United States
                 Environmental Protection
                 Agency
National Risk Management
Research Laboratory
Cincinnati, OH 45268
                  Research and Development
EPA/600/SR-97/063    July 1997
&EPA     Project Summary

                 Evaluation of the  Implementation of
                 Operations and Maintenance
                 Programs in  New Jersey  Schools
                 John R. Kominsky, Ronald W. Freyberg Donald R. Gerber, Gary J. Centifonti
                 Abstract
                   The Asbestos Hazard Emergency Re-
                 sponse  Act  (AHERA)  required all
                 schools to develop and implement an
                 asbestos management plan (AMP). The
                 key component of the AMP is the op-
                 erations and maintenance (O&M) pro-
                 gram. A study was conducted to evalu-
                 ate the implementation of O&M pro-
                 grams at ten  sites representing eight
                 New Jersey schools. The evaluation in-
                 cluded aspects required by AHERA as
                 well as those recommended in the En-
                 vironmental Protection Agency's (EPA)
                 guidance. Each school's O&M program
                 and compliance with their program dur-
                 ing past O&M activities were docu-
                 mented. In addition, ten ongoing O&M
                 activities were documented  to deter-
                 mine the impact of the activities on
                 airborne asbestos levels and to deter-
                 mine compliance with the O&M pro-
                 gram during these activities. Overall,
                 schools were not implementing all the
                 elements of the O&M program. Schools
                 performed more O&M  program ele-
                 ments required by AHERA than those
                 recommended  in EPA guidance. The
                 percentage of performance responses
                 given by the  schools indicating that
                 the elements of the O&M programs were
                 performed (52%) was higher than those
                 provided  by the worker or contractor
                 performing the activity (35% and 22%
                 respectively). Increases in area asbes-
                 tos levels (by transmission electron
                 microscopy [TEM]) were observed dur-
                 ing five of the ten O&M activities evalu-
                 ated, however, none of  the total fiber
                 levels (by phase contrast microscopy
                 [PCM]) exceeded the  Occupational
Safety and Health Administration
(OSHA)  Permissible Exposure Limit
(PEL). This study underscores the im-
portance of a thorough O&M program
and the  effective communication and
implementation of all program ele-
ments.
  This Project Summary was developed
by the National Risk Management Re-
search Laboratory's Sustainable Tech-
nologies Division, Cincinnati, OH, to
announce key findings of the research
project that is fully documented in a
separate report of the same  title (see
Project Report ordering infomration at
back).

Introduction
  The concern for asbestos-containing ma-
terials (ACM) in buildings started in the late
1970s in the U.S. In 1978 the EPA issued
a two-volume guidance document to schools
for identification and evaluation of in-place
asbestos. Subsequently, three  additional
guidance  documents were issued by the
EPA in 1983,1985, and 1990.
  Although removal was encouraged over
alternative approaches of asbestos man-
agement  in the past, in-place  manage-
ment and O&M programs are currently
viewed by the EPA as the most appropri-
ate overall strategy for management of
asbestos  in buildings. In-place  manage-
ment involves the  use of building O&M
work practices and control measures that
minimize  the release of airborne  fibers
from  ACM,  thereby reducing exposures
and associated risks to workers and other
building occupants.
  Operations and maintenance programs
must be prepared and implemented when-
                                                                 Printedon Recycled Paper

-------
 evef friable ACM is present or assumed
 to be present in school buildings. An O&M
 program is an administrative framework
 that prescribes specific work practices and
 training to  maintain friable ACM in good
 condition, ensure cleanup of asbestos fi-
 bers previously released, and prevent fu-
 ture release by minimizing and controlling
 friable ACM  disturbance during installa-
 tion, repair, maintenance, and  cleaning
 activities. A well-developed O&M program
 Is ineffective unless it is implemented prop-
 erly. The O&M program's success is con-
 tingent upon the  commitment of all per-
 sonnel involved in developing, conscien-
 tiously implementing, and conducting O&M
 activities.
  Although  these O&M programs have
 been prepared for schools, no represen-
 tative field  studies have been conducted
 to evaluate the implementation and effec-
 tiveness of these programs in controlling
 the release of asbestos fibers into a build-
 ing. The purpose of this  study was  to
 evaluate the implementation of O&M pro-
 grams in selected schools in New Jersey.

