United States
Environmental Protection
Agency
Risk Reduction
Engineering Laboratory
Cincinnati, OH 45268
Research and Development
EPA/600/SR-93/152    September 1993
Project  Summary
Airborne Asbestos
Concentrations  Three  Years After
Abatement in  Seventeen
Schools
John R. Kominsky, Ronald W. Freyberg, James A. Brownlee,
Donald R Gerber, Gary J. Centifonti, and Kim A. Brackett
  From 1988 through  1991, the U.S.
Environmental  Protection  Agency's
(EPA) Risk Reduction Engineering
Laboratory (RREL) and the New Jersey
Department of Health's (NJDOH) Envi-
ronmental  Health  Service (EHS) con-
ducted air monitoring in 17 schools in
New Jersey to determine the effective-
ness  of their asbestos control pro-
grams. In 1988, a study was conducted
to document Asbestos  Hazard Emer-
gency Response  Act final  clearance
concentrations of asbestos at these 17
schools. The findings of this study
prompted a followup study  in 1990 to
determine the airborne asbestos con-
centrations  2 yr after  the  abatement
efforts in these schools. Although  the
data from the 1990 study provided in-
formation regarding airborne asbestos
levels during simulated occupancy con-
ditions 2 yr after  abatement, whether
these  data were representative of lev-
els during actual occupancy was
equivocal. Another followup study was
conducted in May 1991 to  determine
the airborne asbestos concentrations
in these 17 schools during  actual  oc-
cupied conditions. Eight of the sites
showed airborne asbestos levels above
the AHERA criteria  of 70 s/mm2.
Reentrainment  of  residual  asbestos-
containing debris from the 1988 abate-
ment  or operations and maintenance
(O&M) activities may have contributed
to the elevated  airborne asbestos con-
centrations measured during the May
1991 study.
   This Project Summary was developed
by EPA's Risk  Reduction Engineering
Laboratory, Cincinnati, OH, to announce
key findings of the research project
that is fully documented in a separate
report of the same title  (see Project
report ordering information at back).

Introduction
   T'ne ultimate  goal of every asbestos
abatement project is to eliminate or re-
duce, to the extent possible, the actual or
potential hazard presented by airborne as-
bestos structures. From 1988 through
1991, the EPA's RREL and NJDOH's EHS
conducted a series of studies to deter-
mine the effectiveness of asbestos control
programs in 17 schools in New Jersey.
  The 1988 study documented Asbestos
Hazard  Emergency  Response  Act
(AHERA) clearance air-sampling practices
and final clearance concentrations of air-
borne asbestos at 20 abatement projects
in 17 New Jersey schools. The results of
the study prompted  a followup study in
1990 (Phase II) to determine the airborne
asbestos concentrations  in  these 17
schools 2 yr after abatement. Although
the data from the 1990 study provided
information regarding airborne asbestos
levels  under simulated occupancy condi-
tions, whether the data were representa-
tive of conditions during actual occupancy
remained equivocal.
  Therefore, an additional followup study
was conducted in May 1991 (Phase III) to
determine the airborne asbestos levels dur-
ing actual occupied conditions 3 yr after
abatement in these same schools. The 17
schools  were not a statistical random
sample; their selection was based largely
on availability. Furthermore, because the
                                                  Printed on Recycled Paper

-------
17 schools were  likely to differ  in their
abatement history and status with respect
to  the presence  of  asbestos-containing
material, a site-by-site evaluation was per-
formed. No  consideration  was given to
combining data across all sites to  reach a
general conclusion.

Objectives
  The objectives  of the Phase  III study
were: (1) to determine the airborne asbes-
tos levels measured under occupied con-
ditions in 17 schools that underwent abate-
ment  in 1988, (2) to determine whether
the airborne asbestos levels measured un-
der occupied conditions in 1991 were sig-
nificantly  different from those measured
outdoors,  (3) to determine whether the
airborne  asbestos concentrations mea-
sured in 1991 were significantly different
from the AH ERA clearance concentrations
measured in 1988, and (4) to determine
whether the airborne asbestos concentra-
tions measured under occupied conditions
in  1991 were significantly different from
those measured  under simulated occu-
pancy conditions in 1990.

