18     Cost Estimate:   Mechanical Drives,  Case 1	117

 19     Cost Estimate:   Mechanical Drives,  Case 2	118

 20     Cost Estimate:   Air  Drives,  Case 3	121


                                    ix

-------

-------
                           ACKNOWLEDGEMENTS
     The cooperation of Borough of Edgewater Officials is gratefully
acknowledged.  We are particularly indebted to Mayor Francis P. Meehan
and Borough Clerk Charles M. Susskind for their cooperation and inter-
est in the project, and to Mr. David P. Collins, Superintendent of the
Edgewater Wastewater Treatment Plant, for his participation in the
sampling and operation and maintenance of the experimental units.

     Mr. 0. Karl Scheible is a Project Manager at Hydroscience, Inc.,
and was responsible for management of the Edgewater field program, data
analysis and preparation of the final report.  Mr. Thomas J. Mulligan
is Technical Director of Hydroscience, Inc., and provided assistance in
the management and the technical analysis of the overall project.  Ms.
Carlene Bassell, Hydroscience, Inc., supervised the field program and
participated in the analysis and interpretation of. the field data, and
preparation of the final report.  The guidance provided by Dr. James A.
Mueller, Hydroscience, Inc., in the interpretation and use of the RBC
Kinetic Model is also gratefully acknowledged.

     Mr. Alonso Gutierrez, Project Manager for Clinton Bogert Associ-
ates, was responsible for generation and checking of data and prepara-
tion of text for the portions of this report under CBA's responsibil-
ity.  Participation of Ms. Barbara Grehl, Engineering Assistant, and
Mr. Thorn Lee Wharton, Technical Writer, must be noted.

     The assistance of Mr. Edward J. Opatken, EPA Project Officer, Mun-
icipal Environmental Research Laboratory, Cincinnati, Ohio, is grate-
fully acknowledged.
                                  xi

-------
      (1)   Establish  the  feasibility of upgrading existing primary sedi-
           mentation  plants  to meet the secondary treatment requirements
           of  PL  92-500 through  the installation of RBC units directly
           in  primary clarifiers.  (The U.S. EPA secondary treatment
           standards  -call for monthly average 8005 and SS concentra-
           tions  in the effluent less than or equal to 30 mg/1, with
           percentage of  removal being equal to or better than 85 per-
           cent,  and  weekly  average BOD5 and SS concentrations in
           the effluent less than or equal to 45 mg/1.)

      (2)   Evaluate the degree of pretreatment necessary to successfully
           operate an RBC system in this mode.

      (3)   Evaluate the effects of climatic conditions, diurnal flow,
           and total  daily load and waste characteristic variations on
           process efficiency.

      (4)   Establish  process and plant design parameters and capital and
           operating  costs for the application of this upgrading tech-
           nique  to maximize the use of tankage and facilities at exist-
           ing primary sedimentation plants.

      The facility was modified and upgraded to assure proper operation
and process control  during  the experimental program.  A three-phase ex-
perimental program was then implemented:

      Phase 1:  Investigation of the RBC/Underflow Clarifier under a
               series of  loading conditions encompassing a range suf-
               ficient to determine optimum operating conditions.

      Phase 2:  Evaluation of the system under warm (summer) temperature
               conditions at the predetermined optimum loading condi-
               tions.

      Phase 3:  Evaluation of the system under cold (winter) temperature
               conditions at the predetermined optimum loading condi-
               tions.

The results of the experimental program were then evaluated to deter-
mine  process  kinetic parameters and overall treatment performance.
Process and plant design  considerations were investigated and an
economic analysis was made of the suggested design alternatives.

PARTICIPANTS AND COORDINATION

     The U.S.  EPA Demonstration Grant was awarded to the Borough of
Edgewater  to further evaluate the RBC/Underflow Clarifier system as
installed  in  its treatment plant.   Edgewater retained the firms  of
Hydroscience,  Inc.,  Westwood, New Jersey, and Clinton Bogert  Asso-
ciates, Fort Lee, New Jersey, as its engineering representatives  to

-------
                               SECTION 1

                             INTRODUCTION
BACKGROUND

     The Borough of Edgewater, New Jersey, operates a primary waste-
water treatment facility which discharges into the Hudson River.  In
1971, Edgewater was ordered by the State of New Jersey Department of
Health to improve the degree of treatment being provided by the waste-
water treatment plant to secondary treatment levels.  Constrained by
severe land limitations, several treatment alternatives were considered
which would minimize plant expansion.

     A process which indicated considerable promise involves the in-
stallation of rotating biological contactors (RBC) in the existing pri-
mary clarifiers.  For proper functioning, an intermediate floor was
required to be installed at mid-depth.  After biological treatment of
the raw wastewaters in the upper RBC sector, secondary clarification
would be accomplished in the sector below the floor.  However, because
the proposed treatment scheme involved new concepts, the system needed
to be evaluated in order to confirm its feasibility and to develop de-
sign and cost information.  A program was then developed and financed
by Edgewater to evaluate the RBC/Underflow Clarifier system with a pro-
totype unit.*

     The installation of the RBC/Underflow Clarifier system was com-
pleted in May 1973.  The process evaluation was conducted over a period
of three years by Edgewater personnel and results from these studies
indicated that the modification of the primary clarifier to the two-
tier treatment process could produce a secondary treatment effluent
commensurate with U.S. Environmental Protection Agency effluent re-
quirements.  Realizing its potential, Edgewater officials sought, and
received, a demonstration grant from the U.S. EPA to improve the exist-
ing facility and to continue the process evaluation under an intensive
testing program.

OBJECTIVES AND SCOPE OF STUDY

     Under the grant approved by the U.S. EPA, the primary objectives
of the RBC/Underflow Clarifier pilot evaluation were as follows:

     *Autotrol Corporation, Milwaukee, Wisconsin, claims the RBC/Under-
      flow Clarifier concept to be a patented system.

-------
                                SECTION  2

                               CONCLUSIONS
     A  one-year  experimental program was conducted at Edgewater, New
Jersey,  to  evaluate  the concept of upgrading existing primary waste-
water treatment  plants to  secondary treatment by the installation of
Rotating Bological Contactors  (RBC) in  the primary sedimentation tanks.
The  following  summarizes the results of the experimental program and
conclusions derived  from their analysis.

     The average wastewater characteristics during the one-year experi-
mental  program may be summarized as follows:

          F1<>w                     9920  m3/day (2.6 mgd)

          BOD5 Total                144  mg/1
               Soluble               80  mg/1

          COD  Total                350  mg/1
               Soluble              176  mg/1

          TSS                       169  mg/1

          TKN                        26  mg/1

          NH3-N                      13  mg/1

     The experimental program was conducted in three phases.  The first
phase evaluated the system over a series of loading conditions.   Based
on the results of the Phase 1,  an appropriate loading was selected for
evaluation under warm temperature (Phase 2) and cold temperature condi-
tions (Phase 3).  The following briefly summarizes the results from
these study periods.

-------
carry out the scope of work detailed in the grant.  Edgewater personnel
were responsible for providing labor for upgrading the plant, and the
daily operation and maintenance of the system during the experimental
program.

     Hydroscience, Inc. was responsible for the implementation and con-
duct of the experimental study, and the analysis and interpretation of
all data collected during the program.  Hydroscience personnel conduc-
ted the on-site analysis of samples, performed all field measurements,
and documented the results of all analyses and field measurements.

     Clinton Bogert Associates, as the Borough of Edgewater Engineers,
assisted Edgewater in the administration of the grant and conducted
facility evaluation, design, drafting and construction supervision as-
sociated with the modification and upgrading of the plant.  Addition-
ally, they conducted the economic analysis of the RBC/Underflow Clari-
fier process, based on the process design evaluation conducted by
Hydroscience.

-------
      Based  on the  overall  evaluation, the following observations are
 presented:

 1.    The  RBC/Underflow  Clarifier concept was demonstrated to be an
      effective secondary treatment process, capable of meeting NPDES
      secondary treatment effluent requirements of 30 mg/1 TBOD5 and
      TSS, or  85 percent TBOD5 and TSS removal, whichever provides
      the  greater degree of treatment.

      The  peak monthly loading at Edgewater controlled the process de-
      sign.  The influent peak monthly total BOD5 was 215 mg/1, with
      a corresponding soluble BOD5 equal to 130 mg/1.  In order to
      meet the 85 percent TBOD5 removal secondary treatment require-
      ment,  the limiting organic loadings for the RBC sector were deter-
      mined  to be 10.4 g TBOD5/d/m2 (2.1 lb/d/1000 ft2) and
      6.5  g  SBOD5/d/m2 (1.3 lb/d/1000 ft2).  The process de-
      sign curves project a total RBC media surface area requirement of
      246,000  m2 (2.65 x 106 ft2) for the Edgewater system.

 2.    Pretreatment  of the raw wastes was required throughout the study
      period to remove grit, trash, and floatables.  Effective pretreat-
      ment can be provided by high rate sedimentation, with average
      overflow rates between 285 and 370 m3/d/m2 (7,000 to 9,000
      gpd/ft2).  Average overall removals between 20 and 25 percent
      for TSS  and 10 to 15 percent for Total COD were achieved.  Minimal
      removals  of TBOD5 were noted.  Rough screening was necessary
      to remove  large fibrous material which passed through the high
      rate primary  treatment sector.

 3.    Tracer analyses were conducted and characterized the hydraulics
      through  the RBC/Underflow Clarifier system.  The results indicated
      that each  RBC stage, as defined by baffle placement, behaved as a
      completely mixed tank.  A time-variable analysis of completely
     mixed tanks in series adequately described the hydraulics in the
      system, and matched observed lithium tracer data.

     The combined turnaround and fourth shaft sectors, without a baffle
      separation, behaved as a completely mixed tank.   The mixing char-
     acteristics of the turnaround sector reduced the effective volume
     of the Clarifier by approximately 25 percent.  At Edgewater,  this
     was interpreted as a 25 percent reduction in the effective clari-
     fier surface area from 72.8 m2  (784 ft2) to 54.6 m2
      (588 ft2).

4.   The Edgewater system is a  combined  sanitary/stormwater  treatment
     facility, subject to significant variations related to  stormwater
     flow.  Diurnal flow variations  were approximately 1.5 to 1.0  max-
     imum to average and 0.5 to 1.0  minimum  to  average.   Studies to  es-
     timate diurnal variation in organic and  suspended solids concen-
     trations determined a  maximum to average ratio of 1.69  for Total
     COD and 2.0 for Total  suspended  solids.   The  diurnal variation  of
     pollutant concentrations was  found  to lag  the diurnal waste flow

-------
Low
Load
1,060
(0.3)
Phase 1
Moderate High
Load Load
1,440 2,520
(0.4) (0.7)
Phase 2
(Warm
Temp . )
1,550
(0.4)
Phase 3
(Cold
Temp . )
1,490
(0.4)
Flow m3/day
  (mgd)

Hydraulic Loading
  m3/d/m2         0.058     0.079     0.14      0.085     0.081
  (gpd/ft2)        (1.4)     (1.9)     (3.4)     (2.1)     (2.0)

Temperature, (OG)   13       17        23        26        11

Influent
  TBOD5 (mg/1)      90      155       144       130       154
  SBOD5 (mg/1)      54       96        77        87        79

TBOD5 Loading
  g/d/m2             5.3     11.7      19.7      11.4      12.9
  (Ibs/d/Kft )      (l.l)    (2.4)     (4.0)     (2.3)     (2.6)

SBOD5 Loading
  g/d/m2             2.8      7.7      10.4       8.3       7.4
  (Ibs/d/Kft )      (0.6)    (1.6)     (2.1)     (1.7)     (1.5)

Effluent
  TBOD5 (mg/1)      15       23        55        29        33
  SBOD5 (mg/1)      10       22        31        23        24

Effluent
  TSS (mg/1)        24       23        58        30        24

     A fixed film kinetic model developed by Hydroscience, Inc. and
specifically adapted to the RBC treatment process, was utilized in
evaluating the results of the program.  The model was verified with
interstage data collected regularly, and was demonstrated capable of
predicting system performance over a range of hydraulic and organic
loading conditions using a single set of kinetic coefficients.  The
match of observed data and model predictions indicated that hydraulic
and mass transfer components of the model responded correctly to system
variations.

     Design nomographs were developed using the RBC kinetic model.  The
curves represent single stage solutions dependent on influent dissolved
oxygen, soluble BOD5 and hydraulic loading.  Their iterative use
allows prediction of removal efficiencies in multi-stage systems.  As a
check, the curves were used to predict effluent quality under condi-
tions evaluated during the experiemental program.  The design curves
successfully predicted the average effluent soluble BOD5 observed
during each of the five operating conditions.

-------
      source,  resulting  in  the production of sulfide, which in turn is
      conducive  to growth of beggiatoa.

      The  recurring  appearances of  filamentous organisms did not appear
      to affect  the  treatment efficiency of the system at Edgewater.
      During one period, hydrogen peroxide was evaluated as a control
      mechanism.  At a dosage level of 40 mg/1 , the filamentous growth
      appearing  on all four stages was eliminated within a period of 48
      hours.

 9.    Underflow  baffles  effectively stage the RBC system into a series
      of completely mixed tanks.  Baffling also created higher veloci-
      ties along  the intermediate floor and minimized solids accumula-
      tion.  At  an initial baffle clearance of 15.2 cm (6 in), veloci-
      ties were  not sufficient to prevent considerable accumulations on
      the  floor.  Reduction of the baffle clearance to 5 cm (2 in) ef-
      fectively prevented further solids accumulation.

 10.   Inventories of influent and effluent solids and wasted solids were
      kept on  a continuing basis during the experimental program.  A
      linear correlation of total suspended solids wastage as a function
      of TBOD5 loading to the system was determined.  On the aver-
      age, biological solids growth was estimated to be 0.38 g
                 -                                 '          ฐ
          removed.
11.  A correlation of effluent TSS and underflow clarifier overflow
     rate was constructed on data collected over the entire program.
     The correlation implies an allowable overflow rate between 22 and
     26 m3/d/m2 (550 and 650 gpd/ft2) to obtain an effluent
     TSS less than 30 mg/1.  This correlation assumed an effective in-
     termediate floor surface area of 54.6 m2 (588 ft2).

12.  Chemical addition studies showed that ferric chloride addition to
     the fourth stage effluent would effectively improve solids settle-
     ability.

     A full-scale evaluation of ferric chloride at dosage levels be-
     tween 20 and 70 mg/1 was not successful when a rapid mix period
     was not provided prior to clarification.  Tests indicated that an
     initial rapid mix period must be provided to assure contact of the
     liquor with the coagulant.  Settling tests of a fourth stage mixed
     liquor sample, dosed with 20 mg/1 ferric chloride and rapidly
     mixed for five minutes, showed that effluent suspended solids
     levels between 15 and 20 mg/1 could be expected over an effective
     overflow range of 20 to 40 m3/d/m2  (490 to 980
     gpd/ft2).

13.  Cost analyses were conducted of alternative design sequences at
     Edgewater.   These costs are based on conditions at Edgewater,
     including 1977 loading estimates and removal rate coefficients
     determined  during the field program.  It is important to realize
     that costs  will be sensitive to these parameters.   Thus  higher

-------
     pattern, resulting in greater diurnal variations in waste loading
     than occurred with the flow.  The diurnal pattern of effluent con-
     centrations of measured pollutants (COD and TSS) was found to mir-
     ror the influent pattern.  A 24-hour oxygen profile of the fourth
     stage showed marked variation consistent with the waste load pat-
     tern imposed on the RBC system.

5.   The overall organic removal efficiency of the RBC system was limi-
     ted by oxygen availability as determined by the Kinetic model.
     Oxygen utilization curves developed from COD balances and the
     model indicated that the system reached a limiting condition in
     its ability to transfer oxygen at the higher influent organic
     loading rates.

6.   The overall seasonal effects were minimal based on the evaluation
     of the system under summer and winter conditions.  The temperature
     differential experienced was 15oc.  Although temperature af-
     fects several mechanisms involved in the kinetics of the fixed
     film process, the minimal overall impact experienced over this
     large temperature differential was due to compensating influences
     of the various parameters affected by temperature.  Higher removal
     rates and diffusivities experienced in the summer were offset by
     the low dissolved oxygen levels and the lower dissolved oxygen
     saturation value.  In the winter, the lower kinetic removal rates
     were compensated by high influent dissolved oxygen levels and a
     higher dissolved oxygen saturation value.  Since dissolved oxygen
     penetration into the biofilm was found to be the limiting factor
     in overall treatment efficiency, imposition of high dissolved oxy-
     gen concentrations and/or higher dissolved oxygen saturation
     values effectively increased the oxygen driving force, increasing
     the active film thickness, and resulting in greater substrate re-
     moval.

7.   Pre-aeration was investigated using the kinetic model.  Since the
     system at Edgewater is characterized by decreasing organic load
     with progressive staging, the provision of pre-aeration to the
     influent of the RBC/Underflow process would not have a significant
     impact on removal efficiency.

     Interstage aeration would achieve greater substrate removals.  At
     Edgewater, model simulation of interstage aeration, while allowing
     greater substrate removal, showed it would not significantly
     change the overall process design requirements.

8.   Filamentous organisms appeared intermittently during the warm tem-
     perature months (May through September).  The organisms were visu-
     ally identified as beggiatoa, which are white to clear filamentous
     bacteria, and form large white patches on the surface of the bio-
     film.  Beggiatoa metabolize sulfide to elemental sulfur.  Under
     low dissolved oxygen levels during the warm temperature period,
     sulfate may be utilized by the bacteria as an alternate oxygen

-------
                               SECTION 3

                            RECOMMENDATIONS
1.   Close attention must be given to the hydraulics of the RBC/Under-
     flow Clarifier system.  The staging should be adequately baffled
     to assure each stage is completely mixed.  The turnaround sector
     volume should be minimized since it adds little to the overall
     treatment effectiveness.

2.   Pretreatment should be provided to prevent trash,  grit and heavy
     solids material from reaching the RBC system.  This may be accom-
     plished by microstrainers, swirl separation, or high rate primary
     sedimentation sectors.

3.   Process design modifications should address the provision of chem-
     ical treatment or an alternate procedure to enhance solids cap-
     ture.  Alternative methods may include microscreens or rapid sand
     filters.  This would allow increased soluble BOD5  effluent re-
     quirements and an increase in the design loading to the RBC sys-
     tem.
                                 10

-------
removal rate coefficients would induce lower capital and operating
costs.

In the first alternative, one of the existing five primary sedi-
mentation tanks would be converted to a high rate pretreatment
tank, while the remaining four would be converted to the RBC/Un-
derflow Clarifier process.  New tankage (approximately equivalent
to the existing tankage) was then added to provide the require-
ment for additional surface area in both media and underflow
clarification to meet secondary effluent objectives.  The unit
cost for this upgrading procedure is estimated to be 0.077
$/m3 ($0.29/1,000 gal), considering both operation and main-
tenance and amortized capital costs.

An alternative considered was high rate pretreatment, standard RBC
tankage (no underflow clarifier), and utilization of the existing
primary tanks for secondary clarification.  The unit cost of this
scheme is estimated to be $0.061/m3 ($0.23/1,000 gal), which
is less than the above RBC/Underflow Clarifier.  Land requirements
(included in these costs), however, would be 50 percent higher.

-------
                                                BOROUGH
                                            CLIFFSIDE PARK
                         BOROUGH
                            OF
                       EDGEWATER
 INFLUENT SEWER

O
                     PROPERTY LINE


            SLUDGE DIGESTERS BUILDING
                                  CHLORINE BUILDING
                                               COMMINUTOR
                                                  PRIMARY
                                                  SETTLING
                                                  TANKS
SLUDGE
BUILDING
                                                SITE OF
                                                PILOT FACILITY
                   ADMINISTRATION
                   BUILDING
                                     INFLUENT
                                     SEWER
                        100
                           200
300 FT.
              Figure 1. Wastewater treatment plant site,


                             12

-------
                               SECTION 4

       DESCRIPTION OF EDGEWATER TREATMENT PLANT AND RBC FACILITY

 EDGEWATER WASTEWATER TREATMENT PLANT

     The Borough of Edgewater is in northeastern New Jersey, one kilo-
 meter  (0.6 miles) south of the George Washington Bridge on the western
 bank of the Hudson River, across from New York City.  The 11,000
 m3/day (3 mgd)  treatment plant provides primary treatment for the
 wastewater from within its own boundaries, as well as from most of the
 neighboring Borough of Cliffside Park.

     Figure 1 shows a plan of the existing plant site.  The major fa-
 cilities include an Administration Building, Pump House, comminutor,
 grit collector, five primary settling tanks, Chlorine Building and out-
 fall sewer.  Sludge is processed in two anaerobic sludge digesters and
 two vacuum filters.  A flash dryer is also available although not pre-
 sently used.  Land is limited, comprising only 0.6 ha (1.5 acres) of
 usable area.

     The average daily flow from Edgewater and Cliffside Park is ap-
 proximately 9,800 m3/day (2.6 mgd).  The sewer system is combined,
 which results in peak storm flows exceeding 27,000 m3/day (7.2
 mgd), the maximum flow capacity of the recording meter.  The industrial
 wastewater flow is estimated at 700 m3/day (0.18 mgd) or seven per-
 cent of the average flow.

     Table 1 presents average values of the raw wastewater for the one-
 year testing period, March 1977 through February 1978.

                   TABLE 1.  RAW SEWAGE COMPOSITION

                          Average            Range of values

 Flow, m3/day (mgd)     9,920 (2.6)       4,540-31,800 (1.2-8.4)
 BOD5 total, mg/1             144                   50-573
 BOD5 soluble, mg/1            80                   22-188
 COD total, mg/1              350                  128-772
 COD soluble, mg/1            176                   67-280
 TSS, mg/1                    169                   36-373
 TVSS, mg/1                   137                   44-206
TKN total, mg/1               26                   10- 41
TKN soluble, mg/1             22                    9- 31
NH3-N,  mg/1                   13                    3- 21
                                  11

-------




RBC
EFFLUENT-
FORMER
PRIMARY
TANK
NO. 5 — ^



r
UJ
1
— J
o
o

^
• 	
r—
UJ
\-
O
03
a:



i






X-v XA



^RBC

-> ฉXฎ
^



Shaft 1


— —

ฉ@

Shaft 2


IM*



ฉ ฉ
- - r - "Bl —


Shaft 3



ฉ ฉ
T^^\
)
Shaft 4
>ซ-ป^
ฉ


^~*.
>ฉ
ฉ


















^B —



UJ
>
ง
_j
o
GC
Z
o
o

o
_J
u.
1

^i
"T^T

U
I I





6
z

z
^i
h-

Q^
<
E
Q_

__r—
•c














a.
5
y?
.


(
j
TOTAL
PLANT
EFFLUENT
FLOW METER


k






rO
O
Z
Jb
z
^
h-
or
<
2
E
a.



• ^






CM
d
z
^^


h-
>
<

1
a.


i ^
ฉ
PLANT FLOW METER -^^


^^^









J) WASTEWATER QUALITY SAMPLING SITES






— .
d
z

^
z
1—

ct
^
2
or
a.


-PRIMARY EFFLUENT



















k jk NORTHSIDE
FLOW
^


,, SOUTHSIDE
^ ^ FLOW
1
l
DETRITOR^
(?) TRACER SAMPLING LOCATIONS
I	
 HIGH   FLOW
  BY-PASS
                     Figure 2. Plant flow schematic,
                                   14

-------
 DESCRIPTION OF RBC/UNDERFLOW  CLARIFIER TEST MODULE

      Primary Settling  Tank  No.  5 was  converted  to evaluate the RBC/
 Underflow clarifier  concept.  Raw wastewater, after passing  through the
 comminutor and grit  collector,  was  pumped  from  a point located 3.51 m
 (11.5 ft) from the influent side of Settling Tank No. 3.  The layout of
 the  plant and test module is  shown  on Figure 2.

      Figure 3 shows  a  cross-section of  the primary settling  tank before
 being converted.  The  effluent  channel  of  Tank  5 was modified to incor-
 porate an influent channel  and  a separate  treated effluent channel.  A
 flow meter was installed in the effluent channel.  The top of Tank No.
 5  was structurally modified and the RBC units were installed with the
 bearing blocks on top  of the  walls.   Covers were installed over the RBC
 units to protect the media  and  the  biomass from the weather.

      Figure 4 shows  a  cross-section of  Tank 5 after conversion.  The
 intermediate floor was installed to provide an underflow clarifier with
 a  water depth of 1.42  m (4  ft 8 in).   Four RBC units with diameters of
 3.61 m (12 ft)  were  installed in the  21.34 m (70 ft) long by 4.37 m (14
 ft 4 in)  wide tank with a water depth of 1.22 m (4 ft) above the inter-
 mediate floor.

      The RBC units are made of  high-density polyethlyene.  Stages one,
 two  and three each have a surface area  of  1,220 m2/m of shaft
 length (4,000 ft2/ft)  and stage four  has a surface area of 1,830
 m2/m (6,000 ft2/ft).   Each  of the four  shafts is 4.1 m (13 ft 5
 in)  long.   The unit  was immersed 1.07 m (3 ft 6 in) which provides a
 total effective wetted surface  area for the four shafts of 18,200
 m2 (196,500 ft2).  The small  portion  of the central surface
 free of microorganisms represents 17 percent of the total surface area.

      Employment of the RBC  unit involves both mechanical and biological
 processes.   As  the RBC unit rotates in  its designed position, the media
 are  passed  through the wastewater,  carrying a film of wastewater upward
 above the  surface.   The wastewater  contacts the biomass while trickling
 across  the  media.  Microorganisms normally found in wastewater will ad-
 here to the surface  of the media and grow, eventually covering the en-
 tire surface.   Organic material is  provided to the biomass as the media
 pass through  the wastewater, while  oxygenation is accomplished when the
 media pass  through the atmosphere.  This continual rotation provides
 the  necessary materials for the biological reactions which reduce the
 BOD  of  the  wastewater.  Meanwhile,  the  shearing action of the wastewa-
 ter  on  the  biomass strips some  of the growth from the media.   Sloughed
 biomass and  primary  solids are  swept along the intermediate floor to-
 ward  the hopper end  of the clarifier (see Figure 4) by the combined ro-
 tational effect of the discs and fluid velocity.  At the influent end
 of the  clarifier, some of the solids drop off the end of the  intermedi-
 ate  floor into the sludge hopper.   The biologically treated wastewater
 now  reverses direction and flows under the intermediate floor back to-
ward  the effluent end of the clarifier where it is discharged.   Addi-
 tional  solids settling out during  this clarification step are scraped
 into  the sludge hopper by the sludge collector mechanism.

                                  13

-------
LU
                       Z
                       O

                       h-
                       o
                       LJ
                       <
                       z
                       o
G
3

00
                                           •u
                                           0)
16

-------
                  I-
                  o
                  UJ
                  CO
                  o
                  ID
                  H

                  O

                  o
                  _J
                                      s
                                      VM
                                      O
                                      e
                                      o
00
6
                                      
-------
Pretreatment

     The configuration of the testing unit under the previous evalua-
tion work provided primary settling in Tank No. 4.  The overflow rate
was approximately 40'.7 m3/d/m2 (1,000 gpd/ft2) with grit,
trash and floatables being removed in this tank.  Total BOD5 and SS
removal averaged 37 and 61 percent, respectively.

     The test program, however, anticipated the removal of grit and
trash without removing substantial portions of BOD and SS.  Since the
plant detritor could be by-passed at times of high influent flows to
the plant, a modification was introduced to provide the intake to the
RBC pump at a point 3.51 m (11 ft 6 in) from the head of Settling Tank
No. 3.  As shown on Figure 2, the total flow passing through this por-
tion of the tank was the total effluent of Tank No. 3 and the pumped
flow which was divided to provide the RBC flow and the Tank No. 4 flow.

Controlled Pumping

     During the previous work there was no control of the influent to
the RBC unit.  Part of the effluent flow from Tank No. 4 was diverted
to the RBC unit.

     In order to control the influent to the RBC unit a pump was re-
quired as part of the installation.  The diurnal variation is presented
in Figure 5 with the peak to average ratio equal to 1.5 and the minimum
to average ratio equal to 0.5.  It was anticipated that a maximum test
flow of 5,680 m3/day (1.5 mgd) might be required.  A pump capable
of providing this large flow was installed.  A programmer providing a
variable signal to an electrically operated valve was installed, to
provide lower flows.

     The large pump capacity used in the tests made it necessary to in-
stall a by-pass feeding pipe to Tank No. 4, located ahead of the con-
trolling valve.  The by-pass rate was kept relatively constant through-
out the testing period.

Influent Channel

     An influent weir was built in the influent channel to the RBC to
distribute the flow uniformly.  Additionally, screens were attached to
this influent channel to catch large fibrous materials.

Other Improvements

     The intermediate floor and the influent channel were adequately
caulked to prevent leakage and/or exchange of effluent and incoming
wastewaters.  Additionally, a fourth stage baffle was installed in June
1977 to segregate the turnaround sector from the 4th stage of the
treatment sector.
                                  18

-------
    160

    150

    140

ฃ   130
O
^   120
UJ

1   M0
UJ
^   100
u.
0   90
I-
UJ   80
g
M   7n
Q.   70

    60

    50

    40
       12      3

   MIDNIGHT
9123

    NOON
9      12

   MIDNIGHT
          Figure 5. Hourly variation of wastewater flow.
                                17

-------
 SAMPLING

      Seven sampling  locations  were  utilized  to monitor water quality
 through the RBC system.   These are  shown on  Figure 2.  Daily, 24-hour
 flow-proportioned  composite  samples were drawn from  the raw influent,
 RBC influent,  and  the  final  effluent  from  the RBC/Underflow Clarifier.
 Discrete samplers, ISCO model  number  1680  with multiplexers, model num-
 ber 1295,  were positioned at the  RBC  influent and underflow clarifier
 effluent;  a single composite sampler,  ISCO model number 1580W, was
 maintained in  the  raw  influent waste  stream.  Each sampler was packed
 with ice during sampling  periods.

      Periodically  throughout each of  the study conditons, 24-hour flow-
 proportioned composite samples were drawn  from each  of the four stages
 in the  RBC system.   These samples were drawn from mid-depth with sub-
 mersible pumps,  and  composited in 18.9 1 (5 gal) jugs.  The sample jugs
 were kept  in 67.7  1  (20 gal) plastic  trash cans packed with ice and
 insulated.  All samplers  were  engaged by a signal from the effluent
 flow meter. Icing was omitted in the winter when ambient temperatures
 remained below freezing.

 ANALYTICAL PROGRAM

      Table 2 summarizes the  analytical schedule followed during the ma-
 jor phases of  the  experimental  program.  The numbers indicate the num-
 ber of  samples to  be analyzed  per week.  Thus, as an example, the raw
 influent total 5-day Biochemical  Oxygen Demand (6005) was analyzed
 seven times per  week, or  daily.   During each acclimation period the
 analysis was limited to monitoring  the RBC influent and RBC effluent
 for total  and  soluble BOD5 and  Chemical Oxygen Demand (COD),  and
 Total Suspended  Solids (TSS).   These data  were used to determine the
 extent  of  acclimation.

      Sludge  was  pumped at a constant rate  from the RBC clarifier sludge
 hoppers  two  to  three times daily.   Pumping time was measured  to deter-
 mine  the total volume of  sludge removed.   During each pump cycle,  a
 sample was  taken by continuously drawing off a side stream from the
 sludge  pump.   Composite sludge  samples were then constructed  by combin-
 ing  the  samples  in direct proportion to the pumping volume.   These com-
 posite  samples were used  for laboratory analysis,  as indicated  on Table
 2. .

     Analysis of Total Volatile Solids (TVS) and Total Volatile Sus-
 pended Solids  (TVSS)  was discontinued after June 30,  1977 since the
 data correlated well  with the Total Solids (TS)  and TSS results.   The
 frequency of analyses for the nitrogen series was  reduced following the
 summer, warm temperature loading condition.  Sulfate and total  sulfide
analyses were conducted only intermittently on the raw influent waste.
Ortho- phosphate and  total phosphate analyses were conducted  occasion-
ally, typically in conjunction with grease and oil analyses,  on the raw
influent, RBC influent, and RBC effluent samples.
                                  20

-------
                               SECTION 5

                  EXPERIMENTAL AND ANALYTICAL PROGRAM
Phase 1; Load Evaluations

     Phase 1 of the experimental program studied the RBC system per-
formance over a wide range of loading conditions.  The initial loading
was set relatively low to ensure an effluent quality greater than EPA
requirements.  EPA secondary treatment standards presently call for 85
percent BOD5 and TSS removal or monthly average BOD5 and SS
concentrations less than or equal to 30 mg/1.  Maximum weekly average
BOD5 and SS concentrations must be less than or equal to 45 mg/1.
The loading was then increased to yield an effluent quality approxi-
mately equivalent to EPA standards.  The third and final loading condi-
tion was chosen to stress the RBC system, i.e. violate the 30/30
BOD5/SS standards.

     Under actual operation, the low loading condition was run for ap-
proximately two weeks.  The moderate and high loading conditions were
each evaluated over an approximate period of five weeks.  Several days
were provided before each analysis period for the system to acclimate
to the change in loading.  Typically, this acclimation period extended
over one to two weeks.

Phase 2:  Steady State Operation Under Warm Temperature Conditions

     An optimum system loading rate was selected based on an analysis
of the data collected from Phase 1.  This selection was aided by use of
a computer simulation model of fixed film kinetics with particular ap-
plication to the RBC system.  The second phase of the program studied
long-term steady state operation of the RBC at the pre-selected optimum
loading rate applied during warm temperature conditions and low dis-
solved oxygen levels.  A two-week acclimation period was provided be-
fore this study period, which lasted two months.

Phase 3;  Steady State Operation Under Cold Temperature

     Phase 3 of the experimental program imposed the optimum loading on
the system during winter, cold temperature conditions for a period of
2-1/2 months.  The loading was maintained at or near that evaluated
during the summer months.
                                   19

-------
      Interstage  analyses were conducted approximately twice per week
 during  each of the major study phases.  Table 2 indicates the analyses
 conducted on  each of the stage samples.

      Dissolved oxygen  (DO) and temperature of sewage were measured
 daily on samples drawn at peak hydraulic conditions (10 to 11 AM).  A
 YSI Model 5IB with field probe was utilized.  Daily pH measurements
 were  made on  the 24-hour composite samples, using an Accumet Model 150
 pH Meter.

      All filtrations for separation of the soluble fraction were per-
 formed  immediately upon receipt of the samples.  Whatman No. 2 filter
 papers  were used throughout.  Whatman 4.25 cm GF/C pads were used in
 the gravimetric  analysis for suspended solids.  Analyses for COD, TSS,
 and TVSS were typically performed within 24 hours of receipt of sam-
 ples.   Samples for BOD5 were accumulated and set twice a week,
 typically on  Wednesdays and Fridays.  The filtrates and total samples
 were  preserved by freezing.  Special studies indicated that samples
 held  four days (frozen) did not exhibit any significant change in
 8005.   Four days was typically the maximum time a sample was held
 for BOD5 analysis.

      Samples  for the nitrogen series and sulfide analyses were pre-
 served  according to Standard MethodsU) and shipped via air freight
 to the  U.S. EPA  Waste  Identification and Analysis Section Laboratory,
 Cincinnati, Ohio, for analysis.  Grease and oil samples were preserved
 by acidification and shipped to the Hydroscience Westwood Laboratory
 for analysis.  The samples for phosphorus analysis were frozen and also
 analysed at the  Hydroscience Laboratory.  All other analyses were con-
 ducted  by Hydroscience personnel at the Edgewater Treatment Plant Lab-
 oratory.  Edgewater personnel were responsible for all sampling, and
 the maintenance  and operation tasks associated with the RBC system.
 Additionally, Edgewater personnel conducted flow, DO,  temperature, and
 pH measurements  as required by the schedule.

     Analysis for TS,  TVS,  TSS, TVSS, total Kjeldahl nitrogen (TKN),
 ammonia (NH3~N), nitrate (N03~N), nitrite (N02~N),  sulfate
 (SO^),  sulfide (S-), grease and oil and phosphorus  (P04-P) were
 conducted according to Standard Methods and/or U.S.  EPA recom-
mended^) procedures.

     The BOD5 analysis was performed by a modified  multiple dilu-
 tion procedure as described by Standard Methods.  Stale,  settled raw
 influent was used in all cases as seed.  A standard solution of 150
mg/1 each of Glutamic Acid  and Glucose was analyzed regularly as a
routine check on technique  and reagent quality.   The mean BOD5
measured for 21 samples (6  dilutions per sample) was 193  mg/1, with a
standard deviation of 19 mg/1.  This compares favorably with the re-
sults reported by Standard  Methods.

     The COD analyses were  performed using a modified  rapid  procedure
as developed by Jeris (3).   Split samples were analyzed by both the


                                  22

-------
                     TABLE 2.   ANALYTICAL SCHEDULE
                 (NUMBER OF SAMPLES ANALYZED PER WEEK)
              Raw
AnalysisW influent
Flow
Temperature
pH
DO
BOD5 (T)
BOD5 (S)
COD (T)
COD (S)
TS
TVS
TSS
TVSS
TKN (T)(2)
TKN (S)(2)
Recorded

7
7
7
5
5
5


7
7
3
3
N02~N(2)        3
N03-N(2)        3
so4
Total sulfide(2)
Grease/oils
  (T)(3)     biweekly
P04-P total(3)
POA-P T-ortho(3)
  RBC
influent
Stages
1,2,3&4
                                        7
                                        7

                                        2(D

                                        2(D
                2(D
                2(D

                2(D
                2(D
                2(D
  biweekly
 Periodically
 Periodically
  RBC
effluent

 Recorded
    7
    7
    7
    7
    5
    5
    5
               7
               7
               3
               3
               3
               3
               3
               1
               1

           biweekly
  RBC
 sludge

When drawn
                                                          When drawn
                                                          When drawn
     (1)  Only during interstage studies.
     (2)  Conducted at EPA Laboratories, Cincinnati, Ohio.
     (3)  Conducted at the Hydroscience Laboratory, Westwood, New
          Jersey.
     (4)  (T) = Total; (S) = Soluble, as defined by filtrate.
                                    21

-------
                                SECTION 6

               EXPERIMENTAL  RESULTS  - SUMMARY AND ANALYSIS
 INTRODUCTION
      A considerable  amount  of monitoring  data was obtained over  the
 one-year  experimental  period at  Edgewater.   Complete  tabulations of
 these data may  be  found  in  Appendix A.  Table A-l presents all routine
 monitoring data relating to flow, pH, DO, temperature, BOD5, TSS
 and  COD.  Table A-2  summarizes all nitrogen  series analyses, including
 interstage data.   Sulfur data are contained  in Table  A-3, and the
 grease and oil, and  phosphorus data are presented in  Tables A-4 and
 A-5,  respectively.   All  interstage data relating to BOD5, COD, SS
 and  DO are contained in  Table A-6.  For convenience and ease in  the
 presentation and analysis of the performance of the RBC/Underflow Clar-
 ifier system, the  data are  presented in terms of summary tables and
 chronological records within the text of  this report.

       The system was evaluated in five periods, including a series of
 three loading conditions and under summer and winter  operation at a
 prescribed optimum loading  rate.  Table 3 presents a  summary of the
 performance and operation of the system during each of these periods.

 HYDRAULIC CHARACTERIZATION  OF THE RBC SYSTEM

 Pretreatment

      To preclude the accumulation of debris in the RBC system and clog-
 ging  of the openings within the media, sufficient treatment of the
 waste  to remove  solids must be provided prior to the  RBC system.  At
 Edgewater, the  entire plant flow passes through a detritor.  Additional
 pretreatment provided for the RBC system influent consisted of a high
 rate  gravity settling zone  followed with coarse screening.  The intake
 for the influent pump to the RBC system was a 0.203 m (8.0 inch)  diam-
 eter  pipe.  Early in the study period, the intake pipe faced the di-
 rection of flow 1.52 m (5.0 ft) from the raw influent channel,  and 0.76
m (2.5 ft) below the water surface.  The intake in this position was
 too close to the influent channel and was drawing solids from the
 sludge hopper located directly below the channel.  The resulting  water
quality was not suitable for application to the RBC system.   Heavy
solids were accumulating on the media surface,  a condition which cannot
be tolerated over an extended period of time.
                                  24

-------
rapid method and the Standard Methods reflux procedure.  The results
indicated no significant difference between the two procedures relative
to the Edgewater waste samples.  A standard solution of 0.850 mg/1 po-
tassium hydrogen phthalate, with an equivalent COD of 1,000 mg/1, was
analyzed frequently as a control of procedure and reagent quality.  For
a total of 108 standards analyzed by the modified rapid procedure, a
mean of 1,003 mg/1 COD was obtained, with a standard deviation of 6.6
percent.

     In addition to the water quality analyses as outlined in Table 2,
studies were conducted periodically to characterize the physical and
hydraulic operation of the system.  These included tracer analyses,
zone and flocculant settling tests, diurnal loading studies, and chemi-
cal addition tests.

     During each flow condition, or major modification to the physical
system, a tracer analysis was conducted to characterize the hydraulics
through the RBC system and to monitor the system for any physical ab-
normality such as leakage, etc.  Lithium chloride was evenly distribu-
ted across the RBC influent channel and samples taken with time at se-
lected sampling locations (see Figure 2).  The samples were then trans-
ported to the Hydroscience Westwood Laboratory for analysis of lithium
by standard atomic absorption spectrophotometer procedures.

     Flocculant settling tests were conducted using 2.13 m (7 ft) high,
15.24 cm (6 in) diameter columns with sampling ports at 0.305 m  (1 ft)
intervals.  Sample (typically from the fourth stage) was pumped  into
the column and aliquots drawn at each port at regular  time intervals.
Standard jar test procedures were employed to evaluate the effects and
feasibility of chemical addition to improve solids capture in the RBC/
Underflow Clarifier.

     Diurnal analyses were conducted to determine  COD and SS concentra-
tion and loading variability over a 24-hour period.  Discrete samplers
were utilized, and a series of samples, representing specific incre-
ments of waste volume to the RBC system, were analyzed for COD and SS.
                                    23

-------
 0) CM
 O, I
 a -ซ
 V ~-ป
 4J CM
                                                                                                       -HOO— <    -* eo -H co  -ซ o
          vo in o* eo vo —<
          CM >-' -* ^    ป^
                                    ซ* eo -ป O    CM
                                    CO CO CM O    00
                                    —I —i    eo
                                                                                   O m
                                                                                   CM -H
    TJ ^
    O in
    •H CM
 S 00
 01 ~i
                    •* r-ป  ro
                 oo •* O  O
             m  ปo eo in •-ซ
                                                                                                                          •^  O -< CO
                                 CO _
                                 \e CM  eo
                                 \o CM  eo o
                                 -H -H     WD

                                           <*"
    TJ r-ป
    O --.
    •H O
    t- CO
 a.v
T3 CO
 (0 CM
 O ^
              O CO -*  ซป >C -*     f-ป 00
              ซป N-X CM  ^    ^     r-ป CM
                                                                                         -H.^fO'^CO-^-H     —( CO  -H O -H vO
                                               O    in
                                               o    m
                                               CO
                                                                                  aซmo
                                                                                  -H-HV
    i-( CO
 0)  I* ^^
 *J  4) ^
 <0  A.u-1
 t-      I
 0>  00 r-
•O  C r^
    V.  vฃ>


 >  *••?
 O  O0r~.
,J  C  P^
   •H  •—.
   "O  CM
    ซ0  CM
    O  ^
          CO CO O O  -H CM
\O CM  eo O     —•
r^cMCMg     co
                                                              oococoooincoco-^OinincMOO
                                                              CMCM-nVVcMCM-H        —i  _, ^  V V
                                                                                                                       O O  O vO O  >O
                                                                                                                       v o\  v oo v  r-ป
                                                              CM CM  CM CM CM
         CM  CM ON i-H  CO O
                                    -a- >ป o
                                    CM CM O
                                    -^    >ป
                                                                                                                          CO CO CO CO

                                                                                                                          -H O —I O
         2ง
                   TJ ^^

                   To 4J
                      1*4
                    01
                   ซJ O
                    (0 O
                        .
                       OOCM
                          4J
                       C 
-------












3s

rT
Oi
w
Q
U

.
w
H
1
H
w
1

H
Q
O
Z
M
M W
Z H
O CO
OT
(L,
o a:
w
>-. ft



CO

a
CQ
^4
H












00
f-V
•O ^
O >fr
•H CN

^3 4) CN
•H 0-
cS ^E
B ^
4J CM
f 1
^
fx.
O m
B ซ3 ON"
j_ O.
cd rx,

Ou "^*
B oo
CD -i
4J 	

"O P-
O ~--
•H 0
r- CO
8."""
00 1
33 C rx
T3 CO
cd CM
O --x
1—4 iO


T3 rซ.
O -x
•H ro
4) ^ '•H
4J Of ->x
cd & m
t- I
v oorx
TJ C rx
S T3 -H
cd f <
o ~x
ft xt

O fx
•H ^x.
$ x^.
CL xT
2 I
i-J C PX
•H ~^
•O CM
C8 CM
o -^









Q
Ol
4J
0)
cd
P.
cd
cm
^> CM
CO CM —I
O CO CO O O O
mcoooooo OCM ^ONOO^CO-*
CO -^ rH PH
fT f"


/-N CO
'"^ ON CM in '•^
m o o oo oo
CM -* r>ป O O O
mcMOOooo OCM OP^-*P^ONCO
m m fi -H
M M
00 -H



/<~V
s~* in co ^~^
•-H vD vO O -* 00
CM vO CO O -H CO
OCMOO-HO Oco ^•p^comm'-H
co m fi ^
00 CN




^ ^
r-s — l — ( ON ^-^
ON ON ON CO P^ -^
CO CO f< O O ON
OCMOOP^O o-< mvooooococM
O >^ *ป v-' ^-^ x-'. in ON ^ ON CM CM
O st -* -H
#. ซ.
ON -H




^
^•X ป-4 00 •*""*•
'•^ oo vo o m CM
ซป CM O O O -ป
OcOOOvCO O-H O-*CMOOinO
r-ปv^vฃ>^^ v^ ^^ oNinoN-*- Ol 0)
fl ป 0 ^N 3 3 3
*ป-l OrH OCM .H^rH
fl <4-l -HCM 4J 14-I 14-I U-l
CO 4J 00 CO T5 -O 00
ft B T3 U-~x,CX >BCJ CJ
(x a 3 T>co oo cd pa PQ
flrH SsS^ odpeJoe!
rH (X O) f.
ซo m
4J O O CJ Q
o oa PQ pa o
H 06 t6 06 CO

^^ S~** s**\ /"•S
rn CN ^~^ ^^ GO vD CN
CTs CNCNl^-HOOCNCOvฃ)OCNin-l
r^ .-H rn




-*™N >^V X"N /"N
CO sO CJ\ '•N x^* i/1^ ^ oo 00
oo -H CM oo f! fi o tv. r-. oo -i vo ^,
^x






^ ^ /-N
^f CO ^"^ s**- *~^ vO \O
m r^o-*-H-H ^^ px t-n in
^ mficMooN^rocM-a-ocMco
00 NM^ ^-'X *— * ^^ f< Nw^ >^^ SM^






CM CM CM
4-1 4J 4-1
4-1
C O O O
0>CM CMOCMOCMOCM CM
SB BOBOBOB B
0) OOCM tX)~~x 00^^ OO — 00 ^ 00 /-N
4J CO CO CO CM CM
O Ol<4-l 0) ฃ> 9) ft Q) ft o>4J 0) 4-1
/-X4J4-I 4-li-(4Jr-t4-lr-l4-)l4-l4J14-l

v_x 4J U O U ^s 1- x-N P./-S UO Pซ O
C O Ol Ol 01 O O
f) O> 00— i 0000 0000 OOOOflO flO
CO 3 C ^x,. c cd C cd C CO cd fi cd *-H
B C cd co cd co cd 8*^ Bฐ^~>
OI-H O -Q O 4J O 4-1 O 4-> OIU) Ol CO
PC! rHrHrHtJUiHCOrHa) U ^ kซ^
O V^ ^ ,H -H ft ft
Q Od Q Q O Q a Q
O^O O O O O O
PQ PQ PQ PQ PQ PQ PQ
H H CO H CO H CO



O 00 CO CO ON px
tx, xfr CM 00 OO Px
CO -H CO ft






•-^ in ^o PX oo ON
CO CM CO CM f<









px m o oo \o m
CO —1 CM "H -H









CO -H ON CM 00 CM
CM oo \o oo px rx
CO ~H CM ~H








in CM NO ON OH \G
xt o ^H o m xt
CM -H CM fi










H CO H co H CO
4-1 4J 4J
ccc
01 01 Q)
333
fl ft ft
M-l *4-l 14H
C <~N C ซ4-l
•H ft M W
ป opu u
co B pa n

ง
0
25

-------
     The pipe was repositioned against the direction of flow from the
primary settling tank, 3.51 m (11.5 ft) from the raw influent channel.
The resulting settling area was sufficient to provide adequate grit and
trash removal while allowing most primary solids to enter the system.
With the intake positioned well below the water surface, intake of
floatables (grease and oils) was minimized.

