United States
           Environmental Protection
           Agency
Office of
Research and Development
Cincinnati, OH 45268
EPA/625/6-91/030
October 1991
           Technology Transfer
&EPA     Handbook
           Sewer System
           Infrastructure Analysis and
           Rehabilitation

-------
                                               EPA/625/6-91/030
                                                  October 1991
               Handbook

     Sewer System Infrastructure
      Analysis and Rehabilitation
    U.S. Environmental Protection Agency
    Office of Research and Development

Center for. Environmental Research Information

           Cincinnati, OH 45268
                                           Printed on Recycled Paper

-------
                                              Notice
This document has been  reviewed in accordance with the U.S. Environmental  protection Agency's peer and
administrative review policies and approved for publication. Mention of trade names orcommercial products does not
constitute endorsement or recommendation for use.

-------
                                              Contents


Chapter                                                                                      Page

.1       INTRODUCTION	1

        1.1     Purpose and Intended Audience	1
               1.1.1   Definition of Sewer System Infrastructure	1
               1.1.2   Importance of Maintaining Infrastructure System Integrity	1
               1.1.3   Existing Source Documents	4
        1.2     The Need for a Sewer System Infrastructure Handbook	4
               1.2.1   Changing Requirements	4
               1.2.2   Comprehensive Analytical Procedures	 5
        1.3     User's Guide	5
        1.4     References	5


2      REGULATORY REQUIREMENTS	.....7,

        2.1     Historical Background	7
        2.2     Summary of Applicable U.S. EPA and State Regulations	7
        2.3     Description of the Relative Roles of the U.S. EPA, State Agencies,
               and Local Agencies	...8
        2.4     Certification Requirements	8
               2.4.1   Historical Perspective	8
               2.4.2   Current Situation	8
        2.5     References	11


3      PRELIMINARY ANALYSIS OF SEWER SYSTEMS	13

        3.1     Introduction	13
        3.2     Historical Reasons for Sewer System Analysis and Evaluation	13
               3.2.1   Regulatory Requirements	13
               3.2.2   Structural Failure	13
               3.2.3   Capacity Limitations	13
               3.2.4   Citizens'Complaints	14
        3.3     Financial Reasons for Evaluation of Sewer Infrastructure Needs	, 14
               3.3.1   Need to Enlarge Service Area	14
               3.3.2   Budgetary Planning Needs	14
               3.3.3   Financial Planning	14
               3.3.4   Benefits Versus Cost of Sewer System Evaluation	15
        3.4     Methodology for Preliminary Sewer System Analysis	15
               3.4.1   Sources of Information and Preliminary Methods of Analysis	15
               3.4.2   Monitoring and Equipment Needs for Preliminary Analysis	19
        3.5     Infiltration and Inflow Analysis	19
                                                   in

-------
                                               Contents (continued)


Chapter                                                                                      Page
                                                                                                 \.
              3.5.1    Introduction	..19
              3.5.2   Preliminary Information Needed	20
              3.5.3   Rainfall Information	252
              3.5.4   Topographic and Geologic Information	23
              3.5.5   Groundwater Information	24
              3.5.6   Baseline Sewer Flows	24
              3.5.7   Analysis of Infiltration and Inflow	27
       3.6    Exfiftration and Its Impacts	32
              3.6.1    Introduction	32
              3.6.2   Summary of Information on Impacts	'.	32
              3.6.3   Consideration in I/I Analysis	 32
              3.6.4   Present and Future Environmental Impacts	32
              3.6.5   Exfittration Tests and Methods	32
       3.7    References	....35


4      SEWER SYSTEM EVALUATION	39

       4.1    Introduction	39
       4.2    Planning the Survey and Use of Sub-System Approach	40
       4.3    Physical Survey	40
              4.3.1    Aboveground Inspection	40
              4.3.2   Flow Monitoring	40
              4.3.3   Flow Measurement	40
              4.3.4   Manhole and Sewer Inspection	',	4(3
              4.3.5   Rainfall Simulation	4(5
              4.3.6   Smoke Testing	46
              4.3.7   Dyed Water Testing	4(5
              4.3.8   Water Flooding Test	4(5
       4.4    Cleaning	;	47
       4.5    Internal Inspection	47
              4.5.1    Television Inspection	;	47
              4.5.2   Photographic Inspection	•.	47
              4.5.3   Physical Inspection	47
       4.6    Cost-Effectiveness Analysis	47
       4.7    Case Study  Example and Detailed Method of Analysis	50
       4.8    References	,	56


5      CORROSION ANALYSIS AND CONTROL	;	59

       5.1    Introduction  and Background	59
       5.2    Types and Mechanisms of Corrosion	59
              5.2.1    Common Types of Pipe Corrosion	59
              5.2.2   Other Types of Corrosion	59
       5.3    Conducting a Corrosion Survey	59
              5.3.1    Factors Affecting Corrosion	;	59
              5.3.2   Identifying Likely Locations for Corrosion	60
              5.3.3   Performing Visual Inspections	60
             , 5.3.4   Collecting Data	60
                                                  IV

-------
                                                Contents (continued)


Chapter                                                                                       Page

              5.3.5   Predicting Sulfide Corrosion	,.. 60
        5.4    Rehabilitating Corroded Sewers	60
        5.5    Controlling Corrosion	60
              5.5.1   Sulfide Corrosion Control	60
              5.5.2   Control of Other Forms of Corrosion	62
        5.6    References	63


6       SEWER SYSTEM REHABILITATION	65

        6.1    Introduction	65
        6.2    Excavation and Replacement	65
              6.2.1   Description.....	,	,	65
              6.2.2   Procedures and Equipment	 65
              6.2.3   Costs	66
        6.3    Chemical Grouting	66
              6.3.1   Description	66
              6.3.2   Costs	63
        6.4    Insertion	63
              6.4.1   Description	63
              6.4.2   Procedures and Equipment	65
              6.4.3   Costs	72
        6.5    Cured-ln-Place Pipe Inversion Lining	73
              6.5.1   Description	73
              6.5.2   Procedures and Equipment	74
              6.5.3   Costs	.74
        6.6     Fold and Formed	74
              6.6.1   U-Liner	•.	76
              6.6.2   NuPipe	76
        6.7    Specialty Concrete	77
              6.7.1   Description	77
              6.7.2   Procedures and Equipment	77
              6.7.3   Costs	.'	79
        6.8    Liners	79
               6.8.1   Description	79
               6.8.2   Procedures and Equipment	80
               6.8.3   Costs	82
        6.9     Coatings	82
               6.9.1   Description	82
               6.9.2   Procedures and Equipment	82
               6.9.3   Costs	83
        6.10   All Techniques for Manholes	83
               6.10.1  Description of Materials, Equipment and Products	83
               6.10.2  Description of Procedures	83
               6.10.3  Costs	85
        6.11    Service Lateral Techniques	:	85
               6.11.1  Description	,	85
               6.11.2  Procedures and Equipment	85
               6.11.3  Costs	•.	..85
        6.12   Miscellaneous Costs	86

-------
                                              Contents (continued)


Chapter                                                                                    Page

              6.12.1  Rehabilitation	86
              6.12.2  Costs for Preliminary and I/I Analysis with SSES	86
       6.13   Matrix of Problems and Applicable Corrective Measures	86
       6.14   References	87


GLOSSARY          	i	89
                                                 VI

-------
                                               Tables

Number                                                                                       Page

1-1     Construction Grants Funding Spending for Category IIIA	2
1-2    Construction Grants Funding Spending for Category IIIB	3
1-3    Summary of Handbook Contents	6

2-1     State Agency Regulations for Sewer System Improvements	9

3-1     Major Infrastructure Financing Mechanisms Advantages and Disadvantages	16

4-1     Sewer System Testing and Inspection Methods	'.	39
4-4    Cost Summary for SSES and Sewer Rehabilitation	51
4-3    Qualification of I/I Through the Subarea System
       Approach for the Washington Suburban Sanitary Commission	,	55
4-4    Cost Effective Analysis for I/I Reduction for the                       „
       Washington Suburban Sanitary Commission..;	55
4-5    Cost Effective Analysis by Point Source for I/I  Reduction for the
       Washington Suburban Sanitary Commission	55

5-1    Common Sewer Corrosion Problems and Applicable Rehabilitation Methods	61
5-2    Guidelines to Select Pipe Materials to Resist Corrosion	63

6-1    Rehabilitation Costs for Excavation and Replacement	66
6-2    Rehabilitation Costs for Grouting	69
6-3    Advantages and Disadvantages of Sliplining	69
6-4    Rehabilitation Costs for Sliplining with HPDE and Polybutylene Pipe	72
6-5    Rehabilitation Costs for Sliplining with PE Pipe	72
6-6    Rehabilitation Costs for Sliplining with Reinforced Thermosetting Resin	72
6-7    Miscellaneous Rehabilitation Costs for Sliplining	 73
6-8    Advantages and Disadvantages of Cured-ln-Place Lining	:	73
6-9    Rehabilitation Costs for Cured-ln-Place Inversion Lining	74
6-10   Advantages and Disadvantages of Specialty Concretes	79
6-11   Costs for Rehabilitation Using Specialty Concretes	80
6-12   Advantages and Disadvantages of Liners.....	81
6-13   Rehabilitation Costs for Lining with Cement Mortar and Shotcrete	82
6-14   Rehabilitation Costs for Lining with Anchors	82
6-15   Advantages and Disadvantages of Coatings	83
6-16   Costs for Rehabilitation Using Coatings	,	83
6-17   Advantages and Disadvantages of Manhole and Sump Rehabilitation Methods	84
6-18   Rehabilitation Costs-Manhole Techniques	:	 85
6-19   Service Lateral Rehabilitation Costs	86
6-20   Miscellaneous Additional Rehabilitation Costs	86
6-21   Sewer System Evaluation Survey Costs	86
6-22   Sewer Pipe Problems with Applicable Rehabilitation Methods	87
                                                   VII

-------
                                                Figures

Number                                                                                         Page

3-1    Approach to Conducting Sewer System Evaluation	17
3-2    I/I Analysis Major Activity Flow Chart	21
3-3    Static Groundwater Gauge Installation Elevation	25
3-4    Groundwater Gauge Installation Detail	26
3-5    Effects of Groundwater on Migration	29
3-6    Typical Entry Points of Rainfall Induced Infiltration	31
3-7    Determination of Total Yearly I/I	33
3-8    Determination of Total Yearly Infiltration	34

4-1    Sewer System Evaluation Flow Diagram	,	41
4-2    Typical Manhole Defects	44
4-3    Quick Method of Inspecting Sewer Lines	45
4-4    Preparatory Cleaning	48
4-5    Internal Color TV Inspection	49
4-6    Cost-Effectiveness Analysis Curve for Infiltration	!	53
4-7    Cost-Effectiveness Analysis Curve for Inflow	54

6-1    Grouting Equipment and Procedures	67
6-2    Insertion Methods	71
6-3    Installation of Cured-ln-Place Inversion Lining (Insituform)	75
6-4    U-Liner Installation method	;	77
6-5    NuPipe Installation Method	,	78
6-6    Detail of Liners with Anchors	:	81
                                                    Vill

-------
                                        Acknowledgments
The preparation and review of this Handbook was undertaken by many individuals. Contract administration was
provided by the U.S. Environmental Protection Agency's (EPA) Center for Environmental Research Information
(CERI).

Authors:
John M. Smith, Robert P. G. Bowker, and Hemang J. Shah - J. M. Smith & Associates, PSC, Consulting Engineers,
Cincinnati, Ohio

Peer Reviewers:
Philip M. Hannan - Washington Suburban Sanitary Commission, Hyattsville, Maryland
Roy C. Fedotoff - Metcalf & Eddy, Santa Clara, California
James F. Kreissl - U.S. EPA-RREL, Cincinnati, Ohio
Lam K. Lim - U.S. EPA, Washington, DC
Charles Pycha - U.S. EPA Region 5, Chicago, Illinois
Sarah C. White - Municipality of Metropolitan Seattle, Seattle, Washington

Peer Reviewers:
Andrew T. Cronberg - Department of Sanitary Sewers, Tampa, Florida
Henry N. Gregory - Public Utilities Department, Houston, Texas

Technical Direction/Coordination:
Denis J. Lussier - U.S. EPA-CERI, Cincinnati, Ohio
                                                 IX

-------

-------
                                           CHAPTER 1
                                           Introduction
Many of our nation's sewer systems date back over 100
years to the 19th century,  when brick sewers where
common.1 These and other more recent sewer systems
can be expected to ultimately fail in time, but because
they are placed underground, signs of  accelerated
deterioration and  capacity  limitations are not readily
apparent until there is a major failure. Sewer pipe failures
start with cracking, lateral deflection, crown sag and off-
set joints, as well as by deteriorated mortar and exposed
reinforcing caused by  hydrogen sulfide (H2S) corrosion.
Most of what the community sees is the inevitable result
of prolonged neglect, such as cracked pavement,
collapsed streets, backed-up sewers, streams and
groundwater contamination or local flooding.1 Proper
sewer  evaluation  and maintenance schedules would
help communities identify the condition of their sewer
system's infrastructure, and timely rehabilitation could
save the community large expenditures required to
replace the deteriorated sewers, and extend the sewer
use life. Tables 1-1  and 1-2  indicate the amount of
money spent for sewer system  major  rehabilitation
projects by U.S. EPA under the construction grants
program.2 In addition to the construction grants program,
municipalities and utilities have utilized State Revolving
Funds, Community Development Block Grant and other
funding options to fund Infrastructure needs. Adequate
sewer system Infrastructure  evaluation and rehabilitation
is of prime importance as the first step in this effort.

1.1    Purpose and Intended  Audience

This Handbook provides guidance on the evaluation and
rehabilitation of existing sewers. It presents information
on typical  problems, procedures and  methods for
rehabilitation, case study information, budgetary costs,
advantages and disadvantages of rehabilitation
techniques, and application of these techniques and
materials/equipment used in rehabilitation. It also guides
the reader in understanding  the importance of, and ways
for, conducting the  sewer system evaluation and
identifying the rehabilitation procedure that best suits a
particular problem. By necessity, information contained
in this Handbook for conducting a sewer  system
evaluation is general and not site-specific. The intent is
to present sufficient information to enable engineers and
public decision makers to plan and conduct sewer system
evaluation and rehabilitation under circumstances which
might be encountered when dealing with a specific sewer
system.  Because a variety of circumstances are
encountered in sewer systems, all of the methodology
presented in this Handbook will not apply to each project.
It is emphasized that the reader should apply only those
portions of the  methodology that are relevant  to the
specific project under study.

1.1.1  Definition of Sewer System Infrastructure
Sewer system infrastructure conveys wastewater used
by  individuals  and by commercial and industrial
establishments to  wastewater treatment  facilities,
ultimately to be returned to the natural environment.
These systems protect public health and the environment
and encourage economic development.3

1.1.2  Importance of Maintaining Infrastructure
       System Integrity
The primary importance of sewer system evaluation and
rehabilitation is to maintain the structural integrity of the
sewer  system for dependable transfer of wastewater
from the source to the treatment facility.4 Since the
passage of Public Law 92-500 in 1972, more emphasis
has been placed on sewer rehabilitation to reduce the
hydraulic loads placed on the treatment  plants from
excessive infiltration/inflow (I/I). When the integrity of a
sewer system is allowed to deteriorate, extraneous water
from I/I sources enterthe sewers. These flows reduce the
capability of sewer systems and treatment facilities to
transport and treat domestic and industrial wastewaters.
As a result, wastewater treatment processes are upset
and poorly treated wastewater is discharged  to the
environment.

Infiltration occurs  when existing sewer lines undergo
material and joint degradation and deterioration, as well
as  when new sewer lines are poorly designed and
constructed. Inflow normally occurs when rainfall enters
the sewer system through direct connections such as roof
leaders, catch basins, manholes, and other direct cross
connections. The elimination of I/I by sewer system

-------
CM
o

g

§
DC

I
o
LLI

m
        I
       i

       i
       00
       CO
       o
       o>
       CO
       CO
       o>
5    s
<     en
I     e
O     o>
z     "•"
0

ai
Q.     »~
CO     g

o     *-
«     S
co     T-
       S
o
ULJ
DC


   '
          F*"* **^  f*» en  ^* ^*  c^ co  en co
          r*» CM  o ^-  en co  CM     CMin
                  CM •»—  co co  T-     r-        en




                  co co  o in  CD CM  o i»»     co
           i   icqcqr-^cocococsi-^

                  coKcricdco'oincd
                         T-            CM





          en  j   CO^COOT— oino>
          co  '   CM ^r  co ^f"  co *^*  co ^f
          o     K  ^T CO  <£>  i   CO -^     O

          co" co  ^ c\i  10 r*^  CNI     r^   10 Is*  oo oo
          OJ 00  CO t^*  CVJ 00  LO ^f  (O ^^
          C\j CM  O O>  O t^  C\j C3  C\j C)     CO
                                                 CM




          CO OO  CD CO  T- CO  IO  i    !  CD
          cqincMi-^cqcMin!    >co

          N^e»CMTj?'  r^> co  ^j* o)  co CM  co ^t*     o
          CM ^  ^t1 CM  -^T CM                   CO




              S^-T-OT-^CD  join
            ^•^CMcqcMoqcM  '^cq
              oo  T— co  co ^  en     i~ o     ^*
              T-  m T-  a> •$•  T-               in
                                                 CM



          CO ^*  ^        _  _
          ^M - oj  ^** ^r  ^4* CM  ^^  *   ^^ ^»     co
          eriiri^cMcoericd   -o'co'
          T-     T- T-  CM     »—




          incno>CMh*»co^f  i   »— en
          cocococor*;C.>^  *   cn^

          o Tj1  CM en  co N*  ^     o r^     o
                  CM     i— 00  i—     T—




          r^T-cowT-cvjoor-inco
          •r^i^cqcacMinooininin
          c5CDe5'r^'«ti-;-CMCD     oo"
                     T-  t>» •*  T-               CO
                         co  co in  v~ r^
                         CM  i- CM  CO CO
           s"
                         GO
                         o
CO  CO  O

in  co  CM  CM
                                   Q  2 8
                  Ttm^co^ococM


                  <3'*C?CMCX)T^O>C\i
                                              ^  5; ^  X
R
i
                                                                in
                                                 Z5
                                                 CO

                                                                                 "S  ..

                                                                                  I  I 1


                                                                                 Pi
                                                                                 |||




                                                                                  111

                                                                                  CO  »- ~
                                                                                  D) -SS £

                                                                                 TTI  CO  C^*
                                                                                 1  £  2

                                                                                 -III
                                                                                 •*•;  o  fl>
                                                                                  §  °  Q.
                                                                                 *sr* CD  _*
                                                                                  O  N^  co

                                                                                  °" -D  O
                                                                                  i;  o 'o
                                                                                  E  c»^

                                                                                  «|  "
                                                                                  r  S  8
                                                                                  d)  .5  
                                                                                  '55  ^ S  j
                                                                                  I:  « *~  S
                                                                                  52  T3  W  |

                                                                                  S  «  I  a
8  ™. =S  ®
JI>  CO t^  g


CjJ) "°°~ -j77  


I5  .1 I  «
                                       c  S  |  w
                                       .1  E  I "g
                                       ^ "O  W ns
                                       r^  Cd  **~  CO

                                       a.  S  ° «




                                       ^ ¥?  o

-------
ffl"
i
i
CO

0>

I

1

T-
--^
£ 1
O
5 _•.
. s
m A
>'
O
iu S
cc
O ,v,
«- 8
z 2
o
111
0- ^
w S
o *-
z
o
Z9 O
% 8
CO T-

PS,
S
§
s

0
t


$
9
5
8

5
CO


=


s
CM
CM
§
i

in
CD
CO
3
CO
00
CM
*~-
co
CO
oo*

o
-

ff
ft
8
8'

s
CO
CM


CO
CO
*
CO
o
8

00
co


>


co
^t
5

•§
c^
CO
CM
CO
in
«
o
in
S
CO*
«D
-^}-
§

3
S
o
CO
s

CO
CO
CO


8
CM
s
o
m

CO
CO
o
CO


>


§1
1

t
',

in
CO
o
i

cq
c\i
CO
0
^
r**
f~

s
8
S
S

S
8


ff
a
§
CO

8
0


>


o
in
00
CM


CO
0
CO
CM
«
o
1

^
o
.,
1


CO
m
5
in

§
CM


8
CO
5
8

o
CO
CM


P


00
V


o
CO
5
^
V)

^
CO
j

co
T~
^

00
"*
1


CO
r-


f^
°
o
CO
^™

8
o


1


§
00
CO

1
:

i

8
o
1

CO
00
T"
CO
CO.
"*

CO
CO
in
CO
o

s?
CM


co
(O
s
CM

S
"*


x


CO
o
CO


5
T™
i

CO
cq

i

(O
V-
evi

o
m'

CM
CO
o
*
o

o
CO
*-


$
00
CO
in
CM

S
CO


X


«
cS
?

(s.
^
«
CD"
q
in
m
CO
T"
in
S
CO
r^*
CM

N.
cl
§
^

CO
CM
£
T~

s
s
CM
8
CO
oo
CO

CO
CM


_l


         Q
    a] *tS '-^
      S? co
     n 2*t ^J
    ^ (0 j=

    °> fe -°
    .2 * <8
      ~
  S £ 2


    II
      0> 0

        "

    £ «= °> ~
    •o 2 ® 5
    3 js .g E

    S -S * 1
CO


o
  Js> O» c


Ifl*



Illf
P e o  ® 2
* S 5 to w

~ o) ^ o £


IlliS
•c c « « o>
S ~B> 5 S .E
S. £' « 
-------
rehabilitation can often substantially reduce the cost of
wastewater collection and treatment. However, a logical
and  systematic  evaluation of the sewer system is
necessary to determine the cost-effectiveness of any
sewersystem rehabilitation program designedto eliminate
exfiltration, infiltration and inflow.

The reduction of I/I can result in a significant reduction in
hydraulic loading at collection and treatment facilities
during periods of wet weather, thus lowering capital and
O&M costs and prolonging the lifetime-capacity of the
treatment facility.3 Pipeline rehabilitation techniques can
restorecapacity and structural reliability for30-70 percent
of the sewer replacement costs.

1.1.3  Existing Source Documents
There have been a number of reports published that
provide information on sewer system  infrastructure
evaluation and rehabilitation.  A description  of these
materials is provided in order, starting from the oldest
dated publication:

• Handbook for Sewer  System Evaluation  and
  Rehabilitation*^^ document was prepared to provide
  the general guidance and technical information on the
  methodology necessary for an effective investigation
  and correction of I/I conditions in a sewer system. The
  handbook describes the  methods for conducting I/I
  analysis, sewer system evaluation  surveys, sewer
  system rehabilitation and budgetary cost estimating
  techniques for the  rehabilitation  methodologies
  mentioned. The handbook does not contain regulatory
  requirements to  indicate the applicable U.S.  EPA
  regulations on existing, new or upgraded systems.
• Sewer System Evaluation, Rehabilitation and  New
  Construction: A Manual of Practice.5 This document
  was prepared to assist the  reader in the detailed
  investigation of Sewer System Evaluation and Sewer
  Analysis. It emphasized sewer system evaluation,
  sewer rehabilitation and the design of new systems to
  minimize I/I. Sewer cleaning equipment and methods
  of  sewer inspection are discussed in detail. Factors
  which govern the cost of conducting rehabilitation work
  and an analysis of factors to be considered for each
  rehabilitation method  are described. The MOP does
  not provide detailed  information on the regulatory
  requirements.
• Existing Sewer Evaluation and Rehabilitation.3 This
  manual  provides guidelines for the evaluation and
  rehabilitation of sanitary sewers.  It describes the
  purpose and scope of sanitary sewer rehabilitation and
  also provides detailed information to the user
  implementing a sewer rehabilitation program. Major
  emphasis of the manual is on the reduction of I/I, while
  less emphasis is placed on maintaining the structural
  integrity of the sanitary sewer. The manual describes
  the various methods and  materials used for sewer
  system rehabilitation.
• Recommended Specifications for Sewer Collection
  System Rehabilitation. Fifth Edition. August 1987. The
  National Association of Sewer SJervice Companies
  (NASSCO) has published recommended specifications
  for sewer collection system rehabilitation. The book is
  intended to assist engineers and municipal officials in
  properly specifying materials, methods,  equipment
  and procedures  for sewer rehabilitation projects.
  Specifications are  provided for the following
  rehabilitation procedures: sewer line cleaning, sewer
  flow control, TV inspection, sev/er pipe joint testing,
  sewer pipe joint sealing, sewer manhole sealing, sewer
  manhole rehabilitation, sewer manhole lining, sliplining
  of sewers, and cured-in-place pipe installations. The
  document also contains sections on measurement of
  payments, contract responsibilities and definitions.

These reports summarize and provide information and
procedures that were applicable at the time of publication
on various elements of a comprehensive sewer system
analysis.  There was not, however until now, a single
source document that can be referred to by a reader to
obtain comprehensive information  on state-of-the-art
sewer  system  rehabilitation  techniques and
methodologies.

1.2   The Need for  a  Sewer  System
       Infrastructure Handbook

1.2,1   Changing Requirements
This handbook has been prepared to address the need
forconsolidating, updating and expanding the information
presently available from various sources and to refine
some of the previous data analysis methodologies.

The Handbook  for Sewer System Evaluation and
Rehabilitation* took into account the regulations in effect
at that time  and also the available  technological
procedures to reduce I/I. Federal regulations pertaining
to I/I were subsequently revised and simplified  in 1981
and 1982.
                               I

Studies conducted by U.S. EPA in 1980 concluded that
I/I removal rates were substantially less than expected
for  those rehabilitation  methods due to migration  of
infiltration from rehabilitated  areas to non-rehabilitated
areas.

Currently, new materials of construction and new
techniques and approaches for sewer rehabilitation have
been developed and shown to be cost-effective in sewer

-------
system  rehabilitation.  These  new techniques are
described in Chapter 6 of this handbook.

1.2.2  Comprehensive Analytical Procedures
Unique investigative and analytical techniques have
been developed that should be utilized to obtain reliable
flow reduction estimates of rehabilitation effectiveness,
and selection of rehabilitation methods. Measurements
and separate identification of rainfall induced infiltration
(Rll) is carried out by new methods of evaluating and
analyzing flow and rainfall data. New techniques such as
the analysis and understanding of infiltration migration
phenomenon and improved cost-effectiveness analysis
procedures have been implemented by many consulting
engineersto more realistically project I/I reduction. These
new techniques are described in later sections of this
handbook. Studies conducted by the U.S. EPA found
that  infiltration sources  removed by rehabilitation  will
migrate  under certain  conditions to unrehabilitated
locations.6'7 As a result, the cost-effectiveness analyses
were made applicable for an entire subarea rather than
the more conventional individual source approach.

With the availability of new materials of construction such
as polyethylene, PVC and other plastic  and durable
materials described in  Chapter 6, coupled with new
techniques fortrenchless pipe installation, sewer system
rehabilitation has become more  cost-effective and easy
to implement. Consulting engineers, municipalities and
utilities have started to understand and take into account
the total water balance of a sewer system, based on
infiltration, inflow, Rll, exfiltration and migration. New
data and  procedures have  led to a  more realistic
understanding of the limitations and accuracy of methods
now employed.

1.3   User's Guide

This document contains six chapters that provide the
reader with a condensed summary of pertinent I/I and
SSES evaluation and rehabilitation methodologies. It
differs from previous documents in that more emphasis
is placed on state-of-the art technology rather than on
prescribed regulatory requirements.

Table 1 -3 presents a brief description of each of the six
chapters of this handbook along with a user profile for
each chapter.
1.4    References

When an NTIS number is cited in a reference, that
reference is available from:

       National Technical Information Service
       5285 Port Royal Road
       Springfield, VA 22161
       (703) 487-4650

1.  Brown   and Caldwell. Utility  Infrastructure
    Rehabilitation. NTIS No. PB86-N14642, Department
    of Housing and Urban Development, Washington,
    DC, 1984.

2.  Grants  Information and  Control System,  Sewer
    System  Major Rehabilitation Projects, U.S. EPA,
    Construction Grants Federal Budget Spending.

3.  Existing Sewer System Evaluation and Rehabilitation.
    ASCE Manuals and Reports on Engineering Practice
    No. 62, WPCF Manual of Practice FD-6. American
    Society of Civil  Engineers, Water Pollution Control
    Federation, 1983.

4.  Handbook for Sewer  System  Evaluation and
    Rehabilitation. EPA/430/9-75/021, Municipal
    Construction Division, Office of Water Program
    Operations,  Environmental Protection Agency,
    Washington, DC, 1975.

5.  American Public Works Association. SewerSystem
    Evaluation Rehabilitation and New Construction: A
    Manual of Practice. EPA/600/2-77/017d, NTIS No.
    PB-279248. U.S. Environmental Protection Agency,
    Municipal Environmental Research Laboratory, Office
    of  Research and Development, Cincinnati, Ohio,
    December 1977.

6.  RJN Environmental Associates, Inc.  National
    Alternative  Methodology for  Sewer System
    Evaluation,  Wellington  Suburban Sanitary
    Commission, 1988.

7.  National Water Well Association, RJN Environmental
    Associates, Inc., and Washington Suburban Sanitary
    Commission. Impact of Groundwater Migration  on
    Rehabilitation of Sanitary Sewers. 1984.

-------
Tab!* 1>3.
Summary of Handbook Contents
Chapter
                                 Description
User Profile
1. Introduction
2. Regulatory Requirements
  Requirements
3. Preliminary Analysis of Sewer Systems
4. Sewer System Evaluation
                                 Describes purpose, intended audience,
                                 definition of infrastructure, describes
                                 source documents, and importance of
                                 sewer system infrastructure evaluation.

                                 Provides summary of past U.S. EPA
                                 regulations relative to roles of state
                                 and federal agencies; provides matrix
                                 of state regulations and approval
                                 requirements for sewer system improvements

                                 Describes historical and financial
                                 reasons for evaluation of sewer
                                 infrastructure needs, outlines a
                                 simplified preliminary sewer system
                                 and I/I analysis evaluation methodology
                                 including sources of information and
                                 required resources, presents flow
                                 diagram of a sewer system evaluation
                                 plan, summarizes the basic elements of
                                 infiltration inflow analysis, including
                                 the impact of exfiltration and migration

                                 Describes new techniques and sub-system
                                 approach to the traditional sewer
                                 system evaluation, includes planning
                                 the survey, the physical survey,
                                 cleaning, inspection and presentation
                                 of separate infiltration and inflow data,
                                 cost effective analysis, references
                                 other source documents for specific
                                 details and proven technological approaches
  All readers
  Regulatory personnel
  City officials
  Consulting engineers
  Public works directors
  City planners

  City planners
  City officials
  Public works directors
  Sewer system study planners
  Consulting engineers
  Su|3ervisors and staff
  conducting a sewer
  evaluation
  City sewer
  Public works directors
  Public works officials
  Consulting engineers
  City managers
  Su|>ervisorsandstaff planning
  and conducting sewer
  evsJuations
  City sewer maintenance staff
5. Corrosion Analysis and Control
6. Sewer System Rehabilitation
                                 Describes the types and mechanisms of
                                 sewer corrosion, the importance of
                                 corrosion to the integrity of the sewer
                                 system, describes how to plan and conduct
                                 a sewer system corrosion survey,
                                 corrosion inspections techniques,
                                 analytical data required, provides
                                 methods of rehabilitating corroded
                                 sewers; methods for predicting
                                 corrosion and methods of conducting
                                 corrosion surveys

                                 Provides the latest information on
                                 state-of-the-art sewer rehabilitation
                                 techniques including a) excavation
                                 and replacement, b) chemical grouting,
                                 c) insertion lining, d) inversion
                                 lining, e) specialty lining,
                                 f) liners, g) coalings and h) building
                                 sewers; includes detailed cost
                                 estimates for each technique
                                 along with case histories of successful
                                 projects.
  City planners
  City Officials
  Consulting engineers
  City engineers
  City sewer maintenance
  start
  Supervisors and staff
  conducting a sewer
  system evaluation
  Public works directors
  City managers
  Public works officials
  Consulting engineers
  City engineering staff
  Supervisors and staff
  planning and conducting
  rehabilitation projects
  Contractors
  Sub-contractors
  Inspectors

-------
                                           CHAPTER 2
                                   Regulatory Requirements
2.1    Historical Background
The Water Pollution Control Act Amendments (Public
Law 92-500, October 18, 1972), require that the U.S.
EPA construction  grant applicants investigate the
condition of their sewer systems. The grant cannot be
approved unless it is docu mented that each sewer system
discharging into such treatment works is not subject to
"excessive infiltration and inflow." This requirement was
implemented in the Rules and Regulations for Sewer
Evaluation and Rehabilitation (40CFR35.927). In addition,
I/I analysisandSewerSystem Evaluation Surveys(SSES)
were required  to be conducted on a routine basis to
document I/I, and also to indicate the most cost effective
method of rehabilitation required to correct the sewer
pipe and manhole structure damage.1

The I/I analysis should document the non-existence or
possible existence of excessive I/I in each sewer system
tributary to the treatment works. The analysis should
identify the presence and type of I/I that exists in the
sewer system including estimated flow rates. The following
information should be evaluated and included:

• Estimated flow data at  the treatment  facility, all
  significant overflows and bypasses, and, if necessary,
  flows at key points within  the sewer system
• Relationship of existing population  and industrial
  contribution to flows in the sewer system
• Geographical and geological conditions  which may
  affect the present and future flow rates or correction
  costs for the I/I
• A discussion  of  age, length, type, materials of
  construction  and known  physical conditions of the
  sewer system

The SSES should include a systematic  examination of
the sewer system to determine the specific locations,
estimated f tow rates, method of rehabilitation and cost of
rehabilitation versus the cost of transportation and
treatment for each defined sou rce of infiltration and each
defined source of inflow.1 The resultsof the SSES should
be summarized in a report that should include:2
• A justification for each sewer section cleaned and
  internally inspected
• A proposed rehabilitation program forthe sewer system
  to eliminate all defined excessive I/I

2.2    Summary of Applicable U .S. EPA and
       State Regulations

The  following is a  Summary of Federal and  State
Regulations  and Guidelines for I/I analysis and SSES
applicable under the U.S. EPA construction  grant
program.1'3

The grant applicant must determine the I/I conditions in
the sewer system by analyzing the preceding year's flow
records from existing treatment plant and pump stations.
For smaller  systems where flow records may not be
available, the grant applicant shall obtain flow data by
conducting flow monitoring at asingle point atthetreatment
plant during  high groundwater periods and also during
rainstorms. If there is a likelihood of excessive I/I in a
portion of the collection system, it is desirable to monitor
that  portion separately. No further I/I  analysis will be
necessary if domestic wastewater plus non-excessive
infiltration does not exceed 120 gallons per capita perdav
(gpcd) during periods of high groundwater. The total daily
flow  during a storm should not exceed 275 gpcd. and
there should be no operational problems, such as
surcharges,  bypasses or poor treatment performance
resulting from hydraulic overloading of the treatment
works during storm events. The flow rate of 120 gpcd for
infiltration analysis contains two flow components: 80
gpcd of domestic base f lowand 40 gpcd of non-excessive
infiltration. This is a national average based on the results
of a needs su rvey of 270 Standard Metropolitan Statistical
Area Cities. Where the flow rate (domestic base flow and
infiltration based on  the highest 7 to 14 day average)
does not significantly exceed 120 gpcd (in the range of
130 gpcd) the city may proceed with the treatment works
design without further analysis.  When infiltration
significantly exceeds 120 gpcd, further evaluation of the
sewer system must  be performed to determine  the
possibility of excessive I/I through a cost effectiveness

-------
analysis. Following the I/I  study, a SSES must be
performed. The result of the SSES will allow the city to
formulate sewer rehabilitation program to eliminate the
portion of the I/I that is excessive and size the treatment
plant accordingly.

