United States
  Environmental Protection
  Agency
  Risk Reduction
  Engineering Laboratory
  Cincinnati, OH 45268
 Research and Development
 EPA/600/SR-92/031   April 1992
  Project  Summary
  Reclamation and
  Redevelopment  of  Contaminated
  Land:   Volume II.
  European  Case  Studies
 Garrie L. Kingsbury and Tayler H. Bingham
   The Research Triangle Institute (RTI)
 began work for the U. S. Environmental
 Protection Agency (EPA) in 1983 to in-
 vestigate  contaminated sites in the
 United States where cleanup measures
 have been carried out to enable spe-
 cific redevelopment of a site. This work
 resulted in a report issued by EPA in
 August 1986, documenting 16 uncon-
 trolled hazardous waste sites.  Case
 studies presented land use history and
 redevelopment  objectives, the nature
 of the contamination, descriptions of
 the remedial actions undertaken, the
 planned upgraded reuse of the prop-
 erty, and the criteria for cleanup.
  During the course of the study of
 U.S. sites, it became apparent that con-
 taminated land  reclamation and rede-
 velopment  were of international inter-
 est. Thus, the EPA study was extended
 to include experiences in certain Euro-
 pean countries.  This report presents
 highlights  of programs dealing with
 contaminated land in England, Wales,
 Sweden, the Netherlands, and then the
 Federal Republic of Germany.
  This report is a companion document
to the August 1986 EPA report address-
 ing reclamation  and redevelopment in
the U.S. (EPA/600/2-86/066).
  This Project Summary was developed
by EPA's Risk Reduction Engineering
Laboratory, Cincinnati, OH, to announce
key findings of the  research project
that is fully documented in a separate
report of the same title (see Project
Report ordering information at back).
 Introduction
   There ar.e numerous instances in the
 United States and Europe where uncon-
 trolled  dumping or industrial spills have
 contaminated properties with hazardous
 materials. Since many of these properties
 are in prime urban locations, issues sur-
 rounding the reclamation and redevelop-
 ment of contaminated sites have become
 important international topics. This report
 documents experience in reclamation and
 redevelopment at selected contaminated
 sites jn England, Wales,  Sweden, The
 Netherlands, and the then Federal Re-
 public of Germany. Much of the informa-
 tion is drawn from interviews with various
 government officials and local authorities
 from each country who are responsible for
 overseeing and implementing the contami-
 nated  land activities related to reclama-
 tion and redevelopment.
  Interviews and site visits were conducted
 during February and March of 1985. Ad-
 ditional information was subsequently re-
 ceived through correspondence with vari-
 ous individuals previously contacted in
 Europe.  The report  is  current  through
 April 1985 with certain portions updated
 through 1987 and early 1988. The report
 does not critique or judge any country's
 program or compare European approaches
to approaches applied in the U.S.  The
 objective is merely to extend the informa-
tion base pertaining to contaminated land
 reclamation actions undertaken for spe-
cific land reuse.
  The  study addresses site assessment
and reclamation programs, available fund-
ing sources, and guidelines established to
                                               Printed on Recycled Paper

-------
assist reclamation. The reclamation and
redevelopment experience at selected sites
In each country  is described in detailed
case studies. Each case study describes
the land use history and redevelopment
objectives, the nature and  extent of  the
contamination, remediation  activities,  site
reuse, and criteria for cleanup.