 Objectives
  The objectives of this study were to (1)
 document and assess each school's O&M
 program and other related components in
 the AMP; (2) document and assess each
 school's  compliance with their O&M pro-
 gram  during  previously conducted  O&M
 activities; (3) observe and  document the
 conduct of selected O&M activities involv-
 ing ACM or in the vicinity of ACM; and (4)
 determine the impact of selected  O&M
 activities on airborne asbestos levels.

 Site Selection
  An "O&M Activities Survey Form" was
 distributed to 26 candidate schools repre-
 senting  14 different school districts that
 planned to  perform O&M activities involv-
 ing ACM or activities in the vicinity  of
 ACM  during the  summer of 1994. This
 form solicited information regarding three
 types of O&M activities: (1) Operations
 (custodial/service); (2) Maintenance (heat-
 ing, ventilation, and air-conditioning, plumb-
 ing, electrical/communications, fire protec-
 tion, and other building systems or com-
 ponents); (3)  and Renovation  (general
 space modifications, ceiling tile  replace-
 ment, carpet removal, and roofing repair).
  Eight schools, representing ten distinct
 O&M activities, were selected based on
the type of planned activity and the sched-
 ule for conducting the planned activity.
The results obtained from  the  different
 schools studied were used to document
the implementation of the O&M programs
 at these schools and to identify common
 factors that may influence airborne asbes-
tos levels during O&M activities on or near
ACM.

Evaluation of O&M Programs
  A "Site Evaluation/Assessment Docu-
mentation Form" was used to standardize
the evaluation of each school's O&M Pro-
gram. To prevent any ambiguity regarding
the questions or  recording of the re-
sponses, the form was administered  by
an  Environmental  Health Services-New
Jersey  Department of  Health (EHS-
NJDOH) representative  who was  thor-
oughly instructed  on the basis of  each
question, as well as its application to the
various parts of the evaluation (i.e.,  Parts
1, 2, and 3  as described  below). To en-
sure data consistency the same persons
completed the Site Evaluation/Assessment
Documentation Form.
  Each school's O&M program evaluation
included three primary parts. Part  1  in-
volved a review of each school's  O&M
program and other related components in
the AMP on  file with the NJDOH to deter-
mine  the  overall  comprehensiveness of
the O&M program. Part 2 involved an on-
site interview with the school's AHERA
Designated Person to  assess  each
school's compliance with their O&M pro-
gram  during previously conducted  O&M
activities. Part 3 involved interviewing the
school's AHERA Designated Person and
observing and  interviewing the worker
(school employee or contractor) perform-
ing an actual O&M activity.
  Part 1 - Each school's AMP, which was
on file with the EHS-NJDOH, was evalu-
ated by an EPA-accredited Inspector and
Management Planner prior to initiating the
planned activity.  The Inspector/Manage-
ment Planner completed the Site Assess-
ment/Documentation Form during the re-
view of the school's O&M program. The
evaluation included the program elements
required by AHERA as well as those ele-
ments recommended by EPA  in issued
guidance.  Therefore, the evaluation was
based on three categories of program ele-
ments: those program elements required
by AHERA; those program elements rec-
ommended in EPA guidance documents;
and all of the program elements (i.e., those
required by  AHERA and those recom-
mended in EPA-issued guidance). A "Site
Evaluation/Assessment  Documentation
Form" was used to standardize the evalu-
ation  of the respective O&M programs.
Each school's O&M Program was evalu-
ated regarding the following elements:
  • Comprehensiveness: The program
    should be developed by a qualified
    Asbestos Management  Planner and
    implemented by a qualified Asbestos
    Program Manager/Designated Person
    following a comprehensive building
    inspection to identify and assess the
    condition of all ACM in the building.
    The written O&M Program should be
    site-specific  and take  into account
    function and building design. The pro-
    gram  should address specific activi-
    ties and procedures related to use,
    cleaning, maintenance, repairs, equip-
    ment  service, and fiber release epi-
    sodes.
  • Administration/Awareness:  The writ-
    ten AMP should  be available  at the
    school and updated to keep it current
    with ongoing O&M, periodic surveil-
    lance, inspection, reinspection, and
    response  action  activities.  Addition-
    ally, maintenance and custodial per-
    sonnel must be made aware and have
    reviewed the AMP and O&M Program
    prior to conducting activities.
  • Notification:  AHERA requires that
    workers (school employees and con-
    tract workers),  tenants,  and building
    occupants be notified where ACM is
    located, and how and why to avoid
    disturbing the ACM. All persons af-
    fected should be properly informed.
  • Surveillance: AHERA requires regu-
    lar 6-month ACM surveillance and 3-
    year reinspections  to note, assess,
    and document any changes  in the
    condition of the ACM.
  • Controls: The program should include
    a work control/permit system to con-
    trol activities that  might disturb ACM.
  • Work  Practices: The program should
    describe O&M work practices to avoid
    or minimize fiber release during ac-
    tivities affecting ACM.
  • Recordkeeping: AHERA  requires spe-
    cific documentation of O&M activities.
  • Worker  Protection:  AHERA requires
    medical and respiratory protection pro-
    grams, as applicable.
  • Training:  AHERA  requires  proper
    training of custodial  and  maintenance
    staff who may deal  with activities in-
    volving ACM.
  Part 2 -  Information  regarding  previ-
ously  conducted  O&M  activities at the
school was obtained by interviewing each
school's designated person using the "Site
Evaluation/Assessment  Documentation
Form." This information included the type
and location  of the O&M activity, the date
of the activity, whether  key elements of
the O&M program were followed, etc. This
information  was used to  assess the
school's perception of  compliance with
their O&M  program during previously con-
ducted O&M activities.