Study Sites
  The study summarized  here was con-
ducted at the same 17 schools involved in
the 1988 EPA-RREL/NJDOH-EHS study,
which documented AHERA air monitoring
practices and final clearance  concentra-
tions of airborne asbestos,  and in the 1990
EPA-RREL/NJDOH-EHS  study,  which
measured airborne  asbestos  concentra-
tions 2 yr after abatement.
  The 17 schools involved 20  abatement
sites.  Access to each school was coordi-
nated directly by NJDOH-EHS. Area air-
borne asbestos concentrations were mea-
sured at each site in the  same three ar-
eas as in the previous studies:  (1) the
previously abated area, (2) the perimeter
area (outside the  abated area but inside
the building), and (3) outdoors. The actual
abatement and perimeter areas could not
be separated because the containment
barriers present during the 1988 abate-
ment had been removed. Also recognized
was  the  fact that,  in the interim since
1988, other sources (e.g.,  routine  mainte-
nance of asbestos-containing resilient floor
tile or other O&M activities)  may have
contributed to the current concentrations
of  airborne asbestos.

Air Sampling Strategy

Phase III-May 1991
  At each site, five area air samples and
three  quality assurance  samples (one
closed and two open field blanks) were
collected  at approximately the same loca-
tions as those collected during the 1988
and 1990 studies. The samples were col-
lected during school hours,  8:00  am to
3:00 pm. Because certain sampling situa-
tions (e.g., inside a classroom) could not
tolerate  noise from  an  electrically pow-
ered sampling  pump,  the pumps were
placed in special acoustical  cases de-
signed to attenuate the noise of the sam-
pling pump to a sound pressure level of
<40 dB (RE 20 N/m2) at a distance  of 3 ft.
A noise  level of 40 dB  is rated as  "quiet"
for private offices and conference rooms.

Phase III Followup - Summer 1991
  Followup air sampling in the previously
abated work  area and in the  perimeter
area was conducted during  unoccupied
conditions in  accordance with a modified
aggressive sampling protocol designed to
simulate normal building activity. The pro-
tocol involved sweeping  only the floors
with the  exhaust of a 1 -hp leaf blower at a
rate of 5 min/1,000 ft2 of floor space. One
stationary fan (18-in. diameter, axial flow)
per 10,000 ft3 was positioned with  the air
directed toward the ceiling to maintain air
movement during sampling.

Phase Ilia - Early August 1991
  Followup air monitoring was conducted
in August 1991 at 10 of the 20 sites (Sites
B, D-H, K, M  ,N, and  Q). Sites B, D-G, K,
and M were selected  because the aver-
age  airborne asbestos  concentration in
the previously abated area and/or  perim-
eter area exceeded  0.02 asbestos struc-
ture per cubic centimeter (s/cm3). Sites N
and Q were also monitored because these
sites were in the same schools as sites K
and B, respectively, which had  levels ex-
ceeding  0.02 s/cm3. Site H was monitored
because  replicate analyses  of selected
samples at this site  showed  average as-
bestos levels above 0.02 s/cm3. This value
(0.02 s/cm3) is  derived from  the AHERA
40 CFR  763 initial screening criteria of 70
s/mm2. At each of the 10 sites, 5 area air
samples and 3 quality assurance samples
were collected in the same three areas as
the samples collected during occupied con-
ditions in May 1991.

Phase Illb - Late August 1991
  Based  on  the results of the Phase Ilia
monitoring,  four schools  (Sites F,  G, H,
and M) were required to conduct response
actions  (i.e.,  cleaning)  in the previously
abated area and/or perimeter area to re-
duce residual airborne asbestos contami-
nation. After these response  actions, ad-
ditional area air samples were collected.
At each  of the four schools, five area air
samples and three  quality  assurance
samples were collected in the same areas
as were the Phase III  and  Phase  Ilia
samples (no outdoor samples were col-
lected at Site M).

Phase Illc - September 1991
  Airborne asbestos concentrations at Site
M were still elevated after the Phase  Illb
monitoring.  Therefore,  the  previously
abated  area and  the perimeter area  re-
sponse actions were again conducted, and
five additional  samples  and one  closed
and two open field blanks were collected
in these areas.

