United States           Air and Radiation
                Environmental Protection  (6202 J)
                Agency
    DRAFT
February 1996
                A Guide for Methane
                Mitigation Projects

                Gas-to-Energy at Coal Mines
Emissions Overview • Identify Opportunities • Preliminary Site Assessment
Government Policies *• Next Steps *• List of Experts *• Funding Sources

-------
A Guide for Methane Mitigation Projects
          Gas-to-Energy at Coal Mines
                    DRAFT
        Editors: Dina Kruger and Karl Schultz
        U.S. Environmental Protection Agency
            Office of Air and Radiation
                 February 1996

-------
                                       ACKNOWLEDGMENTS
This report was prepared under Work Assignment 2-15 of U.S. Environmental Protection Agency Contract 68-D4-
0088 by IGF Incorporated.  The principal authors were Sonali Shah and Mary DePasquale of IGF.  The authors wish
to thank Dina Kruger and Karl Schultz of the U.S. Environmental Protection Agency for guidance and comment during
the  preparation of this document.  Mention of trade names or commercial products does not constitute endorsement
or recommendation for use.

This document is a working draft being used by Country Study Program participants to develop methane mitigation
projects.  Users of this document and those implementing methane mitigation projects are encouraged to  provide
feedback. Please direct comments to:

                                  U.S. Environmental Protection Agency
                                           Methane Branch
                                          Mail Code 6202 J
                                          401 M Street, S.W.
                                       Washington D.C. 20460
                                          Tel: 202/233-9768
                                          Fax: 202/233-9569

-------
CQALBED METHANE GUIDELINES	Table of Contents



                         TABLE OF CONTENTS

1. INTRODUCTION	1

2. OVERVIEW OF COAL MINE METHANE EMISSIONS AND EMISSIONS
REDUCTION OPPORTUNITIES	4
2.1 METHANE is A POTENT GREENHOUSE GAS	4
2.2 METHANE EMISSIONS FROM COAL MINING	5
2.3 OPPORTUNITIES TO REDUCE METHANE EMISSIONS FROM COALMINES	6
2.4 REFERENCES	9

3. IDENTIFY OPPORTUNITIES FOR REDUCING METHANE EMISSIONS	11

4. PRELIMINARY SITE ASSESSMENTS	16
4.1 GENERAL SITE INFORMATION REQUIRED	16
4.2 IDENTIFY POTENTIAL RECOVERY METHODS AND ESTIMATE GAS PRODUCTION	18
  4.2.1 Gas Production Methods	19
  4.2.2 Criteria for Selecting a Gas Production Method	24
  4.2.3 Estimate Recovery Potential	25
4.3 IDENTIFY POTENTIAL USES FOR RECOVERED METHANE	27
  4.3.1 Options for Using Coal Mine Methane	27
  4.3.2 Select Use Options for Further Analysis	30
4.4 ASSESS ECONOMIC FEASIBILITY	32
  4.4.1 Costs Analysis	33
  4.4.2 Benefits Analysis	36
4.4 REFERENCES	43

5. IDENTIFICATION AND ASSESSMENT OF KEY GOVERNMENT POLICIES	44
5.1 NATIONAL ENERGY PRICING,  SUBSIDIES, AND TAXES	44
5.2 NATIONAL ENERGY SUPPLY PRIORITIES	45
5.3 ENVIRONMENTAL GOALS	45
5.4 FINANCING	46
5.5 TECHNOLOGY DEVELOPMENT	47
5.6 CONCESSION PROCESS	47
5.7 REFERENCES	48

6. NEXT STEPS	49
6.1 Focus ON THE MOST PROMISING PROJECTS	49
6.2 AVAILABILITY OF TECHNOLOGY AND EXPERTISE	52
6.3 MOTIVATE DECISIONMAKERS	53
  6.3.1 Outreach Activities	53
  6.3.2 Demonstration Projects	55
  6.3.3 Information Clearinghouses	55
6.4 RE VIEW REGULATORY FRAMEWORK	56
  6.4.1 Evaluate Existing Regulations	58
  6.4.2 Develop Feasible Options	59
  6.4.3 Implement Options	59
6.5 OBTAIN PROJECT FUNDING	60
  6.5.1 Review  Types of Assistance Available	60
  6.5.2 Identify Funding Requirements	61
  6.5.3 Select Sources of Funding	62
6.6 REFERENCES	65

-------
Table of Contents                                                     COALBED METHANE GUIDELINES
                        APPENDIX A:  DIRECTORY OF SELECT COAL MINE METHANE RECOVERY
                        AND USE EXPERTS IN THE U.S	1

                        APPENDIX B:  DIRECTORY OF POSSIBLE FUNDING AGENCIES	1
                          International Bank of Reconstruction and Development (IBRD)	2
                          Global Environment Facility (GEF)	3
                          International Finance Corporation (IFC)	4
                          European Bank for Reconstruction and Development (EBRD)	5
                          Inter-American Development Bank (IDB)	6
                          Asian Development Bank (ADB)	7
                          African Development Bank (AfDB)	8
                          Trade Development Agency (TDA)	9
                          U. S. Agency for International Development (USAID)	  10
                          Overseas Private Investment Corporation (OPIC)	  11
                          Export-Import Bank (EXIMBANK)	  12
                          U. S. Initiative on Joint Implementation (USIJI)	  13

-------
COALBED METHANE GUIDELINES
     1.  INTRODUCTION
          THIS report  provides  guidance  for developing  programs to reduce
          methane emissions from underground coal mines  through coal mine
          methane recovery  and  use.    Methane  trapped  in  the  coal  and
     surrounding strata  is released during mining.  Because methane is a valuable
     source  of energy,  recovering  and  utilizing  coal  mine  methane  is  an
     economically attractive option for reducing greenhouse gas emissions.

     This  document is  directed  towards  program  managers  responsible  for
     developing greenhouse gas (GHG) mitigation programs in developing countries
     and countries with economies in  transition.  By  focusing on  identifying and
     evaluating opportunities  to reduce emissions,  this  report complements  the
     guidance  developed  by  the  U.S.  Country Studies Program  and materials
     available from related efforts of the U.S. Environmental Protection Agency and
     others.  Furthermore, as a guidance document for reducing  methane emissions
     from coal  mines, this report assists countries in fulfilling commitments under the
     United  Nations Framework Convention on Climate Change  (UNFCCC)  to
     implement greenhouse gas mitigation programs.

     The main  goal of this report is to provide a step-by-step method for performing
     a national assessment of the opportunities to reduce methane emissions from
     coal mining.  The  report  presents steps for identifying and evaluating gassy,
     underground  coal  mines.  Those characteristics that make gas recovery and
     utilization  technically and economically  attractive are presented.  Additionally,
     this report discusses how national policies affect the viability of coal mine
     methane  recovery  projects and identifies the  steps which may be  taken to
     encourage the development of this resource.

     The remainder of this report is organized into the following five chapters:

     2.      Overview of Coal  Mine  Methane  Emissions  and Emissions
            Reduction Opportunities:  This section  provides a  brief background
            to the topic of methane emissions and emissions reductions from coal
            mines.

     3.      Identify  Opportunities  to  Reduce  Methane  Emissions:   This
            section describes a   screening  process  by  which  the  program
            managers can  identify whether underground  coal  mines  in  their
            countries  present attractive options for reducing emissions.

     4.      Perform Preliminary  Site Assessments:  This section presents the
            process for conducting preliminary site assessments for individual
            sites or representative facilities identified as being good candidates for
            gas  recovery projects  in  Section 3.  Based on this information,  the
            program   manager can  begin  to  design  an  emissions  reduction
            strategy for this source of methane emissions.
Given the economic value of methane as
a fuel source and the potential availability
of international donor funding, coal mine
methane recovery and utilization presents
one of the most cost-effective options for
reducing methane emissions.

-------
Introduction                                                                                 COAL GUIDELINES
                                    5.      Identify and Assess  Key  Government  Policies:   This section
                                            identifies the key government policies that will promote or hinder coal
                                            mine methane recovery projects..  Based on this information, potential
                                            policy options will be assessed in the context of national priorities.

                                    6.      Next Steps: This section discusses the steps that may be taken by
                                            program  managers to further the development of  an  emissions
                                            reduction  program for underground  coal  mines.    Information  on
                                            international funding sources for coal mine methane recovery projects
                                            is presented in this section.

                                    Exhibit 1-1 summarizes how this document can be  used to meet various
                                    objectives.  The first column lists several common objectives and the second
                                    column lists the chapter to consult and key elements of that chapter

-------
COALBED  METHANE GUIDELINES
 Exhibit 1-1:  How to use this Document
                    Objective
 I WANT AN OVERVIEW OF METHANE AS A GREENHOUSE GAS
     •    What are the sources of methane emissions
          and how does  methane contribute  to the
          greenhouse effect?
                          Chapter to Consult
                          2.  Overview Of Methane Emissions And
                             Emissions Reduction Opportunities
                             2.1 Methane is a Potent Greenhouse Gas
                             2.2 Methane Emissions from Coal Mining
                             2.3 Opportunities to Reduce Methane Emissions
                                 from Coal Mines
 SHOULD I TRY TO REDUCE METHANE EMISSIONS FROM COAL
 MINES?
     •    How do I assess whether we have coal mines
          that  would  be   conducive  to  methane
          emissions reductions?
     •    What data can  I collect to identify promising
          opportunities to reduce  methane emissions
          from coal mines?
       IDENTIFY
  OPPORTUNITIES
3.  Identify Opportunities For Reducing Methane
   Emissions
   Identify Basins or Coal Regions with Gassy
   Underground Mines
   Determine the number of Large Mines
   Obtain Methane Release Information
   Determine Mine Lifetimes
   Evaluate Energy Demand
 I WANT TO ESTIMATE POTENTIAL EMISSIONS REDUCTIONS
     •    How do I estimate the emissions reduction
          from individual methane projects?
     •    How do I estimate and compare costs and
          revenues  from individual  methane recovery
          projects?
     •    How do I develop a national assessment of
          emissions reduction and energy production?
                          4.  Preliminary Site Assessments
                             4.1 General Site Information Required
                             4.2 Identify Potential Recovery Methods and
                                 Estimate Gas Production
                             4.3 Identify Potential Uses for Recovered
                                 Methane
                             4.4 Assess Economic Feasibility
 WHAT POLICIES AND REGULATIONS ARE IMPORTANT?
     •    What policies affect the economic viability of
          coal bed methane recovery projects?
     •    How can  methane  recovery  projects  help
          meet other environmental goals?
     •    What   policies  affect   the  availability  of
          financing and technology?
      POLICIES
5.  Identify And Assess Key Government
   Policies
   5.1 National Energy Pricing, Subsidies, and
       Taxes
   5.2 National Energy Supply Priorities
   5.3 Environmental Goals
   5.4 Financing
   5.5 Technology Development
   5.6 Concession Process
 WHAT CAN I Do NEXT TO FACILITATE A PROJECT?
     •    What additional studies are needed?
     •    How do I remove the barriers that are slowing
          down the process?
     •    Where can I  get funding to undertake these
          activities?
                          6.  Next Steps
                             6.1 Focus on the Most Promising Projects
                             6.2 Availability of Technology and Expertise
                             6.3 Motivate Decisionmakers
                             6.4 Review Regulatory Framework
                             6.5 Obtain Project Funding
 WHERE CAN I GET ADVICE FROM EXPERTS?
Appendix A: Directory of Select Coal Bed Methane Recovery Experts in the
U.S.
 WHAT ARE THE MAIN  FUNDING SOURCES APPLICABLE To
 COAL MINES?
Appendix B: Directory of Possible Funding Agencies

-------
                                                                           COALBED METHANE GUIDELINES
                                   2.  OVERVIEW OF COAL MINE METHANE EMISSIONS
                                   AND EMISSIONS  REDUCTION OPPORTUNITIES
                                       THIS  chapter  provides a brief background  to the topic  of  methane
                                       emissions and opportunities to reduce emissions from underground coal
                                       mines.  First, background information is provided about the atmospheric
                                   importance of methane.   Next,  methane  emissions from coal mines  is
                                   discussed.   Finally, the opportunity to reduce methane  emissions and the
                                   benefits of reducing emissions are presented.
                                   2.1  Methane is a Potent Greenhouse Gas
Because methane is a source of energy
as well as a greenhouse gas, reducing
methane emissions coal mines is eco-
nomically beneficial.
Methane (CHU) is an important greenhouse gas and a major environmental
pollutant.  Methane is also the primary component of natural gas and as such
can be a valuable energy source. Methane emissions reduction strategies offer
one of the most effective means of mitigating global warming in the near term
for the following reasons:

•      Methane (ChU) is one of the principal greenhouse gases, second
        only to carbon dioxide (CCte) in its contribution  to potential  global
        warming. In fact, methane is responsible for roughly 18 percent of the
        total contribution in 1990 of all greenhouse gases to "radiative forcing,"
        the measure used to determine the extent to which the atmosphere is
        trapping heat due to emissions of greenhouse gases.  On a kilogram
        for  kilogram basis,  methane is a more potent greenhouse gas than
        C02 (about 24.5 times greater over a 100 year time frame).

•      Methane concentrations in the atmosphere have risen  rapidly.
        Atmospheric concentrations of  methane have been increasing  at
        about 0.6 percent per year (Steele et al.  1992) and have more than
        doubled over the last two centuries (IPCC 1990).  In contrast, C02's
        atmospheric concentration is increasing at about 0.4 percent per year.

•      Reductions in  methane  emissions  will  produce  substantial
        benefits in the short-run.  Methane  has a shorter atmospheric
        lifetime than other  greenhouse  gases -- methane  lasts around 11
        years in the atmosphere, whereas C02 lasts about 120 years  (IPCC
        1992). Due to  methane's high potency and short atmospheric lifetime,
        stabilization of  methane emissions will have an immediate impact on
        mitigating potential climate change.

•      Because methane  is a source of energy as well as a greenhouse
        gas, many emissions control options have additional economic
        benefits. In many cases, methane that would otherwise be emitted to
        the atmosphere can be recovered and  utilized  or the quantity  of
        methane emitted can be significantly reduced through the use of cost-
        effective management methods.   Therefore,  emissions reduction

-------
COALBED METHANE GUIDELINES
             strategies have the potential  to be low cost, or even profitable.   For
             example,  methane recovered from coal  mines can be  used as an
             energy source.

     •       Well demonstrated technologies are commercially available for
             reducing methane emissions.   For all of the major sources of
             anthropogenic  methane  emissions  (except  rice  cultivation  and
             biomass burning), cost effective methane reduction technologies are
             commercially  available.    While  offering   substantial  emissions
             reductions and economic benefits, these technologies have not been
             implemented on  a wide scale in the U.S.  or globally  because of
             financial, informational, legal, institutional, and other barriers.

     The unique characteristics of methane emissions demonstrate the significance
     of promoting strategies to reduce the  amount of methane discharged  into the
     atmosphere.
     2.2  Methane Emissions from Coal Mining

     Methane and coal are formed together during coalification, a process in which
     vegetation is converted by biological and geological forces into coal.  Methane
     is stored within coal seams and surrounding  rock strata and is released to the
     atmosphere during mining or  through natural erosion.  Typically, significant
     quantities  of methane are  trapped  in  the  coal  and  surrounding strata of
     underground mines, while little methane is associated  with  surface-mined
     deposits.

     In underground  mines, methane is hazardous in the working areas because
     methane  is  explosive in concentrations  of five  to  fifteen  percent in  air.
     Therefore, all underground coal mines use ventilation systems.  These systems
     pump large quantities of air through the mine to dilute the methane to  safe
     levels.  In very gassy mines, however, additional degasification  techniques
     must be used  along with ventilation systems. The methane  recovered  from
     these systems is frequently vented into the atmosphere.1

     There are  two important factors that influence  the amount of  methane
     generated in coal seams:

     +      Coal Rank.  Coal is ranked by its carbon content;  coals of a higher
            rank have a higher carbon content and generally a higher  methane
            content.^
       Methane does not typically pose a hazard at surface mines, and ventilation systems
       are not used.  Methane released during the mining of surface deposits disperses in
       the atmosphere and does not reach explosive concentrations.
Underground coal mines account for 70 to
85 percent of methane emissions from the
coal fuel cycle.
       In descending order, the ranks of coal  are: Graphite,  Anthracite,  Bituminous,
       Subbituminous, and Lignite.

-------
                                                                               COALBED METHANE GUIDELINES
                                    +      Coal Depth.   Pressure, which increases with depth, tends to keep
                                            methane in coal seams and surrounding strata from migrating to the
                                            surface. Thus, within a given coal rank, deep coal seams tend to have
                                            a higher methane content than shallow ones.

                                    In 1990, the coal fuel cycle  (which includes coal  mining, transportation, and
                                    usage) emitted an estimated 24-40 teragrams (Tg) of methane.3 An additional
                                    1.3 Tg  of methane was recovered  by coal mines  and used as  an energy
                                    source.  Underground coal mines were responsible for 70 to 85 percent of all
                                    emissions, while surface mines and the transportation of coal were estimated to
                                    contribute 10 to 20 percent.  Coal combustion was estimated to contribute the
                                    remaining 5 to 10 percent (USEPA1994).
There are many opportunities to expand
the recovery and use of methane  iron
gassy underground coal mines.   The
techonolgies are well known and have
been demonstrated worldwide.
2.3  Opportunities to Reduce Methane Emissions
from Coal Mines

Methane recovery and use is technically feasible at many large and gassy coal
mines, but may require a shift in the traditional perception that coal companies
and  government  authorities  have of  mine  degasification.   Techniques for
removing methane  from  mines have been  developed primarily for  safety
reasons. Thus,  in  many cases the  recovered  methane is released  to the
atmosphere with little attention paid to the development of gas use projects.  At
mines throughout the world, however, these same techniques have been
successfully  adapted to recover methane, allowing the mines to both improve
mine safety and harness the methane for fuel.  Many additional  opportunities
exist to expand the use of these technologies and reduce worldwide emissions
of methane into the atmosphere.

There are a variety of reasons why coal mine methane projects are a good way
to reduce methane emissions.  First, individual gassy coal  mines can be large
emitters of methane.  Therefore, developing a few key projects  can result in
significant emission  reductions.   Current data  indicate  that  there  are  a
significant number of large and gassy underground mines around the world that
are good candidates for such emissions reduction projects.

Second, the  technologies for  recovering  methane  in conjunction with coal
mining have been well demonstrated and are currently  in  use throughout the
world (see Exhibit 2-1). The methane  recovered using these technologies can
be used in a variety  of ways to meet local energy needs, including: on-site use
as gas; on-site use to generate  electricity; or sale for off-site use to residential,
commercial, or industrial customers (see Exhibit 2-2).
                                      One teragram is 106 metric tons, or 1012 grams.

-------
COALBED METHANE GUIDELINES
Exhibit 2-1: Summary of
Underground Mining
Method
Vertical Wells
Gob Wells
Shorthole Horizontal
Boreholes
Longhole Horizontal
Borehole
Cross-measure
Boreholes
Methods for Recovering Methane from
Description
Drilled from the surface to the coal seam several
years in advance of mining.
Drilled from the surface to a few meters above the
coal seam just prior to mining.
Drilled from inside the mine to degasify the coal
seam.
Drilled from inside the mine to degasify the coal
seam.
Drilled from inside the mine to degasify surrounding
rock strata.
      Exhibit 2-2: Summary of Methods for Utilizing Methane from
      Underground Mines
         Method
      On-site
      Off-site
                       Description
Recovered methane can be used on site directly as gas, or can be
used to generate electricity to meet on-site mine requirements. For
example, the methane can be used in the coal preparation plant or
for space heating  or water heating.  To produce electricity, the
methane can be used to power an engine-generator.
Coal mine owners and developers can sell recovered methane to
nearby industrial,  commercial, and residential users.  The quantity
and quality of methane  produced and the local demand for the
energy will determine the distance that the gas must be transported
and how it will be  used. In some cases the methane can be sold to
the local gas distribution network. Similarly, if more electricity is
produced than is required on site, the excess electricity can be sold
to the local power grid.
     The benefits of recovering and using coal mine methane are summarized in the
     following four main areas:

     +       Economic.  There are several ways by which coal  mine methane
             recovery and  use can lead to economic benefits.   For example,
             methane  recovery  through  degasification  systems  can  reduce
             ventilation costs and improve mine productivity.  Also, the mine can
             realize cost savings by using the methane  for on-site energy needs.
             Alternatively, the methane can be sold to customers off site.  If the cost
             of recovering and using (or selling) the  gas is less than the value  of
             the energy derived, the mine will earn a profit.

     +       Energy.  Coal  mine  methane  can  be used  to meet  the  energy
             requirements of the mine and nearby areas.  The  gas can also be
             used as  a residential, commercial, or industrial fuel.  This increased
             source of domestic energy can  be especially important in  nations
             where  demand is  growing  rapidly  and  domestic  supplies  are
                                                              In   addition   to   reducing   methane
                                                              emissions,   recovering   coal   mine
                                                              methane has other important benefits:
                                                              the  gas can be  used as  an energy
                                                              source;  ventilation  requirements  are
                                                              reduced;    and  local air  quality  is
                                                              enhanced.

-------
Overview                                                                         COALBED METHANE GUIDELINES
 Exhibit 2-3:  The UN Framework Convention on Climate Change (UNFCCC)

                      The signature of the United Nations Framework Convention on Climate Change (UNFCCC) by around
                      150 countries in Rio de Janeiro in June 1992 indicated a widespread recognition that climate change is a
                      potentially major threat to the world's environment and economic development.

                      The Convention aims to stabilize greenhouse gas concentrations in the atmosphere at a level that
      -—•-M-   -^—-    would prevent dangerous  anthropogenic interference with  the climate system.  Such a level  is to be
    achieved within  a time frame sufficient to allow ecosystems to adapt naturally to climate change. The Convention calls for Annex
    I countries to take measures designed to limit emissions of carbon dioxide dioxide and other greenhouse gases, with the aim of
    returning to 1990 emissions levels by the year 2000.

    To achieve  this objective,  the Convention sets out a series of principles and general commitments.  The key principles
    incorporated in  the treaty are the precautionary principle, the common but differentiated responsibility of states (which assigns
    industrialized states the lead in combating climate change), and the importance of sustainable development. The general
    commitments, which apply to both developed and developing countries,  are to adopt national programs for mitigating climate
    change; to develop adaptation strategies; to promote the sustainable management and conservation of greenhouse gas "sinks"
    (such as forests);  to take climate change into account when setting relevant social, economic, and environmental policies; to
    cooperate in technical, scientific, and educational matters; and to promote scientific research and the exchange of information.
                                              constrained.  The increased reliance on domestic energy resources
                                              can  also  help  reduce  energy imports,  thereby improving energy
                                              security and the balance of payments.

                                              Environment. As explained above, methane is a potent greenhouse
                                              gas.   By  reducing  emissions, coal mine  methane projects fulfill  a
                                              country's commitment to the  United Nations  Framework  Convention
                                              on Climate Change (UNFCCC).   The  UNFCCC requires developed
                                              countries  (also  known  as Annex I  countries) to adopt measures to
                                              reduce greenhouse  gas emissions, with the aim of reducing to 1990
                                              emissions levels by the year 2000 (see Exhibit 2-3).

