-------
The FY 1994 Enforcement and Compliance Assurance Accomplishments Report
was prepared by  the Targeting and Evaluation Branch  within the Office of
Enforcement  and  Compliance  Assurance.    The  title  was  revised  from
"Enforcement Accomplishments Report" to reflect the mission of the Office of
Enforcement and Compliance Assurance created in FY 1994 during the Agency's
reorganization  of its compliance and  enforcement  operations.   Information
contained in the report was supplied by the EPA Regional Offices and the Office
of Enforcement and Compliance Assurance.
                        Printed on recycled paper

-------
                         3£>0 R
    FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                          TABLE OF CONTENTS
1.0    INTRODUCTION		 1-1

2.0    REINVENTING A STRONG NATIONAL ENFORCEMENT AND COMPLIANCE
      ASSURANCE PROGRAM	 2-1

      2.1    ENVIRONMENTAL LEADERSHIP PROGRAM	 2-1
      2.2    MULTIMEDIA APPROACHES TO ENVIRONMENTAL PROBLEMS	 2-4
      2.3    ENVIRONMENTAL JUSTICE	 2-7
      2.4    INDUSTRY-SPECIFIC SECTORS	  2-10
      2.5    SUPPLEMENTAL ENVIRONMENTAL PROJECTS  	  2-12
      2.6    SENSITIVE ECOSYSTEM PROTECTION	  2-15
      2.7    FEDERAL FACILITY ENFORCEMENT AND FEDERAL ACTIVITIES	  2-16
      2.8    OTHER ENFORCEMENT AND COMPLIANCE ASSURANCE ACTIVITIES  .  2-18

            2.8.1   Redelegation	  2-18
            2.8.2   Task Forces and Work Groups 	  2-19
            2.8.3   Training and Guidance	  2-19
            2.8.4   Initiatives 	  2-20
            2.8.5   Regulations, Rulemaking, Policy,  and Interpretive Guidance	  2-21
            2.8.6   Native American Affairs	  2-22
            2.8.7   International Activities	  2-23

3.0    REGIONAL AND STATE ENFORCEMENT AND COMPLIANCE ASSURANCE
      ACTIVITIES	 3-1

      3.1    MULTIMEDIA APPROACHES TO ENVIRONMENTAL PROBLEMS	 3-1
      3.2    ENVIRONMENTAL JUSTICE	 3-4
      3.3    INDUSTRY-SPECIFIC SECTORS	 3-6
      3.4    SUPPLEMENTAL ENVIRONMENTAL  PROJECTS 	 3-9
      3.5    SENSITIVE ECOSYSTEMS  	•	  3-12
      3.6    FEDERAL FACILITIES 	  3-13

4.0    ENVIRONMENTAL ENFORCEMENT ACTIVITIES AND PENALTIES 	 4-1

      4.1    CRIMINAL ENFORCEMENT	 4-2
      4.2    CIVIL ENFORCEMENT	 4-4
      4.3    CIVIL REFERRALS	 4-8
      4.4    CERCLA ENFORCEMENT	 4-8

            4.4.1   Alternative Dispute Resolution	 4-9

      4.5    EPA CONTRACTOR LISTING .	  4-10

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                   LIST OF FIGURES
 Figure 2-1.     FY 1994 Enforcement Actions		 2-3
 Figure 2-2.     FY 1994 Monetary Breakout	 2-3

 Figure 4-1.     EPA Civil Penalties and Criminal Fines	 4-2
 Figure 4-2.     Office of Criminal Enforcement	 .... 4-3
 Figure 4-3.     Number of Administrative Penalty Orders by Statute/Program Area  	 4-6
 Figure 4-4.     Total Penalties Assessed in Administrative Penalty Orders
               (by Statute/Program Area)		 4.5
 Figure 4-5.     Number of Civil Judicial Penalties by Statute/Program Area	 4-7
 Figure 4-6.     Total Amount of Civil Judicial Penalties (by Statute/Program Area)  	 4-7
                                   LIST OF TABLES
Table 3-1.

Table 4-1.

Table 4-2.
Table 4-3.
Table 4-4.
Types of Supplemental Environmental Projects in Case Settlements  	  3-11

Number of New Investigations Opened and Referrals to DOJ by EPA's
Criminal Enforcement Program in FY 94	  4.4
Administrative Penalty Orders by Statute/Program Area	  4-5
Civil Judicial Penalties by Statute/Program Area	  4.5
Number of Civil Referrals by Statute	  4-8
                                            11

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT j
                                  1.0  INTRODUCTION
       In Fiscal Year 1994, under the direction of Administrator Carol Browner, the U.S. Environmental
Protection Agency (EPA) reorganized its enforcement and compliance operations to further strengthen
enforcement capability and place increased emphasis  on compliance assurance.  The result of this
reorganization was the Office of Enforcement and Compliance Assurance (OECA). This newly created
office now provides a single voice for national enforcement and compliance  assurance policy and
direction.

       OECA's national policy integrates enforcement  and compliance assurance into an approach that
targets noncomplying sectors of the regulated community, as well as sensitive ecosystems and populations.
This new  enforcement and compliance approach fully supports the Federal initiative of "reinventing
government," which, from the Agency's standpoint, translates into improving environmental compliance
and encouraging innovative solutions to compliance problems.

       This FY 1994 Enforcement and Compliance Assurance Accomplishments  Report documents the
steps EPA has taken in the past year to improve environmental compliance and incorporate innovative
solutions into its enforcement cases. This document reports on EPA efforts on the national and regional
levels and provides information on  some of  the enforcement  and compliance  assurance activities
undertaken by some States.  It also provides national,  regional, and State enforcement highlights and
includes information on the cases taken, developed, and settled by EPA and the States.

       The report is structured around six  Agency themes:

       •   Multimedia approaches to environmental problems
       •   Environmental justice
       •   Industry-specific sectors
       •   Supplemental environmental projects
       •   Sensitive ecosystem protection
       •   Federal facility environmental management.

       Definitions  and general information on each of these themes is  presented in Section 2.  As
expected, not all FY 94 enforcement and compliance assurance accomplishments can be categorized under
the six themes.  Significant accomplishments  outside the  themes are also  addressed throughout the
document.

       Specifically, Section 2 of the report discusses  reinvention efforts underway in EPA's national
enforcement program and the role EPA (Headquarters and Regions) and the States play in that reinvention.
It defines national enforcement initiatives and highlights some of specific enforcement activities conducted
throughout the year. In addition, it provides information on enforcement and compliance assurance efforts
led by the primary offices  within OECA.

       Section 3 focuses on regional enforcement accomplishments and region-specific initiatives.  It also
discusses the relationship between the EPA Regions and the States and highlights some of the coordinated
efforts between the two partners.  It also contains State-specific activities, including initiatives, penalties,
and cases.
                                              1-1

-------
        FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       Section 4 of the report provides overview information on the enforcement activities (e.g., civil and
judicial enforcement, referrals) and penalties sought and assessed by EPA, at both Headquarters and the
regional level.  This section includes graphics and tables that display the specific numbers and amounts
of actions initiated and closed by EPA.  (Note:  State-specific information on these topics is included in
Section 3.)

       Finally, Appendix A to this report contains significant judicial, administrative, and criminal cases
settled in FY 94 by EPA. The cases are presented by statute  (multimedia cases are first, however) in
alphabetical order.  Appendix B presents the cases reported by individual States.  These cases are ordered
by EPA Region, that is,  States from Region I are presented first, and so on.
                                              1-2

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
      2.0  REINVENTING A STRONG NATIONAL ENFORCEMENT AND
                      COMPLIANCE ASSURANCE PROGRAM
       When the Agency reorganized its enforcement and compliance program and created the Office of
Enforcement and Compliance Assurance, it realized that the changes would affect all levels of its national
enforcement program, including Headquarters, the Regions, and the States. EPA knew that the national
program itself would need to undergo "reinvention." An integral part of reinventing the national program
was recognizing that EPA's traditional enforcement tools—monitoring, administrative actions, criminal
sanctions, and monetary penalties—could not, in isolation, lead to sustained compliance in the regulated
community. After detailed analysis, Agency officials determined that EPA needed to combine compliance
assistance and promotion programs with the traditional aspects of compliance monitoring and enforcement.
The heart of EPA's national enforcement program now comprises the following components:

       •  Compliance assistance:  Activities designed to assist the regulated community and encourage
          voluntary compliance with regulations

       •  Compliance monitoring: Activities designed to provide information on the compliance status
          of the regulated community

       •  Enforcement actions:  Powerful sanctions designed to compel compliance by the regulated
          community.

       These three components, together with enhanced coordination of EPA and State actions, will lead
to improved compliance with national environmental laws.  When  EPA Headquarters and Regional
personnel join forces with individual States, the result is a far-reaching national program fully capable of
using all available compliance tools within each of the three components.

2.1    ENVIRONMENTAL LEADERSHIP PROGRAM

       One new tool in the area of compliance assistance is recognizing and rewarding facilities that
exhibit leadership in environmental management and compliance.  To this end, EPA developed the
Environmental Leadership Program (ELP). The ELP is a national pilot program with a two-fold purpose:

       •  To recognize facilities  that  develop and implement innovative environmental  management
           systems and "beyond compliance" programs

       •   To work with these facilities and  understand  their systems and programs, and then share the
           information gathered with the regulated community to  improve  environmental management
           and increase compliance.

Forty proposals were submitted for the  ELP  volunteering to demonstrate innovative approaches to
environmental management and compliance.  In April 1995, EPA selected 12 facilities to participate in
the pilot program.

        In exchange for participants' commitment to demonstrate their innovative approaches, EPA offers
the facilities several benefits, including:
                                             2-1

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        •  Public recognition by EPA as an environmental leader
        •  A limited period to correct any violations identified during the pilot program
        •  An absence of routine inspections by EPA or the State.

        By offering these benefits, EPA has attracted the environmental leaders from all industrial sectors,
including Federal facilities.  The Agency will use the ELP pilot projects to explore ways that it and the
States can encourage facilities to develop innovative auditing,  compliance, and pollution prevention
programs and to establish public accountability for compliance with existing standards in environmental
laws.  The pilots  also will help  EPA develop the elements of a full-scale Environmental Leadership
Program, which will be open to all facilities willing and able to meet the program criteria.  The pilot phase
of this project will run approximately 12 months.

        The second component, compliance monitoring, is being reshaped to provide a holistic, facility-
wide perspective instead of the more traditional programmatic  one. This multimedia concept continues
to mature into a significant method of accomplishing EPA's goals. During the past year, EPA inspectors
conducted approximately 2,000 multimedia inspections at facilities nationwide.  Multimedia inspections
not only provide EPA and State personnel  with a comprehensive view of a facility, but also result in a
more efficient allocation of resources and effective use of personnel.  In addition, these inspections are
usually less time consuming and burdensome to the inspected facility.

        Compliance monitoring activities are also being refocused to support specific Agency initiatives.
For example, facilities are now being targeted for inspection based on their location or specific industry
type. Environmental justice concerns are playing an increasingly more important role in targeting facilities
for inspection, as are  concerns about sensitive ecosystems.

        EPA's  increased emphasis  on compliance  assistance did not signal weakening of traditional
enforcement,  the third component. The Agency combined quality cases that protected the public and the
environment in substantial ways with a record level of cases to promote deterrence. As shown in Figure
2-1,  the Agency brought a record 2,246 enforcement actions with sanctions, including 220 criminal cases,
1,596 administrative  penalty actions,  403  new civil  referrals to the Department  of Justice, and 27
additional civil  referrals  to enforce existing  consent  decrees.  In  addition, the States took  11,334
enforcement actions.  These administrative and judicial sanctions, which surpassed those taken last year,
are the primary enforcement  tools to correct violations, establish deterrence, and create incentives for
future compliance.

        As shown  in Figure 2-2, EPA assessed penalties for FY 94 totaling approximately $151 million
combined for civil penalties and criminal fines and another $206 million was returned  to the Treasury
through Superfund cost recovery.  Injunctive  relief and supplemental  environmental projects in non-
Superfund cases exceeded $740 million.  The number of consent orders, decrees, and penalties and the
vigor with which they were pursued illustrated that EPA is serious about its enforcement commitments.
The  following high-profile examples illustrate  EPA efforts under the  new enforcement and compliance
assurance approach:

        •   A corporation will spend more than $3 million to  eliminate the generation  of hundreds of
           pounds of hazardous wastes it currently disposes of through underground injection.

        •   Another corporation will pay for an independent audit covering TSCA compliance at all of
           its facilities, not just the one facility in violation.  It will also disclose  and correct all
           violations  discovered as a result of the audit.
                                              2-2

-------
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                                 Criminal Referrals
                                                 FY1994
                                                        FY
          Civil Judicial Referrals
            1994 (includes consent decree enforcement actions)
                                                               Administrative Penalty Actions
                                                               FY 1994 (a subset of total administrative activity)
                                                                        State Enforcement Actions
                                                                        FY1994
                        Figure 2-1. FY 1994 Enforcement Actions
                                                                        $740 Million
                        Civil/Criminal Fines
Superfimd Cost Recovery
   Non-Superfund
Injunctive Relief and SEPs
                         Figure 2-2.  FY 1994 Monetary Breakout
                                             2-3

-------
             1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
         •  A company will spend $1 million to develop an innovative cooling system that will reduce
            the amount of water it has to withdraw from an aquifer by 259 million gallons annually.

         •  A State highway department will conduct lead paint abatement on bridges, targeting those
            located in minority and low income residential areas.

         These types  of settlements both significantly expand the environmental and health protection
 achieved through individual enforcement actions and enhance the prospects for long-term compliance.
 Similarly, EPA enforcement actions  are sending a clear deterrence message to would-be violators,  as
 illustrated by the following examples:

         •   The manager and shop foreman of a facility  whose illegal disposal of toluene in a dumpster
            resulted in the death of two 9 year-old boys  were sentenced to 27 months in prison.

         •   The owner of a now-defunct electroplating facility who illegally abandoned more than 27,000
            gallons of hazardous substances within 500 feet of an elementary school received a sentence
            of 2 years in prison.

        •   A laboratory that falsified pesticide residue  data used by EPA to ensure the  safety  of the
            American food supply  received a $15 million fine and its owner was sentenced to 5 years in
            prison.

        When EPA prosecutes violations and publicizes the results, it sends an unmistakable message to
 violators:  "If you threaten the health and safety  of the public, you will be caught and you will be
 prosecuted." This combination of strong, fair, and effective enforcement and  compliance promotion will
 continue to characterize future Agency efforts.

        The remainder of this section highlights selected enforcement and compliance assurance activities
 accomplished at the national level.  Several of the activities involved extensive coordination among EPA
 Headquarters and regional personnel and States. Sections 2.2 through 2.7 discuss national efforts in each
 of the six themes  identified Section 1.  Section 2.8 presents information on national enforcement and
 compliance assurance activities  that cannot be categorized according to the themes.

 2.2     MULTIMEDIA APPROACHES TO ENVIRONMENTAL PROBLEMS

        Multimedia enforcement is a unique and effective tool for addressing environmental problems in
 a comprehensive way. It encompasses a range of enforcement activities, including inspections, notices
 of violations,  administrative orders, and judicial actions, using a wide-range approach  to  evaluate the
 violations, risks, and  problems  and to develop remedies across multiple environmental programs and
 statutes in a deliberate and  coordinated manner.

        Multimedia enforcement is  integral to  EPA's mandate to protect human health and  the Nation's
environment. Because it is comprehensive, multimedia enforcement provides EPA with  the opportunity
to further the Agency's most important goals,  including:
                                              2-4

-------
                                                                                          5 •
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT f ^
       •   Improving ecosystem health

       •   Creating incentives for business to adopt pollution prevention and environmental auditing as
           a corporate commitment

       •   Attacking the complex problems posed by environmental justice

       •   Creating partnerships among States, Regions, tribes, and EPA Headquarters.

       Multimedia enforcement is effective and appropriate in almost any situation, from small companies
to major corporate entities.   Moreover,  it can be implemented  on a local, regional, or  State, level.
Multimedia approaches also benefit industry. Facility-wide multimedia assessments can assist corporate
planners  in achieving production goals, while complying with environmental laws, in a cost-effective
fashion.

       The consolidated multimedia design utilizes trained  and experienced teams of experts to develop
cases from inspection through litigation or settlement. Potential multimedia cases are identified through
multimedia  inspections,  integrated   targeting,
coordinated   case   screening,   and   improved
communication among regulatory programs.  To
prepare personnel for these multimedia activities,
a national multimedia enforcement workshop was
held at NETI-West.  Nearly 100 people attended,
representing  legal  and  program  offices from
OECA, nine Regions, the National Enforcement
Investigations  Center  (NEIC),  Department  of
Justice, and four States. Panel discussions focused
on key multimedia issues, including  the use  of
geographic  initiatives;   targeting  multimedia
enforcement   for   risk   reduction,  ecosystem
protection, environmental justice, or other factors;
multimedia  inspections;  case development and
management; use of supplemental environmental
projects  and pollution  prevention  in multimedia
cases;   and   State,   local,   and  community
involvement. A primary purpose of the workshop
was  to  provide  training  on  the  challenges
presented  by  multimedia enforcement  and  to
discuss solutions developed by various Regions.
Inspection Types

Consolidated  Inspections:
Comprehensive facility
evaluations not only addressing compliance in targeted,
program-specific  regulations,  but  also  identifying
environmental  problems  that might otherwise be
overlooked.   When  regulated  activities or waste
streams  are identified, a compliance evaluation  is
made with respect to applicable requirements.

Coordinated Inspections: Concurrent and coordinated
program-specific pompliance investigations conducted
by a team of investigators representing two or more
program offices, Regions,  or  States.   The team
conducts a detailed compliance evaluation for each
target program.

Single Media Inspections with a Multimedia Checklist:
Program-specific compliance  inspections that are,
conducted  by  one  or  more  inspectors.   The
inspector(s) screens for and reports on  obvious key
indicators  of possible  ndncompliance with other
environmental statutes, usually using a multimedia
checklist.
        Using this training as the springboard, EPA inspectors conducted approximately 2,000 multimedia
.inspections in FY 94.  It should be noted that there are at least  three different types of multimedia
inspections:  1) consolidated,  2) coordinated, and 3) single media  with multimedia checklists.. Of the
2,000 inspections, 113  were  consolidated,  42 were coordinated, and 1,917  were single media using
multimedia checklists.
                                                2-5

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        These inspections resulted in the following enforcement actions:

        •   Nineteen multimedia civil judicial referrals to DOJ
        •   Thirty-two multimedia administrative actions
        •   Four multimedia administrative/judicial actions
        •   Twenty-two single media actions with multimedia settlements.

        The following list highlights some examples of these enforcement actions and the coordination
among HQ, regional, and State enforcement personnel:
           £7.5. v. Marine Shale:  In the 1994
           multimedia trial against Marine Shale
           Processors  (MSP),  the  complaint
           alleged violations  of  RCRA,  CAA,
           and CWA and sought cost recovery
           under   CERCLA.     The  original
           complaint, filed in  1990, alleged that
           the  company  violated  RCRA  by
           operating an incinerator and hazardous
           waste storage units without a permit
           or interim  status, placing  on  the
           ground incinerator ash that exceeded
           land    disposal   restriction   (LDR)
           treatment  standards  and storing the
           incinerator ash in unpermitted  waste
           piles.   The company  claimed that  it
           operated a RCRA-exempt recycling
           facility  that  produced an  aggregate
           product from hazardous waste.  The
           complaint  was amended in 1993 to
           allege   violations  of   the    CAA,
           including   failure   to   obtain   a
           Prevention of Significant Deterioration
           (PSD)   permit,   violations  of  the
           company's State  minor source air
           pollution  permit  and  operating 29
           unpermitted  air  pollution  emission
           sources;  violations  of  the  CWA,
           including discharging water pollution
           without a permit; and demanding the recovery of the government's costs in a cleanup action
           under CERCLA.  Information on the violations was obtained from citizen complaints and
           through a number of EPA and State inspections  and requests for information. The results of
           the trial are provided on the next page.

          Allied Tube & Conduit:  Region V issued a landmark multimedia administrative complaint
           against Allied Tube & Conduit for alleged violations of EPCRA and RCRA. This action arose
           from multiple inspections to determine the company's compliance under both statutes. As a
           result of the EPCRA inspection, EPA determined that the company  failed to  report toxic
           chemical releases  to the air in 1989.  The RCRA inspection revealed numerous violations,
 In the Marine Shale multimedia trial, the District Court
 divided the trial into 5 phases; the results were as
 follows:

 •  In the RCRA sham recycling issues, the jury was
   not able to determine whether MSP was a legitimate
   recycler or an incinerator. The jury was dismissed,
   and no  date was set for the retrial.

 •  The court ruled MSP was liable for failure to obtain
   a PSD  permit  and for failure  to obtain a State
   Implementation Plan permit for 29 miscellaneous
   emission sources.   The  court assessed  civil
   penalties  of  $2.5  million  and  $1  million,
   respectively.

 •  The court ruled that MSP had operated four water
   outfalls  without an NPDES permit and that it had
   discharged large volumes of heated water into the
   adjacent bayou in violation of its NPDES permit. A
   civil penalty of $3 million was assessed.

 •  The judge ruled in favor of the United States on a
   summary judgment motion claiming that MSP was
   storing certain hazardous wastes without a permit
   and without meeting LDR treatment standards. The
   court assessed civil penalties  of $1 million  for
   storage  violations and  $500,000 for land disposal
   restricted waste violations.

•  The Court also entered an  injunction prohibiting
   further violations of the CAA, CWA, and  RCRA;
   however, the effectiveness  of the injunction was
   stayed pending appeal.
                                              2-6

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
          including failure to 1) properly mark containers, 2) record weekly inspections, 3) conduct
          personnel training, 4) adequately maintain fire protection equipment, aisle space, and closure
          of hazardous waste containers, and 5) properly prepare several hazardous waste manifests.
          Corrections of these multiple statutory violations will provide benefits to the public health and
          environment.

       •  U.S. v. Burlington Northern Railroad Company: DOJ filed a civil multimedia action against
          the Burlington Northern Railroad Company on behalf of Regions V and VIII.  The complaint
          alleges  that the company discharged hazardous substances into the Nemadji River near
          Superior, Wisconsin, discharged oil into the North Platte River in Guernsey, Wyoming, and
          discharged oil into navigable waters near the Bighorn River in Worland, Wyoming.  DOJ also
          sought a cost recovery claim under CERCLA for costs incurred by EPA in response to the
          Nemadji River spill.

       •  U.S. v. Tenneco Settlement Finalized:  After almost 3 years of negotiations, Tenneco reached
          a settlement with EPA for cleanup of PCB contamination along its natural gas pipelines and
          payment of a TSCA civil administrative penalty. Tenneco and the Tennessee Gas Pipeline Co.
          will pay a $6.4 million administrative TSCA penalty and cleanup under a CERCLA Removal
          Administrative Order on Consent (AOC).  Region IV is the lead region on this case, which
          covers contaminated sites in five Regions.  In the AOC, Tenneco has agreed to reimburse EPA
          for past costs of $357,087. Long-term cleanup costs covered by the AOC may exceed $240
          million.

2.3    ENVIRONMENTAL JUSTICE

       Many minority, low-income communities have raised concerns about the disproportionate burden
of health consequences they suffer from the siting of industrial plants and waste dumps, as well as from
exposures to pesticides or other toxic chemicals at home and on the job.  Their primary concerns are that
environmental programs do not adequately address these disproportionate exposures.

       In accordance with President Clinton's Executive Order 12898, EPA is addressing these concerns
by assuming a leadership role in environmental justice initiatives and developing an environmental justice
strategy to enhance environmental quality for all U.S. residents. The Agency looks to assure, through its
policies,  programs, and activities, that no  segment of the population,  regardless of race, color, national
origin, or income, bears disproportionately high and adverse human health and environmental  effects.

       To achieve the objectives of its environmental justice strategy, EPA is:

       •  Ensuring that environmental justice is part of all Agency programs, policies, and activities

        •  Identifying  methodologies, research, and  data needed to identify and evaluate populations at
           disproportionately high environmental or human health risks,as well as ensuring  that these
           needs are considered in developing the overall Federal research program

        •  Promoting outreach, communication, and partnerships with stakeholders to ensure sufficient
           stakeholder access  to training, information, and  education.
                                              2-7

-------
         FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        Because implementation of the Agency's environmental justice policy is ongoing, the majority of
 its efforts to date have been in outreach and education for both Agency employees and the public. The
 Agency is refining  its  strategies and analyzing data to direct its compliance assurance, compliance
 monitoring, and enforcement activities more effectively in support of this principle.

        Of primary concern to OECA is the lack of capacity of some low-income and minority populations
 to become involved in permit decisions and enforcement and compliance monitoring activities. To address
 this issue, the Enforcement Capacity and Outreach Office (ECOO) of OECA is leading a pilot program
 to provide education on a variety of environmental justice topics, including:

        •  Citizens' rights and regulatory processes
        •  Opportunities for community involvement in permitting decisions
        •  Training in interpreting data and enforcement/compliance monitoring activities.

        In addition to these outreach efforts, the National Enforcement Training Institute (NETI) developed
 an approach for heightening environmental justice awareness among OECA employees and for enhancing
 citizen participation in environmental compliance monitoring and enforcement functions. Several of the
 individual HQ and regional offices have  also developed and sponsored environmental justice training for
 their employees.  In addition, the Office of Compliance sponsored the Environmental Justice Bike Tour,
 which educated students and communities about environmental awareness and environmental justice issues.

        At the national policy level, OECA established a process for assuring environmental justice in all
 OECA programs, policies,  and activities.  It named  a full-time Environmental Justice Coordinator and
 established an Environmental Justice Coordinating Council (EJCC). The EJCC comprises representatives
 from each major office within OECA and assists in  developing the agency-wide strategic plan.  It also
 provides recommendations to promote environmental justice through enforcement activities at all levels—
 regional, State, and national.

        To date, the EJCC has produced three major draft documents for use within the Agency:

        •   OECA draft strategy  outline, which describes the office's goals and objectives

        •   Potential  projects list, which  provides a matrix of current and future activities

        •   Draft  OECA  workplans, which include  project  descriptions, descriptions of project
           relationships to goals set forth in the strategy outline, anticipated time frames for the projects,
           and key efforts for completing the projects.

        These documents are currently being circulated throughout the Agency for review and comment
 and will be the Agency's road map for all environmental justice  activities.

        Several of the primary  offices  in  OECA are  developing their  own strategies for  including
 environmental justice concepts into enforcement and compliance assurance activities. In conjunction with
 the  Regions,  ORE  is  developing enforcement  guidance  documents  concerning  identification of
environmental justice cases and emphasizing the need for discussion of environmental justice concerns in
 litigation packages and consent decrees. It is also coordinating a national enforcement initiative to ensure
that pesticide registrants adhere to the pesticide product labeling requirements of the agricultural Worker
                                              2-8

-------
      FV 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I ^
Protection Standard (WPS). In October 1994, the first civil administrative cases under the WPS were filed
against  two of the Nation's largest  pesticide manufacturers for  misbranding or incorrectly labeling
pesticides and posing a risk to workers' health.  EPA is seeking a total of $2.1 million in penalties.

        EPA is undertaking other activities to incorporate environmental justice into its enforcement and
compliance monitoring activities.  For example, OC provided access to an extract of the 1990 Census data
in the Integrated Data for Enforcement Analysis (IDEA) information retrieval system that allows IDEA
users to identify regulated facilities based on Census data, such as race and/or income, and then gather
compliance/enforcement  information  about the  facilities.   Environmental justice  efforts under  the
Superfund program have involved conducting a comparative analysis of Superfund enforcement process
data for all NPL sites. OSRE also continues to coordinate with OSWER on identifying site characteristics
and environmental justice indicators to ensure that information relevant to environmental justice issues are
incorporated with enhancements to the Superfund information system (CERCLIS).
                                                   The Office of Criminal Enforcement has implemented
                                                   an aggressive, multimedia, cross regional enforcement
                                                   initiative that strategically targets businesses and other
                                                   violators in minority communities. In partnership with
                                                   the  FBI, ATF, U.S. customs, and other Federal and
                                                   State law enforcement and regulatory officials, OCE
                                                   special agents will investigate business enterprises in
                                                   these  communities  using confidential  informants,
                                                   undercover  sting  operations,  aerial-infrared and
                                                   electronic surveillance,  and  covert sampling and
                                                   monitoring. The overall effect of this combined effort
                                                   will  have direct and positive impact on the health and
                                                   safety of community residents.
        In  addition, EPA is meeting  the White
House's call  for  making  the Federal sector a
national leader in environmental justice efforts.
For example, OFA assisted with the development
of an executive order on environmental justice,
analyzed   environmental  justice   issues   and
socioeconomic impacts under NEPA, and drafted
preliminary guidance for assessing environmental
justice  in  CAA  Section 309  reviews of other
agency   NEPA  documents.    EPA's  Federal
facilities offices also completed projects related to
environmental  justice, including  an  extensive
geographical information system (GIS)  analysis at
25 Federal facilities nationwide.   This  analysis was based on  environmental justice parameters,  as
designated in Executive Order 12898.  These 25 surveys will be sent to the 10 EPA Regions as models
for conducting GIS analysis at the regional level.

        In  FY 94, the Criminal Investigations Division of OCE dedicated 27 percent of its resources to
conducting investigations  in minority communities.   OCE's other accomplishments  in  achieving
environmental justice include:

        •   Special agents in charge from all 10 Regions have submitted innovative plans for proactive
           strategic targeting initiatives on environmental  criminal violations  in communities  with
           environmental justice concerns.  These plans include joint investigations with other Federal
           and State agencies and tribal governments  to prosecute violators  in environmental justice
           communities, as well as geographical initiatives that target environmental criminal violations
           in  such communities.

        •   OCE  modified its agent training course and  other law enforcement personnel training to
           include an  environmental justice segment.

        •   Low income and minority areas of Dallas, Texas, received $6 million in remediation projects
           as the result  of EPA's criminal prosecution in United States v. Robert M. Brittingham and
           John J. LoMonaco (N.D. Tex.).   The former board chairman and the former president of a
           large  ceramic tile manufacturer  were convicted for dumping lead-contaminated hazardous
                                               2-9

-------
| FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                              Tifton is a small Georgia town of approximately 15,000
                                              residents. A total of 19 CERCLA potential hazardous
                                              waste sites are located in Tifton. Of these, one is
                                              already on the National Priorities List (NPL) (Tifton
                                              Drums), one is being evaluated for inclusion on the
                                              NPL, and six have undergone waste removal or are
                                              currently undergoing waste removal.

                                              EPA, in conjunction with CLOUT (a citizen's group in
                                              Tifton), the Georgia Environmental Protection Division,'
                                              and the lift County  Board of  Commissioners, is
                                              implementing the lift County, Georgia, Environmental
                                              Justice   Geographic  Initiative  to   address   the
                                              environmental harm from the multiple sites in Tift
                                              County.  The  Agency for Toxic Substances and
                                              Disease  Registry  (ATSDR) has  also  been active
                                              through existing agreements with  EPA, which provide
                                              for  public   health  assessments in  communities
                                              surrounding  NPL sites. To highlight  the activities in
                                              Tift County, Region IV's senior management officials
                                              attended several  community/public meetings  to
                                              maintain open communication with local community
                                              leaders and residents.
           waste into a sand and gravel pit in a
           Dallas suburb.

        Although somewhat limited, high profile
situations have involved environmental justice and
enforcement and compliance monitoring activities.
In these situations,  EPA Headquarters, Regions,
States, and municipalities have worked together to
forge a solution beneficial to  all involved.  The
Tift County Georgia (Region IV) Environmental
Justice Geographic Initiative is an example of this
coordination.   Under this initiative,  Region  IV
developed and is in the process of implementing
a pilot project in Tift County, Georgia, to address
waste sites located within the city of Tifton and
throughout Tift County.

        Another  environmental  justice   case
involves a major utility company with four electric
power plants  in the Catano, Puerto  Rico,  area.
Catano  is a community in which the  majority of
the people are below the  poverty level and suffer
from poor air and water quality.  The major thrust
of the action is to improve the regional water and
air quality. Section 3 provides more detail on this
case.

2.4     INDUSTRY-SPECIFIC SECTORS

        The    new    framework   for   EPA's
enforcement and compliance assurance programs
reorients  the  Agency's   focus  to  compliance
problems  that pervade certain  sectors of the regulated community. This  "sector approach" enables the
Agency to 1) address noncomplying sectors more effectively, 2) allow for  "whole facility" approaches to
enforcement and compliance, 3) measure more specifically rates of compliance and the effectiveness of
enforcement strategies, 4) augment enforcement strategies with appropriate compliance enhancement
activities, and  5) develop sector expertise,  which  should improve performance in  all aspects of the
Agency's enforcement program.  During the  past  year, EPA made great strides in developing sector
expertise, which will allow the  Agency  to begin  making sector-based  enforcement  and compliance
assurance an integral part of everyday activities.

        The agency-wide Common Sense Initiative  is a prime example of EPA's  sector-based initiatives
and effort to extend its expertise. This program is considered the Agency's cornerstone sector-based
initiative. The purpose of this initiative is to develop and implement strategies for making environmental
regulation more efficient  and more effective. Six industrial sectors were selected to participate:
                                              EPA provided a $200,000 Clean Water Act grant to the
                                              Texas Attorney General to fund a Strike Force that
                                              enforces State and local laws against developers of
                                              colonias. The purpose of the money is to remedy the
                                              colonias' current environmental situation. Colonias are
                                              Hispanic communities concentrated near the Mexican
                                              border in Texas and New Mexico; they usually lack
                                              adequate infrastructure. OFA also worked with ORE,
                                              Region VI, DOJ, the Department of Housing and Urban
                                              Development, and  the  Texas  and New  Mexico
                                              Attorneys'  General  Offices  to  explore additional
                                              responses  to the colonias'  problem.   This initial
                                              groundwork will form the basis of an enhanced Federal
                                              and State effort in 1995.
                                         2-10

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        •   Iron and steel
        •   Electronics and computers
        •   Metal plating and finishing
        •   Auto assembly
        •   Petroleum refining                                                 .    .:
        •   Printing.

        For each  sector,  EPA  is  convening  a  high-level team comprising industry executives,
environmental leaders, government officials, and labor and environmental justice representatives. OECA
is represented on every sector team and is the Agency lead for the printing sector.  The teams will be
looking at six key elements that affect the specific sector:

        •   Promoting pollution prevention opportunities                       .
        •   Conducting regulatory reviews
        •   Undertaking innovative compliance assistance and enforcement initiatives
        •   Simplifying and improving reporting and recordkeeping requirements
        •   Implementing permit streamlining opportunities
        •   Promoting innovative environmental technologies.
                                                   The Common Sense Initiative, one of EPA's primary
                                                   sector-based efforts, comprises 18 industries:
                                                     Printing

                                                     Pulp and Paper
                                                     Inorganic Chemicals
                                                     Organic Chemicals
                                                     Petroleum Refining
                                                     Iron and Steel
                                                     Rubber, and Plastics
                                                     Non-Ferrous Metals
                                                     Auto Assembly
Ship/Rail/Car/Truck
Cleaning
Dry Cleaning
Metal Mining
Non-Metallic Mining
Lumber/Wood
Furniture and Fixtures
Stone/Glass/Concrete
Metal Fabrication
Electronics and
Computers.	
       To   further   enhance   the   Agency's
knowledge  of specific  sectors, the  Office  of
Compliance is conducting an extensive analysis to
develop  a comprehensive  profile  of 18  major
industrial sectors.  The  completed profiles will
contain  a  variety  of  information,  including
industrial   process   descriptions,    multimedia
regulatory  requirements,  historical enforcement
performance data, pollutant release information,
current public and private sector initiatives, and an
assessment  of  potential  pollution  prevention
opportunities for the sector.  These profiles will be
the basis for development of sector compliance strategies, which will address the appropriate mix of
compliance  and  enforcement activities,  inspection priorities,  regional/State  roles, and  the use  of
enforcement actions and targeted initiatives.

       In addition to these sector-based programs, several other projects focus on industrial sectors. Some
of the programs specifically target  compliance  assistance;  others  are primarily enforcement-based
programs.  Some of the specific sectors and descriptions of the initiatives are described below.

       Compliance assistance initiatives included:

       •   Dry cleaning:   To assist  the perchloroethylene (perc) dry cleaners in complying with the
           various  environmental  regulations,  OC  is  developing  an  easy-to-read  version of  the
           environmental requirements for dry cleaners, including a Korean language translation of the
           brochure.  This document explains the environmental requirements under CAA, RCRA, CWA,
           and SDWA and includes commonly asked questions concerning the regulations and a quick
           reference  checklist of activities that an owner/operator must perform to comply with the
           regulations.
                                              2-11

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       •  Auto body shops: OC is also working with auto body shops and the Department of Education
          to develop  a  new  national  curriculum for auto technicians that includes environmental
          requirements.

       •  Animal feeding operations:  The Water Enforcement Division of ORE participated in the
          development of an  initiative targeting animal  feeding operations.  The goal is  to increase
          protection of water resources by promoting, encouraging, and requiring sound environmental
          management and practices in the animal feeding operation community.

       •  Pulp and paper mills:   The Toxics  and  Pesticides Division of ORE helped develop a
          voluntary program to restrict the land application of sludges containing dioxin. The American
          Forest and  Paper Association, as well as two pulp and  paper  mills, signed  agreements
          implementing the program.

       The following examples were all enforcement-based initiatives:

       •  Municipal waste combustion facilities:  The RCRA  Enforcement Division of ORE, in
          conjunction with OC, developed and wrote a  strategy for  implementing the U.S. Supreme
          Court decision in the City of Chicago v. Environmental Defense Fund concerning municipal
          waste combustion (MWC) ash.  The decision held that RCRA Section 3001 (i) exempts MWC
          facilities from RCRA hazardous waste regulations but  that MWC ash is not exempt from
          RCRA's hazardous waste definition. The  strategy provided the Regions with guidance in
          bringing waste-to-energy  facilities affected by the decision into compliance with RCRA
          Subtitle C as quickly as  possible.

       •  Incinerators and boilers and industrial furnaces  (BIFs):  EPA and  DOJ announced the
          second  Hazardous  Waste Combustion  Initiative, which  included filing  13  settlement
          agreements  and  10 complaints against owners  and operators of incinerators and  BIFs.  The
          settled cases recovered $1.5 million in penalties from 4 incinerators and 9 BIFs.  The 10
          complaints included the first civil judicial BIF complaint; the 9 remaining administrative
          complaints sought $4.8 million in penalties from 7 BIFs and 2 incinerators.

       Also in  FY 94, OFA updated its Environmental Assessment (EA) guidance for reviewers of new
source NPDES permits. This EA guidance was completed for the following industrial  sectors: mining,
fossil-fueled electric steam generating  stations, pulp and paper mills,  timber processing, and  coal
gasification facilities.

       These strategies and other compliance assurance projects will eventually lead the Agency to sector-
based compliance monitoring and enforcement.  All of this preliminary work, however, will only make
those activities more effective and efficient when they are undertaken.

2.5    SUPPLEMENTAL ENVIRONMENTAL PROJECTS

       Historically, when the U.S.  Environmental Protection Agency took a civil administrative action
against a violating facility, it sought only monetary penalties.  In the 1990s, however,  EPA  changed its
enforcement approach to seek not only  monetary penalties but also an improvement in environmental
quality.  Environmental improvement is expected to occur as  a  result of Supplemental Environmental
Projects (SEPs). A SEP is a project that a respondent/defendant in a case agrees to conduct as a term of
settlement sometimes in exchange for partial mitigation of a civil  penalty.  The purpose of these projects
                                            2-12

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I
is to expand protection of human health and the environment beyond that required by the specific Federal,
State, or local law directly related to an enforcement action.
                                                  Types of SEPs Used In Enforcement Cases

                                                  •  Cleanup/restoration projects
                                                  •  Disposal
                                                  •  Environmental audit
                                                  •  Outreach/public awareness projects
                                                  •  Training
                                                  •  Source reduction/pollution prevention—process
                                                     modification
                                                  •  Source reduction/pollution prevention—recycling
                                                  •  Source reduction/pollution
                                                     prevention—technological improvement
                                                  •  Waste minimization/pollution reduction—process
                                                     modification
                                                  •  Waste minimization/pollution reduction—recycling
                                                  •  Waste minimization/pollution
                                                     reduction—technological improvement
       SEPs are an important tool in promoting
the  Agency  goals  of  pollution  prevention,
pollution reduction, and environmental justice. In
addition  to  the  continued  use  of  SEPs  in
enforcement  cases,  the  Revised  Supplemental
Environmental Project Policy is being prepared
which will make it easier to incorporate SEPs into
settlement  negotiations.   The  policy  has  been
revised to allow maximum flexibility to achieve
settlements that enhance environmental protection
while maintaining  a  strong penalty policy to
promote  deterrence.  As part of an enforcement
settlement, the amount of the agreed-upon penalty
may be reduced  to reflect the commitment made
by an alleged violator to undertake a SEP.  Two
critical factors must be considered in negotiating
SEPs:  1) the assessed penalty must reflect the gravity of the violation and the economic benefit achieved
and 2) the enforcement settlement must foster a deterrent effect.  In addition, projects undertaken in SEPs
must go beyond  compliance requirements with applicable laws and regulations.

       During FY 94, EPA incorporated SEPs  in  settlements for violations under a broad range of
programs.  As in the past, SEPs were applied in EPCRA,  TSCA, and FIFRA cases.  In FY 94, for
example, 190 cases with SEP terms were negotiated under TSCA (55), EPCRA Section 313 (49)  and
FIFRA (8), with an additional 78 SEPs negotiated under other sections of EPCRA.  EPA also applied
SEPs in cases brought  under CAA, CWA, RCRA, and CERCLA.

       Many of the SEP cases in FY 94 represented landmark cases in terms of the scope of the action,
the nature of the'violation, the type of environmental benefits achieved, or for other reasons. For example,
the State-Federal agreement resolving a case against the Massachusetts Highway Department represents
the largest ever commitment of public resources to address RCRA violations at State facilities anywhere
in the country. In a consent agreement resolving a RCRA administrative action, EPA-New England, the
MA DEP, and the Massachusetts Highway Department (MHD) agreed that MHD will spend $20 million
to investigate and remediate environmental problems at all 138 of its facilities and will dedicate $5 million
to several SEPs,  including projects that will benefit environmental justice areas. The 138 State facilities
are the most facilities to be addressed by a single RCRA-related agreement.

       Another  record setting component of this SEP is MHD's $5 million commitment, a significant
portion of which is designated for training approximately 350 local  and  municipal transportation  and
public  works agency personnel and for providing emergency response equipment to Local Emergency
Planning Committees (LEPCs)  affected by MHD operations, with particular focus on low-income  and
minority neighborhoods.

       Region IV s case against Ashland Petroleum is another notable example.  EPA filed a consent
agreement  and consent order (CACO) that  settled  alleged  reporting violations under Section  304 of
EPCRA. The CACO provided for a $1.56 million penalty, for which Ashland agreed to pay $312,000
in cash to EPA, with the remainder of the penalty to be put toward SEPs valued at more than $1,248,000.
                                              2-13

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
The total $1.56 million value of the settlement made this the Agency's largest EPCRA penalty ever.  This
is also the first multi-State EPCRA action in Region IV's history.

       The following list provides additional examples  of SEP agreements and the specific  activities
conducted under the SEP terms:

       •   U.S. v. Eastman Kodak Co. (W.D.N.Y.): EPA and DOJ announced the settlement of a RCRA
           case against Eastman Kodak in Rochester, New York.  The consent decree included a cash
           penalty of $5 million, a $12 million investment in six SEPs to reduce hazardous wastes in its
           2,200 acre Kodak Park, and a compliance schedule.  The aggregate reduction in hazardous
           wastes as a result of the SEPs is expected to exceed 2.3 million pounds of pollutants by the
           year 2001.

           The major violations addressed in the complaint and consent decree involved Kodak's failure
           to properly characterize waste streams, the leakage of hazardous wastes from a massive (31-
           mile long) industrial sewer, and operation of an  unpermitted incinerator. An NEIC-led team
           that conducted a  9-week,  comprehensive multimedia investigation of the Kodak facility
           discovered these violations.

           In a separate TSCA administrative enforcement action against Kodak, the company agreed to
           spend $3.6 million to remove 17 PCB transformers located at the Rochester facility.  Based
           on  this very valuable SEP, a $17,000 penalty reduction was allowed; the final cash penalty
           provided for in the October 1993 settlement was $42,000.

       •   United States v. Beech Aircraft Corporation  (D. Kansas):  The U.S. District Court for the
           District of Kansas entered a consent decree resolving civil violations of the CWA  at Beech
           Aircraft Corporation's Wichita, Kansas, facility.  Beech was required to pay a civil penalty of
           $521,000 for its violations of Federal categorical pretreatment standards for metal finishers,
           failure to meet the reporting requirements of the general pretreatment regulations, and failure
           to comply  in a timely manner with an administrative order issued by Region VII.

           In addition to paying the civil penalty, Beech agreed to perform a supplemental environmental
           project valued at approximately $200,000 that consists of installing centrifuges or equivalent
           systems to remove sludge from the Wichita facility's existing water wash paint spray booths.
           The purpose of this pollution prevention project is to reduce the total volume and toxicity of
           hazardous waste sludge generated and to allow the recycling of paint spray booth wastewater,
           thereby reducing the volume and concentration of pollutants in the wastewater ultimately
           discharged to the city of Wichita's POTW.

       •   United States  v. City and County of Honolulu (D. Hawaii):  A consent decree was lodged
           resolving a CWA enforcement action brought by the United States and the State of Hawaii
           against the City and County of Honolulu. This action arose as a result of the city and county
           of Honolulu's poor maintenance of its sewer system, which resulted in more than 300 spills
           of raw or partially treated sewage into Hawaiian waters (including a spill of 50 million gallons
           of raw sewage into Pearl Harbor in 1991 that  attracted national attention).  The  city and
           county of Honolulu also failed tp implement an adequate pretreatment program to regulate the
           discharge of toxics from industries discharging into its sewer system.
                                             2-14

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
           Under the consent agreement, the city and county of Honolulu will pay a civil penalty of $1.2
           million and committed to improving the  operation and maintenance  of its  sewer system,
           including the renovation  of 1,900 miles of sewer lines during the next 20 years, and to
           developing and implementing a pretreatment program to regulate the discharge of industrial
           toxic wastewater.   Under the decree, the city and county  also committed to spending $30
           million on SEPs for treating and reusing wastewater and sludge.  Honolulu will recycle 10
           tons of sewage sludge per day by 1998 and 10 million gallons of wastewater per day by the
           year 2001.

2.6    SENSITIVE ECOSYSTEM PROTECTION

       The United States  and other parts of the world are experiencing a serious loss of essential natural
resources. If this continues, this loss will result in a long-term threat to  the Nation's economic prosperity,
security, and the sustainability of remaining ecological systems.  The value of ecosystems can be measured
in many different ways.  Living things and the ecosystems upon which  they depend provide communities
with food, clean air, clean water, and a multitude of other goods and  services. Native American tribes
and many others believe that air life is interconnected—that the health of one depends directly on the
health of another.  Consequently, the high rates of species endangerment, loss of natural resources (e.g.,
timber), habitat fragmentation, and losses of recreational opportunities pose a potential threat to the health,
cultural values, lifestyle, and economic future of virtually every American.

       Many  EPA activities  have helped protect ecosystems.  The Agency  has implemented laws to
control many of the major sources that pollute the Nation's air, water, and land. Yet, even as the more
obvious problems are resolved, scientists discover other environmental stresses that threaten  ecological
resources and general well-being.  Evidence of these problems can be  seen in the decline of the salmon
populations in the Pacific Northwest and the oyster stock in the Chesapeake Bay, the decrease in migratory
bird populations, and degraded coral  reef systems.

       Although  many Federal, State, tribal, and local regulations address these problems, past efforts
have been as fragmented as the laws enacted to solve the problems. Because EPA concentrated on issuing
permits, establishing  pollutant limits, and setting national standards, as required by environmental laws,
the Agency did not pay enough attention to the overall environmental  health of specific ecosystems.  In
short, EPA has been  "program-driven" rather than "place-driven."

       As the Agency moves increasingly to a place-driven approach, existing barriers to progress must
be identified and addressed.   EPA must collaborate with  other Federal, State, tribal, and local agencies,
as well as private partners, to remove the barriers and achieve the ultimate goal of healthy, sustainable
ecosystems.  The  Agency, therefore, will  act to solve  integrated environmental  problems  through a
framework of ecosystem  protection in close partnership  with others.   This approach will integrate
environmental management with human needs,  consider  long-term ecosystem health, and highlight the
positive correlation between economic prosperity and environmental well-being.

       EPA is currently  placing high priority  on  developing compliance assurance and enforcement
programs that focus on sensitive ecosystem  protection. However, it is still a relatively new emphasis in
the Agency, and, therefore, applicable projects are developing.  To date, EPA has promoted this initiative
and mandated that it become  an integral part of all  Agency decision making,  as well as an integral part
of the compliance assurance and enforcement programs in particular.
                                              2-15

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT

        OECA's Office of Federal Activities (OFA) has been active in sensitive ecosystem protection >. .1
 has taken the lead in a number of important ecosystem management and protection initiatives during fY
 94:

        •  Midwestfloods:  OFA served as EPA's representative to the White House Task Force on levee
           repair and long-term recovery and ensured a focus on the opportunities for significant long-
           term transformation of floodplain management practices in the region.  OFA established an
           overall principle for the Task Force: the need to capitalize upon the lessons learned from this
           event to trigger  reinvention of current Federal programs affecting floodplain management.
           OFA, in conjunction with the White House, pursued a strategic assessment of Federal activities
           in floodplains and issued the report entitled, Sharing the Challenge: Floodplain Management
           Into the 21st Century.

        •  Everglades: OFA represented EPA at the final negotiations and signing of the multiagency
           agreement on restoration of the Everglades. OFA continues to coordinate with Region IV, the
           Office of Wetlands, Oceans, and Watersheds, and  other EPA offices to build a team of experts
           to participate in the technical and scientific studies of this complex ecosystem necessary to
           create a plan for environmentally sustainable development in the region.

        •  Endangered species activities: OFA has been a lead for the Endangered Species Coordinating
           Committee, which was established to describe current activities and obligations, set priorities,
           and establish appropriate training, support,  and liaison functions with the U.S. Fish and
           Wildlife Service and National Marine Fisheries Service.   OFA also coordinated the Deputy
           Administrator's agency wide Taskforce on Endangered Species Management within EPA.

        •  Forest conference:  The forest conference was designed to break the impasse developed over
           the use and protection of the Northwest forest resources. From the beginning, OFA has been
           an active member of the President's Forest Team, providing input to ecosystem protection and
           watershed management in particular.  OFA staff have been involved in both the review and
           preparation of the Draft Forest Conference Supplemental EIS.

2.7     FEDERAL FACILITY ENFORCEMENT AND FEDERAL ACTIVITIES

        EPA's newly reorganized enforcement and compliance program has provided the Federal facilities
offices With improved  opportunities to  assure compliance with environmental requirements across the
Federal sector.  The 1992 Federal Facility Compliance  Act  boosted enforcement capability by clearly
establishing RCRA penalty authority against Federal facilities. The act authorizes EPA to levy fines
against other Federal agencies.

        In addition to traditional enforcement measures, the Federal facilities program includes compliance
assistance activities designed to ensure full compliance without exacting severe penalties.  Executive Order
12856, Federal Compliance with Right-to-Know Laws and Pollution Prevention Requirements, committed
Federal agencies to implement pollution prevention practices across all missions and activities.  EPA is
taking a leadership role in implementing the Executive  Order and has issued a guide for agency-wide
pollution prevention strategies, interpretive guidance for all  of the Executive Order's requirements,
guidance for developing facility-specific plans, a guide for meeting pollution reduction goals, and a user's
guide to environmental cost accounting.
                                             2-16

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT!^
       To further educate its employees and exchange and develop ideas, EPA held the annual Federal
Facilities Coordinator's Meeting. The meeting included Headquarters and regional personnel and covered
a range of topics, including regional impacts from  the  HQ reorganization,  revision of the Federal
compliance strategy, Federal Facility Compliance Act implementation, implementation of Executive Order
12856, OMB A-106 revisions, and current status of the multimedia initiative.

       To help Agency personnel monitor compliance at  Federal facilities, the Federal facilities office
developed a new  version of the Federal Facility Tracking  System (FFTS), a pilot computer system that
tracks compliance activities at Federal facility  sites.  The new system provides  a multimedia view of
activities to assist with planning, targeting inspections, and reporting.
                                                          In FY 94, EPA and participating States issued:

                                                            15 Warning Letters
                                                            27 Notices of Violation
                                                            8 Notices of Noncompliance
                                                            18 Administrative Orders
                                                            3 Field Citations
                                                            4 Federal Facility Compliance Agreements.
       In  FY  94,  EPA  and  the  States  issued  40
administrative orders totaling more than $6.5 million in
penalties.  The Federal facilities compliance strategy will
continue to include joint  EPA  and State multimedia
inspections  at  targeted  Federal  facilities.   EPA  and
participating States recently completed first year activities
associated   with  the   FY  93/94  Federal  Facilities
MultiMedia Enforcement/Compliance Initiative (FMECI).
In FY 94,  EPA evaluated  31 Federal facilities using a
multimedia approach; the FY 93 inspections resulted in 75 FY 94 enforcement actions under nine statutes.
Federal facilities in seven Regions were assessed a total of $2.1 million in penalties.

       EPA continued its FY 93 enforcement efforts in cleanup and environmental restoration. At the
end of FY  94, EPA had crafted 111 Interagency Agreements with Federal agencies  defining the cleanup
process at  121 NPL Federal facilities.  These agreements are backed by stipulated  penalties, which are
used to ensure compliance  with the terms of the cleanup activities.

       In July 1994, for example, the Department of Energy settled a CERCLA penalty action with EPA
and the State of Colorado for $2.8 million for violations of several cleanup deadlines for the Rocky Flats
facility. These violations are resulting in the delay of the overall cleanup at this facility.

       The following  list highlights selected examples of the enforcement actions taken against Federal
facilities in FY 94:
           Coast Guard, Kodiak, Alaska Facility:  EPA Region 10 issued a complaint against the U.S.
           Coast Guard Kodiak Support Center, Kodiak, Alaska, seeking $1,018,552 in penalties.  The
           complaint resulted from two major violations of RCRA:  1) failure to properly monitor ground
           water in an  area where  cleaning solvents  had been dumped and 2) the illegal storage of
           hazardous waste without a proper permit from EPA.  The complaint was the first action
           brought against a civilian Federal agency under the Federal Facility Compliance Act of 1992.

           The Presidio:  Region IX  filed a complaint and  citations against the U.S. Army Garrison,
           Presidio  of San  Francisco,  for violating RCRA and assessed a penalty of $556,500 for the
           hazardous waste violations.  Region IX inspectors identified a number of violations at the
           Presidio, including failure to transport hazardous waste offsite within 90 days, failure to label
           properly approximately  200  drums of hazardous wastes,  failure to keep 15 containers of
           hazardous wastes closed, and failure  to make weekly inspections of three hazardous waste
           storage areas.
                                               2-17

-------
       ) FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        •   Schofield Barracks: Region LX assessed $543,900 in penalties under RCRA against Schofield
           Barracks, a U.S. Army facility located in Wahiawa, Hawaii.  The facility operates numerous
           motorpools and maintenance shops that generate various wastes, including waste paint, waste
           solvents, and contaminated waste oils, which are listed  as hazardous waste under RCRA.
           Region IX inspections determined that the facility was illegally operating as a RCRA storage
           facility.  Violations included failure to transport RCRA-regulated waste offsite within the
           allowed 90-day accumulation period, failure to label waste properly, and failure to make
           adequate hazardous waste determinations.  In addition,  the facility failed to comply  with
           requirements pertaining to the hazardous waste training program, the contingency plan, and
           preparedness and prevention measures.

        EPA's Federal facility offices are also responsible for reviewing all Federal facility documentation
prepared under NEPA. In FY 94, for example, 515 environmental impact statements (EISs) were  filed
with OFA under its delegation from the Council on Environmental Quality (CEQ) (278 draft and 237
final).  EPA commented on 210 draft EISs and  172 final EISs. Of these, EPA rated 2 draft EISs EU
(environmentally unsatisfactory), 30 draft EISs EO (environmental objections), and the  remaining draft
EISs either EC (environmental concerns) or LO (lack of objections). Also during the year, OFA approved
eight Environmental Policy  Agreements between EPA and  other Federal agencies, including the
Department of Justice, Department of Agriculture, Department of Interior, Department of Defense, Small
Business Administration, Department of Commerce, and Department of Transportation.
2.8
OTHER ENFORCEMENT AND COMPLIANCE ASSURANCE ACTIVITIES
        In FY 94, enforcement and compliance assurance accomplishments occurred in arenas beyond the
six theme areas.  Significant achievements were accomplished across all program  areas and under each
environmental statute. The following sections document some of the more significant accomplishments
throughout the year.

2.8.1   Rcdelegation

        As an adjunct to the reorganizational changes  that occurred in  FY 94,  OECA eliminated
unnecessary or duplicative layers of review by assessing and revising existing delegation of authority and
concurrence procedures by redelegating a substantial portion of the authority to manage and settle civil
judicial and administrative enforcement cases to the Regional Counsel.  The redelegation authorizes  the
Regions to settle a substantial number of enforcement cases without the formal involvement of OECA,
thus eliminating a potentially redundant and time-consuming level of review and freeing OECA to focus
with the Regions on enforcement cases that present nationally significant issues.

        The Assistant  Administrator  redelegated  to  the Regional Counsel  the authority to settle
enforcement cases with bottom-line penalties of less than $500,000 without formal OECA involvement,
provided that the cases present no nationally significant issues.  With the agreement of OECA's Office
of Regulatory Enforcement, the Regional Counsel may also settle non-nationally significant cases with
penalties higher than $500,000. OECA's continued formal involvement in nationally significant cases,
regional audits, the regional Counsels' reporting relationship to the Assistant Administrator, and numerous
informal contacts  between OECA and the regions will  all ensure that national policy goals will continue
to be met.

        Redelegation marks  a real  turning-point  in  the  Headquarters/regional relationship in  the
enforcement and  compliance assurance arena.   The new approach preserves  and  enhances  OECA's
                                             2-18

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
leadership role of setting national directions and policies on enforcement issues, while providing regional
managers the flexibility to implement their compliance and enforcement programs in a more efficient
manner.  To help implement the redelegation, OECA's Office of Regulatory Enforcement produced a
uniform, cross-media set of procedures that further emphasize trust, flexibility, and common sense as the
fundamental principles of the Headquarters/regional relationship.

2.8.2   Task Forces and Work Groups

       In FY 94, Headquarters and regional personnel represented OECA on numerous task forces and
work groups. The Air Enforcement Division of ORE worked on an intergovernmental task force designed
to coordinate the government-wide response to the illegal importation of ozone depleting chemicals. OFA
chaired a work group  that examined  EPA programs  and  NEPA.  The work  group conducted a
comprehensive study of EPA activities with respect to the key NEPA criteria—environmental analysis,
consideration of alternatives, and public participation.  The  work group also look  at program office
compliance with other environmental requirements, such as the Endangered Species Act.

        OFA also represented EPA on the Technical Advisory Group to develop  international standards
for environmental auditing by  coordinating EPA comments and working on this draft report to reflect
EPA's preferred positions. In addition, OFA chaired a new group designated to  develop U.S. proposed
standards for environmental audits of Environmental Management Systems.

        The Enforcement Capacity and Outreach Office's Constituent Outreach Team  (COT) established
a framework that assists OECA in consulting with State, local, and tribal governments on broad policy
and specific  issues  associated  with  enforcement and compliance assurance.  As a  result, OECA has
designed an intergovernmental  relations  framework that  incorporates three components:  a Forum of
senior-level policy makers to focus on broad enforcement and  compliance policies; a network of federal,
State, local, and tribal enforcement and compliance practitioners; and specific strategies for strengthening
regional and State interaction.

        When fully  implemented, the network  will consist  of 30 to  40 environmental  enforcement
practitioners from EPA  (Headquarters and  regions) and State, local, and tribal governments.  The  main
objectives of the network are  to enhance State/EPA  communications and to  develop a network of
environmental enforcement and compliance assurance managers to provide expertise on planning and
priority setting process.

2.8.3   Training and Guidance

        As a result of the OECA reorganization, the National Enforcement Training Institute (NET!)
experienced significant growth  in FY 94.  NETI made progress in the area of training technology by using
the computer and satellite transmission to disseminate training  materials,  information, and courses.  NETI
also emphasized its role serving as a clearinghouse for training information, in assessing constituent needs,
in  continuing international training, and developing plans for the  state-of-the-art NETI Headquarters
Training Center in Washington, DC.  In FY 94, NET! trained more than 7,000 enforcement professionals.
NETI provided training through 180 courses conducted in all 10 regional offices,  the NETI-West facility
at Lakewood, Colorado, various State locations, and Mexico.  Through funding by grants and cooperative
agreements, NETI assisted the four  Regional Environmental Enforcement Associations. This year, the
associations jointly sponsored the Environmental Crime Awareness Training for Law Enforcement, which
was transmitted via satellite to 2,200 local law enforcement officers.
                                              2-19

-------
            1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        Moreover, NETI redesigned and delivered the Basic Environmental Enforcement Course, which
focuses on the entire enforcement process, including a walk-through inspection, writing inspection reports,
and a mock negotiation simulation. NETI offered several new courses, including the Advanced RCRA
Inspector Institute.  Experienced EPA and State RCRA inspectors applied their experiences in RCRA
enforcement through an exchange of information, concepts, and skills.

        EPA also conducted several inspector training courses in FY 94, including the following FIFRA
and EPCRA courses:  FIFRA Worker Protection Inspector Training, Pesticide Use Inspector Training,
Pesticide Product Enforcement Course, and EPCRA Section 313 Inspector Training and EPCRA Health
and Safety Training.

        EPA also developed and distributed several guidance documents, including:

        •  Acid Rain Compliance/Enforcement Guidance

        •  Waste Analysis Plan Guidance

        •  Final guidance on  ways to incorporate pollution prevention into NEPA and Clean Air Act
           Section 309 environmental review processes.

2.8.4    Initiatives

        In addition to the accomplishments discussed according to the six themes, EPA began several other
national initiatives, as demonstrated by the examples in the following list:

        •   Oil Pollution Act  Initiative:  EPA, in conjunction with DOJ and the U.S. Coast Guard,
           announced  the coordinated filing of 28 cases against commercial polluters who unlawfully
           discharged  oil or other hazardous substances into waters of the United States or adjoining
           shorelines and, in some cases, who violated oil spill prevention regulations.  The initiative
           included two judicial cases filed by DOJ on behalf of EPA and the Coast Guard — 1 civil and
           1 criminal — as well as 26 EPA administrative penalty actions in 13 States. The administrative
           cases collectively sought civil penalties of approximately $1 million.

           One DOJ case involved the discharge of bilge water and waste oil from the cruise ship Viking
           Princess that  left a 2.5-mile oil slick off the Florida coast.  This case resulted in a plea
           agreement and the payment of a $500,000 fine. Among the administrative cases, one involved
          Tosco Refinery,  a refiner and  marketer of wholesale petroleum products in  Martinez,
          California, for spilling more than 2,500 gallons of oil into a drainage ditch that emptied into
          U.S. waters.  Another involved Burlington Asphalt Corporation in Mt. Holly, New Jersey,
           which spilled more than 7,500 gallons of fuel oil onto county property and a storm drain that
          emptied into a creek.

       •  Diesel Enforcement Initiative: EPA' s Mobile Source Program executed a joint initiative with
          the State of Maryland and the Internal Revenue Service for enforcement of the diesel
          desulfurization regulations. Upon receiving a tip from a Maryland State trooper about possible
          diesel  misfueling, including  the  use  of untaxed, high-sulfur diesel in motor  vehicles in
          violation not only of EPA's diesel desulfurization regulations but of both Federal and State
          tax laws,  a series of joint inspections were conducted, resulting in both State and Federal
                                             2-20

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I
           enforcement actions.  Eight notices of violations with proposed penalties of $46,500 were
           issued. Three of the cases have been settled for penalties of $8,400.

       •   TSCA Inventory Update Rule (IUR) Case Initiative: The IUR seeks information to update
           EPA's TSCA Chemical Substance Inventory, which is EPA's baseline of information on toxic
           substances. To target violators and highlight the importance of compliance with the IUR, EPA
           Headquarters and regional offices filed complaints  seeking approximately $2.9 million  in
           penalties against 39 U.S. chemical manufacturers and importers for failing to report  specific
           chemical production and site information in a timely and accurate manner. EPA launched the
           IUR case initiative to increase industry awareness of IUR reporting requirements and of the
           IUR reporting cycle.

       •   FIFRA Good Laboratory Practice Standards Case Initiative:  EPA issued 12 civil complaints
           against pesticide registrants proposing $183,000 in penalties for violations of the Agency's
           GLP standards and FIFRA. Citing the GLP violations, the Agency also issued five warning
           letters to the testing facilities that had conducted studies supporting pesticide registrations and
           issued one warning letter to another registrant for less serious violations. These enforcement
           actions reaffirm EPA's  commitment to  vigorous  enforcement  of FIFRA's data quality
           provisions.

2.8.5   Regulations, Rulemaking, Policy, and Interpretive Guidance

       In FY 94, EPA proposed and promulgated several rales and regulations that focused on various
aspects of  the Clean  Air Act.  For instance, AED worked with the Office  of Air and Radiation on
numerous Title Vl-related rales and regulations, including:

       •   A rale on the phase out of ozone depleting chemicals
       •   A rale on the sale of nonessential products
       •   A proposed rale concerning the labeling of products containing ozone depleting chemicals
       •   Regulations addressing certification of individuals to service motor vehicle air conditioners.

       In addition, AED contributed to a proposed rale for the Clean Air Act Field Citations Program
and a proposed rale for the Clean Air Act Citizens Awards.  The Mobile Source Enforcement Branch
(MSEB)  of  AED completed the  reformulated  gasoline  (RFG)  and  anti-dumping  standards  and
requirements.

       EPA also completed its first year of compliance monitoring and enforcement of the diesel
desulfurization regulations.  These regulations, which require the removal of approximately 80 percent of
the sulfur content from unregulated diesel fuel, are a companion to other agency regulations that require
substantial  reductions  in particulate emissions from diesel motor vehicle engines beginning with the  1994
model year. Program office and enforcement staff conducted extensive public outreach targeting all levels
of the diesel fuel industry, including diesel fuel users, to ensure a smooth industry transition into this new
requirement and to maximize compliance. EPA inspectors were in  the field monitoring compliance  on
the first effective date of the regulations and completed more than 4,000 inspections during the first year.

       EPA also undertook the following regulatory and ralemaking efforts in FY 94:
                                              2-21

-------
         FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        •  Published a proposal to create a new EPCRA Section 313 reporting threshold of 1 million
           pounds for facilities that release and/or transfer offsite less than 100 pounds of a regulated
           toxic chemical per year.

        •  Published in the Federal Register a final rule adding 21  chemicals and proposed another rule
           to add more than 300 chemicals to the list.

        •  Published in the Federal Register a final rule amending EPA's hexavalent chromium rule. The
           amendment resulted from a petition filed by the Chrome Coalition in the DC Circuit Court of
           Appeals. EPA negotiated a settlement agreement under which it would propose an amendment
           to narrow the scope of the hexavalent chromium rule.

        •  Proposed  several amendments to its new chemical review process under TSCA Section 5.
           These amendments included an expanded exemption for polymers, an expanded low volume
           exemption, increased opportunities to use the expedited process for issuing significant new use
           rules, and various procedural changes.

        •  Completed the interim final amendments to the Agency's asbestos Model Accreditation Plan.
           This regulation now extends the training and accreditation requirements of AHERA to asbestos
           inspectors and  abatement personnel in all public  and commercial buildings.   The new
           regulation also contains criteria and standards for revoking the accreditation of persons and
           the approval of training courses  and state programs.

        •  Proposed requirements  for lead-based paint activities. These regulations establish a training
           and accreditation program for lead abatement workers that resembles the asbestos Model
           Accreditation Plan.  The regulations also prescribe standards for conducting lead-based paint
           inspections,  hazard  assessments, and abatements  in target housing  (housing built prior to
           1978), public and commercial buildings, and superstructures, such as bridges.

        In addition to the rules and regulations, EPA issued some major  policies and strategies.  For
example, the Agency  published the Combined Sewer Overflow  (CSO) Control Policy, which addresses
pollution that occurs as a result of combined sewer overflows. CSOs are overflows that occur when the
capacity of sewer systems or treatment facilities is exceeded due to a precipitation event.  The policy is
both a permitting and enforcement strategy  and  clarifies how CSOs should be permitted in the future.
EPA also issued its Storm Water Enforcement Strategy.  The enforcement priorities for the storm water
program were designed to address covered municipalities that have not applied for a storm water permit
and to identify and enforce against  covered facilities with industrial  activity that have  failed to  apply for
a storm  water permit.  EPA also  revised the UIC Class I Wells Significant Noncompliance (SNC)
definition in FY 94.  Under the revised  definition, violations with the potential to affect underground
sources of drinking water are maintained as SNC violations; minor infractions  would not necessarily
require SNC reporting.

2.8.6   Native American Affairs

       Throughout FY 94, the Agency, specifically OFA, was involved extensively in Native American
affairs and programs.   OFA held  Interagency Indian  Work  Group meetings with numerous Federal
agencies, chaired the  Headquarters Indian work group monthly meetings, and sponsored the annual
national conference. In  addition, OFA completed the FY 93 report entitled, Environmental Activities on
                                             2-22

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT

Indian Lands and assisted many of the 545 tribes and Alaska Native villages that are preparing to
environmentally manage to their lands.  Selected accomplishments in this area include the following:

       •  General Assistance Program:  The Multimedia Assistance Program began in FY 90 with
          $151,000 for two pilot projects.  In FY 94, $8.5 million was appropriated for the program,
          bringing the total to $22.9 million with 133 new and continuation grants serving more than
          350 tribes under individual tribal and intertribal consortia grants.

       •  Treatment as a State Regulations:  An intra-agency work group, chaired by OF A, drafted
          regulations simplifying the procedure and making it less burdensome and offensive to tribes
          to apply and become eligible for grants and program authorization.

       •  Tribal Enforcement Report: OFA prepared the first annual report to Congress on the number
          of tribes approved by the Administrator to enforce environmental laws and the effectiveness
          of that enforcement.  Although the Administrator had not  approved any Native American
          tribes  to enforce  environmental laws, the Agency did enter into pesticide enforcement
          agreements with 23 tribes and certified a number of tribal pesticides inspectors.

2.8.7  International Activities

       EPA is becoming more involved in international environmental affairs, especially with our North
American neighbors. In FY 94, EPA designed and delivered several programs to  an international
audience. For example, NET! trained 56 Mexican inspectors at a 5-day Multimedia Inspection Course.
This course  is  part of ongoing cooperative training activities between EPA and  Mexico's environmental
protection agency, the Secretaria de Desarrollo Social (Ministry of Social Development) (SEDESOL).
NETI also designed and presented a 4-day Train-the-Trainers workshop in Mexico City for 17 SEDESOL
officials, who were selected as future trainers in Mexico.

       OFA developed a training course for U.S. and Mexican customs and environmental officials  in
detecting and inspecting hazardous waste shipments. The course will be delivered at key border crossings
throughout 1995.  OFA  also performed  the following activities:

        •  Trained  and provided  technical  assistance  to  Mexican environmental  inspectors  and
           enforcement personnel

        •  Promoted interagency cooperation among agencies on both sides of the border through grants
           to  border enforcement programs implemented by State environmental agencies

        •  Initiated efforts' to promote voluntary compliance with applicable environmental laws among
           U.S. operations in Mexico through environmental auditing and pollution prevention

        •  Helped prepare subpoenas  issued  under the Toxic  Substances Control  Act to U.S. parent
           companies of Maquiladoras operating in Mexicali, Mexico.

        In conjunction with Regions VI and IX, OFA led EPA efforts with the U.S. /Mexico Cooperative
 Enforcement Strategy Work Group. EPA initiated cooperative training efforts  with U.S. /Mexican customs
 officials in compliance monitoring for transboundary shipments of hazardous waste and began activities
 to  encourage  U.S.  parent companies to take  leadership  roles in promoting compliance and  pollution
                                             2-23

-------
   TS?
   • HOtlF
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
prevention among their Mexican operations  through  participation in Mexico's environmental  audit
program.

       In addition, through cooperative activity with Federal and provincial officials, EPA worked with
the Province of Manitoba, Canada, to require  pollution control for a major new facility that is equally
stringent to the control on U.S. plants. The Canadian precedent will help maintain competitiveness of U.S.
industry by requiring comparable levels of pollution control for facilities in both countries.  OFA also
supervised management of an environmental project in Nizhnii Tagil, Russia, designed to target low-cost
efforts to  address the most serious problems in  a highly polluted provincial region.  Compliance and
enforcement are key elements in the  institution building project component, which also includes training
and technical assistance in monitoring, risk assessment, standards, and regulations.
                                            2-24

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
      3.0  REGIONAL AND STATE ENFORCEMENT AND COMPLIANCE
                               ASSURANCE ACTIVITIES
       As discussed  in Section 2,  EPA's enforcement and compliance  assurance program  involves
coordinated efforts  among  EPA Headquarters and regional and State  offices.  This section focuses
primarily on the accomplishments of the regions and on partnerships that exist between the regions and
States in monitoring and ensuring compliance throughout the regulated community.

