United 'States
                    Environmental Protection
                    Agency	
Risk Reduction
Engineering Laboratory
Cincinnati OH 45268
                    Research and Development
 EPA/600/S2-90/026  July 1990
&EPA         Prpject  Summary
                    Treating  Chlorinated  Wastes
                    with  the  KPEG  Process
                         i
                    M. L. Taylor, J. A. Wentz, M. A. Dosani, W. Gallagher, and J. S. Greber
                      The two reports summarized here
                    describe  development of the  alkali
                    metal (polyethylene gylycolate (APEG)
                    chemical technology to dechlorinate
                    hazardous hydrocarbons in soils and
                    its application at four demonstration
                    sites:  field-scale application  to
                    contaminated soils on the island  of
                    Guam;  pilot-scale demonstration  in
                    Moreau, New York; and drum-stored
                    contaminated  materials  at the
                    Bengart & Memel site in New York
                    and ir|i  Omaha, Nebraska. The Omaha
                    site  involved tetrachlorodibenzo-p-
                    dioxiri (TCDD) in waste herbicides.
                      Equipment for  the field-scale
                    application  on  Guam included  a
                    stearji-jacketed  mixer,  a  steam-
                    generating plant,  and a  condensate
                    collection system.  Approximately  15
                    yd3  of contaminated  soil  (with
                    concentrations averaging 3535 ppm
                    Aroclbr 1260) were batch treated with
                    potassium polyethylene glycoiate
                    (KPEG). The  polychlorinated biphenyl
                    (PCS)  concentrations were reduced
                    by more than 99%, with no individual
                    PCB congener exceeding 2 ppm.
                      The  reports  provide detailed
                    information about preparation  of
                    contaminated soils before treatment,
                    equipment and reagents used during
                    treatment, and analyses done before,
                    during, and  after treatment. Potential
                    users are given sufficient information
                    of th:e KPEG process to ascertain
                    which  version of the  process is best
                     suited for a particular site.      '•.
                       This Project Summary was develo-
                    ped by EPA's  Risk Reduction  Engi-
                     neering Laboratory, Cincinnati, OH, to
                     announce  key  findings  of \the
 research projects that are fully docu-
 mented in  two separate reports  (see
 Project Report ordering information at
 back).

 Introduction
   The  two  reports concern a chemical
 dechlorination  process that employs a
 reagent, typically prepared by reacting a
 base (e.g., potassium hydroxide) with one
 of several  polyethylene glycols (e.g.,
 PEG 400).  Early  laboratory- and drum-
 scale studies are  described that proved
 the feasibility of the KPEG technology to
 treat PCB-contaminated soils.  In-depth
 descriptions are  given of the KPEG-
 process demonstrations that have  been
 done to date.
   A typical laboratory-scale procedure for
 dechlorinating polychlorinated dibenzo
 dioxins (PCDD)- and PCB-contaminated
 soil involves mixing potassium hydroxide
 (KOH) and polyethylene glycol-400
 (PEG-400,  average molecular weight of
 400 Daltons) to  produce  the  reagent
 KPEG. This KPEG reagent is mixed with
 the contaminated  soil, heated to approx-
 imately 150°C (302°F), and maintained
 at that temperature while being  con-
 tinuously stirred for  1  to 4 hr. Excess
 reagent is  then  decanted,  the soil is
 neutralized  with acid and rinsed two or
 three times with  water, and the decon-
 taminated soil is discharged.
   The reaction of the KOH and PEG-400
 produces an alkoxide (ROK) (Equation 1),
 which  in turn reacts with one of  the
 chlorine atoms  on the aryl  ring to
 produce an ether  (ArCI,^ OR) and potas-
 sium  chloride (KCI) salt (Equation 2).
 Replacement  of the chlorine atom on the
 aryl ring  with  an  ether-linked  PEG

-------
detoxifies the compound.  The  dechlo-
rination process is described in Equations
1,2, and 3:
ROH + KOH

ROK + ArCln
                   ROK + H20      (1)

                        ! OR + KCI (2)
            AH

 Ar Cln., OR — •*" Ar Cl n.t OH + CH2 =


                                   (3)
   H
   I  -OR
   C
Pilot-Scale and Field-Scale
KPEG Treatment
Demonstrations
  Four site demonstrations of the KPEG
process  are discussed.  A pilot-scale
demonstration  was conducted  at the
Moreau, New York, site, and a field-scale
demonstration  was conducted  at the
Guam site. At the Bengart & Memel site
in  New  York  and  a site in  Omaha.
 Nebraska, drum-treatment  demonstra-
 tions of the  KPEG process  were  con-
 ducted. Discussions of these four site
 demonstrations should  assist potential
 users of the KPEG process with sufficient
 information to assess which of the four
 versions of the  KPEG  process  is  best
 suited for implementation  at a particular
 site.

