EPA-340/1-84-013
Nitric Acid Plant Inspection Guide
Prepared by
PEDCo Environmental, Inc.
11499 Chester Road
Post Office Box 46100
Cincinnati, Ohio 45246-0100
Contract No. 68-01-4147
Task Order No. 44
EPA Project Officer: John R. Busik
EPA Task Manager: Kirk E. Foster
Prepared for:
Stationary Source Compliance Division
Office of Air Quality Planning and Standards
U.S. Environmental Protection Agency
Washington, D.C. 20460
August 1984
-------
DISCLAIMER
This report was prepared by PEDCo Environmental, Inc., Cincinnati, Ohio,
under Contract No. 68-01-4147, Work Assignment No. 44. It has been reviewed
by the Stationary Source Compliance Division of the Office of Air Quality
Planning and Standards, U.S. Environmental Protection Agency and approved for
publication. Approval does not signify that the contents necessarily reflect
the views and policies of the U.S. Environmental Protection Agency. Mention
of trade names or commercial products is not intended to constitute endorse-
ment or recommendation for use. Copies of this report are available from the
National Technical Information Services, 5285 Port Royal Road, Springfield,
Virginia 22161.
11
-------
CONTENTS
Figures , iv
Tables. . . vi
Acknowledgment vii
1. Introduction. 1
SIP requirements 2
2. NSPS Requirements and SIP Emission Limitations 5
NSPS requirements 5
3. Process Description, Atmospheric Emissions, and
Emission Control Methods 8
Process description 8
Atmospheric emissions 21
Emission control methods 25
4. Startup, Shutdown, and Malfunctions 51
Startup _,. ; 52
Shutdown - 53
Malfunctions 54
5. Process Control System and Emission Monitoring
Instrumentation 56
Process monitoring instrumentation 56
Emission control instrumentation . 59
Emission monitoring instrumentation 63
Chemiluminescence . 67
Electrochemical 70
6. Performance Tests and Continuous Monitor Performance
Evaluations 73
Performance tests 73
Pretest arrangements 73
Observing performance tests 74
Continuous monitor performance evaluation. ....... 75
7. Inspection Procedures 77
Plant inspection - 77
~ Estimation of emissions from nitric acid plants 80
References 85
Appendices
A. NSPS regulations „ 87
B. EPA methods 1, 2, 3, and 7 and performance
specification 2 ..... 109
C. Glossary of terms 157
iii
-------
FIGURES
Number Page
1 Basic ammonia oxidation process 9
2 Conversion of ammonia to nitric oxide as a function of
temperature and gas velocity 12
3 Effect of pressure on the oxidation of ammonia at
different temperatures 12
4 Rate constant 13
5 Rate of oxidation of ammonia converter products at 100°C. . . 13
6 Minimum time for absorption-in water of nitrogen oxides
from ammonia oxidation 15
7- Flow diagram of a typical 120-ton-per-day nitric acid
plant using the atmospheric pressure process 16
8 Flow diagram of a typical 120-ton-per-day nitric acid
plant using the pressure process 18
9 Flow diagram of a typical 120-ton-per-day nitric acid
plant using the combination pressure process 22
10 Acid plant incorporating catalytic reduction for
NOV abatement 28
A
11 Extended absorption system for NO emissions control 33
4
12 NSPS test results of NO emissions at nitric acid plants. . . 34
A
13 Flow diagram of the MASAR process 39 •«-
14 Process flow diagram for the Goodpasture process 41
15 Schematic flow sheet of the CDL/VITOK NOV removal process . . 44
A
16 Two-bed Purasiv N process (Vessel A under adsorption and
Vessel B under regeneration heating) for control of NO
in nitric acid plant tail gas 46
-------
FIGURES (continued)
Number page
17 The Bo "line NO recovery system • 47
X
18 Instrumentation flow diagram for ammonia oxidation process. . 57
19 Catalytic reduction unit instrumentation flow diagram .... 60
20 Molecular sieve adsorption unit instrumentation flow
diagram 62
21 Nondispersive ultraviolet analyzer 64
22 Nondispersive infrared analyzer 66
23 Variable wavelength NDIR analyzer 68
24 Gas cell correlation spectrometer analyzer 68
25 Single-beam, dual wavelength NDIR 69
26 Chemiluminescence analyzer ". 71
27 Electrochemical analyzer „ 72
28 Production rate vs. air feed rate 81
29 Conversion of NO tail gas concentration to mass emission . . 82
A
30 Ammonia feed rate vs. production rate 84
-------
TABLES
Number
1
2
3
4
5
6
7
Page
Summary of SIP requirements specific to nitric acid plants. .
Typical compositions of tail gas emissions for nitric
acid plants with and without catalytic combustors
23
NO control methods for nitric acid plants 26
/\
Typical nitric acid plant tail gas emission compositions. . . 27
Operating conditions for treating nitric acid plant
tail gas by catalytic reduction 31
Compliance test results for-nitric acid plants subject
to the NSPS since the 1979 review
Excess emissions data from extended absorption nitric
acid plant operations at CF Industries, Donaldsonville,
LA
*
Design specifications for the Bolme NOX recovery process
applied to a new 220-metric-ton-per-day medium-pressure
nitric acid plant
35
36
48
-------
ACKNOWLEDGMENT
This report was prepared for the U.S. Environmental Protection Agency by
PEDCo Environmental Inc., Cincinnati, Ohio. Mr. Kirk Foster was the EPA Task
Manager. The principal author was Mr. Gary Saunders. This report was based
on an original manuscript by Mr. Edward Wyatt.
-------
-------
SECTION 1
INTRODUCTION
New Source Performance Standards (NSPS) have been promulgated by the
U.S. Environmental Protection Agency (EPA) for nitric acid (HN03) plants pro-
ducing weak nitric acid (30 to 70 percent strength) as authorized under
Section 111 of the Clean Air Act (42 U.S.C. Section 1857 et sej_.), as amended.
Under Section 111, the Administrator of EPA is authorized to develop and
promulgate standards of performance for new stationary sources that are con-
sidered to contribute significantly to air pollution. The nitric acid stand-
ards of performance that were promulgated December 23, 1971, apply to all
nitric acid plants constructed or modified after August 17, 1971.
Each State agency may develop its own enforcement program for NSPS sources
within its jurisdiction. If the program is determined to be adequate, the
State agency may be delegated authority to oversee enforcement of the NSPS.
This authority would be granted over all new and modified sources subject to
a particular NSPS regulation, provided the emission limitations adopted at the
State level for the NSPS sources are at least as stringent as the Federal NSPS
standards.
Effective implementation and enforcement of the NSPS program depends
primarily on the inspection program used to ensure compliance with the appli-
cable emission limitations. For nitric acid plants, this requires a mix of
the recordkeeping requirements and periodic field surveillance.
The purpose of this manual is to aid in the development of uniform evalu-
ation procedures to determine compliance with the NSPS requirements for nitric
acid plants. This manual discusses the operating principles for nitric acid
plants and the control techniques that may be employed to meet emission limi-
tations and describes inspection techniques that may be used to determine
compliance with the regulatory requirements.
This manual is divided into 7 sections. Section 1 is the introduction.
The other six sections are summarized as follows:
-------
o Section 2 - This section briefly outlines the requirements of the
NSPS for nitric acid plants and those of the State Implementation
Plans (SIP's). It is designed to aid and familiarize enforcement
personnel with the regulations applicable to nitric acid plants.
o Section 3 - This section is intended to help familiarize personnel
with the processes and instrumentation involved in the production
of nitric acid, the control equipment that may be applied to reduce
emissions, and the level of emissions or degree of control that may
be expected from each type of control equipment.
o Section 4 - This section discusses some of the effects of startup,
shutdown, and malfunctions on the emissions from nitric acid plants
and some of the steps that may be taken to reduce or minimize their
impact.
o Section 5 - This section discusses the operating parameters that
should be observed during the performance test for demonstration of
compliance. In addition, this section discusses the continuous
emission monitoring testing requirements.
o Section 6 - This section discusses recordkeeping requirements, data
required in these records, emission monitoring techniques, and methods
for evaluating performance ajid excess emission reports.
o Section 7 - This section discusses inspection techniques that may
be used by enforcement personnel to determine compliance with
applicable limitations during routine field surveillance and followup
inspections.
This manual also contains three appendices:
Appendix A: Nitric Acid NSPS Regulations
Appendix B: EPA Methods 1, 2, 3, and 7
Appendix C: Glossary of Terms.
1.1 SIP REQUIREMENTS
Existing nitric acid production facilities not subject to NSPS are subject
to the emission limitations contained in the SIP's. Most States limit the
emissions from nitric acid plants through a general process weight rate regu-
lation. The following States, however, limit the emissions as a result of
regulations that are specific for nitric acid plants:
-------
Al abama
Arizona
Connecticut
Georgia
Kentucky
Louisiana
Maryland
Minnesota
Nebraska
North Dakota
Pennsylvania
South Dakota
Tennessee
Texas
Virginia
Washington
Wisconsin
Wyomi ng
Table 1 summarizes the SIP limits for the States that have specific
requirements for nitric acid plants. The nitrogen dioxide (N02) limits from
existing nitric acid plants generally range from 3.0 to 5.5 Ib/ton of 100
percent acid produced.
-------
TABLE 1. SUMMARY OF SIP REQUIREMENTS SPECIFIC TO
NITRIC ACID PLANTS
State
Alabama
Arizona
Connecticut
Georgia
Kentucky
Louisiana
Maryland
Minnesota
Nebraska
North Dakota
Pennsylvania
South Dakota
Tennessee
Texas
Virginia
Washington
Wisconsin
Wyoming
Pollutant
N02
N02
N02
N02
N02
N02
N02
N02
N02
N02
N02
N0?
N02
N02
N02
N0?
NO
N02
Limit, Ib/ton of 100% acid
5.5
^ g3,b,C g gb,C,d
5.5
25.0e'f 3.0f>g
3.0f,h,1,j 5<81,k
6.5
3.0
3.0Ctl 5.5c'm
5.5
3.0 ' )J
5.5
_J,K
3.0c'n 5.5C'°
600P
5.5
5.5
3.0b
3.0b'C'h 5.5b'c'k
aPlant under construction or in production on or after August 20, 1973.
bWeak acid (30-70% in strength).
cMaximum 2 hour average.
Plants under construction or in production before August 20, 1973.
ePlants constructed before January 1, 1972.
Must be equipped with a continuous NOX monitor and recorder or an alternate
system approved by the Director.
9Plants constructed after January 1, 1972.
Plants under construction or in production before August 17, 1971.
10pacity not to exceed 10 percent.
•'Owner or operator must record the daily production rates and hours of operation.
Plants under construction or in production before August 17, 1971.
Plants under construction or in production on or after February 1, 1972.
'"Plants under construction or in production before February 1, 1972.
"Plants under construction or in production on or after April 3, 1972.
°Plants under construction or in production before April 3, 1972.
''Parts per million by volume.
1
-------
SECTION 2
NSPS REQUIREMENTS AND SIP EMISSION LIMITATIONS
2.1 NSPS REQUIREMENTS
Standards of Performance for new nitric acid plants producing weak nitric
acid were published and promulgated in the Federal Register on December 23,
1971. The regulation (see Appendix A) applies to all plants producing 30 to
70 percent strength nitric acid that are constructed or modified after
August 17, 1971. Designated Subpart G of the NSPS, the regulations are sum-
marized below. In addition to the requirements of Subpart G, nitric acid
plants subject to NSPS are also subject to the monitoring and recordkeeping
provisions of Subpart A.
The current emission standards were reviewed in 1979 and 1984 by EPA to
determine if any changes in the current emission limitations were warranted.
No revisions to Subpart G and the emission, standards are proposed at this
time.
2.1.1 Emission Standards
The allowable emissions limits for nitrogen oxides and opacity are stated
in Section 60.72. Emissions of nitrogen oxides are limited to less than 1.5 kg
(expressed as N02) per metric ton of nitric acid produced (3.0 Ib/ton). Nitric
acid production is expressed as 100 percent nitric acid. Opacity is limited
to 10 percent or less.
2.1.2 Performance Testing
Determination of compliance is made according to performance tests con-
ducted according to Section 60.8 of the NSPS. This section requires the plant
operator to provide a written report of the tests that must be conducted at
conditions representative of the normal operating conditions. Testing for
nitrogen oxides is conducted using Method 7 and the criteria of Methods 1 and
2.
-------
Performance tests are required to be conducted within 60 days of achieving
maximum production rate, but not longer than 180 days after initial startup.
The EPA must receive at least 30 days notice prior to all performance tests.
In addition, the plant owner or operator is responsible for providing the
following performance testing facilities:
1. Sample ports adequate for applicable test methods,
2. Safe sampling platform(s),
3. Safe access to sampling platforms, and
4. Utilities for sampling and testing equipment.
Tests in addition to the initial performance test may be required from time-
to-time by the Administrator as authorized under Section 114 of the Clean Air
Act.
2.1.3 Stack and Process Monitoring
Nitric acid production facilities^are required to install, operate, and
maintain a continuous emission monitor for the measurement of nitrogen oxides
(NOX). Because the units of the emission standard are expressed as N02» the
emission monitor should display the output as N02- Requirements for these
continuous monitoring systems are outlined in Section 60.73, Section 60.13,
and Appendix B of 40 CFR 60 - Performance Specification 2.
The monitoring system is required under Section 60.13 to meet the require-
ments of Performance Specification 2. This performance evaluation is required
to be conducted within 30 days of any performance test required under Section
60.8 and at any other time it is deemed necessary by the Administrator.
In addition to operating and maintaining the continuous monitor, the
plant operator must perform zero and span checks on the monitor at least once
every 24 hours. The plant operator may zero and span the instruments at more
frequent intervals, if desired.
The plant owner or operator must record daily production rates and hours
of operation. A conversion factor established during the performance test
(Section 60.8) or performance evaluation (Section 60.13) to convert from ppm
NOp to units of the standard shall be used to determine excess emissions.
These excess emissions are calculated as the arithmetic mean of any three
-------
contiguous 1-h periods as measured by the continuous monitoring system exceeding
the standard in Section 60.72(a) (1.5 kg/metric ton).
2.1.4 Recordkeeping and Reporting
The recordkeeping and reporting requirements for nitric acid plants subject
to NSPS are outlined in Section 60.7. Enforcement personnel should be particu-
larly aware of the requirements of Section 60.7(b) and (c). Section 60.7(b)
requires the plant owner or operator to maintain records of any startup,
shutdown, or malfunctions that occur at an affected facility, any malfunction
of control equipment, or any periods in which the continuous monitor is in-
operative. In addition, Section 60.7(c) requires the plant owner or operator
to submit a quarterly excess emission report postmarked by the 30th day fol-
lowing the end of each calendar quarter. The excess emission report must
include the identification of any periods of excess emissions, including
excess emissions that occur during periods of startup, shutdown, and mal-
functions. The report must also identify the nature and cause of the mal-
function and the corrective action taken with respect to the malfunction. In
addition, the excess emission report must include the date(s) and time(s) of
any periods when the continuous monitor was inoperative (except for daily zero
and span calibration checks) and the nature of repairs or adjustments necessary
to restore monitor operation.
The plant owner or operator must maintain a record, in a manner suitable
for inspection, of all monitoring data, maintenance records, performance
tests, continuous monitor performance.evaluations, and excess emission reports
for a period of two years. These requirements are outlined in Section 60.7(d).
-------
SECTION 3
PROCESS DESCRIPTION, ATMOSPHERIC EMISSIONS,
AND EMISSION CONTROL METHODS
3.1 PROCESS DESCRIPTION
Presently all weak nitric acid is manufactured by the ammonia oxidation
process (AOP). In general, this process involves the oxidation of ammonia by
air (oxygen) with subsequent cooling and water absorption of the reaction
1 2
gases to produce nitric acid. A majority of AOP plants are located at or
near ammonia plants, and the product acid is used in the production of nitrates.
Thus, ammonium nitrate plants are usually located in the same production
complex with ammonia and nitric acid plants.
Earlier processes, based on the reaction of sulfuric acid on saltpeter
or the passing of air through an electric arc, have been replaced and antici-
pated breakthroughs for the direct combination of nitrogen and oxygen in
•nuclear reactors has not taken place. Also with the new generation of ammonia
plants cutting the cost of ammonia in half, it appears unlikely that other raw
materials for nitric acid would become competitive in the near future and
therefore, the ammonia oxidation process will remain the main source of weak
nitric acid production.
3.1.1 Basic Process Description of AOP
Despite many variations in operating details among the plants producing
nitric acid, three basic steps are common to all: 1) oxidation of ammonia to
nitric oxide, followed by 2) oxidation of nitric oxide to N02, and finally 3)
absorption of N02 in water to produce nitric acid with the release of additional
nitric oxide.
The essential equipment and flow sequence in AOP are illustrated in
Figure 1. Ammonia vapor is mixed with preheated air and passed over a
catalyst, where the ammonia is oxidized to nitrogen oxide. The hot reaction
gases are cooled in waste heat boilers (for heat recovery and steam generation)
and heat exchangers, permitting the nitric oxide to be oxidized to N02 by the
8
-------
VI
LU O£
CJ LU
O 1—
Q- 3
f
C£.
LU
0
oo
CO
i
\_—
4_
>
Juj
.
0
q;—H
LU
CO
LU
Q
O Z
ss
CL, U.
Q
OO C3
V)
d)
o
o
Q.
o
fO
X
O
(C
OS
o
CQ
O>
3
-------
oxygen remaining in the process gas stream. On cooling, water condenses and
some N02 dissolves to form weak nitric acid. The process gas then flows to an
absorber where the nitric acid is formed by absorption of N02> Nitric oxide
is released in the absorption of N02 to form nitric acid and the nitric oxide
passes through the absorber column. The weak nitric acid produced in the
cooling and N02 formation step is introduced into the absorber at the point in
the vertical tower where the acid in the tower is the same concentration as
the nitric acid that is produced. The balance of the oxygen (bleach air)
required to oxidize the released nitrogen oxide is introduced into the bottom
of the absorber. The tail gas leaving the top of the absorber contains resi-
dual nitrogen oxides, a low percentage of oxygen, and water vapor with the
balance of the material being inert nitrogen. The nitric acid produced is
withdrawn from the bottom of the absorber.
The chemical reactions involved in AOP are exothermic and the heat pro-
duced is used to generate process steam superheat and/or to evaporate the
ammonia and to heat process air. The tail gas is typically reheated and
expanded through a turbine to recover "part of the compression power. Many
plants are self-sustaining after they are started by using auxiliary energy
. \
sources.
In summary, the essentials of an ammonia oxidation nitric acid plant are:
1. Converter or oxidation section where the ammonia vapor and air are
mixed and reacted catalytically to oxidize the ammonia.
2. Cooler-condenser section where the nitrogen dioxide is produced by
cooling the reaction gases and weak nitric acid is formed.
3. Absorber section where the cool NCL is absorbed in water to form the
product nitric acid.
3.1.2 Basic Process Chemistry
Knowledge of the basic chemistry is necessary to understand the commercial
plant designs where the pressure and temperature characteristics of AOP chemistry
are most efficiently used. The chemistry used in AOP for the manufacture of
nitric acid involves the following three reactions:
10
-------
4 NH3 + 5 02 + 4 NO + 6
•2 NO + 02 -»• 2 N02
3 N02 + H20 •* 2 HN03 + NO
(1)
(2)
(3)
4
The first reaction (1) is a heterogeneous gas-phase catalytic reaction. The
primary oxidation of ammonia to nitric oxide, with a platinum alloy catalyst,
is carried out at approximately 1500° to 1750°F, with a very short contact
time. This reaction has been extensively studied, but no completely satis-
factory reaction mechanism has resulted. The reaction rate is very rapid
with a 95 percent or more yield of nitric oxide under a fairly wide range of
conditions. In addition to this main reaction, other side reactions are
defined and discussed in Reference 1.
The results of earlier experiments (Figure 2) show the relationship
between contact time (inverse of gas velocity) and catalyst temperature.
These data indicate that the conversion of ammonia to nitric oxide can be
maximized for each gas velocity by the optimum catalyst temperature. This
reaction is so rapid that the percent conversion ultimately depends on the
rate at which ammonia and oxygen can be contacted with the catalyst surface.
Figure 3 shows the effect of pressure on the ammonia-oxidation reaction.
Increased pressure reduces the maximum amount of conversion that can be
obtained for a given temperature and contact time.
The second reaction (2) is a homogeneous, noncatalytic, gas-phase reaction
between nitric oxide and oxygen to produce N02- This is not only a slow
reaction, but it is also strongly dependent on temperature. This reaction is
unique in that the reaction rate decreases with increasing temperature as
shown in Figure 4. This reaction is also strongly dependent on pressure.
Figure 5 shows that increasing pressure causes a higher percent oxidation of
nitric oxide and also reduces the reaction time necessary to reach maximum
conversion in the process.
The third reaction (3) is a heterogeneous equilibrium reaction and con-
sists of the absorption of N02 in water to form nitric acid. The rate of this
reaction is controlled by the following steps:
11
-------
o
o
I—I
CO
UJ
O
o
UJ
<_3
01
LU
a.
100
80
60
40
20
I I I i
DATA OF ANDRUSSOW
i I i
V-GAS VELOCITY,
cm/s .
600
700 800
TEMPERATURE, °C
900
1000
Figure 2. Conversion of ammonia to nitric oxide as a function of
temperature and gas velocity.5
100
oo
a:
o
o
80
_L
_L
700 800 900
TEMPERATURE, °C
1000
Figure 3. Effect of pressure on the oxidation of ammonia at
different temperatures.6
12
-------
20
<" 10
;• 8
E 6
to
to
z
o
f^ 1
§ 0.8
i—*
0.6
DATA OF BOOENSTEIN & LINDNER
O
0.4
i
j_
_L
100 200 300 400 500
TEMPERATURE, °C
RATE CONSTANT FOR REACTION
2 NO + 0,
-»-2 NO,
J O ^^ *" "VQ
Figure 4. Rate constant.7
600
100
NO = 9.3% BY VOL.
02 = 6.3% BY VOL.
60 80 100 120
TIME IN SECONDS
Figure 5. Rate of oxidation of ammonia converter products at 100 C.i
13
-------
1. The oxidation of nitrogen oxide to NCL in the gas phase.
2. The physical diffusion of the reacting oxides from the gas phase
to liquid phase.
3. The chemical reaction in the liquid phase.
Both steps 1 and 2 proceed more rapidly at low temperatures than high tempera-
tures, while step 3 is retarded by low temperature. Because step 3 is inherently
rapid even at low temperatures, it tends not to be a controlling factor in the
formation of nitric acid.
The equilibrium conditions that determine the maximum strength of the
nitric acid are not appreciably affected by temperature, but are favorably
affected by increased pressure, which makes the production of higher acid
strengths possible. Figure 6 shows the effects of elevated pressure on the
overall absorption rate.
Although the efficiency of AOP declines slightly with increased operating
pressure, the nitric oxide oxidation and the absorption reaction rates are
greatly increased by increased pressure.
3.1.3 Commercial Processes for Weak Acid Production
Before the development of stainless iron and steel alloys in the 1920's,
the only material suitable for absorption of nitric acid were stoneware and
acid-proof brick. Because this limitation prevented operations at pressures
greater than one atmosphere, very large-sized equipment was required and
nitric acid strength was limited to approximately 50 percent concentration.
With the advent of acid resistant alloys capable of operating at higher pres-
sures and the desirability to produce higher strength acids, industry decided
i o "5 Q
to construct pressure or combination (dual-pressure)- process plants. '''
A description of each type of process for weak acid production is pre-
sented in the following sections.
3.1.3.1 Atmospheric Pressure Process-
It is very improbable that any new atmospheric process plants will be
built. Although some of these early plants are still in existence, they are
generally used only in a standby capacity. The atmospheric pressure process
shown in Figure 7 is presented simply as a basis for understanding the
other more common processes, because they can be considered derivatives
of the atmospheric pressure process.
14
-------
10% NH3 AT CONVERTER, 5% i
CURVE A -'8 ATMOS., 92% CONVERSION* 50% NHO
IN EXIT GAS
IN CONOENSATE
CURVE B -
100
40
UJ
£20
UJ
Q_
1 ATMOS., 96% CONVERSION, 25% NHO, IN CONDENSATE
I
I
I
100 200 300 400 500
TIME IN SECONDS
600 700
Figure 6. Minimum time for absorption in water of nitrogen oxides
from ammonia oxidation.1
15
-------
?
lou.
o
01
CO
„
10
ur>
CO
CM
i— «
-^ UJ
O 2
> O
x
a:
3=
§
o m o i-»
O CO
o o
A
in
O 0 O
»•
O 0
in co
co"
O 0
§(«
^
o LO
m cn
O m ro o **•
in Cn -
fO VJO
* 0
* uj co ;>
3: o_ to ro
«j Lu ce o o
u_ i— a. • as z
m
CM O CM •
o ^* *s* ^^
0
o
o o
o o
LO m
co cn co
00* CO
CM r*-
r-« f-^. CO
CM r-s
0 r^ 10 co
•a- ««• m en
o CM «*• co
\Q LO CO
t— < U3
r-* co m
co o •-*
co cn ro
0* 0 00
CU (*^
in
o
V
** ** ,- +j ** JH»
0^03^^
CO
CM O O O
O CM CM Z CM CM
2= o :c :n n: 3:
0)
c
•r—
trt
3
•M
C
, O)
. CO O
•o o
I S-
i- Q.
ou
Q. O)
C 3
O to
4-> to
I (U
O S-
CM O.
r-1
O
r— «r"
(T3 S-
o cu
a. o.
>> to
-M O
re ->->
o
3
cn
16
-------
In the atmospheric process, ammonia oxidation and conversion to nitric
acid of the resultant nitrogen oxides is carried out at pressures near atmos-
pheric. Briefly, this process includes the following steps.
Step 1. Liquid ammonia is evaporated and the resulting gas is collected
and pumped by a fan to a mixer where filtered air is added. The resultant
mixture of ammonia and air, usually containing from 9.5 to 11 percent ammonia,
is brought in contact with the catalyst, where the ammonia is oxidized to
form nitrous oxide and water.
Step 2. After leaving the catalyst, the nitrous gases are cooled in
the air preheater and the waste heat boiler where nitric acid is oxidized to
NOp. The gases are further cooled in a series of cooler-condensers in which
nitric acid begins to form. The cooler-condenser will produce an acid con-
taining approximately 20 to 22 percent nitric acid (HNOo). The condensate
formed during this step is conveyed to the absorption section of the plant
where it is passed through a series of absorption towers. The final product
(45 to 52 percent HNOg) is drawn off from the last absorption tower.
Considering current technology, the main advantages of atmospheric-type
plants are the lower platinum consumption and higher conversion efficiency
from ammonia to nitric oxide in the burner. However, the improvement of
platinum filter design, the efficiency of pressure burner units, and the
greater absorption efficiency of pressure processes in the production of
increased strength acid, make pressure processes much more economically
attractive.
It should be noted that in the atmospheric pressure process, the low
oxygen content of the tail gas and the low absorption efficiencies of NOg
require a large number of towers to reduce the nitric oxide content of the
tail gas to the acceptable figure of approximately 0.2 to 0.3 percent nitric
oxide.
3.1.3.2 The Pressure Process—
The typical pressure process plants shown in Figure 8 are the result
of technical advances in nitric acid production since the 1940 through 1950
time period. During World War II many of the pressure process plants were
built to manufacture munitions, but these facilities did not have catalytic
reduction units or turbine expanders. The first pressure-type plants operated
17
-------
I— 1
<_) "X.
*< LU
CO — 1
LU
U.
LU
O •—•)
en
CO
Q£
UJ
t-
2
0
0
in
o
o
in
i-H
0
in
^~
0
10
0
r-.
u.
o
UJ
cc
£
a.
0
CM
in
CM
r-H
in
CT>
o
CM
t— <
§
o
CM
,— 1
r— <
OJ
•— t
0
0
en
V)
a.
LU
CO
in
UJ
£
1 »-"• ~* CO 1 1 CM O
• z: co ^- CM
O 0)
o m 10 t l 2
• • O ">O
o a o\
i i i i i i i i
1 1 1 1 O O 1 1
VO *f
i i i en i i co
O CO
1 1 CM 1 O O 1 1
• tn 10
.— i i i
o o
•$- m
o »— « ^
O CO O *3- 1 1 O
en in en
r-<
o i i co i i tn
o
-H o r-
i i i crt i i co
O CO
§i i i i in t i
0
i— i •
o
(_**(_(_4J**^J**
O i— O O 3 +•> r—
> 0 > > 36 4J 0
CO CO
gCM O O O CM
zgi^JlaTlariS
t/)
CO
a>
u
o
a.
O)
s_
3
CO
V)
(U
s-
Q.
O)
-M
a
ro
O
(O
o
•r—
S-
(O
-o
S-
a>
a.
I
o
CM
(O
o
(C
(O
cn
(a
o
GZ
00
(U
18
-------
at approximately 80 to 130 pounds per square inch absolute (psia) and had
reciprocating compressors that recovered about 40 percent of the compressor
power. In the 1950's the development of high temperature designs for gas
turbines permitted improved power recovery and the use of centrifugal compres-
sors permitted the production of air hot enough to be used directly in the
converter. A catalytic reduction unit was added to the process to further
improve power recovery. By heating the tail gas to approximately 1250°F
before expansion, the catalytic reduction unit has resulted in the recovery
of all the power required for air compression. The side effect of reducing
the nitrogen oxide concentration in the tail gas was an added advantage as
air pollution regulations have been broadened in recent years to include the
control of nitrogen oxide emissions.
The pressure process, in which both ammonia oxidation and conversion of
the resultant nitric oxides are carried out at greater than atmospheric
pressure, consists of the following steps.
Step 1. Liquid ammonia is evaporated either directly from the heats of
formation of nitrous gases or nitric acid, or indirectly by steam generated
from the recovery of the heats of reaction in waste heat boilers.
Step 2. Air is compressed to a pressure that varies somewhat from plant
to plant but in the most recent plants, is approximately 110 pounds per square
inch gauge (psig). In large capacity units, the compressor used is generally
of the centrifugal type.
Step 3. The streams of filtered ammonia gas and air mix and the mixture
then goes to the burner. Air, delivered by centrifugal compressors, is usually
hot (450° to 500°F) enough to avoid preheating. If reciprocal-type compressors
are used, however, the air must be preheated. In both cases, the temperature
of the air before being mixed with ammonia must be approximately 500°F. In
the burner itself, the temperature at the catalyst is maintained at approxi-
mately 900°C (1,650°F).
Step 4. If power recovery, is adopted, the gas leaving the burner passes
through a heat exchanger to lower the tail gas temperature to approximately
950°F. The burner gas is then cooled at a pressure of 150 to 225 psig. A
catalyst recovery filter is usually installed at the cold end of the boiler.
Finally, the gas is cooled in a cooler-condenser in which most of the water
produced by the oxidation reaction is removed as 40 to 45 percent nitric acid.
19
-------
Step 5. The gas then flows into the absorption system where the oxidation
of NO to N02 is then completed and these oxides are absorbed in water to form
nitric acid.
Step 6. Weak acid from the condenser is introduced at an appropriate
point in the absorption system. The absorption system proper may consist of
one bubble-cap tray or of a cascade of absorption drums, each equipped with
one tray and several coolers. In the bubble-cap tray tower, the coolers are
placed directly on the trays around the bubble-caps.
Step 7. The product acid is bleached in the lower section of the
absorption tower itself or in a separate bleacher. The acid produced (57
to 60% HNOg) does not contain more than 0.05 percent nitrous acid.
The overall efficiency of absorption under pressure is sufficiently high (98
to 99%) to permit the elimination of alkali scrubbers.
The main advantage of the pressure type plant when compared with the
atmospheric pressure type plant of the same efficiency is a significant reduc-
tion in equipment volume required for oxidation, heat exchange, and most
importantly, absorption.
3.1.3.3 Combination Process—
In the combination process for nitric acid production, ammonia oxidation
takes place near atmospheric pressure while absorption occurs at pressures
much higher than atmospheric pressure, thereby using the optimum economic
efficiencies for both conversion and absorption. The oxidation of ammonia
typically occurs at pressures from atmospheric to 50 psia. The resulting
nitrogen oxides are then cooled and compressed to approximately 50 to 215 psia
for absorption. The lower conversion (oxidation) pressure gives the highest
conversion efficiency at a lower operating temperature (1500°F) which prolongs
the life of the catalyst by a factor of 3 to 5 over the pressure process. The
high pressure absorption, using smaller equipment, gives a high absorption
efficiency and higher strength acid. This process, popular in Europe, is
finding increased popularity in the United States. Increasing cost for elec-
trical power, catalyst material, and ammonia, coupled with increasingly
stringent nitrogen oxide (NO ) emission regulations are causing this type of
A
plant to be given increased consideration.
20
-------
In this type of plant (Figure 9), the nitrous gases leaving the atmos-
pheric oxidizer pass through condensers where they are cooled to a temperature
close to that of the cooling water. A stainless steel turbo-compresser
compresses gases to a pressure that may vary from 50 to 215 psig according
to the type of plant.
Because these nitrous gases contain an excess of air, this compression
helps considerably in completing the oxidation of NO to I^ and N^O*. The
compressor is followed by a condenser from which 33 to 42 percent nitric acid
is withdrawn. This acid is pumped to the absorption tower and introduced at
the level in the tower that corresponds to the same acid strength.
The acid condensed prior to compression is added at the appropriate
points in the absorption system. In order to recover the power consumed for
air compression, the tail gas leaving the absorption system is preheated by
heat exchange with the hot nitrous gases leaving the ammonia burner before
being released to the atmosphere by an expander mounted on the shaft of the
gas compressor.
This combined scheme claims the advantage of higher ammonia oxidation
yield and lower platinum loss, added to higher absorption efficiency and power
recovery.
3.2 ATMOSPHERIC EMISSIONS
Ammonia oxidation nitric acid plants have one point of emission, the
tail gas stack. The tail gas from nitric acid plants contains no particulate
matter, and the temperature of the tail gas is high enough to prevent any
mist formation as a result of water vapor condensation. Typical compositions
of tail gas emissions from plants operating with and without controls are
presented in Table 2.
21
-------
1
o <
>— a.
U UJ
«t >
i
)
f
a:
UJ
CO
as
1 . 1
0
32
O
1
O
o
.J*
a
z: o
8af
X
00 E
cc.
CM •— »
s
s
o
in
CO
-t3-
O
LO
^
CO
0
o
•o^
ro
o
m
M
r-H
0
in
o
r-i
CO
O
CO
CM
in
0
CO
U3
m
**"
0
in
in
CO
in
0
m
CM
-C
£
§
U.
S ° 2 o °*
00*
m o CD o o
co ^r *-< T-< *
co o"
O 0
to LO
o o
CO
o uo
IT)
CM
m o •-* co
°^ ^*" So
CM
O O O •-* CM O
^-« m co co
o ^r o to o CM
m • •
in o\ *£>
•— *
o m CM r-.
CM O CO
t-H r-4
o in co
^° o
CM
o un o
P-. O
t-H r~t
U.
0 O)
M M
z§ ** a< ** a<
h- UJ ( — « —
So: o i— o r—
Z3 > 0 >• O
UJ CO > =»
Q- CO CO
E IAJ 3= CM
in co
i—i ^t"
en
in co
f-* q!
en
0
o
0 0
o* o
IO ^~
en co o o
o co Ln in
f-^ rH CO
10 ^H
^j- en
> OJ
(O O
•o o
S- CL
1
O
d)
1-
CVJ O.
i— O
•r— (O
Q. C
03 O
O
(O
O)
(O
o
cr>
o>
22
-------
TABLE 2. TYPICAL COMPOSITIONS OF TAIL GAS EMISSIONS FOR NITRIC ACID PLANTS
WITH AND WITHOUT CATALYTIC COMBUSTORS9
Tail gas emissions
Nitrogen oxide, ppm
Nitrogen dioxide, ppm
Oxygen, percent by volume
Temperature, °F
Pressure, psig
Absorber exit
1000-2000
1000-2000
2-4
90-100
85-95
Catalytic
combustor exit
40-350
0-350
0-1.5
1000-1300
75-90
The NSPS specify that NO emissions must not exceed: 1) 3.0 Ib of nitrogen
/\
oxides expressed as NO^ per ton of nitric acid (100 percent) produced (3-h
average) and 2) a plume opacity of 10 percent. The emission limit of 3.0 Ib
of nitrogen oxides per ton-of acid produced is equivalent to approximately
209 ppm (0.0209 percent by volume) concentration of nitrogen oxides in the
process tail gas in a typical plant.
Nitric acid plants are primarily designed to achieve a specified production
rate (tons of nitric acid in a water solution) using a given quality of ammonia
feed. Other considerations necessary for the design of a plant are the speci-
fications for certain auxiliary utilities such as cooling water, condensate
quality water, boiler feed water, electricity, and process instrumentation.
When a plant is designed for a certain production rate, acid strength,
and emission rate (Ib NO per ton 100 percent acid), an increase in the pro-
duction rate and/or acid strength will typically increase the NO emission
/\
rate. This is due to the fact that increasing the production rate decreases
the time available for the oxidation of the nitrogen oxide to N02, decreases
the absorption of the N02 resulting in efficiency losses and overloading of
the catalytic reduction unit (if used), and increases the amount of NOX
emissions per ton of acid produced. On the other hand, if the plant is
operated below the production rate and/or the acid strength is reduced, the
time available for reactions and absorption is increased and a reduction of
NO emissions would be expected.
23
-------
3.2.1 Types of Emissions
3.2.1.1 Nitrogen Oxides--
Nitrogen oxide (NOV) emissions consist mainly of NO and N00 and are
« c.
emitted to the atmosphere in the absorber tail gas after it leaves the ex-
pander and final heat exchangers. These emissions vary with the plant design,
maintenance practices, production rate, and absorber efficiency. Absorber
efficiency can be increased by higher pressure and Tower temperature. This
will result in lower NO emissions. Emissions of NO from well -maintained
* x
and properly operated nitric acid plants without catalytic combustion devices
or extended absorption average from 2000 to 3000 ppm. However, NO emissions
as low as 1000 ppm have been reported at many existing plants. Catalytic
combustion devices can reduce the N02 content significantly by reducing the
NO to
Catalytic combustion can also aid in energy recovery. Because N0
is the cause of the reddish-brown plume that may be observed, the effectiveness
of the catalyst combustion process is evidenced by the colorless tail gas
stack conditions.
