-------
1988 Abatement Area \
i
The average airborne asbestos concentration measured in 1988 (0.016 s/cm3)
was significantly greater than the average concentration measured in 1990 (0 s/cm3).
Differences between average levels measured in 1990,1991, and 1992 were not
statistically significant. Similarly, differences; between average levels measured in
1988,1991, and 1992 were not statistically Significant. The highest average
concentration (0.016 s/cm3) and the highest Individual concentration (0.045 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
i
Perimeter
The average airborne asbestos concentration measured during the AHERA
clearance phase of the 1988 abatement (0.062 s/cm3) was significantly greater than
the average levels measured in 1990 (0 s/cm3), 1991 (0.005 s/cm3), and 1992 (0.025
s/cm3). Differences between average levels;measured in 1990, 1991, and 1992 were
not statistically significant. The highest average (0.062 s/cm3) and highest individual
(0.206 s/cm3) concentrations were measured during the AHERA clearance phase of
the 1988 abatement. ;
Outdoors i
i
i
The average airborne asbestos concentrations measured outdoors in 1988,
1990,1991, and 1992 were not significantly idifferent. The highest average
concentration (0.003 s/cm3) and the highest individual concentration (0.012 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
Structure Morphology and Size Distributions
Table B-49 presents the distribution of structure type and morphology at each
sampling location separately for each year o!f monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 181 asbestos structures, all of which were
chrysotile asbestos. Overall, the asbestos structures were primarily fibers (70.2
percent), and to a lesser extent, matrices (22.1 percent), bundles (6.1 percent), and
clusters (1.7 percent). j
Table B-50 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 97.2 percent
of the observed asbestos structures were less than 5 \im in length. Of the 127
asbestos fibers observed, none were greater than 5 |im in length.
159
-------
CO
t-
o
2
g
GL
DC
O
o
z
IU
Q.
Ill
DC
O
DC
b
s
co
Ul
CO
CO
u.
o
o
m
DC
s
Q
0>
ffi
^^S
i^f-i
Jv»-;
in
CM
Si
CO
CO
co
'
o
CO
10
0
«c-
m
,fT
£
cv
Tr •, T*
R
to
o
o
o
o
CM
O*
s
co
CO
co
co
CO
co
co
co
co
co
co
CD
I
03
•o
1
8
I
CO
co
co
CO
160
-------
CO
W
DC
1
UJ
cc
I
CC
I
CO
Ul
m
a.
O
O
P
ffl
E
Z)
O
CQ
UJ
CD
,o
K*
VI
£
s
£
tl
-*«,:
^n^Ns
Ivl
a
S
U)
00
en
CO
•CO
CO
CO
g
s
0
o
g
o
0
o
o
in
CM
WE
o?
o
o
I
o
1
cc
co
I
I
CO
0)
1
00
03
.c
fe
T3
S
.2
8
£
i
to
ca
W
-------
FoIIowup Air Monitoring - August 1991
.*t
The average airborne asbestos concentrations in the previously abated area
and the perimeter area in May 1991 exceeded 0.02 s/cm3. Therefore, EPA/NJDOH
conducted followup monitoring under simulated occupancy conditions on August 15,
1991, The average airborne asbestos concentration in the previously abated area
(0.035 s/cm3) exceeded 0.02 s/cm3; therefore, NJDOH directed the school to initiate a
response action to reduce the airborne asbestos concentrations in this area. The
school subsequently employed an asbestos abatement contractor to clean the
previously abated and perimeter areas. When the cleaning action was complete,
EPA/NJDOH conducted followup air monitoring on August 29,1991, to determine the
residual levels of airborne asbestos. The average airborne asbestos concentrations in
the previously abated area and in the perimeter area were below 0.02 s/cm3;
therefore, no further monitoring activity was required at this school. Intervention
continued, however, to resolve the elevated asbestos concentrations at this site.
Followup Air Monitoring • August 1992
Because the average airborne asbestos concentration in the perimeter area
(0.025 s/cm3) in May 1992 exceeded 0.02 s/cm3, NJDOH-EHS required a response
action at this school. The school subsequently used in-house staff to clean the
previously abated and perimeter areas. When the cleaning action was complete,
EPA/NJDOH conducted followup air monitoring in August 1992 to determine the
residual levels of airborne asbestos. The average airborne asbestos concentration in
the previously abated area (0.02 s/cm3) and perimeter area (0.015 s/cm3) did not
exceed 0.02 s/cm3; therefore, no further monitoring activity was required at this school.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site H as part of the State's traditional quality assurance program which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Two visual inspections were required at this site. The site failed the first visual
inspection because of the presence of debris on heating units, on pipes in the
hallways and classrooms, on electrical wires and outlet boxes, at floor-wall corners,
and around air vents. The contractor was required to reclean these areas. After the
areas were recleaned, NJDOH conducted a second visual inspection, which the site
passed.
162
-------
1991 Inspection
On August 16,1991, NJDOH conducted a visual inspection at Site H to
determine potential sources of airborne asbestos measured by EPA/NJDOH in April
1991. The visual inspection strategy considered the asbestos-abatement history of
the site, the O&M activities, and other sources of possible asbestos contamination
(i.e., materials not included in the Asbestos Management Plan). Only those areas of
the 1988 abatement indicated in the following subsections were examined.
1988 Abatement Areas
Corridor by the Shop ,-4reas~Spray-applied ceiling debris collected from the top
surface of the ceiling access panels contained 7 percent chrysotile asbestos (Table
B-51). As indicated in the table, an accumulation of dust found on the baseboard
heating pipes tested positive for asbestos, and the TSI on pipes above the ceiling did
not contain asbestos. i
Corridor to the Gymnasium-The TSI on pipes above the ceiling did not contain
asbestos (Table B-51). j
i
i
Mechanical Arts Shops-Metal partition walls along the windows contained
ceiling debris (8 percent chrysotile) and dust'that tested positive for asbestos (Table
B-51). Radiators were also found to contain !debris and dust that tested positive for
chrysotile asbestos. '
1988 Perimeter Areas ;
Hallway by the Custodian's Locker Room-Dud insulation above the ceiling in
the hallway outside the men's custodian locker room was friable and contained
1 percent chrysotile and 6 percent amosite asbestos (Table B-51). The duct insulation
was not included in the Asbestos Management Plan.
Auditorium-^ fireproofing type of material adhered to several areas of the stage
wall. Two samples of this material contained 27 and 35 percent chrysotile asbestos
(Table B-51). , ;
i
Conclusions ' • '.
I
The asbestos-containing debris and dust on ceiling panels and behind partition
walls were a potential source of airborne asbestos fibers measured in May 1991. This
debris was from improper O&M activities or fj-om uninventoried or residual ACM from
the 1988 abatement. No asbestos-containing duct insulation was identified in the
Asbestos Management Plan. The Asbestos Management Plan also erroneously
identified the TSI on pipes above the corridor ceilings as asbestos-containing material.
i
163
-------
Because the Asbestos Management Plan was in error, the potential exists for the
disturbance of unidentified ACM.
164
-------
TABLE B-51. SUMMARY OF BULK SAMPLE RESULTS-SITE H
1991 INSPECTION
1988 Abatement Area
Drafting storage
Halt at shops
Hall at shops
Hall at shops
Hall to gymnasium
Half to gymnasium
Hall at shops
Hall intersection (shop-cafe),
access panel
End shop, partition wall
Drafting shop, partition wall
Drafting shop
1988 Perimeter Area
Hall at Custodian's office
Auditorium stage, wall at
electrical panel
Auditorium stage, by duct
Block pipe insulation debris
i
Above suspended ceiling, 4-in. block
pipe insulation |
i
Above suspended ceiling, elbow debris
with dark spots ;
Above suspended ceiling, 7-in. block
pipe insulation with straw
Above suspended ceiling, elbow with
dark spots
Above suspended ceiling, block pipe
insulation with straw
Radiator dust
Residual ceiling materia
Dust and debris
Ceiling debris
Radiator dust
Duct insulation
Debris
Debris
Negative
Negative
Negative
Negative
Negative
Negative
Positive8, chrysotile asbestos
7% chrysotile asbestos
Positive, chrysotile asbestos
8% chrysotile asbestos
Positive, chrysotile asbestos
1% chrysotile asbestos
6% amosite asbestos
35% chrysotile asbestos
27% chrysotile asbestos
This classification was defined by the NJDOH laboratory
material was available to allow a full quantitative evaluation,
asbestos was present and to determine the specific type
the analyst, the sample is considered to contain greater than
to accommodate samples for which inadequate
i, but were of sufficient size to determine that
of asbestos. Based on the professional judgment of
1 percent asbestos.
165
-------
SITE I
Background
Site Description
The abatement project at this single-story school building involved the removal
of approximately 5100 ft2 of spray-applied, asbestos-containing, acoustical ceiling
plaster. The abatement area included an office, a lobby, and an auditorium. The
project specifications indicated that the asbestos content of the ceiling plaster was
approximately 5 to 25 percent chrysotile. The information regarding the abated ACM
and associated asbestos content was obtained from the asbestos abatement
specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST. In 1990, air samples
were collected at this school by use of a modified aggressive sampling technique to
simulate occupied conditions. The samples were collected at approximately the same
locations as those collected in 1988. In 1991 and 1992, air samples were collected at
this school during occupied conditions (i.e., during normal school operating hours) at
approximately the same locations as those collected in 1988 and 1990.
Summary of Air Monitoring Results
Table B-52 summarizes the results from the four sampling efforts. Figure B-9
shows the mean airborne asbestos concentrations at Site I. A single-factor ANOVA
was used to compare mean concentrations measured in each of the three sampling
locations. Table B-53 presents the results of the ANOVA analysis. The following
subsections summarize the pairwise comparisons of the mean concentrations in the
three sampling locations.
166
-------
TABLE B-52. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3)MEASURED AT SITE la
MJtt
Win
Mean
Mlrt
Max
0.005
0.020
0.001
o.oosi
0.011
0.056
0.001
0.005
0.003
0.007|
0.005
0.011
0.005
0.020
0.001
0.002 i 0.001
0.003 0.002
0.009
Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-53. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE I
Saiaj&tig peHmi: s s
Statistically signiricanr ddffofen^es
mean
0.0389
0.7400
0.6961
0.4809
0(0.005)
P(0.011) AfO.OOD 0(0.001)
PfO.OOS) 0(0.005) AfO.003)
O(0.002) AfO.OOD P(0.001 )
' If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
[
b A » 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location. '
d Sampling locations (means) connected by a line ar|e not significantly different.
167
-------
q
o
o
o
o
o
o
6
rt
0)
q
d
o
o
o
o
q
6
EWO/S 'UOI1BJJU80UOQ S01S9QSV eUJOQJIV
168
O)
0)
0)
at
o
0)
en
oo
00
0)
0>
*j
CO
•D
0)
3
CO
03
O
E
0)
o
c
o
o
(A
O
W
cd
0)
c
Q
o
o
9
CO
0
3
D)
LL
-------
Summary of Air Monitoring Results
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have passed the
AHERA initial screening test because the average filter concentration (0 s/mm2) was
below 70 s/mm2. Furthermore, the site would have passed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. These results are
consistent with AST sampling results.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.005 s/cm3). I
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.005 s/cm3). :
i
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0 s/cm3) was not
significantly different from the average concentration measured in the perimeter areas
(0 s/cm3).
Simulated Occupancy -1990 \
i
Comparison of the Previously Abated Area With Outdoors
i
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (O.Q01 s/cm3).
169
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.011 s/cm3) was not significantly different from the average outdoor
concentration (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.011 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured outdoors (0.005 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured outdoors (0.005 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.005 s/cm3).
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.002 s/cm3).
170
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.001 s/cnf?) was not significantly different from the
average concentration measured outdoors (0.002 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to cbmpare mean concentrations measured in
1988,1990,1991, and 1992. Each sampling location was evaluated separately.
Table B-54 presents the result of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
TABLE B-54. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE I
Statistically significant differences in mean airborne
' " ' '*
„.„,...„.„•> ' A,
area ,
Perimeter area M "
0.1141
0.2019
0.6690
1991(0.003) 1992(0.001) 1990(0.001) 1988(0)
1990(0.011) 1991(0.005) 1992(0.001) 1988(0)
1988(0.005) 1991(0.005) 1992(0.002) 1990(0.001)
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
171
-------
1988 Abatement Area
Differences between average levels measured in 1988,1990, 1991, and 1992
were not statistically significant. The highest average concentration (0.003 s/cm3) and
the highest individual concentration (0.007 s/cm3) were measured during occupied
conditions in 1991, 3 years after the 1988 abatement.
Perimeter
Differences between average levels measured in 1988, 1990, 1991, and 1992
were not statistically significant. The highest average (0.011 s/cm3) and highest
individual (0.056 s/cm3) concentrations were measured during simulated occupancy, 2
years after the 1988 abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1988,
1990, 1991, and 1992 were not significantly different. The highest average
concentration (0.005 s/cm3) and the highest individual concentration (0.020 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement and during
occupied conditions in 1991, 3 years after the 1988 abatement.
Structure Morphology and Size Distributions
Table B-55 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 43 asbestos structures, all of which were
chrysotile asbestos. Overall, the asbestos structures were primarily fibers
(88.4 percent), and to a lesser extent, matrices (11.6 percent). Table B-56 presents
the cumulative size distribution of asbestos samples at each sampling location
separately for each year of monitoring. All of the observed asbestos structures were
less than 5 jim in length.
NJDOH Visual Inspection
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site I as part of the State's traditional quality assurance program which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected AHERA clearance
air samples only after the site had passed the NJDOH visual inspection.
172
-------
CO
3
o
D.
CC
i
Q
Ul
DC
QC
CO
1U
m
CO
<
u.
O
z
o
I-
m
oc
m
ui
m
o
f
g
53
o
E
i£
ss^O
fZ -^*K.
0
o
LO
CM
CD
in
0
o
0
o
o
o
o
CO
s
o
LO
o
o
0
8
to
:f
^' -"' ^'Vr'' " '
-'- -.^r-'l' '"• /
s
§
•o
T3
(0
S
(0
8
£
i
ca
CO
173
-------
B
ff\
5
O
LU
EC
Z)
0)
<
LU
S
LU
DC
|
I
S
LU
.
LL
o
2*
g
H~~
m
E
**%
Cw
Q
LU
N
(0
LU
>
H
3
CO
LU
m
<
H
L,,>
: v ••
V,
•;§
§
• •"IS*
•*2
|
'$
15
f
{**
*.
'f*i
3
I
^
'
r
>•. •"
S
S*
3£
._
„
^-,-
' ww
^ ,v
— '
f Sff
" O
^5*
*M«
'4
iJK
~ ««,
^
r?
••*•'•"•
fSSSSf f
g
-St.
*?.
-
3,
Vf
•••'•'&
1
'^
\ '
^
'«»
" 3
5 'S
$i
^,
1
Is
td
cfe
§
a,
5
1
1
1
1
1
,
O
1
s ;
~,,
,»>-
•• ••
,,V.v.
S
^ ••••••
O
O
'
s
*~
0
o
o
o
1—
o
o
o
o
^~"
*"
i
^
' -fl
1
'• •• (I
^ 1
c
1
1
•C
<(
o
0
0
o
*~
o
o
o
0
o
o
1—
o
0
^w
^
i
••
^
s-""
*
1
1 '
I w
i "-
I
t
o
0
o
o
"*"
o
0
o
0
^—
o
o
o
^~
il
' -i
11 ^ :
v.:
' i
,' 1
X. ^.|
" =
,
1
,
,
1
0
CO
'
-
, ',
§
o
0
1
o
o
§
in
in
£
o
o>
i
J
fl
»
%»
<
K
0
o
§
1
o
o
0
o
O)
^f
h*
il
1
r
|
i.
*•
*
}
»
0
O
8
0
o
T1™
o
o
0
o
T—
•w-i
0
o
8
o
o
o
o
T
in
00
j^j
in
•^
§
"•
•.•^
••
•••f
s
'
'
o
o
0
o
o
o
o
o
^
1
,v ,
••^
ff
'• :t
'' 1
•
O
o
T™
0
o
o
o
o
0
o
o
CO
CO
CO
si
~
k
h
r
t
s
>;>-.
o
0
^~
0
o
o
o
o
0
o
o
T—
o
in
•t
**
%
ff
'• -.f
'
--,-
0
I
0
E
CO
CO
CO
0)
^
co
0
•c
0)
Q.
T3
i
E
1
f^
ca
00
CO
O)
J£
«*^
c
i_
CO
1
o
TJ
o
1
8
£
0)
5
CO
"5.
co
(0
174
-------
Four visual inspections were required at this site. The site failed the first visual
inspection because of the presence of residual materials or loose granular debris on
corkboards and walls, on tops of wood partitions under the stage, on light fixtures and
electrical cords, at ceiling-wall junctions, and on the carpeted area around the stage.
The contractor was required to reclean these areas. After the affected areas were
recleaned, NJDOH conducted a second visual inspection. The site failed the second
visual inspection because of debris at ceiling-wall junctions, above the entry doorway,
on electrical wires, and on corkboards. The Contractor was again required to reclean
the affected areas. After the areas were recleaned, NJDOH conducted a third visual
inspection. The site failed the third visual inspection because of the presence of
debris at ceiling-wall junctions and on the floor. After these areas were recleaned,
NJDOH conducted a fourth visual inspection, which the site passed.
1991 Inspection
Although monitoring conducted in May 1991 found airborne asbestos levels
within the AHERA criterion, on October 30, 1(991, NJDOH conducted a visual
inspection at Site I as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in October 1991.
1988 Abatement Areas \
i
Entry Lobby and Athletic Office-Dust from one sample on top of the trophy
cabinet and inside the radiator at the east window wall tested positive for chrysotile
asbestos (Table B-57).
/Aad/tor/i/m-Unsecured scaffolding limited the inspection, and extension ladders
were not available. No debris was noted.
1988 Perimeter Areas \
i
Cor/7'c/brs-Thermal system insulation was noted above the suspended ceilings
of the corridors. It appeared to be in generally good condition.
Library Office-Residue from the ceiling abatement was found on the window
soffit. This material tested positive for chrysotile asbestos (Table B-57).
i
Library Air-Handling Room-Thermal system insulation debris (2 to 5 percent
chrysotile asbestos) was found on the floors and the upper surfaces of the air-handiinq
units (Table B-57). j
175
-------
CO/7C/17S/0/7S
Residual asbestos-containing dust was noted on horizontal surfaces in several
areas of the 1988 abatement area and perimeter areas.
