&EPA
                         United States
                         Environmental Protection
                         Agency
                                    National Risk Management
                                    Research Laboratory
                                    Cincinnati, OH 45268
                         Research and Development
                                    EPA/600/S-95/019  September 1995
ENVIRONMENTAL
RESEARCH    BRIEF
               Pollution Prevention Assessment for a Manufacturer of
                               Electroplated Truck Bumpers

                        Richard J. Jendrucko*, Thomas N. Coleman*, Brian T. Hurst*,
                                        and Gwen P. Looby"
Abstract
The U.S. Environmental Protection Agency (EPA) has funded
a pilot project to assist small and medium-size manufacturers
who want to minimize their generation of waste but who lack
the expertise to do so.  In an effort to assist these manufactur-
ers Waste Minimization Assessment Centers (WMACs) were
established at selected universities  and procedures were
adapted from the  EPA Waste Minimization  Opportunity As-
sessment Manual (EPA/625/7-88/003, July 1988). That docu-
ment has been superseded by the Facility Pollution Prevention
Guide (EPA/600/R-92/088, May 1992). The  WMAC team at
the University of Tennessee performed an assessment at a
plant that manufactures electroplated  bumpers and miscella-
neous parts for trucks.   Steel and aluminum parts received
from a nearby facility are cleaned, rinsed, etched, and electro-
plated. The team's report, detailing findings and recommenda-
tions, indicated  that a  considerable amount of wastewater
treatment sludge is generated from the onsite treatment of
wastewater, and that significant waste reduction and cost sav-
ings could be achieved  by reducing drag-out from the plating
tanks.

This Research Brief was developed by the principal  investiga-
tors and EPA's National Risk Management Research Labora-
tory, Cincinnati, OH, to  announce key findings of an ongoing
research project that is fully documented in a separate report
of the same title available from University City Science Center.


Introduction
The amount of waste generated  by industrial plants has be-
come an increasingly costly problem for manufacturers and an
* University of Tennessee, Department of Engineering Science and Mechanics
* University City Science Center, Philadelphia, PA
                         additional stress on the environment.   One solution to the
                         problem  of waste generation is to reduce or eliminate the
                         waste at its source.

                         University City Science Center (Philadelphia, PA) has begun a
                         pilot project to assist small  and medium-size manufacturers
                         who want to minimize their generation of waste but who lack
                         the in-house expertise to do so. Under agreement with EPA's
                         National  Risk Management Research Laboratory, the Science
                         Center has established three WMACs.  This assessment was
                         done by  engineering faculty and students at the  University of
                         Tennessee's (Knoxville) WMAC. The assessment teams have
                         considerable direct experience with process operations in manu-
                         facturing plants and also have the knowledge and skills needed
                         to minimize waste generation.

                         The pollution prevention opportunity assessments are done for
                         small and medium-size manufacturers at no out-of-pocket cost
                         to the client. To qualify for the assessment, each client  must
                         fall within Standard Industrial Classification Code 20-39,  have
                         gross annual sales not exceeding $75 million, employ no more
                         than 500 persons, and  lack in-house expertise  in pollution
                         prevention.

                         The potential benefits of the pilot project include minimization
                         of the amount of waste generated by manufacturers, and
                         reduction of waste treatment and disposal costs for participat-
                         ing plants. In addition, the project provides valuable experience
                         for graduate and undergraduate students who participate in the
                         program, and a cleaner environment without more regulations
                         and higher costs for manufacturers.


                         Methodology of Assessments
                         The pollution prevention assessments require several site vis-
                         its to each client served.  In general, the WMACs follow the

-------
procedures outlined in the EPA Waste Minimization Opportu-
nity Assessment Manual (EPA/625/7-88/003,  July 1988).  The
WMAC  staff  locate the sources  of waste in  the  plant and
identify  the current disposal or treatment  methods and  their
associated costs. They then identify and analyze a variety of
ways to reduce or eliminate the waste.  Specific measures to
achieve that goal are recommended and the essential support-
ing technological and economic information is developed. Fi-
nally, a confidential report that details the WMAC's  findings
and  recommendations (including cost savings, implementation
costs, and payback times) is prepared  for each  client.


