United States
           Environmental Protection
           Agency
              Office of
              Inspector General
              401 M Street, SW
              Washington, DC 20460
EPA
Report of  Internal and
Management  Audit
                REPORT OF AUDIT ON THE
      MANAGEMENT OF THE CHESAPEAKE BAY PROGRAM
            POINT SOURCE POLLUTION PROGRAM
        AUDIT REPORT NUMBER E1H98-03-0208-9100467

                  SEPTEMBER 11, 1989

-------
%3- i"
(Wi
                              TABLE OF CONTESTS
    OBJECTIVES,  SCOPE  AND METHODOLOGY.

    SUMMARY OF FINDINGS	

    ACTION REQUIRED	

    BACKGROUND	

    FINDINGS AND RECOMMENDATIONS
         1.   IMPROVED  ENFORCEMENT ACTIVITIES NEEDED TO
              PROTECT THE BAY	,
         2.   WATER QUALITY STANDARDS AND TOXIC CONTROL
              STRATEGIES  DELAYED	
    APPENDIX A - REGION  3  RESPONSE TO DRAFT AUDIT REPORT.

    APPENDIX B - DISTRIBUTION	
1

4

6

6
10


24

29

30
                           HEADQUARTERS LIBRARY
                           ENVIRONMENTAL PROTECTION AGENCY
                           WASHINGTON, D.C. 20460

-------

-------
             UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

                       OFFICE OF THE INSPECTOR GENERAL

                           MID-ATLANTIC DIVISION

                           841 CHESTNUT BUILDING

                       PHILADELPHIA. PENNSYLVANIA  19107
September  11,  1989

MEMORANDUM
SUBJECT:
FROM:
TO:
Audit Report Number E1H98-03-0208-9100467
Report of Audit on the Management
of the Chesapeake Bay Program  -  Point
Source Pollution/Control Program
P. Ronald Gandolfo
Divisional Inspector
Edwin B. Erickson
Regional Administrator
                                  'neral for Audit
OBJECTIVES. SCOPS AND METHODOLOGY

     We performed an  audit of  the Chesapeake Bay Program
administered by Region  3  of the Environmental Protection Agency.
This audit is the third in a series we plan to perform of the
Chesapeake Bay Program.   The purpose of this audit was to determine
if:

     o Region 3 and the states actively and aggressively
       enforced National  Pollutant Discharge Elimination
       System (NPDES) permits.

     o Region 3 ensured that states adequately performed
       their enforcement  responsibility.

     o Region 3 ensured the states implemented Clean
       Water Act  (CWA)  requirements to reduce the amount
       of toxics  entering the  Bay.

-------
     We  performed  the  audit  in  accordance with the Standards for
Audit  of Governmental  Organizations, Programs, Activities and
Functions issued by the  Comptroller General of the United States as
they apply to  economy  and  efficiency and program results audits.
Our review included tests  of the program records and other auditing
procedures we  considered necessary.

     Although  the  Chesapeake Bay is surrounded by the States of
Delaware,  Maryland,  Pennsylvania, Virginia and West Virginia and
the District of Columbia,  our review focused on Maryland,
Pennsylvania and Virginia  because of the high concentration of
dischargers in these states  that affect the Bay.  We performed our
work primarily at  EPA  Region 3; the Maryland Department of the
Environment (MDE);  the Pennsylvania Department of Environmental
Resources (PA  DER);  and  the  Virginia State Water Control Board
(VA SWCB).

     During this audit we  reviewed the Chesapeake Bay Agreements
entered  into with  the  states and legislation authorizing the
cleanup  of the Chesapeake  Bay.  We met with officials and staff
from the Region 3  Water  Management Division and the state agencies.

     To  determine  if Region  3 and the states actively and
aggressively enforced  NPDES  permits, we reviewed the CWA to
identify the requirements  and responsibilities of the delegated
states and EPA.  We  also reviewed the memorandums of agreement
between  EPA and the  states to determine the responsibilities of
each.

     Our work  included a review of the actions taken by Region 3 to
ensure that the states complied with the requirements of the CWA
for controlling toxic  substances.  We obtained information
concerning the status  of documents submitted by the states and
reviewed each  to determine if the documents were consistent with
the CWA  requirements.

     To  evaluate Region  3's  and the states' enforcement programs,
we reviewed the quarterly  noncompliance reports to determine the
number of  Chesapeake Bay facilities in violation of their NPDES
permit.  We then reviewed  the permit files, maintained by Region 3
and the  states, to determine the violations that occurred and the
enforcement actions  taken  to bring the violating facility into
compliance.  These enforcement  actions included administrative
orders,  consent orders,  consent order and agreements, and the
assessed  fines.  We  also determined whether the dischargers adhered
to compliance  schedules  included in these orders.  Enforcement
actions  taken  against  municipal and industrial dischargers were
evaluated  to determine if  these actions complied with the CWA as
well as  EPA regulations  and  procedures.

-------
     Region  3  provided the total number of  major and minor
dischargers  to the Chesapeake Bay.   Municipal  facilities
discharging  a  flow of  one million gallons or more per day are
classified as  major.   Industrial dischargers may be classified as
major depending on both the amount of  toxic pollutants and the
volume of the  discharge.   Dischargers  who do not meet these
criteria are classified as minors.   Figures provided by Region 3
show that there are 4,294 dischargers  into  the Chesapeake Bay
permitted under the NPDES.  Of this number,  329 are classified as
major dischargers  and  3,965 as minor dischargers.   As of March
1988, 88 or  27 percent of the 329 major dischargers were listed as
out  of compliance  on the quarterly noncompliance report.
       CHESAREAKE  BAY MAJOR  DISCHARGERS
   8 .,1


   I .=
   !*> „
          DC
                                             OP MAJOR DISCHARGERS

                                      NUMBER OUT OF COM PLIANCE
                 MO  PA
                 STATES
We randomly selected  11 of the  88 major dischargers reported as  out
of compliance.  Seven of these  were municipalities and  four were
industrial dischargers.  The breakdown of these facilities by  state
is as follows:
Maryland
Pennsylvania
Virginia
Mimi.ci.pali. ties

Frederick City
Freedom District
Pocomoke City

Athens-Sayre
Kelly Township
Wellsboro Authority

Waynesboro
Industries

Trans-Tech
Eastern Stainless Steel
L.A. Clarke & Son
U.S. Marine Corps, Quantico

-------
     Our audit  covered  enforcement activities during the period
October 1,  1985 through June  30,  1988.  Limited testing of
activities  prior to  October 1,  1985 was also performed where
warranted.   Our study focused on  major facilities since they have
the most significant environmental impact on the Bay.

     This review disclosed several areas needing improvement which
are discussed in this report.   Recommendations were provided to
assist Region 3 and  the states  to improve their enforcement
program.  Our work included a review of EPA's internal controls for
monitoring  the  states'  enforcement programs.  We evaluated EPA
procedures  to ensure the states were administering their
enforcement programs in accordance with the CWA and EPA
regulations.  We examined EPA's mid-year and end-of-year reviews
of state programs to identify weaknesses and those actions taken or
planned to  resolve them.  In  addition, we reviewed EPA's procedures
to ensure the states completed  all the tasks required by the CWA
for controlling the  discharge of  toxic substances to the Bay.

     The Permits Compliance System is the National data base for
the NPDES program.   The total number of dischargers in the
Chesapeake  Bay  Basin was  obtained from this system.  We did not
review the  general and  application controls of the data base
because the main purpose  of our review was to evaluate the
effectiveness of the NPDES enforcement program.  No other issues
came to our attention which we  believed were significant enough to
warrant expanding the scope of  this audit.

     Our survey for  this  review began on June 15, 1988 and was
completed on November 4,  1988.  As a result of this survey, we
initiated an in-depth review  on November 18, 1988.  The fieldwork
for this audit  was completed  on February 28, 1989.  The matters
contained in this report  were discussed with responsible personnel
from Region 3 and the state agencies.


SUMMARY OF  FINDINGS

     The findings included in this report are summarized below.
The detailed findings,  along with related recommendations for
corrective  action, are  provided in the "Findings and
Recommendations"  section  of this  report.

1.

     Region  3,  as well  as the States of Pennsylvania, Virginia and
Maryland,  need  to take  more aggressive enforcement action against
polluters of the Chesapeake Bay.  We found that Region 3 and the
three states in  our  review did  not effectively perform their
responsibilities  to  enforce against dischargers who violated their
NPDES permit.   Specifically our review disclosed:

-------
     o Region  3  and  the  states  have been  slow in  revising
       outdated  memorandums  of  agreement.

     o Region  3  did  not  require the states  to complete
       Enforcement Management System  (EMS)  guides.

     o States  hesitated  to take enforcement action
       against municipalities.

     o Region  3  did  not  take enforcement  action when
       the  states failed to  initiate  appropriate  enforcement.

     o Region  3  oversight was inadequate  to ensure proper
       coordination  of enforcement actions.

     During the  past several years, EPA and the states established
various  goals  and implemented numerous initiatives intended to
restore  and protect  the  Bay.  These initiatives such as research
projects, animal waste management systems,  fertilizer management
and nutrient reduction,  while costly, are reported to be
beneficial.  In  spite of these  efforts, associated costs  and the
expressed commitment to  the  Chesapeake Bay  Agreements of  1983 and
1987, NPDES enforcement  actions against violating facilities were
weak.  As a result,  polluters were allowed  to discharge millions of
gallons  of  inadequately  treated wastewater  into the Chesapeake Bay
for many years.  This pollution could diminish the benefits
achieved from  other  initiatives already implemented and possibly
hinder the  achievement of numerous worthwhile goals and objectives
in the Chesapeake Bay Agreements.
2.
WATER QUALITY STANDARDS ASP TOXIC CONTROL STRATEGIBS DELATED
     EPA needs to ensure that Maryland, Pennsylvania, and Virginia
take more expeditious and aggressive action to control toxic
pollutants.  These states did not complete all of the tasks
required by the CWA  for controlling toxic discharges.  Completing
these tasks are vital to reduce toxic pollutants entering the Bay.
This is critical because a key objective of the 1987 Chesapeake Bay
Agreement is to work towards a toxic free Bay by eliminating the
discharge of toxic substances from all controllable sources.
                               *****
     On June 19, 1989, a draft report was issued to the Regional
Administrator.  Written comments to our draft report were provided
by the Regional Administrator on August 18, 1989.  His response
included additional comments by personnel from the Virginia State
Water Control Board, and the Pennsylvania Department of
Environmental Resources.  Subsequently, we received comments from
the Maryland Department of the Environment.  Personnel from Region
3 requested that we include this response in our report.

-------
 Consequently,  we appended  these  comments to our report.  Region  3's
 response generally agreed  with our recommendations, but did not
 provide  a plan for correcting the deficiencies discussed in our
 report.   After evaluating  the comments provided by both Region 3
 and  the  states our position  remained unchanged.

      On  September 6,  1989  we held an exit conference with Region  3
 personnel.   During the  conference we explained various details
 concerning our report.   Region 3 agreed with the findings and
 stated that corrective  action would be provided.

      To  provide a balanced understanding of the issues, we
 summarized the Regional Administrator's comments after each
 finding.   Also included is our rebuttal to the response.  We
 also included  the complete response in Appendix A.

      The courtesies and cooperation extended by your staff during
 this audit are appreciated.


 ACTION REQUIRED

      In  accordance with EPA  Directive 2750, the action official  is
 required to provide this office  with a written response to the
 audit report within 90  days  of the audit report date.


 BACKGROUND

      In  1975,  under Public Law 94-116, Congress directed EPA to
 conduct  a five year study  of the Chesapeake Bay's water quality and
 resources.   Congress  also  directed EPA to develop management
 strategies  to  preserve  the Bay's quality.  Consequently, in 1976
 EPA  established a research program to identify and study the major
 environmental  problems  in  the Chesapeake Bay.  The research
 program,  which ended  in 1981, indicated there was a historical
 decline  in  water quality and living resources.  This decline was
 due  primarily  to nutrient  enrichment, contamination by toxic
 chemicals,  and loss of  much  of the submerged aquatic vegetation.
 Nutrients and  toxic chemicals entered the Bay from point sources
 such as  sewage treatment plants  and industrial facilities, and from
 nonpoint  sources such as urban,  suburban and agricultural runoff.