Discussion

England,  United Kingdom (U.K.)
   England is one of the most industrial-
ized nations of the world and has a popu-
lation density about 15 times higher than
that of the U.S.  As a result of this indus-
trialization and urbanization, the potential
problems associated with the redevelop-
ment of contaminated land were  recog-
nized earlier in England than in the U.S.
   Several legislative  Acts  of Parliament
provide  the framework for dealing  with
contaminated land in England and Wales.
The Derelict Land Act of  1982 encour-
ages the redevelopment of contaminated
and derelict land, particularly where pri-
vate sector development will result.  The
disposal of  all controlled material,  includ-
ing surplus  excavated material from rede-
velopment  sites is regulated under the
 Control of  Pollution  Act of  1974.  Site
 licensing is  the primary means of regulat-
 ing the disposal of all controlled wastes.
 The Town  and Country Planning Act  of
 1971 empowers local authorities to  con-
 trol most forms of development including
 development of contaminated land.
   Within Central Government, the Depart-
 ment of the Environment (DOE) sets  envi-
 ronmental policy for  England and Wales
 and Is responsible for implementing the
 programs related to the various  environ-
  mental legislative Acts.  The Central Di-
  rectorate  on  Environmental  Pollution
  (CDEP) within the DOE is  mainly respon-
  sWs for dealing with issues involving con-
  taminated  land and  advising  local au-
  thorities.
    The Interdepartmental Committee on the
  Redevelopment  of Contaminated  Land
  (ICRCL) was established in 1976 to  coor-
  dinate government activities and advice
  relating to contaminated land. The ICRCL
  includes representatives of several British
  government departments.  A basic objec-
  tive of the ICRCL is "to restore contami-
  nated land to beneficial use economically".
  The ICRCL has developed a series of
  Formal Notes to address redevelopment
  at landfill sites,  sewage works and farms,
  gas works  sites, and scrap yards and simi-
  lar sites.
    One of  the tasks carried out by the
 •CDEP for the  ICRCL is  an effort to de-
  velop guidelines pertinent to contaminant
levels at sites where redevelopment  is
being considered.   In 1983, the ICRCL
issued guidance  for local authorities vand
prospective developers on assessing and
redeveloping land that has been contami-
nated by its former use.  This guidance
included 'Tentative Trigger Levels" to serve
as  criteria  for comparison  with  specific
contaminant levels  in soils.  The  appli-
cable concentrations vary with the pro-
posed use  of a site. The Tentative Trig-
ger Concentrations are reviewed and up-
dated periodically  by the ICRCL   The
guidance issued with the trigger concen-
trations stresses the importance of an ad-
equate  investigation of the site prior  to
applying the assessment criteria.
   Methane or other combustible or explo-
sive materials are  present on many sites
being considered for redevelopment. The
assessment of fire and explosion hazards
of contaminated land is an important pro-
gram aspect of the CDEP and the ICRCL.
The ICRCL has developed  "Notes on the
 Fire Hazards of  Contaminated  Land."
   The Greater London Council (GLC) was
 established in 1965 to be responsible  for
 London fire service, refuse disposal, high-
 ways and  traffic planning,  and structure
 planning.  Until abolition in March 1986,
 the GLC had absolute control over plan-
 ning for Inner London and  strategic plan-
 ning control for  outlying areas. The GLC
 also coordinated efforts  to bring derelict
 land into beneficial use.
   The GLC in 1979 suggested guidelines
 for use during site  assessments to define
 various levels of soil contamination. The
 degree of soil contamination is classified
 as  "uncontaminated," "slight  contamina-
 tion," "contamination," "heavy  contamina-
 tion," or "unusually heavy contamination."
 The ranges  of  contaminant levels corre-
 sponding to the various classifications are
 based  on  comparison  with  typical
 "uncontaminated" soils rather than on an
 assessment.
    The case studies for England are  the
 Corby Steelworks in the town of Corby in
 Northhamptionshire in the English  Mid-
 lands; the Wandsworth Gas Works, Lon-
 don; and the planned  community of
 Thamesmead on the Thames River in Lon-
 don. Experience at these sites illustrate
 the manner in which certain problems were
  dealt with during  site reclamation  and re-
  development.
    The Corby Steelworks  operated from
 the 1930's until 1979. When the steel mill
  closed, the Corby district Council acquired
  the steelworks site for redevelopment. At
  several tracts  of land formerly occupied
  by the steel works (or its  ancillary opera-
  tions), site reclamation  to deal with  con-
  tamination had to precede any redevelop-
ment  activity.  Chemical contaminants
found in the various areas of the former
steel mill property included heavy metals,
cyanides,  sulfur salts,  naphthalene and
other  volatile organics, coal tar, various
oily wastes, phenols and asbestos.  The
site reclamation plan was developed on
the basis of a detailed site assessment to
determine the  extent  of  the  contamina-
tion. Guidelines developed by the Greater
London Council (GLC)  were used in the
assessment.
   Future use plans for the reclaimed steel
mill site focus  primarily on industrial de-
velopment that  will provide jobs. The fact
that the sites offered in Corby are, in many
cases, reclaimed contaminated land does
not appear to have any influence on the
attractiveness of the redevelopment prop-
erties.
   The Wandsworth Gas Works produced
gas from coal for about 100 yr. The gas
works site extended some 550 m along
the Thames  River. Parts of the s'rte were
 reclaimed from river marsh by filling with
 process wastes such as spent iron oxide
from gas cleanup.  The site  was  pur-
 chased by the GLC for development as
 housing.  Based on findings  of extensive
 contamination  in site assessment in 1976,
 the GLC determined that redevelopment
 of the site should be for less sensitive
 land use. Contamination from  coal tar is
 believed to pose the mosjt serious poten-
 tial hazard at the site.
   Disturbing the buried foundations, tanks,
 pipelines, pits, and other structures was
 considered to pose a major pollution prob-
 lem and a direct exposure hazard to work-
 ers.  Because  of these problems, the GLC
 recommended, "reduction of site distur-
 bance to the  minimum  possible."  Suffi-
 cient remedial work was carried out  in
 1983 to insure  that contamination  from
 the gas  works did not pose a hazard to
 the surrounding areas.   Portions of the
 site  are  scheduled for redevelopment for
 light industry to provide jobs in the area.
 A refuse transfer station has  been con-
 structed on a 20-hectare (49 acres) tract
 at the western end of the site. Remedial
  measures must precede any  redevelop-
  ment of the remainder of the site occupied
  by the gas works.
    Some 400  hectares (988 acres) of the
  Thamesmead development are on the site
  of the former Royal Arsenal in Woolwich.
  The extent of the contamination from the
  old arsenal activities was first recognized
  in 1975. Chemical contaminants of con-
  cern at site  include  heavy metals, coal
  tars, oils, phenols, sulfur salts, free and
  complexed cyanides, combustible materi-
  als  and asbestos.  For the purposes of
  development, the Thamesmead site has