                                              Furthermore, the recovery of methane increases the supply of natural
                                              gas,  which has several advantages  over other fossil  fuels.   The
                                              displacement of coal (and to a lesser degree oil) with gas will reduce
                                              emissions of S02, NOX,  and particulates (USEPA 1986). This will lead
                                              to a cleaner local environment.
                                      ^       Safety.  At gaseous concentrations of 5 to 15 percent, methane is
                                              explosive.  Thus the buildup of methane in underground mines poses
                                              a serious safety hazard.  Increased use of degasification systems may
                                              improve safety by reducing methane levels in the mine.  Techniques
                                              for recovering methane  before mining (through use of vertical wells
                                              drilled from the  surface, for  example) can significantly reduce the
                                              amount of methane in the coal when mining occurs (USEPA, 1993).

                                      A variety of coal mine methane recovery activities are currently in place around
                                      the world.  There are  examples of profitable  projects involving gas sales and
                                      on-site use.   However, many more coal  mines can implement economically
                                      viable methane recovery  and utilization projects.  In some cases, national or
                                      local  policies  hinder these projects from being  undertaken.  Relevant policies

-------
COALBED METHANE GUIDELINES
    should be  evaluated to assess  if  they  encourage or discourage  methane
    recovery and utilization projects.  Important issues to analyze include energy
    production and pricing, environmental policy, financing issues, and technology
    transfer policies.
    2.4 References
    Crutzen, P.J. 1991.
             1991.
"Methane's Sinks and Sources" Nature No. 350.  April
     IPCC (Intergovernmental Panel on Climate Change). 1990.  Climate Change:
            The  IPCC  Scientific   Assessment.     Report  Prepared   for
            Intergovernmental Panel on Climate Change by Working Group 1.

     IPCC (Intergovernmental Panel on Climate Change).  1992.  Climate Change
            1992. The Supplementary Report to the IPCC Scientific Assessment,
            Published for the Intergovernmental Panel on Climate Change (IPCC),
            World   Meteorological  Organization/United   Nations  Environment
            Program. Cambridge University Press.  Edited by J.T. Houghton, G.J.
            Jenkins, and J.J. Ephraums.

     Steele, L.P., E.J. Dlugokencky, P.M  Lang, P.P Tans, R.C. Margin,  and  K.A.
            Masarie. 1992.   "Slowing  down of  the  global  accumulation  of
            atmospheric methane during the 1980s." Nature. Volume 358.  July
            23,1992.

     USEPA (United States Environmental Protection Agency).  1986. Supplement
            A  to  a  Compilation  of Air Pollutant Emission Factors; Volume I:
            Stationary  and Point  Sources,  U.S.  Environmental  Protection
            Agency/Office  of Air  Quality Planning and  Standards,  Research
            Triangle Park, N.C.

     USEPA (U.S. Environmental Protection Agency). 1993.  Options for Reducing
            Methane Emissions  Internationally, Volume I: Technical  Options for
            Reducing Methane Emissions, Report to the Congress, prepared by
            the Office of Air and Radiation, EPA, Washington, D.C.
     USEPA  (U.S.  Environmental  Protection Agency).    1994.    International
            Anthropogenic Methane Emissions: Estimates for 1990, Report to the
            Congress, prepared by the Office of Policy, Planning and Evaluation,
            EPA, Washington, D.C.

-------
Identify  Opportunities  for Reducing  Emissions                              COALBED  METHANE GUIDELINES
                                    3.  IDENTIFY OPPORTUNITIES FOR REDUCING  METHANE
                                    EMISSIONS

                                        THIS chapter presents a screening process for national program managers
                                        to  determine if there  are coal mines  in  their countries  that are good
                                    candidates  for  emissions reduction  projects.   This screening  of  project
                                    opportunities requires five important pieces  of information:  (1) the  location of
                                    regions or basins that are known to have gassy mines; (2) the number of large
                                    mines in those regions; (3) the amount of methane emitted from each mine;
                                    (4) the expected  lifetime of each large and gassy mine; and (5) potential uses
                                    of the recovered methane.  This information may be assembled  for all mines in
                                    the  nation, or,  in those nations with a large number of mines,  for the largest
                                    mines from each region or basin.

                                    A step-by-step approach is presented  to assess whether opportunities for the
                                    implementation of gas recovery projects exist.  Each step  in the process is  a
                                    hurdle to be crossed.  If a hurdle cannot be crossed, it is unlikely that promising
                                    emissions reduction opportunities exist. For  example, if the gassy mines in the
                                    nation  are likely to  close  in the near future, then there are no  emissions
                                    reduction opportunities and the analysis ceases.   Assuming  that there  are
                                    gassy mines, you may find that there can be no market for the  recovered  gas.
                                    In this case, gas recovery projects cannot be profitable, and emissions can only
                                    be reduced at a cost.  The analysis would only proceed if the program manager
                                    is willing to consider emissions reduction options that cost money.  In many
                                    countries, this step-by-step process is likely to identify gassy coal mines with
                                    potential for energy recovery resulting in emission reductions.

                                    The initial screening steps are as follows:

                                    1.       Identify  Basins  or  Coal  Regions   That  Contain  Gassy,
                                            Underground Mines. The first step in the screening process involves     The first step it
                                            locating  coal basins or regions that have gassy coal mines. Typically,     to  determine  \
                                            coal industry experts will be knowledgeable regarding the gassiness of     underground cc
                                            the underground coal mines in each mining region. In  the absence of
                                            specific  gas  content  information,  the presence of  degasification
                                            systems, the coal rank, or the coal depth can be used as indicators of
                                            gassiness.   If suitable coal  basins  or  regions  exist, the analysis
                                            proceeds to the next step.

                                    2.       Determine  the  Number of  Large,  Underground Mines in Each
                                            Coal Basin or Region Identified. For initial screening  purposes, coal
                                            mines producing more than 300,000 metric tons of coal  annually will
                                            be considered as potential candidates.  Coal mines of this size could
                                            generate enough methane to support  a recovery project.  It should be
                                            noted, however, that this size criterion is not absolute. Smaller coal
                                            mines potentially could support successful recovery and use projects,
                                            given a high level of methane content in the seams.

-------
            COALBED  METHANE GUIDELINES
                                                                                                                IDENTIFY
urposes, mines
cubic meters of
 ton  of  coal
d  as potential
snce of data on
idicators of gas
ised.
3.       Obtain Information on Methane Released During Coal Mining. For
        initial screening purposes, mines that emit more than 10 cubic meters
        of methane per metric ton of coal produced are considered sufficiently
        gassy  to  be regarded  as  potential candidates.   Like  the criteria
        regarding  coal production, this criterion is not absolute.  In  addition,
        while annual production data may be readily available, information on
        methane emissions may not be available without directly contacting
        individual  mine operators.   If  emissions data is unavailable,  other
        indications of gasiness may  be  used,  including   in-situ  methane
        content,  records  of  outbursts or  explosions, or use   of  mine
        degasification systems.

4.       Determine  Projected  Mine   Lifetime.    For a  project to  be
        economically viable,  the mine  should remain open  for at least five
        years.  Once again, this minimum lifetime is only an  estimation.  The
        lifetime  necessary for a project to be  economically viable will be
        specific to each mine.  Because some  nations are liberalizing and
        privatizing their energy sectors, as well  as  enacting environmental
        legislation that may affect coal  consumption,  many factors other than
        the  geology of the reserve must be  considered in estimating  the likely
        life  time of a coal mine.  If this information is not readily available, the
        remaining life span may be estimated by dividing the total remaining
        reserves by the annual production.   Examining the economic and
        geological status of  other  mines in the basin  or  region may  also
        provide some clues.

5.       Determine Use for the Recovered Methane: In nearly all cases, the
        mine will be able to use the recovered methane on-site.  Because the
        candidate mines are relatively large, they have significant energy and
        electricity  needs for the mining equipment, for  the coal  preparation
        process, and for water and space heating. In cases where the amount
        of methane recovered exceeds on-site  energy requirements  it  is
        important to determine if there are other potential energy customers in
        the  surrounding area.

There are a variety of sources from which the above data may be obtained.
These include the following:

+       Various  Government Organizations.   In many nations,  the  coal
        mines  are  owned  by  the central  or   local  governments and/or
        government ministries that  may be familiar with the mining industry
        because  they  are  involved in  energy  planning,  policymaking,  or
        regulation.  For this reason, government  entities such as  the Ministry
        of Coal, Ministry of Industry, Ministry of the Environment, Mine Safety
        Bureau, or Geologic Ministry or Institute may have  readily  available
        sources of information.

        For example,  many  countries have  a  ministry that collects  coal
        production and coal reserve data for each mine in the nation.  Also,
        one or more  government  agencies may  collect  data regarding
OPPORTUNITIES

-------
Identify  Opportunities for  Reducing  Emissions                              COALBED  METHANE GUIDELINES
                                             methane emissions and mine life time.  Alternatively, if specific data
                                             are not readily  available, industry experts may  know if mines in a
                                             particular basin  or region are known to be gassy.  The mine safety
                                             agency staff might know that mine operators in a particular  area were
                                             experiencing problems due to high methane levels and planned to
                                             expand  their  degasification  systems.    Similarly, central  planning
                                             ministry staff might be aware of likely shifts in coal production among
                                             mines or mine shutdowns resulting from government actions such as
                                             coal sector restructuring or additional environmental regulation.

                                     ^       Coal Mine Operators. If all the information is not readily available in a
                                             centralized  location,  it may be necessary to contact individual mine
                                             operators.  Data on methane emissions, in particular, may be difficult
                                             to obtain from sources other than those at the mine.  Mine operators
                                             will  almost  certainly have this information because it is needed to
                                             design and operate  their  mine ventilation system. The feasibility of
                                             contacting  individual  mine operators however, will depend on the time
                                             and resources available for conducting this screening step.

                                     •       Trade   Associations,    Energy   Institutes,    and    Research
                                             Organizations.  These entities may have some of the necessary data,
                                             and in fact, may have more data or may be more accessible than the
                                             government ministries in some cases.  Some of these organizations
                                             may  prepare  energy studies,  publish  reports,  and have  their own
                                             energy databases.

                                     ^       Coalbed  Methane Project  Developers.   Project  developers  who
                                             recover and use coal mine methane or  have done so in the past may
                                             be a good  source of information.  They may be able  to assist in
                                             obtaining the preliminary information or may be willing to share their
                                             experiences with those interested in promoting the implementation of
                                             similar projects.

                                     Using the  information from the above five steps, the initial appraisal can be
                                     performed.  Exhibit 3-1 lists the questions addressed by each of the five steps.
                                     If each of the questions listed in the exhibit can  be answered "Yes,"  there are
                                     likely to be good opportunities for reducing methane emissions through the
                                     implementation of gas recovery and use projects.

                                     Even if one or more questions cannot be answered "Yes,"  there may exist,
                                     under certain circumstances, attractive opportunities for reducing emissions.

-------
COALBED  METHANE  GUIDELINES
      Exhibit 3-1:  Initial Appraisal Results Checklist
      4.
Are there any coal regions that have underground mines?

Do any of the underground mines in the identified region(s)
produce more than 300,000 metric tons annually?

Do any of the mines in the identified region that produce more
than 300,000 metric tons annually:  1) emit more than 10 cubic
meters of methane per metric ton of coal produced; 2) employ
degasification methods; or, 3) exhibit other indications of high
methane emissions?

Do any of the mines that meet the above criteria have a life span
greater than another five years?

Do the coal mines meeting the above criteria have significant
energy requirements; OR are there energy requirements in the
surrounding area?
                                                                 Yes Q   No a
                                                                 Yes a   No a
                                                                 Yes a   No a
                                                                 Yes a   No a
                                                                 Yes a   No a
         If the answer is YES to all of the above questions, there are promising options for gas
           recovery.  Proceed to Chapter 4, where the technical and economic feasibility of
                      gas recovery at each candidate site will be evaluated.
     The following economic and social conditions would favor gas recovery from
     coal mines:
                                                                                                        IDENTIFY
                                                                                                    OPPORTUNITIES
     +      High Energy Cost. If the cost of alternative fuels -- such as oil, coal,
             and conventional  natural gas -- is high in the area surrounding the
             mine, smaller sites may be able to undertake a recovery and utilization
             project profitably.

     +      Recovery Systems Already in Place.  Some gassy mines already
             may  use  degasification systems to  recover  methane   for  safety
             reasons.  In such cases, the cost of the project would  include only the
             cost incurred to employ the recovered methane. Smaller  coal  mines
             would be potential candidates  for methane  recovery and  utilization
             projects in such cases.

     +      Energy  Shortage.   Providing  coal  mine  methane to  areas  facing
             energy shortages  offers social and economic benefits that  will not be
             apparent in  a simple financial assessment of the particular project.
             The government may undertake a gas  recovery project  to provide
             households with low cost and clean  energy, thereby improving their
             standard of living.  Indirectly, such projects also may have economic
             benefits.  In such cases, the attractiveness of a gas recovery project is
             better evaluated in terms of the social value of energy provided rather
             than on a financial cost-revenue comparison.

     Finally, it may be desirable to recover and combust methane recovered from
     coal mines even if they do not meet the criteria listed above. In particular, even
     if there is no opportunity to use the gas economically, methane emissions can
     be reduced at relatively low cost by simply collecting and flaring the gas.  Such

-------
Identify  Opportunities  for  Reducing Emissions                              COALBED  METHANE  GUIDELINES
                                    projects  may  be attractive  to  investors  in  developed countries who are
                                    identifying low-cost  options for reducing greenhouse gas emissions  through
                                    joint international  action.  There are a number of safety issues that must be
                                    addressed, however, before flaring  may be considered  a viable option.  The
                                    U.S. Environmental Protection Agency is currently examining this issue.

-------
            COALBED METHANE GUIDELINES
             ASSESSMENT
3 pre-feasibility
f at evaluating
omic feasibility
s a preliminary
d   to   allow
it data to show
 pursuing  the
                              4.  PRELIMINARY SITE ASSESSMENTS
              HIS  section  presents  guidance for conducting preliminary
              assessments  of  the  candidate  sites identified  in Sections.
              These assessments will provide a more comprehensive  and
              concrete evaluation of the attractiveness of each of the  gas
recovery opportunities.  Using site specific information,  project  development
options that are most technically appropriate and cost effective will be identified.

Some countries may not  have the technical and labor resources needed to
conduct site assessments.  Appendix  A (at the end of this document)  lists
experts  that may be contacted to conduct project feasibility assessments  and
develop gas recovery projects.   Furthermore,  Chapter 6 presents steps for
identifying and filling gaps in  the  availability of technology and  expertise
required.

In most cases,  the screening process in  Section 3 will identify several candidate
sites worthy of  this level of analysis. Under this circumstance, a preliminary site
assessment can be conducted for each site. In some cases, however, so many
sites may be considered  candidates that it may not be possible to conduct
preliminary site  assessments for each  at  this time.   In this case,  it is
recommended  that several sites with significant emissions  reduction potential
be selected for assessment.  For example, the mine with the largest estimated
emissions in each coal region or  basin  could be selected.  Alternatively, sites
could be selected to represent a range  of mine characteristics.  Based on the
results of the  analysis of these sites,  the need  for additional preliminary
assessments at additional sites can be determined.

The  preliminary site assessment examines the main factors  influencing  the
attractiveness of gas recovery projects.  Section 4.1 describes the general  site
information required.  Section 4.2 presents the various  recovery techniques
and  Section 4.3 discusses the  possible  use options.   Finally,  Section  4.4
discusses the economic feasibility of these methods.
                                                                                                           ASSESSMENT
                 4.1 General Site Information Required

                 The preliminary site assessment begins by collecting general site information.
                 which will be used to examine the following: methods for recovering methane;
                 the quantity of gas likely to be produced;  and  the potential uses for the gas
                 recovered.  For  purposes of this preliminary assessment,  the amount of gas
                 that can be  produced  will  be  estimated from  information on the amount of
                 methane  released by  the  mine  during  mining  activities.   The  following
                 information should be obtained or estimated:

                 +       Current and  Future  Coal Production.  Obtain  recent annual coal
                         production statistics from the mine (metric tons per year).  Estimate
                         the  number of years that the mine will  continue to produce coal.

-------
                                          COALBED METHANE  GUIDELINES
      Identify  whether the rate of coal  production is expected to change
      significantly in the near future.

      Degasification  System.    Identify  whether  the   mine  has  a
      degasification system (in addition  ot the ventilation system).  Section
      4.2 (below) describes various degasification  systems that may be in
      use.

      Methane Emissions. Estimate current and expected future methane
      emissions from this mining activity. Options for estimating this quantity
      include:

      1.   Ventilation  System  Emissions:   Methane  emissions from  the
          ventilation  system  equal  the  methane  concentration  in  the
          ventilation air (typicaly less than one percent) times the volume of
          ventialtion  air  (e.g., in cubic  meters  per  day).   The  mine's
          engineering  staff   generally  knows  or  can  estimate  these
          quantities.

      2.   Degasification System Emissions:  If the mine has a degasification
          system  (in  addition ot  the  ventilation system) the  methane
          emissions from  this  system must be estimated and added to the
          emissions from  the ventilation  system.   Degasification system
          emissions are highly site-specific and must be  estimated from
          individual mine  data obtained from the mine's engineering staff.
          Identify the amount  of methane emitted (e.g., in cubic meters per
          day) and the concentration of the methane in the gas flow from
          the degasification system (e.g., in percent).

      3.   In Situ Gas Content: The methane emissions from the mine can
          be approximated using the in situ gas content of the coal.  At a
          minimum the methane emissions will be equal to  the gas content
          per ton times the annual coal production in tons. In addition to
          these emissions, methane is  generally  released  from  strata
          surrounding the coal.  The emissions from the surrounding strata
          are highly  site-specific,  but may  be equal  in magnitude to  the
          emissions from  the gas in the coal itself.  The mine's engineering
          staff can normally estimate  the in situ gas content and emissions
          from surrounding strata if emissions cannot be  estimated from
          ventilation and degasification system data.

      Coal Characteristics.  The permeability of the coal will influence the
      types of gas production techniques that can be used.   Obtain from the
      mine's engineering staff whether the coal has  high or low permeability.
      Permeability of 1-2  millidarcies (md) is considered low, 3-10 md is
      medium, and permeability of over 10 md is high.4
The mine's er
has sufficient
current metha
mine.  Current
estimate poten
preliminary ass
Permeability is a measure of fluids to flow through the coal and surrounding strata.
Permeability is measured in darcies.

-------
COALBED METHANE GUIDELINES
     +       Terrain and  Land Use.  The local terrain and land use may impose
             constraints on the types of gas production techniques that can  be
             used.  Obtain a  general description of the local terrain and land use
             condition.  In particular, assess whether wells can be drilled  from the
             land surface into the coal seam being mined and its surrounding
             strata.

     +       On-site  Energy Requirements.   Estimate current  and expected
             future on-site energy requirements.  Current or potential on-site gas
             use (e.g., for coal preparation or water and space heating) may  be
             estimated in  terms of energy requirements (e.g., megaJoules (MJ) or
             BTUs required per day).  Estimate electricity usage in kiloWatt-hours
             (kWh) per day.   In addition  to the quantity of on-site energy use,
             estimate the cost of this energy.

     ^       Potential Off-site Gas Use.  If the mine is unable to use all the gas
             produced, off-site gas use options must be examined. To conduct this
             examination,  a general survey of energy-using opportunities around
             the site may be required.  At a minimum, determine whether there is a
             gas transmission/distribution system or an electric power grid in close
             proximity to the  mine.  Also, identify any large energy using  facilities
             near the mine. A more detailed survey should be conducted once it is
             clear that on-site energy requirements  are less than  the amount of
             energy produced.

     It is expected that not all the above information will be  available from all the
     relevant facilities. As much information should be obtained as  possible  within
     the time and resources available so that a reasonable overview of the mine and
     its  energy  situation can  be obtained.   If necessary, "general  usage factors"
     regarding energy requirements for the mine can be applied to provide a rough
     approximation of the likely energy demand.

     One way to obtain this information is to prepare  a survey send it to the mine.
     The mine's engineering staff should be able to provide the information relatively
     easily.  If possible,  verify the information in follow up meetings with the mine
     personnel.   Once the information is obtained, the assessment moves  to the
     next step to identify  potential gas production techniques.
ASSESSMENT
     4.2  Identify Potential  Recovery Methods and Estimate Gas
     Production
     The purpose of this step is to identify  one or more potential gas recovery
     techniques that can be  used  to  produce gas  at the mine  site.   The final
     selection  of  the preferred  technique  requires  a detailed  gas  production
     assessment that is beyond the scope  of  the  preliminary site  assessment.
     However, this step will provide a  rough indication of the  alternatives to  be

-------
Preliminary Site Assessments                                                COALBED METHANE  GUIDELINES
                                     considered  so the potential  economic  performance of the project can be
                                     examined.

                                     Each of the major gas production techniques is described in the next section.
                                     Following these descriptions,  the criteria for selecting one or more method for
                                     evaluation in the preliminary assessment are presented.
                                     4.2.1  Gas Production Methods

                                     Methods for producing gas from active coal mines include vertical wells, short
                                     horizontal  boreholes, longhole horizontal  boreholes, gob wells, and  cross-
                                     measure boreholes.  Vertical wells and gob wells are drilled from the surface to
                                     the coal seam, while the various types of boreholes are drilled from inside the
                                     mine.  Vertical wells, horizontal boreholes, and longhole horizontal boreholes
                                     recover methane in advance of mining, and typically can produce nearly pure
                                     methane gas.  Gob wells and cross measure boreholes  recover methane from
                                     areas  that have already been mined  and  consequently usually produce gas
                                     that is contaminated with mine air, so that it is not pure methane.

                                     This section describes each of the  major degasification  methods and  provides
                                     information for determining whether  a  method  might  be appropriate for a
                                     particular mine.
                                     Vertical Wells

                                     Description:  Similar in design to conventional oil and gas wells, vertical wells
                                     are  drilled from the  surface into the coal seam several years in advance of
                                     mining. In the U.S., they range from 300 to 600 meters in length, depending on
                                     the  depth  of the mine. Well spacing depends on reservoir, geological, and
                                     surface conditions.  In  the  U.S.,  well spacing can range from  one well  per
                                     8 hectares (20 acres) to one well per 65 hectares (160 acres).

                                     Vertical wells usually require hydraulic fracturing of the  coal seam to activate
                                     the flow of methane.  These wells may produce large quantities of water and
                                     small volumes of methane during the first several months of operation.  As this
                                     water is removed and the pressure in the coal seam is lowered, gas production
                                     increases. This water produced by vertical wells is the same water that would
                                     be removed when the coal is mined.  Generally, this water must be treated and
                                     disposed in a manner that is similar to the treatment and disposal performed for
                                     the water produced during mining.  Since vertical wells are operated  several
                                     years in advance of mining, the equipment for  water treatment would need to
                                     be installed and operated sooner than would be necessary if the water were
                                     handled during mining.

                                     Vertical wells typically  produce gas with a  methane  content greater than 95
                                     percent because the methane that is recovered is  not diluted with air from  the
                                     mine workings.  The total  amount of methane recovered  using vertical pre-
                                     drainage will depend on both the site specific geology  and the number of years

-------
COALBED METHANE  GUIDELINES
     the well is drilled prior to the start of mining.  Recovery of from 50 to over 70
     percent of the methane  that would otherwise  be emitted during mining
     operations is possible for operations drilling vertical degasification wells at least
     10 years in advance of mining.