      During 1982 and  1983, EPA analyzed the research findings.  The
Agency concluded that the  reduction of nutrient loadings and toxic
 contamination  to the  Bay from both point and nonpoint sources was
needed.    In December  1983, the Governors of Pennsylvania, Maryland
and  Virginia,  the Mayor of the District of Columbia, and the
Administrator  of EPA pledged to  implement a coordinated plan to
restore and protect the waters and the living resources of the Bay.
This  commitment,  known  as  the Chesapeake Bay Agreement of 1983,

-------
pledged to address point and nonpoint  sources of pollution
affecting the Bay.  These parties reaffirmed their commitment by
signing the  1987 Chesapeake Bay Agreement.

     Water quality improvement is the  most critical element  to  the
restoration  and protection of the Chesapeake Bay.  To achieve this,
the parties  of the Agreements pledged  to: reduce nutrient loadings
by 40 percent; manage  and control conventional pollutants; and
reduce toxic pollutants entering the Bay.  Numerous objectives  were
included in  the Agreements to achieve  the goals of reducing
nutrient loadings and  toxic substances.  Some of these are to:

     o Provide timely  construction of  public and private
       sewerage facilities to assure control of pollutant
       discharge.

     o Reduce the discharge of untreated or inadequately
       treated sewage  from such sources as combined sewer
       overflows, leaking sewage systems, and failing
       septic systems.

     o Establish and enforce pollutant limitations to
       ensure compliance with water quality laws.

     o Identify and control toxic discharges to the
       Bay system including metal and  toxic organics
       to protect water quality, aquatic resources and
       human health through implementation of the
       states NPDES permit programs and other programs.

     o Reduce the discharge of metals  and organics from
       industrial sources.

     o Reduce chlorine discharges in critical finfish
       and shellfish areas.

Many of these objectives can be accomplished by ensuring compliance
with water quality laws.  This compliance can be achieved by
aggressively enforcing NPDES permits.

     The establishment of the NPDES under the CWA of 1972 mandated
that permits be issued to all point sources discharging directly
into navigable waters.   NPDES also required effective compliance
monitoring and a strong enforcement program by EPA and the states.
The NPDES permit established the kind  and quantity of treated
wastewater a permittee may discharge.  It also contained specific
requirements for pretreatment, monitoring and reporting.

-------
     The CWA  enabled  EPA to delegate the NPDES program to the
states.  EPA  delegated the program to all three states in our
review.  The  delegated states issue permits to both major and minor
dischargers,  which  self-monitor their discharges and submit
summaries of  effluent data to the states.  The states are
responsible for  identifying instances of noncompliance and taking
timely and appropriate enforcement action which may include the
assessment of fines to deter noncompliance.  These enforcement
actions are intended  to bring the violating facility into
compliance as expeditiously as possible.  The states are required
to escalate enforcement action when compliance is not achieved in
an expeditious manner.

     EPA's function is to provide oversight to delegated states
through the review of state issued permits, program audits, and
analysis of states' enforcement and monitoring activities.  The CWA
requires EPA  to  initiate its own enforcement action, which may
include the assessment of fines, when states fail to take timely
and appropriate  enforcement action.  Under 40 CFR 123.63, EPA can
withdraw the  authority delegated to the state to administer the
NPDES Program if the  state fails to carry out the program as
required.

     The Clean Water  Act also addressed the problem of toxic and
highly concentrated industrial waste being introduced into Publicly
Owned Treatment Works (POTW's) by requiring pretreatment programs.
Pretreatment  programs require industries to remove excessive and
highly concentrated pollutants from their wastewater before
discharging into the  municipal sewage treatment system.  The POTW
regulates the discharge of toxic wastes or unusually strong
conventional  wastes through control mechanisms such as individual
permits or sewer use  ordinances.  These mechanisms establish
enforceable limits, monitoring conditions, and reporting
requirements.  EPA regulations require the POTW to initiate
enforcement action against an industry when violations occur.
These actions  can include fines assessed by the POTW against the
industries.   If the POTW does not take enforcement action, it may
be taken by EPA or the state.

     In September 1985, Region 3 delegated responsibility for the
pretreatment  program  to the State of Maryland.  As a result,
Maryland was  responsible to ensure that POTW's operated their
pretreatment  program  in accordance with EPA requirements.  Because
pretreatment  responsibility was not delegated to Pennsylvania and
Virginia,  Region 3 administered the pretreatment program for these
states.

-------
     In 1987, the CWA was amended to provide an increased focus on
toxic contamination.  To accomplish this the states are required to
identify and address waters that do not meet water quality criteria
for the 126 priority pollutants defined in Section 307(a) of the
CWA.  Complex, man-made compounds such as dioxins and PCBs,
pesticides such as DDT and EDB, and metals such as mercury and lead
are just a few of the more troubling toxic substances recently
found in the environment.  Many of these chemicals, when present in
sufficient quantities, are known to pose a variety of hazards to
the Bay ecosystem.

-------
FINDINGS AND RECOMMENDATIONS

!•    IMPROVED ENFORCEMENT ACTIVITIES NEEDED TO PROTECT THE BAY

      Region  3,  as well  as the  States of Pennsylvania, Virginia and
Maryland, need to take  more  aggressive enforcement action against
polluters of  the Chesapeake  Bay.  We found that Region 3 and the
three states  in our  review did not effectively perform their
responsibilities to  enforce  against dischargers who violated their
NPDES permit.   Specifically  our review disclosed:

      o Region 3 and  the states have been slow in revising
       outdated memorandums  of agreement.

      o Region 3 did  not require the states to complete
       Enforcement Management  System (EMS) guides.

      o States hesitated to take enforcement action
       against  municipalities.

      o Region 3 did  not take enforcement action when
       the states failed to  initiate appropriate enforcement.

      o Region 3 oversight was  inadequate to ensure proper
       coordination  of  enforcement actions.

      During the past several years, EPA and the states established
various goals and implemented  numerous initiatives intended to
restore and protect  the Bay.   These initiatives such as research
projects, animal waste  management systems, fertilizer management
and nutrient  reduction,  while  costly, are reported to be
beneficial.   In spite of these efforts, associated costs and the
expressed commitment to the  Chesapeake Bay Agreements of 1983 and
1987,  NPDES enforcement actions against violating facilities were
weak.  As a result,  polluters  were allowed to discharge millions of
gallons of inadequately treated wastewater into the Chesapeake Bay
for many years.  This pollution could diminish the benefits
achieved from other  initiatives already implemented and possibly
hinder achievement of the numerous worthwhile goals and objectives
in the Chesapeake Bay Agreements.

                         OUTMODED PROCEDURES

      Formal agreements  between EPA and the states became outdated
and were not  enforced.   In addition, Region 3 failed to require the
states to develop written enforcement procedures as required by the
Agency.

      EPA formally delegated  the NPDES program to the states under
memorandums of  agreement which established the basis for
cooperation and coordination between the Agency and the states.
These  agreements defined the relationship between EPA and the state

                                 10

-------
and indicated the responsibilities of each.  In accordance with
EPA's NPDES State Program Guidance, dated July 29,  1986, modi-
fications to the agreements were expected to be made within a
reasonable time to assure consistency with new or revised Federal
regulations.  EPA was responsible for initiating revisions to the
memorandums of agreement with the state agencies.   Revising these
agreements was needed to ensure that the NPDES program is
administered in the most effective manner consistent with Federal
regulations.

     The agreements between Region 3 and the States of Maryland,
Pennsylvania and Virginia were formalized over a decade ago.  Since
that time, the statutes regulating the NPDES program were revised
twice.  As a result, these memorandums of agreement are outdated
and do not reflect the extensive revisions to the NPDES program.
Region 3 has been negotiating revisions to all three agreements for
several years, but has been unable to resolve the numerous dis-
agreements that arose with the states on the content of the
agreements.  More importantly, Region 3 did not require the states
to comply with the requirements of the existing agreements.  For
example, the agreements called for timely and appropriate
enforcement.  The Pennsylvania and Maryland agreements specifically
required enforcement action within 30 days of the permittee having
been notified of a violation.  We found that none of the states we
reviewed adhered to these requirements and allowed NPDES violations
to persist for years.  Region 3 should have proposed revisions to
the agreements to reflect the new laws in a more timely manner.
This would have strengthened the enforcement programs of the
states.  Also, Region 3 should have ensured that the states
complied with existing memorandums of agreement.

     The methods used by Region 3 to obtain enforcement management
system guides from the states is another example of lack of
forceful direction.  The EMS guides were intended to be used as a
tool by the states to document and ensure the adequacy of their
enforcement procedures.  The EMS defines the principles necessary
for the operation of an effective enforcement program and provides
the basis for evaluating the performance of administering agencies.
Region 3 did not require state agencies to complete their guides as
required by EPA's national EMS guide.   As a result, the states do
not have written enforcement procedures consistent with EPA's EMS
guide or Federal regulations.

     EPA Headquarters published the Agency's EMS guide in 1977 and
subsequently revised the guide on February 27,  1986.  This national
guide required each state to have management procedures to track
the status of permit compliance, to surface violations, and to take
timely and appropriate enforcement action.  In all, the national
                                 11

-------
guide lists  seven basic principles that should be included for the
states to have an effective EMS.  These written procedures were to
be in place  by October 1,  1986 and are subject to annual review.

     The State of Maryland submitted a draft EMS guide to Region 3
in October 1987.  A Region 3 review, dated December 3, 1987,
disclosed that the proposed EMS guide was incomplete.  As of
February 1989, the State had not provided any additional infor-
mation to Region 3.  As a  result, two years after the October 1986
deadline, the EMS guide was still incomplete and Region 3 took no
action.

     Pennsylvania submitted a proposed EMS guide to Region 3 for
approval during October 1987.  Region 3 personnel believed the
guide was inadequate.  We  found that the guide was incomplete.
However, Region 3 accepted the incomplete guide because the effort
to obtain a  completed EMS  was not a high priority and the receipt
of any system from Pennsylvania was considered an accomplishment.
We could not find documentation to indicate Region 3 personnel
informed the State that the EMS was inadequate.

     Virginia did not submit an EMS to Region 3.  We could not find
documentation to indicate  the Region required the State to submit
the EMS.

     Region  3's approach to the three states was inconsistent.
Maryland submitted an incomplete draft EMS, and the completion of
the EMS was  made a requirement of their Section 106 grant.  Each
year EPA awards these grants to the states to provide funds for
activities such as establishing water quality standards,
permitting,  enforcement and monitoring.  The Region did not use
its ability  to withhold grant payments to pressure the State.
Completing the EMS was not made a requirement of the Section 106
grants for the other two states.  We believe Region 3 should have
actively pursued the completion of EMS's in all three states in
order to achieve consistent enforcement activities, not only for
those dischargers affecting the Bay, but for all dischargers.

                       FORCELESS ENFORCEMENT

     In addition to the lack of aggressive action by Region 3 and
the states to update procedures, other aspects of their enforcement
programs intended to ensure the integrity of the Bay were defi-
cient.  For  example, even  when the pollution was serious or
longstanding, the states were very patient with polluters.  States
assessed only insignificant penalties after several years or did
not assess any penalties.  Also, Region 3 was hesitant to take
action against violators when the states failed to take timely and
appropriate  enforcement action.  This became evident during our
review of dischargers to the Bay.
                                 12

-------
     Based on our review of  11 facilities, we found the  following
were the only penalties collected  for NPDES permit violations:
Facility

Athen s-Sayre, PA
Wellsboro, PA
Trans-Tech Inc., MD

TOTAL
Type of
Facility

Municipal
Municipal
Industrial
Penalty
Collected

$    200
   7,800
 107.700

S115.700
     The $200 paid by Athens-Sayre was for violating interim permit
limits contained  in  the  1986 consent order and agreement.
Wellsboro Municipal  Authority paid $7,800 for numerous NPDES permit
violations that occurred since 1986.  This amount included $3,200
for two incidents in which more than 1600 fish were killed because
of pH violations.  Between February and December 1987, this plant
also violated the Biochemical Oxygen Demand (BOD) limit in the
consent decree that  was issued by the State.  For these violations
the State fined the  Municipal Authority $1,000.  We estimate the
penalty could have been at least $390,000 for these BOD violations.
Trans-Tech, Inc.  is  an industrial facility that paid two penalties.
The first was $100,000 for consistent NPDES permit violations as
far back as 1981.  The second penalty for $7,700, was paid for
permit violations from November 1987 to May 1988.  The files lacked
documentation to  support the basis for these penalty calculations.
We believe the penalties collected are insignificant and did not
hinder noncompliance.

