United States
             Environmental Protection Air and Radiation  EPA/400/1-91/005.D
             Agency        (ANR-445)     April 1991
  c.a         	'•	
(V-
   en
   CD
   EPA    Acid Rain Advisory
             Committee Meeting:
             December 13-14,1990
 ,            Permits and Technology
             Issue Papers
                 HEADQUARTERS LIBRARY
                 ENVIRONMENTAL PROTECTION AGENCY
                 WASHINGTON, D.C. 20460

-------

-------
           Permits  and  Technology  Issue Paper
                         Index

P-l                 Background Paper on Permits
                     and Compliance Plans
p-2                 Key Issues for Acid Rain Permits, Permit
                     Applications and Compliance Plans
P-3                 Permit Term Issue Paper

-------

-------
                                                                 PI
         BACKGROUND PAPER ON  PERMITS AND  COMPLIANCE PLANS

     The Acid  Rain requirements will  be implemented  through an
operating permits program under Section 408 of the Acid Rain Title
and  the  general  permits  provisions,  Title  V,  of  the  Act.
Regulations implementing the permitting requirements will include
provisions  regarding  schedules  for  submission  and approval or
disapproval of permit applications and compliance plans, contents
of permits and compliance plans,  and permit issuance and amendment
procedures.

     Permits and compliance plans should complement the allowance
system and  foster  trading by providing sufficient flexibility to
allow sources to make real time allowance trading decisions.  Our
challenge in this  critical program element is to develop permit
and compliance  plan requirements which  maximize  flexibility for
the  market,  certainty   and  predictability   for  sources,  and
accountability.

Why are Operating Permits Necessary or Desirable?

     An affected source  under the Clean Air Act,  as  amended, is
typically subject  to  numerous requirements.   These  include Acid
Rain program  requirements such as sulfur  dioxide and nitrogen
oxides   limits;   compliance   deadlines;  emissions   monitoring,
recordkeeping   and  reporting  requirements;   and   regulations
concerning  allowance  tracking  and  trading.    In  addition,  each
source is potentially subject to State implementation plan (SIP)
emissions  limits,  New Source Performance Standards  (NSPS),  air
toxics   requirements,   and   new  source  review/prevention   of
significant   deterioration   (NSR/PSD)    requirements.      These
requirements apply  to a  greater or lesser degree to a particular
source depending on the  type of facility involved.   An affected
source might,  for example, be subject to the year 2000 compliance
deadline or it  might  be granted a repowering  extension to 2003.
Similarly the applicable NOx limit will vary depending on the type
of boiler involved.

     The intent of  Section 408 of the  Acid Rain  title and by the
general permits title, Title V of the Clean Air Act Amendments of
1990, is, thus, to establish a mechanism for clearly articulating
the specific  requirements applicable  to an individual source in
one document.   Operating permits will  provide greater certainty,
thereby facilitating compliance by individual sources and oversight
by air pollution control agencies.

Whv is Flexibility Desirable?

     Flexibility is desirable  in order to —

     (1)  Promote  efficiency:  Rigid  and inflexible requirements
     for compliance would hamper the ability of  sources to make
     decisions based on  economic considerations.   Flexibility in
     allowing  sources  to  determine  (and  modify)  methods  of

-------
     compliance  will  promote  economic  efficiency  and  reduce
     compliance costs.

     (2)    Foster  active  allowance  trading:    Flexibility  in
     selecting methods of  complying with  the requirements of the
     Acid Rain  program will  foster  an active  allowance trading
     market.  Since the Acid Rain program  is the first substantial
     market-based environmental program, it is important that the
     trading  system not  stifled through  inflexible command-and-
     control requirements.

     (3)  Allow compliance program modifications:  Flexibility is
     essential  to  allow  sources  to   modify  their  methods  of
     compliance as  necessary  to minimize  the cost of compliance.
     Provided each affected unit complies with its obligations by
     applicable  deadlines, sources  should  not  be burdened  by
     excessive impediments to obtain permit and  compliance plan
     modifications.

