United States
                     Environmental Protection
                     Agency
Risk Reduction
Engineering Laboratory
Cincinnati, OH 45268
                     Research and Development
EPA/600/SR-94/148    September 1994
^ EPA       Project Summary

                     Alkaline  Noncyanide  Zinc
                     Plating  and  Reuse of
                     Recovered  Chemicals
                     Jacqueline M. Peden
                      A metal finishing process can create
                     environmental  problems because it
                     uses chemicals that are not only toxic
                     but also resistant to degradation or de-
                     composition. A study was undertaken
                     at a zinc  electroplating  operation  to
                     achieve zero discharge of wastewater
                     and total recycle of recovered precipi-
                     tates. The first step in this project was
                     to change an existing zinc cyanide (CN)
                     plating line to one that used an alkaline
                     noncyanide (ANC) zinc bath.  The
                     project then investigated  a closed-loop
                     system to treat plating  rinsewater from
                     the ANC zinc plating line so the plating
                     chemicals  were recovered and the wa-
                     ter purified. The goal was to return both
                     the recovered zinc hydroxide and the
                     clean water to the plating line for con-
                     tinued  use. The system  that was de-
                     signed and installed,  at P&H  Plating
                     Co., a Chicago area operation used pre-
                     cipitation by pH adjustment to remove
                     the zinc from the rinsewater. The pre-
                     cipitated zinc hydroxide was collected
                     on filters, dewatered using a filter press,
                     and stored for reuse in the plating line
                     as needed. Once filtered, the water was
                     recirculated to  the rinsing portion  of
                     the plating line. The recovery/recycle
                     system successfully purified the
                     rinsewater and facilitated the recycling
                     of the cleaned water and the precipi-
                     tated zinc  hydroxide. Eliminating cya-
                     nide from  the plating  process meant
                     the line workers were dealing with a
                     less  toxic  plating bath, made compli-
                     ance with  regulations  easier, and re-
duced treatment and disposal costs for
the company. The recycling of the re-
covered water and the zinc hydroxide
further reduced the costs for treatment
and disposal. The replacement of this
single CN  line with an ANC line re-
sulted in  an  annual savings to  P&H
Plating of $14,000 from the elimination
of the need to pretreat the plating line
rinsewater to oxidize cyanide. The ad-
dition of the  recovery/recycle system
increased the company's  savings to
$62,000/yr. The reuse  of 30% of the
recovered zinc hydroxide and 70% of
the treated rinsewater reduced annual
water usage and wastewater discharge
by 841,911 gal and reduced the amount
of sludge disposed annually by 14 yd3.
The payback  period for the  recovery/
recycle system is slightly less than 18
mo. Installation and use of this system
for other ANC plating operations would
result in reductions in wastes and in-
creased economic benefits similar to
those experienced by P&H Plating Co.
  This Project Summary was developed
by EPA's  Risk Reduction Engineering
Laboratory, Cincinnati, OH, to announce
key findings  of the WRITE program
demonstration that is fully documented
in a separate report of the same title
(see  Project Report ordering informa-
tion at back).

Introduction
  This cooperative effort between the U.S.
Environmental Protection Agency (EPA)
and the Illinois Hazardous Waste Research

-------
and Information Center (HWRIC) was un-
dertaken to evaluate the feasibility of us-
ing an innovative, closed-loop rinsewater
treatment system  to precipitate plating
chemicals for recovery and reuse and to
produce purified water for  recirculation to
the rinsing tanks and sprayers. The goal
of this study was to achieve  zero  dis-
charge of the wastewater and  total re-
cycle  of the recovered precipitate thereby
reducing  the  amount and  toxicity  of the
waste from an  electroplating  shop's zinc
plating operation. The CN plating line was
converted to one that used an ANC plat-
ing bath.  A  recovery/recycle  (R/R)  unit
was then  designed,  installed, and  tested
to determine how completely the goals of
the project were being met. The effective-
ness  of the  R/R system in reducing the
process wastes was evaluated by: quanti-
fying the effectiveness of the removal of
the zinc through precipitation by pH ad-
justment  (the basis of the  recovery sys-
tem);   determining  the quality  of  the
precipitate and the treated water that were
recovered; comparing the  plating quality
of the CN-based operation to that of the
ANC-based processes and analyzing the
costs  associated with the  change  in the
process and  the installation  of the  R/R
system. The  R/R unit was designed, in-
stalled, and tested  by engineers from the
Center  for  Neighborhood  Technology
(CNT). Their  initial analysis that the sys-
tem would be effective in reducing wastes
and facilitating recycling of the bath com-
ponents was  confirmed by HWRIC engi-
neers who again tested the system after
more  than 1  yr of operation. A slightly
modified unit that accommodates two plat-
ing lines, rather than one, is still in opera-
tion at P&H Plating  Co. after  more than
Syr.

