United States
                     Environmental Protection
                     Agency
Risk Reduction
Engineering Laboratory
Cincinnati, OH 45268
                     Research and Development
EPA/600/S2-91/003 Apr. 1991
&EPA        Project Summary

                      Assessment of Asbestos
                      Removal  Carried  Out  Using
                      EPA  Purple  Book Guidance
                     John R. Kominsky, Ronald Freyberg, Robert S. Amick, and
                     Thomas J. Powers
                        An evaluation was made of airborne
                     asbestos data collected before, during,
                     and after removal of spray-applied as-
                     bestos-containing fireproofing at three
                     university  buildings. Each abatement
                     project was conducted in accordance
                     with the work practices and procedures
                     recommended by the U.S. Environmen-
                     tal Protection Agency in "Guidance for
                     Controlling Asbestos-Containing Mate-
                     rials in Buildings," (the  Purple Book).
                        Containment barriers should be de-
                     signed so they effectively prevent a sig-
                     nificant increase in airborne concentra-
                     tions outside the work area during and
                     after abatement. An increase in asbes-
                     tos concentration outside the work area
                     could allow an abatement  site  to be
                     cleared when the level  inside the con-
                     tainment is similarly elevated. This holds
                     true whether phase contrast microscopy
                     or transmission electron microscopy is
                     used for the clearance.
                        This Project Summary was devel-
                     oped by EPA's Risk Reduction Engi-
                     neering Laboratory, Cincinnati, OH,  to
                     announce key findings of the research
                     project that is fully documented in a
                     separate report of the  same title (see
                     Project Report ordering information at
                     back).


                     Introduction
                        The Office of  Pesticides and Toxic
                     Substances of  the U.S. Environmental
                     Protection Agency (EPA) provides guidance
                     and information on the identification of as-
                     bestos-containing materials in buildings and
                     on the abatement actions for potential as-
                     bestos hazards.
                        The EPA guidance in  effect at the time
                     of this study, entitled "Guidance for Con-
                     trolling Asbestos-Containing Materials in
                     Buildings," EPA 560/5-85-024 (June 1985),
                     known as the "Purple Book," contains rec-
ommendations for work practices and pro-
cedures to be used in performing asbes-
tos-abatement projects. The recommen-
dations include 1) constructing  airtight
plastic containment barriers around the
work area, 2) using negative-pressure air
filtration systems, 3) wetting all asbestos-
containing material (ACM) prior to its re-
moval, 4) containerizing of ACM and as-
bestos-contaminated debris while it is wet,
5) conducting rigorous postabatement
cleanup with wet cleaning and high-effi-
ciency  particulate air  (HEPA)  filtered
vacuuming techniques, and 6) performing
visual inspections and  air monitoring  to
determine asbestos-abatement completion
and work area decontamination.
   The EPA guidance document recom-
mends that air monitoring for post-abate-
ment clearance be conducted after the
work area has passed a thorough visual
inspection. According to the EPA "Purple
Book" guidance, two methods for measur-
ing airborne asbestos can be used: trans-
mission electron  microscopy (TEM) and
phase contrast microscopy (PCM). If  TEM
is used, at least five samples from inside
and five samples from outside each homo-
geneous work area should be collected.
The average of the work-area concentra-
tions should be statistically (t-test) no larger
than the average of measured concentra-
tions outside the  work area.  If  PCM  is
used, at  least five samples from inside
each homogeneous work area should be
collected, and none of the concentrations
should be higher than the reliable limit of
quantitation  (approximately 0.01 f/cm3).
Although  the Purple Book recommends
TEM as the method of choice based on  its
sensitivity to smaller fibers and specificity
for asbestos, the decision to select an air
sampling protocol  for  determining  suc-
cessful abatement completion is left to the
abatement project manager.  Thus, the
determination of  work-area cleanliness

-------
depends on which method is chosen for
measuring asbestos fibers.
   Although the Purple Book contains the
latest  EPA-recommended  guidance  for
work practices and procedures to be used
in performing asbestos-abatement projects,
it did not represent the latest EPA guid-
ance for clearance testing of an abatement
site at the time the study report was pre-
pared. This  guidance is presented in the
final rule (October 30, 1987; 52 FR41826)
for the Asbestos  Hazard Emergency Re-
sponse Act  (AHERA) of 1986.  The final
rule establishes TEM as the preferred ana-
lytical method to  be  used for analysis of
samples taken for clearance air monitoring
and also specifies a procedure for deter-
mining when an asbestos site is sufficiently
clean for the critical  containment barriers
to be  removed. The procedure  requires
the collection of five  samples from inside
and five samples  from outside the  abate
ment work area, but not necessarily outside
of the building. The average of the concen-
trations inside the work area must be sta
tistically (Z-test) no larger than the average
of measured concentrations outside the
work area.