-------
  been divided into a number of areas, each
  with its own characteristics and planned
  use.  About 40 % of the site had been
  developed by  1985.   When  complete,
  Thamesmead is planned to accommodate
  some 40,000 people, including homes, rec-
  reation and shopping, and local employ-
  ment on purpose built industrial estates.
  Recommendations for remedial measures
  are proposed  based  on  projected long-
 term hazards to site users.

  Wales, United Kingdom
   The  Principality of Wales  is  politically
 united with  England, and the two coun-
 tries have shared common systems of law
 and government for nearly 450 yr.  The
 legislative Acts  of Parliament effective in
 England also apply to Wales. The largest
 category of derelict sites in Wales involves
 coal  wastes.  Because so little land  in
 Wales is  suitable for development due to
 the steep slopes, there is pressure to de-
 velop any unused land, particularly in  or
 near towns, and to reclaim derelict land.
 In the narrow valleys characteristic of the
 mining areas, level ground is primarily oc-
 cupied  by  surface  works, and mining
 wastes  are tipped on the valley sides.
   The Central Government of the U.K.
 establishes environmental policy in both
 England and Wales. The role of the Welsh
 Office in Wales is analogous to the role  of
 the DOE in England.  The Environmental
 Protection Division within the Welsh Of-
 fice, Cardiff, is responsible for administer-
 ing the environmental programs in Wales
 including programs pertaining to contami-
 nated land.
  The Welsh Development Agency (WDA)
 is empowered to make grants to County
 and District Councils for the  purpose of
 reclaiming derelict land.   The costs re-
 quired to bring such sites to a "greenfield"
 state  are  eligible for these grants,  the
 WDA also engages in site redevelopment.
  In 1983, the Welsh Office and the WDA
 co-sponsored a survey of sites  that are
 believed to  be contaminated.  Emphasis
 was placed on contaminated sites of 0.5
 hectares (1.2 acres)  or larger; sites cur-
 rently in beneficial uses  were excluded.
 More than 700 sites were cataloged dur-
 ing the  initial survey,  and additional up-
 dates and expansion of the data base are
 planned.
  The Lower Swansea Valley near the
 south coast of Wales is  described in detail
 in a case study.  From the beginning of
the 18th century, the  port of Swansea
was an important shipping outlet for coal
from the South Wales  Coal Field.  The
 Lower Swansea Valley became  a major
center for smelting of copper,  zinc, and
other  metals and later for steel  and tin
  plate production.  The heavy industrial
  activity in the Valley ceased after World
  War II, leaving the Valley  in a polluted,
  derelict state. It was estimated in 1964,
  that approximately 12 hectares (400 acres)
  within  the  Lower Swansea Valley were
  covered by waste tips containing some 5
  million tons of industrial waste containing
  high levels of copper and zinc as  well as
  antimony, arsenic, cadmium and lead.
   The Lower Swansea Valley Project was
  initiated in 1961 to address the dereliction
  and contamination in the  Valley  and to
  begin the planning for future development.
  Among the recommendations of the project
  that influenced later work were: An accu-
  rate and detailed base map,  visual  im-
  provements  through  planting  trees and
  grasses, statement of the need for a single
 body to acquire all the land to be redevel-
 oped,  and planning  for the Valley that
  included housing and recreation  as well
 as industry.
   The  first major  reclamation schemes
 were undertaken beginning in 1966 when
 Swansea was designated a Development
 Area, qualifying the area for financial as-
 sistance from Central Government to re-
 claim derelict land for industrial develop-
 ment. The policy was to clear the derelict
 land, return the land to active use, and
 encourage new and modern industry  to
 the  area.
   By 1974, the Local Authority had ac-
 quired some 330 hectares (815 acres)  of
 land and the reclamation programs were
 substantially complete for  172 hectares
 (425 acres).  Additional land clearance,
 reclamation, infrastructure, amenity plant-
 ing, and industrial promotion were carried
 out between 1974 and 1983  supported by
 grant  aid  from the  WDA, and  other
 sources.

