^   o
         I
                                   United Starn
                                   Environmental ProMction
                                                    Officaof •.'-;     •-.'." >..'
                                                   -tn«Mctor Gwionl :
                                                    401 M Stratt. SW
                                                    Washington. DC  20460     /

                                                                                             • r-i' ''•''. ' ""   ;
                                                                                                  • -»-ir^a :
                                                                                                 '•*?$£$
                                      REPORT ON AUDIT OP EPA, REGION III /
                                    MONITORING  OF SUPERFDND  REMEDIAL SITES

                                  AUDIT  REPORT NUMBER E5eH7HJ3-0254-7190A

                                               September 15,
                                                                                  V-T-,/-;;-1
      I
              ..-   ': ..*:?.*»8&
            •:• .    , V:^'£.^2£v
.-••>-\:::x^*
                                     '•'-' •  • -  -,.--.>" • '.,'•...-• ~'  ^"'-S
                       '  ' •       *. .,. '••-*.••„•• ->.*-V •;. •-';•.>:  :'••*•£
                                                      ,:-,.r.s W-V1
                V.S.  Environmental Prota«t-loa
                Llb^rrv,  Room  3404  P»>21>^  i
                401 M Street,  S*ff.    -<•"*'


-------
                              TABLE OF CONTENTS


                                                                     Page
SCOPE AND OBJECTIVES	   1

SUMMARY OF FINDINGS	   2

ACTION REQUIRED	   3

BACKGROUND	   3


FINDINGS AND RECOMMENDATIONS

     1 - QUESTIONABLE NPL PLACEMENTS	.-	   5

     2 - DEFICIENT CONTRACTOR WORK PRODUCTS	   11

APPENDIX A - DISTRIBUTION	   17

-------
             UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                         OMICI Of THI (WtMCTOH QINIMAL

                             MIO.ATL.ANTIC OIVIIION

                             Ml CHltTNUT lUILDINO
                         PHILADtLPHIA, PENNSYLVANIA 191C7
September 15, 1987
MEMORANDUM
SUBJECT:
FROM:
TO:
Audit Report Number E5eH7-03-0254-71904
Report of Audit on Region Ill's
Monitoring of Supo/fund Remedial^Sites
P. Ronald Gandolfo
Divisional Inspector GeneH

James M. Seif
Regional Administrator
                                       for Audit
SCOPE AND OBJECTIVES

     This is the second in a  series  of reports we plan to issue on the audit
we conducted of Region III oversight of remedial Superfund sites administered
by the  Oomoonwealth of  Pennsylvania Department  of  Environmental  Resources
(DER).  The purpose  of this  audit  was to  evaluate actions taken  by DER to
clean up the  sites,  as well as the adequacy  of  EPA's stewardship over DER's
remedial program.   We  performed the audit  in  accordance  with  the Standards
for Auditof Governmental Organizations, Programs, Activities and Functions
issued by the Comptroller  General  of the United  States.   At the time of our
review DER  was  responsible  for  16  National  Priorities  List  (NPL) sites,
while 8 other  NPL sites had  been  recently transferred back to EPA  control.
We reviewed 19  of  these  sites plus  1  additional  site that was proposed to
the NPL.  Our fieldwork began  on July 1,  1986 and was completed on March 31,
1987.  During this audit we also:

     1.  Examined EPA and DER site files which contained various
         reports relating to past site activities.

     2.  Conducted interviews with EPA and  DER project officers,
         U.S.  Geological Survey staff, site inspection contractor
         personnel, and EPA Contract Laboratory Program officials.

     3.  Made  visits to several of the sites.

     4.  Discussed the preliminary results  of  our review with
         senior staff of the Region III Superfund program.

-------
 SUMMARY OF PIMPINGS

 1.   QUESTIONABLE NPL PLACEMENTS

          Region III  was overzealous  in proposing  two  sices to  the  NPL  in
     order to  qualify  them  for  the  remedial  program.    While  most  nomina-
     tions were  valid,  we believe  that two  sites  were  proposed  to  the  NPL
     based OD  inaccurate,  incomplete,  or  questionable  information.   This
     may have  occurred because  of  a  prior  NCP restriction  against  initiat-
     ing removals  at sites  that were not  Immediate  threats to  the  public
     or the  environment.  However   placing  these  sites  under  the  remedial
     program produced  a  variety of  results.   Site  cleanups  were  delayed;
     overall costs  increased;  site   conditions  deteriorated;  and,  most impor-
     tantly, public  confidence  in  EPA  was  diminished.   It  is  important
     to note that,  EPA  generally will  not  consider deleting a  site  from the
     NPL based  on erroneous  MRS scores  unless  an Rl/FS,  which  on  average
     costs $800,000,  shows  that  an  error  was  made.   We  recommend  that
     EPA evaluate  the   first  site as  a removal  candidate and  reanalyze  the
     second site to determine if it is in fact contaminated.

 2.   DEFICIENT CONTRACTOR WORK PRODUCTS

          DER and  Region  III  contract  management  needs  improvement.   We
     reviewed the  files for  20  remedial  sites  with  which  DER  had  current
     or past  association,  and  found  reports  of  contractor  studies  that
     were  submitted  late,  frequently  inaccurate,  and  sometimes of  question-
     able  value.   Based upon the documents  reviewed,  we  found  that contrac-
     tors  were  not  penalized and received full  payment for their  work.   We
     could not  always  determine  the  amount  of  these  payments  because prior
     to fiscal year  1986,  EPA did not  require  contractor billings to be task
     specific.  However,  we  estimate  the amounts  to be  substantial  based on
     the number and  size of the  documents  produced.  The  overall  result was
     that  the  remedial  process  to   address  potentially  hazardous  sites  was
     delayed, which ultimately  resulted in public  concern over  how the sites
     were  being  handled.  We  recommend  that  EPA aggressively monitor con-
     tractor performance  to  ensure   that  EPA  receives   high  quality  work
     products in  a  timely manner.   Region  III personnel  should  also  notify
     contracting officers  when  deficient  work  products  are   received from
     contractors.

