Title:
      SUBJECT:   Audit Report No.  E1SFF9-11-0015-0100227
                Review of the  Fiscal Year 1988
                Sviperfund_ReQfi*rt  to Congress

-------
Finding:
 Removal Program                .    . .

     The Annual Report's nationwide and Region 4 and 5 totals  for
 Kemoval Starts and Removal Completions differed slightly from those
 tot-ai J T^L S Printouts provided to us. Nationwide Removal  Starts
        328 in the Annual Report  and  326  in  CERCLIS.  Nationwide

            aioletions totaled 282 in the Annual Report, but only 277
     oval comp R  ion 4  and 5 Removal Starts  totaled 96 in the Annual
   in CBRcLIj'o5 in CERCLIS, while Region 4 and 5 Removal Completions
         a
   Re        in the Annual Report and 85 in CERCLIS.  OSWER officials
   totaled B   these differences to the fact that  the  larger numbers
   actiribit account sites with more than one removal action, whereas
   take i."rTTS  totals equate each site with  only one such action.
   the CERi-^J-3
       of the  47  Removal  Starts  and  11  Removal  Completions  we
       wed, 51 (88 percent) were valid FY88 actions.  However, seven
   rev^h*»  actions  were not valid  FY88 accomplishments.
   of trie
       Four of these seven actions were  not  valid  because,  based on
   fficial Agency definitions,  they should have been  recorded in a
  j-fferent fiscal year.  In fact, one of these four was actually an
  FY87  Removal Start that was counted  in both  FY87 and FY88.

       For the other three actions, the source documentation did not
  show  any evidence that the Agency definitions of a start or a com-
  pletion were  met,  regardless  of  the  fiscal  year involved.   For
  example, the Marietta Mercury Spill site in Region  4  was counted
  as both an EFA-lead first Removal Start and  first Removal Comple-
  tion, even though the definition was never entirely  met in either
  case.  Specifically, EPA  received   notification of   "about a six
  ounce mercury spill"  on the  floor of a personal  residence  in
  Marietta,  Georgia.   The On-Scene Coordinator (OSC) first mobilized
  a contractor to assist in removing the mercury.  The  OSC then went
  to the residence and was  told EPA's assistance  was  not required.
  The resident of the home said that a relative would help in remov-
  ing the mercury.  The  OSC  subsequently stated in  a  memorandum to
  his file that  EPA did not  use the  contractor to do  any removal
  actions  at the residence.  EPA paid $1,000 to mobilize the contrac-
  tor,  even though the contractor's services were  not  needed.

      OSWER Directive 9200.3-1A states  that a  first  Removal  Start
 occurs when removal activity has begun.  Furthermore,  the directive
 states that a  first Removal Completion is counted on  the day the
 on-site  removal action is completed. We believe that the  Marietta
 Mercury  Spill  site does not meet the Agency definition of a Removal
 Start or a Removal Completion.   In addition,  our review of CERCLIS
 revealed that  this site was also counted as a responsible  party-
 lead  subsequent Removal Start and Removal  Completion,  because the
 resident of  the house stated she would clean up  the  mercury.

-------
Finding:
    Remedial Program

        Both the Annual  Report  and the CERCLIS printouts listed  150
    RI/FS Starts  nationwide in FY88.   For the  two  regions which we
    reviewed, CERCLIS reported 42 RI/FS Starts.   We sampled 13 RI/FS
    Starts and determined that all 13 were valid FY88 actions.  .

        We found that the number of Records of Decision (RODs) listed
    in the Annual  Report aa completed nationwide during FY88 was almost
   identical to  CERCLIS.   The Annual  Report  listed 152 and CERCLIS
   listed 154 RODS in F788.   CERCLIS identified 37 RODs for Regions
   4 and 5, and all 15 RODs we reviewed were valid FY88 actions.

        The nationwide totals for Remedial Design (RD) Starts and RA
   Starts contained  in  the Annual  Report agreed with those  on the
   CERCLIS printouts provided to us.  Of the 99 RD Starts during FY88,
    23 were in Regions 4 and 5.  For RA Starts, these regions accounted
    for 18 of the 72 nationwide.
       Qf the 15 RD Starts and 15  RA Starts we  reviewed,  29  (97  per-
        were valid FY88 actions.  The one invalid action was due  to
   ce funds not being obligated on an EPA-lead  site  as of the end  of
   chaa   The definition of an RD Start for this  type  of site  includes
   F t bating the funds.   Figure 2 provides  the detailed results  of
   ob ID and RA Starts review.
   our i*"

-------
Finding:
  pre-Remedial Program

       The nationwide  totals  for  PAs and  Site  Inspections (Sis)
  contained  in the Annual  Report agreed with  those on the CERCLIS
  printouts  provided to us.   Of the 2,884 PAs completed during FY88,
  784 were in  Regions 4 and  5.  For Sis, these regions  completed 413
  of the 1,237 nationwide.

       Of the  44 PA  completions  and  31 SI  completions we reviewed,
  25 (33 percent) were  valid FY88 actions.  Five were not valid FY88
  actions; instead,  according  to official Agency definitions, they
  should have  been recorded in a different fiscal  year.   Three of
  these five were part  of a  batch of  74 PA reports actually input to
  CERCLIS on  November  4,  1988  (FY89),  but which  were erroneously
  recorded as  November 4,  1987 (FY88).

       In addition,  we were  unable to locate  adequate source docu-
  mentation  for 45  (60 percent)  of  the 75 sample  cases.   Specifi-
  cally, in  Region 4  we located all of the reports,  but there was no
  evidence on  the reports, such as a date and signature, to show that
  they had been reviewed and accepted by the Agency. A log was main-
  tained of  approximately 60 percent  of the reports, but it did not
  show review  and acceptance.  Further, some of the  reports themsel-
  ves were undated, and others were very old, in one case dating back
  to FY81.   Region 4  officials  stated that they did  not document the
  review and acceptance on the reports because  they entered the dates
  into a computer database instead.   In Region 5, regional personnel
  could not  locate some of the  reports.  The regional log was spora-
  dically maintained  during  FY88,  and as a  result,  in some cases
  there  were  no entries for these reports documenting  Agency review
  *nd   acceptance.    Figure  4 provides the detailed results of our

-------
Finding:
                   Annual Report  Chapters  3.0 and 4.0  -
                            Additional Coaments

          According  to  OSWER  officials,  CERCUS waa expanded  and
     improved during PY88. However, as previously discussed, our review
     identified concerns with the accuracy of some data in the system.
     Further examples of  system problems include the following!

          --   In  December 1988, we  requested  that Headquarters OSWER
              officials provide us CERCLIS  printouts   from  which  to
              select our  samples  for Regions 4  and 5.   We were "«-ti-
              ally  advised that printouts could not be provided  due

             to "data  discrepancies."   During  January  1989,  these
             officials  apparently  believed  the  discrepancies were
             sufficiently resolved, and  we received   our  printouts.

         —  During our  field work.,  Region  5  officials  advised the
             auditors  that  they considered  the  system to contain
             inaccuracies.

         From our  discussions  and  observations  in  the two  regions,
    ^e believe that inadequate  input controls continue to hamper the
    accuracy and reliability of CERCLIS.   OSWER  officials advised us
    that a work group has  been  formed to review these  input controls
    and make recommendations for   improvements.    In addition,   they
    stated they are conducting monthly data quality audits.

         In addition to our  concern about the accuracy of the data,
    CSRCLIS accomplishments for FY88  differed depending on the date of
    the printout.  For example, we obtained  three different figures for
    Removal starts in Region 4.   A Headquarters  CERCLIS report dated
    October 19,  1988, listed 62; the draft Annual Report dated February
    23, 1989, listed 67?  and a  Region 4  CERCLIS  printout  dated March
    14, 1989, listed 65.                '

         OSWER  Directive   9200.3-1A  established  a cut-off  date  of
    October  17,  1988,  for producing  final  quarter  accomplishments
    reports.   However,  the regions did not  adhere to the cut-off date
    and continued  to input information into CERCLIS months after the
    end of the fiscal year.  OSWER officials  stated that for purposes
    of  completeness,  the  Agency wants to  get  all accomplishments into
    CERCLIS,  .regardless of lateness.   Nevertheless, since  the CERCLIS
    runs used for  the Annual Report  were generated shortly after the
    cut-off date,  and since the regions continued to enter accomplish-
    ments into the system, the Annual Report may be understating some
    Agency accomplishments.