With the elimination of the U.S. EPA construction grants
program in October of 1990, all Federal regulations for M
I analysis and SSES underthis program will no longer be
applicable. Individual states nowhavetheirownguidelines
and regulations to follow. A survey of state regulatory
officials  indicates that many states however still follow
Ten States Standards2 and past  U.S. EPA standards
such as CG853 I/I and SSES guidance documents (See
Table 2-1). State agencies evaluate general plans and
feasibility studies submitted by an applicant for any
treatment plant modification application. If the general
plan and feasibility study submitted by the applicant show
flow variations during wet weather conditions, the State
Agency  investigates the cause and  may request the
applicant to conduct a SSES and I/I analysis. They may
further request information on the cost effectiveness of
rehabilitation versus building a new plant.

2.3     Description  of the Relative  Roles of
        the U.S. EPA, State Agencies, and
        Local Agencies

The U.S. EPA has been very involved in sewer system
evaluation and rehabilitation projects since 1973 as a
result of the construction grant  program.  Under this
program, the U.S. EPA provided grants to municipalities
for I/I analyses, for SSES if excessive flow was found,
and for rehabilitation if excessive I/I was found. With the
completion of the construction grants program in 1990,
the U.S. EPA will play a smaller role in this effort, while
the roles of the state and local agencies will become
larger.

Table 2-1 outlines the regulations which currently (April
1991) apply to sewer expansion and rehabilitation in
each state.4 As the table shows, requirements vary from
state to  state. Within the states, requirements depend
upon the source of funding for the project.

2.4     Certification Requirements

2.4.1    Historical Perspective
Section 204 of the 1981 Amendments to the Clean Water
Act requires that U.S. EPA grant applicants must, after
one year's of operation, certify to the U.S. EPA that the
project  meets design specifications and effluent
limitations, including I/I reduction projections. The purpose
of the certification requirementsisto ensure that effective
sewer rehabilitation projects were carried out through the
grant assistance programs. On May 12,1982, U.S. EPA
promulgated regulations which clarified and implemented
the 1981 requirements. These regulations can be found
in 40CFR35. The definition of municipal treatment works
was expanded to include interceptor and collector seweirs.
Furthermore, I/I analysis and SSES work were included
in the treatment works performance certification
requirements. The grantee  is required to  certify
performance after one year,  as stated in the 1981
regulations. In addition,  the grantee must prepare a
corrective  action report for projects  not  meeting
performance requirements, establish  a  schedule for
corrections, and determine a new certification date.
These  certification requirements apply to all Step 3
grants awarded on or after May 12,1982.5

As a basis for the grantee's  certification  that SSES
performance specifications are being met, a six to twelve
month post-rehabilitation monitoring program  is
recommended. This program will generally include one
or more flow monitoring stations, grou ndwater and rainfall
measurements, and other measurements as required to
quantify I/I reduction in the rehabilitated areas.5

It is the grantee's responsibility to certify that the SSES
design and performance standards for I/I reduction have
or have not been met. If it is found that these standards
have not been met,  the grantee must identify specific
causes and must rectify the situation at otherthan federal
expense.5

2.4.2  Current Situation
With the completion of the construction grants program,
it is uncertain whetherthe states will require a certification
program similarto the one required forthe federal grants.
However, ft is a good practice for cities to continue this
policy to ensure program effectiveness.
                                                   8

-------
Table 2-1             State Agency Regulations for Sewer System Improvements

              Regulations to be followed for SSES and I/I
               analysis (CG 85,10 States) or for expansion
               or rehabilitation of existing sanitary
               sewers or lift stations:
Required before
applying to expand
or upgrade a
treatment plant:

STATE
AK
AL
AR
AZ
CA
CO
CT
DE
FL
GA
HI
IA
ID
IL
IN
KS
KY
LA
MA
MD
ME
Ml
MN
MO
MS
MT
NC
ND
NE
NH
NJ
NM
NV
NY
OH
OK
OR
PA

CG85
(a)
(a)
(a)
no
(a)
(a)
(d)
(a)
(a)
(I)
yes
(a)
yes
(a).
yes
(d)
(?)
no
no
(a)
(d)
(a)
(d)
(a)
no
(a,d)
no
(d)
yes
(d)
(d)
(a)
no
yes
(a)
(a)
no
(c,d)
10 States
Standards
yes
(a)
(b,c)
no
no
no
no
yes
yes
(b,l)
(c)
(I)
yes
no
yes
(d)
yes
no
no
no
no
yes
yes
no
yes
yes
no
yes
yes
no
no
no
yes
yes
(D
no
no
no
State
Review
yes
(a)
yes
yes
(a)
no
yes
(a)
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
State
Approval
yes
(a)
yes
yes
(a)
(b)
yes
yes
yes
yes
yes
yes
(c)
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
(i)
yes
yes
yes
yes
yes
yes
Permit to
Install
yes
no
no
no
no
(b)
no
yes
yes
no
no
yes
no
yes
yes
yes
yes
yes
(i)
yes
no
yes
yes
yes
no
no
yes
no
(b)
no
yes
no
no
(c)
yes
yes
no
yes

Other
no
no
(e)
(g)
no
no
(e)
(h)
no
no
(g)
(g)
no

-------
Table 2-1, continued.
               Which regulations must be followed for SSES
                and I/I analysis (CG 85,10 States) or for
                expansion or rehabilitation of existing
                sanitary sewers or lift stations?
What is required
before applying to
expand or upgrade
a treatment plant?

STATE
Rl
SO
SD
TN
TX
UT
VA
VT
WA
Wl
WV
WY

CG85
yes
(c,d)
no
no
yes
(a)
no
yes
(d)
no
(c,d)
(a)
10 States
Standards
no
yes
(d)
d)
no
(a)
no
yes
no
no
yes
no
State
Review
yes
yes
yes
yes
yes
no
yes
yes
yes
yes
yes
yes
State
Approval
yes
yes
yes
yes
yes
no
yes
yes
yes
yes
yes
yes
Permit to
Install
'no
yes
no
no
no
no
yes
yes
no
no
yes
yes

Other
(e)
(g)
no
(g)
no
no
(g)
(e,g)
(g)
(g)
no
(g)

SSES
yes
no
(a)
: (f)
(i)
no
no
yes
no
ttl)
(f)
no
I/I
Analysis
yes
yes
(a)
(a)
yes
no
yes
yes
yes
(g)
yes
yes
            (a) for projects funded by EPA grants, the State Revolving Fund,
                or similar programs
            (b) for expansion or rehabilitation of lift stations.
            (c) for expansion or rehabilitation of sewers.
            (d) for SSES and I/I analysis.
            (e) other published texts, manuals or guidelines.
            (f) decision to perform SSES is based on results of I/I analysis.
            (g) state regulations or standards.
            (h) for expansion.
            (I) sometimes.
            (|) for state funded projects.
            (k) permit to discharge required for expansion of sewers.
            (I) as a guideline.
                                                10

-------
2.5    References

When an NTIS number is cited in a reference, that
reference is available from:

       National Technical Information Service
       5285 Port Royal Road
       Springfield, VA 22161
       (703) 487-4650

1.  American Public Works Association. Sewer System
   Evaluation, Rehabilitation and New Construction: A
   Manual of Practice. EPA/600/2-77/017d, NTIS No.
   PB-279248. U.S. Environmental Protection Agency,
   Municipal Environmental Research Laboratory, Office
   of Research and  Development, Cincinnati, Ohio,
   December 1977.

2.  Recommended Standards for Sewage Works,
   Policies for the Review and Approval of Plans and
   Specifications for Sewage Collection and Treatment,
   1978 Edition; A Report of the Committee of the Great
   LakesUpper Mississippi River Board of State Sanitary
   Engineers. (Ten-States Standards)

3.  Construction Grants 1985. EPA/430/9-84/004, Office
   of Water,  U.S. Environmental Protection Agency,
   1984.

4.  State Agencies Responses to Questionnaires sent
   by J.M. Smith & Associates, August, 1990.

5.  Code of Federal Regulations, Title 40 (40CFR35).
   Office of the Federal Register, National Archives and
   Records Service, General Services Administration,
   May 12,1982.
Additional Reading

Handbook for  Sewer System Evaluation and
Rehabilitation. EPA/430/9-75/021,  Office of Water
Program Operations, U.S. Environmental  Protection
Agency, 1975.

Analysis of Acceptable Ranges for Infiltration and Inflow
Reduction in Sewer System Rehabilitation Projects. J.M.
Smith and Associates, EPA, Contract #68-01-6737,1984.

Handbook of Procedures, Transmitted  Memorandum
89-1, Office of Water, U.S. Environmental Protection
Agency, 1989.
                                                 11

-------

-------
                                            CHAPTERS
                            Preliminary Analysis of Sewer Systems
3.1    Introduction
This chapter presents information on how to conduct a
preliminary sewer system analysis to determine quickly
and easily if there  are serious  infiltration/inflow  (I/I)
problems, evaluate the extent of these problems, and
select the approach for fu rther analysis and investigation.

Before implementing a thorough I/I analysis and Sewer
System Evaluation Survey (SSES), a preliminary analysis
of the  sewer system should be conducted to quickly
establish the degree of I/I inthesystem. For systems that
have not been evaluated, the following occurrences
indicate the need for a preliminary sewer system analysis:

• Greater than anticipated  flows  measured  at  the
  wastewater treatment plant
• Flooded basements during periods of intensive rainfall
• Lift station overflows
• Sewer system overflows or by-passes
• Excessive power costs for pumping stations
• Overtaxing  of lift station  facilities, often  resulting in
  frequent electric motor replacements
• Hydraulic overloading of treatment plant facilities
• Excessive costs of wastewater treatment including
  meter charges levied by sanitary .districts or other
  jurisdictional authorities
• Aesthetic and water quality problems associated with
  by-passing of raw wastewater
• Surcharging of manholes resulting in a loss of pipe
  overburden through defective pipe joints and eventual
  settlement or collapse
• Odor complaints
• Structural failure
• Corrosion

3.2     Historical Reasons for Sewer System
        Analysis and Evaluation

Historically, the evaluation of sewer systems has occurred
because of regulatory requirements to receive Federal
funding; capacity limitations; structural failure; and indirect
evidence of excessive I/I in theoverall system. I/I problems
are often abated by the construction of relief sewers,
larger lift stations and treatment plants, and by the use of
wastewater bypasses throughout the system. This last
approach, however, often results in untreated wastewater
flows being discharged into rivers, streams, lakes and
open ditches which is no longer acceptable as a solution.
An effective sewer system evaluation and rehabilitation
plan will be required for  effective protection of the
infrastructure in nearly all cases regardless of the initial
reasons for the evaluation.

3.2.1  Regulatory Requirements
Regulations promulgated as a result of Public Law 92-
500 require that any engineer or public official concerned
with thedesign of improvements to existing sewersystem
infrastructure componentsorwastewatertreatment plants
become familiar with and follow certain procedures to
insure that excessive I/I was not present in order to
become eligible for U.S. EPA grant funding.

Although many changes in the regulations have since
been made, the underlying importance of preserving
sewer system capacity and structural integrity remains.
As shown in Table 2-1, many state regulatory officials still
follow a rigorous state review and approval process for
improvements to  sewer  system  infrastructure
components.

3.2.2  Structural Failure
Wastewater collection system structural failures often
occur due to H2S crown corrosion, natural ageing, and
factors such as defective design, excessive overburden,
soil settlement, and earthquakes. The historical method
forrepairing structural problems in sewer systems was to
excavate and replace the pipe. With the advent of new
technologies,  described  herein,  rehabilitation  of
wastewater collection  lines  has  became more cost
effective and can often be accomplished without extensive
excavation and replacement.

3.2.3  Capacity Limitations
With the natural increase in  population and industrial
growth within a city, the capacity of the wastewater pipes
often become  insufficient.  Sewer collection lines and
                                                   13

-------
treatment plants become inadequate to handle the
increase in sanitary flows. Without the correction of
excessive I/I, existing sewer lines, are unable to carry the
increased flows, thus prohibiting expansion and growth
within the existing tributary area.

3.2.4   Citizens' Complaints
Citizens' complaints are often reported during periods of
extensive rainfall because sewers surcharge and cause
local, area, and residential flooding.  When  such
phenomena occur on a  regular basis, a preliminary
analysis of the sewer system  is necessary because
these complaints indicate that the sewer lines exhibit
excessive amounts of I/I during periods of rainfall.

3.3     Financial Reasons for Evaluation of
        Sewer Infrastructure  Needs

3.3.1   Need to Enlarge Service Area
Traditional  planning of sewer  systems has included
allowances for growth and expansion within specific
drainage basins or within specific geographical or political
subdivisions of communities. As existing systems continue
to expand, however, the demands on the existing sewer
infrastructure continue to grow and the capacity and
condition of existing interceptor sewers, lift stations, and
appurtenant structures must be continually evaluated.
[Hiring these planning activities, it often becomes apparent
that existing facilities have experienced deterioration and
require rehabilitation or replacement to remain serviceable
and  to  accommodate the flow  of expanding  service
areas.

Evaluation of many existing systems as a part of federally-
funded I/I and SSES investigations has often shown that
severedeterforation has occurred, thuscreating additional
financial pressures for future sewer system planning and
expansion. Since sewer systems are designed for service
lifetimes of 30-50 years or more and the plan ning of these
systems do not normally include replacement financing,
future expansion and development planning must take
into account the cost of this replacement. The continued
expansion  of  existing collection  systems normally
continues until the capacity of the critical components of
existing collection and treatment systems are reached.
Because of the high cost of increasing interceptor and
collection system capacity especially in fully developed
areas, it is important that I/I be minimized and that the
necessary  investment be made over the lifetime of
existing facilitiesto preserve their condition and capacity.
It is forthis reason that the major federal funding sources
forsewer construction have emphasized the importance
of I/I control and protection of systems from major
deterioration due to corrosion.
At any given point in time within a sewered community,
there is a continuing need to recognise the: 1) value of the
existing sewer infrastructure; 2) condition of the system;
3) rateof deterioration;^ cost of mitigation of deterioration;
5) estimated remaining service lifetime; and 6) ultimate
system capacity.  A realistic  evaluation  of the above
factors is a crucial element of sound  public works
management and a fundamental requirement for effective
financial planning of sewer system infrastructure
improvements.

3.3.2  Budgetary Planning Needs
Sewer system budgetary planning normally includes the
following major cost categories:

• Legal and administrative       ',
• Long term and short term debt
• Short term capital financing
• Operations and  maintenance labor
• Operations materials and utilities
• Contingency or reserve funds

These budgets are often prepared on an annual or bi-
annual basis and are presented to city council or other
governing bodies for approval. Whether wholly or partly
financed  by sewer or sewer and water revenue bonds,
some elements of the sewer systein budgets compete
with other municipal infrastructure needs.

Evaluation  of the  age  and condition of existing sewer
systems allows inclusion of the total system needs into
the sewer system operations budget. A well planned
sewer system survey will provide information such as:

• Sewer  line manhole (other structure)  replacement
  needs and costs
• Lift station equipment needs
• Extent of corrosion of lift station  equipment and
  structures, force mains and down stream  receiving
  sewers
• Immediate and longer term rehabilitation needs
• Long and short term maintenance needs

Although all needs cannot be met by annual operating
budgets, the budgeting and expenditure of funds annually
for repair, maintenance rehabilitation and replacement of
critical sewer system components in many cases can
eliminate or reduce the need for major capital expenses
at a later  date.  For example, early identification  of
deterioration due to corrosion may save over 60 percent
of the cost of eventual  repair or replacement.

3.3.3  Financial Planning
Financial planning to satisfy infrastructure needs includes
the consideration of both the short- and long-term
                                                   14

-------
budgetary needs as described in Section 3.3.2, as well as
thegrowth needs as described in Section3.3.1. Effective
planning must recognize not only the importance of an
accurate and realistic assessment of needs, but also
knowledge of the alternative financing mechanism that
are available. These elements should be considered
over a planning period of 15-25 years. It should be
recognized that even though the estimated lifetime of
major portions of the sewer system infrastructure is 30-
50 years, it is necessary to assess the capital improvement
needs of existing systems on  a routine basis at least
every 5-10 years. Sewer system needs shou Id be forecast
forl 0-25 years and should include short term rehabilitation
needs and longer term capital improvements needs.

A major element of financial planning includes the analysis
of a wide variety of financing mechanisms available to
municipalities, as well as a clear understanding of the
required financial resources.

Table 3-1 outlines the advantages and disadvantages of
the more common infrastructure financing mechanisms.

3.3.4  Benefits  Versus Cost of Sewer System
       Evaluation
Since the early 1970's, over 90  percent of sewer system
evaluations were  performed in  response to Federal
Grant funding requirements as now  defined by
40CFR35.2120.

The  experience gained during the past 15 years with
sewer system evaluation efforts (either I/I or SSES) has
proved extremely valuable in  identifying the need for
precise information regarding the condition of the nation's
sewer system infrastructure. Equally important has been
the development and refinement of a wide range of cost
effective sewer evaluation and rehabilitation techniques.
These include:  1) improved sewer system monitoring,
analysis and inspection techniques; 2) testing and grouting
techniques; 3)  slip-lining technology; 4) cured in-place
linings; 5) fold and fomed; 6) specialty concrete products
and grouting techniques; 7) new coatings; 8) new service
lateral techniques; 9) new liners; and 10) new manhole
rehabilitation techniques.

Another major finding of sewer system evaluations has
been the realization of the extent, impact, and monetary
significance of corrosion on existing sewer systems. This
alone prompted U.S.  EPA to undertake a  series of
investigations and to publish a design manual in 1985 on
sewer system odor and corrosion control techniques.1
Further concerns over the impact of  sewer system
corrosion led the U.S. Congress to require U.S. EPA to
undertake additional studies and to submit a report to
Congress on the costs and impacts of corrosion on the
sewer system infrastructure and the effects of rainfall
induced infiltration (Rll) on sewer systems.2'3

Although the costs and benefits of sewer system
evaluation have not been explicitly defined on a national
basis in the United States, some level of routine sewer
system evaluation is cost effective for all of the nation's
sewer systems. Experience over the past 15 years has
shown that rehabilitation cost are significantly less than
replacement costs in most instances. As shown in Chapter
6, rehabilitation costs are 20-25 percent of replacement
cost for specialty concrete, cement mortar, and epoxy
coatings; 60-80 percent of replacement costsforgrouting;
and 55-85 percent of replacement costs for sliplining and
inversion lining. Comprehensive sewer system surveys
including cleaning and inspection are 5-7 percent of
sewer replacement  costs. Given  the  fact that
comprehensive  sewer system evaluation plus
rehabilitation  costs  are 25-92 percent  of sewer
replacement costs, sewer system evaluation and
rehabilitation is extremely cost effective in maintaining
the capital asset value of this infrastructure system.

This cost advantage  is  in addition to the  benefit of
maintaining existing flows and future capacities due to
reduction of infiltration and inflow. The highest benefit/
cost ratios are found in areas where the sewer corrosion
potential is the highest.

Deterioration rates in systems due to corrosion have
been shown to decrease sewer life times from the normal
30-50 years to as low as 2-4 years in extreme cases and
9-14 years in moderate cases.
3.4
3.4.1
       Methodology for Preliminary Sewer
       System Analysis
       Sources  of Information and Preliminary
       Methods of Analysis
The extent of the preliminary sewer system analysis
depends on the size of the system and the amount of
information available.  A diagram outlining the major
steps to be taken in a preliminary survey is presented in
Figure 3-1. Each of these steps are discussed below.

A preliminary sewer system survey is normally conducted
by municipal personnel and their consultants. The first
step in the procedure is to assemble the survey team.
The team usually consists  of the city's consultants,
representatives from the city or municipal administration
departments, central  engineering staff,  sewer and
wastewater superintendent,  and key  sewer system
operating and maintenance personnel. Other staff that
have pertinent knowledge and experience with the major
sewer system components should be  assigned. It is
                                                  15

-------
Table 3-1.
Advantages and Disadvantages of Major Infrastructure Financing Mechanisms
Advantages
                            Disadvantages
General fund appropriation
Genera) obligation bonds
Revenue bonds
State gas tax
Other dedicated taxes
State revolving funds
                            Administrative: appropriations reflect
                            current legislative priorities
                            Equity: ail taxpayers contribute
                            to capital projects
                            Fiscal: no debt incurred, so projects
                            cost less during periods of inflation
                            Equity: capital costs shared by current and
                            future users
                            Fiscal: bonds can raise large amounts of
                            capital; general obligation bonds usually
                            carry lowest available interest rates

                            Administrative: do not require voter approval
                            and are not subject to legislative limits
                            Equity: debt service paid by users fees,
                            rather than from general revenues
                            Administrative: established structure allows
                            tax increase without additional administrative
                            expense
                            Equity: revenues are usually earmarked for
                            transportation, so users pay
                            Fiscal: revenues relatively high compared to
                            other user taxes

                            Administrative: voters prefer dedicated taxes
                            Fiscal: provides relatively reliable funding
                            source not subject to annual budgeting
                            Administrative: promote greater State
                            independence in project selection
                            Fiscal: debt service requirements provide
                            incentives for charging full cost for services;
                            loans'Can leverage other sources of funds;
                            loan repayments provide capital for new loans
Administrative: infrastructure must
compels with other spending
priorities each year; cannot plan long-
term project around uncertain funding
Equity: no direct link between
beneficiary and who pays, and current
generation pays for capital projects
that benefit future generations.

Administrative: States often impose
debt ceilings and requires voter
approval
Fiscal: adds to lax burden,
especially If interest rates are high

Administrative: require increased
reporting and restricted by Tax
Reform Act limitations
Fiscal: usually demand higher
interest rates them general obligation bond

Administrative: revenue fluctuates with
use of gas
Equity: fiscal burdens are not evenly
distributed between urban and rural
areas
Fiscal: revenue does not rise with
inflation or reflect differences

Administrative: reduces districts
ability to meet changing needs
Fiscal: major economic downturns
can reduce revenues significantly

Administrative: States bear
increased administrative and financial
responsibility
Equity: poor districts cannot afford
loans
Fiscal: repaying loans will mean
increases in use charges or taxes
Source-Office of Technology Assessment 1990
                                                                  16

-------
Figure 3-1.
Approach to conducting sewer system evaluation.
                                                        Assemble Survey Team
                                                   Collect and Review Available Data
        co
        CO
        £
        a.
                                                        Analyze Available Data
                                                         and Develop Survey
                                                         Establish System and
                                                        Sub-System Boundaries
                          Non-Problem
                             Areas
                                  Prioritize Sub-System Problems
                                 and Eliminate Non-Problem Areas
                                                     Conduct Further Investigation
                                                         of Problem Sub-Areas
                                Effects of Exfiltration
                                   and Migration

        B
        W
        >»
        03
                                                    Eliminate Non-Problem Segments
                                                           of Problem Areas
                                                      Conduct SSES Investigation
                                                         and Corrosion Survey
                                                    Conduct Cost-Effective Analysis
                                                            of All Problems

         0)
        CC
                                                    Develop Final Rehabilitation Plan
                                                    Establish Planning Time Frames,
                                                   Specific Work Scopes and Budgets
                                                                                   Mappjng Information

                                                                                Previous I/I, SSES Studies

                                                                            O&M Records, Inspection Reports,
                                                                                  Construction Reports

                                                                                 Geologic, Topographic,
                                                                                  Hydrologic Information

                                                                               Flow records from Treatment
                                                                                   Plants. Lift Stations,
                                                                                  Bypasses, Overflows

                                                                                 Odor Complaints, Odor
                                                                                 Surveys, Corrosion Data

                                                                                    Rainfall Records,
                                                                                 Ground/rater Monitoring
                                                 Implement Plan, Procure Equipment and
                                                       Services, Award Contracts
                                                                 17

-------
 important that all staff assigned be able to commit the
 necessary time for proper planning and implementation
 of the survey. The major  purposes for conducting a
 preliminary sewer system survey are to identify, localize
 and prioritize those areas of the sewer system sub-areas
 with the greatest potential problems, and to identify the
 preliminary scope of the subsequent investigations. A
 preliminary survey is a forerunnerto the traditional I/I and
 SSES procedures. The major sources of information
 used in the preliminary survey are outlined below:

 • As-built sewer maps
 • Sewer  system operation and maintenance (O&M)
   records
1 • Existing geographical, geological, climatological and
   topographical records
 • Existing city or municipal planning documents
 • Existing treatment plant performance records
 • Sewer  system monitoring records such as treatment
   plant flow records, lift station flow records, overflows
   and by-passes
 • Interview information from public officials  and
   supervisory sewer system O&M staff
 • Historical sewer system and treatment plant flow and
   performance information
 • Rainfall and groundwater data
 • Water use records
 • Population and user history
 • Industrial survey information

 The more important of the above data sources are:
 available sewer maps, information from previous l/l'and
 SSES studies, along with system and sub-flow monitoring
 information. The preliminary information also includes
 the normal data sources used for I/I analysis including
 flow monitoring, rainfall, groundwaterlevels, and anecdotal
 evidence of exfiltration.

 The proper assignment of data collection responsibilities
 toindividualsthat haveaccesstothe required information,
 and the  organization of responsibilities by the survey
 team leader is a major factor in the success and efficiency
 of the preliminary survey.

 The goal of this preliminary survey, however, is to utilize
 the available data to make the best judgments possible
 regarding the condition of the existing sewer system and
 to define the  specific problems within the system and
 sub-system areas. The final plan resulting from the
 analysis of available data should, as a minimum, provide
 the following information:

 • Clear delineation of all  sub-areas, and location  of
   monitoring points
• Clear understanding and preliminary ranking of the
  problems within each sub-area. This may include the
  relative severity of infiltration and inflow,  suspected
  sources of each, identification  of  major areas of
  corrosion, the impact of lift stationson surf idegeneration
  and corrosion, evidence of structural failures, sewer
  blockages or other  damage to  the sewer system
  infrastructure
• Identification of all non-problem sewer sub-areas
• Identification of sewer system monitoring and data
  needs for all priority problems in each sub-area selected
  for study
• Schedule for establishing  system monitoring
  requirements. For example monitoring for inflow would
  be conducted during high-groundwater conditions while
  monitoring for corrosion or exfiltration  would  be
  conducted during low-flow, dry weather conditions.

An estimate of resources needed  to conduct the
investigation of the sub-systems should include:

• Permanent  or  temporary sampling  and  flow
  measurement equipment
• Sewer cleaning and inspection equipment
• Sulfide and corrosion measurement and  monitoring
  equipment
• Groundwater monitoring needs
• Rainfall simulation equipment

The resource estimate should include a summary of all
activitiesto be conducted by municipal employees and all
activities to be completed by contract services. A summary
work scope, budget and schedule should be prepared for
all service contracts.

The preliminary survey differs from the initial stages of an
I/I analysisorSSES investigation in the following respects:

• The scope of the preliminary sewer system survey is
  broader than I/I  or SSES  and includes surveys of
  physical damage to the sewer system infrastructure,
  capacity  limitations,  effects of corrosion and sewer
  system deterioration rates, and excessive I/I, including
  those areas  that would  possibly  be affected  by
  groundwater migration and exfiltration.
• The preliminary survey establishesthe problem priorities
  for the entire system and sub-systems and defines the
  overall work scope of subsequent investigations
• The preliminary survey defines the costs, objectives,
  and time frames for implementing all investigations
  necessary for a complete infrastructure analysis.
                                                    18

-------
3.4.2  Monitoring and Equipment Needs for
       Preliminary Analysis
The monitoring and equipment needs for a preliminary
sewer system survey depend on the size of system or
sub-systems under investigation and the schedule for
conducting the survey. Sub-systems may vary in size
from af ew tenths of a square mile to several square miles
and may include up to 20 or more separate monitoring
stations. The preliminary survey includes flow monitoring
at critical junctions, limited physical surveys, preliminary
corrosion surveys and information to correlate flows with
rainfall and groundwater information.

Although equipment needs vary depending on the size of
the sub-system, typical equipment needs for a single
sub-system investigation are:
  2-3 fully automatic recording flow meters
  1-2 velocity meters
  1-2 depth sensors
  2-3 20- to 76-cm (8-30-in) weirs
  1 metal detector
  pH ORP meters
  Recording DO meters
  Smoke bombs, and a gasoline driven blower (1,500-
  3,000 cfm)
  Camera and film
  Sand bags and plugs, 20-76 cm (8-30 in)
  60-90 m (200-300 ft) of fire hose and fluorescent dye
  1-2 tipping bucket rain gauges
  2 proportional samplers and sample containers
  Device for measuring corrosion such as a sonic caliper
  1 extendable penetration rod
  4-6 sulfide test kits
  Miscellaneous sewer and manhole sampling and access
  equipment including ladders, lights, buckets, sample
  containers,  rope, tapes, hand tools, and safety
  equipment
Of the above equipment, selection of the appropriate flow
measuring devices (flow meter or weirs) and the
equipment for the preliminary corrosion survey is the
most important. The above list does not include
preparatory sewer cleaning or TV inspection equipment
since the preliminary survey does not extend to that level
of detail.

3.5     Infiltration and Inflow  Analysis

3.5.7   Introduction
Infiltration is that volume of water that enters sewers
and building sewer connections from the soil through
foundation drains, defective joints, broken or cracked
pipes, faulty connections, etc.4
Inflow is that volume of water that is discharged into
existing sewer lines from such sources as roof leaders,
cellar and yard area drains, commercial and industrial
discharges, drains from springs and swampy areas, etc.4

I/I is the major deterrent to the successful performance
of a wastewater conveyance or treatment system.5
Excessive I/I in a sanitary sewersystemcan hydraulically
overload sewer lines and wastewater treatment plants,
resulting  in surcharging, basement backups, sewer
bypasses, and reduced treatment efficiency.6  It also
adversely affects the urban environment and the quality
of the water resources. Some detrimental effects of I/I
are: utilization of sewer facility capacity that could be
reserved  for  present sanitaiy waslewater  flows and
future urban growth; need for construction of relief sewer
facilities before originally scheduled dates; surcharging
and backflooding of sewers into streets and  private
properties; bypassing of raw wastewater at various points
or diversion into storm drains or nearby watercourses;
surcharging of pump stations resulting in excessive wear
on equipment, high power costs, bypassing of flows to
adjacent  waterways,  diversion of  flow away from
secondary or tertiary treatment stages, or bypassing of
volumes of untreated wastewater into receiving waters;
and increases in the incidence and duration of stormwater
overflows at combined sewer regulators.7 Proper analysis
of I/I is thus required to demonstrate possibly excessive
or nonexcessive flows in a sewer collection system and
to identify sources for later correction.