3.2.1.2 Acid Mist--
Acid mist emissions do not occur from a properly operated plant. Acid
mist is present in the gases leaving the absorber. These emissions, however,
are largely removed by centrifugal collectors or mesh mist collectors before
the gases are heated prior to entering the catalytic combustor or turbo-
expander. Trace quantities of acid mist present in the tail gas are vaporized
as the gas is reheated.
3.2.1.3 Visible Emissions--
Visible emissions of a reddish-brown color occur from uncontrolled nitric
acid plants due to the N02 in the exit gas. The opacity of stack gases varies
with the N02 content and the stack diameter. The approximate visible threshold
concentration of N02 is given by the suggested equation:
10
Co =
2400
where
d s stack diameter in inches
Co - visible concentration, ppm
24
-------
Thus for a 12-inch diameter exit stack, a visible emission would occur at an
NOp concentration of approximately 200 ppm. With larger diameter stacks, the
visible plume would occur at lower NOp concentrations. The acid production
system and storage tanks are the only significant sources of visible emissions
at most plants. The amount of emissions from storage tanks is considerably
less than the emissions from the stack. '
3.2.1.4 Reducing Compounds—
Through the application of catalytic reduction systems, the NO abatement
A
of nitric acid plant tail gas can result in the production and emission of
hydrocarbons, carbon monoxide, and other reducing compounds. These compounds
are produced as a result of the reducing atmosphere in the catalytic system.
Although little data are available on the subject, it is expected that for a
given system, reducing compounds are produced in inverse proportion to NO .
/\
The relevance of these secondary emissions is not well-documented. To date,
no attempt has been made to control the release of reducing compounds to the
atmosphere.
3.3 EMISSION CONTROL METHODS
After the promulgation of the 3.0 Ib of NO per ton of acid NSPS in
X —
1971, catalytic reduction was the primary NO abatement system installed on
/\
new nitric acid plants until 1975. With the developing natural gas shortage
in 1975 and the advent of a proven alternate NO control technology (extended
/\
absorption), the entire nitric acid NO control situation was radically changed.
X
From 1975 through mid-1978, 50 percent of new nitric acid plants employed the
extended absorption process for NO control. Since 1979, all but one of the
11
new or modified nitric acid plants were designed to use extended adsorption.
Although the extended absorption process can achieve the NSPS level of NO
/\
control, it is not able to reduce emissions to the same level obtainable with
catalytic reduction. Other methods used for NO control on nitric acid
X
plants include wet scrubbing, chilled absorption, and molecular sieve adsorption.
The various NO control methods are summarized in Table 3. Table 4 provides
X
typical tail gas analyses from uncontrolled plants, plants employing catalytic
reduction, and those using the extended absorption process.
25
-------
TABLE 3.
NOV CONTROL METHODS FOR NITRIC ACID PLANTS1'2
X
Process
Methods
Impacts
Catalytic reduction
(nonselective)
Catalytic reduction
(selective)
Extended absorption
Wet chemical scrubbing
Chilled absorption
Molecular sieve
adsorption
Reduce NOX and 02 with CH*,
H2 or CO to form N2, H20,
and C02. Pt or Pd catalyst
used.
Reduce NOX with NH3 using a
Pt catalyst to form N2 and
H20.
Uses an additional absorp-
tion unit.
Scrubbing tail gases with
urea, NHs, NaOH, sodium
carbonate or potassium
permanganate.
NOX solubility increased in
chilled H20.
Uses synthetic zeolite ad-
sorbent/catalyst bed. NO
recycled by thermal regen-
eration.
Fuel penalty usually
required. Operable at
any pressure. Energy
recovery possible.
Energy recovery not pos-
sible. Operable at any
pressure.
Increases yield of HN03.
Requires inlet pressure
of 760 KPa.
Operable at any pressure,
but performs better at
high pressure.
Usually cannot meet NSPS
alone when plant operated
at capacity.
High energy and capital
requirements.
sions <50 ppm
NOX emis-
26
-------
TABLE 4. TYPICAL NITRIC ACID PLANT TAIL GAS EMISSION
COMPOSITIONS (PERCENT BY VOLUME)
Component
or tail
gas
NO
N02
N2
°2
H20
co2
Plant control method
Uncontrolled3
0.10
0.15 :
96.15
3.00
0.60
Catalytic
reduction
0.01
trace
94.20
trace
3.80
2.00
Extended ,
absorption
0.015
96.00
3.50
0.50
Conventional design has been 98 percent absorption efficiency (this
composition is typical of the tail gas before catalytic reduction).
This plant is controlled by increasing the absorption efficiency to 99.8
percent plus.
3.3.1 Catalytic Reduction1'2
3.3.1.1 Nonselactive—
As illustrated in Figure 10, the nonselective catalytic reduction unit
is an integral part of the nitric acid plant design when it is used. Converter
effluent gas is used for preheating the tail gas from the absorption tower.
In the catalytic unit, fuel is burned to generate heat and reduce NO emissions
X
in the tail gas. Hot exhaust gases from the catalytic unit are directed to
an expander to drive the ammonia converter process air compressor. To keep
the expander inlet temperature below its design maximum, typically 677°C
(1250°F),% a waste heat boiler is sometimes used directly after the catalytic
unit. Prior to venting the tail gas to the atmosphere, a waste heat boiler
recovers energy from the expander outlet gas in the form of steam.
In nonselec£ive reduction, absorber tail gases are mixed with a fuel such
as methane, carbon monoxide, or hydrogen and heated to the required ignition
temperature. Ignition temperatures range from 150°C to 200°C for carbon
monoxide and hydrogen and from 480°C to 510°C for natural gas (methane). The
absorber tail gas fuel mixture is passed to the catalytic reduction unit
27
-------
C
o
~u >
4 /
r \ \
Q- z:
O — 1
00 O
CQ 0
>.
«c
LU
i
O)
-(->
(O
jQ
s_
o
q-
o
4J
O
O)
S-
o
03
O
CD
s=
03
O
Q.
S-
O
O
C
03
O.
-o
O)
S-
28
-------
where the fuel reacts with NOX and oxygen to form C02, water, and nitrogen
over a 0.5 percent platinum or palladium catalyst. When methane (natural
gas) is used for fuel, the following reactions occur:
CH
20
C0
2H20
CH- + 4N00 ->• 4NO + CO,
4NO
C0
2H20
2H20
These reduction reactions are highly exothermic. The temperature rise
resulting from catalytic reduction is 128°C for each percent oxygen burnout
when methane is used as the fuel, and 150°C when hydrogen is employed. Due
to the catalyst thermal limitation, the final reduction reaction must be
limited to a temperature of 843°C (1550°F). It is interesting to note that
the second reaction given above does not decrease total NO emissions; it
}\
simply converts N02 to colorless NO.
Although the catalyst thermal limitation is 843°C, the-maximum tempera-
ture limit for the turbo-expanders is approximately 650°C (1200°F). Thus,
absorber tail gas with greater than 2.8 percent oxygen will require cooling
to prevent catalyst deactivation. Even greater cooling is required if power
recovery is practiced. In the single-stage units, ceramic spheres are used
as catalyst supports, at hourly gas space velocities up to 30,000 volumes per
hour per volume. Single-stage units can only be used when the oxygen content
of the absorber tail gas is less than 2.8 percent. The effluent gas from
these units must be cooled by heat exchange or quenched to meet the temperature
limitation of the turbine. Two-stage reduction units often employ honeycomb
ceramic catalysts, with hourly space velocities of approximately 100,000
o
volumes per hour per volume in each stage. One system uses interstage heat
removal while another feeds only 70 percent of the fuel to the first stage
and uses the remaining 30 percent (preheated to only 250°F) for contact '
9 12 13
interstage cooling. ' ' This second system eliminates the need for coolers
or waste heat boilers. Historically, experience with single-stage reduction
units has been more satisfactory than that obtained with two-stage units.
29
-------
Usually, 90 to 95 percent of the nitrogen oxides in the tail gas are
decomposed by nonselective catalytic reduction. Table 5 summarizes the
typical operating conditions for both selective and nonselective reduction
units. Fuel requirements for nonselective reduction with natural gas are
typically 10 to 20 percent over stoichiometric, and some hydrocarbons and
CO are discharged in the treated tail gas. Less surplus fuel is required
when hydrogen is used. The particular process chosen is governed by a
balance between capital costs and the availability and cost of fuels. Sig-
nificant economic return, however, can be obtained by recovery of heat
generated in the reduction unit, depending on the overall plant heat balance.
3.3.1.2 Selective—
In the selective catalytic reduction process, ammonia is added to absorber
tail gas and the mixture is usually directed through a honeycomb support
platinum or another type catalyst. The following reactions occur and reduce
the nitrogen oxides to nitrogen:
8NH3 + 6N0
4NH + 6NO
5N
Proper operation of this process requires that the tail gas stream be maintained
between 210°C and 270°C.
Above 270 C, ammonia may be oxidized to NO and
/\
below 210 C, ammonium nitrate may be formed. This process can operate at any
pressure. Many systems, however, operate at ambient pressure. User experience
with this process has been good with catalyst lifetimes of over two years
reported. The cost of ammonia,' however, may not be competitive with other
fuels even when less is required. On the other hand, the process does not
require any gas stream cooling, and its lack of pressure sensitivity makes it
applicable as a retrofit control device for existing low pressure nitric acid
plants.
3.3.2 Extended Absorption
Prior to promulgation of NSPS in 1971, most nitric acid plants were
designed with absorption efficiencies of 98 percent and an emission rate of
15 to 17.5 kg of NO (as N09) per metric ton of nitric acid produced. Since
/\ £
1975, increasing the design absorption efficiency has become the preferred
30
-------
^^-
CO
oo
^^
U3
i
1
1— H
•a:
1 —
h-
-
U 1
^c
oo t—
^^ ^^
O 0
*— 1
|__
*— 1
f^
3PT
o
0
fO *l—
O 4->
CJ
ai 3
^> ^j
•i— CD
4-> S-
0
O>
r—
CD
oo
E
O
•i—
4->
CJ
3
T3
O)
S-
o
•1 —
4J
^
(C
4-5
fO
O
a>
>
«r^
•4-^
o
a>
lu
(/)
c~
O
to
c
o
•^
4-5
•r—
-a
s=
o
CJ
to
to
a>
CJ
o
s_
Q.
(G (G
•i — -i—
C £
0 0
Jl
OJ
OJ
E
rt3
Q.
O
s-
a.
#i
to
CO
CD
c
01
>
o
4-> CO
fO TCI 1
2: z: CM
^^
to
« O)
to en
fO ns
to i — en 4-5
r— CU 10
O> 3 r—
3 t- T- <+-
4- (O O
~O 4-5
O) O) S-
r— E c: a>
•O 3 *^ ^~>
(8 to E
tO tO OJ 3
=> 0 CO
D_ CO I-H O
CU
en
(O «tf-
4-5 O °
to O i— I
O 1
"a « o cr>
c TD o to
CM CL to ^f O
cu o
en 4->
fO CU •» CU
t_J •< ,_ (]J = (/,
C i- 3 R3
T3 r— -i- 3 i— cn
CU CU 4-5 O
s- > E (0 > i—
S- 3 S- •.-
ai a> E cu «n3
M— O -r— Q. i — 4-5
cu to c E cu
S- Q. -r- CU 3 4-
D- OO S 4-5 LU O
O
1
o
CM
cn
ar—
^
e|_
(8
4J
C
o
o
to
ro
cn
fM.
•1—
| ^
E
O
s-
M-
CM
f—
r—
fO
CM
O
O
CO &«
^-1 ^
CJ
o
^
cu
to
i_
cu cu
H3 3
•i— (O
X S_
o cu
S- CL
CL E
CL CU
.
CM
I— 1
•
fO
^J
cu
cu
CL
to
cu
1
t ,
•r—
CD
• •
cu
o
S-
3
o
oo
31
-------
control method for NO emissions from new nitric acid plants. Thus the
X
extended absorption process, in which a second absorption tower is added in
series to the existing or first absorber, is not really an add-on control
device for new plants but an integral component of the design for new nitric
acid plants.
The Grande Paroisse version of the extended absorption process is illu-
strated in Figure 11 along with typical operating conditions. The nitrogen
oxides in the tail gas from the first absorber is contacted with water in the
second absorption tower to form additional nitric acid. The weak acid from
the second absorber is recycled to the first. Thus, no liquid effluent is
created by this process. Process economics usually require inlet gas pressures
at the absorber of at least 730 Kilopascals (kPa) or 107 psig, and cooling of
the tail gas is generally required if the inlet NOV concentration is greater
8
than 3000 ppm. The D.M. Weatherly Company's version of the extended
absorption process uses cooling water refrigeration to decrease the required
volume and number of trays in the second absorption tower. In this version
of the process, two cooling water systems are used for cooling the absorbers.
The entire second absorber and approximately one-third of the trays of the
first tower are cooled with water at approximately 7°C (45°F). Other trays in
the first absorber are cooled with normal plant site cooling water, which is
generated by mechanical refrigeration. This refrigeration process is a part
of the ammonia vaporization section of the nitric acid plant.
The extended absorption process cannot control NO emissions to the same
X
degree as that obtained with catalytic reduction, and this process frequently
allows NO emissions greater than NSPS levels during startup and shutdown and
X
during periods of high ambient temperatures unless the plant is specifically
designed to compensate for these periods. Figure 12 illustrates the results
of NSPS performance tests conducted on new nitric acid plants from 1971 to
1978. Table 6 summarizes the results of compliance tests obtained from 10
new nitric acid plants that have been constructed since 1979. A review of
Figure 12 and Table 6 indicates that plants controlled by the extended absorption
process generally had higher NO emissions. All design conditions must be
X
precisely controlled for the extended absorption process to operate within
NSPS emission limits. Absorber pressure, temperature, and the oxygen and NO
/\
content of the tail gas must remain within design limits. Table 7 shows
32
-------
O
o
o
in
c
o
to
in
•r-
E
at
Q£
H-1
•a:
o
u_
ce
LU
Q-
ce
LU
ca
en
o
01
CO
t—
Qi ^.« Q O t-J
O _1 Q c£ 3C :3
fv* «^ r~i >^^ r~t
LUOCUJ ot 2^«a; ^o
3 LU a; a: LU o —^ <: 01 _i
h- LU3 OZ3Z<
LU i— a: t_> i— a -a: oz
_jt-iQ.e5»—oicC2:oii—10
^x z: ct >- v_ LU 01 t— i—
1-. LU CC 1—1 h— _J I— LUcCh—
x xs OLUI— LU i—i o LU en
oooo—letiscccca.a
ZZI— OLU<_>U-SCLO<:
O
a:
a
01
01
10
>i
in
£
O
Q.
O
in
J3
(O
TD
O)
-a
c
a)
CO
CO
*
33
-------
z
.a
41
CO
CO
LU
01
CO
co
Q.
CO
<:
C£
LjJ
3.5
3.0
2.5
2.0
1.5
. «
1.0
0.5
CURRENT EPA NSPS - NITRIC ACID PLANTS
/ D
NOT OFFICIAL NSPS TESTS
O O i
0 200 400 600 800
PLANT REDUCTION RATE, TPD
LEGEND
O CATALYTIC REDUCTION
D EXTENDED ABSORPTION
A CHILLED ABSORPTION AND
CAUSTIC SCRUBBING
1000 1200
Figure 12. NSPS test results of NOX emissions at nitric acid plants.11
34
-------
TABLE 6. COMPLIANCE TEST RESULTS FOR NITRIC ACID PLANTS
SUBJECT TO THE NSPS SINCE THE 1979 REVIEW11
Plant
A
B
C
D
E
Fa
G
H
I
J
Control
technique
Chilled absorption &
caustic scrubbing
Catalytic reduction
Extended absorption
Extended absorption
Extended absorption
Extended absorption
Extended absorption
Extended absorption
Extended absorption
Extended absorption
Average
NO emissions,
x Ib/ton
1.84
1.13
1.3
2.75
1.8
4.1
2.55
2.81
2,74
2.13
NSPS = 3.0
Plant was tested upon startup, then shut down, and has not restarted.
35
-------
TABLE 7. EXCESS EMISSIONS DATA FROM EXTENDED ABSORPTION
NITRIC ACID PLANT14 EXPERIENCING OPERATING PROBLEMS9'b
Date
7/2/78
7/11/78
7/23/78
8/7/78
8/16/78
8/20/78
8/22/78
8/24/78
8/25/78
8/29/78
Time period
12-1 pm
1-2 pm
2-3 pm
3-4 pm
6-7 pm
7-8 pm
8-9 pm
2-3 pm
3-4 pm
4-5 pm
3-4 pm
4-5 pm
5-6 pm
6-7 pm
7-8 pm
6-7 pm
7-8 pm
8-9 pm
11-12 am
12-1 pm
1-2 pm
2-3 pm
11-12 am
12-1 pm
1-2 pm
2-3 pm
1-2 pm
2-3 pm
3-4 pm
1-2 pm
2-3 pm
3-4 pm
5-6 pm
6-7 pm
7-8 pm
Emissions,
1b NOX per
ton of 100% HN03
3.83
4.52
4.26
3.52
5.89
4.99
4.15
5.71
6.65
3.76
4.27
4.23
3.27.
5.20
3.48
4.25
5.65
2.32
2.81
3.29
3.40
3.07
2.88
3.23
3.24
3.00
5.49
4.17
3.74
4.25
2.89
2.46
3.23
2.63
3.55
Cause
Startup
Startup followed shutdown
due to expander bypass valve
malfunction
Startup
Startup followed shutdown
due to high gauge tempera-
ture trip
Startup followed shutdown
due to NOX compressor trip
Reduced absorption tower
efficiency due to high
ambient temperature
Reduced absorption tower
efficiency due to high
ambient temperature
Startup followed shutdown
due to NO compressor trip
Startup followed shutdown
due to mysterious trip
Startup followed shutdown
due to electrical power
failure
Increased emissions occur during startups due to lag time in establishing
required absorption tower pressure and lowered circulating water temperature.
No external NOX abatement system is used at this acid plant.
Pounds of NOX are calculated based on 225 ppm(v) equal to 3 Ib/ton at 100
percent production rate.
36
-------
the NO emissions from one plant controlled by the extended absorption process
A
during unstable operating conditions and times of high ambient temperatures.
Unstable operating conditions must result in high NO emissions with this
A
process because no external control device is available in these situations
to reduce emissions. Ambient temperatures of 95° to 100°F create higher NO
A
vapor pressures than the second absorber can handle. For this reason, one
vendor will only guarantee performance within the specified NO emission
X
limit 95 percent of the time for plants located in the southern tier of
States.
Recent trends indicate that the extended absorption process will remain
the preferred NO control technology at new nitric acid plants for the next
/\
several years. Of the nine extended-absorption process-controlled new nitric
acid plants that came on stream through mid-1978, eight came on stream since
the energy crisis of the mid-19701s. This control technology choice appears
to have been influenced by the increasing uncertainty of an adequate natural
gas supply (the principal fuel used for catalytic reduction) together with
the anticipated sharp increases in natural gas prices over the next several
years. The economics of catalytic reduction, however, can be more favorable
than those of extended absorption if the nitric acid plant is to be located
in a fertilizer complex with an available contract for a low-price, long-term
natural gas supply.
3.3.3 Met Chemical Scrubbing
Wet scrubbing consists of contacting absorber tail gas with alkali
hydroxides or carbonates, ammonia, urea, or potassium permanganate solutions
to absorb NO in the form of nitrate and/or nitrite salts. Although these
X
processes have traditionally been used for retrofit control of existing nitric
acid plants, at least one nitric acid plant subject to NSPS employs a combi-
nation of chilled absorption and caustic scrubbing for NO control. Some of
A
these processes create potentially serious water pollution problems, and if a
market cannot be found for recovered ammonium nitrate, there is also a solid
waste disposal problem. Nitrogen oxide control, through use of wet chemical
scrubbing, has generally proved to be adequate.
37
-------
3.3.3.1 Urea Scrubbing16—
The MASAR process serves as a representative example of urea scrubbing
and is illustrated in Figure 13. The process control device consists of a
three-stage absorption column with gas and liquid chillers on the feed gas
and recirculated solvents. Liquid ammonia or some other form of mechanical
refrigeration is used as the cooling medium. The chemical reaction mechanisms
proposed for urea scrubbing are as follows:
HN02 + CO(NH2)
HNCO + HN0
HNCO + 2
C0
HNCO + H20 + H+ * NH4 + C0217
Under actual process operating conditions, the last reaction listed above
predominates so that the overall reaction is:
HN02
CO(NH2)2
HN0
This process has been reported to reduce NO emissions from 4000 to 1QO ppm
X
and can theoretically be designed for no liquid effluent. In practice, how-
ever, liquid blowdown of 16 kg/h (35 Ib/h) of urea nitrate in 180 kg/h (396
Ib/h) of water is estimated for a plant with a capacity of 320 Mg of acid/day
(350 tons/day).
In the MASAR process, absorber tail gas is first cooled in a gas chiller
where condensation occurs with the formation of nitric acid. Normal plant
absorber feedwater is chilled in Section C of the MASAR absorber and is then
fed to Section A, where it flows countercurrent to the incoming chilled tail
gas in the packed bed. After additional N0v is scrubbed from the tail gas,
X
the scrubbing water is recirculated through a chiller to remove reaction heat;
this weak acid stream is used as feed to the nitric acid plant absorber. In
Section B of the MASAR absorber, the tail gas is scrubbed with the urea-
containing solution forming nitric acid and nitrous acid that reacts to form
CO(NH2)> N2 and FLO. Recirculation of the scrubbing solution causes the con-
centration of nitric acid and ammonium nitrato to rise. Therefore, a bleed
38
-------
O)
o
o
o.
et
s:
o>
to
en
a>
en
39
-------
stream is required to keep the system in balance. Makeup urea/water solution
is fed to the scrubbing system at a rate sufficient to maintain a specified
minimum urea residual content. To maintain temperature control in Section B,
the recirculated scrubbing solution is pumped through a chiller to remove the
heat of reaction. Prior to leaving the MASAR unit, the tail gas is again
scrubbed with plant absorber feed water in Section C.
1 ft
3.3.3.2 Ammonia Scrubbing --
Goodpasture, Inc., developed an ammonia scrubbing process in 1973 that is
suitable to retrofit existing plants for reduction of an inlet concentration
of 10,000 ppm NO to within NSPS emission, limitations. A flow diagram for
A
the Goodpasture process is shown in Figure 14. As shown in the figure, the
entire process is conducted in a single packed contact absorption tower with
three sections operated in a concurrent flow. In the Goodpasture process,
there are three distinct sections of the absorption tower:
1. A gas absorption and reaction section operating on the acidic side.
, 2. A second gas absorption and "reaction section operating on the
ammoniacal side.
3. A final mist collection and ammonia recovery section.
Feed streams to this process are ammonia and water. Ammonium nitrate is pro-
duced as a byproduct of this process. Successful operation of this'process
requires that ammonium nitrite formation be kept to a minimum, and any ammonium
nitrite that does form must be oxidized to ammonium nitrate.
As shown in Figure 14, tail gas enters the first or acidic section of the
tower where NO in the gas stream is converted to nitric acid. Ammonia is
A
added to the process in the second section in sufficient amounts to maintain
the pH at a level of 8.0 to 8.3. In this section of the tower, ammonia reacts
with NO in the gas stream to form ammonium nitrate and ammonium nitrite; the
A
proportion of each is dependent on the oxidation state of the nitrogen oxides.
Product solution from the second section is fed to the first where ammonium
nitrite is oxidized to ammonium nitrate by the acidic conditions, and ammonium
nitrate is formed directly from the reaction of free ammonia with nitric acid.
The resulting solution is split into two streams. One stream is withdrawn from
the process as product solution, while the other is fed to the second or
ammoniacal section of the tower. Feed streams to the third and final section
40
-------
TAIL
GAS IN
ACIDIC
SECTION
PHRC
AMMONIACAL
SECTION
TREATED
TAIL- GAS
OUT
t
MIST COLLECTION
PRODUCT
AMMONIUM
NITRATE SOL'N
STEAM
CONDENSATE
Figure 14. Process flow diagram for the Goodpasture process
1 8
41
-------
of the tower consist of process water or steam condensate in sufficient quan-
tities to maintain the product ammonium nitrate solution in the 30 to 50 per-
cent concentration range, and a small amount of solution from the acidic
section to control the pH to approximately 7.0. In this section of the
process, mists are eliminated, and any free ammonia is stripped from the
solution. Product solution withdrawn from the first section of the process
contains 35 to 40 percent ammonium nitrate and 0.05 percent ammonium nitrite.
The ammonium nitrite can be oxidized by heating the solution to 240°F or by
simply holding it in a day-tank for 24 hours without heating.
Existing ammonia scrubbing systems have given reliable operation and
have met the emissions requirements for which they were designed. An advantage
of this process is that the pressure losses are only 6.8 to 13.0 kPa (1-2 psi),
which allows the process to be easily retrofitted for control of existing
low-pressure plants. Special precautions must be taken, however, to prevent
deposition of ammonium nitrate on the turbine blades. One potential dis-
advantage of the process is that the requirement for 85 percent ammonium
nitrate solutions by modern fertilizer"piants can necessitate additional
evaporators to concentrate the 35 to 55 percent ammonium nitrate solution
recovered as a byproduct from the Goodpasture process.
3.3.3.3 Caustic Scrubbing15' 19~
Strong bases such as sodium hydroxide and sodium carbonate have been used
for scrubbing NOX in the tail gas from nitric acid plants. Typical reactions
for caustic scrubbing are:
2NaOH + 3N0
NaN0
NO
2NaOH + NO + N02 -»• 2NaN02 + HLO
One serious problem with this process is that disposal of the spent scrubbing
solution can create a serious water pollution problem. At least one nitric
acid plant subject to NSPS, however, has successfully employed a combination
of caustic scrubbing and chilled absorption for NO control.
/\
42
-------
19
3.3.3=4 Potassium Permanganate Scrubbing —
Several Japanese plants employ solutions of potassium permanganate for
scrubbing NO emissions, but no U.S. plants are known to use the process. In
this process, permanganate is reduced to manganate that must be electrolytically
oxidized. The cost of electrolysis along with permanganate makeup costs are
believed to make this process uneconomical in the United States.
20
3.3.4 Chilled Absorption u
The chilled absorption process exploits the increased solubility of NOX
in cold water. This method has been primarily used as a retrofit for existing
plants, and as a sole control device, it is not capable of meeting NSPS emis-
sion limits. Both water and brine have been used in a closed loop system to
provide local cooling to the liquid on the trays of the absorption tower.
One representative chilled absorption process is the CDL/VITOK process, which
is illustrated in Figure 15. Nitrogen oxide in the tail gas is both chemically
oxidized and physically absorbed as it is contacted with a nitric acid solution
upon entering the absorber. In the upper portion of the absorber, cooled water
is employed to improve absorption. Nitric acid solution from the absorber is
split off to a bleacher where further oxidation occurs and air removes entrained
gases. Bleached nitric acid solution can either be stored or recycled to the
absorber after the addition of makeup water. A closed loop system is used to
chill both recirculated acid and cooling water by ammonia evaporation. Vari-
ations in the CDL/VITOK process include addition of an auxiliary bleacher
operating in parallel with the primary unit and use of a secondary absorber
with its own bleacher.
21 22
3.3.5 Molecular Sieve Adsorption '
Although the molecular sieve process has been somewhat successful in
controlling NO emissions from existing plants, there have been no new nitric
acid plants built that are subject to NSPS which employ this form of N0x con-
trol.1 Principal objections to the process are high capital and energy costs,
the problems of coupling a cyclic system to a continuous acid plant oper-
ation, and bed fouling. In addition, molecular sieves are not considered as
state-of-the-art technology for NO control in nitric acid plants. ' A
/\
flow diagram of the Purasiv control system that was developed by Union
43
-------
OJ
o
OJ
Ol
Ol
o:
Ol
-E
o
oo
o>
a z:
UJ O
LU ce:
44
-------
Carbide is shown in Figure 16. The pressure drop through the sieve bed is
rather high and averages 34 kPa (5 psi). The average concentration of NOX in
the treated tail gas discharged to the atmosphere, however, is only 50 ppm.
The fundamental principle behind molecular sieve control is selective
adsorption of NO followed by recycle of the NO back to the nitric acid
A A
plant absorption tower. As illustrated in Figure 16, the first step of the
process is to chill the absorber tail gas to between 7° and 10°C; the exact
temperature required is governed by the NO concentration in the tail gas
A
stream. Next, the chilled gas is passed through a mist eliminator to remove
entrained water and acid mist. Weak acid collected in the mist eliminator is
either recycled to the absorption tower or stored. Partially dried tail gas
then passes to the sieve bed where several operations proceed simultaneously:
1. Dessicant contained in the bed removes the remaining moisture
from the gas stream.
2. NO in the tail gas is converted catalytically to NO,,.
3. NOp is selectively adsorbed.--
Regeneration is accomplished by thermal-swinging (cycling) the adsorbent/
catalyst bed after it is nearly saturated with N02. Regeneration gas is
obtained by heating a portion of the treated tail gas in an oil- or gas-fired
heater. This gas is then used to desorb N02 from the bed for recycle back
to the nitric acid plant absorption tower. Both adsorption and regeneration
of the bed require approximately four hours.
23
3.3.6 Emerging Technology
The new Bolme nitrogen oxides recovery process recovers NOX removed from
tail gas and recycles it as feed to the plant absorption tower. When installed
in a new medium-pressure plant, as part of an integrated nitric acid-NOx
recovery system, it can reduce total capital cost and yield a modest increase
in operating profit. The process is illustrated in Figure 17 and design
specifications are listed in Table 8. In essence, the process employs a 25
to 30 weight percent nitric acid solution for scrubbing NOX in absorber tail
gas, and then the recovered NO is steam stripped from the scrubbing solution
A
and recycled. This process can be economically designed for NO emissions of
/\
only 70 to 85 ppm when operated at capacity during the hottest week of the
45
-------
S-
CD
)
a> t—
> -r-
«
-o +J
(O -4->
c:
C rt)
O i—
•r- Q_
4->
Q.T3
S_ -i-
o o
(/i
-a T-
c s=
3
«=C T-
O
tO O
to i-
o c
. o o
S- O
Q.
z: o
«t-
>
to en
S- •(-
3 -M
O_ ro
OJ
•O ^=
O)
f^ CI
I O
O T-
I— rtS
(U
• c
VO CD
«—I CT>
O)
O) S-
s_
en
46
-------
. +. 1000 PPM NOX
r-"" -^ (TREAT TO DESTROY)
2640 PPM
NOX
tJ
2A
PRODUCT MU-»
Ji_
sc
-««.
c
1
> ,
i
ss
i
i
IHE
p ;
1 1
t
PS
F * FEED
C * CONDENSER
B = BLEACHING SECTION
A = ABSORBER
SC = SCRUBBING SECTION
W - MASHING SECTION
06 - CLEAR GAS
FW * FEED WATER
AM * ACID WASH
PS * PREGNANT SCRUBBING SOLUTION
HE * HEAT EXCHANGER
ST - STRIPPING TOWER
SS » STRIPPED SOLUTION
T-C ' TRIM COOLER
RNOX = RECOVERED NITRIC OXIDER
BL * BLEED
RA * RECOVERED ACID
Figure 17. The Bolme NO recovery system.23
A
47
-------
TABLE 8. DESIGN SPECIFICATIONS FOR THE BOLME NOX RECOVERY PROCESS APPLIED
TO A NEW 220-METRIC-TON-PER-DAY MEDIUM-PRESSURE NITRIC ACID PLANT23
Combined scrubbing-stripping tower:
Diameter, m (in.) 2 (80)
Internal cooling none
Trays (sieve type)
Scrubbing, number 15
Washing, number 3-4
Stripping section, number ... 3
Feed/Product heat exchanger
(Spiral type, i.e., coiled sheet)
area, m2 (ft2) 440 (4,750)
Trim Cooler (Spiral type, i.e.,
coiled sheet) area, m2 (ft2) ... 65 (700)
Liquid ring compressors (Nash or
Siemens-Hinsch) Vacuum-to-
atmospheric
Atmospheric-to-recycl-e pressure
Pump, liter/h (gal/min) 115,000 (500)
Condenser
Controls
Operating costs and benefits
Utilities:
Steam @ 5 lb/in.2 gauge (130 kPa-
gauge), kg/h (Ib/h 1,745 (3,850)
Power, kW 125
Cooling water, liter/min (gal/min) 2,500 (660)
Benefits:
HNOa from RN02 (2500 -> 100 parts/
million), kg/day (lb/day) . . .
4,670 (10,295)
48
-------
year. As indicated in Figure 17, one major advantage of the process is that
the nitric acid plant absorber is 40 percent smaller than one required to
reduce the NO tail gas concentration to 1000 ppm. Another significant oper-
A
ating advantage of the process is that it tends to compensate for upsets. For
example, a 2640 ppm jump in the NOV entering the recovery process will produce
A
only a 283 ppm jump in the NO in the exhaust,
X
The Bolme process is tased on the same three"reactions as~the nitric acid
process itself:
1.
2,
3,
2ND + 0
2NO,
HN0 + HN0
3HN0 + HN0
H20
3
2NO
•/O 1 I ll Wo
The scrubbing solution employed in the process stabilizes nitrous acid and
removes it as fast as it is formed. This is accomplished by using a 25 to 30
weight percent nitric acid solution that can reverse the last reaction,
but allows the second reaction to proceed in the indicated direction. The
solubility of nitrous acid is maximum in this concentration of nitric acid.
The recovery process chemistry is complimentary to that of the basic nitric
acid process. At low NO partial pressures, the Bolme process works well,
A
while at high NO partial pressures, the basic nitric-acid process works
A
efficiently.
As illustrated in Figure 17, the integrated NO control method begins
A
with the normal nitric acid process. The feed (F) passes through a condenser
(C) and enters the absorption tower. Secondary air passes through a bleaching
section (B) and joins the feed. These combined streams then enter the plant
absorber (A); tail gas from the absorber contains 2600 ppm NO . Tail gas is
A
then directed to the scrubbing section (Sc) where the NO content is reduced
A
to approximately 150 ppm (70% N02). Exit gas from the scrubber enters the
washing section (W) where it is contacted with feed water (FW) to convert N02
to HN03 and NO. Clean gas (CG) from the washing section is sent to the power
recovery and the acid wash (AW) is fed to the absorber. Pregnant scrubbing
solution (PS) is heated to approximately 70°C in a feed-product heat exchanger
(HE) before it is stripped with steam in the stripping tower (ST) to produce
the stripped solution (SS). Stripped solution is first cooled in the same
49
-------
heat exchanger (HE) and then further cooled in the trim cooler (T-C) prior to
recycle. Recovered nitrogen oxides (RNOV) are cooled in a condenser and
X
compressed for recycle; bleed (Bl) is also compressed and the combined streams
are recycled to the absorber inlet. Recovered acid (RA) joins the acid wash
as feed to the absorber.
50
-------
SECTION 4
STARTUP, SHUTDOWN, AND MALFUNCTIONS
Prior to the inspection of a nitric acid plant, the field inspector
should become familiar with the plant's startup and shutdown procedures and
also with possible plant malfunctions.
All ammonia oxidation nitric acid plants use platinum alloy catalysts to
promote the oxidation reaction. The efficient life of a catalyst varies in
each plant as a result of the plant's design and operation practices. In
general, however, the catalyst at pressure process nitric acid plants is
changed once a month. This catalyst renewal requires a complete plant shut-
down and startup. Additional unplanned shutdowns and startups are due to
abnormal process conditions such as abnormally high temperatures and/or
pressures that jeopardize the mechanical or process equipment.
In addition to abnormal process shutdowns, any of the following service
upsets or failures will result in a plant shutdown:
1. Mechanical and/or process equipment,
2. Ammonia supply,
3. Lack of usage or storage for nitric acid,
4. Waste heat boiler feed water,
5. Absorber feed water,
6. Cooling water,
7. Instrument air, and
8. Electric power.
The average modern nitric acid plant will have 20 to 30 set points that, when
exceeded, will trigger an automatic plant shutdown. Shutdowns due to service
failures and abnormal process conditions are a function of the owner's mode
of performance. Poor maintenance and operation will result in frequent shut-
downs. Good maintenance and operating habits, however, should minimize these
shutdowns to approximately one per month.
51
-------
4.1 STARTUP
Before the ammonia oxidation reaction is started in a nitric acid plant,
not only must all of the process equipment be in operating condition, but all
of the numerous services must be available. With these prestartup conditions
assured, the next procedures are:
1. The air compressor has been run at a low rate until it is at its
operating temperature and pressure.
2. The ammonia vaporizing and supervising system is at operating
temperature and pressure.
3. -All downstream equipment such as heat exchangers, waste heat
boilers, and cooler-condenser are warmed up with auxiliary steam.
4.
5.
6.
The cooling water is circulating in the absorber.
The absorber feed water rate has been adjusted for startup.
The platinum catalyst gauze has been preheated and ready for the
light-off.
Under these conditions, the air flow is diverted to the ammonia-air mixer and
the ammonia vapor is added. The mixture passes over the catalyst in the con-
verter, which is at ignition temperature, and the ammonia oxidation reaction
starts. As the hot reaction gases pass through the preheated exchanger train,
the warmup stream is shut off and a water spray wash is turned on to wash out
ammonium nitrate and nitrite salts that form during this period of the startup
(these salts are formed by unreacted ammonia and nitrogen oxides fumes during
startup and are highly explosive). The bleach air flow is started and all
air and ammonia flows are increased and adjusted until the desired operating
conditions and rates are reached. The reaction gases flow to the absorber
where the oxi'dation of nitrogen oxide continues and absorption produces the
product acid.
The tail gas leaving the absorber reaches its equilibrium when the process
upstream has leveled out at the selected operating rate temperature, pressure,
etc. Only when this is achieved and the reheated tail gas is driving the
power recovery expander can a catalytic reduction unit be put on stream. If
the reduction unit were placed on stream before the tail gas had reached its
reheated temperature, reaction ignition would not take place and the unit
52
-------
would not operate. The tail gas composition must be stabilized with the
oxygen concentration design limits when the unit is ignited and put in oper-
ation because wide oxygen fluctuations would prevent proper operation. Con-
centrations above the design concentrations will produce temperatures above
the thermal limitation of the catalyst and result in a safety shutdown.