     Preliminary draft findings were provided to the Hazardous Waste Management
Division  (HVMD) by  May 22,  1987.  On  July  13, 1987 a draft audit report  was
issued  to the  Regional Administrator.  We held  an exit conference with  HWMD
officials on  September  14,  1987.   During  this   conference  we  were  informed
that the  Region  would  not be providing written comments to  the draft report.
We were also informed  that the Region basically agreed  with  most  of  the facts
contained in the  report, but  not  necessarily  with the  report's conclusions
and  recommendations.

-------
ACTION REQUIRED

      In accordance with  EPA  Order 2750,  the  Administrator  of  Region III is
required to provide  this  office  with a written response to the audit report
within 90 days of the audit report.  If you have any questions,  please contact
me or Carl Jannetti at 597-0497.

      The courtesies  and  cooperation  extended  by your  staff  during this  audit
are appreciated.


BACKGROUND

      The "Superfund"  program  was established  by the Comprehensive  Environ-
mental Response, Compensation and Liability Act (CERCLA),   Public Law 96-510,
enacted on December  11,  1980.   The  Superfund program was created to protect
public health and the environment from the  release, or  threat  of  release,  of
hazardous substances  from abandoned  hazardous waste sites  and other sources
where response  was  not  required  by  other  Federal laws.    A  Trust  Fund  was
established by  CERCLA to provide funding for responses ranging from control
of emergency  situations  to  provision  of  permanent remedies at uncontrolled
sites.  CERCLA  authorized a $1.6  billion  program financed by a  five year
environmental tax on industry and  from  general revenues.   CERCLA requires
that  response, or payment for  response,  be sought from those responsible for
the problem.

      Superfund's taxing  authority expired on  September 30,  1985. , The avail-
able  funds from  fiscal year  1985 appropriations along  with estimated future
cost  recoveries  fell  $657 million short of planned fiscal  year 1986 program
requirements.  This  resulted  in a  slowdown of activities  from August 1985.
EPA received  interim funding  of  $150 million on April  1,  1986 which allowed
resumption of some cleanup activities.

     CERCLA was revised and  expanded by the  Superfund Amendments and  Reauthor-
ization Act  (SARA),  Public  Law  99-499,  enacted on  October 17,  1986.   SARA
reinstituted the environmental tax  and expanded the  taxing  mechanisms  avail-
able for a  five  year period.   It authorized  an $8.5  billion program for the
1987-1991 period.  The Trust Fund was renamed the  Hazardous Substance  Super-
fund.

     The basic regulatory blueprint for the Superfund Program  is  the National
Oil and Hazardous  Substances  Contingency  Plan  (NCP),  40 CFR  Part  300.  The
NCP was first published in 1968 as part of the Federal Water Pollution Control
Plan, and has been  substantially  revised  to  meet  CERCLA  requirements.  A
1982  revision  authorized the  following  types  of  responses   for  incidents
involving hazardous substances:
                            \
     o  Immediate Removal - a prompt  response at any site to
        prevent or mitigate immediate  and significant risk
        of harm to human life, health or  the  environment.
        Generally a removal is to be  completed  within 6 months
        or after expenditure of $1 million.

-------
     o  Planned Renoval - an expedited,  but  not  necessarily
        immediate response, at any site  (1)  where  there will
        be substantial cost savings by continuing  an  immediate
        removal when only a small amount of  work, is necessary
        to complete the cleanup, or (2)  when the public and/or
        the environment will be at risk  from exposure to  haz-
        ardous substances if response is delayed.  The 6
        month/$l million limitation also applies,  and States
        are required to contribute 10 percent of the  costs.

     o  Remedial Action - a long term usually more expensive
        attempt to achieve a permanent and cost-effective
        solution.  These actions usually require a series of
        extensive investigations and studies to determine
        remedial alternatives which will range from no further
        action to total site cleanups.  If EPA decides to take
        further action, the method selected is then designed
        and eventually implemented.  The NCP limits  these
        long-term cleanup actions to sites included on the
        National Priorities List (NPL).   This list desig-
        nates the nation's worst sites known to be con-
        taminated with hazardous substances.  NPL  sites
        are generally determined by EPA's Hazard Ranking .
        System (HRS) under which individual scores are
        developed based on the release or potential  for
        release, of hazardous substances into groundwater,
        surface water, and the air.  These scores  are
        weighed and combined to calculate an overall  site
        score ranging from zero to 100.   Sites scoring
        28.5 or higher are eligible for  NPL listing.

     o  Initial Remedial Measure - a cost-effective  expedited
        remedial response at an NPL site to limit  exposure to
        a significant health or environmental hazard.  Such
        actions can include the removal  of hazardous  substances
        found in drums, barrels, tanks and other bulk storage
        containers above the surface, or the removal of  highly
        contaminated soils largely at or near the surface.

     In November  1985,  a  second  revision  to  the   NCP eliminated planned
removals and  Initial  remedial  measures as distinct   response  categories.
As of  February 18,  1986  these responses  were  included  under  an expanded
removal authority.   By  quicker  response  EPA  hoped to  help   reduce  health
and environmental risks, as well as reduce long-term cleanup costs.