     Figure 6 presents the approximate overflow rate in the high rate
primary sedimentation section as a function of both plant flow and flow
directed to the RBC system.  The total flow passing thru this portion
of the tank is the sum of the Tank 3 effluent (see Figure 2) and the
pumped flow.  The pumped flow is split between Tank 4 and the RBC sys-
tem.  Thus the computed overflow rate is dependent upon both the total
plant flow and the RBC flow.  The nominal surface area used in the com-
putation assumes use of the entire area to the point of intake, i.e.
4.27 m (14.0 ft) wide by 3.51 m (11.5 ft) long, or 15 m2 (160
ft2).  This is conservative, since the effective surface may be
considerably smaller due to the constricted influent to the tank and
the constructed intake.  The shaded area on the figure presents the
normal operating range for the RBC unit, indicating high rate primary
treatment overflow rates between 285 and 370 m3/day/m2 (7,000
and 9,000 gpd/ft2).

RBC/Underflow Clarifier

     Seven tracer studies were conducted and analyzed during the exper-
imental program.  Lithium was batch loaded into the RBC influent chan-
nel and sampled at selected points through the system.  The data analy-
sis was directed to defining effective detention times in key portions
of the system and to monitor the system for any apparent occurrence of
short-circuiting or other physical anomalies such as leakage.  The in-
itial study, conducted November 2 through 5, 1976, determined that
there was significant leakage through the intermediate floor, and poor
distribution at the influent channel.  These problems were corrected as
part of the plant modifications program conducted December 1976 through
February 1977, as described in Section 4.  The tracer studies conducted
during March through October 1977 showed no recurrence of these prob-
lems.

     Subsequent tracer studies conducted on the Edgewater RBC/Underflow
Clarifier system were under the following operating modes:

     March 2:  Q = 2000 m3/d (0.525 mgd), baffles between shafts 2
               and 3, and 3 and 4-.

     March 25: Q = 1200 m3/d (0.32 mgd), baffles between shafts 1
               and 2, 2 and 3, and 3 and 4.

     May 24:   Q = 3000 m3/d (0.8 mgd), baffles between shafts 1
               and 2, 2 and 3, and 3 and 4.
                                  28

-------
3  8,7
3  .ฃ
    S-~
    4J CM
 s  ai;
5   •!
    8 oo
    oi -ซ
    o -^
   •H O
    i- m
 oo    i
•H  oor-
ae  c  r-
    •H  -^
    •O  ro
    CO  CM
    O  ^
    O *-
    •H m
 0)  U -H



 01  OCr-ป
•O  C r-
    TJ  CM
    CO  -^
                                                    •3o
                                                     o r*
                                                    M CM
                                                     CO   •
                                                     U 00

                                                     ซ
                                                     4J >4-l
                                                     CO  O

                                                        CO
                                                    •H  0ป
                                                    •H  I-
                                                    <  CO
                       01
                       00    00  01
                       X     •  U
                       ^H    ^^  6
                       CO  •     4
                           SCO 4J iH
                          •H CO  ซ
                           00    .O
                           SX at
                          r-t -H  CM
                       4J  
-------
     June  23:  Q  = 3000 m3/d  (0.8 mgd), baffles between shafts 2
               and 3, 3 and 4, and after shaft 4.

     Oct.  3:   Q  = 1900 m3/d  (0.50 mgd), baffles between shafts 1
               and 2, 2 and 3, 3 and 4 and after shaft 4.

     A  seventh tracer study was conducted on July 14 to determine if
back dispersion from the turnaround to the fourth stage was occurring,
and to  confirm the absence of leakage through the intermediate floor.
For this particular study the lithium was loaded in the turnaround sec-
tor.  The  analysis indicated no back dispersion and lithium was not de-
tected  in  any stage, confirming no exchange of wastewater through the
intermediate floor from the underflow clarifier to the RBC sector.

     Figure 7 presents the lithium tracer results from the March 2,
1977 run.  In the analysis of the data, a non-steady-state model was
applied, based on completely mixed tanks in series.  The model used was
a modification of the steady-state model described in Appendix B.  Non-
steady  conditions were imposed in this case and the influent substrate
constituent was assumed conservative.  The solution includes the diffu-
sivity  of  lithium into (and from) the biofilm.  Initially the higher
concentration of lithium is in the liquor and there is diffusion into
the biofilm.  With time, the lithium washes out of the system and the
lithium in the biofilm begins to diffuse back into the liquor.  The
overall effect is to cause a tailout of the tracer and affect an ap-
parently longer liquid detention time than would actually occur under
steady-state conditions.  The result of this solution is superimposed
on the March 2 survey data (Figure 7).  Without a baffle after the
fourth shaft, the fourth stage and the turnaround sector (see Figure 4)
behaved as a single completely mixed tank.   This single run is provided
within the context of this report as an example; the solution was de-
termined to be applicable to the spectrum of conditions evaluated
during the study.

     The nominal volumes for all stages and zones are computed directly
from the tank dimensions.   These are summarized on Table 4.   The actual
volumes shown on Table 4 are computed by approximating the displacement
of the media and biofilm.   A film thickness of 0.23 cm was assumed for
use in these calculations,  with a media thickness of 0.15 cm.  The ac-
tual volumes were used in all subsequent calculations.  The  effective
volumes of the turnaround and clarifier sectors are different than the
actual volumes reported in Table 4.
                                  30

-------
24,000
20,000
LU
K    I6pOO

cr
  04
^  <*-

3  ^ 12,000
U.  Q.
fy  o>
UJ
 8,000
 4,000
1,000



 900


 800


 700


 600
      U  o  500
         TJ
 400


 300


 200


 100
    O1—
                              V
                                      NORMAL OPERATING
                                        RANGE
                       8,000      16,000    24,000
                                mVday
                                            I
                                         32,000
0
2.0 4.0 6.0
mgd
FLOW
8.51
           Figure  6.   Hydraulic character of
             high-rate pretreatment  sector
                         29

-------
    TABLE 4.  RBC/UNDERFLOW CLARIFIER - NOMINAL AND ACTUAL VOLUMES

                Nominal volume             Actual volume
                m3(gallons)           m3(gallons)

Stage 1         21.9   (5,800)             18.2   (4,800)
      2         23.5   (6,200)             19.7   (5,200)
      3         23.5   (6,200)             19.7   (5,200)
      4         19.3   (5,100)             13.6   (3,600)
Turnaround      55.6  (14,700)             55.6  (14,700)
Clarifier      100.0  (26,400)            100.0  (26,400)

Total          243.8  (64,400)            226.7  (59,900)


     The apparent discrepancy in peak heights between predicted and
observed data in Stages 2 and 3 on Figure 7 suggests the occurrence of
short-circuiting.  This was known to occur along the floor due to the
higher velocities created at the baffles and at the bottom of the
discs.  The lithium studies measured lithium concentrations in the
later stages sooner than should have occurred if there was no short-
circuiting.  An estimate of the degree of short-circuiting was made by
comparing the areas under the observed and predicted tracer curves
shown on Figure 7.  In Stage 2, the mass passed after 25 minutes was 10
percent greater than predicted for completely mixed tanks in series.  A
similar analysis for Stage 3 (plus turnaround) showed the mass passed
after 50 minutes was 11 percent higher than predicted.

     An important observation derived from the series of tracer analy-
ses was the ineffective use of the turnaround sector and the reduced
effective volume of the underflow clarifier sector.  Table 5 summarizes
the tracer results as given by measured detention times in each of the
five tracer studies.  The observed detention times, tm, are pre-
sented and compared to the expected detention times, to, computed
as volume divided by flow.  A comparison of observed and expected de-
tention times through the secondary clarifier revealed that, on aver-
age, the observed detention time was 75 percent of the expected time
when based on the actual volume of 100 m3 (26,400 gal).  This was
attributed to the fact that considerable mixing occurred in the turna-
round sector, effectively decreasing the quiescent volume available for
secondary clarification.  Thus, the effective clarifier volume was de-
termined to be 75 percent of the nominal volume.  The remainder was
added to the turnaround sector volume.  Table 5 shows good agreement
between observed and expected detention times when based on the adjust-
ed effective turnaround and clarifier volumes.  These effective volumes
where used in the non-steady state solution shown on Figure 7.

     The results shown for the October 3 survey are somewhat anomalous
relative to the previous studies, whereby the measured detention time
in the Stage 4 and turnaround sectors are lower than the expected de-
tention time.  No conclusive reasons are evident.  Recovery during the
                                  32

-------
0ป
 1.2

 I.I

 1.0

0.9

0.8

0.7
 r  0.6
    0.5

    0.4

    0.3

    0.2

    O.I

     0
                STAGE  1 & 2
       i>- ACTUAL VOLUME = 37.9m3
                         (lOOOOgal.).
                      C: = 1.37 mg/l
             50      100     150
               TIME (minutes)
                                 200
 1.2

 I.I

 1.0

 0.9

0.8

0.7

0.6

0.5

0.4

0.3

0.2

 0.

  0
         STAGE  2
ACTUAL VOLUME= 19.7m3
                (5200 gal.)

             MARCH 2, 1977
             0 = 2000m3/day
                 (0.525 mgd)
             Li  input = 52 gm.
    50      100      150
     TIME (minutes)
                                                                                  200
u.y
0.8
0.7
__
^ 0.6
oป
ฃ 0.5
5*
Z) 0.4
X
t 0.3
_J
0.2
O.I
0
C
STAGE 3
-EFFECTIVE VOLUME^ 93.5 m3
(24700 gal.)
(INCLUDES TURNAROUND)
—
—
_
—
0ฎ 	
/ 1 1 1 1 1 1 1
) 50 100 150 2C

0.8
0.7

0.6
0.5
0.4
0.3
0.2
O.I
0
)0 C
CLARIFIER
-EFFECTIVE VOLUME= 75.7m3
( 20000 galj

—
-
_
-
- x^n^-^^
^^ 1 1 1 1 1 1
) 50 100 150 20
Legend:
TIME (minutes) e -observed TIME (minutes)
— — -predicted
           Figure 7.  Results of  March 2nd hydraulic tracer analysis
                                         31

-------
 study was  poor  (70 percent).   It is suggested that the lower flow rate
 (1,890 m3/d vs. 2,975 m3/d during the June 23 survey, conducted
 under a  similar operation mode) may have effectively created a dead
 zone  in  the turnaround sector.  The lower velocities would have caused
 less  mixing and a more direct  routing to the underflow clarifier zone.

      In  summary, the following observations were made from the tracer
 analyses conducted during the  experimental program:

      (1)  Each stage in the RBC sector with either one or two shafts,
           as defined by baffle placement, behaves closely as a com-
           pletely mixed tank.

      (2)  The combined turnaround and fourth shaft sectors, without the
           baffle separation, behave as a completely mixed tank.

      (3)  Short-circuiting is apparent in the RBC sector, probably due
           to the higher velocities created at the baffles along the
           intermediate floor.  It is felt that the degree to which it
           occurs is minor.  Removal and kinetic coefficients determined
           in this study would, of course, reflect any short-circuiting
           which may occur through the system.

      (4)  The effective volume of the clarifier was estimated to be 75
           percent of the actual volume, the remainder of which is part
           of the completely mixed turnaround sector.

 WASTE CHARACTERIZATION

 Raw Wastewater

      The Edgewater sewerage system is a combined sanitary/stormwater
 collection system.  Wastewaters received are predominantly domestic
 with  approximately a 7 percent input from industrial sources.  As a
 combined system, periods of rain result in a dilution of the waste
 strength to the system.  Table 6 summarizes the monthly waste charac-
 terization for both the plant raw influent and the RBC influent.  The
 plant raw  influent is representative of samples drawn from the influent
 channel  to the primary tanks, subsequent to the detritor.  The RBC in-
 fluent samples were drawn from the distribution channel prior to shaft
 one.

     Weekly average plant raw influent waste characteristics are chron-
 ologically displayed on Figure 8.   Included on the figure are the pre-
 cipitation record and the flow to the RBC unit.  Periods of rain reduce
 the waste  strength considerably, as evidenced during generally wet and
 dry seasons and with occasional storms.  Since the flow to the RBC was
maintained at a fixed daily average flow and diurnal pattern, the storm
 periods  with high dilutions and flows were experienced by the RBC only
at lower waste loading periods.  Conversely, during periods with low
                                  34

-------




















CO
M
3
i
w

J5
,_J
a
M
i— i
fn
M
a
jj
u

w

M
H

W

fc
w

m*
PQ

H

































0)

•H
4-1
O

MH"
<4H
W















•H
CO
4-1
O












>M
CU
•H
II i
*+H
•H
j^
CO
T3
C
3
O
j_,
CO

>H
3
H


O ON I-H
m ซ^ co
r— • m m




vO
•
CO *^ *^
oo cu a)
C 00 ON C
•H • • -H
•O r*^ r— t&
0 so r*^ 0
0 0


4-1
CO
CO
CU
•H
C|_j
•H
>-,
CO

C
3
0
V.
CO

j_
3
H
o o
CO
ON
•— i


O 
,J 0
O
6>? CU


sO CM
O ON
i— H


>•>
>. CO
co -a
*O ^— .
CO -^ CO
0 CO 0
0
CO * O
e cu ^ o -H
ง1— t ON CM
v_x 0>i f-H
0) iH ^H
0 O >•ป II
3 > T) II
.H P 0*
O CU 4J O*
> > CO •*
•H ••> o 0 r-
iH 4-> IH r- 4-1 4-1 r-.
co o  <4H CO CM CM
O <4H IH ^*. "•ป.
<3 W H co co


O
o









o
•
,__)
,_(
^-|






O
•
ON
i-H
^






^~
•
CM
00































O
4->







m
CO
00








o
•
00
CM
i— I





^
in 6s?
• o
co r-
00 v_x







0
•
00
CM
<— i






























0
4-1







O ••"• sO CO sO vO
• • • • • •
vo co so so r^ in
co co co co m so




r- •<*• oo oo
• • • •
'C 00 <— i O ON
CU CO CO sO CM
C m ON
•H • •
rO ซ^- i— 1
0 -ป' r^ป so ^~^




ON -tf
• • co oo
'O SO "— H • •
CU CM CO CM ON
C ON O -3" CM
•H • •
43 CM -H
0 CO ซtf
O
CJ
so r*>ป -^ co
• • • •
sO r— CO sO
i-H i-H



CO CO O
oo oo r-



>•, >N >N
CO cO cO
*O *O *Q
"***. "**• • "^>-
CO CO CO
060

o m o
co r— ON
O ON 00
CO CM -H

II II II

o* cx o-

• M •*> ซซS
P— O 0 P>> O 0 F^ O 0
r-. 4-> 4_) r-. 4-> 4-i r-4->4->
*— ^ ^"— '**—
<ฑ CO CO
CM CM ^
-^ ^x. O
m so ซ-H




























•
0)
i ^

C
•H
0
"*^

CU
0
•H
4J

C
o
•H
4J
d
4J
0)
"S
v_
cu
w
,0
o
II

0
4-)

• *
cy
"—ป,
^

it

o
4J


.<~\
-H
'^^





33

-------
2
O

I-
<
O
liJ
or
a.
O
_l
^ -D
K oป
2 E
U_ en
o 6
m
or

 in
Q
O
GO

< \
o: o>
_i E
O
o

<
CO
CO  —
<  E
(T
   4


   3


   2


   I


   0
   4


   3


   2


   I

   0
 0.8

 0.6


 0.4


 0.2


 0.0
300


200


100


  0
500


400


300


200


100


  0
300


200


100
                               III  ,1  ,  Ul, I   ,  Jl
                                                                  PRECIPITATION
                                                                  TOTAL PLANT
                                                                     FLOW
            I  I  I  I  I  I  I  I  I  I  I
                                                                      RBC FLOW
            I  I  I 1   I  I  I  I  I i  i  |
                                       I  I  I  I  I  I  I  I  I  I
                                                             I  I  I  I  i  i  i  i  i
            ป  I  ป  I  I  I  I  t  I  I  I  I  I  I  i  I  I I   I I  I  I  I  I  I  I  I  I  I  I  I  i  i  i
                                            Jl
                                                                     RAW TCOD
                       -,   Jl
            I  M  I  I  ป  I  I  I  I  ป  ปป  ป I  i  I  I  ซ  I  i  i  ป  i  I  t  I  I  I  I  I  i  i  i
                                                                      RAW TSS
          0   20  40  60  80  100  120  140  160  180 200 220 240 260 280 300 320  340
           MAR.
                APR.
                MAY
JUN.
JUL.
AUG.
SEP
OCT.
                                                           NOV.
                                                                DEC.
                                                               JAN.
                                                FB
      Figure 8.   Chronological record of  raw wastewater characterization
                                     36

-------


>;
ง
CO
z
o
I-H
H
M
W
H
CJ
3

p3
CJ
04
w
H 00
3: ON
W — '
H
CO >-<

Z PQ
W W
fa O
Z H
M
Z ON
,j
PM PC
O
S3
2
Q 1


H pd
U
H W
Z O
O Q
2 W

ป
vO

W
PQ
H












4J
C
 oq m
H S| CM
m
Q i"H 1
PQ OOl vD
co ij


m
PQ ซJ O
H
oo
CO
13 1 ^o
o
.H
0 0
-> 00
CM
S -H

>— 1 1
CO' — 1 ON
CO 6d vO


QrHl
o^"*-! co
o ool NO
H 0| CM

m
Q .Hi
O "•ป. m
PQ od o
Hf* \ 	 .
P I ^^

/^N ON
T3 O
B CO
^
O
fa in
T3 ON
*•>. ^D
i— i
Bl


r-ป o
rป VH
2 S
oo
•— i

vO


CO
CM


O
ON




m
CO

m

CO


o
CM
i— I


,3-
^O



00
ON
CM



vO
CO
^H

^
CM


m
o

o
i— i


iH
•H
^,
CX
O
CM
O



i— i
CM


CO




CM

i-H
ON



00
m
00
r— 1


m




00
CO
CO



vO

*"H

CM
CM


^
f^
^
00




^>
2
o


r^


oo
CM


oo




m

.—i
ON



m
1— 1
CM


oo
f^



oo
CO
CO



,^
**


CM
CM


^j.
m
m
oo



0)
c
P
m
CM

00


i— 1
CM


oo
00




00
CO

p^
00



CO
00
.—1


CO
00



o
CO
co



CM

^

ON
O
CM


O
i— i
ON
f^.




,_{
^
00
i-H

ON


CM
O
CO


i-H




CM

^
ON
CO


0
00
^H


0
oo



CO
m
CO



m
CM


m
CM
CM


vO
i-H
m
00



CO
60
P
r^
i— i
CO
CM
rvl
t >4

 o t*ป
O 
CM CO


ON CM
oo o
--H



ON -H
CO ON
i-H ซ-H
X^X /^N
-H O
r- CM
co ปซx \~s


— i m
CO ON
-a- CM
-H O
~* i-H

>,
1 8
C ,0
CO CU
35

-------
                                          AV6. RAW INF= 41.0 Kg/hr (90.3 Ibs/hr,
                                          AVG. RBC INF= 33.6 Kg/hr (74.0 Ibs/hr)
                                          AVG. RBCEFF=I6.I Kg/hr (35.4 Ibs/hr)
                                         AVG. RAW INF= 30.9 Kg/hr (68.1 Ibs/hr)
                                         AVG. R3C INF= 18.2 Kg/hr (40 I Ibs/hr)
                                         AVG. RBC EFF= 8.2 Kg/hr (I a I Ibs/hr)
                                                      FLOW

                                            AVG. RBC 0 = 2710 m3/d (0.7lmgd)
                                 TIME OF DAY
Figure 9.  Diurnal variations  of TCOD,  TSS,and RBC  flow
                              38

-------
plant flows and resulting higher-strength wastes,  the RBC system re-
ceived an increased waste load.

Diurnal Variations

     Diurnal sampling was conducted twice on the raw influent,  RBC in-
fluent, and RBC effluent waste streams to characterize the variations
occur ing over a 24-hour period.  Throughout the experimental program
the RBC flow was controlled at a fixed diurnal pattern, as shown on
Figure 5.  The expected peak-to-average and minimum-to-average  flow
ratios were 1.5 to 1.0 and 0.5 to 1.0, respectively.  These flow ratios
are consistent with the diurnal flow variations generally experienced
at the Edgewater STP.  The maximum-to-average and minimum-to-average
flow ratios actually realized during the June and October diurnal
samplings were as follows:
                                         June 8-9      October 5-6

          Maxim urn/Average Ratio            1.53           1.63
          Minimum/Average Ratio            0.42           0.44

     The average RBC flows for the June and October diurnal studies
were 2,710 m3/d (0.71 mgd) and 1,360 m3/d (0.36 mgd), respec-
tively.

     The diurnal variations of pollutant concentrations tended to lag
the diurnal waste flow pattern, thereby resulting in greater diurnal
variations in waste loading than occur with the flow.

     Figure 9 displays the results of the June 8-9, 1977 diurnal sam-
pling, presenting the variations in flow, COD, and TSS.  The results
obtained during the October analysis showed similar responses.  During
both studies the peak influent organic loading occurred between 9 and
11 AM, when the hydraulic loading was maximum.  The effluent mass dis-
charge is shown to display the same variations to the influent mass
loading.  The maximum-to-average and minimum-to-average ratios derived
from both the June and October diurnal studies are as follows:

                                              Influent
                                         TCOD           TSS

          Maxim urn/Average                1.69           2.0
          Minim urn/Average                0.44           0.25

     The  diurnal variation of  the RBC fourth stage dissolved oxygen
 concentration  is displayed on  Figure 10.   The 24-hour oxygen profile,
 recorded  10/4-5/77,  shows marked diurnal variations consistent with the
 waste  load  variation imposed on the RBC system.  All DO monitoring data
 reported  herein represent levels between 9 and 11 AM; as shown on
 Figure 10,  these  are actually  the minimum  DO levels experienced by the
 system through the day.


                                   37

-------
Parameter Correlations

     Correlations between major water quality parameters were developed
and  are  summarized on Table 7.  These relationships reflect changes in
waste characteristics with the various levels of treatment in the RBC
system.

PRETREATMENT

     Pretreatment of the waste to remove heavy solids and trash was
necessary before application to the RBC system.  The pretreatment pro-
vided removal of grit, scum and floatables, and the heavier fraction of
primary  solids from the waste which could cause clogging of the media
if passed into the RBC system.

     As  previously described, the raw influent samples were taken after
passage  through the detritor, while the RBC influent samples were ob-
tained after the high rate primary treatment zone at the RBC pump in-
take.  The waste reductions accomplished by pretreatment described re-
movals obtained in this high rate primary settling zone only.  Refer to
Figure 2 for actual sampling locations.

     Figure 11 presents TSS and TCOD removals accomplished by high rate
primary  treatment.  As shown, 20 to 25 percent TSS removal and 10 to 15
percent  TCOD removals were observed at nominal overflow rates between
280  and  370 m3/d/m2 (7,000 and 9,000 gpd/ft2).  Minor re-
movals of TBOD5 were measured, typically between 0 and 5 percent.

     Periodically, settling tests were conducted to determine the set-
tling characteristics of the solids at specific points in the process.
Figure 12 presents the results of a test conducted in the raw influent
which had an initial TSS of 173 mg/1.  Although data was not recorded
at equivalent overflow rates greater than 80 m3/d/m2 (2,000
gpd/ft2) the results imply that TSS removals in the order of 20
percent  can be expected at overflow rates between 280 and 370 m3/
d/m2 (7,000-9,000 gpd/ft2).  This is similar to the results
presented on Figure 11.

RBC/UNDERFLOW CLARIFIER PERFORMANCE SUMMARY

Phase I;  Loading Evaluation - March through June 1977

     Figures 13 through 15 present chronological records of waste load-
ings and reductions obtained during this phase of the study.  Various
loadings were applied to the RBC system to assess the optimum loading
that would meet EPA effluent standards.  Computed averages are shown on
each of  the Figures.  Table 3 presents average summaries of each of the
parameters analyzed during this period.

     During March the flow to the RBC system was constant and did not
reflect diurnal variations.  The programming valve which was to  accom-
plish this was delayed in shipment and was not installed until the


                                   40

-------
Z
UJ
o
>
X
o

o
UJ
>
_J
o
en
3.2




2.8




2.4




2.0




1.6




1.2




0.8




0.4
       4

       PM
ป                             NORMAL
                             SAMPLING
                             PERIOD
                             (9-11 AM)
                                                    I	I
                 10
12

AM
                                                   10
12

PM
              10/4/77
                                       10/5/77
                               TIME OF DAY
                  Figure 10.  Example of diurnal

                   dissolved oxygen variations
                                39

-------
o
o
o
ง
o
5
LJ
o:
Z
LU
O
o:
LJ
0.
en
CO
 I
_J
LU
o:
LU
o
o:
LU
a.
70

60
50
40

30
20
10
0
70
60
50
40
30
20
10
0

TCOD
—
—

—
^^
9
i
TSS



\


1







> <3>(
1





ฎ^

i

LfSfAfO-
1 3/22-4/6/77
2 4/1 1-5/13/77
3 5/23-6/30/77
4 7/18-9/25/77
5 12/1/77-2/24/78
|
1

ฎ
D^^^
1 1





5\
0
1 1
                100
200
             2,000    4,000
                                   300
                                ms/day /m2
                               J	L_
                   400
          500
                                       600
   6,000   8,000

       gpd/ft2

   OVERFLOW RATE
10,000   12,000   14,000
                 Figure 11.  Performance  summary of
                    high-rate pretreatment sector
                                42

-------
        TABLE 7.   CORRELATION OF  MAJOR WATER  QUALITY  PARAMETERS
Raw influent                    BOD5  (T)  =  0.5  COD  (T)  -  30
                                BOD5  (S)  =  0.6  COD  (F)  -  15
                                BOD5  (TSS)  =  0.4  TSS  -  20
                                COD (TSS) = 1.0 TSS - 30

Raw influent                    BOD5  (T)  =  0.6  COD  (T)  -  20
                                BOD5  (s)  =  0.6  COD  (F)  -  15
                                BOD5  (TSS)  =0.5  TSS  -  20
                                COD (TSS) = 1.0 TSS - 20
                                VSS = 0.8 TSS

Stage 1                         BOD5  (s)  =  0.6  COD  (F)  -  15
      2                         BOD5  (s)  =  0.6  COD  (F)  -  10
      3                         BOD5  (S)  =  0.4  COD  (F)  -  5
      4                         BOD5  (S)  =0.4  COD  (F)  -  5

Effluent                        BOD5  (T)  =  0.45 COD (T) - 10
                                BOD5  (S)  =  0.35 COD (F) - 5
                                BOD5  (TSS)  =  0.5  TSS  -  5
                                COD (TSS) = 1.0 TSS - 10
                                TVSS  =0.9  TSS

RBC sludge                      TVSS  =0.8  TSS
                                  41

-------
                                                           HYDRAULIC
                                                            LOADING
                                                              RATE
DAY-
DATE-
-10    20    30    40
 18    28     7     17
 HMARCH-!	—APRIL-
            Figure 13.   Chronological record of RBC flow^
            BOD5 and hydraulic rates; Phase I (3/77-6/77)
                                 44

-------
    100
     80
     60
                                     RAW INFLUENT

                                  SETTLING TEST, 9/16/77
                                  INITIAL TSS= I73mg/l
LJ
a:
LU
O
a:
UJ
a.
40
     20
                20

                 I
                    40        60
                     mVday/m2
                    _J	I
80
 I
100
               500       1000       1500
                           gpd/ft2
                       OVERFLOW RATE
                                       2000
            Figure 12.  Settling test results
                 on raw influent sample
                          43

-------
  o>
  E
  Q
  O
  U
  oป
  E
   •\
  Q
  O
  O
  UJ
  00

  O
 O
 o
 o:
 Z>
 h-
 <
 tr
 UJ
 Q.
 5
 UJ
 H-
 U,
 U.
 UJ
     600
      500
      400
300
      200
      IOO
        0
     400
300


200


IOO


  0
 30




 20
 10
              LOW
            LOADING
DAY —
DATE-
   10    20
   18    28
   I-MARCH
                                                                TOTAL COD
                       MODERATE
                       LOADING
         HIGH
       LOADING
                                                             SOLUBLE COD
                                                              I      i
                                                      TEMPERATURE
30    40    50
 7     17    27
	APRIL	
60    70
 7     17
	MAY-
80
27
90
 6
  IOO
   16
•JUNE-
MO
26
120
 6
            Figure  15.   Chronological record of TCOD,  SCOD,
                 and  temperature; Phase I  (3/77-6/77)
                                    46

-------
    250
    200
 oป
 E
  ~  I 50
 ID
Q
O
CD
  ,  100
o
h-
oป
E
O
QQ
LJ
CD
CT
E
C/f
Q
H
o
en
Q
LU
Q
•z.
LU
0.
 50


  0
225
200

175

150

125

100

 75

 50

 25
  0
250


200


150


100


 50
  en

DAY-
DATE-
             LOW
           LOADING
          INFs 9l.6mg/l
•10     20
 18     28
 hMARCHy-
30
 7
                        MODERATE
                         LOADING
                           I48mg/l
         HIGH
       LOADING  TOTAL BOD5
                                                               SOLUBLE BOD.
                                                       INF= 75.4 mg/l
     EFF= 30.7 mg/ I
INFLUENT
      7
                                         EFFLUENT
                                                          SUSPENDED SOLIDS
   40
   17
•APRIb-
50
27
60
 7
  70
  17
MAY-
                                                  80
                                                  27
                                                     9O
                                                     6
             100
              16
           •JUNE-
110
 26
120
 6
            Figure  14.   Chronological record  of TBOD  , SBOD ,
                       and TSS;  Phase I  (3/77-6/77)
                                                                         •JY-I
                                     45

-------
     The hydraulic loading was increased on May 15 for evaluation of
 the  system under a high loading condition.  After one week acclimation
 the  high loading was investigated from May 23 to June 30.  The initial
 average flow setting was 2,500 m3/d (0.66 mgd) and the organic
 loading was 20.0 g TBOD5/d/m2 (4.9 Ibs TBOD5/d/l,000
 ft2).  Soon after adjustment to this new loading, filamentous bac-
 teria appeared on all stages, most heavily on the initial stages.  No
 steps were taken to remove them and by June 6, all signs of these bac-
 teria were gone.  They had been visually identified as the sulfur bac-
 teria , beggiatoa, which are white-to-clear, filamentous organisms, and
 form large white patches on the surface of the biofilm.  There was no
 measurable deleterious impact on treatment efficiencies during the
 presence of these organisms.

     Tracer analyses (discussed earlier in Section 6) which were con-
 ducted to hydraulically characterize the RBC/Underflow Clarifier sys-
 tem, indicated that the combined fourth stage and turaround sector
 behaved as a single completely mixed tank.  To offset this and poten-
 tially make better use of the turnaround sector for clarification, a
 fourth stage baffle was installed on June 10.  This remained for the
 duration of the program.  On June 21, the baffle between Stages 1 and 2
 was  removed to reduce the load to the first stage by doubling the
 available surface area in Stage 1.  This was done as a precaution
 against excessive growth accumulations in the first shaft under the
 high organic loading conditions.  Subsequent tracer analyses indicated
 that with this baffle removed, the two-shaft stage was still completely
 mixed.  No measurable differences in treatment efficiency were observed
 subsequent to these modifications.

     The high loading condition, conducted May 23 and June 30, was set
 to stress the RBC system.  Overall, the flow averaged 2,520 m3/d
 (0.665 mgd) which represented a hydraulic rate of 0.14 m3/d/m2
 (3.38 gpd/ft2).  The influent TBOD5 and TSS concentrations
 averaged 143 and 128 mg/1, respectively.  The TBOD5 loading rate
 averaged 19.7 g/d/m2 (4.04 lb/d/1,000 ft2),  resulting in an
 effluent TBOD5 of 55 mg/1 (62 percent removal).   As the loading
 rate increased, the BOD5 removal rate also increased.  However, the
 percent removal of total BOD5 through the system decreased.  The
 average effluent TSS was 58 mg/1 (55 percent removal).  The increased
 temperatures,  averaging 23.2 degrees C in this time period resulted in
 lower dissolved oxygen levels throughout the RBC system.  The average
 influent DO at peak diurnal loading was 2.2 mg/1,  while the effluent
 averaged 0.8 mg/1.

     Figure 16 presents a summary of the effluent quality obtained
under the various hydraulic and organic loading  conditions evaluated
during Phase I.  As indicated, the criteria  of 30 mg/1 TBOD5 and
 TSS  (30-day average) would be met at hydraulic loadings between 0.08
and 0.09 m3/d/m2 (2.0 and 2.2 gpd/ft 2) and  organic loadings
between 12 and 14 g TBOD5/d/m2 (2.45 and 2.86 Ib TBOD5/d/
 1,000 ft2).  Based on these findings,  these  conditions were recom-
                                  48

-------
first week of April.  Thus the low loading condition was ev'aluated un-
der a constant flow mode.  In mid-March,  deposits of solids were noted
on the intermediate floor in the early stages,  and were also accumula-
ting on the media surface.  To alleviate  a potential problem due to
solids accumulation, a baffle between Shafts 1  and 2 was installed (to
increase velocity between shafts), and the influent pump intake was
moved further downstream from the raw influent  channel.  On April 12th,
the roughing screens were placed in the RBC influent channel to catch
larger fibrous solids which did not settle out  in the initial pretreat-
ment step.

     The low loading condition was maintained from March 22 through
April 6, 1977.  The RBC flow was initially set  at an average rate of
760 m3/d (0.20 mgd).  This was maintained until March 29 when flows
were increased to 1,140 m3/d (0.30 mgd).   The increased flow was
required to maintain the desired organic  loading at the low BOD5
concentrations in the plant influent.  Overall, the flow averaged 1,060
m3/d (0.28 mgd) and was maintained for the duration of the low
loading condition.  The TBOD5 averaged 92 mg/1  and the TSS 124
mg/1, indicating a relatively dilute waste during this period.  The
average TBOD5 loading was 5.31 g TBOD5/d/m2 (1.09 Ibs
TBOD5/d/1,000 ft2).  The BODs removal rate averaged 4.47 g
TBOD5/d/m2 (1.91 Ibs TBODs/d/l,000 ft2) and the average
effluent TBOD5 was  14 mg/1.  Effluent solids averaged 24 mg/1.
These represented 84 percent and 80 percent BOD5 and SS removal,
respectively.  The dissolved oxygen levels were relatively high
throughout this time period, averaging 6.9 and 4.3 mg/1 in the influent
and  effluent, respectively.  The average temperature was 13 degrees C.

     Waste reductions obtained during this loading condtion were used
to aid in the selection of the flow required for the moderate loading
condition, where effluents would be commensurate with EPA standards.

     Diurnal flow variation was instituted on April 7 and the flow rate
increased to deliver 1,510 m3/d (0.40 mgd).  This flow was main-
tained throughout the moderate loading study period.  After approxi-
mately one week acclimation (April 6 to April 11), the moderate flow
condition was investigated from April 11 through May 13, 1977.  Over-
all, the flow averaged 1,440 m3/d  (0.38 mgd), representing an
effective hydraulic loading of 0.079 m3/d/m2 (1.94 gpd/
ft2).  The influent TBOD5 and TSS  concentrations were  148 mg/1
and  122 mg/1, respectively.  The TBOD5 loading averaged 11.7 g
TBOD5/d/m2 (2.39 Ibs TBOD5/d/l,000 ft2), and the
resulting  average  effluent TBOD5 was 23 mg/1 (84 percent removal).
This reflected a removal rate of 9.86 g TBOD5/d/m2  (2.02 Ibs
TBOD5/d/l,000 ft2).  The plant flow was relatively constant
during  this period  resulting in uniform daily waste loadings through-
out.  DO concentration levels at peak diurnal loading averaged 5.0 mg/1
influent and  1.5 mg/1 in the effluent.  The average temperature was
17.2 degrees  C.  Effluent TSS averaged 23 mg/1 during  this period (81
percent removal).
                                   47

-------
mended  for steady state evaluation under both summer and winter condi-
tions.

Phase II: Warm Temperature Operation - July 18 through September 25

     The second phase of the Edgewater study evaluated steady state op-
eration of the RBC/Underflow Clarifier system under warm temperature
conditions.  The optimum loading was selected based on results of Phase
I.  The results of this loading period are summarized on Table 3.
Chronological records of daily monitoring data and loadings are dis-
played  on Figures 17 to 19.

     On July 1, the RBC flow was programmed to deliver 1,700 m3/d
(0.45 mgd) which represented a hydraulic rate of 0.093 m3/d/m2
(2.29 gpd/ft2).  This flow was reduced to 1,510 m3/d (0.40 mgd)
on July 30.  Overall, the average hydraulic loading through the summer
period  was 0.085 m3/d/m2 (2.08 gpd/ft2) and the BOD5
loading was 11.4 g/d/m3 (2.33 lbs/day/1,000 ft2).  The average
total effluent BOD5 and TSS were 28 mg/1 (79 percent removal) and
30 mg/1 (75 percent removal), respectively, essentially the values pre-
dicted  by Figure 16.

     On July 28, the RBC system was drained and heavy accumulations of
sludge  were found on the false floor, especially in the early stages of
the system.  The floor was cleaned, and the first stage baffle was re-
installed.  The clearance on all baffles was reduced from 18 cm (7 in)
to 5 cm (2 in) to affect higher velocities along the floor and to mini-
mize any further solids deposition.  The tank was again drained in
March 1978 and no significant accumulation of solids was observed.
                *
     An acid dump of unknown origin passed through the RBC system on
August  15.  There was an immediate sloughing of the biofilm, and then
gradual build-up within ten days.  The effluent quality was noticeably
poor for only one day, day 161, as shown on the chronological figures.

     On September 1-3, a series of acid dumps again passed through the
system, resulting in severe losses of biofilm coverage.  Sampling was
discontinued until Septemer 11, when the biofilm had regrown.  At this
point a pH alarm system was installed to prevent any recurrence.  The
RBC pump would be shut down should any sign of extreme pH conditions
appear  in the plant influent.

     Under these warm temperature conditions, dissolved oxygen levels
were frequently very low throughout the RBC system.  Low oxygen levels
were induced by the higher temperatures with lower saturation levels
and the resulting lower driving forces.  During the summer months the
influent DO averaged 1.5 mg/1 at peak diurnal loading, while the ef-
fluent averaged 0.5 mg/1.

     With the lower oxygen levels,  the aerobic layer of the biofilm is
reduced.  The increased anaerobic layer may partially explain the in-
termittent recurrence of the filamentous organism beggiatoa through the


                                  50

-------
oป
E
C/D
 10
Q
O
m
i-
z
UJ
D
_J
LL
U_
LU
 Oป
 E
 IO
Q
O
m
h-
bJ
z:
u.
UJ
70




60




50




40




30




20




10



 0
70



60



50




40



30



20



 10
                           TSS
                  0.05         O.I          0.15

                           mVday /m2
                 	J	I	
                 .0       2.0        3.0        4.0

                            gpd/ft2

                  HYDRAULIC LOADING RATE
                           10        15

                           g /day/m2
                                         20
                        Ibs/day/ 1000 ft2

                      BOD5 LOADING  RATE


             Figure 16.  Summary of Phase I

               load evaluation performance
                                                  0.2
                                                   5.0
25
1
0
1
1.0
1
2.0
1
3.0
1
4.0
1
5.0
                           49

-------
       250
       200
 E
  .  150
 m
Q
O
m
  .  100
   o
   oป
   E
   CO
   Z>
   -J
   o
   CO
  CO
  Q

  _J
  o
  CO

  O
  UJ
  Q
  2
  UJ
  CL
  CO
  Z)
  CO
DAY-
DATE-
     50



      0

    225

    200

    175

    150
cP  125
O
0ฐ   100
UJ
     75

     50


     25

      0
   250
      200
    150
    100
    50
     110
     -26

      1-4
                               AVG. INFLUENT = 134 mq /1
                                                     WARM TEMPERATURE PERIOD
                                                                   TOTAL
                                                                    BODS
                                                                     AVG. EFFLUENT
                                                                       28 mg/l
                                AVG. INFLUENTs 97 tnq/ I
                                                                   SOLUBLE
                                                                     BODg
                                                                     AVG. EFFLUENT
                                                                       23 mg/l
                                                          AVG. INFLUENT= I 21 mg/l
                                                                SUSPENDED
                                                                  SOLIDS
120

 6
  130
  16

-JULY-
140   150    160    170

26     5     15     25

          •AUGUST-
ISO   I9O    200
 4     14    24

   •SEPTEMBER
                 Figure 18.  Chronological  record of  TBOD
                     SBOD5, and  TSS; Phase  II (7/77-9/77)
                                      52

-------
    1.0


   0.9


   0.8


   0.7


   0.6


   0.5


H-  0.4
O

CC  0.3


   0.2


   0. I

   0

   6.0
3
O
00
cr
    5.0
0=0
0<2.0
-I (A


g~'ฐ
00

    0
 *  5.0
O   4.0


-j"S-
<   2.0

O

x   i.o
            3.5
       —   3.0
         O
         O  2.5
         O
       Ux  2.0
         a
         •o
            1.0



            0.5



             0


            25



            20
        -ฃ   15
         TO


        -*   10



             5



             0

            0.2




         E 0.15
        •o
         T3
            O.I
           0.05
             0
     DAY	110
     DATE	26

              N
                                                         WARM TEMPERATURE PERIOD
                                                                      R8C FLOW
                                              AVG. FLOW= I550m2/day
                                                        (0.409 mgd )
                                    AVG. TBOD5 LOADING= I 1.4 g/day/m2
                                                      (2.32 Ibs/day / 1000ft')
                                                                       BODS LOADING
                                                                         RATE
                                                 AVG SBOD5 LOADING = 8.26 g/day/m2
                                                                   ( 1.69 Ib/day/IOOOft3)
                                                    I       I      I      II
                            \
                              AVG. HYDRAULIC LOADING = 0.085 m3/day/m2
                                                     (2.08gpd/ft3)
                            •*V\ซ/ป
                                   jlWrtA
                                                                       HYDRAULIC
                                                                        LOADING
                                                                         RATE
                                 I
                                        I
                                                    J_
                                                                 I
                                                                       _L
                    120    130   140    150    160   170
                     6     16    26    5     15    25
                   	JULY	1	AUGUST	
                                                          180    I9O    200
                                                          4     14     24

                                                         	SEPTEMBER
                    Figure  17.   Chronological record  of RBC flow,
                   BOD , and  hydraulic  rates; Phase II (7/77-9/77)
                                          51

-------
 summer period.  Additionally, the bacteria appeared at times  when sig-
 nificant loading changes were imposed,  as in early June and early July.

