Project XL Stakeholder Involvement Evaluation

              Draft Final Report
        For Participant Review and Comment
                                     U.S. EPA Headausrters Library
                                           Mail code 3201
                                     1200 Pennsylvania Avenue NW
                                        Washington DC 20460
                  May 2, 2000

-------
                                      CREDITS:

       This evaluation  report  was prepared based  on  interviews  with over  seventy-five
participants in Project XL stakeholder  processes. The names of these individuals are noted in
Appendix A of this report.

       Consultant  support  was  provided  under Contract 68-W4-0001  between  EPA and
RESOLVE, Inc. and Contract 68-W-99-010 between EPA and Marasco Newton Group, Ltd.
Under subcontract to RESOLVE and Marasco Newton Group, Michael Elliott of the Southeast
Negotiation Network, Atlanta, Georgia, served as principal investigator and author. Research
assistance was provided by Tony Giarrusso and Alison Nichols.

       The Project Officer was Katherine Dawes, of EPA's Office of Policy and Reinvention.
Eric Marsh, also of EPA's Office of Policy and Reinvention, assisted in the review and editing of
this report.
                                                                                              r
                                                                                              T

-------
                                        Table of Contents

        Credits	i

        Tabie of Contents 	ii

        Introduction  	1

               Stakeholder Involvement in Project XL 	1
               How do Stakeholder Involvement Processes Fit Into Project XL Decision Making? .... 2
               Approach to Evaluating Stakeholder Involvement for Project XL	3
               Brief Overview of the Eight XL Projects 	4
               Organization of this Report  	9

        Findings and Conclusions	10

               1. The Need for Flexibility	10
               2. Stakeholders' Expectations and Concerns  	15
               3. Barriers to Effective Stakeholder Involvement 	23

        Case Studies  	26

™      Andersen Corporation	27

        Atlantic Steel Summary	33

        CK Witco 	44

        ExxonMobil	49

        HADCO 	57

        Intel	62

        New England University Laboratories	67

        Vandenberg Air Force Base	77

        Appendices 	81

        Appendix A (List of Interviewees)	82

•        Appendix B (Research Method)	85

        Appendix C (Glossary) 	87

-------
f

-------
                                      Introduction

 Stakeholder Involvement in Project XL

        The U.S. Environmental Protection Agency initiated Project XL in March 1995. Project
 XL seeks to promote innovative initiatives that improve environmental performance at reduced
 cost. Sponsors of projects range from manufacturing facilities and university labs to municipalities
 and military installations. Each sponsor proposes an environmental management project that
 requires some flexibility in environmental regulations or procedures. All projects are therefore
 individually designed by project sponsors and reviewed by EPA personnel for inclusion into
 Project XL. If the project is approved, flexibility is afforded to project sponsors on an
 experimental basis, conditional on demonstration of expected environmental benefits.

        EPA seeks to ensure that modification of regulatory requirements or procedures will truly
 meet local needs while protecting the environment. To this end, EPA requires meaningful and
 organized participation on the part of stakeholders in all XL projects. Stakeholder involvement is
 a collaborative working relationship between sponsors - the organizations who propose the XL
 project - and people who believe they or their community could be affected by the project. EPA
 defines stakeholders as

        •  communities near the project,

        •  federal, state, tribal or local governments,

        •  businesses,

        •  environmental and other public interest groups, or

        •  similar entities.

        Such participation helps ensure that negotiations around specific projects remain open and
 accountable to the communities in which they are located. Stakeholder involvement requirements
 also help ensure that stakeholders with an interest in the proposed project have an opportunity to
 learn about the nature of the project,  identify issues that may have escaped the notice of project
 sponsors and regulators, and provide feedback regarding their concerns.1

       To assist project sponsors and stakeholders, EPA provides guidance as to who constitutes
 a stakeholder and what constitutes meaningful and organized participation. In the April 1997
Federal Register notice, EPA delineated stakeholders into three categories:

       • direct participants: stakeholders who work in partnership with the project sponsors to
          develop the project agreement in detail, either because they have legal authority to
          issue permits and rules necessary for implementation of the project (e.g., federal, state,
          local or tribal agencies or authorities) or because they have a strong interest in the
1 April 23, 1997 Federal Register Notice.

Draft for participant review:               Introduction - 1
Do not cite or quote.

-------
                                                                                                     r
 involvement was a Superfund site, and the suggestions were made in reference to the citizen
 involvement requirements of Superfund, rather than Project XL.

       EPA encourages, but does not require, involvement of stakeholders in the development of
 the proposal. Only one of the eight project sponsors discussed in this report actively involved
 stakeholders in developing the project proposal and the stakeholder plan. Thus, decisions about
 how to involve stakeholders are often made before stakeholders are involved in the process.

       The most active phase of stakeholder involvement occurs during the development of the
 Final Project Agreement (FPA). The FPA serves as the agreement amongst the signatories and
 delineates the specifics of the XL project. The FPA is negotiated amongst these "direct
 participants." Signatories typically include the project sponsor, EPA, and local and state agencies.
 Signatories can also include other stakeholders, although this is uncommon..

       Stakeholders are also involved in monitoring implementation of the FPA, and possibly in
 renegotiating clauses in the FPA as conditions change. Citizen and environmental stakeholders are
 typically less actively involved in this phase of the XL project.
Approach to Evaluating Stakeholder Involvement for Project XL

       In September 1998, a report entitled Evaluation of Project XL Stakeholder Processes was
prepared by RESOLVE, Inc. This report provided a review of the design and conduct of the
stakeholder processes at four of the initial XL projects to reach Final Project Agreements. For
each XL project reviewed, the report describes how stakeholders were involved in the drafting
and/or implementation of the Final Project Agreement, the stakeholder involvement model used
by company sponsors, and the level of stakeholder satisfaction with the process.

       Following completion of this initial evaluation, evaluators with the Southeast Negotiation
Network evaluated the eight XL projects presented in this report in 1999. The assessment
evaluates six new XL projects and further evaluates two projects previously documented by
RESOLVE. The cases were selected to clarify the purposes, techniques and impacts of
stakeholder involvement at the various stages of decision-making.

       At the start of the evaluation, the evaluation team selected two XL projects that were
developing their project agreements, two that had recently finalized their project agreements, and
four that had been implementing their project agreements for one year or more. For projects in the
process of developing their project agreements, the analysis focused on the initiation and early
dynamics of the stakeholder process. These case studies included:

       •  Atlantic Steel, and

       •  New England University Labs

       For projects that  had recently signed the Final Project Agreement (FPA), the analysis
focused on stakeholder satisfaction and the effectiveness of stakeholder involvement in the
process. These case studies included:


Draft for participant review:              Introduction - 3                     Do not cite or quote.

-------
o
   urban community and involving a wide range of development issues, governmental
   procedures, and constituencies. The stakeholder involvement process used by Jacoby
   focused on public meetings, with informal negotiations between Jacoby and specific
   stakeholders around issues of particular concern to those stakeholders.

•  CK Witco is a chemical specialties manufacturer. The facility is located on an 1,300
   acre site in rural West Virginia. The CK Witco XL project seeks to reduce air
   emissions and to promote waste minimization in order to reduce hazardous air
   emissions. CK Witco's stakeholder involvement process included community outreach,
   and the inclusion of two community representatives on the project negotiation team.

•  ExxonMobil (Sharon Steel Superfund Site) involves the cleanup of a Superfund site.
   The proposal describes an alternative strategy for investigation, risk assessment,
   remedy selection and remediation of the site. Using an administratively streamlined
   process, ExxonMobil hopes to clean up the contaminated site in half the time of
   traditional cleanups and at less cost. Additionally, ExxonMobil is working with
   stakeholders to locate businesses interested in redeveloping the site. ExxonMobil
   involved stakeholders through a community advisory committee.

•  HADCO is a leading manufacturer of printed wiring boards (PWB) and electronic
   interconnection products, located in New Hampshire,  New York and elsewhere. As a
   PWB manufacturer, HADCO generates wastes that are classified as hazardous waste
   under the Resource Conservation and Recovery Act (RCRA). Since the wastewater
   sludge produced fay HADCO's operations is classified as hazardous under RCRA, it
   must be shipped to a third-party processor before it can be sent to a smelter for
   reclamation of the valuable copper contained within. HADCO seeks a conditional
   delisting of the sludge that would allow them to bypass the third-party processor and
   ship the wastes directly to an approved smelter. Efforts to involve stakeholders proved
   difficult, and little participation was achieved in this project.

•  Intel, a large semiconductor manufacturer, produces Pentium microprocessors and
   other state-of-the-art computer chips. Located in Chandler, Arizona, in the Phoenix
   metropolitan area, the FAB-12 facility is a state-of-the-art facility. The FPA provides
   for a facility-wide cap on various air pollutants.  The facility-wide cap replaces
   individual permit limits for different air emissions sources. The FPA also limits  water
   use and waste generation. Intel designed and implemented a consensus building
   process to involve stakeholders in the design and implementation of the FPA.

•  New England University Labs seek to develop flexible performance-based standards
   for managing university laboratory hazardous waste. The project is designed to
   develop and implement an integrated Environmental Management Plan (EMP) for
   managing hazardous lab waste at three universities (Boston College; University of
   Massachusetts, Boston; University of Vermont). These laboratories typically use small
   quantities of many different chemicals. A management plan to control their use and
   disposal offered environmental advantages relative to the traditional regulatory
   requirements set forth in the Resource Conservation and Recovery Act (RCRA). The
   New England University Labs employed two distinct stakeholder involvement
     Draft for participant review:
                              Introduction - 5
Do not cite or quote.

-------
        Table 1 provides an overview of the primary7 characteristics of these XL projects.
                                                                                                                f
- - .. . . .- . • •.-.Table 1 • :. - .•. : ..... - '• :;
Eight XL Projects Evaluated: Location, Status and Format of Participation

XL Project &
Location

Andersen
Corp.
Bayport, MN
/•_,..„ n
(ruraij
Atlantic Steel
Atlanta, GA
(urban)




CK Witco
(OSi
Specialties)
Sistersville,
WV (rural)
ExxonMobil
Fairmont, WV
(rural)

HADCO
Owego. NY
0 f
Deny and
Hudson, NH
(small town)
Intel
Chandler, AZ
(suburban)

Year of Initial
Project XL
Proposal and
Project Status •
as of June
1999
1997

Activity of
Project
Sponsor

window
FPA recently < manufacturing
finalized ,


1998
Developing
FPA




1995
FPA finalized
over one year
previously

1998
FPA recently-
finalized

1995
FPA finalized
over one year


1995
FPA finalized
over one year 1
previously ;


redevelopment
of 138-acre
brownfield site
located in a
central city


chemical
specialities
manufacturing

Environmental
Benefit of
Project

reduce air
emissions; reuse
waste materials


redevelop
brownfield site;
minimize
transportation-
induced air
pollution and
urban sprawl
reduce air
emissions;
pollution
I prevention

Superfund
remediation

printed wiring
board
manufacturing

:
computer chip
manufacturing

*•
1 ;
i

more timely and
efficient
Superfund
cleanup
hazardous waste
delisting; material
reuse


pollution
prevention;

Format for Participation

Direct dialogue within a 15-
person Community Advisory
Committee composed mostly
of citizens

Public meetings, with written
and oral comments; several
interactive workshops
sponsored by stakeholders
other than the project
sponsor

Public meetings and an
informal XL project team
that included two citizens


Direct dialogue within a 25-
person stakeholder panel
composed mostly of citizens

Primarily direct negotiations
between project sponsor and
government agencies


Direct dialogue and
consensus building within a
reduce air i stakeholder negotiation
emissions: j group that included four
i . .
increase water ! citizen members

reuse '
Draft for participant review:
Introduction - 7
Do not cite or quote.

-------
third, can we identify specific characteristics of stakeholder involvement processes that contribute
to or block effective involvement and satisfaction with that involvement?

       These questions frame our evaluation of the Project XL stakeholder involvement
processes. What, then, are our findings and conclusions with respect to these questions?
Organization of this Report

       The remainder of this report first presents the findings and conclusions that emerged from
our evaluation of the XL project stakeholder involvement processes. Following this discussion,
the report presents more detailed project descriptions and assessments for each of the eight XL
project studied. A list of interviewees, a description of the research method, and a glossary of
terms is presented in the appendices.
Draft for participant review:
                                    Introduction - 9
Do not cite or quote.

