-------
Chemical Impairment
Only (2.8%)
Biological Impairment
Only (49.8%)
Agreement (47.4%)
Case II: Ecoregional threshold concentrations for nutrients
improves the performance of water chemistry
Chemical Impairment
Only (6.2%)
Biological Impairment
Only (36.4%)
Agreement (57.4%)
Figure 6. Comparison of the abilities of biocriteria and chemical criteria to detect impairment of aquatic life uses in
625 waterbody segments throughout Ohio. Based on the use of chemical water-quality criteria as currently in the Ohio
WQS (upper) and supplemented with nutrients data using threshold values based on ecoregional analysis (lower).
93
-------
bias in estimates of water-resource status related to the
exclusion of tools such as biosurveys has been un-
known.
We performed an analysis to estimate the degree of bias
between an integrated biosurvey-based environmental
assessment and its water-column chemistry subcom-
ponents compared against water quality numerical
criteria (17). We found that the use of the water-column
chemistry data alone failed to detect impairment in 49.8
percent of the water bodies where an integrated biosur-
vey-based assessment indicated the aquatic life was im-
paired (Figure 6, top panel). Only 2.8 percent of the
water bodies examined showed impairment of chemical
water-quality criteria when the integrated biosurvey-
based assessment indicated attainment. A majority of the
water bodies with impaired aquatic life uses exhibited
problems related to organic enrichment or low dissolved
oxygen, sedimentation, and habitat degradation.
The inclusion of nutrient parameters (in relation to
ecoregional background concentrations of these
parameters (17)) improved the performance of the water
chemistry in detecting the impairment of aquatic life (an
additional 13.4 percent of the water bodies). However,
greater than one-third of the water bodies examined
were biologically impaired, but still not detected by the
water-column chemistry (Figure 6, bottom panel). Ob-
viously, simple water-chemistry-based "screening" ap-
proaches to detecting nonpoint source impaired waters
are insufficient to characterize all nonpoint impacts on
aquatic life uses. This is an especially critical finding,
considering that dollars are being spent on implementa-
tion of best management plans.
SUMMARY
Our experience in Ohio suggests that it is not possible to
adequately assess the effects of nonpoint pollution and
habitat degradation accurately without the use of biosur-
vey data. In situations where temporal impacts are in-
dividually small but cumulatively large over time (a
characteristic of many nonpoint and habitat problems),
environmental measures that reflect cumulative impacts
are important. Without the "common currency" of biosur-
vey results that provide overall measures of biological in-
tegrity, nonpoint control and restoration efforts will be
susceptible to the same criticism that the construction
grants program received: "What did the public receive for
the dollars spent on pollution control?" (18).
As a percentage of the money and effort that will be in-
vested in control and restoration for nonpoint pollution,
monitoring and biosurvey costs are comparatively small
(19). Finally, habitat assessment must be part of any
nonpoint assessment activity because of the close
relationship between the activities that cause nonpoint
runoff and habitat disturbance. Without integrated as-
sessment techniques, including chemical, physical, and
biological methods, important impacts to the nation's
aquatic life will be underrated or altogether overlooked.
REFERENCES
1. Ohio Environmental Protection Agency, 1990. State
of Ohio Section 319 Annual Report Fiscal Year 1990.
Nonpoint Source Management Section, Division of
Water Quality Planning and Assessment, Columbus,
OH.
2. Karr, J.R. and others, 1986. Assessing biological in-
tegrity in running waters: A method and its rationale,
///. Nat. Hist. Surv. Spec. Publ. 5, 28 pp.
3. U.S. Environmental Protection Agency, 1990.
Biological Criteria: National Program Guidance for
Surface Waters. EPA/440-5-90-004, U.S. EPA, Of-
fice of Water Regulations and Standards,
Washington, DC.
4. Hughes, R. M. and others, 1986. Regional reference
sites: a method for assessing stream potentials, Env.
Mgmt. 10:629-635.
5. Ohio Environmental Protection Agency, 1989.
Biological Criteria for the Protection of Aquatic Life:
Volume III, Standardized Biological Field Sampling
and Laboratory Methods for Assessing Fish and
Macroinvertebrate Communities, Division of Water
Quality Planning and Assessment, Columbus, OH.
6. Rankin, E.T. and C.O. Yoder, 1990. The nature of
sampling variability in the index of biotic integrity (IBI)
in Ohio streams, Proc. 3rd Midwest Poll. Control
Biologists Conf., U.S. EPA, Region V, Chicago, IL,
pp. 9-18.
7. Rankin, E.T., 1989. The Qualitative Habitat Evalua-
tion Index (QHEI): Rationale, Methods, and Applica-
tion, Division of Water Quality Planning and
Assessment, Columbus, OH.
8. Plafkin, J. L. and others, 1989. RapidBioassessment
Protocols for Use in Streams and Rivers: Benthic
Macroinvertebrates and Fish, U.S. EPA, EPA/444/4-
89-001, Office of Water, Washington, DC.
9. Karr, J. R., 1981. Assessment of biotic integrity using
fish communities, F/s/7er/es6(6):21-26.
10. Gammon, J.R., 1976. The fish populations of the
middle 340 km of the Wabash River. Tech Rep. 86,
Purdue University, Water Resource Research
Center, West Lafayette, IN.
11. Gammon, J.R. and others, 1981. The role of
electrofishing in assessing environmental quality of
the Wabash River. In J.M. Bates and C.I. Weber,
Ecological Assessments of Effluent Impacts on Co/77-
-------
munities of Indigenous Aquatic Organisms, STP 703,
ASTM, pp. 307-324.
12. Ohio Environmental Protection Agency, 1987.
Biological Criteria for the Protection of Aquatic Life:
Volume II, Users Manual for Biological Field Assess-
ment of Ohio Surface Waters, Division of Water
Quality Monitoring and Assessment, Surface Water
Section, Columbus, OH.
13. Miller, D.L. and others, 1988. Regional applications
of an index of biotic integrity for use in water
resource management, Fisheries 13(5): 12-20.
14. Hughes, R.M. and others, 1990. A regional
framework for establishing recovery criteria, Env.
Mgmt.-\ 4: 673-683.
15. Ohio Environmental Protection Agency, 1990. 1990
Ohio Water Resource Inventory: Executive Summary
and Volume I, Ecological Assessment Section,
Division of Water Quality Planning and Assessment,
Columbus, OH.
16. U.S. Environmental Protection Agency, 1990. Na-
tional Water Quality Inventory, 1988 Report to Con-
gress, EPA/440-4-90-003, U.S. EPA, Office of
Water, Washington, DC.
17. Rankin, E.T. and C.O. Yoder, 1990. A comparison of
aquatic life use impairment detection and its causes
between an integrated, biosurvey-based environ-
mental assessment and its water column chemistry
subcomponents, Appendix I in Ohio Water Resource
Inventory, Volume I, Ecological Assessment Section,
Division of Water Quality Planning and Assessment,
Ohio EPA, Columbus, OH.
18. U.S. Government Accounting Office, 1986. The
Nation's Waters: Key Unanswered Questions about
the Quality of Rivers and Streams. GAO/PEMB-86-6,
U.S. GAO, Program Evaluation and Methods
Division, Washington, DC.
19. Ohio Environmental Protection Agency, 1990. The
Cost of Biological Field Monitoring, Division of Water
Quality Planning and Assessment, Columbus, OH.
20. Yoder, C.O., 1989. The Development and Use of
Biological Criteria for Ohio Surface Waters, U.S.
EPA, Criteria and Standards Div., Water Quality
Stds. 21st Century, pp. 139-146.
95
-------
DEVELOPING NFS MONITORING SYSTEMS FOR RURAL SURFACE WATERS:
WATERSHED TRENDS
Donald W. Meals
School of Natural Resources
University of Vermont
Burlington, Vermont
INTRODUCTION
Nonpoint source (NFS) monitoring systems must be tied
closely to monitoring objectives. If, for example, the ob-
jective is to establish a cause-effect relationship between
treatment and response, four criteria must be met: as-
sociation, where, for example, a change in water quality
is correlated with a change in land use; consistency,
where the same association holds in different cases;
responsiveness, where the dependent variable changes
predictably when the independent variable changes; and
mechanism, where the relationship can be attributed to a
step-by-step path of specific processes (1). Rigorous es-
tablishment of cause-effect in NFS monitoring is very dif-
ficult and requires the tight experimental control generally
found only in short-term intensive monitoring of specific
practices or sites.
However, demonstrating the effectiveness of single prac-
tices in isolation is not the ultimate goal of many NFS
programs; the objective is more often to evaluate the
overall effectiveness of a program of practices at a
watershed or regional level. To do this, we must look at
broad watershed trends, most likely using a long-term,
fixed-station network.
The following discussion will focus on five important
points to consider in developing a monitoring system that
will provide a data base suitable for watershed trend
detection, i.e., a long sequence of data, collected sys-
tematically at regular intervals by consistent methods.
UNDERSTAND THE SYSTEM YOU WANT TO
MONITOR
A basic understanding of how the system to be
monitored behaves and what variables are important is
essential. The first step, therefore, is to collect and
evaluate existing background data. A more detailed in-
ventory or reconnaissance may be required to identify
hot spots or critical areas. Some preliminary new data
collection also may be necessary if adequate back-
ground data do not exist. Early development of stage-dis-
charge ratings, for example, should be a top priority at
previously ungauged stream stations.
These early efforts will contribute to one of the most im-
portant elements in designing the monitoring system:
identification and quantification of variability (2,3).
Variance and covariance, seasonality, and autocorrela-
tion are particularly important. Knowledge of the variance
of parameters to be monitored is essential to the deter-
mination of required sampling frequency; identification of
significant covariates may allow elimination of redundant
parameters. Cyclic seasonal patterns, which may
obscure trends, must be accounted for in trend analysis.
Autocorrelation must be assessed for two reasons. First,
most trend detection tests are sensitive to lack of inde-
pendence in time-series data. Second, in systems with
significant autocorrelation, reduced sampling frequency
may yield almost as much information at lower cost,
compared to more frequent sampling.
The primary goal of this preliminary assessment is to
characterize patterns not associated with treatment, e.g.,
natural variability; daily, monthly or seasonal cycles;
hydrologic cycles or changes; and preexisting trends, so
that their effects can be removed in subsequent analysis.
These sources of variability must be understood to detect
the signal amid the noise. Ward and Loftis (2) and Reck-
how and Stow (3) present excellent discussions of these
issues.
DESIGN THE MONITORING SYSTEM TO MEET
OBJECTIVES
Clear objectives for NFS monitoring should translate
easily into testable hypotheses; a specific hypothesis
provides a direct indication of what is necessary to ade-
quately test that hypothesis. In other words, monitor what
and where you expect response to treatment. Each site
or parameter should be tested against this rule.
Monitoring sites should be as close to the impaired use
and/or the treatment area as possible to avoid confound-
ing influences. If measurement of load is important to
project objectives, then streamflow monitoring is neces-
sary and the suitability of a site for flow measurement
adds an additional set of site-selection criteria. If violation
of water-quality standards is an issue, the parameters to
96
-------
be monitored and the site to be selected may be obvious.
In other cases, the impaired use or known source ac-
tivities will provide guidance in parameter selection.
Here, understanding of important covariates should as-
sist in parameter selection and might also improve cost
effectiveness by streamlining the parameter list. Conduc-
tivity, for example, may be a cheaper surrogate analysis
for total dissolved solids.
One monitoring design feature deserves special mention:
the control or reference watershed. Availability of parallel
water-quality data from an adjacent, untreated watershed
is of great value in controlling for the effects of year-to-
year climatic and hydrologic variation. In the LaPlatte
River Watershed Project in Vermont, data from an un-
treated control watershed was used in a paired water-
shed analysis. This analysis revealed significant changes
in posttreatment phosphorus export that were not
detected in a simple time series (4).
Once background variability is assessed, sampling fre-
quencies can be chosen for the level of precision re-
quired by the objectives or the magnitude of change
hypothesized (3). High variability, greater precision, and
smaller changes, of course, require higher sampling fre-
quencies. Some balance must be struck between captur-
ing significant information and the problems of
autocorrelation. Cost will also play a part.
Stream NFS monitoring often requires special considera-
tion of individual storm or snowmelt events. To maintain
the flexibility needed for such intermittent, intensive
monitoring without prohibitive cost, a schedule of routine-
ly collecting discrete samples that can be composited
over base flow periods might be appropriate. Such a
program, however, requires automated sample collection
and close coordination. Given'appropriate instrumenta-
tion and data, flow-proportional sampling may be the
most efficient sampling routine. Gilbert (5) provides a
thorough discussion of many specific monitoring designs.
PAY ATTENTION TO DETAILS AT THE
BEGINNING
Many of the nuts-and-bolts details of long-term monitor-
ing, which seem trivial at the start of a 10-year project,
loom large at the end. Management of large data sets,
for example, is a critical issue that requires more person-
nel and even more time than is initially believed.
Moreover, the people and the technology to manage
large amounts of data will inevitably change over the life
of a long-term project. Data checking and error screening
procedures must be built into a data management
system.
Quality assurance (QA) must be designed into all
aspects of the monitoring, including field operations as
well as the traditional laboratory QA/QC program. Even if
chain-of-custody protocols are not legally required, a
detailed sample tracking system is extremely valuable,
allowing unusual values on a data printout to be tracked
back to the time and place of sample collection. The im-
portance of routine maintenance, frequent field checks,
and detailed record-keeping cannot be overemphasized.
These are especially important in cold, northern climates.
Finally, some practical logistics must be considered. Im-
portant factors include site access, landowner coopera-
tion, availability of power, travel, and scheduling between
lab and field. Such considerations will inevitably temper
statistically ideal monitoring designs with practicality.
Optimum sampling frequency, for example, may differ for
different parameters; some compromise may be
necessary.
Some adjustment of parameter selection may also be
needed. Transient parameters such as dissolved inor-
ganic P and ammonia N, with short holding times for
laboratory analysis, often drive monitoring schedules and
personnel requirements, and thereby monitoring costs.
The question must be asked—are these parameters
worth the effort? In many cases, the answer will be yes,
but perhaps not always. In the LaPlatte River Watershed
Project, for example, results of trend analysis and overall
project conclusions were not substantially different for TP
and PO4-P or for TKN and NHa-N. In hindsight, analysis
for the transient parameters did not add dramatically to
the project results, but probably cost one full-time
equivalent in the laboratory each year for 10 years.
MONITOR SOURCE ACTIVITIES
In watersheds with point sources, it is essential to
monitor such discharges to account for their influence.
Because of their relative consistency, monitoring
schedules for point sources may differ from those
designed for NFS. The variability and vagaries of small,
rural wastewater treatment facilities, however, should not
be underestimated.
More often overlooked in this regard is land use and ac-
tivity monitoring. Generally, simple counting of best
management practices (BMPs) implemented will not be
enough. Land use and agricultural (or other source) ac-
tivity monitoring should be initiated early and information
should be collected at as great a level of detail as pos-
sible. Tracking compliance with BMPs after contract ex-
piration is particularly important.
In two Vermont agricultural NPS monitoring projects, for
example, land-use monitoring was a combined effort of
the land treatment implementation agencies (USDA-SCS
and ASCS) and the water-quality personnel (4,6). Infor-
mation was collected directly from watershed farmers.
The parameters monitored included:
• Animal population (animal units)
• Animal density (animal units/acre)
• Animals under BMP (percent of total)
97
-------
• Land in corn (acres and percent of watershed)
• Land in pasture (acres and percent of watershed)
• Land receiving manure (acres and percent of water-
shed)
• Manure applied (tons)
* Manure from storage (percent of total)
* Manure incorporated (percent of total)
• Erosion control (acres and percent of watershed)
The information collected in this program provided impor-
tant insights into observed water-quality data. Such land-
use monitoring efforts can be complex, time consuming,
and labor intensive. A Geographic Information System
(GIS) is an effective platform for management and
analysis of this kind of spatially referenced data.
BUILD IN FEEDBACK LOOPS
In intensive monitoring efforts, it is easy to focus on the
process and ignore the meaning of the accumulating in-
formation. It is very important, therefore, to build in feed-
back between monitoring data collection and evaluation
of monitoring results. The best way to do this is to look at
the data and look at it frequently. One effective but
sometimes painful way of doing this is to impose regular,
perhaps quarterly, reporting requirements, in addition to
traditional annual reports. Such requirements focusing on
basic data, not detailed analysis or interpretation, force at
least a minimum level of housekeeping so that data are
not lost or garbled.
More importantly, frequent looks at the data provide the
feedback loops that can improve both the monitoring and
implementation programs. Problems with field installa-
tions, sample collection, or laboratory analysis can be
caught before they become fatal. A close look at the data
can improve monitoring efficiency. Some parameters, for
example, might be eliminated if they are adequately rep-
resented by covariates. Station redundancy can be
evaluated by examining correlations between stations.
Monitoring data can be tested against objectives—does
the monitoring program provide the basis for testing the
initial hypotheses and meeting monitoring objectives? If
not, opportunities for a mid-course correction may exist.
Implementation patterns can also be adjusted, based on
water-quality results.
SUMMARY
Proper design of NPS monitoring systems makes trend
detection and data interpretation easier. Understanding
of the system to be monitored, especially quantification
of variability, will facilitate separation of the signal from
the background noise. Clear objectives for the monitoring
program should translate to hypotheses that are testable
using monitoring data. Practical details like data manage-
ment, QA/QC, and logistics should be carefully ad-
dressed at the start. Land treatments, as well as land use
and source activities, should be monitored in order to re-
late changes in water quality to the land treatment
program. Finally, feedback between data collection and
data evaluation should be built into the program to im-
prove monitoring effectiveness and, perhaps, to adjust
implementation patterns to serve water-quality goals.
The LaPlatte River Watershed Project was funded by the
USDA-Soil Conservation Service under the PL-566
program.
REFERENCES
Mosteller, F. and J.W. Tukey, 1977. Data Analysis
and Regression, Addison-Wesley Pub. Co., Reading,
MA.
1.
2.
3.
4.
5.
6.
Ward, R.C. and J.C. Loftis, 1986. Establishing statis-
tical design criteria for water-quality monitoring sys-
tems: Review and Synthesis. Water Resources. Bull.
22(5):759-767.
Reckhow, K. and C. Stow, 1990. Monitoring design
and data analysis for trend detection, Lake and
Reserv. Management. 6(1):49-60.
Meals, D.W., 1990. LaPlatte River Watershed Water
Quality Monitoring and Analysis Program - Year 11,
Program Report No. 12, Comprehensive Final
Report, Vermont Water Resources Research Center,
University of Vermont, Burlington, VT, 345 pp.
Gilbert, R.O., 1987. Statistical Methods for Environ-
mental Pollution Monitoring, 1987. Van Nostrand
Reinhold Co., Inc., New York, NY.
Vermont RCWP Coordinating Committee, 1989.
1989 Summary Report St. Albans Bay Rural Clean
Water Program, Vermont Water Resources Re-
search Center, University of Vermont, Burlington
VT, 257 pp.
98
-------
DEVELOPING A MONITORING SYSTEM FOR RURAL SURFACE WATERS:
INDIVIDUAL BMPS
John C. Clausen
University of Connecticut
College of Agriculture and Natural Resources
Storrs, Connecticut
INTRODUCTION
The previous paper discussed the development of a
water quality monitoring system for evaluating long-term
water quality trends in the data. An alternative objective
for a water quality monitoring study might be to evaluate
water quality improvements associated with individual
best management practices (BMPs). This latter objective
is appropriate when:
1. The water quality problem can be addressed by in-
dividual BMPs
2. Monitoring results are desired in the short-term (3 to
5 years)
3. The watershed receiving the BMP is small and
uniform
Monitoring individual BMPs may be highly appropriate.
There may be some quantitative uncertainty in their ef-
fectiveness of transferring results from other locations.
This paper reviews the steps needed to plan such a
monitoring system, suggests criteria for selecting sites,
discusses several experimental approaches in conduct-
ing the monitoring, and presents cost data. The informa-
tion presented in this paper is based primarily on
experiences obtained through monitoring the St. Albans
Bay Watershed Rural Clean Water Program and the
Laplatte River Watershed PL-566 land treatment
program.
STUDY PLANNING
Similar to the design of this workshop, there are several
steps that should be followed in planning a monitoring
system for an individual BMP (1,2,3). These steps are:
1. Define objectives. The objectives must address the
identified water quality problem. They also must be
useful to the study planners and executers to keep
everyone on track. The monitoring objective should
not be confused with a water quality goal or objec-
tive. An example of a monitoring objective might be:
"determine the effect of a vegetated filter strip on
fecal coliform exports." The associated water quality
goal might be: "reduce fecal coliform concentrations
in Unlucky Bay below 200/100 ml." The objectives
are critical in making sure that the right data are col-
lected from the right sites at the right time.
2. Select water quality parameters. These charac-
teristics of water quality should directly link to the ob-
jectives and are related to the activity being
monitored (e.g., mining, agriculture); the type of
waterbody (e.g., lake, stream); and previous
knowledge (e.g., probability of exceeding standards).
Activity matrices, correlation matrices among charac-
teristics, and probabilities of exceeding standards
are all useful tools in selecting parameters. Fre-
quently, too many parameters are measured. Two
parameters that are highly related to each other,
such as total P and ortho P, can often be reduced to
one. Parameters that are rejated to the public's per-
ception of the problem are highly recommended ad-
ditions. For example, some measurement of algae
productivity would be useful in impaired eutrophic
waters even though the cause of the problem may
be phosphorus.
3. Select sampling method. There are several
methods for sampling surface waters, including:
grab, depth integrated, continuous, and composite
collections. Furthermore, for composite sampling, a
decision is needed on whether to composite on a
time or flow basis.
4. Determine sampling locations. The actual location
to sample depends on the type of water body, the
study design, and characteristics of the station itself.
5. Estimate sampling frequency. Some method
should be used to determine how frequently to
sample. Sampling can be random, systematic, or
flow related. The number of samples to collect
should be based on the variability in the system as
well as the desired precision.
99
-------
6. Describe data analysis strategy. A system should
be established that identifies how data will be
managed and analyzed during and at the end of the
monitoring program.
SITE SELECTION CRITERIA
For monitoring the effectiveness of an individual BMP,
proper site selection is critical. The following is a list of
site-selection criteria that can serve as a basic beginning
point in selecting locations for monitoring:
• Topographically defined "small" watershed(s)
• Homogeneous land cover/use and soils
• Accessible, with power available
• Suitable for monitoring setup
• Land-use history is known
• Water-quality problem is documented
• Located within priority watershed
• Landowner is cooperative and willing to adopt BM P
• Ownership is economically stable
In our experience, the most difficult criteria to fulfill is
finding a small enough watershed, in a single land use,
with good topographic control, and no outside influences.
Also, I would recommend the use of multi-disciplinary,
multi-agency site-selection teams to develop criteria and
final selections.
STUDY DESIGNS
There are several experimental designs that have been
used for evaluating the water quality effect of a change in
activity in small watersheds (1). Four of these designs
are shown in Figure 1. Single watersheds are sometimes
monitored before and after treatment (Figure 1a). This
before period has sometimes been referred to as
"baseline." Differences in water quality due to the BMP
are usually expressed as means for the two time periods,
which are analyzed using the t-test. This is one of the
worst designs to use since differences may be due to
weather and not the BMP. For example, a dry year may
be followed by a wet year, in which case, concentration
reductions would be observed.
Monitoring in a single watershed above-and-below an
area receiving a BMP (Figure 1b) also has been used. If
done only after the BMP has been installed, the differen-
ces between stations may be inherent watershed dif-
ferences and not due to the BMP. This design is not as
susceptible to year-to-year climate differences as the
single watershed design with before and after sampling.
If monitored both before and after BMP implementation,
the design resembles paired watersheds as further dis-
cussed below.
Two watersheds, one with the BMP and one without,
also have been used to evaluate water quality effects
(Figure 1c); however, this method is incorrect since any
differences may be due to the watersheds and not the
BMP. The only conclusion from this two watershed ap-
proach is that the water quality may be different; the
cause cannot be identified, even when differences are
large.
The paired watershed design (Figure 1d) also uses two
watersheds but includes before and after periods (1, 4).
Since no two watersheds are alike, a regression equation
is used to describe the relationship between a control
and treatment watershed prior to the implementation of a
BMP. A second regression is developed following use of
the BMP and the two regressions are tested for differen-
ces in slopes and intercepts. The data used in this
design are paired concentrations, flows, organisms, in-
dices, or mass exports. Data may represent individual
samples or more often, daily, weekly, or monthly com-
posites. The paired watershed technique is considered
the best method for use at the watershed scale.
Two other designs described elsewhere are the nested
and multiple watershed methods (5, 6). These techni-
ques have some advantages over paired watersheds.
For example, the multiple watershed approach utilizes
perhaps 30 watersheds, half in the BMP and half without
it. These watersheds are typically spread over a broad
region and, therefore, represent a broader range of con-
ditions than obtainable with a single paired watershed
study. Multiple watershed sampling, however, also can
be conducted in a relatively short time frame. Nested
watershed designs facilitate separation of inherent water-
shed differences due to, for example, geology.
COSTS
The costs of conducting a paired watershed experiment
in Vermont ranged from $30,000 to $50,000/yr for three
or four years. These costs included personnel, con-
tinuous discharge and water sampling, and the analysis
of approximately six water quality characteristics.
SUMMARY
When developing a monitoring system for evaluating in-
dividual BMPs, a systematic planning approach is highly
recommended. An appropriate study design should be
selected before monitoring commences. Many frequently
used study designs have severe shortcomings for the
evaluation of water quality improvements associated with
BMPs.
REFERENCES
1. Ponce, S.L., 1980. Water Quality Monitoring
Programs, U.S. Forest Service, WSDG-TP-00002.
Fort Collins, CO.
100
-------
B
SINGLE WATERSHED
(Before & After)
ABOVE AND BELOW
D
TWO WATERSHEDS
PAIRED WATERSHEDS
Figure 1. Alternative study designs for evaluating BMP water quality efectiveness. (a) a single watershed sampled
before and after, (b) single watershed sampled above and below, (c) two watersheds in two activities/uses, and (d)
paired watersheds (1).
101
-------
2. Sanders, T.G., Ward, R.C., Loftis, J.C., Steele, T.D., 5.
Adrian, D.D., and Yevjevich, V., 1983. Design of Net-
works for Monitoring Water Quality, Water Resour-
ces Publications, Littleton, CO.
3. Whitfield, P.H., 1988. Goals and data collection 6.
designs for water quality monitoring, Water Resour-
ces Bulletin 24(4):775-780.
4. Clausen, J.C., 1991. Paired Watersheds for NPS
Water Quality Studies, Univ. of Conn, (in prep).
Striffler, W.D., 1965. The selection of experimental
watersheds and methods in disturbed forest areas,
I.A.S.H. Pub. No. 66, Symp. of Budapest, p. 464-.
473.
Clausen, J.C. and Brooks, K.N., 1983. Quality of
runoff from Minnesota peatlands: II, A method for as-
sessing mining impacts, Water Resources Bulletin.
19(5):769-772.
102
-------
MONITORING PROGRAM DEVELOPMENT IN AN URBAN WATERSHED
Thomas E. Mumley
California Regional Water Quality Control Board
Oakland, California
INTRODUCTION
The California Regional Water Quality Control Board,
San Francisco Bay Region (Regional Board) is the state
water pollution control agency responsible for protection
of the beneficial uses of San Francisco Bay and its
tributaries. Using its authority under both state and
federal law, the Regional Board required the develop-
ment and implementation of a nonpoint source control
program by the municipalities in the Santa Clara water-
shed, which drains into the South Bay segment of San
Francisco Bay. The focus of the program has been the
control of toxic pollutants in urban runoff within this
watershed.
An integral element of the program has been the
development of a comprehensive monitoring program.
The rationale and general design of the monitoring
program resulted from linking precise objectives for
monitoring with key management issues and questions
relating to nonpoint pollutant discharge in the watershed.
Monitoring tasks to fulfill these objectives were then iden-
tified, including an awareness of how these tasks will
provide for more informed management of the nonpoint
source control program. Explicitly linking management is-
sues and monitoring program objectives is vital if
monitoring programs are to generate information useful
to decision makers. Without this linkage, scientifically
valid (and costly) monitoring programs may be estab-
lished that generate new data about pollution but do not
provide relevant information from the management
perspective.
MANAGEMENT QUESTIONS
The discharge of toxic pollutants in urban runoff is con-
sidered an important source of pollution in the South Bay
and its tributary watersheds. To obtain the information
necessary to address this issue, the following working
management questions must be answered:
1. To what degree is nonpoint source discharge con-
tributing to water-quality standards exceedances in
the South Bay watersheds?
2. What are the pollutants of concern in urban runoff
nonpoint source pollution?
3. What are the pollutant loads entering the South Bay
due to nonpoint source discharge to tributary
streams?
4. What are the relative contributions of runoff loads
from various land uses?
5. Are pollutant loads during dry-weather periods im-
portant compared with wet-weather loads?
6. How do nonpoint source loads of pollutants compare
with point source loads?
PROGRAM OBJECTIVES
The next step in the monitoring program design involves
developing monitoring program objectives which, when
achieved, will provide the necessary information to
answer (to the maximum extent possible) these manage-
ment questions. The following objectives were developed
for the Santa Clara program:
• Determine whether water-quality standards (chemi-
cal specific and toxicity) are being attained in South
Bay watersheds
• Obtain sufficient precipitation and hydrology data to
calibrate and verify hydrologic model
• Determine pollution concentrations and loads during
storm events from sites repesentative of various land
use categories (open, single-family residential,
multifamily residential, commercial, and heavy
industry)
• Calibrate and verify watershed (systemwide)
hydrologic pollutant load model and provide nonpoint
source pollutant load estimates
• Evaluate the role of stream bed sediments as both a
source and sink of pollutants associated with non-
point source runoff
103
-------
MONITORING PROGRAM ELEMENTS
To meet the established objectives, specific monitoring
program elements or tasks are identified and imple-
mented, A handicap on any monitoring program is the
limited availability of funds. It is important, therefore, to
(ocus available resources toward obtaining the most rep-
resentative data that will meet program objectives. It is
also appropriate to consider a phased implementation
schedule that relies on initial pilot scale or screening ac-
tivities leading toward more long-term comprehensive
elements to meet program objectives. Additionally, single
monitoring tasks may satisfy, in part, several objectives.
This is an inherent benefit of an effective monitoring plan
with clearly defined objectives. Finally, all elements
should include rigorous sampling and laboratory quality
assurance protocols.
The following monitoring program elements or tasks
were Identified and implemented in the Santa Clara
program:
1, Twelve monitoring stations were selected.
Eight were points in storm drains which drain small,
relatively homogeneous land use catchments.
These stations were assumed to represent runoff
from areas of similar land use categories throughout
the watershed. Water-quality data from these catch-
ments were used as input to the loading model.
Four were in streams located in the lower portions of
the watershed, which received a composite of storm
runoff waters from multiple land use categories.
Stream stations were monitored to provide data to
compare with numerical water quality standards and
to calibrate the loading model.
2. The hydrology monitoring element consisted of con-
tinuously monitoring flows at streams and land use
stations at hourly intervals throughout the duration of
the program in order to estimate the hydrological
component of the load.
3. Wet-weather monitoring consisted of monitoring
water quality at land use and stream stations for
seven storm events. Flow composite samples were
collected using automatic samplers to provide event
mean concentrations. Parameters monitored in-
cluded toxic pollutants (metals, petroleum hydrocar-
bons, pesticides, and herbicides), nutrients, bacteria,
and conventional pollutants (BOD, suspended sedi-
ments, pH, etc.).
4. Dry-weather monitoring was conducted by obtaining
grab samples at the four stream stations quarterly.
The same suite of pollutants as the wet-weather ele-
ment were monitored.
5. Streambed sediment sampling for toxic pollutants
and sediment characteristics (organic carbon, grain
size, etc.) was conducted quarterly at the four stream
stations.
6. A toxicity testing program was designed as an initial
screening of toxicity exerted by wet-weather samples
(three events) obtained from land use and stream
stations and dry-weather samples (three events) at
stream stations. Bioassays were conducting using
three test species: ceriodaphnia dubia (water flea), sur-
vival and reproduction; pimephales promelas (fathead
minnow), survival and growth; and selanastrum
capricornutum (green algae), cell density.
7. The empirical data obtained from the monitoring
program were incorporated into a systemwide
hydrologic and pollutant load model (the Stormwater
Management Model).
MONITORING PROGRAM RESULTS
The initial phase of the Santa Clara monitoring program
was conducted over, a 2-year period. The examples of
monitoring program results (see Table 1) illustrate how
the monitoring program objectives were met and how the
management questions were addressed by implementa-
tion and completion of the monitoring program elements.
Selected trace metals results from stream station
monitoring are presented in Table 1. The site median
concentration for each station is the transform of the log
mean of all data from that station. (The data were repre-
sented by a log-normal distribution.) The presentation of
these data illustrates two points:, 1) concentrations of
these metals at the steam stations are significantly
greater during storm events than during dry-weather
periods; and 2) water-quality standards for these metals
are exceeded at the stream stations during storm events
but not during dry-weather periods.
Selected trace metal results from land-use station
monitoring are presented in Table 2. These data illustrate
several points: 1) there was no significant difference
among site median concentrations from the various
residential and commercial land-use sites; 2) there were
significant differences among the combined residential-
commercial data and the industrial land-use median
concentrations and the open land-use median concentra-
tions; and 3) the open land-use results were comparable
to dry-weather period stream station results.
A time series plot of annual total nonpoint source load for
copper versus Water Year is presented in Figure 1. The
loads are predicted by application of the Stormwater
Management Model using the hydrologic and water
quality monitoring data. Water Years begin on October 1.
The upland 'areas of the Santa Clara watershed contain
several reservoirs. The Wet Weather Reservoir Releases
loads represent the copper loads associated with
releases from these reservoirs during intensive rainfall
periods.
104
-------
so-r
fl 40-
"5
c. soH
•o
2
9- 20-j
10 H
• Diy Weather Row
D Wet Weather Reservoir Releases
Wot WeattMr Runoff
Average Annual Point
Source Load (8000 fcs)
77-78 78-79 79-80 80-81 81-82 82-83 83-84 84-85 85-86 86-87 87-88 88-89
Water Year
Figure 1. Santa Clara monitoring program—time series of annual total nonpoint source load for copper.
Several points are illustrated in this figure: first, dry-
weather flow loads are insignificant compared to wet
weather runoff loads; second, annual wet-weather runoff
loads vary significantly. They are related to the significant
variation in annual precipitation and associated runoff.
For example, precipation during Water Years '82-'83 and
'85-'86 was much greater than the norm, whereas
precipation during Water Years '87-'88 and '88-'89 was
much less than the norm. Third, during 1987 and 1988
the average annual load of copper from the three public
treatment works that discharge to the South Bay was
8,000 pounds. Thus, the total nonpoint source load of
copper is significantly greater some years and sig-
nificantly less other years when compared with the total
point source load of copper.
The above results are representative of the success of
the Santa Clara monitoring program. The main results of
the monitoring program are summarized below:
1. Water-quality loads are directly proportional to
cumulative runoff volume.
2. Concentrations of pollutants at land-use stations are
relatively uniform among runoff events. Higher
values are not observed for the first storm event of
year.
3.
4.
5.
Concentrations of pollutants in streams are higher
during the first storm event compared with later
events.
Water quality was distinctly different for open, com-
mercial/residential, and heavy industry.
Trace metals (cadmium, chromium, copper, lead,
nickel, and zinc) were prevalent during wet weather.
6. Organochlorine pesticides (DDE, DDt, etc.) and
polynuclear aromatic hydrocarbons were detected at
trace levels (u.g/L) in about 25 percent of wet-
weather samples.
7. Wet-weather runoff is distinctly toxic, both acute and
chronic, to test species.
8. Trace metals (chromium, copper, lead, nickel, and
zinc) in sediments are consistently detected at levels
well above 50 mg/kg.
9. Organochlorine pesticides and polynuclear aromatic
hydrocarbons are commonly detected in sediments.
10. Stream sediments may be acting as a sink (during-
low flow periods) and a source (during high-flow
periods).
105
-------
Table 1. Santa Clara County Trace
Site
Wet Weather
S-1
S-2
S-3
S-4
Water Quality Standard
Dry Weather
S-1
S-2
S-3
S-4
Table 2. Santa Clara County Trace
Site
Residential/Commercial Land Uses
L-1
L-2
L-3
L-4
L-5
Metals Results — Stream Sites
Copper
47
42
48
33
20
7
3
3
6
Site Median Concentrations (|ig/L)
Lead
39
39
52
'44 ' '" ' ' •
10
1
1
2
1
Nickel
47
32 . • ...-,..;.
65 ; - ,
23
100 ••,•:•'."
2
2
2
2
Metals Results— Land-Use Sites
Copper
35
22
22
33
47
Site Median Concentrations (p.g/L)
Lead
63
47
40
44
49
Nickel
47
15
25
23
27
All Residential Commercial Sites
31
37
25
Industrial Land Use
L-2
49
121
48
Open Land Use
L-7
106
-------
11. Runoff loads are comparable to point source loads.
12. Annual loads are highly variable from year to year.
SUMMARY
The Santa Clara, program provides an instructive ex-
ample of the successful development and implementa-
tion of a monitoring program in an urban watershed. The
key to the program's success is the approach taken to
develop clearly defined monitoring program objectives.
Precise objectives were linked with key management is-
sues and questions relating to nonpoint pollutant dis-
charge in the watershed. This approach allows limited
monitoring resources to be focused on monitoring tasks
designed to fulfill these objectives and consequently ad-
dress the management issues of concern. The success
of the Santa Clara program has enabled managers in the
Santa Clara watershed to design a comprehensive and
cost-effective nonpoint source control program.
Monitoring efforts continue and build upon results ob-
tained to date. The continuing monitoring program is
based upon an annual evaluation of management issues
and monitoring program objectives. This intrinsic linkage
between management issues and monitoring objectives
should ensure continued success of the program.
107
-------
-------
SECTION SEVEN
BUILDING SUCCESSFUL TECHNOLOGY TRANSFER PROGRAMS
-------
BUILDING SUCCESSFUL RURAL STATE-LEVEL TECHNOLOGY TRANSFER
PROGRAMS
Thomas E. Davenport, Wayne P. Anderson, and
James W. Meek
EPA Region 5, Chicago, Illinois;
Minnesota Pollution Control Agency, St. Paul,
Minnesota;
USDA, Washington, DC
INTRODUCTION
The 1987 amendments to the Clean Water Act estab-
lished Section 319 to address nonpoint source pollution.
For many waterbodies, nonpoint source pollution ex-
ceeds that of point source pollution and still needs to be
addressed. Section 319(1) mandates EPA "collect infor-
mation and make available, through publications and
other appropriate means, information pertaining to
management practices and implementation methods,"
thus EPA has a mandate to implement a national tech-
nology transfer program. In accordance with Section
319(b), states have the leadership role in technology
transfer and information/education at the state and local
levels.
Nonpoint source management tools are evolving in
response to the need for clear, useful methods for con-
trolling nonpoint source pollution and prioritizing actions
to reduce or eliminate nonpoint source pollution. These
tools must be distributed at the local level for use, and to
other members of the research community so as not to
waste money through a duplication of effort. This trans-
ferring of ideas and tools will be accomplished through a
two part process of information/education and technology
transfer efforts. The information/education process builds
awareness and acceptability of technology transfer tools
and kteas. The technology transfer process provides the
tool to the end user. For the purpose of this paper, tech-
nology is defined as the branch of knowledge that deals
with applied science.
ERA'S ROLE
In January 1989, EPA released "Nonpoint Sources Agen-
da for the Future: Nonpoint Source Solutions." This
Agenda set forth a National Nonpoint Source Program
aimed at supporting and reinforcing state and local
governments' nonpoint source control efforts developed
in response to Section 319 requirements. The Agenda
outlined five areas for EPA to focus its energy, resour-
ces, and actions on:
• Public awareness
• Successful solutions
• Financial forces and incentives
• Regulatory programs
• Good science
EPA's nonpoint source technology transfer activities are
included in two areas, "successful solutions" and "good
science." Each area has its own focus. For EPA to
achieve its goals in either of these two areas, the "public
awareness" component needs to be successfully imple-
mented. Under "good science," EPA will be developing
tools state and local governments need to establish
sound water quality programs for nonpoint source con-
trol. EPA's Office of Research and Development and in-
dividual program offices have specific areas of
responsibility under this component.
Under successful solutions, EPA will 'Work with the
public and private sectors to package and deliver high-
quality technology transfer and training workshops to
help states and local governments" (1). Rather than un-
dertaking an enormous technology development
program, EPA will direct its energies and resources to
sharing information and experiences with existing and/or
new creative nonpoint source management approaches
developed by others.