      Beggiatoa is a filamentous bacteria which metabolizes sulfide to
 elemental sulfur.  With low DO levels,  sulfate may be  utilized  by the
 bacteria as an oxygen source, resulting in the production of  sulfide.
 Increased sulfide levels are conducive  to the growth of beggiatoa.
 Table A-3 in Appendix A summarizes the  sulfate and sulfide analyses
 conducted during the program.  These  data indicated only minor  activity
 in terms of sulfate reduction or sulfide production.   During  the  occur-
 rence of the bacteria in late September, H202 was  evaluated as
 a  possible remedy to remove beggiatoa from the system.   The hydrogen
 peroxide was metered at a dosage of 40  mg/1  over a 48-hour period.
 Within 24 hours the filamentous growth  had disappeared.

      As displayed on the chronological  records of  BOD5  and TSS,
 Figure 18,  treatment performance was  not adversely impacted by  the re-
 currences of the filamentous growth.  Operating conditions with the RBC
 system were apparently not conducive  to the  extended growth of  these
 bacteria.  Typically the growth would disappear within  a period of one
 to two weeks.   The feeding of H202 into the  system was  success-
 ful  in eliminating the bacteria,  but  depending on  the degree  and  impact
 of the coverage,  the use of E202 (or  a  similar remedy)  may not
 be required.

      Table  A-2  in Appendix A presents a summary of nitrogen series an-
 alyses conducted  throughout the study.   The  data indicated that at no
 time,  including the summer months,  was  nitrification occurring  to any
 significant degree within the RBC system.

 Phase  III;   Cold  Temperature  Operation  - December  1 through February
 24,  1978                         	B	~

     The  third  major phase of the  experimental  program  at Edgewater
 evaluated steady  state  operation under  cold  temperature, winter condi-
 tions.  The  hydraulic  and  organic  loading conditions selected were the
 same as those investigated  during  the summer, warm  temperature,  evalua-
 tion.   Overall  average  results  are  presented on Table 3.  Chronological
 records of  the  system's operation  and performance are displayed  on
 Figures 20  through  22.

     The  average  flow during  the period December 1, 1977 through
 February  24, 1978 was 1,490 m3/d (0.393 mgd), which represented  a
 hydraulic loading of 0.081 m3/d/m2  (2.0 gpd/ft2).   The  in-
 fluent TBOD5 and TSS concentration averaged 158 and 133 mg/1,  re-
 spectively.  Average effluent TBOD5 and TSS were 33 mg/1 (79 per-
 cent removal) and 24 mg/1  (82 percent  removal), respectively,  and  the
 average temperature was 11.3 degrees C.   With the  lower temperatures,
higher DO levels were measured during  Phase 3; the  influent DO during
peak diurnal loading averaged 6.1 mg/1,  and the effluent average DO was
 3.4 mg/1.                                                     ฐ
                                  54

-------
o>
E

cT
o
CJ
 UJ
 _J
 00
     600
     500
     400
     300
 O   200
 H-
     100
       0

     400
  0>
  E  300

 Q*
 O
 O
     200
O   100




      0

     30

O
o
 u
 cc
 o:
 UJ
 CL
 5
 UJ
 U.
 U.
 UJ
DAY-

DATE-
      20
       10
                                                 WARM TEMPERATURE PERIOD
                                    AVG. INFLUENT= 316 mg/l
                                                              TOTAL
                                                               COD
                                                    AVG. EFFLUENT= 118 mg/
                         I	I	I	I	I
                                                               I 	I
                                                 AVG. INFLUENT= 207 mg/l
                                                              SOLUBLE
                                                                COD
               I      I      I     I
                                         •AVG. EFFLUENT= 99 mg /

                                       I      I      I      I
                             AVG. = 26ฐC
                                                         TEMPERATURE
               I
                     I
                           I
                                 I
                                             1
                                                 _L
                                                       _L
 110    120    130    140   150    160    170

-26     6     16    26     5     15    25

  |-J-|	JULY	1	AUGUST	
                                                 180    ISO    200

                                                 4     14    24

                                                    SEPTEMBER
                 Figure 19.   Chronological  record of TCOD,

                SCOD  and temperature; Phase II  (7/77-9/77)
                                     53

-------
250
                       COLD TEMPERATURE
                           PERIOD
                           AVG. INF* 158 mg/l

                 AVG. EFF = 33 mg/l
                                                           SOLUBLE
                                                            BOD9
                        AVG. INF = 9| tng/l
                                                        SUSPENDED
                                                          SOLIDS
270   280   290
 3     13    23
	DECEMBER
                                    310   320
                                     12    22
                                   JANUARv
DAY	250   260
DATE	13     23
        I	NOV
         Figure 21
:MBER	1	JANUARV	1—FEBRUARY—M
Chronological record of TBOD_,
           SBOD5 and TSS; Phase III (12/77-2/78)
                             56

-------
    1.0

    0.9

    0.8

    0.7
T3
Oป
g   0.6
O
u.
    0.5

    0.4
o
GO
^   0.3
    0.2

    O.I
    0
O   6'ฐ
CD
K   5.0


.  ซ4.0
<0

 >2 3.0
    1.0
ง   '-ฐ
CD
    0
 .   5.0

cr
Q
    kO

    1.0

    >.o

    1.0
            3.5
            3.0
          O
          ง2.5
   o
  •o
  >
   e 1.5
             1.0


            0.5

             0


       —    25
       — N 20
          E
   CT
—   10
       —    5


             0

            0.2

          N
          ฃO.I5
          o
          TS
            O.I
           0.05
     0
     DAY-
     DATE
                     I
                                                         COLD TEMPERATURE PERIOD
                                                                  RBC FLOW
                                                V
                                                   AVG. FLOW = 1490
                                                              (0.393 mgd )
                    I      1
                                     AVG. TBOD5 LOADING = I2.9g/day/m2
                                                        (2.63 Ibs/day/IOOOfr)
                  AVG. SBOD5 LOADING= 7.4g/day/m2
                    •	.	I     (L52 Ib/day/IOOOft')  ,
                                                                      BODS LOADING
                                                                        RATE
                                                                       I    "  I
                                    AVG. HYDRAULIC LOADING = 0.081 m3/day /rr,2
                                                           (2.0 gpd/ft2)
                                                                       HYDRAULIC
                                                                     LOADING RATE
                                  I
                                        I
                                              I
                                                           I
                                                                 \
                                                                       I
                                                                             I
     •250   26O
     -13     23
       |	NOV
 270    280   290
  3     13     23
I	DECEMBER—
                                             300   310   320
                                              2     12    22
                                            \	JANUARY—
                                                               330   340   350
                                                                 I      II     2!
                                                               -I	FEBRUARY
360
 4
                Figure 20.   Chronological  record of RBC  flow, BODC
                    and hydraulic rates; Phase III  (12/77-2/78)
                                         55

-------
     During the cold temperature evaluation there were two periods
during which the loading to the system was significantly different than
average.  The first occurred January 16 through February 3.  The flow
was 1,310 m3/d (0.347 mgd), and the TBOD5 loading was 9.53 g
TBOD5/d/m2 (1.95 Ibs•TBOD5/d/l,000 ft2).  At this lower
loading the effluent TBOD5 averaged 21 mg/1 (82 percent removal)
and the TSS was 15 mg/1 (88 percent removal).  The lower flow rate was
due to a malfunction in the automatic programming valve.  Once re-
paired, the flow was inadvertently readjusted to a higher rate.  From
February 4 through 14 the flow averaged 1,750 m2/d (0.462 mgd) and
the TBOD5 loading was 17.3 g TBOD5/d/m2 (3.54 Ibs
TBOD5/d/ft2).  During this higher loading condition the efflu-
ent TBOD5 averaged 48 mg/1 (73 percent removal) and the TSS was 29
mg/1 (78 percent removal).  Both of these monitoring periods were in-
cluded in the overall averages discussed earlier and summarized on
Table 3.  However, it should be noted that the effluents observed
during each were close to the values indicated by the curves shown on
Figure 16.

Interstage Analysis of RBC System

     Throughout the experimental program at Edgewater, 24-hour flow
proportioned composite samples from each stage were analyzed on a regu-
lar basis.   These data are tabulated on Table A-6 in Appendix A.  A
summary is presented on Table 8, and is divided into the six different:
periods representing specific RBC operating conditions.  Since diffu-
sion and reaction in the biofilm of the RBC system is a function of
soluble organics, only the soluble COD and BOD5 were measured in
each stage.  DO measurements were taken between 9 and 11 AM and repre-
sent the peak diurnal loading conditions.  The interstage data were
used to calibrate an RBC kinetic model developed by Hydroscience.  This
in turn was utilized in the development of design nomographs discussed
in a subsequent section.  The model is described in detail in Appendix
B.

     Essentially, the model is a series of material balance equations
which are solved to determine substrate and oxygen levels in the efflu-
ent from each stage and in the attached biofilm.  Mass transfer resis-
tances, determined as a function of operating conditions, are con-
sidered in both the liquid phase and biofilm, and the reaction rate is
related to substrate and oxygen concentrations through the kinetic
equations.

Model Verification—

     The interstage data obtained during the Edgewater study (and sum-
marized on Table 8) was used to calibrate and verify the RBC kinetic
model.  The basic approach in this procedure was to establish values of
the variables associated with the physical and biological process and
to perform a search for appropriate removal rate and oxygen utilization
rate constants.
                                  58

-------
    600
    500
~   400
o>
E
o
LU
ft
o:
UJ
a.
5
LU
LL
Lu
UJ
    300
O   20ฐ
h-
    100
      0
    400
    300
    200
 O
 O
 O

 LU
 _l
 CD
 ID
O    ,00
      0

     30
     20
     10
                           COLD TEMPERATURE
                                PERIOD
                    I      I      I      I     I       III       I
                              AVG. INFLUENT= 183 mg / I
                                I
                                                  I
                                                                   TOTAL
                                                                   COD
                                                             SOLUBLE COD
               I      I      I    \-AVG. EFFLUENT^ 77 mg/l	i	i	i
                                                            TEMPERATURE
                                                       I
                                                             I
                                                                     I
DAY	250   260    270    280   290    3OO   3IO   320

DATE	'3    23     3    13    23     2     12    22

        |	NOV	1	DECEMBER	1	JANUARY—
               Figure 22.  Chronological  record of TCOD,

             SCOD, and temperature;  Phase III (12/77-2/78)
                                                      33O   340   350   360

                                                        I     II     21    4

                                                           FEBRUARY	[to\
                                   57

-------
RO =  [a'k   S     +  b'Xv]    c
      Coupled Michaelis kinetics are used to  simultaneously compute  oxy-
 gen and substrate profiles through the fixed-film treatment process.
 The rate equations,  which assume the reactions to occur  exclusively in
 the biofilm layers,  are as follows:

                                                       (1)


                                                       (2)


 where:     Rs    =    rate of  substrate removal (mg/l/min BOD5)
           Ro    =    rate of  oxygen consumption (mg/l/min  02)
           S     =    Substrate  (6005 or COD)  concentration (mg/1)
           C     =    oxygen concentration (mg/1)
           sm    =    substrate  Michaelis constant (mg/1  BOD5)
           cm    =    oxygen Michaelis constant (mg/1 02)
           k     =    maximum  rate  of substrate removal (mg/l/min
                      BOD5)
           a/     =    oxygen utilization coefficient (mg  02/mg
                      BOD5)
           b/     =    endogenous reaction rate  (mg 02/mg  VS/min)

      The rate  constant,  k,  is the  combined term,  yXv/Y, where y is
 the maximum specific  growth rate,  Xv is the biomass concentration,
 and Y is the organism yield coefficient.   Because each is  assumed con-
 stant in the model, a single  rate  constant (k)  is employed.

      Further model simplification  was accomplished by using first order
 kinetics with  respect to substrate.   First order  kinetics  were induced
 by  setting  a high Michaelis half rate constant  of  10,000 mg/1.  Thus
 the term,

                                                            (3)


 may be written (since SmปS),

               M                                          (4)


 The first order rate  constant, k', reported herein, is then defined as

                    _k
               k' = Sm = min-1                             (5)

     The model input  provides a description of the physical system,
which includes the number of stages, surface area, tank volume,  rota-
 tional speed, and hydraulic loading rate.  Input necessary  in the  de-
 scription of the biological process includes influent  organic loading,
dissolved oxygen levels, substrate and oxygen diffusion rates and  co-
efficients describing substrate and oxygen utilization.

                                   60

-------























^J
H

O

w
o
^J
H
CO
oi
u
y
M

u
3
&H
O

ฐ5
1
CO

.
00

J
DQ
^*
H
















































co

Q

O

h- (
el

u

PH

00

M
CO
j


z

























TJ
O
CN ป-i
•~-- TJ Ol
CM ^ OH
m O •
•^. a
t M
01
H
•o
O
CO V.
^ B 0)
I cd
"•^ ^ ป
-^, a
00 0
01
H
00
C
-. -H T3
-- TJ O
r** n) *H
1 0 1-
CM J O"
CM DM
^ JC
\O 00
•r4
X



00
c
r*. -H
— > "O ~O
^^. cd O
vฃ) O -H
J ปJ I.
-H 0)
-^. J= OH
vO 00
a

00
c
•o
•-H cd
-H O TJ
m T-I
1 0) >-i
(*1 4-1 0)
-H Cd CM
"^** t*
-J- 0)
00
vO C
^ T3 T)
T 3 t
^ t— 1 b
— i 0)
CO O



V. U
Ol 0)

oi cd
งt.


OH vx



-* ON oo r~ CM co
x~\ • • • • • •
"* ^iง ^ m^-cococo f^^^f"^^0^^
m >ป -H
-H •
o




CM in oo \o m r~
-ป -3-CM \O -^OOOO fOOcMNOr>-OOONCO
oo ON CM ^o co r^ in co CM CM CM
•^ CO *^ ^H
i— 1 •
O




r^ o CM ON m
x*^ ซ • • • •
CO CMr^*- *^ CN*~* OO ONO*^ OO^CMf**'
mcMCM ^rปr*.mco\oco
r^* ^^ *^
CM •
O








*3" r^ in ~H o> ^o
"* ^ง S -•-'-•oo 5ss^2^?;s
\^ r^ *^
CM •
0






ON ^f CM in CO f^
*^ OvO o incocMCM^H \ov^ooNONcoin co
U1ON -H vOOOvOCOCMCMCMCM
*^ ro *~*
••H •
o
>^x


oo m m -* CM o
-* ^CM CM OO-*-*'*'* -*CMONOOCMซ*NOCM
-* CO
o
rH
u ^ป
CO O rH 00
0ป>> •*-. B-HCMCO-*
ccf -S-a '^ M*-H co^- n-i'e 4J itJ>ซ
2 ^-^"00 H-l H —***•• ** CMOOOTOOt/JWW
OOCO0 V UH 4J 4J 4J *J -HII II
a ^-^ ^-^ c co co oo co loooo H oo
>*-i M H
o •
ป o, i m
00 Q
O iH 0) O O
Z PH H Q ซ
                            co •—•  —^ ซ-ซ
                                                          CM  -* m CM m
                            vOcMCMcncMONOOvo
                                                          ON  -* co CM \o
                            \o  cMf^vOooocMP^    in^mr^-*
                            ooocoooooooor^    —i  o CM -H CM
                            CM  CM —< -H                  —i  —< ^H i—(CM
                                                          m  CM vo co oo

                                                          -H  CM CM -* CM
                             8ฐ                           C
                                   -H CM  CO -*            00 -H

                             CC4-I4J4J4JU-I<4-I         4J
                            MMCOOOOOOOWW
                             III             II
                            H 00  00           H  00

                            o
                            o
59

-------
oป
E

 to
O
O
CD

LU
-J
CO
ID
-J
O
 in

O
CD

LU
_J
CO
D
_J
O
CO
0ป

ฃ


 IO
Q
O
CO

LU
_J
CO
o
CO
     120
     100
      80
      60
      40
      20
     120



-   100

on

ฃ    80
      60
      40
      20
LOW LOADING PERIOD
  (3/14 and  3/17 )
  0 = I,480m3/d
  HLsO.081 m3/d/m2
  SL= 2.6 g SBODj /d/m2
  TEMP. = 12.8 ฐC
                                  4E
                       MODERATE LOADING PERIOD

                             (4/11-5/13/77)
                             0= 1,900 m3/d
                             HL= 0.082 m3/d /iป2
                             SL = 7.06 g SB005/d/nป2
                             TEMP, s I6.9ฐC
                                  4 E
1 C.V

100


80

60
40

20



_


—


(
^
\
—
HIGH LOADING PERIOD
(6/1-6/17/77
— 0= 2,690m3/d

>

<
^V
•
—
HL= 0.19 m3/ d /m2
)


SL: ll.9g SBOOs/d/m2
TEMP. = 23.4 ฐC
> T
^1 I

Q
—



1 1 1







                        z
                        LU
                        CD

                        X
                        O
                        o
                        LU
                                                    CO

                                                    O
                        LU
                        O

                        X
                        o

                        o
                        LU
                        O
                        CO
                        CO
                        o>
                        E

                        •ฃ
                        LU
                                                   X
                                                   o
                                                   o

                                                   >
                                                   -J
                                                   o
                                                   CO
                                                   CO
                            3

                         STAGE
                                 4  E
                 Legend:

                     O
                              0


                              12



                              10



                              8
                                                                    0 : 0.69 mg
                                                                                    BOO
                                                                    b'Xv =3.94mg 02/ l-mln

                                                                    k':0.23min-l
                                                                      PEAK
Q s 0.65 mg 02/mg BOOg

b'Xv'9.92mg 02/l-miiป

k's0.27min-l
                                                               PEAK
                                                         10
                                                                    a - 0.69 mg 02/mg BOOj

                                                                    b'X - 7.9 mg 02/ 1 -min

                                                                    k'=0.34mln-'
                                                AVERAGE-
                                                    -observed
                                                      predicted
     2

  STAGE
                  Figure 23.   RBC kinetic model  verification
                    based on interstage SHOD  and D.O.  data
                                           62

-------
     Temperature corrections for the removal  rate  constant  was  defined
by the relationship
                 KT = K20 c <^x " 20)

where 0 was set at 1.04.  Diffusivities were corrected for temperature
by an equivalent 0 of 1.028.  The endogenous oxygen utilization rate,
b', was corrected for temperature by an equivalent 0 of 1.1.

     Figures 23 and 24 show the final verification results for each  of
the six study periods.  As shown in the figures,  the model was able  to
effectively predict soluble 8005 and DO profiles  through the  system
using a single set of kinetic parameters for all  cases.  Equivalent
model predictions were made for the interstage soluble COD data, as.
shown on Figure 25.  Oxygen profiles were not shown for the COD verifi-
cation runs.  They were very similar to those shown on Figures 23 and
24 for the 6005.

     The kinetic parameters found appropriate were as follows:

          k'      =    0.3 min-1 at 20oC, 0 = 1.04
          a'      =    0.65 mg 02/mg BOD5 removed
          a'      =    0.4 mg 02/mg COD removed
          b'      =    0.2 day at 20oc, 0 = 1.1
          Xv      =    40,000 mg/1
          Sm      =    10,000 mg/1
          CHI      =    0.001 mg/1

A k' =0.3 min~l represents a maximum removal rate k (equation 1)
of 3,000 mg/l-min.  When COD was used as the substrate input, a non-
degradable fraction of 30 mg/1 was assumed.  On Figures 23, 24 and 25,
HL and SL represent the hydraulic and soluble organic loading rates,
respectively.  The effective (wetted) surface area of Stages 1, 2 and  3
is 4,000 m2 (43,000 ft2); the  Stage 4 surface area is 6,200
m2 (66,700 ft2).

     The oxygen concentrations presented in Table 8 and on Figures 23
and 24 represent measurements  taken between 9 AM and 11 AM each day, at
which time the loading to the  system is greatest.  The oxygen profiles
generated by the model are based on peak loading conditions.  The peak
conditions are based  on the maximum to average conditions determined
from the diurnal studies described in Section 6, whereby the hydraulic
loading is increased  by a factor of  1.5 times the average, and  the
average substrate and solids (interstage) levels are increased  by a
factor of 1.7.  Additionally,  the average dissolved oxygen profile pre-
dicted under average  conditions is shown on each of the displays, on
Figures 23 and 24.  The BOD5 and COD verifications shown are based
on average daily loadings.

     It is concluded  from this analysis that the model is capable of
predicting system  performance  over a range of hydraulic and organic
                                   61

-------
    240
 _  200
 \
 o>
 E   160
 Q
 O
 O
 UJ
 _l
 GO
 ID
 _J
 O
 CO
    120
     80
     40
 en
 E
    240
    200
    160
O
O
O  120
UJ
_l
CD
     80
CO   40
    240
 Oป
 E
O
O
UJ
_J
CD
ID
_l
O
CO
    200
    60
     20
    80
    40
                         LOW  LOADING PERIOD
                           (3/14 and  3/17)
                           SL= 9.43 g SCOD/d/m2
                           TEMP ปI2.8*C
                               4  E
                    MODERATE LOADING PERIOD
                          (4/11-5/13/77)
                          SL* 16.69 SCOO/d/m2
                          TEMPป I6.9ฐC
              J	L_L
                              4  E
                        HIGH LOADING PERIOD
                          ( 6/1-6/17/77 )
                          SL*23.5g SCOD/d/m2
                          TEMP*23.4ฐC
                                O
 240


 200


 160


 120


  80


  40
 240


 200


 160


 120


 80


 40
  0

240

200


160


120


 80


 40
                   2     3     4 E
                      STAGE
                                     Legend.'      T-
                                         O  -observed
                                       	predicted
      HIGH LOADING PERIOD
       (6/22-7/1/77)
       SL= 30.9g SCOD/d/m2
       TEMP= 24.7ฐC
                                                                         4 E
WARM TEMPERATURE PERIOD
       (7/18-9/23/77)
       SL= 17.1 9 SCOO/d/m2
       TEMP =26.1 ฐC
                                                                           Q
                                                   J	\	L
                                                                        4  E
COLD TEMPERATURE PERIOD
      (1/5-2/24/78)
      SL= 14. 8 g SCOD/d/m2
      TEMPซ II.4ฐC
                                                   J	1	L_L
                2    3    4  E
                  STAGE
                   Figure 25.   RBC kinetic model verification
                          based on interstage  COD data
                                         64

-------
I2U

^ 100

I 80
O
O 60
CO
UJ
m 40
_l
O 20
CO


120

_ too

rjป
E 80
-
QW 60
0
CO

UJ 40
_J
CO
D
_j 20
O
CO




— 100
\
oป
E 80

O 60
00
UJ
_l 40
CO
13
0 20
CO
f\
HIGH LOADING PERIOD
(6/22-7/1/77)
~" 0= 2,750 m3/d
T HLsO.13 m3/d /m2
-j- SL= ll.Sg SB009 /d/m2
_l I TEMP.s 24.7ฐC
_JL ^N^~ 1
^ ซJ
^""""""is. T
o ฐ
1
I 2 3 4 E
WARM TEMPERATURE PERIOD
1 (7/18-9/23/77)
~~ (^ 0- I,480m3/d
\ _ HLsO.081 m3/d/m2
\ SL= 8.1 g SBOD5/d /m2
— Ny TEMP. = 26. 1ฐC
( >v T
?L
l^^v
1 ^^vT"
1 ^S
— <)\. -r
>I
.J— T Q
— JL

\
I 2 3 4 E
T COLD TEMPERATURE PERIOD
( 1/5-2/24/78 )
~~ Os 1,515 m3/d
\Y HL = 0.083 m3/d/m2
SL* 7.8 g SBOOs/d/m2
TEMP.= 1 I.4ฐC

.
t hv
\
TV
1 1 t^To
1 1
_L.
1
1 ฃ
\
? "0
c
Z* 8
Ul
O
>< 6
O
Q
UJ 4
_J.
O 9
CO '
CO
0 0
w
1 9
1 ฃ
\
C7. 10

ซ
Z 8
Ul
0
^< 6
O

Q
UJ 4
3
O_
2
CO
CO
ฐ 0
w

\
oป 10
E
ซ.
Z 8
UJ
O
X 6
O
0
Ul 4
1
_J
0
CO 2
CO
o
rป
d'= 0.65mg Og/mg BOOg
b X..s 7.9 mg O,/ 1 -min
•^ i *

-
—


"" AVERAGED
T PEAK^ \^
1 1 1 I
I 1 2 3 4
Q = 0.65 mg Og/mg BOOg
b Xy=7.9mg Og/ 1 -min
~~ k'=0.38miปi-l


^

—



- AVERAGE-v
_ PEAK-i \
i^ \ \
— 1 \ ^*
p^g— ^V^^^
.1 111
I 1 2 3 4
a : 0.65 mg O^/mg BOD5
b Xtf s 3.3? mg Q^/ ' -min
k =0.21 min~ '


—

AVERAGE-^
(>V T PEAK-^\/
"~ ^ j^*^*^"
^** A. ~*~^& T
i i
—

1 1 1 1
I 2 3 4 E Legend: I I 2 3 4
STAGE o -observed STAGE
                             -predicted
Figure 24.  RBC kinetic model verification
  based on interstage  SBOD  and D.O.  data
                     63

-------
      5.0
      4.0
   O  3-0
   O
UJ  O
      2.0
      1.0
               25
               20
 -  M  ' 5
    E
    \
    >ป
    o

    *x
    0ป

I—     10
         —      5
      O1—
                     LEGEND:

                       I 3/22-4/6/77

                       2 4/II-S/I3/77
                       3 S/23-6/30/77
                       4 7/18-9/25/77
                       3 12/1/77-2/24/78
                                                    TCOD REMOVAL
                                                        RATE
ESTIMATED Oj UTILIZATION
RATE (MODEL PREDICTION)
                                          ESTIMATED 0,UTILIZATION
                                          RATE (COD BALANCE)
                          10
                                    20        30

                                     g /day/m2
                 40
                           50
                          2.0
                                   4.0
                                             6.0
                                                       8.0
                                 Ibs/day/IOOOft2

                               TCOD LOADING RATE
                                                                 10.0
      Figure 26.   Estimate of RBC  oxygen utilization rates
                                66

-------
loading conditions using a single set of kinetic parameters,  k',  a'  and
b'Xv.  The match of the observed data indicates that hydraulic and
mass transfer components respond correctly to system variations.

Oxygen Utilization

     A primary role of the rotating media is to provide an effective
means for oxygenation of the fixed biofilm and prevent anoxic or  oxy-
gen-limiting conditions in the removal of substrate.  The system  can be
approximated by a COD balance (assuming minimal autotrophic activity)
which estimates the total oxygen utilization for both substrate oxida-
tion and cell synthesis:

     02 Utilization = RBC Influent COD - Effluent COD - COD Wasted

     The term (influent COD - effluent COD) is effectively the TCOD re-
moval rate and is presented on Figure 26 as a function of TCOD loading
to the system.  The COD wasted can be estimated from the daily sludge
wasting data and the estimated COD/TSS ratio of 1.0 (Table 7), whereby
the mass of solids wasted per day (combined primary and sloughed solids
drawn from sludge hopper on a daily basis) is converted to an equiva-
lent oxygen mass.  This COD equivalent was then subtracted from the COD
removal rate and plotted as the net oxygen utilization rate, as shown
on Figure 26.  The oxygen utilization rate, as predicted by the kinetic
model is also shown on Figure 26, and corresponds closely with the
curve based on the COD balance.

     The shape of the Qฃ utilization curve on Figure 26 is similar
to the organic removal rate curve shown on Figure 33.  The flattening
of the rates at the higher influent loadings suggest the system is
reaching a limiting condition in its ability to transfer oxygen.

     The RBC model is capable of constructing oxygen and substrate pro-
files through the RBC stages and into the biofilm.  Figure 27 presents
an example of biofilm SBOD5 and DO profiles in  Stage 1 under  the
high loading condition of 91 g BOD5/d/m2  (18.6  Ibs  BOD5/
d/1,000 ft2).  The kinetic equations used in the model (see equa-
tions  1 and 2) cause a reduction in  substrate removal rate when the
ratio C/(C + C^)  drops significantly below unity.   Thus, if the DO
is less than the  Michaelis constant  (C  <  Cm) in regions of the bio-
film,  the reaction is limited by a deficiency of oxygen.   Figure 27  is
an example of this.  Substrate concentrations are in excess of 44 mg/1
SBOD5 throughout  the biofilm, and oxygen  concentrations dropped
below 0.001 mg/1  at biofilm depths in excess of 350y m.  Therefore,  for
all  practical purposes,  the active biomass depth in Stage  1 is 350 y m,
beyond which substrate removal  is minimal.

Active Biofilm

     Figure  28 presents  an estimation of  active biofilm depth for  each
stage  under high  and moderate loading conditions.   Only sector five  is
presented.  As indicated on Figure B-l  (Appendix B),  Sector 5 is that

                                   65

-------
             HIGH LOADING
                                       MODERATE LOADING
 oป
 E

2
LU
O
>
X
O

O
UJ
O
CO
0   100  200  300  400 500

    BIOFILM DEPTH (p.)
                                            100  200  300  400  500  600  700
                                                BIOFILM DEPTH (p.)
                          o>
                          E
                          LU
                          O
                          >
                          X
                          O

                          O
                          LU
                          O
                          en
      0   100 200  300  400  500

          BIOFILM DEPTH (yu.)



   HYDRAULIC LOAD= 0.14 m3/d/m2
 SOLUBLE  SUBSTRATE LOAD=10.4 g/d/m2
                                0    100  200  300 400  500  600 700

                                        BIOFILM DEPTH (JJL )



                                   HYDRAULIC LOAD=0.08 m3/d/m2
                                 SOLUBLE SUBSTRATE LOAD= 7.7 g/d/m2
             Figure  28.  Biofilm concentrations of substrate
                and  dissolved oxygen in successive stages
                                  68

-------
           SOLUBLE BOD5 WITHIN BIOFILM
                  69 mg/l B005

/

/
/

/


/

/
/

/

/
/

/
/
/
/
                                              44 mg/l B009
                                                   SUBMERGED
                                                    SECTORS
                                           AERATED
                                           SECTORS
0   70  140  210  280  350 420  490

       BIOFILM DEPTH (/x)
        DISSOLVED OXYGEN  WITHIN  BIOFILM
               1.9 mg/l D.O.
                                                   SEBMER6ED
                                                    SECTORS
                                          AERATED
                                          SECTORS
0   70  140  210  280  350  420  490

       BIOFILM DEPTH ()
                    STAGE 1 SUBSTRATE LOADING= 91 g /day /m
                                           (18.6 Ibs/day/IOOO ft'
 Figure  27.  Predicted substrate and oxygen profiles in biofilm
                            67

-------
      Temperature will affect several of the mechanisms involved in the
 kinetics of the fixed film process, including substrate removal rates,
 oxygen saturation values (hence, mass transfer driving forces), and the
 diffusivities oxygen and substrate.  As discussed earlier,  each of
 these kinetic parameters were corrected for temperature in  the kinetic
 model verification.

      The minimal impact of temperature on system performance is due to
 compensating effects of the various parameters affected by  temperature.
 Thus, the higher removal rates and diffusivities experienced in the
 summer were offset by the low dissolved oxygen levels  and the lower
 dissolved oxygen saturation value.  In the winter,  the lower kinetic
 removal rates were compensated by high influent dissolved oxygen con-
 centrations and higher dissolved oxygen saturation  values:   since dis-
 solved oxygen penetration was found to be the limiting factor (as
 graphically displayed on Figures 27 and 28),  imposition of  high dis-
 solved oxygen concentrations and/or higher dissolved oxygen saturation
 values will effectively increase the oxygen driving force,  increase the
 active film thickness and result in increased substrate removal.   Thus,
 although one would expect lower substrate removals  during the winter
 due to suppression of the kinetic removal rate,  the increased oxygen
 driving force provides effective compensation,  resulting in substrate
 removals similar to that of the summer.

      As an example, Figure 29 presents substrate, DO,  and active  film
 layer profiles through a four-stage system under the following  condi-
 tions:

           Influent SBOD5      =    IQQ mg/1
           Influent Flow       =    1,510  m3/d  (0.4  mgd)
           Influent DO         =0.0 mg/1
           Temperature         =    25oc

 The kinetic  coefficients k',  b',  a', and  the diffusivities  have all
 been adjusted  to equivalent  rates  at 25oc.  The  two solutions shown
 on  Figure  29,  however,  represent  oxygen saturation values of 8.4 mg/1
 and 11.3 mg/1.  As  can  be  seen,  by  simply  increasing oxygen solubility
 the oxygen driving  force  is  increased, increasing the depth of diffu-
 sion into  the  biofilm, with  subsequently higher  substrate utilization.

 Underflow Clarifier Performance

     Beyond  the fourth shaft  (refer to Figure 4), the RBC/Underflow
 Clarifier system effectively consists of two distinct sectors, the
 turnaround sector and the underflow clarifier sector.   Tracer analyses
 indicated that the entire turnaround sector behaved  as  a completely
mixed system.  The studies showed that the mixing characteristics of
 the  turnaround sector effectively reduced the volume nominally asso-
 ona™d Wlth the underflow clarifier from 100 to 75 m3  (26,000 to
 20,000 gallons), or by approximately 25 percent.  The nominal surface
area, i.e., that which is below the intermediate floor  is 72.8 m2
                                   70

-------
segment of the disc subsequent to emergence from the  liquid,  and  repre-
sents a near minimum active layer segment.   The data  show a  slowdown  of
the substrate removal reaction as the DO approaches limiting  condi-
tions.

     As shown on Figure 28, the active film layer is  between  300  and
600 ym, typically dictated by oxygen limiting conditions, and dependent
upon loading conditions.  This suggests that excessive growth of  bio-
film does not result in additional substrate removal.  This  was ob-
served in the late summer months when acid  dumps caused considerable
sloughing of the attached growth.  Effective treatment was still  main-
tained with a relatively thin biofilm.  A judgment as to whether  the
biofilm in excess of the active depth is useful is difficult.  While  it
adds considerably to the mass to be supported by the  shaft,  the large
solids inventory may serve to control net solids production by anaero-
bic endogenous respiration.

Seasonal Effects

     An important consideration  in the summer and winter evaluations
was the overall impact of  temperature on treatment efficiencies.   Aver-
age effluent  temperatures  were 26ฐC and 11ฐC during the  summer
and winter periods,  respectively, representing  a total differential of
15QC.

      Table 9  presents a portion  of the data obtained during  these per-
iods.  A complete data  tabulation is presented  in Table  3.

         TABLE 9.   COMPARISON OF SUMMER AND WINTER PERFORMANCE

                                         Summer           Winter
                                     7/18/77-9/25/77    12/1/77-2/24/78
Hydraulic loading
m3/d/m2
(gpd/ft2)
TBOD5 loading
g/d/m2
(lb/d/1,000 ft2)
RBC Influent BOD5 T
mg/1 S
Effluent BOD5 T
S
TBOD5 removal (%)
SBOD5 removal (%)

0.085
(2.08)

11
(2.3)
134
97
28
23
79
76

0.081
(2.0)

13
(2.6)
158
91
33
24
79
74
 The above results indicate that under equivalent loading conditions,
 similar removal efficiencies (as expressed by percent removal)  were
 experienced during both the summer and winter evaluation periods.
                                   69

-------
 (784 ft2).  Based on the estimated 25 percent reduction,  the  avail-
 able, or effective, surface area becomes 54.6 m2  (588  ft2).

      Figure 30 presents the correlation of  effluent  TSS as a  function
 of overflow rate, based on average observed data  from  each of the major
 sampling periods.  The correlation shown on the Figure, while not par-
 ticularly uniform, implies an allowable effective clarifier overflow
 rate between 22 and 26 m3/d/m2 (550 and 650 gpd/ft2) to ob-
 tain an effluent TSS less than 30 mg/1.  At Edgewater  this is equiv-
 alent to a hydraulic loading rate to the RBC of 0.065  to  0.08 m3/
 d/m2 (1.6 to 1.9 gpd/ft2),  assuming an effective  surface  area
 of 54.6 m2 (588 ft2).   The  overall average  TSS in the  fourth
 stage during the experimental program (based on thirty-eight  24-hour
 composite analyses) was 160 mg/1.  The percent removals shown on Figure
 30 are based on a fourth stage concentration of 160 mg/1.

      During the interim period between the  warm and cold  temperature
 evaluations,  i.e., October  and November 1977,  experiments were con-
 ducted to determine if the  settling characteristics could be  improved,
 thereby increasing the solids capture efficiency  of the underflow clar-
 ifier.  The tests centered  on evaluation of  chemical addition to the
 fourth stage mixed liquor,  relying on the mixing  provided by  the fourth
 shaft.

      A number of coagulant  and flocculant aids were screened  by stan-
 dard jar test procedures to determine an effective chemical additive,
 and  approximate dosage requirements.   These  included ferric chloride,
 alum,  lime,  combinations of ferric chloride  with  lime, alum with lime,
 and  a series of polymers.   The  tests  indicated that ferric chloride
 addition was the most  effective.   A series of  flocculant settling tests
 were then conducted to confirm  the effectiveness  of ferric chloride,
 using samples drawn from the  fourth stage mixed liquor.  The upper dis-
 play on Figure 31  demonstrates  the improvement in solids removal at a
 dosage of  20 mg/1  FeCl3,  as derived  from  the lab  scale settling
 tests.

      A full-scale  evaluation  was  undertaken by feeding FeCl3 di-
 rectly to  the  fourth stage.   The  solution was evenly distributed across
 the  tank  on  the  upstream  side of  the  fourth RBC shaft.   During the con-
 trol  period,  October 20  through November 9,   1977,  the flow was set at a
 relatively high  rate of  2,200 m3/d  (0.58 mgd), which represented a
 hydraulic loading  of 0.12 m3/d/m2  (2.95 gpd/ft2)  and an
 effective  secondary clarifier overflow rate of 40 m3/d/m2  (980
 gpd/ft2).  The  effluent  TSS during this period averaged 39 mg/1.

     The ferric chloride was metered to the  fourth stage from November
 10 through November 21,  1977 at dosages increasing from 20 mg/1 to 75
mg/1 FeCl3.  The average flow was 2,240 m3/d (0.593 mgd).   The
average effluent TSS during this time was 46 mg/1, indicating  no im-
provement in solids capture with addition of the  ferric chloride.   Sub-
sequent bench scale flocculant settling tests demonstrated that the
                                  72

-------
o>
ฃ

 in
O
O
GO
LU
CD

X
O _

O v.
LU 0ป
o

CO
o
LU
> E
P ฐ
o  -
< o:
_ LU
I 2
I -- 1
w LT
LU "•
 120



 100



 80



 60



 40



 20


   0
 5.0


 4.0



 3.0



 2.0



 1.0


   0
0.05


0.04



0.03



0.02



0.01



   0
                                                k's 0.3SS min'1


                                                0 = 0.69 mg Og/mq BOOj

                                                b Xy* 7.9mg Qz/mq- min


                                                Tป25ฐC

                                                Qs ISIO m3/d
                       D.O. SATURATION* 8.4 mfl/l

                       0.0. SATURATION. 11.3 mg/l
                I NF
                                    STAGE
       Figure 29.   Evaluation of  impact of dissolved
            oxygen  gradients  on substrate removal
                                 71

-------
 problem  was  attributable  to  inadequate mixing in the fourth stage.  The
 lower  display  on Figure 31 presents  these data.  Unless adequate agita-
 tion is  provided initially for  proper contact between waste solids and
 the  coagulant,  the  effect of chemical addition will be minimal.  The
 bench  scale  data on F.igure 31 suggests that ferric chloride effectively
 improves settling characteristics when applied under rapid mix condi-
 tions, followed by  a  period  of  slow mixing.

 RBC/Underflow  Clarifier Removal Efficiency Correlations

     Figures 32 and 33 present correlations of effluent TSS and organic
 removal  rates  with  the overall hydraulic and BODs loading rate, re-
 spectively (based on  effective  surface area).  The data represent aver-
 ages of  each of the indicated study periods.  As shown, a reasonable
 correlation  exists  with respect to hydraulic loading and effluent
 solids,  while  the organic loading rate is more appropriate in predict-
 ing  the  removal of  BOD5.

     As  discussed earlier, due  to compensating effects, temperature, as
 described by summer and winter conditions, was found to have minimal
 impact on removal efficiency.   In light of this, the correlations pre-
 sented on Figures 32  and  33 reflect actual conditions and have not been
 adjusted for differing temperatures.

 Solids Handling

     Figure  34  presents weekly average data relating to the inventory
 of influent, effluent, and waste solids.  These data indicate, as ex-
 pected,  increasing  inventories with increasing BOD5 removal rates.
 Addition of  the  effluent  solids and waste solids yields the total
 sludge wastage.   This is  correlated with the total BOD5 removal
 rate on  Figure  35.

     Figure  36  presents a correlation of net solids produced (computed
 by subtracting  the  influent solids inventory from the total sludge
 wastage) to  the  soluble BOD5 removal rate.  As shown, between the
 normal operating  range of 5 to 7.5 g SBOD5 removed/d/m2 (1.02
 to 1.53 lbs/d/1,000 ft2),  there was a net solids growth between 1.0
 and 7.5 g SS/d/m2 (0.20 and 1.53 lbs/d/1,000 ft2).

 Nutrients

     Tables  A-2 and A-5 tabulate the nitrogen and phosphorus analyses
conducted throughout the experimental program.  The nitrogen data are
 further summarized on Table 3.   The data confirm non-limiting condi-
 tions with respect to either nitrogen or phosphorus.   A prime objective
in the frequent analysis for the nitrogen series was  to monitor the
occurrence of nitrification,  especially in the warm temperature months
and in the latter stages.   As shown, nitrification  did  not  occur at any
time during  the entire experimental period.
                                  74

-------
CO
CO
2
LU
LL
LU
     50
     40
     30
     20
10
    LEGEND:
      I 3/22-4/6/77
      2 4/11-5/13/77
      3 5/23-6/30/77
      4 7/18-9/25/77
      5 12/1/77-2/24/78
                     OVERALL AVG TSS
                       RAW INF = I 70 mg/l
                       RBC INF = 125 mg/l
                      STAGE FOUR= 160mg/l
                           \
                                                   D
                                                   
-------
o
<ฃ>
               O
               to
       o
       CVJ
                                               o   —'
                                                          LU
                                                          h-
                                                          <
                                                          Ct
                                                      row  Q
                                                       ฃ <

                                                       ^ O

                                                        Q.
                                                      CVJ 0ป O
                                                   or
                                                   o
          I/6UJ   'SSI  lN3nidd3
                                                                              C W
                                                                              (0 t*

                                                                              O 4J
                                                                              •H C
                                                                              C (U
                                                                               i-H
                                                                              ^ U-l
                                                                       0 O
                                                                         4->
                                                                       c
                                                                       o >
                                       —  o —
                                          •a

                                          m
                                                 OQ

                                                 E
                                               M   W
                                                C  K


                                                O  QC
                                                      10
                                                O
                                                O  Z
                                                ffl  <
                                                a>  o
                                                .a  a:
                                                -  o
O
ro
O
CM
                                                   -Jo
                                                                              0
                                                                              U
                                                                              CM  O
                                                                              CO -H
                                                                              en T3
                                                                              •H  >,
          l/6uj   ' SSI
                                        76

-------
0ป

E
CO
CO
UJ
u_
UJ
     80
     60
     40
     20
                                               10/4/77


                                          Bench Seal* Flocculant
                                              Settling Test

                                             ( 4^ stage mixed

                                              liquor sample)
                          CONTROL NO
                          CHEMICAL ADDITION
0ป
E


CO
CO
h-

\-
z
UJ
u_
LU
      80
      60
      40
      20
                            20         30        40
                                    mVday /m2
                                  I        i	L
                                                    50
                                                                      60
0      200     400      600     800     1,000     1,200     1,400



                                                I/I2/78


                                         Bench Scale  Flocculant

                                              Settling Test

                                             (4i!ปstage mixed

                                              liquor sample)

                                         CONTROL
                                              YCON1KUL
                                          •20 mg/l Fed  'SLOW MIX ONLY
                                        20mg/l FeCI3 =  W RAPID MIX
                  10
                    20         30        40
                            m3/day /m2

                          I         I	I
                                                            50
                                                                      60
               200
                400
                                                1,000
1,200
1,400
            Figure  31.  Evaluation of  chemical  treatment
                      for improved solids capture
                                   75

-------
   o  o
UJ
o
<
ป-
(O
<



UJ
o
o
3
_l
to
                      o o\ o
                           o  o
                   CO
                o
                CO

                r-
                Z
                UJ
               o
               CO
               cc
o
?
o
8
                                             00
                                       CO
                                       o

                                       Ij

                                       O
                                       CO

                                       r-

                                       Z
                                       UJ
        o
        S
            o
o o
  o
  Xop/SS
o
o
CJ
                                     J	L_l
 o   o   o  o
 o   o   o  o
     ?U)   *  CM

  op/ss  sqi
                  Aop/ss

         J	ป    i    I   i
o o   o   o   o   o
  10   o   m   o   10
  CM   CM   —   —

                 o   o  o
                     c  o
                     CD.  (0   <

                     Aop/ss
                            o
                            o
                            
-------
                                            *•'   <
                                                a:

                                                o
                                            o   ?
                                            roซi. Q
                                            o   or
                                            -   Q
            o
            CM
                    Q08
(0
             1VAOW3H OINVOdO
in

1 * ซ
1 t-^ UJ
1 ^" ^^ I
@ H00 CD w —
V3|

i J^ -
RtSCS ฎ 1
io O "^ <\j ^l' fO

^^ "*^ ^* ^^ ^* ^w 1
* If) ซ0 ซ N ^^.