 Sweden
   The Ministry of  Environment and En-
 ergy is responsible for environmental pro-
 grams throughout Sweden.   Environmen-
 tal policy is implemented through permits
 and National physical planning.  Environ-
 mental issues are among the  highest rated
 priorities of the Swedish general  public.
 Except for some sites in metropolitan ar-
 eas, however, the reuse of contaminated
 land in Sweden has  not been a  major
focus of concern.
   The Central Organization of Swedish
Communities has completed a national
inventory of oil dumps and landfills.  In all,
3,800 properties have been registered in-
cluding  about 500 that are believed  to
represent a potential threat  to man and
the environment. High priorities have been
assigned to about 20 dump sites.
    Two sites are addressed in case stud-
  ies. These are the Augustendal Dumpsite
  in Nacka, a suburb of Stockholm, and the
  BT-Kemi Pesticide Plant, near Malmo, in
  Southern  Sweden.   The cleanup  of the
  BT-Kemi site was the first remedial action
  project in-Sweden.

  The Netherlands
    The Netherlands is the most densely
  populated country in Europe. The Neth-
  erlands is also a highly industrialized na-
  tion, smaller than the State of New York.
  Metal manufacturing (iron, steel,  alumi-
  num) and, in more recent years, the chemi-
  cal industry are the most important  indus-
  tries. The Netherlands is a parliamentary
  democracy under  a constitutional mon-
  arch.
    Because of  the scarcity of land  in the
  Netherlands, every site is needed.  Many
 sites, particularly in the municipalities, have
 been used for many decades and for more
 than one type of use. Contaminated land
 in  The Netherlands is viewed as a very
 serious problem because of the high popu-
 lation density, the relative scarcity of land,
 the high water table in many parts  of the
 country, and the reliance on groundwater
 from  drinking  supplies.   Protection of
 groundwater is of special concern in the
 Netherlands.
   A survey of contaminated sites in 1980
 identified more  than 4,000 potentially con-
 taminated sites.  In 1981, about 350 in-
 vestigations and  30  cleanup operations
 were started at a cost equivalent to about
 20 million  U.S. dollars.  In 1985, it was
 estimated that  urgent cleanup measures
 were needed at 1,170 sites.   The major
 types of contaminated sites identified are
 waste dumps, former factories and manu-
 facturing plants, former gas  works, and
 other sources.
  The Soil Protection Bill  which became
 law on Jan. 1,  1984, provides for a 5-yr
 program of measures aimed at protecting
 the soil.  The program is to be overseen
 by the Ministry of Housing, Physical  Plan-
 ning, and the Environment.  The  policy
 regarding soil protection  is that the soil
 must retain  its  ability to perform a  wide
 variety of functions adequately. The cre-
 ation of ground-water protection  areas is
 a short-term policy objective.
  Under the Soil Cleanup (Interim) Act,
 which  came into force in January  1983,
 the Provincial Authorities  are  required to
 submit each year to the Ministry of Hous-
 ing, Physical Planning, and the Environ-
 ment, a cleanup program to deal with soil
contamination.  A cleanup program  runs
for  a period of 5  yr  and  covers all in-
stances of severe soil contamination within
each province.  Each province, in consul-