-------
  Part 3 - Selected O&M activities involv-
ing  ACM,  or in the vicinity of ACM, were
observed and documented at each school
by using the Site  Evaluation/Assessment
Documentation  Form. The  school's
AHERA Designated Person was observed
and  interviewed. In addition, the school
employee  or  contract worker performing
the  O&M activity was also interviewed re-
garding use of  the elements (e.g., work
practices and procedures) specified in the
school's O&M program. This information
was used  to determine the extent of ac-
tual compliance with their O&M program
during the activity.

Impact of O&M Activities on
Airborne Asbestos Levels
  The impact of the selected O&M activi-
ties on the exposure of custodial workers,
maintenance workers, and/or building oc-
cupants was evaluated by air monitoring
for  asbestos  structures and total fibers.
Characterization of the ACM or  source of
asbestos structures potentially involved in
the  O&M activity or near the O&M activity
was determined  by collecting bulk samples
of the material(s).

Sampling Methods

Fixed-Station Area Air Samples
  The fixed-station area air samples were
collected on open-face, 25-mm  diameter,
0.45-n.m poresize,  mixed cellulose ester
(MCE)  filters with  a 5-(im poresize MCE
diffusing filter and  cellulose support pad
contained  in a three-piece cassette. The
labeled filter cassettes were positioned on
tripods approximately  5 feet above  the
floor with  the filter face at  a 45°  angle
toward the floor. The filter assembly was
attached to an electric-powered (110 VAC)
1/6-horsepower  vacuum pump  operating
at a flowrate of  approximately 9 liters per
minute (L/min).

Personal Breathing Zone
Samples
  One personal  breathing zone air sample
was collected on  an open-face, 25-mm
diameter, 0.8-p.m poresize MCE filter and
cellulose support pad contained in a three-
piece cassette with a 50-mm. conductive
extension cowl. This sample was collected
in accordance with NIOSH Method 7400
for analysis by PCM for comparison to the
OSHA  PEL. Two additional  personal
breathing zone air samples were collected
on open-faced, 25-mm-diameter, 0.45-ja.m
poresize MCE filters with a 5-jim poresize
MCE diffusing filter and a cellulose sup-
port pad contained in a three-piece cas-
sette. These two samples were collected
for  analysis  by  TEM. The three labeled
filter cassettes were  positioned in  the
breathing zone of the individual perform-
ing the O&M activity. Each filter was at-
tached to approximately 50 feet of Tygon
tubing that was attached to  an electric-
powered  (110 VAC)  1/6-horsepower
vacuum  pump operating at a flowrate of
approximately 9 L/min. Traditional battery-
powered, personal sampling pumps could
not be used because of their limited air-
flow rates (approximately 2 L/min with the
0.45-jim poresize MCE filter with a 5-|im
poresize MCE diffusing filter and a cellu-
lose support pad contained  in a three-
piece cassette).