Site Documentation
  For each of the  17 schools monitored in
May  1991, the NJDOH-EHS documented
the history of the abatement activities  be-
tween 1988  and 1991 and  the O&M  ac-
tivities  on any  remaining  asbestos-con-
taining  building material  (ACBM)  in  the
previously abated area and perimeter area.
This information was obtained from abate-
ment notices required under the New Jer-
sey Administrative Codes (N.J.A.C. 8:60-
7 and N.J.A.C. 12:120-7), AHERA Asbes-
tos  Management  Plans,  and  information
provided by the designated person and/or
school officials who  were interviewed.

NJDOH Visual Inspection
  After  conducting the followup air moni-
toring at the eight  schools, which involved
10 sites, in August  1991 (Phase  Ilia), a
certified AHERA building inspector from
NJDOH-EHS visually inspected each of
these schools.  Before conducting  the in-
spection, the  inspector  reviewed each
school's Asbestos Management Plan. The
review included (1) recording the material
category (e.g., thermal system  insulation),
amount  of material (e.g., linear feet), and
condition of material (e.g., damaged ther-
mal system insulation) for the ACBM  re-
maining in the previously abated area and
perimeter area; (2)  recording  completed
response actions (including O&M);  and
(3)  recording any renovations that  had
occurred.

Sampling Methods

Fixed-Station Area Air Samples
  Air  samples were collected on open-
face, 25-mm-diameter, 0.45-u,m-pore-size,
mixed cellulose ester (MCE)  membrane
filters with a 5-(o.m-pore-size,  MCE, backup
diffusing filter and cellulose support pad
contained in a three-piece cassette. The
filter  cassettes  were positioned approxi-
mately 5 ft above the floor on tripods, with
the filter face at approximately a  45-de-
gree angle toward the floor. The filter  as-
sembly  was  attached to  a 1/6-hp  electri-
cally powered vacuum pump operating at

-------
a flow rate of approximately 9 L/min. Air
volumes ranged from 943 to 2536 L. At
the end of the sampling period, the filters
were turned upright before being discon-
nected from the vacuum pump; they were
then stored in this position. The sampling
pumps were calibrated  with a calibrated
precision rotameter both immediately be-
fore and after sampling.

Bulk Samples
   Bulk  samples of suspect ACBM (e.g.,
thermal system insulation, fireproofing, and
resilient floor tile) or debris were collected
by  the NJDOH inspector for laboratory
analysis to determine the asbestos con-
tent. The  samples were collected  by ei-
ther a standard coring tool or the collec-
tion of debris. Both types of samples were
placed in labeled containers.

Analytical Methods

Air Samples
  The MCE filters were prepared  and ana-
lyzed in accordance with the nonmandatory
transmission electron microscopy  (TEM)
method, as described in the AHERA final
rule (40 CFR 763). A sufficient number of
grid openings were  analyzed for  each
sample  to  ensure a sensitivity (the con-
centration represented by a single struc-
ture) of no greater than  0.005 s/cm3 of air
sampled.  In addition to the  requirements
of the nonmandatory TEM method, the
specific length and width of each  structure
were measured and  recorded.  The
samples were prepared and analyzed by
EPA's TEM laboratory in Cincinnati, OH.

Bulk Samples
   The type and percentage of asbestos in
the bulk samples were determined by po-
larized light microscopy and X-ray diffrac-
tion. The samples were prepared  and ana-
lyzed in  accordance with  the "Interim
Method for Determination of Asbestos in
Bulk Insulation Samples" (EPA 600/M4-
82-020). The samples were prepared and
analyzed  by the NJDOH's Public  Health
and Environmental Laboratories in Tren-
ton, NJ.

Statistical Methods
   Airborne asbestos concentrations mea-
sured in each of the three sampling loca-
tions were characterized by the use  of
descriptive statistics. Because the 20 sites
were likely to differ in their abatement
history and status with respect to the pres-
ence of asbestos-containing material, each
site was considered separately. The de-
scriptive statistics included the arithmetic
mean, minimum and maximum concentra-
tions, and sample size.
  A  single-factor analysis of variance
(ANOVA) was used to examine differences
between  concentrations measured in the
previously abated work area,  perimeter
area, and outdoors for each site. A single-
factor ANOVA analysis  was also  used to
compare  airborne asbestos concentrations
measured in  1988,  1990, and 1991 for
each sampling location.  All statistical com-
parisons  were performed at the 0.05 level
of significance.