How Can Flexibility Be Promoted While Ensuring Accountability?

     While the benefits of building flexibility into the Acid Rain
permit program are  clear,  the Agency must ensure that units are
held accountable for  compliance with the  emissions reduction and
other  program  requirements.    The  Agency  must balance  these
objectives through the implementing regulations.

     The Agency contemplates promoting flexibility by creating an
administratively  adjustable  compliance  planning process.    As
currently  contemplated,   plans could   be adjusted  periodically
without the need of a formal  permit  revision or lengthy approval
process.  The incorporation of explicit emissions monitoring and
reporting requirements will complete the measures  needed to enable
the Agency to take  this  passive role in compliance planning.  Up
to  date,  accurate  emissions  data will  couple  with the  Act's
stringent excess emissions offset  and  fee requirements to enable
the Agency  to close  the loop and ensure that  the goals  of the
program are achieved.

     To accomplish  this, EPA  is exploring  procedural mechanisms
for building flexibility  into  the program.  For example, different
types of information requirements,  and amendment procedures can be
established  for permits  and compliance  plans.    In  addition,
reliance on  forms and electronic  systems may contribute  to the
program flexibility.

     (1) Permit Application, Compliance Plan, and Permit Contents;
     A critical program element to  facilitate real-time allowance
     trading  decisions,  is that permit applications,  compliance
     plans, and permits  will  not  have to be amended  each time a
     source engages in allowance trading.   Rather the success of
     the Acid Rain  control  program will  depend  heavily  on  a

-------
reliable allowance tracking and trading system to support end-
of-year compliance determinations.

The permit documents must, however, articulate the essential
requirements  of  the Acid  Rain program.   Since  the permit
application, compliance plan, and permit  are binding on the
source,  maximum  flexibility  will  depend  on limiting  the
information required in these documents to what is necessary
for ensuring compliance at the affected units.  Although many
of the Acid Rain  program  requirements that must be included
in the permit documents are explicitly enumerated in Title IV,
additional  information  may  be   needed   to  ensure  program
accountability.   The  Agency needs to  consider  what  data
elements are implicitly needed to ensure compliance with the
CAA.

For  example,  the legislation authorizes a  wide range  of
compliance methods. The compliance plan, which becomes a part
of the permit and is required to be developed by sources and
submitted with their permit applications,  is the vehicle for
the source  to articulate its choice  of  one or more of the
authorized compliance methods.  Certain compliance  options may
be chosen  for affected units at  the source which  must  be
supported by information and commitments to achieve mandated
deadlines (e.g. demonstrations of compliance by substitution
sources, deadlines for achieving repowering demonstrations).

By contrast, the permit is expected to contain the more rigid
requirements, such as the emissions monitoring, recordkeeping
and reporting requirements, prohibitions  concerning  the use
of allowances,  operational information  such as  the unit's
baseline, the number of allowances initially allocated to each
unit  covered  by  the permit,  and  the  applicable  compliance
deadlines.  Permit application contents  will depend on the
information needed for permit issuance.

(2) Amendments Procedures;  The Agency is considering adding
flexibility to the program by authorizing amendments by notice
for modifications to compliance  plans.   Amendments  to the
terms of the permit would, by contrast, require more extensive
Agency   review   and   opportunities  for   public  comment.
Provisions  necessary  to  ensure  accountability,  such  as
emissions monitoring  requirements  for  each unit, would  be
included  in the  permit.   Thus,   a source which  decides  to
change its method of compliance could  do so with only minimal
restrictions.   The process  would  have  to  include  certain
safeguards, however, to ensure the source is accountable for
its   emissions   and   compliance   with  other   applicable
requirements.