Analytical Methods

Area Air Samples
  The MCE filters were prepared and ana-
lyzed in accordance with the nonmandatory
TEM method specified in the AHERA Fi-
nal Rule (October 30,1987; 52 CFR 4826).
In addition to the requirements of  the
AHERA  nonmandatory TEM method, the
specific length and width of each structure
were measured and recorded. A sufficient
number of grid openings were analyzed to
ensure a sensitivity (the concentration rep-
resented by the finding of a single struc-
ture) of  no greater than 0.005 asbestos
structures per cubic  centimeter of air
sampled, unless the degree of loading
made this impractical. On heavily loaded
samples, counting stopped after comple-
tion of the grid square in which the 100th
asbestos structure was found.

Personal Breathing Zone
Samples
  The 0.8-jim poresize MCE filters were
analyzed by PCM. These samples were
prepared and analyzed according to the
NIOSH 7400 protocol (Revision 3, June 5,
1989, NIOSH Manual of Analytical Meth-
ods). All fibers > 5 )im in length and with
an  aspect ratio of > 3:1 were counted
using the "A" counting  rules. The analyti-
cal sensitivity was approximately 0.01 fi-
ber per cubic centimeter of air sampled.

Bulk Samples
  The type and percentage of asbestos in
bulk samples was determined  by polar-
ized light  microscopy  (PLM) and X-ray
diffraction  (XRD) in  accordance with the
"Interim  Method for Determination of As-
bestos in  Bulk Samples" (EPA-600/M4-
82-020).

Statistical Methods
  Airborne asbestos levels measured be-
fore and during each O&M activity were
characterized for each  site by the use of
descriptive statistics. The descriptive sta-
tistics included the arithmetic mean, mini-
mum  and maximum concentrations, and
sample size. A one-factor analysis of vari-
ance (ANOVA) was used to examine over-
all differences between baseline concen-
trations, area air concentrations measured
during the O&M activity,  and personal
breathing zone concentrations measured
during the activity. The transformation ln(x
+ 0.002), where In is the natural logarithm
and x is the mean airborne asbestos con-
centration, was applied to each  measure-
ment  before the ANOVA was performed.
The transformation was used to make vari-
ances more equal  and to  provide data
that are better approximated by a normal
distribution. The constant 0.002, a value
chosen to be smaller than the majority of
analytical sensitivities,  was used because
some zero values were present  (the natu-
ral logarithm  of zero is undefined). The
transformation was used only for the
ANOVA analysis; it was not used for any
other  part of the data analysis (e.g., plots
or descriptive  statistics). The data  were
transferred back to the original scale for
reporting purposes. The Tukey multiple
comparison procedure  was used to distin-
guish  pairwise differences between mean
concentrations. All statistical comparisons
were  conducted at  the 0.05 level of sig-
nificance.

Quality Assurance
  During the study, sample chain-of-cus-
tody procedures were  an  integral part of
both the sampling and  analytical activities
and were followed for all  air  and bulk
samples collected. The field custody pro-
cedures documented each  sample from
the time of its collection until its receipt by
the analytical laboratory. Internal labora-
tory records then documented the cus-
tody of the sample through its final dispo-
sition. Specific quality assurance proce-
dures outlined in the  AHERA rule  were
used to ensure the precision of the collec-
tion and analysis of air samples, including
filter lot  blanks,  open and closed field
blanks, and repeated sample analyses.

Results and Discussion

Site  Descriptions
  Eight schools representing seven school
districts were surveyed during this study.
All eight of  these  schools  have partici-
pated in past asbestos-related studies con-
ducted cooperatively by EPA  and  EHS-
NJDOH. A total of ten O&M activities were
evaluated at these eight schools; two ac-
tivities were evaluated at two of the schools
(Sites F and G) and one activity was evalu-
ated at each  of the other six schools. A
summary matrix of each  study site and

-------
 the O&M activity evaluated is presented
 in Table 1.

 Assessment of O&M Programs
   The evaluation of the data for each
 school's O&M program was grouped into
 three categories: AHERA Elements, in-
 cluding those program elements required
 by AHERA; Guidance Elements, including
 those program elements recommended in
 EPA-issued guidance; and All Elements,
 including all of the program elements (i.e.,
 the first  two categories combined). Each
 school's O&M program evaluation was also
 divided into three primary parts: Part  1
 (AMP), which included the information con-
 tained in the school's AHERA AMP filed
 with the EHS-NJDOH; Part 2 (previous
 O&M activities), which included the previ-
 ously conducted O&M activities  informa-
 tion obtained by interviewing each school's
 AHERA  Designated Person; and Part 3
 (observed O&M activities), which included
 the information obtained by  direct obser-
 vation of O&M activities.