(M n PJ _ ^ K>
^ IO * to N ^! ^Z/ —
5^ _ pj (O * IO ^L
ki ^
\
1 1 I 1 1
CVJ —



0
CO
M

IO >ป
— o —
TJ
V.
IO
Q
20 .


E
o*
UJ —


o
IO

UJ
** I—
ฐฃ5
' o o:
o|i
(0^0
^^ ,^*
13
' tf>
CM ^^ ^J
t—J .__-
o 2
"•* ^
o ฐ* to
-5 a:
o

o
D 10 O IO O 10 O
O CV1 CM — —
                                                        C i
                     Q08
|
(O
1
in
1

-------
•a o
•j.\J
UJ
Jj
Or
Zw 2.0
0 C
h- 0
o o
ID 0
Q —
O ^
nr "0 1.0
™~ ^^
A. ^
co to
Q W
1 ^^

o - oo
CO u
H-
UJ
z

-1 0
15.0



- 10.0

CM
E

_

- ^ 5.0

CO
CO
0


— 00





•— -5O

NET SOLIDS PRODUCED =
TOTAL SLUDGE WASTAGE -
INFLUENT SOLIDS
—

Oo
8
0 0



o o

0 ฐ ฐfl 0
0 0
0 o 00ฐ
ฐ oo
o ww
o
0

NOTE:
DATA SHOWN ARE WEELY AVERAGES
1
























0 2.5 5.0 7.5 10.0 12.5
g SBOD5 REMOVED/d/m2

	 . 	 1 	 1 	 1 i i
           0.5       1.0       1.5       2.0
             Ibs SBOD5 REMOVED /d / 1000 ft2
                SBOD5 REMOVAL RATE
2.5
Figure 36.   Correlation of net solids
  production to  SBOD  removal rate
                 80

-------
                               SECTION 7

   ANALYSIS AND DISCUSSION - PROCESS DESIGN ALTERNATIVES  EVALUATION


     The extensive field study conducted  at Edgewater,  New Jersey, re-
sulted in the collection of a large amount of data to describe  the phy-
sical and biological performance of the RBC/Underflow Clarifier pro-
cess.  The data analysis and evaluation presented in Section 6  deter-
mined the concept of modifying primary tanks with RBC systems to be  an^
effective treatment sequence, capable of  accomplishing  secondary treat
ment effluent requirements under reasonable operating conditions.  This
section projects the results of this analysis to the development of
process design alternatives.  The RBC kinetic model, calibrated with
the Edgewater data, was utilized to develop design nomographs and to
project the impact of variations in operating conditions.  The surveys
can facilitate the preliminary design for upgrading similar municipal
wastewater primary treatment plants and are used in a subsequent sec-
tion  to develop a process design applicable to the Edgewater plant.

PRETREATMENT

      Observations and data  gathered  in the  study indicated a need for
pretreatment  to remove  grit,  trash,  and  floatables prior  to  the RBC
system.   Typically,  20  to  25 percent removals were accomplished  in the
pretreatment  sector  of  the  Edgewater system in addition  to  the  removal
of large  fibrous materials  on coarse screens.  The  influent  TSS concen-
tration to the RBC  system  averaged between 120 and  140 mg/1. Conserva-
tively, the nominal  overflow rates to accomplish this was estimated be-
tween 285 and 370 m3/d/m2  (7,000 to 9,000 gpd/ft2)  on
average,  with a peak rate  of approximately 500 m3/d/m2  (12,300
gpd/ft2).

      Several alternatives may be available at a  specific installation
 to provide pretreatment.  If the plant is not at hydraulic capacity,
 the removal accomplished by the existing screens/grit  chamber  may prove
 adequate.  If further treatment is required, this may  be provided by
 incorporating high-rate gravity settling (as with Edgewater) and/or by
 the installation of sieves or screens.  In the case of Edgewater, at
 the primary peak flow of 30,000 m3/d (8 mgd), the use  of one of the
 existing clarifiers to provide pretreatement would yield an overflow
 rate of  325 m3/d/m2 (8,000 gpd/ft2), which is well within
 the recommended range.
                                    81

-------
 ROTATING BIOLOGICAL CONTACTORS

      RBC fixed film systems function primarily in the removal of solu-
 ble organic material, measurable as soluble BOD5 and COD.   Thus the
 design of the system-is based on soluble organic loading and soluble
 effluent organic requirements.  As shown on Figure 33,  the rate of
 removal of TBOD5 is relatively linear with the rate of  TBOD5
 loading.  The removal of soluble BOD5 reaches a limiting rate,
 however, at the higher soluble (and total) BOD5 loading rates to
 the system.  These relationships suggest that the fraction of the
 TBOD5 influent loading associated with solids will be removed from
 the system by clarification and these removals are related more to the
 hydraulic loading of the system.  The soluble removals,  however, are
 directly related to biofilm kinetics and the ability of  the system to
 transfer sufficient oxygen.

      The design sequence assumes, based on the above, that the  second-
 ary clarification sector will provide adequate solids removal effici-
 ency and reduce TSS levels  to within a desired range.   The BOD5 as-
 sociated with these solids  can be computed from measured BOD5 to
 TSS correlations;  from this the required effluent soluble  BOD5  can
 be determined.  As an example, if the effluent solids are  to  average 25
 mg/1,  and the 6005:TSS correlation is BOD5 =0.5 TSS -  5,  the
 effluent BOD5 associated with the solids is 7.5 mg/1.   If  a similar
 25 mg/1  criteria is set for average effluent BOD5,  the  soluble
 fraction should not exceed  17.5 mg/1.

 Design Nomographs

     The design of a full-scale system  can be  facilitated  through mod-
 eling  techniques.   Single stage design  nomographs were developed  on  the
 basis  of the  kinetic model  verifications discussed  in Section 6.   These
 design curves were developed  from the  system evaluation  at  Edgewater
 and as such should not  be directly  applied  to  the design of systems  for
 tuea^eut ฐf  different  wastewaters.   The appropriate kinetic  parameters
 should be determined and  new  design nomographs developed for  any par-
 ticular  application.   The curves  are based  on an evaluation of a muni-
 cipal  wastewater system and may be  useful  in preliminary design appli-
 cations  and general  process sizing  for  the  treatment of  similar waste-
waters.
     The design of an RBC system should maximize BOD removals in each
stage by controlling the BOD loading on the media surface.  Maximizing
removals in each stage minimizes the total media surface area require-
ments, thereby minimizing the initial capital expenditure requirements
The design curves presented on Figure 37 utilize this design basis.

     Figure 37 shows the relationship between the applied soluble
BOD5 loading and resulting removal rates.  These curves were de-
veloped with the RBC model for a single stage by varying the waste
strength, hydraulic loading, and waste loading on the media surface
area.  The curves are based on the effective, or wetted, surface area
                                  82

-------
     2.0 -
UJ
h-
<
or
-J N
< 1.
> ซ•-
o o
5 8
UJ O
o 5
CD 7ป
UJ f
CD
-J
O
     1.5
      .0
     0.5
                   100% 50%
  PERCENT  REMOVAL
30%    20%
                                                              10%
           O
           •o
                                         INFLUENT SOLUBLE
                                         BOD9 (mg/l)
                                  BASED ON EFFECTIVE SURFACE AREA
                                  40       60
                                   g/day /m2
                                      10
                                                  15
                                Ibs/day/ 1000 ft2
                             SBOD5 LOADING RATE
                                                             20
         Figure 37.  Process design curves relating BOD5
               loading rates to BOD5 removal rates
                               83

-------
 of the media.  For a given influent waste concentration,  a point  is
 reached where a further increase in the BOD5 loading rate (or hy-
 draulic loading)  does not significantly increase BOD5 removal.  The
 design loading should not greatly exceed this point since the limit  for
 removal by the available media has been reached.  The percent removals
 begin dropping off significantly, resulting in an effluent concentra-
 tion ultimately approaching the influent concentration.   Effectively,
 the optimum design to maximize removal  and minimize area  would  dictate
 keeping the loading equal in each stage.  This means "pyramiding" the
 shafts; the greater number would be in  the first stage, progressively
 decreasing with each stage.  However, to achieve an effluent  concentra-
 tion without an infinite number of stages of decreasing size, practical
 limits dictate actual design loadings selected for the latter stages in
 a system.   The initial stages,  of course, could be loaded to  obtain
 maximum removals.

      When  dealing  with a specific application of upgrading primary
 treatment  plants through the installation of RBC's in existing  tanks,
 the waste  loadings  to each stage are not readily modified through vary-
 ing stage  sizes, since the stage sizes  are dependent  on the dimensions
 of the existing tankage.   As an example,  the stages at the  Edgewater
 plant were separated  with removable baffles,  allowing the  stage size
 and media  surface  area per stage to be  changed  only by their  placement.
 The system remained constrained by the  total surface  area  which could
 be fit to  the  available tankage.   This  resulted  in decreased  BOD5
 loading per  media  surface area  progressively through  the  system.  The
 decreasing BOD5 loadings  result  in decreasing  BOD5  removals.
 In order to  remain  in the practical limit  of number of stages and still
 achieve the  30 mg/1 criteria, a  higher  density media  with more discs
 and therefore  greater surface area per  shaft, can  be  installed in the
 latter stages.  Although  the increased  surface area further reduces the
 BOD loading  and resulting  BOD removal per media  surface area, total re-
 movals  are increased  with the greater overall surface area.  The
 higher-density  media  can  only be  employed where waste loadings are suf-
 ficiently  low  so that media  clogging is not  a problem.

      Figure  38  presents a  series  of single stage solutions based on a
 temperature  of  20oC,  and an  influent DO of 0.0 mg/1.  The  reaction
 kinetics described and verified  in  the previous section were used  in
 the development of the curves.  At  the appropriate influent soluble
 BOD5  and hydraulic loading rate  the resulting effluent soluble
 BOD5  is determined.   The predicted effluent  SBOD5 concentration
 from  the first  stage becomes the influent SBOD5 to the second
 stage.  The  iterative use of the design curves allows the  prediction of
 the effluent from a multi-stage RBC system.

     To illustrate the use of Figure 38, consider the following  exam-
ple :

     Influent Waste     Q = 9,460 m3/d  (2.5 mgd)
                        TBOD5 =200 mg/1
                        SBOD5 =120 mg/1


                                   84

-------
0ป
E
Q
O
OQ

UJ
_l
CD
K
Z
UJ
u.
UJ
                                                HYDRAULIC LOADING
            I NF D.0.= 0.0 mg/l
            T= 20ฐC
            20   40   60   80  100  120   140   160  180  200  220  240  260

                       INFLUENT  SOLUBLE BOD5, mg/l
      Figure 38.  Single stage process design solutions relating
        effluent SBOD  to influent SBOD5 and hydraulic loading
                                   85

-------
                         DO  =  0.0 mg/1
                         Temperature =  20oc
      Plant  Capacity      6 rectangular  tanks
                         Each  Tank:  5  shafts
                                    6,000 m2  (64,500 ft2)/shaft
      The  effective hydraulic  loading rate to  each stage would be 0.26
 m-Vd/m2  (6.4 gpd/ft2).   Entering Figure 38 at an influent
 SBOD5 of  120 mg/1, the effluent SBOD5  from Stage 1 would be 87
 mg/1. The  figure is re-entered at the influent of 87 mg/1 from Stage
 2,  and so on.   The final effluent from Stage  5 would be projected at 19
 mg/1  SBOD5.  if  the secondary clarification zone is effective., and
 allows an effluent SS less  than 30 mg/1 on average, the criteria of 85
 percent BOD5 removal (effluent BOD5 =  30 mg/1) would be met in
 this  particular  example.

 Influent  Dissolved Oxygen Effects

      A third design curve,  Figure 39,  presents the effect of influent
 DO  on the treatment efficiency of the  RBC system.  The presence of DO
 in  the influent  provides an additional source of oxygen for the bio-
 film,  and may additionally allow a higher concentration gradient, en-
 hancing mass transfer into  the biofilm.  A discussion of this may be
 found in  Section 6.  As  indicated on Figure 39, the greater impact oc-
 curs  at the higher substrate levels.   At an influent SBOD5 of 150
 mg/1,  an  influent DO of  6.0 mg/1 may allow approximately a 12 percent
 improvement in BOD5 removed in the initial stage.  In the earlier
 example,  at an influent  DO of 6.0 mg/1, the effluent from the first
 stage  would be 83 mg/1,  versus an effluent BOD5 of 87 mg/1 if the
 influent  DO is 0.0 mg/1.

 Comparison of Predicted and Observed RBC Removal Efficiencies

     The  operating conditions and equivalent removals experienced dur-
 ing the Edgewater field program were evaluated using the design Figures
 38 and 39.  Again, these were developed with the model, based on kinet-
 ic parameters determined during the study.  Table 10 presents the ob-
 served average  effluent SBOD5 and the  predicted effluent.   The
operating conditions  for each experimental period are also summarized
in Table 3.

     TABLE 10.   COMPARISON OF OBSERVED AND PREDICTED RBC EFFLUENTS

Study period

Low loading (3/22-4/6/77)
Moderate loading (4/11-5/13/77)
High loading (5/23-6/30/77)
Warm temperature (7/18-9/25/77)
Cold temperature (12/1/77-2/24/78)
Observed
eff. SBOD5
(mg/1)
10
22
31
23
24
Predicted
eff. SBOD5
(mg/1)
7
21
31
23
19
                                  86

-------
o

UJ
DC
O
CO
UJ
cn
<
UJ
oc
o
z
UJ
o
a:
UJ
a.
16



14




12



10



 8



 6



 4



 2



 0
Qs 1500 mVdoy
T= 20ฐC
    INFLUENT

DISSOLVED OXYGEN

    6 mg/l
                                    3 mg/l
                                     mg/l
                  50          100          150         200

                     INFLUENT SOLUBLE BOD5,  mg/l
                                                           250
       Figure 39.   Single stage  process design curves relating

          the effect of dissolved oxygen  on SBOD_ removals
                                 87

-------
      As  shown,  the  effluents  predicted  by  the design  curves closely
 approximate the observed  data,  especially  under  the range of loading
 conditions determined  optimum for  the system.

 Secondary Clarification

      The pilot  study evaluation at Edgewater indicated  that a limiting
 process  condition in the  operation of the  system was  the solids removal
 efficiency accomplished by  the  secondary clarification  zone.  The ex-
 perimental data determined  the  maximum  effective overflow rate to ob-
 tain an  effluent SS  of 30 mg/1  was 26.5 m3/d/m2  (650  gpd/
 ft2).  This is  shown on Figure  30.   Thus,  the hydraulic loading to
 the  RBC  system  may be limited by the effective surface  area available
 in the secondary clarification  zone.  The  tracer analyses (Section 6)
 determined this to be 54.6  m2 (588 ft2) in the Edgewater system
 (a 25 percent reduction from  the nominal area of 72.8 m2).  The
 maximum  flow to the  system  would therefore be 1,450 m3/d (0.38
 mgd) .

     The flow of 1,450 m3/d (0.38  mgd)  would be equivalent to a hy-
 draulic  loading of 0.07 m3/d/m2  (1.93 gpd/ft2) for the
 Edgewater system.  At an  influent  soluble  BOD5 of 90 mg/1, the de-
 sign curves on  Figure 38 would  project  an  effluent.SBOD5 of 19
 mg/1.  Adding the BOD5 associated  with  the 30 mg/1 TSS, the
 TBOD5 is projected at 26.5 mg/1.   Although this will meet criteria,
 the  secondary clarifier is effectively  limiting the design of the RBC
 system to the 18,270 m2 (43,000  ft2) effective media  surface
 area.  Denser media, which would allow  a higher organic loading could
 not  be considered since the clarifier would become hydraulically over-
 loaded.

     To  maximize  the organic  loading to the RBC sector and minimize the
 RBC  surface area requirements, consideration must be given to the de-
 sign of  the underflow clarifier  system  to accomplish efficient solids
 capture.   This  may involve provision of additional secondary clari-
 fiers, the  use  of chemical addition to  improve the efficiency of the
 existing  underflow clarifiers, or  the use of rapid sand filters as a
 final treatment  step.

 Other Process Considerations

 pH —

     As with any biological system, effective pH control in the range
 of 6 to 8 is a necessity.   Extreme pH drops at Edgewater during August
 and September 1977 caused  sloughing of the biofilm and loss of  treat-
ment efficiency for a period of days.  Depending on the type of system,
 especially  in highly industrialized areas,  pre-neutralization facili-
 ties may be required.
                                  88

-------
Pre-aeration —

     Due to the nature of the system (decreasing loading with progres-
sive staging) the provision of pre-aeration to the RBC/Underflow Clari-
fier process would probably not be effective in improving treatment ef-
ficiency.

     A simulation was run to demonstrate the effect of pre-aeration
during summer conditions.  Table 11 presents soluble BOD5 and DO
concentrations in each stage under moderate loading conditions.

                 TABLE 11.  EVALUATION OF PRE-AERATION
                                   1,550 m^/day (0.409 mgd)
     Hydraulic loading             0.085 m3/d/m2
                                   (2.08 gpd/ft2)
     Soluble BOD5 loading          8.26 g SBOD5/d/m2
                                   (1.69 Ibs SBOD5/d/l,000 ft2)
     Temperature                   26.1oc
     02  saturation                 7.9 mg/1
     Influent  soluble BOD5         100 mg/1

     Influent  dissolved  oxygen  (mg/1)          0*0
Soluble



* \-J
BOD5 stage 1
2
3
4
Dissolved oxygen stage










1
2
3
4
78
58
43
27
0.6
0.7
1.3
2.0
75
56
41
26
2.2
1.2
1.5
2.1
 As shown, the impact of pre-aeration is relatively minimal  on a multi-
 stage system.  The systems,  beyond the first stage, become  increasingly
 similar in dissolved oxygen levels with each stage.  Thus,  BOD5 re-
 movals are relatively the same, except in the first stage which exper-
 ienced the greater Qฃ differential.

 Filamentous Organisms

      The recurring appearances of filamentous organisms did not appear
 to affect the treatment efficiency of the Edgewater system.  If, how-
 ever, under certain circumstances they create a problem, the use of  hy-
 drogen peroxide appeared to an effective remedy.  Also, in  the specific
 case of beggiatoa, the addition of an alternate oxygen source (other
 than sulfate), such as nitrate, or pre-aeration, may prove  to be an
 effective preventive during the warm summer months.
                                   89

-------
Staging Baffles

     Baffles effectively stage the RBC system into a series of com-
pletely mixed tanks.  Their consideration in process design should be
to the extent that each tank, as defined by the baffles,  should be
close to completely mixed.  At Edgewater, a stage with one or two
shafts was shown to be completely mixed.  It is probable  that a stage
with three shafts would also be shown completely mixed.

     Baffling will also create higher velocities along the intermediate
floor and minimize solids accumulation.  In line with this, placement
of baffles beyond two shafts may not be appropriate.  The underflow
clearance is also an important consideration in the installation of the
baffles.  A clearance of 5 cm (2 in) was found to be effective at Edge-
water, inducing sufficient wastewater velocity to keep the intermediate
floor free of significant sludge deposits.
                                 90

-------
                               SECTION 8

             PROCESS DESIGN EVALUATION OF EDGEWATER SYSTEM


     The following example is presented to demonstrate the  use  of  the
design curves and to further discuss process considerations relating to
the RBC/Underflow Clarifier system.  Since the curves are based on the
experimental program at Edgewater, the example describes the process
requirements to upgrade the existing Edgewater facility to  secondary
treatment capabilities, based on the present-day waste characteriza-
tion.  Subsequent sections (9 and 10) discuss plant design  considera-
tions, and develop costs related to design of the Edgewater system.

WASTE CHARACTERIZATION - PRESENT CONDITIONS

     Because Edgewater is a combined system, the variations in flow and
pollutant strength do not coincide, i.e., at higher storm flows the
waste strength becomes highly diluted.  For this reason, the loadings
to the system do not show the high variations exhibited by the flow and
concentrations.  Peak organic loading conditions are not a direct mul-
tiplication of peak flow and peak concentrations, since it is assumed
they would not occur simultaneously.  Actual design of the RBC system
is based on the average loadings to the system, while the clarifier
design is considered on the basis of peak flows.

     The waste characterization summarized on Table 12 is based on
cumulative normal distributions of the data obtained during the experi-
mental program.  Daily average is the mean occurrence, while the peak
monthly average is  taken as the 91.5 percent occurrence.  The 98 per-
cent occurrence represents the peak 7-day average.
                                   91

-------
   TABLE 12.  EDGEWATER WASTE CHARACTERIZATION:  PRESENT CONDITIONS

Flow, m3/d (mgd)
TBOD5, mg/1
SBOD5, mg/1
TSS, mg/1
Daily
average
9,800 (2.6)
145
90
170
Peak monthly
average
13,600 (3.6)
215
130
260
Peak 7 -day
average
15,900 (4.2)
250
150
300
TBOD5 loading, kg
  TBOD5/d (Ibs/d)      1,620 (3,570)   2,120 (4,670)  2,490 (5,480)
SBOD5 loading, kg
  SBOD5/day (Ibs/day)    855 (1,885)   1,320 (2,900)  1,550 (3,400)
TSS loading, kg TSS/d
  (lbs/d)              1,620 (3,570)   2,630 (5,790)  3,130 (6,900)
Temperature                 Hoc (winter) to 26oc (summer)
Influent DO (mg/1)           5.0 (winter) to 1.0 (summer)
EFFLUENT REQUIREMENTS

     The Federal standards and requirements based on the Federal Water
Pollution Control Act Amendments of 1972 (PL 92-500) call for monthly
average 6005 and SS concentrations less than or equal to 30 mg/1,
or a percent removal equal to or greater than 85 percent, whichever al-
lows the greater treatment.  Additionally, weekly average BOD5 and
SS concentrations must not exceed 45 mg/1.  Effluent limitations based
on percent removals are more stringent for wastes having a low influent
BOD5, as is the case for Edgewater.  The effluent criteria which
would apply to Edgewater under the influent waste characterization de-
scribed in Table 12 are presented on Table 13.

               TABLE 13.  ESTIMATE OF EFFLUENT CRITERIA
          (Based on Waste Characterization Shown on Table 12)


Total BOD5
Total SS
Soluble BOD5
Daily
average
22
25
14
Peak monthly
average
30
30
20
Peak 7 -day
average
45
45
27
• 	 — 	 	 	
     The daily average BOD5 and TSS are limited by the 85 percent
removal criteria, while the concentration limitations govern the allow-
able peak monthly and peak 7-day BOD5 and TSS levels.  An equiva-
lent soluble BOD5 is shown; it was estimated by subtracting  from
the total the BOD5 associated with the solids (Table 7).

PRETREATMENT

     The results of the Edgewater study indicated  that the influent  to
the RBC sector should not exceed 120 to 140 mg/1 suspended solids.   A

                                  92

-------
single primary clarifier at Edgewater would  be  used  to  provide high
rate primary treatment for the entire plant  flow.  The  monthly average
overflow rate would be 170 m3/d/m2 (3,600 gpd/ft2),  with a
peak storm flow overflow rate of 340 m3/d/m2 (7,200  gpd/
ft2).  Figure 12 shows that within this range,  20  to 25 percent  TSS
removals can be expected.  No removals of BOD5  are assumed  through
this pretreatment step.

SECONDARY CLARIFICATION

     Figure 30 presents the relationship of  effluent TSS as a  function
of effective overflow rate developed from the experimental  program.
The designs projected on Table 14 are based  on this  figure.

TABLE 14.  UNDERFLOW CLARIFIER PROCESS DESIGN REQUIREMENTS  AT  EDGEWATER

                             Daily    Peak monthly    Peak  7-day
                            average      average        average

Required effluent SS
criteria (D, mg/1           25             30           45
Required effective overflow
rate  (2), m3/d/m2            23.5           26.5         35
(gpd/ft2)                  (570)          (650)         (860)
Actual  flow  (3),
m3/d  (mdg)                 9,800  (2.6)    13,600 (3.6) 15,900 (4.2)
Required effective inter-
mediate floor area, m2       420             510          450
(ft2)                     (4,560)         (5,540)      (4,890)
      (1)   From Table  13.
      (2)   From Figure 30.
      (3)   From Table  12.

 The  controlling  condition  is  the peak monthly average, whereby a total
 effective  surface  area of  510 m2 (5,540 ft2) is required.  The
 effective  surface  area in  the Edgewater system was estimated at 54.6
 m2  (588 ft2)  per tank.  With  four available tanks, the above
 design would  indicate an additional 290 m2 (3,120 ft2) of ef-
 fective surface  area  is required.

      The test module  used  at  Edgewater could be redesigned to provide a
 greater surface  area. The intermediate floor can be extended to a
 total length  of  19.8  m (65 ft), to allow a clearance of  1.5 m (5 ft)
 for  the turnaround and scraper mechanism.  The false floor area in this
 case would be 86 m2 (930 ft2).  Assuming 75 percent effective
 use  of the available  surface  area, the effective surface area would be
 64.5 m2  (700  ft2), and the additional surface area requirement
 would be reduced to 250 m2 (2,670 ft2).  Additional improve-
 ments in the  hydraulics of the turnaround/clarifier sector to allow 100
 percent utilization of the clarifier would reduce the  additional area
 requirement to  165 m2 (1,770  ft2).  Note that these assumptions

                                    93

-------
are based on an evaluation of the Edgewater underflow clarifier, with a
depth of 4.5 ft.  Deeper clarifiers may exhibit different characteris-
tics.

RBC ORGANIC REMOVAL

     Four primary clarifiers would be available for conversion to the
RBC system at the Edgewater plant.  Maximum use of the tankage would
allow four 4.1 m (13.5 ft) shafts (3.65 m diameter) per tank.  High-
density media would be installed in all but the first shaft in each
tank and conventional density media would be installed in the 'first
stage.  Each shaft would be 0.46 m (30 in) above the water surface.

     Using Figures 38 and 39, the effluent resulting from this configu-
ration of the four-tank system would be computed as shown on Table 15.
The flow and hydraulic loading are derived from the stated soluble
BOD5 loading and concentrations.  As shown, the projected effluent
SBOD5 is substantially higher than the required SBOD5.

     Figure 40 presents the solutions for a varying number of tanks
based on the design curves shown on Figures 38 and 39.  For the partic-
ular application described above, the soluble effluent BOD5 criter-
ia under peak monthly conditions would be met with a total of nine
tanks, each with four RBC shafts and a total effective media surface
area of 22,600 m2 (243,000 ft2) per tank.  The total nominal
media surface area per tank would be 27,300 m2 (294,300 ft2).

     Assuming extension of the intermediate floor to provide an effec-
tive surface area of 64.6 m2 (695 ft2) per tank, nine tanks
would provide a total surface area (effective) of 580 m2 (6,250
ft2). This would be in line with the required secondary clarifier
surface area under peak monthly flow conditions as shown on Table 14.

SUMMARY OF PROCESS DESIGN EVALUATION

     The process design of both the underflow clarifier and the RBC
sectors was controlled by the peak monthly average condition at Edge-
water.  The design is summarized on Table 16.  A total of ten tanks
would thus be necessary at Edgewater, one for high-rate pretreatment,
and the remaining nine modified or newly constructed as RBC/Underflow
Clarifier processes.

     The total primary tankage surface area presently at Edgewater is
465 m2 (5,000 ft2).  This is equivalent, at an average flow of
9,500 m3/day (2.5 mgd) to a primary overflow rate of 20.4 m3/
d/m2 (500 gpd/ft2).  By doubling the tankage, the equivalent
overflow rate is reduced to 10.2 m3/d/m2 (250 gpd/ft2).
Such an analogy becomes useful for extrapolation of the Edgewater
results to a similar primary treatment plant.  If a plant is designed
for an average primary overflow rate of 30.6 m3/d/m2 (750 gpd/
ft2) the plant tankage would need to be tripled to accommodate
sufficient RBC media surface area.

                                   94

-------
     TABLE 15.   PRELIMINARY DESIGN OF
                EXISTING TANKAGEU)
            EDGEWATER MODIFICATION USING
Influent Flow(2),
         (mgd)
Hydraulic LoadingO)
  m3/d/m2
  (gpd/ft2)
     Overall
     Stage 1
     Stages 2, 3 & 4

TBOD5 Loading Rate,
  g/d/m2
  (lbs/d/1000 ft2)

SBOD5 Loading Rate,
  g/d/m2
  (lbs/d/1000 ft2)

Influent  Soluble
  BOD5
Temperature  (C)

Dissolved Oxygen  (mg/1)

Soluble  BOD5  (mg/1)
      Stage  1
      Stage  2
      Stage  3
      Stage  4

Soluble  BOD5
   Requirement(4)
  Daily
 Average

9,460
(2.5)
0.1 (2.57)
0.59 (14.5)
0.38 (9.4)
15.2
(3.1)
 9.5
 (1.9)
 90

 20

  3.0
 77
 59
 45
 33
 14
Peak Monthly
   Average

  10,200
  (2.7)
 0.11 (2.77)
 0.64 (15.7)
 0.41 (10.1)
 23.5
 4.8)
  14.6
  3.0)
  130

   20

    3.0
  114
   92
   73
   59
  20
Peak 7-Day
 Average

   10,200
  (2.7)
 0.11 (2.77)
 0.64 (15.7)
 0.41 (10.1)
 27.5
 (5.6)
  17.1
  (3.5)
  150

   20

    3.0
  134
  109
   87
   69
  27
      (1)  One primary clarifier is  converted  to  high  rate  system.   Re-
           maining four are used for RBC conversion.
      (2)  Computed from Organic Loading and Concentrations on  Table 12
      (3)  Effective surface area Stage 1 = 4,000 m2  (43,000
           ft2);  Stages 2,  3 and 4 = 5,200 m2  (67,000  ft2);
           Total  Surface Area/Tank - 22,600 m2 (244,000 ft2).
      (4)  From Table 13.
                                   95

-------
 oป
 E

 Jo
o
O
CD

LU
-J
CD
U
-I
O
en

i-
z
LU
LU

O
LU
I-
O
LU
a.
X
LU
0\J


70

60



50
40



30


20




10






0
FLOW= 10,200 mVdoy (2.6 MGD) NFLUENT
4 STAGES /TANK SBODS
INFLUENT DISSOLVED OXYGEN = 3.0 mg/l PEAK
ALL STAGE DISSOLVED OXYGEN* 2.0 mg/ 1 7-dซป
— * AVERAGE

•Mป



—


/
/
/
/ /

i J
/
A
ESTIMATED /
SOLUBLE BOD5 /
_ REQUIREMENTS
PEAK 7-doys 27 mg/l /



/

*
PEAK MONTHLY" 20 mg/l


/

AVERAGE DAILY: 14 mg/l










/






\
/
/
/



/

<0
^
^
Z
X
(A

V




J
/

a>
H
2
X

X


H
z
X
(A





1
/




^
/
/
s

at

z
(A







1
/
/



S
/
S "


Ot
Z
3^
O>








	 L
(150 mg/l)
PEAK
MONTHLY
AVERAGE
(130 mg/l)


DAILY
AVERAGE
(90mg/l)
45 mg/l

z
A
30 mg/l


22mg/l
NPDES
REQ'D
TBODg






                 500
1,000
                                     1,500      2,000      2,500      3,000
                                   ms/day
               O.I     0.2     0.3     0.4     0.5

                                     MGD

                          EQUIVALENT FLOW/TANK
                          0.6
0.7
                                          0.8
              Figure 40.   Process  design at Edgewater
                                 96

-------
TABLE 16.  PROCESS DESIGN SUMMARY AT EDGEWATER UNDER PRESENT  CONDITIONS
Process conditions:
  Peak monthly average
     TBOD5 loading                  2,120 kg/day (4,670 Ibs/day)
     SBOD5 loading                  1,320 kg/day (2,900 Ibs/day)
     SBOD5                            130 mg/1
     Temperature                       20oc
     Flow (based on loading)       10,200 m3/day (2.7 mgd)
     Influent DO                        3.0 mg/1
     Flow to clarifier             13,600 m3/day (3.6 mgd)

Process design parameters:

  TBOD5 loading rate               10.4 g/d/m2
      D                              (2.1 lb/d/1,000 ft2)
  SBODs loading rate                6.5 g/d/m2  (effective)
                                     (1.3 lb/d/1,000 ft2)
  Equivalent hydraulic  loading rate     0.05 m3/d/m2
                                     (1.2 gpd/ft2)
  Clarifier overflow  rate  at  peak
     Monthly Hydraulic  Flow         23.5 m3/d/m2

 Process design  (using existing Edgewater  tank design):

  Total nominal RBC media
      Surface  Area                 246,000 m2
                                      (2.65  x  106 ft2)
  Total  effective RBC media
      surface  area                 203,400 m2
                                      (2.2 x 106 ft2)
   Shafts/tank                           4
   Total  RBC tanks                       9
   Total  intermediate floor
      surface  area                     580 m2  (6,200 ft2)
                                   97

-------
 PROCESS DESIGN MODIFICATIONS

      Specific improvements  can be made  in  the design of the Edgewater
 plant which may result  in a reduction of total  required tankage.  Two
 methods suggested are aeration to DO levels  of  5.0 mg/1 throughout the
 system, and the use  of  chemical treatment  to improve solids capture
 efficiency.

      Aeration can be provided  by a  supplemental air supply.  Although
 not evaluated directly  during  the Edgewater  study, the potential impact
 of interstage aeration  was  simulated by the  use of the design Figures
 38 and 39.   The results were superimposed  over  results of the initial
 Edgewater design example  (Figure 40) and are displayed on Figure 41.
 The simulation indicated  that  provision of interstage aeration alone
 did not significantly improve  the design.

      Tests  were conducted during the study which indicated that the ad-
 dition of FeCl3 to the  four stage mixed liquor would significantly
 enhance the settleability of the solids.   The bench scale tests indi-
 cated, however,  that it was necessary to provide a sufficient period of
 agitated contact  between the waste  and  coagulant prior to the clarifi-
 cation zone.   The results of these  studies (Figure 31) showed that
 within the  clarifier operating  range of 20 to 25 m3/d/m2 (over-
 flow rate),  chemical addition  (20 mg/1  FeCl3) would allow an efflu-
 ent TSS of  15 to  20  mg/1.

      At  Edgewater, the  rapid mix zone would  need to be provided to as-
 sure efficient  chemical treatment.  Alternatives may involve injecting
 the FeCl3 solution directly above the air header if supplemental
 air is being  provided or by installing a separate baffled stage on the
 extended intermediate floor, with adequate mechanical mixing.

      If  the effluent solids are maintained at 15 mg/1, soluble BOD5
 effluent requirements change significantly.  These are shown on Figure
 41.   The BOD5 associated with the 15 mg/1 TSS is assumed to be 3
 mg/1  (Table 7).   Thus the daily, peak monthly,  and peak 7-day average
 SBOD5  requirements become 19,  27 and 42 mg/1, respectively.  As
 shown  on Figure 41,  the peak monthly condition again governs,  but the
 tankage  requirement  for the RBC system is now reduced to seven tanks
 (vs. nine in  the  initial design), assuming provision of supplemental
 air.

     The use of seven tanks would allow an effective clarifier surface
area of  450 m2 (4,850 ft2).   At the  peak monthly flow of 13,600
m^/d  (3.6 mgd) the effective clarifier overflow rate would  be  30
m3/d/m2  (740 gpd/ft2).   Figure 31 indicates that with ade-
quate chemical treatment,  effluent TSS criteria  will be met.
                                   98

-------
 10
O
O
CD

LU
_l
CD
Z)
_l
o
CO
"Z.
LU
Z)
_J
li-
lt.
LU

O
LU
h-
o
LU
CL
X
LU
80




70



60





50



40




30






10


n

FLOW= 10,200 mVdoy (2.6MGO) INFLUENT
4 STAGES /TANK SBOD5
PEAK
LEGEND^ 7- day
_ INF D.0.= 3.0 mg/l AVERAGE
ALL STAGE D.O. = 2.0mg/ yj
	 INF D.0.= 5.0 mg/l /t
ALL STAGE D.O. = 5.0 mg/ / /
— / /
/
/ / /
>
ESTIMATED /
SOLUBLE 80D5 />
_ REQUIREMENTS /'
(REO'MTS SHOWN IN PARANTHESES / /
ASSUME CHEMICAL TREATMENT TO >
AN EFFLUENT TSS= ISmg/l ) /
(PEAK 7-doy = 42 mg/l) //
"" //
A

//'
// ,

PEAK 7-doys 27 mg/l /
(PEAK MONTHLY" 27 mg/l) /
i/^
PEAK MONTHLY^ 2O mg/l f/
(AVERAGE DAILYa 19 mg/l) /'
AVERAGE DAILY s 14 mg/l





1 1


>
p
(O
z
Ui

/ /
/
''

/
'

0
•>
(A


f /
/ .
/ /
( /
t
,
— s

'
~+
H
z
X

-------
                               SECTION 9

                      PLANT DESIGN CONSIDERATIONS
GENERAL
     There are many ways in which a primary treatment plant may be up-
graded  to secondary treatment by using the RBC/Underflow Clarifier
process.  One of them consists of adding new tanks containing the RBC
units,  followed by new secondary clarifiers.  Another scheme consists
of providing pretreatment by using rotary screens, stationary sieves or
settling tanks with high overflow rates, followed by the RBC units in
new tanks and by secondary settling provided in the existing clari-
fiers.  In plants where there are multiple settling tanks, it may be
possible to use one of them for pretreatment, install RBC units in new
tanks and use the remaining existing tanks for secondary settling.
Some deep primary settling tanks could be converted to the RBC/Under-
flow Clarifier scheme by the installation of an intermediate floor.
This section discusses this last method and presents some examples and
costs.

PRETREATMENT

     Proper performance of the RBC process requires efficient grit,
trash and floatables removal to prevent possible buildup of solids on
the intermediate floor and clogging of the media openings.  Grease con-
centration up to 200 mg/1 (as hexane solubles) will not reduce RBC
treatment efficiency.(4)

     During this study the comminutor and grit collector facilities
provided proper removals at low plant flows only;  during high plant
flows these facilities were bypassed by part of the flow.  Efficient
grit and trash removal was obtained by creating a high-overflow-rate
settling tank.  Overflow rates ranging from 204 to 725 m3/d/m2
(5,000 to 18,000 gpd/ft2) produced average removals of 25 percent
and four percent in SS and TBOD5, respectively.  Manufacturers of
rotary screens and stationary sieves claim similar or better removals
for their units when used for pretreatment without previous grit re-
moval.  Efficiencies are related .to the screen opening selected.

PRIMARY TANK MODIFICATIONS

     Installation of RBC units in existing primary settling tanks re-
quired several modifications to the tanks.  Figures 3 and 4 present a
cross-section of the primary settling tanks before and after the in-
stallation of RBC units.   Modifications to existing tanks may differ

                                 100

-------
completely from those required  in Edgewater, but  in general will con-
sist of:

     (1)  Sludge Collecting Mechanism.   The division  of  the tank cre-
          ated by the intermediate floor requires that the chain sludge
          collectors operate in the sedimentation zone with the flights
          return located at about 0.90  m (3 ft)  above the tank floor.
          Other types of sludge collectors such  as the travelling
          bridge and the rotary collectors must  be completely removed
          and replaced by chain collectors.   Cross-collectors may  or
          may not have to be removed, depending  on the dimensions  of
          the tanks and the space required by the RBC units.

     (2)  Scum Collection Equipment.  Scum-collecting arms, troughs,
          revolving skimming pipes, etc., must be removed.  Scum re-.
          moval must be accomplished by pretreatment  facilities.

     (3)  Effluent Collection Launders.  Some tanks are  provided with
          launders, troughs or weirs that project toward the  tank  or
          are installed in the periphery of  the  tanks.   This  equipment
          must be removed.

     (4)  Cross-Tank Beams.  In general, it  is necessary to remove the
          cross-tank beams and replace them  with new beams.  Cross-beams
          usually do not have the separation required for installation
          of  the RBC units, and generally do not have sufficient width
          to  allow proper  installation of covers and baffles  leaving
          adequate separation between covers.  New cross-beams are
          usually installed in pairs to allow the installation of
          baffles between  them.

     (5)  Intermediate Floor.  An  intermediate floor must be installed
          to  separate the  two  zones  of the tank.  The intermediate
          floor must be adequately supported, since  the sludge-collec-
          ting mechanism may require service  from time  to time.  The
          intermediate  floor must  be installed so as not to allow in-
          termixing  or  short-circuiting  of the sewage.

     (6)  Sidewalls.  When multiple  tanks are to be  upgraded by the
          installation  of  RBC  units, it  may be necessary to change the
          design of  the partition walls  in order to  provide adequate
          space for  the support  of bearings and  motors.  Interior can-
          tilever walls (T-shape)  are  not recommended,  since they pro-
          vide spaces  that may create  short-circuiting.  Figure 46 il-
          lustrates  this problem.   In  tanks with multiple bays, it may
          be necessary  to  separate the flow  streams  by  separating the
          bays with complete  sidewalls.   This may, in some cases, re-
          quire relocation of  interior columns,  which represents  a com-
           plete redesign of the tanks.

      (7)   Baffles.  Interstage baffles between  adjacent shafts must be
           installed.  Since there are  periods in which  it may be  desir-

                                     101

-------
           able to remove baffles between two stages,  it is important
           that these baffles be easily removed.   Normally, the baffles
           should  be  installed  to  provide underflow.   Installation of
           baffles providing  overflow between stages requires the in-
           stallation of  fillets to eliminate dead zones where  sludge
           may  accumulate.  If  built from concrete, these fillets will
           represent  a heavy  weight to be supported in addition to the
           intermediate floor.  These two types of arrangements are
           shown on Figure 42.

           Rearrangement  of Influent and Effluent Channels and Weirs.
           As can  be  seen in  Figure 4, the influent and effluent chan-
           nels are located in  the same side of the tank.  This requires
           changes in the influent line and installation of proper chan-
           nels and weirs.  When upgrading very long tanks it may be
           necessary  to divide  the tank(s) into two or three sections
           with individual RBC  units.  This scheme requires installation
           of intermediate influent and effluent channels.

           Sludge  Hopper.  Existing tanks with rotary or travelling
           bridge  sludge  collectors require the installation of sludge
           hoppers for the proper  sludge removal.  Tanks with concave
           bottoms require addition of a flat bottom for proper opera-
           tion of the chain-type  sludge collectors.

TYPICAL LAYOUTS

     There is no  "typical" primary treatment plant, since each plant
has different configurations and dimensions.  Accordingly, the layouts
herein presented  should  be considered as representative examples.  The
proper capacity in each  case should be determined by the hydraulic and
organic loads imposed by a particular waste.  Costs associated with
each application  will determine the economics of the system.

Example 1  - Small Plant with Multiple Tanks.  Figures 43 and 44 present
one possible layout  to upgrade the Fxigewater and similar primary treat-
ment plants.  Of  the  five primary settling tanks, the center tank is
kept as a  high-rate  primary settling tank.  The four remaining tanks
are provided with RBC units.    In order to reduce construction work on
the partition walls  as much as possible, the motors are located at the
left side  of the  shafts in one tank and at the right side in the adja-
cent tank, and the covers designed to enclose two shafts instead of in-
dividual units.   In  this particular case, the wall between Tanks No. 3
and 4 is a double wall which provides enough space for the motor.  The
wall between Tanks No. 2 and 3 requires a beam with a cantilever to
support the motor.   Installation of RBC units in Tank No. 3 would have
been impractical, as  a consequence of the clearances required between
motors, which substantially reduce the shaft length for this tank.   In
those cases where  the strength of the sewage requires an RBC area
greater than can be accommodated with this layout, additional tanks may
be provided if land  is available.

Example 2 - Small Plant with Two Tanks.  Figure 45(a)  presents a layout

                                 102

-------
EFFLUENT TO
SECONDARY
CLARIFIER
                 COVER
    INFLUENT
    FROM
    PRIMARY
    TREATMENT,
                     FLOW OVER  BAFFLES
      CONTOURED TANK  FO'R  MULTIPLE  RBC  SHAFTS
EFFLUENT TO
SEDIMENTATION
ZONE OF TANK
INFLUENT
FROM HIGH
RATE OVERFLOW
CLARIFIER
                     FLOW UNDER BAFFLES
             FLAT  BOTTOM RBC TESTING  TANK
                Figure 42. RBC bottom configurations
                             103

-------
                RAW SEWAGE
x~*
ซ>
•*•
o
CO
ฅ
ro

-------
                    h-
                    O
                    UJ
                    CO
                    en
                    co
                    O
                    (T
                    O
ง•
CO
                                      00
                                      •H
                                      fe
105

-------
 for a small plant  consisting  of  two  existing primary tanks.  Minimal
 changes can be obtained  by  installing  overhangs on both sides of the
 tank  to accommodate the motors*  The covers may be designed to enclose
 two shafts, which reduces the clearance required between tanks.

 Example 3 - Small Plant with Two Tanks - Maximum Shaft  Size.  Figure
 45(b) presents a layout similar to Example 2 with the difference that
 the width of the tank allows the use of the largest shaft  now built,
 7.6 m (25 ft) in length.  In a case such as this,  the sludge collectors
must be in pairs since the normal width for sludge collectors is 6.1 m
 (20 ft) which is less than the shaft's length.