-------
                             Findings and Conclusions
       The findings and conclusions of this report are presented with reference to the three major
questions raised above. First, we examine the need for flexibility in the design of stakeholder
involvement processes, and the implications of this on EPA policy and guidance efforts. Second,
we examine the degree to which involvement processes afford stakeholders opportunities to
participate consistent with their expectations, concerns and stake in the outcome. And, third, we
identify specific characteristics of stakeholder involvement processes that contribute to or block
effective involvement and satisfaction with that involvement.
1. The Need for Flexibility

       To what degree should EPA policies and guidance documents prescribe specific
approaches to stakeholder involvement? The eight case analyses indicate that projects are highly
diverse in context and levels of complexity and concern. For stakeholder processes to respond
effectively to these varying conditions, the policies developed by EPA need to provide for a wide
latitude of processes. At the same time, this flexibility increases the responsibility of EPA project
coordinators to ensure that the design and implementation of stakeholder processes are consistent
with the objectives of meaningful involvement.

       1.1 EPA policies and guidance documents provide considerable latitude in the
       design of XL project stakeholder involvement processes.
       Guidance documents set a goal that the process of strategy development "engages those
parties affected by environmental regulations and policies in an unprecedented effort to find
solutions that work better." EPA Project XL guidance documents describe three levels of possible
involvement for stakeholders to participate in an XL project:

       •  direct participants who engage in  the day-to-day negotiations,

       •  commentors who have a direct interest in the project but who do not participate in
          day-to-day negotiations or project development, but instead provide written or oral
          comments, and

       •  the general public, who are to be provided clear access to information on project
          development and results.

       Thus Project XL envisions a range of possible roles,  with differing levels of participation.
At one extreme are stakeholders who "negotiate," while at the other extreme are stakeholders
who have "clear access to information."  In the middle, commentors have access to information
and can present their perspectives. Alternatively, we can describe these three roles as each based
on the following forms of communication:

       • two-way communication (including weakly consultative,  strongly consultative, joint
         problem solving, and consensus building processes),

Draft for participant review:               Findings -10                     Do not cite or quote.

-------
    provide overall guidance while permitting considerable latitude in process design therefore seems
    appropriate.

           1.3 EPA policy, while providing flexibility to process design, does not delineate
           criteria for determining which stakeholders should be afforded what levels of
           involvement. This can engender significant tension when the expectations of the
           stakeholders for involvement in the process  exceed the willingness of project
           sponsors to involve these stakeholders.
           Given the broad policies established by EPA, how does EPA ensure that individual XL
    projects meet the fundamental goal of involvement processes, namely to develop a collaborative
    working relationship between Project XL sponsors and people who believe that they or their
    communities might be affected by these projects? What happens when the expectations of the
    sponsors differs significantly from the expectations for involvement held by stakeholders?

           Project XL stakeholder involvement processes are designed and implemented by the
    project sponsors. Project sponsors are the companies or governmental agencies who seek the
    regulatory flexibility afforded by XL projects. Within the eight XL projects evaluated for this
    report, over half of the sponsors developed involvement processes that primarily sought to share
    information with stakeholders, while a smaller number sought to promote dialogue or to build
    consensus with stakeholders. In most cases, the differences in levels of involvement bear a
    reasonable relationship to the context and preferences of the stakeholders for participation. But
    the cases also show that the predilections of the sponsors to involve stakeholders, as well as the
    ability of the sponsors to design and manage more complex forms of participation, also play an
    important role in shaping the levels of participation.

            As we will discuss in more detail below, given the broad criteria set forth in EPA policy,
    sponsors design stakeholder involvement processes primarily to meet the sponsors' need to build
    relationships of cooperation with their communities, public agencies, and the EPA. The need to
    build cooperative relationships therefore depends not only on the  issues raised by the XL project
    and the community's concerns with these issues, but also on the capacity of the sponsors to
    design effective participation processes (in a situation where most sponsors have never designed a
    community involvement process before), as well as the sponsor's  assessment of the political need
    for cooperation.

           At the same time, the broad criteria embedded in EPA policy helps contribute to overly
    high expectations on the part of some stakeholders as to their influence over project decisions. No
    XL project sought the consensus of all stakeholders in developing the Final Project Agreement.
    Most limit the core negotiations to the company, government agencies and possibly a few key
    stakeholders. Only  one was broadly inclusive in a process clearly designed to build consensus.
    Yet, when a project involved stakeholders who believed that they had a large stake in the
    outcome,  it was not uncommon  for these stakeholders  to expect considerable influence over the
    outcome.

||          These differences between sponsor and stakeholder expectations are by no means unique
    to Project XL. Differences in interests often lead to differences in  perception and expectations in
    stakeholder involvement processes. Yet two aspects of this problem stand out.  First, greater


    Draft for participant review:               Findings - 12                      Do not cite or quote.

-------
       1.5 EPA minimum standards for stakeholder involvement, particularly as
       interpreted by the regional XL project coordinators, appear to be the most
       important external impetus to the sponsor for designing more meaningful processes
       of participation.
       Often, EPA personnel felt that more full participation would have been desirable. These
personnel actively encouraged greater efforts to reach out to additional  stakeholders, at times
suggesting specific types of stakeholders that could be included. From time to time, EPA
personnel also suggested when and why projects sponsors should hold meetings, as well as the
format for those meetings. Project sponsors usually implemented EPA suggestions, at least in
part.

       But while EPA project coordinators felt that they could encourage more extensive forms
of participation, the project sponsor remained solely responsible for the design and
implementation of the stakeholder involvement process. EPA personnel felt free to enforce
minimal standards of acceptability, but hesitant when it came to insisting on levels of participation
not clearly required in the guidance documents. Several reasons exist for this hesitancy.

       •  First, Project XL is a voluntary program, and as such the project proponent is
          voluntarily accepting responsibility to design the project agreement and to initiate and
          maintain the stakeholder involvement process.

       •  Second, the stakeholder processes may well be subject to the Federal Advisory
          Committee Act (FACA) if initiated and managed by EPA. FACA requirements would
          be cumbersome and difficult to apply in the experimental projects that XL is designed
          to attract.

       •  Third, Project XL coordinators are more concerned with developing strategies that
          improve the environment while lowering costs of compliance than they are with
          promoting stakeholder involvement in environmental decision making for its own sake.
          Participation helps legitimize the projects and provides forums where concerns can be
          raised. Beyond assuring that the process is open and transparent, then, EPA personnel
          mostly seek to assure that XL projects do not generate high levels of opposition. In the
          absence of controversy, EPA project coordinators are less likely to strongly
          encouraged more extensive forms of participation.

       What can be done to balance  these conflicting concerns within EPA? To begin with, EPA
has already made significant progress in clarifying the role of stakeholder processes in XL project
development, and in providing clearer guidelines for process design and implementation. In
September 1998, EPA released its first report of XL stakeholder involvement entitled Evaluation
of Project XL Stakeholder Processes. Based on this report and additional stakeholder input, in
1999 EPA released the Project XL Stakeholder Involvement: A Guide for Sponsors and
Stakeholders. These documents , as well as in the future this report, will help EPA personnel and
project sponsors clarify the goals and processes employed to promote stakeholder involvement.

       In addition, together with the project sponsors and the regional EPA project coordinators,
more active EPA Headquarters review  of the stakeholder process designs  may help build
institutional capacity to promote more effective involvement. Currently, few project coordinators
Draft for participant review:
Findings - 14
Do not cite or quote.

-------
Table 2
Relationship Between Desire to Participate and Focus and Format of Participation
XL Project
Andersen Corp.
Atlantic Steel (Jacoby)
CK Witco (OSi
Specialties)
ExxonMobil
HADCO
Intel
New National
England Process
University
Labs
Local
Processes
Vandenberg AFB
Stakeholder
Desire to
Participate
moderate
very high
low
moderate
very low
very high
high
low
low
Focusof
Involvement
Process
Information sharing
and consultation
Information
sharing, with some
ad hoc negotiations
with specific
stakeholders
Information sharing
Information
sharing, with some
focus on joint
problem solving
Government agency
negotiations
Consensus building
Joint problem
solving
Information sharing
Information sharing
Format for Participation
Direct dialogue within a 15 -person
Community Advisory Committee
composed mostly of citizens
Public meetings, with written and
oral comments; several interactive
workshops sponsored by
stakeholders other than the project
sponsor
Public meetings and an informal XL
project team that included two
citizens
Direct dialogue within a 25-person
stakeholder panel composed mostly
of citizens ;
i
Primarily direct negotiations
between project sponsor and
government agencies
Direct dialogue and consensus
building within a stakeholder
negotiation group that included four
citizen members
Problem solving workshops and an
email list server involving research
labs
informal meetings with university
personnel and various forms of
public outreach to communities
located around the universities
Presentations to pre-existing
environmental citizen committees
Draft for participant review:
Findings - 16
Do not cite or quote.

-------
 project sponsors initiated community advisory panels to focus community involvement on issues
 raised about the projects. Although the panels were clearly advisory, they allowed for ongoing
 information-sharing and dialogue between community representatives and the companies. Most
 interviewees indicated that while they had originally expected a more consensus-oriented process,
 the emphasis on information sharing and consultation were acceptable. However, a few
 participants indicated that the advisory nature of their involvement discouraged participation on
 their parts, or discouraged other stakeholders from actively participating, thereby muting
 opposition to the project.

        The most vocal concerns about the participation process were raised in the Atlantic Steel
 and Intel processes. Both projects raised issues of significant concern to stakeholders and, in
 response, stakeholders made large demands for participation. In neither case were the
 expectations of stakeholders met. Interestingly, of the eight processes studied, the Intel process
 was probably the most effectively designed process and the most oriented toward consensus
 building. In this case,  dissatisfaction seems to spring primarily from stakeholder concerns about
 the degree to which their participation affect the specifics of the project agreement, as well as
 more general concerns about the appropriateness of affording regulatory flexibility to Intel, rather
 than from concerns about the design and implementation of the participation process per se.
 Atlantic Steel, on the  other hand, generated  considerable objections to the design and
 implementation of the participation process because while  it offered opportunities for information
 sharing and comments, it did not meet the expectations of stakeholders for more meaningful
 involvement.

       Finally, in one process (the national New England Labs process) stakeholders came to a
 high level of consensus with the project sponsors. However, EPA requested important revisions
 to the proposed agreement proposed by the  sponsor. Participants in the national process consisted
 largely of representatives of university and private research labs. Interviewed participants were
 largely supportive of the involvement process, including the interactive workshops and list serve
 email systems. However, a number of stakeholders expressed dissatisfaction with the outcomes of
 the process and the resulting FPA. For the most part, these participants felt  that EPA had limited
 the project agreement by too narrowly restricting the flexibility afforded to the project, thereby
 limiting the value of what the labs considered to be an "experiment." In addition, the long
 negotiations between the project sponsors and EPA created difficulties with managing the national
 participation process.

       From these cases, we can conclude that satisfaction with the participatory process in these
 projects depended primarily on three variables:

       •  the willingness of project sponsors to involve stakeholder at a level consistent with the
          stakeholders'  concerns and expectations,

       •  the consistency between the stakeholder's expectations as to their influence over
          decision-making and the stakeholder's  perception about their actual impact, and

       •  the level and efficiency of effort required to participate.

These variables are explored more fully in Table 3 below.
Draft for participant review-
Findings - 18
Do not cite or quote.

-------
        As is shown in Tables 2 and 3 above, project sponsors rarely design interactive processes
 of participation in communities unless demand for participation is moderately high. In
 communities where desire to participate is low, sponsors have little incentive to actively engage
 stakeholders. Even if they try, response is sporadic.  Typically, XL projects in which stakeholder
 interest in participating is low are located in rural communities or are dispersed across many
 communities. These facilities are often physically isolated from neighbors, with relatively little
 potential for negative impacts as a result  of the XL project.

        On the other hand, projects that elicit a high degree of community concern and that have
 greater potential for negative impacts on stakeholders do not necessarily develop processes that
 encourage greater participation. Stakeholder involvement is also linked to the local and regional
 politics of the project. Sponsors of complex and potentially conflictual projects (such as Atlantic
 Steel) may well design processes that bifurcate stakeholder in ways that allows for more direct
 involvement of parties with the power to block the project, and less direct involvement of
 impacted stakeholders who lack that power. Project sponsors have incentives to bifurcate
 participation processes because 1) the financial and time resources needed to design and
 implement a well-integrated participation processes increases with the number of stakeholder
 groups and the complexity of the issues and 2) integrated processes may provide a forum that
 legitimizes concerns of groups that may otherwise have little voice in the process.

        From the cases examined, sponsors  are most likely to design interactive, dialogue-based
 forums for participation when:

        • the proposed project affects a  clearly recognizable community of stakeholders,

        • those stakeholders are capable of organizing, and

        •  the stakeholders are important constituencies of the project sponsor.

        2.4 In several projects, it was clear that neither the project sponsors nor EPA
        personnel involved in the projects had specific training or experience in developing
        stakeholder involvement processes. In these cases, project sponsors designed
        involvement processes that lacked clear structure and objectives, were reactive
        rather than proactive, and fostered stakeholder expectations that were inconsistent
        with process design.
        Challenges to the design and implementation of participation processes are many. XL
 projects often involve specialized issues, technical knowledge and dispersed impacts. Stakeholder
 groups can be varied and unfamiliar with each other. The project and timetable are often difficult
 to predict and manage. The goals of processes also vary.

