United States
                Environmental Protection
                Agency
 Risk Reduction
 Engineering Laboratory
 Cincinnati, OH 45268
                Research and Development
 EPA/600/SR-94/142    September 1994
EPA       Project Summary
                Field  Investigation  of
                Effectiveness  of Soil Vapor
                Extraction  Technology
                Michael H. Corbin, Nancy A. Metzer, and Michael F. Kress
                  A research project was undertaken
                to study the effectiveness of soil vapor
                extraction (SVE), an emerging technol-
                ogy for remediation of soils contami-
                nated with volatile organic compounds
                (VOCs). As part of the project, two soil
                vapor extraction systems, Site D and
                Site G at the Twin Cities Army Ammu-
                nition Plant, were  selected for evalua-
                tion.
                  Site  information regarding  residual
                soil concentrations  before and after
                treatment were gathered to compare
                residual levels of volatile organics be-
                fore and after treatment. Operational
                data are analyzed to present  the per-
                formance of the systems and  the pro-
                gression of treatment with time. Capital
                as well as operating and  maintenance
                costs are presented.
                  Results of the evaluation indicate that
                soil vapor  extraction  has been  effec-
                tive in reducing the residual  concen-
                trations, generally  by several orders of
                magnitude. In most cases, residual con-
                centrations were non-detectable. The
                variability of the concentrations, when
                detectable, also decreased. Samples
                taken in silty clays and waste materials
                showed the highest residual  concen-
                trations. Operational data indicated that
                mass removal rates decreased rapidly
                during the  first few days of treatment
                and, within a few months,  reached a
                level one tenth of the initial rates.
                  This Project Summary was developed
                by EPA's Risk Reduction Engineering
                Laboratory, Cincinnati, OH, to announce
                key findings  of the research project
                that is fully documented In a separate
report of the same  title (see Project
Report ordering information at back).

Introduction
  The purpose of this project was to char-
acterize and assess the effectiveness of
SVE in reducing the concentration of VOC
soil contamination.
  SVE,  an  emerging technology  for
rennedatiing soils contaminated with VOCs,
is done by mechanically drawing  air
through the contaminated soils in the  va-
dosse (unsaturated) zone. An array of sub-
surface vents  is  installed  in  the
contaminated area. A vacuum pump is
then manifolded to the vents to induce air
flow. The VOC-laden air is drawn from  the
soils to the  vents, through the manifold
and pump, and is either discharged to  the
atmosphere  or treated before discharge,
depending on specific site considerations.
  Initially, attempts at determining the ef-
fectiveness of the technology used a mass
balance approach.  This  involved a
preremediation site characterization to de-
termine the quantity (in pounds) of con-
taminants in the soils, measurement of
the  total mass of contaminants removed
during remediation, and a post-remediation
site characterization to determine the quan-
tity of residual contaminants remaining in
the  soils after treatment. Because of the
high cost of soil sampling and  analysis
and the heterogeneous nature of soil con-
tamination, the mass balance cannot  be
done with much precision unless exten-
sive resources are expended. This has
not proven to be a reliable, cost-effective
means of assessing the system's effec-
tiveness.
                                                                 Printed on Recycled Paper