Plant Background
This plant electroplates various types of bumpers and miscella-
neous parts for trucks. Approximately  100,000 parts are pro-
duced by this plant each year.


Manufacturing Process
Steel and aluminum sheet stock is stamped  into various shapes
at a  nearby company facility. The resulting  parts are manually
buffed and polished. A coating of rust-inhibiting oil is applied to
the steel parts in order to minimize surface  corrosion during
transportation and storage at the electroplating facility.

As parts are required for electroplating, they are removed  from
their packaging and inspected. Parts that pass inspection are
placed onto racks for processing.  The parts  that do not  pass
inspection are manually buffed and  sanded onsite  to  repair
defects.

An  overhead hoist is  used to transfer the racked parts to  a
series of tanks where parts are cleaned, rinsed, etched, and
copper,  nickel, and chrome electroplated.  After the parts have
been  plated and  rinsed in a  final  heated tank, they are re-
moved from the racks  and  allowed to  air  dry.

During a final inspection,  each part  is  cleaned  using  paper
towels.  Any surface irregularities in the plated parts are identi-
fied and repaired.  Parts passing final  inspection are packaged
and stored until shipment.

An  abbreviated process flow  diagram  for the production  of
plated bumpers is shown in Figure 1.


Existing  Waste Management Practices
This plant already has  implemented the following techniques to
manage and minimize  its wastes.

  •  Two filter presses  and a drying oven are used to reduce the
    volume of hazardous wastewater treatment sludge shipped
    offsite.

  •  Filtration units have been installed on the major plating tanks
    to remove contaminants so that the life of the active solutions
    can be extended.
Steel Bumpers


and Other
Truck Parts
Racking and
Inspection



Alkaline
Cleaning



Electro-
cleaning



Copper
Strike




Chrome
Plating


Nickel
Plating


Copper
Plating


Acid
Rinse




Hot Water
Rinse


Manual
Cleaning


Inspection
                                                                                   Bumpers and
                                                                                   Parts Shipped
                                                                                   to Customers
Figure 1. Abbreviated process flow diagram for steel bumper electroplating.

-------
Pollution Prevention Opportunities
The type of waste currently generated by the plant, the source
of the waste,  the waste  management method, the quantity of
the waste,  and the waste management cost for  each waste
stream identified are given in Table  1.

Table 2 shows the opportunities  for pollution  prevention that
the WMAC team recommended for the plant. The opportunity,
the type of waste, the possible waste reduction and associated
savings, and  the implementation  cost along  with  the simple
payback time are given  in the  table.  The  quantities of waste
currently generated by the plant and possible waste reduction
depend on the production level  of the plant. All values should
be considered in that context.

It should be noted that the economic savings of the opportuni-
ties, in most cases,  results from the need for less raw material
and from reduced  present and future costs  associated with
waste treatment and disposal.   Other savings not quantifiable
by this study include a  wide variety  of possible future costs
related to  changing  emissions standards,  liability,  and em-
ployee health.  It also should be noted that the savings given
for each opportunity reflect the savings achievable when imple-
                                   menting  each  pollution prevention opportunity independently
                                   and do not reflect duplication of savings that may result when
                                   the opportunities are implemented in a package.


                                   Additional Recommendation
                                   In  addition to the opportunities recommended and analyzed by
                                   the WMAC  team,  one additional  measure  was  considered.
                                   This measure was  not analyzed completely  because of a lack
                                   of  sufficient information.  Since this approach to pollution pre-
                                   vention may, however,  increase in attractiveness with changing
                                   conditions in the plant,  it was brought to the plant's attention for
                                   future consideration.