       Yet, despite the variation of contexts and goals, XL participation processes need to exhibit
 several characteristics if they are to promote acceptance of project agreements and satisfaction
 with participation processes. These include:

       •  clear presentation of the intent of the sponsor as to the purpose of the process and its
          impact on decision making,
Draft for participant review:
Findings - 20
Do not cite or quote.

-------
       At the same time, we should note that EPA now uses guidance resources more extensively
 with newer XL projects. In addition, as noted above, EPA has significantly refined its guidance
 documents for supporting involvement process design and implementation. These materials were
 published at the same time as this evaluation project was conducted, and hence were not available
 to the eight XL projects discussed in this report.
Table 4
Design of the Participation Process
XL Project
Andersen
Corporation
Atlantic Steel
Site (Jacoby)
CKWitco(OSi
Specialties)
ExxonMobil
(Sharon Steel
Superfund Site)
HADCO
Intel
New England
Labs (national
process)
New England
Labs (local
processes)
Vandenberg Air
Force Base
Stakeholders
systematically
identified?
^
o
3
•
O
9
?
3
3
Issues
systematically
identified?
3
3
3
9
3
•
•
3
3
Process goals
and steps
clearly
articulated?
3
O
3
«
O
9
3
O
3
Process
facilitated by
neutral?
9
(5
O
«
o
•
•
o
(3
scale: ('"Mow (^ moderately low (^ moderate ^Mhigh ^fc very high
Draft for participant review:
Findings - 22
Do not cite or quote.

-------
that low stakeholder interest is correlated with less organized participatory processes, but which is
cause and which is effect remains difficult to determine for these limited number of cases.

       3.3 Efforts to keep the XL project meetings focused exclusively on XL issues created
       considerable frustration on the part of stakeholders when those stakeholders were
       primarily concerned with community issues associated with, but not directly caused
       by, the XL project.
       At times, stakeholders,  sponsors and EPA cannot easily distinguish between issues that are
under the prerogative of XL and those that are not. For example, conceptual models of urban
design were included in the analysis for the Atlantic Steel project, while specifics about urban
design were excluded for discussion because they were viewed as beyond the scope of the XL
process. At other times, Project XL participatory processes provide an opportunity for
stakeholders to raise concerns that are not directly related to the XL project. For example,
stakeholders from local communities in the New England Labs project were primarily concerned
with university impacts on neighborhoods (such as student activity and noise) rather than the
management of hazardous wastes in the labs.  Similarly, stakeholders in the  Andersen project
voiced general concerns over the impact of Andersen on its neighbors. In each of these cases,
stakeholders were frustrated by the inability of the process to address issues of concern.

       By comparison, in the ExxonMobil  case,  the process allowed discussion of and worked to
address ancillary community concerns. This contributed to overall stakeholder satisfaction.
However, this approach raises its own concerns.  A state agency representative, for example, felt
that the process should have been more focused on issues central to Project XL, in order to
reduce the amount of time taken up by the process.

       3.4 Most processes did not actively involve national groups. Moreover, in those
       projects where national groups were included, the interaction between the local and
       national groups was very limited.
       National stakeholder groups were explicitly concerned with three of the XL projects
explored in this report:  Intel, Atlantic Steel, and New England Labs.  In all of these cases, national
groups were involved as commentors, and did not participate in stakeholder involvement or public
meetings. While the comments  made by national groups were at times useful to local stakeholders
in clarifying issues, in none of these cases did national  and local stakeholders participate together.

       In the Intel project, a national group requested more active participation as a participant
on the stakeholder negotiation team. Participation by the national stakeholders was allowed on a
limited basis. The national organization, however, refused to sign a confidentiality agreement with
Intel, a requirement for participation that was agreed to by all local stakeholders. This effectively
blocked participation by the national group.

       In Atlantic Steel, the sponsor worked directly with larger environmental groups to
determine and address their concerns outside the local public meeting process. Finally, in the New
England Labs project, the sponsor designed three distinct participation processes, one for national
stakeholders, one for university stakeholders,  and a third for local community stakeholders.
Draft for participant review:
Findings - 24
Do not cite or quote.

-------
Case Studies

-------
                               Andersen  Corporation
 Project Background
       Andersen Corporation, a window and door manufacturing company, is located in
 Washington County, Minnesota. The manufacturing facility is located near the towns of Bayport
 and Stillwater, with 3,500 and 15,000 residents respectively. About half of the adults in this
 region either currently work or have worked for Andersen in some capacity.

       In early 1998, Andersen submitted an XL project proposal to the EPA. The final project
 agreement was signed on June 30, 1999. Under the agreement, Andersen will reduce their air
 emissions of volatile organic compound (VOC) emissions per standard unit of production. This
 performance-based regulatory approach seeks to provide incentives for Andersen to improve their
 environmental performance. Specifically, The agreement encourages Andersen to:

       • manufacture more of its windows from wood fiber and vinyl to reduce its use of virgin
          materials;

       • experiment with the recovery of window components by removing paint, processing
          any lead in the paint for reuse, and using the recovered wood to produce new
          windows;

       • substitute low-solvent processes for solvent-based coating and wood-preservative
          processes to reduce air emissions, and

       • develop greater production efficiencies and emission improvements.

       Although the Andersen XL project is currently in implementation, this analysis focuses
 upon stakeholder satisfaction and the effectiveness of the stakeholder involvement process used
 during the development of the FPA.

       Stakeholders interviewed for this report are listed in Appendix A. Interviewees included
 participants representing the community, Andersen Corporation, EPA, and the Minnesota
 Pollution Control Agency.
Stakeholder Involvement Process

       Andersen Corporation designed the stakeholder involvement plan in the fall of 1997.
Andersen sought to establish a process for informing and involving a variety of people and
organizations interested in the company's Project XL initiative.

       In October  1997, Andersen began seeking participation of stakeholders. Four articles in
local newspapers described the XL project. These articles also made known Andersen's search for
community representatives to the project. An XL project public information repository was made
available at the local library. This repository was mentioned in the news articles and
Draft for participant review:
Andersen - 27
Do not cite or quote.

-------
 stakeholder process was designed to share information between the company and community.
 Some members also felt that because the C AC included members who had previously complained
 about the company, the CAC provided a vehicle for working out some problems between the
 community and the company. At the same time, members also felt that Andersen was not
 accountable to the CAC, and that the CAC needed more latitude to set the overall goals of the
 stakeholder process, and to alter them as the project progressed.

       Both the EPA and Andersen representatives stated that the CAC was very effective in
 disseminating information about the project to the community. EPA stated that the goals of the
 stakeholder process were primarily designed to share information with the community but with
 the added intention of improving community relations with the company. Several CAC members
 believe that the CAC would continue even if the XL project were discontinued. Andersen and
 EPA reiterated this.
 Issues Raised at Meetings

       All interviewees stated that the majority of issues raised at the CAC meetings were
 appropriate and adequately addressed. However, several issues raised were not related to the XL
 project (odor from the plant, traffic, noise, etc). While Andersen addressed these issues, several
 CAC members questioned the adequacy of their response. CAC members felt that the above
 issues were important and Andersen could have better responded to the concerns.

       Several CAC members also stated that EPA and Andersen seemed to be more concerned
 with each other than with issues raised by the CAC. For example,  CAC members stated that the
 EPA was only concerned with legal and technical issues while Andersen was only concerned with
 what the EPA demanded. These members believed that the CAC role was limited to commenting
 on what EPA and Andersen had already worked out.

       The majority of CAC members felt that the right people were involved to effectively
 represent stakeholder interest. However, one CAC member stated that representatives of Bayport
 merchants, the school district, and the St. Croix River Valley Boundary Commission were needed
 if the CAC was to effectively represent a broad array  of stakeholder interests.
Roles of the CAC in the Development of the Project XL Agreement

       The CAC was not involved in development of the initial project proposal. Opinions
differed as to the impact of the CAC on the development of the FPA. Some members felt their
role was significant, while others did not.

       According to EPA, Andersen originally established the CAC to review and comment on
the FPA, but that over time the CAC developed stronger roles for themselves. The EPA felt that
comments made by CAC members were taken seriously. Both EPA and Andersen stated that
Andersen would not continue on any part of the XL agreement without support of the CAC.
Draft for participant review:              Andersen - 29                     Do not cite or quote.

-------
 Satisfaction with the Stakeholder Process and Suggestions for Improvement

        Both the EPA and Andersen were very satisfied with the stakeholder process. EPA was
 very content with Andersen's efforts to include stakeholders and manage the CAC in the XL
 project. Andersen had no suggestions for improving the process while EPA suggested including a
 technical expert on the CAC. Andersen felt that the stakeholder process provided an excellent,
 regular forum for discussion. They felt that this forum was beneficial to both the company and
 community. The EPA felt that the ability of Andersen to listen and react to community concerns
 was a great benefit of the process.

        All except one of the CAC members expressed a general satisfaction with the stakeholder
 process. The majority of CAC members felt that Andersen did a fine job of publicizing and
 garnering support for the XL project. They stated that the process allowed substantial opportunity
 for input.  All information on the project was also open and available to the public. The process
 provided a way for the community to get to know Andersen on a personal basis and help to
 resolve misgivings associated with the company. The CAC was seen as a dynamic group that
 understood the key concerns and could provide input.

        Most members stated that they had nothing to which to compare the process. Without a
 context, they felt satisfied. Some members felt that they went into the process believing that the
 CAC would hold decision-making power in developing the project. They later felt that, given the
 complexity of the project, these attitudes were unrealistic. Several members felt that the end result
 of the stakeholder process (increased awareness of Andersen's activities, better rapport with the
 company, and full disclosure of info) was very satisfying. The CAC members observed that
 initially CAC and Andersen did not share a similar vision for the role the CAC would play in the
 project. This lack of understanding initially created a reluctance on the part of individuals to
 participate as CAC members.

       A few CAC members also expressed concerns about the management of technical issues.
 Two CAC members felt that the CAC was  not prepared to address technical issues and therefore
 were not able to effectively comment on technical issues.

       Also, one CAC member objected to the lack of Andersen critics on the CAC, and felt that
 the CAC was formed simply to fulfill an XL requirement. The interviewee further felt that the
 EPA and Andersen had too much control over the decision-making process, and that while the
 CAC was given an opportunity for input, the impact of that input was low. Despite this
 interviewees concern about the XL initiative, the CAC member was somewhat satisfied with the
 accomplishments made. The member felt that the full access to information afforded to the CAC
 was very important and helped build some confidence in the process.

       CAC members and the state agency representative felt that the project did not progress
 efficiently, and that this hampered the stakeholder process. They felt that the EPA slowed down
 the process immensely. Most CAC members did not understand the reasons  for these delays.  The
 state agency representative identified problems associated with the EPA review process that led to
commenting from multiple EPA staff, as well as the distance between EPA's regional and
headquarter offices that led to confusion about who was responsible for decisions at EPA. CAC
Draft for participant review:
Andersen - 31
Do not cite or quote.

-------
                              Atlantic Steel Summary
 Project Background
       In 1998, Jacoby Development, Inc. proposed redevelopment of an 138-acre brownfield
 owned by Atlantic Steel. Although many years of steel manufacturing left the site contaminated,
 the site is highly desirable for urban redevelopment because of its proximity to Atlanta's central
 and midtown business districts. The developer's proposal includes a high-density mix of
 residential and business uses.

       While well situated, the project site suffers from poor accessibility. The site adjoins
 Interstate 75/85 and the Midtown district of Atlanta, but is directly accessible from neither.
 Furthermore, 1-75/85 blocks the site from  the existing MARTA (Metropolitan Atlanta Rapid
 Transit Authority) rapid rail transit system. The project plan therefore includes a multi-modal
 bridge that would cross 1-75/85 at 17th Street (17th Street bridge). The bridge is designed to
 connect the site to Midtown and a nearby MARTA mass transit station, as well as to provide
 access to the interstate. Jacoby will undertake redevelopment of the site only if the bridge is
 constructed. In addition, the City of Atlanta conditioned  its rezoning on construction of the 17*
 Street bridge.

       The bridge is a major transportation project, requiring federal funds to complete. Atlanta,
 however, is currently not in conformance with the requirements of the Clean Air Act, and cannot
 use federal funds for new construction until it develops a plan to bring the region into
 conformance. The proposed redevelopment of the brownfield site, however, is seen as
 environmentally beneficial both because it would result in the clean-up of the existing
 contamination, and because its plan and location promise reductions in air pollution relative to
 alternative projects that it is likely to displace.