       Authority to implement  the wide variety  of  environmental regulations is  sometimes widely
distributed across several regional and State programs. Accordingly, several  situations involving disparate
program offices require cooperation and coordination between those offices.  To achieve this coordination,
many of the regions have actively promoted region/State partnerships, and FY 94 provided numerous
examples of the beneficial results, including:

       •   EPA-New England and Massachusetts have begun piloting a coordinated case initiative for
           CAA violations; the region is also working with Connecticut to direct pilot efforts  at CWA
           violations. EPA-New England also undertook an initiative to coordinate  CAA Stage I bulk
           terminal vapor recovery activities with the States. The region provided inspector training for
           the States, issued information requests and  emission testing requirements  to subject sources,
           and conducted emission tests in Massachusetts, Maine, and Connecticut.

       •   Region II conducted consolidated inspections that were performed jointly with the New York
           State Department of Environmental Conservation, the first such joint Federal/State multimedia
           inspections in Region II.

       •   Region V and the States in the region have entered into cooperative agreements with EPA for
           pesticide enforcement. The States now work closely with Region V on inspections and take
           many enforcement actions for pesticide misuse violation. The  States still refer most of the
           product  violations to Region V for enforcement.  Therefore, most  of Region V's FIFRA
           enforcement actions are based on the findings of State inspections.

       •   Region VIII Multimedia Field Inspection Team performed several cooperative inspections that
           included State and city agency personnel.

       These are a few examples of the coordination that is currently occurring between regions and
States.  The following sections provide more examples of these partnerships, as well as further describing
regional and State enforcement and compliance assurance accomplishments.

3.1    MULTIMEDIA APPROACHES TO ENVIRONMENTAL PROBLEMS

       As described  in  Section 2,  multimedia compliance  monitoring  and  enforcement  represent
increasingly important tools in EPA's efforts to enforce environmental regulations.  Multimedia inspections
provide a  cost-efficient approach for directing compliance monitoring resources and also increase the
environmental return on enforcement investments.

       During FY 94, EPA regions continued to expand their multimedia enforcement activities.  Positive
developments have taken place in areas of multimedia program coordination, inspections conducted, and
multimedia enforcement cases brought and settled.  Joint efforts have included:  increasing the focus on
                                             3-1

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
multimedia  issues  and methods through  implementation of oversight committees, participation in
multimedia  enforcement  training,  and  incorporation of national  and region-specific priorities in
enforcement targeting strategies.  As  a  result, more multimedia inspections were conducted, with a
corresponding increase in  case referrals, administrative actions, criminal actions, and case settlements.

       Overall, regional multimedia activity for the year increased.  Region II reported 12 consolidated
multimedia inspections, involving essentially all of the program offices. Region III also placed increasing
importance on the  role of multimedia enforcement.  During FY 94, the region  undertook six major
multimedia  inspections.   The inspections focused  on several  major  regional objectives, including
environmental justice, State-Federal relations, and Federal facility compliance. Region VII conducted eight
consolidated multimedia inspections. These inspections, resulting from the regional targeting mechanism,
included State and local participation, and evaluated environmental justice factors.

       Region IV multimedia activities for FY 94 included 19 consolidated multimedia inspections with
two or more programs sending inspectors simultaneously. Two of the inspections were undertaken as part
of the Federal Facility Multimedia Enforcement/Compliance Initiative (at Fort Stewart, Georgia, and the
Naval  Complex, Pensacola, Florida).  In addition to the 19 multimedia  inspections, all of Region IV's
Federal facility inspections were multimedia in nature. The Region  IV Federal Facilities Coordination
(FFC)  program conducted seven Federal facilities multimedia inspections in FY 94.  These FFC  program
inspections resulted in at least seven State or EPA Region IV enforcement actions.
                                                   Region VIII defined an organizational plan designed
                                                   to  more  effectively  address  cross  cutting,
                                                   multimedia issues.  The goal of this reorganization
                                                   was  to  place  programs  and  functions  in
                                                   organizations  that  will  enhance  multimedia
                                                   opportunities and maintain the  large majority of
                                                   single-media responsibilities.  In FY 94, the region
                                                   conducted 10 targeted multimedia inspections. By
                                                   including census data evaluation and  the three
                                                   "lifestyle clusters"  suggested by OECA into both
                                                   targeting and screening activities, an environmental
                                                   justice profile was prepared for each site.	
       Region IV settled six cases in FY 94
resulting from these multimedia activities.  The
total  penalties amounted  to  more than  $10.3
million   with  several  penalties   yet  to  be
determined.   The RCRA .program settled its
multimedia case against Gulf States Steel for $1.1
million.     The  RCRA   program  and  the
Underground  Storage  Tank  (UST)  program
participated in a major multimedia case against
Somerset Refinery  and reached  settlement  in
principle with penalties of $2.75  million.  The
TSCA/CERCLA  multimedia  case  handled by
Region IV against Tennessee Gas Pipeline  for violations in several regions was settled for $6.4 million.

       Region X multimedia efforts continued to integrate and strengthen a cross-program/multimedia
perspective and capacity into all  stages of the compliance assurance and enforcement planning and
decision-making process.   The region targets multimedia inspections using risk factors, including the
toxicity and amounts of the pollutant(s) emitted, the proximity to sensitive/disadvantaged populations, the
sensitivity of the environment and  history of noncompliance. The region also continued to invest in the
National Multimedia Federal Facilities Initiative, which resulted in enhanced compliance at the Federal
facilities that have been  inspected.  Two facilities  received  comprehensive multimedia  compliance
inspections.

        These  examples reflect  the increasing emphasis  the regions  have  placed on  multimedia
enforcement activities during FY 94. For some regions, the emphasis is maintained and leveraged through
the development of multimedia oversight committees responsible for coordinating multimedia enforcement
activities. In Region VIII, for example, the multimedia program is carried out by a number of offices and
through  several  mechanisms.   The Regional  Enforcement Officer and  the  Regional Enforcement
                                               3-2

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 Coordinator  are responsible for  coordinating the multimedia activities of the 15  separate Regional
 enforcement  programs.  The Regional Enforcement Forum represents all enforcement programs and
 coordinates the review and  implementation of regional, cross-program, and multimedia inspection and
 enforcement  activities  including inspection coordination and review of selected enforcement actions.

        In addition to  providing a management structure  supportive of multimedia enforcement,  some
 regions have increased awareness of the potential for multimedia actions through training.  Training has
 been directed at both regional program office staff and State agency personnel.  During FY 94, Region
 VII provided multimedia training to the Nebraska Department of Environmental Quality (NDEQ).  This
 training was a result of dialogues between the region and NDEQ management in which NDEQ identified
 several specific training needs.  Region VII then designed, developed, and provided training  that met
 NDEQ's needs.

        Another example of the region-State partnership at work in multimedia enforcement is provided
 by the multimedia inspection of KBP Coil Coaters (Denver, Colorado) conducted in Region VIII. Six
 environmental programs  were interested in this facility and inspectors participated from four entities,
 including EPA, the State, the Denver County Air Program, and the Denver Metro Wastewater Reclamation
 District. Various violations were discovered during the inspection, including unidentified waste streams,
 unknown process modifications, abandoned underground storage tanks and drums, potential PCB leaks,
 fire code violations, and potential OSHA violations.

        Based on the coordinated inspections, Region VIII and Colorado began a coordinated enforcement
 response  to bring  this facility  into compliance and seek penalties for past violations. The response
 includes coordination  of additional information requested from the facility, financial status research,
 prioritization of compliance activities, tracking and timed issuance of two NOVs, and two administrative
 complaints. A team approach involving EPA and State personnel was  taken in all these activities.
                                                                    *
        The regions have improved implementation of multimedia enforcement through oversight, training,
 and State/region coordination. Equally important, however, are changes in the application of enforcement
 efforts. The Regions have expanded the use of multimedia enforcement as one of many tools in support
 of broad regional and  national  enforcement initiatives. For example, an inspection of the New Jersey
 Transit Bus Operations supported the national transportation facilities  initiative and South Dakota and
 Region VIII conducted a multimedia inspection at Merrilat Industries in support of the National Wood
 Products Initiative.

        Regional  targeting  strategies directly address national priorities.   A primary example is the
 incorporation of environmental justice considerations in prioritizing and targeting multimedia inspections.
 Regions III,  IV, VIII,  and  X reported consideration of environmental justice in multimedia targeting
 strategies.  Region VIII, for example, prepares an "environmental justice profile" for each site included
 in its inspection targeting and screening process,  so that environmental justice is evaluated with  other
 criteria in determining  the need for action at particular sites.  (For more information on environmental
justice activities, see Sections 2.2 and 3.2.)

        Multimedia enforcement in the regions has also benefitted from the consideration of priorities
particular to the individual regions. For example, Region II actively pursued several regional geographic
enforcement initiatives. The region's initiative in the Catano region of Puerto Rico generated a number
of enforcement cases in addition to its major multimedia cases against PREPA and the Caribbean Petro-
leum Company.  The region also pursued geographic initiatives in the Corning, Chemung, and Cortland
aquifer regions of New York, the Camden Aquifer region of New Jersey, and the Niagara Frontier region
                                              3-3

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
of New York. Similarly, as part of the Puget Sound Initiative, Region X participated in inspections in the
Duwamish River watershed, an environmental justice area identified by a GIS mapping system used for
multimedia targeting. In conjunction with these inspections, Region X worked with contractors to create
a multimedia checklist designed to obtain readily available information relating to potential violations of
CWA, EPCRA, CAA, and TSCA.

        Region X's experience illustrates another development in multimedia enforcement activities in the
regions, the use of multimedia checklists. Several of the regions have increased their use of this tool to
broaden the scope of program-specific investigations.  Region II  leads the Nation in single-media
inspections performed using multimedia checklists.

3.2     ENVIRONMENTAL JUSTICE

        FY 94 efforts to include environmental justice in enforcement activities vary widely among
regions, with some regions explicitly including environmental justice as a criterion in targeting and others
creating specific geographic initiatives to address enforcement and compliance issues in environmental
justice areas. Some regions have incorporated environmental justice-oriented projects in SEP terms of case
settlements or included  equity considerations  as  part  of  larger geographic initiatives.  This section
summarizes select environmental justice activities in the regions, focusing first on  compliance monitoring
efforts  and second on enforcement.   Taken together,  these examples indicate that consideration  of
environmental justice is becoming a  standard operating procedure in the regions, with environmental
justice activities being combined  with other ongoing enforcement and compliance assurance activities.
        Region  III  developed  two  geographic
initiatives  aimed  at areas  with  environmental
justice concerns. One of these initiatives focuses
on Chester, Pennsylvania, an area in which more
than  68 percent of the residents are African-
American, more than 60 percent are on  public
assistance, and the average per-capita income is
less than $9,200. This area has a concentration of
industrial sources contributing to pollution, as well
as traffic and noise, which are of great concern to
the residents.  The region's enforcement strategy
in Chester has two components:  toxic emission
reductions and compliance.
Region IV has made environmental justice a focus
of its enforcement activities  within its NPDES
program by doubling monitoring efforts at facilities
located in minority or lower income areas to ensure
compliance.  All of the major  industrial facilities
along the Lower Mississippi Corridor, from  Baton
Rouge to New Orleans, Louisiana, are monitored
closely to ensure  compliance.  These facilities
comply with their NPDES effluent limitations more
than 99 percent of  the time. Compliance rates of
municipalities in the  corridor are  also closely
monitored as  it became  necessary to  file a
complaint against the  City  of New Orleans in FY
1994, for  long-term  improper treatment  of its
        Region  III ranked facilities in Chester using the chronic index,  a system of weighing TRI
emissions by their toxicity. The 10 highest scoring facilities were then reviewed for enforcement potential
and a number of multimedia and single-media inspections scheduled. Four multimedia inspections and
numerous single-media inspections are planned in FY 95. The goal of these actions is to reduce,  either
directly through injunctions or indirectly through SEPs, emissions of toxic  pollutants.  A second aspect
of the toxic emission reduction strategy will grow out of a long-term risk assessment for Chester that is
targeted for completion in FY 95.  Emissions estimates will be used to model exposures in order to
determine which areas of the city are at the greatest risk. Facilities with the highest emission levels will
then become candidates for  increased enforcement surveillance.  Region III also plans to improve
compliance with environmental regulations in Chester by increasing oversight in a number of programs.
                                               3-4

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       The region's second geographic initiative focuses on the Anacostia River, Washington, DC.  The
Anacostia River is among the most contaminated in the country.  Fish tissue contamination is a public
health concern.  Economically disadvantaged residents of the surrounding communities are exposed to
risks that EPA and others are seeking to eliminate.  Recent studies of the Anacostia identified "hot spots"
of sediment contamination that appear to be associated with particular storm sewers.  The sources of these
contaminants, and their potential as continuing sources, are not fully understood.

       Region Ill's enforcement strategy is to identify the major sources of the contamination isolated
in the sediment/storm sewer studies and commence enforcement for ongoing discharges. The region will
separately evaluate the contribution of spills (especially of PCBs) in the storm drain area to the observed
contamination of sediments and fish in  the Anacostia and evaluate enforcement as a means of preventing
future spills. In addition, the region will evaluate nearby Federal facilities and assess their present or
historic contribution to the problem and responsibility for participating in its solution.
                                                   Region X is incorporating multimedia enforcement
                                                   tools  to address enforcement and  compliance
                                                   issues in an environmental justice area. As part of
                                                   the Puget Sound Initiative, Region X oversaw SPCC
                                                   inspections in the Duwamish River watershed, an
                                                   environmental justice area identified by the  GIS
                                                   mapping system used for multimedia targeting. In
                                                   conjunction with  these inspections, the region
                                                   created a multimedia checklist designed to obtain
                                                   readily available information  relating to potential
                                                   violations  of  CWA,  EPCRA, CAA,  and TSCA.
                                                   Region X is working cooperatively with the State of
       In at least two cases in FY 94, EPA-New
England   incorporated   environmental   justice
projects in SEP terms of case settlements.  One
such case, involving the Massachusetts Highway
Department (MHD), includes SEP conditions for
provision   of   hazardous  materials  emergency
response  equipment  to  the local  emergency
planning committees (LEPCs)  in communities
affected by MHD operations, with particular focus
on low-income and minority neighborhoods. The
equipment will assist the local committees  in
tracking and storing information on the identity
and  location  of hazardous  chemicals in  their
districts and enhance their response action information systems.  Efforts will also be made to remediate
lots in inner city communities affected by MHD's hazardous waste practices; the plan is then to convert
the lots into beneficial  areas, such as parks,  green  spaces, or economic development projects  in  the
neighborhoods.

       Similarly, EPA entered a consent agreement  and final order in  which the city of Boston agreed
to pay $117,300 in civil penalties for violation of the TSCA PCB requirements at Boston City Hospital.
The city  also  agreed to perform a  SEP  as  part of the  settlement,  which involves removal  of 10
underground storage tanks located throughout the city  at a cost of more than $80,000.  Boston City
Hospital serves mostly  a low income, minority population.  The  settlement will bring this inner city
hospital into compliance with environmental regulations  and reduce the  risk of harm to public health and
the environment in the Boston minority community.
        During FY 94, Region VI developed a civil judicial enforcement action that was filled on October
27, 1994, in the Middle District of Louisiana, against Borden Chemicals and Plastics and two related
Borden entities. The case involves alleged hazardous contaminant releases at Borden's Geismar, Louisiana
facility, which is located in a highly industrialized area on the Mississippi River with  a predominantly
African-American population.  In addition, the case alleges other violations, including  illegal export of
hazardous wastes  to South Africa.  In a press release issued on October 27, 1994, EPA Administrator
Carol Browner said, "The Clinton  Administration is committed to making sure that no  company will
realize unfair profits from pollution anywhere in the U.S.,  but particularly in minority  and low-income
communities that already face disproportionate risks."  The Administrator also noted that "environmental
                                               3-5

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
pollution does not stop at U.S. borders, and we will use all of our enforcement authorities against those
who engage in the illegal international hazardous waste trade."

3.3    INDUSTRY-SPECIFIC SECTORS

       FY 94 witnessed significant enforcement activities aimed at specific  industrial sectors in the
regions.  Some of the initiatives represented regional efforts to implement larger national programs, as
described in Section 2; others developed from region-specific priorities.  This section highlights selected
industry-specific initiatives by region.

       Several of the regions accomplished industry-specific compliance monitoring activities during FY
94.   EPA-New England,  for example, developed and implemented an initiative under the  CAA
amendments  of 1990.   Under the  CAA  Stage  II  initiative,  the  State of Connecticut conducted
approximately 970 inspections at  gasoline stations and other facilities subject to the  vapor recovery
requirements  and  issued approximately 800 notices  of violation.   Also, as  part of the  National
Administrative Order with Automotive Service Stations project, Region III confirmed the closure of all
facilities inventoried by the major oil corporations within this region.  More than 200 wells were closed
as part of the compliance and outreach effort  specified in this order. The region also issued  proposed
orders for noncompliant facilities that required the violators to inventory  all facilities operated in this
Region for additional injection wells and to implement pollution prevention measures at all facilities.

       Region VI provides  an example of compliance monitoring under the  National Combustion
Initiatives.  The region and the States annually inspect 100 percent of the combustion facilities actually
burning waste. During FY 94, Region VI issued consent agreement and final  orders (CAFOs) for five
combustion cases. In addition, through the course of 30 inspections, Region VI discovered wide-spread
noncompliance among foundries.  Based on pervasive noncompliance and the concerns over impacts to
the environment and worker safety, the region targeted the foundry sector for compliance assistance. The
Region  conducted  inspections, gathered data, and met with  industry and State agencies to lay the
groundwork for a meaningful State/EPA  compliance outreach to the industry in FY 95.

       Region VI's EPCRA enforcement activities included targeted -compliance sweeps of facilities in
a number of industrial sectors. EPA conducted these sweeps in  San Antonio and Fort Worth, Texas,
targeting manufacturers, plating shops, refineries, and warehouses.  Of the 120 facilities inspected,  11
complaints were issued under EPCRA Section 312, for non-filing of inventory reports with State and local
emergency response agencies.
        Region  VII also focused  much of  its
efforts on industry-specific compliance assistance
activities.  For example, the region conducted the
following activities:

        •  Conducted extensive outreach for two
           new  air  toxics  rules  that   were
           promulgated under the CAA during
           FY 94.  Two massive mailings  were
           sent to  the dry cleaning industry and
           the region set up a hot-line number to
           allow people quick access for answers.
Region VI initiated an effort to ensure that quality
data is being submitted by laboratories. The region
developed   an  initiative  within  the  NPDES
Enforcement Program to inspect and enforce, as
necessary, against contract laboratories that have
been providing analytical services to a  number of
major discharge  facilities.   The   Enforcement
Program also  works closely with  the Regional
Office of Criminal Investigation to develop cases
against individuals for falsification of  discharge
monitoring report data.	
                                               3-6

-------
FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
  •  Conducted outreach efforts in the chemical manufacturing industry for the new Hazardous
     Organic NESHAPs regulation.  A mail-out was sent to 300 potential sources subject to the
     new requirements. The region emphasized education and outreach to facilities subject to new
     toxics rules promulgated under Section 112 of the CAA.

  •  Implemented the Missouri Voluntary Compliance Program, which was aimed at non-metallic
     mineral processing plants.  This program offered a time-limited opportunity to a specific
     industrial  sector to disclose violations of the CAA NSPS testing/reporting requirements in
     exchange  for reduced administrative penalties and compliance assistance.  This program
     brought 45 facilities into compliance, most of  which would  not  have been reached via
     traditional enforcement  methods.  Region VII  is continuing with the second phase of this
     program,  which is to follow  up with non-participating facilities in this sector with  strong
     traditional inspection and enforcement activities.

  •  Conducted outreach meetings  with the Cement Kiln Recycling Coalition to assist that industry
     sector in complying with the  RCRA Boilers and Industrial Furnaces Rule.

  •  Conducted extensive outreach/compliance assistance activities in the four States to alert and
     inform members of the agricultural sector, Congress, State legislatures, and the public of the
     requirements of the FIFRA Worker Protection Standards (WPS).

  In FY 94, Region VIE conducted three major compliance and enforcement initiatives:

  •  Mining Initiative: The goal of the Mining Initiative was to obtain compliance with the CWA
     at approximately 300 active metal mines and metal mining exploration facilities.  In South
     Dakota, EPA identified  and inspected all metal mines prior to delegation to the State.  EPA
     has issued NPDES permits to  two of the mines and is pursuing an administrative enforcement
     action for discharge without an NPDES permit for one of the mines. It is expected that the
     State will  issue permits to the remaining South Dakota  mines by the end of 1994.  The
     knowledge gained during the initiative will help identify and develop optimum approaches for
     regulating mining activities.   Previous RCRA inspections  at about a dozen mining facilities
     (including two trona mines)  in Wyoming led to 8 RCRA §  3008(a) orders with FY 94
     settlements totalling $506,267 and SEPs totalling $675,794.

  •  Refinery Initiative:  Under this initiative, Region VIII reviewed the issues surrounding the
     RCRA/CWA interface pertaining to contaminated ground  water seeps to surface water from
     petroleum refineries. (This issue gained attention due to recent citizen suits against CRC and
     Texaco in the Region.)  The region identified approximately 40 operating and  closed
     refineries. Of these, six  have a "high" RCRA corrective action ranking for surface water under
     NCAPS.   In FY  94, the Court entered a consent decree  between the United  States and
     Defendants known as the Powder River Crude Processors (Texaco Refining and Marketing,
     Conoco Pipeline Company, Phillips Petroleum Company, Eighty-eight Oil Company, and True
     Oil  Company) which requires, among other things, payment of $300,000 in penalties and
     performance of work at the Site,  estimated to  cost several million dollars, which addresses
     conditions posing imminent and substantial endangerment  to the environment. The Regional
     Refinery Workgroup is now completing a comprehensive evaluation of and strategy for all the
     refineries in  the Region.
                                         3-7

-------
       | FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        •   Trona Initiative:  Wyoming holds the largest deposits of soda ash in the U.S., in the form of
           an ore known as "trona." As a result, five trona mines and processing plants have been built
           and are currently in operation.  The region of southwestern Wyoming in which these plants
           are congregated often has a visible layer of air pollution hanging over it, which has prompted
           several citizen complaints over the past few years.  EPA and the States believe that the five
           trona plants are contributing significantly to this pollution.  Region VIE decided that, due to
           exceedances of mass particulate limits, as determined by stack tests, condensable organic
           matter is  being  emitted and  is likely  a major contributor  to the pollution.  Due to the
           grandfathering of these sources to the test methods for measuring condensable organics,  none
           of these "violations" has been able to go forward. The goals of the initiative are to determine
           an approach for documenting the opacity violations at these plants and a strategy for correcting
           this deficiency, such as a Finding of Violation pursuant to CAA Section 113(a)(2), which may
           also  lead  to additional controls for volatile condensable organics.  In FY 94, the  RCRA
           program settled two RCRA § 3008(a) orders with two trona mines for a total of $239,000.
           Additionally, the RCRA program  identified a need  for  training in the management  of
           hazardous waste at several of the plants. The Region is also addressing acid rain and visibility
           issues affecting the Wind River Reservation (9,000 Arapahoe and Shoshone) in the Rock
           Springs area.  The U.S. Fish  and Wildlife Service  is looking into issues affecting how the
           evaporation ponds affect migratory birds and effects on the Bridger and Fitzpatrick Wilderness
           Area. Other programs participating in  this initiative include: RCRA, NPDES, EPCRA §§
           311/312/313, TSCA/PCB,  and  TSCA  §§ 5  and  8.  The  Region is  now completing  a
           comprehensive multimedia compliance evaluation of all trona mines arid auxiliary industries
           in the Region.

        Region VIII also contributed to  other industry-specific initiatives.  In response to the Data Quality
Initiative, the Region  undertook targeted inspections of injection well  operators'  data gathering and
reporting procedures.  As a result of  the  initiative, the  region reinforced its belief that clearer  UIC
reporting requirements  in the UIC regulations are needed and that continued outreach is needed for
operators to ensure that permit/regulatory requirements are thoroughly understood and expectations for
compliance are consistent.

        As part of the Federal enforcement program in Colorado and  Wyoming, Region VIII specifically
targeted pesticide-producing establishments potentially subject to the WPS, including bulk repackagers and
users of aluminum phosphide type pesticides for prairie dog control.   Both  initiatives documented
compliance issues (i.e., bulk repackagers are not complying with worker protection relabeling requirements
and users of aluminum phosphide type pesticides continue to violate endangered species labeling).

        Region X participated in industry-specific initiatives in FY 94.  One Region X air program
initiative involved rock crushing operations subject to Federal NSPS under the CAA. Region X conducted
an intensive training effort to inform the regulated community about the Federal requirements, including
giving operators copies of the checklists used  by  compliance  inspectors, to help facilities voluntarily
comply. Region X conducted several  inspections in northern Idaho, met with concerned citizens, and
assisted the State of Idaho in its enforcement against several facilities that were out of compliance.  In
addition, Region X reviewed more than  100 pest  control advertisements that allegedly made false  or
misleading safety claims. A citizen's group submitted the advertisements  to EPA for review.  As a result
of the review, the region issued 25 warning letters for clear violations of FIFRA and 16 letters advising
companies  to make changes  to their advertisements for less obvious  violations.
                                              3-8

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       Region X also funded an  initiative  by the Idaho Department of Agriculture to conduct a
compliance audit of every commercial and public pesticide applicator in the State during a 2-year period.
The  State inspector uses a checklist during the site visit to evaluate recordkeeping,  pesticide  use,
mixing/loading, storage, and disposal.  The inspector signs the checklist, which serves as a warning letter
if violations were noted, and the applicator is given time to make corrections.  The initiative gives the
department a chance to make contact with every applicator. More than 400 audits were conducted in FY
94, and the program has been well received in the State.
                                                   Under two separate initiatives aimed at public water
                                                   systems, Region III issued 209 NOVs to systems
                                                   that failed to comply with sampling and reporting
                                                   requirements of the Lead and Copper Rule, SDWA,
                                                   and 226 NOVs to systems that failed to comply with
                                                   sampling and reporting requirements  for nitrate
                                                   under the Phase II Rule, SDWA.
       Several   regional   industry-specific
enforcement actions also  took place  in FY 94.
Region II initiated industry-specific enforcement
activities under the  CAA.  The Region  issued
administrative  penalty  complaints against the
owners of six boating supply stores for violating
the ban on the  sale of "non-essential" products
containing CFCs. The region issued these penalty
actions after inspections of the stores  revealed that each store was selling CFC-based propellants for
marine safety horns.  Region II also initiated the first administrative penalty actions to secure compliance
with the  Sewage Sludge Use/Disposal Regulations (Part 503 Regulations)  recently promulgated under
Section 405 of the Clean Water Act.  In August 1994, the Region  filed five administrative complaints
against municipal wastewater treatment works under Section 309(g) of the CWA.

       Region IV s RCRA program continued to lead the Nation  in providing cases  for the National
Combustion Initiative. Region IV and its States had 12 of the 22 cases settled and 2 of the 10 new actions
announced under this national initiative.  Special emphasis was also given to the CFC initiative in the
region. Region IV announced the filing of nine administrative enforcement actions seeking $256,989 in
penalties for violations of Sections 608 and 609 of the CAA.  The cases involving Section 608 allege
violations of disposal regulations for appliances containing refrigerant capable of damaging the ozone layer
and/or violations of prohibitions of venting refrigerant directly into the atmosphere. The cases involving
Section 609  allege failure  to have certified equipment  and technicians servicing  motor vehicle air
conditioners.

       During FY 94, Region VII issued  26 administrative complaints for violations of Section 609(c)
of the CAA. Respondents were charged with servicing or repairing motor vehicle air conditioners without
proper training and certification by an approved technician certification program and/or without proper
use of approved equipment. The complaints addressed violators in each of the States located in Region
VII and  the proposed penalties totaled $170,000.  Eleven of the 28 FIFRA administrative  complaints
issued by Region VII in FY 94 involved cross-contamination of bulk repackaged pesticides. These cases,
which are highly complex and controversial and have no precedent, have consumed a significant amount
of regional resources to develop and litigate. They have also focused national attention on the regulated
community and the Agency on pesticide product cross-contamination and have encouraged coordination
among the members of the regulated community, States, and the  Agency to try and resolve the difficult
regulatory and potential risk and food safety issues posed by cross-contamination of pesticides.

3.4    SUPPLEMENTAL ENVIRONMENTAL PROJECTS

       EPA uses SEPs to gain significant environmental benefits in conjunction with  the settlement of
enforcement cases.  Nominally, SEPs are  projects voluntarily undertaken by members of the regulated
community in conjunction with case settlements to provide some level of environmental benefit usually
                                               3-9

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 unrelated to the nature of the violations committed.  In exchange for SEP performance, the facility is
 granted penalty relief equaling some fraction of the total value of the stipulated penalty.  Historically
 applied predominantly in reporting violation cases, SEPs  are maturing into a more versatile tool, with
 SEPs now included in  CAA, CWA, RCRA, and other program area settlements.

        In FY 94, EPA-New England negotiated 21 SEPs  worth approximately $7.3 million.  Region II
 included SEPs in 28 settlements under the CAA, EPCRA, TSCA, RCRA, and CWA programs with a total
 dollar value of more than $18.5 million. In most cases, the value of these SEPs substantially exceeded
 the value of the civil penalties that they were used to  offset; overall, penalty offsets totaled less than $4
 million.  Region IH negotiated  10 SEPs, at a total dollar value of approximately $10.2 million.  Region
 VII incorporated SEPs  into settlements at a value of more than $7 million. Region V also settled several
 cases using SEPs with  a total value of the SEPs  being approximately $5.4 million. Thirteen SEPs were
 worth more than $100,000.  Region X negotiated 25 SEPs in FY 94.  The dollar value of the. SEPs was
 nearly $1.3 million.  Of the 25  SEPs,  20 were in  the pollution reduction and pollution prevention
 categories.

        In FY 94, SEPs included diverse projects  such as resource commitments to local emergency
 planning councils, an air toxics reduction technology demonstration  study, source reduction and pollution
 reduction programs and process changes,  energy conservation, land reclamation, and recycling. Pollution
 prevention projects received  particular attention,  in keeping with current regional and national priorities.
 Table 3-1 lists some of the types of projects included  as SEPs in case settlements.

       Some of the SEPs incorporated into settlements  require substantial process modifications  at
 manufacturing facilities resulting in significant source reduction gains benefitting the environment. Region
 III  executed  a  CACO, with  an associated  Settlement  Conditions  Document, settling  an  EPCRA
 administrative action filed against the Homer Laughlin China Company for violations of EPCRA Section
 313.  The settlement included a substantial SEP, exceeding $9 million, in which Laughlin converted its
 entire china dinner-ware production system to a  lead free process.

       A consent decree filed in settlement of claims against I.E. DuPont de Nemours for violations of
 its NPDES permit and  Section  301 of the CWA contained a pollution prevention SEP.  This SEP will
 prevent the generation of between 60 million and 145 million pounds of RCRA hazardous waste per year
 currently being deep well injected in onsite disposal wells. The information on the violations was received
 from self-reporting and from an EPA inspection.  Under the consent decree, DuPont agreed to pay a civil
penalty of $516,430 and to perform a SEP costing an  estimated $3.2 million.

       The process modifications required in some SEPs may also involve the application of developing
innovative technologies, thereby serving a valuable technology demonstration function  with possible
attendant environmental benefits at future sites. For example, Region IV filed a CACO against Everwood
Treatment Company, Inc., resolving Everwood's  violations of Section 103 of CERCLA and  Section 304
of EPCRA. The CACO settled this action for $54,500 and required the respondent to pay $32,000.  In
addition, the CACO calls for Everwood to implement a SEP to construct a new wood treatment plant built
specifically for the use of a wood  preservative that is not a hazardous  waste.  This  SEP will cost
approximately $225,000. If successful, Everwood's SEP could set a precedent for other wood  treaters and,
thus encourage the reduction in one the Nation's most toxic hazardous wastes.
                                             3-10

-------
                                                                                  s •
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I^
    Table 3-1.  Types of Supplemental Environmental Projects in Case Settlements
SEP Category
Cleanup/Restoration Projects
Disposal
Environmental Audit
Outreach/Enforcement-Related Environmental
Public Awareness Projects
Source Reduction/Pollution Prevention —
Process Modification
Source Reduction/Pollution Prevention —
Technological Improvement
Training
Waste Minimization/Pollution Reduction—
Process Modification
Waste Minimization/Pollution Reduction —
Recycling
Waste Minimization/Pollution Reduction —
Technological Improvement
Example of Project Type Included in FY 1994 SEP
• UST removal
• Abandoned oil production well plugging and site restoration
• Abandoned mine land reclamation (partial)
• PCB testing and removal
• Asbestos abatement
• Facility environmental and chemical usage audits
• Resource commitments (e.g., computers, other equipment,
personnel) to LEPCs
• Solvent substitution and other toxics reduction through product
substitution
Installation of alternative cooling system to reduce fresh water
withdrawals
Compliance awareness publications in trade journals
Training for LEPCs
• Installation of high-efficiency lighting
Wastewater treatment facility improvements
Utilization of wastewater treatment sludge as fertilizer
• Improved scrubber performance for air toxics reduction
• Demonstration project for air toxics reduction
                                             In  Region IV,  the U.S.  District Court entered  a
                                             consent decree that settled Crown, Cork & Seal
                                             Inc.'s  (CC&S)  alleged violations  of the CAA's
                                             prevention  of  significant deterioration  (PSD)
                                             requirements and NSPS.  The CACO had a civil
                                             penalty of $343,000 and required CC&S to perform
                                             three SEPs valued at more than $2 million. The
                                             penalty  represents  one  of  the  largest  CAA
       Several FY 94 SEPs required violators to
perform environmental projects at locations other
than where  violations occurred.   This approach
directed  effort  toward  achieving  a  greater
environmental benefit than may otherwise have
been  practicable.  In one such case,.the U.S.'
District Court entered a  consent decree resolving
a suit brought by EPA and the State of Arizona
against Magma Copper  Company in response to
violations of the CWA and related State law at three copper mining and processing facilities operated in
southeastern Arizona. The decree requires Magma to pay penalties of $385,000 to the United States and
$240,000 to the State of Arizona.  The decree also requires Magma to undertake compliance measures and
to complete a SEP designed to control contamination at  an  abandoned mine.  The cost to Magma is
estimated to be $1.5 million. In addition, the decree further requires Magma to pay $50,000 to fund three
additional SEPs that  the U.S. Forest Service will complete to benefit the affected watersheds.

       In another multisite SEP, Region  III and Anzon, Inc., a manufacturer of lead products, settled a
TSCA administrative complaint involving violations of the Inventory Update Rule (IUR) requirements of
the TSCA.  Anzon failed to submit IUR reports  on four chemicals manufactured at its Philadelphia,
Pennsylvania, plant.  Anzon agreed to pay a $57,000 civil penalty, $43,620 of which may be remitted by
EPA upon completion of SEPs in Anzon's Philadelphia and Laredo, Texas, facilities. The Philadelphia
project involves the early  removal and disposal  of four PCB transformers. The Laredo project requires
increased controls for the  capture of antimony oxide emissions from the facility. These projects have a
combined estimated  cost of $198,800.  The Laredo project represents a TSCA settlement in Region III
with an "inter-regional"  SEP.
                                         3-11

-------
             1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        In Region V, two noteworthy SEPs were negotiated in FY 94.  In the first, Ohio Power agreed
 to remove 600 PCS capacitors at a cost of $61,547. The second SEP, for EPCRA Section 313 violations,
 requires Welded Tube in Chicago, Illinois, to replace its solvent paint with water-based paint to reduce
 the release of toluene and xylene by 298,610 pounds per year. The SEP is estimated at $300,000.

 3.5     SENSITIVE ECOSYSTEMS

        Unlike other initiative areas discussed in this  document, consideration of sensitive ecosystems in
 regional enforcement  activities does not  relate  to  discrete  program activities.   Whereas SEPs and
 multimedia activities relate to the specific category of enforcement activity conducted, and industry-
 specific or Federal facility initiatives relate to identifiable  sub-populations of the  regulated community,
 sensitive ecosystem activities can include a wide range of enforcement or compliance assurance tactics
 and can be aimed at any specific or mixed population of the regulated community.  As shown in Section
 3.2, several environmental justice initiatives could also be categorized as sensitive ecosystem or sensitive
 environment initiatives.  This section presents regional efforts to protect identified sensitive ecosystems
 and environments, other than those with environmental justice concerns.

        During  FY 94,  a  number of regions  conducted  geographic initiatives  targeting identifiable
 ecosystems.  Region II, for example,  brought a case against Broomer Research, Inc., which is located in
 a mixed industrial and residential area of Islip,  Long Island, New York, and is situated directly over a
 ground water aquifer, a source of drinking water for the community. The plant manufactures optical
 lenses and uses  thorium fluoride and organic solvents in the coating and cleaning  process.  The  Suffolk
 County Department of Health (SCDOH) identified organic  solvents in the wastewater sludges generated
 and then discharged by Broomer into  its sanitary septic system. EPA, SCDOH, the U.S. Attorney for the
 Eastern District of New York, and several other Department of Defense offices executed a search  warrant
 to inspect this facility.  Samples taken during this inspection contained appreciable amounts of  organic
 solvents in the wastewater and appreciable levels of radionuclides, assumed to be thorium, in the sludge
 discharged to the septic system.  On June 24, 1994, Region II issued an administrative order on  consent
 to Broomer Research, Inc. under the "emergency" authorities of Section 7003 of RCRA and Section 1431
 of SDWA.  This is the first time the Region has used  its  emergency authority under Section 1431 of
 SDWA.

        The Mid-Snake River area (near Twin Falls, Idaho) has and continues  to be a high-priority
 watershed for Region X.  The region conducted a workshop  in Boise, Idaho, for State and EPA inspectors
 in preparation for the upcoming inspections of feedlots and dairies in the Twin Falls and Boise areas.  The
 workshop covered items to look for at these operations and information required for the inspection reports.
 Region X and the State inspected 74 facilities, several of which were identified as having violated the
 CWA.  EPA is preparing these cases  for formal enforcement actions. The inspections also identified 24
 facilities with potential  problems.  These  facilities were  sent letters notifying them of the  potential
problems.

        Another example of ecosystem protection is Region V's new effort to protect  the ecosystem of
the Mississippi River basin.  In addition to its  Cleveland office, the region's Criminal Investigation
Division has recently announced the opening of new offices in Minneapolis and Detroit. These offices
ensure that a  local workforce is available to investigate and support prosecutions in these areas.  Region
V has also taken steps to protect other sensitive  ecosystems in the region,  including:

        •   21 SEPs negotiated in the Great Lakes Basin  of Region V in hopes of providing added
           protection for that sensitive environment
                                             3-12

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT f
        •   6 SEPs negotiated in the geographic region of the SEMI Initiative

        •   SEPs in other geographic initiatives as well, including 2 under the Gateway Initiative.

3.6     FEDERAL FACILITIES

        In FY 94, the regions continued to focus their enforcement and compliance assistance activities
on Federal facilities.  Using the Federal Facilities Compliance Act as its basis, Regional enforcement
personnel continued to target, inspect, and take enforcement actions against Federal facilities. In several
of the activities, the region and the applicable State worked closely to ensure that the action taken would
benefit  both public health  and the environment. EPA-New England initiated a specific compliance
assistance program in FY 94 — the Multimedia Federal Facility Program environmental management review
(EMR) effort.  The purpose of conducting an EMR is to review a Federal facility's overall environmental
management program (structure, staffing, training program) and assist the facility with compliance issues.
After an EMR is conducted, a brief report is prepared and provided to the facility.  In FY 94, two EMRs
were conducted, and six are planned for FY 95.

        Several regions also conducted compliance monitoring activities at Federal facilities. During FY
94, for  example, Region III  continued  its  vigorous oversight of environmental regulations/statutes  at
Federal  facilities. This included multimedia inspections at Ft. Belvoir, Maryland, and the Naval  Surface
Warfare Center at  Indian  Head, Maryland.   Regions  n  and IV  also  targeted  Federal  facilities for
multimedia inspections.  Region II conducted three Federal  facility multimedia inspections in  FY 94;
Region  IV conducted seven Federal facility multimedia inspections.

        While the majority of such actions  are typically taken against military  installations (i.e., Army
bases, Navy bases), some are taken against other types of Federal  facilities.  For example, Region HI
issued an emergency administrative order under Section 1431 of the SDWA to the District of Columbia.
The Government of the District of Columbia owns and operates a public water system for the storage and
distribution of piped water for human consumption to  the residents ,of the District and surrounding areas.
The Army  Corps of Engineers,  Baltimore  District, provides the water.   In late  1993, water samples
collected by the District and analyzed were total coliform positive, a violation of the Total Coliform Rule.
One repeat sample was fecal coliform positive, an acute violation that may pose a risk to human health.
The District issued a boil water advisory to the people in the vicinity of the fecal coliform positive sample
location, issued public notice  of the violations, and increased its distribution system flushing program.

        In response  to the imminent  and substantial  endangerment  created  by the unusually high
percentage of total coliform-pbsitive samples within the District of Columbia' s public water system, EPA
Region  III issued an Emergency  Administrative Order to the U.S. Army Corps of Engineers, Baltimore
District, to determine whether the Corps  contributed to or could  have helped prevent the  District's
violation.  EPA staff from Region III, Headquarters, and Cincinnati, inspected the treatment plants and
made recommendations for further action by the Corps of Engineers.

        Before the Corps had the opportunity  to implement EPA's recommendations, an exceedance  of
the turbidity maximum contaminant level (MCL) occurred at the Dalecarlia water treatment plant.   In
response to this turbidity MCL exceedance, EPA issued a boil water notice to all users of the distribution
system in Falls Church and Arlington, Virginia, as well as  in the District. EPA established a command
center and hotline in the offices  of the Metropolitan Washington Council of Governments and directed
the Corps to conduct extensive  water  quality monitoring.  Testing was negative, and the boil water
advisory was lifted. Following inspections of the Dalecarlia plant by EPA Headquarters, Cincinnati, and
                                              3-13

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
regional personnel and a subsequent investigation by EPA's NEIC, Region HI issued an Emergency Order
to the Corps that incorporated the recommendations from the inspections.  In addition, the order
incorporated the recommendations from EPA's previous investigation of the coliform problem. EPA
subsequently  participated  hi two congressional hearings on the matter  conducted by  the District's
Representative to Congress.
94:
       EPA and the States initiated the following enforcement actions against military installations in FY
           Naval Construction Battalion Center (NCBC):  EPA-New England reached a precedent-
           setting settlement with the Navy under RCRA. The Navy agreed to pay a penalty of $57,223
           for RCRA violations at the Naval Construction Battalion Center in Davisville, Rhode Island.
           The penalty was the first RCRA penalty collected by the region against a Federal facility and
           the first collected nationally from the Navy under the Federal Facility Compliance Act of
           1992. The action resulted from  a multimedia inspection of the facility conducted by EPA-
           New England with State participation.   The complaint alleged numerous hazardous waste
           management and disposal  violations by the Navy.

           Natick Army Laboratory:  EPA-New England issued  its first complaint against the Army
           pursuant to EPA's authority under the Federal Facility  Compliance Act of 1992.  Based on
           an inspection at the Natick facility, the region proposed a  civil penalty of $117,000.  The
           respondent violated a variety  of RCRA base program requirements, including failure  to
           properly conduct hazardous waste determinations, failure to clearly label and mark satellite
           accumulation containers, failure to keep containers of hazardous waste closed during storage,
           and failure to label properly containers stored at the less than 90 day  storage area.

           West Virginia Ordnance  Works:  A dispute with the U.S. Army resulted in payment  of
           stipulated penalties to Region III in the amount of $500,000 for violations occurring at the
           West Virginia Ordnance Works  Superfund  Site.  EPA assessed  stipulated penalties in the
           amount of $2 million for the  Army's failure to submit documents  within the  established
           deadlines of the second IAG.  The Army invoked the dispute resolution provisions of the
           lAGs; the disputes were eventually elevated to the Senior Executive Committee, which settled
           on a  $500,000 penalty with requirements to implement an improved  reporting and tracking
           system.

           RCRA-Aberdeen Proving Ground Facility:  EPA Region HI issued a RCRA Section 3008(a)
           administrative complaint to the  U.S. Army Aberdeen Proving Ground (APG) facility  in
           Aberdeen, Maryland, citing APG for storing for more than 1 year 171 containers of hazardous
           waste restricted from  land disposal.  The complaint also  cited APG for manifest violations
           concerning the shipment  of land disposal  restricted hazardous  waste.   The penalty was
           $115,546.  This administrative complaint was the first issued by Region III to a Federal
           facility pursuant to the newly enacted Federal Facility  Compliance Act.  In addition to this
           RCRA action, the SDWA-UIC program is undertaking  an inventory and remediation action
           at Aberdeen in response to the identification of numerous injection wells at the facility.

           In the Matter of U.S. Naval Air Facility, El Centra, California: Region IX signed a CACO
           resolving an administrative complaint  against the U.S.  Naval Air Facility  in  El Centro,
           California, involving various RCRA violations. Under the terms of the settlement, the Navy
           will pay a penalty of $100,000 and will implement two SEPs relating to pollution prevention.
                                             3-14

-------
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I rw^}
                                                                                 V
     The first SEP involves the installation of six jet parts washers that will use high-velocity water
     and biodegradable detergent in lieu of the solvents currently used  to achieve a 90-percent
     reduction in the volume of hazardous wastes used in degreasing  operations. The second SEP
     involves the construction of a hazardous waste minimization center, which will achieve a 25-
     percent reduction in hazardous waste generation through centralized ordering and distribution
     of hazardous  materials.  The total cost of the two supplemental environmental projects is
     approximately $250,000.

     The case is significant because it was Region IX' s first enforcement action under the Federal
     Facility Compliance Act of  1992. In addition, the consent agreement is significant because,
     for the first time in an agreement with a Federal facility, EPA was able to limit the dispute
     resolution process to the regional level. Any disputes under this consent agreement will not
     go beyond the Deputy Director of Region IX' s Hazardous Waste Management Division.
                                       3-15

-------

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
   4.0  ENVIRONMENTAL ENFORCEMENT ACTIVITIES AND PENALTIES
        The U.S. Environmental Protection Agency's (EPA's) mandate to protect public health and safety
depends on effective enforcement. The costs of violating environmental laws, both direct litigation costs,
as well as costs resulting from remediation and the assessment of civil penalties or criminal fines and
incarceration, are great. Strong, deterrence-based enforcement—as reflected, for example, in the rapid
growth of EPA's criminal enforcement program—creates a climate that forcefully motivates innovation,
prevention, and compliance by the regulated community.

        EPA's  enforcement and  compliance assurance program operates at  its  peak  when  strong
enforcement is used in tandem with the compliance assistance programs.  The tools and methods are
familiar:

        •   Criminal sanctions

        •   Administrative actions/injunctive relief that force violators to correct their violations

        •   Civil/Judicial referrals

        •   Monetary  penalties that are  designed to punish violators and assure the  recovery of the
           economic benefit of noncompliance.

        These tools, used in conjunction with the compliance assurance activities identified and discussed
throughout this document, will continue to play a pivotal role in increasing compliance with environmental
laws and regulations, and thus protecting human health and the environment.

        During FY 94, the Agency brought a record 2,246 enforcement actions with sanctions, surpassing
the previous mark established in FY 93.  This record includes 220 criminal cases, 1,596 administrative
penalty actions, 403 new civil referrals to the Department of Justice, and 27 additional  civil referrals to
enforce existing consent decrees.  These  administrative, judicial, and criminal sanctions are the primary
enforcement tools  used to correct violations,  establish deterrence,  and create incentives for  future
compliance.

        The FY 94 figures also indicate that the States were active in their enforcement efforts against
noncomplying entities. These figures indicate that States took  11,334 enforcement actions. The States
take the majority of environmental enforcement  actions and are primary partners with EPA in assuring
national compliance with the environmental laws and regulations.

        Penalties for FY 94 totaled a record $151 million combined for civil penalties and criminal fines
and another $206 million was returned to the Treasury through Superfund cost recovery. Figure 4-1
presents the FY 94 penalty totals compared to the totals for the last 5 years.

        The Agency's Federal Facilities Enforcement Office (FFEO)  greatly expanded the scope of its
activities.  In October 1992, Congress, through the Federal Facility Compliance Act (FFCA), clarified that
EPA has RCRA order and penalty authority against Federal agencies.  Since passage of the FFCA, EPA
has issued 20 compliance orders to Federal agencies.  In FY 94, it issued 10 RCRA administrative penalty
orders  to military facilities  with proposed penalties exceeding $5.7 million.  In addition, the program
negotiated 5 federal facility compliance  agreements and  2 CERCLA cleanup agreements.  OFFE also
                                              4-1

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                     Figure 4-1. EPA Civil Penalties and Criminal Fines
               $22 Exxon
               ValdezFine
continued to implement its Federal Facilities Multimedia Enforcement/Compliance Initiative by taking
follow-up enforcement actions after conducting 41 multimedia investigations at federal facilities across
the country in FY 93.

       The following sections discuss some of the specific environmental enforcement activities, including
criminal enforcement, administrative  enforcement, referrals, and CERCLA enforcement. There is also a
general discussion of penalties. This section concludes with several tables that contain regional-specific
information pertaining to environmental enforcement activities and penalties.

4.1    CRIMINAL ENFORCEMENT

       EPA's criminal enforcement program set new records in several categories, including 220 referrals
to the Department of Justice (36 percent more than the record of 140 set in FY 93), criminal charges
brought against 250 individual and corporate defendants (40 percent more than the record of 161 set in
FY 93), and 99 years worth of jail sentences imposed (25 percent  more than the 74.3 years  of
incarceration imposed in FY 93). The program also assessed $36.8 million in criminal fines (19 percent
more than the $29.7 million assessed in FY 93).  Figure 4-2 provides a statistical comparison of criminal
enforcement activities over the last 5 years.

       The Pollution Prosecution Act (PPA) of 1990 authorized a number of enhancements to EPA's
enforcement program. Most significantly, the Act mandated an increase in criminal investigators to 200
by FY 96.  In addition, the PPA required "increasing numbers of additional support staff (i.e., technical,
legal, and  administrative) to the Office of Criminal  Enforcement."  By the end of FY 94, EPA had
increased the number of criminal agents to 123 compared to 47 in FY 89. As shown in Figure 4-1, this
                                             4-2

-------
FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
1
•MK


•B
O
CM
O
 \O tr>

                                                        §  10  O •* TT
                                                        a
                                                            §3; o T-I  o
                                                            o in ^o  in
                                                         T-I  i—< i—< rH  C O
                                                              ^ s
                                                                   •^  V)
                                                         O  rH P<  tf) Tf

                                                         S  S 21  S1 ^
                                                         Q^  o> vs  ^ 9\
                                                                fa  t£
                                                                            a
                                                                              o
                                                                              O
                                                                              I
                                                                              *
                                                                           *  *
                                     4-3

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
additional investment in agents has yielded significant increases in most key areas of the criminal program
including 525 new investigations in FY 94.

       As  mentioned,  OCE  referred 220 criminal cases to  DOJ in FY  94 and opened 525 new
investigations.  Table 4-1 presents information on  the number of referrals and new investigations by
statute.
            Table 4-1.  Number of New Investigations Opened and Referrals to DOJ
                      by EPA's Criminal Enforcement Program in FY 94
Statute/Program Area
Clean Air Act
Clean Water Act
Wetlands
Safe Drinking Water Act
RCRA
CERCLA
TSCA
FIFRA
Other
Total
New Investigations Opened
89
174
14
7
173
21
11
22
14
525
Referrals to DOJ
39
66
3
2
74
12
6
15
3
220
        Also contributing to the increase in criminal enforcement activity is a document issued by OCE—
 "Guidance on the Exercise of Investigative Discretion."  This guidance was the first comprehensive
 guidance issued by EPA that established discrete criteria for Agency investigators  when considering
 whether or not to proceed with a criminal investigation.   The guidance was  designed to promote
 consistent, but flexible application of the criminal environmental statutes.

 4.2     CIVIL ENFORCEMENT

        In  FY  94, the Agency took  nearly 3,600 administrative enforcement actions.   This number
 emphasizes the importance EPA is  placing on administrative enforcement mechanisms to address
 violations, compel regulated facilities to achieve compliance, and assess penalties.  EPA's expanded
 authority with administrative actions now allows the Agency to impose injunctive relief and penalties that
 are comparable to those that could be imposed through civil judicial enforcement.  In FY 94, EPA issued
 1,596 administrative penalty orders for  more than  $48 million.  Table 4-2 provides information on
 administrative penalty orders by statute/program area.
                                             4-4

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I
               Table 4-2.  Administrative Penalty Orders by Statute/Program Area
Statute/Program
Clean Air Act
Clean Water Act
Safe Drinking Water Act
RCRA
UST
TSCA
EPCRA
FIFRA
CERCLA
Total
No. of Cases
171
272
70
103
102
288
242
150
35
1,433'
Penalties
(in dollars)
3,882,550
5,154,892
393,402
9,824,031
3,760,190
14,236,483
8,266,020
1,779,448
723,925
48,021,941'
           1    These  numbers do not include the 163  administrative penalty actions  taken  by EPA
               Headquarters under the Clean Air Act. Penalty amounts were not available at the time of
               publication.
       In addition to the administrative penalty orders, EPA issued a total of 166 civil judicial penalties
totalling more than $65 million. Table 4-3 presents a breakout of those penalties by statute/program area.

       Figures 4-3 through 4-6 on the following pages are graphical representations of the administrative
and civil judicial statistics.
                  Table 4-3.  Civil Judicial Penalties by Statute/Program Area
Statute/Program
Clean Air Act
Clean Water Act
Safe Drinking Water Act
RCRA
TSCA
EPCRA
FIFRA
CERCLA
Multimedia
Total
No. of Cases
67
51
2
24
2
0
1
17
2
166
Penalties
(in dollars)
13,490,486
20,006,225
20,000
12,342,760
1,121,100
0
500
4,999,859
13,655,000
65,635,930
                                               4-5

-------
FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Figure 4-3.  Number of Administrative Penalty Orders by Statute/Program Area
                 300
                 250
                 200
                 ISO
                 100
                 50
                              272
                                                        242
                        Clean Air Clean   Safe  RCRA   UST   TSCA EPCRA  FIFRA CERCLA
                          Act   Water  Drinking
                               Act  Water Act
     Figure 4-4.  Total Penalties Assessed in Administrative Penalty Orders
                           (by Statute/Program Area)
              $15,000,000
              $12,000.000
               $9.000.000
           •1
               $6.000.000
               $3,000,000
                   $0
                           Clean  Clean  Safe   RCRA   UST  TSCA  EPCRA FIFRA CERCLA
                           Air Act  Water Drinking
                                 Act Water Act
                                        4-6

-------
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT j
        Figure 4-5.  Number of Civil Judicial Penalties by Statute/Program Area
                        80
                        70
                        60
                        50
                        30
                        20
                                 Clean   Clean   Safe   RCRA  TSCA  EPCRA  FffRA CERCLA Multimedia
                                 Air Act  Water  Drinking
                                        Act  Water Act
    Figure 4-6.  Total Amount of Civil Judicial Penalties (by Statute/Program Area)
   $24,000,000 -

   $22,500,000 -

   $21,000,000 -

   $19,500,000 -

   $18,000,000 -

   $16,500,000 -

| $15,000,000 -

•§ $13.500,000 -
.3.
g $12,000,000

1| $10,500,000

^*  $9,000,000

    $7,500,000

    $6,000,000

    $4,500,000

    $3,000,000

    $1,500,000

         $0
                                     $20,006,225
                               $13.490,486
                                                                             $13,655,000
                                  Clean  Clean   Safe   RCRA  TSCA  EPCRA  FIFRA  CERCLA Multimedia
                                  Air   Water Drinking
                                  Act    Act  Water Act
                                                4-7

-------
         FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
        Several regions reported information on injunctive relief.  In Region II, for example, there was
 approximately $350 million in non-CERCLA injunctive relief (largely driven by the Kodak settlement)
 and approximately $112 million in CERCLA injunctive relief.   In Region III, preliminary estimates
 indicate an injunctive relief/cost recovery total of nearly $412 million. The large dollar value reported
 is  largely  attributable  to the region's Superfund  Enforcement Program, especially  the  Removal
 Enforcement Program, which had a $267 million multi-regional settlement in FY 94. In Region V, there
 were 63 injunctive relief cases. The value of the injunctive relief in FY 94 was $141 million. However,
 there are still several cases pending that could change this number.  Region VIII reported five cases with
 injunctive relief.

 4.3     CIVIL REFERRALS

        The 430 civil referrals brought in FY 94 by the regions and the regulatory enforcement office—
 both  new and to enforce  existing consent decrees—are the highest 1-year total in EPA's history.  In
 addition to the 403 civil referrals, the Agency also referred 27 cases to DOJ to enforce existing consent
 decrees. Table 4-4 presents information on the statute/program area of the 430 FY 94 civil referrals.
                        Table 4-4. Number of Civil Referrals by Statute
Statute
Clean Air Act
Clean Water Act
Safe Drinking Water Act
RCRA
TSCA
EPCRA
FIFRA
CERCLA
Total
Number of Civil Referrals
139
86
11
35
6
6
1
144
428'
                          This number does not include 2 civil referrals made by EPA Headquarters.
4.4    CERCLA ENFORCEMENT

       The Superfund  program secured more than $1.4 billion in private  party remedial cleanup
commitments in FY 94.  This was the fifth consecutive year in which private party cleanup commitments
exceeded $1 billion, bringing the total value of private party cleanups to $10 billion since the program's
inception.  Potentially Responsible Parties (PRPs) conducted  approximately 80 percent of the remedial
work at National Priority List sites during FY 94, the largest percentage to date.

       Of this total amount, approximately $959 million was for remedial design and remedial action
(RD/RA) response work. The three types of RD/RA settlements and their associated values were:
                                              4-8

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       •   35 consent decrees referred to the Department of Justice (DOJ) for cleanup response estimated
           at $585 million

       •   35 unilateral administrative orders (UAOs) issued to PRPs and with which they have agreed
           to comply, for response worth over $295 million

       •   18 administrative orders on consent (AOCs) for remedial design estimated at close to $79
           million.

       The Superfund program also concluded "de minimis" settlements with over 4,000 PRPs, by far
the most negotiated in any single year since the inception of the program.  The Superfund enforcement
program has expanded the use of these settlements to make negotiations more efficient and to reduce the
transaction costs to parties that had been only minor contributors of wastes to superfund sites.

       In FY 94 the Agency issued a total of 110 unilateral administrative orders (versus 126 in FY-93),
and signed 154 administrative orders on consent (versus 108 in FY-93)  with PRPs. The Agency addressed
186 past costs cases, including statute of limitations cases, for amounts greater than or equal to $200,000.
Of these actions:

       •   42 were cases  referred to  DOJ for cost recovery

       •   34 were administrative settlements

       •   74 were decision documents in which EPA formally decided not to pursue any further cost
           recovery actions.

       The program achieved total cost recovery settlements  worth over $205 million (compared to $199
million achieved in FY 93).

       In FY 94 approximately 75 percent of the total RD/RA starts at non-federal facility sites were
initiated by PRPs. In FY 93, the percentage of PRP initiated RD starts  was 65 percent, and the percentage
of PRP initiated RA starts was 79 percent.

       Since the inception of the Superfund Program in 1980, PRPs have committed to response actions
estimated at over $10 billion, and the program has achieved cost recovery settlements for over $1.4 billion.

4.4.1   Alternative Dispute Resolution

       During  FY 94, the Office of Enforcement and Compliance Assurance and the Regional Offices
of Regional Counsel made substantial  progress toward the  Agency's  stated  goals  of making  the
consideration and appropriate use of alternative dispute resolution (ADR) mechanisms standard operating
procedure for all enforcement actions and implementing the  Administrative  Dispute Resolution Act and
Executive Order on Civil  Justice Reform. Significant strides were made in every aspect of the ADR
Program including case use of ADR, case support systems, training and internal  ADR  services, and
outreach to the regulated community.

       The use of ADR mechanisms to assist resolution of enforcement negotiations were initiated by
Regional offices in  13 civil  actions during FY 94.  These results substantially surpassed the figures for
FY 1993.  In addition, at  29 sites regional offices supported PRP  allocation settlement efforts through
                                              4-9

-------
       I FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
encouraging and providing ADR services in coordination with OSRE.  Regional support for the use of
ADR grew substantially, with all regional offices using or supporting PRP use of ADR to assist settlement
efforts. FY 94 also heralded an increased awareness of ADR as a tool for increasing the efficiency of
resolution of future disputes, with mediation included in the dispute  resolution provisions of several
judicial and administrative settlement documents.

        The scope of ADR use also expanded during FY 94, with the first significant uses of ADR beyond
traditional Superfund cost recovery and RD/RA cases.  For the first time in actions of this magnitude,
Region n and Region IH utilized ADR professionals to obtain agreement on major de minimis settlements
involving over 1,000 parties.  In addition, a pilot in the use of arbitration to resolve Superfund cost
recovery cases, conducted with the assistance of private arbitration experts, resulted in the drafting of
proposed case selection criteria and hearing procedures.

4.5     EPA CONTRACTOR LISTING

        In June of 1994,  the responsibility for administering the contractor listing program shifted from
OECA to the Office of  Administration and Resources Management.  Prior to the reorganization,  18
facilities were added to EPA's List of Violating Facilities (List) under the authorities provided to EPA by
the Clean Air Act (CAA) Section 306 and Clean Water Act (CWA) Section 508.  Under these sections
of the CAA and CWA, Federal agencies are prohibited by statutory mandate from entering into contracts,
grants, or loans (including subcontracts, subgrants, or subloans)  to be performed at facilities owned or
operated by persons who are convicted of violating air standards under CAA 113(c) or water standards
under CWA 309(c), effective automatically on the date of the conviction.  Facilities that are mandatorily
listed remain on the List until EPA determines they have corrected the conditions that resulted  in the
violations.  As of June 1994, 133 total  facilities were on the List.  Eighteen of these were added  in FY
94.  Seven facilities were removed from the List in FY 94 and an additional  13 removal requests were
pending.
                                              4-10

-------
     I FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                 TABLE OF CONTENTS
REGION I  	•	,	A-l
       CLEAN AIR ACT			-	A-l
          U.S. v. D'Addario Industries, Inc., et al. (D. Conn.)	• •  A-l
          In re Syncor International Corporation	A-l
       CLEAN WATER ACT	 .  A-l
          U.S. v. L.S. Starrett Company (D. Mass.)		A-l
       RCRA	A-l
          Allegro Microsystems, Inc	• • • •.....;....  A-l
          In re Massachusetts Highway Department 	A-l
          U.S. v. Hanlin Group, Inc. (D. Maine)	-	  A-l
          In re Hamilton-Standard	A-2
          In re Upjohn Company	A-2
       TSCA	A'2
          U.S. v. New Waterbury, Ltd. (D. Conn.)	A-2
          In re City of Boston, Boston City Hospital	A-2
       EPCRA	A-2
          In re Wyman-Gordon, Inc	A-2
       CERCLA	A-3
          U.S. v. O.K. Tool Company, et al. (D. N.H.)	A-3
          U.S. v. Conductron Corporation,  et al.  (D. N.H.)  	A-3
          U.S. v.  William Davis, et al. (D. R.I.)  	A-3
          U.S. v. DiBiase Salem Realty Trust, et al. (D. Mass.)	A-3

 REGION II	A-4
       CLEAN AIR ACT	A-4
          In re Ronzoni Foods Corporation 	A-4
          U.S. v. Amelia Associates and Joey's Excavating, Inc. (D. N.J.)	A-4
          U.S. v. 179 South Street (D. N.J.) 	A-4
       CLEAN WATER ACT	A-4
          U.S. v. PRASA  	A-4
          U.S. v. City ofHoboken (D. N.J.) 	A-4
          In re Cheeseborough Ponds Manufacturing Corp	A-4
       SDWA  	A-5
          U.S. v. Kennemuth (d/b/a Moose Oil) (W.D. N.Y.)  	A-5
          U.S. v. Wasson &  Regis (W.D., N.Y.)  	-	A-5
          In re PRASA	A-5
          U.S. v. Melvin Blum	A-5
       RCRA	A-5
          U.S. v. Eastman Kodak (N.D. N.Y.)  	A-5
          In the Matter of Redound Industries, Inc. d/b/a Interflo Technologies and Liqui-Mark,
              etal.  	A-6
          U.S. v. BCF Corp. (E.D. N.Y.)	A-6
          In the Matter of Puerto Rico Sun Oil Company	A-6
                                           A-i

-------
JTFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
'
                      TABLE OF CONTENTS (Continued)
    In the Matter of PPG Industries, Inc.	A-6
    In re Westchester County, New York, Sportsmen's Center  	A-6
    In the Matter of Gaseteria Oil Corp	'A-6
 TSCA	A-7
    In the Matter ofDIC Americas,  Inc	A-7
    In the Matter ofSUNY-New Paltz	A-7
    In the Matter of Cray Valley Products, Inc	A-7
    In the Matter of Eastman Kodak Co	A-7
    In the Matter of Sharp Electronics Corporation	A-7
    In the Matter of General Electric Company  	A-8
    In the Matter of Presbyterian Homes of New Jersey Foundation	A-8
    U.S. v. State of New York Department of Transportation (N.D. N.Y.)	, . .  . . A-8
    In the Matter of New York State Department of Mental Health	A-8
    In re Corporacion Azucarera de Puerto Rico	A-8
    In re Edgewater Associates	A-8
    TSCA §8 Inventory Update Enforcement Initiative	A-9
    In the Matter of Ciba-Geigy Corporation	A-9
    In the Matter of OCG Microelectronics Materials, Inc	A-9
 EPCRA	A-9
    In the Matter of Mobil Oil Corp	A-9
    In the Matter of Agway Petroleum Corporation  	A-9
    In the Matter of Rich Products Corp	A-9
    In the Matter ofNTU Circuits, Inc	A-9
    In the Matter of R&F Alloy Wires, Inc	A-IO
    In the Matter of Silverton Marine Corporation	A-10
    In re Rexon Technology Corp	,	A-10
    In re Goodyear Tire & Rubber Co	A-10
    Catano EPCRA Enforcement Settlements	A-10
    In the Matter of National Can Puerto Rico, Inc	A-10
    In the Matter of Petroleum Chemical Corp	A-11
    In re Hess Oil Virgin Islands	A-11
    In re Statewide Refrigerated Services, Inc	A-11
    In the Matter of Freeman Industries, Inc	A-11
    In re E.I. DuPont de Nemours and Co	A-11
 CERCLA	-	A-12
    The Lipari Site	 A-12
    U.S. v. CDMG Realty Co., et al. (D. N.J.)		A-12
    £7.5. v. Vineland Chemical Company,  et al.  (D. N.J.)	A-12
    U.S. v. The Carborundum Company, et al. (D. N.J.)	 A-12
    In the Matter of the Frontier Chemical Superfund Site	A-12
    U.S. v. Ciba-Geigy Corp (D. N.Y.)	A-13
    In the Matter of Diamond Alkali Superfund Site  	A-13
    In the Matter of Liberty Industrial Finishing Site   	A-13
    In re ENRX and Buffalo Warehousing Superfund  Sites	A-13
                                      A-ii

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT!*
                           TABLE OF CONTENTS (Continued)
                                                                                    Page

          In re York Oil Company Superfund Site	A-13
          In re A&Y Realty Corp	A-13
          In re PVO International, Inc	 A-14
          Quanta/New Jersey Non-Complier Case Settlements	 A-14
          In re Niagara County Refuse Superfund Site	A-14
          In re Muratti Environmental Site	A-14
          U.S. v. Signo Trading International, Ltd., et al	A-14
          U.S. v. Zaklama (D. N.J.)	': . .  . A-15
          U.S. v. Thiokol Corp. (D. N.J.)	A-15
          U.S. v. Town of North Hempstead (ED. N.Y.)	A-15
          In the Matter of Aero Haven Airport Site	A-15
          U.S. v. Wheaton Industries, Inc. (D. NJ.)	 A-15
       MULTIMEDIA CASES  .	 A-15
          In the Matter of Brookhayen National Laboratories and Associated Universities,
             Inc.  "..'.	 . .... .''.'.' .... . .  .'. . . . .	. . :'.	 A-15
          In re American Cyanamid Company	A-16
          In re Broomer Research, Inc	A-16
          In re Abbott Laboratories	A-16
          In re Picatinny Arsenal 	A-17
          Port Authority of New York and New Jersey	A-17
          Safety Kleen	A-17

REGION III 	A-18
       CLEAN  AIR ACT	A-18
          Ohio Power Company (N.D. W.Va.)	 A-18
          Bethlehem Steel Corporation (E.D. Penn.)  	A-18
          U.S. v. Coors (D. Va.)	A-18
          Florida Marina and Boat Sales	A-18
          Hussey Copper	A-18
          Manny, Moe, and Jack, Inc.- The Pep Boys	 A-18
          U.S. v. Sun Oil, Philadelphia (E.D. Penn.)	A-19
          U.S. v. Sun Oil, Marcus Hook (E.D. Penn.)  	A-19
          LTV (W. D. Pa)  	A-19
          U.S. v. Sun Company, Inc. (E.D. Penn.)	A-19
       CLEAN  WATER ACT	A-19
          U.S. v. Sun Oil, Marcus Hook (E.D. Penn.)  	A-19
          Sun Oil, Philadelphia (E.D. Penn.)	A-20
          Sun Company (Pennsylvania)	A-20
          Ocean Builders Supply .'...'	A-20
          DELCORA (E.D. Pa)	A-20
          City of Philadelphia (E.D. Pa.)	A-20
          Eastern Energy Investments  	A-21
       SDWA  	A-21
          Consolidated Gas Transmission Corporation (1311)	A-21
                                          A-iii

-------
          1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                           TABLE OF CONTENTS (Continued)
          Jiffy Lube (7538)  	A-21
      RCRA	A-21
          Bethlehem Steel Corporation Steelton Plant	A-21
          Medusa Cement  	A-21
          U.S. v. National Rolling Mills (E.D. Penn.)	A-21
          Osram Sylvania Glass, Wellsboro, Pennsylvania	A-22
          Action Manufacturing Company, Atglen, Pennsylvania  .	A-22
          Quaker State Corporation, Newell, West Virginia	A-22
          Ravenswood Aluminum Corporation, Ravenswood, West Virginia 	A-22
          AT&T, Richmond,  Virginia  	A-22
          Johnson Controls Battery Group, Inc., Middletown, Delaware  	A-22
          ITT Corporation, Roanoke, Virginia  	A-22
      TSCA	A-22
          Allied Colloids 	'•	A-22
          Bethlehem Steel Corporation  	A-23
          Reading Tube Corporation	A-23
          Anzon, Inc	A-23
          Columbia Gas	A-23
          VA Dept of Emergency Services	A-23
      EPCRA	• • •	A-23
          T.L. Diamond, Spelter, West Virginia	A-23
          Premium Beverage Packers, Wyomissing, Pennsylvania	A-23
          Steel Processing, Inc., Pottstown, Pennsylvania	A-24
          Messer Greisheim Industries, Inc., Philadelphia, Pennsylvania  	A-24
          Diversey Corporation, East Stroudsburg, Pennsylvania	A-24
          Homer Laughlin China	A-24
          Action Manufacturing  	A-24
      EDFRA	A-24
          DuPont	A-24
      CERCLA	A-24
          Columbia Gas	A-24
          Greenwood Chemical	A-25
          Recticon/Allied Steel Site	; . .	A-25
          Sackville Mills Company	A-25
          United Chemical Technologies 	A-25
          U.S. v. Lord Corporation (W.D. Penn.) .	A-25
          U.S. v. Chromatex  (3rd Cir.)	A-25

REGION IV	•	A-26
      CLEAN AIR ACT	•	A-26
          U.S. v. Rohm and Haas, Inc. (W.D. Ky.)	'.	A-26
          U.S. v. Olin Corporation (E.D. Tenn.)	A-26
          U.S .v. Crown, Cork & Seal, Inc. (N.D. Miss.)	A-26
      CLEAN WATER ACT/SDWA  	A-26
                                          A-iv

-------
FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS
                     TABLE OF CONTENTS (Continued)
    U.S. v. Metro-Dade County, et al	A-26
    United States v. IMC-Agrico Company (M.D. Florida)	A-27
    U.S. v. Perdue-Davidson Oil Company (E.D. Kentucky) 	A-27
    In the Matter of Manatee County, PL:	A-27
    In the Matter of IMC-Fertilizer, Bartow FL  '.	A-27
    In the Matter of Jacksonville Beach, FL		A-27
    Oil Pollution Act Enforcement Initiative	A-28
    U.S. Environmental Protection Agency v. Polk County	A-28
    United States v. City of Port St. Joe, Florida; et al.	A-28
 RCRA	A-29
    Holnam, Inc	A-29
    Arizona Chemical Company	A-29
    Giant Cement Company	A-29
    Todhunter International, Inc., d/b/a Florida Distillers	A-29
    U.S. v. Gulf States Steel, Inc. (N.D. Ala.)	A-29
    Laidlaw Environmental Services (TOC), Inc	A-29
    Florida Department of Transportation  	A-30
 TSCA	A-30
    Tennessee Gas Pipeline Company/Tenneco, Inc. .	A-30
    General Electric Company	 A-30
 EPCRA			A-30
    Gro-Tec, Inc	A-30
    Everwood Treatment Company, Inc	A-31
    North  American Royalties, Inc., d/b/a Wheland Foundry 	A-31
    Ashland Petroleum Company	A-31
 FIFRA  	A-31
    Courtaulds Coatings, Inc	A-31
 CERCLA	A-31
    Kerr-McGee Chemical Corporation	A-31
    Parramore Fertilizer Site in Tifton, Georgia  	A-32
    Distler Farm and Distler Brickyard Superfund Sites in Kentucky	A-32
    Jadco/Hughes Site, Gaston County, North Carolina	A-32
    T.H. Agriculture & Nutrition Co. Site in Albany, Georgia		A-32
    Helena Chemical Company for Fairfax, South Carolina Site	A-32
    Rochester Property Site in Travelers Rest, South Carolina  . .	A-32
    Jones Tire and Battery Site in Birmingham, Alabama  	A-33
    Townsend Saw  Chain Superfund Site in Pontiac, Richland  County, North Carolina .  . A-33
    Yellow Water Road Superfund Site, Baldwin, Duval County, Florida 	A-33
    Smith's Farm Site in Bullitt County, Kentucky	A-33
    Cedartown Battery Superfund Site in Polk County, Georgia	A-33
    Enterprise Recovery Systems Site in Byhalia, Mississippi  	A-33
    The City of Cedartown, Polk County, Georgia  	A-34
    Bypass 601  Groundwater Contamination  Site,  Cabarrus County, Concord, North
       Carolina	A-34
                                    A-v