 Example 4 - Extra-Wide Tanks.  Figure 45(c) presents a layout for a
 tank with a width greater than 8.2 m (27 ft).  This type of tank is
 usually divided into bays with several sludge-collecting mechanisms.  A
 possible layout consists in accommodating the shafts perpendicularly to
 the sewage flow.  Each set of shafts should be located in the respec-
 tive bays of the tank.  The dividing walls between bays would have  to
 be extended to the top of the tank to separate the stream flows.

 Example 5 - Multiple Tanks.  Figure 46(a) presents a layout for the in-
 stallation of RBC units in multiple adjacent settling tanks.  Figure
 46(b) presents a detail of the dividing wall.  This detail shows the
 space required by the motor and bearings and the clearance required to
 service the motor.

 Example. 6 - Extra-Large Tanks.  Figure 47 shows two possible layouts
 for the installation of RBC units in large tanks.   The original set-
 tling facilities consist of three tanks, each with three bays 64 m  (210
 ft) long.  Since it appears that the increment in efficiency is low for
more than four stages, the layout for this type of tank consists of
making subdivisions to the tanks to the upper zone, which contains  the
RBC units.  The settling zone is a continuous zone.  The effluent from
 the RBC units is brought to the head of the settling zone in order  to
provide adequate solids removal.  It must be observed that the RBC/
Underflow Clarifier method may present some maintenance problems for
such large tanks.  The shallow depth of the clarifier,  1.2 to 1.8 m (4
to 6 ft), may present problems with servicing the  chain collectors  in
long tanks.  If one of the RBC shafts located in the center portion
should have to be removed for service, it would be necessary to use
long-reach cranes.  This problem may be aggravated by adjacent structures
or lack of adequate free space around the tank.

Example 7 - Square Tanks.  Figure 48 presents a layout  for a medium-
size square tank.  The original sludge collectors, influent entrance,
peripheral effluent channels,  etc., should be removed and  replaced  with
new influent and effluent channels and a longitudinal sludge collector.
An intermediate floor must be provided and the  bottom of the tank has
to be leveled.  Square tanks can be converted when they have an approx-
imate side length of 24.4 m (80 ft).  Smaller tanks will not allow  the
installation of four stages unless the RBC units selected  are of the
small-diameter type.  Very large tanks must be  divided  as  in Example 6.

                                    106

-------
     ง
     E
Tl
          ~nrn
           *   i
          LULULU
          Lil
             2lm(70ft)ฑ
               PLAN
                        CROSS SECTION
                 (a) LAYOUT EXAMPLE NO. 2.
.ฃ o
E E
(D 00
       u
            *

                 m
           2lm(70ft)ฑ
             PLAN                    CROSS SECTION

                (b)  LAYOUT EXAMPLE NO.  3.
ป
i 	
1

t.
1 II
1 II
HII 1
II 1
. 	 L
^
1|
n^

ฃ™
1

t.

HII 1
II 1
HII 1
II 1
1\
•
11
i
38m(l25ft)ฑ
                                    t  i
           PLAN                       CROSS SECTION

               (c) LAYOUT EXAMPLE NO.  4.


            Figure 45. RBC layouts in small tanks.
                         107

-------
m
uJ
r


n


m
HI
rn
•
LLJ
ffl
T
i
ft]
LU
rti
u.
j]
rti
i
UJ
rn
4-
T
i
t
T
4-




        PLAN                      CROSS  SECTION

                 (a) LAYOUT EXAMPLE  NO. 5.
                             RBC
                             UNITS
                         INTERMEDIATE
                             FLOOR
                          RELOCATED
                            SLUDGE
                          COLLECTOR
  NOT   RECOMMENDED

(SPACE "d1 ALLOWS SHORT
 CIRCUITING)
             B
                        RECOMMENDED
               fWITHOUT COVERS  1.3 m(4ft-4in)ฑ
               LWITH COVERS

(b) DIVIDING WALL DETAIL
l.6m(5ft-4in)ฑ
   Figure 46. Layout and dividing wall detail for adjacent tanks
                             108

-------
J
-1-1
ฃ
00

+i
ซ*-
O
ฃ
*
UENT
•
•i
•
•i
•i
mt
•
••
i
































































































k

^
^— •
64m(2IOft)ฑ
1
A-OR
? Th
Th
J
— WALL
II
. 	 BEAMS
r EFFLUENT
                                               A-ORIGINAL  LAYOUT

                                                  THREE TANKS
                                                  THREE BAYS
    INFLUENT
                                               B-ALTERNATIVE

                                                  TWO BAYS PER TANK
                                                  INTERMEDIATE  INFLUENT
                                                  AND EFFLUENT CHANNELS

                                                  RBC UNITS PARALLEL
                                                  TO FLOW
EFFLUENT
RBC
EFFl
TOS
ZONE
.UENT
ETTLjNG^,
INFLUENT
ป
ฅ
ฅ
















J
I











iiiiiiiiiiiiiiinrnrnnrnTTii
^
13
p
p
    C-ALTERNATIVE 'B*

       FOUR BAYS PER TANK
       INTERMEDIATE INFLUENT
       AND EFFLUENT CHANNELS

       RBC UNITS PERPENDICULAR
       TO FLOW
                                           EFFLUENT
           Figure 47. RBC layouts in large tanks CExample No. 6)
                                  109

-------
 z
 LJ
                                 r
                                   EFFLUENT
                                        CROSS  SECTION
                PLAN


                (a)  ORIGINAL  PRIMARY  SETTLING TANK.
    INFLUENT
z
LJ
LJ
                                       CROSS   SECTION
             24m(80ft)ฑ
               PLAN


                (b) RBC  INSTALLATION EXAMPLE NO. 7
            Figure 48. RBC layout in medium size square tank,
                             110

-------
LIMITATIONS

     There are several limitations on upgrading primary treatment
plants using the RBC/Underflow Clarifier concept.   It  must  again be
noted that there are no typical solutions and that each plant  presents
particular limitations either in physical aspects  or in design load-
ings.  These limitations include:

     (1)  Depth.  A depth of at least 3.05 m (10 ft) is required for
          this process in order to provide adequate space for  the  RBC
          units, the intermediate floor and the underflow clarifier.

     (2)  Width.  The prior examples address, in part, the  problem of
          width.  Since the RBC units require clearances on both sides,
          the length of each shaft is substantially reduced in narrow
          tanks.  Very wide tanks may have to be divided.

     (3)  Length.  The length of the tank must be  adequate  to  allow the
          installation of the number of stages required.  In some  cases
          it may be necessary to use two or three  shafts per stage.

     (A)  Weight.  Three loads should be considered in designing an RBC
          unit:  the drive weight and the two bearing loads.  The  bear-
          ing load closer to the drive unit is larger because  of the
          main drive sprocket and chain casing.  Each manufacturer
          should specify these loads, which will change with the size
          of the drive unit and the shaft length.   Typical weights may
          be of the order of 1,190 kg/m (800 Ibs/ft) for new dry shaft
          and 2,830 kg/m (1,900 Ibs/ft) for wet shaft with biomass.

OTHER CONSIDERATIONS

Maintenance —

     The  simplicity of the equipment makes maintenance a relatively
easy task.  A drive unit consists of an electric motor, belt drive,
gear reducer and chain drive.  A shaft is supported by two bearings.
The following maintenance description and discussion of problems refer
not only  to the one-year testing period under this program but the five
years' experience obtained at Edgewater since the installation of  the
RBC system.

Lubrication —

     Shaft bearings have been checked on a weekly basis and lubricated
as needed.  This has averaged about once every two weeks.  The external
grease fittings made it possible to lubricate the bearings with the
covers on at all times.  However, during the winter, with the side
covers on, it was not possible to check and  lubricate the gear reducer
(to date, this has not presented any problems).   Since the Edgewater
covers were not provided with entrance doors, the general practice has
been to remove half of the side cover during the  spring and replace it
at the beginning of winter.  The design of new covers provides entrance

                                  111

-------
 doors which facilitate maintenance and inspection of the drive  units.
 The oil in the gear reducer has been changed once a year.  In general,
 lubrication was performed following the manufacturer's  recommendations.
 The average annual cost of oil and grease was $50 per drive unit.

 Covers —

      As mentioned before, the Edgewater covers were not provided with
 access doors.   Removable windows allowed inspection of  the  media in
 several places.  The panels overlapped each other and were  attached  to
 the floor with pin locks.  Vibration and wind effects show  this to be a
 poor anchoring system.  At one point,  with half of the  side cover re-
 moved, a strong wind resulted in the cover's losing several pins.  The
 treatment plant personnel secured the  covers with ropes,  thus protect-
 ing them from  being destroyed by the wind.  It has also been observed
 that the operation of side cover removal has deteriorated some  of the
 side covers.   Sometimes it is necessary to remove the end panels to
 service the drive units.   It  is,  therefore,  essential that  the  RBC
 covers be secured but also easy to take apart.

 Drive Unit Service —

      During the five-year period  it  was necessary to  service one gear
 reducer and two bearings.   This service required  the  use  of  a crane  to
 remove and replace the gear reducer.   For large plants  with multiple
 shafts,  side by side,  sufficient  space to operate a crane should be
 provided.   Since it is not a  good  practice to  keep a  shaft  out  of ser-
 vice for a long time  because  of the  unbalanced  growth that  will occur
 on the media,  it is advisable to maintain sufficient  spare  parts for
 the RBC units.

 Sludge Collecting Mechanism —

      This  equipment was inspected  several  times and  repaired before the
 start of  the program.   The inspection  and  service  required  that the
 tank be  completely drained.   The chains  and  flights required a week to
 repair.  The intermediate  floor provides  a clarifier depth of 1.42 m (4
 ft  8  in) which  made welding very difficult.

 Sludge Accumulations --

      During the  course of  the  testing  program, it was observed that
 some  sludge accumulated under  or near  the baffles separating the
 stages.  The original  clearance of 0.15 m  (6 in) was reduced to  0.05 m
 (2  in) increasing  by three  times the horizontal velocity at  these
 points.  Sludge  accumulations on the intermediate floor  can  also be
 removed by dewatering  the  RBC unit to  just below the intermediate
 floor.

 Odors —

     During the summer months, with the side covers off, a very  un-
pleasant odor was detected at night during low loading to the RBC

                                  112

-------
units.  The odor problem may be associated with high temperatures,
hydrogen sulfide production, beggiatoa growth,  air stagnation,  etc.

Insects —

     The continuous rotation and wetting of the biomass prevents the
attraction and breeding of insects, particularly flies, associated  with
some other secondary treatment processes.

Power Consumption

     Power consumption measurements were made using a wattmeter on  each
drive motor.  The electrical power consumption for Shaft No. 4  equipped
with high-density media was five percent higher than that for Shafts 1,
2 and 3.  There was no appreciable difference in power consumption  be-
tween the first stage and subsequent stages.  The shafts at Edgewater
each contain 3.9 m (13 ft) of media.  Scaling the power measurements to
the standard maximum shaft length of 7.6 m (25 ft) results in an aver-
age power consumption of just over 3.73 kwhr/shaft (5 HP).  Table 17
presents the power consumption.

               TABLE 17.  GENERALIZED POWER CONSUMPTION

     Stagekwhr.(HP)kwhr.  (HP equivalent)

                   3.9 m    (13 ft) of media  7.6 m (25 ft) of media

      1,2,3         1.84     (2.5)             3.64  (4.8)

         4         1.99     (2.6)             3.83  (5.1)

                           Average           3.73  (5.0)
                                    113

-------
                               SECTION 10

                COST ANALYSIS  OF  EDGEWATER MODIFICATIONS

      As mentioned  before, there  is no  "typical" existing primary treat-
 ment  plant  to  illustrate the  upgrading process since, in general, there
 is  no  typical||  plant nor sewage.  In  order to illustrate the costs as-
 sociated  with  "upgrading primary treatment plants with the RBC/Under-
 flow  Clarifier  system" a comparison of four estimates to upgrade the
 Edgewater Treatment Plant is  presented.  Two of these estimates con-
 sider the use of mechanical drives and the other two consider the use
 of  air drives and  chemicals to enhance solids removal.

 CONSTRUCTION COSTS

      The  construction costs include those structural, mechanical, elec-
 trical and  control features within the limits of the RBC process as
 well  as the connecting piping and the  land required to accommodate the
 new units required.

      The  cost estimates are based on costs incurred in 1972 to convert
 one tank  for the test module, upgraded to 1978 costs using the ENR
 annual factors, the present costs of equipment,  and current construc-
 tion  costs for the New York Metropolitan Area.  To develop total con-
 struction costs, it is necessary to add appropriate amounts for en-
 gineering; legal, fiscal and administrative functions;  interest during
 construction and contingencies to cover other costs of  general work not
 directly associated with any item of the cost estimate.

     To estimate the construction costs,  the  facilities  were  defined by
dimension, construction material, equipment,  piping and  appurtenant  re-
quirements.

     The construction cost  estimates  are  presented  in Tables  18 through
21.   The main items include:

     Sludge  Collectors.   Costs are  presented  for chain sludge  collec-
     tion equipment in rectangular  basins.  To modify existing tanks  to
     the RBC/Underflow Clarifier  process it will be  necessary  to  relo-
     cate  the sludge collectors.

     Concrete Removal.   Costs  are presented for removal  of cross-beams
     to allow the installation of the  3.61 m  (12 ft)  (diameter) shafts.

    New Concrete.   Cost estimates  include concrete,  reinforcing  steel,
    labor,  etc., for  the new  concrete  required for  influent and  efflu-

                                 114

-------
    ent channels, motor supports, new cross-beams, intermediate floor
    supports and for the new additional concrete tanks.

    Intermediate Floor.  The intermediate floor required by the RBC/
    Underflow Clarifier process was considered a separate item in cost
    estimating.  The intermediate floor was considered to be construc-
    ted of precast slabs 0.15 m (6 in) thick.

    RBC Media and Covers.  This item includes estimated purchase costs
    of process equipment and other items which are factory-made.

    RBC Installation.  An amount equal to 10 percent of the RBC media
    was taken for this item.

    Electrical Work.  A unit cost per shaft was considered for the RBC
    equipment.   In addition, 10 percent of the cost of other equipment
    was considered for this item.

    Piping.  This item includes the purchase and  installation price of
    all types of pipes, valves, fittings and support devices grouped
    as a  single  component.

    Baffles.  These were considered to be made from 0.05 m by 0.15 m
    (2 in by 6 in) redwood planks.

    Blowers and  Mixers.  These  two items include  the estimated pur-
    chase cost of the  equipment  including the  installation costs.

    Engineering, Contingencies,  etc.  Under  this  item, we have grouped
     the costs associated with all  the basic  and  special  engineering
     services,  the cost of  legal  and fiscal services, the administra-
     tive  services, the interest  during construction and  the cost of
     contingencies.   All  these costs may be substantial and will vary
    with  the  size complexity of  the project.   A  value  equal to 50 per-
     cent  of  the  total  construction cost was  used for this  item.

OPERATION  AND MAINTENANCE

     Operation and maintenance  requirements had been established  during
the operation of  the  pilot  plant in Edgewater.

     Labor.  The  manpower requirements refer  to the RBC/Underflow Clar-
     ifier.  They do not  include any  allowance for general  plant  admin-
     istration,  laboratory work or other  plant manpower requirements.

     Power.  Cost estimates are based  on power requirements for the  RBC
     units and other equipment  related to  this process.

     Supplies.   This item includes the oil,  grease and  other  supplies
     required for the RBC equipment.

     Aeration Equipment.   Operation and maintenance manpower  for the
     aeration equipment was obtained from charts given in the  EPA pub-

                                  115

-------
      lication "Estimating Costs and Manpower Requirements  for  Conven-
      tional Wastewater Treatment Facilities," published  in 1971.   The
      estimated operation and maintenance labor requirements are  for
      diffused air systems according to the  blower  capacity.

      Material and supply cost estimates were derived  from  the  same
      source.

 MECHANICAL DRIVES

 Case 1

      As  described in Section 8 and  presented in Table  16,  a total of
 nine tanks with four 4.1  m (13.5 ft)  shafts  would  be required  to pro-
 vide the total surface area to meet the effluent BOD5  criteria
 under peak monthly conditions.  For the first cost estimate, we have
 considered that one of the five existing settling  tanks would  be used
 to provide the necessary  high-rate  primary  treatment for the entire
 plant flow.  The remaining four tanks  would  be converted to the RBC/
 Underflow Clarifier process and three  new tanks, two of them accommo-
 dating 7.62 m (25 ft)  shafts and one accommodating a 5.50  m (18 ft)
 shaft would be constructed.  This arrangement provides as  equal amount
 of surface area as the five 4.1 m (13.5 ft)  shafts, but is  more econ-
 omical in the new concrete required.   All the RBC/Underflow Clarifier
 tanks would be divided with a  six-inch thick intermediate  floor.  Table
 18 presents the summary of costs, and  Figure 49  shows  the  schematic
 layout for this alternative.

 Case  2

      The  second cost estimate  considers  the  construction of one high-
 rate  primary  settling  tank to  provide  an overflow  rate of 2,500 gpd/
 ft2 and  five  tanks with four 7.62 m (25 ft)  shafts each,  which
 would be  equivalent  to  the  nine  tanks  required with 4.1 m  (13.5 ft)
 shafts.   The  tanks would be  only  1.80 m  (6 ft) deep since they will not
 provide  the underflow clarifier.  The  existing settling tanks would be
 used  as secondary clarifiers.   Table 19 presents the summary of cost
 estimates  for  this case, and Figure 49 shows  the schematic layout of
 this  alternative.

 AIR DRIVES AND  CHEMICAL ADDITION

 Case  3

     As described in Section 8, interstage aeration and chemical  addi-
 tion  to the fourth stage mixed liquor effluent would require seven
 tanks with four 4.1 m (13.5 ft) tanks instead of nine  tanks as  de-
 scribed for the mechanical drives.  The design modifications are  an
hypothetical case since this alternative was not evaluated  on a full-
 scale basis.  It is presented here in order  to present  a  cost compari-
son with the mechanical drives.  It  is claimed that the air-drive RBC
systems provide the aeration required to keep the DO levels at  5.0  mg/1

                                  116

-------
        TABLE 18.   COST ESTIMATES:   MECHANICAL DRIVES - CASE 1
Construction cost estimate:
Sludge collectors
Concrete removal
New concrete
Intermediate floor
RBC media and covers
RBC installation
Electrical work
Piping
Baffles
Land
           Sub-total
                                  Costs to modify
                                  existing tanks
$
 30,800
 22,800
 38,200
 46,200
549,600
 55,000
 67,100

  5,500
    Costs of
additional tanks

$    73,500

    144,100
     60,500
    502,400
     50,300
     55,300
     10,000
      7,200
     25,000
$  815,200          $   928,300

            $  1,743,500
 Engineering,  contingencies,  etc.  @  50%

           Total  construction cost
            $   817,750

            $  2,615,250
 0 & M cost estimate;

 Labor
 Power
 Supplies
           Total Annual O&M Cost
            $      7,300
                 26,000
                  1,400

            $     34,700
                                    117

-------
         TABLE  19.   COST  ESTIMATES:  MECHANICAL  DRIVES  -  CASE  2


 Construction cost  estimate:

 Sludge  collectors                                      $  24,500
 New  concrete                                             205 700
 RBC  media and  covers                                     858*500
 RBC  installation                                         85*800
 Electrical work                                          82*500
 Pipin8                                                   40-^500
 Baffles                                                   4>200
 Land                                                    50,000
 Settling Tank  Restoration                                20,000

     Sub-total                                       $1,371,700

 Engineering, contingencies, etc. @ 50%               $   685,850

     Total construction cost                         $2,057 550

 0 &  M cost estimate;

^abor                                                $    5,200
1ฐ™                                                    27,100
Supplies                                                  1,000

     Total Annual O&M Cost                           $   33 399
                                 118

-------
                     INFLUENT
EFFLUENT











0







0



RBC




13.5 Ft.
Shafts




IT
\
^ I








n t





p
R
E
T
R
E
A
T
M
E
N
T
0



Q



RBC




13.5 Ft.
Shafts








t t I- I-
? ? ?





r










i i
f
1


r



RBC
25 Ft.
Shafts







|J
f
1










a



RBC
18 Ft.
Shafts




' i T
f
          CASE  I  - RBC/UNDERFLOW  CLARIFIERS
     ESTIMATED ANNUAL  COST $ 0.29 PER 1,000 GALLONS

EFFLUENT
~^ —
INFLUENT


PRETREATMENT

_i_ * ; ; * * * 4 f

SEC
CLA
ONDA
RIFIE
RY
:RS



RBC
25 Ft.
Shafts
(Typ)


ป

i 1 t t i t t t t

t

              CASE 2 - SEPARATED RBC  UNITS
       ESTIMATED ANNUAL  COST $ 0.23 PER  1,000 GALLONS
         Figure 49. Mechanical drives schematic  layout,
                         119

-------
 throughout  the system and at the same time provide the rotation re-
 quired  to accomplish the treatment with the RBC units.  A similar ar-
 rangement to that of the preceding cases was considered for the cost
 estimates.  Case 3 would present the cost estimates of maintaining one
 of  the  existing settling tanks to accomplish the required pretreatment,
 converting  four of the existing settling tanks to the RBC/Underflow
 Clarifier process and adding two new tanks with 6.10 m (20 ft) shafts
 equivalent  to the three 4.1 m (13.5 ft) shafts, with the same process.
 As  described in the process design modifications (Section 8), it was
 considered  that the mechanical mixing zone could occupy a small portion
 of  the  turnaround sector located after the fourth RBC stage.  According
 to  the  laboratory tests, no flocculation tanks were required.  Floccu-
 lation  and  settling would occur in the clarification zone.  Table 20
 presents the summary of costs for Case 3, and Figure 50 shows the
 schematic layout for this alternative.

 Case 4

     The fourth case considers an arrangement similar to that of Case
 2,  but  including the air drive and the rapid mixers for the chemical
 addition.   Four tanks with four 7.62 m (25 ft) shafts each would be
 equivalent  to the seven tanks required with the 4.1 m (13.5 ft) shafts.
 Table 21 presents the cost estimates for Case 4,  and Figure 50 shows
 the schematic layout for this alternative.

 EQUIVALENT ANNUAL COSTS

     The previously presented capital costs and annual operating costs
may be combined by calculating present worth or calculating the equiva-
 lent annual cost.

     For the purposes of this presentation the equivalent annual cost
will be calculated and converted to a cost per 1,000 gallons treated.
The basis of converting the capital cost to annual  cost is a 20-year
useful life and 6-5/8 percent interest.

     Table 22 presents the results  for the four alternatives.
                                 120

-------
      TABLE 20.  COST ESTIMATES:  AIR DRIVES - CASE 3
Construction Cost Estimate:


Sludge collectors
Concrete removal
New concrete
Intermediate floor
RBC media and covers
RBC installation
Blowers
Rapid mixers
Electrical work
Baffles
Land
Piping
Chemical storage tanks &
dosing pumps

Sub-total
Engineering, contingencies, etc.
Total construction cost
0 & M estimate:
Labor
Power
Supplies
Ferric chloride

Costs to modify
existing tanks
$ 30,800
22,800
38,200
46,200
549,600
55,000
15,900
40,000
72,700
7,200
-
3,000


$ 881,140
$1,530
@ 50% $ 765
$2,295

$ 21
37
3
6

Costs of
additional tanks
$ 49,000
™"
94 , 500
36,300
302,000
30,200
15,900
40,000
40,500
5,400
16,000
9,700

30,000
$ 649,500
,600
,300
,900

,100
,800
,200
,800
Total Annual O&M Cost
$   68,900
                             121

-------
            TABLE 21.  COST ESTIMATES:  AIR DRIVES - CASE 4
Construction cost estimate;

Sludge collectors                                     $   24,500
New concrete                                             172,400
RBC media and covers                                     686,800
RBC installation                                          68,700
Blowers                                                   21,300
Rapid mixers                                              40,000
Electrical work                                           72,600
Piping                                                    43,500
Baffles                                                    4,200
Land                                                      43,000
Settling tank restoration                                 20,000
Chemical storage & dosing pumps                           30,000

                                                      $1,227,000

Engineering, contingencies, etc. @ 50%                $  613,500

     Total Construction Cost                          $1,840,000

0 & M cost estimate:

Labor                                                 $   23,200
Power                                                     29,700
Supplies                                                   3,200
Ferric chloride                                       	6t7QQ

     Total Annual O&M Cost                            $   62,800
                                 122

-------
                              INFLUENT
EFFLUENT
   -^	











0







0



RBC




13.5 Ft.
Shafts




MT
N 1
^
f



- k




J






p
R
E
T
R
E
A
T
M
E
N
T
i
1



0



a



RBC




13.5 Ft.
Shafts




t




j
V "V
? ?















I

i
a










i
s
r


^M-
0



RBC
20 Ft.
Shafts








i

V
                                                     Location of
                                                     Mixers ITyp)
                CASE  3 - RBC/UNDERFLOW CLARIFIERS

           ESTIMATED ANNUAL  COST %  0.29  PER  1,000 GALLONS
INFLUENT
MIXERS— \
\ \ \ \ ,

SEC
CL/S
OND4
^RIFIE
RY
:RS

i i * * ,
|BซJ '


r

i


\
PRETREATMENT

t
RE
25
Sha
(Tj
JC
Ft
fts
fp.)
t

\ i


\
\

\
^—
1
                  CASE  4 - SEPARATED  RBC  UNITS

          ESTIMATED ANNUAL COST  $  0.24 PER 1,000 GALLONS
     Figure 50. Air drives  and chemical treatment schematic layout,
                             123

-------
                 TABLE 22.  COMPARISON OF ALTERNATIVES
II — — — _^______^_^____
Capital
Cost
($)


Annual
O&M Cost
($)


Amortized
Capital*
($}

Total
Annual
Cost


Unit
Cost
($71000
gal.)
Mechanical drives

   Case 1
   Case 2

Air drives & FeCl3

   Case 3
   Case 4
2,615,250
2,057,550
2,295,900
1,840,500
34,700
33,300
68,900
62,800
239,714
188,595
210,442
168,700
274,414  0.29
221,895  0.23
279,342
231,500
0.29
0.24
   *CRF = 0.09166, 20 years and 6-5/8% interest.
                                 124

-------
1.
                              REFERENCES
     APHA, WPCF, AWWA, 14th Edition, 1975.
2.   Manual of Methods for Chemical Analysis of Water and Wastes,
     EPA-625/6-74-003, U.S. Environmental Protection Agency, Office of
     Technology Transfer, Washington, B.C.  20460,  1974.

3.   Jeris, John S.,  "A Rapid COD Test," Water and  Wastes Engineering,
     May 196,7.

4.   Antoine, Ronald L., Fixed Biological Surfaces-Wastewater Treat-
     ment, CRC Press, Inc., Cleveland, 1976.
                                  125

-------
              APPENDIX A
        TABULATION OF RAW DATA
TABLE A-l.  EDGEWATER RAW DATA  SUMMARY


Day
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35


Date
3/9/77
3/10/77
3/11/77
3/12/77
3/13/77
3/14/77
3/15/77
3/16/77
3/17/77
3/18/77
3/19/77
3/20/77
3/21/77
3/22/77
3/23/77
3/24/77
3/25/77
3/26/77
3/27/77
3/28/77
3/29/77
3/30/77
3/31/77
4/1/77
4/2/77
4/3/77
4/4/77
4/5/77
4/6/77
4/7/77
4/8/77
4/9/77
4/10/77
4/11/77
4/12/77

Flow
Plant
2.90
2.40
2.50
2.40
2.50
4.00
2.60
2.90
2.80
2.80
3.90
3.30
3.00
2.90
6.30
4.40
3.30
2.80
2.70
2.50
2.80
2.50
2.80
2.40
3.70
2.90
3.60
4.70
3.70
3.50
-
—
—
2.60
2.50

RBC
(mgd)
0.400
0.400
0.285
0.390
0.380
0.355
0.411
0.428
0.485
0.430
0.425
0.423
0.423
0.297
0.228
0.212
0.220
0.242
0.240
0.225
0.305
0.305
0.320
0.320
0.324
0.305
0.311
0.315
0.275
0.409
—
_
_
0.403
0.400
RBC
Sludge
(gpd)
_
—
—
_
_
_
—
2,340
2,180
2,940
2,390
2,390
1,795
1,990
2.420
1,740
1,539
2,023
2,137
1,082
1,169
968
2,763
1,538
2,308
1,424
883
968
1,082
1,066
_
_
_
911
968
Temp
. ฐc
RBC
In
13.0
13.5
15.5
13.0
13.0
13.5
13.0
14.5
13.5
_
13.5
12.5
14.0
11.5
11.0
13.0
13.0
13.0
12.5
13.0
15.0
16.0
16.5
15.5
14.0
13.0
15.0
_
14.0
14.0
_
_
_
15.0
-
Out
12.0
12.5
14.5
12.0
12.0
12.4
13.0
13.0
13.0
_
13.0
12.0
13.0

10.0
11.0
11.0
12.0
12.0
15.0
13.5
15.0
15.0
14.0
14.0
13.0
14.0

12.0
12.0
^
_
_
14.0
15.0
PH
RBC
In
6.8
7.5
7.1
7.4
7.2
7.2
7.2
7.2
7.3
7.4
7.5
6.9
7.3
7.2
7.1
7.0

_
7.1
7.2
7.2
7.2
7.3
6.9
7.8
7.3
7.5
7.2
6.7
7.2



7.2
7.4
Out
7.0
7.0
6.9
7.2
7.2
7.1
7.1
7.3
7.4
7.4
7.3
7.0
7.3
7.3
7.2
7.1
7.3
7.1
6.9
7.2
7.3
7.3
7.2
7.0
7.6
7.2
7.4
7.2
7.0
7.0



7.2
7.4
                126
                                            continued

-------
TABLE A-l.  (continued)


Day
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75


Date
4/13/77
4/14/77
4/15/77
4/16/77
4/17/77
4/18/77
4/19/77
4/2U/77
4/21/77
4/22/77
4/23/77
4/24/77
4/25/77
4/26/77
4/27/77
4/28/77
4/29/77
4/30/77
5/1/77
5/2/77
5/3/77
5/4/77
5/5/77
5/6/77
5/7/77
5/8/77
5/9/77
5/10/77
5/11/77
5/12/77
5/13/77
5/14/77
5/15/77
5/16/77
5/17/77
5/18/77
5/19/77
5/20/77
5/21/77
5/22/77

Flow
Plant
2.50
2.50
2.50
2.60
2.50
2.50
2.20
2.20
2.30
2.30
2.20
2.60
2.20
2.30
2.20
2.20
2.40
2.20
2.20
2.00
2.10
1.80
2.60
2.30
3.10
2.70
2.60
2.60
2.20
2.40
2.40
2.30
2.30
2.10
2.30
2.10
2.30
2.10
2.20
2.20

RBC
(mgd)
0.418
0.407
0.392
0.400
0.370
0.405
0.385
0.395
0.405
0.415
0.365
0.365
0.395
0.380
0.375
0.375
0.450
0.380
0.370
0.390
0.390
0.407
0.388
0.230
0.360
0.345
0.365
0.370
0.369
0.368
0.370
0.380
0.350
0.365
0.680
0.775
0.840
0.660
0.618
0.632
RBC
Sludge
(gpd)
1,198
1,396
2,023
2,790
1,139
2,051
2,222
2,194
2,648
3,135
2,079
2,279
1,139
1,797
968
-
-
-
-
-
-
1,852
1,567
712
2,849
2,336
1,909
2,335
1,851
1,079
3,162
3,247
1,824
1,882
2,109
2,907
2,906
3,390
3,595
1,994
Temp
. C
RBC
In
17.0
17.0
17.0
17.0
16.7
18.0
18.0
-
-
19.0
17.0
17.0
-
-
18.0
19.0
17.0
18.0
18.0
17.0
17.0
19.0
18.0
19.0
-
18.0
18.0
18.0
19.0
19.0
20.0
19.0
18.0
20.0
21.0
21.5
21.0
21.5
21.0
21.0
Out
16.0
16.0
15.0
16.0
16.0
17.0
17.0
18.0
18.0
18.0
19.0
17.0
17.0
-
18.0
18.0
17.0
17.0
17.0
18.0
18.0
18.0
17.0
19.0
-
17.0
16.5
17.0
18.0
19.0
19.0
19.0
19.0
20.0
20.0
20.0
21.0
21.0
21.0
• 21.0
pH
RBC
In
7.4
7.3
7.4
7.8
7.4
7.3
7.3
7.2
7.1
7.2
7.3
7.5
7.3
7.3
7.3
7.6
7.5
7.3
7.2
7.1
7.1
6.6
7.0
6.9
-
7.2
6.9
6.9
7.0
7.0
6.8
7.1
7.1
7.2
7.1
7.2
7.2
7.2
7.6
7.1
Out
7.5
7.4
7.4
7.6
7.4
7.4
7.4
7.3
7.2
7.2
7.3
7.2
7.4
7.4
7.4
7.5
7.5
7.4
7.1
7.1
7.1
6.8
7.2
6.8
-
7.0
6.9
7.0
7.0
7.0
7.6
7.2
7.1
7.2
7.2
7.3
7.2
7.2
7.2
7.2
                                     continued.
           127

-------
TABLE A-l.  (continued)

Day
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115

Date
5/23/77
5/24/77
5/25/77
5/26/77
5/27/77
5/28/77
5/29/77
5/30/77
5/31/77
6/1/77
6/2/77
6/3/77
6/4/77
6/5/77
6/6/77
6/7/77
6/8/77
6/9/77
6/10/77
6/11/77
6/12/77
6/13/77
6/14/77
6/15/77
6/16/77
6/17/77
6/18/77
6/19/77
6/20/77
6/21/77
6/22/77
6/23/77
6/24/77
6/25/77
6/26/77
6/27/77
6/28/77
6/29/77
6/30/77
7/1/77
Flow
Plant
2.00
2.20
2.10
2.10
2.10
2.20
2.00
1.90
1.80
2.00
2.10
2.10
2.00
2.10
2.00
2.60
1.90
2.20
4.30
3.10
2.30
1.90
2.10
1.90
2.20
2.10
2.30
2.30
2.10
2.40
2.00
2.20
2.30
2.30
2.40
2.10
2.10
2.30
2.20
1.80
RBC
(mgd)
0.618
0.717
0.678
0.558
0.625
0.585
0.260
0.480
0.685
0.685
0.670
0.685
0.685
0.685
0.640
0.655
0.570
0.710
0.670
0.305
0.695
0.935
0.698
0.696
0.710
0.705
0.705
0.711
0.711
0.635
0.725
0.695
0.720
0.700
0.685
0.685
0.685
0.720
0.945
0.770
RBC
Sludge
(gpd)
2,251
2,450
2,548
2,133
2,251
2,250
3,076
1,453
2,763
3,988
5,357
4,445
4,231
2,393
3,875
7,921
2,252
3,901
1,453
3,249
2,136
2,194
2,991
1,595
2,421
3,019
3,943
3,162
3,969
2,821
1,396
3,078
2,310
3,696
3,619
3,962
2,298
2,566
2,764
2,165
Temp . C
RBC
In
23.0
23.0
23.0
23.0
23.0
23.0
19.0
21.0
23.0
23.0
23.5
24.0
22.0
22.0
24.0
23.0
23.0
-
_
22.0
22.0
23.0
23.5
23.5
24.0
24.0
24.0
_
25.0
25.0
24.0
24.5
25.0
24.0
24.0
25.0
24.0
25.5
25.5
25.5
Out
22.0
23.0
23.0
22.0
23.0
23.0
22.0
21.0
23.0
23.0
23.5
23.0
22.0
22.0
23.0
22.0
22.0
_
_
21.0
21.0
22.5
23.0
23.5
23.5
24.0
24.0
_
24.5
24.0
24.0
24.0
25.0
24.0
24.0
24.5
24.0
25.0
25.5
25.5
pH
RBC
In
6.8
6.9
6.8
7.2
7.3
7.5
6.8
7.1
7.0
7.1
7.2
7.0
6.9
6.7
7.2
7.3
6.7
_
_
7.9
7.3
7.5
8.8
7.9
7.5
7.5
7.8

7.3
7.3
7.7
7.3
7.5
8.4
7.1
7.2
7.3
7.2
7.3
7.6
Out
7.2
7.0
6.9
7.3
7.2
7.4
7.0
7.2
7.1
7.2
7.3
7.0
7.0
6.8
7.3
7.3
6.9
_
_
7.9
7.5
7.5
8.5
7.8
7.5
7.5
7.6

7.4
7.4
7.4
7.4
7.5
8.0
7.5
7.3
7.4
7.4
7.6
7.6
                                    continued,
        128

-------
TABLE A-l.  (continued)


Day
j
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155


Date
7/2/77
7/3/77
7/4/77
7/5/77
7/6/77
7/7/77
7/8/77
7/9/77
7/10/77
7/11/77
7/12/77
7/13/77
7/14/77
7/15/77
7/16/77
7/17/77
7/18/77
7/19/77
7/20/77
7/21/77
7/22/77
7/23/77
7/24/77
7/25/77
7/26/77
7/27/77
7/28/77
7/29/77
7/30/77
7/31/77
8/1/77
8/2/77
8/3/77
8/4/77
8/5/77
8/6/77
8/7/77
8/8/77
8/9/77
8/10/77

Flow
Plant
2.20
2.10
1.90
2.00
2.30
2.10
2.10
2.30
2.00
1.90
2.10
2.30
1.90
2.10
2.30
2.00
1.90
2.30
2.00
2.20
2.20
2.20
2.00
1.90
2.30
1.90
2.10
2.10
2.30
2.10
1.90
2.50
2.00
2.30
2.20
2.20
2.10
2.20
2.10
2.20

RBC
(mgd)
0.555
0.500
0.495
0.490
0.550
0.530
0.507
0.527
0.465
0.460
0.495
0.475
0.495
0.475
0.400
0.492
0.470
0.482
0.492
0.485
0.502
0.515
0.480
0.490
0.490
0.495
0.485
0.210
0.430
0.395
0.390
0.410
0.435
0.405
0.420
0.440
0.405
0.390
0.415
0.385
RBC
Sludge
(gpd) .
_
—
-
-
2,736
2,365
2,336
3,733
3,760
3,106
3,933
3,306
4,416
3,078
3,675
2,222
1,880
2,650
2,079
2,421
2,421
3,020
4,104
2,790
4,445
2,192
2,023
-
3,049
3,020
3,305
2,849
2,763
2,393
3,106
2,307
2,536
2,449
1,879
1,595
Temp.
C
RBC
In
_
—
-
-
27.0
26.0
26.0
30.0
29.0
26.5
26.0
27.0
27.0
27.0
27.0
27.0
28.0
28.0
28.5
28.0
28.0
27.0
27.0
28.0
27.0
27.0
-
27.5
26.0
27.0
27.5
27.0
27.0
27.0
27.0
27.0
27.0
27.0
27.0
27.0
Out
—
—
—
—
26.0
26.0
26.0
29.0
30.0
26.0
25.0
26.5
27.0
27.0
27.0
27.0
27.5
28.0
28.0
28.0
28.0
27.0
27.0
27.0
26.5
27.0
—
27.5
26.5
26.0
27.0
26.0
27.0
26.0
27.0
'27.5
27.0
27.0
27.0
27.0
PH

RBC
In
-
—
—
—
7.3
7.3
7.5
7.2
7.4
7.3
7.3
7.1
7.1
7.1
7.2
7.1
7.3
7.1
7.3
7.0
7.4
7.4
7.2
7.2
7.2
7.3
—
7.6
7.4
7.3
7.2
7.4
7.4
7.2
7.2
7.5
7.4
7.1
7.5
7.4
Out
-
~
—
—
7.5
7.4
7.6
6.8
7.2
7.5
7.4
7.1
7.1
7.1
7.3
7.2
7.5
7.0
7.3
7.1
7.4
7.4
7.4
7.3
7.3
7.3
—
7.6
7.4
7.3
7.3
7.4
7.4
7.3
7.3
7.4
7.4
7.4
7.1
7.4
                                      continued
           129

-------
TABLE A-l.  (continued)

Day
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195

Date
8/11/77
8/12/77
8/13/77
8/14/77
8/15/77
8/16/77
8/17/77
8/18/77
8/19/77
8/20/77
8/21/77
8/22/77
8/23/77
8/24/77
8/25/77
8/26/77
8/27/77
8/28/77
8/29/77
8/30/77
8/31/77
9/1/77
9/2/77
9/3/77
9/4/77
9/4/77
9/6/77
9/7/77
9/8/77
9/9/77
9/10/77
9/11/77
9/12/77
9/13/77
9/14/77
9/15/77
9/16/77
9/17/77
9/18/77
9/19/77
Flow
Plant
1.90
2.30
2.30
1.90
2.00
2.00
2.40
2.30
2.30
2.30
2.40
3.60
2.50
2.30
2.30
2.40
2.10
2.00
2.30
2.00
2.30
2.30
2.40
2.30
2.20
2.10
2.10
2.50
2.10
2.30
2.70
2.30
2.10
2.40
2.10
2.20
2.20
3.00
2.40
2.20
RBC
(mgd)
0.395
0.385
0.400
0.328
0.385
0.393
0.408
0.395
0.388
0.390
0.410
0.365
0.385
0.380
0.375
0.395
0.373
0.370
0.330
0.380
0.383
0.375
0.375
0.373
0.380
0.380
0.365
0.375
0.370
0.380
0.400
0.390
0.350
0.405
0.375
0.375
0.375
0.390
0.425
0.420
RBC
Sludge
(gpd)
2,619
2,478
2,535
1,794
2,735
2,707
1,938
2,108
2,221
2,079
1,851
1,823
1,481
2,307
1,908
2,081
1,595
1,710
1,681
2,450
2,736
1,823
1,171
1,680
1,823
2,964
1,937
2,223
1,908
2,422
2,193
2,165
2,023
2,052
1,938
1,424
2,478
2,166
1,424
1,453
Temp. C
RBC
In
27.0
_
27.0
27.0
27.5
27.0
27.0
27.0
27.0
26.0
25.0
23.0
26.0
26.5
25.0
25.0
26.0
26.0
27.0
27.0
27.0
27.0
28.0
27.0
26.0
26.0
27.0
26.5
27.0
25.0
25.0
25.0
25.0
26.0
26.0
26.0
26.0
24.6
24.5
25.0
Out
27.0

27.0
26.5
27.0
26.5
27.0
26.0
26.0
26.0
25.0
24.0
26.0
26.0
24.0
25.0
25.0
26.0
27.0
27.0
26.0
27.0
27.0
27.0
26.0
26.0
27.0
26.0
26.0
25.0
25.0
25.0
25.0
25.0
25.0
25.0
25.0
24.0
25.0
25.0
PH
RBC
In
7.2

7.3
7.2

6.9
7.2
7.2
7.0
7.4
6.8
6.9
7.1
6.3
6.0
7.0
7.6
7.2
7.4
7.3
6.5
6.4
7.0
6.9
7.3
6.8
6.8
6.8
7.3
6.5
7.4
7.0
6.2
7.0
7.0
6.9
7.6
7.4
7.2
7.4
Out
7.3

7.2
7.2
6.0
6.8
7.3
7.3
7.0
7.4
7.0
7.1
6.5
6.5
7.0
7.0
7.5
7.3
7.5
7.4
6.9
6.3
7.0
7.0
7.2
6.8
6.7
6.8
7.3
6.5
7.4
6.8
6.2
7.1
7.0
7.0
7.5
7.3
7.1
7.4
                                   continued.
        130

-------
TABLE A-l.  (continued)


Day
j
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235


Date
9/20/77
9/21/77
9/22/77
9/23/77
9/24/77
9/25/77
9/26/77
9/27/77
9/28/77
9/29/77
9/30/77
10/1/77
10/2/77
10/3/77
10/4/77
10/5/77
10/6/77
10/7/77
10/8/77
10/9/77
10/10/77
10/11/77
10/12/77
10/13/77
10/14/77
10/15/77
10/16/77
10/17/77
10/18/77
10/19/77
10/20/77
10/21/77
10/22/77
10/23/77
10/24/77
10/25/77
10/26/77
10/27/77
10/28/77
10/29/77

Flow
Plant
2.50
3.10
2.30
2.30
-
-
-
-
-
-
-
-
-
-
2.50
2.30
2.40
2.50
2.40
3.10
4.00
3.10
2.60
2.70
2.70
3.80
3.20
2.90
3.00
2.50
3.20
4.10
3.20
2.70
2.40
2.60
2.00
2.80
2.50
2.60

RBC
(mgd)
0.425
0.845
0.370
0.355
-
-
-
-
-
-
-
-
-
-
0.355
0.353
0.355
0.378
0.570
0.570
0.330
0.435
0.390
0.470
0.435
0.465
0.415
0.420
0.435
0.460
0.585
0.605
0.560
0.708
0.678
0.523
0.553
0.553
0.555
0.572
RBC
Sludge
(gpd)
1,795
-
2,791
2,165
—
-
—
—
—
-
—
—
-
-
1,852
1,481
2,108
2,108
-
-
2,649
1,767
1,563
2,763
2,164
2,707
1,653
1,909
2,593
2,906
2,279
941
2,905
2,648
2,192
2,450
2,622
1,852
1,682
2,252
Temp.
C
RBC
In
25.0
24.0
24.0
24.0
—
—
—
—
—
—
—
—
—
-
24.0
-
22.0
22.0
20.0
18.0
21.0
21.0
21.0
21.0
20.0
17.0
20.0
20.0
20.0
21.0
18.0
19.0
20.0
19.0
20.0
20.0
21.0
20.0
21.0
19.0
Out
25.0
24.0
23.0
24.0
—
—
—
—
—
—
—
—
—
—
22.0
-
22.0
22.0
20.0
18.0
20.0
20.0
21.0
19.0
19.0
17.0
20.0
19.0
19.0
20.0
17.0
18.0
19.0
18.0
19.0
19.0
20.0
20.0
20.0
19.0
PH

RBC
In
7.3
7.2
7.2
6.6
—
—
—
~
"•
—
—
—
—
—
7.1
6.8
—
6.7
7.4
7.3
6.8
6.2
6.7
6.5
7.3
7.2
7.0
7.0
7.0
7.0
6.9
7.6
8.2
7.2
7.1
7.2
7.5
8.2
7.8
8.1
Out
7.3
7.2
7.2
6.5
"~
"•
•~
™ •
•~
—
•™
—
—
—
7.2
6.7
—
6.7
7.5
7.3
6.8
—
6.4
6.8
7.3
7.2
7.0
6.8
7.3
7.3
7.0
7.7
7.7
7.3
7.1
7.3
7.4
7.5
7.5
7.8
                                      continued.
          131

-------
TABLE A-l.  (continued)

.. y.
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275

Date
10/30/77
10/31/77
11/1/77
11/2/77
11/3/77
11/4/77
11/5/77
11/6/77
11/7/77
11/8/77
11/9/77
11/10/77
11/11/77
11/12/77
11/13/77
11/14/77
11/15/77
11/16/77
11/17/77
11/18/77
11/19/77
11/20/77
11/21/77
11/22/77
11/23/77
11/24/77
11/25/77
11/26/77
11/27/77
11/28/77
11/29/77
11/30/77
12/1/77
12/2/77
12/3/77
12/4/77
12/5/77
12/6/77
12/7/77
12/8/77
Flow
Plant
2.60
2.30
2.50
2.20
2.30
2.30
2.50
2.40
2.30
5.40
5.80
3.10
4.00
3.60
3.00
2.60
2.60
2.40
3.00
3.00
2.70
2.50
2.20
2.40
2.70
3.00
2.60
3.10
3.50
2.70
—
—
—
—
—
—
-
3.50
3.30
3.00
RBC
(mgd)
0.540
0.580
0.615
0.545
0.580
0.580
0.585
0.570
0.560
0.595
0.555
0.595
0.595
0.608
0.595
0.588
0.605
0.605
0.590
0.615
0.625
0.540
0.560
0.585
0.750
0.455
0.340
0.345
0.345
0.335
_
_
_
_
_
_
_
0.415
0.435
0.420
RBC
Sludge
(gpd)
1,537
4,188
3,981
4,160
3,363
3,363
2,736
2,820
3,505

_
1,737
3,134
1,908
1,767
2,536
3,219
4,303
5,243
2,392
2,650
912
2,508
2,395
3,191
ป
..
_
..
_
_
1IL
•
_
^
—
^
2,279
1,681
1,767
Temp . C
RBC
In
19.0
20.0
20.0
20.0
21.0
21.0
20.0
19.0

_
17.0
18.0
18.0
18.0
18.0
18.0.
18.0
18.0
18.0
19.0
17.0
17.0
18.0
18.0
15.0

_


_







15.0
15.0
16.0
Out
19.0
19.0
19.0
20.0
20.0
20.0
20.0
19.0


16.0
17.0
18.0
17.0
17.0
17.0
18.0
17.0
18.0
17.0
17.0
16.0
17.0
17.0
14.0












14.0
15.0
15.0
pH
RBC
In
7.5
7.6
7.6
7.5
7.3
7.3
7.0
7.6
6.9
\J 9 S

7.5
7.4
7.8
7.2
7.4
7.6
7.3
7.6
7.7
7.4
7.5
7.6
7.8
7.2












7.7
7.2
* • *m
7.3
Out
7.6
7.5
7.5
7.5
7.4
* • ™
7.4
7.0
/ • \J
1 6
/ • \J
7 i
/ • j.