       Project XL provides a vehicle for enabling federal transportation funds to be used in the
 project. Jacoby has worked with representatives of EPA, the State of Georgia, local authorities,
 and public stakeholders to develop a site-specific Project XL Agreement that will allow
 construction of the bridge.

      Due to the complexity of the project and the numerous processes and analyses necessary
to implement it, EPA and Jacoby adopted a two-phased approach to the Project XL Agreement.
The Phase 1  Agreement between EPA and Jacoby set out the intentions of Jacoby and EPA
related to development  and implementation of this project. Signed on April 13, 1999, the Phase 1
Agreement detailed the project and the intentions of each party, and described areas where
further details or additional discussions between EPA, Jacoby and stakeholders were needed.

      The Phase 2 Project Agreement, which also  served as the Final Project Agreement
between EPA and Jacoby, addressed these concerns. The agreement was signed on September 7th,
 1999.
Draft for participant review:             Atlantic Steel - 33                   Do not cite or quote.

-------
 project, offered conditional support for the project. The focus of concern was primarily on the
 scale, interconnectivity and design of the project, rather than on the appropriateness of the project
 itself.

        Stakeholder involvement was an important part of the concept and rezoning
 considerations since the project began in early 1997. Multiple public meetings, discussion groups,
 individual contacts, and a full public notice and review process were held during the rezoning of
 this property. The City of Atlanta Planning Department, Georgia Department of Transportation,
 Atlanta Regional Commission,  nine neighborhood organizations, and several other groups such as
 the Midtown Alliance and Georgia Tech all participated in this process. These groups
 collaborated on the concept,  design, and conditions put in place in the rezoning document, which
 replaced the existing industrially zoned land use classification with a mixed-use  classification that
 allowed for residential, retail, office, and hospitality uses. After the public input and review, the
 rezoning was approved by all of the involved neighborhoods, the City of Atlanta Zoning Review
 Board 9-0, recommended to  the City Council by the Zoning Committee 5-0, and passed by the
 Atlanta City Council 15-0.

        The Stakeholder Involvement Plan was intended to supplement previous activities and
 described the basic methods by which additional input would be solicited and received particularly
 as it related to Project XL.
 Goals of the Stakeholder Process

        The goals of the early stakeholder input and the Stakeholder Involvement Plan was to
 ensure that interested stakeholders were afforded the opportunity to participate in the
 development of this project and to provide the stakeholders with the information they needed to
 participate in decisions on the future of the Atlantic Steel Redevelopment.

        The following were objectives of the plan as stated by Jacoby:

        •  identify stakeholders and their role in this project,

        •  describe methods of communication between the project sponsor and the stakeholders,

        •  ensure all stakeholders have an opportunity to participate in the project,

        •  promote stakeholder involvement in the development of the FPA, and

        • assure all previously involved stakeholders that discussions, agreements, and contracts,
          particularly relating to zoning conditions, remain fully intact.
Roles of Stakeholders Involved in the Process

       Stakeholders included individuals, government agencies, neighborhood organizations,
academic centers, and companies with an interest in the progress of the Atlantic Steel
Draft for participant review:
Atlantic Steel - 35
Do not cite or quote.

-------
 XL process and one each before the public comment period for the Phase 1 and Final Project
 Agreements), an urban design workshop conducted by the US EPA, and another workshop
 sponsored by the Georgia Conservancy to help residents of the most affected neighborhood
 (Home Park) clarify their own goals and desired outcomes in regards to this project.

       Community and environmental stakeholders had no direct role in the development of the
 FPA.

       Aside from public agencies, most other interviewees felt that their roles were never clearly
 defined. The community groups and non-profits stated that the EPA or Jacoby should have better
 explained the roles of the stakeholders at the beginning of the project. The state and city agencies,
 on the other hand, were more confident in applying their traditional regulatory roles to the XL
 process.

       Many interviewees stated that the EPA's role in the process was never well defined. They
 would have liked to have been better informed on the allocation of responsibility between EPA
 and Jacoby. For example, some stakeholders stated that while there were not enough public
 meetings, they did not know whether to blame EPA or Jacoby.
Outreach to Stakeholders

       The stakeholder involvement plan developed by Jacoby called for contacting potential
stakeholders prior to and during development of the FPA and to set up an advisory committee of
direct participants. Jacoby never established such a committee. Jacoby did established a project
mailing list to inform interested stakeholders of opportunities to comment or participate during
project development and implementation.

       The plan proposed using the following methods to contact and inform additional potential
stakeholders.

       Local Newspapers: The stakeholder plan called for display and legal ads in the major local
newspapers to inform the general public of public meetings and comment periods. Ads appear to
have been completely ineffective at reaching public participants. More effective were newspaper
articles in local newspapers, written by reporters. As of June, 1999, approximately 12 articles
were published. These articles focused primarily on transportation and economic development
issues. One article briefly discussed the EPA urban design workshop.  None of the articles
referenced or informed citizens of the public meetings.

       Cable Television: The stakeholder plan called  for notices of public meetings and comment
periods to be sent to the community access cable station, and to tape and broadcast the public
meetings on the community access station. However,  this part of the plan was not implemented.

       Newsletters /Fact Sheets: The plan also called for publishing fact sheets and mailing these
newsletters to everyone on the project mailing list. The plan suggested that newsletters would
provide status reports, timelines, mileposts,  contacts,  and future meeting times and locations. This
plan was  partly implemented. A project mailing list of 60 people was developed. At EPA's

Draft for participant review:             Atlantic Steel  -37                   Do not cite or quote.

-------
       Jacoby placed meeting announcements in the legal section of the local newspaper a week
 or two before they were held, and mailed notices to persons who had indicated an interest in the
 project. However, local community stakeholders often did not receive these mailings, and
 therefore called other community members to keep informed.

       Participants at these meetings included residents of adjacent neighborhoods, the Federal
 Highway Administration (FHWA), Georgia Department of Transportation (GA DOT), Jacoby
 Development), Atlantic Steel, EPA Region IV and Washington, the Georgia Conservancy, the
 developer's consulting firms, the surrounding neighborhoods, other special interest stakeholders
 and the general public.

       Typically, each of the general meetings included a number of presentations, primarily by
 the developer and the US EPA, with time for questions and comments. For example, at the first
 meeting, presentations were made by the project sponsor (opening remarks and a detailed
 presentation of the Atlantic Steel project), EPA's Region IV's Air Quality Division (a brief
 overview of EPA's Project XL), the Georgia Conservancy (an overview of air quality problems in
 the Atlanta Region and the Conservancy's Smart Growth Initiative), the EPA Region IV Atlantic
 Steel XL Project Coordinator (a summary of EPA's Project XL program and criteria),  and EPA
 headquarters (explanation of the air quality performance methodology that will be used). The
 meeting concluded with a question and answer session. After close of the meeting, Atlantic Steel
 and EPA project information remained on display, with additional questions answered  one-on-
 one.

       The public meetings held in February and June 1999 took place upon completion of the
 draft Phase 1  Agreement and the draft Final Project Agreement. The meetings were designed to
 inform the  public of what was involved in the draft agreements, to solicit comments on the
 agreements and to inform attendees of their right to comment during the public notice  period.
 Once again, the meetings were primarily organized around formal presentations. A court
 stenographer was employed to record the proceedings.

       Home Park Charrette

       In November  1998, the Georgia Conservancy sponsored a community development
 workshop in Home Park, the residential neighborhood adjacent to the Atlantic Steel project.
 Urban design faculty and students of Georgia Tech and the Inter-professional Community Design
 Collaborative facilitated the workshop. This charrette was not directly related to the XL project.
 However, a large part of the workshop focused on how to integrate the XL project
 redevelopment with neighborhood plans. Prior to the workshop, most Home Park residents did
 not want to incorporate the development into their plans for the neighborhood. They preferred to
 isolate the neighborhood from the project. However, as a result of the workshop, the Home Park
 Civic  Improvement Association (HPCIA) concluded that Atlantic Steel needed to be a part of the
 neighborhood. Several community goals regarding the Atlantic Steel project came out  of the
 workshop.  They included:

       • Protect and develop neighborhood edges, particularly along the Atlantic Steel
         boundary with residential uses that carefully provide transition from existing lower to
         proposed higher densities.
Draft for participant review:
Atlantic Steel - 39
Do not cite or quote.

-------
       All interviewees stated that substantial issues were raised throughout the process. Most
interviewees felt that every possible issue was raised. However, the majority of interviewees
stated that these issues were not adequately addressed due to the size of the project. The EPA and
the developer stated that the issues often raised at public meetings were not specific to the XL
project and therefore were not addressed. The community groups,  non-profits, and state and city
representatives stated that determining which issues pertained to the project and which did not
was very difficult. These groups felt that the EPA and Jacoby should have done a better job
clarifying pertinent issues.

       All interviewees stated that the right people were involved in the process to effectively
represent stakeholder interests. All interviewees stated that the number and diversity of
stakeholders as well as the inter-agency communication were outstanding. No groups had ever
seen such effective inter-agency coordination prior to this project.

       Overall, the community groups and citizens living closest to the development site felt that
they should have  had more input into the process. Community residents interviewed felt that the
stakeholder process did not meet their expectations. Community residents interviewed who
attended the public meetings stated that the meetings provided no forum for input. They felt that
the meetings were informational at best, and that EPA had decided prior to any public meetings
that the project would be approved regardless of any concerns raised by citizens. Most community
concerns focused on the impact  of the project on the community and the integration of the project
into the community (rather than on the design and impact of the bridge).

       Environmental and other non-residential interviewees generally felt that the formal public
meetings, which tended to focus on providing project updates, offered limited opportunity for
effective feedback. In general, the larger groups (Environmental Defense Fund, the Georgia
Conservancy, the Sierra Club, Midtown Alliance) did not attend the public meetings. Instead, they
provided their feedback through more informal meetings or through written communications. In
this context, these groups felt that the developer met with their groups and provided other
avenues for feedback. From their perspective, the developer sought to incorporate their feedback
into the design of the project, and that the conceptual designs for the project evolved as a result of
community input. However, since the design remains at a conceptual level of detail, the impact of
these design changes on the project will depend heavily on future design choices.

       The EPA  staff felt that the stakeholder process effectively shared information with all
concerned parties. The EPA and state agencies were also very satisfied with the amount and level
of communication and dedication between state and federal agencies. The  City of Atlanta noted
that while the process was designed solely to share information, the project was too large and
complicated to create a more interactive forum for problem solving with stakeholders.

       At the same time, the community groups and non-profits stated that their level of
involvement was not adequate to make any impact on the project. They reiterated that it appeared
that the project would go forward regardless of any of their concerns. They felt that the level of
coordination between all regulatory agencies involved was evidence that the outcome of the
project was pre-determined.
Draft for participant review:            Atlantic Steel - 41                    Do not cite or quote.

-------
 discussions with EPA or Jacoby. This level of involvement was relatively efficient, and they did
 not seek more direct participation.

        Other interviewees were not satisfied with the stakeholder involvement process. They felt
 that the stakeholder process was unclear from the beginning, did not provide a sufficient forum
 for input, and was managed as a formality. The stakeholders were especially concerned about the
 organization of the stakeholder participation process. The non-profit groups, state agencies and
 city of Atlanta, and community residents felt that the stakeholder participation process had few
 advantages. While they felt that the Atlantic Steel XL project should be developed, the
 stakeholder participation process had added little and was not effective. The state and city
 agencies felt that the process had not adequately identified or reached out to community
 stakeholders. Interviewees recognized that the complexity and scope of the project inhibited
 efforts for substantial stakeholder participation, but felt that Jacoby did not sufficiently recognize
 the need for meaningful participation, nor did the company act effectively to improve the process
 in response to community concerns.

        At the same time, many of these stakeholders felt that the developer was generally
 approachable and concerned about public opinion.

        Almost all interviewees stated that there were too many people, agencies, and issues
 involved in this project. Several people stated that it was difficult to stay focused on XL related
 issues. Many interviewees also stated that it was almost impossible to determine which issues
 were XL related and which were not. Many interviewees felt that the EPA should have clarified
 these ambiguities.

        The non-profits and community residents felt that the short notice of public meetings and
 lack of timely information from Jacoby and EPA were major weaknesses of the project. They
 stated that it was often difficult  to tell what phase the project was in at any given time. They felt
 that either EPA or Jacoby should have better informed them of the project status. They also felt
 that more continuity between meetings was needed if the issues were to be addressed seriously.

       Suggestions for improving the process varied. Many interviewees focused on the need for
 considerably more public notice for the meetings. The community groups felt that they had the
 largest stake in the project due to their proximity to the development yet were not sufficiently
 included. Aside from Jacoby, all interviewees stated that the process should have been better
 organized from the beginning. These interviewees stated that there  should have been more initial
 clarity and explanations concerning the developer and EPA roles in the project.
Draft for participant review:
Atlantic Steel - 43
Do not cite or quote.