     In all 11 facilities reviewed, enforcement actions did not
escalate when violators did not take corrective measures.  EPA's
EMS guide requires that enforcement actions escalate when
compliance is not achieved expeditiously after taking the initial
action.  An example  is the wood preserving operation of L.A. Clarke
in Virginia that produced railroad ties, foundation pilings and
landscape lumber.  This facility violated their NPDES permit for 13
years and not one penalty was assessed.  Since 1976, five consent
decrees were issued.  Three of these were for NPDES violations and
two were for violating state air regulations.  In addition, a
special order and a  board directive were issued because of NPDES
violations.

     The violations  at the L.A. Clarke facility were frequently
covered by local newspapers which sharply criticized EPA's
performance.  These  reported that:

     Federal Officials say the ground, soil, groundwater
     and lagoons in  and around the 26 acre site are soaked
     with contaminants from years of using creosote to
     preserve wood.
                                 13

-------
     The  SWCB  charged  in  1982 that the company had violated
     water pollution standards  162 times since 1975.

The  special  order  that was  issued in April 1978 documented that
L.A. Clarke  consistently  violated its NPDES permit for phenolics
since  1975.  The operation  of this facility caused a number of
environmental  problems such as  surface and groundwater contamina-
tion.  As a  result, during  June 1986 the site was listed on the
Superfund National Priorities List and the cost of the cleanup was
estimated at $23 million.   In July 1988, the State finally revoked
the  NPDES permit for this facility.  More aggressive NPDES enforce-
ment might have forced the  industry to act more responsibly and
mitigated the  extent of the Superfund cleanup.

     The  wastewater treatment plant in Frederick, Maryland is
another illustration of enforcement that did not escalate.  This
facility  violated  its  NPDES permit for over 12 years.  During this
time,  the State issued one  consent agreement, three consent orders,
one  complaint  and  order,  and two amended consent orders, but again
no penalties were  assessed.  In general, states did not take
aggressive enforcement action against municipalities, especially
when grant funds were  needed to construct additional facilities.
However,  EPA guidance  provides  that this is not a valid reason for
delaying  enforcement.  The  irony is that many municipal wastewater
treatment plants received flow  from significant industries.
Because municipalities received patient treatment from the states,
industries were in turn given a "free ride".  Municipalities did
not aggressively enforce  against industries or assess penalties,
even when industrial waste  significantly contributed to municipal
NPDES  violations.  Consequently, these industries received an
economic  advantage because  pretreatment requirements were not
enforced.  Both Region 3 and the State of Maryland were remiss in
not requiring  municipalities to implement an effective pretreatment
program.

     The  pretreatment  program in Frederick, Maryland is an example
where  industries contributed to the violations at a POTW and
received  an  economic advantage.  It also illustrated lax
enforcement  by the State.   On April 15, 1986, the State issued a
consent order  that required industries to comply with the City's
pretreatment program.  This requirement was not achieved.  Subse-
quently,  on  January 29, 1987, another consent order was issued.
This order required a  dairy, with a history of violations, to
construct a pretreatment facility designed to reduce BOD loadings.
A second  dairy, that was also violating its pretreatment permit,
was to discharge to this new facility.  Because of various delays
by the dairies, the City amended this order twice, allowing
construction of a  $3 million treatment plant to be postponed for
several years.   As a result, three years later the dairies were
still not pretreating  their wastewater.
                                 14

-------
     Kelly Township in Pennsylvania  illustrates that Region  3  had
similar enforcement problems.   This  Township did not comply  with
the July  1983 deadline for  submitting an approved pretreatment
program.  In response, during April  1984, Region 3 issued an
administrative  order.  In spite of this, it was not until
September 1985  that the  Township  submitted a complete program
that was  approved  by Region 3.  An inspection by Region  3 in May
1986 revealed that the Township had  not issued the required  permits
to industrial users and  had not adequately inspected and sampled
industrial users.  Region 3 performed another review of  Kelly
Township  in October 1987.   This review found that the Township
still did not issue permits to  their industries.  According  to EPA
guidelines, these  permits should  have been issued early  in 1986.
Region 3  did not issue any  additional enforcement documents  or
assess any penalties when the Township failed to do this.  Overall,
the pretreatment program was not  followed even though an approved
program existed.

     Kelly Township consistently  violated their Total Suspended
Solids (TSS) permit limit for almost four years.  During that  time,
industries contributed 70 percent of the flow being processed  at
the Township's  plant.  The  Township's plant was originally designed
to accept the flow from  these industries without pretreatment.
However,  the treatment plant was  in  need of additional construction
to meet NPDES permit limits.  Industries discharging to  the
treatment plant benefited because no penalties were assessed,
construction was delayed and the  treatment plant was allowed to
violate their NPDES permit  for  almost four years.

     Frederick  City and  Kelly Township demonstrate that  munici-
palities  were often slow to establish pretreatment programs, and
once established,  reluctant to  take  effective enforcement action.
More effective  enforcement  action against industries would greatly
reduce the amount  of pollutants entering the Chesapeake  Bay.

     On January 30, 1984, EPA issued the National Municipal  Policy
(NMP) which required treatment plants to achieve secondary
treatment by July  1, 1988,  whether or not they received  Federal
funding.   There were numerous examples where the states  did  not
take enforcement action  because POTW's were waiting for  an EPA or
state grant in order to  finance new  facilities.  This resulted in
years of violations occurring without aggressive enforcement action
taken against the  facility.

     For example, Athens-Sayre  in Pennsylvania was ordered to
upgrade their facility as far back as 1969.  This facility had
continuous BOD and TSS violations.   In September 1986, a consent
order and agreement was  issued ordering Athens-Sayre to  upgrade its
facility.   It was not until  20 years after the initial order that
construction of the new  facility  was completed.  We were informed
that the reason for delay was that Athens-Sayre attempted numerous
times to obtain a Federal grant.  In 1974,  the State informed

                                15

-------
Athens-Sayre that they did not qualify for a grant, yet no action
was taken by the State until 1986 when the consent order was
issued.  Consequently, Athens-Sayre was allowed to delay
construction for almost 20 years while waiting for a grant.
Pennsylvania officials indicated that the NMP was used as the tool
for finally taking enforcement action against this facility.

     Another example of a treatment plant waiting for a grant was
Pocomoke City in Maryland.  Since 1981, this facility had
continuous violations of the total chlorine residual limit in its
permit with no enforcement action taken.  During discussions with
Maryland officials, we found that only $5,000 was needed for
dechlorination equipment to eliminate the violations.  In April
1988, Maryland awarded Pocomoke City a grant to install
dechlorination.  We believe that since such a minimal amount of
funds were needed to correct the situation, either a grant should
have been awarded earlier or the City required to correct the
problem with local funds.  Also, Pocomoke has industrial users who
could have shared in these costs.  Any of these remedies would have
eliminated the chlorine violations that occurred during the past
seven years.

                      INADEQUATE EPA OVERSIGHT

     The weak enforcement by the states and Region 3 is not a
recent phenomenon.  A fiscal year 1988 review by EPA Headquarters
documented shortcomings in this area.   The following comments are
excerpts from this report:

     o For the first two quarters in fiscal year 1988
       Region 3's enforcement activity was low.

     o Formal enforcement was taken against only 2 of 14
       POTW's considered by the Region to be in reportable
       noncompliance for failure to implement pretreatment.

     o Only 3 of 16 POTW's either completed implementation
       of all needed remedial pretreatment measures
       communicated to them or were referred for
       failure to complete such remedial measures.

     o State penalties were often low compared to
       Federally assessed penalties.  The Region will
       continue to encourage higher penalties, but
       believes they have little leverage.
                                 16

-------
     o Pennsylvania  should expedite enforcement and issue
       unilateral orders.  Pennsylvania was a problem with
       24 of the 32  cases in Region 3 that were shown on the
       Exceptions List because they violated their permits  for
       an inordinate amount of time.

     The Headquarters review, as well as our audit, disclosed that
the states were not  forceful regulators and that Region 3's over-
sight was lacking.   In spite of this, the Region 3 reviews were not
critical of state enforcement programs.  These reviews of state
enforcement programs were not used as an effective management tool.
For example, the Region  3 review of Maryland's water program grants
for fiscal year 1987 disclosed only that:

     Another major shortfall in FY '87 involved the
     State's failure to assess penalties for municipal
     noncompliance.   MD must begin imposing penalties
     where appropriate; otherwise, EPA will consider
     taking penalty  action.

     Contrary to the Headquarters review, Region 3's mid-year
review of Pennsylvania did not criticize them for not issuing
unilateral orders.   Also, Pennsylvania was not criticized for not
escalating enforcement actions or for not assessing appropriate
fines.  This review  only provided the following general comment:

     Our respective  staffs continue to work toward
     the reduction in the number of cases on the
     Exceptions List.  We would like to encourage
     your staff to continue these efforts to reduce
     the number of cases.

     We were unable  to evaluate the mid-year review of Virginia's
enforcement program.  Region 3 personnel informed us that the
review results were  provided verbally to the State.  Based on our
review, it appears that the enforcement program of this State also
could have been more forceful.

     Region 3 did not require the states to modify practices that
conflicted with EPA's policies.  This was evidenced by Region 3's
disagreement with Maryland's policy of not assessing fines against
municipalities.  State personnel attempted to achieve compliance
through cooperation.  They believed compliance would be achieved
more quickly if they provided technical assistance to
municipalities rather than to initiate enforcement action.
Maryland's philosophy regarding municipal dischargers is to be a
partner rather than  a regulator.  We did find that the State was
tougher on industrial dischargers.  In some cases,  however, even
the fines assessed against the industrial violators were
inadequate.
                                 17

-------
       We  disagree with  Region  3 allowing the State to continue
 this  philosophy.   The  seriousness of Region 3's inaction was
 evident  in the  case of Frederick.  The State tried extremely hard
 to  assist  this  facility.   They  went as far as prescribing the type
 of  treatment  process the City should design.  Eventually the City
 expanded their  plant and the dairies started construction of their
 pretreatment  facility.   However, it took years to complete the
 City's plant  and  the dairies were still not pretreating.  When the
 new plant  developed operational problems, the State did not take
 enforcement action because they helped select the treatment
 process.   Normally the design engineer should have been responsible
 to  correct these  problems.  If  not corrected in a timely manner,
 the State  should  have  initiated enforcement action.

      Similar  problems  occurred  with Freedom District also in
 Maryland.   This facility violated its NPDES permit for over three
 years.   The State attributed the violations to inadequate sludge
 disposal,  which resulted in sludge washing out of the plant at
 least 45 times  during  1986.  These washouts which impaired water
 quality  were  also a health hazard.  Because the sludge washouts
 continued,  the  State issued a consent order during September 1987
 requiring  the design and construction of a new facility.  However,
 the design and  construction was not completed.  A second order was
 issued during March 1988  because the District was unable to meet
 the Total  Kjeldahl Nitrogen limit in their permit.  This order
 prescribed specific operational measures which the District
 implemented,  but  the problem persisted.  The result of the State's
 lack of  enforcement to date is: the District is still violating
 their permit; the State  is  unsure of what other operational
 techniques  to try;  the District started to design plant
 improvements; no  penalties  were assessed; and Region 3 still did
 not initiate  any  action.