STATES' ROLE
Section 319 required states to complete a State Assess-
ment Report describing the state's nonpoint source
problems, and a state management program document-
ing what the state plans to do in the next four years to
address their nonpoint source problems. The manage-
ment program should include information/education and
technology transfer programs, since the statute specifi-
cally mentions technology transfer under Section 319
(b)(2)(B). This legislative mandate establishes the state's
leadership role in nonpoint source technology transfer ef-
110
-------
forts. Through the Management Program development
process, the state should have identified clear agency
roles for the nonpoint source technology transfer
program. For example, in Minnesota the Metropolitan
Council is responsible for conducting technical transfer
activities in the Twin Cities metropolitan area. The Min-
nesota Pollution Control Agency is the lead agency for
nonpoint source control in Minnesota and is responsible
for establishing the framework and funding priorities for
technology transfer activities under Section 319.
TECHNOLOGY TRANSFER PROCESS
The act of disseminating technical material from the
development/modification stage to the local end user is
called the technology transfer process. The technology
transfer process is considered an ideal process. Suc-
cessful technology transfer programs are built upon ag-
gressive and comprehensive information/education
programs which create an awareness of what the
problems are and what can be done to solve them.
Technical products (tools/techniques) are developed in
response to three factors, the first two of which are re-
lated to problem awareness:
• Identified nonpoint source problem
• Concern of agencies and landowners about the
problem
• Inadequate materials to address problem
Recognition of a problem, the need to address the
problem, and the lack of an appropriate tool constitute
the first steps in the technology transfer process. Based
upon this recognition, the appropriate organization
develops an action plan to address the need through the
development/modification of a tool or technique. For ex-
ample, in 1990, the United States Department of Agricul-
ture-Cooperative Extension Service distributed
information/education packets on the National Drinking
Water Week and National Water Quality Initiative to their
county offices. The purpose of these packets was to
develop an awareness of these programs at the county
level . The initial results from the followup surveys indi-
cate awareness of these programs had increased sub-
stantially.
The action plan needs to include the following:
• A development/modification process
• A clearly identified end product (i.e., a tool/technique
with user's guide)
• A product distribution mechanism or implementation
strategy
• An evaluation component
The development/modification process needs to include
field application/demonstrations to verify the end product.
Through the use of cost sharing with individual land-
owner/operators, Section 319 highlights the need for
demonstrations of new technology or approaches. It is
important to note that tools/techniques not properly field
tested or verified, can create greater water quality
problems than they are designed to solve. Untested
tools/techniques may transfer the problem to another
media or water resource type such as ground water.
The development of the Agricultural Nonpoint Source
(AgNPS) model followed this approach. Based upon the
initial acceptance of the AgNPS model, the Minnesota
Pollution Control Agency expanded the model's initial
development group and established a steering commit-
tee of interested agencies to assist in the further
development of the AgNPS Model. The Steering Com-
mittee assisted the initial group in creating a framework
for the long-term development and distribution/transfer of
the AgNPS model. The AgNPS development plan al-
lowed other agencies to target funding for their specific
program needs. The process provided the framework
under which the USDA National Standards and
Specifications for Nutrients and Pesticides were
developed.
Any developed or modified tool or technique needs to be
field tested prior to large scale distribution, and in recog-
nition of the "Hawthorne Effect," the evaluation com-
ponent needs to be targeted at examining the
implementation of the product outside of the develop-
ment setting. The "Hawthorne Effect" describes how in-
dividuals produce at a higher level in response to special
attention. Specifically, the evaluation needs to con-
centrate on the following: whether or not the tool addres-
ses the identified need, whether the tool is being used
properly, and whether there have been problems with its
application.
PRODUCT DISTRIBUTION PROCESS
For each tool being developed or modified, a distribution
plan needs to be developed to effectively transfer the tool
from the development stage to the implementation
phase. Figure 1 shows three mechanisms for transferring
technology to the end user. Each mechanism needs a
specific evaluation component to determine if the end
user is using the tool properly. Any new tool needs a
combination of all three mechanisms to be transferred to
the end user in an effective manner. For tools being
modified, such as the CREAMS model, only two of the
three mechanisms for distribution are needed for the suc-
cessful transfer of technology—workshops (training) and
publications.
Workshops or training walk the end user and trainer
through the application of the tool, while publications ex-
plain the tool and provide documentation of its com-
ponents and its effectiveness. Demonstration projects
are designed to educate individuals on the use of non-
111
-------
PRODUCT DISTRIBUTION
MECHANISM
WORKSHOP/TRAINING
PUBLICATIONS
DEMONSTRATIONS
Figure 1. Distribution plan for transferring technology.
point source best management practices (BMPs) and to
demonstrate their feasibility and utility. They may also be
research projects that document the effectiveness and
applicability of BMPs as nonpoint source management
tools. Demonstration projects have three different phases
as they relate to the technology transfer process:
• Announcement phase. The purpose of this phase is
to detail the concept and purpose of the demonstra-
tion project.
• Progress report phase. The purpose of this phase is
to keep interest in the concept and to document
progress on the issue.
• Results phase. The purpose of this phase is to report
the results of the tool's application.
In order to build support for the concept being
demonstrated, outside the demonstration area as well as
within, it is imperative to keep the public, including re-
lated projects' personnel, informed.
The target audience for technology transfer efforts in-
cludes those who deliver the tool (agencies/private
sector), those who are affected by the tool (land-
owner/operator), and those who support the change
(private sector). The acceptability of the tool to the latter
two groups is affected to varying degrees by the success
of the information/education program in developing
awareness of the problem and the need to do something
about it.
FARMSTEAD ASSESSMENT SYSTEM
CASE STUDY
The University of Wisconsin Extension, working with
farmers, identified a need for a systematic evaluation
process that farmers could use to assess the potential of
their farmstead layout and activities to contaminate
ground water. Recognizing this need, the University of
Wisconsin-Extension and other state and federal agen-
cies initiated the farmstead assessment project. This
project resulted in the development of the Farmstead As-
sessment System, which consists of a series of basic
worksheets that provide information on the factors that
affect ground-water pollution risks and provide guidance
in evaluating farm-specific pollution potential. The
worksheets also provide information on methods to
reduce the contamination potential of the activities or
structures evaluated. In addition, each worksheet iden-
tifies local resource agencies and personnel who can
provide advice on the 'assessment system and assis-
tance in making recommendations concerning possible
changes in farmstead operations. The worksheets repre-
sent the best professional judgment of experts, and
these worksheets were extensively peer reviewed. The
System has received extensive national exposure
112
-------
through various publications, and this has generated in-
terest in the project nationwide.
The evaluation of the applicability and feasibility of the
System consists of a two pronged approach: 1) focus
group discussions and 2) field testing. The focus group
discussions with farmers, county-level staff, and private
sector personnel concentrate on the following areas:
• Clarity and utility of worksheets and the overall Sys-
tem
• Degree of technical support and training required for
technical staff as well as users (farmers)
• Effectiveness of procedures designed to assist
farmers in establishing priorities for minimizing
ground-water contamination
• Effectiveness of the delivery mechanisms
• Potential for behavior modification based on use of
the System
The field testing approach consisted of applying the as-
sessment in four counties and examining the same five
factors as the focus group discussions did. The field test-
ing component has been completed and the results are
being analyzed. Based upon the initial results and the
nationwide interest in the Farmstead Assessment Sys-
tem approach, there is a process underway to transfer
the farmstead assessment system nationwide. For more
information on the development of the Farmstead As-
sessment System, see Jones (2). For information on the
status of the Farmstead Assessment System, please
contact Ms. Sue Jones, University of Wisconsin-Exten-
sion Service, Environmental Resource Center, Agricul-
ture Hall, Room 216, 1450 Linden Drive, Madison, Wl
53706. Her phone number is 608-262-2031.
REFERENCES
1. EPA, 1989. Nonpoint Source Agenda for the Future:
Nonpoint Source Solutions.
2. Jones, S.A. and G.W. Jackson, 1990. Farmstead As-
sessments: a strategy to prevent groundwater pollu-
tion, Journal of Soil and Water Conservation,
March-April, 45 (2).
113
-------
MITIGATING THE ADVERSE IMPACTS OF URBANIZA TION ON STREAMS:
A COMPREHENSIVE STRATEGY FOR LOCAL GOVERNMENT
Thomas Schueler
Metropolitan Washington Council of Governments
Washington, DC
INTRODUCTION
Urban streams are arguably the most extensively
degraded and disturbed aquatic systems in North
America. In general, stream systems tend to reflect the
character of the watershed in which they drain. Given the
massive physical conversion in a watershed that accom-
panies urbanization, the degraded nature of urban
streams is not surprising.
Over the last two decades, substantial evidence has ac-
cumulated regarding the pervasive impacts of urbaniza-
tion on stream hydrology, geomorphology, water quality,
habitat, and ecology (Table 1). In response, local
governments within the rapidly growing Washington
metropolitan area have developed an increasing number
of stringent measures to mitigate the impact of new
development on streams. The effectiveness of these
measures has varied considerably, in large part because
they have not been applied in a coordinated and com-
prehensive manner.
This paper outlines a watershed approach for urban
stream protection that incorporates the most useful and
effective planning and engineering techniques that have
evolved in the Washington metropolitan area. The
stream protection strategy is based on comprehensive
and continuous regulation of the development process
from the master planning stage until it is ultimately
realized.
THE IMPACTS OF URBANIZATION ON
STREAMS
Urbanization has a profound influence on stream quality.
The extent of this influence is obvious when an urban
stream is compared with another in a rural or natural
watershed. Impacts on urban streams can be loosely
grouped into four categories: changes to stream hydrol-
ogy, geomorphology, water quality, and aquatic ecology.
The intensity of the impacts is typically a function of the
intensity of urbanization. A convenient measure of
development intensity is the percentage of watershed
area devoted to impervious surfaces (roads, parking lots,
rooftops, sidewalks, compacted fill, etc.). Operationally,
watershed imperviousness can be simply defined as the
fraction of watershed area that is unvegetated.
Changes in Stream Hydrology
The hydrology of urban streams changes immediately in
response to site clearing. The natural runoff storage
capacity is quickly lost with the removal of the protective
canopy of trees, the grading of natural depressions, and
the elimination of spongy topsoil and wetland areas. As
the soil is further compacted and resurfaced by imper-
vious materials, rainfall can no longer percolate into the
soil and is rapidly and effectively converted into surface
runoff. Thus, the net effect of development is to dramati-
cally change the hydrologic regime of the urban streams
such that:
• The magnitude and frequency of severe flood
events increases. In extremely developed water-
sheds (impervious >50 percent), the postdevelop-
ment peak discharge rate may increase by a factor
of five from the predevelopment rate. These more
severe floods reshape the dimensions of the stream
channel and its associated floodplain.
In addition, watershed development increases the
frequency of bankfull and sub-bankfull flooding
events. Bankfull floods are defined as floods that
completely fill the stream channel to the top of its
banks, but do not spill over into the floodplain.
Schueler (1) estimated that the number of bankfull
floods increases from one every other year (prior to
development) to over five each year (fora 50 percent
impervious watershed). In practical terms, this
means that a short but intense summer thunderstorm
that scarcely raised water levels prior to develop-
ment may turn an urban stream into a raging torrent.
The greater number of bankfull floods subject the
stream channel to continual disturbance by channel
scour and erosion.
• More of the stream's annual flow is delivered as
surface storm runoff rather than baseflow or in-
terflow. In natural undeveloped watersheds,
anywhere from 5 to 15 percent of the annual
streamflow is delivered during storm events, depend-
114
-------
Table 1. Major Stream Impacts Caused by Urbanization
Changes in Urban Stream Hydrology
Increase in Magnitude and Frequency of Severe Floods
Increased Frequency of Erosive Bankfull Floods
Increase in Annual Volume of Surface Runoff
More Rapid Stream Velocities
Decrease in Dry-Weather Baseflow on Stream
Changes in Urban Stream Morphology
Stream Channel Widening and Downcutting
Increased Streambank Erosion
Shifting Bars of Coarse-Grained Sediments
Elimination of Pool/Riffle Structure
Imbedding of Stream Sediments
Stream Relocation/Enclosure or Channelization
Stream Crossings Form Fish Barriers
Changes in Urban Stream Water Quality
Massive Pulse of Sediment During Construction Stage
Increased Washoff of Pollutants
Nutrient Enrichment Leads to Benthic Algal Growth
Bacterial Contamination During Dry and Wet Weather
Increase in Organic Carbon Loads
Higher Levels of Toxics, Trace Metals, and Hydrocarbons
Water Temperature Enhancement
Trash/Debris Jams
Changes in Stream Habitat and Ecology
Shift from External to Internal Stream Production
Reduction in Diversity of Aquatic Insects
Reduction in Diversity and Abundance of Fish
Destruction of Wetlands, Riparian Buffers, and Springs
ing on watershed vegetative cover, soils, and geol-
ogy. By contrast, in developed watersheds, the
majority of annual streamflow occurs as surface
runoff. As a general rule, the amount of storm runoff
increases in direct proportion to the amount of water-
shed imperviousness. For example, surface runoff
typically comprises half the annual streamflow in a
watershed that is 50 percent impervious (1).
Consequently, the amount of baseflow and interflow
available to support streamflow during extended
periods of dry weather is greatly reduced. In smaller
headwater streams, the reduction in dry-weather flow
can cause a perennial stream to become seasonally
dry. In larger urban streams, the reduced dry-
weather flow can significantly restrict the wetted
perimeter of the stream that is available for aquatic
habitat.
• The velocity of flow during storms becomes
more rapid. This is due to the combined effect of
greater discharge, rapid time of concentration, and
smoother hydraulic surfaces. In a 50 percent imper-
vious watershed, postdevelopment runoff velocities
exceed thresholds for erosivity, requiring channel
protection measures or even stream enclosure. In
addition, streamflow becomes extremely flashy, with
sudden and sharp increases in discharge followed by
an equally abrupt return to prestorm discharge
levels.
Changes in Urban Stream Morphology
Stream channels in urban areas must respond and ad-
just to the altered hydrologic regime that accompanies
urbanization. The severity and extent of stream adjust-
ment is a function of the degree of watershed imper-
viousness, and can be summarized as follows:
• The primary adjustment to the increased
stormflow is channel widening, and to a lesser ex-
tent, down-cutting. Stream channels in moderately
developed watersheds may become four times wider
than after development (1). The channel-widening
process is primarily accomplished by lateral cutting
of the streambanks. As a consequence, the riparian
zone adjacent to the channel is severely disturbed by
undercutting, tree-fall, and slumping.
• Sediment loads to the stream increase sharply
due to streambank erosion and upland construc-
tion site runoff. The coarser-grained sediments are
deposited in the new wider channels and may reside
there for years until the stream can export them from
the watershed. Much of the sediment remains in
temporary storage, in the form of constantly shifting
sandbars and silt deposits. The shifting bars often
accelerate the streambank erosion process by
deflecting runoff into sensitive bank areas.
• Together, the massive sediment load and channel
widening produce a major change in the morphology
of urban streams. The series of pools and riffles
so characteristic of natural streams is eliminated,
as the gradient of the stream adjusts to accom-
modate the frequent floods. In addition, the depth of
flow in the channel becomes shallower and more
uniform during dry-weather periods. The loss of pool
and riffle structure in urban streams greatly reduces
the availability and diversity of habitat for the aquatic
community.
• The nature of the streambed is also modified by the
urbanization process. Typically, the grain size of
the channel sediments shifts from coarse-
grained particles towards a mixture of fine- and
coarse-grained particles. This results in a
phenomenon known as imbedding, whereby sand,
silt, and even clay fill up the interstitial voids between
115
-------
larger cobbles and gravels. Imbedding reduces the
circulation of water, organic matter, and oxygen to
the filter-feeding aquatic insects that live among and
under the bed sediments. These insects are the
basic foundation of the stream food chain. In addi-
tion, imbedding of the stream sharply limits the
quality and availability of fish spawning areas, par-
ticularly for trout.
• In intensively urbanized areas, many streams are
totally modified by man to "improve" drainage
and reduce flooding risks. Headwater streams
tend to suffer disproportionately from enclosure.
Quite simply, the headwater stream is entirely
destroyed, and is replaced by an underground net-
work of storm drainpipes. In the past, larger urban
streams have been engineered and channelized to
more efficiently and safely convey floodwaters.
Although large-scale stream channelization is now
discouraged, some form of future channel
"improvement" is inevitable if development is allowed
within the postdevelopment f loodplain.
• Another inevitable consequence of urbanization
is stream crossings by roads and pipelines.
These structures must be heavily armored to
withstand the down-cutting power of stormwater.
Many engineering techniques utilized for this pur-
pose (drop structures, gabion mats, culverts, etc.)
create barriers to the migration of both resident and
anadromous fish. Even a 6 in. drop can block the
upstream movement of many fish species, making
recolonization of upstream areas impossible after a
disturbance event.
Changes in Stream Water Quality
During the initial phase of development, an urban stream
receives a massive pulse of sediment eroded from
upland construction sites. Unless erosion and sediment
controls are used, sediment loads and turbidity levels in-
crease by two to three orders of magnitude from
predevelopment levels. Sediment levels often decline
once upland development stabilizes but never return to
predevelopment levels, because of increased stream-
bank erosion.
Once construction is complete, the dominant pathway of
pollutants to a stream is the washoff of accumulated
deposits from impervious areas during storms (2). Sub-
stantial quantities of nitrogen, phosphorus, carbon,
solids, and trace metals are deposited on urban surfaces
as both dry and wet atmospheric deposition, and are
rapidly and directly conveyed to the stream via storm
drains. Other non-atmospheric sources of pollutant ac-
cumulation are also important, such as pet droppings,
leaf litter, vehicle leakage, and deterioration of urban
surfaces.
In general, the pollutant levels in urban streams are one
to two orders of magnitude greater than those reported in
forested watersheds. The degree of pollutant loading has
been shown to be a direct function of the percentage of
watershed imperviousness (1). In urban streams, the
higher pollutant loadings translate into water-quality
problems, such as:
• Nutrient enrichment. Nitrogen and phosphorus con-
centrations in urban runoff stimulate excessive algal
growth, particularly in shallow, unshaded stream
reaches. Most algal growth is benthie in nature, at-
taching on rocks or growing within the slime coating
that surrounds rock surfaces in urban streams.
• Bacterial contamination. Bacterial levels in urban
streams routinely exceed U.S. Public Health stand-
ards during both wet and dry weather, rendering
them unsuitable for water contact recreation. The
sources of bacterial contamination are complex, but
include the washoff of pet feces and leakage from
sanitary sewer lines.
• Organic matter loads. Loads of organic matter
delivered during storm events are equivalent in
strength to primary wastewater effluent. When the
organic matter eventually settles out in slower
moving lakes and estuaries, the oxygen demand ex-
erted during their decomposition depletes oxygen
from the water column.
• Toxic compounds. A large number of potentially
toxic compounds are routinely detected in urban
stormwater. These include trace metals (lead, zinc,
copper, cadmium, and zinc), pesticides, and
hydrocarbons (derived from oil/grease and gasoline
runoff), among others. While the duration of ex-
posure to these toxic chemicals is limited during
storms, they tend to accumulate in benthal sedi-
ments of urban streams, lakes, and estuaries. Not
much is known about the individual or collective
toxicity of these compounds to the stream com-
munity. However, some degree of impact is likely,
given the consistently poor aquatic diversity noted in
these ecosystems.
• Temperature enhancement. Impervious areas act
as heat collectors. Heat is then imparted to
stormwater runoff as it passes over the impervious-
ness. Recent data indicate that intensive urbaniza-
tion can increase stream water temperatures by as
much as 5 to 10°C during storms (3). A similar
temperature increase may occur during dry weather
periods, if a stream's protective riparian forest
canopy has been eliminated or if ponds and lobes
are created upstream.
The thermal loading severely disrupts aquatic or-
ganisms that have finely tuned temperature limits.
116
-------
Cold-water organisms such as trout and stoneflies
are particularly sensitive, and often become locally
extinct in intensively developed streams.
• Trash/debris. A conspicuous and diagnostic feature
of urban streams is the presence of large debris
jams in the stream and floodplain, composed of litter,
leaves, and trash that have washed through the
storm drain system. The debris jams greatly detract
from the scenic appearance of the stream.
Changes in Stream Habitat and Ecology
The ecology of urban streams is shaped and molded by
the extreme shifts in hydrology, morphology, and water
quality that accompany the development process. The
stresses on the aquatic community of urban streams are
both subtle and profound, and are often manifested in
the following ways:
• Shift from external to internal stream production.
In natural streams, the primary energy source driving
the entire aquatic community is the import and
decomposition of terrestrial detritus, namely leaf litter
and woody debris. However, in many urban streams,
internal benthic algal production becomes a major
energy source supporting the aquatic community,
due to the combined effect of increased light
penetration and nutrients (and the rapid washout of
terrestrial detritus through the stream system). This
shift is often manifested in changes in the-rnix of
species found in the stream community. For ex-
ample, environmental conditions are more favorable
for species that graze algae from rocks (e.g., snails)
than for species that shred leaves or filter coarse-
grained detritus (e.g., caddis flies, stoneflies).
• Reduction in diversity in the stream community.
The cumulative impact of the loss of habitat structure
(pools/riffles), the imbedding of the streambed,
greater flooding frequency, higher water tempera-
tures, extreme turbidity, lower dry-weather flows,
eutrophication, and toxic pollutants conspire to great-
ly reduce the diversity and richness of the urban
stream community. In intensively developed areas,
streams support only a fraction of the fish and mac-
roinvertebrates that exist in natural reference
streams.
• Destruction of freshwater wetlands, riparian buf-
fers, and springs. In the past decade, it has been
necessary to abandon the notion that a stream
ecosystem is defined solely by its channels. It is now
understood that a stream ecosystem extends to in-
clude the extensive freshwater wetlands, floodplains,
riparian buffers, seeps, springs, and ephemeral
channels that are linked to the stream. These areas
contribute, in varying ways, many of the ecological
functions and processes upon which the stream
community depends. Unfortunately, these areas are
frequently destroyed or altered by indiscriminate
clearing and grading during the construction phase
of development.
COMPREHENSIVE URBAN STREAM
PROTECTION STRATEGY
For the past two decades, governments in the
Washington metropolitan area have attempted to deal
with the complex impacts of urban growth on streams by
creating an equally complex series of regulations,
programs, and controls on the urban development
process. The success of these measures in mitigating
the impacts on streams, however, has been less than an-
ticipated. The primary reason has been that individual
measures are developed in response to a single impact
that occurs during a unique phase of the development
cycle. Until recently, little effort has been made to craft a
comprehensive stream protection strategy throughout the
entire development cycle, from development of water-
shed master plans to the ultimate realization of that
development.
What follows is an attempt to outline the elements of an
effective local stream protection strategy that can mini-
mize the impacts of growth on urban streams (see Table
2). It is hoped that this strategy can be further refined
and adjusted to aid local governments in developing ef-
fective programs to maintain stream quality.
The comprehensive stream protection strategy has six
primary components that roughly relate to various stages
of the development cycle. They are:
1. Watershed Master Planning
2. General Development Restrictions
3. Environmental Site-Planning Techniques
4. Sediment and Erosion Control During Construction
5. Urban Stormwater Best Management Practices
6. Community Stream Restoration Programs
Watershed Master Planning
The future quality of an urban stream is fundamentally
determined by the broad land-use decisions made by a
community. It is therefore essential that the impact of
future development on streams be assessed during the
master planning process. The appropriate planning unit
for this assessment is the watershed. The location and
intensity of future development within the watershed
should be carefully examined from the following
perspectives:
• Evaluating stream resources. The first step in the
planning process is to survey the stream resources
within a jurisdiction to obtain basic information on
their use, quality, and value. It is also useful to sur-
vey and delineate floodplains, wetlands, and other
environmentally sensitive areas during this stage.
117
-------
Table 2. Six Elements of a Comprehensive Stream Protection Strategy
1. Watershed Master Planning
Evaluation and Mapping of Stream Resources
Designating Stream Quality Classes
Zoning to Protect Unique and Sensitive Stream Systems
Evaluation of Adequacy of Current
Stream Protection Programs
Regional Stormwater Management Planning
2. Adoption of General Development Restrictions
Variable-width Stream Buffer Requirements
Floodplain Development Restrictions
Steep Slope Restrictions
Nontidal Wetland Protection
Protection of Environmentally Sensitive Areas
Upland and Riparian Tree Cover
Requirements
Waterway Disturbance Permits
Community Open-Space Requirements
3. Environmental Site Planning Techniques
Cluster Development
Transferable Development Rights
Planned Unit Developments
Flexible Road Width Requirements
Fingerprinting of Site Layout
4. Sediment and Erosion Control During Construction
Limit Area and Time of Construction Disturbance
Immediate Vegetative Stabilization of Disturbed Areas
Use of Super-basins for Sediment Control
Frequent Inspection of Erosion and Sediment Controls
Strong Civil Enforcement Authority for Violations
5. Urban Stormwater Best Management Practices
BMP Performance and Maintenance Criteria
First Flush Treatment Requirements
Use of Extended Detention Wet Pond Marsh Systems
Use of Infiltration Systems with Pretreatment
BMP Landscaping, Safety, and Appearance Guidelines
Careful Environmental Review of Urban BMPs
Strong Local BMP Plan Review and Inspection
Public BMP Maintenance Responsibility and Financing
6. Community Stream Restoration Programs
Long-term Stream Trends Monitoring
Watershed Assessment of Restoration Opportunities
Retrofitting of Older Urban BMPs
Construction of New Urban BMPs
Riparian and Upland Reforestation Programs
Instream Fish Habitat Improvements
Urban Wetland Restoration and Creation
Removal of Fish Barriers
Urban Stream Stewardship
• Designating stream quality classes. The next step
Is to rank and prioritize the stream systems within a
locality, based on the stream resource surveys.
Stream use classes are designated to set forth the
appropriate targets for stream quality that will be
maintained during the development process. Unique
areas, such as cold-water trout streams, warmer
water stream fisheries, scenic reaches, and exten-
sive stream/wetland/floodplain complexes should be
targeted for special protection. The upland water-
sheds draining to these unique areas can only be
protected through a combination of low-density
zoning, open space preservation, and stream valley
park acquisition (as well as strict subdivision, sedi-
ment, and Stormwater controls during the low-density
development process). Based on experience in the
Washington area, it is almost impossible to maintain
the quality of these unique systems if upland water-
shed imperviousness exceeds 10 to 15 percent.
* Evaluating the adequacy of stream protection
programs. The watershed master planning stage
provides an excellent opportunity for a community to
critically review the adequacy of its stream protection
measures before development begins. This requires
a thorough analysis of whether the community has
the authority, criteria, review staff, and enforcement
capability to maintain its stream protection programs
in the areas of environmental subdivision review,
construction sediment controls, Stormwater manage-
ment, and stream restoration. If a community is un-
willing to commit the financial and staff resources to
stream-protection programs, watershed master plan-
ning becomes a meaningless exercise.
• Regional Stormwater management planning. An
important component of watershed master planning
is the use of hydrologic and hydraulic simulation
models to project a stream's future hydrologic
regime. Models are a useful (but not sufficient)
means of evaluating the impact of future develop-
ment scenarios on stream quality. The models also
can be used to identify the most effective locations in
the watershed to construct regional Stormwater
118
-------
management facilities, thereby enabling a com-
munity to acquire the sites to construct regional
facilities before development begins.
Development Restrictions
The second phase in a community stream protection
plan is the adoption of a comprehensive and integrated
set of environmental restrictions to govern the develop-
ment process. The greatest level of stream protection is
afforded when a single development ordinance is
adopted by a community and administered by a single
planning authority. In short, the ordinance mandates a
minimum level of environmental site planning during
development and includes, but is not limited to, the fol-
lowing items. Several innovative local regulations from
the Washington metropolitan area are referenced.
• Stream buffer requirement. Development is not al-
lowed within a variable width buffer strip on each
side of ephemeral and perennial stream channels.
The minimum width of the buffer strip is 50 ft for low-
order headwater streams, but expands to as much
as 200 ft in larger streams (4). The stream buffer fur-
ther expands to include floodplains, steep slopes,
wetlands, and open space areas to form a con-
tiguous system, according to prescribed rules.
• Floodplain restrictions. No development is allowed
within the boundaries of the post-development 100-
year floodplain, as designated in the watershed
masterplan. This eliminates the need for future flood
protection measures for these properties, and forms
an essential component of the stream buffer system.
• Steep slope restriction. No clearing and grading is
permitted on slopes in excess of 25 percent (5).
These areas may be tied into the stream buffer sys-
tem, or may exist as isolated open space reserves.
• Nontidal wetland protection. No development is
permitted within nontidal wetland areas and a
perimeter buffer area (25 to 50 ft). In many cases,
the establishment of the stream buffer system will
have already protected these important areas (6).
• Protection of environmentally sensitive areas.
Development is not allowed within unique habitat
areas and plant communities and protective
perimeter buffers, as identified in the watershed
master planning study (7). It is critically important to
provide corridors from upland environmentally sensi-
tive areas to the stream buffer system.
• Upland and riparian tree cover requirements. An
allotted percentage of upland pre-development tree
cover must be maintained after site development (8).
In addition, the riparian tree cover (which should be
entirely contained within the stream buffer system)
must also be retained, or reforested (if no tree cover
currently exists). Where possible, tree-save areas
should be lumped into large blocks tied into the buf-
fer system rather than small and isolated stands.
Numerous studies have confirmed that local wildlife
diversity cannot be maintained in small islands of
trees surrounded by urbanization (9).
• Waterway disturbance permits. Certain forms of
development such as roads and utilities, must, by
their very nature, cross through the stream buffer
system and thereby reduce its effectiveness. Linear
developments must be closely scrutinized to locate
them in the narrowest portions of the buffer system,
and ensure that they do not form barriers to either
fish or riparian migration. In addition, the time "win-
dow" during which the stream and buffer system can
be disturbed by construction activity should be
limited to exclude critical fish spawning seasons.
• Community open-space requirements. Once the
stream buffer system has been delineated, the
developer is still required to preserve an additional
percentage of open space at the site to accom-
modate the residents, future requirements for parks,
playgrounds, ballfields, and other community needs.
If an acceptable amount of commmunity open space
is not reserved for this purpose, it is extremely dif-
ficult to maintain the integrity of the stream buffer in
the future.
Environmental Site Planning at the Site Level
Significant opportunities still remain to protect streams
during the site planning stage. The major objective is to
minimize the total amount of site imperviousness at the
site, and cluster development into centralized areas
where stormwater can be effectively treated. The best
tools at this stage are incentive methods, such as trans-
ferable development rights, cluster zoning, site
"fingerprinting," planned unit development, and flexible
site and road width layout. An excellent review of how
these site-planning methods can be applied to protect
streams is contained in Yaro et al. (10).
Erosion and Sediment Control During Construction
The fourth objective of an effective stream protection
strategy is to reduce the massive pulse of sediment that
inevitably occurs during the construction stage of
development. To accomplish this goal, it is necessary to
both minimize the degree of erosion within the construc-
tion site (erosion control) and to remove sediments borne
in construction site runoff as they leave the site (sedi-
ment control). An excellent design manual of state-of-
the-art erosion and sediment control techniques is the
forthcoming Maryland Standards and Specifications (11).
119
-------
Several strategies have been shown to be very effective
in reducing downstream sediment concentrations during
the construction phase. These include:
• Reduce the area and length of time that a site is
cleared and graded. This reduces the potential for
erosion and can be done by prohibiting clearing and
grading from all postdevelopment buffer zones at the
site, configuring the site plan to retain as much un-
disturbed open space as possible (e.g., cluster
zoning and the environmental site planning techni-
ques noted earlier); and phased construction se-
quencing to limit the amount of disturbed area
exposed at any given time.
• Immediate vegetative stabilization of disturbed
areas. Recent studies in the Washington
metropolitan area indicate that the rapid estab-
lishment of a grass or mulch cover on cleared and
graded areas in construction sites can result in a six-
fold reduction in downstream suspended sediment
levels (12).
• Use of "super" sediment control basins.
Superbasins have wet and dry storage equivalent to
1 in. of sediment per acre of upland watershed area.
If properly designed and maintained, superbasins
can provide reliably high rates of sediment removal
for most of the storms during the year (12). Smaller,
conventionally designed sediment basins and sedi-
ment traps exhibit highly variable sediment removal
rates, and are often overwhelmed during larger
storms.
• Frequent onslte inspection of erosion and sedi-
ment controls. The landscape at a construction site
often changes dramatically from week to week. Con-
sequently, it is critically important that sediment in-
spectors visit the site at least every two weeks to
ensure that the sediment control plan is working and
that all control measures are being properly initiated
and maintained. In particular, inspections should be
concentrated during the latter stages of construction,
when the sediment delivery potential from the site is
at its highest.
• Provide sediment control inspectors with strong
enforcement authority. This authority is needed to
allow inspectors to direct contractors to promptly cor-
rect violations of the sediment control plan in the
field. The best success has been enjoyed in com-
munities where inspectors are empowered to issue
automatic and costly civil fines for sediment control
violations. These strong enforcement tools are criti-
cal in forcing construction contractors to make
erosion and sediment control a part of their daily
operations.
Urban Best Management Practices and
Stormwater Control
The fifth objective of an effective stream protection
strategy is establishing local requirements to install urban
stormwater best management practices (BMPs) to con-
trol postdevelopment stormwater runoff. Urban BMPs try
to replicate the natural, predevelopment hydrologic
regime of a stream by infiltrating, retaining, or detaining
the increased quantity of urban stormwater produced by
development. In addition, urban BMPs may partially
reduce the increased load of pollutants generated from
developed areas.
In recent years, major advances have been made in
urban BMP planning and design. While a thorough dis-
cussion of current urban BMP techniques is outside the
scope of this paper, several reviews are available on the
subject (1,13). In addition, area local governments have
prepared model ordinances to implement effective urban
stormwater programs (14).
Several important points should be kept in mind about
urban BMPs. First, urban BMPs can never fully mitigate
the wide spectrum of hydrologic and water-quality im-
pacts that accompany urbanization. That is, they can
never compensate for poor watershed master planning,
an inadequate stream buffer network, or sloppy site plan-
ning. Second, urban BMPs are a simple technological
solution to a complex problem, and in some cases may
create as many environmental problems as they
eliminate. For example, pond BMPs have been shown to
increase water temperatures and stress cold-water or-
ganisms (3), to be a significant cause of destruction of
freshwater wetlands, and to represent a local interruption
to the stream continuum. Similarly, infiltration BMPs may
increase the risk of ground-water contamination and
have a high rate of failure (13).
Third, urban BMPs are a significant feature of the com-
munity, and can become a locally unwanted land use
(LULU) if careful attention is not paid to concerns such
as landscaping, appearance, safety, stagnation, and
maintenance. Finally, urban BMPs must be maintained if
they are to continue to protect streams in the future.
Communities must recognize, accept, and finance the
maintenance burden of stormwater management.
Stream Restoration Techniques
The final element of an effective stream protection
strategy is a community stream restoration program. The
primary purpose of stream restoration is to enhance the
aquatic habitat and ecological functions of urban streams
that have been lost or degraded during the urbanization
process. In a sense, stream restoration programs are an
attempt to fix the mistakes made during the development
process. The best way to identify these mistakes is to
120
-------
look at the postdevelopment stream from the perspective
of a fish. That is, what are the dominant changes in the
postdevelopment stream that have contributed most to
the decline of a healthy stream community?
• Long-term stream trends monitoring. The first
step is to conduct systematic biological surveys
throughout the stream system every five to ten years
to identify reaches where the aquatic community has
shown the greatest decline. These reaches indicate
that some aspect of the stream protection effort has
failed, and they become the first candidates for
stream restoration.
• Watershed assessment of restoration oppor-
tunities. The second step is to walk the stream and
its upland watershed to determine the dominant im-
pacts that have degraded the aquatic community,
and identify feasible opportunities for restoring
stream habitat or water quality. Stream assessments
are best done on 1 to 10 mi2 sub-watersheds, where
a team of aquatic biologists and engineers can iden-
tify possible restoration opportunities within urban
BMPs, the stream buffer network, and the stream
itself.
• Retrofitting of urban BMPs. The best restoration
opportunities often involve the improvement of exist-
ing urban BMPs. Unfortunately, many urban BMPs
never achieve in the field what was hoped for at the
drafting table. In addition, since urban BMP design is
constantly changing and improving, most older urban
BMPs do not have the pollutant removal capability of
current designs (e.g., the dry stormwater manage-
ment pond).
These older urban BMPs offer great opportunities for
retrofitting at relatively modest investment. Pond
retrofitting has been the primary focus of restoration
efforts in the Washington metropolitan area (15), and
has typically involved converting older dry
stormwater ponds into extended wet pond marsh
systems.
• Construction of additional urban BMPs. In water-
sheds where development has occurred prior to1 the
implementation of a community stream protection
strategy, it is often necessary to retrofit new urban
BMPs into the urban landscape. This is not an easy
task, given the limited amount of space available.
However, surveys have shown that acceptable sites
can be found in a developed watershed, and that
public land agencies will participate in a retrofit
program, particularly if it is demonstrated that the
proposed urban BMPs will improve the, amenity
value on those public lands (5,16). Innovative retrofit
techniques are currently being developed for these
areas, including the peat-sand filter (17), oil grit
separator inlets (18), and extended detention
lake/wetland systems (19).
• Riparian reforestation programs. A common
problem encountered in urban streams is that the
riparian stream buffer zone has been cleared. For-
tunately, the buffer zone can be gradually reforested
within a matter of years, through cooperative com-
munity tree-planting programs at a relatively low
cost. These volunteer programs have become ex-
tremely popular in the Washington area, and are
most effective when local governments arrange the
logistics, assemble the sites, and secure the plant
stock according to a long-term watershed plan.
• Upland reforestation programs. A useful method
for reducing the adverse impact of watershed imper-
viousness on urban streams is to reforest upland
areas. Quite simply, impervious areas are converted
into pervious, forested areas. Again, a community
reforestation program, that utilizes native tree
species and citizen volunteers, is a useful tool.
These programs have the additional benefits of in-
creasing citizen awareness about environmental
stewardship and improving the appearance of the
urban landscape.
• Instream fish habitat improvement. From the
perspective of a fish, the dominant impact associated
with urbanization is probably the degradation of
stream habitat structure, most notably the loss of
pools, riffles, and clean spawning areas. These
habitat features can be re-created within urban
streams by adapting habitat improvement techniques
developed by stream biologists to increase fish
production in more natural stream systems. These
techniques include the use of boulder and log deflec-
tors, log drop structures, brush bundles, willow wat-
tles, boulder placement, and imbricated rip-rap.
These stream restoration techniques are being ap-
plied in several highly degraded stream reaches of
the urbanized Anacostia watershed to test the
hypothesis that an improvement in stream habitat
can improve local fish diversity and abundance in
urban streams (3).
• Urban wetland creation/restoration. Despite recent
regulatory protections, it is likely that most water-
sheds have lost, and will continue to lose, large
areas of freshwater and tidal wetlands to the
development process. This is because urban
stormwater runoff exerts the same series of per-
vasive and adverse impacts to urban wetlands as it
does to urban streams. It is therefore critical to ac-
tively restore and manage urban wetlands, rather
then merely conserve them. Otherwise, the ecologi-
cal value and functions of urban wetlands will
gradually diminish over time. It is equally critical to
create new urban stormwater wetland areas that par-
tially substitute for the lost ecological functions of the
destroyed or degraded wetland system.
121
-------
A series of urban wetland restoration and creation
projects are currently being performed in the
Anacostia River basin (20). At present, the goal of
these programs is to augment the total acreage and
environmental function of urban wetlands at the
scale of the sub-watershed.
* Identification and removal of fish barriers. The
urban stream network should be periodically sur-
veyed to detect possible barriers to anadromous and
resident fish migration. Fish barriers can be detected
through systematic upstream/downstream fish col-
lections at suspected structures during spring runs
(21), or in some cases, by visual surveys. In many
cases, urban fish barriers are created by relatively
low-drop structures that can be rather easily modified
to allow migration. In the Anacostia, simple and low-
cost modifications to two-drop structures are planned
that are expected to open up several miles of spawn-
ing habitat to anadromous fish (22).
• Stream stewardship. The foundation of effective
community stream restoration programs are citizens
who take an active and personal interest in maintain-
ing urban stream quality. Local governments should
recognize these individuals, and encourage them to
adopt a stream and participate in streamwalks, tree-
plantings, and other volunteer programs. These
urban stream stewards can also be of great value in
reporting oil spills, sediment control violations, pollu-
tion problems, and sewer overflows. Most of all,
stewards can act as effective advocates for urban
streams.