TABLE B-57. SUMMARY OF BULK SAMPLE RESULTS - SITE I
1991 INSPECTION
Location
Analyses
1988 Abatement Area
Entry lobby
Entry lobby
Entry lobby
1988 Perimeter Areas
Library, office
Library, air-handling
room
Library, air-handling
room
Library, air-handling
room
Dust, top of trophy cabinet,
east side (wipe sample)
Dust, top of trophy cabinet,
east side (wipe sample)
Dust inside east radiator
(wipe sample)
Residue, window soffit
Elbow debris on floor
Top air unit, elbow debris
Debris, top of east unit
Negative
Positive3, chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
2% Chrysotile asbestos
5% Chrysotile asbestos
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
176
-------
SITE J
Background
Site Description
The abatement project at this two-story school building involved the removal of
approximately 5300 ft2 of spray-applied asbestos-containing fireproofing from structural
steel and metal ceiling decks. The abatement area included two electrical transformer
vaults and two mechanical equipment rooms. The project specifications indicated that
the asbestos content of the cementitious fireproofing was approximately 10 to 25
percent chrysotile. The information .regarding the abated ACM and associated
asbestos content was obtained from the asbestos abatement specifications for this
site. i
Air Monitoring Summary
i
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area but inside the building), and outdoors at
approximately the same time and location as^those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST. In 1990, air samples
were collected at this school by use of a modified aggressive sampling technique to
simulate occupied conditions. The samples vyere collected at approximately the same
locations as those collected in 1988. In 1991! and 1992, air samples were collected at
this school during occupied conditions (i.e., during normal school operating hours) at
approximately the same locations as those collected in 1988 and 1990.
i
Summary of Air Monitoring Results
i
Table B-58 summarizes the results frorn the four sampling efforts. Figure B-10
shows the mean airborne asbestos concentrations at Site J. A single-factor ANOVA
was used to compare mean concentrations measured in each of the three sampling
locations. Table B-59 presents the results of the ANOVA analysis. The following
subsections summarize the pairwise comparisons of the mean concentrations in the
three sampling locations.
177
-------
TABLE B-58. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Ja
,
" sawing $88rfod
Wn'-
Mean
Win
Max
Mln
-
tee
0.004
0.004
0.004
0.001
0.004
0.001
0.004
0.003
0.005
0.003
0.011
0.001
0.004
0.003
0.005 0.012
0.055 0.001
0.003
" Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-59. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE J
Posl:abat erne nt-1988 -
- -
0.0086
0.0156
0.2878
0.5921
A(0.004) P(O.OOI) O(0.001)
P(0.003) A(0) 0(0)
A(0.003) O(0.001)
P(0.012) A(0.003) 0(0.001)
8 If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pain/vise differences between sampling locations.
b A = 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
d Sampling locations (means) connected by a line are not significantly different.
178
-------
q
d
b
o
o
o
q
o
\
0)
«*-"
0)
'C
0)
Q.
CO
CO
O)
ELUO/S 'UOJ1BJ1U80UOQ SO}S9QSV 8UJOQJJV 86BJ9AV
179
CM
O
0)
03
O
O
0)
o>
CO
CO
0)
XJ
o
(0
d
(A
g
'8
4-<
c
0
o
c
o
o
(A
o
•H*
(/)
(1)
.D
0
c
1_
o
•£
rt
0
0
o
T-
li
0
3
D)
L
-------
Summary of Air Monitoring Results
Postabatement • 1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have passed the
AHERA initial screening test because the average filter concentration (27 s/mm2) was
below 70 s/mm2. Furthermore, the site would have passed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. These results are
consistent with AST sampling results.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.004 s/cm3) was
significantly greater than the average concentration measured outdoors (0.001 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.001 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.001 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.004 s/cm3) was
significantly greater than the average concentration measured in the perimeter areas
(0.0011 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
180
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.003 s/cm3) was significantly greater than the average outdoor concentration
(0 s/cm3).
i
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured in the perimeter areas (0.003 s/cm3).
Occupied Conditions • 1991 i
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured outdoors (p.001 s/cm3).
Comparison of the Perimeter Area With Outdoors
i
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured in the perirrieter area (0 s/cm3).
Occupied Conditions -1992 \
.
Comparison of the Previously Abated Area With Outdoors
i
The average airbdrne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/crn3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
181
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.012 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.012 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988, 1990, 1991, and 1992. Each sampling location was evaluated separately.
Table B-60 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990,1991, and
1992.
TABLE B-60. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE J
„ ' MocaHfjtf^ " ™-
% $. % * S f fjf 'fff^ff "VS fff\? '• -. w "* f ~' "*•••*• V. "" „£ jf ff \v. ,f
Statistically significant differences in mean airborne
' '
0.0219
0.2544
0.6112
1988(0.004) 1991(0.003) 1992(0.003) 1990(0)
1992(0.012) 1990(0.003) 1988(0.001) 1991(0)
1988(0.001) 1991(0.001) 1992(0.001) 1990(0)
a Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
c Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
182
-------
1988 Abatement Area \
Differences between average levels measured in 1988, 1990, 1991, and 1992
were not statistically significant except that the average concentration measured
during simulated occupancy in 1990 was significantly less than that measured during
the AHERA clearance phase of the 1988 abatement. The highest average
concentration (0.004 s/cm3) was measured during the AHERA clearance phase of the
1988 abatement, and the highest individual concentration (0.011 s/cm3) was measured
during occupied conditions in 1991, three years after the 1988 abatement.
Perimeter
Differences between average levels measured in 1988,1990,1991, and 1992
were not statistically significant. The highest average (0.012 s/cm3) and highest
individual (0.055 s/cm3) concentrations were measured during occupied conditions, 4
years after the 1988 abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1988,
1990,1991, and 1992 were not significantly different. The highest average
concentrations (0.001 s/cm3) were measured! in 1988,1991, and 1992 and the highest
individual concentrations (0.004 s/cm3) were measured during the AHERA clearance
phase of the 1988 abatement and during occupied conditions in 1991, three years
after the 1988 abatement. |
Structure Morphology and Size Distributions
Table B-61 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 46 asbestos structures, all of which were
chrysotile asbestos. Overall, the asbestos structures were primarily fibers (78.3
percent), and to a lesser extent, clusters (10.9 percent), matrices (11.6 percent), and
bundles (4.3 percent).
Table B-62 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 97.8 percent
of the observed asbestos structures were less than 5 n.m in length. Of the 36
asbestos fibers observed, none was greater than 5 |im in length.
183
-------
U)
O
3
o
o.
DC
O
a
<
u
a.
u
oc
oc
CO
CO
ui
CD
u_
o
o
ffl
E
fe
Q
ffi
UJ
m
*»
«,
at
'*££.$*
o
CM
in
g
O)
o>
(0
CO
CO
00
CO
-~ •
-8
JB
fi)
CO
CO
CO
0
o
CO
CO
00
00
CO
o
0
CO
CM
"T"
ca
to
a*
0>
f
V
9
Q
o
•8
1
ca
CO
CO
£
CO
a5
S.
TJ
CO
S
a>
o>
co
co
TJ
fi
_CO
8
1
ca
05
184
-------
CO
fe
o
HI
DC
|
Ul
to
Ul
DC
O
DC
S
i
(/)
UJ
ffl
W
U.
O
z
o
=>
m
E
&
S
HI
N
(5
UJ
i
o
CN
CD
HI
m
I-
185
-------
NJDOH Visual Inspection
1988 Inspection
The NJDOH did not perform a visual inspection at this site. Upon completion of
the final cleaning, the abatement contractor requested that a visual inspection be
conducted by the onsite AST, who was the building owner's representative. The AST
conducted the visual inspection within 2 hours after notification and did not identify any
areas that required further cleaning.
1991 Inspection
Although monitoring conducted in May 1991 found airborne asbestos levels
within the AHERA criterion, on November 8,1991, a NJDOH Visual Inspection was
conducted at Site J as a follow-up. This facility did not have an AHERA Management
Plan and being a college is not required to do so. The visual inspection strategy
considered the asbestos abatement history of the site, the operations and
maintenance (O&M) activities, and other sources of possible asbestos contamination.
Only those areas indicated in the following subsections were examined by the NJDOH
inspector in November 1991.
1988 Abatement Areas
Mechanical Hoom-This area contains the air-handling and electrical equipment
for the building. The main room is dominated by the ductwork and blower units of the
HVAC system. Non-asbestos spray-on replacement material had been applied to the
abated surfaces. The replacement materials and the accompanying debris from their
application made it difficult to detect debris or residual material from the original
asbestos application.
It appears that the fiberglass pipe insulation with cementitious joint and elbow
compounds were not removed during the 1988 abatement. Debris was noted in all
areas examined. Also, the repairs made to the materials have rendered a high
number of homogeneous "types." These materials were not sampled because the
facility assumes they are asbestos.
The top of the ducts, wall and ceiling surfaces, mechanical support stands and
brackets, floor drains, and the electrical equipment all showed contamination [5 to 19
percent chrysotile asbestos (Table B-63)]. The areas from which bulk samples were
collected were probably covered with polyethylene sheeting during the 1988
abatement, and were not accessible for a visual inspection prior to air sampling.
186
-------
TABLE B-63. SUMMARY OF BULK SAMPLE RESULTS -- SITE J
1991 INSPECTION
Type of Material
1988 Abatement Area
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
Mechanical room
1988 Perimeter Area
Hallway at mechanical
room entry
Hallway at elevator
Hallway at slate foyer
Hallway at school store
Residue behind ducting
Spray-on debris on wall at
"Dover box \
Spray-on debris top of duct,
filter entry ;
Floor drain, spray-on debris
Spray-on debris, "Alpha"
tank supports
Spray-on debris under main
filter duct
Spray-on debris in floor trap
Southwest corner, spray-on
debris on floor !
Debris in hangers
Wall at entry door, smudge
of spray-on, on Wall
New sealant at duct
Spray-on debris above drop
ceiling j
Spray-on debris above drop
ceiling
\
Overspray above drop
ceiling \
Spray-on debris above
ceiling tile \
9% chrysotile asbestos
Positive8, chrysotile
asbestos
5% chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
19% chrysotile asbestos
Negative
Positive, chrysotile asbestos
Negative
Positive, chrysotile asbestos
Negative
13% chrysotile asbestos
7% chrysotile asbestos
16% chrysotile asbestos
7% chrysotile asbestos
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
187
-------
1988 Perimeter Areas
Hallway at Mechanical Room Entrance-Ths cementitious joints and elbows
associated with the fiberglass pipe insulation were noted in the area above the
dropped ceiling. All of these materials appeared to be in good condition.
The areas below several pipe and duct penetrations in the wall have become
contaminated during abatement or repair actions (7 to 16 percent chrysotile asbestos).
Thick slabs and pieces of spray-on debris from the mechanical room are lying on the
upper surface of the dropped ceiling system by the elevator, by the mechanical room
entrance, and in the area by the slate foyer. The game room and other areas were
not accessed for inspection because of student occupancy and equipment storage.
Overspray was also noted in these perimeter areas on the beams, block walls, and
ductwork.
Conclusions
As noted earlier, debris was found in areas that may have been covered by
polyethylene sheeting during clearance air sampling or in areas that were outside the
abatement zone (above dropped ceilings). Clearance and followup testing would not
have disturbed such material. Also, much of the asbestos residue and debris has
been covered by replacement material.
Most debris was located on top of and under ducts or in other inaccessible
areas. This material might not be disturbed by floor-level aggressive sampling or daily
operations. Free fibers may have been scavenged from remaining material over time
and exhausted by the ventilation system in these areas.
188
-------
SITEK
Background
Site Description
During the summer of 1988, asbestos-containing acoustical ceiling plaster was
removed from Sites K and N. Site K involved removal of approximately 8200 ft2 of
spray-applied acoustical plaster from an "egg crate design" concrete ceiling. The
abatement area included the carpentry shop, mechanical arts classrooms, and offices.
The acoustical plaster contained 10 to 25 percent chrysotile asbestos. The
information regarding the abated AGM and associated asbestos content was obtained
from the asbestos abatement specifications for this site.
During the summer of 1991, 75,600 square feet of asbestos-containing ceiling
plaster was abated. No other abatement activity occurred between 1988 and 1992.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area, and outdoors at approximately the same time and location as those
samples collected by the Asbestos Safety Technician (AST) for the AHERA clearance
of the site. Final clearance of the abatement site was based on the samples collected
by the AST. In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988. In 1991 and
1992, air samples were collected at this school during occupied conditions (i.e., during
normal school operating hours) at approximately the same locations as those collected
in 1988 and 1990. I
Summary of Air Monitoring Results
Table B-64 summarizes the results from the four sampling efforts. Figure B-11
shows the mean airborne asbestos concentrations at Site K. A single-factor ANOVA
was used to compare mean concentrations rpeasured in each of the three sampling
locations. Table B-65 presents the results of! the ANOVA analysis. The subsections
following the tables summarize the pairwise comparisons of the mean concentrations
in the three sampling locations.
189
-------
TABLE B-64. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Ka
Sarapiiftg period
-sain
Max
Mean
Iffis'
Max
Win
.Poslafoatemenirisaa
0.063
0.035
0.103
0.008
0.015
0.007
0.005
0.010
0.001
0.005
0.041
0.014
0.097
0.003
0.007
,, 0.007
0.017 0.002
0.005
0.004
0.012
Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-65. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE K
0.0001
0.0059
0.0001
0.3567
A(0.063) P(0.008) O(0)
P(0.007) O(0.001)
A(0.041) P(0.003)
A(0.007) O(0.004) PfO.002)
a If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b A = 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
Sampling locations (means) connected by a line are not significantly different.
190
-------
o
d
g
d
o
o
o
.. ^^..^
- -~
o
o
T>
*•*
O
q
o
o
o
etUO/S 'UOJJBJ1U80UOQ SO}S8QSV 8UJOqj|V 86BJ9AV
191
o
o
o
w
0)
0>
0)
O)
o
0)
0)
CO
CO
en
i
(0
c
o
o
c
o
o
CO
CD
0
c
o
•E
'(5
O)
2
0
I
CO
0)
DJ
LL
-------
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured during the AHERA clearance
phase of the 1988 abatement by EPA/NJDOH showed that this site would have failed
the AHERA initial screening test because the average filter concentration (431 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. Although the site
ultimately passed AHERA clearance by using the AST sampling results, the
EPA/NJDOH results clearly show that elevated levels of airborne asbestos still existed
in the school in 1988.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.063 s/cm3) was
significantly greater than the average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.008 s/cm3) was
significantly greater than the average concentration measured outdoors (0 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.063 s/cm3) was
significantly greater than the average concentration measured in the perimeter area
(0.008 s/cm3).
Simulated Occupancy - 1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
192
-------
Comparison of the Perimeter Area With Outdoors
i
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.007 s/cm3) was significantly greater than the average outdoor concentration
(0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured in the perimeter area (0.007 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.041 s/cm3) was significantly less than the average
concentration measured outdoors (0 s/cm3). :
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.003 s/cm3;) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.041 s/cm3) was significantly greater than the
average concentration measured in the perimeter areas (0.003 s/cm3).
Occupied Conditions -1992 !
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.007 s/crfn3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
193
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.002 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.007 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.002 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988, 1990, 1991, and 1992. Each sampling location was evaluated separately.
Table B-66 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
TABLE B-66. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE K
.
location*
... ANQVA
Statistically significant differences ia mean airborne
area,.
perimeter arsa ,,,,
0.0001
0.3674
0.2137
1988(0.063) 1991(0.041) 1992(0.007) 1990(0)
1988(0.008) 1990(0.007) 1991(0.003) 1992(0.002)
1992(0.004) 1990(0.001) 1988(0) 1991(0)
a Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
c Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
194
-------
1988 Abatement Area
The average airborne asbestos concentrations measure during the AHERA
clearance phase of the 1988 abatement (0.063 s/cm3) and during occupied conditions
in 1991 (0.041 s/cm3) were not significantly different, but they were significantly
greater than the average concentrations measured during simulated occupancy in
1990 (0 s/cm3) and during occupied conditions in 1992 (0.007 s/cm3). Furthermore,
the average concentration measured in 1992 was significantly greater than the
average concentration measured in 1990. The highest average concentration and the
highest individual concentration were measured during the AHERA clearance phase of
the 1988 abatement.
i
Perimeter
Differences between average levels measured in 1988, 1990, 1991, and 1992
were not statistically significant. The highest1 average (0.008 s/cm3) and highest
individual (0.015 s/cm3) concentrations were 'measured during the AHERA clearance
phase of the 1988 abatement.
i
Outdoors '
,
The average airborne asbestos concentrations measured outdoors in 1988,
1990,1991, and 1992 were not significantly different. The highest average
concentration (0.004 s/cm3) and the highest individual concentration (0.012 s/cm3)
were measured during occupied conditions in 1992, four years after the 1988
abatement.
Structure Morphology and Size Distributions
Table B-67 presents the distribution ofi structure type and morphology at each
sampling location separately for each year of| monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 169 asbestos structures, all of which were
chrysotile asbestos. Overall, the asbestos structures were primarily fibers (84.6
percent), and to a lesser extent, matrices (107 percent), clusters (3.0 percent), and
bundles (1.8 percent). i
Table B-68 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each y6ar of monitoring. Overall, 97.6 percent
of the observed asbestos structures were less than 5 urn in length. Of the 143
asbestos fibers observed, only 1 (0.7 percent} was greater than 5 |im in length.
195
-------
2*
1=
CO
(3
3
o
Q.
tr
i
Q
Z
Ul
o.
I-
Ul
QC
§
i
CO
Ul
ffi
U,
O
Z
o
a
E
ffi
UJ
m
t
jf
-I
'^«
f""^
•vX-X-> ^ ^
B
.-. S
CO
CM
co
CM
CO
o
o
CO
"o
o>
O)
O
O)
CO
CM
to-,
""•CO"
CO
§
s
o
o
o
0
in
CO
i
1
.$»«:
I
i
CO
•c
8.
T3
CD
-------
O)
IU
EC
3
<
LU
(0
01
DC
tr
CO
I
Ul
m
CO
<
u.
O
o
p
CD
I
Q
N
CO
UJ
O
CD
CD
CQ
UJ
ffl
f
§
$
o
S
t
'JU
a*
a:
O>
OJ
0)
CM
CT
cS
8
in
o
o
o
o
o
0
o
0
o
0
<£>
s!
V
i
2
o
1
o
T3
(0
(0
<5
o
Q.
TJ
i
•a
CO
CO
O)
CD
1
0)
8
£
i
s
t
CD
w
o
197
-------
Followup Air Monitoring - August 1991
Because the average airborne asbestos concentration in the previously abated
area (0.041 s/cm3) exceeded 0.02 s/cm3 in April 1991, EPA/NJDOH conducted follow-
up monitoring under simulated occupancy conditions on August 14, 1991, to determine
whether airborne asbestos was still present at levels similar to those measured in April
1991. The August 14 results revealed that the average airborne asbestos
concentrations in the previously abated area and in the perimeter area were below
0.02 s/cm3; therefore, no further monitoring activity was required at this school.
Intervention continued, however, to resolve the elevated asbestos concentrations at
this site.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site K as part of the State's traditional quality assurance program which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Four visual inspections were required at this site. The site failed the first visual
inspection because of the presence of gross debris on the concrete substrate
surfaces, under pipe hangers, on vertical and horizontal surfaces, and on the
scaffolding equipment. The contractor was then required to reclean the affected
areas. After the areas were recleaned, NJDOH conducted a second visual inspection.
The site failed the second visual inspection because of gross debris found behind
immovable wooden shelves, at floor-wall junctions, behind student lockers, on
horizontal surfaces, and on other immovable objects. The contractor was again
required to reclean the affected areas. After the areas were recleaned, NJDOH
conducted a third visual inspection. The site failed the third visual inspection because
of gross debris on horizontal surfaces, behind immovable objects, and at floor-wall .
junctions. After the affected areas were recleaned, NJDOH conducted a fourth visual
inspection, which the site passed.
1991 Inspection
On August 15, 1991, an NJDOH visual inspection was conducted at Sites K
and M as a followup. The visual inspection strategy considered the asbestos-
abatement history of the site, the O&M activities, and other sources of possible
asbestos contamination (i.e., materials not included in the Asbestos Management
Plan). Only those areas indicated in the following subsections were examined.
