United States
             Environmental Protection
             Agency
                 Robert S. Kerr Environmental
                 Research Laboratory
                 Ada, OK 74820
&EPA
Research and Development  EPA/625/9-89/007

Injection Well
Mechanical Integrity

-------

-------
                                 EPA/625/9-89/007
                                    February 1990
             Injection Well
         Mechanical Integrity
              Jerry T.Thornhill
Robert S. Kerr Environmental Research Laboratory
     U.S. Environmental Protection Agency
            Ada, Oklahoma 74820
             Bobby G. Benefield
       Environmental Research Institute
            Ada, Oklahoma 74820
     Office of Research and Development
     U.S. Environmental Protection Agency
           Washington, DC 20460

-------
                         Disclaimer
   The information  in this document has been funded wholly or in
part by the United States Environmental Protection Agency. It has
been subjected to the Agency's peer and administrative review, and it
has been approved for publication as an EPA document.

-------
                            Abstract
Underground injection control regulations of the U.S. Environmental
Protection  Agency  (EPA) require that all injection wells  demonstrate
mechanical integrity,  which is defined as  no significant leak in the
casing, tubing  or packer; and no significant fluid movement into an
underground source  of drinking  water through vertical  channels
adjacent to the injection well bore.

    This initial research project, examining the question of mechanical
injection well  integrity,  was  conducted  by  the  Robert S.  Kerr
Environmental  Research Laboratory and funded  in 1981. The three-
phased project determined the state-of-the-art methods  available for
mechanical integrity testing of injection wells and field tested specific
analysis methods to determine their adequacy as mechanical integrity
tests.

   The first phase  of  the  project  resulted in a  separate  report
entitled,  "Methods for Determining the Mechanical Integrity of Class II
Injection Wells," EPA 600/2-84-121. The report represented state-of-
the-art  methods  available for determining  mechanical  integrity of
Class II wells. The technology described may also be applied to other
classes of injection  wells.

    The  second  and  third phases  of  study  involved  test  wells
constructed for mechanical integrity testing: "Logging Well  No; 1" to
test for channels in the cement behind the casing; "Logging Well Mo.
2" to  test for  channels  in the cement behind the casing and to
evaluate cement behind fiberglass  casing;  "Fiberglass Calibration
Well" for use in calibrating tools to free fiberglass casing; "Leak  Test
Well!' for developing  methods for testing the integrity of the tubing,
casing and  packer as well  as locating fluid movement  in channels
behind  the  casing; and  three monitoring  wells to  determine  fluid
movement and  pressure buildup as a result of injection.

    Channels covering 90, 60, 30, and 6 degrees of the 360 degree
circle described by the casing were built into the cement of Logging
Well No. 1,  and channels covering 30, 25, 20, 15 and 10 degrees of
the 360  degree circle described by  the casing were built into the
cement of  Logging Well  No.  2. Three generations  of logging tools
were  run in the logging wells:  the. "cement bond" tool  and  the
"cement evaluation" tool, in addition  to prototype tools that are not
yet available for commercial use.

-------
    None of the logging tools presently commercially available located
 any of the  6  degree channels in Logging Well No. 1. The "second
 generation" tools located all of the 30, 60, and  90 degree channels
 and a calibrated "cement bond" tool  with dual receiver 3-foot/5-foot
 spacing located all but one of the 30 degree and all of the 60 and 90
 degree channels.
    Results of tests in  Logging Well No.  2 indicate that none of the
 presently available tools  are capable of  evaluating cement behind
 fiberglass pipe. Initial indications  are  that some prototype tools are
 able to identify 10 degree channels on the steel casing; however, this
 is based on preliminary data and much more testing  must be done
 before definitive conclusions can be reached.
                   1        '   •                              •. !
    The tools must  be  calibrated  prior to  their use.  Industry  is
 encouraged to continue research  to  increase the sensitivity of the
 tools for mechanical integrity determinations.

    The Leak Test Well was designed to correspond generally to a
 typical  salt  water disposal well  used by  the petroleum industry.  It
 incorporates the use of surface casing, long string, tubing and packer.
 Additional modifications included two packers, a sliding sleeve on the
 injection tubing and a 2 3/8-inch tubing attached to the outside of the
 long string running to the surface. Flow into the well can be controlled
 so  that the  injected fluids are directed into  the 2 3/8-inch injection
 tubing, or to the 2 3/8-inch leak string. Return flows can be controlled
 from the 2 3/8-inch leak string and also from the annulus  of the 5 1/2-
 inch casing.
    A number of tests have been performed  on the Leak Test Well.
 These  include hydraulic  conductivity of  the  injection zond;  radial
 differential temperature  log; temperature log;  differential  temperature
 log; radioactive tracer survey;  noise log;  flow meter survey; oxygen
 activation techniques; volume-pressure relationships; effect of mud in
 the long string/surface casing annulus; down-hole TV; and pressure
 tests  using  compressed  gas.  Tests  planned for the  well include
 helium leak  test,  annulus  pressure  changes  resulting  from
temperature variances and a "mule tail" test.

    Three monitoring wells have been constructed to observe each of
the zones open to the Leak Test Well. Tests have been conducted
with pressure transducers  in the zones as injection was conducted to
determine lateral and vertical  movement within  the  zone  and well
bore.
                                IV

-------
                           Contents


 Abstract	   iii

 Figures  	  vii

 Tables	   ix

 Acknowledgments	   x

 Introduction	   1
 Mechanical Integrity Test Wells  	   2
    Logging Well No. 1  	   2
        Cement Evaluation  	   2
        Logging Tools  	   4
        Log Interpretation  	   5
    Logging Well No. 2	   8
        Cement Evaluation	   9
        Logging Tools	 .   9
    Well Logging Conclusions and Recommendations	   9
        Well Completion <	   9
        Logging Equipment  	   11
        Log Interpretation  	   15
    Leak Test Well  	   15
 Conclusions  	   21
 References  	   22

 Appendix A.  Logging Well Design Specifications and
                 Installation Procedures    	   23
    Logging Well No. 1		   23
        Logging Test Well Material Specifications	   23
        Detailed Description of Well Construction 	   23
           Log Interpretation	   29
    Logging Well No. 2  	   48
        Logging Test Well Material Specifications .........   48
        Detailed Description of Well Construction 	   48

Appendix B.  Leak Test Well Design and Testing
                 Criteria and Test Summaries  	   49
    Leak Test Well	   49
    Test Summaries	   52

-------

-------
                            Figures


Number                                                Page

  1.      Logging Well No. 1	   3
  2.      Cement bond tool - single transmitter/receiver	   5
  3.      Cement bond tool -
             single transmitter/dual receiver	   6
  4.      Second generation tool	   7
  5.      Composite wave form.  .  ..	   8
  6.      Field reference transit time	   9
  7.      Logging Well No. 2.	    10
  8.      Amplitude, chevron and free pipe	   .13
  9.      Tool riot centered	    14
 10.      Leak Test Well	    16
 11.      Injection well head and flow lines	    17
 12.      Monitoring Well No. 1	',	• •    18
 13.      Monitoring Well No. 2	    19
 14.      Monitoring Well No. 3	    20

A-1.      Preparing fiberglass with epoxy resin.   	    25
A-2.      Applying initial fiberglass layer	    26
A-3.      Completed channel - prior to using wire
            brush to remove excess	    27
A-4.      Removing excess fiberglass with wire brush	    28
A-5a.    Single receiver 3-ft spacing	    30
A-5b.    Single receiver 4-ft spacing	    31
A-5c.    Single receiver 5-ft spacing	 .    32
A-5d.    Dual-receiver 3-ft/5-ft spacing	    34
A-5e.    Second generation log - Company A.  . . .	    35

A-6a.    Single receiver 3-ft spacing.   . .	    36
A-6b.    Single receiver 4-ft spacing	    37
A-6c.    Single receiver 5-ft spacing	    39
A-6d.    Dual-receiver 3-ft/5-ft spacing	    40
A-6e.    Second generation log • Company B.	    41

A-7a.    Single receiver 3-ft spacing	    42
A-7b.    Single receiver 4-ft spacing	    44
A-7c.    Single-receiver 5-ft spacing	,  .. .    45
A-7d.    Dual-
-------
                    Figures (Continued)
Number
B-3.     CBL liquid flow test - Phase II ................   55
B-4.     Neutron activation tool liquid flow test - Phase I.   . .   59
B-5.     Neutron activation tool liquid flow test - Phase II.  . .   60
B-6.     Neutron activation tool liquid flow test - Phase III.   .   62
B-7.     Neutron activation tool liquid flow test - Phase IV.  .   63
B-8.     Testing for a hole in the long string ............   66
B-9.     Leak Test Well ..........................   70
B-10.   Neutron activation tool liquid flow test ..........   74
B-11.   Radial differential temperature  survey ....... ...   76
B-12.   RDT scan no-flow condition ......... '. ...... •   77
B-13.   RDT scan flow condition ...................   78
B-14,   Leak Test Well.  . . . ................... • • •   83
B-15.   Monitoring wells.  . .......  . ...............   84
B-16.   Standpipe ................. ............ •   87
B-17.   Pressure decline over time ................. •   90
B-18.   Changes in water level - 700-ft zone.   .........   92
B-19.   Changes in water level - 900-ft zone.   ... ......   94
B-20.   Leak Test Well ......................... •   97
B-21.   Atlas Wireline Services SONAN Leak Test Well.   ..   99
B-22.   Atlas Wireline Services SONAN Leak Test Well.   .   100
B-23.   Leak Test Well .................. .......   102
B-24.   Leak Test Well ..... ............... ......   104
B-25.   Gearhart Industries, Inc., continuous flow survey.    105
B-26.   Gearhart Industries, lnc;, continuous flow survey.    106-
B-27.   Gearhart Industries, Inc.,, continuous flow survey.    1 07
B-28.   Gearhart Industries, Inc., continuous flow survey.    108
B-29.   Leak Test Well ............... : ...... • • •   1 10
B-30.   Tracer runs showing fluid movement
            during injection at 1/2 bpm 300 psi ..... ...   111
B-31.   Slug #6 ejected at 1,1 25-ft channel down check.     112
B-32.   Slug #7 ejected at 1,1 25-ft channel down check.     113
B-33.   Leak Test Well ......... ... ........... '•• •   114
B-34:   Leak Test Well ....... . : ......... • • • • • ...   116
B-35.   Leak Test Well.  .....:.:... ..... . . • ---- •   118
B-36.   Leak Test Well;  ---- ............. ..... • •   122
                              VIII

-------
                           Tables
Number                                             Page

B-1.    Procedure for Drilling the Monitoring Wells  	   52
B-2.    Effects of Adding Pressure to Depress Water  ....   69
B-3.    Depth to Water in Monitoring Wells  	, .   84
B-4.    Water-Level Decline in Standpipe  	   87
B-5.    Pressure Decline Over Time	   89
B-6.    Flow through Profile Nipple  	   90
B-7.    Changes in Water Level  - Monitoring Wei). No. 1  . .   91
B-8.    Changes in Water Level  - Monitoring Well No. 2  . .   93
B-9.    Flow of Water (gpm) through Holes
           at Different Pressures	   94
B-10.    Leak Test Well - SONAN Data	   98
B-11.    Oxygen Activation Log Data, Leak Test Well -
           November 3, 1987	    119
B-12.    Oxygen Activation Log Data, Leak Test Well -
           September 14, 1988	    123

-------
                     Acknowledgments


    This report reflects  the work done to date on unique research
wells designed for testing  methods  of determining the mechanical
integrity of injection wells. The successful, design of the wells is due
to the time and effort which  an unusually able advisory  panel  was
willing to devote to the project.

    Grateful acknowledgment  is made to the advisory group for their
Contributions:

    Terry Anderson
    Halliburton Cementing Services

    Dick Angel
    Phillips Petroleum

    Al Bryant
    Schlumberger Well Service

    Mike Cantrell
    Oklahoma Basic Economy Corp.

    Cecil Hill
    Baker Packers

    Gene Littell
    Litteil and Randolph Engineering

    Tal Oden
    Oklahoma Corporation Commission

    R. C. Peckham
    U.S. EPA, Region VI

    Gary Batcheller,  Schlumberger Well Service, and  Alerdo  Maffi,
Tom Hansen Company,  both  made incalculable Contributions to the
project through  their advice,  encouragement and  participation  in a
training course for EPA and  State employees on October 16, 17 and
18,  1985.

-------
                          Introduction


    Underground injection control  regulations of the United  States
Environmental Protection Agency (U.S.  EPA) require that new
injection wells demonstrate mechanical integrity prior to operation and
all injection wells demonstrate such integrity at least every 5 years.

    The regulations state that an  injection well  has   mechanical
integrity if:          .

    (1)  There is no significant leak in the casing, tubing or packer.

    (2)  There is no significant fluid movement into an  underground
        source of drinking water through vertical channels adjacent to
        the injection well bore.

    The initial research project to examine the question of mechanical
integrity was funded July 1,  1981. The three-phased  project was to
determine the state-of-the-art for  mechanical  integrity testing  of
injection wells and  to test specific field methods to determine their
adequacy.

    The first phase of the project resulted in a report, "Methods  for
Determining  the  Mechanical  Integrity of Class  II Injection Wells."
Although this report represented the state-of-the-art for  determining
mechanical integrity for  Class II wells,  the technology  described may
be applied to other classes of injection wells.

-------
              Mechanical integrity Test wens


    The second and third phases of the project involved construction
and testing of wells designed to evaluate various tools and techniques
used  to determine mechanical integrity  of injection  wells. The test
wells  - two "logging  wells," a "leak test well,"  a "calibration Well,"
and three "monitoring wells" - were designed for developing methods
testing  the integrity of the tubing, casing and  packer; locating  fluid
movement in channels behind the casing;  and testing for channels in
the cement  behind the casing. The wells are located  on a 110-acre
site approximately 11 miles west of Ada, Oklahoma.

Logging Well No. 1
    The purpose of this well is to determine the present capability in
the industry for  evaluating  the  cement  bond   between  the
cement/casing and cement/formation coupling in injection  wells, and
to provide a test facility for evaluating new tools developed for cement
evaluation.
    After much discussion among members of the advisory group, it
was determined  that the  best method to simulate poor  cement
bonding, or  channels in  the cement, would be to attach water-filled
polyvinyl chloride  (PVC)  pipes to  the  outside of the casing.  Thus,
PVC pipe was attached to the  outside of the casing to cover either
90, 60,  30 or 6 degrees  of the  360 degree radial surface of the pipe
(Figure  1).
    Having installed the  "channels" on the casing,  attention  was
turned to a second vital factor in the  completion of this well, the
quality  of the cement job. The  planned  cementing  program was
designed  to  provide  the most favorable  conditions for obtaining
excellent bonding of the cement  to the  casing and coupling of the
cement to the formations, so  that the  "channels" identified  by the
logging  tools would be those purposely created for the project.

    A thorough review of  the logs run to evaluate the cement bonding
indicates that about 60 percent  of the well has good cement bonding
and provides an excellent facility  for determining the sensitivity of
various  down-hole  cement  evaluation  techniques.  The  other  40
percent of the well provides an opportunity for testing  techniques for
repairing channels in cement, and  for evaluating the success of the
repair efforts.

    The well  specifications,  along with a detailed description of the
installation process, are provided in Appendix A.

Cement Evaluation
    With the completion of the  well, the actual testing portion of the
project,  determining the present capability for evaluating the cement,

-------
                            12-1/4" dia borehole
 9 5/8-in dia
 easing
  8 5/8-in dia.
  casing
  7-in dia
  casing
  840-tt depth
  5 1/2-in dia.
  casing
 4 1/2-in dia
 casing











tt depth
^
\m m m •—
[• • * * * •
• •••••{
mmmmmm
mmmm.mm
••••••
m mmmmm
mmmmmm
••*•••
mmmmmu
•••ซ••
"H"

mm mmmm
t m mmmm
mmmm**
mmmmmm
mmmmmm
mmmmmm
mmmmmm
••••••
••••*•
••*•••














f-^tmmm
• • • •
• • • •
• • • •
• • • •
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mm m m
mmmm
• •••
••••
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mmmm
mm m
m m m
mmm
mmm
mmm
mmm
mmm
mmm
mmm
mmm

                                                           cement-filled annulus
                                                                       X
                                                                   formation wall
                                                             well casing
                            8 3/4-in dia borehole
Figure 1.    Logging Well No. 1.

-------
was  ready to proceed,  uontact was  mauซ wim as  many
companies as possible to determine the types of tools  that are being
used  for evaluating cement in a well  and to run  as many different
tools as possible in the well. At the initial contact with each company
contracted to log the well, the construction and purpose of the well
were  fully explained, except for the  location   of the  manmade
channels. Each company representative was also asked to provide a
complete  interpretation of the  condition  of the cement in the well,
based on  the  information from  the -company's   log,  prior to their
leaving the site.
    Nine  companies  have  produced  16 logs on the  well, two
companies have refused  to run a log on the well.

Logging Tools
    Basically, two  generations of logging tools have been run in the
well: the  "cement bond" tool, consisting of single transmitter/single
receiver  or  single  transmitter/dual  receivers;  and  the "cement
evaluation" tool which has eight ultrasonic transducers.

    The typical cement  bond tool presents a log with the following
data:  gamma-ray and casing  collar locator (CCL), which are included
for depth  control; transit  time (TT), which measures the time  it takes
for a  certain level sound wave to travel from the transmitter to the
receiver;  amplitude, which   measures  the  strength of  the first
compressional  cycle  of  the  returning sound wave;  and a  graphic
representation of the wave form, which displays the manner in which
the received sound wave varies  with time.  This representation  is
called variable density  log  (VDL), seismic spectrum,  or  micro-
seismogram, and is a function of the property of the material  through
which the signal is transmitted.
    There  are  various  transmitter/receiver  spacings  available, the
most  common being a single  transmitter with a single receiver located
3  feet away (Figure  2).  Other tools include the  single transmitter/
single receiver with 4-foot or 5-foot  spacing, or a single transmitter/
dual receiver with 3-foot/5-fobt spacing  (Figure 3).

    The  "second generation" tools for determining the adequacy  of
cement bonding  include  a tool having  eight ultrasonic  transducers
spiraled around it  to survey the circumference of  the  casing (Figure
4). The information presented on  the  log  from these  tools includes
casing ovality; average casing I.D.; casing collars; hole  deviation; fluid
velocity;  eccentering  of  the  tool; rotation  of the tool;  gamma-ray,
maximum and minimum cement compressive strength;  average of the
energy  returned  to all  eight transducers;  and cement distribution
around the casing.                     '

-------
   Electronic
   Section
     Trans.
     Acoustical
     Section
      Receiver
                   Borehole
                    Liquid
                                             Casing
                                             Bonded Cement
                                             Sheath
      Sonic Pulse
      Path
_       _


— —  Formation
Figure 2.   Cement bond tool - single transmitter/receiver.
Log Interpretation
    The bonding of cement to casing can be measured quantitatively,
but the bonding, or rather the coupling, of cement to the formation is
only a qualitative  estimate. Therefore, when attempting to evaluate
cement in a well,  it is extremely  important  to obtain  as  much
information as possible.
    The components of  the sound wave that are of primary interest
when  analyzing a "bond  log"  are the casing,  formation and fluid
(mud)  signals. Each medium has different characteristics, thus the

-------
               Transmitter
             3 ft Receiver
             5 ft Receiver
Figure 3.   Cement bond tool - single transmitter/dual receiver.
sound waves will have different amplitudes and velocities. Figure 5
indicates these  wave forms and a composite signal.