-------
  Subsequent efforts have focused on
determining the residual concentrations of
contaminants remaining in the  soil after
the effluent air contaminant concentrations
drop to a very low level when compared
with the initial concentrations. The premise
behind this approach is that if the soils
have low or nondetectable levels of con-
taminants, they can be considered  clean.
Many Superfund  site remediation  plans
specify soil cleanup concentration  levels
using risk-based  analysis  or regulatory
standards. To date, no full-scale SVE sys-
tems documented in the  literature have
reached a final site cleanup stage  based
on stipulated  soil cleanup levels and post-
treatment sampling.
  The  following approach was identified
to meet the project objectives. A literature
search and a review of internal projects
identified sites employing  SVE technol-
ogy. Site evaluations were based on the
duration of the SVE system operation, the
quality of site characterization, the amount
and  availability of operational  data, the
willingness of the site owner/operators to
participate in the project, and the site char-
acteristics, such as soil type, contaminant
type, and size. After site selection, site
information regarding soil VOC concen-
trations before treatment  was  obtained.
Operational data from the system owners/
operators were obtained  and evaluated
with respect  to  system performance. A
soil sampling program to evaluate the re-
sidual  contamination levels  remaining in
the treated soils was performed. The ini-
tial and  current contamination levels in
terms of magnitude and distribution of con-
tamination were compared. The two SVE
systems  (Site D and Site G) at the Twin
Cities  Army  Ammunition  Plant in New
Brighton, MN, were selected  for this
project.
  Site  D is the location of former  leach-
ing/burn  pits where solvents,  explosive
primer wastes, and other combustibles
were disposed of through open burning.
The surficial  geology of the site consists
of the  Arsenal sand, stained sediments,
and residues from burning activities. The
Arsenal sand consists of brown-gray, fine-
to-cparse sands and gravels. The stained
sediments  and residues consist of dark
gray-to-black, fine-to-coarse  sands  and
silts. The Arsenal sand extends below the
site to a depth of approximately 120 ft.
The contamination observed at Site D con-
sisted  primarily of  VOCs, ranging from
nondetectable (ND) to  7,000 mg/kg.
Trichloroethylene  (TCE)  and  1,1,1-
trichloroethane (TCA) comprised 71% and
20%, respectively, of the total VOCs and,
as such, were the primary contaminants.
The full-scale SVE system  was installed
at Site D in January  1986 following the
placement of a  soil  cover. The system
consists of 39 air extraction vents, placed
from 34  to 54 ft below ground surface
(bgs). The system layout is shown in Fig-
ure 1.
  Site G was an active landfill from the
1940s to the 1970s. The landfill contains
heterogeneous  materials,  ranging  from
sands to  clays to waste materials. Under-
lying the landfill  materials  is a silty clay
(Twin Cities Formation till). There were
some indications that the silty clay is con-
tinuous throughout the site. Beneath the
silty clay are the fine-to-medium-grained
Arsenal and Hillside sands. These sands
were encountered to a depth of 135.5 ft
bgs. The contamination observed at Site
G consisted primarily  of VOCs with total
VOC concentrations ranging from ND to
960 mg/kg. Most of the sample with high
total VOC concentrations were taken from
the waste material. TCE comprised 16%
to 88% of the total VOC concentrations. A
full-scale SVE system was installed at Site
G in February 1986 following  the place-
ment  of  a soil  cover. The system con-
sisted of  89 air extraction vents, installed
at depths ranging from 32 to 54 ft bgs. An
activated carbon vapor control system was
installed for emissions treatment. The sys-
tem layout is shown in Figure 2.
  As part of this project, seven soil borings
were installed at Site  D and seven more
at Site G in May  1989. Site D soil borings
were installed to depths ranging from 30
to 35 ft;  samples were collected at ap-
proximately  10-ft intervals.  Site G  soil
borings were installed to depths ranging
from 15 to 60 ft; samples were collected
at 15-ft intervals. The  samples  were ana-
lyzed for TCE  and  TCA  (EPA Method
5030/8010),  full VOC analysis  (EPA
Method  8240),  and  moisture  content
(ASTM Method D2216).