-------
          1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                           TABLE OF CONTENTS (Continued)
                                                                                   Page
          Stoller Chemical Company Site in Jericho, South Carolina	A-34
          Firestone Tire & Rubber Co. Site in Albany, Dougherty County, Georgia	A-34
          Woolfolk Chemical Works NPL Site, Fort Valley, Georgia  	A-35
          Hercules 009 Landfill Site, Brunswick, Glynn County, Georgia  	A-35
          U.S. v. Otto Skipper (ED., N.C.)	A-35
          National Southwire Aluminum Superfund Site in Kentucky	A-35
          Prairie Metals and Chemical Company Site (Prairie, Mississippi)  	A-35

REGION V	A-36
       REGION V's CONTEMPT INITIATIVE  	A-36
          Anthony Chambers (Midland, MI) .	  A-36
          Big D Campground/Rodebaughs (Ashtabula, OH)	A-36
          Petoskey Site (Petoskey, MI)  	A-36
          Copperweld Steel (Mahoning, OH)	A-36
          Midwestern Drum Services (Venice, IL)   	A-36
          Silvertone Plating Company (Ypsilanti, MI)	A-37
          GTE North (Belvedere, IL)	A-37
          Bethlehem Steel Corporation (Burns Harbor, IN)  	A-37
       ILLINOIS CASES  	A-37
       OHIO CASE	A-37
       CLEAN AIR ACT	A-37
          B&W Investment Properties, Inc., and Louis Wolf	A-37
          New Boston Coke Corp. (S.D. Ohio)	A-38
          U.S. v. Consolidated Papers, Inc. (Wisconsin Rapids, WI)	A-38
          Monitor Sugar Co. (E.D. Mich.)	A-38
          Stern Enterprises, Inc., et  al. (U.S. District  Court for the  Northern District  of
             Ohio/Eastern Division)	A-38
       CLEAN WATER ACT	A-39
          LTV Steel (East Chicago, IN)	A-39
          1MB Urban Development Company (Columbus, OH)  	A-39
          City of Middletown (OH)	A-39
          Wayne County-Wyandotte (MI) Wastewater Treatment Plant	A-39
          IBP,  Inc. (Joslin, IL)  	A-39
          Appleton Papers (Appleton, WI)	A-40
          Commonwealth Edison Company, Inc. (Chicago, EL)	A-40
       MULTIMEDIA CASES  	A-40
          Taracorp Industries (Granite City, IL)  	A-40
          Glidden Company (Strongsville, OH)	A-40
       EPCRA	A-40
          Vie De France (Bensenville, IL)	A-40
          HRR Enterprises, Inc. (Chicago, IL)  	A-41
          Shell Oil Company's Wood River Manufacturing Complex (Roxana, IL)	A-41
          Consumers Power Co. (West Olive, MI)   	A-41
          Karmazin Products Corp. (Wyandotte, MI)	A-41
                                          A-vi

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS
                           TABLE OF CONTENTS (Continued)
       TSCA	A-42
          University of Illinois (Champaign-Urbana, IL)	A-42
          Wayne State University (Detroit, MI)	 A-42
          U.S. Graphite, Inc. (Saginaw, MI)	A-42
       RCRA/UST . .	A-42
          BASF Corp. North Works (Wyandotte, MI)		A-42
          Hilton Davis Co. (Cincinnati, OH)	A-42
          Greater Cleveland Regional Transit Authority (Cleveland, OH)  .	A-43
          Northwest Airlines, Inc. (Saint Paul, MN)	 A-43
          U.S. v. Bethlehem Steel Corp. (7th Cir. 1994)	 A-43
          U.S. v. Ekco Housewares, Inc. (Massillon, Ohio)  	A-43
          U.S. v. Laclede Steel Company  . . .	A-43
          City of Columbus, Ohio and the Solid Waste Authority of Central Ohio  ......... A-43
       SDWA	A-44
          Total Petroleum (Alma, MI)	. .	 A-44
          George Perry (Oceana County, MI)		A-44
          JPT Petroleum Production Corp. (Gibson County, IN)	A-44
          Gahanna Water Department (Gahanna, OH)	A-44
       CERCLA		. .	 . A-44
          Circle Smelting (Beckmeyer, IL)	  . .	A-44
          Core Craft (Northern Township, MN)  	A-45
          Kerr-McGee Site (Chicago, EL)		. .  . . A-45
          Lockhart Construction (Akron, OH)	A-45
          National Presto (Eau Claire, WI)	 .	 A-45
          Olin Corporation (Ashtabula, OH)	A-45
          Wedzeb (Lebanon, IN)	  .... A-46
          Jackson Drop Forge (Jackson, MI)	•'...••	A-46
          Spickler Landfill Site (Marathon County, WI)	A-46

REGION VI	:	;.;.... ; ....... A-47
       CLEAN AIR ACT	',	A-47
          U.S. v. Enpro Contractors, Inc.; Train Property, Inc.; and Jimmy Patton Contractor,
              Inc. (E.D. Ark.)	A-47
          In the Matter of Herd Enterprises,  d/b/a Broward Factory Service	A-47
       CLEAN WATER ACT	.  .	 A-47
          U.S. v. City  of Kenner and the State of Louisiana (E.D. La.)	 A-47
          U.S. v. City  of Bossier City, and the State of Louisiana (W.D. La.)	A-47
          U.S. v. E.I. DuPont De Nemours and Company  (E.D. Tex.)	 A-47
          Vulcan  Chemical	A-47
          In the Matter of Albert Kramer III d/b/a Kramer Development Corporation ....... A-48
          Citgo Pipeline Company		A-48
          Hamner Inc	A-48
          Jayhawk Pipeline Corporation	A-48
          Petrolite Corporation  	A-48
                                         A-vii

-------
|FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                      TABLE OF CONTENTS (Continued)
    Red River Entertainment Group  	A-48
 RCRA	A'48
    In the Matter of Micro Chemical Company  	A-48
    In the Matter of Dow Chemical	A-49
    In the Matter of Chemical Waste Management	A-49
    In the Matter of Chemical Waste Management	  A-49
    In the Matter of Texas Industries	A-49
    In the Matter ofAristech  	A-49
    In the Matter ofRexene	A-49
    In the Matter ofChapparal Steel	A-49
    In the Matter of Hydrocarbon Recyclers, Inc	A-50
    In the Matter ofREM TEX	A-50
    In the Matter of Jeep Collins 	A-50
    In the Matter ofRanco	A-50
    In the Matter of Citgo Refining	A-50
    In the Matter ofAquaness Chemical  	••,••••  A-50
    In the Matter of Helena Chemical	A-50
    In the Matter of Helena Chemical	A-51
    U,S. v. Marine Shale Processors, Inc. (W.D. La.)	A-51
 TSCA	A-51
    In the Matter ofAsarco, Amarillo, Texas	A-51
    Central Power and Light Company, Corpus Christi, Texas	A-51
 CERCLA	A-51
    U.S. v. David Bowen Wallace, etal. (N.D. Tex.) Bio-Ecology Systems Superfund Site,
        Dallas County, Texas	• •  A-51
    U.S. v. American National Petroleum Company, et al (W.D. La.) Gulf Coast Vacuum
        Superfund Site, Abbeville, Louisiana, and Gulf Coast Vacuum Services Superfund
        Site, Vermillion Parish,  Louisiana	A-52
    U.S. v. City of Jacksonville, Arkansas (E.D. Ark.) Jacksonville Municipal Landfill,
        Lonoke County, Arkansas, and Rogers Road Municipal Landfill, Pulaski County,
        Arkansas	A-52
    U.S. v. Gulf States Utilities Company (S.D Tex.) Industrial Transformer/Sol Lynn Site,
        Harris County, Texas	A-52
    U.S. v. Venae Chemical Corporation, et al., Arkansas  Department of Pollution
        Control and Ecology v.  Vertac  Chemical Corporation, et al. (E.D. Ark.).  In the
        Matter  of Hercules Inc.,  Uniroyal  Chemical Ltd.,  and Vertac  Chemical
        Corporation (Administrative) Vertac Superfund Site, Jacksonville, Arkansas  . . .  A-53
    In  the Matter  of Amerada Hess  Corporation, et  al, PAB  Oil  Superfund Site,
        AbbeVille, Louisiana	A-53
    In the Matter of Waste Management of Oklahoma, Inc., Mosley Road Sanitary Landfill
        Superfund Site,  Oklahoma City, Oklahoma	  A-53
    In the  Matter of Aluminum Company of America, Alcoa/Lavaca Bay Superfund Site,
        Point Comfort,  Texas	A-53
                                     A-viii

-------
       FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS
                           TABLE OF CONTENTS (Continued)
                                                                                    Pas
          In the Matter of National Zinc Site, Bartlesville, Oklahoma; Salomon, Inc.,  Cyprus
              Amax Minerals Company,  and Kerramerican, Inc., National Zinc  Company
              Superfund Site, Bartlesville, Oklahoma	 A-54
          Marco of Iota	 A-54
          Pab Oil	A-54
          South 8th Street	A-54
          B.P. Chemical	 A-54
          Miles Inc	A-54

REGION VII	 A-56
       CLEAN AIR ACT	'	A-56
          U.S. v. Archer Daniels Midland (S.D. la.)	A-56
          U.S. v. Hunt Midwest Mining, Inc. (W.D. Mo.)	A-56
          In the Matter of Holnam, Inc	A-56
       CLEAN WATER ACT		A-56
          In the Matter of the Boeing Company  	A-56
          U.S. v. Beech Aircraft Corporation (D. Kan.)	 A-56
       RCRA	A-57
          In the Matter of Burlington Northern Railroad	A-57
          In the Matter of The Dexter Company	 A-57
          In the Matter of Missouri Highway Transportation Department	A-57
          In the Matter of Iowa Army Ammunition Plant	A-57
          In the Matter of G.E. Company	A-57
          In the Matter of Cuba Paint Company	A-58
       EPCRA	A-58
          In the Matter of Kaw Valley, Inc	 A-58
          In the Matter of The Iowa Packing Company  .	A-58
       CERCLA	A-58
          U.S. v. Chemical Waste Management of Kansas, Inc.  (D. Kan.) . .	A-58
          U.S. v. TIC Investment Corp., et al. (N.D. la.)	A-58
          In the Matter of the Big River Mine Tailings Site	A-59
          In the Matter of Lee Chemical Co. Superfund Site, Liberty, Missouri  	A-59
          U.S. v. Boehringer Ingelheim Animal Health, Inc. (D. Neb.)	A-59
          In the Matter of Renner Road Shooting Park  	A-59
          U.S. v. City of Clinton, Iowa (S.D. la.)  	A-59
          U.S. v. Midwest Asbestos Control,  Inc., et al. (D. Kan.)	A-60

REGION Vin	A-61
       CLEAN AIR ACT	A-61
          Sinclair Oil Corporation	 A-61
       CLEAN WATER ACT			 . . A-61
          Dirt Merchant Construction/Sandra Tarr	A-61
          Lucas Western (Jamestown, North  Dakota)	A-61
          Farmers Union Central Exchange  COOP (CENEX) (Billings, Montana)  	A-61
                                          A-ix

-------
         1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                           TABLE OF CONTENTS (Continued)
                                                                                     Page

          Burlington Northern Railroad (W.D., Wise.)  	A~61
          Hub City, South Dakota	A'62
          City of Sioux Falls, South Dakota:   	A~62
          Star Circuits	A'62
       SDWA . . .,	A'62
          Town ofMeeteetse, Wyoming 	A-62
          City Oil Corporation	A'62
       RCRA	A"63
          Reclaim Barrel	A"63
       EPCRA	•	A"63
          Advanced Forming Technology	A-63
          Accurate Plastics (now SPM/Denver)  	A'63
          Denver Metal Finishing Company	A-63
          Nephi Rubber Products  	A"63
          Thatcher Chemical Company 	A-63
       FIFRA 	A"63
          Biotrol International, Inc	A-63
       CERCLA	A'64
          Apache Energy and Minerals Co. (D. Colo.)  	A-64
          Smuggler-Durant Mining Corporation  (D. Colo.)  	A-64
          Clear Creek/Central City Superfund Site, Western Diversified Builders	A-64
          Whitewood Creek  	A-64
          Petrochem/Ekotek Site	A"65
          Petrochem/Ekotek  	A'65
          Colorado School of Mines Research Institute	A-65
          North American Environmental, Inc	A-65

REGION DC	A"67
       CLEAN AIR ACT	A'67
          U.S. v. Shell Western E&P,  Inc.  (E.D. Calif.)	A-67
          U.S. v. TABC, Inc. (C.D. Calif.)  	A-67
          U.S. v. Minerec, Inc. (D. Ariz.)	A~67
          U.S. v. All American Pipeline Company (C.D. Calif.)  	A~67
       CLEAN WATER ACT	• • •  A'67
          U.S. v. American Global Line, Inc. (N.D. Calif.)	A-67
          U.S. v. Magma Copper Co.  (D. Ariz.)	A~67
          U.S. v. City and County of Honolulu (D. Haw.)  	A-68
          U.S. v. Southern Pacific Transportation Corp. (E.D. Calif.)	A-68
          U.S. v. Teledyne, Inc. (S.D. Calif.)  	A-68
          U.S. v. County Sanitation Districts of Los Angeles County (S.D. Calif.)	A-68
       RCRA	•	A'69
          U.S. v. Hawaiian  Western  Steel, Ltd., Estate  of James Campbell,  Ipsco  Inc. and
              Cominco Ltd.  (D. Hawaii)   	A~69
          In the Matter of U.S. Naval Air Facility, El Centra, California	A-69
                                            A-x

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPon
                            TABLE OF CONTENTS (Continued)
          U.S v. City of Los Angeles and U.S. v. Lockheed Corporation (C.D. Calif.)	A-69
          U.S.  v. Hawaiian Western Steel, et al. (D. Haw.)  	A-69
       CERCLA	A-69
          U.S.  v. Peter Gull and NL Industries, Inc. (C.D. Calif.)	A-69
          Pearl Harbor Naval Complex Federal Facilities Agreement	A-69
          U.S.  v. Montana Refining Co. (9th Cir.)	A-70
          In the Matter of Iron Mountain Mine	A-70
          U.S.  v. Alcatel Information Systems, Inc. (D. Arizona)	A-70

REGION X	 A-71
       CLEAN AIR ACT	A-71
          Alyeska Pipeline Services Company and ARCO Products  	A-71
          Norma and Frank Echevarria, d/b/a Echeco Environmental Services 	A-71
          Phillips Petroleum Company and AGI, Inc	A-71
          Trans-AK  Environmental Services & Construction  Corp., Giddings Mortgage and
              Investment Company, and Neeser Construction	A-71
          U.S.  v. Global  Travel, Jordan-Wilcomb Construction, and Allied Construction (D.
              Id.)	A-71
          U.S.  v. Zemlicka and Davis  	A-71
          U.S.  v. Martech  USA,  Hobbs Industries, Chugach Electric Association, Inc.	A-72
          U.S.  v. Hagadone Hospitality Co	A-72
       CLEAN WATER ACT	A-72
          Wesley M. Sherer	A-72
          U.S.  v. Steve Burnett and Dean Schroder (W.D. Wash.)	A-72
          Kenco Marine	A-72
          City  of Ocean Shores, Washington  	A-72
          Rodger Forni  	A-72
          Martin Nygaard	A-73
          Rogge Mills  	A-73
          Washington State Department of Transportation (WSDOT) 	A-73
          Northlake Shipyards  	A-73
          City  of Tacoma	A-73
          Arctic Fisheries	A-73
          U.S.  v. Stanley C. Rybachek	A-73
       RCRA	A-73
          U.S.  v. Robert and Geneva Stobaugh (W.D. Wash.)   	A-73
          U.S.  v. R.H. Bowles, Inc. and Central Marketing, Inc. (E.D. Wash.)  	A-74
          Alaska Railroad Company  	A-74
          Boeing Company	A-74
          U.S.  Army, Fort Wainwright, Alaska	A-74
          U.S.  Army, Fort Richardson	A-74
       CERCLA	A-75
          Commencement Bay - South Tacoma Channel	A-75
          Bunker Hill  	A-75
                                           A-xi

-------
          1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                           TABLE OF CONTENTS (Continued)
                                                                                  Page
FEDERAL FACILITIES ENFORCEMENT OFFICE	A-76
       RCRA/FFCA	A-76
          RCRA/FFCA Penalty Order-Coast Guard, Kodiak, Alaska Facility	A-76
          Presidio of San Francisco	A-76
          Schofield Barracks	A-76
          Norfolk Naval Shipyard	A-76
          Yorktown Naval Weapons Station, Yorktown, Virginia	A-76
          Naval Surface Warfare Center, Dahlgren Division, Dahlgren, Virginia	A-76
          Fort Dix, New Jersey	A-77
          U.S. Naval Station Roosevelt Roads, Ceiba, Puerto Rico	A-77

OFFICE OF REGULATORY ENFORCMENT	A-78
       CLEAN AIR ACT	A-78
          U.S. v. Atlantic Richfield Company and Snyder Oil Corporation (D. Wyo.)	A-78
          U.S. v.  W.R. Grace Company (D. Mont.)	A-78
          U.S. v.  ICI International, Inc	A-78
          U.S. v.  JBA  Motorcars, Inc. and Dr. Jacob Ben-Ari (S.D. Fla.)	A-78
          U.S. v.  Daniel Rosendahl (S.D. Tex.)	:	A-78
          U.S. v.  Ken  Ball and Phil McCreery (W.D. Mo.) 	A-78
       TSCA	A-78
          Town of Wallingford, Connecticut	A-78
          Cressona Aluminum Company PCB Cleanup 	A-79
          USS Cabot/Dedalo	A-79
          Port of New Orleans 	A-79
          Sunshine Mining Company	-.	A-79
          Imperial Holly Corporation	A-79
       EPCRA	A-79
          General Chemical Corporation  	A-79
          Alaska Pulp Corporation 	A-80
          Trail Wagons	A-80
          Northwest Castings  	A-80
       FIFRA  	A-80
          Pinnacle Agricultural Technologies	A-80
          Accuventure, Inc.: Criminal and Civil Enforcement Coordination	A-80
          Argent Chemical Laboratories,  Inc	 A-80
       MULTIMEDIA CASES 	A-81
          Allied Tube & Conduit 	A-81
          U.S. v. Columbus Solid Waste Reduction Plant	A-81
          U.S. v. Southern Pacific	A-81
          U.S. v. Texas Eastern (S.D., Tex.)	A-81

OFFICE OF CRIMINAL ENFORCEMENT	A-82
          U.S. v. Hartford Associates (D. Md.)	A-82
          U.S. v. Penn Hills (W.D. Penn.)  	A-82
                                          A-xii

-------
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORif^sg^}
                      TABLE OF CONTENTS (Continued)
    U.S. v. Reilly	A-82
    U.S. v. Wietzenhoff	A-82
    U.S. v. Laughlin, 10 F.3rd 961 (2d Cir. 1993), cert, denied, 114 S.Ct. 1649 (1994) . .  A-82
    U.S. v. Advance Plating Works, Inc., et al. (S.D. Ind.)	 .  A-83
    U.S. v. Carlo Arco and Automatic Plating Company, Inc. (D. Conn.)  	A-83
    U.S. v. AT&T and Harry J. Kring (E.D. Penn.)	A-83
    U.S. v. Richard Vernon Bates,  et al. (C.D. Calif.)	A-83
    U.S. v. Giacomo Catucci (D. R.I.)	A-83
    U.S. v. Larry A. Christopherson (E.D. Wise.)	• •  • • •	A-84
    U.S. v. Craven Laboratories, Inc., et al. (W.D. Texas)	A-84
    U.S. v. Dean Foods Company and Winfred Smith (W.D. Ky.)  	A-84
    U.S. v. Doyle  Crews, (N.D. Tex.) 		. .  A-84
    U.S. v. Charles A. Eidson and Sandra A. Eidson (M.D. Fla.)	  A-84
    U.S. v. Cherokee Resources, Inc., et al. (W.D. N.C.)	, .  . . .	A-85
    U.S. v. Garlick Helicopter, Inc. (D. Mont.)	A-85
    U.S. v. Gaston (D. Kan.)	A-85
    U.S. v. Hedge, (S.D. Ohio); State of Ohio v. Hedge and City Bumper Exchange, Inc.,
        (Hamilton County Court of Common Pleas)	A-85
    U.S. v. Hofele. (W.D. Mo.)	A-85
    U.S. v. Robert H. Hopkins (D. Conn.)	A-85
    U.S. v. George Frederick Heidgerken (W.D. Wash.)	A-85
    U.S. v. Comer's Diesel and Electric Company (D. Mont.)	A-86
    U.S. v. Jay Jurek (W.D. Wash.)	A-86
    U.S. v. MOR,  Inc. (S.D. Fla.)	  A-86
    U.S. v. Francis Morgan, et al. (D. Haw.)	  A-86
    U.S. v. M. Tyronne  Morgan and Meydenbauer Development Corp. (E. D. Wash.)  . . .  A-86
    U.S. v. Bob Murphy, et al. (D. Nev.)	  A-87
    U.S. v. Norwood Industries, Inc., et al. (E.D. Penn.)	A-87
    U.S. v. OEA, Inc. (D. Colo.)	  A-87
    U.S. v. Palm Beach Cruises (S.D. Fla.)  	A-87
    U.S. v. Pacific Aqua Tech, Ltd. (E.D. Wash.) . .	A-87
    U.S. v. Robert Pardi (S.D. N.Y.)	A-88
    U.S. v. Nicholas Pasquariello (S.D. Fla.)	A-88
    U.S. v. Norma Phillips, et al. (W.D. Mo.)	A-88
    U.S. v. Pioneer Chemical, Inc. and Gerald Butler (D. Ky.)	  A-88
    U.S. v. John Pizzuto (S.D. Ohio)	A-89
    U.S. v. Nobert Efren Pohl (D. N.M.)			A-89
    U.S. v. R&D Chemical Company, Inc. (N.D. Ga.)	  A-89
    U.S. v. Recticel Foam Corporation, et al. (E.D. Tenn.)	  A-89
    U.S. v. William C. Reichle and Reichle, Inc. (D. Ore.)	A-90
    U.S. v. Reilly  and Dowd (D. Del.)	A-90
    U.S. v. Sentco Paint Manufacturing, Inc., et. al. (N.D. Ohio)	A-90
    U.S. v. Mark Steven Stewart,  et al. (D. Ariz.)	A-90
                                     A-xiii

-------
|FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                     TABLE OF CONTENTS (Continued)
    U.S.  v. Thermocell S. E. Inc.,  Douglas  Kirchofer and Sherwin T. Haskell (E.D.
        Tenn.)	A-90
    U.S. v. Weaver Electric (D. Colo.)	A-91
    U.S. v. Safety Kleen	A-91
    U.S. v. Steve Weinsier (S.D. Fla.)	A-91
    U.S. v. Larry Kenneth West (W.D. Mich.)  	A-92
    U.S. v. William C.  Whitman and Duane C. Whitman (M.D. Fla.)	A-92
    Harry Zucker (W. D. Pa)	A-92
    U.S. v. Dale Valentine et al. (D. WY)	A-92
                                   A-xiv

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                         REGION I
CLEAN AIR ACT

U.S. v. D'Addario Industries, Inc.,  et al (D.
Conn.):  On July 5, 1994, the court approved a
Stipulated Settlement Agreement (SSA) resolving
a consent decree enforcement action in this CAA
asbestos  case.  The SSA  requires defendants to
pay the full amount of stipulated penalties owed,
plus interest, for a total payment to the United
States of over $109,000. EPA took this action for
stipulated penalties after defendants paid a portion
of the underlying penalty more than 6 months late.
The  decree  required  payment  of  stipulated
penalties of $500 per day for each day the penalty
payment was late.

In  re  Syncor International Corporation:   On
September 26, 1994, EPA issued an administrative
order  to  Syncor  International  Corporation  of
Woburn, MA, for  failure to comply with the
radionuclide   NESHAP  (Subpart  I)  emission
standard.  The order required Syncor to comply
with the emission standard and to begin submitting
monthly reports to EPA and a compliance plan as
required by Subpart I for those facilities that report
exceedances of the radionuclide emission standard.

CLEAN WATER ACT

U.S. v. L.S. Starrett Company (D. Mass.):  On
May 12,  1994, the court entered a consent decree
resolving   violations   of   CWA  pretreatment
requirements by  the  L.S. Starrett  Company,  a
metal finisher located in Athol,  MA.  EPA had
alleged that Starrett had violated §§ 307 and 308
of the  Act by (1) exceeding effluent limitations,
(2)  violating the pH standard, and (3) failing to
comply with reporting requirements. The consent
decree requires Starrett to maintain compliance
with pretreatment requirements and to  pay a civil
penalty of $325,000 for its past violations.

RCRA

Allegro Microsystems, Inc.:  On April 5,  1994,
EPA-New  England issued a  RCRA  complaint
against Allegro Microsystems, Inc. of Worcester,
MA.  The complaint alleges that since August 21,
1991, Allegro has been burning hazardous waste
in two  industrial  boilers without  a permit or
interim status.  In addition, the complaint alleges
that Allegro failed to comply with the  operating
conditions for boilers contained in the boiler and
industrial  furnace  (BIF) regulations.     These
regulations require emissions monitoring and set
emissions standards for a number of pollutants.
The complaint proposes a penalty of $102,194 and
orders Allegro to cease burning hazardous waste.
This was the first action brought by EPA pursuant
to the BEF regulations.

In re  Massachusetts Highway Department: In a
consent   agreement   resolving   a    RCRA
administrative action  issued  on  September 30,
1994, EPA, the MA DEP, and the Massachusetts
Highway Department  (MHD)  agreed that MHD
will   spend   $20  million  to  investigate  and
remediate environmental problems at all  138 of its
facilities  and will dedicate $5 million to  several
SEPs,  including  projects   that  will  benefit
environmental justice  areas.  In  addition,  MHD
will pay a civil penalty of $100,000 to  settle this
action brought by  EPA  for  the  state  agency's
violations of hazardous waste laws.

U.S.  v.  Hanlin Group, Inc. (D. Maine):   On
December 22,  1993, a consent decree was entered
by the court against the Hanlin  Group, Inc. of
Linden, NJ.  Hanlin agreed to pay a $1,152,000
penalty for violations of RCRA at its Orrington,
Maine, facility. Hanlin also agreed to complete a
site investigation and  corrective  measures study
prior  to  undertaking  any  necessary  corrective
action at the facility. EPA determined that Hanlin
had   allowed   releases  of   mercury,  carbon
tetrachloride,  1,1,2-trichloroethane,    and
trichloroethylene into the groundwater flowing
under the facility and the Penobscot River.  A
1986  administrative consent  agreement entered
into by Hanlin and EPA had required  Hanlin to
undertake  an  RCRA   facility   investigation,
including  sampling, analysis, monitoring,  and
                                             A-l

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
reporting of hazardous wastes, at the facility.  The
December  23,  1994  settlement addressed the
violations of the 1986 consent agreement.

In re Hamilton-Standard:  On April 18, 1994,
EPA and Hamilton-Standard entered into EPA's
first RCRA §3008(h) corrective action order  to
contain  Alternate Dispute  Resolution  (ADR)
provisions.   EPA determined that a plume  of
contaminated groundwater  migrating  from the
facility might present an imminent and substantial
endangerment to human health or the environment,
specifically  to  groundwater used by residents.
Further,  the   contaminated  plume  released
hazardous levels  of volatile organic compounds
(VOCs) into the  basements of some  residences.
The consent order abates known and potential
threats through implementation  of four separate
interim  corrective  measures, including:   (1)
groundwater containment, (2) monitoring of VOC
levels in indoor air of residences above the plume,
followed by any necessary corrective measures, (3)
monitoring  of residential drinking water, followed
by  any necessary provision  of alternate water
supplies, and  (4) containment  of contaminated
water flowing to  the wetland area to minimize
ecological impacts.

In re Upjohn Company:  On June 12, 1994, EPA
signed a RCRA corrective  action consent  order
with the UpJohn  Company  for  the remediation
(including  immediate control of the  release  of
hazardous  wastes to  groundwater) of its North
Haven,  CT,  facility.  Upjohn's plant  is  now
inactive, but in the past produced more than  20
different specialty and industrial chemicals.   In
1989, EPA issued an  RCRA §3013 administrative
order to Upjohn, requiring the company to conduct
a RCRA Facility Investigation (RFI) at the facility.
Based on reports generated  by  that order, EPA
determined  that  the  facility  poses  a threat  to
human health and the environment.

TSCA

U.S. v. New Waterburv, Ltd. (D.  Conn.):   On
May 23, 1994, the U.S. District Court entered a
civil consent decree settling PCB violations under
TSCA.   The consent decree  requires defendants
New Waterbury Ltd.,  Vanta, Inc., and  Winston
Management and Investment, Inc. to  remove and
properly  dispose  of  approximately  91  tons of
abandoned, illegally stored PCBs from equipment
at the former Century Brass Products, Inc. facility
in Waterbury,  CT.  Pursuant to this settlement,
defendants have removed and properly disposed of
all PCB equipment and PCB waste at an estimated
cost of $450,000.

In re City of Boston, Boston City Hospital:  On
September  30, 1994, EPA entered a consent
agreement and final order in which  the City of
Boston agreed to pay $117,300 in civil  penalties
for violation of the TSCA PCB requirements at
Boston City Hospital.  The City also agreed to
perform an SEP as part  of  the settlement which
involves removal of ten underground storage tanks
located throughout the  city at  a cost  of over
$80,000.  This civil administrative case arose as a
result of  EPA's PCB  inspection of the  hospital.
The complaint alleged that the City  violated  the
PCB regulations  by failing to  comply  with  the
marking    and   recordkeeping   requirements
pertaining to PCB transformers.

EPCRA

In  re  Wvman-Gordon.  Inc.:   In  a consent
agreement   issued   on   May    18,   1994,
Wyman-Gordon,  Inc., of North Grafton, MA,
agreed to pay a $137,955 penalty and implement
a SEP to reduce its use of two dangerous acids to
settle a  complaint alleging that the  company
violated §103 of CERCLA and §§ 312 and 313 of
EPCRA.    Wyman  Gordon,  a  forged   metal
components  manufacturing  facility, failed to
immediately notify the National Response  Center
of a release of hydrofluoric acid during a fire at
the facility on September 24, 1988. The  company
also failed to  submit  emergency and hazardous
chemical  inventory  forms  and  report various
emissions of chemicals  during  1987 and  1988.
The company has agreed to construct a $474,000
acid purification  and recovery system to recover
80 percent of the hydrofluoric and nitric acid from
its waste acid stream.
                                             A-2

-------
         1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
CERCLA

U.S. v. O.K. Tool Company, et al (D. N.H.):  On
December 5, 1994, the court entered this consent
decree settling all remaining CERCLA and fraud
claims in connection with the Savage Municipal
Water Supply Well  Superfund Site in Milford,
NH.  The cashout settlement represents the final
agreement in a global resolution of the legal issues
arising out of the contamination of a groundwater
aquifer which supplied Milford with 45 percent of
its drinking  water prior to 1983.  A mixed work
consent decree with two other corporate PRPs at
the Site, as  further described below, was entered
by the Court on June 27, 1994.  The work being
performed by the government  is valued at $10
million.  Under the cashout consent decree, 22
settling defendants whose liability arises out of a
relationship to O.K. Tool Company have agreed to
pay  the federal  government approximately  $2.1
million.

U.S. v. Conductron Corporation, et al. (D. N.H.):
On June 27, 1994, the court entered a civil consent
decree  in which two corporate PRPs  agreed to
perform the remedial action for part of the Savage
Municipal Water Supply Well Superfund  Site in
Milford, NH.  The consent decree resolves claims
under  CERCLA   for  releases   of  hazardous
substances into the environment. Under the terms
of the decree, Conductron, d/b/a Hendrix Wire &
Cable and Hitchiner Manufacturing Company, will
undertake response  actions including  extraction
and treatment of contaminated groundwater, long-
term monitoring, and  institutional controls  to
protect human health. It is estimated that the cost
of  the  response action to  be performed  by the
settling parties will be $15  million. The settling
defendants have also agreed to pay  approximately
$1 million in past costs and oversight costs subject
to a ceiling of $3 million or 15 percent of the cost
of the work, whichever is greater.

 U.S. v. William  Davis, et al (D. R.I.):  On
January 18,  1995, the court entered a consent
decree that resolves the liability of Clairol, Inc.
and Ciba-Geigy Corporation,  defendants  in  the
Davis  Liquid  Superfund  Site  cost  recovery
litigation.  Under the settlement, Clairol will pay
$3 million plus interest and Ciba-Geigy will pay
$475,000 plus interest.  In exchange, both settling
parties will receive a covenant not to sue under
CERCLA §107(a) with standard reopeners.  The
decree also contains a "cost reopener" that allows
the government  to  institute  new proceedings
against Clairol and Ciba-Geigy in  the event that
the total response costs  at the site exceed $68
million.

On October 31, 1994,  the court entered a civil
consent decree providing that Providence Journal
Co., also a defendant in the Davis cost recovery
litigation, will  pay $650,000  plus interest.   In
exchange, Providence Journal obtained a covenant
not to sue  with standard  reopeners.   Also on
October  31,  the District  Court entered a third
consent decree providing that Pfizer, Inc., another
defendant in this cost recovery litigation, will pay
$1.5  million  plus interest.    The decree  also
contains  a  cost  reopener  that  allows  the
government to  institute new proceedings against
Pfizer in the event that total response costs exceed
$68 million.   In exchange,  Pfizer received  a
covenant not to sue with standard reopeners.

U.S. v. DiBiase Salem Realty Trust,  et al.  (D.
Mass.):  On December 5, 1994, the court entered
this consent decree in connection with  the Salem
Acres  Superfund Site in Salem, MA.  Under the
terms  of the  settlement,  DiBiase Salem Realty
Trust and Ugo DiBiase agreed to pay $80,329 in
past costs, to perform remedial activities valued at
approximately $650,000 on a portion of the Site,
and to pay the future oversight costs incurred in
connection with those  remedial activities, valued
at approximately $110,000.  The DiBiases agreed
to these terms to settle a civil action brought under
CERCLA.
                                               A-3

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                        REGION H
CLEAN AIR ACT

In re Ronzoni Foods Corporation: On January
25, 1994, EPA entered into a consent agreement
with Hershey Foods, the parent of Ronzoni Foods,
resolving an  administrative enforcement  action
brought  under the Clean Air  Act to address
opacity violations at Ronzoni's facility located in
Queens, NY.  Hershey Foods elected to close the
violating facility because it felt it could not ensure
long-term   compliance,   but    volunteered  to
undertake a supplemental environmental project
(SEP) involving another facility, its San Georgio
plant located  in Philadelphia, PA (within EPA
Region HI).  The  consent agreement included a
$30,000 penalty.

U.S. v. Amelia Associates and Joey's Excavating,
Inc. (D. N.J.): On November 3, 1993, the court
entered a consent decree that settled CAA claims
against a  real estate partnership and demolition
contractor regarding the defendants' demolition of
a 5-story hotel building in Atlantic City, NJ, in
1990.   The  complaint   in  the case  charged
defendants  with  violations of  the NESHAPs
pertaining  to  asbestos  removal  in demolition
operations.  The settlement provides for payment
of a civil penalty of $112,000, and includes broad
injunctive relief. The consent decree requires both
defendants  to  implement  an  asbestos control
program,  with the goal  of ensuring that the
companies' future operations are in compliance.

U.S. v. 179 South  Street (D. NJ.):  On July 29,
1994,  the  court entered  a consent decree that
enjoins the defendants from further violations of
the asbestos NESHAP. The decree also requires
the defendants to  institute an  Asbestos Control
Program, and  obligates them to pay $74,000 in
civil  penalties.    The  case  involved several
violations,  including failure to  notify EPA  of
asbestos removal,   failure to   ensure  that  the
asbestos remained wet prior to disposal, failure to
properly dispose of the asbestos and failure to
comply with previously issued compliance orders.
CLEAN WATER ACT

U.S. v.  PRASA:  During FY94, EPA filed four
more quarterly  Motions   to  Enforce  in  this
enforcement  action  against the  Puerto  Rico
Aqueduct and Sewer Authority (PRASA). In these
motions, EPA  sought a total  of $284,000 in
penalties from  PRASA based  on violations of
provisions of the 1985 and  1988 consent decrees
entered  in the action.  Substantial penalties result
from PRASA's noncompliance with the "alternate
power"  and "sludge handling" provisions of the
1985 Court Order.  EPA has been filing quarterly
Motions to Enforce  the   requirements  of the
consent decrees against PRASA since  January
1989, pursuant  to a "preclusion order" from the
Court that violations be promptly identified. The
motions  allege  violations  based on  the  Court-
appointed Monitor's quarterly compliance reports.
In the 24 Motions  filed to date, EPA has sought
nearly $3.3  million in noncompliance penalties
from PRASA.  In  FY94, PRASA paid close to
$1.5  million  in  judicial   and  administrative
penalties for CWA and consent decree violations
at its various facilities.

U.S. v. City ofHoboken (D. NJ.): On September
13, 1994, the Court entered a stipulation and order
in this case. Under the stipulation, the Hoboken,
Union   City, Weehawken  Sewerage  Authority
(HUCWSA) agreed to pay stipulated penalties in
the amount of $2.8 million for its violations of a
January  1991 consent decree entered in this action.
Of this  amount, $1,152,000 will be paid to the
EPA; $850,000 will be paid to the  New Jersey
Department of Environmental Protection, and the
balance  will be paid to the  Interstate  Sanitation
Commission.

In  re   Cheeseborough Ponds   Manufacturing
Corp.:    On March 31,  1994,  EPA  issued an
administrative   order  on  consent   against
Cheeseborough Ponds, which assessed a penalty of
$105,000 in administrative penalties under CWA
§309(g).  The  company owns and  operates  a
wastewater treatment plant  at its manufacturing
                                             A-4

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
facility in Las  Piedras,  Puerto  Rico, which has
effluent discharges into  Los Muertos Creek.  In
March  1993,  EPA  issued  an  administrative
complaint alleging  violations  of  Respondent's
NPDES  permit between  1989  and  1993  and
proposing  the  assessment  of   $125,000  in
administrative penalties.

SDWA

U.S. v. Kennemuth (dfbla  Moose Oil) (W.D.
N.Y.):   On June 1, 1994, the court entered  a
Default Judgment requiring the defendant to plug
75 injection wells in Allegheny County, NY, in
accordance with a previously approved plugging
and  abandonment plan,  and the  payment  of
$138,095 in civil penalties.

U.S. v. Wasson & Resis (W.D.. N.Y.):  On April
26,  1994, a  complaint  was  filed in the court
alleging that Wasson & Regis was in violation of
an administrative order issued by EPA. The order
was  to enforce the financial responsibility, casing
and  cementing  and closure requirements of the
underground  injection control (UIC) program of
the  Safe Drinking Water Act  against Class II
enhanced  recovery  injection wells owned  and
operated by defendants in Allegheny County, NY,
The   judicial  complaint   seeks   to  compel
defendants' compliance  with the administrative
order and seeks penalties for past violations of the
substantive requirements of the UIC program and
the administrative order.

In re PRASA:  On September 30, 1994 the EPA
issued   four   CACOs    that   resolved   four
administrative penalty  actions  against  PRASA
under §1414(g)(3) of the Safe Drinking Water Act
(SDWA) for violations  of  the Surface Water
Treatment  Rule (SWTR).   The  four  CACOs
assessed  a collective administrative penalty of
$15,000 and established  new compliance dates by
which PRASA must install filtration. PRASA had
failed  to  comply  with  previous administrative
compliance   orders  requiring  that  it  initiate
filtration pursuant to the SWTR at four of its
public water supplies.
U.S. v. Melvin Blum: The President of Burlington
Bio-Medical  Corporation was found  guilty on
August 8, 1994 on  two counts  of conspiring to
obstruct an EPA investigation and three counts of
falsifying  pesticide  records  submitted to EPA
under FIFRA. A codefendant pled guilty on May
19, 1994 to  FIFRA violations.  On October 31,
1994, Melvin Blum was sentenced to 5 months
imprisonment, to  be followed by  5 months of
home confinement and  2 years of probation,  and
fined   $10,000.     His  codefendant,  Charles
Monteleone,  was given  1 year of probation and a
$25 fine.

RCRA

U.S. v. Eastman Kodak (N.D. N.Y.): On October
7, 1994, EPA lodged a consent decree with the
court   to  resolve  various   RCRA  violations
concerning   Eastman   Kodak   Corporation's
Rochester, NY, facility.  Under the settlement,
Kodak agreed to upgrade  miles  of industrial
sewers and  reduce  the discharge  of hazardous
wastes.   Kodak  agreed to an  $8 million civil
penalty, and  will spend millions of dollars more to
inspect, repair and upgrade an estimated 31 miles
of industrial  sewers at the facility, and will correct
a series of other violations.  Kodak violated RCRA
by failing to identify hazardous wastes generated
at the Kodak Park facility, and by allowing the
unlawful disposal of various hazardous  wastes
through leaks in  the facility's industrial sewer.
Kodak will be permitted to reduce the penalty by
up   to   $3   million   by  implementing  six
environmental projects worth at least $12 million
to reduce hazardous wastes in  its  2,200 acre
Kodak Park.  The aggregate reduction is expected
to exceed 2.3 million pounds of pollutants by the
year 2001, which should improve the water quality
of  the  Genessee  River and   air  quality  in
northwestern New York.

In addition to its  other RCRA violations, Kodak
failed to obtain a permit for an incinerator used to
treat its industrial wastewater sludge, and failed to
disclose   both  hazardous  and   solid   waste
management units that should have been included
in Kodak Park's RCRA permit. Kodak also failed
to  comply  with  several  of its  RCRA  permit
                                             A-5

-------
            1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
conditions, and additionally committed violations
of regulations covering the import and export of
hazardous wastes and the proper closure of certain
underground storage tanks.

Jn the Matter of Redound Industries, Inc. dlbla
Interflo Technologies and Liqui-Mark, et al.: On
June   24,   1994,   EPA  issued  a  unilateral
administrative order pursuant to RCRA §7003 to
Redound, its President Irving Wolbrom, and Fil
Realty Ltd. This order directs the Respondents to
perform numerous tasks at various facilities owned
or operated by them to abate an imminent and
substantial hazard  to  the  environment,  their
employees and surrounding  areas.  Respondents
are engaged in the manufacture of water-based and
alcohol-based marking pens, ballpoint pens and a
variety of porous plastic products.  They conduct
their business at several facilities in Greenpoint,
Brooklyn, and Westbury,  Long Island.   All  of
these  facilities  generate   hazardous  wastes.
Nevertheless, none  of the Respondents had ever
notified EPA or the State of New York, pursuant
to the requirements of RCRA  §3010,  of  their
hazardous waste activities.

U.S. v. BCF Corp. (E.D. N.Y.):  On May 4, 1994,
the court entered a consent decree executed by the
United States and BCF, a used oil refiner located
in Brooklyn, NY. The decree addresses violations
of RCRA requirements  at  the facility, which
handled  waste  oil  contaminated with hazardous
waste although it was not  authorized to do so.
The  settlement includes detailed provisions for
operation of the facility so as to ensure that no
contaminated waste oil  will be received in the
future.  The decree  also provides for payment of
$100,000 civil penalty to resolve the  past
violations.

In the Matter of Puerto Rico Sun Oil Company:
On June 14, 1994, EPA issued  an administrative
order on consent pursuant to RCRA §3008(h) to
Puerto Rico Sun Oil. The order requires PRSO to
investigate 17 solid waste management units/areas
at its facility to determine the nature and extent of
any possible contamination from these units/areas.
The PRSO refinery, formerly known as Yabucoa
Sun Oil, was the subject of a Corrective Action
order issued unilaterally by EPA in 1992.

In the Matter of PPG Industries, Inc.:  On May
27,   1994,   EPA  issued  an   administrative
Modification/Amendment on consent to a 1990
RCRA §3008(h) corrective action consent order to
PPG  Industries,  Inc.    As a  result  of  the
development of  groundwater monitoring  wells,
purging and sampling of groundwater monitoring
wells and aquifer testing at its Guayanilla, Puerto
Rico facility, PPG generated wastewater for which
it  needed  storage.   The   company  requested
approval of a temporary storage unit for 1 year.
Approval of the unit  was  published for public
notice and comment; no comments were received.
The  Amendment/Modification   specifies  the
conditions under which the temporary storage unit
is  required to operate and the contingency plan
which will be implemented in the event of a spill
or discharge from the unit.

In   re  Westchester   County,   New   York,
Sportsmen's Center:  On January 28, 1994, EPA
issued an administrative order on  consent  to the
County  of  Westchester.  The order was issued
pursuant to RCRA §7003, and requires the County
to   assess   the   nature  and   extent   of  the
contamination (predominantly lead) from shooting
activities at the Sportsmen's Center located in the
Blue  Mountain  Reservation,  in  the  town  of
Cortlandt, NY. The County is further required to
design and implement a plan for the remediation
of the contamination, and to design and implement
a  plan  to  prevent the re-contamination of  the
facility in the future.

In the Matter of Gaseteria  Oil Corp.:  On April
28,   1994,   EPA  settled  an   administrative
enforcement   action   against   Gaseteria   Oil
Corporation.  The 1992 complaint which initiated
the action alleged that  Gaseteria violated RCRA
Subtitle I requirements concerning  underground
storage  tanks (USTs).   Under the settlement the
company agreed  to the  assessment of  a civil
penalty of $3 million; the parties further agreed to
a $339,000 settlement of this assessed penalty in
the  context  of  the  company's  reorganization
pursuant to Chapter 11  of the Bankruptcy Code.
                                             A-6

-------
                                                                                       M
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT!
TSCA

In  the  Matter  of PIC Americas,  Inc.:   In
December 1993, an EPA administrative law judge
issued a Decision and order assessing the full
$85,000  civil penalty sought  by EPA  in an
EPCRA enforcement action against DIG Americas,
Inc.   DIG  imports  chemical  substances  for
commercial purposes.  Based on an inspection of
its  Fort  Lee,  NJ,  facility  EPA  issued  an
administrative complaint citing the company for
failures to submit, by the December 1986 deadline,
the required  Inventory Update reports for five
chemical   substances   imported  during   the
company's 1985 fiscal year.  The judge had, in
December  1991, issued an order finding in favor
of EPA on the issue of DIC's liability.  A hearing
on  the question of, the amount of the civil penalty
to be paid.was held in March 1992.  This case is
now  before  the  Environmental  Appeals Board
awaiting a decision on Respondent's appeal.

In  the Matter of SUNY-New Paltz:  In  October
1993, EPA entered into an administrative consent
agreement and order with the State University of
New York at New Paltz. The order required the
University to pay a civil penalty  of $90,750 for
various TSCA violations,  and replace all  PCB
transformers  at the campus.  The action arose out
of an incident in December 1991:  an electrical
surge resulted in PCB transformer explosions and
damage to six  separate buildings.   Based on
subsequent inspections  EPA determined SUNY
had failed to  comply with TSCA PCB regulations;
an administrative complaint was issued in June of
 1992.  In  addition  to the penalty, the settlement
provided for the removal and proper disposal of 10
PCB transformers from the campus by November
 31, 1994.

In the Matter of Cray Valley Products, Inc.: On
 September 1, 1994, EPA entered into a CACO
 with  Cray  Valley  Products,  Inc.   The  1992
 administrative complaint which initiated the case
 charged the company with eight counts of TSCA
 violations concerning its failure to comply with
 premanufacturing notice and chemical importation
 requirements. Under the CACO the company will
 pay a civil penalty of $175,000.
In the  Matter of Eastman  Kodak  Co.:   On
October 25, 1993, EPA finalized settlement of an
administrative case against Kodak. The complaint,
filed  in  1992,  charged the company with ten
violations of the TSCA PCB regulations.  Under
the settlement, Kodak paid  a penalty of $42,000
and, in addition, undertook an environmentally
beneficial expenditure by removing and properly
disposing of 17 PCB Transformers at a cost of
approximately $4 million. The removal work was
completed by  September 30, 1994.   On March
18,1994, EPA entered into another administrative
consent order  with Kodak, which required the
company to pay $13,750. The complaint in that
case,  issued on December  9, 1993, charged the
company with one count of  unauthorized disposal
of PCBs, based on a voluntary disclosure made by
Kodak  on  July  1,   1993.    In addition   to
emphasizing   the   importance   of  pollution
prevention, the settlement, which was negotiated
during FY94, emphasizes the federal government's
commitment  to  cleaning  up  aging  industrial
facilities, the strong deterrent effect of a large
penalty, the efficiencies resulting from prefiline
negotiations, the ability of multimedia inspections
to serve as a catalyst for changing the ways that
companies do  business,   and  the  outstanding
cooperative partnership with  New York State
throughout the entire process.

In the Matter of Sharp Electronics Corporation:
On December  10,  1993, EPA  issued a consent
agreement  and  order  to  Sharp  Electronics
Corporation resolving an  administrative TSCA
enforcement action brought pursuant to TSCA §§
 5 and 13. The complaint in  this action cited Sharp
 for importing chemicals which were not on the
 TSCA Inventory without prior notification to EPA
 of its  intent  to  import,  and for  inaccurately
 certifying to U.S. Customs officials that  it was
 importing the  chemicals  in compliance with
 TSCA.   Under the settlement  agreement, the
 company will pay a $685,000 penalty.  Sharp also
 agreed  to  carry out  several  environmentally
 benefical projects at a cost  in excess of $800,000.
 Sharp  agreed to develop and implement  TSCA
 training programs  for its  company and  for  the
 electronic trade, to upgrade its internal compliance
 program, to produce a compliance manual and a
                                              A-7

-------
         FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 video  presentation   on  TSCA  and  Sharp's
 compliance programs and to undertake an internal
 TSCA audit of its last 5 years of operation.

 In the Matter of General Electric Company:  On
 December 30,1993, EPA issued an administrative
 complaint to the General Electric Company (GE)
 charging multiple violations of TSCA, and seeking
 a penalty of $139,875.  GE operates  a research
 and development facility in Niskayuna, NY, where
 for many years it conducted research on PCBs
 without an approval from EPA. Since research on
 PCBs is deemed to  be a form of disposal,  the
 complaint charges GE with unpermitted disposal.
 The complaint also charges that GE manufactured,
 processed, and distributed  PCBs  without  the
 requisite EPA permits, and failed to prepare annual
 documents concerning the disposition of its PCB
 materials.  The matter was settled in June 1994,
 with GE's agreement to pay a penalty of $70,000
 and   maintain   compliance  with  the  TSCA
 requirements.

 In the Matter of Presbyterian Homes of New
 Jersey Foundation:  On March 31, 1994, EPA
 issued a  two count complaint to  Presbyterian
 Homes of New Jersey for its failure to maintain
 records of  quarterly inspections  of its  PCB
 Transformer,  and  its  failure  to compile  and
 maintain annual documents on  the disposition of
 PCBs and PCB-items. The complaint proposed a
 penalty of $197,000.  The violations were detected
 during an inspection  in 1993 at the Foundation's
 Hightstown, NJ facility.   EPA discovered  that
 Respondent had not compiled any of the requisite
 documents for any of its several PCB transformers.

 U.S.  v.  State  of New  York  Department  of
 Transportation (N.D. N.Y.): On March 23, 1994,
 the court  entered  a  consent decree settling  an
 action brought by EPA under TSCA against the
 New  York State  Department  of Transportation.
 The Transportation Department had sought  and
 received a temporary  EPA approval to dispose of
 the dredged material.  The approval was granted,
 but the Department failed to live up  to its terms,
as well as the terms of a later  administrative
consent order reached with EPA. The complaint
filed  in  this  case  cited  the  Department  for
 violations of EPA's PCB regulations as well as of
 the TSCA approval and the administrative consent
 order.  An injunctive order will ensure that the
 Department properly  maintains two disposal  sites
 for PCB-contaminated material dredged from the
 Hudson River.

 In the Matter of New York State Department of
 Mental Health: On June 29, 1994, EPA issued an
 administrative complaint to the New York State
 Office of Mental Health citing violations of the
 TSCA PCB  regulations and  proposing  a civil
 penalty  of  $215,000.    The Mental  Health
 Department  owns   and   operates  the   Bronx
 Psychiatric Center in  New York City.  During an
 inspection  of the Center  EPA found  that  the
 Department had failed to compile and maintain
 required records and  logs concerning inspections
 and  the  disposition of PCBs  and had failed to
 dispose of PCBs in an authorized manner.

 In re Corporation Azucarera de Puerto Rico:  On
 September 27,1994, EPA issued an administrative
 complaint under TSCA against the Corporacion
 Azucarera de Puerto  Rico (Sugar Corporation of
 Puerto Rico).   The  complaint cited nineteen
 violations of  TSCA  §6(e)  and proposed a civil
 penalty of $798,000.  The  violations occurred at
 four different facilities owned and operated by the
 Respondent in  Aguada, Arecibo,  Guanica  and
 Mercedita,  Puerto Rico.   Inspections of these
 facilities  revealed that Respondent  had numerous
 violations of inspection, record keeping, disposal,
 marking and registration requirements concerning
 PCB Transformers.

In re Edsewater Associates:  On September  30,
 1994,  EPA issued an administrative  complaint
under TSCA against Edgewater Associates for 8
 violations of  PCB regulations  at  its  facility in
Edgewater,  NJ.   The  complaint proposes a civil
penalty  of  $222,000.    EPA  conducted   an
 inspection of the  facility in December 1993, to
determine whether Respondent was in compliance.
The  inspection was conducted because EPA  had
become aware that Respondent had been engaged
in PCB waste handling activities and storing PCB
contaminated oil at its facility.
                                            A-8

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
TSCA  §8  Inventory  Update  Enforcement
Initiative:   In June  1994, EPA  issued  eight
administrative complaints as part of a nationwide
initiative targeting TSCA  §8 Inventory Update
Rule  violators.   The  cases  were filed against:
Alnor Chemical, Inc., Valley Stream, NY, with a
proposed penalty of $85,000; Browning Chemical
Corp., White Plains, NY, $136,000; Capelle, Inc.,
Scarsdale, NY,  $12,000; Coastal Eagle Point Oil
Co., Westville, NJ, $374,000; Kyowa Hakko USA,
Inc., New York, NY, $6,000; Magna-Kron Corp.,
Jackson, NJ, $17,000;  Nippon  Paint (America)
Corp., New York, NY, $18,000;  and White Cross
Corp., Rye, NY, $51,000. The violations alleged
involve  either failure to submit inventory update
forms or late submission of forms to EPA for
chemicals  these  companies manufactured  or
imported.

In the Matter of Ciba-Geigy Corporation:  On
December  17,   1993,  EPA entered  into  an
administrative  consent  order with  Ciba-Geigy
Corporation  of Ardsley, NY. The order required
the company to pay a civil penalty of $182,550 for
violations of TSCA §§  5, 8,  and  13.   The
complaint,  which  was  the  consequence  of  a
voluntary  disclosure of the  TSCA violations  by
Ciba-Geigy, was issued on November 24, 1993.

In the Matter ofOCG Microelectronics Materials,
Inc.: On December 30, 1993, EPA entered into an
administrative   consent   order   with   OCG
Microelectronics Materials, Inc. of West Paterson,
NJ.   The order required OCG to pay a civil
penalty  of $162,900 for violations of TSCA §§5
and 13.  The complaint, resulting  from a voluntary
disclosure of the TSCA violations by OCG, was
issued on September 29, 1993.

EPCRA

In the Matter of Mobil Oil Corp.: On September
29, 1994, EPA's Environmental Appeals Board
(EAB)  rejected an  appeal  by Mobil  Oil  from
decisions by two EPA Administrative Law Judges
(ALJs).   In  December 1993, Senior ALJ Gerald
Harwood ruled  for EPA in this EPCRA action.
Judge  Harwood  determined that  Mobil  had
unreasonably delayed  in  notifying  the  Local
Emergency Planning Commission (LEPC) of a
reportable release of sulfur dioxide; that Mobil
could have notified the LEPC  at  least 3 days
earlier than it did; and, accordingly, that Mobil
should pay a penalty for each of the 3 days during
which noncompliance continued. This was the first
time  EPA had  sought and  been  awarded  a
multiple-day  penalty assessment in  an EPCRA
case.

In the Matter of Agway Petroleum Corporation:
On August 4, 1994, EPA issued an administrative
complaint against  Agway Petroleum Corporation
for violations of the  regulations  promulgated
pursuant to §312 of EPCRA. The complaint cited
violations of EPCRA and assessed a proposed civil
penalty of $1,926,600.  Agway  Petroleum owns
and operates numerous  facilities  throughout New
York and New Jersey. The complaint cites Agway
for its failure to submit Tier  One or Tier Two
Forms for at least one of five possible petroleum-
related hazardous chemicals found at each of 164
of the company's facilities.  The violations were
with respect to the 1990 and 1991 reporting years.

In the Matter of Rich Products  Corp.:  On
November   12,   1993,   EPA   executed   an
administrative consent  agreement  and  consent
order  (CACO) with Rich  Products Corp.   The
settlement resolved an action commenced in July
1992 citing the company for five violations of the
EPCRA  reporting requirements  relating to the
chemicals phosphoric acid and sodium hydroxide
"otherwise used"  at the company's Buffalo, NY,
facility for the 1987 through 1989 reporting years.
Pursuant to the settlement, Rich Products will pay
a  penalty of $34,425  and,  in addition,  will
undertake an SEP in  the  form of the design,
installation and startup  of  a Modified  Clean-In-
Place  system.  This  system, which will cost the
company about $64,000,  will serve  to reduce
phosphoric acid usage  at the facility; the project
was required  to be completed by November 30,
1994.

In the Matter ofNTU Circuits, Inc.: In February
1994,  EPA issued an administrative consent order
to NTU Circuits, Inc.  requiring  the company to
pay a  civil penalty of $97,500 for its violations of
                                            A-9

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
EPCRA §§ 311, 312, and 313.  NTU had stored
and "otherwise used" sulfuric acid and ammonia in
quantities exceeding the reporting thresholds at its
facility in Bayshore, NY, since  1986.  NTU had
failed to  submit MSDSs  and  emergency  and
hazardous chemical inventory forms (Tier I or Tier
II forms)  to  the appropriate  local  and  state
agencies.  NTU also had failed to submit toxic
chemical release forms (Form R) to EPA and the
State of New York for four out of 5 years from
1988 to 1992.

In the Matter  of R&F Alloy Wires,  Inc.:  In
March 1994, an EPA Administrative Law Judge
issued an order granting EPA's Motion  for Partial
Accelerated Decision on the question of liability in
an EPCRA enforcement action against R&F Alloy
Wires, Inc.  The company was held  liable for
eleven violations of EPCRA. The complaint, filed
in 1993, assessed a civil penalty  of $79,000. The
violations  at R&F involved its  failure to file a
Form R  in  a  timely  manner for  chemicals
manufactured,  processed  or otherwise used in
amounts   exceeding   the   threshold  reporting
requirements. R&F failed to submit Forms R in a
timely manner for ammonia, copper, and 1,1,1-
trichloroethane  in 1988, 1989,  1990 and 1991.
The case was settled in September 1994 for a cash
penalty of $25,000 plus a commitment by R&F to
implement  a substantial  SEP,  valued at  over
$55,000.

In the Matter  of Silverton Marine Corporation:
On June 20, 1994 EPA issued an administrative
complaint against Silverton Marine Corporation for
violations of the regulations promulgated pursuant
to §313 of EPCRA.   The complaint cited six
violations of EPCRA and assessed a proposed civil
penalty of $129,441.  Silverton Marine owns and
operates a facility in Millvile, NJ. The complaint
cites  Silverton  for  failure  to submit  Toxic
Chemical Release Inventory Reporting Forms to
EPA and the State of New Jersey for styrene and
acetone which  were  manufactured,  imported,
processed,  or  otherwise used at the facility in
quantities  exceeding the applicable  thresholds.
The  violations  were with respect  to  the 1989,
1990, and 1991 reporting years.
In re Rexon  Technology Corp.:  On September
15, 1994, EPA issued a complaint proposing a
penalty   of  $102,000  Dollars  against  Rexon
Technology Corp., Wayne, NJ, for violations of
EPCRA §313. Specifically, the complaint alleged
that the  corporation had failed to submit to EPA,
as required by EPCRA, Toxic Chemical Release
Inventory Reporting Forms (Forms R) for Methyl
Chloroform and Freon 113 for the 1990 through
1992 reporting years.

In re Goodyear  Tire  &  Rubber  Co.:   On
September  30,   1994,   EPA  II  issued   an
administrative complaint  to The Goodyear Tire &
Rubber  Company  for  violations  of CERCLA
§103(a)  and EPCRA  §304.   Goodyear failed to
immediately notify the appropriate officials after
releases  of vinyl chloride on three occasions from
its facility in Niagara Falls, NY. EPA is seeking
$165,900 in penalties for these violations.  The
company did not notify  the NRC,  SERC,  and
LEPC of vinyl chloride  releases  on August 17,
1992, July  26, 1993, and August 2,  1993  until
about 7-31 hours  after  the releases  occurred.
Further,  the releases contained from 2-19 times the
reportable quantities for vinyl chloride.

Catano  EPCRA  Enforcement Settlements:  On
September 30, 1994,  EPA executed a settlement
resolving five administrative enforcement actions
brought  against facilities  operating in the Catano
region of Puerto Rico. These cases were part of
EPA's Catano geographic initiative carried out
over the previous  2  years.   The  complaints in
those  five cases alleged violations of EPCRA §§
311,  312, and 313.  The  settlement provides for
the five companies to jointly pay a civil penalty of
$90,000.  Under the settlement  they will also
implement SEPs valued at $210,000 in the form of
training  and  education  programs for both the
regulated and the local community; and provide
$100,000 worth of emergency response equipment
to the Catano  Health Center.  The five companies
are: American Chemical, Inc.; Easton, Inc.; Goya
de Puerto Rico, Inc.; Island Can Corp.; and Water
Treatment Specialists, Inc.

In the Matter of National Can Puerto Rico, Inc.:
In August  1994, EPA issued an  administrative
                                            A-10

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
complaint against National Can for violations of
the regulations promulgated pursuant .to §312 of
EPCRA-  The complaint cited twelve violations of
EPCRA  and assessed a  proposed penalty of
$300,000. National Can owns and operates a can
manufacturing plant in the Catano area of Puerto
Rico. The complaint cites National Can for failure
to submit Tier I or Tier II forms to the fire
department,  LEPC and SERC  for the extremely
hazardous substance,  sulfuric  acid, which was
present at the facility in  amounts  equal  to or
greater than the  reporting  threshold in the years
1990 through 1993.

In the Matter of Petroleum Chemical Corp.: In
June  1994,  EPA  issued   an  administrative
complaint against Petroleum Chemical Corporation
for  violations of the  regulations promulgated
pursuant  to  EPCRA  §§  312  and 313.   The
complaint cited nine violations of EPCRA §312,
four violations of §313  of EPCRA and assessed a
total proposed penalty  of  $245,000.  Petroleum
Chemical owns  and operates  a facility  in  the
Catano area of Puerto Rico.  The complaint cites
Petroleum Chemical for failure  to submit Tier I or
Tier II forms to  the local fire department, LEPC
and SERC for the extremely hazardous substance,
phosphorus   pentoxide,   and   the  hazardous
chemicals   asbestos,   kerosene   asphalt  and
aluminum paste,  which  were present at the facility
in amounts equal to or greater than the reporting
thresholds in the years 1987 through  1992.  In
addition, the complaint cites  Petroleum Chemical
for  failure  to submit  Toxic Chemical  Release
Inventory Forms to EPA and the Commonwealth
of Puerto Rico  for friable asbestos which was
processed at the  facility in quantities exceeding
applicable thresholds for the years 1988  through
1992.

In re Hess Oil Virgin Islands:  On June 21, 1994,
EPA issued  an  eleven-count  administrative
complaint   against  Hess   Oil  Virgin   Islands
Corporation  citing EPCRA  violations.    The
complaint alleges that Hess failed to submit in  a
timely manner the required Form R for each of
five chemicals;  and alleges that Hess  failed to
report a reasonable estimate  of its fugitive air
emissions for another.  The complaint alleges these
violations for calendar years 1988 through 1990
and  seeks  a civil penalty  of $252,000.  This
complaint arose out of an earlier consolidated
multimedia:  inspection at the facility.

In re Statewide Refrigerated Services, Inc.:  On
September 30,1994, EPA issued an administrative
complaint to Statewide Refrigerated Services, Inc.
for violations of CERCLA  §103(a) and EPCRA
§§ 304,  311,  and  312.    Statewide  failed  to
immediately notify the appropriate officials of a
release that occurred at its Rochester, NY, facility.
EPA  is seeking $147,120  in penalties for these
violations.  The company did not notify the NRC,
SERC, and LEPC of an ammonia  release that
occurred on November 12, 1993 until about 94
hours after  the  release occurred.  Further,  the
company had failed to submit a MSDS and annual
Tier I/II forms as required by EPCRA §§ 311 and
312.

In the Matter of Freeman Industries, Inc.:  On
September 29, 1994, EPA issued an administrative
complaint proposing a penalty of $108,900 against
Freeman Industries, Inc. of Tuckahoe, NY,  for
violations  of   EPCRA   §§   311   and  312.
Specifically, the complaint  alleges that Freeman
failed  to  submit the MSOSs, for bromine,  an
extremely hazardous substance, to the SERC for
New York, the LEPC for Westchester County, and
the Fire Department for the Town of Eastchester,
as it was required to do by January of 1991.  In
addition Freeman failed to submit the Emergency
and Hazardous Chemical Inventory Forms to these
agencies from 1991  through 1994.

In re E.I. DuPont de Nemours and Co.: On May
17,  1994,  EPA  issued  a  seven-count civil
administrative   complaint   against   DuPont's
Chambers Works, Deepwater, NJ, facility, alleging
violations of EPCRA §313.  The complaint was
the  result of  an  EPCRA §313 Data  Quality
Assurance inspection conducted at the facility on
July 21,  1993 as part of a Regional multi-media
investigation.   It alleged that DuPont failed to
submit   in  a  timely  manner  Forms   R  for
nitrobenzene for the years 1988, 1989, 1990, 1991,
and 1992, and  for formaldehyde for  1991.  The
complaint sought penalties of $142,000.
                                             A-ll

-------
      IFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
CERCLA

The Lipari Site: On March 16, 1994, the U.S.
lodged  a  proposed  consent decree  in  partial
resolution of U.S., et al. v. Rohm & Haas, et al.,
an injunctive relief and cost recovery case arising
out of EPA's  work  at the Lipari  Landfill site,
which is the number one site on the NPL.  Under
the decree, Rohm & Haas,  one of the primary
responsible parties at the site, which is located in
Mantua Township, NJ, agreed to perform the ROD
III  remedy at  the  Site.   The site  received
hazardous industrial  wastes  from 1958 through
early  1971.   Rohm  &  Haas  was the largest
contributor of wastes to the Site.

On April 15, 1994,  the court entered a separate
consent decree in this case, which resolved the
liability of Rohm & Haas and two other PRPs,
Owens-Illinois and ManorCare, for ROD I, ROD
II, and two additional components of ROD III at
the Lipari site. Because the portion of the remedy
settled  in  this decree  had  been  essentially
completed by EPA, the three defendants agreed to
cash-out payments to EPA and the State of New
Jersey valued at $52,939,375. In September 1994,
EPA signed a settlement with Mr. Nick Lipari, the
owner of the Lipari  Site, resolving his liability.
Under this proposed  settlement,  Mr.  Lipari,
through his insurers,  has  agreed to pay  to  the
United States and the State a total of $1.3 million.

U.S. v. CDMG Realty Co., et al. (D. N.J.):  On
December 2, 1994,  the court entered  a consent
decree,  in  partial resolution of this  CERCLA
action   concerning    the   Sharkey's   Landfill
Superfund  site,  located  in  the Townships  of
Parsipanny-Troy Hills and East Hanover, NJ. The
decree involves various settling parties, including
two owner  parties, twenty-nine non-owner parties
and  twelve de  minimis parties.   The decree
requires  that  the  settling parties  design  and
construct the remedy and perform the necessary
operation and  maintenance.   This  work has  an
estimated present value  of approximately $42
million. The settlement also provides that parties
reimburse EPA $1.75 million of its past costs and
up  to  $250,000 of  its Supervisory  Costs and
reimburse the State of New Jersey $300,000 of its
past costs.  The de minimis Settling Parties have
agreed to pay $1,390,034 to the  other settling
parties towards  the  cost  of implementing  the
remedial action.

U.S. v, Vineland Chemical Company, et al.  (D.
N.J.): In March 1994, the U.S. entered a consent
decree pursuant to CERCLA and RCRA, resolving
litigation between the United States and Vineland
Chemical Company  and  its owners/operators,
Miriam  Schwerdtle and  the Estate of Arthur
Schwerdtle.  In the consent decree the defendants
confessed liability for $76 million under CERCLA
and agreed to  surrender all but certain specified
assets to the United States  for  payment of an
earlier RCRA penalty  judgment  and for  costs
incurred and to be incurred by the United States in
performing  all  response  actions pursuant  to
CERCLA. The settlement included agreement by
the defendants to bring money back from two
overseas trusts which the United States alleged had
been established to prevent EPA from recovering
its CERCLA costs.

U.S. v. The Carborundum Company, et al.  (D.
N.J.): On March 30, 1994, a consent decree was
lodged in the court which partially settles EPA's
cost recovery  claims  relating to  the Caldwell
Trucking Company Superfund Site in  Fairfield
Township,  NJ.  The  nine  settling  defendants
agreed to pay  $2.46 million  for EPA's past and
future costs  and  also agreed  to perform  all
scheduled remedial and natural resource restoration
work at  the site,  valued at  an  additional  $32
million.   Under the  decree,  the  State of New
Jersey will also receive its first natural resource
damage  payment under CERCLA  and the U.S.
Department   of  the  Interior   will   receive
compensation for its  assessment  and  monitoring
costs.

In  the   Matter  of  the   Frontier  Chemical
Superfund Site:  On July 5, 1994, EPA issued an
administrative consent order for the removal of all
wastes contained in tanks at the Frontier Chemical
Superfund  site located in  Niagara  Falls,  NY.
There are approximately 45 tanks at  the  Site
containing over 360,000 gallons  of waste.   The
                                            A-12

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 order was issued to 31 PRPs; the work is expected
 to cost about $3.6 million.

 U.S. v. Ciba-Geiev Corp (D. N.Y.):  On April 21,
 1994, the court entered a consent decree settling
 EPA's  CERCLA  claims   against  Ciba-Geigy
 Corporation.   The  settlement provides for the
 performance,  by Ciba-Geigy, of the remedial
 design,   the  remedial  action,   operation  &
 maintenance and post-remediation monitoring for
 the first operable unit (groundwater) at the Ciba-
 Geigy Superfund Site  in Toms River, NJ.  The
 estimated cost of the work is approximately $60
 million.  In addition to providing that Ciba-Geigy
 undertake the response work, the decree calls for
 the company to reimburse  the United States for
 $8.4 million in past response costs incurred by the
 U.S. with respect to the Site, and future response
 costs, including costs to be incurred by EPA with
 respect to overseeing the work to be performed by
 Ciba-Geigy.

In the Matter of Diamond Alkali Superfund Site:
 On April 20, 1994, EPA issued an administrative
 consent  order  pursuant to  which  Occidental
 Chemical Company agrees to undertake the RI/FS
 for the Passaic River  Study Area portion of the
 Diamond  Alkali Superfund Site in Newark, NJ.
 Remedial action on the property where the facility
 was located has been  undertaken by Occidental
 pursuant to a judicial consent decree.  Because of
 the presence of dioxin in  the sediments of the
Passaic  River, EPA  determined  that  a RI/FS
 should be undertaken for  areas  in  the  River
 adjacent to the site. The Passaic River Study Area
 identified in the RI/FS is a six-mile area up-River
from   the   confluence  of  the   Passaic  and
Hackensack Rivers.  The study is expected to cost
$10 million.

In  the Matter of Liberty  Industrial Finishing
Site:   On August  30,  1994,  EPA  issued an
administrative  consent  order to 9  PRPs for the
removal  of, inter alia, soils contaminated  with
PCBs at  the Liberty   Industrial  Finishing  Site,
Village of Farmingdale, NY. At the same time, a
second administrative order was issued unilaterally
to six non-settling PRPs requiring them to perform
the same removal  action  and  participate and
coordinate with the recipients of the consent order.
The recipients  of the consent  order include two
federal agencies, the Department of Defense and
the General Services Administration.  All the PRPs
are current or former owners or operators  of the
facility.   The  work is expected to cost  about
$500,000.

In   re   ENRX  and  Buffalo   Warehousing
Superfund Sites:  On September 30, 1994, EPA
entered into an administrative settlement to recover
over $1  million from more than 90 PRPs at these
two sites, pursuant to  §122(h)  of  CERCLA.
Beginning in September 1989  and concluding in
March 1992,  EPA performed a removal action at
the ENRX Site which included such activities as
the securing,  segregating, sampling, transporting
and off-site disposal of 400 drums and containers,
and the treatment and disposal  of materials  found
in  various tanks.   Starting in July  1991  and
concluding in April 1992, EPA also performed a
removal action at the Buffalo Warehousing Site.
The removal  action at this  site consisted of the
securing, segregating, sampling, transporting and
off-site disposal of approximately 66 drums and
containers.  The settling PRPs are parties who
generated  waste which was disposed of at the two
sites.