                                     • Reduce  the number of parts that must be coated with rust-
                                       inhibiting oil at the fabrication plant through careful schedul-
                                       ing of part fabrication, shipping, and electroplating operations.
                                   This research brief summarizes  a part of the work done  under
                                   Cooperative  Agreement No. CR-819557 by the  University City
                                   Science  Center under the sponsorship  of the  U.  S.  Environ-
                                   mental Protection Agency.  The EPA Project  Officer was Emma
                                   Lou George.
Table 1. Summary of Current Waste Generation
Waste Stream Generated
Miscellaneous solid waste
Cleaning solution and rinse water
Source of Waste
Unpacking of pan's (primarily)
Cleaning of steel pan's prior to plating
Annual Quantity
Waste Management Method Generated (Ib/yr)
Shipped offsite to municipal landfill 2,160 yd3
Sewered 20,961,000
Annual Waste
Management Cost
$14,380
10,800
Cyanide-contaminated rinse water



Acid rinsing solution



Rinse water from electroplating


Rinse water from electroplating
Alkaline cleaning solution and
rinse water

Caustic and zinc oxide cleaning
solution and rinse water
Contaminated nitric acid cleaning
solution

Rinse water
Rinse following copper-strike coating
of steel pan's and surface treatment
of aluminum parts

Acid rinse following copper-strike of
steel parts and surface treatment of
aluminum parts

Rinses following copper- and chrome-
plating of steel and aluminum parts

Rinse following nickel-plating of steel
and aluminum parts

Alkaline cleaning of aluminum parts
prior to plating

Zinc cleaning of aluminum parts prior to
plating and rinsing of parts following
acid cleaning

Acid cleaning of aluminum parts prior to
plating

Rinse following surface treatment of
aluminum pan's prior to copper plating
Treated in onsite wastewater
treatment plant; sewered           7,806,000
Treated in onsite wastewater
treatment plant; sewered            165,000


Treated in onsite wastewater       26,502,000
treatment plant; sewered

Treated in onsite wastewater        14,442,000
treatment plant; sewered

Sewered                       8,118,000
Treated in onsite wastewater       20,608,000
treatment plant; sewered
Treated in onsite wastewater         165,000
treatment plant; sewered

Treated in onsite wastewater         488,000
treatment plant; sewered
 6,800




  140


23,100


12,590


 4,180


17,960




  140


  420
Evaporated water
Contaminated filter tubes
Wastewater treatment sludge
Heated tanks in electroplating lines
Filtering of plating solutions
Onsite wastewater treatment plant
Evaporates to plant air
Shipped offsite for disposal
as hazardous waste
Shipped offsite for disposal
as hazardous waste
6,963,000
3,850
179,190
2,6501
30,550
78,280
 Includes waste treatment, disposal, and handling costs
 Includes raw material cost

-------
Table 2. Summary of Recommended Pollution Prevention Opportunities
                                                                   Annual Waste Reduction
Pollution Prevention Opportunity
Waste Stream Reduced   Quantity (Ib/yr)
                                                                                   Per Cent
                              Net Annual     Implementation    Simple
                               Savings          Cost      Payback (yr)
Reduce drag-out from plating tanks by utilizing
spray rinsing and drag-out boards. Install rinse
devices above each plating and wash tank to
spray a mist of water onto part racks as they
are removed from the tanks. Drag-out boards
should be installed between tanks in series.
This opportunity will lead to savings in plating
chemical purchases and reduced generation
of wastewater treatment sludge.

Reuse effluent from the onsite wastewater
treatment system in the rinsing stations follow-
ing each plating tank in  the steel parts electro-
plating line.

Meter the wastewater leaving the plant in
order to reduce sewer charges. Currently,
sewer charges are assessed based on the
total amount of water purchased by the plant.

Utilize available covers  on all heated process
tanks during periods of light or non-production
in order to reduce evaporative water losses.
Wastewater treatment
sludge
 53,800
                                                                                      30
$41,200        $31,300         0.8
Rinse water
n/a
Evaporated water
                        25,725,000
                           n/a
3,482,000
                                            37
                                           n/a
                                            50
                                11,860
                                                         3,270
  1,320
                19,700         1.7
                                                8,700
                                                                                      2.7
                                                                          0        immediate
United States
Environmental Protection Agency
National Risk Management Research Laboratory (G-72)
Cincinnati, OH 45268

Official Business
Penalty for Private Use
$300
                                                                        BULK RATE
                                                                 POSTAGE & FEES PAID
                                                                            EPA
                                                                     PERMIT No. G-35
EPA/600/S-95/019

-------