United States
Environmental Protection
Agency
Research and Development
                                                           Risk Reduction Engineering
                                                           Laboratory
                                                           Cincinnati, OH 45268
                                                           EPA/600/S2-90/038 Sept. 1990
w EPA       Project  Summary
                      Fuel-Efficient  Sewage Sludge
                      Incineration
                      Michael J. Walsh, Albert B. Pincince, and Walter R. Niessen
                         A study was performed to evaluate
                     the status of incineration with low fuel
                     use as a sludge disposal technology.
                     The  energy requirements, life-cycle
                     costs, operation and maintenance re-
                     quirements, and process capabilities of
                     four sludge incineration facilities were
                     evaluated. These facilities used a range
                     of sludge thickening, conditioning, de-
                     watering, and incineration technologies.
                         The results provided realistic cost
                     and energy requirements for a fuel-effi-
                     cient sludge incineration facility  and
                     highlighted operational, managerial, and
                     design features that contributed to the
                     fuel efficiency  of the incineration pro-
                     cess. This information provides a basis
                     for evaluating both the applicability of
                     sludge incineration in future facilities
                     and the  cost and energy efficiency of
                     existing  incineration facilities.
                         This Project Summary was devel-
                     oped by EPA's Risk Reduction Engi-
                     neering  Laboratory, Cincinnati, OH, to
                     announce key findings of the research
                     project that is fully documented in a
                     separate report of the same title (see
                     Project Report ordering  information at
                     back).

                     Introduction
                        To be considered an alternative sludge
                     technology  under the U.S.  EPA's Con-
                     struction  Grants program,  an incineration
                     system is required to be "self-sustaining" or
                     a net energy producer. In determining if a
                     system is a net energy producer, the energy
                     used for  sludge  dewatering, combustion,
                     and pollution control equipment is included.
                     The purpose of this study was to determine
                                     if, in fact, a fuel-efficient,  well-operated
                                     sludge incineration system could be "self-
                                     sustaining."
                                         The  energy requirements, life-cycle
                                     costs, operation and maintenance (O&M)
                                     requirements, and process capabilities of
                                     four sludge  incineration facilities were
                                     evaluated to determine the status of incin-
                                     eration with lowfuel use. The four facilities
                                     used a variety of sludge thickening, condi-
                                     tioning, dewatering, and incineration tech-
                                     nologies.

                                     Plant Information
                                         Detailed  information for the following
                                     four facilities is included as appendices in
                                     the Project Report.

                                     Upper Blackstone WPCF
                                        The Upper Blackstone Water Pollution .
                                     Control Facility (WPCF) in Millbury, MA is a
                                     secondary wastewatertreatment facility with
                                     an average capacity of 2,400 L/s (56 mgd).
                                     Currently, the facility treats an  average of
                                     1,400 L/s (33 mgd) and processes ap-
                                     proximately 27 dry metric tonnes (30 dry
                                     tons) of dewatered sludge cake per day.
                                        The solids handling processes include
                                     flotation thickening of the waste activated
                                     sludge (WAS), storage  and mixing of the
                                     WAS and primary sludge, polymer condi-
                                     tioning, beltfilterpress dewatering, multiple-
                                     hearth (MH) incineration, and ash disposal
                                     by landfilling.  The MH does not include an
                                     afterburnerchamberorany means of waste
                                     heat recovery.

                                     Metropolitan WPCF
                                        The Metro facility in St. Paul, MN is a
                                    secondary wastewatertreatmentfacility with

-------
an average  capacity of 11,000 Us (250
mgd). The plant currently receives an av-
erageof 9,600 Us (220 mgd). Approximately
163 dry metric tonnes (180 dry tons) of
dewatered sludge cake are processed at
the plant daily.
    Sludge  handling processes include
gravity thickening of the primary sludge,
flotation thickening  of the WAS, sludge
storage, heat  conditioning (Zimpro*) and
decanting of the WAS, blending of the pri-
mary sludge and WAS, polymer condition-
ing, roll press dewatering, and  MH  incin-
eration. The  MH incineration system in-
cludes a waste heat boiler system for heat
recovery and  a zero hearth afterburner
chamber for air emission control. Auxiliary
fuelisnotaddedtotheafterburnerchamber.