         The  reader should understand that  in some instances,  activi-
    ties conducted at a site are claimed  in multiple categories,  i.e.
    both as Removals  and  Remedial Actions.  These same  activities are
    apparently considered  to  meet more  than  one  Agency  definition.
    For example, at the Region 4 Newport  Dump site, the documentation
    in  the files stated  that  "the  remedial  action  was initiated on
    July 2,  1987 and  completed on October 31, 1987."  Yet  the CERCLIS
    printouts we received  indicated  that not one, but three  actions
    occurred  on October 30, 1987:   a Removal Completion;  a  first  RA
    Completion; and a final RA Completion.  Some Agency officials have
    devised the term  "removials" to apply to these cases; OI6 auditors
    in  Region 4  have  initiated an audit of  this  practice.

-------
 Finding:
                    Annual Report Chapter 5.0 -
               The National Priorities List Of Sites

      The Annual  Report  listed five  sites  deleted  from . the  NPL
 nationwide in FY88.  We  obtained documentation  from Headquarters
 which verified that the Agency deleted  these  five  sites  from the
 NPL.   Two of  the  sites  deleted were  in Region  4,  while  Region 5
 did not  have  any sites deleted.  We did not do any further work in
 Region 4 validating the completion dates for the  two sites deleted.
   Finding:


                     Annual Report Chapter 6.0 -
                   Enforcement Program Activities

       We reviewed four categories of enforcement  activities  dis-
  cussed in the Annual Report:  Administrative Orders (AOs); RI/FS
  Settlements;  RD/RA Settlements;  and Referrals.  In most cases, the
  nationwide CERCLIS totals provided  to us agreed with  the totals
  shown in  the Annual Report.  The  only instance in which the nation-
  wide totals did  not  agree was  in the AO category.  The CERCLIS
  printouts showed 202 Unilateral/Administrative Orders,  while the
  Annual Report contained 207.

       For  our  samples  of cases  selected in each activity category,
  we were able  to locate all appropriate source documents and verify
  that the  actions  occurred during FY88, as claimed.   Figure 5 out-
  lines the number  of sample cases reviewed.
    Finding:
                    Annual Report Chapter 11.0-
         Technology-Related Research And Development

     We reviewed the information presented in the Annual Report on
the SITE Program.  Concurrent with our review of  the Annual Report,
the OIG was conducting a  survey of the SITE Program.  To determine
if the information presented on the SITE Program was reasonable and
accurate, we asked the auditors working  on the SITE Program survey
to analyze this chapter.  Based on  their review,  we believe that
the information presented on the SITE Program is generally reason-
able and accurate.                                        >

-------
Performance Audits

-------
Title:
    SUBJECT:  Audit Report E1SJF9-05-0274-0100207
              Review of. Superf und Cost Recovery Accounts
              Receivable Establishment and Collection

-------
Finding:
    1.    Accounts Receivable Need  To  Be  Recorded

    Neither Headquarters nor the regions timely recorded accounts
    receivable  on the financial records  of  the Agency.   For FT 1989,
    $5.3  million of  $5.9 million (90  percent)  of the payments  we
    reviewed were not timely recorded as accounts receivable.   Thus,
    the Agency's control over monies  owed to the Superfund Trust fund
    was ineffective.   Because receivables were not recorded, the
    Agency  was  not aware of what payments were due the  Superfund
    Trust Fund.   As  a result, a payment  might  be diverted,  lost, or
    not paid without anyone being  aware  of  it.   This also results  in
    late  payments with a resulting loss  of  the applicable interest as
    discussed in Finding Number 2.

    The Agency  was also not meeting internal control standards which
    require that significant events be promptly recorded and properly
    classified.   The failure to record accounts receivable for
    amounts due to the Superfund Trust Fund is a material weakness in
    internal controls.

    The FY  1989  Agency Operating Guidance stated that the success  of
    collecting  cost  recovery payments depends  on being  sure case
    closing information is  immediately sent to the regional financial
    offices.  This ensures  that collections can be properly recorded
    and receivable amounts  can  be  accurately reported to management.
    We  found that accounts  receivable were  not recorded becauses   (a)
    internal controls were  not  established  for forwarding settlement
    documents to the Financial  Management Office, (b) judicial orders
    were  not promptly obtained  from the  Department of Justice,  and
    (c) the Financial, Management Office  did not timely  record
    accounts receivable on  the  financial records when settlement
    documents were received prior  to payment.   In addition,  the
    regions  did  not  establish routine procedures to regularly
    reconcile Superfund and Office of Regional Counsel  records  with
    the financial records.

     In response to  our draft report  recommendations, the Assistant
     Administrator for Administration and Resources Management
     outlined several measures  to  strengthen the control over  accounts
     receivable.  He also stated that all regions will  be provided a
     copy of the final report.   Each  region will be requested  to
     continue to strengthen procedures for  internal controls over
     Superfund  accounts receivable.  The actions outlined by the
     Assistant Administrator, when implemented, will substantially
     correct the deficiencies cited in our  draft report.

     We recommend that the  Deputy  Administrator ensure  that the
     Assistant Administrators for  (a) Administration and Resources
     Management,  (b)  Solid  Waste and  Emergency Response, and (c)
     Enforcement and  Compliance Monitoring, the General Counsel, and-
     the Regional Administrators work together to complete  the  planned
     corrective  actions.

-------
Reconunendation(s):
        We recommend that the Deputy Administrator ensure that the
        Assistant Administrators for (1) Administration and Resources
        Management, (2) Solid Waste and Emergency Response, and  (3.)
        Enforcement and Compliance Monitoring, the General Counsel, and
        the Regional Administrators work together to complete the planned
        corrective actions.

        We also recommend that the Deputy Administrator take appropriate
        action to ensure that Regional Administrators and Offices of
        Regional Counsel reconcile their, records to ensure that  cost
        recovery amounts due in the past have been collected.  Where cost
        recovery amounts have not been collected, the amount due must be
        recorded as an account receivable and appropriate action taken
        for collection.  Further, the Financial Management office should
        notify the Regional Administrator when settlement documents are •
        not provided timely for appropriate corrective action.
                                        . '           •
        In addition, we recommend that the Deputy Administrator  ensure
        that the Assistant Administrator for Administration and  Resources
        Management provide guidance on when amounts owed, particularly
        when the amount in under appeal or in litigation, should be
        recorded as accounts receivable.

-------
Finding:


 '  2.    Promot Action Needed To Collect Amounts Owed

   Neither Headquarters nor the regions were promptly collecting
   cost recovery amounts owed to the Superfund Trust Fund.   This
   resulted from (a)  delays in sending accounting data to
 •  responsible parties, (b) late payment of amounts due,  (c) delays
   due to responsible party requests for further documentation
   and/or dispute of  cost billed, and (d) delays in notifying
   responsible parties of the effective date.  These conditions
   existed primarily  because (a) the regions did not have a system
   for tracking when  accounting data were needed and (b)  consistent
   action was not taken to ensure prompt collection of payments.
   Delays in collecting amounts owed resulted in lost interest to
   the Superfund Trust Fund of $103,856.

   Of  the 55 settlement documents reviewed, we found 22 cases (40
   percent)  where collection of amounts owed was delayed.  The U.S.
   Treasury Department currently invests  Superfund monies in 52-week
   U.S.  Treasury MK Bills.   When cost recovery amounts are not
   promptly collected, the Superfund Trust Fund loses the interest
   which would have accrued.

   In  response to our draft report recommendation, the Assistant
   Administrator for  Administration and Resources Management stated
   that guidance for  Monitoring and Collecting Oversight
   Reimbursement was  distributed to the regions on February 20,
   1990.   Also,  review procedures will be established to  ensure that
   oversight billings are promptly issued.  The actions outlined by
   the Assistant Administrator, when implemented, will substantially
   correct the deficiencies cited in our draft report.

   We  recommend that  the Deputy Administrator ensure that the
   Assistant Administrators for (a) Administration and Resources  .
   Management,  (b) Solid waste and Emergency Response, and (c)

  Enforcement and Compliance Monitoring,  the General  Counsel, and
  the Regional Administrators work together to  complete  the planned
  corrective actions.

-------
Recommendation(s):
     We recommended in our draft report: that  the Assistant
     Administrator for Administration and Resources Management take
     appropriate  action to:

       1. Coordinate.with the Assistant Administrator for Solid Waste
          and Emergency Response to require the Office of Waste
          Programs Enforcement to complete and implement the guidance
          on tracking  and collecting reimbursement of oversight costs.