7.5
/ • _/
7.5
7.6
/ • \J
7.2
7.2
/ • ซ•
7.5
/ • -J
7.3
/ • ~J
7.4
/ • ~
7.4
/ • *T
7.0
/ • w
7.7
f • /
7.4
/ • ~
7.9
7.2












7 4
/ • *T
7 ?
/ • ฃ.
7.2
                                   continued
       132

-------
TABLE A-l.  (continued)


Day
j
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315


Date
12/9/77
12/10/77
12/11/77
12/12/77
12/13/77
12/14/77
12/15/77
12/16/77
12/17/77
12/18/77
12/19/77
12/20/77
12/21/77
12/22/77
12/23/77
12/24/77
12/25/77
12/26/77
12/27/77
12/28/77
12/29/77
12/30/77
12/31/77
1/1/78
1/2/78
1/3/78
1/4/78
1/5/78
1/6/78
1/7/78
1/8/78
1/9/78
1/10/78
1/11/78
1/12/78
1/13/78
1/14/78
1/15/78
1/16/78
1/17/78

Flow
Plant
2.80
3.10
2.60
2.50
2.70
2.50
4.10
3.50
3.20
2.90
3.80
4.00
3.60
5.30
-
32.50
3.40
3.10
2.70
2.70
2.80
2.80
2.90
2.90
2.50
2.40
2.30
2.10
2.30
2.30
2.10
3.10
3.60
3.10
2.70
2.40
3.10
4.00
2.80
2.60

RBC
(mgd)
0.390
0.165
0.270
0.385
0.395
0.405
0.413
0.393
0.430
0.400
0.395
0.403
0.400
0.110
—
0.470
0.465
0.435
0.455
0.435
0.455
0.650
0.270
0.440
0.435
0.425
0.415
0.390
0.420
0.400
0.395
0.385
0.405
0.400
0.410
0.420
0.385
0.195
0.380
0.398
RBC
Sludge
(gpd)
1,909
2,450
2,165
2,108
2,450
2,052
1,369
1,852
2,166
1,680
1,396
2,079
1,369
—
—
-
—
-
-
-
-
-
—
-
-
2,164
455
3,534
2,677
1,880
1,738
2,223
1,881
1,937
2,508
2,251
1,396
1,880
1,708
2,051
Temp.
C
RBC
In
13.0
14.0
—
15.0
15.0
15.0
14.0
14.0
14.0
14.0
12.0
13.0
—
—
•—
—
—
—
—
—
—
-
—
—
-
13.0
13.0
13.0
14.0
13.0
11.0
12.0
13.0
13.0
13.0
13.0
9.0
11.0
12.0
-
Out
14.0
13.0
—
14.0
14.0
14.0
14.0
13.0
13.0
12.0
11.0
12.0
—
—
•~
—
—
—
—
—
—
-
—
—
-
12.0
13.0
12.0
13.0
12.0
12.0
12.0
12.0
12.0
13.0
12.0
9.0
11.0
11.0
—
pH
RBC
In
7.0
—
—
7.6
7.9
7.4
8.7
7.2
7.2
7.9
7.3
7.3
7.5
•~
™ *
—
—
—
—
—
—
—
•~
—
—
7.6
7.5
7.4
8.5
8.2
7.4
7.2
7.4
7.5
7.6
7.6
7.5
7.1
7.4
7.0
Out
7.2
—
—
7.4
—
7.4
8.2
7.2
7.2
7.6
7.1
7.2
7.2
~
^
—
"•
™
—
~
—
—
~
—
—
7.4
—
7.6
7.9
7.7
7.3
7.2
7.2
—
7.5
7.6
7.4
6.9
7.3
7.0
                                      continued
           133

-------
TABLE A-l.  (continued)
Da XT
L>ay
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
T^ ซ•* *• *+.
JJate
1/18/78
1/19/78
1/20/78
1/21/78
1/22/78
1/23/78
1/24/78
1/25/78
1/26/78
1/27/78
1/28/78
1/29/78
1/30/78
1/31/78
2/1/78
2/2/78
2/3/78
2/4/78
2/5/78
2/6/78
2/7/78
2/8/78
2/9/78
2/10/78
2/11/78
2/12/78
2/13/78
2/14/78
2/15/78
2/16/78
2/17/78
2/18/78
2/19/78
2/20/78
2/21/78
2/22/78
2/23/78
2/24/78
Flow
Plant
1.80
3.80
3.30
3.10
3.00
2.70
2.60
2.60
5.20
7.00
4.10
3.10
2.10
2.90
2.80
2.60
8.40
2.50
1.20
2.10
2.50
2.60
2.70
2.70
2.90
2.60
2.30
2.60
2.60
2.50
2.50
2.40
2.50
2.50
2.40
2.40
2.50
2.60
RBC
(mgd)
0.219
0.403
0.413
0.400
0.400
0.380
0.400
0.350
0.295
0.305
0.335
0.305
0.290
0.320
0.305
0.310
0.390
0.495
0.490
0.465
0.495
0.515
0.460
0.475
0.430
0.430
0.468
0.363
0.385
0.390
0.385
0.390
0.400
0.420
0.405
0.395
0.405
-
RBC
Sludge
(gpd)
2,251
2,222
1,882
1,744
1,560
2,621
3,414
2,590
1,452
1,253
1,766
1,197
2,535
1,509
1,994
1,482
1,994
2,677
1,966
1,994
2,222
2,963
3,048
3,029
3,076
2,309
2,706
3,562
2,907
3,021
3,334
3,190
2,073
2,193
3,674
2,507
2,222
-
Temp . C
RBC
In
9.0
11.0
11.0
10.0
12.0
12.0
7.0
9.0
10.0
10.0
11.0
11.0
11.0
12.0
12.0
11.0
10.0

ซ•
12.0
12.0
12.0
11.0
10.0
12.0
12.0
12.0
12.0
12.0
11.0
11.0

12.0
12.0
12.0
12.0
Out
10.0
10.0
10.0
10.0
12.0
11.0
7.0
7.0
9.0
9.0
10.0
10.0
11.0
10.0
11.0
9.0
9.0


11.0
11.0
11.0
10.0
9.0
11.0
12.0
11.0
12.0
12.0
10.0
10.0

11.0
11.0
10.0
11.0
pH
RBC
In
7.0
7.2
7.4
7.0
6.8
7.0
7.2
7.1
8. 1
W * X
7. 1
/ • x
7.6
7.4
7.5
7.5
7.4
7.4
7.4
7.4
6.8
7.0
6.8
7.0
6.9
7.2
7.9
7.5
7.3
7.2
7.2
7.1
7.1
7.6
/ • w
6.9

7.6
8.2
7.4
7.6
Out
6.9
7.0
7.4
6.8
6.8
7.0
7.2
7.0
7 i
/ . i
7 1
/ . 4.
7 6
/ • \J
7 4
/ • ^
7.4
7.4
/ • ~
7.4
/ • ~
7.3
/ • ~J
7.3
7.3
/ • -J
6.9
v/ • j
7.0
I • W
6 8
\J • Q
6.9
7 i
/ • X
7 i
/ • J.
7.6
/ • \J
7.5
f • .*/
7 2
/ • ^.
7 2
/ • ฃ.
7 2
/ • A.
7 i
/ • X
7. 1
/ • x
7 7
/ • /
7 0
/ • W
7 5
/ • -/
8 0
vJ • VJ
7.2
7.3
                                   continued
        134

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
m in iT
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Date
3/9/77
3/10/77
3/11/77
3/12/77
3/13/77
3/14/77
3/15/77
3/16/77
3/17/77
3/18/77
3/19/77
3/20/77
3/21/77
3/22/77
3/23/77
3/24/77
3/25/77
3/26/77
3/27/77
3/28/77
3/29/77
3/30/77
3/31/77
4/1/77
4/2/77
4/3/77
4/4/77
4/5/77
4/6/77
4/7/77
4/8/77
4/9/77
4/10/77
4/11/77
4/12/77
4/13/77
4/14/77
4/15/77
4/16/77
4/17/77

Raw
8.4
8.6
7.9
7.4
8.0
8.6
7.4
8.5
6.8
-
7.6
8.2
7.6
-
9.1
8.1
7.5
7.8
7.2
9.7
7.2
7.2
5.8
6.6
7.0
9.2
6.5
-
8.1
7.4
-
-
-
6.0
6.2
5.9
5.9
6.0
5.6
4.9
RBC
In
7.0
7.0
7.0
7.2
7.4
8.5
7.6
8.4
6.6
-
6.4
7.5
6.7
-
8.7
7.3
6.7
8.0
6.2
7.6
6.3
5.6
5.3
6.0
7.2
9.1
6.0
-
7.6
6.6
-
-
-
5.4
5.0
4.8
5.3
5.0
5.0
4.6
Stg
1
4.6
3.8
4.6
4.6
4.8
4.6
4.0
4.4
4.2
-
4.2
4.6
3.8
-
6.8
5.6
5.7
6.0
5.4
5.0
3.8
3.3
3.3
3.3
3.8
6.0
3.5
-
5.0
4.8
-
-
-
2.9
2.4
2.8
2.6
3.0
3.0
3.2
Stg
2
4.6
4.0
4.5
4.8
4.8
4.6
3.6
4.1
3.3
-
4.2
4.6
4.1
-
7.1
6.4
6.3
5.8
5.8
5.2
3.8
3.0
3.5
3.2
3.2
5.8
3.5
-
4.5
4.8
—
—
-
2.4
2.3
2.6
2.5
2.9
2.9
2.0
Stg
3
4.3
3.6
4.0
3.8
4.6
4.4
3.8
3.9
2.9
—
3.9
4.4
3.6
—
7.2
6.8
6.6
6.0
6.0
5.7
4.2
3.3
3.2
3.6
3.0
6.0
4.1
-
4.6
5.6
—
—
-
2.7
2.7
2.6
2.9
3.1
3.1
2.8
Stg
4
4.0
3.4
3.0
2.6
3.8
4.2
3.4
3.7
2.9
—
3.9
4.4
3.5
—
6.6
6.6
6.2
6.0
5.4
5.9
4.8
3.1
3.3
3.4
2.6
5.4
4.1
—
4.5
4.9
—
—
—
2.6
2.4
2.0
2.0
2.2
2.2
2.6
RBC
Out
3.8
3.4
2.6
2.2
3.4
4.2
2.9
3.4
2.9
—
3.5
4.2
3.5
—
5.9
6.1
5.6
5.6
5.4
5.9
4.4
3.2
2.8
3.0
1.4
4.4
3.2
—
3.7
4.5
—
—
—
2.3
1.6
1.0
1.1
1.6
1.2
0.8
                                     continued
           135

-------
TABLE A-l.  (continued)

Day
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80

Date
4/18/77
4/19/77
4/20/77
4/21/77
4/22/77
4/23/77
4/24/77
4/25/77
4/26/77
4/27/77
4/28/77
4/29/77
4/30/77
5/1/77
5/2/77
5/3/77
5/4/77
5/5/77
5/6/77
5/7/77
5/8/77
5/9/77
5/10/77
5/11/77
5/12/77
5/13/77
5/14/77
5/15/77
5/16/77
5/17/77
5/18/77
5/19/77
5/20/77
5/21/77
5/22/77
5/23/77
5/24/77
5/25/77
5/26/77
5/27/77

Raw
5.1
5.5
5.6
4.9
5.1
5.2
5.0
5.9
-
6.0
6.6
-
6.0
6.0
5.7
5.7
6.3
7.9
7.0
-
7.8
6.4
6.4
6.9
5.3
5.2
5.4
6.0
4.6
5.2
4.6
5.0
4.1
3.8
4.3
4.6
3.9
5.5
4.8
4.6
RBC
In
4.2
4.1
4.6
3.9
3.2
4.4
3.8
4.9
—
5.0
5.9
4.2
5.1
4.3
4.1
5.1
5.1
7.5
8.2
—
7.2
5.8
5.4
5.2
4.8
4.8
5.0
4.8
2.6
3.1
2.4
2.2
2.2
2.2
2.4
1.6
-
2.4
2.6
2.2
Stg
1
2.8
2.5
3.0
2.3
2.4
3.8
3.6
3.5
—
3.3
4.0
-
3.0
3.4
2.5
2.5
3.3
3.9
5.2
—
5.1
4.0
3.8
3.6
3.6
3.2
4.0
3.8
2.2
2.2
2.2
2.2
1.8
2.2
1.8
1.2
-
2.0
2.2
2.0
Stg
2
1.9
2.0
2.0
1.6
1.7
3.6
3.4
2.6
_
2.3
2.9
—
2.8
3.2
1.9
1.9
2.1
2.7
4.4
_
1.2
3.2
2.4
2.8
2.8
2.4
3.4
3.6
1.8
1.4
1.5
1.4
1.2
1.2
1.2
1.4
_
1.6
1.8
1.6
Stg
3
1.6
1.5
1.7
1.4
1.5
3.4
3.4
2.1
_
2.1
2.4

3.0
3.0
2.1
2.1
1.5
2.1
—
_
1.4
2.8
2.0
2.4
2.2
2.6
3.2
3.8
1.6
1.0
1.4
1.0
0.8
1.6
1.0
1.4

1.2
1.4
1.4
Stg
4
1.0
1.0
1.2
0.8
1.1
2.2
2.6
1.9

1.8
1.7
2.0
2.8
2.6
1.2
1.2
1.0
1.5
3.8
_
4.1
2.8
1.5
2.2
1.8
2.4
3.0
3.4
1.2
0.6
1.2
0.6
0.4
1.6
0.8
1.0

0.8
0.6
1.0
RBC
Out
0.8
0.8
0.7
0.3
0.4
0.4
0.4
1.6

1.5
0.7

1.0
1.9
0.7
0.3
0.7
1.1
4.2

5.2
2.8
1.9
2.4
1.8
2.2
2.0
2.2
1.0
0.8
0.8
0.4
0.2
0.6
0.6
1.2
0.6
0.4
0.5
0.8
                                   continued.
        136

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
*
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120

Date
5/28/77
5/29/77
5/30/77
5/31/77
6/1/77
6/2/77
6/3/77
6/4/77
6/5/77
6/6/77
6/7/77
6/8/77
6/9/77
6/10/77
6/11/77
6/12/77
6/13/77
6/14/77
6/15/77
6/16/77
6/17/77
6/18/77
6/19/77
6/20/77
6/21/77
6/22/77
6/23/77
6/24/77
6/25/77
6/26/77
6/27/77
6/28/77
6/29/77
6/30/77
iniii
7/2/77
7/3/77
7/4/77
7/5/77
7/6/77

Raw
4.6
4.4
3.0
4.2
4.0
4.6
5.0
3.2
3.8
4.0
4.4
4.6
-
-
5.2
5.0
4.6
4.8
4.2
4.2
4.4
4.8
-
4.6
4.6
5.0
4.6
3.8
5.0
5.2
4.2
4.4
5.2
3.2
3.0
-
-
-
-
3.2
RBC
In
2.0
1.4
2.2
2.8
2.2
1.2
1.6
2.4
1.6
1.6
3.2
1.4
-
-
4.2
2.4
2.2
2.8
1.6
1.0
2.0
2.2
-
1.8
1.8
2.2
1.8
1.8
3.8
3.8
1.4
2.2
3.4
0.8
0.8
-
-
-
-
1.0
stg
1
2.0
3.4
2.2
1.8
1.4
1.2
1.4
1.8
1.2
1.6
2.2
1.4
-
-
3.2
2.0
2.2
2.2
1.2
1.0
2.0
2.0
-
1.8
1.8
1.4
1.4
1.2
2.2
2.0
1.2
1.2
1.6
0.6
0.8
-
-
-
-
0.8
Stg
2
1.6
3.8
2.2
1.4
1.0
1.2
1.0
1.6
1.0
1.4
1.8
1.2
-
-
2.8
1.8
1.4
1.8
1.0
0.8
1.6
1.2
-
1.4
1.4
1.4
1.2
1.0
2.0
1.8
1.2
1.0
1.4
0.6
0.8
-
—
-
-
0.8
Stg
3
1.5
3.4
2.2
1.0
0.8
1.0
1.0
1.2
1.0
1.0
1.4
0.8
-
-
2.2
1.4
1.0
1.4
0.6
0.6
1.0
1.2
-
1.2
1.2
1.2
1.0
0.8
1.4
1.6
1.0
0.8
1.0
0.4
0.6
—
—
-
-
0.6
Stg
4
1.0
2.4
2.2
0.6
0.8
0.8
0.8
0.8
0.8
0.8
1.0
0.6
-
-
1.0
1.2
0.8
0.6
0.4
0.4
0.4
0.6
—
1.2
1.2
0.4
1.0
0.4
0.6
0.4
0.6
0.6
0.4
0.2
0.4
—
—
—
-
0.4
RBC
Out
0.8
1.2
2.2
0.6
0.8
0.6
0.8
i-.o
0.6
0.6
0.6
0.6
-
—
0.8
1.0
0.8
0.6
0.4
0.4
0.4
1.0
—
1.2
1.2
0.4
1.0
0.2
0.6
0.4
1.0
0.6
0.8
0.4
0.4
—
—
—
-
0.4
                                     continued
           137

-------
TABLE A-l.  (continued)

Day
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160

Date
7/7/77
7/8/77
7/9/77
7/10/77
7/11/77
7/12/77
7/13/77
7/14/77
7/15/77
7/16/77
7/17/77
7/18/77
7/19/77
7/20/77
7/21/77
7/22/77
7/23/77
7/24/77
7/25/77
7/26/77
7/27/77
7/28/77
7/29/77
7/30/77
7/31/77
8/1/77
8/2/77
8/3/77
8/4/77
8/5/77
8/6/77
8/7/77
8/8/77
8/9/77
8/10/77
8/11/77
8/12/77
8/13/77
8/14/77
8/15/77

Raw
3.8
5.2
4.4
3.8
3.8
4.3
4.4
3.4
4.6
3.0
3.0
4.0
0.8
3.8
2.6
1.6
4.0
3.0
4.6
4.0
3.0
-
3.2
2.2
2.2
2.6
3.6
1.2
3.2
1.4
3.4
2.2
3.6
3.2
3.2
3.6
-
3.4
4.0
4.0
RBC
In
1.6
3.2
1.2
1.4
2.4
2.2
1.4
2.6
2.8
1.2
1.0
1.4
1.2
3.2
0.4
0.6
1.6
1.0
0.4
0.3
0.2
—
1.0
0.6
1.0
0.8
1.8
1.3
0.4
0.4
0.6
0.4
1.8
1.6
1.0
1.2
-
1.8
1.4
2.6
Stg
1
0.8
1.2
2.0
1.0
1.0
0.8
0.8
1.0
1.4
0.8
0.4
0.6
0.6
0.8
0.2
0.4
0.6
0.8
0.4
0.3
0.3
—
0.8
0.8
0.6
0.8
1.2
0.6
0.4
0.4
0.6
0.4
1.2
0.8
0.6
0.6
_
1.0
1.0
4.2
Stg
2
0.8
1.2
1.2
1.0
1.0
0.8
0.8
1.0
1.6
0.8
0.6
0.8
0.8
0.8
0.2
0.4
0.4
0.8
0.6
0.4
0.4
_
0.8
0.8
0.6
0.6
1.0
0.6
0.3
0.4
0.6
1.6
1.2
0.6
0.6
0.6
_
0.8
0.8
4.4
Stg
3
0.8
1.0
1.4
0.8
0.8
0.6
0.6
0.8
1.4
0.8
0.6
0.4
0.4
0.6
0.2
0.2
0.4
0.8
0.4
0.5
0.2
_
0.8
0.8
0.6
0.4
0.4
0.4
0.3
0.4
0.8
2.0
1.2
0.6
0.6
0.4
_
1.0
0.8
4.4
Stg
4
0.2
0.2
0..8
0.6
0.4
0.2
0.4
0.6
1.2
0.6
0.4
0.4
0.4
0.4
0.1
0.2
0.8
0.6
0.4
0.2
0.4
—
0.8
0.6
0.3
0.4
0.2
0.2
0.4
0.6
0.6
0.8
0.6
0.8
0.8
0.6

1.2
1.0
3.8
RBC
Out
0.0
0.4
0.6
0.8
0.4
0.4
0.4
1.2
1.2
0.6
0.2
0.4
0.4
0.2
0.2
0.6
0.8
0.8
0.4
0.2
0.2
_
0.2
0.6
0.2
0.4
0.6
0.8
0.4
0.4
0.4
0.4
0.4
0.6
0.4
0.6

0.6
0.4
2.0
                                    continued.
         138

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200

Date
8/16/77
8/17/77
8/18/77
8/19/77
8/20/77
8/21/77
8/22/77
8/23/77
8/24/77
8/25/77
8/26/77
8/27/77
8/28/77
8/29/77
8/30/77
8/31/77
9/1/77
9/2/77
9/3/77
9/4/77
9/4/77
9/6/77
9/7/77
9/8/77
9/9/77
9/10/77
9/11/77
9/12/77
9/13/77
9/14/77
9/15/77
9/16/77
9/17/77
9/18/77
9/19/77
9/20/77
9/21/77
9/22/77
9/23/77
9/24/77

Raw
4.0
4.2
4.0
3.9
4.6
3.2
6.2
3.0
4.2
3.6
6.0
3.8
2.8
4.5
?.?
4.2
5.0
6.0
3.0
2.8
3.0
4.6
3.2
3.4
5.2
4.2
3.8
2.8
2.5
2.5
2.5
2.5
4.6
3.2
2.6
2.5
2.5
4.0
2.6
-
RBC
In
1.6
1.0
0.8
1.1
2.8
1.0
4.8
2.2
1.8
3.4
4.2
1.2
1.0
2.3
? ?
4.3
1.8
2.2
1.2
0.8
1.0
4.2
1.0
1.2
0.6
2.6
0.8
0.6
1.4
1.4
1.4
1.4
3.6
1.0
1.4
1.4
1.6
1.6
1.4
-
stg
1
1.0
0.7
0.8
0.7
1.2
0.8
3.2
0.6
0.8
1.2
2.0
0.8
0.6
0.6
?.?
5.7
1.1
1.2
1.2
1.2
1.0
1.6
1.8
1.0
0.8
1.5
1.0
0.8
1.0
0.8
0.8
1.0
1.4
0.8
0.6
0.8
0.8
0.8
0.6
-
Stg
2
1.0
0.4
0.5
0.7
0.8
1.2
2.4
0.6
0.2
1.2
1.6
0.6
0.4
0.4
?.?
5.8
1.4
0.8
1.4
1.4
0.8
0.8
1.2
0.8
0.8
1.8
1.2
0.8
0.8
0.8
0.8
0.8
1.0
0.8
1.0
1.0
0.6
0.6
0.6
-
stg
3
1.0
0.3
0.2
0.4
0.6
1.6
1.8
0.6
0.2
1.2
1.4
0.4
0.4
0.4
?.?
5.7
1.0
0.6
1.8
1.6
1.0
0.8
1.2
0.6
0.6
2.2
1.8
0.8
0.8
1.0
0.6
0.7
1.0
1.0
0.8
1.0
0.6
1.0
0.6
-
Stg
4
1.0
0.3
0.2
0.4
0.8
1.8
1.6
0.9
0.3
1.4
1.8
0.8
0.8
0.6
?.?
5.7
1.6
1.0
2.4
2.0
0.8
0.6
1.4
1.0
0.8
2.2
2.0
1.0
1.0
1.4
1.0
1.0
1.4
1.4
1.0
1.0
0.3
1.4
1.0
-
RBC
Out
0.4
0.3
0.2
0.4
0.6
0.8
0.6
0.3
0.2
0.6
1.6
0.6
0.2
0.2
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
1.4
0.4
0.6
0.8
0.6
0.4
0.2
0.4
0.3
0.4
0.4
0.4
0.3
0.3
0.3
0.6
0.4
-
                                     continued.
          139

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240

Date
9/25/77
9/26/77
9/27/77
9/28/77
9/29/77
9/30/77
10/1/77
10/2/77
10/3/77
10/4/77
10/5/77
10/6/77
10/7/77
10/8/77
10/9/77
10/10/77
10/11/77
10/12/77
10/13/77
10/14/77
10/15/77
10/16/77
10/17/77
10/18/77
10/19/77
10/20/77
10/21/77
10/22/77
10/23/77
10/24/77
10/25/77
10/26/77
10/27/77
10/28/77
10/29/77
10/30/77
10/31/77
11/1/77
11/2/77
11/3/77

Raw
_
—
-
-
-
-
-
-
-
3.2
-
6.0
2.6
5.4
-
5.1
5.2
4.3
4.4
4.6
7.6
5.2
1.0
5.2
4.2
7.4
6.2
5.4
4.0
4.0
4.6
5.6
5.2
4.4
5.0
3.8
4.0
4.2
4.0
3.8
RBC
In

—
—
—
—
-
-
—
-
1.8
—
3.5
2.8
3.6
-
4.6
3.1
3.0
2.0
3.0
6.8
2.6
3.4
2.0
3.0
7.0
5.8
5.0
2.8
1.6
2.8
2.8
3.4
2.6
3.4
3.0
3.0
2.8
3.4
2.2
stg
1

_
_
_
_
—
—
_
—
1.0
—
1.8
1.6
2.2
-
2.6
2.4
2.6
1.0
2.0
4.6
2.8
2.0
1.6
2.2
4.2
3.6
3.2
2.2
1.8
2.0
2.0
2.8
2.0
2.8
2.4
2.0
2.0
2.4
2.2
Stg
2

_
_
_
_
_
_
_
_
0.8
_
1.2
1.4
1.4
—
1.5
1.6
2.6
1.0
1.4
3.8
2.4
1.6
1.6
1.8
2.2
2.4
2.4
2.0
0.8
1.4
1.4
2.0
1.2
2.0
1.8
1.4
1.6
1.4
1.0
stg
3

_
_
_
_
_
_
_
_
1.4
_
1.0
1.4
1.4
—
1.2
1.4
2.2
1.4
1.4
4.0
2.2
1.6
1.6
2.0
2.0
2.2
1.8
1.8
0.8
1.0
0.8
0.8
0.8
1.6
1.2
0.8
0.8
0.8
0.6
stg
4

_
_
__
_
_
_
_
_
1.8
_
1.4
2.0
2.2
_
1.5
2.4
3.0
2.4
2.4
4.2
2.8
2.0
2.4
2.4
2.0
2.6
1.8
1.8
0.8
1.4
0.8
0.8
0.8
1.6
1.6
0.8
0.8
0.6
0.4
RBC
Out





—
_
_
_
0.2
_
0.6
0.4
0.4
_
0.4
0.4
0.5
0.8
0.6
3.0
4.2
1.2
0.8
0.4
2.8
2.6
1.0
1.4
1.2
0.8
0.6
0.8
0.4
0.6
0.4
0.5
0.8
0.4
0.4
                                    continued
        140

-------
TABLE A-l.   (continued)
          Dissolved Oxygen (mg/1)

Day
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280

Date
11/4/77
11/5/77
11/6/77
11/7/77
11/8/77
11/9/77
11/10/77
11/11/77
11/12/77
11/13/77
11/14/77
11/15/77
11/16/77
11/17/77
11/18/77
11/19/77
11/20/77
11/21/77
11/22/77
11/23/77
11/24/77
11/25/77
11/26/77
11/27/77
11/28/77
11/29/77
11/30/77
12/1/77
12/2/77
12/3/77
12/4/77
12/5/77
12/6/77
12/7/77
12/8/77
12/9/77
12/10/77
12/11/77
12/12/77
12/13/77

Raw
3.8
4.2
4.0
-
-
5.2
5.4
4.8
4.4
2.4
5.4
5.4
5.4
5.8
5.6
4.2
5.2
4.8
1.2
6.2
-
-
-
-
-
-
-
-
-
-
-
-
6.6
7.0
6.4
8.2
4.8
-
5.4
4.8
RBC
In
2.2
1.0
2.8
-
-
5.6
4.2
5.4
4.8
6.2
5.2
4.6
4.4
4.8
5.0
4.6
5.2
4.2
3.8
6.6
-
-
-
-
-
-
-
-
-
-
-
-
6.6
6.6
6.0
4.2
5.8
-
5.2
5.2
stg
1
2.2
2.4
2.2
-
-
5.0
5.0
4.6
4.2
5.0
3.6
3.5
3.2
3.8
3.8
3.8
4.0
3.6
2.8
5.6
-
-
-
-
-
-
-
-
-
-
-
-
6.4
5.2
4.6
6.4
5.2
-
4.5
4.0
Stg
2
1.0
1.4
1.6
-
-
5.0
4.2
4.0
3.6
4.2
3.0
2.4
1.8
2.8
2.8
3.6
3.6
2.4
2.0
5.0
-
-
-
-
-
-
-
-
-
-
-
-
4.6
4.4
3.4
5.8
5.0
-
3.6
3.4
Stg
3
0.6
1.4
1.6
-
-
4.2
4.4
3.8
3.2
4.0
2.0
2.0
1.0
1.6
1.8
3.8
2.8
1.6
1.2
4.4
-
-
-
-
-
-
-
-
-
-
-
-
4.6
4.4
2.6
5.4
5.4
-
3.0
2.6
Stg
4
0.4
1.4
1.6
-
-
4.2
4.5
3.4
3.0
4.2
2.2
2.2
1.4
1.6
2.2
3.6
2.6
1.8
1.4
4.2
-
-
-
-
-
-
-
-
-
-
-
-
3.8
4.0
2.8
5.2
5.4
-
3.2
2.8
RBC
Out
0.6
2.6
1.0
-
-
4.2
4.1
3.4
3.0
4.0
1.6
1.8
0.8
0.8
1.8
0.2
2.4
1.2
0.6
2.8
-
-
-
-
-
-
-
-
-
-
-
-
3.6
3.8
1.0
7.6
3.6
-
3.2
2.4
                                     continued
         141

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320

Date
12/14/77
12/15/77
12/16/77
12/17/77
12/18/77
12/19/77
12/20/77
12/21/77
12/22/77
12/23/77
12/24/77
12/25/77
12/26/77
12/27/77
12/28/77
12/29/77
12/30/77
12/31/77
1/1/78
1/2/78
1/3/78
1/4/78
1/5/78
1/6/78
1/7/78
1/8/78
1/9/78
1/10/78
1/11/78
1/12/78
1/13/78
1/14/78
1/15/78
1/16/78
1/17/78
1/18/78
1/19/78
1/20/78
1/21/78
1/22/78

Raw
5.0
4.0
3.8
3.8
4.4
3.4
4.2
-
-
-
-
-
-
-
-
-
-
-
-
-
4.6
5.2
3.4
3.6
4.2
6.2
3.8
1.2
1.2
1.2
2.8
2.4
1.0
2.0
-
9.2
8.8
-
8.2
7.6
RBC
In
4.8
5.2
5.2
3.2
3.0
4.8
5.4
-
-
-
-
-
-
-
-
-
-
-
-
-
4.6
4.8
3.8
4.0
4.6
6.2
4.2
2.0
2.4
1.6
2.8
4.4
1.4
2.8
-
9.0
9.6
-
8.2
8.2
Stg
1
4.0
4.4
4.6
4.2
-
4.4
4.8
-
-
-
-
-
-
-
-
-
-
-
-
-
4.4
4.2
3.4
3.4
4.2
5.4
4.4
2.1
2.2
2.2
2.8
3.0
2.2
2.8
-
7.8
7.6
-
5.4
6.2
Stg
2
3.2
3.8
3.6
3.6
-
4.0
4.4
'—
-
-
—
-
-
-
-
-
-
-
-
-
3.4
3.4
2.8
3.2
4.0
4.4
4.2
2.0
2.0
1.8
2.8
3.0
2.0
2.6
—
7.8
6.4
-
5.2
5.8
Stg
3
2.6
3.2
3.4
3.4
-
4.0
3.8
-
—
-
-
-
-
-
-
-
-
-
-
-
3.4
3.2
2.8
2.8
3.2
4.2
3.6
1.6
1.6
1.6
2.6
2.8
2.4
2.8
—
7.0
5.8
—
5.0
6.8
Stg
4
2.8
3.2
3.2
3.8
-
4.1
4.0
—
-
—
—
-
-
-
-
-
-
-
-
—
3.2
3.4
2.8
3.0
3.0
4.0
3.6
1.6
1.6
1.6
2.6
2.8
2.6
2.8
—
6.6
5.0
—
5.0
7.0
RBC
Out
2.4
3.2
3.2
3.0
-
3.8
3.8
—
—
—
_
-
-
-
-
-
-
-
—
—
3.4
2.4
1.6
1.2
2.0
4.0
2.6
1.6
1.2
1.6
2.4
4.4
1.8
2.0
—
3.2
5.1
—
5.0
5.2
                                    continued,
         142

-------
TABLE A-l.  (continued)
          Dissolved Oxygen (mg/1)

Day
r
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353

Date
1/23/78
1/24/78
1/25/78
1/26/78
1/27/78
1/28/78
1/29/78
1/30/78
1/31/78
2/1/78
2/2/78
2/3/78
2/4/78
2/5/78
2/6/78
2/7/78
2/8/78
2/9/78
2/10/78
2/11/78
2/12/78
2/13/78
2/14/78
2/15/78
2/16/78
2/17/78
2/18/78
2/19/78
2/20/78
2/21/78
2/22/78
2/23/78
2/24/78

Raw
8.2
2.6
-
10.2
8.8
9.0
8.6
8.8
7.4
8.1
8.0
8.4
8.6
9.0
-
-
5.4
6.2
8.0
8.4
7.2
9.6
8.6
7.8
9.2
7.4
8.2
8.6
-
8.2
9.4
7.8
6.6
RBC
In
6.6
7.0
-
10.1
8.2
8.2
8.2
8.0
6.8
7.8
6.4
7.5
7.2
8.2
-
-
6.2
5.8
6.3
8.0
6.0
7.8
8.1
8.0
8.2
6.9
8.2
8.0
-
7.4
7.0
6.6
6.2
Stg
1
4.6
4.6
-
9.4
6.7
7.2
6.8
7.0
4.4
5.0
4.0
5.1
6.0
7.0
-
-
5.0
5.0
5.0
4.0
4.0
6.2
6.0
6.0
5.8
5.6
7.2
6.8
-
6.2
5.4
5.2
5.0
Stg
2
3.8
3.8
-
9.7
7.3
6.8
6.8
6.8
4.2
4.4
3.8
3.6
5.6
6.0
—
-
4.8
3.8
3.5
3.8
3.8
4.9
4.2
5.0
5.4
4.0
6.0
6.0
-
4.8
3.8
4.0
4.4
Stg
3
3.2
3.8
—
8.6
7.2
7.2
6.8
6.8
4.2
4.5
4.4
3.6
5.0
5.4
—
—
3.6
3.8
2.8
3.2
3.2
4.4
3.6
4.4
4.0
3.2
4.5
5.6
—
4.0
3.2
3.4
3.8
Stg
4
3.4
3.8
—
8.3
6.8
6.6
6.6
6.8
4.4
4.4
4.5
3.4
4.8
5.4
—
—
3.4
3.6
2.4
3.0
3.0
4.2
3.2
4.0
3.8
3.0
5.2
5.0
—
3.6
3.0
3.2
3.7
RBC
Out
3.0
2.8
—
8.2
6.8
5.2
5.6
6.0
4.2
3.6
4.2
2.8
4.4
1.6
—
—
2.8
2.8
2.4
4.0
4.0
3.6
2.0
2.2
3.2
2.6
2.4
4.4
—
3.2
2.8
3.2
3.4
                                     continued.
          143

-------
TABLE A-l.  (continued)
1"\ _ -.
uay
i
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

Date
3/9/77
3/10/77
3/11/77
3/12/77
3/13/77
3/14/77
3/15/77
3/16/77
3/17/77
3/18/77
3/19/77
3/20/77
3/21/77
3/22/77
3/23/77
3/24/77
3/25/77
3/26/77
3/27/77
3/28/77
3/29/77
3/30/77
3/31/77
4/1/77
4/2/77
4/3/77
4/4/77
4/5/77
4/6/77
4/7/77
4/8/77
4/9/77
4/10/77
4/11/77
4/12/77
4/13/77
4/14/77
4/15/77
4/16/77
4/17/77

Raw
106
190
151
123
130
72
108
97
124
93
87
-
108
112
50
80
64
71
-
-
121
111
93
59
105
87
111
141
51
127
-
—
—
169
117
195
171
132
-
-
— Q 	 -
In
109
160
183
140
142
70
90
88
126
87
87
—
119
118
51
62
-
-
84
84
112
112
101
72
120
93
100
82
_
117
_
_
_
135
102
159
159
117
126
135
RBC
Out
34
34
45
33
38
15
18
16
23
20
30

26
22
14
13
14
17
17
11
13
9
16
18
19
10
10
16
_
20
_,
_
-^
22
13
_
27
15
19
24

Raw
52
109
76
82
87
22
46
43
74
49

_
57

28

39
50

—
84
_
50
29
86
37
58
87
42
63



62
68
42

41

-

In
61
84
91
91
86
26
48
37
98
s \j
56


77

29

_
_
62
24
64

33
38
71
41
43
75

63



72
71
41

50
156
81
ซ6' -1-/
RBC
Out
22
itt L*
29
ฃ* y
35
19
25
&• — /
13
i 5
X -J
i i
ฑ. X
?s
4.J
14
J. ™

14
j. ~
15

10
9
10

12

5
4
10
10
JL. \J
9
12
X 4U
11



g
VJ
g
\j
19
X 7
99
ฃ.ฃ.
9
7
i 7
X /
16
                                   continued
       144

-------
   TABLE A-l.  (continued)
BOD,-T (mg/1)
BOD,-S (mg/1)
J RBC
Day
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
Date
4/18/77
4/19/77
4/20/77
4/21/77
4/22/77
4/23/77
4/24/77
4/25/77
4/26/77
4/27/77
4/28/77
4/29/77
4/30/77
5/1/77
5/2/77
5/3/77
5/4/77
5/5/77
5/6/77
5/7/77
5/8/77
5/9/77
5/10/77
5/11/77
5/12/77
5/13/77
5/14/77
5/15/77
5/16/77
5/17/77
5/18/77
5/19/77
5/20/77
5/21/77
5/22/77
5/23/77
5/24/77
5/25/77
5/26/77
5/27/77
Raw
156
195
183
225
109
-
162
144
171
168
207
129
100
158
161
174
185
234
128
-
72
111
110
147
147
128
153
104
137
131
153
131
204
176
126
162
143
98
171
-
In
137
191
191
197
102
100
195
144
146
165
183
142
-
138
170
153
162
221
114
-
-
121
102
150
159
123
147
122
138
155
168
129
162
153
110
141
137
95
149
155
Out
18
39
25
30
17
18
21
15
27
26
25
24
26
23
18
50
30
20
25
-
17
15
16
29
21
16
20
14
21
16
50
53
60
67
38
47
55
36
58
44
Raw
77
123
188
129
61
105
108
68
100
108
153
-
64
92
87
138
149
180
71
-
42
46
57
107
122
102
-
-
-
-
-
-
-
-
-
—
-
45
90
-
RBC
In
86
129
210
150
60
82
86
94
114
104
144
96
-
67
92
108
113
-
94
-
-
89
63
96
111
92
-
-
-
-
-
-
-
-
-
—
-
43
85
-
Out
9
33
22
25
12
15
20
15
18
76
28
13
24
26
13
25
31
63
27
-
16
16
17
27
20
17
-
-
-
-
-
-
-
-
-
-
-
25
34
28
                                        continued,
            145

-------
TABLE A-l.  (continued)

Day
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120

Date
5/28/77
5/29/77
5/30/77
5/31/77
6/1/77
6/2/77
6/3/77
6/4/77
6/5/77
6/6/77
6/7/77
6/8/77
6/9/77
6/10/77
6/11/77
6/12/77
6/13/77
6/14/77
6/15/77
6/16/77
6/17/77
6/18/77
6/19/77
6/20/77
6/21/77
6/22/77
6/23/77
6/24/77
6/25/77
6/26/77
6/27/77
6/28/77
6/29/77
6/30/77
7/1/77
7/2/77
7/3/77
7/4/77
7/5/77
7/6/77

Raw
143
159
144
148
159
179
155
119
116
137
—
-
183
68
-
102
123
123
168
124
170
136
-
153
201
135
136
162
120
118
153
183
153
166
112
-
—
—
—
180
J
In
145
140
135
124
144
120
144
159
108
129
_
-
185
68
—
119
96
147
158
128
146
111
—
143
174
153
128
146
148
138
180
190
152
189
123
—
—
_
_
152
RBC
Out
60
45
18
43
72
54
74
78
45
48
_
_
25
26
—
42
30
20
51
57
66
53
_
53
98
86
47
52
56
57
53
86
66
114
57
_
_
_
_
48
                       BOD.-S  (ing/I)
                          ^     RBC
                   Raw
                   117
                    83
                    23

                    60
                    65
                    70
                    90
                    79
                    92
                    63

                    63
                    71
                    61
                    55
                    80
                   104
                   108
                    84
                   108
In
                             55
                             65
                             63
                             65
                             80
 72
 86
 21

 62
 52
116
 93
 78
105
 66

 58
 92
 69
 57
 72
102
115
 84
105
 99
Out
          15
          20
          25
          24
          39
 30
 32
 16

 25
 28
 37
 39
 24
 30
 14

 19
 46
 38
 28
 28
 24
 56
 48
 57
 42
                                    continued.
        146