Industry Partner
   P&H Plating Co.  is one of 174 plating
operations in  Cook County, Illinois. It is a
large job shop that operates 16 hr/day,  6
days/wk.  It uses barrels, hoists, and racks
to move parts  through  the plating pro-
cess.  Although  this  project concentrated
on zinc plating, the  shop is  capable of and
does plate nickel, brass, copper, and cad-
mium on  a variety of surfaces. The facility
contains  a waste treatment area that re-
ceives effluent at an average rate of 150
gal/min.  For  this  project,  the  company
made two changes  to one  of its  barrel
plating lines. It replaced a CN plating line
with  one that used an ANC  bath and  in-
stalled the CNT-designed R/R system. An
evaluation of the effectiveness of these
changes continued over 2 yr.

Problem Statement
  Achieving  waste reduction in the elec-
troplating  industry is  important because
the wastes can create many environmen-
tal problems. The chemicals  used are not
only  toxic but  also resistant to degrada-
tion or decomposition. Many opportunities
are open to  electroplaters to reduce their
wastes.  Simple housekeeping techniques
such as  slowing down the  movement of
parts through  the operation to increase
drain time can  significantly reduce  the
amount  of plating bath chemicals  carried
over into  the wastewater. Other options
include recovering bath chemicals, clean-
ing and  recycling rinsewater,  using less
toxic chemicals when possible, and using
technologies such as  ion  exchange  to
clean and maintain plating baths.  Adopt-
ing these types  of process modifications
are generally not only environmentally ad-
vantageous  but  frequently result in eco-
nomic benefits.
  Federal and state regulations set limits
on the amounts of toxic plating line con-
stituents that can be discharged. The costs
to comply with these  regulations can  be
considerable. Cyanide is a particularly dif-
ficult contaminant to treat; it  readily com-
bines with metals, particularly iron, to form
stable complexes that  may not be  de-
stroyed by standard treatment methods. It
poses substantial health and  environmen-
tal risks if not handled correctly or treated
completely.  Enforcement efforts on both
the state and federal  levels are well coor-
dinated, and prosecution of violators has
increased. Electroplaters must develop an
integrated approach to waste management
that  meets compliance standards and  in-
cludes waste reduction as a  vital compo-
nent.

The CNT Recovery/Recycle
(R/R) System
  The relatively simple principles involved
in the design of the CNT R/R system are
similar to those for a standard wastewater
flocculation treatment to remove  metals
before  disposal  of  water  and  sludge
wastes.  Ideally,  100% of the zinc  in the
CNT R/R system's  rinsewater would  be
recovered and  returned to the plating bath.
Additionally,  all rinsewater would  be re-
cycled. The projected result would be sub-
stantial savings for the company in plating
chemicals and water from this rinsewater
purification that both recovers and reuses
as well as treats.
  In the plating process at P&H, there is
the usual  parts pretreatment or cleaning,
followed by the plating process, a spray
rinse, and finally, submersion into  two
counterflow rinse  tanks.  Although clean-
ing requirements for ANC plating are gen-
erally more stringent than those for CN
plating,  no change  was  required to the
pretreatment  portion  of the line at P&H.
The company had already installed a very
stringent cleaning component to their plat-
ing lines to  ensure good parts cleaning
and, presumably,  better plate quality.  The
CNT R/R  system was  plumbed from the
spray rinse tank  into which the counter
flow tanks ultimately  overflowed.   The
rinsewater flows into a tank where the pH
is  measured  and automatically adjusted
to  a pH  between 10 and 10.5.
  This pH monitoring and control tank is a
continuous flow stirred  reactor (CFSR). It
is  designed to stimulate  precipitation by
sparging with compressed air entering from
the bottom of the  tank.  The  flow  rate
through  the  CFSR is set at  10 gal/min.
The precipitate/water slurry next flows into
a flat-bottomed clarifying tank.  To facili-
tate the settling process, the tank is baffled.
A recirculating pump  is used to pull water
from the clarifying tank through the dual
filtering system to remove suspended hy-
droxide.  The filtered water then either flows
to a storage tank for reuse or to the waste
treatment  area for disposal.  The precipi-
tate that has  settled in  the clarifying tank
is  removed and  combined with that  col-
lected on  the filters.  This composite hy-
droxide is  placed in a filter press to remove
as  much  water  as  possible. The  water
that is removed is returned to the precipi-
tation reactor and the dewatered hydrox-
ide is analyzed and stored for future  use
or disposed if not needed. Figure 1 shows
the system components and the path of
the water and  the  solids as they  flow
through  the system.