       2. Work with the Deputy Administrator  and coordinate with the
          Assistant Administrator for Solid Waste and Emergency
          Response to:
                                                     i
            a. Require each EPA Region to provide formal assurance
               that the guidance on tracking  and collecting
               reimbursement of oversight costs has been fully
               implemented and procedures have been established to
               ensure  that oversight billings are promptly sent to
               responsible parties.

            b. Include,  .as part' of the annual Headquarters review of
               regional programs, a determination of whether the
               procedures and controls have been implemented and are
               adequate to ensure that oversight billings are promptly
               sent to  responsible parties.

          The reason we asked that the Assistant Administrator for
          Administration and Resources Management work with the Deputy
          Administrator is because we recognize that senior program
          officials  do  not have line authority over regional offices.


      3.  Work with the Deputy Administrator,  and coordinate with the
         General Counsel and the Assistant Administrators  for Solid
         Waste and Emergency Response and Enforcement and  Compliance
         Monitoring, tor

           a.  Require that all administrative and judicial orders and
              decrees include a statement that interest will  accrue
              from the due date when disputed costs in oversight
              billings are found to be payable.

           b.  Require that oversight billings a statement  that
              interest will accrue from the due date if disputed
              costs are  found to be payable.

-------
Title:
          SUBJECT:  Audit Report No. E1SJF9-05-0274-01Q0172
                    Review of Superfund Cost  Recovery Accounts
                    Receivable Establishment  and Collection

-------
Finding:

   i.   Accounts Receivable Meed To Be Consistently Recorded

   For 9 of 14 settlement documents we reviewed, neither
   Headquarters nor Region 3 were consistently and promptly
   recording accounts receivable (about $3.1 million) on the
   Agency's financial records.  Thu», the Agency's control over
   monies owed to the Superfund Trust Fund was ineffective.  Because
   receivables were not recorded, the Agency was not aware of all
   payments which were due the Superfund Trust Fund.  As a result, a
   payment might be diverted, lost, or not paid without anyone being
   aware of it.


 The  Agency was also not meeting internal control standards which
 require that significant events be promptly recorded.and properly
 classified.  The failure to record a receivable for amounts due
 to the Superfund Trust Fund is a material weakness in internal
 controls.

The  FY 1989 Agency Operating Guidance stated that the success of
collecting cost recovery payments depends on being sure that case
closing information is immediately sent to the regional financial
offices.  This ensures that the collections can be recorded
properly and receivable amounts can be accurately reported to
management.  Accounts receivable were not consistently recorded
in Region 3 because!  (a) the Office of Regional Counsel did not
timely forward settlement documents to the Financial Management
Office in all cases, and (b) there was no assurance that
Financial Management Office received settlement documents timely.

In response to our draft report, the Regional Administrator
stated that he believed the finding was overstated because it
includes those actions that Headquarters was responsible for
prior to FY 1989.  If the actions prior to FY 1989 are eliminated
from the review, no material weakness in Region 3's internal
controls would be found.  The Region believed that an internal
control review is not justified because existing procedures
adequately insure the recording and recovery of all Trust Fund
receivables.

 notwithstanding the comments  made by the Region,  we are still of
 the opinion that the existing procedures were not adequately
 implemented to ensure that all amounts due for Superfund cost
 recovery are recorded as accounts receivable.  We recognize that
 the Headquarters Financial Management Division, and not Region 3,
 was responsible for recording accounts receivable and ensuring
 payments were collected prior to FY 1989.  However, for each year
 we reviewed,  Region 3 was responsible for all other activities,
 including forwarding settlement documents to financial
 management.   As stated in our report, we found that (a)
 settlement documents were not consistently forwarded to the
 Financial Management Office and (b) only one settlement document
 was date stamped by the Financial Management Office as
 verification of when it was received.

 We agree that Region 3's procedures, when consistently followed,
 are adequate to ensure the recording and recovery of all
 Superfund Trust Fund receivables.  In our opinion, the Region's
 inconsistent implementation of its procedures is a material
 weakness in internal controls because it significantly weakens
 safeguards against waste,  loss, unauthorized use or
misappropriation of  funds.

-------
 we  i.c'c.>ww»'*t5C?  i'^s  Regional  Administrator,  Region 3,  takes
 appropriate action to direct the Office of  Regional Counsel,  tne
 Hazardous Waste Management Division,  and  the Financial Management
 Office to ensure  that (a)  settlement  documents  are  timely
 forwarded to  the  Financial Management Office and (b) Office of
Regional Counsel's tracking system is regularly reconciled with
the financial management system.   Also, an  alternative internal
control review should be conducted during FT 1990 to ensure
receivables are promptly recorded on  the  financial  records.

-------
Recommendation(s): .
    We recommend that the  Regional Administrator, Region  3,  take
    appropriate action tot

      1. Direct the  Office of Regional Counsel,  the Hazardous  Waste
    N    Management  Division, and the Financial  Management Office  to
         ensure that (a) settlement documents  are timely  forwarded to
         the  Financial Management Office and (b) Office of Regional
         Counsel's tracking  system is regularly  reconciled with  the
         financial records.

      2. Direct the  Financial Management Office  to ensure that
         settlement  documents are date stamped as verification of
         receipt.
                !
      3. Perform an  alternative  internal control review during FY
         1990 to determine whether the procedures are being  followed
         to ensure that receivables are promptly recorded on the
         financial records.

-------
Finding:
     2.    Prompt Action Needed To Collect Amounts Owed

     Region 3  was not promptly collecting cost recovery amounts owed
     to  the Superfund Trust Fund because of (a) delays in sending
     accounting data to responsible parties,  (b) late payment of
     amounts due, and (c)  delays in notifying responsible parties.
     These conditions existed primarily because the enforcement
     personnel in the Superfund Remedial and Removal Branches had not
     reported  all oversight cases for billing to the CERCLA Cost
     Recovery  Section.   Delays in collecting amounts owed resulted  in
     lost interest to the  Superfund Trust Fund of $11,553.

     Of  the 14 settlement  documents reviewed, we found 6 cases (43
     percent)  where collection of amounts owed was delayed.  The U.S.
     Treasury  Department currently invests Superfund monies in 52-week
     U.S.  Treasury MK Bills.  When cost recovery amounts are not
     promptly  collected, the Superfund Trust Fund loses the interest
     which would have accrued.

     In  response to our draft report, the Regional Administrator
     stated that the Office of Regional Counsel, the Hazardous Waste
     Management Division and the Office of the Comptroller developed
     written procedures for billing oversight costs.  The procedures
     will be reviewed and  finalized during FT 1990.  Also, the
     Comprehensive Environmental Response and Liability Information
     System (CERCLIS) will track oversight billings and ensure that
     the bills are issued  timely.

     The actions planned by the Region, when properly implemented,
     will substantially correct the deficiencies cited in this
     finding.   We recommend that the Regional Administrator ensure
     regional  officials complete their planned actions.

-------
Reconunendation(s) :
we recommended that the  Regional Administrator,  Region 3,  require
the:

 1.  Hazardous Waste Management Division,  the Office of Regional
     Counsel, and the  Financial Management Section to complete
     and implement procedures  for  billing  oversight costs.

 2.  Hazardous Haste Management Division to establish a tracking
     system to (1) identify all orders  and decrees which require
     oversight billings  and (2) promptly issue oversight
     billings.

-------
Title:
   SUBJECT:  Audit Report Mo. E1SJF9-05-0274-0100152
             Review of Superfund Cost Recovery Accounts
             Receivable Establishment and Collection

-------
  ending:
    1.  Accounts Receivable Used To  Be* Recorded

    For all 21 settlement documents  we reviewed, neither Headquarters
    nor Region. 4 promptly or accurately recorded accounts receivables
    amounting to about $2.6 million on the  financial records of the
    Agency.  Thus, the Agency's  control over monies owed to the
    Superfund Trust Fund was ineffective.   Because receivables were
    not recorded, the Agency was not aware  of what payments were due
    the Superfund Trust Fund. As a result, a payment might be
    diverted, lost, ox not paid  without anyone being aware of it.
    This also results in late payments with resulting loss of
    applicable interest as discussed in Finding  Number  2.

    The Agency was also not meeting internal control standards which
    require that significant events be promptly  recorded and properly
    classified.  The failure to  record a receivable for amounts due
    to the Superfund Trust Fund  is a material weaJcness  in internal
    controls.