 Pilot-Scale Demonstration  of
 KPEG Process in Moreau,
 New York
  The objectives of the  demonstration at
 the Moreau site were to document that
 the KPEG  reagent could effectively de-
 chlorinate PCBs to acceptable levels  at
 the 40-gal scale  (from hundreds  and
 thousands of parts per million to less than
 3 to 4 ppm) and to gather process  data
 that would  subsequently be used  to
 design a larger (2-yd3 or 400-gal)  reactor.
 The test at Moreau was not intended  to
 be a site cleanup; only a small portion of
the contaminated soil was treated as part
of the test.
  The Moreau site  was formerly a drag
strip. The  drag  strip was  oiled period-
ically, and  some of the oil used for this
purpose  was transformer oil containing
PCBs. The PCS concentrations in the soil
at the site ranged from nondetectable up
to tens of thousands  parts per million.
The  pipe reactor (Figure 1) used during
the pilot-scale tests was constructed from
a 40-in. length of 16-in. steel pipe. It was
mounted on a  stand that  allowed it  to
rotate about the indicated pivot point, and
because it rotated through an arc of 180°
in about  10 sec, mixing  inside the pipe
was gentle. A baffle along the side of the
pipe (midway down  its length) redirected
the flow of  slurry along the  pipe wall and
enhanced mixing.
  Four electric heating straps heated the
reactor. One 1000-watt heating strap was
wrapped  around the top of the  reactor,
and  another was wrapped  around the
bottom. Both straps were  about  10  in.
wide. Two  3-in.-wide  1500-watt straps
were wrapped  around the center portion
of the reactor
                                    Hose Connection for
                                       Draining and
                                     Adding Reagent
                            1000-W
                         Strap Heater


                        Thermometer
                         0°-/50°C
                            Sample Valve
                          1500-W
                       Strap Heater

                           Internal Baffle

                         1500-W
                       Strap Heater


                            Arc of Rotation
                           1000-W
                        Strap Heater
                                                                       16-Bolt
                                                                       Flange
                                                                     Screen Stack for
                                                                    'Draining Reagent in
                                                                       Top Flange
                                                                    1/2 Area Internal Baffle to
                                                                  Protect Screen Stack from Rocks
                                                                              -60 psi Gage
                                                                       Vent Line
                                                                   Welded
                                                                  End Plate
                                                      Removable Insulation Is Used During Operation
Figure 1.   Reactor detail for the Moreau, New York pilot-scale demonstration.

-------
  During the reactor operation, tempera-
ture and  pressure were recorded  every
15  min.  The  reactor  motion and its
direction were  controlled by a hand-held
switch; therefore, during the entire time
the reactor was operating, someone held
the switch  and manually  reversed  the
reactor's  direction at the  end of each
180° turn.
  Vapor from  the  reactor  was vented
through a smalt fan-cooled condenser
(Figure 2).  The condenser condensate
was collected in Condensate Drum  No. 1,
which was  vented to an ice  condenser
consisting of a coil submerged in  an ice
bath that drained to Condensate  Drum
No. 2. Condensate  Drum No.  2 was
vented through an  activated carbon
canister to remove  any trace volatiles
before atmospheric discharge.
  The treatment procedure involved pre-
paring  the  solvent   PEG  mixture —
dimethylsulfoxide (DMSO), triethylene
glycol methyl ether (TMH), and PEG-400
[ratio  2:1:1]—in a  55-gal drum. The soil,
solvent mixture, and  45%  KOH solution
were  then  loaded into the reactor  and
mixed. The reactor was heated to 150°C,
and the  samples were withdrawn  by
removing the  thermometer and pouring
the slurry (-50 g) out of the thermometer
insertion port.
  Altogether, four runs were made with
this npactor. Table  1  lists the reactor
contents for each of these runs. After the
samples were  taken out of the reactor,
both soil and reagent  were analyzed for
RGBs] The reductions  in PCB concentra-
tion in| the  soil achieved during Run No. 1
ranged  from  93.9%  to  99.8%  ^and
averaged 98.3%. The  PCB reduction in
the rehnaining three runs (Runs 2 through
4) was greater than 99%. PCBs were jalso
founcj  in  the recovered  reagents,
generally  at higher concentrations  than
thosel in  the  soil;  this indicated  that
although the PCBs were being  extracted
from the  soil  into the  liquid phase,
chem cal  dechlorination  was not  yet
comp ete.  The PCB concentrations in the
reagent were 0.16 ppm in Run 1, 74.8
ppm In Run 2,  72.4 ppm in Run 3,  and
4.25 ppm in Run 4.