Study Objectives
   The following were the primary  objec-
tives of the study:
     To  determine the effectiveness of
     containment barriers in preventing the
     release of asbestos fibers outside of
     the work area.
     To determine the effectiveness of fi-
     nal cleanup procedures.
 •   To evaluate the TEM clearance crite-
     ria  for both the t-test and, to the
     extent that the data allow, the Z-test.
     To determine if  an abated site  meets
     both TEM and PCM clearance crite-
     ria  and to evaluate whether PCM
     provides false positives for clearance
     decisions.
     To  determine  if 0.8-u.m pore-size
     mixed  cellulose ester  and 0.4-fim
     pore-size  polycarbonate membrane
     filters produce equivalent estimates
     of airborne asbestos concentrations.

Project Description

Site Selection
   The three study sites, which were all
school buildings, were chosen based on
the following selection criteria:
 1.   No significant abatement of ACM had
     occurred inside the building site within
     the last 12 mo.
 2.   Each abatement site was in a differ-
     ent geographical location or building.
 3.   The  abatement project  involved the
     removal of spray-applied  asbestos-
      containing fireproofing from structural
      members and decking.
  4.   The abatement project was governed
      by written specifications that comply
      with the minimum  requirements  in
      the  latest EPA guidance document
      (the Purple Book).
  5.   The building owner and abatement
      contractor agreed to cooperate with
      the  EPA and to  provide access  to
      selected areas of the building.

 Abatement Programs
   The abatement contractors prepared
 the work  areas,  removed  the asbestos-
 containing fireproofing, and conducted de-
 contamination activities in accordance with
 the latest EPA guidance (the Purple Book).
 The abatement activities were performed
 in three distinct stages:  preparation, re-
 moval, and decontamination.  Work areas
 were prepared by removing  all  movable
 objects;  turning off the ventilation  and
 electrical systems; sealing off all  air ducts
 and openings; covering the floors, walls,
 and immovable objects with plastic sheet-
 ing; installing  HEPA-filtered, negative-
 pressure  air  filtration  systems; and con-
 structing two entrance and egress con-
 tamination-control facilities—one  with
 showers and change rooms for personnel
 and the other for waste-material handling.
 Suspended  ceilings and carpeting  were
 either removed and disposed  of as con-
 taminated waste or cleaned and disposed
 of by conventional means.
   Workers wearing full protective cloth-
 ing and  approved respiratory protection
 removed the fireproofing by first wetting
 the material with an amended water solu-
 tion and then  scraping it off. The asbestos-
 containing debris was placed in double  6-
 mil polyethylene bags and disposed of  at
 an approved sanitary landfill. All substrate
 surfaces from which asbestos was  removed
 were wire-brushed and wet-wiped repeat-
 edly to remove as much of the fireproofing
 material as possible. All stripped or poten-
 tially contaminated surfaces were sprayed
 with an  asbestos sealant to bond any re-
 sidual fibers to the substrate. During de-
 contamination of the work area,  all loose
 debris was removed, as was the plastic
 sheeting from the walls and floors. Decon-
 tamination also involved two complete final
 cleanups entailing  wet-wiping  or mopping
 of the walls and floors. At Site 1, an 8-h
 period elapsed between the final cleanings;
 at Site 2,  a 24-h period elapsed between
 cleanings. The work areas  were then vi-
 sually inspected to assure the absence of
 debris and visible dust on surfaces. When
the work area passed  a thorough visual
 inspection and air monitoring showed that
the total fiber concentrations  were  less
than 0.01 f/cm3 (by phase contrast micros-
copy), all remaining critical containment
barriers  (on windows,  doors,  and vents)
were removed, and the area was consid-
ered acceptable for reoccupancy.