     At most  remedial  sites,  the States  must  pay  10  percent  of  the  costs
of the  remedial  cleanup.   CERCLA section  104(c)(3) provides  that no  reme-
dial actions  shall  be  taken  unless  the  State in  which the  release occurs
enters into a  contract or cooperative  agreement  with EPA to provide certain
assurances, including  cost-sharing.    Pre-remedial  activities   (preliminary
assessments, site  inspections)  remedial  planning  (remedial  investigations,
feasibility studies,   remedial  designs)  and   removals  may   be funded  100
percent by EPA.  For facilities operated by a State  or  political subdivision
at the time of disposal  of  hazardous substances,  the State must pay at  least
50 percent of  all response  costs, including  removals  and  remedial planning
previously conducted.
                                      4

-------
                         FINDINGS AND  RECOMMENDATIONS
 1.  QUESTIONABLE NPL PLACEMENTS

     Region III was  overzealous in proposing two  sites  to  the NFL in order
 to qualify them for the remedial program.   While most  nominations  were valid,
 we believe  that two  sites were  proposed  to the  NFL based  on  inaccurate,
 incomplete, or questionable information and  that a removal  action at a third
 site would have prevented a bad situation  from  becoming  worse.  These situa-
 tions may have occurred because of a prior  NCP restriction against initiating
 removals at sites that  were not immediate threats to the public or the environ-
 ment.  However, placing  these  sites  under the  remedial program  produced  a
 variety of  results.   Site  cleanups were  delayed;  overall  costs  increased;
 site conditions  deteriorated;  and,  most   importantly, public  confidence  in
 EPA was diminished.   It  is  important  to  note  that,  EPA generally will  not
 consider deleting a  site  from the  NPL  based on erroneous HRS  scores unless
 an RI/FS,   which on  average costs  $800,000,  shows that  an error  was  made.

     At the time of  our  review, DER was still responsible  for  16 NFL sites.
 We examined the files  for  14 of these sites, plus one additional site  being
 proposed to the NPL, and found conflicts  between  DER and the Region on the
 disposition of  three of  the Sites.  DER requests  for  removal  actions  at the
 Voortman and Hebelka Sites  were denied by  the  Region  which wanted the  sites
 studied under the remedial program.  The apparent lack of action at Voortman,
 coupled with deteriorating  site conditions, resulted  in public  criticism of
 both EPA and DER.   It now appears  that  EPA's  inaction will result  in a similar
 condition at Hebelka.   We  believe that more  expeditious cleanup  action at
 Voortman could have  prevented  many of  the problems  experienced,  and that a
 removal action at Hebelka now could prevent  development of a similar situation.

     At the third site, East Mount Zion, the samples taken by an EPA contrac-
 tor disagreed with  earlier DER sample  results  used to  qualify the site for
 the NPL.   We  believe  that  the East  Mount Zion  site should  be   re-examined
 before procurement of additional  costly and  time  consuming  remedial studies.
Discussion of the specific  issues concerning these three sites are presented
 below.

                                    Voortman

     The Voortman farm site ranks  number 700 on the NPL  with an HRS score  of
 28.62.  It is an example of what  can go wrong  when cleanup action is excess-
 ively delayed.  The  site  is a sinkhole over a  groundwater  channel that  con-
 tained an  undetermined amount  of  battery  casings,  tires, drums  and   other
debris.  A  local  township  official brought it  to the  attention of  DER  and
Region III in March 1980.   Over the next  six  years  DER  and EPA  commissioned
various studies and investigations; debated  over site  cleanups, and inadvert-
ently confused  the  public  by  indicating a removal would occur, when in  fact
money had only  been obligated for  further studies.   The site owners refused
DER access to  the  site,  and  in time the  batteries  subsided  further towards
 the groundwater.  DER  was  still trying to  contract for  remedial  studies  when
a fire at the site made a removal  action necessary.

-------
     Between 1980 and  1981  local township, county, and state  officials pres-
sured DER to take action.  OER investigated the site, searched for responsible
parties, and issued  an Administrative Order  to  the owners  to  clean up the
site.  The site  owners appealed the order to the Pennsylvania  Environmental
Hearing Board and  the  natter was still unsettled  six years  later.  In  1981
DER and local  officials noted  that  materials had  subsided  deeper into the
sinkhole,  however  in  1982  a DER  contractor  reported no  contamination  in
samples of nearby  wellwater.   The  same contractor  computed an HRS  score  of
28.62 and EPA placed the site  on the  NPL.   In 1983 another  contractor  con-
ducted a site investigation,  but did  not  issue a report until  1985.   Noting
that about half  the  batteries had  disappeared into the sinkhole,  DER  in the
fall of 1984 recommended their  removal as an initial  remedial measure  (IRK),
and offered  to   pay  10Z of the cost.   The  Region considered the  site  an
immediate removal  candidate  and declined  DER'8  offer.   The  Region  also
obligated $513,000 on  September 27,  1984  for DER  to  contract for  remedial
RI/FS studies.    In a March 1985 public meeting, the  regional project officer
indicated that an  "Octoberish"  removal might take place.   Subsequent  to the
meeting, DER and EPA's  Emergency  Response  Team  (ERT) arrived at differing
conclusions concerning  site  samples.  In Hay  1985,  ERT  reported  that the
threat was not immediate.   However,  ERT  also pointed  out that  a  removal now
would be relatively  quick  and inexpensive,  while further delay could  result
in the casings subsiding into the groundwater.  DER argued that ERT misinter-
preted the situation  and  that  the  threat  was  immediate.    In August,  1985
the Region decided  against a  removal  and instructed  DER to  expedite RI/FS
procurement.   The  local  township,  learning  that  DER requested  proposals for
remedial studies, asked  about the  October removal that EPA had mentioned  in
the March public  meeting.   The Region notified  the township  on  October 16,
1985 that   since  there  was  no immediate  threat  the  site  would  be  more
thoroughly studied through the RI/FS  process due  to  begin  the  next  month.
DER was still negotiating  the RI/FS  contract  11  months later  when  the  site
caught fire and  burned for two weeks.  A DER removal contractor  took out a
portion of the batteries, but could not get  them  all  since  some had subsided
too far into the hole.  The effect on the groundwater was  unknown.