     Although not widely used in the coal mining industry, vertical wells are used by
     numerous stand-alone^ operations that produce methane from coal seams for
     sale to  natural gas pipelines.  The use of this recovery method is growing in the
     U.S.  Exhibit 4-1 presents a schematic of a vertical degasification well.

     Suitability/Technical Feasibility:  Vertical wells (along with longhole horizontal
     boreholes) are the preferred recovery technique when nearly pure methane
     must be produced. Vertical wells are suitable  for mines that have access  to
     advanced  technology, can  plan  several  years in advance of mining,  have
     medium or highly permeable coal  seams, and have geological characteristics
     that permit drilling from the surface. One advantage of vertical wells is that they
     may be used in conjunction with virtually  all coal mining methods.  U.S.  coal
     mines employing this technique have  successfully recovered large amounts of
     high quality methane for sale through conventional gas pipelines.

     Vertical wells cannot be used on low permeability coals (less than 3 md), when
     surface access is  restricted,  or  when  degasification  cannot be planned  in
     advance.  In low permeability coal seams, vertical wells may not be effective
     due to  limited  methane flow through the seam.   Additionally, there is some
     concern that in certain geologic conditions the hydraulic fracturing required  to
     stimulate production from a vertical well may cause damage to the roof rock,
     which would hinder mining operations.  However, U.S. mines employing this
     technique  have shown that hydraulic fracturing can be controlled and should
     not adversely affect future mining.  Finally, due to the need to fracture the coal
     seam   in  advance  of mining,  vertical  wells require a  more advanced
     technological expertise than do some of the other methods.
ASSESSMENT
       The term "stand-alone" refers to coalbed methane operations that produce methane
       from coal seams that are not being mined. In most cases, these operations recover
       methane from deep and gassy coal seams that are not likely to be mined  in the
       foreseeable future.

-------
                                           COALBED  METHANE  GUIDELINES
 Exhibit 4-1:  Schematic of a Vertical Degasification Well
                                                      Vertical Well
                                                             n
       Mined Area
                                 Unmined Area
                                        ,Coal Seams
                                     -*-h
                         Mining Equipmer/
Short Horizontal Boreholes

Description:  Short horizontal boreholes are drilled from  inside the mine (as
opposed to from the surface) and they drain methane from the unmined areas
of the coal seam or blocked out longwall panels shortly before mining.  These
boreholes are typically 10 to 300 meters in length. Several hundred boreholes
may be drilled within a single mine and connected to an in-mine vacuum piping
system,  which transports the methane out of the mine and to the surface.  Most
often, horizontal boreholes have been used  for short-term  methane control
during mining.

Because methane drainage only occurs from the coal seam being mined  (and
not from the surrounding strata), the recovery efficiency of this technique is low
-- approximately 10 to 18 percent of methane that  would otherwise be emitted is
captured (USEPA 1990).  However, this methane is typically 95 percent  pure
methane.  (USEPA 1993a).   Exhibit  4-2  presents a schematic  of  a  short
horizontal borehole.

Suitability/Technical  Feasibility:   Horizontal boreholes recover nearly  pure
methane and therefore can be used when  high  quality gas is desired.  They
require access to advanced drilling technology and are most  successful when
the coal is relatively  permeable.   As the recovery  efficiency is quite  low,
however, other recovery  methods may be preferred  for economic reasons.
Because they drain methane prior to mining, horizontal boreholes can be used
in  conjunction with  all mining  methods.   They are difficult  to  implement,
however, when coal seams are steeply inclined.

-------
COALBED METHANE GUIDELINES
     Exhibit 4-2: Schematic of Short- and Long hole-Horizontal Boreholes
                                                                                                ASSESSMENT
     Longhole Horizontal Boreholes

     Description:   Like  horizontal  boreholes, longhole horizontal boreholes are
     drilled from inside the mine in  advance of mining.  They are greater than 300
     meters in length  and are drilled in unmined  seams using directional drilling
     techniques.  Nearly pure methane  is recovered and the recovery efficiency is
     about 50 percent.  Exhibit 4-2 presents a schematic of a longhole horizontal
     borehole.

     Suitability/Technical Feasibility: Longhole horizontal boreholes recover nearly
     pure  methane and  therefore can  be used when high  quality gas is desired.
     They  are most suitable for  mines  that have  access to advanced drilling
     technology.   They are particularly effective for  gassy, low permeability  coal
     seams that require long diffusion  periods.   As they drain methane prior  to
     mining, longhole horizontal boreholes can be used in conjunction with all mining
     methods.
     Gob Wells
     Description:   The  fractured zone caused  by  the  collapse  of  the  strata
     surrounding the coal seam in longwall and room-and-pillar mining is known as
     a "gob" area.  Following collapse of this area, a significant amount of methane
     is released.  Gob wells are drilled from the surface to a point 2 to 15 meters
     above the target seam just prior to mining.  In the U.S., they range from 300 to
     600 meters in length, depending on the  depth  of the  mine.  Although the
     spacing of gob wells varies  at each  mine, generally two to six gob wells are
     used per  longwall  panel.  As mining advances under the well, the methane-
     charged coal and strata around the well fractures. The methane emitted from
     these fractured strata flows into the gob well and up to the surface.  A vacuum

-------
                                            COALBED METHANE GUIDELINES
 Exhibit 4-3: Schematic of a Gob Well
is  pulled on the well in most cases to prevent methane from entering mine
working areas.  Exhibit 4-3 presents a schematic of a gob well.

Initially, gob  wells  produce  nearly  pure  methane.    Over time,  however,
additional  amounts  of  mine air  can  flow  into the gob area  and dilute the
methane, reducing purity to between 30 and 80 percent. In some cases, it is
possible to maintain nearly pure methane  production  from  gob wells through
careful monitoring and management.  For example, the Jim Walter Resources
mines in Alabama have been able to maintain nearly pure methane production
from their gob wells.

Methane production rates from  gob wells  can  be very high,  especially
immediately following the fracturing of the strata as mining advances under the
well. Jim Walter Resources reports that their gob wells initially produce at rates
in excess of 56,000 cubic meters per day.  Over time, production rates typically
decline until a relatively stable rate is  achieved, typically in the range of 2,800
cubic meters per day (USEPA 1990).   Depending on the number and spacing
of the wells, gob wells can recover an estimated 30 to over 50 percent of the
methane that would otherwise be emitted from the coal  mine  (USEPA 1990).

Suitability/Technical Feasibility:  Gob  wells can be used to produce  medium
quality  gas, and if the initial quality is maintained, can produce high quality gas
as well. Such wells are suitable for all  types of mining methods where gobs are
created, and for mines where wells may be drilled from the surface.  Gob wells
can be effectively used in  both  low and  high permeability seams as the coal
seam is fractured by the mining  activity.  This fracturing and breaking  of the
seam and strata releases large amounts  of methane, even in low permeability
areas.   As with the vertical  wells, it is necessary to  consider the surface
conditions when assessing the technical  feasibility of  using gob wells.  If it is
heavily populated or if the terrain from  the surface to the target seam is harsh, it
may be difficult to drill a well.  In addition, gob wells may be difficult to place in
mines  where  multiple seams have been  mined.   However, the technology
required to drill a gob well  is not as complex as that required to drill  a vertical

-------
COALBED METHANE GUIDELINES
     Exhibit 4-4: Schematic of a Cross Measure Borehole
        Mined Area
                                                      Unmined Area
                                                  Coal Seams
                                   Cross-Measure
    well.  This is because hydraulic fracturing of the coal seam in advance of mining
    is not required for gob wells.
     Cross-Measure Boreholes

     Description:  While horizontal boreholes recover methane from the target coal
     seam, cross-measure boreholes degasify the overlying and  underlying rock
     strata. These boreholes are drilled from within the mine and generally produce
     medium quality gas (similar to the gas produced by gob wells) depending on
     site specific conditions. In the U.S., these boreholes typically range from 45 to
     90 meters in length, are developed to depths ranging from 45 to 85 meters, and
     are installed 60 to 90 meters apart. Cross-measure boreholes recover up to 20
     percent of methane that would otherwise be emitted.  A schematic of a cross
     measure borehole is presented in Exhibit 4-4.

     Suitability/Technical  Feasibility:   Methane  recovered from  cross-measure
     boreholes can be used when medium quality gas is sufficient.  This method
     requires only a low level of technology, and can be used effectively in both low
     and  high permeability seams.   However,  as recovery efficiency is quite low,
     alternative production techniques may be preferred for economic reasons.

     Exhibit 4-5 summarizes the characteristics of the gas production technologies.
     As shown in the exhibit, vertical wells have the highest recovery efficiency (up
     to 70 percent) and can typically recover nearly pure methane.
     4.2.2  Criteria for Selecting a Gas Production Method
                                                                                               ASSESSMENT
     For purposes of conducting the preliminary assessment, select one or two gas
     production options for evaluation.   As mentioned  above,  when  the project
     moves  beyond the  preliminary assessment  a  detailed  gas  production

-------
Preliminary Site Assessments                                                COALBED  METHANE GUIDELINES
                                     assessment will be conducted to select the preferred gas production method.
                                     Therefore, this selection is strictly for  preliminary evaluation purposes.  The
                                     following criteria are recommended.

                                     4      Existing   Degasification  System.   If the  mine  already   has  a
                                             degasification system that  is  optimized to promote  efficient mine
                                             production, then this existing system should be the primary candidate
                                             for consideration.

                                     4      Coal Mining and Site Conditions. Select the option that is consistent
                                             with existing coal production conditions.  If the terrain and land  use
                                             activity permit it, vertical wells and gob wells would  likely be the  two
                                             options most worthy of consideration.   Both methods have  high
                                             recovery efficiencies.  Additionally, both vertical and  gob wells do not
                                             require advanced in-mine drilling technology.  Vertical wells should not
                                             be considered, however, when the coal has low permeability, or when
                                             degasification cannot take place in advance of mining.  Gob wells
                                             cannot be  used if the mining technique does not produce gob areas.

                                     4      Gas Quality Requirements.  If nearly pure methane  is required for
                                             gas use, gob wells may be less preferred. In this case, vertical wells
                                             and in-mine drilling options should be examined.  If longhole drilling
                                             can be conducted, its higher recovery rate may make it attractive.

                                     The selection of the gas production method may need to be revisited when the
                                     gas use options are examined. As discussed below, the  perferred gas use may
                                     impose constraints on gas quality and quantity.
                                     4.2.3 Estimate Recovery Potential

                                     Once the preferred gas production methods are selected, the amount of gas
                                     that  can  be produced by  each is  estimated.   If a mine  has an  existing
                                     degasification system,  gas quantity and quality are simply estimated based on
                                     the current performance of the system. This information was collected as part
                                     of the general site information (see above).   If the  mine's engineering staff
                                     expects that enhanced production is possible as  part of a recovery project,
                                     increased rates of gas  production can be considered.

-------
Exhibit 4-5: Summary of Meth
Method/Description
ods for Recovering M
Methane Quality
Bthane from U
Recovery
Efficiency3
iderground Mining
Applicability
Possible Utilization Options
Vertical Wells
Drilled from the surface to the
coal seam several years in
advance of mining.
Recovers nearly pure
methane.
up to 70%
May be used with all mine types where the terrain
permits drilling from the surface; not suited for low-
permeability seams.
All use options; preferred method for use options
requiring nearly pure methane.
Gob Wells
Drilled from the surface to a few
meters above the coal seam just
prior to mining.
Recovers medium
quality gas: methane
mixed with mine air.
Quality can vary over
time.
up to 50%
Can be used with all mining methods that create
gob areas; can be used in low and high
permeability seams; the terrain must allow for
surface drilling.
Some mines may be able to recover nearly pure
methane from gob wells. In such cases, the use
options would be the same as for vertical wells.
When recovery of high quality methane is not
feasible, gas use would be limited to power
generation and other options that can use medium
quality gas.
Short Horizontal Boreholes
Drilled from inside the mine to
degasify the coal seam.
Recovers nearly pure
methane.
up to 20%
Can be used with all mining methods; may not be
suited for low-permeability or steeply inclined
seams; best when used in conjunction with other
degasification techniques.
Same as vertical wells, though recovery efficiency
is low, so may need to be used in conjunction with
another method.
Longhole Horizontal
Drilled from inside the mine in
advance of mining.
Recovers nearly pure
methane.
up to 50%
Can be used with all mining methods; effective in
low and high permeability seams.
Same as for vertical wells.
Cross-measure Boreholes:
Drilled from inside the mine to
degasify surrounding rock strata.
Recovers medium
quality gas: methane
mixed with mine air.
Quality can vary over
time.
up to 20%
Can be used with all mining methods that create
gob areas; can be used in low and high
permeability seams; best when used in conjunction
with other degasification methods.
Gas use options are limited to power generation
and other options that can use medium quality
gas. May need to be used in conjunction with
another method as recovery efficiency is low.
Sources: USEPA 1993a,b.
a Percent of methane recovered that would otherwise be emitted.

-------
                                                               COALBED  METHANE GUIDELINES
                    If there is no degasification system in place, the amount of methane that may
                    be  recovered from  a  new system  can  be estimated by multiplying methane
                    emissions  from  the ventilation system  by the recovery efficiency listed  in
                    Exhibit 4-5.  The emissions from the ventilation system were etimated as part of
                    the general site  information.  For example, if a mine emits 600 million cubic
                    meters of  methane annually from its  ventilation  system,  gob wells, which
                    recover up  to fifty  percent of the  methane  emitted, should be expected  to
                    produce up to 300  million cubic meters of methane annually.  Alternatively,
                    vertical wells would produce up to 420 million cubic meters (70 percent  of
                    emissions).   Actual  gas production will vary with site conditions and system
                    operation.

                    Exhibit 4-5 also lists the quality of the gas likely  to be produced by each of the
                    methods.  For example, the gob wells would likley produce medium quality gas,
                    whereas vertical wells  can produce high quality gas (nearly pure methane).
                    4.3  Identify Potential Uses for Recovered  Methane

                    Methane recovered from coal mines can be used in a variety of applications.  In
                    general, any equipment that  can use natural gas as  a fuel source can be
                    operated  using coal mine  methane.  Additionally,  coal mine methane can
                    substitue  for oil and coal in many applications.  The preferred methane use
                    option at  each mine will depend  on  a variety of factors including the quantity
                    and quality of the methane recovered and local energy  needs. First, the main
                    use options are described.  Then, a process for selecting which  options  to
                    consider in the preliminary assessment is presented.
                    4.3.1  Options for Using Coal Mine Methane
                    The easiest and often least costly option for using coal mine methane is to use
                    the gas to fuel equipment at the mine.  Both high quality and medium quality
                    gas (methane mixed with air) can  be used in a variety of on-site applications,
                    including:

                    +       Coal Preparation Plants.   Coal preparation involves cleaning and
                            drying the coal.  Coal mine methane can fuel the thermal dryers that
                            heat the air used to remove surface moisture from the coal. Although
                            coal is typically used to fuel the  coal drying  process,  the equipment
                            can be converted to use gas.  The coal that would have been used to
                            fuel the thermal dryer can  then be made available for sale.

                    +       Mine Boilers. Recovered methane can be used in boilers for space
                            and water heating.  For example, some mines may have bath houses
                            or dormitories that require hot water.  Also, in some regions, it may be
                            necessary to heat the ventilation  air in the winter before it is pumped
                            into the mine.  In the Donetsk Basin in Ukraine, a small  amount of coal
                            mine methane is used in mine boilers.
In the Rybnik a
Silesian Basin it
use recovered
drying plants as
/looses.  CONS
Virginia (USA) h
coal in its prepar
with coal mine rr
•O-

-------
COALBED METHANE  GUIDELINES
     ^       Cooking.  Mines that have kitchens can use the recovered methane
             for cooking purposes.

     ^       Water  Treatment.  Coal  mine methane can  be used  to  fuel the
             process of treating water recovered during mining.  A demonstration
             project  is underway at the Morcinek mine in Poland that involves using
             the methane for this purpose.  Once the water is treated, it will be used
             for agricultural purposes.

     The advantages of using coal  mine methane in these  uses on-site include:
     (1) the gas does not need to be tranported over a long distance; (2) gas quality
     need only be maintained at the level required for the on-site equipment; and
     (3) purchase agreements or other  sales arrangements do not need  to  be
     negotiated.  Additionally, experience indicates that only minimal  conversion of
     existing equipment is needed to convert from other fuels to coal mine methane.

     An  alternative  to using the  gas on  site  in  heating, drying,  and  related
     applications is to use the gas to produce electricity.  The electricity can be used
     on site or, as discussed below, sold off site.

     Gas turbines, internal combustion (1C) engines,  and boiler/steam turbines can
     each be adapted to generate electricity from coal mine methane.  However, the
     most likely choice of a prime mover for a coal mine methane project would be a
     gas turbine.  Boiler/steam turbines are generally not  cost effective in the size
     range typically  encountered with coal mine methane  projects (e.g.,  below
     30 MW), and 1C engines are more sensitive to variations in fuel heating values
     than are gas turbines.  Furthermore, gas  turbines are smaller and  lighter than
     1C engines and historically have had lower operation and maintenance costs. A
     methane/air mixture with a  heating value  of at least 13,000 kJ/m3 is a suitable
     fuel for each of  the prime mover options. All of the gas production methods
     discussed above, including gob wells, can produce gas of this quality, which is
     the equivalent of about 35 percent methane in air.

     Generating  electricity is an attractive  option because most coal mines  have
     significant electricity loads.   Electricity is  required to run nearly every piece of
     equipment including mining machines,  conveyor belts, desalination  plants, coal
     preparation  plants, and  ventilation fans.  Ventilation systems in  particular
     require large amounts of electricity because they run 24 hours a day, every day
     of the year.  In the U.S., about 24 kWh of  electricity are required per ton of coal
     extracted from the mine and 6 kWh are required per ton of coal processed in
     the  coal preparation plant.   Several  small  power  generation projects are
     operating at coal mines  in  China, the  Czech  Republic, Poland, Australia,
     England, and Germany (Sturgill  1991).

     The viability of producing electricity from coal mine methane may be limited,
     however, if the  amount  and  consistency of  the gas  produced varies
     considerably from day to day. For example, some gob wells are not predictable
     with respect to length of production, methane concentration, and rate of flow.
     Equipment  to blend the air and methane  may be  needed to ensure that
     variations in heat content  remain within  an acceptable range for the prime
ASSESSMENT

-------
                                                                                 COALBED  METHANE GUIDELINES
If the opportunity to use gas on site is
similar  to the level of estimated gas
production, direct on-site use will likely
be  the  preferred  use  option  for
subsequent evaluation.
mover.  A supplemental  gas source may  be desired, and a reliable back-up
power source may  be required to guard against potential gas production or
equipment problems.

In the event that electricity generating  potential exceeds on-site needs, the
excess  electricity can be  sold  to  the  local power grid.   Because on-site
electricity requirements vary  by time of day and day of week depending on
mining activity, the availability of excess  electricity for sale may  be intermittent.
Arrangements will  be required  with  the  local  power  authority to sell the
electricity into the system.

If on-site use and electricity generation are not feasible, the gas can be sold to
customers  off site.   The  most  attractive off-site  sales option  is  to  a gas
transmission or distribution system in close proximity to the mine.  To be viable,
the coal mine methane must be processed  to meet the specifications  of the
pipeline receiving  the gas.   For  most coal mine methane,  the  principal
contaminants are water and sand, which can be easily removed. After being
processed,  compressors are used  to pressurize the gas to the appropriate
pressure for injection into the pipeline.

In most regions,  conventional gas pipelines carry  high quality gas, which would
be the equivalent of nearly pure methane.  Therefore, to sell gas to this type of
pipeline, the coal mine methane  recovery system would need to be designed
and operated in a manner to produce this high quality gas. If lower quality gas
were produced it would need to be enriched.  However, enrichment is often too
costly to be economically viable.

In some areas,  medium quality  gas is  distributed through pipelines.   These
pipelines are typically separate from the pipelines that distribute conventional
gas, depending  on  the local  pipeline quality standards.  Because coke oven
gas and methane recovered from coal mines can have similar heating values,
in some cases  medium  quality  coal mine methane can be transported via
existing coke oven gas pipelines. If  a medium quality gas pipeline is available,
the constraints on gas quality produced at the mine are reduced.

To be economical,  the pipeline receiving the coal  mine methane must be in
reasonably close proximity to the mine. Building and operating a pipeline solely
to carry the  coal mine methane can be costly, and consequently the transport
distance should  be  minimized.  If no suitable pipelines are in proximity  to the
mine, alternative gas uses near the mine  must be identified.

As described above, coal mine methane can  be used to fuel nearly all types of
equipment that use  natural  gas. Additionally, the gas can be substituted for oil
or coal in many applications.  Therefore,  industrial, commercial,  institutional, or
household energy requirements  near the  mine can  be met using coal mine
methane. The principal limitation to using the gas in these sectors is the cost of
transporting the gas to its point of use.

Coal mine methane can also be used as a feedstock in chemical production.
Methane is  a feedstock in several important  chemical processes, such  as the
                                                                                                                 In the  United
                                                                                                                 Resources  is
                                                                                                                 methane recov-
                                                                                                                 Alabama  to  a
                                                                                                                 company.   Th<
                                                                                                                 same basis  at
                                                                                                                 gas,  and in 15
                                                                                                                 approximately '•.

-------
COALBED METHANE GUIDELINES
     synthesis of ammonia, methanol, and acetic acid. Using high quality gas as a
     chemical feedstock  may  be attractive  for gassy  mines  in  countries with
     substantial  domestic petrochemical markets. Alternatively, high quality methane
     from several small mines could be collected at  a central location in order to
     meet the volume required by the chemical plant.  Currently, in Poland's Upper
     Silesian  Basin, a  small  amount of  coal  mine  methane is  being  used  as
     feedstock for a chemical plant.

     Exhibit 4-6  summarizes the characteristics of these gas use options.
ASSESSMENT
     4.3.2  Select Use Options for Further Analysis

     For purposes of conducting the preliminary assessment, each of the major gas
     use  options  should  be examined.   When  the  project  moves  beyond the
     preliminary assessment a  detailed gas use  assessment will be conducted to
     select the preferred option..The following options are recommended.

     ^       On-site Use. Compare the on-site energy requirements (estimated as
             part of the general site information) to the amount of gas anticipated to
             be produced. If the opportunity to use gas on site is similar to the level
             of estimated gas production,  direct on-site use  will likely be the
             preferred use option for subsequent evaluation.  If the  potential for
             direct  on-site gas use  is  much   less  than  the anticipated gas
             production, an alternative use option should be identified.

             It is recommended that the estimated gas production be compared to
             on-site gas needs on an energy basis.  The energy content of the gas
             is estimated from its methane content.  Pure methane has a heating
             value of approximately 37 million Joules per cubic meter (MJ/m3) at
             standard temperature and pressure.  Gas that is 50 percent methane,
             for example,  will have a heating value of 50 percent that amount, or
             about 18.5 MJ/m3.