-------
                                       CK Witco
 Project Background

        CK Witco (formerly Witco and OSi Specialties Inc.) is a specialty chemical manufacturer.
 The XL project focuses on CK Witco's 1,300-acre West Virginia chemical manufacturing plant.
 The plant produces a broad range of silicone and silicane products.

        CK Witco's plant is located six miles north of Sistersville. Five other towns are located in
 the vicinity of the plant, including Ben's Run, Friendly, Middlebourne, Paden City, and St Mary's.
 The population of these communities totals approximately 1,500 people. Both Tyler County
 (location of the plant) and Pleasants County (the down-river county) are predominantly rural, with
 populations totaling 10,000 and 7,500 respectively.

        Since the arrival of Union Carbide in the 1950's, these communities have relied on the
 manufacturing industry, including CK Witco, for employment. Over 50% of Tyler and Pleasants
 county citizens are employed in the manufacturing sector, six hundred of these by CK Witco at
 the Sistersville plant.

       Through its XL project, CK Witco's chemical plant is testing alternative methods of
 pollution prevention, waste minimization and air emission reductions.  CK Witco installed an
 incinerator that will destroy 98 percent of the air emissions from a process unit and will recover
 some 500,000 pounds of methanol per year from a wastewater treatment unit. In exchange, EPA
 and West Virginia are deferring hazardous waste air emission standards for CK Witco's two
 hazardous waste lagoons. CK Witco also conducted a study to identify additional waste reduction
 opportunities and is implementing many of the study's recommendations.

       The initial project proposal was submitted to EPA in September 1995. The final project
 agreement was published in the Federal Register in June  of 1997 and signed in October. The
 project is now in the implementation phase.

       This analysis focused upon the stakeholder involvement process  leading up to the signing
 of the FPA and during its implementation. At the time of these interviews, the facility was
managed by CK Witco's corporate predecessor: OSi Specialties, Inc. (OSi). Consequently, this
report hereafter refers to the corporation as OSi.

       Stakeholders interviewed for this report are listed in Appendix A. Interviewees included
participants representing the community, OSi, the OSi union, EPA, and the West Virginia
Division of Environmental Protection.
Stakeholder Involvement Process Before Signing the FPA

       OSi did not involve stakeholders in developing either the stakeholder involvement plan or
the initial project proposal. Community members became involved in the OSi project beginning in
December of 1995, after EPA accepted the initial proposal and the FPA was under development.

Draft for participant review:              CK Witco - 44                     Do not cite or quote.

-------
 Role of the Stakeholders in the Development of the Project XL Agreement

        The community representatives felt that their primary role was to provide information and
 reaction for OSi consideration. This role was agreeable to all parties involved, including OSi,
 EPA, West Virginia Division of Environmental Protection (WVDEP), and the citizens themselves.
 As stated above, the community stakeholders became involved only after the FPA was largely
 developed. (The kick-off meeting occurred in July 1996, after the June publication of the draft
 FPA). Two union employees of the plant were involved earlier. Because these employees also
 lived in the surrounding communities, they felt that they represented the community in the
 development of the FPA. EPA representatives  believe that stakeholders should be involved earlier
 in the process. However, company representatives and the two community representatives from
 Tyler and Pleasants counties felt that stakeholders did not have the specialized knowledge
 necessary to become involved in proposal development.
 EPA and OSi Roles in the Stakeholder Process

       The company designed the stakeholder involvement plan and was responsible for the
 mailings, the news and radio ads, the library repository, the door-to-door alarm update, and all
 public meetings.

       EPA provided overall guidance to the project. EPA attended all meetings and provided
 support. EPA had no direct role in the stakeholder process other than verifying that OSi met the
 stakeholder requirements for an XL project. One community representative felt that EPA and OSi
 worked in unison to create opportunities for community involvement. All interviewees felt that
 both the company and EPA were effective in their roles despite the lack of public participation.
 Management of Technical Issues

       Interviewees stated that the technical issues were clear and understandable to all involved.
 The technical issues focused on air emissions and health concerns. The community did not raise
 any specific technical concerns. Several interviewees believed that potential concerns were
 addressed through an informational interview held by OSi on public radio. The community
 representatives believed residents knew they could contact OSi and obtain answers to technical
 questions if they so desired. The community representatives believed that residents deeply trust
 OSi.
Differences in Interests or Perspectives between Stakeholders

       All interviewees agreed that no substantial differences existed amongst the interests and
perspectives of the stakeholders. The EPA stated that the project was very clear-cut. All
interviewees stated that OSi was very receptive to any stakeholder questions that were raised.
Draft for participant review:
CK Witco - 46
Do not cite or quote.

-------
of this type. Although the two representatives did not give specific suggestions for improving
community participation, their concerns focused on increasing community involvement. They both
believed that OSi did everything possible to involve the community. They would however like to
see EPA become involved with local leaders prior to  initiating a project. They believed that local
leaders understand the public concerns better than the EPA. One representative stated that the key
to participation comes from understanding the local culture.

       The company representatives, while satisfied  with the project, were dismayed by the lack
of community involvement. They felt that the company did as much as it could to involve the
community. Company representatives felt that they might have increased community participation
by putting public notices in the local churches, but this was not attempted.

       The company representatives also felt that this project was a good way for both EPA and
OSi to learn how to work with each other. One union representative felt that EPA benefitted
greatly by seeing how a company can gain the trust of a community through effective
communication.
       The EPA and WVDEP were impressed with OSi's initiative and respect in the community.
They stated that OSi's relationship with the community serves as a model for other companies.
They felt that OSi did everything it could to involve the community. However, they felt that the
representation of two communities out of six possible communities provided for insufficient
community participation. They suggested that Project XL should require a minimum level of
community participation (such as one person per community).
Draft for participant review:
CK Witco - 48
Do not cite or quote.

-------
                                    ExxonMobil
       Project Background

       The Sharon Steel Corporation - Fairmont Coke Works Superfund Site is located in
Fairmont, West Virginia. Fairmont sits along the 1-79 industrial corridor. Fairmont is a town of
15,000 located in a county of 58,000. Approximately 1,000 residents live within a one-mile radius
of the Superfund site.

       Domestic Coke Corporation (Domestic Coke) purchased the original 44.6 acres of the
current site in 1918. Domestic Coke was a wholly owned subsidiary of Standard Oil of New
Jersey, the corporate predecessor to ExxonMobil Corporation. Domestic Coke conveyed the land
to the U.S. Department of War, who built the Fairmont Coke Works and operated the plant
between  1918 and 1920. The land with improvements was reconveyed to Domestic Coke in 1920.
Domestic Coke made additional land purchases to bring the total acreage of the coke plant to
approximately 103 acres. All process units were located within an approximately 50-acre parcel at
the center of the site. The rest of the site consists of a wooded hillside that descends to the
Monongahela River. The site is one of the few large areas of flat, developable industrial land
along 1-79 in West Virginia.

       In 1948, Sharon Steel Corporation purchased the business and operated the coke plant.
The coke plant was closed in 1979 following Sharon Steel's reported failure to comply with Clean
Air Act and Clean Water Act regulations. In 1991, Sharon Steel was liquidated under jurisdiction
of bankruptcy court, with the land transferred to FAC, Inc., a subsidiary of Sharon Steel. In June
1998, Green BluffDevelopment, Inc. (a subsidiary of Exxon) bought the site.

       On November 30, 1999 Exxon merged with Mobil to become ExxonMobil Corporation.
Since this report focuses on activities conducted before this date, the report refers to the
corporate entity as Exxon Corporation.

       EPA began evaluating the site for inclusion on the National Priority List (NPL) in 1987.
The site was listed on the NPL on December 23, 1996. Because of Sharon Steel's bankruptcy and
Exxon's prior ownership, Exxon signed a Comprehensive Administrative Order on  Consent
(AOC) with EPA in September, 1997. The AOC sets out procedures to conduct a Remedial
Investigation and Feasibility Study (RI/FS) and Risk Assessment for the site. In 1998, Exxon was
the  only potentially responsible party with an AOC for this site.

       Exxon submitted its XL proposal on September 1998. The proposal described an
alternative strategy for investigation, risk assessment, remedy selection and remediation of the
site. Using an administratively streamlined process, Exxon hoped to clean up the contaminated
site in half the time of traditional cleanups and at less cost. Additionally, Exxon planned to work
with other stakeholders to locate businesses interested in redeveloping the site. The Final Project
Agreement was signed on May 24, 1999.

      Although the Exxon XL project is currently in implementation, this analysis focuses upon
the stakeholder process used in development of the FPA.
Draft for participant review:
ExxonMobil - 49
Do not cite or quote.

-------
       •  Start and end on time. (Keep meetings to two hours. End at 7:30 p.m.)

       •  Send minutes, agendas, updates a week in advance of meeting.

       •  Provide breaks.

       •  Speak up!

       •  Always provide opportunity for input from guests.

       •  Publicize ail meetings one week ahead.

       •  Give ample lead-time for public input.

       •  Strive to reach consensus input and recommendations through full discussion.

       The meeting agendas were originally drawn up by the consultants but eventually were set
by panel members with input from the consultants.


Outreach

       At the end of 1998, several panel members gave presentations about the Exxon XL
project to various community groups in the area (Kiwanis Club, PTA, etc.). These presentations
were designed and run solely by panel members. They felt responsible for sharing information
with the community. Presentations provided the best means for accomplishing that objective.

       In early 1999, several community outreach efforts were conducted to gather input on the
project. A one-half page  advertisement was placed in the local paper describing and  asking for
input on and concerns about the project. The ad included an 800-telephone number and an e-mail
and mail address where comments could be sent.

       A tri-fold pamphlet was also  sent out to all residents living within one mile of the site.
Eight hundred pamphlets were mailed. The pamphlets were designed to gather feedback from the
community about the project and any community concerns that may have been overlooked by the
panel. The pamphlet contained the following questions:

       •  How should the property be used in the future to meet the needs of the citizens of
          Fairmont?

       •  What suggestions do you have  for making information about the site more accessible
          to the general  public (e.g., direct mail, newspaper articles. TV, radio announcements,
          etc.)?

       •  Exxon wants the input and support of people who have a specific interest in the
          environmental impact of the cleanup. If you have a specific interest, how would you
          like to be informed of the project?


Draft for participant review:             ExxonMobil - 51                    Do not cite or quote.

-------
       The community interviewees felt that they served primarily as liaisons between the
community and Exxon. Exxon would present progress reports at the meetings and the
stakeholders would make comments based on what they perceived to be in the community's best
interests. Panel members felt that it was their responsibility to keep the community informed of
project progress.

       Panel members also felt that the process afforded them the opportunity to work out
problems and community concerns between Exxon and the community. Most community
grievances were related to the time frame of the cleanup and past alleged wrong-doings by Exxon
(burial of toxic waste on site). All comments and grievances were noted by the facilitator and
passed on to Exxon. Exxon would then address concerns at the following meetings. However,
some members felt that there was no way to verify the accuracy  of responses by Exxon to
concerns raised by the panel, since all the information and analysis was generated by the company.

       While some interviewees felt that the panel provided the  greatest benefit to Exxon, and
was used as a public relations tool, all panel members who were interviewed also felt that the
process was effective at providing information and clarifying community concerns. All
interviewees stated that the right issues were raised and adequately addressed throughout the
process. Most panel members felt that the right people were in the process to effectively represent
stakeholder interests. The panel members stated that the panel was a good cross-representation of
the community (citizens, business owners, and government officials). One stakeholder would have
liked more county government representation, but noted that the opportunity to join the panel was
made available and apparently county officials were not interested. Another member would have
liked more neighborhood representation.
Roles Of Stakehoiders in Development of Project Agreement

       The stakeholders had no role in the development of the initial XL proposal. Stakeholders
also had a relatively small role in the development of the FPA (timeline, goals, wording of FPA).
According to the interviewees, suggestions made by the panel did not lead to substantive changes
in the FPA, although panel members also felt that Exxon was generally responsive to community
concerns.

       Exxon originally established stakeholder roles, with panel members primarily acting as
liaisons between the community and Exxon. The roles were designed to allow community
concerns to be heard and addressed by Exxon. All stakeholders felt that this was accomplished.

       The majority of stakeholders initially belived that they would have more input into the
drafting of the final FPA than they were afforded. They felt the emphasis of the panel on
information sharing, the time involved, and the members' lack of technical expertise did not
permit more active involvement. The EPA stated that the panel gave as much input as they could,
given their limited technical knowledge.

       All stakeholders stated that the EPA acted to support and guide the XL project process.
Stakeholders were satisfied with the EPA's role in the project. They felt that the EPA
Draft for participant review:
ExxonMobil - 53
Do not cite or quote.