                                   Hebelka

     This site is  a potential  Voortman.   Hebelka  is a  junkyard containing
battery casings  and  abandoned  vehicles.   In 1986, EPA proposed  the  site  to
the NPL and  announced plans  to spend  $500,000 for  remedial  studies.   We
believe that  full-scale  RI/FS studies are not needed, and  that the  batteries
should be  removed now to  prevent  the  recurrence  of  what  happened  at  the
Voortman site*

     Since 1982  DER, EPA,  and various firms  under  contract  to both agencies
periodically inspected  the site.   A 1985 report  on  a  1983 site  inspection
indicated that,  although there had been no  groundwater contamination,  there
was a threat of  contamination if the estimated  750 cubic yards of  batteries
in the piles,  and 250 cubic yards  in the  vehicles,  were  not removed.  DER
requested a  removal,  but  Region   III opted to  take  the  remedial   route.
Between June  1983 and  June  1985,  the site  received  six  HRS  scores  ranging

-------
 from 18.2  to  31.94.   In 1986 EPA proposed the site to the NPL and announced
 plans to  spend $500,000 for  an 18 month  RI/FS study  which would include:

      "...  definition of the nature and extent of the problem at
      the site, characterization of the hazardous substances
     present, a hydrogeological Investigation, soils and sediments
     analysis, a surface water investigation and air investigation,
     the development of remedial response objectives, the identifi-
     cation of remedial action alternatives, evaluation of the the
     alternatives, an environmental assessment of the alternative,
     cost  analyses, recommendation of  a cost-effective remedial
     alternative, conceptual design of the proposed alternative,
     and community relations activities."

 The  community relations activites would be conducted:

     "...to inform and receive input from public officials and the
     affected community.  These will include preparing a community
     relations plan, holding public meetings, organizing press
     conferences and workshops, distributing press releases,
     speaking to concerned citizen's groups, preparing fact
     sheets, and establishing a community relations repository."

     We believe that the site  does not merit  placement  on the  NPL,  and that
 the  Region should  simply remove  the  batteries.  This  belief  is based  on a
 review of  the  site  file, visits  to the  site, and  interviews  with  personnel
 from Region III, DER, the U.S. Geological Survey (USGS), and the site inspec-
 tion contractor.  The  site  was only  proposed to the NPL  after a series  of
 six  HRS  rankings.   The fifth  HRS document  prepared by the  site  inspection
 contractor scored the site at  21.2, well  below the 28.5 NPL threshold.  This
 document was dated June 28, 1985.  The sixth HRS document, which was prepared
 by the contractor and a Region III employee,  scored the site at 31.94.  This
 document was also dated  June  28,   1985.  Both  documents cited the  aquifer of
 concern as being a  groundwater basin  consisting of "hydraulically  intercon-
 nected" flows  from  separate  rock formations  which in  effect  functioned as
 one  aquifer.    The primary  reason  for the score differences  between the  two
 documents was how the distance between the  ground  surface and the aquifer of
 concern was  calculated.   The  first  document  calculated the distance  at 80
 feet, while  the second  document, citing  the  depths  of  two  private   wells
within three miles  of  the  site,  calculated  the  distance at  6 feet.   Both
documents referenced a "Water Resource Report" prepared by  the  U.S. Geological
 Survey.  We contacted  one  of  this Report's authors at  USGS  who informed us
 that:

     (1)  The hydraulic interconnection between  the  formations was
          relatively poor,  and there was little  likelihood  that
          they would function as one aquifer.

     (2)  The wells cited in the second document were too  far  from
          the site to have a direct bearing,  and did not
          necessarily provide analogous information  to  the
          hydraulic settings on site.

-------
      (3)  The aquifer of concern was at least 100 feet below the
          ground surface.

 Our  recomputation of the HRS score  based  on this information yielded a  score
 of only 19.16.

      Based on a site inspection, DER in June  of  1985  recommended  that  Region
 III  remove the  batteries.  DER  received  no response until June 1986 when  it
 was  learned that EPA was proposing the site to the NFL.  Contractor personnel
 responsible for  the site  inspection  were  also of  the  opinion, that  the
 batteries should  be removed and  that  the  RI/FS  was  not  warranted.   Region
 III  personnel  informed  us  that the site had been evaluated as a  removal
 candidate, but  that the NCP precluded a  removal  action.   We disagree with
 this  position  and  believe  that  the   revised  NCP  does  now authorize  such
 response under  the  expanded  removal  category.   We  also  learned that  the
 Region had never  considered  the site  for a removal action, and  that  no  one
 from EPA had ever visited the site to make such an evaluation.

      We visited the  site  on three  separate occasions.  We  found that, con-
 trary to the Region's  belief  that the site was  closed,  it  was in fact open
 for  business*  There were  indications  that plates  were  being  extracted from
 the  battery casings, and that underground gasoline storage  tanks were recently
 dumped on site.

