V
                          Report  of Audit
>vt J-  -
                               REPORT. OM AUDIT 0? EPA, REGIO* HI
                             MONITORIHG OF SDPERfUHD REMEDIAL SITES

                            AUDIT REPORT JIUMBEE E3«H6-03-022»-71903

                                     September 15, 1987
                                            .'«•'-•••••• l».     .  :„.•-
                                               •• " . •£•'•- •' • •!•.•»*
                               U.S. Envlrorunental Proteotlva
                               Library. Raom 2404  PH-21V4
                               ;«0l M- Street, S.W.
                               •aahingtou, DO  20460


-------

                              TABLE OF CONTENTS



                                                                     Page
SCOPE AND OBJECTIVES	   1

SUMMARY OF FINDINGS-.	   2

ACTION REQUIRED.	   3

BACKGROUND	   3



FINDINGS AND RECOMMENDATIONS

     1 - SITE CLEANUP DELAYS	   5

     2 - TRANSFER OF ENFORCEMENT SITE.S	   14

APPENDIX A - DISTRIBUTION;	   18

-------
            UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                        OMICt OP TMI INtflCTOH OfNIHAL

                             MID.ATLANTtC OIVIIION       ,

                             §41 CHIITNUT • UllDINO
                        PHIUADf LPHIA. PENNSYLVANIA  ItIS?
September 15,  1987

MEMORANDUM

SUBJECT:  Audit Report Number E5eH6-03-0228-71903
          Report of Audit on Region Ill's
          Monitoring of Supe^fund Remedial Sites
FROM:
TO:
          ft
P. Ronald CandoJ
Divisional Inspector Gene]

James M. Seif
Regional Administrator
                                       for Audit
SCOPE AKD OBJECTIVES

     This is  the  first  in  a   series  of  reports  we  plan  to  issue  on the
audit we  conducted  of  Region  Ill's  oversight of  remedial  Superfund sites
administered by  the  Commonwealth- of  Pennsylvania Department  of  Environ-
mental Resources (DER).   The purpose of this  audit was to  evaluate  actions
taken by DER to clean up the sites, as well as the adequacy of  EPA's steward-
ship over DER's remedial program^   We  performed the audit  in accordance with
the Standards for Audit of Governmental Organizations, Programs,  Activities.
and Functions issued  by  the Comptroller General of  the  United  States.  At
the time  of  our review DER was responsible for  16 National Priorities List
(NPL) sites,  while  8 other  NPL sites had been recently transferred  back to
EPA control.  We reviewed 19' of these  sites plus  1 additional site that was
proposed to the NPL.   Our fieldwork began on  July  1,  1986 and was completed
on March 31,  1987.  During  this audit we also:

     1,  Examined EPA and DER site  files which contained various
         reports relating to past  site activities.

     2.  Conducted interviews with EPA and DER project officers,
         U.S. Geological Survey staff, site inspection contractor
         personnel, and EPA Contract Laboratory Program  officials.

     3.  Made visits  to several of the sites.

     4.  Discussed the preliminary results of  our review with
         senior staff  of  the Region III  Superfund program.

-------
SUMMARY OF FINDINGS                                                -

!•  SITE CLEANUP DELAYS                    "                  ».

         DEE's failure to procure  Remedial  Investigation/Feasibility  Studies
    (RI/FS) delayed site cleanups,  and  unnecessarily tied up over $6  Billion
    that EPA needed  for other  Superfund projects.   The  studies, which  can
    take over  two  years  to complete,  are prerequisites  to site  cleanups.
    EPA obligated $513,000  for  an  RI/FS at the first DER  site  in June  1984.
    Over the next two years  this funding was increased to more than $6  Billion
    for studies  of  eight DER  sites.  As  of  September  1986, more than  two
    years after  the  initial obligation, DER  had yet  to  formally execute™ a
    single 1I/FS  contract,   and the  funds  remained  unused.  This  failure,,
    resulted from procurement   inexperience  on the  part  of DER staff,  and
    from indecisiveness  on  the part  of  DER  top  management  in  dealing  with
    recalcitrant contractors. . We   recommend   that  EPA -aggressively  monitor
    DER procurement procedures and deobligate excess .funds.

2.  TRANSFE1 OF ENFORCEMENT SITES

         DEI enforcement efforts have been ineffective.   EPA "policy" requires
    state agencies to  enter into -formal Consent.  Order  and Agreements (COAs)
    with potentially  responsible  parties (PRPs)  to guarantee  that  remedial
    studies and  cleanups  are  performed in   accordance   with  the  National-
    Contingency Plan  (NCP).  At  the  time  of  our   audit, DER  had  enforce-
    ment responsibility  for eight  National  Priorities List  (MPL) siteSfT  We
    reviewed'six of  the sites  and found that  DER  had failed  to enter  into
    enforceable agreements with any of the  PRPs for  remedial  work.  Evidently,
    DER was  reluctant to press the  PRPs  to  sign  agreements  in the  belief
    that it was  more beneficial to  get  PRPs  to perform  remedial work  on an
    informal basis.  We  did note that COAs were  executed by DER for  removal
    efforts at  various  sites.   However, DER's attitude  regarding COAs  for
    remedial work  not only conflicted  with  EPA policy,  but  left DER  with
    little leverage  to  force recalcitrant  PRPs to actually perform the  work.
    The overall  result is  that final cleanups and  NPL  delistings  have  been
    delayed by years.   We  recommend that  EPA transfer  all PER enforcement
    NPL sites back t«> EPA control.                                ,    -
        j                                    '                      S
    Preliminary draft findings  were provided  to the  Hazardous Haste Mangement
Division (HHMD*)  by Hay  22,  1987.   The Region's' comments received on June 29,
1987 indicated disagreement with the first finding and concurrence with the
second finding.  Our evaluation of  the  Region's comments did  not alter the
content of the findings.  On July  13, 1987  a  draft  audit  report was issued to
the Regional Administrator.  We held  an exit conference with HWMD officials on
September 14t  1987.   During this conference we were informed that the Region
would not be  providing written comments to .the draft report.   We were also
informed that  the  Region basically  agreed  with most  of the facts contained
in the  report,  but  not   necessarily   with   the   report's   conclusions  and
recommendations* ^                       .         '                .