Duffln Creek WPCP
    The Duffin Creek Water Pollution
Control Plant (WPCP) in Pickering, Ontario
is a secondary wastewater treatment plant
with an average capacity of 2,100 L/s (48
mgd). Currently, the plant treats an average
of2,100 L/s (47 mgd) and processes about
24dry metrictonnes (27drytons) perday of
dewatered sludge cake.
    WAS is returned to the primary clarifi-
ars and co-settled with the primary sludge.
The solids handling processes include two-
stage anaerobic digestion, sludge storage,
polymer conditioning, diaphragm filter press
dewatering, fluidized bed (FB) incineration,
and ash disposal by landfilling.  The incin-
eration system has a hot windbox  design
and includes a waste heat boiler system for
energy recovery.

 Cranston WPCF
     The Cranston, Rhode Island WPCF is
a secondary wastewater treatment facility
with an average capacity of 1000 Us (23
mgd). The plant currently receives an av-
erage of 400 L/s (10 mgd) and processes
about 8 dry metric tonnes (9 dry tons) of
dewatered sludge cake daily.
     The solids handling processes include
dissolved air flotation thickening of WAS,
 gravity thickening of primary sludge, sludge
 storage and blending, chemical condition-
 ing, dewatering with fixed-volume filter
 presses, and MH  incineration.  The MH
 system includes an  external afterburner
 chamber and a separate scrubbing and
 heat recovery system. The furnaces were
 designed for operation in the pyrolysis
 (starved air) mode but have only operated in
' this manner during start-up.  No auxiliary
 fuel is added to the afterburner chamber.
    Mention of trade names or commercial
    products does not constitute endorse-
    ment or recommendation for use.
Cost and Energy Consumption
    The estimates of cost and energy con-
sumption presented here reflect plant op-
eration  under current  emission control
regulations.  Changes in these regulations
could significantly affect the cost and en-
ergy efficiency of the incineration process.
Exhaust gas temperatures for the three MH
furnaces ranged from  480°C (900°F) to
590°C (1100°F).  None of the MH systems'
employs afterburning of the furnaces ex-
haust gas stream, although two of the instal-
lations have an afterburner chamber incor-
porated into the incineration system. Each
of these facilities employs a venturi wet
scrubbing system.  If  new air emission
regulations require operation of an after-
burner for all MH systems, cost and energy
requirements for MH incinerationwill jn-  .
crease significantly. Requirements for more
sophisticated emissions control technolo-
gies will also increase the capital, labor, and
power costs for sludge incineration.

Basis of Analysis
     For the purpose of this evaluation, the
solids handling train included all processes
following the clarifiers  through the incin-
eration system, including airemission control
and waste heat recovery systems. The cost
of energy consumption required to treat the
sidestream flow that is returned to the head
of the plant was considered essentially equal
at each facility and therefore was not included
in this evaluation.  However, at the Metro
facility, the sidestream flow is of much higher
strength due to the heat conditioning process
and must be treated to reduce its strength
before it can be returned to the head of the
plant.   Because this  additional level  of
sidestream treatment  represents an addi-
tional cost to  the solids handling system,
costs and energy consumption associated
with the rotating biological contactors used
forsidestream treatment at the Metrofacility
were included in this evaluation.
     Plants with waste heat recovery sys-
tems must have an auxiliary  boiler system
to supplement steam generation from the
waste heat boilers during periods of low
sludge  production  or high steam demand.
The auxiliary boiler system is considered a
 part of the incineration/heat recovery system;
therefore, energy, fuel, and costs associated
with auxiliary boilers  were accounted for
 under the incineration system.
     Raw data for  each facility were ob-
tained through a review of available  plant
 records and discussions with plant  staff.
 For the purposes of the economic evalua-
 tion, both capital cost and O&M cost data
 were obtained for each unit process, and
O&M cost data were further broken down
into six components: (1) labor; (2) electric-
ity; (3) fuel (eitherfuel oil or natural gas); (4)
chemicals; (5) materials and supplies; and
(6) contracted services.
    Because of the lack of complete data
regarding actual metered  electrical con-
sumption, electrical consumption at each
facility was estimated by using a combina-
tion of  available  plant data and typical
consumption figures presented in industry
publications.

