United States
                   Environmental Protection
                   Agency
Air and Energy
Engineering Research Laboratory
Research Triangle Park NC 27711
                   Research and Development
EPA/600/S7-90/009 July 1990
&EPA         Project  Summary
                   Comparison  of  West
                   German  and  U.S.  Flue  Gas
                   Desulfurization  and  Selective
                   Catalytic  Reduction  Costs

                   T.E. Emmel, M. Maibodi, and J. A. Martinez
                    By the end of the 1980s, more than
                  45,000 MWe and, by early 1990, more
                  than 34,000 MWe of coal- and oil-fired
                  utility boilers in the Federal  Republic:
                  of Germany  (FRG) will  have been
                  retrofitted with  flue gas  desulfuriza-
                  tion (FGD) and selective  catalytic
                  reduction (SCR), respectively. This
                  report documents a comparison olf
                  the actual cost of retrofitting FGD and
                  SCR on FRG boilers to cost  es-
                  timating procedures used in the  U.S.
                  to estimate the retrofit of these con-
                  trols on U.S. boilers. The estimated
                  capital  costs of FGD  using the  U.S.
                  procedures compared well to  the
                  reported capital cost for  the 13  FRG
                  boilers  evaluated. The difference be-
                  tween the estimated and actual costs
                  was -8 to  12%. However, there  are
                  significant design differences  be-
                  tween U.S. FGD systems built to com-
                  ply  with New Source Performance
                  Standards  (NSPS) and the FRG
                  systems. These  differences,  which
                  result in significantly  lower capital!
                  costs on a dollar per  kilowatt basis
                  for  the FRG systems, include: no
                  spare absorber modules, large scrub-
                  ber modules, and smaller sorbenl:
                  and waste handling systems due to
                  the low sulfur coals  burned  in  the
                  FRG. The estimated capital cost olf
                  SCR using the U.S. procedures  also
                  compared well to the reported  capital
                  costs for the nine  FRG boilers
                  evaluated. The  difference  was  be-
                  tween -5 to 16%. However,  the  U.S.
                  procedures were modified to  reflect:
                  the catalyst volume and cost used in
                  the FRG boilers. The previous  U.S.
estimates used larger catalyst  vol-
umes and higher catalyst costs,  and
incorporated  process contingences
that were not used in this study to
develop the SCR cost estimates.
   This  Project  Summary was
developed by EPA's Air and Energy
Engineering Research  Laboratory, Re-
search Triangle Park, NC, to announce
key findings of the research project
that is fully documented in a separate
report of the  same title (see Project
Report ordering information at back).


Introduction
  In  the  mid-1980s, the Federal
Republic of Germany (FRG) enacted leg-
islation requiring significant reductions in
sulfur dioxide (SOa) and nitrogen oxides
(NOx) from existing large utility boilers. As
a result, by 1988 more than 45,000 MWe
of conventional lime/limestone (L/LS) flue
gas desulfurization  (FGD) and lime spray
drying  (LSD)  FGD systems had been
installed, and by 1990 more than 34,000
MWe of  selective  catalytic reduction
(SCR) systems will have been installed.
The reported capital costs for the L/LS-
and LSD-FGD systems appear to be
much lower than  the  actual costs of
similar systems in the U. S. The reported
capital costs of the SCR systems are also
much lower than the estimated cost of
applying SCR systems to U.S. utility
boilers.
  This report  documents the results of
an analysis for comparing estimated ver-
sus actual capital costs for FGD and  SCR
systems installed at several utility boilers
in the FRG.