     ^       Electricity Generation.  If on-site  gas use is not feasible, or if the
             amount of  gas produced greatly exceeds on-site needs, electricity
             production  may  be an  attractive  option.  Compare  the on-site
             electricity  requirements  (estimated as  part  of  the  general site
             information) to the amount of electricity that can be generated from the
             gas anticipated to be produced.  The amount of electricity that can  be
             generated from the methane  may  be  estimated using the following
             formula:
                              Electricity Generated (kWh) =
                  [Gas Recovered (m3) x Heating Value of the Gas (MJ/m3)] /
                              Generator Heat Rate (MJ/kWh)

-------
                                    COALBED  METHANE GUIDELINES
The  generator  heat  rate  varies  somewhat  among  generation
technologies, but can be assumed to be about 11.6 MJ/kWh, which is
appropriate for combustion turbines.

Using  these  values, an  example  calculation of  potential  electricity
production  is as follows.   Assume that  200,000 m3/day of gas  is
produced that is 50 percent methane.  The heating value of the gas is
18.5 MJ/m3.   The total electricity that can be produced is therefore:
200,000 m3/day x 18.5 M J/m3 /11.6 MJ/kWh = 318,965 kWh/day.  The
generator capacity is this  value  divided by  24 hours,  or about
13,300 kW, or 13.31
If  on-site  requirements  are  much less  than  potential  electricity
production, then off-site  electricity  sales may be  required to make
electricity production economically feasible.  Such  off-site sales may
be less attractive than off-site gas sales, discussed next.  Also,  a
combined gas use/electricity production approach can be examined in
which a  portion of the gas is used directly or sold, and  a portion is
used to produce electricity.

Off-site  Gas Sales.    Generally,  off-site  gas  sales  should  be
considered when the above on-site use options are not attractive.
Some site-specific conditions, however,  may  make off-site gas sales
the most attractive gas use option.  In particular, if an off-site customer
in  close  proximity to  the mine can use the  gas without costly  gas
enrichment or processing, this option will be  attractive.   Off-site gas
                                                  sales can also
                                                  be   examined
                                                  in combination
                                                  with    on-site
                                                  use.
                                                  To assess the
                                                  off-site     gas
                                                  sales option, a
                                                  brief survey of
                                                  potential   gas
                                                  use in the area
                                                  around     the
                                                  mine        is
                                                  warranted.
Exhibit 4-6: Summ
Option
Direct use on-site
On-site electricity
generation
Sale into an
Existing Gas
Distribution or
Transmission
System
Sale directly to an
industrial,
residential, or
commercial user
Chemical Feedstock
aryof Coal Mine Mi
Min. Quality
Necessary
Medium
Medium
High
Medium
Medium
High
jthane Use Options
Applicability
Suitable for most mines, can be used
to fuel coal preparation plants, heat
space and water, and treat water
Most suitable for mines with large
electricity needs, especially those
which already produce their own
electricity.
Most suitable for mines using
premining degasification and located
near existing high quality gas
pipelines.
Most suitable for mines located near
medium quality pipelines.
Suitable for mines located near
industrial or commercial facilities, or
near residential areas.
Most suitable for very gassy mines
using degasification techniques that
recover nearly pure methane and are
located near chemical plants.
                                                   Identify
                                                   location
                                                   existing
                                                   pipelines
                                                   well
                                                   potential
                                                   industrial,
                                                   commercial, or
                                                   residential
the
  of
gas
 as
 as
        If an off-site cu.
        to the mine a
        costly gas enric
        use option will L

-------
            COALBED  METHANE GUIDELINES
• to be required,
and gas sales
as  part of the
it
        customers. The distance to these potential gas customers should be
        determined because distance is one of the key driving factors of the
        cost of supplying gas to them.

The choice between off-site electricity sales and off-site gas sales will depend
on site-specific conditions. The advantage of off-site electricity sales is that the
gas quality need only be maintained at the level required for the on-site electric
power  generator  system.   If only medium  quality  gas  is  produced,  this
advantage can be important.  The disadvantages are that an electric power grid
must be near by, and a power sales agreement must be negotiated. The price
at which the electricity can be sold will determine the economic feasibility of this
approach.

The advantage of off-site gas sales is that if a customer is near by, the cost of
producing and transporting the gas can be quite low.   However, if the gas
customer needs high quality  gas and only medium quality gas is produced by
the mine, the enrichment cost may make the project uneconomical. Given the
site-specific  nature of the choice between  these  off-site sales  options,  it is
recommended  that if off-site  sales appear to be required, that both electricity
sales and gas sales  be evaluated as part of the preliminary assessment.  If
either or both of the options  appears promising based on the preliminary
assessment results, they can  both be  evaluated  in subsequent site-specific
studies.
                                                                                                             ASSESSMENT
                 4.4  Assess Economic Feasibility

                 The purpose of evaluating the economic feasibility of the project options is to
                 ensure that the project meets a target level of cost effectiveness.  There may be
                 several  goals of  a gas  recovery  project:  profitability;  energy supply;   or
                 emissions reductions (or a combination of the three).  If only profitable projects
                 are to be considered, then revenues must exceed costs.  If a net cost can be
                 incurred to reduce methane emissions and meet other environmental goals, the
                 threshold may be set in terms of cost per ton  of emissions (e.g., $2/ton of C02
                 equivalent emissions avoided). Alternatively, if the goal of the project is to meet
                 national or local energy demands, the threshold may be set in terms of cost per
                 unit of energy supplied (e.g., $0.07/kWh).  Regardless of the objective, the
                 capital and operating  costs  of the project must be  estimated  and  balanced
                 against the estimated revenues and other benefits.

                 Information from all parties  potentially  involved in  the gas recovery project
                 should be  considered  at  this stage  of the  assessment, including potential
                 energy users, the facility owner or operator, and equipment suppliers. If energy
                 production or prices are regulated, information from the appropriate ministries
                 should be obtained as well to help assess potential costs and revenues.  First,
                 the cost analysis is presented, followed by the benefits analysis, which includes
                 a discussion of how to compare the costs and  benefits  to assess economic
                 feasibility.

-------
Preliminary Site Assessments                                                 COALBED METHANE  GUIDELINES
                                     It should be noted that labor and equipment costs can vary significantly among
                                     countries and regions within countries. The dollar cost estimates presented in
                                     this section represent U.S. prices.  Potential additional transportation costs or
                                     tariffs are not reflected.  Additionally, operating and maintenance costs include
                                     labor charges, which can vary significantly.  Adjustments to local currencies
                                     and cost conditions should be attempted whenever possible.
                                     4.4.1 Costs Analysis

                                     Costs of recovering and using coal mine methane are highly dependent on the
                                     amount of gas  involved,  the specific technologies used, and  site-specific
                                     factors.  The cost estimates developed as part of this preliminary  assessment
                                     will be compared to revenue  (or cost savings) estimates to make a rough
                                     assessment of the economic viability of the project alternatives.  If one or more
                                     alternative project configurations looks promising, more detailed cost estimates
                                     will be conducted as part of subsequent more detailed studies. Therefore, the
                                     cost estimates prepared here are solely for preliminary assessment purposes.

                                     As with all  project evaluations, both capital  costs and  annual operating costs
                                     will be  considered.   To estimate these costs,  a  listing  of each  piece  of
                                     equipment required must first be prepared. Exhibit 4-7 lists the major pieces of
                                     equipment required for the project configurations that may be considered.  As
                                     shown in the exhibit,  three main  systems are required for all  projects:   the
                                     degasification system; the gas collection and gathering system; and the gas
                                     processing system.  If the mine already has one or more of these systems, and
                                     does  not plan modifications for this project, then the costs for  the existing
                                     components may be excluded.  For example, some mines will already have a
                                     degasification system in place  and operating.

                                     The pieces of equipment required for on-site gas use, electricity production,
                                     and off-site gas use are also listed.  Gas enrichment equipment is listed  for off-
                                     site gas sales, but will only be required when  the gas quality must be enhanced.

                                     In addition to the costs for these pieces of equipment, additional costs that must
                                     be considered include:

                                     +      System Design.  The costs of the system design and construction
                                             management may be on the order of 15 percent  of the  total  capital
                                             cost for the project.

                                     ^      Legal.  Siting, permitting,  and land use requirements must be  met.
                                             These costs, which can be substantial, include the costs  of obtaining
                                             necessary permits and  licenses, and potentially  installing pollution
                                             control equipment.

                                     ^      Financing. Financing costs include the cost for obtaining  financing as
                                             well  as interest  payments.   These costs depend on the financing
                                             method and project specific factors.

-------
COALBED METHANE  GUIDELINES
     ^       Rights-of-Way.  Costs of obtaining rights-of-way to run pipelines or
             power lines must be considered and may be substantial.

     Experience in the U.S. indicates that these additional non-equipment costs can
     be substantial.  However, due to their site-specific nature, general cost factors
     cannot be provided to estimate each type of cost.

     Given this approach, the equipment capital and operating costs are the primary
     costs  estimated in  the preliminary assessment.   Exhibit 4-8 provides cost
     coefficients for  the main pieces of equipment required.  It must be noted, that
     costs will vary  significantly among projects and among countries. The costs
     presented here are based on  U.S.  experiences and  technologies and  are
     presented in U.S. dollars.

     To estimate project costs, perform the following:

             1.   Define the project configuration  in terms  of the gas production
                 system and gas use option.

             2.   Identify  the  pieces  of  equipment  required  for  the project
                 configuration.  Do not include equipment  that the  mine already
                 has in  place  (e.g.,  if the mine  has an existing degasification
                 system).

             3.   Select a project lifetime, for example between 10 and 20 years.
                 The sensitivity of the costs and benefits to the project lifetime can
                 be examined.

             4.   Estimate the  average annual amount of coal mined  (in tons)
                 during the life of the project.
ASSESSMENT

-------
                                            COALBED  METHANE GUIDELINES
        5.  Estimate the average daily total gas production during the life of
            the project (cubic meters per day).

        6.  If off-site gas sales are anticipated, estimate the distance to the
            point of sale (in meters).

        7.  Using the cost coefficients in Exhibit 4-8, estimate the capital and
            operating costs for the system components required.

        8.  Summarize the estimated costs to show one-time capital costs in
            yearl,   and   recurring  capital   costs  and   operation   and
            maintenance costs in each year of the project.  Add a percentage
            of the one-time capital costs (e.g.,  20 percent) to account for
            system design and other costs.

For example, to estimate the costs for gob wells, the  annual  average coal
production (tons per year) is used to estimate the number of wells required per
year.  The cost  per well ($25,000 to $50,000) is  multiplied  by the number of
wells  required per year to estimate the  annually  recurring  cost of installing
these wells.

If vertical wells are planned instead of gob wells, the number of wells required is
estimated using  the total planned coal  production over the  life of the  project.
The cost per well is then used to estimate the total one-time capital costs for
these wells,  which is incurred at the start of the project.   Unlike the other gas
recovery wells which are drilled  throughout the life of the project as the coal is
mined, all the vertical wells are typically drilled at the beginning of the project.
The other cost components are  estimated in a  similar manner.  Compressor
Exhibit 4-7: Summary o
System Component
Degasification System
(Required for all options)
Gas Collection and
Gathering System
(Required for all options)
Gas Processing System
(Required for all options)
On-site Gas Use System
Electric Power Generation
System
Off-site Gas Sales System
: Major Pieces of Equipmen
Purpose
Withdraw the gas from the
coal and and/or surrounding
strata.
Collect the gas from the
withdrawal wells to a central
point for use or sale.
Remove water and
impurities from the gas.
Convert on-site equipment
for direct gas use.
Produce electricity from the
recovered coal mine
methane.
Prepare and transport gas to
an off-site customer.
t Required
Equipment Required
• Withdrawal wells (vertical; gob; or in-mine)
• Water treatment and disposal equipment
(required only for vertical wells)
• Wellhead exhauster/blower
• Wellhead and satellite compressors to move the
gas to the central collection point
• Gathering line
• Wellhead separator
• Dehydrator
• Preparation plant conversion equipment
• Gas turbine
• Utility interconnect
• Gas enrichment equipment
• Sales compressor
• Sales meter and gas analyzer
• Transmission pipeline

-------
COALBED METHANE  GUIDELINES
     requirements, for  example, are estimated based on  the  horsepower  (HP)
     required per million cubic meters of gas production per day and  the cost per
     HP. Gathering line costs are estimated based on distance estimates.

     It should be emphasized that the cost ranges are representative of conditions
     found in the U.S.  For an  initial evaluation, values in the middle of the ranges
     presented may be used.  However, if possible, site-specific conditions should
     be  considered in selecting values from the ranges.  Particularly important site-
     specific factors may include well depths, water treatment requirements (vertical
     wells only),  gathering  line distances,  gas  enrichment requirements,  and
     equipment conversion costs.
ASSESSMENT
     4.4.2 Benefits Analysis

     The goals of a gas recovery project may be several - profits from revenues or
     cost savings, energy supply, and/or emissions reductions. The benefits of gas
     recovery will  be  evaluated  in  terms of  these project goals.   The  benefits
     analyzed in this section include: revenues generated from the utilization of the
     gas; energy supplied; and methane emissions avoided.
     Revenues/Savings

     The revenue from the project is estimated as the amount of energy (gas or
     electricity) produced  multiplied by its price.  If the  energy is used to offset on-
     site energy costs (e.g., coal, natural gas, oil, electricity), the value of this offset
     is counted as revenue to the facility. If the energy is sold, the revenue is the
     quantity sold times the price. Tax credits or other government incentives may
     supplement these revenues.

     The value of the energy will vary according to local energy prices.  These
     prices may be negotiated with individual suppliers or customers, or may be set
     by national or state policy.  Important factors affecting energy prices include the
     price of competing sources of energy, supply reliability, energy subsidies and
     taxes, and the quantity purchased.

     The revenue or savings resulting from each project must be estimated using
     local information obtained from electricity/energy authorities. A brief description
     of how these values may be estimated is as follows.

     +      On-Site Use.  The savings associated  with  the use  of coal mine
            methane on-site are estimated using  the cost of the fuel displaced, or
            the value of the coal that otherwise  would have been used.  These
            values should be estimated from on-site energy consumption records.

-------
Exhibit 4-8: Gas Recovery and Utilization Cost Factors
   System Component/
   Equipment Required
                                      Number or Size of Units Needed
                Cost Per Unit
                  Comments
Degasification System (Cost to drill, install, and complete wells and boreholes)
Gob Wells
                                 1 well for every 200,000 to 500,000 tons of coal mined
                                 each year.  This estimate was derived by assuming
                                 that approximately 1 million tons would be mined per
                                 longwall panel  and that from 2 to 5 wells would  be
                                 drilled  per  panel.    More  accurate  data  can  be
                                 substituted if more detailed information  is available
                                 regarding longwall panel sizes and well spacing.
                                 1  well for every  250,000 to  1,000,000  tons of coal
                                 mined over the life of the project. This estimate was
                                 developed assuming well spacing of from  20  to  80
                                 acres.
$25,000  to  $50,000  per  well.   This  estimate
assumes that drilling costs are roughly $90 to $140
per meter of well depth.
Cost for drilling  gob wells  is an  annual  capital  cost
(incurred each year).  The  rate of advance of mining
dictates when gob wells are drilled.
Pre-mining Vertical Wells
$100,000 to $500,000 per well
Cost per well  includes cost of hydraulic fracturing  of
coal seam to stimulate gas production.  Cost for drilling
vertical wells is a one-time capital cost. Total number
of wells required over  project lifetime may be drilled
during first year so that individual wells can produce
gas for as long as possible before being mined through.
However,  if up-front capital is limited, well  drilling can
be spread out throughout the life of the project.	
Longhole Horizontal Boreholes
                                 1  longhole borehole drilled  each year per 1 million
                                 tons  of coal  (approximately 1 borehole  per longwall
                                 panel).  Typical length of longhole borehole may  be
                                 1200 meters.
$60,000  to $100,000 per 1  million  tons  of  coal
(approximately   1 longwall   panel).     Estimate
assumes borehole length of approximately  1200
meters and drilling cost of $50 to $80 per meter.
Drilling  longhole  horizontal  boreholes  is  an annual
capital  cost  (incurred  each  year).  Rate of drilling
longhole horizontal  boreholes  determined  by rate  of
advance of mining.	
Shorthole Horizontal Boreholes
                                 4,500  meters  of borehole drilled each year  per
                                 1 million tons of coal (approximately 1 longwall panel).
                                 Shorthole    horizontal    boreholes    are   drilled
                                 perpendicular to  the longwall  panel.  This estimate
                                 assumes 30 boreholes are drilled into  the  longwall
                                 panel  and that each  borehole is  150 meters long.
                                 Given  that  a typical  longwall panel  is about 1800
                                 meters long, boreholes would be  spaced every  60
                                 meters.
$30 to $50 per meter or $135,000 to $225,000 per 1
million   tons  of  coal  (approximately   1 longwall
panel).
Drilling shorthole  horizontal  boreholes is  an annual
capital cost (incurred each  year).   Rate  of drilling
shorthole  horizontal boreholes is determined by  the
rate of advance of mining.
Capital Cost for Water Disposal
Costs for Vertical Pre-Mining
Degasification Wells
                                 1 disposal system needed per project.
Range:  $100,000 to $2,800,000. Capital costs vary
substantially  depending  on  local  environmental
conditions and disposal requirements. The low end
of the range of capital costs is for a simple aeration
system with discharge to surface water, which may
be used for relatively low volumes in some  areas.
The higher end cost represents deep-well injection,
which may be required in some areas.
Cost for a water disposal system are a one-time capital
cost.  Note that a coal seam is dewatered as part of the
normal mining process.  Accordingly, the same water
produced from pre-mining degasification  wells would
otherwise have been removed as part of the  normal
mining process. Therefore, unless  there is significant
recharging of the water table during the time between
well drilling and mining, costs for water disposal should
not be considered  as  an incremental cost associated
with a degasification project.  However, costs would be
incurred at the time of well drilling, as opposed to at the
time of mining.	

-------
Exhibit 4-8: Gas Recovery
System Component/
Equipment Required
Operating Cost for Water
Disposal for Vertical Pre-Mining
Degasification Wells
and Utilization Cost Factors
Number or Size of Units Needed
Water production might range from 17 to 70 barrels
per thousand cubic meters of gas produced. Water
production will be highly site specific. Water
production is significantly higher during the first years
of production.
Cost Per Unit
Annual operating costs for water disposal range
from $0.02/barrel to nearly $2/barrel. The lower
operating cost is typical for a simplified aeration
system, while the higher operating cost is typical for
a system requiring transport to an off-site disposal
location.
Comments

Gas Collection and Gathering System Costs
Wellhead exhauster/blowers for
gob wells
Wellhead and satellite
compressors for all degasification
systems.
Gathering Lines from Satellite
Compressors to Central
Collection Point
Gathering Lines for Gob Well
System: Lines from the wells to
the Satellite Compressor
Gathering Lines for Pre-Mining
Vertical Well Degasification
System: Lines from the wells to
the Satellite Compressor
Gathering Lines for In-mine
Borehole Systems: Lines from
the wells to the Satellite
Compressor
1 blower per maximum number of gob wells drilled in
a year. Number of gob wells drilled annually
estimated above based on annual coal production.
14,000 to 25,000 HP per million cubic meters per day
of total gas production (maximum projected daily gas
production).
6,000 to 25,000 meters of gathering line, depending
on overall size of project and whether there is more
than one gob field.
Movable Lines from Gob Wells to Satellite
Compressors: 2,500 meters per 1 million tons of coal
mined annually (assuming a typical longwall panel
may contain 1 million tons of coal).
Lines from Wells to Satellite Compressors: 3,000
meters per well.
Underground Lines: 2,500 meters per 1 million tons
of coal mined (assuming a typical longwall panel may
contain 1 million tons of coal).
$20,000 per gob well.
$650/HP
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
Average: $26/meter. Ranges from $13/meter to
$46/meter, depending on whether line is buried,
material used (HPDE or steel), and size of line.
Most projects will require a combination of less
expensive and more expensive piping material.
$20/meter
If a mine already uses gob wells, the mine will already
have an exhauster/blower at the wellhead.
Horsepower includes total horsepower for wellhead
compressors and satellite compressors.
One-time capital cost. Highly dependent on site-
specific conditins.
Lines running from gob wells to satellite compressor
can be moved from year to year as some gob wells
stop producing and others come on-line. (A typical gob
well might produce gas for a few months to a few
years, though typically will produce gas for less than
one year). Since gathering lines can be moved, costs
for purchasing gathering lines is a one-time capital
cost. However, the cost for moving and installing
gathering lines is an annual cost. Roughly half of the
costs shown are for recurring (i.e., annual) installation
costs.
Cost for purchasing and installing gathering lines is a
one-time capital cost. Lines running from vertical wells
to satellite compressors would not be moved on a
regular basis, since vertical wells will likely produce gas
for many years.
Underground lines can be moved from one borehole to
another. Cost for purchasing line would be a one-time
capital cost, while cost for moving and re-installing lines
would be an annual cost. Roughly half of the costs
shown are for recurring (i.e., annual) installation costs.

-------
Exhibit 4-8: Gas Recovery
System Component/
Equipment Required
and Utilization Cost Factors
Number or Size of Units Needed
Cost Per Unit
Comments
Gas Processing System
Wellhead Separators
Glycol Dehydrator Capital Cost
Dehydration Operating Cost
For surface wells: 1 separator for each well
(1 separator for maximum number of wells drilled per
year).
For in-mine boreholes: 1 separator is needed for
every four longwall panels drilled (every 4 million tons
of coal drilled each year). Since separators can be
moved, total number of separators needed would be
based on maximum number of longwall panels drilled
each year.
1 Dehydrator per project.

$2,000 per separator
Initial capital cost: $30,000 to $50,000.
Annual operating cost: $3,000 per year
Wellhead separators are a one-time capital cost.
Because vertical wells produce simultaneously, one
separator is required for each well drilled. Because gob
wells and in-mine boreholes produce sequentially, one
separator is needed for the maximum number of wells
drilled in a single year. For long project lifetimes (more
than 15 years), separators may need to be replaced
once.
Dehydrator costs are a one-time capital cost. For long
project lifetimes (more than 15 years), the dehydrator
may need to be replaced once.

On-Site Gas Use System
Preparation plant conversion
equipment

$250,000 to $750,00
Initial capital cost (depends on site-specific equipment
requirements).
Electric Power Generation System
Gas Turbine Capital Cost
Gas Turbine Operating Cost
Utility Interconnection Cost
Installed capacity of the turbine in kiloWatts (kW)

Initial cost per project.
$1 ,100/kW installed capacity.
$0.01/kWh of electricity generated.
$300,000 to $500,000 per project.
Initial capital cost. Capacity estimated based on gas
production and engine-generator heat rate (see text).
Annual operating cost. Electricity generated estimated
based on gas production and engine-generator heat
rate (see text).
Initial capital cost.
Off-Site Gas Sales System
Gas enrichment equipment
capital cost.
Gas enrichment system
operating cost.
Sales compressor to bring the
gas to pipeline pressure
Sales meter and gas analyzer
One system per project.