F/e/o-Sca/e Demonstration of
KPEp Process in Guam
   The; U.S. Navy Public Works Center on
Guarr  was selected for the field-scale
rrj
o
demostration  of  the  KPEG  chemical
dechlprination system. The PCB concen-
trations in the soil at the  site averaged
3535 jppm, with "hot-spots" as high as
45,860 ppm (4.59%). Soil  contamination
(found  primarily  in  a nearby  storm
drainage ditch) was the result of leaks
from a  transformer  rework  building  and
waste PCB stored outside  the building.
Excavated, contaminated soil was stored
in a 12.2- by  18.3-m (40- by 60-ft) metal
building with a heavy rubber liner erected
on a concrete pad. Also another 30.5- by
30.5-m (100- by 100-ft) concrete pad was
poured  for the installation  of the field-
scale KPEG treatment system.
  Soil and particles smaller than 1/2 in.
were passed through  the  screens  and
collected separately  so that particles
would not be jammed in the mixer.
  Laboratory studies of contaminated soil
samples from  Guam  determined  the
soil's potential for KPEG treatment and
established the reagent formulation and
other operating parameters.  Figure 3 is a
simplified mechanical flow diagram of the
KPEG system at Guam. As illustrated, the
mixer was the primary component of the
system  in which  the  chemical dechlo-
rination  process occurred. An extensive
pipe network connected  the ancillary
equipment with each other  and with the
mixer.
  The principal components of the Guam
KPEG treatment system (mixer, platform,
liquid reagent loading  system, heating
system, nitrogen system, condensate col-
lection system, process cooling system,
reagent collection system, and ventilation
                                           Condenser
                          Center
                        Pivot Point
                         Pipe
                       Reactor
                      Thermometer -	""  ,./
                                                                                       Vent
                                             Arc of
                                             Rotation
                  Condensate
                   Drum #7
                          Condensate
                            Drum #2
 Figure 2.   Equipment arrangement for the Moreau Test.
Run
1
2
3
4
Soil
33.5
32.5
34.0
39.0
Sulfolane
0.0
0.0
0.0
15.0
DMSO
11.0
10.0
12.0
0.0
TMH
PEG-400
5.5 5.5
5.0
6.0
5.0
6.0
7.5 7.5
45% KOH
11.0
10.0
12.0
13.0
Total ,
Liquid
32.9
30.0
35.9
43.0,
      Nitrox
      Drum

-------
        Contaminated
            Soil
         KOH Pellets
        Liquid Reagent
         (PEG-400)
          Process
        Cooling Water
           Steam
         Generator
         Diesel Fuel
            Air
         Compressor
                              ~ System Air Requirements
                                                                                                   Condensate
                                                                                                    Collection
                                                          Neutralization
                                                             Acid
                                                                                                     Nitrogen
                                                            Reagent
                                                           Collection
                                                                                                Required Process