Results

Soils
   In general, the concentrations at Site D
have been reduced by four or five orders
of  magnitude   to   levels   that   are
nondetectable or in the very low parts per
billion (ppb). Only 5 of 21  samples had
detectable VOC concentrations; the high-
est was 29 ppb TCE. TCA was detected
in only one sample at a concentration of
0.8 ppb.  In comparison, TCE concentra-
tions before treatment were reported as
high as 7,000 parts per million (ppm).
  The moisture content of the soils at Site
D ranged from  1.7% to 14%  and aver-
aged  approximately 6.1%.  This  may be
compared with pretreatment levels of 3.3%
and 4.6% in  two samples collected and
analyzed during the initial site investiga-
tion. These results do not indicate a sig-
nificant change in the soil moisture content
over the treatment period. This is interest-
ing: considering the large volume of air
that passed through these soils, one would
anticipate a  significant decrease in the
soil moisture. Because the site is capped,
however, the air was forced to flow through
a large volume of uncapped soil before
reaching the  treatment area,  and, there-
fore, the total volume of soil was too large
to be significantly dried. Finally, the mois-
ture content  results are  consistent  with
the previous  description  of  well-drained
soils.
  Split-spoon samples were obtained from
each soil boring installed at  Site G. The
number of  samples collected from each
boring  varied because of the subsurface
conditions  encountered  as  the borings
were advanced, e.g., a tar-like layer was
encountered at approximately 25 to 30 ft
in two  borings. When this layer was en-
countered, it was not possible to advance
the auger through the layer.
  The  VOC  concentrations  at Site  G
showed a higher degree of variability than
those at Site D. Concentrations of post-
treatment  total VOCs  ranged  from
nondetectable to 0.420  ppm. TCE and
TCA were detected at maximum concen-
trations of  0.420 ppm and  0.200 ppm,
respectively. In comparison, the maximum
concentrations  of TCE and  TCA in the
pretreatment  samples were 400 and 100
ppm, respectively, roughly three orders of
magnitude  greater than  after treatment.
Of the  21  samples, TCE or TCA  was
detected in 15 samples; however, only 6
of these 15 samples showed concentra-
tions above the detection limit (the other
results were estimated values). Of the six
samples showing concentrations above the
detection limit,  all were  composed  of a
waste material or had components of silt
or clay. The other samples were generally
composed of sandy soils. This  would be
expected because the volatile  compounds
should adsorb more strongly to silts, clays,
and waste  materials and  would therefore
be more difficult to remediate. Also, air
flow through these materials would be
much less than through sandy soils. There-
fore, the VOCs would be removed more
easily from the sand.

Operations
  The  mass removal rate (Ib/day) for Site
D is plotted against the days of  operation
in Figure 3. The  removal rate at the be-
ginning of operations was approximately

-------
                       	,	I	i
                               Building \
                             I2760CFM '  **-"—I
                                Total

_!!_!_	           _i
       I                                ~~
                                                                             j	i
                                                                             r                 r~
                                                                                  Legend
                                                                                    • Air Extraction Vent
                    Scale in Feet


Figure 1. Full-scale SVE system layout, Site D, Twin Cities Amy Ammunition Plant.


                                                             3

-------
                          Extent of Clay Cap
                                    Legend
                                      • Air Extraction Vent
                                                                                                           SO
Scale in Feet
                                                                                                                     100
Figure 2.  Full-scale SVE system layout, Site G, Twin Cities Army Ammunition Plant.