3,500 HP per maximum expected production in million
cubic meters per day. Compressor HP needed will
vary based on pressure of sales pipeline and distance
to sales pipeline or pressure required by industrial
end-user and distance to end-user.
1 sales meter and gas analyzer per project
$1 to $3 million, depending on gas flow rates and
gas quality.
$3.50 per thousand cubic meters of gas enriched.
$650/HP
$20 ,000 per project.
Initial capital cost. Enrichment will not be required for
gas produced from vertical pre-mining degasification
wells or horizontal boreholes. Gas produced from gob
wells or cross-measure boreholes, however, may
require enrichment. Enrichment equipment includes
cost for pressure swing adsorption system and a
catalytic deoxygination unit.

Initial capital cost.
Initial capital cost.

-------
Exhibit 4-8: Gas Recovery and Utilization Cost Factors
   System Component/
   Equipment Required
     Number or Size of Units Needed
             Cost Per Unit
                Comments
Transmission Pipeline
Length of transmission pipeline will vary substantially
depending on distance between mine and commercial
pipeline or industry end-user.	
$32/meter.
Initial capital cost.

-------
Preliminary Site Assessments                                                COALBED  METHANE GUIDELINES
                                     ^      Electricity Sales. If electricity is to be distributed through the electric
                                             power  grid,  the owner/operator of  the  grid (such  as a national
                                             electricity company) will typically purchase the electricity at the point at
                                             which it enters the grid. There are a variety of methods by which the
                                             electricity price may be determined.  For example, the price could be
                                             set at the average marginal cost of generating electricity elsewhere in
                                             the system, or it could be set at the price given to electricity producers
                                             using conventional fuels.   It is  recommended  that potential  pricing
                                             arrangements be explored with the proper authorities as part of this
                                             preliminary assessment. In some cases, the electric power generation
                                             aspect of the project is best developed jointly with the electric power
                                             authority.

                                     ^      Sale of Gas.  The expected price of gas sold directly to customers can
                                             be based on the price of alternative fuels, such as propane, oil, natural
                                             gas or coal,  on an energy basis (e.g., price per million Joules).  The
                                             relevant fuel  price to  use  depends on which fuel the coal  mine
                                             methane  will be replacing.  The  price of gas sold  to a pipeline
                                             company can be based on the price paid for other gas supplies on a
                                             comparable energy basis.  If the customer must convert his equipment
                                             to use the coal mine  methane,  the gas may need to be sold at a
                                             discount.

                                     +      Tax  credits.   Tax credits or other government programs  can also
                                             affect project revenues.   Some government programs  may offer tax
                                             credits or subsidies  for  producing  energy from  non-conventional
                                             sources, including coal mines.   The applicability of these incentives
                                             usually depends on the structure  of the project and  the coal  mine
                                             owner/operators' tax situation.  Therefore, a complete understanding
                                             of the tax laws and their application is critical to ensuring a project's
                                             ability to take full advantage of the incentives.

                                     Under some conditions royalties are paid to the resource owner.  Royalties can
                                     be viewed as compensation for gas rights or as a financial incentive for allowing
                                     the project to  be developed. Royalties are usually estimated as a percentage
                                     of total  revenue or  energy  produced.  Any royalty payments should be
                                     subtracted from the revenue estimate prior to comparing costs and revenues
                                     from the project developer's perspective.
                                     Cost/Benefit Analysis

                                     Once  the revenues  are  estimated, they  must be  compared  to  the costs
                                     (estimated in the previous section).  This comparison requires a  time profile of
                                     the  project's costs and revenues.  From the information above, the capital
                                     costs,  annual  operating  costs,  and  annual revenues  can be estimated.
                                     Possible increases or decreases in energy prices and gas production over the
                                     life of the project should be taken account when estimating  annual revenues
                                     and savings.  For purposes of evaluation, it can be assumed that the project
                                     continues for 10  to 20 years, and the annual operating expenses are incurred
                 -en-

-------
COALBED METHANE GUIDELINES
     each year.  Using the time profile of costs and revenues, three main techniques
     can be used to determine the economic feasibility of the project:

     +       Payback Method.  The payback method  involves determining the
             number of years it would take for a project to generate profits equal to
             the initial capital outlay.  The  advantage of this method is that it is
             simple.  It may  be particularly suitable where there is a great amount
             of risk and uncertainty  associated with a project and the emphasis is
             on recovering capital expenditures as quickly  as  possible.   Its  main
             drawbacks are  that it does not consider  the costs and  benefits that
             accrue at the end of the payback period and that it takes no account of
             the time when costs are incurred or benefits received  The payback
             method is  appropriate to  use when making  a rough preliminary
             assessment  of a project's economic feasibility.

     ^       Discounted   Cash  Flow  Method.    The basic  premise  of the
             discounted cash flow technique is that costs or benefits occurring in
             the future are worth less that those occurring now.  This means that
             costs and benefits cannot simply  be added up over the years of the
             project.   The costs and  benefits in  each year  of the project are
             adjusted by a discount factor so that costs or benefits occurring in one
             year can  be  compared  with the costs or benefits occurring in another
             year.   The  discounted costs and benefits  in  each  year  can be
             aggregated  to give  a net  present value (see Exhibit 4-9) of future
             cash flows of the project.   The discount rate  used will normally be
             chosen on the basis of prevailing  interest rates or on the basis of the
             minimum desired rate of return for the project.  If the net present value
             is positive, the appraisal shows that the project is capable of yielding
             this minimum rate of return.
                 ASSESSMENT
Exhibit 4-9: Net Present Value
The  Net Present  Value  (NPV) is the
present value of a project's  cash flows,
including all investment costs.  If the
NPV  is greater than  0, a project  is
considered to be profitable  at the
chosen discount rate.   The  net present
value can be expressed as follows:
             n
                  ACF
  NPV=
                             IO
 where:

 ACFt
 r
 10
 n
         = annual cash flow in year t
         = discount rate
         = initial cash outlay
         = life of the project
     +       Internal Rate of Return  Method.  The internal rate  of  return (see
             Exhibit 4-10) is the discount rate at which the present value  of the
             project would be zero.   This value shows the total  rate  of  return
             achieved by the project.  This rate can be compared  to return rates
             from alternative investment opportunities.

     Sensitivity analyses should be carried out to examine  how changes in  key
     parameters such as electricity prices or gas production can affect the economic
     viability of the project.  These sensitivity analyses  can  carried  out before the
     financing arrangements for the project have been worked out and are useful in
     providing an initial indication of the project's viability.  Further analysis can be
     conducted  to  examine  the  implications  for  viability  of  different  financing
     schemes.
Exhibit   4-10:   Internal  Rate  of
Return
The   Internal  Rate  of  Return  is
calculated as follows:
               ACF
 0 =

where:

ACFt
10
n
IRR
                             10
        =  annual cash flow in year t
        =  initial cash outlay
        =  life of the project
        =  internal rate of return.

-------
                                                                                 COALBED  METHANE GUIDELINES
                                      Energy Supplied

                                      The cost effectiveness of a gas recovery project may be evaluated in terms of
                                      the quantity of energy supplied. The cost of gas recovery would be compared
                                      with alternative  energy supply options to determine the most cost effective
                                      option.  The threshold level of cost effectiveness may be set in terms of energy
                                      supplied per unit cost.  For example, gas recovery projects that  supply energy
                                      at a cost of $0.07/kWh may be defined as being  cost effective  if the marginal
                                      cost of alternative electricity supply options is $0.07/kWh.

                                      In some cases, energy from  the gas recovery  project may be provided to
                                      customers who otherwise  would be  using wood (e.g., for  residential cooking).
                                      In this case, the value of preventing over-harvesting of forest resources may be
                                      the measure of cost effectiveness for the project.  An alternative may be to set
                                      a threshold level in terms of the number of households served  by the energy
                                      supplied.  This would require data on average household energy consumption.
                                      For example, a cost effective project may be one that costs  less than $3 per
                                      household served. Such evaluations are prudent particularly in areas of energy
                                      scarcity.
                                      Emissions Avoided
Benefits  of  emission  reduction  are
difficult to evaluate in monetary terms
as they do not accrue directly to  a
project developer.    However,  such
benefits are important to consider in the
formulation of national energy policy
and  tax  and  subsidy regimes  for
emissions mitigation   or  renewable
energy projects.
Recovery  and utilization of methane from coal mines  prevent the release of
methane and provide a clean energy source.  Methane is a potent greenhouse
gas; over a 100 year period, a ton of methane emitted into the atmosphere has
the equivalent global  warming  impact  of about  21 tons of carbon dioxide.
Combusting the coal mine methane prevents its emission into the atmosphere,
thereby reducing greenhouse gas emissions

Although  the  emphasis of this document is to  identify  projects that are
economically viable in their  own right,  gas  recovery  projects may  be
implemented specifically to reduce methane emissions from the mine.   The
economics of such a project will  be  evaluated in terms of the cost of emissions
avoided. For example, a threshold level of cost effectiveness may be set at $50
per ton of methane emissions avoided.  If the project costs less than $50 per
ton of methane emissions avoided, the project is considered cost effective.

The emissions impact of a gas recovery projects is, simply,  the amount of gas
recovered and combusted. The methane emissions avoided can be expressed
in terms of carbon dioxide emission avoided  using a Global  Warming Potential
of methane equal to 21 .6 The following equation expresses the relationship.
                             C02 Equivalent Emissions Avoided (tons/yr)

                   CH4 Emissions
                                        of a gas relative to the warming impact of carbon (
                                        has 21 times the impact of one gram of carbon dioxic
                                              of the relative warming impact
                                              oxide.  One gram of methane
                                              3 over a 100 year period.

-------
COALBED METHANE GUIDELINES
     By expressing the emissions reduction  in terms of an equivalent amount of
     carbon dioxide, the reductions from this project can be compared to alternative
     methods of reducing greenhouse  gas emissions.  The  extent to which  the
     recovered coal mine methane is substituted for more polluting fuels, emissions
     of other pollutants will also be reduced.
                                                                                             ASSESSMENT
    4.4 References

    Sturgill, C.   1991.   Power Generation:  On-Site  Use and Sale to  Utilities.
            Prepared for US EPA Office of Air and Radiation,  EPA, Washington,
            D.C.

    USEPA (U.S. Environmental Protection Agency).  1990.  Methane Emissions
            from Coal Mining:  Issues and Opportunities for Reduction, Office of
            Air and Radiation, EPA, Washington, D.C.

    USEPA (U.S. Environmental  Protection  Agency).   1993a.   Anthropogenic
            Methane Emissions in the United States, Report to the  Congress,
            prepared by the Global Change Division,  Office of Air and Radiation,
            EPA, Washington, D.C.

    USEPA (U.S.  Environmental Protection  Agency).    1993b.   International
            Anthropogenic Methane Emissions: Estimates for 1990, Report to the
            Congress, prepared by the Office of Policy, Planning and Evaluation,
            EPA, Washington, D.C.

    USEPA  (U.S.   Environmental  Protection  Agency).    1995.    Economic
            Assessment of the Potential for Profitable  Use of Coal Mine Methane:
            Case Studies  of Three  Hypothetical  U.S. Mines,  prepared  by  the
            Office of Policy, Planning and Evaluation, EPA, Washington, D.C.

-------
Government  Policies                                                    COALBED METHANE GUIDELINES
                               5. IDENTIFICATION AND ASSESSMENT OF KEY
                               GOVERNMENT POLICIES
                                   THE government can play an  important role in developing domestic coal
                                   mine methane resources.  The policies that it formulates can promote or
                               hinder the recovery and use of this clean energy source. The purpose of this
                               section is to: 1) identify the key policies that will affect the development of coal
                               mine methane projects; and 2) assess whether these policies pose barriers that
                               must  be overcome  or are potential  leverage points to promote project
                               development.   Although there are various policies that can encourage coal
                               mine methane projects, it is not possible to recommend a general set of policies
                               for every circumstance. Rather,  policies must be tailored  individually to suit
                               each country.
                               5.1  National Energy Pricing, Subsidies, and Taxes

                               A primary barrier to coal mine methane recovery and use in both developing
                               and developed countries is  often artificially low energy prices.  Conditions
                               influencing electricity  and  natural gas  prices, such  as government energy
                               policies and subsidies, can have an important effect on the economic viability of
                               coal mine projects.

                               Energy subsidies can both help and  harm coal mine methane recovery and
                               utilization projects. Artificially low energy prices can pose a barrier to coal mine
                               methane utilization.  If the prices of natural gas, oil,  and coal are less than the
                               cost of producing coal mine methane, it will be difficult to develop a profitable
                               coal mine methane  project.   Using market prices for natural resources would
                               allow coal mine methane to compete  fairly.  If  even under market prices coal
                               mine methane is uncompetitive, however, the government may offer tax credits
                               or  other financial incentives to  encourage  these projects because  of  their
                               environmental and safety benefits.

                               Energy taxes must also be assessed for their impact on gas recovery projects.
                               Energy taxes based on fossil  carbon content would give recovered methane an
                               edge over coal and oil. Similarly, higher taxes on imported energy would allow
                               domestic coal mine methane  to be more competitive. Depending on a nation's
                               energy goals, the tax structure may prefer one source of energy over another.

                               For example, in the United States, several federal, state, and local incentives
                               are available for coal  mine  methane  projects,  such as  the Internal Revenue
                               Service (IRS) Section 29 Tax Credit (see Exhibit 5-1).

-------
COALBED METHANE GUIDELINES
                                                                                                 POLICIES
     5.2  National Energy Supply Priorities

     The nation's energy supply goals will help determine the emphasis placed upon
     coal  mine methane development.   There  are  two  main national  energy
     concerns that may  affect coal mine methane promotion: supply security and
     increasing domestic demand.

     Many nations are concerned about relying on foreign sources of energy.  The
     most notable example is reluctance of many nations to depend on oil and gas
     from unstable regions.  Because  the price of natural  resources has a great
     impact on a nation's economy, and domestic sources of energy are considered
     to be more stable, many nations share the common goal of increasing domestic
     natural  resources.  Therefore, nations  may choose to encourage coal mine
     methane recovery and utilization to expand their domestic supply of energy.

     For nations where energy demand is growing  rapidly and there are shortfalls in
     supply,  energy policy may include the development of coal mine methane to
     help  meet the nation's energy needs.   For example, in many developing
     nations, the shortage of energy  has slowed down  the process of electrification
     of towns and villages.  The use of coal mine methane as a fuel  to generate
     electricity could help to meet the goal of universal  electrification. Furthermore,
     the use of domestically produced  energy will decrease the amount of foreign
     exchange required  to import  energy.  Many  developing countries and those
     with economies in  transition face a shortage of foreign exchange.  Coal
     restructuring may force uneconomic or unsafe coal mines to close down, which
     may cause some economic hardships.  However, the benefits that coal mine
     methane recovery produces,  including jobs and safer,  more profitable mines,
     can offset the losses.

     If coal  mine  methane recovery and utilization is consistent with a  nation's
     energy  supply  priorities,  it  may be easier to create  policies  to  promote its
     development.    For example,  a  detailed   resource  assessment  may  be
     undertaken or information on technologies, financing, and pertinent policies can
     be made publicly available.  If, however,  a nation has ample quantities of
     domestically produced  energy, it may not involve  itself in the  issue simply for
     the  purpose  of expanding  energy  supplies.    Rather,  in  such  cases,
     environmental goals may be more important.
Exhibit 5-1:  U.S.  Internal  Revenue
Service (IRS) Section 29 Tax Credit

This  is  a U.S.  federal tax  credit for
producing energy from  non-conventional
sources, including coal  mines.  This tax
credit applies to wells drilled before 1992
and  will  expire  on  January  1, 2003.
When the tax credit was  established in
1979, the value of the credit was set at
$0.52 per thousand cubic feet of gas. The
value of  the  credit  changes  annually,
depending  on  a  number  of  factors,
including the domestic oil  price and the
inflation rate.  In 1994, the  credit equaled
$0.90 per thousand cubic feet of gas.
     5.3  Environmental Goals

     A nation's  environmental goals will also play a  large role in  determining the
     importance given to coal mine  methane projects.  Coal mine methane may be
     encouraged when environmental  issues are  placed highly  on  the  national
     agenda.  The two main issues concerning environmental policy and their impact
     on coal mine methane can be divided into a global concern and a local/national
     concern.

-------
Government  Policies                                                      COALBED  METHANE GUIDELINES
                               As explained in Chapter 2, methane is a greenhouse gas,  affecting the global
                               environment. If a nation has an active interest in reducing methane emissions,
                               it may promote the recovery of methane from coal mining.

                               Both  national and local environmental policy may call for the use of cleaner
                               fuels  to reduce local pollution and for the clean  up of water discharged during
                               mining.  Coal mine methane can be used to displace more polluting fuels, such
                               as coal  or  oil.   Methane  has several advantages over other fossil fuels.
                               Emissions  of S02,  NOX,  and  particulates can  be  reduced  through  the
                               displacement of  coal (and to a  lesser degree oil) with  gas.   Natural gas
                               combustion  produces  no  S02  or particulate  emissions,  and lower  NOX
                               emissions.

                               Coal  mine methane can also be used to treat mine water before it is discharged
                               into rivers or used for other purposes.  The disposal of this water is a significant
                               local  environmental problem  in  many countries.  As described  above, a
                               demonstration project is underway at the Morcinek mine in Poland that involves
                               using coal mine methane for this purpose.
                                5.4  Financing

                                In  order to assess  the  impact of government  investment  polices on  the
                                financing of coal mine methane projects, one  must look at both the overall
                                investment regime and the financial  regulations  specifically concerning coal
                                mine methane.  When studying the overall regime, it is necessary to look at the
                                corporate tax structure,  import and  export  taxes and  quotas,  and  laws
                                concerning foreign ownership.  Low  limits on foreign ownership  and a high
                                corporate tax structure in  comparison to other nations with potential coal mine
                                methane projects may pose barriers to foreign investors.  In cases in which the
                                equipment  must  be  imported  from abroad, high  import duties  will  place a
                                burden on both domestic and foreign investors.

                                The government also may have financial regulations dealing  specifically with
                                coal mine methane.  For example, low interest loans, tax credits, loans, grants,
                                and subsidies for coal mine methane projects will ease the financial burden on
                                the investor.  As mentioned above, the use of such incentives will depend on
                                the overall energy and environment goals of the government.

                                For example,  in  the U.S., many state  governments provide grants or  low
                                interest loans to projects that improve the environment or increase the  local
                                supply of clean fuels. As coal mine methane projects can do both,  they may be
                                eligible to receive various types of state funding.  Examples of such programs
                                include one by the Pennsylvania Energy Development Authority that provides
                                loans and grants for the development of new sources of energy, as well as the
                                Indiana  Recycling   and   Energy  Development  Program,  which  provides
                                assistance  for  the  development of new energy  resources and  recycling
                                programs.

-------
COALBED METHANE GUIDELINES
                                                                                                POLICIES
    5.5 Technology Development

    As some of the technologies associated with coal mine methane recovery and
    utilization  may  not  be available in  many  nations,  the government's policy
    towards the development of technology  is important to  assess.  There  are
    various ways in which the  government can encourage  the development of
    technologies specific to coal mine methane projects:

    ^      Encourage foreign participation in coal  mine methane  projects.
            This would  allow foreign technology to be introduced without requiring
            domestic capital.   Foreign  participation, however  may  bring forth
            issues of ownership of the recovered  methane. These arrangements
            may thus require detailed contracts regarding use and rights of both
            parties involved, discussed further in section 5.6 below.

    ^      Lower  import  duties,  taxes,  and  restrictions  on  required
            technologies, thereby  reducing  the  cost of a coal mine  methane
            project.

    +      Fund   demonstration  projects  at  domestic mines to allow  the
            industry to see and understand new technologies.

    +      Organize study tours  and  training  trips abroad for key personnel
            so that they may learn from the experiences of other nations.

    +      Finance research and  development into recovery and use methods
            to assist the local industry.

    If  technology is a strong barrier to  the development of coal mine  methane
    projects, government policies that encourage the transfer of technology and the
    development of local  technology can  help  promote these  projects.   An
    important part of technology transfer that must not be overlooked is the need to
    ensure the safety of those using the equipment.  Governments could involve
    safety  and certification agencies to examine and evaluate the technology; in
    some cases a formal licensing or approval process could be established.
    5.6 Concession Process

    Through the granting  of  natural  resource  concessions,  governments can
    encourage project development.   In  granting a concession,  a government
    authorizes a developer to extract and sell a natural resource.   Typically, the
    grantee pays to obtain  the concession, and often is required to pay a royalty
    based on the amount of resource extracted.

    There are two main issues that must be analyzed in this process.  First, before
    the concession process can begin, the  issue of ownership of the coal mine
    methane must be resolved.   If natural  resources are owned  by the  private
    sector, coal  mine  methane resources can belong to the owner of the surface

-------
Government  Policies                                                     COALBED  METHANE  GUIDELINES
                                rights, the owner of the coal rights, or the owner of the oil and gas rights.  If
                                natural resources are nationalized, it may be uncertain whether the national  or
                                regional government has the authority to grant concessions.  This uncertainty
                                can prevent projects from being developed.  Furthermore, in nations in which
                                the  natural resource sectors  are  being  privatized,  the  laws  concerning
                                ownership may be in flux.

                                The  second matter  concerns the clarity,  efficiency, and stability of the actual
                                concession  process.  A  long,  complex concession  process can act  as a
                                deterrent to investment in coal mine methane resources.  Common problems
                                faced  by investors include delays in  the decision making process, confusion
                                over who is in charge, sudden changes in regulations, and the reversal  of
                                decisions.   These  problems  are exacerbated  in  nations where all natural
                                resources were  previously  owned by the government and the concession
                                process  is still  being formulated.   The following questions  are useful  in
                                determining whether the current concession process may be a potential barrier
                                to project development:

                                +      Who should be contacted for questions concerning various steps  of
                                       the concession process? Is it clear exactly who is in charge of what
                                       step and are those persons easily accessible?

                                +      How long does the concession process take?

                                +      Once a decision has  been made, what is the likelihood of  it being
                                       overturned?

                                Clear laws concerning coal mine methane ownership and a clear, efficient, and
                                stable concession process will help to promote coal mine methane projects.
                                5.7 References

                                USEPA  (U.S.  Environmental  Protection  Agency).   1993.   Anthropogenic
                                        Methane Emissions in the United  States, Report to the Congress,
                                        prepared by the Global Change Division, Office of Air and Radiation,
                                        EPA, Washington, D.C.

                                USEPA  (U.S.  Environmental   Protection  Agency).   1994.    International
                                        Anthropogenic Methane Emissions: Estimates for 1990,  Report to the
                                        Congress, prepared by the Office of Policy, Planning and Evaluation,
                                        EPA, Washington, D.C.

-------
COAL GUIDELINES                                                                               Next stePs
   6. NEXT STEPS
      THIS section outlines the next steps for evaluating and implementing coal
      mine methane recovery and utilization projects in developing countries and
   countries with  economies in transition.  The  steps encompass a range  of
   initiatives that may be tailored to meet individual country objectives.   These
   initiatives are divided into the following five main areas:

   +       Focus on the Most Promising Projects.  This section presents next
           steps for focusing on the most promising coal mine methane projects
           in your country.

   ^       Availability of Technology and Expertise.  This section identifies
           approaches for assessing whether the technology and  expertise
           required for implementing projects are available.