                               East Mount Zion

     This site  ranks  346 on the  NPL with  an ERS  score of 41.01, primarily
 based on DER sampling  results.  There  is however,  an  unresolved  question
 whether the  site  actually  contains  hazardous  substances,  as  subsequent
 sampling by  an EPA  contractor did  not  confirm the  earlier DER findings.
 Since we found  no evidence  that  this sampling  issue was ever  settled,  we
 believe that  a  reanalysis  is  warranted  before   initiation  of  additional
 remedial measures.

     The East  Mount Zion  site is  a landfill that was  closed   in  1972   for
 operating without a permit.  Based  on  samples taken by DER, EPA  proposed  the
 site to the NPL in  September 1983.  The  narrative supporting the  NPL  listing
 stated that paint thinner  and  electroplating sludge were  known  to have been
 disposed on the  site,  and that DER  had  detected vinyl  chloride  and  benzene
 in the groundwater,  as  well as various  priority pollutants  in  the  sludge.
During November  1983,  an  EPA  contractor  conducted  a  site  inspection.   On
 September 27, 1984  the  Region  obligated  funds for  an RI/FS, and  at the time
 of our review  two years later, DER  was  negotiating the award of a $933,795
 contract.  We subsequently learned  that  negotiations  were terminated  because
 the contractor  raised  the  price,  and  the DER was  seeking to initiate a  new
procurement.

     It is still  unclear  what, if  any,  hazardous  substances  were placed on
 the site.  DER samples  taken in  1983 indicated that the site was contaminated,
 but other samples,  also taken  in  1983, by  an EPA site  inspection contractor
did not confirm the  DER results.   Unfortunately,  the  EPA contractor  did  not
 report the  site  inspection  results   until  late  1984,   one  year after  the
site was placed on the NPL.

-------
      In a  November,  1984  assesseuent  of  the  site  Inspection  results,  a
 Region III toxicologist reported that:

      "Problems concerned with this Site Inspection document relate
      to inconsistencies between the State analytical  results and
      the findings of the EPA analysis.  The site  was  placed on
      the NPl because of the reported presence of  vinyl chloride
      and benzene in the groundwater taken from a  downgradient
      monitoring well during the State analysis.  These substances
      were not detected during the EPA analysis."

      The Toxicologist concluded that, "since this site was placed
      on the NFL because of this state data it could seem reason-
      able to initate a reanalysis of all possible groundwater
      sources including the Test Well before any further remedial
      measures are undertaken."

     We interviewed  the  toxicologist  and  the  regional  project  officer  who
 both Indicated that  the  dispute  over the samples had not  been resolved.   We
 found no evidence that  the issue was  settled beyond verbal assurances  from
 DER, that the  state data was valid,  and that the EPA  contractor's was  not.

     The most  recent  report on  the  site was  a Remedial-  Action Master  Plan
 (RAMP) prepared by  a  DER contractor in  1984  to summarize  available informa-
 tion concerning the site.  Rather than settling the  contamination issue how-
 ever, the RAMP made it more confusing.   For example, the  RAMP assumed  that
 the site may contain hazardous substances,  because there were no site opera-
 tion records  to  prove  otherwise.   The  RAMP also  mentioned  an unconfirmed
 statement by a person  who  claimed to  have  dumped  paint thinner on the site,
 and a notation that on one  occasion a septic tank truck was observed dumping
 sludge.  The sludge was reported to  be from the  settling  tanks  of  a chain
 and cable company.   As  for the DER  samples, the  RAMP reported that  an  off-
 site well sampled  by DER  was  not  ideally  located to  intercept groundwater
 leaving the site,  and that DCR  had not actually  found  sludge  on  site,  but
 rather had found contaminants  in the settling tanks located at  the chain and
 cable company.

     Based on  the  above, we  agree  with  the Region  III toxicologist that a
 further analysis  should  be performed  before additional remedial measures are
 initiated.

Conclusion

     Under Che 1982  NCP, the Agency's option to initiate  removal actions was
 limited to sites  considered  to  pose  an immediate threat  to  the  public or
environment*   Therefore,  it  is   plausible   that  this  restriction  may  have
 increased the  Region's motivation  to  propose sites  that  did  not  fit  the
 removal category   to the  NPL  for  remedial  action.   However,  placing   such
 sites under the  remedial program has  increased costs  and  delayed  cleanups.
Remedial sites undergo  a vast  array of  time-consuming studies  that  can  take
 four years to procure and complete.  Unless  an  immediate threat arises,  there
was little likelihoood that such sites would be cleaned up before the studies
were completed.  Moreover,  EPA  was reluctant to  conduct  cleanups  as initial
 remedial measures (IRMs),  as  evidenced  by  a March 1985 GAO. report entitled,

-------
Cleaning Up Hazardous Wastes;  An Overview of Superfund Reauthoritation  Issues
(GAO/RCED-85-69).   GAO cited  a  December 1984 EPA report which admitted  that
relatively few  IRMs  were  undertaken  because  little  distinction  was  made
between the type  of  on-site  activities  conducted for  IRMs  and for removal
actions*  The criteria  established  in the  NCP  for  determining whether  to
conduct an  IRM  were essentially  the  same  as the  criteria for  determining
the need  for removal  actions*   However,  EPA  required  substantially  more
documentation for   IRMs  than  for removal  actions.   This  documentation  was
required to ensure that  the  action  taken  was cost-effective, and  to  enable
EPA to  demonstrate  for  cost-recovery purposes  that  initial  actions  were
consistent with  the NCP*   Because of these additional administrative require-
ments, IRMs were more time-consuming to conduct than removals.