Quality  Assurance
  Specific quality assurance procedures
outlined in the AHERA  rule were  used to
ensure the precision of  the collection and
analysis of air samples, including  filter lot
blanks, open  and closed field blanks, and
repeated sample analyses.

Site Descriptions
  Post-1988  abatement occurred at 1 of
the 20 sites  (Site O)  in the  previously
abated area and at 4 of  the 20 sites (Sites
A, D, L,  and  N) in the perimeter area. At
15 sites,  ACBM is still present in the pre-
viously abated  areas; at  all of the  sites,
ACBM is still  present in the perimeter ar-
eas.

Airborne Asbestos Levels During
Occupied Conditions In May 1991
  Table  1 presents the mean, minimum,
and maximum airborne  asbestos  concen-
trations measured at  each of the  20 sites
in the 17 schools. Figure  1  illustrates the
average  airborne asbestos concentrations
in the previously abated  and perimeter
areas. Eight of the 20 sites showed  levels
above the AHERA initial  screening crite-
rion of 70 s/mm2 (40 CFR 763) and above
0.02 s/cm3 (NJDOH clearance criterion).

Comparison of Previously Abated
Area With Outdoors
   At 6 of the  20 sites (Sites B, E,  F, G, K,
and  Q),  mean airborne asbestos  concen-
trations in the previously abated area were
significantly  higher than were those out-
doors. Mean  concentrations in the  previ-
ously abated  area were at least one order
of magnitude (i.e., 10 times) greater than
were the mean concentrations outdoors.
At all of  the other 14 sites, the difference
between mean  levels  in  the  previously
abated areas and outdoors was not  statis-
tically significant.

 Comparison of Perimeter Area
 With Outdoors
   At 4 of the 20 sites (Sites B, F, N, and
Q),  mean airborne  asbestos concentra-
tions in  the  perimeter  area were signifi-
cantly higher (at least one order of magni-
tude)  than  were those outdoors. At the
remaining 16 sites, the difference between
mean levels in  the perimeter areas and
the outdoors was not statistically signifi-
cant.

Comparison of Previously Abated
Area With the Perimeter Area
  At 3 of the 20 sites (Sites E, G, and K),
mean airborne asbestos concentrations in
the previously abated area were signifi-
cantly greater than were those in the pe-
rimeter area.  Mean concentrations in the
previously abated area were approximately
4 times greater than  were those in the
perimeter area at Site E, approximately 5
times greater at Site G, and approximately
14 times greater at Site K. At all of the
other 17 sites, the  difference  between
mean concentrations in the previously
abated area and the perimeter areas was
not statistically significant.

Overall Structure Morphology and
Length Distributions
  The TEM analysis  of 100 samples col-
lected during occupied conditions in the
previously  abated area,  94 samples col-
lected in the  perimeter  area,  and 85
samples collected outdoors yielded a total
of 601 asbestos structures,  99.7% of which
were  chrysotile asbestos and 0.3% were
amphibole. Overall, the asbestos  struc-
tures were  primarily fibers (66%), and to a
lesser extent, matrices, bundles, and clus-
ters.
   Overall,  1.5% of the measured asbes-
tos structures were greater than 5  u,m in
length; most of  the structures  (92%) were
less than 2 |o.m  in length.

Phase III Follow-up Air Monitoring-
August1991
   Followup air monitoring was conducted
by EPA-RREL/NJDOH-EHS in August
1991  at 10 of the 20 sites (B, D-H, K,  M,
N,  and  Q). These sampling results indi-
cate  that four  sites  (F, G,  H, and M)
showed average levels exceeding 0.02 s/
cm3 in  both the previously  abated area
and the perimeter areas.  Based on the
results  at these four  sites, NJDOH-EHS
required response action  at each of the
four schools. Three  of  the four schools
employed  licensed asbestos-abatement
contractors and one used in-house, trained
staff  to conduct response actions  to re-
duce the levels of airborne asbestos.
   After the response actions at these four
schools, EPA-RREL/NJDOH-EHS  con-
ducted  followup air  monitoring to  deter-
mine the residual levels of  airborne as-
bestos. Based on these sampling results,
NJDOH-EHS determined that further ac-