-------
ACTION REQUIRED

     In accordance vith EPA  Order 2750,  the  Administrator  of Region  III  is
required to provide this off ice, with a written response to the  audit  report
within 90 days of  the audit report.  If you have'any questions, please contact
toe or Carl Jannetti at  597-0497.

     The courtesies and cooperation  extended  by  your  staff  during this audit
are appreciated.
BACKGROUND

     The "Superfund" program  was  established  by the Comprehensive  Environ-
mental Response,  Compensation and Liability Act (CERCLA),  Public Law 96-510,
enacted on December 11,  1980.   The'Superfund program was  created to protect
public health and the  environment  from the  release,  or  threat  of release,  of
hazardous substances from abandoned  hazardous  waste sites  and other sources
where response was  not  required  by  other  Federal laws.   A Trust  Fund  was
established by CERCLA  to provide  funding for  responses  ranging from control
of emergency situations  to  provision  of permanent remedies at uncontrolled
sites.  CERCLA authorized  a $1.6  billion  program  financed by a  five  year
environmental tax on  Industry  and from  general revenues.  CERCLA requires
that response, or payment for  response,  be sought from those responsible for
the problem.                              .                            '

     Superfund1s taxing  authority  expired on September 30,  1985.  The avail-
able funds from  fiscal  year 1985  appropriations along  with estimated future
cost recoveries fell $657 million short  of  planned  fiscal year 1986 program
requirements.  This resulted  in a slowdown of activities  from August 1985.
EPA received interim funding  of $150 million on April  1,  1986 which allowed
resumption of some cleanup activities.

     CERCLA was revised and  expanded by the  Superfund Amendments and  Reauthor-
ization Act  (SARA),  Public Law 99-499,   enacted on October 17, 1986.  SARA
reinstituted the environmental  tax and expanded the taxing mechanisms avail-
able for. a  five  year  period.   It  authorized an $8.5 billion program for the
1987-1991 period.  The Trust Fund  was renamed  the  Hazardous Substance Super-
fund.                            '0.

     The basic regulatory ^blueprint for  the Superfund Program  is the National
Oil and  Hazardous. Substances Contingency Plan (NCP),  40  CFR  Part  300.  The
NCP was first published in 1968 as part of the Federal Water Pollution Control
Plan, and  has been  substantially, revised  to  meet CERCLA  requirements.    A
1982 revision  authorized  the   following types  of  responses   for  incidents
involving hazardous substances:

     o   Immediate Removal - a prompt  response  at any site  to
         prevent or mitigate Immediate and significant risk
         of harm  to human life,  health or the environment.
       '  Generally a removal is  to  be  completed within 6 months
         or after expenditure of $1 million.

-------
     o  Planned Removal - an expedited, but not necessarily  •,  "'
        immediate response, at any site (1) where ther.e will ,
        be substantial cost savings by continuing an immediate       *
        removal when only a small amount of work .is necessary •           ,  '
        to complete the cleanup, or (2) when the public and/or
~"       the environment vill be at risk from exposure to haz-
        ardous substances if response is delayed.  The 6
        •onth/Sl million limitation also applies, and States     ' ,
        are required to contribute 10 percent of the costs. •

     o  Remedial Action - a long term usually more expensive
        attempt to achieve a permanent and cost-effective
        solution.  These actions usually require a series, of
        extensive investigations and studies to determine
        remedial alternatives which will range from no further
        action to total site-cleanups.-  If EPA decides to take.
        further action, the method selected Is then designed
        and eventually implemented.  The NCP limits these
        long-term cleanup actions to sites included on the            '   - •
        National Priorities List (NFL).  This list design-
        ates the nation's worst sites known to be con-
        taminated with hazardous substances.  NPL sites
        are generally determined by EPA's Hazard Ranking
        System (HRS) under which individual scores are
        developed based on the release or potential for
        release, of hazardous substances into grouhdwater,
        surface water, and the air.  These scores are
        weighed and combined to calculate an overall site
        score ranging from zero to 100.  Sites scoring
        28.5 or higher are eligible for NPL listing.

     o  Initial Remedial Measure - a cost-effective expedited
        remedial response at an NPL site to limit exposure  to
        a significant health or environmental hazard.  Such
        actions can include  the removal of hazardous substances
        fouad in drums, barrels, tanks and other bulk storage
        containers above the surface, or the removal of highly
  •  '    contaminated soils largely at or near the surface.

     In November  1985,  a  second  revision  to  the  NCP-eliminated  planned
 removals  and  initial  remedial  measures  as distinct  response   categories.
 As  of  February  18,  1986  these  responses  were  included  under  an  expanded
 removal authority.   By  quicker  response  EPA  hoped to  help  reduce  health
 and environmental  risks, as  well as reduce long-term cleanup costs.

     At most  remedial sites,  the States  oust pay  10 percent  of  the  costs
 of  the  remedial cleanup.   CERCLA section  104(c)(3) provides  that  no  reme-
 dial actions  shall be  taken unless  the  State  in which  the  release  occurs
 enters  into  a  contract or cooperative agreement  with EPA  to provide certain
 assurances, including  cost-sharing.   Pre-remedial  activities  (preliminary
 assessments, site  inspections)  remedial  planning  (remedial  investigations,
 feasibility studies,   remedial  designs)  aad  removals   may  be  funded  100
 percent by EPA.   For facilities operated by a State or political subdivision
 at  the  time  of disposal  of hazardous substances,.the State must pay at least
 50 percent of all  response costs,' including  removals and  remedial planning
 previously conducted.                                         .