-------
tatton with the Municipal Authorities devel-
ops priorities for she cleanups.  The Min-
ister determines which cases are to be
considered for remedial measures or in-
vestigations with Central Government as-
sistance.
  The Soil Clean-Up Act was later incor-
porated in the Soil Protection Bill. Cleanup
costs are shared by central government,
the provinces, municipalities, and certain
industries.  The Ministry of  Health  and
Environmental protection normally contrib-
utes approximately 90% of the cleanup
operations. In some instances, an indus-
try is  responsible for paying the cost of
cleanup, and the government will collect
the payment from  the responsible party
after the cleanup is completed.  The Cen-
tral Government has budgeted  equivalent
to about  700  million U.S.  dollars for the
program over a 15-yr  period to provide
for site clean-ups and also for the Central
Government's program in research, stan-
dards development, analysis, and coordi-
nation to insure consistency in the cleanup
 efforts.
   The Ministry of Housing, Physical Plan-
 ning, and the Environment (1983) has de-
 veloped guidelines to  be used in site in-
 vestigations to assess the degree of con-
 tamination.   Soil  contamination  means
 there is a chemical in the ground exceed-
 ing the level normally expected to occur.
 Constituents for which the guidelines are
 developed are recognized as indicators of
 pollution.
   The capacity of  cleanup installations in
 Tha Netherlands is insufficient to treat all
 the excavated contaminated soil from site
 cleanups.  As a result, storage of a con-
 siderable amount of material is necessary
 while awaiting processing. It is estimated
 that The Netherlands  has 1.5 million tons
 of contaminated soil from old gas works
 and an even greater  quantity  of soil pol-
 luted with oil.
    The contaminated land problem in the
 Netherlands first came to public attention
 In 1978  with the discovery of serious soil
 contamination near homes in the town of
 Lekkerkerk.  The  contaminated area (8.9
 hectares [22 acres]) underlies 268 houses.
    Excavations in the area revealed chemi-
 cal waste buried in containers and in bulk
  in trenches and pits.  The wastes depos-
  ited at Lekkerkerk originated  at a variety
  of industries including the building  indus-
 try, paints and varnish manufacture, paint
  spraying, plastics manufacture and pro-
  cessing, chemical industry, and printing
  ink manufacture  and application.  Soils
  adjacent to the buried wastes were also
  polluted.  Pollutants  were found beneath
  houses, just below the floor.
  The remediation activities involved the
excavation  and removal of 93,800 m3 of
contaminated soil.  This material was pro-
cessed in a domestic refuse incinerator at
Rotterdam.
  No polluting materials were allowed to
remain at Lekkerkerk.  The total  cost of
the  remediation  work  at  Lekkerkerk
amounted to about 65 million U.S.  dollars,
paid by the Netherlands  Central govern-
ment.  If Lekkerkerk were discovered to-
day, the remedial action for the site would
likely be very different as the cost  of such
a program cannot be justified ($242,000
per house).
  Other case studies of contaminated sites
in the Netherlands include Delfshave, an
older area  of Rotterdam Harbour where a
special infilling technique is being  used to
provide land for housing; Merwedepolder,
Dordrecht, where remedial action was un-
dertaken after a housing development was
built over a former chemical waste dump;
and the Tilburg Gas Works where exten-
sive excavations  were necessary to re-
claim the site for housing.
   The Tilburg Gas Works produced gas
from coal  for more than 100 yr on a 5.5
 hectare (13 acres) site that is now in cen-
tral Tilburg. The plant also produced coke
 as well as byproduct tars, benzene, tolu-
 ene, naphthalene, and  ammonia.  Site
 investigations were  carried out in 1982.
 Available maps and site history were stud-
 ied to identify areas where contamination
 was likely  to  be  most concentrated.
 Samples were taken both at the surface
 and at depth on a 10 x 10 m grid.  Chemi-
 cal analyses revealed the presence of vola-
 tile  aromatics,  polynuclear aromatic hy-
 drocarbons, and  cyanides.,  Tar and oil
 products polluted large areas to a depth
 of 4 m.  The pH  of water  at  the site
 measured 2.5 due to the presence of hy-
 drogen sulfide. Coal and sinters covered
 several acres of the she.
   The remediation  work was carried out
  during the winter 1984-1985 and in Octo-
  ber and November of 1985.  The excava-
  tions were performed during the  winter in
  order to minimize worker exposure to vola-
  tile contaminants. During the winter 1984-
  1985 a total of 28,186 m3 of polluted soil
  were excavated  and transported off-site
  for temporary storage and thermal treat-
  ment.
    Guidelines from the Ministry suggested
  that contamination  should be cleaned up
  to background levels.  All detectable pol-
  lution to  a depth of 2 m was  removed.
  Excavations were also carried out to lower
  depths (below the water table) to reduce
  contaminant levels  and to minimize fur-
  ther contamination  of the aquifer.
Federal Republic of Germany
  The Federal Republic of Germany (FRG)
before German unification of October 1990,
was somewhat smaller than the state of
Oregon in the U.S. and had a population
of just  over 61 million people. The coun-
try included 10 states plus the territory of
Berlin.  The individual states (Lander) en-
joyed considerable political autonomy.
  The  Federal  Environmental Agency,
Umweltbundesampt, headquartered in Ber-
lin was responsible for establishing basic
environmental policies for the  FRG,  al-
though the individual Lander implemented
their own programs.  The Federal Waste
Disposal  Act,  issued in  1972,  required
wastes to be disposed of in a way that
avoided environmental damage.
  The German work "Altlasten" (meaning
old  burdens) is used to  refer to environ-
mentally hazardous waste disposal prob-
lem sites. Although  the total number of
sites containing hazardous  materials is
quite large, the subset of waste disposal
problem sites was estimated in 1983, to
be  less than 1,000.   Investigations  and
possibly remedial action is needed at these
sites.
   Although there are no official guidelines
to  assess soil contamination in the FRG,
threshold levels for certain  heavy  metals
 are recognized based on average levels
 found in soils.  These normally occurring
 and acceptable levels derive from a litera-
 ture search  and  recommendations pub-
 lished in  1977.
   The discussion of reclamation and re-
 development in the then FRG addresses
 three  different  areas:  The  City-State of
 Hamburg, the Ruhr district, and the Cen-
 tral and  South Regions.  The programs
 for environmental planning reflect the very
 different  geographical features of these
 areas. The concerns in Hamburg, a city
 of  over a million people, differ from the
 issues of the Ruhr district which is marked
 by many small to medium-sized industrial
 towns located adjacent to each other.  The
 Central and Southern regions include sub-
 stantial rural areas as well as several very
  large industries.
    The Ruhr District (Ruhrgebiet) in the
 state of Nordrhein-Westfalen is perhaps
 the largest industrial area in Europe.  En-
 vironmental problems associated with the
  residue from  more than 100 yr of heavy
  industrial activity (i.e., coal industry, iron
  and  steel  working,  chemicals manufac-
  ture) are  prevalent  throughout the
  Ruhrgebiet.   Contaminated land in the
  Ruhrbegiet is often  reclaimed for new in-
  dustrial  use, but with  stringent  controls
  aimed at softening the  environmental im-
  pacts on the region.