-------
 Table 1. Airborne Asbestos Concentrations* Measured During Periods of Occupancy at Seventeen Schools in May 1991
                 Previously abated area
 Site

 A
 B
 C
 D
 E
 F
 G
 H
 I
 J
 K
 L
 O
 P
 Q"
 R
 S
 T
Mean
Minimum
                       Maximum
0.001
0.027
0.005
0.020
0.037
0.043
0.027
0.004
0.004
0.003
0.041
0.006
0.023
0.004
0.005
0.004
0.009
0.005
0.001
0.001
0
0.01
0
0.003
0.011
0.032
0.011
0
0
0
0.014
0
0
0.003
0
0
C
0
0
0
0.003
0.055
0.012
0.059
0.069
0.066
0.037
0.014
0.007
0.011
0.097
0.016
0.056
0.009
0.022
0.011
0.018
0.010
0.004
0.007
                          Mean


                          0.003
                          0.012
                          0.001
                          0.004
                          0.010
                          0.036
                          0.005
                          0.005
                          0.005
                          0
                          0.003
                          0.003
                          0.004
                          0.015*
                          0
                          0.001
                          0.012
                          0.001
                          0.003
                          0.001
Perimeter area


  Minimum

     0
     0004
     0
     0
     0
     0.010
     0
     0
     0
     0
     0
     0
     0
     0
     0
     0
     0.004
     0
     0
     0
Outdoors
Maximum
0.008
0.024
0.003
0.009
0.029
0.058
0.011
0.011
0.011
0
0.007
0.006
0.007
0.046
0
0.004
0.024
0.004
0.011
0.004
Mean
0.003
0.001
0.003
0.004
0.003
0.001
0.001
0.003
0.005
0.001
0
0
0.003
0
0.001
0
0.001
0.004
0.001
0
Minimum
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Maximum
0.005
0.004
0.007
0.012
0.007
0.002
0.004
0.006
0.020
0.004
0
0
0.007
0
0.003
0
0.004
0.012
0.004
0
 'Asbestos concentration, s/cm3 (N=5)
 ' Outdoor samples are the same as those collected at Site C (i.e., Site M was the second abatement project at this site).
 ' Outdoor samples are the same as those collected at Site K (i. e., Site M was the second abatement project at this site).

 " Perimeter and outdoor samples are the same as those collected at Site 3 (i.e., Site Q was the second abatement project at this school).
tion was required at Site  M. Further re-
sponse  actions were performed  at this
school,  and NJDOH-EHS  collected addi-
tional samples. The final results showed
an average concentration  of 0.005 s/cm3
in the previously abated area and 0 s/cm3
in the perimeter area; therefore, no further
action was required at this school.


NJDOH  Visual Inspections
  Asbestos-containing debris  (including
fireproofing, thermal system insulation, ceil-
ing tile,  and plaster dust) was present at
all of the  10  sites.  The  sources of  the
debris were the 1988 abatement, abate-
ments that occurred  after 1988, and/or
O&M activities.
   Six sites (B, E, F, K, H, and Q) con-
tained at least one ACBM not identified in
the  original AHERA  inspection;  i.e.,  the
original  AHERA inspection did not record
the presence of this material in  the Man-
agement Plan for the school. The previ-
ously  unidentified  materials included ven-
tilation duct insulation and TSI.  (These
data were  provided to the school officials,
and the  schools have reportedly corrected
their Management Plans accordingly.)
   At  one  site (Site  F), the Management
Plan was in error regarding the identifica-
                             tion  and location of asbestos-containing
                             material  (ACM). The  Management  Plan
                             indicated the presence of spray-on mate-
                             rials. No spray-on materials were present;
                             however, TSI was found. (These data were
                             provided tc  the  school  officials,  and the
                             school has reportedly corrected  its Man-
                             agement Plan accordingly.)

                             Post-Abatement (1988) versus
                             Simulated Occupancy (1990)

                             Previously Abated Area
                               On average,  concentrations measured
                             during simulated occupancy (1990) in the
                             previously abated area were  significantly
                             less  than  were the post-abatement  con-
                             centrations (1988) at  11 of the  20  sites
                             (Sites C, D,  F, H, J-N, Q, and T). At the
                             remaining nine sites, no significant differ-
                             ences were noted.