(3)   Standardized  Permitting:    To  facilitate  information
transfer, the Agency is  considering allowing the electronic

-------
     submission  of  permit  applications,  and  computer generated
     permits.   In addition, the  Agency  may develop  a series of
     forms to  reflect the   differing data requirements  for the
     various compliance  options  authorized by  the legislation.
     For example, all affected sources would be required to submit
     a general form, accompanied by specific forms  for each of the
     alternative  compliance methods  chosen  (e.g.,  substitution
     plans,  repowering).    Thus,  a  source  considering either a
     substitution or a Phase I extension would submit the general
     form, the form for substitution plans and the form for Phase
     I extensions.  In this instance the compliance  plan would also
     have  to indicate a  date certain by  when  the  source would
     decide  which option  it will  pursue.    The forms could be
     available  in electronic format  for sources wishing  to use
     electronic submissions of applications.

How Will Permits Be Issued?                               y

     As  with all other  facilities regulated  by the  CAA,  every
affected  source  is  required  to  develop  and  submit a  permit
application  and  a compliance plan for each affected unit at the
source.  Acid Rain  operating permits  are required  to have a term
of five  years.   (See Section 408(a).)   EPA is required to issue
permits  for  affected sources in  Phase  I,  which begins  in 1995.
For Phase II, which begins in 2000,  Title IV provides that permits
will be  issued  by States  and localities  with  approved permitting
programs under Title  V, or by EPA in the event of state default.
Eventually, all CAA requirements  (Acid Rain,  SIPs, KSPS, etc.) will
be incorporated into one permit.  EPA must develop regulations to
implement  the  requirements of the  Acid  Rain  Program, consistent
with the Title V general operating permits program.

     A  critical  issue  EPA  will  have   to  resolve  early on in
developing the  program concerns  the timing of  permit issuance.
Phase I permit applications,  binding on the source until the permit
is issued, must  be  submitted by each affected source for Phase I
by  February 15,  1993.    EPA  must review  the  compliance plans
submitted with each such application within  six months.  (There is
no deadline  by  which EPA must issue  Phase  I  permits.)  Phase II
permit  applications are  due January  1, 1996  (or 1998  for NOx
requirements and some new sources).  Phase II permits  are required
to be  issued by  States  or localities with approved programs by
December 3J., 1997, or by EPA  in the event of  a State/local default,
by January 1, 1998.  Given the legislative mandate that Acid Rain
permits  have a term of- five years:   (1) if a Phase I permit is
issued before 1995, it will expire before Phase I ends. EPA would
have to  issue another permit to cover the last two years of Phase
I, or Phase  II permits issued by the States would have to include
the requirements  for the last two years of Phase  I.   (2) If the
Phase I permit  is not issued until  December 31,  1994  (so  it lasts
throughout Phase I),  the source will have  two Acid Rain permits
from 1998 through 2000.

-------
     The Agency is  considering  using computerized expert systems
to generate all or  part  of  the  Acid Rain permits.  Use of expert
systems would facilitate expeditious permitting and would ensure
consistency in permit  requirements,  particularly during Phase II
permitting  by States and localities.  At a minimum, expert systems
would  help  ensure  that  essential  Acid  Rain  program  permit
conditions are not  inadvertently left out of  permits.   Although
such a  system promises  efficiency and  national consistency,  its
success will depend on an effective outreach and training program.

How  Will  Acid  Rain  Permits  Be  coordinated   With  The  General
Operating Permits Program?

     The CAA requires that the Acid Rain permit program operate in
accordance with  the general  permits title  (Title V),  except as
modified  by the  Acid Rain  title   (Title IV).    Where the  two
permitting  programs  differ,  the Acid  Rain  requirements  take
precedence for purposes  of  the  Acid Rain portion of the permit.
(See Section 506(b)).

     (1)   Relationship  Between  Acid Rain.  SIP.  NSPS.  and Other
Clean Air Act Permit Requirements.  It is important to keep in mind
in any  discussion of integration issues  that  the general  permit
program under Title V  does  not  establish any substantive program
requirements, only  the  permitting  program.    Each  permit  issued
under  Title V  will,  thus,   have .essentially   separate  chapters
specifying  Acid   Rain  requirements,   SIP  requirements,   NSPS
requirements, NESHAP requirements, as appropriate depending on the
source involved.   A paramount  concept to understand in considering
how these separate programs  might affect operations at a source is
that  nothing  in   one   substantive  program  can  supersede  the
requirement to comply with other programs. Thus,  a source subject
to a strict SIP or NSPS limit  of S02 may not emit in excess of that
limit just because it holds allowances under the Acid Rain program.
A  source  in that  situation will  be  better  off  selling  the
allowances it cannot use. Similarly, a  relaxed SIP limit will not
override the absolute Acid Rain prohibition that a unit cannot emit
SO2 in excess of the allowances  it holds for use in that year.  As
a practical matter, therefore, the most stringent CAA requirement
will govern the operations at a source.