Correction of infiltration in existing sewer systems involves:

• Evaluation  and interpretation of  wastewater flow
  conditions to determine the presence and extent of
  excessive extraneous water
• The location and  measurement of such infiltration
  flows
• The elimination of these flows by various repair and
  replacement methods; and
• A diligent, continuous maintenance and  monitoring
  program.

Correction of inflow involves:

• Discovery of locations of inflow, determination of their
  legitimacy,  assignment of the  responsibility for
  correction of such conditions
• Establishment of  inflow control policies where none
  have been in effect; and
• Institution of corrective policies and measures backed
  by monitoring and enforcement procedures.

Control of I/I in all existing and new sewer systems is an
essential  part of sewer system management. A sewer
                                                   19

-------
system cannot be rehabilitated and then be expected to
never develop additional points of I/I. Proper preventive
maintenance programs must be established to monitor
and control  excessive I/I as an integral part of the
rehabilitation program.

The procedures involved in  conducting an I/I analysis
should be listed as an orderly sequence of tasks. Step-
by-step actions should be designed to explore the scope
and details of the problem.6This exploration will ascertain
the need and the techniques required for the subsequent
evaluation of causes, effects  and corrective actions.
Information must be gathered for making separate cost
estimates fortransportation and treatment of the infiltration
and inflow components versus elimination through
corrective action. Figure 3-2 provides the sequence of
events that shou Id be considered to properly analyze and
reduce I/I. If this  initial analysis indicates that the I/I is
excessive, the next phase should be the SSES, which
should determine the specific locations of inflow, flow
rates, and rehabilitation costs for each I/I  source. In
general, the  main goals of an I/I analysis report are to:

• Identify which  sewer systems  have reliable  data
  available to conclusively demonstrate nonexcessiveor
  excessive  I/I.
• Generate sufficient flow data and characteristics of the
  sewer system to enable a sound engineering decision
  to be  made regarding excessive and nonexcessive
  flow.
• Obtain realistic cost estimates for rehabilitation of
  sewers that contain excessive I/I and compare these
  costs to thecost of transporting and treating extraneous
  water.
• Enable the engineer, in the event of excessive I/I, to
  detail the work tasks for the new evaluation i.e., the
  SSES.

I/I analysis thus provides the fundamental evaluation and
indication of the existence of excessive flows in sewer
lines.

3.5.2   Preliminary Information Needed
Priorto conducting an I/I analysis, all pertinent information
and data should be collected on the specific wastewater
treatment and collection system under investigation.
This preliminary information should be enough to allow
the investigator to make a judgement of nonexcessive or
possibly excessive I/I.6'7

3.5.2.1 Interviews
Much of the basic data required for the I/I analysis can be
obtained from local sources by carefully planned and
executed interview programs. It is generally found that
the people who are most familiar with the sewer system
are public officials {both present and retired) and local
residents who will know from experience where many
defects may be located, where hidden interconnections
exist, what the history of performance has been, and
what the community's planning and growth needs have
been  and  will be. They know both permitted and non-
permitted  points of flow  into sewers as  well  as the
applicable  regulations  for plumbing  and  sewer
connections.

Results from well-conducted interviews may save the
engineer considerable field work and  also give  a clear
overview of the problems to be faced. The results from
the interviews may be utilized along with other findings to
make a proper judgement as to the seriousness of the I/
I problem in  the study area, the major problem areas in
the system, the percentage of the I/I which can possibly
be removed, and the areas which may require further
investigation. A specific interview pattern  and form is
used  by many consultants and municipal officials; this
form includes a broad spectrum of subjects, such as:

•  Sanitary sewer system
•  Storm sewer system
•  Existing and historical sewer maintenance program
•  Problem areas in and around the sewer system
•  Geological and geographical conditions in the sewered
  area
•  Population and water consumption data
•  Legal and jurisdictional aspects of the sewer system.

A thorough interview form is included in the Handbookof
Sewer System  Evaluation and Rehabilitation.4 This
interview form should be used as a guide and should be
adapted and/or modified to the system under study.

The purpose, nature and significance of the study should
be explained to the individuals being interviewed to avoid
any misunderstandings and to obtain full cooperation.
Good public relations should be practiced at all times.
Before an  interview, maps of the study area should be
studied by the interviewer to become familiar with the
area.  This will enable the interviewer to mark important
information on the maps to supplement the description
recorded in the interview forms.

Summary information from the interview should be plotted
on the map for easy identification. Discrepancies among
interviewees and/or between the interview results and
existing records should be evaluated. Some spot checking
should be performed to substantiate the interview results.
From the analysis of the collected information, a plan of
action can be made to gather more data needed for the
completion of the I/I analysis.
                                                   20

-------
Figure 3-2.
I/I analysis major activity flow chart.
                                  Assemble I/I Survey Team
                              Collect and Analyze Available Data
                                     on Sewer System
                                     Conduct Interviews
                                 Define System Components

                        • Define Sub-Basins
                        • Locate Critical Segments
                        • Conduct Sewer and Topographic Map Analysis
                        • Identify Overflow Points
                        • Locate Critical Monitoring Points
                        - Identify Surcharge Lines and Points, If Present
                                            I
                             C Tiduct Short-Term Flow Monitoring

                        • Select Monitoring Points
                        • Select Monitoring Techniques
                        • Select Monitoring Schedules
                        • Monitor Flow
                        • Record and Analyze Flow Monitoring Results
                        • Develop Baseline Flows .
                              Perform System Hydraulic Analysis

                        - Inflow/Rainfall Correlation and Distribution Studies
                        - Infiltration Effects
                        - Exfiltration Effects
                        - Migration Effects
                        - Rainfall Induced Infiltration
                        - Groundwater Effects
                        - Capacity Analysis
                        - Surcharge Predictions
                        • Model Development and Flow Distribution Analysis
                        - Future Flow Impact Analysis
                                                                               Sewer Maps

                                                                           As-Built Sewer IE-cords

                                                                      Past Studies, Engineering Reports

                                                                          Sewer Maintenance reco

                                                                      Lift Station and Plant Flow Records

                                                                          Sewer Overflow Records
                                                                       Conduct Rainfall Simulation and
                                                                       Inspection Studies as Required

                                                                        Select Design Rainfall Events

                                                                               Field Surveys

                                                                              Smoke Testing

                                                                             Rainfall Monitoring

                                                                            Dyed Water Flooding

                                                                        Nighttime Flow Measurements

                                                                        Pipe and Manhole Inspections

                                                                           Groundwater Monitoring
                          Perform Preliminary Cost-Effective Analysis

                        • I/I vs. Rule-of-Thumb Excessive vs. Non-excessive I/I
                        • Sub-Basin Analysis of I/I
                        • Indentification of SSES Study Areas
                        • Identification of Major Overflow Locations
                        • Identification of Surcharged Points/Segments
                                                                 21

-------
The patterned interview involves the first look at the
extraneous water  problem  in  the community. A
professional who is experienced in the area of I/I should
interview everyone who is or has been connected with
the sewer system. Subsequent analysis of the data will
answer questions and give the analyst a feel  for the
overall problem. The general objective of the interview is
to focus  on the more important  problem areas. The
questions should cover a broad spectrum of subjects,
ranging from technical matters to municipal performance
capabilities as well as questions  regarding the socio-
economic profile of the city. A well-planned interview also
helps the municipality to think about its problems -In an
orderly fashion and to recognize alternate methods for
solution.

3.5.2.2 Mapping and Map Analysis

a. Mapping
• All sewer lines and appurtenant structures should be
  recorded on authenticated maps.  As-built drawings
  should be available for all new sewer systems and
  some of the older sewers.

b. Updating or preparation of maps
• Augmentation of existing  maps with details of new
  construction and revisions
• Preparation of  new  maps from  as-built records,
  additional underground surveys and other data
• Sewer maps, as a minimum, should be drawn to scale
  and should indicate sewer sizes, slopes, direction of
  flow, manhole locations, as well as other major sewer
  system elements, e.g., pumping stations, treatment
  plants, bypasses, pointsof overflow, force mains, force
  main discharge points, etc.

In sewer systems where sewer maps are available, it
may be advisable to verify some of the critical points in
the field before total acceptance. Sewer maps should
also be updated to include new sewer extensions, sewer
line changes, buried manholes, and any other pertinent
data.7

In systems where  maps  are not  available  or are
incomplete, they must be developed before the study can
continue.

A street map is generally useful for the preparation of a
sewer map. In cases where street maps are not available,
a schematic layout of the sewer system may be suitable,
oramap may be developed. Sewer location and direction
of flow can also be  determined by dye tracers, floats,
smoke, metal detectors and interviews with people having
considerable knowledge of the sewer system.
c. Map Analysis?
Map analysis normally includes the following elements:

• Establishment of rational major sub-basins based on
  system layout,  drainage areas, main sewers  and
  tributary lines, system configuration and other local
  factors and system conditions
• Determination of sub-sections  when and where they
  are required to cover a more detailed study of conditions
  in specific parts of any sub-basins
• Preparation of sewer system flow diagrams and flow
  sheets
• Selection of key junction manholes for monitoring and
  gaging flows  in  each sub-basin which will reflect I/I
  conditions in constituent parts of the sewer system

Based on  the sewer maps, the following information
pertinent to I/I can be indicated and overlaid on the sewer
maps:

• Topography of the study area
• Soil and hydrogeologic formations
• Groundwater mapping
• Sewer age, type, and size
• Known or potential  problem areas such as areas
  subject to flooding during rainfalls, surcharged sewers,
  overflowing manholes, overloaded pumping stations,
  houses with sewer backup problems, obvious inflow
  sources,  existing and historical swampy areas, etc.

This information, along with the sewer maps, may enable
one to gain valuable information into the I/I problems of
the area such as:7

• Storm sewers crossing,  parallel to, or in the same
  trenches as the  sanitary sewers are likely I/I sources
• Sewersconstructednearrivers, streams, ditch sections,
  ponding areas and swamps may present serious I/I
  problems due to groundwater seepage or direct
  drainage.
• Sewers constructed in unsuitable soils that may be
  subjected to settling  resulting in open joints  and/or
  cracked  piping
• Older sewers  or ones of particular materials, joints or
  construction practices may present greater potential
  for I/I. Manholes with perforated covers may present
  serious inflow problems in low  lying street areas.
• Sewers constructed above seasonal high groundwater
  level should present few  infiltration problems.

3.5.3   Rainfall Information
                                                   22

-------
3.5.3.1 Sources of Information  and  Methods of
       Analysis
The measurement of precipitation as a part of sewer
system evaluation is undertaken to correlate rainfall with
flow metering data. Several items are generally of interest:
rainfall intensity, total volume per event, and duration of
the event. These data can be obtained from tipping
buckets or continuous weighing rain gauges. Charts that
record rainfall for several events and a totalizer that
provides a check against recorded data is useful. Snow
melting devicesforcolder climates are also available with
the precipitation measuring devices. Less sophisticated
devices such as graduated  cylinders may also be
appropriate to provide crude, supplemental information
in some cases.

Prfortotheimplementationofaprecip'rtation measurement
program, other less site-specific data should be obtained
and evaluated. Sources of precipitation data  are the
National Oceanic and Atmospheric Association (NOAA),
airports, state weather observers,  electronic media
weather observers, other public works and research
agencies and private citizens. NOAA has an extensive
nationwide  network of  recording rain gauges. Those
gauges with hourly rainfall data are summarized by state
in a monthly publication  entitled Hourly Precipitation
Data. Another useful publication  containing daily
precipitation quantities from  NOAA  stations  is
Climatobgical Data, which is also published monthly for
each state.

Rainfall causes inflow and can also cause infiltration by
the following mechanisms:6

* Rainfall and/or surface run-off may be carried directly
  through the cracks in a clay soil surrounding shallow
  sewer lines and manholes and leak through the
  deteriorated manhole walls  and sewers to cause an
  infiltration problem.
• During and immediately after heavy  rainfall, the
  rainwater  reaches the  groundwater by percolating
  through  overlying soils and causes an increase  in
  groundwater level. The amount and rate of piezometric
  head increase isafunction of the soil type and structure.
  This increases the potential hydraulic head. If the  level
  is above the sewer pipes it increases the driving force,
  which can cause the water to enter the pipes through
  defective joints, etc.
• In locations where the sewer pipes are cut in u nderly ing
  bedrock, the rainwater,  after percolating through the
  overlying soils, will likely flow in the same trench and
  thereby cause an increased  infiltration problem in the
  sewers.
• During heavy rainfalls, anotherphenomenon may occur
  in the soil and increase the infiltration rate in the
  sewers. This is the case when a large ground surface
  is covered  by impounded rainwater: as this  large
  blanket of impounded water percolates through the
  soils underneath, it leaves little chance for the air in the
  soil to escape. Because of this, the air is subjected to
  increased pressure. The pressure is transmitted to the
  groundwater above the sewer pipe and may cause an
  increased infiltration rate through defective pipe joints,
  etc.3

3.5.4   Topographic and Geologic Information

3.5.4.1  Sources  of Information and Method of
        Analysis
Soil conditions in  the sewer system study area often
affect the I/I problems. Sewers constructed on unsuitable
soils  may  be subjected to settling,  expansion, or
contraction resulting in open joints or cracked pipes. Soil
chracteristics that  affect I/I response are:4

• Permeability, among other soil characteristics, affects
  the rate of movement  of groundwater through the soil
  matrix adjacent  to sewers and sewer trench backfill
  materials.
• Backfill and bedding materials immediately surrounding
  the sewer affect the  structural integrity of sewers.
  Granular sewer bedding materials are quite porous
  and often act as a secondary conduit that transmits
  groundwater along the sewer line  thus  providing
  additional opportunities for infiltration at downstream
  locations.
• Impermeable soils  such  as clays that are used as
  backfill above the granular bedding layer reduce the
  vertical penetration of surface waters entering the
  sewer envelope.

Information on soil distribution and soil characteristics in
an area can be obtained from the following sources:7

• Soil  Conservation Service.  U.S.  Department of
  Agriculture. The  Soil Conservation Service  has
  published many soil  maps with descriptions of soil
  characteristics. They  have offices in most counties
  throughout the country.
• Boring logs in sewer construction contract documents.
  Boring logs contained in the sewerconstruction contract
  document provide certain details about the soils along
  the sewer construction route.
• State Agricultural  Extension  Service. Data on soil
  types and soil characteristics may have been collected
  by the State Agricultural Extension Service.
• Local Construction Companies or Contractors. Local
  construction companies or contractors, particularly
  well drilling firms, should have some information about
  the area's soils.
                                                   23

-------
• Field Investigation. For locations  where  no soil
  information is available  or existing  information  is
  contradictory or indicative of serious problems, a field
  soil study may be needed. The study may include the
  test borings at key points and interpretation of the
  collected soil samples. For complex and unusual cases,
  the soil samples should be interpreted by a soil scientist.
  Assistance may be available from the Soil Conservation
  Service, Agricultural Extension Service representatives,
  consulting soil scientists or agronomists.

3.5.5  Ground Water Information

3.5.5.1 Sources of  Information  and Methods of
       Analysis
Information is required to determine the variations in the
groundwater level. Most of the infiltration phenomena in
sewers are  groundwater  related.  Determination  of
infiltration in  the sewer system should be based on a
comparison of the wastewater flow data collected in the
high groundwater periods with data collected in the low
groundwater periods. Sewer line inspections should be
conducted during highgroundwaterperiods. Groundwater
monitoring should be conducted if no data are available.
The level and,  in  certain  cases   the chemical
characterization of the groundwater affect the degree of
infiltration in the sewers. General groundwater information
can be obtained from a number of sources:47

• State Water Resource Agencies
• U.S. Geological Survey
• Local or County Water Conservation Districts
• Groundwater users, including municipalities,  water
  companies and individuals
• Local construction companies or contractors

Two types of groundwater level measurement gauges
are commonly used for sewer evaluation studies: the
manhole gauge and the piezometer. The manhole gauge
shown in Figure 3-3 is used to determine groundwater
levels adjacent to  manholes. These gauges are
inexpensive  and fairly easy to install; however, they do
clog easily from mineral deposits. The piezometer shown
in Figure 3-4 is generally installed in a hole excavated by
a powered flight auger. Piezometers are more permanent
and are far less prone to clogging. They are also more
expensive, but with proper maintenance should last for
years and provide higher  quality data than manhole
gauges

  Installation  sites for groundwater gauges should be
away from underground utilities and streets to prevent
damage  from  street  maintenance equipment.
 Groundwater levels can be recorded on a periodic basis.
A plot of groundwater levels versus time is helpful in
interpreting  meter data  and determining  levels of
infiltration. The recorded data obtained from groundwater
gauges should be reviewed and screened carefu lly before
beingused. Pumping waterfrom nearby wellsmay cause
atemporary drawdown of the groundwater surface at the
monitoring stations, which may give biased groundwater
levels. Groundwater levels should be measured during
periods of the day when groundwater pumping in the
study area is at a minimum.

3.5.6  Baseline Sewer Flows

3.5.6.1 Population and Flow Projection Methods
Population  and  flow  data  are essential for the
determination of I/I. They determine the  theoretical (or
base) wastewater production rate in the study area. The
theoretical wastewater production represents the total
quantity of wastewater including domestic, commercial,
and industrial wastewaterflows, but excluding all infiltration
and inflow. Flow rates are expressed as gal/capita/day
(gpcd).

Monitoring of flows at treatment plants, lift stations, and
properly located junction  manholes is essential.  Flow
monitoring should be carried out at different times of the
day as necessary to permit differentiation between normal
expected sanitary flows and I/I volumes. Treatment plant
and  lift station flow  records should be evaluated and
necessary information should be gathered to produce an
adequate I/I analysis. The baseline sewerf low monitoring
tasks should include the following:4

• Verify flows from plant records, pumping or lift station
  charts or log sheets, or from previous sewer monitoring
  at the same or nearby locations involved in the current
  analytical procedure.
• Gauge flows at key  junctions, manholes,  pumping
  stations and overflow points during hours of minimal
  flow to  determine the presence  and  amounts of
  infiltration volumes in various subsections of the sewer
  network.
• Determine daily and hourly flow variations in a limited
  number of locations for the purpose of monitoring the
  effect of rainfall on the flow characteristics in various
  sub-systems and to ascertain the quantity of infiltration
  and inflow and to differentiate  between the two
  components.

The population data should be gathered only for the
periods in  which records for water  consumption,
wastewater flow, groundwater and rainfall are all available.
Both the total population  and the sewered population
should be known  for the determination  of I/I. In areas
where there are seasonal fluctuations in populations, a
detailed breakdown of the population according to season
                                                   24

-------
Figure 5-3.        Static groundwater gauge installation elevation.
                                                                   Known Elevation
                                                                              Install Gauge As Near As
                                                                              Possible to the Top of the
                                                                              Lowest Pipe in the Manhole
                                                           Groundwater
                                                          Gauge Reading
                                                              25

-------
Figure 3-4.
Groundwater gauge installation detail.
                                                                 Threaded Cover
                                                                 (to extend above
                                                                 ground surface)
                              Concrete Seal
                                                                                      Steel Casing
                                                                                PVC Casing
                                                                          Opening to Allow
                                                                          Entering of Groundwater
                                                                    Filter-Cloth Wrapping
                                                                    Over Slotted Section
                                                                         Cap
                                                               26

-------
or month should be provided. Population records are
availablefromthe U.S. Census Bureau, local government
offices and sanitary districts. Such data may also be
reported in previous engineering study reports. If no data
are available, a physical survey to include census, house
count, and aerial maps may have to be performed to
determine the population.6-7 Preference should be given
to wastewaterf low records. All water use does not end up
in the  sewer. Water consumption (metered) is also
measured on a cumulative basis (e.g., 100 cu ft/mo).

3.5.6.2 Water Use and Wastewater Generation
       Estimates
The  water consumption data to  be obtained should
coincide with the available records for wastewater flow,
groundwater and rainfall. Metered water data available
for all'users  in the study area should be collected and
used for the estimation of the wastewater production
rate. Waterconsumption recordscan usually be obtained
from local water departments, private water companies,
industrial  plants and individual  well users. Water
consumption estimatescan be made based on population
and  an inventory of the  residential, commercial  and
industrial establishments in the study area using typical
water use rates. Water production records can also be
used where water consumption data are not available. If
water  production  data  are  used, allowances for
consumptive use should be made so baseline wastewater
flows are not overstated.

Wastewaterflow recordscovering the entire sewersystem
over a period of 1-2 years should be used for I/I analysis.
These records should include and representgroundwater
and rainfall conditions in the study area. For larger sewer
systems, flow records may have  to be gathered from
more than one treatment plant, pump station or flow
measuring station in  the system. Flow records for
overflows, bypasses and emergency pumping should be
gathered for the I/I analysis. Wastewater flow records
can  be obtained from wastewater treatment plants,
sanitary districts  or sewer departments in local
governments.

The  water consumption  and wastewater flow records
should be checked for accuracy before being used. The
accuracy can be determined by checking the accuracy of
the instruments used  for recording and totalizing the
flows.

3.5.7  Analysis of Infiltration and Inflow

3.5.7.1 Purpose of Analysis
Properanalysis of the data to determine I/I flow rates into
the sewer system is essential for accurate estimation of
the effectiveness of sewer rehabilitation. Discrepancies
between estimated and actual I/I reductions are likely if
improper I/I analysis occurs. Establishing the quantities
of I/I entering a collection system is: far from being an
exact science.  I/I analysis should consider various
inaccuracies of flow measurement in  sewer systems.
The procedures for interpreting I/I data should recognize
the impact of  rainfall events, groundwater  levels,
antecedent soil and weather conditions and monitoring
schedules on the overallcomponenl flows.

Baseline wastewater flow data are normally collected
during dry-weather conditions. Groundwater infiltration
should be measured during high groundwater since it will
be significantly impacted bygroundwaterlevelsthroughout
the sewer systems. Inflow and  Rll component flow
information are strongly related to the characteristics of
the rainfall events occurring during the monitoring period.
As discussed in Section 3.5.7.3, Rll flows are strongly
rainfall dependent even though they do not  enter the
sewer system directly.

In many cases  it is not possible to clearly distinguish
inflow, groundwater infiltration and Rll. The sum of these
components however can be estimated by subtracting
the baseline flow from the total flow. These numbers can
be used and compared to the accepted  rules of thu mb of
450 Lpcd (120 gpcd) of domestic plus non-excessive I/I
flow and the storm flow of 1,000 Lpcd  (275 gpcd). The
cost-effective analysis for infiltration and inflow requires
that these two components be  separated. The  cost of
transportation and treatment requires that peak flows be
determined. A proper cost-effective analysis generally
requires that the following flows be determined:
  Peak infiltration
  Peak inflow
  Peak I/I
  Total yearly infiltration
  Total yearly inflow
  Total yearly I/I

3.5.7.2 Groundwater Migration
It is believed that much  of the infiltration removed by
rehabilitation of a source "migrates" to other sources that
were either inactive or less active before rehabilitation.
This phenomenon, known  as migration, has led to
disappointing results in typical rehabilitation programs,
which have demonstrated a disparity between anticipated
and actual reduction of infiltration.8

Sanitary sewer rehabilitation has seldom resulted in the
infiltration reduction projected by sewer system surveys.
Studies performed at two sites in the Washington
Suburban Sanitary Commission (WSSC) sought to
determine whether the assumed removable infiltration
                                                   27

-------
migrates to sources which were inactive or less active
before rehabilitation.8 To investigate the impact  of
migration on rehabilitation, 43 groundwater wells were
installed in two study areas with a recording flow meter at
each site. Well level readings, nighttime flow, isolation
measurements, and local rainfall data were obtained.

After all sewersystem defects were inventoried, selective
rehabilitation consisting of line and manhole  grouting,
excavation and repair of sewer segments and grouting of
service connections was conducted. Rehabilitation was
implemented  in two phases in  each study area with
groundwater and infiltration response measured before,
during, and after each phase of rehabilitation. Migration
of grou ndwater infiltration to previously inactive locations
was documented at both study sites. This migration
effect was accompanied by a corresponding increase in
groundwater level at one of the two study sites. Based on
an analysis of the data, it was observed that migration
effects travelled as much as 60 m (200 ft)  to reach
unrehabil'rtated sources. Results of this study indicate
that the traditional point source method of I/I analysis is
only about half as accurate as it would be if migration
were properly integrated.

Migration of groundwater infiltration to previously inactive
sources can be documented by a corresponding increase
in groundwater level at the study sites. One documented
occurrence of groundwater level increasing after
rehabilitation is illustrated in Figure 3-5. In this figure,
Well 03 was located away from the sewertrench and Well
E was located on the trench.8

One factor that affects  migration phenomena is soil
permeability. An important characteristicof existing SSES
methodology  is the reliance on individual line section
nighttime isolation and measurement to identify sewer
reaches subject to excessive infiltration. This fragmented
approach provides an opportunity for migration since this
process identifies conditions at  one point  in time,
eliminating potentially defective elements of the system
from further study. To effectively account for migration,
the flow monitoring procedure must be revised to expand
the data on an  individual line segment basis. This will
involve initially monitoring  sub-areas with extended
duration metering.9

Migration of infiltration from rehabilitated tounrehabilitated
sources was  observed  and documented under work
carried out by the WSSC. The extent of migration was
primarily dependent on the number and  location  of
rehabilitated  sources in addition to differences  in
permeability between trench material and surrounding
soil. Results of the study by WSSC indicate that
rehabilitation should be clustered in areas conducive to
migration to achieve net flow reductions. If rehabilitation
is not generally concentrated then flow removed from
one source  would  essentially  migrate to nearby
unrehabilitated sources. General conclusions applied to
the WSSC study on migration were:8

• Migration is probably not significant for a sewer system
  constructed substantially below the groundwater level
  since increases in in-trench groundwater as a result of
  rehabilitation would probably result  in only a minor
  increase in head compared to the existing head on the
  sewer system. Interceptors that run along the banks of
  creeks and rivers  are typical of sewer lines below
  groundwater levels.
• Sewers located in highly granular areas would not be
  subject to significant migration because groundwater
  movement would not be restricted by low permeability,
  thereby allowing exfiltration from the trench.
• Topographically flat areas would be less subject to
  migration since the lack of steep gradients would result
  in some outward dissipation rather than exclusive in-
  trench movement.
• Sewers in soils of lowpermeability are highly conducive
  to migration. Despite  backfill consolidated during
  construction the sewer trench would be considerably
  morepermeablethanthe surrounding soil since sewers
  are normally supported by granular material such as
  gravel and sand.

In a comprehensive rehabilitation program, it would be
desirableto eliminate sources located on private property,
especially house services. Here rehabilitation tends to be
more expensive on the basis of unit flow rates. Private
sector rehabilitation has political implications when part
or all of the rehabilitation is paid by the property owners.

3.5.7.3 Rainfall Induced Infiltration (Rll)
Rainfall Induced Infiltration (Rll) is a form of infiltration
that behaves.somewhat  similar to and  is sometimes
confused with storm water inflow.  Rll generally occurs
during or immediately after rainfall events. It is caused by
the seepage of percolating rainwater into manhole, pipe,
and lateral defects that lie near or are readily reached
from the ground surface. Foundation drains are a special
case  which has been classified  as both inflow and
infiltration by regulatory authorities. The quick rainfall
response of Rll causes a  more rapid build-up of flow in
sewers than  normal I/I flows thus creating a greater
potential for sewer surcharging and overflow.

An  ancillary problem associated with  Rll as with any
infiltration problem  is that there  is the potential for
exfiltration of  untreated wastewater at these same pipe
and manhole defects. In  some cases, discharged
wastewater may cause groundwater contamination; in
                                                   28

-------
Rgure 3-5.
Effects of groundwater on migration.
          t
          I   *
          "S   *J .
                                    •e
                                    0)
                                   o>
                                                                                                                     c =
                                                                                                                     i S
                                                                                                                     o 
-------
other cases it might be channelled by sewer trenches to
potential points of direct human exposure. Data based on
a study conducted by the U.S. EPA indicates the following
conclusions and findings regarding the impact of Rll:3

• Rll is  a type of  infiltration since it enters the sewer
  system through  defects.  However,  its  flow
  characteristics resemble those of inflow i.e., there is a
  rapid increase in flow which mirrors the  rainfall event
  followed by a decrease as the rain stops.
• Becauseofitsflowcharacteristics, Rllhasoccasionally
  been  misidentified as  inflow in  many  cases.
  Consequently, rehabilitation programs aimed at inflow
  sources have not achieved the anticipated reduction in
  extraneous flows in these cases.
• Rll appearsto represent a significant portion of the flow
  to some wastewatertreatment plants during wet weather
  periods. InthelOcase studies conducted by U.S. EPA,
  the peak wet weather flows were 3.5-20 times the dry
  weather flow. The contribution from Rll was estimated
  to be between 60-90 percent of the wet weather flows,
  the remainder being groundwater infiltration and inflow.
• Collection and treatment systems often do not have the
  capacity to handle peak wet weather flows. Peak flows,
  therefore, can cause wastewaterbackupsintobuildings,
  overflows  and treatment  system bypasses. Such
  occurrences are a hazard to public health and a
  violation of the municipality's discharge permit.
• Sewer trenches can  act  as collectors of  rainfall
  percolating into the soil. The trenches channel the
  water, thus providing  multiple opportunities  for the
  water to seep into the  collection system at defective
  points.
• The shallow portions of a collection system, e.g. building
  laterals, manhole defects, etc. are more vulnerable to
  Rll. Interceptors sewers, which are typically deeper, do
  not appearto be a significant entry point for Rll, but are
  more  likely sources of groundwater infiltration, which
  normally minimizes peak to average flow ratios.
• The extent of Rll problems in sanitary sewer systems
  is related  to the age and condition of the sewers,
  material of construction, pipe, lateral and manhole
  defects, climate, geology, groundwater levels, and
  depth of sewers.

Figure 3-6 presents the typical entry points of Rll.

3.5.7.4  Method of Analysis
The following techniques can be used to estimate the
total infiltration in a sewer system:

a. Water Use Evaluation
This method uses the water supply records  for the
purpose of estimating the amount of domestic wastewater
discharged to the sanitary sewer system. Monthly water
use records are obtained. As an estimate, the percentage
of the water that would reach the sanitary sewer would
range from 70 percent in summerto 90 percent in winter.
Given these facts, the rates at which domestic, industrial
and commercial wastewater should flow into the sanitary
sewers can be determined. These calculated flow rates
can be subtracted from the total flow measured at the
wastewatertreatment plant to obtain an estimate of the
infiltration entering the sewer system. Factors that should
be considered when using this method for  infiltration
analysis are:

• Confirmation of the consumptive use mentioned above
• The amount of unaccounted water supplied through
  the system through wells, springs,  or reservoirs that
  would not  be accurately measured due to faulty or
  inaccurate meters or lack of metering. Unaccounted
  for water also includes  illegal taps and unmetered
  withdrawals from fire fighting lines, street flushing fire
  lines, or hydrants.
• For areas supplied with a secondary water system, the
  water balance must include this source.

b. BOD Evaluation
The mass BOD  loading from domestic and industrial
sources are used in this method. The method assumes
that the average BOD of domestic waste without infiltration
is 200 mg/L  Monthly treatment plant flow records are
used to determine  total flow and  average actual BOD
daily loading. The industrial flow and BOD loading must
also be estimated in order to use this method.

First, the total BOD loadtothetreatment plant iscalculated
in mass/d from the plant influent flow and actual influent
BOD. Next the industrial flow and BOD load is estimated
and subtracted from the total plant load. The normal
domestic flow is calculated by knowing the domestic
BOD load and using an influent BOD concentration of
200 mg/L. The infiltration isthen calculated by subtracting
the calculated domestic flow plus the estimated industrial
flow from the actual plant flow. The procedure can be
completed on a daily, monthly or annual basis. The
accuracy of the procedure depends on the accuracy of
estimating industrial flow  and BOD load. It should be
applied to the total system rather than to sub-systems
because of limitations due to unequal distribution of
domestic and industrial flows in smaller sub-systems.

c. Maximum-Minimum Daily Flow Comparison
This method  assumes that infiltration will be constant
throughout the day if there is no precipitation. Industrial
flows are also assumed to be constant throughout the
day, so the daily flow variations measured are strictly
attributed to the domestic flow contribution. Treatment
plant influent data can be evaluated to obtain the domestic
                                                   30

-------
Figure 3-6.
Typical entry points of rainfall induced Infiltration.
                                                                                                 Si
                                                                   31

-------
flow rate. The domestic flow rate and the industrial flow
rate are subtracted from the total flow rate, which gives
the resultant quantity as the rate of infiltration. This
procedure can be carried out using monthly averages to
obtain the estimated infiltration for the entire year.

d. Determination of Total Yearly I/I
The following procedure is used to estimate the yearly I/
I in the sewer system:

•  Obtain the average  daily, weekly, and monthly
  wastewater flow data from treatment plants for the time
  period of interest. A minimum of  one year of data
  should be used.
•  Obtain and/or calculate  the theoretical wastewater
  production rates; also the rainfall  and groundwater
  levels throughout the sewer system  area should be
  noted throughout the study period.
• Plot  the rainfall  duration and intensity along with
  groundwater levels.
• For each storm, plot the average wastewaterf lows and
  the theoretical wastewater production rateasafunction
  of time, as shown in Figure 3-7.
• The area in the plot which is between the theoretical
  wastewater  production rate and the recorded
  wastewater flow rate represents an  estimate of the
  yearly I/I.