-------
 Stakeholder Roles after Signing of the FPA

       Since signing the FPA, the panel has continued to meet. The panel largely functions as a
 'watchdog'. Panel members will continue to monitor the project, albeit from a distance.
Satisfaction with the Stakeholder Process and Suggestions for Improvement

       Exxon expressed great satisfaction with the stakeholder process. This interviewee stated
that the panel provided an excellent means of gathering and disseminating information about the
project to the community. The interviewee also stated that the stakeholder process opened a
direct line of communication between the company and the community, something not attempted
prior to the project. The interviewee had no suggestions for improving the process.

       The EPA was also very satisfied with the stakeholder process. The EPA felt that Exxon
was very open to panel suggestions and committed to working with the community. To improve
the process, the EPA suggested conducting more initial public meetings to identify stakeholders
and including technical experts on the panel. The EPA felt that one public meeting was not
adequate for identifying stakeholders. The EPA also felt that most community members did not
have the necessary background to make substantive comments concerning technical issues.

       The state regulatory agency representative felt the stakeholder involvement process was
over-designed, allowing for too much involvement by too many people. Monthly meetings
allowed special interest groups to maintain their momentum between meetings and thereby tie up
regulatory time. Quarterly meetings would have been more efficient.

       All stakeholder panel members expressed satisfaction with the stakeholder process. Most
panel members stated that the process was a very positive experience. These interviewees stated
the stakeholder process afforded them the opportunity to establish direct links between the
community and Exxon. The stakeholder process gave the community confidence in Exxon. The
panel members now feel that if they have concerns about anything that Exxon is doing, they have
contacts at Exxon who will adequately address those concerns. They can now put faces to the
names. Exxon has effectively been 'humanized' by their efforts in the stakeholder process. They
are no longer viewed by the community as a faceless corporation.

       Almost all the interviewed stakeholders were very  satisfied with the outcome of the
process. They felt that the process afforded them the opportunity to gather, analyze, and
disseminate information to the community. The also stated that this process was an effective way
to create a good working relationship and open line of communication between the community
and Exxon.

       Some  of the strengths specifically noted by the panel members included:

       • Meetings provided an open forum for public participation in the project.

       * Active membership on the panel helped to keep public interest in the project high.
Draft for participant review:             ExxonMobil - 55                   Do not cite or quote.

-------
                                      HADCO
Project Background

       HADCO Corporation is a leading manufacturer of printed wiring boards (PWB) and
electronic interconnection products. The company is headquartered in Salem, New Hampshire but
has additional operations in the United States and Malaysia. The original sites involved in the
HADCO XL project were the Salem, Hudson, and Deny sites in New Hampshire, the Owego site
in New York, and a site in California. HADCO dropped the California site because of the
difficulties in applying the proposed regulation to that state. The Salem site was eventually
dropped because HADCO was in the process of moving its headquarters and the facility was
having difficulty maintaining sludge constituent levels that were necessary for delisting. The
project involved HADCO, EPA Regions I and II, EPA Headquarters, and representatives from
the New York State Department of Environmental Conservation (NYSDEC) and the New-
Hampshire Department of Environmental Services (NHDES).

       As a PWB manufacturer, HADCO generates wastes that are classified as hazardous waste
under the Resource Conservation and Recovery Act (RCRA). Since the wastewater sludge
produced by HADCO's operations is classified as hazardous under RCRA, it must be shipped to a
third-party processor before it can be sent to a smelter for reclamation of the valuable copper
contained within.

       Since the 1970's, HADCO has made changes in its  manufacturing processes  and believes
that the sludge created as a by-product of its operations is now less toxic and no longer needs to
be regulated as a hazardous waste. The HADCO project sought to reduce the regulatory burden
of RCRA while promoting waste recycling throughout the PWB industry. HADCO,  through
Project XL, sought a conditional delisting of the sludge that would allow them to bypass the
third-party processor and ship the wastes directly to an approved smelter. This action would save
costs and decrease the risks associated with  shipment of the wastes over long distances. It was
determined through the course of the project that the sludge could be eligible for a conditional
delisting in NH and for a solid waste variance in NY.

       The initial project proposal was submitted to EPA in July 1995 and was accepted March
1996. The draft Final Project Agreement (FPA) was submitted to EPA in November 1996. The
FPA was reviewed and revised and the final  FPA was published in the Federal Register on
October 2, 1997.

       Since the FPA was approved, HADCO has been sampling their sludge according to the
FPA and communicating with EPA and the state agencies regarding the  samples. HADCO has
decided to go with a solid waste variance in  New York. To complete the delisting petition for
New Hampshire, EPA must have details of contracts with smelters who  will receive the waste. As
of May, 1999, HADCO had not yet  submitted them. Representatives from HADCO  noted that
they are waiting for details from the smelters that were needed to complete the contracts.

       This analysis focused on the  stakeholder involvement process used during the
implementation of the FPA, but also includes references to the stakeholder process leading up to
Draft for participant review:
HADCO - 57
Do not cite or quote.

-------
 that since this was the first XL project to involve multiple jurisdictions, it would have been
 prudent to plan the structure in more detail before it actually started.

       Most participants said that their individual roles played out as expected, but generally
 required more time and attention from them than they had anticipated. With the exception of
 having insufficient involvement from community stakeholders, respondents generally believed that
 the right people were at the table HADCO invited participation by the smelters who were
 scheduled to receive the delisted sludge, but these companies chose not to participate. HADCO
 representatives felt that their presence would have been helpful.  The presence of attorneys who
 represented an hazardous waste processor tended to focus attention onto the specifics of
 regulatory requirements and therefore had an important impact on the FPA. Most said they did
 not envision the time it would take to work out the details and the wording of the FPA.
 Role of the Stakeholders Since the Signing of the FPA

       As noted above, to complete the delisting petition for New Hampshire, EPA must have
 details of contracts with smelters who will receive the waste. As of May, 1999, HADCO had not
 yet submitted them.

       Since the FPA was signed, all participants have been involved in reviewing and
 commenting on sample data to ensure that a conditional delisting or a solid waste variance can be
 supported. No stakeholder meetings or other stakeholder communication were conducted
 between the signing of the FPA and May 1999. Most participants said that there has been no need
 for additional stakeholder involvement until the sample data are approved and HADCO has more
 information to share.
Differences in Interests and Perspectives between Stakeholders

       No real differences in interests have emerged among the participants since the FPA, but
several came up during the negotiation and near the end of the process. Some disagreements
existed between Region II and New York on requiring toxicity testing of the sludge before
allowing a delisting. New York felt that the toxicity tests should be done before making a
determination on the allowance of a delisting, but HADCO officials felt that all necessary
information regarding toxicity was in the comprehensive report incorporated into the FPA.

       Until near the signing of the FPA, the New York agencies were unaware of EPA's
requirement for HADCO to reinvest all savings into its pollution prevention and recycling
programs. This requirement was seen as excessive and unnecessary, although HADCO accepted
the condition since so much time and effort had been spent in reaching the FPA.

       At times HADCO designated certain information as proprietary, but some participants felt
this was inappropriate given that XL is supposed to  be a transparent process.

       The third-party processor felt that some of the wording contained within the FPA
effectively precluded their company from competition among potential waste recipients and was

Draft for participant review:              HADCO - 59                      Do not cite or quote.

-------
 participant felt that the stakeholder participation helped keep the process "honest." Another said
 that the idea of offering flexibility through innovation and finding new ways of doing business was
 worthwhile.

        On the other hand, respondents thought that the time commitments needed to participate
 were excessive. Several interviewees also indicated that stakeholders with a narrow view or
 special interests should not be fully involved in decision-making, particularly if they have financial
 interests in the decision. These respondents viewed special interests as causing unnecessary delays
 in the process.

        Participants felt the process addressed almost all issues that should have been addressed.
 HADCO representatives questioned why the issue of toxicity testing was not mentioned until after
 the FPA was drafted. They felt it would have been more constructive to discuss it earlier in the
 process. The definition of "conditional delisting" was discussed, but not to the satisfaction of
 some parties.

        Some participants felt that more effort should be made to secure stakeholder involvement,
 and it was suggested that teleconferencing be available to help attain that end.  Another suggested
 that since most companies were  not experienced in eliciting stakeholder participation, a better way
 to identify potential stakeholders was needed. At the same time, it  was suggested that all involved
 should be able to add something to the process instead of inviting participants  simply for the sake
 of having people at the meetings. Stakeholders should be knowledgeable of the project goals and
 the means available for reaching the goals, and should have some technical knowledge of the
 issues.
Draft for participant review:
HADCO-61
Do not cite or quote.

-------
                                          Intel
 Project Background
       Intel, a large semiconductor manufacturer, produces Pentium microprocessors and other
 state-of-the-art computer chips. Located in Chandler, Arizona, in the Phoenix metropolitan area,
 the FAB-12 facility uses the company's 0.35-micron manufacturing process to produce 8" silicon
 wafers. The facility covers 1,500,000 square feet of building area, occupies 720 acres of land, and
 initially employed over 2,000 high-skill, high-wage workers. At the time of construction, the
 facility was the largest private construction project in the state with an estimated capital cost of
 $1.3 billion.

       The initial project proposal was submitted to the Arizona Department of Environmental
 Quality (AZ DEQ) and EPA on June 30, 1995. Meetings for developing the Final Project
 Agreement (FPA) were held between January 24, 1996 and July 23, 1996.  The stakeholder
 involvement process was based on consensus building amongst stakeholders. The FPA was signed
 on November 19, 1996, and the project has been in implementation since that time.

       The FPA provides for a facility-wide cap on various air pollutants. The facility-wide cap
 replaces individual permit limits for different air emissions sources. The FPA also limits water use
 and waste generation. The FPA sets standards that would exceed or, at a minimum, fully comply
 with applicable emissions standards. Although the initial proposal was developed solely for the
 FAB-12 facility, Intel envisioned expanding the contract to cover other Intel operations in the
 Chandler area. These proposals would be contingent upon demonstrating the feasibility and the
 utility of the new system.

       The Maricopa County Bureau of Air Pollution Control is responsible for oversight of most
 aspects of the agreement. The Bureau uses FPA criteria to review specific changes proposed by
 Intel. The engineers and field compliance people go over proposed changes and collect
 supplemental data. Interviewees report  that procedures have basically been implemented
 according to the FPA.

       This report focuses on the Intel  XL Project's stakeholder involvement since the signing of
 the FPA on November 19, 1996. but includes references to the stakeholder process leading up to
 the FPA. The report is an addendum to the description of Intel's project presented in the
 RESOLVE, Inc. report "Evaluation of Project XL Stakeholder Processed (September 1998).

       Stakeholders interviewed for this report are listed in Appendix A. Interviewees included
 participants representing the community, Intel, EPA, the city of Candler and county of Maricopa,
and the Arizona Department of Environmental Quality.
Stakeholder Involvement Before Signing the FPA

       Intel organized a Stakeholder Team to draft the FPA within a consensus building process.
The Team served as a multi-interest executive committee (plenary- group) with working groups

Draft for participant review:                Intel - 62                       Do not cite or quote.

-------
 Stakeholder Involvement Since Signing of the FPA

        Intel remains responsible for managing the participation process since the FPA was signed.
 Intel schedules and sponsors the stakeholder and public meetings, distributes the quarterly report,
 and maintains a web page with up-to-date information. EPA provides information and obtains
 data when needed and is involved in reviewing the reports.

        As required by the FPA, Intel holds quarterly stakeholder meetings and semi-annual public
 meetings. The company also produces quarterly reports regarding emissions and air and water
 quality as affected by its operations. The stakeholder team reviews and discusses the quarterly
 reports before they are made public to ensure that the reports are comprehensible to the public.
 The team also reviews the reports to ensure that Intel is meeting the superior environmental
 performance as directed by Project XL.

        The stakeholders use the quarterly meetings to discuss potential revisions to the FPA. An
 example is the team's decision to revise the company's goal of "100% water reuse" to "95%
 water reuse" because of the technical difficulties with meeting the original goal. This decision was
 reached by a unanimous agreement among stakeholders. Another issue addressed by the
 stakeholder team regards the amount of notice that should be given to the stakeholders before
 Intel makes a process change.

        Since the FPA was signed, some stakeholders have felt that their involvement has been
 limited. As an example, they cite Intel's decision to change from using arsenic to arsene gas in one
 of its processes. This decision was made without consultation, Several interviewees felt that the
 issue should have been discussed with the stakeholders before the decision was made, although
 most felt that the issue itself was not a great threat to public safety. Most interviewees also noted
 that Intel made great efforts to alleviate stakeholder concerns regarding the change.

       Because Intel has been granted regulatory flexibility, other area industries have requested
 the same flexibility but without going through the process. Many stakeholders strongly object to
 the potential for state and local regulators to consider this allowance.