-------
                         FINDINGS  AND  RECOMMENDATIONS
J.   SITE CLEANUP DELAYS

     .DER's failure   to  procure  Remedial  Investigation/Feasibility   Studies
(RI/FS) delayed  site  cleanups,  and  unnecessarily tied  up over  $6  million
that EPA needed for other  Superfund projects.  The  studies,  which can  take
over two  years  to  complete,   are  prerequisites to  site   cleanups.    EPA
obligated $513,000  for  an  RI/FS at  the  first DER site  in June 1984.   Over
the next two years  this  funding was increased to more  than  $6 million  for
studies of eight DER sites.  As  of September 1986, more  than  two years after
the Initial obligation, DER had  yet  to  formally execute  a single RI/FS  con-
tract an.d. the funds remained unused.  This  failure resulted .from procurement
inexperience on the part of DER staff,  and from indecisiveness on the  part
of DER top management  in dealing with recalcitrant contractors.  ,

  •   ,It took DER staff  one year to  assemble Requests for Proposal/Qualifi-
cation (RFP/Q)   packages  for   five  sites.   These  packages   contained   the
specifications  to  enable  prospective  contractors  to  submit  proposals  to
perform the RI/FS  studies.  By January. 1986, DER management had selected the
contractors.  However, the contractors  selected  for four of  the five sites
refused to  abide  by  the  original  specifications  in the RFP/Qs.   Instead
of terminating  the.offers,  DER management  spent the next  nine months  negoti-
ating with these contractors.   During this  time, DER  continuously  told  both
the public and  Region  III that the studies would soon commence.

     The overall effect  of DER's failure to procure  the  studies is  that  site
cleanups have been  seriously  delayed.   In  our  review  of DER's attempt to
obtain the studies  we  also  learned that:

     (1)  Region III knew from the beginning that DER was ill-
          equipped  to  handle the procurements, yet the Region
          continuously accepted DER assurances that the con-
          tracts would be awarded "soon."
                                       '                     3
                                      -.,'••                  /
     (2)  DER evaluation of proposals and selection of contrac-
          tors were not performed in accordance with the Code
          of Federal Regulations (CFR).  As  a result, award of
          the contracts could generate protest by unsuccessful
          contractors, and would produce $1  million in questioned
          costs upon final audit.

     .(3)  Region III obligated over  $4.4 million  of the $6 million
          far in advance of DER's anticipated need.  For example,
          $3 Billion was obligated because  the Federal fiscal year
          was ending and the Region  evidently.wanted to reserve the
          money for DER's  future use.  We  also  found that DER has
          no real need for $1.3 million of  the  $4.4 million  .   .
          advanced because the Potentially Responsible Parties
          (PRPs) have agreed to perform  the RI/FS studies  for
          two of the sites.  DER is  merely holding this money
        • as an enforcement tool to  guarantee PRP performance*

-------
                                  Background

     DER was  bound  by  40 CFR,  part  33  to.  evaluate  and  certify that  Its
procurement system  net  Federal  regulations.   The  multi-site  cooperative
agreement (KSCA) of February  9, -1984 enabled EPA to fund DER procurement  of
RI/FS studies.  On  June 29,  1984  Region  III  obligated $513,000  for  studies
at the Haver town  site.   DER,  lacking a Superfund  staff of Its own,  hired a
project management  consultant" in July 1984.  The consultant  was  to assemble
RFP/Qs to solicit proposals,  and to prepare  RI/FS  Workplans  for  the use  of
contractors selected  to  perform the  actual RI/FS  studies.   Region  III  in-
structed DER to accelerate  these workplans at  an  additional  cost  of $4,250
so that RI/FS funds  could be  obligated by  the  end of fiscal  year 1984.   On
September 27, 1984, Region  III obligated an° additional $3,078,000 for  RI/FS
studies at the  Voortman, East Mt.  Zion,  Dorney Jtoad,  Brodhead Creek,  Berks
Sand Pit, and  Welsh Road Sites.   The consultant prepared  an RFP/Q  for  the
Welsh Road Site, but it did not meet with the approval of  DER.  After failing
in a  second  attempt,  the  .consultant  was  removed  from this  task in  March
1985, and* DER  prepared  its -own  specifications.   In  June  1985,   Region  III
funded $845,592 for an -RI/FS  at Whitmoyer, the eighth DER site.  .By  the  end
of the year  DER had  evaluated contractor  RI/FS proposals for  five of  the
sites, and decided  on contractor  selections.   On  April 9, 1986,  Region  III
authorized DER  to "advance  match" an additional $1.6  million of  State  funds
to cover the  difference between  the original  estimates  and  the  contractor
prices for  the  five  sites.   This  money  would be reimbursed  by EPA  when
Superfund was reauthorized.

                             Contract or' Se 1 e ct ion  :

     DER was- bound  by  the  requirements of  40 CFR,  part 33 in its selection
of RI/FS contractors.  This  reference provides two  methods   of  competitive
negotiation.  Both methods  required PER to  inform  prospective contractors of
the criteria by which proposals would be evaluated, and  the  relative impor-
tance attached  to each.   Basically  the first method  allowed DER to  solicit
contractor qualifications, proposals, and proposed prices in a single package
while the second  outlined a  series of steps to follow before negotiating a
price.  The first method required DER to:    ,

     o  Conduct meaningful negotiations with the best qualified
        contractors, who had acceptable proposals within the
        competitive price .range.'   .    '   .

     o  Permit revision, of proposals to obtain best and final
        offers.

The second method required DER to:

     o  First determine the 'most qualified contractors.

     o  Then solicit proposals from those contractors.

     o  Then determine the best technical proposal.
     o
Then  negotiate  a  fair  and  reasonable  price  with,  the  contractor
who had the best'technical proposal*

-------
     o  If necessary  terminate  negotiations if a  price  could not  be  agreed
        on, and open negotiations with  the contractor vho had the  next  best
        proposal.