SUMMARY
Protecting urban streams from development is obviously
a difficult task. The six-step strategy outlined in this
paper requires an extensive commitment of knowledge,
resources, and staff on the part of a community. To be
successful, a community must be willing to place the
protection of urban streams on a par with economic
growth and the creation of urban infrastructure. If these
conditions can be met, it is possible to mitigate the im-
pact of development, and to maintain a quality stream
system for the future generations that will live and work
within them.
REFERENCES
1, Schueler, Thomas R., 1987. Controlling Urban
Runoff: A Practical Manual for Planning and Design-
ing Urban Best Management Practices, Metropolitan
Washington Council of Governments.
2. Montgomery County Planning Board, 1983.
Guidelines for the Protection of Slopes and Stream
Valleys, Environmental Planning Division, Maryland
National Capital Park and Planning Commission, Sil-
ver Spring, MD.
3. Galli, F. John, 1990. A Study of Thermal Impacts As-
sociated with Urbanization and Stormwater Manage-
ment. Final Report. Prepared for Maryland
Department of the Environment, Dept. of Environ-
mental Programs, Baltimore, MD.
4. Baltimore County Department of Environmental
Protection and Resource Management, 1989.
Regulations for the Protection of Water Quality,
Streams, Wetlands and Floodplains. Towson, MD.
5. Galli, F. John and Lorraine Herson, 1989. Prince
George's County Stormwater Retrofit Inventory,
prepared for the Prince George's County Dept. of
Environmental Resources by the Metropolitan
Washington Council of Governments.
6. Maryland Department of Natural Resources, 1989.
Draft, Non-tidal Wetland Protection Regulations,
Non-Tidal Wetlands Division, Annapolis, MD.
7. Maryland Chesapeake Bay Critical Area Commis-
sion, 1986. Chesapeake Bay Critical Area Criteria for
Local Critical Area Program Development, Maryland
Registered Code (COMAR) Title 14, Subtitle 15. An-
napolis, MD.
8. Prince George's County Department of Environmen-
tal Resources, 1989. Tree Cover Ordinance and
Handbook, County Administration Bldg. Upper
Marlboro, MD.
9. Hench, J.E., K. Van Ness, and R. Gibbs, 1987.
Development of a Natural Resources Plan and
Management Process, p. 29-25, in L.W. Adams and
D.L. Leedy, (eds.). Integrating Man and Nature in the
Metropolitan Environment, Proceedings of a National
Symposium on Urban Wildlife. Chevy Chase, MD.
4-7, November, 1986.
10. Yaro, R.D., R.G. Arendt, H.L. Dodson, and E.A.
Brabec, 1988. Dealing with Change in the Connec-
ticut River Valley: A Design Manual for Conservation
and Development. Lincoln Institute of Land Policy.
11. Maryland Department of the Environment, 1990.
Revised Standards and Specifications for Erosion
and Sediment Control. Sediment and Stormwater
Administration, Baltimore, MD.
122
-------
12. Schueler, Thomas R. and Jonathan Lugbill, 1989.
Performance of Current Sediment Control Measures
at Maryland Construction Sites, prepared for the
Maryland Dept. of Environment by the Metropolitan
Washington Council of Governments. 90 p.
13. Maryland Department of the Environment, 1983.
Standards and Specs for Infiltration Practices. Sedi-
ment and Stormwater Administration, Baltimore, MD.
14. Montgomery County Department of Environmental
Protection, 1985. Stormwater Management Regula-
tions 93-84 (and subsequent amendments), Rock-
ville, MD.
15. Herson, Lorraine, 1989. The State of the Anacostia:
1988 Status Report, Metropolitan Washington Coun-
cil of Governments, Washington, DC.
16. Galli, F. John and Lorraine Herson, 1988.
Montgomery County Stormwater Retrofit Inventory,
prepared for the Montgomery County Dept. of
Environmental Protection by the Metropolitan
Washington Council of Governments.
17. Galli, F. John, 1989. Peat Sand Filters: A proposed
Stormwater management practice for urbanized
areas. Department of Environmental Programs,
Metropolitan Washington Council of Governments.
18. Shepp, 1989.
19. Schueler, Thomas R. and M. Helfrich, 1988. Design
of Extended Detention Wet Pond Systems, in Design
of Urban Runoff Controls. L. Roessner and B. Ur-
bonas (eds.), American Society of Civil Engineers.
20. Kumble, Peter, 1990. The State of the Anacostia:
1989 Status Report, Metropolitan Washington Coun-
cil of Governments.
21. Cummins, James, 1989. Maryland Anacostia Basin
Fisheries Study. Phase II. Interstate Commission on
the Potomac River Basin, Rockville, MD.
22. Cummins, James, 1988. Maryland Anacostia Basin
Fisheries Study. Phase I. Interstate Commission on
the Potomac River Basin, Rockville, MD.
123
-------
-------
SECTION EIGHT
PLANNING AND IMPLEMENTING AN EFFECTIVE
INFORMA TION/EDUCA TION PROGRAM
-------
EFFECTIVE INFORMATION AND EDUCATION PROGRAMMING—
A RURAL PERSPECTIVE
Bud Stolzenburg
University of Nebraska
Lincoln, Nebraska
INTRODUCTION
An effective information and education (I&E) program is
a key component in watershed projects concerned with
nonpoint source pollution. Whether the project is re-
search or demonstration oriented, information is either
available or being generated, and must be communi-
cated to the appropriate audiences. This communication
of information is the education component of I&E. If
education is to occur then there must be 1) a selection of
appropriate information, 2) suitable methods for com-
municating that information, and 3) a response from the
audience.
This paper provides assistance in planning and im-
plementing an effective I&E program, particularly in a
rural watershed program. It is generic in nature with the
intent of being suitable in a variety of situations. Any I&E
program will, of course, need to be adapted and fitted to
the particular location, need, and audience.
PREPROJECT PLANNING
The I&E program needs to be included in the early, plan-
ning stages of the watershed project. The following items
should be considered in preproject planning:
1. Historical Resources. We have learned a great
deal from watershed projects already completed.
Search out reports and materials that have been
written about other projects. Much information has
been generated and many lessons learned already.
Find and contact people who have worked with these
projects. There is no need to re-invent the wheel.
2. Budget Considerations. I&E should be a budget
item. You should include staff salary and support, as
well as program development and support.
3. Staff/Agency. Staff and/or staff time needs to be al-
lotted for I&E. This can be done by assigning primary
responsibility to a particular agency or portions of the
responsibility to different agencies. In a total program
all participants will have I&E roles, but overall coor-
dination should be assigned to one agency.
4. Program Responsibility. The overall responsibility
for I&E should be clearly defined and assigned, just
as technical assistance and fiscal management.
5. Plan of Action/Calendar/Time Line. Develop a
chronological plan of action. Your plan can have
flexibility to respond to mitigating circumstances, but
it needs to be outlined and have a logical sequence.
6. Local/State/Federal Coordination. It is important to
establish a communication system that shares infor-
mation at all levels of the project. An effective team
at all levels is needed to assess the project and
respond to needs and concerns.
PROJECT ACTIVITIES
As you make planning decisions, both preproject and on-
going, you need to include those activities that will con-
tribute to the success of the project. The following
discussion suggests some activities and ideas you may
want to consider.
A good local leadership group can be a real asset to your
project. This group may include agency representatives,
appropriate local organizations, lending institutions,
producers, related businesses, and government officials.
The membership of the group will be determined by the
project and the local environment. This is the group of
people that needs to know what is going on with the
project. They help to identify needs, propose and evaluate
solutions, and provide "local ownership" of the project.
Keep the public informed through various media that are
available to you—newspapers, newsletters, radio,
television, etc. A regular newsletter to those producers
and people associated with the project is also an effec-
tive information tool. Community activities such as county
fairs, special water festivals, and agriculture days provide
another opportunity to profile your activities. Videotapes
have been used to highlight project efforts. Youth
programs such as Future Farmers of America, Boy and
Girl Scouts, and 4-H are other ways to increase visibility.
One of the keys to success is one-on-one contact with
the producer. This one-on-one relationship should be
126
-------
one of respect and confidence. This process takes time
and a lot of effort, but it produces results.
As you work with producers you need training and infor-
mation meetings to assist them in incorporating new
and/or different ideas and practices into their manage-
ment scheme. Informal "coffee-cup" sessions with small
groups have worked well and provide good opportunities
for discussion.
Demonstrations are one of the most important keys to
success. They can be set up and organized in a variety
of ways. The important point is that they take an idea
from paper to practice. They can be the focus for field
trips and field days. They provide excellent material for
the news media. Demonstrations don't just tell how a
practice works, they show how it works. The learning
process is enhanced with visual and sensory com-
ponents.
Also, be aware of the "expansion effect." An idea or
practice that is developed and accepted in a project has
the potential to spread to the surrounding area. If a
problem is recognized as legitimate and valid, others will
work towards the solution.
Monitoring and evaluation are important parts of any
project. They can be incorporated into the I&E program
or they can be handled independently. But they need to
be included from the inception of the project.
Finally, the I&E component should continue for the dura-
tion of the project, from preproject planning to final
evaluation. It is needed early on to publicize and explain,
it is needed throughout to support and nurture, and it is
needed at the conclusion to summarize, evaluate, and
share the results.
127
-------
THE DEVELOPMENT AND IMPLEMENTATION OF AN URBAN NONPOINT
POLLUTION EDUCA TION/INFORMA TION PROGRAM
Richard Badics
Huron River Pollution Abatement Project
Washtenaw County Health Bureau
Ann Arbor, Michigan
OVERVIEW OF THE HURON RIVER POLLUTION
ABATEMENT PROJECT
The Huron River Pollution Abatement Project (HRPAP)
was formed in 1986 by the Washtenaw County Drain
Board. The project was modeled after successful pilot
projects in the cities of Ann Arbor and Ypsilanti. These
innovative pilot projects discovered that 17 percent of the
660 buildings dye-tested from 1982 through 1986 had il-
licit storm drain connections.
The HRPAP was given the responsibility of locating and
eliminating sources of nonpoint pollution to the Huron
River. The methodology includes sampling the river and
storm drain outfalls and laterals, surveying and dye-test-
ing buildings to locate and eliminate improper discharges
to the storm drains, responding to pollution complaints
and emergency release incidents, and education.
The funding is entirely generated through annual assess-
ments on properties within the district. The total for the 6
year project is over $1.7 million including investments.
The assessments are made through the Michigan Drain
Code, P.A. 40 of 1956, as amended, and range from an
annual fee of $4.50 per year for homes to $200.00 per
year for large commercial parcels.
The HRPAP district is 32,633 acres of the urbanized core
of Washtenaw County located in southeast Michigan. It
includes the cities of Ann Arbor and Ypsilanti as well as
portions of Ann Arbor, Pittsfield, Scio, Superior, and Yp-
silanti Townships. To date, 15 percent of the over 2,200
buildings dye-tested have had improper storm drain con-
nections.
The HRPAP is considered a national model for
demonstrating that local governments can abate non-
point pollution. The HRPAP was cited in the Federal
Registry in December 1988 and November 1990, used
as a model program (i.e., Wayne County, Michigan), and
the project was a part of Michigan's Urban Nonpoint Pol-
lution Committee. The HRPAP won the Michigan State
Health Department's Director's Award in 1988, the 1990
Michigan Department of Natural Resources Environmen-
tal Excellence Award, and received a Letter of Recogni-
tion from the United States Department of Health,
Education, and Welfare in 1991.
PLANNING FOR NONPOINT POLLUTION
EDUCATION
The development and implementation of a nonpoint pol-
lution education and information program is critical to
having a successful urban nonpoint pollution project. The
reason is twofold. First, public awareness of urban non-
point pollution is low. The public is inundated daily with a
barrage of potential risks by the press ranging from the
threat of war, crime, and youth violence to recession,
drugs, and the threat of AIDS. In the environmental field,
the news is of radon, toxic waste, recycling, air pollution,
and contaminated ground water—not urban nonpoint pol-
lution. Therefore, the publicizing of urban nonpoint pollu-
tion to the community is an important first step in gaining
public support.
Second, the education and information program is impor-
tant to having a successful urban nonpoint project be-
cause most of the urban nonpoint pollution can be
directly attributed to people. This is true even of the col-
lection systems that were designed mainly for water
quantity not quality. However, newer and customary
sources of urban nonpoint contamination such as air-
borne contaminants and erosion need to be included in
the public's awareness. It is the actions of people at both
home and work that affect the type and amount of non-
point pollution from their community. Simple changes in
individual activities can have dramatic results. A study by
the Michigan Department of Natural Resources in 1989
found that more oil is illegally released into the environ-
ment in Michigan annually than was released in the Val-
dez, Alaska, incident. Getting the community to buy into
the idea that they are a "major part" of the problem is an
important first step in gathering their support and
cooperation.
The first step in developing a successful urban nonpoint
education and information program is to define your tar-
get audience. A specific program tailored for each
audience is required to address their particular wants
128
-------
and needs. An education program that is too general will
not provide this and will not be as successful. The one
goal that must always be remembered is to provide un-
derstandable and useful information. The better you un-
derstand your target audience (education, background,
industry type) the better your education program will be.
The second step in developing a successful urban non-
point education and information program is to define the
types of media to use in your programs. A multi-media
approach will increase the chances of reaching all com-
munity segments. Different approaches work more effec-
tively with various groups. For example, pamphlets will
not reach the segment of the community that cannot
read. Some of the more beneficial methods to use in-
clude:
1. Fact sheets
2. Pamphlets
3. Radio/television
4. Newspaper/magazines
5. Displays/models/posters
6. Group presentations/one-on-one community events
The education and information component must be a key
element in any urban nonpoint pollution program. To be
successful the community must "buy into" their contribu-
tion to nonpoint pollution and their ability to abate it. The
education and information program must be innovative
and well conceived to reach all segments of the com-
munity. A nonpoint education and information program
designed for a homeowner will not necessarily address
the needs and problems of industry. Each program
should be tailored to best reach its audience.
HRPAP EDUCATION AND INFORMATION
PROGRAM
Overview
The education and information program during the earlier
pilot water quality projects in the cities of Ann Arbor and
Ypsilanti from 1982 through 1986 evolved as needs
arose. The first need was the need for funds to conduct
the project. This required the education of the two cities
and the county as to the benefits of starting and later
continuing a local nonpoint pollution program. Since the
survey and dye-test program was voluntary, each in-
dividual or organization contacted needed to be edu-
cated on nonpoint pollution in order for our staff to gain
entrance.
When the HRPAP was formed, education was a key ele-
ment in the methodology. The education program was
designed after reviewing the pilot water quality programs
and analyzing the community. Some of the items that
were noted during this phase included that the com-
munity was mainly urban, well educated, generally sup-
portive of environmental issues, had many industrial
shops, and had numerous organized and influential civic
and professional groups.
Based on this analysis, the education and information
program was developed with three main components.
The first was the business and industry component, the
second was the community and civic groups component,
and the third was the classroom or school component.
HRPAP BUSINESS AND INDUSTRY
EDUCATION AND INFORMATION PROGRAM
The HRPAP enters facilities without regulatory powers.
The business and industry education and information
program is fundamental to gaining entrance for conduct-
ing the HRPAP survey and dye-test program. The educa-
tion and information program is designed to be a service
the HRPAP provides to the business, industry, and in-
stitutional community as well. The institutional community
includes local government facilities such as utility depart-
ment yards and the local colleges and universities.
When first entering facilities, owners and managers are
interviewed. In addition to providing information on the
HRPAP, staff provide information and contacts that may
assist their particular situation. An example would be ex-
plaining to a company the need for registering their un-
derground storage tanks or pointing out that poor
chemical storage practices may lead to future expensive
cleanup costs. Many facilities have reduced their chemi-
cal inventories after the HRPAP education and informa-
tion program, thereby saving thousands of dollars.
When a need is discovered during the interview process,
the HRPAP staff provide assistance. For example, a
number of facilities encountered had oil separators.
Many of the facility operators had no knowledge concern-
ing oil separator maintenance. The facility operators that
tried to maintain their oil separators could not find a
licensed waste hauler that would service them. The
HRPAP staff developed a short letter describing the
maintenance procedures for oil separators and a list of
licensed waste haulers operating in the area that would
service them. This information was distributed to all
facilities with oil separators.
HRPAP COMMUNITY AND CIVIC GROUP
EDUCATION AND INFORMATION PROGRAM
The HRPAP began in 1987 with four educational presen-
tations to the community. In 1989, the staff conducted 40
presentations for an increase of 1,000 percent. The first
groups targeted for education and information programs
were local civic groups. These programs allowed contact
with business owners and managers who were later in-
spected by the HRPAP and served as a forum for discus-
sions of common environmental issues faced in the
community. The HRPAP staff provided information on
nonpoint pollution abatement, new environmental regula-
129
-------
lions, problems discovered in the community based on
facility type, and distributed informational packets
generated by the HRPAP staff.
Informational posters, pamphlets, and two pollution dis-
play models were developed by HRPAP staff for use at
community gatherings. The posters and the models at-
tract people for one-on-one discussions to increase their
awareness of the many types of pollution and more im-
portantly to provide them with sensible practices they can
use at home and at work to abate nonpoint pollution.
The HRPAP uses the media for educating the com-
munity. The HRPAP staff early on developed a working
relationship with the local press. Feature articles con-
cerning the HRPAP were published including follow-up
stories. Press releases were made when significant
events occurred, such as winning an award or securing a
federal grant to do a study. The HRPAP staff also have
been interviewed on local radio talk shows and have ap-
peared on public access television. The project staff
have had articles published in professional magazines.
HRPAP SCHOOL EDUCATION AND
INFORMATION PROGRAM
The HRPAP school education and information program
is one of the most important and exciting programs. The
HRPAP made its first school education presentation to a
third grade class in 1988. Word of the presentation
spread to other teachers in the school system. This lead
to more presentations and the discovery of the need to
have a devised lesson plan for school education
programs.
HRPAP student interns with an education background
began to formulate lesson plans for various grade levels
on nonpoint pollution and issues such as the water cycle.
HRPAP staff later attended workshops for school
teachers to better define and target the programs.
Announcements are now annually sent out to the schools
within the HRPAP district. In October 1990, over 10
classroom presentations were made. The grade levels
now involved with the program range from third grade
through the twelfth grade.
The information gathered from teacher's surveys state
that the education program is particularly well received
by the lower elementary grades. These students discuss
the program throughout the year. One reason for this
success could be the use of hands-on models. One
model is electronic and is entitled "Pathways of Pollu-
tion." This model lights up various pollution pathways
when the appropriate button is pushed. The second
model is a transparent representation of a town showing
the sanitary and storm sewer systems. The students can
place a dye into catch basins, floor drains, and toilets
and observe the route the water takes to either the
stream or the treatment plant. The model has both
proper and improper examples.
Educational presentations have also been made at the
local universities for both the undergraduate and
graduate levels. These presentations include a more
technical presentation on nonpoint pollution and other
environmental programs. This overview allowed the stu-
dents to see a practical application of classroom instruc-
tion. A large number of the student interns used on this
project were hired after these college programs.
SUMMARY
The majority of urban nonpoint pollution can be directly
attributed to the activities of people. Most people are not
aware of the impact their routine activities at home and
work have on water quality. For these reasons, education
and information must be a major component in any urban
nonpoint pollution program.
Before developing an education and information
program, an analysis of target groups within the com-
munity must be made. Only after assessing the impact
and needs of these groups can effective programs be
designed.
When implementing an urban nonpoint pollution educa-
tion and information program, a multi-media approach
will increase the chances of reaching all segments of the
community. To be effective with the general community,
the program needs to educate and inform the public of
practical things they can do. For business and industry,
tailor the program to their specific situation and relate
how these changes can save money now or in the future.
School programs have greater impact when a hands-on
segment is included.
The community must be provided with information that
will sustain their awareness and respect for the inter-
dependence of all elements in the ecosystem. This will
lead to a sense of responsibility and commitment to en-
vironmentally appropriate actions over the long term.
130
-------
EXPERIENCES FROM PUGET SOUND
Nancy Richardson Hansen
City of Bellevue Storm and Surface Water Utility
Bellevue, Washington
INTRODUCTION
Those of us who work in the arena of nonpoint pollution
know that it is a topic unfamiliar to the general public. We
also know that, more than any other type of water pollu-
tion, effective nonpoint pollution control requires an in-
formed and supportive citizenry. Solutions involve
decisions and actions on behalf of everyone; they are not
easily relegated to agencies or technology.
This paper is drawn primarily from the experience of
several local governments working to educate and in-
volve a variety of audiences in nonpoint pollution control.
These governments were involved in developing water-
shed action plans in accordance with the nonpoint pollu-
tion program in the Puget Sound Water Quality
Management Plan*.
Two important points about education and public involve-
ment should be made at the outset. First, education and
public involvement are too often viewed as luxuries that
can only be carried out if staff time and budget permit, or
they are conducted to merely meet the requirements of
law. Rather than an adjunct to the planning process,
education and public involvement are essential com-
ponents and often key to the success of the plan.
Second, education and public involvement should not
just be used during the nonpoint planning process. They
are also important implementation tools. A well-planned
education program may be a far better approach for
reaching a particular audience than regulation.
PLANNING AN EFFECTIVE
INFORMATION/EDUCATION PROGRAM
There are three important questions to answer in plan-
ning an effective information/education (I/E) program:
• Who is your audience?
• What is your message?
• How will you communicate it?
These three questions should be asked for each
audience. An effective I/E program has several different
audiences, and information needs to be tailored to each
one.
Audience: Who Needs to Be Involved?
A common mistake in designing an I/E program is to as-
sume that there is only one audience. To be effective, an
education program needs to identify and target a number
of different audiences. For example, a member of an ad-
visory committee will need a different level of information
than a member of the general public attending a meeting.
Among the important audiences to consider are:
• Your "friends"—people who are supportive of the
nonpoint planning effort. Local environmentalists,
concerned citizens, Indian tribes, groups that stand
to benefit (e.g., oyster growers). These audiences
are basically on board, and their involvement needs
to be used in support of the planning process.
• "Affected parties"—individuals or groups who may
be contributing to nonpoint problems but who also
have a potentially important role in solutions. Com-
mon examples include farmers, developers, boaters,
and foresters. They usually need to be convinced
that there is a problem before they can be educated
as to their role in solutions.
• Local elected officials—key decision makers and
opinion leaders who have an influential role in allow-
ing a watershed planning effort to be accepted and
implemented. They are usually most interested in the
political and financial implications of the nonpoint
planning process.
"The Puget Sound plan was prepared by the Puget Sound Water Quality Authority, a state agency established in 1985 and directed
to develop a comprehensive water-quality management plan for Puget Sound. The Authority has jurisdiction in the 12-county Puget
Sound area. The Puget Sound plan contained a major new initiative addressing nonpoint pollution. Local governments were asked
to develop plans for controlling nonpoint pollution in priority watersheds. The plans are developed by a committee representative of
the local governments and other interests in the watershed.
131
-------
• Government agencies—officials and technical staff
from a wide range of local, state, and federal agen-
cies. Agencies can provide both technical and politi-
cal support to nonpoint planning efforts. Some
agencies, such as the transportation department or
forest management agency, may be contributors to
nonpoint pollution. Important agencies to consider in-
clude city and county government (such as planning,
public works, or health), special purpose districts
(such as drainage, ports, or sewer), state agencies
(such as fisheries, transportation, recreation, or
agriculture), and federal agencies (such as the U.S.
Soil Conservation Service, Forest Service, or EPA).
• The "general public"—that amorphous group that is
typically the target of any public involvement effort.
Each of these audiences is reached through different
channels. For example, local officials are usually best ap-
proached directly. Reaching the general public, however,
involves working through the media, public meetings, or
other large-scale formats. Groups of friends and affected
parties are often easily reached by working through or-
ganized groups and associations. However, it is also im-
portant to cultivate contacts with key individual members
of these groups.
Each nonpoint planning effort will have its own mix of
audiences, depending on the location and the nonpoint
issues of concern. The important question to ask when
identifying audiences as part of any nonpoint planning ef-
fort is, Who needs to be involved in order for this effort to
be effective? As many planners know, leaving an impor-
tant constituency out of the planning process can often
result in a prolonged and wasted effort.
Message: What Do They Need to Know?
As indicated by the variety of audiences listed above,
each audience may require a different message. Ex-
perience in Puget Sound shows that there are two
general types of information that people need to know.
First, they need to understand some basic concepts
about nonpoint pollution: What is it? How does it affect
me? What can be done about it? Second, they need to
understand the planning process: What am I being asked
to do? What is Section 319? How will the process work?
Concepts
For each audience, it is important to develop a clear un-
derstanding of nonpoint pollution and related concepts.
Some key concepts include:
• Watershed—This concept provides a geographic
framework 'for dealing with nonpoint pollution.
Everyone lives in a watershed. An understanding of
the watershed concept can also help explain other
related concepts, such as wetlands and ground water,
and places in the watershed where water is stored.
• Water cycle—This concept illustrates the relationship
between precipitation, surface water, groundwater,
and vegetation in the watershed. It explains, for ex-
ample, why underground piping of storm water tends
to remove water from the system, while use of
natural features for storm water control keeps water
in the watershed.
• Beneficial use—This concept is commonly used
when dealing with water-quality protection. In a
watershed, it usually relates to a water-quality goal to
be achieved or a level of water quality to be
protected. Uses that are considered beneficial in-
clude: fish consumption, shellfish harvesting, aquatic
life protection, swimming, provision of drinking water,
and irrigation.
• Source control—Efforts to curb nonpoint pollution
by various sectors such as agriculture or forestry are
often referred to in terms of source control. However,
this term tends to compartmentalize and target cer-
tain sectors as polluters. An alternative approach
would be to think in terms of controlling particular
pollutants ("bacteria control" or "sediment control")
targeting all the potential sources of a pollutant in a
watershed.
• Cumulative effects—This concept helps link all of
the previous concepts together. The concept of
cumulative effects points to the multiple causes of
nonpoint pollution within a watershed. It keeps
people from finger-pointing and promotes a sense of
shared responsibility for nonpoint problems and solu-
tions in the watershed.
Process
While concepts relating to nonpoint pollution are impor-
tant, people also need to understand the planning
process they're being asked to participate in. They need
to understand the sequence and timing of the planning
steps, as well as their individual role. It should also be
clear to participants what the expected outcome is.
Failure to adequately educate about the process can
lead to confusion and frustration on behalf of par-
ticipants.
Peer Education
Peer education—using members of a group to educate
others in the group—is an extremely valuable tool in
communicating information to difficult audiences. Infor-
mation about a planning process or changes that may
need to be made as the result of a watershed plan are
much better received from a fellow farmer or a realtor
than from a bureaucrat. Whenever possible, seek out
opportunities to use members of various audience
groups to deliver information.
132
-------
Format: How Should We Tell Them?
Given the endless combination of audiences and mes-
sages, there are also a variety of formats for conveying
information. The choice of format is closely linked to the
audience. Some commonly used formats include:
• Special events—Events, such as an open house or
information fair, work well as a "kickoff" to watershed
planning activities. Scheduled early in the process,
these activities can set a positive tone for the rest of
the process.
• Watershed tours or field trips—An outing is one of
the most effective means of providing an under-
standing of nonpoint pollution and watersheds. Field
trips are most useful for people who will have a sig-
nificant role in the watershed planning process. A
watershed tour is ideal for citizens, local elected offi-
cials, or other individuals called upon to help develop
a watershed plan. A smoothly run field trip requires
careful planning: routes should be driven prior to
each trip; knowledgeable speakers should be
recruited to describe each stop; maps and handouts
should be available.
• Written materials—Written materials such as
newsletters and brochures work best with larger,
more general audiences. Flyers and fact sheets may
be most useful in giving a quick overview of a project
or in announcing a meeting, while a newsletter offers
a means of periodically keeping people up to date on
the project. The effectiveness of printed materials will
be enhanced if they are planned in advance as a
coordinated package, with a similar graphic style. It
is also important to develop a mailing list for the
various audiences interested in the planning
process.
• Meetings and workshops—Unlike printed
materials, meetings provide unique opportunities for
two-way communication. Remember that what can
be learned from the public is often more important
than what you originally planned to tell them. Meet-
ings can serve as forums where issues can be
debated and discussed, while workshops allow
citizens and committee members to dig more deeply
into the issues. With either activity, success depends
on adequate preparation.
• Speakers—Guest speakers can be used effectively
to provide credibility and/or depth on certain topics.
Speakers who avoid technical jargon and who relate
their subject matter to the interests of the audience
are most effective. It can also be extremely fruitful to
request to be a guest speaker at an event involving
affected parties. For example, ask to speak at the
local farm bureau, association of realtors meeting, or
local chamber of commerce. This serves to get you
on their turf and provides an opportunity for a frank
discussion of issues.
• Media—Radio, newspapers, and television can all
be used to help educate the public about nonpoint
pollution, garner public support, and publicize meet-
ings and events. Personal contacts with reporters
and editors yield the best results.
In selecting formats, it is important to understand that
people have different styles of learning. Some people
can easily process written information; others may need
to see or experience something directly before they un-
derstand it. Because of the differences in the way people
learn, the educational activities and methods used
should be varied. A mix of techniques that reach a
variety of audiences, and that allow for different learning
styles, will have the greatest chance of being effective.
LESSONS FROM PUGET SOUND
A number of important lessons can be passed on to
other regions based on watershed planning experiences
in Puget Sound:
• View education and public involvement as neces-
sities, not luxuries. Education and public involve-
ment are needed to identify and involve all parties
that have a role in cleaning up nonpoint pollution. If
key audiences are left out of the process, they may
become involved later as vocal opponents.
• Make an up-front commitment of both time and
money. The time needed to adequately educate par-
ticipants in watershed planning concepts and
process should not be underestimated. Both budget
and staff time should be set aside to do the neces-
sary education work, especially at the start of the
planning process.
• Specifically tailor the message and format to
each audience. Target information on concepts and
process to each different audience. Use a variety of
educational techniques. Take advantage of peer
education wherever possible.
• Learn to anticipate and recognize common reac-
tions. People just learning about nonpoint pollution
(especially targeted groups) will exhibit some com-
mon reactions. They are likely to deny that a real
problem exists ("Prove it!"), point fingers at some
other source ("It's the sewage treatment plant!"), or
both. These reactions should be anticipated and
steps taken to diffuse them; otherwise, anger and
confusion may result.
• Use education as a solution to nonpoint
problems. Build education into the implementation
strategy of each nonpoint plan. Recognize and use
the important potential of education as a tool for solv-
ing nonpoint problems.
133
-------
REFERENCES
1. Hansen, N. R., C. Dyckman, and S. Kelly, 1990. Ef-
fective use of public involvement, education, and
decision making techniques in nonpoint pollution
control. In: Making Nonpoint Pollution Control
Programs Work; Proceedings of a National
Conference. National Association of Conservation
Districts.
2. Puget Sound Water Quality Authority, 1989. Manag-
ing Nonpoint Pollution: An Action Plan Handbook for
Puget Sound Watersheds. Seattle, WA.
134
-------
SECTION NINE
EVALUATING THE NFS WATERSHED IMPLEMENTATION PROJECT
-------
SURFACE WATER TRENDS AND LAND-USE TREATMENT
Donald W. Meals
School of Natural Resources
University of Vermont
Burlington, Vermont
INTRODUCTION
Most NPS implementation programs are designed to im-
plement changes in land-use treatment as quickly and
efficiently as possible. Monitoring to assess water quality
response is usually organized around this purpose. Lack-
ing the control of ideal experimental design, watershed-
level NPS monitoring programs are typically faced with
incremental implementation of BMPs, uneven spatial dis-
tribution of treatments, unknown operation and main-
tenance of practices, and uncooperative weather. From
the point of view of monitoring personnel, land treatment
often seems to occur too quickly or too slowly, at the
wrong place or at the wrong time, and during a prolonged
drought or an exceptional flood.
As a result, evaluation of NPS watershed projects can
rarely be treated as a simple short-term before/after or
above/below exercise. Rather, the approach must be to
evaluate long-term trends, gradual or subtle shifts in
water quality that may occur in response to the land
treatment program. Not only must such trends be
detected but they must also be linked with the land treat-
ments applied. All this must, of course, be done in the
context of the tremendous noise added by hydrologic
variability, seasonal cycles, and human activities.
This paper will outline some statistical considerations im-
portant in evaluating NPS monitoring data, present ex-
amples of water quality trends in one NPS
implementation project, and discuss several issues con-
cerning the analysis of land use/water quality relation-
ships.
STATISTICAL CONSIDERATIONS
Trend analysis is easier if it has been considered in the
monitoring design. Continuous regular data collection,
consistent monitoring procedures, and careful data
management are essential elements. If sources of
variability such as seasonality, flow dependence, and
pre-existing trends were evaluated at the start, then their
effects can be minimized or removed by appropriate
statistical techniques (1).
Trend detection in water quality data requires rigorous
statistical analysis; there is ample discussion of specific
techniques in the literature (1, 2, 3, 4, 5, 6, 7, 8, 9). Some
general guidelines can be applied.
The basic statistical behavior of the data set must be as-
sessed. Three assumptions are of concern—inde-
pendence of observations, constant variance, and
normal distribution—and water quality data generally vio-
late these. Violation of independence, often by
seasonality or autocorrelation, is thought to be the most
serious problem (5), potentially resulting in finding a
trend where none exists or failing to document a trend
that does exist.
The statistical structure of the data will dictate the selec-
tion of trend analysis technique. Nonparametric tests for
trend, for example, have been developed that account for
seasonality and lack of independence. Adjustments can
be made to the data. For parametric statistics, for ex-
ample, log transformation often normalizes distribution.
Time series data can sometimes be aggregated to
reduce autocorrelation and stabilize variance.
Control for the effects of climatic and hydrologic
variability on concentration, stream discharge, and load
is critically important. Year to year differences in rainfall
and runoff, for example, will obscure real changes in
NPS phosphorus export. Some specific statistical techni-
ques like analysis of covariance or nonparametric tests
such as the seasonal Kendall can be helpful in dealing
with variability.
One particularly effective approach is paired regression,
an adaptation of the paired watershed technique (10). A
regression relationship between a treated watershed and
a control (untreated) watershed is developed for a
specific parameter before land treatment (calibration).
After treatment, a similar regression relationship is
derived, and significant difference in slope and/or inter-
cept between the calibration and treatment regressions
indicate treatment effects. This technique accounts for
meteorologic and hydrologic variability by including the
variability from the control watershed that receives the
same background inputs as the treated watershed, but
no treatment. The effectiveness of this technique often
136
-------
justifies the effort required to monitor an untreated con-
trol watershed.
Finally, a number of different techniques should be used;
no single approach or test should be relied on exclusive-
ly. Some techniques may be exploratory; some must
control for hydrologic variability. In the LaPlatte River
Watershed Project, for example (11), the following tech-
niques were employed for trend analysis:
• Time regression, testing the slope of a regression
line of water quality data versus time
• Frequency distribution, comparing distributions
between years or monitoring periods, and evaluating
probability of exceedance of water quality standards
• t-test, ANOVA, comparing means between years or
monitoring periods
• Flow/concentration regression, evaluating chan-
ges in flow/water quality relationships following land
treatment
• Analysis of covariance, comparing groups after ad-
justment forcovariate effects (e.g., flow)
• Paired regression
• Nonparametric techniques, including seasonal
Kendall, Mann-Whitney, and Spearman/Lettenmaier
EXAMPLES OF WATER QUALITY TRENDS
Some trends are obvious, even before confirmation by
statistical analysis. For example, Figure 1 shows mean
fecal streptococcus (FS) bacteria counts from 10 years of
NPS monitoring at 4 stations in the LaPlatte River Water-
shed in Vermont (11); FS counts clearly declined bet-
ween 1980 and 1989. This decline was confirmed by all
statistical analyses, pointing to a 50 to 75 percent decline
in mean annual FS over the monitoring period.
Total phosphorus (TP) export, however, did not present
as clear a picture (Figure 2). Pronounced year to year
variations in precipitation and streamflow obscured, any
FECAL STREP BACTERIA
1980 - 1989
LaPlatte River Watershed
MEAN ANNUAL FS COUNT (#7100 ml)
700
0
1980
1981 1982 1983 1984 1985
YEAR
1986 1987 1988 1989
WS 1
WS 2
WS 3
WS 4
Figure 1. Trends in annual mean fecal strptococcus bacteria counts in four monitored subwatersheds, LaPlatte River
Watershed, Vermont. (11)
137
-------
TOTAL PHOSPHORUS EXPORT
WS 4 1980-1989
LaPlatte River Watershed
WEEKLY TP EXPORT (Ibs)
100s
1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990
0.01 i
0.001
TP
Figure 2. Weekly total phosphorus export from WS 4,1980-1989, LaPlatte River Watershed, Vermont. (11)
obvious trends. However, paired regression did reveal a
significant trend. The results of this analysis are shown in
Figure 3, with only the regression lines shown for clarity.
The pre-best management practice (BMP) period
(calibration) included 3 years of data collected before
land treatment was complete; post-BMP data were col-
lected over 5 years following full implementation of land
treatment. In Figure 3, Watershed 3 was the control
watershed and Watershed 4 was the treatment water-
shed.
The post-BMP regression line in Figure 4 is shifted sig-
nificantly downward from the pre-BMP line, suggesting a
significant decrease in TP export from the treated water-
shed. Under pre-BMP conditions, for example, a 5
IbA/veek TP export level from the control was associated
with an export of 8.25 Ib/week from Watershed 4. After
animal waste management was fully implemented in
Watershed 4, however, the same 5 Ib/week export level
from the control watershed saw a corresponding export
of 6 Ib/week from Watershed 4. Thus, paired regression
analysis was extremely valuable in evaluating the effects
of treatment despite high variability in phosphorus export.
Not all the parameters monitored in the LaPlatte River
Watershed Project showed such a response to land
treatment. Some of the parameters often monitored as
standard procedures—temperature, pH, and DO—did
not change significantly over 10 years of monitoring. Fur-
thermore, trends among some fractions—volatile
suspended solids, dissolved P, and ammonia N—did not
behave differently from trends in total suspended solids,
total phosphorus, or total Kjeldahl N, nor did the propor-
tions of these fractions change significantly during the
project. Thus, at least in hindsight, these analyses added
little to the overall conclusions of monitoring. It is, of
course, difficult to know this at the start, but it is worth
considering.
LAND-USE/WATER QUALITY RELATIONSHIPS
Linking observed changes in water quality to changes in
land use/treatment should be part of project evaluation.
Ideally, if land-use and management activity monitoring
was part of the monitoring design, detailed data will be
available. The lead land treatment implementation agen-
cies (e.g., USDA-SCS), may also be able to supply, data
138
-------
WS 4 TP LOAD
Pre-BMP vs Post-BMP
WS 4 TP LOAD (Ib/wk)
100 s
0.01
'• •'•0.05
0.5 5
WS 3 TP LOAD (Ib/wk)
Pre-BMP
Post-BMP
Figure 3. Paired regression lines of pre-BMP and post-BMP total phoisphorus loads, WS 4 versus WS 3 (control), La-
Platte River Watershed, Vermont. (11)
on land treatment and agricultural activities from par-
ticipating farms.
A Geographic Information System (GIS) is an effective
way to store and manipulate such spatially referenced
data. In the LaPlatte River Watershed Project, for ex-
ample, ARC/INFO was used to manage and display farm
management and activity data collected directly from
farmers and from USDA-SCS records. A result of this
land-use monitoring program is given in Figure 4, specifi-
cally identifying what land in the watershed received
manure and from what source in 1989. This manure data
set can be easily combined and compared with other GIS
coverages, such as soils, topography, or proximity to sur-
face waters.
Two key points must be emphasized in the effort to relate
land use and water quality. The fist is the confounding in-
fluence of weather and season on agricultural (or other
NPS) activity. In Vermont, for example, rainfall or snow-
melt are the major generators of surface runoff and
transport of field-spread manure to surface waters. Yet
these wet periods are often the times least likely for
manure to be spread, since farmers cannot readily work
their muddy fields. Thus, a straightforward correlation
analysis between manure application, runoff, and stream
nutrient levels would be inappropriate, since they may be
already inversely correlated.
Solutions to these confounding influences are not clear.
Application of multivariate statistical techniques such as
discriminant analysis may be useful. Alternatively, data
may be aggregated to seasonal or even annual periods
to avoid these confounding effects.
Secondly, the issue of spatial variation must be con-
sidered. For example, on a strictly numerical basis, the
same number of watershed acres may be in corn from
year to year, yet individual locations (fields) may rotate
into or out of corn production in any given year. The loca-
tion of these fields in relation to surface waters, for ex-
ample, may be a strong influence on water quality.