                                                                                                Optional Process
Figure 3.  Mechanical How diagram of KPEG field-scale treatment system.
system) are described in detail in the full
report.
  Six 55-gai  drums  were placed on a
metal pallet, the pallet was positioned in
the metal building next to the stockpiled
soil, and the  soil was shoveled into  the
drums.  The  six drums  of  soil were
relocated to  the  scale,  where  a small
forklift with  a  drum-lifting  attachment
placed them on the scale. A grab sample
was collected from each of the six drums
of soil. These samples were placed  in a
container  and  mixed  thoroughly to
provide a homogeneous sample for PCS
analysis.
  A crane hoisted the drums of  soil, and
two  persons  on the platform used  the
manual  chainfall on  the  drum  lifter to
dump the drum  contents  into the mixer.
After  every second  drum of soil  was
loaded, the mixer was turned on for a
short time  to disperse the  soil evenly
throughout the mixing cylinder.
After  all  the  soil was loaded  into the
mixer, the components  of this  KPEG
(PEG 400  and KOH) formulation  were
added. The mixer was run  at low speed
(30 rpm) while the PEG-400 was pumped
into it; this allowed thorough dispersion  of
the PEG-400  and KOH to initiate the first
reaction shown in Equation 1. When the
reagents and  soil were completely mixed,
the mixer was switched to high speed (60
rpm). The vent line from the mixer to the
condensate  collection  system  was
opened,  and  the  fan condenser was
turned on.
  The steam-generating plant was ignited
and 80-psi steam was circulated through
the mixer jacket.  The  mixer  contents
reached 150°C  in  approximately 2 hr,
and  the temperature  and  mixing  were
maintained for 4 hr. At the end of 4 hr,
the steam generator and mixer were shut
down, the fan condenser was turned off,
and the contents were  allowed  to  cool
overnight.
  After cooling  overnight, all the treated
batches of  soil were  neutralized  with
concentrated  sulfuric  acid  and  dis-
charged. Samples were  collected from
the sample-collection port, and the slurry
pH was measured.  If  the  collected
sample had  a pH in the 6 to 9 range, it
was also used  as the posttreatment soil
sample. The treated soil  and reagents
used in the  treatment process were dis-
charged into the  soil-collection hoppers
pending analytical results.
  A  high-pressure  (2000-psi)  water
washer  was used to decontaminate the
process equipment, and the resulting
water was collected in 55-gal drums. The
collected condensate and  water were
passed  through  a  series  of cartridge
filters and activated-carbon canisters. The
treated  water  was  then  collected,
sampled, and  held  until  results of

-------
analyses  for  PCB  contamination  were
obtained. Treated  waters with  nonde-
tectable PCB concentrations were either
collected  by a liquid transport truck and
discharged  into  the sanitary sewer
treatment plant or pumped back onto the
hot zone.
  PCB analyses  employed  an EPA-
developed field-screening  method, which
was  followed  with  a more  vigorous,
corroborative analysis.  A  review  of
treated soil  analytical  data  from  both
analyses  indicated that the destruction of
the total  PCB concentration  exceeded
99%. In  both sets  of data, however,
analysis of each of the congener peaks
showed  that a  tetrachlorobiphenyl
congener concentration in  a portion of the
treated batches was  slightly  above the
R&D  permit requirement  of  2  ppm  or
lower per PCB peak. The batches  con-
taining greater than 2 ppm of the  tetra
congener were  loaded  back into  the
mixer, mixed with the new KPEG formu-
lation of  1.3  moles KOH and  1.0  mole
PEG-400, and retreated.  Analytical re-
sults  of the retreated batches indicated
the tetra congener in each batch was well
below 1 ppm.