198
-------
1988 Abatement Areas
Carpentry Shop and C/assroom--The surface dust found on building and
equipment surfaces tested positive for asbestos (Table B-69). Floor tile from the
carpentry classroom contained 7 percent chrysotile. The floor tile was not identified as
ACM in the Asbestos Management Plan. |
1988 Perimeter Areas ',
Hallway and Miscellaneous Classrooms-Samples of building materials found in
these areas did not show detectable levels of asbestos.
Conclusions
Asbestos-containing dust was present; on surfaces in the carpentry shop.
Asbestos materials in the brake and clutch assemblies in various high speed
equipment could be a possible source of the elevated asbestos levels in the 1988
abatement area. The misidentification of vinyl asbestos-containing floor tile (VAT) in
the Asbestos Management Plan could also lead to uncontained VAT removals,
improper O&M, and possible contamination.
199
-------
TABLE B-69. SUMMARY OF BULK SAMPLE RESULTS
SITE K 1991 INSPECTION
Tyjteof material
Analyses
1988 Abatement Area
Dust samples:
Carpentry loft
Carpentry shop
Carpentry shop
Carpentry shop
Carpentry shop
Carpentry shop
Bulk samples:
Carpentry shop
Carpentry classroom
Carpentry shop
Carpentry shop
Carpentry shop
Carpentry shop
Carpentry shop classroom
Carpentry shop
1988 F'erimeter Area
Hall outside carpentry shop
Special education
Exterior storage
Duct grill
North Nesbitt heater
South Nesbitt heater
Table saw motor box
Window ledge, north
Window ledge, north
Spray-on ceiling material
Dust, top of ceiling
Roofing felt
Spray flakes, window ledge
Roof shingles (display)
Ceiling tile
Floor tile
Sheetrock (display)
Ceiling tile
Sheetrock (stored)
Mason's stand
Negative
Positive0, amosite asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
Positive, amosite asbestos
Positive, chrysotile asbestos
Positive, amosite asbestos
Negative
Negative
Negative
Negative
Negative
Negative
7% Chrysotile asbestos
Traceb, chrysotile asbestos
Negative
Negative
Negative
" This classification was defined by the NJDOH laboratory to accommodate samples for which inadequate material
was sivailable to allow a full quantitative evaluation, but were of sufficient size to determine that asbestos was
present and to determine the specific type of asbestos. Based on the professional judgment of the analyst, the
sample is considered to contain greater than 1 percent asbestos.
b Trace = <1 percent asbestos.
200
-------
SITEL
Background
Site Description
i
The abatement project at this single-sjtory school building involved the removal
of approximately 1600 ft2 of trowel-applied, asbestos-containing, acoustical ceiling
plaster. The abatement area was an auditorium. The project specifications indicated
that the asbestos content of the ceiling plaster was approximately 15 to 25 percent.
The information regarding the abated ACM and associated asbestos content was
obtained from the asbestos abatement specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area, but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST. In 1990, air samples
were collected at this school by use of a modified aggressive sampling technique to
simulate occupied conditions. The samples were collected at approximately the same
locations as those collected in 1988. In 199]l and 1992, air samples were collected at
this school during occupied conditions (i.e., during normal school operating hours) at
approximately the same locations as those collected in 1988 and 1990.
i
Summary of Air Monitoring Results
Table B-70 summarizes the results frdm the four sampling efforts. Figure B-12
shows the mean airborne asbestos concentrations at Site L. A single-factor ANOVA
was used to compare mean concentrations measured in each of the three sampling
locations. Table B-71 presents the results of the ANOVA analysis. The subsections
following the tables summarize the pain/vise comparisons of the mean concentrations
in the three sampling locations. I
Postabatement -1988 \
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have failed the
AHERA initial screening test because the average filter concentration (768 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA Z-test
201
-------
TABLE B-70. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(S/cm3) MEASURED AT SITE La
Sampling period
Mean
Mirt
Max
Max
Mean
0.118
0.093
0.156
0.060
0.026
0.181
0.004
0.015
0.002
0.010
0.001
0.005
0.006
0.016
0.003
0.006
0.003
0.007 0.002
0.005
• Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-71. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE L
"'
Statistically sjgnifieanl deferences in mean
0.0001
0.6016
0.0752
0.0408
A(0.118) R0.0601 O(0.004)
A(0.002) PfO.OOD O(0)
A(0.006) P(0.003) O(01
A(0.003) P(0.002) O(0)
If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
A = 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
Sampling locations (means) connected by a line are not significantly different.
202
-------
q
c>
o
q
d
o
o
q
6
o
o
o
(0
o
o
•o
oo
oo
o
CD
•I-J
£0
TO
Q)
Cti
0
(0
c
g
i
••_>
c
CD
O
C
o
o
to
o
4-1
(/}
0)
.Q
CD
C
i_
O
•9
"5
CD
0
CM
T~
I
m
0)
3
D)
LL
-------
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the^perimeter concentrations. Although the site
ultimately passed AHERA clearance by using the AST sampling results, the
EPA/IMJDOH results clearly show that elevated levels of airborne asbestos still existed
in the school in 1988.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.118 s/cm3) was
significantly greater than the average concentration measured outdoors (0.004 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.060 s/cm3) was
significantly greater than the average concentration measured outdoors (0.004 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.118 s/cm3) was not
significantly different from the average concentration measured in the perimeter areas
(0.060 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.002 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.001 s/cm3) was not significantly different from the average outdoor
concentration (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.002 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
204
-------
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
I
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.006 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.003 s/cm3|) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.006 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.003 s/cm3).
i
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/crn3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.002 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
i
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/cnS3) was not significantly different from the
average concentration measured in the perimeter area (0.002 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
i
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990, 1991, and 1992. Each sampling location was evaluated separately.
i
205
-------
Table B-72 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
TABLE B-72. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE L
j?-vatueh
Fn rae&n airftorae
area
0.0001
0.0001
0.1191
1988(0.118) 1991(0.006) 1992(0.003) 1990(0.002)
1988(0.060) 1991(0.003) 1992(0.002) 1990(0.001)
1988(0.004) 1990(0) 1991(0) 1992(0)
a Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
1988 Abatement Area
The average airborne asbestos concentrations measure during the AHERA
clearance phase of the 1988 abatement (0.118 s/cm3) was significantly greater than
the average concentration measured during simulated occupancy in 1990 (0.002
s/cm3) and during occupied conditions in 1991 (0.006 s/cm3) and 1992 (0.003 s/cm3).
Differences between average airborne asbestos concentrations measured in 1990,
1991, and 1992 were not statistically significant. The highest average concentration
(0.118 s/cm3) and the highest individual concentration (0.156 s/cm3) were measured
during the AHERA clearance phase of the 1988-abatement.
206
-------
Perimeter
The average airborne asbestos concentration measured during the AHERA
clearance phase of the 1988 abatement (0.060 s/cm3) was significantly greater than
the average concentrations measured during simulated occupancy in 1990
(0.001 s/crn3) and during occupied conditions in 1991 (0.003 s/cm3) and 1992 (0.002
s/cm3). Differences between average airborne asbestos concentrations measured in
1990,1991, and 1992 were not statistically significant. The highest average
concentration (0.060 s/cm3) and the highest individual concentration (0.181 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
i
Outdoors
The average airborne asbestos concentrations measured outdoors in 1988,
1990,1991, and 1992 were not significantly different. The highest average
concentration (0.004 s/cm3) and the highest individual concentration (0.015 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
Structure Morphology and Size Distributions
Table B-73 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 273 asbestos structures, of which 99.6 percent
were chrysotiie asbestos and 0.4 percent were amphibole asbestos. Overall, the
asbestos structures were primarily fibers (61J9 percent), and to a lesser extent,
clusters (18.3 percent), matrices (14.3 percent), and bundles (5.5 percent).
Table B-74 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each yjear of monitoring. Overall, 93.0 percent
of the observed asbestos structures were less than 5 jim in length. Of the 169
asbestos fibers observed, only 9 (5.4 percent) were greater than 5 ^m in length.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site L as part of the State's traditional quality assurance program which provides a
check and balance to asbestos abatement to! ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
207
-------
o
Q.
DC
O
a
UJ
Q.
UJ
DC
DC
(0
UJ
ffi
ffi
1
5
UJ
ffi
;|
1a
/ "
*
'"<$
JO
•>
CO
CM
to
1—
CM
CO
o>
in
8
o
tn
CM
to
CO
CO
CO
CM
CO
in
CO
r
»
CO
cvi
CM
CO
0)
o
0
CO
o
CM
U)
« ;,.,,..
& »
ft. ta
0
o
in
CO
s
o
o
1
.2
"S
•c
0>
Q.
•o
Q3
CD
CO
CO
CO
O5
I
CO
£
"I
o
.1
_OJ
8
s
I
to
CD
208
-------
55
Q
111
CC
1
CO
HI
CC
1
DC
I
Ul
1
I
CO
E
i
CO
111
1
O
m
in
m
a
3
*» v
. <-»
rf ^•y/
l!
OJ :
CM
S
§3
to
10
CM
00
a>
CO
CM
LO
O)
CD
00
10
9
,•-.•«•,, >'.
m
05
i
i
I
o
TJ
CO
U)
co
s
co
CD
CD
Q.
1
CO
0)
CD
i
s
O)
CD
I
I
0)
T3
fi
•22
8
£
i
CO
.CD
CO
CO
209
-------
Two visual inspections were, required at this site. The site failed the first visual
inspection because of the presence of debris on thes upper ledge of the auditorium
ceiling and on the wooden blocks used to support th*e polyethylene containment
barriers. The contractor was then required to reclean these areas. After the areas
were recleaned, NJDOH conducted a second visual inspection, which the site passed.
1991 Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, NJDOH conducted a visual inspection at Site L on
October 24, 1991, as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated the following subsections were
examined by the NJDOH inspector in October 1991.
1988 Abatement Areas
Auditorium-DufmQ the abatement of acoustical ceiling materials in the
auditorium in 1988, scaffolding was used to access the materials, which were
approximately 35 feet above the floor. The sloping floor prevented the use of
conventional extension ladders to access the abatement zone. An attempt was made
to access the overhead areas via an opening in the wall above the projection booth
area; however, it was questionable whether the 1 ft-by-6 in. ductwork in this area or
the plaster ceiling would support any weight. No catwalks were available to gain
access to the truss/black-iron system to conduct an inspection for debris or overspray
materials. Either some white "splotches" remained after abatement or they were
splashes of encapsulant.
1988 Perimeter Areas
Stage-The Asbestos Management Plan does not list thermal system insulation
in the stage area; however, the roof drain appears to be cementitious material that has
sustained some minor damage from stored lumber (Table B-75).
Comctors-Thermal system insulation is present on pipe joints and elbows in the
plenum above the corridor drop ceiling. The materials appear to have been disturbed.
The Management Plan does not reflect this activity.
COA7C/L/S/O/7S
Inaccessibility to the abated areas prevented a definitive reinspection of the
site.
210
-------
TABLE B-75. SUMMARY OF BULK SAMPLE RESULTS - SITE L
1991 INSPECTION
•'"type of teertal
Air handling loft, stage
Air handling loft, stage
Elbow, air unit
Elbow, air unit
Negative
Trace3, chrysotile asbestos
Trace ~ <1 percent asbestos.
211
-------
SITEM
Background
Site Description
During the summer of 1988, two asbestos abatement projects were conducted
at this school. Asbestos-containing thermal system insulation (TSI) was removed from
a boiler, water tank, fan duct, and pipes in the boiler room located in the basement
and from pipes in the corridor adjacent to the boiler room (Site C). TSI was removed
from pipes in the corridors, classrooms, offices, storage rooms, and gymnasium
located in the basement (Site M). The TSI contained approximately 40 to 60 percent
chrysotile asbestos. The information regarding the abated ACM and associated
asbestos content was obtained from the asbestos abatement specifications for this
site. There has been no additional abatement activity since 1988.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area but inside the building), and outdoors at
approximately the same time and location as the samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Preabatement samples
were also collected in the abatement area and outdoors before the 1988 abatement
activities. Final clearance of the abatement site was based on the samples collected
by the AST.
In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988.
In 1991 and 1992, air samples were collected at this school during actual
occupied conditions (i.e., during normal school operating hours) at approximately the
same locations as those collected in 1988 and 1990.
Summary of Air Monitoring Results
Table B-76 summarizes the results of the five sampling efforts. Figure B-13
illustrates the mean airborne asbestos concentrations at Site M. A single-factor
ANOVA was used to compare mean concentrations measured in each of the three
sampling locations. The results of the ANOVA analysis are presented in Table B-77.
The following subsections summarize the pairwise comparisons of the mean
concentrations in the three sampling locations.
212
-------
TABLE B-76. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Ma
Mean
Mean
Max
Mean
Win
0.001
0.004
0.003
0.011
0.322
0.054
0.530
0.002
0.008
0.002
0.004
1990
1991
0.023
0.056
0.004"
0.007
0.003
CXasup&rf condhfc&s^
199? *
0.003
0.005
0.005"
0.013
0.003
0.007
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b Outdoor samples are the same as those collected at Site C in 1990. 1991, and 1992 (Site M was the second
abatement project at this school in 1988).
0 Preabatement samples were not collected in the perimeter areas.
* N-4.
TABLE B-77. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE M
0.4466
0.0001
1.0
0.1924
0.8649
O(0.003) A(0.0011
A(0.322) P(0.002) O(0.002)
A(0) P(0) 0(0)
A(0.023) P(0.004) O(0.003)
P(0.005) A(0.003) O(0.003)
* If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b As 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location. :
d Sampling locations (means) connected by a line are not significantly different.
213
-------
q
6
o
o
o
o
o
CO
CO
0)
4->
0)
E
oo
CO
0)
CJ
05
0)
O)
0)
o
0)
O5
CO
CO
0)
o
6
o
o
o
o
o
0
4->
CO
S
•a
CO
0
E
(A
C
O
'
o
c
o
o
o
•t-l
CO
0
c
as
0
D)
0
CO
1
CO
0
O)
E
BLUO/S '
sojseqsv
e6BJ9Av
214
-------
Preabatement -1988
The average airborne asbestos concentration measured in the abatement area
before the abatement (0.001 s/cm3) was not significantly different from the average
concentrations measured outdoors (0.003 s/cm3).
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement by EPA/NJDOH showed that this site would
have failed the AHERA initial screening test because the average filter concentration
(2146 s/mm2) exceeded 70 s/mm2. Furthermore, the site would have failed the
AHERA Z-test regardless of whether the abatement area concentrations were
compared with the outdoor concentrations or| with the perimeter concentrations.
Although the site ultimately passed AHERA clearance by using the AST sampling
results, the EPA/NJDOH results clearly show that elevated levels of airborne asbestos
still existed in the school in 1988.
r
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.322 s/cm3) was
significantly greater than the average concentration measured outdoors (0.002 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.002 s/cm3) was not
significantly different from the average concentration measured outdoors (0.002
s/cm3).
Comparison of the Abatement Area With the Perimeter Area
i
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.322 s/cm3) was
significantly greater than the average concentration measured in the perimeter areas
(0.002 s/cm3).
215
-------
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0 s/cm3) was not significantly different from the average outdoor concentration
(0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.023 s/cm3) was not significantly different from the
average concentration measured outdoors (0.003 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured outdoors (0.003 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.023 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.004 s/cm3).
216
-------
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/crp3) was not significantly different from the
average concentration measured outdoors (0.003 s/cm3).
Comparison of the Perimeter Area With Outdoors
i
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured outdoors (0.003 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.005 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990,1991, and 1992. Each sampling location was evaluated separately.
Table B-78 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
1988 Abatement Area
i
The average airborne asbestos concentrations measure during the AHERA
clearance phase of the 1988 abatement (0.322 s/cm3) was significantly greater than
the average concentrations measured during simulated occupancy in 1990 (0 s/cm3)
and during occupied conditions in 1991 (0.023 s/cm3) and in 1992 (0.003 s/cm3).
Differences between average airborne asbestos concentrations measured during
occupied conditions in 1991 and 1992 were not statistically significant. Nor were the
average concentrations measured in 1990 and 1992 statistically significant. The
average concentration measured during occupied conditions in 1991 was, however,
significantly greater than the average concentration measured during simulated
occupancy in 1990. The highest average concentration (0.322 s/cm3) and the highest
individual concentration (0.530 s/cm3) were measured during the AHERA clearance
phase of the 1988 abatement.
217
-------
TABLE B-78. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990,1991, AND 1992 AT SITE M
.;- Samptteg
AMOVA
Sfatl^tlcaJly ^igftiilcaRi Differences tti wiean a!rt?orne
, "\ „, asbestos
Abatement area
Perimeter area
0.0001
0.1487
0.2707
1988(0.322) 1991(0.023) 1992(0.003) 1990(0)
1991(0.005) 1992(0.005) 1988(0.002) 1990(0)
1991(0.003) 1992(0.003) 1988(0.002) 1990(0)
8 Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
Perimeter
The average airborne asbestos concentrations measured in the perimeter area
in 1988, 1990, 1991, and 1992 were not significantly different. The highest average
concentrations (0.005 s/cm3) was measured during occupied conditions in 1992 and
the highest individual concentrations (0.013 s/cm3) were measured during occupied
conditions in 1992, 4 years after the 1988 abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1988,
1990, 1991, and 1992 were not significantly different. The highest average
concentration (0.003 s/cm3) and the highest individual concentrations (0.011 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
Structure Morphology and Size Distributions
Table B-79 presents the distribution of structure type and morphology at each
sampling location for each year of monitoring. The TEM analysis of 20 samples
collected in the abated area, 20 collected in the perimeter area, and 20 collected
218
-------
s
m
Q.
DC
Q
<
W
D.
UI
CC
I
I
0)
111
GQ
u.
O
1
ED
I
5
ffi
IU
ffl
s
f
CO
CM
s
CM
'to*
CO
CO
-
T'
in
s
CM
•i
'
0
o
CO
Of)
CO
CO
§
TJ
CO
cS
CD
I
•a
co
a>
00
§
I
ca
CD
CD
•§
.CD
8
CD
CD
CO
^
t
ca
ca
t3
CD
CD
I
i
CO
CD
S
CD
.is
OT,
CM
O)
en
T-
•O
CO
O)
CD
cn
CD
CO
to
T3
CD
"G
CD
™ 8
I
CO
CO
CD
CD
£
co
CO
t
ea-
CD
£
219
-------
outdoors yielded a total of 317 asbestos structures, of which 99.7 percent were
chrysotile asbestos and 0.3 percent were amphibole asbestos. Overall, the asbestos
structures were primarily fibers (68.1 percent), and to a lesser extent, matrices
(22.4 percent), clusters (7.3 percent), and bundles (2.2 percent).
Table B-80 presents the cumulative size distribution of asbestos samples at
each sampling location for each year of monitoring. Overall, 94.6 percent of the
obseived asbestos structures were less than 5 ^.m in length. Of the 216 asbestos
fibers observed, only 7 (3.3 percent) was greater than 5 jim in length.
Followup Air Monitoring - August 1991
Because the May 1991 average airborne asbestos concentration in the
previously abated area (0.023 s/cm3) exceeded 0.02 s/cm3, EPA/NJDOH conducted
followup monitoring on August 13, 1991, under simulated occupancy conditions, to
determine whether the airborne asbestos was still present at levels similar to those
measured in May. The average airborne asbestos concentrations in the previously
abated area (0.033 s/cm3) still exceeded 0.02 s/cm3; therefore, NJDOH directed the
school to initiate a response action to reduce the airborne asbestos concentrations in
the previously abated area. The school subsequently employed a licensed asbestos
abatement contractor to clean these areas.
i
When the response action was complete, EPA/NJDOH conducted followup air
monitoring on August 29, 1991, to determine the residual levels of airborne asbestos.