Methods of relating such spatial data to water quality
data have not been adequately studied.
139
-------
MANURED AREA LAPLATTE RIVER WATERSHED, 1989
LEGEND
m
Hum 1 1 in limit -
Ml iitirpi'liri|i 10!
Uutri ail tt«ic4 -
28J icft:
set iti«
92 sett]
2.OI inn
[""] l> rni« if('i*' 22,tit iciti
[717] litMuItt il S«i«iU
-------
(a)
PHOSPHORUS AND BMPs
WATERSHED 2 1981 - 1989
LaPIatte River Watershed
0.2
0.15
0.1
0.05
0
Mean Annual P Cone, (mg/l)
-r = 0.03
° 0.05
j L_
0 10 20
30 40 50 60 70
Animals Under BMP (%)
—- [TP] "«- [P04-P]
80 90 100
(b)
PHOSPHORUS AND BMPs
WATERSHED 2 1983 - 1989
LaPIatte River Watershed
Mean Annual P Cone, (mg/l)
90 91
93 94 95 96 97
Animals Under BMP (%)
98 99 100
[TP]
v" [PO4-P]
Figure 5. Regressions for WS 2 annual mean phosphorus concentration versus percent of animals under BMP waste
management: (a) all data; (b) 90-100% of animals under BMP, LaPIatte River Watershed, Vermont. (11)
141
-------
However, looking at the data points in Figure 5(a) sug-
gests that something may be going on with the points on
the far right (where >90 percent of the animals are under
BMP). Expanding that region of the plot (Figure 5(b))
suggests that there may indeed be a relationship: r =
0.59, P » 0.043. This region represents year-to-year
variation in the extent of BMP waste management and in
animal populations after most implementation was com-
plete. This pattern seems to suggest that above a certain
level of land treatment, lower stream P levels may be as-
sociated with higher levels of manure management. In
the LaPlatte River Watershed, similar relationships were
found in several other monitored subwatersheds for both
P and N concentrations, leading to the possible inference
of a threshold principle, where a certain level of treat-
ment must be achieved before a water quality response
is observed. Such as observation would certainly have
been overlooked relying on statistics print-out alone.
SUMMARY
Evaluation of water quality trends in NPS project areas
requires rigorous statistical analysis. The basic statistical
behavior of the data set must be assessed with particular
regard to the critical assumptions of independence, con-
stant variance, and normal distribution.
Control for the effects of hydrologic variation is critically
important. Paired regression is an effective method to
control for such background variability; in long-term
monitoring, paired regression may reveal significant
changes in water quality hidden in noisy time series data.
Efforts to link observed changes in water quality to the
land treatment program require detailed land treatment
data that may be effectively managed in a GIS. The con-
founding influence of weather and season on source ac-
tivities and the spatial variability of source activities are
important issues that need to be addressed.
Visual and graphical examination of data is extremely im-
portant. Looking at the data can help identify patterns
that are not obvious in statistical print-out.
The LaPlatte River Watershed Project (11) was funded
by the USDA-Soil Conservation Service under the PL-
566 program.
REFERENCES
1. Reckhow, K. and C. Stow, 1990. Monitoring design
and data analysis for trend detection, Lake and
Reserv. Manage. 6(1):49-60.
2. UNESCO, 1978. Water Quality Surveys, R.M. Gale,
W.H. Gilbrich, R: Helmer, M.S. Konovalori, P. Perret,
R.H. Siddifi, eds., IMD-WHO Working Group on
Water Quality, UNESCO-WHO, Paris, 248 pp.
3. Hirsch, R.M., J.R. Slack, and R.A. Smith, 1982.
Techniques of trend analysis for monthly water
quality data, Water Resour. Res. 18(1):107-121.
4. Crawford, C.G., J.R. Slack, and R.M. Hirsch, 1983.
Nonparametric tests for trends in water-quality data
using the Statistical Analysis System, U.S. Geologi-
cal Survey, Open-File Report 83-550, USGS,
Lakewood, CO, 103 pp.
5. Ward, R.C. and J.C. Loftis, 1986. Establishing statis-
tical design criteria for water quality monitoring sys-
tems: review and synthesis, Water Resour. Bull.
22(5):759-767.
6. Gilbert, R.O., 1987. Statistical Methods for Environ-
mental Pollution Monitoring, Van Nostrand Reinhold
Co., Inc., New York, NY.
7. Berryman, D., B. Bobee, D. Cluis, and J. Halmmerli,
1988. Nonparametric tests for trend detection in
water quality time series, Water Res. Bull. 24(3) :545-
556.
8. Lettenmaier, D.P., 1988. Multivariate nonparametric
tests for trend in water quality, Water Res. Bull.
24(3):505-512.
9. Fisher, F.M., K.L. Dickson, J.H. Rodgers, K. Ander-
son, and J. Slocomb, 1988. A statistical approach to
assess factors affecting water chemistry using
monitoring data, Water Res. Bull. 24(5) :1017-1026.
10. Hewlett, J.D. and L. Pienaar, 1973. Design and
analysis of the catchment experiment, In E-.M. White,
ed., Proc. Symp. Use of Small Watersheds in Deter-
mining the Effects of Forest Land on Water Quality,
Univ. Kentucky, Lexington, pp 88-106.
11. Meals, D.W., 1990. LaPlatte River Watershed Water
Quality Monitoring and Analysis Program - Year 11,
Program Report No. 12, Comprehensive Final
Report, Vermont Water Resources Research Center,
University of Vermont.
142
-------
EVALUATING INDIVIDUAL BMPSAND MODELS
John C. Clausen
University of Connecticut
Storrs, Connecticut
INTRODUCTION
A critical component of a nonpoint source control
program is the evaluation of the best management prac-
tices (BMPs) being implemented. This paper discusses
evaluating the success of individual BMPs. Additional
brief mention will be made of the application of models to
evaluation, since this practice seems to be increasing.
Most of this paper is based on experiences obtained
through the evaluation of the St. Albans Bay Rural Clean
Water Program and the Laplatte River Watershed PI-566
land treatment projects in Vermont.
Evaluating the success of a BMP should be relatively
simple if the appropriate steps have been followed in
designing a reliable monitoring program (1). However,
surprises occur even in the best-planned experiments.
The methods of evaluating individual BMPs can best be
viewed following the concept of causality, which was dis-
cussed previously in the workshop (2). At the end of the
monitoring period there is a need to determine whether
there is an association between the BMP and water
quality that 1) is consistent with other data, 2) changes
appropriately with the level of BMP implementation, and
3) follows a logical mechanism. In addition, during the
monitoring period, preliminary insights into the success
of the BMP may be developed.
EVALUATING BMPS
The ability to evaluate the success of the BMP will be a
function of the monitoring design employed. If the design
was to sample watershed water quality before the BMP
and compare that with the water quality after the BMP,
differences due to the BMP could be confounded with
climate variations year-to-year (Table 1). Sampling
above and below a BMP after it has been installed does
not allow separating the cause due to the BMP from that
associated with watershed differences. As Table 1 indi-
cates, only the paired and multiple watershed designs
allow isolating the effect of the BMP. Significant differen-
ces obtained through the use of the other designs do not
allow attaching causality to the BMP alone.
LESSONS LEARNED
There were several lessons learned from evaluation of
the effectiveness of BMPs in the St. Albans and Laplatte
projects.
Year-to-year water quality differences because of climate
can be significant and can overshadow the effect from
the BMP. For example, during a paired watershed study
of the effect of manure applications to a hayland in Ver-
mont, concentrations in field runoff from the control
declined from the calibration period to the treatment
period for suspended solids and ammonia nitrogen
(Table 2). Runoff during the treatment period was half
that during the calibration period (3). Any evaluation
method that cannot control for this effect is weakened by
climate variations. This issue is also pertinent to long-
term trend analysis, as the previous paper by Meals
(1991) discussed.
Watershed-to-watershed water quality differences can be
significant and possibly greater than the BMP effect. In
the paired hayland study in Vermont, the soon-to-
become treatment watershed was higher in concentra-
tions than the control watershed during the calibration
period for suspended solids, phosphorus, and nitrogen
(Table 2). These two fields were adjacent and land
usage was identical. This influence is especially true for
large watersheds used for long-term trend analysis.
Constant care must be exercised in supervising the ac-
tual BMP to avoid catastrophic surprises for the land-
owner. For paired watershed studies, land-use activities
must be identical between fields, except for the BMP
change. Landowners frequently want to continue to
manage a field, for example, with a manure application,
because they always did. In one paired watershed study
where the water quality effects of winter-applied manure
were being investigated, the manure to apply to the field
actually had to be purchased because the owners'
manure pit had frozen.
143
-------
Table 1. Potential Causal Factors Explaining Significant Water Quality Differences for Various Watershed Designs
Design
Time Period
Single watershed — before and after
Above and below— after
Two watersheds — two treatments
Paired watersheds — before and after
Multiple watersheds— after
Typical
Statistical Approach
t-test of means
t-test of means
t-test of means
regression
ANOVA
Causal
Factors
BMP-Weather
BMP-Watershed
BMP-Watersheds
BMP
BMP
Table 2. Mean Runoff Concentrations (mg/L) from the Control and Treated Hayland Fields During Calibration and
Treatment Periods
Calibration
Control Treated
Treatment
Control Treated
Total suspended solids
Total phosphorus
Ammonia nitrogen
Discharge (cm)
13.0
0.49
0.6
10
19.3
0.59
2.0
12
9.1
0.64
0.4
5
15.8
0.98
0.7
5
A multitiered evaluation approach for BMPs is recom-
mended. Intensive short-term evaluations should be
planned and complemented with broader long-term
evaluation. In our studies, which spanned 10 to 12 years,
we were annually asked to assess BMP effectiveness in
large watersheds. However, responses took many years
and we could only demonstrate responses due to in-
dividual BMPs and develop preliminary assessments
after3 to 5 years of monitoring.
EVALUATION USING MODELS
BMP evaluation is a test in which the primary question is:
"What are the effects on water quality of implementing
this BMP or package of BMPs?" Models can only simu-
late the water-quality conditions that one might expect in
a given situation. A great deal of uncertainty exists in at-
tempting to model the water quality achievable by im-
plementing a given set of BMPs. Models may be used as
planning tools and are especially useful for targeting
priority areas for BMP implementation. However, models
should never be used to evaluate the effectiveness of
BMPs.
SUMMARY
The evaluation of the water-quality effectiveness of in-
dividual BMPs can be straightforward if properly planned
from the beginning. Actual causality can be
demonstrated with some, but not all, commonly used
designs. Year-to-year and watershed-to-watershed
water-quality differences must be planned for in design-
ing and evaluating water quality monitoring studies. The
author discourages the use of models in evaluating the
water-quality effectiveness of BMPs.
REFERENCES
1. Clausen, J.C., 1991. Developing a monitoring sys-
tem for rural surface waters: individual BMPs, Proc.
Nonpoint Source Watershed Workshop, U.S. En-
vironmental Protection Agency, New Orleans, LA,
Jan.29-31.
2. Mosteller F. and J.W. Tukey, 1977. Data Analysis
and Regression: A Second Source in Statistics,
Addison-Wesley Pub., Reading, MA.
3. King, J.R. and J.C. Clausen, 1989. Hayland manure
applications and the quality of surface runoff, Proc.
Dairy Manure Management Symp., Northeast
Regional Agricultural Engineering Service Publ.,
NRAES-31, Syracuse, NY. Feb. 22-24.
144
-------
EVALUATION OF SITE-SPECIFIC GROUND-WATER QUALITY DATA
Jeanne Goodman
South Dakota Department of Water and Natural
Resources
Pierre, South Dakota
INTRODUCTION
This discussion will present information on techniques
used for site-specific ground-water quality data evalua-
tion of nonpoint source pollution projects. The informa-
tion presented is based on experience gained during the
Oakwoods/Poinsett Rural Clean Water Program (RCWP)
project in eastern South Dakota. The Oakwoods/Poinsett
RCWP project is a Comprehensive Monitoring and
Evaluation project with the goal of evaluating the impacts
of agricultural best management practices (BMPs) on the
vadose zone, the ground water, and the Oakwood Lakes
system. The BMPs selected for implementation in the
project were accepted for surface water pollution abate-
ment, but the effects on ground water were not known.
The primary pollutants evaluated are nitrate and pes-
ticides in the vadose zone and ground-water portions of
the project, and nitrate and phosphorus in the Oakwood
Lakes study portion of the project.
The land areas evaluated for nonpoint source pollution
problems are usually large. Adequate ground-water
monitoring and evaluation of large areas can be cost
prohibitive, so smaller areas that are representative of
the whole project must be selected (1). Site-specific
monitoring also increases the probability of detecting
changes in ground-water quality due to changes in the
land use.
The Oakwoods/Poinsett project area is over 106,000
acres. Seven field sites between 10 and 80 acres were
selected for ground-water monitoring. Six of the sites
were farmed fields and one site was an unfarmed state
park. One of the farmed sites was not subjected to land-
use changes through the implementation of BMPs. BMPs
were implemented on the farmed sites prior to the instal-
lation of monitoring equipment, so the control site con-
cept (sites with no BMPs and an unfarmed site) was
necessary to determine cause and effect relationships of
pre- versus post-BMP implementation.
The following discussion describes the statistical
methods used in data evaluation, the types of data ag-
gregation used, and other analyses completed using
hydrologic parameters and spatial and temporal distribu-
tions. Specifically, the use of the geozone classification
system, evaluation of nitrate data, and evaluation of pes-
ticide data will be discussed.
GEOZONES
Progress reports with data analysis were required for the
RCWP projects. This provided an opportunity for the
project technical team to reevaluate the monitoring and
evaluation strategies annually. Following the annual
report on 1985 activities, a new method to aggregate and
reduce the variability in the data was developed for the
project.
The "geozone" classification system was devised to char-
acterize each monitoring well by: 1) the geologic material
in which the well was screened, 2) the depth of the well
screen, and 3) the thickness of the overlying fine-grained
materials (for wells screened in sand and gravel). The
depth of the well screen was expressed by the depth
below ground surface for wells screened in till, and depth
below the water table for wells screened in sand and
gravel. There were 11 geozone classifications for the
Oakwoods/Poinsett project. Even though the classifica-
tions were project specific, the methodology is applicable
to any ground-water investigation (2).
Figure 1 illustrates the 11 geozones on a diagrammatic
cross-section. This is not a real cross-section but a com-
posite of stratigraphic sequences encountered during
test hole drilling at the field sites. The water table depicts
the relative position of the water table to the geozone
and does not represent the ground-water flow direction.
The relative vertical position of each geozone to another
is accurately depicted. Horizontal relationships have
been forced and are not accurate, as in where the sand
and gravel is shown in connection with the till (2).
The geozone classification system was used to ag-
gregate the water-quality data into hydrologically and
geologically meaningful groups. It was used as a sorting
criteria during the statistical analysis. The geozone
diagram was used to illustrate the analytical results in
relationship to the site geology.
145
-------
GEOZONES
S6LT5GTIO- •"• •....;
LEGEND
- SIIT/SANO (ALTER)
- WEATHEBEO TILL H|] - CLAYjSILT AOWTARO
WWEATHEREOTIU. U-'H - SAND a GRAVEL
Figure 1. Geozone cross-section.
NITRATES
Several analysis methods were used for the evaluation of
the nitrate data: "looking" at all data, median nitrate con-
centrations for each geozone, testing for statistical dif-
ferences, trend analysis, analysis of variance, and
correlations.
All nitrate values from wells unaffected by point sources
of contamination were plotted versus sampling depth
below water table. Figure 2 is the resulting plot, which il-
lustrates the distribution of nitrates from all the wells rela-
tive to the sample depth. The analysis was valuable
because it indicated further analysis was needed to ex-
plain the mechanisms of nitrate reduction with depth.
Vertical ground-water velocities were estimated to deter-
mine if it was mathematically possible for nitrates to
move deeper in the saturated zone. Since the calcula-
tions indicated it was possible, it was theorized that
denitrification was occurring. Plots similar to the nitrate
plots in Figure 2 were prepared for dissolved oxygen and
chloride to substantiate the denitrification theory.
The nitrate data set was tested for normality and was
found to have nonnormal distributions. When data have a
nonnormal distribution, the median is a more appropriate
measure of central tendency (3). The median concentra-
tions were used in describing the nitrate data for each
geozone as shown in Figure 3. The plot was used for dis-
cussing "hot spots" in nitrate concentrations relative to
the geology and depth below the water table. This type of
information was also used to evaluate the nitrate con-
centrations in relation to the position of the geozone in
the subsurface. For example, the median nitrate con-
centrations for five geozones were plotted by year. The
geozones represented the logical progression through
the hydrogeologic system from the land surface to depth.
The plot (Figure 4) illustrated the ranking of nitrate con-
centrations and the magnitude of changes through time.
The plot showed less magnitude of change with depth
and a lag time for change of the deeper geozones com-
pared with the shallower geozones.
Various levels of data aggregation were used and tested
for significant differences. A test for significant differen-
ces between all the data for various populations were
conducted using the Mann Whitney U or equivalent Wil-
coxan 2 sample test (4). These nonparametric tests for
comparing two populations are more appropriate and
more powerful (3) than the equivalent parametric tests
when the population distribution is nonnormal. Popula-
tions of nitrate data were compared between the follow-
ing: field sites, site types (outwash and till), the control
(unfarmed and no BMPs) sites, geozones, wells, and
years. This analysis has proven the need for control-type
sites when using real farmed sites. Statistical testing has
not shown significant differences in nitrate concentrations
146
-------
10-
-50-
NO3-N (mg/l) vs. DEPTH BELOW WATER
2469 Samples From May 1984 to December 1989
et below the water table
<--- 5 mg/l nitrate as nitrogen
- 5 10 15 20 25 30 35
NO3-N Concentrations (mg/l)
Figure 2. Nitrate concentration (mg/L) versus depth below water table.
40
45
50
Median Nitrate Concentrations
WTLT15
WTGT15
UT
SS-A
e SG-UA
§ SGLT5LT10
CD
0 SGLT5GT10
SGGT15
SG5-15LT10
SG5-15GT10
SC
4 5 67
Median Nitrate as N Cone, (mg/l)
10
Figure 3. Median nitrate concentration by geozone.
147
-------
MEDIAN NITRATE CONCENTRATIONS
by Year
Figure 4. Median nitrate concentrations by year.
between sites with BMPs and sites with no BMPs, but
there are significant differences between all farmed sites
and the unfarmed site.
The preceding methods of nitrate evaluation were used
with success. Other analyses that were found to be less
useful or were labor intensive include cluster analysis,
analysis of variance, and trend analysis. The cluster
analysis and analysis of variance yielded information on
the distribution of nitrate concentrations between sites
and geologies and differences in the sample populations,
but the differences were often of low statistical sig-
nificance. Simpler techniques such as the median nitrate
concentration of wells in each geozone were less work
intensive and more illustrative of the system. The non-
parametric analyses were also more "statistically ap-
propriate" than the equivalent parametric tests. To date,
analysis of trends in nitrate concentrations with time have
been inconclusive.
PESTICIDES
Pesticide data analyses were concentrated on evaluating
the spatial and temporal distribution of the number of
pesticide detections. Any further analyses were difficult
since 85 percent of the pesticide detections were one-
time events, i.e., a sample had positive detections of
pesticides one month, but there were no detections in
samples from the same well taken the following sampling
event.
The geozone classification system was used to illustrate
the spatial distribution of pesticide detections. Figure 5
shows the resulting plot. The number of pesticide detec-
tions also were examined by grouping data from all sand
and gravel geozones and comparing them to data from
all glacial till geozones. Although more samples were
taken from the sand and gravel, a higher percentage of
detections were from till samples. This type of analysis
allowed a comparison of the sample population with the
hydrogeologic system in the project area. It also il-
lustrated the importance of preferential flow in the till
materials. This type of information can be used in dis-
cussing relative vulnerability of materials with various
permeabilities.
Sampling of representative monitoring wells for pesticide
analysis was done on a monthly basis for most of the
project period. This frequency allowed a determination of
the times of the year most likely for pesticide detections
in the ground water (Figure 6). This type of monitoring
not only yielded information on the timing of the use of
the chemicals on the land surface, it also allowed the
project's technical team to adjust the sampling schedule
to more efficiently assess pesticide occurrence in the
ground water. The frequency of pesticide detections also
were compared on an annual basis. The annual frequen-
cy distribution showed that the number of detections
greatly increased during two years of well below normal
precipitation. This indicated a more thorough investiga-
148
-------
Geozones with Pesticide Detections
WTGT15(10.1%)
WTLT15(29.5%)
SGLT5LT10(25.6%)
SG-UA(10.1%)
SG5-15LT10(4.7%)
UT (6.2%)
Figure 5. Geozones where pesticides were detected.
SGLT5GT10(5.4%)
SS-A (8.5%)
Months when Pesticides were Detected
•JUN (18.096)
MAY (14.8%)
APR (4.7%)
FEB (0.8%)
JAN (4.7%)
JUL(18.0%)
DEC (8.6%)
NOV(1.6%)
OCT (4.7%)
SEP (10.9%)
Figure 6. Months of pesticide detections,
AUG (13.3%)
149
-------
tion is needed of the relationship between precipitation
and the number of detections.
The occurrences of pesticide detections also were ex-
amined in conjunction with the hydrologic data that had
been collected on a weekly basis. The timing of the
detections was compared to hydrographs to determine
the relationship of the detections with the fluctuation of
the water table. It appeared most detections were on the
falling limb of the peaks, corresponding to post-spring
recharge events. However, the recharge events also
were the most common times of application, which has
been deemed the most important factor in the timing of
the detections (5).
The pesticides detected in the ground water were com-
pared with the land-use data, which included chemical
type, rate, and timing, for the sites where pesticides were
detected. Over 65 percent of the detections could not be
related to use on that site (6). The exact mechanisms for
this are not known, but field observations of runoff events
during chemical use and crop growth in the later years of
the project indicated overland flow from adjacent land,
ponding, and subsequent ground-water recharge may be
an avenue for chemical transport to the subsurface.
SUMMARY
In summary, information on techniques used to evaluate
site-specific ground-water quality data for the Oak-
woods/Poinsett RCWP project were presented. In par-
ticular, methods used to evaluate the nitrate and
pesticide data were discussed and a classification sys-
tem (geozones) used to aggregate and reduce variability
of data was described. The 10-year report for the Oak-
woods/Poinsett project is currently being prepared. The
data analysis for the report will include in-depth analysis
of each field site. Land-use data for each site have also
been tracked throughout the life of the monitoring project.
The land-use data, such as cropping patterns, type,
amount, and timing of agricultural chemical application,
timing and depth of cultivation, and timing of harvest
have been collected. These data will be used to evaluate
what, if any, correlations exist between the land surface
activities and the water-quality data by creating new ag-
gregation categories based on land-use information.
The vadose monitoring portion of the Oakwoods/Poinsett
RCWP project will be used extensively for explaining the
impacts of land-use practices on the chemical and water
movement through the soil profile and unsaturated zone.
The Master Site is extensively instrumented with state-of-
the-art equipment to provide continuous measurements
of water and chemical movement. Work at this site has
been on the leading edge of defining macropore flow and
the implications for ground-water impacts. Although this
high-budget study is not feasible for many nonpoint
source pollution projects, the information generated by
the Agricultural Chemical Leaching Study of the Oak-
woods/Poinsett RCWP project will be used for assess-
ment of the effectiveness of various BMPs and the im-
pacts on water resources.
Some of the lessons learned from the 10-year Oak-
woods/Poinsett RCWP project relative to data evaluation
are as follows:
1. Annual progress reports required periodic data
analysis, which allowed modification and refinement
of the monitoring program to ensure meeting the
project's goals and objectives.
2. A detailed description of the hydrogeologic system
and the use of the geozone classification system will
contribute to extrapolating the site-specific informa-
tion to the whole project area and areas of similar
geology. The geozone classification system also al-
lowed a practical application of the statistical
analysis results.
3. Understanding the hydrogeologic system is impera-
tive to evaluating the ground-water quality data. This
includes the collection of hydrologic data such as
water levels and hydraulic conductivities.
4. The tracking of land use is difficult, and very
cooperative landowners are needed. Consistently
working with the landowners helps to gather land use
data, but results can be mixed.
5. The control sites (unfarmed and no BMPs) were
necessary when working with real farmed fields.
However, it would have been extremely valuable to
have the land use at a site radically change after the
first few years of monitoring. (This is true for this
project, since no monitoring was possible prior to
BMP implementation.)
6. Onsite precipitation measurements are needed be-
cause precipitation is the vector by which nutrients
and contaminants are transported through the soil
profile to the ground water.
7. Shallow ground-water quality appears to change
faster than originally envisioned. It was initially an-
ticipated that changes could be seen in 5 to 6 years,
but the data indicate there is the potential for chan-
ges to occur in a much shorter time period.
REFERENCES
1. Kimball, C.G., 1988. Ground-Water Monitoring Tech-
niques for Non-Point-Source Pollution Studies,
Ground-Water Contamination: Field Methods, ASTM
STP 963, A.G. Collins and A.I. Johnson, Eds.,
American Society for Testing and Materials, Philadel-
phia, PA, pp.430-441.
2. South Dakota Department of Water and Natural
Resources, 1986. 1986 Oakwood Lakes - Poinsett
RCWP Annual Progress Report - Project 20, Open
File Report, 194pp.
150
-------
3. Crawford, C.G., 1984. Application of Selected Non- 5.
parametric Statistical Methods to the Analysis of
Hydrologic Data, prepared for Statistical Analysis of
Water Quality Data (G0062), U.S. Geological Sur-
vey, Reston, VA.
4. Sokal, R.R. and F.J. Rohlf, 1969. Biometry, W.J. 6.
Freeman and Company, San Francisco, CA.
Kimball, C.G. and J. Goodman, 1989. Non-Point
Source Pesticide Contamination of Shallow Ground
Water, paper presented at 1989 International Winter
Meeting, The American Society of Agricultural En-
gineers, New Orleans, LA, December 12-15.
South Dakota Department of Water and Natural
Resources, 1989. 1989 Oakwood Lakes - Poinsett
RCWP Comprehensive Monitoring and Evaluation
Technical Report Project 20, Open File Report,
Pierre, SD.
151
-------
EVALUATING NONPOINTSOURCE CONTROL PROJECTS IN AN URBAN
WATERSHED
Thomas E. Mumley
California Regional Water Quality Control Board
Oakland, California
INTRODUCTION
The California Regional Water Quality Control Board,
San Francisco Bay Region (Regional Board) is the state
water pollution control agency responsible for protection
of the beneficial uses of San Francisco Bay and its
tributaries. Using its authority under both state and
federal law, the Regional Board has required the
development and implementation of a nonpoint source
(NFS) control program by the municipalities in the Santa
Clara watershed which drains into the South Bay seg-
ment of San Francisco Bay. The focus of the program
has been on the control of toxic pollutants in urban runoff
within this watershed.
The local municipalities in the Santa Clara watershed
have responded pro-actively to develop and now imple-
ment a comprehensive NFS control program. The
program was developed through an extensive planning
process. The planning process priorities were set
through the establishment of clearly defined goals for the
overall program and tangible objectives for the assign-
ment and implementation of control measures. This al-
lowed for an effective project screening process resulting
in assignment of projects with specific goals and objec-
tives that when implemented will result in attaining the
overall program goals. These specific projects are now
being implemented. The built-in evaluation process in the
Santa Clara program provides an illustration of how the
effectiveness of specific projects and the overall program
can be evaluated.
EVALUATION PROCESS
The watershed project evaluation process involves the
recurring review and assessment of project activities to
ensure that resources are being utilized in the most ef-
fective way to achieve established objectives. At a mini-
mum, there should be a formal evaluation annually of the
project which provides documentation of project
progress, milestones accomplished, and degree of suc-
cess in meeting objectives. The annual evaluation should
also include considering modifications to project activities
based on experience and knowledge gained during the
year. With planning foresight, this flexibility should en-
sure that project goals and objectives remain quantitative
and measurable and should lead to attaining overall
program goals and objectives.
Evaluating the effectiveness of a project is a challenge
because: 1) the sources of specific pollutants found in
storm drain systems are not currently well understood; 2)
the effectiveness of control measures, especially those
that focus on source control, are by their very nature dif-
ficult to predict; and 3) the annual variability in rainfall
and the storm-to-storm variability in water quality and
pollutant load will tend to mask any long-term (multi-year)
gradual trends in improved water quality associated with
implementation of the project.
Because of these uncertainties, most projects are
designed so that many of the early activities focus on
evaluating the feasibility of implementation through pilot-
scale studies. Also, monitoring efforts are being designed
to assist in identifying important sources before im-
plementing costly control measures. Additionally, the
evaluation takes into account experience gained in other
programs, such as hazardous waste management
programs and technical results from demonstration
studies.
Because of the difficulty of evaluating project effective-
ness from routine monitoring data, surrogate measures
are, used where appropriate. For example, the effective-
ness of storm drain stencilling to discourage illegal
dumping of used oil and incentives for recycling used
motor oil may be based on estimates of the increased
volume of used oil recycled. In some cases, where sur-
rogate measures of effectiveness are not available, level
of effort is provided. Although level of effort does not
provide a measure of effectiveness towards attaining
water quality objectives, it does provide a means of
documenting that the best job is being performed at the
most reasonable cost (i.e., maximum extent practicable).
In most cases implementing a control measure and
evaluating its effectiveness should be done in a phased
process. In general, the phases include:
152
-------
• A planning phase to analyze, evaluate and plan in
greater detail the initial tasks for implementation in-
cluding establishing objectives for implementation.
• A preparation phase, which follows the planning
phase or is done concurrently with final planning
tasks, consists of preparing budget and resource
needs and obtaining permits and necessary ap-
provals.
• A pilot-scale (or initial level) implementation
phase as a means to test procedures or tech-
nologies, to gain experience with new activities, to
determine feasibility of implementing at full scale,
and to evaluate the effectiveness and cost ramifica-
tions of the proposed approach. Alternatively, this
phase may consist of an initial level of implementa-
tion (reduced or limited level) of a demonstrated con-
trol measure, where full-scale implementation would
be costly.
• A full-scale implementation phase that is the ma-
ture, final phase of a control measure. The tasks and
activities in this phase will be. operating at the ap-
propriate level of effort, and in the final design, as
determined during earlier phases. " ,
• An evaluation/documentation phase that will be
conducted continuously for each control measure
simultaneously with each of the other phases. Con-
trol measure tasks are reviewed and considered pe-
riodically in order to determine effectiveness (in
terms of controlling pollution; in terms of doing the.
best job for the most reasonable cost; and in terms
• of adaptability to municipal agency structure, prac-
tices, and resources). This effort may be considered
as a revision of existing compounds, where the ap-
propriateness of each task is assessed and new
tasks may be considered.
Also in this phase, an annual report is prepared
documenting the achievements and effectiveness of
the control measures during the preceding year. The
report may contain recommendations for changing
tasks or schedules in the forthcoming year(s). The
report should allow an agency, such as the Regional
Board, to monitor progress, review the kinds of tasks
implemented, to verify level of effort, and to comment
on proposed activities and schedules.
The following example based on the .Santa Clara
program illustrates, how these phases could be described
for a given control measure.
EXAMPLE OF PHASING IMPLEMENTATION
AND EVALUATION
Control Measure
City X decides to change the frequency of cleaning storm
drain inlets (currently it is done on an as-needed basis, in
response to complaints and when the inlets overflow),
and possjbly modify the method of cleaning, if a proven
more effective method 'can be found (currently, lines are
flushed).
Planning Phase
• Study what is currently being done in other cities and
states to clean and maintain storm drain inlets.
Choose a method (e.g., using a vactor truck to clean
out debris prior to flushing lines) that appears to
have success in another location.
• Choose a new frequency, such as seasonally (i.e.,
before the first large storm events each year).
• Develop a plan to pilot test the selected method in
the city. (For example, choose two test areas: in one
area, use the old cleaning method and simply vary or
• increase the frequency; in the second area, test the
new method in combination with a new frequency.)
• Determine how to evaluate the effectiveness of the
new method. For example, monitoring the water in a
downstream outfall for each test area by analyzing
physical characteristics (e.g., with field test kits) on a
monthly basis.
• Determine the length of time for a good pilot-scale
study ,in order to observe and measure effectiveness
(e.g., one year). .
• Determine the resources needed to conduct the pilot
test, such as additional or specially trained staff,
and/or new or leased equipment.
Preparation Phase
• Submit the plan with projected costs and schedule to
the appropriate agencies, departments, and City
Council. Obtain all approvals/authorizations neces-
sary to proceed with the work.
Pilot-Scale Implementation Phase
• Purchase/lease equipment and hire/train personnel
to conduct the work. Alternatively, hire a contractor
and execute contracts.
• Send personnel or contractors to the test areas to
conduct the work described in the pilot program plan.
153
-------
Evaluation/Documentation Phase
• Study and measure effectiveness (e.g., by inspecting
the identified outfalls in the test areas on a monthly
basis), if debris is found, note amount and physical
characteristics.
• Based on the results of the pilot-scale implementa-
tion, choose the combination that results in best
water quality found at the test outfall during
inspections.
Full-Scale Implementation Phase
• Design the full-scale implementation program, iden-
tify outfalls in which to monitor effectiveness over a
period of time, and obtain approvals for schedule
and costs.
• Purchase/lease equipment and hire/train personnel
to conduct the work. Alternatively, hire a contractor
and execute contracts.
• Conduct work in all areas of the city, according to the
full-scale implementation schedule.
Evaluation/Documentation Phase
• Study effectiveness of the full-scale improved main-
tenance program by inspecting the identified outfalls
on a regular basis and comparing water quality over
a period of time. Record observations of improved
water quality for preparing annual report for the
Regional Board.
• Prepare and submit annual report to the Regional
Board, and make modifications to the program as
necessary based on comments.
SUMMARY
Evaluating the effectiveness of a watershed project is a
challenging endeavor. The process involves the recurring
review and assessment of project activities to ensure that
resources are being utilized in the most effective way to
achieve established objectives. This requires estab-
lishment of clearly defined goals for the overall program
and tangible objectives for the assignment and im-
plementation of control measures. In addition to routine
monitoring data, surrogate measures are used where ap-
propriate. Effectiveness evaluation normally should be
conducted in a phased process including a planning
phase, a preparation phase, a pilot-scale implementation
phase, and a full-scale implementation phase. Finally,
there should be a formal evaluation annually of the
project that provides documentation of project progress,
milestones accomplished, and degree of success in
meeting objectives. The annual evaluation should also
include considering modifications to project activities
based on experience and knowledge gained during the
year. With planning foresight, this flexibility should en-
sure that project goals and objectives remain quantitative
and measurable and should lead to attaining overall
program goals and objectives.
154
-------
SECTION TEN
INNOVATIVE STATE AND LOCAL REGULATORY PROGRAMS
THAT SUPPORT LOCAL NFS PROJECTS
-------
CONTROLLING STORMWATER: SOME LESSONS FROM THE MARYLAND
EXPERIENCE
Greg Llndsey
Molly Cannon
Maryland Department of the Environment
Sediment and Stormwater Administration
Baltimore, Maryland
INTRODUCTION
The State of Maryland has implemented a number of
programs designed to control nonpoint source pollution.
Maryland's Stormwater Management Program is the
cornerstone of efforts to control urban nonpoint source
pollution and has received national and international at-
tention. This paper provides a synopsis of state efforts to
control Stormwater, a review of the strengths and weak-
nesses of the programs, and some observations about
the implications of new federal programs and regulations
for Maryland programs.
STORMWATER MANAGEMENT IN MARYLAND
The Stormwater Management Act
Programs to control urban Stormwater in Maryland are a
sub*set of a wide variety of programs aimed at controlling
urban nonpoint source pollution. The Stormwater
Management Program is administered by the Sediment
and Stormwater Administration (the Administration)
within the Maryland Department of the Environment. Re-
lated programs not reviewed here include a parallel,
complementary Erosion and Sediment Control Program,
also administered by the Sediment and Stormwater Ad-
ministration; the Department of Natural Resources'
Chesapeake Bay Critical Areas Program; and the
Department of the Environment's Water Quality Certifica-
tion Program. The timeline in Figure 1 shows significant
events in the evolution of programs to manage
Stormwater in Maryland.
The Stormwater Management Act was passed by the
Maryland General Assembly in 1982. The primary goal of
state and local programs established by the Act is to
"maintain after development, as nearly as possible, the
predevelopment runoff characteristics." In terms of quan-
tity control, regulations promulgated by the state in 1983
define this as onsite control of 2- and 10-year storm
events for most of Maryland. In addition, the Administra-
tion has established a list of preferred management prac-
tices for quality control. Pursuant to this list, local officials
responsible for plan review are required to investigate
the feasibility of infiltration of the first half-inch of runoff.
This so-called first flush contains most of the pollutants in
runoff. If infiltration is not feasible, other practices may be
used. These other practices, in order of preference, are
vegetated swales, retention ponds, extended detention
ponds, and detention facilities. The position of each prac-
tice on the list was determined primarily by its potential to
provide pollutant removal. Infiltration is preferred be-
cause it offers the highest potential for reduction in pol-
lutants such as sediment and phosphorus, has potential
for groundwater recharge and maintenance of base flow,
and mitigates thermal impacts. All incorporated counties
and municipalities in Maryland were required to adopt or-
dinances by 1984 that establish programs which, at mini-
mum, provide these controls on every development that
disturbs more than 5,000 ft2 of land and significantly
changes site hydrology (waivers may be issued if the dif-
ferences in 2- and 10-year discharge for pre- and
postdevelopment are less than 10 percent).
The Act is quite broad, and those who drafted it recog-
nized that it would significantly change the way develop-
ment occurs throughout the state. The authors also
recognized that the mandates of the law would push
technical knowledge in the area of Stormwater manage-
ment and that significant assistance would have to be
provided to local governments to achieve successful im-
plementation. The Act authorizes local governments to
establish fee systems to cover the cost of plan review
and program implementation, mandates that state
regulatory officials review local programs at least trien-
nially, requires that the state conduct research and
provide technical assistance and training in the applica-
tion of Stormwater management technology and program
implementation, and provides for civil and criminal penal-
ties for violation of the law.
In addition to establishing minimum controls and
preferred practices, the 1983 regulations establish state
responsibilities, criteria for exemptions and waivers, and
requirements for construction and maintenance inspec-
tion and enforcement. State regulatory staff responsible
156
-------
1983
1990
STATE ACTIVITIES
MARYLAND
SUM
MGHT.
ACT
ADOPTED
MARYLAND COUNTY
SUM AND
REGULATIONS MUNICIPAL
PROMULGATED ORDINANCE
ADOPTED
PROGRAM
GRANTS-
Itf-AID
AUTHORIZED
STATE REGULATORY REVIEWS OF LOCAL STORMHATER
MANAGEMENT PROGRAMS UNDERTAKEN
PROGRAM GRANTS-IN-AID AWARDED
CAPITAL COST SHARE GRANTS AWARDED
CHESA-
PEAKE BAY
NUTRIENT
REDUCT ION
GOALS
ESTABL ISHED
MD ' S
NUTRIENT
REDUCT ION
PLAN
PREPARED
BAYWIDE
NUTRIENT
REDUCTION
STRATEGY
ADOPTED
CAPITAL COST
SHARE GRANTS
AUTHORIZED
FEDERAL ACTIVITIES
CONGRESS
PASSES
WATER
QUALITY
ACT
EPA
I SSUES
DRAFT
NPOES
REGULA-
TIONS FOR
STORMWATER
SYSTEMS ,
CONGRESS
ALLOCATES
FUNDS FOR
NONPOI NT
PROGRAMS
EPA
AWARDS
NONPOINT
SOURCE
GRANTS
TO STATES
FINAL
NPDES
REGULA-
TIONS TO
BE ISSUED
1982
1985
1986
SWM=STORMWATER
Figure 1. Milestones in the evolution of Maryland's stormwater management program.
157
-------
for program review are required to determine whether
local programs are acceptable. To be acceptable, local
programs must have 1) an approved ordinance, 2) ade-
quate administrative procedures, 3) adequate plan
review, 4) acceptable construction inspection and enfor-
cement, and 5) acceptable maintenance inspection and
enforcement.
Since 1982 the Administration has worked with
Maryland's 23 counties and 151 municipalities to imple-
ment local programs. Forty-seven municipalities chose to
implement programs; the remaining 104 adopted resolu-
tions that gave the county governments the authority to
implement programs within their respective jurisdictions.
The Administration has conducted 25 local program
reviews, completed a number of research studies, and
held several training conferences and workshops to as-
sist local officials. Details concerning implementation are
summarized below.