R/R System Performance
  Although the system had  problems, it
proved to be a highly  efficient  and eco-
nomically  advantageous  addition  to  the
plating operation.  The  quality of the  zinc
hydroxide precipitate and the purified  wa-
ter  were sufficient for  recycling. Careful

-------
      Product
Treatment
   or
 disposal
                        Rinse          Four-part plating process

                           Can be returned to plating bath
                           meter   Counter flow rinses
           Precipitate collection
                                           Filter press
Figure 1. P&H Plating alkaline noncyanide plating line with CNT designed recovery/recycle system.
and regular analysis of the essential bath
chemicals is recommended to ensure con-
taminants are not introduced through these
recycling efforts.
  The CNT R/R system has been in con-
tinuous operation for  over 3 yr. Mainte-
nance consists of proper  care of the
mechanical parts and periodic replacement
and cleaning of the filters. Zinc hydroxide
is removed from  the  rinsewater with  an
efficiency averaging 84%. The amount of
precipitate  recycled to the bath  depends
largely on  the  number of jobs  requiring
use of that line. The  company estimates
that it recycles  30% of the zinc hydroxide
it recovers. The quality of the purified wa-
ter is generally  acceptable for recycling or
for discharge. Approximately 70% is used
in the rinsing operation or to replenish the
plating bath. The system works well pro-
viding both environmental and economic
benefits to P&H.

Plating Quality Comparison
  Although the  reasons for  plating  are
sometimes purely ornamental, more  fre-
quently  the  plate is for protection. Fin-
ishes may be bright or dull, and it may not
always be possible to achieve the desired
luster with the ANC  system. Advances in
the last decade  have, however, provided
less toxic bath alternatives that  produce
parts more like  the  bright,  shiny objects
that result from  a  CN-based operation.
Ultimately, whether  the  plate is  satisfac-
tory or not is  up to the customer, but two
commonly used standard tests can be per-
formed to evaluate quality—thickness and
corrosion resistance. When  parts plated
on both the CN and ANC lines were  com-
pared for these standards, both processes
produced parts with the desired thickness
and acceptable corrosion protection.

Toxicity Comparison
   Had there  been no economic benefit
from the change to ANC plating, the re-
duction in  health  and environmental risk
resulting from  the  elimination of cyanide
from the process  would have been  suffi-
cient to warrant its adoption. CN plating
requires extensive treatment before dis-
posal and uses chemicals  hazardous to
human health. Chemical substitution to

-------
achieve source reduction, as was done
for this project, not only reduced process
costs but also the company's liability be-
cause of the reduced toxicity of the chemi-
cals  being handled and disposed.
  The exposure of shop workers to toxic
chemicals  presents the  most  serious
health and  safety problems for the elec-
troplating industry. Although no occupa-
tional illness has been documented for
electroplating operators, they are routinely
exposed to hazardous substances known
to cause serious health  problems.  The
use of cyanide, generally considered the
most potentially dangerous of the electro-
plating chemicals,  is carefully monitored
and employees are trained to use it prop-
erly.  Combining employee education with
substitution  of less  toxic  chemicals  may
provide the least costly and most produc-
tive  control  of workplace hazards.   Re-
placing  cyanide  plating  solutions  with
          noncyanide  baths  is strongly  recom-
          mended.