Recommendation(s) :

    We recommended that the Region 4 Regional Administrator take
    appropriate action toi

     1.   Direct the applicable offices to develop a Memorandum of
         Understanding to ensure that thei

          a.   Waste Management Division promptly forwards settlement
              documents to the Financial Management Unit.

          b.   Financial Management unit promptly and accurately
              records accounts receivable for all cost  recovery
              amounts owed.

          c.   Office of Regional Counsel works with Department of
              Justice to timely  obtain orders and decrees.

          d.   Financial Management Unit, Office of Regional Counsel,
              and waste Management Division establish and implement
              procedures to regularly reconcile Waste Management
              Division and Office of Regional  Counsel records with
              fittacial management system and to exchange information
              oa~ftny changes in  amounts due and on the status of
              debts, including cases concluded by Department of
              Justice.

          e.   Financial Management Unit,  Office of Regional Counsel
              and Waste Management Division reconcile their records
              to ensure that cost recovery amounts due have been
              collected.  Where  cost recovery amounts have not been
              collected, the amount due should be recorded as an

             account receivable and appropriate action  taken  for
             collection.

    2.   Perform an  internal control review of the procedures  in  the
        Memorandum of Understanding during  the latter part  of FT
        1990 to determine whether the  procedures .are being followed
        and whether they are adequate  to ensure that receivables are
        promptly recorded on the financial records.

-------
 Finding:
     2.   Prompt Action Needed To Collect Amounts Owed,

     Region 4 was not promptly collecting coat recovery amounts owed
     to the Superfund Trust Fund because of (a) delays in sending
     written notification of the effective date to responsible
     parties, (b) late payment of amounts due, and (c) delays in
     sending accounting data to the responsible party.  These
     conditions existed primarily because (a) the Waste Management
     Division did not have a system to track when written notification
     of effective dates are to be sent and (b) consistent action was
     not taken to ensure collection of late payments.  Delays in
     collecting amounts owed resulted in lost interest to the
     Superfund Trust Fund of at least $13,071.

     Of the 21 settlement documents we reviewed, we found 6 cases (29
     percent) where collection of amounts owed was delayed.  The U.S.
     Treasury Department currently invests Superfund monies in 52-week
     U.S.  Treasury MK Bills.  When cost recovery amounts are not
     promptly collected, the Superfund Trust Fund loses the interest
     which would have accrued.
Recommendation(s):
      We recommended that the Region 4 Regional Administrator direct
      the Waste Management Division toi

       1.  Implement a system to promptly issue written notices of the
           effective date for cost recovery agreements.

       2.  Take prompt action to follow-up on late payments, including
           Middleaboro Rehabilitation Center and Linecrest Way.

-------
Recommendation(s)
     3.    FMS Heads To Accurately Reflect Transaction Dates

     The Integrated Financial Management System (IPMS) did not
     accurately reflect the (a) date of the accounts receivable, (b)
     due date,  (c)  collection date, and (d) interest rate for past due
     amounts.  Also, handling charge and penalty waivers were not
     indicated.  IFMS data were not accurate because (a) information
     was not forwarded promptly to the Financial Management Unit, (b)
     the Financial  Management Unit was not inputting data from source
     documents  correctly, and (c) the interest rate was not changed to
     reflect the interest charged on Superfund debts.  As a result,
     IFMS did not provide accurate financial reports, and demand
     payment letters were not generated accurately.
 Finding:
      We recommended that the Region 4 Regional Administrator direct
      S?Q^f?oiai Mana*~nt Ul*t to correctly and timely input
      ihouTFSi ?J?rHf28t: recowv receivables'into IFMS/ This area
      Inrc1990          M P*" °f the *•»*«» internal control review

-------
   Title:


            Audit Report No. E1SJF9-05-0274-0100126
            Review of Superfund Cost Recovery Accounts
            Receivable Establishment and Collection


Finding:      1.  Accounts Receivable Meed  to be  Recorded

            For all 20 settlement  documents we  reviewed,  neither Headquarters
            nor Region 5 recorded  accounts  receivable amounting to about $5

            million on the financial records of the Agency.  Thus, the
            Agency's control over monies owed to the Superfund Trust Fund was
            ineffective.  Because receivables were not recorded, the Agency
            was not aware of what payments were due the Superfund Trust Fund.
            As a result, a payment might be diverted, lost, or not paid
            without anyone being aware of it.  This also results in late
            payments with resulting loss of applicable interest as discussed
            in Finding Number 2.

            The Agency was also not meeting internal control standards which
            require that significant events be promptly recorded and properly
            classified.  The failure to record a receivable for amounts due
            to the Superfund Trust Fund is a material weaJcness in internal
            controls.

            The FT 1989 Agency Operating Guidance stated that the success of
            collecting cost recovery payments depends on being sure case
            closing information is immediately sent to the regional financial
            offices so the collections can be recorded properly and
            receivable amounts can be accurately reported to management.  We
            found that accounts receivable were not recorded because:  (a)
            Office of Regional Counsel (ORC) and' Waste Management Division
            (WMD)  did not forward the settlement documents to the Superfund
            Accounting Section (SFAS) in all cases, and (b) SFAS did not
            establish accounts receivable in the Financial Management System
            (FMS)  when settlement documents were received prior to payment.
            In addition, routine procedures have not been established to
            regularly reconcile WMD and ORC records with FMS.

            Region  5  is  currently  formalizing procedures  between the offices
            involved  in  cost recovery.  ORC,. WMD  and SFAS are preparing a
            Memorandum of  Understand (MOU)  concerning Superfund cost recovery
            procedures.  According to a November  13,  1989 draft of the MOU,
            WMD will  be  responsible for providing the SFAS with all
            administrative orders.   ORC will be responsible for providing all
            Judicial  consent decrees and  orders.

            In response  to our draft report,  the  Regional Administrator
            stated that  the  Memorandum of Understanding La expected to be
            fully executed by the  end of  January  1990.  Alao,  an internal
            control review of accounts receivable, which  will include a
            review of the  procedures in the Memorandum of Understanding,  is
            scheduled in February  1990.

            The actions planned by the Regional Administrator,  when
            implemented, will substantially correct  the deficiencies cited in
           i-our report.  We  recommend that  the  Regional Administrator ensure
           ^ regional officials complete their planned actions.

-------
K.ecommenaacion(s> :                     ,  •    •
                                   t
      Draft  Report Recommendations

      We  recommended that the  Region  5  Regional Administrator take
      appropriate action to:

       1. Instruct Waste Management  Division/  Office  of  Regional
          Counsel/ and Superfund Accounting Section to complete the
          Memorandum of Understanding  and  implement the  procedures.

       2. Perform an internal control  review of  the procedures  in the
          Memorandum of Understanding  during FT  1990  to  determine
          whether the procedures are being followed and  whether they
          are adequate to ensure that  receivables  are promptly
          recorded on the financial  records.

       3. Instruct the Financial Management Branch to implement its
          Superfund Accounts  Receivable  -  Interim  Operating
          Procedures/  as outlined in its August  30/ '1989 memorandum/


          to identify settlement documents not forwarded to Superfund
          Accounting Section.  Where cost recovery amounts have not
          been collected, the amount owed should be recorded as an
          account receivable and action taken for collection.

       4. Instruct Office of Regional Counsel and Waste Management
          Division to  establish a consolidated tracking system for
      ,    cost recovery.  Until a consolidated tracking system is
      '•    established/  require the Office of Regional Counsel and the
          Waste Management Division to continue to reconcile their
          tracking system reports.   Also, require that tracking
          reports  be provided to Superfund Accounting Section.

      5.   Instruct Superfund Accounting Section to regularly reconcile
          tracking reports provided by Office of Regional Counsel and
          Waste Management Division to the financial management
          system.

-------
            Finding:        "                     	

                2.    Prompt Action  Needed  to Collect Amounts Owed

                Region  5 was  not promptly  collecting cost recovery amounts owed
                to  the  Superfun4 Trust  Fund because of  (a) delays in sending
                accounting  data  to  responsible parties,  (b)  responsible party
                requests for  further documentation and/or dispute of cost billed,
                and (c) late  payment of amounts due.  These  conditions exist
                primarily because 'the responsibility for sending accounting data
                was not clearly  assigned within the Waste Management Division
                (WMD).  Delays in collecting amounts owed resulted in lost
                interest to the  Superfund  Trust Fund of  at least $79,232.