     The evaluation  criteria  contained  in the RFP/Q packages closely  par-
alleled the first »etho;d described in  the CFR.  The RFP/Qs generally explained
that, although price  would  play a  significant  role  in  proposal  evaluation,
selection would not necessarily be  based solely  on  a low cost basis'.   Only
those contractors determined Co be qualified and having an adequate technical
approach, and whose proposals were found  to  be qualified  and within a competi-
tive price range, would be selected for complete evaluation.   These proposals
would be evaluated in accordance with the following criteria:

     o  Technical merit of overall approach, including schedule
        and phasing.

     o  Safety and security practices to ensure the health and.
        safety of employees and the general public.

     o  Response of offerer's references regarding quality of
        work, performed on prior projects.

     o  Overall cost.

DER then planned to  conduct  interviews or  contract  negotiations  with  any or
all contractors in  the  competitive  range,  and  make  an award  based  on price
and the other factors considered.

     DER did not adhere to the  CFR,  or to  its own RFP/Qs, when  it evaluated
the proposals.   Instead  DER used a  method  that combined  aspects of  both
the methods described  in CFR.   Evaluation  summaries for the five proposed
awards were on  file in Region  III.   These  summaries  indicated  that DER had
ranked contractor  proposals  as  either  "superior,  acceptable^,  marginally
acceptable, or unacceptable," but did not show which proposal was recommended
for award.   However,  comparison  of  the amounts  obligated   by  EPA,  to  the
amounts in the  summaries,  indicated that DER only considered the "superior"
proposals for  award,  even  though there  were  far less  costly  "acceptable"
proposals for  four of  the  five  sites.  At  DER  we  verified that  only  the
proposals Judged as "superior"  were considered  for  award.  A DER official
defended this procedure  by  asserting,  "Why buy a Chevy when you  can buy a
Cadillac." Be advised DER  that  the  difference in  price  between  the "Chevys"
and "Cadillacs"  would be  questioned  upon  final  audit  of  .the  cooperative
agreement.  It  was  important  that  DER follow  the  competitive  negotiation
methods prescribed  by CFR,  because  the  aggregate  total '. of the variances
between the "acceptable" and the "superior" proposals was-$1,049,737.

     During our  audit we  informed  Region0III  of  DER's selection method.
Regional personnel were of  the opinion that DER would  have additional informa-
tion, beyond  the evaluation  summaries,  that  would  show, that  the proposed
procurements complied with the CFR. .

-------
                                        Proposal Evaluations

                Ironically, the contractors vhose proposals are  listed  as "superior" in
           the above chart, were  the contractors to which DER was  experiencing  so much
           difficulty awarding  contracts.   We  concentrated  our  proposal  evaluation
           review on these four sites.  We were  able  to find only one complete evaluation
           package, and two  partially complete  packages.   The fourth  package had been
           thrown out.  From  this  information,  and from interviews  with DER personnel,
           we were able to piece  together  how  the proposals  had been evaluated.  Evident-
           ly, various segments  of  the  proposals were  individually  scored by evaluation
           team members.  The combination of  the Individual  scores  dictated whether the
           proposal was considered  "superior,  acceptable,  etc."   Ve   believe that the
           evaluation teams  were conscientious  in  performing their  reviews.   However,
           as explained below,  we also believe that their  efforts  were compromised by
           their inexperience, and  more importantly, by the restraints placed upon them
           by DER management.

                (1)  The evaluation  team members were engineers, hydro-
                     geologists, and chemists by profession.  As far as we
                     could determine, none of the people who assembled  the
                     RFP/Qs, and reviewed the contractor proposals, had any
                     experience in contracting.  For example, even though
                     DER had requested  lump sum  prices, the teams evaluated
                  .  .proposed profit margins, labor  rates, and overhead
                     within the various phases of the RI/FS.   It was erro-
                     neously believed that if the contractor performed  a
                     phase of the study for less than the original estimate
                     DER would keep  the difference.

                (2)  Ho one from DER was allowed to  contact the contractors
                     to get clarifications on the proposals.   Several
                     team members told us that  clarifications would have
                     placed "acceptable*1 proposals,  into the "superior"
                     category.  *

              .* (3)  the evaluation  methods'were very subjective*  For
                     example, one team  ranked contractor qualifications
                     based on contractpr  employee resumes.  Another  team,
                     realizing there was no 'guarantee the employees proposed
                     would actually  perform the  work, looked at the  company's
                     overall experience.  Consequently, a contractor con-
                     sidered only marginally  qualified by one  team,  was
                     actually selected  by another team.

                (4)  The  evaluations were also  arbitrary.   For example,
                     a proposal  for  one site  was Judged "superior,"  and
                     selected for award despite the  fact that  the pro-
                     posal contained the  wrong  .site  name.   By  contrast,
                     a proposal  for  a second  site was judged non-responsive
                     because  although notarized, it  lacked  signatures.
                     Interestingly  enough, at the  same  time a  different
                     team selected  this contractor  for a third site.   In
                     any  event,  ye  believe the  decision to  declare  the
                     proposal non-responsive  because of missing  signatures
_

-------
          was harsh.  Especially in light of the fact that DER
          had initially misplaced this contractor's proposal,
          and did not review It until seven weeks after the
         ""^competitors' proposals.  Moreover, this review dis-
          closed that the proposal was acceptable from a tech-
          nical standpoint, and was in fact $158,000 cheaper
          than the proposal finally* selected.  Ironically, had
          DER obtained the signatures it may have expedited
          •at.ters, because one year later DER had yet to sign
          an agreement with the contractor that had been selected.

                           DER Confused the Public

     In a September  4,  1986  letter,  concurrently released  to  the press,  the
then Secretary of DER advised the Region III Administrator  of Pennsylvania's
aggressiveness in cleaning up hazardous  waste  sites.  The Secretary asserted
that Pennsylvania had, more  money spent at  more  sites than any  other  state.
The Secretary stated that "Congressional inaction for over a year has stalled
reauthoriration of  Superfund,  with funding  still  a far-from-settled issue."
To ameliorate  the  situation the  Secretary of fered to quickly  provide,  i.e.
lend, state  funds  to  allow  for  site  studies"...that  might  falter  during
Congressional debate on Superfund."