     In  order to  improve  oversight procedures, Region 3 should also
 focus attention on how the  states actually resolved noncompliance.
 We  found that violators were often given interim permit limits that
 were less  stringent than  their  original permit.  The interim limits
 often masked  the  violation.  This allowed violators to be
 considered  as "resolved  pending".  However, the facility was
 discharging the same amount of  inadequately treated wastewater.
 This occurred in  five  of  the 11 cases included in our review.  For
 example, in September  1986  Kelly Township, Pennsylvania entered
 into a consent  order and  agreement with the State to upgrade its
 facility.   The  Township was given interim limits, which were in
 effect from September  1986  until March 1988, that were 1.5 times
 less stringent  than the  final limits.

     During July  1987, Virginia did revise their enforcement
 program.   They  implemented  a computer system to compare discharge
monitoring  report data with permit limits.  Based on this analysis,
 violations  will be accumulated  and the violator informed of
 noncompliance problems.   This system is essentially a warning

                                 18

-------
device which identifies violations.  If corrective action is not
taken, the enforcement section is notified so that appropriate
action can be taken.  Personnel from the State contend that this
system will improve enforcement.  However, the review period for
this audit preceded implementation of the system and therefore the
benefits from the new system are not known.


CONCLUSION

     The reviews by EPA Headquarters, as well as our audit,
highlighted that the states were not forceful regulators and that
Region 3's oversight was lacking.  We found that Region 3 did not
take action, as required by the CWA, when the states failed to
aggressively pursue violators.  Improved oversight would require
the states to take stronger and more effective enforcement actions.
Stronger enforcement would reduce the number of violations and
protect the Bay.  Moreover, enforcement is not the only area where
Region 3 should require more action by the states.  The second
finding in this report discusses the need for more action by the
states to reduce toxics entering the Bay.


RECOMMENDATIONS

     In order to achieve the goals intended to restore and protect
the Chesapeake Bay, we recommend that the Region 3 Administrator:

     1.  Update memorandums of agreement to ensure that
         the NPDES program is administered consistent with
         the current law and Federal regulations.

     2.  Ensure the states finalize EMS guides to
         strengthen the adequacy of state enforcement
         procedures.

     3.  Assure that aggressive enforcement action
         is taken in a more timely manner and that
         enforcement action escalates when compliance
         is not achieved.

     4.  Require the states to assess penalties
         against violators which are significant
         enough to deter noncompliance.

     5.  Initiate direct Federal enforcement action when
         states fail to pursue violators.
                                19

-------
      6 .   Require  that  reviews  performed by Region  3
          of  the state  programs are used as an effective
          management  tool.   Deficiencies in state
          enforcement programs  should be disclosed  fully
          during these  reviews,  along with actions
          required to correct the deficiencies.

      7.   Assure that POTW's implement pretreatment
          programs in a timely  manner.  If the POTW's
          fail  to  initiate  action when violations occur,
          Region 3 or the states should take enforcement
          action against industrial users .

   lion 3's Response  to Recommendation Number 1

      Region  3  agreed that  the  memorandums of agreement should be
updated and  indicated  they have been negotiating new agreements
over  the  last  several  years .   These negotiations can be very time
consuming since they are not taken lightly by either EPA or the
states.   Maryland's  memorandum of agreement has just been signed by
the State and  EPA, and is  now  official.  Pennsylvania's agreement
is nearing completion.  Further, the states routinely included
commitments  in their annual work plans to ensure the relationships
between Region 3  and the states reflect current policy even though
the memorandums of agreement may not be completely updated.

Inspector General ' 8  Coronon't.8

      The  annual work plans  submitted by the states are not a
substitute for the memorandums  of agreement.  The memorandums of
agreement define  responsibilities, policies and procedures while
the work  plan  establishes  the  states ' activities and program
commitments  for the  year such  as the number of compliance
monitoring inspections to  be performed.  In our opinion, these
documents have different purposes and updated memorandums of
agreement are  essential.

Region 3's Response  to Recommendation N"™****' ">

      Region  3  agreed with  this  recommendation and  indicated that
draft EMS guides  were  received from the states and are currently in
the process  of approving the guides.  Although EMS guides were not
approved  by  the Region, all states have enforcement policies and
procedures which  they  follow.

Insector General ' s
     As our report indicated, the guides from Maryland and
Pennsylvania were received by Region 3 in 1987 and the guides were
still not approved.  The guide from Virginia was not submitted.
Moreover, we could find no documentation to indicate Region 3
pressured the states to submit complete EMS guides .

                                 20

-------
     We believe  that Region  3  should have required the  states  to
complete these EMS guides  as mandated by the Agency's national
policy.  Moreover, the  enforcement policies and procedures that the
states currently are using are not a substitute for an  effective
EMS guide.  These guides represent an opportunity for Region 3 and
the states  to document  organization assignments, procedures,
timeliness  requirements and  enforcement responses needed to ensure
an effective program.   Region  3 and the states' performance
described in the audit  indicates a high priority need for EMS
guides which will enable the states to meet the objectives of  the
CWA.
     Region  3  concurred and  indicated they never hesitated to take
enforcement  actions.  Very often a decision not to act is made
based on the severity of the violation, the lack of available
Region 3 staff time, the states' assurance that action will be
taken or the fact that a Federal action, over and above a state
action may not result in quicker resolution to the problem.  A
considerable amount of time  is needed to take actions and impose
penalties.   There are currently 47 active civil cases and seven
active administrative penalty actions being pursued by Region 3.
The Exceptions List for the  Region has been reduced from nearly 50
cases to 19  cases in less than three years (See Attachment B of
Region 3's complete response).  While we are not satisfied with the
present level, this does show progress and we will pursue further
reductions.

     In addition to Region 3's response, the Virginia State Water
Control Board indicated that enforcement actions did escalate.

Inspector General'a Comments

     The intent of this recommendation was that EPA should ensure
the states take enforcement  action.  The states were responsible
for identifying instances of noncompliance and taking timely and
appropriate  enforcement action.  These enforcement actions should
attempt to bring the violating facility into compliance as
expeditiously as possible.   The states are required to escalate
enforcement  action when compliance is not achieved in a expeditious
manner.  The CWA requires EPA to initiate its own enforcement
action when  states fail to take timely and appropriate enforcement
action.  For this reason, we believe that Region 3 needs to ensure
that more aggressive enforcement is taken by the states.

     We do not agree with the Virginia SWCB comments that
enforcement  action escalated.  For example, considering the
severity of  L.A. Clarke's NPDES violations which persisted for 13
years and the fact that the  state did not assess any penalties, we
cannot concur that there was an effective escalation of enforcement
action.

                                 21

-------
Region 3'a Response to Recommendation Number 4

     Region  3 agreed with this recommendation.  The Region
considers penalties, as well as injunctive relief, as part of the
enforcement  response to violations.  States very often use other
punitive measures  in lieu of fines.  Several states restricted new
sewer connections  until compliance was achieved.  This action not
only restricts the income of the violators, but also acts as an
incentive to complete corrective measures as soon as possible.

Inspector General's Comments

     The sample of cases reviewed during this audit did not provide
any examples where the states restricted sewer connections.  We
did find that one  state had a system for restricting the sewer
connections  to facilities that violated their NPDES permit.
However, we  found  that the system was very rarely used to restrict
sewer connections.  Furthermore, considering the length of time
that the facilities in our review violated their permits, it would
seem that injunctive relief should have been abandoned and more
stringent enforcement initiated.

Region 3's Response to Recommendation Number 5

     Region  3 agreed with this recommendation and indicated they
initiated appropriate enforcement actions when the states have not.
The entire Regional NPDES enforcement caseload consists of actions
against dischargers in delegated states (except the District of
Columbia).  This is done as part of our oversight responsibilities.
The size of our current caseload (i.e., 71 civil and administrative
cases) reflects our commitment to strong Federal oversight.

Inspector General's Comments

     During our review we did note instances where Region 3
initiated enforcement actions when the states did not.  However,
our review indicated that Region 3 needs to intensify their efforts
in this area.  We  did review the enforcement actions initiated by
Region 3 during FY 1988 and found that most actions were for cases
in Pennsylvania.   We believe this was caused by Pennsylvania's
difficulty to issue unilateral orders.   This is corroborated by
the Headquarters review of Region 3.  Region 3 needs to initiate
enforcement actions not only in Pennsylvania but also needs to
increase their efforts in the other states.

Region 3's Response to Recommendation Number 6

     Region 3 agreed with our recommendation and indicated that
quarterly enforcement meetings are conducted with each of the
delegated states.  When deficiencies are uncovered, we work with
the states to correct them, and formalize any corrective action
plans as appropriate, including discussions and agreements between

                                 22

-------
the Regional Administrator and State Secretaries and, if necessary,
the Governors.  We believe that these meetings have been
instrumental in our success in achieving a 60% reduction in our
Exceptions List over the past three years.

Inspector General's Comments

     We realize that these quarterly meetings serve a useful
purpose.  However, the reviews of state programs are required by
EPA regulations and these regulations require that the results
should be documented.  Since both our review and the past EPA
Headquarters reviews indicated there were problems with the states
enforcement programs, we believe the Region 3 reviews should have
documented these problems.

     We were aware that the number of facilities on the Exception
List was reduced.  However, as discussed in our report, the methods
used to prevent a facility from being shown on the Exceptions List
does not always result in less pollution.  Very often facilities
were placed in the "Resolved Pending" category for several years
using interim limits that were less stringent than their original
limits.

Region 3 * B Response to Recommendation Number 7

     The Region agrees with this recommendation, and sees it as a
crucial component of a successful pollution control program.  It is
not surprising to see delays in initial enforcement action by the
POTW's since this is a relatively new experience for many POTW's.
Enforcement action continues to be taken against POTW's and
industrial users for failure to comply with pretreatment
regulations.

Inspector General * B CnmHif>iitB

     The pretreatment program was delegated to the State of
Maryland four years ago and Region 3 administered the pretreatment
program for Pennsylvania and Virginia during this time.  After four
years, we cannot agree that the newness of the program should cause
delays in taking enforcement action.
                                 23

-------
2.   WATER  QUALITY STANDARDS AND  TOXIC CONTROL STRATKaTKS r>KT.MYKn
     EPA needs to ensure  that Maryland, Pennsylvania, and Virginia
take more expeditious and aggressive action to control toxic
pollutants.   These  states did not complete all of the tasks
required by  the CWA for controlling toxic discharges.  Completing
these tasks  are vital to  reduce toxic pollutants entering the Bay.
This is critical because  a key objective of the 1987 Chesapeake Bay
Agreement is to work towards a toxic free Bay by eliminating
contamination by toxic substances from all controllable sources .

     The CWA includes a national commitment to control toxic
substances discharged by  NPDES permitted sources.  Subsequently,
the Water Quality Act (WQA) of 1987 amended the CWA requiring the
states to adopt water quality standards to control toxic
pollutants.   These  standards are the cornerstone of the process to
control pollutants,  including toxic substances.  To establish water
quality standards,  states must designate uses for their waters.
Typical designated  uses are for drinking water, public recreation,
protection and propagation of fish, agriculture and industrial
uses.  Criteria are then  adopted to ensure the water quality is
appropriate  for its designated use.  These criteria are later used
to formulate limits in NPDES permits.  Revising water
quality standards for toxics was also a requirement of the fiscal
year 1987 and 1988  Section 106 grants awarded by Region 3 to these
states.  If  these grant requirements were not achieved, 40 CFR
30.900 provides specific  actions to be taken by Region 3.  These
include withholding grant payments or terminating the assistance
agreement .