Drum Treatment Demonstration
of KPEG Process at  Bengart &
Memel  Site, New  York
   The preceding two KPEG  demonstra-
tions  were performed to prove the effec-
tiveness  of the KPEG process at  larger
scales and to promote the development
of a  full-scale system. The  demonstra-
tions  described in this section  and the
one  that follows concern  the in  situ
treatment of smaller quantities  of  con-
taminated  materials that  may   have
already  been placed  into  drums for
storage.  This  process offers an alterna-
tive to the costly and hazardous process
of emptying  drums of  hazardous  mate-
rials.
   When  Bengart & Memel, Inc., a whole-
saler of  nonferrous  scrap metals,  dis-
mantled  PCB transformers  and capaci-
tors, PCBs were released into the soil. In
the  mid-1970"s,  soil  samples from this
site  contained  PCB  concentrations ex-
ceeding 50  ppm.  Soil  sampling  and
analysis indicated  that  PCB concen-
trations were  excessive  in  seven  loca-
tions on the  property.  As part of the
remedial program, the contaminated soil
was excavated and placed in 166 55-gal
 steel drums. Because of a consent  order
deadline, only 51 drums of soil  were
treated  in this  demonstration. All the
 remaining drums were shipped, un-
 processed, directly to a landfill.
  During the KPEG treatment process, a
weighed quantity (typically 150 to 170 Ib)
of a  single-phase  reagent  mixture
(2:2:4:9:5-PEG:TMH:DMSO:45%  KOH:
water!) was added  to  each of the' soil
drums. A  bimetal thermometer was in-
serted into the 3/4-in. bung on each drum
coveij, and the drums  were heated :from
the bottom to ensure that all of the soil
contaminants would react. The  soil |tem-
perature was monitored 9 to 12 in. below
the top of the drum, and the soil temper-
atures were typically maintained between
105° and 110°C for several hours.  ;
  The drums were vented  to  a central
condenser system with a capacity  pf 16
drums  (see  Figure 4). During heating,
vapors exited from the drum through an
insulated flexible line connecting the 2-in.
drum bung  with  the  main  header.
Because  part  of  the  header  was: ice-
jacketed, much of  the water vapor was
condensed and drained directly  into a 55-
gal holding drum.  The remaining  vapor
was drawn through an air-cooled radiator
(used  as a  condenser),  which  also
drain'ed liquid to the 55-gal  holding  drum.
An ice-jacketed scrubber  containing a
dilute sodium  hypochlorite  solution (for
odor
control) trapped most of the rernain-
ing condensables. From the scrubber, the
vapo' passed through a 55-gal drunrvfilled
with a mixture  of activated  carbon  and
containing a molecular sieve. A vacuum
pump provided  negative pressure for the
vapoj' control system.
  A 30-in. auger attached to a  hand drill
was {used to collect  treated  soil samples
from the drums. Four samples  (one; from
the center, one close to the drum; wall,
and two  spaced between the center and
wall); were collected from the  drum  by
penetrating the soil as deeply as possible
with the auger.
  After  the treated  soil  had  been
decontaminated, the  soil   had to  be
brought from a highly alkaline to a neutral
pH bjy the addition of dilute acid.
  Soon  after  the  KPEG treatment
(October 1986), EPA determined the con-
centrations of PCBs  in selected drums. A
second group of drums was  sampled and
analyzed in February  1987  after the
reagent had been in contact with the soil
for 5 mo. Group 2 included fresh samples
froml the drums that  EPA found  contained
PCB  concentrations exceeding  50; ppm,
samples from treated drums not analyzed
.by the EPA, and one  soil sample that
contained less  than 50 ppm when EPA
analyzed it. The low-concentration j sam-
ple Was  analyzed to check the potential
reacfion  progress in  drums with  PCB
concentrations  below  50 ppm. A :com-
parison  of the reduced concentrations
                                   reported  in February with the October
                                   results indicated that the reaction  con-
                                   tinued during the holding period.
                                     A review of treated-soil  analytical data
                                   indicated that PCB  concentrations  were
                                   reduced  from 108 to  27 ppm (a  75%
                                   reduction). The  PCB levels in the soil in
                                   one drum with an initial concentration of
                                   1300  ppm  were reduced  to  78 ppm (a
                                   93% reduction).
Drum Treatment Demonstration
of KPEG Process at an Omaha,
Nebraska, Site
  This 1987 EPA study was designed to
demonstrate  the  effectiveness of  the
KPEG  process for treating  drummed,
contaminated herbicide wastes containing
dioxins. The contaminated  waste  con-
tained 17,800  ppm  2,4-D,  2800  ppm
2,4,5-T, and 1.3 ppm 2,3,7,8-TCDD.
  The KPEG reagent used in this demon-
stration was prepared  with PEG  and
KOH. The field-scale testing of the KPEG
technology was performed on one 20-gal
batch of the contaminated waste.
  The  treatment equipment consisted of
a 55-gal drum, a clamp-on heating band,
and a stirring motor. The drum containing
the KPEG reagent  and the contaminated
waste  was  heated to a temperature of
70° to 85°C for 2 days while being con-
tinually stirred.  After 2  days, the heater
was  turned off  and the  reaction mixture
was  allowed  to cool to ambient  tem-
perature. The  treated  waste  samples
were  then  analyzed to determine the
posttreatment concentration of the  con-
taminated waste.
  Table 2 presents the analytical results
of samples  collected before treatment
and after the first and second treatments.
The  KPEG treatment reduced  the  con-
centration of 2,3,7,8-TCDD in the waste
to less than the detectable  range.  The
concentrations of both 2,4-D  and 2,4,5-T
were reduced by 98%.
                                    Conclusions
                                      The pilot-scale KPEG demonstration in
                                    Moreau, New York, represented the first
                                    attempt to  dechlorinate  PCBs  in a
                                    reactor/mixer at a  scale larger than that
                                    used in the laboratory. Results of  the
                                    demonstration indicated that PCBs  could
                                    be reduced  by an  average of 98.3%
                                    (reductions  ranged from  93.9%  to
                                    99.8%).
                                      The field-scale demonstration  at Guam
                                    proved the effectiveness  of  the  KPEG
                                    technology for treating  soils with  initial
                                    PCB concentrations averaging 3535 ppm