     We found  no  response to the Secretary  in  our  review of the file.  How-
ever, in view  of DER's protracted negotiations with the *RI/FS contractors,
the Regional Administrator could  have  responded  that DER  had  control of  over
$6 million of  EPA  funds  for over two years  and  had yet  to award a contract.
In fact, DER officials were  overly optimistic in their comments to the press
about when the RI/FS studies .would begin.   One such example is the Ha vet town
PCP site.                          •

     In 1953  a township  health  inspector  found pentachlorophenol  (PCP) .in
underground pools at  the  site.   Litigation by the  township against the  PRPs
progressed through,  the  Commonwealth  Court, the Pennsylvania  Supreme  Court,
and, finally  in October  1980,° the  U.S.  Supreme   Court.   At  that  time  the
township Manager concluded  "We  really won all along*  I believe it's the end
of the road."  In  the meantime,  EPA had taken  initial cleanup steps; filters
were installed  to  prevent contaminants from leaving  the  site  and entering, a
nearby stream.  The  site  was placed  on the NPL  in  1982.   DER inspections in
1984 and 1985  disclosed  that;, the PRPs were not  maintaining the filters,  and
contaminants were  entering  the  stream.   On January  9,  1986 DER selected  a
contractor to perform an  RI/FS  study  to  determine  final  cleanup options.  At
the time of our review,, nine months later,  no  contract had. been signed,  and
subsequent inquiries over a three month period  indicated no change in contract
status.                                *  .       •      '
                                         *        *
     Since early  1984,  DER  repeatedly  told both the press and the township
residents that the RI/FS  studies would soon occur.  DER placed the blame for
the delays on  the United States Congress.  A September" 15,  1986* newspaper
article reported that the then  Secretary  of DER announced he was launching a
$782,000 RI/FS study to get the  .cleanup project out  of "limbo."  The Secretary
explained that  delays in  congressional funding had  led to a "general hiatus
in action", but the  state had  budgeted $8 million,  and "I'm going  around the

-------
state to start  spending it."  When asked why the study was needed,  the  Secre-
tary replied,  "In  order to  get  the  Federal  money  you have  to go through
their process."   It  was estimated that  the  study  would  begin in October
1986.

     DER has not liv.ed up  to its promises  to the public  since  1984  about
when the studies would start.  Likewise, DEE sought to transfer the blame for
the delays  to  the  Federal  government.   The  Secretary's  inference that  the
U.S. Congress  was somehow  responsible for  the delay in  cleanup of  the  Haver-
town site it without  merit.   As explained  in the background paragraph  above,
Region III had  obligated RI/FS  money  for the site as far  back as  June 1984.
Therefore DER  had the  money all along to,award  a  contract.   We believe that
Region III  should have  been  more  aggressive  in  monitoring  what DER  was  or
was not doing,   but  the  responsibility for the delay  rests with DER.   Ue now
understand that  an  RI/FS study  of.  the site was scheduled to begin on June 1,
1987.  It is entirely possible  that the  studies  could have been already well
on their way,  or even completed, had DER  not engaged in protracted contract
negotiations.

                            Contract Negotiations

     DER had difficulty awarding contracts.   The  contractors selected  in
January. 1986 for four of the five sites balked at the terms  of the proposed
contracts, even  though  these  terms  were  contained as  specifications  -in
the. RFP/Qs.  Nine  months later DER was still negotiating with the contrac-
tors.  During  this period, DER  repeatedly  told Region III that the contracts
would be awarded "soon."   In  September  1986 we were told the awards would be
executed "any  day now."  Subsequent contacts  with DER through December 1986
Indicated that  the contracts had  yet   to  be  formally  executed.  We  later
learned that,  after almost a  year .of discussions,  DER had terminated negotia-
tions with  one  contractdr  for attempting to  increase the proposal  price.  In
our opinion, DER should have terminated  negotiations with  any contractor,
who  refused to perform  in accordance with  the specifications.
                      *•   '
     DER experienced  various problems in  negotiating  contracts for the four
sites.  The Issues  Involved matters such as  site  security, insurance,  indem-
nification, method  of  payment,  penalties,   and  completion  dates.   We  use
the  Havertovn -site  as an example, because  it was the only instance where we
found that  DER  had issued an  ultimatum to  the  contractor,   and  because we
believe the contractor's  proposal should  have  been  originally rejected as
non-responsive  to the RFP/Q.

     By September  1985, DER  had received  12 proposals  to perform the  RI/FS
'of  the  Ravertown site.  On January 9, 1986,  DER selected  a $781,980 proposal,
that it  considered as  "superior."  By  comparison,  a $502,998  proposal  sub-
mitted  by  a contractor with  previous  site  experience  was rejected  because
DEE considered  it   only "acceptable."   DER  negotiations .with the selected
contractor  stalled  over  several  issues.    Finally,  on  April  4,  1986,  D£R.
provided  the  contractor  with  the Department's  "best  and final   offer"  and
as  such,  not  subject  to  negotiations.   The  contractor rejected DER's  offer
as  unacceptable.   The  contractor  maintained that his proposal  never  offered
or  agreed   tip   guarantee the  completion date  of the  project  or to pay a
penalty if  the  work  was  late.  The contractor  also  had problems  relating
to  site security,  hours  of  operation,  insurance,  and  method of  payment.
                                       10

-------
 We reviewed the  proposal  and  found that  the  contractor  was  correct.   The
 proposal  never  agreed to guarantee the project's completion date  as  required
 in the RFP/Q.   Moreover,   the  contractor's  proposal  price did not  include
 security, which was also an  RFP/Q  requirement.   Security in  fact  would  cost
 an additional $2,,075 per week.

      As  seen elsewhere,  a  proposal  could  be rejected because it simply lacked
 signatures. Based  on the  above,  we believe that instead of  considering  this
 proposal  "superior" it  should. have  been  rejected, as  it  was clearly  non-
 responsive to  the  RFP/Q.    In  any  event,  once  the  contractor refused  the
 Department's "best  and final offer,"  DER should  have  terminated negotiations.