     Section 307 (a)  of the CWA contains a list of 65 compounds
which are among the most  persistent, prevalent and toxic chemicals
known to man.  These 65 compounds have been translated into 126
priority pollutants.  Section 304(1) of the CWA contains three
specific requirements relating to the NPDES program for controlling
toxic substances by permitted dischargers.  First, the states were
required to  list the waters not expected to meet water quality
criteria for the 126 priority pollutants defined in Section 307 (a)
of the CWA.   Second, states must list the toxic pollutants of
concern and  identify the  dischargers causing the problem.  Third,
states must  issue an Individual Control Strategy (ICS) for each
discharger identified.  EPA defined the ICS as a NPDES permit with
discharge limitations and a proposed compliance schedule to reduce
toxics to an acceptable level .  The CWA mandated that the states
complete these tasks by February 1989.  Region 3 is required to
approve or disapprove the lists and ICS's by June 1989.  If the
states fail  to submit, or Region 3 disapproves the submittal, then
Region 3 must develop the lists and ICS's by June 1990.  Final
compliance with the  toxic requirements of the CWA is required by
June 1992.
                                 24

-------
     As of March  1989, Maryland, Pennsylvania and Virginia did not
adopt water quality  standards  for  toxic pollutants as required by
the CWA and none  of  the  sanctions  available to Region 3 were
imposed on the  states.   Maryland and Pennsylvania officials
indicated that  these standards were not revised because of
insufficient  staff.   However,  we found that the 106 grants
previously discussed in  this report provided funds to complete
these tasks.

     Virginia also did not  adopt water quality standards to control
toxics.  The  State was awaiting EPA guidance for implementing this
provision of  the  Act.  In spite of this, during April 1988, Region
3 approved standards without controls for toxics.  At the same
time, Region  3  informed  the State  that, "we share concern over the
need to adopt additional water quality standards for toxic
pollutants as mandated by the  recent revisions to the Clean Water
Act."  Region 3 further  suggested  that EPA and State staff meet to
further discuss the  matter.  The State's fiscal year 1989 work plan
for the 106 grant indicates further delay is likely because the
standards for toxics will not  be adopted until receipt of "final
nationwide guidance  from EPA."  This lack of guidance does not
appear to be  a  valid reason for delay.  Final guidance was
available for numerous pollutants  and draft guidance was available
for others.   The  failure to adopt  these standards in a timely
manner hinders  the NPDES permit program and delays the toxic
controls for  the  Bay.

     Increased  efforts are  also needed to fulfill the requirements
of Section 304(1) of the Act.  By  February 1989, only Maryland
submitted all the required  documents.  The list of waters impaired
by toxics that  was submitted by Pennsylvania was not complete.
Region 3 personnel indicated that  the list submitted by Virginia
may also be incomplete.  Moreover, neither state submitted the
required ICS's.

     In 1981, Pennsylvania  implemented its own Toxic Management
Strategy.  The  State intends to continue using this existing
strategy to satisfy  the  requirements of Section 304(1) of the 1987
WQA.  However,  this  strategy does not provide enforceable permit
limits for controlling toxics.  For example, when the limits for
toxics are exceeded  the  discharger must only perform a toxic
reduction evaluation.  This evaluation determines what actions are
needed to achieve compliance with the NPDES permit.  The discharger
is not subject  to enforcement action for violating toxic limits
until the toxic reduction evaluation is completed and the results
included in a modified permit.  Region 3 personnel indicated as
many as 60 dischargers were performing toxic reduction evaluations.
These dischargers were not  included on the list of dischargers
requiring an  ICS.
                                 25

-------
     Pennsylvania submitted a list of 78 dischargers that required
an ICS.  However, the State listed only the NPDES dischargers with
permits expiring this year as needing an ICS.  The 60 dischargers
requiring a toxic reduction evaluation were not included.  The
State indicated that unexpired permits with toxic limits and
dischargers requiring a toxic reduction evaluation "need not be
identified or listed".  As a result, the number of ICS's submitted
to Region 3 was understated and the list of toxic impaired waters
was incomplete.

     In the case of Virginia the required lists were submitted but
not the ICS's.  Their submittal indicated that 14 dischargers
needed an ICS.  However, in March 1989, the State wrote EPA
indicating that they were "still unclear as to what constitutes an
ICS."  Our discussions with Region 3 personnel during early April
1989, disclosed they were in the process of requesting
documentation from the State to determine the basis for requiring
only 14 ICS's.  This indicated that Region 3 did not resolve the
confusion that existed and continued delays are possible before the
new and important provisions of the CWA are implemented.

     Clearly much work is still required by the states to comply
with the requirements of the CWA.  Region 3 is not planning to
prepare the absent ICS's as required by the CWA.  They intend to
permit the states to complete the ICS's during the time designated
for Region 3 action (between February 1989 and June 1990).  In
effect, Region 3 has granted an informal time extension to the
states.  This cooperation risks the possibility of more delays and
is contrary to the CWA.


RECOMMENDATIONS

     To fulfill the commitments of the Chesapeake Bay Agreement of
1987 and to comply with the CWA requirements for controlling
toxics, the Region 3 Administrator should ensure that:

     1.  Water quality standards for controlling toxics
         are adopted by the states.

     2.  The lists of waters impaired by toxic pollutants
         are completed.

     3.  Each state provides a complete list of
         dischargers that require an ICS.  Moreover,
         an ICS must be completed for each discharger.
                                 26

-------
     4.  Appropriate  sanctions  are  initiated when  the
         states do  not  fulfill  the  CWA requirements  for
         controlling  toxic  pollutants in a timely  manner.
         Because  these  were a requirement of the 106
         grants awarded to  the  states, consideration
         should be  given to withholding 106 grant  funds
         during the current fiscal  year.  Also EPA must be
         prepared to  complete,  in a timely manner/ those
         requirements not accomplished by the states.

Region  3'B Response to  Recc

     Region  3  agrees  that water quality standards  needed to be
upgraded to  comply  with the Water Quality Act.  They indicated that
Pennsylvania has  already adopted the necessary standards and is in
compliance.  Virginia and Maryland  are working to  achieve com-
pliance with further  standards  to be adopted the later half of
1989.

Inspector General's Comments

     Pennsylvania's compliance  is noted.  However, more action is
needed to ensure  that Virginia  and  Maryland overcome historic
difficulties which  delayed  adoption of the necessary water quality
standards.

Region 3'a Response to  Recommendatioi
     Region 3 agrees with the recommendation and reported that all
states have submitted their  lists and they were approved by the
June 4, 1989 deadline.

Inspector General's Comments

The response indicated compliance with this recommendation.

Region 3's Resonse to Recoy™endation N^mher 3
     Region 3 agrees with the recommendation.  Each state submitted
a list of dischargers needing ICS's.  In some cases, the Region
added discharges to the list, as part of the 304(1) approval
process.  We are now working with the states to formalize
commitments to issue ICS's  (in the form of NPDES permits) by the
statutory deadline.

Inspector General fs Comments

     A more specific commitment is needed from the states.  The
missing ICS's from the states are late.  The Region is permitting
the states to use the time allowed in the statute for EPA action.
While this may be practical, the Region must provide more vigorous


                                 27

-------
oversight to ensure the states comply with the Water Quality Act.
Region 3 must be prepared to act on those required ICS's which the
state fails to complete before the statutory deadline.

           Response to Recommendation Knmha-r A

     Region 3 agrees with this recommendation.  As with all grant
conditions, the Region is prepared to take sanctions and other
actions as appropriate, if the states fail to meet their
requirements.  The Region has the authority to complete the ICS's
but does not have the resources should there be a significant
inability of the states to fulfill this responsibility.

Inspector General's Comments

     We agree with the response provided.  However, Region 3 must
be prepared to exercise various sanctions such as, delegation
withdrawal or recovering grant funds when states are unwilling or
unable to meet their responsibilities under the Clean Water Act.
This is particularly important when the states are permitted to use
the statutory time allotted for EPA action.
                                 28

-------
                                                                   -appendix A
                                                                   Page 1 of 27
                   UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                  REGION III
                              841 Chestnut Building
                           Philadelphia, Pennsylvania 19107

           Response to Draft Report of Audit on the
SUBJECT:    Management of the CBP - Point Source          DATE-
           Pollution Program Audit Report Number E1H98-03-0208

FROM:      Edwin  B. Erickson •   ' ~ '-'    .   -   • —
           Regional Administrator  (3RA00)

TO:         p.  Ronald Gandolfo
           Divisional Inspector  General for Audit  (3AI00)
AUB 181989
                Thank  you for the opportunity to respond to the subject
          draft audit and the cooperation shown to our staff  in  the
          preparation of our response.  The Region's response to the
          specific  findings and recommendations is attached.  As you
          know,  Bob Mitkus provided Carl Jannetti with additional
          comments  concerning proposed changes to improve the tone and
          context of  the report.  These changes should preclude
          misinterpretation and provide a more accurate description of
          the  issues,  findings and recommendations.  We also  added
          responses received from the states of Virginia and  Pennsylvania
          If your staff  needs further information or clarification,
          please have them contact Bob Mitkus at 7-3420.

          Attachments
                                       29

-------
                                                           Appendix A
                                                           Page 2 of 27
Enforcement Action
Recommendation No.. 1: "The Region should update memorandums
of agreement to ensure that the NPDES program is administered
consistent with the current law and Federal regulations."

Response:  The Region agrees with this recommendation.

Region III has been negotiating new MOA's over the last
several years.  These negotiations can be very time consuming
since they are not taken lightly by either EPA or the States.
Maryland's MOA has just been signed by the State and EPA, and
is now official.  Pennsylvania's MOA is nearing completion.

The States routinely include commitments in the annual workplans
to follow the current policy and laws.  Thus, our relationships
with the States reflect current policy even though the MOA's
may not be completely updated.

Recommendation No. 2: "The Region should ensure the States
finalize EMS guides to strengthen the adequacy of State
enforcement procedures."

Response:  The Region agrees with this recommendation.

Each State has management procedures in place to track the
status of permit compliance, to identify violations, and to
take enforcement action.  As part of EPA's enforcement program
requirements all States are to prepare and submit for approval,
EMS Guides.  We received Draft EMS Guides from the States and
are currently in the process of approving the Guides.  Although
no EMSs have been approved by the Region, all States have
enforcement policies and procedures which they follow.  Where
deficiencies exist, the Region uses every resource available
to get corrections, even to the point of disallowing program
delegations to States with inadequate statutory enforcement
authority.

Recommendation No. 3: "The Region should assure that aggressive
enforcement action is taken in a more timely manner and that
enforcement action escalates when compliance is not achieved."

Response:  The Region agrees with this recommendation.

Region III has never hesitated to take enforcement actions.  Very
often a decision not to act is made based on the severity of the
violation, the lack of available Region III staff time, the States'
assurance that action will be taken or the fact that a federal
action, over and above a State action, may not result in quicker
resolution to the problem.

-------
                                                            Appendix A
                                                            Page 3 of 27
The factors Region III considers in taking enforcement action
are:   (1) what is needed to obtain compliance, and  (2) the
availability of staff time to assess penalties or refer for
civil  litigation.  A considerable amount of time is needed to
take actions and impose penalties.  There are currently 47
active civil cases and seven active administrative penalty
actions being pursued by the Regional Compliance Sections
(see attachment A).

To determine if enforcement actions are effective, all enforcement
actions taken over a period of time should be examined to determine
how successful or unsuccessful they have been.  The trend chart
in attachment B shows that the Exceptions List for the Region has
been reduced from nearly 50 cases to 19 cases in less than three
years.  While we are not satisfied with the present level, this does
show progress and we will pursue further reductions.

Recommendation No. 4: "The Region should require the States to
assess penalties against violators which are significant enough
to deter noncompliance."

Response:  The Region agrees with this recommendation.

The Region's first priority is to return facilities to compliance
with their permit requirements.  But, the Region considers penalties,
as well as injunctive relief, as part of our enforcement response
to violations.

States very often use other punitive measures in lieu of fines.
Several States restrict new sewer connections until compliance
is achieved.  This action not only restricts the income of the
violators, but also acts as an incentive to complete corrective
measures as soon as possible.

Recommendation No. 5: "The Region should initiate direct Federal
Enforcement action when States fail to pursue violators."

Response:  The Region agrees with this recommendation.