 Comparison By Category
  Table 2 summarizes the individual per-
 formance responses for each site by part
 and category. It also presents the overall
 average  percentage of performance  re-
 sponse for all sites by part and category.
 The responses to questions on the Site
 Assessment/Documentation Form are
 termed "performance responses" in this
 report. A "yes" indicates an affirmative re-
 sponse to the respective question, as well
 as  indicates that the particular activity or
 function had been accomplished.
  AHERA Elements - Overall, the perfor-
 mance responses were highest for ele-
 ments required by AHERA. The AMP per-
 formance responses ranged from 69.6%
 to 95.7% with an average of 88.3%. At
 seven of ten sites, the AMP's  indicated
 greater than 90% performance response.
 Only one site's AMP had less than 70%
 performance response. It should be noted
 that for the evaluation  of the information
 required by AHERA in the AMP, it is pos-
 sible to have less than 100% performance
 for the purpose of this study. Some O&M
 program  elements could not be verified
 because they would not be performed un-
 til a future date, i.e., a date beyond the
 time when the AMP was reviewed by the
 EHS-NJDOH inspector.  In previous O&M
 activities, performance responses in eight
 of ten sites were less than those noted in
 the AMP. In the observed O&M activities,
 performance responses in all sites were
 less than those documented in the AMP
 and averaged 58.9%.
  Guidance Elements - Overall, in all three
 parts, the performance  responses noted
 in this category were the lowest. The AMP
 performance responses ranged from 7.1%
 to 71.4% with  an average  of 41.4%. At
 eight of ten sites, the AMP indicated less
 than 70% performance  response. The
 lower responses could  be attributed to
 some of  the guidance information (par-
 ticularly the "Green Book") not being avail-
 able when the AMP's were prepared in
 1987 to 1989. The performance responses
 averaged only slightly higher in  previous
 O&M activities (54.1%) and during the ob-
served O&M activities (44.0%).
  Although all of the guidance was avail-
able for approximately five years prior to
this evaluation, the most recent EPA guid-
ance (the "Green Book") is not geared
Table 1. Summary of O&M Activities Evaluated by SITE
Site
A
B
C
0
E
F,
FS
G,
G*
H
O&M Category
Operations'
Maintenance"
Renovation
Maintenance'
Renovation
Maintenance"
Maintenance
Renovation'
Maintenance
Maintenance
Description of O&M Activity
Wet-stripping of resilient floor tile.
HEPA-vacuuming of boiler interior.
Spacemodification (demolition of plasterwalls/ceilings; pipes).
HEPA-vacuuming of HVAC unit in classrooms.
Removal of carpet over resilient floor tile.
HEPA-vacuuming of interior air handling unit.
Wiring pulled above suspended ceiling for smoke detectors.
Removal/replacement of suspended ceiling panels.
Romex cable pulled above suspended ceiling.
Holes drilled in acoustical plaster to install smoke detectors.
•Denotes that the work was performed by an employee of the school.
 specifically toward schools, but for build-
 ings  in general. Therefore, the schools
 may not be aware of the guidance or may
 choose not to  implement  the  guidance
 recommendations since it's not a regula-
 tory requirement. A comparison of the data
 contained in the AMP, with  the perfor-
 mance responses from previous O&M ac-
 tivities and a comparison with the observed
 O&M activities and a comparison suggest
 a trend in decreasing percentage of per-
 formance  responses. The  AMP's  docu-
 mented an average performance response
 of 70.6%, whereas the school stated that
 it performed 57.6% of the O&M elements
 during previous O&M activities, and per-
 formed 49.2% of the elements during the
 observed O&M  activity. In  the  observed
 O&M activities, performance responses in
 eight of ten sites were less  than  those
 noted in the AMP.