-------
1,200 Ib/day. It dropped to several hun-
dred pounds per day  within 1 wk and
continued to decline with time. As of June
1990, a cumulative total of 108,460 Ib of
VOCs had been removed from the soils at
Site D.
  The operational data plotted in Figure 3
suggest  a  logarithmic  decay in  the  re-
moval rate. Two curves that  approximate
the decay are shown on the graph. The
first curve, y = 895.7 - 305.64* log (x), is a
logarithmic function.  The second curve,
y = (1,000 + 3 x)/(1 + 0.09 x), is a hyper-
bolic function. Both curves simulate the
high initial removals, the rapid decrease,
and the tailing in later treatment. The hy-
perbola indicates a long period  of later
treatment characterized by low removals,
while the logarithmic decay indicates "zero"
removal at approximately 900 days of op-
eration.
  The  estimated installation cost for Site
D is $257,000. This cost does not include
design or construction management costs.
The operations and maintenance costs of
$194,000 are for the total operations pe-
riod from February 1986 to  May 1990.
The labor costs were estimated at 70% of
the Site  G system  costs,  since  specific
information for  the Site D system labor
was not available. The estimated present
worth was calculated by using a 4% infla-
tion rate compounded  annually  and an
additional 15% design/construction man-
agement cost on the capital costs. The
estimated volume of  soil treated, assum-
ing a 17 ft  radius of influence for each
vent, is 35,000 yd3. By estimating a present
worth of  $573,000 and the volume of soil
treated, the treatment cost per cubic yard
is $17.
  The mass removal rate (Ib/day) for Site
G is plotted against time (days of opera-
tion) in Figure 4. The maximum daily mass
removal  rate, 5,015 Ib/day, was encoun-
tered on the second day  of operations.
Within  2 wk  of operation, the mass re-
moval rate was below 1,000 Ib/day. It must
be  noted that the mass removal rates
were intentionally reduced during the ini-
tial stages of operations. The total VOC
mass removal rate continued to decrease,
reached  a removal rate of approximately
200 Ib/day after 76 days of operation, and
dropped below 50 Ib/day after 195 days of
operation. The system, as of 21 May 1990,
has removed  97,727 Ib of  VOCs.  The
mass removal rate for  the first 5 mo  of
1990 ranged from 1 to 10 Ib/day.
  As with Site D, hyperbolic and logarith-
mic functions were used to  approximate
the operational data. The equations  of
these lines are y = (1,500 -  1.1 x)/(1 +
0.08 x) and  y = 2357.4 - 922.53*  log (x)
for the  hyperbolic and logarithmic func-
tions, respectively. Although these func-
tions  can represent the  general  trends
seen  during the SVE system  operation,
these functions skew from the actual data
because they are unable to simulate  the
sharp decline of mass removal rates dur-
ing the initial operation while still simulat-
ing the asymptotic nature of  the  curve
during later stages of operations.  Addi-
tionally, the operational data vary  unpre-
dictably because of periods of inoperation
and initial manipulation of the operating
parameters to control the mass removal
rate.
  After September 1986, the Site G sys-
tem was operated with a vapor treatment
system. The vapor treatment system con-
sisted of two beds of carbon, initially con-
taining 6,500 to 9,600 Ib of carbon. The
length of time that the system was shut
down for changeouts varied greatly due to
logistical factors.  The carbon  treatment
system was deactivated  in April 1989 as
the mass removal rate dropped below a
level where VOC emissions would pose
any health threat. Through April 1989, a
total of 248,000 Ib of carbon was spent at
Site G.
  The estimated installation cost for Site
G is $257,000. This cost does not include
the design or construction  management
of the system. The capital cost of imple-
menting  the vapor control  system was
$213,000, bringing the total capital costs
to $467,000. Operation and maintenance
costs  include labor, power, system  moni-
toring, and carbon changeouts  (removing
and regenerating the spent carbon). These
costs  totalled $500,000 for 4 yr of opera-
tions (February 1986 through June 1990).
The present worth was calculated based
on  4% inflation rate, compounded  annu-
ally, and  15% design and construction
costs  for the capital costs. Therefore,  the
total cost to apply the SVE technology to
remediate Site G in 1990 dollars would be
$1,121,000. The estimated volume of  soil
treated, assuming a 17-ft radius of influ-
ence for each  vent, is 91,000 yd3. Treat-
ment  costs may be expressed  as dollars
per cubic yard of soil treated to date.  For
Site G, the treatment costs are  $13/yd3 of
soil treated.

Conclusions
  The following conclusions can be  made
from the results of the technical evalua-
tion and the soil sampling and operational
information collected for the sites.

1.  SVE treatment at both Site D and Site
    G  effected  significant treatment.
    Comparison of pretreatment and post-
     treatment data shows that TCE and
     TCA concentrations have decreased
     by several orders of magnitude  at
     both  sites. The  residual  con-
     centrations of  TCE   and TCA,
     however, varied  at each site due to
     varying soil conditions.
2.   At Site D,  which  consisted of a
     uniform sand, most of the soils have
     nondetectable  TCE  and  TCA
     concentrations (16 of 21 samples),
     with  a highest  detected  con-
     centration of 0.029 mg/kg TCE.
     Before  treatment, the highest
     concentration of TCE was 7,000 mg/
     kg.  Similar  results  were noted for
     TCA,  where the  highest post-
     treatment con-centration was 0.0008
     mg/kg (an estimated value), and the
     highest pretreatment concentration
     was 1,000 mg/kg.
3.   At Site G, which consisted of a more
     variable strata including  sands,
     clays,  and  waste  material, the
     residual concentrations of TCE and
     TCA were more variable. TCE and
     TCA concentrations were below the
     detection limit in 15 of 21 samples,
     with maximum  concentrations  of
     0.420   mg/kg and  0.200  mg/kg,
     respectively. Before treatment, the
     highest detected concentration  of
  .   TCE  was  400  mg/kg, and the
     highest concentration of TCA  was
     100 mg/kg. All of the samples
     showing maximum concentrations
  1   (both   pretreatment  and post-
     treatment) were taken from waste
     material. The higher residual TCE
     and TCA concentrations found  in
     the waste material and clays at Site
     G may indicate the following:

        The less permeable materials
        or  materials with  a  higher
        organic  content tend to absorb
        or  retain the contaminants to a
        greater   degree than  do the
        sands.
        The air flow through the sands
        is   greater; therefore,  the
        contaminants are removed from
        them more readily.