Region III has initiated appropriate enforcement actions when
the States have not, and we will continue to do so.  The entire
Regional NPDES enforcement caseload consists of actions against
dischargers in delegated States (except the District of Columbia).
This is done as part of our oversight responsibilities.  We
believe that the size of our current caseload (i.e., 71 civil and
administrative cases) reflects our commitment to strong Federal
oversight.

-------
                                                           Appendix A
                                                           Page 4 Of 27
                             3

Recommendation No. 6: "The Region should require that reviews
performed by Region III of the State programs are used as an
effective management tool.  Deficiencies in State enforcement
programs should be disclosed fully during these reviews, along
with actions required to correct the deficiencies."

Response:  The Region agrees with this recommendation.

Region ill conducts quarterly enforcement meetings with each
of the delegated States.  At these meetings we discuss potential
enforcement cases, as well as the States' enforcement programs
in general.  When deficiencies are uncovered, we work with the
States to correct them, and formalize any corrective action plans
as appropriate, including discussions and agreements between the
Regional Administrator and State secretaries and, if necessary,
the governors.  We believe that these meetings have been
instrumental in our success in achieving a 60% reduction in
our Exceptions List over the past three years (Refer to Attachment
B) .

Recommendation No. 7: "The Region should assure that POTW's
implement pretreatment programs in a timely manner.  If the
POTW's fail to initiate action when violations occur, Region
III or the States should take enforcement action against industrial
users."

Response:  The Region agrees with this recommendation,, and sees it
as a crucial component of a successful pollution control program.

With the responsibility for issuing permits and enforcing them
still a relatively new activity for POTWs under the pretreatment
program, it is not surprising to see delays in initial enforcement
by the POTWs.  POTWs are requiring Industrial Users to install
treatment, and EPA is continuing to provide training in the area
of permitting and enforcement.  EPA also continues to take
enforcement action against POTWs for failure to develop and
implement pretreatment programs, and against Industrial Users
for failure to comply with applicable standards and reporting
requirements.

Water Quality Standards and Toxic Control Strategies

Recommendation No. 1: "The Region should ensure that standards
for controlling toxics are adopted by the States."

Response:  The Region agrees with this recommendation.

Pennsylvania adopted toxic water quality standards in March 1989
which are consistent with the Clean Water Act and its 1987
Amendments.  Virginia and Maryland have adopted standards and
criteria for some toxic pollutants; both States are working
to achieve compliance with the Clean Water Act with further
water quality standards scheduled to be adopted in the later
half of 1989.

-------
                                                           Appendix A
                                                           Page 5 of 27
Recommendation No. 2: "The Region should ensure that the list
of waters impaired by toxic pollutants are completed."

Response:  The Region agrees with this recommendation.

All States submitted their 304(1) lists in accordance with the
Clean Water Act Amendments, and all lists were approved by the
Region by the June 4, 1989 statutory deadline.

Recommendation No. 3: "The Region should ensure that each State
provides a complete list of dischargers that require an ICS.
Moreover, an ICS must be completed for each discharger."

Response:  The Region agrees with this recommendation.

Each State submitted a list of dischargers needing Individual
Control Strategies (ICSs), as required by the Clean Water Act
Amendments.  In some cases, the Region added dischargers to
the list, as part of the 304(1) approval process.  We are now
working with the States to formalize commitments to issue ICSs
(in the form of NPDES permits) by the statutory deadline.  And,
while it is the Region's opinion that it would be more effective
and efficient for the States to maintain control of their permits
and issue them whenever possible, EPA has the authority to prepare
ICSs if it appears that the States will not meet the statutory
deadline.  However, limited resources have been allocated to
perform this activity, and may limit EPA to exercising preemption
authority on only the highest priority permits.

Recommendation No. 4: "The Region should ensure that appropriate
sanctions are initiated when the States do not fulfill the CWA
requirements for controlling toxic parameters in a timely manner.
Because these were a requirement of the 106 grants awarded to the
State,  consideration should be given to withholding 106 grant funds
during the current fiscal year.  Also, EPA must be prepared to
complete, in a timely manner, those requirements not accomplished
by the States."

Response:  The Region agrees with this recommendation.

As with all grant conditions, the Region is prepared to take
sanctions and other actions as appropriate, if the States fail
to meet their requirements.  And, as stated earlier, the Region
has the authority to perform this activity, but does not have the
resources to assume these tasks should there be a significant
inability of the States to fulfill this responsibility.

-------
                                                             Appendix A
                                                             Page 6 of 27
                         ATTACHMENT A

                 Judicial and Administrative
                     Enforcement Actions
The Region's current active NPDES caseload is:

     Civil Judicial Actions                  32

     Civil Judicial Consent Decrees          15

        Subtotal  (Civil)                         47

     Administrative Penalty Actions           7

     Administrative Compliance Orders        17
     (not including those issued prior
     to FY'89)

        Subtotal  (Administrative)                24

     Total                                   71
in FY'89 the Region settled:  (a) 3 initial judicial actions
for a total of $1,730,000 in penalties and requiring the
expenditure of about $2,750,000 in pollution control equipment;
(b) 2 contempt actions for violations of existing consent
decrees for $190,000;  (c) stipulated penalties for consent
decree violations for  $125,000; and  (d) 3 administrative
penalty actions for $54,500.

-------
                                                             Appendix A
                                                             Page 7 of 27
                         ATTACHMENT B

                         Trend Charts
      Exceptions List and Significant Noncompliance Rate
Significant Noncompliance  (SNC) is defined as follows:

       Violation of any condition of a Judicial Decree.

       Violations of compliance schedule milestones for
       start construction, complete construction, or attain
       final compliance by 90 days or more from the date of
       the milestone specified in an enforcement order or
       a permit.

       Failure to provide a compliance schedule report or
       a monitoring report within 30 days of the due date
       specified in an enforcement order or a permit.

       Violation of any monthly average effluent limitation
       contained in a enforcement order.

       Violation of monthly average effluent limitations
       contained in a permit that meet the following criteria -
       four violations in a six month period, or two violations
       which exceed the Technical Review Criteria (TRC) in a
       six month period.  The TRC is 1.4 times the effluent
       limitation for conventional pollutants, and 1.2 times
       the effluent limitation for toxic pollutants.

The Exceptions List contains facilities which have been in
SNC for two consecutive quarters and have not been address by
an enforcement action.

The trend chart shows the Regional Exceptions List and SNC
rates for the third quarter FY'86 through the second quarter
FY'89.  The Exceptions List is in numbers of facilities
(on the List), while SNC is the percentage of facilities in
significant noncompliance.  The chart identifies SNC rates
for municipal and industrial dischargers, along with composite
SNC rates for the Region as a whole.

-------
                                                               Appendix A
                                                               Page 8 of 27
                REGION EXCEPTIONS LIST AND SNC RATES
  86    86   87    87   87    87   88    88   88    88   89   89
                            FISCAL QUARTER
    REG EX LIST (NO.) °" REGSNC(%)
MUNICIPAL SNC   •» NON-MUNICIPAL
   (%)          SNC (%)
For the  Regional Exceptions  List the
improvements.   Out of a  total  of 777
19 on the  list.
   statistics
   facilities
show continued
there were  only

-------
                                                                  Appendix A
                                                                  Page 9 of 27
The  trend charts for the Chesapeake Bay States are  presented
below.
                    MD EXCEPTIONS LIST AND SNC RATE
                      (Universe of 99 Facilities)
    K     ^
   86    86    87    87    87   87   88    88    88    88    89    89
                              FISCAL QUARTER

                       ••- EX LIST (NO.)  -O- SNC (%)

     NOTE:  The rise in SNC rates for Maryland in  1987 was largely due
           to start-up problems  and delayed construction for municipalities
           not meeting secondary treatment levels under the National
           Municipal Policy (NMP).
   86    86
                    PA EXCEPTIONS LIST AND SNC RATE
                       (Universe  of 399 Facilities)
87    87
87    87   88   88
    FISCAL QUARTER
88
          EX LIST (NO.)
                                        SNC (%)

-------
                                                                Appendix A
                                                                Page 10 of 27
                VA EXCEPTIONS LIST AND SNC RATE
                   (Universe of 137 Facilities)
     86   87
87
87    87    88    88
    FISCAL QUARTER
88    88    89    89
                  ••- EX LIST (NO.)  O- SNC (%)

NOTE:   In 1987 Virginia experienced a dramatic increase in SNC
       rates because of NMP enforcement.

-------
                                                                   Appendix A
                                                                   Page 11 of 27
                                  f
                                  £>-&
   Richard N. Burton
   Executive Director

  Post Office Box 11143
Richmond, Virginia 23230-1143
    (804) 367-0056
COMMONWEALTH o/ VIRQINIA
        ST/!T£ WATER CONTROL BOARD
              2111 Hamilton Street
    Mr. Alvin R. Morris,  Director
    Water  Management Division
    US Environmental Protection Agency
    Region III
    841 Chestnut Building
    Philadelphia, PA  19107

    Dear Al:

    Enclosed  are Virginia's  comments on the draft audit of Chesapeake
    Bay activities by the Office of the Inspector General.  I
    apologize for the delay,  but a number of my staff had to review
    this document and make comments.  I hope these comments can still
    be forwarded to the Inspector General.

                                      Sincerely,
                                                    BOARD MEMBERS

                                                    William T Clements
                                                   Henry O Hollimon. Jr.
                                                    Ronald M Plolkin
                                                     VelmaM Smith
                                                    Patrick L. Standing
                                                    W Bidgood Wall. Jr.
                                                    Robert C Wmmger
                                      Richard )N.  Burton
                                      Executive Director
                                      Virginia State Water Control  Board
    Enclosure

-------
                                                           .Appendix A
                                                           Page 12 of 27
                    VIRGINIA WATER CONTROL BOARD

                         8/4/89 COMMENTS ON:

                    DRAFT REPORT OF AUDIT ON THE
              MANAGEMENT OF THE CHESAPEAKE BAY PROGRAM
                   POINT SOURCE POLLUTION PROGRAM

                 BY THE OFFICE OF INSPECTOR GENERAL
ENFORCEMENT

The Inspector General has used the QNCR for the quarter ending March
31, 1988, to illustrate noncompliance by Chesapeake Bay dischargers.
We think that the Inspector General is misusing the QNCR in trying to
demonstrate lack of enforcement for Bay dischargers.  The chart in
the draft audit indicated that 20 major Virginia Bay facilities were
in noncompliance.  In fact, 11 of these facilities were in a resolved
pending status meaning that Virginia had already taken appropriate
action for previous violations.  The Inspector General should realize
that once an action has been taken against a facility, that facility
must remain on the QNCR until all requirements of the action have
been completed and the action has been closed out.  The main
criterion relating the QNCR to the taking of appropriate enforcement
action is the Exceptions List, which is the list of facilities
appearing on the QNCR for two consecutive quarters for the same
violation where no appropriate action has been taken.  The inspector
General failed to note that there were no Virginia Bay facilities on
the Exceptions List of the QNCR he Was using to attempt to show how
lax enforcement had been for the Bay area.

We agree that a formal Enforcement Management System (EMS) has not
been submitted to Region 3.  However, we have been implementing all
of the requirements of an EMS for many years.  Region 3 received our
Compliance Auditing System Manual in early 1988 which we believe
satisfies most of the requirements of an EMS.

The Inspector General stated that escalation of enforcement actions
had not occurred for the 11 Bay facilities chosen for review  (for
Virginia - Waynesboro, L.A. Clarke, and USMC, Quantico).  Following
are the escalations that actually occurred:

L.A. Clarke:

     Board Directive                       November 1976
     No Disch. system implemented          December 1978
     Facility closed, still testing        1979
     Operations resumed                    1980

-------
                                                           Appendix A
                                                           Page 13 of 27
L.A. Clarke  (continued)

     Referred to Attorney General          December 1981
     Referral affirmed by Board            March 1982
     Bill of Complaint filed               April 1982
     Consent Decree entered                June 1982
     Filed for bankruptcy                  March 1983
     2nd Consent Decree(lst still eff.)    July 1983
     Contempt petition to Court            March 1985
     Contempt order entered by Court       May 1985
     Referral to Attorney General          February 1988
     Superfund RI/FS                       March 1988
     Discharge Permit revoked              July 1988

Waynesboro:

     Referral to Attorney General          October 1985
     NMP Consent Decree                    December 1985
     Referral to Attorney General          December 1987
     New, more stringent Cons, decree      April 1988

USMC, Quantico

   VA0028363, Mainside

     Consent Order                         June 1986
     New Consent Order                     December 1987
     Amendment to Consent Order            January 1989

   VA0002151, Industrial Plant

     Consent Order                         January 1989

NOTE:     Federal Law provides that federal facilities are liable
          for only those state civil penalties imposed by the
          State Court to enforce an order or the process of such
          court.