                             Perimeter Area
                               On average,  concentrations measured
                             during simulated occupancy (1990) in the
                             perimeter area were significantly less than
                             were  the  post-abatement  concentrations
                             (1988) at 5 of the 20 sites (Sites D, H, L,
                             P, and T). At only one of the sites was the
                             mean  concentration significantly greater
                             during simulated occupancy than during
                                                             post abatement (Site R). At the remaining
                                                             14 sites,  no significant differences were
                                                             noted.

                                                             Outdoors
                                                               On average, concentrations  measured
                                                             outdoors  in 1990 were significantly less
                                                             than  were  concentrations measured  in
                                                             1988 at 2 of the 20 sites (Sites D and N).
                                                             At only one site was  the mean  outdoor
                                                             concentration greater in 1990 than in 1988
                                                             (Site  R).  At the  remaining  17 sites, no
                                                             significant differences were noted.

                                                             Post-Abatement (1988) versus
                                                             Occupied Conditions (1991)

                                                             Previously Abated Area
                                                               On average, concentrations  measured
                                                             in the previously abated area during occu-
                                                             pied conditions (1991)  were  significantly
                                                             less than were the post-abatement con-
                                                             centrations  (1988)  at  8 of the 20 sites
                                                             (Sites  C,  D, H, L-N,  Q, and  T). At two
                                                             sites  (Sites E  and G), mean  concentra-
                                                             tions  of  airborne  asbestos  were  signifi-
                                                             cantly higher in the previously abated area
                                                             during occupied conditions in  1991 than
                                                             they were post-abatement in 1988. At the
                                                             remaining  10  sites, no significant differ-
                                                             ences were noted.

-------
Perimeter Area
  On average,  concentrations  measured
in the perimeter area during occupied con-
ditions (1991) were significantly less than
were  the  post-abatement concentrations
(1988) at 5 of the 20 sites (Sites D, H, L,
P, and T). At only one of the sites (Site F)
was the mean concentration significantly
greater during occupied conditions than
they were post abatement in 1988. At  the
remaining 14 sites,  no  significant differ-
ences were noted.

Outdoors
  On  average,  concentrations  measured
outdoors  in  1991 were  significantly less
than  were concentrations measured  in
1988  at 2  of the 20 sites (Sites  D and  N).
The mean  outdoor  concentration was
greater in  1991  than  in  1988 at two sites
(Sites A and E). At the remaining 16 sites,
no significant differences were noted.

Simulated Occupancy (1990)
versus Occupied Conditions
(1991)

Previously Abated Area
  On  average,  concentrations  measured
in the previously abated area during occu-
pied conditions  (1991) were  significantly
greater than were those measured during
simulated occupancy  (1990) at 7 of the 20
sites  (Sites  D-G, K,  M, and R).  At the
remaining  13 sites,  no significant differ-
ences were noted.

Perimeter Area
  On  average, concentrations  measured
during occupied  conditions  (1991) were
significantly greater than were those mea-
sured in the perimeter area during simu-
lated occupancy (1990) at only 1 of the 20
sites  (Site  F).  Conversely,  on average,
Site R showed  significantly  greater con-
centrations during simulated occupancy
than during actual occupied conditions. At
the remaining  12 sites, no significant dif-
ferences were  noted.

Outdoors
  Mean outdoor concentrations of airborne
asbestos measured in 1991 were signifi-
cantly  greater  than were concentrations
measured in  1990 at 2 of the 20 sites
(Sites A and E). At the remaining 16 sites,
no significant differences were noted.