During this period before the catalytic reduction unit can be put on stream,
very careful startup operation is necessary to keep the plant emissions to a
minimum.
Should the plant be designed with sufficient absorption efficiency and
no control device, the startup must be well controlled to keep the absorption
process stabilized. With the absorption process under control, no difficulty
should be experienced in meeting the standard during the startup period.
Desirable conditions for adsorption systems (molecular sieves) are con-
stant bed temperatures, feed rates, and gas composition. If a nitric acid
plant is equipped with an adsorption system, it must be preheated and put on
stream when the tail gas composition and temperature have stabilized. This
means that the unit will be the last equipment put into operation. As with a
catalytic reduction system, before the adsorption unit is in operation, very
careful startup operational procedures are required to keep the plant's emis-
sions to a minimum.
4.2 SHUTDOWN
The first step in the shutdown of a nitric acid plant is to reduce the
production rate, usually to approximately one-half of the design rate. This
is done by reducing the reaction air flow to the ammonia-air mixer. The flow
ratio controller maintains the correct amount of ammonia flow as the air flow
is reduced. Next, the ratio of ammonia to ammonia-air mixture is reduced,
which lowers the reaction temperature (catalyst gauze); when the catalyst has
cooled to approximately 1000°F, the ammonia flow is shut off. After the ammonia
flow is shut off, the catalytic unit should be shut down because the oxygen
concentration in the tail gas will increase and the catalytic unit temperature
will rise to the thermal limitation set point and it will cause an automatic
shutdown. At this point, the air flow is further reduced; care must be taken
to maintain the pressure of the absorption column, or excessive emissions
53
-------
will result. The air flow is continued until all nitrogen oxides are purged
from the tail gas heater, waste heat boiler, and cooler-condensers. All drains
from these exchangers are opened to purge condensed water and weak acid. The
bleach air is now shut off and the absorption water to the absorber is reduced.
The air to the ammonia-air mixer may now be reduced to a minimum permitting
the compression train to turn slowly and cool. The compression train must be
cooled down carefully to avoid damage. As the plant is cooled down, all
services such as boiler feed water, absorber water, and cooling water should
be shut off. During this purge and cooling of the plant, the absorber pressure
and cooling must be maintained until the maximum amount of unabsorbed nitrogen
oxides are absorbed, or excessive emissions will result.
A nitric acid plant designed with sufficient absorption capacity without
an emission control system will have the same shutdown procedure as described
in the previous paragraph (excluding the catalytic unit shutdown). The same
care must be exercised to maintain absorption pressure and cooling or excessive
emissions will result.
If a nitric acid plant is equipped with an adsorption system, it must be
purged back into the absorber (all beds) to remove all nitrogen oxides before
the ammonia feed to the converter is shut off. This cleans the unit of
nitrogen oxides. The nitrogen oxides are absorbed before the plant temperatures
change and while the purge gas is normal. If the adsorption unit was operated
to the end, the oxides would have to remain in the cold adsorption beds or be
purged to the atmosphere. It would not be desirable to keep the oxides absorbed
in a cold adsorption bed. As in all nitric acid plants, during shutdown the
pressure and cooling must be maintained on the absorber tower or excessive
emissions will result.
4.3 MALFUNCTIONS
Any nitric acid plant designed with sufficient absorption capacity or
equipped with emission control devices will have difficulty controlling their
emissions if they experience any of the following upsets or malfunctions:
1.
Insufficient process air (converter and bleach air) will result in
an excess of unoxidized nitrogen oxide that the absorber and
catalytic unit cannot eliminate.
54
-------
2. Insufficient cooling of the cooler-condensers and absorber will
hinder the absorption of nitrogen dioxide and tetroxide.
3. Operation of the cooler-condenser and absorber below the design
pressure will lower the absorption efficiency and overload the
abatement system with nitrogen oxides.
4. If the plant is operated above design production rate and/or acid
concentration, the cooler-condensers and absorber will not perform
at their designed efficiency.
5. The mechanical failure of pumps, control valves, instruments, etc.,
will create unstable operations such as insufficient cooling, poor
reactant flow control, etc., which will hinder the proper absorption
and catalytic unit operations.
6. Process equipment malfunctions such as leaking exchangers could
easily allow bypassing of nitrogen oxides past the catalytic unit
to the atmosphere. Plugged trays in the absorber would reduce
absorption efficiency.
7. The loss of any utility such as waste heat boiler feed water,
instrument air, electricity, and process water would trigger
an emergency shutdown that would vent excessive nitrogen oxides
to the atmosphere.
55
-------
SECTION 5
PROCESS CONTROL SYSTEM AND
EMISSION MONITORING INSTRUMENTATION
Monitoring instrumentation plays three very important roles in the
operation of a nitric acid plant:
1. Informing the plant operators and inspectors of the various flows,
temperatures, pressures, and concentrations necessary to define
plant performance and emission control performance.
2. Performing process control functions such as automatic flow control,
automatic temperature control, and other control functions that may
be performed along with the monitoring of these functions.
3. Helping to protect the process from damaging and hazardous operating
conditions through the use of alarms, which notify the operator
when control limits are reached, and the use of trip-out and inter-
lock systems, which shut down parts or all of the plant when certain
preset control limits are reached.
Therefore, based on the above instrumentation functions, all nitric acid
^plant inspectors must be thoroughly familiar with all types of plants, control
systems, and emission monitoring instrumentation that can be encountered in
the industry. The following sections will define the general concepts of
performing the above monitoring functions. After understanding the general
concepts, the plant inspector must become familiar with the particular details
of each plant's monitoring system. With a thorough understanding of the
monitoring information, a plant inspector will be able to determine such
important parameters as plant process and production rates during the inspec-
tion.
5.1 PROCESS MONITORING INSTRUMENTATION
Although the nitric acid manufacturing process has many variations, the
basic ammonia-oxidation process can be considered a baseline for monitoring
nitric acid manufacturing processes. Figure 18 is an instrumentation flow
diagram of the AOP process.
56
-------
< 3 = £
uo i- S
u u.
UJ 1—
a a
u
« i
o — ce
t— t— uj
< « a
u u a:
i i i I I
LO 1/1
w un 3 3 3
« S 3 3 3
a. o. u. u. u.
I ^
S I
a <
5 1 g
— 01-
= 55
h- h- 1— UJ
S 2 g §
UJ Ul UJ bO
V)
1/5
O)
e_>
o
o.
to
-a
x
o
s-
o
E
ea
Ol
(O
O)
E
S-
-(->
ui
CO
(1)
s-
CT)
57
-------
The plant production rate is controlled by the air and ammonia feed
rate. The air rate to the air-ammonia mixer is manually set and controlled
by a flow indicating controller. This flow rate may also be recorded by a
flow recorder. The ammonia flow to the mixer is regulated by a ratio flow
control system governed by the air flow. The control system records air and
ammonia flow rates; the ammonia flow is adjusted to the desired set point
ratio which is selected on the ratio flow control to maintain a constant
concentration between 9.5 and 10.5 volume percent ammonia in the process
stream. The balance of the air needed for the process (approximately 20
percent) is introduced into the bottom.of the absorber by a flow indicating
controller. This bleach air flow rate may also be recorded by using a flow
recorder. The sum of these two air streams is the total air flow introduced
into the process. The introduction of water (condensate grade) to the absorber
is controlled by a flow indicating controller and is adjusted to produce the
amount (at a definite concentration) of acid to be generated by the air and
ammonia feed rates.
The rate of nitric acid product reaving the bottom of the absorber (or
bleach column if the plant has one separate from the absorber) is measured by
a flow recorder. The nitric acid concentration is determined by taking the
specific gravity of a sample at regular intervals. Some plants may have a
recording density instrument to determine the acid concentration. In any
event, a reliable production rate measurement method must be provided and be
sufficiently accurate to comply with the NSPS standard. The absorber gas
flow inlet and outlet are equipped with temperature and pressure indicators
that aid the operators in maintaining the optimum conditions for absorption
efficiency.
The exit gas flow from the absorber (tail gas) has numerous temperature
and pressure indicators before and after the equipment that it must pass
through before being exhausted to the atmosphere. Some of these temperature
indicators have high temperature alarms to alert the operators when there is
danger to certain equipment with temperature limitations, such as the expander
(temperature limit is usually 1250°F) and catalyst in the catalytic unit (if
the plant has one).
The catalytic unit may be controlled by an oxygen analyzer which, through
a ratio controller, adjusts the fuel feed rate to the unit for efficient auto-
matic operation.
58
-------
The tail gas stream is analyzed for nitrogen oxides before being exhausted
to the atmosphere. This instrument is required by the NSPS and must be an
indicating-recording analyzer (reading in ppm nitrogen dioxide). It must be
in continuous operation and maintained in optimum operating condition at all
times.
The instrumentation shown in Figure 18 is only the minimum required for
the process control. The following auxiliaries have numerous instruments and
controls for their proper operation and plant protection, and the inspector
should become familiar with instrumentation for these processes.
1. Compression train (startup turbine, compressor, and expander),
Ammonia vapor supply system,
Waste heat boiler feed water supply system,
Cooling water system,
2.
3.
4.
5.
Absorber water supply and treatment (condensate quality for
absorption),
6. Product nitric acid storage, and
7. Electric supply system.
These various systems are interlocked with the process controls, so it is
important that their possible effects on plant production and emission control
be understood.
5.2 EMISSION CONTROL INSTRUMENTATION
It should be emphasized that there are many possible instrumentation
concepts for the control techniques discussed in Section 3.3. The following
section discusses a general type of instrumentation scheme for each control
technique. The inspector should become familiar with the details of a given
emission control instrumentation scheme prior to the inspection.
5.2.1 Catalytic Reduction
The control instrumentation used on catalytic reduction units is as varied
as the number of suppliers. The simplified general flow diagram in Figure 19
illustrates the instrumentation scheme recommended by one supplier but is not
the only system in use.
59
-------
to
cr>
60
-------
The fuel must be clean (free of sulfur compounds, etc.) to protect the
catalyst and should be well mixed with the tail gas before passing over the
catalyst. The flow rate of fuel gas is controlled by the oxygen concentration
in the tail gas. The oxygen concentration is determined by a continuous ana-
lyzer that measures and controls the fuel flow rate. The fuel concentration
in the tail gas is analyzed by an analyzer-controller that maintains the flow
rate as required by the oxygen analyzer and controller. The ratio of fuel to
oxygen is controlled by a ratio flow controller in the system. This ratio is
selected to maintain optimum operation and protect the catalytic unit from
excess fuel that would decompose and poison the catalyst (carbon). In ad-
dition, a temperature recording controller with a high alarm is used to warn
the operator of abnormally high temperatures (usually about 1500°F) that
would damage the catalyst. As an additional safety precaution, this control
will also shut off the fuel supply if there is a lapse in time.
5.2.2 Absorption
Emission control by absorption is-somewhat misleading as no emission
control equipment is necessary if the plant is designed and built with suf-
ficient absorption capacity to ensure that the emissions will be below the
NSPS standard. A plant so designed will need no additional instrumentation
because the normal process instrumentation will be sufficient.
5.2.3 Molecular Sieves
The operation of molecular sieve adsorption systems tends to be simple.
Most operate on automatic valve sequencing, with time mechanisms providing
primary control. Performance evaluation is based on flow, temperature, pres-
sure, and composition measurements. The adsorption instrumentation diagram
shown in Figure' 20 schematically illustrates desirable instrumentation. The
analyzer-recorders for the inlet and outlet gas flows determine the nitrogen
oxides concentrations as nitrogen dioxide. From these two analyzers, the
unit's efficiency can be monitored. The exit analyzer does not replace the
continuous stack monitor as required by the NSPS. The various sample con-
nections are not only designed for gas samples but for absorbent samples as
well. These absorbent samples are useful in measuring the unit's performance
and in projecting when the absorbent will have to be changed. These adsorbent
analyses also help to identify other adsorbates and adsorbent poisons.
61
-------
O
UJ
(/)
o
O UJ
_J Q-
U O
5 8
CM
(_>
O
<_) O
S 5
z o
"" S
Z O UJ Z
CD I— U_ UJ
—.
10
I ^HYF^ J
CL
S-
o
t/1
•a
ta
OJ
O)
t/j
s~
ro
0)
"o
o
CM
ai
3
CD
I THYFV- I
62
-------
5.3 EMISSION MONITORING INSTRUMENTATION
Several different types of continuous emission monitoring techniques may
be used to determine the NO concentrations in the tail gas prior to release.
X
Some of these methodologies are summarized below. Each system has both ad-
vantages and disadvantages and the monitor selector must take this into con-
sideration along with the stack conditions expected to be encountered.
5.3.1 Ultraviolet Absorption-
The main type of ultraviolet absorption monitor is the nondispersive
ultraviolet analyzer shown in Figure 21. This analyzer uses the concept of
a split-beam photometer. It monitors the concentration of a pollutant by
measuring the difference in the amount of radiation absorbed at two different
wavelengths (ultraviolet, visible, or near-infrared). Radiation from the
source, usually a gas discharge lamp, is partially absorbed as it passes
through a sample of gas. As radiation leaves the sample, it is divided into
two beams by a semitransparent mirror. Each beam then passes through an optical
filter that removes all wavelengths except the one to be measured. The filtered
beam then strikes a phototube. The beam splitter is set up to reflect and
transmit so that the intensities of the radiation striking each phototube will
be nearly equal during normal operation of the analyzer*
The beam reaching one phototube is in a wavelength that is absorbed
strongly by the pollutant being measured; thus, this beam actually measures
the concentration. The beam directed to the second phototube is in a wave-
length that is absorbed weakly or not at all by the pollutant and is used as
a reference. If the concentration of the absorbing pollutant changes, the
intensity of radiation reaching the first phototube varies in accordance with
the concentration of pollutant. The radiation to the second phototube varies
very little, or not at all.
In each phototube, the current flow is proportional to the intensity of
radiation striking the phototube. This current is fed to an amplifier that
outputs a dc voltage that varies logarithmically with the current, and, hence,
with the intensity of the radiation. Voltage output from the reference beam
amplifier is subtracted from that of the measuring beam amplifier. This dif-
ference in voltage ouput varies linearly with the concentration of the pollu-
tant being measured. Therefore, the gaseous pollutant concentration may be
read directly or indirectly through the difference in output voltage.
63
-------
01
N
to
tO
Ol
tO
CD
O)
Q.
(M
O)
cn
L
64
-------
5.3.2 Infrared Absorption
Two main types of infrared sensors are commonly used—nondispersive and
dispersive. The term "nondispersive" refers to the lack of a light-dispersing
element such as a prism or grating that selects a particular analytical wave-
length of light. The more traditional Luft-type nondispersive infrared (NDIR)
analyzer has been used to make process and environmental measurements of nitric
oxide for over 20 years. A schematic of this type of analyzer is shown in
Figure 22.
In the NDIR analyzer, two identical infrared-radiation emitters serve as
matched sources of broad-brand infrared energy. Radiation from these sources
is modulated by a motor-driven chopper disk, and passed through filters and
measuring cells into an energy receiver. The reference cell is filled with
a gas such as nitrogen that does not absorb infrared energy. Another cell
contains the gas being analyzed. The amount of infrared energy passing through
the analysis cell that will be absorbed by the gas depends on the concentration
and wavelength band of the gas.
The energy receiver consists of two chambers separated by a membrane.
Both chambers are filled with a mixture of argon and the gas to be measured.
As the gas absorbs infrared energy, it heats up and pressure increases. If
the two chambers are exposed to equal amounts of energy, the membrane will
remain in a neutral position and there will be no output from the instrument.
Because the gas in the analysis cell absorbs more energy, pressure on that
side of the chamber increases and the membrane deflects. This deflection is
detected as a change in electrical capacitance between the membrane and a
fixed electrode and therefore, as a change in ac voltage at a resistor. This
ac voltage change is displayed as dc current using a measuring amplifier on
an indicating instrument.
If the gas to be tested contains components with absorption bands that
slightly overlap those of the pollutant being measured, identical filter cells
are filled with the interfering components to screen them out. This "positive
filtering" makes it easier to measure the pollutant.
The Luft-type NDIR analyzer generally uses an extractive sampling system
to transport the sample of stack gas to the analyzer. Particulate matter and
water vapor that interfere with the species measurement are removed. Generally,
Luft-NDIR analyzers are used to monitor S02, N02, NO, CO, and CO,,.
65
-------
s*: o >- <"
oo i— —i
H-1 O O- IJJ
o s: cu ts a:
r> <: LU
a: a: oo I— >—i
LU UJ _J U_
a. o_ o; o i—i
Q_ O- LU > _J
003 ,0.
3: z o o s:
o c_3 a. o > >
oo
oo
>— 4
00
LU OO
C£ LU
<_>
O
—
t_3 LU O
00
LU LU Z
00 O Q_ O
•—i Z= 3E t-t
OO LU 5 I—
>- o; i
Q.
CM
O)
t— I OO
a: _i
or LU Q o; o
O LU
>- _l
l.i i iii i_i
3E LU C£ U.
•-i evj co
66
-------
A schematic of another nondispersive analyzer is shown in Figure 23. In
contrast to the Luft-type analyzer, which looks at a broad spectral region and
must be sensitized for each particular gas using a detector cell, this NDIR
spectrometer can be set at any wavelength within its range. In addition, the
adjustable analyzer can measure any gas within its spectral region, and
unlike the Luft-type analyzer, is not limited to a single, preselected gas.
When many absorbing gases are present, however, it may be difficult to locate
a wavelength in a spectral region where other gases do not absorb.
The analyzer shown in Figure 23 uses a narrow-band pass filter that scans
the spectral region between 2.5 and 14 microns. Because the analyzer has a
variable path length from 3/4 to 20 meters, it has a large sensitivity range.
These and similar analyzers can measure many gases simultaneously; however,
other gases, water vapor, or particulates may cause absorption problems in
the spectral region of the pollutant.
Another type of NDIR analyzer is the gas cell correlation spectrometer
shown in Figure 24. EPA researchers are investigating this, type of analyzer
as an in-situ analyzer for various pollutants. The analyzer uses a broad band
IR source and detector, one or two cells filled with varying concentrations
of the gas to be measured to provide the wavelength selection. This technique
has shown potential for rejecting interference. Thus, it can be used to
improve low level sensitivities, or to simplify or eliminate requirements for
sampling systems. In addition, switching selection cells allows several pol-
lutants to be monitored by the same unit. Figure 25 shows a single-beam,
dual wavelength NDIR analyzer. In this analyzer, a single IR radiation beam
is passed through the sample gas and filtered into two wavelengths by a
chopper. The wavelengths are chosen so that one wavelength has no absorption,
while the other has maximum absorption. The ratio of their absorptions is
sensed by a conventional thermal electric IR detector.
5.4 CHEMILUMINESCENCE
Chemiluminescence is a chemical and optical monitoring technique. In
this technique, a gas molecule reacts with a reagent to form an excited molecule
that spontaneously decays, producing photoemissions. Sensitivity, rapid
response time, and instrument stability make the chemiluminescence method
67
-------
PATHLENGTH CAN BE VARIED WITH AN OUTSIDE ADJUSTING
KNOB FROM 3/4 METER TO MORE THAN 20 -METERS
PATHLENGTH
ADJUSTMENT
FILTER
WHEEL
SAMPLE CELL
OUT IN
FIELD MIRROR // i
HIGH CONCENTRATION CELL LOCATION-^ SOURCE
ELECTRONIC
"BOARD
Figure 23. Variable wavelength NDIR analyzer.
CORRELATION
CELL
BAND
SAMPLE PASS
CELL FILTER
SOURCEQ=
DETECTOR
ATTENUATOR
AMPLIFIER
AND METER
Figure 24. Gas cell correlation spectrometer analyzer.
68
-------
-M
cn
a
to
to
to
-------
suitable for continuous monitoring, although care must be taken to maintain
the monitored stream at constant flow rates. A typical NO and NO analyzer
f A
is shown in Figure 26. In this analyzer, NO molecules combine with 03 to
form an excited molecule (N02). A photomultiplier detects photoemission decay
and sends the signal to a sample-and-hold circuit. To detect N02, a N02 and
NO converter is connected into the gas stream and the NO analysis is run again.
After the second pass, a circuit subtracts the first reading from the second
to obtain the N02 reading. Few interferences have been observed, but high
concentrations of C02 or water vapor may partially quench the chemiluminescence.
In addition to monitoring NO and NOX, chemiluminescence devices are also used
to detect 03 and S02.
5.5 ELECTROCHEMICAL
Analyzers using electrochemical transducers measure the current induced
by the electrochemical oxidation of the pollutant at a sensing electrode.
Sensors are available for measuring Sp_2, CO, H2S, NO, and N02. Figure 27 shows
a simplified schematic of an electrochemical transducer. In this analyzer,
the pollutant diffuses through the semipermeable membrane into the transducer
at a rate proportional to the concentration. At the sensing electrode, the
pollutant undergoes an electrochemical oxidation or reduction that causes a
current directly proportional to the partial pressure of the gas being monitored.
Since electrons are produced at the sensing electrode, this electrode is at a
lower potential than the counter electrode. Thus, an electron current can
flow from the sensing electrode through the amplifier to the counter electrode,
and the current will be proportional to the concentration of the pollutant.
70
-------
CM
GO
GO
GO
GO
'
X
o
CM
O
X
O
o
o
o
o
o
cC
OL
CD
t/1
O
o a:
Z LU
o cc
1 — LU
CM Z
z S
1
i
t
(
J
n
JJ
_J
y
/I
t
V
•7
1
o
<
LU
LU
CS
CO
nJ
\\
_
n
ETECTOR
CONTROL
O
1
LU
C£
GO
CM
0
C
(_
J
c
h
mfm
3
j
L.
•1
LU
1— I
a.
i—
S^-X
rS
••••i
C
2
i—
G*
C
^
3
^
5
•>
>
1
L
<<
M
•^M*
<^
GO
C£
O
O_ GO
O 3
! «=C
UJ
_ I
D_
s_
OJ
IM
(O
cu
o
c:
cu
o
to
cu
cu
.c
o
to
CM
0)
GO
OC
LU
CO
O
1—4
O
LU
O£
71
-------
GAS CONTAINING POLLUTANT
...-L....1.....1...
I-I-I-I- SELECTIVE MEMBRANE -------
THIN
FILM ELECTROLYTE
SENSING ELECTRODE
BULK ELECTROLYTE
ELECTROCHEMICAL TRANSDUCER
- + RETARDING POTENTIAL
'AMPLIFIER
Figure 27. Electrochemical analyzer.
72
-------
SECTION 6
PERFORMANCE TESTS AND
CONTINUOUS MONITOR PERFORMANCE EVALUATIONS
6.1 PERFORMANCE TESTS
Compliance with the emission limitations of the NSPS is demonstrated
through performance tests conducted as required by Section 60.8. The initial
performance tests are required within 60 days of achieving maximum production
rate, but no later than 180 days after initial startup. The plant owner or
operator is required under Section 60.8(d) to provide at least 30 days prior
notice to the Administrator before conducting performance tests. In addition,
the plant owner or operator must also notify the Administrator 30 days prior
to the expected date of initial startup and within 15 days of actual startup
that such is occurring.
The test methods used by nitric acid plants in demonstrating compliance
are Method 7 for determination of NO -concentration, Method 1 for sampling
/\
point determination, Method 2 for determination of velocity and volumetric
flow rate, and Method 3 for gas analysis. A copy of these Methods is pro-
vided in Appendix B.
6.2 PRETEST ARRANGEMENTS
Field enforcement personnel should arrange a pretest meeting with respon-
sible plant personnel to review the methods of testing and regulatory require-
ments. Although the requirements are specified in the NSPS, this meeting
would clarify the testing requirements and avoid any potential misunderstanding
associated with the testing requirements during onsite testing.
It is recommended that a pretest protocol be established that sets forth
certain conditions such as production rate, acid strength, the sampling
location(s), methods to be used, and date(s) of test(s). A pretest protocol
will help to address any special circumstances that may arise by specifying
procedures that will be used. The objective in establishing this protocol
73
-------
is to ensure that a representative performance test is conducted at conditions
representative of the nitric acid plant's normal operation.
6.3 OBSERVING PERFORMANCE TESTS
Agency personnel observing performance tests should ensure themselves
that the test is conducted under representative conditions. This does not
require, however, that the agency representative observe the entire stack
sampling procedure to determine if each run is conducted in accordance to the
test method. Agency personnel should be more concerned with establishing
that the nitric acid plant conditions are representative because the test
methods are relatively rigid and the requirements straight forward.
The agency representative should observe, at the minimum, the following
parameters at the nitric acid plant:
1. Ammonia feed rate,
2.
3.
4.
5.
6.
7.
8.
Air flow rate to ammonia burner,
Catalyst temperature at ammonia burner,
Bleach air flow rate,
Ammonia burner and absorption column pressure,
NOX concentration in tail gas,
Acid strength, and
Acid production rate (either at production strength or 100 percent
basis). A material balance should be performed to confirm
accuracy.
In addition to these parameters, the operating temperatures, pressures,
flow rates, and any operating cycles associated with the control equipment
should be noted. Although many of these values are not directly required
for the calculation of emission rates, they are useful in establishing the
representativeness of any future performance tests and in the evaluation of
operating conditions in followup inspections.
74
-------
6.4 CONTINUOUS MONITOR PERFORMANCE EVALUATION
Prior to conducting tests to determine compliance with the emission
limitations, Section 60.13 requires that the continuous monitor be installed
and operating. The monitor must have completed the 168-h conditioning period
specified in Performance Specification 2, Appendix B of the NSPS. Section
60.13 also requires the continuous monitor to be certified through a performance
evaluation, also in accordance with Performance Specification 2, within 30
days of any performance test required by Section 60.8; in addition, the
Administrator must be furnished with two copies of the report within 60 days
of the monitor evaluation.
Briefly, the continuous monitor performance evaluation consists of two
portions: the conditioning period and the operating test period. The con-
ditioning period is 168 hours of continuous normal operation where negative
zero drift is quantified by offsetting the zero setting by 10 percent of the
span. The operating test period is the portion of the monitor performance
evaluation, 168 hours in duration, whe_re the monitor is calibrated and checked
for accuracy, drift, and response time.
The accuracy of the monitor is determined by comparing monitor output
values with values obtained by the performance test reference methods. In
addition, the monitor calibration error is checked by comparison of the monitor
response with samples of known gas concentrations. Monitor drift is checked
throughout the monitor test period as is monitor response time. The monitor
requirements are summarized below.
6.4.1 Continuous Monitor Performance Specifications
1. Accuracy (error)
Calibration (error)
3.
4.
5.
Zero drift (2-h)
Zero drift (24-h)
£20 percent of mean value of reference
method test data (95 percent confidence
interval)
£5 percent of each (50 percent, 90 percent)
calibration gas mixture value
2 percent of span
2 percent of span
Calibration drift (2-h) 2 percent of span
75
-------
6. Calibration drift
(24-h)
7. Response time
8. Operational period
2.5 percent of span
15 min
168 h (minimum)
The span value for nitric acid plants subject to NSPS is 500 ppm NO (measured
as N02). Performance Specification 2 is presented in Appendix B of this
document.
As in performance testing, the objective is to obtain a representative
and valid test. Portions of the monitor performance evaluation may be con-
ducted concurrently with a performance test conducted under Section 60.8. A
pretest protocol is highly recommended to familiarize the agency representative
with the scheduling of the various tests. In addition to obtaining the produc-
tion data noted previously, the agency representative may wish to observe
various aspects of the test to observe the method in which each of the require-
ments is checked. A schematic of the monitor sampling system and the operation
manual for the continuous monitor(s) may be useful to the agency representative.
76
-------
SECTION 7
INSPECTION PROCEDURES
Field enforcement personnel must make periodic inspections of the nitric
acid production facilities. It should be noted that a distinction is made
between a followup inspection and observation of the performance tests although
the data obtained from each are useful in determining the compliance status
of the plant.
With the exception of performing visible emissions observations, a field
inspector can determine very little from physically examining the mechanical
components of the nitric acid process other than noting any major changes in
equipment placement or fugitive emissions. Although records kept by the
plant owner or operator will provide information to the field inspector so
that an evaluation of the compliance status and the effectiveness of the
maintenance may be conducted, the major emphasis of the inspection should be
placed on reviewing continuous monitor outputs and operating records.
7.1 PLANT INSPECTION
7.1.1 Plant Entry
Because a major emphasis is placed on using available records to evaluate
the performance of the nitric acid plant, the plant management must be con-
tacted. The inspector should present his or her credentials and state the
purpose of the inspection. In the interview with plant management the inspector
should be able to determine whether the plant is operating, the production
rate, and acid strength.
It should be noted that some of the information obtained during the
inspections may be considered confidential by plant management. Ammonia
feed rate, conversion efficiencies, and operating pressures are examples of
data that plant managers often consider confidential because of economic and
competitive reasons. These data should be handled in the manner as directed
77
-------
by Section 114(c) of the Clean Air Act, which specifies the rights and respon-
sibilities of field inspectors in obtaining confidential data. These data,
however, when compared with the same data obtained during performance testing
or continuous monitor performance evaluation, will allow the field inspector
to assess if any significant change in plant operation has occurred.
7.1.2 Inspection of the Plant
After ascertaining that the nitric acid plant is operating, the inspector
should physically examine the plant. The inspector should start with an
evaluation of any visible emissions that are present at the tail gas stack.
The inspector should also check for any obvious changes in process equipment
that may affect plant operation.
Proper operation of the continuous monitor is extremely important to
the field inspector in determining the existence of excess emissions. The
inspection should include a check of the following areas:
1. Is the monitor sited at the same point as during the monitor
performance evaluation and any previous inspections?
2. Is the monitor the same (same model and serial number) as the
one tested in the most recent performance evaluation?
3. What is the location of calibration gas injection or the method
of required daily calibration checks?
4.
What is the value of the span gas or cells used in daily
calibration?
The continuous monitor display may be located near the analyzer or it may be
placed in the control room or both. Typically the display will be in the
control room with the other process instrumentation. A notation on the strip
chart may be useful to the inspector if data from the day of the inspection
is analyzed at a later date.
At this point, the inspector should obtain the readings from the nitric
acid plant instrument panels. This would include, if possible, the level of
N02 in the tail gas (ppm), the ammonia feed rate and/or the feed air volumetric
flow rate, the operating temperatures and pressures, and the operating
parameters monitored for any tail gas control device. Comparison of these
values with the baseline values established during the performance test can
78
-------
aid in determining the compliance status. Methods for estimating emission
rates are discussed in Section 7.2.
The inspector should also review operator logs and maintenance records
to determine if any problems are recurring that have an unfavorable impact on
the emissions. Daily production rates and operating hours should be scanned
to determine if the owner or operator is meeting or exceeding any production
limitations or restrictions listed in an operating permit. In addition, the
field inspector should determine if the production rate is relatively constant
and establish some value for average daily production. Although the conversion
factors and figures presented in Section 7.2 are relatively accurate, the
field inspector may wish to use the individual conversion rates established
during the performance test for each nitric acid plant.
If the inspector establishes from the operating records that the nitric
acid production rate is relatively constant from day to day and establishes
an average value for production, the inspector may also establish a value in
ppm NCL above which the NCL level exceeds the standard of 1.5 kg/metric ton.
Establishing this level allows the inspector to quickly scan the data from the
continuous monitor strip charts to determine if any potential excess emission
period has occurred. If a set of values is discovered above this level, the
production rate for those days should be used and not the average value as
established above.
This procedure will quickly identify potential excess emission periods,
although it will not identify all of these periods. This may only be
accomplished through checking the daily records and comparing the averages of
each 3-h period with the specified emission limit indicated in ppm.
The inspector will also need to verify that a daily zero and span cali-
bration check is performed. This will usually be displayed as a square spike
on the strip chart. The lack of daily zero and span calibration should be
noted for the periods when the monitor is operating. If the monitor does
not have an automatic zero and span calibration cycle, it is likely that the
daily zero and span calibrations may be missed. If, however, the monitor is
calibrated infrequently, then the data recorded on the monitor output may be
in error. The options available to the field inspector are citing the owner
or operator for not performing daily calibration checks and requiring the
79
-------
owner or operator to conduct a new performance evaluation of the monitor to
determine if the monitor still fulfills the requirements of Performance Speci-
fication 2, Appendix B of the NSPS.
As with most pieces of equipment, continuous monitors can and do fail.
The times when the monitor is inoperative are required to be recorded (Section
60.7(c)(3}) along with a notation with respect to the nature of the repairs
and/or adjustments that were necessary to make the monitor operable again.
The agency must decide if the monitor downtime is excessive and what actions
should be taken to remedy any problems with monitor operation.
7.2 ESTIMATION OF EMISSIONS FROM NITRIC ACID PLANTS
An estimate of the tail gas volumetric flow rate within an accuracy of
+5 percent can be calculated from the air feed rate for an ammonia oxidation
nitric acid plant. This is possible because the closed system design of the
pressure process allows no gas loss or gain from the beginning introduction
point to the exit exhaust stack. The .oxygen content of the air is the only
component in the air that is used in the reaction and it is carefully con-
trolled to an excess of approximately 2 to 5 percent. Therefore, a definite
ratio exists between the stack volumetric flow rate and the feed air volumetric
flow rate. A small portion (4 to 10 percent) of the ammonia feed is reduced
to inert nitrogen by the side reactions in the converter, but this amount is
relatively constant and does not significantly affect the ratio of stack flow
rate to feed air flow rate.
Furthermore, with the ammonia efficiency (sometimes expressed as nitrogen
efficiency) being constant, the production rate of nitric acid (as 100 percent
concentration) can also be estimated from the air feed rate. Because nitric
acid plants are usually run at ammonia efficiencies of between 90 to 95
percent, an average of 93 can be used.
The graphs shown in Figures 28 and 29 were constructed based on the
average data reported for numerous nitric acid plants under various operating
conditions. These graphs can be used to estimate the stack volumetric flow
rate and the plant emission rate in the following manner.
80
-------
100.0
l/l
o s^
4-J O
O
«>!—4
.
0:0
I— or
10.0
1.0
100
1—I—I I I I I
EMISSION RATE
(TAIL GAS)
AIR FEED RATE
1000 10,000
AIR, scf/h X 1000
100,000
Figure 28. Production rate vs. air feed rate.
81
-------
100.0C 1 1—i i i i i i 1—i 1—i i i i 11 1—i 1—i i
I
CO
o
c
o
CVJ
o
1.0
0.1
J—I—I—' I I I ll
BASIS: 93% AMMONIA
EFFICIENCY
J 1 I I I I 111
10
100
1000
10,000
N0?, ppm (BY VOL.)
IN TAILGAS
Figure 29.
Conversion of NO tail gas concentration to mass emission.
/\
82
-------
1. Read the air flow rate to the converter (Fl, usually in standard
cubic foot per hour (scf/h).
2. Read the bleach air flow rate (F2, usually in scf/h).
3. Add the two air flows; this is the total air to the process. Assume
this figure is 1,443,400 scf/h from Figure 28, the plant production
rate is 10 tons/h HMO, (100 percent) and the stack volumetric flow
rate is 1,209,000 scf/h.
4. Read the continuous nitrogen oxides monitor.— Assume it reads 150
ppm NOo; from Figure 29, the emission rate is 2.1 Ib N0?/ton HMO,
(100 percent).
The graph shown in Figure 30 is useful to check ammonia efficiency and/or
production rate when the plant ammonia feed rate is known. Before using the
curves in Figure 30, one must know either the ammonia efficiency (nitrogen
efficiency) or accurate ammonia and production rate values.
83
-------
ioo.or
c
o
i.o
NITROGEN EFFICIENCY
10,000
100,000
AMMONIA FEED RATE, scf/h
1,000,000
Figure 30. Ammonia feed rate vs. production rate.
84
-------
REFERENCES
1. Chilton, T.H. The Manufacture of Nitric Acid By the Oxidation of Ammonia,
Chemical Engineering Progress Monograph Series, No. 3, Volume 56, 1960.
2. Newman, D.J., and L.A. Klein. Recent Developments in Nitric Acid.
Chemical Engineering Progress, No. 4, Volume 68, 1972.
3. Hellmer, L. Three New Nitric Acid Processes. Chemical Engineering
Progress, No. 4, Volume 68, April 1972.
4. Reed, R.M., and R.L. Marvin. Nitric Acid Plant Fume Abaters. Chemical
Engineering Progress, No. 4, Volume 68, April 1972.
5. Andrussow, L., and Z. Angew. Chem., Vol. 39, No. 321 (1926); Vol. 40,
No. 166, 1927.
6. Fauser, G. Chem. Met. Eng., Vol7'35, No. 474, 1928.
7. Bodenstein, M.Z. Elektrochem., Vol. 24, No. 183, 1918.
8. Newman, D.J. Nitric Acid Plant Pollutants. Chemical Engineering
Progress, Vol. 67, No. 2, February 1971.
9. U.S. Environmental Protection Agency. Control of Air Pollution From
Nitric Acid Plants. Draft. August, 1971.
10. Chem. Eng., Vol. 59, No. 1, 238. 1952.
11. U.S. Environmental Protection Agency. Review of New Source Performance
Standards for Nitric Acid Plants. EPA 450/8-84-011, April 1984.
12. Gillespie, G.R., A.A. Boyum, and M.F. Collins. Catalytic Purification
of Tail Gases. Chemical Engineering Progress, No. 4, Volume 68, April
1972.
13. Snyder, A.D., et al. Monsanto Research Corporation. Instrumentation
for the Determination of Nitrogen Oxides Content of Stationary Source
Emissions.
14. U.S. Environmental Protection Agency. An Air Pollution Compliance
Analysis Report on Nine Industries. Volume V. Nitric Acid Industry,
Final Report, September 1978.
85
-------
15. Drabkin, M. A Review of Standards of Performance for New Stationary
Sources - Nitric Acid Plants. MITRE Technical Report - 7911. EPA
Contract No. 68-02-2526, January 1979.
16. MASAR Process for Recovery of Nitrogen Oxides. Company brochure, MASAR,
Inc.
17. NOX Abatement in Nitric Acid and Nitric Phosphate Plants. Nitrogen,
No. 93, January/February 1975.