     (2)   Timing  Conflicts  Between Titles IV  and V.   A critical
issue,  related to the permit-term issue discussed  above,  is the
conflict between permit  duration and permit issuance deadlines in
Title IV and Title V.  As previously noted, Section 408(a) mandates
that  Acid Rain  permits  have a  term of five  years.   Title  V
authorizes permit terms  of  u£ £fi five  years,   but allows states
the discretion to issue permits  of shorter duration.  In addition,
Title V mandates revisions to operating permits before the end of
five years to incorporate new requirements.

-------
     EPA needs  to address these permit-term  conflicts  to ensure
effective use of resources by the permitting authority and to avoid
burdening facilities  which are both  SIP arid Acid  Rain affected
sources with multiple permitting.  The permit issuance process is
resource-intensive for both the permitting authority and the source
involved.   It  is,  therefore,  important  to ensure  that  all air
permitting  requirements  (e.g.  Acid Rain,  SIPs, NSPS,  etc.)  are
included in a source's permit as quickly  as  possible  — preferably
by the beginning of Phase II.   Unless the  authority for shorter
permit terms  in Title V is deemed to be superseded by  Title IV,
affected  sources under  the  Acid  Rain  program  will tend  to be
burdened inordinately by repeated permitting.

     (3)  Compliance Plan Contents  Under  Titles  IV and V.  Another
area needing integration is the extent to which Title V compliance
planning requirements  might  be superseded  by Title IV.   Section
408(b) limits the contents  of  compliance  plans for sources not
seeking approval  of one  or more  special  compliance options which
are specifically enumerated.  This  provision presumably applies to
the planning requirements for achieving initial  compliance.  Plans
may, however, include such Title V components as a description of
the source's operation and maintenance,  and compliance monitoring
program.

-------
                                                                   P2
Key Issues for Acid Rain Permits. Permit Applications and
Compliance Plans

     What must be in the permit application, in the compliance
     plan, and in the permit?

     How can the integrity of the acid rain program be ensured,
     particularly state-issued permits during Phase II?  For
     example, how can the shield provisions of Title V be
     interpreted restrictively in the context of the Acid Rain
     program?  Should regulations bar state permits if state law
     is changed to significantly alter the approved permit
     program?  What mechanisms must be created and what tasks
     performed to ensure that permit applications and proposed
     compliance plans faithfully articulate and are consistent
     with:

           (1) special allowance allocation authorities, such as
     clean states, energy conservation-renewable energy
     (404(e)/503(j)), incentive units (section 503(m))?

           (2) requirements for NOx program, and for the
     alternative methods of compliance in the S02 program, e.g.
     election sources (section 410/509), substitution plans
     (section 404(b)/504(c)), Phase I scrubber extensions
     (section 404(d)/504(e), and repowering/CCT demonstrations
     (sections 402(1), 409/502(a)(14), 508)?

     How can the Acid Rain permit program best be  structured to
     facilitate the transition from Phase I Federal permitting to
     Phase II State permitting?  (e.g. use of expert systems)

     What  dangers exist  of sources trying to use ambient program
     permit requirements to insulate themselves from Acid Rain
     program requirements?