Economic Evaluation
    Variations in the unit costs for labor,
electricity, fuel, and other consumables
amongthefourfacilities were accounted for
by converting O&M costs to a common set
of unit costs.  Original capital costs were
updated to" 1988  dollars  using the Engi-
neering News Record cost index. Updated
capital costs were amortized assuming a40
year useful life for all structures, a 20 year
useful life for all equipment, and a discount
rate of 8%.
    The actual load on  a plant (versus
desig n capacity) can sig nif icantly affect O& M
costs. Forthis reason, a facility operating at
design  capacity should not be compared
directly with a facility that is  in the early
stages  of its design life.  Because of the
influence of the difference between load
and capacity, costs were evaluated  for op-
eration  at current loads and for operation at
capacity. To estimate the costs at capacity,
the capacity of each solids handling system
was estimated, and costs for operation at
capacity were developed.
    The capacity of each solids train was
taken to be the maximum amount of sludge
that the solids train could process while
 maintaining a reasonable amount of stand-
 by capacity.
     Each facility's expenditures for labor,
 electricity,   chemicals,  and  other
 consumables were scaled up to reflect op-
 eration at capacity. Costs were scaled up
 based upon the percent increase in sludge
 production, the increase in the number of
 units on-line under average conditions, or
 some other appropriate parameter.
     All costs presented below are on the
 basis of dewatered sludge cake, and are
 expressed as dollars per dry metric tonne
 (per dry ton). Based on the methodology
 presented  above, the  following  ranges
 represent a reasonable estimate of capital
 and O&M costs for a well-operated sludge
 incineration system operating at capacity,
 including furnaces, heat recovery system,
 air pollution control system, and ash dis-
 posal system.

-------
Annual
O&M        $ 77 to $ 99  ($ 70 to $ 90)
Amortized
Capital       $110 to $138 ($100 to $125)
Total Annual
 Cost       .$187to$237 ($170to$215)

    The following ranges represent a rea-
sonable estimate of capital and O&M costs
for a complete, well-operated incineration
solids train operating at capacity, when the
thickening and dewatering processes are
also included.

Annual
O&M       $198 to $220 ($180 to $200)

Amortized
Capital      $220 to $253 ($200 to $230

Total Annual
 Cost       $418 to $473 ($380 to $430)


Limitations on Cost Estimates
    It is important to recognize the limits of
these cost estimates.   Capital costs are
presented on the basis of dollars per ton of
instal led capacity, allowing for a reasonable
amount of reserve capacity.  It  must be
recognized that capital costs  can  vary sig-
nificantly due to site-specific factors such as
subsurface conditions, local materials costs,
size constraints, constructions market
conditions, and the amount of redundancy
built into the system. These factors make it
difficult to generalize about capital  costs;
therefore the capital costs figures presented
here-should be applied carefully.
    Estimates of O&M costs were  based
upon operation  at system capacity.  O&M
costs can vary significantly over the life of a
facility depending on thedifference between.
initial and design year sludge quantities, the
use of multiple units rather than one large
unit in equipment selection, and otherdesign
factors.  A system that operates at a fairly
constant sludge feed throughout its design
life  will see little change  in per ton O&M
costs.
    Actual per ton O&M  costs for sludge
incineration at the four subject  facilities
ranged from 6% to 186%  greater than the
per ton  costs estimated  for  operation at
capacity.  The fluctuation in per ton costs
over the design life of an  incineration sys-
tem should be considered when using the
figures presented in this study.