Sampling Strategy
   At each of the three abatement sites,
area  air samples were collected before,
during,  and after removal of  the spray-
applied  asbestos-containing fireproofing.
Samples were collected inside the work
area (i.e., the abatement area); outside the
work area (i.e., the perimeter area outside
the abatement area); and from the ambi-
ent air (i.e., outside of the building). Side-
by-side samples were collected at each
location for separate PCM  and  TEM
analysis.
   The preabatement  air samples were
collected inside and outside the work area
before the containment barriers were con-
structed. The  sampling was  conducted
under static conditions (i.e., activity in the
area was minimal and  the heating, venti-
lating, and air-conditioning system was not
in operation).
   During the removal phase of the abate-
ment, air samples were collected outside
the work area at scheduled  intervals and
under static sampling conditions.
   The postabatement air samples out-
side the work  area also  were collected
under static sampling conditions. The
postabatement air samples inside the work
area  were collected  under aggressive
sampling conditions. The aggressive sam-
pling conditions were created by sweeping
all horizontal and vertical surfaces with a
hand-held,  electric-powered,  leaf blower
and then using floor fans to generate con-
tinuous air turbulence throughout sampling
period.

Sampling Methods
   Two side-by-side area air samples were
collected at each sampling location inside
and outside the work area and outdoors.
Each  pair of samples consisted of a 25-
mm, 0.4u.m pore size, Nuclepore* polycar-
bonate filter and a 25-mm,  0.8-u.m pore
size, Millipore mixed cellulose  ester filter.
Each 25-mm filter was mounted on a 5-jim
pore size, mixed cellulose ester,  backup
diffusing  filter  and cellulose  support pad
and was contained in a three-piece cassette
with  a 50-mm conductive cowl and face
cap. The filter cassettes were positioned 4
to 5 ft above the floor and were arranged  in
a  horizontal line by clipping them  to  a
Mention of trade names or commercial products does
not constitute endorsement or recommendation for

-------
sturdy stand. The filter cassettes were
placed approximately 5 cm apart and were
oriented in the  same direction with  the
filter face angled slightly downward. Dur-
ing  sampling, the face cap was removed
to expose the full face of the filter to  the
air stream.
   The filter assembly was attached to an
electric-powered vacuum pump. An inline
calibrated precision rotameter was used
to  regulate the  air-flow rate through  the
filter assembly at 8 to 12 L/min. The air
samples  were  generally collected for a
period of approximately 6 to 9 h to achieve
a minimum air volume of 3,000 L for each
sample; however, a  limited  number of
samples  were  collected  for periods  ex-
tending  up to   17 h, which  yielded  air
volumes of approximately 11,000 L.

Methods of Analysis

Phase-Contrast Microscopy
   The mixed cellulose ester membrane
filters  were analyzed by PCM, and  the
polycarbonate  membrane filters were
analyzed by TEM.  The PCM and TEM
analytical protocols are presented in  the
Quality Assurance Project Plan  (QAPP)
prepared for this research study.
   The mixed cellulose ester filters were
prepared and analyzed for total fibers by
PCM in accordance with National Institute
of Safety and Health Method 7400.

Transmission Electron
Microscopy (TEM)
   The polycarbonate membrane filters
were analyzed by TEM. The  filters were
prepared and analyzed for asbestos fibers
by TEM in accordance with the Yamate
Revised Method. A TEM Level II analysis
was performed on  all polycarbonate
samples collected in this study.

Quality Assurance
   The QAPP contains the complete  de-
tails of the quality assurance  procedures
followed during  this research project.
   Specific quality assurance procedures
used to ensure the accuracy and precision
of  the TEM analysis of  air samples in-
cluded the use of lot blanks, field blanks,
and replicate TEM analyses.
   Lot blanks are unused filters submit-
ted for prescreening analysis for back-
ground contamination before  the start of
field work to determine the integrity of the
entire lot of filters purchased for EPA field
studies. Analysis of 100 lot blanks showed
an average background contamination of
1.8 asbestos structures per 10 grid open-
ings. The lot of filters was  subsequently
considered "acceptable" for use because
the average asbestos structure count did
not exceed 3 structures per 10 grid open-
ings.
   Field  blanks are filters taken into the
field and handled  in the same  manner as
exposed  air samples to check for contami-
nation  that might not be  a result of  air
sampling. A total  of 27 field blanks were
collected at Sites 1, 2, and 3. Because the
average  asbestos structure count  did not
exceed 3 asbestos structures per  10 grid
openings at any site, background contami-
nation was not considered a problem.
   Replicate  sample analysis  provides a
means of quantifying  analytical variability
introduced  by the filter preparation proce-
dure and refers to the analysis  of different
filter preparations  from the  same sample.
The replicate analyses showed no signifi-
cant tendency toward higher or lower struc-
ture counts.