An estimate of yearly infiltration can be estimated as
follows:

• Select several months of data from the total yearly I/I
  plot (Figure 3-7) and plot rainfall duration and intensity,
  total  recorded  wastewater  flow and  theoretical
  wastewater production rate.
• Draw a line through the lower limit of the recorded
  wastewater flow  as shown in Figure 3-8.
• The distance between this line and the theoretical
  wastewater production provides an  estimate of the
  infiltration.

Total yearly inflow can  be estimated by the following
procedure:

• The total yearly inflow  can be obtained by subtracting
  the total yearly infiltration from the total yearly I/I. The
  total yearly inflow obtained may contain some amou nts
  of infiltration which is induced by rainfall and is known
  as Rll.

3.6    Exfiltration and Its Impacts

3.6.1   Introduction
Exfiltration is a relatively new topic in the sewer system
rehabilitation field.  Exfiltration occurs when deteriorated
or poorly  designed or constructed sewer lines allow
wastewaterto escape from the sewer into the surrounding
soil. An exfiltration study was initiated by the U.S. EPA
because it was not known what effect exfiltration from
sewers had on the groundwater in the area. It was
believed that industrial and domestic wastes flowing in
the sewers could  be escaping into the nearby soil and
possibly percolating to the grou ndwater and contaminating
it. Results of the Evaluation of Groundwater Impacts of
Sewer Exfiltration^0 summarizes the activities and findings
of this study. The U.S. EPA study showed that it was
impossible to correlate infiltration with exfiltration.
Previously exfiltration has been used to estimate
infiltration. This  practice appears  to have limited
applicability unless a special case can be demonstrated
where such a correlation does exists.

3.6.2   Summary of Information on Impacts
The U.S. EPA study showed that substantial exfiltration
does  exist in locations where the groundwater level is
sometimes or always below the sewer. In fact, in the two
field studies which were performed, exfiltration rates
were found to be greater than infiltration ratesin locations
where fluctuating groundwater levels allowed for both
infiltration and exfiltration.

As  a part of the U.S.  EPA exfiltration study, the
groundwater was  sampled and analyzed in areas where
sewer exfiltration existed. The results of the groundwater
analyses were inconclusive. Tests performed in one area
indicated that exfiltration was not contaminating the local
groundwater. Tests in a second area showed slightly
higher levels of several contaminants but the study could
not prove that these contaminants were a  result of
exfiltration.

3.6.3   Consideration in I/I Analysis
It is important that the possible effects of exfiltration be
considered in an  I/I analysis. Ignoring exfiltration could
lead to the calculation of inaccurate infiltration rates.

3.6.4   Present and Future Environmental Impacts
Even though the results of the exfiltration study were
inconclusive, the environmental impacts of exfiltration
are potentially significant. If exfiltration of wastewater is
contaminating groundwater, it  could  have a serious
impact on the environment.  More research  is required
before the environmental  impact of exfiltration can be
determined,  but  the potential  for contamination of
groundwater is greatest in coarse soils above unconfined
aquifers.

3.6.5   Exfiltration Tests and Methods
Exfiltration tests have historically been used as an indirect
method of estimating infiltration potential for both old and
                                                    32

-------
Figure 3-7.
Determination of total yearly infiltration/Inflow.
                 •a
                 cc
                  I
                  2
                                                                     corded Wastewater Flow
                        lljlljjjljj. .
                                          Theoretical Wastewater Production Rate
                                                              Time
                                                                                                          j
                                                                                                         1 Year
                                                                 33

-------
Figure 3-8.        Determination of total yearly infiltration.
                                                              Recorded Wastewater Flow
                                                                             Non-Rainfall Day
                                                                             Wastewater Flow
                                                Theoretical Wastewater Production Rate
                                                                                                   •Maximum Infiltration
                                                                                             1 Month
                                                              Time
                                                                34

-------
new sewer systems. It is most commonly applied io new
sewers and is normally a part of new sewer construction
specifications. Accurate exfiltration  tests requires a
knowledge of ground water levels, adequate pre-soak
times and maintenance of adequate head differentials on
the system.

Prior to the initiation of an exfiltration test, the level of
groundwater adjacent to each section undergoing the
testing must be measured and recorded. The exfiltration
test works on the basis that a certain pressure will force
water out of the line into the soil surrounding the pipe. The
following is an outline of an exfiltration test procedure:

• Clean the pipe section from manhole to manhole for
  each  reach of  sewer being tested (applies to  old
  sewers).
• Seal the upstream pipe inlet of the upstream manhole
  and the upstream pipe of the downstream manhole
  with plugs to ensure tight seals against water leakage.
  Since the exfiltration test can take several hours, the
  need fortemporary wastewaterbypassing around the
  test section should be anticipated.

The exfiltration test is based on the loss of water from the
section of sewer being tested and thus requires a method
of establishing a specific pressure head on the system.
The upstream manhole is often used as a reservoir for
maintaining the pressure head. A standpipe may be used
in stead oftheupstreammanholeforprovidingthe pressure
head on the system.

• Afterproperty sealing and isolating the test section, the
  sewer and manhole or standpipe must be filled with
  water. The upstream manhole or stand pipe is used to
  introducetestwaterintothe system and for maintaining
  an adequate pressure head. The test head should be
  60 cm (2 ft) above the pipe crown at the highest point
  or 60 cm (2 ft) above the groundwater level.
• Water shou Id be allowed to stand in the test section for
  a period long enough to allow water absorption in the
  pipe. This time should be as much as 6 hours for
  concrete pipe depending upon the degree of saturation
  prior to testing. After the absorption period, the pipe,
  upstream manhole, or stand pipe is refilled and the test
  begun. This step is not necessary for vitrified clay or
  plastic pipe.
* Determination of the actual exfiltration is based upon
  the method used for providing pressure head on  the
  system, either by standpipe orthe upstream manhole.
• Use of the standpipe requires that a constant water
  level be maintained in the standpipe to maintain  the
  specified pressure head on the sewer section  under
  test. Therefore, the volume of water  added to  the
  standpipe over the one hour test period is the actual
  exfiltration rate from the section under test.
• When using the manhole, the exfiltration rate will be
  determined by measuring the difference of the final
  water elevation and the initial  water elevation  and
  converting this to actual gallons lost through the pipe in
  a one hour period.
• If the pipe being tested does not meet the permissible
  loss, the section of sewer is considered unacceptable.
  Another exfiltration test should not be conducted until
  thegroundwaterconditionssurroundingthe pipe return
  to a condition similar to those existing at the beginning
  of the test period. The groundwater elevation should be
  determined prior to initiation of the second test.

A less commonly used exfiltration testt is the continuous
flow monitoring  technique. Continuous  flow monitoring
should be performed in a 300-m (1,000-ft) section of
sewer  or greater which contains nothing that could
interfere with  the test results. The groundwater level
must be below  the sewer to ensure that no infiltration
occurs and there must be no laterals or cross connections.
Certain characteristics of the test section must be constant
forthe entire section: the size, type and age of sewer pipe
and the type of soil surrounding the pipe. The flow rates
at the beginning and  end of the test section  are
continuously measured  and the difference between the
two is the amount of exfiltration. In the exfiltration study,
the flow measurements were made using a weir  and
differential pressure sensing bubbler flow meter  and
flows were measured and recorded for at least 48 hours.5
Other types of flow measurement schemes would  also
work, based on  the same physical principles.

If a 300-m  (1,000-ft) section of sev/er that meets the
above criteria cannot be found, a shorter sewer or one
which contains  a few disturbances may be used.  The
effect of the disturbances would need to be measured
and analyzed, however, and would introduce significant
errors into the calculation of the exfiltration.

3.7     References

When  an NTIS number is cited in a reference,  that
reference is available from:

       National Technical Information Service
       5285 Port Royal Road
       Springfield, VA  22161
       (703) 487-4650

1.  Odor and Corrosion Control in Sanitary Sewerage
    System and Treatment Plants. IE PA/625/1-85/018,
    EPA, Cincinnati, Ohio, 1985.
                                                   35

-------
2.   Report to Congress: Hydrogen Sulfide Corrosion in
    WastewaterCollectionandTreatmentSystems.EPfiJ
    430/09-91/009.  U.S.  Environmental Protection
    Agency, Washington, D.C.

3.   Rainfall Induced Infiltration  into Sewer Systems,
    Report to Congress, 1990.

4.   Handbook for Sewer System Evaluation and
    Rehabilitation. EPA/430/9-75-021, Office of Water
    Program Operations, U.S. Environmental Protection
    Agency, Washington, D.C., 1975.

5.   Technology and Design Deficiencies at Publicly
    Owned Treatment Works, Water Environment and
    Technology, December 1989.

6.   American Public Works Association. Sewer System
    Evaluation, Rehabilitation and New Construction: A
    Manual of Practice. EPA/600/2-77/017d, NTIS No.
    PB-279248. U.S. Environmental Protection Agency,
    Municipal Environmental Research Laboratory, Office
    of Research  and Development, Cincinnati,  Ohio,
    December 1977.

7.   Existing Sewer System Evaluation and Rehabilitation.
    ASCE Manuals and Reports on Engineering Practice
    No. 62, WPCF Manual of Practice FD-6. American
    Society of Civil Engineers, Water Pollution Control
    Federation, 1983.

8.   National Water Well Association, R JN Environmental
    Associates, Inc., and Washington Suburban Sanitary
    Commission. Impact of Groundwater Migration on
    Rehabilitation of Sanitary Sewers.  1984.

9.   Montgomery County Sanitary Department. Ground
    Water Infiltration and Internal Sealing of Sanitary
    Sewers. Water Pollution Control Research Series,
    U.S. Environmental Protection Agency, 1972.

10. Engineering-Science. Results of the Evaluation of
    Groundwater Impacts of Sewer Exfiltration. Study
    conducted under  contract  no. 68-03-3431,
    Performance Assurance Branch, Municipal Facilities
    Division, Office of Water,  U.S. Environmental
    Protection Agency, 1989.
Additional Reading

American Public Works Association. Control of Infiltration
and Inflow into Sewer Systems. 11022 EFF12/70, Water
Quality Office,  Environmental Protection Agency and
Thirty-nine Local Governmental Jurisdictions, 1970.
American  Public Works Association. Excerpts from
Control of Infiltration and Inflow into Sewer Systems and
Prevention and Correction of Excessive Infiltration and
Inflow into Sewer Systems. EPA/670/9-74-004, Water
Quality Office, Environmental Protection Agency & Thirty-
nine Local Governmental Jurisdictions, 1971.

American  Public Works Association. Prevention and
Correction of Excessive Infiltration and Inflow into Sewer
Systems. NTIS No.  PB-203208, Manual of Practice,
Water Quality Office, Environmental Protection Agency
& Thirty-nine Local Governmental Jurisdictions, 1971.

Bodner, R. L. and R.E. Nelson. Measuring Effectiveness
of Infiltration/Inflow Removal. Public Works  113:50-52,
October 1982.

Carter, W. C.,  A.J. Hollenbeck, and R.J. Nogaj. Cost
Effectiveness and Sewer Rehabilitation. Public Works
117:64-67, October 1986.

Connelly, Conklin, Phipps & Buzzell, Inc. Evaluation of
Infiltration/Inflow Program Final Report. EPA-68-01 -4913,
Off ice of Water Program Operations, U.S. Environmental
Protection Agency, 1980.

Construction Grants 1985. EPA/430/9-84-004, Office of
Water, U.S. Environmental Protection Agency, 1984.

Darnell, P.E. Conducting Sewer System Evaluations for
Small Systems. Water &  Sewage Works  123:68-71,
November 1976.

Debevoise, N.T.  and  R.B.  Fernandez.  Recent
Observations and New Developments in the Calibration
of Open ChannelWastewaterMonitors.J\NPCF5B-A185-
1191, November 1984.

Deciding  to Rehabilitate, Repair, or Replace. Water
Engineering & Management 132:50-53, May 1985.

Driver, F.T. Manhole I/I Stopped with Special Repairs.
Water Engineering & Management 130:31 -32, April 1983.

Experts Discuss Private Sector Infiltration/Inflow. Water
Engineering & Management 130-32-34, September 1983.

Fernandez, R.  B. Sewer Rehab Using a New Subarea
Method. Water Engineering & Management  133:28-30,
February 1986.

Goss, R., R. Stalnaker, and R. Thornhill. Inflow Reduction
Eliminated Need for New Interceptor. Water Engineering
& Management 136:52-55, September 1989.
                                                 36

-------
Gray, W. R. and R.J. Nogaj. Sanitary Sewer Bypass
Reduction Program. Water Engineering & Management
137-36-40, May 1990.

Heinecke, T.L. and C.H. Steketee. The Key to Effective
I/I Control. Public Works 115:88-92,106-107, June 1984.

Hollenbeck, A.J.  Designing  for Removal of Sanitary
Sewer Cross  Connections. Water  Engineering &
Management 131:29-31, April 1984.

Hollenbeck, A.J.  and G.D.  Lambert. New Approach
Achieves Inflow Reduction in Sanitary Sewers. Public
Works 118:119-121, September 1987.

Hollenbeck, A.J. and R.J. Nogaj. Inflow Distribution in
Wastewater Collection Systems. Water Engineering &
Management 129:30-33, January 1983.

Hollenbeck, A.J. and R.J. Nogaj.  One Technique for
Estimating Inflow with Surcharge Conditions. JWPCF
53:491-496, April 1981.

Infiltration  Inflow Collection System Management:
Challenge of the 80's. I/I Evaluation and Control Division,
Department of Maintenancelind Operations, Washington
Suburban Sanitary Commission, Hyattsville, MD, 1982.

J.M. Smith & Assoc. Analysis of Acceptable Ranges for
Infiltration and Inflow Reduction in Sewer  System
Rehabilitation Projects. Study conducted under contract
EPA  68-01-6737,  Performance Assurance Branch,
Municipal Facilities Division, Off ice of Municipal Pollution
Control,  U.S. Environmental Protection Agency,
Washington, D.C.

Johnson, W.D., S.R. Maney, and G. McCluskey. Open
Cut Sewer Construction Across Railroad Tracks Saves
Money. Public Works 120:73, June 1989.

Mayer, J.K., F.W. MacDonald and S.E. Steimle. Sewer
Bedding and Infiltration, Gulf Coast Area. 11022 DEI 057
72, Office of Research and Monitoring, Environmental
Protection Agency, 1972.

Montgomery CountySanitary Department. Determination
of Ground  Water Infiltration and  Internal Sealing of
Sanitary Sewers. Water Quality Office, Environmental
Protection Agency, 1971.

Nelson, R.E. New Ways to Fix Leaky Sewers. American
Crty & County Magazine 95:39-42, September 1980.
Nogaj, R.J. I/IRehab Success Comes With Understanding
System Behavior.  Water/Engineering & Management
131:36-38, February 1984.

Owens, R. A U.S. Testforlnsituform;or, Howto Rebuild
a Pipe from Within. American City & County Magazine,
September 1980.

RJN Environmental Associates,  Inc.,  Consulting
Engineers. Making Effective Use of Existing Collection
Capacity. Water/Engineering & Management 132:38-
40, September 1985.

RJN Environmental Associates,  Inc.,  Consulting
Engineers. National Alterative Methodology for Sewer
System  Evaluation.  Washington Suburban  Sanitary
Commission, 1988.

Three Cost Effective I/I Programs. Public Works, January
1983.

Wilson & Company. Implementation of a Comprehensive
Infrastructure Assessment  Program, Case Study:
Pittsburgh, Kansas. Department of Public Works, City of
Pittsburgh, Kansas.

Sewerage Rehabilitation Manual. Water Research Center,
Blagrove, Swindon, Wilshire, 1983.
                                                 37

-------

-------
                                                CHAPTER 4
                                       Sewer System Evaluation
4.1     Introduction
The SewerSystem Evaluation Su rvey (SSES) is the third
phase of an overall sewer system evaluation (See Figure
3-1). The purpose of the SSES is to quantify the amount
of infiltration/inflow (I/I) and rainfall induced infiltration
(Rll) that can be reduced and the cost of such reduction
on a source-by-source and sub-system basis. The SSES
confirms and refines the overall findings of the I/I analysis.
The SSES employsTVinspection, rainfall simulation and
othertechniques to identify specific sources as required
to develop the detailed cost-effectiveness analysis for I/
I.

The findings of the SSES should be sufficiently specific
to describe the corrective actions that need to be taken
along with the amount of infiltration, Rll, and inflow that
will beeliminated from each majorsource, sewer segment
and sub-basin . The SSES must separately define the
cost effectiveness of infiltration removal  and inflow
removal.

Where corrosion is present, the  extent of corrosion
mitigation expected due to I/I  rehabilitation should  be
noted. Specific corrosion potential shou Id also be defined
and recommendations made to reduce this potential to
acceptable  levels. The procedure for conducting a
corrosion survey as a part of an SSES  is presented in
Chapter 5.

The following tasks are usually included in the SSES:1"3

• Survey Planning and Cost Estimating
• Physical Survey
• Rainfall Simulation
• Preparatory Cleaning
• Internal Inspection
• Preparation of Survey  Report  and  Cost Effective
  Analysis
Table 4-1.

Method
Sewer System Testing and Inspection Methods

      Application
Smoke testing
Rainfall simulation (dye
flooding and tracing)
Building plumbing
inspection
Manhole inspection
Flow isolation
TV inspection
                                                          Lateral testing
       Most common routine source detection
       method to identify inflow and Rll sources.

       Source detection after previous lining or
       replacement.

       Used after smoke testing to confirm
       suspected storm drainage connections,
      ' and other inflow and Rll connections.

       As needed after smoke testing to confirm
       suspected inflow sources, such as roof
       leaders and foundation drains.

       Primary source detection to evaluate I/I
       sources and structural condition.

       Inspection performed along with other
       investigation procedures.

       Follow-up source detection after sealing;
       used to verify migration, identify I/I.

       Used where flow monitoring indicates
       high infiltration in large areas.

       Used where smoke testing indicates
       potentially major infiltration sources.

       Primary internal inspection technique for
       SSES, degree of inspection areas for
       pipes as determined by I/I analysis.

       Routine inspection for pipes rehabilitated
       by sealing if interim detection does not
       reveal I/I sources

       Used after grouting and sealing techniques.

       Used to verify smoke testing, flow
       isolation  or when temporary flow
       monitoring indicates excessive I/I.

       Used where smoke testing
       indicates major defects

       Used where building inspection indicates
       major defects.
                                                        39

-------
Table 4-1  describes the most commonly used sewer
system testing and inspection methods.
4.2    Planning the Survey and Use of Sub-
       System Approach

The SSES must be planned and executed to produce
accurate  estimates of flow reduction and estimated
costs. An  overall  block diagram for the conduct of a
preliminary sewer system evaluation plan was presented
in Figure 3-1. Figure 3-2 presented the sequence of steps
for conducting an I/I  analysis. Figure 4-1 presents a
diagram of the methodology to be followed in the conduct
of an SSES. The following sections of this chapter
presents the detailed procedure for an SSES.

The physical survey is performed to isolate the problem
areas and to determine the general physical conditions of
the sewer sections selected for future study. Rainfall
simulation is conducted to locate the rainfall-associated
I/I sources in the sewer lines.

Preparatory cleaning of the sewers is necessary prior to
internal inspection. Internal inspection locates the I/I
sources, the flow rate from each source and the structural
defects in the pipe. Finally, the survey report summarizes
the results obtained during the survey and presents a
cost-effectiveness analysis of the I/I sources which can
be economically corrected.

4.3    Physical Survey

The physical survey of the sewer collection system is
performed  to isolate the obvious problem areas, to
determine the general condition of the sewer sections
selected forfurther study. The following tasks are normally
included in the physical survey:2'3

4.3.1   Aboveground Inspection
This should include  the investigation of the general
conditions of the study area such as topography, streets,
alleys, access to manholes, etc. Potential problem areas,
such as waterways,  river crossings,  natural ponding
areas, should also be located. Key manholes are identified
for additional  flow measurements and  groundwater
monitoring. Manholeaccessproblems.suchaseasement,
access, buried structures, traffic interferences, should
be noted.  The accuracy and completeness of sanitary
sewer maps should be verified. The proximity of storm
and  sanitary sewers, inflow  sources,  such as roof
downspouts, yard and area  drains, creeks, low or
inundated manhole covers and frames, and foundation
drains, etc. are all indications that rainfall simulation tests
in the form of smoke  testing and/or dyed water testing
should be planned. A program for uncovering manholes,
improving and raising frames to above grade should be
planned.

4.3.2  Flow Monitoring
This should include determining  and isolating areas
where I/I  exists. During the I/I analysis, flow monitoring
work would have already been performed in a few
selected manholes. The additional flow monitoring work
performed  during the physical survey is actually a
continued effort to further reduce the number of areas to
be investigated. Flow monitoring should be conducted
during the  highest groundwater conditions to identify
maximum infiltration flow. Monitoring for inflow should be
conducted  during storm  events  under wet weather
conditions. Dry weather and wet weatherflows should be
monitored for comparison. To minimize the effects of
normal wastewater flows, the flow monitoring should be
conducted during the early morning hours. Sub-system
and plant flow monitoring should be conducted on a 24-
hr/d basis.

4.3.3  Flow Measurement
Flow in sanitary sewer systems consists of base flows,
infiltration and  inflow. Separation and quantification of
these components is  the  prime objective  of  flow
monitoring. Flow  measurement in sewer systems  is
undertakentodefinevariationsof certain flow components
with time or to define  peak and/or  minimum  flow
conditions. Sewers should be cleaned thoroughly before
velocity measurements are undertaken.

Many techniques are used for the measurement of flows
in sanitary sewers. The equipment and techniques
selected  will depend upon the resources available, the
degree of precision required, and the physical conditions
within the sewers.

a. Manual Methods
This is the most widely used technique for measurement
of instantaneous  or short term flow.  Generally, the
equipment  is portable and flows can  be determined
immediately using published curves, nomographs or
tables.

Weirs
The weir is a common device for measu ring low wastewater
flows because of its ease of  installation and low cost.
Flow measurements through weirs  are  obtained by
recording the head (water level) above the weircrest and
determining flow rates by calculations, nomographs or
tables. Advantages and disadvantages of weirs are:
Advantages
• Low costs
Disadvantages
•  Fairly high head loss
                                                  40

-------
FlflUM 4-1.
Sower system evaluation flow diagram.
                                                    Assemble SSES Team
                                                       Review I/I Report
                                                      and Results Study
                                               Develop Specific SSES Study Plan

                                 • Develop Project Study Scope, Budget, and Schedule
                                 • Identify Sub-Basins and Analyze to Minimize Migration Effects
                                 - Develop Physical Survey and Inspection Plan Budget
                                 • Develop Cleaning Plan and Budget
                                 - Develop Physical Survey Plan and Budget
                                 • Select Internal Inspection Methodology
                                 • Identify Need for Rainfall Simulation and Additional Flow Monitoring
                                                   Conduct Physical Survey

                                          - Conduct Aboveground Inspections
                                          - Verify Adequacy of I/I Monitoring
                                          - Select Flow Monitoring Equipment
                                          - Conduct Manhole Inspect'ons
                                          - Conduct Rainfall Simulation, If Required
                                          - Conduct Row Monitoring Studies
                                                       Conduct Sewer
                                                      Cleaning Program
                                                  Conduct Internal Inspection

                                               - TV Inspection
                                               - Photographic Inspection
                                               - Physical Inspection (Large Sewer)
                                            Conduct Cost-Effectiveness Analysis of I/I
                                            by Sub-Systems and for Total Study Area

                - Develop Costs for Infiltration as a Function of Infiltration Removed
                - Array Costs and Develop Cumulative Cost vs. Infiltration Removed Curve
                - Develop Cost for Transportation and Treatment
                • Develop Total Cumulative Rehabilitation, Transport, and Treatment Costs and Choose Optimum Point
                - Develop Costs for Inflow as a Function of Inflow Removed
                - Array Costs and Develop Cumulative Cost vs. Inflow Removed Curve
                - Develop Cost for Transport and Treatment
                - Develop Total Cumulative Rehabilitation Plus Transport and Treatment Cost and Choose Optimum Point
                                                 Summarize All Recommended
                                                    Rehabilitation Activities
                                                              41

-------
  Easy to install
  Easy to obtain flow by
  standard equations,
  nomographs, etc.
  Direct flow reading
  Many designs available
  for flexibility
  Generally accurate
                           Must be periodically
                           cleaned; must be suitable
                           for channels carrying
                           excessive solids
                           Accuracy affected by
                           excessive flows and
                           debris
                           May be difficult to make
                           accurate manual
                           measurements in
                           sewers because of
                           limited access
                           Cannot be used in
                           sewers flowing full
Additional information on the measurements of flow
through weirs is provided in the report Existing Sewer
System Evaluation and Rehabilitation.3

Flurries
Flumes operate on the Venturi principal. In flumes, the
constriction of the throat causes the flow to have a critical
depth. This is followed by a hydraulic jump if the slope
allows subcritical (low velocity) flow. There are several
types of open channel flumes, including the Parshall,
Palmer-Bowles, H-FlumeandTrapezoidalconfigu rations.
Flumes are  capable of providing results accurate to
within 3-5 percent. Advantages and disadvantages of
flow measurements by flumes are as follows:
                          Disadvantages
                          • High cost
                          • May be difficult to install
Advantages
• Self-cleaning to a
  certain degree
• Relatively low head loss
• Accuracy less affected by
  approach velocity than it
  is with weirs
• Data easily converted to
  flow using tables or
  nomographs
Manual Depth Measurement
An instantaneous flow measurement in sewers can be
obtained by the following formula: Q=AV, where Q is the
volumetric flow rate, V is the mean velocity of flow, and
A is the cross-sectional area of the pipe. The mean
velocity of flow must be measured or obtained theoretically
through the Kutter's formula:

                V=1.486R2/3S1/2/N

Where,

  N = Mannings Coefficient
  R = Hydraulic Radius, ft
  S = Slope, ft/ft

Staff gauges marked to the nearest 3 mm (1/8-in) are
used to measure depth. In manholes that are relatively
clean and accessible, the staff gauge may be inserted
into the invert of the manhole channel and the depth of
flow measured. The depth of sediment in the pipe should
be noted and the depth of flow corrected accordingly.
Advantages and disadvantages of this technique are as
follows:

Advantages                Disadvantages
• Inexpensive             • Instantaneous result
                           that may not be
                           representative
                         • Determination of mean
                           velocity is critical
                         • Cannot be used in
                           surcharged sewers
                         • Low degree of accuracy
Timed Volume
This method is used to determine flow rates from leaking
manhole walls, wetwell walls and accessible point sources
of inflow. The method involves the use  of a vessel of
known volu me; the time to fill this vessel is measured with
a stop watch or a watch. Equipment required for flow
measurement by thistechnique includes plasticcontainers
or 208-L (55-gal) drums, depending on the amount of
flow. A stop watch or a watch with a sweep second hand
is suitable  for measuring time.  Advantages and
disadvantages to this method are:
                                                      Rapid results

                                                      Ease of operation
Advantages
• Accurate
                                                      Inexpensive

                                                      No specific expertise
                                                      required
Disadvantages
• Generally cannot be used
  for flow in any but the
  smallest sewer pipes
• Not adequate for high
  velocity flows
                                                    Dye-Dilution Method
                                                    This technique is a simple, potentially accurate, and
                                                    quick method for the determination of flows in sanitary
                                                    sewers. The method is based on  measuring the
                                                    concentration of dye in a waste stream into which has
                                                    been added aknown concentration of dye, then calculating
                                                    the flow. Flows can be measured under partial or full flow
                                                    conditions without entering manholes. This method is
                                                    employed  to obtain instantaneous flow rates but with
                                                    added equipment it can be used to monitor flow on a
                                                    continuous basis. Advantages and disadvantages to this
                                                    method are:
                                                   42

-------
Advantages
• No entering of manholes
  Saves time and provides
  instantaneous flow data
  on many sewer sections
  Independent of sewer
  sfte.dimensions, velocity
  and surcharging
Disadvantages
• Samples must be
  analyzed as soon as
  possible (most dyes
  decay in sunlight).
• Temperature correction
  may be required
• Instrumentation is
  expensive
• Dye is expensive
• Need at least 100
  sewer diameters for dye
  mixing before sampling.
Three watersolublefluorescenttracerdyes are extensively
used: Rhodamine B, Rhodamine WT, and Fluorescein.
For accurate flow measurements in sewers, a dye which
has a  low sorptive tendency with the solids in the
wastewater should always be used. The fluorescence of
the Rhodamine dyes is not suitable outside of the pH of
5-10. Since the fluorescence of the dye is also affected
by temperature, a correction factor should be applied to
the measured concentrations if the temperature of the
sample is different than the room temperature.

Commercial solution feeders are available forfeeding the
dye at a constant rate to the manhole. Collection of the
samples at the downstream manholes can be achieved
by lowering a container with  a rope attached to the
sampler. To minimize the loss of dye due to absorption,
the sample container should be made of high quality
glass or other similar material. The samples should be
allowed to stand to reach room temperature and to settle
the suspended solids before measurements are taken

b. Automatic Flow Measurement
Automatic flowmeters can continuously monitor flows
with a minimum of labor. Data collected can be displayed,
recorded on charts, sorted on magnetic tapes or solid
stale memory, or even transmitted from the field to the
office  by telephone or radio. These  meters save
considerable time  and effort  compared  to manually
recorded flow data, but proper installation, calibration,
and  maintenance require  individuals with  a basic
knowledge of hydraulics  and  proper  maintenance
procedures for the meter  in  use.  Following  are the
capabilities of various automatic meters:

Depth Measurement
Depth recorders  are used to measure liquid levels in a
pipe, head over a weir, depth in  a flume,  or other
applications. Commonly used  equipment for recording
liquid depths includes probes, bubbler, pressu re sensors,
floats, ultrasonic devices and capacitance/electronic
probes.
Velocity Measurements
Automatic flow monitors that use velocity measurements
can provide accurate data even under highly fluctuating
liquid levels. Velocity may be automatically  recorded
using ultrasonic doppler methods, magnetic methods,
mechanical current meters, or other methods. In most
cases the depth of flow is recorded along with the velocity
in order to utilize the flow equation Q = AV.

Electromagnetic/Doppler meters
Velocity measurements by these methods are usually
taken by connecting the probe to the outside of the pipe
to be monitored. This is generally used for pipes flowing
full and  having sufficient suspended  solids to be
transmitted back to the receiver. The advantage to this
type of flow measurement is the ability to record flows in
closed pipes without obstructing the fluid flows.

Orifice/Nozzle/and Venturi meters
These types of flow meters are used for measuring flows
in completely full pipes. The basic concept is to form a
constriction in the flow so that the velocity increases and
the pressure decreases. The constriction provides an
opportunity for solids to accumulate,,

4.3.4  Manhole and Sewer Inspection
This task is required to determine the actual condition of
the sewer system. Inspection should include descending
and  examining conditions of manholes and lamping of
sewer lines to ascertain sub-system I/I conditions. Each
manhole should be numbered and its physical condition
noted in log sheets and standardized field forms. Safety
precautions should be taken at all times before entering
the manholes and proper NIOSH-OSHA procedures and
references should be consulted. Sewer inspection should
be carried out and identified on the manholes numbered.
An inventory of the length, size, type, depth and the
general conditions of the sewer pipes provides a basis for
the estimation of the amount of work required for the
preparatory cleaning and internal inspection. Depth of
flow in sewers provides a rough indication'of the capacity
of the sewer pipe and whether or not I/I is present in the
sewer section. Temperature can also be used as an
indicator for the detection of extraneous water entering
the sewer section being investigated since temperature
nearthe point of entry for extraneous waters will be lower
than the average temperature in the sewer lines, if the
extraneous source represents a significant portion of the
total flow. AH the observations made during the manhole
and sewer pipe inspection should be recorded in field log
sheets and correlated with the sewer maps. Figure 4-2
indicates the typical defects found during  manhole
                                                  43

-------
Figure 4-2.
Typical manhole defects.
                                                                Broken/Cracked Cover
                                                                Broken/Cracked Frame
                                                                Deteriorated Frame Seal
                                                                Deteriorated Frame Adjustment
                                                                 Defective Cone (Corbel)
                                                                Defective Wall
                                                                 Steps
                                                                Deteriorated Trough (Invert)
                                                               Deteriorated Pipe Seal
                                                               Deteriorated Bench
                                               44

-------
        Quick mathod of Inspecting sawar HIM*.
Magnified Night Scope
                                                                                       Adjustable Polished
                                                                                          Stool Mirror
                                                                              Remote Halogen Light
                                                45

-------
inspection and Figure 4-3 indicates a quick method of
inspecting sewer lines without entering the manholes.

4.3.5  Rainfall Simulation
This task involves the identification of the sections of
sewers that exhibit I/I conditions during rainfall events.
Rainfall simulation  does not have to be performed in
every SSES. A careful study of the  sewer maps and
review of the I/I analysis report, smoke test results and
the physical  survey results indicate whether rainfall
simulation is required.