18. Service, W.J., R.T. Schneider, and D. Ethington. The Goodpasture
Process for Chemical Abatement and Recovery of NOX. Conference on
Gaseous Sulfur and Nitrogen Compound Emissions, Salford, England,
April 1976.
19. U.S. Environmental Protection Agency. Control Techniques for Nitrogen
Oxides Emissions from Stationary Sources (2nd ed.). EPA-450/1-78-001,
January 1978.
20. Gerstle, R.W., and R.F. Peterson. Atmospheric Emissions from Nitric Acid
Manufacturing Process. National Center for Air Pollution Control,
Cincinnati, Ohio, PHS Publication Number 999-AP-27, 1966.
21; Rosenberg, H.S. Molecular SieveJIOx Control Process in Nitric Acid
Plants. Environmental Protection Technology Series, EPA-600/2-76-015,
January 1976.
22. Chehaske, J.I., and J.S. Greenberg. Molecular Sieve Tests for Control
of NOX Emissions from a Nitric Acid Plant. Volume I, EPA-600/2-76-048a,
March 1976.
23. Bolme, D.W., and A.M. Bolme and Associates. The Humphreys and Glasgow/
Bolme Nitric Acid Process. Chemical Engineering Progress, p. 95-98,
March 1979.
86
-------
APPENDIX A
NSPS REGULATIONS
87
-------
Chapter I—Environmental Protection Agency
§60.71
Subpart G—Standards of
Performance for Nitric Acid Plants
§60.70 Applicability and designation of
affected facility.
(a) The provisions of this subpart
are applicable to each nitric acid pro-
duction unit, which is the affected fa-
cility.
(b) Any facility under paragraph (a)
of this section that commences con-
struction or modification after August
17, 1971, is.subject to the requirements
of this subpart.
(Sees. Ill and 301(a) of the Clean Air Act;
sec. 4(a) of Pub. L. 91-604, 84 Stat. 1683: sec.
2 of Pub. L. 90-148.-81 Stat. 504 (42 U.S.C.
1857C-6. 1857g(a)))
[42 PR 37936, July 25, 1977]
§ 60.71 Definitions.
As used in this subpart, all terms not
defined herein shall have the meaning
given them in the Act and in Subpart
A of this part.
88
-------
§ 60.72
Title 40—Protection of Environment
(a) "Nitric acid production unit"
means any facility producing weak
nitric acid by either the pressure or at-
mospheric pressure process.
(b) "Weak nitric acid" means acid
which is 30 to 70 percent in strength.
§ 60.72 Standard for nitrogen oxides.
(a) On and after the date on which
the performance test required to be
conducted by § 60.8 is completed, no
owner or operator subject to the provi-
sions of this subpart shall cause to be
discharged into the atmosphere from
any affected facility any gases which:
(1) Contain nitrogen oxides, ex-
pressed as NO,, in excess of 1.5 kg per
metric ton of acid produced (3.0 Ib per
ton), the production being expressed
as 100 percent nitric acid.
(2) Exhibit 10 percent opacity, or
greater.
[39 PR 20794, June 14, 1974, as amended at
40 PR 46258, Oct. 6, 1975]
§ 60.73 Emission monitoring.
(a) A continuous monitoring system"
for the measurement of nitrogen
oxides shall be installed, calibrated,
maintained, and operated by the
owner or operator. The pollutant gas
used to prepare calibration gas mix-
tures under paragraph 2.1, Perform-
ance Specification 2 and for calibra-
tion checks under § 60.13(d) to this
part, shall be nitrogen dioxide (NO,).
The span shall be set at 500 ppm of ni-
trogen dioxide. Reference Method 7
shall be used for conducting monitor-
ing system performance evaluations
under § 60.13(c).
(b) The owner or operator shall es-
tablish a conversion factor for the pur-
pose of converting monitoring data
into units of the applicable standard
(kg/metric ton, Ib/short ton). The
conversion factor shall be established
by measuring emissions with the con-
tinuous monitoring system concurrent
with measuring emissions with the ap-
plicable reference method tests. Using
only that portion of the continuous
monitoring emission data that repre-
sents emission measurements concur-
rent with the reference method test
periods, the conversion factor shall be
determined by dividing the reference
method test data averages by the mon-
itoring data averages to obtain a ratio
expressed in units of the applicable
standard to units of the monitoring
data, i.e., kg/metric ton per ppm (Ib/
short ton per ppm). The conversion
factor shall be reestablished during
any performance test under § 60.8 or
any continuous monitoring system
performance evaluation under
§ 60.13(0.
(c) The owner or operator shall
record the daily production rate and
hours of operation.
(d) [Reserved]
(e) For the purpose of reports re-
quired under § 60.7(c), periods of
excess emissions that shall be reported
are defined as any 3-hour period
during which the average nitrogen
oxides emissions (arithmetic average
of three contiguous 1-hour periods) as
measured by a continuous monitoring
system exceed the standard under
§ 60.72(a).
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[39 PR 20794, June 14, 1974. as amended at
40 PR 46258, Oct. 6, 1975; 43 PR 8800. Mar
3, 1978]
§ 60.74 Test methods and procedures.
(a) The reference methods in Appen-
dix A to this part, except as provided
for in § 60.8(b), shall be used to deter-
mine compliance with the standard
prescribed in § 60.72 as follows:
(1) Method 7 for the concentration
of NOr;
(2) Method 1 for sample and velocity
traverses;
(3) Method 2 for velocity and volu-
metric flow rate; and
(4) Method 3 for gas analysis.
(b) For Method 7, the sample site
shall be selected according to Method
1 and the sampling point shall be the
centroid of the stack or duct or at a
point no closer to the walls than 1 m
(3.28 ft). Each run shall consist of at
least four grab samples taken at ap-
proximately 15-minute intervals. The
arithmetic mean of the samples shall
constitute the run value. A velocity
traverse shall be performed once per
run.
(c) Acid production rate, expressed
in metric tons per hour of 100 percent
nitric acid, shall be determined during
each testing period by suitable meth-
89
-------
Chapter I—Environmental Protection Agency
§ 60.84
ods and shall be confirmed by a mate-
rial balance over the production
system.
(d) For each run, nitrogen oxides,
expressed in g/metric ton of 100 per-
cent nitric acid, shall be determined by
dividing the emission rate in g/hr by
the acid production rate. The emission
rate shall be determined by the equa-
tion,
g/hr=Q.xc
where Q,=volumetric flow rate of the
effluent in dscm/hr, as determined in
accordance with paragraph (a)(3) of
this section, and c=NOx concentration
in g/dscm, as determined in accord-
ance with paragraph (aXl) of this sec-
tion.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[39 PR 20794. June 14. 1974. as amended at
43 PR 8800, Mar. 3, 1978]
Subpart H—Standards of
Performance for Sulfuric Acid Plants
§ 60.80 Applicability and designation of
affected facility.
(a) The provisions of this subpart
are applicable to each sulfuric acid
production unit, which is the affected
facility.
(b) Any facility under paragraph (a)
of this section that commences con-
struction or modification after August
17, 1971, is subject to the requirements
of this subpart.
(Sees, ill and 301(a) of the Clean Air Act;
sec. 4(a) of Pub. L. 91-604, 84 Stat. 1683; sec.
2 Of Pub. L. 90-148, 81 Stat. 504 (42 U.S.C.
1857C-6, 1857g(a»)
C42 PR 37936, July 25, 1977]
§ 60.81 Definitions.
As used in this subpart, all terms not
defined herein shall have the meaning
given them in the Act and in Subpart
A of this part.
(a) "Sulfuric acid production unit"
means any facility producing sulfuric
acid by the contact process by burning
elemental sulfur, alkylation acid, hy-
drogen sulfide, organic sulfides and
mercaptans, or acid sludge, but does
not include facilities where conversion
to sulfuric acid is utilized primarily as
a means of preventing emissions to the
atmosphere of sulfur dioxide or other
sulfur compounds.
(b) "Acid mist" means sulfuric acid
mist, as measured by Method 8 of Ap-
pendix A to this part or an equivalent
or alternative method.
[36 PR 24877, Dec. 23, 1971, as amended at
39 PR 20794, June 14, 1974]
§ 60.82 Standard for sulfur dioxide.
(a) On and after the date on which
the performance test required to be
conducted by § 60.8 is completed, no
owner or operator subject to the provi-
sions of this subpart shall cause to be
discharged into the atmosphere from
any affected facility any gases which
contain sulfur dioxide in excess of 2 kg
per metric ton of acid produced (4 Ib
per ton), the production being ex-
pressed as 100 percent H2SO«.
[39 PR 20794, June 14, 1974]
_. § 60.83 Standard for acid mist.
(a) On and after the date on which
the performance test required to be
conducted by § 60.8 is completed, no
owner or operator subject to the provi-
sions of this subpart shall cause to be
discharged into the atmosphere from
any affected facility any gases which:
(1) Contain acid mist, expressed as
HjSO,, in excess of 0.075 kg per metric
ton of acid produced (0.15 Ib per ton),
the production being expressed as 100
percent HjSO,.
(2) Exhibit 10 percent opacity, or
greater.
[39 PR 20794, June 14, 1974, as amended at
40 PR 46258, Oct. 6, 1975]
§ 60.84 Emission monitoring.
(a) A continuous monitoring system
for the measurement of sulfur dioxide
shall be installed, calibrated, main-
tained, and operated by the owner or
operator. The pollutant gas used to
prepare calibration gas mixtures
under paragraph 2.1, Performance
Specification 2 and for calibration
checks under § 60.13(d), shall be sulfur
dioxide (SO,). Reference Method 8
shall be used for conducting monitor-
ing system performance evaluations
under § 60.13(c) except that only the
sulfur dioxide portion of the Method 8
90
-------
§ 60.85
results shall be used. The span shall
be set at 1000 ppm of sulfur dioxide.
(b) The owner or operator shall es-
tablish a conversion factor for the pur-
pose of converting monitoring data
into units of the applicable standard
(kg/metric ton, Ib/short ton). The
conversion factor shall be determined,
as a minimum, three times daily by
measuring the concentration of sulfur
dioxide entering the converter using
suitable methods (e.g., the Reich test,
National Air Pollution Control Admin-
istration Publication No. 999-AP-13)
and calculating the appropriate con-
version factor for each eight-hour
period as follows:
CF=kC1.000-0.015r/r-s]
where:
CP =.conversion factor (kg/metric ton per
ppm, Ib/short ton per ppm).
lc =constant derived from material bal-
ance. For determining CF in metric
units, k=0.0653. For determining CF
in English units, k=0.1306.
r = percentage of sulfur dioxide by volume
entering the gas converter. Appropri-
ate corrections must be made for air
injection plants subject to the Admin-
istrator's approval.
s = percentage of sulfur dioxide by volume
in the emissions to the atmosphere de-
termined by the continuous monitor-
ing system required under paragraph
(a) of this section.
(c) The owner or operator shall
record all conversion factors and
values under paragraph (b) of this sec-
tion from which they were computed
(i.e., CP, r, and s).
(d) [Reserved]
(e) For the purpose of reports under
§ 60.7(c), periods of excess emissions
shall be all three-hour periods (or the
arithmetic average of three consecu-
tive one-hour periods) during which
the integrated average sulfur dioxide
emissions exceed the applicable stand-
ards under § 60.82.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
139 PR 20794, June 14. 1974, as amended at
40 FR 46258, Oct. 6, 1975; 43 PR 8800, Mar.
3, 1978]
§ 60.85 Test methods and procedures.
(a) The reference methods in Appen-
dix A to this part, except as provided
for in § 60.8(b), shall be used to deter-
mine compliance with the standards
Title 40—Protection of Environment
prescribed in §§ 60.82 and 60.83 as fol-
lows:
(1) Method 8 for the concentrations
of SO, and acid mist;
(2) Method 1 for sample and velocity
traverses;
(3) Method 2 for velocity and volu-
metric flow rate; and
(4) Method 3 for gas analysis.
(b) The moisture content can be con-
sidered to be zero. For Method 8 the
sampling time for each run shall be at
least 60 minutes and the minimum
sample volume shall be 1.15 dscm (40.6
dscf) except that smaller sampling
times or sample volumes, when neces-
sitated by process variables or other
factors, may be approved by the Ad-
ministrator.
(c) Acid production rate, expressed
in metric tons per hour of 100 percent
H,SO,, shall be determined during
each testing period by suitable meth-
ods and shall be confirmed by a mate-
rial balance over the production
system.
(d) Acid mist and sulfur dioxide
emissions, expressed in g/metric ton of
100 percent HjSO«, shall be deter-
mined by dividing the emission rate in
g/hr by the acid production rate. The
emission rate shall be determined by
the equation, g/hr=Q,xc, where
Q,=volumetric flow rate of the efflu-
ent in dscm/hr as determined in ac-
cordance with paragraph (a)(3) of this
section, and c=acid mist and SO3 con-
centrations in g/dscm as determined
in accordance with paragraph (aXI) of
this section.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[39 FR 20794. June 14, 1974, as amended at
43 FR 8800, Mar. 3, 1978]
Subpart I—Standards of Performance
for Asphalt Concrete Plants
§ 60.90 Applicability and designation of
affected facility.
(a) The affected facility to which
the provisions of this subpart apply is
each asphalt concrete plant. For the
purpose of this subpart, an asphalt
concrete plant is comprised only of
any combination of the following:
Dryers; systems for screening, han-
dling, storing, and weighing hot aggre-
91
-------
Chapter I—Environmental Protection Agency
§60.101
gate; systems for loading, transferring,
and storing mineral filler; systems for
mixing asphalt concrete; and the load-
ing, transfer, and storage systems asso-
ciated with emission control systems.
(b) Any facility under paragraph (a)
of this section that commences con-
struction or modification after June
11, 1973, is subject to the requirements
of this subpart.
(Sees. Ill and 301(a) of the Clean Air Act;
sec. 4(a) of Pub. L. 91-604, 84 Stat. 1683; sec.
2 of Pub. L. 90-148, 81 Stat. 504 (42 U.S.C.
1857C-6,1857g(a»)
C42 FR 37936, July 25, 1977]
§ 60.91 Definitions.
As used in this subpart, all terms not
defined herein shall have the meaning
given them in the Act and in Subpart
A of this part.
(a) "Asphalt concrete plant" means
any facility, as described in § 60.90,
used to manufacture asphalt concrete
by heating and drying aggregate and"
mixing with asphalt cements.
§ 60.92 Standard for particulate matter.
(a) On and after the date on which
the performance test required to be
conducted by § 60.8 is completed, no
owner or operator subject to the provi-
sions of this subpart shall discharge or
cause the discharge into the atmos-
phere from any affected facility any
gases which:
(1) Contain particulate matter in
excess of 90 mg/dscm (0.04 gr/dscf).
(2) Exhibit 20 percent opacity, or
greater.
C39 FR 9314, Mar. 8, 1974, as amended at 40
FR 46259, Oct. 6, 1975]
§ 60.93 Test methods and procedures.
(a) The reference methods appended
to this part, except as provided for in
§ 60.8(b), shall be used to determine
compliance with the standards pre-
scribed in § 60.92 as follows:'
(1) Method 5 for the concentration
of particulate matter and the associat-
ed moisture content,
(2) Method 1 for sample and velocity
traverses,
(3) Method 2 for velocity and volu-
metric flow rate, and
(4) Method 3 for gas analysis.
(b) For Method 5, the sampling time
for each run shall be at least 60 min-
utes and the sampling rate shall be at
least 0.9 dscm/hr (0.53 dscf/min)
except that shorter sampling times,
when necessitated by process variables
or other factors, may be approved by
the Administrator.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[39 FR 9314, Mar. 8, 1974, as amended at 43
FR 8800, Mar. 3, 1978]
Subpart J—Standards of Performance
for Petroleum Refineries
§ 60.100 Applicability and designation of
affected facility.
(a) The provisions of this subpart
are applicable to the following affect-
ed facilities in petroleum refineries:
fluid catalytic cracking unit catalyst
regenerators, fuel gas combustion de-
vices, and all Glaus sulfur recovery
plants except Glaus plants of 20 long
tons per day (LTD) or less. The Glaus
sulfur recovery plant need not be
physically located within the bound-
aries of a petroleum refinery to be an
affected facility, provided it processes
gases produced within a petroleum re-
finery.
(b) Any fluid catalytic cracking unit
catalyst regenerator or fuel gas com-
bustion device under paragraph (a) of
this section which commences con-
struction or modification after June
11, 1973, or any Glaus sulfur recovery
plant under paragraph (a) of this sec-
tion which commences construction or
modification after October 4, 1976, is
subject to the requirements of this
part.
(Sees. Ill, 114, 301(a), Clean Air Act, as
amended (42 U.S.C. 7411, 7414, 7601(a)))
[43 FR 10868, Mar. 15, 1978, as amended at
44 FR 61543, Oct. 25, 1979]
§ 60.101 Definitions.
As used in this subpart, all terms not
defined herein shall have the meaning
given them in the Act and in Subpart
A.
(a) "Petroleum refinery" means any
facility engaged in producing gasoline,
kerosene, distillate fuel oils, residual
fuel oils, lubricants, or other products
92
-------
Chapter I—Environmental Protection Agency
§60.2
Subpart A—General Provisions
§ 60.1 Applicability.
Except as provided in Subparts B
and C, the provisions of this part
apply to the owner or operator of any
stationary source which contains an
affected facility, the construction or
modification of which is commenced
after the date of publication in this
part of any standard (or, if earlier, the
date of publication of any proposed
standard) applicable to that facility.
[40 PR 53346, Nov. 17, 1975]
§ 60.2 Definitions.
The terms used in this part are de-
fined in the Act or in this section as
follows:
"Act" means the Clean Air Act (42
U.S.G. 1857 et seq., as amended by
Pub. L. 91-604, 84 Stat. 1676).
"Administrator" means the Adminis~-'
trator of the Environmental Protec-
tion Agency or his authorized repre-
sentative.
"Affected facility" means, with ref-
erence to a stationary source, any ap-
paratus to which a standard is applica-
ble.
"Alternative method" means any
method of sampling and analyzing for
an air pollutant which is not a refer-
ence or equivalent method but which
has been demonstrated to the Admin-
istrator's satisfaction to, in specific
cases, produce results adequate for his
determination of compliance.
"Capital expenditure" means an ex-
penditure for a physical or operational
change to an existing facility which
exceeds the product of the applicable
"annual asset guideline repair allow-
ance percentage" specified in the
latest edition of Internal Revenue
Service (IRS) Publication 534 and the
existing facility's basis, as defined by
section 1012 of the Internal Revenue
Code. However, the total expenditure
for a physical or operational change to
an existing facility must not be re-
duced by any "excluded additions" as
defined in IRS Publication 534, as
would be done for tax purposes.
"Commenced" means, with respect
to the definition of "new source" in
section lll(a)(2) of the Act, that an
owner or operator has undertaken a
continuous program of construction or
modification or that an owner or oper-
ator has entered into a contractual ob-
ligation to undertake and complete,
within a reasonable time, a continuous
program of construction or modifica-
tion.
"Construction" means fabrication,
erection, or installation of an affected
facility.
"Continuous monitoring system"
means the total equipment, required
under the emission monitoring sec-
tions in applicable subparts, used to
sample and condition (if applicable),
to analyze, and to provide a perma-
nent record of emissions or process pa-
rameters.
"Equivalent method" means any
method of sampling and analyzing for
an air pollutant which has been dem-
onstrated to the Administrator's satis-
faction to have a consistent and quan-
titatively known relationship to the
reference method, under specified con-
ditions.
"Existing facility" means, with refer-
ence to a stationary source, any appa-
ratus of the type for which a standard
is promulgated in this part, and the
construction or modification of which
was commenced before the date of
proposal of that standard; or any ap-
paratus which could be altered in such
a way as to be of that type.
"Isokinetic sampling" means sam-
pling in which the linear velocity of
the gas entering the sampling nozzle is
equal to that of the undisturbed gas
stream at the sample point.
"Malfunction" means any sudden
and unavoidable failure of air pollu-
tion control equipment or process
equipment or of a process to operate
in a normal or usual manner. Failures
that are caused entirely or in part by
poor maintenance, careless operation,
or any other preventable upset condi-
tion or preventable equipment break-
down shall not be considered malfunc-
tions.
93
-------
§60.3
Title 40—Protection of Environment
"Modification" means any physical
change in, or chanse in the method of
operation of, an existing facility which
increases the amount of any air pollut-
ant (to which a standard applies) emit-
ted into the atmosphere by that facili-
ty or which results in the emission of
any air pollutant (to which a standard
applies) into the atmosphere not pre-
viously emitted.
"Monitoring device" means the total
equipment, required under the moni-
toring of operations sections in appli-
cable subparts, used to measure and
record (if applicable) process param-
eters.
"Nitrogen oxides" means all oxides
of nitrogen except nitrous oxide, as
measured by test methods set forth in
this part.
"One-hour period" means any 60-
minute period commencing on the
hour.
"Opacity" means the degree to
which emissions reduce the transmis-\
sion of light and obscure the view of"
an object in the background.
"Owner or operator" means any
person who owns, leases, operates, con-
trols, or supervises an affected facility
or a stationary source of which an af-
fected facility is a part.
"Particulate matter" means any
finely divided solid or liquid material,
other than uncombined water, as
measured by the reference methods
specified under each applicable sub-
part, or an equivalent or alternative
method.
"Proportional sampling" means sam-
pling at a rate that produces a con-
stant ration of sampling rate to stack
gas flow rate.
"Reference method" means any
method of sampling and analyzing for
an air pollutant as described in Appen-
dix A to this part.
"Run" means the net period of time
during which an emission sample is
collected. Unless otherwise specified, a
run may be either intermittent or con-
tinuous within the limits of good engi-
neering practice.
"Shutdown" means the cessation of
operation of an affected facility for
any purpose.
"Six-minute period" means any one
of the 10 equal parts of a one-hour
period.
"Standard" means a standard of per-
formance proposed or promulgated
under this part.
"Standard conditions" means a tem-
perature of 293 K (68°P) and a pres-
sure of 101.3 kilopascals (29.92 in Hg).
"Startup" means the setting in oper-
ation of an affected facility for any
purpose.
"Volatile Organic Compound" means
any organic compound which partici-
pates in atmospheric photochemical
reactions; or which is measured by a
reference method, an equivalent
method, an alternative method, or
which is determined by procedures
specified under any subpart.
[44 FR 55173, Sept. 25, 1979, as amended at
45 FR 5617, Jan. 23, 1980; 45 FR 85415, Dec.
24, 1980]
§ 60.3 Units and abbreviations.
Used in this part are abbreviations
and symbols of units of measure.
These are defined as follows:
(a) System International (SI) units
of measure:
A—ampere
g—gram
Hz—hertz
J—joule
K—degree Kelvin
kg—kilogram
m—meter
m3—cubic meter
mg—milligram—10"3 gram
mm—millimeter—10"3 meter
Mg—megagram—106 gram
mol—mole
N—newton
ng—nanogram—10"9 gram
nm—nanometer—10"» meter
Pa—pascal
s—second
V—volt
W—watt
ft—ohm
Hg—microgram—10"6 gram
(b) Other units of measure:
Btu—British thermal unit
°C—degree Celsius (centigrade)
cal—calorie
cfm—cubic feet per minute
cu ft—cubic feet
dcf—dry cubic feet
dcm—dry cubic meter
dscf—dry cubic feet at standard conditions
dscm—dry cubic meter at standard condi-
tions
eq—equivalent
94
-------
Chapter I—Environmental Protection Agency
§60.4
°F—degree Fahrenheit
ft—feet
gal—gallon
gr—grain
g-eq—gram equivalent
hr—hour
in—inch
k—1,000
1—liter
1pm—liter per minute
Ib—pound
meq—milliequivalent
min—minute
ml—milliliter
mol. wt.—molecular weight
ppb—parts per billion
ppm—parts per million
psia—pounds per square inch absolute
psig—pounds per square inch gage
°R—degree Rankine
scf—cubic feet at standard conditions
scfh—cubic feet per hour at standard condi-
tions
scm—cubic meter at standard conditions
sec—second
sq ft—square feet
std—at standard conditions
(c) Chemical nomenclature:
CdS—cadmium sulfide
CO—carbon monoxide
COs—carbon dioxide
HC1—hydrochloric acid
Hg—mercury
HaO—water
H,S—hydrogen sulfide
HjSO*—sulfuric acid
N3—nitrogen
NO—nitric oxide
NO,—nitrogen dioxide
NO,—nitrogen oxides
O,—oxygen
SO,—sulfur dioxide
SO,—sulfur trioxide
SO,—sulfur oxides
(d) Miscellaneous:
A.S.T.M.—American Society for Testing and
Materials
(Sees. Ill and 301
-------
§60.4
Title 40—Protection of Environment
sion. 645 S. McDonough Street, Montgom-
ery, Alabama 36104.
(C) [Reserved]
(D) Arizona:
Maricopa County Department of Health
Services. Bureau of Air Pollution Control,
1825 East Roosevelt Street, Phoenix, AZ
85006.
Pima County Health Department, Air
Quality Control District, 151 West Congress,
Tucson, AZ 85701.
Pima County Air Pollution Control Dis-
trict, 151 West Congress Street, Tucson, AZ
85701.
(E) [Reserved]
(F) California:
Bay Area Air Pollution Control District, 939
Ellis Street, San Francisco, CA 94109.
Del Norte County Air Pollution Control Dis-
trict, Courthouse, Crescent City, CA
95531.
Frensno County Air Pollution Control Dis-
trict, 515 S. Cedar Avenue, Fresno, CA
93702.
Humboldt County Air Pollution Control
District, 5600 S. Broadway, Eureka, CA
95501.
Kern County Air Pollution Control District,
1700 Flower Street (P.O. Box 997), Bakers-""
field. CA 93302.
Madera County Air Pollution Control Dis-
trict, 135 W. Yosemite Avenue, Madera,
CA 93637.
Mendocino County Air Pollution Control
District. County Courthouse, Ukiah, CA
95482.
Monterey Bay Unified Air Pollution Control
District, 420 Church Street (P.O. Box 487)
Salinas, CA 93901.
Northern Sonoma County Air Pollution
Control District, 3313 Chanate Road,
Santa Rosa, CA 95404.
Sacramento County Air Pollution Control
District, 3701 Branch Center Road, Sacra-
mento, CA 95827.
San Diego County Air Pollution Control
District, 9150 Chesapeake Drive, San
Diego. CA 92123.
San Joaquin County Air Pollution Control
District, 1601 E, Hazelton Street (P.O.
Box 2009) Stockton, CA 95201.
Santa Barbara County Air Pollution Con-
trol District, 4440 Calle Real, Santa Bar-
bara, CA 93110.
Shasta County Air Pollution Control Dis-
trict. 1855 Placer Street, Redding, CA
96001.
South Coast Air Quality Management Dis-
trict, 9420 Telstar Avenue, El Monte, CA
91731.
Stanislaus County Air Pollution Control
District, 820 Scenic Drive, Modesto, CA
95350.
Trinity County Air Pollution Control Dis-
trict, Box AJ, Weaverville, CA 96093.
Ventura County Air Pollution Control Dis-
trict, 625 E. Santa Clara Street, Ventura.
CA 93001.
(G) State of Colorado, Colorado Air Pollu-
tion Control Division, 4210 East llth
Avenue, Denver, Colorado 80220.
(H) State of Connecticut, Department of
Environmental Protection, State Office
Building, Hartford, Connecticut 06115.
(I) State of Delaware (for fossil fuel-fired
steam generators; incinerators; nitric acid
plants; asphalt concrete plants; storage ves-
sels for petroleum liquids; sulfuric acid
plants; sewage treatment plants; and elec-
tric utility steam generating units), Dela-
ware Department of Natural Resources and
Environmental Control, Edward Tatnall
Building, Dover Delaware 19901.
(J)—(K) [Reserved]
(L) State of Georgia, Environmental Pro-
tection Division, Department of Natural Re-
sources, 270 Washington Street, S.W., At-
lanta, Georgia 30334.
(M) [Reserved]
(N) State of Idaho, Department of Health
and Welfare, Statehouse, Boise, Idaho
83701.
(O) [Reserved]
(P) State of Indiana, Indiana Air Pollu-
tion Control Board, 1330 West Michigan
Street, Indianapolis, Indiana 46206.
(Q) State of Iowa, Iowa Department of
Environmental Quality, Henry A. Wallace
Building, 900 East Grand, Des Moines, Iowa
50316.
(R) [Reserved]
(S) Division of Air Pollution Control, De-
partment for Natural Resources and Envi-
ronmental Protection, U.S. 127, Frankfort,
Ky. 40601.
(T) [Reserved]
(U) State of Maine, Department of Envi-
ronmental Protection, State House, Augus-
ta, Maine 04330.
(V) State of Maryland: Bureau of Air
Quality and Noise Control, Maryland State
Department of Health and Mental Hygiene,
201 West Preston Street, Baltimore, Mary-
land 21201.
(W) Massachusetts Department of Envi-
ronmental Quality Engineering. Division of
Air Quality Control, 600 Washington Street,
Boston, Massachusetts 02111.
(X) State of Michigan, Air Pollution Con-
trol Division. Michigan Department of Nat-
ural Resources, Stevens T. Mason Building,
8th Floor, Lansing, Michigan 48926.
(T) Minnesota Pollution Control Agency,
Division of Air Quality, 1935 West County
Road B-2, Roseville, Minn. 55113.
(Z) [Reserved]
96
-------
Chapter I—Environmental Protection Agency
§60.4
(AA) Missouri Department of Natural Re-
sources, Post Office Box 1368, Jefferson
City, Missouri 65101.
(BB) State of Montana, Department of
Health and Environmental Services, Cogs-
well Building, Helena, Mont. 59601.
(CO Nebraska Department of Environ-
mental Control, P.O. Box 94653, State
House Station, Lincoln, Nebraska 68509.
(DD) Nevada:
Nevada Department of Conservation and
Natural Resources, Division of Environ-
mental Protection, 201 South Pall Street,
Carson City, NV 89710.
Clark County County District Health De-
partment, Air Pollution Control Division,
625 Shadow Lane, Las Vegas, NV 89106.
Washoe County District Health Depart-
ment, Division of Environmental Protec-
tion, 10 Kirman Avenue, Reno, NV 89502.
(EE) New Hampshire Air Pollution Con-
trol Agency, Department of Health and
Welfare, State Laboratory Building, Hazen
Drive, Concord, New Hampshire 03301.
(FF) State of New Jersey: New Jersey De-
partment of Environmental Protection,
John Pitch Plaza, P.O. Box 2807, Trenton,
New Jersey 08625. __
(GG) [Reserved]
(HH) New York: New York State Depart-
ment of Environmental Conservation, 50
Wolf Road, New York 12233, attention: Di-
vision of Air Resources.
(II) North Carolina Environmental Man-
agement Commission, Department of Natu-
ral and Economic Resources, Division of En-
vironmental Management, P.O. Box 27687,
Raleigh, North Carolina 27611. Attention:
Air Quality Section.
(JJ) State of North Dakota, State Depart-
ment of Health, State Capitol, Bismarck,
North Dakota 58501.
(KK) Ohio-
Medina, Summit and Portage Counties; Di-
rector, Air Pollution Control, 177 South
Broadway, Akron, Ohio 44308.
Stark County; Director, Air Pollution Con-
trol Division, Canton City Health Depart-
ment, City Hall, 218 Cleveland Avenue
SW., Canton, Ohio 44702.
Butler, Clermont, Hamilton and Warren
Counties; Superintendent, Division of Air
Pollution Control, 2400 Beekman Street,
Cincinnati, Ohio 45214.
Cuyahoga County; Commissioner, Division
of Air Pollution Control, Department of
Public Health and Welfare, 2735 Broad-
way Avenue, Cleveland, Ohio 44115.
Lorain County; Control Officer, Division of
Air Pollution Control, 200 West Erie
Avenue, 7th Floor, Lorain, Ohio 44052.
Belmont, Carroll, Columbiana, Harrison.
Jefferson, and Monroe Counties; Director,
North Ohio Valley Air Authority
(NOVAA), 814 Adams Street, Steubenville,
Ohio 43952.
Clark, Darke, Greene, Miami, Montgomery,
and Preble Counties; Supervisor, Regional
Air Pollution Control Agency (RAPCA),
Montgomery County Health Department,
451 West Third Street, Dayton, Ohio
45402.
Lucas County and the City of Rossford (in
Wood County); Director, Toledo Pollution
Control Agency, 26 Main Street, Toledo,
Ohio 43605.
Adams, Brown, Lawrence, and Scioto Coun-
ties; Engineer-Director, Air Division,
Portsmouth City Health Department, 740
Second Street, Portsmouth, Ohio 45662.
Allen, Ashland, Auglaize, Crawford, Defi-
ance, Erie, Fulton, Hancock, Hardin,
Henry, Huron, Knox, Marion, Mercer,
Morrow, Ottawa, Paulding, Putnam, Rich-
land, Sandusky, Seneca, Van Wert, Wil-
liams, Wood (except City of Rossford),
and Wyandot Counties; Ohio Environmen-
tal Protection Agency, Northwest District
Office, 111 West Washington Street,
Bowling Green, Ohio 43402.
Ashtabula, Geauga, Lake, Mahoning, Trum-
bull, and Wayne Counties; Ohio Environ-
mental Protection Agency, Northeast Dis-
trict Office, 2110 East Aurora Road,
Twinsburg, Ohio 44087.
Athens, Coshocton, Gallia, Guernsey, High-
land, Hocking, Holmes, Jackson, Meigs,
Morgan, Muskingum, Noble, Perry, Pike,
Ross, Tuscarawas, Vinton, and Washing-
ton Counties; Ohio Environmental Protec-
tion Agency, Southeast District Office,
Route 3, Box 603, Logan, Ohio 43138.
Champaign, Clinton, Logan, and Shelby
Counties; Ohio Environmental Protection
Agency, Southwest District Office, 7 East
Fourth Street, Dayton, Ohio 45402.
Delaware, Fairfield, Fayette, Franklin, Lick-
ing, Madison, Pickaway, and Union Coun-
ties; Ohio Environmental Protection
Agency, 'Central District Office, 369 East
Broad Street, Columbus, Ohio 43215.
(LL) [Reserved]
(MM) State of Oregon, Department of En-
vironmental Quality, 1234 SW. Morrison
Street, Portland, Oregon 97205.
(NN) (a) City of Philadelphia: Philadel-
phia Department of Public Health, Air
Management Services, 801 Arch Street,
Philadelphia, Pennsylvania 19107.
(b) Commonwealth of Pennsylvania, De-
partment of Environmental Resources, Post
Office Box 2063, Harrisburg, Pennsylvania
17120.
(OO) State of Rhode Island, Department
of Environmental Management, 83 Park
Street, Providence, Rhode Island 02908.
(PP) State of South Carolina, Office of
Environmental Quality Control, Depart-
ment of Health and Environmental Control,
2600 Bull Street, Columbia, South Carolina
29201.
97
-------
§60.5
Title 40—Protection of Environment
(QQ) State of South Dakota, Department
of Environmental Protection, Joe Poss
Building. Pierre. South Dakota 57501.
CRR) Division of Air Pollution Control.
Tennessee Department of Public Health,
256 Capitol Hill Building. Nashville, Tennes-
see 37219.
(SS) State of Texas, Texas Air Control
Board. 8520 Shoal Creek Boulevard, Austin,
Texas 78758
(TT) State of Utah, Utah Air Conserva-
tion Committee, State Division of Health,
44 Medical Drive, Salt Lake City, Utah
84113.
(UU) State of Vermont, Agency of Envi-
ronmental Protection, Box 489. Montpelier,
Vermont 05602.
(W) Commonwealth of Virginia, Virginia
State Air Pollution Control Board, Room
1106, Ninth Street Office Building. Rich-
mond. Virginia 23219.
(WW) Washington: State of Washing-
ton, Department of Ecology. Olympia,
Washington 98504.
(ii) Northwest Air Pollution Authority,
207 Pioneer Building, Second and Pine
Streets, Mount Vernon, Washington 98273.
(iii) Puget Sound Air Pollution Control
Agency, 410 West Harrison Street, Seattle,
Washington 98119. . _.
(iv) Spokane County Air Pollution Control
Authority, North 811 Jefferson, Spokane,
Washington 99201.
(v) Southwest Air Pollution Control Au-
thority, Suite 7601 H, NE Hazel Dell
Avenue, Vancouver, Washington 98665.
(vi) Olympic Air Pollution Control Au-
thority, 120 East State Avenue, Olympia,
WA 98501.
(XX) [Reserved]
(YY) Wisconsin—Wisconsin Department
of Natural Resources, P.O. Box 7921, Madi-
son. Wisconsin 53707.
(ZZ) State of Wyoming, Air Quality Divi-
sion of the Department of Environmental
Quality. Hathaway Building, Cheyenne,
Wyo. 82002.
(AAA) [Reserved]
(BBB) Commonwealth of Puerto Rico:
Commonwealth of Puerto Rico Environ-
mental Quality Board, P.O. Box 11785, San-
turce, P.R. 00910.
(CCC) U.S. Virgin Islands: U.S. Virgin Is-
lands Department of Conservation and Cul-
tural Affairs, P.O. Box 578, Charlotte
Amalie, St. Thomas, U.S. Virgin Islands
00801.
(Sees. 101, 110, 111. 112. 114, 160-169, 301.
Clean Air Act as amended (42 U.S.C. 7401,
7410, 7411. 7412. 7414. 7470-7479, 7491,
7601))
C40 PR 18169, Apr. 25. 1975, as amended at
40 PR 26677, June 25, 1975]
NOTE For amendments to § 60.4 see the
List of CPR Section^ Affected appearing in
the Finding Aids section of this volume.
§ 60.5 Determination of construction or
modification.
(a) When requested to do so by an
owner or operator, the Administrator
will make a determination of whether
action taken or intended to be taken
by such owner or operator constitutes
construction (including reconstruc-
tion) or modification or the com-
mencement thereof within the mean-
ing of this part.
(b) The Administrator will respond
to any request for a determination
under paragraph (a) of this section
within 30 days of receipt of such re-
quest.
[40 FR 58418, Dec. 16, 1975]
§ 60.6 Review of plans.
(a) When requested to do so by an
owner or operator, the Administrator
will review plans for construction or
modification for the purpose of pro-
viding technical advice to the owner or
operator.
(bXl) A separate request shall be
submitted for each construction or
modification project.