    A recommended approach to evaluating the cement bond log is to
first  determine  the  information  available  from  the graphic
representation of the wave form (VDL), then examine  the amplitude
curve to see if  the two are in agreement. For example, if the casing
diameter and transmitter/receiver spacing are known, the transit time
for the casing arrivals can be predicted.  Figure 6 is a  chart that,  for
practical field or reference purposes, gives an  idea of the approximate
transit time for  the casing signal for various tool spacing and casing
I.D. By examining the  VDL,  the time, in microseconds of the first
arrival, can be determined. This time can then be checked against the
chart to determine if it is a casing signal.

    The fluid,  or  mud,  wave  has  a  velocity of about  189
microseconds/foot, and its arrival can be predicted,  if the tool spacing
is known, by multiplying the tool spacing by 189. The fluid wave has a

-------
              Eight
          Ultrasonic
        Transducers
              Fluid
           Velocity
         Transducer
                                       .3X^,3 Casing
                                       ฃ:H?~  Bonded     -.--•
                                       3-I-I-I-I-I  Cement Sheath
                                               --  Formation
Figure 4.    Second generation tooL
destructive interference; thus when it enters the receiver, distortion of
the wave occurs. Because of this,  the only part of the VDL that is
useful for interpretive purposes is that part that reaches the receiver
prior to the arrival of the fluid wave.

    The "second generation"  tools generate a  pulse of ultrasonic
energy from each of the eight focused transducers that are arranged
around the circumference of the tool. The strength and  duration of the
echoes reflected from the casing and cement are used  to  form  an
image of the cement distribution and quality around the casing. This
information  and  the  cement compressive  strengths  are two  very
useful pieces  of  data for evaluating the casing/cement bonding in a
well.

    As  stated  earlier, 16 different logs  have been produced from the
well. Appendix A contains a detailed comparison of specific sections
of the well  that  have been logged by "first  generation"  tools with
single  transmitter/receiver,  3-,  4- or 5-foot spacing;  and the second
generation ultrasonic logging tool.

-------
   1r
Fluid
      Casing
   Ir
Formation
       Composite
Figure 5.   Composite wave form.
Logging Well No. 2
    Analysis of the tests completed on Logging Well  No.  1  identified
two  areas  that needed further  investigation.  As has  been  stated,
certain logging tools located all of the 90 and 60 degree channels, all
but one  of the  30  degree channels, but none of the 6 degree
channels. Thus,  the  detection  limit  for  the  tools  is  somewhere
between  30 and 6 degrees. The second area of  concern relates to
the inability of presently  available  equipment to  evaluate  cement
behind fiberglass pipe.
    To address these concerns, Logging  Well No. 2 was  designed
and constructed with both steel and fiberglass pipe and with  channels

-------
                                  Aft
             Din

4
5
6
7 .
3
235
250
265
280
4
292
307
322
337
5
349
364
379
394
                  A ft - Receiver spacing
                  D in - Casing diameter
                  Figure 6.   Field reference transit time.

on the steel pipe covering 30. 25, 20, 15 and  10 degrees of the 360
degree radial surface of the pipe (Figure 7).

    The well specifications,  along with a detailed  description  of the
drilling and completion process, are provided in Appendix A.

Cement Evaluation
    With the completion of the well, the  process of determining the
capability for locating channels on steel pipe and evaluating cement
behind fiberglass pipe was ready to begin. Only those logging tools
that produced satisfactory  logs in Well No. 1 were run on Well  No.  2,
with the exception of some experimental  tools that have  been  run  in
the well but are not yet available for general use.
    Ten logs have been  produced on  the well. Of these, four were
produced from experimental tools.

Logging Tools
    Three generations of logging tools have been run in the well. The
"cement bond" tool consists of a single transmitter/dual receiver with
the receivers spaced 3 feet and 5 feet from the transmitter.  The
"cement evaluation" tool  has eight ultrasonic transducers spiraled
around a  2-foot section of the tool. Prototype tools  are not  yet  in
commercial use.

Well Logging Conclusions and Recommendations

Well Completion
    Greater care must be exercised  in planning the cement job  and In
carrying  out that  plan when  cementing injection  wells, especially
Class I wells where cement is to be circulated to the  surface around
the long string.  The plan should include equipment and activities that
will enhance the possibility  for obtaining  the  best cement bonding
possible. This should include the use  of a  caliper  log to determine
exact hole  size  to better estimate the volume of cement necessary  to

-------
   5 1/2-in dia Casing
  l57S-ft Depth
                                               Fiberglass Casing
                            8 3/4-in dia. Borehole
Figure 7.   Logging Well No. 2.


complete the well; properly conditioned drilling mud prior to beginning
the cementing operation; centralizers, to ensure  that the casing is
centered in the hole; pre-flush, to help clean out the hole prior to
pumping cement;  rotating  and/or reciprocating  the pipe during  the
cementing  operation to further aid in cleaning out the hole;  and at
least  100  percent  excess  cement. The experience  in  cementing
Logging Well  No.  1 indicates  that those areas where the greatest
volume of cement flowed past had  cleaner holes and better  cement
bonds, thus the use of 100 percent excess  cement will enhance the
probability of a good cement job throughout the casing length.
                               10

-------
     Yn Logging Well No. 1,  although  cement  was circulated to the
 surface,  after  the cement set for 72  hours, the top of the cement
 behind the casing was 132 feet below land surface. This "fall back"
 of the cement behind the casing must  be monitored and corrected so
 that there is cement fill-up behind the casing  to the surface of the
 ground.

     Because of the  problems encountered in cementing Logging Well
 No. 1, extreme care was taken to ensure that a good cement job was
 obtained in Logging  Well No. 2. The top  of cement behind the casing
 was 42 feet below land surface in this  well, as opposed to 132 feet in
 No.  1.  Approximately 1,075 sacks of  cement were used to cement
 Well No. 2 with about 500 sacks circulated  to the surface during the
 cementing operation.

 Logging Equipment

     None of the 'egging tools presently available located any of the 6
 degree channel? in Logging Well  No. 1.  The second generation tools
 located all of the 30, 60 and 90 degree channels that were designed
 into  and  couM be identified  in  the  well.  A calibrated  single
 transmitter/dual .eceiver cement bond  tool with  3-foot/5-foot  spacing
 located the  60 and  90 degree channels and all but  one of the 30
 degree  channels.  The  other cement bond  tools  with  single
 transmitter/single receiver 3-foot,  4-foot,  or 5-foot spacing presented
 very inconsistent results.

    The 3-foot spacing is the best currently available for measuring
 and evaluating  the amplitude of the first compressional arrival and the
 attenuation of this signal is a measure of the bonding of the  cement
 to  the  casing.  However,  this  spacing  is  not satisfactory for
 determining data on  or evaluating the  relationship of  the cement  to
 the formation. Five-foot spacing between the transmitter and receiver
 is the best currently available for evaluating the relationship of the
 cement to the formation, but it is not accuratetfor determining bonding
 to the casing. Four-foot spacing is being used; however, it does mot
 have satisfactory  resolution for evaluating  the relationship  of  the
 cement to either the  casing or formation.

    The  significant fact remains that none of the  tools  located
 channels  smaller  than 30  degrees in  the well.  Such channels
 represent a  significant avenue  for movement of fluid  and methods
 must be developed to locate these and even smaller  channels.  It  is
 recommended  that the  logging industry continue research  efforts
 toward increasing the sensitivity of the logging tools.

    The research conducted on Logging Well No. 1 indicates that with
 the presently available  tools, the ideal approach for  evaluating  the
 cement in an injection well is to run  both the second generation  tool
.and a calibrated cement bond tool  with single transmitter/dual receiver

-------
3-foot/5-foot spacing. This combination gives the most information for
interpretive purposes.
    An alternative to this approach is the use of either the second
generation tool or a calibrated "bond tool" with single transmitter/dual
receiver  3-foot/5-foot spacing. The second  generation tool  gives no
information  on the cement/formation  coupling, but  gives  excellent
information on the cement/casing bonding and its presentation allows
for easy interpretation. The "cement bond"  tool provides information
on both casing/cement bonding  and coupling to the formation,  but is
somewhat harder to  interpret and may be less  sensitive  in  some
specific situations.
    Calibration of both  tools is imperative for reliable data  to be
produced. The size and weight of the casing must  be  available for
use with  the second generation tool. A standard  shop calibration of
the cement bond tool is  essential to its use  and must be included for
there to  be any chance  of obtaining  reliable information. Quality
control on the "cement bond" tools can be included, to some degree,
on site, in that certain  checks can be  made to determine whether or
not the tool is working properly.
Some of the checks that can be made include:
    1   If the well contains  free pipe, the chevron effect must be
        obvious.  The chevron effect is the "W" seen opposite casing
        collars in free pipe.  Figure 8  indicates a  bond log with free
        pipe.  Note the  well-developed chevron  effect opposite the
        casing collars.
    2.  In free  pipe,  certain  casing diameters call  for certain
        amplitude readings. For example, for 5-inch  (I.D.) casing the
        amplitude should read about 74  millivolts  (mv); 7  inch - 60
        mv; 8 inch - 55  mv; 9 inch - 30-35  mv. Such information can
        be used to determine if the tool has been  calibrated. Figure 8
        indicates an amplitude reading of over 60 mv in 9-inch free
        pipe. This indicates that the tool was not calibrated.

    3.  In free pipe, the transit time  from a properly  centered tool
        should be constant, except for the influence of the  casing
        collars. In Figure 8, the decrease in transit time (immediately
        below the  arrow) and the  corresponding  decrease in
        amplitude, indicates  a slightly eccentered tool. Figure  9 also
        indicates free pipe. Note, however,  the wavy free pipe signal
        on  the VDL and the significant drift of the transit time (over
        one-half  of a chart division).  This indicates an  improperly
        centered tool.
     4  The fluid  wave  should  be  visible on  each wave  form
        presentation  (VDL). If  the  fluid wave is  not  visible,  this
        indicates a  low  response  tool  and  its  use  should  be
        questioned.
                                12

-------
  8
Figure 8.   Amplitude, chevron and free pipe.


    An  API  committee  is  presently  working  on  standardizing  a
calibration system. This work should  be encouraged  and continued
until an adequate system is developed that can  be used throughout
the industry.

-------
Figure 9.   Tool not centered.
    The cement bond tools and second generation logging tools run
in Logging Well No. 2 located the 30, 25, 20 and 15 degree channels.
However, none 'consistently located the 10 degree channels on the
casing. A 10 degree  channel  on the 5  1/2-inch  casing  represents
about 1/2 inch.
                               14

-------
     One of the prototype tools consistently located the  10 degree
  channels. This is very encouraging; however, much more research
  needs to be completed on these new tools to  be assured of their
  capability for locating channels in cement.

     Only one tool presented data that could be used to evaluate the
  cement behind fiberglass  casing. This second  generation tool  had
  been modified to  respond to the resonance of fiberglass and seemed
  to work well in  the test  well.  However, the tool is  not available
  commercially and will not be available in the foreseeable future.

     Additional research will be done in these  two areas during the
  next 3 years of the mechanical integrity research project.

  Log Interpretation

    A significant problem that became apparent during  the research
 efforts, especially  on Logging Well  No. 1, was the inability of  some
 logging  company  personnel to  interpret  the  logs they produced.
 Several companies  had good  equipment,  but onsite personnel
 apparently did not have sufficient  knowledge  of the  equipment  to
 properly operate th'   system  or interpret the  log.  This is a critical
 concern if these too ,  are to be used to  evaluate the  cement  in an
 injection well.  The  egging  company,  injection  well owner, or
 regulatory agency  must have  trained personnel that are capable  of
 evaluating a log to determine as much information as possible on the
 quality of the cement behind each casing string.

 Leak Test Well

    The purpose of  the  Leak Test  Well  is to provide a  facility to
 develop methods  for testing the integrity  of the  tubing, casing and
 packer and for testing the capability of various down-hole tools to
 detect fluid movement behind the casing.

    The design  of the well  generally corresponds  to a typical salt
 water  disposal well used in  the oil  and  gas  industry. That  is,  it
 includes the  use of surface casing,  long  string, tubing  and packer.
 The deviation  from the norm in this well includes two packers and a
 sliding sleeve on the injection tubing and a  2 3/8-inch tubing attached
 to the outside of the  long string  and running to the surface (Figure
 10). Detailed  discussion, on well design and installation is provided in
 Appendix B.

    Flow into the well  can be controlled so  that the injected fluids are
 directed into the 2 3/8-inch injection tubing, or to the 2 3/8-inch leak
 string.  Returned flows  can be controlled  from  the 2 3/8-inch  leak
 string and also from the annulus of the 5 1/2-inch casing (Figure 11).

    Monitoring wells have  been constructed to each  of the zones!
open to the Leak  Test Well (Figures 12,  13,  and  14).  These are
multipurpose wells  that are being  used to monitor pressure  changes

-------
iiH





4-
5-
— ป


.V."
;•&•
,*****
**** *
gat
A A *


	

ooo
ฃฃ8SS3&&8S&i
^H_I

t 1
* 1
\
P

_^
III
V""
ZZ
M
I
/

&
^
aSul M
— 10 —
I
<
%"

I
f
r
*~
:::
•>/:••"'"

Xvlv
A * * * A
A A A A A
A A A A A
	 fjQO ft
rrr-8 ' , ' '
	 '.. 710 ft
tins ft
—7
,,, 	 ,,,, ., ...'. 935 ft
— 6
1057 ft Depth of
Upper Packer
	 Cement
1. Baker Model "C-1
2. 2 3/S-in Tubing'
3. Baker Model "L"
4. Baker Model "R"
5. Baker Model "Ad
, 6. 2 3/8-in Tubing
7. Baker Model "R"
8. Baker Model "F"
9. 5 1/2-in Long Strir
10. Perforations
1084 ft Depth of
Lower Packer
•t ion ft
HMIIM — i 	 .1 1 1 ii >.;1 1 e\l n
	 	 1130ft
                                                     Injection Zones '
                                                C-1 " Tandem Tension Packer
                                                g'
                                                "L" Sliding Sleeve
                                                "R" Profile Nipple
                                                "Ad-1 " Tension Packer

                                                    Profile Nipple
                                                    Profile Nipple
Figure 10.    Leak Test Well.
                                     16

-------
                                                     5 1/2-in Casing
                                                       ,_Head
                                                    2 3/8-in Long
                                                     String Tubing
       High Pressure
         Steel Pipe

          /
                                                      2 3/8-in Leak
                                                         String
    Flow Return to
    Water Supply Tanks
5 1/2-in Annulus Connection
 Figure 11.    Injection well head and flow lines.

 in  the  respective  zones  during injection  and  to determine the
 capability to evaluate certain  types of  cement.  Well No.  1  was
 cemented using a latex cement, No. 2, a spherelite cement, and No.
 3, a foam cement. Detailed discussions on monitoring well design and
 installation are provided in Appendix B.
    A number of tests have  been conducted or are  planned for the
Leak  Test Well. In addition to  a test  to determine  the  hydraulic
conductivity of the injection zone, such tests include:
    Test

  1. Acoustic Cement Bond Tool
  2. Nuclear Activation Technique
  3. Testing for Hole in Casing
  4. Ada Pressure Test
  5. Nuclear Activation (PDK-100)
  6. Radial Differential Temperature
  7. Nuclear Activation Technique
     ( Oxygen Activation)
  8. Mechanical Integrity Research
       (Mud in Annulus)
       (Pressure  Monitoring)
       (Standard  Pressure Test)
       (Volume vs Pressure/Monitoring Wells)
       (Volume vs Pressure/Hole Size)
  9.  Noise Survey
10.  Temperature Survey
11.  Continuous Flow  Survey
        Date Completed

              1/13/87
              1/24/87
              2/02/87
            12/04/85
              4/08/87
              4/27/87

              8/31/87
              2/22/88
             2/15/88
             9/10/85
            10/13/87

-------
  9 5/8-in Conductor Pipe-
           80 ft
            680ft
        Latex Cement •
     2-in Steel Linepipe
          20 ft Long
             I
    Bottom of 41/2-in.
      Steel Casing
                    ,685 ft
            30 ft
                         Shale Cup
                   20 ft  Injection
                    I      Zone
                    ' 705 ft
     4 1/2-in to 2-in Swedge

               Surface

             -12 1/4-in Borehole
            • Neat Cement
        — 4 1/2-in Casing
         Centralizer on Each Collar
                                                 — 8-in Borehole
       •Johnson "K" Packer,
             4 1/2-in
        9ft
 •3 7/8-in Borehole
- 2-in Stainless Steel Screen
 .010-in Shot, 30 ft Long
                                        4—710ftTD
Figure 12.   Monitoring Well #1.


 12. Radioactive Tracer Survey                          5/19/88
 13. Differential Temperature Survey                    11/04/87
 14. Annulus Pressure Changes Due to Temperature     Planned
 15. Helium Leak Test                                  Planned
 16. "Mule Tail" Test                                    Planned
 17. Tracers Involving Monitoring Wells                  Planned
 18. Oxygen Activation (Water Quality  and Flow)         Planned
                                  18

-------
   9 5/8-in Conductor Pipe
                   80ft
             905ft
  Spherelite Cement
    Bottom
     Steel
         20ft
of 4 1/2-in I
Casing  Nv
            30ft
           1910 ft

               Injection
         20 ft   Zone



         ?930ft
                                         4 1/2-in to 2-in Swedge

                                                     Surface

                                                   12 i/4-in Borehole
                                                  Neat Cement
                                           	 4 1/2-in Casing
                                            Centralizer on Each Collar
                                                         • 8-in Borehole
                                                      Johnson "K" Packer,
                                                          4 1/2-in
• 2-in Steel Linepipe
    20 ft Long
                                               • 3 7/8-in Borehole
                                            -.2-in'Stainless Steel Screen
                                               .010-in Shot, 30 ft Long
                                           4— 935 ft TD
Figure 13.     Monitoring Well #2.

-------
                                               • 4 1/2-in to 2-in Swedge
miiiiisiiii
*
9 5/8-in Condi
11
Foam Cei
2-in Steel Line
20ft Lo
jctor P pe -V
80ft i
30ft


A
ig
2
i
4
2
r '
Oft
k1110tt
)ft
Inject
Zone
1130 ft
i
K,

<
P: :

sir.
— V

o
'ik
=



"ii1"*1*!







"^Z>
,Z^->
"4^r><
,|ll|i|lllllllll|i Surface
L — 12 1/4-in Borehole
J| — Neat Cement
, 	 /\ 1/2 in Casing
Centralizer on Each Collar
•4 — 7 7/8-in Borehole
	 ,,,.r Johnson "K" Packer,
4 1/2-in
Bottom of 4 1/2-in
Steel Casing
- 2->n Stainless Steel Screen
.01 0-in Shot, 20 ft Long
Perforations
*^
4 — 1130 ft TD
Figure 14.    Monitoring well #3.
                                    20

-------
                         Conclusions
    The  viability  of  deep  well  injection as  a waste  management
alternative rests on  the  ability to  emplace wastes  in  geologic
formations beneath  and  isolated  from  underground  sources of
drinking water. Wastewater injected  into wells may escape through
leaks in the well casing caused  by mechanical failure within the  well
or by migration of wastewater between the well's outer casing  and
well bore  because of  faulty cementing.  Although technology is
available  to  construct  and operate  injection  wells that  meet
mechanical integrity criteria, technology for determining injection  well
mechanical integrity must be tested and proven to ensure that sound
decisions  are made and that underground sources of  drinking water
are protected.

    No  one  test provides sufficient information  to   make a
determination of the  mechanical integrity  of  an injection well.  This
determination is made from a combination of  tests which individually
provide  pieges of information that  must  be  evaluated  together to
provide  a basis for   making  an  informed  judgment regarding  the
mechanical integrity of an injection well.