                Of  the  20 settlement documents we reviewed,  12 required that
                accounting  data  be  sent to the responsible parties as a billing
                of  cost incurred by EPA.   In 10 of 12 cases  where accounting data
                was required, there were delays in the collection of amounts due.
                In  another  case,  the responsible party is contesting the court
                order and has not paid  the cost due.

                The Treasury  Department currently invests Superfund monies in 52-
                week U.S. Treasury  MK Bills.  When cost  recovery amounts are not
                promptly collected, the Superfund Trust  Fund loses the interest
                which would have accrued.

                Our draft report recommended that Region 5 (a) establish formal
                procedures  between  the  Waste Management  Division, the Office of
                Regional Counsel, the and  Superfund Accounting Section to
                identify all  settlement documents which  include provisions for
                billing of  oversight costs and forwarding settlement documents to
                Superfund Accounting Section, and (b) instruct Superfund
                Accounting  Section  to develop an automated tracking system for
                billings.   In response  to  our draft report,  the Regional
                Administrator stated that  the Memorandum of  Understanding will
                ensure that settlement  documents are promptly forwarded to the
                Superfund Accounting Section.  Also, an  automated tracking system
                for billing oversight costs will be included as part of the newly
                developed Cost Documentation Monitoring  Systc
               The actions planned by the Regional Administrator, when
               implemented, will substantially correct the deficiencies cited  in
               our report.  We recommend that the Regional Administrator ensure
               regional officials complete^ their planned actions.
^ecommendation(s):

                We recommended that the Region 5 Regional Administrator take
                appropriate action to:

                 1.   Establish formal procedures between the Waste Management
                     Division, the Office of Regional Counsel, and the Superfund
                     Accounting Section to identify all settlement documents
                     which include provisions for billing of oversight costs.
                     The procedures should include forwarding settlement
                     documents to Superfund Accounting Section.

                2.    Instruct Superfund Accounting Section to develop an
                     automated tracking system for billings.

                3.    Instruct Waste Management-Division to promptly notify
                     Superfund Accounting Section of all oversight billings
                     required, until all settlement documents are forwarded to
                     Superfund Accounting Section and/or an-automated tracking
                     ftvaten is developed,
               4*   £«|»*rnefth« SuP«*und Accounting section to promptly
                    Prepare accounting data and send billings to responsible

-------
         Title:, Review of Region  2's Oversight of Superfund
                Post-Settlement Activities
                Audit Report No.  EISJCS.-0 2-0055-0100230

         Finding: 1. LENGTH OF REGIONAL REVIEWS DELAY SUPERFUND CLEANUPS

                Initiation of Superfund cleanup work was unnecessarily delayed
                after the Region had reached a settlement with PRPs.  The
                approval of workplans, project operation plans and other
                documents required prior to initiating field work on RI/FSs, or
                other work phases took between 6 and 36 months.  This occurred
                because of a lengthy review process which lacked definitive EPA
                review and approval timeframe guidelines.  In addition, the
                Region did not maintain an automated post-settlement tracking
                system to monitor the timeliness of PRP submissions or the
                overall status of settlement cases.  Another contributing factor
                was an understaffed and overworked project manager corps which
                could not always devote essential review time to individual
                projects.  As a result, Superfund cleanup actions were
                significantly prolonged (up to several years) increasing the
                potential for adverse public health effects and further
                environmental degradation.
'.ecommendation(s) :
                1.
                2.
 we recommend that guidelines be developed and implemented which
 set specific timeframe deadlines for Regional review and approval
 of PRP submissions.   We also recommend the development and
 implementation  of an automated tracking system to monitor
 specific  post-settlement milestone dates,   in addition, we
 recommend streamlining the review process  for PRP draft
 submissions.  We  further recommend the review of project
managers'  workload to determine whether any reassignments are
necessary to better  equalize workload.   Finally, we recommend
that  a  systematic approach for the preservation of documentation
in project files  be  developed and  implemented.

     Direct  the Director,  ERRD,  to develop and implement
     guidelines which set  specific timeframe deadlines for
     Regional review and approval  of  PRP submissions.

     Direct the Director,  ERRD,  to develop and implement an
     automated  tracking system to  monitor  specific post-
     settlement milestone  dates.   The use  of personal computers
     should be  considered  for this system  due to their
   -availability to ERRD  enforcement personnel.

     Consider streamlining the review process for PRP draft
     submissions.  While initial reviews should continue to be
     sent to all  appropriate  parties,  technical review of any
     revised submission  should be  primarily limited to the
     project manager.

     Review the current  project managers'  workload and determine
     whether there are extreme cases  where reassignments are
     necessary  to better equalize workload.   Once this is
     accomplished a  plan of action  should  be developed for case
     assignments taking  into  consideration such items as optimal
     project manager/site  ratio, site status, project manager
    experience, and contingencies  for staff turnover.

    Develop and implement a  systematic approach for preserving
    documentation in project  files.  Files  should be maintained
    in an organized and orderly fashion so  that information can
    be readily obtained.
                3.
               4.
               5.

-------
Finding:   2.
                  REGION N
                  PENALTIES
        .     Stipulated penalties  were not beino assA««^ *
             with settlement milestone dates   The »*~*   f°f noncoi«pUance
             taking aggressive enforcement action  M^?Lr?5rained froin
             verbal negotiations or warning letters ^Z»*itS.*Ctions to
             penalties in extreme  instance!.  The !J?JW  2^°nly sou^nt
             as much as 51,157,500 in  penalties  ?«£?    did not assess PRPS
             reviewed.  As a result, there  was no f J ° °f the 13 cases we
             comply with compliance order reo^ir™"?"06"6?* for PR*s to
            enforcement encourages PRPS to Strement? •   This lack of
            provisions of the settlement Soc^t^?6?"^ imP°«a^
            unnecessary lengthening of the oSSii  nff   lead8 to an
            detrimentally affect the public hlalti I»* ?KP  Process-   This  can
            recommend the Emergency and Remedial p^  d the  envi*onnient•  We
            concert with  the Office of R«oi«dff ^ esponse DivisiorfTin
            the option of  stipulated penalties  whfnn«i'  aWe«ively pursue
            with settlement document  reauiri™L?  * PRPs  are in noncompliance
            provided  and approved  Sy  ap^opr?f?e R*a£*^ficatio« should 22
            instances where stipulated penalties frf n f1 »«•«•" L» those
Recommendation(s):                        penalties are not  pursued.

          we recommend  that you require the Director  ER»n   ,-«
          the Office  of Regional Counsel,  to i«®"°f;..f??D^.in concert
          of stipulated penalties when  PRPs
          settlement  document requirements,   j
          provided and approved by appropriate
          instances where stipulated penalties
                                                      f?"tt* the °Ption
                                               nonc°n>pUance with

                                                       Sh°Uld be

-------
  Find      3>   OVERSIGHT  OF  TECHNICAL  ENFORCEMENT  SUPPORT  f TES K CONTRACTORS
               NEEDS  IMPROVEMENT

           The Region  needs to improve  its oversight  responsibilities  of  TES
           contractors.  Specifically,  the Region did not effectively
           monitor the timely submission and processing of  required
           contractor  reports and plans; conduct and  document  field
           oversight reviews, quality assurance audits, and contractor
           office reviews; and give emphasis to project manager  training.
           These conditions occurred because of inadequate  monitoring,
           untimely or lengthy Regional reviews and approvals, lack of
           written procedures and low priorities or insufficient resources
           assigned to certain tasks.   As a result, there were work
           stoppages and unnecessary delays which have contributed to  a


           lengthier  cleanup process ,  there was no assurance  that TES teats
           or .records were reliable or accurate and  there  was nS  assurance
           that project managers were  sufficiently knowledgeable  to
           adequately administer TES contractors.  We recoSmend the Reaion-
           (i) improve the quality and timely EPA monitoring of TES Regi°n*
           contractors' required reports and workplan submittals  and
           compliance with- miles tone dates; (ii) expedite  the Regional
           review and approval system  for TES deliverables ; and (UiV
           develop timetables and minimum requirements for periodic field
           oversight  reviews, quality assurance audits, and contractors
           office reviews are scheduled ,  performed and adequately
           documented.  We also recommend that project managers be  reouired
           ^™tte!!d Prescribed training.   Suciftraining sS2u!5 generally t
           received prior to performing TES oversight responsibilitiS.