Statistical Analysis Methods
   Nonparametric statistical methods were
selected  to analyze the data collected dur-
ing this study. Nonparametric  procedures
analyze the relative ranks of the data rather
than the actual data values, and  they do not
require any assumptions regarding the form
of the  underlying  statistical distribution  of
the data.
   The Kruskal-Wallis one-way analysis
procedure was used to examine the differ-
ences between airborne asbestos concen-
trations in the perimeter area before, dur-
ing,  and after abatement.  The Wilcoxon
rank sum test was used to  make all other
comparisons.
   The TEM clearance comparison was
made with the Student's t-test as recom-
mended  in the Purple Book,  and to the
extent  the data allowed, with  the Z-test
required  in the AHERA final rule. Because
all three sites used negative-pressure  air
filtration systems during abatement and the
makeup or "background"' air came from other
parts of  the  building  rather than  directly
from outdoors, the postabatement samples
inside the work area were compared with
the postabatement samples outside the work
area but  within the building.

Results
   Average airborne asbestos  concentra-
tions and respective sample sizes are pre-
sented in Table 1. The  results are pre-
sented for Sites 1, 2, and 3 by abatement
phase  (before, during, and  after);  location
of sample (inside the work area,  outside the
work area, and ambient); and  microscopy
technique (TEM and  PCM). Figure 1 pre-
sents average airborne asbestos concen-
trations graphically for Sites 1, 2, and 3
according to abatement phase and sample
location. The study report includes a de-
tailed presentation and discussion of the
results for  each  site, including plots  of
structure lengths and diameters determined
by TEM analysis.

Conclusions
   The following principal conclusions from
this study are presented for  each study
objective.

Comparison of Concentrations
Outside the Work Area
   Asbestos concentrations measured
outside the work area before,  during, and
after abatement at Sites 1 and 3 did not
vary significantly. This indicates that the
containment  barriers at these two sites
were effective in preventing the release of
asbestos fibers outside the work area.  At
Site 2, however, the asbestos concentra-
tions measured after abatement were sig-
nificantly  higher than those measured be-
fore and  during abatement. The average
asbestos concentration  after abatement
was approximately 80 times higher than
the average  concentration before abate-
ment. These elevated asbestos concen-
trations suggest that 1) the  containment
barrier was not  effective at  this site;  2)
work practices recommended in the Purple
Book were not followed; or 3) asbestos-
containing material outside the abatement
containment was disturbed, which resulted
in elevated asbestos concentrations in that
area.

Comparison of Work Area
Concentrations Before and After
Abatement
   At Site 1, asbestos concentrations did
not increase significantly after abatement.
At Sites 2 and 3,  however, asbestos con-
centrations did increase significantly after
abatement.
   Final cleanup procedures can effectively
control postabatement airborne asbestos
concentrations inside the work area. The
higher postabatement concentrations may
be attributable to improper or inadequate
implementation of final cleanup procedures,
or they may be due to sampling conditions
(i.e., static conditions in the preabatement
phase versus aggressive conditions in the
postabatement phase, or both).

TEM Clearance Comparisons
   Sites 1, 2, and 3 passed the TEM clear-
ance  criteria for  both  the t-test recom-
mended  in the Purple Book and Z-test
specified in the final rule under AHERA.  At
Site 2, the  increase in the postabatement
asbestos concentration outside the work

-------
   Table 1.  Average Airborne Asbestos Concentrations Before, During, and After Abatement at Sites
           1, 2, and 3
   Location


   Ambient
   Perimeter
   Work area
   Ambient
   Perimeter
   Work area
   Ambient
   Perimeter
   Work area
               Average Airborne Asbestos Concentration (s/crrfySample Size
         Site 1                    Site 2                    Site 3
   JEM        PCM         JEM        PCM        JEM         PCM
                      Preabatement phase
  0.0041/3     0.0007/3     0.0011/5      0.0012/5     0.0000/3     0.0020/3
  0.0052/12    0.0003/12    0.0030/5      0.0014/5     0.0008/3     0.0040/3
  0.0091/10    0.0000/10    0.0367/5      0.0012/5     0.0001/8     0.0020/8
  0.0034/4
  0.0089/31
  0.0067/4
  0.0057/5
  0.0056/5
       Durinq-abatement phase
0.0008/4    " 0.0005/5     0.0010/5
0.0023/31    0.0304/31     0.0015/31
                                                   0.0129/49    0.0106/61
0.0002/5
0.0022/5
0.0015/5
                                  Postabatement phase
0.2410/7
0.3082/5
0.0027/7
0.0024/5
0.0000/3
0.0028/2
0.0023/7
0.0107/3
0.0074/5
0.0080/7
   ' Dashes indicate that no samples were collected.
                      Average Airborne Asbestos Concentration (s/cm3)
   0.35