Although the average airborne asbestos concentrations in the previously abated area
(0.001 s/cm3) was below 0.02 s/cm3, the average concentration in the perimeter area
(0.029 s/cm3) exceeded 0.02 s/cm3, therefore, NJDOH directed the school to reclean
the perimeter areas. After the second response action NJDOH collected additional
samples on September 3,1991, in the previously abated area and the perimeter area.
Average airborne asbestos concentrations in the previously abated area (0.005 s/cm3,
N=2) and the perimeter area (0 s/cm3, N=8) were both below 0.02 s/cm3; therefore, no
further action was required at this site. Intervention continued, however, to resolve the
elevated asbestos concentrations at this site.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site M as part of the State's traditional quality assurance program. This provides a
check and balance to asbestos abatement and ensures that high-quality abatement
and state-of-the art work practices are used. The onsite AST collected AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
220
-------
E
CO
LU
DC
1
(0
UJ
GC
I
(0
CO
LU
m
u.
O
z
o
I-
m
I
5
UJ
N
CO
LU
1=
O
op
CD
Ul
_J
ffl
0
CO
CO
CO
8?
*
to
CM
U)
g
CO
CO
**
£2
CO
CO
I
CD
8. £
l
CD
0>
CO
|
CO
£
8
£
CD
^
CO
•!
Q.
I
52
I
1
CD
1
g
CO,
CM
en
en
o
en
en
O
W
co
52
.co
8
8
co
co
CD
co
CO
CD
I «
§•
CO •
.2 eo"
Q-m
E £
co ^
«o c
H
221
-------
Three visual inspections w^re required at thislsite. The site failed the first
because debris was present on the floors and on pipe joints and elbows. The
contractor was then required to reclean these areas^ After the areas were recleaned,
NJDOH conducted a second visual inspection. The site failed the second visual
inspection because debris was found on pipes, on the floors and in wall penetrations.
When these areas were recleaned, NJDOH conducted a third visual inspection and
the site passed.
1991 Inspection
NJDOH conducted another visual inspection at Site M on August 14, 1991 to
determine potential sources of airborne asbestos measured by EPA/NJDOH in May
1991. The visual inspection strategy considered the asbestos-abatement history of
the site, the O&M activities, and other sources of possible asbestos contamination
(i.e., materials not included in the Asbestos Management Plan). In August 1991, the
NJDOH inspector examined only those areas indicated in the following subsections.
1988 Abatement Areas
Classroom, Small Gymnasium, and Corridors
No TSI debris was found in these abatement areas. Plaster debris from the
wall and ceiling surfaces was evident in many areas. Top-coat plaster from the
recreation room and hallway did not test positive for asbestos; however, the browncoat
underlay in the adjoining hallway showed trace amounts of chrysotile asbestos (Table
B-81). The storage and office areas were locked and could not be accessed.
1988 Perimeter Area
Boiler Room-Miscellaneous debris mixed in with the coal tested positive for
chrysotile (19 percent), amosite (3 percent), and crocidolite (trace) asbestos (Table B-
81). The TSI debris mixed in with the coal tested positive for chrysotile asbestos.
The TSI debris found under the boiler room stairway tested positive for chrysotile
asbesitos (67 percent).
Large Gymnasium-Plaster dust and debris from renovation work were
widespread along the north wall. No samples of the plaster dust were collected.
Other Considerations
The School's Asbestos Management Plan identified plaster as an asbestos-
cpntafning building material (ACBM). Samples taken by the NJDOH were reported as
either 1 percent chrysotile asbestos, <1 percent chrysotile asbestos, or as negative for
asbestos (Table B-81). Although none of these materials tested greater than 1
222
-------
percent asbestos, the Asbestos Management Plan classified them as friable surfacing
materials with damage and indicated that repairs would be made by September 1,
1989. At the time of the NJDOH inspection, no repairs had been made, however, the
plaster debris on the floor surfaces in the large gymnasium had been cleaned up.
Conclusions
The deterioration of the plaster in the building and activities involved in the
renovation and repair of the plaster may have contributed to the elevated
concentrations of airborne asbestos measured in May 1991.
TABLE B-81. SUMMARY OF BULK SAMPLE RESULTS-SITE M
1991 INSPECTION
material
1988 Abatement Area
Basement recreation
room/classroom
Basement hallway
Basement hallway
1988 Perimeter Area
Boiler room, coal area
Boiler room, coal area
Boiler room, under stairs
Plaster, top coat
Plaster, top coat
Plaster, browncpat
Debris mixed in coal
j
TSI debris >
i
TSI debris
Negative
Negative
Positive3, chrysotile asbestos
3% chrysotile,
19% amosite, positive,
crocidolite asbestos
Positive, chrysotile asbestos
67% chrysotile asbestos
" This classification was defined by the NJDOH laboratory to accommodate samples for which
inadequate material was available to allow a full quantitative evaluation, but were of sufficient size to
determine that asbestos was present and to determine the specific type of asbestos. Based on the
professional judgment of the analyst, the sample is considered to contain greater than 1 percent
asbestos. '
223
-------
SITEN
Background
Site Description
During the summer of 1988, asbestos-containing acoustical ceiling plaster was
removed from Site N. The Site N abatement involved the removal of approximately
11,000 ft2 of ceiling plaster from an "egg crate" design concrete ceiling. The
abatement area included corridors, mechanical arts classrooms, and offices. The
acoustical plaster contained 10 to 25 percent chrysotile asbestos. The information
regarding the abated ACM and associated asbestos content was obtained from the
asbesitos abatement specifications for this site.
During the summer of 1991, 75,600 square feet of asbestos-containing ceiling
plaster was abated. There has been no other abatement activity between 1988 and
1992.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside of the abatement area but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST.
In 1990, air samples were collected at this school by a modified aggressive
sampling technique to simulate occupied conditions. The samples were collected at
approximately the same locations as those collected in 1988.
In 1991 and 1992, air samples were collected at this school during occupied
conditions (i.e., during normal school operating hours) at approximately the same
locations as those collected in 1988 and 1990.
Summary of Air Monitoring Results
Table B-82 summarizes the air monitoring results from the four sampling efforts.
Figure B-14 illustrates the mean airborne asbestos concentrations at Site N. A single-
factor ANOVA was used to compare mean concentrations measured in each of the
three sampling locations. The results of the ANOVA analysis are presented in Table
B-83. The following subsections summarize the pairwise comparisons of the mean
concentrations in the three sampling locations.
224
-------
TABLE B-82. SUMMARY OF AIRBORNE
(s/cm3) MEASURED
ASBESTOS CONCENTRATIONS
AT SITE Na
Mifl
Max
Ouldaoisi*
*
0.100
0.076
0.129
0.003
0.016
0.004
0.004
0.004
\'s'v *" 3 ""> ^ -A ww* •«
<«cupaH; -
0.007
0.031 !
0.004
0.011
0.001
0.005
0.004
0.003
0.009
0.015
0.046
0.004 0.002 0.008
0.006 0.003 0.013 0.004
0.012
* Samples were collected each year in the 1988 abatement
b Outdoor samples are the same as those collected
second abatement project at this school in 1988).
and perimeter areas and outdoors.
at Site K in 1990,1991, and 1992 (Site N was the
TABLE B-83. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE N
iiiiffer^nceis lii.
0.0001
0.6268
0.0125
0.2949
A(0.100) O(0.004) P(0.003)
A(0.007) P(0.004) O(0.001)
P(0.015) A(0.004) O(0)
P(0.006) A(0.004) O(0.004)
" If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pain/vise differences between sampling locations.
b A = 1988 Abatement area;. P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location. i
d Sampling locations (means) connected by a line are not significantly different.
225
-------
q
d
o
q
6
o
o
o
I I
••••^f-y^v- -.•. w •. ^.v
»'- "s;-"- 'VV " „' ,-"•.
2
o
o
T3
4-1
3
o
ns
2
(5
mi i i i i i li ill II i i in i i in I
q
c>
o
q
o
o
o
o
elUO/S 'UO!JBJ}U80UOQ S01S9QSV 9UJOqj|V 6BBJ8AV
226
CO
to
0
(0
CtS
0
E
0)
CM
O)
0)
PI
EJII
O)
O)
T—
o
OJ
^^
H
, 00
00
0)
1
^
O
?
C
0
o
c
o
o
(0
o
w
0
X}
w
03
0
c
0
1
0
O)
CO
0
I
m
0
D)
LL
-------
Postabatement - 1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have failed the
AHERA initial screening test because the average filter concentration (663 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. Although the site
ultimately passed AHERA clearance by using the AST sampling results, the
EPA/NJDOH results clearly show that elevated levels of airborne asbestos still existed
in the school in 1988.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.100 s/cm3) was
significantly greater than the average concentration measured outdoors (0.004 s/cm3).
i
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.003 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.004 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos
during the AHERA clearance phase of the
significantly greater than the average
(0.003 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.007 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
concentration measured in the abatement area
abatement in 1988 (0.100 s/cm3) was
concentration measured in the perimeter areas
227
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.004 s/cm3) was not significantly different from the average outdoor
concentration (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.007 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.004 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.015 s/cm3) was significantly greater than the
average concentration measured outdoors (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.015 s/cm3).
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
228
-------
Comparison of the Perimeter Area With Outdoors
\
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.006 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
\
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.006 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990, 1991, and 1992. Each sampling location was evaluated separately. The
result of the ANOVA analysis is presented in Table B-84, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990,1991, and
1992.
TABLE B-84. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE N
Sta|i$llcaffy signiljcant <3i«emnces in mean airborn
"'*-"' " '
Abatement
•f "*^
, ,S V *'
Perimeter ar&a
\
""•^ •" ^ -,-i
Outdoors /^s
0.0001
0.2248
0.0282
1988(0.100) 1990(0.007) 1991(0.004) 1992(0.004)
1991(0.015) 1992(0.006) 1990(0.004) 1988(0.003)
1988(0.004) 1992(0.004) 1990(0.001) 1991(0)
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring. ;
d Years (means) connected by a line are not significantly different.
229
-------
1988 Abatement Area -6. » '
The average airborne asbestos concentrations measure during the AHERA
clearance phase of the 1988 abatement (0.100 s/cm3) was significantly greater than
the average concentrations measured during simulated occupancy in 1990
(0.007 s/cm3) and during occupied conditions in 1991 (0.004 s/cm3) and in 1992
(0.004 s/cm3). Differences between average airborne asbestos concentrations
measured during occupied conditions in 1990,1991 and 1992 were not statistically
significant. The highest average concentration (0.100 s/cm3) and the highest
individual concentration (0.129 s/cm3) were measured during the AHERA clearance
phase of the 1988 abatement.
1988 Perimeter Area
The average airborne asbestos concentrations measured in the perimeter area
in 1988, 1990, 1991, and 1992 were not significantly different. The highest average
concentrations (0.015 s/cm3) were measured during occupied conditions in 1991 and
1992 and the highest individual concentrations (0.006 s/cm3) were measured during
occupied conditions in 1991, 3 years after the 1988 abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1988 was
significantly greater than the average concentration measured in 1991. Other
differences in the average concentrations measured in 1988, 1990, 1991, and 1992
were not statistically significant. The highest average concentrations (0.004 s/cm3)
were measured in 1988 and in 1992 and the highest individual concentration (0.012
s/cm3) was measured in 1992.
Structure Morphology and Size Distributions
Table B-85 presents the distribution of structure type and morphology at each
sampling location for each year of monitoring. The TEM analysis of 20 samples
collected in the abated area, 20 collected in the perimeter area, and 20 collected
outdoors yielded a total of 203 asbestos structures, all of which were chrysotile
asbestos. Overall, the asbestos structures were primarily fibers (72.9 percent), and to
a lesser extent, matrices (19.2 percent), clusters (4.9 percent), and bundles (3.0
percent).
Table B-86 presents the cumulative size distribution of asbestos samples at
each sampling location for each year of monitoring. Overall, 96.6 percent of the
observed asbestos structures were less than 5 jam in length. Of the 148 asbestos
fibers observed, only 2 (1.4 percent) were greater than 5 |im in length.
230
-------
z
111
CO
§
o
cc
§
Q
Ul
a.
ui
cc
I
CO
CO
I
LIJ
CQ
a.
O
z
o
i=
CQ
CC
Ul
CD
'40
5
EOLI
•*•£•> 1
3 "•*',
f A X
> , >
O)
«o
CO
CO
U)
CO
v?^ V S S'
CM
#4
CM
in
o
o
CD
I!
CO
£
S
Q.
CD
I
£3
CD
8
o
CO
0)
£2
8
I
o
1
CO
05
cc
w
g
O>
i
s §
& «
0
en
O)
T3
i
E
o
£
CO
m i»gj
±S w
«
CO
CO
en
0)
03
I
CD
•a
0)
J
8
I
•t**
$
i
0)
•§ £
8
£
CO
CO
-
-
CO
a
231
-------
HI
CO
a
UJ
DC
1
in
S
co
UJ
EC
0)
g
Ul
CD
S
m
£
»
Q
UJ
N
CO
UJ
1
O
co
°?
m
UJ
a
O.
CM
(M
00
KJJ
81
CNJ
in
CO
S ^
2
"i
CO
CO
I
05
Q.
1
co
05
00
CO
a>
CO
05
co
o
8
8>
ji
i
CD
CO
CO
lc
1
CD
1
CO
I
CO
Z
to
CO
T3
CO
S 8
en T-
05
CO
15
T3
S 8
£
05
CO
|
CO
co
05
CO
CO
S
co
CO
?
o
232
-------
Followup Air Monitoring - August 1991
Although the average airborne asbestps concentrations in the previously abated
area and in the perimeter area did not exceed 0.02 s/cm3 in May 1991, EPA/NJDOH
conducted followup monitoring under simulated occupancy conditions on August 14,
1991, because the average airborne asbestos concentration in the previously abated
area from another abatement project at this school (Site K) did exceed 0.02 s/cm3.
The August 14 results revealed that the average airborne asbestos concentrations in
the previously abated area and in perimeter areas of Site N were below 0.02 s/cm3;
therefore, no further monitoring activity was required at this site.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site N as part of the State's traditional quality assurance program. This provides a
check and balance to asbestos abatement and ensures that high-quality abatement
and state-of-the art work practices are used. The onsite AST collected AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Two visual inspections were required at this site. The site failed the first visual
inspection because debris was present on light fixtures, on the tops of heating
elements, on conduit pipe, on the walls behind ventilation ducts, and on the floors.
The contractor was then required to reclean these areas. When the areas were
recleaned, NJDOH conducted a second visual inspection, which the site passed.
1991 Inspection
On August 15,1991, an NJDOH Visual Inspection was conducted at Sites K
and N to determine potential sources of airborne asbestos measured by EPA/NJDOH
in April 1991. The visual inspection strategy!considered the asbestos-abatement
history of the site, the O&M activities, and other sources of possible asbestos
contamination (i.e., materials not included in the Asbestos Management Plan). Only
those areas indicated in the following subsections were examined.
1988 Abatement Areas
Refrigeration/AC Room, Mechanical (Engine) Room-Surface dust was noted
but not sampled.
233
-------
1988 Perimeter Areas
Classrooms, Mechanical Arts Room-Surface dust was noted but not sampled.
The floor tile in classrooms was not identified as ACM in the Asbestos Management
Plan.
Conclusions
Asbestos materials in the brake and clutch assemblies in various high speed
equipment could be a possible source of airborne asbestos. The misidentification of
VAT in the Asbestos Management Plan could also lead to uncontained VAT removals,
improper O&M and possible contamination.
234
-------
SITED
Background
Site Description
The abatement project at this two-story school involved the removal of
approximately 2,100 ft2 of 2-ft by 4-ft lay-in, asbestos-containing, acoustical ceiling
tiles. The abatement area included corridors, classrooms, and offices. The project
specifications indicated that the asbestos content of the ceiling plaster was
approximately 5 to 10 percent amosite. The information regarding the abated ACM
and associated asbestos content was obtained from the asbestos abatement
specifications for this site. ,
Air Monitoring Summary
i
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST. In 1990, air samples
were collected at this school by a modified aggressive sampling technique to simulate
occupied conditions. The samples were collected at approximately the same locations
as those collected in 1988. In 1991 and 1992, air samples were collected during
occupied conditions (i.e., during normal school operating hours) at approximately the
same locations as those collected in 1988 and 1990.
i
Summary of Air Monitoring Results ;
I
Table B-87 summarizes the results from the four sampling efforts. Figure B-15
illustrates the mean airborne asbestos concentrations at Site O. A single-factor
ANOVA was used to compare mean concentrations measured in each of the three
sampling locations. The results of the ANOVA analysis are presented in Table B-88.
The following subsections summarize the pairwise comparisons of the mean
concentrations in the three sampling locations.
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured
clearance phase of the 1988 abatement showed
AHERA initial screening test because the
average
235
by EPA/NJDOH during the AHERA
that this site would have passed the
filter concentration (31 s/mm2) was
-------
TABLE B-87. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Oa
Mean
f-f'- _ _ ''S-fffff f
I/lax ;
Mean
Win
. .Mean '•
Mast
0.004
0.003
0.007
0.003
0.010
0.001
0.004
occupancy- tSS&
0.001
0.005
0.018
0.086
0.001
0.005
Occuipjad conditions- 1391
0.005
0.022
0.001
0.003
Oecuipleci conditions- 1S92
0.002
0.005 0.001
0.003
0.027
0.012
0.047
Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-88. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE O
Sampling period
Statistically significant differences In"
t&¥i afthftrttfi ftfthoclAfe /*rin**ant^ttt}rtWW^
0.1084
0.4478
0.3298
0.0001
A(0.004) P(0.003) 0(0.001)
P(0.018) A(0.001) O(0.001)
AfO.OOS) O(0.001) P(0)
O(0.027) A(0.002) PfO.OOD
a If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b A = 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
d Sampling locations (means) connected by a line are not significantly different.
236
-------
o
o
o
10
o
o
q
6
(0
D.
00
CO
0)
CO
CO
CD
.O
(0
(0
0)
C
d
CD
m
o
o
d
o
o
o
o
o
euuo/s
237
-------
below 70 s/mm2. Furthermore, the site would have passed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. These results are
consistent with AST sampling results.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.004 s/cm3) was not
significantly different from the average concentration measured outdoors (0.001
s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.003 s/cm3) was not
significantly different from the average concentration measured outdoors (0.001
s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.004 s/cm3) was not
significantly different from the average concentration measured in the perimeter areas
(0.003 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.018 s/cm3) was not significantly different from the average outdoor
concentration (0.001 s/cm3).
238
-------
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/crn3) was not significantly different from the
average concentration measured in the perimeter areas (0.018 s/cm3).
i
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.005 s/cbi3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
i
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (6.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0 s/cm3).
Occupied Conditions - 1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.002 s/crn3) was significantly less than the average
concentration measured outdoors (0.027 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.001 s/cm3) was significantly less than the average
concentration measured outdoors (0.027 s/cm3).
239
-------
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.002 s/cm3) was not significantly different from the
average concentration measured in the perimeter areas (0.001 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988, 1990, 1991, and 1992. Each sampling location was evaluated separately.