-------
   TABLE A-l.  (continued)
BOD,-T (mg/1)
J RBC
Day
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
Date
7/7/77
7/8/77
7/9/77
7/10/77
7/11/77
7/12/77
7/13/77
7/14/77
7/15/77
7/16/77
7/17/77
7/18/77
7/19/77
7/20/77
7/21/77
7/22/77
7/23/77
7/24/77
7/25/77
7/26/77
7/27/77
7/28/77
7/29/77
7/30/77
7/31/77
8/1/77
8/2/77
8/3/77
8/4/77
8/5/77
8/6/77
8/7/77
8/8/77
8/9/77
8/10/77
8/11/77
8/12/77
8/13/77
8/14/77
8/15/77
Raw
192
189
-
-
-
-
-
573
144
-
132
104
168
96
132
159
165
154
98
146
117
119
-
146
111
110
138
143
185
161
111
120
108
102
131
122
92
138
120
126
In
134
170
-
-
-
-
-
120
140
164
126
118
173
122
156
144
105
143
-
144
105
144
-
158
114
102
132
159
146
138
131
95
146
113
126
122
129
128
62
-
Out
58
64
-
-
-
-
-
15
51
72
34
21
46
29
48
53
24
31
20
44
31
31
-
44
22
18
29
37
32
30
21
21
13
38
26
31
28
19
13
11
BOD -S (mg/1)
   5     RBC
                      Raw
                        54
                       101
                        65
                        62
                       100
                        60
                        71
                       109
                        52
     In
Out
     102
     108
      68
     114
     103
       48
       66
       86
      109
       94
       80
       71
       63
      116
       115
 31
 34
 25
 35
 26
53
85
-
-
43
94
73
80
21
30
23
16
   9
  16
  21
  17
  17
  11
  33
  20
  18
  35
                                        continued.
             147

-------
   TABLE A-l.  (continued)
BOD,-! (mg/1)
T\ r+ t-r
Day
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
TN .
Date
8/16/77
8/17/77
8/18/77
8/19/77
8/20/77
8/21/77
8/22/77
8/23/77
8/24/77
8/25/77
8/26/77
8/27/77
8/28/77
8/29/77
8/30/77
8/31/77
9/1/77
9/2/77
9/3/77
9/4/77
9/4/77
9/6/77
9/7/77
9/8/77
9/9/77
9/10/77
9/11/77
9/12/77
9/13/77
9/14/77
9/15/77
9/16/77
9/17/77
9/18/77
9/19/77
9/20/77
9/21/77
9/22/77
9/23/77
9/24/77

Raw
113
102
129
130
104
107
130
95
117
79
142
140
161
118
150
147
—
—
—
—
-
-
—
-
-
—
—
76
128
153
144
189
117
108
122
132
224
156
-
	 D 	
In
152
112
146
141
130
120
120
100
120
110
170
165
115
122
135
135
_
_
_
_
_
_
_
_
_
_
_
83
131
223
153
201
117
117
124
149
209
—
RBC
Out
63
22
27
33
23
19
22
19
26
20
36
31
15
9
20
38
—
_
—
ซ.
^
M
_
^
—
_^
_>
17
38
41
26
35
19
18
16
28
73
25


Raw
57
77

94

_
_
59

85
115
	
	
__L_
111











ซ_
nT1
127

m
M
_
_
-
152
98

^ *^ ป hS \ I
In
82
74
115
90


113
81
72
88
145

75
93
122











93

169
121
149


91
120
164

"&/ •*• /
RBC
Out
46
"V
Of)
4t w
30
ซJ w
?s
ฃ• -J

17
X /
1 f>
X w
1 9
X ฃ.
70
•b \J
25

1 0
X \J
1 6
X VJ
40
™ w










1 9
x y
9A
t,H
98
/. O
24
&• *T
30
J W

20
&• \J
28
60

                                      continued
         148

-------
TABLE A-l.  (continued)
                       BQDC-S
RBC
Day
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
Date
9/25/77
9/26/77
9/27/77
9/28/77
9/29/77
9/30/77
10/1/77
10/2/77
10/3/77
10/4/77
10/5/77
10/6/77
10/7/77
10/8/77
10/9/77
10/10/77
10/11/77
10/12/77
10/13/77
10/14/77
10/15/77
10/16/77
10/17/77
10/18/77
10/19/77
10/20/77
10/21/77
10/22/77
10/23/77
10/24/77
10/25/77
10/26/77
10/27/77
10/28/77
10/29/77
10/30/77
10/31/77
11/1/77
11/2/77
11/3/77
Raw
	
-
-
-
-
-
-
-
-
171
159
161
177
155
-
57
134
-
159
140
132
84
138
195
179
178
113
120
122
158
249
282
137
183
195
178
175
186
210
186
In
—
-
-
-
-
-
-
-
-
193
160
185
197
-
-
64
135
135
251
183
-
123
149
164
124
180
105
132
117
140
209
206
138
105
171
136
138
174
131
150
Out
_
-
-
-
-
-
-
-
-
33
26
30
44
-
-
6
27
145
95
33
23
12
19
41
46
56
29
22
28
25
66
70
40
56
65
41
38
45
45
50
                                RBC
                   Raw
In
Out
                            127
                            171
                             85
                             121
                             92
                             144
                             57
                              73
                             113
                             119
                              88
                             107
                              93
                              58
                              32
                              56
                             113
                              88
         22
         18

         72
          16
          43
          19
          21
          16
          24
          46
          31
          26
          28
          41
          30
          18
          22
          33
          22

         continued
         149

-------
TABLE A-l.  (continued)

ฃฃZ
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
T> •ป*.—.
Date
11/4/77
11/5/77
11/6/77
11/7/77
11/8/77
11/9/77
11/10/77
11/11/77
11/12/77
11/13/77
11/14/77
11/15/77
11/16/77
11/17/77
11/18/77
11/19/77
11/20/77
11/21/77
11/22/77
11/23/77
11/24/77
11/25/77
11/26/77
11/27/77
11/28/77
11/29/77
11/30/77
12/1/77
12/2/77
12/3/77
12/4/77
12/5/77
12/6/77
12/7/77
12/8/77
12/9/77
12/10/77
12/11/77
12/12/77
12/13/77

Raw
165
109
110
-
_
—
69
111
72
74
97
168
219
194
170
130
128
101
171
222
_
—
—
—
_
—
_
—
_
_
_
119
137
116
81
122

146
150
~~ ^
In
179
122
113
116
_
_
56
109
78
78
95
139
208
161
170
137
117
128
147
192
_
_
__
_
__
—
-t-
—
mm
^
^^
144
167
134
143
M
134
197
RBC
Out
58
34
32
31

_
18
43
17
23
35
57
82
44
73
44
38
37
45
60











31
40
35
38

20
UWf. O V1
Raw In
96

- ftfi
\j\j

63
74 84

7A
100
139
111
92 123

- 71
/ 1
88 97
136











77 73
75 89
81 76
70

78
110
"&/ J-y
RBC
Out
24

09
JZ

31
34

o o
zz
30
62
40
42

~
38
49

~
"

~
~
~
"~
~
"^
^
20
23
16
17
™"
11
                                   continued,
       150

-------
   TABLE A-l.  (continued)
BOD/-T (mg/1)
J RBC
Day
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
Date
12/14/77
12/15/77
12/16/77
12/17/77
12/18/77
12/19/77
12/20/77
12/21/77
12/22/77
12/23/77
12/24/77
12/25/77
12/26/77
12/27/77
12/28/77
12/29/77
12/30/77
12/31/77
1/1/78
1/2/78
1/3/78
1/4/78
1/5/78
1/6/78
1/7/78
1/8/78
1/9/78
1/10/78
1/11/78
1/12/78
1/13/78
1/14/78
1/15/78
1/16/78
1/17/78
1/18/78
1/19/78
1/20/78
1/21/78
1/22/78
Raw
152
113
141
122
129
114
102
131
-
-
-
-
-
-
-
-
-
-
-
-
134
257
159
164
186
135
123
107
189
174
92
99
87
131
146
242
87
74
96
92
In
141
119
141
137
135
107
168
167
-
-
-
-
-
-
-
-
-
-
-
-
182
206
174
159
180
152
146
98
161
168
158
144
96
119
108
221
104
98
119
126
Out
39
31
22
21
25
15
12
19
-
-
-
-
-
-
-
-
-
-
-
-
38
-
49
35
34
34
23
20
—
38
32
26
17
19
26
27
20
10
16
32
                      Raw
                       94
                        60
                        59
Y'S  (mg/1)
                                   RBC
  In
   89
   55
   94
                                 60
                                 74
                                 67
   86
   69
   91
  112
  108
   87
   82
  135
   62
   59
Out

 22
 22
 23
           13
           13
           15
98
153
-
-
96
129
119
106
23
-
29
27
  15
  18

  20
  23
  16
  14
  21
  24
  13
                                        continued
            151

-------
   TABLE A-l.  (continued)
BOD -T (mg/1)

Day
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353

Date
1/23/78
1/24/78
1/25/78
1/26/78
1/27/78
1/28/78
1/29/78
1/30/78
1/31/78
2/1/78
2/2/78
2/3/78
2/4/78
2/5/78
2/6/78
2/7/78
2/8/78
2/9/78
2/10/78
2/11/78
2/12/78
2/13/78
2/14/78
2/15/78
2/16/78
2/17/78
2/18/78
2/19/78
2/20/78
2/21/78
2/22/78
2/23/78
2/24/78

Raw
192
252
168
101
77
66
60
132
126
219
102
196
164
159
137
185
216
222
210
129
125
201
242
227
182
341
157
105
—
201
302
237
210
	 D 	
In
260
213
185
72
57
83
66
125
50
155
168
174
195
188
174
183
167
171
162
170
150
192
243
225
209
203
173
153

213
261
242
218
RBC
Out
24
25
31
17
10
12
10
16
29
33
17
33
135
53
46
42
45
49
45
46
46
45
41
46
41
50
20
30

53
102
55
56
                          BOD,-S (mg/1)

Raw
_
-
—
—
:
34
-
-
—
67
57
-
—
-
:
69
—
-
—
-
99
—
-
—
	 D 	
In
92
137
108
52
45
53
42
94
85
104
90
87
85
119
84
107
113
125
99
87
109
136
116
99
RBC
Out
22
20
21
12
11
12
16
29
11
24
26
30
39
37
34
36
29
34
32
29
29
81
34
38
                                      continued,
         152

-------
    TABLE A-l.  (continued)
COD-T (mg/1)
COD-S (mg/1)
RBC
Day
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Date
3/9/77
3/10/77
3/11/77
3/12/77
3/13/77
3/14/77
3/15/77
3/16/77
3/17/77
3/18/77
3/19/77
3/20/77
3/21/77
3/22/77
3/23/77
3/24/77
3/25/77
3/26/77
3/27/77
3/28/77
3/29/77
3/30/77
3/31/77
4/1/77
4/2/77
4/3/77
4/4/77
4/5/77
4/6/77
4/7/77
4/8/77
4/9/77
4/10/77
4/11/77
4/12/77
4/13/77
4/14/77
4/15/77
4/16/77
4/17/77
Raw
250
-
396
-
-
184
-
235
-
250
-
-
-
-
-
-
-
-
-
-
-
-
-
237
-
-
298
-
201
-
-
-
-
328
-
326
252
278
-
-
In
306
-
388
-
-
205
-
155
-
224
-
-
-
-
-
-
-
-
-
236
-
-
-
242
-
-
171
-
-
-
-
-
-
270
-
302
238
254
-
-
Out
141
-
82
-
-
110
-
Ill
-
108
-
-
-
-
-
-
-
-
-
60
-
-
-
55
-
-
38
-
-
-
-
-
-
58
-
78
73
70
-
-
Raw
168
-
136
-
-
110
-
114
-
148
-
-
-
-
-
-
-
-
-
-
-
-
-
133
-
-
106
-
66
-
-
-
-
124
-
200
176
166
-
-
RBC
In
187
-
120
-
-
134
-
98
-
102
-
-
-
-
-
-
-
-
-
121
-
-
-
114
-
-
92
-
-
-
-
-
-
146
-
218
180
180
-
-
Out
129
-
82
-
-
73
-
51
-
74
-
-
-
-
-
-
-
-
-
58
-
-
-
48
-
-
33
-
-
-
-
-
-
42
-
72
69
58
-
-
                                        continued.
              153

-------
    TABLE A-l.  (continued)
COD-T (mg/1)
TV
Day
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80

Date
4/18/77
4/19/77
4/20/77
4/21/77
4/22/77
4/23/77
4/24/77
4/25/77
4/26/77
4/27/77
4/28/77
4/29/77
4/30/77
5/1/77
5/2/77
5/3/77
5/4/77
5/5/77
5/6/77
5/7/77
5/8/77
5/9/77
5/10/77
5/11/77
5/12/77
5/13/77
5/14/77
5/15/77
5/16/77
5/17/77
5/18/77
5/19/77
5/20/77
5/21/77
5/22/77
5/23/77
5/24/77
5/25/77
5/26/77
5/27/77

Raw
310
-
322
446
228
—
—
304
—
312
—
332
—
—
316
-
384
412
316
-
—
188
-
320
436
320
—
—
376
296
328
356
368
-
—
348
432
220
204
408
RBC
In
292
—
286
316
224
_
_
292
—
266
_
268
_
_
264
_.
286
330
274
—
_
226
—
304
158
261
_
_
292
319
287
256
277
—
_
336
314
202
210
362
Out
79
_
91
80
65
_
_
70
_
76
_
77
_
_
144
_
86
105
72
_
_
49
_
70
80
73
__
_
63
89
116
131
132

_
117
150
102
96
126
Raw
136

202
200
124
^
— ป
140
_
204

200

_
270

200
232
190

_
108

170
184
204


.^
_|_
„
_
—
^

_
ซ*•
93
93
— ~* \, *"ฃ> f J. /
RBC
In
138

208
186
128


176

184

218


182

196
258
192


130

176
130
228


_








93
82
Out
58
— / \J
81
70
52


58

71

72


142

89
105
68


45
~ -•/
67
69
\? s
74











75
/ — '
58
97
                                       continued
            154

-------
    TABLE A-l.  (continued)
COD-T (mg/1)
RBC
Day
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
Date
5/28/77
5/29/77
5/30/77
5/31/77
6/1/77
6/2/77
6/3/77
6/4/77
6/5/77
6/6/77
6/7/77
6/8/77
6/9/77
6/10/77
6/11/77
6/12/77
6/13/77
6/14/77
6/15/77
6/16/77
6/17/77
6/18/77
6/19/77
6/20/77
6/21/77
6/22/77
6/23/77
6/24/77
6/25/77
6/26/77
6/27/77
6/28/77
6/29/77
6/30/77
7/1/77
7/2/77
7/3/77
7/4/77
7/5/77
7/6/77
Raw
w
-
396
-
324
244
264
-
-
256
-
-
-
128
-
-
320
436
384
392
284
-
-
316
548
444
392
236
-
-
344
372
372
361
316
-
-
-
-
-
In
_
-
240
215
285
229
165
-
-
223
-
-
346
136
-
-
277
378
346
325
266
-
-
285
413
389
317
275
-
-
291
323
352
330
243
-
-
-
-
323
Out
_
-
75
106
150
102
123
—
-
96
-
-
100
64
-
-
115
186
186
144
124
-
-
116
284
236
148
98
-
-
136
166
178
159
112
—
-
-
-
130
Raw
_
-
-
-
-
-
106
—
-
194
—
—
181
66
—
—
160
178
176
176
170
—
—
208
269
275
173
157
—
-
205
205
211
213
-
-
-
-
-
-
RBC
In
_
-
200
172
120
96
96
—
—
205
—
—
181
53
—
—
133
200
197
184
162
—
—
-
237
288
187
155
—
-
181
205
221
219
152
—
-
-
-
187
Out
_
—
46
76
92
62
75
~ •
—
69
—
—
100
48
—
—
71
109
118
97
116
—
—
89
160
173
88
70
—
—
85
162
121
116
77
—
—
-
—
74
                                         continued.
             155

-------
    TABLE A-l.  (continued)
COD-T (mg/1)

Day
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160

Date
7/7/77
7/8/77
7/9/77
7/10/77
7/11/77
7/12/77
7/13/77
7/14/77
7/15/77
7/16/77
7/17/77
7/18/77
7/19/77
7/20/77
7/21/77
7 722/77
7/23/77
7/24/77
7/25/77
7/26/77
7/27/77
7/28/77
7/29/77
7/30/77
7/31/77
8/1/77
8/2/77
8/3/77
8/4/77
8/5/77
8/6/77
8/7/77
8/8/77
8/9/77
8/10/77
8/11/77
8/12/77
8/13/77
8/14/77
8/15/77
RBC
Raw
_
-
-
—
-
-
-
-
309
—
—
—
-
260
368
412
-
-
288
-
356
—
—
—
—
352
-
376
336
346
-
-
268
468
588
544
—
—
284
In
320
280
—
_
295
288
236
252
295
_
_
_
402
285
373
357
-
_
245
186
269
_
_
_
_
296
307
316
268
267
—
_
163
256
288
293.
344
_
_
-
Out
195
118
_
_
132
152
128
123
112
_
_
_
146
112
126
122
-
_
74
112
104
_
_
_
_
86
94
98
90
98
_
_
83
142
88
136
130
^
-^
108
Raw

_
_
_
_
_
_
_
194
_
M
_
_
173
_
_
_

184
_
_
_
_

_
219

_
_
222


-
179
264
280


160
> — o ' '
RBC
In
138
189


188
202
143
214
171



__
_
221
245


184
179
176




171
193
201
175
152


128
189
195
219
224



Out
100
101


112
101
110
104
97



121
95
104
116
108

59
98
100




68
71
/ J.
90
j\j
80
82


66-76?

85
vS~s
98
ซ/ \j

7ft
                                       continued
           156

-------
                         TABLE A-l.   (continued)
                     COD-T (mg/1)
 Day   Date

 161   8/16/77
 162   8/17/77
 163   8/18/77
 164   8/19/77
 165   8/20/77
 166   8/21/77
 167   8/22/77
 168   8/23/77
 169   8/24/77
 170   8/25/77
 171   8/26/77
 172   8/27/77
 173   8/28/77
 174   8/29/77
 175   8/30/77
 176   8/31/77
 177   9/1/77
 178   9/2/77
 179   9/3/77
 180   9/4/77
 181    9/4/77
 182    9/6/77
 183    9/7/77
 184    9/8/77
 185    9/9/77
 186    9/10/77
 187    9/11/77
 188    9/12/77
 189    9/13/77
 190    9/14/77
 191    9/15/77
 192    9/16/77
 193    9/17/77
 194    9/18/77
 195    9/19/77
 196    9/20/77
 197    9/21/77
 198    9/22/77
 199    9/23/77
200    9/24/77

Raw
—
248
360
292
338
-
236
208
304
414
366
370
446
384
460
588
448
388
456
284
328
382
400
496
380
264

In
392
411
352
287
307
275
152
300
319
301
308
344
415
309
349
344
424
288
365
405
288
332
307
349
324
-
RBC
Out
192
127
86
106
107
90
96
99
109
103
94
147
332
164
152
121
153
75
138
140
108
126
76
109
137
74
COD-S (mg/1)

Raw
_
179
-
160
_
-
-
117
235
_
-
232
260
183
-
187
256
_
-
192
-
™*
_
—
225
189

In
216
221
240
163
192
189
180
216
264
217
203
220
287
180
189
195
256
173
217
227
245
255
220
213
245
-
RBC
Out
126
102
112
133
78
73
92
112
126
58
85
119
213
124
100
90
120
65
96
94
116
125
87
108
106
75
                                                            continued
                                  157

-------
    TABLE A-l.  (continued)
COD-T (mg/1)

Day
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
RBC
Date
9/25/77
9/26/77
9/27/77
9/28/77
9/29/77
9/30/77
10/1/77
10/2/77
10/3/77
10/4/77
10/5/77
10/6/77
10/7/77
10/8/77
10/9/77
10/10/77
10/11/77
10/12/77
10/13/77
10/14/77
10/15/77
10/16/77
10/17/77
10/18/77
10/19/77
10/20/77
10/21/77
10/22/77
10/23/77
10/24/77
10/25/77
10/26/77
10/27/77
10/28/77
10/29/77
10/30/77
10/31/77
11/1/77
11/2/77
11/3/77
Raw
_
-
-
-
-
—
-
—
-
454
286
420
324
-
—
182
294
351
346
236
-
-
320
340
-
224
252
-
-
316
456
516
224
290
-
-
356
348
596
356
In

-
—
—
-
—
-
_
—
415
312
347
349
—
—
199
307
279
381
309
—
—
280
336
128
328
272
—
_
245
363
395
299
335
_
—
376
268
316
284
Out

—
_
_
—
_
_
_
_
100
80
100
96
—
_
51
82
388
172
78
_
_
76
114
72
102
80
_
_
72
116
158
110
101
_
_
104
98
108
131
COD-S (mg/1)
                                    RBC
                       Raw
      In
Out
                               250
               81
                               252
                               224
                               203
                               128
                               211
                               173
                               149
                               192
                               235
                               184
                               209
                               128
                               181
                               178
               84

              106
               79
              106
               63
               88
               77
               44
               95
              123
               86
              101
              66
              104
              102

              continued
            158

-------
    TABLE A-l.  (continued)
CQD-T (mg/1)
COD-S (mg/1)
RBC
Day
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
Date
11/4/77
11/5/77
11/6/77
11/7/77
11/8/77
11/9/77
11/10/77
11/11/77
11/12/77
11/13/77
11/14/77
11/15/77
11/16/77
11/17/77
11/18/77
11/19/77
11/20/77
11/21/77
11/22/77
11/23/77
11/24/77
11/25/77
11/26/77
11/27/77
11/28/77
11/29/77
11/30/77
12/1/77
12/2/77
12/3/77
12/4/77
12/5/77
12/6/77
12/7/77
12/8/77
12/9/77
12/10/77
12/11/77
12/12/77
12/13/77
Raw
480
-
-
-
-
- .
262
284
-
-
320
461
488
374
344
-
-
384
364
438
-
-
-
-
-
-
-
-
-
-
-
-
320
292
336
304
-
-
284
428
In
268
-
-
301
-
-
170
243
-
-
273
309
351
311
337
-
-
257
309
311
-
-
-
-
-
-
-
-
-
-
-
-
491
336
304
349
-
-
243
405
Out
101
-
-
116
-
-
85
117
-
-
137
144
146
123
163
-
-
98
104
125
-
-
-
-
-
-
-
-
-
-
-
-
120
85
93
125
-
-
54
-
RBC
Raw In
216
-
-
117
-
-
137
196 185
-
-
181
212
241
225
235 272
-
-
192
200 220
219
-
-
- -
-
-
-
-
-
-
-
-
-
155 181
197
173 157
226
-
-
157
208
Out
105
-
-
91
-
-
89
95
-
-
88
101
121
109
144
-
-
102
109
113
-
-
-
-
-
-
-
-
-
-
-
-
72
61
71
89
-
-
45
-
                                         continued.
             159

-------
    TABLE A-l.  (continued)
CQD-T (mg/1)
RBC
Day
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
Date
12/14/77
12/15/77
12/16/77
12/17/77
12/18/77
12/19/77
12/20/77
12/21/77
12/22/77
12/23/77
12/24/77
12/25/77
12/26/77
12/27/77
12/28/77
12/29/77
12/30/77
12/31/77
1/1/78
1/2/78
1/3/78
1/4/78
1/5/78
1/6/78
1/7/78
1/8/78
1/9/78
1/10/78
1/11/78
1/12/78
1/13/78
1/14/78
1/15/78
1/16/78
1/17/78
1/18/78
1/19/78
1/20/78
1/21/78
1/22/78
Raw
444
308
268
-
-
252
312
288
-
-
-
-
-
-
-
-
-
-
-
-
304
464
484
384
-
-
260
288
400
424
276
—
—
276
296
492
196
132
—
-
In
344
237
275
—
-
234
272
315
-
-
-
-
—
-
-
-
-
—
—
—
309
355
336
320
-
—
248
188
275
304
336
—
—
253
208
421
203
109
—
—
Out
92
76
61
—
—
49
72
80
—
_
—
—
—
—
—
—
-
—
_
—
76
—
113
105
—
—
75
87
_
111
115
_
_
71
80
64
63
31
_
_
COD-S (mg/1)
                                    RBC
                       Raw
                       162
      In
     112
     165
                               144
                               173
                               133
                       123
                        93
     128
     155
     176
     261
     200
     179
     125
     213
     131
      59
Out

 77
 76
 64
               59
               81
               68
168
270
-
-
168
214
203
213
80
-
93
92
 61
 88

116
 71
 74
 52
 61
 65
 30
                                        continued.
            160

-------
    TABLE A-l.  (continued)
COD-T (mg/1)
RBC
Day
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
Date
1/23/78
1/24/78
1/25/78
1/26/78
1/27/78
1/28/78
1/29/78
1/30/78
1/31/78
2/1/78
2/2/78
2/3/78
2/4/78
2/5/78
2/6/78
2/7/78
2/8/78
2/9/78
2/10/78
2/11/78
2/12/78
2/13/78
2/14/78
2/15/78
2/16/78
2/17/78
2/18/78
2/19/78
2/20/78
2/21/78
2/22/78
2/23/78
2/24/78
Raw
176
232
341
376
164
-
-
256
484
520
565
336
-
-
460
364
380
696
340
-
-
380
464
432
408
400
-
-
-
508
772
476
440
In
149
197
343
224
157
-
-
235
448
144
466
376
-
-
307
187
371
405
301
-
-
299
456
536
592
360
-
-
-
475
499
517
424
Out
39
36
81
44
35
-
-
55
60
88
47
75
-
-
87
85
124
145
101
-
-
85
108
99
115
-
-
-
-
157
235
136
152
COD-S (mg/1)

Raw
67
-
-
-
—
107
-
-
-
131
91
-
-
-
:
109
-
-
-
-
277
-
-
-

In
80
125
209
99
72
147
181
189
160
157
136
179
277
221
152
176
213
237
445
208
283
272
219
259
RBC
Out
32
36
80
48
41
49
69
66
58
66
74
78
92
132
89
74
90
87
103
100
120
177
114
113
                                         continued
             161

-------
                        TABLE A-l.  (continued)
Day
Date
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
3/9/77
3/10/77
3/11/77
3/12/77
3/13/77
3/14/77
3/15/77
3/16/77
3/17/77
3/18/77
3/19/77
3/20/77
3/21/77
3/22/77
3/23/77
3/24/77
3/25/77
3/26/77
3/27/77
3/28/77
3/29/77
3/30/77
3/31/77
4/1/77
4/2/77
4/3/77
4/4/77
4/5/77
4/6/77
4/7/77
4/8/77
4/9/77
4/10/77
4/11/77
4/12/77
4/13/77
4/14/77
4/15/77
4/16/77
4/17/77


Raw
136
294
145
143
139
188
234
155
141
160
125
^
136
154
83
63
155
158
•™
—
322
282
168
99
119
101
150
188
48
136
206
178
162
161
150
~
^
TSS
RBC
In
161
156
144
201
183
161
131
128
100
111
112
—
132
125
91
51
-
-
87
194
175
132
159
116
116
114
117
132
-
100
132
146
108
100
110
91
89
(mg/1)

Out
37
33
44
45
61
26
31
23
20
19
37
-
27
21
16
11
29
28
19
83
27
11
36
17
15
11
8
22
36
15
25
29
20
14
23
17
21

RBC
Sludge

_
_
_
_
_
_
19,060
20,700
22,020
27,780
22,260
27,650
22,000
25,240
22,000
25,200
22,500
14,100
16,200
17,500
16,000
13,800
23,200
17,200
18,800
16,300
19,00
20,600
20,400
22,600
25,200
33,000
30,600
25,400
16,300
13,400
                                                           continued.
                                162

-------
                        TABLE A-l.  (continued)
                                          TSS  (mg/1)
Day
Date
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
4/18/77
4/19/77
4/20/77
4/21/77
4/22/77
4/23/77
4/24/77
4/25/77
4/26/77
4/27/77
4/28/77
4/29/77
4/30/77
5/1/77
5/2/77
5/3/77
5/4/77
5/5/77
5/6/77
5/7/77
5/8/77
5/9/77
5/10/77
5/11/77
5/12/77
5/13/77
5/14/77
5/15/77
5/16/77
5/17/77
5/18/77
5/19/77
5/20/77
5/21/77
5/22/77
5/23/77
5/24/77
5/25/77
5/26/77
5/27/77
RBC
Raw
178
212
192
308
137
119
149
181
198
110
160
148
234
140
148
195
220
238
172
-
-
153
168
193
132
175
115
173
234
104
206
190
-
132
244
219
248
164
173
143

In
127
109
125
131
96
104
168
151
116
108
81
108
170
136
134
120
113
106
121
-
-
Ill
168
143
114
147
118
103
125
134
145
115
-
97
137
141
149
123
122
141

Out
17
33
22
25
22
20
26
21
26
24
22
25
29
19
22
15
9
26
40
-
-
13
38
26
21
28
25
13
20
26
54
49
-
44
45
61
77
57
45
46
RBC
Sludge
18,400
10,000
21,800
19,700
14,200
27,100
13,000
36,400
22,800
-
-
-
-
-
-
29,700
33,700
28,200
38,900
19,400
14,600
24,400
24,800
16,800
18,200
11,600
23,200
24,600
25,600
28,900
33,800
16,800
35,900
29,800
21,300
22,700
26,600
15,800
29,000
26,100
                                                             continued.
                                 163

-------
                        TABLE A-l.  (continued)
Day
Date
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
5/28/77
5/29/77
5/30/77
5/31/77
6/1/77
6/2/77
6/3/77
6/4/77
6/5/77
6/6/77
6/7/77
6/8/77
6/9/77
6/10/77
6/11/77
6/12/77
6/13/77
6/14/77
6/15/77
6/16/77
6/17/77
6/18/77
6/19/77
6/20/77
6/21/77
6/22/77
6/23/77
6/24/77
6/25/77
6/26/77
6/27/77
6/28/77
6/29/77
6/30/77
7/1/77
7/2/77
7/3/77
7/4/77
7/5/77
7/6/77


Raw
155
103
186

186
184
164
169
179
130


205
67
~
135
108
252
344
252
147
140
~"
240
299
128
149
122
136
222
135
182
175
~
113
*
289
TSS
~~RBC
In
109
96
92
~
143
152
113
126
117
74
^
""
175
79
•~
105
106
146
125
105
107
109
—
154
189
136
137
138
136
163
122
147
147
~
95
_
181
(mg/1)

Out
53
38
26
-
78
59
72
77
58
59
—
—
82
38
—
56
35
78
92
46
30
51
-
53
105
65
38
39
48
60
39
66
74
—
43
-
58

RBC
Sludge
36,400
11,100
17,900
24,900
11,900
11,000
17,600
31,300
18,900
34,400
26,600
25,500
26,000
30,300
44,100
39,800
41,100

18,500
32,670
23,700
22,360
21,330
16,580
16,630
23,080
26,270
13,200
27,090
21,730
17,730

23,270
26,900
13,900
21,170
26,000
                                                           continued.
                                164

-------
                       TABLE A-l.  (continued)
Day

121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
 143
 144
 145
 146
 147
 148
 149
 150
 151
 152
 153
 154
 155
 156
 157
 158
 159
 160
  Date

7/7/77
7/8/77
7/9/77
7/10/77
7/11/77
7/12/77
7/13/77
7/14/77
7/15/77
7/16/77
mini
7/18/77
7/19/77
7/20/77
7/21/77
7/22/77
7/23/77
7/24/77
7/25/77
7/26/77
7/27/77
7/28/77
7/29/77
7/30/77
7/31/77
8/1/77
8/2/77
8/3/77
 8/4/77
 8/5/77
 8/6/77
 8/7/77
 8/8/77
 8/9/77
 8/10/77
 8/11/77
 8/12/77
 8/13/77
 8/14/77
 8/15/77

RBC
Raw
302
332
214
216
207
258
252
170
157
136
170
203
143
134
156
170
20
134
155
229
151
127
152
149
171
304
178
167
197
122
102
218
172
278
214
280
182
135
130
TSS

In
180
128
130
95
99
83
108
107
106
105
95
98
145
139
138
-
-
108
118
142
108
163
202
-
129
133
197
110
105
90
56
83
75
99
100
79
99
52
-
(mg/1)

Out
66
58
51
23
15
52
21
24
40
44
39
15
38
37
40
31
-
31
19
55
71
27
31
10
15.2
14.9
35.2
9.6
5.3
6
19
9
43
26
27
18
34
17
33

RBC
Sludge
22,360
17,830
3,290
10,690
15,410
9,000
13,080
10,460
2,620
22,400
16,000
17,640
23,640
27,730
20,000
30,080
6,720
6,520
11,690
11,140
7,650
12,120
27,200
29,200
19,200
22,960
43,040
22,000
22,800
23,090
36,080
24,560
29,610
31,100
31,200
38,800
22,500
12,000
30,300
                                                             continued.
                                  165

-------
                        TABLE A-l.  (continued)
Day
Date
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
8/16/77
8/17/77
8/18/77
8/19/77
8/20/77
8/21/77
8/22/77
8/23/77
8/24/77
8/25/77
8/26/77
8/27/77
8/28/77
8/29/77
8/30/77
8/31/77
9/1/77
9/2/77
9/3/77
9/4/77
9/4/77
9/7/77
9/8/77
9/9/77
9/10/77
9/11/77
9/12/77
9/13/77
9/14/77
9/15/77
9/16/77
9/17/77
9/18/77
9/19/77
9/20/77
9/21/77
9/22/77
9/23/77
9/24/77
                                          TSS  (mg/1)

Raw
169
180
174
148
152
125
205
136
168
149
99
89
127
234
208
373
227
139
~
104
256
126
113
307
155
106
117
143
181
104
111
141
105
59
156
159
138
109
RBC
In
212
179
157
133
104
104
136
112
—
167
112
108
95
107
156
141
173
133
87
39
90
96
77
224
174
106
100
130
125
149
147
108
74
95
123
87
110
—

Out
80
33
34
42
23
22
22
21
81
30
32
19
7
13
30
26
145
45
14
9
12
14
34
30
52
29
27
14
27
39
30
26
93
16
14
28
39
14
RBC
Sludge
21,000
35,800
23,100
17,400
26,400
27,200
30,100
28,800
25,600
31,100
24,200
25,000
25,700
25,200
23,700
31,400
23,000
16,700
25,900
21,800
18,400
22,500
25,200
29,300
27,300
26,400
24,500
22,100
24,400
40,400
25,900
20,800
27,500
26,400
38,300
21,900
26,360
25,140
                                                           continued.
                               166

-------
                        TABLE  A-l.   (continued)
Day

201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
 237
 238
 239
 240
  Date

9/25/77
9/26/77
9/27/77
9/28/77
9/29/77
9/30/77
10/1/77
10/2/77
10/3/77
10/4/77
10/5/77
10/6/77
10/7/77
10/8/77
10/9/77
10/10/77
10/11/77
10/12/77
10/13/77
10/14/77
10/15/77
10/16/77
10/17/77
10/18/77
10/19/77
10/20/77
10/21/77
10/22/77
10/23/77
10/24/77
10/25/77
10/26/77
10/27/77
10/28/77
 10/29/77
 10/30/77
 10/31/77
 11/1/77
 11/2/77
 11/3/77
                                RBC
Raw
 135
 105
 129
  90
                                          TSS   (mg/1)
                                       In
154
130
117
103
75
106
127
121
86
163
68
136
118
-
99
60
—
31
130
140
172
50
163
180
194
238
208
346
292
99
101
95
145
119
128
102
114
113
104
102
49
46
69
58
147
138
112
197
110
156
104
172
154
152
                                             Out
34
 8
20
15
                         RBC
                        Sludge.
22,940
22,060
22,100
22,100
12
18
314
70
19
13
3
8
50
-
42
40
9
17
17
29
19
26
120
45
21
26
34
45
40
26,500
31,320
30,480
29,540
33,880
23,816
19,180
23,340
21,346
17,388
13,448
13,872
12,644
12,688
13,120
13,400
13,620
26,300
20,600
30,900
26,700
31,500
28,800
24,100
26,900
                                                             continued.
                                 167

-------
                          TABLE A-l.   (continued)'
                                           TSS
  Day

  241
  242
  243
  244
  245
  246
  247
  248
  249
  250
  251
  252
  253
  254
  255
 256
 257
 258
 259
 260
 261
 262
 263
 264
 265
 266
 267
 268
 269
 270
 271
 272
 273
 274
 275
 276
 277
 278
 279
280
   Date

  11/4/77
  11/5/77
  11/6/77
  11/7/77
  11/8/77
  11/9/77
  11/10/77
  11/11/77
  11/12/77
  11/13/77
  11/14/77
  11/15/77
  11/16/77
  11/17/77
 11/18/77
 11/19/77
 11/20/77
 11/21/77
 11/22/77
 11/23/77
 11/24/77
 11/25/77
 11/26/77
 11/27/77
 11/28/77
 11/29/77
 11/30/77
 12/1/77
 12/2/77
 12/3/77
 12/4/77
 12/5/77
 12/6/77
 12/7/77
 12/8/77
 12/9/77
12/10/77
12/11/77
12/12/77
12/13/77
RBC 	
Raw
164
117
147
-
77
142
104
60
126
152
199
125
109
86
72
178
304
211
In
150
146
175
138
64
99
83
83
100
103
130
102
111
97
109
110
105
112
Out
42
33
57
56
22
45
33
25
72
70
68
51
47
43
30
31
45
35
RBC
Sludee
•••""fp*-
30,280
23,410
23,300
28,050
25,710
28,900
24,780
21,200
18,800
22,000
19,210
13,270
27,140
27,030
16,650
26,380
19,300
21,630
136
121
119
100
123

153
168
170
126
118
 86
 86
197
66
32
34
30
—
—
22
—
28,480
29,140
25,270
22,910
19,190
19,450
20,150
15,220
                                                           continued
                                168

-------
                        TABLE A-l.   (continued)
Day
Date
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
12/14/77
12/15/77
12/16/77
12/17/77
12/18/77
12/19/77
12/20/77
12/21/77
12/22/77
12/23/77
12/24/77
12/25/77
12/26/77
12/27/77
12/28/77
12/29/77
12/30/77
12/31/77
1/1/78
1/2/78
1/3/78
1/4/78
1/5/78
1/6/78
1/1/18
1/8/78
1/9/78
1/10/78
1/11/78
1/12/78
1/13/78
1/14/78
1/15/78
1/16/78
1/17/78
1/18/78
1/19/78
1/20/78
1/21/78
1/22/78
                                          TSS  (mg/1)
                                RBC
Raw

163
162
 88
 83
 78
108
 98
121
 In

142
152
 98
110
140
110
125
136
129
188
176
123
183
127
152
168
134
236
92
36
161
91
200
345
128
180
189
164
133
125
162
102
126
134
153
86
104
106
102
43
144
99
93
153
83
120
129
79
Out

 25
 32
 10
 10
 17
 16
 11
 10
 RBC
Sludge

12,540
10,540
13,960
27,240
25,850
20,180
21,540
23,450
18
-
36
59
28
34
25
14
-
32
33
22
28
20
13
16
7
17
28
2
11,970
5,790
28,520
26,610
20,440
16,520
17,940
16,930
17,030
18,220
24,280
20,480
21,720
19,280
18,600
19,420
18,820
22,620
22,000
20,850
                                                             continued
                                 169

-------
TABLE A-l.  (continued)
                  TSS  (mg/1)

Day
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
RBC
Date
1/23/78
1/24/78
1/25/78
1/26/78
1/27/78
1/28/78
1/29/78
1/30/78
1/31/78
2/1/78
2/2/78
2/3/78
2/4/78
2/5/78
2/6/78
2/7/78
2/8/78
2/9/78
2/10/78
2/11/78
2/12/78
2/13/78
2/14/78
2/15/78
2/16/78
2/17/78
2/18/78
2/19/78
2/20/78
2/21/78
2/22/78
2/23/78
2/24/78
Raw
146
188
194
241
89
284
147
178
257
393
207
233
207
192
210
220
225
310
231
57
251
245
311
217
260
209
298
259
-
183
349
307
208
In
127
174
143
137
70
106
90
81
171
195
243
157
110
118
116
147
116
129
123
134
131
159
230
217
240
155
107
136
-
162
164
211
128
Out
36
13
15
9
4
14
13
14
10
14
15
23
26
29
19
29
40
24
30
39
35
28
22
20
24
20
32
22
_
45
54
35
13
RBC
Sludge
24,600
25,880
24,110
f
22,510
17,340
20,260
22,220
27,410
22,710
20,190
26,870
24,020
18,040
15,640
19,340
25,290
21,630
18,290
18,170
27,170
21,980
24,270
18,320
20,670
j
12,910
23,980
25,780
25,730
18,410
31,420
27,100
j
-
        170

-------
TABLE A-2.  EDGEWATER NITROGEN DATA SUMMARY


Date
3/16/77
3/28/77
4/1/77
4/4/77
4/7/77
4/11/77
4/13/77
4/15/77
4/18/77
4/20/77
4/22/77
4/27/77
4/29/77
5/2/77
5/4/77
5/6/77
5/9/77
5/11/77
5/13/77
6/1/77
6/6/77
6/9/77
6/10/77
6/13/77
6/16/77
6/17/77
6/20/77
6/22/77
6/27/77
6/29/77
7/7/77
7/20/77
7 722/77
7/25/77
7/27/77
8/1/77
8/4/77
8/5/77

Raw
inf.
0.1

0.1
0.1
0.9
0.2
0.1
0.5
0.1
0.1
0.2
0.1
0.4
0.4
1.6

0.1
1.8
9.8
0.3
0.1
0.1
0.1








0.1


0.1





RBC
Inf.
0.9
0.1
0.1
2.6
2.2
0.5
0.1
0.7
0.1
0.2
0.1
0.1
0.7
0.2
0.1
0.1
3.1
0.9
0.1
0.2
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.2
0.1
-
Eff.
0.6
3.3
1.8
0.1
4.3
0.9
0.4
0.6
0.5
0.5
0.5
0.1
0.1
1.2
0.1
0.1
2.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.2
0.1
0.1
N00

1
0.1





0.1
0.2

0.1




0.1


0.1

0.1

0.1


0.1


0.1


0.1
0.1
0.1
-
0.1

0.1
0.1
-N


Stage
2






0.1
0.1

0.1




0.1


0.1

-

0.1


0.1


0.1


0.1
0.1
0.1
-
0.1

0.1
0.1
3






0.1
0.1

0.1




-


2.9

0.1

0.1


0.1


0.1


0.1
0.1
0.1
—
0.1

0.1
0.1
4






0.1
0.1

0.1




2.1


2.2

0.1

0.1


0.1


0.1


0.1
0.1
0.1
-
0.1

0.1
0.1
                                    continued.
                 171

-------
                        TABLE A-2.   (continued)
 Date

8/8/77
8/10/77
8/12/77
8/17/77
8/19/77
8/24/77
8/26/77
8/29/77
8/31/77
9/2/77
9/14/77
10/17/77
10/25/77
10/31/77
12/21/77
1/27/78
2/3/78
2/10/78
2/17/78
2/24/78
Raw
inf.
RBC
Inf.
—
—
~
—
—
—
—
—
—
0.1
—
0.1
1.8
0.7
0.9
0.8
0.9
Eff.
0.3
0.1
—
0.6
0.4
0.6
0.5
1.2
1.5
0.2
0.5
0.1
2.1
0.8
0.5
0.3
0.1
1

0.1
0.1
0.1
0.1
0.1
0.1

0.1



1.6
0.5
0.4
0.1
0.3
J — 	 	
Stage
2

0.1
0.1
0.1
0.1
0.1
0.1

0.1



1.6
0.1
0.1
0.1
0.1
3

0.1
0.1
0.1
0.1
0.1
0.1

0.1



2.1
0.1
0.3
0.2
0.4
4

0.1
0.1
0.1
0.1
0.8
0.3

0.5



2.5
0.9
0.6
0.3
0.1
                                                      continued
                            172

-------
TABLE A-2.  (continued)
             TKN Total

Date
3/16/77
3/28/77
4/1/77
4/4/77
4/7/77
4/11/77
4/13/77
4/15/77
4/18/77
4/20/77
4/22/77
4/27/77
4/29/77
5/2/77
5/4/77
5/6/77
5/9/77
5/11/77
5/13/77
6/1/77
6/6/77
6/9/77
6/10/77
6/13/77
6/16/77
6/17/77
6/20/77
6/22/77
6/27/77
6/29/77
iniii
7/20/77
7/22/77
Raw
inf.
24.4

19.5
20.1
47.4
34.5
19.4
34.0
40.8
21.1
23.1
25.5
24.8
27.7
25.8

20.5
37.7
34.0
28.5
26.6
26.3
29.7








20.3

RBC
inf.
22.5
20.2
18.8
20.2
44.2
31.9
11.8
29.9
35.0
22.3
19.4
23.1
23.0
26.1
26.4
24.1
28.0
34.6
19.2
24.4
29.9
29.3
11.6
25.2
16.1
21.3
19.4

24.6
22.4
24.8
24.4
24.1

eff. 1
14.2
11.2
11.8
9.8
28.5
12.2
11.8 29.9
16.4 23.8
22.2
16.0 19.1
14.5
14.9
15.1
16.8
17.3 26.9
14.3
14.2
17.6 15.9
15.7
33.6 32.4
21.0
26.8 25.0
14.0
18.7
18.9
19.6
15.9

17.5
16.6
16.3
18.2 22.6
17.7 22.5
Stage
234






29.1 27.8 22.3
22.8 22.3 28.3

19.4 17.4 21.7




36.1 - 39.6


24.7 16.7 24.1

31.7 24.4

35.7 25.7 26.7









28.4 18.8 18.2
40.0 24.5 23.0
                              continued.
       173

-------
TABLE A-2.  (continued)
             TKN Total
Date
7/25/77
7/27/77
8/1/77
8/4/77
8/5/77
8/8/77
8/10/77
8/12/77
8/17/77
8/19/77
8/24/77
8/26/77
8/29/77
8/31/77
9/2/77
9/14/77
10/17/77
10/25/77
10/31/77
12/21/77
1/27/78
2/3/78
2/10/78
2/17/78
2/24/78
Raw
inf.