   +       Decisionmaker Motivation.   This section presents  approaches for
           motivating decisionmakers to undertake coal mine methane recovery
           and utilization projects.

   ^       Resolution of  Regulatory Issues.   This section  lists regulatory
           issues that  should  be examined to assess whether existing  policies
           hinder or further the goal of implementing coal mine methane projects.

   +       Funding. This section identifies possible sources of funding for these
           next step activities.

   Exhibit 6-1  summarizes  how this chapter  can be used  to meet  various
   objectives.  The first column lists several common objectives and the second
   column lists the chapter section to consult.
   6.1  Focus on the Most Promising Projects

   Although the site screening and preliminary assessments discussed  above in
   chapters 3 and 4  may show that  a variety of promising  projects exist,  the
   available data may be insufficient for identifying the most promising project
   opportunities. In particular, if there are a large number of gassy mines, detailed
   site-specific information on all the sites may not have  been collected in  the
   screening step (chapter 3) because of the level of resources that are  required.
   This section provides guidance for collecting additional site-specific information
   that will  enable prefeasibility assessment activities to be focused  on  the most
   promising opportunities. This initiative is only required when there are a large
   number of potential sites that need to be evaluated.
     Exhibit 6-1:  How to use this Chapter

-------
                                                          COAL GUIDELINES
Objective:
To focus on the most promising
coal mine methane projects.
To assemble the technology
and expertise needed to
develop coal mine methane
recovery and utilization projects.
To motivate decisionmakers to
invest in and implement coal
mine methane projects.
To identify and eliminate
regulatory barriers.
To obtain funding for program
development or project
implementation.
Section to Consult:
Section 6.1 - Focus on the Most Promising
Projects summarizes steps for collecting
additional data on candidate sites to better
focus efforts.
Section 6.2 - Availability of Technology and
Expertise presents steps for identifying and
filling gaps in the availability of technology and
expertise needed to develop projects.
Section 6.3 - Motivate Decisionmakers
presents options for assisting decision makers
and providing incentives.
Section 6.4 - Resolution of Regulatory
Issues discusses those policies and
regulatory structures that should be reviewed
to identify potential barriers.
Section 6.5 - Funding presents candidate
funding sources that can be consulted.
To collect this information, a specific program activity should be defined  with
data collection as its objective.  Such an initiative was conducted in the United
States to  identify the  most promising coal mine  methane  opportunities  (see
Exhibit 6-2).  Section 6.5 describes funding sources that may be contacted  to
obtain funding for these types of activity.  A sample five step program  plan for
collecting the necessary data is as follows:

Stepl: Define Minimum Information

The first task is to define the minimum information that is required for each  coal
mine. As discussed in Chapter 3, the three primary factors that makes a site a
promising  opportunity for gas recovery and use are 1) coal production of  at
least 0.3 million tons of coal annually, 2) methane emissions of at  least  nine
cubic meters per metric ton of coal produced, and 3) a remaining life span  of at
least five years.  Therefore,  it is recommended that this information collection
effort focus on obtaining the best possible information on three factors:

+      The number of tons of coal produced annually;

+      Methane emissions per ton of coal mined; and

+      Remaining mine lifespan.

-------
COAL  GUIDELINES
    Exhibit 6-2:  US EPA Coal Mine Profiles Project

    The  US  EPA Coal  Mine Profiles Project was  developed to  identify the most
    promising coal mine  methane project opportunities  in the United States.  This
    information is being provided to coal mine owners and operators, electric utilities,
    natural gas pipeline companies, state and local government officials, and potential
    project developers. Based on publicly available data collected primarily from state
    and federal reports and  industry press,  a minimum  data set was developed for
    large  and gassy  mines from which  a profile is created. These  profiles  are then
    used  to  identify those  mines that may  offer attractive  energy  development
    opportunities.

    The profile for each coal mine has the following information:
             Coal mine location and operating status;
             Coal production;
             Methane emissions;
             Energy potential of the methane (including the amount of electricity that
             may be generated from the recovered methane);
             Existing methane recovery and use;
             Distance from mine to a pipeline;
             Nearby institutional or industrial facilities; and
             Contact information (i.e., coal mine owner/operator).
    Based on this information, the gas recovery and use potential and associated
    environmental and energy benefits from a potential project are estimated.  These
    profiles are currently available from the US EPA for over 80 mines in 10 states.
   Additional information on energy needs surrounding the coal mine and potential
   consumers  in the  area may also be collected  if the information  is  readily
   available. Since methane can be used at the mine itself, this information is not
   on the list of the minimum information required.

   Step 2:  Define the Data Collection Method

   The  purpose of this second step is  to define how the data will  be  collected.
   Options may include working with  local  government officials who collect coal
   production and methane emissions data or surveying individual coal mines to
   collect or estimate this data. The  techniques to be used to  collect the data
   should be selected based on the type of information most  likely to be available
   and the resources available for collecting the data.  It may be appropriate to test
   several  different data collection  methods before settling on the recommended
   approach.

   Step 3:  Develop a Data Handling System

   The purpose of this third step is to develop a system for handling the  coal mine
   data.  A database program can be used to organize the data so the subsequent
   data analysis and evaluation is facilitated.   Data handling and quality  control
   procedures  should be developed as part of this step, including  checking the
   accuracy of both the data collection and data entry activities.

-------
Next  Steps                                                                                   COAL GUIDELINES
                                     Step 4: Collect the Data

                                     In  this step the program  personnel collect the  data according to the method
                                     defined in step  2.  The data are entered into  the data system developed  in
                                     step 3.

                                     Step 5: Analysis and Recommendations

                                     Based on the data collected, the gas recovery and use potential for candidate
                                     coal mines is estimated (Chapter 4  presents  equations for estimating  gas
                                     recovery). The  most promising project opportunities will be those that produce
                                     the most gas in areas  that can use the energy.  A list of the most attractive
                                     projects can be created, along with the information available on each.

                                     Once the most  promising opportunities are identified, this information can be
                                     disseminated  to potential project developers  to promote  the  projects (see
                                     section 6.3).
                                     6.2  Availability of Technology and Expertise

                                     Specific technical  expertise is  required to plan  and implement  coal  mine
                                     methane recovery  and  utilization  projects.   Additionally,  access to  and
                                     experience with specialized drilling and gas monitoring equipment are needed.
                                     The absence of the necessary expertise and equipment can be a significant
                                     barrier to the implementation of these projects.  This issue may be particularly
                                     important in  developing countries and countries with  economies in transition
                                     because technical and labor resources may not be available to construct and
                                     operate the projects.

                                     Once it has  been determined that  promising  opportunities exist,  necessary
                                     expertise and equipment should be located.  Ideally, one or more local experts
                                     with coal mine methane recovery and use expertise should be identified.  For
                                     example, a request for qualifications can be  issued to  identify local or regional
                                     individuals and organizations with the necessary expertise.

                                     In some cases a coal mine methane expert familiar with the latest technologies
                                     may  not exist in the nation.  In this circumstance, a program can be organized
                                     to train local personnel in the detailed aspects of coal  mine methane  recovery
                                     and utilization. Training programs could  include visits to  existing projects  in
                                     other countries as well as  inviting experts from other countries to give seminars.

                                     To augment local expertise, nations may wish to  contact foreign companies
                                     with the expertise  necessary to complete the project. Foreign involvement may
                                     take  any of  a  variety  of forms,  including  the build-operate-transfer  (BOT)
                                     financing model.  The BOT is currently being  used for various infrastructure
                                     projects in  developing  countries and is  applicable  for  coal  mine  methane
                                     projects as well.  Such arrangements with foreign companies allow technology

-------
COAL GUIDELINES                                                                              Next stePs
   to be introduced without requiring the use of domestic capital.  For countries
   that have  limited  or  no experience  with  coal mine  methane  recovery and
   utilization, this may be an attractive short-term option. Appendix A lists selected
   U.S. coal mine methane development experts available to provide training or
   participate in project development.
   6.3  Motivate Decisionmakers

   Because coal mine methane recovery and utilization projects are relatively new
   in many countries, steps to motivate decisionmakers may be necessary to get
   promising  projects  built.   Examples  of  decisionmakers  include coal mine
   owners, government officials in the energy and environment  ministries, and
   potential project developers.  In addition to financial  incentives, several targeted
   initiatives  have  proven effective  for both raising  awareness regarding  the
   benefits of such projects, as well as creating the nucleus of interested parties
   needed to create a viable project.  Three main initiatives are recommended to
   provide the information  needed  to  motivate decisionmakers:    outreach
   activities, demonstration projects, and information clearinghouses.

   6.3.1 Outreach Activities

   Because the concept of recovering and utilizing methane from coal mines may
   be unfamiliar, outreach activities may be required to educate and motivate the
   community  and its leaders on the  technology and benefits of coal mine
   methane projects. Outreach should be targeted to the following parties:

   +      Coal mine owners and operators,  who may not  recognize  the
          resource they have;

   +      Potential users of coal mine methane, who may not recognize the
          opportunity to obtain low cost energy;

   +      Energy planners, who may not recognize how energy  from coal mine
          methane can contribute to meeting local energy needs;  and

   +      Environmental and community groups, who  may not be aware of
          the environmental and safety benefits of coal mine methane projects.

   Outreach activities to  educate and motivate these parties must be defined in
   terms of the message that is being  delivered and the mechanism that is used to
   deliver  the  message.   The message must include the information needed to
   educate and motivate each target group.  The information must be presented in
   a way  that each target group can understand, and  must  be  delivered in  a
   manner that ensures  that each target group  receives and assimilates  the
   information.   Because each  target group  is  different,  separate  outreach
   strategies may be needed for each.

-------
                                                              COAL GUIDELINES
  Exhibit 6-3:  The US EPA Coalbed Methane Outreach Program

                     EPA's Coalbed  Methane  Outreach Program encourages
                     the use of coal mine methane as an energy resource.  EPA
                     enlists the support of coal  mine  owners and  operators,
                     electric utilities,   state agencies,  private  financiers,  and
                     project developers to reduce methane  emissions from coal
                     mines through the development of profitable energy recovery
  The Coalbed Outreach Program promotes coal mine methane recovery and use
  projects in the U.S. as well as in countries such as Russia,  China, Poland, and
  Ukraine. Projects undertaken by the Program in the U.S.  include:

  •   Profiles  of the gassiest mines in the nation (these profiles are discussed
      above);
  •   Guides to possible sources of funding for coal mine methane projects in West
      Virginia and Pennsylvania, two state with several gassy mines;
  •   Study of the  barriers facing  coal mine  methane  projects and  possible
      solutions to these barriers; and
  •   Detailed technical and financial feasibility assessment for potential coal mine
      methane project developers.

  To promote  coal  mine methane projects abroad, EPA has  helped establish
  clearinghouses in Poland, Russia, and China.  EPA has also written reports  on the
  coal  mine methane potential  of these nations and has profiled some  of the
  gassiest mines.  At present,  EPA is working with  the Chinese Coalbed Methane
  Clearinghouse to  develop a financial  model to evaluate  coal  mine methane
  projects in China.
For example, outreach to national planners and decisionmakers may employ
existing decisionmaking  processes.   Alternatively, outreach to local  officials
responsible for the local coal industry may require seminars, training sessions,
or technical guidebooks to inform them of the coal mine methane recovery and
utilization opportunities.  Options for reaching potential foreign partners may
include conducting studies through international funding agencies  (discussed
below in section 6.5) or issuing  requests for proposals for specific  projects or
studies.  Exhibit 6-3 summarizes the outreach program currently being used in
the United States to reach these various groups.
Exhibit 6-4:  Demonstration Project in Russia

During its visit to Russia in 1995, the EPA identified a demonstration project at the
Kirov  mine in  the Kuzbass coal basin.  This project would use methane recovered
from the degasification systems to fuel the three central boilers.  At present, these
boilers run on coal. Currently, EPA is preparing a project opportunity report on this
project.  This report will be distributed to potential lenders.

The successful implementation of  this demonstration project will facilitate the
development of other coal  mine methane projects in Russia.	

-------
COAL GUIDELINES                                                                               Next stePs
   6.3.2   Demonstration Projects

   Sometimes information is not enough to promote the use of a new technology.
   Users may want to see the technology in use. Demonstration projects are an
   effective tool  to test and promote the effectiveness of  coal  mine methane
   recovery and use projects,  especially in developing countries and countries
   with  economies in transition where such projects may  be uncommon.   By
   providing analysis, technical support, and funding, the  government can facilitate
   projects to serve as examples for the industry as a whole.

   In  selecting projects  to  support  and  promote,  several  criteria  should  be
   considered, including: choice of technology, time frame for the project,  type of
   government  assistance  required,  and  how  projects  will   promote  the
   government's goals.   In most  cases, after a  specific  project is selected,
   technical and financial analyses will be required to evaluate the effectiveness of
   the technology, as well as its costs  and benefits.

   Upon completion of the demonstration  project, the results of the project must be
   summarized,    including   both    positive   and   negative   aspects   and
   recommendations  for improvement. This information  must be disseminated to
   promote the technology.  The demonstration site itself can  then be used for
   training and education purposes.
   6.3.3 Information Clearinghouses

   To  provide  owners, developers, regulators, and other stakeholders with
   comprehensive  information concerning  all  aspects of coal mine methane
   recovery  and utilization  technology, finance, and economic development,  a
   central  information   clearinghouse   could   be   established.   Information
   clearinghouses  provide  a  central  location  for  information where  current
   environmental,  technical,  financial,  and  business contact  information   is
   available.

   The clearinghouse can function at the national level of the country and can
   involve professionals from  leading  research and development  laboratories,
   educational institutes, industries,  and other organizations.  The clearinghouse
   can strengthen the existing infrastructure of national  and  regional  bodies
   involved in the training,  information  dissemination and implementation of the
   programs in energy efficient technology. It can also facilitate training programs
   and interactions with local and international experts.

   The clearinghouse can also assist in developing  the technical capabilities  of
   non-governmental organizations,  consultants, industry  associations, and any
   other groups engaged in  the promotion of energy efficiency activities. This can
   be done by conducting regular training programs  (both in  the field and in the
   classroom),  thereby exposing   the  participants  to  the  latest  tools and
   techniques.

-------
Next  Steps                                                                                    COAL GUIDELINES
                                     At a minimum, the information clearinghouse should contain information in the
                                     following areas:

                                     •       profiles of gassy mines;
                                     •       current technologies and new research;
                                     •       coal mine methane ownership laws;
                                     •       permitting requirement;
                                     •       applicable energy purchase rules (if any);
                                     •       international and domestic capital/funding sources; and
                                     •       government energy development policies.

                                     An automated index of all  materials  could  be made available electronically
                                     through a bulletin board, or as a "fax-back" system.  A collection of hardcopy
                                     materials could also be assembled for use by  anyone interested  in coal mine
                                     methane projects.  US EPA has helped establish three clearinghouses abroad.
                                     A description  of these clearinghouses along with their contact information is
                                     presented in Exhibit 6-5.
                                     6.4     Review Regulatory Framework

                                     Regulatory  barriers  are key obstacles facing  potential coal mine  methane
                                     projects in  many developing  countries and countries  with  economies  in
                                     transition.  In many of these nations, the regulatory frameworks do not address
                                     issues  related to coal  mine methane  recovery and use projects.  This is not
                                     unusual, given that such projects may be relatively new in these countries.

                                     There are many types of regulatory  barriers that a project may face.   For
                                     example, local,  state,  and national ownership and permitting legislation can
                                     obstruct coal mine methane projects.  Artificially low energy prices can  pose a
                                     barrier to coal mine methane utilization if the prices of alternative fuels are less
                                     than the cost of coal  mine methane.  Furthermore, in most developing  countries

-------
Exhibit 6-5: Coalbed Methane Clearinghouses
  The Polish Coalbed Methane Clearinghouse

The   Polish  Coalbed   Methane  Clearinghouse,
established in January, 1991, is part of the Polish
Foundation for  Energy Efficiency  (FEWE) and is
jointly sponsored by the FEWE and the US EPA.
The clearinghouse provides consulting services to
public- and  private-sector clients (e.g., assisting
contractors with pre-feasibility studies on directional
drilling and gob gas recovery), hosts  workshops,
and publishes journals, brochures, and newsletters
(e.g.,  the  Silesian  Coalbed Methane Newsletter).
Together,  EPA and  the  Polish  Clearinghouse
prepared  a report entitled  "Reducing  Methane
Emissions from  Coal Mines in Poland:  A Handbook
for  Expanding  Coalbed  Methane  Recovery and
Utilization  in the Upper Silesian Basin."  This report
profiles the top candidate mines in Poland.   For
more information, contact:

             Jan Surovka, Director
     Polish Coalbed Methane Clearinghouse
              ul. Powstancow41a
            40-024 Katowice, Poland
            48-3-10355114 (phone)
              48-3-10355120 (fax)
   Chinese Coalbed Methane Clearinghouse

The Chinese Coalbed Methane Clearinghouse was
established  in  August  1994  in  Beijing.   The
Clearinghouse is part of  the  Ministry  of Coal
Industry's  (MOCI) China Coal Information Institute
and is jointly funded by the MOCI and the US EPA.
Activities of the  Clearinghouse include  providing
consulting   services,   hosting  seminars   and
conferences,  and  publishing  the journal China
Coalbed Methane in both  English and Chinese.  In
a joint report with EPA entitled "Reducing Methane
Emissions from Coal Mines in China: The Potential
for   Coalbed   Methane   Development,"    the
Clearinghouse   has    profiled   coal    mining
administrations that have  the top candidate mines
for  coalbed  methane  projects.     For  further
information, contact:
           Mr. Sun Mayouan, Director
     China Coalbed Methane Clearinghouse
               21 Hepingli Beijie
                P.O. Box 1419
             Beijing 100713, China
            86-10-420-1328 (phone)
              86-10-421-5187 (fax)
          adb310@istic.sti.ac.cn (email)
   Russian Coalbed Methane Clearinghouse

The  Russian  Coalbed  Methane  Clearinghouse
opened  in 1995 in  Kemerovo.  It is located at the
Russian  Institute  of Coal  and is affiliated  with
Partners in Economic Reform (PIER) and the U.S.
EPA.  Like the other Clearinghouses, the Russian
Clearinghouse is  promoting the development of
coal  mine  methane  projects  by disseminating
information.  It assisted the U.S. EPA in preparing a
report entitled "The Potential for Coalbed Methane
Development" which includes  profiles of  the top
candidate  mines.   The  Clearinghouse  is  also
working  with EPA  to  develop a  demonstration
project at  the Kirov mine  (see box above).   For
further information, contact:
           Dr. Oleg Tailakov, Director
     Russian Coalbed Methane Clearinghouse
                Institute of Coal
                  Room 208
              Rukavishnikova 21
            Kemerovo 65061, Russia
        root@tailak.kemerovo.su (E-mail)

-------
Next  Steps                                                                     COALBED  METHANE GUIDELINES
                                     and  countries with economies in transition,  all  major  power and natural gas
                                     producers and distributors are or have been  State-owned.  Privatization of the
                                     energy  industry  is only recently occurring in many countries; therefore,  the
                                     concept of private, independent power producers or private gas producers may
                                     be unfamiliar  (Watts, 1995).   These, and  other  barriers, are discussed in
                                     Chapter 5.

                                     The following is recommended to review the regulatory framework for coal mine
                                     methane recovery and utilization:  identify and evaluate  existing regulations;
                                     develop feasible options for removing barriers that will not compromise other
                                     regulatory objectives; and implement the necessary changes.
                                     6.4.1 Evaluate Existing Regulations

                                     To  evaluate the existing situation, the relevant laws, rules, regulations, and
                                     policies must first  be  identified  and  summarized by  conducting  literature
                                     reviews and contacting  appropriate regulatory and legislative experts.   In
                                     addition, attention must be paid to  institutional arrangements.  The following
                                     steps should be undertaken:

                                     +      Step 1: Identify Decisionmakers.  The  purpose of  this step  is to
                                             identify the key decisionmakers involved in the approval of coal mine
                                             methane  projects.     These  decisionmakers  may  include  local,
                                             provincial,  or national regulatory  bodies  that  are  involved in  coal
                                             production,   land  ownership,  energy  production, financing,  and
                                             equipment purchasing/importing.

                                     +      Step 2: Identify Decision Criteria.  The purpose of this step  is to
                                             identify the decision criteria used by the key decisionmakers and the
                                             underlying  objectives they are trying to  achieve.   This  information
                                             would be  obtained  principally through contacts with the  relevant
                                             agencies and institutions in the country.

                                     ^      Step 3: Identify Typical Project Development Path. The purpose of
                                             this step is to describe the typical path that a  project would take in
                                             order to be developed. A concise  listing of the major steps in getting
                                             the project defined, approved, financed, and built should be developed
                                             based on discussions with the relevant institutions involved.   This
                                             summary of  the project development  path could then  be  used to
                                             promote the implementation of coal mine methane projects.

                                     The results of the above steps should be compiled in a concise summary report
                                     highlighting  the policies and current practices affecting gas recovery  and use
                                     the options available to the government to reduce the barriers to projects. Any
                                     policies or requirements that significantly add to the cost of the project, create
                                     uncertainty in the viability of the project,  or delay its implementation should be
                                     identified as major barriers requiring further analysis.

-------
COALBED METHANE GUIDELINES                                                                Next steps
   6.4.2 Develop Feasible Options

   The purpose of this section is to develop available options for overcoming any
   major barriers identified above. The options selected will be those that most
   effectively promote the government's development objectives and are feasible
   in terms of political  acceptance, effectiveness, secondary  impacts, costs, and
   legality.

   An Evaluation Team consisting of the decisionmakers and participants involved
   in coal mine methane recovery and utilization can be established as a working
   group to guide this process. This group would be charged with ensuring that
   the  recommended  options  incorporate the  views of  the  representative
   stakeholders in each area. At a minimum, the Evaluation Team should include
   the following groups:

   ^       Regulatory  Community:   municipal  agencies,  local  government
           regulators,  ministries in charge of power, coal, natural gas, and the
           environment, and others;

   +       Owner, Operator, and  Developer Community:  coal mine owners
           and operators, recognized  local, national, or international coal  mine
           methane project developers; and

   ^       Financial Community:  local, national, or international  grant/loan
           agencies and venture capitalists.

   The assessment of available options will involve considerable debate on which
   options can  be  implemented without compromising other  pressing  national
   priorities. As such, proposed regulatory changes must be viewed in the context
   of their impact on other national priorities.
   6.4.3 Implement Options

   Using the input and recommendations of the Evaluation Team, the options or
   optimum mix of options can be implemented. The implementation strategy will
   depend on  the type of option to be implemented.  Implementation  strategy
   options include, among others:

   •       legislative/regulatory actions (environmental, safety, ownership, import
           restrictions);

   •       administrative  and   executive   actions   (committees,   meetings,
           conferences);

   •       inter-governmental  liaison  actions (local,  municipal, national,  inter-
           national); and

   •       outreach (training programs, demonstration projects, etc.)