Table B-89 presents the result of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
TABLE B-89. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE O
-------
individual concentration (0.022 s/cm3) were measured during occupied conditions in
1991, 3 years after abatement.
Perimeter \
The average airborne asbestos concentrations measured in the perimeter area
in 1988,1990, 1991, and 1992 were not significantly different. The highest average
concentrations (0.018 s/cm3) and the highest individual concentrations (0.086 s/cm3)
were measured during simulated occupancy, conditions in 1990, 2 years after the 1988
abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1992 was
significantly greater than the average concentration measured in 1988, 1990, and
1991. Differences in the average concentrations measured in 1988, 1990, 1991 were
not statistically significant. The highest average concentrations (0.027 s/cm3) and the
highest individual concentration (0.047 s/cm3) was measured in 1992.
Structure Morphology and Size Distributions
Table B-90 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 95 asbestos structures, of which 97.9 percent
were chrysotile asbestos and 2.1 percent of which were amphibole asbestos. Overall,
the asbestos structures were primarily fibers (80 percent), and to a lesser extent,
matrices (10.5 percent), clusters (5.3 percent), and bundles (4.2 percent).
Table B-91 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. All of the observed
asbestos structures were less than 5 |im in length.
NJDOH Visual inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site O as part of the State's traditional quality assurance program. This provides a
check and balance to asbestos abatement apd ensures that high-quality abatement
and state-of-the art work practices are used.: The onsite AST collected AHERA
clearance air samples only after the site had| passed the NJDOH visual inspection.
241
-------
o
CO
*
o
_J
o
QL
DC
O
Q
<
LLJ
CL
>•
H-
111
DC
0
ID
DC
CO
8
H
CO
OQ
CO
<
1 1
UL
0
z
o
D
CO
I
5
^«
i
CO
UJ
_J
m
"
/
•v ^
1
5
;|
1
:i
;i$
.- *•
*•
"v,,.,-.
X
J. ..
''*
jfi
1
*"* »G
18
13r
V4l&'
0
-• .W
<£ %
-1*
?
"
"^
--
"
."(•
1
:*
wf
,J
v ^
c-
• l»
] [ I I 1 ] I 1 t '*!
_
-|
:1
•• vA
V^
£
&
(fit'
^sC
.••V
"i
\J
'"o
^
*" si
5,0
2,
-?-w
:---l'
' ^
^^^
"" •.-.
5 "O
^ ^fi
s
^
CO
0
o
CO
CO
CO
fS,
CD
CO
s
CO
0§
eft
^
;
'^ '
^ V,
o
o
o
o
o
o
0
o
§,
,
•• ^ %
"" ?
-
^ ^
•"
o
o
o
o
0
o
o
o
CO
,<
1
si *
:jS S
««
o
in
0
o
s
o
§
§1
o>
.-
'
^ ^
1 >
o
CO
o
CM
0
o
CM
o
0
o
in
$
ca
^
^
s - v,
in
o
T"
T—
CM
0
^f
CO
CD
O
O
O
m
g
o>
^ %
ft
.
1
1
1
1
1
o
T*
%o*
-o*
.•
fe
^ S
w 5
fi* ^!
O
m
o
o
S
o
in
S
CM
'S
.•
f
>'
O
O
o
o
o
o
0
o
^™
i
'"S*
•V >••
\%s
o
o
0
o
o
T~
o
o
o
^^
T—
0
' O>
•• ••
,'
••
o
o
0
o
o
. o
o
o
T"
CM
•tf
o>
' "'
1
1 *
3
o
CM
c\i
o
r^
CO
,_
§
o
o
o
co
$
-o>
3?
"' '
.
' ^
«
1
^
o
TJ
co
CO
CO
£
CO
<5
CO
E
CO
Q.
1
CO
r—
o
£
CO
co
CO
00
O)
T™
CO
&_
CO
1
09
•a
1
8
u
CO
c
1
§•
CO
CO
19
242
-------
o
UJ
CO
H
UJ
DC
-3
§
Si
E
CO
UJ
DC
H^
|
1
«
CO
UJ
CD
CO
U.
O
P«V
O
3
m
E
|H»
CO
s
m
N
CO
Ul
>
••••
«~
2
o
•
9
m
UJ
m
jrf
!«•
I™
l|
: **.
S3
ll
i*
»
S
B
f |k
:i
i
i
: ^**
3
J
£>
;||*
;!C ,
:»
: ^
i v^.
? %
^
• ^*
S
£
o.
1 \
*
«L
?^l
' -%
• '* s
; s«
: °;
• 5.
;|
: T
i S
: \jf|
sv S
> v
sv
S
\^
:
;I
> s'
V2
t5
•K
^1
v
«
' o
o
s*" *
f
. S.
w
0
o
0
o
o
o
T*™
CO
CO
CO
CD
CO
rv
CD
^~
CO
<, ^
•; :
??
-.i'^
\^
>•-. ^s
tli
\-l5S
'J*
ff
^5
g
g
g
Y^
O
0
1
g
.,_
t -
/°
S'i
s.^
^5\ -4-j
^*i
is
ij^S
*i'£
' <
O
o
o
o
o
0
0
o
in
o
in
00
•. •«
i
^T\
\.\:
••'*&••.-,
-tr-l v.
^v-- '
g|
^X^i
i-^r^
r^" \
l^V*
h % .;
O
o
o
o
o
0
1
o
o
o
in
^
V S^
&\
-^1
\v
f ^vi
%•••• :
"s":
V:
••xH
&^ •
s^ :
; ;
O
o
o
o
o
CO
s
§
0
U)
•.
i
^
i!
s\*
0
* ' <
f
o
o
T"
g
o
o
o
o
O5
CO
58
CM
cn
"*"
0
'
%
s S
\- "\
f' ^
£
jfc
s«
i
i
i
t
i
i
O
•*** i
- :
\ \
^
[•.
\',? '
^ f
*'
y
o
o
0
o
o
o
o
o
g
T-
o
in
CM
i
'!
%**•?
j
%X
.. :
g
0
o
o
o
o
o
0
o
o
o
"
.,_
o>
f f
\
V •.
%
"•
^
I
g
1
1
i
o
o
i
o
o
g
I
g
T"
^.
•• :
o i
-
",
^
%
<
T
^%
0
o
o
o
o
0
I
o
o
o
in
CM
i
*\s
A^
(
f
r -^
i ** s
o
o
o
o
g
00
fe
CO
O)
CO
00
CO
"*
I
' " X
.v^.
'
*" ""
g
^
1
T3
ca
CO
CO
co
o
CO
Q.
1
co
*_•
c
CO
CO
to
J3
CO
CO
CO
f
.c
co
0)
>.
CO
I
o
CO
8
s
CO
>
^
CO
15.
E
co
03
8
243
-------
•!=•• r; -|
Two visual inspections were required at this site. The site failed the first visual
inspection because debris was present on overhead pipes, on the grid system
framework for suspended ceiling panels, and in corners of floor-wall intersections.
The contractor was then required to reclean these areas. Once the areas were
recleaned, NJDOH conducted a second visual inspection. The site passed the second
visual inspection.
1991 Visual Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, on October 29, 1991, NJDOH conducted a visual
inspection at Site O as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in October 1991.
1988 Abatement Areas
First Floor Corridor and Stairwell-Minor debris (flakes that tested positive for
chrysotile asbestos) was obtained from the lip of a suspended Nesbitt heater unit
(Table B-92) Other flakes of debris found on a wall tested negative for asbestos.
Fiberglass pipe insulation with cementitious elbows and joints was noted above the
drop ceiling. Debris recovered near an elbow above the drop ceiling at a water
fountain tested positive (6 percent chrysotile, 21 percent amosite asbestos). Another
sample, taken from an elbow, tested negative for asbestos. These materials are not
listed in the Asbestos Management Plan.
Second Floor Corr/cfor-This inspection was limited by heavy fiberglass batting
applied atop the drop ceilings. No debris was found in this area.
1988 Perimeter Areas
Hallway at Gym and Boiler Room-No suspect asbestos-containing thermal
system insulation was found.
Boiler f?oom--Approximately 5 linear feet of corrugated pipe insulation
(22 percent chrysotile asbestos) with damaged friable elbow insulation (4 percent
chrysotile, 4 percent amosite asbestos) was found (Table B-92). This material was
apparently overlooked during abatement.
Pipe Tunnel-Thermal debris (1 percent chrysotile, 4 percent amosite asbestos)
was found at the entry to the tunnel (Table B-92).
244
-------
TABLE B-92. SUMMARY OF BULK SAMPLE RESULTS
1991 INSPECTION
SITEO
Type of
Analyses
1988 Abatement Areas
North stairwell
South stairwell
Corridor 1st level
Corridor 1st level
1988 Perimeter Areas
Boiler room
Boiler room
Pipe tunnel entry
Encapsulated flakes on wall
Residue on Nesbitt heater
Elbow with fiberglass
insulation
Elbow debris at water
fountain
NE corner - corrugated pipe
insulation
N/E corner - elbow
Thermal debris
Negative
Positive3, chrysotile asbestos
Negative
6% chrysotile asbestos
21% amosite asbestos
22% chrysotile asbestos
4% chrysotile asbestos
<1 % amosite asbestos
1% chrysotile asbestos
4% amosite asbestos
a This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
Basement of New Wing-Room 114 and Science Storage have cementitious
elbows associated with fiberglass pipe insulation. These materials do not appear in
the Asbestos Management Plan.
Conclusions
[
A number of asbestos sources were identified in the various areas of the
building. The school's Asbestos Management Plan must be revised to reflect the
presence of these materials.
245
-------
SITEP
Background
Site Description
The abatement project at this three-story school building involved the removal
of trowel-applied, asbestos-containing, acoustical ceiling plaster and mixed-diameter
pipe insulation. The abatement area included corridors, classrooms, and offices. The
project specifications indicated that the abatement involved the removal of
approximately 8500 ft2 of acoustical ceiling plaster containing 91 to 93 percent
chrysotile and approximately 1600 linear feet of mixed-diameter pipe insulation. The
latter included hard-packed pipe insulation (24 percent chrysotile), air-cell-paper pipe
insulation (4 to 10 percent chrysotile), and hard-packed joint insulation (60 percent
chrysotile). The information regarding the abated ACM and associated asbestos
content was obtained from the asbestos abatement specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Preabatement samples
were also collected in the perimeter areas and outdoors before the 1988 abatement
activities. Final clearance of the abatement site was based on samples collected by
the AST. In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988. In 1991 and
1992, air samples were collected at this school during occupied conditions (i.e., during
normal school operating hours) at approximately the same locations as those collected
in 1988 and 1990.
Summary of Air Monitoring Results
Table B-93 summarizes the results of the five sampling efforts. Figure B-16
shows the mean airborne asbestos concentrations at Site P. A single-factor ANOVA
was used to compare mean concentrations measured in each of the three sampling
locations. Table B-94 presents the results of the ANOVA analysis. The following
subsections summarize the pairwise comparisons of the mean concentrations in the
three sampling locations.
246
-------
TABLE B-93. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Pa
< Sean '"
j' .%!'',-?: '..'•'.
Max
Mean
Win
Max
Outsets,
Mean
0.001
0.005
0.005
0.011
0.007
0.018
0.003
0.016
- tsso
0.005
0.025
0.004
0.011
0.001
0.004
Occulted condi«ofls.-t992
0.003
0.010
0.006
0.020
0.009°
0.018
* Samples ware collected each year in the 1988 abatement and perimeter areas and outdoors.
b Abatement area was not accessible for preabatemant sampling.
c N-4.
TABLE B-94. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATlbNS MEASURED AT SITE P
Statlstlcafly sighificanl differences m im&
«lrl>ome
0.3466
0.4285
0.3966
0.0891
0.4714
P(0.001) OKH
P(0.007) A(O.OOS) O(0.003)
AfO.OOS)
O(0)
A(0.004) P(0.001)
O(Q.OQ9) P(0.006)
" If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b A « 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
d Sampling locations (means) connected by a line ar|e not significantly different.
247
-------
q
d
o
o
o
o
o
o
o
o
o
iJJ.J,.,.L.L.,,..i...,..,.,l ,,1J.,).,I..4...L,1......I JZ^
O
d
o
q
d
o
o
o
d
o
o
o
q
d
etuo/s 'uogBJiueouoo sojseqsv eujoqjjv 86BJ9AV
248
CM
a>
O)
0)
o
0)
O)
ID
0
13
J3
OJ
*j
(0
O
a
CO
CO
o
0)
D
(0
CO
CD
E
10
c
CD
O
C
to
o
*J
CO
CD
.Q
(0
cd
0)
c
CD
0
CO
CO
CD
D
D)
E
-------
Preabatement -1988
The average airborne asbestos concentration measured in the perimeter area
before the abatement in 1988 (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (p s/cm3).
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have passed the
AHERA initial screening test because the average filter concentration (30 s/mm2) was
below 70 s/mm2. Furthermore, the site would have passed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. These results are
consistent with AST sampling results. :
Comparison of the Abatement Area With Outdoors
\
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.005 s/cm3) was not
significantly different from the average concentration measured outdoors (0.003
s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.007 s/cm3) was not
significantly different from the average concentration measured outdoors (0.003
s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.005 s/cm3) was not
significantly different from the average concentration measured in the perimeter area
(0.007 s/cm3).
249
-------
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0 s/cm3) was not significantly different from the average outdoor concentration
(0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.004 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
250
-------
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/cpi3) was not significantly different from the
average concentration measured outdoors (0.009 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.006 s/cm3) was not significantly different from the
average concentration measured outdoors (0.009 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.003 s/cfn3) was not significantly different from the
average concentration measured in the perimeter area (0.006 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
i
A single-factor ANOVA was used to compare mean concentrations measured in
1988, 1990,1991, and 1992. Each sampling location was evaluated separately.
Table B-95 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subseptions following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992. ;
1988 Abatement Area
Differences between average airborne asbestos concentrations measured
during occupied conditions in 1988, 1990, 1991, and 1992 were not statistically
significant. The highest average concentrations (0.005 s/cm3) were measured in 1988
and 1990, and the highest individual concentration (0.025 s/cm3) was measured during
simulated occupancy in 1990, 2 years after abatement.
i
Perimeter
i
The average airborne asbestos concentrations measured in the perimeter area
in 1988,1990, 1991, and 1992 were not significantly different. The highest average
concentration (0.007 s/cm3) was measured during the AHERA clearance phase of the
1988 abatement, and the highest individual concentration (0.020 s/cm3) was measured
during occupied conditions in 1992, four years after the 1988 abatement.
251
-------
TABLE B-95. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990,1991, AND 1992 AT SITE P
\ ,r$ar8:piing
,- - % ^location;* -
Abaietts&iji area
v.y, •> f'-~- >"••• f "~ ff
FeriBieferarea''" -
^outdoaitt ss " 71
--ANOVA
'fj»vaiBefe'
0.9024
0.0856
0.0088
Stai isireaR? *f pif lean*
-------
Q.
P
CO
§
i
Q.
CC
§
Q
<
HI
O.
UJ
CC
I
m
s
LL
O
Q
l-
m
DC
to
UJ
m
m
i
1
JZ
&
&
E"
SI
o
10
CD
CO
CO
CO
CO
CM
CO
to
in
CO
CO
cb
U)
CM
LO
CM
O
en
cd
CO
o>
in
CM
CO
o
o
01
CM
CO
i
I,
CD
£
CD
CO
Q.
T3
CD
CO
I
CD
*••
_c
CD
I
1
JOJ
8
CD
i
i-
ca
CO
253
-------
Table B-97 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 98.4 percent
of the observed asbestos structures were less than 5 |im in length. Of the 45
asbestos fibers observed, only 1 (2.2 percent) was greater than 5 ^m in length.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site P as part of the State's traditional quality assurance program, which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state»of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Three visual inspections were required at this site. The site failed the first
visual inspection because of the presence of debris on pipes, in openings where the
pipes penetrated the walls, on electrical fixtures and wires, in door jambs, at ceiling-
wall junctions, on walls, inside a fireplace and chimney, and in a sink used for disposal
of asbestos-contaminated wastewater. The contractor was then required to reclean
these areas. After the areas were recleaned, NJDOH conducted a second visual
inspection. The site failed the second visual inspection because of debris found
behind the fireplace, at ceiling-wall junctions, and on floors and residual slurry found
on walls and underneath stairs. After these areas were recleaned, NJDOH conducted
a third visual inspection which the site passed.
1991 Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, NJDOH conducted a visual inspection at Site P on
November 5, 1991 as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in November 1991.
1988 Abatement Areas
Kindergarten ffoom-Unencapsulated residual ceiling material was noted on the
top of the windows and exterior aluminum wall columns (Table B-98). Encapsulated
and painted material was noted at the ceiling and wall junctions. Approximately
35 linear feet of corrugated pipe insulation was found in the space above the lavatory
and the closet storage area. These pipes do not appear in the Asbestos Management
Plan.
254
-------
0.
Ul
s
DC
CO
CO
UJ
DC
O
CO
I
CO
Ul
m
CO
z
o
m
E
CO
1
o
CD
UJ
-J
CD
f
i
CO
CO
in
10
o?
o
0
0
o
o
o
o
o
0
o
o
o
o
0
CO
CO
CO
CO
CO
CO
o
o
o
o
o
o
O
0
CO
CM*
O)
CO
en
CM
CO
cb
II
CM
% ^
ff ^ -JW( "*
-S '\' '
CO
CO
i
CO
8.
1
1
CD
CO
CO
o>
^»
CO
CD
£.
I
8
QJ
CO
0)
co
CO
255
-------
TABLE B-98. SUMMARY OF BULK SAMPLE RESULTS - SITE P
,1991 INSPECTOR
Lotion
Type of Material
1988 Abatement Area
Kindergarten (KDGA)
KDGA
KDGA
SW Stairwell
1988 Perimeter Areas
2nd Floor classroom
Spray-on residue at top of
windows
Dust inside radiator
Painted over residue on wall
at ceiling and wall junctions
Floor tile debris under
radiator
Dust inside radiator
Positive3 for chrysotile
asbestos
Negative
Positive for chrysotile
asbestos
8% Chrysotile asbestos
Negative
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
First Floor Corridor, 1965 Wing-Pipe insulation was observed in the plenum
above the hallway through a new penetration. Intercom-type wire had recently been
run on top of this insulation. This material does not appear in the Asbestos
Management Plan.
Classroom No. 2~From a closet overhead area, pipe insulation was noted to be
running through vertical shafts along the exterior wall. Pipe insulation was also visible
above the corridor ceilings. These materials do not appear in the Asbestos
Management Plan.
1988 Perimeter Areas
1st Floor Corridor, Old W/?g~Thermal system insulation was noted in the
plenum above the hallway. This material is listed in the Asbestos Management Plan.
Foyer Chase-Jhe floor under the entry foyer contains thermal system insulation
that is not listed in the Asbestos Management Plan.
256
-------
Girls Lavatory, 1st F/oor-lnaccessible thermal systems insulation was
observed. The Asbestos Management Plan does not list these remaining materials.
Boiler floom-Packing and lag were noted around the caps on top of the boilers
and are not included in the Asbestos Management Plan.
Pump Room-Debris was noted at the entrance to the pipe tunnels.
Conclusions
TSI was present in the 1988 abatement and perimeter areas, but not listed in
the Management Plan and the potential for disturbance exists. Residual materials are
located above the suspended ceiling and as such, would not be disturbed during
subsequent air sampling.