In  re York Oil Company Superfund Site:  On
September 30, 1994,  EPA  issued  a unilateral
administrative order in connection with the York
Oil Company Superfund Site in the Town of
Moira, NY.    The  order  requires  respondent
Aluminum Company  of  America  (Alcoa),  a
generator  PRP, to  undertake certain removal
activities there.  Because of the deteriorated and/or
unstable condition of the tanks and drums at this
site, EPA  issued the order to Alcoa requiring the
company to undertake a removal action at the Site
pursuant  to  CERCLA.  This removal  action
includes the  characterization,  removal, disposal
and/or treatment of on-Site tanks and drums and
their  contents,  and  is expected to  cost  about
$200,000.

InreA&YRealty Corp.: On  September 29, 1994,
EPA reached an administrative settlement with the
A&Y Realty  Corporation mandating  the sale of
                                            A-13

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
real property that constitutes part of the Radium
Chemical Company (RCC) Superfund Site located
in New York City. The proceeds of the sale (after
satisfaction  of prior tax  obligations  and  the
expenses  of sale)  will  be reimbursed to  the
Superfund. The settlement agreement specifies the
terms upon which the real property is to be sold.
Contemporaneously   with   the  administrative
settlement, the Site is being noticed in the Federal
Register for intended deletion from the National
Priorities List,  since Site remediation has been
completed.  In December 1994  the property was
sold under the agreement, realizing some $250,000
for the Superfund, and resulting in the return of
the property to full commercial use.

In re PVO International,  Inc.:  On September 30,
1994,  EPA issued an administrative order  on
consent to  PVO International Inc.   requiring
performance of a removal action at its site in
Boonton Township, NJ. Under the order PVO has
agreed to sample  and dispose of several thousand
containers, drums, vats and tanks off-site.  The
estimated cost of the work is $350,000. PVO also
has agreed to pay EPA approximately $63,000 in
past response costs, plus interest. PVO's payment
obligation will be secured by an EPA lien on the
Site,  which  will continue until  the  payment
obligation is fully satisfied.

Quanta/New   Jersey   Non-Complier   Case
Settlements:   On  March 24, 1994,  the  U.S.
District Court  for the District of  New Jersey
entered seven  consent  decrees settling EPA's
claims against 8  PRPs at the Quanta  Resources
Site in Edgewater, NJ.  The settlements provide
for reimbursement of past response costs totaling
$940,000, civil penalties and punitive damages in
an  amount  of  $800,000,  and  placement  of
$785,000 into an escrow account to finance future
removal activities at the  Site, resulting in a total
settlement  value  of $2,525,000.   The Settling
Defendants are:  Estate of James Frola, co-owner
of the property; Albert Von Dohln, co-owner of
the property;  Republic  Environmental  Systems
(New  York),   Inc.   (formerly   Chemical
Management,  Inc.);  Petroleum Tank  Cleaners;
Snyder Enterprises;  Texaco,   Inc.;  and  Total
Recovery, Inc.
In re Niagara  County Refuse Superfund Site:
On  September  23,  1994,  EPA  signed  an
administrative  order  on consent  with  11  de
minimis parties to settle their liability with respect
to the Niagara County Refuse Superfund in New
York pursuant to §122(g) of CERCLA. A ROD
was signed in September 1993 selecting a cap and
related measures as the remedy for the Site, with
a cost  presently estimated at  about $20 million.
The  de minimis settling  parties each contributed
less than one percent of the total wastes disposed
of at the Site.   These de minimis parties have
agreed  to pay $793,866  to the Superfund.  This
settlement was reached in conjunction  with a
major party consent decree, which has been signed
by the PRPs and by EPA, and is awaiting lodging
with the court.   Taken together, the de minimis
settlement and the major party settlement would
require  the settling parties to undertake the full
performance of the RD/RA; the payment of EPA's
future   response costs;   and  the  payment  of
$866,280 of EPA's past response  costs (out of
total past response costs  of $1,030,000).

In re Muratti Environmental Site:  On September
30,  1994, EPA entered into  an  administrative
cost recovery agreement  with 12 PRPs pursuant to
§122(h)(l) of CERCLA, regarding the  Muratti
Environmental Site  (Site),  located in Penuelas,
Puerto  Rico.   Under  the agreement the settling
PRPs will pay EPA $525,000 in reimbursement of
95 percent of EPA's unreimbursed past costs for
a removal action at the site.  The settling PRPs are
the generators of hazardous substances that were
disposed of at the  site, which  consists of an
abandoned, approximately 2-acre former industrial
waste disposal facility.

U.S. v. Sisno Trading International, Ltd., et al.:
On  December  10,  1993,  the court signed two
partial  consent decrees and a default judgment in
connection with the Signo Trading Superfund Site
in Mt.  Vernon, NY.  These court orders resolve an
action  brought in 1987 on behalf of EPA, seeking
recovery of response costs incurred by EPA in the
performance of a removal action at the Site, and
seeking treble damages against certain defendants
for noncompliance  with an EPA administrative
cleanup order issued in 1984.  Under the decrees,
                                             A-14

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
defendants Jack  and Charles Colbert and the
"Colbert Companies" (Signo Trading International,
Ltd., SCI Equipment and Technology, Ltd., Mount
Vernon Trade Group, Ltd., Northeast By-Products
Recycling Corp.) agreed  to  pay $22,500  as  a
penalty for  failure  to comply with  the order.
Defendants Arnold Schwartz,  Arnold Fader,  New
Island  Investors  and  Lynric Associates,  Inc.,
agreed to pay  $71,000 in past  response costs.
Finally, a default judgment  was entered  by the
court against defendant 11 Hartford Avenue, Inc.
in the  amount of $311,658.54, for costs incurred
by EPA in connection with the Site.

U.S. v. Zaklama  (D. N.J.):  On  April 25, 1994,
the District Court  of New  Jersey ordered the
owner   of a  residential  property within  the
Montclair/West Orange Superfund Site to grant
access  to EPA  for the purpose of conducting
additional  sampling  and  performing remedial
construction on the property.  Esmat Zaklama, the
absentee owner of a  residential property at the site,
refused to grant  EPA access to remediate his
property because the government had refused his
demand that it buy the property or compensate
him because   he  could  not  lease  out  the
contaminated property.

U.S. v. Thiokol Corp. (D. N.J.):  On October 26,
1994, the court entered a judicial consent decree
between  the  United States  and Thiokol Corp.
Under  the settlement, which had  earlier  been
lodged with the court, Thiokol agreed  to conduct
remedial action, operation and maintenance and
post-remediation monitoring  for a portion of the
Rockaway Borough Site  in  New Jersey, and
reimburse the U.S. for all associated oversight
costs.  Thiokol  also  agreed  to  fund  the future
operation   and   maintenance   of   Rockaway
Borough's water  treatment system, which treats
contaminated groundwater from the  site.  The
decree also provides for recovery of approximately
half of the $2 million in total costs incurred by the
United States  at the Site, resulting  in a  total
settlement value of approximately $13  million.

U.S. v. Town of North Hempstead (E.D. N.Y.):
On September 18, 1994, a consent decree in this
case was lodged with the U.S. District Court for
the Eastern District of New York.   The decree
would settle ongoing litigation against the Town of
North Hempstead  for  recovery  of some  $2.64
million in past EPA cleanup costs incurred at the
Port Washington Landfill.  The Town is already
undertaking the remedial work at the landfill, at an
estimated cost of $45 million.

In  the  Matter of Aero Haven Airport  Site:
During FY94, EPA entered into two administrative
orders on consent pursuant  to which Owens-
Corning  Fiberglas  Corp. will perform  and fund
private removal actions to permanently close an
asbestos containing material (ACM) landfill at the
Aero Haven Airport Site.  The first order was
signed on June 27,  1994, and the second order was
signed on September 30, 1994.  In the first  order
Owens-Corning agreed to fund and  perform  an
emergency removal action to stabilize the Site by:
(1)  installing  high  visibility  fencing around
portions of the Site, (2) covering exposed areas of
ACM with clean  fill  or soil,  and  (3) posting
warning signs.  The second order was signed  on
September 30, 1994, pursuant to  which Owens-
Corning has agreed to properly and permanently
close the  site  by:  (1) consolidating the current
18.5 acres of ACM and satellite piles of ACM into
a fill area (or approximately 122,000 cubic yards
of ACM), (2) placing a cover over the ACM, and
(3) installing  vegetation and erosion  and run-off
system. The total cost of the work required under
both orders is in excess of $1.2 million.

17.5. v. Wheaton Industries. Inc. (D. N.J.): The
court entered  a consent decree settling EPA's
complaint brought under §107 of CERCLA against
Wheaton  Industries, Inc.  The consent decree
requires  Wheaton  to  pay $4 million in  full
settlement of the litigation. The complaint sought
recovery of past and future response costs incurred
by  the United States at the  Williams Property
Superfund site, located in Cape May County, NJ.
The State of New Jersey joined in this lawsuit to
recover state funds expended on this Site.

MULTIMEDIA CASES

In   the   Matter   of  Brookhaven  National
Laboratories and  Associated Universities, Inc.:
                                             A-15

-------
            1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
During 1994 Region n settled a number of actions
involving this Federal research facility on Long
Island,  New York, and the private contractor
which operates  it  for the U.S. Department of
Energy.  On March 29, 1994, Region II executed
an administrative consent order with Associated
Universities  which   resolved   the   TSCA
enforcement action.    The  TSCA  settlement
provided for a penalty of $31,875, and included
injunctive provisions  to insure  compliance with
applicable TSCA requirements.  On May 10, 1994
Region II and the U.S. DOE also signed a Federal
Facility Compliance Agreement which resolved a
Notice of Noncompliance  issued under  TSCA,
relating to some of the same violations as those
for which Associated Universities was penalized.

On April 23, 1994 Region II entered a consent
order  with  DOE   and  Associated  Universities
resolving alleged RCRA violations set forth in a
Notice  of  Violation  issued  to  DOE  and  an
administrative complaint issued to  Associated.
These actions were merged into a single settlement
document due to the  enactment  of  the Federal
Facilities Compliance  Act and because of DOE's
indemnification agreement.  Subsequent Federal
violations referred to EPA by the New York State
Department  of Environmental Conservation, were
also  merged into  this action.   The  settlement
included a  penalty  of  $63,250  and requires
compliance with the RCRA provisions, violations
of which were cited in the action.  In addition,
DOE  and   Associated  Universities  agreed  to
implement   two   supplemental  environmental
projects  jointly  valued   at  $170,000.    The
Respondents will perform a wildlife management
survey and,  if necessary, implement a subsequent
management plan  for the wetland and forested
areas at the Long Island, New  York  facility.
Should these projects not be timely  completed,
Associated Universities will be required to pay an
additional penalty of $85,000.

In re American Cyanamid Company:  In April,
1994  Region  II   issued  two  administrative
complaints to the American Cyanamid Company
of Wayne,  New  Jersey for violations  of  the
EPCRA and  TSCA. The complaints seek to assess
a combined civil penalty of $27,000 for violations
at the Lederle Laboratories  facility  in  Bound
Brook,  New Jersey.   The EPCRA  violations
include the failure to  file a Form R in a timely
manner for Ammonia  otherwise used in amounts
exceeding the threshold reporting requirements;
and TSCA violations  include failure to compile
and maintain annual documents concerning the
disposition of  PCBs   and  PCB  Items.    The
complaints cover violations  at the facility  for the
years  1989 through 1992.  The TSCA matter was
settled in May,  1994,  with a penalty payment of
$10,000. The EPCRA  matter resulted in a consent
order  issued in  September,  and assessment of a
$9,000 penalty.

In re Broomer Research, Inc.:  On June 24,
1994, Region II issued an administrative order on
consent to Broomer Research,  Inc. and 3  Beech
Realty under the "emergency" authorities of §7003
of RCRA and §1431 of SDWA. EPA found that
these  companies'  handling of hazardous and
radioactive wastes  at their facility in Islip,  New
York  may present  an  "imminent and substantial
endangerment"  to  the  health  and environment.
This is  the  first time  the Region  has used  its
emergency authority under §1431 ofSWDA. The
order requires Broomer immediately to  post signs
and restrict unauthorized access to the facility and
prohibits it from treating, disposing or removing
hazardous  waste from the  facility without prior
EPA  approval  of  such action.  Broomer was
required to submit,  within 20 days after the order,
a workplan for the Investigation of Releases at the
facility,  including  the implementation   of  a
sampling plan and medical  monitoring program.
After  Broomer  completes the Investigation, it is
required by this order to submit its findings  to
EPA, and submit a workplan for the Remediation
of Releases, which it must then implement starting
within ten days  after EPA approval.

In re  Abbott Laboratories: On May 18, 1994
EPA initiated a multi-media action against  Abbott
Laboratories'  facility   located   in  Barceloneta,
Puerto Rico. The action consisted of the filing of
two administrative complaints. The first complaint
was issued under the Clean  Air Act, and alleged
that Abbott violated the Puerto Rico SIP by failing
to operate its air pollution control equipment at all
                                            A-16

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
times.  The CAA complaint seeks a proposed civil
penalty of $50,000. The second complaint alleged
that Abbott violated §313 of EPCRA by failing to
timely  submit a  required Toxic Chemical and
Release Inventory Reporting form. This complaint
included  a proposed penalty of $34,000.   The
violations were documented  as  the  result  of  a
consolidated multi-media inspection in March of
1994.

In re Picatinny Arsenal:  In August, 1994 Region
II initiated enforcement actions against the U.S.
Army's Picatinny Arsenal, citing violations under
RCRA, the Clean Air Act, TSCA and the  Clean
Water  Act.  On September 13,  1994 the Region
sent  to the Arsenal four enforcement actions, and
a   proposed   Federal   Facility   Compliance
Agreement (FFCA) to address  these violations.
The   enforcement   actions   were:     1)  an
administrative complaint citing RCRA storage and
disposal  violations,  proposing   a  penalty  of
$60,150,  2) a RCRA Notice of  Violation  citing
certain  additional storage  and  land   disposal
violations, 3) a compliance order under the  Clean
Air Act arising out of  violations of New Source
Performance Standards  for steam generating units,
and 4)  a  Notice of Violation  under the Clean Air
Act for constructing equipment and control devices
without first obtaining the necessary State permit
to construct.
Port Authority of New York and New Jersey:
In April,  1992  Region  II conducted a major
consolidated multi-media inspection of Kennedy
International Airport in New York City, which is
operated by the Port Authority of New York and
New  Jersey.   A number of violations  were
documented, both at facilities operated by the Port
Authority  itself,  as well  as  at some facilities
operated by airline or service companies. In Fiscal
Year  1993 a complaint was  issued to the Port
Authority  citing  it for  TSCA violations and
proposing a penalty of $289,000.  On June 28,
1994,   Region   II   issued   three   additional
administrative complaints  to  Ogden  Aviation
Services, Inc., citing that company for violations
of  the   Federal  underground  storage  tank
regulations,  and  proposing  penalties totalling
$109,125.

Safety Kleen:  In Fiscal Year  1994  Region II
carried out inspections at a number of facilities
operated by Safety Kleen, Inc., a waste oil and
chemical recycling and disposal firm.  Region II
documented violations at several  Safety Kleen
facilities.   An administrative  complaint under
§309(g) of the Clean  Water Act was issued on
June 30 in connection with the company's Manati,
Puerto Rico facility, seeking $125,000 in penalties
for NPDES violations.   Another complaint was
issued on March 31, 1994, citing RCRA violations
at the company's Linden, New Jersey facility.
That  case was  settled  in September with the
company's agreement to pay a penalty of $35,075.
                                             A-17

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                       REGION HI
CLEAN AIR ACT

Ohio Power Company  (N.D. W.Va.):    On
November  15,  1994,  the  U.S. Department  of
Justice filed  a  CAA complaint with the  court
alleging  that Ohio  Power Company violated
federal sulfur dioxide emission limitations at the
Kammer Power Plant in Moundsville, WV.  On
the same date,  the Department lodged a partial
consent decree resolving the United States'  civil
claims for  injunctive relief relating  to  these
violations.    The  partial   decree  requires  the
Defendant  to operate the Kammer  plant  in
compliance with applicable provisions of the CAA,
including a 2.7 Ibs/mm BTU hourly SO2 'emission
standard.  Ohio Power is also required to install
and maintain a Continuous  Emission  Monitoring
System  (CEMS),  which  will  enable EPA  to
monitor Defendant's compliance with the interim
and  final emission limitations,  and  to submit
quarterly  reports   documenting   Defendant's
compliance status.

Bethlehem Steel Corporation (E.D. Penn.):  On
July 5, 1994, the court entered a consent decree
which resolved the United State's claims in U.S. v.
Bethlehem Steel Corporation (Civil Action No. 92-
5213, a civil action filed against Bethlehem Steel
Corporation  (BSC), for violations  of CAA and
NESHAP regulating benzene emission from coke
by-product recovery  plants, 40 C.F.R. Part  61,
Subpart L, at the company's coke works facilities
in Bethlehem, PA, and Sparrows Point, MD.  BSC
failed to  meet compliance deadlines set forth in
the NESHAP, as a result of which BSC continued
to operate sources of benzene in violation of the
NESHAP. BSC also failed  to submit  interim and
final reports  required  by   the  NESHAP.   The
decree required BSC  to pay a civil penalty  of
$650,000 and to comply with the requirements of
the  NESHAP  with'  respect  to  any and  all
operations at  these two facilities.

U.S. v. Coors (D. Va."): On January 31, 1994, the
court entered a consent decree with  the Coors
Brewing  Company (Coors)  which required Coors
to pay a  civil penalty of $245,000 and  to  not
construct  a  brewery  at  its  facility  in  the
Shenandoah  Valley  in Elkton, VA  (Facility)
without a permit authorizing such construction.
The consent  decree  resolved  violations  of  the
Prevention of Significant  Deterioration  (PSD)
regulations.  Coors had initiated the construction
of the facility without undergoing new BACT and
modeling review, and without obtaining a revised
PSD permit to include the new emissions sources,
in violation of §165(a)  of the Clean Air Act and
the   Commonwealth   of   Virginia's    State
Implementation Plan.

Florida Marina and Boat Sales: On January  26,
1994, EPA issued an  administrative  complaint
against  Florida  Marina  and  Boat Sales, Inc.
(Respondent)  for violations of §610(b) of the CAA
and the Nonessential Products Rule.

Respondent, a retailer of new and used boats and
marine supplies, is alleged to have sold at least six
(6) noise horns propelled by a CFC, in violation of
the Rule and the CAA.  Respondent agreed to pay
a civil penalty of $3,000.

Hussey Copper: On April 28,  1994, EPA settled
an administrative CAA complaint  with  Hussey
Copper for violations of the  Pennsylvania SIP.
Hussey  Copper  engages in  the  smelting  and
production of secondary  copper.   Specifically,
EPA's complaint alleged  that  Hussey violated
Article XX  of  the  Pennsylvania SIP  which
established mass and visible emissions limitations
for fugitive  particulate  matter  (PM-10).   In
settlement, Hussey agreed to pay a civil  penalty in
the amount of $135,000.

Manny, Moe, and Jack, Inc.- The Pep Boys:
On March 15, 1994, EPA filed an administrative
penalty action against  the Pep Boys  - Manny,
Moe,  and  Jack, Inc. for violations of §609 of  the
CAA and the regulations at 40 C.F.R. Part  82.
Those provisions, among other things, prohibit  the
sale of small containers  of CFC-12 unless the sale
is to a certified technician or to a person intending
                                            A-18

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I i
to resell the containers.  The complaint  alleged
that PEP Boys sold such containers in violation of
the regulations on numerous occasions, and sought
a penalty of $8,726.

U.S. v. Sun Oil, Philadelphia (E.D. Penn.):  On
July 27,  1994, the court entered a consent decree
between EPA,  Sun Company, Inc.  (R&M),  and
Atlantic  Refining   and Marketing   Corporation
resolving  many  violations  of  the  CAA  at
Defendants' refinery located in South Philadelphia.
The violations included the expansion of the fluid
catalytic cracking unit at the refinery, resulting in
increased emissions of nitrogen oxides and sulfur
dioxide. This expansion triggered the permitting
and  technology  review  requirements  of  the
prevention of significant deterioration (PSD) rule,
which protects air quality in areas where the air is
cleaner than mandated by national air standards for
certain pollutants.  Defendants also violated limits
on  visible emissions  and  failed  to  meet the
deadline for conducting a performance evaluation
on a continuous emission  monitor.  Additionally,
Defendants committed many violations of work
practice rules  designed to minimize emissions of
VOCs at the Refinery.

In addition to injunctive  relief that will reduce
emissions   and   prevent   future  violations,
Defendants paid a civil penalty  of $1.4 million
plus interest.

 U.S. v.  Sun  Oil,   Marcus Hook (E.D.  Penn.):
 During  FY94, EPA and Sun Oil  negotiated  a
 consent decree requiring Sun  Company,  Inc.
 (R&M) ("Sun") to pay a civil penalty of $160,230
 and  to operate its  petroleum refinery in Marcus
 Hook, PA ("Facility") in compliance with EPA's
 Benzene Transfer  NESHAP.  EPA alleged that
 Sun violated the Benzene Transfer NESHAP when
 it failed to meet the requirements of 40 C.F.R. §§
 61.302, 61.304, and 61.305  by the February 28,
 1992 deadline that was imposed under the waiver
 of compliance that was granted to Sun and in that
 it failed to meet certain deadlines required by the
 waiver.

 LTV (W. D. Pa):  On April 11, 1994, the United
 States lodged a consent decree between the United
States, Allegheny County and the Commonwealth
of  Pennsylvania,  Plaintiffs,  and  LTV  Steel
Company  (LTV),  Defendant,  in  response  to
violations  of the Clean Air Act by LTV at  its
Pittsburgh, Pennsylvania coke production facility.
The violations  alleged  in  the  initial complaint
pertained  to the doors, lids, charging, offtakes,
pushing and combustion stacks emission standards.
The decree requires LTV to pay a civil penalty of
nine hundred thousand dollars  ($ 900,000). The
amount to be paid in settlement takes into account
payments  of over $ 150,000 previously made to
Allegheny County for violations alleged  in the
complaints.   The decree requires LTV to make
significant improvements, at a cost of over  $3
million, and implement, and make available to the
Plaintiffs and the public, the results of two studies
of coke oven door back pressure.

U.S.  v. Sun Company, Inc. (E.D. Penn.):  On
May  26,  1994, EPA,  lodged a consent decree in
the court resolving many violations of the CAA at
the Sun Company  refinery in South Philadelphia.
The most environmentally significant  violations
were for  increased emissions of nitrogen  oxides
and sulfur dioxide.  As part of the settlement, the
defendants  will restrict their  emissions  at the
cracking  unit and will apply  advanced  control
technology  to  reduce  their emissions,  thereby
contributing a benefit to the environment.

CLEAN  WATER ACT

U.S.  v. Sun Oil. Marcus Hook (E.D. Penn.):  On
June 6, 1994 Defendant Sun Oil (R&M) signed  a
proposed consent decree  that  resolves  a civil
judicial action for Sun's pretreatment violations of
the CWA occurring at Sun's Marcus Hook, PA,
 Refinery. EPA brought the case against Sun for
 incidents of "pass through" by which the Marcus
 Hook Refinery  discharged oil  and grease to the
 receiving POTW,  DELCORA  in  Chester, PA,
 causing DELCORA to violate its NPDES limits
 for oil and grease. The case also focused on Sun's
 numerous  violations  of  national   and  local
 pretreatment standards applicable to the Refinery
 discharge,  including oil  and  grease,  ammonia,
 phenols,  pH, benzene and other pollutants. Under
 the proposed settlement, Sun would pay the United
                                              A-19

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
States a penalty of $1.058 million plus interest.
For injunctive relief, Sun  would  upgrade its
wastewater treatment, conveyance and operational
practices  to   prevent  further   violations  of
pretreatment standards  and  incidents  of  pass
through.

Sun Oil. Philadelphia (E.D.  Penn.):  On June 6,
1994 Defendants Sun Oil (R&M) and Atlantic
Refining & Marketing Corp. signed a proposed
consent decree that settles a civil judicial action to
resolve violations of the CWA and NPDES permit
occurring at Defendants' Philadelphia, PA, oil
refinery.  On  numerous  occasions  Defendants'
Philadelphia  Refinery  discharged  pollutants
(including oil and grease, total  suspended solids,
BOD,  ammonia,  pH and  phenols)  into  the
Schuylkill   River  in  amounts exceeding  the
limitations set in their NPDES permit. Defendants
also violated NPDES requirements for monitoring,
sampling, reporting  and  bypassing.   Under the
proposed settlement, Sun would pay the United
States  a penalty of  $1.25  million with interest.
For injunctive relief, Defendants would upgrade
their Philadelphia Refinery wastewater treatment,
stormwater conveyance and operational practices
to prevent further violations of the NPDES permit.

Sun Company  (Pennsylvania): On September 7,
1994,  EPA and  the  Department  of  Justice
announced the  settlement of  two  CWA lawsuits
against Sun  Company, Inc., at  its  Marcus Hook
and Passyunk  Avenue Refineries, respectively.
The settlement levied penalties exceeding  $2.3
million, and will also require  the improvement of
poor environmental  practices at both  facilities.
Sun was alleged to  have  violated numerous
parameters of its NPDES permit at the Passyunk
Avenue Refinery, including illegal discharges of
oil and grease, chromium, ammonia-nitrogen, and
zinc.  In addition,  the refinery illegally discharged
untreated wastewater on 14 separate occasions to
the Schuykill River between 1991 and 1994.  The
Marcus  Hook   facility   illegally  discharged
excessive amounts of oil and grease, which caused
the Delaware County Regional Water Authority's
(DELCORA) sewer system to violate its NPDES
permit.  The improper discharges  from both of
these refineries added to the overall degradation of
the Schuykill and Delaware Rivers.

Ocean Builders Supply:  On July 6,  1994, EPA
issued a proposed $125,000 administrative penalty
to Ocean Builders Supply and Mr. Leonard Jester
for filling a high quality wetland on Chincoteague
Island, VA, despite the fact that a permit for the
action had previously been denied.

Despite being denied a permit, Mr. Jester acquired
a  local  building permit  in  June  1992  and
subsequently built the structures  on land owned by
his company,  Ocean Builders  Supply.   Similar
unauthorized activities  have taken place on  two
adjacent  lots to Mr. Jester's but  have not yet
resulted in irreversible impacts.

DELCORA (E.D. Pa):   On July  28,  1994, a
consent decree was entered in the United States
District  Court  for  the  Eastern  District  of
Pennsylvania in the  case  of United States  and
Commonwealth  of  Pennsylvania  v.  Delaware
County Regional Water Quality Control Authority
(DELCORA).    The consent  decree  required
DELCORA to construct an additional secondary
clarifier at its wastewater treatment plant at a  cost
of  approximately $3.5 million  dollars to  be
completed  by  May 1,  1997, and to pay a civil
penalty of $350,000 plus interest. The decree  also
provided  for  stipulated  penalties  for  NPDES
effluent violations and failure to meet construction
milestone deadlines.  This  facility is  located in
Chester, Pa., a community of  mostly poor  and
minority residents.

City of Philadelphia (E.D. Pa.):  On January, 27,
1994, the Court entered  a consent decree requiring
the City of Philadelphia to pay $225,000 in civil
penalties  to the U.S. and Pennsylvania,  and
perform  injunctive  relief  necessary to  prevent
future violations.  The complaint filed May  21,
1992, charged that  on  19 occasions, the  City
responded to backups of sewage at the House of
Corrections  and  the   Detention  Center   by
intentionally  pumping   raw  sewage   into  the
Pennypack Creek, a tributary  of the Delaware
River.  The U.S. and  the Commonwealth each
received 50% of the  civil penalty.  The  City  has
                                             A-20

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 completed the projects necessary to prevent further
 violations at an expenditure of over $1. million.

 Eastern Energy Investments:   On March 24,
 1994, the Office of Surface Mining (OSM) listed
 the first EPA case, Eastern Energy  Investments,
 Inc., of Pinch, West Virginia, onto its Applicant
 Violator  System  (AVS).    Section 510(c)  of
 SMCRA  requires  OSM  to deny new mining
 permits to an entity or its "owners or controllers"
 when any Federal  agency  notifies  OSM of  an
 unresolved air or water violation resulting  from
 surface mining by that entity. OSM will not  issue
 a   new   mining   permit  until   the   violator
 demonstrates  to  EPA's  satisfaction  that  the
 violation  has been  or is  being  corrected.   This
 "permit block," through OSM's ownership and
 control  rules, reaches not only  Eastern Energy
 Investments, Inc., but other mining  entities  with
 which  Eastern's   corporate   officers,  board
 members, and stockholders with greater than a
 10% interest are associated.  On January  12, 1994,
 EPA, Region III, issued an administrative order
 (AO) to  Eastern Energy for outstanding pH and
 metals violations, including discharges in violation
 of a permit  and, after the NPDES permit had
 expired, discharges without a permit.  This AO
 formed the basis for the AVS listing.

 SDWA

 Consolidated Gas  Transmission  Corporation
 (1311):  On September  26,  1994, EPA issued  an
 administrative penalty action against Consolidated
 for violating the conditions of its permit for the
 operation  of  a brine  disposal  well  in Potter
 County, PA.  Specifically, EPA found that  they
 had operated the well without mechanical integrity,
 and numerous other provisions of the permit, in
 violation of 40 CFR Part 144. The action required
 Consolidated to pay  a  penalty  of $10,000 and
 perform corrective action to ensure the integrity of
 the well.

Jiffy Lube (7538):  On October 4, 1993, Region
III issued an administrative penalty action against
Jiffy Lube for the operation of a shallow injection
well which could cause the migration of petroleum
and  other  harmful  chemicals into underground
 sources of drinking water. The settlement required
 Jiffy Lube to inventory all of the faciliies operated
 in  the  region  and  determine  if  there were
 additional wells in operation. Jiffy Lube identified
 a total of eight facilities operating similar disposal
 wells.  Jiffy Lube was required to remediate each
 of the locations and institute  recycling and best
 management practices at each facility,  and pay a
 penalty of $3,200. This administrative action was
 coordinated with  the State of Maryland where
 several wells were located.  Maryland issued  its
 own  administrative  action,  modeled  after  the
 regional action.

 RCRA

 Bethlehem  Steel Corporation Steelton  Plant:
 On January 21,  1994, EPA  and Bethlehem Steel
 Corporation  (BSC) signed  an Addendum to  a
 March  2,  1992, RCRA  §3008(h)  Corrective
 Measures   Study   consent   order   for   the
 implementation  of final  corrective measures  at
 BSC's Steelton,  PA, facility.  BSC will install a
 concrete  cap  inside  its   steel   manufacturing
 building, modify manufacturing procedures to limit
 worker exposure to lead contaminated electric arc
 furnace  dust  and use institutional  controls  to
 further limit possible exposure.

 Medusa Cement: On February 23, 1994, EPA
 signed a consent order resolving an administrative
 penalty action against Medusa Cement Company
 for violations of regulations regarding the burning
 of hazardous wastes in  boilers   and  industrial
 furnaces.   The  complaint alleged that Medusa
 failed  to  submit  a  revised certification   of
 precompliance and failed to reduce feed rates  as
 required under  40 C.F.R.  §266.103.   Medusa
 agreed  to pay a  civil penalty of $200,000  in
 settlement of the action.

 U.S. v. National Rolling Mills (E.D. Penn.): On
 July 11,  1994,  National  Rolling  Mills  (NRM)
 agreed to pay a civil penalty of $300,000  for
RCRA violations.  The civil charges included the
 storage of land disposal restricted (LDR) waste for
over a year, shipment of LDR waste for disposal
to   off-site  facilities   without notifying   those
facilities  whether  the  waste met  applicable
                                             A-21

-------
      IFY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
treatment standards, and various other violations of
RCRA.

Osram   Sylvania   Glass,   Wellsboro,
Pennsylvania:    OSRAM  Sylvania  signed  a
3008(h) consent  order  on October  22,  1993.
OSRAM submitted the RH Workplan on January
25, 1994.  EPA approved the RH Workplan for a
Phase I investigation of the  Osram  facility on
September 29, 1994. The Workplan outlines the
schedule and activities  for the investigation of
soils and groundwater at the facility. The RFI will
focus on  the chromium contamination of  the
groundwater  and  the identification of potential
human and ecological receptors.

Arfion   Manufacturing  Company,  Atglen,
Pennsylvania:  On  September 23,  1994, Action
signed an RCRA §3008(h)  consent order.   The
order was effective September  29,  1994.  It
requires Action to  conduct an RCRA Facility
Investigation  (RFI)  to   define  the  extent of
environmental contamination, and  a Corrective
Measure Study  to evaluate clean-up alternatives.
Action is an explosives manufacturing facility with
a history of land-based disposal activities.

Quaker   State  Corporation,   Newell.  West
Virginia:   On  December 30,  1993 a unilateral
order was issued to the Quaker State Congo Plant
in Newell, WV. This order required Quaker State
to perform Interim Measures (IM), an RCRA RFI,
and a Corrective Measures  Study (CMS).  EPA
has approved Quaker State's IM Work Plan.  The
IM Work Plan  requires  Quaker State to recover
free floating  petroleum product from  a series of
wells installed in a portion of their facility.

Ravcnswood   Aluminum   Corporation,
Ravenswood, West Virginia: On September 30,
1994 an RCRA  §3008(h) consent order was issued
to  Ravenswood Aluminum  Corporation.    This
order required  Ravenswood to perform IM, an
RFI,  and   a  CMS.     EPA   has  received
Ravenswood's IM Work Plan and is reviewing it
for technical adequacy and completeness. The IM
Work Plan requires Ravenswood to  install  and
operate a network of recovery wells to recover
petroleum contaminated  groundwater.
AT&T, Richmond, Virginia:  On June 20, 1994,
EPA issued an Initial RCRA §3008(h) unilateral
order to AT&T to implement corrective measures
at its Richmond, VA, Facility.   The unilateral
order was issued after AT&T failed to negotiate a
consent order in good faith.  The unilateral order
required AT&T to submit a  work plan within 30
days  to  pump  and treat  chlorinated  organic
contamination  in  the   groundwater.    AT&T
appealed EPA's issuance of the order.  As a result
of  the  appeal,   EPA  and  AT&T   resumed
negotiations to resolve the appeal. A settlement
was  reached  between the  parties  and a  joint
stipulation was submitted to  the presiding officer
for approval.

Johnson   Controls   Battery   Group.   Inc.,
Middletown.  Delaware:  On March 8, 1994, an
RCRA §3013  consent order was issued to the
Johnson Controls Battery  Group.   The order
required Johnson Controls to conduct an RFI to
determine  the extent of contamination  that has
resulted from activities at the facility.  Johnson
Controls submitted its RFI Work Plan in a timely
manner.

ITT Corporation, Roanoke, Virginia:  On May
19,  1994,  EPA  issued an  RCRA  §3008(h)
administrative order on consent  to  the  ITT
Corporation.  This order required ITT to perform
an RFI t'o determine the extent of contamination
and  to conduct  a  CMS to  evaluate  potential
remedial  alternatives  that  might  be  used to
mitigate  releases   of   hazardous  wastes  or
constituents from their Roanoke, VA facility.

TSCA

Allied Colloids:    Allied  Colloids,  Inc.  paid
$398,000 in stipulated penalties as a result of an
audit  of its  operations.   The  audit  revealed
violations  of TSCA §§5  arid 13 involving a
variety of chemicals.  This audit payment is in
addition  to  payments  totalling  $900,000,  plus
interest, made by Allied  Colloids  in settlement of
TSCA violations alleged by  EPA in an underlying
enforcement proceeding.
                                            A-22

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Bethlehem Steel Corporation:  EPA  issued a
complaint against Bethlehem Steel Corporation for
violations of the PCB  Rule  at its  facility in
Sparrows Point, Maryland.  The complaint alleged
that Bethlehem Steel:  (1) improperly disposed of
PCBs by  allowing  spills  onto the ground,  (2)
failed to maintain adequate records of inspection
and  maintenance   history  for  leaking  PCB
Transformers,   (3)  failed  to  conduct   daily
inspections  after a  leak  was  discovered  in
numerous PCB  transformers, and (4) failed to
repair the source of the leak and to remediate the
contaminated area within 48  hours.  EPA sought
a total penalty of $145,500 for these violations.

Reading Tube  Corporation:   On January  21,
1994, EPA and  Reading Tube Corporation (RTC)
settled an administrative penalty action for alleged
violations of the PCB Rule  at RTC's Leesport,
PA,  facility.   RTC,  a  manufacturer of copper
tubing, agreed to pay  a cash penalty  of $75,000
and   to   undertake   an  SEP  involving   the
replacement of 7 PCB Transformers and 74 PCB
Capacitors  with  new non-PCB Equipment,  at an
estimated cost of $313,500.

Anzon. Inc.:  On June 1, 1994, EPA  and Anzon,
Inc,  a manufacturer of lead products,  settled a
TSCA   administrative    complaint   involving
violations of the Inventory  Update Rule (IUR).
Anzon failed  to submit  IUR  reports  on  four
chemicals manufactured at its Philadelphia, PA,
plant.   Anzon   agreed to pay a $57,000 civil
penalty, $43,620 of which may be  remitted by
EPA upon completion of SEPs to be performed in
Anzon's  Philadelphia,  PA,  and Laredo,  TX,
facilities.   The  Philadelphia  project involves the
early removal  and   disposal  of   four  PCB
transformers.    The  Laredo  project  requires
increased controls for the capture of  antimony
oxide emissions from  the facility. These projects
have a combined estimated cost of $198,800.

Columbia Gas:   On   September  23,  1994,
Columbia Gas Transmission Corporation agreed to
pay  a civil penalty of $4,916,472 in settlement of
violations  of the TSCA  dating to  1989.   The
settlement  involved TSCA violations in Regions
IE,  IV, and  V.  Following issuance of a 1992
subpoena, Columbia offered  to enter into  an
expedited process to clean up the  pipeline and
settle TSCA civil penalties. This settlement, along
with a CERCLA administrative order on consent,
resulted from that process.  The administrative
complaint alleged three broad classes of violations:
unauthorized use of PCBs in air compressors at 29
compressor stations  spread over  much of the
19,000-mile length of the pipeline system; regular
improper disposal of PCBs to the environment as
a result  of  liquid  blowdowns from these  air
compressors;  and additional improper disposals
(that  are not  the  result of  air  compressor
blowdown) of  PCB-contaminated  liquids from
pipeline  and  air  compressors  to  soils  and
sediments at these stations.

VA Dept of Emergency Services:  On December
27, 1993, EPA filed a  consent order settling a
TSCA administrative penalty complaint against the
Virginia  Department of  Emergency Services.
Under  the   terms  of  the   settlement,  the
Commonwealth of Virginia agreed to pay a civil
penalty and to perform underground storage tank
upgrade  (UST) projects, at an estimated cost of
$100,000.  The UST upgrades will significantly
reduce the  risk  of underground  storage tank
contamination at Commonwealth facilities, which
was  the major focus of EPA's concern about the
Cheatham Annex site.

EPCRA

T.L. Diamond, Spelter,  West Virginia: On June
3,   1994,   EPA   settled  an   administrative
enforcement action brought against T.L. Diamond
& Company for violation of §313 of the EPCRA.
T.L.  Diamond  and Company  violated §313 by
failing to file a toxic chemical inventory  release
form for  zinc dust and zinc oxide in calendar years
1990 though  1992 for its operations at its Spelter,
WV, plant.   The settlement provided for a cash
penalty payment of $41,477, the penalty amount
proposed in the complaint.

Premium  Beverage   Packers,   Wyomissing,
Pennsylvania:  On August 1, 1994, EPA executed
a consent order with Premium Beverage Packers,
Inc. settling violations of EPCRA §§ 311 and 312.
                                             A-23

-------
         FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 The  violations  involved  the presence of  two
 hazardous chemicals at the facility in excess of
 threshold reporting levels (ammonia and carbon
 dioxide) for the years 1988 and 1989. Under the
 terms of the consent order, Premium Beverage
 Packers, Inc. agreed to pay a penalty of $73,011.

 Steel Processing, Inc., Pottstown, Pennsylvania:
 On August 14, 1994 EPA signed a CACO settling
 an administrative  enforcement  action  brought
 against  Steel   Processing,  Inc.,   located   in
 Pottstown, PA, for violations of EPCRA §§311
 and 312. Steel Processing, a carbon steel sheet
 manufacturer, failed to submit an MSDS or list for
 hydrochloric  acid  to the LEPC, SERC,  and  the
 local  fire department,  in violation of §311  of
 EPCRA and failed to submit an Emergency  and
 Hazardous Chemical  Inventory  Form  for  the
 calendar years 1988, 1989, and 1990, in violation
 of §312 of EPCRA. An inspection of the Steel
 Processing facility revealed that Steel Processing
 utilized  as  much  as   617,000  pounds   of
 hydrochloric  acid  during  those   years.   The
 settlement provided for the payment of a $7,500
 penalty.

 Messer Greisheim Industries, Inc., Philadelphia.
 Pennsylvania: On September 6,1994 EPA signed
 a CACO negotiated in settlement of a nine count
 administrative complaint issued against Messer
 Griesheim Industries, Inc., d/b/a M.G. Industries,
 Inc., a Philadelphia welding supply business,  for
 violating the Emergency Planning and Community
 Right to Know Act (EPCRA).  M.G. Industries
 failed to report to the State Emergency Response
 Commission,  the  Local  Emergency Planning
 Committee, and the Local  Fire Department  for
 reporting years  1991 and  1992, in violation of
 EPCRA §§ 311  and 312.  M.G. Industries agreed
 to pay a $100,000 civil penalty. At the time, this
penalty  was the fifth  largest ever obtained  for
EPCRA §§ 311/312 violations.

Diversey   Corporation,  East   Stroudsburg.
Pennsylvania:  A  Pennsylvania Corp  with  63
employees,  Diversey   is   a manufacturer  of
industrial cleaning compounds. On April 27,1992
there was a non-permitted release of chorine and
the facility  failed to  notify  the  NRC,   the
 Pennsylvania SERC, or the Monroe County LEPC.
 EPA and Diversey Corporation settled the case
 with an assessed penalty  of $43,750,  and an
 agreement that Diversey would undertake a SEP
 with a projected  cost of  $10,974.   The  SEP
 involved the donation of computer, software, and
 other equipment to the LEPC.

 Homer Laughlin China: On December 9,  1993
 EPA executed  a CACO,  with  an  associated
 Settlement   Conditions  Document,  settling an
 EPCRA administrative action filed against the
 Homer Laughlin China Company for violations of
 §313 of that  Act.   The settlement included a
 substantial SEP, exceeding $9 million in cost, in
 which  Laughlin  converted  their  entire  china
 dinner-ware  production  system to a  lead  free
 process.

 Action Manufacturing:  On September 28, 1994,
 EPA settled a penalty complaint against Action
 Manufacturing in which the company  agreed to
 pay  an  administrative penalty of $37,658.  The
 settlement also included a SEP which required the
 company to  spend at least $93,000 to replace its
 current  1,1,1-TCA parts-washing system with an
 aqueous-based parts washing  system.  The  new
 parts washing  system  will  allow Action to
 significantly reduce its  use of 1,1,1-TCA and
 Trichloroethylene  (TCE)  at  its  Philadelphia
 facility.

 FIFRA

 DuPont: On September 29, 1994, EPA and E.I.
 DuPont de  Nemours (DuPont), Platte  Chemical
 Company (Platte) and Lesco, Inc. (Lesco) settled
 an administrative FIFRA penalty action  involving
 the distribution of Benlate, a fungicide, which had
been  contaminated with atrazine,  an herbicide.
The consent  order required DuPont and Platte to
pay a total of $1 million in civil penalties.

 CERCLA

 Columbia Gas:  On September 23, 1994, EPA
entered  into  a multi-regional  CERCLA consent
order   with   Columbia   Gas   Transmission
Corporation  under  which  the company  will
                                            A-24

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
characterize contamination and perform CERCLA
removal actions selected by EPA at compressor
stations and other locations along the Columbia
pipeline system.   Columbia estimates  that this
project will require expenditures of between $15 to
20 million a year for approximately 12 years.

Greenwood Chemical:  On June 30, 1994 EPA
issued an order pursuant to §106 of CERCLA to
the Greenwood Chemical Company and the High
Point Chemical Corporation to implement EPA's
Remedial  Design  for the excavation, treatment
(where  necessary),  and  offsite  disposal   of
contaminated soils at the Greenwood Chemical
Site,  located   approximately  20  miles  from
Charjottesville, VA.

Recticon/Allied Steel Site:  On March 24, 1994,
EPA  issued   an   order  pursuant  to  §106  of
CERCLA to Highview Gardens, Inc.; Allied Steel
Products  Corporation;  Allied   Steel  Products
Corporation  of  Pennsylvania;  and  Rockwell
International Corporation for the Recticon Allied
Steel Site, located in Parker Ford, Chester County,
PA.   This order requires the  performance  of
Remedial Design  and Remedial Action  as called
for in EPA's June 30, 1993 Record of Decision for
the Site.

Sackville Mills Company:  On June 17,  1994,
Sackville Mills Company, the present and former
owner/operator of  a  closed  textile  mill   in
Wallingford, PA, entered into an administrative
order by consent (Order) with  EPA to  conduct
removal response activities at the former textile
mills  facility.  The order  also prohibited the PRP
from  disturbing or excavating areas on  the Site
which are suspected to  contain anthrax  bacteria
allegedly disposed of during the textile operations;
required measures to be taken to identify potential
anthrax  contamination  in  soils; and  required
removal of anthrax  from a part of an on-Site
building.

United  Chemical Technologies:  On  June  27,
1994, EPA issued a unilateral removal CERCLA
§106   order   directing   United   Chemical
Technologies,  Inc. ("United"), the operator of a
chemical manufacturing facility in Bristol, PA, to
stabilize and clean up hazardous substances at a
site which was the scene of a massive explosion
and  fire  on June 21.   The order provided  a
comprehensive framework  for  establishing  site
security, site stabilization, and identification  and
proper handling  and  disposal  of  hazardous
substances on site.

U.S. v. Lord  Corporation  (W.D.  Penn.):   On
March 15, 1994, the  court entered  a  consent
decree, settling the  United  States'  claims under
CERCLA §§ 106 and 107 for injunctive relief and
reimbursement  of  costs related  to  the  Lord
Corporation Property portion of the Saegertown
Industrial  Area Superfund  Site ("Site").   The
consent  decree required Lord  Corporation  to
implement  the selected  remedy for  the  Lord
Corporation Property portion of the Site, a remedy
estimated to cost $3.4 million. The consent decree
also required Lord Corporation to pay $21,928 in
past response costs incurred by the United States,
and to pay certain categories of the United States'
future response costs associated  with the consent
decree and Site.

U.S. v. Chromatex (3rd Cir.): On September 29,
1994, the Third Circuit Court of Appeals ruled in
favor of the United States' interpretation of the
statute of limitations provision of CERCLA.  The
court affirmed the  district court's February 9,
1994, summary judgment ruling  under §107(a) of
CERCLA  finding  the  defendant's  liable  for
$682,002  in  Agency  response costs incurred
during a removal action at the site. On appeal, the
defendants argued that EPA had let more than  3
years pass since completion of the removal action,
at the Valmont Superfund Site and consequently
was barred by the statute of limitations.  The Third
Circuit rejected this argument, applying a broad
standard to determine when  a removal action was
completed.  As a  result, the court found that the
United States had brought suit for removal costs
within the  3  years  of completing the removal
action.
                                            A-25

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                       REGION IV
CLEAN AIR ACT

U.S. v. Rohm and Haas. Inc. (W.D. Ky.):  On
August   2,   1994,  a  stipulation,  settlement
agreement and order (Stipulation) was entered by
the court concluding a  1992 CAA Pre-Referral
judicial enforcement action against Rohm & Haas
Kentucky, Inc. and provided for the payment of a
$32,500 civil penalty to the United States. Rohm
and  Haas operates a specialty  chemical  CAA
processing plant in Louisville, KY.  Rohm  and
Haas violated  §lll(e)  of  the  act  and  its
implementing regulations codified  at 40 C.F.R.
Part 60  Subparts  A and  D  when it failed to
monitor and measure emissions of nitrogen oxides
from a natural gas boiler located at its plant from
July 1989 to June 1991.

U.S. v. Olin Corporation (E.D. Tenn.):  On June
9, 1994, the court  entered a consent decree to
resolve violations of the mercury standards  under
the CAA NESHAP by Olin's Chattanooga facility.
The  penalty  amount was $1 million.

EPA filed a civil complaint alleging violations of
the work practice standards for mercury NESHAP,
and issued an agreed order for decontamination of
the workers' homes under §106 of CERCLA. A
second  amended  complaint  in January  1992
alleged  additional  NESHAP mercury violations,
and added a count for failing to notify the NRC of
the mercury  release, a violation of CERCLA §103.

U.S  .v. Crown, Cork & Seal, Inc.  (N.D. Miss.):
On January  3, 1994, the court entered a consent
decree which settled Crown, Cork  & Seal  Inc.'s
(CC&S's) alleged violations of the CAA's PSD
requirements  and  New  Source  Performance
Standards (NSPS).  The  CACO  required  the
payment  of a civil penalty of  $343,000  and
required  CC&S to perform three SEPs valued at
more than $2 million after tax. During June 1987,
Crown commenced operations of a new two-piece
can coating facility in Batesville, MS, without first
obtaining a  PSD permit, or testing and reporting
commencement pursuant  to  requirements under
NSPS.

CLEAN WATER ACT/SDWA

U.S. v.  Metro-Dade  County, et  al:   Concerns
regarding  the  structural  integrity of a  sewage
pipeline (cross-bay  line)  under  Biscayne  Bay
prompted Region IV to initiate a civil enforcement
action in June 1993. Rupture of the cross-bay line
would  have caused  catastrophic environmental
damage  to  Biscayne Bay  and  surrounding
waterbodies. In December, 1993,  the government
and Metro-Dade County  entered into a partial
consent decree addressing the emergency claim,
contingency plans and short term measures. Under
this First Partial consent decree,  the County has
completed construction of the new cross-bay line
(a year  ahead  of schedule) and the line is now
operational.

In an action filed in  the United States  District
Court for the Southern District of  Florida on June
10,1993, the Region sought emergency relief from
the court based on the deteriorated  condition of the
cross-bay line.  Metro-Dade had experienced some
very large sewer spills due to breaks in lines that
were of a similar age and type as the line under
the bay and it was therefore feared that the cross-
bay line could break at any time. Janet Reno, then
the State Attorney, convened a special grand jury
to investigate pollution in the Miami River and the
grand jury concluded that the aged and corroded
sewer system, and the cross-bay line in particular,
presented the greatest threat  to the health of the
river.

The action also contains  four claims  addressing
system-wide unpermitted  discharges, improper
operation   and  maintenance,   and   reporting
violations.  The Second and Final Partial consent
decree, which addresses all other  injunctive relief
and penalty, is in the  last  stages of finalization.
                                            A-26

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
United  States v. IMC-Asrico  Company  (M.D.
Florida):  On April 1, 1994, Region IV submitted
a referral to the Department of Justice asking that
a civil judicial action be filed against IMC-Agrico
(IMC) for the company's alleged  violations of
Section 301 (a) of the CWA.  EPA alleged IMC
exceeded its permit effluent limits for a variety of
parameters  as  well   as  non-reporting  and
stormwater violations.   IMC owns  and operates
phosphate rock mines and associated processing
facilities in Florida and Louisiana.  Eight of its
mineral extraction  operations and its Port  Sutton
Phosphate  Terminal were  the  subject of  this
referral action.  The subject IMC facilities  had
over  1,500  permit violations  since 1988.   On
October 17,1994, IMC submitted a signed consent
decree resolving this multi-facility civil referral.
The settlement provides for an up-front payment
of  $835,000  and  a   $265,000  Supplemental
Environmental  Project  (SEP).    The SEP  will
involve conversion IMC's scrubber discharge and
intake water systems into  a closed loop system
(greatly reducing  pollution loading at  the Port
Sutton facility).

U.S.  v. Perdue-Davidson  Oil Company  (E.D.
Kentucky):   On May 6, 1994, the U.S. District
Court for the Eastern District of Kentucky required
Perdue-Davidson and Charles Perdue to pay EPA
stipulated penalties, calculated at $3.8 million, and
compliance  with all requested injunctive  relief.
Perdue-Davidson is an  oil  production company
which produces crude oil from two stripper-well
fields in eastern Kentucky.  As a result of Perdue-
Davidson's  repeated violations of  a  prior UIC
administrative  order  on  consent,  as  well  as
statutory   and   regulatory   environmental
requirements,  EPA filed  this multi-media civil
referral pursuant to § 301 of the CWA, §  311 of
the CWA, § 1423 of the SDWA (UIC) and § 311
of the EPCRA.

On  March  10,  1994,  the  government filed a
motion for partial summary judgement on  five of
the ten claims for relief in the  complaint.  In
addition,  the  government  requested  injunctive
relief  and that the Defendants  pay  stipulated
penalties due to violations  of a UIC AOC. This
represents an  important court decision requiring
payment of stipulated penalties for violation of a
UIC administrative order on consent, as well as for
corporate officer civil liability for company and
corporate officer  violations of  §§ 301 and 311
(SPCC) of the CWA.

In the Matter of Manatee County, FL;:  On
February 1,  1994, the  Regional  Administrator
ratified  the negotiated settlement in  this action,
which provided for payment of a $60,000 penalty.
In September 27,  1993,  EPA initiated  a CWA
Class  II administrative  penalty  action  against
Manatee County under  Section  309(g)  alleging
violations of  Section 301 (a) of the CWA by
exceeding the no-discharge requirements of its
NPDES permit.   The County  had  periodically
discharging from  its wastewater treatment plant
into the receiving stream during the period of June
through October 1992. Based on consideration of
the factors  identified at Section 309(g)(3), EPA,
and following settlement discussions, the parties
reached a negotiated settlement of $60,000.

In the Matter of IMC-Fertilizer. Bartow FL:
On February  17, 994, the Regional Administrator
ratified  the negotiated settlement in  this action,
which provided for a $40,000 penalty. In March
1993,   EPA  initiated    a  CWA   Class  II
Administrative Penalty  Action  against  IMC
Fertilizer under Section 309(g) alleging violations
of Section 301 (a)  of the CWA by exceeding the
permit effluent limits for Dissolved Oxygen, Total
Suspended   Solids,  Fixed  Suspended   Solids,
Unionized Ammonia, and pH during the period of
March  1988  through  February  1991   at  its
Haynsworth   mining  facility.      Based   on
consideration of the factors identified at  Section
309(g)(3), and following settlement  discussions,
the parties  reached a  negotiated settlement with
penalty  of $40,000.

In the Matter of Jacksonville  Beach, FL: On
May 6, 1994, the signed consent agreement was
ratified by the Regional Administrator. This case
was the first regional action against a facility for
failure to comply with the new stormwater permit
application requirements.  In December 1993, EPA
initiated a Class I administrative penalty action
against  the  City   of  Jacksonville Beach under
                                             A-27

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Section 309(g) of the CWA alleging violations of
Sections  301 (a) and 308 of the CWA through
failure to submit a timely and complete stormwater
permit  application  for  the  City's  municipal
stormwater system. Based on consideration of the
factors  identified  at  Section  309(g)(3),  and
following settlement discussions,  EPA and  the
Jacksonville Beach reached a negotiated settlement
with a penalty of $3,500.

Oil Pollution Act Enforcement Initiative:  In a
concerted  drive  against  contamination  of  the
nation's  waters,  Region IV participated in a
government enforcement action announced on
May 26, 1994.  This action was filed against 28
commercial polluters who discharged oil and other
hazardous  substances  into water  and adjoining
shorelines.   These  actions  reinforce  the clear
Congressional intent to punish violators of Clean
Water Act provisions prohibiting  of oil  and
hazardous   substance   spills   and   requiring
preventative measure against such spills.

Region IV filed five administrative cases against
two individuals and three corporate commercial
entities:

Alamco   Inc.,  (Complaint  seeks  penalty  of
$123,942) located in Clairfield, TN, is an oil and
gas  exploration  and producing  company.   It
spilled at least 7,300 gallons of crude oil affecting
the Clearfork and the Hickory Creeks and failed to
prepare an SPCC plan.

Cumberland Lake Shell, Inc.,  (Complaint seeks
penalty   of $92,387)  located  in   Somerset,
Kentucky,  is  a  distributor of  gasoline  and
petroleum products to service stations; it spilled at
least 200 gallons of diesel affecting Sinking Creek.
Cumberland also  failed to prepare an SPCC plan.
Texfi Industries, Inc., (Complaint seeks penalty of
$24,672) located in Jefferson, Georgia, is a fabric
manufacturer.  It spilled at least 1,900 gallons of
diesel affecting  an  unnamed tributary  of the
Oconee River and failed to prepare an SPCC plan.
Wesley Griffith,  (Complaint  seeks penalty of
$78,287) an independent oil producer,  spilled at
least 11,130 gallons of oil affecting South Fork of
Coles Creek and failed to prepare an SPCC plan.

John  D. Herlihy,  (Complaint seeks penalty of
$37,425) an independent oil producer,  spilled at
least 2,100 gallons of oil affecting Cameron and
Middle Fork   Creeks.   Herlihy also  failed to
implement an SPCC plan.

U.S. Environmental Protection  Agency v. Polk
County: A consent agreement and order assessing
administrative  penalties  was   signed  by  the
Regional  Administrator on  February 24,  1994,
settling this  case for  a  penalty  of  $100,000.
Region IV issued a Class II administrative penalty
order complaint against Polk County, Florida, on
September 30  1991.    The complaint assessed
penalties in the amount of $125,000 for alleged
discharged without  a valid NPDES permit from
the Wilson Acres waste water treatment plant since
at least September  30,  1986.   EPA alleged the
facility had been continuously discharging since at
least March 20, 1983.   The agreement provided
that up to $15,000 in   penalties to be paid the
State  of Florida  would be  credited toward the
penalty in this case, conditioned on the connection
of the Wilson  Acres  WWTP  to  the City of
Auburndale collection  system.   That connection
has  been  completed  and all  discharges from
Wilson Acres WWTP have stopped.

United States v. City of Port St. Joe, Florida; et
aL:  On August 13, 1994, the U.S. District Court
for the Northern  District  of  Florida  entered  a
consent  decree settling litigation  between  the
United States and the City of Port St. Joe, Florida;
the St. Joe Forest Products Company; and the
State of Florida. The consent decree provides for
the payment of a $25,000 civil penalty by the City
and a $325,000 civil penalty by the Company, for
a total civil penalty of $350,000.  This  case, filed
as  part  of the  National Pulp and  Papermill
Enforcement Initiative,  alleged that the City and
the County violated the federal Clean Water Act.
The  City  operates   a  municipal wastewater
treatment  facility   which   discharges   treated
wastewater into the waters  of the United States,
                                              A-28

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
under  a permit issued pursuant to  the National
Pollutant Discharge Elimination System (NPDES)
program. EPA alleged that, since November 1988,
the  City  repeatedly  violated  the  discharge
parameters set in its NPDES permit.  EPA alleged
the   Company    violated   the   pretreatment
prohibitions  of  the  Clean   Water  Act   by
contributing pollutants in  excessive  quantities,
which caused interference and pass through of the
City facility and  caused  the City to  violate  its
NPDES permit.

RCRA

Holnam, Inc.:    A  CACO  was  entered   on
September  30, 1994, resolving  an RCRA action
filed against Holnam, Inc. addressing violations of
the BIF Rule found in routine EPA inspections in
1992 and 1993 at two cement kilns operated in
Holly Hill,  SC. The company had failed to make
a  hazardous  waste/Bevill determination  on  its
cement kiln dust, failed to submit a complete and
accurate Certificate of Compliance for one kiln,
and failed to submit an adequate Waste Analysis
Plan.  In the  CACO, Holnam  agreed to pay a
penalty  of   $670,000,   to   make   required
submissions,   and   to   conduct    additional
groundwater monitoring.

Arizona Chemical Company:  On September 28,
1994, a  CACO was entered settling  an RCRA
action  filed against Arizona  Chemical Company
for violations  of the BIF Rule.   The violations
were identified by a joint EPA and state inspection
at the facility located  in Panama City, FL.  The
facility   had  failed  to  operate  within  limits
contained in its Certification of Pre-compliance
and Certification of Compliance; failed  to develop
an inspection schedule, an adequate waste analysis
plan, and a closure plan for one  boiler; and failed
to conduct required air emissions monitoring.  In
settlement,  the company  agreed to  pay a civil
penalty  of $79,000   and  to   make  required
submissions.

Giant Cement Company: On February 15, 1994,
a  CACO  was   entered  settling  an  RCRA
administrative  action filed against Giant  Cement
Company. The complaint was based on violations
found  during an  EPA  inspection  of Giant's
Harleyville, SC, Portland Cement manufacturing
facility.    The  violations  included BIF  Rule
violations, as well the facility's failure to make a
Hazardous Waste/Bevill determination for cement
kiln dust.  The CACO required Giant to pay a
civil penalty of $520,000  and to implement a
cement kiln dust sampling and analysis protocol
approved by the Agency.

Todhunter  International.  Inc..  d/b/a  Florida
Distillers:     A  CACO   was  entered    on
September 30, 1994, settling an action  filed in
1993 that found numerous RCRA violations at
facilities  in Lake  Alfred  and Auburndale,  FL,
where  the  Respondent manufactures  beverage
alcohol products. The CACO settles this case for
$400,000, $100,000 in cash, with up to a $300,000
reduction in the penalty for implementation of a
specified SEP.  The  SEP, which will cost more
than $1 million, involves installation of cooling
tower equipment, significantly reducing cooling
water withdrawal from the Floridan aquifer, and
the upgrade of a waste water treatment plant to
significantly reduce the loading of nutrients and
BOD.

U.S. v. Gulf States Steel, Inc. (N.D. Ala.):  On
September  27, 1994,  the  U.S.  District Court
entered a civil consent decree that requires  Gulf
States Steel Corporation to pay a civil penalty in
the amount of $1.1 million.  The consent decree
also provides  for  a possible  reduction  in the
penalty of up to $300,000 for SEPs to be proposed
for EPA approval, as well as extensive injunctive
relief, including corrective action. This settlement
was reached in pre-filing negotiations pursuant to
Exec. Order No. 12778, which requires that the
government make reasonable efforts to settle prior
to litigation.

Laidlaw  Environmental  Services (TOC),  Inc.:
On September 30,  1994,  EPA entered into an
RCRA §3013 order on  consent with Laidlaw
Environmental Services (TOC), Inc., addressing
TOC's commercial  hazardous waste incinerator in
Roebuck, SC. The order requires TOC to conduct
a systems design and  quality control evaluation of
the computer control system which monitors and
                                            A-29

-------
      I FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
controls the incinerator's emissions; and to gather
information  to  enable  EPA to conduct a site-
specific  multi-pathway risk  assessment.    In
addition to agreeing to perform the work required
under the consent order, TOC has agreed to pay
penalties in the amount of $500,000.

Florida  Department  of  Transportation:   A
CACO  was  entered  on September 20, 1994,
settling an administrative action filed against the
Florida  Department   of   Transportation  for
violations of RCRA at the Fairbanks Disposal Pit
Site in Fairbanks, FL.  Under the CACO, FOOT
has agreed to pay a civil penalty of $2,407,550,. of
which  $170,000 will  be paid in cash and the
remainder of which  may  be  satisfied  through
performance of 3 SEPs. Under the SEPs, FOOT
will discontinue the application of lead and high
VOC content (or solvent-borne) pavement marking
paints and thermoplastics on all roads constructed
and maintained by FOOT throughout the State.
The CACO  also requires FOOT to submit and
implement an adequate closure/post-closure plan.

TSCA

Tennessee Gas Pipeline Company/Tenneco, Inc.:
In FY  94,  Region 4 negotiated  two separate
settlement agreements  relating to  the Tenneco
natural gas pipeline system that stretches 16,000
miles from Texas and Louisiana to different parts
of the Northeast. On August 10,1994,1994, EPA
executed a consent agreement and consent order
(CACO) under the Toxic Substances Control Act
(TSCA) with respondents Tennessee Gas Pipeline
Company and Tenneco, Inc. The CACO settled
an administrative penalty action that alleged TSCA
violations at 42 compressor stations  along the
pipeline, the multi-Regional, multi-state settlement
required the two companies to pay a civil penalty
of $6.4 million for violations relating to  use and
disposal  of  polychlorinated  biphenyls  (PCBs)
dating  back to 1979.  The $6.4 million penalty is
the largest administrative penalty ever recovered
by the Agency for TSCA violations.

On the same day, the Region also executed an
administrative order  on  consent  (AOC) under
CERCLA with  the two companies for study and
cleanup of PCB contamination along most of the
pipeline.   (State  agencies  in  New  York and
Pennsylvania   are   independently   addressing
contamination at compressor stations within their
respective borders,   although  the  stations  in
Pennsylvania may be added  to the AOC if the
respondents   do   not   conduct   the   work
appropriately.)  The value of this settlement is not
certain since  it will ultimately depend  on the
amount of contamination that is identified.  EPA
expects, however, that  the response action will
likely cost more than $240 million, thus  making
this  the  largest  administrative   settlement  in
CERCLA history.

The multi-media settlements reflect the Agency's
first  coordinated use of CERCLA authority for
cleanup with TSCa  authority for  administrative
penalties. Shortly after the announcement of these
two   settlements,  Region  3  announced  the
successful negotiation of two similar settlements
for the Columbia Natural Gas Pipeline.

General  Electric  Company:  On November 1,
1993, the Environmental Appeals  Board (EAB)
issued its Final Decision in EPA's 1989 TSCA
PCB case against General Electric Company (GE).
The  Final Decision  upheld  EPA's position that
PCB solvent distillation  systems used in disposing
of PCB transformers  are subject to PCB disposal
regulations. The decision also clarified that once
PCBs are in a state  of  disposal, those PCBs are
governed only by the PCB disposal regulations
and cannot be simultaneously subject to PCB use
regulations.  Based  upon its findings, the  EAB
assessed a $25,000 penalty against GE for its PCB
disposal  violations.   The EAB's Final Decision
was  appealed by GE and is currently pending in
U.S. District Court.

EPCRA

Gro-Tec, Inc.:  On  April 1,  1994, a CACO was
filed  for the payment  by  Gro-Tec, Inc.  of a
$12,750 penalty and the  performance of two SEPs.
The SEP calls for Gro-Tec, Inc., to  donate at least
$21,000  worth  of equipment to  the  Eatonton-
Putnam County Emergency Management Agency.
Additionally, it requires the company to undertake
                                            A-30

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
certain  construction  activities  at  its  facility,
designed to accomplish pollution reduction. The
projected costs  of these activities will equal or
exceed $60,000.  The  complaint, filed April 1,
1994  alleged that Gro-Tec, Inc., a producer of
agricultural products, was in violation of EPGRA
§§ 311 and 312 and charged the company with
failure to  submit an  MSDS,  and  complete
emergency  -and  hazardous chemical inventory
forms.  The complaint  proposed  an  $85,000
penalty.

Everwood  Treatment  Company,  Inc.:   On
August 29,  1994, a CACO was filed  resolving
Everwood   Treatment   Company,   Inc.'s
(Everwood's) violations of §103 of CERCLA and
§304  of EPCRA.  The  CACO settled this action
for $54,500 and required the Respondent to pay
$32,000 (plus interest) in cash in four installments
within 1 year of the effective date of the CACO.
In addition, the CACO calls for Everwood to
implement  a SEP  which  requires it  to  expend
approximately $225,000 to construct a new wood
treatment plant that is built specifically for the use
of a wood preservative that is not a hazardous
waste.

A complaint was filed  against Everwood  on
January 5,  1994, pursuant to §103 of CERCLA
and §304 of EPCRA alleging that Everwood failed
to immediately  notify the NRC of a release of
arsenic  acid, failed to immediately  notify the
SERC of a release of arsenic acid, and failed to
provide a written follow-up emergency notice of
the release to the SERC and the LEPC. Everwood
is located in Irvington, AL, and is in the business
of treating wood with a copper, chromate, arsenate
solution.

North American Royalties, Inc., d/b/a Wheland
Foundry:  On December 20, 1993, a CACO was
filed  which  settled an  EPCRA  administrative
enforcement  action  against  North   American
Royalties, Inc. d/b/a Wheland Foundry (Wheland).
The CACO required that Wheland  pay a civil
penalty of  $25,724.   In addition,  the CACO
provided that Wheland undertake, as a SEP, the
purchase of an emergency response vehicle, to be
donated  to the Hamilton County  (Tennessee)
LEPC.  The SEP expenditure was estimated at
$102,880.

Ashland Petroleum  Company:   On  May 10,
1994, a CACO was  filed which settled  alleged
reporting violations under §304  of the EPCRA.
The CACO provided  for a $1.56 million penalty,
for which Ashland agreed to pay $312,000 in cash
to EPA, with the remainder of the penalty to be
provided in SEPs valued at over $1,248,000 in
after tax value.  In addition to the $312,000 cash
penalty  to  the  government, Ashland  will  pay
$45,000 to the Cabell-Wayne (WV) LEPC for its
use, and will pay $48,500 to the Kentucky SERC
for computer hardware  for the SERC and for
various projects benefitting the Boyd (KY) LEPC.
The  SEPs performed  in-house  at  Ashland's
Catlettsburg refinery will total $2,382,500 in actual
cost, arid include reducing hydrocarbon emissions
from storage tanks, routing relief valve discharges
to a flare, and performing asbestos abatement
projects on site.

FIFRA

Courtaulds Coatings, Inc.:   On November  11,
1993, EPA filed a CACO in settlement of FIFRA
violations alleged against Courtaulds Coatings Inc.
(Courtaulds),  located in  Louisville, KY.   The
settlement required Courtaulds to pay a $38,640
penalty and comply with FIFRA and the pesticidal
regulations.

In November 1992, EPA filed an administrative
complaint  against  Courtauld's   for  selling
unregistered pesticidal products.   Eight  Porter
Paint products in the PorterSept product line were
cited  for making pesticidal claims.  PorterSept
products contain Intersept, an antimicrobial.  The
labels and advertising on this product inferred that
PorterSept products had antimicrobial properties.
As part of the settlement, Courtaulds  agreed to
disconcontinue  the violative advertising, correct
the labels, and pay a penalty of $38,640.

CERCLA

Kerr-McGee Chemical Corporation:  On March
14,  1994, a  CACO  was  filed  to  settle an
                                            A-31

-------
       Jl FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       •
 administrative enforcement action against Kerr-
 McGee Chemical Corporation  (Kerr-McGee) for
 violations  of CERCLA 103(a).   The  CACO
 required the payment of a $32,940 penalty and the
 performance of  a  SEP.  Under the SEP, Kerr-
 McGee  is  required  to  undertake   certain
 environmental improvements at its Hamilton, MS,
 facility which will reduce the potential for titanium
 tetrachloride emissions from its control equipment.
 The project will be performed at an estimated cost
 of $280,000.

 Parramore Fertilizer Site in Tifton, Georgia:
 On December 16,  1993, EPA issued a UAO for
 removal response  activities  to  Atlantic Steel
 Industries,   Inc.,  Florida   Steel  Corporation,
 Georgetown  Steel  Corporation,  Owen Electric
 Steel  Company of South Carolina, Inc., and U.S.
 Foundry & Manufacturing Corporation. The UAO
 requires these steel companies to take over clean
 up of the Parramore Fertilizer Site in Tifton, GA.
 The Site is contaminated with  emissions control
 dust (EC Dust) from electric arc furnaces, a  RCRA
 listed  hazardous  waste  (K061),  which  was
 generated by the steel companies.

 Distler Farm and Distler Brickyard Superfund
 Sites  in Kentucky:  On January 3, 1994, EPA
 forwarded  a  signed  consent  decree to  the
 Department of Justice for lodging, reflecting  the
 settlement of cost recovery actions arising  out of
 the Distler  Brickyard and Distler Farm Superfund
 Sites in Hardin and Jefferson Counties, KY.

 Under the terms of the consent decree, four  groups
 of defendants and the owner of the Brickyard Site
 will pay $6,355,000 for past costs incurred  by the
 United  States   and  the  Commonwealth  of
 Kentucky,  as well as all additional costs  which
 EPA and the Commonwealth incur in performing
 remedial actions  at the Sites.  A core group of
 generator defendants will be responsible for paying
the  costs  of the remedial action  as  they  are
 incurred. The three other groups and the owner of
the  Brickyard will  contribute fixed  sums  in
 varying amounts.

Jadco/Hughes  Site,  Gaston  County,   North
 Carolina:   On November 1, 1993, EPA executed
two consent decrees, one of which was previously
executed by each member of the Jadco/Hughes
Site  Steering  Committee,  the  other  being
previously  signed by  AKZO  Coatings,  Inc.,
(AKZO) and Jadco, Inc., (Jadco), both of which
are late-settling parties. The Steering Committee's
decree provides that its members will reimburse
EPA past costs in the amount of $555,000, and the
AKZO   and   Jadco   decree   provides  for
reimbursement of  $75,534.04 (by  AKZO)  and
$151,919.16 (by Jadco).

T.H.  Agriculture &  Nutrition  Co.  Site  in
Albany, Georgia:   On  October 22, 1993, four
PRPs which were named as  Respondents in  a
UAO for Remedial Action/Remedial Design (RD/
RA) for Operable Unit 1 at the T.H. Agriculture &
Nutrition Co., Site (the Site) provided notice to
EPA that they intended to comply with the UAO.