-------
                                                                                 COALBED  METHANE GUIDELINES
                                    The above options must be evaluated on an ongoing basis in  terms of their
                                    ability to promote promising projects.  A structured program of data collection
                                    for monitoring the progress of the objectives may be developed  in this regard.
                                    Once data has been collected, reviewed,  and analyzed, an evaluation of the
                                    impact  of the option  can  be made and  the  established objectives  can  be
                                    retained or modified as appropriate.
                                    6.5     Obtain  Project Funding

                                    Each of the  activities  discussed above requires resources,  as does the
                                    implementation of individual  projects.  This section lists steps for obtaining
                                    assistance from international funding  agencies for these initiatives.  The key
                                    steps  are  to  review  the types  of  assistance available, identify funding
                                    requirements, and select specific source(s) of funding.   Once the appropriate
                                    source of funding has been identified,  a project proposal can then be prepared
                                    in accordance with the specific criteria of the funding agency.
The  first  source  of  funding  that
countries should consider is forming a
partnership  with  local and  foreign
private   sector project  developers.
This method is often the quickest and
cheapest method of obtain funding.
However,  such  funding  is  only
available for projects that are clearly
profitable.  For projects with a lower
economic rate of return, funding may
be   available   from  international
agencies.
6.5.1 Review Types of Assistance Available

The  main types of assistance offered  by international funding  agencies are
grants, loans, and other packages (including loan guarantees, venture capital
funds, and business consulting assistance).  These types  of assistance are
available  to  both  governments  and  businesses.    In some cases,  the
government may  reallocate the  funds to eligible  businesses.   The  funds
provided may  cover  costs to conduct  feasibility  assessments, implement
demonstration projects, or  acquire equipment and technical expertise.  The
main types of financial assistance are further described below:

^      Grants.  These are direct monetary payments for specific projects that
        do not need to be  reimbursed.  For example, grants may be used to
        develop  a demonstration project or to fund  a training program to
        enhance local expertise.

^      Loans.  These are  made by the funding  agencies directly to the
        eligible parties and must be paid back in a specified period of time.
        Typical recipients  of such  loans may  be  government  agencies (for
        direct  use  or reallocation   to  businesses);  or  businesses  in
        manufacturing,  industrial  export/import  services,  or  technology
        development.

^      Other.    Loan  guarantees,  venture capital  funds,  and  business
        consulting services are some of the other types of assistance that are
        offered by these institutions. These are described below:

        •        Loan Guarantees are commitments to repay the lender if the
                 borrower  defaults.    In these cases,  a  funding agency
                 guarantees its proportionate share of loss in accordance with

-------
COALBED METHANE  GUIDELINES                                                                 Next  steps
                   the percentage of the guarantee.   Loan guarantees are
                   important to mitigate risk at projects that have a high degree
                   of uncertainty.

                   Venture Capital Funds offer loans or equity to support the
                   start-up  of new  businesses  or expansion  of  existing
                   businesses.  Funding  agencies may appropriate funds or
                   generate funds from private investors by selling shares in the
                   company.

                   Business Consulting Services include technical, managerial,
                   and  financial consulting   and  support services.    Typical
                   sources of such assistance are governments, multilateral and
                   bilateral  agencies,  and   business-  and  research-related
                   entities.   Technical  services may  range  from  providing
                   technology transfer to  providing engineering assistance to
                   offering  use  of  research   and  development  facilities.
                   Managerial   consulting   includes    offering    seminars,
                   workshops,   and  consultations  on  improving   project
                   operations.  Financial  consulting may involve  assistance in
                   creating packages to finance a project or group of projects.
   6.5.2 Identify Funding Requirements

   The type of funding required is driven primarily by two factors: the objectives of
   the program, and the country's resource allocation. These are briefly described
   below.

   +      Program Objectives. Government programs aimed at exploring the
           opportunities  for coal mine  methane  projects  (e.g.,  by conducting
           feasibility studies) would most likely seek grants  or other concessional
           funds.   On the other hand,  businesses and government  agencies
           pursuing profitable projects are eligible for loans, loan guarantees, and
           venture capital funding.

   +      Resource Allocation.   The  extent of economic  development and
           resource endowments for a given country will determine its financial
           requirements.   Countries with a  low  GNP per capita  will typically
           require  grants  to undertake  coal mine methane projects.   Some
           countries  may  face  difficulty when  securing  loans,  if they  have
           creditworthiness problems.

   Once the funding requirements have been assessed, the  next step is to  identify
   the funding available.

-------
Next  Steps                                                                    COALBED METHANE GUIDELINES
                                    6.5.3 Select Sources of Funding

                                    There are a wealth of possible funding sources which provide assistance that
                                    can  be used for coal mine methane projects.  These  include  multilateral
                                    institutions, regional development banks, U.S.  government agency programs,
                                    country- and region-specific enterprise funds, and other institutions.  Exhibit 6-5
                                    lists funding sources most applicable to coal mine methane recovery and use
                                    projects,  and summarizes the types of funding offered by each.   Summary
                                    profiles of  the funding agencies are presented  in  Appendix B.  The  main
                                    categories of funding sources are briefly described as follows:

                                    ^      Private  Sector.    Funding may be  available  from private sector
                                            associations or firms interested in coal mine methane recovery.  Such
                                            funding is most commonly  available for projects with  a high expected
                                            rates of return  and  usually  takes  the  form  of  a  profit-sharing
                                            partnership. This method is often the quickest and cheapest method
                                            of obtaining project funding.

                                    ^      World  Bank Institutions.  The  World  Bank institutions  fund
                                            environmental and   energy  infrastructure  projects  in  developing
                                            countries for which  the procurement of technical  assistance,  civil
                                            works, materials and equipment,  are necessary.  These agencies
                                            provide  grants and loans to  government ministries and businesses,
                                            which implement projects  under local procurement  and  contracting
                                            regulations.   Examples of  such institutions include  the World  Bank
                                            itself (also  known as the International Bank for  Reconstruction and
                                            Development), International Finance Corporation (IFC), and the Global
                                            Environment Facility (GEF).

                                    ^      Multilateral Development Banks.  These are  international lending
                                            institutions  owned by member countries that promote economic and
                                            social development in developing member nations by providing loans,
                                            technical assistance, capital  investment,  and help  with  economic
                                            development plans.   Examples of such institutions include the Asian
                                            Development Bank (ADB), the European Bank for Reconstruction and
                                            Development (EBRD),  and the Inter-American  Development  Bank
                                            (IDB).

                                    ^      U.S. Government Agency  Programs.    There are  several  U.S.
                                            government agencies that promote development by funding feasibility
                                            studies,  training programs,  and seminars in developing  countries. In
                                            most cases,  these  agencies/programs  support   projects  that  offer
                                            export or investment potential for U.S.  enterprises. Examples of such
                                            agencies/programs include the Trade Development Agency (TDA)
                                            and the Overseas Private Investment Corporation (OPIC).

                                    +      U.S. Initiative on Joint Implementation  (USIJI):  The  USIJI  is a
                                            voluntary  private program  that provides recognition  and select
                                            technical assistance to U.S. companies implementing  greenhouse gas
                                            reduction projects in other countries.  While no funding is available

-------
COALBED METHANE GUIDELINES                                                                Next steps
           through the USIJI, projects that meet the USIJI criteria will be likely to
           attract U.S. investors solely on the recognition of USIJI acceptance.

   For more information on the types of funding available and sources of funding
   for coal mine methane recovery and use projects contact:

                     U.S. Environmental Protection Agency
                              Methane Branch
                              Mail Code 6202 J
                             401 M Street, S.W.
                           Washington D.C. 20460
                             Tel: 202/233-9768
                             Fax: 202/233-9569

-------
Exhibit 6-5: Summary Table of Promising So
Name of Agency
urces of Funding and Other Assistant
Type of Assistance Provided
Grants
Loans
Other
;e
Comments
World Bank Agencies/Programs
International Bank of Reconstruction and
Development (IBRD)
Global Environment Facility
International Finance Corporation (IFC)









The World Bank finance capital infrastructure projects through the International Bank for
Reconstruction and Development (IBRD) and its affiliates - IFC, IDA, and MIGA.
GEF funds the difference between expected project revenues and project costs.
Therefore, GEF funding is ideal for conducting feasibility assessments.
IFC provides loans and other financial packages to private sector enterprises only. The
minimum support provided by IFC is $10 million.
Multilateral Development Banks
European Bank For Reconstruction and
Development (EBRD)
Inter-American Development Bank (IDB)
Asian Development Bank (ADB)
Africa Development Bank (AfDB)












EBRD provides loans, equity, and guarantees to Central and Eastern European
countries for developing into market-based economies.
IDB provides loans for development projects in Latin America and the Caribbean.
Grants are available for poorer member countries.
ADB provides loans for the economic and social advancement of member countries.
Concessional funds are available through special funds established by the ADB.
AfDB provides loans for the economic and social advancement of African countries.
Grants are available for the poorest countries through special funds.
U.S. Government Agency Programs
Trade Development Agency
United States Agency For International
Development (USAID)
Overseas Private Investment Corporation (OPIC)
Export-Import Bank (EXIMBANK) of the United
States
U.S. Initiative on Joint Implementation (USIJI)















TDA provides funding to projects in developing countries that offer export or investment
potential for U.S. enterprises. The average grant size ranges from $300,000 to
$400,000.
USAID's Office of Environment, Energy, and Technology assists in developing market-
based solutions to environmental problems in developing countries.
OPIC provides funding by facilitating U.S. private investment in developing countries
through loans, loan guarantees, and special services.
EXIMBANK provides loans and guarantees to foreign buyers of U.S. goods and
services. The bank finances up to 85% of the U.S. export value.
Projects that meet the USIJI criteria are likely to attract U.S. investors seeking to obtain
recognition and other amenities available to U.S. participants in the USIJI program.
This includes loan guarantees, venture capital funds, consulting services etc.

-------
COALBED  METHANE GUIDELINES
                                                                                               NEXT
    6.6  References

    Watts,  Robert  A.,  (1995)  Profitable Market  Opportunities  for  Pollution
            Prevention - International Market Opportunities,  Presentation for US
            EPA Atmospheric Pollution Prevention Division Forum, April 10, 1995,
            Washington D.C.
STEPS

-------

-------
COALBED METHANE GUIDELINES                                                Appendi>
    APPENDIX A: DIRECTORY OF SELECT COAL MINE METHANE RECOVERY AND USE
                                EXPERTS IN THE U.S.
                 Listing of experts does not constitute endorsement or recommendation for use.

-------
PROJECT DEVELOPMENT

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Name Address
Alternative Energy Development,
Inc.
Burns and Roe NIS Consortium
Dominion Energy Advisors
Energy Resources International,
Inc.
HVS Consulting
ICF Incorporated
ICMG / E.L. Lasseter &
Associates
I. Havyrluk and Associates
Murray & Associates
Resource Enterprises
United Energy Development
Consultants
8455 Colesville Road, Suite 1225
Silver Spring, MD 20910
1400 K Street N.W., Suite 910
Washington, DC 20005
14389 Emerald Pool Drive
Centreville, Virginia 22020
101 5 18th Street NW
Washington, DC 20036
4898 Hartland Parkway
Lexington, KY 40515
1850 K St., NW, Suite 1000
Washington, DC 20006
36 10 Watermelon Road
Suite 104
Northport, AL 34576
P.O. Box 252
Carnegie, PA 15106-0252
200 Union Blvd.
Suite 21 5
Lakewood, CO 80228-1830
1245 East Brickyard Rd.
Suite 170
Salt Lake City, UT 84106
Park West One, Suite 170
Pittsburgh, PA 15275
Contact Person
Mathew S. Mendis, President
Tel: (301)608-3666
John Leonhardt
Tel: (202)898-1500
Charles M. Boyer
Engineering Consultant
Tel: (703) 803-6007
David W. South
Vice President
Tel: (202)785-8833
Hilmar von Schonfeldt
Tel.: (606) 272-71 12
Mary DePasquale, Project Manager
Tel.: (202) 862- 11 24
Edward L. Lasseter
President
Tel: (205) 759-2046
Ihor Havryluk, President
Tel.: (412) 343-3285
Keith Murray
President
Jeffrey Schwoebel, Vice President
Tel. (801) 467-9981
Isaias Ortiz
Tel.: (412) 787-7880
Area(s) of Expertise
Project Development
Project Development
Project Development
Project Development
Project Development
Project Development; Gas Use
Gas Production, Project Development
Project Development
Project Development
Project Development, Gas Production and Resource Assessment
Project Development

-------
GAS PRODUCTION AND RESOURCE ASSESSMENT

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Name
Amoco Production Company,
Natural Gas (International)
Bureau of Economic Geology
University of Texas
CD Exploration, Inc.
Conoco, Inc.
CONSOL, Inc.
Enron Exploration Company
GeoMet, Inc.
Gustavson Associates
Halliburton Energy Services
ICMG / E.L. Lasseter &
Associates
Address
550 West Lake Park Boulevard
Houston, TX 77079-2696
University Station
BoxX
Austin, TX 78713-8924
5485 Beltline Rd. STE 280
Dallas, Texas 75240
P.O. Box2197
Houston, TX 77252
Route 1, Box 119
Morgantown, WV
1400 Smith Street
Houston, TX 77002
18263rd. Ave, North
Suite 301
Bessemer, AL 35020
5757 Central Avenue
Suite D
Boulder, CO 80301
Halliburton Center
Suite 2300, 5151 San Flipe
Houston, TX 77056
36 10 Watermelon Road
Suite 104
Northport, AL 34576
Contact Person
Bruce N. Erickson
Marketing Advisor
Tel: (713): 556 4128
Andrew Scott
Research Associate
Tel: (512)471-1534
James W. Akers
Mining Engihneer
Tel: (214)392-1880
John Oehler
Tel: (713)293-6292
Pramod Thakur
Tel.: (304) 983-3207
J. Bradley Williams
Director, Oil & Gas Ventures
Tel: (713) 853-4777
Bret Camp
Senior Vice President
Tel: (205)425-3855
John B. Gustavson
President
Tel: (303)443-2209
Bruce D. Thomas
Regional Technical Manager
Tel: (7 13) -624-2000
Edward L. Lasseter
President
Tel: (205) 759-2046
Area(s) of Expertise
Gas Production and Resource Assessments
Gas Production
Gas Production
Gas Production
Gas Production and Resource Assessment
Gas Production
Gas Production
Gas Production
Gas Production
Gas Production, Project Development

-------
GAS PRODUCTION AND RESOURCE ASSESSMENT
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Name
Jim Walters Resources, Inc.
LAND Energy, Inc.
Lapp Resources, Inc.
North American Drillers
Pennsylvania State University
Pocahontas Gas Partnership
Raven Ridge Resources, Inc.
Resource Enterprises
The River Gas Corporation
Taurus Exploration
Union Texas Petroleum
Address
P.O. Box 133
Brookwood, AL 35444
P.O. Box2185
Granbury, TX 76048
4900 Sportsman Drive
Anchorage, AK 99502-4169
Rt. 9 Box 106-C
Morgantown, WV 26505
Hosier Building
Pennsylvania State Univ.
University Park, PA 16802
P.O. Box 200
Mavisdale, Virginia 24627
584 25 Road
Grand Junction, CO 81505
1245 East Brickyard Rd, Suite 170
Salt Lake City, UT 84106
51 1 Energy Center Blvd.
Northport, AL 35476
2101 Sixth Avenue North
Birmingham, AL 35203-2784
1330 Post Oak Boulevard
P.O. Box 2 120
Houston, TX 77252-2120
Contact Person
Charles Dixon, Senior Vice President,
Engineering
Tel.: (205) 554-6 106
David Elliot
Tel: (81 7)- 326-2562
David W. Lappi
President Tel: (907)248-7188
Bill Maloney
President Tel: (304)291-0175
Jan Mutmansky
Tel: (814) 863-1632
Raja V. Ramani
Tel: (814) 863-1617
Randall Albert
Program Manager
Raymond Pilcher, President
Tel.: (970) 245-4088
Jeffrey Schwoebel, Vice President
Tel. (801) 467-9981
Joseph Stevenson
Vice President
Tel: (205) 759 3188
Walter Ayers, JR.
Senior Exploration Geologist
Tel: (205) 326-2774
R..D LoPiccolo
Project Manager
Tel: (713)968-2522
Area(s) of Expertise
Gas Production and Resource Assessment
Gas Production
Gas Production
Gas Production
Gas Production and Resource Assessment
Gas Production
Gas Production and Resource Assessment
Project Development, Gas Production and Resource Assessment
Gas Production
Gas Production
Gas Production

-------
GAS USE

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Name
Allison Gas Turbines
AquaTech Services, Inc.
Black Warrior Methane Corp.
Energy Systems Associates
Gas Separation Technologies
ICF Incorporated
International Fuel Cells
Michael Baker Engineering Group
Nitrotec Engineering
Northwest Fuel Development
Powerbridge
Solar Turbines Inc.
Address
P.O. Box 420
Indianapolis, IN 46206
P.O. Box 946
Fair Oaks, CA
P.O. Box 140
Brookwood, AL 35444
300 Gateway Two
Pittsburh, PA 15222-1402
1667 Cole Blvd.
Suite 400
Golden, CO 80401-3313
1850 K St., NW, Suite 1000
Washington, DC 20006
195 Governors Highway
P.O. Box 739
South Windsor, CT 06074
4301 Dutch Ridge Road
Beaver, Pennsylvania 15009
611-M Hammonds Ferry Road
Linthicum, MD
P.O. Box35833
Canton, OH 44735
3710 Rawl ins Street
Suite 1060
Dallas, TX 75219
818 Connecticut Ave, NW
Contact Person
R.F. Merrion, Director
Tel: (317)230-411
John Tait, Principal
Tel: (916) 723-5107
R.G. Sanders, President/ General
Manager
Tel.: (205) 554-6288
Roger Glickert
Tel: 412-392-2390
Jerry Comer
Tel: (303)-232-0658
Mary DePasquale, Project Manager
Tel.: (202) 862- 11 24
Fax:(202)862-1144
Murdo J. Smith
Tel: (203) 727-2269
Rebecca Rannich
Tel: (412)495-4042
Joseph D'Amico
President
Tel: (301) 636-7200
Dale R. Jesse
V.P. Engineering
Tel: (909) 736-1203
James R. Clemments
President
Tel: (214) 520-8177
Peter A. Carroll
Area(s) of Expertise
Gas Use
Gas Use
Gas Use
Gas Use
Gas Use
Project Development; Gas Use
Gas Use
Gas Use
Gas Use
Gas Use
Gas Use
Gas Use

-------
GAS USE


13.
14.
15.
Name

Stord, Inc.
UOP
Viking Systems
Address
Suite 600
Washington, DC 20006-2702
309 Regional Road South
Greensboro, NC 27409
13105 Northwest Freeway, Suite
600
Houston, TX 77040
20270 William Pitt Way
Pittsburgh, PA 15238
Contact Person
Vice President
Tel: (202) 293-4327
Jeff Johnson
Tel: (910) 668-7727
Ronald J. Buras
Account Representative
Tel: (713) -744-2881
Jack Saluja
President
Tel: (412)826-3355
Area(s) of Expertise

Gas Use
Gas Use
Gas Use

-------
APPENDIX B:  DIRECTORY OF POSSIBLE FUNDING
AGENCIES

Profiles of the following funding agencies are provided:
World Bank Agencies/Programs
  International Bank of Reconstruction and Development (IBRD)
  Global Environment Facility (GEF)
  International Finance Corporation (IFC)

Multilateral Development Banks
  European Bank For Reconstruction and Development (EBRD)
  Inter-American Development Bank (IDB)
  Asian Development Bank (ADB)
  Africa Development Bank (AfDB)

U.S. Government Agency Programs
  Trade Development Agency (IDA)
  United States Agency For International Development (USAID)
  Overseas Private Investment Corporation (OPIC)
  Export-Import Bank (EXIMBANK)

U.S. Initiative on Joint Implementation

-------
                                                                               COALBED  METHANE GUIDELINES
                                    International Bank of Reconstruction and Development
                                    (IBRD)
The World Bank, through its affiliates
IBRD, IDA, IFC,  and MIGA, provides
financial  assistance  to  developing
countries  for  social and  economic
development projects.
Overview:  The World Bank, established in 1945, comprises the International
Bank  for  Reconstruction and  Development (IBRD)  and its  affiliates:  the
International Development Agency, the International Finance Corporation (IFC),
and the  Multilateral Investment Guarantee  Agency  (MIGA).   155 member
countries have subscribed capital  to the Bank enabling it to finance its lending
operations primarily from its  own borrowing  in capital markets.  However, a
substantial  portion of  the IBRD's  resources also  come from the retained
earnings and the flow of repayment.

The World  Bank  finances capital  infrastructure,  such as roads and railways,
telecommunications, and port  and power facilities.   However,  the  Bank's
development strategy emphasizes investments that can directly affect the well-
being  of poor people in developing countries  by making them more productive
and integrating them as active partners in  the development  process.  The
Bank's efforts to reduce poverty  include investments to  improve  education,
ensure   environmental   sustainability,   expand   economic   opportunities,
strengthen population-planning,  health and nutrition  services, and develop the
private sector.

Criteria:  The IBRD's charter requires that it:  (1) lend for productive purposes
to stimulate economic growth  in developing countries; (2) pay due regard to the
prospects of repayments; (3) make loans to  governments or with guarantees
from the government;  (4) not  restrict procurement to purchases from any
particular member country;  and  (5) make  lending decisions  on economic
considerations alone.

The IDA provides assistance to poorer developing countries, i.e., those with an
annual per capita gross domestic product of  $580 or less, expressed in 1989
U.S. dollars. Terms of the IDA loans are less stringent than those of "regular"
IBRD loans.

The IFC is legally and financially a separate  entity.  Its purpose is to promote
growth in the private sector of the less developed country economies,  largely
by taking equity positions in projects (see profile).

The MIGA encourages equity investment and other direct investment through
the mitigation of  non-commercial  investment barriers.  MIGA  must: (1) offer
investors guarantees against non-commercial risks; (2) advise developing
member countries  on policies,  programs,  and  procedures related to foreign
investment; and  (3) sponsor a dialogue between the international business
community and host governments on investment issues.

Contact Information:  For further information, contact

                           The World Bank
                           1818 H Street, N.W.
                      Washington D.C. 20433  USA
                           Tel:  202/477-1234

-------
COALBED METHANE GUIDELINES
     Global Environment Facility (GEF)
     Overview: The Global Environment Facility (GEF), an organization established
     by the  United  Nations  Development  Program  (UNDP), the United Nations
     Environment Program  (UNEP),  and  the  World  Bank,  offers  grants  and
     concessional funds to developing countries for projects that are beneficial to the
     global environment.  GEF funds are used to cover the difference between the
     costs of a project undertaken with global environmental objectives in mind, and
     the costs of an alternative project that  the country would have implemented  in
     the absence of global environmental concerns. GEF resources are available  to
     projects that  address  the following  four areas:  climate  change, loss  of
     biological diversity, pollution of international waters, and depletion of the ozone
     layers.  Listed below are several types of projects that the GEF may fund.

     •        Technical  assistance  projects  focused on  human  development,
             capacity building, training, and information sharing;
     •        Feasibility  studies for investment projects and complex  technical
             assistance projects;
     •        Small grants for community-based grassroots organizations and non-
             governmental organizations in developing nations; and
     •        Grants  to investment projects  to  fund the incremental  costs  of
             achieving global environmental benefits.