          Economic Comparison
            When  the  R/R system is installed on
          the ANC line, the  economic benefits be-
          come significant. An  economic compari-
          son for the change to ANC and then for
          that change plus the  addition of the R/R
          unit is provided in Table 1. An annual cost
          savings of $14,000 is achieved by switch-
          ing from  a CN to an ANC process with a
          savings of $62,000 when the R/R system
          is  also  added  to  the line; this savings
          takes into account the annual cost of op-
          eration  of the R/R system  which  is
          $10,900.
            Making the switch from CN to ANC re-
          quires  disposal of the existing  1,800 gal
          CN bath at  a cost  of $20/gal  for a total
          cost of $36,000. This must be calculated
          as part of the capital investment  for this
                project. Adding the R/R system increases
                the capital investment by $51,822  for a
                total of $87,822. These capital investments
                and the operational  expenses  listed  in
                Table 1 were entered into a spreadsheet
                program that calculates a number of eco-
                nomic  indices. The  calculations  were
                based on  1992 costs.  They use an infla-
                tion rate of 4%, a discount rate of 7.7%, a
                depreciation schedule of 7 yr, and a project
                life of 10 yr. It was assumed for all calcu-
                lations that the line operates 8 hr/day, 5
                days/wk for 50 wk/yr. Table 2 contains the
                results  of the  spreadsheet calculations.
                This analysis shows the  recycling  option
                provides the greater economic benefit, the
                shorter payback  period,  and  the  larger
                return on investment.

                Discussion
                  As a normal part of a plating line, a
                rectifier is used to convert alternating cur-
Table 1.
          Comparison of Annual Operational Costs for CN Process, ANC Process without R/R Unit, and ANC Process with R/R Unit at P&H Plating
          Co.
Process Operation
        CN Costs ($)
ANC Costs ($)
ANC + R/R* Costs ($)
Bath makeup
Bath maintenance

Water usage
1. Use @ $7.56/7480 gal
2. Sewering @ $5.59/7480 gal

Wastewater treatment
1. Cyanide oxidation
2. Metal precipitation
3. Labor @ $15/hr

Sludge  disposal @ $209/yd3

Total
            1771
          22325
            1213
            897
           14000
           69000
            7500

            2600

          119306
    1860
   21225
    1213
     897
       0
   69000
    7500

    2600

  104295
       1860
      19425
        364
        269
          0
      20700
       2250

       1820

      46688
* Assumes 70% water and 30% zinc hydroxide recycled
Table 2.   Comparison of Economic Indices for the Alkaline Noncyanide Plating Process with
          and without the Recovery/Recycle System
      Index
                                 ANC
                                                     Option
                                                                     ANC + R/R
Capital Investment
Payback Period
Net Present Value
Implied Rate of Return
$36,000
    3yr
$57,500
 27.0%
  $87,822
    1.5 yr
 $281,122
   71.9%

-------
rent to the direct current needed for the
plating process.  Some type  of cooling  is
needed to prevent the rectifier parts from
overheating  and  thus  damaging or de-
stroying the entire  unit. The rectifier  on
the test plating  line is  cooled  by water
although  air-cooled models  are  used  on
other zinc plating lines at P&H. Tap water
used in this  noncontact cooling system is
not discarded  but is rather added to the
counter flow rinsewater tanks on  the plat-
ing line. Because of this continuous  addi-
tion of fresh water to the plating line, a
holding tank to  collect the  R/R treated
water was installed. Water in  this  tank can
be used  in the rinsing operation and  as
makeup water for replenishing the plating
bath. The tank is designed with  an  over-
flow valve that opens and sends excess
water to P&H's wastewater treatment area
for further treatment before discharge. Al-
though this  means that the objective  of
zero discharge has not been  met and that
this precipitation  process is partially  serv-
ing as  a pretreatment step, the company
estimates  that the amount of water from
this line that needs treatment has  been
reduced by  more than  60%.  Additionally,
the cost of the precipitation  pretreatment
is  less  than would be the cost of  pretreat-
ing the cyanide  containing  rinsewaters.
The compliance  criteria that need to  be
met by the final treatment are only those
for zinc, since there is  no longer cyanide
in this rinsewater. The maximum discharge
levels  for  metals are generally  easier  to
achieve than are those  for cyanide. This
results in  reduced  treatment costs and
fewer compliance problems.
  The  recovery efficiency for zinc hydrox-
ide from the CNT system averages  84%;
however, because of the variability in the
numbers and types of plating jobs and the
general fluctuations in  business (all  of
which  play a role in the amount of zinc
hydroxide  needed for the line), the  com-
pany does not recycle all of the precipi-
tate that  is  recovered.  Additionally, the
recovered zinc hydroxide is  not  a totally
suitable substitute for the zinc ingots tra-
ditionally  used to add zinc to the plating
bath. All  of the   precipitate  produced  is
passed through   the filter press, which
greatly  reduces its  volume. A portion,
which  varies  depending  on production
needs,  but generally averaging 30%,  is
returned to the plating bath. The remain-
ing 70% is stored  for later use  or dis-
posed  as  a  hazardous waste. While it
would be possible to petition to  delist this
waste, the amount being produced is less
than 5% of the metal waste that the  com-
pany  produces and must routinely dis-
pose. Since much of the other metal waste
was from  cyanide-based lines and  prob-
ably contained residual amounts of cya-
nide, even after treatment,  it was disposed
as a hazardous waste. Currently, it is  more
economically advantageous to simply add
the zinc hydroxide to that  waste and dis-
pose of it as hazardous rather than sepa-
rating  it,  storing  it, and applying  for
delisting.
  The company has recently converted
all of its plating lines from CN-based to
ANC-based. This change will eliminate the
need for  cyanide   destruction  in the
company's treatment operations, will  elimi-
nate one  potential  compliance  problem,
will eliminate the potential health risk as-
sociated with cyanide exposure, and will
ultimately save the company money. The
change was completed more quickly than
originally anticipated. Now that  it is  com-
plete, it may become more economically
inviting to pursue the delisting process for
the zinc hydroxide that isn't being recycled.
Also, the elimination of the cyanide  lines
will allow use  of the  precipitated zinc hy-
droxide to replenish other zinc  plating
baths, which  is an option  currently under
consideration at P&H.