-------
Methodology

   The  effort  was  conducted in two
phases. In Phase 1,  site visits were con-
ducted  at  five coal-fired utility  boiler
power  plants in the FRG. Two  of the
plants (Walheim and Mannheim) were set
up by the Institute for Industrial Produc-
tion  (IPP); two  other  plants  (Nieder-
aussem and Scholven) were visited  as
part of a North Atlantic Treaty  Organiza-
tion (NATO) committee meeting  on the
Control  of Air Pollution from  Coal Com-
bustion, and the fifth plant (Ibbenbueren)
visit  was set up  by EPA's  contractor.
Table 1 summarizes the boiler and coal
characteristics for the  five plants visited
and evaluated under this study.
   Prior to the site visits, a questionnaire
was sent to each utility company with the
information  needs  of the study. This
questionnaire provided the basis  for the
data gathering effort conducted  during
the plant visits. This  data collection effort
focused on obtaining capital cost informa-
tion, general  design and  operating
parameters, plot plans, and aerial photo-
graphs of the FGD and SCR systems.
   In Phase 2, the collected  information
was  used  to  develop cost estimates
based  on  U.S.  cost estimating  proce-
dures. The procedures used were devel-
oped under a National Acid Precipitation
Assessment Program  (NAPAP) project
that estimated the cost and performance
of SOg and NOX controls at existing coal-
fired utility boilers. The FGD  procedures
were based on the Electric  Power Re-
search Institute (EPRI) report. The  SCR
cost estimating  procedures were based
on an  EPRI report and  a  Tennessee
Valley Authority (TVA) report funded by
U.S. EPA. The capital cost  estimates
developed  using  the  U.S. procedures
were then  compared to  the  reported
costs  for  plants  evaluated  under this
study. This comparison was conducted to
identify  capital cost  differences, reasons
for the differences, and changes needed
to the cost estimating procedures.

Summary of FGD Results
   Table 2  summarizes the capital cost
comparison for  L/LS- and LSD-FGD for
four of the plants. Capital  cost  estimates
were  not  available for  the individual
boilers  at the  Scholven plant. The
estimated capital costs  for L/LS-FGD
versus  the  reported actual costs were
very close, having an absolute difference
between -8 and 12%.  Likewise, the
average difference for  the two  LSD-FGD
systems was 12%. The conversion rate
used for this analysis was 2  deutsche
Table 1.  German Plant Visits
                 Fuel      Size    Boiler
   Plant/Units     Typea    (MWe)   Typeb
                         SCR    SCR On-           FGDOn-
                         Typec   line Date FGD Typed line Date
 Walheim 1
        2

 Mannheim 3,4
         7

 Ibbenbueren  B
HC
HC

HC
HC

HC
 W3
 153


2x220
 475


 770
WB
WB


WB
DB


WB
HD


TG
HD


TG
1988


1988
1988


1988
LSD
LSD


 LS
 LS
1987
1987


1988
1988


1987
Niederaussem
A-H

Scholven B





C
D
E
• F
G,H
LG

BC
BC
BC
BC
- HC -
Oil
9x300

370
370
370
370
•••-740
2X714
DB

DB
DB
DB
DB
DB
Oil
—

HD
HD
HD
HD
HD
HD
—

1989
1989
1989
1989
1989
1986-87
LS

LS
LS
LS
LS
LS
-
1988

1988
1988
1987
1987
1979-87
-
aCoal types: HC = hard coal, LG = lignite, BC = ballast coal.
bBoiler types: DB = dry bottom, WB = wet bottom.
°SCR types: HD = high dust, TG = tail gas.
dFGD types: LSD = lime spray drying, L = lime, LS = limestone.
marks (DM)  to the  U.S. dollar. The
following changes were made to the FGD
cost estimating model for this study.
Number of Spare Absorber
Modules
   None of the FGD systems evaluated in
the FRG have  spare  absorber modules
because  German legislation  allows the
plant  to be  out of  compliance  for 240
hours a year. Therefore,  the boiler  does
not have  to  shut down  due to  FGD
system operation problems. In the U. S.,
the  1979  New Source  Performance
Standard (NSPS) does not allow a boiler
to operate out  of compliance unless  a
spare absorber module  is  available.
Additionally, operating out of compliance
for any significant amount  of time would
result in noncompliance  with the  30-day
rolling average emission limit. As a result,
most U.S. utility companies have  chosen
to have spare  absorber  modules rather
than reduce the load or shut down when
the  FGD system  is  not  operating
adequately. This increases capital costs
by 20% for a 500-MWe unit.