     Criteria: The GEF has established general criteria for all areas in which it may
     fund projects, as well as criteria specific to each of the four areas. The general
     points which are assessed include:

     •        Potential to benefit the global environment;
     •        Contribution to human welfare and sustainable development;
     •        Financability of project without GEF support;
     •        Scientific and technical basis of project;
     •        Plans for evaluation and dissemination of results;
     •        Host nation political, legal, economic,  and administrative conditions
             under which the project must be executed
     •        Development of human and institutional  resources;
     •        Plans for post-GEF project continuation; and
     •        Involvement of local communities.

     Contact Information: For further information, contact the GEF at:

                    GEF Administrator, Environment Department
                                   World Bank
                               1818 H Street,  N.W.
                             Washington, DC 20433
                               Tel.: 202/473-1053
                               Fax: 202/477-0551
GEF will fund only those projects
which cannot pay for themselves, i.e.,
whose  project costs exceed project
revenues.  Therefore, GEF funding is
ideal   for   conducting   feasibility
assessments.

-------
 ppendix B                                                                     COALBED  METHANE GUIDELINES
                                     International Finance Corporation (IFC)

                                     Overview:  The  International  Finance Corporation  (IFC) was established in
                                     1956 to help strengthen the private sector in developing countries.  IFC lends
                                     directly to the private sector. IFC aids private sector development by providing
                                     long-term loans, equity investments, guarantees and "stand-by financing",  risk
                                     management and "quasi-equity instruments",  such  as subordinated loans,
                                     preferred  stock,  and income  notes.   IFC advisory services and technical
                                     assistance help private business increase their chances of success.   Other
                                     relevant information on IFC is as follows:

                                     •       Source of funds:  About 80% is borrowed  in the international financial
                                            markets through  public bond issues private placements and 20% is
                                            borrowed from IBRD;
                                     •       Lending:  Each year,  IFC  approves  about $4 billion  in  financing,
                                            including syndications and  underwriting for private-sector projects in
                                            developing countries.  The minimum amount of IFC support available
                                            is $10  million; and
                                     •       Loan Conditions:   Interest rate on IFC loans and financing  are based
                                            on market rates, which vary between countries and projects; maturity
                                            on loans ranges from 3 to 13 years.

                                     Criteria: Project  proposals will  be  assessed  on  the basis of  the following
IFC  will  provide  loans  and  other     information:
financial     instruments     (equity
investments, guarant- ees, etc.) to the     .       Project Descnpf/on: brief description of the project and current status;
pnvate  sector onfy.   The minimum     .       Sponsorship and Management  history  and business  of  sponsors,
support provided by IFC is $10 million.               r         ,           4     j  4  u  •  .           *
                                            management arrangements, and  technical arrangements;
                                     •       Markets and Sales: market orientation (export/domestic), production
                                            volumes  and  sales  objectives,  potential  users  and distribution
                                            channels, and relevant tariffs and protective measures;
                                     •        Technical Feasibility:  equipment availability, labor  and  infrastructure
                                            facilities, resource accessibility, and potential environmental  issues;
                                     •       Financing Requirements:  breakdown of  project  costs,  proposed
                                            financial plan, type of assistance sought, and expected profitability;
                                     •       Government Regulations: government controls,  exchange controls,
                                            tax regulations, export/import licences,  and price controls applicable to
                                            the project.

                                     Contact Information: For further information, contact the IFC at:

                                                         International Finance Corporation
                                                             1850 I (Eye) Street, N.W.
                                                             Washington, D.C. 20433
                                                               Tel.: 202/477-1234
                                                               Fax: 202/477-6391

-------
COALBED METHANE GUIDELINES
     European Bank for Reconstruction and Development
     (EBRD)

     Overview: The European Bank for Reconstruction and Development (EBRD) is
     a multinational institution  set up with the specific aim of assisting countries of
     central and eastern Europe to develop into market-oriented economies.  The
     EBRD provides financial assistance to both the private and public sector.  The
     types of financial instruments offered include: loans; equity and  quasi-equity
     investments; and guarantees.  Other information about EBRD financing:

     •        Minimum  Loan Amount The  minimum lending  requirement for  the
             Bank is ECU 5 million ($6.5 million, as of November 1995).
     •        Interest Rates: Interest rates  are set  at a  margin  over a market
             benchmark (usually LIBOR - London Interbank Offered Rate).  Loans
             can be either variable rate or fixed rate;
     •        Loan Term:  Maturities generally range from 5 to 10 years, depending
             on the individual operation requirements; and
     •        Currency: The EBRD lends  in hard currencies  -  US  dollar,  the
             Deutschmark, and the ECU.

     Criteria: The first step in the approval process is the Concept Clearance stage.
     Prospective borrowers approach the banking staff to advise on procedure and
     potential structuring options.  Based on  information on the scope of the project,
     financing requirements, and technical and economic/commercial aspects,  the
     Bank will determine whether the project fits within its guidelines and strategies.

     If the project  is cleared, a Mandate Letter, defining the legal requirements for
     entering  to a  relationship with the Bank, is signed and  an  Operation Leader is
     assigned as the  key  Bank contact for the project.  The next stage is the Initial
     Review which requires detailed project information, including:

     •        detailed description of the enterprise,  project, and key personnel;
     •        financial statements audited to  international standards;
     •        financial projections about the viability of the project;
     •        regulations applicable to the project; and
     •        assessment of the environmental impact of the project.

     Once the project has cleared Initial Review, it has to pass Final Review by the
     Bank's Operation Committee.  This evaluation process covers financial,  legal,
     economic, technical, and environmental issues.

     Contact Information: For further information, contact:
                          EBRD, One Exchange Square
                        London EC2A2EH,  United Kingdom
                              Tel:  44 71 338-6282
                              Fax: 4471338-6102
EBRD  provides  loans, equity,  and
guarantees to countries of central and
eastern Europe that  are developing
into market-based economies.

-------
                                                                                  COALBED METHANE GUIDELINES
                                       Inter-American Development Bank (IDB)
IDB provides loans to  governments
and private sector agencies for social
and economic development projects in
Latin America  and the Caribbean.
Grants   are  available   for  poorer
member countries.
Overview:  The  Inter-American  Development Bank  (IDB)  is  a multilateral
development  bank  created  to  help accelerate  the  economic and  social
development of its member countries in Latin America and the Caribbean. The
IDB provides the following  types of assistance to its member countries: loans
and  other  financial instruments; concessional funds for  needier  countries
(through  its  Fund  of  Special  Operations);  and technical assistance  to
strengthen  regional development institutions and help identify and implement
investment  projects.  Other  relevant information about the IDB is as follows:

•       Extent of Financing: The IDB finances a certain percentage of project
        costs, ranging from 50% for more economically developed countries to
        80% for poorer countries.
•       Loan Conditions: Interest rates on IDB loans and financing are based
        on market rates, which vary between countries and projects; maturity
        on loans ranges from 15 to 25 years.
•       Capital Resources: The IDB  has a capitalization of over $100 billion
        that can support a  level of annual lending of over $7 billion .

Typical borrowers of IDB funds include governments, ministries, or an agency
or utility under  a ministry. The borrower makes the key decisions on awarding
contracts for engineering,  design,  project management, works  construction,
and purchase of capital goods.  While governments and related  agencies are
the  primary recipients of IDB funds, private sector enterprises too are eligible
for some forms of assistance.

The  IDB has  an  Environmental  Division  that monitors the environmental
component of the  Bank's operations  and  develops  loans and  technical
assistance packages specifically directed towards protecting the environment.

Criteria: The following analyses are conducted to evaluate project proposals:
                                               Institutional:  borrower's administrative and  operational  capability to
                                               carry out the project;
                                               Technical: technical equipment, labor, and infrastructure required;
                                               Socio-economic: social and economic costs and benefits, impacts on
                                               trade, income distribution, production, and employment; and
                                               Environmental: environmental impacts of the project.
                                       Contact Information: For further information, contact:
                                                           Inter-American Development Bank
                                                             1300 New York Avenue, N.W.
                                                            Washington  D.C. 20577  U.S.A
                                                                  Tel: 202/623-1000
                                                                  Fax: 202/623-3096

-------
COALBED METHANE GUIDELINES
    Asian Development Bank (ADB)
     Overview: Established  in 1966, the Asian  Development Bank (ADB)  is a
     multilateral development bank whose primary objective is poverty  alleviation
     through sustainable economic growth in Asia.  The Bank has 35 developing
     member countries,  of which  China, India,  and Indonesia are the largest
     recipients.  ADB assistance is channeled into the following sectors: agriculture
     and agro-industry; energy; industry and non-fuel minerals; financial services;
     transport  and  telecommunications;  social  infrastructure  (e.g.,  education,
     health); and urban development.

     Typical borrowers of ADB funds include governments, ministries, or an agency
     or utility under a ministry. The borrower makes the key decisions on awarding
     contracts  for engineering, design,  project  management, works construction,
     and purchase of capital  goods.  While governments and related agencies are
     the primary recipients of ADB funds, private sector enterprises too are eligible
     for some forms of assistance.  For private sector support, a project must play a
     catalytic role in the development of the country.  For  such  projects, ADB
     assistance is limited to 50% of project costs or up to $50 million, whichever is
     less.  The minimum  loan  is $5 million.

     The financial  resources of the  Bank consist of ordinary capital  resources
     comprising subscribed capital from member  countries,  reserves and funds
     raised  through  borrowings;  and  Special  Funds,   including  the  Asian
     Development Fund, which is made up of contributions from member countries
     and other  accumulated  income;  and  the ALGAS fund, which is designed to
     support GHG mitigation activities in developing member countries.

     Criteria: The projects or programs are analyzed in terms of:

     •       the borrower's capacity to finance and administer the project;
     •       its economic, technical, and environmental feasibility; and
     •       its social and economic benefits to the recipient country.

     Contact Information: For further information, contact:

                            Asian Development Bank
                 Office of the Environment and Social Development
                      6 ADB Avenue, 1501 Mandaluyong City
                          0401 Metro Manila, Philippines
                              Tel.:  632/813-2148
                               Fax: 632/741-7961
ADB provides loans for the economic
and social advancement of developing
member  countries.    Grants  are
available   through   special   funds
established by the ADB (e.g., ADF,
ALGAS).

-------
                                                                                   COALBED  METHANE  GUIDELINES
AfDB provides loans for the economic
and social  advancement of African
countries. Grants are available for the
poorer  countries through the Africa
Development Fund  and the Nigeria
Trust Fund.
                                        African Development Bank (AfDB)

                                        Overview: The African Development Bank (AfdB) is a multilateral development
                                        bank whose primary objective is to finance economic and social development in
                                        African countries.  It achieves this objective through the provision of: loans and
                                        other financial instruments; technical assistance and institutional support; and
                                        mobilization of external resources for  investment in Africa.  Grants and other
                                        concessional funds are allocated for the poorest countries through the African
                                        Development Fund (ADF) and the Nigeria Trust Fund (NTF). The main criteria
                                        for defining the poor countries is GNP per capita.  The loan terms are as
                                        follows:
Terms
Interest Rate
Service Charge
Repayment Period
AfDB
Variable
1%
20 years
ADF
None
0.75%
50 years
NTF
4%
0.75%
25 years
The interest rate is reviewed every 6 months. As of June 30, 1995, the rate was 7.42%
Typical borrowers of AfDB funds include governments, ministries, or an agency
or utility under a ministry.   While governments and related agencies are the
primary recipients of AfDB funds, private sector enterprises too are eligible for
some forms of assistance.   For private sector support,  AfDB assistance is
limited to a third of project costs. The size of private sector loans are generally
in the $100,000 to $10 million range.

Criteria: The AfDB approves projects or program financing only on the basis of
appraisal reports prepared and submitted by the Bank's own staff,  even where
a project have been previously appraised by other co-financing  institutions.
The appraisal process accounts for the following:

•       the borrower's administrative  and operational  capability to carry out
        the project;
•       technical equipment, labor,  and infrastructure required and available;
        and
•       social and economic costs and benefits.

Contact Information: For further information, contact:

                       African Development Bank
                         01 BP 1387 Abidjan 01
                           Cote d'lvoire, Africa
                            Tel:  225/2041 18
                           Fax: 225/204006

-------
COALBED METHANE GUIDELINES
     Trade Development Agency (TDA)
     Overview: Established in 1980, the U.S. Trade Development Agency (TDA) is
     a government organization  that promotes U.S. exports by providing grants for
     feasibility studies for large development projects in developing and middle
     income countries. The purpose of these grants is to provide U.S. firms with the
     opportunity to undertake feasibility studies for large overseas projects, thereby
     increasing the chance that they will be involved in project implementation. TDA
     grants the funds on the condition that U.S.  firms are utilized to conduct  the
     study.  TDA is currently involved in: energy, environment, mining and minerals
     development,  health care, manufacturing, telecommunications,  transportation,
     water resources, agriculture, and aviation.

     There are two types of studies which the TDA may fund:  (1) feasibility studies
     for projects in which U.S. companies intend to make equity investments, and (2)
     feasibility studies for  public sector projects.   Before TDA funds a feasibility
     study, experts are hired to  develop reports regarding the feasibility study and
     the project to be implemented at the conclusion of the study.   If the TDA
     decides to fund the feasibility study, it asks interested firms to submit proposals.
     The host government decides which of the competing companies will undertake
     the study.

     The agency  may provide up to one million dollars per study, although  the
     average grant amount ranges between $300,000 and $400,000.  While up to
     20 percent of the TDA funding may be used  to pay subcontractors in the host
     country, the remainder must be used for services sourced in the U.S.

     Criteria:  All  feasibility study proposals must include the  following information:
     project description;  U.S. export  potential; information on host country partners;
     evidence  of the host  nation's commitment to the project; justification for why
     TDA  funding  is needed; a financial analysis  of the project; an assessment of
     foreign competition for project implementation; and the impact of the project on
     U.S. labor. A few of the most important criteria include:

     •       The project must be a development priority for the host country.
     •       The export potential  of the project must be significantly greater than
             the cost of TDA assistance.
     •       The procurement process must be open to U.S. firms.

     Contact Information:  For further information, contact the TDA at:

                           Trade  Development Agency
                                Room 309, SA-16
                          Washington, D.C. 20523-1602
                               Tel.:  703/875-4357
                               Fax:  703/875-4009
TDA will  provide grants to conduct
feasibility   studies   in   developing
countries  on  the condition that U.S.
firms be hired to conduct the  study.
The average  grant size ranges from
$300,000 to $400,000.

-------
                                                                                   COALBED METHANE GUIDELINES
                                        U.S. Agency for International Development (USAID)
USAID's    Office    of   Energy,
Environment,    and    Technology
provides   grants   and   technical
assistance to developing countries for
meeting    their    energy    and
environmental needs.
Overview:  USAID's Office of Energy, Environment,  and Technology assists
developing countries and emerging economies find market-oriented solutions to
their energy and  environmental  problems.  The Office's programs address
three  main issues:  1)  high rates of energy demand and economic growth
accompanies with lack of energy,  especially  in rural  areas;  2) financial
problems, including lack of investment capital; and 3) growing environmental
threats, especially global climate change, acid rain, and urban air pollution. The
Office focuses its efforts in the following areas:

•       Energy Efficiency
•       Renewable Energy Project Development
•       Private Sector Energy Development
•       Energy Technology Innovation
•       Training/Technical Assistance

The Office has two main strategies for achieving its objectives:
•       Tapping   U.S.   Know-how:  The  Office   arranges   cooperative
        relationships between developing  countries and  U.S.  energy and
        environment industries,  multilateral development  banks,  and  non-
        governmental organizations; and
•       Promoting Private Sector Initiatives: The Office assists countries put in
        place  market-oriented policies  and institutions to support private
        environment and energy  initiatives.

The types of assistance offered  include: financing (loans, investment funds);
policy,  legislative, and regulatory   development assistance;  reports and
workshops on market conditions and opportunities; and engineering and other
technical  assistance.

Criteria: The criteria for USAID fund varies on a case-by-case basis.  However,
the following points are generally considered in the project evaluation process:

•       Potential  of the project to meet its goals
•       Contribution to human welfare and sustainable development;
•       Scientific and technical basis of project;
•       Host nation political, legal, economic, and administrative conditions

Contact Information:  For further information, contact:

          U.S. AID: Office of Energy, Environment and Technology
                           Room 508,  SA-18
                      Washington  D.C. 20523-1810
                          Tel.: 703/528-4488
                          Fax: 703/528-2280

-------
COALBED METHANE GUIDELINES
     Overseas Private Investment Corporation (OPIC)
     Overview: OPIC is a  U.S.  government agency that  provides loans, loan
     guarantees, and  political  insurance  to American business ventures  in the
     developing world.   These services are provided to those projects  that are
     economically  and  technically sound but are  unable  to  receive  sufficient
     financing  or insurance from the commercial sector.  Projects supported  by
     OPIC must have a positive effect on  the U.S. economy, be financially sound,
     and provide significant benefits to the social and economic development of the
     host nation. While OPIC does not require the foreign enterprises to be owned
     entirely by U.S. interests, generally the U.S. investor is expected to own at least
     25 percent of the equity in the project.  Neither financing nor insurance will  be
     available  for investments  in business that are majority owned  by a foreign
     government.  Furthermore, only the portion of the investment made by a U.S.
     investor may be insured  by OPIC.

     OPIC's finance division offers loans and loan guarantees. Loans are generally
     granted to small U.S. businesses and range from $2 million to $10 million.  For
     larger  projects, in the $10 million to $75 million range, loan guarantees are
     provided.  OPIC's insurance division offers coverage against the following three
     risks:   currency inconvertibility,  expropriation,  and political  violence.  Other
     investor services provided  by OPIC include investment missions and outreach
     activities.

     Criteria: Eligible projects must meet the following criteria:

     •       Positive effect  on the U.S.  economy:  Projects must demonstrate
            positive balance of payments  and  employment effects on the U.S.
            economy;
     •       Development contribution:  Projects must benefit the economic and
            social development of the host nation;
     •       Performance requirements:  OPIC  will not become involved in any
            project subject to  performance  requirements  that will reduce the
            potential for U.S. trade and employment benefits.
     •       Environmental impact:  the project should not have  an unreasonable
            or major adverse impact on the host nation's environment; and
     •       Worker's  rights:    All  projects  supported  by  OPIC must  meet
            internationally recognized standards with regards to worker's rights.

     Contact Information: For further information,  contact OPIC at:
                     Overseas  Private Investment Corporation
                           1100 New York Avenue, N.W.
                             Washington,  D.C. 20527
                               Tel.: 202/336-8799
                               Fax: 202/408-9859
                     Fax-ion-Demand System: 202/336-8700
OPIC  will provide  loans  and loan
guarantees for projects in developing
countries  that US enterprises have a
stake  in.   The  project must have a
positive effect on the US economy.

-------
                                           COALBED  METHANE GUIDELINES
Export-Import Bank (EXIMBANK)

Overview: The Export-Import Bank (EXIMBANK) of the United States is a U.S.
Government agency that facilitates the export financing of U.S.  goods and
services to foreign buyers.   EXIMBANK supports export sales by providing
direct loans to foreign  buyers, guarantees to U.S.  and foreign  commercial
lenders for credit risk  protection, export credit  insurance,  to U.S. exporters
against failure of foreign buyers to meet payment obligations, and pre-export
financing for small business through its Working Capital Guarantee Program.

Relevant information about EXIMBANK loans includes:
EXIMBANK   provides  loans   and
guarantees to foreign buyers of US
goods and services.  The bank covers
up to 85% of the US export value.
•       Types of Loans: EXIMBANK provides both  direct and  intermediary
        loans'  Direct loans are Provided to fore'9n  buVers of U'S' exPortsi
        intermediary loans fund parties that extend loans to foreign buyers;
•       Interest  Rates:   EXIMBANK loans carry the lowest  interest rate
        permitted under the OECD Arrangement for the market and term. , this
        rate is the OECD Commercial Interest  Reference  Rate (CIRR), which
        changes monthly.   For relatively poor  countries,  lower interest rates
        loans are available; and
•       Extent of Assistance: Loan and guarantee programs cover up to 85%
        of the U.S. export value.

Criteria: Transactions are  evaluated in  terms  of the creditworthiness of  the
buyer, the buyers country, and the exporters ability to  perform.  In general  the
following information is assessed:

•       Financial Data: Balance sheets and income statements for the past 3
        years for the buyer and any guarantor(s);
•       Credit Data: at least two credit references are checked;
•       Technical   Feasibility:  technical  characteristics of   the   project,
        breakdown  of  costs,   project  scheduling,  participant  profiles,
        environmental aspects, etc.; and
•       Applicant and Exporter Data: Evidence of the  applicants  ability  to
        implement the requested loan or guarantee.

Contact Information:  For further information, contact:

                  Export-Import Bank of the United States
                       Credit Information Section
                       811 Vermont Avenue,  N.W.
                        Washington D.C. 20571
                           Tel:  202/377-6336
                          Fax:  202/566-7524
                 Fax -on-Demand system: 800/424-5201

-------
COALBED METHANE GUIDELINES
     U.S. Initiative on Joint Implementation (USIJI)
     Overview: The U.S. announced its Initiative on Joint Implementation (USIJI) in
     October 1993.  This voluntary pilot program provides recognition  and select
     technical  assistance  to  U.S.  greenhouse  gas  reduction projects  in  other
     countries. This program allows U.S. companies to reduce emissions at a lower
     cost than would be incurred by projects undertaken at home.  U.S. government
     agencies  involved  in  this  program  include the  Environmental  Protection
     Agency, the Department of Energy, the  Department of State,  the Agency for
     International Development, the Department of Commerce, and the Department
     of Agriculture, among others.

     The benefits of this program to U.S. participants include public recognition,
     including use of the USIJI logo and  media events, and technical assistance.
     This assistance may include help in obtaining host country acceptance of the
     project, identifying or developing  methodologies for establishing a greenhouse
     gas emissions baseline, and guidance on how to  monitor and verify emissions
     reduced or sequestered.  For foreign participants, the benefits may include
     technology  transfer,  investments  in technologies  that  benefit the  global
     environment as well  as the local economy,  employment opportunities and
     training, and local environmental benefits.

     Eligible program participants include U.S. citizens, U.S. companies,  and any
     U.S. federal, state, and local government entity.  Foreign partners may include
     private  citizens and public entities of all nations  that have ratified  the  United
     Nations Framework  Convention on Climate Change (UNFCCC).

     Criteria: Projects accepted into the USIJI program must:

     •       obtain host country acceptance;
     •       prove  that  the specific measures to reduce  or sequester greenhouse
            gases are being undertaken as a result of USIJI or in its anticipation;
     •       provide sufficient and reliable data to establish a baseline of current
            and future greenhouse gas emissions;
     •       provide for the tracking of emissions reduction or sequestration;
     •       allow for external verification of emissions reduction or sequestration;
     •       identify benefits or  negative effects  on the economic and social
            development of the host country and on the local environment.

     Contact Information: For further information, contact:
                              The USIJI Secretariat
                     600 Maryland Avenue,  SW Suite 200 East
                             Washington, D.C. 20585
                               Tel.: 202/426-0072
                      Fax-on-Demand System: 202/260-8677
Projects that meet the  USIJI criteria
are likely  to attract  US investors
seeking the  recognition  and  other
amenities available to  participants in
the USIJI program.

-------