4.3.6  Smoke Testing
This is an inexpensive and  quick method of detecting
inflow sources in sewer systems. Many inflow sources
such as  roof leaders, cellar, yard, and  area drains;
foundation drains;  abandoned  building sewers; faulty
connections; illegal  connections;  sewer cross
connections, structural damages and leaking joints can
be identified by smoke testing  under ideal conditions.
Key steps for smoke testing are:

• Conduct smoke tests in selected  sanitary  lines
  (adequate notification r^st be made before smoke
  testing is done. This requires notification to residents,
  the local fire department, public meetings, etc.)
• Record, both in  written and  photographic form,  all
  sources from which smoke emissions are noted.
• Visually inspect manholes suspected of having direct
  inflow connections into sanitary sewers.
• Identify direct inflow connections to sanitary sewers.
• Identify interconnections between sanitary and storm
  systems as evidenced by smoke emissions during the
  smoke test.

Smoke testing should not be conducted on sewer lines
which contain sags, or are flowing full. Smoke testing
cannot detect structural damage, or leaking joints in
buried sewers and service connections when the soils
surrounding and above the pipes are saturated, frozen or
snow covered. Smoke testing should not be performed
on windy days when the smoke coming out of the ground
may be blown away so quickly as  to escape visual
detection. The following equipment is usually required to
conduct smoke testing:

• Smoke bombs
• Air blowers
• Camera and film
• Sand bags and/or plugs
• Two-way radios

The smoke bombs used should be non-toxic, odorless
and non-staining. An air blower is used to force the
smoke into the sewer pipes. The camera is used to take
pictures of the smoke coming out of the ground, catch
basins, pipes and other sources during the test. Sand
bags and/or plugs are used to block the sewer sections
to prevent the smoke from escaping through the manholes
and adjacent sewer pipes. It is important to coordinate
with the fire department to prevent false alarm if for some
reason the smoke would enter a house and would trigger
a false alarm.

4.3.7   Dyed Water Testing
Dyed-water testing is used primarily to detect infiltration
and Rll sources in storm sewer sections, stream sections,
and ditch sections. It can also be used to verify the results
of smoke testing. This method of testing is more expensive
and time consuming than smoke testing and requires
large quantities of water.

Fluorescent dyes are used for this testing technique. The
dyes should be safe to handle, biodegradable and inert
to the soil and debris in sewers. Further information on
the common types of dyes can be obtained from Reference
5.

The procedure for dyed  water testing includes:

• Plug and flood with  dyed water any storm sewer
  sections which are parallel to or cross sanitary sewers
  and house service lines which have shown evidence of
  smoke when nearby sections have been smoketested.
• Where applicable, flood  catch basins,  ditches and
  ponding areas  in close proximity to sanitary sewers
  with dyed water.
• The presence of dye or absence in adjacent downstream
  manhole indicates the infiltration potential.
• The response time of the appearance of the dye and in
  some cases the visual  increase  in flow  provides
  additional insight into the infiltration or Rll pathway.
• Analyze findings and recommend appropriate sewer
  sections for cleaning and internal inspection.

4.3.8   Water Flooding Test
This test is similar to dyed water testing, except that no
dyes are used. With accurate flow measurement, pipe
imperfections can be detected with this technique. The
water flooding tests can be conducted by the following
methods:

• Sprinkler test - Inflow and/or Rll under unpaved areas,
  particularly in service connections during wet weather
  conditions, can be determined by the sprinkler test.
  Irrigation sprinkler pipes with spray nozzles are used to
  simulate rainfall conditions, and the rate of application
  of the waterandthetotalwaterdistributed are monitored.
• Exfiltration test - The exfiftration test is used to check
  the sewer lines and manholes for possible leakage.
                                                   46

-------
  The procedures involved in the exfiltration test are
  covered in Chapter 3.

4.4   Cleaning

Internal inspection of lines suspected of having I/I sources
and any flow velocity measurement requires clean pipes.
Debris in sewer inverts, grease accumulation and heavy
root infestations notonly obstruct visual orvideo inspection
but they also may hide or mask actual infiltration sources.
Preparatory cleaning is an essential first step in any
meaningful internal examination procedure. Thecleaning
procedure should clean the sludge, mud, sand, gravel,
rocks, bricks, grease and roots from the sewer pipes,
manholes and pumping station wet wells to be inspected.
The pipe walls should be clean .enough for the camera
used in the inspection  to discover structural defects,
misalignment and I/I sources. The .following steps are
required for cleaning:

• Clean all sewer lines by appropriate means and with
  proper  equipment immediately  prior to  internal
  inspection or velocity measurement.
• Determine, if possible, allobstructionsorotherphysical
  alignment, joint or connection conditions which could
  interfere with or prevent the insertion and movement of
  inspection equipment.

The equipment required for cleaning includes:2'3

• Rodding machines, bucket machines, high-velocity
  water machines  and other hydraulically propelled
  devices
• Debris removal equipment, such as vacuum machines
  and trash pumps
• Debris transport vehicles
• A proper debris disposal site

Forpropercleaning, factorsto be considered are: access
and condition of manholes, depth of sewer, size of pipe,
depth and type of solid materials to be removed, degree
of root intrusion, amount of flow,  structural integrity of
pipe, availability of hydrant water and the degree of
cleanliness required.  Figure 4-4 indicates some
techniques involved in preparatory cleaning. Direct
observation and camera are the usual forms of internal
inspection equipment used for  sewer  lines. Direct
observation is used for large lines that can be walked or
crawled, while cameras are used  on  small-diameter
sewers.

4.5   internal Inspection

Internal inspection involves the following tasks:3-4
• Set up TV camera or other equipment in the sewer lines
  under investigation.
• Plug and flood all storm sewers in close proximity to
  sanitary sewers under inspection, if recommended by
  rainfall simulation findings.
• Internally inspect, designate footage, and  note all
  structural defects and all leaks in terms of location and
  flow rates.
• If services are found to be running, verify whether the
  flow is caused by infiltration or actual water usage.
• Record findings on log sheets and support with video
  tapes.

Internal inspections can be accomplished in the following
ways:3-4

4.5.1  TV Inspection
The TV inspection technique utilizes a closed-circuit TV
camera to observe the conditions in the sewer lines. The
TV cameras used are specially designed to detect the
sewer conditions.

The camera is mounted in a casing and is pulled through
the sewer with cables. Recently self propelled cameras
have been used, but the  disadvantage of this type of
camera is required service and recovery if they fail or get
stuck in the middle of the pipe run. The results are shown
on the TV monitor and documentation can be made by a
videotape or  by photographs of  the monitor. A light
source isprovidedby the camera for illumination purposes.

4.5.2  Photographic Inspection
This technique utilizes a camera to take a series of color
photographs  along the inside of sewer lines. This
technique is best for analyzing the structural conditions
of the sewers. A camera is pulled through the sewer line
being inspected. Pictures are taken at equidistant intervals
or at some predetermined problem sections.

4.5.3  Physical Inspection
This technique involves the direct inspection of  larger
sewers not in service. Before inspectiion, the safety of the
person entering the line should be carefully considered
and the sewer section thoroughly ventilated to remove
H2S and other harmful gases that might be present.

Proper NIOSH-OSHA safety practices and procedures
should be  followed to properly carry out  physical
inspections.

Figure 4-5 shows the technique involved in TV inspection.

4.6    Cost Effectiveness Analysis
                                                   47

-------
Figure 4-4.
Preparatory cleaning.
                                                                   48

-------
Figure 4-5.        Internal color TV Inspection.
                                                                  49

-------
Based on the results and findings of the SSES, a detailed
evaluation and analysis should be carried out to determine
the most cost-effective means of correcting or alleviating
excessive I/I conditions found in the system.

Cost-effectiveness analysis for SSES is similar to the
cost-effectiveness analyses for I/I. However, the SSES
cost-effectiveness analysis provides a detailed and
thorough analysis of the sewer system including the flow
rates from each source, and the best method for
rehabilitation of each  source. For an  effective  cost
analysis, the cost of correction for infiltration, inflow, Rll
and groundwater migration must be considered. Existing
SSES methodologies rely on individual line segment
nighttime isolation  and measurements  to identify
excessive infiltration.

Subarea SSES analysis including migration effects is an
Improved approach to the traditional  point source
approach for evaluating sewer systems. (See Section
4.7 for a description  of the subarea approach  to
rehabilitation). Row adjustments for infiltration should be
carried out  before the cost-effectiveness  analysis is
conducted.2

Costs for the evaluation survey should be based on the
total  actual expenditure for the  survey. Costs for
rehabilitation should be based on the actual physical
conditions discovered. The costs for transportation and
treatment of wastewater shouId then be developed for at
least four typical flow conditions so that a cost curve can
be drawn to indicate the general cost pattern.3

Acost summary similarto that shown in Table 4-2 can be
prepared to summarize  the overall cost of a sewer
system evaluation and  rehabilitation  program. The
presentation of the costs for Infiltration and  Inflow must
beseparatelydevetoped.Thegeneralproceduresoutlined
below should be followed to develop both Infiltration and
Inflow costs in a format forthe cost effectiveness analysis
curve preparation:

• Determine the total correction cost for each Infiltration
  and Inflow source and calculate the cost required for
  eliminating each unit of flow.
• Arrange the costs  in a descending order with lower
  costs ahead of the higher costs.
• Arrange the costs in  groups  and  determine the total
  correction cost for each group. Add costs for engineering
  services, administrative  costs, contingency costs,
  interest during construction, etc. to derive the total
  required cost to eliminate the I/I from all sources within
  each group.
• Calculate  the total accumulative cost (Curve B of
  Rgures 4-6  and 4-7) against the total accumulative
  infiltration and inflow separately to be reduced and
  draw a curve passing through all data points. Plot a
  curve showing the relationship between the cost of
  transportation and treatment and the total infiltration
  and inflow (separate) to be reduced (Curve A). Derive
  a composite cost curve (Curve C) by adding the costs
  of each of the two derived curves' (curves A and B).  •
  Locatethe minimumcost point on the composite curve,
  and draw a straight line passing this point and parallel
  to the cost axis. The line intercepts the cost curve for
  infiltration and rehabilitation (Figure 4-6) and inflow
  rehabilitation (Figure 4-7) at a point which represents
  the optimal point for sewer rehabilitation. The flow
  figure corresponding to these points on each curve
  represents the infiltration or inflow which can be cost-
  effectively removed from the sewer system, and the
  cost figure corresponding to this represents the total
  cost which will be needed for the corrective actions.

4.7    Case Study Example  and Detailed
       Method  of  Analysis

This section outlines a detailed method of analysis for
SSES taking into account migration and rainfall-induced-
infiltration. This detailed analysis was performed by the
WSSC to develop a  new approach to sewer system
evaluation  and rehabilitation known  as the System
Approach to evaluate Subarea Rehabilitation (SASR).4
The subarea approach represents a large area (6,000-
30,000 lineal m [20,000-100,000 lineal ft] of sewer)
undergoing a sewer system evaluation survey as opposed
to the traditional method of evaluating smaller segments
and single sources. Field activities incorporated in this
study included the following:

Rainfall Monitoring - Monitoring was conducted by four
continuous recording gauges to measure precipitation to
1/100th of an inch versus time, to allow for correlation of
inflow to rainfall intensity.

Continuous Flow Monitoring - This was performed at
each subarea outlet utilizing flow meters to record depth
and velocity.

Internal  Night-Time Flow Measurements - Flow
measurements conducted within each subarea to identify
mini-systems subject to infiltration.

Manhole and Visual Pipe Inspections - Inspection for
each manhole began at the surface by identifying potential
for ponding and concluded with evaluation of the condition
of the bench and trough, and  lamping of connecting
pipes.
                                                   50

-------
Table 4-2.        Cost Summary for SSES and Sewer Rehabilitation1


                                                Est. Quantity                           Estimated Cost
Description                                    Quantity         Unit                   $/Unit           Total


SEWER SYSTEM EVALUATION SURVEY
1.   PHYSICAL SURVEY
    Above Ground Inspection                      	         manhour                	         	
    Flow Monitoring                             	         manhour                	         	
    Manhole and sewer inspection                   	         ft(m)                  	         	
    Subtotal
2.   RAINFALL SIMULATION
    Smoke Testing                              	         ft (m)
    Dyed Water Testing                          	         ft(m)
    Water Flooding Tests                         	         ft (m)
    Subtotal

3.   PHYSICAL SURVEY REPORT                  	         manhour
4.   PREPARATORY CLEANING                .   	         ft(m)
5.   INTERNAL INSPECTION                      	         ft(m)
6.   ENGINEERING                             	         manhour
7.   OTHERS                                  	

TOTAL SSES COSTS
SEWER SYSTEM REHABILITATION
• CORRECTION FOR INFILTRATION
1.   SEWER EXCAVATE AND REPLACE             	         ft(m)
2.   CHEMICAL GROUTING                       	         ft (m) Lump
3.   SLIPLINING OR INSERTION                   	         ft(m)
4.   CURED-IN-PLACE INVERSION LINING           	         ft(m)
5.   SPECIALTY CONCRETE                      	         ft (m) or Lump
6.   LINERS                                  	         ft (m) or Lump
7.   COATINGS                                	         ft (m) or Lump
8.   MANHOLE WET WELL REPLACEMENT          	         Lump
9.   MANHOLE WET WELL REPAIR                 	         Lump
10.  FAULTY TAPS REPAIR                       	         Lump
11.  HOUSE SERVICE PIPE REPLACEMENT          	         ft (m) or Lump
12.  HOUSE SERVICE PIPE REPAIR                 	         ft (m) or Lump

• CORRECTION FOR INFLOW
1.   LOW LYING MANHOLE RAISING                	         Lump
2.   MANHOLE COVER REPLACEMENT             	         Lump
3.   CROSS CONNECTION PLUGGING              	         Lump
4.   ROOF LEADER DRAIN DISCONNECTION         	         Lump
5.   FOUNDATION DRAIN DISCONNECTION          	         Lump
6.   CELLAR DRAIN DISCONNECTION              	         Lump
7.   YARD DRAIN  DISCONNECTION                	         Lump
8.   AREA DRAIN  DISCONNECTION                 	         Lump
9.   COOLING WATER DISCHARGE
    DISCONNECTION                          	         Lump
10.  DRAINS FROM SPRINGS AND SWAMPY
    AREAS TO BE PLUGGED                     	         Lump

BOTHERS
1.   ENGINEERING SERVICES                    	         Lump or Manhours
2.   LEGAL AND ADMINISTRATIVE SERVICES         	         Lump
3.   CONTINGENCY                            	         Percent
4.   INTEREST DURING CONSTRUCTION            	         Percent
5.   SALVAGE VALUE                           	         Lump

TOTAL REHABILITATION COST
                                                    51

-------
Figure 4-C.
Cost-effectiveness analysis curve for Inflltralon.
                                          i Composite Cost Curve
                                            Infiltration Reduction
                                                (Curve C)
                                      Cost Curve for Transportation
                                       and Treatment of Infiltration
                                               (Curve A)
                                                                   Optimal Cost/Bnefit Level for
                                                                  Infiltration Sewer Rehabilitation
                                                                            (Curve C)
               Cost Curve for
            Infiltration Rehabilitation
                  (Curve B)
                                                            Infiltration Reduced, gpd
                                                                 52

-------
Rgura 4-7.
Cost-«H»ctIven«ss analysis curve for Inflow.
                                          Composite Cost Curve
                                             Inflow Reduction
                                                (Curve C)
                                      Cost Curve for Transportation
                                         and Treatment of Inflow
                                              (Curve A)
     UJ
     S
                                                                  Optimal Cost/Bnefit Level for
                                                                   Inflow Sewer Rehabilitation
                                                                          (Curve C)
                Cost Curve for
              Inflow Rehabilitation
                  (Curve B)
                                                            Inflow Reduced, gpd
                                                               53

-------
Smoke Testing - Performed with an intensive technique
requiring isolation of each segment by blocking flow and
injecting smoke using blowers, one on each of two
adjacent manholes.

Dyed Water Flooding - Inflow sources identified during
smoke testing were quantified by the dyed water flooding
technique.

TV Inspection  - As a result of nighttime  flow
measurements, certain sewers were identified for TV
inspection.

Building  Inspections - This consisted primarily of
determining inflow connections to the service laterals,
such as storm and combination sump pumps, and external
drains such as areaway and roof drains.

The total of the assigned flows from all of the identified
inflow sources was then compared to and balanced with
the measured flow of each subarea at a 1 -yr storm event.
Inflow at a 1 year storm event was determined by linear
regression of moderate storms, when the system was
not in a' hydraulscally  restricted or surcharged state.
Infiltration sources were quantified and monitored at the
outlet flow meters. Quantification of inflow and infiltration
obtained during the subarea evaluation is presented in
Table 4-3.

A cost-effectiveness analysis'for the WSSC example
was performed on a subarea basis incorporating the
effects of migration, capital cost of treatment, O&M cost
fortreatment, cost of relief lines, and cost of rehabilitation.
As a result of the analysis, clustered rehabilitation was
recommended by subarea. This type of rehabilitation
minimizes the migration effect. Also, the effectiveness of
rehabilitation can be measured  more rapidly because
flow reduction is concentrated instead of dispersed over
a wide area. I/I rehabilitation was then recommended for
the entire subarea

A summary of the cost effective analysis for the subarea
is presented in Table 4-4. Anticipated flow reductions
after implementation of the recommended rehabilitation
provides the estimated unit construction cost ($/gpd).
Finally, a comparison of point-source rehabilitation with
the sub-system approach was performed for each method
and is presented in Table 4-5.

The point-source analysis initially  resulted in  a unit
rehabilitation  cost of $0.25/L/cl ($0.95/gpd), but by
incorporating  the effect of migration, less infiltration
would actually be removed, thus resulting in an actual
                                                    54

-------
Table 4-3.         Quantificationof 1/IThroughtheSubareaSystem
                 Approach for the  Washington Suburban
                 Sanitary Commission4 (Reprinted  with
                 Permission from Water Engineering  and
                 Management
                                                            Table 4-4.         Cost-Effective Analysis for I/I Reduction for the
                                                                             Washington Suburban Sanitary Commission4
                                                                             (Reprinted with Permission from Water
                                                                             Engineering and Management}
Source
INFLOW
Public Sector Inflow
Manhole Defects
Cover/rim leaks, ponding(1)
Frame seals
Corbels and broken frames
Cross connections
Subtotal
Private Sector Inflow
Downspouts
Area-wide drains
Foundation drain connection
Flow {mgd) Percent of Total


(
0.020 0.8
0.261 10.1
0.078 3.0
0.026 1.0
0.385 14.9

0.288 11.2
0.539 20.9
0.011 0.4
Suspect foundation drain connection 0.773 30.0
Defective lateral dean outs
Suspect defective service laterals
Storm sump pump connection
Subtotal
Total
0.009 0.3
0.364 14.0
0.212 fiJ2
2.196 85.1
2.581 100.0
                                                            SUMMARY OF RECOMMENDED PLAN
INFILTRATION
Manhole Defects
Cracked/defective walls
Defective pipe seals
Bench/trough leaks
Pipe Defects
Groutable defective joints/pipes
Non-groutable defective pipes
and groutable service connection
Infiltration in line segments and
manholes not inspected
Total

0.039
0.024
0.004

0.387
0.34
0.137
0.932

4.2
2.6
0.4

41.5
36.6
JfLZ
100.0
Estimated
Rehabilitation Item Quantity
Inflow
Manhole cover/frame replacement
Manhole frame seals/raising
Manholes corbel
Cross-connection
Subtotal
Infiltration
Manhole walls, pipe seals, bench/trough
Relining/replacement
Line grouting
Pipe replacement
Connection grouting, lateral repair
Subtotal

38
121
16
1


22
20
27
7
25

Estimated
Construction
Cost, $(1986)

17.710
96,800
9,900
4.000
127.800

14,996
386.015
20,082
35.000
45.000
501.091
                                                            Total
                                                            ESTIMATED FLOW REDUCTION
                                                            Source Type
                                                                                     Estimated
                                                                                   Flow Reduction,
                                                                                     mgd (1986)
                                                                                                            628,891
       Estimated
  Construction Cost,
      $/gpd (1986)
                                                            Inflow
                                                            Infiltration
                                                                                        0.385
                                                                                        0.297
         $0.33
         $1.69
                                                            Table 4-5.         Cost-Effective Analysis by Point Source for I/I
                                                                             Reduction for the Washington Suburban
                                                                             Sanitary Commission4 (Reprinted with
                                                                             Permission from Water Engineering and
                                                                             Management)
                                                            Approach
                                                                                      Removable
                                                                                   Infiltration, mgd
 Rehabilitation Costs
Total $      $/gpd
                                                            Point Source Approach
                                                              Assumed without migration     0.164     $156,000     0.95
                                                              Estimated, with migration      0.081     $156,000     1.93
                                                            Sub System Approach          0.143     $238,000     1.66
                                                          55

-------
unit rehabilitation cost of $0.51/L/d ($1.93/gpd). I/I cost
effective analysis utilizing the subarea approach,was
found to be $0.44/L/d ($1.66/gpd).4

4.8    References

When an NTIS number is cited in a reference, that
reference is available from:

       National Technical Information Service
       5285 Port Royal Road
       Springfield, VA 22161
       (703) 487-4650

1.  Handbook for Sewer System  Evaluation and
    Rehabilitation. EPA/430/9-75-021, Office of Water
    Program Operations, U.S. Environmental Protection
    Agency, Washington, D.C., 1975.

2.  American Public Works Association. Sewer System
    Evaluation, Rehabilitation and New Construction: A
    Manual of Practice.  EPA/600/2-77/017d, NTIS No.
    PB-279248. U.S. Environmental Protection Agency,
    Municpal Environmental Research Laboratory, Office
    of Research and Development, Cincinnati,  Ohio,
    1977.

3.  Existing Sewer System Evaluation and Rehabilitation.
    ASCEManualsand Reportson Engineering Practice
    62, WPCF Manual of Practice FD-6, American Society
    of Civil Engineer, Water Pollution Control Federation,
    1983.

4.  Fernandez, R.B. Sewer Rehab Using a NewSubarea
    Method. Water/Engineering & Management 133-28-
    30, February 1986.

5.  Odor and Corrosion Control in Sanitary Sewerage
    System and Treatment Plants. EPA/625/1-85/018,
    U.S. Environmental Protection Agency, Cincinnati,
    Ohio, 1985.

6.  American Consulting Services, Inc. Sewer System
    Evaluation for Infiltration/Inflow. Technology Transfer
    Program, U.S. Environmental Protection Agency.
Additional Reading

American Public Works Association. Control of Infiltration
and Inflow into Sewer Systems. 11022 EFF12/70, Water
Quality Office,  Environmental ProUjction Agency and
Thirty-nine Local Governmental Jurisdictions, 1970.

American  Public Works Association. Excerpts  from
Control of Infiltration and Inflow into Sewer Systems and
Prevention and Correction of Excessive Infiltration and
Inflow into Sewer Systems. EPA/S70/9-74-004, Water
Quality Office, Environmental Protection Agency & Thirty-
nine Local Governmental Jurisdictions, 1971.

American  Public Works Association. Prevention and
Correction of Excessive Infiltration and Inflow into Sewer
Systems. NTIS No.  PB-203208, Manual of Practice,
Water Quality Office, Environmental Protection Agency
& Thirty-nine Local Governmental Jurisdictions, 1971.

Braam, G.A. and R.J.  Nogaj. Selection of Optimum
Storm Frequency for Sewer Studies. JWPCF 54:1401-
1407, October 1982.

Carter, W.C., A.J. Hollenbeck,  and R.J. Nogaj.  Cost
Effectiveness and Sewer Rehabilitation. Public Works
117:64-67, October 1986.

Connelly, Conklin, Phipps & Buzzell, Inc.  Evaluation of
Infiltration/Inflow Program Final Report. EPA-68-01 -4913,
Officeof Water Program Operations, U.S. Environmental
Protection Agency, 1980.

Construction Grants 1985. EPA/430/9-84-004, Office of
Water, U.S. Environmental Protection Agency, 1984.

Cronberg,A.T.,J.P.Morriss,andT.Price. Determination
of Pipe Loss Due to Hydrogen Sulfide Attack on Concrete
Pipes.

Darnell, P.E. Conducting Sewer System Evaluations for
Small Systems. Water & Sewage Worksxi23:67\8-71,
November 1976.

Deciding to  Rehabilitate, Repair, or Replace. Water/
Engineering & Management 132:50-53, May 1985.

Driver, F.T. Manhole I/I Stopped with Special Repairs.
Water/Engineering & Management 130-31 -32, April 1983.

Edward H. Richardson  Associates, Inc. Evaluation of
Trenchless Sewer Construction at South Bethany Beach,
Delaware. EPA/600/2-78/022, NTIS  No. PB-278776.
U.S. Environmental  Protection Agency,  Municipal
                                                  56

-------
Environmental Research Laboratory, Off ice of Research
and Development, Cincinnati, Ohio, 1978.

Evaluating Utility System Conditions. Water/Engineering
& Management 132:43-49, May 1985.

Gray, W.R. and R.J. Nogaj. Sanitary Sewer Bypass
Reduction Program. Water/Engineering & Management
137:36-40, May 1990.,

Gutierrez, A.F.  and J.H. Rowell. Five Years of Sewer
System Evaluation. Journal of  the  Environmental
Engineering Division, December 1979.

Heinecke, T.L. and C.H. Steketee. The Key to Effective
I/I Control. Public Works 115:88-92,106-107, June 1984.

Hersch, P. Philadelphia Formulates a Comprehensive
Main Rehab Program. Water/Engineering & Management
132:61-66, May 1985.

Hollenbeck, A.J. Designing for Removal of Sanitary
Sewer Cross  Connections. Water/Engineering  &
Management 131:29-31, April 1984.

Hollenbeck, A.J. and M.J. Jankovfc. Smoke Testing: It's
Not Always as Easy as It Seems. American City and
County Magazine, February 1982.

Hollenbeck, A.J. and  G.D. Lambert.  New Approach
Achieves Inflow Reduction in Sanitary Sewers. Public
Works 118(9):119-121,  September 1987.

Hollenbeck, A.J. and R.J. Nogaj. Inflow Distribution in
Wastewater Collection  Systems. Water/Engineering &
Management 129:30-33, January 1983.

Hollenbeck, A.J. and R.J. Nogaj. One Technique for
Estimating Inflow with Surcharge Conditions. JWPCF
53:491-496, April 1981.

Infiltration Inflow  Collection System Management:
Challenge of the 80's. I/I  Evaluation and Control Division,
Department of Maintenance and Operations, Washington
Suburban Sanitary Commission, Hyattsville, MD, 1982.

Infrastructure in the Commonwealth. Department of Local
Government, Frankfort, KY, 1989.

J.M. Smith & Assoc. Analysis of Acceptable Ranges for
Infiltration and Inflow  Reduction in Sewer System
Rehabilitation Projects. Study conducted under contract
EPA 68-01-6737,  Performance Assurance 'Branch,
Municipal Facilities Division, Off ice of Municipal Pollution
Control,  U.S. Environmental Protection Agency,
Washington, D.C.

Johnson, W.D., S.R. Maney, and G. McCluskey. Open
Cut Sewer Construction Across Railroad Tracks Saves
Money. Public Works 120:73, June 1989.

Lipman,  S.G. Metropolitan District Commission, I/I
Experience. Presented at Technology Transfer Seminar
on New Concepts in I/I Evaluation and Sewer System
Rehabilitation, U.S. Environmental Protection Agency,
Cincinnati, Ohio, March 1984.

Mayer, J.K., F.W. Macdonald and S.E. Steimle. Sewer
Bedding and Infiltration, Gulf Coast Area. 11022 DEI 05/
72, Office of Research and Monitoring, Environmental
Protection Agency, 1972.

Milwaukee Metropolitan Sewerage District Cost-
Effectiveness Analysis.

Montgomery County Sanitary Department. Determination
of Ground  Water Infiltration and Internal Sealing of
Sanitary Sewers. Water Quality Office, Environmental
Protection Agency, 1971.

Montgomery County Sanitary Department. Ground Water
Infiltration and Internal Sealing of Sanitary Sewers. Water
Pollution Control Research Series, U.S. Environmental
Protection Agency, 1972.

National Water Well Association, RJN Environmental
Associates, Inc.,  and Washington Suburban Sanitary
Commission. Impact of Groundwater Migration on
Rehabilitation of Sanitary Sewers, 1984.

Nelson, R.E. New Ways to Fix Leaky Sewers. American
City & County Magazine 95:39,40,42, September 1980.

One Way to Handle Lateral Connections. American City
& County Magazine.

RJN Environmental Associates, Inc. Making Effective
Use of Existing Collection Capacity. Water/Engineering
& Management 132:38-40, September 1985.

RJN Environmental Associates, Inc. National Alternative
Methodology for Sewer System Evaluation. Washington
Suburban Sanitary Commission, 1988.

RoyF. Weston, Inc. Analysis ofNonexcessive Infiltration
Rates, Study conducted under EPA Contract No. 68-01 -
6737, Municipal Construction Division, Office of Water
Program  Operations, U.S. Environmental Protection
Agency, Washington, D.C., 1983.
                                                 57

-------
Roy  F.  Weston, Inc. Determination  of Excessive/
Nonexcessive Inflow  Rates. Study conducted under
EPA Contract No. 68-01-6737, Municipal Construction
Division, Office  of Water Program Operations, U.S.
Environmental Protection Agency, Washington, D.C.,
1984.

Wilson & Company. Implementation of a Comprehensive
Infrastructure Assessment Program,  Case  Study:
Pittsburgh, Kansas. Department of Public Works, C'rty of
Pittsburgh, Kansas.
                                                 58

-------
                                           CHAPTERS
                                Corrosion Analysis and Control
5.1    Introduction and Background

Structural problems in wastewater collection systems
can sometimes occur as a result of corrosion, and thus
it is important to consider corrosion when designing,
rehabilitating, or analyzing sewer systems. This chapter
discusses the types of sewer corrosion, explains how a
corrosion survey is conducted, and describes methods
for controlling corrosion. Major emphasis is placed on
hydrogen sulf ide (H2S) corrosion, as it isthe most prevalent
form of corrosion in sewer systems.

Internal corrosion in sewer systems is normally related to
the characteristics of the wastes being transported and
is caused by chemical, electrochemical, and biochemical
reactions.  External corrosion is primarily caused by
thermal, physical, structural or electrochemical stresses.

5.2    Types and Mechanisms of Corrosion

5.2.7   Common Types of Pipe Corrosion
Internal pipe corrosion in sewer systems is primarily
caused by two mechanisms: 1) direct attack by corrosive
gases released from the wastewater, such as H2S and
SO2; and 2) bacterial oxidation of H2S to sulfuric acid in
the unsubmerged portions of the pipes. H2S and SO2 in
their gaseous forms are directly corrosive to metals. It is
important to note that the presence of H2S raises concerns
for safety, as H2S gas is toxic to humans. H2S represents
an imminent life threat at a concentration of 300 ppm by
volume in air.  OSHA  recommends a time weighted
average exposure during an 8-hr period of less than 10
ppm by volume.1

Corrosive wastes (e.g. industrial acidic wastes) discharged
to the sewer can cause direct corrosion in submerged
portions of the sewer. Furthermore, certain chemicals
which are, used in  wastewater treatment and collection
systems can be corrosive.

5.2.2   Other Types of Corrosion
Electrochemical corrosion may occur due to electrical
currents created between dissimilar metals or when an
electrolytic waste removes one or more metals from an
alloy.2

Hydrogenation occurs when hydrogen ions react with
metal pipes.Thishoweveroccursunderhightemperature,
pressure, stress and anaerobic conditions, and is not
commonly found in sewer systems.

Fatigue corrosion and stress corrosion are similar, as
both are caused by external stresses applied to the pipe
and occur inside  of the pipe. Fatigue corrosion occurs
when pipes are exposed to repeated stresses.

Filiform corrosion occurs on metal piping with organic
coatings. It is characterized by filament-like corrosion in
the metal surface originating at pinpoint penetrations of
the surface. It is important to note that corrosion is often
the result of more than one mechanism. For example, if
iron  pipe is already experiencing  hydrogen sulfide
corrosion, it becomes more brittle and is more prone to
cracking when stress is applied.

Further information on the mechanisms of both internal
and external corrosion may be found in Reference 2.

5.3    Conducting a Corrosion Survey

5.3.1   Factors Affecting Corrosion
As a part of a Sewer System Evaluation Survey (SSES),
sewer systems  should  be examined  for certain
characteristics that encourage corrosion. Corrosion is
more likely to occur when the dissolved oxygen (DO) is
belowO.Smg/L, since theseconditionsfavorthe anaerobic
bacteria that convert sulfate to sulfide. In gravity sewers,
DO levels are likely to decrease when the wastewater
velocity decreases,  because the lower  velocity: 1)
decreases the scouring of the microbial slime growing on
the submerged pipe walls and invert; 2) promotes solids
deposition; and 3) increases the residence time. In force
mains, inverted  siphons,  and surcharged  sewers,
anaerobic conditions often  exist since the pipe  is full,
thereby precluding surface aeration by oxygen addition
from the sewer atmosphere.
                                                  59

-------
The depth of flow in sewers, the amount of exposed
surface area, BOD of the waste, and pipe slope also
affectthe DO. Turbulence (which isfound at pipe junctions
and places where the pipe changes direction or slope)
can add oxygen to the water,  preventing  sulfide
generation. However, if sulfide is present, turbulence has
an  overall negative  effect as it allows H2S gas to be
released from the wastewater making h available for
corrosion above the water level.