Recommendation(s) :


       we recommend that you:

           improve the quality and  timely monitoring of  TES

                                             workplan
       2'   deliverable.. R99i°Ml rSVieW and aPP«™l  systen  for TES
       3'   ??IT0Lii??tSl" and minimuo requirements for periodic
                                    re»pon»ibiUtie».
                                                                if it

-------
Follow-Up Review

-------
Title:
         SUBJECT:  Review of EPA Region 8's Corrective
                   Actions Taken in Response to
                   Audit Report No. E5eH7-08-0005-71992
                   Review of EPA Region 8's Administration of
                   Superfund Cooperative Agreements
                   Special Report No. E1SGG9-08-5000-0400013
Finding:
          Region 8 initiated actions to correct the audit findings
     discussed in the audit and to implement the 10 recommendations.
     The Region's implementation of its action plan, however, was not
     timely in all instances nor fully effective in correcting the.
     previously reported conditions.  Our followup review disclosed
     that corrective action to implement two of the audit report's
     recommendations remained incomplete.  Also, the corrective
     actions on two other audit recommendations were not fully
     effective in correcting the deficiencies discussed in the audir.

          Our followup review also disclosed that the Region does not
     have an effective system for tracking the implementation of
     corrective actions.  Consequently, Regional management has no
     assurance or knowledge that its commitments to correct audit
     identified deficiencies have been met.

-------
RecoouEendation(s):
        We recommend that the Region 8 Regional Administrator:

        1. Prepare and implement an updated action plan which
   addresses each of the incomplete corrective actions in audit
   report no. E5eH7-08-0005-711992.  Specifically, the following
   corrective actions should be included.

        a. Assure that Regional Superfund staff are aware of and
   fully instructed in Regional policies and procedures implemented
   to enhance oversite of state performance in the Superfund
   cooperative agreement program.  Specifically, the importance of
   the policy entitled "Region VIZI Policy on Documentation in
   Project File of Region's Acceptance/Rejection of Completed
   PA's/SI's", dated April 7, 1 988, should be re-emphasized.

        b. Assure that all remaining Si's covered by SARA's original
   completion goal of January 1, 1989 are adequately tracked and
   completed to the extent possible, pending implementation of the
   revised HRS.

        c. Give special attention to expediting action at the
   following three NFL sites identified in both the audit and our
   followup review as experiencing inordinate delays:
                                               /•
        - Sharon Steel Site
        - Silver Bow Creek Site
        - Arsenic Trioxide Site
         d. Continue to take an active  role  in monitoring the
    timeliness and adequacy of state  Superfund cooperative agreement
    performance; including having  in  place for each state:  (i)  a
    signed final SMOA; or (ii) alternative oversight methods tailored
    to state.

    2.  Enter the corrective action plan from our followup review into
    MATS and monitor progress until all corrective action items  are
    complete.

-------
Cooperative Agreements

-------
      Title:  Audit Report No,  P5BFN9-04-0189  - 0300035
             Report on  Interim Audit of Alabama
             Department of Environmental  Management
             Cooperative Agreement No.  V004S50-87
    Finding:  in the auditor's opinion,  subject to the effect of EPA's ultimate resolution of
              the questionable expenditures summarized below and presented in the report, the
              costs  claimed  fairly present  the financial  information  in  accordance with
              financial provisions  of the grant and generally accepted accounting principles.
Recommendation(s):

            We recommend that EPA not participate in the $6,021 of ineligible costs.  If any
            portion of  the ineligible cost  is determined to  be valid project cost,  the
            balance due EPA should be appropriately adjusted.  Region 4 should recover all
            funds due EPA in accordance with established procedures.

-------
Title:
      SUBJECT:  Audit Report No. P5cG*8-04-0091 - 0300010
                Report en Interim Audit of Kentucky
                Natural Resources and Environmental Protection Cabinet
                Cooperative Agreement No.  V004484-85
Finding:
     Direct  involvement  hours  by  site included  in  the  quarterly  reports
     submitted  to  EPA  were significantly below total hours  charged  to  the
     Agreement  through  March  31,  1989.  KNREP did not  maintain  or  retain
     schedules  supporting  the  direct involvement  hours  reported.   KNREP's
     formal  timekeeping  system, though providing for tracking total hours  by
     program,  did  not  acconnpdate  the  tracking   of  hours  by  site.  The
     site-specific  hours cannot, therefore, be reconciled with the formal tine
     summaries.

     Attachment  A  to  EPA's "State Participation in  the  Superfund  Remedial
     Program"  indicates  states are not required to track costs by. site  under
     pre-remedial  PA/SI cooperative agreements.  The quarterly report required
     by EPA does, however, require the reporting of direct involvement hours by
     site.

     We  believe  that KNREP's system did not provide for proper monitoring  of
     program efficiency or the supplying of accurate productivity data to EPA.
Reconunendacion(s);


      We  recommend that  KNREP   implement  a  timekeeping  system which will
      facilitate the  tracking  of hours, by site as well as  by  activity and
      project.   We further recommend that KNREP reconcile hours  reported  to EPA
      with the formal timekeeping  system and ensure that the data being  reported
      is accurate.
  Finding:
         In  suonarizing costs for the month of March 1985, KNREP did not  take
         into account the fact that the first payroll in March 1985 covered the
         latter half of February 1985.  The beginning project and budget period
         date  of  March 1, 1985 is delineated in the grant award.   Cumulative
         cost  claimed  includes  direct labor and  indirect costs  incurred  prior
         to  the  effective date of the Agreement in the amounts of $2,455  and
         $643, respectively.  W* believe that costs incurred prior to the start
         of  the  project period are  ineligible.  Accordingly, the  $2,455  and
         $643 have been questioned.
   Recommendation(s):
         Wfe  recoomend that KNREP implement cost  reporting procedures to ensure
         that costs  claimed  represent cost  incurred within the  project and
         budget period.

-------
    Finding:
          Seventy-five  hours  of  time  expended by  an  Environmental  Program
          Coordinator  during the pay period ended October 15, 1988,  on  another
          project  (and  indicated as such on the employee's tine  report)  were
          charged  to the cooperative agreement as the result of an input error.
          This  resulted  in  the  overstatement  of  cost  claimed  under   the
          Cooperative  Agreement.  The $1,086 and $520 of personnel and  indirect
          costs,  respectively, claimed as a result of the error are   ineligible
          and have, thus, been questioned.'
  Recommendation(s):
          5*  tBM-)  ^~™<^£%«S^t££&i-ot
          errors.
   Finding:
       EPA  approved  the  use of CERCLA funds to purchase  two vehicles  costing
       $32,534.  An  amendment to the cooperative agreement included a  list  of
       proposed equipment, its unit cost and written justification.  Not included
       was  a  cost-effectiveness  comparison of purchasing  with federal  funds
       versus  other  options.  Appendix T to EPA's "State Participation  in  the
       Superfund Remedial Program" requires the submittal of a cost-effectiveness
       comparison when equipment is to be purchased with CERCLA funds.
        Ws  believe that the purchase authorization was not obtained in accordance
        with  the requirements of Attachment T.  However, the $32,534 has riot been
        questioned inasmuch as EPA approval was obtained.
Recommendation(s) :
        We recommend that KNREP and EPA act in accordance with the requirements of
        EPA  policies  and regulations.

-------
 Title:   Audit Report No. P5bFN9-06-01fl8 -0300033
          Report on Interim Audit of Texas Water Commission
          Cooperative Agreement No.  V006454-01
Finding:  in the 'auditor's opinion,  subject to the effect of EPA's ultimate resolution of
          the questionable expenditures summarized below and presented in the report, the
          costs  claimed fairly  present the  financial information  in  accordance  with
          financial provisions of the grant and generally accepted accounting principles.
Recortunendation(s):
          We recommend that EPA not participate in the $9,373 of ineligible costs.   If any
          portion of  the ineligible cost  is determined to  be valid project  cost, the
          balance due EPA should be appropriately adjusted.  Region 6 should recover all
          funds due EPA in accordance with established procedures.

-------
 Title:
     SUBJECT:       Audit Report No. E5BGL9-06-0134-0100079
                    Interim Audit Sikes Disposal  Site No.  22
                    Superfund Cooperative Agreement V006450-01
                    Texas Water Commission - Austin,  Texas
                    March l, 1986 through June  30,  1989
  Finding:
        In our opinion,  the  costs  summarized below and presented in
        Exhibit A present  fairly the financial information in accordance
        with the financial provisions of  the cooperative agreement and
        generally accepted accounting principles.
Recommendation(s):
        we again recommend that EPA require TWC to prepare a summary
        record of negotiations setting forth the principal elements of
        negotiations.  This record should contain sufficient detail to
        reflect the significant considerations controlling the
        establishment of price and other terms of the contract.