     EPA is frequently criticized for  not having cleaned up more  NPL  sites.
This is an  oversimplification of a complicated and time  consuming process.
We noted  that a  great deal   of  progress has  in fact  been  made at some of
the sites  we reviewed.   Several  sites  were either  partially or entirely
cleaned up, and appeared  to  only require monitoring or  completion of  infor-
mation gaps.  We  commend both EPA and DER for these successes.  However, as
shown above, we  believe the Region has unnecessarily complicated its workload
by placing some  sites on  the  NPL as remedial candidates, that could possibly
now be more expeditiously handled as removal projects under the revised NCP.

Recommendations

     We recommend  that Region III:

          1.  Evaluate the Hebelka  site as a  removal candidate.

          2.  Conduct a  reanalysis  of the East Mount Zion site
               to  determine if it is in fact  contaminated with
              hazardous  substances.
                                       10

-------
 2.   DEFICLEMT CONTRACTOR WORK PRODUCTS

     DER and Region III  contract management needs improvement.  We  reviewed
 the files for 20 remedial sites with which DER had current or past association,
 and found reports of contractor  studies that were  submitted late,  frequently
 inaccurate, and sometimes of questionable  value.   Based upon the documents we
 reviewed, the  contractors  were not penalized and  received full payment for
 their.work*   We could  not always  determine the  amount  of  these  payments
 because prior  to  fiscal  year 1986, EPA did  not  require  contractor  billings
 to be  task  specific.   However,  we estimate  the amounts  to  be  substantial
 based on the  number and  size of the documents produced.   The  overall  result
 was that  the   remedial  process  to  address potentially  hazardous  sites was
 delayed, which ultimately  resulted in public concern  over how  the  sites  were
 being handled.

     A great portion of the Superfund  remedial program was contracted  out  to
 private firms.  Region 111 assigned contractors  to perform site inspections,
 conduct responsible party  searches, and  calculate HRS scores.  DER hired  a
 contractor to  assemble  procurement proposals,  and  compile site  background
 reports.  EPA  funded  all  these  assignments  either directly  through  Agency
 contracts, or  indirectly  under  the  cooperative  agreement with  DER.   For
 various reasons we were unable to examine  all of the reports for the sites  in
 our review.  DER was  in  a  file  reconsolidation  process.   Portions  of  files
were in boxes,  or in use at  other  DER  offices,  or being  reviewed by prospec-
 tive RI/FS contractors.  Likewise,  some reports  were not  on  file at  Region
 111 because they were evidently being used by the various  Superfund  sections.
 However, we were  able to  review the  bulk of the work  products  associated
with the contractor studies.   We found that while some were of high quality,
others were not, which raised the question whether EPA received all that  it
paid for.  Specific comments are presented below.

                               Site Inspections

     Late issuance of  site inspection  reports  delayed  the cleanup process.
Sites with waste problems suspected to be hazardous undergo site inspections.
The inspections generally  include a one  day  visit by an EPA  contractor who
takes soil and groundwater samples that  are later analyzed to evaluate the
seriousness of the problem.  The report on the  site visit  frequently becomes
a key element  of  the HRS  score,  which in turn determines placement  on the
NPL.  There were occasions, however, where  contractors computed  scores without
ever visiting the sites.

     We found  site  Inspection reports for  9  of  the  20  sites in  our  review.
 In several instances,  it had taken the contractor up  to  two years  to finalize
the results of these  one  day  visits.   For example,  samples  taken  at the
Voortman Farm  site  by the  contractor  underwent  review  for one year, and  it
took an additional six months to issue a  report.   It took two years to  issue
the Hebelka inspection  report.  It took  one year to  issue a report for the
Osborne site,   and most of  the test results were of  questionable  qualitative
significance based on a quality assurance  review.   The East Mount  Zion report
was more than  a year  overdue,  and  the test  results  conflicted  with  those
submitted earlier by DER.   Region 111 personnel  blamed most of these  delays
on contractor  inability  in  the  past   to  obtain  timely  lab sample  analyses.
By contrast, we  noted that DER  and ERT inspection results for three  of  the
nine sites were finalized within six months.

                                       11

-------
                 Potentially Responsible Party (PRP) Searches

      Region III files  contained reports of contractor attempts to  determine
 the  parties  responsible for contaminating five  of  the sites in our  review.
 Two  of  the reports appear adequate in that the contractor went beyond  review-
 ing  DER/EPA  files.   The reports  reference  contractor visits and  interviews
 with various  parties,  which ...resulted  in  identification of  PRPs  previously
 unknown to EPA.  There is a question, however,  as  to the  value of  the  other
 three reports.  For example, one  report  was basically a  recapitulation  of  an
 earlier site  inspection  report,  plus a property title search performed  by a
 subcontractor.  No  new  PRPs  were  identified.  The   report  advised  EPA  to
 visit the  site,  interview the  owner,  appraise the property, hire  a  private
 investigator  to interview neighbors, and contact employees of the  PRP  already
 identified in the regional  files.  The  responsible  party search for a second
 site was assigned by Region III  to a contractor in Illinois, who subcontracted
 the  assignment to a  company in Massachusetts.  A North  Carolina  division  of
 this second company  subsequently  subcontracted portions  of the assignment  to
 a private  investigator,  and a  law firm  in  Pennsylvania.  The Region  rated
 the  contractor's report  as  unsatisfactory,  but accepted  it so that EPA could
 "control and  conclude  the  research." The  report alleged various  responsible
 parties, but  as  noted  by the  regional enforcement  officer no attempt  was
 made to confirm the  allegations.   The  only individual clearly established as
 a responsible  party  was the  site  owner.    Specific comments  made  by  the
 enforcement officer on this work  assignment were:

     o  the assignment was completed five months late, and sub-
        mitted in two sections instead of being edited into one
        concise report*

     o  Region III was seldom appraised of on-going developments
        and constant prodding was necessary to complete  the
        project.

     o  Numerous copies  of documents submitted were illegible.