 Comparisons by Part
  Table 2 summarizes the individual per-
 formance responses for each site by part
 and category. It also presents the aver-
 age percentage of performance  response
 for all sites by part and category.
  Part 1 - At all sites, the individual per-
 centage of AHERA  element performance
 responses was  higher than those recom-
 mended in EPA Guidance elements. The
 number of  sites with performance  re-
 sponses less than 70% was only one of
 ten for AHERA elements and eight of ten
 for  Guidance elements. The average per-
 formance response  for AHERA  elements
 (88.3%) was 53.1% higher than  the aver-
 age performance response for Guidance
 elements (41.4%).
  Part 2 - The  average performance re-
 sponse for Guidance elements  (54.1%)
 was 9.8% lower than the average perfor-
 mance response for AHERA elements
 (60.0%). All  three categories  had six of
 ten sites with performance responses less
 than 70%.
  Part 3 - The  average performance re-
 sponse for  Guidance elements  (44.0%)
 was 25.3% lower than the average perfor-
 mance response for AHERA elements
 (58.9%). Both the AHERA elements and
 Guidance elements categories had seven
 of ten sites with performance responses
 less than 70%.

 Comparisons of School, Worker,
 and Contractor Performance
 Responses
  Further evaluation was made to  com-
pare the performance responses of the
school officials to those of the persons
actually performing  the observed O&M
activity. Both the school Designated Per-
son and the school maintenance worker

-------
Table 2. Percentage of Performance Responses for Program Elements
Study Site
A
B
C
D
E
F,
P2
G,
G2
H
Average
Rec
Parti"
95.7
. 91.3
78.3
91.3
69.6
95.7
95.7
91.3
91.3
82.6
88.3
luired by AHER
Part2b
58.3
50.0
95.8
54.2
95.8
12.5
16.7
75.0
75.0
66.7
60.0
A
Part3c
66.7
22.2
77.8
77.8
66.7
44.4
44.4
55.6
55.6
' 77.8
58.9

Parti
50.0
35.7
50.0
71.4
7.1
14.3
14.3
50.0
50.0
71.4
41.4
EPA Guidance
Part 2
47.1
41.2
100
23.5
" 76.5
23.5
23.5
8.2
88.2
29.4
54.1

PartS
46.7
6.7
80.0
20.0
66.7
13.3
13.3
80.0
73.3
40.0
44.0

Parti
78.4
70.3
67.6
83.8
45.9
64.9
64.9
75.7
75.7
78.4
70.6
Ail Elements"
Part 2
53.7
46.3
97.6
41.5
87.8
12.5
19.5
80.5
80.5
51.2
57.6

PartS
54.2
12.5
83.3
33.3
66.7
25.0
25.0
70.8
66.7
54.2
49.2
"Part 1 involved a review of each school's Asbestos Management Plan.
bPart 2 involved an interview with the school's AHERA Designated Person regarding previous O&M activities.
cPart 3 involved information from the school's AHERA Designated Person and the individual performing the observed O&M activity.
"Includes the O&M program elements required by AHERA and those recommended in EPA-issued guidance.
or the outside contractor performing  the
activity where asked specific questions re-
garding the observed O&M activities. Table
3  summarizes the  responses for these
specific questions for the "All  Elements"
and  "AHERA Elements" categories.  The
performance response for "All  Elements"
indicated by the school  Designated Per-
son was 52.5%, whereas the performance
response indicated by the school mainte-
nance worker was 35%. The outside con-
tractor indicated that 22.5% of the O&M
elements were performed. Approximately
a 33.3% decrease in the performance re-
sponse from the school  Designated Per-
son to the school maintenance worker was
also observed. Similarly, a 57.1 % decrease
in  the performance response from  the
school Designated  Person to the outside
contractor was observed.  This also  re-
flects a 35.7% decrease in performance
response from  the  school  maintenance
worker to the outside contractor. The per-
formance responses for "AHERA Ele-
ments" were very similar as was the trend
of decreasing performance responses from
the school  Designated Person to   the
school maintenance worker and the out-
side contractor.

Comparisons by Program
Elements
  Table 4 presents the  performance  re-
sponses  to  the  individual program ele-
ments for both the AHERA-required and
EPA-recommended elements by Parts 1,
2, and 3. Generally, decreases in perfor-
mance  responses for each element is
noted from the elements documented in
the AMP (Part 1), to previous O&M activi-
ties (Part 2),  and to  what was actually
observed during the O&M activity (Part 3).
Across  all  sites for  each program  ele-
ment, an overall average was calculated.
When the AMP is evaluated according to
the "All Elements" category; surveillance,
recordkeeping, and training had the high-
est percentage of performance responses.
Other program elements scored less, with
all being less  than 80%. Work practices
and work permit system program elements
scored the lowest with 57.5% and 38.9%,
respectively.