UAOs were issued to five PRPs at the Site after
no PRP submitted a good faith offer in response to
a special notice letter.   One of the PRPs, T.H.
Agriculture & Nutrition  Co., Inc., (THAN)  has
indicated that it will comply with the UAO  and
will undertake the work required to implement the
Record  of Decision for  Operable Unit  1  at the
Site.  Three other PRPs  which  received UAOs
have indicated that they  will propose a level of
participation to THAN and enter into negotiations
with  THAN  to   reach  agreement  about  an
appropriate level of participation in the RD/RA, as
required by participate and cooperative provisions
of the UAO.  A fourth PRP, Phillips Electronics
North America Corporation, the parent company of
THAN  which exercises  pervasive control over
THAN,  has indicated that it will not comply with
the UAO because  it  does not believe  that it is
liable under CERCLA.

Helena  Chemical Company for Fairfax, South
Carolina Site:  On Thursday, May 26, 1994, EPA
issued a unilateral  order for the performance of
Remedial Design and Remedial Action to Helena
Chemical Company ordering  Helena  to begin
remediation at the above-referenced Site.

Rochester  Property  Site in Travelers Rest,
South Carolina:  On May 17, 1994, EPA issued
                                            A-32

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
a unilateral administrative order for Remedial
design/remedial  action  to  Colonial   Heights
Packaging, Incorporated, to conduct groundwater
remediation at the Rochester Property Superfund
Site located in Travelers Rest, Greenville County,
SC.    According   to the  most  recent  cost
documentation, EPA  has expended a  total  of
$303,446.50 through September 30, 1993.  EPA
will seek  to recover all past response costs and
will seek a commitment from Colonial Heights to
pay all future response costs.

Jones Tire and Battery  Site in Birmingham,
Alabama:   On May 3,  1994,  EPA  formally
requested   DOJ  to  concur in  a  de   miminis
Settlement with 79 small quantity generators at the
Jones Tire &  Battery Site in Birmingham, AL.
Cleanup  is  underway at the  Site and  is  being
conducted  by  large quantity generators  under a
UAO.   The de miminis  Settlement offer was
initially made to 219 PRPs, of which 79 indicated
their desire to accept the settlement.

Townsend  Saw   Chain  Superfund   Site   in
Pontiac,   Richland  County, North Carolina:
EPA issued a unilateral  administrative  order to
Textron,   Inc.,  to  conduct  an  Interim Action
Remedial Action to contain and control chromium
contaminated groundwater at the Site. The UAO
was signed on May 4, 1994, and was issued to
Textron, Inc., the owner of the Homelite-Textron
chainsaw chain manufacturing facility at  the Site.

Because unrestricted migration of the contaminated
groundwater at the Site may pose a possible threat
to private water-well  users living near  the Site,
EPA determined that an Interim Action Remedial
Action was necessary to control and contain the
contaminated groundwater plume.  Due to  the
time-critical nature of the proposed action, EPA
and Textron, Inc.,  determined  that a unilateral
administrative order,  instead   of a traditional
consent decree, would be more appropriate  as the
enforcement document  used  to  implement  the
Interim Action Remedial Action.

Yellow Water Road Superfund Site, Baldwin,
Duval County. Florida: On April 21, 1994, EPA
notified  102  desettlors   that   the  de   minimis
settlement for the Yellow Water Road Site was
finalized.  The public  comment period for this
administrative settlement expired on  April  11,
1994, and  no public comments were received
which caused EPA to seek modification of or to
withdraw from the settlement. The settlement will
recover  approximately  $300,000  in  EPA's
response  costs,  which   currently  total  over
$1,897,000.    In  addition, the  settlement  will
recover approximately  $1.3  million  in future
response costs and premium money.

Smith's Farm Site in Bullitt County, Kentucky:
On  April  22,  1994,  EPA   issued  unilateral
administrative orders, requiring 10 PRPs for the
Smith's Farm Superfund Site to  conduct  the
Remedial Design/Remedial Action  for Operable
Unit Two.  On October 28, 1993, special notice
letters were  sent to 41  PRPs  for Operable Unit
Two Remedial Design/Remedial Action at  the
Smith's Farm  Superfund Site.   These letters
envisioned  a  global settlement  including  the
remediation of both operable units at the Site and
the payment of past costs, which are currently the
subject of ongoing cost recovery litigation. Based
upon the PRPs failure  to present an  acceptable
final offer for settlement of the case, unilateral
administrative orders  were issued to all  PRPs who
did not qualify for a  de minimis settlement at the
Site.

Cedartown  Battery Superfund Site in Polk
County. Georgia:    On March 31, 1994, EPA
referred to  the Department of Justice  an action
against nine (9) potential owner/operator/generator
Defendants to recover approximately $1.5 million
in removal response costs for a Fund-lead removal
action at the Cedartown  Battery Superfund Site
(Site).

The  referral requests that DOJ file suit against
AmSouth  Bank, N.A., the current owner and
operator at the time the disposal occurred, together
with one (1) operator  and seven (7)  generators
who supplied batteries to  the Site.

Enterprise Recovery Systems Site in Byhalia.
Mississippi:  On March 23, 1994, EPA executed
an administrative order  on consent for de miminis
                                             A-33

-------
      } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
settlement  with  275  small  quantity generators,
regarding liability for an ongoing removal action
at the  Enterprise  Recovery  Systems  Site  in
Byhalia, Marshall County,  MS.   The settling
parties included  271 private Respondents and 4
settling   Federal  Agencies.    The   proposed
settlement provides a release from liability and
contribution protection  for  the  settling  parties
while raising  over  $500,000  to   assist major
generators  in  performing  the  removal  action
projected to cost approximately $1.3 million.

The City of Cedartown, Polk County, Georgia:
On March 25,  1994, EPA issued a  unilateral
administrative  order to the  City of Cedartown,
Polk  County,  and  12 private  companies  for
remedial response  activities at  the Cedartown
Municipal Landfill Site in Cedartown,  GA, some
60 miles northwest of Atlanta. The  UAO requires
the Respondents to maintain the  existing landfill
cover, repair seeps, maintain  institutional controls
including a ban on new drinking water wells in the
area, and monitor groundwater  quality through
sampling and analysis.

Bypass  601 Groundwater Contamination Site,
Cabarrus County, Concord, North Carolina:  In
accordance   with   the    recent   Superfund
Administrative Improvements Initiatives, EPA has
signed  a  consent decree  at  the   Bypass  601
Groundwater  Contamination   Site,   Cabarrus
County, Concord, NC. Entering into a precedent
setting settlement which embodies $10.1 million of
Preauthorization  Mixed Funding, a separate de
minimis settlement, and  a  unique  de  micromis
settlement included within the consent decree.

Through   detailed   records   and   ledgers,
approximately  4,000 PRPs were  identified at the
Site, including approximately 2,400 de micromis
Parties.   Of the non-de micromis  parties, only
approximately  500  PRPs   were   located,
approximately  150 of which  will  be treated as de
minimis, and each of these parties received Special
Notice  Letters in  August  1993.   The remedy
selected for the Site includes soil solidification and
stabilization, as well as an aggressive pump-and-
treat system.  The remedy  is expected to  cost
approximately  $40 million, but could escalate to as
much as $100 million, depending  on the soil
quantities to be treated.  Additionally, past costs at
the Site currently total approximately $4 million.

EPA has entered into a consent decree with the
Steering Committee at the Site which provides for
Preauthorization Mixed Funding of approximately
$10.1  million  under  the  newly  promulgated
regulations  at 40 C.F.R. Part 307, because of the
large orphan  share at the Site.  As part of the
settlement,  EPA will recover 100 percent of its
outstanding past costs.  Additionally, EPA has
negotiated a unique de micromis settlement within
the consent decree, which provides for a covenant
by the Settling Defendants not to sue de micromis
parties at the Site.  This approach achieves the
policy  goal  of  protecting small  parties   from
contribution suits and  unnecessary transactional
costs with a relatively low administrative burden
on the Agency.

This settlement also includes a separate traditional
de miminis settlement. The de miminis settlement
will be  embodied in a  separate AOC, and will
follow the new HQ guidance and matrix approach.
The de miminis settlement will also include the
same covenant language in  the  consent decree
regarding de micromis parties, thus affording these
parties greater protection.

Stoller  Chemical  Company  Site  in Jericho,
South Carolina:   On January 21, 1994,  UAOs
were sent to approximately 60 PRPs at the Stoller
Chemical Company Site in Jericho, SC, requiring
the implementation of a removal action.   EPA
documented the release of hazardous substances
from the facility during a Site Assessment in  June
1992 and determined that  a removal action was
necessary.

Firestone Tire &  Rubber Co. Site in Albany,
Dougherty County, Georgia:  The U.S. District
Court for the Middle District of Georgia, Albany
Division, entered  the  Remedial  Design  (RD)/
Remedial Action  (RA) consent  decree  for the
above-referenced  Site   on August  10,  1994.
Pursuant to   the  consent  decree,  Defendant
Bridgestone/Firestone, Inc., will perform soil and
groundwater  remediation estimated to cost $2
                                             A-34

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
million.  In  addition, the Defendant  agrees  to
reimburse EPA for all of its past costs totalling
$348,333 and for all of its future oversight costs;-

Woolfolk Chemical  Works  NPL Site.  Fort
Valley. Georgia:  On May 23,  1994, EPA issued
a CERCLA  §106 UAO to three PRPs  at the
Woolfolk Chemical  Works Site.  The  order
requires the PRPs to implement the RD/RA for
Operable Unit 1, which will address groundwater
contamination at the Site.

One PRPj Canadyne-Georgia Corporation (CGC),
is  the former owner/operator of a  pesticide
formulation plant at the Site and current owner  of
a portion of the Site.  The other two PRPs are the
first and second-level parent corporations of CGC.

CGC has submitted a notice of its intent to comply
with the UAO,  which will cost approximately $4
million.  Canadyne  Corporation  and  Reichold,
Limited have indicated that they will not comply,
with the UAO.

Hercules 009 Landfill Site, Brunswick,  Glynn
County,  Georgia:  On November 29, 1993, the
U.S. District Court  for  the Southern District  of
Georgia  entered a consent decree executed by
Hercules, Incorporated, (Hercules), the EPA, and
the Department of Justice. Under the terms of the
consent decree, Hercules will  conduct the final
remedial   design  and  remedial  action, , and
reimburse the government for all past and future
costs associated with the Site.  Under the terms  of
the consent  decree  entered  by  the  Court on
November  29,  1993, Hercules  will perform the
remedial action enumerated  in the  Record  of
Decision designated OU#1.  The remedial action
will consist of a removal action to consolidate
soils, and a treatability study followed by in-situ
stabilization of toxaphene-contaminated soil. The
remedy is expected to cost about $10 million; the
settlement also requires Hercules to reimburse the
government for all past costs ($544,199) as well as
100 percent  of. all future response and oversight
costs.

U.S. v. Otto Skipper (E.D., N.C.):  On  October
21, 1993, the court entered a CERCLA consent
decree resolving the liability of the McLambs 'and
Investors Management Corporation  (IMC) with
respect to the Potter's Pits Site. EPA's past costs
total $1,822,477, while projected future costs total
$10 million.   Within 30 days  of entry of  the
decree, the  McLambs,  who  are  also  the  sole
representatives of the now defunct EMC, will pay
a lump sum  of $230,000 to  resolve their liability
and the liability of IMC.

National Southwire Aluminum Superfund Site
in Kentucky:  On April  19,  1994, the U.S.
District Court for the Western District of Kentucky
entered a consent decree for performance of an
interim remedial action at the National Southwire
Aluminum (NSA) site in Hawesville, KY. Under
the terms of the  settlement, NSA will  perform
interim  cleanup  actions and  reimburse  EPA
$407,544 in  past response costs.

Prairie  Metals and  Chemical  Company  Site
(Prairie, Mississippi):  On  September 28,  1994,
EPA  referred  to  the  Department of Justice  an
action against two potential  owner Defendants to
recover approximately $1.4 million in costs for a
Fund-lead removal action conducted at the Prairie
Metals and  Chemical  Company  Site (Site)  in
Prairie, MS.  Beginning in  1973 and continuing
until February 1977, the Site was operated  as a
chromium metal production facility. Operations at
the Site resulted in serious levels of chromium in
the Site soils and surface water.   Between 1989
and 1991, EPA conducted  a Fund-lead  removal
action at the Site expanding approximately  $1.4
million.
                                             A-35

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                        REGION V
REGION V's CONTEMPT INITIATIVE

As part of an effort to crack down on violators of
Federal consent decrees and orders, Region V and
DOJ  took  eight enforcement  actions  in the
Midwest during FY94.  In addition, Illinois EPA,
the Illinois Office of the Attorney  General, Ohio
EPA, and the Ohio Office of the Attorney General
also recently took separate actions to enforce State
decrees and orders. The following  are summaries
of the FY94 Regional cases.

Anthony Chambers (Midland, MI):  Anthony
Chambers  operated  two  underground-injection
wells in Midland County  without  the permits
required under the Safe Drinking Water Act. He
failed  to comply with an  administrative  order
requiring that he pay a 48,650 civil penalty and
either demonstrate the mechanical integrity of his
wells or plug and abandon  them.   The United
States filed an enforcement action on June 7, 1994
against  Mr.  Chambers in U.S. District  Court,
Eastern District of Michigan.  Through this action,
EPA seeks to enforce the terms of the order and to
collect penalties for noncompliance with the order
and the Act.

Big  D  Campground/Rodebaughs (Ashtabula,
OH):  Joseph and Glenna Rodebaugh failed to
comply with a March 1994 access agreement at
the Big  D  Campground Superfund site.   The
Rodebaughs refused to allow EPA  access to their
170-acre property, where EPA plans to install four
groundwater-extraction   wells   to   intercept
contaminated  groundwater  leaching  from the
campground. After EPA referred this matter to
DOJ, the Rodebaughs agreed to provide access to
their  property  at  the  campground  site.   No
penalties were sought in the agreement.

Petoskey Site (Petoskey, MI):  The PRP  at this
Superfund  site,  Petoskey  Manufacturing  Co.
(PMC), filed for protection under bankruptcy laws.
PMC agreed in bankruptcy court to  reimburse
EPA for some of the costs the Agency incurred at
the Petoskey Superfund site, but was delinquent in
its payments.  On May 19, 1994, the United States
filed a motion for conversion or dismissal in the
Bankruptcy Court  for  the  Western District of
Michigan.

Copperweld Steel (Mahoning. OH): Copperweld
Steel Co. uses an electric arc furnace process to
manufacture steel and steel alloys.  This process
generates furnace dust (a hazardous waste). This
waste is disposed of in a landfill at the site.  In
1986, a complaint was  filed in the U.S. District
Court,   Northern  District  of   Ohio,   against
Copperweld for failing to obtain either  interim
status or a permit under RCRA as  well  as for
other  RCRA  violations.  A May 1990 consent
decree  with  Copperweld  required  numerous
compliance activities  including closure and post-
closure care of the landfill.  On November 22,
1993, Copperweld filed a Chapter 11 petition for
bankruptcy. In a proof of claim filed on April 20,
1994, with  the U.S. Bankruptcy  Court, Northern
District of Ohio, the United States is seeking to
enforce the terms of the 1990 decree. Specifically,
EPA is seeking  the payments that Copperweld
committed to  make to the site's post-closure trust
fund.

Midwestern  Drum Services (Venice, IL):   In
November  1989,  EPA  filed  an  administrative
complaint against Midwestern Drum Services, Inc.,
for RCRA  violations.    A  December 1990
administrative agreement resolved the complaint
and required  that $112,125  in civil penalties be
paid in six installments. Midwestern Drum failed
to make  full, timely  payments for the last four
installments.  It now owes approximately $74,000
(not including interest and late payment charges).
On September 13, 1993, the company filed for
Chapter 11  reorganization in the U.S. Bankruptcy
Court of the Southern  District of Illinois.  On
February 4, 1994, DOJ, on behalf of EPA,  filed a
proof-of-claim with the bankruptcy court seeking
payment  of  the  amount  owed  under  the
administrative agreement and additional penalties
for noncompliance.
                                            A-36

-------
                                                                                         f^ '
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT!tw?l
 Silvertone Plating Company  (Ypsilanti.  MI):
 Silvertone generates spent stripping and cleaning
 bath  solutions  containing  chromic  acid  and
 cyanide, along with other hazardous wastes. On
 October 15,  1992,  the United  States filed  a
 complaint against the company for its repeated
 failure to fulfill its obligations under an April 1988
 administrative agreement with EPA.  Specifically,
 Silvertone failed to submit and carry out a closure
 plan for its facility, remove all hazardous waste in
 90 days, and  comply with applicable hazardous
 waste regulations. Silvertone had agreed in a May
 1993  consent decree  to   comply  with   these
 obligations, to submit and carry out a closure plan
 and to pay a $1,000 civil penalty.

 GTE North (Belvedere. ID: Under a March 19,
 1993 consent decree, GTE North was required to
 reimburse EPA for $575,000 in costs related: to
 cleanup  activities at  the Belvedere Municipal
 Landfill Superfund site.  Although the  decree
 required GTE North to pay  by  April 1993,  EPA
 did not receive payments until late July 1993. The
 decree carried a proviso that GTE North would
 pay stipulated penalties of $1,000 a day for each
 day of violation.  In response to EPA's demand,
 GTE North has tentatively agreed to pay $30,000
 in  stipulated  penalties,   in   addition  to another
 $10,500 in interest payments.

 Bethlehem Steel Corporation  (Burns Harbor.
 IN): This matter arose from U.S. EPA's discovery
 that Bethlehem Steel Corp. was in violation of a
 May 1991 partial consent decree.  The violations
 involved visible  emissions  from a  coke   oven
battery.  On December  30,  1993, EPA advised
Bethlehem of the violations and assessed stipulated
penalties  of  $255,750.     Bethlehem  quickly
responded by paying in  full  the entire stipulated
penalty, and the matter was  resolved  without
litigation.

ILLINOIS CASES

Illinois EPA took action  against two violators for
contempt:    Robert  Krilich  d/b/a Lakemoor
Building  Associates   (Lakemoor,   IL)   and
Enamelors & Japanners of Chicago.
 OHIO CASE

 The State of Ohio took a contempt action against
 Union Cheese Co. of Holmes County.

 CLEAN AIR ACT

 FY94 was a highly successful year for Region V's
 air enforcement program, marked by record levels
 of initiated actions and administrative resolutions.
 Increasingly, these  accomplishments flow  from
 efforts to target Federal  enforcement activity.  In
 1994, the  Region  targeted sources .located in
 specific  geographic  areas   that  have   high
 concentrations   of   industry,   a  history   of
 environmental insults, and are often significant for
 environmental justice reasons. Also targeted were
 sources   that  are subject  to  the many  new
 regulatory requirements of the Clean Air Act, and
 industrial  categories   which  are  technically
 complex.

 B&W Investment Properties, Inc., and Louis
 Wolf:  On October 24,  1994, the U.S. Court of
 Appeals for the Seventh Circuit upheld a February
 17,  1994,  District Court's decision that B&W
 Investment Properties Inc., (B&W), Chicago, and
 Louis Wolf should pay a civil penalty of $1.675
 million.  The Appellate Court also upheld the
 District Court's September 30, 1992, decision to
 grant the  Government's motion  for  summary
judgment on liability.

 The  case involved an improper asbestos removal
 project which  took  place in  August  1990, at  a
 former factory complex  in Cicero, Illinois.  The
 property  was  owned  by Mr. Louis Wolf and
 managed by B&W.  Asbestos.removal operations
began at the site without the prior notice required
 by U.S.  EPA's  asbestos NESHAP regulations.
The  work  practices used in  the  removal also
 violated the NESHAP regulations. In late August
 1990,  EPA   issued  ah  administrative  order
 requiring   compliance   with   the   NESHAP
 regulations at the site.  The buildings, at that time,
 were unsecured  and  located  adjacent to  the
 terminal of a Chicago Transit Authority commuter
 rail  line.   Transients   occasionally  used  the
 buildings in the complex for shelter.
                                            A-37

-------
       | FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Louis Wolf and B&W argued that they were never
given a notice of violation prior to the filing of the
complaint. B&W and Louis Wolf also argued that
they were not owners or operators as those terms
are defined in the regulations. They also argued
that they had no prior knowledge of the renovation
project. Both the District Court and the Court of
Appeals   found  the   arguments  irrelevant  or
unpersuasive.  B&W and .Louis Wolf challenged
the size of the penalty awarded by  the District
Court after a  trial on the penalty.

The Court assessed fines of $1,675,000 against
both defendants, but reduced Mr. Wolfs liability
to $1,500,000 based  on his inability to  pay a
higher penalty.  The penalties were assessed only
for the work practice violations of the asbestos
regulations. No penalty was assessed for failing to
provide EPA prior notice of the project because, in
part, Mr. Wolf was in the hospital at  the time of
the violation  and the penalty already imposed for
the work  practice violations had exhausted  his
ability to pay additional penalties. (SIC/N/A)

New Boston Coke Corp. (S.D. Ohio):  In October
1993, more than 3 years after the government filed
a motion in Federal Court (S.D. Ohio) to compel
New Boston Coke Corp. (New Boston) to comply
with a 1986 consent order at its New Boston, OH,
a major modification  to the consent decree  was
entered with  the court. In the settlement, New
Boston agreed to maintain compliance at its coke
oven battery,  rebuild a major portion of the rest of
the plant,  and  install  equipment to  control  the
emission of hazardous benzene. As a result of the
rebuild, numerous leaking process vessels  and
storage tanks were to be  replaced,   eliminating
wastewater discharges to  the Ohio   River.   In
addition, wastewater treatment equipment is to be
installed  to treat other coke  plant  wastewater,
which had been discharged to the atmosphere as
steam. The agreement also assesses a $250,000
civil penalty.  (SIC/3312)

U.S.  v. Consolidated Papers, Inc.  (Wisconsin
Rapids. WI):  An  October  19, 1993, consent
decree (U.S.  District  Court, Western  District of
Wisconsin) settles the Clean Air Act case against
Consolidated  Papers,  Inc.  (CPI).    CPI  must
achieve,  demonstrate and  maintain  compliance
with  the  Federal   Prevention  of  Significant
Deterioration  (PSD) regulations  and  pay  a
$510,000 civil penalty. The case arose from CPI's
violation of the particulate limits contained in the
PSD permit for its lime kiln.  The case was filed
in September 1992 (after a notice of violation) as
part  of the Agency's pulp and paper industry
initiative.  (SIC/2611)

Monitor Sugar Co. (E.D. Mich.):  Monitor Sugar
Co. has agreed to pay $1.06 million to the State of
Michigan  and  the   Federal  Government  after
reaching a  settlement  with  the  DOJ.   The
agreement ends the  court case against Monitor
Sugar brought by EPA for violations of a 1987
consent judgment.   Specifically,  on January 7,
1993, the District Court for the Eastern District for
Michigan  held  Monitor Sugar in  contempt for
failing  to comply  with the judgment and ordered
the  company   to pay  $478,500  in  stipulated
penalties.  Following the court decision, Monitor
agreed   to  settle two  outstanding  issues for
$581,500 and forego appealing the decision.  In
the past year, Monitor Sugar replaced  its  three
coal-fired boilers with three new natural gas-fired
boilers.    This change  alone is expected  to
eliminate the ongoing opacity violations of the old
boilers.  (SIC/2063)

Stern Enterprises,   Inc.,  et  al.  (U.S. District
Court for the Northern District of Ohio/Eastern
Division):  Under this  July  18,  1994, consent
decree with Stern Enterprises,  Inc., Elie Wrecking
Co., Obie  Elie,  Herbert  Sugarman  and the
executors of the Estate of Ernest Stern must pay a
$205,000 civil penalty for asbestos violations at a
Cleveland  facility.   Additionally,  the consent
decree  requires the  owners to do what citizens,
city  officials  and  local judges  unsuccessfully
demanded for years—abate all the  asbestos at the
facility. The settlement was especially significant
because it obtained  relief for minority and low-
income   persons  who   are   disproportionately
affected by the environmental hazards posed by
asbestos.

This case was unique because  it was the first time
the Government has alleged in a  Clean Air Act
                                             A-38

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
judicial complaint  that  the  stripping activities
conducted  by  vandals  in a  vacant  building
constitute  a "renovation,"  as defined  in the
regulations  thus  subjecting the owners of the
facility to a civil judicial penalty.  After vigorous
opposition, the defendant finally agreed to pay the
Region's  second  largest  civil penalty  for an
asbestos  NESHAP  case  for  a  judicial  case.
Furthermore,  the defendants  have  agreed to
remove all remaining asbestos in the facility at a
cost of $1 million.  (SIC/N/A)

CLEAN WATER ACT

LTV Steel (East Chicago, IN): On .February  1,
1994,  EPA  'approved   LTV's   court-ordered,
sediment  remediation and disposal plan.   It
outlines the removal of all of the oil-contaminated
sediment  (approximately 110,000  cubic  yards)
from LTV's No. 2 Intake flume, located off Lake
Michigan.  The remediation project which began
in July 1994 consists of removing sediment (via
diver-assisted vacuuming of the sediment) and de-
oiling/de-watering it (via coagulation/flocculation
in  conjunction with  final sand-filtering of the
discharge and belt filter pressing of the sludges).
The de-oiled/de-watered solids are being disposed
of in a special-waste landfill in Wyatt, IN.  Oils
from the sediment are being recycled back into the
facility's waste oil reclamation system. The final
discharge of any waters  from the remediation
project are sent_ through  an NPDES-permitted
outfall. LTV's estimated $3 million remediation
is  part  of the  Region's  Northwest  Indiana
initiative.   (SIC/3312/blast furnace/steel works/
rolling.)

JMB Urban Development Company (Columbus,
OH):   A January  1994  consent  decree  (U.S.
District Court  in Columbus, OH)  resolved all
Clean Water Act allegations  against JMB Urban
Development Co., Chicago. EPA alleged that the
JMB violated Sections 301 and 404 of the Act by
discharging  dredge   and  fill  materials  into
approximately 37 acres  of wetlands  adjacent  to
Olentangy River during the initial development of
a shopping mall.  JMB must mitigate the violation
by constructing an 80-acre wetland to be donated
as  an educational facility to the local  school
district. The total injunctive relief in excess of $1
million, includes a civil penalty of $200,000 also
paid  by  the  defendant.     (SIC/1542/general
contractor, non-residential buildings.)

City of Middletown (OH):   A February 1994
consent decree  (U.S. District  Court  for  the
Southern  District  of Ohio/Eastern   Division)
resolves the combined NPDES, pretreatment, and
wetlands case against  the City  of  Middletown.
The City's wastewater treatment plant  was cited
for past NPDES effluent limit violations (total
suspended solids, fecal colifbrm, and ammonia),
failure to  adequately  carry  out  its  approved
pretreatment  program, and  filling in , a ; river
channel of the Great Miami River  to  expand a
City park.  The City contracted for professional
services to administer its pretreatment program and
made plant improvements costing $209,000.  A
total   civil    penalty  of   $288,000   was
assessed—$188,000 for CWA §402 violations, and
$100,000 for CWA §404 violations.  (SIC/4952/
sewerage systems).

Wayne County-Wyandotte (MI)  Wastewater
Treatment Plant:  A May  1994 consent  decree
(U.S. District Court, Eastern District of Michigan/
Southern  Division)  resolved  Wayne  -County's
water  violations  at  the  Wyandotte wastewater
treatment plant and tributary sewer systems.  In
1987,  the Government filed suit against Wayne
County and 13 tributary communities for illegally
discharging untreated wastewater into the Detroit
River  and  Lake  Erie.  The  defendants paid a
$413,000 civil penalty (equally divided between
the United States and the  State of Michigan).
Injunctive  relief will  consist of sewer system
rehabilitation,   plant  improvements,   and
construction  of  a  tunnel   storage system  for
overflows.   The  estimated $230 million project
will take about 6 years to complete. This  case is
located within the Southeast Michigan Initiative
area.  (SIC/4952/sewerage systems).

IBP. Inc. (Joslin, IL)t A July 26, 1994, consent
decree (U.S. District Court in Rock Island,  IL)
resolved all outstanding violations alleged by U.S.
EPA   and  Illinois  EPA   in their   respective
complaints against IBP, Inc. of Joslin, IL.  The
                                              A-39

-------
       IFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 Agencies alleged that IBP had repeatedly violated
 the effluent limits  of its  NPDES .permit  for
 ammonia-nitrogen, total  suspended solids,  and
 fecal coliform.  EBP must pay civil penalties of
 $250,000 to the United States and $30,000 to the
 State, expand  its current wastewater  treatment
 system and install equipment to treat ammonia-
 nitrogen.  The case is significant because IBP was
 unsuccessful in  its  attempt  shield itself  from
 enforcement by adjudicating its NPDES permit
 limits.  (SIC/201 I/meat packing plants and 311II
 leather tanning & finishing.)

 Appleton Papers  (Appleton, WI):  A July  1994
 consent decree with  Appleton Papers, Inc. (U.S.
 District Court in the Eastern District of Wisconsin)
 resolved this 1992 pretreatment case.  EPA had
 cited the facility for violating bypass provisions
 and local limits for  aluminum, copper, zinc and
 pH. Injunctive relief was not required because the
 company  has maintained  consistent compliance
 since it installed the necessary treatment plant and
 pretreatment equipment.    The   civil  penalty
 assessed was $670,000, plus interest from the date
 of  lodging.    (SIC/267 I/coated and laminated
 packaging.)

 Commonwealth  Edison    Company,   Inc.
 (Chicago. IL):  EPA's August 1994 consent order
 to Commonwealth Edison Co. (CpmEd), Chicago,
 resolved this case involving Section 301  and 404
 violations.  ComEd had discharged dredge and fill
 materials  into  2  acres of  wetlands in South
 Chicago. The consent agreement requires ComEd
 to pay a $10,000 civil penalty and to contribute a
 minimum of $90,000 to the Nature  Conservancy
 for the purchase and preservation  of the Indian
 Boundary   Prairie  in   Markham,    IL.
 (SIC/491 I/electrical services).

 MULTIMEDIA CASES

 Taracorp Industries (Granite City, ID:   On
 September 19,  1994,  the U.S. Southern District
 Court of Illinois' decision  resolved a multimedia
 civil action filed against Taracorp Industries, Inc.,
 of  Granite  City,  IL.   EPA  had  alleged  that
Taracorp violated the Clean Water Act (excessive
discharges of lead and antimony to Granite City's
 wastewater treatment plant) and RCRA (financial
 assurance violation).  The Court awarded a cash
 civil penalty of $201,850 and $199,500,for the
 RCRA and CWA violations,  respectively.  No
 injunctive  relief  was necessary since Taracorp
 completed  installing the  required  pretreatment
 system before the trial.

 Importantly,   the  Court   rejected  Taracorp's
 argument that its delay in installing the treatment
 system caused economic detriment (rather than
 benefit)  due   to  inflation,  higher  fees  and
 equipment costs.  As the Court ruled these higher
 costs   resulted  directly   from   defendant's
 noncompliance and deemed it "inappropriate to
 view as mitigation  a cost that  the  defendant
 incurred only because it did not comply with the
 Clean Water  Act."   On  September  30,  1994,
 Taracorp filed a motion to amend the conclusions
 of law and judgment  on the CWA count. Region
 V filed a motion  in opposition in October 1994.
 To date, the Court has not ruled on EPA's motion.
 This case is located within the Gateway (East St.
 Louis) Initiative area.   (SIC/3356/roll, draw  &
 extruded nonferrous).

 Glidden Company  (Strongsville,  OH):    In
 December  1993, Region V settled  enforcement
 actions under TSCA  and FIFRA against Glidden
 Co. for importing and distributing an unregistered
 pesticide.   Glidden  had made  a  series of self
 disclosures  to EPA regarding violations of TSCA
 §§ 5, 8, 12, and 13. This case marks the first time
 that Region V has taken simultaneous actions for
 violations of both TSCA and FIFRA.  Glidden
 paid a total penalty of $290,100.  (SIC/2851)

 EPCRA

 Vie De France (Bensenville. ID:  On  February
 14,  1994,  The Region filed an  administrative
 complaint seeking a $247,140 penalty against Vie
 De France, Bensenville, IL, for failing to report to
 authorities both its release of anhydrous ammonia
 and  its storage of ammonia.    The complaint
 addresses Vie  De France's May 1991 release  of
 about 4,000 pounds of anhydrous ammonia due to
a  broken  pipe  in  the  refrigeration  system.
Employees  were evacuated  and the doors of the
                                            A-40

-------
                                                                                       0^ '
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I rw^»|
 plant were opened to vent the ammonia.  Vie De
 France notified the National Response Center and
 the  State Emergency  Response  Commission
 (SERC)  26  days after  the  release  but never
 notified the Local Emergency Planning Committee
 (LEPC). The company submitted a written follow-
 up report to the SERC 43 days after the release,
 but never a written follow-up report to the LEPC.
             > ' -
 The maximum quantity of ammonia stored at the
 facility  during each of the calendar years 1989-
 1991 was  5,000 pounds.    Ammonia  is an
 extremely hazardous substance with a threshold
 planning quantity of 500 pounds.  The facility has
 never submitted Material Safety Data Sheets under
 Section  311 of EPCRA and has never filed a Tier
 report under Section 312 of EPCRA to the SERC,
 LEPC, or local fire department. (SIC/2051)

 HRR Enterprises. Inc. (Chicago. ID: On March
 28,  1994,  the  Region  filed  an administrative
 complaint  seeking a  $186,450 penalty  against
 HRR Enterprises, Inc. (a division  of Kane-Miller
 Corp. Chicago) for failing to immediately report a
 toxic release. In July 1992, HRR  Enterprises had
 released 200 to 300 pounds of anhydrous ammonia
 but  failed  to  notify Federal,  State and  Local
 emergency-response officials for more  than 24
 hours.  EPA further alleges that HRR Enterprises
 failed to file a Material Safety Data Sheet for
 anhydrous ammonia.' HRR Enterprises did not file
 an Emergency and Hazardous Chemical Inventory
 Form from 1987-1990 and filed late reports 1991.
 (SIC/2079)

 Shell   Oil   Company's   Wood   River
 Manufacturing  Complex (Roxana. ID:   The
 $431,312 penalty required by this September 1994
consent  agreement with Shell  Oil  Co.'s Wood
River Manufacturing Complex, Roxana, IL, is the
highest to date for violations of CERCLA 103(a)
and EPCRA 304.  In a 1992 compliant, EPA had
alleged  that 57  separate violations arose from
Shell's failure to  immediately notify the proper
Federal,  State and local emergency authorities
about a  number of separate releases  at various
locations.   EPA cited Shell for  air releases of
benzene, hydrogen sulfide, methyl mercaptan and
sulfur dioxide, and a sulfuric acid release to the
 ground. The Region also cited Shell for failing to
 provide emergency follow-up notices after each
 release.

 Shell Oil's answer to EPA's complaint claimed
 that many of the releases were Federally permitted.
 The company interpreted CERCLA 101 (10)H to
 mean that having ia permit or being subject to a
 control  regulation exempted  it from  CERCLA
 103(a) emergency notification requirements.  The
 company  also  claimed  that  the  hazardous
 substances released were fractions of petroleum
 and thus exempt under CERCLA. EPA contended
 that  individual   chemicals  were  released.
 (SIC/2911, 4612, 5541,1311,2821, and 1221)

 Consumers  Power Co. (West Olive, MI):   A
 September  1994   consent  agreement resolved
 EPA's administrative complaint against Consumers
 Power  Co.,  West  Olive,  MI,  for  EPCRA
 violations. The company agreed to carry out three
 supplemental environmental projects (SEP's) at a
 total estimated cost of $247,741.50.  The projects
 are:  (1) convert heat exchangers from ethylene
 glycol to propylene glycol which is 300 times less
 toxic;   (2)   send  information   on   EPCRA
 requirements  (via  mail) to an estimated  3,000
 facilities in  Ingham,  Kalamazoo,  and Ottawa
 Counties; and (3) conduct an outreach program on
 the EPCRA  302 notification requirement to the
 rural community in Ingham and Ottawa Counties.
 The company must also certify its compliance with
 EPCRA. In its complaint, EPA alleged that the
 company failed to notify Federal, State and  local
 authorities about an accidental release of 1,400
 pounds of sodium  hypochlorite. The total  cash
 penalty  and  estimated cost  of the SEPs equals
 $255,769.50 or 2.5 times EPA's proposed penalty
 of $100,000.  The settlement requires  a $7,828
cash penalty to be paid to a Superfund account.
(SIC/4911)

Karmazin Products Corp.  (Wyandotte, MI):
EPA's   May   1994  consent  agreement   with
Karmazin  Products, Corp.,  Wyandotte,  MI,
required a $195,560 penalty to resolve a  1993
complaint alleging that Karmazin failed to notify
the proper authorities that it stored large quantities
of hazardous chemicals. This violation contributed
                                           A-41

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
to the  injury  of 3  Karmazin  employees,  12
firefighters, and 8 police officers who. responded
when an employee was overcome by vapors when
using trichloroethylene to clean an underground,
sludge-filled pit.  That employee later died  from
exposure  to   trichloroethylene.     (SIC/3443/
3585/3531)

TSCA

University of Illinois (Champaign-Urbana, IL):
A January  1994 consent  agreement  with the
University  of  Illinois  called for  a  $74,500
supplemental environmental project and a $1,000
fine to  resolve PCB violations.   EPA cited the
university improperly storing six 55-gallon drums
of PCB's and 524 large PCB  capacitors. These
drums  and  capacitors  were  moved  from one
building to another for storage, awaiting disposal.
During  the move, PCB's were spilled or leaked at
several  places  between the  buildings.   Under
Federal regulations, leaks  and spills constitute
illegal disposal. The stringent agreement calls for
the university to remove and dispose of the PCB
items   from  the  Environmental  Engineering
Research Laboratory and the Aeronomy Field as
partial settlement.

Wavne State University (Detroit, MI):  EPA's
March  1994 consent agreement with Wayne State
University included  a  $631,000  supplemental
environmental  project  as well as a $7,150 fine.
The university was cited for violating Federal rules
on PCB use and recordkeeping.  As part of the
agreement, the university did asbestos abatement
work at several buildings on campus.  Removing
friable  asbestos  from Wayne State's buildings
prevents its potential release into the environment.

U.S. Graphite.  Inc.  (Saginaw. MI):   EPA's
March   1994  consent  agreement  with   U.S.
Graphite, Inc.,  to resolve PCB includes a $10,000
 fine and  removal  of  more  than 500  PCB-
contaminated transformers and capacitors  at an
estimated cost  of $195,000.  Earlier the company
 had  spent  $32,025   to  remove  two   PCB-
 contaminated transformers and 16 PCB capacitors.
 EPA had cited U.S. Graphite for improper use,
 disposal, marking,  storage, and recordkeeping of
PCB  equipment.   This  outstanding  settlement
moves Region  V closer to the goal of totally
eliminating all PCB's.

RCRA/UST

BASF Corp. North Works  (Wyandotte. MI):
EPA's March  1994  consent  order with BASF
Corp. called for an investigation into hazardous
waste at its Wyandotte site.   BASF agreed to
evaluate  the  effectiveness  of  a  groundwater
cleanup project already proceeding under State
consent orders and to investigate the nature  and
extent  of   present   soil   and   groundwater
contamination at the facility.   In its order, EPA
specified  that  the   company  must  perform
appropriate  cleanup  if  the investigation shows
additional dangerous  contamination.

BASF's North Works facility is a 230-acre site on
the Trenton Channel of the Detroit River.   The
facility  has been a  source of hazardous  waste
releases to the river in the past. EPA is concerned
that hazardous wastes from the facility may still be
migrating into the  river.    While  owned  and
operated by BASF,  the North Works has been
used  as  a  manufacturing, research, and  pilot
projects  site for  industrial  organic  chemicals,
polyether polyol resins, polyurethane plastics and
castings, vitamins A and E. The site was used for
the manufacture  of  soda and coke in the  late
1800s.

Hilton Davis Co. (Cincinnati. OH): EPA's  July
1994 administrative  order to Hilton  Davis  Co.
proposed a $1.6 million  penalty  for hazardous,
waste violations at its Cincinnati, OH, plant.  EPA
alleges  that the  company failed  to:   conduct
adequate  waste analysis; properly monitor  and
record  operating parameters;  develop a closure
plan; establish financial  assurance  for closure;
monitor  equipment  leaks;   submit  accurate
precompliance certification,   and  comply   with
emissions standards for  ash, chlorine, arsenic,
chromium and lead.

The Hilton Davis plant makes organic chemicals
 including dyes, food colors, organic pigments, and
 optical brighteners. It also generates, treats, stores,
                                              A-42

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
and deposes of hazardous wastes.  Until August
1992, the plant operated a boiler using hazardous
waste from as many as 60 different processes as
fuel.  As a result, it had  to comply with EPA
regulations for boilers and industrial furnaces,
known as the BIF rule which became effective in
August  1991.

Greater Cleveland Regional Transit Authority
(Cleveland. OH):  In August 1993, Region V
filed  an administrative  complaint  against the
Greater  Cleveland Regional  Transit Authority
(GCRTA) for alleged  violations of underground
storage  tank (UST) regulations at three of its
facilities. EPA alleged that GCRTA failed to meet
construction,  notification, release detection, and
closure requirements at its Brooklyn, Triskett, and
Hagden  facilities.  Violations were  uncovered
during an April 1992 inspection, and a complaint
was  issued  when a March  1993  follow-up
inspection  revealed repeated  and uncorrected
violations.

On August 12, 1994,  after less than a year of
negotiations, the Region  and GCTRA reached a
verbal   agreement  that  was  formalized  in  a
September  CAFO.   GCRTA  corrected  all past
violations and paid $174,718 in penalties.

Northwest Airlines, Inc. (Saint Paul. MN):  In
February 1993, Region V filed an  administrative
complaint against Northwest Airlines for alleged
violations   of   UST   regulations   at  its
Minneapolis/St.   Paul  airport   facility.    The
complaint  proposed  a  $115,710  penalty  and
alleged   that   Northwest  failed to  meet  tank
notification and release detection requirements. A
February  CAFO   requiring  a   $54,989   and
compliance resolved this case.

U.S. v.  Bethlehem Steel Corp. (7th Cir. 1994):
On September 26, 1994, the court affirmed in part
and vacated in part the district court's  grant of
summary judgment in  this  action.  The  Seventh
Circuit  upheld the district  court's rejection  of
impossibility  as  a defense to  allegations that
Bethlehem  Steel   failed to  comply with  the
corrective action requirements of its IUC permit.
The corrective action claim accounted  for $4.2
million of the district court's 1993  $6 million
judgment in this case. The vacated portions of the
decision involved the  government's claims that
Bethlehem Steel  had illegally disposed of F006
waste   (wastewater  treatment  sludge   from
electroplating operations, which can contain such
hazardous  constituents as hexavalent chromium
and cyanide).

U.S. v. Ekco Housewares, Inc. (Massillon, Ohio):
On January  28,  1994, the  court issued  a $4.6
million judgment for the government based on
Ekco's failure to maintain financial assurance for
closure, financial assurance for post-closure, and
liability coverage.  This case arose because Ekco
generated waste products at its Massillon, OH,
facility which it discharged to an on-site surface
impoundment.  In its complaint, the United States
cited violations of  both  a  1987 Partial Content
Agreement and Order (PCAO), and RCRA rules
(including   financial   assurance  and  liability
insurance provisions.  Ekco appealed the penalty
assessment to the U.S. Court of Appeals for the
Seventh Circuit.

U.S. v. Laclede Steel Company:  Laclede Steel
entered into  a  consent decree settling this civil
judicial action  for violation  of RCRA's land
disposal  restrictions  (LDR)  rules.     In  the
complaint, the United States alleged, among other
things, that Laclede had illegally land disposed of
tons of lead-bearing K061  electric  arc  furnace
baghouse  dust.   The consent,  decree  requires
Laclede to pay a $300,000 civil penalty, complete
an environmental audit, and remediate its illegal
waste  piles,  in accordance  with  the State  of
Illinois-approved closure  plan, using a new, $25
million  High  Temperature   Metals Recovery
(HTMR)unit.

City of Columbus, Ohio and the Solid Waste
Authority  of Central Ohio:  An RCRA §7003
administrative order was  issued on September 9,
1994, by EPA to the City of Columbus (owner)
and the Solid Waste Authority of Central Ohio
(SWACO)  (operator).  The  order  required the
respondents to  conduct  measures to abate the
potentially  imminent threat to public health and
the environment posed by  the past  and  present
                                             A-43

-------
      } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
emissions of dioxins.   The incinerator, which
burns approximately 1,700 tons of trash daily, was
determined by a stack test in 1992 to have among
the highest MWC dioxin emissions in the nation
(i.e.t an average concentrations of 13,000 ng/dscm,
with  highest  concentrations  at  nearly  18,000
ng/dscm).

SDWA

Total  Petroleum  (Alma. MI):  A May  1994
consent order resolved EPA's  case against Total
Petroleum  for failing  to: maintain the annulus
pressure differential in an on-site injection  well,
report the violation and,  sign the monitoring
report.   Class  I wells are the most  likely  to
endanger drinking water. The pressure differential
is a safeguard necessary to ensure even leaks will
not stop the  waste from flowing to  its intended
zone, not to  an underground source of drinking
water. (SIC/2911/petroleum refining).

George  Perry  (Oceana County, MI):  EPA's
December  1993 consent order resolved the case
against Perry for failing to  plug and abandon a
Class II injection well that was in disuse for more
than  2  years.   Not only  did Perry  plug the
injection well, he agreed to a SEP to plug three oil
production wells also in disuse.  EPA does not
regulate oil production wells. Perry's actions will
eliminate four potential sources of contamination
to  underground sources   of  drinking   water.
(SIC/1311.)

JPT  Petroleum  Production  Corp.   (Gibson
County, IN): On February 1,  1994, the Indiana
Department of Natural Resources and JPT signed
an administrative agreement  regarding  missed
deadlines for demonstrating mechanical integrity
of three Class  II wells.   The agreement also
addressed minor violations associated with nine oil
and gas wells in Gibson County. These violations
were discovered through file reviews and routine
inspections conducted in 1992.  JPT agreed to pay
a $3,000  penalty.   This  action  will prevent
contamination of underground sources of drinking
water.  (SIC/131 I/crude petroleum & natural gas.)
Gahanna Water Department (Gahanna. OH):
A June  1994 consent order resolved EPA's case
against  the  Gahanna  Water  Department  for
violating public notice requirements. Gahanna has
agreed  to  notify  the  public  of its  failure  to
complete  monitoring  on  time.   In  addition,
Gahanna completed a  second round of lead and
copper monitoring in June 1994, sampling twice
the  number of homes as  required by SDWA
regulations.   Gahanna  also sent an educational
notice on how to avoid the hazards of lead in
drinking water to  selected  residences.   The
additional monitoring and educational notice were
considered a SEP and thus the final penalty was
reduced  by $2,300.   Gahanna paid  a  $1,000
penalty.

CERCLA

Circle Smelting (Beckmeyer, IL): On March 22,
1994 the Region issued a unilateral administrative
order for a time  critical removal to potentially
responsible  parties  (PRPs)  ASARCO,  Inc.,
Federated Metals Corporation, and Circle Smelting
Corporation  at  the Circle  Smelting  Site  in
Beckmeyer, Illinois.  The UAO directs the PRPs
to perform  an estimated $710,000  time critical
removal of lead-contaminated materials along a
water main route in residential areas of the Village
of Beckmeyer.

Since the operation of the secondary zinc smelter
began   in  the early  1900's  lead-contaminated
material from the  smelt  operations  was  used
extensively  as fill throughout  the  Village  of
Beckmeyer.   On March  17,  1994 the  Region
issued an action memorandum for the time critical
removal of lead-contaminated material in the path
of  a water main  replacement project  in  the
residential areas of the village.  There was concern
that trenching through  the contaminated material
(lead concentrations ranged as high as 31,000ppm)
might expose residents to the lead-contaminated
material.  ASARCO, Inc. agreed to  comply with
the UAO and the removal action was completed in
August 1994.  This case demonstrated  that an
expediated cleanup can be achieved at an NPL-
caliber   SACM   site  by   using   accelerated
investigations and coordination techniques.
                                             A-44

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 Core  Craft (Northern Township. MN):   On
 March 1, 1994, a consent decree was entered with
 the U.S. District Court of Minnesota between the
 U.S. and Core Craft,  Inc.  The  consent  decree
 providel for payments by the defendants of a total
 amount   of  approximately   $5  million  as
 reimbursement for response costs  incurred and to
 be incurred by  the U.S. EPA at  the Kummer
 Sanitary Landfill Superfund Site. Additionally, the
 decree provides for the payment by the defendants
 of $22,000  to the U.S. Fish and Wildlife Service
 as reimbursement for damages to natural resources
 at the  site.

 Kummer Sanitary Landfill was licensed to  accept
 "mixed municipal  waste" from  1971-1984, at
 which   time  groundwater  contamination  was
 detected in  private wells downgradient from  the
 facility. The site was placed on the NPL in 1986.
 Because the largest contributor of waste at the site
 was a  municipality  which  demonstrated  an
 inability to pay, and because the evidence against
 the other defendants presented difficult liability
 issues, the Agency  agreed to this mixed-funding
 cash-out settlement despite the lack of other viable
 PRPs from whom to seek full recovery.

 Kerr-McGee Site (Chicago. ID:  Region V, with
 DOJ and  OECA consultation, negotiated for the
 conduct of removal actions at the West Chicago
 Residential  Areas  NPL  site,  which involves
 radioactive contamination of possibly hundreds of
 residential  properties  at  a  potential cost  of
 $100,000,000.   On October  31,  Kerr-McGee
 refused EPA's final offer. EPA issued a unilateral
 order to Kerr-McGee on November 18, 1994.

 Lockhart  Construction  (Akron,  OH):    On
February  24, 1994,  Region  V  executed  an
administrative order on consent  with Lockhart
Construction for a removal at its facility.  In the
order, Lockhart agreed to complete a removal at
the site and  pay $8.6 million for costs.

The  Lockhart Construction site  is located  in
Akron,  Ohio.   In  May  of  1992, during  an
inspection by the Army Corp of Engineers, it was
discovered that illegal fill activities  had  taken
place at the facility, and that wetlands along the
 Ohio Canal  had been filled in.   A subsequent
 delineation   of  the  wetland  indicated   that
 approximately  five acres  of wetlands  had been
 filled in by Lockhart. Later inspections discovered
 that several leachate seeps were flowing toward
 the Ohio Canal and these leachate seeps had pH
 levels greater  than   13   as  well  as  phenol
 contamination.

 National Presto (Eau  Claire. WD: On October
 14, 1993 U.S. EPA issued an administrative order
 on consent  pursuant to which  National Presto
 Industries, Inc. (NPI) agreed to conduct a removal
 action at the NPI Superfund Site in Eau Claire,
 Wisconsin.  NPI will  spend approximately $2.2
 million pumping VOC contaminated sludges from
 a large lagoon on the NPI property. The sludges
 will be  transported off-site and  burned  as  a
 secondary fuel at a RCRA permitted cement kiln.

 The NPI site was listed  on the NPL in  1986.
 Until 1980, the NPI facility produced 8-inch and
 105-mm shells for the  Department of the Army.
 The fogging operation at the facility pumped into
 on-site lagoons.  Lagoon No. 1, the subject of this
 removal action, contains  approximately  13,000
 gallons of floating oil and over one million gallons
 of sludge. U.S. EPA has determined that the oil
 and  sludge  present  a  potential  imminent  and
 substantial endangerment to groundwater as well
 as to migratory birds and fowl.

 Olin Corporation (Ashtabula. OH): On March
 3, 1994, a consent decree was lodged in the U.S.
 District Court for the Northern  District of Ohio.
 Under the  terms  of this  consent decree,  Olin
 Corporation,  the sole  PRP  in  this action,  has
 agreed to pay $1,542,540.82 to the U.S. EPA for
 past response costs incurred plus interest through
 September  1992,  at  the  Big  D  Campground
 Facility.  As a result of the consent decree, U.S.
 EPA will be recovering approximately 98% of its
past costs.    Olin  is also agreeing to pay the
Agency's  future  oversight  costs, which  are
 anticipated to be between $500,000 and $600,000.
The total consent decree is worth over $2 million.

The Big D Campground Superfund  site is located
in Kingsville, Ohio, and consists of a former 1.5
                                            A-45

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
acre quarry used as a landfill. The facility was a
sand and gravel quarry from 1964 to 1976. Olin
delivered and disposed of hazardous materials at
the quarry during its operations.  U.S. EPA placed
the facility on the National Priorities List in early
1983.   Olin  is  currently  complying  with a
unilateral  administrative order for the Remedial
Design/Remedial Action work.

Wedzeb (Lebanon, IN):  During May  through
July  1994,  the Southern  District  of  Indiana,
Indianapolis  Division,  entered  five   separate
consent decrees resolving outstanding  claims by
the U.S. EPA against Wedzeb, its owner,  William
Daniels, its  successor,  USA Manufacturing, and
various manufacturer  defendants.  The United
States recovered a total of $2.14 million to offset
the costs of the removal action.  In  addition, a
penalty of $100,000 was assessed against William
Daniels and Wedzeb for violation of a Section 106
CERCLA order and a penalty of $50,000 was
assessed against USA Manufacturing for violations
of Section 104(e) of CERCLA.
Jackson  Drop  Forge  (Jackson.  MI):    The
Region's January 1994,  administrative consent
order required  two  Jackson/Innova  Corp.  and
Mercer Forge Corp. to remove several thousand
drums of hazardous substances and  contaminants
from the Jackson Drop Forge Site and reimburse
EPA for the Agency's past  costs.  This  site,
located in a mixed industrial and residential area,
was used as both a forge and a dump for several
years. Adjacent to the Grand River, the site is in
a flood plain.  The Region's December removal
action memorandum approved spending about $2
million to address conditions at the Site.'

Spickler Landfill Site (Marathon County. WI):
The Region's January 1994 unilateral order directs
all the  PRP's  to carry out an  estimated $4.9
million remedy for the first operable unit at the
Spickler landfill in  Marathon County, WI,  The
remedy involves constructing an impermeable cap
over the mercury brine pit and a  solid waste cap
over the rest of the landfill. In addition, the PRP's
must pump and treat contaminated leachate, install
a system to collect  landfill gases, and monitor
groundwater.
                                             A-46

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I rw/li
                                        REGION VI
CLEAN AIR ACT

U.S. v. Enpro Contractors, Inc.; Train Property,
Inc.; and Jimmy Patton Contractor, Inc.  (E.D.
Ark.): On October 3, 1994, a civil consent decree
was entered  by the court  in  which the above
defendants agreed to pay $20,000, $12,270, and
$10,000,  respectively.    The  Government had
settled in FY93  with a fourth Defendant, Missouri
Pacific   Employees'   Hospital   Association
(MPEHA) , for >, $62,000,  bringing  the  total
settlement, amount to $104,270.  These actions
arose from violation of the CAA and the NESHAP
promulgated  thereunder.    In  particular,  the
Defendants failed to keep friable asbestos materials
adequately wetted until collected for disposal as
required by the NESHAP during demolition of the
Missouri Pacific Hospital in Little Rock, AR.

In the Matter of Herd Enterprises, d/b/a Broward
Factory Service:  EPA  issued an administrative
penalty order (APO) on December 28, 1993, to
Herd Enterprises for a violation which occurred in
Richardson, TX.  Technicians for the  company
were observed (one case was video taped) venting
refrigerant during service/repair of residential air
conditioning units.  The source  of the information
came  from the people  at whose  homes  the
violations occurred; in both cases the home owners
themselves were knowledgeabje about  both  the
regulations and air conditioning work.  In one
instance a video tape was provided of the actions
of the technician.  The penalty assessed in  the
final order was  $20,650.

CLEAN WATER ACT

U.S. v. City ofKenner and the State of Louisiana
(E.D. La.): On  January 4, 1994, a consent decree
was entered by the court settling the Government's
claim that the City of Kenner, LA, had violated
the CWA and assessing  a  civil  penalty   of
$215,000. The complaint alleged that the City had
violated certain  conditions of its NPDES permit,
including  failure to adequately  implement   its
approved  pretreatment program and causing  the
unpermitted discharge of pollutants to waters of
the United States.

U.S. v. City of Bossier City,  and the State of
Louisiana (W.D. La.):  A SEP which had been
included in a consent decree under the CWA with
Bossier City, LA, filed on February 4, 1993, was
substantially completed in 1994. In lieu of EPA's
proposed settlement amount of $325,000, Bossier
City agreed to pay a civil penalty of $200,000  and
to conduct the SEP.  The project cost of the SEP
was approximately, $375,000. The complaint filed
in U.S. District Court alleged that Bossier City  had
violated the CWA by failing to properly operate
and maintain its POTW,  failing to comply with
effluent limitations  in its NPDES permit,  and
failing  to   fully   implement   its   industrial
pretreatment program.

U.S. v. E.I. DuPont De Nemours  and Company
(E.D. Tex.):   A  pollution prevention SEP was
contained  in the consent decree filed on August
15, 1994,  in U.S. District Court in settlement of
claims against DuPont for violations of its NPDES
Permit and §301 of the CWA. Under the consent
decree, DuPont agreed to pay a civil penalty in the
amount of $516,430 and to perform a SEP costing
an  estimated $3.2 million.  The SEP requires
replacement of existing  steam-powered vacuum
jets  in their adiponitrile  process  units with
mechanical   vacuum pumps.     The   steam,
contaminated with   waste  materials  from  the
adiponitrile process, was condensed as water  and
became a waste stream.

Vulcan Chemical:  EPA received  information in
correspondence from Vulcan  regarding NPDES
permit violations  involving zinc and  issued  an
administrative order  under the CWA to Vulcan
establishing  a schedule to reduce  zinc from  the
company's wastewater discharges.  In response,
Vulcan  devised and implemented  an alternative
treatment technology which resulted in a reduction
of pollution created  at the facility with only a
minimal delay in the compliance schedule.
                                            A-47

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
In the Matter of Albert Kramer III dlbla Kramer
Development Corporation:  On January 21, 1994,
a consent  agreement/final  order  was  issued in
which Mr. Kramer agreed to pay $6,005 to resolve
an administrative penalty action. Development of
the case, which was referred to EPA from the U.S.
Army Corps of Engineers, included an original
proposed penalty of $10,000. Kramer had initiated
construction of a series of roads  in wetlands as
part of an unspecified future development project.
No permit  had been  obtained under CWA §404,
for the discharge of fill material into wetlands.

Citgo Pipeline Company:   An administrative
Class II complaint was  issued to Citgo Pipeline
Company, Tulsa,  Oklahoma,  on March 4, 1994,
with a proposed penalty of $124,900 for violations
of  §311(b)(6)(B)(ii)  of  the  CWA.    The
corporation's facility discharged 200  barrels of
crude oil from its onshore  pipeline  in  Claiborne
Parish, LA, and 250  barrels of crude oil from an
onshore  pipeline   in   Gregg   County,  TX.
Information on the discharge was received from
the report  made  by Citgo  to  the  NRC.  The
discharged  oil entered navigable waters of the
United  States in  quantities  determined to  be
harmful under 40  C.F.R. §110.3.

Hamner  Inc.:    An  administrative Class  I
complaint was issued to Hamner,  Inc.,  Corpus
Christi, TX, on May 24, 1994, with a proposed
penalty   of   $9,108   for  violations   of
§31 l(b)(6)(B)(ii) of the CWA. The corporation's
tanker truck overturned, discharging approximately
24 barrels of petroleum naphtha.  The petroleum
naphtha entered navigable waters of the United
States in quantities determined to be harmful under
40C.RR. §110.3.

.Tayhawk Pipeline  Corporation:   A consent
agreement  and final  order  was signed July 11,
1994, concerning Jayhawk Pipeline Corporation's
discharge of 20  barrels of  crude  oil from  an
onshore pipeline in Kay County, Oklahoma. The
spill was reported to  the NRC by the responsible
party  and EPA responded to  the spill. Jayhawk
paid a penalty of $3,825 to the Oil Spill Liability
Trust Fund.
Petrolite Corporation: A consent agreement and
final order was signed July  11, 1994, concerning
the corporation's violation of §311(b)(6)(B)(ii) of
the CWA. Petrolite Polymer Division discharged
200 barrels  of wax from its facility located  in
Kilgore, Gregg County, TX. The oil entered the
stormwater drainage and migrated  off-site into
drainage areas and Rabbit Creek.  The discharge
was reported to the NRC and EPA responded to
the spill.  Petrolite paid a penalty of $5,500 to the
Oil Spill Liability Trust Fund.

Red River Entertainment Group:  On May 19,
1994, a consent agreement/final order was issued
in which  Red River Entertainment agreed to pay
$3,000 to resolve an administrative penalty action.
Development of the case, which was referred to
EPA from the Corps  of Engineers, included  an
original proposed penalty of $5,000.  Red River
had applied for a CWA, §404, permit to build a
bulkhead associated with  casino development  on
the Red River in  Shreveport,  LA, but initiated
construction work in waters of the U.S. prior to
issuance  of the permit.    The impacts  of the
violation   were corrected, and the  permit was
eventually issued by the Corps  of Engineers.

RCRA

In the Matter of Micro Chemical Company: An
RCRA administrative CAO on consent was issued
to Micro Chemical  Co. on  September 30, 1994.
The order followed from a citizen's complaint of
releases from the facility.  The order first requires
the facility to stabilize a ground water plume of
pesticides, located 3,000 feet upgradient from the
city's  drinking water wells.  The  order  then
requires clean up of the soil on the remainder of
the site. Thus, the site requires ground water and
soil remediation measures.  The study phase for
both media may cost  $1.4 million.  The ground
water remediation will be carried out over a great
deal of time (10 to 20 years) which will involve
substantial yearly costs. The soil remediation will
require a much shorter period of time to reach a
conclusion but will require a greater amount of
money.  A  rough estimate of the total cost of
remediation of the site would be in the area of $4
to 10 million.
                                             A-48

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
In  the  Matter of Dow Chemical:   Violations
found at this facility in Plaquemine, LA, related to
RCRA BIF requirements. They included failure to
maintain the prescribed scrubber blow down rate
and liquid-to-gas ratio and failure to maintain the
operating'controls and end points for  automatic
waste feed cut off established in the Certification
of  Compliance.    The case was settled with a
consent agreement and final order, filed September
9,  1994,  in  which  the  assessed  penalty  was
$26,000.

In the Matter of Chemical Waste Management:
This facility operates a hazardous waste incinerator
in Port Arthur,  TX,  permitted under both  the
RCRA (for hazardous waste) and the TSCA (for
polychlorinated biphenyls,  PCBs).   The facility
commingled  the   listed  hazardous  waste  F039
(leachate  from   landfills)  with  PCB's  from
capacitors and transformers during incineration.
The resulting ash  failed to meet the RCRA land
disposal restriction (LDR) treatment standards for
PCBs in F039. Although the PCB concentrations
in the ash were probably derived from the PCBs in
the electrical equipment, not the F039, the Mixture
Rule requires that the ash meet LDR standards for
F039.   The facility failed to make an adequate
waste determination  and  shipped the  ash to a
disposal facility  without notifying  the disposal
facility that the ash did not meet LDR treatment
standards.  The ash was subsequently placed on
the  land  without having  met  LDR  treatment
standards  for PCB's  in F039.   (The  receiving
facility, Chemical Waste  Management, Carlyss,
LA, also received a penalty.) Shipments occurred
on several occasions during 1993.  The company
self-reported the violations. An order assessing a
civil penalty  of $15,000 was issued on April 8,
1994.

In the Matter of Chemical Waste Management:
This  facility is  a hazardous  waste treatment,
storage, and  disposal facility  in Carlyss,  LA.
Violations found at this facility related to disposal
on  the land of hazardous wastes which may be
land disposed only if they meet  LDR treatment
standards.   The   facility  in  Port  Arthur,  TX,
commingled  the   listed hazardous  waste  F039
(leachate  from  landfills)  with  polychlorinated
biphenyls (PCBs) from capacitors and transformers
during  incineration  and  failed  to  notify  the
receiving facility that the resulting ash failed to
meet the RCRA land disposal restriction  (LDR)
treatment standards for PCBs in F039.  (The Port
Arthur facility also received a penalty.)

In the Matter of Texas Industries: This facility
is a cement plant in Midlothian, TX, which burns
hazardous waste as a part of its fuel.  Violations
found  at  this facility  related  to RCRA BIF
requirements.     The   facility  violated   these
requirements by its  failure to operate the kiln
within  feed  rate  limits  established  in,  the
Certification of Precompliance, failure to make an
adequate Bevil exclusion determination, and failure
to maintain unit inspection records.   An order
assessing a civil penalty of $26,000 was issued on
June 23, 1994.

In the Matter of Aristech:  Violations found at
this  chemical  plant in Pasadena, TX,  related to
RCRA  BIF  requirements.     They  included
exceedances of waste storage accumulation times,
failure to conduct unit integrity testing, failure to
label waste storage tank, failure  to maintain unit
inspection records, failure to update waste analysis
and contingency plan, and failure to prepare unit
closure plan.  A  civil  penalty of  $21,500 was
assessed in an order issued on August 8, 1994.

In the Matter ofRexene: Violations found at this
chemical plant in Odessa, TX, related to RCRA
BIF  requirements.   They  included  failure  to
establish appropriate Certification of Compliance
operating limits, failure to comply with prescribed
feed rates, failure  to amend waste analysis plan,
inspection schedule  and contingency  plan, and
failure to prepare unit closure plan.  A penalty of
$33,750 was  assessed  in  an  order  issued
September 15, 1994.

In the  Matter of Chapparal Steel:  This steel
manufacturing  company  in  Midlothian,  TX,
exports emission control dust and sludge from the
primary production  of  steel in  its  electric  arc
furnaces,  listed  hazardous  waste  K061,  for
recovery of other metals.   It failed  to provide
annual reports of  its hazardous  waste exporting
                                             A-49

-------
   SEP
      IFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
activities for 1991 and 1992 and failed to properly
manifest  shipments during  that  period.   On
December 23,1993, an order was issued assessing
a civil penalty of $5,000.

In the Matter of Hydrocarbon Recyclers, Inc.:
This  hazardous  waste treatment,  storage,  and
disposal  facility in  Tulsa,  Oklahoma,  receives
hazardous waste which has been imported from
another country. The case involved violations of
the RCRA requirement that treatment, storage and
disposal facilities submit advance notice to EPA or
the authorized State agency of anticipated receipt
of foreign waste.   An order  assessing a civil
penalty of $35,000 was issued on May 4, 1994.

In the Matter ofREM TEX: This case  involved
violations of the RCRA hazardous waste importing
requirements  by a manufacturer of electrical and
electronic equipment in Del Rio, TX.  Violations
included  failure to notify EPA or the authorized
State  agency  of  hazardous  waste  activity  and
failure to provide foreign generator's name on
manifest.   REM-TEX acts  as  U.S.  importer of
hazardous  waste for  its  foreign  maquiladora
facility, located in Tamaulipas, Mexico.  REM-
TEX operates a U.S. facility, located in  Del Rio,
TX, which serves as a warehouse or transfer point
for waste imported from REM-TEX's maquiladora
facility destined for TSD facilities in the United
States. A civil penalty of $9,000 was assessed in
an order issued on May 31, 1994.

In the Matter of  Jeep  Collins:     This case
involved violations of the RCRA hazardous waste
importing requirements by a jewelry manufacturer
in Fredericksburg, TX.  Violations included failure
to notify EPA or the authorized State agency of
hazardous waste activity and failure  to provide
foreign generator's  name on  manifest.   Jeep
Collins acts as U.S. importer of hazardous waste
for its foreign maquiladora  facility,  located in
Coahuila, Mexico.  Jeep Collins operates a U.S.
facility, located in  Fredericksburg,  TX, which
serves as a warehouse  or transfer point for waste
imported from Jeep Collins' maquiladora facility
destined for TSD facilities in the United States. A
civil penalty  of $6,300 was assessed in  an order
issued on May 31, 1994.
In the  Matter of Ranco:  The case involved
violations by a manufacturer in Brownsville, TX,
of plastic and metal parts  for  heating and  air
conditioning units of requirements for storage and
manifesting  of hazardous waste.   The  facility
imports hazardous  waste  from  its  maquiladora
operation  in  Mexico, and it  used  an incorrect
RCRA ID number on its manifests. An order was
issued on August 3, 1994, assessing a civil penalty
of $19,520.

In the Matter of Citeo Re fining;  This petroleum
refinery in Lake Charles, LA,  failed to meet the
regulatory deadline for retrofitting impoundments,
which receive  toxicity  characteristic  hazardous
wastes,  with  liners  and leak detection systems.
Even after the statutory deadline for retrofitting
impoundments  or ceasing to  use  them, Citgo
continued to  place  hazardous   wastes  in the
impoundments. The violations  were  self reported.
The  facility  was  assessed  a civil penalty  of
$47,500 in an order issued September 30, 1994.

In the Matter ofAauaness Chemical: Aquaness
Chemical, formerly an oil field chemical blending
operation  in  LaFayette, LA, was converting  its
facility to a warehouse and distribution center for
oil field chemicals.   The facility failed to notify
EPA  or  the authorized  State   agency  of  its
hazardous waste  activity  and hazardous waste
storage. The company was involved  in generating
large quantities  of various  hazardous  wastes
(thousands of gallons a year)  without notifying the
authorized State or EPA about their activity.  In
addition, wastes wt"v, being managed in a  manner
that  presented a potential  for  release  to the
environment  because of mislabeling  the waste
containers and not inspecting the areas where the
waste was stored on  a regular basis.  The facility
also  failed to adequately train its  personnel in the
management of hazardous waste.  A civil  penalty
of $105,350 was  assessed  in an  order issued  on
October 1, 1993.

In the  Matter of  Helena  Chemical:   Helena
Chemical in Delhi, LA,  is  a  pesticide distribution
warehouse for northeast Louisiana.  This facility
failed to notify the regulatory agency of hazardous
waste activity and to comply with hazardous waste
                                             A-50

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                                                                       X
storage  requirements.   The facility  had  been
storing hazardous wastes in one of its warehouses
since it ceased its pesticide blending operation in
1986, without  following  the requirements for
storing  hazardous waste.    A civil penalty  of
$71,482  was  assessed  in  an order  issued  on
October 1, 1993.

In  the  Matter of Helena  Chemical:   Helena
Chemical in West Helena, AR, blends technical
grade pesticides and herbicides for distribution to
warehouse facilities in the mid-west and southern
United States.   The facility also  does contract
blending  and  packaging of  pesticides for  other
companies.   The facility  failed to  notify the
regulatory agency of hazardous waste activity and
failed  to follow hazardous  waste storage and
manifesting requirements. The facility was storing
15,000 gallons of a mixed hazardous  waste in a
tank at the facility.  The company  had failed to
characterize this waste  as  hazardous and had
actually manifested similar waste from the site as
non-hazardous. The company was assessed a civil
penalty  of $98,125   in  an  order  issued  on
December 29, 1993.

U.S.  v.  Marine  Shale Processors, Inc. (W.D.
La.):  On August 30,  1994, the court issued an
opinion requiring Marine Shale Processors (MSP)
to pay the United States and the State of Louisiana
an $8  million  civil  penalty for  violating  the
RCRA, the CAA, and  the CWA.  The court also
ordered  Southern  Wood  Piedmont  (SWP), a
company that sent hazardous waste to the MSP, to
pay a $25,000 civil penalty for sending hazardous
waste to MSP  was in violation of  the RCRA
storage  permit  regulations.  Finally, the  court
prohibited  MSP  from  disbursing   dividends,
royalties,  loans,  debentures  and  other funds to
company  shareholders   and  officers,  except
 amounts  to pay their normal current salaries and
MSP's local,  state and federal taxes.   The  MSP,
 SWP and the government have appealed  portions
 of these decisions to the U.S. Court of Appeals for
 the Fifth Circuit.
TSCA

In the Matter of Asarco. Amarillo, Texas:  An
administrative complaint under the TSCA was
issued  to  Asarco,  Inc.,  Amarillo,  TX,   on
September 29, 1993 for failure to comply with the
PCB  regulations.  Violations included improper
disposal of PCBs, inadequate records of PCBs, and
failure to notify EPA of PCB  waste handling
activity.  The proposed penalty in this complaint
was $51,500.   This complaint was  settled  on
February 8, 1994, through the issuance of a C AGO
with a final penalty of $51,500.  In addition, the
CACO required that the company  conduct post-
verification sampling of a PCB spill that was the
subject of a count contained in the  complaint.

Central Power and Light Company. Corpus
Christi. Texas:   An  administrative complaint
under the TSCA was issued to Central Power and
Light on September 30, 1994, with a proposed
penalty of $90,750. Among the violations found
were failure  to properly mark PCB  containers,
improper storage  and  disposal of  PCBs,  and
inadequate recordkeeping.  The .facility  failed to
cleanup three spills for 82 days, 69 days, and 58
days respectively.

CERCLA

U.S.  v. David Bowen Wallace, et al. (N.D. Tex.)
Bio-Ecology Systems Superfund Site,  Dallas
County, Texas:  On August  1, 1994, the  United
States filed  a  Notice  of Lodging of a consent
decree .for recovery of past and future  costs, as
well as  operation and maintenance costs.  This
consent decree, if entered by  the Court,  would
provide  for  recovery  of $8.34 million in U.S.
response costs and $1.14 million in State of Texas
response costs associated with implementation of
a Superfund  remedy at the Bio-Ecology National
Priorities List (NPL) Site. The settlement resolves
the liability  of 73 defendants, including 59 de
minimis  generators  of  hazardous  substances
disposed at the site.
                                              A-51

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
U.S. v. American National Petroleum Company,
t  at (W.D. La.) Gulf Coast Vacuum Superfund
Site,  Abbeville,  Louisiana,  and  Gulf  Coast
Vacuum Services Superfund  Site,  Vermillion
Parish,   Louisiana:     In  FY94,  both   an
administrative order on consent  and a consent
decree were signed for this site where both the soil
and  a shallow perched aquifer  are contaminated
with oil field wastes containing barium, arsenic,
mercury, cadmium, lead, benzene, and numerous
other organic compounds.  About 15,000 cubic
yards of sludge and 19,500 cubic yards of site
soils will be remediated. On September 28, 1994,
an  administrative  order  on  consent  became
effective after a 30-day public  comment period.
The order, between EPA and 54 de  minimis
parties,  allowed the parties to  "cash out"  their
liability at the site by paying a settlement based on
their volumetric percentage of waste at  the site.
The de minimis settlement raised $ 3.1 million for
EPA expenses and contractor oversight of clean-up
activities for Operable Unit 1  at the site.