     Since nothing  in Acid Rain  program  immunizes  source from the
     obligation to  comply fully  with other CAA requirements  (e.g.
     SIP  or NSPS  limits), under  what circumstances would it be
     appropriate  to rely on optional authority in  Section
     408(b)(l) of requiring demonstration of attainment of the
     NAAQS or of  compliance with a SIP,  NSPS or other  limitation,
     be appropriate?  Are there  statutory or policy  reasons or
     benefits for conditioning Acid Rain permit approval on
     demonstrations of compliance with other requirements under
     the  Act?  E.g.  if the  SIP is known  to  be  inadequate? when
     reviewing substitution plans?  other?  or  should we require
     demonstrations of attainment only  if there is no  SIP in
     place?  What are the dangers of  intermingling the ambient
     and  total loadings  programs in this way?

     If the  facility  has SIP, NSPS, or  NSR/PSp limits  on NOx  or
     SO2,  can or  should  the Acid Rain  permit  impose  the most
     stringent limit  as  an  operating  requirement  for purposes of

-------
Acid Rain permitting?  Should a source be obligated to
transfer allowances based on more stringent non-Acid Rain
limits?  Or should non-Acid Rain limits be addressed
completely separately from the Acid Rain portion of the
permit?  Should this issue addressed differently in Phase I
and Phase II permitting?

How should permit challenges be handled?  Should challenges
to permits be time-barred?  What permit challenge procedures
should be provided for?  Should procedures be mandated
during Phase II?  Should enforcement be barred while a
permit challenge is pending?  Should there be some type of
interim relief?  Would treatment in case of initial permit
challenges differ from challenges to permit revisions?

How specific should compliance planning requirements be so
as to ensure accountability yet afford maximum flexibility
in support of the allowance trading provisions of the
program?  (E.g. should compliance plans relying on the
intent of the owner or operator to obtain allowances by end
of year, be required to include a fall back add-on schedule
with increments of progress if allowances are not available
by a date certain?  Should advance back-up planning be
required for sources seeking Phase I or repowering
extensions, in the event an increment of progress is missed
or the technology does not give intended results?)

What policy decisions and guidance should be included in the
regulations to address conflicting statutory deadlines?
(See more detailed issue paper.)

Applications for various extensions and for optional
alternative baselines are due March 31, 1991, before the
regulations defining designated representative are due.  How
should we deal with this timing issue?

The permit application and compliance plan are binding until
the permit is issued.  What should be required to be
included in the application based on this fact?  Should an
application form be mandated containing or referencing
applicable prohibitions?

What criteria in addition to submittal of required
information will be used to determine whether compliance
plans should be approved or modified by the permitting
authority?  For example, in reviewing Phase I substitution
plans submitted under Sections 404(b) and (c), should EPA
approve plans that are facially sufficient and rely on the
strength of the excess emissions and other enforcement
provisions as the incentive for not sources to overextend?
or must EPA assess whether allowances will be available
under the trading system rather than, or in addition to, the

-------
allowance allocations specified in Table A?

Under what circumstances should integrated permit
applications or compliance plans be required?  (Section
408(b) — governing more than one source)

Can EPA approve allowance pools, obviating the need for an
end-of-year unit-by-unit accounting?  If so, what
limitations should be imposed?

Reduced Utilization or Shutdown:  Section 408(c)(l)(B)
limits the planning requirements to affected sources under
section 404 (Phase I - S02) and section 407 (NOx).  Does
this mean that such plans cannot be required from Section
405 units which intend to comply in this manner?

Substitution Plans:  Should or can the language "unit(s)
under the control of such owner or operator" be read to
include units which, by agreement of two or more owners or
operators, are placed under the control of one designated
representative?

Energy Conservation and Renewable Energy:  Units may begin
earning credits under Section 404(f) towards allowances 4
months before EPA issues conservation/renewable regulations
and permit regulations.  What guidance should EPA provide
regarding certification of emissions avoided during this
time period?

A Phase II unit could presumably earn allowances under this
subsection from 1992 through 2000.  When would the Phase II
source have to submit a permit application?  (Phase II
permit applications are normally due by January 1, 1996. If
a source wants to receive conservation/renewable allowances
beginning in 1995, it seems that the source should submit
some type of permit application by the Phase I permit
application deadline.)