257
-------
SITE Q
Background
Site Description
During the summer of 1988, two asbestos abatement projects were conducted
at this school (Sites B and Q). Spray-applied acoustical ceiling plaster was removed
from the second floor (Site B) and from the first floor (Site Q). The abatement areas
at both sites included corridors, classrooms, and offices. The ceiling plaster contained
approximately 2 to 6 percent chrysotile asbestos. The information regarding the
abated ACM and associated asbestos content was obtained from the asbestos
abatement specifications for this site. No additional abatement activity has occurred
since 1988.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area, but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Preabatement samples
were also collected in the perimeter area and outdoors before the 1988 abatement
activities. Final clearance of the abatement site was based on the samples collected
by the AST. In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988. In 1991 and
1992, air samples were collected at this school during occupied conditions (i.e., during
normal school operating hours) at approximately the same locations as those collected
in 1988 and 1990.
Summary of Air Monitoring Results
Table B-99 summarizes the results from 1988, 1990, 1991, and 1992. Figure
B-17 shows the mean airborne asbestos concentrations at Site Q. A single-factor
ANOVA was used to compare mean concentrations measured in each of the three
sampling locations. The results of the ANOVA analysis are presented in Table B-100.
The following subsections summarize the pairwise comparisons of the mean
concentrations in the three sampling locations.
258
-------
TABLE B-99. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Qa
Max
"Jala*
0.001
0.004
0.099
0.029
0.157
0.055
0.115
0.007
0.021
0.019
0.040
0.010
0.040
0.001
0.005
0.009
0.018
0.012
0.004
0.024
0.001
0.004
0.053 0.025 0.104 0.438 0.142 1.02
0.001
0.003
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b Perimeter and Outdoor samples are the same as those collected at Site B in 1990, 1991, and 1992 (Site Q was
the second abatement project at this school in 1988).
c Abatement area was not accessible for preabatement sampling.
TABLE B-100. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE Q
•. atrbome asbestos ^6ncen|ralion
v ,
pccupfed conditIoosrif92: v;
0.3466
0.0095
0.0907
0.0059
0.0001
P(0.001) CXO)
P(0.055) O(0.007)
A(0.019) P(0.010) O(0.001)
P(0.012) A(0.009) O(0.001)
P(0.438) A(0.053) O(0.001)
* If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b A s 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location. l
d Sampling locations (means) connected by a line are not significantly different.
259
-------
o
d
o
o
O
o
o
(C
0
(d
o
•• %V*-SS ^ 's ^ \-- s ^^%s^-.-A ^ •S.'*'"
CM
en
o
O)
O)
o
01
0)
oo
oo
0)
o
0)
-a
CD
CO
CD
E
CO
o
ts
o
c
o
o
CO
o
+->
CO
CD
1
CD
c
o
.Q
'co
CD
D)
0
I
CO
CD
D
O)
o
6
o
o
o
o
o
8iuo/s '
soiseqsv
96BJ8AV
260
-------
Preabatement - 1988
The average airborne asbestos concentration measured in the perimeter area
before the abatement (0.001 s/cm3) was not significantly different from the average
concentration measured outdoors (0 s/cm3).
Postabatement -1988
\
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have failed the
AHERA initial screening test because the average filter concentration (648 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA 2-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. Although the site
ultimately passed AHERA clearance by using the AST sampling results, the
EPA/NJDOH results clearly show that elevated levels of airborne asbestos still existed
in the school in 1988.
Comparison of the Abatement Area With Outdoors
. i
The average airborne asbestos concentration measured in the abatement area •
during the AHERA clearance phase of the abatement in 1988 (0.099 s/cm3) was
significantly greater than the average concentration measured outdoors (0.007 s/crn3).
This result is consistent with the AHERA Z-test comparison reported previously.
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0.055 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.007 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.099 s/cm3) was not
significantly different from the average concentration measured in the perimeter area
(0.055 s/cm3).
261
-------
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the previously
abated area 2 years after the 1988 abatement (0.019 s/cm3) was not significantly
different from the average concentration measured outdoors (0.001 s/cm3).
Comparison of the Perimeter Areas With Outdoors
The average airborne asbestos concentration measured in the perimeter area 2
years after the 1988 abatement (0.010 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area ,
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.019 s/cm3) was not significantly different from the
average airborne asbestos concentration measured in the perimeter area
(0.010 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.009 s/cm3) was significantly greater than the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Perimeter Areas With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.012 s/cm3) was significantly greater than the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.009 s/cm3) was not significantly different from the
average airborne asbestos concentration measured in the perimeter area
(0.012 s/cm3).
262
-------
Occupied Conditions - 1992
Comparison of the Previously Abated Area With Outdoors
i
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.053 s/cm3) was significantly greater than the
average concentration measured outdoors (6.001 s/cm3).
Comparison of the Perimeter Areas With Outdoors
f
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.438 s/cm3) was significantly greater than the
average outdoor concentration of airborne asbestos (0.001 s/cm3). The unusually high
average level in the perimeter areas is due primarily to one sample (1.02 s/cm3); the
other four samples ranged from 0.014 to 0.038 s/cm3.
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.053 s/cm3) was significantly less than the average
airborne asbestos concentration measured in the perimeter area (0.438 s/cm3). The
unusually high average level in the perimeter area is due primarily to one sample
(1.02 s/cm3); the other four samples ranged [from 0.014 to 0.038 s/cm3.
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990, 1991, and 1992. Each sampling location was evaluated separately.
Table B-101 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
1988 Abatement Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the 1988 abatement (0.099 s/cm3) was
significantly greater than the average concentrations measured during simulated
occupancy in 1990 (0.019 s/cm3) and during occupied conditions in 1991
(0.009 s/cm3), but not significantly different from the average concentration measured
during occupied conditions in 1992 (0.053 s/cm3). Furthermore, the average
concentration measured during occupied conditions in 1992 was significantly higher
than the average concentration measured in 1991. Other differences between
average concentrations were not statistically, significant. The highest average
263
-------
concentration (0.099 s/cm3) and the highest individual concentration (0.157 s/cm3)
were measured during the AHERA clearance phase of the 1988 abatement.
TABLE B-101. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE Q
Statisiicaiiy significam differences IB mean airborne
— —^ asbestos coneealraflon^ -- "-* - ,t"•
area
0.0019
0.0002
0.1871
1988(0.099) 1992(0.053) 1990(0.019) 1991(0.009)
1992(0.438) 1988(0.055) 1991(0.012) 1990(0.010)
1988(0.007) 1990(0.001) 1991(0.001) 1992(0.001)
a Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pain/vise differences between sampling locations.
c Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
Perimeter Area
The average airborne asbestos concentrations measured in the perimeter area
in 1992, 4 years after the 1988 abatement (0.438 s/cm3), was significantly higher than
the average levels measured in 1988,1990, and 1991. The differences between the
average levels in 1988, 1990, and 1991 were not statistically significant. The highest
average concentration (0.438 s/cm3) and the highest individual concentration (1.02
s/cm3) were measured in 1992 4 years after the 1988 abatement.
Outdoors
Differences in average airborne asbestos concentration measured outdoors in
each of the 4 years were not statistically significant. The highest individual
concentration (0.021 s/cm3) was measured in 1988 during the AHERA clearance
phase of the abatement.
264
-------
Structure Morphology and Size Distributions
Table B-102 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 889 asbestos structures, of which 99.7 percent
were chrysotile asbestos and 0.3 percent were amphibole. Overall, the asbestos
structures were primarily fibers (92.2 percent), and to a lesser extent, matrices (5.4
percent), clusters (1.5 percent), and bundles (0.9 percent).
!
Table B-103 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 98.7 percent
of the observed asbestos structures were less than 5 jim in length. Of the 820
asbestos fibers observed, only 4 fibers (0.5 percent) were greater than 5 urn in length.
Followup Air Monitoring - August 1991
Although the average airborne asbestos concentration in the previously abated
area and the perimeter area in May 1991 did not exceed 0.02 s/cm3, EPA/NJDOH
conducted followup monitoring on August 13,1991, under simulated occupancy
conditions because the average airborne asbestos concentration in the previously
abated area from another abatement project at this school (Site B) did exceed
0.02 s/cm3. The August 13 results showed that the average airborne asbestos
concentration in the previously abated area and perimeter area of Site Q were below
0.02 s/cm3; therefore, no further monitoring activity was required.
Followup Air Monitoring - August 1992
Because the average airborne asbestos concentrations in the previously abated
area (0.053 s/cm3) and the perimeter area (0.438 s/cm3), EPA/NJDOH conducted
followup monitoring in July 1992 under simulated occupancy conditions to determine
whether airborne asbestos concentration were still present at the levels observed in
May 1992. The average airborne asbestos concentration measured in the perimeter
area in July (0.006 s/cm3) was below 0.02 s/cm3; therefore, no further action was
required in this area. The NJDOH did, however, require a response action in the
previously abated area at this school, based on the May 1992 data. The school
subsequently employed a licensed asbestosrabatement contractor to clean the
previously abated area. When the cleaning fiction was complete, NJDOH conducted
followup air monitoring in August 1992 to determine the residual levels of airborne
asbestos. The average airborne asbestos concentration measured in August
(0.009 s/cm3) was below 0.02 s/cm3; therefore, no further monitoring activity was
required at this school.
265
-------
O
UJ
t-
co
o
o
_l
0
X
o.
DC
O
5
0
z
^^
UJ
CLa
^M
|—
UJ
cc
I
o
3
OS STR
i—
CO
UJ
m
CO
u.
o
z
o
m
E
Q
CM
o
CQ
TABLE
: -
•. ,
' % %
'••
I -f
i
} .35
'^J
'jy
' M
$&'
(if
/ >
•*•.• •*
•• *•
, --
..v.-
i
> ••
1
JEfr
. lg)
f9
S1S
B>
is*.
"
t«!
^
''^
,:'^
.j
-^
s
« «
,>
'I
•">ji
•• w
%>'3
•.^*'
' ^
••S*
^*
i^
f "^^
•««•
^ A-
,„
^S
o
.Q
a.
£s
%^*C
iS
•
%
••%iH*
§
" '
;«
5 o
«
•nnn^
:j
^ ^^^
II
'
in
in
!^
o
00
s
00
o
CM
§
S
ov
"
r
00
in
o
CO
in
cn
S
in
0
T"
in
en
00
^
1'
^^
^^
o
o
CO
CM
en
o
o
0
CO
T-
e»
en
v,t, 2
«
^i
r_
o
^.
CO
cn
in
cn
0
0
o
en
i
»
.
:
': %
2s
S
CM
«.
cn
o
^
$
o
o
o
E
:1
""•-
%s
o
o
o
o
o
o
o
0
0
i
CO
0
o
CM
§
o
0
o
£
I
:
fl
"
o
o
00
o
CM
cn
O)
o
o
o
CO
in
i
f
in
o
o
in
CM*
CO
o
o
o
00
£
*
o
0
0
o
0
o
o
o
T-
i
-,>,,,"„
o
o
o
0
o
o
o
o
eb
en
|:
£«k
O
o
o
o
o
o
8
"
1^
>-^>,,
E
CO
CO
CO
T3
1
"Jo
CO
3
a
CD
W"
CM
cn
cn
2^j
p"
O CO
^ .--
•s en
o °2
^^
C 0
ca en
eo 2
CO ^
CD £
m " ;
™ CO
CD £
IT* ffl
CQ
-------
111
Q
UI
DC
1
HI
S
(0
Ul
DC
I
CO
I
HI
ffi
<
U.
o
o
F
m
cc
LU
N
(0
UJ
i
O
w
o
CD
Ul
m
i
Of
I
If 31
'I
;
si
cv
at
CO
00
en
* '^/ c A>v-. •>
C5>
8
O7
CO
CO
in
CO
o
to
co
CD
$
O
w,
CM
50 1
o co
I S
O °>
CO
CO
s>
co
32
CD
I
§
I
s
8
s
i
CO
CD
CO
CO
o
en
en
CD
O
to
•o
€
CD
| 8
C CD
I S
o> :
00 (D
? I
*^ CO
CD O
£ 5
'H £
g «
>» K
18
o ~
O o
11
o S
"2 co
QJ to
its
•— .92,
£ Q.
267
-------
NJDOH Visual Inspections
1
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site Q as part of the State's traditional quality assurance program, which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Four visual inspections were required at this site. The site failed the first visual
inspection because of the presence of debris on the tops of storage closets and on
structural beams. The contractor was then required to reclean these areas. After the
areas were recleaned, NJDOH conducted a second visual inspection. The site failed
the second visual inspection because of debris in openings at wall penetrations and on
several light fixtures. The contractor was again required to reclean the affected areas.
After the areas were recleaned, NJDOH conducted a third visual inspection. The site
failed the third visual inspection because of debris at wall-ceiling junctions, in door
jambs, and in corners of window sills. After these areas were recleaned, NJDOH
conducted a fourth visual inspection. The site passed the fourth visual inspection with
the stipulation that the overhead area be sprayed with encapsulant.
Background for 1991 and 1992 Inspections
On August 14,1991, and July 16,1992, NJDOH conducted a visual inspection
at Sites B and Q to determine potential sources of airborne asbestos measured by
EPA and NJDOH in May 1991. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in August 1991 and July 1992.
1991 Inspection
1988 Abatement Areas
Two samples of overspray and debris were collected from the structural steel
and closet overhead areas in the first-floor classrooms (Table B-104); one sample of
spray-on debris tested positive for chrysotile asbestos, and a sample of sandy debris
from an air shaft tested negative for asbestos.
268
-------
TABLE B-104. SUMMARY OF BULK SAMPLE RESULTS-SITE Q
1991 INSPECTION
Type of material
Analyses
1988 Abatement Area
1st floor classroom
1st floor classroom, air
shaft ledge
1988 Perimeter Areas
Basement all-purpose
room
Flakes of spray-on debris
Flakes of spray-on debris
Positive, chrysotile
asbestos
Negative
Composite, ceiling sample
Negative
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
1988 Perimeter Areas
In the basement all-purpose room, thermal system insulation (TSI) not identified
in the Asbestos Management Plan was observed in the ceiling overhead spaces in the
corridor, kitchen, and storage closet. This material appeared to be in generally good
condition.
Conclusions
Incomplete assessment and abatement failed to account for overspray in the
ceiling overhead spaces and the closet recessions. These asbestos-containing
materials could have contributed to the elevated airborne asbestos levels measured in
May 1991.
269
-------
1992 Inspection
v*- .,-
1988 Abatement Area f
First-Floor Classrooms-\n 1991, the NJDOH inspectors found residual spray-
applied asbestos-containing material on the black iron trusses above the ceilings and
ventilation panels in closets of the classrooms. Samples of this material showed it to
contain asbestos (Table B-105). The black iron trusses support the wire lathe, scratch
coat, and acoustical plaster layers that make up the ceiling system in each classroom.
The ceilings of the closets consist of wood paneling and a metal ventilation panel.
The flakes of asbestos-containing acoustical plaster on the trusses appeared to be the
result of overspraying the scratch coat, which took place before the storage closets
were installed. Overspray material was also observed on the trusses above the light
fixtures, where holes for electrical connections or for mounting the fixtures were open
during the spray application of the acoustical plaster.
The presence of oversprayed acoustical plaster on the trusses in the closets
could not be verified during the July 16, 1992, visual inspection because the ceiling in
the closets had been reinstalled and the ventilation panels were inaccessible because
of stored books and other materials in the closets.
1988 Perimeter Areas
Basement All-Purpose Room-lr\ the soffit in the all-purpose room (which is
accessible through access panels in the ceiling), some air-cell-paper pipe insulation
and cementitious elbows/fittings were noted. The fibrous-glass lines and cementitious
fittings appeared to be in good condition; however, the air-cell-paper insulation had
opened (unsealed) seams and had delaminated in a couple of areas. These materials
were not identified in the Asbestos Management Plan.
Kftc/)e/7--Extensive deposits of extremely friable, white, powdery material were
found inside the kitchen along the base of the exterior wall below the radiators. These
deposits are believed to be caused by efflorescence of the concrete-masonry block
and/or mortar. The white powdery material tested positive for asbestos (Table B-105).
The flooring in the kitchen was 9 in. x 9 in. asbestos-containing (15 percent chrysotile)
resilient floor tile (Table B-105). Two 15 in. by 15 in. transite hot plates were present
on the grill.
Boiler Room-As shown in Table B-105, the following asbestos-containing
materials were noted in the kitchen: 1) mud used to seal the boiler segments, 2) a
cementitious pipe elbow debris behind the hot water tank, 3) spray-on ceiling debris in
the cavity of concrete-masonry wall at the make-up air feed for the boiler, and 4) tan
paint from the boiler stack. These materials were not identified in the Asbestos
Management Plan.
270
-------
TABLE B-105. SUMMARY OF BULK SAMPLE RESULTS - SITE Q
1992 INSPECTION
1988 Abatement Area
1st Floor S/E classroom above closet
1st Floor S/E classroom above closet
1988 Perimeter Areas
Kitchen, floor at South wall
Kitchen, wood sink
Kitchen, south wall
Kitchen, South wall on floor
Kitchen, South wall surface
Kitchen, South wall
Kitchen, South wall
Kitchen by storage room
Kitchen by storage room
Bingo hall
Bingo haS, East wall
Bingo hail, N/E comer
Bingo hall, girls room
Bingo hall, girls room
Boiler room
Boiler room
Boiler room, beam
Boiler room, ceiling pipe entry
Boiler room, air entry
Boiler room, chimney
Boiler room, beam
Boiler room, floor
Boiler room
Construction block
t
Mortar
I
White powder
White cement spray
Blue paint/white undercoat
White efflorescence
White efflorescence
Mortar, gray cement
Concrete-masonry block
Vinyl floor tile, grey 9" x 9"
Mortar from floor trap
Floor paint, grey
Glue paint with yellow and green
Concrete-masonry block
Paint
Soft debris in floor drain
Boiler segment mud
Boiler, fiber, rock wood
Plaster/granular cement
Overspray, soft granular
--
Spray-on debris
Paint, tan
Paint and plaster
Elbow debris, hot-water heater
Mortar debris on pipe
Negative
Negative
Positive8, chrysotile asbestos
Positive, chrysotile asbestos
Positive chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile, asbestos
Negative
2% chrysotile asbestos
15% chrysotile asbestos
Negative
Negative
1% chrysotile asbestos
Negative
Negative
Negative
30% chrysotile asbestos
Negative
Negative
Trace", chrysotile asbestos
2% chrysotile asbestos
Positive, chrysotile asbestos
Trace, chrysotile asbestos
2% chrysotile asbestos
Negative
This classification was defined by the NJDOH laboratory to accommodate samples for which inadequate material was
available to allow a full quantitative evaluation, but were of sufficient size to determine that asbestos was present and to
determine tha specific type of asbestos. Based on the professional judgment of the analyst, the sample is considered to
contain greater than 1% asbestos.
Trace = <1 percent asbestos. i
271
-------
Conclusions
Several asbestos sources were identified that could have contributed to the
elevated asbestos levels measured in 1992 (and 1991). Elevated levels in the
classrooms and hallways could have been caused by disturbance of asbestos-
containing dust and/or friable asbestos-containing acoustical plaster overspray on the
steel trusses above the ceilings and vents in the classroom storage closets. Wind
could caused air to flow from the roof vents through the ducts in this passive
ventilation system and into the classrooms and hallways.
The elevated asbestos levels in the kitchen may be due to the extensive
deposits of extremely friable, white, powdery material caused by efflorescence of the
concrete-masonry block and/or mortar. Other possible contributory sources are the
transite plates and asbestos-containing resilient floor tile.