On June 14,1994, EPA completed negotiations for
a  proposed  consent  decree  with   15  major
Potentially Responsible Parties (PRPs), including
many large oil companies.  The parties signed the
proposed consent decree which calls for a change
in the remedy for organic contamination specified
in the 1992 Record of Decision  from incineration
to biological treatment to the same treatment
standards as incineration.  The proposed consent
decree will become effective after it is lodged and
entered and after an Amended Record of Decision
is issued.  On January 26, 1994,  EPA received the
final close-out report from the 15 major PRPs for
their work on Operable Unit 2 (the Interim Source
Action)  under  a  December  1992  unilateral
administrative order.  All activities  under the order
were certified complete except for Operation and
Maintenance  prior to the  initiation of Operable
Unit  1  construction;  therefore, the  PRPs  have
fulfilled  their  obligations  under  the unilateral
order.

U.S. v. City of Jacksonville, Arkansas (E.D. Ark.)
Jacksonville    Municipal   Landfill,   Lonoke
County, Arkansas, and Rogers Road Municipal
Landfill, Pulaski County. Arkansas: On April 6,
1994, the U.S. District Court, Eastern District of
Arkansas,  lodged two consent decrees  for  the
Jacksonville and Rogers Road Municipal Landfill
Superfund Sites which were subsequently entered
on June 20,1994.  Approximately 800 cubic yards
of soil in the two landfills are contaminated with
dioxin that  was produced by  a local herbicide
manufacturer. "The City agreed to pay $100,000 in
past costs.

U.S. v. Gulf States Utilities Company (S.D Tex.)
Industrial Transformer/Sol Lynn Site. Harris
County,  Texas:   The  first  EPA Prospective
Purchaser Agreement was lodged with the court on
November   18,   1993,   for   the   Industrial
Transformer/Sol Lynn Site (the Site) in Houston,
TX.  The Site  was the location  of an electrical
transformer  salvage  and  recycling  operation
conducted by the property owner, Sol Lynn, from
approximately 1965 to 1975. Contamination at the
Site  resulted   from  the  transformer   salvage
operations and from a chemical manufacturing and
supply company which leased property from Sol
Lynn.  The principal contaminants of concern are
PCBs and TCE.  Both of these substances were
released onto  the ground at  the Site.   TCE
migrated  into  the  ground   water and  PCBs
remained in the first two feet  of soil.  The Site
was placed on the NPL in March 1989.

On April  9, 1.991,  the  United States  filed  a
complaint  against the Estate of Sol Lynn seeking
past and future cleanup costs pursuant to §107 of
CERCLA.  The settlement was achieved through
two documents.  First, the consent decree settled
the civil  liability  of the defendants for cleanup
costs and injunctive relief while retaining certain
"reopener"  rights for previously  unknown site
conditions. The United States received an up-front
payment  from  sale  of site  property, and  will
receive a percentage of a future sale of other real
property owned by the Estate.

Second, the Agreement and Covenant Not to Sue,
requiring Department of Justice approval, between
EPA and the purchaser of the Estate's interest in
the site required  the purchaser  to establish  an
escrow for the  purchase.   The Estate's payment
under the consent decree was funded through this
                                             A-52

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
escrow.  In consideration for funding the Estate's
payment, the purchaser received a covenant not to
sue for civil liability and injunctive relief related
to existing contamination at the Estate property
and  an adjacent tract.   The agreement  imposes
certain use  restrictions  on current  and  future
owners of the  Site and will give EPA, the Texas
Water Commission, and their cleanup contractors
irrevocable  access  to  the property for  future
remediation.

U.S.  v,  Vertac  Chemical Corporation,  et  al.,
Arkansas Department of Pollution Control and
Ecology  v.  Vertac Chemical Corporation, et al.
(E.D. Ark.).  In the Matter of Hercules Inc.,
Uniroyal Chemical Ltd.,  and Vertac Chemical
Corporation (Administrative) Vertac Superfund
Site, Jacksonville. Arkansas: Hercules, Inc., the
principal viable  PRP agreed to comply  with  a
UAO  issued  in  March 1994  to  perform  site
cleanup.     Under   the  order,  Hercules  will
implement a $28.5  million remedy to dismantle
the old  manufacturing  process plant, and treat
residual liquids and sludges left in old tanks  and
vessels.  The combined costs to clean up all six
operable  units is expected to exceed $100 million.

Additionally,  in  the civil  enforcement  action
associated with this site, on October 12, 1993, the
U.S. District Court granted summary judgment to
the United States on the issue of Hercules' joint
and  several liability for  past and  future costs
related to remediation of the Vertac  Site. That
summary judgment was an interim ruling as part
of ongoing CERCLA cost recovery action brought
by the EPA against multiple parties.

In the Matter  of Amerada Hess Corporation, et
al.,  PAB   Oil   Superfund  Site,  Abbeville,
Louisiana:  In September 1994, EPA issued  a
UAO to  approximately 30 potentially responsible
parties (PRPs) requiring them  to clean  up  the
abandoned site.  Most PRPs subsequently agreed
to comply with the order.  Under the order, PRPs
will undertake  a $13 million effort to bioremediate
hazardous organic wastes left in pits and lagoons
at this site in southern  Louisiana. Surface water
will also  be treated and discharged. In addition to
the UAO, EPA offered de minimis settlement to a
large number of small volume contributors. Most
of  the de  minimis  parties have signed  the
settlement which is now being finalized- All non-
settling PRPs have been offered an opportunity for
Alternate Dispute Resolution (ADR).  The ADR
will not interrupt the ongoing  site remediation
being performed under the UAO, but will afford
the PRPs an  opportunity to resolve  allocation
issues  that could not be  resolved prior  to the
deadline for a "good faith offer" to settle.

In  the  Matter  of  Waste Management  of
Oklahoma, Inc., Mosley Road Sanitary Landfill
Superfund Site, Oklahoma City, Oklahoma:  A
UAO  was  issued  to  Waste  Management  of
Oklahoma (WMO) on January  28, 1994.  The
UAO requires  WMO to conduct the Remedial
Design and Remedial Action at the site. The site
was contaminated with liquid industrial  wastes
which were  hazardous substances and which had
been disposed of in a solid waste landfill under
state permit.  The remedy selected in the Record
of  Decision  was the  capping  of the landfill,
construction  of  a  gas recovery  system,  and
remediation of the contaminated ground water.  A
settlement in the form of an administrative order
on consent was reached with 19 de minimis parties
on  March  24, 1994, for $1.2  million.    This
settlement was included in the national de minimis
initiative. The de minimis settling parties included
18 generators and a transporter.

In  the  Matter  of Aluminum  Company  of
America,  Alcoa/Lavaca  Bay  Superfund  Site,
Point Comfort,  Texas:   The  site includes the
Aluminum  Company of  America's  (ALCOA)
Point Comfort Operations  Plant which  covers
approximately 3,500 acres and Lavaca Bay which
is approximately 68 square miles in size.

In May 1993 EPA proposed the Site for listing on
the National Priorities List (NPL), and the listing
became final on April  23, 1994.  In. January of
1994, EPA's site negotiation team set a goal of 45
days to reach agreement with ALCOA on a scope
of   work   for  a   comprehensive   remedial
investigation and feasibility study (RI/FS).  This
deadline was established so as  to  try and  meet
                                            A-53

-------
            1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
NOAA's and  the  State's  statute  of  limitations.
The result was an administrative order on consent.

In the Matter of National Zinc Site, Bartlesville,
Oklahoma;  Salomon,  Inc.,  Cyprus  Amax
Minerals  Company,  and  Kerramerican, Inc.,
National  Zinc   Company   Superfund  Site,
Bartlesville,  Oklahoma:  On February 2, 1994,
EPA  issued a  UAO  for removal  action at  the
National Zinc  Site  in  Bartlesville,  Oklahoma.
During  operation of the National  Zinc  smelter,
lead and cadmium were  deposited through  air
releases on surface soils within three miles of the
facility.  The  UAO  required PRPs, Salomon,
Incorporated, and Cyprus-Amax,  to remove lead
contaminated soil from residential properties in the
area contaminated by the smelter.  In addition, this
two-pronged process provided for state oversight
in  a  separate  agreement  by  the   Oklahoma
Department  of Environmental Quality (ODEQ)
with the PRPs  to perform a RI/FS to address a
long term remedy  for the  site. The RI/FS was
carried out by the PRPs with  a state  Record of
Decision targeted for late in calendar 1994.

Marco  of  Iota:     An   Alternative  Dispute
Resolution (ADR)  process  has been  initiated to
assist in reaching a cost recovery agreement at the
Marco of Iota Superfund site in Iota, LA.  Marco
of Iota was a fuels  blending and recycling facility
located in Iota, LA. The Louisiana Department of
Environmental  Quality had repeatedly cited  the
facility  operators for  operational violations.  In
January  1992,  the Louisiana State  Police in
conjunction with LDEQ closed down the facility
and initiated a criminal investigation.   At closure
the  operators   abandoned   a  large  volume  of
hazardous substances on the site.  WPA identified
over 600 potentially responsible parties (PRPs) and
offered  them  the opportunity to conduct  the
cleanup. The PRPs declined the opportunity and
EPA began a Fund removal action in July 1992.
The removal was completed in June  1994, at a
cost of $4.5  million.

Pab Oil:  In 1994, EPA initiated an Alternative
Dispute Resolution (ADR) process to help resolve
allocation issues among Potentially Responsible
Parties  (PRPs)  at  the  PAB  Oil  NPL  site in
Abbeville, LA.  The site includes impoundments
which  were used to  hold hazardous  substances
from oil field truck discharges. EPA has identified
in excess of 30 PRPs.  While the ADR process is
not complete, most PRPs  agreed to participate in
the process and early signs are encouraging.  The
offer of ADR appears to have convinced PRPs to
comply with the  UAO  for RD/RA and  will
hopefully lead to a cost recovery agreement based
on the  final allocation of liability.

South  8th Street: In 1994, EPA also  initiated an
ADR process to help  resolve allocation issues
among PRPs at the South 8th Street NPL site in
West Memphis, AR. EPA has identified in excess
of 30  PRPs.  While the ADR  process is  not
complete, most PRPs agreed  to participate in the
process and early signs are encouraging and EPA
is hopeful that the effort will lead to an allocation
which will facilitate a settlement agreement.

B.P. Chemical: This petrochemical plant in Port
Lavaca, TX, had a release to the environment of
ammonia in an amount just above the reportable
quantity.  A consent agreement and final order was
signed   October  6,  1993,  concerning   B.P.
Chemical's late reporting of the  release to  the
NRC under CERCLA §103. B.P., located in Port
Lavaca, TX, agreed to perform certain SEPs to
mitigate the penalty, which was reduced to  zero
because  of uncertainty  regarding the  amount
released.  In return for the penalty reduction, B.P.
provided  the LEPC in  Calhoun County   with
funding  to  purchase  a  weather  radar   for
environmental determination.  Additionally,  B.P.
purchased and installed a pump on the ammonia
blow down stream to reduce pressure problems on
the production unit. The projected cost of the two
SEPs is $49,000. SIC code 2869.

Miles Inc:   A consent agreement and final  order
was signed  August 29,  1994, concerning Miles
Inc.'s late reporting to the NRC  of a release of
dichlorodifluoromethane. This petrochemical plant
should have reported the release immediately, as
required by CERCLA §103.  A penalty of $1,000
was agreed to by both parties.  Miles, located in
Baytown, TX, agreed to perform certain SEPs to
                                            A-54

-------
     PV1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORTItjwz)
mitigate the penalty.  The projected cost of the
SEPs is $13,000.
                                       A-55

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                        REGION VH
CLEAN AIR ACT

U.S. v. Archer Daniels Midland (S.D. la.):  In
1989,   EPA  began  documentation  of  CAA
violations at the Archer Daniels Midland (ADM)
Cedar Rapids and Des Moines, Iowa, facilities
resulting in establishment of 88 violations of PSD
permit  conditions,   state-issued  PSD  permit
conditions, and NSPS violations.  The case  was
concluded with a consent decree, which required
ADM to hire a contractor to conduct a company-
wide  environmental  management  audit,   to
document   and   recommend  practices   and
procedures  to ensure compliance  with federal,
state, and local environmental laws. The consent
decree also requires payment of a civil penalty of
$700,000.

U.S. v. Hunt Midwest Mining, Inc. (W.D. Mo.):
A consent decree was entered  on June 30, 1994,
resolving  notification,  testing,  and  emission
violations of NSPS  Subpart OOO  at two Hunt
Midwest Mining, Inc. facilities.  Hunt will pay a
civil penalty of $134,800.  Hunt owns two plants
in Missouri, one  in Kansas  City and one in
Randolph.  Hunt Midwest Mining installed a new
primary crusher and a new bin  with loadout at the
Kansas City,  MO,  plant,  and  replaced  the
Randolph,  MO, plant in  its  entirety after the
Subpart OOO applicability  date of August 31,
1983.    Hunt  failed  to  give  the required
notifications,  failed  to  conduct  the required
performance tests at the Kansas City plant,  and
was 30 months late  performing these  same
requirements at the  Randolph plant. There were
also emissions violations at the Randolph plant.

In the Matter of Holnam, Inc.:  EPA issued a
3008(a) complaint in July 1993, as part of the  BIF
regulations initiative against Holnam, Inc.,  which
owns and operates a cement kiln in Clarksville,
MO,  manufactures  Portland cement,  and  burns
hazardous waste as fuel. The facility was unable
to  certify  compliance  with  certain  emissions
standards by August 21, 1992, as required under
the BIF regulations.  The violations alleged in the
complaint included failure to obtain  a detailed
analysis  of  hazardous  waste  before burning,
inadequate waste analysis  plan, and  failure to
minimize  releases  of hazardous  waste.   The
consent  agreement/consent  order  has  been
executed by  all parties  resolving the violations
contained  in  the  July  1993  BIF  complaint.
Holnam is to pay $100,874 in penalties, and must
adjust  their  closure cost estimates  and financial
assurance for closure.

CLEAN WATER ACT

In the Matter  of the Boeing  Company:  The
Boeing Company filled approximately 1.4 acres of
the Arkansas River channel with broken concrete,
dirt, reinforcing bar, conduits (metal and plastic)
and  miscellaneous  demolition  debris.    The
administrative   consent   order  requires   the
Respondents  to  develop, obtain approval from
EPA, and  implement a plan for removing the fill
material and restoring the area to its full condition.
The   penalty  paid  was   $30,000.     EPA
simultaneously  filed  a  complaint  and consent
agreement against Boeing for violations of EPCRA
§313 reporting requirements, conducted pre-filing
negotiations,  and reached settlement  by which
Boeing agreed to pay full penalty of $58,500.

U.S. v. Beech Aircraft Corporation (D. Kan.):
On May 27, 1994, the court entered  a consent
decree resolving civil  violations of the CWA at
Beech Aircraft Corporation's Wichita, KS, facility.
Under  the consent decree, Beech was required to
pay a civil penalty of  $521,000 for its violations
of federal categorical  pretreatment  standards for
metal  finishers, failure  to  meet  the  reporting
requirements  of   the   general    pretreatment
regulations, and failure to timely comply with an
administrative order issued by EPA.  In addition to
paying a civil penalty of  $521,000, Beech also
agreed under the consent decree to perform a SEP
valued at approximately $200,000 that consists of
installing  centrifuges  or  equivalent systems to
remove sludge from its Wichita facility's existing
water wash paint spray booths.
                                             A-56

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 RCRA

 In the Matter of Burlington Northern Railroad:
 An RCRA §7003 consent order was issued on July
 8,   1994,   addressing   chlorinated   solvent
 contamination in the groundwater in the northeast
 portion of the Hobson Yard, believed  to  have
 resulted from a leaking perchloroethylene (PCE)
 tank and from historical discharges of wastewater
 into unlined  lagoons.   Burlington  Northern's
 Hobson Yard in Lincoln, ME,  has a history of
 environmental   problems.      A   multi-media
 inspection of the northeast portion of the Yard was
 done in the  summer of 1992, and  based on
 findings from the inspection, a UAO was issued to
 Burlington Northern in the  spring of 1993 citing
 RCRA, CERCLA,  CWA, and OPA  authorities.
 The UAO required  Burlington Northern to cease
 the discharge  of oil and chlorinated solvents to
 surface waters,  including a  rare  inland saline
 wetland located on Burlington Northern's property.
 The consent prder requires Burlington Northern to
 characterize .the extent of contamination, define the
 source(s), and  develop  remedial alternatives  to
 address the same.

 In the Matter of The Dexter Company:  EPA
 Region VII issued an administrative complaint to
 The  Dexter Company  (SIC  2851) for RCRA
 violations at its  storage facility in  Fairfield, IA.
 The complaint charged The Dexter Company with
 the following  RCRA  violations:   violation of a
 May 15, 1991  consent agreement/consent order
 Respondent  previously entered  into with EPA;
 storing hazardous wastes at its facility  without
 having achieved interim status or having a permit
for storage in violation of Section 3005 of RCRA;
 and  failure  to label  or date  hazardous waste
containers.  The total penalty proposed under this
complaint was $280,537.  Under the terms of the
consent agreement, Respondent is to carry out a
pollution prevention SEP valued at $776,131, pay
a $32,125 penalty, and conduct closure at the Site.
The SEP involves the Respondent  changing the
nature  of  its current  painting  operation to  one
which  does not use  solvents, thus ceasing its
generation of this waste stream.
 In   the  Matter   of  Missouri   Highway
 Transportation Department:  On September 30,
 1994,   Region   VII   issued   a   consent
 agreement/consent  order  requiring   sampling,
 further clean-up if needed, and development of a
 plan for future handling of sandblast residue. The
 case  involved  RCRA violations resulting from
 sandblasting lead based paint from the Chariton
 River bridge and the  subsequent handling of the
 sandblast   residue.      Missouri   Highway
 Transportation Department (SIC 9621) will pay an
 initial penalty of $70,000. An additional $115,398
 penalty will be deferred and subject to offset upon
 completion of SEPs estimated to cost more than
 $350,423.

 In the Matter of Iowa Army Ammunition Plant:
 On March 8,  1^94,  EPA Region  VH filed  a
 consent agreement/consent order (CA/CO) settling
 a   RCRA   Section   3008(a)   administrative
 enforcement   case   with   the   Iowa  Army
 Ammunition Plant, Middletown, IA (IAAP) (SIC
 9711).  This was the first time the Army entered
 into a RCRA CA/CO that included penalties since
 the enactment of the Federal  Facility Compliance
 Act  on October  6,  1992.   The twelve count
 complaint alleged violations  of the groundwater
 monitoring requirements and  of IAAP's operating
 permit conditions for storage and incineration of
 hazardous wastes.   The  complaint assessed  an
 initial  penalty  of  $201,640.     During  the
 negotiations the  penalty was reduced to the
 amount of $138,921.75.  The IAAP will initially
 pay  $75,704  and  the balance  of  the penalty,
 $63,217.75,  will  be   deferred  to  allow   for
 implementation  of a SEP which  is estimated to
 cost in excess  of $300,000.  If IAAP completes
 the SEP in two years, the deferred amount will be
 waived.  The planned  SEP will eliminate one of
 lAAP's NPDES permitted discharges of explosive
 contaminated wastewater.

 In the Matter of G.E. Company:  On June 30,
 1993, as part of EPA's illegal operator initiative,
 a civil administrative action was filed against G.E.
Company (SIC 3469) for its violations of RCRA
at  its  facility  in West Burlington,  IA, for a
proposed total penalty of $38,250. The settlement
reached included the payment of $10,500, plus the
                                            A-57

-------
      IFY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
obligation to conduct a SEP, which involves the
consolidation of two metal plating lines, with an
estimated  35%  reduction  in  the  amount of
hazardous wastes generated, and an estimated 80%
reduction in the generation of plating rinse waters.
The cost of the SEP totals an estimated $225,000.

In the Matter of Cuba Paint Company:  On
September 30, 1992, EPA issued a complaint to
Cuba Paint Company,  Inc.  (SIC  2851), for
violations of RCRA at its facility in Cuba, MO.
The  complaint  proposed  a  total  penalty of
$257,335. On May 11, 1994, the parties reached
a  settlement whereby Cuba agreed  to  pay  a
mitigated  penalty of $87,000, and to perform two
SEP. The value of the SEPs total an estimated
$417,000.

EPCRA

In the Matter of Raw Valley,  Inc.:   This case
arose out of an administrative complaint issued to
Kaw Valley of Leavenworth, KS, by EPA alleging
three counts of failure to file reporting forms as
required under EPCRA §313. An Administrative
Law Judge found Kaw Valley liable for failure to
report.  Kay Valley, however, argued that EPA's
proposed  penalty of $15,000 should be reduced.
Kaw Valley, relying on information presented in
a 1987 EPA seminar, believed it was exempt from
reporting.   The  ALJ reduced  the  penalty to
$12,750 on the grounds that the seminar presented
a definition of "full-time  employee" that differed
significantly from the definition later adopted in
EPA's final rule. The ALJ found that only a small
reduction was  warranted because, although it was
informed  in  January 1989, by EPA officially that
it  was required to file, Kaw Valley submitted its
Form Rs  at least 6 months later, only after the
EPA filed a  complaint.   Kaw  Valley  sought
judicial review in the federal District of Kansas of
the  EPCRA   §313  definition  of  "full-time
employee" at 40 CFR §327.3, arguing that EPA
lacked authority to  issue the definition, and that
EPA's rulemaking defining "full-time  employee"
failed   to  comply  with   the  Administrative
Procedure Act.  Kaw Valley  also appealed the
penalty assessment.  The  federal district court
found that EPA had authority to interpret the term
"full-time employee,"  that EPA's interpretation
was   reasonable,   that  the  rulemaking   was
procedurally adequate, and, alternately, that issuing
such an interpretation  was within the Agency's
inherent authority and exempt from notice and
comment requirements.

In the Matter of The Iowa Packing Company: A
CACO was entered August 8, 1994, whereby the
Iowa Packing Company of  Des Moines, Iowa,
agreed to  pay $28,000 for failing  to submit
EPCRA  §312 Tier II  reports for ammonia to
SERC and LEPC for 1988  and  1989,  and for
failing to report EPCRA §313 use of ammonia for
calendar  years 1987 through 1989.  In addition,
Respondent agreed to construct and implement a
wastewater pretreatment facility for a  cost of
$850,000,  which   will   significantly  reduce
pollutants discharged into the City of Des Moines,
IA sanitary sewer system. Respondent also spent
$11,500 for the installation and implementation of
an ammonia diffusion system for its Des Moines,
IA facility.

CERCLA

U.S. v. Chemical Waste Management of Kansas,
Inc.   (D.  Kan.):   On July 21, 1994, a  cost
recovery consent decree in this matter was entered
with  the  court.    The   National  Industrial
Environmental  Services  Site  (the  Site)  is  a
contaminated hazardous waste facility located near
Furley, KS. The Site has been stabilized through
remediation by Chemical Waste Management of
Kansas, Inc. (CWMK) with EPA oversight. EPA
continues its oversight with regular sampling and
related activities.  In this consent decree, CWMK
has agreed to pay 90 percent of EPA's past costs
($1,561,594.24) plus 100 percent of all of EPA's
oversight costs after the date of  entry.  In return,
EPA is granting CWMK a covenant not to sue and
contribution protection regarding the  Site.

U.S. v. TIC Investment Cory., et al. (N.D. la.):
On  September 18, 1994, the  court  issued an
opinion and order holding two parent corporations
and  a corporate officer/shareholder directly liable
on summary judgment for costs of response at the
White Farm Equipment Dumpsite in Charles City,
                                             A-58

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 Iowa.  The opinion is significant for two reasons.
 The decision held a  parent corporation  and a
 corporate officer directly liable under §107(a)(3)
 as arrangers for disposal.  It also held the parent
 company liable on summary judgment. The court
 held that there must be some actual parent/officer
 involvement  in the operations of the subsidiary,
 but that it is not necessary to show involvement in
 waste disposal activities or daily operations of the
 subsidiary. The opinion also contains a discussion
 of  the  policy   considerations  which  support
 extending use of parent "owner/operator" liability
 case law to "arranger" cases.

 In the Matter  of the  Bis  River Mine Tailings
 Site:   On July  7,  1994,  EPA issued  an AOC
 requiring Doe Run Resources Corporation and St.
 Francis  County  Environmental  Corporation to
 perform  a  non-time   critical  removal   action
 designed to prevent any further  releases of  lead
 from the 600-acre tailings pile. The estimated cost
 of the  work to  be performed  is $12  million.
 Under the terms of the AOC, Doe Run Resources
 agreed to perform  extensive  slope stabilization,
 regrading, and revegetation of the entire pile.  The
 objective of the removal action is to prevent any
 further releases of lead-contaminated tailings from
 the site.

 In the Matter of Lee  Chemical Co. Superfund
 Site, Liberty, Missouri:  A  CERCLA  §122(h)
 Agreement for Recovery of Costs filed on May 23,
 1994, recovered $389,522 from the Department of
 Energy  and Allied  Signal,  Inc.,  which  was  100
 percent of EPA's past response costs  for the site
 located  in  Liberty, MO.   The  settlement  was
 initiated  as .  part  of   a cooperative  EPA/state
 enforcement effort in which the State of Missouri
 took the  lead  for  ensuring completion  of the
 remedial action via an AOC with the site owner,
 a municipality,  while  the  EPA  pursued its past
 costs against  the federal agency and government
 contractor parties who were  the site's  waste
 generators.

 U.S.  v.  Boehrinser Inselheim  Animal  Health,
Inc. (D. Neb.):  This consent decree settled EPA's
 Superfund cost  recovery case against Boehringer
Ingelheim Animal Health, Inc.  (BIAH) as a de
 minimis waste  contributor  settlement.   BIAH
 contributed about 0.495 percent of the 1,354,801
 pounds of hazardous substances processed at the
 Site.  The total  EPA costs, incurred for the EPA
 clean-up  of  the   Economy  Products  facility
 amounted to  $3,812,461.  BIAH's pro rata share
 of the response costs is calculated at $18,872. The
 $100,000  settlement  includes   a   400-percent
 premium.

 In the Matter of Rentier Road Shooting Park:
 The Renner Road Shooting Range Site is  located
 in  Shawnee,  KS.    It  contains serious  lead
 contamination from years  of operation  as  a
 shooting  park.     EPA  issued ,  an  Action
 Memorandum on March 18, 1993, for conducting
 a  time-critical removal, which was completed in
 1994.  EPA incurred approximately $1 million in
 clean-up costs.

 In September 1994, EPA  issued two AOCs to the
 two de  minimis  parties pursuant to the authority
 under the de minimis waste contributor provisions
 of CERCLA  §122(g)(l)(A).   The  de minimis
 settlements provide that the parties  will pay a total
 of $41,250. The  settlement amounts were $30,000
 for one  party  and $11,250 for the other, based on
 the amount of waste each party contributed to the
 site (5 percent and  1.7 percent, respectively).

 U.S. v.  City  of Clinton.  Iowa (S.D.  la.):  In
 September 1994, EPA referred to the  Department
 of Justice a de minimis landowner RD/RA consent
 decree that it is  proposing to  enter into with the
 City of  Clinton, Iowa,  pursuant  to .CERCLA
 § 122(g)( 1 )(b). The City of Clinton has held title
 to the Chemplex Superfund Site since 1967 as part
 of an  industrial development bond sale-leaseback
 arrangement.  There is no evidence that the City
 has had any involvement with the  Site other than
 as a nominal  title  holder who holds indicia of
 ownership to protect a security interest.  Thus, the
 EPA  is entering into a  de  minimis  landowner
 settlement with the City of Clinton, Iowa.  The de
minimis settlement requires the City to  provide site
 access to EPA and the other PRPs, and to comply
 with deed  restrictions.    In exchange, the  City
received a covenant not to sue and contribution
protection.
                                            A-59

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
U.S. v. Midwest Asbestos Control, Inc., et al. (D.
Kan.): On July 25, 1994, Philip Buch, a former
supervisor for Midwest Asbestos Control, Inc., and
the company itself were sentenced in the District
Court of Kansas after their respective guilty pleas.
The pleas stemmed from the unlawful disposal of
asbestos at the site of a related company, Midwest
Metals, Inc.

Buch pled guilty to the CERCLA misdemeanor of
failing to notify EPA of the existence of a facility
at which hazardous substances had been disposed,
a violation of 42 U.S.C. §9603(c).  He was
sentenced to 3 years probation and 100 hours of
community service, and was fined $25 in Special
Assessments.   Midwest Asbestos Control pled
guilty to the CERCLA felony charge of failing to
notify the  appropriate government agency  of the
release into  the  environment  of a reportable
quantity of a  hazardous substance, a  violation of
42  U.S.C.  §9603(b).   Midwest Asbestos was
sentenced to a fine of $2,500 and a $200 special
assessment.
                                             A-60

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT {4gg)
                                       REGION Vin
 CLEAN AIR ACT

 Sinclair Oil Corporation:  On October 15,  1993,
 EPA filed a fiilly executed CACO for Payment of
 Civil Penalties,  settling a §113(d) administrative
 penalty order issued May 20, 1992. The violations
 cited   involved   NSPS   Subpart  "J"   CEM
 requirements,  specifically  the  failure  to  install
 continuous emission monitors for all affected fuel
 gas combustion devices by October 2, 1991.  The
 original administrative action sought a penalty of
 $105,187.  The settlement reduced the penalty to
 $35,000 and gave credit of $70,187 in  exchange
 for a SEP valued at about $270,000, resulting in a
 3.85:1 offset ratio.  The SEP required the upgrade
 of the existing sulfur recovery unit.

 CLEAN WATER ACT

 Dirt Merchant Construction/Sandra Tarr:  On
 April 14,  1994,  EPA issued an AO against Dirt
 Merchant Construction Company, Inc. and Sandra
 Tarr, a Delta, CO, landowner  for violations of
 §404 of the CWA.  The violations occurred when
 the  company  built two  illegal   dikes  in the
 Gunnison River near Delta, CO,  in endangered
 fish  species  habitat.    The enforcement action
 successfully abated an  imminent  threat to  river
 stability and endangered fish species.  The owner
 of the property is now cooperating with the Corps
 of Engineers by seeking authorization  for  bank
 protection measures.

Lucas Western (Jamestown, North Dakota): On
June 26, 1991,  EPA referred the  Department of
Justice a case citing Lucas Western for violations
of federal pretreatment regulations.  Lucas Western
discharges  its  wastewater  to  the  Jamestown
wastewater  treatment  plant.   Lucas  Western
violated reporting requirements  and pretreatment
discharge limitations for pH and  chromium and
NPDES proceeded to refer the case independently.
On  May 4, 1992,  the complaint was  filed in
Federal Court.   In FY95,  the  Court  entered a
consent decree settling the case for $250,000, plus
an environmental audit.
 Farmers  Union   Central  Exchange  COOP
 (CENEX} (Billings. Montana):  EPA issued an
 NOV to the State of Montana  on November 11,
 1990,  for violation  by CENEX of its NPDES
 permit limits for Oil and Grease dating back to
 December  1986.     The   State  replied  on
 January 29, 1991, that due to a  lack of resources,
 the State would not pursue enforcement against
 CENEX.   On June  26, 1991, EPA referred  the
 CENEX case to the Department of Justice.  EPA
 agreed to settle this action with  the Company for
 a penalty of $316,000.

 Burlington  Northern Railroad (W.D., Wise.):
 The case against Burlington Northern, a registered
 corporation, is being jointly pursued by Regions V
 and VIII.  It involves three incidents: [1] On June
 30, 1992, several cars of a freight train operated
 by  Burlington  Northern  derailed on  or  near a
 trestle  over  the Nemadji  River in Wisconsin.
 Three of the cars fell from the  trestle.  One car,
 which  contained  a  product called  "aromatic
 concentrates,"   ruptured   and  discharged
 approximately 21,000 gallons of its contents into
 the Nemadji River.   [2] On January 9, 1993, 25
 cars of a  freight train  operated by Burlington
 Northern'  derailed  on  or near  a track  in the
 Wendover Canyon,  adjacent to  the  North  Platte
 River in Guernsey, WY.  Eleven  cars fell from the
 track.  Several  of these cars,  which contained
 decant  oil,  ruptured and  discharged at  least
 100,000 gallons  or 2,380 barrels  of oil into the
 North Platte River.  [3] On May 6, 1993, nine cars
 of a freight train operated by Burlington Northern
 derailed from a  track near Worland, Wyoming.
Three of these cars, which contained clarified oil,
 ruptured and discharged at least 40,000 gallons or
 953 barrels of  oil into  drainage ditches which
empty  into  and are tributaries  of  the Bighorn
River.

The spill into the Nemadji River released benzene,
toluene,  isoprene,  naphthalene,  and styrene in
excess  of their reportable quantities.   The  two
Wyoming releases caused a film  or sheen upon or
discoloration  of  the  surface of  the North  Platte
                                            A-61

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
River, the drainage ditches of the Bighorn river or
their adjoining shorelines, or caused a sludge or
emulsion to be deposited beneath the surface of
those bodies of water or upon their adjoining
shoreline.   Burlington  Northern  made  proper
notifications to EPA about the Wyoming spills.

In this civil action, brought under the  CWA as
amended by the Oil Pollution Act (OPA),  EPA
also sought $279,078 to recover costs incurred
consistent with the National Contingency  Plan
under CERCLA and OPA, and natural resource
damages totalling $250,000.  The CWA penalties
totaled $2.5 million.

Hub  City. South  Dakota:    EPA  issued  a
complaint dated December 2, 1992 charging Hub
City with violations of the Clean Water Act and
the General Pretreatment  Regulations Reporting
Requirements for failing to timely submit a BMR,
a  90-day  Compliance  Report  and  Periodic
Compliance Reports.  EPA Region VIII and Hub
City, Inc. have signed a consent agreement settling
this administrative case.  Hub City has agreed to
pay a civil penalty of $12,500 and to undertake a
SEP  requiring  the installation  of a  coolant
recycling  system, to recycle spent coolant  from
Hub City's machining process.   The SEP will
reduce loadings of biological oxygen demand to
the City of Aberdeen, South Dakota's sewer. It is
estimated that the cost of the SEP will be at least
$68,000.  The project will be completed by Hub
City by December  31, 1994.  The cash penalty
amount of $12,500 recovers economic benefit and
the cost of the SEP ($68,000) is more than two
times the gravity which was calculated at $27,000.

City of Sioux Falls, South Dakota:: EPA Region
VIII and  the City of Sioux Falls,  South Dakota
have agreed to  settle this Clean  Water Act
administrative case for a civil penalty of $26,250
and the undertaking by the  City of a SEP.  The
SEP is a household  hazardous  waste  recycling
program which  cost will be in the  $150,000  -
$200,000 range.   EPA initiated  this action by
issuing a complaint to the City dated November
19, 1992  alleging violations of the Clean  Water
Act,  its   NPDES  permit  and  the  General
Pretreatment regulations codified at 40  CFR Part
403.  Most of the violations relate to the City's
failure  to  properly  implement  the  Industrial
Pretreatment requirements of 40 CFR Part 403.

Star  Circuits:   EPA  Region  VIII and  Star
Circuits, Inc.  have agreed to settle this Clean
Water Act administrative case for a civil penalty
of $17,500 and the undertaking by Star Circuits of
two SEPs requiring environmental audits of both
the Star Circuits facility, as well as Star Circuit's
parent,  Daktronics'  facility,  both  located  in
Brookings,  South  Dakota.  The second SEP is a
waste minimization project for  the Star Circuits
facility. It is estimated that the costs of the SEPs
will total approximately $30,000.

SDWA

Town ofMeeteetse, Wyoming:  On September 1,
1994, EPA  issued an  emergency administrative
order to the Town of Meeteetse, Wyoming.  The
order was issued when tes*« indicated the presence
of  Giardia  in  the  finished  drinking  water.
Additional testing, performed immediately after the
emergency order was issued, detected the presence
of Cryptosporidium in the finished drinking water.

The   emergency  order  required  the Town  to
provide an  alternate  source of potable water;
provide . public  notice  of  the  presence  of
microbiological contaminants in the public water
supply; issue a boil water notice to those served
by  the system; perform  an evaluation  of the
system  to determine changes necessary  to  bring
the system  into  compliance with the filtration
requirements for a system that uses a surface water
source; and submit quarterly reports on  progress
made toward bringing the system into compliari'ce
with requirements for a system that uses a surface
water source.

City Oil Corporation:   A default judgment was
entered  against  Christopher  Martin  Pedersen
requiring compliance and  assessing a penalty of
$1.8  million.    The  case  against City  Oil
Corporation  resulted   in  the  same  judgment,
including the  $1.8 million penalty.  There were
numerous violations of the UIC program for 19
injection wells located on or near the Blackfeet
                                             A-62

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Indian  Reservation  in  Northwestern Montana.
Violations  included:    unauthorized injection,
failure to maintain gauges, monitor, report perform
mechanical integrity tests, plug and abandon, etc.
City Oil Corporation filed for bankruptcy and the
bankruptcy court ordered that the wells could  be
abandoned from the company's liabilities.

RCRA

Reclaim Barrel:  This facility is a former barrel
reconditioner  located  in  West Jordan,  Utah.
Following an inspection in FY94, it was identified
as an illegal storage and disposal facility. Three
Regional  programs   (RCRA,  CERCLA,  and
NPDES) coordinated  their  information requests
and  sampling.    An  initial  RCRA  §3008(a)
complaint and order was issued on September 14,
1994.  The proposed penalty is $488,749.

EPCRA

Advanced Forming Technology:  In FY94,  an
administrative complaint was issued to Advanced
Forming Technology  for failure to report under
EPCRA §313 for the use of 1,1,1-Trichloroethane
(TCA). As a result, EPA and Advanced Forming
Technology  settled in FY94 for  a  penalty  of
$8,110 and a SEP costing approximately $20,000.
The  SEP  required the facility  to purchase and
install  Vapor Trap Freeboard Chillers and Mylar
Rolling Covers on  each  of the  two  solvent
degreaser baths in  order to reduce the amount of
TCA released to the environment. The outcome of
the project resulted in a 35-percent usage reduction
of TCA, while production output increased by 45
percent.

Accurate Plastics (now SPM/Denver): On March
2, 1992, an administrative complaint was issued to
Accurate  Plastics  for failure  to  report under
EPCRA §313 for  the use of Ethyl Ketone and
Toluene in  1989.   EPA and Accurate  Plastics
settled the case in  FY94 for a penalty of $2,060
and  a SEP costing approximately $89,742.  The
facility purchased and installed  a Graco-Assisted
Airless  Paint Spray Unit and a Fanuc Robotics
Spray Unit to reduce  total VOCs releases to the
atmosphere by as much as 10 percent.
Denver Metal Finishing Company: In December
1991, EPA  issued  an  administrative complaint
against  Denver  Metal  Finishing  Company  for
failure to report under EPCRA §313 chemicals
that were otherwise used. In FY94, the  case was
settled requiring the facility to pay a monetary
penalty   of  $8,900   and to  undertake  a SEP
requiring the purchasing and installation of a DSF
12 DynaSand Filter. The DynaSand Filter is a
continuous backwash, upflow, deepbed granular
media filter.   The filter media is continuously
cleaned by recycling the sand internally through an
airlift pipe and sand washer.  The  purpose of the
filter is  to remove any  heavy metals from waste
generated during the process conducted by  the
facility.

Nephi Rubber Products: An EPCRA §311/312
compliance  inspection   was  conducted at  the
facility in Nephi, Utah, and $49,920 in proposed
penalties  were  assessed  as  a   result  of  the
inspection findings.   In addition to  the EPCRA
violations, the State of Utah issued  a NOV and
CO for RCRA violations. Prior to  the issuance of
the complaints, the company filed a petition  for
bankruptcy. The company has little, if any, ability
to pay a penalty.The State of Utah and EPA will
negotiate with the Respondent on which the P2
project is to  be  undertaken by the facility as a
SEP.

Thatcher Chemical Company:  Over 100 pounds
of  sulfur   dioxide  was  released   into   the
environment when a hose connection failed during
a transfer from rail car to fixed tank.  Notification
to the proper authorities was delayed—a violation
of EPCRA  §304.    Proposed  penalties in this
complaint were $33,250. Negotiations  with  the
Respondent on a SEP as partial settlement to this
complaint were successful. The SEP included the
construction   of  a  building   with  scrubbing
equipment for enclosure of vehicles while loading
products to  prevent  future  releases  into  the
environment of hazardous chemicals.

FIFRA

Biotrol   International,   Inc.:    EPA   settled
administrative actions against Biotrol and Stepan
                                            A-63

-------
       | FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Company (subregistrant and registrant) for making
unsupported claims for the disinfectant vacusal.
EPA  also  finalized settlement  of two previous
cases against Biotrol for a $21,000 penalty.

CERCLA

Apache Energy and Minerals Co. (D. Colo.): On
December  15, 1993, the district court entered a
consent decree in  which the Denver and Rio
Grande Western Railroad (D&RGW) agreed to
reimburse EPA over $1,125,000 in past response
costs  at the site.  D&RGW also agreed to conduct
a feasibility study and implement remedies to be
selected by EPA in the future for certain portions
of the site. On August  17, 1994, the district court
entered a consent decree in which Hecla Mining
Company agreed to pay $516,000  for past and
future response costs.   The United States  as
defendant  agreed  to  pay EPA $172,000 for
response costs to resolve claims for its potential
liability at  the  site.  On August 26, 1994 the U.S.
District Court  entered a consent decree in which
Asarco,  Inc.,  Resurrection  Mining  Company,
Newmont Mining Company and the Res-Asarco
Joint  Venture  agreed to reimburse EPA  for $7.4
million in  past response costs at the site.  The
Settling  Defendants also  agreed   to  complete
feasibility studies and perform remedial actions at
a majority of the site. It is estimated that Settling
Defendants commitment to perform work at the
site is in excess of $60 million.

SmuEKler-Durant Minine Corporation (D. Colo.):
On July 6, 1994, the court entered a civil consent
decree in which the Atlantic Richfield Corporation
(ARCO)  and  the United  States Department  of
Interior both agreed to  pay $1.6 million  each for
past   response costs incurred at the Smuggler
Mountain  Superfund site in  Aspen, CO.   The
Department of Interior paid their portion of the
settlement  from  the  newly established   DOJ
judgment fund. In addition, EPA concluded very
difficult and lengthy negotiations with both Pitkin
County  and MAXXAM.   Two  civil  consent
decrees were completed in late FY94. The County
decree was lodged  in  December 1994  and the
MAXXAM decree should be lodged in January
1995.  The conclusion of negotiations with these
parties in FY94 means that only one party of the
original eleven parties  that were  sued by  the
United  States  in  1989 now  remains in  the
CERCLA§107 litigation.

Clear Creek/Central City Superfund Site, Western
Diversified Builders:   EPA assessed  stipulated
penalties in the amount of $44,000 for violations
of an  AOC  for Removal Action  at  the  Clear
Creek/Central  City Superfund site.   Under  the
order,  Respondent was  obligated to perform a
removal action at the National Tunnel  portion of
the site. The action included piping of discharge
from a mine and the removal and proper disposal
of contaminated soils.  Despite repeated notices
and warnings, Respondent failed to  submit  status
reports  and  was  substantially behind  schedule.
EPA imposed penalties  to  ensure  a return to
compliance for reporting violations and to push
completion of the removal action. After issuance
of  the  penalties,  Respondent  returned  to
compliance and  agreed  to Complete the project
according to a revised schedule.  EPA agreed to
settle  payment of the penalties  for $22,000, if
Respondent completed  the project  on schedule.
Respondent completed the project on schedule and
made payment of $22,000 as final  resolution of
the penalty action.

Whitewood Creek: EPA's Cost Recovery Program
sent  its annual bill  for  oversight  costs in  the
amount of  $681,164   to  Homestake  Mining
Company (Homestake) on May 14, 1992, pursuant
to a consent decree with Homestake. On June 9,
1992, Homestake invoked the dispute  resolution
and placed the $681,164 in  an  interest-bearing
escrow  account.   Several  letters  and  phone
conversations occurred during the following year
with no resolution. On March 2, 1993, EPA sent
its second  annual billing to  Homestake in  the
amount of  $238,966.23.    Homestake,  again,
disputed this bill and placed the amount in another
interest- bearing escrow account. In FY95 EPA
received a check for $992,204 from Homestake
Mining, the total amount in dispute.  In addition to
collecting $63,604 in interest that had accumulated
in the Escrow Account,  EPA during this period,
discovered an additional $8,471  in expenditures
that were omitted from original billings.
                                             A-64

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT f
Petrochem/Ekotek Site:  EPA's Cost Recovery
Program  billed the  Ekotek  site  Remediation
Committee  (ESRC)  PRPs  for  oversight costs
pursuant to AOC (CERCLA-Vni-92-21) for a
RI/FS in the amount of $416,636.39 in August of
1994.   The ESRC objected to many of EPA's
oversight costs, EPA's cost accounting procedures,
and the level of documentation that was provided.
In FY95 the ESRC paid EPA the total amount in
dispute.

Petrochem/Ekotek: During FY94, EPA conducted
a  de  minimis settlement  project  resulting  in
settlement proposals being offered  to over 1,000
Potentially Responsible Parties (PRPs) who were
believed to have  sent  waste materials  to this
Superfund site.  Early projections for cleanup costs
at the site had been projected at approximately $69
million.  In an effort  to be fair to these smaller
waste contributors, EPA moved quickly, sending
out hundreds  of CERCLA  104(e) Information
Request letters, proposing settlement offers and
reviewing eligibility for de minimis settlement.  In
July,  1994, the Hazardous  Waste Management
Division Director signed 363 administrative orders
on consent, including 16 federal entities.  This
expedited de minimis  settlement is  anticipated to
generate $7.8 million.  The funds will be placed in
a special account to be used for site cleanup and
EPA oversight of the selected remedial  action,
which is projected to occur in the Spring of 1995.
EPA  has  also  initiated proposed de  minimis
settlements with two additional groups at the site
totaling 38 parties.  One of these groups include
parties  who have  successfully demonstrated  to
EPA their inability to  pay  the  full settlement.
EPA has offered these parties reduced settlement
payments in an effort to ensure significant but fair
PRP participation in the cleanup of the site. It is
anticipated that when  these additional settlement
are finalized, total de minimis settlements for the
site will total $8.3 million.

Colorado School of Mines  Research Institute:
Waste   materials  which  resulted  from  work
performed by CSMRI at the  facility include low-
level radioactive waste, lead, arsenic, and other
heavy metals.  Removal actions began at the Site
on January 25,  1992, in response to a water main
break.   Negotiation for a removal AOC started
almost immediately; however, these negotiations
were not successful. A de minimis settlement was
offered to 56 PRPs on June 10, 1994. The offer
was accepted by 47 PRPs.

The de minimis AO was finalized in FY95, for a
total of $1,340,584. One de minimis PRP was a
federal facility, the Tennessee Valley Authority,
and the remaining PRPs were private companies or
corporations.

North American Environmental, Inc.:  The North
American Environmental, Inc. (NAE) Site engaged
in  the  business   of   collecting,   packaging,
transporting,  and disposing of waste oils  and
debris (transformers, capacitors, light ballasts, etc.)
containing PCBs. Other contaminants found at the
Site included solvents and cyanide.  NAE began
receiving wastes at the Site in September of 1986.
In August of 1990, NAE submitted an application
to EPA for a commercial storage permit for PCB-
contaminated wastes  for  the Site.   EPA denied
NAE's application  for a permit due to the failure
of  NAE to  provide  sufficient  and/or complete
information   regarding  a  financial  assurance
mechanism required for closure.  On October 5,
1990, EPA notified NAE that it should not accept
any more waste at the  Site,  and that it should
dispose of the remaining inventory within 30 days.
On December 3, 1990, EPA notified NAE that it
was denied  final  storage approval  and that  it
should close the facility.  NAE claimed financial
inability to do so, and abandoned the Site.

On  February  28,  1992,  EPA  allowed  the
landowner (Freeport Center Associates), to provide
an  opportunity  for the generators of the waste
stored at the Site to retrieve and dispose of their
own wastes,  according  to  EPA protocol, from
March  1, 1992, through September 1,  1992.  On
September 2, 1992, approximately  700 drums and
26 transformers remained at the Site. In addition,
four railroad  tanker  cars,  containing  varying
volumes  of liquid waste and one railroad boxcar
containing  approximately 15  drums  of  waste
remained at  the Site.   EPA negotiated a removal
AOC with Freeport Center Associates, the current
owner of the Site, and the U.S. Defense Logistics
                                             A-65

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Agency, a generator of wastes at the Site. The
AOC  was issued to the two above-mentioned
Respondents on  October 5,  1993.   The AOC
required that a site inventory be completed prior to
the start of the removal action.

Respondents were found to be in violation of the
AOC for failure to  notify EPA in writing seven
days before beginning  the  site inventory  of
hazardous  substances and for  failure to submit
daily, weekly, and monthly reports as required by
the AOC.  EPA assessed stipulated penalties for
these violations and  sent a demand letter for
$12,000 to the Respondents on March 23, 1994.
Payment was received on April  4,  1994.  The
PRP-lead removal action began on August 1, 1994
and is scheduled to be complete by the 3rd quarter
ofFY95.
                                           A-66

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                        REGION IX
CLEAN AIR ACT

U.S. v.  Shell Western E&P. Inc. (E.D. Calif.):
On  August  11,  1994,  the  court  entered  a
stipulation and order of dismissal in which Shell
Western agreed to pay $337,000 in civil penalties
in order to settle a civil action brought under the
CAA.   This  action arose from Shell Western's
violations  of   California   SIP   requirements
applicable  to oil  recovery  at  the company's
Belridge Oil Field in Kern County, CA. The civil
complaint alleged violations relating to emissions
of VOCs and breakdown reporting violations. An
NOV was issued  to  Shell Western after  EPA
reviewed the company's responses to information
requests under §114 of the CAA.

U.S. v.  TABC,  Inc. (C.D. Calif.):  On May 26,
1994, the court entered a consent decree in which
TABC agreed to pay  $485,000 in civil penalties
and  to  install  and  operate  pollution  control
equipment in order to  settle a civil action brought
under the CAA.  This action arose from TABC's
violations of California SIP rule that limits the
VOC content of coatings applied to automobile
parts at TABC's facility in Long Beach, CA. The
civil complaint alleged that TABC violated the SIP
at its facility by using coatings with VOC contents
that exceeded the limits imposed by the SIP rule.

U.S. v. Minerec, Inc.  (D.  Ariz.):  On August 26,
1994, EPA issued an emergency order to Minerec
Mining Chemicals, a chemical manufacturing plant
located in the San Xavier District of the Tohono
O'odham Nation in Arizona. EPA made a finding
that operations at the Minerec facility presented an
imminent and  substantial  endangerment to the
public health or welfare or the environment and
issued an order requiring  that Minerec shutdown
its manufacturing  operations.  That  order was
subsequently amended to allow limited production
at the facility, and to  require that Minerec install
monitoring  devices.    This case  involves the
precedent setting use of  a CAA §303 order to
close  down  a  facility  based on  the risk  of
uncontrolled releases of hazardous chemicals.
U.S. v. All American Pipeline Company (C.D.
Calif.): On September 19, 1994, the court entered
a civil consent decree in which All American
Pipeline Company (AAP) agreed to pay $714,000
in civil penalties.  AAP also agreed to perform an
SEP and injunctive relief.  For the SEP,  AAP
agreed to remove three internal combustion (1C)
engines,  thereby  eliminating substantial  NOX
emissions.

CLEAN WATER ACT

U.S. v. American Global Line, Inc. (N.D. Calif.):
On  September 20, 1994,  the captain of an 800-
passenger luxury liner and two shipping company
executives pled  guilty  in federal  court  in San
Francisco  to  illegally dumping several tons  of
debris into the ocean. The firm, American Global
Inc., pleaded guilty to a felony violation and was
fined $100,000.  Lloyd R. Haugh, captain of the
Independence, pleaded  guilty to  a misdemeanor
offense for instructing his crew to illegally dump
about five tons of debris into the ocean  in May
1992.  He was ordered to pay a $5,000 fine and
placed on probation for  a year.  The incidents
involved the dumping of renovation debris  from
the  cruise ships Independence and Constitution
during trips  from  Honolulu to  Portland and
Honolulu to San Francisco.

Two corporate officers  of American Global Line,
Peter  Bianchi  Jr.,  senior  vice-president  for
operations, and  Robert  Elder  White  III,  vice
president of marine operations also pleaded guilty
to a misdemeanor. They were each fined $5,000
and placed on probation for a year.

U.S. v. Magma  Copper Co. (D.  Ariz.):   On
November 8, 1994, the court entered a  consent
decree resolving a suit brought by EPA  and the
State of Arizona against Magma Copper Co. The
suit  was brought in response to violations of the
CWA and related State law at three copper mining
and  processing facilities  operated by Magma in
southeastern Arizona. The decree requires Magma
to pay penalties of $385,000 to the United States
                                             A-67

-------
       Jl FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
       '
and $240,000 to  Arizona.   The  decree  also
requires Magma to undertake compliance measures
and to complete  a  SEP  designed  to  control
contamination at an abandoned mine. The cost to
Magma of implementing  the SEP is difficult to
predict prior to completion of the project planning
phase, but is estimated to be $1.5 million.  The
decree further requires Magma to pay $50,000 to
fund three additional SEPs which the U.S. Forest
Service will  complete to  benefit  the affected
watersheds.

U.S. v. City and County of Honolulu (D. Haw.):
On October 3, 1994, a consent decree was lodged
resolving  a CWA enforcement action brought by
the United States and the State of Hawaii against
the City and County of Honolulu.   This action
arose as  a result  of the City  and County  of
Honolulu's poor maintenance of its sewer system,
which resulted  in  over 300  spills of raw  or
partially-treated  sewage into  Hawaiian  waters
(including a  spill of  50 million gallons  of raw
sewage into Pearl Harbor in 1991 that attracted
national  attention).   The City  and County  of
Honolulu  also failed  to implement an adequate
pretreatment program to regulate the discharge of
toxics from industries discharging into its sewer
system.

Under the consent agreement, the City and County
of  Honolulu will  pay  a  civil  penalty of $1.2
million  and   has   committed  to  improve  the
operation   and   maintenance   of  its   sewer
system—including the renovation of 1900 miles of
sewer lines over the next 20  years and to develop
and implement a pretreatment program to regulate
the discharge  of  industrial toxic  wastewater.
Under the  decree,  the  City  and  County   of
Honolulu has also committed to spend $30 million
on SEPs for treating and reusing wastewater and
sludge.  Honolulu will recycle 10 tons of sewage
sludge per day by 1998 and  10 million gallons  of
wastewater per day  by the year 2001.

U.S. v.  Southern Pacific Transportation Corp.
(E.D. Calif.):  On March  14,  1994, a consent
decree was lodged in court resolving the remaining
claims of the United States arising from the 1991
spill of metarn sodium into the Sacramento River
 caused by a Southern Pacific train derailment on
 July 14,  1991.

 The settlement  resolves  the causes  of action
 against Southern Pacific Transportation Company,
 its  parents and subsidiaries, against  the  General
 American Transportation Corporation and GATX
 Corporation (owners of the tank car), as well as
 against the companies that were lessors/lessees of
 the tank car. The settlement provides for recovery
 of $36 million in response costs, which provides
 for full payment of all EPA response costs.  The
 decree also requires payment of a $500,000 CWA
 civil penalty, equivalent to the statutory maximum
 for the  violations  in question.  In addition, the
 consent  decree   requires  that   the   Settling
 Defendants establish a $14 million  fund to be
 administered  by  the natural  resource  trustees,
 including the U.S. Fish and Wildlife  Service, for
 use in restoration/mitigation  of natural resource
 damages.

 U.S. v. Teledvne. Inc. (S.D. Calif.): On April 12,
 1994 a consent decree was entered resolving the
 CWA enforcement action  against Teledyne, Inc.
 for violations at its Ryan Aeronautical facility in
 San Diego, CA.  The decree requires Teledyne to
 pay a civil penalty of $500,000 in settlement of
 the United States claims. This action was  brought
 as a result of Teledyne's repeated violation of the
 federal   categorical   pretreatment    standards
 governing metal finishing point sources. Teledyne
 had also violated the prohibition against dilution as
 a substitute for treatment by adding unnecessary
 quantities of water to its process wastewater prior
 to discharge into the City sewer system.

 U.S.  v.  County   Sanitation  Districts  of  Los
Aneeles County (S.D. Calif.): On June 6, 1994,
 a consent decree was entered  resolving the CWA
 enforcement action against the County Sanitation
 Districts of Los Angeles County (CSDLAC).  The
 United States and the State of California sued in
 January  1992  to  compel  CSDLAC  to  achieve
 secondary treatment at the Joint Water Pollution
 Control  Plant  located in  Carson, CA,  and to
 address additional intermittent violations of other
 permit conditions.  Under the terms of the consent
 decree,  CSDLAC  was required to pay  a civil
                                             A-68

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I ^
penalty of $300,000 to the United States and a
penalty of $200,000 to the State of. California.
The decree further requires CSDLAC to complete
a program to promote  the beneficial reuse of its
wastewater, and requires CSDLAC to implement
a household hazardous waste collection program
costing at least $1.2 million.

RCRA

17.5. v. Hawaiian  Western Steel, Ltd., Estate of
James Campbell, Ipsco Inc. and Cominco Ltd.
(D. Hawaii):   On August 2,  1994, the court
entered the consent decree signed by three of the
four defendants in this case. The decree provides
for payment  of $700,000  in  penalties by  all
settling defendants jointly.   The decree also
provides that HWS will  implement corrective
action  and closure at the facilities at issue and the
Estate  will annually survey its tenants concerning
their compliance with environmental laws  and
organize programs educating its tenants concerning
hazardous waste laws and pollution prevention.

In the Matter of U.S. Naval  Air Facility,  El
Centra, California:  On August 29, 1994, EPA
signed  a  CACO  resolving an  administrative
complaint against the U.S. Naval Air Facility in El
Centro, CA,  involving various  violations of the
RCRA.  Under  the terms of the settlement, the
Navy  will pay  a  penalty  of $100,000 and in
addition will perform  at the facility two SEPs
relating to pollution prevention.  The total cost of
the two SEPs is  approximately $250,000.

U.S v.  City of Los Angeles and U.S. v. Lockheed
Corporation  (C.D.  Calif.):   On  September 14,
1994, the United States filed settlements in five
industrial pretreatment civil cases. The settlements
totaled $750,000 in civil penalties.  The defendants
were   Lockheed  Corporation   (an  aerospace
manufacturer), Chevron, U.S.A.  (an  oil  refiner),
Teledyne   Industries   (a   computer  chip
manufacturer), Stainless Steel Products,  Inc. (an
aerospace manufacturer), and Zero Corporation (an
aerospace manufacturer).  All of the defendants
operate facilities in the greater Los Angeles area
and discharge into the City  of Los Angeles sewer
system. The defendants had numerous violations
of  EPA's  categorical  pretreatment  standards,
mostly for toxic metals, which contributed to the
City of Los Angeles' discharge of toxics into
Santa Monica Bay from its Hyperion Treatment
Plant.

U.S. v. Hawaiian Western Steel, etal. (D. Haw.):
Hawaiian Western Steel operated a secondary steel
production plant in the Campbell Industrial Park in
Ewa Beach, Oahu,  HI.   The  plant's emission
control system collected particulate matter from
the furnace, thereby  generating "baghouse dust"
which is an RCRA hazardous waste due  to high
concentrations  of  lead   and   cadmium.
Approximately 43,500 tons  of HWS' waste filled
a 4.5-acre on-site landfill.  Three of the four
named defendants, including Hawaiian Western
Steel signed a consent decree which required them
to pay $700,000 in penalties for violating RCRA's
permitting requirements for storing  and treating
hazardous waste, and  complete closure  of the
landfill and on-site and off-site corrective action at
an estimated cost of over $5 million.

CERCLA

U.S. v. Peter Gull and NL Industries, Inc. (C.D.
Calif.):  On April 12, 1994, the court signed a
judgment approving $2,687,982 in response costs
and  $3,670,274  in  punitive damages  for  NL
Industries'  failure to comply with  a CERCLA
§106 order to  clean up lead contamination at the
B&H Battery site in  Norco, CA.  The only other
defendant,   property   owner Peter  Gull, had
previously entered a settlement with the United
States.  In imposing  the penalty, the court found
that NL did not have  a sufficient cause defense to
the order because it "did not have an objectively
reasonable basis for  believing that  EPA's order
was  either  invalid  or  that EPA's order was
arbitrary and capricious."

Pearl Harbor Naval  Complex Federal Facilities
Agreement: On March 17, 1994, EPA, the State
of Hawaii, and the U.S. Navy signed the Federal
Facilities Agreement  (FFA) for the Pearl  Harbor
Naval Complex CERCLA site.   This  agreement
contains   several  changes  over  prior   FFAs,
including  strengthened  language  on splitting
                                             A-69

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
stipulated penalties with the State and a modified
dispute resolution process.  Under the modified
dispute resolution process, only the Secretary of
the  Navy   may   elevate  disputes   to  the
Administrator, and the parties state their intention
that  such disputes will be limited  to issues of
national significance.

U.S. v. Montana Refinins Co. (9th Cir.):  On
August 17,  1994, the Ninth  Circuit  granted the
United States' appeal of the district court decision
in this CERCLA cost  recovery  case  brought
against C. Michael Wilwerding, Poly-Carb, Inc.,
and  Montana Refining  Company in connection
with a removal action conducted at the Poly-Carb
facility in Wells, NV.  Montana Refining sent two
shipments of toxic spent phenolic caustic to the
Poly-Carb   facility,   operated   by   Michael
Wilwerding,  allegedly  as  "feedstock"   for  an
untested recycling  operation.   Montana Refining
paid the costs of shipment and did not have any
arrangement with Mr. Wilwerding for payment for
the feedstock. The phenolic caustic subsequently
spilled. EPA incurred response costs  of $482,410
in cleaning  up  the spill  after Montana Refining
failed to comply with an  EPA order.  The United
States  subsequently brought a cost recovery case,
the first such action in Nevada.

In the Matter of Iron Mountain Mine:  On April
22, 1994, EPA issued a CERCLA §106 order to
the current and  operators of the  Iron Mountain
Mine  Superfund Site,  T.W. Arman and Iron
Mountain Mines Inc., and the former owners and
operators Rhone-Poulenc Inc., requiring that they
construct new facilities and operate facilities
currently under  construction to treat  the  three
largest sources of acid mine drainage.  This acid
mine  drainage eventually enters the  Sacramento
River where it has been responsible for fish kills
and chronic  adverse  impacts on  an  important
fishery population, including a commercial run and
the winter  run  chinook salmon, an  endangered
species. Iron Mountain Mine was identified as the
largest uncontrolled  toxic  point  source in the
nation under the CWA §304(1) program and was
one of the first sites placed on  the Superfund
National Priorities List.

U.S. v.  Alcatel  Information Systems, Inc. (D.
Arizona): On September 2, 1994, a civil consent
decree for the remedial design and remedial action
at the Hassayampa Landfill Superfund site ("Site")
was lodged in the court.  The settlement requires
12 major settling defendants to design, construct,
and operate the remedy selected in EPA's Record
of Decision for the Site and to reimburse EPA for
all of its past and future response costs at the Site.
The   twelve major  settling  defendants  are:
Honeywell  Inc.; Bull HN  Information Systems,
Inc.; Alcatel Network Systems; Digital Equipment
Corp.; General  Instrument  Corp.; AT&T  Corp.;
Shell  Oil  Company;  Arizona  Public Service
Company; American National Can Company; Intel
Corporation;  Reynolds  Metals  Company;  and
Maricopa County,  AZ  (all  of the major settling
defendants  are  generators  except  for  Maricopa
County, which owned and operated the Site). The
settlement  also  provides  for  74  de  minimis
corporate generators and 3 settling federal agencies
(the U.S. Air Force, the Veterans Administration
and the  U.S. Forest Service)  to  resolve their
generator liability at the Site by cashing out to the
twelve major settling defendants.
                                             A-70

-------
      PV 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                                                                      V
                                        REGION X
CLEAN AIR ACT

Alyeska Pipeline Services Company and ARCO
Products:  On  November 4, 1993, the Regional
Administrator entered a CACO resolving the three
administrative complaints issued to Alyeska.  The
CACO assessed a final penalty  of $135,000 and
incorporated  the requirements  of an alternative
monitoring plan (AMP) to be used at the pump
stations  in  lieu  of the CEMS.    Under  the
alternative monitoring plan, Alyeska installed H2S
treatment process to remove H2S from the fuel gas
at the pump stations.   The  treatment,  a dry
chemical bed produced by SulfaTreat Company,
will reduce SO2 emissions to virtually zero (from
the existing  approximately  120  ppm).    On
September 30, 1994, the CACO was modified to
allow until October 8, 1994 for the SulfaTreat
systems to be installed and to require that  the
topping unit  at Pump Station 8 be permanently
shut down no later than March 31, 1995.

Norma and  Frank Echevarria,  d/b/a Echeco
Environmental Services: On December 27,1993,
EPA held that respondents were strictly liable for
violations of the CAA  and  asbestos NESHAP,
EPA  need  not  prove that visible  emissions  of
asbestos occurred to prove violation of the wetting
requirements, EPA could rely on the observations
of  inspectors  to  establish  that  asbestos  is
inadequately  wetted and  that once the asbestos
material  has  been collected  and contained,  the
wetting requirements of 61.145 no  longer apply.
EPA ordered  Echeco to pay a penalty  of $9,500.

Phillips  Petroleum Company  and AGI,  Inc.:
EPA filed an administrative case against these two
companies alleging they had violated the asbestos
NESHAP wetting requirements. After obtaining
affidavits from  Phillips documenting  that it had
hired  and paid a qualified  contractor (AGI)  to
perform  the  asbestos  removal properly and an
independent third party to monitor the contractor's
work, EPA entered into a settlement ordering AGI
to pay a penalty of $16,500,  and a stipulation  of
dismissal of the claim against Phillips (at Phillips'
and AGI's request).

Trans-AK   Environmental   Services    &
Construction  Corp.,  Giddings Mortgage  and
Investment Company, and Neeser Construction:
In  FY94,  EPA   issued   and  resolved   an
administrative    complaint   against   Giddings
Mortgage and  Investment  Company,  Neeser
Construction,   and   Trans-Ak  Environmental
Services  & Construction Corp.  The  complaint
alleged  violations   of the  asbestos  NESHAP
regulations during  renovation of the city hall  in
downtown  Anchorage,  Alaska.   The consent
agreement assesses a penalty of $40,000.   In
addition,   Trans-Ak   agreed  to  develop  and
implement an internal asbestos control program.

U.S.   v.   Global   Travel,   Jordan-Wilcomb
Construction, and  Allied Construction (D. Id.):
On October  18,  1993,  a consent decree  was
entered in by the court resolving a complaint filed
against Global Travel, the building owner, Jordon-
Wilcomb Construction, the general contractor; and
Allied Construction, the demolition contractor,  in
October  1992  for violations  of the  asbestos
NESHAP.  The complaint had alleged  violations
of the notice provision of the asbestos  NESHAP
and  three  work  practice requirements during
renovation of a building in Boise, Idaho.  In the
consent decree, the Defendants agreed to pay a
$50,000 penalty and to injunctive relief.

U.S. v. Zemlicka and Davis:   On October 20,
1993, two consent decrees were entered  which
resolved an asbestos NESHAP case in Idaho.  The
defendants were the owner of a building and the
demolition contractor that he hired to demolish the
building.  A preliminary environmental assessment
prepared  for the owner showed the likelihood of
asbestos-containing material in the building, yet he
failed  to point this  out  to  the  demolition
contractor.   The contractor  hired more than a
dozen itinerant workers  who had no respiratory
protection while working.  The penalties paid were
$25,000 (building owner) and $1,000 (contractor),
                                            A-71

-------
       } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
which reflect reductions for inability to pay.  The
injunctive relief is valued at $4,000 to.$6,000.

U.S. v. Martech USA, Hobbs Industries, Chueach
Electric  Association, Inc.:   In  late 1993, the
United  States  filed  a partial  consent decree
resolving its claims against Martech USA in this
asbestos  NESHAP case. Martech had previously
escrowed the $85,000 penalty, which the court
then released to the United States after Martech
filed  for Chapter 11  bankruptcy protection in
November 1993.   The consent  decree settled
claims arising  out  of asbestos  removal work
performed   by   Martech  USA,  Inc.   at  a
decommissioned power plant in Anchorage, Alaska
in 1990.   The first consent decree,  entered in
November 1991, resolved claims against Martech's
co-defendants,  Hobbs  Industries   and Chugach
Electric Association, Inc.

U.S. v. Haeadone Hospitality Co.: On August 13,
1993, the United States filed a complaint against
the Hagadone  Hospitality  Company of Coeur
D'Alene,  Idaho,  alleging  asbestos  NESHAP
violations under the CAA.  At the same time the
US lodged a consent decree in which Hagadone
agreed to  a penalty of $48,000  and injunctive
relief. The violations occurred during the summer
of  1990  when   Hagadone  was  demolishing
buildings to build a large  resort. The consent
decree was entered on November 30,  1993.

CLEAN WATER ACT

Wesley   M.  Sherer:   An  order was issued
requiring removal of fill and bulkhead from the
Stehekin River  at Stehekin, WA.   Fill had been
put in by  an individual for bank protection of
private  property  within  the  boundary  of  the
Stehekin National  Recreation  Area  and in  a
designated National Scenic River.  This settlement
agreement provided for complete  removal of the
fill, restoration of the site, provision of a buffer,
continuing negotiations  for  acquisition  of  a
conservation easement on the property, and an
understanding  by  the  county to  require future
compliance  with   state  shoreline   protection
measures. Fill removal was begun in the spring of
1994 and completed in November.
U.S. v. Steve Burnett and Dean Schroder (W.D.
Wash.):   In  September 1994 a Plea Agreement
and  Judgment was entered  which provided for
establishment of a Trust Agreement.  A Trustee
was  established to receive, hold, administer, and
distribute more than $150,000 "to preserve, protect
and restore wetlands in the Battle Ground area for
the benefit of the community's citizens." The plea
to  the  misdemeanor  charge  resulted   from
investigation  of a citizen complaint of filling of
wetlands adjacent to the Salmon River near Battle
Ground,   WA.     Compliance  was   initially
established with  a  fill  removal  order.   The
Defendants subsequently refilled the same  area,
again without benefit of a  Corps  of Engineers
permit. Additional investigation by the Corps and
EPA resulted in the bringing of criminal charges
which were resolved by the Plea Agreement.

Kenco Marine: An order was issued for removal
of fill material placed in the Duwamish River at
Seattle, WA.   The  violator, Tom  Kent (d/b/a
Kenco Marine), placed fill, including concrete
rubble, in an anadromous fish-bearing river which
is currently the focus  of watershed restoration
efforts.   EPA assumed the lead for enforcement
from  the Corps  of Engineers  and,  following
negotiations and  issuance of a removal order,
established compliance by fill removal and site
restoration  including  revegetation.  Significantly,
the site is adjacent to a coastal America restoration
project which was occurring  simultaneously.

City of  Ocean  Shores, Washington:  At the
request  of the Corps  of Engineers,  the   EPA
assumed  the lead for enforcement against the City
of Ocean Shores for placing  fill  in  interdunal
wetlands adjacent to the Pacific Ocean.  Following
difficult  negotiations,  the  city  removed  the
unauthorized  fill, replanted the site,  and restored
an adjacent site which had long been degraded by
vehicle traffic. The compliance action resulted in
a net gain of  wetlands functions and values.

Rodger Forni:  Individual (d/b/a Lighthouse Inn)
entered a settlement agreement which provided for
creation  and  restoration  of  interdunal wetlands
adjacent  to the Pacific Ocean  at Ocean Shores,
WA.  EPA assumed  the lead for enforcement at
                                             A-72

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
the   request  of   the   Corps   of  Engineers.
Negotiations  coordinated  with  the.  State   of
Washington   resulted  in  wetlands   creation,
restoration (at a 2:1 ratio) and the deeding to the
state  of dunal wetlands and beach  adjacent to a
public access and state park in an accreting coastal
reach.     Educational   signs  indicating   the
significance of the wetlands were also erected by
the violator.

Martin Nygaard:  Repeat violator attempted to
drain approximately 15 acres of freshwater marsh
near Warrenton, OR, by ditching.  EPA entered
into a joint enforcement action with the State of
Oregon Division of State Lands resulting in  the
complete restoration of the wetlands as well as a
state fine.

Rogge Mills:  The mill in eastern Oregon was
responsible   for  unauthorized   placement   of
woodwaste in approximately five acres of wetland
in violation of the CWA  and  two state statutes.
EPA assumed the Federal lead  and in conjunction
with the State  of  Oregon  obtained fill removal
from  most of the wetlands as  well  as mitigation
for remaining fill.

Washington   State   Department   of
Transportation (WSDOT): Unauthorized filling
of several acres of wetland in conjunction with a
major highway project in western Washington led
to the halting of construction (at a cost of several
million dollars) and an agreement by WSDOT to
have middle and upper management undergo 404
training sponsored  by the Corps of Engineers,
EPA  and  the Washington State  Department  of
Ecology.

Northlake Shipyards:  EPA,  DOJ  and the state
negotiated a complex settlement arrangement with
Northlake and the bankruptcy trustee for Unimar
for cleanup of the contaminated site. Under that
arrangement, Northlake entered into  a prospective
purchaser  agreement .with  the state that creates a
trust  fund  to pay  for  remediation of existing
sediment contamination  and resolves Northlake's
liability under the state's  Superfund law.  EPA
agreed to terminate the existing  CWA consent
decree. Northlake will pay up to $1.1 million into
the trust fund.  This  will pay  for  the cleanup
contemplated by the original CWA decree.