Conclusions
  Seven of the 20  sites  (5 of the 17
schools)  sampled under occupied condi-
tions in 1991  showed significantly higher
airborne  asbestos  concentrations in  the
previously abated area and/or the perim-
eter area than did those existing outdoors.
Differences in  mean concentrations  be-
tween those measured inside the schools
and those existing outdoors were not sta-
tistically significant at the other 13 sites.
  Eight of the 20 sites showed average
airborne  asbestos  concentrations above
the AHERA initial screening criterion of 70
s/mm2. Visual  inspections  conducted by
the NJDOH  indicated that reentrainment
of residua! asbestos-containing debris from
the 1988 abatement  or from  O&M activi-
ties may  have  contributed to the elevated
asbestos concentrations  measured in
these schools.
  At the 10 sites where followup air moni-
toring was conducted in 1991, visual in-
spections conducted  by the NJDOH-EHS
showed that 6 sites had at least one ACM
that  was not  identified in  the Asbestos
Management  Plan. At one of  these  six
sites, the Asbestos Management Plan was
in error regarding the identification, loca-
tion,  and  condition of  ACM.
  Three  of the 20 sites showed  signifi-
cantly  higner  airborne asbestos concen-
trations in the previously abated area and/
or the perimeter area in  1991  than  did
those measured in 1988. Conversely, 9 of
the 20  sites showed significantly  lower
airborne asbestos concentrations in  the
previously abated area and/or perimeter
areas in 1991  than  those measured in
1988. Differences between mean  concen-
trations  measured in  1988 and  1991  at
the other eight sites were  not statistically
significant.
  The mean airborne asbestos  concen-
trations  measured in the previously abated
area and/or the perimeter area at 7 of the
20 sites during occupied conditions in 1991
were significantly greater than were those
measured under simulated occupancy con-
ditions  in 1990.  Conversely, one  site
showed significantly lower concentrations
during occupied conditions  than during
simulated occupancy. Differences  in mean
concentrations  measured in 1990  and
1991 at the other 12 sites were not statis-
tically significant.

Recommendations
  Followup air monitoring should  be con-
ducted  at these schools  to  determine if
elevated post-abatement airborne  concen-
trations  of  asbestos   is  continuing.  The
followup air monitoring should be  coupled
with detailed visual inspections to deter-
mine the sources of the asbestos and to
identify  appropriate  remedial measures.
The results of the followup study  will pro-
vide information regarding the long-term
effectiveness of  asbestos control pro-
grams. This  information  may  assist EPA
in  evaluating the need  for  issuance  of
guidance on asbestos management  prac-
tices.
  The full report was  submitted  in partial
   fulfillment of Contract No. 68-D2-0058,
Work  Assignment No. 1-18,  by Environ-
mental  Quality  Management, Inc. under
subcontract to Pacific Environmental Ser-
vices, Herndon, Virginia 22070. This work
was conducted  under the sponsorship of
the U.S. Environmental Protection Agency.

-------
       I
       I
              0.05
              0.04
              0.03
              0.02
0.01
          o

          §
         O

              0.05
              0.04
0.03
              0.02
              0.07
                                                                                               Previously abated area
                    A    BCDEFGHIJ    KLMNOPQRST
                    A    BCDEFGHIJ    KLMNOPQRST
                                                                                                                          0.05
                                                                                                                        _ 0.04
                                                                                                                      	0.03
                                                                                                                     	0.02
                                                                                                                          o.or
                                                                                                                    	., 0.05
                                                                                                                  	  0.04
                                                                                                              	0.03
                                                                                                            0.02
                                                                                                         	'. 0.01
                                                                                                                     ->    o
Figure 1.   Average airborne asbestos concentrations (s/cm3) in the previously abated area (top) and perimeter area (bottom) measured during occupied

           conditions in May 1991.
                                                                                   ŁU.S. GOVCtNMENT PRINTING OFFICE: 1993 - 7SO-07I/800JM

-------

-------
   J.R. Kominsky and R.W. Freyberg are with the Environmental Quality Manage-
     ment, Inc., Cincinnati, OH 45240; J.A. Brownlee, D.R. Gerber, and G.A.
     Centifonti are with the New Jersey Department of Health, Environmental
     Health Service, Trenton, NJ 08625; Kim A. Bracken is with the International
     Technology Corporation,  Cincinnati, OH 45246
   Thomas J. Powers is the EPA Technical Project Officer (see below)
   The complete report, entitled "Airborne Asbestos Concentrations Three Years
       After Abatement in Seventeen Schools," (Order No. PB93-218501AS;
       Cost: $27.00, subject to change)  will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA 22161
           Telephone: 703-487-4650
   The EPA Project Officer can be contacted at:
           Risk Reduction Engineering Laboratory
           U.S. Environmental Protection Agency
           Cincinnati, OH 45268
United States
Environmental Protection Agency
Center for Environmental Research Information
Cincinnati, OH 45268

Official Business
Penalty for Private Use
$300
      BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
EPA/600/SR-93/152

-------