Scrubber Module Size
   Many L/LS-FGD modules at the FRG
plants handled 300-500 MWe  equivalent
of flue gas. Large module sizes  reduce
capital costs  due to economy of scale.
The size of most U.S. scrubber modules
is typically 100-150  MWe to minimize
spare module costs.
                      Sorbent and Waste Handling
                      Quantities
                         All FRG coals are low in sulfur (~1%),
                      which results in lower capital costs due to
                      smaller sorbent and waste handling sys-
                      tems. By  contrast, U.S. boilers have coal
                      sulfur contents of 1 to 4%. Additionally,
                      most of the  L/LS-FGD systems  in  FRG
                      receive the sorbent pulverized, and the
                      capital cost for  pulverization  is reflected
                      in the cost of the sorbent (consumables)
                      and not in the system capital costs.

                      General System Design
                         The  FRG  FGD  systems  represent
                      current FGD  design concepts, which in
                      general are  less complex and lower in
                      capital costs than those built in the-U.S.
                      before  1985.  Process design  simplifica-
                      tion examples include single-loop scrub-
                      ber with slurry addition and oxidation in
                      the scrubber bottom,  and  the  use  of
                      hydroclones instead of thickeners before
                      vacuum  belt  dewatering. These  designs
                      represent state-of-the-art  technology and
                      are used on new U.S. systems.

                      Combined Systems
                         Another factor which affects the capital
                      cost of FGD systems is the system size.
                      Larger systems cost less on a $/kW basis
                      because of economies  of  scale. Because
                      the FRG  regulations required almost  all
                      utility boilers  to  retrofit scrubbers, flue
                      gas from adjacent  boilers at the  same
                      plant were  typically tied  into a single

-------
 large FGD  system. Thus, economies of
 scale resulted from having a single large
 system, instead of multiple smaller ones,
 and from having larger  absorber mod-
 ules. For example, at the Niederaussem
 plant  a  2700  MW  system  was
 constructed instead of eight units ranging
 in size from 150 to 600 MW.

 Summary of SCR Results
   Table 3  summarizes the capital cost
 comparison for SCR at four of the plants.
 Capital cost estimates  were  not possible
 at the lignite-fired plant in Niederaussem
 because these  boilers are expected to
 meet the NOX  emission limit  by retro-
 fitting  combustion modification controls.
 As  Table  3  shows,  the  difference
.between  the  actual  cost  and  the
 estimated capital cost varied between -5
 and 16%. Catalyst volume and costs for
 the SCR systems were based on informa-
 tion  from'  the plants. Access  and
 congestion  retrofit difficulty and  scope
 adders were estimated based  on proce-
 dures  developed for FGD systems.  The
 study results  confirm  that the  major
 variables that affect  the capital cost are
 catalyst volume and  cost, retrofit difficul-
 ty, and scope adder costs. However, still
 unknown  is the expected catalyst  life
 when firing  U.S. coals having high sulfur,
 alkali metal  and/or arsenic contents.
   Access and congestion retrofit difficul-
 ty and general  facilities  were  estimated
 using  the  methodology developed for
 FGD systems. The following access  and
 congestion  retrofit factor  description  was
 found  to give close approximation to the
 actual reported SCR  capital costs:
 • Base - Similar to new plant  where
   there is  free access for large  cranes
   and equipment near  the boiler  (hot
   side) or  chimney  (cold side). The
   Ibbenbueren  plant with a  cold  side
 •-  SCR system  behind the existing chim-
   ney is representative of this situation.
 • Low-Space is somewhat limited such
   that a standard  equipment  layout is
   not possible, but access  exists for
   large cranes on two sides. The Schol-
   ven units B-E with the hot  side SCR
   reactors  at  ground  level  next to  the
   ESPs  are  representative of  this
   situation. Limited  space  existed  be-
   tween the  units for locating the  SCR
   reactors  and cranes.
 • Moderate - Limited space  requiring
   special  equipment designs  and  lay-
   outs and crane access limited  to  one
   side. The Scholven F and  Mannheim 7
   units represent this situation where the
   SCR  reactors are elevated between
   the economizer  and  air  heater,  but
   Table 2.   Summary of FGD Capital Cost Comparison
            Plant Name          Mannheim Ibbenbueren Niederaussem
                          Walheim
Boiler/Block
Coal sulfur
FGD type
FGD size (MWe)
SO2 removal efficiency (%)
Number of absorbers
Estimate of retrofit difficulty
Access/Congestion factor
Scope adder costs ($/kWe)
General facilities (%)
Total capital cost ($/kWe)
EPA Contractor's Estimate
Actual reported3
Percent difference
7
1.0
LS-FGD
475
80
1
1.10
Low
0
8