     During the same  time period, Region  III assigned the responsible party
 search  for a third site  to the same contractor in Illinois, who again subcon-
 tracted with the firm  in Massachusetts.  Basically the  report duplicated  the
 findings of  a DER   investigation  completed   five   years earlier.   No   new
 information vas supplied to the  Region.   The report  advised EPA to contact
 PRPs; assess  their  financial  status;  and identify, locate,  and interview
 other individuals who might possess useful facts.

                      Hazard Ranking System (HRS) Scores

     Sites receiving an  HRS score of at least 28.5 qualify for NPL placement
 and  remedial  Superfund  expenditures.  Scores  for the 20 sites in  our  review
 were computed by EPA contractors, and  reviewed by DER and  Region  III.   Revi-
 sions of the  contractor scores  were fairly  common.   At  least  11  of the  20
 sites had multiple  scores.  Some of the score  revisions were due either to
 a reinterpretation of existing data, or  to  the discovery of  additional  infor-
 mation.  He were unable, however, to determine  the rationale for  some  score
 changes due to data  gaps  at  both agencies,  i.e. the  files did not contain
 all  of  the referenced  scoring documents.   We  did note that  7 of  the  11  sites
with multiple scores did not  qualify for NPL  status  until  after  their  scores

                                       12

-------
were revised.   Coupled with the file  data  deficiencies,  this  raised  several
questions.  Here the contractors  competent,  or was the Region  overzealous to
get the sites  on the NFL?  Although we could draw  no clear conclusions, we
do believe the Region needs  to more  closely Monitor the site scoring process,
and to better  document  site files to explain why  revisions are made*   This
need is demonstrated below.

     o  The Craig Faro site  ranks  number 699 on the NPL based on
        a score of 28.71 computed  by an EPA contractor on July
        23, 1982.  We found  reference  to a second score of
        24.44  in an August 27, 1982  draft list of Region III
        NPL sites submitted  to EPA Headquarters.  We were
        unable to determine  the origin or the basis upon which
        the lower score was  calculated.

    , o  The Berks Sandpit site ranks number 597 on the NPL.  An
        EPA contractor computed an URS score of 31.99  on April 1,
        1983.   A memo in the DER file  Indicated that EPA Head-
        quarters found an error which  lowered the score to  26.02,
        but that the Region  "... is  working on this  to try  to get
        the score back over  28.5."  On June  18, 1983,  Region III
        scored the site at 32.02.  We  were unable to obtain the
        earlier scoring documents  to establish what  caused  the
        score  increase.

     o  The Westinghouse Elevator  Plant ranks number 458 on
        the NPL.  An EPA contractor  drafted an HRS  report
        dated  March 2, 1984  which  scored the site at 27.28.
        DER examined the report and  concurred with  the score.
        Region III did not concur.  The score was raised  to
        36.38  because the contractor had used  the wrong
        compound to calculate  the  "toxicity and persistence"
        of site wastes, and  because  Region  111 personnel
        believed the contractor had  underestimated  the
        number of people served by domestic wells.

     o  The Shriver's Corner site  ranks number  235  on  the  NPL.
        The site is actually two  separate  properties upon which
        the local township chairman  allegedly  dumped wastes pur-
        ported to be from the  Westinghouse  Elevator Plant.  In
        May 1983 DER inspected one property,  "drove past" the
        second property, and estimated that the  two sites con-
        tained 90 drums.  In 1984, an EPA  contractor drafted two
        HRS reports scoring  the sites  at  14.94 and  13.91.   The
        contractor relied on DER  files to  compute the  scores
        without ever having  visited  the  sites.   DER examined
        the reports and concurred with the scores.   Region  III
        did not concur.  Also  vising  DER files,  the Region com-
        bined  the sites and  arrived  at a  single  score  of 46.13.
        Aside  from considering the properties  as a single site,
        the increased score  resulted from the  Region's assertion
        that:   (1) there was an  observed  release of wastes  into
        the groundwater, (2) the  wrong compound was used to
        calculate the "toxicity  and  persistence" of the
                                      13

-------
        site wastes, (3) the surrounding population  had been
        underestimated, and (4) based on testimony supplied
        to DER by the alleged dumper, approximately  1,200
        drums of waste had been emptied on site.

     o  The He be lit a site is being proposed to the NPL.  Between
        June 1983 and June 1985, an EPA contractor computed six
        HRS site scores ranging from 18.2 to 31.94.   The first
        three scores were considered Invalid because the con-
        tractor used a wrong site location.  The  next two  scores
        were unacceptable because the Region believed the  con-
        tractor miscalculated the distance between  the ground
        surface and the water table.  The sixth score,  the only
        score above 28.5, was accepted.  As seen in  the finding
        entitled "Questionable NFL Placements," this score is
        also invalid because the Region miscalculated the
        distance between the ground surface and the  water  table.

                       RFP/Qs RAMPs and RI/FS Workplans

     Originally DER hired a consultant to prepare Request  for Proposal/Quali-
fication (RFP/Q)  specification  packages  for use   by  prospective  contrac-
tors.  However, after  initial  submissions proved unsatisfactory,  DER removed
the consultant from  this  job function, and prepared its  own specifications.
The same  consultant  was  tasked  by DER  to  prepare  Remedial  Action  Master
Plans (RAMPs) and RI/FS  Workplans.  A RAMP is a summary  report  of available
site background data,  that  is  generally extracted  from  DER and  EPA  files.
The RAMP is used to develop an RI/FS Workplan report,  which  is an outline of
tasks to be done  during  the actual RI/FS.   These reports are  also presented
to inform  the  public  of  actions taken  in  the past, and actions planned in
the future.