5.3J2    Identifying Likely Locations for Corrosion
The first step In a corrosion survey is to interview people
involved in design, cleaning, inspection, and repair of the
sewer system to identify locations where corrosion may
have been observed. Collection system maps should be
available that include sizes and type of pipes, slopes of
lines,  flows,  manhole locations, frequency of pumping
operations, and locations of force main discharges and
surcharged sewers. Maintenance records, odorcomplaint
files, and TV inspection logs can also  be informative.
Likely field locations to check include:
  Locations of low velocities or solids deposits
  Force main discharge points
  Transition manholes
  Sewage lift stations
  Areas of high turbulence
  Sewers w'rth flat slopes and long detention times
  Inverted siphon discharges
  Headworks of wastewater treatment plants
  Junction chambers and metering stations

5.3.3  Performing Visual Inspections
Avisual inspection of the condition of manholes, metering
stations, wet wells, headworks, and other structures as
apart of the SSES physical survey, is essential to identify
corrosion problems. Areas that are accessible can be
entered and inspected, However, hazardous atmospheres
can exist in such confined spaces, and proper safety
procedures for confined space entry must be strictly
followed.

Items noted in a visual inspection include:

• Condition of ladder rungs, bolts,  conduit, and other
  metal components
• Presence of protruding concrete aggregate
• Presence of exposed reinforcing steel
• Development of'black coating (copper  sulfate) on
  copper pipes and electrical contacts
• Loss of concrete from pipe crown or walls
• Soundness of concrete
• Depth of penetration, using screwdriver or a sharp tool
  to expose uncorroded material
A quick method of inspecting the general condition of
sewers can be performed with a telescoping rod onto
which are attached a halogen light and adjustable mirror
at one end, and a low-magnification (e.g., 4x) sight scope
at the other end. The rod is inserted into a manhole, and
by slightly tilting the rod and flashing the light beam down
the sewer, its condition can be obser/ed. This procedure
is useful when small-diameter sewers are involved. Also,
because entry into a confined space is not required, there
is little risk of being overcome by potentially harmful
sewer gas.

5.3.4   Collecting Data
Usefuldatawhichcan be collected to assess the presence
of, or the potential for corrosion include the following:1

• Concentration of gaseous H2S in manholes and sewer
  atmospheres
• Wastewater pH
• Total and dissolved sulfide in wastewater
• DO and Oxidation Reduction Potential (ORP)
• Surface pH on manhole and sewer walls
• Total and soluble BOD
• Temperature
• Depth of corrosion penetration

One of the most useful "early warning" indicators of
potential H2S corrosion problems is the pH of the pipe
crown or structure wall. This is a simple test using color
sensitive pH paper which is applied to the moist crown of
the pipe. New concrete pipe has a pH of 10-11. After
aging the pH of the crown under non-corrosive conditions
may drop to near neutral. Pipe experiencing severe H2S
corrosion may have a pH of 2 or lower. pH levels below
4 are generally indicative of corrosion problems.

If it is possible to estimate the amount of concrete lost
from sewers or manholes and their age is known, the rate
of corrosion can be approximated.1 Estimates of the
remaining useful life of a structure (e.g., to exposure of
reinforcing steel) can then be used to prioritize sewer
segments or structures for further action.

5.3.5   Predicting; Sulfide  Corrosion
Models have been developed which allow the prediction
of the rate of sulfide accumulation in sewers as well as the
rate of hydrogen sulfide corrosion of concrete pipe. The
predictive equations can be found in References 1 through
4.

5.4    Rehabilitating Corroded Sewers

If it is determined that a sewer is severely corroded and
will require rehabilitation, an appropriate rehabilitation
method must be chosen. Table 5-1 lists common sewer
                                                   60

-------
Table 5-1.        Common Sewer Corrosion  Problems and
               Applicable Rehabilitation Methods

Problem                        Rehabilitation Method
1. Severe corrosion and poor
  structural integrity
2. Severe corrosion; minor
  structural reinforcement
  needed
3. Corrosion in structurally sound
  pipes with diameters 76 cm
  (2.5 ft) or greater
4. Corrosion in non-circular pipes
5. Corroded pipes under busy
  streets
a. Excavation and replacement
b. Sliplining
c. Some specialty concretes

a. Cured-in-place inversion lining
b. Sliplining
c. Some specialty concretes
d. Fold and formed pipe

a. PVCor other corrosion resistant
  liners
b. Sliplining
c. Cured-in-place inversion lining
d. Some specialty concrete
e. Fold and formed pipe

a. Cured-in-place inversion lining
b. Some specialty concretes

a. Cured-in-place inversion lining
b. Fold and formed
c. Sliplining (may be applicable)
problems involving corrosion and provides applicable
rehabilitation methodsforeach. Rehabilitation techniques
are discussed in detail in Chapter 6.

5.5    Controlling Corrosion

5.5.7   Sulfide Corrosion Control
H2S corrosion can be controlled by reducing the levels
of dissolved sulfide in the wastewater. Common control
techniques includeoxygenation, oxidation, precipitation,
and pH elevation.2

If the concentration of DO in the wastewater exceeds
1.0 mg/L, sulfides will not be generated. Therefore,
maintaining a high DO concentration is an effective
method of sulfide corrosion control. Common methods
of H2S control in sewer systems are summarized below.

5.5.1.1  Aeration
Aeration can be a cost effective method for controlling
sulfide generation, but unless air is introduced by passive
means, such as the presence of turbulent conditions in
the system, equipment must be provided to compress
the air  and to introduce  it  into the wastewater. An
advantage of using air injection can be the simplicity of
equipment when compared to other sulfide control
methods.1'3 Often, compressed  air is added to the
discharge side ofthewastewater pumps atthe upstream
end of a force main. The major disadvantages of this
approach are: 1) the potential for gas pocket formation
and air binding, and 2) the relatively short duration for
which aerobic conditions can be maintained due to DO
uptake by bacteria.

5.5.1.2  Pure Oxygen
Because pure oxygen is five times more soluble in water
than air, it is possible to achieve higher  DO  levels in
wastewater by injecting  pure oxygen into wastewater
instead of air. As with air injection, use of pure oxygen as
a sulfide control measure is particularly advantageous in
pressurized systems, because dissolution of oxygen is
greater at higher pressures. However, since less oxygen
gas is required than air to achieve the desired DO levels,
the potential for gas pocket generation in force mains is
substantially reduced. Maintaining the DO above 1 mg/
L is usually sufficient to prevent sulfate reduction.

5.5.1.3  Hydrogen Peroxide
When hydrogen peroxide (H2O2) is added to wastewater,
itoxidizesdissolved sulfide. Excess H2O2decomposes to
water and oxygen. Common dosage rates are 1-5 Ib
H2O.,/lb H2S, depending upon the degree of control
desired, wastewater characteristics, sulfide levels and
length of time involved between the injection and sulfide
control point. Equipment used for H2O2 addition is relatively
simple, consisting mainly of a storage vessel and metering
pumps. Materials for storage and feed equipment must
be compatible with H2O2.1'3

5.5.1.4 Potassium Permanganate
Potassium permanganate (KMnO4) is a strong oxidizing
agent which has a reaction similar to that of H2O2. It is
normally supplied in a dry state, and is fed as a 6-percent
solution  in water. Therefore, equipment for dissolving
and  feeding it  must be supplied. Because of its high
costs,  it is not commonly used for sulfide control in
wastewater collection systems.

5.5.1.5 Chlorine
Chlorine will oxidize sulfide to  sulfate or to elemental
sulfur, depending on pH.  It is commonly added at a
dosage rate of 10-15 Ib Cl/lb H2S removed. It may be
added as sodiu m hypochlorite or a chlorine solution using
equipment similar to that installed in wastewater treatment
plants for effluent disinfection.

5.5.1.6 Iron Salts
Iron salts react  with sulfide to produce insoluble
precipitates, and are added afterthegeneration of sulfides
has occurred to tie up the dissolved sulfide and prevent
the release of H2S into the sewer atmosphere. Dosages
are usually dependent on  initial sulfide levels and  the
targeted level of control, but will generally be 4-15 Ib Fe/
Ib H2S. Iron salts may be purchased as dry chemicals and
dissolved in waterforease of injection, but are commonly
                                                     61

-------
purchased as a solution. Ferrous chloride and ferrous
sulfate are often purchased in bulk, usually as a 40-
percent solution, and being acidic in nature, they must be
handled in corrosion-resistant materials. As with other
sulfide control chemicals (such as hydrogen peroxide), a
typical feed system involves feeding the iron solution at
multiple rates in relationto diurnal fluctuations in dissolved
sulfkte and flow rate.1-5

5.5.1.7 Sodium Hydroxide
H2S corrosion may also be controlled by inactivating the
sulfate-reducing bacteria. Sewer systems in LosAngeles,
as well as other cities, have used pH elevation to control
sulfide corrosion. A caustic solution is added as a shock
dosage for 20-30 minutes, raising the pH in the sewer to
12-13. Soon after the high-pH slug has passed, the
sulfate-reducing bacteria will become re-established so
that dosing with caustic must be repeated when sulfide
levels begin to increase. Typically, the caustic will be
added at intervals which vary from  several days to two
weeks.1-5

With  this  approach, caution must be taken  to avoid
upsetting the biological treatment system with the slug of
high pH wastewater. The slug may be diluted as it passes
through the sewer system,  in which case there is no
problem. If this in not the case, the slug can be diluted by
directing it to spare tankage and  slowly adding  it to
treatment plant influent.1'5

Although  a pH above 8.0 will result in lower  levels of
dissolved H2S gas, continuously adding causticto maintain
a high pH is not generally practical.

5.5.1.8  Sodium Nitrate
The addition of sodium nitrate to sulfate-containing
wastewaters will suppress the generation of H2S. This
occursbecause bacteria will preferentially reduce nitrates
before sulfates. Thus, no sulfides will be produced until
the sodium nitrate has all been reduced.1-5

5.5.1.9  Designing to Avoid Corrosion
Sulfide corrosion can be minimized through careful design
of the sewer system. The  corrosion resistance of the
, materials used is an important factor. The characteristics
of many  typical materials  are described in  detail  in
several references. Other aspects of the design are also
discussed in these references. The  most important
considerations when designing for sulfide control are:1

• Minimizing the occurrence offeree mains, siphons and
  surcharged sewers
• Designing for velocities which are sufficient to prevent
  the accumulation of solids and which provide surface
  aeration of the wastewater.
• Prohibiting the direct addition of sulfides from any
  source

Further details  on each of these  sulfide control
recommendations can be found in the Design Manual:
Odor and Corrosion Control in Sanitary Sewerage
Systems and Treatment Plants,3 Sulfide in Wastewater
Collection and Treatment Systems* and Detection,
Control, and Correction of Hydrogen Sulfide Corrosion in
Existing Wastewater Systems.6 These referencse are
also an excellent source of information on designing
sewer systems to avoid corrosion problems.

Design practices can affectthe degree of corrosion found
in a sewer system. If pipes are oversized, wastewater
flow rates will  be reduced and organic materials may
accumulate. This condition is favorable forthe production
of sulfide and can lead to corrosion  problems. O&M
practices also affect corrosion. Since accumulation of
organicsolidsisfavorableto initiation of sulfidegeneration,
regular cleaning of oversized segments will help prevent
these problems. Prolonged surcharging,  or  other
conditions which result in full pipes, should be avoided
since lack  of air in the pipes can  increase  sulfide
production. Short periods of surcharging, however, can
be beneficial since the increased flow rates may wash out
accumulated solids.1 Lift station and force main designs
that allow long pipeline detention times increase the
pressure of H2S.

5.5.2   Control of Other Forms of Corrosion
Where industrial wastes contribute to H2S generation,
industries which dischargetothe sewer should be required
to meet some type of pretreatment standards. If the
wastewater in the sewers is found to be significantly
acidic or basic, the pH should be adjusted.

Moisture must be present for most types of corrosion to
occur. Forexample, a moist atmosphere allows corrosive
vapors to condense on pipe walls and on other fixtures in
the sewer system. Ventilation systems have been used
to reduce moisture and corrosion in sewers. Some
general guidelines for these systems can be found in the
 Design Manual: Odor and Corrosion Control in Sanitary
 Sewerage Systems and Treatment Plants.3

When designing a new system or making replacements
 in an old system, materials should be chosen which are
 resistant to the types of waste present. Guidelines for
 selecting resistant materials are provided in Table 5-2.4

 If electrochemical corrosion of iron or steel isthe problem,
 cathodic protection  may be appropriate. One type of
                                                    62

-------
Table 5-2.        Guidelines to Select Pipe Materials to Resist
                Corrosion (4)

Various types of pipe material can be specified as part of the overall
design strategy. Eithercorrosion-resistantor co rrosksn-sensitive materials
can be employed, depending on predicted sulfide levels, required service
life, and economic considerations. The designer has the option of simply
specifying an acid-resistant material or specifying an acid-sensitive
material together with other corrosion control strategies, such as:

  Providing O2 to water.
  Providing chemical control of sulfide generation.
  Designing system hydraulics to avoid sulfide generation.
  Providing sacrificial concrete cover.
  Providing sacrificial metal thickness (steel or ductile iron).
  Using concrete modification, such as calcareous aggregate.
  Using a protective liner or coating.

The following materials, varying in sensitivity to  acid corrosion, are
available for sanitary sewer construction:

• Vitrified Clay Pipe (VCP) is virtually immune to acid attack. In older
  VCP lines, cement mortar joints expanded, and sometimes broke the
  bells. Other types of gasketed joints now in general use avoid this
  problem. However, VCP is brittle, and so needs special installation
  practice and care in handling and transport.
• 'Steel pipe is susceptible to direct corrosion by H2SO4, H2S corrosion
  of the iron component, and the normal oxidation of iron.
• Cast Iron Pipe (CIP) is also susceptible to H2SO4and H2S, and normal
  oxidation corrosion. It generally lasts longer than steel, simply because
  a thicker pipe wall is used.
• Reinforced Concrete Pipe (RCP) is susceptible to acid corrosion.
  However, despite its vulnerability, concrete represents an important
  sewer pipe material, particularly for large trunk sewers. Concrete can
  be fortified against attack by using calcareous aggregate, increasing
  the cement content, or both, which provides additional alkalinity and
  acid  neutralizing capacity where severely corrosive conditions are
  anticipated, PVC liners can be employed.
• Asbestos Cement Pipe (ACP) is susceptible to acid corrosion. Due to
  its higher cement content, it corrodes at a slower  rate than granitic
  aggregate concrete, although this attribute is offset by a generally
  thinner pipe wall.
• Thermoplastic pipes, such as Polyvinyl Chloride (PVC), Polyethylene
 • (PE), and Acrylonitrile-Butadiene-Styrene (ABS), are resistant to acid
  corrosion, although subject to strain corrosion in the presence of some
  materials, such as detergents, organic solvents, and fats and oils.
• Thermoset plastic pipes, such as Reinforced Plastic Mortar (RPM) and
  Reinforced Thermosetting Resins (RTR), are resistant to acid attack.
cathodic protection involves  impressing an  electrical
current  on the corroding surface. The  metal surface
which is to be protected is electrically connected to the
negative terminal of a current source and a "sacrificial"
anode is connected to the positive terminal. The sacrificial
anode must be in the electrolytic wastewater and must be
constructed of a material which has a higher electrical
potential than the protected material. Cathodic protection
does not always work well, so an experienced corrosion
control  engineer should  be consulted before such  a
system  is attempted.1

5.6     References

When an NTIS  number  is cited in a reference, that
reference is available from:

         National Technical Information Service
         5285 Port Royal Road
         Springfield, VA 22161
         (703) 487-4650

1.  Odor and Corrosion Control in Sanitary Sewerage
    System and Treatment Plants. EPA/625/1-85/018.
    U.S. Environmental Protection Agency, Cincinnati,
    Ohio, 1985.

2.  Report to Congress: Hydrogen Sulfide Corrosion in
    Wastewater Collection and Treatment Systems. EPA/
    430/9-91/009. U.S. Environmental Protection Agency,
    Office of Water, Washington, D.C. in preparation.

3.  Odor and Corrosion Control in Sanitary Sewerage
    System and Treatment Plants. EPA/625/1-85/018,
    EPA, Cincinnati, Ohio, 1985.

4.  Sulfide in Wastewater Collection and  Treatment
    Systems. ASCE Manual and Reports on Engineering
    Practice No. 69, ASCE, New York, 1989.

5., Sulfide and Corrosion Prediction and Control.
    American Concrete Pipe Association, Vienna, VA.,
    1984.

6.  Detection, Control,  and Correction  of Hydrogen
    Sulfide Corrosion in Existing Wastewater Systems.
    EPA/430/9-91/019. U.S. Environmental  Protection
    Agency, Office of Water, Washington, DC. 1991.
                                                          63

-------

-------
                                           CHAPTER 6
                                  Sewer System Rehabilitation
6.1    Introduction
Many methods of sewer system rehabilitation are
available. This chapter examines contemporary methods
and provides guidance on the situations where each
method  is applicable.  A general description of each
rehabilitation technique, and the procedures, equipment,
and cost estimates are discussed in the following sections.

The reader is cautioned in the use of the costs for various
rehabilitation techniques presented herein. Although the
cost  information presented is from the best available
sources, there are some major differences in the basis of
these costs since all cost components are not included in
every rehabilitation technique. Some costs have been
extracted from earlier reports and indexed to the present
time while other costs are from recent sources. Some
costs include engineering and some do not. An attempt
was made to present the cost on a consistent basis ($/
length of sewer), but this may be misleading for some
techniques such as chemical grouting since these costs
vary depending on the number of joints grouted.

It should further be recognized that there are some rather
strong geographical differences in cost for some of the
techniques such, as sliplining and cured-in-place inversion
lining. Also the reported cost of some techniques exhibits
a wide cost range for the same size of pipe due to site-
specific  factors. The actual cost  ranges are reported
where available. Examinationofthecosttables will show,
forexample, that the high side of the reported cost ranges
for some techniques such as sliplining and inversion
lining are higherthan replacement costs. The basis of the
cost for each rehabilitation technique is described at the
bottom of each cost table. All costs have been indexed to
a March 1991  Engineering News Record Construction
Cost Index (ENRCCI=4773).

6.2    Excavation  and Replacement

6.2.1  Description
Replacement of deteriorated pipelines was once the
most common  rehabilitation practice but is becoming
more limited due to the availability of trenchless
technologies. Excavation and replacement of defective
pipe segments is normally undertaken underthe following
conditions:1

• When the structural integrity of the pipe has deteriorated
  severely; forexample, when pieces of pipe are missing,
  pipe is crushed or collapsed, or the pipe has large
  cracks, especially longitudinal cracks
• When the pipe is significantly misaligned
• When additional pipeline capacity is also needed.
• When trenchless rehabilitation methods that would be
  adequate to restore pipeline structural integrity would
  produce an unacceptable reduction in service capacity
• For point repair where short lengths of pipeline are too
  seriously damaged  to be effectively rehabilitated by
  any other means
• Where entire reaches  of pipeline are too seriously
  damaged to be rehabilitated
• Where removal  and replacement is less costly than
  other rehabilitation methods

The following are the disadvantages of pipeline removal
and replacement as a method of sewer line rehabilitation:

• Removal and replacement is usually more expensive
  than other rehabilitation methods.
• Removal  and  replacement  construction  causes
  considerably greater and longer-lasting traffic and
  urban disruption than does rehabilitation.
• Removal and replacement construction involves a
  greater threat of damage to, or interruption of, other
  utilities than does pipeline rehabilitation.

6.2.2   Procedures and Equipment
Sewer pipe rehabilitation through pipeline  replacement
can be carried out in the following two general forms:

• Excavation and replacement where the existing pipeline
  is removed and a new pipeline is placed in the same
  alignment
• Abandonment and  parallel replacement where  the
  existing pipeline is abandoned in place and replaced by
  a newpipeline in either: 1) physically parallel alignment
                                                  65

-------
  adjacent to the existing line, or 2) a functionally parallel
  alignment along a different route

Pipeline replacement  materials  include traditional
materials such as reinforced concrete, clay, ductile iron
and a variety of plastics.

Removal of an existing  pipeline and replacement with
new pipe involves all of the problems which occur in
construction of new pipelines in new alignments, plus
special problems which are unique to removal and
replacement. The problems unique to removal and
replacement are:

• MaintainingtributaiysystemanaVorserviceflowsduring
  construction
• Removal and disposal of old pipes
• Fill up old abandoned pipes with structurally sound
  material to prevent potential collapse
• Workingthroughutilitiesoverlyingorcloselyparallelto
  the pipe. These special problems usually result in
  added construction costs which often do not occur in
  new construction along a new pipe alignment.

Problems which occur in both removal and replacement
and in new construction on a new alignment are:

• Disruption of street traffic
• Disruption of access to residential, commercial, and
  industrial properties
• Temporary loss of street parking
* Trench shoring in deep construction involving unstable
  soil
* Trench dewatering in areas with high groundwater

6.2.3   Costs
The cost of pipeline excavation and  replacement is
specific to individual job conditions. Cost factors are:

  Old pipe removal and  disposal
  Manhole removal and replacement
  Trench shoring
  New pipe materials installation
  Service reconnections to sanitary sewer
  Street inlet reconnections to storm drains
  Upstream flow diversion during construction
  Maintenance of local sanitary service
  Traffic control systems and scheduling
  Pavement restoration
  Interference with other utilities
Table 6-1 presents approximate costs forthe excavation
and replacement method of sewer rehabilitation. The
costs in this table are based on costs taken from the
Handbook for  Sewer System Evaluation  and
Table 6-1.       Rehabilitation Costs* for  Excavation and
               Replacement (EMRCCI-4773)
Pipe
Diameter
(in)
6
8
10
12
14
16
18
20
30
40
48
54
60
72
90
102

Reference 2*

45-70
50-75
55-85
65-95
70-105
75-110
80-120
95-145
135-205
195-240
235-285
240-295
275-340
365-450
465 - 555
530-645
Cost ($/Lf\
' References**




40-55
45-65
50-75
.65-90
70-105
105-155
150-225
190-230
235-285
260-320
325-360
415-510
495 - 605
      2.7 m (9 ft) depth assumed.
      Costs include site preparation, excavation, backfill, pavement,
      pipe materials, removal of existing pipes, pipe installation,
      reconnection of one house service connection for every 6 m (20
      ft) of pipe installed. Depth of cover over crown of pipe at 2.7 m (9
      ft), pipe in moderately wet soil conditions. Cost to remove the
      existing pipe is 50 percent of that required to install a new pipe.
      Excludes ledge excavation.
      3 m (10 ft) depth assumed.
      Costs based on minimum project size of 300 m (1,000 LF).
      Costs do not include design engineering, construction
      management, bypassing of wastewater, reconnection of services
      or street drain inlets, trafficcontrol, utility interference, or removal
      and replacement of manholes.
      Excludes ledge excavation.
Rehabilitation2  and from  Utility  Infrastructure
Rehabilitation3 and were adjusted to current pricesthrough
the use of the ENRCCI. Costs  were also verified by
contacting vendors and contractors.

6.3    Chemical Grouting

6.3.1   Description
Chemical grouting of sewer lines is mainly used to seal
leaking joints and circumferential cracks. Small holes
and radial cracks may also be sealed by chemical
grouting. Chemical grouts can be applied to pipeline
joints,  manhole walls, wet wells in pump stations and
other  leaking  structures  using  special tools and
techniques.1 One grouting procedure  is illustrated in
Figure 6-1. All chemical grouts are applied underpressure
after appropriate cleaning and testing of the joint. Chemical
grouting is used in precast concrete brick, VCP sewers
and other pipe materials to fill voids in backfill outside the
sewer wall. Such backfill voids can reduce lateral support
                                                    66

-------
Figure 6-1.       Grouting equipment and procedures.
                     .Chemical Catalyst and
                     Air Pressure Feed Lines
                                                                                              Winch
                                         Manhole
                                          Roller
                                        Assembly
Sealing
Packer
                                                                            TV Camera
                                                          67

-------
of the wall and allow outward movement resulting in the
rapid deterioration of the structural integrity as the arch
of the  top of the pipe looses its support. Chemical
grouting adds no external structural properties to the pipe
where  joints or circumferential cracking problems are
due to  ongoing settlement or shifting of the pipelines. It
is not effective to use chemical grouting to seal longitudinal
cracks or to seal joints where the pipe near the joints is
longitudinally cracked. Grouting is a joint sealing technique
to be used for each joint in a pipeline segment that fails
the initial leakage test. Chemical grouting is normally
undertaken to control groundwater infiltration in non-
pressure pipelines when  these are caused by leaking
pipe joints or circumferential cracking of pipe walls.

Chemical grouting is applied internally within a pipe, and
thusdoesnotdamageorinterferewithotherunderground
utilities. It does  not  require  excavation or surface
restoration, such as pavement or sidewalk replacement
and ground cover reseeding.

Chemicalgroutingdoes not improvethe structural strength
of the pipeline and thus should not be considered when
the pipe is severely cracked, crushed or badly broken.
Chemical grouts may also dehydrate and shrink if the
groundwater drops below the pipeline and the moisture
content of the surrounding soil is reduced significantly.
Large joints and cracks may be difficult to seal because
large quantities of grout may be required. Large cracks,
badly offset joints and misaligned pipes may  not be
sealable. Offset joints may prevent the inflatable rubber
sleeves of the sealing unit from seating properly against
the walls of the pipe, making it impossible to isolate and
seal the joint.

The most common chemical grouts currently available
are acrylamidegel, acrylic gel, acrylategel, urethanegel,
and polyurethane foam. The use of acrylamide gel as a
grout may possibly be banned by U.S. EPA since it is
suspected that this grout causes health problems for the
application workers. The basic characteristics of foam
and gel grouts are described below.

Gel Grouts are resistant to most chemicals found in
sewer  lines but they may  produce a gel-soil mixture
which  is  susceptible to dehydration and shrinkage
cracking. When using gel grouts, the grouting contractor
and/or the grout supplier should be required to submit
data supporting the non-shrink  characteristics of the
grout. Acrylamide gel is significantly more toxic than the
acrylate polymer or urethane gel grouts. Urethane gel
uses water  as the catalyst. No significant  water
contamination of the urethane grout should be permitted
prior to its injection. Gel grouts are not recommended
where  there are large voids outside the pipeline joints.
Foam grouts consist  of liquid urethane  prepolymers
which are catalyzed by waterduring injection. Thefoaming
reaction of the grout and water expandsthe materials into
the joint cavity, thereby sealing the crack. The foam
grouts are capable of expanding 8-12 times their initial
volumes. Foam grouts are usually difficult to apply and
are more expensive than gel grouts,

Before choosing to use grouting for joint rehabilitation,
the pipeline should be inspected for the following:1

« Determine pregrouting cleaning  needs and extent of
  root intrusions.  For effective grouting,  the pipeline
  must be relatively free of sand,  sediment and other
  deposits. Cleaning should occur just prior to grouting.
• Identify crushed or broken  sections that must be
  replaced. Deformed and longitudinally cracked pipe
  sections should not be grouted.

Joints and circumferential cracks in small- and medium-
sized pipes  (15-107  cm [6-42 in] diameters) can be
remotely tested and grouted using a packer system
monitored by closed-circuit IV.

The service life of the grout is an important consideration.
Acrylamide grout has been used successfully since the
1950's to stabilize soils and help control underground
water movements in  tunnels, darns,  dikes, pits and
various other underground structures. The urethane
grouts are more recent. Pipe size, joint spacing, and the
percentage of joints  requiring sealing are. factors to
consider in determining the cost of chemically sealing a
line. The larger the pipe, the higher the cost because of
increased manpower, equipment and materials. Chemical
grouting requires  rerouting of wastewater flow around
the section being grouted until the  grout is cured.

6.3.2   Costs
See Table 6-2 for approximate grouting costs. The costs
in this table are based  on costs taken  from  Utility
Infrastructure Rehabilitation3 and were adjusted to current
prices through the use of a cost index.  Costs were also
verified by contacting vendors and contractors. Table 6-
2 reflects 100 percent joint grouting  with 60-cm (2-ft) pipe
sections. Grouting costs may be significantly lower than
that shown for grouting fewer joints based on leakage
tests or for longer (1 -2 m [3-6 ft]) pipe lengths.

6.4   Insertion

6.4.1  Description
Pipe insertion is used to rehabilitate sewer pipelines by
sliding a flexible liner pipe of slightly smaller diameter into
an  existing pipeline and then reconnecting the service
                                                    68

-------
Table 6-2.
Rehabilitation Costs for Grouting
Pipe
Diameter
(in)
6
8
10
12
15
18
21
24
27
30
33
36
39
42
48
54
60
66
72
78
84
90
96
102
108
Grouting
Prep. Cost
($/LF)
1.00
2.00
2.00 •
3.50
6.00
7.50
9.50
12.00
14.50
18.00
21.50
28.00
32.50
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Dec. 1984
Grouting Cost
($/tF)
18.00
21.00
24.50
28.00
32.00
36.00
61.00
70.00
79.00
83.00
93.00
104.00
110.00
122.00
325.00
365.00
450.00
580.00
645.00
780.00
865.00
1,000.00
1,500.00
1,325.00
1,465.00
Total
($/LF)
19.00
22.00
26.50
31.50
38.00
43.50
70.50
82.00
93.50
101.00
114.50
132.00
142.50












Mar. 1991
Total Costs
($/LF)
20-30
24-36
28-42
32-48
36-54
40-60
68-102
76-95
88-132
96-144
108-162
124-186
132 - 198












Grouting Preparation Costs
Table 6-3.        Advantages and Disadvantages of Sliplinlng

Advantages                   Disadvantages
• Based on minimum project size of 300 m (1,000 LF).
« Root kill includes application of herbicide inside pipe before root
  removal and cleaning.                     -
• Cleaning costs apply to entire pipe reach.
• Costs are at December 1984 cost level (ENRCCI=4144); 1991 costs
  based onadjustmentofthe 1984coststoMarch 1991 (ENRCCM773).

Unit Grouting Costs
• Based on minimum project size of 300 m (1,000 LF) and grouting 100
  percent of joints.
• Remote testing and grouting packer system monitored  by closed
  circuit TV.
• Costs are at December 1984 (ENRCCM144); 1991 costs based on
  adjustment of the 1984 costs to March 1991 (ENRCCI=4773).
• Does not include grouting preparation costs.
connection to the new liner. This is done by pulling or
pushing new pipe into a deteriorated pipeline. The liner
forms a continuous, watertight length within the existing
pipe after installation.1

Pipe  insertion techniques can be used to rehabilitate
sewer,  water and other pipe lines that may have severe
structural problems such as extensive cracks, lines in
unstable soil conditions, deteriorated pipes in corrosive
environments, pipes with massive and destructive root
intrusion problems and pipes with relatively flat grades.
                                                            Minimal disruption to
                                                            traffic and urban activities
                                                            (as compared to replacement)

                                                           • Minimal disturbances to other
                                                            underground utilities; affects
                                                            only those in the vicinity of
                                                           access pits.

                                                            Significantly less costly than
                                                            replacement
                                                            Quick installation time.
                                                            Good protection against acid
                                                            corrosion
                                                            Does not require bypassing.

                                                            Wide range of pipe sizes
                                                            (i.e.,3-144in)

                                                            Can be used to rehabilitate
                                                            pipelines with severe
                                                            corrosion.
                                                                      • Possible reduction in
                                                                        pipecapacity
                                                                        Requires excavation
                                                                        of an access pit.
                                                                        Less applicable to sewers with
                                                                        numerous curves or bends, since
                                                                        multiple pits would be required.

                                                                        Requires obstruction removal
                                                                        of internal obstructions prior to
                                                                        sliplining.

                                                                        Installation difficulties may be
                                                                        encountered during
                                                                        grouting of annular space.
                                          Advantages and disadvantages of sliplining as a method
                                          of rehabilitation can be found in Table 6-3.

                                          The most popular materials used to slipline sewer lines
                                          are polyolefins, fiberglass reinforced polyesters (FRP),
                                          reinforced thermosetting resins (RTR), polyvinyl chloride
                                          (PVC), and ductile iron (cement lined and polyvinyl lined).