        Site G  is still operating  and
        residual  levels may decrease
        further with time.

4.   The mass removal rate for VOCs
     varies  significantly over time. Initially,
     the mass removal rate is very high,
     but within days it decreases rapidly
     and shortly,  within  a few months,
     reaches levels that are one-tenth

-------
                    I
                    o
                    i
                            1000 •+


                            eoo -

                            goo 4 y=895.7-305.64*log(x)
                                   (logarithmic function)
                  y=(1000+3x)/(1+0.09x)
                   (hyperbolic function)
                                                                                       NOTE: Y axis truncated to pro-
                                                                                           vide better resolution.
                                                                 Days of Operation
Figure 3. Mass removal rate versus time. Site D, Twin Cities Army Ammunition Plant.
                    I
                    cr

                            2SOO -f-
                            2000 -
                            1500 -
                            1000
                            GOO - -
y=(1500-1.1x)/(1+.08x)
 (hyperbolic function)
                  y=2357.4-922.53*log(x)
                   (logarithmic function)
                                                                                       NOTE: Y axis truncated to pro-
                                                                                           vide better resolution.
                                                                         EOO

                                                                Days of Operation
                                                                                                                  1000
Figure 4. Mass removal rate versus time, Site G, Twin Cities Army Ammunition Plant.

-------
5.
those of the initial  rates. This has
important implications for the design
of air emissions treatment  units for    6.
SVE   systems.  An   emissions
treatment  unit  sized for the  initial
mass  removal  rates would  be
completely oversized for the majority
of the systems' operational lifetime,
whereas a unit sized for the later low
removal rates could not handle the
initial removals.
The Site D system  removed a total    7.
of 108,460 Ib of solvents  between
January 1986 and May 1990 at an
estimated present worth total cost of
$573,000, or $17/yd3 soil ($5.28/lb
VOC) treated, for costs incurred as
of May  1990. Air emission controls
 were not required for the Site  D
 system.
 The Site G  system removed a total
 of  98,727 Ib of  solvents  between
 February  1986 and May 1990. The
 Site G soils  have been treated at an
 estimated present worth total cost of
 $1,121,000 or $13/yd3 soil ($11.35/lb
 VOC) treated, for costs incurred as
 of May 1990. Air emission controls
 were implemented at Site G.
 Treatment costs  for other sites will
 depend on the following:
•   site size and area! extent;
    regulatory  requirements  for
  :  approvals, design, permitting and
    operations;
    •   air emission controls;
    •   site  and  chemical  specific
        conditions;
    •   site cleanup criteria.

  Treatment costs for other sites will likely
b&  higher because of stricter  regulatory
requirements,  more  detailed  design  re-
quirements, and more emissions monitor-
ing requirements.  Therefore,  treatment
costs for other sites should  be evaluated
on a site-by-site basis.
  The full  report was submitted  in
fulfillment of Contract No 68-03-3450 by
Roy F. Weston Inc  under the sponsorship
of the U.S.  Environmental  Protection
Agency.

-------
M.H. Corbin, N.A. Metzer, and M.F. Kress are with Roy F. Weston Inc,
  Westchester, PA 19380-1499
Janet Houthoofd is the EPA Project Officer (see below).
The complete report, entitled "Field Investigation of Effectiveness of Soil Vapor
    Extraction Technology," (OrderNo. PB94-205531; Cost: $27.00, subject to
    change) will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
        Risk Reduction Engineering Laboratory
        U.S. Environmental Protection Agency
        Cincinnati, OH 45268
  United States
  Environmental Protection Agency
  Center for Environmental Research Information
  Cincinnati, OH 45268

  Official Business
  Penalty for Private Use
  $300
     BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
  EPA/600/SR-94/142

-------