-------
   Five sites are described in case stud-
 ies.  The Havighorster Moor site, in Ham-
 burg, was used as a dumping area after
 World War II. After arsenic contamination
 was found in a nearby stream, an exten-
 sive cleanup operation was  undertaken
 by the State.  The source of  the arsenic
 contamination was removed to a permit-
 ted facility or isolated  in a specially  de-
 signed pit on-srte.  After the cleanup was
 completed, new problems at the site  be-
 came apparent. Low levels of chlorinated
 organics were found in water seeping from
 the site.  A new remediation scheme has
 been planned to  treat the contaminated
 water using an aquatic plant (Phragmites
 communis).
   At the site in Bielefeld in the Ruhr Dis-
 trict, buried industrial waste has been dis-
 covered in a housing development. Meth-
 ane  resulting from  municipal  waste for-
 merly dumped at  the site  is also of con-
 cern. The town has offered to purchase
 the homes of any owner who wishes to
 relocate.
   At an industrial site in Dortmond, a ma-
 jor cleanup is underway in which contami-
 nated soil and water are mixed with lignite
 fly ash in a patented process.  The result-
 ing mixture  hardens  to  a concrete-like
 mass and is disposed on-site in a lined
 Pit-
   Additional case studies describe the re-
 medial actions at  an urban site contami-
 nated with diesel fuel  and an industrial
 site where residues from Lindane produc-
 tion were deposited.