    The research facilities described  in this document  offer industry,
state regulatory agencies and EPA a  unique  capability  to  test and
evaluate a variety  of  methods for determining mechanical  integrity.
Such testing can" improve the confidence of industry and permitting
agencies in'approved methods and can speed  the acceptance of new
methods that may be developed.                        •         •

-------
                        References

Batcheller, Gary W.,  Schlumberger Well Services, Cement Evaluation
Seminar.
Gearhart,  undated material, Pulse Echo Loq,  Cement Evaluation,
Casing Inspection.
Maffi, A., Tom Hansen Co., Cement Evaluation Seminar.
Tom Hansen Co., undated material, Lazer Logging Systems Cement
Bond Log.
Schiumberger,  undated  publication, Cement Bond, Variable Density
Log.
Schlumberger,  undated publication, Cement Evaluation Tool.
Thornhill  .Jerry T.   and  Benefield,  B.G.,  Mechanical Integrity
Research, Proceedings  of  the International  Symposium on
Subsurface Injection of Liquid Wastes,  New  Orleans,  Louisiana,
March 3-5, 1986.
                              22

-------
                         APPENDIX A
   Logging Well Design Specifications and Installation
                          Procedures
 Logging Well No. 1

 Logging Test Well Material Specifications
     Casing                    Weight                  Grade

     3 joints of 9 5/8-inch        53.5#/ft                  N-80
     3 joints of 9 5/8-inch        36.0#/tt                  K-55
     8 joints of 8 5/8-inch        24.0#/ft                  J-55
     4 joints of 7-inch            23.0#/ft                  K-55
     2 joints of 5 1/2-inch        23.0#/ft                  N-80
     3 joints of 5 1/2-inch        17.0#/ft                  J-55
     3 joints of 5 1/2-inch        15.5#/ft                  J-55
     2 joints of 4 1/2-inch        13.5#/ft                  N-80
     4 joints of 41/2-inch        11.6#/ft                  J-55
     5 joints of 41/2-inch         9.5#/ft                  J-55

     Eguipment                 Size                     Grade

     Swage nipple               5 1/2-inch x 4-1/2-inch     K-55
     Swage nipple               7-inch x 5 1/2-inch        J-55
     Swage nipple               8 5/8-inch x 7-inch        J-55
     Swage nipple               9 5/8-inch x 8-5/8-inch     J-55
    Swage nipple               9 5/8-inch x 5-1/2-inch     J-55
     10 centralizers              4 1/2-inch
    7 centralizers               5 1/2-inch
    3 centralizers               7-inch
    7 centralizers               8 5/8-inch
    5 centralizers               9 5/8-inch

Detailed Description of Well Construction

    On  August 14, 1984, the process  of  preparing the "channels"
was begun. PVC  pipe, either  3/4  or  1/2 inches in diameter, was
sealed on  one end, filled with water saturated  with boric acid and
capped. The next step was to attach the PVC pipe to the outside of
the casing so that the channel would  cover either 90,  60, 30 or 6
degrees of the 360 degree radial surface of the pipe (Figure  A-1).
This was accomplished  by attaching the PVC pipe to the surface of

-------
the casing, which had been sandblasted to remove mill varnish, using
fiberglass cloth and epoxy resin. Three layers of fiberglass were used
to ensure that the PVC pipe was securely sealed and attached to the
casing (Figures A-1 to A-4). This phase of the project was completed
on September 17, 1984.
    The casing was  then wrapped with heat tape and  insulation to
prevent freezing  of the channels while awaiting  the availability of the
drilling rig.
    The driller began moving the rig to  the  site on December 13,
1984. Rigging up continued  on the 14th and 15th and drilling began at
2:30 p.m. on December 15,  1984. The procedure followed  and the
date each step was accomplished are indicated below:

    Activity
Date Completed
    1)   Prepare site                                 12/13/84
            (Baulch Drilling Company)
    2)   Move in rig and rig up                        12/15/84
    3)   Drill 15-inch hole to 40 feet, set 13 3/8-inch
            conductor pipe (OK Cement, 35 sx)        12/15/84
    4)   Drill 8 3/4-inch hole to 1,530 feet. Collect
            drill cuttings every 10 feet starting
            at 100 feet                              12/18/84
    5)   Condition hole for logging                     12/18/84
    6)   Run Dual Induction  Laterolog, Gamma         12/18/84
            Ray, Compensated Neutron, Compensated
            Density, and B.H.C. Sonic Log (Gearhart)
    7)   Ream  12 1/2-inch hole to 758 feet            12/20/84
    8)   Clean out hole to TD, condition  for            12/20/84
            setting casing
    9)   Set casing                                  12/20/84
   10)   Run 2 3/8-inch tubing and string into Baker     12/20/84
            Duplex Cement  shoe. Condition hole
            for cementing.
   11)   Cement casing                              12/20/84
            (Halliburton, 700 sx. 50/50 Posmix)
   12)   Remove tubing, flush out hole                 12/20/84
   13)   Weld steel plate between 9 5/8-inch and       12/27/84
            13 3/8-inch casing.  Install 9  5/8-inch
            x 5  1/2-inch swage  nipple on
            9 5/8-inch casing. Screw locking
            cap on swage.
   14)   Install rock pad and cement slab               9/10/85
                               24

-------
Figure A-1. Preparing fiberglass with epoxy resin.

-------
Figure A-2.  Applying initial fiberglass layer.
                                   26

-------
Figure A-3. Completed channel - prior to using wire  brush  to  remove
           excess.

-------
Figure A-4.  Removing excess fiberglass with wire brush.
                                 28

-------
   The design  of  the  Logging Well presumed  that  the  channels
would remain in place during the process of setting and cementing
the casing. The driller took special precautions when moving the pipe
from the pipe racks to the rig, and during the pipe setting process to
ensure that this was the case. No problems were encountered during
the entire casing setting and well cementing operation, thus there was
a high degree of confidence that the channels were not  damaged and
were in place as  designed. Later review  of logs  run on the well
reinforced this confidence.

Log Interpretation
   Figures A-5, A-6 and A-7 are portions of logs from the Logging
Well that compare  single transmitter/single receiver with either 3-, 4-,
or 5- foot spacing; single transmitter/dual receiver  with both  3-foot
and  5-foot spacing;  and  the  second  generation   logs.  Each
interpretation is based solely on  information from the log.

   Figure  A-5a indicates a  log section from  a tool with single
transmitter/single receiver, 3-foot spacing. The fluid  wave should
enter  the receiver at  about   567  microseconds;  however, it  is
indistinguishable on this log.  Casing signals are present in the  upper
part  of  the VDL,  but no other interpretation  can be made. The
amplitude  curve indicates poor bonding in the  upper part  of  the
section, which  seems to agree with the VDL, and casing/cement
bonding throughout the remainder of the section.

   Interpretation:    Excellent casing/cement bonding  throughout
                  the section  with a possible  channel or  micro-
                  annulus in the upper part of  the section. Coup-
                  ling to the formation cannot be determined.

   Figure A-5b  is  the same section  from a single transmitter/single
receiver tool, with  4-foot spacing.  The fluid wave should enter  the
receiver at about 756 microseconds,  as  indicated  on the log. Casing
signals may be present in the upper part  of the  section, although the
signals are weak.  The  amplitude curve  indicates a  problem in  the
upper part and  casing/cement  bonding  for  the  remainder of the
section.
   Interpretation:    Excellent casing/cement bonding  throughout
                  the section  with a possible  channel or  micro-
                  annulus in  the  upper part of  the section.  No
                  coupling to the formation.

   Figure  A-5c is  the same section  from  a tool  with  single
transmitter/single receiver, 5-foot spacing. The fluid  wave should
enter the receiver at about 945 microseconds. In this case, the fluid,
wave is pushed far enough to the right to allow  the formation signals
to be seen.  The  VDL indicates formation signals  throughout the
section, and some casing signals in the upper part of the section. The

-------
Figure A-5a.    Single receiver 3-foot spacing.
                                  30

-------
Figure A-5b.    Single receiver 4-foot spacing.

-------
Figure A-5c.    Single receiver 5-foot spacing.
                                  32

-------
amplitude  curve  indicates  a  problem  in the  upper  part with
casing/cement bond throughout the remainder of the section.

   Interpretation:    Excellent casing/cement bonding  throughout
                   the  section with  a possible  channel  or
                   microannulus in the upper part of the section.
                   Possible coupling of cement to the formation.

    Figure  A-5d  is the same  section  from a  tool  with  single
transmitter/dual receivers and a 3-foot/5-foot  spacing. The VDL shows
formation signals  throughout the section and casing signals in  the
upper and lower parts of the section. The amplitude curve indicates a
problem in  the upper  part  with  casing/cement  bonding  indicated
throughout the remainder of the section.

   Interpretation:    Excellent casing/cement bonding  throughout
                   the section with either channels or  microannuli
                   in the  upper and lower parts  of the  section.
                   Possible coupling to formation.

    Figure  A-5e  is  the same  section from  one  of  the  second
generation logs. The white areas on the  bond image portion of the  log
indicate the presence of poor casing/cement bonding.  The minimum
compressive strength curve  also indicates  some problems  in  three
areas that coincide with the white areas  on the bond image portion of
the log.

   Interpretation:    Excellent casing/cement bonding  with  three
                   channels  or microannuli in the  upper,  middle
                   and lower parts of the section. No  information
                   is available on formation coupling.

    A second comparison  of the  different logging  tools run  in the
Logging Well is shown in the Figure A-6 series. Figure A-6a is a  log
section  from  a  tool with  single transmitter/single  receiver,  3-foot
spacing. The  fluid wave should enter the receiver at about 867
microseconds; however,  it  is not distinguishable on this log. There
may be formation  signals in the presentation;  however,  they  are not
distinctive, making it difficult to  determine the character of the log.
The amplitude curve only registers in two places on the log, and the
transit time curve is not definitive.

   Interpretation:   Excellent  casing/cement bonding throughout
                  the section.

    Figure  A-6b  is  the same section from a tool  with  single
transmitter/single  receiver,  4-foot spacing. The fluid signal  is very
strong,  with  the  VDL  indicating  casing/cement  bonding  but  no
formation  coupling. The amplitude curve indicates casing/cement
bonding..

   Interpretation:   Excellent casing/cement  bonding, no formation
                  coupling.

-------
Figure A-5d.    Dual receiver 3-foot/5-foot spacing.
                                  34

-------
Figure A-5e.    Second generation log - Company A.

-------
Figure A-6a.    Single receiver 3-foot spacing.
                                  36

-------

r


03
.-a . 	
3

JL 	
1
Sv-a
0)
2 '

13
^
	 < 	 	



-, .. , „,, ,,n^',.









/',
Figure A-6b.    Single receiver 4-foot spacing.

-------
    Figure A-6c represents  a  log  rrom a  1001  wun smyio
transmitter/single receiver,  5-foot spacing. It  shows very  clear
formation  signals on the VDL, with one area near the center of the
section showing  casing  signal.  The  amplitude curve shows
casing/cement bonding, with a possible problem in  the  center of the
section.
   Interpretation:   Good  casing/cement  bonding  with  the
                  possibility of a  channel or microannulus in the
                  middle  of the  section.  Formation  signals
                  indicate coupling to  the formation.

    Figure A-6d represents  a  log  from a  tool  with single
transmitter/dual receivers with 3-foot/5-foot spacing.  The VDL shows
formation  signals throughout  the section  and definite casing signals
near the middle and in the lower part of the section. The amplitude
curve indicates cement/casing bonding,  with a very slight response in
the middle of the section.
   Interpretation:   Excellent  casing/cement bonding  with  the
                  possibility  of channels  or microannuli  in the
                  middle  and lower  parts  of   the section.
                  Formation signals  indicate  coupling  of the
                  formation  to the casing.

    Figure A-6e is  a log  of  the  same section of  the  hole from a
second generation tool.  The  bonding display indicates  two channels
or microannuli, one  in the middle and one in the lower  section. The
average cement strength curve correlates with the bonding display.

   Interpretation:   Excellent  casing/cement bonding  with  the
                  exception of two channels or microannuli in .the
                  middle  and  lower  part of the section.  No
                  information on formation coupling.

    The  third comparison  of  results  from  various  logging  tools
involves the  occurrence of "fast  formations," those formations that
exhibit a travel time that is  equal to or  faster than the travel time for
casing.
    Figure A-7a is a section from a tool  with a single transmitter/single
receiver with 3-foot spacing.  The VDL  indicates what appears  to be
casing signals in the upper part of the section and formation signals in
the lower part of the section. The VDL signal in  the lower part is
called formation signal because no chevrons are visible opposite the
casing collars. The  amplitude curve indicates some  casing signals in
three parts of the section.
   Interpretation:    Poor casing/cement bonding in  the  upper part.
                   The amplitude curve and VDL are contradictory
                   in the  lower  part  of  the section.  The VDL
                   indicates  casing/cement bonding and  the
                   amplitude indicates  poor bonding in one area.
                               38

-------
Figure A-6c.    Single receiver 5-foot spacing.

-------
           *ซfc^^
Figure A-6d.    Dual receiver 3-foot/5-foot spacing.
                                  40

-------
Figure A-6e.    Second generation log - Company B.

-------
                                                1*8
Figure A-7a.    Single receiver 3-foot spacing.
                                  42

-------
    Figure /V-7b is a log of the same section with a tool  with single
 transmitter/single receiver, 4-foot  spacing.  The  VDL  indicates
 casing/cement bonding  in  most of the  section with one area  of
 formation signal  in  the  lower  part. The amplitude  curve indicates
 casing signal in the lower part.

   Interpretation:    Good casing/cement bonding in the upper part
                   of  the  section.  No  formation coupling in  the
                   upper part.  The amplitude curve  and VDL are
                   contradictory in the lower part of the section.

    Figure A-7c is a log of the same section from a tool  with single
 transmitter/single receiver, 5-foot  spacing.  The  VDL   indicates
 formation signals throughout the section  with possible casing signals
 in the upper part. The amplitude curve indicates poor casing/cement
 bonding  throughout most of the section  except for about  10 feet in
 the upper part and the  lower 20 feet.

   Interpretation:    Poor cement/casing  bonding throughout the
                   section except for about 10 feet in the upper
                   part and the lowermost 20 feet. The amplitude
                   curve and VDL  are  contradictory in  the lower
                   part.  The amplitude  curve reads  over  70 mv,
                  which indicates free pipe.

    Figure A-7d indicates a log  of the same section from a tool with
 single transmitter/dual  receiver  with 3-foot/5-foot spacing.  The  VDL
 indicates formation signals throughout the section with casing signals
 in the upper part.  The amplitude  curve  indicates  cement/casing
 bonding with one  possible problem in the upper part of the log.

   Interpretation:   Excellent cement/casing bonding throughout
                  most of the section. Possible  channels or
                  microannuli  in the upper part of the section.
                  Formation coupling throughout most of the log.

    Figure  A-7e  is the  same  section  from  one of the  second
generation logs.  The  bond image  part  of  the log  indicates  three
channels  or  microannuli in the upper  two-thirds  of the  log.  The
minimum  compressive  strength curve supports that  some problem
exists in these areas.

   Interpretation:    Excellent cement/casing bonding with three
                  channels  or  microannuli. No information on
                  formation coupling.

    As can  be seen  from these  examples,  casing  signals  and
formation  signals are  very difficult to  differentiate  when a  fast
formation is involved.

-------
Figure A-7b.    Single receiver 4-foot spacing.
                                  44

-------
Figure A-7c.    Single receiver 5-foot spacing.

-------
                                     I
                                          1
Figure A-7d.    Dual receiver 3-foot/5-foot spacing.
                                  46

-------
Figure A-7e.    Second generation log -.Company A.

-------
Logging Well No. 2
Logging Test Well Material Specifications
    Casing                    Weight                  Grade
    2 joints of 8 5/8-inch        conductor pipe
    39 joints of 5 1/2-inch       17.0#/ft                  J-55
    5 joints                    fiberglass with
                                steel in collars
    Eguipment
    43 centralizers
Detailed Description of Well Construction
    On  May  26, 1987, the process of preparing the channels was
begun. Essentially  the same process that was used on Logging Well
No.  1  was repeated,  with  the exception of the  size  of  channel
material. PVC pipe, 1/4-inch polyethylene tubing, and fiberglass were
used to  create the 30,  25,  20,  15 and  10 degree  channels. The
excess  resin  and  fiberglass  were  sandblasted  to  ensure  that the
channels were the correct size, and the completed  work was moved
to the drilling rig on June  25, 1987.
    The driller began moving to the site on June 22, 1987, and began
drilling the rat hole on June 23, 1987. The procedure followed for this
well included:
                      Activity                   Date Completed
   1)  Prepare site (Baulch Drilling Company)          6/22/87
   2)  Move in rig  and rig up                          6/22/87
   3)  Drill 12 1/4-inch hole to 80 feet:                 6/24/87
      set conductor pipe
   4)  Drill 8 3/4-inch hole to  1,575 feet               6/26/87
   5)  Condition hole for logging                      6/26/87
   6)  Run Dual Induction - SFL and Microlog          6/26/87
      (Schlumberger also ran some
      experimental open hole logs.  They logged
      the well from 1:00 a.m. until 9:15 p.m.)
   7)  Set casing                                    6/27/87
   8)  Cement casing (Halliburton, 1,075 sacks         6/27/87
      50/50  Posmix)
   9)  Install rock pad and cement slab                7/08/87
    No significant problems were encountered in completing the well,
and the first log was run on July 14, 1987.
                               48

-------
                        APPENDIX B

Leak Test Well Design and Testing Criteria and Test
                         Summaries

Leak Test Well
    The purpose of the "Leak Test Well" is to provide a facility to
develop methods for testing the integrity of the tubing, casing and
packer and  for testing the capability of various down-hole tools to
detect fluid movement behind the casing.

    The design of the well  generally corresponds to a typical  salt
water disposal  well used in the oil and gas  industry. That  is, it
includes the use of surface casing,  long string, tubing and packer.
The deviation from the norm in this well includes two packers and a
sliding sleeve on the injection tubing and a 2 3/8-inch tubing attached
to the outside of the long string  and running to the surface (Figure
10).                                        ,
    The depth  to  which surface casing was  set  was  based on
Oklahoma Corporation Commission regulatory requirements to extend
below the occurrence of ground water having 10,000 mg/L or  less
total dissolved  solids. The selection of the  depth for locating .the
profile nipples and the  injection zone was based on porosity data from
Compensated  Density  and  Compensated  Neutron logs  from  the
Logging Well.
    The 2 3/8-inch  tubing, outside the 5  1/2-inch long string, extends
from a 1/4-inch hole  in  the long  string at 1,070 feet below  land
surface to the surface of the ground. The hole was drilled using a 1/4-
inch bit, and a 2 3/8-inch elbow was welded to the casing so that the
tubing could be attached. Profile nipples were placed in  the tubing
opposite the 680- to 710-foot sand at 700 feet and the 905- to 935-
foot sand  at 920 feet. These nipples  will control the leakage of  fluid
from the tubing, in that fluid can exit the tubing at either of the nipples
or be brought to the surface.