-------
         Title:  New York State Department of
               Environmental Conservation
               Interim Audit Multi-Site Cooperative Agreement
               Number V-002437-84-1C250394-02
               Audit Report Number P5BGL9-02-0366-0100245
Finding:    The ineligible costs of $71,897 claimed by the grantee consisted
          of:

               *    $66,649 of Contractual Services due to costs associated
                    with invalidated analytical data and costs incurred
                    after the lapse of the project period.

               *    $4,551 of Personnel Costs due to costs associated with
                    invalidated analytical data and costs incurred after
                    the lapse of the project period; and

               *    $697 of Travel Expense due to costs associated with
                    invalidated analytical data and costs incurred after
                    the lapse of the project period.

               Unsupported costs of $221,135 claimed by the grantee
          consisted of:

               *    $77,749 of Personnel Costs in excess of the grant
                    budget and inadequate documentation;

               *    $4,379 of Travel Expenses in excess of the grant budget
                    inadequate documentation; and

               *    $135,901 of Contractual Services due to inadequate
                    documentation; and

               *    $3,106 of Equipment and Supplies in excess of the grant
                    budget.


   Recommendations):

           The  Regional  Administrator, Region. II, not  participate  in the
           ineligible  costs  of  $71,897  {$71,897 Federal  share) and determine
           whether EPA should participate in  the  unsupported  costs of
           $221,135  ($221,135 Federal  share).

-------
Interagency Agreements

-------
Title:
          SUBJECT:  Audit of Superfund Interagency Agreements
                    with the U.S. Army Corps of Engineers -
                    Fiscal 1988
                    Audit Report No. M5BFLO-11-0017-0100029
 Finding:
       As required by section lll(k) of the Superfund Amendments
  and Reauthorization Act of 1986, the U.S. Army Audit Agency
  prepared the subject report.  One issue is outstanding.  At the
  end of the audit, the Corps' New England Division  could  not
  locate supporting documentation for a $187,292 obligation.  The
  Division indicated that it would deobligate  the  funds  if
  documentation is not found.  To ensure that  this issue is
  adequately resolved, we are making the following recommendation.
Recomraendation(s):
   We recommend that the Director, Grants  Administration Division
   obtain a written response from the Corps  of Engineers regarding
   resolution of the $187,292 obligation.

-------
Title:
        SUBJECT;  Audit of Superfund Interagency Agreements with the
                  Department of Energy - Fiscal 1988
                  Audit Report No. 115BFLO-11-0016-0100027
  Finding:
       The Office of Inspector General,  Department of Energy
  prepared the  subject report which is required by section lll(k)
  of the Superfund Amendments and Reauthorization Act of 1986.
  We are not making any recommendations  to  you and are closing this
  report upon issuance.   However, the Grants  Administration
  Division may  want to emphasize to the  Department of Energy that
  indirect costs  can be applied to Superfund  interagency agreements
  only if a rational,  defensible allocation plan is being imple-
  mented.  General or Agency-wide indirect  costs are not allowable
  unless specifically authorized by legislation.

-------
Title:
      SUBJECT:  Audit of Superfund Interagency Agreements With
                The Department-of Interior - Fiscal 1987
                Audit Report Number M5BFL9-11-0046-0100058  -
 Finding:
         In accordance with section lll(k) of the Superfund Amend-
    ments and Reauthorization Act of 1986, the Inspector General,
    Department of the Interior (DOI) performed the subject audit.
    Attached are the reports for the two agencies reviewed - the U.S.
    Fish and Wildlife Service and the U.S. Geological Survey.  The
    attached reports discuss (1)  001 agencies conducting valid Super-
    fund work activities prior to an accepted interagency agreement
    and (2) costs incorrectly charged to Superfund interagency agree-
    ments.  DOI has resolved both audit reports per the Department's
    internal procedures.  We will request the Inspector General, DOI
    to follow up on the status of the corrective actions planned but
    not implemented during the fiscal 19S9 audit, particularly con-
    cerning questionable charges.  Based on the reports, we are
    making the following recommendation.
Recommendacion(s):
      We recommend that the Director, Grants Administration Division
      emphasize to Headquarters and regional offices the need to issue
      interagency agreements prior to starting work or, if this is not
      possible, timely documenting EPA's request for services via a
      memorandum to the other agency.  When work is started before an
      interagency agreement is executed, the interagency agreement
      should reflect the time period work actually began.

-------
Title:
         SUBJECT:  Audit Report No. M5CPLO-11-0019-0100080
                   Audit of Superfund Activities in the
                   Department of Justice's Land and Natural
                   Resources Division for Fiscal Tear 1988

-------
Finding:
          II  INTERNAL CONTROLS
              Our examination of the accounting records, supporting
              documentation,  and tests of Superfund cosrs for
              allowability and allocability disclosed no material,
              discrepancies in the FY 1988 Superfund costs reported
              by the LNRD to  the EPA.  However, internal control
              weaknesses were found relating to the time reports and
              the travel documents- that unnecessarily increase the :
              risk that errors could occur and not be detected in a
              timely manner.   The conditions found could have been
              minimized, or possibly eliminated, had:   (1) those
              employees working on Superfund cases exercised greater
              care in the preparation and timely submission of the
              required weekly time reports; and (2) those officials
              involved in the request,  authorization, and approval
              of travel, including the traveler, exercised greater
              care in the preparation and review of travel documents
              relating to Superfund cases.
 Recommendation(s):
               Ensure that the control procedures  over the employee time
               reporting system, as  indicated  in the LNRD's response to
               the prior audit of.the FY 1987  Superfund activities, are
               completed and implemented no later  than October 1, 1989.
           2.  Require the issuance of written policy and  procedures thax
               will hold the employees' immediate supervisors responsible
               and accountable for obtaining and reviewing the employees •
               weekly time reports on a timely basis.

           3.  Require the establishment of the necessary  controls for
               verifying the completeness and accuracy of  the case
               numbers related to the purpose of the travel recorded on
               the Official Travel Request and Authorization and the
               related travel vouchers, including the allocation of
               travel costs now required to be recorded on the vouchers.

-------
Finding:
          2.   T3AVEI.  CSSTS

              Because of  limitations within the  Department's
              Financial Management  Information System (FMIS),  the
              LNRD is not readily able to accurately  account for
              case-specific travel  costs relating, to  trips involving
              more than one case.   As a result,  the travel charges
              made to a specific case could be over or understated
              on the  reports to EPA.  However, in our opinion,  this
              does not materially affect the  financial reports to
              EPA or  the  cost data  prepared for  litigative cost
              recovery actions.
 Recommendation(s):
           we recommend that the Assistant Attorney General for the LNRD
           instruct the Executive office to:

               4.   Modify the system of accounting to identify those travel
                   vouchers having multiple cases for which travel .costs mus
                   be allocated.

-------
Other

-------
.Title:

 GAO Report:  "Contractors Should Be Accountable for Environmental Performance"
             GAO/RCED-90-23  (SRIS# GA00092)"


 Finding:

 DOD and DOE  contractors have been charged with nearly  identical RCRA
 violations.  DOD holds it contractors accountable for  these charged violations
 and does  not pay any resulting contractor penalties, settlement payments,  or
 legal costs  unless the contractors can demonstrate that  these  costs resulted
 from circumstances beyond the contractors' control.  In  contrast, DOE does not
 hold its  contractors accountable for similar charged violations unless  its
 contractors' top management engaged in criminal activity.  Although the unique
 nature  of DOE's work may warrant a special relationship  with its contractors
 and DOE's policy and practice of paying its contractors' penalties, settlement
 payments,  and  legal costs, we believe DOE will reduce  contractors' incentives
 to  comply with RCRA and may negate the benefits of EPA's initiative of  seeking
 enforcement  actions against contractors that operate federal facilities.
Recommendation:
To ensure  that its contractors are held accountable for charged RCRA
violations and resulting costs, GAO recommends that the Secretary of Energy,
in consultation with appropriate congressional oversight committees, initiate
a rulemaking to revise DOE's current policy and practice of paying for
penalties, settlement agreements, and legal costs incurred by  its contractors.
Recognizing that there may be limited circumstances warranting such payment,
the revised .policy should include criteria that detail when such payments
should or  should not be allowed.
Finding:


Although neither DOD nor DOE regulations and guidelines require consideration
of contractors' environmental performance in determining award fees, both
agencies consider such performance to varying degrees.  DOD and DOE usually
judged their contractors' environmental accomplishments to outweigh the
contractors' environmental weaknesses, including charges of RCRA violations.
Because we could not judge whether the cited accomplishments should or should
not have outweighed these weaknesses, we were.unable to assess whether DOD and
DOE gave appropriate consideration to contractors' environmental performance
in the award-fee process.  However, because award fees are intended to
motivate contractors to strive for excellent performance and these contractors
have been repeatedly cited for environmental weaknesses, DOD and DOE should
ensure that contractors' environmental performances are adequately considered
in ail award-fee determinations.