 Conclusions

 The Role of Central
 Government
   In  each country the central government
 is  responsible for formulating  policy  re-
 garding the cleanup of contaminated sites.
 The actual cleanups, however,  are carried
 out by local authorities in most instances.
 Government regulations are established
 in  each country to control the  disposal of
 contaminated materials. The Central gov-
 ernments in Wales, Sweden, and the Neth-
 erlands have  conducted surveys of con-
taminated  sites to assess the extent  of
contaminated land. Efforts were also made
to  prioritize sites based on their potential
 impacts on people and the environment.
 Such surveys in England and  in the then
 FRG have been limited to specific regions
 or municipalities.
  Of the cleanup  efforts investigated  for
this report in England, Wales,  and the
 Netherlands,  almost all  were financed
through funding programs made available
through the  Central Government of the
 respective country. In most cases, a small
 percentage of the total rehabilitation cost
 (typically 10%) is borne by local govern-
 ments.

 Very Large Sites
   Three sites that are treated in detail in
 case studies encompass areas exceeding
 100 hectares (247 acres).   These  are
 Thamesmead,  London, England;  Corby
 Steelworks, Northhamptonshire,  England;
 and the Lower Swansea Valley,  West
 Glamorgan,  Wales.   Although  each  of
 these sites is subdivided into many smaller
 areas for specific reclamation work,  the
 success of the various individual  reclama-
 tion and redevelopment efforts is depen-
 dent on the overall reclamation scheme
 for the  area.  Common ownership by a
 single authority and a coordinated master
 plan for site reclamation have been vital
 to the success of the  redevelopment of
 these areas.  Because the quality of con-
 taminated soil and debris is so great at
 these large  sites, the  cost of complete
 removal of  the contaminated  material
 would be prohibitive.  The master plan for
 reclamation and redevelopment  at these
 sites includes contaminant areas for on-
 srte  disposal  of large quantities of con-
taminated materials.

 Response When Contamination
 Impacts Current Land Use
  At three of  the sites addressed in case
 studies, the  remedial  actions  were
 prompted by  concern over  potential ad-
verse health effects from exposure to con-
taminants present in the ground beneath
private  homes.  The local municipalities
were considered responsible for the de-
velopments since they had granted plan-
 ning permission for the developments  in
spite of the buried waste.  The remedial
efforts at Merwedepolder and Brake were
still being  discussed in 1985.   At
Lekkerkerk, all buried waste and contami-
nated soil were removed from the housing
area. At Brake and Merwedepolder, the
local authorities  offered to purchase, at
market prices, all the houses affected by
the buried waste in order that  the people
might relocate.  Although the presence of
toxic materials near homes at Lekkerkerk,
Merwedepolder, and Brake is  clearly es-
tablished, there is no medical evidence of
serious  adverse effects from exposure in
any of the inhabitants.