       Most interviewees feel that their role in the process was consistent with what they had
 expected, but that the time commitment was unanticipated. The citizen stakeholder who
 commented on Intel's decision to move from consensus decision making to advisory roles for
 citizens had expected a more active role than the interviewee felt was achieved. Most stakeholders
 felt that the right people were involved in the process, but many commented on the need for more
 citizen participation. However, those who had been involved with similar processes noted that it is
 always difficult to get citizens involved.

       The  Stakeholder Team has discussed the possibility of transferring elements of this project
 to other industries in the Phoenix area, but concluded that this would be difficult because of the
 uniqueness of each XL project.
Differences in Interests and Perspectives between Stakeholders

Draft for participant review:                 Intel - 64
Do not cite or quote.

-------
 Satisfaction with the Stakeholder Process and Suggestions for Improvement

       The participants were all at least fairly satisfied with the stakeholder process, but one
 stakeholder was dissatisfied with the structure and the difficulty of completing a large task in a
 short amount of time. Some dissatisfaction also existed over the inability of more citizens and
 environmental representatives to be involved in the process. Respondents noted that the time
 requirements were an important barrier to potential participants, as well as a source of difficulty
 for their own participation. Insufficient resources were also cited as a barrier. One participant
 noted that a smaller company could not participate in a process as complex as this. The time
 involvement was a source of dissatisfaction for a number of participants, and an agency
 representative noted that their agency would not be able to commit such tremendous resources to
 all permitting processes.

       Stakeholders praised Intel's efforts to make the process viable, including the provision for
 conference calls in lieu of meetings. The company was commended for its endeavor to make the
 community aware of the process and in using the  Internet to do so. The dialogue and information
 sharing that resulted from the process was seen as a major strength, particularly in the current
 dialogue regarding worker health and safety. Another strength was the decision to use the
 Arizona Ambient Air Quality Standards to  set an  absolute maximum amount of exposure to
 VOCs, particulates, NOX concentrations, etc.

       Stakeholders expressed concern that all parties at the table were not equals,  even though
 equality was a premise of the original process. Most stakeholders felt that more citizen
 participation would have improved the process. Some issues emerged from the lack of clarity
 around groundrules, and most participants said that groundrules should be written instead of
 being based on a verbal agreement.

       All participants felt that all issues that should have been addressed were discussed.

       Suggestions for improving the process generally centered around finding ways to get more
 citizen involved and obtaining funds for educating participants  on technical issues. Groundrules
and deadlines should be established up front, with full understanding of the rules by  all
participants. Scoping should be revisited at some point during the process to make sure that
important issues are being addressed.
Draft for participant review-
- 66
Do not cite or quote.

-------
                      New England University Laboratories
 Project Background
        The Laboratory Consortium for Environmental Excellence (LCEE) is an umbrella
 organization for university-based environmental and safety officers. Eight New England
 universities participate in LCEE, including the Amherst and Boston campuses of the University of
 Massachusetts, Boston College, Harvard University, Northeastern University, Trinity College,
 Tufts University, and the University of Vermont.

        In September 1997, LCEE submitted an XL proposal to EPA to develop flexible
 performance-based standards for managing university laboratory hazardous waste. The Final
 Project Agreement was approved on September 28, 1999.

        The project is designed to develop and implement an integrated Environmental
 Management Plan (EMP) for managing hazardous lab waste at three universities. These
 laboratories typically use small quantities of many different chemicals. A management plan to
 control their use and disposal offered environmental advantages relative to the traditional
 regulatory requirements set forth in the Resource Conservation and Recovery Act (RCRA). The
 RCRA process involves a substantial amount of paperwork, sometimes for a small amount of
 infrequently generated  waste. Under the EMP, environmental professionals will seek opportunities
 for reusing materials within the university. The universities will not be required to make a RCRA
 hazardous waste determination until the laboratory wastes reaches a central on-site location. The
 FPA requires reductions in waste generation and material reuse as a result of providing regulatory
 flexibility.

       While the FPA  is now signed and the project is being implemented, this analysis focuses
 upon the initiation and  early dynamics of the stakeholder process used in project development.

       Stakeholders interviewed for this report are listed in Appendix A. Interviewees included
 participants representing the communities, environmental groups, the university sponsors, other
 universities, EPA, and state environmental agencies.
Overview of the Stakeholder Involvement Processes

       The stakeholder process developed for the New England Labs project differed from that
of other XL projects. This project involved several parallel stakeholder processes: one focused on
national constituencies, and a series of processes designed to address the concerns of local
stakeholders more locally concerned with each of the university campuses. These processes aimed
to involve three distinct constituencies:

       •  national constituencies with an interest in the environmental management of university
          laboratories,
Draft for participant review:
New England Labs - 67
Do not cite or quote.

-------
       Stakeholders have continued to be involved at different levels. Although the scope of the
 project initially appeared to be broad in its applicability, schools in some states realized that
 implementation would be difficult due to particular nuances in their schools or in their state
 regulations. Participants also believed that the various EPA regional offices managed issues of
 laboratory waste differently, with some regions applying specific standards more stringently than
 others. Thus, some participants determined that the issues identified by the New England schools
 were less problematic for their universities.

       The project was eventually narrowed to include three schools in New England: The
 University of Vermont, (UVM) Boston College (BC), and the University of MA-Boston(UMass-
 Boston). These three schools and the LCEE worked with the EPA and state agencies, and other
 stakeholders, to develop the FPA.

       Involvement in the Process

       Interviewees felt that the stakeholder process was well designed and implemented.
 Respondents felt that participants felt free to speak and contribute to the discussion. At the same
 time, most respondents felt that the participants were operating under too many constraints.  A
 number of participants at the meetings sought to shift the focus of the XL project from regulation
 of specific wastes to comprehensive environmental management plans for the labs. Lab-based
 interviewees believed that EPA was too cautious, preferring to adapt existing regulatory language
 as little as possible. Many respondents believed EPA's conditions precluded creativity and
 innovation. Interviewees questioned why EPA placed these restrictions on a pilot project that
 could be stopped at any time if it did not yield the desired results.  Many lab-based stakeholders
 believed that minor issues became major points of contention and that this was contrary to the
 purpose of Project XL.

       Most stakeholders felt that their level of involvement was appropriate, given that many of
 them participated only in the Florida meeting and through the listserve. Interviewees were
 generally frustrated,  however, with the length of time that passed between the end of the national
 meetings (March 1998) and the signing of the FPA (September 1999). One  interviewee observed
 that more groundwork could have been done between EPA and LCEE before holding the Florida
 meeting in order to coordinate efforts more effectively.

       Most interviewees felt  that there were no barriers to participation, but representatives
 from some schools would have participated more fully had they been closer to Boston, which was
 the location of a number of smaller meetings (predominantly between the LCEE institutions).
 Environmental groups noted that they lacked both the funds and the time to participate in a longer
 process.

       Most interviewees believed that the right people were at the table, but some felt that
 environmental groups,  representatives from EPA Headquarters, and smaller universities should
 have been better represented. An EPA representative noted that participation by environmental
groups was insufficient, and that the project sponsors and EPA needed to work more effectively
at promoting such participation. Another interviewee suggested that EPA should fund
involvement by non-profit organizations, since such organizations do not have the resources  to
participate otherwise.
Draft for participant review:
New England Labs - 69
Do not cite or quote.

-------
       Meeting Management
       ML Strategies and the LCEE schools developed the agenda for the Florida meeting. At
 the same time, interviewees said that the process allowed for additional issues to be raised.
 Members had little to say about groundrules; some said none were developed, while others said
 groundrules existed but were not of major concern. Most viewed ML Strategies as the primary
 facilitator, responsible for not only keeping the meeting running smoothly but also for building
 agreement amongst the various labs as to an appropriate direction. One interviewee viewed the
 EPA representative as the primary facilitator. All agreed that ML Strategies kept the process
 moving and kept participants encouraged and focused on the goal. It appears that everyone was
 comfortable in speaking about issues they viewed as relevant.

       Satisfaction with the Stakeholder Process and Suggestions for Improvement
       Most interviewees were satisfied with the stakeholder process, but some were dissatisfied
 with what they perceived to be EPA's unwillingness to innovate much beyond the traditional
 regulatory model. These interviewees reasoned that as a pilot project, Project XL should allow for
 more experimentation.

       Most interviewees approved of bringing interested parties together and believed that
 participants were all able to contribute effectively. No one reported dissatisfaction with his or her
 participation in the stakeholder process. One member wondered if, given the breadth of the issues,
 the diversity of the stakeholders involved was too narrow.

       Several interviewees noted that EPA had little sense of deadlines, and that the numerous
 rewritings of the project agreement was inefficient. Interviewees also noted that  EPA seemed too
 concerned with worst-case scenarios.

       Interviewees applauded the process for attempting to give labs a more efficient way to
 manage waste, for encouraging group membership that was largely appropriate for the issues, for
 focusing on long-term goals, and for including the input of lab directors and environmental
 managers from across the nation. Interviewees viewed the meetings as constructive engagements
 with people sharing viewpoints, and felt these meetings were meaningful and important
 experiences. Some  interviewees said that the project accomplished what labs have been trying to
 achieve since 1984:  establishing performance-based standards for university labs.

       Interviewees believed that most issues had been addressed. Exceptions included EPA's
 position on the types of allowable treatment within labs and storage areas, the definition of what
 constituted a "lab unit", and issues associated with on-site  storage and the "arbitrary" 90-day limit
 for storing waste.
Local Stakeholder Involvement Processes

       Overview of Local Community Processes

       The XL project applied to three New England academic institutions, including Boston
College (BC), University of Massachusetts - Boston (UMass-Boston), and the University of
Draft for participant review:
New England Labs - 71
Do not cite or quote.

-------
 solicited interest in participating in the stakeholder involvement process. Twelve faculty,
 administrators and staff volunteered to be on the stakeholder panel

        An initial meeting was held in February 1998. This meeting was primarily informational
 and focused on explaining XL projects in general as well as specifics related to the project at
 UMass. Stakeholders were also asked what roles they would like to take as participants in the
 project. The group decided on a commentary role.  No subsequent meetings have been held.

        The twelve stakeholders are periodically sent e-mails as project updates occur. They are
 encouraged to review the documents and send their comments to the university's project lead.
 The project lead also made two presentations describing the project to an environmental
 compliance group on campus. The group was asked for their input on the project. No comments
 were received from either group.

        The project lead feels that the stakeholder panel is comprised of a solid cross-section of
 faculty, staff, and administrators, but remains concerned that the project is attracting little
 community interest. The interviewee feels that the stakeholders will become more involved once
 the project is being implemented.

       Internal to UVM

       UVM has not held any formal internal stakeholder meetings. The project lead contacted
 and met with several groups and individuals on campus. The project lead sent updates to each of
 these internal groups and asked  for comments. Interviewees stated that the campus stakeholder
 process was designed to share information, and that the right groups were involved in the process.
 All participants in this processes were technically proficient.

       The project lead at UVM was also responsible for formulating and maintaining an e-mail
 list server. The list server was designed to keep national and local stakeholders informed and to
 obtain input from those stakeholders. The list server was established in October 1998 and as of
 May 1999 had 150 members. The list server membership includes national and campus-specific
 stakeholders, as well as people not affiliated with the project but who were interested in
 regulatory issues. Project progress reports were e-mailed monthly to members. The UVM project
 lead  responded to concerns that come in through the list server.

       E-mail comments on the progress reports have been minimal. According to the managers
 of the list server, more comments were received at professional conferences than through the list
 server. The majority of comments focused on health and safety management in a laboratory
 setting. Commentors often expressed concerns that the difficulty of organizing a centralized
Environmental Management Plan may prove to be more difficult than complying with RCRA on
college and university campuses. Aside from this question, however, most commentary on the
project has been supportive.

       External to Boston College

       In late 1997, BC's project lead identified 10 external stakeholders. The stakeholders were
asked to participate based on their community involvement, their technical  skills, and their interest
Draft for participant review:
New England Labs - 73
Do not cite or quote.

-------
       Goals of Internal and External Stakeholder Processes

       All interviewees stated that the objective of the local stakeholder processes was to share
information between the project coordinators, internal stakeholders, and the community. Most
interviewees felt that the process accomplished that objective. However, each university's project
lead felt that the specifics of the XL project were too complicated for the external stakeholders to
understand and this caused the external groups to become disinterested. Several external
stakeholders reiterated this point.

       The internal processes were designed to increase awareness amongst laboratory personnel.
All interviewees felt that this goal was reached.  Interviewees also agreed that all interests were
effectively represented on the internal panels

       The external processes were designed to reach out to and educate the surrounding
communities. However, community interest in the specifics of the XL project was low. Several
interviewees felt a greater effort made to include other parties in the external process was needed.
The project leads all stated that community residents were primarily interested in issues
neighborhood impacts such as noise, traffic, and student housing, issues that were not related to
the XL project.