                                          Polyethylene (PE) isthe most common polyolefin material
                                          used and is available in low density, medium density and
                                          high density. High-density PE (HOPE) compounds are
                                          best suited for rehabilitation applications as they have
                                          good stiffness,  are hard, strong, tough and corrosion
                                          resistant. PE pipe is manufactured as either extruded or
                                          corewall.1  Extruded pipe has smooth  inner  and outer
                                          surfaces and  has  structural characteristics that are
                                          determined by  wall thickness. Corewall  pipe has an
                                          exterior hollow rib which gives structural integrity to the
                                          pipe and minimizes pipe weight. Extruded PE  pipe is
                                          manufactured in diameters of 5-122 cm (2-48 in) and
                                          corewall PE pipe 30-366 cm (12-144 in). Two national
                                          specifications ASTM  P1248 and  ASTM D3550,  are
                                          available for design and reference. These  standards
                                          apply to extruded PE pipe with circular cross-sections
                                          and diameters of 10-122 cm (4-48 in).
                                                        69

-------
Polybutytene (PB), another polyolefin, is similarto medium
density PE pipe in stiffness and chemical resistance but
has better continued stress loading characteristics.  It
also has  good temperature  resistance. PB pipe is
manufactured as extruded pipe in diameters of 8-107 cm
(3-42 in).

Centrifugally cast FRP pipe was originally manufactured
in Switzerland in the 1960's and is now being widely used
in U.S. It is a composite of resin made from fiberglass and
sand that is formed within a revolving mold. It is frequently
specified as an acceptable alternative to polyethylene.
FRP pipe has very good chemical and corrosion resistance
and is suitable for use over a pH of 1-10. FRP pipe is
manufactured in standard 6-m  (20-ft) lengths and is
available in diameters of 46-244 cm (18-96 in).

RTR pipe is a composite of fibers and resins that are
either spiral wound on a rotating mandrel or composited
on the inside of a rotating drum, similarto FRP pipe. RTR
pipe has good axial and longitudinal strength, enabling it
to be  pushed into an existing pipe without  buckling.
Friction losses are low due to smooth interior surfaces.
This pipe has high strength  and a high modules of
elasticity. It also hasgood corrosion, erosion and abrasion
resistance. Manufactured sizes are lengths of 6-24 m
(20-80 ft) and diameters of 10-360 cm (4-142 in).

Flexible PVC has been used successfully as a sliplining
material. PVC is highly resistant to acid attack and is very
smooth, exhibiting  good hydraulics. Grouting of the
annular space is required to give strength to the PVC.

6.43   Procedures and Equipment
Prior to sliplining. the sewer should be first thoroughly
cleaned and inspected by closed circuit TV to identify all
obstructions such as displaced joints, crushed pipes and
protruding service laterals. The inspection also should
JocateaHserviceconnectionsthatwillneedto be connected
to the new liner pipe. The pipe  must be thoroughly
cleaned. It may at times be necessary to proof test the
existing pipe by pulling a short piece of liner through the
sewer section.

Sliplining is performed by either apush or a pull technique;
both methods are illustrated in Figure 6-2.1 In the pull
method a pulling head is attached to the end of the pipe.
A cable is run from the termination point to the access
point and is connected to the pulling head. The sliplining
pfpe is then pulled through the existing pipe with the cable
by a track mounted winch assembly. Pulling is used for
extruded  PE and PB pipe that is  heat fused into a
continuous length. The push method can be performed
by ertherabackhoeorajacking machine. Abackhoe can
be used for extruded heat fused PE or PB pipe, Corewall
PE pipe, FRP pipe and RTR pipe. However, the backhoe
is limited to small diameter and/or short length pipe. The
jacking machine is used for larger diameter, sleeve-
coupled or bell spigot jointed pipes (e.g. Corewall PE,
FRP, and RTR) but it is not used for heat fused polyolefin
pipe.

For most insertion projects it is not necessary to eliminate
the entire flow stream within the existing pipe structure.
Actually, some amount of flow can assist positioning of
the liner by providing a lubricant along the liner length as
it movesthroughthe deteriorated pipe structure. Excessive
flows can inhibit the insertion process, however, the
insertion procedure should be timed to take advantage of
cyclic periods of low flows that occur during the operation
of most gravity  piping systems.  During  the insertion
process, often a period of 30 minutes or less, the annular
space between the sliplining pipe and the existing pipe
will probably carry sufficient flow to maintain a safe level
in the operating section of the system being rehabilitated.
Flow can then be diverted  into  the  liner  upon final
positioning of the liner. During periods of extensive flow
blockage, the upstream piping system should  be
monitored, and  provisions for bypassing provided in
order to avoid  unexpected flooding and drainage areas.

Once the sliplining pipe has been pulled through  the
existing pipe, it is grouted in place. Grouting at manhole
connection is required, but grouting of the entire length of
the pipe is not required if the liner is strong enough to
support loads in the event of collapse of the original pipe.
It must be determined on a site-specific basis whether or
not to grout after  evaluating the severity of structural
deterioration and anticipated hydrostatic and structural
loadings. Grouting provides the following advantages:
  Provides structural integrity
  Increases hydrostatic and structural loading capabilities
  Prevents liner from moving
  Locks in service connections
  Extends the service life of the pipe
  Provides increased temperature resistance
  Provides support to liner when cleaning
 One of the advantages of sliplining to replacing a sewer
 line is that it requires minimal excavation which limits
 traffic disruption and minimizes interferences with surface
 structures, such as retaining walls, landscaping,  or
 portions of buildings. Sliplining also can be used to avoid
 extensive dewatering that is necessary for conventional
 open trench construction. Sliplining can be installed in
 pipelines having moderate horizontal or vertical deflection
 due to the flexible nature of the sliplining pipe.
                                                    70

-------
Figure 6-2.        Insertion methods.
"Pull" Insertion Technique
                      /Winch Assembly
                                                     Ramp for
                                                 Two-Way Insertion
                                                                                 Min. of 12x
                                                                                Liner Diameter
Liner Pipe
     Remote Manhole
      or Access Pit
                        Existing Pipe    Cable Attached
                                       to Guide Cone
                                                                                                       Pipe Support Roller
"Push" Insertion Technique
                                                   Existing Pipe
                Winch Asembly
                        7*7 /
                      Guide Cone
            Existing Pipe
Remote Manhole
 or Access Pit
                                                                     Minimum of Standard
                                                                        Pipe Length
                                              Cable Passing Through
                                              Lining Pipe Anchored
                                                  to Push Plate
                                                            71

-------
Equipment required forthe insertion of the sliplining pipe
are: jointing equipment, pulling or pushing head, winch,
rollers, proofing tool, grout tank and pump. The jointing
equipment is used to join segmented pipe lengths to form
a continuous pipe of desired  length. This is done by
aligning the two pipes together, heating the ends and
butting the ends together. The pulling head is used to
facilitate the pulling of the pipe into the sewer. One end
of the pulling head is attached to the pipe to be pulled
while the other end is attached to the pulling cable. The
winch, consisting of a power operator and a pulling cable,
is used to pull the pipe. The rollers are used to grout the
annular space between thepipe and manhole connections
to prevent groundwater migration.

6.4.3    Costs
Tables 6-4 through 6-7 indicate the approximate costs for
sliplining as a method of sewer rehabilitation. The data in
these tables are based on costs taken from the Handbook
for Sewer System Evaluation and Rehabilitation* and
Table 6-5.
Rehab Costs for Sliplining with PE Pipe
Tab!* 6-4.         Rehab Costs for Sliplining with HOPE and
                 Polybutylene Pipe
Pipe
Diameter

4
8
12
16
20
24
28
32
36
40
42
48
55
63
Dec. 1984
ENRCCI-4144
(S/LF)
8-17
12-29
19-38
25-47
30-60
28-75
44-92
58-112
68-132
78-152
85-156
90-196
105-209
123-252
March 1991
ENRCCI=4773
($/LF)
9-20
15-35
25-45
30-55
35-70
35-90
55-110
70-130
80-155
90-180
100-185
105 - 230
125-245
145-295
  1984 costs from Reference 3; 1991 costs based on adjusted 1984
  costs.
  Based on mln. project size of 300 m (1,000 LF).
  Polybutylene pipe not available In sizes larger than 122 cm (48 in).
  Lower cost ranges may apply to pipelines with good alignment, no
  need for spot repair, and no significant groundwater.
  Higher cost ranges may apply to pipe with poor alignment, some need
  for spot repair and need for groundwater dewatering.
  Costs do not Include: preparation of Insertion access pit(s); grouting
  or sand fitting of entire liner pipe/existing pipe annual space; bypassing
  ofwastowa!er;costs Jordeslgnenglneering, construction management
  or design related services.
Pipe
Diameter
(in)
6
8
10
12
14
16
18
22
26
28
32
36
42
48
52
58
68
72
80
88
92
100
Mid 1974
ENRCCI=1993
($/LF)
20
21
23
25
28
32
34
39
45
54
62
72
88
102
110
135
152
174
200
225
250
275
March 1991
ENRCCI=4773
($/LF)
35-60
40-60
45-70
50-75
55-80
60-95
65-80
75-115
90-130
105-155
120-180
155-190
190-230
220 - 275
250-290
290-355
330-400
375-460
430-530
485 - 595
540-660
595-725
                                                              1974 costs from Reference 2; 1991 costs based on adjusted 1974
                                                              costs.
                                                              Costs include site preparation, insertion pit, pipe, materials, pipe
                                                              welding, pipe installation, connection of one house service for every 6
                                                              m (20 ft) of pipe, pipe sealing at manholes J'.nd mobilization.
                                                            Table6-6.         Rehab  Costs  for  Sliplining Reinforced
                                                                             Thermosetting Resin
Pipe
Diameter
(in)
8
12
16
20
24
30
36
42
48
54
60
66
Dec. 1984
ENRCCI=4144
($/LF)
20-26
35-45
45-55
60-70
75-80
85-110
. 110-130
125-150
145-170
165-185
175-220
185-235
March 1991
ENRCCI=4773
($/LF)
25-30
40-55
55-65
70-85
85-90
100-130
130-150
145-175
170-200
190-215
215-255
215-275
   Costs based on min. project size of 300 m (1,000 LF).
   1984 costs from Reference 3 ; 1991 costs based on adjusted 1984
   costs.
   Lower costs may apply for existing pipe with poor alignment, some
   need for spot repair, and need for groundwater dewatering during
   construction.
   Costs do not include preparation of insertion access pit, connection of
   service to new line, grouting or sand fitting of the entire "liner pipe
   existing pipe" annular space, or bypassing of wastewater.
                                                          72

-------
Table 6-7.

    Service
Connection Size
Miscellaneous Rehab Costs for Sliplining
        Dec. 1984
      ENRCCI=4144
 March 1991
ENRCCI=4773
4 or 6 in @ 4-8 ft depth
4 or 6 in @ 8-12 ft depth
4 or 6 in @ 12-16 ft depth
4 or 6 in @ 16-20 ft depth

Grouting

Access Pit
  <1 Oft depth
10-20 ft depth
  >20 ft depth
           ($)

        400/each
        550/each
        750/each
        1,000/each

     200/cu yd of grout
     ($)

  465/each
  640/each
  870/each
  1,165/each

  230/cu yd
       1,000/ft depth      1,165/ft depth
       800/ft depth       930/ft depth
       1,000/ft depth      1,165/ft depth
  Costs are for average traffic conditions and include pit sheeting and
  shoring in reasonably stable soil where groundwater dewatering is not
  necessary.
  1983 costs are from Reference 3; 1991 costs based on 1984 adjusted
  costs.
from Utility Infrastructure  Rehabilitation*  and  were
adjusted to current prices through the ENRCCI. Costs
were also verified by contacting vendors and contractors.

6.5    Cured-in-Place  Pipe Lining

6.5.1   Description
Inversion lining is formed by inserting a resin-impregnated
felt tube into a pipe, which is inverted against the inner
wall of the pipe and allowing it to cure. After the lining
system has been installed and cured, a special cutting
device is used with a closed-circuit TV camera to reopen
service connections, which are located with the camera
before the liner  is installed. The pliable  nature of the
resin-saturated  felt prior to curing  allows installation
around curves,  filling of  cracks, bridging of gaps, and
maneuvering through pipe defects. After installation, the
fabric cures to form a new pipe of slightly smaller diameter,
but of the same shape as the original pipe. The new pipe
has no joints or seams and has a very smooth interior
surface which may actually improve flow capacity despite
the slight decrease in diameter.

Two resin types (polyester and epoxy) are widely used in
this method of pipe rehabilitation. Both these resins are
liquid thermosetting resins, and have excellent resistance
to domestic wast ewater. Chemical resistance tests should
be specified forCIPP forotherthan domestic wastewater
in accordance with ASTM F1216x2. Vinylester resins
may be used where superior corrosion  resistance is
required at high temperatures. Epoxy resins are used
where adhesion to the existing pipeline is desired.
Table 6-8.        Advantages and Disadvantages of Cured-ln-
                Place Unlng

Advantages	Disadvantages	
                                Bypass required during
                                installation

                                Post-installation remote
                                camera inspection required

                                Maximum effluent
                                temperature 82°C (180°F)
                                using specially formulated
                                resins
Applicable to all shapes


Rapid installation


Minimum traffic disruption




Excavation normally not required

In-line lateral reconnections

Improved hydraulics

Bridges gaps and misaligned joints

Special resins are available
to provide acid resistance.

Custom designed wall thickness
to aid in structural strength

Only 50-70 percent of
replacement costs

Adds some structural integrity

Does not interfere with or
damage other utilities

No pavement repairs

Safer than some other rehabilitation methods.
                                          Inversion lining is successful in dealing with a number of
                                          structural problems, particularly in sewers needing minor
                                          structural reinforcement. Caution must beused, however,
                                          in the application of this method to any structural problems
                                          involving major loss of pipe wall. Inversion lining can be
                                          accomplished relatively quickly  and without  excavation
                                          and thusthis method ofpipeline rehabilitation is particularly
                                          well suited for repairing pipelines located under existing
                                          structures, large trees,  or busy  streets  or highways
                                          where traffic disruption  must be  minimized. Inversion
                                          lining produces minor reductions in pipe cross-sections.
                                          It is  applicable to  non-circular pipes and  pipes with
                                          irregular cross-sections.  This method is also effective in
                                          correcting corrosion  problems  and can  be used  for
                                          misaligned pipelines or  in pipelines with bends where
                                          realignment or additional access is not required. See
                                          Table 6-8 for a summary of the advantages and
                                                       73

-------
disadvantages of sewer rehabilitation by cured-in-place
lining.

There are currently three processes that have been
introduced in the United States that are classified as
cured-in-place: Ins'rtuform, Pattern, and KM Inliner.

6.5.1.1 Insltuform
The Ins'rtuform process was developed in England in the
early seventies. Since its introduction in the United
Statesln 1978, approximately 2,400 linear km (8,000,000
ft) have been installed in a variety of piping applications.
Third party  testing has been performed  by several
agencies verifying structural properties, design methods,
corrosion resistance and the ability to enhance, flow
capacity. The process has been used on circular and non
circular pipes in diameters of 10-275 cm (4-108 in). The
maximum installation length is approximately 360-750 m
(1,200-2,500 ft)  depending  on the diameter and wall
thickness. ASTM F-1216-89, as well as other national
and federal specifications, specifically  covers the
Ins'rtuform process. The Insrtuform process is  installed
throughout the United States by a network of  licensed
instaiters. Ins'rtuform tubes are manufactured inthe United
States by Ins'rtuform of North America, Inc.

6.5.1 £ Pattern
PaRem (Pipeline Automatic Lining System) wasdeveloped
in Japan through a joint venture between Tokyo Gas and
a private company, Ashimori Industries, for rehabilitating
natural gas  lines.  Since being brought to the United
States in 1988, there have been various demonstration
projects and some full-scale municipal sewer projects.
The published  size range is 2-100 cm (0.75-40 in);
however, in the United States, 10-60 cm  (4-24 in) is
available for gravity flow sanitary sewer work. Although
information  is  available through  the parent company
relevant to physical testing, at this time there appears to
be no third party documentation for the Pattern system.
The specifications covering this process is included in
ASTM F-1216.

6.5.1.3 KM Inliner n
TheKMInlinerprocess was developed in West Germany
by the Kanal Mueller Gruppe in 1985. It has been
marketed in  the United States since 1988. The material
is being manufactured in Germany; however, there are
plans to establish a manufacturing facility in the eastern
United States. Diameters of 20-60 cm (8-24 in) can be
reconstructed using this process, and there are indications
that pipes up to 90 cm (36 in) may be available sometime
in the future. The  maximum  installation length is
approximately 180 m (600 ft). Application for inclusion in
ASTM F-1216 was made in 1990 and is still pending.
There is no third party testing available verifying the
Table 6-8.
RehabCostsforCured-livPlacelnveislon Lining
Pipe
Diameter
(in)
6
10
14
18
21
24
27
30
33
36
42
48
54
60
Dec. 1984
ENRCCI=4144
($/LF)
25-40
49-65
65-105
75-125
85-135
95-165
105-175
115-190
120-215
130-230
140-265
160-300
175-335
185-375
Mar. 1991
ENRCCI=4773
($/LF)
30-45
60-75
75-125
90-145
100-160
110-190
125-205
135 - 220
140-250
155-270
165 - 305
185-350
205-390
215-435
  Costs are based on minimum project size of 300 m (1,000 LF).
  1984 costs from Reference 3; 1991 costs based on adjusted 1984
  costs.
  Costs do not include providing temporary water or natural gas service
  for the curing process, design construction management, or design
  related services.
physical properties or design parameters used for this
process.

6.5.2  Procedures and Equipment
Installation of cured-in-place inversion lining is carried
out by inserting the resin-impregnated fabric tube (turned
inside out) into the existing pipe line and inverting it as it
progresses inside the pipe. It is then  cured in place
through the use of heated water or air steam. Prior to the
installation of the liner, the pipeline section must be
cleaned to remove loose debris, roots, protruding service
connections, and excessive solids. The preparation and
installation procedures are illustrated in Figure 6-3.1 The
pipeline segment must be isolated from the system by
bypassing flows during the installation of the inversion
lining. The inversion felt tube liner is usually inserted from
existing manholes. Following curing of the liner, the ends
are cut and sealed and service connections are restored.

6.5.3   Costs

See Table 6-9 for approximatecostsof sewer rehabilitation
by cured-in-place inversion lining. The costs in these
tables are based on costs taken from Utility Infrastructure
Rehabilitation3 and were adjusted to current pricesthrough
the use of a cost index. Costs were also  verified by
contacting vendors and contractors.
                                                    74

-------
Figure 6-3.       Installation of Cured-ln-PIace inversion lining (Insituform).
                       STEP 1
                          RESIN
                      IMPREGNATED
                       INSITUTUBE©
INVERSION TUBE
    I   I
  MANHOLE
                                                          75

-------
6.6    Fold and Formed

This process uses a folded thermoplastic (PE or PVC)
pipe that is pulled into place and is then rounded to
conformtothe internal diameterof the existing pipe. This
method of pipe rehabilitation can be considered as an
improved version of sliplining. Excavation is not required
for installation when there are existing manhole access
points, and lateral  reinstatement  is accomplished
internally. The finished pipe has no joints and produces
a  moderately-tight fit to the existing pipe wall. This
method of pipe rehabilitation is less versatile than cured-
in-place  methods in terms of diameter range .and
installation length. Only slight offsets and bends can be
negotiated.

The  fotd and formed  method of rehabilitation does not
require a long curing process in terms of speed of
installation. This process of rehabilitation has been canied
out in the United States for the last 2-3 years.There are
currently two fold and formed processes commercially
available in the  United States: U-Liner and .NuPipe.
Some municipalities  have tried them for experimental
and  evaluation purposes. Fold and formed method of
pipeline rehabilitation are suitable for pipe diameters of
10-40 cm (4-16 in) with typical lengths of installation of
90-180 linear m (300-600 ft). Fold and formed technology
is currently being developed for 60-cm (24-in) diameter
pipe. Butt-fused U-Liner pipe can be used for lengths up
to the stress-resistant pull force of the material.

6.6.1  U-Liner
The  U-Liner technology was developed by Pipe Liners
Inc.  of New Orleans  with the  pipe  material being
manufactured in the United  States  by Quail Pipe
Corporation of Roaring Springs, Texas. The U-Liner
manufacturing process is specified by ASTM as deformed
HPDE. This  rehabilitation  technology has  been
commercially available in the United States since 1988.

High density  polyethylene  resin conforming to  the
requirements of ASTM 1248, Type III, ClassC, Category
5, Grade P34, is used, and it is currently available in SDR
32.5, 26  and 21. The selection of the appropriate wall
thickness will depend on the particular loading conditions
from project to project. U-Liner is extruded as round pipe,
conforming to ASTM  D-3350, and then through a
combination of heat and pressure, is deformed into the
"U"  shape.  It  is  then wound onto spools ready for
installation. This technology is currently applicable for
pipe sizes of  10-40  cm (4-16 in). Approximately  100
linear km (350,000 ft) of pipe has been installed in the
U.S. by U-Liner Licensees. The U-Liner polyethylene
material has  been independently tested for material
strength and physical properties and has been accepted
in the Standard Specifications for Public Works
Construction.6

The  installation of U-Liner is  basically a  three step
process. After cleaning and TV inspection and analysis
to identify defects and to determine the applicability of U-
Liner, the first step includes winching of a pre-engineered
seamless coil of pipe of a precut length into place. The
pipe is pulled  off the spool  at ambient temperature, fed
through an existing manhole, and is winched through the
existing pipe to the terminal point. Once it is in place,
steam  is fed through the inside of the folded pipe,
softening the plastic to allow for the reforming process.
Installation in  pipes below the water table may make it
difficult to heat the plastic sufficiently due to groundwater
entering the  system which  will  coo) the  plastic.
Temperatures of 110-130°C (235-270°F) are  used to
soften  the  plastic. A  diagram depicting the  U-Liner
installation procedure is presented in Figure 6-4. After
the plastic has been heated, pressure is used to reround
the pipe. The rerounding of the pipe occurs simultaneously
from end to end and may trap water or air in between the
U-Liner and the host  pipe. The  pressure required to
reround the pipe will vary, depending on the wall thickness,
between 170 and 240 kPa  (25 and 35 psi).

Due to the relatively high coefficient of thermal expansion
of polyethylene combined with the extreme temperature
changes associated with the process, sufficient time
should be allowed for the system to  stabilize before
laterals are reinstated and end treatment  is finished.
Laterals are recut utilizing a remote-controlled cutter
head, in conjunction with a TV camera.

6.6.2   NuPipe
The NuPipe process was developed in the U.S. and has
been commercially  available since  1990.  NuPipe is
manufactured from  PVC and is  extruded in a folded
shape. While  it is still pliable, the folded PVC is wound
onto spools. It is currently available in 15-30 cm (6-12 in)
in SDR 35. Third party testing has shown that SDR 35 is
capable of withstanding nearly all loading conditions
experienced in buried pipelines.7 The resin composition
conforms to ASTM 1784, cell class 12454-B or 12454-C
and the  installed pipe  meets the performance
requirements of ASTM  D-3034 which is standard
specification  for direct  bury PVC  pipe.  As with
polyethylene, the corrosion resistanceof PVC is excellent.

The installation of NuPipe includes cleaning of existing
host pipe along with a TV  inspection to determine the
extent of deterioration and to verily the applicability of
NuPipe.  A flexible  reinforced liner called the Heat
                                                   76

-------
6.6    Fold and Formed

This process uses a folded thermoplastic (PE or PVC)
pipe that is  pulled into place and is then rounded to
conform to the internal diameter of the existing pipe. This
method of pipe rehabilitation can be considered as an
improved version of sliplining. Excavation is not required
for installation  when there are existing manhole acess
points, and lateral  reinstatement  is accomplished
internally. The finished pipe has no joints and produces
a  moderately-tight fit to  the existing pipe wall.  This
method of pipe rehabilitation is less versatile than cured-
in-place  methods in terms of diameter range and
installation length. Only slight offsets and bends can be
negotiated.

The fold and formed  method of rehabilitation does not
require a long curing  process in terms of speed of
installation. This process of rehabilitation has been carried
out in the United States for the last 2-3 years. There are
currently  two fold and formed processes commercially
available in  the United States: U-Liner and NuPipe.
Some municipalities  have tried them for experimental
and evaluation purposes.  Fold and formed method of
pipeline rehabilitation are  suitable for pipe diameters of
10-40 cm (4-16 in) with typical lengths of installation of
90-180 linear m (300-600 ft). Fold and formed technology
is currently being developed for 60-cm (24-in) diameter
pipe. Butt-fused U-Liner pipe can be used for lengths up
to the stress-resistant pull force of the material.

6.6.1  U-Liner
The U-Liner technology was developed by Pipe Liners
Inc.  of New Orleans  with the pipe material being
manufactured  in the  United States by Quail  Pipe
Corporation  of Roaring Springs, Texas. The  U-Liner
manufacturing process is specified by ASTM as deformed
HPDE.  This  rehabilitation technology has  been
commercially available in the United States since  1988.

High density  polyethylene resin conforming to the
requirements of ASTM 1248, Type III, Class C, Category
5, Grade P34, is used, and it is currently available in SDR
32.5, 26 and 21. The selection of the appropriate wall
thickness will depend on the particular loading conditions
from project to project. U-Liner is extruded as round pipe,
conforming  to  ASTM  D-3350, and then through a
combination of heat and pressure, is deformed into the
"U" shape.  It  is then  wound onto  spools  ready for
installation. This technology is currently applicable for
pipe sizes of 10-40 cm (4-16 in). Approximately 100
linear krn (350,000 ft) of pipe has been installed in the
U.S. by U-Liner Licensees. The U-Liner polyethylene
material has been independently tested  for material
strength and physical properties and has been accepted
in the  Standard Specifications for Public  Works
Construction.6

The installation  of U-Liner is basically a three step
process. After cleaning and TV inspection and analysis
to identify defects and to determine the applicability of U-
Liner, the first step includes winching of a pre-engineered
seamless coil of pipe of a precut length into place. The
pipe is pulled off the spool at ambient temperature, fed
through an existing manhole, and is winched through the
existing pipe to the terminal  point. Once it is in place,
steam  is fed through the inside of the folded pipe,
softening the plastic to allow for the reforming process.
Temperatures of 110-130°C (235-270°F)  are used to
soften  the  plastic. A  diagram  depicting  the  U-Liner
installation procedure is presented in Figure 6-4. After
the plastic has been heated, pressure is used to reround
the pipe. The pressure required to reround the pipe will
vary, depending on the wall thickness, between 170 and
240 kPa (25 and 35 psi).

Due to the relatively high coefficient of thermal expansion
of polyethylene combined with the extreme temperature
changes associated with the process, sufficient time
should be allowed for the system  to stabilize  before
laterals are  reinstated and end treatment is finished.
Laterals are recut utilizing a remotee-controlled  ..cutter
head, in conjunction with a TV camera.

6.6.2  NuPipe
The NuPipe process was developed in the U.S. and has
been commercially  available since 1990. NuPipe is
manufactured from PVC  and is extruded in a folded
shape. While it is still pliable, the folded PVC is  wound
onto spools.  It is currently available in 15-30,cm (6-12 in)
in SDR 35. Third party testing has shown that SDR 35 is
capable of withstanding nearly all  loading conditions
experienced in buried pipelines.7 The resin composition
conforms to ASTM 1784, cell class 12454-B or 12454-C
and the installed  pipe  meets the performance
requirements  of  ASTM  D-3034 which is standard
specification  for direct bury PVC pipe. As with
polyethylene, the corrosion resistance of PVC is excellent.

The installation of NuPipe includes cleaning of existing
host pipe along with a TV inspection to determine the
extent of deterioration  and to verify the applicability of
NuPipe. A flexible  reinforced  liner called  the Heat
                                                   76
                                   (Revised 4/94)

-------

-------
 Figure 6-4.
U-Uner installation method.
                                                                Power, Steam/Pressure Generation,
                                                                    Studio Operating Room
   Winch Pulls Pipe
         Coil
     Steam, Pressure,
       Temperature
      Instrumentation
    Hydraulic Advantage
    Gradual Transition
                                                                                             Steam,
                                                                                            Pressure
                                                                                       000   Injector
                                                            Lateral recognized
                                                            for Remote Cutting
                                  Restored Broken Pipe
                                                                                         End Restrained
Containment Tube (HCT) is inserted into the host pipe.
The HCT provides a closed environment in which the
NuPipe is installed and processed. After the HCT has
been strung through the host pipe. The folded PVC is
heated while on the spool and is pulled through the host
pipe. Heating the plastic reduces the forces required to
pull the pipe in place. Once the folded NuPipe reaches
thetermination point, steam is introduced into the system
both through the interior and around the exterior of the
folded pipe. The use of the HCT also allows for heating
both sides of the plastic to provide complete heat transfer
through the pipe wall which minimizes the effect of
infiltrating water. After  the PVC becomes pliable, a
rounding device is introduced into one end of the pipe
which is then propelled through the folded pipe. The
rounding device progressively rounds the NuPipe, moving
standing water out of the way while also expanding the
plastic tightly against the host pipe, creating a mechanical
lock at joints and laterals. Approximately 35-70 kPa (5-10
psi) is needed to propel the rounding device. Cold water
is then injected into the Nu Pipe effectively quenching the
plastic. The installation process is shown in Figure 6-5.

6.6.3   Costs
The costs of U-Liner and NuPipe are not well established
due to the recent entry of these two technologies into the
sewer rehabilitation field. The cost of Fold and Formed
                                       installations vary widely in different geographic regions of
                                       the country depending on availability of materials,
                                       availability  and experience of installation  contractors,
                                       level of competition, and length and loading condition of
                                       the sewers to be rehabilitated.

                                       Review of limited competetive bid prices received from
                                       Pipe Liners, Inc. for U-Line indicates a price range of $60-
                                       78/LF for 20- to 30-cm (8-12-in) diameter pipe, including
                                       cleaning. Laterial reinstatement costs were reported to
                                       range from  $200 to $216/unit. Price information was not
                                       available from NuPipe.

                                       Engineers  and municipalities  considering  Fold and
                                       Formed technologies are encouraged to  contact  the
                                       manufacturer and local installers of thetechnology and to
                                       review installation costs for recently-installed projects in
                                       their locality.

                                       6.7    Specialty Concrete1

                                       6.7.1  Description
                                       Specialty concretescontaining sulfate resistant additives
                                       such as potassium silicate and calcium aluminate have
                                       shown greater resistance than typical concrete to  acidic
                                       attack on sewer pipes and manhole structures.
                                                     77

-------
Flflur* 6>5.        NuPlpfl Installation method.
                                                                78

-------
Table 6-10.
Advantages
Advantages and Disadvantages of Specialty
Concretes
Cement Mortar
• Minimal service interruption

• Improved structural integrity

• Applicable for wide range of
  pipe sizes
Shotcrete
• Minimal excavation required
  Access is through manholes
• Can restore structural
  integrity to a pipe that
  would otherwise require
  replacement
• Minimum traffic interruptions
• Applicable to all shapes of
  man-entry size pipes
Cast Concrete
• Established procedure
• Simple to design
• Applicable to all shapes of
  pipes
                Excavation required for sharp
                ends or curves
                Cannot be done in winter if
                freezing potential exists
                Bypass required
                Extensive surface
                preparation required
                (e.g., chipping, sandblasting)
                Access holes required every
                150-210 m (500-700 ft)
                Concrete shelf life must be
                tracked for the project duration
                Transportation cost
                higher for concrete
                May not provide adequate
                corrosion resistance
                Extensive surface
                preparation required
                Extended downtime period
                of 3-7 days or longer
                required for cleaning
                Some reduction in
                hydraulic capacity
                Limited to man-entry
                size structures
                Concrete shelf life to be
                tracked for project duration
                Transportation cost high
                for concrete
                May not provide 'adequate
                corrosion resistance.
                Cleaning required
                Bypass required
                Seldom applicable to pipes
                less ttian 1.2m (4 ft) in
                diameter
                Concrete shelf life to be
                tracked for project duration
                Transportation cost high for
                concrete
                May not provide adequate
                corrosion resistance
Specialty concrete isusedtoreinforce weakened concrete
pipes and structures by applying an acid resistant coating
over the original surface. Specialty concretes are unique
in that their matrix is not formed by a hydration reaction.
Rather, they are the result of the  reaction of an acid
reagent with an alkaline solution of a ceramic polymer of
potassium  silicate. Portland cement releases calcium
hydroxide  during hardening whereas the  specialty
cements  do not release calcium hydroxide.  Specialty
cements can resist attack by many substances including
mineral salts, mild solutions of organic and mineral acids,
sugar solutions, fats and oils. Acid reagents used in some
cases are also effective bactericides.1

Applicability of specialty concrete depends on the degree
of corrosion-related deterioration  and the  structural
integrity of  the sewer. Thin film  specialty concrete is
applicable to  mildly deteriorated pipes or  structure,
whereas  an  elastic membrane concrete system is
applicable to all cases. After curing, the specialty concrete
bonds firmly to  the original surface. The new acid-
resistant layer, if applied and cured properly, extends the
useful life of the structure. Advantages and disadvantages
of specialty concretes are listed in Table 6-10.

6.7.2   Procedures and Equipment
Specialty concretes are available in three types: cement
mortar, shotcrete, and cast concrete. Acid resistant
mortars have been used in industry as linings in tanks or
as mortar bricks. Development  of mechanical in-line
application methods (centrifugal and mandrel)  has
established mortar  lining  as a successful and viable
rehabilitation technique for sewer lines, manholes  and
other structures.