140
140
0
B
1.0
L-FGD
770
85
2
1.10
Low
0
5

119
,130 ,
-8
A-H
1.0
LS-FGD
2700
90
9
1.87
Low
4.6
5

260
240
8
1-2
1.0
LSD-FGD
256
90
2
1.16
Low
0
10

190
170
12
   aCosts are based on an exchange rate of DM 2 to the U.S. dollar.
   outside of the boiler  building. Both
   units  are end units  allowing for
   reasonable crane access.
•  High  - Severe space limitations with
   access for large cranes blocked on all
   sides. The Walheim 2 unit represents
   this situation  where the boiler building
   wall was  removed to allow access to
   construct  the SCR reactors between
   the economizer and air heater.


Conclusions

Flue Gas Desulfurization
   The results of this study show that
FRG  capital costs for  conventional
lime/limestone wet and dry FGD systems
are similar when differences in the scope
of supply (design) are taken into account.
The major design differences  between
the FRG and U.S. designed systems are
due to:           -  	    	
•  Coal  Sulfur  Content -  Higher coal
   sulfur content of most U.S.  coals
   results in higher capital costs for
   sdrbent and  waste handling facilities
   and use of spare  absorbers to ensure
   operating  reliability.
•  Combined Systems - Most FRG sys-
   tems are large because of flue gas
   from multiple units is processed in one
   system. Combined  systems  have
   lower capital  cost requirements due to
   economy  of scale.
•  Regulatory - NSPS bypass and aver-
   aging  provisions have resulted in use
   of spare modules and small absorber
   sizes  to  minimize  cost  of   spare
   absorbers.
•  Technology  Status -  Most  FRG
   systems  employ  1980s  technology
   whereas most U.S.  systems employ
   1970s technology because of when
   the systems were built. Newer designs
   are more  reliable, reduce the need for
   spare absorbers, and allow the use of
   larger absorber sizes.
Results of this study indicate that:
1.  The lower capital cost of FGD systems
   in FRG relative to U.S. systems is due
   to  scope of the  supply  (design)
   differences.
2.  Future U.S. systems will  have lower
   capital cost requirements  than  past
   systems due  to technology improve-
   ments.
3.  Regulatory  provisions having  less
   stringent  bypass  and  averaging
   requirements  than NSPS  can signif-
   icantly reduce the capital cost of FGD
   systems.
4.  Combined handling  of flue.,gas  from
   multiple units  can significantly  reduce
   system capital costs.


Selective Catalytic Reduction
   Study  results show that FRG  SCR
system capital cost can  be accurately
estimated  if catalyst  cost and  retrofit
difficulty are known. The retrofit difficulty
adjustment  methodology  found in an
EPRI report  can  be used to  account for
different access  and congestion  situa-
tions in  the  FRG. Study results indicate
that:
1.  The FRG SCR  system capital costs
   can be used  to estimate  U.S. retrofit
   applications  if adjustments for retrofit
   difficulty and catalyst costs are made.