    Casing and equipment for the Leak Test  Well include:

    571 feet of 13 3/8-inch casing
    1,215  feet of 5  1/2-inch long string
    1,070  feet of 2  3/8-inch tubing outside the long string
    1,120  feet of 2  3/8-inch tubing inside the long string
    Baker Model "L" Sliding Sleeve
    Baker Model "AD-1" Tension Packer

-------
*    DelKfcJr IVIUUBI  O-U  lezllUOIII I Cl loiui I  I aorvci
    Baker Model "R" Profile Nipple 1.78
    Baker Model "RW" Profile Nipple 1.81
    Baker Model "F"  Profile Nipple 1.87
    Baker 5 1/2-inch Float Shoe
    Hinderliter 10FSF Wellhead for dual completions (5 1/2-inch and
        2 3/8-inch)   .
    3 centralizers 5 1/2-inch                                   '
    The surface equipment for the  Leak Test Well  consists of two
100-barrel  fiberglass tanks,  a  10-horsepower electric  powered
injection pump,  high pressure injection  flow  lines and  schedule 40
plastic return flow lines (Figure 11). The water supply is from the City
of Ada, Oklahoma. The control accessories are an air chamber, which
smooths out the pumping actions of the pump  pistons; a pressure
control valve, which can be set to any predetermined pressure from
10 to 600 psi; a check valve which prevents back flow in the injection
line; a strainer to catch foreign material that may be pumped into the
line; a flow meter to record the number of barrels of liquid pumped; a
flow outlet pipe used to calibrate  the flow meter; a  control valve to
regulate the flow to the injection well; a thermometer to determine the
temperature  of the injected fluids; and pressure gauges to indicate
the injection pressure (Figure B-1).
    Flow into the well can be  controlled so that the injected fluids are
directed into the 2 3/8-inch injection tubing, the tubing/casing anriulus
or to the 2 3/8-inch  outside tubing. Returned flows can be  controlled
from the 2 3/8-inch outside tubing and also from  the annulus of the 5
1/2 inch casing.
    Three monitoring wells  were  constructed around the  Leak Test
Well to depths of 710, 935 and 1,130 feet. The casing and equipment
for the monitoring wells included:

A/o. 1
15 Baker Centralizers, 4 1/2-inch
Halliburton Super Seal Float Shoe
671 feet of 4 1/2-inch steel casing, 10.6 #/ft
2-inch Johnson stainless steel well screen, .010-inch  slot with bottom
  plate
20 feet of 2-inch line pipe on top of screen
2- to 4-inch shale cup
Johnson "K" type packer, 4 1/2-inch
80 feet of 9 5/8-inch conductor pipe, 36 .#/ft
4 1/2- to 2-inch steel swage/cap

A/o. 2
21 Baker Centralizers, 4 1/2-inch
Halliburton Super Seal Float Shoe
905  feet of 4 1/2-inch steel  casing, 10.6 #/ft
                                50

-------
        Flow Return Line
                *
                                    Flow   Thermometer
                                    Meter
     From Water
     Supply Tank
 o
                                                              To
                                                           Injection
                                                              Well
Pressure
Gauges
 Figure B-1. Injection pump and control accessories.

 2-inch Johnson stainless steel well screen, .011-inch slot with bottom
  plate
 21 feet of 2-inch line pipe on top of screen
 Johnson  "K" type packer, 4 1/2-inch
 80 feet of 9-5/8" conductor pipe, 37 #/ft
 4 1/2- to 2-inch steel swage/cap
 A/o. 3

 27 Baker Centralizers, 4 1/2-inch
 Halliburton Super Seal Float Shoe
 1,130 feet of 4  1/2-inch steel casing, 10.6 #/ft
 2-inch Johnson stainless steel well screen, .010-inch slot with  bottom
  plate
 20 feet of 2-inch line pipe on top of screen
 80 feet of 9 5/8-inch conductor pipe, 36 #/ft
 4 1/2- to 2-inch steel swage/cap

Wells No.  1   and  2 were drilled  using  air rotary to  prevent
contamination of the zones to be monitored by drilling fluids. Well No.
3 could not  be  completed using air so it was drilled with mud rotary.

    The  procedure  followed for  drilling  the wells  and  the  dates
involved are indicated in Table B-1.

-------
  Table B-1.    Procedure for Drilling the Monitoring Wells
                       Activity	
                                                Date Completed
   Monitoring Well No. 1
       1.   Rig up, air drill 9-inch diameter hole to 82
           feet, ream 12 1/2-inch hole to 82 feet, set
           and cement 9 5/8-inch conductor pipe
       2.   Drill 8-inch hole to 680 feet, run 4 1/2-inch
           steel casing with centralizer on each collar,
           cement with latex cement (Halliburton)
       3.   Drill remaining 30 feet with 3 7/8-inch bit
       4.   Set 2-inch by 30-foot Johnson stainless steel
           screen

   Monitoring Well No. 2
       i.   Rig up, air drill 12 i/4-inch diameter hole

       2.   Cement conductor pipe
       3.   Drill 8-inch hole to 905 feet, run 70 sacks of
           gel to stabilize hole
       4.   Run 4 1/2-inch steel casing with centralizer
           on each collar
       5.  Cement with spherelite cement (Halliburton)
       6.  Drill to 935 feet with 3 7/8-inch tricone bit, set
           2-inch by 30-foot  stainless steel screen with
           bottom plate

   Monitoring Well No. 3

       1.   Rig up. drill 12 1/4-inch diameter hole to 80
            feet,  set and cement 9 5/3-inch conductor
            pipe             |
            Dig mud handling pit
            Drill 7 7/8-inch hole  to 1,130  feet,  run 4 1/2-
            inch steel casing with float shoe
            Cement with foam cement (Halliburton)
2.

3.


4.

5.


6.
            Perforate zone from 1,120 to 1,130 feet, 21
            shots
            Swab casing, set 2-inch by 20-foot stainless
            steel screen                       	
                                                   11/17/87



                                                   11/24/87



                                                   11/28/87

                                                   11/28/87
                                                   11/30/87

                                                   12/01/87

                                                   12/03/87


                                                   12/04/87


                                                   12/08/87

                                                   12/21/87
12/01/87



12/08/87

 1/09/88


 1/10/88

 1/14/88


 1/14/88
Test Summaries
    A number of specific tests are planned for the Leak Test Well. As
the tests are  completed,  brief summaries are prepared and forwarded
to  the  Underground  Injection  Control Program  Offices   in  EPA
Headquarters and  the regions. Summaries of those  tests completed
to date are included as follows:
                                     52

-------
 Test Mo. 1: Acoustic Cement Bond Tool  Test for  Flow Behind
 Casing


 Introduction

    In November 1986, personnel from Regions IV and V witnessed a
 demonstration  of  the use  of  an acoustic  cement bond  tool  for
 detecting fluid movement behind casing. The demonstration was
 conducted by Dresser Atlas personnel at their field office  in Olney,
 Illinois, and  involved pumping  water through  the annular space
 between two concentric  pieces of pipe while holding the bond tool
 stationary in the inner pipe.

    EPA personnel suggested that the tool(s) be tested in the  Leak
 Test  Well at the Robert  S.  Kerr Environmental Research Laboratory
 (RSKERL) to get a better definition of the sensitivity of the tool and
 the conditions under which it will or will not work.

    C.D. "Mac" McGregor, a log analyst for Dresser Atlas, contacted
 RSKERL personnel, and plans were made to run the tests on January
 23, 24, and 25, 1987.

 Test Well Conditions

    The  purpose of the  test was to determine if  flow of water at
 various rates could be detected behind pipe using the data presented
 by the fluid wave from a cement bond tool. The test was developed in
 two phases: Phase  I looked  at flow immediately behind  casing under
 free-pipe conditions, and Phase II looked at flow  in tubing behind
 casing under  conditions  which  would possibly simulate  flow  in a
 channel in cement.

    Figure  B-2  indicates  the configuration  of  the Leak Test Well  for
 the initial test.  In  this configuration, water was pumped  down the
 tubing/casing annulus  into the injection zone.  This represents flow in
 the free-pipe condition, i.e.,  no cement behind the  pipe (2 3/8-inch
 tubing in this case).

    Figure  B-3  indicates  the  well configuration  for the  second  test,
 which  was designed to simulate flow in  a channel in  cement.  The
 section of the well between  1,070 and 950 feet has cement behind
 the 5  1/2-inch casing and  thus around the 2 3/8-inch  tubing. Thus the
 tubing in that area represents, to some degree, a channel in the
 cement. In this phase, water was pumped down the 2 3/8-inch tubing,
 into the 5 1/2-inch casing  and out the perforations.

 Test • Phase I
    The test was conducted with a 1 11/16-inch OD Acoustic Cement
 Bond  Tool with a single transmitter/single receiver with 4-foot spacing.
The tool  was placed in  the injection tubing at 57 feet and  the
oscilloscope was viewed in the no-flow and flow conditions.

-------
                                           .680ft
                                                        Flow=
                                             710ft
                                            • 905ft
                                             935ft
                                                     Injection Zones
                                           CBL Liquid Flow Test - Phase I
                                              1.   Unseat packers #1 & #5.
                                              2 '  Plug profile nipple #4
                              1057 ft Depth of  3.   Fill tubing (#2) with water
                                Upper Packer  4.   Set CBL tort in 2 3/S-.n
                                 HH               tubjnฃ at yajiable depths
                                              5   Pump water down 5 1/2-in
                                                  casing at 3 different rates
                                   Cement
                                   1070ft
               1.   Baker Model "C-1"
                   Tandem Tension Packer
               2.   2 3/8-in Tubing
               3.  Baker Model "L" Sliding
                   Sleeve
               4.   Baker Model "R"
                   Profile Nipple
               5.   Baker Model "Ad-1"
                   Tension Packer

1084 ft Depth of *•  B^Mbde^V
  Lower Packer  •  p^f fla Nipple
               8.  Baker Mpdel "F'1'
	1100ft         .Profile Nipple
               9.  5 1/2-in Long String

.....,...................-,.v  1120ft
                                 Leak Test Well
Figure B-2. CBL liquid flow test - Phase I.
                                     54

-------
           Cement Bond Log Tool
                                                           Flow=
                                                 . 905 ft
                                                  935ft
                                                          Injection Zones
                                               CBL Liquid Flow Test - Phase II
                                             1.  Pull tubing and packers
                                             2.  Set plug in 5 1/2-in casing at
                                                101.0 ft
                                             3.  Pull tubing
                                            4.  Fill 5 1/2-in casing with water
                                            5.  Set CBL tool in 5 1/2-in casing
                                                at variable depths
                                            6.  Pump water down 2 3/8-in leak
                                                tube at 3 different rates
                                       Cement
                                            1.   2 3/8-in Tubing
                                            2.   Baker Model "R" Profile Nipple
                                            3.   Baker Model "F" Profile Nipple
                                            4.   5 1/2-in Long String
                                                 1120ft
                                   Leak Test Well
Figure B-3. CBL liquid flow test - Phase II.

-------
                         1 I OOl "" I I 1C1OO I
                                           Oscilloscope
            Time           Flow Rate        Response
          1:50 p.m.          No flow            None

          2:00 p.m.           8 gpm             Yes
          2:03 p.m.           4 gpm             Yes

          2:17 p.m.         0.78 gpm            Yes

          2:20 p.m.       0.78 gpm  + air         Yes
          2:24 p.m.       6 gpm + air          Yes

          2:30 p.m.      Stopped injection        Yes


    The test was repeated with the tool at various depths in the well,
with the same  results; that is, the oscilloscope indicated no distortion
of the fluid wave in the no-flow condition and distortion at all three
flow rates. The distortion was greater when air was added to simulate
gas movement behind the pipe.

Test - Phase II
    The second  test  was conducted  with the  tubing  and  packers
removed and  a bridge plug set, as indicated by  Figure B-3. The
Acoustic Cement Bond Tool  used for this test was a 3 5/8-inch OD
tool with single transmitter/single receiver with 5-foot spacing.

  •ป                      Test - Phase II
                                           Oscilloscope
      Tool Depth (feet)  Flow Rate (qpm)     Response
            600                8               None

            700                8               None
            800                8               None

            900                8               None

            1,000               8               None
    The tool was initially set immediately above the bridge plug and
the oscilloscope viewed in the no-flow condition. Water was then
pumped down the outside tubing at a rate of 8 gpm.  No distortion of
the fluid wave was evident on the oscilloscope. The tool was then
moved up the hole in 100-foot increments. No distortion of the fluid
wave was evident at any depth, thus no flow was detected  in the
tubing.
                              56

-------
Conclusions
    The  Phase I test results indicate  that the  fluid  wave  of the
Acoustic Cement Bond Tool responded to fluid movement behind the
tubing  in a free-pipe  condition, that is, with  no cement behind the
pipe. A response was  evident with flow as low as 0.78 gpm.

    The tool  used  in the Phase II  test did not  pick up flow in the
2 3/8-inch tubing either within or above the cemented section of the
well. Thus, flow in the manmade channel behind the 5 1/2-inch casing
could not be detected under the test conditions.

    One explanation  for the responses observed  under  the test
conditions previously  outlined is  that under free-pipe conditions, the
paths for movement of the sound wave are through the casing arid
fluid. Thus, under static conditions, where the tool is not moving and
there is no movement of fluid in or behind the pipe, the fluid wave, as
presented on the oscilloscope, is also static. On the other hand, flow
of fluid behind the pipe while the tool is stationary affects the sound
wave as it moves through the fluid,  causing a distortion of the wave.
This distortion shows up as rapid changes in amplitude in the display
of the fluid wave on the oscilloscope and indicates movement of the
fluid. Thus, under free-pipe conditions, the fluid wave has the capacity
to reflect fluid movement behind pipe.

    The  presence  of cement behind pipe presents a  much more
difficult set  of conditions for identifying fluid  movement  with  the
cement bond  tool.  The  paths for  the sound wave  under these
conditions are movement along the  casing and  cement (small signal
because of the attenuation effect of the cement behind the casing),
movement thro'ugh  the formation and  movement through  the  fluid.
The heterogeneity of the formation, the  size of the channel, and type
and amount  of fluid movement will all affect the ability of the  tool to
identify fluid  flow in channels in  cement. Thus, the  capability of the
Acoustic Cement Bond  Tool to identify fluid  flow  in  channels  is
unproven, though certainly not impossible.

Recommendations
    Field data should  be accumulated to determine  the  capability of
this type of tool  for  detecting flow behind casing in varying well
conditions, i.e., free pipe and channels in cement.

    When running other tools, such  as  temperature or noise surveys
for detecting flow  behind pipe,  service companies should run the
bond tool for comparison purposes  to determine if flow in  channels
can be detected.

-------
 Behind Casing

                                                             ]„..
 Introduction
     On January 23 and 24, 1987, personnel from the Robert S.  Kerr
 Environmental Research Laboratory (RSKERL) and Dresser Atlas
 conducted a  series of tests for determining  flow behind pipe using
 two neutron activation tools.
                                                     •
     The purpose  of  the tests  was  to determine if  flow of  water  at
 various rates could be detected behind pipe using the data presented
 by & pulsed neutron  lifetime logging system (PDK-100) and  a Cyclic
 Activation Tool.

 Tools Tested
     Two tools were tested during the 2-day period:

     • A 1 11/16-inch diameter PDK-100 Tool
     * A 3 5/8-inch diameter Cyclic Activation Tool

     The  operation  of both tools is based on a nuclear activation
 technique in which flowing water is irradiated with neutrons emitted by
 a logging sonde. These neutrons interact with oxygen nuclei in  the
 water to produce nitrogen-16 (16N), which  decays with a half-life of
 7.13 seconds,  emitting gamma radiation.  The flow is then computed
 from the energy and  intensity response of two gamma ray detectors
 mounted in the logging sonde.

 Test Well Conditions

    The tests were developed in four phases, the first three using the
 PDK-100 Tool and the last using the Cyclic Activation Tool.
                          i                                   i . •
    Figure B-4 indicates  the  configuration of the Leak Test  Well for
 the  initial test. In  this configuration, water was pumped down  the
 tubing/casing annulus  into  the  injection zone with the 1  11/16-inch
 diameter PDK-100  Tool'held stationary  in the 2 3/8-inch  injection
 tubing. This condition represented flow in the free-pipe condition, i.e.,
 with no cement behind the pipe (2  3/8-inch tubing  in this case). A
 valve at the surface on the outside 2 3/8-inch tubing was closed so
 that circulation was not possible up that tubing.

    Figure B-5 indicates  the well configuration  for the second test,
 which was designed to simulate upward flow in a channel in cement.
 Water, pumped down the  tubing/casing  annulus, moves  through a
 1/4-inch hole in the 5 1/2-inqh casing at 1,070 feet and up the 2 3/8-
 inch outside tubing. The  section  of the well between 1,070 and 950
feet has  cement behind the 5 1/2-inch casing and  thus around the
2 3/8-inch tubing. The tubing in that area represents, to some  degree,
a channel in the cement.
                               58

-------

1% vX
1



5-







-
_M
looo
V
s~
*.li
* II
\_
1
_^
1
~\
1,
"'



<
V—
1
t
-7>

^
^ V<
(
1
1

,
>
4-
i
/,'jlM
_ Lo

" .if".!

- *J
(1
i :


.\x- 8:::::::::v:vv.'v::::::.'v:: Flow- X
:::::;x:S:::::;::::x::: ::fe: :::x x: :: 7 1 Q ft

	 905 ft

Injection Zones
	 nryK ft '
— 6
1057 ft Depth of
Upper Packer
NAT Liquid Flow Test - Phase I
1 . Unseat packers #1 & #5
2. Set NAT tool in 2 3/8-in tubing
at variable depths
3. Pump water down 5 1/2-in
casing at 3 different rates
	 Cement
1 070 ft
1 . Baker Model "C-1 " Tandem
Tension Packer
2. 2 3/8-in Tubing
14 ft Depth of 3. Baker Model "L" Sliding Sleeve
wer Packer 4. Baker Model "R" Profile Nipple
5. Baker Model "Ad-1"Tension
. Packer
6. 2 3/8-in Tubing
7. Baker Model "R" Profile Nipple
8. Baker Model "F" Profile Nipple
9. 5 1/2-in Long String
	 1 1 00 ft
..v.:.:.v:..y-:-:-: :•:•.•••.. ' l<;u u

                               Leak Test Well
Figure B-4.  Neutron activation tool liquid flow test - Phase I.

-------
Ni

.
	
i"


4"
5-
	 1,


'&**&%&.
i
m
*•>**.•••&?.
(ffjs'j
:i.{
8
•\1
-v.;..... • -\
*"v.::'*::'. :' '*•

1
I
(>

4 "
4
V
ป
ooo

^
/
k 1
* 1
\
*

1

_>
4
\
1,
't
	
'8
•# ฃฃ vl^^iii-^1-
V
>
	 71




<
II
1
i
1
1
j*l
yi.
!'!•
S'
IP
X
'••> -V
•u>
;<-9ii
VJ •
j5t,i\
^ir
*' -C
f-
r
^^_
L
_ซ.*ป.
iS
f
ft'MK
|ซ*f,
Hj\5>;:
'li^i
ปซ
;>.}>>'•
'>.,&# K*PI
.R.;ซ<;i.iA\ft.
l|
•\2i"
.&.
••^ป
" 's
?I*
r "
V
S^l
!ปl!!iMi
•?c3rrf
Vs
^
ฃ•
	 680 ft
^ o fiSSS'-:''-^:!'!^:'-? Flow = 1
|vj: o:::::i:::v:i:>.::v;v>.:::™ •
•Wx^xWivXiAvX:::^::! 7m ft


	 on=; ft •..;:..:.:.:.:.:::.:;..

*-J 7 Injection Zones
CMR ft
~6
1057ft Depth of
Upper Packer
NAT Liquid Flow Test - Phase II
1. Unseat packer #1
2. Plug profile nipple #4
3. Set NAT tool in 2 3/8-in tubing
at variable depths
4. Pump water down 5 1/2-in
casing and up 2 3/8-in tubing
	 Cement
1. Baker Model "C-1" Tandem
in?nft Tension Packer
2. 2 3/8-in Tubing
3. Baker Model "I." Sliding Sleeve
4*. Baker Model "R" Profile Nipple
5. Baker Model "Ad- 1 "Tension
Packer
6. 2 3/8-in Tubing
7. Baker Model "R" Profile Nipple
8. Baker Model "F" Profile Nipple
9. 5 1/2-iii Long String
1084 ft Depth of
Lower Packer
	 1100 ft
11 on ft
	 	 1130ft

                              Leak Test Well
Figure B-5. Neutron activation tool liquid flow test - Phase II.
                                   60

-------
     Figure 8-6 indicates the well configuration for the third test, which
 was designed to simulate downward flow in  a  channel  in  cement.
 Water, pumped  down the 2 3/8-inch outside tubing,  moves through
 the 1/4-inch hole in the  5 1/2-inch casing at 1,070 feet and up the 5
 1/2-inch casing to the surface.