(2) Each request shall identify the
location of such project, and be accom-
panied by technical information de-
scribing the proposed nature, size,
design, and method of operation of
each affected facility involved in such
project, including information on any
equipment to be used for measure-
ment or control of emissions.
(c) Neither a request for plans
review nor advice furnished by the Ad-
ministrator in response to such re-
quest shall (1) relieve an owner or op-
erator of legal responsibility for com-
pliance with any provision of this part
or of any applicable State or local re-
quirement, or (2) prevent the Adminis-
trator from implementing or enforcing
any provision of this part or taking
any other action authorized by the
Act.
[36 FR 24877, Dec. 23, 1971, as amended at
39 FR 9314, Mar. 8, 1974]
§ 60.7 Notification and record keeping.
(a) Any owner or operator subject to
the provisions of this part shall fur-
nish the Administrator written notifi-
cation as follows:
98
-------
Chapter I—Environmental Protection Agency
§60.7
(1) A notification of the date con-
struction (or reconstruction as defined
under § 60.15) of an affected facility is
commenced postmarked no later than
30 days after such date. This require-
ment shall not apply in the case of
mass-produced facilities which are
purchased in completed form.
(2) A notification of the anticipated
date of initial startup of an affected
facility postmarked not more than 60
days nor less than 30 days prior to
such date.
(3) A notification of the actual date
of initial startup of an affected facility
postmarked within 15 days after such
date.
(4) A notification of any physical or
operational change to an existing fa-
cility which may increase the emission
rate of any air pollutant to which a
standard applies, unless that change is
specifically exempted under an appli-
cable subpart or in § 60.14(e). This
notice shall be postmarked 60 days or
as soon as practicable before the
change is commenced and shall in~~
elude information describing the pre-
cise nature of the change, present and
proposed emission control systems,
productive capacity of the facility
before and after the change, and the
expected completion date of the
change. The Administrator may re-
quest additional relevant information
subsequent to this notice.
(5) A notification of the date upon
which demonstration of the continu-
ous monitoring system performance
commences in accordance with
§ 60.13(c). Notification shall be post-
marked not less than 30 days prior to
such date.
(b) Any owner or operator subject to
the provisions of this part shall main-
tain records of the occurrence and du-
ration of any startup, shutdown, or
malfunction in the operation of an af-
fected facility; any malfunction of the
air pollution control equipment; or
any periods during which a continuous
monitoring system or monitoring
device is inoperative.
(c) Each owner or operator required
to install a continuous monitoring
system shall submit a written report
of excess emissions (as defined in ap-
plicable subparts) to the Administra-
tor for every calendar quarter. All
quarterly reports shall be postmarked
by the 30th day following the end of
each calendar quarter and shall in-
clude the following information:
(1) The magnitude of excess emis-
sions computed in accordance with
§ 60.13(h), any conversion factor(s)
used, and the date and time of com-
mencement and completion of each
time period of excess emissions.
(2) Specific identification of each
period of excess emissions that occurs
during startups, shutdowns, and mal-
functions of the affected facility. The
nature and cause of any malfunction
(if known), the corrective action taken
or preventative measures adopted.
(3) The date and time identifying
each period during which the continu-
ous monitoring system was inoperative
except, for zero and span checks and
the nature of the system repairs or ad-
justments.
(4) When no excess emissions have
occurred or the continuous monitoring
system(s) have not been inoperative,
repaired, or adjusted, such informa-
tion shall be stated in the report.
(d) Any owner or operator subject to
the provisions of this part shall main-
tain a file of all measurements, includ-
ing continuous monitoring system,
monitoring device, and performance
testing measurements; all continuous
monitoring system performance evalu-
ations; all continuous monitoring
system or monitoring device calibra-
tion checks; adjustments and mainte-
nance performed on these systems or
devices; and all other information re-
quired by this part recorded in a per-
manent form suitable for inspection.
The file shall be retained for at least
two years following the date of such
measurements, maintenance, reports,
and records.
(e) If notification substantially simi-
lar to that in paragraph (a) of this sec-
tion is required by any other State or
local agency, sending the Administra-
tor a copy of that notification will sat-
isfy the requirements of paragraph (a)
of this section.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[36 PR 24877, Dec. 28, 1971, as amended at
40 PR 46254, Oct. 6, 1975; 40 PR 58418i Dec.
99
-------
§60.8
Title 40—Protection of Environment
16. 1975; 43 PR 8800, Mar. 3, 1978; 45 PR
5617, Jan. 23,1980]
§ 60.8 Performance tests.
(a) Within 60 days after achieving
the maximum production rate at
which the affected facility will be op-
erated, but not later than 180 days
after initial startup of such facility
and at such other times as may be re-
quired by the Administrator under sec-
tion 114 of the Act, the owner or oper-
ator of such facility shall conduct per-
formance test(s) and furnish the Ad-
ministrator a written report of the re-
sults of such performance test(s).
(b) Performance tests shall be con-
ducted and data reduced in accordance
with the test methods and procedures
contained in each applicable subpart
unless the Administrator (1) specifies
or approves, in specific cases, the use
of a reference method with minor
changes in methodology, (2) approves
the use of an equivalent method, (3)
approves the use of an alternative_
method the results of which he has"
determined to be adequate for indicat-
ing whether a specific source is in
compliance, or (4) waives the require-
ment for performance tests because
the owner or operator of a source has
demonstrated by other means to the
Administrator's satisfaction that the
affected facility is in compliance with
the standard. Nothing in this para-
graph shall be construed to abrogate
the Administrator's authority to re-
quire testing under section 114 of the
Act.
(c) Performance tests shall be con-
ducted under such conditions as the
Administrator shall specify to the
plant operator based on representative
performance of the affected facility.
The owner or operator shall make
available to the Administrator such re-
cords as may be necessary to deter-
mine the conditions of the perform-
ance tests. Operations during periods
of startup, shutdown, and malfunction
shall not constitute representative
conditions for the purpose of a per-
formance test nor shall emissions in
excess of the level of the applicable
emission limit during periods of star-
tup, shutdown, and malfunction be
considered a violation of the applica-
ble emission limit unless otherwise
specified in the applicable standard.
(d) The owner or operator of an af-
fected facility shall provide the Ad-
ministrator at least 30 days prior
notice of any performance test, except
as specified under other subparts, to
afford the Administrator the opportu-
nity to have an observer present.
(e) The owner or operator of an af-
fected facility shall provide, or cause
to be provided, performance testing
facilities as follows:
(1) Sampling ports adequate for test
methods applicable to such facility.
(2) Safe sampling platform(s).
(3) Safe access to sampling
platform(s).
(4) Utilities for sampling and testing
equipment.
(f) Unless otherwise specified in the
applicable subpart, each performance
test shall consist of three separate
runs using the applicable test method.
Each run shall be conducted for the
time and under the conditions speci-
fied in the applicable standard. For
the purpose of determining compli-
ance with an applicable standard, the
arithmetic means of results of the
three runs shall apply. In the event
that a sample is accidentally lost or
conditions occur in which one of the
three runs must be discontinued be-
cause of forced shutdown, failure of
an irreplaceable portion of the sample
train, extreme meteorological condi-
tions, or other circumstances, beyond
the owner or operator's control, com-
pliance may, upon the Administrator's
approval, be determined using the
arithmetic mean of the results of the
two other runs.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[36 PR 24877, Dec. 23, 1971, as amended at
39 PR 9314. Mar. 8, 1974; 42 PR 57126, Nov.
1, 1977; 43 PR 8800, Mar. 3, 1978; 44 PR
33612, June 11, 1979]
§ 60.9 Availability of information.
The availability to the public of in-
formation provided to, or otherwise
obtained by, the Administrator under
this Part shall be governed by Part 2
of this chapter. (Information submit-
ted voluntarily to the Administrator
for the purposes of § § 60.5 and 60.6 is
100
-------
Chapter I—Environmental Protection Agency
§60.11
governed by § 2.201 through § 2.213 of
this chapter and not by § 2.301 of this
chapter.)
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[41 PR 36918, Sept. 1, 1976, as amended at
43 PR 8800, Mar. 3, 1978]
§ 60.10 State authority.
The provisions of this part shall not
be construed in any manner to pre-
clude any State or political subdivision
thereof from:
(a) Adopting and enforcing any
emission standard or limitation appli-
cable to an affected facility, provided
that such emission standard or limita-
tion is not less stringent1 than the
standard applicable to such facility.
(b) Requiring the owner or operator
of an affected facility to obtain per-
mits, licenses, or approvals prior to ini-
tiating construction, modification, or
operation of such facility.
(Sec. 116, Clean Air Act as amended (42-.
U.S.C. 7416))
[36 PR 24877, Dec. 23, 1971, as amended at
43 PR 8800, Mar. 3, 1978]
§60.11 Compliance with standards and
maintenance requirements.
(a) Compliance with standards in
this part, other than opacity stand-
ards, shall be determined only by per-
formance tests established by § 60.8,
unless otherwise specified in the appli-
cable standard.
(b) Compliance with opacity stand-
ards in this part sho.ll be determined
by conducting observations in accord-
ance with Reference Method 9 in Ap-
pendix A of this part or any alterna-
tive method that is approved by the
Administrator. Opacity readings of
portions of plumes which contain con-
densed, uncombined water vapor shall
not be used for purposes of determin-
ing compliance with opacity standards.
The results of continuous monitoring
by transmissonieter which indicate
that the opacity at the time visual ob-
servations were made was not in
excess of the standard are probative
but not conclusive evidence of the
actual opacity of an emission, provided
that the source shall meet the burden
of proving that the instrument used
meets (at the time of the alleged viola-
tion) Performance Specification 1 in
Appendix B of this part, has been
properly maintained and (at the time
of the alleged violation) calibrated,
and that the resulting data have not
been tampered with in any way.
(c) The opacity standards set forth
in this part shall apply at all times
except during periods of startup, shut-
down, malfunction, and as otherwise
provided in the applicable standard.
(d) At all times, including periods of
startup, shutdown, and malfunction,
owners and operators shall, to the
extent practicable, maintain and oper-
ate any affected facility including as-
sociated air pollution control equip-
ment in a manner consistent with
good air pollution control practice for
minimizing emissions. Determination
of whether acceptable operating and
maintenance procedures are being
use'd will be based on information
available to the Administrator which
may include, but is not limited to,
monitoring results, opacity observa-
tions, review of operating and mainte-
nance procedures, and inspection of
the source.
(eXl) An owner or operator of an af-
fected facility may request the Admin-
istrator to determine opacity of emis-
sions from the affected facility during
the initial performance tests required
by § 60.8.
(2) Upon receipt from such owner or
operator of the written report of the
results of the performance tests re-
quired by § 60.8, the Administrator will
make a finding concerning compliance
with opacity and other applicable
standards. If the Administrator finds
that an affected facility is in compli-
ance with all applicable standards for
which performance tests are conduct-
ed in accordance with § 60.8 of this
part but during the time such per-
formance tests are being conducted
fails to meet any applicable opacity
standard, he shall notify the owner or
operator and advise him that he may
petition the Administrator within 10
days of receipt of notification to make
appropriate adjustment to the opacity
standard for the affected facility.
(3) The Administrator will grant
such a petition upon a demonstration
by the owner or operator that the af-
fected facility and associated air pollu-
101
-------
§ 60.12
Title 40—Protection of Environment
tion control equipment was operated
and maintained in a manner to mini-
mize the opacity of emissions during
the performance tests; that the per-
formance tests were performed under
the conditions established by the Ad-
ministrator; and that the affected fa-
cility and associated air pollution con-
trol equipment were incapable of
being adjusted or operated to meet the
applicable opacity standard.
(4) The Administrator will establish
an opacity standard for the affected
facility meeting the above require-
ments at a level at which the source
will be able, as indicated by the per-
formance and opacity tests, to meet
the opacity standard at all times
during which the source is meeting
the mass or concentration emission
standard. The Administrator will pro-
mulgate the new opacity standard in
the FEDERAL REGISTER.
(Sec. 114, Clean Air Act as amended (42
0.S.C. 7414))
t38 PR 28565, Oct. 15, 1973, as amended at"""
39 PR 39873, Nov. 12. 1974; 42 FR 26206,
May 23, 1977; 43 FR 8800. Mar. 3, 1978: 45
FR 23379, Apr. 4. 1980]
§ 60.12 Circumvention.
No owner or operator subject to the
provisions of this part shall build,
erect, install, or use any article, ma-
chine, equipment or process, the use of
which conceals an emission which
would otherwise constitute a violation
of an applicable standard. Such con-
cealment includes, but is not limited
to, the use of gaseous diluents to
achieve compliance with an opacity
standard or with a standard which is
based on the concentration of a pollut-
ant in the gases discharged to the at-
mosphere.
£39 FR 9314. Mar. 8. 1974]
§ 60.13 Monitoring requirements.
(a) For the purposes of this section,
all continuous monitoring systems re-
quired under applicable subparts shall
be subject to the provisions of this sec-
tion upon promulgation of perform-
ance specifications for continuous
monitoring system under Appendix B
to this part, unless:
(1) The continuous monitoring
system is subject to the provisions of
paragraphs (c)(2) and (c)(3) of this
section, or
(2) otherwise specified in an applica-
ble subpart or by the Administrator.
(b) All continuous monitoring sys-
tems and monitoring devices shall be
installed and operational prior to con-
ducting performance tests under
§ 60.8. Verification of operational
status shall, as a minimum, consist of
the following:
(1) For continuous monitoring sys-
tems referenced in paragraph (c)(l) of
this section, completion of the condi-
tioning period specified by applicable
requirements in Appendix B.
(2) For continuous monitoring sys-
tems referenced in paragraph (c)(2) of
this section, completion of seven days
of operation.
(3) For monitoring devices refer-
enced in applicable subparts, comple-
tion of the manufacturer's written re-
quirements or recommendations for
checking the operation or calibration
of the device.
(c) During any performance tests re-
quired under § 60.8 or within 30 days
thereafter and at such other times as
may be required by the Administrator
under section 114 of the Act, the
owner or operator of any affected fa-
cility shall conduct continuous moni-
toring system performance evaluations
and furnish the Administrator within
60 days thereof two or, upon request,
more copies of a written report of the
results of such tests. These continuous
monitoring system performance evalu-
ations shall be conducted in accord-
ance with the following specifications
and procedures:
(1) Continuous monitoring systems
listed within this paragraph except as
provided in paragraph (c)(2) of this
section shall be evaluated in accord-
ance with the requirements and proce-
dures contained in the applicable per-
formance specification of Appendix B
as follows:
(i) Continuous monitoring systems
for measuring opacity of emissions
shall comply with Performance Speci-
fication 1.
(ii) Continuous monitoring systems
for measuring nitrogen oxides emis-
sions shall comply with Performance
Specification 2.
102
-------
Chapter I—Environmental Protection Agency
§ 60.13
(iii) Continuous monitoring systems
for measuring sulfur dioxide emissions
shall comply with Performance Speci-
fication 2.
(iv) Continuous monitoring systems
for measuring the oxygen content or
carbon dioxide content of effluent
gases shall comply with Performance
Specification 3.
(2) An owner or operator who, prior
to September 11, 1974, entered into a
binding contractual obligation to pur-
chase specific continuous monitoring
system components except as refer-
enced by paragraph (c)(2)(iii) of this
section shall comply with the follow-
ing requirements:
(i) Continuous monitoring systems
for measuring opacity of emissions
shall be capable of measuring emission
levels within ±20 percent with a confi-
dence level of 95 percent. The Calibra-
tion Error Test and associated calcula-
tion procedures set forth in Perform-
ance Specification 1 of Appendix B
shall be used for demonstrating com-
pliance with this specification.
(ii) Continuous monitoring systems
for measurement of nitrogen oxides or
sulfur dioxide shall be capable of
measuring emission levels within ±20
percent with a confidence level of 95
percent. The Calibration Error Test,
the Field Test for Accuracy (Relative),
and associated operating and calcula-
tion procedures set forth in Perform-
ance Specification 2 of Appendix B
shall be used for demonstrating com-
pliance with this specification.
(iii) Owners or operators of all con-
tinuous monitoring systems installed
on an affected facility prior to October
6, 1975 are not required to conduct
tests under paragraphs (c)(2)(i) and/or
(ii) of this section unless requested by
the Administrator.
(3) All continuous monitoring sys-
tems referenced by paragraph (c)(2) of
this section shall be upgraded or re-
placed (if necessary) with new con-
tinuous monitoring systems, and the
new or improved systems shall be dem-
onstrated to comply with applicable
performance specifications under
paragraph (c)(l) of this section on or
before September 11, 1979.
(d) Owners or operators of all con-
tinuous monitoring systems installed
in accordance with the provisions of
this part shall check the zero and span
drift at least once daily in accordance
with the method prescribed by the
manufacturer of such systems unless
the manufacturer recommends adjust-
ments at shorter intervals, in which
case such recommendations shall be
followed. The zero and span shall, as a
minimum, be adjusted whenever the
24-hour zero drift or 24-hour calibra-
tion drift limits of the applicable per-
formance specifications in Appendix B
are exceeded. For continuous monitor-
ing systems measuring opacity of emis-
sions, the optical surfaces exposed to
the effluent gases shall be cleaned
prior to performing the zero or span
drift adjustments except that for sys-
tems using automatic zero adjust-
ments, the optical surfaces shall be
cleaned when the cumulative automat-
ic zero compensation exceeds four per-
cent opacity. Unless otherwise ap-
proved by the Administrator, the fol-
lowing procedures, as applicable, shall
be followed:
(1) For extractive continuous moni-
toring systems measuring gases, mini-
mum procedures shall include intro-
ducing applicable zero and span gas
mixtures into the measurement
system as near the probe as is practi-
cal. Span and zero gases certified by
their manufacturer to be traceable to
National Bureau of Standards refer-
ence gases shall be used whenever
these reference gases are available.
The span and zero gas mixtures shall
be the same composition as specified
in Appendix B of this part. Every six
months from date of manufacture,
span and zero gases shall be reana-
lyzed by conducting triplicate analyses
with Reference Methods 6 for SO2, 7
for NO,, and 3 for Oa and CO,, respec-
tively. The gases may be analyzed at
less frequent intervals if longer shelf
lives are guaranteed by the manufac-
turer.
(2) For non-extractive continuous
monitoring systems measuring gases,
minimum procedures shall include
upscale check(s) using a certified cali-
bration gas cell or test cell which is
functionally equivalent to a known gas
concentration. The zero check may be
performed by computing the zero
value from upscale measurements or
103
-------
§60.13
by mechanically producing a zero con-
dition.
(3) For continuous monitoring sys-
tems measuring opacity of emissions,
minimum procedures shall include a
method for producing a simulated zero
opacity condition and an upscale
(span) opacity condition using a certi-
fied neutral density filter or other re-
lated technique to produce a known
obscuration of the light beam. Such
procedures shall provide a system
check of the analyzer internal optical
surfaces and all electronic circuitry in-
cluding the lamp and photodetector
assembly.
(e) Except for system breakdowns,
repairs, calibration checks, and zero
and span adjustments required under
paragraph (d) of this section, all con-
tinuous monitoring systems shall be in
continuous operation and shall meet
minimum frequency of operation re-
quirements as follows:
(1) All continuous monitoring sys-
tems referenced by paragraphs (cXl)
and (c)(2) of this section for measur-—
ing opacity of emissions shall complete
a minimum of one cycle of sampling
and analyzing for each successive ten-
second period and one cycle of data re-
cording for each successive six-minute
period.
(2) All continuous monitoring sys-
tems referenced by paragraph (c)(l) of
this section for measuring oxides of ni-
trogen, sulfur dioxide, carbon dioxide,
or oxygen shall complete a minimum
of one cycle of operation (sampling,
analyzing, and data recording) for
each successive 15-minute period.
(3) All continuous monitoring sys-
tems referenced by paragraph (c)(2) of
this section, except opacity, shall com-
plete a minimum of one cycle of oper-
ation (sampling, analyzing, and data
recording) for each successive one-
hour period.
(f) All continuous monitoring sys-
tems or monitoring devices shall be in-
stalled such that representative meas-
urements of emissions or process pa-
rameters from the affected facility are
obtained. Additional procedures for lo-
cation of continuous monitoring sys-
tems contained in the applicable Per-
formance Specifications of Appendix
B of this part shall be used.
Title 40—Protection of Environment
(g) When the effluents from a single
affected facility or two or more affect-
ed facilities subject to the same emis-
sion standards are combined before
being released to the atmosphere, the
owner or operator may install applica-
ble continuous monitoring systems on
each effluent or on the combined ef-
fluent. When the affected facilities are
not subject to the same emission
standards, separate continuous moni-
toring systems shall be installed on
each effluent. When the effluent from
one affected facility is released to the
atmosphere through more than one
point, the owner or operator shall in-
stall applicable continuous monitoring
systems on each separate effluent
unless the installation of fewer sys-
tems is approved by the Administra-
tor.
(h) Owners or operators of all con-
tinuous monitoring systems for mea-
surement of opacity shall reduce all
data to six-minute averages and for
systems other than opacity to one-
hour averages for time periods under
§ 60.2 (x) and (r) respectively. Six-
minute opacity averages shall be cal-
culated from 24 or more data points
equally spaced over each six-minute
period. For systems other than opac-
ity, one-hour averages shall be com-
puted from four or more data points
equally spaced over each one-hour
period. Data recorded during periods
of system breakdowns, repairs, calibra-
tion checks, and zero and span adjust-
ments shall not be included in the
data averages computed under this
paragraph. An arithmetic or integrat-
ed average of all data may be used.
The data output of all continuous
monitoring systems may be recorded
in reduced or nonreduced form (e.g.
ppm pollutant and percent O, or lb/
million Btu of pollutant). All excess
emissions shall be converted into units
of the standard using the applicable
conversion procedures specified in sub-
parts. After conversion into units of
the standard, the data may be round-
ed to the same number of significant
digits used in subparts to specify the
applicable standard (e.g., rounded to
the nearest one percent opacity).
(i) After receipt and consideration of
written application, the Administrator
may approve alternatives to any moni-
104
-------
Chapter I—Environmental Protection Agency
taring procedures or requirements of
this part including, but not limited to
the following:
(1) Alternative monitoring require-
ments when installation of a continu-
ous monitoring system or monitoring
device specified by this part would not
provide accurate measurements due to
liquid water or other interferences
caused by substances with the effluent
§ 60.14
gases.
(2) Alternative monitoring require-
ments when the affected facility is in-
frequently operated.
(3) Alternative monitoring require-
ments to accommodate continuous
monitoring systems that require addi-
tional measurements to correct for
stack moisture conditions.
(4) Alternative locations for install-
ing continuous monitoring systems or
monitoring devices when the owner or
operator can demonstrate that instal-
lation at alternate locations will
enable accurate and representative
measurements.
(5) Alternative methods of convert""
ing pollutant concentration meas-
urements to units of the standards.
(6) Alternative procedures for per-
forming daily checks of zero and span
drift that do not involve use of span
gases or test cells.
(7) Alternatives, to the A.S.T.M. test
methods or sampling procedures speci-
fied by any subpart.
(8) Alternative continuous monitor-
ing systems that do not meet the
design or performance requirements in
Performance Specification 1, Appen-
dix B, but adequately demonstrate a
definite and consistent relationship
between its measurements and the
measurements of opacity by a system
complying with the requirements in
Performance Specification 1. The Ad-
ministrator may require that such
demonstration be performed for each
affected facility.
(9) Alternative monitoring require-
ments when the effluent from a single
affected facility or the combined efflu-
ent from two or more affected facili-
ties are released to the atmosphere
through more than one point.
(Sec. 114, Clean Air Act as amended (42
U.S.C. 7414))
[40 PR 46255, Oct. 6, 1975; 40 FR 59205,
Dec. 22, 1975, as amended at 41 PR 35185,
Aug. 20, 1976; 42 FR 5936, Jan. 31, 1977; 43
FR 7572, Feb. 23, 1978; 43 FR 8800, Mar. 3,
1978]
§ 60.14 Modification.
(a) Except as provided under para-
graphs (e) and (f) of this section, any
physical or operational change to an
existing facility which results in an in-
crease in the emission rate to the at-
mosphere of any pollutant to which a
standard applies shall be considered a
modification within the meaning of
section 111 of the Act. Upon modifica-
tion, an existing facility shall become
an affected facility for each pollutant
to which a standard applies and for
which there is an increase in the emis-
sion rate to the atmosphere.
(b) Emission rate shall be expressed
as kg/hr of any pollutant discharged
into the atmosphere for which a
standard is applicable. The Adminis-
trator shall use the following to deter-
mine emission rate:
(1) Emission factors as specified in
the latest issue of "Compilation of Air
Pollutant Emission Factors," EPA
Publication No. AP-42, or other emis-
sion factors determined by the Admin-
istrator to be superior to AP-42 emis-
sion factors, in cases where utilization
of emission factors demonstrate that
the emission level resulting from the
physical or operational change will
either clearly increase or clearly not
increase.
(2) Material balances, continuous
monitor data, or manual emission tests
in cases where utilization of emission
factors as referenced in paragraph (b)
(1) of this section does not demon-
strate to the Administrator's satisfac-
tion whether the emission level result-
ing from the physical or operational
change will either clearly increase or
clearly not increase, or where an
owner or operator demonstrates to the
Administrator's satisfaction that there
are reasonable grounds to dispute the
result obtained by the Administrator
utilizing emission factors as referenced
in paragraph (bXl) of this section.
When the emission rate is based on re-
sults from manual emission tests or
continuous monitoring systems, the
procedures specified in Appendix C of
this part shall be used to determine
whether an increase in emission rate
105
-------
§ 60.15
Title 40—Protection of Environment
has occurred. Tests shall be conducted
under such conditions as the Adminis-
trator shall specify to the owner or op-
erator based on representative per-
formance of the facility. At least three
valid test runs must be conducted
before and at least three after the
physical or operational change. All op-
erating parameters which may affect
emissions must be held constant to the
maximum feasible degree for all test
runs.
(c) The addition of an affected facili-
ty to a stationary source as an expan-
sion to that source or as a replacement
for an existing facility shall not by
itself bring within the applicability of
this part any other facility within that
source.
(d) [Reserved]
(e) The following shall not, by them-
selves, be considered modifications
under this part:
(1) Maintenance, repair, and replace-
ment which the Administrator deter-
mines to be routine for a source cate-
gory, subject to the provisions of para-
graph (c) of this section and § 60.15.
(2) An increase in production rate of
an existing facility, if that increase
can be accomplished without a capital
expenditure on that facility.
(3) An increase in the hours of oper-
ation.
(4) Use of an alternative fuel or raw
material if, prior to the date any
standard under this part becomes ap-
plicable to that source type, as pro-
vided by §60.1, the existing facility
was designed to accommodate that al-
ternative use. A facility shaU be con-
sidered to be designed to accommodate
an alternative fuel or raw material if
that use could be accomplished under
the facility's construction specifica-
tions as amended prior to the change.
Conversion to coal required for energy
considerations, as specified in section
lll(a)(8) of the Act, shall not be con-
sidered a modification.
(5) The addition or use of any
system or device whose primary func-
tion is the reduction of air pollutants,
except when an emission control
system is removed or is replaced by a
system which the Administrator deter-
mines to be less environmentally bene-
ficial.
(6) The relocation or change in own-
ership of an existing facility.
(f) Special provisions set forth under
an applicable subpart of this part shall
supersede any conflicting provisions of
this section.
(g) Within 180 days of the comple-
tion of any physical or operational
change subject to the control meas-
ures specified in paragraph (a) of this
section, compliance with all applicable
standards must be achieved.
C40 FR 58419, Deo. 16, 1975, amended at 43
FR 34347, Aug. 3, 1978; 45 FR 5617, Jan. 23.
1980]
§ 60.15 Reconstruction.
(a) An existing facility, upon recon-
struction, becomes an affected facility,
irrespective of any change in emission
rate.
(b) "Reconstruction" means the re-
placement of components of an exist-
ing facility to such an extent that:
(1) The fixed capital cost of the new
components exceeds 50 percent of the
fixed capital cost that would be re-
quired to construct a comparable en-
tirely new facility, and
(2) It is technologically and economi-
cally feasible to meet the applicable
standards set forth in this part.
(c) "Fixed capital cost" means the
capital needed to provide all the de-
preciable components.
(d) If an owner or operator of an ex-
isting facility proposes to replace com-
ponents, and the fixed capital cost of
the new components exceeds 50 per-
cent of the fixed capital cost that
would be required to construct a com-
parable entirely new facility, he shall
notify the Administrator of the pro-
posed replacements. The notice must
be postmarked 60 days (or as soon as
practicable) before construction of the
replacements is commenced and must
include the following information:
(1) Name and address of the owner
or operator.
(2) The location of the existing fa-
cility.
(3) A brief description of the exist-
ing facility and the components which
are to be replaced.
(4) A description of the existing air
pollution control equipment and the
106
-------
Chapter I—Environmental Protection Agency
§ 60.16
proposed air pollution control equip-
ment.
(5) An estimate of the fixed capital
cost of the replacements and of con-
structing a comparable entirely new
facility.
(6) The estimated life of the existing
facility after the replacements.
(7) A discussion of any economic or
technical limitations the facility may
have in complying with the applicable
standards of performance after the
proposed replacements.
(e) The Administrator will deter-
mine, within 30 days of the receipt of
the notice required by paragraph (d)
of this section and any additional in-
formation he may reasonably require,
whether the proposed replacement
constitutes reconstruction.
(f) The Administrator's determina-
tion under paragraph (e) shall be
based on:
(1) The fixed capital cost of the re-
placements in comparison to the fixed
capital cost that would be required to
construct a comparable entirely new--
facility;
(2) The estimated life of the facility
after the replacements compared to
the life of a comparable entirely new
facility;
(3) The extent to which the compo-
nents being replaced cause or contrib-
ute to the emissions from the facility;
and
(4) Any economic or technical limita-
tions on compliance with applicable
standards of performance which are
inherent in the proposed replace-
ments.
(g) Individual subparts of this part
may include specific provisions which
refine and delimit the concept ,of re-
construction set forth in this section.
[40 PR 58420, Dec. 16, 1975]
§ 60.16 Priority list.
PRIORITIZED MAJOR SOURCE CATEGORIES
Priority Number'
Source Category
1. Synthetic Organic Chemical Manufactur-
ing
(a) Unit processes
• Low numbers have highest priority; e.g.,
No. 1 is high priority, No. 59 is low priority.
(b) Storage and handling equipment
(c) Fugitive emission sources
(d) Secondary sources
2. Industrial Surface Coating: Cans
3. Petroleum Refineries: Fugitive Sources
4. Industrial Surface Coating: Paper
5. Dry Cleaning
(a) Perchioroethylene
(b) Petroleum solvent
6. Graphic Arts
7. Polymers and Resins: Acrylic Resins
8. Mineral Wool
9. Stationary Internal Combustion Engines
10. Industrial Surface Coating: Fabric
11. Fossil-Fuel-Fired Steam Generators: In-
dustrial Boilers
12. Incineration: Non-Municipal
13. Non-Metallic Mineral Processing
14. Metallic Mineral Processing
15. Secondary Copper
16. Phosphate Rock Preparation
17. Foundries: Steel and Gray Iron
18. Polymers and Resins: Polyethylene
19. Charcoal Production
20. Synthetic Rubber
(a) Tire manufacture
(b) SBR production
21. Vegetable Oil
22. Industrial Surface Coating: Metal Coil
23. Petroleum Transportation and Market-
ing
24. By-Product Coke Ovens
25. Synthetic Fibers
26. Plywood Manufacture
27. Industrial Surface Coating: Automobiles
28. Industrial Surface Coating: Large Appli-
ances
29. Crude Oil and Natural Gas Production
30. Secondary Aluminum
31. Potash
32. Sintering: Clay and Fly Ash
33. Glass
34. Gypsum
35. Sodium Carbonate
36. Secondary Zinc
37. Polymers and Resins: Phenolic
38. Polymers and Resins: Urea—Melamine
39. Ammonia
40. Polymers and Resins: Polystyrene
41. Polymers and Resins: ABS-SAN Resins
42. Fiberglass
43. Polymers and Resins: Polypropylene
44. Textile Processing
45. Asphalt Roofing Plants
46. Brick and Related Clay Products
47. Ceramic Clay Manufacturing
48. Ammonium Nitrate Fertilizer
49. Castable Refractories
50. Borax and Boric Acid
51. Polymers and Resins: Polyester Resins
52. Ammonium Sulfate
53. Starch
54. Perlite
55. Phosphoric Acid: Thermal Process
56. Uranium Refining
57. Animal Feed Defluorination
107
-------
§60.20
Titla 40—Protection of Environment
58. Urea (for fertilizer and polymers)
59. Detergent
OTHER SOURCE CATEGORIES
Lead acid battery manufacture"
Organic solvent cleaning"
Industrial surface coating: metal furniture"
Stationary gas turbines*"
"Minor source category, but included on
list since an NSPS is being developed for that
source category.
"•Not prioritized, since an NSPS for this
major source category has already been pro-
posed.
C44 PR 49225, Aug. 21, 1979]
108
-------
APPENDIX B
EPA METHODS 1, 2, 3, AND 7 AND
PERFORMANCE SPECIFICATION 2
109
-------
Chapter I—Environmental Protection Agency
App. A
METHOD 1.—SAMPLE AND VELOCITY TRAVERSES
FOR STATIONARY SOURCES
1. Principle and Applicability
1.1 Principle. To aid in the representa-
tive measurement of pollutant emissions
and/or total volumetric flow rate from a
stationary source, a measurement site where
the effluent stream is flowing in a known di-
rection is selected, and the cross-section of
the stack is divided into a number of equal
areas. A traverse point is then located
within each of these equal areas.
1.2 Applicability. This method is applica-
ble to flowing gas streams in ducts, stacks,
and flues. The method cannot be used
when: (1) flow is cyclonic or swirling (see
Section 2.4), (2) a stack is smaller than
about 0.30 meter (12 in.) in diameter, or
0.071 m2(113 in.2) cross-sectional area, or (3)
the measurement site is less than two stack
or duct diameters downstream or less than a
half diameter upstream from a flow disturb-
ance.
The requirements of this method must be
considered before construction of a new fa-
cility from which emissions will be meas-
ured; failure to do so may require subse-
quent alterations to the stack or deviation
from the standard procedure. Cases involv-
ing variants are subject to approval by the
Administrator, U.S. Environmental Protec-
tion Agency.
2. Procedure
2.1 Selection of Measurement Site. Sam-
pling or velocity measurement is performed
at a site located at least eight stack or duct
diameters downstream and two diameters
upstream from any flow disturbance such as
a bend, expansion, or contraction in the
stack, or from a visible flame. If necessary,
an alternative location may be selected, at a
position at least two stack or duct diameters
downstream and a half diameter upstream
from any flow disturbance. For a rectangu-
lar cross section, an equivalent diameter
(A), shall be calculated from the following
equation, to determine the upstream and
downstream distances:
2LW
''(L+W)
where i=length and W=width.
2.2 Determining the Number of Traverse
Points.
110
-------
App. A
Title 40—Protection of Environment
SINIOd BSU3AVU1
111
-------
Chapter I—Environmental Protection Agency
App. A
2.2.1 Particulate Traverses. When the
eight- and two-diameter criterion can be
met, the minimum number of traverse
points shall be: (1) twelve, for circular or
rectangular stacks with diameters (or equiv-
alent diameters) greater than 0.61 meter (24
in.); (2) eight, for circular stacks with diam-
eters between 0.30 and 0.61 meter (12-24
in.); (3) nine, for rectangular stacks with
equivalent diameters between 0.30 and 0.61
meter (12-24 in.).
When the eight- and two-diameter crite-
rion cannot be met, the minimum number
of traverse points is determined from Figure
1-1. Before referring to the figure, however,
determine the distances from the chosen
measurement site to the nearest upstream
and downstream disturbances, and divide
each distance by the stack diameter or
equivalent diameter, to determine the dis-
tance in terms of the number of duct diame-
ters. Then, determine from Figure 1-1 the
minimum number of traverse points that
corresponds: (1) to the number of duct di—
ameters upstream; and (2) to the number of
diameters downstream. Select the higher of
the two minimum numbers of traverse
points, or a greater value, so that for circu-
lar stacks the number is a multiple of 4, and
for rectangular stacks, the number is one of
those shown in Table 1-1.
TABLE 1-1. CROSS-SECTION LAYOUT FOR
RECTANGULAR STACKS
Number of traverse points
9
12
16
20
25
30
36
42
49
Matrix layout
3x3
4x3
4x4
5x4
5x5
6x5
6x6
7x6
7x7
112
-------
App. A
Title 40—Protection of Environment
3S«3Avai do aaawnN
ro
a
c
o
c
C
'5
a
QJ
o
02
E
3
C
E
3
E
c
O)
113
-------
Chapter I—Environmental Protection Agency
APP. A
2.2.2 Velocity (Non-Paniculate) Tra-
verses. When velocity or volumetric flow
rate is to be determined (but not paniculate
matter), the same procedure as that for par-
ticulate traverses (Section 2.2.1) is followed,
except that Figure 1-2 may be used instead
of Figure 1-1.
2.3 Cross-sectional Layout and Location
of Traverse Points.
2.3.1 Circular Stacks. Locate the traverse
points on two perpendicular diameters ac-
cording to Table 1-2 and the example shown
in Figure 1-3. Any equation (for examples,
see Citations 2 and 3 in the Bibliography)
that gives the same values as those in Table
1-2 may be used in lieu of Table 1-2.
For paniculate traverses, one of the diam-
eters must be in a plane containing the
greatest expected concentration variation,
e.g., after bends, one diameter shall be in
the plane of the bend. This requirement be-
comes less critical as the distance from the
disturbance increases; therefore, other di-
ameter locations may be used, subject to ap-
proval of the Administrator.
In addition for stacks having diameters
greater than 0.61 m (24 in.) no traverse
points shall be located within 2.5 centi-
meters (1.00 in.) of the stack walls; and for
stack diameters equal to or less than 0.61 m
(24 in.), no traverse points shall be located
within 1.3 cm (0.50 in.) of the stack walls.
To meet these criteria, observe the proce-
dures given below.