    0.3


   0.25


    0.2


   0.15


    0.1


   0.05
                                                     r Work Area
                                                     Perimeter
                                                               Outdoor
        Pre  Dur  Post
           Site 1
               Pre  Dur Post
                  Site 2
                    Pre  Dur  Post
                       Site 3
Figure 1.
Mean airborne asbestos concentrations before, during, and after abatement for
samples analyzed by TEMat sites 1, 2, and 3.
area,  as noted in the preceding discus-
sion, enabled the site to pass both clear-
ance tests. Conversely, a comparison of
the postabatement  concentrations inside
the work area with ambient concentrations
resulted in the site  failing both clearance
tests. This single incident points up a seri-
ous  limitation  in  the comparison  of
postabatement  asbestos concentrations
                              inside the work area with those outside the
                              work area.
                                 Both the Purple Book and AHERA final
                              rule clearance strategies could allow an
                              abatement  site to be cleared despite the
                              fact that the airborne asbestos concentra-
                              tion outside the work area  is significantly
                              higher than preabatement  building  con-
                              centrations.
Comparison of TEM and PCM
Clearance Test Results
   Sites 1,2, and 3 passed the TEM clear-
ance criteria  based  on  both  the  t-test
(Purple Book) and the Z-test (AHERA final
rule). Sites 1  and 2 also passed the PCM
clearance criterion (0.01  f/cm3); however,
Site  3 failed. Thus, this study  identified a
false positive PCM clearance  situation
where a site failed PCM and passed TEM.
   The differences in conclusions reached
by the two protocols are probably due to
the  limited ability of PCM to  distinguish
asbestos from nonasbestos materials. Air-
borne fiber concentrations  estimated by
PCM reflect total fiber concentrations, not
just  asbestos  fiber concentrations; there-
fore, they may lead to erroneous conclu-
sions regarding abatement clearance.

Comparison of Concentrations
Measured on Mixed Cellulose Ester
and Polycarbonate Filters
   The TEM analysis of 69 paired 0.8-jim
pore size mixed  cellulose ester and 0.4-
u,m  pore  size polycarbonate  membrane
filters revealed a statistically significant dif-
ference in asbestos concentrations on the
two filter types. This comparison was made
because the guidance  in the Purple Book
allowed for the  choice of either type of
filter. Asbestos concentrations on 0.4-jim
pore size polycarbonate filters were sig-
nificantly higher than those on 0.8-u,m pore
size  mixed cellulose ester filters. The two
types of filters do not produce equivalent
estimates of airborne asbestos concentra-
tions. The difference in asbestos concen-
trations may be  due to the differences in
the pore sizes or in the chemical composi-
tion  of the two types of filters.

Recommendations
   Because the  elevated levels  outside
the containment area at Site 2 would have
allowed a contaminated site to pass under
the AHERA sampling strategy, monitoring
of the contamination level outside the work
area during abatement or after abatement
should  be  strongly considered  as a pre-
requisite to using this area as a clearance
reference point. If additional monitoring is
not considered reasonable,  the guidance
should be revised to emphasize the impor-
tance  of  the  location  of the "outside"
samples.
   The full report was  submitted in  fulfill-
ment of EPA Contract 68-03-4006 by PEI
Associates, Inc.,  under the sponsorship of
the U.S. Environmental Protection Agency.

-------

-------

-------

-------
  John R. Kominsky, Ronald Freyberg, and Robert S. Amick are with PEI Associates, Inc.,
    Cincinnati, OH 45246.
  Thomas J. Powers  (also the EPA Project Officer, see below) is with the Risk Reduc-
    tion Engineering Laboratory, Cincinnati, OH 45268.
  The complete report, entitled "Assessment of Asbestos Removal Carried Out Using
    EPA Purple Book Guidance," (Order No. PB91-148338/AS; Cost: $17.00, subject to
    change) will be available only from:
          National Technical Information Service
          5285 Port Royal Road
          Springfield, VA 22161
          Telephone: 703-487-4650
  The EPA Project Officer can be contacted at:
          Risk Reduction Engineering Laboratory
          U.S. Environmental Protection Agency
          Cincinnati, OH 45268
United States
Environmental Protection
Agency
Center for Environmental Research
Information
Cincinnati, OH 45268
      BULK RATE
POSTAGE & FEES PAID
 EPA PERMIT NO. G-35
Official Business
Penalty for Private Use $300
EPA/600/S2-91/003

-------