     Figure B-7 indicates the well configuration for the final test, which
 was designed to simulate downward flow in a  channel in cement
 using the  larger  Cyclic Activation Tool.  Water,   pumped down the
 2 3/8-inch outside tubing, flows into the 5 1/2-inch casing through the
 1/4-inch hole and out through  perforations into the injection interval
 from 1,120 to 1,130 feet.

 Test - Phase I

     This test was conducted  with the  PDK-100 Tool with the two
 detectors located below  the neutron generator so  that downward flow
 could be  detected.  With the  tool  located at  300 feet inside the
 2 3/8-inch injection tubing, data was  obtained under conditions of no
 flow and flow of  8, 4 and 1 gallon per minute (gpm). Two replications
 of these flow rates were  conducted and flow was detected by the tool
 in all instances.

 Test - Phase II

     This test was conducted with the PDK-100  Tool with the two
 detectors located above the neutron generator to determine if flow Lip
 the outside 2 3/8-inch could be detected. With the tool located at 600
 feet, data  was obtained  under no flow,  and 8 gpm flow conditions.
 Flow up the outside 2 3/8-inch tubing could not be  detected.

 Test - Phase III

    This test was conducted with the PDK-100 Tool at 600 feet with
 the  generator-detector configuration  identical to  the  Phase  II test.
 Water was  pumped down the  2 3/8-inch outside tubing  and up the
 5- 1/2" casing at three different rates (8,4 and 1 gpm). Upward flow
 was detected in the 5 1/2-inch casing at all three flow rates.

    The tool configuration was then changed with the.detectors below
 the generator to  determine if downward  flow in  the outside tubing
 could be detected. Flow down the outside 2 3/8-inch tubing could not
 be detected.

 Test - Phase IV

    This  test  was  conducted using  a 3 5/8-inch diameter Cyclic
Activation Tool. The detectors were located below the  generator for
detecting flow in  the 2 3/8-inch tubing  as water moved  down the
tubing, through the 1/4-inch hole into the 5 1/2-inch casing  and out
the perforations into the injection interval.  Flow rates for this test were
7.8, 6.1 and 0.79  gpm. All three flow rates were detected by the tool,

-------
9I



1 -
3.

4.
5-
	 &


jj^-a-j.
i
?ฃJ*2$ฃ
aiifejy
~^E$
IS


l|i
3
1
t
t
\

t
t
X
ooo

^_
t

„ 1
* 1
r
ff

I
,ป • "-1
1
I
J
t
\
I
t
4
"R
'SKSSirtMcSii'in;
k >






^ <
ซ
H
-^

~
ts
T
t
1
"i
I
•
i
-
4
1
J,
^

k
P*
-*-
— — ~
'•+
n


'•:• . •/••• :':-.-;'. -'::::: :::::
..v'.v HVV.-!.. :'.'-: 710 ft
905 ft
: -..'•. •"' ;' '•''• • ' en* ft tn-

3W= 1



ection Zones
1057 ft Depth of
Upper Packer
NAT Liquid Flow Test - Phase III
1. Unseat packer #1
2. Plug profile nipple #4
3. Set NAT tool in 2 3/8-in tubing
at variable depths
4. Pump water down 2 3/8-in
tubing and up 51/2-in casing
	 Cement
1. Baker Model "C-1" Tandem
1070ft Tension Packer
2. 2 3/8-in Tubing
3. Baker Model "I." Sliding Sleeve
4. Baker Model "R" Profile Nipple
5. Baker Model "Ad-1 "Tension
Packer
6. 2 3/8-in Tubing
7. Baker Model "R" Profile Nipple
8. Baker Model "F" Profile Nipple
9. 5 1/2-in Long String
1 084 ft Depth of
Lower Packer
— •• — 1 1 00 ft
11TI ft



                               Leak Test Well
Figure B-6.  Neutron activation tool liquid flow test - Phase III.
                                   62


-------
 5 1/2-in I
                                      Cement
                                       1070ft
                                  ........,,,..:.:.;.:.•.• :.:.;.;.:.v!; 680 ft

                                  I 3W$i$i%iiff ;         Flow= j
                                  mmmmyfm 710ft
                                                  935 ft
                                                          Injection Zones
                                           NAT Liquid Flow Test - Phase III
                                           1.   Pull tubing and packers
                                           2.   Set plug ins 1/2-in casing at 1010 ft
                                           3.   Pull tubing
                                           4.   Set NAT tool in 5 1/2-in casing at
                                               variable depths
                                           5.   Pump water down 2 3/8-in leak
                                               tube at 3 different rates
                                             1 .  2 3/8-in Tubing
                                             2.  Baker Model "R" Profile Nipple
                                             3.  Baker Model "F" Profile Nipple
                                             4.  5 1/2-in Long String
                                                1120ft

                                                1130ft
                                  Leak Test Well
Figure B-7.  Neutron activation tool liquid flow test - Phase IV.

-------
arid IIUW VtJlUUlUWS wwiw
tool.
                                   num mo vjaia oun-av^i.^0 w
Conclusions
    The PDK-100 Tool was able  to detect all three flow rates when
flow was up or down the 5 1/2-inch casing.  The tool did not detect
any flow up or down the outside 2 3/8-inch tubing.
    The Cyclic Activation Tool was able to detect all three flow rates
in the outside  2 3/8-inch tubing. In addition, the computer associated
with the tool has the capability to  compute a velocity of flow for each
flow rate.

Recommendations
    Additional  work should be done to increase the sensitivity of the
PDK-100 Tool. It  should  be noted here  that since the tests were
conducted, Dresser Atlas personnel have made some modifications to
the PDK-100 Tool and have been  able to detect flow in outside tubing
in a well constructed  very  similarly to  the  Leak  Test  Well.  The
adjusted tool will be retested'at the RSKERL  Test Facility as soon as
it can be arranged. In the meantime, Dresser Atlas  personnel will run
the tool in several  wells owned by Mobil, and will make  those results
available to RSKERL personnel.
    The Cyclic Activation  Tool should  be tested  under "real well"
conditions to verify the results seen during the tests on the Leak Test
Well.
    The capability  of this equipment to locate flow behind pipe could
be  a  significant  breakthrough  for  mechanical   integrity  testing.
Especially the PDK-100 Tool, which can  be  run in tubing  filled with
water or with  only air present. Thus, no workover costs  would  be
involved in testing  a well, i.e., setting plugs, pulling tubing, etc.
                         i         '                         i
                                64

-------
 Test No. 31. Testing fop a Hole in the Long String


 Introduction

    On January 23, 24 and 25,  1987, test results from testing tools
 for detecting flow behind casing indicated a possible hole in the 5 1/2-
 inch long string of the research well. A series of tests was conducted
 on the well on January  25 and 27, and February 2, 3, 10, 11  and 12
 to determine whether there was a hole in the pipe.

 Test Well Conditions

    Figure  B-8 indicates the  well  configuration  during most  of the
 tests  to be discussed. Any changes in the well will be noted  as the
 various tests are discussed.

    During  testing of an  Acoustic Cement Bond Tool (ACBT), the
 5 1/2-inch casing was full of fluid above a bridge plug and water was
 being pumped down the outside 2 3/8-inch  tubing at about 8 gpm.
 Pumping had  been in progress  only  about 5 minutes  when  water
 began flowing out of the 5 1/2-inch casing at about 2 1/2 gpm.

    The  immediate  thought  was  the  bridge plug  was  leaking;
 however, the  Baker Packer  representative  was  confident  that  the
 bridge plug could not leak.  In checking  the setting depth for the  plug it
 appeared possible that it was located opposite a casing  collar. The
 plug was reset to ensure that it was properly set between collars.

Acoustic Cement Bond Tool

    A plan was developed to systematically check the  well to
determine where the leak was in  the system. The first approach was
to use the  ACBT to determine if flow in  the  5 1/2-inch casing was
occurring. The tool was set immediately above the bridge plug,  which
was set at  1,010 feet, and readings were taken to determine  if flow
would be reflected by the fluid wave. The tool was then moved up the
well at 100 foot increments and readings taken,  with the following
results:

                                     Flow Indicated
                     1,000                 No
                       900                 No
                       800                 No
                       700                 No
                       600                 No
                       500                 No
                       400                 No
                       300                Yes
                       250                Yes
                       200                Yes

-------
                                  • Cement
                                    •1070ft
                                              680ft


                                              710ft



                                             -905ft


                                             • 935 ft
Injection Zones
                                          1.  2 3/8-m Tubing
                                          2.  Baker Model "R" Profile Nipple
                                          3.  Baker Model "F" Profile Nipple
                                          4.  5 1/2-m Long String
                                             1120ft
                                          	1130ft
                                Leak Test Well
Figure B-8.  Testing for a hole in the long string.
                                    66

-------
     7r\e tests were rerun with the same results. Thus, the ACBT data
 indicated that  flow might be  coming into the casing at around 300
 feet.

 Down-Hole TV

     On  January 27, 1987 Layne-Western  Company  brought their
 down-shot camera to survey the well, to locate any hole that might be
 present. The regular lens would not give a good image, so a lens that
 must be  used in  air rather than water was tried.  First the well was
 swabbed so that the water  level  was about  870 feet below  land
 surface.

     The camera,  which had  never been run in 5 1/2-inch  casing,
 provided  an excellent picture  of the casing  as it was lowered down
 the casing. An anomaly was seen  at  about 240 feet  that could
 possibly be a damaged area of the casing.

 Pressure Test - Gas

     The next test was to pressure the well with nitrogen and shut it in
 to determine if any loss of pressure would occur over time. The well,
 with the bridge plug still intact at 1,010 feet, was pressured to 185 psi
 with nitrogen and shut in. There was no loss of pressure evident after
 1 hour.

 Pressure  Test - Water

    The gas pressure was relieved and the injection pump hooked up
 to fill the  5 1/2-inch casing with water. After filling, 150  psi pressure
 was added to the weight of the water column and the well was shut in
 for 1 hour. No pressure drop was noted.

    Pressure was  relieved and water was pumped down the outside
 2 3/8-inch tubing at about 8 gpm. After pumping for only 5 minutes,
 water  began flowing out of the 5 1/2-inch casing  at a rate of about
 2 1/2 gpm.

 Pressure Test - Packer

    Next, Baker Packer, using a full-bore packer on tubing performed
a series of pressure tests with the packer set at various depths in the
casing, as follows:

      Packer
      Depth          Pressure       Drop in Pressure
       feet             psi           after 5 Minutes

        11r             92                None
       295            115                None
       595            100                None

-------
    The  final  test  was  !a  modified "Ada  Pressure Test."  After
removing the bridge plug, nitrogen was used to move the state water
Ivel toward the hole in the  5  1/2-inch casing. A pressure of 380 psi
was placed on the fluid in the  casing and held overnight with no loss
of pressure.

Conclusions
    The  series  of  pressure tests  performed  on  the well  clearly
indicated no hole is present in the 5  1/2-inch casing. The differential
presste bridge'plug  apparently did  not  have  sufficient  pressure
differential  to set securely, thus  allowing  the  plug to leak  when
injection was taking place down the outside tubing.
    The  ACBT and down-hole TV were inconclusive in that a doubt
still existed after reviewing data from  the tests.
                                 68

-------
Test No. 4: Ada Pressure Test

Introduction

     Early in the mechanical integrity test program, it was discovered
that some wells could not be tested using the standard pressure test.
For example, a number of wells in Osage  County,  Oklahoma,  could
not use the standard pressure test because  of perforations in the long
string above  the packer. EPA  regional  personnel suggested that a
procedure similar to  the air line  method for determining the  water
level in a producing water well  should be explored  as an  alternative
for testing those wells whose  "special" construction  would  not permit
the use of standard pressure tests.

Development of Test

    A possible  alternative to  the standard  pressure  test  is to use
compressed air or nitrogen to depress the static water  level below the
point to be tested and hold the pressure for a specific period of  time.
If the pressure holds, the tubular goods above the fluid level  have no
leaks.

    Table B-2 indicates theoretically what would take place in the well
as pressure is added to the tubing to depress the water. With a static
fluid level of 360 feet below the  land surface, the hydrostatic head at
the perforations would be 760 feet. The tubing  gauge pressure and
the pressure at the fluid level would both be zero.  This hydrostatic
head would exert 307  psi at a depth of  1,070 feet, and 329  psi at a
depth of  1,120 feet.  As  pressure is  added  from cylinders  of
compressed gas, the gauge pressure increases and  depresses the
fluid level, thus reducing the hydrostatic head  by  a  corresponding
amount.  The pressure at the  gauge and pressure at the fluid  level
remain equal  throughout the procedure. Thus,  the  pressure at the
point of  consideration  remains constant  in that  the hydrostatic
pressure is replaced by gas pressure during the test.
Table B-2   Effects of Adding Pressure to Depress Water
                       Hydrostatic
Tubing
Gauge
Reading
(psi)
0
100
200
300
307
329

Depth to
Fluid Level
(feet)
360
591
822
1,053
1,070
1,120
Head
Above
Perforations
(feet)
760
529
298
67
50
0


psi @ Fluid
Level
0
100
200
300
307
329


psi ฉ Hole
(1,070 feet)
307
307
307
307
307
329


psi @ Pert.
(1,1 20 feet)
329
329
329
329
329
329

-------
impiemenuriy ii
     On December 4, 1985, two tests were implemented to determine
if pressure testing with compressed air was a viable option for testing
special wells.  The configuration  of the Leak  Test Well  was  altered
slightly for  each of  the tests  to represent real world situations  as
closely as possible (Figure B-9).
                          i                .  .                   i
                                                   Injection Zones
                                          1.   Surface Casing (571 ft)
                                          2.   2 3/8-in Tubing
                                          3.   Baker Model "L" Sliding
                                              Sleeve
                                          4.   Baker Model "R" Profile
                                              Nipple
                                          5.   Baker Model "Ad-1"
                                              Tension Packer
                                          6.   2 3/8-in Tubing
                                          7.   Baker Model "R" Profile
                                              Nipple
                                          8.   Baker Model "F" Profile
                                              Nipple
                                          9.   5 1/2-in Long String
                                          10.  Baker Model "C-1" Tandem
                                              Tension Packer
1084 ft Depth of
 Lower Packer
       1100ft
        1120ft
        1130ft
 Figure B-9. Leak Test Well.
     The first test was  conducted with the sliding sleeve  closed,  to
 represent no leak in the system,  and the second test was  conducted
 with the  sliding sleeve open,  to  represent a leak in  the tubing  at a
 depth of  1,070 feet. The fluid level in the injection tubing as measured
 with an  Echo Meter was 360  feet  below the land surface.  That
                                  70

-------
         a hydrostatic head of 710 feet at the hole at 1,070 feet arid
 760 feet of head at the perforations at 1,120 feet. Assuming 2.31 feet
 per psi, it would require 307 psi to depress the water level to a depth
 of 1,070 feet and  329 psi to depress  the  water level to a  depth of
 1,120 feet.

 Test  1

    In  the  first test,  with the  sliding  sleeve closed,  the pressure
 should have  reached 329  psig before the pressure could not be
 increased. This would indicate that the fluid level was at the top of the
 perforations  at 1,120 feet, and with  the  gas source closed the
 pressure gauge should continue to read 329 psig.

    A pressure of 380 psig was added  without reaching the  point
 anticipated. When the cylinder  was  closed the  pressure  dropped
 below 329 psig, and repeated attempts to increase the pressure gave
 the same results. The source of compressed gas was exhausted and
 the test was stopped without reaching the point of stabilization at 329
 psi.

    This behavior  seems  to  indicate that the permeability of the
 injection zone was  low and the formation  would not accept the water
 fast enough to depress the water level  as quickly  as anticipated.
 Thus,  during the time of the test, the fluid level in the tubing was still
 being depressed but had not had time to reach the desired level.

 Tesf 2

    In  the second test, with the sliding sleeve open, 307 psig should
 have depressed the water level to a depth of 1,070 feet, and it should
 have  been impossible to add  additional pressure  because pressure
 was lost through the hole in the long string at that depth. However, an
 inability to  increase the pressure was reached at a pressure of 300
 psig.  The  pressure remained  at  300  psig after  shutting  off  the
 compressed gas source.

    On May 1, 1986, the  well  was  acidized and injectivity  tests
 indicated a permeability of 125 millidarcies  (md). The second series of
tests was  run with  the results comparable to those predicted in the
table.  Nitrogen was used to eliminate any explosion hazard that might
have been presented by using compressed air.

    The test was rerun on February 11, 1987, using  nitrogen, and the
results confirmed the response seen in May 1986.

-------
Conclusions
    The test results indicate that an annulus pressure test can be run
on certain wells that have special conditions that prevent the running
of  standard  pressure  tests. The  following  conditions  are
recommended to assure that the test has validity for a specific well:

1.  The fluid level in the zone being tested must have  reached static
    conditions before the test is run.
                                                           !
2.  The  specific  gravity of the injected water must  be  known to
    calculate the pressure  required to  depress the fluid level  to  a
    specific depth.
                                72

-------
Test No. 5:  Nuclear Activation  Technique for  Detecting  Flow
 Behind Casing

 Introduction
    On  April  8,  1987,  personnel from  the  Robert  S.  Kerr
 Environmental  Research  Laboratory  (RSKERL) and  Dresser  Atlas
 conducted a series of tests to determine flow behind pipe  using the
 PDK-100 Flow Tool.
    The purpose of the tests was to determine if flow  of water  at
 various rates could be detected behind pipe from data presented by a
 pulsed  neutron lifetime  logging system (PDK-100). The 1 11/16-inch
 diameter tool had been tested on January 23 and 24, 1987, and  could
 detect  flow immediately behind the  injection tubing  but could not
 detect  flow in  the  outside  2 3/8-inch  tubing.  The tool had  been
 modified for the new series of tests.
 Test Well Configuration
    Figure  B-10 indicates the configuration of the Leak Test Well for
the test. Both  packers  were set,  the sliding sleeve was open and
injection was maintained down the outside tubing at varying injection
rates.
Tool Testing
    For each flow rate the PDK-100 was held stationary at a depth of
300' in  the injection tubing. After taking two background checks, flow
was initiated down the outside tubing at a rate Of 8 gallons per  minute
(gpm), 6, 4, 2,  and 0.105 gpm. The results of the tests for detecting
flow are as follows:
            Flow Rate (gpm)           Flow Detected


                    8                      Yes
                    6                      Yes
                    4                      Yes
                    2                      Yes
                    0.105                   No
    Readings were taken three times at each  flow rate.

Conclusion
    The PDK-100 was able to detect four of the five flow rates with
no problem. Movement  was detected for the 0.105 gpm  flow but  it
was probably the column of water in the tubing moving toward static
conditions, since at this extremely low flow the fluid level in the tubing
could not be maintained.

The  capacity of this  tool  to  locate flow behind casing  looks  very
promising. The  next phase should  be field testing under  "real well"
conditions.

-------
                                               680ft
                                               710ft
                                               905ft
                                               935 ft
                                                        Flow=
                                                       lr|Ject'on Zones
                                            NAT Liquid Flow Test

                                         Pump water down 2 3/8-in tubing (6),
                                         through sliding sleeve (3),
                                         through injection tubing (2),
                                         into injection zone
                                              Baker Model "C-1 " Tandem
                                              'Tension Packer
                                              2 3/8-in Tubing
                                              Baker Model "I." Sliding Sleeve
                                              Baker Model "R" Profile Nipple

                                                          "Ad"1 "Tension
                                                    i Tubing
                                              Baker Model "R" Profile Nipple
                                              Baker Model "F" Profile Nipple
                                              5 1/2-in Long String
                                      —- 1120 ft

                                           1130ft
                                Leak Test Well
Figure B-10.  Neutron activation tool liquid flow test.
                                     74

-------
 Test No. 6:  Radial Differential Temperature Survey

 Introduction
     On April 27, 1987, Gearhart Industries, Inc., was contracted to
 run a Radial Temperature Survey on the Leak Test Well to determine
 the capability of this tool to detect vertical flow behind casing.