-------
     Drum
    Heaters
                                                                  To
                                                                Vacuum
                                                                 Pump
                  Reaction
                   Drums
Water
                         Sorbent
Figure 4.   Central condenser system, KPEG drum treatment demonstration,  Bengart &
           Memel, Buffalo, New York.
Table 2.   Drum Scale Treatment of TCDD, 2,4-D and 2.4,5-7

                                       Concentration in Treated Waste
Contaminant
TCDD (2,3,7,8)
2.4-D
2.4.5-T
Cone, in Untreated
Waste, ppm
1.3
17,800
2,800
First Treatment,
ppm
0.086 :
9,000
7,700
Second
Treatment, ppm
ND"
334
55
reroef/i
Reduction of
Contaminants
99.99
98.12
98.04
'ND = None Detected

(3260 to 3828 ppm). PCB concentrations
were reduced to an average concentra-
tion of 6.74 ppm  {1.01  to 13.9 ppm),
which represents an average reduction of
99.84% (99.58% to 99.98%) with no
resolvable PCB congener  exceeding 2
ppm (after retreatment).  The process
implemented in  Guam was successful in
its treatment of  PCB-contaminated soil
without the use of DMSO or TMH.
  The KPEG process used at the Bengart
& Memel site successfully  reduced  PCB
levels in soil contained in 55-gal drums to
below the 50-ppm control limit set for the
soil at the site.
  The drum-scale KPEG process at the
Omaha site proved  to be capable  of
degrading  2,3.7,8-TCDD, 2,4-D,  and
2,4,5-T. Initial concentrations of 1.3  ppm
2,3,7,8-TCDD, 17,800 ppm 2,4-D,  and
2,800  ppm 2,4,5-T were reduced to  con-
centrations of none  detectable, 334 ppm,
 and 55 ppm, respectively. The  demon-
 stration also proved  the effectiveness of
 KPEG without the use of DMSO or TMH.
 Recommendations
   The following recommendations were
 made concerning  the  field-scale  KPEG
 system:

 1.  The system should be used at addi-
    tional  sites  to provide more back-
    ground data on the technology.
 2.  Additional field-scale demonstrations
    should be done  in  an attempt  to
    optimize  the reagent formulation and
    operating parameters.

 3.  The  labor  intensity  of the  system
    should be  reduced  by modifying it
    with  materials handling equipment
    and automation.
4,  Attempts should be made to identify
   alternative  equipment manufacturers
   that  may  be  capable  of  further
   increasing  the efficiency  of  the
   system.

5.  Design of a full-scale, fully portable,
   self-supportive  KPEG  treatment
   system  should  be initiated for  soils
   contaminated with halogenated  aro-
   matic compounds.

6.  Efforts should be initiated to delist the
   KPEG-treated  soil  judged  to be
   "clean"  per the requirements of the
   R&D permit.

  The full report was submitted in ful-
fillment of Contract  No. 68-03-3413, Work
Assignment   No.   1-2,   and   IAG
RW17933910 by PEI  Associates,  Inc.,
under the sponsorship of the  U.S.  Envi-
ronmental Protection Agency.

-------

-------
 M. L Taylor, J. A. Wentz, M. A. Dosani, W. Gallagher, and J, S. Greber are with PEI
   Associates, Inc., Cincinnati, OH 45246.
 T. D. Ferguson and C. J. Rogers are the EPA Project Officers (see below).
 The complete reports entitled "Field Applications of the KPEG Process for Treating
   Chlorinated Wastes" (Order No. PB 89-212  7241 AS: Cost: $17.00, subject  to
   change), and  "Comprehensive Report on  the KPEG  Process  for  Treating
   Chlorinated Wastes" (Order No. PB 90 163 643; Cost $23.00, subject to change)
   will be available only from:
         National Technical Information Service
         5285 Port Royal Road
         Springfield, V'A 221'61
         Telephone: 703-487-4650
 The EPA Project  Officers can be contacted at:
         Risk Reduction Engineering Laboratory
         U.S. Environmental Protection Agency
         Cincinnati,  OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati OH 45268 ,
      BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
Official Business
Penalty for Private Use $300
EPA/600/S2-90/026

-------