REVIEW OF THE REMEDIAL  INVESTIGATION/FEASIBILITY STUDY

                                  FOR THE

                           IRON HORSE  PARK SITE

|                      NORTH BILLERICA,  MASSACHUSETTS



-------
                    IRON HORSE  PARK  (IHP) SITE
                  NORTH BILLERICA, MASSACHUSETTS


This report was prepared in response to a request from the
Eastern Audit Division for assistance in their review of Region
1's management of the RI/FS program.

I.  BACKGROUND

    Remedial activities at the IHP site began in October 1985 and
    are still underway.   In consideration of the size and
    complexity of the site, EPA is using a phased approach to
    study and determine what cleanup action(s)  may be needed.
    Under this approach,  the site is separated into a number of
    discrete problem areas.  Where possible, the areas are
    studied and decisions on how to clean them up are made
    independently. The cleanup work that is implemented under
    this approach is called an Operable Unit (OU).  A number of
    OUs taken together form the complete site cleanup.  The
    phased approach was selected pursuant to the agency policy
    established in June 1986 and documented in the "Guidance
    Document for Cleanup of Surface Impoundment Sites" for
    limited RIs and the complementary guidance for Operable Unit-
    Feasibility Study delineated in "Cleanup of Surface Tank and
    Drum Sites"(EPA 1985).

II. OBJECTIVE OF REVIEW

    The objective of our review was 1) to determine if the
    project cost increases during the RI/FS phase are
    attributable to EPA's decision to expand the work plan
    activities for the RI/FS, and 2) to determine if the
    contractor used due professional care in preparing the Final
    Work Plan in 1985 and its amendments which resulted in the
    increase from $610,837 (original budget) to $1,326,000 (in
    1987).

III. SCOPE OF REVIEW

    In conducting this review, we examined selected project
    files, discussed the program directives with the EPA project
    officer and evaluated the various activities performed by
    Camp Dresser & McKee, Inc.(COM), EPA's contractor, including
    some of the project deliverables.

IV. PROGRAM OVERVIEW

    Prior to initiation of remedial activities, once a site of an
    uncontrolled release of hazardous substance is identified a
    preliminary assessment (PA) is conducted by EPA or the State.
    The PA involves review of any available information and

-------
    documents on the site to determine if further action is
    required.  If a potential problem does exist, EPA or the
    State conducts a site inspection (SI).  Typically, the SI
    involves collecting information about the site, e.g., types
    of soil on site, streams or rivers on or near the site,
    number of people in the area, weather conditions, and other
    pertinent information.  Samples of wastes, soil, well water,
    river water, and air are sometimes collected to determine
    what hazardous substances are on the site.  Samples are also
    taken nearby to determine if the substances have traveled or
    migrated away from the site.  These measures are referred to
    as pre-remedial activities.

    The remedial action response at a- site begins with the
    remedial investigation (RI) and feasibility study (FS).  The
    RI is designed to produce information needed to identify,
    select, and evaluate remedial action alternatives in the FS
    based on technological, public health, institutional, cost
    and environmental factors. The ultimate goal is the selection
    of a "cost-effective" remedial alternative which mitigates
    threats to, and provides protection of, public health,
    welfare, and the environment, consistent with the National
    Contingency Plan (NCP).  Typically the RI/FS addresses data
    collection and site characterization from the perspective of
    contaminant migration pathways.  Once pathways are
    established and human and environmental receptors are
    identified, further data collection efforts are directed
    toward evaluating the potential impact upon receptors and in
    evaluating potential remedial technologies and alternatives.

V.  SITE DESCRIPTION

    The Iron Horse Park site occupies an area of approximately
    1300 acres in North Billerica, Massachusetts near the
    Tewksbury town line 20 miles northwest of Boston.  It
    consists of several different facilities including industries
    and landfills, both active and inactive, as listed below:

      Johns-Manville Products Corporation
      Johns-Manville Asbestos Landfill (inactive)
      General Latex and Chemical Corporation
      Shaffer Landfill (inactive)
      Reclamation Services, Inc. Landfill (inactive)
      Boston & Maine Corporation (B&M)
      Massachusetts Bay Transportation Authority (MBTA)
    These facilities, except for the Shaffer Landfill, are
    included within an area bordered by the B&M Railroad tracks
    to the north, High Street to the west, Salem Road to the
    south, and Gray Street to the east.  A site map (Figure 1-1)
    is attached.

-------
With the exception of General Latex and Chemical Corporation,
most of the existing facilities currently discharge domestic
wastewater and drainage system waters into the unlined sewage
lagoon operated by the B&M Corp.  These discharges into the
lagoon were to have been terminated by the end of 1988.  The
remaining facilities on the IHP site are either inactive or *
assumed to be within existing discharge permits and continue
daily operations.  The site has a long history of activities
that have resulted in contamination of soils, ground water,
surface water and air.  Wastes disposed at the site included
asbestos, PCBs, organic solvents, waste oils, and a host of
organic and inorganic chemicals.  Now much of the hazardous
waste is disposed of offsite at RCRA permitted facilities.