      The  Ravertown'situation was by no means unique. DER had similar  problems
 in negotiating  the  other three  contracts as well.  Yet the  only negotiations
 terminated case  as  a result  of  a  contractor raising  the price.   We  believe
 that  instead of  spending almost a year  in protracted negotiations, DER should
 have  terminated  discussion once  it became  clear that  the  contractors would
 not follow the  RFP/Q specifications.  :

                               "Dormant"  Funds

      Because of  the  delay  in  the  reauthorlzatlon of Superfund, EPA was forced
 to seek Bother  sources of funding.  As  a  result,  in February  1986 Region III
 was requested to  review  the cooperative agreement and deobligate  monies  that
 would not be  spent  before June 30,, 1986.   The Region considered deobligating
 $513,000  from the Brodhead Creek site, and $845,592  from  the  Hhitmoyer  Lab
 site,  because it was  thought that  the work  would  be performed by the  site
 owners.   However, the Region waited until  July to  request  DER's  approval to
 deobligate, and  only asked for the return  of -the  Brodhead Creek  funds.   DER
 ignored the request.  We found that, although the Department did not  actually
 plan  to use the  $1.3 million, DER wanted to keep the funds  as an  enforcement
 threat against  the  sife  owners.  Consequently, money  that  vas  sorely  needed
 for other Superfund projects  has  been needlessly tied up by DER for  over  two
 years.

                            EPA Monitoring  of DER

     Region III knew from  the start that DER vas  Ill-equipped  to  handle  the
 sites.  In DER's application  for  the cooperative agreement,  it was made clear
 that the  Department  planned to  hire a  project management consultant  to pre-
 pare  the  RFP/Qs  and the  RI/FS   Workplans.   Likewise,  EPA  Headquarters   was
 not alarmed that DER had little in  the  way  of a  Superfund staff, and  in  fact
 processed DER's  application for  the  agreement  in  just  three days.  EPA  may
 have first  become concerned in March  1985  when  it was  learned that DER  was
 preparing tbe RFP/Qs instead  of the consultant.

      In May 1985, EPA Headquarters  and Region III  personnel made  a  "Manage-
 ment Assistance Visit" to  DER.   The ensuing report on  the visit  warned  that
DER's procurement procedures  were  not  in accordance  with  the CFR, and that
DER's evaluation  process  could   result  in. unnecessary  delays  in  awarding
contracts.  Another  repo.rt,  issued by • the  'Office of  the Inspector  General,
Audit Report Number P5bH5-l1-0056-70538,  covering  the  cooperative agreement
up to  June  30,  1985 likewise reported  that DER's procurement  system did  not
meet Federal  requirements.   Specifically,   40  CFR  33.110  required  DER to
                                      11

-------
 evaluate its own procurement system, and to determine whether its  system  net
 the applicable  requirements of  40 CFR, part  33.   This  previous report said
 that the procurement  system certified  by DER  appeared  more  applicable  to
 snail purchases  such  as typewriters,  rather than for  the  avard  of  large
 contracts.   This report also criticized  EPA  because Regional employees were
 actually on the DER  panel  that selected the  project  management consultant.

      By late 1985,  Regional personnel  were  concerned   over DER's  lack   of
 progress.  Status  reports prepared  by  the Regional project  officer  pointed
 out that:

      o  Mot one  Rl/FS  had started.

      o  $3  million in  unspent RI/FS  dollars were tied up.

      o  Sites were now even  two  years further  from  cleanup.

      o  The DER  procurement  process  was a stumbling block.

      o  DER management  was unable  to quickly decide.on RI/FS
         contractors.

      o  DER had  not responded to the report on.the  Hay
         "Management Assistance Visit."

      Suspecting  that DER might  not have enough personnel  to  handle the pro-
jects,  the  Region conducted  a workload analysis of  the DER Superfund program.
A draft  report of this  analysis, dated January 27,  .1986, highlighted the fact
that  DER fared   unfavorably  when  compared  to national  averages  for other
state programs and EPA.-  The report pointed out that  it took EPA an  average
of  188  days, and other states  an average of  233 days  to Initiate a remedial
investigation.  By contrast, after 730 days DER had yet to  award a contract
to  initiate a remedial  investigation.

      From the  time of  the  January workload  analysis  until our  September
visit, DER informed the Region that it was negotiating with the selected con-
tractors.  On October  28,  1986  DER notified the Region  that  it  had executed
five  contracts.  During December we  were  told  by DER that  the contracts were
executed, but not  in  writing. .  On January  30, 1987 DER informed the Region
that  four of the  contracts  were  executed,  but that  negotiations  with  one
contractor had been terminated.


Conclusion                                          •               .

     DER held EPA money for over two and a half years without actually start-
ing a  single  RI/FS study.   DER  ignored  the  Region's request  to return part
of  the  money,  even though  it  was  obvious  that DER would  not  need  it  and
despite the   fact that  EPA  was  hard-pressed. for  funds.   The  procurements
attempted by DER were  not  in  accordance with the  CFR.    Site  cleanups have
been delayed because of prolonged  negotiations that should have been termi-
nated.  Although responsible for the delays, DER publicly  inferred that the
Federal government  was  somehow  at  fault.   This  Inference  is only valid  to
the extent  that  EPA allowed what  happened,  to happen.   Any furt'her delay
                                      12

-------
will in .CM  In.c.nces e«cend  Che  ti.e  th.t  Che  public could  be exposed to
                                      th>t
Recommendation                                         .


   .  We recommend that the Regional Administrator:


          1.  Aggressively monitor DER procurement  procedures
              and notify DER that deviation from the CFR
              will jeopardize its procurement certification.