Mortar lining is applied using a centrifugal lining machine.
The machine has a revolving, mortar-dispensing head
with trowels on the backto smooth the mortar immediately
after application. In smaller diameter pipes a variable
speed winch pulls the lining machine through a supply
hose. Reinforcement can also  be added to the mortar
with a reinforcing spiral-wound rod. The reinforcing rod is
inserted into the fresh mortar and a second coat is
applied over it. For man-entry structures the mortar can
be applied manually with a trowel.

Shotcrete, sometimes referred to as gunite, is a low-
moisture, high-density mixture of fine aggregate (particle
size of 19 mm [0.75 in] and smaller), cement and water;
solids to liquid mix ratios are typically 5:1. Well placed
shotcrete has a high modules of elasticity (greater than
4 million  psi)  and a coefficient of thermal expansion
similar  to that of low carbon steel. Bonding with the
original surface is usually stronger than the base material
itself, with  better adhesion occurring  with  the more
deteriorated and irregular existing pipe. Shotcrete is
applied to a minimum thickness of 5 cm (2 in). Shotcrete
is used in  man-entry  size sewers (81 cm  [32 in] or
greater) and manholes. Prior to shotcreting, reinforcing
steel is set into place. The shotcrete lining machine is self
propelled and controlled by a person riding it. Mortar is
supplied to an electrically driven supply cart that conveys
mortar  from the access hole  to the feeder which is
attached to the lining machine. The dry specialty cement
                                                       79

-------
Table 6-11.      Costa for  Rehabilitation Using Specialty
               Concretes

                 Repair Cost     Repair Cost     Cost to
Item           Severely Corroded Mildly Corroded  Apply to
                 Concrete '	Concrete   New Concrete

Cement with
Polymer Unlng
Cement with add
Proof Concrete
Cement with urethane
Membrane
(5/sqft)
16-18
22-27
22-27
($/sqtt)
9-11
16-19
16-19
($/sqft)
5-6
16-19
16-19
• Mildly Corroded - Loss than 19-mm (3/4-In) loss of concrete. No
  reinforcement attack.
• Severely Corroded - Greater than 19-mm (3/4-ln) concrete loss. May
  require replacement of reinforcement
• Costs Include Installation.
• Costs obtained from Report to Congress: Sulffde Corrosion In
  Wastewatar Collection and Treatment Systems1.
and aggregate is mixed with water in a specially designed
spray nozzle. Hydration occurs, and the resulting mixture
is shot into place under pressure. Curing occurs under
moist conditions for the first 24 hours and an additional
six days at a temperature above 4°C (40°F).

Cast concretes are potassium silicate bonded, poured or
cast in place structural concretes. They typically have
half the in-place density or strength value of shotcrete.
Solids to liquid mix ratios are generally 2:1, similar to
cement mortar.

Cast concrete is poured over prefabricated or hand built
interior pipe forms that can be removed and reused
sectkm by section. Reinforcing steel is added between
the original surface and the form, setting within the cured
thickness.

Each of the three application techniques requires prior
cleaning to remove oils, greases, foreign objects, and
loose materials, as well as wastewater bypass during
application and initial curing.

6.7.3   Costs
Table 6-11 provides typical costs for the three types of
specialty concrete.1 The costs in this table were obtained
itomReportto Congress: Sulfide Corrosion in Wastewater
Collection and Treatment Systems'1 and were adjusted to
current pricesthrough the use of acost index. Costs were
also verified by contacting vendors and contractors.

6.8     Liners1
6.8.1   Description
Rehabilitation techniques using liners include the
installation of prefabricated panels or flexible sheets on
the existing structure usually with anchorboltsorconcrete
penetrating nails shot into place. The following materials
of liners are available for rehabilitation purposes1:'

• PVC liners
• PE liners
• Segmented, fiberglass reinforced plastic liners
• Segmented, fiberglass reinforced cement liners

PVC liners are manufactured from acid-resistant, rigid
unplasticized PVC which has excellent resistance to
acids and also is initially conductive to better hydraulics
than concrete. The liner is composed of high molecular
weight vinyl chloride resins combined with chemical-
resistant plasticizers. The completely inert mixture is
extruded under pressure and temperature  into a liner
plate with a minimum thickness of 1.6 mm (0.065 in). The
liners are pin-hole free, forming  an effective barrier to
gaseous penetration.

PE liners are similar to PVC liners but  are made of
polyethylene resins. These liners are tough, rigid, acid-
resistance, smooth and inexpensive.

Fiberglass reinforced plastic liners are manufactured in
a range of wall thicknesses and consist of a composite of
fiberglass and acid-resistant resin. The resins are specified
according to the degree of acid resistance required. The
composite has high mechanical and Impact strength and
good abrasion  resistance.  These liners  can be
manufactured to a wide variety of  shapes and are
applicable to sewers over 107 cm (42 in) in  diameter.

These liners do  not provide any structural support but
they do provide an adequatecorrosive barrier and smooth
lining for structurally sound sewers. These  liners have
little absorption and no apparent  permeability.

Fiberglass reinforced cement liners consist of cement
and glass fibers. They usually are 9.8 mm (0.385 in) thick
and are in thin panel form. They  have high  mechanical
and impact strength and good acid and alkaline resistance.
They are also highly resistant to abrasion with negligible
absorption and permeability. These liners are not designed
to support earth loads and  should be  used only in
structurally  sound sewers. The  liners can be easily
assembled to fit variations in grades, slopes and cross-
section. The smooth interior surface improves hydraulic
capabilities. These liners can be used in circular, oval,
rectangular and other sewer shapes above  107 cm (42
in)  in normal size and can be  segmented to fit the
diameter required.
                                                     80

-------
                              Table 6-12.        Advantages and Disadvantages of Liners

                              Advantages  	            Disadvantages	
                                Material cost inexpensive
                                Liner materials have very
                                good acid resistance

                                No disruptions to traffic
                                as installation is performed
                                entirely in-line

                                Smooth surfaces provide
                                good hydraulics
                                                Applicable only to man entry
                                                size sewers (i.e., 76 cm [2.5 ft]
                                                or greater)

                                                Susceptible to leakage
                                                due to number of joints

                                                Timely to install. Thus
                                                total project cost may be
                                                uneconomical.

                                                Prolonged bypass required

                                                Surface preparation required

                                                PE can crack in areas of
                                                turbulent flow
Figure 6-6.
Detail of liners with anchors.
                                 Extruded Anchors
                                   9.5-mm High
                           Concrete Poured in Form
                            Flexible PVC Membrane
                                 1.5-mm Thick
                                                                       •  O
                                                                81

-------
                                                        Tablo 6-13.
Advantages and disadvantages of liners as a sewer
rehabilitation technique are listed in Table 6-12.

6.8.2   Procedures and Equipment
Segmented  plastic  and fiberglass reinforced cement
liners are installed so they overlap at the joints and are
then attached to the concrete surface by anchor bolts or
nails. Space is left between the existing surface and the
linersforgrouting purposes. After athorough line cleaning
and dewatering, the segments are installed in 2.4-m (4-
ft) lengths which overlap at the joints, and the flanges on
the segments may be pre-drilled for filling by screws or
impact nail gun. Joints are coated with an  adhesive to
better connect  panels and are sealed with an  acid
resistant resin. After all the panels are set in place, the
entire section is cement pressure grouted in place to
prevent  sagging and  deformation. Some liners are
installed in conjunction with the casting of concrete by
placing the liners against the inner surface of the form
prfor to  pouring. Anchors become embedded  in the
concreteduring curing, thereby securing the liner in place
(see Figure  6-6).1 Alternate installation procedures for
flexible PVC liners or ribbed sheets involve only grouting,
without anchor bolts or impact nails for attachment.
Installation of another type of liner requires an access pit
to fit the special winding machine that joins a male and
female PVC strip. This process is applicable to pipes up
to 76 cm (2.5 ft) in diameter. The latest liner installation
method uses an acid resistant mastic to fasten the sheets
directly to the sewer concrete surface. This technique
does not require grouting but requires thorough cleaning
prior to installation.

Liner failures can occur due to  leaking joints that allow
H2S gas or sulfuric acid to penetrate the liner materials
and attack the concrete substrate beneath. Linerfailures
have also been reported  in areas of high turbulence
where cracks developed. Cracking has been identified in
PE pipes and thus PE is not recommended in areas of
turbulent flows.

6.8.3   Costs
Table 6-13 gives approximate costs for rehabilitating
sewersbyliningthepipes with cement mortar orshotcrete
and Table 6-14 gives approximate costs for lining with
anchor liners. The costs in these tables are based on
costs taken from Utility Infrastructure Rehabilitation* and
were adjusted to current prices through the use of a cost
index. Costs were also verified by contacting vendors
and contractors.

6.9    Coatings
               Rehabilitation Costs for Lining with Cement
               Mortar and Shotcrete
Pipe 1984
Diameter ENRCCI=4144
(in)
Cement Mortar Lining
12
24
36
48
60
($/LF)

12-21
13-27
16-34
17-42
22-51
March 1991
ENRCCM773
($/LF)

15-25
15-30
20-40
20-50
25-60
  Costs are for cleaning and lining only.
  Valve rehab., bypass installation, pavement removal, etc., are not
  included.
  Costs are base contractor bids.
  1983 costs are from Reference 3; 1991 costs based on 1983 costs.
Reinforced Shotorete Unit Costs
  48                100-125
  54                115-150
  60                125-175
  66                135-185
  72                150-220
  84                176-250
  96                200 - 285
  108                225-315
                        115-145
                        135-175
                        145-205
                        160-215
                        175-255
                        205-290
                        230-330
                        260-365
  Based on minimum project size of 300 m (1,000 LF).
  1983 costs are from Reference 3; 1991 costs based on adjusted 1983
  costs.
  Costs apply to circular and non-circular pipe.
  Lower rates for existing pipe with good pipe alignment, no need for spot
  repair, and no significant groundwater.
  Higher costs for existing pipe with poor pipe alignment and some need
  for groundwater dewatering.
  Costs include cleaning of existing line; material, labor and equipment
  for reinforced shotcrete placement;  bypassing  of wastewater;
  restoration of up to 20 services; contractor mobilization and
  demobilization; bonds and insurance.
Table 6-14.
Rehabilitation Costs for Lining with Anchors
Unit Costs for PVC T-Lock Uners
Item

Black: 4 x 8 ft sheet
White:4x8ft sheet
Anchor liner 4-ft W x 20-ft L
Anchor 25-ft W x 20-tt L
1/16-in thick -48x50 in
3/32-in thick -48x50 in
1/8-in thick -48x50 in
3/16-in thick -48x25 in
April 1989
ENRCCI=4577
($)
60.80/each
60.80/each
1.90/sqft
2.25/sq ft
220/roll
300/roll
400/roll
325/roll
March 1991
ENRCCI=4773
($)
65/each '
65/each
2/sqft
2.35/sq ft
230/roll
320/roll
420/roll • %
340/roll
  Prices do not include primer and installation.
  Prices do not include any site work.
  1991 costs based on adjusted 1989 costs.
                                                       82

-------
Table 6-15.       Advantages and Disadvantages of Coatings

Advantages                    Disadvantages
                        Table 6-16.
               Costs for Rehabilitation Using Coatings
• Economical
  No disruption to traffic or
  other utilities

  Most are fast curing, some
  cure in less than one hour

  Quick to apply

  Can be applied to uneven
  surfaces
Applicable only to man-entry
sewers and manholes

Surface imperfections-
pinholes, blowholes

Poor bonding to vertical
or overhead surfaces

Bypass required

Surface preparation
required

Few contractor inexperience
with products

Surface repairs often required
prior to application

St'll a developing technology
6.9.1   Description
Coatings include a myriad c-proprietary materials including
coal tar epoxy, concrete sealers, epoxy, polyester, silicone,
urethane, and vinylester that can be applied by spray
machines or brushed onto a concrete surface. They are
intended to form an acid resistant layer that protects the
substrate concrete from corrosion. Coatings have been
applied to sewer pipes and manholes since the 1960's,
with mixed success. The lack of success is largely due to
the specification of coating materials on the basis of
manufacturer claims without actual field testing1. As a
result  of these findings,  rehabilitation  engineers are
recommending standard field testing of new products
prior to their  use. Some of  the  advantages  and
disadvantages involved with the use of coatings are
listed in Table 6-15.

6.9.2   Procedures and Equipment
Application  of coatings usually  includes the following
procedures:

• bypass of wastewater
• prepare/clean concrete surface
• allow concrete surface to dry
• apply coating by brush or spray (more than one coat is
  usually necessary)
• allow coating to cure
• remove bypass.
April 1989
Item ENRCC1=4577
Agatapoxy (Epoxy)
Agatapoxy Gel (Epoxy)
Plasite (Epoxy)
Sancon (Urethane)
($/sqft)
9-19
7
5
9
March 1991
ENRCCW773
, ($/sqft)
9-20
7.50
5.50
9.50
  Costs obtained from  Report to Congress: Sulfide Corrosion in
  Wastewatar Collection and Treatment Systems1.
  1991 costs based on adjusted 1989 costs.
Most coatings can be brush or spray applied. Spray
application requires3,000 psi, which isdoublethe pressure
used for conventional airless spraying.

Spraying is excellent for coating uneven surfaces and is
much faster than brush application methods for some
products.

6.9.3   Costs
Approximate costs for  various types of coatings are
shown in Table 6-16.

6.10   All Techniques for Manholes

6.10.1  Description of Materials, Equipment and
        Products
Sewer manholes require rehabilitation to prevent surface
water  inflow and groundwater infiltration, to repair
structural damage and to protect surfaces from damage
by corrosive substances. When rehabilitation methods
will not solve the problems cost-effectively, manhole
replacement should beconsidered. Selection ofaparticular
rehabilitation method  should consider the type of
problems,  physical characteristics of  the structure,
location,condition, age and type of original construction.4
Extent of successful manhole rehabilitation experiences
and cost should also be considered.

Manhole rehabilitation methods are directed at either: (1)
the frame and cover, or (2) the sidewall and base. The
following is a summary of manhole and base rehabilitation
methods.4'5 Advantages and  disadvantages for these
rehabilitation methods are presented in Table 6-17.

6.10.2  Description of Procedures
Manhole rehabilitation methods are directed at either: (1)
the frame  and cover, or (2)  the  sidewall and base.
Manhole frame and cover rehabilitation prevents surface
water (storm water runoff) from flowing into the manholes.
                                                     83

-------
Tabto 6-17.        Advantages and Disadvantages of Manhole and Sump Rehabilitation Methods'18

Method                                       Advantages                                   Disadvantages
FRAME ANO COVER
Stainless steel,
and neoprene washers
or corks In holes
fn covers.

Prefabricated ltd
Insert
Joint sealing tape

Hydraulic cement
Rates frame above
grade
Simple to install
When Installed properly It
prevents surface water, sand and
grit from entering manhole
through or around cover.

Simple tojinstafl

Provides strong waterproof
seal to stop infiltration
Minimizes inflow through
cover and frame.
Restricts natural venting
Requires perfect fit
for success.
Short service life.

Labor-intensive;
freeze thaw cycto may
reduce patch life.

Limited to areas outside of
street right-of-way.
S1DEWALLAND BASE
Epoxy or pdyurethane
coatings on Interior
Infiltration
Chemical grout
Structural liner
Hydraulic cement
Raise frame
SIDEWALL AND BASE
Epoxy or poryurethano
coatings on Interior
walls
Protects interior walls
against corrosion and
Can be very inexpensive
method for stopping
infiltration.

Provides structural
restoration; manholes requires
less disruption of traffic and
utilities than replacement;
longer service life than coatings.

Seals manhole frame in
place. Prevents infiltration
between frame and cone section.

Prevents surface water
inflow through manhole cover.
Protects wall from corrosion
and infiltration on structurally
sound manholes.
Requires structurally
sound and dry manhole surface walls
must be very dean prior
to application; short service life.

Short service life;
cannot predict amount of grout
required to eliminate infiltration.

Complex and easily installation
                                                                84

-------
Surface water from storm runoff, etc., can often flow into
the manholes through the holes in the cover lid, through
the annular space around the lid and the framed cover
and under the frame if it is improperly sealed. Manhole
frames and covers can be rehabilitated by the following
techniques:

• By  installing  stainless steel bolts with caulking
  compound  and neoprene washers or corks  to plug
  holes in the cover.
• By  installing a prefabricated lid  insert  between the
  frame and the cover. These plastic lids are resistant to
  corrosion and damage by su If uric acid or road oils. The
  lids come with gas relief and vacuum relief valves to
  allow gas escape. They prevent water, sand,  and grit
  from entering the manhole. The lids are easy to install,
  can fit any manhole, and require periodic maintenance
  to function properly.
• By installing a  resin based joint sealing tape between
  metal frame and cover. The sealing tape provides
  flexibility to seal imperfectly fitting surfaces and to
  move with ground shifting. These sealing tapes can be
  used for all types of manholes.
• Cracks and openings on the existing manhole/frame
  seals  are applied with  hydraulic  cement  and
  waterproofing epoxy.
• By  raising  the manhole frames to minimize flows
  through the frame covers.

Manhole sidewall  and base rehabilitation is primarily
done  to prevent infiltration of groundwater.  Casting or
patching can be used to rehabilitate structurally sound
sidewalls. Complete replacement should be carried out
for severely deteriorated manholes and bases. Manhole
steps also deteriorate frequently and they  should be
replaced. Manhole sidewall and base rehabilitation can
be carried out by the following procedures:

• By  applying epoxy, acrylic  or polyurethane based
  coatings to the interior wall of the manhole. These
  waterproof and corrosion resistant coatings can be
  applied to brick, block and precast concrete manholes
  and bases. The coatings are applied by towel brush or
  sprayer. Prior to coating application, the surfaces of
  the manhole walls should be cleaned and all leaks are
  plugged using patching or grouting materials.
• By applying chemical grout from interior walls to exterior
  walls to stop infiltration through cracks and holes.
• By inserting structural liners inside existing manholes.
  These liners are typically fiberglass of the reinforced
  polyester mortar type.

6.10.3  Costs
Manhole rehabilitation costs are provided in Table 6-18.
Table 6-18.      Rehabilitation Costs - Manhole Techniques

                                     March 1991
Item	ENRCCI=4773
                                        ($)

                                   540-835/manhole
                                   395-415/manhole
                                   395-430/manhole
                                  645-1,095/manhole
                                   415-645/manhole
                                  4,610 - 13,825/each
                                   1,200-2,395/each
                                     120-1,200/each
                                      240 - 360/each
                                      120-240/each
Chemical grouting*
Seal frames to corbels*
Chemically seal and plaster walls*
Raise manhole to grade*
Replace frame*
Insert structural liner*
Manhole replacement**
Manhole repair**
Raise manhole frame and cover**
Manhole cover replacement**
 * Costs based on Reference 3, Dec. 1984(ENRCCI=4144)adjustedto
  March 1991 (ENRCCI=4773).
 ** Costs based on Reference 2, Mid. 1974 (ENRCCM 991) adjusted to
  March 1991 (ENRCCM773).
6.11   Service Lateral Techniques

6.11.1 Description
Service laterals are the pipes that  connect building
sewers to the public sewer main. The service laterals
usually range in size from 7.5 to 15 cm (3-6 in) and are
often  laid at a uniform slope from the building to the
immediate vicinity of the main sewer. They can enter the
sewer at angles of 0-90 degrees from horizontal. For
many years the effect of leaking service connections
were considered insignificant because it was assumed
that most service connections were above the water
table and therefore subject to leakage only during periods
of excessive rainfall or high groundwater levels. Recent
studies indicate that a significant percent of infiltration in
any collection system is the result of service connection
defects such as cracked, broken or open-jointed pipes.
Service connections may also transport water from inflow
sources such as roof drains, cellar and foundation drains,
basement or subcellar sump pumps, and storm water
flows from commercial and industrial properties.  In a
national survey carried out by state and local agencies,
it was found  that  the estimated percentage of total
system infiltration from service laterals ranges from 30 to
as high as high as 95 percent in some cases.

6.11.2 Procedures and Equipment
Following are  the procedures and equipment used for
rehabilitating service laterals:

Chemical Grouting:  The following chemical grouting
methods are utilized:
                                                    85

-------
T«bl»$-18.
Service Lateral Rehabilitation Costs
Table 6-20.
Miscellaneous Additions I Rehabilitation Costs
Method
                          Unit Cost
                                          Item
Sealing (test and seal by Joint)

SllptWog

Add two way dean out

Air test
    Padal or entire lateral
    Lateral connection to main

ExfKtraHon test
    Partial or entire lateral

TV Inspection

Seal with chemical grout
    Lateral connection to main
    Remaining lateral

Replacement

Chemical Grouting
                          ($/lateral)

                            1,980

                            1,730

                             450
                              75
                             200
                              75

                             200



                             650
                             590-

                            2,880


                         460-1,155
                                       March 1991
                                      ENRCCI=4773
• Costs based on Reference 3, December 1984 (ENRCCU4144)
  adjusted to March 1991 (ENRCCI-4773).
Pump Full Method: Chemical grout is injected through
a conventional sealing packer from a sewer main into the
service connection to be grouted. The forced grout
surroundsthe pipe and a seal is formed afterthe gel has
set. Excessive grout is augured from the building sewer
and the sewer is returned to service afterthe sealing has
been accomplished.

Sewer Sausage Method: This method is similar to the
pump full method except that a tube is inverted into the
service connection before sealing to reduce the quantity
of grout to be used and to minimize the  amount of
cleaning required afterthe sealing has been completed.

Camera-Packer Method:This method utilizes a miniature
TV camera and a specialized sealing packer which is
pulled out while it is simultaneously repairing faults that
are  seen through the TV camera. The equipment is
House service pipe replacement
House service pipe repair
Roof leader drain disconnection
Foundation drain disconnection
Cellar drain disconnection
Area drain disconnection
Cross connection plugging
Drain from springs plugging
                           ($)

                    •I ,440-2,875 each
                      480-960 each
                      120-180 each
                     720-2,875 each
                      120-840 each
                      120-840 each
                     240 -1,200 each
                        1,200-5,990
  Costs based on Reference 2, Mid. 1974 (ENRCCI-1993) adjusted to
  March 1991 (ENRCCI=4773).
Table 6-21.       Sewer System Evaluation Survey Costs

                                        March 1991
	ENRCCI.4773
                                          ($/ft)

Physical Survey Costs                      0.35 - 0.60
Rainfall Simulation
Smoke testing                             0.35 - 0.75
Dyed water testing                          0.60 -1.20
Water flooding                             0.60-1.20
                                          Preparatory Cleaning
(Pipe Diameter, in)
6
8
10
12
15
18
21
24
30
36
Internal Inspection
(Pipe Diameter, in)
6
8
10
12
15
18
21
24
30
36

0.75-2.65
0.60-2.15
0.75-3.15
0.85-4.10
0.95-5.05
1.20-5.40
1.70-8.40
1.95-10.20
2.75-13.20
3.50-16.30


1.10-3.00
0.85-2.90
0.75-2.75
0.75 - 2.90
0.75-3.15
0.85-3.35
0.95-3.75
1.20-4.20
1.35-4.80
1.80-5.30
                                                            Costs based on Reference 2, Mid. 1974 (ENRCCM 991) adjusted to
                                                            March 1991 (ENRCCM773).
                                                        86

-------
Table 6-22.         Sewer  Pipe Problems with Applicable
                   Rehabilitation Methods
Problem
Rehabilitation Method
1.   Poor structural integrity
2. Significantly misaligned pipe

3. Additional sewer capacity needed

4. Most rehabilitation methods would
   reduce sewer capacity to
   unacceptable levels
5. Pipe is seriously damaged

6. Excessive infiltration in
   non-pressure pipes
7. Leaking pipe joints which are not
   badly offset or misaligned
8. Circumferential cracks
9. Small holes
10. Small radial cracks
11. Serious root problems
12. Severe corrosion
13. Damaged pipes under structures,
    large trees, or busy streets
14. Problems in non-circular pipes

15. Mildly deteriorated structure

16. Corrosion; structurally sound;
    diameters of 76 cm (2.5 ft) or
    greater
17. Corrosive or acidic wastes
18. Pipes with misalignment or bends
a. Excavation and
  replacement
b. Insertion
c. Some specialty concretes
a. Excavation and
  replacement
a. Excavation and
  replacement
a. Excavation and
  replacement

a. Excavation and
  replacement
a. Chemical grouting
  sliplining CIPL, etc.
a Chemical grouting, CIPL

a. Chemical grouting
a. Chemical grouting
a. Chemical grouting
a. Sliplining, CIPL
a. Sliplining, CIPL
b. Cured-in-placs inversion
  lining, sliplining
a. Cured-in-place inversion
  lining, sliplining, coatings
a. Cured-in-place inversion
  lining
a. Cured-in-place inversion
  lining
a. Uners, CIPL
b. Coatings

a. Sliplining
b. Specialty concretes
c. Uners
d. Coatings
e. Cured-in-place inversion
   lining
a. Cured-in-place inversion
  lining	
                                                                 87

-------
removed and the service connection returned to service
after the repairs are completed.

inversion Lining: This technique is similarto the sewer
main installation in that it involves the insertion of a resin-
impregnated flexible polyester felt liner into the service
line. No annular space is created between the liner and
the pipe that might result in infiltration migration. No prior
excavations are required to correct slight offsets. An
access point is always needed on the upstream side of.
the service connection line. A variation from the sewer
main installation istheuseofaspecialpressurechamber
to provide the  needed pressure to invert the fabric
materialsthroughthe service pipeline. Afterthe completion
of the curing process, the downstream end of the liner is
cut manually or via a remotely controlled cutting device
placed in the sewer main. The upstream end is trimmed
at the access point, restoring the sewer service.

6.11.3  Costs
Costs for rehabilitating service laterals are presented in
Table 6-19.

6.12   Miscellaneous Costs

6.12.1  Rehabilitation
There are miscellaneous rehabilitation costs which were
not covered by the other sections in this chapter. These
costs are based on costs taken from the Handbook for
Sewer System Evaluation and Rehabilitation* and are
presented in Table 6-20.

6.12JZ  Costs for Preliminary and I/I Analysis  and
       SSES
Approximate costs involved in preliminary analyses, I/I
analyses, and SSES's are given in Table 6-21.

6.13   Matrix of Problems and  Applicable
       Corrective Measures

Table 6-22 lists common problems in sewer pipes with
applicable rehabilitation method(s) for each.

6.14   References

When an NTIS number is cited in a reference,  that
reference is available from:

       National Technical Information Service
       5285 Port Royal Road
       Springfield, VA 22161
       (703) 487-4650
1.   Report to Congress: Hydrogen Sulfide Corrosion in
    Wastewater Collection and Treatment Systems.EPfiJ
    430/9-91/009. U.S. Environmental protection Agency,
    Office of Water, Washington, D.C. in preparation.

2.   Handbook for Sewer System Evaluation and
    Rehabilitation. EPA/430/9-75-021, Office of Water
    Program Operations, U.S. Environmental Protection
    Agency, Washington, D.C., 1975.

3:   Brown and  Caldwell.  Utility Infrastructure
    Rehabilitation. NTIS No. PB86-114642, Department
    of Housing and Urban Development, Washington,
    D.C., 1984.

4.   American Public Works Association. Sewer System
    Evaluation, Rehabilitation and New Construction: A
    Manual of Practice. EPA/600/2-77/017d, NTIS No.
    PB-279248. U.S. Environmental Protection Agency,
    Municipal environmental Research Laboratory, Office
    of Research and Development, Cincinnati,  Ohio,
    December 1977.

5.   Existing Sewer System Evaluation and Rehabilitation.
    ASCE Manuals of Reports on engineering Practice
    No. 62, WPCF Manual of Practice FD-6, American
    Society of Civil Engineers, Water Pollution Control
    Federation, 1983.

6.   American Public Works Association and Southern
    California Districts Associated General Contractors
    of California. Standard Specifications for Public Works
    Construction.^ 991.

7.   Structural Performance of NuPipe. Prof. Reynold K.
    Watkins, Civil and Environmental Engineering, Utah
    State University, Logan, Utah.

Additional Reading

Boyer, K.W. and V. Caballero. Rehabilitating Lakeland's
Western Trunk Sewer. Operations Forum: 17-19, July
1990.

Brennan, L.N., A.A. Doyle, R.C. Fedotoff, B.J. Schrock,
and M.P. Weber. Sewer System Rehabilitation Case
Histories. Presented at 58th Annua.l Conference of the
Water Pollution Control Federation, 1985.

Fernandez, R. B. Sewer Rehab Using a New Subarea
Method. Water/Engineering & Management 133:28-30,
February 1986.

Farmer, H. Sewer System Evaluation and Rehabilitation
Cost Estimates. Water & Sewage Works, April 30,1975.
                                                  88

-------
Farrar, R.R., K.R. Guthrie, and P.M. Hannan. Remote
Chemical Sealing of the Sewer House Lateral. No-Dig
1988, October 1988.

Hannan,  P.M. Cured-ln-Place Pipe: An End User
Assessment. ASTM Buried  Plastic Pipe Technology,
September 1990.

American Public Works Association. Control of Infiltration
and Inflow into Sewer System. 11022EFF 12/70, U.S.
EPA, Washington, DC, NTIS No. PB-200827 (1970).
                                                89

-------

-------
                                             Glossary
U.S. EPA
SRF
CDBG
CG85
PL-92-500
NASSCO
ENRCCI
ASCE
WPCF
Rll
LF
PVC
CFR
SSES
CWA
H2S
O&M
NOAA
WSSC
BOD
S02
DO
NIOSH
OSHA
Service
PE
ASTM
FRP
RTR
T-Lock

Infiltration
Inflow
I/I
United States Environmental Protection Agency
State Revolving Funds
Community Development Block Grant
Construction Grants 1985
Public Law 92-500
National Association of Sewer Service Companies
Engineering News Record Construction Cost Index
American Society of Civil Engineers
Water Pollution Control Federation
Rainfall Induced Infiltration
Linear foot
Polyvinylchloride
Code of Federal Regulations
Sewer System Evaluation Survey
Clean Water Act
Hydrogen  Sulfide
Operation  and Maintenance
National Oceanic and Atmospheric Association
Washington Suburban Sanitary Commission
Biological Oxygen  Demand
Sulfur Dioxide
Dissolved  Oxygen
National Institute of Occupational Safety and Health
Occupational Safety and Health Administration
LineSewer pipes that connect building sewers to public sewers
Polyethylene
American Standards for Testing of Materials
Fiberglass Reinforced Polyester
Reinforced Thermosetting Resins
Trade name for Ameron Liners

The water entering a sewer system and service connections from the ground, through such
means as, but not limited to, defective pipes, pipe joints, connections, or manhole walls.
Infiltration  does not include, and is distinguished from inflow.

The water discharged into a sewer system, including  service connections, from such
sources, as but not limited to, roof leaders, cellar, yard and area drains, foundation drains,
cooling water discharges, drains from springs and swampy areas, manhole covers, cross
connections from storm sewers and combined sewers, catch basins, storm sewers, surface
run-off, street wash waters, or drainage. Inflow does not include, and is distinguished from,
infiltration.

The total quantity of water from both infiltration and inflow without distinguishing the source.
                                                  91

-------
I/I Analysis


Excessive I/I



Combined Sewer


SSES



Storm Sewer


Sanitary Sewer


Rehabilitation




Preparatory Cleaning



Internal Inspection



Physical Survey



Rainfall Simulation
An engineering and if appropriate, an economic analysis demonstrating possible excessive
or non-excessive I/I.

The quantities of I/I which can  be economically eliminated from a sewer system by
rehabilitation, as determined by cost-effectiveness analysis that compares the costs for
correcting the  I/I condition with the total cost for transportation and treatment of the I/I.

A sewer intended to serve as a sanitary sewer and a storm sewer, or as an industrial sewer
and storm sewer.

Asystematic examination of the tributary sewer systems or subsections of the tributary sewer
systems that have demonstrated possibly excessive I/I. The examination will determine the
location, flow rate and cost of correction for each definable element of the total I/I problem.

A sewer intended to carry only storm waters, surface run-off, street wash waters, and
drainage.

A sewer intended to carry only sanitary and industrial  wastewatere from residences,
commercial buildings, industrial plants and institutions.

Repair workon sewer lines, manhole and other sewer system appu rtenainces that have been
determined to contain excessive I/I. The repair work may involve grouting of sewer pipe joints
or defects, sewer pipe relining, inversion an desliping, sewer pipe replacement and various
repairs or replacement of other sewer system appurtenances.

An activity of the sewer system evaluation survey. This activity involves adequate cleaning
of sewer lines prior to inspection. These  sewers were previously identified as potential
sections of excessive I/I.

An activity of thesewer system evaluation survey. This activity involves inspecting sewer
lines that have previously been cleaned.  Inspection may be accomplished by physical,
photographic and/or TV methods.

An activity of the sewer system evaluation survey. This activity involves determining specific
flow characteristics, groundwater levels and physical condition of the sewer system that had
previously been determined to certain possibly excessive I/I.

The activity of the sewer system evaluation survey. This activity involves determining the
impact of rainfall and/or run-off on the sewer system. Rainfall simulation may include dyed
water or water flooding of storm sewer sections, ponding areas, stream sections and ditches.
In addition, other techniques such as smoke testing and water sprinkling may be utilized.
* U.8. GOVERNMENT PRINTING OFFIC&1992-648-003/41821
                                                    92

-------