     The Radial Differential Temperature  (RDT)  tool  employs  two
 highly sensitive temperature probes which extend from the centralized
 1 11/16-inch O.D. housing to contact the casing. As these probes are
 rotated, they measure any difference in temperature at two points on
 the casing 180 degrees apart.

 Well Configuration

     Figure B-11  indicates the  Leak Test  Well configuration for the
 RDT survey. The fluid level  in both the  5 1/2-inch  casing., and the
 2 3/8-inch tubing was 190 feet below the surface of the ground.

 Radial Differential Temperature  Survey

     The procedure for running the RDT in the Leak Test Well was to
 run a conventional  temperature profile, take RDT readings at five
 depths under no-flow conditions, then repeat the RDT readings at the
 five depths after  beginning  injection  down the  outside  2 3/8-inch
 tubing.

    The temperature profile indicated that the fluid level in the 5 1/2-
 inch casing was at 190 feet below land surface. RDT  scans at 1,050,
 1,025, 1,000, 975,  and 850 feet, under no-flow  conditions, showed
 the same temperature for both probes as they were  rotated at each
 depth. (See Figure B-12.)

    injection down the outside 2 3/8-inch tubing was started at 10:57
 a.m., and the RDT surveys at 11:05 a.m. The scan at  975 feet began
 to show a temperature difference as a result of the injection down the
 tubing. The temperature  differential is easily  seen  at 1,025  feet
 (Figure B-13).

    A final scan at  850 feet indicated the  temperature  variation one
 would expect with cooler fluid flowing in a channel outside the  long.
 string.

 Conclusion

    The Radial  Differential Temperature tool easily identified cooler
water flowing in the outside tubing in the Leak Test Well.

-------
               I
                                                     Flow =
                                             710ft
                                            905ft
                                        1^— 935 tt
                                                    Injection Zones
                                  Cement
                                   1070 ft
                                         1.  2 3/8-in Tubing
                                         2.  Baker Model "R" Profile Nipple
                                         3.  Baker Model "f" Profile Nipple
                                         4.  5 1/2-in Long String
                                   1100ft
                                           • 1120 ft

                                           •1130ft
                                Leak Test Well
Figure B-11.  Radial differential temperature survey.
                                    76

-------
                                               ~ ;•->•_—•-.	—•—i- -i—|—
                                  1 ™ ' " ' t~^ ^ ~ "\^	.__''.~".f"~*^ ~~ ** *"~ ' ""1'

Figure B-12.  RDT scan no-flow condition.

-------



                             ~:~_."  Scan #9 .   '. ;_' [i...:,1^.—	1'-—1—l:-,-r~
                             "'  1025ft  - • -i - j •:: r;~zq.r4=^T-t-n-
                             :~".:;1140 Hours  \r^-.^.r^^=^~^~^^:



Figure B-13.  RDT scan flow condition.
                                   78

-------
Test Mo. 7:   Nuclear Activation Technique for Detecting Flow
Behind Casing


Introduction

    On August 28 and 29, 1987, personnel from the Rdbert S. Kerr
Environmental Research Laboratory (RSKERL); EPA Regibn IV, Atlas
Wireline and Shell Western  E &  P conducted  a series  of tests to
determine flow behind  pipe using the PDK-100 pulsed neutron logging
system.

    The purpose of the test was to determine if flow of water at  two
different rates could be detected behind pipe in a "real world" well.
Shell personnel  had agreed to the use  of an abandoned  10,600-foot
gas  well in which a 100 + foot channel had been identified using a
radioactive tracer survey.

Test Well Conditions

    The well, Little Creek 2-6A, has 5 1/2-inch long string which hiid
been cleaned out to perforations at 4,163 feet.  The test was then
conducted in two stages: with a packer set at 4,000 feet and  the
PDK-100 located below the packer in  the long  string, and with  the
packer set at 4,125 feet and the PDK-100 located within the tubing.

Test Procedure

   The  first  objective  was to determine if the  previously identified
channel was  still present behind the casing. This was done with a
radioactive tracer survey as follows:

   A. Tracer FloLog

        1.  Rig up  Atlas Wireline Services and go into the hole with
           1  11/16-inch  O.D. dual detector tracer instrument. Place
           instrument 5 feet above perforations.

       2.  With the instrument stationary, start water injection into
           the  perforations  at  4,162  feet  with  the pump  truck
           operating at a rate of 1/2 barrels per minute (BPM),

       3.  When  the  injection  rate stabilizes,  eject a slug  of
           radioactive  iodine-131 into the flow and verify its mode of
           travel. The  material should travel downward past the two
           radiation detectors and  into the perforations.  If upward
           channeling exists, the material should travel up behind the
           casing within  the  channel, passing the detectors again,
           but in reverse order.

       4.  After channeling  has  been detected and  the radioactive
           material has  moved  past  the  instrument,  move the
           instrument  upward rapidly,  catching  and  recording the
          travel  path of  the radioactive material.  (The instrument is

-------
           moved up and down past the slug repeatedly to accom-
           plish this.)
       5.  Reposition the FloLog instrument 5 to 10 feet above the
           perforations  and repeat steps  2 through 4  to  verify  all
           previous measurements.
       6.  Stop  water  injection  and  remove the  Tracer FloLog
           instrument from the well.
   .   .     •"        .   •   .!          ;   •       • ,    •    •    .j  '.
    This  procedure established that a channel  existed behind  the
casing from 4,162 feet  to about 4,020 feet. Having established this
fact, the following procedure was used to test the PDK-100:
       1   Configure the PDK-100 with the pulsed  neutron source
           beneath the radiation detectors  so  that upward flow may
           be identified.
       2.  Go into the hoje and  locate too! 5 to 10 feet above the
           perforations but: below the tubing and packer.
       3.  Turn the PDK-lOO instrument on and  record the no-flow
           response.
       4.  Start the water injection at the rate of 1/2 BPM.
       5.  Turn the PDK-100 on and record the results. Adjust the
           flow to 1/4 BPM and record the results.
                         I  • .•  ,     •      ,  i    , .  •  •       i
       6.  Move the PDK-100 to the mid-range of the channel.

       7.  Turn on and record the results at both 1/2 and 1/4 BPM.
       8.  Move to  the top of the channel and record  the results at
           both flow rates.
                  ...    •  •,.j   ..   ,   i           ...            i .
       9.  Move out of the channel area and record the results. If no
           movement is present, stop the water injection and remove
           tool from the well.
       10. Reset packer at 4,125  feet and rerun surveys with the
           PDK-100 within the tubing.
                         I                                 • i •
       11. Rig  the  wireline  unit down and  review  results of both
           surveys.
                               80

-------
Conclusions
    The  first series of tests,  with  the tool  below the  tubing  and
packer, included stations at 4,180, 4,150, 4,100, and 4,050 feet. The
second series,  with the tool located within the tubing, included tests
at 4,100, 4,050, 4,000, 3,990, and 3,950.
    The PDK-100 detected both flow rates with the  tool either in the
casing or within the tubing. The top of the channel was determined to
be between 4,000 and  4,050 feet.
    The PDK-100 has  the potential for providing an excellent method
for detecting  flow behind pipe. However, additional work needs to be
done to determine specific applications for the  tool.

-------
 Introduction

     During the week  of  February  22,  1988, a series of tests  was
 conducted on the Leak  test Well  at the Mechanical Integrity Test
 Facility  at Ada, Oklahoma. The series  included  pressure  tests,
 monitoring well response, and  volume versus pressure tests. Each
 test was designed to  provide information  on mechanical integrity of
 injection wells and to determine  whether or not flow from a leak in an
 injection well could be  identified  in an adjacent monitoring well.
                         1          !                      '
 •Well Configuration
    The Leak  Test  Well  was configured as shown in Figure B-14:
 surface  casing set  at 5^1  feet and cemented to the surface; long
 string set at 1,215 feet and cemented to 925 feet; injection tubing set
 on a packer at 1,084  feet; sliding  sleeve  in injection  tubing closed;
 profile nipple at 700 feet  in  outside tubing  open; profile nipple at  920
 feet in  outside tubing  closed. The  profile nipple has three 3/16-inch
 openings to allow flow  from the outside tubing.

    Two pressure gauges and two  flow meters were installed in  the
 flow line between the pump  and  the  injection  well so that an accurate
 determination  of the injection pressure and flow to the well could be
 obtained.

    Three  monitoring wells are located around the Leak Test Well in a
 radial pattern  20 feet  from the Leak Test Well (Figure B-15).  Table
 B-3 indicates  the  depths of the monitoring  wells and  the depth to
 water in each well. The water table  was measured using a weighted
 steel tape and was corrected to depth below land surface.

    On  Monday, February  22,  1988,  pressure transducers  were
 installed in the 710-foot and 935-foot wells  to monitor any water-level
 changes that might occur prior to and during  the tests. The pressure
 transducers were  used  in  conjunction with an  SE200 Hydrologic
 Analysis System which is marketed  by  In-Situ, Inc. The transducers
 are  0.85-inch  diameter stainless steel  and the  SE200 was
 programmed to record data (in this case water levels)  every  10
 minutes for 10,000 minutes.

 Mud in Annulus

    The Leak Test Well was completed in January 1985 with the long
strong/surface  casing annulus full of native drilling mud above  the top
of the cement around the  long string  The mud weight  was recorded
as 9.7 Ib/gal upon completion of reaming the well, prior to setting and
cementing  the  long string. The gel  strength  was 3 lb/100  ft2 at  10
seconds and 4 lb/100 ft2 at 10 minutes.
                               82

-------
                                                     Injection Zones
                                           1.   Surface Casing (571 ft)
                                           2.   2 3/8-in Tubing
                                           3.   Baker Model "L" Sliding
                                               Sleeve
                                           4.   Baker Model "R" Profile
                                               Nipple
                                 Cement    5   Baker Mode, ซM_^ „

                                               Tension Packer
                                           6.   2 3/8-in Tubing
                                           7.   Baker Model "R" Profile
                                               Nipple

                                           8.   Baker Model "F"  Profile
                                               Nipple
                              084 ft Depth Of
                              Lower Packer                    a
                                    1100ft

                                     1120ft

                                     1130ft
Figure B-14. Leak Test Well.

    The purpose of this test was to determine if water, injected into
the well and out the profile nipple at 700 feet, would move into a zone
open to the well bore or move up  the  well bore through  the drilling
mud to the surface. Water was to be injected down  the outside tubing
while a surface valve on the tubing/long string annulus was open so
that the flow would discharge at the surface, thus removing any air in
the system as the outside tubing and tubing/casing  annulus filled with
water. In addition, a bull plug was  removed from the  surface casing

-------
                       Monitoring Well
                       No.1
                                   O
                                   Monitoring Well
                                   No.2
                                   O

                                 Leak Test Well
                                                              North
                       Q Monitoring Well
                      |    No.3
           Monitoring        Monitoring
Removable     Well     '        Well
Well   — •-ซซ.   1                2
                                                       Monitoring
                                                         Well



680 ft


710 f



-
I
!
(
1


t





f


=
—








>!
! i







1*1


\







7 ft


3ement


905 ft


935 f










t

f






^=:
— .
t
a



i





5c
j\
152 ft

/ Borehole
/





reen
1120 ft


(f

;
',

.'


i



f







JU

'

1


'!
#
i





195 ft




/-Casing



."'v:',;/"'
                                                  1130 ft
Figure B-15. Monitoring wells.
       Table B-3.    Depth to Water in Monitoring Welis
          Monitoring Well
                         Depth (feet)
Water Level Below
Land Surface (feet)
                                    710

                                    935

                                   1,130
                                                 157

                                                 152

                                                 195
                                     84

-------
 so  that  the  surface casing/long  string  annulus was open to  the
 surface.

     At 1:05 p.m. the pump was turned on to begin pumping water into
 the  outside  tubing.  In  8 minutes  water began  flowing out of  the
 tubing/long string annuius at the surface. At that time the valve on  the
 tubing/long string annulus was closed so that the flow into the outside
 tubing would exit only through the profile nipple at 700 feet.

     At 1:46  p.m. a  significant pressure drop  was  noted  on the
 pressure gauge (from 300 psig to 70 psig), and water began flowing
 at the surface  through the bull plug opening in the surface casing.
 The water flowing from  the surface  casing  was  clear,   indicating
 channeling through the mud rather than displacement of the  mud.

     On Friday,  February 26,  after all the other tests were completed,
 an attempt was made to determine how much pressure  would  be
 necessary to reopen the apparent channel in the mud and establish
 flow at the surface. The bull plug  in the surface casing was removed
 and injection  begun down the tubing/long string annulus at a pressure
 of 30 psig and a flow of 3.3 gpm. Within 1 minute flow of clear water
 appeared  at  the surface from  the bull plug opening in  the surface
 casing. The pressure was gradually  reduced and the flow decreased.
 Even when the pressure gauge snowed zero pressure, there was a
 trickle  of water flowing from  the  surface  casing. The low  pressure
 necessary  to induce flow indicates that the  channel  created on
 February 22 remained open.

    The fact that a channel was created in the  mud initially and the
 channel did not "heal" over the 5-day test period is of concern when
 considering abandoned  wells  and  wells with  inadequate casing
 through underground sources of  drinking water.  In a report titled,
 "Determining  the Area of Review for  Industrial Waste Disposal Wells,"
 Stephen E.  Barker investigated mud   strengths and  the  pressure
 required to initiate flow in  abandoned walls. He stated that in addition
 to the  pressure required to  overcome  the hydrostatic head of the
 borehole mud, the pressure  necessary to displace  the  mud varies
 directly with  the gel strength and  well  depth  and inversely with
 borehole diameter.

                            0.00333 (GS)  (h)
                                 D

 GS =  gel strength, pounds/100 ft2

 h   =   height of mud column or depth of well, feet

 D   =   hole diameter, inches

P   =   displacement pressure, psi

The constant 0.00333 has the units ft/inch

-------
    The resistance to flow in the long string/borehole annulus ot me
Leak Test Well includes the mud column in the long string/borehole
annulus (mud gradient .499 psi/ft),  and the gel strength of the  mud
(assume 25 lb/100 ft2)
                          j Mud Column

                      .499 psi/ft X 700 ft = 349 psi
                          Gel Strength

                   .00333 ft/in X 251W100 ft2 X 700 ft
                               6 in

    Thus, the resistance to flow is  the sum of the mud column and
the gel strength: 349 psi + 9.7 psi =  358.7 psi.
    The inducement to flow  includes the  water column in the  long
string above the 700-inch zone and the pump pressure:
Hydrostatic pressure      =    .434 psi/ft x 700 ft  = 303.8 psi

Pump pressure           -    300 psig
                                    •  .                       '
Inducement to flow        =    603.8 psi
    Thus, the differential pressure available to cause flow in the long
string annulus is 245.1 psi (603.8 psi - 358.7 psi).
    If the gel strength of the mud  in the  annulus  had reached 120
lb/100 ft2, the displacement pressure due to the gel strength woud
have only been 46.6 psi and the differential pressure to cause flow in
the annulus, 208.2 psi.
    It appears  that at shallow depths,  the probability of fluids  from
leaks in the system being able to move through the mud, either to the
surface or  into  permeable  zones, is very  high when injection
pressures are additive to the hydrostatic pressure.

Pressure Monitoring
    This test was  designed  to  establish if  monitoring  a positive
oressure, without an initial pressure test, could detect the  same leak
in the system that could be detected with a pressure test. To perform
the test a 5  1/2-foot standpipe was attached to the tubing/long string
annulus to provide the positive pressure for the test (Figure B-16).
The plastic standpipe was graduated  into 1 foot increments and  each
foot of  the standpipe held 1  gallon of water. The  base of the stand-
pipe was located 3.2 feet above the land surface.
    The standpipe was attached to the  well on Wednesday morning
and the system was filled with water to the 5-foot level. The water-
level decline was then  measured  every hour  for  7 hours, until the
                                86

-------
                           Injection
                           Tubing
             Long
             Bull Plug
                                                        5ft
                                                           • Standpipe
                        Long
                        String
           Surface Casing
           Bull Plug

Figure B-16.  Standpipe.
        Valve

Outside
Tubing
      Land Surface
     Table B-4    Water-Level Decline in Standpipe
Time
(24 hours)
0810
0910
1010
1110
1210
1310
1410
1510
1610
Elapsed Time
(hours)
0
1
2
3
4
5
6
7
8
Water Level Decline/Hour
(feet) (feet)
5.0
4.3
3.7
3.1
2.4
1.8
1.2
0.5
Below
0.0
0.7
0.6
0.6
0.7
0.6
0.6
0.7
base of standpioe

-------
water level fell below the base or me' stanop.pe.  iaiwป DV*
the water-level decline in the standpipe over the period of the test.

    At 1:45 p.m. on February 25, 1988 (about 29 hours after start of
the test) the bull plug in the long string was removed and  a water-
L j  measu'emenf was taken.  The  water  level inthetubmg/lor*
string annulus was 16.1  feet below the base of the standp.pe.
    The  average decline in the  standpipe  was  .64  ft/hour, slightly
slower thin thl  tubing/casing annulus decline of .76  ft/hour  This is
due S  he fact that the  standpipe contained  1 gallon perJtoot and  fte
tubing/casing annulus  contained only  7938 gaUona.per.foot The
decline noted calculates to a .01  gpm, .6 gpd or .34 bpd leak.
    The data indicate that the monitoring system can detect a leak of
this size. The amount of positive pressure is  not signrfcantrt  is just a
means of putting the fluid level  above the surface  where the water
level  decline can  be  readily observed.  The  pressure deferential
created by the hydrostatic column  in the casing/tubing annulusand
the formation pressure is what controls the rate of decl.ne andI rateoi
volume lost.  Had the test been  allowed to run long enough,  the rate
of decline and volume of fluid lost would have stead.ly decreased until
equilibrium was reached.

Standard Pressure Test
    The standpipe was removed and the well was subjected to  the
standard mechanical integrity pressure test to  determine effects, of
different pressures and length of tests on the capability for' detecng
leaks. Table  B-5 indicates the pressures applied and pressure decline
over time.
     In some UIC  programs, if  a well does not lose more  than 10
 percent of the pressure in 30  minutes,  it passes the pressure test.
 The  Leak Test Well failed the test in less than 2 minutesi ataฎ
 pressures  (Figure B-17). In each of the tests (50, 100, 200  and  400
 psig), more than 75 percent of the initial pressure was lost  within 15
 minutes.
     The water-in-annulus test, in which  a well passes the mechanical
 integrity test (MIT) if the water level does not decline more than 5  feet
 per hour, is of concern. A water-in-annulus  test would have indicated
 that  the Leak Test Well had mechanical integrity.  As themonrtonng
 showed, the water-level decline was only  0.76 ft/hour.  Thus, under
 the  pressure differential  (70 psi)  created during this  test by   the
 hydrostatic column in  the annulus, the fluid  loss was 01  gpm,,0.6
 qph  14.4 gpd or .34 bpd. However, a tubing or packer leak,  sufficient
 to create only a 120 psi differential (equivalent to the 50 psig test on
 Table B 6) between the annulus and the receiving formafon  wouki
 lose 0.8 gpm, 48  gph,  1,152 gpd or 27.4 bpd through the same holes.
                                 88

-------
   Tafafe S-5   Pressure Decline Over Time

   Pressure Applied     50 psig    100psig      200 psig    • 400 psig
   Pressure Differential   120 psi     170 psi       270 psi      470 psi
       (700 ft sand)


       Time (min)                 Pressure Decline (psig)
0
5
10
15
20
25
30
50
.25
15
10
5
3
0
100
43
22
13
7
5
3
200
77
35
18
13
7
6
400
225
117
60
34
23
15
 Injected Volume Versus Pressure/Leak Detection through Monitoring
 Wells
    The next test run on the well involved evaluating injected volume
 versus pressure, to determine whether or  not a monitoring  well can
 detect an  increase in pressure as a result of flow through a leak in
 the system.