Stormwater Program Grants-In-Aid
In 1984, as part of a legislative package known as the
Chesapeake Bay Initiatives, the General Assembly
authorized two additional programs related to stormwater
management. One of these was the Stormwater
Management Grants-in-Aid Program. This program,
which became effective in 1985, allocated approximately
$1.5 million annually to local governments to assist them
with implementation. Grants-in-aid may be used to fund
personnel, but local governments must have an Ad-
ministration-approved program to apply. Criteria used to
evaluate funding requests are not rigorous and pertain
mainly to the "reasonableness" of the request. In general,
this refers to whether there appears to be sufficient work
to justify the proposed positions. To assist local jurisdic-
tions in estimating manpower requirements, the Ad-
ministration provides productivity guidelines. Most funds
are used to pay plan-review staff and inspectors, al-
though some clerical and administrative positions also
are funded. Since the grants-in-aid program is competi-
tive and is not an entitlement program, some local
governments choose not to seek support.
Stormwater Pollution Control Cost Share Program
The Stormwater Pollution Control Cost Share Program,
which also was authorized in 1984 and implemented in
1985, is a grant program that matches up to 75 percent
of the cost of stormwater management retrofits. These
projects serve areas developed without stormwater
management. The objectives of the Cost Share Program
are to demonstrate best management practice (BMP)
pollutant removal efficiency, cost effectiveness, social ac-
ceptability, and maintenance requirements. Grants are
awarded competitively and funds for the projects are
raised through the sale of state bonds. In total, between
1984 and 1990, the Maryland General Assembly
authorized $5 million for stormwater capital projects
under this program.
Chesapeake Bay Agreements
In 1987 the governors of Maryland, Virginia, and
Pennsylvania, the mayor of Washington, DC, the chair-
man of the Chesapeake Bay Commission, and the U.S.
EPA administrator signed an agreement calling for a 40
percent reduction in nutrient loadings to the Chesapeake
Bay. In 1988, Maryland's Nutrient Reduction Plan was
completed, outlining a strategy for implementation of the
nutrient reduction objectives. The Plan calls for a 40 per-
cent reduction in all point and nonpoint sources, includ-
ing urban stormwater. To control urban runoff, three
strategies are identified: 1) the continuation of the exist-
ing cost share program, 2) a massive new retrofit
program to be funded by stormwater utilities, and 3) a
redevelopment program aimed at "explicit management
of development intensity." No complete cost estimates
for implementing these programs are available. Although
direct construction costs for retrofits have been estimated
at $71 million, this estimate is extremely low and does
not include any ancillary costs such as planning, model-
ing, or design.
EPA Nonpoint Source Control Programs
In 1987 Congress passed the Water Quality Act, a com-
prehensive overhaul of the Clean Water Act. Section 319
of the Act requires that all states develop assessment
and management reports that identify and categorize
sources of nonpoint pollution and outline coordinated
strategies for implementation of programs to control
them. The primary goal of Maryland's Assessment and
Management Reports is to implement the Nutrient
Reduction Plan. State officials made nutrient reduction
the focus of the nonpoint source program because sig-
nificant effort had been put into developing the Nutrient
Reduction Plan, quantitative goals already were in place
(i.e., the 40 percent reductions), and steps towards im-
plementation already were underway. Maryland's As-
sessment and Management Reports were approved in
August and December 1989, respectively. In 1989, Con-
gress authorized $40 million for implementation of non-
point source management plans, and in March 1990,
EPA awarded Maryland a $447,771 grant for FY 1990.
NPDES Permits for Stormwater Discharges
The 1987 Water Quality Act also directed EPA to promul-
gate regulations to require National Pollutant Discharge
Elimination System (NPDES) Permits for stormwater dis-
charges. It appears that numerous industries and at least
five major jurisdictions in Maryland will be required to
apply for permits. To receive permits, local jurisdictions
must have in place, among other items, programs to con-
trol pollutants from urban runoff from both existing and
new development. Final regulations are to be issued in
July 1990. Like existing NPDES programs for wastewater
treatment facilities and hazardous waste management
operations, the program is designed to be administered
by the states.
158
-------
Observations
To summarize, Maryland requires by statute and regula-
tion that local governments manage both the quantity
and quality of runoff from new development. The state
assists local governments in implementation with both
program grants and technical assistance. The state also
has established a grants program for capital projects to
address pollution problems in older areas developed
without stormwater controls. Since creation of these
programs, the state has established an extremely am-
bitious objective: a 40 percent reduction of nitrogen and
phosphorus loadings from urban runoff from existing
areas. More recently, EPA has required that the state
develop nonpoint source management plans to address
urban stormwater runoff. EPA will soon begin regulating
some stormwater systems and facilities.
Thus, the government apparatus to manage stormwater
in Maryland includes the state's regulatory program, two
grant programs, and the nutrient reduction program, all of
which now are overlain by two federal programs, one of
which is regulatory. This in itself may seem complicated,
but readers should keep in mind that this is only a partial
picture. For example, the state's Erosion and Sediment
Control Program, which in certain ways is more complex
than the regulatory program required under the
Stormwater Management Act, has not been described at
all. In addition, the Maryland Critical Areas Law estab-
lishes special stormwater-related requirements for
projects in the Critical Area (the strip of land 1,000 ft wide
that surrounds the high tide area of the Chesapeake
Bay). The Department of Environment's Water Quality
Certification Group has issued special guidance and re-
quirements for stormwater discharges into wetlands.
These brief summaries, though incomplete, provide a
good snapshot of some of the major state and federal ac-
tivities that impact the stormwater management com-
ponent of the nonpoint source management program.
IMPLEMENTATION
This section provides an overview of implementation
status for each of the programs summarized above, fol-
lowed by a subjective evaluation of overall progress.
When possible, judgments of both technical progress
(i.e., an assessment of progress toward objectives) and
administrative performance are provided.
The Stormwater Management Act and
Implementation of Local Programs
Local jurisdictions implemented stormwater management
programs in 1984, following approval of local ordinances
by the Administration. In late 1984 and early 1985, the
state completed a cursory review to determine whether
local jurisdictions had begun implementation. The data
that were collected were used to set priorities for the first
round of triennial field reviews. To date, 23 jurisdictions
have been reviewed. The Administration has reviewed all
the counties but one and Baltimore City. None of the 47
smaller municipalities that opted to implement their own
programs has been reviewed. Using the five criteria
noted above, the Administration determined that 13 of
the programs were acceptable and 10 were unaccep-
table. Since the initial review, two programs have been
brought into compliance and are now acceptable
(Table 1).
These findings require some interpretation. Per the
regulations (COMAR 26.09.01), a program is unaccep-
table if it is deficient in any of the categories mentioned
previously. In general, programs found to be deficient
had inadequate administrative procedures or documenta-
tion in files, were failing to provide adequate plan review,
were issuing waivers for too many projects, or were fail-
ing to provide adequate construction inspection. During
the first round of reviews, reviewers essentially ignored
the issue of maintenance because the program was too
new for local officials to establish a performance record
in this area. While about a third of the counties apparent-
ly were operating unacceptable programs, these data
may be misleading. Many of the findings were made 4 to
5 years ago, when programs were new and few data
were available for evaluation.
During the early reviews, programs were judged to be
acceptable if all program elements were in place. Track
records for performance evaluations are not available.
The findings of program evaluations are summarized by
year in Table 2. It is concluded from these data that the
Administration has become more stringent in its review of
local programs. This makes sense, and as local officials
gain experience, it seems reasonable to expect more of
them. However, given that almost a third of the programs
were last reviewed in 1985 and 1986 when reviews were
less rigorous, it may be that more than eight of the major
jurisdictions are not operating acceptably.
Although a number of programs may be unacceptable, it
is difficult to judge what this means in terms of environ-
mental impact. For example, a finding of unacceptable
for failure to provide adequate documentation in plan-
review files.may be nothing more than a paper deficien-
cy. On the other hand, it may be a clue that local officials
are issuing waivers in situations in which stormwater
management, or at least quality controls, ought be re-
quired. In and of itself, issuance of a waiver may not be
significant, either in terms or runoff quantity or quality.
However, the cumulative effects of waiving projects are
precisely those that the regulations are intended to
prevent.
Several problems emerged consistently during the
reviews. These include the issuance of waivers for
development of agricultural land in row crops because
hydrologic models show that runoff volumes will
decrease following development, failure to adhere to the
preference list for facilities, lack of construction inspec-
tions, failure to require submittal of as-buiit plans, lack of
159
-------
Table 1. Most Recent Sediment and Stormwater Administration Stormwater Reviews
County/
City
Allegany
AnneArtindel
Baltimore County
Baltimore City
Calvort
Caroline
Carroll
Cecil
Charles
Dorchester
Frederick
Garrett
Harford
Howard
Kent
Montgomery
Prince George's
Queen Anne's
Somerset
St. Mary's
Talbot
Washington
Wicomlco
Worcester
Date of Review
2/87
6/89
4/86
4/87
10/85
4/87
4/86
3/90
11/85
4/87
5/89
7/87
8/87
10/88
3/87
1/88
11/86
4/90
9/89
3/86
9/89
Ongoing
4/86
11/85
Finding
Acceptable
Acceptable
Acceptable
Acceptable
Acceptable
Unacceptable
Acceptable
Acceptable
Acceptable
Acceptable
Unacceptable
Acceptable
Unacceptable
Unacceptable
Unacceptable
Acceptable
Acceptable
Acceptable
Unacceptable
Unacceptable
Unacceptable
Acceptable
Acceptable
Current Status:
15 Acceptable (65%)
8 Unacceptable (35%)
(Note: Programs in Cecil and Anne Arundel Counties initially were found unacceptable but in later reviews were found to be acceptable.)
facility maintenance (including failure to maintain inven-
tories), and failure to notify homeowners' associations
that responsibility for maintenance had been transferred
to them. While some of these problems were corrected
during the review process, others will require changes in
regulations.
In assessing the review process, we also examined our
own performance. First, reviews have not been com-
pleted as frequently as required by the Stormwater
Management Act. Not only have the major jurisdictions
not been reviewed triennially (in 1990 a second round of
reviews should be completed), but only one of the 47
municipalities (Baltimore City) which elected to imple-
ment their own programs has been reviewed. The failure
to achieve timely reviews is attributable primarily to staff
shortages; only two to three individuals have been avail-
able at any one time to undertake reviews, and these in-
dividuals had other responsibilities.
The 23 reviews completed initially were conducted by
nine individuals, including several engineers, a geog-
rapher, and a planner. Despite general guidance in the
regulations, different reviewers have emphasized dif-
ferent criteria, and the reviews reflect this. We examined
each of the reviews in detail to determine if the reviewers
addressed the same program elements. We established
17 items pertinent to the review and noted whether
reviewers commented on each of these program
aspects. For example, we found that each review in-
cluded a summary comment on the quality of plan
review, but that comments about the quality of hydrologic
and hydraulic calculations were included in only 15 of the
23 reviews. Seventeen of the reviews included the num-
ber of inspectors on staff, but only eight noted the types
160
-------
Table 2. Findings of Program Reviews by Year
Year
1985
1986
1987
1988
1989*
1990*
Total
Jurisdictions
Found
Acceptable
3
4
4
1
1
2
IF
Jurisdictions
Found
Unacceptable
0
1
3
2
4
0
To
Reviews
3
5
7
3
5
2
25
* Includes one review in which one county was upgraded from
unacceptable to acceptable.
of enforcement tools available to the inspectors, and nine
reviewers included findings relative to enforcement ac-
tivity and the use of enforcement tools. Of the 17
program elements that were included in the review, the
only single program element that was mentioned explicit-
ly in each of the 23 initial reviews was the quality of plan
review and design. To ensure consistency in administra-
tion, the assessment of past reviews is used to develop
new procedures for conducting triennial reviews. These
include a requirement for annual administrative reviews
based on data supplied by each local jurisdiction in a
detailed 20-page data form.
Stormwater Program Grants-in-Aid
Data on the grants-in-aid awarded by the Administration
are presented in Table 3. Between 1985 and 1988,
Maryland awarded almost $9 million in grants-in-aid.
Twenty-one of Maryland's 23 counties have requested
and received funds, and nine of the 47 municipalities
have requested and received funds. Slightly over 82 per-
cent of the total funds have been awarded to counties,
and almost 18 percent have been awarded to
municipalities. Of the counties that have received funds,
14 of the programs were acceptable at the last review,
and seven were unacceptable. One of the two counties
that had not requested funds was unacceptable; a review
has not been completed for the other. The City of Bal-
timore is the only municipality to receive funds that has
been reviewed. In sum, 65 percent of the grants have
gone to counties with acceptable programs, and just over
17 percent have gone to counties with unacceptable
programs. Just over 6 percent of the total grants have
been given to Baltimore City, which operates an accept-
able program. Program reviews have not been com-
pleted for the other eight municipalities that have
received almost 12 percent of the total awards.
It is difficult to assess the effect that the grants have had
on jurisdictions responsible for implementing stormwater
programs, let alone the effects of the grants on mitigating
adverse effects of development on water resources, it is
not even known, for example, the percentage of each
local stormwater budget that is made up of state funds.
Thus, the extent to which state funds have helped local
jurisdictions establish successful programs cannot be as-
sessed. It is noted above that just over 17 percent of the
grants ($1.56 million) have been allocated to seven
counties that operate unacceptable programs; it is
believed that the number of unacceptable programs
would be higher if state funds were not available.
With respect to impact on the environment, enough data
are available to make a general assessment of whether
the funds are being allocated to the "right" jurisdictions.
Intuitively, organizations would hope to grant funds to
those jurisdictions where the greatest impact on the en-
vironment is occurring, which is, in this case, those with
the most development. Table 4 shows the total funds
granted to each major jurisdiction between 1985 and
1990 along with the total number of housing starts bet-
ween 1985 and 1988. Although the grants are not tied
directly to development levels, the funds would be ex-
pected to track development. This generally seems to be
the case. In most cases, the difference between the per-
centage of total funds received and the percentage of
total housing starts is very small.
The following conclusion can be made: for the smaller
jurisdictions, the percentage of funds received generally
corresponds to the percentage of housing starts.
However, among the larger jurisdictions, there is greater
variation. For example, Prince George's County has
received more than 22 percent of the total grants, al-
though just 12.2 percent of the total housing starts have
occurred within the county. For Baltimore, Howard, and
Montgomery counties and Baltimore City, the percentage
of housing starts that have occurred in the jurisdiction is
higher than the percentage of total program grants that
have been awarded to the jurisdiction. Howard County is
the only one of these five major jurisdictions that had an
unacceptable program at the time of review. It appears
that local officials in Prince George's County have been
more aggressive in seeking funds than other local juris-
dictions. One other program that stands out in this crude
analysis is St. Mary's County, which has received ap-
proximately 6 percent of the total grants awarded, al-
though the number of housing starts in the area
comprises just 2 percent of the total. Despite receiving
funds disproportionate to development activity, St. Mary's
program was unacceptable at the time of the last review.
Stormwater Pollution Control Cost Share Grants
Since 1984 the General Assembly has authorized ap-
proximately $5 million for stormwater pollution control
grants. The Sediment and Stormwater Administration
has obligated 47 grants totalling $4.97 million. The funds
have been used to support a variety of projects, including
seven infiltration facilities, 19 extended detention facilities
with wetlands, two extended detention dry ponds, eight
161
-------
Table 3. Stormwater Management Grants-in-Aid Program
The Cr«nt-fn-Aid Progra« (s designed to assist Local jurisdictions in reducing stream channel erosion, pollution, local flooding, and adverse impacts
County FIBS
Allcginy S<6.««5
AnneArun 1134,097
liltlnor* 191,554
C.lvert 132.378
Orel Ine
C»rrol 128,817
C«cll
Chtrlei 158.292
DorcheXer $30,466
Frederick HO. 552
Gtrrelt $24.877
Hirford 177,763
Kouird 182,21?
Kent 122,419
Montgooery 133,835
Prince Ceo $118,366
Oueen Anne's $38, 162
Soneriet 18,790
St.mry't 171.736
Tatbot 124,876
Uithlngton
Uleoalco 132.895
Worcester
Hunlclpilltlet
Aberdeen
Araupolis 133,021
liltoCUy $78,637
loule 16,144
Ceo&rldge $20,644
Frederick
Ocean City $32,422
RockvllU 135,789
Salisbury
FY86
$35,787
$109,994
$111,032
$30,579
$24,727
$51,982
$25,184
$25,802
$75,231
$64,518
$22,419
$113,239
$378,013
$26,125
$80.494
$27,134
$37,443
$35,246
$92,346
$29,282
$4,870
$18,250
$9,325
$36,643
$1,410
FYB7
$36,152
$138,861
$102,611
$30,399
$27,963
$50,862
$57,233
$26,380
$21,952
$26,504
$71,500
$33,989
$22,437
$95,880
$423,375
$28,720
$77,064
$13,741
$34,000
$5,688
$10,000
$38,680
$95,293
$39,472
$2.150
$9,195
$66,353
$13,153
Fvaa
$36,355
$142,122
$105,589
$31,615
$29,082
$52,896
$59,018
$15,524
$74,360
$30,510
$22,436
$128,580
$423,000
$29,869
$102.253
$35,360
$7,789
$23,385
$40,194
$99,105
$41,051
$2,236
$13,140
$33,965
$18,160
FV89
$33,080
$129,330
$109,080
$28,770
$26,460
$52,298
$63,493
$14,130
$20,770
$25,080
$76,467
$48,266
$20,420
$117,300
$384,930
$19,712
$93,100
$32,180
$21,280
$36,570
$90,180
$37,360
$2,030
$60,934
$9,950
$30,910
$16,520
FY90
$31,503
$143,800
$175,882
$43,710
$28,000
$56,409
$54,627
$15,745
$21,960
$32,577
$67,038
150,355
$18,786
$133,312
$283,132
$30,616
$108,735
131,984
$10,140
$33,092
$90,157
151,024
$52,207
$8,640
$32,671
$16,520
Total
FY85-FY90
$219,542
$798,204
$695,750
$197,451
$165,049
$212,465
$344,645
$127,429
$75,234
$134,840
$442,359
$309,855
$128,917
1622,146
12010,816
1173,204
$8,790
$533,382
165,751
$203,862
$13,477
164,805
1216,803
$545,718
$204,333
$31,930
$131,391
$82,672
$236,331
$68,141
construct!
'/. of Total
2.4X
8.8%
7.7X
2.2X
o.ox
1.BX
2.3%
3.8%
1.4%
0.8%
1.5%
4.9%
3.4%
1.4%
6.9%
22.2%
1.9%
0.0%
5.9%
0.7%
0.0%
2.3%
0.2%
0.7%
2.4%
6.0%
2.3%
0.4%
1.5%
0.9%
'2.6%
0.8%
$1175,416
$1467,075
$1599,607
$1597,594
$1600,600
$1625,000
$9065,292
162
-------
Table 4. Stormwater Management Grants-in-Aid and Housing Starts
COUNTIES
Program
Grants
TOTAL
FY 1985
FY 1990
PERCENT OF
TOTAL GRANTS
HOUSING
STARTS
1985-1988
PERCENT OF
TOTAL
Allegany
Anne Arundel
Baltimore
Calvert
Caroline
Carroll
Cecil
Charles
Dorchester
Frederick
Harford
Howard
Garrett
Kent
Montgomery
Prince George's
Queen Anne
Somerset
St. Mary's
Talbot
Washington
Wicomico
Worcester
219,542
798,304
695,750
197,451
0
165,049
108,707
344,645
127,409
75,234
442,359
309,855
134,840
128,917
622,146
2010,816
173,204
8,790
533,382
65,751
0
203,862
13,477
2.4%
8.9%
7.8%
1
1
6
22
1
2%
0.0%
1.8%
1.2%
3.8%
1.4%
0.8%
4.9%
3.5%
5%
4%
9%
0.1%
6.0%
0.7%
0.0%
2.3%
0.2%
877
15,429
21,222
3,515
954
6,698
3,252
6,242
721
7,844
11,338
15,805
1,200
399
30,342
20,121
2,182
674
3,327
1,426
2,955
2,829
3,730
0.5%
9.3%
12.8%
2.1%
0.6%
4.0%
2.0%
3.8%
0.4%
4.7%
6.8%
9.5%
0.7%
0.2%
18.3%
12.2%
1.3%
0.4%
2.0%
0.9%
1.8%
1.7%
2.3%
163
-------
wetlands, one sand filter, and 10 other practices. The
projects are at various stages of implementation.
Overall, 14 jurisdictions have received cost share grants,
including 11 counties and three municipalities. Of the
counties that received grants, four had unacceptable
stormwater programs at the time of the last review. Two
of the municipalities that received grants never have
been reviewed. As Table 5 shows, Prince George's
County has received a disproportionate share of funds
(21.7 percent), and Baltimore County has received an
unexpectedly small share (3 percent). Like the Grants-in-
Atd, the cost share program is not an entitlement
program. Since retrofits are not required by state law or
regulation, the effort put forth at the local level to identify
and rectify stormwater pollution problems varies greatly.
To a significant degree, the allocation of cost-share funds
to local jurisdictions reflects the sophistication of local
programs.
Chesapeake Bay Agreements
Regionally, implementation of the Chesapeake Bay
Agreements is being coordinated through an Interstate
Implementation Committee. In Maryland, the Sediment
and Stormwater Administration has been designated as
the lead agency for nonpoint source pollution controls.
An Interagency Steering Committee has been estab-
lished to coordinate all statewide efforts to control all
types of nonpoint source pollution, including nutrients,
conventional pollutants, and toxics. The Committee
presently is updating Maryland's Nutrient Reduction
Plan, which is the best-developed statement of the
state's overall efforts to control pollution in the Bay. Sec-
tions of the Nutrient Reduction' Plan concerning nonpoint
pollution have been extracted and used to develop
Maryland's nonpoint source management plan for EPA
pursuant to Section 319 of the Water Quality Act.
Specific implementation activities have included exten-
sive retrofit efforts in selected or targeted watersheds.
EPA Nonpoint Source Control Programs
While the State of Maryland has been active in
stormwater management, direct federal support for im-
plementation of related nonpoint source management
programs has evolved more recently. Maryland has
redefined existing programs to control nonpoint pollution
in the Bay, particularly the Chesapeake Bay nutrient
reduction plan, to fit into the framework outlined by EPA
pursuant to Section 319 of the Clean Water Act. In March
1990, Maryland received its first nonpoint source im-
plementation grant. Projects, activities, and items funded
include:
• One staff position to coordinate nonpoint source
programs
• Two staff positions to implement stormwater utilities
• One stormwater retrofit project manager
• Four agricultural soil conservation planners
• Ground-water modeling study
• Demonstration wetlands joint use project
• Cooperative Extension Service nonpoint source
conference
Table 5. Stormwater Pollution Control Cost-Share Grants by County
County
Allegany
Anne Arundel
Baltimore
Cah/ert
Caroline
Dorchester
Harford
Howard
Kent
Montgomery
Prince George's
Baltimore City
Crisfield
Ocean City
Total
Number of
Projects
1
5
2
1
1
2
4
1
1
9
12
3
1
4
47
Total Funds
$65,000
777,000
147,000
24,578
25,000
320,908
416,750
37,500
45,000
826,000
1,080,000
628,508
303,750
272,400
$4,969,394
Percent of Funds
1 .3%
15.6
3.0
0.5
0.5
6.5
8.4
0.8
0.9
16.6
21.7
12.6
6.1
5.5
1 00.0 %
164
-------
These projects were identified by a statewide, interagen-
cy task force that was created to guide implementation of
projects funded by EPA. As is evident from the projects,
about half of the programs are for projects related to
urban nonpoint source programs. The coordinator posi-
tion will be based in the Sediment and Stormwater Ad-
ministration to strengthen existing programs. The staff to
assist with utilities will build on ongoing technical assis-
tance activities to help local jurisdictions identify ade-
quate financing for programs, and the stormwater retrofit
project manager will improve the existing cost-share
program by strengthening management capabilities, in-
cluding capabilities for project evaluation. At this time, it
is anticipated that funds will be available under Section
319 for the next three or four years and that in years
hence, funds will be used increasingly for implementation
of capital and educational projects.
NPDES Permits for Stormwater Discharges
EPA expects to issue final regulations for implementation
of the permit system in late July or August 1990. The
State of Maryland has determined that municipal permits
will be issued by the Sediment and Stormwater Ad-
ministration, and industrial permits will be issued by the
Hazardous and Solid Waste Management Administra-
tion. While details of the permitting program have not yet
been developed, it is clear that implementation of the
program will require substantial effort and resources not
currently available to the Administration.
Administration
Primary responsibility for implementation of the
Stormwater Management Act initially was delegated to
the Sediment and Stormwater Division within the
Maryland Department of Natural Resources (DNR). In
1984 the Division included only three staff members. In
1987 a new Department of the Environment (MDE) was
created, and programs were transferred from DNR to
MDE. The Division was elevated to the Sediment and
Stormwater Administration (SSA), an organizational leap
of two steps. The Administration now includes three
programs: 1) the Policy and Evaluation Program, which
is responsible for local program reviews, 2) the Construc-
tion Management Program, which administers the two
state grant programs, and 3) the Compliance Program,
which is responsible for sediment and erosion control in-
spection and enforcement and is the largest program.
Table 6 includes a summary of the Administration budget
and number of staff for fiscal years 1987 through 1991.
The budget remained relatively constant between FY
1987 and FY 1989, but increased significantly between
FY 1989 and FY 1991. The growth primarily has been for
more inspectors to strengthen the erosion and sediment
control inspection and enforcement programs.
The Compliance Program is by far the largest in the Ad-
ministration, accounting for over two-thirds of the staff (in
FY 1990), very few of whom have any involvement with
stormwater management. The Construction Management
Program is the second-largest in terms of budget and
personnel. The FY 1991 budget figures for this program
include, however, about $1.6 million for the Stormwater
Program Grants-in-Aid, about 89 percent of the Program
budget. The Policy and Evaluation Program, which has
primary responsibility for review of local stormwater
programs, is the smallest of the three programs. It ac-
counts for fewer than 10 percent of the Administration
employees and about 12 percent of the Administration
Budget. The division responsible for review of local
programs currently includes only three staff members.
Excluding administrative and clerical staff, approximately
five to six technical staff (planners and engineers) actual-
ly work to administer stormwater regulations and grant
programs. No new positions have been authorized to the
Administration specifically for development of programs
to achieve the 40 percent reductions in nutrients in urban
nonpoint source loadings to the Bay, although the sedi-
ment and erosion control initiatives work towards this
goal. Since the Sediment and Stormwater Administration
has been designated the lead agency in Maryland to ad-
minister EPA's nonpoint source programs, the Section
319 grant will fund four additional staff people in the
SSA. The SSA also has been assigned responsibility for
development and administration of the NPDES system;
however, no positions have been authorized to assist
with development of the program.
LESSONS LEARNED
To sum up, the state has made significant investments in
managing stormwater. Since 1984, the state has
awarded $9 million in program grants-in-aid and about $5
million for pollution control cost share projects. It is es-
timated that the annual costs to administer these
programs (including stormwater regulatory reviews) is
about $1 million annually. These investments have
resulted in significant progress: all the counties have im-
plemented programs. Literally thousands of best
management practices (BMPs) have been built in
Maryland. Most of these are functioning, though perhaps
not as designed. With respect to existing programs, a
number of areas need to be improved, at both local and
state levels. The pending stormwater regulations have
the potential to significantly impact the Administration's
current operations and budget. It is unlikely that im-
plementation of new federal permit requirements will
proceed smoothly. For example, the draft regulations
specify that, to obtain a permit, local governments must
have water-quality monitoring and modeling programs as
well as stormwater management programs, sediment
and erosion control programs, and retrofit programs
similar to those already in place in Maryland. These will
require significant new resources.
165
-------
Table 6. Sediment and Stormwater Administration, Staff and Budget
Fiscal Year
1987
1988
1989
1990
1991
Budget ($ Million)
Policy and Evaluation
Construction Management
Compliance
Other Grants and Administration
Total Budget
Permanent Positions
Policy and Evaluation
Construction Management
Compliance
Other Grants and Administration
Permanent Positions
3.3
46
3.2
44
3.4
4.1
43
58
0.6
1.8
1.4
1.1
4.9
5
8
39
6
58
The following observations should be noted.
• State law and regulations are making a difference.
On-site controls are helping to mitigate the effects of
urbanization. With respect to pollution control,
however, these controls simply slow the rate of pollu-
tion. BMPs are not 100 percent effective. Regulators
and Stormwater managers should clearly communi-
cate the limitations of the practices that are being
used.
• Effective Stormwater management requires a com-
mitment by elected decision makers at the local
level. Despite the existence of state regulations and
technical assistance activities, a number of programs
at the local level in Maryland are not acceptable.
This probably results, in large part, from the failure of
local officials to allocate adequate resources to the
programs. This is particularly a problem in moderate-
ly populated jurisdictions that now are experiencing
significant growth.
• Given that BMPs have limitations in their ability to
control pollutants, growth management must be
viewed as a key element of nonpoint source control
efforts. Planning at the watershed level to mitigate
against nonpoint source pollution will be required for
efficient allocation of scarce resources. For example,
major, yet-to-be defined elements of Maryland's
Nutrient Reduction Plan involve definition of growth
management objectives through watershed planning
processes.
The State's plans for implementation of the federal
NPDES program are not well developed. It is not
known at this time exactly what the regulations will
require or the number of people that will be required
to administer the permit system. According to
timetables set forth by EPA, implementation should
be occurring soon.
Finally, the Maryland experience suggests that
evolution of programs will be required to control
urban nonpoint source pollution effectively. Despite
the existence of path-breaking regulations and sig-
nificant financial and technical assistance, there
have been problems with implementation. Recogni-
tion of the pervasiveness of the nonpoint source
problem and the limitations of even innovative struc-
tural approaches leads to the conclusion that growth
management approaches are essential. Maryland's
program must evolve to incorporate these. Respond-
ing to federal regulatory requirements will require ad-
ditional new elements in the state's Stormwater
programs, and continual evaluation and reevaluation
will be essential to achievement of objectives.
166
-------
THE CLEAN COLORADO PROJECT AND URBAN NONPOINT SOURCE
POLLUTION CONTROL: THE LCRA PROGRAM
Patrick Hartigan and Kolleen Wilwerding
Environmental Quality Division
Lower Colorado River Authority
Austin, Texas
BACKGROUND
The Lower Colorado River Authority (LCRA) is a soil and
water conservation district that was created in 1934 by
the Texas legislature to manage the resources of the
lower Colorado River. The LCRA has a 10:county
statutory district encompassing some 9,800 mi of the
Colorado River basin from San Saba County in Central
Texas to Matagorda Bay on the Texas coast. The agen-
cy has a 15-member board of directors appointed by the
governor, with each director serving a six-year term. Bet-
ween 1935 and 1951, the Authority constructed a series
of dams that created a chain of reservoirs in Central
Texas known as the Highland Lakes. These lakes
provide water supply, hydroelectric power, flood control,
tourism and recreational opportunities, and wildlife
habitat for the region.
One of the main goals of the LCRA is to protect the water
quality of the Colorado River. In order to develop and im-
plement aggressive and innovative strategies to protect
and enhance the water quality of jts district, LCRA
launched the Clean Colorado project in 1988. The Clean
Colorado project is a multifaceted project that includes
LCRA's nonpoint source pollution prevention program,
an extensive water-quality monitoring program, scientific
research projects to determine the effectiveness of
water-quality management strategies, and a public infor-
mation and education program that includes a citizen-
based water-quality monitoring program.
Although water-quality protection has traditionally meant
the addressing of wastewater issues, a recognition has
developed in recent years for the need to control non-
point source (NFS) pollution. An analysis of LCRA's
monitoring program shows that over 90 percent of the
pollution in the Highland Lakes is NFS in origin. LCRA
estimates that the NFS loads in the Lake Travis basin
could increase on the order of 200-600+ percent in the
future, largely due to the conversion of rangeland to
urban and suburban development. While the exact ef-
fects of this increase are not well known, intuitively it ap-
pears the impacts could be severe. Already there is
some noticeable degradation resulting from new
development, especially following heavy rainfalls when
turbidity and sedimentation increase.
Responding to the need to protect the quality of the
reservoirs in the face of this continuing urban develop-
ment, the LCRA began exercising its pollution control
powers in the 1980s. A key step was the development of
the Water Quality Leadership Policy in 1988 by the board
of directors, which mandated that LCRA take the lead
role in controlling NFS pollution in its 10-county district,
beginning with the Highland Lakes. The policy discus-
sions made it clear that pollution prevention would be the
basis of LCRA's programs, along with a "polluter pays"
philosophy. An extensive public education program was
conducted in 1988 and 1989, including the production of
a 30-minute video titled "Pointless Pollution: America's
Water Crisis," narrated by Walter Cronkite. Realizing that
public education alone would not be sufficient to protect
the lakes, LCRA proposed in 1989 to develop a
regulatory program for the Lake Travis watershed in
Travis County. This proposal received widespread public
and private support, and the Lake Travis Nonpoint
Source Control Pollution Control Ordinance was adopted
by the LCRA Board of Directors in December 1989. The
Ordinance went into effect on February 1, 1990, and ex-
pansion of the ordinance to the other Highland Lakes is
expected to occur in 1991. The Ordinance targets new
urban and suburban development for an area of ap-
proximately 250 mi2 in western Travis County. The or-
dinance exempts agriculture and existing development.
The Lake Travis Ordinance establishes a set of "perfor-
mance" standards that require new development to
remove a specified amount of the annual NFS pollution
load, depending on the site's proximity to the shoreline
and the slope of the property, as shown in Table 1. Sites
within 500 feet of the lake and/or those on steep slopes
require a higher level of runoff treatment than inland or
flatter sites. In general, the more intensively a site is
developed, the more pollution must be removed. This ap-
proach acknowledges the link between land use and
NFS pollution. However, there are no land use control
stipulations in the ordinance, as LCRA's mandate is to
167
-------
protect water quality and not to control land use. A Tech-
nical Manual has been developed in conjunction with the
Ordinance, which provides criteria on how to meet the
Ordinance's standards. The manual does not mandate
specific practices, as its intent is to provide guidance and
recommendations on options for achieving the perfor-
mance standard.
DEVELOPMENT OF THE ORDINANCE
STANDARDS
II was the LCRA's goal to develop a set of performance-
based standards that were strict but feasible, readily un-
derstood, and easily enforceable. Several steps were
taken to develop these standards.
First, LCRA defined three specific pollution problems
which the Ordinance targets for control:
1. Sedimentation—primarily caused by construction site
runoff and streambank erosion
2. Eutrophication—resulting from nutrients in urban
runoff (e.g., landscaping and golf courses)
3. Toxics—such as pesticides, oil and grease from
parking lots and roads, and heavy metals from urban
areas
LCRA investigated three possible approaches to control
these problems:
1. Set effluent standards for runoff.
2. Establish technology-based standards to treat runoff.
3. Set receiving water-quality standards.
An important aspect of LCRA's approach is that it in-
tegrates water quantity and quality control, since conven-
tional flood detention basins should also be designed to
accomplish water-quality treatment.
Option 1 was not considered viable due to the extreme
variability of flows and pollutant concentrations, the un-
predictable nature of runoff events, and the difficulty of
monitoring for compliance.
Option 3 would "be the preferred approach, but our
knowledge of the lake's dynamics are currently too
limited to develop such standards. In particular, the
trophic dynamics and transport fate of pollutants are
poorly understood.
Option 2 has been adopted at this time with the intent of
eventually linking technology-based standards to desired
receiving water-quality conditions. By technology-based,
LCRA means the use of best management practices, or
Table 1. Percent of the Annual Pollutant Load, Over Predevelopment Conditions, That Must be Removed
Property
Location
Inland
Near shore
(within 500 ft
of 691 msl)
Slope of
Property
under 1 0%
10-20%
over 20%
under 1 0%
10-20%
over 20%
Total
Suspended
Solids
70%
80%
90%
75%
90%
90%
Total
Phosphorus
70%
75%
85%
75%
85%
85%
Oil&
Grease
70%
75%
85%
75%
85%
85%
Notes:
1. Oil and grease standards apply to commercial and multifamily development only.
2. Inland property located more than 500 ft from the 691-ft msl contour measured horizontally in a direction away
from the lake surface.
3. Near-shore property is located within 500 horizontal ft of the 691 -ft contour.
To summarize the sequence one must follow to meet the performance standard:
- Determine what the performance standards are for TSS, TP, and O&G (if commercial or multifamily) based on the slope
of the site and its proximity to Lake Travis.
- Calculate the annual pollutant loads for the site for both pre- and postdevelopment conditions.
- Determine the streambank erosion control volume requirement.
- Screen the BMPs in the Technical Manual and select ones which, separately or together, can meet the pollutant
removal requirements.
- Proceed with a detailed design of the site and BMPs.
168
-------
BMPs. Examples of BMPs are vegetative filter strips,
sedimentation ponds, silt fences, and even source reduc-
tion techniques, such as street sweeping and low-
maintenance landscaping.
The technology-based approach was then linked to the
three targeted problems by developing standards to:
1. Control sedimentation from construction sites by re-
quiring temporary erosion and sedimentation
controls.
2. Control streambank erosion by using permanent
BMPS to control the release of stormwater flows
from developed sites—recognizing that streambank
erosion is often the largest source of sediment.
3. Remove pollutants in stormwater by treating runoff
with permanent BMPs. The BMPs used for runoff
treatment may be the same BMPs used to control
streambank erosion.
To meet the first standard, a temporary erosion control
plan must be developed using BMPs such as silt fences,
brush berms, rock berms, and sediment ponds.
The second standard, controlling streambank erosion,
evolved from studies indicating that low-frequency
storms (e.g., less than two-year return periods) may
largely define the shape and characteristics of natural
channels (1). The Ordinance currently requires that the
one-year storm be detained for a period of 24 hours to
control streambank erosion. The intent here is to retain
the natural hydrologic flow regime to the fullest extent
possible.
The third standard, treating pollution in the runoff, was
developed by investigating the relationship between the
pollutant removal efficiencies of BMPs and the increase
in pollutant loads resulting from development. The
primary goal was to develop an easily understood proce-
dure that allowed land developers to quickly assess their
sites by estimating pollutant loads, comparing those
loads with the performance standards, and selecting
BMPs that would reduce the pollutant loads to the perfor-
mance standard levels. Several steps were required to
develop this standard, as summarized and discussed in
the following:
1. Select parameters that are indicators of the pollution
problem targeted by the Ordinance.
2. Develop a methodology to estimate pollutant loads.
3. Evaluate the effectiveness of BMPs to treat the in-
dicator pollutants.
4. Apply the BMPs to various development scenarios to
select feasible performance standards.
STEP 1. SELECT INDICATOR PARAMETERS
The following indicator parameters in stormwater runoff
were selected for treatment by the Ordinance:
a. Total Suspended Solids (TSS) as an indicator of
sedimentation
b. Total Phosphorus (TP) as an indicator of
eutrophication
c. Oil and Grease (O&G) as an indicator of toxics
The advantage of using these indicator parameters is
that they represent the range of suspended, soluble, and
colloidal pollutants. Thus, BMPs designed to treat these
three pollutants will also treat a wide range of other
pollutants.
STEP 2. ESTIMATE POLLUTANT LOADS
A simple loading equation was developed which is the
product of annual runoff volume and the average annual
stormwater pollutant concentration:
L =AxRFxRvxCxK
where:
L = Annual pollutant load in pounds
A = Area of site in acres
RF = Annual rainfall in inches (32.5" assumed)
Rv = Annual average runoff-to-rainfall ratio
C = Annual average pollutant concentration
in mg/L
K = A conversion factor (0.2266)
This load is the annual pollutant load for an average year
of rainfall. In order to maintain consistency and fairness
for all developments, LCRA has defined rainfall (RF),
runoff coefficient (Rv), and pollutant concentrations (C).
This also streamlines the administrative review process.
The area used in this calculation is the developed area of
the site, not the total area. This distinction is made to
clarify the intent of the Ordinance, which is to treat runoff
from developed areas. Runoff from undeveloped land is
considered as the natural "background" load. For urban
development, the amount of impervious cover is the best
index for estimating runoff volumes and, indeed, is the
best indicator of urbanization overall. A national runoff
equation was adopted (1):
Rv = 0.05 + (0.009 x 1C)
where:
1C is the percent impervious cover of the
developed area
Next, pollutant concentrations had to be defined, and a
review of both local and national data was conducted.
The LCRA concluded that there is a difference in con-
centrations between developed and undeveloped land.
However, there is no conclusive evidence that a dif-
ference exists in concentrations for different types of
developed land (i.e., residential concentrations are as-
sumed to equal commercial concentrations). Table 2
169
-------
shows pollutant concentrations, in mg/L, which were
defined for the Ordinance (2,3,4):
As more local data are collected it is likely that these as-
sumed concentrations will be revised.