Impact of O&M Activities on
Airborne Asbestos Levels

TEM Air Monitoring Results
  Airborne asbestos levels were measured
before and during each O&M activity at
each site. A one-way  ANOVA was used
to compare airborne asbestos levels mea-
sured before each activity to area  and
personal breathing zone levels measured
during the activity at each site. Table 5
summarizes the results of these compari-
sons for each  O&M activity. Some O&M
activities were  performed in the vicinity of
ACM without causing elevated airborne
asbestos levels. Five of ten activities (Sites
A, C, F,, F2, and  H) showed  significant
increases in airborne asbestos levels dur-
ing the associated O&M activity when com-
pared to  baseline  measurements. Addi-
tionally, when O&M activities disturbed
ACM in the vicinity or were conducted on
ACM, airborne  asbestos  levels were el-
evated at or above 0.02 s/cm3 in four of
ten sites (A, C, F,, and H). The 0.02 s/cm3
criterion  was derived  from the AHERA
clearance criterion  of 70 s/mm2 (40 CFR
763). Another study, conducted over a 4
year period, concluded that O&M activi-
ties that disturbed ACM (including thermal
system insulation and plaster,  and resil-
ient  floor  tile)  may have contributed to
elevated airborne asbestos levels at sev-
eral of the sites.
  The airborne asbestos levels measured
during wet-stripping of the resilient floor
tile were three orders of magnitude higher
than the levels measured during the other
O&M activities. These elevated levels dur-
ing wet-stripping of resilient floor tile are
consistent with those levels measured dur-
ing other studies involving the same floor
care maintenance practice.
   Additionally,  a  study previously con-
ducted on the  spray-buffing of resilient
floor tile demonstrated that this common
maintenance procedure increased airborne
asbestos  levels at the majority of the study
sites.

-------
TabloS.  Percentage of Performance Responses for Parts with Individual School Designated Person,
Worker, and Contractor Responses
                                 Percentage of Performance Responses
 Elements
     School
Designated Person
School Worker
Contractor
AH Elements
AHERA Elements
      52.5
      60.0
    35.0
    37.5
  22.5
  25.0
Table 4.  Average Performance Responses for all SITES by Element and Part - All Elements Category

                                                        Parts
     Program Elements
                 1°
         2"
Administration                      72.3
Notification                         76.7
Surveillance                       100
Work Control/Permit System           38.9
Work Practices                     57.5
Recordkeeping                     97.5
Personal Protective Equipment        70.0
Training                           90.0
Totals                             70.6
                                      66.4
                                      30.0
                                      75.0
                                      45.6
                                      44.0
                                      70.0
                                      50.0
                                      65.0
                                      57.6
                              68.0
                              35.0

                              38.9
                              33.3
                              75.0
                              80.0
                              45.0
                              49.2
•Part 1 involved a review of each school's Asbestos Management Plan.
*Part 2 Involved an interview with the school's AHERA Designated Person regarding previous O&M
 activities.
«Part3 involved information from the school's AHERA Designated Person and the individual performing
 the observed O&M activity.
Table 5.  Summary of ANOVA Comparisons


              Site-Activity
                         ANOVA
                         p-value
        Tukey pairwise comparisons111'-0
Site A - Perform wet-stripping of resilient floor tile    0.0001

Site B - Vacuum interior of boilers                0.3627

Site C - Contact space modification               0.0102

Site D - Vacuum air-handling unit                 0.4889

Site F, - Changer filter and vacuum air-handling unit  0.0254

Site Fa - Install smoke detector wing               0.0059

Site G, - Remove/replace ceiling tile               0.5192

Site Gj - Install flexible electrical conduit above      0.5650
       suspended ceiling

Site H- Install fire alarm system                  0.0001
                                     B(0.002) DP(3.29T
                                      DP(0.002) BKX003) DA(0.006)

                                      B(0.003) DA(0.020)

                                      BfO.002^ DAfO.003^ DPKX003T

                                      BfO.003) DAfO.007^ DP(0.042)

                                      DA(0.003^ BfO.003^ DP(0.009)

                                      DAfO.004) DPm.006^ BfO.007^

                                      8(0.004) DAfO.009) DPfO.008^


                                      B(0.003) DAfO.053^ DP(0.120^
•8 m Baseline; DA • Area samples taken during the activity; DP = Personal samples taken during the
 activity
'Parenthetical entries are geometric average airborne asbestos concentrations (s/cm3).
•Average concentrations connected by a line are not significantly different.
  In general, personal breathing zone lev-
els  tended to be slightly higher than area
levels during the activities. This difference,
however, was statistically significant dur-
ing  only one activity. The higher concen-
trations of asbestos measured by the per-
sonal breathing zone  samples than the
concentrations measured by the fixed-sta-
tion area samples at  Site  F2  are most
likely attributable to differences in the prox-
imity  of  the sampling cassettes  to the
source of the asbestos release; i.e., the
O&M activity.