Energy Evaluation Summary
    Energy efficiency  was examined  on
several levels, which were defined by how
energy inputs and outputs for the system
were defined. The following generalizations
were made regarding the energy consump-
tion of a well-operated facility.

Level A -
     Based on the auxiliary fuel consumed
within the furnaces only.
  -  Total annual auxiliary fuel consump-
     tion within the furnace itself should
     range from 29 to 38 L fuel/dry metric
     tonne of sludge cake processed (7 to
     9 gal/dry ton).
  -  Frequent downtime (whether sched-
     uled or unscheduled) increased the
     auxiliary fuel consumption by a factor
     of 10.
Level B -
    In addition to Level A, auxiliary fuel use
by the heat/auxiliary boiler equipment, the
emission control equipment, and the ash
disposal system was included. When steam
was produced and used outside of the incin-
eration system, it was included as an energy
output.

  -  When -a waste heat recovery system
     was included in the incineration sys-
     tem, the incineration system could be
     a net energy producer when only aux-
     iliary fuel (no electricity) was consid-
     ered an energy  input  to the system.

Level C -
 .   In addition to Level B, electricity  for
equipment was also included as an energy
input.
  -  An  incineration  system with a waste
     heat recovery system could still  be
     energy producer when operated at a
     maximum efficiency. Two  facilities
     approached the goal of  being a net
     producerattheircurrent loading rates.
     It is possible that, if  these facilities
     were  operating  at capacity, the  in-
     crease in energy efficiency that  re-
     sults from complete equipment utili-
     zation might make those facilities net
     energy producers.

Level D -
    In addition to Level C, energy inputs to
the sludgeconditioning/dewatering system
were included.
  -  When the definition of the incineration
     system was  expanded to include the
     sludge conditioning/dewatering sys-
     tem, the goal of net energy production
     by  the incineration system did  not
     appear achievable.

Level E -
    In addition to Level  D, energy to the
entire solids handling train was  included.
 Auxiliary fuel, electricity for equipment, and
 electricity for general building requirements
 were considered energy inputs.

   -   Total energy consumption for a solids
      train using sludge incineration varied
      widely depending on the thickening
      and dewatering  technologies  em-
      ployed. Total energy consumption for
      a well-operated solids train ranged
      from 5.8 to 10.4 million kJ/dry metric
      tonne (5 to  9 million Btu/dry ton) of
      sludge cake processed.

     Overall, a variety of technologies could
 achieve  energy-efficient  sludge  incinera-
 tion. The most complex systems proved to
 be very energy efficient under each set of
 conditions evaluated. The simplest system
 also proved to be  very  energy  efficient,
 especially in terms of overall energy con-
 sumption by the entire solids train.

 Keys to Fuel-Efficient Operation
     Although  each of the facilities  had
 several features  that contributed to the
 success of its own sludge incineration pro-
 cess, there were some common operational
 and management features that operators at
 each facility agreed were essential to af uel-
 efficient sludge incineration system.

 Sludge Equalization
     A uniform flow of sludge to the incinera-
 tion system was essential, both in terms of
 quantity and quality.  Each time the quality
 or quantity of the furnace feed changed, the
 operator had to adjust the excess air level,
 rabble arm rotation speed,  auxiliary  fuel
 use, or some other operational variable to
 maintain complete combustion conditions
 instead of concentrate  on fine tuning the
 incineration system.  .
     To create a uniform furnace feed, some
 sludge storage and mixing should be pro-
 vided within the solids train. Sludge storage
 also allows the incineration system to be
 taken off-line for regular maintenance and
 equipment calibration.