14.0
24.9

26.9
26.4
25.4
26.2
25.9


22.1
21.8
25.9

30.1
23.9
21.6

16.1
9.9
29.1

29.8

RBC
inf.
29.9
23.3
22.8
26.9
22.7
23.3
22.4
23.0
26.2
23.1
23.4
23.6
25.2
23.3
22.6
30.0
23.9
22.1
—
13.3
8.9
24.1
25.4
27.4
25.1
eff.
28.2
17.0
17.2
26.1
17.1
18.1
14.9
15.9
15.9
17.2
13.4
15.0
15.4
16.3
16.3
21.7
15.5
16.1
_
11.4
3.7
15.4
16.8
17.3
15.7
1

22.0
_
24.4
_

27.5
_
25.6

27.0
22.2

23.6

29.4




7.4
20.3
27.5
31.2
20.8
Stage
2

32.2

26.5
_

51.9

21.5

25.9
27.5

26.1

24.5




10.3
31.0
25.4
30.3
22.1
3

20.3

21.8


27.0

21.4

23.9
29.3

20.7

26.2




7.2
26.6
17.8
30.9
17.4
4

13.6

19.8


18.3

18.8

23.2
21.0

18.3

26. 1




6.3
\y • —/
17.1
19.5
28.0
14.9
                           continued.
     174

-------
TABLE A-2.  (continued)
           TKN Filtered

Date
3/16/77
3/28/77
4/1/77
4/4/77
4/7/77
4/11/77
4/13/77
4/15/77
4/18/77
4/20/77
4/22/77
4/27/77
4/29/77
5/2/77
5/4/77
5/6/77
5/9/77
5/11/77
5/13/77
6/1/77
6/6/77
6/9/77
6/10/77
6/13/77
6/16/77
6/17/77
6/20/77
6/22/77
6/27/77
6/29/77
7/1/77
7/20/77
i mm
Raw
inf.

14.0
18.7
16.8
19.4
14.2
17.0
25.8
30.3
21.1
21.5
23.4
24.3

24.1

22.3
30.7
30.6
21.1
21.9
20.0
8.7
19.4
14.6
19.8
17.8
21.8
21.4
17.6
19.8
-
-
RBC
inf.

9.9
17.9
14.4
15.7
20.7
15.7
24.7
32.1
22.8
21.4
22.8
21.9
23.7
26.0
23.0
21.5
24.7
30.0
29.3
25.0
22.2
6.5
18.1
16.5
17.0
15.7
14.7
15.7
13.0
14.5
-
—

eff. 1


12.0
9.0
27.2
11.8
11.0 19.8
15.6 23.8
20.7
15.6 22.3
14.7
14.9
14.8
16.1
16.9 22.0
16.7
14.2
17.4 23.5
19.3
20.1 20.7
20.4
20.3 19.7
5.9








— —
— —
Stage
234






21.3 20.6 17.7
21.0 18.3 12.1

15.9 23.4 15.3




26.0 - 16.6


21.5 22.2 23.6

22.7 27.3

23.6 23.4 19.5









_ — —
• — ^
                           continued.
        175

-------
TABLE A-2.  (continued)
           TKN Filtered
Date
7/25/77
7/27/77
8/1/77
8/4/77
8/5/77
8/8/77
8/10/77
8/12/77
8/17/77
8/19/77
8/24/77
8/26/77
8/29/77
8/31/77
9/2/77
9/14/77
10/17/77
10/25/77
10/31/77
12/21/77
1/27/78
2/3/78
2/10/78
2/17/78
2/24/78
Raw RBC
inf. inf.
20.6
18.5
32.0
-
_
19.7 16.0
20.6 19.8
18.8
18.1
19.7 20.2
21.0
18.2 18.6
18.1
23.2 20.9
_
_
12.9
7.0
11.7
28.0 24.4
22.2
25.0 17.4
eff.
15.9
13.7
16.6
15.6
15.6

12.4
15.0
14.6
13.8
11.6
13.4
14.1
12.5
14.2
19.5
14.5

_
10.3
2.3
13.9
16.4
15.1
14.9
1

_
„_
16.2

19.9
18.4
17.6
21.8
18.6
17.8
22.3



6.0
17.8
22.2
24.0
15.9
Stage
2



19.2

16.9
18.2
17.3
19.3
18.6
15.4
21.2



6.6
17.9
18.2
19.5 .
15.1
3



19.8

14.0
14.9
16.8
18.5
16.8
14.6
26.2



5.9
15.3
16.0
• 22.1
11.5
4



16.2

9.7
14.0
15.8
16.9
14.6
9.1
26.6



3.3
15.3
18.6
16.2
12.9
                           continued.
    176

-------
TABLE A-2.  (continued)


Date
3/16/77
3/28/77
4/1/77
4/4/77
4/7/77
4/11/77
4/13/77
4/15/77
4/18/77
4/20/77
4/22/77
4/27/77
4/29/77
5/2/77
5/4/77
5/6/77
5/9/77
5/11/77
5/13/77
6/1/77
6/6/77
6/9/77
6/10/77
6/13/77
6/16/77
6/17/77
6/20/77
6/22/77
6/27/77
6/29/77
7/1/77
7/20/77
7/22/77

Raw
inf.
9.4

12.9
13.0
8.9
16.2
10.3
11.6
15.2
13.4
13.2
8.1
12.3
16.7
14.1

11.8
15.6
15.0
16.5
20.7
18.8
5.3








12.8



RBC
inf.
5.9
12.3
12.7
7.0
4.2
15.3
9.7
9.9
14.9
12.5
12.1
11.3
12.8
17.9
12.4
16.1
10.1
16.3
21.8
15.8
22.1
19.0
6.1
17.8
14.0
16.5
16.8
14.3
17.9
14.6
15.9
14.2
15.0
eff.
9.0
7.6
9.5
12.3
3.6
10.7
11.3
11.2
14.1
12.9
13.2
12.7
13.1
14.2
13.3
12.1
11.8
11.4
15.7
16.1
16.7
16.5
5.0
15.6
16.0
14.3
15.6
14.0
14.5
12.8
14.3
11.5
12.0
NH0

1






13.9
14.2

15.6




17.3


12.6

16.9

18.9


16.0


16.8


16.3
13.1
14.9
-N

Stage
2






14.4
14.1

15.8




20.7


14.3

—

20.2


16.5


20.1


16.5
13.9
15.7
3






11.4
12.9

14.2






4






10.
12.

13.













2
6

2




U.b


11.5

16.5

18.3


14.2


14.5


15.8
12.3
13.9




12.1

18

18


13


15


14
11
13

.5

.7


.8


.9


.7
.6
.8
                              continued.
        177

-------
TABLE A-2.  (continued)

Date
7/25/77
7/27/77
8/1/77
8/4/77
8/5/77
8/8/77
8/10/77
8/12/77
8/17/77
8/19/77
8/24/77
8/26/77
8/29/77
8/31/77
9/2/77
9/14/77
10/17/77
10/25/77
10/31/77
12/21/77
1/27/78
2/3/78
2/10/78
2/17/78
2/24/78

Raw
inf.

13.4
16.7
14.5
15.9
14.0
14.1
14.3
14.0
16.3
13.4
17.2
13.6
15.6

6.5
3.3
11.8
11.5
15.7
11.7
NH -N
RBC
inf.
15.9
14.6
17.8
15.3
14.4
15.9
13.3
13.2
14.6
14.5
12.0
13.3
16.4
12.6
14.1
18.7
13.3
15.1
26.8
5.6
2.2
8.0
8.7
11.9
9.9
eff.
13.4
11.9
13.9
12.1
12.7
13.1
9.2
10.7
11.3
12.1
9.4
10.7
11.6
9.8
12.3
16.1
12.0
13.2
16.5
6.6
1.7
9.6
12.4
12.5
11.7
1

13.4
14.9
15.5
13.5
14.7
14.7
14.7
15.4
14.6
13.7
17.3



2.9
13.3
13.0
15.6
12.5
Stage
2

14.2
14.0
14.2
13.9
14.6
13.6
14.3
17.0
14.2
13.0
15.6



3.0
12.6
12.8
15.0
13.2
3

12.6
12.2
13.9
10.8
10.3
11.1
13.3
16.6
13.3
12.0
13.0



3.2
11.3
12.0
19.0
12.0
4

12.6
10.4
12.8
9.4
11.4
10.8
12.3
15.2
12.3
9.9
13.3



1.3
9.7
14.4
12.3
11.8
                              continued,
    178

-------
TABLE A-2.  (continued)
               NO -N

Date
3/16/77
3/28/77
4/1/77
4/4/77
4/7/77
4/11/77
4/13/77
4/15/77
4/18/77
4/20/77
4/22/77
4/27/77
4/29/77
5/2/77
5/4/77
5/6/77
5/9/77
5/11/77
5/13/77
6/1/77
6/6/77
6/9/77
6/10/77
6/13/77
6/16/77
6/17/77
6/20/77
6/22/77
6/27/77
6/29/77
7/1/77
7/20/77
7/22/77
Raw
inf.
0.1

0.11
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1

0.1
0.1
0.1
0.1
0.1
0.1
0.1








0.1

RBC
inf.
0.1
0.1
0.1
0.2
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
eff.
0.1
0.1
0.1
0.1
0.1
0.2
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
^ Stage
1234






0.1 0.1 0.1 0.1
0.1 0.1 0.1 0.1

0.1 0.1 0.1 0.1




0.1 0.1 0.1 0.1


0.1 0.1 0.1 0.1

0.1 - 0.1 0.1

0.1 0.1 0.1 0.1


0.1 0.1 0.1 0.1


0.1 0.1 0.1 0.1


0.1 0.1 0.1 0.1
0.1 0.1 0.1 0.1
0.1 0.1 0.1 0.1
                            continued.
        179

-------
                         TABLE A-2.   (continued)
  Date

 7/25/77
 7/27/77
 8/1/77
 8/4/77
 8/5/77
 8/8/77
 8/10/77
 8/12/77
 8/17/77
 8/19/77
 8/24/77
 8/26/77
 8/29/77
 8/31/77
 9/2/77
 9/14/77
 10/17/77
 10/25/77
 10/31/77
 12/21/77
 1/27/78
 2/3/78
 2/10/78
2/17/78
2/24/78
Raw
inf,
0.1
                                        NO^-N
RBC
inf.
0.1
0.1
0.1
0.1
—
—
—
~
—
—
—
—
—
—
0.1
—
0.1
0.1
0.1
0.1
0.1
0.1
eff.
0.1
0.1
0.3
0.3
0.3
0.2
0.1
—
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.2
1.9
0.2
0.1
0.1
0.1
0.1
1

0.1
—
0.1
0.1

0.1
0.1
0.1
0.1
0.1
0.1

0.1



0.1
0.1
0.1
0.1
0.1
Stage
2

0.1
_
0.1
0.1

0.1
0.1
0.1
0.1
0.1
0.1

0.1



0.1
0.1
0.1
0.1
0.1
3

0.1
_
0.1
0.1

0.1
0.1
0.1
0.1
0.1
0.1

0.1



0.2
0.1
0.1
0.1
0.1
4

0.1

0.4
0.4

0.1
0.1
0.1
0.1
0.1
0.1

0.1



0.2
0.1
0.1
0.1
0.1
                                                  continued.
                             180

-------
TABLE A-3.  EDGEWATER RBC DATA - SULPHUR

Raw
Date inf.
3/16/77
3/28/77
4/7/77
4/13/77
4/20/77
4/27/77
5/4/77 0.1
5/6/77
5/9/77 0.1
5/11/77
5/13/77
6/1/77 0.1
6/6/77 0.1
6/9/77 0.1
6/10/77 0.1
6/16/77
6/20/77
7/8/77
7/20/77
7/27/77
8/4/77
8/17/77
8/19/77
8/24/77
8/26/77
8/31/77
9/14/77
12/16/77
1/27/78 0.1
2/10/78 0.1
2/24/78 0.1


s
RBC
inf.
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
-
-
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
-
-
-
0.1
0.1
0.1
0.1
0.1
eff.
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
-
-
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
o.i
0.1
0.1
0.1
1






0.1


-

0.1

1.3


0.1
0.1
0.1
0.1
0.1
0.1
-
0.1
0.1
0.2
0.1
-
—
-
—
(mg/1)


Stage
2






0.3


0.8

-

7.0


1.2
0.9
0.2
1.1
0.3
0.1
—
0.1
0.1
0.1
0.1
-
—
—
—
3






—


1.1

0.1

2.0


0.1
0.1
0.1
0.1
0.1
0.1
—
0.1
0.1
0.3
0.1
—
—
—
—
4






1.3


0.8

4.0

4.0


0.1
0.1
0.1
0.1
0.1
0.1
—
0.1
0.1
0.1
0.1
—
—
—
—
                                    continued.
                181

-------
TABLE A-3.  (continued)

Raw
Date inf.
3/16/77
3/28/77
4/7/77
4/13/77
4/20/77
4/27/77
5/4/77 88
5/6/77
5/9/77 76
5/11/77 96
5/13/77 100
6/1/77
6/6/77 65
6/9/77 90
6/10/77 65
6/16/77
6/20/77
7/8/77
7/20/77
7/27/77
8/4/77
8/17/77
8/19/77
8/24/77
8/26/77
8/31/77
9/14/77
12/16/77
1/27/78 54
2/10/78 75
2/24/78 73


RBC
inf.
67
78.6
76
78
75
84
80
108
78
92
96
_
55
95
70
75
150
46.4
74
95
42
69
84
77
166
65
55
54
85
93
eff.
70
78.0
77
76
73
78
80
78
78
65
80

65
90
70
83
110
60.8
90
89
65
75
86
144
87
120
84
60
52
75
93
so,

1






75


78

_

130

130
36.4
76
66
48
73
190
94
145
51

mm
_
-
(mg/1)


Stage
2






63


80



85

92
11.2
30
49
29
75
164
78
135
58



-
3









78



100

116
36.7
70
68
66
89
154
79
170
64
v/~


-
4






55
-x -J

76
/ \J


75

128
46.4
70
/ w
89
57
50
144
83
130
Qf.
OU



     182

-------
        TABLE A-4.   EDGEWATER RBC DATA - GREASE & OIL (mg/1)
               Raw           RBC          	  Stage
Date           inf.     inf.     eff.
4/20/77
6/1/77
6/16/77
6/29/77
7/27/77
8/4/77
8/17/77
8/24/77
8/30/77
9/14/77
12/15/77
1/9/78
1/24/78
2/9/78
2/13/78
2/21/78
24
60.6
59.4
58
23
50
27
66
81
20
-
31
22
96
48
48
20
79.0
64.7
22
36
17
40
87
80
27
33
23
35
45
48
42
113
45.4
19.3
60
3
1
39
33
45
1
14
15
9
11
12
14




9 36 18 15
12 26 2 6

78 39 37 21








                                  183

-------
 Date

8/30/77

9/14/77

2/9/78

2/13/78

2/21/78
Ortho-phosphate (mg/1 as P)
Raw inf  RBC inf   RBC eff
                      Total PO/-P (mg/1)
                   Raw inf  RBC inf  RBC eff
  5.50

  3.13
A. 76

4.63
5.87

3.40
                               4.50     4.25      2.60

                               4.75     4.63      2.88

                               5.38     5.50      4.25
                             184

-------
                TABLE A-6.   ANALYSIS OF INTERSTAGE SAMPLES
                                              Chemical oxygen demand
                                                  (COD)   (mg/1)
Date
Day
 Eff.
temp.
 (C)
                       cu m
Flow
(mgd)
RBC
influent
T
S
Stages
1
(S)
2 3
4
Low Loading Period:  March 9-April 6, 1977; Baffles after Shafts 1, 2, 3
                     (6" clearance)
3/14/77   6     12.5   1343    (0.355) 205    134     74    61    94    54
3/16/77   8     13.0   1620    (0.428) 155     98     78    34    63    60
Average

Moderate

4/13/77
4/14/77
4/15/77
4/20/77
5/4/77
5/5/77
5/11/77
Average



Loading

36
37
38
43
57
58
64


12.8
0.4
1484
197
Period: April

16.0
16.0
15.0
18.0
18.0
17.0
18.0
16.9
1.2
High Loading Period:

6/1/77
6/3/77
6/9/77
6/16/77
6/17/77
Average


85
87
93
100
101



23.0
23.0
-
23.5
24.0
23.4
0.5
2, 3
1583
1540
1484
1495
1540
1469
1393
1500
60
(0.
(0
392)
.52)
11 -May
(6"
(0.
(0.
(0.
(0.
(0.
(0.
(0.
(0.
(0.
May 23-June
& 4 (6/16
2593
2593
2687
2687
2668
2646
49
&
(0.
(0.
(0.
(0.
180
35
13,
116
25
76
3
47.5
19
78.5
22
57
4
1977; Baffles after Shafts 1,
clearance)
418)
407)
392)
395)
407)
388)
368)
396)
016)
302
238
254
286
286
330
304
286
31
30, 1977;
6/17)
685)
685)
710)
710)
(0.705)
(0.699)
(0.013)

285
-
346
325
266
306
37
218
180
180
208
196
258
176
202
29
Baffles

120
-
181
184
162
162
29
96
117
133
133
148
210
122
137
36
after

90
-
116
124
156
122
27
73
105
90
109
115
142
106
106
21
Shafts

76
- •
136
130
150
123
32
85
72
78
101
-
126
68
88
22
1, 2,

-
-
170
128
129
142
24
74
73
60
88
91
106
66
80
16
3

52
-
110
97
97
89
25
                                                                continued.
                                     185

-------
TABLE A-6.  (continued)


Date


Day
V f f
Jc.II •
temp.
(C)

cu m
day


Flow
(mgd)

Chemical oxygen demand
(COD) (mg/1)
RBC
influent
T
S


1


2
Stages
(S)
3


4
Baffles after Shafts 2, 3 & 4 (6" clearance)
K/22,/777 Jn7 24'ฐ 2?44 (ฐ'725) 389 288 236 188 173 179
6/9A/77 nซ o.'n 263ฐ (ฐ'695) 31 7 187 i36 138 128 117
A/9Q/77 ^ 25'ฐ 2725 (ฐ'720) 275 155 1ฐฐ 120 101 89
7/T/77 ,,c ?5'ฐ 2?25 (ฐ-720) 352 221 188 140 144
7/1/77 115 25.5 2930 (0.770) 243 172 152 152 117 89
Average 24.6 2751 (0.727) 295 205 162 148 133 119
•67 110 (0.029) 42 53 52 25 28 42
Warm Temperature Period: July 18-September 23,1977; Baffles after Shafts
7/20/77
7/21/77
7/22/77
7/27/77
Average

8/4/77
8/5/77
8/10/77
8/11/77
8/12/77
8/17/77
8/18/77
8/19/77
134
135


149
150
155
156
157
162
163
164
28.0
28.0
28.0
•5
26.0
27.0
27.0
27.0
27.5
26.0
26.0
26.0
1,
1862
1836
1900
1873
1870
265
1533
1590
1457
1495
1457
1544
1495
1468
2, 3 & 4
(0.492)
(0.485)
(0.502)
(0.495)
(0.
(0.
(0.
(0.
(0.
(0.
(0.
(0.
(0.
(0.
494)
007)
405)
420)
385)
395)
385)
408)
395)
388)
(2" clearance)
285 170 112
373 221 224
357 245 188
269 176 176
321
52
268
267
288
293
344
411
352
386
203
35
175
152
195
219
224
221
240
163
159
41
168
164
188
192
252
208
212
212
194
178
174
33
136
132
142
184
216
160
152
190
164
140
142
18
127
126
103
128
157
128
137
152
89
112
116
116
108
13
81
78
88
85
108
143
136
continued.
        186

-------
                          TABLE  A-6.   (continued)
                                              Chemical oxygen demand
                                                  (COD)   (mg/1)
Date
Day
Eff.
temp,  cu m
(C)    day
8/24/77  169
8/25/77  170
8/26/77  171
8/31/77  176

Average
       26.0
       24.0
       25.0
       26.0

       26.2
        1.0
       1435
       1230
       1438
       1449

       1484
         49

Flow
(mgd)
(0.375)
(0.325)
(0.380)
(0.383)
(0.392)
(0.013)
RBC
Stages
influent
T
152
300
319
344
319
45
S
180
216
264
220
210
32
1
222
160
198
254
189
19
(S)
2
110
148
162
175
150
22
3
113
123
151
139
130
15
4
100
75
111
123
99
22
Cold Temperature Period:  December 1-February 24, 1978; Baffles after
                          Shafts 1, 2, 3 & 4 (2" clearance)
1/5/78
1/20/78  316
1/25/78  323
2/3/78   332
2/10/78  337
2/17/78  346
2/24/78  353

Average
       12.0   1476     (0.390)  336
              1563     (0.413)  109
              1324     (0.350)  343
       110    1476     (0.390)  376
       11.0   1797     (0.475)  301
       11.0   1457     (0.385)  360
       12.0   1514     (0.400)  424

       11.4   1514     (0.400)  321
          .6     144     (0.038)  101
203
59
209
157
152
208
259
195
52
167
120
164
188
240
188
38
125
98
152
126
168
117
32
93
81
103
99
111
80
28
87
72
72
96
113
                                178
                                 64
161
 60
128
 50
91
28
78
26
                                                                continued.
                                     187

-------
TABLE A-6.  (continued)
                    Biochemical oxygen demand
                       5-Day (BODr ) (mg/1)


Date Day
Eff .
temp.
(C)
Low Loading Period:
RBC
cu m
day
Flow influent
(mgd) T
March 9-April 6, 1977;
S
Baffles
1
after
— o — ฃ—* — : 	
Stages
(S)
2
Shafts
3 (6" clearance)
3/14/77 6
3/16/77 8
Average

12.5
13.0
12.8
0.4
1343
1620
1484
197
(0.355) 79
(0.428) 88
(0.392) 83.
(0.52) 6
Moderate Loading Period: April 11-May 13,

4/13/77 36
4/14/77 37
4/15/77 38
4/20/77 43
5/4/77 57
5/5/77 58
5/11/77 64
Average

High Loading

6/1/77 85
6/3/77 87
6/9/77 93
6/16/77 100
6/17/77 101
Average


16.0
16.0
15.0
18.0
18.0
17.0
18.0
16.9
1.2
Period :

23.0
23.0
-
23.5
24.0
23.4
0.5
2,
1583
1540
1484
1495
1540
1469
1393
1500
60
26
37
5 31.5
8
19
38
28.
13
1977; Baffles
16
20
5 18
3
3
1. 2,
y 7
24
19
21.5
4
after Shafts 1
3 (6" clearance)
(0.418) 159
(0.407) 159
(0.392) 117
(0.395) 191
(0.407) 162
(0.388) 221
(0.368) 150
(0.396) 166
(0.016) 33
May 23-June 30, 1977;
3 & 4
2593
2593
2687
2687
2668
2646
49
(6/16 & 6/17)
(0.685) 144
(0.685) 144
(0.710) 185
(0.710) 128
(0.705) 146
(0.699) 149
(0.013) 21
41
35
50
210
113
180
96
86
56
Baffles

63
80
86
78
105
82
15
40
22
50
70
76
108
55
60
28
after

51
70
130

115
85
29
21
26
28
48
59
53
40
39
15
Shafts

39
49
91
77
98
71
26
21
16
16
39

48
34
29
13
1, 2,

__
52
74
55
72
63
11
4


13
15
14
1
9

19
17
8
27
25
47
21
23
12


60
52
60
37
56
53
10
                                     continued.
         188

-------
TABLE A-6.  (continued)
                  Biochemical oxygen demand
                      5-Day (BOD ) (mg/1)
Eff.
temp, cu m
Date
Baffles
6/22/77
6/23/77
6/24/77
6/29/77
7/1/77
Average

Day
(C)
after Shafts 2,
106
107
108
113
115


Warm Temperature

7/20/77
7/21/77
7/22/77
7/27/77
Average

8/4/77
8/5/77
8/10/77
8/11/77
8/12/77
8/17/77
8/18/77
8/19/77

134
135
136
141


149
150
155
156
157
162
163
164
24.0
24.0
25.0
25.0
25.5
24.6
.67
Period

28.0
28.0
28.0
27.0
28.0
.5
26.0
27.0
27.0
27.0
27.5
26.0
26.0
26.0
day
3 & 4
2744
2630
2725
2725
2930
2751
110
: July
1, 2
1862
1836
1900
1873
1870
265
1533
1590
1457
1495
1457
1544
1495
1468
RBC J
Flow influent
(mgd) T
(6" clearance)
(0.725) 153
(0.695) 128
(0.720) 146
(0.720) 152
(0.770) 123
(0.727) 140
(0.029) 14
18-September
S

69
57
72
84
99
76
16
23,1977;
1

84
57
58
79
82
72
13
2

84
64
63
94
76
76
13
Baffles
Stages
(S)
3

50
45
47
70
76
58
14
after

4

45
25
23
-
43
34
12
Shafts
, 3 & 4 (2" clearance)
(0.492) 122
(0.485) 156
(0.502) 144
(0.495) 105
(0.494) 132
(0.007) 23
(0.405) 146
(0.420) 138
(0.385) 126
(0.395) 122
(0.385) 129
(0.408) 112
(0.395) 146
(0.388) 141
68
114
103
73
90
22
109
94
63
116
115
74
115
90
45
73
66
41
56
16
69
59
54
81
85
67
84
72
42
83
79
67
68
18
57
41
61
50
69
49
70
43
34
63
49
41
47
12
29
27
40
38
39
36
47
42
26
36
33
25
30
5
23
17
36
41
34
21
-
32
continued.
          189

-------
TABLE A-6.  (continued)
                   Biochemical oxygen demand

Date
8/24/77
8/25/77
8/26/77
8/31/77
Average


Day
169
170
171
176


Cold Temperature

1/5/78
1/20/78
1/25/78
2/3/78
2/10/78
2/17/78
2/24/78
Average



316
323
332
337
346
353


Eff .
temp.
(C)
26.0
24.0
25.0
26.0
26.2
1.0
Period

12.0
-
-
110
11.0
11.0
12.0
11.4
.6
cu m
day
1435
1230
1438
1449
1484
49
Flow
(mgd)
(0
(0
(0
(0
(0
(0
.375)
.325)
.380)
.383)
.392)
.013)
RBC
influent
T
120
110
170
135
133
17
: December 1 -February
Shafts
1476
1563
1324
1476
1797
1457
1514
1514
144
(0
(0
(0
(0
(0
(0
(0
(0
(0
1, 2,
.390)
.413)
.350)
.390)
.475)
.385)
.400)
.400)
.038)
3 & 4
174
98
185
174
162
203
218
173
38
S
72
88
145
122
100
24
24,
(2"
119
59
108
104
84
87
99
94
20
Stages
(S)
1
39
58
91
107
72
19
1978;
2
28
44
66
87
56
16
Baffles
3
17
35
42
55
37
13
after
4
ซ
O
29
24
42
28
10

clearance)
85
29
23
33
64
53
35
46
22
126
26
50
26
67
69
43
58
35
37
16
26
18
38
26
23
26
9
24
13
20
22
25
18
27
21
5
                                     continued.
         190

-------
                          TABLE A-6.   (continued)
                           Total suspended solids
                                (TSS)  (mg/1)
Date       Day    RBC influent     1

Low Loading Period:  March 9-April 6, 1977; Baffles after
                     Shafts 1, 2, 3 (6" clearance)
2/14/77      6         161        244    279    626    234
3/16/77      8         128        340    212    180    202

Average                145        292    246    403    218
                        23         68     47    315     23

Moderate Loading Period:  April  11-May 13, 1977; Baffles
                          after  Shafts 1, 2, 3  (6" clearance)
4/13/77     36         108        104     76    114    120
4/14/77     37         100         82     95    338    280
4/15/77     38         110         60    106      75    207
4/20/77     43         125        162    124      60    160
5/4/77      57         113        109
5/5/77      58         106        118    176     142    356
5/11/77     64         143          95    172     194    220

Average                 115        104    125     117    224
                         15          32      41      54      85

High Loading  Period:   May 23-June 30,  1977;  Baffles  after
                       Shafts 1,  2,  3 & 4  (6/16 & 6/17)
 6/1/77       85          143         134     170      -     568
 6/3/77       87          113          80     376    123     382
 6/9/77       93          175           -
 6/16/77     100          105        127     237     88     147
 6/17/77     101          107        155    300    126     128

 Average                129        124    293    112     306
                         30         32     88     21     209

                                             continued.
                                     191

-------
                           TABLE  A-6.   (continued)
                           Total  suspended  solids
                                 (TSS)   (rng/1)
Date
Baffles
6/22/77
6/23/77
6/24/77
6/29/77
7/1/77
Average

Day RBC
after Shafts 2
106
107
108
113
115


influent
, 3 & 4 (6"
136
137
138
_
95
127
21
1
2
3
4
clearance)
130
114
104
_
102
113
12
373
161
174
_
151
215
106
30
104
132
_M
77
86
43
183
97
97

83
115
46
Warm Temperature Period:  July 18-September 23,  1977; Baffles
                          after Shafts 1, 2, 3 & 4  (2"  clearance)
7/20/77    134        139         104    312     76      64
7/21/77    135        138         112    334     132     133
7/22/77    136          -         112    504     89     154
7/27/77    141        108          94    243-     91     163
Average

8/4/77
8/5/77
8/10/77
8/11/77
8/12/77
8/17/77
8/18/77
8/19/77
8/24/77
8/25/77


149
150
155
156
157
162
163
164
169
170
128
18
110
105
99
100
79
179
157
133
—
167
106
9
93
99
_
191
237
120
149
192
135
94
348
111
170
205
__
538
553
164
140
383
165
136
97
24
74
70

83
49
94
114
262
104
81
129
45
110
117

79
327
106

356
151
90
                                             continued.
                                   192

-------
                          TABLE A-6.   (continued)
                           Total suspended solids
                                (TSS)  (mg/1)
Date       Day    RBC influent     1      2      3
8/26/77    171        121         100    192    280    111
8/31/77    176        141         148    168    137    116

Average               126         142    256    123    156
                       32          48    158     77    100

Cold Temperature Period:  December 1-February 24,  1978; Baffles
                          after Shafts 1, 2, 3 & 4  (2" clearance)
1/5/78                162         179    189    189    169
1/20/78    316        120         134    128    138    167
1/25/78    232        132         253    521    296    151
2/3/78     332        157         163    328    257    112
2/10/78    337        123         218    181    120    117
2/17/78    346        155         239    265    138    140
2/24/78    353        128         141    249     54     64

Average               141         190    266    169    131
                        17          48    130     82     37

                                             continued.
                                    193

-------
                          TABLE A-6.  (continued)
Date
Day    RBC influent
                           Dissolved oxygen  (mg/1)
Low Loading Period
2/14/77
3/16/77

Average
          March 9-April 6, 1977; Baffles after
          Shafts 1, 2, 3 (6" clearance)
           8.5         4.6    4.6    4.4    4.2
           8.4         4.4    4.1    3.9    3.7
           8.45
           0.07
            4.5
              .14
4.35
 .35
4.15
 .35
                                                       3.95
                                                        .35
Moderate Loading Period:
               April 11-May 13, 1977; Baffles after
               Shafts 1, 2, 3
4/13/77
4/14/77
4/15/77
4/20/77
5/4/77
5/5/77
5/11/77
Average

36
37
38
43
57
58
64


4.8
5.3
5.0
4.6
5.1
7.5
5.2
5.4
1.0
* f
2.8
2.6
3.0
3.0
3.3
3.9
3.6
3.2
0.5
2.6
2.5
2.9
2.0
2.1
2.7
2.8
2.5
0.3
2.6
2.9
3.1
1.7
1.5
2.1
2.4
2.3
0.6
— - f
2.0
2.0
2.2
1.2
1.0
1.5
2.2
1.7
0.5
High Loading Period:
6/1/77
6/3/77
6/9/77
6/16/77
6/17/77

Average
 85
 87
 93
100
101
May 23-June 30, 1977; Baffles after
Shafts 1, 2, 3 & 4 (6/16 & 6/17)
2.2         1.4    1.0    0.8    .0.8
1.6         1.4    1.0    1.0    0.8
1.0
2.0
1.7
0.5
1.0
2.0
1.5
0.4
0.8
1.6
1.1
0.3
0.6
1.0
0.9
0.2
0.4
0.4
0.6
0.2
                                                      continued
                                   194

-------
                          TABLE  A-6.   (continued)
                          Dissolved oxygen (mg/1)
Date
Day RBC influent 1
Baffles after Shafts 2, 3 & A
6/22/77
6/23/77
6/24/77
6/29/77
7/1/77
Average

106
107
108
113
115


2.2
1.8
1.8
3.4
0.8
2.0
0.9
2
3
4
(6" clearance)
1.4
1.4
1.2
1.6
0.8
1.3
0.3
1.4
1.2
1.0
1.4
0.8
1.2
0.3
1.2
1.0
0.8
1.0
0.6
0.9
0.2
0.4
1.0
0.4
0.4
0.4
0.5
0.3
Warm Temperature Period:
July 18-September 23, 1977; Baffles
after Shafts 1, 2, 3 & 4 (2" clearance)
7/20/77
7/21/77
7/22/77
7/27/77
Average

8/4/77
8/5/77
8/10/77
8/11/77
8/12/77
8/17/77
8/18/77
8/19/77
8/24/77
8/25/77
134
135
136
141


149
150
155
156
157
162
163
164
169
170
3.2
0.4
0.6
0.2
1.1
1.4
0.4
0.4
1.0
1.2
1.0
1.0
0.8
1.1
1.8
3.4
0.8
0.2
0.4
0.3
.43
.26
0.4
0.4
0.6
0.6
0.6
0.7
0.8
0.7
0.8
1.2
0.8
0.2
0.4
0.4
.45
.25
0.3
0.4
0.6
0.6
0.6
0.4
0.5
0.7
0.2
1.2
0.6
0.2
0.4
0.2
.35
.19
0.3
0.4
0.6
0.4
0.6
0.3
0.2
0.4
0.2
1.2
0.4
0.1
0.2
0.4
.28
.15
0.4
0.6
0.8
0.6
0.8
0.3
0.2
0.4
0.3
1.4
                                                       continued,
                                      195

-------
                          TABLE A-6.  (continued)
Date
8/26/77
8/31/77
Average

Day
171
176


RBC influent
4.2
1.5
1.2
1
2.0
0.8
0.5
2
1.6
0.6
0.4
3
1.4
0.5
0.4
4
1.8
0.7
0.5
 Cold Temperature Period:  December 1-February 24,  1978; Baffles
 ,/c/^o                    after Shafts 1,  2,  3 & 4  (2" clearance)
 !/2$8     316        3:8         3"!    2:8    2-8    2-8
 1/25/78     232         -            _
 2/3/78      332        7.5         5 1    3 6    1  ft    1 A
 2/10/78     337        6.3         5 Q    35    2*8    2*4
 2/1J/78     346        5.6         sM    43.'o    \\\     !
 2/24/78     353        6.2         5.0    4.4    3.8    3.7

 Avera8e               5.9         4.8 ^   3.7    3.2    3.3
	     !•*         0.8    0.6    0.5    0.6
                                  196

-------
                              APPENDIX B

                    RBC STEADY STATE KINETIC  MODEL


     The model used in this study is applicable to the removal of  solu-
ble carbonaceous BOD in multi-stage RBC systems.  Material balances are
solved to determine substrate and oxygen levels in the effluent from
each stage and in the attached biofilm.  Mass transfer resistances, de
terained as a function of system operating conditions, are considered
in both the liquid phase and biofilm, and the reaction rate is related
to substrate and oxygen concentrations through the kinetic equations.

     As shown on Figure B-l, the model assumes the media to consist of
flat discs divided into stationary  pie-shaped sectors.  Each sector
effectively acts as a  flow-through  mixed reactor, with advective
transport of biomass and water across  sector boundaries.  Additionally,
the model assumes  that  the liquid  film remains  static relative to  the
media  as  it moves  through  the air,  and as it enters the tank the liquid
film  is  stripped off and mixes completely with  the wastewater.  Oxygen
transfer  at the wastewater surface  in the tank  is considered negligible
compared  to the aeration which occurs on  the disc surface.

      Due  to the significant  concentration gradients which can  exist
normal to the  disc surface,  the  biofilm  is divided  into layers, as
shown on Figure B-2,  for  sectors above the water line.  Biomass is con
veyed through  the  stationary sectors at  the  volumetric  rates  QF,
while the liquid  film is  transported at  the  rate QLป

      Coupled  Michaelis kinetics  are used to  simultaneously  compute oxy-
 gen and substrate  profiles through the fixed-film treatment process.
 The rate equations,  which assume the reactions to occur exclusively in
 the biofilm layers,  are as follows:
           Rs = k   S
                  S + Sm       C +
           R0 =  [a'k   S     +  b'Xv]   C
                     S + S            C +
                                   197

-------
   LIQUID FILM
   COATS DISC
EFFLUENT
                                                      INFLUENT
                                       ' - V  •   1.. .ซ.
        Figure B-l.  Sketch of  sectors in the RBC model
                             198

-------
UJ

-------
o:
o
i-
o
LJ
CO
    X
MEDIA

/
                           -dy
NSA
LIQUID

 FILM
                           UJ
                           or
                           UJ
                           o
                                                                   o:
                                                                   3
                                                                   (O
                 Figure B-3.  Mass flux through

                 infinitesimal slice of biofilm
                                200

-------
where Rs and RQ are the rates of substrate removal (mg/l/min
BOD) and oxygen consumption (mg/l/min 02), respectively, and

     S      =  substrate concentration (mg/1 BOD)
     C      =  oxygen concentration (mg/1 Gฃ)
     Sm     =  substrate Michaelic constant (mg/1 BOD)
     Cm     =  oxygen Michaelic constant (mg/1 Gฃ)
     k      =  maximum rate of substrate removal (mg/l/min BOD)
     a'     =  oxygen utilization coefficient (mg 02/mg BOD)
     b'     =  endogenous reaction rate (mg 02/mg VS/min)
     Xv     =  biofilm volatile solids concentration (mg/1 VS)

The maximum rate of substrate removal, k, is the combined term,
UXV/Y, where y is  the maximum specific growth rate, Xy is the
biomass  solids concentration, and Y is the organism yield coefficient.
Because  each of these  is assumed constant in the model, a single rate
constant (k) can be employed.

      Further model simplification can be  accomplished by using either
zero  order or  first order kinetics with respect  to substrate.  Previous
work(l)  indicated  that either one effectively predicted  substrate
removal  through the system.   For  this particular model  application,
first order substrate  removal kinetics were  induced by  setting a high
Michaelis half  rate constant of  10,000 mg/1.  Thus the  term,
                             c 4. q
                             b f Sm

 may be written (since ^ ปS):

                               kS


 The first order rate constant, k', reported herein can be defined as:

                                     k
                               k' = Sm = min-1

 where k is the maximum rate of substrate removal used in the RBC model

      Substrate and oxygen concentrations are obtained by material bal-
 ances on the biofilm layers,  the liquid film, and the mixed liquor in
 the tank.  Mass transfer through the biofilm is assumed to follow
 Pick's Law.

                               Ns = -Ds dฃ
                                        dy

                               NO = -Do dฃ
                                        dy
                                    201

-------
where Ds and Do are  the diffusivities of substrate and oxygen,
respectively.

     For the aerated  sectors  (see Figure B-2) a film of liquid is pre-
sent between the atmosphere and biofilm.  Transport through the liquid
film-biofilm interface is described by the equations:

                         NS = Ks (SL - Si)
                         NO = KO (CL - Ci)

where Ks and Ko are  the substrate and oxygen mass transfer co-
efficients, respectively.  SL and CL are the average concentra-
tions in the liquid  film and  Si and GI represent concentrations
at  the  interface.  At the liquid film-atmosphere interface, the trans-
port rate of oxygen  in the liquid is proportional to the difference be-
tween the saturation  oxygen concentration, Cs , and CL:

                         No = KL (cs - CL)

Since the liquid film is assumed stagnant in the model, the mass trans-
fer coefficients at both the biofilm-liquid and liquid-atmosphere in-
terface are equal and designated as KL.

     In the tank, the wastewater is assumed to be completely mixed at
concentration levels  S and C.  A mass transfer resistance exists at the
biofilm interface, allowing the following substrate and oxygen flux
equations:

                         Ns = K's (S - Si)

                         No = K'L (c -
     The RBC model assumes that concentration profiles across the liq-
uid film are approximately linear, with average concentrations of both
substrate and oxygen occurring at the film center.  From this, it fol-
lows that mass transfer coefficients are equivalent to the diffusivity
divided by one half the liquid film thickness.

     Liquid film thickness is computed from operating conditions based
on the theory of plate withdrawal from liquids,

                         h0 = 6.85v2/3

where v is the withdrawal velocity.  An average withdrawal velocity at
the centroid of mass (two-thirds media radius) was employed.  To ac-
count for surface irregularities of the biofilm, a thickness of 25 was
added to the ho computed above.  Thus the actual liquid film thick-
ness is:

                        & = h0 + 25
                                  202

-------
     The mass transfer coefficients are related to 6 L'

                              Kc =
Ds and D0 are the diffusivities of substrate and oxygen in
water, respectively, while 6L/2 represents the diffusion path
length from average concentration to the interface concentration.

     Figure B-3 graphically presents a material balance for substrate
in the biofilm, for which the equation is:

                  2            ^_
                 6  s           OF
          Ds    y2  + (SQ - S) A - Rs = 6 S
                                        6 t

The first term represents the concentration gradient associated with
diffusion through the biomass normal to the media.  Advective transport
through  the stationary sector is described by the second term, and the
third term is the reaction sink.

     At  the liquid-biofilm interface a convective boundary condition is
employed where the mass transfer  in the biomass is set equal to  the
flux  through the adjacent liquid  film.
           -Ds    5Y= Ks  (SL  -  S), where  y = 0

 Similar  equations exist  for  oxygen.   Additional mass balance equations
 are provided  for  the mixed liquor and the liquid  film  carried with  the
 media above  the water  line.   These  equations,  however,  do  not consider
 reaction sinks.

      Solution of  the model equations to  obtain the  desired substrate
 and oxygen concentrations is provided by an efficient  finite-difference
 procedure, and is applicable to both dynamic  and  steady-state simula-
 tions.
                                   203

-------
                                   TECHNICAL REPORT DATA
                            (Please read Instructions on the reverse before completing)
1. REPORT NO.
   EPA-600/2-80-003
                             2.
                                                           3. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
               UPGRADING PRIMARY TANKS WITH
               ROTATING BIOLOGICAL CONTACTORS
                                                           5. REPORT DATE
                                                             March 1980  (Issuing. Date)
               6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
               Alonso Gutierrez, Ivan L. Bogert,
         O.Karl Scheible and Thomas J. Mulligan
                                                           8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
         Clinton Bogert Assoc.
         2125 Center Avenue
         Fort Lee,  N.J.  07024
          Inc
Hydroscience Ass
363 Old Hook Road
Westwood, N.J.  07675
10. PROGRAM ELEMENT NO.

  1RfR77. SOS #3. PI/32
               11. CONTRA'dT/GRANT NO.

                  R-804854
12. SPONSORING AGENCY NAME AND ADDRESS
   Municipal  Environmental Research Laboratory—Gin. ,OH
   Office  of  Research and Development
   U.S.  Environmental Protection Agency
   Cincinnati,  Ohio  45268
               13. TYPE OF REPORT AND PERIOD COVERED
               Final,  September 1976-Aug. 197S
               14. SPONSORING AGENCY CODE
               EPA/600/14
15. SUPPLEMENTARY NOTES
   Project  Officer:   Edward J. Opatken   (513)  684-7643
16. ABSTRACT
       A  one-year experimental program was  conducted at Edgewater, New Jersey,  to
  evaluate  the concept of upgrading existing primary wastewater treatment plants to
  secondary treatment by the installation of rotating biological contactors  (RBC's)  in
  the primary sedimentation tanks.

       The  basic concept was to horizontally divide  a primary sedimentation  tank into
  two zones by installing an intermediate floor  at mid-depth.  Four RBS's were  placed
  in the  upper zone above the intermediate  floor.  This zone provided separate
  biological  contact and treatment of the incoming wastes,  while the lower zone
  functioned  as a secondary sedimentation zone.  Such a configuration would  minimize
  the need  for additional tankage and clarifiers, and would be especially suited to
  plants  with limited space.

       The  experimental program was conducted  in three phases over a full year.  Three
  loadings  were studied during the initial  phase to  determine the optimum system load
  that conformed with EPA standards.  This  loading was then evaluated under  summer and
  winter  conditions.   Little difference in  treatment efficiency was noted between
  summer  and  winter conditions, due primarily  to the interactions of oxygen  availability
  mass transfer,  and kinetic removal rates, and  the  impact  of temperature on each.
17.
                               KEY WORDS AND DOCUMENT ANALYSIS
                  DESCRIPTORS
                                              b.lDENTIFIERS/OPEN ENDED TERMS
                             c. COS AT I Field/Group
  Waste treatment
  Biochemical oxygen  demand
  Benefit cost  analysis
  Beggiatoa
  Chemical removal
  Clarifiers
  Oxygen transport mechanisms
  Mathematical  models	
   Edgewater (New Jersey)
   Rotating biological
    contactors
   Ferric chloride
                                        6F $ 13B
18. DISTRIBUTION STATEMENT

  Release to Public
  19. SECURITY CLASS (This Report)
    Unclassified
                                      21. NO. OF PAGES
                                          216
                                              20. SECURITY CLASS (This page)
                                                                        22. PRICE
                                                Unclassified
EPA Form 2220-1 (Rev. 4-77)
204

-------