Significant features of the site and the surrounding area
include the following:

*   The site is surrounded by densely populated residential
    areas of Billerica and Tewksbury with an estimated total
    of 18,256 persons living within a one mile radius and a
    total of 61,000 people within a 3 mile radius.

*   Most of the IHP site is classified as floodplain.  It is
    situated within two major drainage basins, the Shawsheen
    River basin to the east and the Concord River basin to
    the west.  There is a potentially critical wetland
    habitat area (along Pond Street) within close proximity
    to the site.

*   The three landfills on site are of particular interest
    due to their proximity and/or contact with significant
    natural resource/wetlands areas.  Shaffer L/F, for
    example, is surrounded by potential surface water
    migration pathways that may act as receptors for
    contamination from the landfill.

*   The area topography is characterized by broad, poorly
    drained lowlands and rounded hills and the immediate area
    is relatively level.  The area receives a mean annual
    precipitation of approximately 43", which is distributed
    evenly throughout the year.

*   The site is generally underlain by Pleistocene stratified
    glacial deposits which comprise an aquifer with an
    average thickness of about 20 feet.  The underlying
    bedrock is reported to range in depth over the site from
    0 to approximately 80 feet and is of variable texture.

-------
    *   The site  is  located in an area with a  high water table,
        where ground water could be encountered at shallow depths
        from 1.4 to 6 feet below ground surface.  The ground water
        generally flows toward the east and north.


VI. FINDINGS

A.  WORK PLAN AND AMENDMENTS

     The Work Plan for conducting an RI/FS at the IHP site was
     submitted in August 1985.  The Final 1985 Work Plan (FWP)
     identified specific technical tasks needed to determine the
     nature and extent of both onsite and offsite contamination.
     The plan proposed that the RI be conducted in two phases (1A
     and IB) to allow flexibility in the investigation based on
     the results of initial data collection.  Phase IB started
     upon completion of Phase 1A in order to provide supplemental
     information where data gaps were found.  Eventually, the
     results of the Phase 1A and IB RI work were to lead to
     preparation of an FS Report for remediation of the IHP site
     problem areas.  This Work Plan was amended several times for
     different purposes, as follows:

     -  Amendment No. 1, initiated in December 1985, to allow
        shifting of funds from Feasibility Study tasks in the
        approved FWP to the well drilling program.  As indicated
        in the submittal from CDM, all the bids received for
        drilling, sampling and well installation were
        substantially higher than the amount originally budgeted
        for the work.  Funding for the FS phase was to be
        restored at a later date by a Work Assignment amendment
        prior to initiation of the FS in 1986.

     -  Amendment No. 2, initiated in May 1986,  to address
        expansion of existing tasks 1, 2, 3 and 4 and revisions
        of tasks 5 and 6 in the 1985 FWP.  CDM indicated that
        additional field and office tasks were needed in order to
        collect and analyze additional data and for management
        and coordination requirements.  Additionally, revision of
        office tasks 7,  8 and 9 was necessary to complete the
        Phase 1A field program.  This amendment required
        additional hours and funds, and EPA approved it in May
        1986.   The amendment to the work assignment was not
        available for review.

     -  Amendment No. 3, initiated in March 1987, to incorporate
        the "phased operable unit" approach to selecting a remedy
        for the IHP site.  The Sewage Lagoons area was selected
        to be OU No.  1,  and the Shaffer Landfill was proposed as
        OU No. 2 to be addressed in future amendments.  This

-------
        amendment served as the Work Plan for the RI/FS for the
        lagoons (i.e., IHP OU-1).   The lagoons,  consisting of two
        active infiltration ponds and one overflow pond, have
        received industrial/hazardous wastes in addition to
        sewage during 60 years of operation.  They were
        identified during the preremedial activities to be a
        potential 'source area1 of contamination.

     -  Amendment No. 4, initiated in May 1987,  to increase the
        subpool funds for the site survey subcontract.  This task
        was budgeted at $25K in the 1985 Work Plan.  However, the
        scope of the survey work was considerably revised
        resulting in doubling the area to be surveyed and hence
        increasing the estimated cost for the survey work by
        $59K.  This cost increase plus contractor's fee was
        delineated on Form 60 attached to the amendment letter.

     -  Amendment No. 5, initiated in June 1987, was directed
        toward the RI/FS efforts related to the Shaffer Landfill,
        designated as Operable Unit no. 2 (OU-2).  This amendment
        included an allowance for final Work Assignment closeout
        costs which applied to the overall IHP site.

B.  SCOPE OF RI PHASE 1A & PHASE IB

     Phase 1A of the RI was conducted by COM from October 1985
     through November 1986 and a report was issued in July 1987.
     This phase covered a broad study of the site and helped pin-
     point potential problem areas.  The purpose of this effort
     was to collect the data needed to characterize the site in
     terms of the nature of contamination, to assess the
     potential risk to public health and environment posed by
     these contaminants, and finally to develop and evaluate
     remedial alternatives for the site.  As a result of this
     work, EPA concluded that the wastewater lagoons and the area
     surrounding them should be studied further.  In March 1987,
     EPA amended the 1985 FWP to do this work.