PCM Air Monitoring Results
  None of the personal  breathing zone
levels exceeded the OSHA  PEL of 0.1 f/
cm3,8-hour time weighted  average (TWA).
The 8-hour TWA concentrations were cal-
culated by assuming zero exposure both
before and beyond that which was mea-
sured during the activity.

Conclusions
  The following are the principal conclu-
sions reached during this study:
  1. Overall, schools were not completely
     implementing all the elements of the
     O&M program within  the AMP as
     outlined in AHERA  or  in EPA guid-
     ance documents. The O&M pro-
     grams ranged in overall comprehen-
     siveness from 45.9% to 83.8% with
     an average of 70.6%.
  2. School Designated Persons may not
     be aware of all program elements in
     the AMP. The overall percentage of
     performance responses given by the
     school officials during the observed
     O&M activities was  52.5%. The
     school maintenance worker indicated
     a performance response of only 35%,
     while the outside contractor indicated
     an even lower performance of 22.5%.
     All elements were not  implemented
     and/or communicated by the school's
     designated person.  Additionally, all
     program elements  were  not per-
     formed  by the workers/contractors
     conducting the O&M activity.
  3. Schools implemented more required
     items in accordance with AHERA
     than those additional program ele-
     ments outlined  in   EPA  guidance
     documents.  The percentage of per-
     formance responses was highest in
     the  management  elements of
     AHERA and EPA guidance. The el-
     ements indicating  implementation
     items such as notification to  work-
     ers/contractors, work permit system,
     and work practices for the O&M ac-
     tivities had the least percentage of
     performance responses.

-------
4. O&M activities  were performed in
   the vicinity of ACM without causing
   elevated  airborne asbestos levels.
   When O&M activities disturbed or
   were conducted on ACM, however,
   airborne asbestos levels were sig-
   nificantly  elevated and exceeded
   0.02 asbestos structure/cm3 (School
   Sites A, C, and H).
5. The estimated 8-hour TWA  of total
   fiber concentrations (0.005 f/cm3
   maximum) in the breathing zone of
     the individual performing the  O&M
     activities (as determined by phase
     contrast microscopy) did not exceed
     the OSHA Permissible  Exposure
     Limit of 0.1 f/cm3, 8-hour TWA.
  The full report was submitted in partial
fulfillment of Contract No. 68-D2-0058 by
Environmental Quality Management, Inc.,
under subcontract to  Pacific Environmen-
tal Services, Inc., under the  sponsorship
of the  U.S.  Environmental  Protection
Agency.

-------
   J.R. Komlnsky and R.W. Freybergare with Environmental Quality Management,
     Inc., Cincinnati, OH45240;D.R. GerberandG.J. Centifontiare with the Environ-
     mental Health Services - New Jersey Department of Health, Trenton, NJ 08625.
   Aaron R. Martin Is the EPA Project Officer and Alva Edwards is the EPA Technical
     Project Officer (see below).
   The complete report, entitled "Evaluation of the Implementation of Operations and
     Maintenance Programs in New Jersey Schools," (Order No. PB97-181424; Cost:
     §25.00, subject to change) will be available only from:
           National Technical Information Service
           5285 Port Royal Road
           Springfield, VA 22161
           Telephone: 703-487-4650
   The EPA Technical Project Officer can be contacted at:
           Sustainable Technology Division
           National Risk Management Research Laboratory
           U.S. Environmental Protection Agency
           Cincinnati, OH 45268
United States
Environmental Protection Agency
Center for Environmental Research Information
Cincinnati, OH 45268

Official Business
Penalty for Private Use $300
      BULK RATE
POSTAGE & FEES PAID
         EPA
   PERMIT No. G-35
EPA/600/SR-97/063

-------