As a matter of interest, the City of Fredericksburg, which is
also a Bay facility, after being issued Consent Orders in 1985
and 1986, was assessed $25,000 in civil penalties in a 1987
Consent Decree.
TOXICS

The State Water Control Board has undertaken an aggressive
program to deal with toxic discharges in Virginia for the past
several years.  As recent as a year ago, the State Water Control
Board adopted one of the first Toxics Regulation in the nation to
provide a consistent and systematic approach to regulating toxic

-------
                                                           J^pendix A
                                                           Page 14 of 21
discharges.  We believe that this is not only consistent with the
requirements of the  Clean Water Act  (CWA), but has gone beyond
such requirements.   We have, as a result, incorporated Toxics
Management Programs  into over 200 permits, to identify and
ultimately reduce and/or eliminate toxics discharges throughout
the State.  The State Water Control Board has also undertaken
recently to convert  all Water Quality Criteria for the protection
of aquatic life to Water Quality Standards as required by the CWA
and prompted by Region III.  It is projected, that barring any
major complications  or law suits, these changes to the Water
Quality Standards would become effective later this year.

While Section 304(1) of the CWA requires specific requirements
relating to the NPDES Permit Program for controlling toxic
substances, we believe that Virginia has met the intent of the
CWA and in fact has  somewhat exceeded the requirements based on
the implementation of the Board's Toxic Regulation.  We have
provided EPA with a  list of waters not expected to meet water
quality criteria for the 126 priority pollutants and have
provided EPA with a  list of those dischargers that we believe
have toxic discharges and are regulated under the requirements of
304(1).  It is the Water Control Board's position that upon
completion of EPA's public notice in October of this year, in
compliance with the  304(1)  regulation, we will move immediately
to modify those permits that have been agreed upon to incorporate
Individual Control Strategies (ICS).   EPA had the benefit of
passing final judgement on the State's permit lists based on a
final 304(1)  regulation whereas the States were having to operate
under a proposed regulation which has since changed.  Again, it
is Virginia's intent to comply with the mandate of the CWA to
incorporate ICSs in permittees' permits by February of 1990.  The
ICS as required by the CWA will require compliance by June of
1992.
WATER QUALITY STANDARDS

I must respectfully and strongly disagree with the Inspector
General's assertion that the failure to adopt Water Quality
Standards to deal with toxics in a timely manner hinders the
permit program and delays toxic controls for the Bay.  This is
definitly not the case since Virginia has been in the forefront
for years in dealing with toxic discharges and, as stated before
is one of only a few states that has a Toxics Regulation to
specifically and consistently deal with toxic pollutants.  This
Regulation, that was endorsed by EPA at the time of its adoption,
goes beyond the CWA's requirement of having Water Quality
Standards to control pollutants by requiring all discharges to be
neither acutely nor chronically toxic.  As a matter of fact, this
document has been presented by EPA as a model for other States to

-------
                                                           Appendix A
                                                           Page 15 of 27
use in developing toxics management strategies.  If just the CWA
strategy were followed, toxicity might not be prevented due to
the additive effects of multiple compounds which are not taken
into account by the CWA.
SUMMARY

We do not believe that this document is representative of
Virginia's progress in enforcement, regulating toxic discharges,
nor adopting Water Quality Standards.  There is almost a
pervasive attitude that the only way to secure compliance is
through punishment and the assessing of massive penalties.  We
believe that Virginia has taken a very adequate approach to
combining enforcement actions with less punitive measures.  While
EPA and the State Water Control Board may not agree on the
approach to toxics control and standards adoption, Virginia has
not ignored the situation and is in fact ahead of most states in
dealing with its toxics discharges.  We will continue to
implement the Toxics Regulation through our permits and where
toxicity is found, remove or eliminate the toxic impact that is
seen on State waters.

-------
                                   COMMONWEALTH OF  PENNSYLVANIA
                                DEPARTMENT OF ENVIRONMENTAL RESOURCES
                                           Post Office Box 2063
                                      Harrisburg, Pennsylvania 17120
                                               July 20, 1989
                                                                           717-787-5027
 Alvin R. Morris, Director (3WMOO)
 Water Management Division
 U.S. Environmental Protection Agency
 Region 3
 841 Chestnut Building
 Philadelphia, PA  19107

 Res   Draft Report of Audit in Management
      of the Chesapeake Bay Program Point
      Source/Pollution Program

 Dear Dr^$orrist

           Thank you for the opportunity to review the subject draft audit report. Regarding
 enforcement, we acknowledge it occasionally takes longer to resolve cases than we would prefer.
 However, our enforcement program has become more active in recent years. Our implementation
 of the NMP Program  has resulted in a substantial number of effective compliance actions against
 municipalities.  Most of  those NMP municipalities are in compliance with their NPDES Permit
 limits and many of the remaining cases are under some  enforcement schedule. While we agree
 that our program can be improved, we do not agree that it is nearly as poor as implied by the
 report.

           We do not agree that the issuance of more unilateral orders is the solution to the
 perceived lack of enforcement. We have found that, in the long run, our Consent Order and
 Agreements are more effective in gaining compliance where a substantial commitment is required
 by the violator. The negotiation of a Consent Order and Agreement is often more time intensive
 than issuing an order, but the violator waives his right to appeal which may save considerable time
later.  In addition, penalties (both upfront and stipulated) are associated with the Consent Order
and Agreements, while no penalties are directly imposed by orders.

           We agree  the issuance of orders can substantially reduce the time required to address
emergency or short-term compliance problems. To improve our ability to respond quickly to resolve
or prevent pollution incidents, the Bureau of Water Quality Management is currently preparing to
give our inspectors the authority to issue orders in  the field. We anticipate this program becoming
effective in the fall of 1989. In addition, the Bureau has recently finalized a new guidance related
 to the calculation of penalties for effluent violations. This methodology will significantly increase
 the amount of penalties over what has previously been assessed.

           The Department has developed a good working relationship with the EPA Region in
enforcement staff. We have taken a number of joint actions in the past and continue to cooperate
 with ongoing cases. The Region III staff has been very responsive to our requests for assistance on
specific enforcement actions and we look forward to continuing the teamwork approach in meeting
the goals and commitments of both our agencies.

-------
                                                                             Appendix A
                                                                             Page 17  of 27
Alvin R. Morris, Director (3WMOO)
- 2-
July 20, 1989
           Page 21 of the draft report indicates "3. Pennsylvania did not adopt water quality
standards for toxic pollutants as required by CWA". The Pennsylvania Environmental Quality
Board approved water quality standards, which include toxics provisions, on November 15,1988.
These standards were published final in the Pennsylvania Bulletin on March 11,1989, and are in
effect.

           Also on Page 21, the report states that Pennsylvania has not submitted a complete
304(1) list.  A revised list was submitted to EPA Region III on May 5,1989.  The list was approved
by a June 2, 1989,  letter from the EPA Region III Administrator. This list does include the
60 dischargers with Toxic Reduction Evaluation requirements.  The discussion of Pennsylvania's
Toxics Management Strategy is misleading. The strategy does provide for enforceable permit
limits for toxics.  Only where technology does not exist to meet calculated water quality based
limits is the provision allowed for a time extension  to meet these limits. Under this provision, the
discharger is required to report annually on the status of technology and application of appropriate
technology to comply with the calculated limits.

           Thank you for the opportunity to comment on this draft audit report.  If you have any
questions regarding these comments, please contact Cedric Karper of my staff at 717-787-8184.

                                                Sincerely,
                                                Cichard M. Boar dm an
                                                Director
                                                Office of Environmental Management

-------
                                                                        Appendix A
                                                                        Page  18  of 27
            DEPARTMENT  OF  THE  ENVIRONMENT
                      2500 Broening Highway, Baltimore, Maryland  21224
                               Area Code 301  • 631-3567
   William Donald Schaefer
        Governor
                                      August 21, 1989
Martin W. Walsh, Jr.
    Secretary
Mr. P. Ronald Gandolfo
Divisional  Inspector General
Office of  Inspector General
401 M Street, SW
Washington, DC  20460

Dear Mr. Gandolfo:

     Thank you for the  opportunity  to comment  on the Draft Audit Report on
the Chesapeake Bay Point  Source  Pollution  Program.   The Maryland Department
of the Environment (MDE)  has  a more positive view of sewage treatment plant
compliance than that which  is presented  in the audit report.

     We are disappointed  in that it seems  to focus  only on problems.  It
represents a single point of  time,  and generalizes  compliance based upon
the results of one quarter, rather  than  reflecting  the progress Maryland
has made in increasing  compliance over the past several years.  It also
tends to simplify the difficulty of coordinating enforcement activities
between two agencies located  in  different  cities,  and is apparently
oblivious to the circumstances which hinder effective wastewater treatment
and aggressive enforcement.

     Maryland's compliance rate  has improved steadily since 1985,  from 50%
that year to 58% in 1986, 68% in 1987, and 77% in 1988.  Based upon ongoing
plant upgrades, our anticipated  compliance rate for 1989 is 83%.  These
numbers illustrate the  progress  toward complete compliance in Maryland.
This improvement is all the more remarkable given the increasingly
stringent permit limits (primarily  for nitrogen and phosphorus) and
increased sewage flows.

     Several of the problems  recognized  in the audit have since been
resolved.  A new Memorandum of Agreement between MDE and EPA was finalized
on May 18,  1989.  Similarly an Enforcement Management Strategy has been
drafted and revised, and  MDE  hopes  to get  EPA  approval of the strategy this
fiscal year.

-------
                                                                        Appendix A
                                                                        Page 19 of 27
Mr. P. Ronald Gandolfo
Page 2
     If noncompliance rates in the region remain constant during the second
calendar quarter of 1989, Maryland's projected significant noncompliance
rate of 6.5% will be the lowest in the region except for that of Virginia.
With EPA's statistical analyses lagging one quarter, these results will not
show up until the first quarter of 1990,

     MDE remains confident in the results of its enforcement program, and
hopes that the final Audit Report on the Chesapeake Bay Point Source
Pollution Program will reflect overall compliance, rather than a point in
time.  More specific comments are attached.  If you have any questions,
please call me at (301) 631-3567, or Merrylin Zaw-Mon,  Deputy Director, at
(301) 631-3574.

                                          Sincerely,
                                          J. L. Hearn, Director
                                          Water Management Administration
JLH:dsw

-------
                                                                        Appendix A
                                                                        Page 20 of 27
                       Response to Draft Audit Report

     The Office of  the  Inspector General's draft audit report on the
Chesapeake  Bay Point  Source  Pollution  Program evaluated the progress of EPA
Region 3 and the  states  in enforcing the National Pollutant Discharge
Elimination System  permits and  reducing toxics entering the Bay.  The audit
reviewed the agreements  between EPA and the states for enforcing the Clean
Water Act,  the commitments made by the states in their internal management
strategies, and the compliance  records of treatment plants in the region.
The efficacy of the enforcement programs was evaluated through a detailed
study of a  random group  of noncomplying sewage treatment plants.

     While  the audit  identifies some program weaknesses that are being
addressed,  it sometimes  simplifies the difficulty of coordinating
enforcement activities between  two agencies located in different cities and
is oblivious to the circumstances which hinder effective wastewater
treatment and aggressive enforcement.