Table 2. Pollutant concentrations
Indicator Parameter
Background Developed
Conditions Conditions
(mg/L) (mg/L)
Total Suspended Solids (TSS) 48 130
Total Phosphorus (TP) 0.08 0.26
Oil and Grease (O&G) 0 15
STEP 3. EVALUATE EFFECTIVENESS OF BMPS
A wide variety of BMPs were evaluated for their ability to
treat urban runoff. Some BMPs can theoretically achieve
removal efficiencies of 60 to 80 percent. The efficiency of
BMPs varies not only with the pollutant of interest but
also with the volume of runoff captured. As impervious
cover increases, the capture volume of a BMP must also
increase to maintain an equivalent level of treatment.
In order to achieve high levels of treatment for all three
parameters, the use of multiple BMPs was considered a
viable option. This concept is somewhat controversial as
there is very little information available to estimate the
removal efficiency of multiple BMPs. The LCRA has cur-
rently adopted a simple method to calculate the removal
efficiency of multiple BMPs by assuming that the cumula-
tive efficiency is the product of the individual BMP
efficiencies:
Etot
where:
{1 - ((1 - Ei/100) x (1 - Ł2/100))} x 100
= Annual pollutant removal efficiency
Ei » Annual removal efficiency of first BMP
Ea » Annual removal efficiency fo second BMP
For example, if EI has a removal efficiency of 60 percent
and Ea a removal efficiency of 40 percent, the total
removal eficiency would be calculated to be:
Etot - {1-((1-0.6)x(1-0.4))}x100, or
Etot - 76%
It is a high priority of LCRA's to determine the validity of
the assumption made for sequential BMPs.
LCRA's Technical Manual provides extensive criteria for
selecting various BMPs, and assigns annual pollutant
removal efficiencies for each. In addition to BMPs
described in the manual, other BMPs will be considered
on a case-by-case basis.
STEP 4. APPLY BMPS TO DEVELOPMENT
SITES
A variety of land use and BMP scenarios were simulated
in order to investigate potential reductions of annual pol-
lutant loads. There was a considerable interest in relating
the performance standards to predevelopment conditions
and maintaining those conditions to the fullest extent
possible. This does not appear to be feasible in a num-
ber of cases with medium to high development intensity.
In addition to the land use and BMP simulations, there
were extensive discussions with public and private inter-
ests. A citizens' technical advisory committee was also
formed to assist in the development of the ordinance
standards. The performance standards that were finally
adopted, as shown in Table 1, reflected the input of a
large and diverse group of people. Some of the features
of the performance standards are:
• Implementation of a sliding scale that recognizes the
increased likelihood of pollution from steeply sloped
sites and/or those located in close proximity to the
lake
• The O&G standard is required only for multifamily
and commercial development, based on recommen-
dations by Silverman and Stenstrom (5)
• The annual NPS pollution load to be treated is the
difference between the total annual load and the
predevelopment "background" load
It was discovered that low-intensity sites could, in many
cases, reduce loads to pre-development levels by simply
using vegetative filter strips. In response to this, an "Al-
ternative Standard" was developed for large-lot residen-
tial development; this does not have the extensive design
and engineering requirements of the performance stand-
ard process.
ADMINISTRATION OF THE ORDINANCE
The Ordinance requires all land owners/developers who
are proposing to develop land within the Lake Travis
watershed in Travis County to submit an application for
review and plans on how the surface water runoff from
the site will be handled. The plan must include the.
following:
• A temporary erosion and sedimentation control plan,
including a restoration plan for all disturbed areas
• Descriptions, calculations, locations, and design
details of BMPs used to meet the performance
standards
• Establishment of a maintenance organization to en-
sure that the BMPs are properly maintained
170
-------
• A letter of credit to cover the cost to correct problems
associated with the site's pollution controls
A fee schedule has also been established which lays out
review and inspection fees to recoup a portion of the
program's administrative costs. LCRA conducts inspec-
tions of development sites to ensure compliance with the
Ordinance. LCRA has several legal options available to
ensure compliance:
• Stop-work order for nonpermitted sites or those out
of compliance with the permit
• Permit revocation if compliance with stop-work or-
ders does not occur within 10 days of posting
• Penalties ranging from $500 to $10,000 per day per
violation
• Injunctions
The application process itself takes approximately 30 to
90 days to complete. There is a public notice require-
ment for properties situated within 500 feet of the
development site.
One of the key features of the Ordinance is that there are
no variance provisions, though direct appeals to the
LCRA Board of Directors are allowed. The LCRA
decision not to include a variance provision was in
response to the recognition that variance procedures
have, in some cases, seriously weakened the intent of
other regulatory programs.
EVALUATION OF THE ORDINANCE
There was strong support at the time the Ordinance was
adopted to have it evaluated on a periodic basis. The
evaluation is needed not only to check its compliance
record but also because much of the criteria in the Or-
dinance and Technical Manual has not been locally
verified. LCRA has thus embarked on a program to
monitor and model Lake Travis and the Ordinance. This
evaluation is being conducted jointly by LCRA and the
U.S. Environmental Protection Agency, the U.S. Geologi-
cal Survey, and private consultants.
This project will attempt to provide answers to and/or in-
sight into the following questions:
1. Will the ordinance standards be adequate for
protecting the water quality of Lake Travis?
2. Will the standards actually be met by the best
management practices (BMPs) required by the or-
dinance?
To answer these questions, a set of objectives has been
formulated foreach, as presented in the following:
Objective 1. Evaluate the factors that determine the
water-quality conditions of Lake Travis
Objective 2. Establish a cause-and-effect relationship
between land use and pollution protec-
tion/control strategies with receiving water
quality
Objective 3. Monitor the compliance record of develop-
ment regulated under the ordinance to
determine whether the standards are being
met
This is a five-year project with preliminary findings
scheduled to be reported in early 1993.
SUMMARY
LCRA's Lake Travis NPS Control Ordinance was
developed to protect Lake Travis from sedimentation,
eutrophication, and toxics problems caused by
stormwater runoff. Using a technology-based approach,
the Ordinance requires new urban and suburban
development to remove a large percent of its annual
NPS pollutant load (from 70 to 90 percent in most
cases). The Ordinance became effective in February
1990 and is currently being evaluated for effectiveness.
The work described in this paper was not funded by the
U.S. Environmental Protection Agency, and therefore the
contents do not necessarily reflect the views of the agen-
cy and no official endorsement should be inferred.
REFERENCES
1. Schueler, T. R., 1987. Controlling Urban Runoff: A
Practical Manual for Planning and Designing Urban
BMPs, Metropolitan Washington Council of Govern-
ments, Washington, DC, July.
2. Chang, G. C., J.H. Parrish, and C. Soeur, 1988.
Modeling Studies for the City of Austin Stormwater
Monitoring Program, City of Austin, Department of
Environmental Protection, Austin, TX, October.
3. City of Austin, 1990. Stormwater Pollutant Loading
Characteristics for Various Land Uses in the Austin
Area, Environmental and Conservation Services
Department, Austin, TX.
4. United States Environmental Protection Agency,
1983. Results of the National Urban Runoff Program:
Volume 1—Final Report, Water Planning Division,
Washington, DC, December.
5. Silverman, G. S., and M.K. Stenstrom, 1988. Source
Control of Oil and Grease in an Urban Area,
Proceedings of Engineering Foundation Conference
Design of Urban Runoff Quality Controls, American
Society of Civil Engineers, New York, NY.
171
-------
REGULATION THROUGH LOCAL LEVEL NEGOTIATION—A SUCCESSFUL
APPROACH TO CONTROL OF NONPOINTSOURCE POLLUTION
Catherine Tyrrell
Santa Monica Bay Restoration Project
Monterey Park, California
INTRODUCTION
In November 1990, an article appeared in the Los An-
geles Times lauding Environmental Defense Fund Ex-
ecutive Director Fred Krupp for negotiating a deal with
McDonald's to end the fast-food chain's use of poly-
styrene foam packaging (L.A. Times, November 12,
1990, View Section, page 1). Krupp is quoted saying
"...We may be entering a new era of environmental
problem-solving by negotiation."
The Santa Monica Bay Restoration Project applied a
similar strategy when it brought together a group of its
Management Committee members representing
stormdrain operators, environmentalists, and regulatory
agencies to develop a program to control urban runoff
into Santa Monica Bay.
This paper discusses: 1) the importance of negotiated
regulation for solving nonpoint source pollution problems,
2) the process that was used to negotiate a permit to
control urban runoff into Santa Monica Bay and adjacent
coastal waters in the Los Angeles area, 3) the elements
thai were crucial to the negotiations, and 4) the sub-
stance of the resulting permit.
THE IMPORTANCE OF NEGOTIATION
Effective control of urban runoff is difficult. It makes good
sense, therefore, to use a negotiated strategy. Some of
the barriers to effective control include: 1) the diffuse
sources of the problem (e.g., atmospheric deposition and
tire residues on roads, runoff from fertilized lawns, and
automobile oil); 2) the need for individualized solutions
specific to each watershed's mix of sources, land uses,
rainfall patterns, and receiving water beneficial uses; and
3) in the case of metropolitan Los Angeles, the overlap of
multiple city/county jurisdictional responsibilities for
stormwater system operation and maintenance.
Negotiation can be very useful for lifting barriers to effec-
tive urban runoff control for several reasons:
1. To be effective, solutions must be customized;
negotiation allows for customization.
2. To be effective, solutions must be "owned" by the
agency responsible for implementation; negotiation
allows for the development of "ownership" of the
solutions.
3. To be effective, solutions must be financed creative-
ly; federal and state government cannot afford to pay
for implementation and substantive enforcement.
Negotiated programs can be phased in to allow for
the possibility of a realistic funding strategy at the
local level.
THE PROCESS
Santa Monica Bay was included in the National Estuary
Program (NEP) in 1988 .in recognition of its nationally
significant and unique resources. Bay pollution problems
attributed to urban runoff provided the impetus for the
Santa Monica Bay Restoration Project (the NEP for
Santa Monica Bay) to work toward a program to control
pollution, urban runoff, and stormwater discharges into
Santa Monica Bay and other coastal waterbodies in the
county.
An important component of the Santa Monica Bay Res-
toration Project is its Management Committee, co-
chaired by a member of the State Water Resources
Control Board and by the Director of U.S. EPA Region 9
Water Management Division, and composed of other
regulatory and governmental agency heads, environmen-
tal organizations, industry leaders, and elected officials at
the local, state, and federal levels. This diverse group,
along with a technical and a public advisory committee,
is responsible for developing a Comprehensive Conser-
vation Management Plan for Santa Monica Bay.
The Santa Monica Bay Restoration Project Management
Committee membership includes the key players who
were needed to negotiate a set of requirements and a
172
-------
compliance schedule for implementation of urban runoff
and stormwater management. The Los Angeles Regional
Water Quality Control Board, the U.S. EPA Region 9,
Los Angeles County, and other cities (principally Los An-
geles and Santa Monica) are all represented on this
panel. Key environmental organizations also involved in
the early discussions included Heal the Bay and the Sier-
ra Club. The Management Committee served as an in-
tegral mechanism for informal discussions and conflict
resolution between the involved parties.
THE INGREDIENTS
A successful negotiation requires that all players have a
reason to come to the table. Initially, the County of Los
Angeles' Department of Public Works-^he owner/operator
of over 2,000 mi of stormdrains in the county—was not in-
terested in entering into a National Pollutant Discharge
Elimination System (NPDES) permit with the Regional
Water Quality Control Board earlier than would be re-
quired under anticipated federal Water Quality Act
regulations. Public works officials through their national
association had even considered filing suit against the
federal regulations, citing them as unworkable and cost-
prohibitive given the area's rainfall conditions, as well as
the size, extent, and jurisdictional complexity of Southern
California's stormdrain system.
On the other hand, the city of Los Angeles, the
owner/operator of approximately 1,100 mi of stormdrains,
was interested in pursuing an early permit as provided
for in the Water Quality Act. In recent legal settlements
with EPA and the state of California that stemmed from
sewage treatment violations, the City agreed to not only
correct its sewage treatment problems, but also to begin
clean-up of stormdrain pollution. Management changes
brought about as a result of the legal settlements thus
created the impetus for the City to act proactively on
stormwater pollution control.
Discussions between city and county public works offi-
cials (who together serve a population of more than 8
million), along with an assessment by a Bay Project
Committee of the merits of pursuing an early permit,
resulted in consensus. The County, as the principal per-
mittee, agreed to'pursue an early NPDES permit not only
for the Santa Monica Bay Watershed, but for the whole
of Los Angeles County. All 86 cities in the county would
be eventual co-permittees, with the city of Los Angeles
and other Santa Monica Bay Watershed cities as first
phase co-permittees.
Important factors that convinced county officials to under-
take negotiations for an early permit included: 1) agree-
ment to use a National Association of Flood and
Stormwater Management Agencies recommendation as
the starting point for permit development; 2) strong en-
couragement and commitment to participate in the
negotiations by high-level management at the regulatory
agencies; and 3) consensus that a locally developed
program would not only be less expensive than the
federal model, but also more effective.
Negotiations began once agreement to pursue an early
permit occurred at the end of 1989, and the process cul-
minated with the adoption of the permit by the Regional
Water Quality Control Board in June 1990.
THE PROGRAM
The resulting permit divides Los Angeles County's five
drainage basins into three areas. Programs to be carried
out under the permit are phased in, by area, over three
years.
During the first year, each of the cities in the first phase
area are required to submit information on stormwater
quality, rainfall amounts, and land-use patterns to deter-
mine the sources of stormwater pollution. They are also
required to implement early action programs.
In the second year, the county and cities must begin to
monitor stormwater discharges based on an approved
monitoring plan, establish a timetable to clean up the pol-
lution, and stop illegal discharges.
In the third year, local governments must show that they
have followed through on their monitoring programs and
cleanup plans and have begun to implement specific
programs that will be successful in controlling stormdrain
pollution from identified sources.
By the end of the five years, all of the 86 jurisdictions in
Los Angeles County will have completed first and second
year work, and some 60 will have completed third year
work as well.
Although supported by Heal the Bay and the' Sierra Club
as a "start" on solving the stormdrain pollution problems
of the area, the permit has been challenged by Natural
Resource Defense Council primarily on the grounds that
permit requirements exclude specific limits on con-
taminants in stormwater. Both state and federal
regulators contend that existing numerical limits cannot
be translated to standards for stormwater at this time. In
defense of the permit, the Regional Board stated in a
recent letter to the State Water Resources Control Board
that, "Faced with hard choices, that of issuing no permit
and having to go through yet another rainy season with
no controls whatsoever, or issuing a permit which,
despite its imperfections, attempts to reduce pollutants in
stormwater discharges in a systematic manner, the
Regional Board elected the active approach." A final
decision by the State Water Resources Control Board is
expected shortly. In the meantime, the County and other
Santa Monica Bay Watershed jurisdictions are proceed-
ing with meeting permit requirements.
173
-------
SUMMARY
Negotiation resulted in a workable stormwater program
tailored to the distinct structure and conditions of Los An-
geles County. The effort represents a significant ac-
complishment by regulatory and implementation
agencies to address the threat to water quality posed by
nonpoint sources of pollution, described by EPA Director
William Reilly as "one of the greatest failures of environ-
mental policy in the United States" (EPA Nonpoint
Source News-Notes, February 1990, page 1). Although
contested by one environmental group, the NEP process
as carried out by the Santa Monica Bay Restoration
Project resulted in support and cooperation from other
key Los Angeles environmental groups and early pro-ac-
tive steps, by governmental agencies, and can be con-
sidered a major success for Los Angeles.
174
-------
WORKING WITH LOCAL GOVERNMENTS TO ENHANCE THE EFFECTIVENESS OF
A BAYWIDE CRITICAL AREA PROGRAM
Jennie C. Myers
Land Management Project
Providence, Rhode Island
INTRODUCTION
As a component of its Comprehensive Conservation and
Management Plan (CCMP), the Narragansett Bay
Project (NBP) is defining an approach to land use prac-
tice for water quality protection and enhancement that
will involve focused attention to specific resource area
management needs. It is clear that land use practice will
continue to be the fundamental factor in the state's ability
to approach several key CCMP goals: improved control
of nonpoint source pollutant inputs to the Bay, protection
and restoration of habitat, and preservation of coastal ac-
cess and recreational amenities.
The Land Management Project (LMP), a U.S. EPA Office
of Marine and Estuarine Protection Action Plan program,
has been working with local communities during the
mandatory statewide comprehensive planning process to
apply results of NBP-sponsored research on land
use/water quality relationships. Dealing with the inter-
secting issues of growth management, land use, and
nonpoint source pollution control, the Project has
promoted the development of technical tools and
strategies that may be important to implementation of a
critical area program, and has been given a primary role
in program design.
Although the specific structure and content of the critical
area program under discussion will not be submitted for
NBP Management Committee review until April 1990,
several basic policy initiatives and program elements
have taken shape. The following sections outline poten-
tial elements of the proposed critical area program that
have been submitted by the author to the NBP. Sub-
sequent parts review the applicability of specific LMP ef-
forts to critical area management in the Narragansett Bay
basin and other developing watersheds.
BACKGROUND: THE CRITICAL AREA
CONCEPT
A detailed examination of critical area programs and spe-
cial area management initiatives in 12 states suggests
that these approaches can offer a versatile means of
protecting numerous public values, including public
health and safety; quality, productivity, and uniqueness
of natural characteristics; scenic and landscape values;
recreational importance; and historical, archeological,
and cultural significance. The programs have also been
able to consider in a timely fashion both the magnitude of
economic issues and the irreversibility of resource im-
pacts. A broad range of statutory authorities, jurisdiction-
al coverages, and implementation strategies have been
effective in addressing needs ranging from resolution of
complex harbor-use conflicts to control of construction
practice on fragile slopes.
Critical area programs appear to offer numerous ad-
vantages: the means to seize opportunity in the most
susceptible of key resource areas, to provide focus, and
to create predictability through multilevel commitment to
a shared vision or an agreed course of action. The ap-
proaches have generally been flexible, accommodating
adjustments through time and recognizing disparate
needs among jurisdictions. Of equal importance, the
programs reviewed have tended to encourage innova-
tion—in the use of economic incentives, management
approaches, and specific source controls—within and
outside the program purview (1).
Several factors emerge as fundamental to success:
leadership and advocacy among key political figures;
clearly articulated priorities that are carefully maintained;
a good match between scope and administrative clout;
specificity of intent; clear, defensible delineation criteria;
availability and careful use of data; breadth of repre-
sentation in program design; strong incentives for action;
and public support.
Areas of vulnerability show parallel consistency. Critical
area programs have tended to be subject to challenge
175
-------
when specific actions could be justified only by correlat-
ing small-scale land use change and in-stream pollutant
loads; when monitoring was inadequate to demonstrate
progress; and when unrealistic expectations for improve-
ment were created and a lag in showing results ensued.
Other key problems include inadequate attention to
grandfathered uses, reliance on acceptance of con-
centrated development patterns, insufficient local
flexibility, and weak justification of the delineation method
in terms of program objectives.
RATIONALE FOR THE PROPOSED RHODE
ISLAND PROGRAM
These findings were considered carefully in drafting ele-
ments of the proposed Rhode Island strategy so as to
give maximum land use decision-making flexibility and
discretion to local governments while acting upon scien-
tific findings to meet state resource protection and en-
hancement goals.
There is much to build upon: a strong base of regulatory
standards, a vigorous state natural heritage program, the
special area management program coordinated through
Rhode Island's coastal zone management program, and
several encouraging local efforts. Yet a number of legal
and institutional obstacles have limited the degree to
which state or local programs have succeeded in ad-
dressing the cumulative effects of poorly planned land
use alteration, or in effectively approaching restoration
(2).
A flexible critical area management approach could
serve to rationalize and strengthen specific protection
and restoration efforts while respecting Rhode Island's
strong home rule tradition. The program emphasizes im-
proved definition of those functional areas and values
that are currently considered in the state resource
management framework but that can also be related to
the health and welfare protection powers of local govern-
ment. Consequently, it is recommended that the initial
landward boundary of the critical area be established as
a uniform "study area" extension of existing regulatory
jurisdiction with respect to coastal features, floodplains,
recharge areas, and wetlands. Based upon results of
high priority inventories, the boundary could be adjusted.
Key objectives of the proposed program are to empower
local governments in the area of ecosystem manage-
ment while ensuring a consistent approach to cross-juris-
dictional needs; to encourage use of technically
appropriate and defensible management measures; and
to create predictability with regard to control of cumula-
tive impacts on the Bay basin's functional values.
The LMP has advocated that the Bay critical area ap-
proach be grounded in principles of bioregional planning
and landscape ecology, and that the program pursue a
goal of protecting the "vernacular" landscape of the Bay
basin. A vernacular landscape is valued as a reflection of
traditional human activities and uses, and for its visual
and cultural qualities. This goal would encompass res-
toration of formerly active anadromous and commercial
fisheries, as well as reinforcement of land-conserving vil-
lage settlement patterns and conservation of properly
managed prime agricultural lands.
Other related critical area goal recommendations are: to
manage growth so that land use is fully integrated with
nonpoint source pollutant treatment capacity on a water-
shed basis; to establish decision-making frameworks
capable of ensuring that Bay system functional values
are protected from cumulative impacts; to preserve maxi-
mum habitat diversity and ecosystem complexity in
tributary stream systems; to aggressively protect and
restore wetlands, transition zones, and intertidal areas;
and to emphasize availability and use of effective
economic incentives.
PROGRAM ELEMENTS UNDER DISCUSSION
The proposed critical area program component of the
CCMP will overlap with other CCMP sections in con-
sidering land use controls, nutrient management, com-
prehensive stormwater management planning, and
remedial stormwater management activities. Stormwater
initiatives will also depend upon the outcome of the state
stormwater policy revisions currently underway at the
Rhode Island Department of Environmental Management
(RIDEM). The administrative structure of the proposed
program will depend on the outcome of the current reor-
ganization of state environmental regulatory programs.
Legislative approval would be required for certain
proposed elements, but for a majority of those proposed,
a technical coordinating body could serve to complement
existing state program functions. Brief summaries of
major program elements follow.
DESIGNATING WETLAND CONSERVANCY
AREAS
It will be proposed that RIDEM implement a phased
program of mapping and registering all of the state's wet-
lands that are hydrologically connected to the Bay or to
tributary stream systems on a year-round basis and that
could be expected to influence the water quality of the
Bay system. Mapping would be based upon Rhode
Island Geographic Information Systems (RIGIS) data
and high-resolution infrared or other photographic tech-
niques. Maps would be verified by local conservation
commissions on a plat and lot basis, as has been ac-
complished in the town of Barrington, Rhode Island.
RIDEM would develop designation and valuation ranking
criteria, perhaps building upon the methods of Golet (3)
or Larson (4). It is recommended that the wetland
evaluation scheme consider the existing quality of
vegetation, existing surface water quality, relative water
quality maintenance attributes, wildlife habitat values,
and sociocultural values. RIDEM and the Rhode Island
176
-------
Department of Health would designate appropriate inter-
im buffer requirements based on RIGIS data evaluation.
Final buffer requirements would be based upon the
valuation ranking, and would consider potential for
damage to wetland function and for transport of viruses
and contaminants to water supply sources.
Landowners would have a specified time after notice and
public hearing within which to dispute the designation
and/or to voluntarily list their property as a designated
"Reforestation/Re-buffering Receiving Area," entailing
recording of a permanent negotiated easement. At the
close of the decision period, permanent land use restric-
tions would be entered in the land evidence records by
RIDEM or its designee. Defined restrictions would limit
activities that could be expected to impact wetland func-
tion, and would be incorporated into relevant manage-
ment practices of the proposed critical area.
Advance notice would serve to clarify permissible ac-
tivities, and the delineation of wetland functional values
would support other components of the proposed critical
area program as well as existing state programs. Restric-
tion authority would be drawn from the state's emerging
no-net-loss policy and from the anti-degradation
provisions of the Rhode Island water quality regulations.
DESIGNATING NUTRIENT-LIMITED
WATERSHEDS
Researchers at the University of Rhode Island have
recently completed a number of projects involving char-
acterization of nutrient discharges from septic systems
and turf. Simultaneously, the cycling of nutrient inputs to
enclosed embayments has been extensively studied in
nearby Buzzards Bay in Massachusetts. These efforts
have provided an excellent basis from which to approach
management of land-based nutrient loadings to Nar-
ragansett Bay.
For the purpose of Bay water quality management,
nutrient management efforts related to land use will be
targeted toward enclosed embayments and water supply
watersheds that are nitrogen sensitive or have already
been affected by nitrogen loads. Nitrogen-affected water-
bodies will be identified using Narragansett Bay Project
data and state assessments, while nitrogen-sensitive
ones will be identified using available tidal flushing data,
GIS, and build-out analyses currently being prepared by
most communities as part of the ongoing statewide local
comprehensive planning process.
Communities encompassing these nutrient-limited water-
sheds would be expected to perform a nitrate impact
evaluation and an analysis of management alternatives.
Such a study was completed in 1990 by the town of
Charlestown, Rhode Island, and is under consideration in
several other communities with regard to water supply
protection needs.
Due to the difficulties experienced by towns in basing in-
cremental development decisions on projected eleva-
tions of freshwater pond nutrient concentrations, it is
recommended that a strategy be pursued comparable to
that applied to pond protection by the state of Maine:
critical loading limits are set for each embayment based
on ultimate build-out, mass loading, and embayment-
specific flushing rates. For nitrogen-sensitive water-
bodies, allowable loadings would then be allocated to
each land use class.
To manage allowable loadings, towns would be required
to develop a coordinated strategy of growth manage-
ment, reduced fertilizer application, use of mandatory
cluster to preserve open space and accommodate re-
buffering, use of appropriate best management practices,
and upgrading to denitrifying septic systems. These
strategies would be reflected on a watershed or recharge
area basis in local land use regulations and density-shift-
ing programs, and through cooperative allocation arran-
gements with adjacent watershed communities.
Each community's strategy would be evaluated by the
Rhode Island Division of Planning as an element of the
upcoming comprehensive plan updates. RIDEM approval
of facilities' plans and permitting of community package
treatment plants would be contingent upon implementa-
tion progress. To avoid encouraging overreliance on
large-lot zoning, to improve management of cumulative
effects, and to reinforce effective on-site practice, it is
recommended that where possible a "declining balance"
method of permit availability be used in which a fixed
percentage of the remaining watershed nitrogen alloca-
tion is "awarded" annually on a jurisdictional basis. As a
means of integrating nutrient management with the den-
sity shifting strategy outlined below, towns should also
stipulate that some portion of the nutrient load allocated
annually for each land use category be reserved for
developers who have "offset" a potential nutrient load by
purchasing Bay Development Credits (see below).
For nitrogen-affected water bodies, communities would
be required to employ the planning strategies outlined
above for future development, and to implement restora-
tion strategies (see following sections), limited-capacity
sewering, or other wastewater management techniques
as necessary to address existing nitrate reduction needs.
Funding for analytical support is currently available from
the state Aquafund grant and loan bond program.
FOSTERING HABITAT RESTORATION AND
REFORESTATION
Numerous authors in Rhode Island and elsewhere have
demonstrated the important role that forested buffer
areas and headwaters ecosystems play in regulating
nutrient retention and processing, moderating stream
system function, assimilating pollutants, and maintaining
177
-------
habitat viability (3,5,6,7,8). In view of the need for broad
reliance on multiple-purpose buffer functions, and the
potential for haphazard development of key buffer
resources, it will be recommended that an accelerated
program be instituted to ensure that maximum buffering
capability is preserved on a sub-watershed basis and
that open space connectivity and shape configuration is
preserved to ensure habitat viability.
The Rhode Island Heritage Program is in the process of
defining endangered and threatened species' open
space needs in terms of size, shape, and connectivity on
protected and privately owned lands. It will be proposed
that the Heritage Program coordinate with the wetlands
mapping and valuation effort outlined previously to iden-
tify and set priorities among resource areas to guide ac-
quisition and restoration efforts. Priority habitats within
the critical area's jurisdiction would include Bay embay-
ment recharge areas, defined shoreline ecological zones,
and areas that significantly affect tributary water quality
(not limited to floodplains).
The identification process would target publicly or
privately owned habitats that would be suitable Refores-
tation/Re-buffering Receiving areas, as well as privately
owned Reserve areas needed to provide linkage. Land-
owners accepting Reforestation/Re-buffering Receiving
area designation would be required to grant permanent
conservation easements managed by the Heritage
Program, while Reserve landowners would be asked to
grant voluntary easements managed by land trusts.
Communities would work with land trusts, the Heritage
Program, and other entities to prepare habitat restoration
plans designed to enlarge, round out, and buffer existing
significantly protected wildlife habitat, to link protected
wildlife habitat with greenway corridors, and to effect
habitat restoration in accordance with state and local ob-
jectives. Eligibility for state Open Space Bond Funds
would be based on sufficient demonstration that a town,
in consultation with appropriate entities, could ensure
that a given habitat area was "buffered" from the effects
of anticipated or existing development; prevent adverse
habitat impacts on a case-by-case basis; or guarantee
timely protection from disturbance through covenants,
easement, or other permanent means.
DEVELOPING A STRATEGY FOR
MANAGEMENT OF SUBSTANDARD LOTS
Given its existing mission and its powers to acquire, hold
interest in, and dispose of property, the Rhode Island
Housing and Conservation Trust may be the most ap-
propriate entity to manage a key aspect of the proposed
critical area program: recovery of substandard or poorly
configured lots where development would contribute to
water quality degradation. Significant sections of several
older coastal communities are vulnerable to issuance of
variances, as they are perceived by local governments to
be open to takings claims because development is
precluded by current state requirements and guidance.
Efficient development patterns that allow for effective
wastewater and stormwater management are precluded
by the configuration of the lots, which are largely in multi-
ple ownership. The current real estate slowdown offers
an excellent opportunity to purchase and reconfigure
areas affected by poor lot layout, inadequate open
space, incompatible land use, scattered ownership, or
other factors potentially compromising the viability of vital
resource areas or impeding orderly and sustainable
development.
It will be recommended that the Trust be given power to
undertake, manage, or fund activities that would help im-
plement applicable elements of local comprehensive
plans or would otherwise serve to resolve land use con-
flicts and water quality management needs. These objec-
tives could be accomplished through redevelopment, site
reservation, resource enhancement (facility retrofitting
and/or habitat restoration), public access acquisition, or
urban waterfront restoration.
Authority would be available to acquire and dispose of
property, to accept gifts, to sell Bay Development Credits
(see below), and to acquire interest in land by means of
land exchanges, or other less-than-fee alternatives.
Grants and loans could be made available to local
governments or land trusts for appropriate projects. Any
project would be required to provide for maximum
feasible stormwater management and habitat protection
benefits, and to be consistent with any relevant
provisions of the critical area program.
CREATING A "BAY MODEL WATERSHED"
PROGRAM
In order to initiate a consistent consensus-based water-
shed management planning process for priority Bay
tributaries, a process will be proposed in which strong
technical support and guidance would be made available
on a sustained basis to local governments that share a
watershed in common and have demonstrated clear
commitment to sound land use and water resource
protection. The program would be designed to set a clear
course of action for joint water quality and flood hazard
management, from both a prevention and a mitigation
standpoint. Communities would also be provided a
means of obtaining, at low cost, continuing technical sup-
port for decision making and program refinement over
the long term.
Communities seeking to designate a Bay Model Water-
shed would be required to have in place the authority
and framework of stormwater management districts or
utilities that could provide dedicated funding and the ad-
ministrative/management structure necessary to imple-
ment a watershed management program. In rural
communities, existing fire districts, water districts, or
178
-------
wastewater management districts could prove suitable.
In addition, towns would have responsibility for gathering
specific supporting data required for the watershed
analysis as a part of the selection process, and for
demonstrating that certain local initiatives had been
taken to deal with the identified problems. A coordinating
body having sufficient authority to implement consensus-
based management decisions would also be established
by the town.
The Narragansett Bay institute recently established by
the Rhode Island Assembly is proposed as the entity
responsible for conducting actual studies, in coordination
with the USDA Soil Conservation Service (SCS) and the
advisory body. Upon formal acceptance of the results,
consistency with study recommendations would be re-
quired in state and local decision making. Arrangements
for continued support consistent with needs identified in
the study would be made with SCS and the conservation
districts in a manner paralleling that of the pilot Regional
Site Inspection Program now in place.
STORMWATER MANAGEMENT PLANNING
A significant body of data produced by Hoffman et al.
(1982) and others within the state of Rhode Island, as
well as numerous researchers nationwide, indicates that
stormwater represents a major source of metals and
hydrocarbon loadings to principal Bay tributaries and
contributes to bacterial contamination in poorly flushed
embayments. Along with leachate from failed septic sys-
tems, stormwater sources are believed to be a primary
factor in shellfish bed closures and loss of other benefi-
cial uses. Yet most Rhode Island towns still employ tradi-
tional flood control-oriented "drainage" practices on
public roads and are only beginning to institute up-to-
date stormwater management requirements for sub-
divisions or other developments.
The proposed critical area program offers an opportunity
to improve coordination between stormwater manage-
ment and land use planning in areas influencing the Bay,
and to focus remediation activities to capitalize on new
state and federal initiatives. The timing is good. New
RIGIS coverages, buffer evaluation methods, and the P8
land-based water quality model offer powerful new tech-
nical tools with which to rationalize the decision-making
process and evaluate treatment capacity through time. It
will be recommended that local governments proceed on
two fronts to expedite management efforts, maintaining
consistency with emerging state stormwater manage-
ment policy.
Identification and Mapping of Existing Natural and
Manmade Stormwater Systems
Using RIGIS coverages, flood data, wetland maps, soils
data, and available buffer evaluation tools, towns encom-
passing critical area jurisdiction would map existing
natural stormwater management capability, from both
water quality and water quantity control standpoints. Soil
infiltration and buffering capacity would be mapped,
using acceptable methods (7, and others) and protocols
now under development at the University of Rhode Is-
land for evaluation of ambiguous, moderately well-
drained soils.
Wetlands, floodplains, natural depressional areas, and
drainageways would be mapped for overlay on plats and
composite maps. Basic characteristics of the existing
manmade system would be mapped at comparable
scale, showing the location and dimensions of pipes,
drainage areas, infiltration components and outfalls; loca-
tion of subsurface drainage networks and outfalls; and
appropriate invert elevations.
A key objective of these efforts would be the identifica-
tion of underutilized management alternatives that should
be considered in the development of subsequent water-
shed-based stormwater master plans that would draw
upon the watershed resource inventories described pre-
viously. High buffering capacity soils, natural treatment
and storage areas, and areas suitable for regional
stormwater management should be zoned and managed
to protect or enhance their multiple-use functions for
water management, habitat protection, scenic value, and
recreation. Towns would use delineations of high buffer-
ing capacity soils and potential regional treatment sites in
identifying and configuring appropriate density receiving
areas. Applicable procedures for site plan review evalua-
tion and for allocation of density bonuses should be ad-
justed to ensure that opportunities to integrate land use
and treatment capacity fully and efficiently, and to correct
existing problems, would be capitalized upon and
rewarded.
Targeting Stormwater Discharge Mitigation Efforts
Proposed elements of the critical area program and other
state and local efforts are aimed at correcting existing
stormwater runoff problems that are causing or contribut-
ing to water quality degradation or to Bay shellfish bed
closures. Both regional and local programs are already
being initiated to undertake appropriate mitigation
measures for existing stormwater discharges, via instal-
lation of new structures and retrofitting.
Several practical shoreline inventorying methods, sam-
pling regimes, and targeting protocols have been
developed and applied in Rhode Island and on Cape
Cod that can be used by town governments in setting
preliminary priorities among stormwater facility mitigation
projects. It will be proposed that each community encom-
passing critical area jurisdiction work with RIDEM and
the Rhode Island Coastal Resources Management
Council (CRMC) to identify proposed stormwater mitiga-
tion sites, and use an accepted numerical ranking
process to set priorities among projects. Rank would be
based on RIDEM and the Rhode Island Department of
Health water quality data, on an estimation of other con-
179
-------
tributing sources, and on the communities' current and
projected flood hazard mitigation needs.
It will be recommended that when ranking is complete, a
graduated hierarchy of required treatment levels be es-
tablished jointly for the watershed, based upon location
of facilities in the watershed, feasibility of improving
source control or installing best management practices,
and the beneficial use designation of receiving waters.
RIDEM, CRMC, and the communities involved would
then negotiate and specify a Critical Area Water Quality
Enhancement Level (based on a defined benefit/cost ex-
pectation), which would subsequently be required when
public road and drainage facilities were repaired and
when sites were redeveloped.
Public and private entities could work toward fulfilling
specified water quality improvement obligations by serv-
ing as Reforestation/Re-buffering Receiving areas or by
purchasing offsets serving the same purpose. Enhance-
ment specifications would be periodically renegotiated on
a watershed basis.
P8, the land-based water quality model, could be used
as a consistent method of evaluating retrofit design
potential per unit cost on sites, or in small catchments.
Until communities established a ranking and watershed
enhancement strategy, they would be subject, at a mini-
mum, to RIDEM's recommended 85 percent removal re-
quirement for facility repairs and redevelopments.
The Rhode Island Aquafund currently offers funds for
local watershed-based nonpoint source management
planning. It is recommended that a permanent source of
matching funding be established for watershed evalua-
tions, but that progress in the efforts outlined above, and
in establishment of a stormwater management district or
utility, be considered heavily in awarding grants or loans.
Progress toward targeted mitigation needs also should
be considered by RIDEM as it develops a strategy for
permitting discretionary stormwater discharge under the
new EPA stormwater rule.
BROADENING OBJECTIVES FOR SHORELINE
AREA DESIGNATIONS
Narragansett Bay Project research results, along with a
complementary body of previously existing research
results on the Bay system, suggest that the amount of
development that the estuary's watershed can sustain
while retaining the viability of the resource is uncertain
but limited, and that case-by-case permit review has
deepened uncertainty regarding the cumulative effects of
development and has lead to piecemeal disruption of es-
tuarine resource properties.
There is sufficient evidence to suggest that degradation
has proceeded to the point where documenting the
ecological importance of the loss of a specific component
of the system would be impossible, as would its attribu-
tion to a particular development event. Critical area
designation strategies must therefore focus on preysn-
tion and on ecological restoration. The proposed desig-
nations seek to strengthen existing state programs and
to maintain consistency with Rhode Islanders' traditional
willingness to enact measures to compensate for past
degradation.
Waterfront Revitalization Areas
It will be proposed that CRMC work with communities in
designating waterfront areas, consistent with CRMC's
established water use designations (including High-Inten-
sity Boating, Commercial and Recreational Harbors, and
Industrial Waterfronts) that are suitable for redevelop-
ment involving habitat restoration or re-creation of buffer
areas.
In these Waterfront Revitalization areas, proponents of
new construction or significant redevelopment would be
required to either 1) re-create on-site buffering or other
treatment capacity to achieve a minimum of 10 percent
reduction of pre-existing runoff pollutant load; or 2) pur-
chase sufficient capacity in an off-site stormwater facility
or retrofit project to achieve a similar percent reduction of
pre-existing pollutant load, with a commensurate opera-
tion and maintenance fee; or 3) if physical constraints
preclude either of these alternatives, purchase an offset
calculated on a square footage basis to be used in fee-
simple purchase or easement acquisition of Reforesta-
tion/Re-buffering Receiving areas within the same
watershed. Donation of appropriate space for regional
stormwater treatment could be applied toward reduction
of "fee in lieu of" charges.
Owners of existing developments in Waterfront
Revitalization areas would be able to list their properties
as Reforestation/Re-buffering Receiving areas if re-crea-
tion of a buffer was considered by CRMC to be desirable
from a management standpoint, or to sell Bay Develop-
ment Credits (see below). Easement restrictions would
then be placed on the buffer and it could be counted
toward future offset obligations on the property.
Bay Conservation Areas
It will be proposed that lands within CRMC's jurisdiction
that impact CRMC's designated Conservation areas or
Low Intensity Use areas be identified as Bay Conserva-
tion areas. In addition to existing requirements,
proponents of any new development in these areas
would be required to purchase an offset for use in
Reforestation/Re-buffering Receiving areas within the
same watershed or to replace disturbed buffer as
prescribed by CRMC. Again, owners of existing proper-
ties in Bay Conservation areas would have the option of
listing their properties as Reforestation/Re-buffering
Receiving areas if re-creation of a buffer was considered
advisable by CRMC, and/or by selling Bay Development
Credits. In either case, easement restrictions would then
be placed on the property and entered in the land
evidence records to ensure protection of restricted areas.