       Stakeholder Roles

       Local community stakeholders did not assist in developing either the initial proposal or the
FPA. The internal and external group roles were advisory. All interviewees stated that the
stakeholders were free to develop more active roles in the projects. However, all stakeholder
groups decided to keep their roles as advisory.

       The EPA played very small roles in the stakeholder process at the university and
community level. One EPA official did participate in an external stakeholder meeting at Boston
College.

       Management of Technical Issues

       All interviewees stated that technical issues were adequately addressed. The majority of
internal stakeholders were familiar with the technical language and content of the project prior to
their involvement.

       External  stakeholders stated that they were not concerned with the technical content of
the project. They focused more generally on the potential impacts of the project, and trusted the
universities' experts to appropriately interpret the technical background for them.
Draft for participant review-
                                  New England Labs - 75
Do not cite or quote.

-------
                            Vandenberg Air Force Base
 Project Background
        The Vandenberg Air Force Base conducts and supports missile launches, operates the
 Western Test Range and responds to worldwide military contingencies. The base covers more
 than 98,000 acres and is the Air Force's third largest military installation. Vandenberg AFB is
 located in Santa Barbara County,  15 miles from the nearest municipality, Lompoc (population
 35,000). The base is within 55 miles of Santa Maria and Santa Barbara and 150 miles northwest
 of Los Angeles.

       Under Title V of the Clean Air Act and the California permitting process, Vandenberg
 AFB would be designated as a major source of ozone precursor emissions. Because of the
 Metropolitan Region's air quality  problems,  the designation would require the base to obtain new
 permits for up to 300 previously unregulated emission sources. Through both the ENWEST2 and
 Project XL programs, the base sought  to substantially reduce ozone precursor emissions,
 sufficient to be redesignated as a minor source. This  would result in a substantial reduction in
 compliance costs. Vandenberg AFB sought to fund these emission reduction projects using money
 that would otherwise be spent complying with administrative requirements of Title V, such as
 permitting, record keeping, monitoring, and training.

       The initial project proposal was submitted to the Department of Defense and EPA in
 December 1995. The Draft Project Agreement was developed and submitted to the EPA in March
 1996. The Final Project Agreement FPA was signed  and published in the Federal Register in
 November 1997. The project is now in the implementation phase.

       This analysis focused upon the stakeholder involvement process leading up to the signing
 of the FPA and during the implementation of the FPA.

       Stakeholders interviewed for this report are listed in Appendix A. Interviewees included
 participants representing the community, Vandenberg Air Force Base and EPA.
Stakeholder Involvement Process

       The Stakeholder Involvement Plan was developed in July 1996 by a legal consultant hired
by Vandenberg AFB. The plan was part of the draft FPA. Stakeholders were not involved in the
development of the plan nor were they involved in the development of the draft FPA.
2 As part of the Administration's reinvention initiatives, EPA and the Department of Defense
(DoD) signed a Memorandum of Agreement in 1995 that established how the two agencies would
interact during implementation of DoD's Environmental Investment (ENWEST) program. The
ENWEST program emphasizes regulatory compliance through pollution prevention and
provides an alternative to prescriptive regulatory requirements through a performance-based
environmental management system designed to attain superior environmental results.
Draft for participant review:
Vandenberg - 77
Do not cite or quote.

-------
 Goals of the Stakeholder Process

       All interviewees stated that the goal of the stakeholder process was to share information
 about the project with the community. While the process was not designed to resolve issues
 between the base and the community, very few issues were raised. The only concerns expressed
 were those of an environmental group and they were allayed through direct discussions with
 Vandenberg staff All interviewees felt that the ENWESTYXL project would benefit the
 surrounding communities.
 Role of the Stakeholders

        The CAB and CAC members serve as community representatives on standing committees.
 They saw their roles as providing information to the community and feedback to the AFB. These
 roles were not created through the ENWEST/XL project but were extensions of their duties on
 their respective committees. As such, the specifics of the ENWEST/XL project were only a
 small part of their overall responsibilities.
 Vandenberg and EPA roles in the Stakeholder Process

       As stated previously, Vandenberg hired a legal consultant to develop the stakeholder
 involvement plan. Vandenberg personnel were responsible for the invitations to the workshop, the
 media and newspaper spots, and both of the public meetings. EPA advised Vandenberg on Project
 XL requirements, assisted Vandenberg in the development of their project, attended all meetings,
 and provided support. Vandenberg personnel continue to brief the CAB and CAC boards
 quarterly on the status of the project.
Management of Technical Issues

       CAC interviewees were already familiar with the technical language surrounding the
project, since their council work frequently pertained to environmental and technical issues. Two
CAB members stated that even though they were not familiar with the language used in the
project, they felt that Vandenberg personnel explained everything in a comprehensible manner.
EPA also stated that the Vandenberg staff presented technical issues effectively.
Differences in Interests and Perspectives Between Stakeholders

       .All interviewees stated that, other than the concerns raised by EDC, stakeholders did not
express any substantial differences in interests or perspectives.
Draft for participant review:
Vandenberg - 79
Do not cite or quote.

-------
Appendices


-------
                                  Appendix A
                          List of Interviewees by Project
 Andersen
 Abrahamson, Wally
 Barwick, Brian
 Birnbaum, Nancy
 Hogberg, Kirk
 Kellison, Jim
 Klein, Bill
 Ronchak, Andrew
 Van Zee, Ron
 Weissner, Carol
 Community Advisory Committee
 EPA Region V
 EPA Headquarters
 Andersen Project Lead
 Community Advisory Committee
 Community Advisory Committee
 Minnesota Pollution Control Agency
 Community Advisory Committee
 Community Advisory Committee
 Atlantic Steel
 Brian Leary
 Michelle Glenn
 Tim Torma
 Bernadette Smith
 Tim State
 Mike Brandon
 Shannon Powell
 Brian Hagar
 Mike Replogle
 Dan Cohen
 Connie Cooper
 Randy Roark
Project Lead, CRB Realty (Jacoby)
EPA Region IV
EPA, Headquarters
Home Park Community Improvement Association
Home Park Community Improvement Association
Chairman, Home Park Community Improvement Association
Midtown Alliance
Sierra Club
Federal Transportation Director, Environmental Defense Fund
City of Atlanta, Principal Planner, Current Planning
Facilitator (Cooper / Ross Consulting)
Urban designer and manager of the Home Park Charrette
(Georgia Tech)
ExxonMobil
Bass, Thomas
Bledsoe, Barry
West Virginia Division of Environmental Protection
Community Liaison Panel
Draft for participant review.
 List of Interviewees - 82
Do not cite or quote.

-------
 Brannegan, Dan
 Deady, Karen

 DelaHunt, John
 Frantz, George
 Hawkins, George
 Howard, Suzanne
 Butler, Kathleen
 Kelly, Anne
 Miller, Jim
 Shoener, Ed
 Stuart, Ralph
 Thomann, Wayne
 Thompson, Fay
 Walker, Sherri
 Zehra Schneider Graham
 Pfizer, Inc.
 Director, Environment, Health and Safety, University of
 Massachusetts, Boston
 The Colorado College
 EPA Region I
 Stony Brook Watershed Association
 Project Lead, Boston College
 Community resident, University of Vermont
 EPA Region I
 Massachusetts Department of Environmental Protection
 Ecologia
 Project Lead, University of Vermont
 Duke University
 University of Minnesota
 EPA Headquarters
 University Project Lead, University of Massachusetts, Boston
CK Witco
Barnhart, Jesse
Birnbaum, Nancy
McKnight, Jim
Peters, Eric
Pontivedos, Lucy
Termini, Beth
Tucker, Okey
CK Witco employee and union leader
EPA Headquarters
Stakeholder
Pleasants County Resident
West Virginia Division of Environmental Protection
EPA Region HI
former CK Witco Project Lead
Vandenberg
Dougherty, Jack
Higgins, Mike
McVay, Monty
Satillo, Mark
Segal, Sarah

Draft for participant review:
Santa Barbara, CA resident
Waste Water Authority, Santa Barbara County
Vandenberg Project Lead
Environmental Defense Center
EPA Region LX
  List of Interviewees - 84
Do not cite or quote.

-------
                                     Appendix B
                                   Research Method
        For each case, principal parties to the stakeholder process were interviewed using a semi-
 structured interview protocol. The interviews were designed to clarify the actors and events of
 each case, and to explain not only what conditions existed, but how and why they emerged.
 Interviews were conducted with participants in the stakeholder involvement process, including
 citizen representatives, environmentalists, project  sponsors, local and state officials, and EPA
 officials. A list of interviewees is presented in Appendix A.
        In each interview, the research team explored the interviewee's:

        •  perceptions as to the organization of the process,.

        •  involvement in the process, including their decision to participate, how they were
           invited to participate, and any involvement in their community or with the facility
           before this process began;

        •  perceptions as to whether the stakeholder participation process was well designed and
           implemented,  including whether it afforded the stakeholder a real opportunity for
           input, whether the level of involvement and the timeframe of involvement were
           appropriate, and whether there were any barriers to effective participation;

        •  perspectives as to what the stakeholder process was trying to accomplish, including
           whether the process goals were appropriate and successfully accomplished, and
           whether the process focused on the right issues, addressed those issues adequately, and
           brought  together the right people in the process to effectively represent stakeholder
           interests,

       •  roles of the stakeholders, and that of the company and EPA, in the development of the
          Project XL  agreement, including whether the roles were developed by the company
           alone or in conjunction with  other stakeholders, the stage in the decision making
          process at which stakeholders became involved, whether the roles were consistent with
          what the stakeholders envisioned when  they decided to participate,  and the
          effectiveness of these roles; and

       •  overall satisfaction of stakeholders with the stakeholder involvement process, including
          their perceptions about the major strengths and weaknesses of the stakeholder
          involvement process and suggestions for improving the process.

       The interviews  also explored the interviewee's perspectives concerning

       •  how technical  issues were addressed in the  stakeholder process and if this enabled
          technical information to be understandable to all participants;
Draft for participant review:
Research Method - 85
Do not cite or quote.

-------
                                     Appendix C

                                        Glossary


 Brownfleld: Abandoned, idled or under-used industrial and commercial facilities or sites where
 expansion or redevelopment is complicated by real or perceived environmental contamination.

 Clean Air Act: The Clean Air Act is the comprehensive Federal law that regulates air emissions
 from area, stationary, and mobile sources. This law authorizes EPA to establish National Ambient
 Air Quality Standards to protect public health and the environment.

 Clean Water Act: The Clean Water Act sets the basic structure for regulating discharges of
 pollutants to waters of the United States. The law gives EPA the authority to set technology-
 based effluent standards on an industry basis and continues the requirements to set water quality
 standards for all contaminants in surface water.

 Conditional Delisting: Use of the petition process to have a facility's toxic designation
 rescinded.

 Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA):
 CERCLA is the legislative authority for the Superfimd program which funds and carries out
 EPA's solid waste emergency and long-term removal and remedial activities. These activities
 include establishing of the National Priorities List (NPL), investigating sites for inclusion on the
 list, determining their priority, and conducting and/or supervising cleanup and other remedial
 actions.

 Comprehensive Operating Permit (COP): A COP replaces existing permit systems with a
 single operating and regulatory permit for a facility that encompasses Federal, State and local
 permitting requirements.

 F006 Listing: A hazardous  waste that is wastewater treatment sludge produced from nonspecific
 electroplating processes and operations.

 Final Project Agreement (FPA): The FPA outlines the details of the project and each party's
 commitments. The project's sponsors, EPA, State agencies, Tribal governments, other regulators,
 and direct participant stakeholders negotiate the FPA.

 Hazardous Air Pollutants: Air pollultants that are not covered by the National Ambient Air
 Quality Standards but that may have an adverse effect on human health or the environment.

Hazardous Waste: By-products of society that can pose a substantial or potential hazard to
human health or the environment when improperly managed. Hazardous waste possesses at least
one of four characteristics (ignitability, corrosivity, reactivity, or toxicity), or appears on special
EPA lists.

National Ambient Air Quality Standards (NAAQS): Standards established by EPA under the
Clean Air Act applicable to outdoor air quality throughout the country.

 Draft for participant review:               Glossary - 87                     Do not cite or quote.

-------
       Variance: Government permission for a delay or exception in the application of a given law,
       ordinance, or regulation.

       Volatile Organic Compound (VOC): Any organic compound that easily evaporates and
       participates in atmospheric photochemical reactions, except those designated by EPA as having
       negligible photochemical reactivity.
4»
      Draft for participant review:
Glossary - 89
Do not cite or quote.

-------

-------