City  of Tacoma:   The United  States settled a
CWA judicial action against the City of Tacoma,
WA,    for   secondary   treatment   violations.
Settlement includes payment of a $525,000 penalty
and a SEP  valued at  $100,000 for the sewage
treatment  plant hookup of low  income housing
which currently  discharges untreated wastewater
directly to Commencement Bay.

Arctic Fisheries:  The United States settled this
CWA lawsuit (part of a Region X enforcement
initiative) against the Alaska seafood processor for
$725,000  for the  unlawful  discharge of  fish
wastes.

U.S. v. Stanley C.  Rybachek: The United States
settled the government's long-standing case against
two Alaska placer  miners, for a $15,000 penalty
and   dismissal  of  outstanding  litigation  the
Rybacheks had filed against the government and
individual employees in the Court of Claims and
Alaska  District  Court, requesting  millions  of
dollars in damages.

RCRA

U.S.  v. Robert  and  Geneva Stobaueh  (W.D.
Wash.):  The  State of Alaska notified EPA of a
Chapter  7  bankruptcy  action   filed  by  the
Washington  State   owners  of  two Anchorage
service  stations  with  documented  petroleum
releases. The State requested EPA  assistance in
obtaining  funds  from  the  bankruptcy  estate to
clean  up the sites.   After receiving the Region's
expedited  referral  on  December 10, 1993, DOJ
filed  a protective proof  of claim  with  the
bankruptcy  court  for  the estimated cost  of
investigating and cleaning up the contamination at
the two sites ($427,000 to $779,000).  In March
1994  an  agreed  order was entered  by  the
bankruptcy court placing about $39,477, the funds
remaining   after   payment   of   taxes    and
administration  fees, into an environmental cleanup
trust account to  be used to remove the leaking
tanks  and begin investigation of the  extent of
contamination  and cleanup.
                                             A-73

-------
      ) FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
17.5. v. R,H. Bowles, Inc. and Central Marketing,
Inc. (E.D. Wash.):  Case involved two closed
service stations on the Yakima Indian Reservation
in Toppenish  and  Wapato, WA.   On  May  27,
1994,  EPA sent a referral to  DOJ to file an
objection to the trustee's intent to abandon these
two properties as a part of the liquidation of these
two corporations because petroleum contamination
had been identified at the Toppenish site and the
tanks  had  not been properly closed  at either
facility.  As a result of the objection filed,  the
trustee withdrew his notice of abandonment and is
currently in the process  of selling the properties to
a third party  who has agreed  to  remove  the
abandoned tanks, conduct site assessments, and
undertake remedial action at both properties  as
needed.

Alaska Railroad  Company:   In a settlement
reached between EPA  and the  Alaska Railroad
Company (ARRC)  in April 1994 ARRC agreed to
three Supplemental  Environmental Projects (SEPs),
which  included the following:  1) installation of
three state-of-the-art hazardous waste accumulation
buildings to temporarily store the hazardous waste
and used oil ARRC  generates at  its Anchorage,
Alaska,  repair  and  maintenance  facility;   2)
conducting an audit of  ARRC's waste generation
and management practices and implementing the
findings  of  the   audit;  and  3)  funding  and
sponsoring a series of used oil management and
compliance seminars  in Alaska for the benefit of
similarly-regulated  industries and  the  general
public. These seminars will assist the public and
the regulated community in Alaska to comply with
EPA's newly-promulgated  used  oil  regulations
codified at 40 CFR Part 279. These SEPs were
proposed by ARRC during settlement negotiations.
Implementation of  the SEPs will allow ARRC to
discover  and  implement  changes in  its waste
management practices in order to prevent improper
management of those wastes.  It was  improper
management which led to the violations alleged in
EPA's complaint.   'When  the  complaint  was
originally issued in 1992, EPA proposed penalties
of $1,829,574. The  case was settled for a civil
penalty of $685,999, with $274,400 of the penalty
being  suspended and deferred pending ARRC's
successful completion of the three SEPs mentioned
above. The settlement also requires ARRC to pay
a $411,599 cash penalty, with quarterly payments
over two years, plus interest. This case was one
of the cases filed nationally by EPA as part of the
1992 RCRCA "Illegal operations Initiative."

Boeing  Company:   Seattle,  Washington  and
Portland, Oregon: In January of 1994, the Boeing
Company entered into two separate,  very similar
administrative  orders  on  consent,  pursuant to
Section  3008(h)  of RCRA, to take corrective
action  at its  aircraft  manufacturing/assembly
facilities  in  Seattle and Portland.   The  orders
obligate Boeing  to implement  specified interim
measures and to evaluate and assess opportunities
for   additional   interim  measures   while
implementing  the  orders.   Boeing will also
perform  RCRA   Facility   Investigations  and
Corrective Measures Studies for the facilities, and
following  Final   EPA   Corrective   Action
Decision(s), Boeing will implement  the selected
corrective measures, subject to a right to withdraw
consent  for the implementation of any specific
final corrective measure(s).

U.S. Army, Fort Wainwright, Alaska: On April
29, 1994, Region X issued an  administrative
complaint and  compliance  order  against   the
Department of the Army, Fort Wainwright, Alaska.
The  order  alleges  six  violations  of  RCRA
requirements,  including  illegal    storage   of
hazardous waste  and failure to make hazardous
waste determinations.  Region X and the state of
Alaska   have   tried  through   both   informal
outbriefings  and   through  a  Federal  Facility
Compliance   Agreement   to    address   Fort
Wainwright's failure to achieve  compliance. The
Region decided to use the enhanced enforcement
authority of the Federal Facility Compliance Act
of 1992 to assess a penalty of  $659,450 both to
underscore the significance of the violations and to
force  Fort Wainwright to come into compliance
with RCRA requirements.

U.S. Army, Fort Richardson:   On April  29,
1994, Region X issued an administrative complaint
and compliance order against the U.S. Army, Fort
Richardson, Alaska, for $1,337,332.  In the order,
EPA  alleges twelve  violations  of  the  RCRA
                                            A-74

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
requirements,   including   illegal   storage   of
hazardous waste; failure to make hazardous waste
determinations; inadequate closure,  contingency
and waste  analysis plans; and failure to obtain
detailed physical and chemical analysis. As  with
Fort Wainwright,  Region X and  the State  of
Alaska   have  addressed   Fort   Richardson's
noncompliance over the  past four  years  with
notices  of  noncompliance, informal  and  formal
outbriefings  and  through  a Federal  Facility
Compliance  Agreement.    Because  these  past
efforts have  not been  successful,  Region X is
taking this enforcement  action to  force  Fort
Richardson to come into compliance with RCRA.

CERCLA

Commencement Bay - South Tacoma Channel:
Well 12A, a municipal well in Tacoma, WA, was
contaminated by organic chemicals from property
presently owned by the Time Oil company.

Evidence uncovered in the Time Oil case indicated
that the Boeing Company and the military (Army
and Air Force) were potential generators at the
site.  DOJ filed U.S. v. Boeing Company in 1992;
Boeing  then  countersued based on the possible
military contribution. The parties settled in spring
1994  and  a  consent decree  was  lodged  in
December with the following (terms.  The Boeing
Company will pay EPA $2.3 million »to  settle
claims related to its alleged liability. Boeing has
agreed to drop its claim against the United States
for reimbursement of past and future cleanup costs
which Boeing is  required to pay EPA.   The
military has agreed to pay EPA $7.7 million  to
settle  claims related to their alleged liability.

Bunker Hill:   In a consent decree referred  in
March  1994  and  entered  by  the  court  in
November, EPA settled with six companies who
owned or  operated mines upstream from this
21-square-mile site in Shoshone County,  Idaho..
The site, which  includes  five communities, was
contaminated  by  past  mining  and   smelting
activities.   The respondents  will continue the
residential soil cleanups that were begun several
years  ago under  an Agreement on consent using
removal authorities. The estimated value of the
work to be done by the respondents is $4Q million.
EPA has more recently settled with  other PRPs for
this site, and has undertaken  Fund-lead cleanup
actions at the Bunker Hill smelter complex, for
which the owner-operators  are bankrupt.
                                            A-75

-------
       FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
  •ry
  tnatr
                FEDERAL FACILITIES ENFORCEMENT OFFICE
RCRA/FFCA

RCRA/FFCA   Penalty   Order-Coast  Guard,
Kodiak. Alaska Facility:  On July 14,1994, EPA
Region X issued a complaint against the U.S.
Coast Guard Kodiak Support Center,  Kodiak,
Alaska,  seeking $1,018,552  in  penalties.   The
complaint resulted from two  major violations of
the  RCRA:     failure   to   properly   monitor
groundwater in  an  area where cleaning  solvents
had been dumped on the  ground, and the illegal
storage  of hazardous waste  without a proper
permit from EPA. The complaint was  the first
action brought against a civilian Federal agency
under the Federal Facility Compliance Act of 1992
(FFCA),  an  amendment to RCRA which allows
EPA  to  assess civil penalties against federal
agencies  in  the same way that it does against
private companies.

Presidio of  San Francisco:   Region IX filed a
complaint and citations May 9, 1994, against the
U.S. Army Garrison, Presidio of San Francisco for
violating federal environmental laws and proposed
a penalty of $556,500 for the hazardous  waste
violations.

Besides paying the penalty, the complain  charging
hazardous waste violations required the  Army to
inspect each building on the Presidio for hazardous
wastes and to remove all such  wastes  currently
stored there  by  July 1, 1994.

Schofield  Barracks:    Region   IX   assessed
$543,900 in penalties under the RCRA §3008(a),
April 21, 1994,  against Schofield Barracks, a U.S.
Army facility located in Wahiawa, HI. Schofield
Barracks  is headquarters  for the 25th  Infantry
Division and 45th Support Group.  The facility
operates numerous  motorpools and  maintenance
shops that generate wastes such as waste  paint,
waste solvents,  and contaminated waste oils which
are listed as hazardous waste under RCRA.

Norfolk Naval Shipyard: EPA Region  III issued
RCRA §7003 emergency orders March  25, 1994
(traditionally used in the hazardous/solid waste
area) requiring the Department of the Navy and
the private  operator of the municipal waste
incinerator  at  the Norfolk  Naval  Shipyard  to
address air  emissions.  The order is designed to
address the  dioxin emissions in the short term.

As a result of the Navy's efforts following the
order, a June 1994 stack test indicated that dioxin
emissions have been reduced  by 95 percent from
one of the four units  at  the municipal waste
incinerator.  Region HI and the Navy are moving
to the other three units and hope to accomplish
similar results.

Yorktovm Naval Weapons Station, Yorktown,
Virginia: EPA, the Navy, and the Commonwealth
of Virginia reached settlement on an interagency
agreement (IAG)  for the Naval Weapons Station at
Yorktown, VA.  The Yorktown  Naval Weapons
Station is a 10,624 acre installation  located in
York  and James City  Counties and  the City of
Newport  News.  Hazardous substances and other
contaminants of concern detected among 14 sites
at WPNSTA-Yorktown included arsenic, cadmium,
chlordane,  ethylbenzene, explosives, heptachlor,
hexavalent  chromium,   lead, mercury, PAHS,
PCBS, phenols,  TCE,  TCA,  1,2-DCE, thallium,
toluene, and zinc. EPA conducted an RCRA Solid
Waste Management  Unit Investigation at the
WPNSTA,  and issued a final report  in December
1992.  The final  report identified 94 areas at the
WPNSTA  that  require  additional  investigation
under RCRA.  Of the 94 identified areas, 10 areas
will  be deferred to  the  Virginia Department of
Environmental Quality Underground Storage Tank
(UST) Program. The agreement requires the Navy
to  determine   the   nature  and    extent  of
contamination at the Yorktown  Naval Weapons
Station.  In addition, should  any remedial action
be necessary, the Navy  will perform it.

Naval  Surface  Warfare  Center,   Dahlgren
Division, Dahlgren, Virginia:  EPA  Region III,
the Navy,  and  the  Commonwealth of Virginia
reached settlement on an interagency  agreement
                                            A-76

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
(IAG)  for  the  Naval Surface Warfare  Center,
Dahlgren Division, Dahlgren, VA. The agreement
requires the Navy to determine  the  nature and
extent  of contamination at NSWC-Dahlgren. In
addition, should any remedial action be necessary,
the Navy will perform it.

Fort Dix, New Jersey:  Region II issued a Notice
of Violation July 15,  1994, to Fort Dix, NJ, for a
CWA violation.  The Army violated  the interim
limits on biological oxygen demand contained in
the order on consent EPA-CWA-II-91-95 and the
final limits of the facility's NJPDES permit. Under
the order, the  Army  will be responsible for the
completion  of  an   environmentally  beneficial
project (EBP) to offset the effects of the violation.
The  sum of the EBP  due for the period in
question, January 1994 through March  1994, is
$4,000.
U.S. Naval Station Roosevelt Roads, Ceiba,
Puerto Rico:   EPA settled a dispute  with the
Navy at USNS-Roosevelt Roads in Puerto  Rico.
The  dispute was  over a revised  consent  order
under the NPDES  program for violations of an
existing Federal Facility Compliance Agreement
(FFCA).   The CWA matter in dispute covered
violations of  the  effluent  parameters  of the
facility's  NPDES permit and interim limits  of an
existing FFCA, as well  as  for overflows of the
sewage collection  system. A proposed order was
originally issued on February 12, 1993.  EPA has
issued approximately three  NOVs  to the facility
since 1990 under the CAA and the CWA (SPCC),
and  a Warning Letter pursuant to Subtitle I of
RCRA (UST, all of which have been resolved or
are on track to be  resolved.
                                            A-77

-------
       ) FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                    OFFICE OF REGULATORY ENFORCEMENT
 CLEAN AIR ACT

 U.S. v. Atlantic Richfield Company and Snyder
 Oil  Corporation  CD.  Wyo.):    EPA  settled
 violations of the provisions of Part C-PSD of Air
 Quality PSD of the CAA, at the ARCO Riverton
 (Wyoming) Dome Gas Plant. This consent decree
 provides that the defendants pay a civil penalty of
 $875,000, the  largest CAA settlement in Region
 VHTs  history.

 U.S. v. W.R. Grace Company (D. Mont.): EPA
 resolved an  action  against WR Grace for alleged
 violations of  the  work  practice  standards for
 demolition and renovation activities where the
 building contains asbestos. The alleged violations
 took place during demolition activities at Grace's
 vermiculite  mill in Libby, MT.  The $510,000
 penalty paid by Grace in settlement of this action
 is the  largest paid in  settlement of an Asbestos
 NESHAP  case in  the  Region  and  second
 nationally. In addition to the penalty, Grace also
 agreed to engage in a specific compliance program
 at 29 of its facilities across the nation as part of
 the settlement.

 U.S. v. ICIInternational, Inc.:  An administrative
 settlement agreement was executed by  EPA on
 April 26, 1994 with  the respondent, resolving
 numerous violations of the CAA committed over
 the past  several years.   The  respondent is an
 importer of motor vehicles, who was licensed by
 EPA to convert motor vehicles that do not meet
 Federal emission  requirements  into complying
 vehicles.   The  settlement agreement required that
 the respondent lose its EPA  import license for a
 year, hire an EPA compliance manager, and pay
 $10,000 in civil penalties.  This case was the first
 time that an importer lost its license to import cars
 under EPA's motor vehicle imports  program.

 U.S. v. JBA Motorcars, Inc.  and Dr. Jacob Ben-
Art (S.D. Fla.): On December 15,1993, judgment
 was  entered against the defendant  by the court,
 resolving numerous violations committed over the
past several years. The defendant was an importer
of motor vehicles,  who was licensed by EPA to
convert motor vehicles that do not meet Federal
emission requirements  into complying vehicles.
The court ordered the defendant to pay $196,000
in civil penalties.  This was the  largest penalty
ever assessed under EPA's motor vehicle imports
program.

U.S. v. Daniel Rosendahl (S.D. Tex.): On July
13, 1994,  judgment  was entered against  the
defendant by the court for $120,000. The district
court found the defendant liable for importing 12
disassembled Citroen 2CVs that did meet Federal
motor vehicle emission standards  in violation of
the CAA. Because the defendant had imported the
cars as parts, instead of as whole cars, this case
helped close  a potential  loophole in the CAA
related   to   the   importation  of  incomplete
automobiles.

U.S. v. Ken Ball and Phil McCreery (W.D. Mo.):
A consent decree was formally entered October
17, 1994. Ball, a scrap dealer, had sold McCreery,
a muffler shop owner, used, untested automobile
catalytic converters to be used as replacement parts
on vehicles needing new converters, in violation of
section 203 of the  CAA.   An improper or non-
functioning catalytic converter can result in 400 to
800 greater greater emissions  than would occur
from the same vehicle with a proper converter. A
complaint had been filed on September 29, 1993,
and alleged up  to 39  separate violations of the
tampering prohibition of section 203 of the Act.
Both Defendants made a  showing of financial
hardship. Based on that, the United States settled
with Ball for  $12,500 and with  McCreery  for
$10,000.

TSCA

Town of Wallingford, Connecticut: Wallingford
will test  all town-owned transformers for PCBs
and, at a cost of over a million dollars over the
next 3 years, will remove all that were previously
improperly  disposed and pay  a cash penalty of
                                            A-78

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
$40,050,  pursuant  to  this TSCA  settlement
negotiated by Tom Olivier.

Cressona Aluminum  Company PCS Cleanup:
The United States settled a judicial case against
the Cressona Aluminum Company addressing the
improper use, storage and disposal of PCBs at the
company's facility in  Cressona, PA.   Cressona
manufactures  various extruded aluminum parts at
its 115 acre facility on the bank of the west branch
of the Schuylkill River and high concentrations of
PCBs were previously used in the company's
hydraulic equipment.

EPA's complaint  sought  injunctive relief under
TSCA §§ 6 & 7 to address PCBs that presented an
imminent   hazard.    The  settlement  requires
Cressona to clean up the PCB contamination at the
facility.  The company will decontaminate all plant
equipment, including  the  hydraulic and  waste
water treatment systems, and  where  necessary,
remove  concrete floors up to  1.5" depth.  Plant
outfalls   will  undergo   a  Toxics  Reduction
Evaluation to eliminate PCB discharge  into the
Schuylkill River.  All PCB-contaminated debris
will be disposed of in a proper manner.

USS Cabot/Dedalo:  EPA learned on  June 8,
1994 that the  owners of the USS Cabot/Dedalo, a
retired Navy warship, proposed to export  the ship,
which contains high levels of PCBs in its wiring.
The presence of PCBs at levels over 50 ppb makes
the ship subject to TSCA §6(e).

On June  27,  1994,  EPA  learned  that  the
Foundation had a contract to sell the vessel for
scrap and salvage to a company in the Republic of
India and had requested export clearance  from the
U.S.  Customs  Service.   EPA  requested that
Customs deny clearance until the Foundation could
comply  with  TSCA §6(e).  In response, on July
11, 1994, the Foundation sought a TRO in the
New  Orleans U.S.  District Court,  alleging that
EPA  is without  statutory  or other authority to
instruct  Customs  to restrict the export of this
vessel.  EPA requested and DOJ  has  filed  an
action seeking a TRO to halt the export.  DOJ has
submitted a  legal  brief in opposition to  the
Foundation's motion  as well as a complaint  on
behalf of EPA.

Port of New Orleans: The Port of New Orleans
will  remove and dispose of PCB transformers,
capacitors and contaminated pads as part of a SEP
under the terms of a September 12, 1994, CACO
which  EPA  negotiated  with  the   Board  of
Commissioners of the Port of New Orleans for
violations of the TSCA PCB requirements.  The
Port also will pay a civil penalty of $8,520.

Sunshine Mining Company:  EPA cited Sunshine
Mining Company for  improper disposal of PCBs
both on the surface and underground at the Eureka
Mine in Utah.  Alleging 16 TSCA PCB  counts,
the proposed penalty is $109,500.

Imperial Holly Corporation:   Imperial Holly
Corporation will pay a $7,490 penalty and perform
a  $224,700   SEP  involving   removal  and
replacement  of PCB  equipment pursuant  to  a
settlement with EPA of a TSCA case involving for
PCB registration, record keeping, inspection and
disposal violations.

EPCRA

General  Chemical Corporation:  On July 26,
1993, there was a release of approximately 7800
pounds of sulfur trioxide, an EPCRA extremely
hazardous substance,  from a railroad tank car
located  at  the General  Chemical  facility  in
Richmond,  CA—an  area  where environmental
equity is of critical concern.

On  September  29,   1993,  EPA  issued  an
administrative complaint to the General Chemical
Corporation  (GCC) with  proposed penalties  of
$65,625 for violations of CERCLA Section 103
and  EPCRA  Section 304(a) and (c).   These
violations involved  GCC's failure to immediately
notify the NRC and the SERC of the release and,
its failure to provide  adequate written follow-up
reports to the SERC  as soon as  practicable.  On
February 11, 1994, only 61A months from the date
of the release event, EPA closed the case  with an
executed consent agreement and  consent order
(CACO).  The CACO required GCC to pay 100
                                            A-79

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
percent of the $65,625 penalty proposed  in the
complaint and required them to certify, that it had
come into compliance with CERCLA Section 103
and all Sections of EPCRA.

Alaska Pulp Corporation:  In Region X's first
multimedia settlement, reached on February 17,
1994, Alaska Pulp  Corporation (APC) will  pay
cash penalties  of $64,600 for TSCA violations,
$45,650  for TRI violations,  and  $27,068  for
RCRA violations.  The settlement also requires
APC to spend at least $129,200 to dispose of PCB
transformers at its  Sitka facility;  to spend  a
minimum of $83,000 to implement  a "Nutrient
Pollution Prevention Project" and a "Caustic Wash
Reuse Project"  at its Sitka facility; and to pay up
to an additional $10,062  in cash if  it does  not
expend  at  least $40,250  more on the Nutrient
Pollution Prevention  and Caustic  Wash  Reuse
Projects (over and above the initial $83,000).

Trail Wagons:  EPA inspected Trail Wagons, a
Yakima, WA, van conversion operation, and found
that it had  used 1,1,1-trichloroethane  and styrene
in  amounts  exceeding  the   Toxics  Release
Inventory reporting  thresholds.   EPA filed  an
administrative complaint on October 22, 1992 for
$51,000.   The company submitted  sales data
supporting  penalty reduction because of inability
to pay, and proposed two SEPs which consisted of
a solvent recycling unit and high efficiency spray
equipment, at a total cost of $7,872, resulting in a
final penalty of $7,314 which was paid in cash
pursuant to a settlement entered on January 24,
1994.

Northwest Castings: Northwest Castings, Seattle,
WA,  a  manufacturer  of steel castings  which
contain  chromium,  nickel and  manganese, was
inspected by the EPA  on June 10,  1993, The
inspection revealed that the company exceeded the
TRI  reporting  threshold  for  manganese.   An
administrative  complaint  seeking  penalties  of
$14,200 was issued.  After settlement negotiations,
the company was assessed a penalty of $9,940, of
which $4,970, was paid in cash, and the balance
was  deferred  as  credit for an SEP involving
installation of a baghouse to reduce air particulate
emissions.
FIFRA

Pinnacle Agricultural Technologies:  A tip and
complaint led EPA to ask  the  Arizona  State
Department of Agriculture to inspect two facilities
suspected of  distributing  unregistered growth
regulator  products.     Pinnacle   Agricultural
Technologies was  charged  with three counts of
distributing the unregistered product "Boost" to
three companies in Mexico without obtaining a
foreign  purchaser  acknowledgement.     The
proposed civil penalty is $13,500.  Westmark Ag
Group  was   charged  with  distributing  the
unregistered product  "BIOBOOST"  within the
United States and  to  Mexico without a foreign
purchaser acknowledgement.    The   proposed
penalty for the two violations of §12(a)(l)(A) is
$7,000.

Accuventure.  Inc.;    Criminal  and  Civil
Enforcement  Coordination:    EPA issued  an
administrative  complaint r*n  October  9,  1992,
against Accuventure, Inc.,  alleging 13 violations
for distribution of unregistered pesticides and one
violation for an unregistered establishment.  After
Accuventure failed  to respond to EPA's motion for
accelerated decision on the  issues of liability and
penalty, or to Administrative Law Judge  Frank
Vanderhay den's    order   to   show   cause,
Vanderhayden issued  an order granting EPA's
motion for accelerated decision with regard to both
liability and penalty of $70,000.   The  penalty,
which was due August 3, 1994, has not been paid
and  EPA is filing  a  collection action  with the
Attorney General.

Argent   Chemical   Laboratories,   Inc.:
Negotiations conducted during FY94 have  led to
settlement of  EPA's  July 8,  1993  complaint
against Argent Chemical Laboratories, Inc. for sale
of unregistered pesticides, sale of pesticides  which
compositions differed from those described  on the
product's  Confidential  Statement  of  Formula,
export of products without  required  bilingual
labeling,  and pesticide misuse.  The company has
agreed to pay a penalty of 50,000,  which was
reduced by ability-to-pay considerations, for 21
violations.
                                             A-80

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
MULTIMEDIA CASES

Allied Tube & Conduit: On September 30, 1994,
EPA issued a multimedia administrative complaint
against  Allied  Tube  &  Conduit  for  alleged
violations of EPCRA and RCRA.  In the EPCRA
inspection, the  company  failed to  report toxic
chemical releases to the air in 1989.  The RCRA
inspection revealed numerous violations, including
failure to properly mark containers, failure to
record weekly  inspections, failure  to  conduct
personnel training, failure  to adequately maintain
fire  protection  equipment,  failure  to maintain
adequate aisle space, failure to maintain closure of
hazardous waste containers, and failure to properly
prepare  several   hazardous  waste  manifests.
Corrections  of these multiple statutory violations
will provide benefits  to  the public  health  and
environment.

U.S. v. Columbus Solid Waste  Reduction Plant:
In response to  an EPA administrative order and
community  concerns about dioxin emissions  the
city  of  Columbus agreed to  shut  down  the
Columbus  Solid  Waste  Reduction  Plant  in
Columbus, OH, an electricity generating facility
for the city which operates six refuse and coal-
fired boilers. EPA interest began after numerous
citizen complaints about air emissions.   EPA
negotiated an AOC under RCRA §7003 to require
the facility to design systems to achieve the lowest
dioxin emissions  due  to  be required by EPA's
municipal combustion  regulations.

Subsequently, several  circumstances arose which
affected  the proposed AOC.  First, citizens made
numerous comments about the AOC at a public
meeting.  Second, a meeting was  held  between
EPA and the Agency for Toxic Substances and
Disease Registry on June 23,  1994,  to  discuss
conducting human health evaluations of the area
surrounding the  facility.   Third, two  recent
Supreme Court decisions may result in  the facility
greatly  changing  its  operations.    Then,  on
September  9,  1994,  EPA  issued a  unilateral
administrative  order pursuant  to RCRA  §7003
requiring essentially the same injunctive relief as
the AOC.   In  response,  the  city  decided to
authorize closure of the facility.

U.S. v. Southern Pacific:   A second consent
decree resulted in a multimedia settlement that will
resolve the liability of a number of parties under
a number of statutes (including Superfund, RCRA,
CWA, FIFRA, and others) arising out of the 1991
train derailment  and spill of metam sodium into
the Sacramento  River in California.   The spill
created a toxic  plume which killed  aquatic  life
along a long stretch of the river.

U.S. v. Texas Eastern (S.D.. Tex.): On June 16,
1994,  the  Second Modification  to  the  Texas
Eastern Federal consent decree was lodged by the
court.  The modification incorporates the PCB  and
mercury cleanup  provisions of the  settlement
negotiated  between   Texas Eastern  and  the
Commonwealth  of Pennsylvania into  the federal
decree and also allows the Agency to consider off-
site remediation workplans on a case-by-case basis
for all Texas Eastern sites located in 14 states. To
date,  18   compressor station  sites   have been
remediated pursuant to the federal consent decree.
Six additional  compressor  station sites  will be
remediated in   1994,  as well  as 36 Off-Site
Equipment Area Locations in Pennsylvania.
                                              A-81

-------
         FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                       OFFICE OF CRIMINAL ENFORCEMENT
 U.S. v. Hartford Associates (D. Md.):  The court
 sentenced  Hartford  Associates,  a New  Jersey
 partnership engaged in property development, on
 October 7, 1993, to pay a $100,000 fine  and to
 grant a conservation easement on more than 100
 acres  of  wetlands  for  violating  the   CWA.
 Hartford, a limited partnership based in Berlin, NJ,
 pled guilty to one count of negligently discharging
 dredged or fill  material without a permit in
 wetlands located on a 375-acre tract of land the
 partnership owns near Elkton, Maryland.   Under
 the sentence imposed by Judge  Nickerson, the
 partnership must pay one third of the $100,000
 fine immediately and the remaining portion over a
 2-year period of probation.  The conservation
 easement must become effective within 30 days.
 The easement will effectively  restrict  further
 development of a large portion of the property.

 U.S. v. Penn Hills (W.D. Penn.):  Rejecting pleas
 of municipal poverty and  taxpayer  hardship,  a
 federal judge, on September 8,1994, sentenced the
 Municipality  of Penn Hills, Allegheny County,
 PA, to 5 years probation and a $150,000 fine for
 illegally  disposing of sewage sludge and other
 pollutants  from  three  of its  sewage  treatment
 plants  in violation of its NPDES  permit and the
 CWA. On July 8, 1994, Penn Hills pled guilty to
 a three count information charging it with failing
 to remove  and knowingly illegally disposing of
 sewage sludge and other pollutants in violation of
 the CWA from the three plants.

 U.S. v.  Reillv:   Defendant  William P. Reilly,  a
 shipping company executive, was charged with  a
 violation of the Ocean Dumping Act, 33  U.S.C.
 §1411 (a),  for  the  knowing   discharge  of
 approximately  11,000 tons of incinerator ash from
 the ship  Khian Sea,  a bulk  cargo ship, into the
Atlantic  and  Indian e Oceans.   On appeal,  the
convictions of Reilly and his codefendant, John
Patrick Dowd, which included false  declaration
charges under 18 U.S.C. §1623(a)  were affirmed.
Issues relating to defendant Reilly's knowledge of
the Ocean  Dumping Act's  permit requirements
were not appealed.
 U.S.  v. Wietzenhoff:   Michael Weitzenhoff and
 Thomas Mariani appealed their felony convictions
 for conspiracy and  knowing violations of the
 CWA.  The decision by the U.S. Court of Appeals
 for the Ninth Circuit presents a highly favorable
 precedent concerning the knowledge requirements
 of the CWA's  criminal  provisions.   A jury
 convicted the two plant managers, Weitzenhoff
 and Mariani, of  six felony  counts.  The judge
 sentenced Weitzenhoff to 21  months and Mariani
 to 33 months in prison. On August 3,  1993, the
 Ninth Circuit affirmed the convictions.  The Court
 agreed  with  the  District Court  that the felony
 provisions of the  CWA do not require proof that
 the defendants knew that their conduct violated the
 NPDES permit.   The defendants then requested
 that the Ninth Circuit rehear the case en_ bane. On
 August 8,  1994, the  Ninth  Circuit  denied the
 request and slightly modified its original opinion.
 The Supreme Court denied the defendant writ of
 certiorari on January 23, 1995.

 U.S. v.  Lauehlin, 10 F.3rd 961 (2d Cir. 1993).
 cert,  denied,  114  S.Ct.  1649  (1994):   The
 defendant,  an owner  of a railroad tie treating
 business, was convicted after trial for knowingly
 disposing of hazardous waste without a permit in
 violation of RCRA and for failing to report the
 release  of a hazardous substance in violation  of
 CERCLA.   The  court  held that the RCRA
 provision  prohibiting   knowing  disposal  of a
 hazardous waste without a permit, 42  U.S.C. §
 6928(d)(2)(A), requires only that a defendant have
 a general  awareness that he  is performing acts
 proscribed by the statute, and that the trial court
 did not err in refusing to charge the jury that the
government had to prove the defendant knew that
the waste  was identified or listed under RCRA.
The   court  further  held  that  under  section
6928(d)(2)(A), the government does not have  to
prove that the defendant was aware  of the lack of
a  permit  to   dispose of   hazardous  waste.
Consistent with the RCRA ruling the court also
found that section 9603 (a)  of CERCLA does not
require  proof  of  knowledge  of  regulatory
requirements, but only that the defendant be aware
                                            A-82

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT l^w^l
of his act.  Thus, the trial court did not err when
it failed to instruct the jury that the government
must prove that the defendant knew the release of
the hazardous substance violated the provisions of
CERCLA.

U.S.  v. Advance Plating Works, Inc., et al. (S.D.
Ind.):     Advance   Plating  Works,   Inc.,   an
electroplating and metal finishing shop located in
Indianapolis,  IN, was fined, and its owner and
president,  Eugene Doughty, was sentenced to jail
and fines, on October  8, 1993.  The defendants
engaged in the tampering of samples and illegal
discharges   of   company   wastes   into   the
Indianapolis  sewer  system  under  the  CWA.
Doughty sought to conceal his CWA violations by
tampering  with  discharge samples  which were
being taken in  order to determine compliance.
Advance Plating also illegally stored and disposed
of hazardous  wastes at  its facilities without a
permit to  do so. Doughty was  sentenced to  12
months in jail, and ordered to pay a fine of $3,000
and restitution of $5,165.   Advance Plating was
sentenced to 3 years probation, and was ordered to
pay a fine of $200,000 with $100,000 suspended.

U.S.  v.  Carlo  Area  and Automatic  Plating
Company,  Inc.  (D. Conn.):    Carlo Arco was
sentenced to 15 months in prison for attempting to
cover up the release of sodium cyanide from the
company's Bridgeport, CT, facility. The June 24,
1994, sentencing followed  the March 16, 1994,
conviction of Arco  and Automatic Plating Co.,
Inc. on one count of failing to report the release of
a hazardous substance under the CERCLA and one
count of knowingly  introducing pollutants to the
Bridgeport sewer system in violation of federal
CWA categorical pretreatment standards.

U.S. v.AT&T and Harry J. Krins (E.D. Penn.):
Harry J. Kring was sentenced to 3 years probation,
6 months  of home confinement, and a $5,000 fine
stemming from his plea of guilty to one count of
negligent  violation of the CWA and one count of
making false statements  to  the EPA  and  the
Pennsylvania   Department   of  Environmental
Resources.  Kring pleaded guilty to these  charges
on March 3, 1994.   In a related  case, AT&T
pleaded guilty to a one count information charging
the  company   with   negligently  discharging
pollutants in  violation  of  its NPDES  permit
limitations.  The company was fined $175,000.
Although  Kring  knew that  AT&T's  internal
laboratory conducted monitoring in addition to the
outside laboratory, he failed to  incorporate all the
analytical information and the DMRs. Had Kring
reported all the analytical results, the effluent from
the air stripping tower would have been reported
in violation of the effluent limitations on numerous
occasions.

U.S. v.  Richard Vernon  Bates, et  al.  (C.D.
Calif.):  On April 11, 1994, Richard Vernon Bates
was sentenced for  knowing  violations  of  the
CWA's  Pretreatment Standards.  Bates,  former
vice president and general manager  of Travelin'
West Textiles (also known  as Melody Knitting
Mills, Inc.), Simi Valley, CA, was sentenced to 5
months   incarceration,   100  hours   community
service,  and 3 years probation.  Kenneth Allen
Baber, former plant  engineer, was sentenced to 3
months  incarceration, 3 years probation and  100
hours community service.  The company received
a $45,000 fine. Bates, Baber, and the corporation
had pleaded guilty to two counts each of violating
pretreatment standards in the discharge of acidic
wastewater into the Simi Valley Sanitation District
POTW.

U.S. v.  Giacomo Catucci (D. R.I.):   Giacomo
Catucci,  former  president of Post-Tron,  Inc., a
computer software  company,  was sentenced  on
February 15, 1994, to 27 months in prison for the
unlawful  disposal of polychlorinated biphenols
(PCBs)  and failing to  report  the release of a
hazardous substance into the environment. Catucci
was convicted on October 22, 1993, after a 2-week
trial for  illegal  disposal  of  toxics (PCBs)  in
violation of the  TSCA and failing to report  the
release  of a  reportable  quantity of a hazardous
substance in violation of CERCLA. The violations
occurred  after   Catucci   gave   the   workers
permission  to  scrap  two  PCB  transformers,
knowing that the transformers contained PCBs. At
sentencing, Senior District Court Judge Raymond
Pettine  enhanced the penalty  under  sentencing
guidelines because substantial  clean  up costs had
                                             A-83

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
been incurred by the government as a result of the
illegal acts.

U.S. v. Larry A.  Christopherson (E.D. Wise.):
On May 3, 1994, Larry Christopherson, the former
owner of  Nardi  Electric Company, an electric
contracting firm in Milwaukee, WI, was sentenced
to 3 years probation and 100 hours of community
service. Nardi Electric shut its doors in the 1980s
leaving behind 17 barrels of PCBs  and ignitable
hazardous  waste, principally solvents.  When the
new owner of the property objected to the waste
left behind,  Larry  Christopherson  loaded the
barrels onto  a  trailer  and  abandoned  it  on
neighboring property.  Christopherson had been
charged with and pleaded guilty in January 1994
to the illegal storage and disposal of hazardous
waste, including PCBs and  characteristic waste,
under the RCRA and for violations of the TSCA.

U.S. v. Craven Laboratories, Inc.,  et al. (W.D.
Texas):  Don Craven and his company pleaded
guilty  on December 1, 1993, to various charges
including   FIFRA misdemeanors  and  criminal
conspiracy.  Dale Harris and  Donald Hamerly
together with twelve other defendants pleaded
guilty  to similar charges.  Craven, who was the
owner of the laboratory, directed his employees to
use  testing  short  cuts   that  resulted  in  the
production of false data.  This data was used for
pesticide residue studies,  which in turn was used
for pesticide reregistration. Numerous employees
knowingly  followed Craven's  instructions (and
were often paid  bonuses for  doing  so),  and
understood that the data was false and misleading.
Craven was sentenced to a maximum 60 months
imprisonment and, along  with the company, paid
$30 million in fines  and restitution.  Fourteen
employees  received  sentences  ranging  from
imprisonment  to probation  and fines totaling
$250,000.

U.S. v. Dean Foods Company and Winfred Smith
(W.D. Kv.):  In July  1992, a biologist from the
Kentucky   Department  of  Fish and   Wildlife
investigated a massive fish kill in Beargrass Creek
located in  Louisville.  A  3.5 mile trail of dead
fish, crayfish, algae and other aquatic life led to a
pipe entering an unnamed tributary  of Beargrass
Creek from a facility operated by the Dean Foods
Company,  a  manufacturer and  distributor of
wholesale  and  retail  foods.    The   Kentucky
Department of Fish and Wildlife estimated the fish
kill  at  approximately  15,000.   As a result of
investigations   and  prosecutions  for   illegal
discharges  in violation  of the CWA, Dean Foods
Company was convicted on December 30, 1993,
on one count of negligently discharging pollutants
into navigable waters of the United States without
a permit in violation of the CWA.

U.S. v. Doyle Crews, (N.D. Tex.):  Doyle Crews,
the former President and owner of Crews Plating,
Inc.,  located in  Dallas, TX, was  sentenced on
August  3,  1994, for a criminal violation  of the
CWA. Crews was sentenced to 5 years probation
and  6 months  of  home  confinement  after  he
pleaded guilty to illegally  discharging untreated
chromium wastes into  the  Dallas sewer system.
The Judge declined to impose a fine or prison time
against  Crews,  but  instead   imposed  special
condition of probation that requires Crews to pay
the total costs of the clean-up of the electroplating
facility pursuant to an EPA approved plan.

U.S. v. Charles A. Eidson and  Sandra A. Eidson
(M.D. Fla.):  Sandra Eidson former owner and
officer of  Cherokee Oil  Company,  Ltd., was
sentenced on April 27,  1994, to serve 37 months
in prison and her husband, Charles Eidson, was
sentenced on March 11, 1994 to serve 70 months
in prison for federal  crimes  committed while
operating an oil recycling business. A Florida jury
had previously convicted the Eidsons of one count
of knowingly discharging used oil into  waters of
the United States without a permit, a violation of
the CWA and of three counts of mail fraud. The
Eidson's operated a oil recycling and waste water
disposal business in Tampa, FL. An investigation
revealed that the company represented  to clients
that  it would dispose of the wastes in a lawful
manner. However, they instead illegally disposed
of the wastes into storm sewers. They concealed
their  illegal  practices by  falsifying  business
records. Samples taken in and  around the facility
showed significant contamination of the area with
petroleum by-products.
                                             A-84

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
U.S. v.  Cherokee Resources, Inc., et al. (W.D.
N.C.):  On June 29, 1994, following  an  8-day
trial, a jury convicted Cherokee Resources, Inc.
(Cherokee) and two corporate executives,  Keith
Eidson  and Gabe  Hartsell, on five  counts  of
illegally discharging wastewater into the municipal
sewer system and one count of criminal conspiracy
to violate the CWA.

U.S.  v.  Garlick  Helicopter, Inc. (D.  Mont.):
Garlick  Helicopter, Inc.  (GHI),  a  Montana
corporation,  with  large  federal  government
contracts and one of the largest employers in the
Bitterroot Valley  of Montana, pleaded guilty
January 13,  1994, to illegal storage of hazardous
waste in violation of the RCRA.  GHI is owned by
Ron Dean Garlick, who entered the plea on behalf
of  the  company.    From approximately  1982
through 1992,  GHI  generated hazardous waste in
connection with  its  airplane and helicopter paint
and repair business.

U.S. v,  Gaston (D. Kan.):  Donald Gaston, the
Highway Administrator for Montgomery County,
KS, pleaded guilty to a felony CERCLA charge on
July 21, 1994.  The plea was the result  of an
Indictment returned by a Federal Grand Jury on
March 9, 1994, which charged Gaston with three
RCRA  felony violations  and  one  CERCLA
violation. Sometime after he became the County
Highway  Administrator,  Gaston  ordered  the
employees of both the county road crew and the
county bridge crew to haul 11 drums of hazardous
waste to a closed Montgomery County Landfill
where trenches were dug and the drums buried
with the use of a county backhoe.

U.S. v. Hedse,  (S.D. Ohio);  State of Ohio v.
Hedge  and  City   Bumper  Exchange,  Inc.,
(Hamilton County Court of Common Pleas):
Roland   Hedge,   the  owner of City  Bumper
Exchange,  Inc.  (City  Bumper),  an abandoned
electroplating  facility  in Cincinnati,  OH, was
sentenced by Federal and State courts to a total of
24 months and a $25,000 fine for violations of
CERCLA, and the State of Ohio's hazardous waste
act.   City  Bumper, although defunct,  was also
sentenced in the State  court  to pay  a fine  of
$25,000 for violating the State's hazardous waste
act.   Hedge abandoned  the  facility with  over
27,000 gallons of hazardous substances left on the
site.  Clean-up of the site pursuant to action by
EPA cost the Federal Government $875,000.

U.S. v. Hofele. (W.D. Mo.):  The owner/manager
of a Missouri car repair shop entered a guilty plea
on May 11, 1994, for knowingly releasing freon
(which contains CFCs) while servicing automobile
air  conditioners at his business in Chesterfield,
MO.  As many as 60 automobiles were serviced
by Hofele between January 1992 and July  1993.
Hofele entered a guilty  plea on one count of
violating the CAA, 42 U.S.C. §7671h, in the first
criminal prosecution involving the January  1992,
CAA requirements that repair shops use  freon
recycling  equipment.   The  requirements  also
mandate that employees be trained and certified in
the use of this equipment before servicing motor
vehicle air conditioners.

U.S. v. Robert H. Hopkins (D. Conn.):  On July
20,  1994,  Robert  H.  Hopkins,  former  Vice
President of Manufacturing at Spirol International
Corporation in Killingly, CT, was sentenced to
serve 21 months in prison and to pay a $7,500
fine for tampering  with  wastewater  samples
required under the CWA.  In September  1990,
Hopkins directed and conspired  with others to
filter, dilute, and selectively collect samples of the
discharge  from  Spirol's  wastewater  treatment
system. Hopkins then submitted  false reports to
the  Connecticut  Department of  Protection to
conceal Spiral's discharge of heavy metal bearing
wastewaters to the Five  Mile River—a heavily
stocked trout stream in northeastern Connecticut.

U.S.  v. George Frederick  Heidgerken  (W.D.
Wash.):   George F. Heidgerken, the owner of
several companies   including  GFH   Timber
Products, was sentenced on December 3, 1993, to
5  months in prison, followed by  4 months of
electronically  monitored   home  detention.
Heidgerken  was also sentenced to 3  years of
supervised release subsequent to his incarceration
and ordered  to pay a $4,000 fine.  Heidgerken
pleaded  guilty  to   violation  of the  RCRA.
Heidgerken's offenses involved approximately 260
drums of ignitable lacquers and paints.  The 55-
                                             A-85

-------
      } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
gallon drums were stored  in warehouses  and
outdoors in Detroit, OR, where they were exposed
to the elements in an area of pristine rural land
and natural hot springs.

U.S. v. Comer's Diesel and Electric Company (D.
Mont):  Comer's Diesel  and Electric Co., with
automotive and truck repair facilities located in
Belgrade, Great Falls, and  Missoula, MT, was
sentenced on March 24,  1994, following a plea of
guilty to a one-count of the unlawful transportation
of a hazardous waste in violation of the RCRA, 42
U.S.C. §6228(d)(l). The company was placed on
supervised probation for a period of 2 years and
fined  $100,000  to  $50,000  of  which  was
suspended in recognition of remediation conducted
at its Belgrade facility.

U.S. v. Jay Jurek (W.D. Wash.):   On  July 12,
1994,  Jay  Jurek,  a production  manager for
Boomsnub Corporation and Pacific  Northwest
Plating Company (Boomsnub), entered a plea of
guilty to a federal criminal information charging
him  with  attempting  to  harass a  witness  to
dissuade him from assisting a criminal prosecution
of Boomsnub. On June  6, 1994,  EPA's Criminal
Investigation Division Special Agents  arrested
Jurek, without incident, at the Boomsnub facility
in Vancouver, WA, on a warrant issued by a U.S.
Magistrate. On June 2, 1994, Jurek had threatened
bodily harm to a person for allegedly providing
information  to EPA/CID in the course of EPA's
criminal investigation into activities of Boomsnub.
The person threatened had been named as a source
of information for the EPA by a local newspaper.

U.S. v. MOR, Inc. (S.D.  Fla.):  On May 19, 1994,
MOR,  Inc., pleaded guilty  to  a  one-count
information charging it with knowingly violating
the CAA. In March and April of 1991, extensive
renovations were made to the Sea Isle Hotel (now
known as the Miami Beach  Ocean Resort) in
Miami Beach,  FL,  including the  stripping  of
thermal insulation  materials containing friable
asbestos from piping and the removal of facility
components, such as boilers, that  were encased in
friable asbestos.  The removal  was accomplished
through the use of itinerant workers who were not
supervised by a licensed asbestos contractor nor
provided with respirators or protective clothing.
None of the work practice standards for asbestos
removal were followed and clouds of asbestos
were released as a result of the operation.  The
unsealed asbestos was transported to a solid waste
landfill in ordinary trash dumpsters.

U.S. v. Francis Morgan, et al. (D. Haw.):  On
May 31, 1994, Francis  Morgan was  sentenced to
1 year unsupervised probation and a $6,000 fine
for three  counts  of negligently  discharging  a
pollutant into the Pacific Ocean in violation of the
CWA. The defendants  had been managers at the
Hamakua  Sugar Company  from  1988 to 1990.
The sugar company mill had an NPDES permit to
discharge treated waste  water from the processing
of sugar cane.  The  indictment charged that the
defendants  conspired   to  violate  the  CWA,
manipulated the treatment system to  misrepresent
discharges  during regulatory  inspections, and
falsified  required  discharge monitoring  reports
with regard to exceedences and other violations of
CWA regulations  and  permit requirements.   In
addition, the defendants had been charged with
fourteen  counts of operating  a  secret by-pass
which discharged  untreated waste water directly
into a gulch leading to  the Pacific Ocean.  These
discharges of total suspended solids contributed to
the degradation  of coral  communities off  the
Hamakua Coast of the island of Hawaii.

U.S. v. M. Tyronne  Morgan and Meydenbauer
Development Corp. (E. D.  Wash.):   On  July 6,
1994, a jury  returned  guilty verdicts for both
Marvel  Tyronne Morgan,  the President  of  the
Meydenbauer   Development  Co.,   and   the
Meydenbauer Development Corporation (MDC).
Morgan and MDC were convicted under the CAA
for unlawful removal of asbestos in connection
with  the  demolition/renovation  of the  former
Deaconess  Hospital.  The defendants  were also
convicted  of  failing to report  the release  of
asbestos and PCBs.  Bradley Brown, one of the
defendants  in this, was  sentenced on January 28,
1994, to incarceration for a year and a $5,000 fine
following his guilty plea. The case originated in
September of 1992 when CID received reports of
allegedly  unlawful  removal  and  disposal  of
asbestos, and the alleged unlawful disposal  of PCB
                                             A-86

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
fluid  and PCB  transformers  from  the  former
Deaconess Hospital located in Wenatchee, WA.

U.S, v. Bob Murphy, et al (D. Nev.): This case
involved  the  removal  of asbestos-containing
material from  approximately 70  apartments in a
413-unit complex. Defendants in this case were the
owner of the apartment complex, Robert Murphy,
and the former manager of the apartments, Thomas
Devins. Devins hired casual laborers for asbestos
removal  without following the  required work
practice standards.   After asbestos  debris was
deposited in trash dumpsters at  the complex, other
residents, including small children, were exposed
to airborne asbestos fibers. Murphy was convicted
on  February   3,  1994,  of knowingly violating
asbestos  work practice standards, of failing to
report the release of asbestos and concealing the
violations from local authorities  under the CAA
and failing to report the release of a hazardous
substance in  violation  of CERCLA.    After
pleading guilty  to  violations  of the CAA  and
conspiracy, Devins was sentenced to  32  months
incarceration on  October 25, 1993.

U.S.  v. Norwood  Industries.  Inc., et al. (E.D.
Penn.):  Norwood Industries, Inc.  a southeastern
Pennsylvania  adhesive  tape  manufacturer  was
fined  $100,000  (suspended)  and  ordered  to
perform  beneficial  environmental  projects after
pleading guilty to criminal violations  of the CAA
VOC regulations.   The company was sentenced
March 1, 1994, in federal court in Philadelphia for
failing  to install  control  technology   or  use
compliant coating at its Malvern, PA, plant from
July of 1989 to August of 1990. The plant's VOC
emissions are  regulated by the  Commonwealth of
Pennsylvania's SIP.

The Court order included  requirements that the
company  develop  a  corporate  environmental
regulatory  compliance   program,   including
development   of an environmental  compliance
manual within 90 days  of sentencing and spend at
least  $30,000  annually during the company's 5-
year  period  of  probation   on  research  and
development  to  replace solvent-based  coatings
with water-based materials.
U.S. v.  PEA. Inc.  (D.  Colo.):   OEA, which
manufactures 60 percent  of the world supply of
explosive air bag initiators, pleaded guilty on April
28, 1994, to six felony violations of the RCRA—
illegal transportation of hazardous waste, illegal
treatment of hazardous waste  without  a permit,
illegal disposal, and illegal storage of hazardous
wastes.  The company engaged in the practice of
on-site  detonation  of excess  waste  materials
consisting  of ignitable  solvents  and  reactive
explosives used in the company's manufacturing
process. During the manufacturing process, waste
hexane  and  acetone  mixed  with   explosive
zirconium  potassium  perchlorate  (ZPP)  was
generated,  in  addition   to   flawed  initiators
containing ZPP. These wastes were the subject of
the charged violations. In three separate incidents
four employees were injured, one with serious
burns, during the disposal activities.

U.S. v.  Palm Beach Cruises  (S.D. Fla.):  Palm
Beach Cruises, the corporate owner of the cruise
ship MV Viking Princess, was  sentenced  on
August  30, 1994,  on two  felony counts  of having
knowingly  violated the CWA and the  OPA,  33
U.S.C. §§ 1319(c)(2) and 1321(b)(3).  The basis
for the prosecution was the deliberate dumping of
waste oil from the cruise ship into the  ocean  off
the coast  of Florida.  The discharge  created a
visible sheen which was  detected during a joint
operation conducted by the Coast Guard, EPA,  the
Federal   Bureau   of  Investigation   and    the
Department of Justice. The corporation entered its
guilty pleas to a two count information on May
19, 1994.  Palm Beach Cruises was sentenced to
5  years probation  and   must pay  a fine  of
$500,000.

U.S. v.  Pacific Aqua Tech, Ltd. (E.D. Wash.):
On June 14, 1994, Gerhard Herman Zimm, Sr., the
President  of  Pacific  Aqua  Tech,  Ltd.,   was
convicted  by  jury  trial  of conspiracy  and
substantive  violations of the  CAA   and   the
CERCLA.  Zimm and his  corporation also pleaded
guilty to a CERCLA count in  the indictment and
entered into  a detailed plea agreement with  the
Government which provided for the funding  of  a
$1 million  trust  fund  annuity  for  the  future
medical expenses  of the workers who  were
                                             A-87

-------
       } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 exposed to asbestos during the company's scrap
 metal removal operations (the trust is to pay the
 cost  of medical  and  associated  expenses  of
 asbestosis  or asbestos-related diseases).  Zimm
 conducted  the scrap operation at Pacific  Aqua
 Tech's Toppenish, WA, facility from 1986 through
 the spring  of 1991.  Contamination at the facility
 necessitated  a superfund clean-up effecting the
 removal of  111  tons of asbestos contaminated
 material from Pacific Aqua Tech's property.

 U.S. v.  Robert Pardi (S.D. N.Y.):  On May 25,
 1994, Robert Pardi, an  architect  and the former
 Director of the Asbestos Task Force of the New
 York City Board of Education was sentenced to 30
 months of imprisonment for falsely reporting that
 school   buildings   were  free   of   asbestos
 contamination. He pleaded guilty in federal court
 on March  24,  1994, to making false statements
 and to criminal  conspiracy  to  make  false
 statements  in violation of the criminal laws of the
 United States, 18 U.S.C.  §§  1001 and 371, and to
 a  substantive count of violating the TSCA by
 failing  to  maintain  required reports concerning
 asbestos conditions in the public  schools.  Pardi
 was responsible  for  reporting   to  the  EPA
 concerning the inspection and testing of New York
 City public schools for the presence of asbestos.

 U.S. v.  Nicholas Pasauariello  (S.D. Fla.):   On
 May 16, 1994, sentence  was passed on  Nicholas
 Pasquariello after he was found guilty in a non-
jury trial on all counts,  including six  counts  of
 violating the CWA, among other criminal charges
 alleged  in  a 15-count indictment filed  in  1989.
 Pasquariello was convicted on January 25,  1994,
 after a sporadic bench trial which began in August
 1993, and  took  33 court  days.   The various
 charges  ranged from Pasquariello having  filled
jurisdictional  lakes  and  wetlands  on  property
 owned  by  him  and   associates  in  the  Ft.
 Lauderdale, FL, vicinity, to charges  of  violating
 income  tax laws, criminal conspiracy, and making
 a false statement to Department of Labor officials
 investigating labor law violations. Pasquariello was
 sentenced  to  70 months incarceration  and 36
 months   supervised    probation   following
 incarceration.
U.S. v. Norma Phillips, et al. (W.D. Mo.):  The
owners  and operators of the A-l Electroplating
Company facility  in Kansas  City,  MO,  were
sentenced on February  11, 1994, to prison and
probation for the illegal disposal of pollutants into
the Kansas City sanitary sewer system in violation
of the RCRA and the CWA. During the period of
their  operations, Phillips  and  the  Mammens
ordered  the  discharge of   hazardous  waste
generated by  their  electroplating process.  On
February 11,1994, Philip Mammen was sentenced
to 27 months of incarceration and David Mammen
received a sentence of 18 months of incarceration.
Norma  Phillips  was sentenced to 2 years of
probation and 6 months house arrest.  Hazardous
waste generated by A-l Electroplating was literally
swept  out of  front  and  back  doors into the
adjoining working class residential neighborhood.
The hazardous waste was also discharged into the
sewer  system  where  the  Kansas  City  Water
Department noted numerous violations.  The Water
Department  had  sought civil  fines  from the
business, and ultimately turned off the sewer and
water connections to the facility in an attempt to
stop the discharges.  However, the defendants
managed to dismantle the sewer connection plug
and continued  their illegal  discharges into the
system.   After the  business was  forced to shut
down in early 1990, Phillips and the  Mammens
attempted to start  a new  plating operation in
another  Missouri community.  They  transported
hazardous waste  from  the  Kansas  City,  MO,
facility to the new location and ultimately illegally
disposed of some of the waste at the new location.

U.S. v. Pioneer Chemical, Inc. and Gerald Butler
(D. Ky.):   Gerald Butler and Pioneer Chemical
Inc. were sentenced August 8, 1994, in Louisville,
KY, for violations of the Clean Air Act, 42 U.S.C.
§7413,  for  the illegal  removal  of  asbestos-
containing  material  without  complying  with
applicable  permitting  and    work-practice
requirements.  Pioneer Chemical Inc. (Pioneer)
was  also  sentenced on one count  for  having
violated the RCRA  by  storing  hazardous  waste
without  a permit.  Pioneer was fined $37,300 per
count for a total of $75,000 in criminal fines and
costs.   In addition,  Pioneer  paid $25,000 in
restitution to the Jefferson County Air Pollution
                                             A-88

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Control District Air Quality Trust Fund.  Butler
was sentenced to 1 year of probation. Pioneer had
hired  Butler,  and  a  co-defendant,  Jewell,  to
demolish   and   remove   asbestos-covered
components from  one  of Pioneer's  buildings.
Pioneer's  RCRA conviction resulted  from  its
illegal storage of 100 drums of hazardous waste.

U.S. v. John Pizzuto (S.D. Ohio):  In his second
environmental prosection, Pizzuto pleaded guilty,
on December 16, 1993, in Huntington, WV, to a
three count indictment of violating the TSCA,  15
U.S.C. §§ 2614 and 2615b after his illegal storage
of PCB's in Nitro, WV. On April 1, 1994, he was
sentenced to 18  months incarceration  for  his
violations of TSCA.   As a result of the West
Virginia crimes, which occurred during Pizzuto's
probation in Ohio, the Ohio federal judge on July
18,1994, revoked Pizzuto's probation, and ordered
him jailed for 18 months. The judge imposed the
prison sentence consecutively, not concurrently, to
the  West Virginia  sentence, meaning Pizzuto is
required  to  serve   a  total   of   36  months
imprisonment.

U.S. v. Nobert Efren Pohl (D. N.M.): Defendant
Pohl,  a former owner and  operator of Service
Circuits, Inc. (SCI), an electroplating company that
manufactured printed circuit boards, pleaded guilty
to knowing storage of hazardous waste without a
permit and  the knowing disposal  of  hazardous
waste without a permit under the RCRA.   On
December 20, 1993, Pohl was sentenced to 1 year
and a day incarceration. Pohl generated hazardous
waste at a  metal plating facility  in Albuquerque
from 1985 to 1989. CWA charges were also filed
for   the   knowing   discharge   of  lead   in
concentrations above those allowed under SCI's
wastewater discharge permit and  the  knowing
failure to submit complete quarterly reports to the
City of Albuquerque.  SCI's process involved the
dipping of circuit boards into acidic  solutions
containing heavy metals.  Solvents were used to
clean  and dry the boards and printing inks were
used for labels.   Irresponsible  waste  handling
practices, resulting in serious contamination of the
property,  were discovered  after the  defendant
ceased  operation and abandoned the facility in
1989.
U.S. v. R&D Chemical Company,  Inc.  (N.D.
Ga.):  Noble and  Oscar Cunningham and their
corporation,  R&D  Chemical  Company,   were
charged with conspiracy to  transport hazardous
waste from Ohio to an  unpermitted facility in
Georgia and with  illegal disposal  of hazardous
waste in violation of the RCRA.  R&D Chemical
accumulated a quantity of hazardous waste sludge
from industrial operations on the company farm in
Ohio.  R&D Chemical misrepresented the sludge
as being non-hazardous and made arrangements to
sell it to a Georgia company, calling it "RD-344"
to disguise it as a product. R&D Chemical leased
a truck and trailer and transported approximately
15 roll-off containers of the waste to a company in
Atlanta.  The containers  were  abandoned in the
company's  parking  lot.   In  addition,  R&D
Chemical caused a portion of the hazardous waste
to be disposed of at a non-hazardous landfill in
Atlanta.   Commenting  that the case  involved
"aggravating" circumstances, the  court sentenced
R&D Chemical on  October 6, 1994, to 5 years
probation,  a  $200,000  fine  and  $146,716
restitution to the Atlanta company where the waste
had been abandoned.

U.S. v. Recticel Foam Corporation, et al. (E.D.
Tenn.): On July 22, 1994, Recticel pleaded guilty
to a felony charging that it knowingly omitted
material information in a record  filed with EPA
and the Tennessee Department of Environment and
Conservation (TDEC) and failed to  keep a record
of a hazardous waste determination  made by it in
July 1990.  Recticel also pleaded  guilty to a State
environmental misdemeanor in  a  related State
prosecution. The case had begun on October 15,
1990, when TDEC  conducted  an administrative
inspection of two manufacturing facilities located
in Morristown, TN, owned by  Recticel.   The
TDEC inspectors observed  methylene chloride
waste  in solid waste dumpsters at  the  plants.
Subsequent  investigation revealed  that Recticel
was burying drums containing allegedly hazardous
waste on property owned by Cansler, and dumping
it in rolloff containers  that were destined for
disposal  in  solid  waste  landfills  in  eastern
Tennessee.
                                             A-89

-------
      IFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
U.S. v. William C. Reichle and Reichle, Inc. (D.
Ore.): William Chester Reichle, the President of
Reichle,  Inc. and  his  Portland, OR,  based
corporation both entered guilty pleas on May 23,
1994, in the District of Oregon to one  count each
of felony violations of the RCRA. The federal
charges resulted  from a joint investigative effort
by EPA's Criminal Investigation Division and the
U.S. Department of the Interior's Bureau of Land
Management  (BLM)  special  agents  based in
Portland, OR. Reichle owns and operates a large
commercial painting and drywall company which
performs jobs in  southwest  Washington  and
northwest  Oregon  areas.    Reichle  frequently
participates in contract work at federal, state, and
local construction and  renovation projects.   In
March  1992, an  unpermitted  hazardous waste
disposal site with numerous  55-gallon drums of
paint and spent solvents was discovered on BLM-
administered  public  land in  a  rural  area of
northwest Oregon.  In  June 1992, investigative
efforts led federal agents to a second unpermitted
hazardous waste site on privately-owned land, also
in northwest Oregon, which is used  as a dairy
farm. Reichle and his company were responsible
for the illegal disposal at these sites.

U.S. v. Reilly andDowd (D. Del.):  On October 4,
1993, two shipping executives were sentenced to
prison terms on ocean  dumping,   33 U.S.C.
§1411 (a), and perjury charges in connection with
the  freighter, Khian  Sea.   Reilly received  a
sentence of 37 months imprisonment.  This case
arose after approximately 15,000 tons of municipal
incinerator  ash  was  loaded  on the  Khian  Sea
vessel destined  for a  disposal location  in the
Bahamas.  After sailing the Atlantic in 1987 in an
unsuccessful effort to  find a disposal location, the
ship returned to the lower Delaware Bay in March
of 1988. The ship ultimately sailed away against
the orders  of the Coast Guard, and dumped its
cargo in the Atlantic and  Indian Oceans.  Both
defendants were found guilty of lying to a federal
district court judge concerning what had happened
to the shipment of ash.  Reilly was also convicted
of  one count  of lying   to  a  grand jury in
Wilmington   over  the   ash's   disappearance.
Evidence presented at trial included trans-oceanic
cable  messages  linking  the  defendants  with
instructions to illegally dump the ash in the ocean.

U.S. v. Sentco Paint Manufacturing, Inc., et. al.
(N.D. Ohio):  On March 17, 1994,  Sentco Paint
Manufacturing Company, Inc., was sentenced to 3
years probation and an $8000 fine for its part in
having violated the RCRA through the illegal
disposal of hazardous wastes. The sentencing of
Sentco concluded an investigation which resulted
in previous guilty  pleas and the sentencing of
Roland Brothers,   President of  Sentco;  Rick
Brothers,  Plant Manger;  and  Donald  Cole, a
company employee involved in the illegal disposal
of hazardous waste.  They had pleaded guilty June
1, 1992, to a  1990 indictment charging them with
having buried fifty-six drums of paint waste, a
hazardous waste, under a cement loading  dock at
the  plant site.   The  guilty pleas  resulted in
sentences  of  15 months incarceration of Roland
Brothers,  18  months  incarceration  for  Rick
Brothers, and 6 months home detention for Donald
Cole.

U.S. v. Mark Steven Stewart, et al. (D. Ariz.):
Mark  Steven  Stewart,  the president  of  a crop
dusting company  in Pinal  County, AZ,  was
incarcerated  for a  year  for  illegal  disposal of
methyl parathion (a hazardous waste from his crop
dusting activities) and illegal use of a pesticide in
violation of the FIFRA.  As part of his guilty  plea
on December 13, 1993, Stewart agreed to liquidate
the assets of  the company and use that money to
pay for clean-up costs at the illegal  disposal  site.
Two  aircraft, valued at approximately $60,000,
were forfeited to the United States Marshal under
terms of the plea agreement.  Stewart transported
methyl parathion and unsuccessfully attempted to
incinerate the material in concrete  tanks.  Two
county zoning  officials  who  inspected   the
uncontrolled   site   were  exposed  to  airborne
contaminants and became ill from the exposure.
Stewart's illegal practices lead to a clean-up of the
disposal site contaminated with  methyl parathion.

U.S. v. Thermocell S. E. Inc., Douglas Kirchofer
and   Sherwin   T.  Haskell   (E.D.   Tenn.):
Thermocell Inc. was fined $125,000 for illegal
transportation of hazardous waste in violation of
                                             A-90

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I rwr!
the RCRA, 42  U.S.C.  §6928  (d)(2)(A).   As a
condition of probation, $100,000 of this fine was
suspended on the condition that, as restitution and
compensation   to   the   State  of   Tennessee,
Thermocell   pay   $50,000  into  the  State's
Environmental Protection Fund and pay cleanup
cost  of $38,000.    Kirchofer,   the  corporate
secretary, was sentenced to supervised probation
for 1 year and  fined $5,000.  The comptroller,
Haskell, was sentenced to 1 year of supervised
probation and a $1,000 fine. Each of the men had
pleaded  guilty  to  a  misdemeanor violation of
RCRA as an accessory after the fact pursuant of
Title  18  U.S.C.  §3.    This  case  arose  after
Thermocell  sold machinery  and  320  drums of
chemicals to an Atlanta, GA, manufacturer for one
dollar. The Atlanta manufacturer subsequently had
financial difficulties, and at least 35 drums were
abandoned  on farmland  in Norcross,  GA.   The
farmer contacted Haskell and requested removal of
the drums.  Haskell and an associate  loaded  the
drums on a rented Ryder truck and  abandoned
them  on unused property in an isolated area of
Scott  County,   TN.    The  drums  were  then
discovered  by a U.S. Office of Surface Mining
inspector.

U.S.  v.  Weaver Electric (D.  Colo.):  Weaver
Electric Company was in the business of buying,
refurbishing, and selling used electrical equipment.
As part of its operation,  it collected,  used, and
stored PCBs. Indictments charged individuals with
illegal storage of PCBs, in violation of the TSCA,
conspiracy, and  false  statements.   An  individual
defendant,  Daniel  Rodriguez, was charged with
transporting tractor trailers full of 55-gallon drums
containing PCB fluid for eventual illegal export to
Mexico.   The, Weaver  Electric  Company  was
convicted and sentenced to  pay a  $200,000 fine
and  $300,000   for remedial  activities.    The
company participated in  a scheme to illegally
dispose of PCBs by burial at a remote Colorado
horse ranch  and  to  illegally  export  PCBs to
Mexico  in  order  to  avoid paying   the  costs
associated with the  lawful and proper disposal of
PCBs in the United States.  Rodriguez  had agreed
with Weaver to receive three tractor trailers full of
55-gallon drums containing PCB fluid  in El  Paso,
TX, for eventual illegal  exportation into Mexico.
After   numerous   unsuccessful   attempts  by
Rodriguez to pay individuals to transport the three
trailers  full of leaking  drums,  the trailers were
eventually  discovered by the local fire marshal.
Due to  PCB contamination  at two facilities, the
company   agreed   to   spend   $300,000  for
environmental  remediation.    Restitution  was
ordered  for   superfund   clean-up   of  PCB
contaminated property at the facilities.

U.S.  v. Safety  Kleen:    A joint  Federal/State
investigation of Safety Kleen and Booth Oil Co.
relating to improper handling of hazardous  waste
oils at a Buffalo, NY, facility, resulted on August
19, 1994 in Booth pleading guilty to a State felony
count for possessing hazardous waste (PCB-laden
oil) in violation of its State permit, and paying a
fine of $100,000.  Safety Kleen and Booth Oil had
been running the Booth Oil facility jointly. Safety
Kleen settled in a civil action  with the Federal
government at the same time, by forfeiting $1.9
million; agreeing to purchase the Booth Oil facility
for $2.4 million and install new management; and
accepting appointment of a State  environmental
monitor to assure compliance.

U.S.  v.  Steve  Weinsier (S.D.  Fla.):    Steve
Weinsier,  former  owner  of Florida Waterway
Management, an  aquatic management  company,
entered  a guilty plea January.  18,  1994, to  ten
counts of illegally using the pesticides Direx and
Karmex on aquatic areas  in  violation of  the
FIFRA.  Weinsier had been indicted November 19,
1993, on ten counts of violating FIFRA and  seven
counts of Mail Fraud. Weinsier pleaded guilty to
the illegal use of the pesticides Direx and Karmex
on sensitive Florida aquatic areas.  Weinsier  knew
that the products Direx and Karmex, which contain
the active ingredient diuron, were not approved by
the Environmental Protection Agency for use on
water.   However, he used mail  solicitations to
attract customers for his business of removing and
controlling unwanted aquatic vegetation and algae
growth using these chemicals.  Weinsier obtained
written  contracts  for  his   services by falsely
represented  that  he used  only  EPA-approved
products in his removal and control activities.
                                             A-91

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
U.S. v. Larry Kenneth West (W.D. Mich.):  On
January 14,  1994, Larry K. West, owner of Cal-
Art, a defunct Cassapolis, MI, plastics business,
was sentenced to 4 months home confinement, a
$10,000  fine,  $40,000 restitution, and 2 years
probation for his actions in abandoning drums of
chemicals at his former business site in Cassapolis
in July  of 1988.  West had previously pleaded
guilty on November  5, 1993, to  one count of
violating the RCRA, 42 U.S.C. §6928 (d)(2)(A),
and a second,  under the  CERCLA, for  having
knowingly  and unlawfully failed  to report  an
unpermitted  release of a reportable quantity of a
hazardous material.  This case is related to another
federal  RCRA criminal  case, U.S.  v. William
Meyers, which resulted from the  activities of the
owner of the premises where  Cal-Art had  been
located.  The waste had been illegally transported
to Ohio and abandoned there, and the perpetrator
of that violation had  been ordered to reimburse
EPA for its costs of the  Ohio  clean-up  and
disposal of the waste.

U.S. v.  'William  C.  Whitman  and Duane  C.
Whitman (M.D.  Fla.):    On  July 28,  1994,
following a 2-week  jury trial  in  Tampa,  FL,
William C. Whitman, a plant manager, and Duane
C. Whitman, a shop foreman, of Durex Industries
were found  guilty  of  treating   and .  storing
hazardous waste without a permit from June  1991
to June 1992.   The company that owned  Durex,
William Recht Company, Inc., pleaded guilty to a
two-count   indictment    which    charged   the
defendants with illegal treatment,  storage  and
disposal of hazardous waste without a permit and
knowing endangerment in violation of the RCRA.
The prosecution of the defendants was initiated
following the deaths of two 9-year-old boys  from
toluene fume asphyxiation on June 13, 1992. The
two children had been playing in a dumpster in
which  toluene  waste had been  discarded.  The
company and individual defendants were sentenced
in FY95.

Harry Zucker (W. D. Pa):   On  July 8, 1994,
Harry Zucker was sentenced in  Federal court to
eight months home detention, one year probation
and ordered to pay a $5,000 fine on his conviction
for  discharging brine  waste water  from  oil
production wells into waters of the United States
without a permit in violation of the Clean Water
Act. Harry Zucker plead guilty to count one of an
eight count indictment on February 3, 1994.  The
indictment  charged  the defendant  for  illegal
discharges which occurred between November
1989  until  July  1992.  As  a condition of the
Federal criminal plea, Marley Industries entered a
guilty  plea  to  state  criminal  charges for  the
unpermitted discharges and paid  a $40,000 fine to
the Commonwealth on May 24,  1994.

U.S. v. Dale Valentine et al (D. WY): In one of
the largest RCRA setion 7003  cases ever, EPA
finalzied a series of settlement agreements during
fiscal  year 1994 as well  as receving  a number of
favorable rulings. The case arose from Regions
VIITs  enforcement action relating to the Powder
River  Crude  Processors  site  near  Glenrock,
Wyoming.

In 1991, EPA issued UAOs under RCRA §7003 to
several parties, demanding cleanup of this former
oil re-processing facility. Surface impoundments
at the  site pose  a serious risk  to wildlife,  with
birds and antelope becoming trapped  and dying in
the oily  wastes.   In addition, abandoned above-
ground tanks, which  could fail, pose a potential
risk to human health. Some  of the respondents
constructed a security fence around the facility and
netted  the open pits;  otherwise,  they declined to
clean  up the site. The U.S. subsequently filed a
complaint against ten of the parties.