     Phase IB of the RI was completed and a report was issued in
     January 1988.  It covered the Boston & Maine Wastewater
     Lagoons and fifteen (15) acres of land surrounding the
     lagoons.  The lagoons received domestic and industrial
     wastewater from 5 manufacturing facilities in the IHP
     industrial complex.  In addition to the two active lagoons,
     there is an overflow lagoon that is usually dry and receives
     wastewater only when there is heavy rainfall.

     The FS was completed and a report was issued in May 1988,
     based on the results of the RI.  The cleanup alternatives
     for the lagoon area were limited to addressing the sources
     of contamination (i.e., sediments, soils and sludge).

-------
     Cleanup alternatives for the ground water contamination were
     to be evaluated at a later date, as part of a site-wide
     ground water remedy.

C.  PHASED APPROACH APPLICATION

     In March 1987, the August 1985 work plan was amended to
     encompass a "phased operable unit" approach for selecting a
     remedy for the entire IHP site.  This approach, as pointed
     out in the July 1987 report, was taken "...to remediate the
     site more effectively by establishing priorities for
     potential source areas and then conducting a separate but
     overlapping RI/FS on each designated source area or
     •operable unit1, rather than attempting to remediate all
     source areas simultaneously."

     In other words, the Phase IB work for the overall site RI
     will continue during the implementation of the "phased
     operable unit" approach, as some kinds of contamination
     problems do not fit this approach.

VII. CONCLUSIONS

    l.  Carrying out site remediation under the phased operable
        unit approach is a viable alternative sanctioned by the
        NCP and statutory mandates.  The benefit of this approach
        is that priorities for dealing with complex contamination
        problems can be identified.  The remediation of specific
        and perhaps more critical portions of a site can be
        addressed through the focused, limited RI/FS.  The
        complexity of the IHP site is such that use of the phased
        operable unit approach is appropriate to facilitate
        thorough site investigation and expedited remediation.
        Separating the investigation into phases allows for
        additional data to be collected and evaluated
        sequentially or concurrently which in turn results in
        refinement or redefinition of data collection needs.

    2.  The 1985 Final Work Plan developed by COM was based on
        review of existing information, consistent with the
        agency guidance and under the direction of the EPA
        project manager.  The five amendments to this plan were
        directed toward revising the scope and objectives of the
        site remedial activities.  Each revision, however,
        resulted in an increase in the contractual and/or
        subcontracting pool level of effort.  Although some of
        the additional or revised tasks may have overlapped, this
        is sometimes unavoidable at a site of the complexity of
        IHP.

-------
Cost overruns for remedial activities at Superfund sites
are not uncommon given the magnitude of uncertainties
involved in RI investigations and the lack of available
information.  These uncertainties and problems in
successfully completing RI activities, combined with the
unique contract approach used by the Superfund program,
will often increase the cost of the project work.  The
most costly activity of field investigations is generally
the collection and analysis of environmental samples
which must follow the site specific sampling objectives,
collection methods, chain of custody procedures, and
sample shipment methods.  Considering the magnitude of
environmental sampling and analysis efforts at the IHP
site, the cost of $1.3 million falls within the normal
range.

-------
 . ^•'•v*.;u-
 • i">• < m"» —	.^  - Ihi • ..•„
 .    _
..X ••//'• North
'
 ;,, BUJejica
7:'
;" River
 Pines
-t-%  ^m ^^m^m^-'M
  Miy^Q^r' (.^Y>'*'---:?^S^'^
  ':'•-.-„  iiA-.»."«.K.-#*  •       \^-   --'-•.-.• :';v.;&---<•'
  •-r«>Hr.v=?i---  •-..   .   ;;-^ ..•:..•/..,. ;.-.y\--~-  -V
        - i ni»n ,;T .^ ...  \. <..i-'-   -

      o.' -. \ >i ^•.rA*^1'-*''1/  ^
         X>,.^ •'."'; vfifeiBerica'v^-
^L_.	^I*S&.~:!. J'^TT-V! V .-.7. -


 FROM USGS 8ILLERICA AND
 WILMINGTON QUADRANGLE MAPS
   '°-.V'•"'": •:••'• -,-}.:;A^-^  .  x
/.-::•. •v-;-^..^-- x.-v-. •••;{•:•:• ^-^
• . ..i\:--'  • «- .-,.=•—- Zts1 •': •].'•* . .,-.- •/
• •  - -    - *AV. ., •—  ^r *  J * ^ .*•  i/,  . *\
                                      2000
                                         SCALE IN FEET
                        4000
IRON HORSE PARK
BILLERICA, MA
CAMP DRESSER & McKEE
                                         FIGURE 1-1
                                  SITE LOCATION MAP
                                                       J

-------