272
-------
SITER
Background
Site Description
The abatement project at this four-story school building involved the removal of
approximately 2900 linear feet of asbestos-containing thermal insulation, including
mixed-diameter air-cell-paper pipe insulation and hard-packed fitting insulation. The
abatement area included corridors, classrooms, offices, storage rooms, stairwells, and
recreational rooms. The project specifications indicated that the asbestos content of
the thermal surface insulation was approximately 10 to 25 percent chrysotile. The
information regarding the abated ACM and associated asbestos content was obtained
from the asbestos abatement specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples Were collected in the abatement area,
perimeter area (outside the abatement area, but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Final clearance of the
abatement site was based on the samples collected by the AST. In 1990, air samples
were collected at this school by use of a modified aggressive sampling technique to
simulate occupied conditions. The samples were collected at approximately the same
locations as those collected in 1988. In 1991 and 1992, air samples were collected at
this school during occupied conditions (i.e., during normal school operating hours) at
approximately the same locations as those collected in 1988 and 1990.
Summary of Air Monitoring Results
Table B-106 summarizes the results from the four sampling efforts. Figure
B-18 shows the mean airborne asbestos concentrations at Site R. A single-factor
ANOVA was used to compare mean concentrations measured in each of the three
sampling locations. The results of the ANOVA analysis are presented in Table B-107.
The following subsections summarize the pairwise comparisons of the mean
concentrations in the three sampling locations.
Postabatement-1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have passed the
273
-------
TABLE B-106. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(S/cm3) MEASURED AT SITE R
Win
Otrtstows
Mean
""IX
Max
0.002
0.008
0.011
0.027
0.013
0.038
0.005
0.010
0.001
0.004
0.004
0.012
J 0.001 0 0.005 0.003
0.008 0.004
0.006
Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
TABLE B-107. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE R
Statistically significant differences in mean
0.3966
0.0237
0.3899
0.2505
A(0.002) P(0) OfO)
A(0)
O(0.013) PI 0.011)
A(0.005) O(0.004)
OfO.004) P(0.003) A(0.001)
a If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
b A = 1988 Abatement area; P = 1988 Perimeter area; O = Outdoors
Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
d Sampling locations (means) connected by a line are not significantly different.
274
-------
o
6
o
o
ELUO/S 'UO!1EJ}U80UOQ S01S8QSV
9BBJ8AV •
o
o
o
ci
0)
CD
CO
o
CO
CO
00
00
0)
CC
0
•i-j
CO
0
3
CO
0
E
-------
AHERA initial screening test because the average filter concentration (11 s/mm2) was
below 70 s/mm2. Furthermore, the site would have passed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. These results are
consistent with AST sampling results.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.002 s/cm3) was not
significantly different from the average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the abatement in 1988 (0 s/cm3) was not
significantly different from the average concentration measured outdoors (0 s/cm3).
i
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.002 s/cm3) was not
significantly different from the average concentration measured in the perimeter area
(0 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured outdoors (0.013 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.011 s/cm3) was not significantly different from the average outdoor
concentration (0.013 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured in the perimeter area (0.011 s/cm3).
276
-------
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.005 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
i
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured outdoors (0.004 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.003 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990,1991, and 1992. Each sampling location was evaluated separately.
277
-------
Table B-108 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990, 1991, and
1992.
TABLE B-108. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE R
'-* - location!
ITJT-.--TM. .-•". y -.-.-..- •_-[.-_-, .- •-_-_-.----•-
Statistically significant differences in mean airborne
Afe?tteH»ent area
putdbora -f
\-.-.-" "•
•f "• s AffffSp. •y.'.v. j
0.0636
0.0173
0.0391
1991(0.005) 1988(0.002) 1992(0.001) 1990(0)
1990(0.011) 1992(0.003) 1991(0.001) 1988(0)
1990(0.013) 1991(0.004) 1992(0.004) 1988(0)
a Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cnf) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
1.988 Abatement Area
Differences between average airborne asbestos concentrations measured
during occupied conditions in 1988, 1990, 1991, and 1992 were not statistically
significant. The highest average concentration (0.005 s/cm3) and the highest
individual concentration (0.010 s/cm3) were measured during occupied conditions in
1991,, 3 years after abatement.
Perimeter
The average airborne asbestos concentrations measured in the perimeter area
during simulated occupancy in 1990 was significantly greater than the average
concentration measured during the AHERA clearance phase of the 1988 abatement.
Other differences between average concentrations measured in 1988, 1990,1991,
and 1992 were not statistically significant. The highest average concentrations
278
-------
(0.011 s/cm3) and the highest individual concentration (0.027 s/cm3) were measured
during simulated occupancy in 1990, 2 years after the 1988 abatement.
Outdoors
The average airborne asbestos concentrations measured outdoors in 1990 was
significantly greater than the average concentration measured during the AHERA
clearance phase of the 1988 abatement. Other differences between average
concentrations measured in 1988,1990,1991, and 1992 were not statistically
significant. The highest average concentration (0.013 s/cm3) and the highest
individual concentration (0.038 s/cm3) were measured in 1990, two years after the
1988 abatement.
Structure Morphology and Size Distributions
Table B-109 presents the distribution of structure type and morphology at each
sampling location for each year of monitoring. The TEM analysis of 20 samples
collected in the abated area, 20 collected in the perimeter area, and 20 collected
outdoors yielded a total of 54 asbestos structures, all of which were chrysotile
asbestos. Overall, the asbestos structures were primarily fibers (75.9 percent), and to
a lesser extent, matrices (16.7 percent), clusters (3.7 percent), and bundles (3.7
percent).
Table B-110 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 96.3 percent
of the observed asbestos structures were less than 5 urn in length. Of the 41
asbestos fibers observed, only 2 (4.9 percent) were greater than 5 urn in length.
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site R as part of the State's traditional quality assurance program, which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
i
Seven visual inspections were required at this site. The site failed the first
visual inspection because of the presence of debris on top of ventilation ducts, in wall
penetrations, on horizontal surfaces, and on pipes, pipe fittings, elbows, and joints
throughout the entire containment area. Pipe insulation was also present on counters
and floor coverings. The contractor was required to reclean these areas.
279
-------
DC
t
CO
O
O
DC
O
111
I
III
K
ffi
u.
O
O
Z>
ffl
1
5
O)
o
ffi
'fe
'
£ §
&•!
CM
CM
CO
CO
CO
CO
CO
CO
(6
00
CO
00
O
O
0
to
CO
CO
to
CO
CO
CO
CO
s
O
O
O
O
O
O
CM
CM
CO
CM
CO
CD
ot
-o
at
i
i
2
8
T3
TJ
(0
co
TO
2
CO
I
•I
0)
Q.
T3
CO
CO
CD
CO
CO
CO
280
-------
S
""•O
0
o
o
0
o
0
o
o
o
o
0
o
o
o
o
o
0
o
CM
CM
I
o
o
0
o
o
o
O)
o
en
en
o
en
o
o
o
o
o
o
o
CM
CO
CO
CO
N.
CD
CO
CO
CO
CO
CO
en
to
CO
O
O
CD
o
o
CM
(O
CO
S
CO
S
CO
CO
CO
CO
CO
CO
CO
CO
CO
CO
I
5 J
e
o
1
o
CO
CO-
i
(0
&
TJ
H
i
«
en
i
c
8
0)
_o>
8
p
to
-------
After these areas were recleaned, NJDOH conducted a second visual
inspection. The site failed the second visual inspection because of gross debris on
ventilation ducts, pipes, pipe hangers, elbows, joints, conduit, and other horizontal
surfaces. Residual debris was also found in wall penetrations throughout the
containment area. After these areas were recleaned by the contractor, NJDOH
conducted a third visual inspection. The site failed the third visual inspection because
of debris in wall penetrations and on horizontal surfaces throughout the entire
containment area. After these areas were recleaned, NJDOH conducted a fourth
visual inspection. The site failed the fourth visual inspection because of debris behind
lockers, on pipes, on pipe joints and elbows, on tops of ventilation ducts, and on other
horizontal surfaces throughout the entire containment area. After these areas were
recleaned, NJDOH conducted a fifth visual inspection. The site failed the fifth visual
inspection because of debris on pipes, pipe elbows, and joints; on student lockers;
behind counters; and on the floor. After these areas were .recleaned by the contractor,
NJDOH conducted a sixth visual inspection. The site failed the sixth visual inspection
because of debris on ventilation ducts and fans, on floors, on pipe elbows, and on
other horizontal surfaces. After these areas were recleaned by the contractor, NJDOH
conducted a seventh visual inspection, which the site passed.
1991 Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, on November 7, 1991, a NJDOH Visual Inspection
was conducted at Site R as a follow-up. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in November 1991.
1988 Abatement Areas
Corridors and Classrooms--JS\ residue (positive for chrysotile asbestos) was
collected in the Home Economics Room (Table B-111). Other such residue were
noted in the basement corridors. All abatement areas could not be assessed because
of the extensive construction activity in the abatement area classrooms. All of the
areas examined were coated with an encapsulant.
1988 Perimeter Areas
Central Basement S/70ps-No debris or material was identified.
Ramp to the Kitchen-Damaged thermal system insulation was found behind a
large grille in a wall recession that opens to the abatement area corridor. These
materials do not appear in the Asbestos Management Plan.
282
-------
TABLE B-111. SUMMARY OF BULK RESULTS - SITE R 1991 INSPECTION
I v- to^tloh^^
| Home Economics Room
£ ~$W&<& ftfatariat - -
Debris on pipe riser
""*''- Analyses , , , ' ,
Positive3, chrysotile asbestos
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
Kitchen ^Areas-Thermal system insulation was noted above the suspended
ceiling system.
Conclusions
TSI debris was present on a pipe riser in the 1988 abatement area. Damaged
TSI was present in the 1988 perimeter areas. This TSI did not appear in the
Management Plan and were minor in nature.
have contributed to the acceptable air levels
The heavy use of encapsulants may
of asbestos.
283
-------
SITES
Background
Site Description
The abatement project at this two-story school building involved the removal of
approximately 7200 ft2 of trowel-applied, asbestos-containing acoustical ceiling plaster.
The abatement area included a gymnasium and stage, corridors, and storage areas.
The project specifications indicated that the asbestos content of the acoustical ceiling
plaster was approximately 10 to 20 percent chrysotile. The information regarding the
abated ACM and associated asbestos content was obtained from the asbestos
abatement specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area, but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Preabatement samples
were also collected in the perimeter area and outdoors before the 1988 abatement
activities. Final clearance of the abatement site was based on samples collected by
the AST. In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988. In 1991 and
1992, air samples were collected during occupied conditions (i.e., during normal
school operating hours) at approximately the same locations as those collected in
1988 and 1990.
Summary of Air Monitoring Results
Table B-112 summarizes the results of the five sampling efforts. Figure B-19
shows the mean airborne asbestos concentrations at Site S. A single-factor ANOVA
was used to compare mean concentrations measured in each of the three sampling
locations. Table B-113 presents the results of the ANOVA analysis. The following
subsections summarize the pairwise comparisons of the mean concentrations in the
three sampling locations.
Preabatement -1988
The average airborne asbestos concentration measured in the perimeter area
before the abatement in 1988 (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
284
-------
TABLE B-112. SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE Sa
Sampling
Wit
IfoK
MB**
Owttioors- ' " ' ';' "'
Min
0.001
0.005
0.001
0.005
0.012
0.028
0.003
0.008
, •, ss
Slmtfteted wcopunpy.-
0.003
0.014
0.001
0.005
0.001
0.004
0.003
0.011
0.001
0.004
1982
0.001
0.003
0.007°
0.020
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
I
b Abatement area was not accessible for preabatement sampling.
c N-4.
TABLE B-113. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE S
ANOVA
Statistically significant differences In mean
Gc<^pfe
-------
q
d
o
q
6
o
o
q
6
v>
0
O)
0)
CO
0
.0
(0
cd
CD
c
cd
CD
cd
CD
O)
T-
CQ
CD
3
D)
LL
BLUO/S 'UOJJBJJU90UOQ SO}S8qSV 8UJOQJJV 96BJ9AV
286
-------
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have failed the
AHERA initial screening test because the average filter concentration (82 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA Z-test if the
abatement area concentrations were compared with the outdoor concentrations.
Although the site ultimately passed AHERA clearance by using the AST sampling
results, the EPA/NJDOH results clearly show that elevated levels of airborne asbestos
still existed in the school in 1988.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the abatement in 1988 (0.012 s/cm3) was not
significantly different from the average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the 1988 abatement (0.003 s/cm3) was not
significantly different from the average concentration measured outdoors (0 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the 1988 abatement (0.012 s/cm3) was not
significantly different from the average concentration measured in the perimeter areas
(0.003 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
287
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.001 s/cm3) was not significantly different from the average outdoor
concentration (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.003 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.003 s/cm3).
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured outdoors (0.007 s/cm3).
288
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.007 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Comparison of 1988,1990,1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990,1991, and 1992. Each sampling location was evaluated separately.
Table B-114 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988,1990,1991, and
1992.
i
TABLE B-114. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE S
Saflipfing 5"
location*
Abatement y -
area , ,
perimeter (_?
area " - *
Outdoors
\ X
\ "^
5ANftyA
s '•^ *< rt-k^-i
,p*yaTu«£
0.0779
0.6448
0.0129
_. '< •. ^ ,, •" • f :>f f,j, ^ f f f f f
Statistically significant differences In linean airborne asbestos
' -', " ~ {fcncentratoW4* * , ^ ' V
1988(0.012) 1990(0.003) 1991(0.001) 1992(0)
1988(0.003) 1991(0.003) 1990(0.001) 1992(0.001) 1988P(0.001)
1992(0.007) 1991(0.001) 1988P(0.001) 1988(0) 1990(0)
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was-less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
• 1988P » Preabatement; 1988 = Postabatement
289
-------
1988 Abatement Area
Differences between average airborne asbestos concentrations in the
abatement area in 1988, 1990, 1991, and 1992 were not statistically significant. The
highest average concentration (0.012 s/cm3) and the highest individual concentration
(0.028 s/cm ) were measured during the AHERA clearance phase of the 1988
abatement.
Perimeter
Differences between average airborne asbestos concentrations measured in the
perimeter area in 1988,1990,1991, and 1992 were not statistically significant. The
highest average concentration (0.003 s/cm3) and the highest individual concentration
(0.011 s/cm ) were measured during occupied conditions in 1991, 3 years after the
1988 abatement.
Outdoors
The average airborne asbestos concentration measured outdoors in 1992 was
significantly greater than the average concentration measured postabatement in 1988
and in 1990. Differences between average concentrations measured in 1988, 1990,
and 1991 were not statistically significant. The highest average concentrations
(0.007 s/cm3) and the highest individual concentration (0.020 s/cm3) were measured in
1992, four years after the 1988 abatement.
Structure Morphology and Size Distributions
Table B-115 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 42 asbestos structures, all of which were
chrysotile asbestos. Overall, the asbestos structures were primarily fibers
(71.4 percent), and to a lesser extent, clusters (16.7 percent), matrices (7.1 percent)
and bundles (4.8 percent).
Table B-116 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. Overall, 95.2 percent
of the observed asbestos structures were less than 5 jim in length. Of the 30
asbesitos fibers observed, only 1 (3.3 percent) was greater than 5 ^im in length.
290
-------
V)
LU
03
CL
DC
O
Ul
CL
ui
DC
DC
CO
g
UI
m
s
UL
O
o
m
DC
D
in
t-
CD
UI
m
s
CO
nt
e?1s
"a.*!
EH
CD
CO
co
CO
(O
in
ce
CO
CO
CO
CD
CO
CO
-'0
o*
in
CM
in
CM
in
**
CO
§?
ee
O)
s
1
o
T3
03
M
ca
i
I
•c
s.
ca
s
ca
CO
CO
O)
ca
CD
8
£
CO
JOB
co
CO
a
291
-------
CO
Ul
CO
Q
HI
DC
1
111
CO
1U
DC
O
DC
i
CO
UJ
m
UL
O
o
m
£
N
CO
III
o
to
t—
T-
£0
Ul
ffl
>
-3
" O
w
' V
1
sc-
CO
a
a
CO
*«
o
o
o
o
o
o
o>
o
CD
(O
re
S
re
li
o
•c
CD
Q.
T3
CO
CD
CO
CO
CO
O)
i
I
8
£
I
CO
o
CO
292
-------
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site S as part of the State's traditional quality assurance program, which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AHERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Three visual inspections were required at this site. The site failed the first
visual inspection because of the presence of debris on floors, on electrical wires and
fixtures, behind floor moldings, behind shelving units, and behind balcony seats. After
these areas were recleaned by the abatement contractor, NJDOH conducted a second
visual inspection. The site failed the second visual inspection because of the presence
of minor debris on the tops of exits signs, skylights, and stage fixtures and dust on the
balcony floor and shelving units. After these areas were recleaned by the abatement
contractor, NJDOH conducted a third visual inspection, which the site passed.
1991 Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, NJDOH conducted a visual inspection at Site S on
November 6,1991, as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in November 1991.
1988 Abatement Area
Gymnasium-The asbestos-containing ceiling plaster was removed by scraping
the material from the browncoat and then hammering the browncoat to break it loose
from the supporting wire mesh. This resulted in loose, crumbled browncoat being
trapped above the mesh. Such an approach posed a problem of how to remove the
material above the supporting wire mesh. This area was not accessible to the
workers, but it was now part of the abatement zone. The abatement contractor was
allowed to encapsulate the remaining browncoat by spraying through the mesh. In a
more conventional approach, the asbestos browncoat and wire mesh would have been
removed, which would have allowed the workers to access the upper areas to remove
all of the debris. Residue from the asbestos-containing ceiling plaster was noted on
several duct inlets (Table B-117). Crumbled browncoat plaster was noted above the
supporting wire mesh.
293
-------
Corridors--As noted for the gymnasium, browncoat plaster was noted above the
supporting wire mesh.
1988 Perimeter Areas
C/assrooms-Asbestos-containing block pipe insulation (24 percent chrysotile
asbestos) was noted in the closet overhead areas (Table B-117). This material was
not identified in the Asbestos Management Plan.
/./dra/y-Damaged thermal system insulation (elbows) was noted. This material
is not identified in the Asbestos Management Plan.
Crawl Space-Damaged cementitious elbows and joints of various
homogeneous types (4 to 19 percent chrysotile asbestos) associated with wrapped
fiberglass insulation were noted. Air-cell paper insulation matching the description of
materials located on the second floor was also noted. The crawl space and these
materials do not appear in the Asbestos Management Plan.
Boiler Room by the Gym-Large pieces of elbow debris (22 percent chrysotile
asbestos) were found behind the incinerator (Table B-117).
Conclusions
Debris from the ceiling plaster abated in 1988 was present on surfaces in the
1988 abatement area. TSI was present in the 1988 perimeter areas. This TSI did not
appear in the Management Plan.