          2.  Deobligate any EPA funds that are excess to
              DER' s needs..
                                      13

-------
2.   TRANSFE1 OF ENFORCEMENT SITES

     DEE enforcement efforts  have been  ineffective.   EPA "policy"  requires
state agencies to enter into a formal  legal Consent Order and Agreement (00A)
vith PRPs to  guarantee  that remedial  studies  and cleanups,  are' performed  in
accordance with the  National Contingency .Plan.   At the  time of our  audit,
DER had enforcement-««ponBibility for  eight  NPL sites.  We  reviewed  six  of
the sites and  found that, although in  the  past  several  removal  actions  had
been performed under signed"agreements,  DER had  failed  to execute COAs  with
any of the PRPs  for remedial tasks.  Evidently,  DER  was reluctant  to press
the PRPs to sign agreements in the belief that it  was more  beneficial  to  gee
PRPs to perform  remedial  work  on an  informal  basis.   This philosophy  not
only conflicted with EPA  policy,  but  left DER with little  leverage  to force
recalcitrant FRPs to actually perform the work.  As a result, final  cleanups
and NPL delistings  have  been delayed  by years.  We therefore recommend that
Region III transfer the DER enforcement sites back to EPA control.

     PRPs will  sometimes  accept  responsibility to  conduct  specific  remedial
tasks for  KPL sites.   These tasks  can  include actions  such  as  removals,
RI/FS studies, and  final  cleanups.  EPA requires PRPs to sign  a formal COA,
which then becomes  an  enforcement tool  to ensure that  the  agreed upon  work'
is performed  in accordance with  the National Contingency Plan.. It is there-
fore important that the COA  be in place  before the work is done.  In similar
fashion, although  Superfund  does not  provide  authority  to delegate  EPA's
enforcement responsibility,  the   Agency  does  expect  States  who assume  the
enforcement lead to  also negotiate COAs with the PRPs.  The agreements are
important because  all  Federal  enforcement action is postponed  pending  the
results obtained under  state COAs.  Therefore,  if state enforcement efforts
fail, or are delayed, permanent site cleanups are Jeopardized.
      i,
     By 1986  DER  had accumulated 16  enforcement  NPL sites, none  of which
were covered  by a  COA.   Region  III  attributed this lack  of  success  to a
shortage of  DER  lawyers  and,  recognizing  that  site   cleanups wejre  being
delayed, recommended that DER consider  transferring  some. of the  sites back
to EPA.  Specific issues  used'to  support this recommendation  were:

     o  The absence of remedial action at one site over.a
        five  year period.

     o  DER procurement delays that more than doubled estimated
        project costs at  another  site.

     o  Protracted  negotiations with PRFs over remedial  work in
        process at several  sites  not covered by  any agreement.

     o  PRP legal challenges  to DER authority  to enforce Superfund.

As a  result  of the Region's  recommendation, DER agreed to  transfer 8 of  the
16 sites.                 ,
                                             w                        *
     We  reviewed" the files available  for  five of the transferred sites,  and
for six of the  sites still under  DER control.  .Our overall  Impression  is  that
DER's  problem was  not necessarily a  shortage  of  lawyers, but  rather  the
philosophy that  it  was  more  beneficial to  deal with  PRPs on an informal


                                       14

-------
basis, than to press them to  commit to specific  tasks  under  binding agree-
ments.  This philosophy  may have  evolved from  past  experience.  -In  1983,.
after conducting  a  removal  action, the PRF  for  one site  announced chat it
would negotiate an  agreement  with DER to perform  an  RI/FS  and  conduct a
cleanup.  The PRP  threatened legal  action against EPA i'f the Agency  tried to
interfere.  Notes  of a telephone conversation  between  the  PRP  and DER  indi-
cate that the State was prepared to sign  the agreement even if EPA  objected.
The COA, signed in September of 1983,  was praised both  by DER and  Region  III
officials as a model for voluntary cleanups of  Superfund sites nationally.
However in 1984,  when the RI phase  was  complete,  both DER and EPA  recognized
that soil  sampling  had' not been  part  of  the  COA.   The  PRP  later  obtained
soil samples, but DER rejected the  sample results  as.unreliable,  and requested
new samples.  The  PRP  refused and in  1985  filed legal challenges  with  the
State Environmental Hearing Board  against DER's  authority to  act  on  behalf
of EPA.   Subsequently,  an  EPA contractor  took  new  soil  samples,  and in
1986 Region III decided to transfer the  site from DER's control.   The decision
was later  reversed  because  DER "was  close  to an agreement  with  the  PRP."

     We offer the following comments  to support  our contention that  all  the
sites should be transferred back to. EPA control,  but have omitted  site names
since the enforcement issues have  yet  to be resolved.
                                                  ,               *         *'
                                   Site "A"
     DER consciously operated contrary to  EPA  enforcement  policy.   DER first
became involved with  site  "A" in  1981.   Sampling results  in  1982 indicated
contamination of residents'  wells.  The PRPs  conducted  a   removal  action in
1983 and began  supplying the  residents  with  interim water supplies.   Over
the next two years  DER and the  PRPs  discussed what  additional  remedial
measures should be taken, but never entered  into  a COA:   Region III tried to
expedite matters In 1985 by drafting a COA,  but DER  complained that it- was a
State lead  site and  that the Region's  COA gave  little, if any, enforcement
power to DER.   The  Region acquiesced*   DER  1986  status  reports  that  are
available to  the  public described  the  PRPs as  cooperative,  and explained
that negotiations  were  in  process.   The extent  of  the  PRPs  cooperation is
debatable.  After four  years the  residents'  wells  remain  contaminated,  and
without a COA  in  place  DER has  nothing  to enforce*   We found that although
the PRPs agreed to  voluntarily  provide  the  interim water  supplies, they did
not want to  be  legally  obligated to do  so under  a COA.  DER's reluctance to
press for a COA is evidenced in a. September  1984 memorandum from DER's Office
of Chief Counsel which advised:
                                                              A
          "As I have previously mentioned, as long as the compa-
     nies make some progress toward  pollution abatement, there
     is some advantage to getting  that work done without a  formal
     document,  for one thing we are not limited  in what we can
     request; for another, the companies have received no releases
     whatsoever from the Department, which is thus free to  insti-
     tute suit on any appropriate  cause  of action*  Although         ,   .
     there are advantages to having  firm commitments, they  nay     .£    ...
     possibly be out-weighed regarding this  site  by the fact
     that the threat of CERCLA action hovers over all, and  what    '     .
     we have received so far is, in  technical  legal parlance,  a
     'freebie.'  I strongly recommend you  reconsider  Inclusion
     of the  reference at this time to a  formal document."