The criteria for acceptable plans are difficult to address.
EPA must determine what constitutes "qualified" conservation
and renewable energy under subsection 404(f) (in consulta-
tion with the Secretary of Energy), and the determination
must rely heavily on the potential to demonstrate the
legislated requirements for issuance.  If the reductions
cannot be quantified, can the measure qualify?

How frequently should compliance certifications  (progress
reports) be submitted?  Quarterly?  Within a specified time
period of the occurrence of a scheduled deadline or a change
of circumstances, e.g. 10 days?  (This issue should be
coordinated with the emissions reporting regulations to
minimize reporting burden.)

-------
Can permit application, compliance plan, final permit, and
compliance certification forms be developed to facilitate
use of a expert systems for generating permits, and of
computerized information retrieval systems accessible, to
participants in the allowance trading program?  If so, what
EPA data system should be used to record and provide
regulated community ready access to such information?  What
confidentiality protections should: be established?

Duration of Operating Permits:  Under Section 408(a), acid
rain operating permits shall have a term of five years.
Title V authorizes permit terms of shorter duration.  In
addition, the Title V mandates revisions to operating
permits before the end of five years to incorporate new
requirements.  These permit term provisions conflict with
the initial Phase I and Phase II Acid Rain permitting
requirements which would appear to require longer terms:

(1)  Phase I begins on January 1, 1995.   Phase I permit
     applications, binding on the source until a permit is
     issued, are due 27 months after the date of enactment
     (i.e. February 15, 1993).  EPA must review the
     submission within 6 months, i.e. August 15, 1993.

(2)  Phase II begins January 1, 2000.  Phase II permit
     applications are due on January 1, 1996, or in 1998 in
     the case of Section 407 requirements and for some new
     sources.  Phase II permits are required to be issued by
     the States December 31, 1997, or by EPA in the event of
     a State default, January 1, 1998.

How should EPA address these permit term conflicts?  Will
the Acid Rain portion of the permit be reissued, revoked,
and revised in accordance with state program permitting
schedules?  Section 506(b) seems to indicate this is not the
case.  If not, when the Acid Rain portion of the permit
comes up for reissuance, will the entire permit be reissued
and reopened?  Is there any way of avoiding the permit
reissuance process for Phase I and the first five years of
Phase II? e.g. Can the legislation be read to allow a Phase
I permit to expire December 31, 1999, or must the Phase II
permit issued in 1998, include requirements to govern
operations the last two years of Phase I?  Similarly, must a
Phase II permit issued December 31, 1997, be reissued in
2002?

Assuming two types of amendment processes are used  (formal
amendments and amendments by notice) what should the
effective date of any amendment be:  Upon receipt of notice
by EPA?  Upon EPA notification to source of date of
effectiveness of amendment?

-------
Phase I Extensions:  when should EPA start accepting Phase I
Extension applications?  Note Allowances for units granted
extensions are awarded on a first-come-first-serve basis.
Many sources which may not ultimately actually seek such
extensions would like to begin submitting applications
immediately in order top preserve their place in line.
Presumably EPA will not be in a position to consider such
submissions until permit application requirements are
promulgated in final form in 18 months.

Repowering:  How should EPA define qualifying clean coal
technology for purposes of a Section 409 compliance deadline
extension? ("Repowering" is defined at Section 402(12) as
replacement of an existing coal-fired unit (or any oil or
gas unit which was awarded clean coal demonstration funding
as of January 1, 1991), with an enumerated clean coal
technology or with any other new technology to control
simultaneous multiple emissions and improved efficiency and
waste reduction.)

There is a conflict in the repowering extension referred to
as a 1-year extension at section 403(a)(1) , on p. 15, and as
a three-year extension in section 409.  Is the reference on
p. 15 a typo?

Does a Phase I Extension or a Repowering extension apply to
NOx requirements?  Presumption that extension only applies
to SO2.  However, statutory language is ambiguous.  Is there
authority to include NOx limits in extensions if it will
result in a decrease in NOx emissions?  Do we want to do
this?

Should the technological/economic infeasibility of a chosen
repowering technology demonstration requirement go into the
permit?  If a demonstration is made, should the permit be
modified?  Should the demonstration requirement be separate
from the permit?  Should the compliance plan be required to
specify a back-up technology?