294
-------
TABLE B-117. SUMMARY OF BULK SAMPLE RESULTS - SITE S
1991 INSPECTION
Type of Material
Analyses ,,
1988 Abatement Areas
Gym balcony
Gym SW wall
1988 Perimeter Areas
Library
Library
Classroom, middle, east
wing
Boiler room by gym
Crawl space
Crawl space
Crawl space
Crawl space
Residue on vent
Residue at ceiling wall
junction
Old ceiling tile at pipe entry
Broken joint in corner
Pipe in closet
Elbow debris
Elbow associated with
fiberglass, cloth outer wrap
Joint associated with
fiberglass, cloth outer wrap
2-in. Elbow associated with
fiberglass, paper outer wrap
2-in. Joint associated with
fiberglass, paper outer wrap
Positive81, chrysotile asbestos
Positive, chrysotile asbestos
Positive, chrysotile asbestos
Negative
24% amosite asbestos
22% chrysotile
<1% chrysotile asbestos
4% chrysotile asbestos
19% chrysotile asbestos
<1% chrysotile asbestos
a This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos.
295
-------
SITET
Background
Site Description
The abatement project at this three-story school building involved the removal
of approximately 4100 ft2 of spray-applied, asbestos-containing, acoustical ceiling
plaster. The abatement area included a cafeteria and stairwell. The project
specifications indicated that the asbestos content of the acoustical ceiling plaster was
approximately 10 to 25 percent chrysotile. The information regarding the abated ACM
and associated asbestos content was obtained from the asbestos abatement
specifications for this site.
Air Monitoring Summary
In 1988, postabatement air samples were collected in the abatement area,
perimeter area (outside the abatement area, but inside the building), and outdoors at
approximately the same time and location as those samples collected by the Asbestos
Safety Technician (AST) for the AHERA clearance of the site. Preabatement samples
were also collected in the perimeter areas and outdoors before the 1988 abatement
activities. Final clearance of the abatement site was based on the samples collected
by the AST. In 1990, air samples were collected at this school by use of a modified
aggressive sampling technique to simulate occupied conditions. The samples were
collected at approximately the same locations as those collected in 1988. In 1991 and
1992, air samples were collected at this school during occupied conditions (i.e., during
normal school operating hours) at approximately the same locations as those collected
in 1988 and 1990.
Summary of Air Monitoring Results
Table B-118 summarizes the results of the five sampling efforts. Figure B-20
shows illustrates the mean airborne asbestos concentrations at Site T. A single-factor
ANOVA was used to compare mean concentrations measured in each of the three
sampling locations. Table B-119 presents the results of the ANOVA analysis. The
following subsections summarize the pairwise comparisons of the mean concentrations
in the three sampling locations.
Preabatement -1988
The average airborne asbestos concentration measured in the perimeter area
before the 1988 abatement (0 s/cm3) was significantly less than the average
concentration measured outdoors (0.003 s/cm3).
296
-------
TABLE B-118 SUMMARY OF AIRBORNE ASBESTOS CONCENTRATIONS
(s/cm3) MEASURED AT SITE T
•l&ix
MJn
Max
0.003
0.005
0.049
0.037
0.061
0.030
0.070
0.015
0.050
0.001
0.005
0.001
0.005
0.005
0.015
0.001
0.007
0.001
0.004
0.001
0.003 0.001
0.003
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b Abatement area was not accessible for preabatement sampling.
TABLE B-119. SUMMARY OF ANOVA RESULTS FOR AIRBORNE
ASBESTOS CONCENTRATIONS MEASURED AT SITE T
cJlfferences in......
Simulated
Occtiptetf co
0.04
0.0720
0.2504
0.4214
0.3349
O(0.003) P(0)
A(0.049) P(0.030) O(0.015)
O(0.005) AfO.OOD P(0.001)
A(O.OOI) PfO.OOD O(0)
A(0)
O(0.001)
* If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pain/vise differences between sampling locations.
b A s 1988 Abatement area;" P = 1988 Perimeter area; O = Outdoors
0 Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that
sampling location.
d Sampling locations (means) connected by a line are not significantly different.
297
-------
cvi
CD
0)
0)
o
0>
O)
0)
E
0)
•4-i
XI
co
•t-l
(0
o
0^
CO
co
0)
q
c>
o
q
o
o
o
q
d
0
+•«
c/5
•D
0
£
0
CO
c
o
?
•*-"
c
0
o
c
o
o
CO
o
•*-•
CO
0
CO
OJ
0
c
03
0
D)
0
o
CVI
CD
0
3
D)
LL
eujo/s 'uoRBJiusouoQ sojssqsv
298
-------
Postabatement -1988
AHERA Clearance Test
Airborne asbestos concentrations measured by EPA/NJDOH during the AHERA
clearance phase of the 1988 abatement showed that this site would have failed the
AHERA initial screening test because the average filter concentration (321 s/mm2)
exceeded 70 s/mm2. Furthermore, the site would have failed the AHERA Z-test
regardless of whether the abatement area concentrations were compared with the
outdoor concentrations or with the perimeter concentrations. Although the site
ultimately passed AHERA clearance by using the AST sampling results, the
EPA/NJDOH results clearly show that elevated levels of airborne asbestos still existed
in the school in 1988.
Comparison of the Abatement Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the 1988 abatement (0.049 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.015 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the 1988 abatement (0.030 s/cm3) was not
significantly different from the average concentration measured outdoors
(0.015 s/cm3).
Comparison of the Abatement Area With the Perimeter Area
i
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the 1988 abatement (0.049 s/cm3) was not
significantly different from the average concentration measured in the perimeter areas
(0.030 s/cm3).
Simulated Occupancy -1990
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.005 s/cm3).
299
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area in
1990 (0.001 s/cm3) was not significantly different from the average outdoor
concentration (0.005 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
2 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Occupied Conditions -1991
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 3
years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
3 years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Occupied Conditions -1992
Comparison of the Previously Abated Area With Outdoors
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
300
-------
Comparison of the Perimeter Area With Outdoors
The average airborne asbestos concentration measured in the perimeter area 4
years after the 1988 abatement (0.001 s/cm3) was not significantly different from the
average concentration measured outdoors (0.001 s/cm3).
Comparison of the Previously Abated Area With the Perimeter Area
The average airborne asbestos concentration measured in the abatement area
4 years after the 1988 abatement (0 s/cm3) was not significantly different from the
average concentration measured in the perimeter area (0.001 s/cm3).
Comparison of 1988, 1990, 1991, and 1992 Results
A single-factor ANOVA was used to compare mean concentrations measured in
1988,1990,1991, and 1992. Each sampling location was evaluated separately.
Table B-120 presents the results of the ANOVA analysis, along with the results of the
Tukey multiple comparison test. The subsections following the table summarize the
pairwise comparisons of mean concentrations measured in 1988, 1990, 1991, and
1992.
TABLE B-120. SUMMARY OF ANOVA RESULTS FOR AIRBORNE ASBESTOS
CONCENTRATIONS MEASURED IN 1988, 1990, 1991, AND 1992 AT SITE T
locaBorf
Statistically stpfibartt differences in mean£fr£orne asbestos.
' '• * ' 1** ' '
Abatement
Perimeter
area
Outdoors
0.0001
0.0011
0.3082
1988(0.049) 1990(0.001) 1991(0.001) 1992(0)
1988(0.030) 1990(0.001) 1991(0.001) 1992(0.001) 1988P(0)
1988(0.015) 1990(0.005) 1988P(0.003) 1992(0.001) 1991(0)
* Samples were collected each year in the 1988 abatement and perimeter areas and outdoors.
b If the ANOVA p-value was less than 0.05, the Tukey multiple comparison procedure was then used
to distinguish pairwise differences between sampling locations.
c Parenthetical entries are mean airborne asbestos concentrations (s/cm3) associated with that year's
monitoring.
d Years (means) connected by a line are not significantly different.
• 1988P = Preabatement; 1988 = Postabatement.
301
-------
1988 Abatement Area
The average airborne asbestos concentration measured in the abatement area
during the AHERA clearance phase of the 1988 abatement (0.049 s/cm3) was
significantly greater than the average concentrations measured in 1990 (0.001 s/cm3),
1991 (0.001 s/cm3) , and 1992 (0 s/cm3). Differences between average airborne
asbestos concentrations measured in the abatement area in 1990,1991 and 1992
were not statistically significant. The highest average concentration (0.049 s/cm3) and
the highest individual concentration (0.061 s/cm3) were measured during the AHERA
clearance phase of the 1988 abatement.
Perimeter Area
The average airborne asbestos concentration measured in the perimeter area
during the AHERA clearance phase of the 1988 abatement (0.030 s/cm3) was
significantly greater than the average concentrations measured preabatement in 1988
(0 s/cm3), in 1990 (0.001 s/cm3), in 1991 (0.001 s/cm3), and in 1992 (0.001 s/cm3).
Differences between average airborne asbestos concentrations measured in the
abatement area preabatement in 1988, and those measured in 1990, 1991 and 1992
were not statistically significant. The highest average concentration (0.030 s/cm3) and
the highest individual concentration (0.070 s/cm3) were measured during the AHERA
clearance phase of the 1988 abatement.
Outdoors
Differences between average concentrations measured in 1988, 1990,1991,
and 1992 were not statistically significant. The highest average concentration
(0.015 s/cm3) and the highest individual concentration (0.050 s/cm3) were measured
during the AHERA clearance phase of the 1988 abatement.
Structure Morphology and Size Distributions
Table B-121 presents the distribution of structure type and morphology at each
sampling location separately for each year of monitoring. The TEM analysis of 20
samples collected in the abated area, 20 collected in the perimeter area, and 20
collected outdoors yielded a total of 127 asbestos structures, of which 99.2 percent
were chrysotile asbestos and 0.8 percent were amphibole asbestos. Overall, the
asbestos structures were primarily fibers (88.2 percent), and to a lesser extent,
matrices (11 percent), and bundles (0.8 percent).
Table B-122 presents the cumulative size distribution of asbestos samples at
each sampling location separately for each year of monitoring. All of the observed
asbestos structures were less than 5 urn in length.
302
-------
H
UJ
55
>•
O
••J
X
D.
OC
o
Si
Q
g^f
^**
Ul
Q.
£
III
OC
3
r>
E
CO
m
0
0
=>
m .
oc
5
B
(N
T
CD
HI
m
s
>.
ot
o
3
•iK
t
S
'»
Q
:|
0
" >
; ,
te
! 2
> 1
J
i
'" <
x*i
v
o
o
o
0
o
*~
o
8
, ^ v-."
^
*s~ **
^
^ /- !
&f*
o
o
o
o
o
•""
o
0
o
CM
•.;.•. ^%
li
^ -^
^-^
^ j
^ ' *
i
t
i
i
•
•
0
:|
s-,% V.
^•-;
$* ^
j&
b;v;
CD
O
O
CO
2
o
o
o
CO
CO
•^
o>
^':
^" ""'
••
o
o
o
o
0
1
o
f
%i
?'
f •>'
"; ''
o
o
o
o
o
1-
o
o
o
CM
-.4*
m
v %
j:
jS <
""
o
o
o
o
o
o
o
o
.J
e*
f ^ s
f'' 5 -•
•^ ••
J
CD
in
o
CD
in
en
CO
CO
o
o
o
CO
T-
•I
s r*--
> f
s
o
CM
O
O
o
CO
o
o
o
in
o
i
V
1
I
1
1
I
1
0
S
0>
t
c> '
'
o
o
o
o
o
•*"
o
0
o
CM
o>
V*
^
{ >**%
...^'v
el
o
TJ
S
O
TJ
CO
S
cc
0)
co
i-
i
tJ
f
1
CO
CO
en
•*—
c
m
O
1
0)
TJ
"S
1
(O
eu
t
w
ttf
303
-------
1-
Ul
55
<
o
Ul
DC
<
Ul
^S
w
Ul
CC
e
o
ID
rr
E=
(0
(0
R
05
Ul
m
u.
0
z
O
1-
ffl
E
5
N
(0
Ul
>
g
3
«B
CM'
CM
T-
1
CO
Ul
mJ
ffi
4X
i-
f fVff^
' '•',
''•. ••
r
f f
:"k
2ft
'"* 3
3
w
J
w
?5
»r
*»
Wl
f
' W.
:s
i
•I'*''
"""
;,..
•"•
>JU
!"O 4
!Z
" '
v. •i'1-
•*
"j-. ..
"*
v. •.
H
-"
>
"o
t IH
;
"1
i^
A J
••
a|
./ ;
x
,, :
*
i
' - i
*>
E
^j
"• •
;
;-,, \
:f:
"' i
,,«i
*• Jj '"
> 0 i
•C i
"^:
:'v
•.-.Jg* •
^^* :
^ ••:
,|:
S':
% S« :-
~ ;
,Mi
t'»:
.
:
- i
o
0
Y«
o
o
0
o
o
o
CO
CO
OJ
s
O)
in
«]
•05 •
i^ .
^
*•
f
0
o
T"*
o
o
^™
o
o
o
o
o
o
,-
'0
0)^
^w-
w*«
^ fl
s
w
:;i
?
, <
o
o
^•B
o
o
in*
o
0
T-
o
0
o
o
T-
o
o
CM
o>
0?
T"
'"
! '
I-
i
^
!
' '
.
1
1
'
I
1
O
*J
•£F) :
"^^ :
•• :
<
"•j
8
0
o
CM
O)
CM
O)
O)
CO
CO
S
c§
8
s*
yn-
;' ,
••
8
o
o
o
o
o
0
T-
g
o?
ijpifr
. ^
^^
§
9
^ t 'iQ
-'-!
•x
a
--ft
8
o
o
s
o
in
s
CM
£J
O) •
•^^ :
-.
i
^
L ,,
!. ^ ,
r
1
'•.V, *"
F ' •*
O
O
8
o
0
o
0
o
o
T—
o
o
T-
&*
•O5"
^^
'
*
^
*^
f>f
•"
o
0
8
I
o
o
o
0
T™
O)
§
CO
i
T^^
%
' ,
^
•"
f
•" •"
8
0
o
8
8
o
o
^"
o
in
eT!
tr> :
'«>;
•J^ ;
-•
ff »
i
s
V
m
•c
t
I
1
1
1
1
1
O
•C8 i
«:
>!T^ i
,.,..
> -
I
:
i
>
I
o
o
^^
0
o
o
o
o
o
T~
o
in
CM
«
f
-
"•
.
£
o
•S
"5
1
CO
co
£
CO
k.
"S
•c
CO
Q.
*D
CO
S
E
£
,c
u.
CO
S,
1
o
"CJ
T3
1
£
fli
i
CO
CD
t
CO
CO
s
304
-------
NJDOH Visual Inspections
1988 Inspection
The NJDOH's Environmental Health Service conducted a final visual inspection
at Site S as part of the State's traditional quality assurance program, which provides a
check and balance to asbestos abatement to ensure that high-quality abatement and
state-of-the art work practices are used. The onsite AST collected the AH ERA
clearance air samples only after the site had passed the NJDOH visual inspection.
Two visual inspections were required at this site. The site failed the first visual
inspection because of the presence of debris on floors, walls, pipes, light fixtures, wall-
ceiling junctions, and wall penetrations. After these areas were recleaned by the
abatement contractor, NJDOH conducted a second visual inspection, which the site
passed.
1991 Inspection
Although asbestos monitoring conducted in May 1991 found airborne levels of
asbestos within the AHERA criteria, NJDOH conducted a visual inspection at Site T on
October 22,1991, as a followup. The visual inspection strategy considered the
asbestos-abatement history of the site, the O&M activities, and other sources of
possible asbestos contamination (i.e., materials not included in the Asbestos
Management Plan). Only those areas indicated in the following subsections were
examined by the NJDOH inspector in October 1991.
1988 Abatement Areas
Cafeteria-The residual spray-on materials (positive for chrysotile asbestos)
were obtained from the ceiling and wall junction as encapsulated "bumps" along the
border of the original ceiling application (Table B-123), Loose ceiling debris was also
recovered from one pipe hanger. All the pipes in the abatement area have been
reinstated with fiberglass. This negated a thorough inspection of pipe surfaces
without removing the fiberglass. All pipe penetrations (wall and ceiling) were foamed
or caulked.
The area also has a new suspended ceiling system that isolates the original
abatement zone from the occupied space below. Numerous penetrations of the
browncoat occurred during the ceiling abatement. Air is moved through the lower,
occupied space and into the zone above the suspended ceiling via vents in the wall.
The vents lead to ducts that run throughout the facility.
305
-------
TABLE B-123. SUMMARY OF BULK SAMPLE RESULTS - SITE T
1991 INSPECTION
Type at Material
Analyses
1988 Abatement Areas
Cafeteria, west wall
Cafeteria, SE wall
Cafeteria, NW wall
1988 Perimeter Areas
Basement hall at
custodial office
Basement hall at
custodial office
2nd-Floor hall
3rd-Floor hall
3rd-Floor hall
Debris in hanger
Encapsulated residue
Encapsulated residue
Encapsulated debris at
duct
Encapsulated debris at
duct
1-ft by 1-ft Ceiling tile
1-ftby 1-ft Ceiling tile
Sheetrock above ceiling
tile
Positive3, chrysptile
asbestos
4% chrysotile asbestos
Positive, chrysotile asbestos
39% chrysotile asbestos
Positive, chrysotile asbestos
Negative
Negative
Positive, chrysotile asbestos
This classification was defined by the NJDOH laboratory to accommodate samples
for which inadequate material was available to allow a full quantitative evaluation,
but were of sufficient size to determine that asbestos was present and to determine
the specific type of asbestos. Based on the professional judgment of the analyst,
the sample is considered to contain greater than 1 percent asbestos. ,
1988 Perimeter Areas
Basement Hallway --In 1989, thermal system insulation was removed from the
pipes and ductwork in this (and other) basement areas. Encapsulated "lumps"
(positive for chrysotile asbestos) were recovered from the wall below the ductwork in
this area. The tops of the ducts and the pipe penetrations had been heavily sealed
with expanding foam and caulk. Although the use of foam and caulk-type sealants is
not a preferred practice, this practice does require that the resilient ACM be managed
under an O&M Plan. Pipes had been reinsulated with fiberglass and could not be
inspected without the removal of these materials.
306
-------
Perimeter Comcfo/s~The first and second-floor corridors have asbestos-
containing resilient floor tile and 1-ft by 1-ft interlock ceiling tiles that are assumed to
be asbestos. According to the Asbestos Management Plan, these are nonfriable
miscellaneous materials, in some areas, the ceiling tiles are bowed from water or
other damage and are friable. The plenum area above the 1-ft by 1-ft suspended
ceiling system is not accounted for in the Management Plan. Visual access to the
plenum is limited to holes (damaged areas) in the ceiling system. Ductwork (white-
grey fiber type) and corrugated pipe insulation with solid joints and elbows were
observed. These materials are not identified in the Asbestos Management Plan.
Boiler Room Vertical Shafts-Pipe insulation was in the shafts that rise from the
boiler area. These materials are not mentioned in the Asbestos Management Plan.
Gymnasium-Pipe insulation was noted above the suspended ceiling system in
the gym. It could be seen from a hole in the wall of the basement corridor. This
material is not mentioned in the Asbestos Management Plan.
Third Floor Comcfor-Sheetrock above the suspended ceiling system tested
positive for chrysotile asbestos. This material does not appear in the Asbestos
Management Plan.
Conclusions
The Asbestos Management Plan was not updated regarding the 1989
abatement.
The Asbestos Management Plan noted nine rooms that had not been inspected
during the original AHERA inspection. The Plan does not state whether these areas
were ever inspected in accordance with the AHERA requirements.
Although debris and residual materials were recovered from the areas
inspected, the use of suspended ceilings isolating the abatement zone, the heavy use
of encapsulants, foam and sealant, and the use of fiberglass retrofit materials, have
resulted in acceptable levels. This, however, does not eliminate the potential for
future disturbances through operations and maintenance activities.
307
-------