2.3.1.1 Stacks With Diameters Greater
Than 0.61 m (24 in.). When any of the tra-
verse points as located in Section 2.3.1 fall
within 2.5 cm (1.00 in.) of the stack walls, re-
locate them away from the stack walls to:
(1) a distance of 2.5 cm (1.00 in.); or (2) a
distance equal to the nozzle inside diameter,
whichever is larger. These relocated tra-
verse points (on each end of a diameter)
shall be the "adjusted" traverse points.
Whenever two successive traverse points
are combined to form a single adjusted tra-
verse point, treat the adjusted point as two
separate traverse points, both in the sam-
pling (or velocity measurement) procedure,
and in recording the data.
TRAVERSE DISTANCE.
POINT % of diameter
1 4.4
2 14.7
3 29.5
4 70.5
5 85.3
6 95.6
Figure 1-3. Example showing circular stack cross section divided into
12 equal areas, with location of traverse points indicated.
TABLE 1-2. LOCATION OF TRAVERSE POINTS IN CIRCULAR STACKS
[Percent of stack diameter from inside wall to traverse point]
Traverse point number on a diameter
1«.
2
3... ..
4
6 „.„....„ „
7 „
2
14.6
85.4
Number of traverse points on a diameter—
4
6.7
25.0
75.0
93.3
6
4.4
14.6
29.6
70.4
85.4
95.6
8
3.2
10.5
19.4
32.3
67.7
80.6
89.5
10
2.6
8.2
14.6
22.6
34.2
65.8
77.4
12
2.1
6.7
11.8
17.7
25.0
35.6
64.4
14
1.8
' 5.7
9.9
14.6
20.1
26.9
36.6
16
1.6
4.9
8.5
12.5
16.9
22,0
28.3
18
1.4
4.4
7.5
10.9
14.6
18.8
23.6
20
1.3
3.9
6.7
9.7
12.9
16.5
2O.4
22
1.1
3.5
6.0
8.7
11.6
14.6
18.0
24
1.1
3.2
5.5
7.9
10.5
13.2
16.1
114
-------
APP.A
Title 40—Protection of Environment
TABLE 1-2. LOCATION OF TRAVERSE POINTS IN CIRCULAR STACKS—Continued
[Percent of stack diameter from inside wall to traverse point]
Traverse point number on a diameter
8
g
10
1 1
12
13
14 . .
15
16
17
18
19
20
21
22
23
24
Number of traverse points on a diameter—
2
4
6
8
96.8
'
I
j
10
85.4
91.8
97.4
12"
75.0
82.3
88.2
93.3
97.9
14
63^4
73.1
79.9
85.4
90.1
94.3
98.2
16
37.5
62.5
71.7
78.0
83.1
87.5
91.5
95.1
98.4
18
29.6
38.2
61.3
70.4
76.4
81.2
85.4
89.1
92.5
95.6
98.6
20
25.0
30.6
38.8
61.2
69.4
75.0
79.6
33.5
87.1
90.3
93.3
96 j
98.7
22
21.8
26.2
31.5
39.3
60.7
68.5
73.8
78.2
82.0
85.4
88.4
91.3
94.0
96.5
98.9
24
19.4
23.0
27.2
32.3
39.8
60.2
67.7
72.8
77.0
80.6
83.9
86.8
89.5
92.1
94.5
96.3
98.9
2.3.1.2 Stacks With Diameters Equal to
.or Less Than 0.61 m (24 in.). Follow the pro-
cedure in Section 2.3.1.1, noting only that
any "adjusted" points should be relocated—
away from the stack walls to: (1) a distance
of 1.3 cm (0.50 in.); or (2) a distance equal to
the nozzle inside diameter, whichever is
larger.
2.3.2 Rectangular Stacks. Determine the
number of traverse points as explained in
Sections 2.1 and 2.2 of this method. Prom
Table 1-1, determine the grid configuration.
Divide the stack cross-section into as many
equal rectangular elemental areas as tra-
verse points, and then locate a traverse
point at the centroid of each equal area ac-
cording to the example in Figure 1-4.
If the tester desires to use more than the
minimum number of traverse points,
expand the "minimum number of traverse
points" matrix (see Table 1-1) by adding the
extra traverse points along one or the other
or both legs of the matrix; the final matrix
need not be balanced. For example, if a 4x3
"minimum number of points; matrix were
expanded to 36 points, the final matrix
could be 9x4 or 12x3, and would not neces-
sarily have to be 6x6. After constructing the
final matrix, divide the stack cross-section
into as many equal rectangular, elemental
areas as traverse points, and locate a tra-
verse point at the centroid of each equal
area.
The situation of traverse points being too
close to the stack walls is not expected to
arise with rectangular stacks. If this prob-
lem should ever arise, the Administrator
must be contacted for resolution of the
matter.
2.4 Verification of Absence of Cyclonic
Flow. In most stationary sources, the direc-
tion of stack gas flow is essentially parallel
to the stack walls. However, cyclonic flow
may exist (1) after such devices as cyclones
and inertial demisters following venturi
scrubbers, or (2) in stacks having tangential
inlets or other duct configurations which
tend to induce swirling; in these instances,
the presence or absence of cyclonic flow at
the sampling location must be determined.
The following techniques are acceptable for
this determination.
I
I
I
Figure 1-4. Example showing rectangular stack cross
section divided into 12 equal areas, with a traverse
point at centroid of each area.
Level and zero the manometer. Connect a
Type S pitot tube to the manometer. Posi-
tion the Type S pitot tube at each traverse
point, in succession, so that the planes of
the face openings of the pitot tube are per-
pendicular to the stack cross-sectional
plane; when the Type S pitot tube is in this
position, it is at "0° reference." Note the dif-
ferential pressure (Ap) reading at each tra-
verse point. If a null (zero) pitot reading is
obtained at 0° reference at a given traverse
115
-------
Chapter I—Environmental Protection Agency
App. A
point, an acceptable flow condition exists at
that point. If the pitot reading is not zero at
0' reference, rotate the pitot tube (up to
=90* yaw angle), until a null reading is ob-
tained. Carefully determine and record the
value of the rotation angle (a) to the near-
est degree. After the null technique has
been applied at each traverse point, calcu-
late the average of the absolute values of a;
assign a values of 0* to those points for
which no rotation was required, and include
these in the overall average. If the average
value of o is greater than 10°, the overall
flow condition in the stack is unacceptable
and alternative methodology, subject to the
approval of the Administrator, must be used
to perform accurate sample and velocity tra-
verses.
3. Bibliography
1. Determining Dust Concentration in a
Gas Stream, ASME. Performance Test Code
No. 27. New York, 1957.
2. Devorkin, Howard, et al. Air Pollution,
Source Testing Manual. Air Pollution Con"
trol District. Los Angeles, CA. November
1963.
3. Methods for Determination of Velocity,
Volume, Dust and Mist Content of Gases.
Western Precipitation Division of Joy Man-
ufacturing Co. Los Angeles, CA. Bulletin
WP-50. 1968.
4. Standard Method for Sampling Stacks
for Particulate Matter. In: 1971 Book of
ASTM Standards, Part 23. ASTM Designa-
tion D-2928-71. Philadelphia, Pa. 1971.
5. Hanson, H. A., et al. Particulate Sam-
pling Strategies for Large Power Plants In-
cluding Nonuniform Plow. USEPA, ORD,
ESRL, Research Triangle Park, N.C. EPA-
600/2-76-170, June 1976..
6. Entropy Environmentalists, Inc. Deter-
mination of the Optimum Number of Sam-
pling Points: An Analysis of Method 1 Crite-
ria. Environmental Protection Agency, Re-
search Triangle Park, N.C. EPA Contract
No. 68-01-3172, Task 7.
METHOD 2—DETERMINATION OP STACK GAS
VELOCITY AND VOLUMETRIC PLOW RATE
(TYPE S PITOT TUBE)
1. Principle and Applicability
1.1 Principle. The average gas velocity in
a stack is determined from the gas density
and from measurement of the average veloc-
ity head with a Type S (Stausscheibe or re-
verse type) pitot tube.
1.2 Applicability. This method is applica-
ble for measurement of the average velocity
of a gas stream and for quantifying gas
flow.
This procedure is not applicable at mea-
surement sites which fail to meet the crite-
ria of Method 1, Section 2.1. Also, the
method cannot be used for direct measure-
ment in cyclonic or swirling gas streams;
Section 2.4 of Method 1 shows how to deter-
mine cyclonic or swirling flow conditions.
When unacceptable conditions exist, alter-
native procedures, subject to the approval
of the Administrator, U.S. Environmental
Protection Agency, must be employed to
make accurate flow rate determinations; ex-
amples of such alternative procedures are:
(1) to install straightening vanes; (2) to cal-
culate the total volumetric flow rate stoi-
chiometrically, or (3) to move to another
measurement site at which the flow is ac-
ceptable.
2. Apparatus
Specifications for the apparatus are given
below. Any other apparatus that has been
demonstrated (subject to approval of the
Administrator) to be capable of meeting the
specifications will be considered acceptable.
116
-------
App. A
Title 40—Protection of Environment
1.90-2.54 cm*
(0.75 -1.0 in.)
7.62 cm (3 in.)
TEMPERATURE SENSOR
•SUGGESTED (INTERFERENCE FREE)
PITOT TUBE THERMOCOUPLE SPACING
Figure 2-1. Type S pilot tube manometer assembly.
2.1 Type S Pitot Tube. The Type S pitot
tube (Figure 2-1) shall be made of metal
tubing (e.g. stainless steel). It is recommend-
ed that the external tubing diameter (di-
mension D, Figure 2-2b) be between 0.48
and 0.95 centimeters (%6 and % inch). There
shall be an equal distance from the base of
each leg of the pitot tube to its face-opening
plane (dimensions PA and Pa Figure 2-2b); it
is recommended that this distance be be-
tween 1.05 and 1.50 times the external
tubing diameter. The face openings of the
pitot tube shall, preferably, be aligned as
shown in Figure 2-2; however, slight misa-
lignments of the openings are permissible
(see Figure 2-3).
The Type S pitot tube shall have a known
coefficient, determined as outlined in Sec-
tion 4. an identification number shall be as-
signed to the pitot tube; this number shall
be permanently marked or engraved on the
body of the tube.
117
-------
Chapter I—Environmental Protection Agency
APR.A
TRANSVERSE
TUBE AXIS
\
FACE
OPENING
PLANES
(a)
A-SIDE PLANE
LONGITUDINAL ;
TUBE AXIS
? °t
i *
A
B
PA
PB
NOTE:
1.05 Ot< P<1.50Dt
B-SIDE PLANE
(b)
A ORB
(c)
Figure 2-2. Properly constructed Type S pilot tube, shown in: (a) end view; face opening planes perpendicular
to transverse axis; (b) top view; face opening planes parallel to longitudinal axis; (c) side view; both legs of
equal length and centerlines coincident, when viewed from both sides. Baseline coefficient values of 0.84 may
be assigned to pilot tubes constructed this way.
118
-------
App. A
Title 40—Protection of Environment
TRANSVERSE
TUBE AXIS
(a)
LONGITUDINAL
TUBE AXIS
(e)
02 (+ or •)
(-1- or -)
119
-------
Chapter I—Environmental Protection Agency
App. A
(f)
(9)
Figure 2-3. Types of face-opening misalignment that can result from field use or improper construction of
Type S pilot tubes. These will not affect the baseline value of Cp(s) so long as al and a.2 10°, /31 and /32
5'. z 0.32 cm (1/8 in.) and w 0.08 cm (1/32 in.) (citation 11 in Section 6).
A standard pitot tube may be used instead—
of a Type S. provided that it meets the
specifications of Sections 2.7 and 4.2; note,
however, that the static and impact pres-
sure holes of standard pitot tubes are sus-
ceptible to plugging in particulate-laden gas
streams. Therefore, whenever a standard
pitot tube is used to perform a traverse, ade-
quate proof must be furnished that the
openings of the pitot tube have not plugged
up during the traverse period; this can be
done by taking a velocity head (Ap) reading
at the final traverse point, cleaning out the
Impact and static holes of the standard
pitot tube by "back-purging" with pressur-
ized air, and then taking another Ap read-
ing. If the Ap readings made before and
after the air purge are the same (±5 per-
cent), the traverse is acceptable. Otherwise,
reject the run. Note that if Ap at the final
traverse point is unsuitably low, another
point may be selected. If "back-purging" at
regular intervals is part of the procedure,
then comparative Ap readings shall be
taken, as above, for the last two back purges
at which suitably high Ap readings are ob-
served.
2.2 Differential Pressure Gauge. An in-
clined manometer or equivalent device is
used. Most sampling trains are equipped
with a 10-in. (water column) inclined-verti-
cal manometer, having 0.01-in. H,O divisions
on the 0-to 1-in. inclined scale, and 0.1-in.
HjO divisions, on the 1- to 10-in. vertical
scale. This type of manometer (or other
gauge of equivalent sensitivity) is satisfac-
tory for the measurement of Ap values as
low as 1.3 mm (0.05 in.) H3O. However, a dif-
ferential pressure gauge of greater sensitiv-
ity shall be used (subject to the approval of
the Administrator), if any of the following
is found to be true: (1) the arithmetic aver-
age of all Ap readings at the traverse points
in the stack is less than 1.3 mm (0.05 in.)
H,O; (2) for traverses of 12 or more points,
more than 10 percent of the individual Ap
readings are below 1.3 mm (0.05 in.) H,O; (3)
for traverses of fewer than 12 points, more
than one Ap reading is below 1.3 mm (0.05
in.) H,O. Citation 18 in Section 6 describes
commercially available instrumentation for
the measurement of low-range gas veloci-
ties.
As an alternative to criteria (1) through
(3) above, the following calculation may be
performed to determine the necessity of
using a more sensitive differential pressure
gauge:
_
VA?.*
where:
API=Individual velocity head reading at a
traverse point, mm H2O (in. HjO).
n=Total number of traverse points.
120
-------
App. A
Title 40—Protection of Environment
#=0.13 mm H2O when metric units are used
and 0.005 in H,O when English units are
used.
If T is greater than 1.05, the velocity head
data are unacceptable and a more sensitive
differential pressure gauge must be used.
NOTE: If differential pressure gauges other
than inclined manometers are used (e.g.,
magnehelic gauges), their calibration must
be checked after each test series. To check
the calibration of a differential pressure
gauge, compare Ap readings of the gauge
with those of a gauge-oil manometer at a
minimum of three points, approximately
representing the range of Ap values in the
stack. If, at each point, the values of Ap as
read by the differential pressure gauge and
gauge-oil manometer agree to within 5 per-
cent, the differential pressure gauge shall
be considered to be in proper calibration.
Otherwise, the test, series shall either be
voided, or procedures to adjust the meas-
ured Ap values and final results shall be
used subject to the approval of the Adminis-
trator.
2.3 Temperature Gauge. A thermocou-
ple, liquid-filled bulb thermometer, bimetal-
lic thermometer, mercury-in-glass thermom-
eter, or other gauge, capable of measuring
temperature to within 1.5 percent of the"
minimum absolute stack temperature shall
be used. The temperature gauge shall be at-
tached to the pitot tube such that the
sensor tip does not touch any metal; the
gauge shall be in an interference-free ar-
rangement with respect to the pitot tube
face openings (see Figure 2-1 and also
Figure 2-7 in Section 4). Alternate positions
may be used if the pitot tube-temperature
gauge system is calibrated according to the
procedure of Section 4. Provided that a dif-
ference of not more than 1 percent in the
average velocity measurement is introduced,
the temperature gauge need not be attached
to the pitot tube; this alternative is subject
to the approval of the Administrator.
2.4 Pressure Probe and Gauge. A piezo-
meter tube and mercury- or water-filled U-
tube manometer capable of measuring stack
pressure to within 2.5 mm (0.1 in.) Hg is
used. The static tap of a standard type pitot
tube or one leg of a Type S pitot tube with
the face opening planes positioned parallel
to the gas flow may also be used as the pres-
sure probe.
2.5 Barometer. A mercury, aneroid, or
other barometer capable of measuring at-
mospheric pressure to within 2.5 mm Hg
(0.1 in. Hg) may be used. In many cases, the
barometric reading may be obtained from a
nearby national weather service station, in
which case the station value (which is the
absolute barometric pressure) shall be re-
quested and an adjustment for elevation dif-
ferences between the weather station and
the sampling point shall be applied at a rate
of minus 2.5 mm (0.1 in.) Hg per 30-meter
(100 foot) elevation increase or vice-versa
for elevation decrease.
2.6 Gas Density Determination Equip-
ment. Method 3 equipment, if needed (see
Section 3.6), to determine the stack gas dry
molecular weight, and Reference Method 4
or Method 5 equipment for moisture con-
tent determination; other methods may be
used subject to approval of the Administra-
tor.
2.7 Calibration Pilot Tube. When calibra-
tion of the Type S pitot tube is necessary
(see Section 4), a standard pitot tube is used
as a reference. The standard pitot tube
shall, preferably, have a known coefficient,
obtained either (1) directly from the Nation-
al Bureau of Standards, Route 270, Quince
Orchard Road, Gaithersburg, Maryland, or
(2) by calibration against another standard
pitot tube with an NBS-traceable coeffi-
cient. Alternatively, a standard pitot tube
designed according to the criteria given in
2.7.1 through 2.7.5 below and illustrated in
Figure 2-4 (see also Citations 7, 8, and 17 in
Section 6) may be used. Pitot tubes designed
according to these specifications will have
baseline coefficients of about 0.99±0.01.
2.7.1 Hemispherical (shown in Figure 2-
4), ellipsoidal, or conical tip.
2.7.2 A minimum of six , diameters
straight run (based upon D, the external di-
ameter of the tube) between the tip and the
static pressure holes.
2.7.3 A minimum of eight diameters
straight run between the static pressure
holes and the centerline of the external
tube, following the 90 degree bend.
2.7.4 Static pressure holes of equal size
(approximately 0.1 D), equally spaced in a
piezometer ring configuration.
2.7.5 Ninety degree bend, with curved or
mitered junction.
2.8 Differential Pressure Gauge for Type
S Pitot Tube Calibration. An inclined mano-
meter or equivalent is used. If the single-ve-
locity calibration technique is employed (see
Section 4.1.2.3), the calibration differential
pressure gauge shall be readable to the
nearest 0.13 mm H,O (0.005 in. H,O). For
multivelocity calibrations, the gauge shall
be readable to the nearest 0.13 mm H,O
(0.005 in H,O) for Ap values between 1.3 and
25 mm H,O (0.05 and 1.0 in. H,O), and to
the nearest 1.3 mm H,O (0.05 in. H,O) for
Ap values above 25 mm H,O (1.0 in. H,O). A
special, more sensitive gauge will be re-
quired to read Ap values below 1.3 mm H,O
C0.05 in. H,O] (see Citation 18 in Section 6).
121
-------
Chapter I—Environmental Protection Agency
I (*U.IUJ) Q8 l
App. A
(•uiui)
v>
o
'•M
CO
o
a.
V)
C
.5?
Q)
TJ
cu
J2
D
a.
"O
CO
TJ
C
CO
CM
cu
k.
3
122
-------
App. A
3. Procedure
3.1 Set up the apparatus as shown in
Figure 2-1. Capillary tubing or surge tanks
installed between the manometer and pitot
tube may be used to dampen Ap fluctu-
ations. It is recommended, but not required,
that a pretest leak-cheek be conducted, as
follows: (1) blow through the pitot impact
opening until at least 7.6 cm (3 in.) H,O ve-
locity pressure registers on the manometer;
then, close off the impact opening. The
;pressure shall remain stable for at least 15
seconds; (2) do the same for the static pres-
sure side, except using suction to obtain the
minimum of 7.6 cm (3 in.) H,O. Other leak-
check procedures, subject to the approval of
the Administrator may be used.
3.2 Level and zero the manometer. Be-
cause the manometer level and zero may
Title 40—Protection of Environment
drift due to vibrations and temperature
changes, make periodic checks during the
traverse. Record all necessary data as shown
in the example data sheet (Figure 2-5).
3.3 Measure the velocity head and tem-
perature at the traverse points specified by
Method 1. Ensure that the proper differen-
tial pressure gauge is being used for the
range of Ap values encountered (see Section
2.2). If it is necessary to change to a more
sensitive gauge, do so, and remeasure the Ap
and temperature readings at each traverse
point. Conduct a post-test leak-check (man-
datory), as described in Section 3.1 above, to
validate the traverse run.
3.4 Measure the static pressure in the
stack. One reading is usually adequate.
3.5 Determine the atmospheric pressure.
123
-------
Chapter I—Environmental Protection Agency
APR. A
PLANT.
DATE
.RUN NO.
STACK DIAMETER OR DIMENSIONS, m(in.)
BAROMETRIC PRESSURE, mm Hg (in. Hg)
CROSS SECTIONAL AREA, m2{ft2)
OPERATORS .
PITOTTUBEI.D. NO.
AVG. COEFFICIENT, Cp = .
LAST DATE CALIBRATED.
SCHEMATIC OF STACK
CROSS SECTION
Traverse
Pt. No.
Vel.Hd.,Ap
mm (in.) HjO
Stack Temperature
ts, °C (
mm Hg (in.Hg)
Average
Figure 2-5. Velocity traverse data.
124
-------
App. A
3.6 Determine the stack gas dry molecular
weight. For combustion processes or proc-
esses that emit essentially CO,, O,, CO, and
N,. use Method 3. For processes emitting es-
sentially air, an analysis need not be con-
ducted; use a dry molecular weight of 29.0.
For other processes, other methods, subject
to the approval of the Administrator, must
be used.
3.7.Obtain the moisture content from
Reference Method 4 (or equivalent) or from
Method 5.
3.8 Determine the cross-sectional area of
the stack or duct at the sampling location.
Whenever possible, physically measure the
stack dimensions rather than using blue-
prints.
4. Calibration
4.1 Type S Pitot Tube. Before its initial
use, carefully examine the Type S pitot
tube in top, side, and end views to verify
that the face openings of the tube are
aligned within the specifications illustrated"'
in Figure 2-2 or 2-3. The pitot tube shall
not be used if it fails to meet these align-
ment specifications.
After verifying the face opening align-
ment, measure and record the following di-
mensions of the pitot tube: (a) the external
tubing diameter (dimension A, Figure 2-2b);
and (b) the base-to-opening plane distances
(dimensions P* and Pa, Figure 2-2b). If D, is
between 0.48 and 0.95 cm (.Vie and % in.) and
if PM and Pa are equal and between 1.05 and
1.50 D,. there are two possible options: (1)
the pitot tube may be calibrated according
to the procedure outlined in Sections 4.1.2
through 4.1.5 below, or (2) a baseline (isolat-
ed tube) coefficient value of 0.84 may be as-
signed to the pitot tube. Note, however, that
if the pitot tube is part of an assembly, cali-
bration may still be required, despite knowl-
edge of the baseline coefficient value (see
Section 4.1.1).
Title 40—Protection of Environment
If D,, PA, and PB are outside the specified
limits, the pitot tube must be calibrated as
outlined in 4.1.2 through 4.1.5 below.
4.1.1 Type S Pitot Tube Assemblies.
During sample and velocity traverses, the
isolated Type S pitot tube is not always
used: in many instances, the pitot tube is
used in combination with other source-sam-
pling components (thermocouple, sampling
probe, nozzle) as part of an "assembly." The
presence of other sampling components can
sometimes affect the baseline value of the
Type S pitot tube coefficient (Citation 9 in
Section 6); therefore an assigned (or other-
wise known) baseline coefficient value maj-
or may not be valid for a given assembly.
The baseline and assembly coefficient
values will be identical only when the rela-
tive placement of the components in the as-
sembly is such that aerodynamic interfer-
ence effects are eliminated. Figures 2-6
through 2-8 illustrate interference-free
component arrangements for Type S pitot
tubes having external tubing diameters be-
tween 0.48 and 0.95 cm Cfte and % in.). Type
S pitot tube assemblies that fail to meet any
or all of the specifications of Figures 2-6
through 2-8 shall be calibrated according to
the procedure outlined in Sections 4.1.2
through 4.1.5 below, and prior to calibra-
tion, the values of the intercomponent spac-
ings (pitot-nozzle, pilot-thermocouple, pitot-
probe sheath) shall be measured and record-
ed.
NOTE: Do not use any Type S pitot tube
assembly which is constructed such that the
impact pressure opening plane of the pitot
tube is below the entry plane of the nozzle
(see Figure 2-6b). •
4.1.2 Calibration Setup. If the Type S
pitot tube is to be calibrated, one leg of the
tube shall be permanently marked A, and
the other, B. Calibration shall be done in a
flow system having the following essential
design features:
125
-------
Chapter I—Environmental Protection Agency
App. A
3E
TYPE 5 PITOT TUBE
I
x > 1.90 em (3/4 in.) FOR Dn - 1.3 em (1/2 in.)
SAMPLING NOZZLE
A. BOTTOM VIEW; SHOWING MINIMUM PITOT-NOZZLE SEPARATION.
SAMPLING
PROBE
I
SAMPLING
NOZZLE
TYPE S
PITOT TUBE
NOZZLEjENTRY
PLANE
B. SIDE VIEW: TO PREVENT PITOT TUBE
FROM INTERFERING WITH GAS FLOW
STREAMLINES APPROACHING THE
NOZZLE. THE IMPACT PRESSURE
OPENING PLANE OF THE PITOT TUBE
SHALL BE EVEN WITH OR ABOVE THE
NOZZLE ENTRY PLANE.
126
-------
App. A
Title 40—Protection of Environment
1
0)
c
-------
Chapter I—Environmental Protection Agency
App. A
4.1.2.1 The flowing gas stream must be
confined to a duct of definite cross-sectional
area, either circular or rectangular. For cir-
cular cross-sections, the minimum duct di-
ameter shall be 30.5 cm (12 in.); for rectan-
gular cross-sections, the width (shorter side)
shall be at least 25.4 cm (10 in.).
4.1.2.2 The cross-sectional area of the
calibration duct must be constant over a dis-
tance of 10 or more duct diameters. For a
rectangular cross-section, use an equivalent
diameter, calculated from the following
equation, to determine the number of duct
diameters:
a/.ir
'2-1
where:
D,—Equivalent diameter
Z,« Length
W'=Width
To ensure the presence of stable, fully de-
veloped flow patterns at the calibration site,
or "test section," the site must be located at
least eight diameters downstream and two--
diameters upstream from the nearest distur-
bances.
NOTE The eight- and two-diameter crite-
ria are not absolute: other test section loca-
tions may be used (subject to approval of
the Administrator), provided that the flow
at the test site is stable and demonstrably
parallel to the duct axis.
4.1.2.3 The flow system shall have the ca-
pacity to generate a test-section velocity
around 915 m/min (3,000 ft/min). This ve-
locity must be constant with time to guaran-
tee steady flow during calibration. Note that
Type S pilot tube coefficients obtained by
single-velocity calibration at 915 m/min
(3.000 ft/min) will generally be valid to
within ±3 percent for the measurement of
velocities above 305 m/min (1,000 ft/min)
and to within ±5 to 6 percent for the mea-
surement of velocities between 180 and 305
m/min (600 and 1,000 ft/min). If a more
precise correlation between Cf and velocity
is desired, the flow system shall have the ca-
pacity to generates at least four distinct,
time-invariant test-section velocities cover-
ing the velocity range from 180 to 1,525 m/
min (600 to 5,000 ft/min), and calibration
data shall be taken at regular velocity inter-
vals over this range (see Citations 9 and 14
in Section 6 for details).
4.1.2.4 Two entry ports, one each for the
standard and Type S pitot tubes, shall be
cut in the test section: the standard pitot
entry port shall be located slightly down-
stream of the Type S port, so that the
standard and Type S impact openings will
lie in the same cross-sectional plane during
calibration. To facilitate alignment of the
pitot tubes during calibration, it is advisable
that the test section be constructed of plex-
iglas or some other transparent material.
4.1.3 Calibration Procedure. Note that
this procedure is a general one and must not
be used without first referring to the special
considerations presented in Section 4.1.5.
Note also that this procedure applies only
to single-velocity calibration. To obtain cali-
bration data for the A and B sides of the
Type S pitot tube, proceed as follows:
4.1.3.1 Make sure that the manometer is
properly filled and that the oil is free from
contamination and is of the proper density.
Inspect and leak-check all pitot lines; repair
or replace if necessary.
4.1.3.2 Level and zero the manometer.
Turn on the fan and allow the flow to stabi-
lize. Seal the Type S entry port.
4.1.3.3 Ensure that the manometer is
level and zeroed. Position the standard pitot
tube at the calibration point (determined as
outlined in Section 4.1.5.1), and align the
tube so that its tip is pointed directly into
the flow. Particular car should be taken in
aligning the tube to avoid yaw and pitch
angles. Make sure that the entry port sur-
rounding the tube is properly sealed.
4.1.3.4 Read A',,,1 and record its value in a
data table similar to the one shown in
Figure 2-9. Remove the standard pitot tube
from the duct and disconnect it from the
manometer. Seal the standard entry port.
4.1.3.5 Connect the Type S pitot tube to
the manometer. Open the Type S entry
port. Check the manometer level and zero.
Insert and align the Type S pitot tube so
that its A side impact opening is at the same
point as was the standard pitot tube and is
pointed directly into the flow. Make sure
that the entry port surrounding the tube is
properly sealed.
4.1.3.6 Read Ap« and enter its value in the
data table. Remove the Type S pitot tube
from the duct and disconnect it from the
manometer.
4.1.3.7 Repeat steps 4.1.3.3 through
4.1.3.6 above until three pairs of Ap readings
have been obtained.
4.1.3.8 Repeat steps 4.1.3.3 through
4.1.3.7 above for the B side of the Type S
pitot tube.
4.1.3.9 Perform calculations, as described
in Section 4.1.4 below.
4.1.4 Calculations.
4.1.4.1 For each of the six pairs of Ap
readings (i.e., three from side A and three
from side B) obtained in Section 4.1.3 above,
calculate the value of the Type S pitot tube
coeffficient as follows:
128
-------
App. A
PITOT TUBE IDENTIFICATION NUMBER:
CALIBRATED BY:
Title 40—Protection of Environment
DATE:
RUN NO.
1
2
3
"A" SIDE CALIBRATION
' Apjtd
cm H20
(in. H20)
Ap(s)
cm H20
(in. H20)
Cp (SIDE A)
Cp(s)
DEVIATION
Cp(s)-Cp(A)
RUN NO.
1
2
3
"B" SIDE CALIBRATION
Apjtd
cm H20
(in. H20)
Ap(s)
cm H20
(in. H20)
Cp (SIDE B)
cp(s)
DEVIATION
Cp(s)-Cp(BI
I |Cp(s)-Cp(AORB)|
AVERAGE DEVIATION = u (A OR B)
• MUST BE < 0.01
Cp (SIDE A)-Cp (SIDE B) |-*-MUST BE <0.01
Figure 2-9. Pitot tube calibration data.
129
-------
Chapter I—Environmental Protection Agency
App. A
Equation 2-2
where:
C,=Type S pitot tube coefficient
Cii,,a)=Standard pitot tube coefficient; use
0.99 if the coefficient is unknown and
the tube is designed according to the cri-
teria of Sections 2.7.1 to 2.7.5 of this
method.
•iPi«=Velocity head measured by the stand-
ard pitot tube, cm H,O (in. H3O)
ip,=Velocity head measured by the Type S
pitot tube, cm H,O (in H,O)
4.1.4.2 Calculate Cp (side A), the mean A-
side coefficient, and C, (side B), the mean B-
side coefficient: calculate the difference be-
tween these two average values.
4.1.4.3 Calculate the deviation of each of
the three A-side values of CPt,> from Cf (side
A), and the deviation of each B-side value of
Cpui from Cp Cp (side B). Use the following..
equation:
Deviation = Cp(.!—CV(A or B)
Equation 2-3
4.1.4.4 Calculate S, the average deviation
from the mean, for both the A and B sides
of the pitot tube. Use the following equa-
tion:
a (side A or B):
3
2l
i
Equation 2-4
4.1.4.5 Use the Type S pitot tube only if
Che values of S (side A) and S (side B) are
less than or equal to 0.01 and if the absolute
value of the difference between Cp (A) and
CB (B) is 0.01 or less.
4.1.5 Special considerations.
4.1.5.1 Selection of calibration point.
4.1.5.1.1 When an isolated Type S pitot
tube is calibrated, select a calibration point
at or near the center of the duct, and follow
the procedures outlined in Sections 4.1.3
and 4.1.4 above. The Type S pitot coeffi-
cients so obtained, i.e., Cp (side A) and C,
(side B), will be valid, so long as either: (1)
the isolated pitot tube is used; or (2) the
pitot tube is used with other components
(nozzle, thermocouple, sample probe) in an
arrangement that is free from aerodynamic
interference effects (see Figures 2-6
through 2-8).
4.1.5.1.2 For Type S pitot tube-thermo-
couple combinations (without sample
probe), select a calibration point at or near
the center of the duct, and follow the proce-
dures outlined in Sections 4.1.3 and 4.1.4
above. The coefficients so obtained will be
valid so long as the pitot tube-thermocouple
combination is used by itself or with other
components in an interference-free arrange-
ment (Figures 2-6, and 2-8).
4.1.5.1.3 For assemblies with sample
probes, the calibration point should be lo-
cated at or near the center of the duct; how-
ever, insertion of a probe sheath into a
small duct may cause significant cross-sec-
tional area blockage and yield incorrect co-
efficient values (Citation 9 in Section 6).
Therefore, to minimize the blockage effect,
the calibration point may be a few inches
off-center if necessary. The actual blockage
effect will be negligible when the theoreti-
cal blockage, as determined by a projected-
area model of the probe sheath, is 2 percent
or less of the duct cross-sectional area for
assemblies without external sheaths (Figure
2-10a), and 3 percent or less for assemblies
with external sheaths (Figure 2-10b).
4.1.5.2 For those probe assemblies in
which pitot tube-nozzle interference is a
factor (i.e., those in which the pitot-nozzle
separation distance fails to .meet the specifi-
cation illustrated in Figure 2-6a), the value
of Cp<.> depends upon the amount of free-
space between the tube and nozzle, and
therefore is a function of nozzle size. In
these instances, separate calibrations shall
be performed with each of the commonly
used nozzle sizes in place. Note that the
single-velocity calibration technique is ac-
ceptable for this purpose, even though the
larger nozzle sizes (>0.635 cm or '/< in.) are
not ordinarily used for isokinetic sampling
at velocities around 915 m/min (3,000 ft/
min), which is the calibration velocity; note
also that it is not necessary to draw an iso-
kinetic sample during calibration (see Cita-
tion 19 in Section 6).
4.1.5.3 For a probe assembly constructed
such that its pitot tube is always used in the
same orientation, only one side of the pitot
tube need be calibrated (the side which will
face the flow). The pitot tube must still
meet the alignment specifications of Figure
2-2 or 2-3, however, and must have an aver-
age deviation (8) value of 0.01 or less (see
Section 4.1.4.4).
130
-------
App. A
Title 40—Protection of Environment
03
CO
- * 55
S < «J •~"
H- UJ O
c/l X _j
UJ CO OQ
'a
>•
+^
o
•**-
V}
~z
~a
o.
E
fO
a>
ra.
••^
-------
Chapter I—Environmental Protection Agency
App. A
Figure 2-10. Projected-area models for typi-
cal pitot tube assemblies.
4.1.6 Field Use and Recalibration.
4.1.6.1 Field Use.
4.1.6.1.1 When a Type S pitot tube (iso-
lated tube or assembly) is used in the field,
the appropriate coefficient value (whether
assigned or obtained by calibration) shall be
used to perform velocity calculations. For
calibrated Type S pitot tubes, the A side co-
efficient shall be used when the A side of
the tube faces the flow, and the B side coef-
ficient shall be used when the B side faces
the flow; alternatively, the arithmetic aver-
age of the A and B side coefficient values
may be used, irrespective of which side faces
the flow.
4.1.6.1.2 When a probe assembly is used
to sample a small duct (12 to 36 in. in diame-
ter), the probe sheath sometimes blocks a
significant part of the duct cross-section,
causing a reduction in the effective value of
Cpui. Consult Citation 9 in Section 6 for de-
tails. Conventional pitot-sampling probe as-
semblies are not recommended for use in
ducts having inside diameters smaller than
12 inches (Citation 16 in Section 6).
4.1.6'.2 Recalibration.
4.1.6.2.1 Isolated Pitot Tubes. After each,
field use, the pitot tube shall be carefully"
reexamined in top, side, and end views. If
the pitot face openings are still aligned
within the specifications illustrated in
Figure 2-2 or 2-3, it can be assumed that the
baseline coefficient of the pitot tube has not
changed. If, however, the tube has been
damanged to the extent that it no longer
meets the specifications of Figure 2-2 or 2-
3, the damage shall either be repaired to re-
store proper alignment of the face openings
or the tube shall be discarded.
4.1.6.2.2 Pitot Tube Assemblies. After
each field use, check the face opening align-
ment of the pitot tube, as in Section
4.1.6.2.1; also, remeasure the intercompon-
ent spacings of the assembly. If the inter-
component spacings have not changed and
the face opening alignment is acceptable, it
can be assumed that the coefficient of the
assembly has not changed. If the face open-
Ing alignment is no longer within the speci-
fications of Figures 2-2 or 2-3, either repair
the damage or replace the pitot tube (cali-
brating the new assembly, if necessary). If
the intercomponent spacings have changed,
restore the original spacings or recalibrate
the assembly.
4.2 Standard pitot tube (if applicable). If
a standard pitot tube is used for the velocity
traverse, the tube shall be constructed ac-
cording to the 'criteria of Section 2.7 and
shall be assigned a baseline coefficient value
of 0.99. If the standard pitot tube is used as
part of an assembly, the tube shall be in an
interference-free arrangement (subject to
the approval of the Administrator).
4.3 Temperature Gauges. After each
field use, calibrate dial thermometers,
liquid-filled bulb thermometers, thermocou-
ple-potentiometer systems, and other
gauges at a temperature within 10 percent
of the average absolute stack temperature.
For temperatures up to 405° C (761° F), use
an ASTM mercury-in-glass reference ther-
mometer, or equivalent, as a reference; al-
ternatively, either a reference thermocouple
and potentiometer (calibrated by NBS) or
thermometric fixed points, e.g., ice bath and
boiling water (corrected for barometric pres-
sure) may be used. For temperatures above
405° C (761° F), use an NBS-calibrated refer-
ence thermocouple-potentiometer system or
an alternate reference, subject to the ap-
proval of the Administrator.