New Units: There is an apparent conflict in that §405(g)(4)
provides for allowances for certain new units, but they are
not listed as one of the exceptions for allowance
allocations under §403(e):  (1) Is this a technical error in
Section 403(e)?  (2) Should we presume that new units
authorized to have allowances allocated under the exceptions
in Section 405(g) must submit permit applications by  1/1/96
and meet all other Phase II deadlines?  Or are they on the
more lenient new unit permit application deadline?

How should "designated representative" status be
established?

-------
How should EPA perform offset fee CPI adjustments, and what
mechanisms must be established for the receipt and deposit
of excess emissions fees?

-------
                                                                     P3
November 29, 1990
              ACID RAIN PERMITS,  PERMIT APPLICATIONS
            AMD COMPLIANCE PLANS — PERMIT TERM ISSUE
ISSUE
How can the conflict between Title IV and Title V, resulting from
the  provision in  Title  IV mandating  permit terms  of  5  years
duration, be resolved?
DISCUSSION

     There are  several permit duration  and scheduling conflicts
between the  General Permits title  (Title  V),  and the Acid Rain
Permits requirements (Title IV).

     Section  506 (b)  states  that the  Acid  Rain  Act  (Title IV)
overrides Title V in regards to permits.

     11 Permits Implementing Acid Rain Provisions.— The provisions
     of this title,  including  provisions regarding schedules for
     submission and approval or disapproval of permit applications,
     shall apply to permits implementing the requirements of Title
     IV except as modified by that title.11

     Under Section 408(a), Acid Rain operating permits shall have
a term of five years.  Title V authorizes permit terms of shorter
duration.  In  addition,  Title V mandates  revisions  to operating
permits  before  the   end  of   five years  to  incorporate  new
requirements.   These  permit  term  provisions  conflict with the
initial Phase I and Phase II Acid Rain permitting requirements.

(1)  Phase  I  begins  on January  1,  1995.     Phase I  permit
     applications, binding on the source until  a permit is issued,
     are due 27 months after the date of enactment (i.e. February
     15, 1993).   EPA must review the  compliance  plans submitted
     within 6 months,  i.e. August 15,  1993, although there is no
     mandated date for issuing the permit.

(2)  Phase II begins January 1, 2000. Phase II permit applications
     are due on January 1, 1996,  or  in  1998  in the case of Section
     407 NOx  requirements and  for  some new sources.   Phase II
     permits are required to be issued  by the States or localities
     with approved  programs December 31, 1997, or by  EPA in the
     event of a State or local default, January 1, 1998.

See attached Timelines.

     How should EPA address these permit term conflicts?

          Will the  Acid  Rain  portion of the permit  be reissued,
          revoked, and revised  in accordance with the  Title V state

-------
or  local  program  permitting  schedule,  or  must  all
facilities which are Acid Rain affected sources be placed
on  a  five-year  cycle for  purposes  of  SIP permitting
notwithstanding   a   different   state/local   program
permitting cycle  for  other types of  sources?  Section
506(b) seems to indicate this is not the case.  If not,
when the Acid Rain portion of the permit comes  up for re-
issuance,  will  the  entire  permit  be  reissued  and
reopened?

Is there any  way of avoiding a permit re-issuance process
for Phase I  and  the first  five  years of Phase II? e.g.
Can the legislation be read to allow a Phase I permit to
expire December  31, 1999?   Should the Phase  II permit
issued in 1998, include requirements to govern operations
the last two years of Phase I?  Similarly, must a Phase
II permit issued December 31,  1997, be reissued in 2002?