-------
2. Because of the differences in U.S. coal
   trace element content versus that of
   FRG, the catalyst life  requirements of
   the  FRG applications  are  not directly
   transferable to all U.S. applications. As
   such, catalyst life assumptions used to
   estimate annual costs  must reflect this
   uncertainty.
The following contaminants found in
utility  boiler flue  gases  over  time
deactivate  the catalyst: SOX,  particulate
matter, arsenic,  and  alkali  metals. The
contaminants vary with  the fuel  and
reactor location. SCR has been  com-
mercially applied in Japan and Germany
to the following utility boiler situations:
                                   Table 3.   Summary of SCR Capital Cost Comparison
                                            Plant Name          Mannheim Ibbenbueren  Walheim    Scholven
                                                                                            Scholven
                                   Boiler/Block

                                   Boiler type

                                   SCR type

                                   SCR size (MWe)

                                   NOX removal efficiency (%)
                                   Access/Congestion factor

                                   Scope adder cost ($/kWe)

                                   General facilities (%)

                                   Catalyst cost

                                      Dollarslftz*

                                      DollarslkWe

                                   Total capital cost ($/kWe)
                                                     7          8          2        B-E

                                                 Dry bottom  Wet bottom  Wet bottom Dry bottom
                                                    Hot

                                                    475

                                                    77-32

                                                 Moderate

                                                    3.0

                                                     13


                                                    504

                                                    18.7
Cold

 770

91-92

Base

47.7

 25


 355

 7.4
Hot

153

 88

High

42.5

 13


545

25.2
  Hot

370 each

   67

  Low

  3.1

   13


  283

  16.2
    F

Dry bottom

   Hot

   740

   60

Moderate
   3.4

   13


   283

   7.8

Fuel
Type
Gas
Oil
Coal

Ash
Metals
None
Low
Low

Sulfur
Level
None
Low
1 Per-

Temperat-
ure
Hot
Hot
Hot/Cold

Dust
None
Low
Low/High
Radian estimate 82
Actual reported13 79
Percent difference 4
t>1 m3 = 35.3 ft3.
bCosts are based on an exchange rate of DM 2 to
cExcludes the costs of combust/on modifications.
98 _
703
-5

the U.S.
180 ^_87
789° 75
-5 16

dollar.
57
55
3


  Coal
 High  1 Per-
Arsenic  cent
Hot/Cold  Low/High
 SCR has not been applied  commercially
 with high sulfur and  high alkaline coals.
 Many boilers in the U.S. burn high sulfur
 coals (2-5%) and   coals  with  highly
 alkaline  ash (lignites and subbituminous
 coals).  Also,  many  of  the low  sulfur
 eastern coals have high arsenic contents.
 To address the lack  of data available on
 catalyst life for hot  side SCR for  U.S.
 coals, a number of  SCR pilot programs
 are planned.
                                         I.E. Emmel, M. Maibodi, and J. A. Martinez are with  Radian Corporation,
                                              Research Triangle Park, NC 27709.
                                         Norman Kaplan is the EPA Project Officer (see below).
                                         The complete report, entitled "Comparison of West German  and U.S.  Flue
                                              Gas Desulfurization and Selective Catalytic Reduction Costs," (Order
                                              No.  PB  90-206 319/AS;  Cost:  $17.00, subject  to  change) will be
                                              available only from:
                                                  National Technical Information Service
                                                  5285 Port Royal Road
                                                  Springfield, VA22161
                                                  Telephone: 703-487-4650
                                         The EPA Project Officer can be contacted at:
                                                  Air and Energy Engineering Research Laboratory
                                                  U.S. Environmental Protection Agency
                                                  Research Triangle Park, NC 27711
 United States
 Environmental Protection
 Agency
                          Center for Environmental Research
                          Information
                          Cincinnati OH 45268
 Official Business
 Penalty for Private Use $300
 EPA'600/S7-90/009

-------