    While injecting at pressures of 50, 100, 200 and 400 psig for 30
 minutes, the flow into the profile nipple at 700  feet was measured
 (Table B-6). At the same time  the  injection-volume relationship  was
 being determined, the  In-Situ  Hydrologic  Unit  was recording  the
 changes in water level in the two monitoring wells every 10 minutes
 (Tables B-7 and B-8).

    Injection began  at 3,892 minutes elapsed  time at  50 psig;  100
 psig at 3,922; 200 psig at 3,952; and 400 psig at 3,982. Injection  was
 stopped at 4,012 minutes.

    The data from the transducers clearly demonstrate that the water
 level  in the  700-foot sand  is responding  to the different  rates of
 injection  (Table B-7,  Figure  B-18)  while that  in the 900-foot sand
 (Table B-8, Figure B-19) is not. The water-level drop during  the  400
 psi injection  probably indicates  that some  other zone  began taking
 water, since in this test the  pressure was maintained as a constant,
 rather than  the flow rate.  Additional  "injection  volume  versus
 pressure" tests need to be conducted over  a longer period of time to
establish more data  for determining the reason  for  the  water-level
drop.

-------
 Pressure (psig)


        400 Gh






        300  j-






        200






        100
     Pressure-50

     Pressure-100
     Pressure-200

I—  Pressure-400
            0               10

                                 Time (min)

Figure B-17. Pressure decline over time.
                                            20
                                                            30
Table B-6.
Tim'e
Start Test
0800
0830
0900
0930
Flow through Profil
Elapsed Time
(min)
3892
3892-3922
3922-3952
3952-3982
3982-4012
3 Nipple
Injection
Pressure
(psig)
0
50
100
200
400
Differential
Pressure
(psi)
70
120
170
270
470
Injection
Volume
(spm)
0.01
0.8
1.0
1.2
2.7
Volume Versus Pressure-Hole Size

    The  next test performed was to determine the volume of water
which  could be pumped through a 1/32-, 1/16-,  1/8-, and 3/16-inch
orifice  at varying pressures.  Orifices of these sizes were drilled into
caps fitted onto the injection line. With  all valves closed to the well,
                                 90

-------
different pfegsuteS were applied and the flow rate was measured
a stopwatch and a graduated bucket.

     Table B-7.   Changes in Water Level - Monitoring Well No. 1
Elapsed Time
(min)
3810
3820
3830
3840
3850
3860
3870
3880
3890
3900
3910
3920
3930
3940
3950
3960
3970
3980
3990
4000
4010
4020
' 4030
4040
4046
Water Level
(ft)
167.06
157.06
157.06
157.06
157.06
157.06
157.05
157.05
157.04
157.05
157.07
157.07
157.08
157.07
157.11
157.12
157.12
157.12
157.17
157.05
157.02
157.06
157.10
157.09
157.11
Change in Water level
(ft)
0.06
0.06
0.06
0.06
0.06
C.06
0.05
0.05
C.04
0.05,
0.07
0.07
0.08
0.07
0.11
0.12
0.12
0.12
0.17
0.05
0.02
0.06
0.10
0.09
0.11 .

-------

           157.2  ,—
  Water
  Level
  (ft)
            157.1
            157.0
Water Level
                3,800           3,900          4,000
                          Elapsed Time (min)
Figure B-18.  Changes in water level - 700-ft zone.
                                                            4,
                                                              100
    Table B-9 indicates the results of this test. !t should be noted that
the differential pressure  between the casing/tubing annulus  (gauge
pressure  +  hydrostatic pressure)  and  the formation pressure
opposite the hole determines the volume of a flow through a certain
size hole in a well casing.
                                 92

-------
table  B-8.   Changes in Water Level  - Monitoring Well No. 2
Elapsed Time
(mm)
3810
3820
3830
3840
3850
3860
3870
3880
3890
3900
391 Q
3920
3930
3940
3950
3960
3970
3980
3990
4000
4010
4020
4030
4040
4046
Water Level
(ft)
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.04
152.03
152.03
152.04
152.03
152.04
Change in Water Level
(ft)
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.04
0.03
0.04
0.03
0.03
0.04

-------
             152.5  r-
  Water
  Level
  (ft)
                                           Water Level
152  &^~

   3,800
                                  3,900
                                                   4,000
                                                                    4,100
                             | Elapsed Time (min)

Figure 4-19-  Changes in water level - 900-ft zone.
  Tatjle B-9.   Flow of Water (gpm) through Holes at Different Pressures

                                          Hole Size (inch)
Pressure (psig)
50
100
200
400
1/32
0.675
0.088
0.115
0.160
1716
(3.65
0.85
1.13
1.60
1/8
2.45
3.31
4.50'
•**
3/16
5.5
ill


     Barely reached 50 psi
     Could not get above 220 psi
                                      94

-------
Goncfusions
    The tests run during this  week provide a number of points that
need to be considered in determining  mechanical integrity of injection
wells:

1.  A channel  was created in the  mud in  the  long string/well  bore
    annulus on Monday and the channel was still open on Friday.

2.  Data from  the  monitoring system (standpipe) were  sufficient to
    detect a leak in the Leak Test Well.

3.  The Leak Test Well failed  the standard pressure test in less than
    2 minutes.

4.  The Leak Test Well would have  passed a water-in-annulus test
    even though it failed  the  standard  pressure test.  The water-in-
    annulus test needs more study to  determine if it is  indeed a valid
    test.

5.  The water  level in  the 700-foot zone clearly responded to  the
    injection rates in the Leak  Test  Well, while  the water level in the
    900-foot zone showed no response to the injection.

-------
Introduction
    On February 15, 1988, personnel from Atlas Wireline Services
conducted a noise survey on the  Leak Test Well at the Mechanical
Integrity test Facility. This survey,  termed SONAN, was conducted to
determine if flow through the outside tubing  in  the well could be
identified.
                                   !
                         f    '      :            '            i
Well Configuration
    The well was configured as shown in  Figure  B-20, with injection
maintained down the 2 3/8-inch outside tubing. The noise tool was
located inside the 2 3/8-inch injection tubing.

Noise Survey
    The tool  used by  Atlas  Wireline has  an  outside  diameter  of
1 11/16 inches, a length of 3 feet, a bottom hole temperature rating of
350  degrees and a bottom hole pressure rating  of 15,000 psi. The
tool has the capability to take data  at Steven frequencies as shown on
Table B-10.  On the table, HPO1 relates to  200 HTZ, HPO2  to 600
HTZ, HPO3 to 1,000 HTZ, HPO4 to 2,000  HTZ, HPO5 to 4,000 HTZ,
HP06 TO 6,000 HTZ and  HPO7 to 8,000 HTZ.  On this particular test,
readings  were taken only through 2,000  HTZ,  thus  the  numbers
recorded for  HPO5, 6 and 7 are meaningless.

    Data was taken at. 25 stations in  the well  (Table B-10). At  least
four  readings  are taken  at each  station  to identify  the frequency
character of the sound sources.

    The curves presented on Figures  8-21 and B-22 and  the data on
Table B-10 are developed by  recording the peak  millivolt reading for
each frequency at each station. The readings for HPO1 represent the
noise levels for 200 HTZ  and  up; HPO2 for  600 HTZ and up; HP03
for 1,000 HTZ and up; and HPO4 for 2,000 and up.
                         I   '       ' .                       ;
                         !
Conclusions
    The attached copies of the Sonan Log (Figures B-21 and B-22),
present data indicating increased noise at  the hole in the long string
at 1,070 feet. However,  two noise anomalies (980  and 860 feet) have
not been fully explained.

    R.M.  McKinley,  Exxon Production Research,  Houston, Texas, is
one of the foremost authorities on  the noise tool.  He has stated that
extraneous sources of sound are the greatest impediment to noise log
quality control.  These extraneous sources may be surface equipment
noise or inadvertent flow  past the sonde or continued movement of
the logging tool during measurement.
                              96

-------
                                                   Injection Zones
                                          1.   Surface Casing (571 ft)
                                          2.   2 3/8-in Tubing
                                          3.   Baker Model "L" Sliding
                                             . Sleeve
                                          4.   Baker Model "R" Profile
                                              Nipple
                                 Cement   5_   Baker Model "Ad-1"
                                              Tension Packer
                                          6.   2 3/8-in Tubing
                                          7.   Baker Model "R" Profile
                                              Nipple'
                                          8.   Baker Model "F" Profile
                                              Nipple
                             1084 ft Depth of g   5 1/2.in Long String
 Figure B-20.  Leak Test Well.

    Another  interesting  aspect  of  the log  interpretation  relates  to
 single versus multiphase  flow.  Multiphase flow is characterized by
 lower frequency sound than single phase flow,  and is indicated by the
^separation  of the  200  HTZ  curve  from  the  other curves. This
'phenomenon seems to be quite  vividly portrayed on the log. Thus, air
 was apparently being pumped down the. well along with the water.

    Much additional  testing is  necessary  to  fully  understand the
 capabilities of the noise tool in  mechanical integrity testing and to fully

-------



\ 	
Table B-10. Leak Test Well - SONAN Data
Depth Corrected Data for Line
HPO1 HP02 HP03 HPO4
: , 650.00 58 13
700.00 48 20
750.00 51 10
800.00 74 16

860.00 132 11
. 900.00 83 22
940.00 106 11
980.00 144 12
1000.00 101 17
1020.00 90 11
1040.00 59 10
1050.00 135 29
1055.00 119 16
1060.00 137 13
1065.00 14 16
1070.00 136 9
1075.00 86 14
1080.00 89 11
1090.00 ,64 11
1100.00 73 10
1120.00 62 14
1140.00 35 20
1160.00 26 8
1180.00 20 15
1200.00 17 7
interpret data presented on
that the following articles be
when dealing with noise surv

10
13
9
12

9
12
10
11
11
8
9
7
11
8
8
8
10
8
9
8
13
17
8
7
6
:he noise
9 made a
reys:
98
9 ;
7
6
4

7
7
7
7
7
6
7
4
6
7
7
6
9
.7
7
I
7
8
,_,„
7
4
4
Length, Size
HPO5 HPO6 HPO7
,"'3 '"' 2" ' 1 " '
3 2 1
32 1
3 2 1
1 ii
321
4 2 1
3 2 1
321
3 2 1
3 2 1
3 2 1
3 2 1
3 2 1
321
3 2 1
3 2 1
32 1
3 2 1 ' "\
3 2 1
• 32 1
3 2 1
32 1
3 2 1
3 2 1
3 2 1
log. It is strongly recommended
part of a library for assistance



-------
Figure B-21. Atlas Wireline Services SONAN Leak Test Well.

MoKinley,  R.M., Bower,  P.M.,  Rumble,  R.C., "The  Structure and
Interpretation of Noise from Flow Behind Cemented  Casing," Journal
of Petroleum Technology (March 1973), pages 329-338.

McKinley,  R.M.; Bower,  P.M.,  "Specialized  Applications of Noise
Logging," Journal of Petroleum Technology (November 1979), pages
1387-1395.

McKinley, R.M., "Production Logging," SPE Paper 10035, undated.

-------













































a*






=1
1
i
N
H

y
=i
-t

H











o
a
to
o
0
o
o
o
0

E!"
:ซ
31
i'l
!
3i
I
1
i
3
-1
-1
J
-1
i
3!
fl
3,'
3!
}
i
>
i
i
f
i
                                   V
Figure B-22. Atlas Wireline Services SONAN Leak Test Well:
                               100

-------
 Test No. 70: Temperature Survey

 Introduction
     On  September 10,  1985, personnel  from  the  Tom  Hansen
 Company ran a  temperature  survey in the Leak Test Well. The
 purpose of the survey was to determine the geothermal gradient, the
 .fluid level, and, by including a casing collar locator, the location of the
 casing collars, packers and sliding sleeve in the well.

 Well Configuration
     The well had  surface casing set at 571  feet and cemented to the
 surface, and long string set to 1,215 feet with the top of the cement
 at about 920 feet. When the  injection  tubing was set, calculations
 indicated the upper packer should  be  at 1,057 feet,  and the lower
•packer at 1,084  feet,  with the  sliding  sleeve  at about  1,070 feet
 (Figure B-23).

 Temperature Survey
     The  sequence of  events leading  to  the  temperature  survey
 included:

 9-5-85 The 5 1/2-inch  casing was filled  with  water  and the zone
        1,120-1,130 perforated with 2 shots per'foot {SIEDP - deep
        penetrating shot). The average hole  size  should  be  .411
        inches and the average depth of penetration of the shot,  19
        inches. The water level was measured and was 20 feet below
        the land surface.

 9-9-85 the water level was 46 feet below the land surface. The well
        was swabbed before  setting tubing and packers.  Operators
        set the  tubing  and  packers  and prepared to  run the
        temperature survey.

     Two  runs were  made  in  the  well, each  run taking  about  35
 minutes. A geothermal gradient could not be obtained since the work
 done  in  setting  the tubing  (swabbing, etc.) resulted in moving fluid
 from the casing into the injection zone.  As a result, the log reflected
 the results one would expect after injection has taken place.
     The temperature went from 76 ฐF at the  surface to  75.5 ฐF at total
 depth  in the first run.  The second run indicated a surface temperature
 of 80ฐF and a bottom hole temperature  of 73.5ฐF. The fluid  level in
 the second run was about 474 feet below the land surface.

     A  very  interesting part of  the  log  presentation was the  casing
 collar  locator. It  indicated the upper packer  at a depth  of 1,054 feet,
 sliding sleeve at  1,066 feet and the lower packer at 1,084  feet. This
 compares favorably with the calculated locations made prior to setting
 the tubing and packers.

-------
                                                   Injection Zones
                                          1.   Surface Casing (571 ft)
                                          2.   2 3/8-in Tubing
                                          3.   Baker Model "L" Sliding
                                              Sleeve
                                          4.   Baker Model "R" Profile
                                              Nipple

                                          5.   Baker Model "Ad-i"
                                              Tension Packer
                                          6.   2 3/8-in Tubing
                                          7.   Baker Model "R" Profile
                                              Nipple
                                          8.   Baker Model "F" Profile
                                              Nipple
                                          9.   5 1/2-in Long String
                                          10. Baker Model "C-1" Tandem
                                             Tension Packer
                                    1120ft

                                    1130ft
Figure B-23. Leak Test Well.

                         ](i  ,.       ;  .              ,           |  '
Conclusions
    The CCL portion  of the  log was  good for  comparing  the
calculated  location  of bofh  packers  and  the sliding sleeve.  The
temperature log  gave no significant information since a geothermal
gradient was not obtained. A base log .to establish the geothermal
gradient is extremely  important for developing  a  meaningful  log.
Temperature,  differential temperature  and radial  differential
temperature logs will be run on the well at a later date.
                                102

-------
 Test No. 11: Continuous Flow Survey


 Introduction

     On October 13, 1987, personnel from Gearhart Industries,  Inc.,
 ran a continuous flow survey on the Leak Test Well. The purpose was
 to determine whether or not the survey could identify leaks in the
 well, and, in  turn, whether  or not flow was exiting  through the
 perforations.

 Well Configuration

     The well was  configured as shown  in Figure B-24. The  sliding
 sleeve  was closed so that all flow down  the  injection tubing went to
 the perforations at  1,120 to 1,130 feet.

 Flow Meter Survey

     The survey was run by pumping water down the injection tubing
 at different rates and checking  those rates with calculations  of flow
 from data collected by the flow meter. Also,  readings were taken at
 specific intervals to determine if flow was leaving the injection  tubing.
 Flow rates from the pump were about 7, 6, 1 and  1/2 gallons per
 minute.  However,  accurate determinations of flow  rates were  not
 possible owing to a malfunction of the flow meter in the flow line to
 the well.

    Twenty-one different "runs" were made in  the well under flow and
 no-flow conditions.  Each run was indicated on a log as a file with the
 following information presented:   speed of tool movement, either up
 or down in feet per  minute; depth interval; average revolutions/second
 of the spinner  in a clockwise  and a counterclockwise direction; and
 the  flow  rate,  in revolutions  per  second,  in  the  clockwise and
 counterclockwise direction.

    In the initial test (File  1), the  tool was held stationary at 193 feet
 and water was  injected down the injection tubing at a rate of about 7
 gpm. The calculated flow rate  past the tool was 265 barrels per day
 (7.7 gpm).

    The flow was changed to about 6 gpm, and  the tool (File 2)
 indicated a flow of 221 bpd (6.4 gpm) (Figure B-25).

    For  File 3, the flow rate was changed to about 1  gpm and the tool
 indicated a flow of 44 bpd (1.3  gpm).

    The flow rate for File 4 was about .5 gpm and the calculated flow
from the tool data was 15 bpd (.43 gpm).

    The remaining runs (files) involved moving the tool up or down in
the tubing  under no-flow  conditions to  check the flow meter, stop
checks  above and  below the sliding sleeve  to determine  whether

-------
                                                     Injection Zones
                                           1.   Surface Casing (571 ft)
                                           2.   2 3/8-in Tubing
                                           3.   Baker Model "L" Sliding
                                               Sleeve
                                           4.   Baker Model "R" Profile
                                               Nipple

                                           5.   Baker Model "Ad-1"
                                               Tension Packer
                                           6.   2 3/8-in Tubing
                                           7.   Baker Model "R" Profile
                                               Nipple
                                           8.   Baker Model "F" Profile
                                               Nipple
                                           9.   5 1/2-in Long String

                                           10.  Baker Model "C-1" Tandem
                                               Tension Packer
Figure 6-24. Leak Test Well.
leakage was occurring out the sleeve and a check of the flow out the
perforations.

    Figures B-25 to B-28 indicate specific runs and comments of the
operator based on data provided by the survey.
                                 104

-------
ฃ DATE FLOUM SERIAL * PROGRAM MODE JOB * FILE
••AS 13 OCT 87 O3S 3-ZOOI-04 STAT 0 2
.....:
F







— 1
,=
1 	
.P.?
T/











.!?.S
MI







— i
— 1


N

•j,

ay















t
	 T —
-

N.
bo
r=









=H
	 . 	 , 	 : 	
193
DEPTH










STOP CHECK (FLOUM)
SO CCU NHZ S3
— AVERAGE CU —
'-ง' 	 	 REV /S6C 	 	 5'
-- AVERAGE CCU --
-5
-CCU
„









5
T~?







—

cr










_._i—













































— t

—4
REV/SEC 5
FLOU RATE *CU
R
j 	

EV
—

	 1 	 1
1 	 i




—
	 1
— L






— 1— j
— 1 —
. — n_
.... .. i
/SEC


















— ! —
j —









—












'—









	 , — i 	
--


-


— ' — '






















— I
-•










5










	 1— t—
Figure B-25.  Qearhart Industries, Inc., continuous flow survey.
Conclusions

    The  continuous flow  survey indicated that there  was a  possible
slight loss of fluid through the sliding sleeve  and the  flow was going
out the perforations about equally.

    Continuous flow surveys are a useful tool for determining leaks in
tubing, casing or packers.  Additional tests will be done to correlate
more accurately the flow  rate from the pump with the estimate from
the tool.