If, during calibration, the absolute tem-
peratures measured with the gauge being
calibrated and the reference gauge agree
within 1.5 percent, the temperature data
taken in the field shall be considered valid.
Otherwise, the pollutant emission test shall
either be considered invalid or adjustments
(if appropriate) of the test results shall be
made, subject to the approval of the Admin-
istrator.
4.4 Barometer. Calibrate the barometer
used against a mercury barometer.
5. Calculations
Carry out calculations, retaining at least
one extra decimal figure beyond that of the
acquired data. Round off figures after final
calculation.
5.1 Nomenclature.
A=Cross-sectional area of stack, mMft2).
Bun=Water vapor in the gas stream (from
Method 5 or Reference Method 4), pro-
portion by volume.
CP=Pitot tube coefficient, dimensionless.
Kf=Pitot tube constant.
•U Q- -'-
sec L (°K)(mmH2O) J
for the metric system and
_ft_ f( Ib/lb-mole) (in. _Hg)-|«.
sec L (°R)(in. H20) J
for the English system.
Ma = Molecular weight of stack gas, dry basis
(see Section 3.6) g/g-mole (Ib/lb-mole).
A£r=Molecular weight of stack gas, wet
basis, g/g-mole (Ib/lb-mole).
=Af« (1-.R,,) +18.0 Bw,
132
-------
APR. A
Title 40—Protection of Environment
Equation 2-5
P>ae= Barometric pressure at measurement
site, mm Hg (in. Hg).
P,= Stack static pressure, mm Hg (in. Hg).
P, = Absolute stack gas pressure, mm Hg (in.
Hg).
Equation 2-6
P,u= Standard absolute pressure, 760 mm
Hg (29.92 in. Hg).
Q«i=Dry volumetric stack gas flow rate cor-
rected to standard conditions, dscm/hr
(dscf/hr).
4,= Stack temperature, °C (°F).
T,= Absolute stack temperature, °K. OR).
=273 +t, for metric
Equation 2-7
=460+ 1. for English
Equation 2-3
r,«=Standard absolute temperature, 293 °K
(528° R)
w= Average stack gas velocity, m/sec (ft/
sec).
&?= Velocity head of stack gas, mm HaO (in.
H,O).
3,600=Conversion factor, sec/hr.
18.0= Molecular weight of water, g/g-mole
(Ib/lb-mole).
5.2 Average stack gas velocity.
Equation 2-9
5.3 Average stack gas dry volumetric flow
rate.
^=3,600 (l-
Equation 2-10
6. Bibliography
1. Mark, L. S. Mechanical Engineers'
Handbook. New York, McGraw-Hill Book
Co., Inc. 1951.
2. Perry, J. H. Chemical Engineers' Hand-
book. New York. McGraw-Hill Book Co.,
Inc. 1960.
3. Shigehara, R. T., W. P. Todd, and W. S.
Smith. Significance of Errors in Stack Sam-
pling Measurements. U.S. Environmental
Protection Agency, Research Triangle Park,
N.C. (Presented at the Annual Meeting of
the Air Pollution Control Association, St.
Louis. Mo., June 14-19, 1970.)
4. Standard Method for Sampling Stacks
for Particulate Matter. In: 1971 Book of
ASTM Standards, Part 23. Philadelphia, Pa.
1971. ASTM Designation D-2928-71.
5, Vennard, J. K. Elementary Fluid Me-
chanics. New York. John Wiley and Sons,
Inc. 1947.
6. Fluid Meters—Their Theory and Appli-
cation. American Society of Mechanical En-
gineers, New York, N.Y. 1959.
7. ASHRAE Handbook of Fundamentals.
1972. p. 208.
8. Annual Book of ASTM Standards, Part
26. 1974. p. 648.
9. Vollaro, R. F. Guidelines for Type S
Pitot Tube Calibration. U.S. Environmental
Protection Agency. Research Triangle Park,
N.C. (Presented at 1st Annual Meeting,
Source Evaluation Society, Dayton, Ohio,
September 18, 1975.)
10. Vollaro, R. F. A Type S Pitot Tube
Calibration Study. U.S. Environmental Pro-
tection Agency, Emission Measurement
Branch, Research Triangle Park, N.C. July
1974.
11. Vollaro, R. F. The Effects of Impact
Opening Misalignment on the Value of the
Type S Pitot Tube Coefficient. U.S. Envi-
ronmental Protection Agency, Emission
Measurement Branch, Research Triangle
Park, N.C. October 1976.
12. Vollaro, R. F. Establishment of a Bas-
line Coefficient Value for Properly Con-
structed Type S Pitot Tubes. U.S. Environ-
mental Protection Agency, Emission Mea-
surement Branch, Research Triangle Park
N.C. November 1976.
13. Vollaro, R. F. An Evaluation of Single-
Velocity Calibration Technique as a Means
of Determining Type S Pitot Tubes Coeffi-
cient. U.S. Environmental Protection
Agency, Emission Measurement Branch, Re-
search Triangle Park N.C. August 1975.
14. Vollaro, R. F. The Use of Type S Pitot
Tubes for the Measurement of Low Veloci-
ties. U.S. Environmental Protection Agency,
Emission Measurement Branch, Research
Triangle Park N.C. November 1976.
15. Smith, Marvin L. Velocity Calibration
of EPA Type Source Sampling Probe.
United Technologies Corporation, Pratt and
Whitney Aircraft Division, East Hartford,
Conn. 1975.
16. Vollaro, R. F. Recommended Proce-
dure for Sample Traverses in Ducts Smaller
than 12 Inches in Diameter. U.S. Environ-
mental Protection Agency, Emission Mea-
surement Branch. Research Triangle Park
N.C. November 1976.
17. Ower. E. and R. C. Pankhurst. The
Measurement of Air Flow, 4th Ed., London,
Pergamon Press. 1966.
18. Vollaro, R. F. A Survey of Commercial-
ly Available Instrumentation for the Mea-
133
-------
Chapter I—Environmental Protection Agency
App. A
surement of Low-Range Gas Velocities. U.S.
Environmental Protection Agency, Emission
Measurement Branch, Research Triangle
Park N.C. November 1976. (Unpublished
Paper) •
19. Gnyp, A. W.. C. C. St. Pierre, D. S.
Smith, D. Mozzon, and ,T. Steiner. An Ex-
perimental Investigation of the Effect of
Pitot Tube-Sampling Probe Configurations
on the Magnitude of the S Type Pitot Tube
Coefficient for Commercially Available
Source Sampling Probes. Prepared by the
University of Windsor for the Ministry of
the Environment, Toronto, Canada. Febru-
ary 1975.
METHOD 3—GAS ANALYSIS FOR CARBON DIOX-
IDE. OXYGEN, EXCESS AIR, AND DRY MOLEC-
ULAR WEIGHT
1. Principle and Applicability
1.1 Principle. A gas sample is extracted
from a stack, by one of the following meth-
ods: (1) single-point, grab sampling; (2r~
single-point, integrated sampling; or (3)
multi-point, integrated sampling. The gas
sample is analyzed for percent carbon diox-
ide (CO,), percent oxygen (Oa), and, if neces-
sary, percent carbon monoxide (CO). If a
dry molecular weight determination is to be
made, either an Orsat or a Fyrite ' analyzer
may be used for the analysis; for excess air
or emission rate correction factor determi-
nation, an Orsat analyzer must be used.
1.2 Applicability. This method is applica-
ble for determining Cd and O, concentra-
tions, excess air, and dry molecular weight
of a sample from a gas stream of a fossil-
fuel combustion process. The method may
also be applicable to other processes where
it has been determined that compounds
'Mention of trade names or specific prod-
ucts does not constitute endorsement by the
Environmental Protection Agency.
other than CO2, Oa, CO, and nitrogen (n.)
are not present in concentrations sufficient
to affect the results.
Other methods, as well as modifications to
the procedure described herein, are also ap-
plicable for some or all of the above deter-
minations. Examples of specific methods
and modifications include: (Da multi-point
sampling method using an Orsat analyzer to
analyze individual grab samples obtained at
each point; (2) a method using CO3 or Oj
and stoichiometric calculations to determine
dry molecular weight and excess air; (3) as-
signing a value of 30.0 for dry molecular
weight, in lieu of actual measurements, for
processes burning natural gas, coal, or oil.
These methods and modifications may be
used, but are subject to the approval of the
Administrator, U.S. Environmental Protec-
tion Agency.
2. Apparatus
As an alternative to the sampling appara-
tus and systems described herein, other
sampling systems (e.g., liquid displacement)
may be used provided such systems are ca-
pable of obtaining a representative sample
and maintaining a constant sampling rate,
and are otherwise capable of yielding ac-
ceptable results. Use of such systems is sub-
ject to the approval of the Administrator.
2.1 Grab Sampling (Figure 3-1).
2.1.1 Probe. The probe should be made of
stainless steel or borosilicate glass tubing
and should be equipped with an in-stack or
out-stack filter to remove particulate matter
(a plug of glass wool is satisfactory for this
purpose). Any other materials inert to O,,
CO,. CO, and N, and resistant to tempera-
ture at sampling conditions may be used for
the probe; examples of such material are
aluminum, copper, quartz glass and Teflon.
2.1.2 Pump. A one-way squeeze bulb, or
equivalent, is used to transport the gas
sample to the analyzer.
2.2 Integrated Sampling (Figure 3-2).
2.2.1 Probe. A probe such as that de-
scribed in Section 2.1.1 is suitable.
134
-------
APP.A
Title 40—Protection of Environment
PROBE
FLEXIBLE TUBING
\
FILTER (GLASS WOOL)
TO ANALYZER
SQUEEZE BULB
Figure 3-1. Grab-sampling train.
RATE METER
AIR-COOLED
CONDENSER
PROBE
\
FILTER
(GLASS WOOL)
VALVE
QUICK DISCONNECT
JT
RIGID CONTAINER '
BAG
Figure 3-2. Integrated gas-sampling train.
2.2.2 Condenser. An air-cooled or water-
cooled condenser, or other condenser that
will not remove O,, CO,, CO, and N*. may be
used to remove excess moisture which
would interfere with the operation of the
pump and now meter.
2.2.3 Valve. A needle valve is used to
adjust sample gas flow rate.
2.2.4 Pump. A leak-free, diaphragm-type
pump, or equivalent, is used to transport
sample gas to the flexible bag. Install a
small surge tank between the pump and
135
-------
Chapter I—Environmental Protection Agency
App. A
rate meter to eliminate the pulsation effect
of the diaphragm pump on the rotameter.
2.2.5 Rate Meter. The rotameter, or
equivalent rate meter, used should be capa-
ble of measuring flow rate to within ±2 per-
cent of the selected flow rate. A flow rate
range of 500 to 1000 cmVmin is suggested.
2.2.6 Flexible Bag. Any leak-free plastic
(e.g., Tedlar, Mylar. Teflon) or plastic-
coated aluminum (e.g., aluminized Mylar)
bag, or equivalent, having a capacity con-
sistent with the selected flow rate and time
length of the test run, may be used. A ca-
pacity in the range of 55 to 90 liters is sug-
gested.
To leak-check the bag. connect it to a
water manometer and pressurize the bag to
5 to 10 cm H,O (2 to 4 in. HiO). Allow to
stand for 10 minutes. Any displacement in
the water manometer indicates a leak. An
alternative leak-check method is to pressur-
ize the bag to 5 to 10 cm H,O (2 to 4 in. H,O)
and allow to stand overnight. A deflated bag
indicates a leak.
2.2.7 Pressure Gauge. A water-filled U-
tube manometer, or equivalent, of about 28
cm (12 in.) is used for the flexible bag leak-
check.
2.2.8 Vacuum Gauge. A mercury mano-
meter, or equivalent, of at least 760 mm Hg
(30 in. Hg) is used for the sampling train"
leak-check.
2.3 Analysis. For Orsat and Fyrite ana-
lyzer maintenance and operation proce-
dures, follow the instructions recommended
by the manufacturer, unless otherwise spec-
ified herein.
2.3.1 Dry Molecular Weight Determina-
tion. An Orsat analyzer or Fyrite type com-
bustion gas analyzer may be used.
2.3.2 Emission Rate Correction Factor or
Excess Air Determination. An Orsat analyz-
er must be used. For low CO3 (less than 4.0
percent) or high Oi (greater that 15.0 per-
cent) concentrations, the measuring burette
of the Orsat must have at least 0.1 percent
subdivisions.
3. Dry Molecular Weight Determination
Any of the three sampling and analytical
procedures described below may be used for
determining the dry molecular weight.
3.1 Single-Point, Grab Sampling and
Analytical Procedure.
3.1.1 The sampling point in the duct
shall either be at the centroid of the cross
section or at a point no closer to the walls
than 1.00 m (3.3 ft), unless otherwise speci-
fied by the Administrator.
3.1.2 Set up the equipment as shown in
Figure 3-1, making sure all connections
ahead of the analyzer are tight and leak-
free. If and Orsat analyzer is used, it is rec-
ommended that the analyzer be leaked-
checked by following the procedure in Sec-
tion 5: however, the leak-check is optional.
3.1.3 Place the probe in the stack, with
the tip of the probe positioned at the sam-
pling point; purge the sampling line. Draw a
sample into the analyzer and immediately
analyze it for percent CO* and percent O3.
Determine the percentage of the gas that is
Ni and CO by subtracting the sum of the
percent CO3 and percent O» from 100 per-
cent. Calculate the dry molecular weight as
indicated in Section 6.3.
3.1.4 Repeat the sampling, analysis, and
calculation procedures, until the dry molec-
ular weights of any three grab samples
differ from their mean by no more than 0.3
g/g-mole (0.3 Ib/lb-mole). Average these
three molecular weights, and report the re-
sults to the nearest 0.1 g/g-mole (Ib/lb-
mole).
3.2 Single-Point, Integrated Sampling
and Analytical Procedure.
3.2.1 The sampling point in the duct
shall be located as specified in Section 3.1.1.
3.2.2 Leak-check (optional) the flexible
bag as in Section 2.2.6. Set up the equip-
ment as shown in Figure 3-2. Just prior to
sampling, leak-check (optional) the train by
placing a vacuum gauge at the condenser
inlet, pulling a vacuum of at least 250 mm
Hg (10 in. Hg), plugging the outlet at the
quick disconnect, and then turning off the
pump. The vacuum should remain stable for
at least 0.5 minute. Evacuate the flexible
bag. Connect the probe and place it in the
stack, with the tip of the probe positioned
at the sampling point; purge the sampling
line. Next, connect the bag and make sure
that all connections are tight and leak free.
3.2.3 Sample at a constant rate. The sam-
pling run should be simultaneous with, and
for the same total length of time as, the pol-
lutant emission rate determination. Collec-
tion of at least 30 liters (1.00 ft3) of sample
gas is recommended; however, smaller vol-
umes may be collected, if desired.
3.2.4 Obtain one integrated flue gas
sample during each pollutant emission rate
determination. Within 8 hours after the
sample is taken, analyze it for percent COi
and percent O, using either an Orsat analyz-
er or a Fyrite-type combustion gas analyzer.
If an Orsat analyzer is used, it is recom-
mended that the Orsat leak-check described
in Section 5 be performed before this deter-
mination; however, the check is optional.
Determine the percentage of the gas that is
N, and CO by subtracting the sum of the
percent Cd and percent O> from 100 per-
cent. Calculate the dry molecular weight as
indicated in Section 6.3.
3.2.5 Repeat the analysis and calculation
procedures until the individual dry molecu-
lar weights for any three analyses differ
from their mean by no more than 0.3 g/g-
mole (0.3 Ib/lb-mole). Average these three
molecular weights, and report the results to
the nearest 0.1 g/g-mole (0.1 Ib/lb-mole).
136
-------
App. A
Title 40—Protection of Environment
3.3 Multi-Point, Integrated Sampling and
Analytical Procedure.
3.3.1 Unless otherwise specified by the
Administrator, a minimum of eight traverse
points shall be used for circular stacks
having diameters less than 0.61 m (24 in.), a
minimum of nine shall be used for rectangu-
lar stacks having equivalent diameters less
than 0.61 m (24 in.), and a minimum of
twelve traverse points shall be used for all
other cases. The traverse points shall be lo-
cated according to Method 1. The use of
fewer points is subject to approval of the
Administrator.
3.3.2 Follow the procedures outlined in
sections 3.2.2 through! 3.2.5. except for the
following: traverse all sampling points and
sample at each point for an equal length of
time. Record sampling data as shown in
Figure 3-3.
4. Emission Rate Correction Factor or
Excess Air Determination
NOTE: A Fyrite-type combustion gas ana-
lyzer is not acceptable for excess air or emis-
sion rate correction factor determination.
unless approved by the Administrator. If
both percent CO, and percent O, are meas-
ured, the analytical results of any of the
three procedures given below may also be
used for calculating the dry molecular
weight.
Each of the three procedures below shall
be used .only when specified in an applicable
subpart of the standards. The use of these
procedures for other purposes must have
specific prior approval of the Administrator.
4.1 Single-Point, Grab Sampling and
Analytical Procedure.
4.1.1 The sampling point in the duct
shall either be at the centroid of the cross-
section or at a point no closer to the walls
than 1.00 m (3.3 ft), unless otherwise speci-
fied by the Administrator.
4.1.2 Set up the equipment as shown in
Figure 3-1, making sure all connections
ahead of the analyzer are tight and leak-
free. Leak-check the Orsat analyzer accord-
ing to the procedure described in Section 5.
This leak-check is mandatory.
TIME
TRAVERSE
PT.
AVERAGE
Q
1pm
% DEV.a
%DEV=
Qavg
(MUST BE < 10%)
Figure 3-3. Sampling rate data.
4.1.3 Place the probe in the stack, with
the tip of the probe positioned at the sam-
pling point; purge the sampling line. Draw a
sample into the analyzer. For emission rate
correction factor determination, immediate-
ly analyze the sample, as outlined in Sec-
tions 4.1.4 and 4.1.5, for percent CO, or per-
cent O». If excess air is desired, proceed as
follows: (1) immediately analyze the sample,
as in Sections 4.1.4 and 4.1.5, for percent
CO,, O,, and CO; (2) determine the percent-
age of the gas that is N, by subtracting the
137
-------
Chapter I—Environmental Protection Agency
App. A
sum of the percent CO3. percent O3, and per-
cent CO from 100 percent; and (3) calculate
percent excess air as outlined in Section 6.2.
4.1.4 To insure complete absorption of
the COi. Oi, or if applicable, CO, make re-
peated passes through each absorbing solu-
tion until two consecutive readings are the
same. Several passes (three or four) should
be made between readings. (If constant
readings cannot be obtained after three con-
secutive readings, replace the absorbing so-
lution.)
4.1.5 After the analysis is completed,
leak-check (mandatory) the Orsat analyzer
once again, as described in Section 5. For
the results of the analysis to be valid, the
Orsat analyzer must pass this leak test
before and after the analysis.
NOTE Since this single-point, grab sam-
pling and analytical procedure in normally
conducted .in conjunction with a single-
point, grab sampling and analytical proce-
dure for a pollutant, only one analysis is or-
dinarily conducted. Therefore, great care
must be taken to obtain a valid sample and
analysis. Although in most cases only CO,
or Oi is required, it is recommended that
both COi and O, be measured, and that Ci-
tation 5 in the Bibliography be used to vali-
date the analytical data.
4.2 Single-Point, Integrated Sampling
and Analytical Procedure.
4.2.1 The sampling point in the duct
shall be located as specified in Section 4.1.1.
4.2.2 Leak-check (mandatory) the flexi-
ble bag as in Section 2.2.6. Set up the equip-
ment as shown in Figure 3-2. Just prior to
sampling, leak-check (mandatory) the train '
by placing a vacuum gauge at the condenser
inlet, pulling a vacuum of a least 250 mm Hg
(10 in. Hg), plugging the outlet at the quick
disconnect, and then turning off the pump.
The vacuum shall remain stable for at least
0.5 minute. Evacuate the flexible bag. Con-
nect the probe and place it in the stack.
with the tip of the probe positioned at the
sampling point; purge the sampling line.
Next, connect the bag and make sure that
all connections are tight and leak free.
4.2.3 Sample at a constant rate, or as
specified by the Administrator. The sam-
pling run must be simultaneous with, and
for the same total lengh of time as, the pol-
lutant emission rate determination. Collect
at least 30 liters (1.00 ft3) of sample gas.
Smaller volumes may be collected, subject
to approval of the Administrator.
4.2.4 Obtain one integrated flue gas
sample during each pollutant emission rate
determination. For emission rate correction
factor determination, analyze the sample
within 4 hours after it is taken for percent
COi or percent O, (as outlined in Sections
4.2.5 through 4.2.7). The Orsat analyzer
must be leak-check (see Section 5) before
the analysis. If excess air is desired, proceed
as follows: (1) within 4 hours after the
sample is taken, analyze it (as in Sections
4.2.5 through 4.2.7) for percent CO3, O,, and
CO; (2) determine the percentage of the gas
that is N3 by subtracting the sum of the per-
cent CO,, percent O3, and percent CO from
100 percent; (3) calculate percent excess air,
as outlined in Section 6.2.
4.2.5 To insure complete absorption of
the COi, Oj, or if applicable, CO, make re-
peated passes through each absorbing solu-
tion until two consecutive readings are the
same. Several passes (three of four) should
be make between readings. (If constant
readings cannot be obtained after three con-
secutive readings, replace the absorbing so-
lution.)
4.2.6 Repeat the analysis until the fol-
lowing criteria are met:
4.2.6.1 For percent CO>, repeat the ana-
lytical procedure until the results of any
three analyses differ by no more that (a) 0.3
percent by volume when CO, is greater than
4.0 percent or (b) 0.2 percent by volume
when COj is less than or equal to 4.0 per-
cent. Average the three acceptable values of
percent COj and report the results to the
nearest 0.1 percent.
4.2.6.2 For percent Oj, repeat the analyt-
ical procedure until the results of any three
analyses differ by no more than (a) 0.3 per-
cent by volume when O, is less than 15.0
percent or (b) 0.2 percent by volume when
O, is greater than or equal to 15.0 percent.
Average the three acceptable values of per-
cent Oj and report the results to the nearest
0.1 percent.
4.2.6.3 For percent CO, repeat the ana-
lytical procedure until the results of any
three analyses differ by no more than 0.3
percent. Average the three acceptable
values of percent CO and report the results
to the nearest 0.1 percent.
4.2.7 After the analysis is completed.
leak-check (mandatory) the Orsat analyzer
once again, as described in Section 5. For
the results of the analysis to be valid, the
Orsat analyzer must pass this leak test
before an after the analysis.
NOTE: Although in most instances only
CO, or O3 is required, it is recommended
that both CO, and O, be measured, and that
Citation 5 in the Bibliography be used to
validate the analytical data.
4.3 Multi-Point, Integrated Sampling and
Analytical Procedure.
4.3.1 Both the minimum number of sam-
pling points and the sampling point location
shall be as specified in Section 3.3.1 of this
method. The use of fewer points than speci-
fied is subject to the approval of the Admin-
istrator.
4.3.2 Follow the procedures outlined in
Sections 4.2.2 through 4.2.7, except for the
following: Traverse all sampling points and
138
-------
APP. A
sample at each point for an equal length of
time. Record sampling data as shown in
Figure 3-3.
5. Leak-Check Procedure for Orsat Analyzers
Moving an Orsat analyzer frequently
causes it to leak. Therefore, an Orsat ana-
lyzer should be throughly leak-checked on
site before the flue gas sample is introduced
into it. The procedure for leak-checking an
Orsat analyzer is:
5.1.1 Bring the liquid level in each pi-
pette up to the reference mark on the capil-
lary tubing and then close the pipette stop-
cock.
5.1.2 Raise the leveling bulb sufficiently
to bring the confining liquid meniscus onto
the graduated portion of the burette and
then close the manifold stopcock.
5.1.3 Record the meniscus position.
5.1.4 Observe the menicus in the burette
and the liquid level in the pipette for move-
ment over the next 4 minutes.
5.1.5 For the Orsat analyzer to pass the
leak-check, two conditions must be met.
5.1.5.1 The liquid level in each pipette
must not fall below the bottom of the capil-
lary tubing during this 4-minute interval.
5.1.5.2 The meniscus in the burette must
not change by more than 0.2 ml during this
4-minute interval.
5.1.6 If the analyzer fails the leak-check
procedure, all rubber connections and stop-
cocks should be checked until the cause of
the leak is Identified. Leaking stopcocks
must be disassembled, cleaned, and re-
greased. Leaking rubber connections must
be replaced. After the analyzer is reassem-
bled, the leak-check procedure must be re-
peated.
8. Calculations
6.1 Nomenclature.
Ma=Dry molecular weight, g/g-mole Ub/lb-
mole).
%EA=Percent excess air.
%CO3=Percent CO, by volume (dry basis).
%O3=Percent O, by volume (dry basis).
%CO=Percent CO by volume (dry basis).
%N,=Percent N, by volume (dry basis).
0.264=Ratio of O, to N, in air, v/v.
0.280=Molecular weight of N, or CO, divid-
ed by 100.
0.320=Molecular weight of O, divided bv
100.
0.440=Molecular weight of CO, divided by
100.
6.2 Percent Excess Air. Calculate the per-
cent excess air (if applicable), by substitut-
ing the appropriate values of percent O,,
CO, and N, (obtained from Section 4.1.3 or
4.2.4) into Equation 3-1.
Title 40—Protection of Environment
r
L
100
0.264 %N2( %0,-0.5 %CO)
Equation 3-1
NOTE: The equation above assumes that
ambient air is used as the source of O, and
that the fuel does not contain appreciable
amounts of N, (as do coke oven or blast fur-
nace gases). For those cases when apprecia-
ble amounts of N, are present (coal, oil, and
natural gas do not contain appreciable
amounts of N,) or when oxygen enrichment
is used, alternate methods, subject to ap-
proval of the Administrator, are required.
6.3 Dry Molecular Weight. Use Equation
3-2 to calculate the dry molecular weight of
the stack gas
0.280(%N,+%CO)
Equation 3-2
NOTE: The above equation does not consid-
er argon in air (about 0.9 percent, molecu-
lars weight of 37.7). A negative error of
about 0.4 percent is introduced. The tester
may opt to include argon in the analysis
using procedures subject to approval of the
Administrator.
7. Bibliography
1. Altshuller, A. P. Storage of Gases and
Vapors in Plastic Bags. International Jour-
nal of Air and Water Pollution. 6.-75-81
1963.
2. Conner, William D. and J. S. Nader. Air
Sampling with Plastice Bags. Journal of the
American Industrial Hygiene Association
25.-291-297. 1964.
3. Burrell Manual for Gas Ana)ysts, Sev-
enth edition. Burrell Corporation, 2223
Fifth Avenue, Pittsburgh, Pa. 15219. 1951.
4. Mitchell, W. J. and M. R. Midgett. Field
Reliability of the Orsat Analyzer. Journal
of Air Pollution Control Association 25:491-
495. May 1976.
5. Shigehara, R. T., R. M. Neulicht, and
W. S. Smith. Validating Orsat Analysis Data
from Fossil Fuel-Fired Units. Stack Sam-
pling News. «2):21-26. August 1976
139
-------
App. A
Title 40—Protection of Environment
METHOD 7—DETERMINATION OP NITROGEN
OXIDE EMISSIONS PROM STATIONARY SOURCES
1. Principle and Applicability
1.1 Principle. A grab sample is collected
in an evacuated flask containing a dilute
sulfuric acid-hydrogen peroxide absorbing
solution, and the nitrogen oxides, except ni-
trous oxide, are measured colorimeterically
using the phenoldisulfonic acid (PDS) pro-
cedure.
1.2 Applicability. This method is applica-
ble to the measurement of nitrogen oxides
emitted from stationary sources. The range
of the method has been determined to be 2
to 400 milligrams NO, (as NO,) per dry
standard cubic meter, without having to
dilute the sample.
2. Apparatus
2.1 Sampling (see Figure 7-1). Other grab
sampling systems or_equipment, capable of
measuring sample volume to within ±2.0
percent and collecting a sufficient sample
volume to allow analytical reproducibility to
within ±5 percent, will be considered ac-
ceptable alternatives, subject to approval of
the Administrator. U.S. Environmental Pro-
tection Agency. The following equipment is
used in sampling:
2.1.1 Probe. Borosilicate glass tubing, suf-
ficiently heated to prevent water condensa-
tion and equipped with an in-stack or out-
stack filter to remove particulate matter (a
plug of glass wool is satisfactory for this
purpose). Stainless steel or Teflon 3 tubing
may also be used for the probe. Heating is
not necessary if the probe remains dry
during the purging period.
140
-------
Chapter I—Environmental Protection Agency
APP.A
O
ui
00Q
i'
tc
IU
a
c-
£
3
141
-------
Chapter I—Environmental Protection Agency
App.A
2.1.2 Collection Flask. Two-liter borosili-
cate, round bottom flask, with short neck
and 24/40 standard taper opening, protected
against implosion or breakage.
2.1.3 Flask Valve. T-bore stopcock con-
nected to a 24/40 standard taper joint.
2.1.4 Temperature Gauge. Dial-type ther-
mometer, or other temperature gauge, capa-
ble of measuring 1* C (2° F) intervals from
-5 to 50" C (25 to 125' F).
2.1.5 Vacuum Line. Tubing capable of
withstanding a vacuum of 75 mm Hg (3 in.
Hg) absolute pressure, with "T" connection
and T-bore stopcock.
2.1.6 Vacuum Gauge. U-tube manometer,
1 meter (36 in.), with 1-mm (0.1-in.) divi-
sions, or other gauge capable of measuring
pressure to within ±2.5 mm Hg (0.10 in.
Hg).
2.1.7 Pump. Capable of evacuating the
collection flask to a pressure equal to or less
than 75 mm Hg (3 in. Hg) absolute.
2.1.8 Squeeze Bulb. One-way.
2.1.9 Volumetric Pipette. 25 ml.
2.1.10 Stopcock and Ground Joint
Grease. A high-vacuum, high-temperature
chlorofluorocarbon grease is required. Halo-
carbon 25-5S has been found to be effective.
2.1.11 Barometer. Mercury, aneroid, or
other barometer capable of measuring at-
mospheric pressure to within 2.5 mm Hg"
(0.1 in. Hg). In many cases, the barometric
reading may be obtained from a nearby na-
tional weather service station, in which case
the station value (which is the absolute
barometric pressure) shall be requested and
an adjustment for elevation differences be-
tween the weather station and sampling
point shall be applied at a rate of minus 2.5
mm Hg (0.1 in. Hg) per 30 m (lO'O ft) eleva-
tion increase, or vice versa for elevation de-
crease.
2.2 Sample Recovery. The following
equipment is required for sample recovery:
2.2.1 Graduated Cylinder. 50 ml with 1-
ml divisions.
2.2.2 Storage Containers. Leak-free poly-
ethylene bottles.
2.2.3 Wash Bottle. Polyethylene or glass.
2.2.4 Glass Stirring Rod.
2.2.5 Test Paper for Indicating pH. To
cover the pH range of 7 to 14.
2.3 Analysis. For the analysis, the follow-
ing equipment is needed:
2.3.1 Volumetric Pipettes. Two 1 ml, two
2 ml, one 3 ml, one 4 ml, two 10 ml, and one
25 ml for each sample and standard.
2.3.2 Porcelain Evaporating Dishes. 175-
to 250-ml capacity with lip for pouring, one
for each sample and each standard. The
Coors No. 45006 (shallow-form, 195 ml) has
been found to be satisfactory. Alternatively,
polymethyl pentene beakers (Nalge No.
1203, 150 ml), or glass beakers (150 ml) may
be used. When glass beakers are used, etch-
ing of the beakers may cause solid matter to
be present in the analytical step; the solids
should be removed by filtration (see Section
4.3).
2.3.3 Steam Bath. Low-temperature
ovens or thermostatically controlled hot
plates kept below 70° C (160° F) are accept-
able alternatives.
2.3.4 Dropping Pipette or Dropper. Three
required.
2.3.5 Polyethylene Policeman. One for
each sample and each standard.
2.3.6 Graduated Cylinder. 100 ml with 1-
ml divisions.
2.3.7 Volumetric Flasks. 50 ml (one for
each sample and each standard), 100 ml
(one for each sample and each standard,
and one for the working standard KNO3 so-
lution), and 1000 ml (one).
2.3.8 Spectrophotometer. To measure ab-
sorbance at 410 nm.
2.3.9 Graduated Pipette. 10 ml with 0.1-
ml divisions.
2.3.10 Test Paper for Indicating pH. To
cover the pH range of 7 to 14.
2.3.11 Analytical Balance. To measure to
within 0.1 mg.
3. Reagents
Unless otherwise indicated, it is intended
that all reagents conform to the specifica-
tions established by the Committee on Ana-
lytical Reagents of the American Chemical
Society, where such specifications are avail-
able; otherwise, use the best available grade.
3.1 Sampling. To prepare the absorbing
solution, cautiously add 2.8 ml concentrated
HiSO, to 1 liter of deionized, distilled water.
Mix well and add 6 ml of 3 percent hydro-
gen peroxide, freshly prepared from 30 per-
cent hydrogen peroxide solution. The ab-
sorbing solution should be used- within 1
week of its preparation. Do not expose to
extreme heat or direct sunlight.
3.2 Sample Recovery. Two reagents are
required for sample recovery:
3.2.1 Sodium Hydroxide (1JV). Dissolve 40
g NaOH in deionized, distilled wacer and
dilute to 1 liter.
3.2.2 Water. Deionized, distilled to con-
form to ASTM specification D1193-74, Type
3. At the option of the analyst, the KMNO,
test for oxidizable organic matter may be
omitted when high concentrations of organ-
ic matter are not expected to be present.
3.3 Analysis. For the analysis, the follow-
ing reagents are required:
3.3.1 Fuming Sulfuric Acid. 15 to 18 per-
cent by weight free sulfur trioxide.
HANDLE WITH CAUTION.
3.3.2 Phenol. White solid.
3.3.3 Sulfuric Acid. Concentrated, 95 per-
cent minimum assay. HANDLE WITH CAU-
TION.
3.3.4 Potassium Nitrate. Dried at 105 to
110° C (220 to 230° F) for a minimum of 2
hours just prior to preparation of standard
solution.
142
-------
App. A
title 40—Protection of Environment
3.3.5 Standard KNO, Solution. Dissolve
exactly 2.198 g of dried potassium nitrate
(KNO3) in deionized, distilled water and
dilute to 1 liter with deionized, distilled
water in a 1,000-ml volumetric flask.
3.3.6 Working Standard KNO, Solution.
Dilute 10 ml of the standard solution to 100
ml with deionized distilled water. One mil-
liter of the working standard solution is
equivalent to 100 jig nitrogen dioxide (NO,).
3.3.7 Water. Deionized, distilled as in Sec-
tion 3.2.2.
3.3.8 Phenoldisulfonic Acid Solution. Dis-
solve 25 g of pure white phenol in 150 ml
concentrated sulfuric acid on a steam bath.
Cool, add 75 ml fuming sulfuric acid, and
heat at 100° C (212° P) for 2 hours. Store in
a dark, stoppered bottle.
4. Procedures
4.1 Sampling.
4.1.1 Pipette 25 ml of absorbing solution
into a sample flask, retaining-a sufficient
quantity for use in preparing the calibration
standards. Insert the flask valve stopper
into the flask with the valve in the "purge"
position. Assemble the sampling train as
shown in Figure 7-1 and place the probe at
the sampling point. Make sure that all fit-
ings are tight and leak-free, and that all
ground glass joints have been properly
greased with a high-vacuum, high-tempera""
ture chlorofluorocarbon-based stopcock
grease. Turn the flask valve and the pump
valve to their "evacuate" positions. Evacu-
ate the flask to 75 mm Hg (3 in. Hg) abso-
lute pressure, or less. Evacuation to a pres-
sure approaching the vapor pressure of
water at the existing temperature is desir-
able. Turn the pump valve to its "vent" po-
sition and turn the off the pump. Check for
leakage by observing the manometer for
any pressure fluctuation. (Any variation
greater than 10 mm Hg (0.4 in. Hg) over a
period of 1 minute is not acceptable, and the
flask is not to be used until the leakage
problem is corrected. Pressure in the flask is
not to exceed 75 mm Hg (3 in. Hg) absolute
at the time sampling is commenced.) Record
the volume of the flask and valve (Vf), the
flask temperature (Ti), and the barometric
pressure. Turn the flask valve counterclock-
wise to its "purge" position and do the same
with the pump valve. Purge the probe and
the vacuum tube using the squeeze bulb. If
condensation occurs in the probe and the
flask valve area, heat the probe and purge
until the condensation disappears. Next,
turn the pump valve to its "vent" position.
Turn the flask valve clockwise to its "evacu-
ate" position and record the difference in
the mercury levels in the manometer. The
absolute internal pressure in the flask (Vj) is
equal to the barometric pressure less the
manometer reading. Immediately turn the
flask valve to the "sample" position and
permit the gas to enter the flask until pres-
sures in the flask and sample line (i.e., duct.
stack) are equal. This will usually require
about 15 seconds; a longer period indicates a
"plug" in the probe, which must be correct-
ed before sampling is continued. After col-
lecting the sample, turn the flask valve to
its "purge" position and disconnect the flask
from the sampling train. Shake the flask for
at least 5 minutes.
4.1.2 If the gas being sampled contains
insufficient oxygen for the conversion of
NO to Nd (e.g., an applicable subpart of
the standard may require taking a sample of
a calibration gas mixture of NO in N,), then
oxygen shall be introduced into the flask to
permit this conversion. Oxygen may be in-
troduced into the flask by one of three
methods; (1) Before evacuating the sam-
pling flask, flush with pure cylinder oxygen,
then evacuate flask to 75 mm Hg (3 in. Hg)
absolute pressure or less; or (2) inject
oxygen into the flask after sampling; or (3)
terminate sampling with a minimum of 50
mm Hg (2 in. Hg) vacuum remaining in the
flask, record this final pressure, and then
vent the flask to the atmosphere until the
flask pressure is almost equal to atmospher-
ic pressure.
4.2 Sample Recovery. Let the flask set
for a minimum of 16 hours and then shake
the contents for 2 minutes. Connect the
flask to a mercury filled U-tube manometer.