Conclusions And
Recommendations
  The CNT-designed R/R  system proved
quite  successful  in   meeting  the  project
objectives. By converting from a CN-based
to an ANC-based plating  bath,  the  com-
pany eliminated  one step  from  the  treat-
ment cycle, i.e., the destruction of cyanide.
The removal  of cyanide from the system
also reduced  the risk to  employees by
eliminating a highly  toxic substance from
their work environment. The purification of
the wastewater proved so  successful that
nearly all of the recovered water could be
recycled  as well as much of the precipi-
tated zinc hydroxide. As a result of install-
ing this  recovery unit, annual operational
costs  (including treatment  and disposal
costs, raw material purchases, and water
usage  fees) were reduced  by $62,000.
The costs to  design  and  install  a  R/R
system like the one  in use at P&H Plating
is  recovered during the first  year and a
half of operations. Additionally, recycling
of the recovered materials reduced water
usage and discharge by 841,911 gal and
reduced the sludge disposed by 14 yd3/yr.
These savings  apply to a single line, but
the test unit could easily  accommodate a
second line's waste, which  would double
these waste reduction  figures. This sys-
tem is  simple  and functions well.  It is  in
use at  P&H Plating  today, and its use  in
similar electroplating operations would re-
sult in  economic  benefits comparable to
those described in this  project summary.
   Finally,  there are still  many pollution
prevention opportunities  for the electro-
plating industry left to explore. Documented
case studies of process modifications and
technology evaluations  that lead to source
reduction  are  available, but more are
needed. Distribution of this  information to
the appropriate audience can be achieved
with the assistance of trade groups for the
electroplating industry. Continued associa-
tion with these industry  organizations  is
essential to identify  new pollution preven-
tion options and to promote  adoption of
those that have proven successful. This
continued interaction can only benefit all
parties involved. Economic benefits could
be substantial to companies willing to work
toward source reduction. The environmen-
tal  benefits that could result from the re-
duction  in toxicity  and  volume  of this
industry's  wastes would be significant and
would be  reason enough to  continue to
support research that will bring about those
reductions.
   The full report was submitted in partial
fulfillment of   Cooperative  Agreement
#CR815829 by the Hazardous Waste Re-
search and Information Center under the
sponsorship of the U.S. Environmental Pro-
tection Agency.

-------
Jacqueline M. Peden is with Hazardous Waste Research and Information
  Center, Champaign, IL, 61820.
Paul M. Randall is the EPA Project Officer (see  below).
The complete report, entitled "Alkaline Noncyanide Zinc Plating and Reuse of
    Recovered Chemicals," (Order No. PB94-205549; Cost: $19.50, subject to
    change) will be available only from:
        National Technical Information Service
        5285 Port Royal Road
        Springfield, VA 22161
        Telephone: 703-487-4650
The EPA Project Officer can be contacted at:
        Risk Reduction Engineering Laboratory
        U.S. Environmental Protection Agency
        Cincinnati, OH 45268
   United States
   Environmental Protection Agency
   Center for Environmental Research Information
   Cincinnati, OH 45268

   Official Business
   Penalty for Private Use
   $300
      BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
   EPA/600/SR-94/148

-------