     The Memorandum of Agreement between the EPA and the Maryland
Department  of the Environment  (MOE) was originally completed in 1974 when
the NPDES program was delegated to the State of Maryland.  This agreement
reflected the Clean Water Act requirements in effect at the time it was
written.  EPA and MDE began  revising the agreement in 1987, and worked out
the details through written  correspondence and telephone communications.
The memorandum was  a  lesser  priority than was maximizing NPDES compliance.
Many technical and  programmatic conflicts were resolved before the new
agreement was finalized  on May  18, 1989.  (Recommendation #1 of audit
report)

     Similarly, the EPA  asked MDE to develop an Enforcement Management
Strategy (EMS) in 1987.  A draft was sent to EPA Region 3 in March of that
year, and EPA made  comments  and requested a revision.  The EMS was
rewritten in the  fall of 1988,  and again in the summer of 1989, and the MDE
hopes to get EPA  approval of the strategy this fiscal year. (Recommendation
12 of audit report)

     The lack of  formal  agreements and written strategies does not signify
a lack of communication  between the EPA and the states.  Rather, such
communication takes place on a weekly basis, with personal meetings every
quarter.  In a context where communication between EPA and MDE was limited,
the lack of written agreements would be a serious problem, but with the
regular contact,   there was no loss in accountability.  The quarterly
meetings between  EPA and MDE include detailed discussions of each facility
in noncompliance.

     The audit compares  the tasks accomplished by MDE with those
established as 106  grant commitments.  While MDE has continued to expand
program activities  in response to federal regulations, grants have not
increased.   The toxics program has been primarily state funded, and
Maryland is now developing toxic regulations based upon a schedule agreed
upon with EPA.


-------
                                                                        Appendix A
                                                                        Page 21 of 27
     The history of enforcement  at  randomly  selected  facilities which were
out of compliance  in March  1988  was  studied  as part of  the  audit.
Facilities chosen  in Maryland were  Frederick City, Freedom  District, and
Pocomoke City.  The analyses of  these problems did not  fully consider the
circumstances causing the permit noncompliances.

     The old Frederick City treatment plant  was hydraulically and
organically overloaded.  The City of Frederick had developed a facilities
plan, held public  meetings, and  revised the  facilities  plan before
January 30, 1984 when the National  Municipal Policy (NMP) went into effect.
Since Frederick was already in the  grants process when  the  NMP was adapted,
it would not have  been fair to impose the NMP requirement of enforcement
regardless of availability  of funding upon the City of  Frederick.

     Pretreatment  was identified as  a problem at Frederick City in the
auditor's report.  Although one  dairy was discharging high-strength high
volume wastewater, the domestic  loading alone in Frederick City was enough
to overload the old treatment plant.  The pollutants discharged by this
dairy and the other much smaller food processors, however, are compatible
with biological secondary treatment, and the new plant  (completed in 1988)
was able to treat  these wastes even  without  industrial  pretreatment and
still meet permit  limits.   In May 1989, the one major dairy came on-line
with a $3,000,000  pretreatment facility and  is now discharging domestic
strength wastes to the sanitary  sewer.  Attachment #1 shows industrial
loadings for biochemical oxygen  demand (BOD) before and after pretreatment
compared to the design loading of the new plant.  As is evident, industrial
loadings contribute only a small  percentage of the total incoming BOD to
the City's new plant.

     The Pocomoke  City treatment plant did not meet its permit limit for
chlorine.  The chlorine limit in effect in Maryland is  the result of a 1981
state law and is not a national  standard.  The permit was not written for a
water quality limited discharge.  Thus Pocomoke City was not in violation
of the National Municipal Policy.   Industrial users were suggested as a
source of funding, but the contribution of industrial  waste to the facility
had no effect upon the dechlorination requirement.   The facility was
awarded a dechlorination grant in 1988 and is now in compliance with all
effluent limits.

     The Freedom District treatment  plant did not meet  all the applicable
permit limits due  to limitations  of  the treatment plant.  Consent Orders in
1987 and 1988 recognized operational modifications  which could improve
plant performance.  These improvements were pursued but did not bring the
plant into compliance until  mid  1989.  State funding was requested in
fiscal  years 1986  and 1987 to finance the plant upgrade, but funding was
not made available by the legislature.  State funding was approved in
fiscal  year 1989,   and the upgrade is now under design.

     The audit report notes that  the use of interim limits does not
actually reduce the quantity of  pollutants discharged.  The purpose of
interim limits is  to ensure that the facility is operated to produce the
best possible effluent quality pending an upgrade.   This is a realistic

-------
                                                                        appendix A
                                                                        Page 22 of 27
approach to the problem of noncompliance at publicly owned sewage treatment
plants.

     Noncompliances at publicly owned treatment plants are not caused by
disregard for the Clean Water Act, but by a lack of funding for treatment
plant upgrades.  Public utilities must compete with many other services in
local budgets and upgrades often present a serious financial hardship to
small towns.  The imposition of fines only serves to increase the already
severe budgeting problem.  Closing down a municipal wastewater facility is
not an option.  MDE has intensified its assistance to communities
previously granted state and federal funding to ensure that the needed
facilities are built within established schedules.  Communities are
encourage to complete upgrades in a timely manner to maximize the value of
available grant funding and minimize economic impact upon the users.

     MDE does use progressive enforcement measures to bring facilities into
compliance with their discharge permits.  (Recommendation #3 of audit
report)  Fines are not considered until several initial actions have been
taken to bring the facility into compliance.  The following steps may be
taken in order, or in cases of severe violations, some steps may be
skipped.

     1. Notice of Violation
     2. Administrative Directive
     3. Consent Order
     4. Complaint, Order and Penalty Assessment
     5. Judicial Order

Many municipal facilities are strongly influenced by the possibility of
limitations on hook-ups.  Each municipal treatment plant is evaluated
annually to determine whether or not it can adequately treat higher flows.
Limits on growth are called moratoria,  and are imposed as administrative
directives.  They offer a financial incentive to compliance by threatening
to limit future tax revenue.

     Administrative and Judicial Consent and Unilateral Orders continue to
be finalized at a rate of about twenty-two per year.  Stipulated penalties
have been included in all municipal orders written since October, 1988.
The inclusion of stipulated penalties encourages facilities to develop
reasonable compliance schedules and make every effort to meet those
schedules.   Fines are recognized as a potential deterrent and are used
against municipalities as a last resort, such as in the case of the
Baltimore City Back River Treatment Plant which has been assessed a fine of
$88,000.  (Recommendation #4 of audit report)

     The escalating enforcement described above is aggressive, and improved
tracking of plant data and monthly tracking of outstanding orders will make
enforcement actions more timely.  Recent computerization of our tracking
system have made the data more accessible to MDE and EPA personnel.

     MDE continues to enforce pretreatment requirements.  While we prefer
to assist local utilities in enforcement and issue joint enforcement

-------
                                                                        j^ppendix A
                                                                        Page 23 of 27
actions with the utilities when our  involvement  is  requested, we will take
action against treatment plants not  enforcing their own pretreatment
programs.  The pretreatment program  must  allow  facilities a reasonable
amount of time to establish local pretreatment programs, and will become
increasing active in enforcing pretreatment  limits  where municipalities
fail to enforce these  limits  (Recommendation #7  of  audit report).

     More Maryland  treatment  plants  were  in  compliance in 1988 than in any
of the previous years  (Attachment #2).  Compliance  rates were 50% in 1985,
58%  in 1986, 68% in 1987, and 77% in 1988.   The  projected compliance rate
for  1989 based upon construction schedules and current discharge monitoring
reports is 83%.  Non-compliant facilities are under a compliance schedule,
established by MDE  in  an administrative or judicial order.
Maryland has pursued compliance at minor  treatment  plants as well as
majors.  Our rate for  compliance at  minor treatment plants is approximately
equal to that for major treatment plants.  EPA's emphasis on majors has
caused many states  to  stress  compliance at majors at the expense of minor
plants.

     The total pounds  of pollutants  discharged as measured by biochemical
oxygen demand, total suspended solids, total nitrogen, and total phosphorus
have decreased steadily even  with the increase of wastewater flow
associated with an  increased  population in the Chesapeake Bay Region.  The
lower amounts of pollutants discharged are a result of MDE's imposition of
increasingly stringent permit requirements. Attachment #3 shows that flows
have increased from 356 to 389 million gallons per  day while organic matter
has decreased from  83,000 to  71,000  pounds per day  and phosphorus has
decreased from 8800 to 5700 pounds per day.  Thirty two plants currently
have permitted phosphorus limits and three have nitrogen limits.  More
nutrient limits are being phased in  each year.  The Chesapeake Bay
Foundation's report of July 1988 also reports a reduction in pollutants
discharged, with a  10% decrease in solids discharged and a 7% decrease in
organic material accompanying a 4% increase in flow from 1986 to 1987.

     Another stringent limitation imposed by MDE but not required
nationwide is the chlorine limit of <0.1 mg/1.

     Maryland has just reviewed the major facility  list and expanded it to
include 46 facilities with design flows of 1 MGD or greater.   Thus,
Maryland's municipal noncompliance rate was actually 13% in March 1989 and
will  drop to 6.5% (3 of 46)  in July  1989 as the Salisbury treatment  plant
is now in compliance,  Baltimore City has signed a consent order for the
Back River treatment plant,  and Hurlock has been referred to the Attorney
General's office for judicial  action.  Since the beginning of 1989,
Hagerstown, La Plata,  and Piney Point have also come into compliance with
permit limits.
     If noncompliance rates in the region remain constant during the second
calendar quarter of 1989, Maryland's projected significant noncompliance
rate of 6.5% will be the lowest in the region except for Virginia.

-------
                                                                     Appendix A
                                                                     Page 24 of 27
     Of the three facilities still not in compliance, MDE has finalized a
Consent Order with Baltimore City for the Patapsco treatment plant and
referred Aberdeen Proving Grounds to the Attorney General's office for
enforcement. We expect the Aberdeen Proving Grounds situation to be
resolved before October 1, 1989.  This leaves only Cambridge out of
compliance, which is constructing dechlorination facilities and is due to
complete the project by late September.

-------
                                                                              Appendix A

                                                                              Page 25 of 27
                 O)  C
                 c   o
          E

-0-2
     CD
            O'
                 4
                 CO  0)
                 co  £
                                                           O>
                                                          "35
                                                           o>

                                                          Q
                                                          **
                                                           c
                                                           CO
                                                      t     I     I
                                                           £
                                                                      OD
g

CO
UJ
5
O
O
                                                                             d
                                                                             z
                                                                              CO
                                                                              a
                                                                              a
                                                                  mm*

                                                                 I
                                CDOQ  -^
, c
 0)


 y

-------
                                                                     .Appendix A
                                                                     Page 26 of 27
d
oi

|

CO
LLJ
Q
                CD
                O

                CO

               "5.
                E
                o
               O
                co
               CO

               15
                Q.
               'o
 V
 o
 c
.s?
"a
 E
 o
O
0)



O
o.

<0
                      td
                      2
                      >*—
                      o
                        o
                        o
                                                           o>
                                                           00
         o
         00
                            o
                            (O
o    o
"t    CNJ
                                               0)
                                               *-
                                               o
                                               a>

                                               "o

                                               D.
                                                            cd
                                                            5
                                                            *•»
                                                            o

-------
                                                           Page 27 of 27
     CD
     O)

     cd


     o
     CO

     bo
        o
     *- o
     C cvj
     •+-*  c
     _D  co


     O oo
     Q.
     CO
         cd
     (D
     O)


     i
     0)
     CO
e

u

-------
                                                    APPENDIX B

                        REPORT DISTRIBUTION

         Recipient

Office of Inspector General

     Inspector General (A-109)

Region 3

     Regional Administrator (3RAOO)
     Director, Water Management Division (3WMOO)
     Audit Followup Coordinator (3PM60)
     Office of Public Affairs (3PAOO)

Headquarters Offices

     Comptroller (PM-225)
     Agency Followup Official (PM-225), Attn:  Director, Resource
       Management Division
     Associate Administrator for Regional Operations (A-101)
     Office of Congressional Liaison (A-103)
     Office of Public Affairs (A-107)
                                 30

-------