     RAMPs and Workplans  were prepared  for  11 of   the 20 sites  for approxi-
mately $20,000 per 'site.   The contractor was  required to first  submit draft
reports for  EPA and DER review.   After draft  revision  the consultant  was
then to  submit  final  reports for  use by DER,  EPA, RZ/FS  contractors,  and
the general public.  We found that  reports for 10 of the  sites were submitted
between two and six  months  late, and many of the reports were deficient.  To
a large  extent,  the  deficiencies  occurred  because the   consultant  never
visited the sites.  The  reports  reflected the consultant's interpretation of
existing DER  and  Region III  files.   Consequently,  the reports contained
errors.  Some  were  detected,  others  were  not.   In any  event,  DER and the
Region were forced  to  spend a considerable  amount  of time and effort  to try
to correct the errors.  For  example,

     o  the East Mount Zion  RAMP incorrectly  described the site
        as wooded.

     o  the Welsh Road RAMP  mentioned  the existence of a  number
        of 55-gallon drums containing  coolant wastes;  the Workplan
        did not.  Neither report explained  that  EPA had sampled
        the drums and  found  that they  posed  an Imminent threat
        of fire and explosion.
                                       14

-------
      o The Shrivers Corner RAMP/WorkpIan reported that  In  the
        Spring of 1983 there were an estimated 500 full  drums
        on site, despite the fact that a Hay DER 1983 inspec-
        tion indicated there were only 90 drums on site.

      o One section of the Hunterstown Road RAMP/Workplan
        reported the dumping of approximately 600 drums, while
        another section indicated that approximately 1,200
        drums had been dumped.

      EPA also had contractors prepare RAMPs  and  Workplans  for  several  sites.
However, DER  criticized these  studies   as  not  being  site specific.   In  a
March 1986 newspaper  article, a  DER official  stated that reports  prepared
for  the Ha vert own and Brodhead  Creek sites by an EPA contractor  were  redone
by the DER consultant.   this delayed  progress  on the Havertown site  for
six  months.   The  Brodhead Creek  situation  was  even more complicated.   The
state official neglected to mention that DER had already rejected the revised
Workplan prepared by its consultant,  and had compiled a third  version  of its
own.   Morever, DER's  Workplan Incorporated  portions  of a study  prepared by
a consultant hired  by the  site owner.   Therefore,  there were  four Workplans
for  Brodhead Creek, three of which were funded by EPA/DER,  and it took almost
two years  to  obtain an  acceptable product.   Understandably,  the  public
became upset.   For  example,  Havertown   Township  officials complained  about
delays and said  that residents  were extremely  frustrated over the lack of
progress.  Also, Region  III  mistakenly  informed a local community group that
RAMPs  and  Vorkplans for  the  Westinghouse  Elevator,  Hunterstown Road,  and
Shrivers Corner sites would  be finished in May 1985.  However, contractually
the DER firm was not  required to submit final draft reports until August 31,
1985.  And, because of  deficiencies in  these  drafts, final  reports  were not
available until April  1986.   As  a result,  a local community  group accused
DER of "inexcusable failure."

Conclusion

      Region III needs to become  more aggressive  in  evaluating the products
produced by contractors.   While  we  understand  that the  award of  the  site
inspection, responsible party  search, and  HRS scoring contracts  is a Head-
quarters function, this does not  preclude the Region from actively supervis-
ing specific  site  projects assigned  under these contracts.   If  the reports
produced by contractors are  late, or flawed to  the extent that they require
numerous revisions, the Region should make  the  contracting officer aware  of
the contractors1 lack of  performance.   On  the other hand,  if EPA personnel
are requesting  revisions  that are  not  really necessary,  Regional management
should determine why,  since they  are costly and  contribute  to site cleanup
delays.

     Contract administration problems are not a  new issue. Reviews  conducted
by Region  III during 1983 and  1984 under  the  Federal  Managers'  Financial
Integrity Act  identified  weaknesses  in  Superfund  contract  management  over-
sight.  Regional management  estimated  that  approximately 10  to  20 percent
of the 1983  Superfund  budget could  have been  saved  if  contract  oversight
was improved and  warned  that  EPA's  public  image  would  be  tarnished if  it
                                       15

-------
appeared that contractors were too ouch in control of the process.  Based  on
the issues discussed above,  we believe that Region III still  needs  to  improve
its administration of contracts.

Recommendation

     Ve recommend that the Regional Administrator:

     1.  Aggressively monitor contractor performance to  assure
         that EPA gets work products that are timely and of
         high quality.

     2.  Notify EPA contracting officers of deficient contractor
         work products.
                                       16
                                                                              oo

-------
                                                                 Appendix A


                             REPORT DISTRIBUTION




Recipient                                ... -                        Copies


Office of the Inspector General     .  .            --


  Inspector General (A-109)                                              1




Regional Office


  Administrator of Region III                                            2


  Director, Hazardous Waste Management Division                          1


  Audit Follow-up Coordinator                                            1




Headquarters Office


  Director, Financial Management Division (PM-226)                       1


  Comptroller (PM-225)                                                   1


  Agency Follow-up Official (PM-208)

    Attention:   Resource Systems Staff                                   1



  Associate Administrator for Regional Operations (A-101)                1
                                                                                 a
                                                                                  en

                                                                                   V
                                       17

-------