180
-------
LAUNCHING A DENSITY TRANSFER AND
RECEIVING PROGRAM
Although an increasing number of towns in Rhode Island
have expressed interest in density-shifting mechanisms,
fully successful program implementation will require:
• Legislative approval of revised zoning-enabling legis-
lation
• Revisions to state wastewater management regula-
tions to accommodate innovative individual and com-
munity wastewater management systems
• An enlarged scope of review for local comprehensive
plans
• Changes in administrative hearing processes within
the state permitting agencies
Nevertheless, a density-shifting mechanism within the
proposed critical area program could provide important
focus for communities in rationalizing growth manage-
ment efforts and meeting a range of water resource
protection requirements. A central objective of the den-
sity-shifting program would be to prevent prime develop-
ment sites having potentially significant pollutant
treatment capability from being preempted by premature
low density development. Also important would be the
opportunity to lower costs of housing in areas already
served by infrastructure that are outside of hazard zones,
and to avoid creating pressure for extensions into haz-
ardous or sensitive areas.
The following basic structure is recommended, based on
program implementation experience in similar areas, in-
cluding the New Jersey Pinelands and developing
Maryland counties.
A simple system of equivalency would be set up in
which, for example, one Bay Development Credit could
be sold for each 5 acres of land placed under conserva-
tion easement or coastal access easement. Bay
Development Credits could be sold by property owners in
Bay Conservation areas, in areas designated as ap-
propriate buffers or high value habitat areas through the
Wetlands Conservancy designation process, in areas
identified as having high stormwater management or
habitat value, or in other sensitive areas as identified by
RIDEM and CRMC. For agricultural lands, Bay Develop-
ment Credits would be apportioned on an acreage basis
that recognized speculation thresholds. In harbor and
urban waterfront areas designated by CRMC and RIDEM
as having high priority for public access, Bay Develop-
ment Credits could be sold by landowners who agreed to
record permanent public access easements. Trade in
development credits would be managed by the Rhode Is-
land Housing and Conservation Trust Fund on a supply
and demand basis.
Each Bay Development Credit could be redeemed for a
given incremental increase in density that would depend
upon the base zoned land use and density. Land value
increases with increases in permitted density, but un-
evenly. Outside urban settings, high density development
has proven to be inconsistent with traditional Rhode Is-
land development patterns. Given these considerations,
and to foster a market in development credits, bonus
units would be offered not only in areas zoned for higher
densities, but also where density increases yield highest
profits to developers—at low to moderate density. The
"value" of bonus units at varying base densities would be
accounted for by establishing a sliding scale for different
types of units.
Establishing a streamlined permit review process for
projects using Bay Development Credits would also
serve to create an active market for density transfers.
Additional bonus units might also be made available for
developments in which space or discharge easements
were donated for neighborhood or regional stormwater
management.
Growth Areas
Local governments would be responsible for designating
interim growth areas (town centers, villages, transporta-
tion centers), based on evaluations required in support of
local comprehensive plans and availability of support ser-
vices. State assistance would be available to towns in
assessing environmental constraints to the location of
growth areas. Soils evaluations, maps of stormwater
management capacity, wetland and habitat delineations,
and other critical area resource inventories discussed in
previous sections would be used as available in deter-
mining final growth area delineations, which would estab-
lish acceptable land use categories and locations within
which bonus units could be applied. An analysis of cur-
rent zoned density and density at build-out would be
completed, considering density increasing mechanisms
currently in place (e.g., incentive zoning, and flexible
zoning).
Based upon results of both the zoning and constraints
analyses, growth areas would be required to be zoned
for a significant (perhaps 50 percent) increase in average
base densities to accommodate use of bonus units.
Zoning ordinances would be revised to state where and
under what conditions Bay Development Credits could
be used to increase density in growth areas, for residen-
tial, commercial, and industrial use. It is recommended
that the Division of Planning be responsible for reviewing
the zoning amendments prepared to accommodate den-
sity shifting in growth areas and rural village areas, as an
element of the local comprehensive plan review process
in place.
Where existing villages and town centers are served by
infrastructure but encompass significant critical area
jurisdiction, or where growth is otherwise constrained by
sensitive areas, towns may wish to issue variances to
allow certain types of development serving important
181
-------
community needs. Any compromise of critical area
values anticipated by the issuance of a necessary
variance should require redemption of Bay Development
Credits. Likewise, the ability to sell Bay Development
Credits should be considered an economically viable use
of land, for the purpose of sheltering a community and
critical area implementing agencies from taking claims.
Rural Village Areas
Communities would be responsible for delineating rural
village areas, where environmental constraints could ac-
commodate new villages of clustered or neo-traditional
development that would be served by alternative
wastewater treatment technologies at individual or com-
munity scale. In these areas, in which Wastewater
Management Districts would have to be in place, towns
would designate and purchase sites for package treat-
ment plants or community alternative treatment systems.
Rural village designation would also be applicable to
areas in which a community system upgrade would be
appropriate to serve concentrations of failed septic sys-
tems. As in growth areas, developers would be required
to redeem Bay Development Credits to obtain bonus
density in the rural village areas, and could purchase and
redeem Bay Development Credits in the same watershed
toward a portion of the cost of buying future capacity in a
community wastewater treatment system. Construction,
operation, and maintenance would be managed by the
town and the Wastewater Management District.
Research in the New Jersey Pine Barrens revealed that
additional units could be added on an incremental basis
on relatively small sites with a significant improvement in
return to the developer (9). Consistent with these find-
ings, any nonclustered residential development in these
areas, and any new development using standard in-
dividual septic systems, would require additional redemp-
tion of Bay Development Credits. Rural village areas
would of necessity be relatively compact, since they
would be limited by environmental constraints and ser-
vice availability.
ROLE OF LAND MANAGEMENT PROJECT
EFFORTS IN SUPPORTING A CRITICAL AREA
PROGRAM
The Land Management Project has attempted to an-
ticipate the conclusions of the CCMP and to apply ele-
ments of NBP research results in an aggressive,
experimental fashion. The mandatory statewide com-
prehensive planning process will be nearly complete
prior to most critical area program deliberations. The
LMP's communication with towns during the process has
provided an opportunity to learn which constraints should
be considered by the CCMP and which alternatives are
most likely to be successful in critical area management.
By providing targeted assistance to towns sharing water-
shed resources, the LMP has been able to encourage
local application of new technical tools developed for
resource evaluation and to promote advance planning for
innovative low-tech stormwater control. By providing in-
terpretation of scientific findings on nonpoint source im-
pacts, the Project has supported towns in articulating
watershed management principles, protecting critical
areas, and designing appropriate regulatory approaches.
Essentially, the LMP has served as a proactive agent for
the critical area program, providing pre-interpreted scien-
tific support and assistance in a range of land use and
water quality protection areas. The following sections
outline some LMP activities and describe some specific
research products as they relate to proposed elements of
the critical area program.
TECHNICAL EVALUATION MODELS
Recent research at the University of Rhode Island and
elsewhere suggests that buffers can offer multiple use
benefits and can be effectively integrated into overall
watershed management schemes through land use plan-
ning. Since the late 1970s, vegetated buffer strips have
come into widespread use to control movement of sedi-
ments, nutrients, and other pollutants. However, their
variability of function from site to site and through time
has made delineation formulas difficult to interpret and
often cumbersome to apply.
On the local level, delineation for water quality protection
has proven to be extremely consumptive of local review
time and often poorly grounded in scientific foundation.
At the same time, multiple use wildlife and habitat values
are often underconsidered because of local level con-
fusion regarding the meaning and purpose of regulatory
setbacks versus functioning buffers. The relationship bet-
ween design and function is often poorly understood, and
attention to long-term maintenance needs insufficient.
Yet the incentive to expand the use of buffers in water-
shed management is great. Underuse or loss of natural
buffering capacity can lead to an increasing reliance on
expensive structural solutions that carry inspection and
maintenance requirements beyond the reach of
homeowners, associations, or small town governments.
In Rhode Island, effective buffer evaluation is expected
to be a necessary component of local implementation of
key critical area program components. In view of these
needs, the LMP has undertaken several initiatives in the
area of buffer delineation and management.
A focus of LMP activities has been the Hunt-Potowomut
watershed (North Kingston, East Greenwich, and War-
wick, Rhode Island), where severe induced infiltration
potential has enabled us to show that groundwater and
surface water quality management must be confronted
jointly.
182
-------
Hunt-Potowomut Buffer Utilization Study and
Shoreline Inventory
In the spring and fall of 1990, in three pilot sub-water-
sheds, the LMP worked with local board members, plan-
ners, and volunteers to conduct a simple but focused
inventory of stormwater discharges and low-tech control
opportunities, including use of existing infiltration and
buffering capacity. The intent was to determine the ex-
tent to which low-tech opportunities for flood hazard
mitigation and water quality treatment were being utilized
to test an evaluation method usable by volunteer boards,
and to prepare recommended revisions to local
regulatory requirements that would enhance "pollution
prevention" and institutionalize low-tech nonpoint source
management practices.
Using RIGIS and local public works maps, existing
drainage networks and buffers were identified and
delineated by land use coverage on United States
Geological Survey (USGS) topographic sheets for field
use. LMP staff, town staff, and board members then
worked on foot and from canoes to inventory and map
piped stormwater discharge outfalls affecting the Hunt-
Potowomut, indicating the age and size of the develop-
ment being drained, the availability of nearby buffer
areas, and the appropriateness of using the buffers for
stormwater treatment. The University of Rhode Island
Watershed Watch coding system for volunteer monitor-
ing was used, after having been augmented to include a
buffer description coding component.
Pilot sub-watersheds were chosen so as to evaluate (and
illustrate for town officials) prevention and retrofit options
at various stages of development. The four conditions in-
cluded: a) densely developed residential, with 20 to 30
percent of area remaining as potential buffer; b) mixed
use, moderate density development, with 50 percent of
area available as potential mixed buffer; c) mixed use,
moderate density development, with 35 percent of area
available as forested buffer; d) low density development,
with 65 percent of area available as potential buffer.
The LMP used the field data and other tools in working
with the communities to evaluate constraints concerning
discharge to the available buffers, and in considering
planning and retrofitting potential under a range of
growth scenarios. The project provided an excellent op-
portunity to field-test a buffer design guidance manual
recently prepared with NBP funding, and to test P8, the
land-based water quality model developed during the
past two years with NBP support.
Recommendations were made for significantly increasing
emphasis on infiltration capacity, revising local main-
tenance practice, and restricting public access to natural
buffers that show evidence of channelization. The
program has interested the towns in investigating buffer
discharge easements and in undertaking a feasibility
study to evaluate retrofitting and management oppor-
tunities. The town boards have also agreed to coordinate
with University of Rhode Island (URI) investigators in
monitoring buffers used for direct and indirect discharge
in sub-watersheds having a range of percent-impervious
area.
For the LMP, the program has yielded a tested methodol-
ogy for town officials to use in evaluating low-tech
stormwater management opportunities, on a watershed
basis, that can be directly incorporated into growth
management planning. The LMP has also funded URI to
prepare a protocol for use in evaluating the buffering
capacity of soils classified by the SCS as moderately
well drained. The soils of that classification have a wide
range of buffering capacities (7) and encompass nearly
50 percent of the state's land area.
OTHER ACTIVITIES APPLICABLE TO CRITICAL
AREA MANAGEMENT
Several LMP products have been used by town boards in
preparing data evaluations for local comprehensive
plans, and should be useful to them in meeting proposed
critical area data gathering requirements. In particular,
communities could use the LMP Wetlands Site Review
Guide and our guidance on listing wetlands by plat and
lot in corroborating the RIDEM registration process, set-
ting habitat protection priorities, and identifying areas of
high buffering capacity.
In developing a nutrient management and mitigation
strategy, town boards can make use of three LMP
products: a method developed for preliminary build-out
preparation, a review of nutrient loading models, and a
protocol and worksheet designed for use in developing a
defensible approach to nutrient loading.
Other technical products available from the LMP include
resource evaluation tools, ready reference matrices sum-
marizing the effects of land use on water quality, reviews
of research results, and water quality models. Project
staff have also prepared technical fact sheets, handouts
on planning techniques and best management practice
fundamentals, guidance on growth management and
regulatory options, bibliographies, case histories, model
and sample ordinances, sample resource protection lan-
guage for comprehensive plans, slide shows, and videos.
Demonstration projects initiated with designers in three
regions of the state illustrate recommended approaches
to problems, describe experimental methods, serve as
case study histories, or demonstrate use of LMP evalua-
tion tools. Local officials are offered both slide shows and
site tours showing good and bad examples of land and
water management practices.
The LMP has complemented its project-based technical
assistance efforts with an intensive schedule of training
programs. These include a series of nine technical con-
ferences for resource managers, practitioners, and plan-
ners on land use/water quality relationships, growth..,
•-7-J
183
-------
management, and sustainable development techniques.
Audio tapes and videotapes of presentations are avail-
able to interested groups. Together, the proceedings are
intended to serve as a fairly complete curriculum on
these issues.
Finally, our "in-town workshops" have proven to be a par-
ticularly important aspect of our outreach effort. In this
evening series, the LMP makes individual presentations
to town bodies on six basic land use/water quality issues
of particular importance during the comprehensive plan-
ning process.
CONCLUSION
A "marketable" critical area program for Rhode Island
must be essentially conservative but scientifically
grounded, and must enable an extraordinarily diverse
group of communities to focus specific management
tools in addressing widely differing problems.
Communities have thus far been hindered in their water
resource protection efforts by weak state zoning-enabling
legislation, a lack of other clear authorities for local
resource protection efforts, and a conservative state
judiciary whose decisions have reinforced local reluc-
tance to face takings claims. Nevertheless, the Special
Area Management plans have demonstrated that Rhode
Island communities are basically practical and can react
aggressively when there is a clear expectation that land
use impacts will cause significant change in susceptible
resources. It has been more difficult to encourage con-
sistent planning for compatible uses or to avoid loss of
traditional village character through sound growth
management.
A central source of debate in critical area program
deliberations will be the degree to which requirements
should be imposed on towns by the Assembly, neces-
sitating that the state provide a source of funds, and to
what extent actions can be encouraged via economic in-
centives or by piggy-backing requirements onto other
state-supported initiatives, such as the statewide plan-
ning or well-head protection programs. In fact, new
federal initiatives, such as no-net-loss of wetlands, anti-
degradation provisions, and discretionary stormwater dis-
charge permitting authority under Section 402 of the
1987 Clean Water Act, may prove to be vital in fostering
a consistent approach.
Anticipated critical area mandates will require that com-
munities expand mitigation efforts significantly, yet fiscal
constraints dictate that a significant supporting role in
technical decision making and priority setting will fall to
local volunteer boards and officials. Simple, effective
evaluation methods that make maximum use of Rhode
Island's highly developed geographic information sys-
tems capability will be called for.
Fundamentally, however, technical decision making re-
quires technical staff support. A consistent source of
funding for local technical staff has been essential in all
of the sustained local resource protection initiatives un-
dertaken in the state. Technical staff will become indis-
pensable to local bonds as zoning, subdivision
regulations, and site plan review provisions extend their
traditional scope to meet resource management needs.
Finally, it is clear that a valuable purpose can be served
by a technically grounded advisory entity outside the
state regulatory structure. Our experience suggests that
sound local decision making in large watersheds can be
significantly enhanced if a regionally focused service is
made available on a continuing basis to assist com-
munities with technical questions on land use/water
quality relationships and growth management. In addi-
tion, the face-to-face in-town workshops and conferences
held by the LMP have shown us how important fun-
damental education can be in building local commitment
and resolving misunderstandings.
Recovery of Narragansett Bay resources will present a
tremendous challenge for all involved—decision makers
who shape development trends, their advisors, design
practitioners, the development community, and the
citizens who love their Bay. Creativity, energy, and com-
mitment will be required, and must be nurtured. There is
also tremendous opportunity, and many communities are
ready to seize it. Let us hope that we can give them the
tools to do so.
REFERENCES
1. Myers, J.C., 1990. (Draft) Review of Critical Area
Programs and Special Area Management Initiatives
in Twelve States: Potential Applications in the Nar-
ragansett Bay Basin. Report to the Narragansett Bay
Project, Providence, Rl, 21 pp.
2. Myers, J.C., 1988. Governance of Nonpoint Source
Inputs to Narragansett Bay: A Plan for Coordinated
Action. Prepared for the Narragansett Bay Project,
Providence, Rl, 285 pp.
3. Golet, F.C., 1976. Wildlife wetland evaluation model,
p. 13-34. in J.S. Larson, ed., Models for Assessment
of Freshwater Wetlands. Water Resources Research
Center, Univ. of Massachusetts. Pub. No. 32.
4. Larson, U.S., ed., 1976. Models for evaluation of
freshwater wetlands. Water Resources Research
Center, University of Massachusetts. Pub. No. 32.
91 pp.
5. Carter, W.R. Ill, 1988. The Importance of Buffer
Strips to the Normal Functioning of Stream and
Riparian Ecosystems. Maryland DNR Tidewater Ad-
ministration, unpublished paper, 18 pp.
6. Klein, R.D., 1985. Effects of urbanization upon
aquatic resources (unpublished report). Maryland
Dept. of Natural Resources, Tidewater Administra-
tion, Annapolis, MD, 71 pp.
184
-------
7. Groffman, P.M., AJ. Gold, T.P. Husband, R. Sim-
mons, and W.R. Eddleman, 1989. An Investigation
into Multiple Uses of Vegetated Buffer Strips. Univ.
of Rhode Island, Dept. of Natural Resources,
Kingston, Rl.
8. Roman, CT. and R.E. Good, 1985. Buffer delinea-
tion model for New Jersey Pinelands wetlands. Div,
of Pinelands Research, Center for Coastal and En-
vironmental Studies, Rutgers—the State University,
New Brunswick, NJ, 72 pp.
9. Nicholas, J.C., 1988. A Report on the Economic
Value of Pinelands Development Credits, prepared
for the New Jersey Pinelands Commission, in The
Pinelands Development Credit Program: Report to
the Pinelands Commission, New Lisbon, NJ.
ADDITIONAL REFERENCES
Bedford, B.L. and E.M. Preston, 1988. Developing the
scientific basis for assessing cumulative effects of wet-
land loss and degradation on landscape functions:
status, perspectives, and prospects. Jour, of Envir. Mgt.
12:751-771,
Chesapeake Bay Critical Area Commission, 1989 (J.K.
Sullivan). A Summary of the Chesapeake Bay Critical
Area Commission's Criteria and Program Development
Activities, 1984-1988. Chesapeake Bay Critical Area
Commission, Annapolis, MD, 146 pp. with appendices.
Chesapeake Bay Critical Area Commission, 1987. The
Prospects and Problems of Economic Instruments as
Complements to the Chesapeake Bay Critical Area
Program. Annapolis, MD, 87 pp. with appendices. '
Dennis, J., J. Noel, D. Miller, and C. Eliot, 1988. Phos-
phorus control in Lake Watersheds—A Technical Guide
to Evaluating New Development. State of Maine Dept. of
Environmental Protection, Augusta, ME.
Dillaha, T.A. et al., 1986. Long-term Effectiveness and
Maintenance of Vegetated Filter Strips. Bulletin 153. Vir-
ginia Water Resources Center, Virginia Polytechnic In-
stitute and State University, Blacksburg, VA.
Florida Chapter, American Planning Association, 1990.
The Florida Planning and Growth Management Hand-
book, APA, Tallahassee, FL, 193 pp.
Hartigan, J.P., 1988. Basis for Design of Wet Detention
Basin BMPs, in Urbonas, B. and L.A. Roesner, eds.,
Design of Urban Runoff Controls. Proceedings of an En-
gineering Foundation Conference, Potosi, MO; ASCE
Publications, NY.
Hoffman, E.J., J.S. Latimer, G.L. Mills, and J.G. Quinn,
1982. Petroleum hydrocarbons in urban runoff from a
commercial land use area. J. Water Polln. Control
Federation 54(11):1517-1525.
Huber, W.C., 1986. Modeling Urban Runoff Quality:
State of the Art, in Urbonas, B. and L.A. Roesner, eds.,
Urban Runoff Quality-Impact and Quality-Enhancement
Technology. Proceedings of an Engineering Foundation
Conference, Henniker, NH, ASCE Publications, NY.
IEP, Inc., 1990. P8 Urban Catchment Model User's
Manual and Program Documentation. Prepared for the
Narragansett Bay Project, Providence, Rl.
IEP, Inc., 1990. Vegetated Buffer Strip Designation
Method Guidance Manual. Prepared for the Narragansett
Bay Project, Providence, Rl, 27 pp. with appendices.
Livingston, E.H., 1988. State Perspectives on Water
Quality Criteria, in Urbonas, B. and L.A. Roesner, eds.,
Design of Urban Runoff Controls. Proceedings of an En-
gineering Foundation Conference, Potosi, MO, ASCE
Publications, NY.
Massachusetts Department of Environmental Protection,
1990. Unpublished departmental summary of the Massa-
chusetts Wetlands Conservancy Program. Massa-
chusetts Dept. of Environmental Protection, Boston,
MA, 4 pp.
New Jersey Pinelands Commission, 1988. The
Pinelands'Development Credit Program: Report to the
Pinelands Commission, New Lisbon, NJ, 1988, 70 p. with
appendices.
Rhode Island Dept. of Environmental Management,
1988. Recommendations of the Stormwater Manage-
ment and Erosion Control Committee Regarding the
Development and Implementation ' of Technical
Guidelines for Stormwater Management. RIDEM Office
of Environmental Coordination.
Rhode Island Dept. of Environmental Management, Div.
of Water Resources, 1988 (revised 1989). Policy on the
Implementation of the Anti-Degradation Provisions of the
Rhode Island Water Quality Regulations.
Rhode Island Dept. of Environmental Management, Of-
fice of Environmental Coordination, 1989. Rhode Island's
Nonpoint Source Management Plan.
Rhode Island Dept. of Environmental Management, Of-
fice of Environmental Coordination, 1990. Rhode Island
Nonpoint Source Assessment, State of the States
Report. .
State of Delaware 'Dept. of Natural Resources and En-
vironmental Control, Div. of Water Resources, Nov.
1990. Draft Sediment and Stormwater Regulations.
37pp.
185
-------
THE STORMWATER UTILITY AS A LOCAL REGULATORY TOOL
Nancy Richardson Hansen
City of Beilevue Storm and Surface Water Utility
Bellevue, Washington
BACKGROUND
One of the most important challenges faced by local
governments is controlling the quantity and quality of
urban stormwater runoff. One answer is the estab-
lishment of a local stormwater utility that can provide on-
going funding and staff support for this purpose. The city
of Bellevue, Washington, established such a utility in
1974 in response to citizen concern over flooding and the
deteriorating quality of Bellevue's urban streams.
The City of Bellevue is located in the Puget Sound region
of Washington. First incorporated in 1953, it has grown
dramatically from a population of 6,000 and a land area
of 5 mi2 to over 86,000 residents and 30 mi2 today. The
cily has a varied topography, with a total relief of ap-
proximately 1,200 ft. Precipitation averages 35 to 40 in.
per year.
The city's rapid population growth was accompanied by
the water quality and quantity concerns that typically
plague urbanizing areas. Accelerated surface water
runoff from more impervious surfaces began to cause in-
creased flooding, water pollution, property damage,
streambank erosion, and threats to one of the region's
most precious resources, salmon. During this time, storm
drainage concerns were handled by competing for
general fund revenues within the city's Public Works
Department.
In 1965, state law was changed to allow the estab-
lishment of utilities as a funding mechanism for
stormwater control. A utility is a method of financing
based on payment for services, rather than from general
revenues such as property taxes. During the same time
period, citizen concern over the degradation of
Bellevue's surface water resources began to grow. The
City Council appointed a citizen committee to recom-
mend standards and procedures for preserving
Bellevue's streams.
In 1974, the City Council passed an ordinance estab-
lishing the utility and a system for surface water manage-
ment. The mission given to the new Storm and Surface
Water Utility (SSWU) was to "...manage the storm and
surface water system in Bellevue, to maintain a
hydrologic balance, to prevent property damage, and to
protect water quality for the safety and enjoyment of
citizens and the preservation and enhancement of
wildlife habitat."
Staff began preparing a drainage master plan to address
the pressing issues of flooding and in-stream erosion.
The plan examined a range of alternative solutions from
construction of large storm sewers to the use of open
streams and onsite flood control. An approach was finally
selected using an integrated network of open stream
channels and pipes for conveyance, with lakes, wet-
lands, ponds, and regional detention basins for peak
storage and water quality control. In addition, onsite flood
controls would be required of new development.. The
basic concept behind the selected approach was to use
the natural surface water drainage system to provide for
the conveyance and disposal of stormwater runoff
without degrading that natural system. This approach
has proven to be from four to ten times less costly than
traditional storm sewer improvements and is more
protective of the stream ecosystem.
A final hurdle in the establishment of the SSWU was set-
ting a rate structure to fund the utility's programs. After
significant citizen input, the City Council decided to base
drainage rates on the estimated amount of runoff in-
dividual properties contribute to the total drainage sys-
tem. Each property is classified according to its degree of
development (impervious surface). The classification
combined with total property area determines the service
charge which is billed every two months. Currently, an
average single family household pays $14.50 every two
months for 10,0.00 to 12,000 ft2 of property. Recognizing
the flood control and water quality benefits of wetlands,
changes were later added to the rate structure to benefit
properties encompassing wetlands.
SSWU PROGRAMS
The Storm and Surface Water Utility's programs have
changed and expanded over the years. With an initial
priority to control localized flooding, programs addressing
water quality have grown gradually. The SSWU currently
186
-------
has six major programs that enable it to accomplish its
mission: capital improvement, operations and main-
tenance, water quality, development regulations, public
education, and administration.
Capital Improvement
A fairly expensive capital improvement program was
necessary to put the flood control system in place, even
when using an open stream concept for flood control. A
series of 11 flood control ponds have been constructed
within the Bellevue stream system to provide protection
for the 24-hour, one in 100 probability storm event. They
are operated by remote control from a central telemetry
system which also includes rain gages and flow meters,
fully integrating the city's stream system surveillance.
The capital improvement program also includes storm
sewer and bridge construction, stream channel improve-
ments, wildlife habitat fish passage enhancement, and
water quality projects such as lake restoration.
Operations and Maintenance
An aggressive operations and maintenance program is
probably the most important key to a successful
stormwater utility. Flood control gates are operated
remotely by a central computer, freeing the crew mem-
bers to respond to system and citizen needs. Operation
procedures are designed to minimize fisheries impacts
while providing maximum flood control. During salmon
spawning season, flood control gates are left open until
significant heavy rains begin. The utility also operates a
24-hour emergency telephone line to respond to flooding,
pollution events, or other surface water related emergen-
cies. Maintenance and inspection staff serve as consult-
ants to private property owners working to solve
problems with private drainage systems. Major ongoing
maintenance activities include keeping storm drains and
trash racks clear of debris, repairing structural facilities,
cleaning catch basins, and controlling overgrown vegeta-
tion.
Water Quality
The SSWU is continuing to expand its water quality
programs. Current water quality activities include routine
monitoring of all receiving watersheds, investigative
monitoring of pollution events and sources, emergency
response for spills and other acute problems, stream en-
hancement and lake restoration projects, and inspection
of private stormwater systems. The Utility coordinates
with neighboring jurisdictions on water quality activities.
For example, the city is the lead in a major lake manage-
ment program involving several jurisdictions. The SSWU
has also played a leadership role in the development of
state and federal stormwater regulations. The Utility's
regulatory and education programs also have a sig-
nificant impact on preventing water quality problems. All
of these activities will contribute to successful com-
pliance with upcoming state and federal stormwater
regulations.
Development Regulations
A critical aspect of the SSWU's success is its ability to
use the city's land-use authority to regulate construction;
enforce clearing, grading, and development of sensitive
areas and prescribe strict development standards. The
SSWU has responsibility for enforcing a number of codes
relating to land use and construction. Onsite stormwater
controls for new development are required to provide
protection for the 24-hour, one in 100 probability storm
event. Clearing and grading permits require temporary
erosion and sedimentation control on all construction
sites. Floodplains, wetland, and steep slopes are
protected by a variety of codes that make up the city's
"natural determinants" program. Field inspectors and
development review staff work together to ensure protec-
tion of streams and sensitive areas both before and
during construction.
Public Education
The SSWU conducts a variety of educational activities in
support of its mission. The most visible is the innovative
"Stream Team" program which provides workshops and
volunteer monitoring activities for citizens. A newer
program is called "Business Partners for Clean Water,"
which involves five categories of local business in
developing water quality action programs for the
worksite. Other activities involving water quality and fish
habitat protection include storm drain stenciling (with
"Dump No Waste, Drains to Streams"), salmon rearing
and release projects, and stream rehabilitation.
Administration
Administration includes policy development, financial
management, rate administration, comprehensive drainage
planning, general administration, and support to the City
Council and the SSWU advisory commission. The Utility
also coordinates with other regional governments on
drainage and water quality issues.
STRENGTHS OF A STORMWATER UTILITY
The overriding advantage of a stormwater utility is that it
provides a mission and a source of funding dedicated to
addressing the water quantity and quality issues as-
sociated with urban drainage. The use of a service
charge provides an understandable link between the fee
paid and benefits received. Competition for general tax
revenue is eliminated. With a predictable revenue
stream, a stormwater management program can practice
long-range planning and act to prevent problems, rather
than being destined to react to them.
The establishment of a stormwater utility, however, does
not come without political investment. In Bellevue, al-
though the concept was endorsed by a citizen group and
approved by the City Council, the first utility billing led to
an uproar among some ratepayers. There had been
some advance publicity, but the residents did not fully
understand the basis of their fees or the function of the
187
-------
utility. It took concerted education and public involvement
to bring the community into full support of the SSWU's
existence.
After over 15 years of operation, other reasons for the
SSWU's success can be identified:
• A Unified Agency
A key to Believue's success is that all surface water
functions (operations and maintenance, capital plan-
ning and construction, permitting and enforcement,
and public education and involvement) are together in
one line department whose sole charge is surface
water control and management. This eliminates com-
petition for other priorities which often happens within
multi-purpose departments, and allows for maximum
coordination of activities in support of the SSWU's
mission.
• Strong Regulations
Believue's stormwater utility is effective in addressing
water quality concerns because it has definite
regulatory authority. As mentioned earlier, the SSWU
issues clearing and grading permits that cover all land
clearing and grading in the City. This allows the Utility
to help prevent water problems from occurring during
land development, as opposed to responding to
problems after the fact. The City of Bellevue also has
a strict set of codes addressing the protection of sen-
sitive areas such as wetlands, riparian corridors,
floodplains, and steep slopes and aggressively enfor-
ces these codes.
* Citizen Support
The SSWU would not have been able to move ahead
with a strong stormwater management program
without support from Believue's citizenry and the
leadership and will of the City Council. The Utility is
also supported and guided by a seven-member citizen
advisory commission. Bellevue is fortunate to be able
to be a "service oriented" city; calls for assistance are
responded to quickly and problems are resolved.
Public support of the SSWU is enhanced by educa-
tional programs such as the Stream Team. Through
the Stream Team's workshops, activities, and newslet-
ters, thousands of Bellevue residents have become
more aware of water quality concerns and the benefi-
cial work of the SSWU.
* Attention to Enforcement and Maintenance
Unlike other jurisdictions, all enforcement and main-
tenance activities are staffed within the Utility (as op-
posed to a separate maintenance division, for
example). The SSWU's rate structure also allows ade-
quate financial support for these important functions.
A staff of four full-time field inspectors have the
authority to stop work on a site if permit conditions are
not being followed. An operations and maintenance
staff spends time maintaining and improving the storm
drainage system between storms so that it functions
properly during those crucial times when it is needed.
• Interjurisdictional Coordination
Finally, Believue's stormwater utility does not operate
in a vacuum: it coordinates extensively with other
agencies and governments in the region. Several Bel-
levue streams run between city and county boun-
daries several times during their course. Coordination
with the water quality and drainage activities of neigh-
boring jurisdictions is essential to effective implemen-
tation of the SSWU's programs. The Utility has taken
an active role in several regional planning activities
and has initiated interiocal agreements in the interest
of managing water quantity and quality.
CHALLENGES
In spite of its successes, the SSWU still has challenges.
Although the Utility's purpose and mission is better un-
derstood by a greater cross section of the public, it still
occasionally meets with misunderstanding and disap-
proval. The utility fee is not understood by some who feel
that it is unfair to "tax rain." Debates also occur over who
is ultimately responsible for problems: "top of the hill" ver-
sus "bottom of the hill" property owners. Furthermore, the
benefits of a stormwater utility are not as visible as other
utilities such as water and power. The Utility's true value
lies in preventing problems such as flooding, erosion,
water pollution, and loss of wetlands. Since the SSWU's
benefits are difficult to demonstrate, there is a constant
need to be visible, responsible, and accountable to the
public.
Another challenge lies in adding an even stronger com-
ponent to address water quality. The fee structure
originally established for the utility did not include water
quality as a separate component. Water quality projects
have been funded from grants and as a natural by-
product of good stormwater quantity control. With in-
creasing state and federal regulations addressing water
quality in urban areas, it will become necessary to en-
sure a stable funding base for water quality activities.
This may eventually lead to a revision in the rate struc-
ture that includes a water quality component.
Finally, as with most government programs, last year's
budget is rarely enough for this year's program.
Believue's Storm and Surface Water Utility has under-
gone several rate increases to accompany the increased
cost of service. The ability to adequately fund the
program at a level protective of human property and
ecosystem values will be critically threatened unless
there is continuing public support.
188
-------
CASE STUDIES
-------
CASE STUDIES
INTRODUCTION
The purpose of the case study workgroups was to build
on and respond to the ideas presented in the plenary
sessions and panels; promote open exchange of ideas
by participants from different backgrounds; and reach as
much consensus as possible on the plan development
and implementation process. Each group worked on
developing an approach for restoring the water quality of
the watershed and for monitoring the effectiveness of the
approach.
Workgroup members discussing the case studies had
diverse experiences and backgrounds in handling non-
point source (NFS) problems, yet their philosophies and
technical approaches to addressing these problems were
similar. Most group members agreed that the watershed
case studies involve complex financial, legal, and social
barriers to overcome. The case study discussions were
set up to help participants view these complexities in the
long term and on a regional basis, but also to help in
identifying elements for detailed analysis.
To help organize the workgroup process, certain ques-
tions were used to relate to workshop presentations and
to aid in launching discussion. The questions related to
problem identification; goals and objectives; institutional
arrangements; major watershed plan components; and
NFS controls, monitoring, education, and evaluation.
The following section presents the case studies as they
were developed and used at the workshop. For each
case study, the following information is presented:
• A brief summary of the background material, includ-
ing maps and diagrams that were available to
workgroup participants
• Questions that were used to organize and guide
discussion
• A summary of what was discussed in each
workgroup, conclusions that were reached, and
participants' response to the discussions
CASE STUDY ^—URBAN-
WATERSHED
-BARNSTABLE
Background
Barnstable, Massachusetts, is a coastal resort town with
an area of 64 square miles (see Figure 1). It is the
largest town on Cape Cod (a 70 mile long peninsula in
the Atlantic Ocean) and is the commercial hub of the
area. Barnstable has more than doubled its population in
the last 20 years. It currently has a population of 43,321
year-round residents and 68,400 summer residents.
Most of this growth has been on the south side of the
town. Most jobs are in tourism, construction, fishing,
shellfish harvesting, and light industry. Construction has
recently declined, increasing unemployment.
The southern half of Barnstable is porous sand and
gravel with a gradually sloping (about 4 percent) topog-
raphy. The northern half is alternating areas of clay,
sand, boulders, and silt, with a more varied and steeply
sloped topography. Bedrock lies several hundred feet
below the ground surface throughout the town. Little
space is available in coastal areas for stormwater treat-
ment facilities, and what is available is expensive and
has a high water table.
One large, sole-source, freshwater aquifer lies below the
entire town (see Figure 2). This aquifer is the only source
of drinking water, most of which is still drinkable without
treatment. Some of the problems that have developed in
this watershed include:
• Two public supply wells have been shut down due to
chloroform and freon contamination
• Treatment is needed at two locations because of
gasoline leakage from underground tanks
• Elevated nitrate levels and bacterial counts occur in
the ground water in densely populated areas with on-
site septage tanks
• A large and growing industrial park is located over
one of the town's largest well fields
190
-------
BARNSTABLE, MASS
•<&> i
Atwowl S Bbtkwtll • Cnnsullinl tlaaam • Btttto, Haa
TOWN WIDE PLAN
VILLASE RESIDENTIAL |$SjSg3 WAREHOUSING &
DISTRIBUTION
COUNTRYSIDE RES.
:;;:;;;,:,>;,;,| COMMERCIAL RES.
HliH CENTRAL BUSINESS
HIGHWAY BUSINESS
NEIGHBORHOOD BUS.
RESEARCH PARK
OCEAN ORIENTED
DEVELOPMENT
'^SWi PUBLIC LAND, OPEN
' SPACE, FLOOD PLAIN
ZONE & CONSERVATION
MAJOR HIGHWAY
NETWORK
O MARINA
Figure 1. Barnstable, Massachusetts—town plan.
• Most of the stormwater in developed areas filters
directly into the ground and the aquifer
• The contaminated ground water increases the
nutrient loadings to town bays
• Stormwater runoff is known to cause shellfish bed
closures due to bacterial contamination
Several town agencies and committees are involved with
water-quality issues. The Board of Health issues septic
system and underground storage tank permits, tests
coastal waters, analyzes sources of contamination, and
inventories underground tanks. The Department of Public
Works designs and constructs stormwater treatment im-
provements, coordinates the development of sewer
facility plans, and oversees all government construction
191
-------
LEGEND.
~-20 Water-Tablt Contourt, In F««t Abov« S«a Levtl
Figure 2. Barnstable, Massachusetts—water table.
192
-------
Figure 3. Coastal resources management plan.
193
-------
in the town. The Natural Resources Department monitors
shellfish beds. The Conservation Commission regulates
work within 100 feet of wetlands and assists in the
development of coastal resource management plans.
The Planning and Development Agency is the primary
zoning authority. There is a Shellfish Advisory Committee
and a Water Quality Advisory Committee. Finally, the
Planning Board regulates subdivisions and makes
recommendations on proposed zoning changes.
The county reviews the development of large sub-
divisions and commercial buildings, provides
hydrogeological support to the towns, and advises towns
on issues related to marine water quality. Several state
and federal agencies also are important. For example,
the Massachusetts Division of Water Pollution Control, in
particular, establishes and administers onsite septic sys-
tem standards (and is currently rewriting these regula-
tions). On the federal level, the U.S. EPA provides
technical assistance, as well as funding for certain
projects.
To address water-quality problems, Barnstable mapped
the zones of contribution to 53 of the town's public water
supply wells, inventoried and prioritized 50 locations
where stormwater discharge should be treated, required
new developments to treat runoff, restricted land uses in
zones of contribution, developed a $1 million geographic
information system (GIS) to provide citizens with data on
zoning and water quality, and began work on a
wastewater treatment facility plan. In addition, a Coastal
Resource Management Plan (see Figure 3) has been
developed to improve the water quality of the Cotuit Bay.
Case Study Questions
1. How can the town increase the number of existing
underground tanks reported?
2. What provisions need to be included in the zoning
by-laws to protect water quality?
3. How should departments and agencies be structured
lo include all important parties in the process?
4. How can the town maximize the utilization of county
resources? What types of areas should the town
recommend to the county as areas of critical con-
cern? What requirements should be placed on
development in these areas?
5. What requirements should the town ask the state to
include in regulating onsite septage disposal
systems?
6. How can the town best utilize the technical assis-
tance and resources available from the U.S. EPA?
What funding is available for water-quality projects?
What work could the town do now to prepare it to be
eligible for funding water-quality improvement
projects?
7. How does the infiltration of stormwater through the
porous soils on Cape Cod affect the short-term and
long-term quality of the ground water?
8. With the porous soils along the coast, what criteria
should be established for depth-to-ground water for
infiltration facilities and septic systems and to
eliminate bacteria, heavy metals, and viruses?
9.. Very limited funds are available for stormwater treat-
ment. How should areas be prioritized? How can
treatment facilities be paid for?
10. What additional treatment methods besides infiltra-
tion are available?
11. Infiltration facilities are easily clogged by sediment in
runoff, sometimes within 7 years. How can facilities
be designed to have a longer useful life?
12. How can the productive use of the town's new
geographic information system (GIS) be maximized?
13. How can the town build popular support for the con-
struction of wastewater treatment facilities where it is
necessary to improve water quality? How can the
town include the users of such systems in the plan-
ning process and gain their input and support when
setting sewer user rates?
14. How can the town build popular support for the
recommended actions to improve water quality in
Cotuit Bay and elsewhere in town, establish
stormwater treatment facilities and no-discharge
zones for sanitary waste from boats, control the use
of fertilizer, and support operation and maintenance
facilities?