                                       15

-------
  ..  The memorandum was narked  confidential  and the attorney  warned  against
its release "to  anyone outside  the Department, in  particular, EPA."   Five
months previous,  the  sane attorney  assured  Region  III of  DER's  wishes  to
work cooperatively  with EPA.

                                   Site "B"
     In addition to DER's reluctamce  to execute COAs, policy conflicts between
different DER sections,  and  between  EPA  and DER hindered  Superfund  enforce-
ment.  DER inspected  site "B" in  1981  in  response  to  complaints of  nearby
residents, and determined that their  wells were contaminated.  The DER inspec-
tor found numerous documented incidences of hazardous wastes  disposed  at the
site over a  15  year period*  However, a DER  lawyer advised  deletion  of the
inspector's conclusions in the report sent  to  EPA.   The  lawyer explained that
the State  Bureau  of  Water  Quality  planned  to  charge  the  PRP under  the
Pennsylvania Clean Streams Act.  Under a  DER  consent order,  the  PRP commis-
sioned a  hydrogeological  assessment   In  1983-1984.   The  PRP then agreed  to
enter into a COA with DER for additional  remedial work.   No  COA  was signed,
and DER requested the additional work on  a informal basis.   In 1985, a local
citizens group became concerned that  the  additional  work would cause exhorbi-
tant hookup fees and  water rates.   DER Informed the group that this problem
would be addressed in a COA.  In 1986, Region  III assumed enforcement respon-
sibility for  the  site,  because  of  DER's lack  of progress.   In  a September
meeting, the- PRP agreed  to sign a COA  with EPA to  Implement RI/FS studies.
An internal DER memorandum  concerning this  meeting  described  the State's
enforcement problems*  The delay In enforcement evidently  resulted  from a
dispute between the DER Bureau of Water Quality and the DER Superfund program.
The Bureau  of Water  Quality, unwilling  to implement  Superfund  enforcement
when the  site was  under  DER, now planned  to implement water  quality enforce-
ment even though the  site was transferred back to  EPA.   Consequently, while
Region III was  negotiating  the  COA  for  RI/FS  studies,  the  Bureau  of Water
Quality planned  to  issue  an order  requiring the  PRP  to  conduct  immediate
groundwater pumping  and  treatment   action.   The  author  of  the memorandum
blamed this  confusion on a  lack  of DEE policy to define  the  enforcement
roles played  by different State Bureaus;  as  well  as  the  lack of a written
policy concerning the roles  played by EPA and DER.

                                   Site "C"

     The absence of -enforceable  agreements- delayed  final  cleanup and allowed
PRPs to procrastinatei  A PRP conducted a  removal action at  site  "C" under a
1982 COA with DER*  However in 1984,  Region III became concerned,  because  the.
COA did  not.  require  the  PRP  to conduct  an  RI/FS.   In  response  to  a 1985
letter of inquiry,  Region III Informed a  United States  Senator that the work
done to  date had  not significantly reduced  contamination,   and that  RI/FS
studies were  necessary*   The Region  assured the Senator  that if the PRP  did
not perform these  studies,  EPA  would.   In November  1985, the PRP  agreed to
amend the  earlier  COA to include  the studies.  However,  it took DER  almost
one year  to draft an  amendment,  which the  PRP  refused  to sign because  it  was
felt that "such a level of formality was unnecessary."
                                       16

-------
                                   Site "D"

     DEE even delayed  executing  COAs  with cooperative  PRPs.   Site "D" vas
inspected in 1981 and placed on the NPL in 1982.  DER informed the  PRP in  1983
that a COA  "may  be required  at  some  future date."   The PRP commissioned
a. site environmental  assessment,  and  in  1984 DER  began drafting a COA for
RI/FS studies.   A  1985  Region III  toxicological  assessment concluded  that
there vas substantial  danger  to  anyone  coming in contact  with the  site.
In November  1985 the  PRP agreed to  sign a COA.   By February 1986, DER was
still drafting  the  agreement.   In March the  PRP  hired an  RI/FS contractor
and requested DER to  submit  the  COA so that  on-site work  could  commence  in
June.  The PRP  offered  to  start  the  work before signing an agreement  if DER
would approve the task in writing.   DER declined and informed the PRP  that a
COA was needed  before  the RI/FS  could be started.   As  of September 1986,  no
agreement had been signed.

Conclusion

     Contrary to EPA policy, DER has refused  or failed to negotiate enforce-
able agreements  with  the PRPs.  DER's  informal enforcement  policy  and lack
of aggressiveness have allowed the PRPs to dictate  how,  when,  or  even  if the
sites will  be cleaned up.   In effect the PRPs are  running the  program, and
as a result  final cleanups have been  delayed for years.   Therefore, we believe
that EPA must take  back control of the DER enforcement sites*

Recommendation

     We recommend that  the  Regional  Administrator  transfer all  DER enforce-
ment NPL sites back to EPA control.
                                       17

-------
                             REPORT DISTRIBUTION
                                                                  Appendix A
Recipient
                *^v#i;-j'-- ~ • •  ••'<••"
Office of the Inspector General
                f.C      "     »
  Inspector General (A-109)
Copies
Regional Office

  Administrator of Region III

  Director, Hazardous Waste Management Division

  Audit Follow-up Coordinator


Headquarters Office

  Director, Financial Management Division (PM-226)

  Comptroller (PM-225)

  Agency Follow-up Official (PM-208)
    Attention:  Resource Systems Staff  		

  Associate Administrator for Regional Operations (A-101)
   2

   1

   1
                                       18

-------