 Staff Motivation/Training
    The real key to a  successful sludge
 incineration facility was in the plant O&M
 staff. An incineration system is a relatively
 complex system to operate and maintain.
 The operations staff had to understand the
 effect that changes in operational variables
 had  on the combustion process, and the
 effect that the performance of the preceding
 solids handling processes had on  the
furnace's operation. The maintenance staff
 had  to have the  manpower  and skill to
 provide regular maintenance on a variety of
 equipment.  Management had to  create a
positive workingenvironmentthat motivated
the plant staff.
                                                                             U. S. GOVERNMENT PRINTING OFFICE: 1990/748-012/20099

-------
    Communication among the operators
of all of the solids handling processes re-
garding changing sludge conditions was
essential. Management encouraged this by
implementing programs such as a rotating
employee program or by forming problem
solving committees comprised of engineers,
operators and maintenance personnel from
throughout the solids handling facility.
    Management should encourage  the
plant staff to pursue advanced  levels of
training through  in-house programs,  op-
eratorcert'rfication programs, graduate level
engineering programs, and activity in pro-
fessional organizations and societies.

Maintenance Program
    A  strong  maintenance program in-
creased the cost-effectiveness and energy
efficiency of the incineration process; it:
  -  reduced auxiliary fuel use by minimiz-
     ing  unscheduled maintenance shut-
     downs;
  -  minimized  costs by extending  the
     useful life of furnace components; and
  -  provided the operators with accurate
     information  by keeping  the instru-
     mentation and monitoring equipment
     operable and up-to-date.
    Over the life of a facility, it appeared to
be more economical to pay the annual cost
of proper preventive maintenance than to
pay for major repairs on a periodic basis.

Conclusions
  1. If all energy inputs were considered
     (Level D), none of the incineration
     systems studied could be defined as
     "self-sustaining." These systems did,
     however, provide several keys to fuel-
     efficient operation:
       A uniform sludge flow to the incin-
      eration system was essential, both in
      terms of quantity and quality.
       the real key to a successful sludge
      incineration facility was in the plant
      operations and maintenance staff.
 ."'-   a strong maintenance program in-
      creased the cost-effectiveness and
      energy efficiency of the incineration
      process.
  2. For a well operated system, total an-
     nual auxiliary fuel consumption within
     the furnace itself should range from
     29 to 38 L fuel/dry metric tonne of
     sludge cake processed (7 to 9 gal/dry
     ton).  Frequent downtime (whether
     scheduled orunscheduled), however,
     increased the auxiliary fuel consump-
     tion by a factor of 10.
  3.  A reasonable estimate of total annual
     cost (including amortized capital and
     O&M) for a well-operated sludge in-
     cineration system operating at capac-
     ity, including furnaces, heat recovery
     system, air pollution control system,
     and ash disposal system ranged from
     $187 to  $237 per dry metric tonne
     ($170 to $215 per dry ton) (see note
     on limitations above).
  4.  A reasonable estimate of total annual
     cost (including amortized capital and
     O&M) for a complete well-operated
     solids train, operating at capacity, in-
     cluding thickening, dewatering, and
     incineration, ranged from $418to $473
     perdrymetrictonne($380to$430per
     dry ton) (see rioteon limitations above).
    The full report was submitted in partial
fulfillment of Contract No. 68-03-3346 by
Camp, Dresser & McKee, Inc., under the
sponsorship of  the  U.S. Environmental
Protection Agency.
 MichaelJ. Walsh, Albert B. Pincince, and WalterR. Niessen are with Camp, Dresser
     & McKee, Inc., Boston, MA 02108.
 Donald S. Brown is the EPA Project Officer (see below).
 The complete report, entitled "Fuel-Efficient Sewage Sludge Incineration" (Order No.
     PB90-261 827/AS ; Cost: $39.00, subject to change) will be available only  from:
         National Technical Information Service
         5285 Port Royal Road
         Springfield,  VA 22161
         Telephone: 703-487-4650
 The EPA Project Officer can be contacted at:
         Risk Reduction Engineering Laboratory
         U.S. Environmental Protection Agency
         Cincinnati, OH 45268
United States
Environmental Protection
Agency
Center for Environmental
Research Information
Cincinnati, OH 45268
              BULK RATE
         POSTAGE & FEES PAID
                  EPA
            PERMIT No. G-35
Official Business
Penalty for Private Use $300
 EPA/600/S2-90/038

-------