Workgroup Problem Identification
The workgroups identified major problem areas to be the
threats to drinking water, shellfishing, and recrea-
tion/tourism; poor coastal water quality due to bacterial
contamination; and rapid population growth on Cape
Cod. Table 1 illustrates one group's detailed analysis of
the poor coastal water-quality problem. The potential
sources identified included septic systems, stormwater
runoff, landfills, underground storage tanks, atmospheric
deposition, illicit discharges, recreational boats, animals,
spills/releases, and litter. One group suggested that
deficiencies in past and/or present facility planning and
siting, watershed planning and zoning, technical exper-
tise, growth management, enforcement, standards and,
regulations, regional cooperation, public involvement,
and legal agreements may have contributed to' the
problem.
194
-------
Table 1. Analysis of Poor Coastal Water Quality
Uses
Resources
Problems
Swimming
Support Shellfish
Bathing beaches
Shellfish
Recreation constraints
Shellfish contamination
Reduced shellfish quantities
Pollutants
Sources/Causes
Bacteria
Ground-water inflow
Septic systems
Landfill leachate
Infiltrated stormwater
Nutrients
Toxicants
Stormwater runoff
Septic systems
Pets
Fertilizer
Vehicles
Boats
Sewage
Bottom paint
Waterfowl
Pets
Goals and Objectives
The workgroups identified the following goals for the
project:
• Ensure fishable waters and open shellfish beds and
restore the local water-based economy
• Ensure swimmable waters and keep beaches open
• Protect against loss of wetlands
• Prevent eutrophication
• Guarantee safe supply of drinking water
• Control surface water problems while maintaining
acceptable ground-water recharge
The workgroups agreed that the rapid population growth
also must be limited or its effects must be greatly
mitigated to reach the goals for the project.
Administrative objectives included clearly defining the
problem; using zoning controls to reduce urbanization;
reporting progress to the. public; gaining acceptance by
government leaders; disseminating information; and
using existing organizations and programs to help imple-
ment the project. One group emphasized the importance
of prioritizing the goals and developing a project
schedule.
institutions
To achieve the project goals, the workgroups agreed that
governmental entities must coordinate activities and
provide adequate resources, including regulatory and
legal capabilities. Technical experts could inventory in-
dividual nonpoint sources, estimate loads, and develop
control options. The roles of participating groups must be
established in the beginning of the project to cultivate
project "ownership" and develop the project's driving for-
ces. It also was suggested that regional coordination and
special district authorization be considered. According to
one group, accountability at all levels of government was
strongly encouraged. Memoranda of understanding or
other institutional arrangements seem necessary to en-
courage the project team to deliver on their commit-
ments.
The groups suggested the following specific agencies for
help with the problem: Board of Health; Shellfish War-
den; Harbor Master; Department of Public Works; and
state and federal agencies, including the Soil Conserva-
tion Service (SCS), U.S. Geological Survey (USGS),
Fish and Wildlife Service (FWS), Environmental Protec-
tion Agency (EPA), Food and Drug Administration (FDA),
and the National Oceanic and Atmospheric Administra-
tion (NOAA). Several groups recommended organizing a
195
-------
steering committee to include engineers, scientists,
businesspeople, government staff, politicians, environ-
mental groups, developers, local citizen advisors,
homeowners, and other interested people.
Watershed Plan
A detailed watershed plan must be developed using as
thorough an understanding of the problem as possible.
The groups identified the following major elements of a
watershed plan:
• Designate a lead board or agency.
• Develop an effective institutional framework.
• Assess the adequacy of the existing growth manage-
ment plan.
• Collect, organize, and assess information on the ex-
isting infrastructure (sanitary districts, zoning),
topography, hydrology, soils, nonpoint sources
(stormwater outfalls), underground storage tanks,
water quality (nitrate levels in ground water; bacteria
levels in clams), and other environmental concerns.
The Town of Barnstable's new geographic informa-
tion system (GIS) was considered to be a very help-
ful tool in completing this task.
• Develop a strong public awareness element.
* Develop a very detailed zoning map.
• Develop a comprehensive 20-year growth manage-
ment plan.
• Identify appropriate technologies.
• Evaluate the effectiveness of various alternatives
(e.g., retrofit versus prevention) and the means by
which the technologies can be implemented (e.g., in-
stitutional).
• Set priorities for the use of technologies.
• Develop a budget, cost estimates, and a schedule
with milestones.
• Develop a system to track progress and provide
feedback.
Monitoring
The workgroups agreed that the monitoring program
should focus both on the impacted resources (e.g.,
shellfish beds and ground water) as well as the
suspected sources of contamination (e.g., septic systems
and stormwater). In general, the monitoring program
should:
• Review existing data
• Continue Board of Health monitoring of shellfish and
recreational waters for bacterial contamination
• Monitor effectiveness of stormwater treatment
facilities and the presence of illicit connections
between septic tanks a'nd the stormwater con-
veyance system
• Monitor specific locations to aid in problem assess-
ments, estimating loads, and determining individual
sources
• Assess the status of wellhead protection in the
project area
• Monitor the effects of remedial activities as they are
implemented
Technology Transfer
The following nonpoint source controls were considered
most promising for application in the Barnstable case:
• Mobile boat pump-outs.
• Stormwater infiltration techniques, providing they are
tested in the Barnstable environment before they are
implemented on a widespread basis
*_ Limitation of impervious services in new develop-
ments
• Creation of open spaces (purchase easements)
• Septic system management programs
• Expansion of underground storage tank controls and
dissemination of information to industries that might
need to add controls to underground storage tanks
• Landfill controls
• Encouragement of social pressures to control ac-
tivities such as curbing pets and conserving water
• Wastewater management
The groups mentioned that site-specific factors, such as
water table elevation, costs, location, soil type, topog-
raphy, seasonality, maintenance and operation, and lon-
gevity should be considered in selecting and/or applying
NPS controls. Group members generally agreed that
preventative measures should receive priority over
remedial measures whenever practicable. Controls that
provide multiple benefits and/or treat "all" pollutants were
also preferred.
Information and Education
The groups agreed that the flow of information is very im-
portant and needs to be multidirectional and continuous
among local officials, citizen groups, schools, chambers
of commerce, commercial fishermen, tourists, industry
official, and the media. Project coordinators should
provide information on costs, alternatives, health
aspects, demonstration projects, and opportunities for
citizen involvement.
Workgroup members agreed that public education and
involvement must begin early, reflect specific project
196
-------
phases, target specific audiences (especially influential
groups), account for the seasonal variation in the popula-
tion, and be upbeat and optimistic. This approach should
build grassroots support to implement and pay for solu-
tions and reduce pollutants at their source. The groups
identified town meetings, mailings, field days, local press,
radio, and other media as useful communication
vehicles. One group suggested that a survey of
residents' views of the NPS problem would be useful in
gaining public support. Invited outside experts also could
generate ideas for solving the problems.
Program Evaluation
One way the program could be evaluated is to examine
the program's impact on the use of the affected resour-
ces, such as shellfish beds or beaches. The level of
nitrates in ground-water supplies was also noted as an
important ranking parameter. Implementation levels
could be evaluated, such as by how many septic sys-
tems have been improved. Information and education
whether programs could be evaluated by observing
people's behavior has changed and their interest in solv-
ing the problem has increased.
Stormwater Treatment Financing
Some recommendations for creative ways to finance
stormwater facilities were to establish stormwater and/or
NPS utilities, septic system maintenance districts, and
tax deductions (favored over charging fees) for
homeowners and businesses upgrading septic systems
or stormwater facilities.
CASE STUDY #2—EASTERN
AGRICULTURE—GROVE LAKE WATERSHED
Background
Grove Lake and its watershed are located in Pope Coun-
ty, in west-central Minnesota. The watershed is 10 mi
long and 6 mi wide. Grove Lake has a surface area of
378 acres, average depth of 8.6 ft, a maximum depth of
31 ft, and a shoreline length of 5.7 mi (see Figure 4). It is
used for fishing, swimming, boating, water skiing, aes-
thetics, and wildlife watching.
Grove Lake is epilimnetic in the summer and has the fol-
lowing long-term mean measures: total phosphorus of
44 u.g/L, secchi disc of 2.4 m, and chlorophyll a of 20.5
jig/L Nuisance algal blooms occur for 50 to 60 percent
of the growing season. Agricultural runoff increases
levels of sediment and nutrients to the lake, and septic
systems adjacent to the lake may also cause water-
quality problems. In the watershed's wetlands, ditching is
lowering water levels and volumes. Average rainfall is 25
inches per year, average lake evaporation is 30 inches
per year, and the lake generally is free from ice from
April 15 through November 15. Around the lake, the land
is either nearly level or gently sloping. On the north-
eastern side of the lake, 80 percent of the soil is subject
to drought and soil blowing, and 65 percent of the soil is
subject to erosion around the rest of the lake.
About 95 percent of the land around GroVe Lake is in
private ownership, 5 percent is owned by the U.S. Fish
and Wildlife Service, and less than 1 percent is a town
park. The following land patterns exist: 44 percent
agriculture (crops and domestic animals), 23 percent
pasture, 21 percent wetlands, 6 percent water, and 5
percent forested. In the watershed, there are ap-
proximately 25 farmsteads, 60 to 75 landowners away
from the lake, and 65 landowners adjacent to the lake.
There are 19 permanent and 46 summer homes along
the lake. A town-owned park on the northeast corner of
the lake includes a boat ramp, swimming beach, and a
picnic area.
A watershed management plan is being developed for
the Grove Lake area. Goals of the plan are to improve
water quality, recreational use, and wildlife habitat, and
to reduce sedimentation, flooding, and erosion problems.
Specifically, the following summer epilimnetic water
quality goals for Grove Lake are being proposed: 35 u.g/L
mean total phosphorus (a 38 percent reduction in the
current phosphorus load), 2.4 m mean secchi disc, 12
|ig/L mean chlorophyll a, and nuisance algal bloom
periods for less than 20 percent of the growing season.
The North Fork Crow River Watershed District
(NFCRWD) is sponsoring the development of the water-
shed management plan. NFCRWD has received a 50
percent matching grant from the Minnesota Pollution
Control Agency (MPCA). The Grove Lake Lake Associa-
tion (GLLA) was instrumental in securing the grant and
provides input into plan development. Local project rep-
resentatives are the treasurer and a board member of
the NFCRWD. A consulting firm has been hired to con-
duct the water-quality investigation, and the Pope Soil
and Water Conservation District and the Soil Conserva-
tion Service are conducting the watershed/nonpoint
source (NPS) evaluation. The Agricultural NPS Pollution
Control Model is being used to determine critical areas,
identify necessary best management practices, and es-
timate nonpoint pollution reduction. A GIS assessment of
nonpoint pollution priority areas also is being evaluated.
Water-quality monitoring will be conducted and will be
continued for at least one year after the plan is imple-
mented. The project will be evaluated through an assess-
ment of the BMPs implemented, and a comparison of
water-quality measures and how they relate to the
specified water quality goals. Technology transfer may
be pursued through fact sheets, individual contacts,
group meetings, newsletter articles, field demonstrations,
and tours. Public education and information may be
provided through the GLLA newsletter and annual meet-
ings, public meetings concerning the plan, and a
NFCRWD newsletter.
The MPCA has the authority to govern the storage,
transportation, disposal, and utilization of animal manure.
197
-------
GROVE LAKE
WATERSHED
LEGEND
* SAMPLE STATIONS
M WATER
— SUBWATERSHED
m USFWS LAND
1 mile
Grove Lake
Sampling
Watershed
Locations
ĄRM
Water Research
&
Management,
Inc.
14
St
Seventh
Cloud.
Ave
MN
N.
56303
Figure 4. Grove Lake watershed.
A joint county-state program to address agricultural
runoff is desirable because it promotes local involve-
ment, minimal disruption to agricultural operations, and
environmental protection. The county has the authority to
regulate onsite sewage treatment systems, but has not
adopted any ordinances. By 1993, the county will be re-
quired to enforce specific standards for onsite sewage
treatment systems on all dwellings in the shoreland
areas.
Case Study Questions
1. What are the most important and challenging
problems that need to be addressed in the water-
shed management plan?
2. How do the project goals and objectives relate to
each other? Are there any other goals and objectives
that might be worthy of consideration?
3. How can the individuals and organizations involved
with the water management plan (the cooperators)
best work together toward achieving water-quality
goals? What should the roles of each cooperator be?
How do the roles interrelate and contribute to the
5.
6.
achievement of objectives? What are the estimated
costs of involvement for the cooperators? What in-
stitutional barriers or breakdowns might exist and
what institutional arrangements should be recom-
mended?
What is an appropriate regulatory strategy that util-
izes the identified authorities and encourages land-
owners to implement NFS control measures in a
timely manner? What are the needed regulatory
capabilities for this project? How could they be used
to stimulate implementation of NFS controls? What
would be the positive and negative impacts of using
regulatory capabilities in the project?
Prepare a step-by-step watershed plan that will
enable the time.ly implementation of needed prac-
tices in critical areas. What roles should be played by
each project cooperator? What is a reasonable time
frame for accomplishing each step in the plan? Es-
timate the cost of the plan and relate those costs to
the project budget.
What particular NFS controls appear most promising
to address the problems found in this watershed?
198
-------
What are the specific steps needed to develop sys-
tems for each site that, when combined with all other
site plans in the watershed, will contribute to meeting
water-quality objectives? Make recommendations as
to the types of site plans that are most needed in the
project area. What would barriers be to the im-
plementation of these recommendations? How might
these barriers be overcome? What would the costs
be of these recommendations? What role would the
cooperators play?
7. What steps should be taken to:
a. review and interpret existing data?
b. develop specifics for a monitoring program (site
locations, sampling frequency, parameters,
QA/QC, etc.)?
c. develop an analytic approach?
d. line up needed resources and cooperation (in-
cluding easements)?
e. establish the role of monitoring data in project
development (including monitoring of BMP main-
tenance)?
8. Develop a monitoring program based upon the infor-
mation given. Include any initial provisions (e.g., ini-
tial sampling to get a handle on variability) that must
be made to develop a cost-effective monitoring
program. Estimate associated costs.
9. How can technology transfer become an integral part
of the project? What are the benefits and costs of
technology transfer? Which cooperators should per-
form what functions? When?
10. What outside information or knowledge should be
brought into this project? What can be taken from
this project and shared with others?
11. What additional methods could be used to inform the
general public and affected landowners? What
mechanisms should be used to implement these-
methods, and what are the costs?
12. Develop a project evaluation plan, including evalua-
tion objectives, analytic approaches to be used in
evaluating the project, information needs, methods
for collecting information, schedule, roles of
cooperators, and reporting of findings.
Problem Identification
Group members agreed that in addition to understanding
the physical, chemical, and biological condition of the
lake and its watershed, it would be critical to understand
how individuals or groups that live within the watershed
or use the lake perceive the problems. If the problem is
not clearly understood and defined, much effort could be
expended on improvements not perceived as problems
by lake users. Those responsible for solving the problem
at Grove Lake should also become knowledgeable about
how the problem was manifested, what symptoms are
present, if current data are adequate to diagnose the
problem and develop an implementation plan, or if further
studies are necessary. It also will be necessary to under-
stand socioeconomic issues, special interests, and politi-
cal realities.
Goals and Objectives
Playing the role of a local steering committee, one of the
workgroups formulated three primary goals: 1) to im-
prove water quality and restore wetlands, 2) to make the
project a community effort, and 3) to maintain farm
profitability. The group's objectives for improving water
quality were to define the specific lake water quality
desired, pollutant loading goals, and implementation al-
ternatives. Specific environmental goals have been ini-
tially set to reduce sediment loading to Grove Lake by 75
percent by 1998 and phosphorus loading by 38 percent.
The objectives for involving the community were to en-
sure that the public understands the issues and agrees
that there is a problem; to use existing institutional arran-
gements to the extent possible; and to make education
the initial priority.
Institutional Arrangements
The workgroups considered the formation of one or more
of the following institutional arrangements: a citizens
group to discuss issues, promote education, and surface
needs; an issues group that would include agricultural
representatives and other special interests; and a techni-
cal group, which would direct water-quality monitoring
and watershed assessment.
The groups agreed that a watershed district could serve
as the lead local governmental organization with an initial
activity of conducting a public information meeting to ex-
plain the project. Prior to this meeting, one-on-one dis-
cussions with leading representatives of the community
and target agencies (local, state, and federal) should be
arranged to provide accurate information to potential
speakers. At the meeting, support would be sought for
forming a Grove Lake Restoration Project steering com-
mittee. At a minimum, participation would be sought from
the watershed district, local soil and water conservation
district, state pollution control agency, lake association,
farm representatives, civic leaders, other community
leaders, and any special interest groups that emerge. A
follow-up to the meeting would be to provide the atten-
dees with a summary of what took place and to ask them
for additional input.
The steering committee would be chaired by a lay person
to aid in acquiring community ownership and to minimize
the potential for turf battles in setting project direction.
Staff from the MPCA and local districts would serve the
committee and provide technical guidance. A project
199
-------
consultant would conduct technical studies necessary
under the guidance of MPCA technical staff assigned to
the committee. Subcommittees could be formed, such as
a farm committee to assist in developing an implementa-
tion strategy for best management practices.
Watershed Plan
The workgroups identified three major areas of action for
a watershed plan. The first area was to educate the
public and build a community consensus to protect the
lake and its watershed. The second area was to seek
technical information and assistance from agencies, in-
cluding information on standards, violations, and uses of
the lake. The third area was to develop a detailed water-
shed plan that clearly identifies the problem and avail-
able tools/measures to solve the problem; sets
performance targets and a schedule; obtains commit-
ments by agencies, landowners, etc., to achieve
schedule milestones; and tracks progress.
The groups agreed that it also is important to understand
what tools currently are available to implement the
needed changes in the local land use and management.
Current state and local regulations, incentives, issues re-
lated to zoning ordinances, and plans for septic tanks
and feedlots must be assessed in terms of how they af-
fect Grove Lake. Financial commitments necessary to
implement the watershed protection program must be
made and funding must be secured. It would be useful to
evaluate the experiences of similar watershed protection
efforts. A water-quality monitoring plan should be
developed to establish baseline conditions and document
changes.
Information and Education
Education is a cornerstone of the implementation
strategy. Some available outlets for education include
youth organizations, media, and informal conversations.
Use of trained educators, including the school system
and extension service is important. Building bridges
between historically adversarial groups should be done
slowly and carefully. Whenever possible, issues should
be discussed in a context that appeals to individuals, i.e.,
"How does this benefit me or my children?" Finally, those
active in the project will need to accept varying levels of
acceptance by agencies, groups, and individuals.
Evaluation
To be accountable to the community as well as the
stakeholders (i.e., the funding sources), it is important to
evaluate the success of the project. The more clearly the
project goals and milestones are defined, monitoring sys-
tems are designed, and information is reported, the
easier it will be to evaluate the project. A final report
should be prepared that documents activities undertaken
and presents a project evaluation.
CASE STUDY #3—WESTERN
AGRICULTURE—OTTER CREEK WATERSHED
Background
Otter Creek is in the Great Basin hydrologic region of
Utah (see Figure 5). About one-third of the creek is in
Sevier County and two-thirds is in Piute County. The sur-
rounding watershed covers 240,000 acres and has a
topography characterized by mountains and valleys.
Otter Creek is diverted for irrigation in many locations.
The Koosharem Reservoir (at .the headwaters of Otter
Creek) and the Otter Creek Reservoir (at the end of the
creek) are used for fishing, boating, irrigation, and live-
stock watering. There is a state park facility on the south
shore of Otter Creek Reservoir.
Water-quality problems occur because of runoff from
livestock production, overgrazing, poor irrigation water
distribution and low irrigation efficiency (this has im-
proved in the last 10 to 15 years and sprinkler systems
now predominate), unstable streambanks, poor riparian
zone condition, and (potentially) pesticide use. Erosion
rates in some areas are 9 to 18 tons/acre/year (com-
pared with the Soil Conservation Service standard of 2
tons/acre/year). Sediment deposition in the watershed
exceeds 50 acre-feet/year. The creek fails state water-
quality standards for total phosphorus, nitrogen, total dis-
solved solids, and sodium, and contains high coliform
levels. Sedimentation in the reservoirs reduces their
storage capacities. The Otter Creek Reservoir fails state
water quality standards for total phosphorous,
nitrate/nitrite, sediments, nitrogen, and turbidity and is
eutrophic (and deteriorating).
Land ownership in the watershed is 50 percent Bureau of
Land Management (BLM), 35 percent Forest Service, 10
percent private, and 5 percent state. Land-use patterns
are 95 percent rangeland and 5 percent cropland. There
are 109 farm owners living in the area and 30 to 35 ab-
sentee owners. About 100 are limited-resource farmers,
6 are handicapped farmers, and 15 are minority farm
owners. Average farm size is 110 acres. There are 400
to 450 people in four communities within the watershed.
Most income is generated through livestock production.
There are high-intensity rains and rapid snow melt in the
area. Average crop growing seasons are May 15 to Sep-
tember 15 for alfalfa, April 28 to August 26 for spring
grain, June 2 to September 30 for field corn, and April 28
to October 18 for pasture. Below 8,000 ft elevation, soils
are shallow to deep gravelly and cobbley loams under-
lain with sandstone and shale bedrock; soils are well
drained with moderate to slow permeability; runoff and
sediment production are moderate; and vegetation con-
sists of big sagebrush, oakbrush, pinion pine, and as-
sociated grasses, forbs, and shrubs. Above 8,000 ft, soils
are moderate or deep acidic loams, silt loams, and clay
200
-------
'__si .<<[-••$ \\r
.. K:AA
Otter Creek Watershed
Hydrologic Unit
DIXIE NATIONAL FORES
-"' •
V) •
Figure 5. Otter Creek watershed.
201
-------
loams underlain by bedrock at a depth of 0 to 60 in. or
more; soils are well drained with slow to rapid per-
meability; runoff is slow to medium and sediment produc-
tion is moderately low; and, vegetation consists of aspen,
fir, grasses, forbs, and shrubs.
Otter Creek was once a very productive fishery. Live-
stock grazing, irrigated agriculture, and upstream reser-
voirs all contribute to the nonpoint source-related
problems downstream. Those using and responsible for
managing the watershed aim to alleviate the problems
through some type of cooperative effort. The goals for
the project include:
* Improve water quality so it meets state standards
• Minimize streambank erosion
* Reduce coliform and nutrient loadings, as well as
other contaminants
• Improve riparian habitat
* Provide for improved recreational use
* Inform the public about water-quality management
• Implement a planned water treatment and monitoring
program.
Appropriate management practices for the area include
permanent vegetative cover, irrigation water conserva-
tion, streambank protection, livestock exclusion, and
fencing.
Piute County Soil Conservation District (SCO), the Utah
Department of Agriculture, the Cooperative Extension
Service (CES), and the SCS will select a Project Coor-
dinator (which will be partially funded by the U.S. EPA).
The Coordinator will organize committees and coordinate
activities between the committees and local, state, and
federal agencies. Financial assistance is provided by the
Agricultural Stabilization and Conservation Service and
the Utah Department of Agriculture for improvements in
irrigation management. The SCS will provide technical
assistance to farmers and ranchers. Coordination with
the Forest Service and the BLM to control erosion on
federal lands will be necessary. The CES will conduct
public information activities on agricultural and nonpoint
source (NPS) pollution problems, farming practices being
used to address problems, and the promotion of best
management practices (BMPs). The overall project
budget will be $140,000 each year from 1991-1995.
Case Study Questions
1. What are the most important and challenging
problems that need to be addressed in the water-
shed management plan?
2. Discuss the goals and objectives for this project.
How do the project goals and objectives relate to
each other? Are there any other goals and objec-
tives that might be worthy of consideration?
3. How can the individuals and organizations involved
with the water management plan (the cooperators)
best work together toward achieving water quality
goals? What should the roles of each cooperator be?
How do the roles interrelate and contribute to the
achievement of objectives? What are the estimated
costs of involvement for the cooperators? Should the
Project Coordinator have any authorities to carry out
his/her responsibilities? What would be a reasonable
set of authorities? What institutional barriers or
breakdowns might exist and what institutional arran-
gements should be recommended?
4. What is an appropriate regulatory strategy that util-
izes the identified authorities and encourages land
owners to implement NPS control measures in a
timely manner? What are the needed regulatory
capabilities for this project? How could they be used
to stimulate implementation of NPS controls? What
would be the positive and negative impacts of using
regulatory capabilities in the project?
5. Prepare a step-by-step watershed plan that will
enable the timely implementation of needed prac-
tices in critical areas. What roles should be played by
each project cooperator? What is a reasonable time
frame for accomplishing each step in the plan? Es-
timate the cost of the plan and relate those costs to
the project budget.
6. Discuss specific steps, needed to develop systems
for each site that, when combined with all other site
plans in the watershed, will contribute toward meet-
ing water-quality objectives. Make recommendations
as to the types of site plans that are most needed in
the project area. Comment on barriers to implemen-
tation and how these might be overcome. Estimate
costs and identify the roles of cooperators. ,
7. What steps should be taken to:
a. review and interpret existing data?
b. develop specifics for a monitoring program (site
, locations, sampling frequency, parameters,
QA/QC, etc.)?
c. develop an analytic approach?
d. line up needed resources and cooperation (in-
cluding easements)?
e. establish the role of monitoring data in project
development (including monitoring of BMP main-
tenance)?
8. Develop a monitoring program based upon the infor-
mation given. Include any initial provisions (e.g., ini-
tial sampling to get a handle on variability) that must
be made to develop a cost-effective monitoring
program. Estimate associated costs.
202
-------
9. How can technology transfer become an integral part
of the project? What are the benefits and costs of
technology transfer? Which cooperators should per-
form what functions? When?
10. What outside information or knowledge should be
brought into this project? What can be taken from
this project and shared with others?
11. What methods could be used to inform the general
public and affected landowners? What mechanisms
should be used to implement these methods, and
what are the costs? What assistance, if any, should
be provided to CES to carry out the public informa-
tion campaign?
12. Develop a project evaluation plan, including evalua-
tion objectives, analytic approaches to be used in
evaluating the project, information needs, methods
for collecting information, schedule, roles of
cooperators, and reporting of findings.
Workgroup Problem Identification
The major environmental problems related to the water-
shed relate to the loss of riparian vegetation that stabi-
lizes the stream banks and the degradation of water
quality due to agriculture (excess nutrients and tempera-
ture changes). These water-quality problems directly af-
fect fishery values, aesthetics, recreation, drinking water,
and perhaps ground-water resources due to changes in
the stream geometry.
Some workgroup members felt that the problem was en-
hanced because the area lacks management flexibility.
For example, there are a lack of alternatives for relocat-
ing livestock. Some felt that even if livestock grazing was
discontinued, vegetation still would not return.
Goals and Objectives
Workgroup members agreed that the primary objective of
the project should be to enhance fish and wildlife. The
long-term objective would be to improve the area and
provide additional forage for livestock. „
Institutional Arrangements
Workgroups believed that the key to improving the water-
shed was to involve the local residents in the program.
Some suggestions included:
• Targeting local influential people and educating them
on the need for improved water quality.
• Utilizing small and large demonstration projects
sponsored by local scouting groups, churches,
schools, 4-H clubs, and similar organizations. An
"Adopt-a Stream" project is one example.
• Involving participation by land management agen-
cies, such as the Bureau of Land Management
(BLM) and the Forest Service.
• Educating the public, especially schoolchildren. One
group suggested that a survey conducted before and
after the project began would measure the effective-
ness of the education and information programs.
Many people in the area believe that if they do not par-
ticipate in the project, then a higher authority, such as the
U.S. Environmental Protection Agency, will take over.
Watershed Plan
The workgroups made several recommendations for an
Otter Creek watershed plan. Group members suggested
that the sources of the problems be mapped out to
properly manage the entire watershed, not just the
riparian zones. Natural recovery measures should have
priority over artificial measures. The workgroups also
agreed that it would be useful to develop a consensus
"vision" of what the area could look like after remedial
strategies were in place. It would also be useful to
develop "win-win" attitudes.
Workgroup members felt that cost-sharing should be
provided to help make the adjustment process as easy
as possible for those being affected by the plan and en-
courage participation by others.
CASE STUDY #4—FORESTRY—SOUTH FORK
SALMON RIVER WATERSHED
Background
The South Fork of the Salmon River (SFSR) is in central
Idaho. The surrounding watershed is in Valley County
and covers 237,098 acres (see Figures 6 and 7). The
topography is characterized by steep canyons with sharp
intervening ridges and steep basin slopes (many are
over 70 percent). The area primarily is forested and has
ponderosa pine at lower elevations, coniferous trees in
middle elevations, and subalpine fir at higher elevations.
Meadows are found along the stream course. The water
resources of the SFSR come primarily from snowmelt
(peak time is in the spring), which runs off directly into
"the drainage system and recharges ground water to
maintain baseflow in the river. Discharge from the lower
end of the SFSR ranges from a baseflow of 1,000 to
3,000 cubic feet per second (cfs) to 3,000 cfs in
springtime to 100 to 200 cfs during the rest of the year.
The SFSR is used for fish spawning and rearing—
Chinook and steelhead, which travel from the Pacific
Ocean, and local trout (see Figure 8). Average annual
precipitation varies with elevation from 20 to 60 inches;
most falls in winter as snow. The river flows on a granitic
bedrock formation composed mainly of quartz mon-
zonite. Soils are primarily coarse-textured and extremely
erosive because of high degrees of weathering.
Spawning is being impaired by water-quality problems
(primarily sedimentation). In the 1960s, a. large wildfire
and rain and snow events caused massive sedimentatibn
203
-------
Project Map - South Fork
Salmon River - North Half
Roads
SF Salmon River
Poverty burn
Figure 6. South Fork Salmon River—north half.
204
-------
in the area. Sediment yield has been monitored in the
SFSR since 1965. It peaked above 20,000 cubic meters
per year (m3/yr) (with an estimated 2,000,000 m3
delivered to the river channel). By 1980, sediment yield
declined to 3,000-4,000 m3/yr. Ultimately the river began
to carry fine sediments downstream. Currently surface
fines are between 10 and 15 percent, while depth fines
are between 20 and 36 percent. Cobble embeddedness
ranges from 14 to 56 percent. Nonpoint sources are
responsible for all sediments in SFSR. About 84 percent
of the sediment comes from natural sources (other than
burns), 14 percent comes from roads (logging and other),
and 2 percent comes from new burns.
All but a few hundred acres in the area are in federal or
state ownership, primarily National Forest System land.
There are no communities within the watershed, al-
though there are some summer homes and lodges (two
of which are year round) under special-use permits by
the Forest Service. Land use mostly has been for timber,
but there is currently a moratorium on both timber har-
vesting and road building. The moratorium was estab-
lished in 1966, lifted in 1978, and reinstated in 1984.
Grazing has been removed, and although there has been
some mining in the past, none currently occurs. Several
sediment control measures have been undertaken, in-
cluding the logging moratorium, dragline removal of sand
and gravel cleaning from stream beds, attempts to stabi-
lize cuts and fills on roads, reclamation of roads by mul-
ching and grass seeding, water barring fire lines, grass
seeding, and contour felling of trees. Road paving and in-
tensified cut and fill slope stabilization also have been
proposed.
The goal of the project is to restore the impaired benefi-
cial uses, namely Chinook and steelhead spawning.
Specific objectives are to increase the survival of young
fish and to establish appropriate depth fines, dissolved
oxygen concentrations, and cobble embeddedness for
spawning. A total maximum daily load (TMDL) should be
developed to identify practical levels of sediment reduc-
tion, prescribe best management practices (BMPs), and
monitor success. Site-specific and beneficial use status
monitoring will be conducted. The Forest Service also
has developed a recovery plan that, if implemented, is
expected to reduce half the volume of man-caused
sedimentation to the river if implemented. The SFSR In-
teragency Coordination team, which includes repre-
sentatives from Idaho Division of Environmental Quality,
Payette National Forest, Boise National Forest, U.S.
Forest Service-lntermountain Research Station, and
EPA-ldaho Operations Office, will work to develop the
TMDL and the rest of the program. The Forest Service,
Idaho Division of Environmental Quality, and EPA will
secure necessary funds.
Case Study Questions
1. What are the most important and challenging
problems that need to be addressed in the water-
shed management plan?
2. How do the project goals and objectives relate to
each other? Are there any other goals and objectives
that might be worthy of consideration?
3. How can the individuals and organizations involved
with the water management plan (the cooperators)
best work together toward achieving water-quality
goals? What should the roles of each cooperator be?
How do the roles interrelate and contribute to the
achievement of objectives? What are the estimated
costs of involvement for the cooperators? What in-
stitutional barriers or breakdowns might exist and
what institutional arrangements should be recom-
mended?
4. What is an appropriate regulatory strategy that util-
izes the identified authorities and encourages land-
owners to timely implementation of nonpoint source
(NPS) control measures? What are the needed
regulatory capabilities for this project? How could
they be used to stimulate implementation of NPS
controls? What would be the positive and negative
impacts of using regulatory capabilities in the
project?
5. Prepare a step-by-step watershed plan that will
enable the implementation of needed practices in
critical areas in a timely manner. What roles should
be played by each project cooperator? What is a
reasonable time frame for accomplishing each step
in the plan? Estimate the cost of the plan and relate
those costs to the project budget.
6. What particular NPS controls appear most promising
to address the problems found in this watershed?
What are the specific steps needed to develop sys-
tems for each site that, when combined with all other
site plans in the watershed, will contribute to meeting
water-quality objectives? Make recommendations as
to the types of site plans that are most needed in the
project area. What would barriers be to the im-
plementation of these recommendations? How might
these barriers be overcome? What would the costs
be of these recommendations? What role would the
cooperators play?
.7. What steps should be taken to:
a. review and interpret existing data?
b. develop specifics for a monitoring program (site
locations, sampling frequency, parameters,
QA/QC, etc.)?
205
-------
Project Map - South
Fork Salmon River
- South half -
Roads
SF Salmon River _
Figure 7. South Fork Salmon River—south half.
206
-------
Segmen t 918
UPPER S. F. SALMON RIVER
Major Tribs. above Secesh R.
Glory Hole
K r a s s e I
S e gme n t 919
Segme n t 920
P o v e r t y
Lower Sto
Upper Sto
Scale 1 : 254576
i i i 4 5
Miles
Major spawning areas
Figure 8. South Fork Salmon River—spawning areas.
207
-------
c. develop an analytic approach?
d. line up needed resources and cooperation (in-
cluding easements)?
e. establish the role of monitoring data in project
development (including monitoring of BMP main-
tenance)?
8. Develop a monitoring program based upon the infor-
mation given. Include any initial provisions (e.g., ini-
tial sampling to get a handle on variability) that must
be made to develop a cost-effective monitoring
program. Estimate associated costs.
9. How can technology transfer become an integral part
of the project? What are the benefits and costs of
technology transfer? Which cooperators should per-
form what functions? When?
10. What outside information or knowledge should be
brought into this project? What can be taken from
this project and shared with others?
11. What additional methods could be used to inform the
general public and affected landowners? What
mechanisms should be used to implement these
methods, and what are the costs?
12. Develop a project evaluation plan, including evalua-
tion objectives, analytic approaches to be used in
evaluating the project, information needs, methods
for collecting information, schedule, roles of
cooperators, and reporting of findings.
Case Study Problem Identification
The primary NFS problem at the SFSR is fine sediments,
which impair salmon spawning. Adding to the problem
are the adverse effects of the Columbia and Snake River
dams, which are known to increase smolt salmon and
steelhead mortality and inhibit the return of adults to the
spawning areas. Recovery of the water quality and
spawning reaches is expected only if the sediment load
from the drainage can be further reduced.
Goals and Objectives
• Restore 75 percent of the potential habitat quality for
salmon spawning and recover about 75 percent of
the potential natural recruitment of salmon in the
South Fork system.
• Use recently developed models to predict changes in
sediment yield as a result of applying the total maxi-
mum daily load (TMDL). State the statistical con-
fidence when reporting model outputs.
• Determine to what degree habitat is impaired by
natural incoming sediment. Use a reference stream
(Middle Fork Salmon River) to evaluate and account
for natural spatial and temporal variability. Base the
habitat recovery goal of 75 percent of potential on
the reference comparison.
• Determine the man-caused sediment sources, rela-
tive magnitude of each source, and what proportion
of this sediment yield can be eliminated by applying
nonpoint source controls.
• Use the refined sediment yield model to compare the
relative effectiveness of treatments and prioritize
specific sources requiring treatment.
• Produce an implementation plan which focuses on
treatment application, monitoring to link treatment ef-
fectiveness to beneficial use recovery, and
mechanisms to modify treatments if recovery is not
being achieved.
• Use the feedback loop process to assure that the
water-quality goals are attained.
Institutional Arrangements
The workgroups decided that the involvement of the fol-
lowing agencies, interest groups, and the general public
was important to the SFSR recovery effort:
• Forest Service, which manages the land and has
conducted most of the research on the SFSR. The
Service could link the TMDL planning to the National
Forest Management Plan and could provide a good
starting point for a technology-based approach to
restoring the beneficial uses in the system.
• U.S. Fish and Wildlife Service and the Northwest
Power Planning Commission, both of which are
charged with stewardship of the salmon and steel-
head populations.
• U.S. EPA, responsible for implementing the Clean
Water Act.
• Idaho Division of Environmental Quality (DEQ) and
Department of Fish and Game.
• Idaho state government and Idaho's U.S. Senators,
due to a number of sensitive political issues in the
basin.
• Special interest groups, including the Columbia River
Intertribal Fish Commission, Idaho Conservation
League, Wilderness Society, Idaho Sportsmen's
Coalition, Trout Unlimited, and the timber industry.
• Local citizens.
The workgroups also suggested that those involved in
the project should try to persuade the Forest Service to
make the implementation of the recovery plan a priority
funding activity.
Watershed Plan Development
One workgroup felt that the TMDL approach is ap-
propriate for developing the watershed plan and had no
further comments. Another workgroup decided that a
policy advisory committee (PAC) should be formed under
the leadership of the DEQ to review all recovery plans
208
-------
and coordinate public input. A technical advisory sub-
committee made up of land managers (Forest Service),
water quality regulatory agencies (DEQ and EPA), and
research" personnel (Forest Service Intermountain Sta-
tion) would identify BMPs and projects compatible with
existing plans. This subcommittee would also develop a
compliance schedule requiring completion of the
measures under TMDL conditions within five years. The
PAC and the general public would review the plan, which
would be implemented by the Forest Service with the as-
sistance of DEQ and EPA.
Site Planning and Selection of NPS Control
Measures
The workgroups felt that site-specific planning was im-
portant in selecting nonpoint source control measures
through the identification and prioritization of the most
cost-effective treatments, such as closing roads, directly
removing sediment from tributary streams, constructing
debris basins, implementing erosion control measures on
existing roads, and revegetating road cut and fillslopes.
The group also felt that the expensive treatment
proposed for the SFSR road will be much less effective
in reducing sediment sources than many other less cost-
ly alternatives in the watershed.
Monitoring
One workgroup felt that the DEQ should develop a 10-
year monitoring program to assess the effectiveness of
the implemented BMPs and projects. Workgroup mem-
bers suggested that monitoring should utilize a reference
comparison (Middle Fork Salmon River). The monitoring
proposed on the SFSR should be expanded to include
macroinvertebrates and critical reaches of the stream.
Technology Transfer
The plan managers would educate the project super-
visors, contractors, and others conducting the tasks on
the water-quality concerns for the SFSR. The public
would be informed on the status of the project as plan-
ning and implementation progressed, through periodic
field trips, a project newsletter, and media coverage.
Program Evaluation
One workgroup recommended .evaluating the SFSR
recovery project after five years. Another group sug-
gested that feedback from monitoring should be applied
to make "mid-course" corrections. If the results of the
monitoring indicated that the salmon spawning potential
was recovered, additional measures to reduce sediment
yields would be unnecessary. If the monitoring results in-
dicated insufficient recovery of salmon spawning poten-
tial, additional sediment yield reduction BMPs and
projects would be required. Data on sediment movement
into and through the system also should be used to
refine the sediment models so that they more accurately
predict the effects that sediment delivery can have on the
habitat. Public interest groups would also assess the per-
formance of the implementation agencies and guide the
further progress of the program.
*U.S. GOVERNMENT PRINTING OFFICE: 1 99 3 .750. 003.60115
209
-------
-------
-------
> m c
(ODD
CD < ^
'
X <=
™ in
0) (/>
O :
o ^
'
o n
0) Z,
m
01
CO
to
s S
13 I
"83
r* «r n
u X
•5 2.
>CD
m,
9
CO
an
m
-------