Redevelopment of Gas Works
Sites
  Former gas works  sites are frequently
encountered  in  Europe.  Before  the turn
of the century, gas works were in opera-
 tion in virtually every major city and town
 and the plants were usually centrally lo-
 cated for  ease in distribution.  Besides
 production  of  coal  gas, coking  and
 byproduct refining operations were asso-
 ciated with chemical industries and steel
 making.  Most of the gas plants ceased
 operation  in the  1950's as gas  from the
 North Sea wells  became  available.  The
 contaminants present at  these  types of
 sites include coal tars (which contain poly-
 cyclic aromatic hydrocarbons that are rec-
 ognized to be carcinogenic in animals),
 aromatic solvents (benzene, toluene, and
 xylenes) phenolic compounds, free  and
 complexed cyanides, suffides, sulfates (ag-
 gressive to building materials) and com-
 bustible materials.
   Many of the former gas works sites
 have been acquired for redevelopment by
 local municipalities because of their cen-
 tral locations. In some instances, the ex-
 tent of the contamination  at a gas works
 site was not recognized before redevelop-
 ment plans were made.  Plans for sensi-
 tive reuses (e.g., school, housing) have
 had to be abandoned in light of site as-
, sessment findings.  In some cases, (e.g.,
 Thamesmead, gas works site) the site as-
 sessment led to the conclusion that it  was
 best to allow the contaminated site to re-
 main undisturbed. Factors leading to such
 a conclusion  include:  Uncertainty as to
 the extent  of excavation necessary to en-
 sure that future users of the site would not
 be exposed to chemical contaminants, the
 high cost and the uncertainty of the cost
 to carry out  the site reclamation,  and
 worker safety during site excavation.

 The Problem  of Extremely
 Hazardous Waste
   The  disposal  of  dioxin-contaminated
 waste poses  a serious problem through-
 out Europe. No satisfactory means for its
 disposal has been approved in Sweden or
 Germany.  Until there is a safe, approved
 method for destruction or disposal, stor-
 age of the  material must continue. As the
 volume of stored dioxin-contaminated
 waste increases, so does the likelihood of
 accidental  release and exposure.  An im-
 portant need for the European community
 is an inventory of the stored dioxin waste,
 an estimate of the extent of such waste
 that remains  buried,  and  an agreement
 regarding the  final disposal or destruction
 of dioxin wastes.

 On-Site Disposal Versus
 Removal
   Only a  few sites  were encountered
 where waste is being treated for  disposal

-------
on-sfte. One such she, the industrial site
near Dortmund, involved on-s'rte treatment
of contaminated waste  and soil.   Soils
were treated by mixing with brown coal fly
ash. The mixture hardens as it cools and
the solidified material retains the contami-
nants,  even if exposed to water.  At the
B.T. Kemi site in Sweden, a forced leach-
ing technique  was  applied to  remove
chemicals (phenoxyacids) from low and
medium contaminated soils.  At all  other
sites, the cleanups  involved  excavation
followed  by treatment and/or disposal at
licensed  off-site facilities for most  highly
contaminated waste  and soil.  Less se-
verely  contaminated material (a notably
subjective description) was usually dis-
posed  in a semi-isolated, on-site cell.

Criteria for Cleanup
  None of the countries addressed in this
report  have established statutory limits for
contaminants in soil, nor are there gener-
ally applicable rules  for  determining
whether a given site is suitable for a spe-
cific use.  Guidelines  have been devel-
oped in England and in the Netherlands
to be  applied in site assessments when
contaminated soil is encountered. In En-
gland,  the guidelines, called Tentative Trig-
ger Concentrations, developed by  the
ICRCL, are recognized for site  assess-
ments  throughout the U.K.  The Trigger
Concentrations pertain to specific contami-
nant levels  in soils  below which a  site
could be regarded as uncontaminated. In
the Netherlands, soil assessment levels
are recommended by the Ministry of Hous-
ing,  Physical Planning and the Environ-
ment.   These guidelines all emphasize
the importance of site investigations  and
assessments.
   Protection of groundwater is  of fore-
most concern  in the Netherlands and in
the then FRG. A large portion of drinking
water  in these countries is  taken from
groundwater.
                                                                         •&U.S. GOVERNMENT PRINTING OFFICE: 1992 - 648-080/40242

-------

-------
   Garrle Kingsbuiy, and Tayler Bingham are with Research Triangle Institute,
   Research Triangle Park, NC 27709.
   Naomi Barkley is the EPA Project Officer (see below).
   The complete report, entitled "Reclamation and Redevelopment of Contaminated
     Land:  Volume II. European Case Studies," (OrderNo. PB92-146166/AS; Cost:
           $35.00, subject to change) will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA 22161
           Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
           Risk Reduction Engineering Laboratory
           U.S. Environmental Protection Agency
           Cincinnati, OH 45268
United States
Environmental Protection
Agency
Center for Environmental
Research information
Cincinnati, OH 45268
     BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT NO. G-35
Official Business
Penalty for Private Use $300
EPA/600/SR-92/031

-------