Open the valve from the flask to the mano-
meter and record the flask temperature"(2>),
the barometric pressure, and the difference
between the mercury levels in the mano-
meter. The absolute internal pressure in the
flask (Pf) is the barometric pressure less the
manometer reading. Transfer the contents
of the flask to a leak-free polyethylene
bottle. Rinse the flask twice with 5-ml por-
tions of deionized, distilled water and add
the rinse water to the bottle. Adjust the pH
to between 9 and 12 by adding sodium hy-
droxide (1 N), drop wise (about 25 to 35
drops). Check the pH bv dipping a stirring
rod into the solution and then touching the
rod to the pH test paper. Remove as little
material as possible during this step. Mark
the height of the liquid level so that the
container can be checked for leakage after
transport. Label the container to clearly
identify its contents. Seal the container for
shipping.
4.3 Analysis. Note the level of the liquid
in container and confirm whether or not
any sample was lost during shipment; note
this on the analytical data sheet. If a notice-
able amount of leakage has occurred, either
void the sample or use methods, subject to
the approval of the Administrator, to cor-
rect the final results. Immediately prior to
analysis, transfer the contents of the ship-
ping container to a 50-ml volumetric flask.
and rinse the container twice with 5-ml por-
tions of deionized, distilled water. Add the
143
-------
Chapter I—Environmental Protection Agency
rinse water to the flask and dilute to the
mark with deionized, distilled water; mix
thoroughly. Pipette a 25-ml aliquot into the
procelain evaporating dish. Return any
unused portion of the sample to the poly-
ethylene storage bottle. Evaporate the 25-
ml aliquot to dryness on a steam bath and
allow to cool. Add 2 ml phenoldisulfonic
acid solution to the dried residue and trit-
urate thoroughly with a polyethylene po-
liceman. Make sure the solution contacts all
the residue. Add 1 ml deionized. distilled
water and four drops of concentrated sulfu-
ric acid. Heat the solution on a steam bath
for 3 minutes with occasional stirring. Allow
:he solution to cool, add 20 ml deionized,
distilled water, mix well by stirring, and add
concentrated ammonium hydroxide, drop-
wise, with constant stirring, until the pH is
10 (as determined by pH paper). If the
sample contains solids, these must be re-
moved by filtration (centrifugation is an ac-
ceptable alternative, subject to the approval
of the Administrator), as follows: filter
through Whatman No. 41 filter paper into a
100-ml volumetric flask; rinse the evaporat-
ing dish with three 5-ml portions of deion-
ized. distilled water; filter these three rinses.
Wash the filter with at least three 15-ml
portions of deionized, distilled water. Add-
the filter washings to the contents of the
volumetric flask and dilute to the mark with
deionized, distilled water. If solids are
absent, the solution can be transferred di-
rectly to the 100-ml volumetric flask and di-
luted to the mark with deionized, distilled
•*iter. Mix the contents of the flask thor-
oughly, and measure the absorbance at the
optimum wavelength used for the standards
Section 5.2.1), using the blank solution as a
zero reference. Dilute the sample and the
blank with equal volumes of deionized, dis-
tilled water if the absorbance exceeds A,,
the absorbance of the 400 /ig NO, standard
see Section 5.2.2).
App. A
5. Calibration
5.1 Flask Volume. The volume of the col-
lection flask-flask valve combination must
be known prior to sampling. Assemble the
flask and flask valve and fill with water, to
the stopcock. Measure the volume of water
'.o =10 ml. Record this volume on the flask.
5.2 Spectrophotometer Calibration.
5.2.1 Optimum Wavelength Determina-
tion. Calibrate the wavelength scale of the
^pectrophotometer every 6 months. The
•alteration may be accomplished by using
an energy source with an intense line emis-
-.on such as a mercury lamp, or by using a
•cries of glass filters spanning the measur-
•ng range of the Spectrophotometer. Cali-
bration materials are available commercially
and from the National Bureau of Standards.
Specific details on the use of such materials
>hould be supplied by the vendor; general
..".formation about calibration techniques
can be obtained from general reference
books on analytical chemistry. The wave-
length scale of the Spectrophotometer must
read correctly within ± 5 nm al all calibra-
tion points; otherwise, the specrophoto-
meter shall be repaired and recalibrated.
Once the wavelength scale of the Spectro-
photometer is in proper calibration, use 410
nm as the optimum wavelength for the mea-
surement of the absorbance of the stand-
ards and samples.
Alternatively, a scanning procedure may
be employed to determine the proper meas-
uring wavelength. If the instrument is a
double-beam Spectrophotometer, scan the
spectrum between 400 and 415 nm using a
200 fig NO, standard solution in the sample
cell and a blank solution in the reference
cell. If a peak does not occur, the Spectro-
photometer is probably malfunctioning and
should be repaired. When a peak is obtained
within the 400 to 415 nm range, the wave-
length at which this peak occurs shall be
the optimum wavelength for the measure-
ment of absorbance of both the standards
and the samples. For a single-beam Spectro-
photometer, follow the scanning procedure
described above, except that the blank and
standard solutions shall be scanned sepa-
rately. The optimum wavelength shall be
the wavelength at which the maximum dif-
ference in absorbance between the standard
and the blank occurs.
5.2.2 Determination of Spectrophoto-
meter Calibration Factor Ke. Add 0.0 ml, 2
ml, 4 ml, 6 ml., and 8 ml of the KNO, work-
ing standard solution (1 ml=100 ps NO,) to
a series of five 50-ml volumetric flasks. To
each flask, add 25 ml of absorbing solution,
10 ml deionized, distilled water, and sodium
hydroxide (1 N) dropwise until the pH is be-
tween 9 and 12 (about 25 to 35 drops each).
Dilute to the mark with deionized. distilled
water. Mix thoroughly and pipette a 25-ml
aliquot of e?ch solution into a separate por-
celain evaporating dish. Beginning with the
evaporation step, follow the analysis proce-
dure of Section 4.3 until the solution has
been transferred to the 100 ml volumetric
flask and diluted to the mark. Measure the
absorbance of each solution, at the opti-
mum wavelength, as determined in Section
5.2.1. This calibration procedure must be re-
peated on each day that samples are ana-
lyzed. Calculate the Spectrophotometer cali-
bration factor as follows:
Equation 7-1
144
-------
App. A
Title 40—Protection of Environment
where:
JTC=Calibration factor
4,=Absorbance of the 100-jig NO2 standard
4j=Absorbance of the 200-jig NO2 standard
.43=Absorbance of the 300-jig NO2 standard
<4<=Absorbance of the 400-^g NO2 standard
5.3 Barometer. Calibrate against a mer-
cury barometer.
5.4 Temperature Gauge. Calibrate dial
thermometers against mercury-in-glass
thermometers.
5.5 Vacuum Gauge. Calibrate mechanical
gauges, if used, against a mercury mano-
meter such as that specified in 2.1.6.
5.6 Analytical Balance. Calibrate against
standard weights.
6. Calculations
Carry out the calculations, retaining at
least one extra decimal figure beyond that
of the acquired data. Round off figures
after final calculations.
6.1' Nomenclature.
.A=Absorbance of sample.
C= Concentration of NO* as NO2> dry basis,
corrected to standard conditions, mg/
dscm (Ib/dscf). '
^Dilution factor (i.e., 25/5, 25/10, etc., re^..
quired only if sample dilution was
needed to reduce the absorbance into
the range of calibration).
.K:=Spectrophotometer calibration factor.
m=Mass of NOr as NO2 in gas sample, pig.
.P,=Final absolute pressure of flask, mm Hg
(in. Hg}.
Pi=Initial absolute pressure of flask, mm
Hg (in. Hg).
•P,,= Final absolute temperature of flask, °K
CR).
Ti=Initial absolute temperature of flask, °K
(°R>.
r,,rt=Standard absolute temperature 293° K
(528° R)
V«r=Sample volume at standard conditions
(dry basis), ml.
Vf=Volume of flask and valve, ml.
Va=Volume of absorbing soluton, 25 ml.
2 = 50/25, the aliquot factor. (If other than a
25-ml aliquot was used for analysis, the
corresponding factor must be substitut-
ed).
6.2 Sample volume, dry basis, corrected to
standard conditions.
A"i = 0.3858
mm Hg
for metric units
= 17.64 r
in. Hg
for English units
6.3 Total jig NO: per sample.
Equation 7-3
NOTE: If other than a 25-ml aliquot is used
for analysis, the factor 2 must be replaced
by a corresponding factor.
6.4 Sample concentration, dry basis, cor-
rected to standard conditions.
Equation 7-4
where:
=3 ,-,- for metric units
0.243 X 10-5 - for English units
Equation 7-2
7. Bibliography
1. Standard Methods of Chemical Analysis
6th ed. New York, D. Van Nostrand Co., Inc.
1962. Vol. 1, p. 329-330.
2. Standard Method of Test for Oxides of
Nitrogen in Gaseous Combustion Products
(Phenoldisulfonic Acid Procedure). In: 1968
Book of ASTM Standards, Part 26. Philade-
phia. Pa. 1968. ASTM Designation D-1608-
60, p. 725-729.
3. Jacob, M. B. The Chemical Analysis of
Air Pollutants. New York. Interscience Pub-
lisher, Inc. 1960. Vol. 10, p. 351-356.
4. Beatty, R. L., L. B. Berger, and H. H.
Schrenk. Determination of Oxides of Nitro-
gen by the Phenoldisulfonic Acid Method.
Bureau of Mines, U.S. Dept. of Interior. R.I.
3687. February 1943.
145
-------
Chapter I—Environmental Protection Agency
APP.A
5. Hamil, H. F. and D. E. Camann. Col-
laborative Study of method for the Deter-
mination of Nitrogen Oxide Emissions from
Stationary Sources (Fossil Fuel-Fired Steam
Generators). Southwest Research Institute
report for Environmental Protection
Agency. Research Triangle Park, N.C. Octo-
ber 5, 1973.
6. Hamil, H. F. and R. E. Thomas. Collabo-
rative Study of Method for the Determina-
tion of Nitrogen Oxide Emissions from Sta-
tionary Sources (Nitric Acid Plants). South-
west Research Institute report for Environ-
mental Protection Agency. Research Trian-
gle Park, N.C. May 8, 1974.
146
-------
App. A
Title 40—Protection of Environment
147
-------
Chapter I—Environmental Protection Ageney
App. B
PERFORMANCE SPECIFICATION 2—PERFORM-
ANCE SPECIFICATIONS AND SPECIFICATION
TEST PROCEDURES FOR MONITORS OF SO3
AND NO. FROM STATIONARY SOURCES
1. Principle and Applicability.
1.1 Principle. The concentration of sulfur
dioxide or oxides of nitrogen pollutants in
stack emissions is measured by a continu-
ously operating emission measurement
system. Concurrent with operation of the
continuous monitoring system, the pollut-
ant concentrations are also measured with
reference methods (Appendix A). An aver-
age of the continuous monitoring system
data is computed for each reference method
testing period and compared to determine
the relative accuracy of the continuous
monitoring system. Other tests of the con-
tinuous monitoring system- are also per-
formed to determine calibration error, drift.
and response characteristics of the system. —
1.2 Applicability. This performance speci-
fication is applicable to evaluation of con-
tinuous monitoring systems for measure-
ment of nitrogen oxides or sulfur dioxide
pollutants. These specifications contain test
procedures, installation requirements, and
data computation procedures for evaluating
the acceptability of the continuous monitor-
ing systems.
2. Apparatus.
2.1 Calibration Gas Mixtures. Mixtures of
known concentrations of pollutant gas in a
diluent gas shall be prepared. The pollutant
gas shall be sulfur dioxide or the appropri-
ate oxide(s) of nitrogen specified by para-
graph 6 and within subparts. For sulfur
dioxide gas mixtures, the diluent gas may be
air or nitrogen. For nitric oxide (NO) gas
mixtures, the diluent gas shall be oxygen-
free (<10 ppm) nitrogen, and for nitrogen
dioxide (NO,) gas mixtures the diluent gas
shall be air. Concentrations of approximate-
ly 50 percent and 90 percent of span are re-
quired. The 90 percent gas mixture is used
to set and to check the span and is referred
to as the span gas.
2.2 Zero Gas. A gas certified by the manu-
facturer to contain less than 1 ppm of the
pollutant gas or ambient air may be used.
2.3 Equipment for measurement of the
pollutant gas concentration using the refer-
143
-------
App. B
Title 40—Protection of Environment
ence method specified in the applicable
standard.
2.4 Data Recorder. Analog chart recorder
or other suitable device with input voltage
range compatible with analyzer system
output. The resolution of the recorder's
data output shall be sufficient to allow com-
pletion of the test procedures within this
specification.
2.5 Continuous monitoring system for SO,
or NO, pollutants as applicable.
3. Definitions.
3.1 Continuous Monitoring System. The
total equipment required for the determina-
tion of a pollutant gas concentration in a
source effluent. Continuous monitoring sys-
tems consist of major subsystems as follows:
3.1-.1 Sampling Interface. That portion of
an extractive continuous monitoring system
that performs one or more of the following
operations: acquisition, transportation, and
conditioning of a sample fo the source efflu-
ent or that portion of an in-situ continuous
monitoring system that protects the analyz-
er from the effluent.
3.1.2 Analyzer. That portion of the con-
tinuous monitoring system which senses the
pollutant gas and generates a signal output
that is a function of the pollutant concen-
tration.
3.1.3 Data Recorder. That portion of the-
continuous monitoring system that provides
a permanent record of the output signal in
terms of concentration units.
3.2- Span. The value of pollutant concen-
tration at which the continuous monitoring
system is set to produce the maximum data
display output. The span shall be set at the
concentration specified in each applicable
subpart.
3.3 Accuracy (Relative). The degree of cor-
rectness with which the continuous moni-
toring system yields the value of gas concen-
tration of a sample relative to the value
given by a defined reference method. This
accuracy is expressed in terms of error,
which is the difference between the paired
concentration measurements expressed as a
percentage of the mean reference value.
3.4 Calibration Error. The difference be-
tween the pollutant concentration indicated
by the continuous monitoring system and
the known concentration of the test gas
mixture.
3.5 Zero Drift. The change in the continu-
ous monitoring system output over a stated
period of time of normal continuous oper-
ation when the pollutant concentration at
the time for the measurements is zero.
3.6 Calibration Drift. The change in the
continuous monitoring system output over a
stated time period of normal continuous op-
erations when the pollutant concentration
at the time of the measurements is the same
known upscale value.
3.7 Response Time. The time interval
from a step change in pollutant concentra-
tion at the input to the continuous monitor-
ing system to the time at which 95 percent
of the corresponding final value is reached
as displayed on the continuous monitoring
system data recorder.
3.8 Operational Period. A minimum period
of time over which a measurement system is
expected to operate within certain perform-
ance specifications without unscheduled
maintenance, repair, or adjustment.
3.9 Stratification. A condition identified
by a difference in excess of 10 percent be-
tween the average concentration in the duct
or stack and the concentration at any point
more than 1.0 meter from the duct or stack
wall.
4. Installation Specifications. Pollutant
continuous monitoring systems (SO, and
NO,) shall be installed at a sampling loca-
tion where measurements can be made
which are directly representative (4.1), or
which can be corrected so as to be repre-
sentative (4.2) of the total emissions from
the affected facility. Conformance with this
requirement shall be accomplished as fol-
lows:
4.1 Effluent gases may be assumed to be
nonstratified if a sampling location eight or
more stack diameters (equivalent diameters)
downstream of any air in-leakage is selected.
This assumption and data correction proce-
dures under paragraph 4.2.1 may not be ap-
plied to sampling locations upstream of an
air preheater in a stream generating facility
under Subpart D of this part. For sampling
locations where effluent gases are either
demonstrated (4.3) or may be assumed to be
nonstratified (eight diameters), a point (ex-
tractive systems) or path (in-situ systems) of
average concentration may be monitored.
4.2 For sampling locations where effluent
gases cannot be assumed to be nonstratified
(less than eight diameters) or have been
shown under paragraph 4.3 to be stratified,
results obtained must be consistently repre-
sentative (e.g. a point of average concentra-
tion may shift with load changes) or the
data generated by sampling at a point (ex-
tractive systems) or across a path (in-situ
systems) must be corrected (4.2.1 and 4.2.2)
so as to be representative of the total emis-
sions from the affected facility. Conform-
ance with this requirement may be accom-
plished in either of the following ways:
4.2.1 Installation of a diluent continuous
monitoring system (O, or CO, as applicable)
in accordance with the procedures under
paragraph 4.2 of Performance Specification
3 of this appendix. If the pollutant and di-
luent monitoring systems are not of the
same type (both extractive or both in-situ),
the extractive system must use a multipoint
probe.
4.2.2 Installation of extractive pollutant
monitoring systems using multipoint sam-
pling probes or in-situ pollutant monitoring
149
-------
Chapter I—Environmental Protection Agency
App. B
systems that sample or view emissions
which are consistently representative of the
total emissions for the entire cross section.
The Administrator may require data to be
submitted to demonstrate that the emis-
sions sampled or viewed are consistently
representative for several typical facility
process operating conditions.
4.3 The owner or operator may perform a
traverse to characterize any stratification of
effluent gases that might exist in a stack or
duct. If no stratification is present, sam-
pling procedures under paragraph 4.1 may
be applied even though the eight diameter
criteria is not met.
4.4 When single point sampling probes for
extractive systems are installed within the
stack or duct under paragraphs 4.1 and
4.2.1, the sample may not be extracted at
any point less than 1.0 meter from the stack
or duct wall. Multipoint sampling probes in-
stalled under paragraph 4.2.2 may be locat-
ed at any points necessary to obtain consist-
ently representative samples.
5. Continuous Monitoring System Per-
formance Specifications.
The continuous monitoring system shall
meet the performance specifications in
Table 2-1 to be considered acceptable under
this method.
TABLE 2-1—PERFORMANCE SPECIFICATIONS
Parameter
1, Accuracy'
Z. Calibration error1
3, Zero drift (2 h) '
4. Zero drift (24 h) '
5 Calibration drift (2 h) '
6. Calibration drift (24 h) >
7, Response time.. «
8. Operational period
Specification
<20 pet of the mean value of the reference method test data.
< 5 pet of each (50 pet, 90 pet) calibration gas mixture value.
Do.
Do
2.5 pet of span.
15 min maximum.
168 h minimum.
' Expressed as sum of absolute mean value plus 95 pet confidence interval of a series of tests.
6. Performance Specification Test Proce-
dures. The following test procedures shall
be used to determine conformance with the
requirements of paragraph 5. For NO, ana-
lyzers that oxidize nitric oxide (NO) to ni-
trogen dioxide (NO,),the response time test
under paragraph 6.3 of this method shall be
performed using nitric oxide (NO) span gas.
Other'tests for NO, continuous monitoring
systems under paragraphs 6.1 and 6.2 and
all tests for sulfur dioxide systems shall be
performed using the pollutant span gas
specified by each subpart.
6.1 Calibration Error Test Procedure. Set
up and calibrate the complete continuous
monitoring system according to the manu-
facturer's written instructions. This may be
accomplished either in the laboratory or in
the field.
6.1.1 Calibration Gas Analyses. Triplicate
analyses of the gas mixtures shall be per-
formed within two weeks prior to use using
Reference Methods 6 for SO3 and 7 for NO,.
Analyze each calibration gas mixture (50%,
90%) and record the results on the example
sheet shown in Figure 2-1. Each sample test
result must be within 20 percent of the aver-
aged result or the tests shall be repeated.
This step may be omitted for non-extractive
monitors where dynamic calibration gas
mixtures are not used (6.1.2).
6.1.'2 Calibration Error Test Procedure.
Make a total of 15 nonconsecutive meas-
urements by alternately using zero gas and
each calibration gas mixture concentration
(e.g., 0%, 50%, 0%, 90%, 50%, 90%, 50%, 0%,
etc.). For nonextractive continuous monitor-
ing systems, this test procedure may be per-
formed by using two or more calibration gas
cells whose concentrations are certified by
the manufacturer to be functionally equiva-
lent to these gas concentrations. Convert
the continuous monitoring system output
readings to ppm and record the results on
the example sheet shown in Figure 2-2.
6.2 Field Test for Accuracy (Relative),
Zero Drift, and Calibration Drift. Install
and operate the continuous monitoring
system in accordance with the manufactur-
er's written instructions and drawings as fol-
lows:
6.2.1 Conditioning Period. Offset the zero
setting at least 10 percent of the span so
that negative zero drift can be quantified.
Operate the system for an initial 168-hour
conditioning period in normal operating
manner.
6.2.2 Operational Test Period. Operate the
continuous monitoring system for an addi-
tional 168-hour period retaining the zero
offset. The system shall monitor the source
effluent at all times except when being
zeroed, calibrated, or backpurged.
6.2.2.1 Field Test for Accuracy (Relative).
For continuous monitoring systems employ-
ing extractive sampling, the probe tip for
the continuous monitoring system and the
probe tip for the Reference Method sam-
pling train should be placed at adjacent lo-
cations in the duct. For NO, continuous
150
-------
App. B
Title 40—Protection of Environment
monitoring systems, make 27 NO, concen-
tration measurements, divided into nine
sets, using the applicable reference method.
No more than one set of tests, consisting of
three individual measurements, shall be per-
formed in any one hour. All individual
measurements of each set shall be per-
formed concurrently, or within a three-
minute interval and the results averaged.
For SOa continuous monitoring systems,
make nine SO* concentration measurements
using the applicable reference method. No
more than one measurement shall be per-
formed in any one hour. Record the refer-
ence method test data and the continuous
monitoring system concentrations on the
example data sheet shown in Figure 2-3.
6.2.2.2 Field Test for Zero Drift and Cali-
bration Drift. For extractive systems, deter-
mine the values given by zero and span gas
pollutant concentrations at two-hour inter-
vals until 15 sets of data are obtained. For
nonextractive measurement systems, the
zero value may be determined by mechani-
cally producing a zero condition that pro-
vides -a system check of the analyzer inter-
nal mirrors and all electronic circuitry in-
cluding the radiation source and detector
assembly or by inserting three or more cali-.
oration gas cells and computing the zero--
point from the upscale measurements. If
this latter technique is used, a graph(s)
must be retained by the owner or operator
for each measurement system that shows
the relationship between the upscale meas-
urements and the zero point. The span of
the system shall be checked by using a cali-
bration gas cell certified by the manufactur-
er to be functionally equivalent to 50 per-
cent of span concentration. Record the zero
and span measurements (or the computed
zero drift) on the example data sheet shown
in Figure 2-4. The two-hour periods over
which measurements are conducted need
not be consecutive but may not overlap. All
measurements required under this para-
graph may be conducted concurrent with
tests under paragraph 6.2.2.1.
6.2.2.3 Adjustments. Zero and calibration
corrections and adjustments are allowed
only at 24-hour intervals or at such shorter
intervals as the manufacturer's written
instructions specify. Automatic corrections
made by the measurement system without
operator intervention or initiation are allow-
able at any time. During the entire 168-hour
operational test period, record on the exam-
ple sheet shown in Figure 2-5 the values
given by zero and span gas pollutant con-
centrations before and after adjustment at
24-hour intervals.
8.3 Field Test for Response Time.
6.3.1 Scope of Test. Use the entire con-
tinuous monitoring system as installed, in-
cluding sample transport lines if used. Flow
rates, line diameters, pumping rates, pres-
sures (do not allow the pressurized calibra-
tion gas to change the normal operating
pressure in the sample line), etc., shall be at
the nominal values for normal operation as
specified in the manufacturer's written
instructions. If the analyzer is used to
sample more than one pollutant source
(stack), repeat this test for each sampling
point.
6.3.2 Response Time Test Procedure. In-
troduce zero gas into the continuous moni-
toring system sampling interface or as close
to the sampling interface as possible. When
the system output reading has stabilized,
switch quickly to a known concentration of
pollutant gas. Record the time from concen-
tration switching to 95 percent of final
stable response. For non-extractive moni-
tors, the highest available calibration gas
concentration shall be switched into and out
of the sample path and response times re-
corded. Perform this test sequence three (3)
times. Record the results of each test on the
example sheet shown in Figure 2-6.
7. Calculations. Data Analysis and Report-
ing.
7.1 Procedure for determination of mean
values and confidence intervals.
7.1J The mean value of a data set is calcu-
lated according to equation 2-1.
i n
*-= 2*.
Equation 2-1
where:
x,=absolute value of the measurements,
2=sum of the individual values.
x=mean value, and
n=number of data points.
7.1.2 The 95 percent confidence interval
(two-sided) is calculated according to equa-
tion 2-2:
—1
Equation 2-2
where:
2x,=sum of all data points, t..,,=t,—a/2,
and
C.I...=95 percent confidence interval esti-
mate of the average mean value.
151
-------
Chapter I—Environmental Protection Agency
App. B
VALUES FOR '.975
'1.975
2
3,, , .
4 „
5,....,
6...,. „
7... . .
8,...,
9
10,....,,
11,,,
12,., ,
13..,..™
14.. ,
15 ..
16., „
12.706
4.303
3 182
2776
2.571
2.447
2.365
2.306
2262
2.228
2.201
2 179
2.160
2.145
2.131
The values in this table are already cor-
rected for n-1 degrees of freedom. Use n
equal to the number of samples as data
points.
7.2 Data Analysis and Reporting.
7.2.1 Accuracy (Relative). For each of the
nine reference method test points, deter-
mine the average pollutant concentration
reported by the continuous monitoring
system. These average concentrations shall
be determined from the continuous moni—
toring system data recorded under 7.2.2 by
integrating or averaging the pollutant con-
centrations over each of the time intervals
concurrent with each reference method
testing period. Before proceeding to the
next step, determine the basis (wet or dry)
of the continuous monitoring system data
and reference method test data concentra-
tions. If the bases are not consistent, apply
a moisture correction to either reference
method concentrations or the continuous
monitoring system concentrations as appro-
priate. Determine the correction factor by
moisture tests concurrent with the refer-
ence method testing periods. Report the
moisture test method and the correction
procedure employed. For each of the nine
test runs determine the difference for each
test run by subtracting the respective refer-
ence method test concentrations (use aver-
age of each set of three measurements for
NO,) from the continuous monitoring
system integrated or averaged concentra-
tions. Using these data, compute the mean
difference and the 95 percent confidence in-
terval of the differences (equations 2-1 and
2-2). Accuracy is reported as the sum of the
absolute value of the mean difference and
the 95 percent confidence interval of the
differences expressed as a percentage of the
mean reference method value. Use the ex-
ample sheet shown in Figure 2-3.
7.2.2 Calibration Error. Using the data
from paragraph 6.1, subtract the measured
pollutant concentration determined under
paragraph 6.1.1 (Figure 2-1) from the value
shown by the continuous monitoring system
for each of the five readings at each concen-
tration measured under 6.1.2 (Figure 2-2).
Calculate the mean of these difference
values and the 95 percent confidence inter-
vals according to equations 2-1 and 2-2.
Report the calibration error (the sum of the
absolute value of the mean difference and
the 95 percent confidence interval) as a per-
centage of each respective calibration gas
concentration. Use example sheet shown in
Figure 2-2.
7.2.3 Zero Drift (2-hour). Using the zero
concentration values measured each 2-hours
during the field test, calculate the differ-
ences between consecutive 2-hour readings
expressed in ppm. Calculate the mean dif-
ference and the confidence interval using
equations 2-1 and 2-2. Report the zero drift
as the sum of the absolute mean value and
the confidence interval as a percentage of
span. Use example sheet shown in Figure 2-
4.
7.2.4 Zero Drift (24-hour). Using the zero
concentration values measured every 24
hours during the field test, calculate the dif-
ferences between the zero point after zero
adjustment and the zero value 24 hours
later just prior to zero adjustment. Calcu-
late the mean value of these points and the
confidence interval using equations 2-1 and
2-2. Report the zero drift (the sum of the
absolute mean and confidence interval) as a
percentage of span. Use example sheet
shown in Figure 2-5.
7.2.5 Calibration Drift (2-hour). Using the
calibration values obtained at 2-hour inter-
vals during the field test, calculate the dif-
ferences between consecutive 2-hour read-
ings expressed as ppm. These values should
be corrected for the corresponding zero drift
during that 2-hour period. Calculate the
mean and confidence interval of these cor-
rected difference values using equations 2-1
and 2-2. Do not use the differences between
non-consecutive readings. Report the cali-
bration drift as the sum of the absolute
mean and confidence interval as a percent-
age of span. Use the example sheet shown
in Figure 2-4.
7.2.6 Calibration Drift (24-hour). Using
the calibration values measured every 24
hours during the field test, calculate the dif-
ferences between the calibration concentra-
tion reading after zero and calibration ad-
justment, and the calibration concentration
reading 24 hours later after zero adjustment
but before calibration adjustment. Calculate
the mean value of these differences and the
confidence interval using equations 2-1 and
2-2. Report the calibration drift (the sum of
the absolute mean and confidence interval)
as a percentage of span. Use the example
sheet shown in Figure 2-5.
7.2.7 Response Time. Using the charts
from paragraph 6.3, calculate the time in-
152
-------
App. B
Title 40—Protection of Environment
terval from concentration switching to 95
percent to the final stable value for all
upscale and downscale tests. Report the
mean of the three upscale test times and
the mean of the three downscale test times.
The two average times should not differ by
more than 15 percent of the slower time.
Report the slower time as the system re-
sponse time. Use the example sheet shown
in Figure 2-6.
7.2.8 Operational Test Period. During the
168-hour performance and operational test
period, the continuous monitoring system
shall not require any corrective mainte-
nance, repair, replacement, or adjustment
other than that clearly specified as required
in the operation and maintenance manuals
as routine and expected during a 1-week
period. If the continuous monitoring system
operates within the specified performance
parameters and does not require corrective
maintenance, repair, replacement or adjust-
ment other than as specified above during
the 168-hour test period, the operational.
period will be successfully concluded. Fail-
ure of the continuous monitoring system to
meet this requirement shall call for a repeti-
tion of the 168-hour test period. Portions of
the test which were satisfactorily completed
need not be repeated. Failure to meet any
performance specifications shall call for a
repetition of the 1-week performance test
period and that portion of the testing which
is related to the failed specification. All
maintenance and adjustments required
shall be recorded. Output readings shall be
recorded before and after all adjustments.
8. References.
8.1 "Monitoring Instrumentation for the
Measurement of Sulfur Dioxide in Station-
ary Source Emissions," Environmental Pro-
tection Agency, Research Triangle Park
N.C., February 1973.
8.2 "Instrumentation for the Determina-
tion of Nitrogen Oxides Content of Station-
ary Source Emissions," Environmental Pro-
tection Agency, Research Triangle Park.
N.C., Volume 1, APTD-0847, October 1971:
Volume 2, APTD-0942, January 1972.
8.3 "Experimental Statistics," Department
of Commerce, Handbook 91, 1963, pp. 3-31.
paragraphs 3-3.1.4.
8.4 "Performance Specifications for Sta-
tionary Source Monitoring Systems for
Gases and Visible Emissions," Environmen-
tal Protection Agency, Research Triangle
Park, N.C., EFA-650/2-74-013, January
1974.
HlJ-Sange Calltratlcn <
High-Range fsparl CaHbratiai ^js Mixture
Figure Z-l. Aiulysil of CallBratlon 041 nix
153
-------
Chapter I—Environmental Protection Agency
App. B
Calibration Gas Mixture Data (From Figure 2-1)
Hid (SOS) ppm High (90S) ppm
Run i
Calibration Has
Concentration, ppnr
Measurement System
Reading, ppm
Differences, PPB
4
IS
Kean difference
Confidence interval
Calibration error •
Mean Difference' + C.I.
Wd High
Average Calibration Gas Concentration
x 100
Calibration gas concentration - measurement system reading
Absolute value
Figure 2-2. Calibration Error Determination
154
-------
App. B
Title 40—Protection of Environment
rut
No.
1
2
Data
. and
Time
Reference Mstnod Samoles
SO,
Sampfs 1
( pp.ii }
3 1
4 i
S !
6 1
7
3
g
fean
:est
151 (
tecur
>Exf
reference rr
value (S02J
.onfidence i
ethod
ntervals *
Mean of
NO
Sampfe 1
(ppm)
NO
Sample 2
(ppm)
NO NO Sample
Sample 3 Average
(ppm) (ppm)
1
j
|
Analyzer 1-Hour
Average (ppm)*
S02 NOX
i
Hean reference method
test, value (NO )
+ ppm
(SOJ • +
the differences > gjj confidence Interval .. ,„„ .
ac Mean reference method value " '" -
l»1n and report method used to determine Integrated averages
Difference
(ppm)
S02 NO,
Mean of
the differences
em
« Cso2
NOX)
.
' MX'
Figure 2-3. Accuracy Determination (SOj and NOX)
Jata
Set
NO.
Time
Begin End
Date
Zero
Reading
Zero
Drift
(aZero)
Span
Reading
Span
Drift
(iSpan)
Calibration
Drift
( Span- Zero)
10
14
IS
Zero Drift » [Mean Zero Drift*
Calibration Drift « [Mean Span Drift*
•Absolute Value.
[Span] x 100
•t [Span] x 1C
Figure 2*
Zero and Calibration Drift (2 Hour)
155
-------
Chapter I—Environmental Protection Agency
App. B
Date Zero Span
and Zero Drift Reading
Time Reading (AZero) {After zero adjustment)
Calibration
Drift
Zero Drift « [Mean Zero Drift* + C.I. (Zero)
« [Instrument Span] x 100 « _____
Calibration Drift « [Mean Span Drift*
+ C.I. (Span)
4 [Instrument Span] x 100
Absolute value
Figure 2-5. Zero and Calibration Drift (24-hour)
Date of Test
Span Gas Concentration
Analyzer Span Setting _
_ppm
_ppm
Upscale
_seconds
_seeonds
seconds
Average upscale response .
seconds
Dovmscale
jseeonds
_seconds
seconds
Average downscale response
System average response time (slower tine) « _
^deviation from slower
system average response
_seconds
seconds.
average upscale minus average downscale
slower time
x 100X
Figure 2-6. Response Time
156
-------
APPENDIX C
GLOSSARY OF TERMS
157
-------
Abbreviations
Definitions
uBe
°C
cc
ft
ft2
ft3,
°F
Ibs
Mscfm
ppm
psig
psia
scfm
SCFH
sp.gr.
cf
Degree Baume
Temperature, degrees Centigrade
Cubic centimeter degree Fahrenheit
Feet
Square feet
Cubic feet
Temperature, degree Fahrenheit
Pounds
Thousands of standard dubic feet per minute
Parts per million by volume
Pounds per square inch gauge
Pounds per square inch absolute
Cubic feet per minute measured at standard
conditions (70°F) and 760 mm (29.22") Hg
Standard- cubic feet per hour
Specific gravity—compared to water at 60 F
CHEMICAL SYMBOLS
CH4
C02
H2°
HNO
N2°
NO
NOX
N0
Methane
Carbon dioxide
Water
Nitric acid
Ammonia
Nitrogen
Nitrous oxide (laughing gas)
Nitric oxide
Total nitrogen oxides in a mixture
Nitrogen dioxide
Nitrogen textroxide
Oxygen
158
-------
Words
Absorber
Baume (°Be)
Definitions
A stainless steel tower with bubble cap plates.
Acid strength is determined by use of a floating
instrument (hydrometer) calibrated to read °Be and
by a conversion chart. The Baume can also be
calculated if the specific gravity of the acid at
60°F is known:
°Be = 145 - 145
Catalyst
Catalytic
reduction
system
Converter
Effluent
Emission
Nitric acid (weak)
Nitrogen oxides
Tail gas
sp.gr. '
The platinum-rhodium woven wire gauze on which the
ammonia is oxidized to nitric oxide and water.
A device for reducing the emissions of nitrogen
oxides to the atmosphere by passing the gas over
a catalyst in the presence of a reducing fuel such
as natural gas, hydrogen or ammonia.
The chamber in which the ammonia is converted to
nitric oxide and water by reacting it with air over
a platinum-rh~6dium catalyst.
Waste gas stream that enters the atmosphere from
the process.
Any gas stream emitted to the atmosphere.
Thirty to seventy percent nitric acid.
A general term pertaining .to a mixture of nitric
oxide (NO) and nitrogen dioxide (NCL).
The gas leaving the nitric acid absorber.
*u.s. COVEHHMEHT PRINTING OFFICES 1985—537-002/21,507
159
-------
TECHNICAL REPORT DATA
(Please read Instructions on the reverse before completing)
1. REPORT NO.
340/1-84-013
I. RECIPIENT'S ACCESSION NO.
4. TITLE AND SUBTITLE
5. REPORT DATE
August 1984
Nitric Acid Plant Inspection Guide
6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
G. Saunders,
8. PERFORMING ORGANIZATION REPORT NO.
E. Wyatt
9. PERFORMING ORGANIZATION NAME AND ADDRESS
PEI Associates, Inc.
11499 Chester Road
Post Office Box 46100
Cincinnati, Ohio 45246-0100
10. PROGRAM ELEMENT NO.
11. CONTRACT/GRANT NO.
68-01-4147
Task No. 44
12. SPONSORING AGENCY NAME AND ADDRESS
U.S. Environmental Protection Agency
Stationary Source Compliance Division
13. TYPE OF REPORT AND PERIOD COVERED
Task Final 8/84
14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
EPA Task Manager: Kirk E. Foster, Stationary Source Compliance Division
16. ABSTRACT
This inspection guide was written and organized for use by State and local enforce-
ment field inspectors. The purpose of this guide is to aid in the development of
uniform evaluation procedures to determine compliance with NSPS requirements for
nitric acid plants. The manual describes the operating principles for nitric acid
plants and control techniques that may be used to determine compliance with
regulatory requirements.
17.
KEY WORDS AND DOCUMENT ANALYSIS
DESCRIPTORS
b.lDENTIFIERS/OPEN ENDED TERMS
c. COSATI Field/Group
Air Pollution
Nitric Acid Plants
Emissions
Air Pollution Control Equipment
Plant Inspection
Continuous Monitoring
NSPS
Inspection Procedures
Maintenance and Record-
keeping Requirements
18. DISTRIBUTION STATEMENT
Unlimited
19. SECURITY CLASS (This Report)
Unclassified
21. NO. OF PAGES
158
20. SECURITY CLASS (This page)
Unclassified
22. PRICE
EPA Form 2220-1 (Rev. 4-77) PREVIOUS EDITION is OBSOLETE
------- |