-------
  TIME      DATE     FLOUM   SERIAL *       PROGRAM    MODE JOB  *   FILE
 !:Sl:43   13  OCT  17           03!          3-2O01-04 UP        0   15
        .	......
       FT/'MIM   -100
 1024
DEPTH
                              STOP CHECK  (FLOUH)
                            BO      CCU NHZ     93
-s	
.„--.,


'^S
                                        .--. AVERAGE  ,  CU. .--..,
                                            '   REV /SEC
                                               ..-
                                               REV/SEC
                                         -CCU FLOW RATE +CU
                                                                  i  I
  'P.	SPEED. .-DOWN.,   1080
      FTXMIM    -100 DEPTH "^REV/SEC
                                        ••CCU FLOU RATE  *Cll
Figure B-26. Gearhart Industries, Inc., continuous flow survey.
                                    106

-------
ป it


F
S
W
PF
ป
FO
N~


-O
~f
DU
So'
•4
"FT /Kit? -ioo
JQ81
DEPTH
i
loai
DEPTH
SrOf CHECK tPLOUH) ,
60 CCU NHZ S3
„_ . - - __*ฅ MM A S E 	 C W_.- - 	
"S
^~~t


AVEaAGESECCU -- S
. , RJIV/S6C 5
-CCU FLOW RATE ซCU
T7
ซ

h^
— ^

-J

b2Ji

iiU
TT1

r7T
—
—
—
cc
Ll
w
R
FL
EV
0 •*
/SI
S
:C
A:
i —


*c •


-r
=?
— J

!^-
—


S

-S REV/SEC 5
-- AVERAGE CCU --
... 	 .„....„.. .-
-- AVERAGE CU -- 	
-5" 	 REV/SEC S
STOP CHECK (FLOUM) .
60 CCU NHZ S3'
10 = 54 13 OCT 87 O3S 3-JOOI-O4 STAT O 17
ME DATE FLOUM SERIAL t PROGRAM MODE JOB * FIUE
Figure B-27. Gearhart Industries, Inc., continuous flow survey.

-------
 ME       DATE
 9!S2   13 OCT  87
                   FLOUM
                        SERIAL *
                          03S
PROGRAM   MODE JOB
G-2OO1-CM DOUN
'  FIUE
 o  20
 SPEED   HBOUN
_..„.„.„.„._._ •—•ฃ•.
                            STOP CHECK (FLOUM)
                          'SO     CCU  NHZ     83
                     1 103
                   DEPTH
                          p_
                                           REV/SEC
                                    --  AVERAGE  CCU  --
                           -5
                                              R6V/S6C
                                       -CCU FLOW  RATE  *CU
                                                                        S
                                                                       ....
                                              REV/SEC
    SPEED  -DOUN
   "FT/nTiT   "-Too"
                          -5
                          -S
                           STOP  CHECK  IFLOUMI
                           0      CCU NHZ      83
                                           REV/SEC
                                    --  AVERAGE   CCU --
                                           REV~7s"EC
                                    --  AVERAGE    CU --
                                    	RE"V>"S"E"C	
  • 13  13 OCT  37            O3S
  E       DATE     FLOUM  SERIAL ซ
                                       3-2001-04  DOUN
                                       PROGRAM    MODE  JOB
                      0   20
                      t   FILE
Figure B-28.  Gsarhart Industries, Inc., continuous flow survey.
                                   108

-------
 Test No. 12: Radioactive Tracer Survey


 Introduction

     On  May  19,  1988,  personnel  from the Tom Hansen Company
 conducted a  radioactive tracer survey on the Leak  Test Well. The
 purpose of the survey was to determine if there were  leaks in the
 tubing, casing or packer, or channeling in the cement in the area of
 the perforations in the long string.

 Well Configuration

     The well  was configured  as shown in  Figure B-29.  The sliding
 sleeve was closed so that material injected down the injection tubing
 would exit through the perforations from 1,120 to 1,130 feet.

 Radioactive Tracer Survey
     The first run was to determine a  background. The tool used to
 develop the base log included  a casing  collar  locator and  low-
 sensitivity gamma ray.

     The survey was  conducted while pumping  approximately 1/2  bprn
 at 300 psig, as follows:

 1.   Ejected tracer at about 1,000 feet and followed it  down the tubing
     and out the perforations. Most of the material went out the lower
     part  of  the perforations.  Eight  runs were  taken to trace the
     material (Figure B-30).

 2.   Ejected  tracer at 1,125 feet and checked for movement with a
    detector at 1,139 feet. No channeling detected (Figure B-31).

 3.  Ejected  tracer at 1,125 feet and checked for movement with a
    detector at  1,135  feet (time drive). Some of the material  was
    detected  (Figure B-32), which indicates a channel in  the cement
    below the perforations.

 4.  Ejected tracer at 1,107 feet with a detector at 1,115 feet. No  leak
    indicated.

 5.  Ejected tracer at 1,102 feet with a detector at 1,110 feet. No  leak
    indicated.

 6.  Ejected tracer at 1,066 feet with a detector at 1,076 feet. No  leak
    indicated.

 7.  Ejected tracer at  1,052 feet with a detector at 1,060 feet. No  leak
    indicated.

8.  Ejected tracer at  1,042 feet with a detector  at 1,050 feet. No  leak
    indicated.

-------
                                       si 680 ft
                                          710ft
                                          905 ft
                                        a 935ft
                                                      Injection Zones
                                            1.   Surface Casing (571 ft)
                                            2.   2 3/8-in Tubing
                                            3.   Baker Model "L" Sliding
                                                Sleeve
                                            4.   Baker Model "R" Profile
                                                Nipple
                                            5.   Baker Model "Ad-1"
                                                Tension Packer
                                            6.   2 3/8-in Tubing
                                            7.   Baker Model "R" Profile
                                                Nipple
                                            8.   Baker Model "F" Profile
                                                Nipple
                                           . 9.   5 1/2-in Long Strirtg
                                            10.  Baker Model "C-1" Tandem
                                                Tension Packer
Figure B-29.  Leak Test Well.
                            1                                       i
                       	
Conclusions
       '"" !'             ;:" ,      •          !  ""                        ' ; •
    The radioactive  tracer  survey  indicated a  slight channel  down
from  1,130 to  1,135 feet. There was no  indication of channeling at
1,139 feet. There were no indications of leaks in the tubing or packer'
or channels above the perforations.
                                  110

-------
Figure B-30. Tracer runs showing  fluid movement during injection at 1/2
             bprti 300 psi.

-------
                             -r-i—i-
                                        -+—,—>•
                                            "I"
                                       L;J—!-
Figure B-31.  Slug #6 ejected at 1,125-ft channel down check.
                                112
                           i       •    )

-------
• - -
-_.;-;--;
	 	
_ --;™
	

—-*"-//-{
\=^=
J-5-j 	
'!===
^
/I ' I
^%d
tn i
I—I 	 : 	 1—
— — ;•"--
	
	
•~: — -' '-'-
' — l ' — ; —
	 ; 	 : 	
— i 	 i —
— ; — ' — \ — ! —
! • '

M"| , r-
	 ! 	 1 	 1 	 1 	
' - ,
	 • — ! — i—
\-s^tsnr-
. ' 1 ;

-=;=
	
	

Figure B-32.  Slug #7 ejected at 1,125-ft channel down check.

-------
  .
                                 Cement
                               1070ft
_
nqoft
 11:20 ft
 1130ft
Figure B-33.  Leak Test Well.
                                                    Injection Zones
                                114

-------
 Test No. 13: Differential Temperature Survey


 Introduction

    On  November 4,  1987, personnel from  Schlumberger  Well
 Services ran a differential temperature survey in the Leak Test Well.
 The survey was run after  injection had been ongoing  for about  5
 hours and the well had been shut in for 16 hours.

 Well Configuration

    The well was configured as shown  in Figure B-34. The injection
 tubing had been pulled  and  injection was taking place down the long
 string into the perforations at 1,120 to 1,130 feet.  The surface valve
 on the outside tubing  was closed so that no fluid could move through
 this area.

 Differential Temperature Survey
    The log  presentation included curves  for gamma  ray, casing
 collars,  temperature gradient arid differential temperature.

    The temperature gradient was from  65.5 ฐF at about 200 feet to
 73ฐF  at 1,215 feet. The differential temperature  curve  indicated a
 slight (0.2ฐF) change in  temperature at the base of the injection zone.
 The fluid level was indicated at about  173 feet below land surface by
the temperature gradient curve.

 Conclusion

   The differential temperature log indicated there are no  leaks in the
long string.

-------
                                                    Injection Zones
Figure B-34. Leak Test Well.
                                 116

-------
Test No. 14: Nuclear Activation Technique for Detecting Flow
Behind Casing


Introduction
    On  November  3,  1987, personnel  from the  Robert  S.  Kerr
Environmental Research Laboratory (RSKERL)  and  Atlas  Wireline
Service conducted  a  series of tests to determine flow behind pipe
using an oxygen activation tool.

    The purpose of the tests  was  to  determine if  flow could  be
detected behind pipe  in the Leak Test Well and, if possible, the
detection limit of the tool.

Well Configuration
    Figure  B-35 indicates the configuration of the Leak Test Well. A
packer was set at 1,084 feet and  a profile  nipple was open at 700
feet. Injection was  maintained down the injection tubing/long string
annulus, out the 1/4-inch hole in the long string and  up the outside
tubing.

Tool Test
    The test was  conducted with the  Atias Wireline 1  11/16-inch
diameter  oxygen  activation  tool  (Serial No. 24334) located in the
2 3/8-inch  injection  tubing.  Stationary "no flow"  background gamma
ray count  rates were taken for both the long spaced  (LS) and short
spaced (SS) detectors at depths of  300, 800 and 1,000 feet.

    A background  count  rate was  computed  for each  depth  of
investigation  by  determining  the inelastic gamma ray and  oxygen
count rates for three no-flow measurements at each station. For each
no-flow  measurement, the ratio of  the  oxygen  count  rate  to  the
inelastic count rate  was computed, and the  average of these ratios
was determined. The  result of this activity gives  a long-space factor
and short-space factor that are then multiplied times  the measured
inelastic iong space and inelastic  short space count rate, respectively,
to compute the proper background.
    After  determining the  background factors  for each depth
investigated, the too! was moved down the well at speeds of 15 feet
per minute and 30 feet per minute  to check the velocity calculations.
The finai part of the test involved injecting water oown the tubing/iong
string annulus at different flow rates and determining what flow could
be detected coming up the outside tubing. Flow measurements were
taken at depths of 1,000, 800 and 660 feet.
    Table  8-11  is a summary of specific data taken  at a depth  of
1,000 feet. The  determination of interest  during this investigation was
a fiow or  no-flow indication. The velocity data are  aiso of interest,
although not critical to  this series of tests.

-------
                                                    Injection Zones
                             1084 ft Depth of  g.
                              Lower Packer
Surface Casing (571 ft)
2 3/8-in Tubing
Baker Model "L" Sliding
Sleeve
Baker Model "R" Profile
Nipple
Baker Model "Ad-1"
Tension Packer
2 3/8-in Tubing
Baker Model "R" Profile
Nipple
Baker Model "F" Profile
Nipple
5 1/2-in Long String
                                    1100ft

                                     11213ft
                                     1130ft
Figure B-35. Leak Test Well.
    the criterion for flow indication is that the long space  count rate
must  be  greater  than  1.0 counts/second  after  subtracting the
background reading. Thus, from  Table B-10 flows were indicated  at
stations 17 through 26, 36, and 37.
                                 118

-------
 7ab)8 B"1t. Oxygen Activation Log Data, Leak Test Well -Novembers, 1987
Depth
(feet)
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
iฐpo
1000
1000
1000
1000
1000
1000
1000
1000
Station
11
12
13
17
18
19
20
21
22
23
24
25
26
28
29
30
31
32
33
34
35
36
37
38
39
40
Flow
SS
.35
-.01
.05
5.18
3.52
3.68
3.17
5.24
6.29
4.50
5.46
6.36
5.59
.26
.80
1.99
.95
1.33
.02
-.49
3.47
3.02
2.82
.60
-.11
.05
Ind."
LS •
.19
.16
.11
3.02
3.35
2.60
3.36
4.32
3.73
3i91
2.88
3.16
2.60
.43
.24
.51
.32.
.17
.04
.004
.99
1.19
-1.05
.45
.12
.29
Velocity
None
None
None
14 ft/min
155.88 ft/min
21 .88 ft/min
Q
39.43 ft/min
14.69 ft/min
54.65 ft/min
11. 97 ft/min
10.94 ft/min
9.98 ft/min
0
0
5.67 ft/min
0
0
0
. 0
6.09 ft/min
8.18 ft/min
7.78 ft/min
0
0
0
Comments
Not injecting
Not injecting
Not injecting
Injecting .86 gpm
Injecting .86 gpm
Injecting .86 gpm
Injecting .86 gpm
Injecting 4 gpm
Injecting 4 gpm
Injecting 4 gpm
Injecting 1 .5 gpm
Injecting 1.5 gpm
Injecting 1 .5 gpm
Injecting .46 gpm
Injecting .46 gpm
Injecting .46 gprn
Injecting .46 gpm
Injecting .32 gprn
Injecting .32 gprn
Injecting .32 gprn
Injecting .75 gprn
Injecting .75 gpm
Injecting .75 gpm
No injection
No injection
No injection
•With background subtracted

-------
    AS previously SVaiWU, Ilia vtnucuy iiieaauioiiienio aio 111101001.. .y
but are not  significant in the use  of the  tool for determining flow
behind pipe  at this point in the development of the tool,  with one
exception: one must determine the sensitivity of the tool,  i.e., the
slowest velocity the tool  can  identify as flow. The criteria for a valid
velocity measurement are:
1.  The flow indication signal  for the SS must be at least three times
    the error bar.
2.  The flow indication for the LS must be at least two times the error
   ' bar.  ^  "       .'    '    '.  ',     j    "   [               "  \
3.  The LS signal must be less than the SS signal.

4.  Neither signal can be zero.
      ,;!'„"',„ 1 ,  "	|,  :,"..,     i   .  	         ,1  .1  .
    If any of these criteria is not met, the velocity should be shown as
zero  in the data  listing. A  review of the data sheets  from this test
indicates that the velocity measurements meet these criteria.
Conclusions
    The  1  11/16-inch  oxygen activation  tool  was successful in
detecting  flow up  the outside tubing in each of  the  tests  while
injecting at  .86, 4,  1.5  and .75 gallons per minute.  The tool did not
detect flow at the .46 or the .32 gpm rates.
       "       	| • •:" ";	|   .•    '      • •          " [	
    The minimum velocity the tool was able to detect during the tests
was 3 ft/min. The  results of this  and other tests indicate that the
velocity range of the tool in its present configuration is approximately
3 to 100 ft/min.
                               120

-------
 Test Mo.  15:  Nuclear Activation Technique for Detecting  Flow
 Behind Casing


 Introduction
     On  September  14,  1988, personnel  from the  Robert S.  Kerr
 Environmental  Research  Laboratory (RSKERL) and  Atlas  Wireline
 Service conducted a series of tests to determine flow behind  pipe
 using an oxygen activation tool.

     The purpose  of  the  tests was  to  determine if  flow  could be
 detected behind pipe in the Leak Test Well, both in 2 3/8-inch tubing
 and in  a channel in the mud system, and, if possible, the detection
 limit of  the tool.

 Well Configuration

     Figure B-36 indicates  the configuration of the Leak Test Well.  A
 packer  was set at  1,084  feet and a  profile nipple was open at 700
 feet. Injection was maintained down the injection tubing/long  string
 annulus<> out the  1/4-inch  hole in the long string and up the outside
 tubing,  out the tubing  through the  profile nipple at 700  feet  and
 through a channel in the mud to the surface of the ground.

 Tool Test                                         ;
    The test was conducted with the Atlas Wireline  i 11/16-inch
 diameter oxygen  activation  tool located in the 2  3/8-inch injection
 tubing.  Stationary "ho flow"  background gamma ray count rates were
 taken for both the long spaced (LS) and short spaced (SS) detectors
 at a depth of  1,075 feet,  which  was below  the injection  activity.
 Readings were  taken during  injection at depths of 300, 600 and 1,000
 feet to determine both flow/no-flow and velocity.

    A background count rate was computed for the 1,075 feet depth
 by determining  the  inelastic gamma  ray and oxygen count  races for
 three no-flow  measurements at this station.  For  each  no-flow
 measurement, the ratio of the oxygen count rate to the inelastic count
 rate was computed, and the average of these ratios was determined.
 The result  of this activity gives a long-space factor and short-space
 factor that are then multiplied times the measured inelastic long space
 and  inelastic short  space count rate, respectively, to compute  the
 proper background.

    After determining the background  factor, the final part of the test
 involved injecting water  down the  tubing/long  string annulus at
 different flow rates and determining  what  flow could  be detected
 coming  up the  outside tubing, and through the channel in the mud
from 700 feet to the surface of the ground.

    Table B-12  is a summary  of specific data taken during the test.
The  determination of interest during this  investigation was  a flow or

-------
,1  ln	n n,
                                                                                                     Injection Zones
                                                                                            1.   Surface Casing (571 ft)
                                                                                            2.   2 3/8-in Tubing
                                                                                            3.   Baker Model "L" Sliding
                                                                                                Sleeve
                                                                                            4.   Baker Model "R" Profile
                                                                                                Nipple
                                                                                            5.   Baker Model "Ad-1"
                                                                                                Tension Packer
                                                                                            6.  2 3/8-in Tubing
                                                                                            7.   Baker Model "R" Profile
                                                                                                Nipple
                                                                                            8.   Baker Model "F" Profile
                                                                                                Nipple
                                                                              084 n Depth of  g.  5 i/2-in Long String
                                                                              Lower Packer
                                                 Figure 8-36.  Leak Test Well.
                                                 no-flow indication within bo^h the Outside  tubing and  the channel in
                                                 the mud. The velocity data are of interest,  although not critical to this
                                                 series of tests.
                                                     The criterion for flow indication  is  that the long space count rate
                                                 must be greater  than  1.6  counts/second  after  subtracting the
                                                 background reading. Thus, from Table B-12, flows were  indicated at
                                                 stations 3 (1,000 feet) and 4 through 9.
                                                                                  122

-------
   table B-12.     Oxygen Activation Log Data,, Leak Test Well -
                  September 14,1988
Depth
(feet)
1075
1075
1075 .
1(500
1000
600
600
300
300
300
Station
0
1
2
3
4
5
6
7
8
. 9
Flow
SS
-.61
.16
.51
1.24
.89
71.70
71.17
93.87
57,01
62.19
Ind.
LS
.03
-.01
-.02
1.72
1.68
29.10
26.19
23.76
10.05
10.07
Velocity
None
None
None
0
0
8.49 ft/min
7.66 ft/min
5.57ft/min
4.41 ft/min
4.20 ft/min
Comments
Below injection
Below injection
Below injection
Tubing flow
Tubing flow
Channel flow
Channel flow
Channel flow
Channel flow
. Channel flow
    The tests began with a flow of approximately 20 gpm coining from
the pump. Stations 3, 4, 6 and 7 were taken at that flow rate with the
stations opposite the 2 3/8-inch outside tubing (stations 3 and 4) and
the channel in the mud (stations 5, 6 and  7). Although  flow was
detected at each station, a much higher flow indication was seen at
Stations 5, 6 and 7. Stations 8 and 9 were taken opposite the channel"
but at  a flow  rate of about 10 gpm. A reduced  flow indication is
evident for these stations.

Conclusions
    The  1  11/16-inch Oxygen activation tool was  successful  in
detecting flow  at all stations, although the flow  indication was much
.lower at the stations opposite the 2  3/8-inch outside  tubing than in
those stations  opposite the channel  in the  mud  system.  This  was
probably due to the larger size of the mud channel.
    Additional tests should be run with this tool in real wells to provide
data for evaluating the total capability of  the  tool for  detecting flow
behind pipe.
                 •US GOVERNMENT PRINTING OFFICE:1990-748-159/ao487 REPRINt

-------

-------