In March 1994,  the Agency  lodged  a settlement
with five generator-defendants (Texaco, Conoco,
Phillips Petroleum, True Oil, Eighty-Eight  Oil).
Under the consent decree, the settling defendants
are obligated to pay a $300,000 penalty and clean
up the site.  Cleanup consists  of the removal and
treatment of materials from the impoundments and
tanks, plus contaminated soils.  Estimated cost: at
least $4.5 million, perhaps (depending on amount
of soil requiring remediation) as much as  $8.9
million.

During  the  summer  of  1994,  the  Agency
concluded negotiating a settlement agreement with
one of the former site operators,  Richard Wallace,
                                             A-92

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
obligating  him  to  pay  a  $30,000  penalty.
Settlement negotiations with the four remaining
defendants continued into fiscal year 1995.

The  U.S.  District  Court  for  the  District  of
Wyoming issued several favorable decisions in FY
94 during litigation of this case. For example, in
a decision dated June 1, 1994, the court granted
the government's motion for summary judgement
on issues related to  the presence of an imminent
and substantial endangerment at this particular site.
In addition,  the court held that the administrtive
orders  unilaterlally  issued by  EPA pursuant to
RCRA section 7003 were "reasonable."  In doing
so, the court rejected the argument of one of the
defendants that its due process rights were violated
by the lack of an opportunity for a hearing prior to
issuance of the orders. The court found that EPA
had provided the defendants a timely opportunity
to confer, subsequent to the issuance of the orders,
regarding implementation.  It  also noted that the
defendants would have an opportunity, during an
upcoming trial, to challenge their liability under
RCRA section 7003.  This portion of the court's
decision supports EPA's position that defendants
are not entitled to a judicial hearing to review such
orders prior to the government filing an action to
enforce them.
                                             A-93

-------

-------
     FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
                                 TABLE OF CONTENTS
APPENDIX B  STATE CASES  	. . B-l

       ALASKA  	B-l
          Anchor Forest Products  	B-l
          CH2M-HU1 Engineering	B-l
          City of Angoon, Alaska	B-l
          Construction Rigging, Inc. (CRI)	B-l
          Echo Bay Alaska, Inc	B-l
          Enstar Natural Gas Company  	B-l
          Kake Tribal & Kake Tribal Logging	B-2
          Northland Fisheries, Inc	B-2
          Ronnie C. Fisheries	B-2
          William A. Wood  	B-2
       COLORADO	B-2
          State of Colorado v Colorado Refining  	B-2
          State of Colorado v Conoco	B-2
          State of Colorado v The  City of Ft. Morgan	B-3
       DISTRICT OF COLUMBIA	B-3
          Concerned Citizens of Brentwood, et al., v. The District of Columbia, et al	B-3
          D.C. Department  of Consumer  and Regulatory  Affairs  (DCRA)  v.  Coastline
              Purchasing Corporation 	B-3
          D.C. Department  of Consumer and  Regulatory  Affairs  (DCRA)  v.  Kayfirst
              Corporation  	B-3
          D.C. Department of Consumer and Regulatory Affairs (DCRA) v. The U.S. General
              Services Administration	B-4
          District of Columbia Department of Consumer and Regulatory Affairs (DCRA),
              Environmental Regulation Administration  (ERA)  v.  Respondent Mr.  Jerry
              Schaeffer	B-4
       FLORIDA	B-4
          Boston Chicken	B-4
          Department of Environmental Protection v. Lake County '.	B-5
          Department of  Environmental Protection v.  Pinellas County Board  of  County
              Commissioners	B-5
          Department of Environmental Regulation v. Cabot Corporation  	B-5
          Department of Environmental Regulation v. Pilot Properties Co. and Durham Utility
              Service, Inc	B-5
          Florida Department of Corrections	B-5
          Florida Department of Environmental Protection v. NRG/Recovery Group, Inc., aka
              Ogden Martin Systems of Lake, Inc	B-6
          Florida Gas Transmission	B-6
          Florida Gas Transmission	B-6
          Hazardous Waste Consultants, Inc. and Hazardous Waste Services, Inc	B-6
          Kissimmee Utilities	,	B-7
          Master Packaging	B-7
          Mur-Shel, Inc	B-7
                                           B-i

-------
| FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
    Ogden Martin	B-7
    Pinellas County Department of Solid Waste Management  	B-7
    Polyplastex International  	B-8
    R.P. Scherer Corp	B-8
    South West Florida Water Management District	B-8
    State of Florida Department of Environmental Protection v. United States Naval Air
        Station—Jacksonville	B-8
    State of Florida v. Urbano Diaz-Devillegas; Romulo Juan Delgado; German Delgado;
        Darwin Mesa and Errol Woon  	B-8
    Tampa Bay Center	B-8
    Trend Management	B-8
    Venture Properties	B-9
    Waste Management	B-9
 GEORGIA	B-9
    Oxford Industries, Greenville, Georgia	B-9
    U.S. Navy Submarine Base, Kings Bay, Georgia	B-9
    Young Refining Corp., Douglasville, Georgia	B-9
 IDAHO	B-9
    Envirosafe Services of Idaho, Inc	B-9
    Stibnite Mining Company	B-10
    St. Alphonsus Regional Medical Center, Boise, Idaho	B-10
 ILLINOIS	B-10
    Pork King Packing Company 	B-10
 INDIANA	B-ll
    Confined Feed Lot Facilities	B-ll
    JPT Petroleum Production Corp	B-ll
    State of Indiana v. James E. Nichols, State of Indiana v. Custom Finishing Corp. ... B-ll
 IOWA	B-ll
    In the Matter of the City of Winterset, LA	B-ll
 KANSAS  	B-12
    In the Matter of Dawson Brothers, Inc., Wichita, KS:  	B-12
    In the Matter of Owens-Coming Fiberglas Corporation, Kansas City, KS  	B-12
    In the Matter of Sunflower Manufacturing  Company, Inc., Beloit and Cawker City,
        KS	B-12
 MICHIGAN	B-12
    Ace Finishing, Inc	B-12
 MINNESOTA 	B-13
    LTV Steel Mining Co	B-13
 MISSOURI	B-13
    In the Matter of Barton Nelson, Inc	B-13
    In the Matter of International Paper Company, Joplin, MO  	B-13
    Norfolk and Western  Railway Co	B-14
 MONTANA	B-14
    State of Montana v Continental Lime   	B-14
 NEBRASKA	B-14
    Ash Grove Cement Company	'.	B-14
 NEW JERSEY	'.	B-14
    State of New Jersey v. Patricia Nazzaro, John Martinez, Augustine Scalzitti & Frank
        Scalzitti	B-14
                                    B-ii

-------
FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I t
  NORTH CAROLINA	B-15
     Carolina Mirror Company (North Wilkesboro, NC)	 .  B-15
     Duke University (Durham, NC)	B-15
     Fawn Industries (Middlesex, NC)	 .  B-15
     Greer Laboratories	B-16
     Midway Body Shop (Winston-Salem, NC)	B-16
     NC DOT—Ferry Division (Manns Harbor, NC) 	B-16
     Phillips Plating  Company (Bridgeton, NC)	B-17
     Watts Regulator Co./Regtrol (Spindale, NC)	B-17
  OHIO	B-17
     Andersons Management Corp	B-17
  PENNSYLVANIA	B-17
     ARCO Chemical Company	B-17
     Graphic Controls	B-18
     Keystone Cement Company 	B-19
     Mays Properties, Inc	B-19
     Performax Engine Works, Inc	B-19
     U.S. Steel-Carnegie Natural Gas	B-19
  SOUTH CAROLINA 	B-19
     Gaston  Copper  Recycling Corporation	•. -	B-19
     Green Oasis Environmental, Inc	B-20
     Holnam, Inc	,	  B-20
     Shakespeare Products Group	  B-20
     Spartanburg Steel 	B-20
     ThermalKEM, Incorporated 	B-20
  TENNESSEE	B-20
     Department of Energy K-25	B-20
     Gabriel Ride  Control  Products, Inc	B-21
     State of Tennessee v. Flavil Ray & Robert Wallace Bradford	B-21
     State of Tennessee v. Gabriel Ride Control Products, Inc	B-21
     U.S.  v. Recticel Foam Corporation & State  of Tennessee  v.  Recticel  Foam
         Corporation 	B-22
     Wheland Foundry Division of North American Royalties, Inc	B-22
  TEXAS	B-23
     State of Texas v. Gary Giles Cocke, et al	B-23
  WASHINGTON	B-23
     Fiberglass Technologies Inc	B-23
     Perfection & Letz Paint Company	B-23
     United  States Army Base Fort Lewis,  Washington  	B-23
  WISCONSIN	B-24
     Dean Foods Vegetable Company	B-24
                                     B-iii

-------

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I
                                       APPENDIX B
                                      STATE CASES
ALASKA

Anchor  Forest  Products:    Anchor Forest
Products was convicted of three misdemeanors
following a bench trial. The convictions are for
Pollution, Illegal Discharge  of a  Petroleum
Product, and Illegal Discharge of Non-domestic
and Domestic Wastewater. The court merged the
first two counts, then imposed a fine of $1,000
and 30 days in jail on each of the remaining two
counts, but suspended the fines and jail on the
condition that Anchor Forest Products conduct
adequate remediation over the next two years,
and comply with DEC regulations.

CH2M-HH1   Engineering:      CH2M-Hill
Engineering  agreed  to  pay  a  $25,000  civil
settlement to the state's Hazardous Substance
Mitigation  Account in July 1994 in  Unalaska
District Court.  The agreement resulted from a
compromise  on  four misdemeanor  charges
involving the same chlorine discharge into Icy
Creek to which  CRI pleaded guilty. Magistrate
Hawkins approved  the agreement following
arguments by both sides in favor of the dismissal
and compromise.  CH2M-Hill also agreed to
institute an in-house training program  to avoid
future chlorine discharges.

City of Angoon, Alaska:  The City received a
$5,000 fine in August, 1994 in Juneau  Superior
Court following a plea of no contest to a class A
misdemeanor charge  of  failing  to  file water
treatment records in  a timely  manner.   The
record keeping problems occurred between 1990
and  1993.    Superior Court Judge  Walter R.
Carpeneti suspended  all of the fine and placed
Angoon on probation for a period of 3  years on
the condition that the city have no environmental
violations during that period.   In addition, the
court ordered Angoon to complete a report upon
consultation with DEC which addresses how the
city will supervise its water treatment operators,
verify  reports,  educate  the  community about
water treatment, maintain schedules for supplies
and equipment and fund its maintenance of the
water treatment plant.

Construction Rigging, Inc. (CRI):  CRI,  an
Alaska Corporation, pleaded guilty in July in
Unalaska District Court to four misdemeanor
charges involving a chlorine discharge into Icy
Creek. CRI accepted responsibility for the acts
of its agent whom they had instructed not to
participate in a discharge of the chlorine without
first neutralizing it.    The discharge  killed
approximately   40   Dolly  Varden   (Char).
Magistrate Mary Hawkins sentenced CRI to pay
a total fine of $5,000 with $2,500 suspended on
the condition that CRI not have any  similar
violations for one year.

Echo Bay Alaska, Inc.:  Echo Bay Alaska, Inc.,
entered into a civil Consent Decree with the
State of Alaska in which the company agreed to
pay the State a total of $250,000 for violation of
State environmental laws. The amount includes
$125,000  in  civil  penalties,   $50,000  for
investigation cost reimbursement, and $75,000 to
offset future costs  of  ADEC  oversight and
monitoring of the Alaska Juneau  Mine.  In the
Consent Decree Echo Bay Alaska, Inc., admitted
liability for violating State laws concerning the
reporting of oil spills and disposal of materials
used in oil  spill cleanup actions.  The action
resulted from  an ADEC  investigation  of  a
turbidity event in Gold Creek.  An investigation
led ADEC to inspect operations and discover the
violations.    The mine  is operated  in  an
exploratory phase by Echo Bay Alaska.

Enstar Natural Gas Company:  Enstar paid a
$15,000 civil settlement to the State of Alaska in
October, 1994. The agreement resulted from a
compromise to   three  misdemeanor charges
brought by  the State's  Environmental  Crimes
Unit involving unpermitted stream crossings near
Meadow  Creek  in  Wasilla, Alaska.  Minor
damage resulted  to the rearing habitat of coho
salmon during installation of a gas pipeline. The
                                             B-l

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
crossings occurred in October, 1993. Enstar also
agreed  as  part  of the settlement  to- conduct
mitigation  efforts on  the streams under the
direction of the Department of Fish and Game's
Habitat Division.

Kake Tribal & Kake Tribal Logging:  Kake
Tribal   Logging  Camp  is  located  at  Point
Macartney, five miles northwest of Kake, on
Kupreanof   Island   in  Southeast   Alaska.
Respondents   were  charged  with  numerous
violations of state pollution laws, which included
oil and chemical spills, open burning of used oil
and oily wastes, discharge of improperly treated
sewage, failure  to notify the  State of Alaska
DEC  of oil  and hazardous  substance spills,
unpermitted  disposal   of solid  waste,  and
violations  of   the   State   Drinking  Water
regulations.   In  settlement for damages and
penalties, Respondents agreed to pay  the  state
$125,000 with $50,000 suspended on condition
that the Respondents complete all  cleanup and
remediation required by the Compliance Order
by  Consent entered into by the  parties.  In
addition, the Respondents agreed to pay $15,000
to the City of  Kake  to  purchase emergency
response equipment,  and an additional $15,000
to provide spill response training to citizens of
the Kake community.

Northland Fisheries, Inc.: A Washington State
based corporation, Northland pleaded no contest
to one count of violating  its NPDES permit in
Akutan  Harbor  in the Aleutian  Islands.   The
violation involved discharge of ground  crab
viscera  and  shells at a depth not allowed by
permit.   The  court  fined Northland  $20,000,
suspending all but $17,500 of the fine on the
condition that Northland have no violations for
one year.

Ronnie C. Fisheries:  Ronnie C. Fisheries, an
Oregon  Corporation,  received a $10,000 fine in
August,  1994   in  Unalaska  District Court
following a plea of no contest to a  class A
misdemeanor charge  of illegally discharging oil
into Dutch Harbor. The spill occurred  in March
of 1993 and involved approximately 50 gallons
of diesel  fuel  from the  fishing vessel  "AJ."
Attempts by  the vessel  owners to disperse the
spill with liquid detergent were unsuccessful and
did not meet DEC standards for oil spill cleanup.
Magistrate  Mary Hawkins  suspended all  but
$2,500 of the fine and placed the corporation on
probation  for a  period  of one  year on  the
condition  that  Ronnie  C. Fisheries  have no
similar violations during that period.

William A. Wood: William A. Wood pled no
contest  to three  water treatment misdemeanors
resulting from development of  a trailer court on
Prince of Wales Island in southeast Alaska. The
convictions were for charges of failing to obtain
a plan  review  for his  water  and wastewater
system,  in  addition to  not  conducting  proper
fecal coliform tests. He was utilizing  a surface
water source.  The court imposed a fine of
$5,000 for  each  count concurrently, suspended
the fines and  placed Mr. wood  on probation for
one year.

COLORADO

State of Colorado v  Colorado Refining:  In
coordinated multimedia State and EPA actions,
CDPHE's NPDES and  RCRA programs took
enforcement actions against Colorado Refining to
clean up  seeps  to  Sand Creek.    Colorado
Refining also had effluent violations of their
NPDES permit.   The State ordered injunctive
relief and has settled for $375,000 cash  plus $1.4
million  in  SEPs.    This will be the  largest
penalty  the State has collected.  Further,  the
Agency   got  a   favorable   ruling   on   the
applicability of CWA to discharges of pollutants
reaching surface waters  via groundwater. In a
related citizen's suit under the Clean Water Act,
Sierra Club v Colorado Refining Company, 838
F. Supp. 1428 (D. Colo.  1993),  where pollutants
migrated through the  groundwater into surface
water, the Court concluded that the Clean Water
Act's prohibition  of  the discharge   of any
pollutant into "navigable waters" includes such
discharge  which  reaches  "navigable  waters"
through  groundwater.

State of Colorado v  Conoco:  In coordinated
multimedia State and EPA  actions, CDPHE's
                                             B-2

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT

NPDES and RCRA programs took enforcement
actions against Conoco to clean up seeps to Sand
Creek.  The State ordered injunctive relief and
collected an NPDES penalty of $200,000.  In a
related citizen's suit under the Clean Water Act,
the Sierra Club settled with Conoco for $280,000
per year  for  five  years for  a  Supplemental
Environmental Project along Sand Creek. EPA
supported  these  settlements  as  recovering
Conoco's economic  benefit  ($200,000 cash
penalty to CDH) and appropriate gravity in the
SEP negotiated by the Sierra Club.

State of Colorado v The City of Ft. Morgan:
In  coordinated  State and  EPA actions,  the
Colorado  Department  of  Health's  NPDES
program and EPA's Pretreatment program took
enforcement actions  against The City of Ft.
Morgan.   The State addressed the  effluent
violations and ordered injunctive relief related to
the  effluent violations.   The State collected
$115,000 for the effluent violations.  This is the
largest penalty  the State has collected against a
municipality.

DISTRICT OF COLUMBIA

Concerned Citizens of Brentwood, et al., v.
The District of Columbia, et al.:  The citizen
plaintiffs initially obtained a TRO from the Court
which  set aside District Government  permits
issued to Consolidated Waste Industries, Inc. for
the  purpose   of  expanding  a solid  waste
management operation into a receiving, sorting,
and baling  operation for recyclable materials.
The TRO was in  effect until the  Court  was
satisfied  that  the  District  Government  had
complied with the D.C. Environmental Policy
Act,   which  requires  consideration   of  the
environmental   impact  of  proposed activities
meeting   the   statutory  threshold   criteria.
Multimedia  inspections  were directed by the
Court and ultimately, the Court found in favor of
the government and vacated the TRO,  allowing
the expansion of CWI's operations.

Subsequently,   residents   complained   to   the
Attorney General's office, raising the issue again
as a matter of environmental equity and justice.
Ms.  Reno's office referred the complaint  to
EPA's Office of  Environmental  Justice and
Region HI requested the D.C. ERA to conduct a
Multimedia environmental justice inspection  of
Consolidated  Waste Industries, Inc.,  now  a
business partner  of Browning Ferris Industries,
Inc.  The inspection has been completed  and a
report forwarded to EPA.

D.C.   Department   of   Consumer   and
Regulatory  Affairs  (DCRAV  v.  Coastline
Purchasing  Corporation:     Administrative
enforcement action was  initiated to  remedy
contamination of soil and ground water resulting
from leaking underground storage tanks. DCRA
obtained consent agreement from owner/operator
authorizing  DCRA to  enter  on  property  to
perform further site investigation and corrective
action.   Respondent  acknowledged  that  the
District of Columbia was authorized to recover
costs against it and was further authorized  to file
a notice of lien against the property.  DCRA
agreed  that after  issuing a  demand letter  to
Respondent for  the costs of remediation, that
DCRA would refrain from selling the property at
a tax sale for a period of at least one year and 30
days in order to provide the Respondent with an
opportunity to sell the property and pay off the
lien first.

D.C.   Department   of   Consumer   and
Regulatory  Affairs   (DCRA)  v.   Kaviirst
Corporation: Administrative enforcement action
was initiated to remedy contamination of soil and
ground water resulting from leaking underground
storage tanks.  Action was first brought against
current  owner   of  the  property,   Kayfirst
Corporation,  which had failed  to comply with
agency directives.  However, initial investigation
conducted by Kayfirst Corporation in response to
administrative action revealed that 6 underground
storage tanks, thought to  have been  previously
removed from the property,  were still on-site.
Thereafter, DCRA issued discovery directives to
previous   owners  and   operators,   including
Sunoco, CSX Transportation Corporation, Inc.
and Mount  Clare Properties,  Inc.   Through
discovery responses, it was learned that Sunoco
previously leased the site and operated a  gas
                                              B-3

-------
       } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
station, and that while 3 tanks had been removed
from the site before Kayfirst purchased in 1989,
6 remained, out of 9 tanks shown to have been
installed by Sunoco.

On  July  19,  1994 a revised Stipulation was
entered among the parties.  Once the remediation
system is fully installed and operational, a final
stipulation and conditional  order of dismissal
without prejudice will be entered.

D.C.   Department   of   Consumer   and
Regulatory Affairs  (DCRA)  v.  The U.S.
General Services Administration:   The U.S.
General Services Administration (GSA) operates
two large  heating plants  in Washington, DC.
These  plants  provide steam  to  heat  Federal
buildings.  During the late 1980s, GSA began a
boiler refurbishment and replacement program at
both   plants.      After    completing   their
refurbishment  program,  GSA  planned to burn
coal as their principal  fuel.

In  January  1991, the   U.S.  Environmental
Protection  Agency (EPA)  determined from air
dispersion  modelling  that  violations  of  the
National   Ambient  Air  Quality  Standards
(NAAQS) for sulfur dioxide (SO2) may occur in
areas around these plants when coal is fired in
plant boilers. To  resolve air quality compliance
issues associated with the plants, GSA, EPA and
the  District entered  into  a  Federal  Facility
Compliance Agreement  in the spring of  1992.
The agreement required that GSA increase  the
height  of the smoke stacks at the heating plants
to better disperse air  pollutants or develop an
alternative compliance plan. GSA was unable to
secure  timely approval for taller stacks from  the
National Capitol Planning Commission and other
regulatory  agencies  pursuant to the  agreement.
As  a result, GSA was  forced to develop  an
alternative compliance plan.

In May  1993, GSA committed to  burn only
natural gas and very low sulfur fuel  oil at their
heating plants  to ensure  NAAQS  were not
violated.  EPA and the District accepted this
alternative  compliance plan.  GSA failed to
adhere to commitments made in their alternative
compliance  plan during the  1993/94  heating
season, however.  In  response to violations  of
their alternative compliance plan and other air
quality violations, the District issued a Notice of
Non-Compliance and  Proposed Order to GSA
April 15, 1994. After lengthy negotiations, GSA
has agreed to strictly adhere to their commitment
to burn only natural gas and very low sulfur oil.
GSA has also agreed to improve  continuous
emission monitor performance at their facilities.

The District issued an operating permit to GSA's
heating plants  September 8, 1994.  The permit
requires that GSA operate in compliance with the
significant  elements   of  their   alternative
compliance plan and other air quality regulations.
The operating permit, which has been submitted
to EPA as a State Implementation  Plan (SIP)
revision, is Federally enforceable.

District of Columbia Department of Consumer
and   Regulatory   Affairs   (DCRA),
Environmental   Regulation  Administration
(ERA) v. Respondent Mr. Jerry  Schaeffer:
The   D.C.    Environmental   Regulation
Administration   (ERA)   participated   in   a
multimedia  inspection  and  coordinated  the
issuance  of a multimedia  compliance order
(under RCRA  AU3013) to the violator.   The
facility was used for automobile salvage  and
storage operations.  The investigation revealed
illegal  traffic   in  stolen  vehicles  and parts
distribution was also occurring  at the site.  The
project site was known locally as "the Deanwood
Dump."  The administrative order directed the
site owner to identify the presence and extent of
any soil contamination.  A sampling and analysis
plan was submitted and approved by ERA.  The
area was  found  to be  free of serious toxic
contamination  but was greatly  cleaned up as a
result of this action.   The D.C. City Council
recognized the participants' initiative to  solve a
pressing community problem in a ceremony and
Council Resolution on January 4, 1994.

FLORIDA

Boston Chicken:  Boston Chicken was cited for
no notification, no trained on site representative
                                             B-4

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT!^
                                                                                       V
and inadequate wetting of approximately 2,400
sq. ft. of RACM ceiling  tile.  Boston Chicken
has signed a Consent Order and paid a $25,000
penalty.

Department  of Environmental Protection  v.
Lake County:  Lake County operated the Lake
County  Sign  Shop, a road striping facility,
located  in  Tavares, Florida.   The operation
involved the   use  of  toluene for  cleaning
machinery,  and of  paints containing lead and
chrome.    Toluene, lead  and  chrome  were
discharged  to the ground.  Hazardous waste
violations  were  documented  after a  RCRA
hazardous  waste compliance  inspection  was
conducted.  In settlement of these  matters, the
parties  entered into a Consent Order.   Lake
County  agreed  to  pay  $2,000 in costs  and
$22,000 in in-kind penalties.

Department  of Environmental Protection  v.
Pinellas   County   Board  • of   County
Commissioners:  The violations in this  case
included numerous instances of effluent dumping
in excess of amounts  allowed by the operating
permit  for  the South  Cross  Bayou  waste water
treatment plant.  Treated effluent,  which  was
pumped deep underground, migrated into an
underground  source of  drinking  water.    In
settlement of these matters, a Consent Order was
approved by  the Pinellas County Commission.
Pinellas County agreed to pay $120,400 to  DEP
in penalties and costs.  The County is replacing
the deep-well  injection systems at South Cross
Bayou  and  at  its McKay  Creek treatment plant
with reclaim water reuse systems. A report is to
be  prepared  concerning  potential   impacts  of
deep-well injection at South Cross Bayou on the
drinking water aquifer. The total estimated cost
for replacing the systems at the two  sites is  $133
million.

Department  of Environmental Regulation  v.
Cabot Corporation: Cabot Corporation owned
and  operated  a pine  tar and  charcoal facility
("Facility") in Alachua  County, Florida  from
1945 to 1966.  During the Facility's operation,
by-products  containing  hazardous  substances
were dumped into  three unlined lagoons.  In
1983, the Department filed a complaint against
Cabot and other parties, seeking to require Cabot
and the others  to  clean up  the Cabot/Kopper
Superfund  Site  ("Site")  in  Alachua County.
Prior to this action, EPA  had  placed the Site,
which  included the former Cabot  Corporation
property, in the Superfund National Priority List.
Approximately six years after the court case was
suspended,  the  Department filed  a motion to
revive  the circuit court action.  On March  10,
1989, the Department and the Cabot Corporation
signed a Stipulation  for  Settlement whereby
Cabot  agreed to pay  $650,000 to resolve  the
claims between  the parties.

Department of Environmental Regulation v.
Pilot  Properties  Co. and Durham  Utility
Service, Inc.:  This case involved  a wastewater
treatment plant  located in Jacksonville, Florida.
Pilot Properties  Co. ("Pilot") owns an apartment
complex, Turtle Lake Apartments, along with its
wastewater treatment plant.   Durham Utility
Service, Inc. ("Durham") operates the plant under
Pilot's  direction.    Violations at  this  plant
included the routine  discharge of effluent into
areas that were  accessible to the general public,
thereby creating  a   risk  to  public  health.
Subsequent  to   the  Department  obtaining a
temporary injunction, Pilot connected the facility
into the regional system. The Department settled
with Pilot for a penalty of  $10,000.  Durham, a
co-defendant in the civil action,  had a default
entered against  it on  the issue  of liability.   On
June  1, 1994,  a Final Judgment was entered
against Durham Utility Service,  Inc. and  the
Department was awarded $250,000 in penalties.

Florida Department  of  Corrections:    The
Department executed a Consent Order with the
Florida Department of Corrections on May 3,
1994,  concerning  violations  at  its  Sumter
Correctional Institution regarding replacing  and
operating  process  steam  boilers  without  the
necessary air pollution permits. The Department
discovered  these violations  after  receiving an
after-the-fact  construction  permit  application
from  FDC.  The Department  agreed to waive
penalties if FDC agreed to survey its facilities
statewide to identify  all potential sources of air
                                             B-5

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
pollution and submit permit applications for any
facility found not  in  compliance.   The FDC
found  11  facilities  out  of  compliance and
submitted  permit   applications   within  the
timeframe agreed to in the Consent Order.

Florida  Department   of  Environmental
Protection v. NRG/Recovery Group, Inc., aka
Ogden Martin  Systems  of Lake, Inc.:  On
March 3,1994, Ogden signed a Consent Order to
address its exceedance of the permitted one-hour
100 ppmdv CO standard and six-hour 60 ppmdv
SO2  standard.     The  Department   assessed
penalties  against  Ogden   at  $14,799,  plus
Department costs of $350,00.  The Department
found the company in violation of its State and
Federal Prevention  of Significant Deterioration
(PSD) permit conditions.  The corporation owns
and operates two 288 tons-per-day Municipal
Waste Combustors  located in Okahumpa, Lake
County,  Florida.   The Unit  1  combustor  is
permuted  to   combust   51.60   tons/day  of
biohazardous waste as part of its 288 tons/day
load.  Ogden operated Unit 1 for three  six-hour
periods on July 22,  1993 with SO2 emissions at
65, 85,  and 73 ppm. Ogden also operated Unit
2 on  July 16 and 18, 1993 with CO emissions
for three one-hour periods of 183, 238  and 503
ppm. The  violations were found as a result of
self-reporting   and   subsequent   Department
inspections. Along with the assessed penalties,
the company agreed to install two additional SO2
analyzers to monitor the unabated concentrations
of SO2 in  the flue gas prior to the scrubbers.
The company was previously operating two SO2
analyzers to  monitor the  stack  effluent as
required by its  State  and  PSD permit.   The
installation  of the  additional  analyzers  gives
Ogden an early  warning to allow for a more
timely response  to  fuel related SO2 increases.
Ogden implemented a corrective action plan to
abate the CO  excess emissions.    The plan
involved stepped up inspections of the  material
before combustion, and avoidance of wet waste.

Florida  Gas  Transmission:    Florida  Gas
Transmission  was   cited  for  exceeding the
permitted gas consumption rate, late test report,
and failure to timely apply  for a construction
permit extension. Consent Orders were signed
with the penalty for Brevard's 2 units amounting
to $13,128 and Marion County's amounting to
$7,068.    In  another  county,  Florida  Gas
Transmission  was  cited  for  exceeding  this
permitted gas consumption rate, late test report,
and  failure to timely apply for a construction
permit extension. FGT signed consent orders for
all these units. Penalties received are as follows:
Gadsden, $8,400; Washington, $8,400; Santa
Rosa, $7,800.  Still in another county, Florida
Gas  Transmission was cited for exceeding the
permitted gas  consumption rate and failure to
timely apply for a construction permit extension.
FGT signed a Consent Order and paid a $6,150
penalty.

Florida Gas Transmission:  The  Department
has collected a total of $575,400 from Florida
Gas  Transmission (FGT) for 110 violations in
construction in  the  Florida Panhandle.   In
addition,   the   DEP  executed  a  temporary
emergency suspension of FGT's construction
permit,  required  FGT  to contract with  an
independent consulting  firm  to  oversee their
construction  activities,   and   to   submit  a
restoration proposal.  The violations included a
total lack of required Best Management Practices
in certain construction areas,  the  creation of
excessive levels  of turbidity, and violations of
design' specifications  outlined  in  the permit
application for  the  project.   The  violations
spanned the Florida Panhandle and included the
Blackwater  River  State  Forest,  Joe  Budd
Management  Area  and  Outstanding  Florida
Waters. Of the $575,400 total penalty, FGT paid
a cash penalty to the DEP of $375,400.  The
remaining $200,000 will be paid by the company
for  longleaf pine forest restoration  within  the
Blackwater River State Forest.

Hazardous  Waste  Consultants,   Inc.   and
Hazardous  Waste   Services,  Inc.:    Two
hazardous waste companies, Hazardous  Waste
Consultants, Inc. and Hazardous Waste Services,
Inc., and their president, Patricia Ricketson, were
fined more than $1 million in civil penalties on
September  22,  1994  by an  Orlando  County
Circuit Judge. The lawsuit focused on hazardous
                                             B-6

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT f ^
                                                                                       ^
 waste  violations  in  Orange  and  Seminole
 Counties.    Violations  included  storage  of
 hazardous  waste  past  the  ten-day limit  and
 improper  disposal  of  waste.    Portions  of
 hazardous  waste went to the Seminole County
 landfill which is not a hazardous waste disposal
 facility.  Landfill employees were not told they
 were handling hazardous waste.  A dozen small
 bottles were disposed of in Orange County in the
 Tosahatchee State Reserve near residential areas.
 One bottle contained high levels of mercury.

 Kissimmee Utilities: An inspection revealed the
 facility did not have a continuous monitoring
 system to monitor and record the ratio of water
 to fuel being fired in the turbine and had been
 submitting the CEM quarterly  reports without
 having the required  system  to obtain the data.
 Kissimmee  Utilities  agreed  to purchase  and
 install a new monitoring system to comply with
 NSPS requirements.   After signing  the consent
 order and paying a penalty  of  $14,758.80,  the
 company requested an additional meeting.  The
 district, along  with  the Division  air attorney
 Jeanne  Elias,  met  with  Kissimmee Utilities
 explaining  the state's position on the matter of
 enforcing the NSPS requirement.

 Master Packaging:  A stack test conducted at
 the flexographic printing facility revealed VOC
 emissions were 68.7 Ibs/hr vs. the permitted limit
 of 48.2 Ibs/hr. Also, the 65% minimum capture
 and 90% minimum destruction efficiencies were
 not being met.  On a later date, an inspection of
the source revealed there was circumvention of
the control equipment. Master Packaging signed
a Consent Order and will pay a $7,000 penalty.
In  addition,   they  will be implementing a
Supplemental  Environmental Project,  with a
minimum cost of $45,000, intended to increase
the overall capture efficiency from the presses to
the incinerator from the current  permitted level.
Also, the company is to incur a minimum $6,000
cost for an independent environmental audit of
the air pollution sources, which  is to result in a
compliance plan for these sources.

Mur-Shel.  Inc.:  Larry Shelton,  Lois Shelton
and Melvin Powell were arrested on November
 4, 1994, by Florida Game and Freshwater Fish
 Commission officers for improper storage of a
 hazardous  material "asbestos" in Panama City
 and Fort Walton  Beach, Florida and  several
 counts  of theft.   The  arrests  culminated  a
 criminal investigation initiated  by  DEP  Air
 Resources  Management  staff.    The Sheltons
 operated Mur-Shel, Inc.,  an asbestos  abatement
 company.  During 1990-1992,  they  conducted
 abatement projects for a  number of businesses,
 schools and industries in  the Florida Panhandle.
 The  asbestos  waste  was  placed  in  rented
 warehouses in Fort Walton Beach and Panama
 City.  They  declared bankruptcy in  1992 and
 turned all of their assets,  including the contents
 of the warehouses, over to  Mr.  Powell.  The
 asbestos waste is still stored in the warehouses
 pending negotiations  with   Powell   and  the
 Sheltons for cleanup.

 Ogden  Martin:   Ogden Martin  exceeded the
 permitted one-hour average CO standard on July
 6, 1993 and exceeded the permitted six-hour
 average  SO2 standard on July  22,  1993.   A
 Consent Order was executed on March 3, 1994
 with  a  penalty  of $14,799  assessed for  the
 violations.

 Pinellas County Department of Solid  Waste
 Management:    The  Department  issued   a
Warning Letter  on September 2,  1994  to  the
Pinellas  County Department of  Solid  Waste
Management for excessive  downtime  on its
Resource Recovery  Facility,  Unit 3,  carbon
monoxide  continuous   emission  monitoring
system  during the  first quarter of 1994.  The
Department detected the violation after reviewing
the quarterly excess emissions report. PCDSWM
agreed to purchase and  certify a new  carbon
monoxide monitor, replace the existing monitor
control, upgrade communications between  the
monitor cabinet and the data acquisition system,
purchase a backup strip  recorder, rewrite  the
quality  assurance  plan and  upgrade  the  data
acquisition system  at  a  total  cost  of  nearly
$37,000. Because of the PCDSWN's good faith
effort to achieve compliance, the Department
reduced  the  penalty from  $7,530 to $3,830.
PCDSWM will keep the  old  carbon  monoxide
                                             B-7

-------
        FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
monitor as a spare to prevent future excessive
downtime problems.

Polyplastex International: The facility failed a
VOC compliance test on its incinerator. The test
showed actual emissions to be 82.21 Ibs/hr vs. a
permitted  limit  of  12.21 Ibs/hr.   A  retest
conducted on 4/11/94 showed the facility to  be
in compliance.  The company signed a Consent
Order and has paid a penalty of $22,000.

R.P. Scherer Corp.:  R.P. Scherer Corporation
was  found in violation of its annual permitted
VOC emission limit for 1992. A Consent Order
was  signed and a penalty of $18,000 was paid.

South  West  Florida  Water  Management
District:     SWFWMD   was  cited for   no
notification,  no  survey,  no  wetting  during
removal and improperly packaging and disposing
of 2,000 sq. ft. of asbestos containing floor tiles.
As  property  owner,  they  have  completed
abatement, which totaled approximately $50,000
and  have paid a penalty through  an  in-kind
settlement  totaling   $2,700.    Excluding the
subcontractor,  Thunder and Lighting, the two
other parties involved in the case  have signed
consent orders  and  each has paid  $1,800  in
penalties.   A settlement was not reached with
Thunder  and Lightning and a case report was
sent  to the Department's Office  of General
Counsel (OGC).

State of Florida Department of Environmental
Protection  v.  United   States  Naval  Air
Station—Jacksonville:      The   Respondent
operates a facility in Jacksonville, Florida. The
facility has a large industrial  complex for the
repair and overhaul  of airframes  and engines  of
naval aircraft.  Hazardous waste management,
collection   and   transportation    manifesting
activities  are  conducted  at  the facility.   A
departmental  inspection  documented hazardous
waste  violations,  including the operation of a
hazardous waste storage facility without  a valid
permit.  In settlement  of these  matters, the
parties entered into  a  Consent  Order.   The
Respondent agreed  to  pay  $1,000 in  costs,
$30,000 cash penalty and $120,000 in in-kind
penalties.  This case is significant because it is
believed to be the first monetary settlement in
Florida  since  the  Navy  waived  its  immunity
under RCRA.

State of Florida v. Urbano Diaz-Devillegas;
Romulo  Juan Delgado; German  Delgado;
Darwin Mesa and Errol Woon:  During May
through August,  1993, Special Agents  from
EPA's Criminal Investigation  Division Miami
Resident Office, Federal Bureau of Investigation,
Everglades National Park Service Rangers and
members of the Metro-Dade Police Department
cooperatively conducted an initiative to identify
and apprehend individuals responsible for illegal
disposal of construction debris in the wetlands of
southern Florida.   This  initiative was  called
"Operation Sawgrass."  Both aerial and ground
surveillance activities were conducted to detect
and  apprehend violators. Operation  Sawgrass
resulted in detection of a number of potential
violations of the Federal  Clean Water Act and
State of  Florida  environmental  laws.   Five
individuals were arrested  on probable cause by
the agents after they were actually observed in
the  act  of dumping  construction   debris  in
southern Florida,  near the Everglades National
Park.  As a result of Operation Sawgrass,  the
five individuals arrested by the investigative
team have been  successfully  prosecuted and
sentenced.

Tampa Bay Center:  Tampa  Bay Center, Inc.
was cited for removing 400  square feet of spray
on  fireproof coating from the air conditioning
duct.   Samples  contained  30-35%  asbestos.
Violations cited were failure to notify, failure to
survey,  failure to wet, improper bagging and
improper  disposal, and  untrained   personnel.
Tampa Bay Center, Inc. signed a Consent Order
and is paying a penalty totaling $8,000.

Trend  Management:   Violations  included
demolition without notification,  failure to wet
and  maintain  wet, and  improper disposal  of
approximately 5,218 sq. ft.  of spray  on ceiling
containing regulated asbestos containing material
(RACM).  Trend Management has  completed
abatement and has signed a consent order.  A
                                              B-8

-------
      FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT I
                                                                                        X
penalty amount of $18,000 is to be paid over a
24-month period.

Venture Properties:  The owner of Venture
Properties  and OPC General Contractor,  Inc.
have settled with Duval County over the removal
of approximately 94,000 sq. ft. of RACM ceiling
tile. The violations included failure to maintain
adequately wet and failure to seal the material in
leak tight  containers.   Both parties  signed  a
Consent Order  and paid a total penalty of
$36,000.

Waste  Management:    Waste  Management
exceeded their SO2 emission  limit  on  their
combustion turbines. Waste Management paid a
$60,000 penalty and has signed a Consent Order.
As a requirement of the Consent Order, they will
install a desulfurization control system.

GEORGIA

Oxford  Industries, Greenville, Georgia:  A
Consent Order was executed  July 20,  1994
which   concerned  the  illegal   operation   and
overflow of an in-ground concrete tank  that
contained hazardous waste.   Operation  of this
device  is   believed  to  be  the  source of
contamination of the town's public  water supply
well.  In addition to full RCRA compliance and
facility-wide corrective action, the company was
required to  pay  a cash settlement of $99,000
eliminate the use of chlorinated  solvents at the
plant, and replace the town's well at a cost of
$100,000.

U.S.  Navy  Submarine  Base,  Kings  Bay,
Georgia: A Consent Order was signed June 14,
1994    concerning   the   Navy's  improper
identification, storage and disposal  of hazardous
paint waste.  In addition to rectification of the
violations, the Navy was required as a condition
of the  settlement to construct  and operate  a
protected breeding  habitat for an  endangered
species of migratory marine bird and to conduct
a breeding bird survey for declining neotropical
migratory birds.  The habitat and the population
study must  be done in accordance with state and
federal  wildlife protocols.    The agreement
 included  a $10,000  cash  settlement,  plus  a
 minimum of $40,000 that must be spent on the
 endangered species work.

 Young Refining Corp.. Douglasville, Georgia:
 A Consent Order was  executed July  8,  1994
 which concerned the illegal disposal of listed
 refinery wastes into a lagoon. As a condition of
 the settlement, Young Refining agreed to the,
 required RCRA closure, monitoring, post-closure,
 and   facility-wide   corrective   action,  plus
 supplemental  environmental projects that are
 non-mandatory environmental   improvements.
 The $400,000 penalty included $175,000 in cash
 plus expenditures of not less than $225,000 on
 the supplemental environmental projects.

 IDAHO

 Envirosafe Services of Idaho. Inc.:  Envirosafe
 Services   of  Idaho,  Inc.   (ESII)  is  located
 approximately  ten  miles  west  of Grandview,
 Idaho.  The facility  was originally a  missile
 complex  operated by the U.S.  Air Force  until
 1965, and ultimately taken over by ESII in 1981.
 ESII is situated on  layered interbedded gravels
 and clays which overlay regional basalt flows.
 ESII  is  a  RCRA  permitted  facility  for the
 treatment,  storage  and  disposal  of regulated
 hazardous waste.  Treatment processes at  ESII
 include stabilization  via microencapsulation,
 crushing  and macroencapsulation of  hazardous
debris. Land disposal occurs in  a landfill which
 is constructed to meet the minimum technology
requirements.

The State of Idaho, Division of Environmental
Quality (DEQ), performed  approximately 14
 inspections  and record  reviews at  the  site
between September  1992 and June 1993. As a
result  of  these inspections, two Notices of
Violation  (NOVs) alleging 25 violations of the
 RCRA Operating Permit, proposing penalties of
 $137,492, were issued on October 21, 1993. The
 violations alleged  included  failure  to  comply
 with the waste analysis  plan, preparedness and
prevention, contingency plan, manifesting and
LDR  requirements of the permit.  The NOVs
 also  alleged improper treatment  of  hazardous
                                             B-9

-------
      } FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
waste  to  meet  LDR  standards,  inadequate
response to a fire  in the  landfill trench, and
improper   management  of  spent  aluminum
potliners.

Complex negotiations between ESn and the State
of Idaho to resolve the violations took place. On
March 24,  1994, a Consent Order was signed by
the parties to resolve the violations  and  return
the facility to compliance. A penalty of $50,000
was collected. The  Consent Order requires ESII
to cease acceptance  of spent aluminum potliners,
re-evaluate and   improve  the   stabilization
treatment process and modify the permit  where
necessary.     Idaho's   oversight   of  ESITs
compliance with  the  terms, conditions  and
schedules  set forth in the Consent Order is
ongoing.

Stibnite Mining Company:   On October 20,
1993, the Stibnite Mining Company entered into
a Consent  Order through which Stibnite agreed
to  pay $15,000 in penalties  in  settlement of
violations  of Idaho's Water Quality  Standards.
On July 13, 1992, Stibnite reported a diesel fuel
leak from  an above-ground storage tank  at the
company's cyanidation gold mine facility located
in   Valley  County,   Idaho.     Subsequent
investigations by DEQ indicated  that the fuel
leak, itself a violation, was caused by improper
fuel storage and handling techniques.  Additional
violations  discovered during  the  investigation
included   elevated   nitrate  in ground  water,
possibly caused by  leaky cyanidation ponds, and
failure to  characterize and properly  dispose of
hazardous wastes. Groundwater contamination at
the Stibnite  Mine is   of particular concern
because it discharges to the East Fork  of the
South Fork of the Salmon River, a tributary to  a
major salmon spawning and recreational  stream
in   Idaho.     The  mine,   an  unpermitted
(grandfathered) cyanidation operation, is now in
the process  of   mitigation  of  groundwater
pollution according to conditions set  forth in the
Consent Order, and is in the process of obtaining
a cyanidation permit through the DEQ for future
operations.
St. Alphonsus Regional Medical Center, Boise,
Idaho: On December 13, 1993, a Consent Order
was  signed  in  which St. Alphonsus Regional
Medical Center agreed to pay $11,500 in civil
penalties.    This  action  arose  out  of  St.
Alphonsus's alleged failure to adequately control
visible  emissions  from  their  medical waste
incinerator and failure to  obtain a  Permit to
Construct prior to  construction  of a boiler  and
back-up  electrical  generator.   A  notice  of
Violation  was  issued to St.  Alphonsus   on
February 22, 1993 which included four alleged
violations (two visible emission violations  and
two  failure  to  obtain  permit  to  construct
violations) along with a proposed total penalty of
$21,500.    Settlement  negotiations  with  St.
Alphonsus after  issuance of  the  Notice  of
Violation resulted in the reduction of the penalty
to $11,500.

The  issuance of a Notice of Violation to St.
Alphonsus Regional Medical Center was one of
several  similar actions  taken as  part  of  a
statewide initiative to ensure the proper operation
of medical  waste incinerators in Idaho.   In
addition to  payment of  the  civil  penalty,  the
December 13, 1993 Consent Order also  required
St. Alphonsus to  prepare, and submit to IDEQ
for approval, a comprehensive Operations  and
Maintenance Manual which thoroughly describes
the methods and procedures which St.  Alphonsus
will  follow to ensure compliance with the Idaho
Environmental  Protection and  Health  Act  and
Idaho  Code Section 39-101  through  39-130.
Over a period  of  three months, IDEQ and St.
Alphonsus carried on negotiations to determine
the  scope and content  needed to  develop a
meaningful   and   effective   Operations   and
Maintenance   Manual.    These  negotiations
produced a  document that  was  approved by
IDEQ.

ILLINOIS

Pork King Packing Company: In response to
a citizen complaint, Illinois EPA cited Pork King
Packing Co., (a slaughter/packing operation) for
the  unpermitted discharge of blood wastes and
raw wastewater (contaminated  with BOD,  total
                                              B-10

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
suspended solids, and ammonia) through a tile
field  into  a  small stream  tributary  to  the
Kishwaukee River.  The company was also cited
for unpermitted waste storage pits. The State's
March  1994   consent   decree   required  the
company to haul  wastes off-site temporarily.
Pork King  has since constructed a wastewater
treatment   system   utilizing    an   anaerobic
facultative   percolation   three-stage  treatment
lagoon, plus  groundwater  monitoring  wells
installed  around   the   percolation   cell,   as
confirmed by  a State compliance inspection in
November 1994.  Estimated costs for installing
the system were up to $1 million. The facility
paid a $50,000 penalty to the  State,  as well as
the $l,375/week cost of hauling wastes  off-site
for treatment  while negotiations were  ongoing
and the treatment plant was being constructed.
(SIC/201 I/meat packing plants.)

INDIANA

Confined Feed Lot Facilities:   Confined feed
lot operations have  been  found  to  have  a
significant impact on Indiana streams. Non-point
source discharges  from  such  facilities are not
generally regulated  under NPDES permits. The
State  of  Indiana  has  initiated   aggressive
enforcement against a number of feed lots for
violating State  discharge  permits  limits  for:
biochemical   oxygen  demand  (BOD),  total
suspended solids, ammonia-nitrogen and bacteria.
The State's  settlements are  summarized in the
following table:

JPT   Petroleum   Production  Corp.:    On
February 1, 1994,  the  Indiana  Department of
Natural  Resources  and  JPT  signed   an
administrative  agreement  regarding   missed
deadlines for demonstrating mechanical integrity
of three Class II  wells.  The agreement also
addressed minor violations associated with nine
oil and gas wells  in Gibson County.   These
violations were discovered through file reviews
and routine  inspections conducted in  1992.  JPT
agreed to pay  a $3,000 penalty. This action will
prevent contamination of underground sources of
drinking water.   (SIC/131 I/crude petroleum &
natural gas.)
State of Indiana v. James E. Nichols, State of
Indiana v. Custom Finishing Corp.:  James E.
Nichols, the owner of Custom Finishing, Inc.,
located in Indianapolis, Indiana, was sentenced
on January 19, 1994, in Marion County Superior
Court on one count of storing hazardous waste
without a permit in violation of an Indiana state
statute.  Nichols was sentenced to eighteen (18)
months  of incarceration,  of which the court
suspended twelve (12) months.  The remaining
six (6) will be served under a home  detention
program. Nichol's company, Custom Finishing,
Inc. was fined $250,000 on each of two counts
of the information charging the unlawful storage
and disposal of hazardous waste without a permit
at the facility.  Nichols and the  company entered
guilty pleas to the State charges December 29,
1993.

IOWA

In the Matter of the City of Winterset IA.: In
a   case    representing  the   first  criminal
environmental   charge   against  an   Iowa
municipality, the City of Winterset entered guilty
pleas to:  1) Knowingly discharging a pollutant;
2) Knowingly  constructing  a disposal  system
without a permit; and 3) Falsifying a Monitoring
Report.   The  City was sentenced  to pay the
maximum fines on all three  charges, for a total
of $110,000,  with  fines for two of  the three
charges being applied to  upgrade  the sewage
collection system.   The charges arose from an
investigation  that  revealed  that  the  City  had
installed  covert automatic  sewer  bypass lift
stations,  which  avoided sewage backup  into
residential basements by discharging onto streets
or into  storm drains.  In a related  case, the
former  mayor pled  guilty to Non-felonious
Misconduct in Office and received a deferred
judgment.     Charges of  Conspiracy   and
Knowingly  Constructing  a  Disposal System
without a Permit are pending  against the  city
engineer.   The City  also  paid a $20,000 civil
penalty for effluent violations  at its wastewater
treatment facility.
                                              B-ll

-------
        FY1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
KANSAS

In  the Matter  of Dawson  Brothers, Inc.,
Wichita,  KS;:    Based   on  two  separate
inspections of the Dawson Brothers, Inc. facility,
the  Kansas   Department  of   Health  and
Environment finds  that  the Dawson Brothers
have violated K.A.R.  28-31-1 et seq., which
regulates the generation, transportation, storage,
and  disposal  of  hazardous  waste.    The
inspections   revealed  that  Respondents   1)
disposed of waste paint coated tape in the trash
dumpster; 2) disposed of waste Iridide powder in
the trash dumpster; 3) allowed plating process
tanks to leak; 4) stored for over  90  days  over
1,000  kilograms  of  hazardous  waste  paint
thinner, paint filters, paint-related materials, and
bead blast; 5) had not evaluated stored wastes to
determine if they were hazardous; 6) violated
reporting requirements; 7) did  not mark several
drums of hazardous waste as "Hazardous Waste";
8) did not conduct weekly inspections of the
hazardous waste storage area; 9) did not develop
a hazardous waste training program; 10) did not
develop a Contingency Plan; 11) stored ignitable
hazardous waste within 50 feet of the property
line; and 12) did not allow sufficient aisle space
to allow unobstructed  movement of personnel
and equipment.   The Dawson Brothers paid  a
penalty of $41,500.

In  the Matter of  Owens-Corning  Fiberglas
Corporation, Kansas  City, KS:   On April 9,
1993, the U.S. EPA issued a Notice of Violation
alleging visible  emissions in  excess of  20%
opacity. Recurrent  blue-colored carryover from
combined   stack  and   fugitive   emissions,
periodically emanated from the plant.  Owens-
Corning and  KDHE entered  into a Consent
Agreement to resolve the issues raised by EPA's
NOV.    Owens-Corning agrees  to  establish
written procedures  to operate,  maintain, and
clean the control equipment.   Owens-Coming
agrees to conduct visual emissions evaluations of
stack  emissions  from cooling scrubbers and
smoke  strippers and  prepare  an  emissions
reduction plan.
In the Matter of Sunflower Manufacturing
Company, Inc., Beloit and Cawker City, KS:
On February  10, 1994, the Secretary of KDHE
issued a Notice of Proposed Penalty and Order
for Corrective Action  based  on  results of
separate inspections at the Sunflower-Beloit, and
Sunflower-Cawker City, Kansas facilities.  Both
facilities stored wastes over 90 days in containers
not marked "Hazardous"; had not marked open
containers with the accumulation start  date and
the containers were  not in good condition; had
inadequate aisle  space;  failed to  develop a
contingency plan and failed  to develop and
implement a personnel training program.  Beloit
received regulated quantities of hazardous waste
from the Cawker City facility without a permit.
In addition to the above violations, the Secretary
of KDHE  also found that Cawker City failed to
prepare a manifest for the shipment of hazardous
waste; failed to apply  for and obtain  an EPA
identification  number  prior  to   generating,
treating,  storing,  dispo-;ng,  transporting, or
offering for  transportation  hazardous waste;
transported waste without first registering  as a
transporter to a facility which is not authorized;
and failed to  prepare a land disposal restriction
notice for  each shipment of  hazardous waste.
The Secretary assessed a penalty of $57,600 and
an order to come into compliance.

MICHIGAN

Ace Finishing, Inc.:  A July  1994  jury verdict
against Ace Finishing,  Inc.  in Macomb County
Circuit Court, MI, resolved an important  case
taken by the State of Michigan. API is a metal
finishing facility that discharges  to the City of
Warren's wastewater treatment plant. The City
imposed  pretreatment  limits  on API  to  meet
categorical limits and  to prevent harm  to the
wastewater treatment works and the environment.
After a routine inspection uncovered an ongoing
sludge discharge, the  City  began  monitoring
API's control manhole.  Discharges of zinc and
chromium resulted from the company's improper
operation  of its pretreatment system.  API was
diverting all or part  of the  wastestream around
the  treatment  facility.    Manhole sampling
                                             B-12

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
confirmed numerous violations  of  the  City's
sewer use ordinance.

The City requested assistance from the Michigan
Department of Natural Resources and the State
Attorney General in initiating legal action.  API
was  charged  with  felony  violations  of the
Michigan  Water  Resources Commission Act
(1929 PA 245, as amended). The jury returned
guilty verdicts against API for 10 felony  counts
for  the  unlawful   discharge   of  zinc  and
chromium. API has 3 years to pay a $100,000
penalty  ($10,000 per count).  In addition, API
will be  on a  3-year probation.  The court also
ruled that AH had 90 days to reimburse the City
and  the State  for  court costs.    The  total
restitution   to   be  paid   was   $9,228.67.
(SIC/347I/plating and polishing.)

MINNESOTA

LTV Steel Mining  Co.:  On July 27, 1994, the
Minnesota Pollution Control Agency  (MPCA)
and  LTV  Steel  Mining Co.  Steam Electric
Generating Plant (LTV) of Taconite Harbor, MN,
entered  into a negotiated stipulation agreement to
address  environmental problems caused by  a
landslide  of ash  from  LTV's  power  plant.
Almost  exactly a year earlier (on July 28, 1993)
a  landslide  of about 400,000  cubic  yards  of
power plant ash (mixed  with 8,000 gallons  of
mineral oil  from a subsequent spill)  cascaded
down a slope from  LTV  property towards Lake
Superior.  LTV subsequently spent about $10
million  to clean up the ash spilled on the land.
MPCA  also requested  that LTV  conduct  a
dredging survey which determined that about 400
cubic yards of contaminated sediment ended up
in Lake Superior.

MPCA  then proceeded  with an enforcement
action,  citing  LTV  for  violations  of  State
environmental   statutes.     The  stipulation
agreement requires LTV  to pay  a $66,430
reimbursement to the MPCA for expenses related
to the slide and a calculated $240,000 economic
benefit  recovery  (LTV's estimated savings for
not removing the ash from Lake Superior.) The
State will assess the environmental damage after
the Minnesota Dept.  of  Natural  Resources
conducts a detailed survey of native fish habitat
along the north shore of Lake Superior.   The
survey   is  scheduled   for  Summer  1995.
(SIC/101 I/iron ores).

MISSOURI

In the Matter of Barton Nelson, Inc.:  City and
Federal  inspections  established  that  Barton
Nelson, Inc. violated Section  110 of the Clean
Air Act, and Missouri Department  of Natural
Resources regulations when it failed to  obtain
permits for construction presses in 1992. Barton
Nelson also violated 40 CFR Subpart RR, New
Source  Performance  Standards  for  Pressure
Sensitive Tape  and  Label  Surface  Coating
Operations.  The City of  Kansas City, Missouri
and the State of Missouri referred this matter to
the EPA when settlement negotiations between
Barton Nelson and the City/State broke down.
In July, 1994, EPA, the City and State met with
Barton Nelson and reaffirmed the State's bottom
line offer of $100,000. EPA gave the source a
specific time deadline to settle with the State for
the full $100,000, or EPA would initiate its own
action against Barton Nelson.  Barton Nelson,
Inc.  settled  with  the State  of Missouri for
$100,000 the day  before the deadline expired.

In  the  Matter  of   International   Paper
Company. Joplin, MO:  International Paper
Company will pay a $273,000 penalty as a result
of its alleged failure to meet a timetable to close
several  hazardous waste ponds  at its  wood
treatment facility.  Waste sludge from the wood
treatment process, classified as a hazardous waste
due   to  creosote   and   pentachlorophenol
contamination, was placed in nine ponds at the
facility.  In 1986, MDNR had approved a plan to
close the ponds and treat soil contaminated with
hazardous waste.   The Company failed  to
comply with the original plan's timetable and did
not submit a modified closure plan in a timely
fashion. In addition to the penalty, International
Paper is also required to close the ponds and
treat the contaminated soil under a modified plan
approved by MDNR.
                                             B-13

-------
       IFY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
 Norfolk  and  Western  Railway  Co.:    The
 railway  company has paid  $700,000 in civil
 penalties and damages and will provide another
 $2.7 million in payments and equipment to the
 State of  Missouri to compensate for illegally
 disposing of more than 500 containers  waste
 paint at its Moberly railroad yard.  In the civil
 settlement, Norfolk and Western agreed to:  1)
 pay $350,000 in civil penalties to the Randolph
 County School  Fund as required by the Missouri
 Constitution; 2)  pay $350,000  to  the Natural
 Resources Protection Fund;  3) take any steps
 necessary, including closing the site, to bring the
 railroad  yard into compliance with hazardous
 waste management laws and regulations; and 4)
 comply with the Missouri Hazardous Waste Law
 and RCRA.

 Under the terms  of  the criminal plea, Norfolk
 and Western agreed to:  1) pay $1 million to the
 Missouri  State  Parks Earnings Fund to benefit
 the  Katy  Trail  State Park,  2) buy for the state
 $1.7 million worth of material and equipment
 used  in   identifying,    investigating,   and
 prosecuting   environmental  offenses, and  3)
 develop  and implement an  organization-wide
 environmental awareness program. The criminal
 plea  also  requires  the  company  to pay  a
 $500,000 fine -  the highest penalty allowed. The
 company also must pay an additional $500,000
 to the United States for its cost and damages.

 MONTANA

 State of Montana v Continental Lime:  This
 case was comprised of several NSPS, SIP permit,
 and  PSD  violations  which included failure  to
 obtain a PSD permit for SO2 emissions, failure
 to submit quarterly  excess emissions reports,
 failure to install a State-required baghouse for
 control  of  paniculate  emissions,  failure  to
 conduct initial performance tests for particulates
 and opacity, and failure to conduct CEM initial
 performance  tests.   The State used the  EPA
Stationary Source Civil Penalty Policy but then
 reduced the calculated amount by  60%, or a
 factor of  0.4 purportedly  to account for  its
$10,000 per day per violation maximum penalty
compared to  EPA's maximum of $25,000 per
 day per violation (i.e., $10,000/$25,000 =  0.4)
 and did not include the PSD permitting violation
 due to equitable defenses the source had against
 the State, but which it did not have against EPA.
 This resulted in a State penalty assessment  of
 $60,000.   On June  17,  1994,  EPA  issued  an
 NOV and Order to Continental Lime, but in the
 cover  letter  encouraged  CL  to  reach   an
 appropriate settlement with the State.  The State
 and Continental Lime  agreed to the penalty  of
 $144,000 thereby avoiding an EPA civil judicial
 action.   This is an example of State capacity
 building using EPA oversight and  enforcement
 agreements.

 NEBRASKA

 Ash  Grove Cement  Company:    The  Ash
 Grove Cement  Company  will  pay $15,000  in
 accordance with a settlement with the Nebraska
 Department of Environmental Quality (NDEQ)
 and  Nebraska Attorney funeral's Office.   Ash
 Grove Cement  owns  and operates a portland
 cement  manufacturing  facility.  The  Company
 manufactures cement by  heating a mixture  of
 limestone,  clay, sand,  and mill scale in  two
 cement  kilns that are fueled primarily by coal.
 The kilns use hazardous waste as a supplemental
 fuel.  A March, 1993 NDEQ inspection allegedly
 found:    recordkeeping  violations  involving
 inspections of a hazardous waste storage  area;
 improperly marked containers;  no independent
 certification of  the facility's hazardous  waste
 storage  tank system integrity;  and inadequate
 information in the facility's contingency plan and
 training records.

 NEW JERSEY

 State of New Jersey v. Patricia Nazzaro, John
 Martinez,  Augustine  Scalzitti  &  Frank
 Scalzitti: On October 5, 1993, Patricia Nazzaro,
 John  Martinez,  Augustine  Scalzitti, Frank
 Scalzitti and Paul Scalzitti pleaded guilty to  a
 New  Jersey State Accusation for violations of
New  Jersey Code § 2A(2): 17 - 2C, Reckless
Release 'and Abandonment of Hazardous Waste
and Toxic Pollutants.  On November 18, 1993 in
Passaic County  Criminal Court,  John Martinez,
                                            B-14

-------
      FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPOJRT I t*j*^l
                                                                                        i^^AIA^^.y
Augustine  Scalzitti, Frank  Scalzitti,  and Paul
Scalzitti were  each sentenced to  three years
probation, fined $1,000, and directed to perform
100 hours  of community  service.   Patricia
Nazzaro was sentenced to four years probation,
fined $85,000 and directed to perform  100 hours
of community service.  Martinez  and   the
Scalzittis were workers hired by Nazzaro to pack
up  and dispose  of hazardous  printing  and
lithographic wastes from her property located in
Fairfield, New Jersey.  En  route to the dump
site, the trailer caught  fire due to incompatible
wastes   having  spilled  and  mixed  during
transport.    The  smoking  trailer was  then
abandoned.

NORTH CAROLINA

Carolina    Mirror   Company   (North
Wilkesboro, NO:   Carolina Mirror Company
manufactures a variety of mirror products for
commercial use which vary in shape, size and
thickness.   Lead  based paint  is used in the
manufacturing  process to coat  the back  of the
plate glass.  Various activities produce mirror
cullet  which  consist  of off-specification  or
damaged broken  pieces of mirrors, and mirror
generated  by  cutting,  polishing  and  other
processes.  The facility disposed of mirror cullet
in a North Carolina solid  waste landfill  and
stockpiled  cullet  on-site.  Some  of the  waste
exhibits   the   hazardous    waste   toxicity
characteristic.

An  Administrative Order on  Consent with  a
$25,000 penalty pending characterization  of the
mirror   cullet  entered  on  April  14,  1994,  to
address the characterization and remediation of
the  mirror cullet on-site and at the  solid waste
landfill.    The  agreement   was  revised   on
December 7, 1994, to include a potential SEP if
Carolina Mirror   can  initiate  a  Household
Hazardous Waste Collection  Program in Wilkes
County at a reduction in penalty of $0.50 on the
dollar.

Duke . University  (Durham,  NC):    Duke
University is a private institution which generates
and manages hazardous waste from  a variety of
sources.  This Consent Agreement specifically
addresses the management of hazardous waste
located  at  the  Paul  M.  Gross  Chemical
Laboratory.   During a routine inspection as a
Large  Quantity  Generator  (Generator) Duke
University was found to be storing mercury and
dioxin related waste longer than ninety (90)
days.  Therefore,  a Consent Agreement  was
entered with the university to address the closure
of the unpermitted storage unit. The settlement
was entered into February 28,1994, and included
a $10,000 administrative penalty with a SEP in
the amount  of $15,000 which called  for  an
external environmental audit of all environmental
protection programs  and implementation of an
inventory and risk analysis of previously utilized
hazardous waste TSD facilities.

Fawn  Industries  (Middlesex,  NC):    Fawn
Industries is located approximately 1/4 mile from
the nearest resident. The Compliance Order with
Administrative Penalty  was the  result  of the
following violations:  failure to conduct a proper
waste determination; failure to properly label and
date containers of hazardous waste; failure to
maintain  adequate aisle space; and failure to
properly complete land disposal restriction forms.

Total penalty assessed against the facility was
$21,250.  The settlement figure was $10,000 and
approved SEPs estimated at 295,000. Settlement
date was  July 21,  1994.

SEPs consisted of:

•    RCRA Compliance Audit (cost $68,000).

•    Pollution Prevention:
       product substitutions such as water-based
       paints, alternate solvents and re-tooling
       manufacturing process (cost $72,000);

       purchasing in bulk to reduce paint can
       residues (cost $5,000); and

       evaluate  on-site wastewater treatment
       (initial equipment/permit/operation cost
       $150,000 with payback in 2.3 years).
                                             B-15

-------
       } FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
Greer Laboratories:   Greer  Laboratories is
located approximately 1/4 mile from the nearest
resident.      A   Compliance   Order   with
Administrative Penalty was issued as a result of
the following violations:   operating without a
correct  EPA   identification   number;   tank
violations including failure to obtain  a written
certified   assessment,   provide    secondary
containment,  conduct daily  inspections  and
properly label the tank;  failure to  maintain a
contingency plan; and failure to properly train
personnel and maintain  the required training
documentation.

Total penalty  assessed against the facility was
$17,200. The settlement figure was $10,000 and
an  approved  SEP.    The  SEP  consisted  of
development and implementation of a acetone
recovery system (Cost $7,290).  Settlement date
April 26, 1994.

Midway Body  Shop  (Winston-Salem.  NO:
Midway Body  Shop  is  a  small  business
personally owned and operated which performs
body  shop  repairs  and  automobile painting
operations.  The facility  transported five  55-
gallon drums of spent paint thinner to a piece of
property owned  by brother of the  body shop
owner.  Two of the containers appeared  to be
leaking during an on-site inspection. The brother
contended that he was using the spent solvent to
clean painting equipment, though two drums
were labeled "Hazardous Waste."

The Compliance  Order  with  Administrative
Penalty was issued  to address  the following
violations: transporting hazardous waste to a site
that has not  received an EPA  identification
number; failure to manifest the shipment of
hazardous waste; and failure to properly label
and date containers of hazardous waste.  The
penalty was assessed at 75,000.  Review  of the
owner's financial documents indicated that the
company was in poor financial condition  and
could  not  pay  the  penalty.   A Consent
Agreement was entered on September 29, 1994,
in which the owner would pay a $5,000 penalty
and perform eight hours of community service as
a volunteer at the Envirofair in Winston-Salem,
North Carolina.

NC DOT—Ferry Division (Manns  Harbor,
NC):  An Administrative Order on Consent for
NC DOT - Ferry Division was the result of the
following violations:  open container  of waste
paint   thinner;   failure   to   conduct   weekly
inspections; failure to train personnel involved in
hazardous  waste management and  complete
annual training  updates;  failure   to  maintain
training  records; and  the  facility  was   not
maintained and operated to minimize releases.

Total  penalty assessed against the facility was
$25,750.  The settlement figure was $10,000 and
approved SEPs.   Settlement date was  June 6,
1994.

SEPs  consisted of:

•   Waste reduction:
       replace conventional oil   filters   with
       reusable oil  filter screening system and
       use of filtration units on coolant system
       (six  systems replaced at $625, expected
       annual savings of $3,512);

       use  of filter system in parts  cleaning
       machines to  cut down on replacement of
       solvent (initial cost $8,070  with payback
       in 1.06 years); and

       implement a solvent distillation system
       (initial cost $14,625 with payback in 1.5
       years).

•   Recycle Program:
       further development of a ferry customer
       newsletter on recycled paper

       aluminum/cardboard/plastic  collection
       operation  at four additional ferry sites;
       re-use of plastic dredge piping as chafing
       gear on  piling clusters; (Cost  $4,400)
       and
                                             B-16

-------
     FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT f <
       public awareness through use of posters
       and   distributing  brochures  -to  ferry
       customers.

Phillips Plating  Company (Bridgeton. NO:
Phillips Plating  Company  was  cited  in  the
Compliance Order with Administrative Penalty
for the following  violations: failure to properly
determine what waste  is  a hazardous waste;
disposal of hazardous waste in a non-permitted
unit.    The  facility  operated  a  wastewater
treatment  system  under a Clean Water Permit.
The  units,  however,  would  not  structurally
qualify as tanks due to their design, construction
and evidence of  cracks.  Therefore, the units
which received wastewater exhibiting the toxicity
characteristics of hazardous waste due to  the
cadmium  and  lead content were considered
surface impoundments  subject  to  hazardous
waste permit standards.

The total penalty  issued against the facility was
$75,000.   An  ABLE  analysis indicated  the
company  was in  poor  financial condition.   A
settlement was reached November 21, 1994, with
a  $5,000  administrative penalty and a $5,000
SEP commitment to conduct one or more SEP
projects (to be  initiated by December 20, 1995,
and  completed by November  21, 1995).   In
addition, Phillips  Plating will be retro-fitting its
wastewater  treatment  system as  it  undergoes
extensive site characterization and remediation to
address any contamination resulting from the use
of existing wastewater treatment system.

Watts Regulator Co./Regtrol (Spindale. NO:
Watts   Regulator    is   located   in    an
industrial/business  area.  The  distance to the
nearest residence  is approximately 1/4 mile from
the  facility.   The  Compliance  Order  with
Administrative Penalty was the result of the
following violations:   open hoppers of D008
sand  and  failure to properly  label  and date
containers/hoppers;  •• storage  tank  violations
including no written assessment  of the D008
hazardous waste coolant storage  tank  system,
lack of a leak detection mechanism, failure to
remove  released waste  from  the secondary
containment system within 24 hours and operate
the facility in a manner to minimize the potential
for releases, failure to provide overfill protection
equipment, failure to conduct daily  inspections
and failure to document inspections; and failure
to complete annual training for all employees
engaged   in   hazardous  waste  management
activities.

Total penalty assessed against the facility was
$85,999. The settlement was signed February 9,
1994, with an administrative penalty of $37,000
and   approved   SEPs  which   included  an
environmental education/awareness program for
all employees and construction at the baghouse
collection area to eliminate the  possibility  of
baghouse dust handling  problems.

OHIO

Andersons Management Corp.: On November
14,  1994, a  State consent  order with  the
Andersons Ltd. Partnership and the Andersons
Management Corp. was filed in Common Pleas
Court, Lucas  County,  OH.   At Ohio  EPA's
request, the State Attorney General's Office took
action again the Toledo facility on August 14,
1992.  The violations of the Ohio Revised Code
(ORC) 6111 relate to  the unpermitted discharge
of  pollutants   into    the   Maumee  River.
Stormwater  and   subsurface   drainage  was
contaminated with arsenic, lead, phosphorus and
other  pollutants.     The  source  was  glass
manufacturing waste placed in settling lagoons
by previous owners. The  consent decree levied
a $430,000 penalty and required  the following:
compliance with the applicable sections of ORC
6111;    cessation of  discharge  (except  in
accordance with  NPDES   regulations)  and
analytical testing of all wastewater removed from
the facility. (SIC/4221/ farm prod, warehousing
& storage.)

PENNSYLVANIA

ARCO Chemical Company:  ARCO owns and
operates a manufacturing  facility known as the
Beaver Valley Plant, which is  located on the
south bank of the Ohio  River.  Other waters that
flow through or bound the plant  site  include
                                              B-17

-------
       I FY 1994 ENFORCEMENT AND COMPLIANCE ASSURANCE ACCOMPLISHMENTS REPORT
dangerous waste outside in  containers without
lids  or labels,  and failure  to ship dangerous
waste to a facility authorized to  treat, store, or
dispose of it within ninety days of generating it.
The case was settled when Fort Lewis agreed to
pay $15,000 to Ecology, develop a "continuous
inspection  program"  with  the  help  of  an
independent contractor,  and  conduct a detailed
waste streams study of Madigan Army Hospital.

WISCONSIN

Dean Foods Vegetable  Company: During  FY
94,  eight judgments resolved  the  State  of
Wisconsin's case  against  nine  Dean  Foods
Vegetable Co. (formerly known as The Larsen
Company) facilities.  Wisconsin had alleged
numerous violations of  wastewater discharge
permits and State water pollution laws.  Dean
Foods discharged not only excessive pollutants
but also wastewater at excessive temperatures
and  pH  levels.   The company  also failed  to
sample its wastewater on  hundreds of occasions
between  1987 and 1993.  In addition, spills at
several plants resulted in the illegal discharge of
pollutants into State waters.  The spills consisted
of  treated/untreated process   wastewater and
leachate from  sweet corn  silage stacks.  A total
forfeiture of $207,500 was assessed (penalty
breakdown for each facility  is  listed  below).
Wisconsin has a large food canning industry, and
the  whole industry took note  of this  case.
(SIC/2033/canned fruits,  vegetables,  preserves,
jam.)
                                             B-24

-------