-------
                            TIMELINES


1.  ACID RAIN PERMITTING TIMELINE:  The Acid Rain Permits Program
(Section 408 of Title IV) specifies the following timeline —

     May 15, 1992:  Promulgate final regulations

     February  1993:   Phase  I permit  applications and  proposed
     compliance plans due

     August, 1993:  Deadline  for  EPA to act on  Phase I compliance
     plans.  (Note,  there is  no express statutory deadline for EPA
     to issue  Phase  I permits.   If issued on this  date,  Phase I
     permits would  have to  be  reissued  before August  1998  for
     remainder of Phase  I due to 5-year  permit  term restriction.
     Re-issuance could be virtually automatic.  Alternatively, the
     legislation might be construed to authorize the EPA to issue
     permits with an effective date beginning  1995, particularly
     since the source will be bound by the permit application and
     proposed plan until the permit is issued.

     January 1,  1995:    Phase  I  emissions  limitation  compliance
     begins, except for  sources with extensions.  Closing date for
     sources to submit applications for 15-month NOx extensions.

     April  1,  1995:   Deadline  for EPA  to  act on  NOx extension
     petitions

     January 1, 1996:   Phase II  permit  applications and proposed
     compliance  plans  due.   (Must  be   submitted  to  States  or
     localities and to EPA since we will not know until July who
     has to issue the permits.   See, below).

     July l, 1996:   Deadline for  approval  of State/local permit
     programs.   If State or local program is not approved by this
     date, EPA must issue Phase II permits by 1/1/98.

     December 31, 1997:   Deadline for States/locals with approved
     programs to issue Phase II permits for SO2 (including approved
     compliance plans).   Since  permits  are of  5-year duration,
     query whether we can  make  the effective date  of  the permit
     begin in the year 2000 in order to avoid re-issuance in 2002?

     January 1, 1998:  Deadline for EPA to issue Phase II permits
     for S02, where State/local does not have approved program by
     July 1,  1996.    (Permits  shall include approved  compliance
     plans).  Note, permits are of 5-year duration.  One issue is
     whether we can make the  effective date of the permit begin in
     year 2000 in order to avoid re-issuance in 2002.

     January 1, 1998:   Sources must submit  (Phase II)  NOx permit
     application and proposed compliance plan.

-------
     January 1, 2000:  Phase  II  emissions limitations compliance
     begins  (except  for  sources   vith  three-year  Repowering
     extensions.)

     December 31,  2002:   Reissue five-year Phase IZ permits.

     December 31, 2003:   Phase II compliance begins for sources
     vith three-year Repovering extensions.
II.  PERMITS TITLE TIMELINES:   The General Permits Title calls for
     the  following  regulatory  development  and  implementation
     timeline —

     November 15, 1991:  Promulgate final regulation

     November 15, 1993:  Deadline for submission of State or local
     permit programs to EPA

     November 15, 1994:  Deadline for EPA to act on State or local
     permitting program

     November 15,  1995:   Deadline  for sources to  submit permit
     applications unless EPA has to promulgate the permit program
     (presumably for non-acid rain permitting requirements)

     November 15, 1996:  EPA promulgates state/local permit program
     where State or locality defaults

     May 15, 1997:  State must have issued 1/3 of initial permits
     with terms of up to five years

     May 15, 1998:  State must have issued 2/3 of initial permits
     with terms of up to five years  in duration.  (Presumably Acid
     Rain SO2  permits issued  by December  1997, and  NOx permits
     issued based on January 1,  1998  submissions,  can be counted
     in meeting this obligation.)

     May 15, 1999:  State must  have  issued initial permits for all
     sources, vith  terms  of   up to   five   years  in  duration.
     (Presumably, Acid Rain NOx permits,  which  must be issued
     before 1/1/2000 can be included in this number).

-------
Other Issues:

There is a conflict  in  the repowering extension referred to as a
1-year extension at section 403(a) (1), on p. 15, and as a 3 year
extension in section 409.  Is the reference on p. 15 a typo?.

The closing date for sources  to  submit applications for a 15-day
NOx extension  for Phase  I is the date that Phase  I compliance
begins.  How will last minute applications be handled?

Repowering extension documentation for Phase II is due on the date
that Phase II compliance begins.  How will last minute submissions
be  evaluated  in  time  to  require  Phase  II  compliance  if  the
documents  fail to  show adequate advancement in  the repowering
process.

-------

-------