-------
Recommendation:

To help maximize award-fee contractors' incentives to comply with
environmental laws and regulations, the Secretaries of Defense and Energy
should initiate a rulemaking to-revise DOD-'s and DOE's regulations to require
all award-fee contracts.to include environmental performance as a distinct
evaluation area.

-------
                                                     Potential FNFIA lltafcnrssaa                                    Page;    52
                                                               FT 1990                                             Data: 09/13/90
                                                            Division: Alt
          (  1):   Finding 1 Summary

                    Before we began our evaluation, EPA had developed an information system that included five data collection
                mechanisms that provided some information on hazardous waste generation or management. EPA experienced specific
                problems with the individual data collection mechanisms or with the information system as a whole in four ereas:
                (t) system development, <2) information requirements,  (3) measurement, and (4) data collection. Through 1986,  these
                problems had prevented EPA from determining  with reasonable precision or certainty how much of what type of
                hazardous waste was generated, how it waa managed, whether sufficient management capacity existed, or whether
                progress waa being made in reducing hazardous waste generation.

                    EPA initiated 13 efforts to improve the hazardous waate information system that directly affected the quality
                of Its information on hazardous waste generation and management. In this chapter, we presented our evaluation of
                EPA efforts to improve the  information system development process; efforts aimed at improving specific-information
                system components are discussed in subsequent  chapters. Four information system development problema*haverbeen
                identified: (1) lack of a comprehensive plan to coordinate data  collection efforts; (2) no comprehensive
                evaluation of existing regulatory development data; (3) isolated data collection efforts that were narrowly focused
                and resulted in duplication of effort; and (4) data planning and collection responsibilities that were-divided
                among program offices, with Inadequate integration of data collection efforts (including cross-media data
                collection  efforts).

                    EPA s evaluation of data collection activities has fully corrected the second of these problems.-However,  the
                improvement.efforts we evaluated are not likely to prevent the problem of the isolated development of data
                collection efforts needed to ensure integrated data collection that fully supports the program mission. No overall
                data collection plan has been developed. The central coordinating office does not have full authority-to develop
                data  collection efforta and did not use a central prime contractor for developing systems. The coordinating office
                had to rely on contributions from the budgets of program offices, other offices continued to have responsibility
                for improvement projects, and the tracking system does not provide a mechanism for ensuring consistency. .These
                factors also contribute to the possibility both of failure to collect needed information in some areaa and of
                redundant data collection in others.

                    The principal planning mechanism (the new life cycle management system) is a major improvement,  but it needs
                refinement to ensure that it accomplishes its intent.  In th* one applicable case where it waa used,  the analysis
                and documentation were inadequate given the importance of the system. Important potential data collection
                alternatives were not considered,  the analysis of costs and benefits waa inadequate, previous problems with the
                data collection mechanism were not systematically examined,  and specific information needs were not  systematically
                identified.  Finally, the legal authority for collecting new information was not clarified.

                    Our findings show that EPA haa established an improved information system development process that is largely
                consistent with federal guidelines and EPA policy. Our findings also show that further improvements  ere needed. EPA
                should develop a comprehensive plan for data collection.  The life cycle management system should require complete
                and detailed documentation for major information system components. Placing the final authority for  developing
                Information system components in the central coordinating office, which would have control over the  information
                system development  budget and use a prime contractor  when appropriate, is an additional  step EPA should consider
                in order to achieve an overall  Information system that effectively supports the program mission.

                    EPA officials indicated that in general they agreed with our findings and are already taking steps that at
                least partially address some of them. They stated that a survey of the states to determine what state officials
                believe their data needs are has now been completed, that the central coordinating office now has its own budget
                that is supposed to be adequate for system development (although the office may still obtain additional  funding
                from substantive divisions),  and that they now have a  prime  contractor for the RCRA reporting system. We did  not,
                however,  evaluate EPA's recant activities.                                                                      '  .

M:                               Offices                          Div:                              Branch:


                We recommend that the Administrator of EPA direct that tha Assistant Administrator for Solid Waste and Emergency
                Response take appropriate steps to enhance its information system development process and fully ensure that data
                collection efforts complement each other and support the program mission. Specifically, a comprehensive  data
                collection plan should be developed.  Steps  should be taken to improve the assignment of responsibilities for
                planting and directing the development of information  system components by increasing the authority  of the central
                coordinating office to develop data collection efforts and ensure consistency. Finally, the life cycle managmiiint
                system should be refined to ensure the complete and detailed analysis and documentation of each stage of the cycle
                for major system components.


M:                               Office):    *                    Olvs

Beport/Audit:   Hazardous  Waste: EPA's generation  and Management Data  Need Further Improvement
Title

Beport/Audit Author: GENERAL  ACCOUNTING OFFICE

-------
                                                     Potential FNFIA wXetiiMiin                                    Page:    S3
                                                               FT 1990                                             Date: 09/13/90
                                                            Oiviaion: All
Publication Date: 02/01/90
         < 2):  Finding 2 Sunnery

                Our analysis shows that EPA has extensive needs for hazardous waste generation and management information.  The
                information requirements can be divided into three groups baaed upon the amount of detail required.

                All the data gaps identified in the original information system are filled by one or more of the new or revised
                data collection instruments. The vast majority of the additional data needs we identified have also been addressed
                by one or more of the instruments developed by EPA. This represents e significant accomplishment by EPA. However,
                we also found that three information requirements have not been satisfied. Without this information, EPA regulatory
                development research and national capacity analyses, including SARA capacity assurances, will be  significantly
                flawed.

AA:                               Office:                          Div:                              Branch:


                  We recommend that the Administrator of EPA direct the Assistant Administrator for Solid Waste and Emergency
                Response to take appropriate and feasible steps to fill remaining information gaps, including (1) the volumes of
                waate located at CERCLA and corrective action sites that will ultimately require management capacity, (2)  the
                volumes of waata that will require  management capacity under proposed  regulations (including the large volumes of
                waste expected from the cleaning up of leaking underground storage tanks), and (3}  the potential disposal  capacity
                of salt domes and other geological formations that are capable of preventing the migration of wastes.

AA:                               Office:                          Div:                              Branch:

Report/Audit:   Hazardous Waata: EPA's Generation and Management Data Need Further Improvement
Title

Report/Audit Author: GENERAL ACCOUNTING OFFICE

Publication Date:  02/01/90


         (  3):  Finding 3 Sumnary

                The measures included in EPA's  revised data collection instruments are much improved. The problems of undercounting
                and over-counting the total volume of wastes generated have been corrected. The previous problems with the measures
                of waate management technologies, with the exception of those involving treatment technologies,  have also been
                fully corrected. In addition, significant improvements have been made in the measures of waste end treatment  type,
                although these improvements have not completely eliminated the original problems.

                There still  remain some measurement problems that may produce significant errors In determining the volume  of  each
                type of waste generated, the type of treatment technologies used, the total capacity of management technologies
                (such as some types of incineration),  and the degree of waste minization. The RCRA waate codes,  which are used on
                all data collection instruments,  will  continue to produce inaccurate counts of the volume* of regulated waste
                streams due  to misclaaaification. The qualitative measure of waate type EPA developed to supplement the RCItA  waste
                codea, although  an improvement  over peat methods, has not fully solved the problem. The mixture of independent
                attributes creates a complex and redundant measure that can significantly reduce reliability because respondents
                are likely to interpret  it differently.  Qualitative measures are also much less accurate than available
                quantitative measures, on some  instruments,  EPA has included the preferable quantitative measures; these represent
                an important improvement over the quantitative measures. EPA should continue to expand the use of quantitative or
                continuous variables for measuring waate characteristics.

                Although EPA has developed new, much improved measures of the types of monegtmiiiit technologies,  misclassification
                remains likely due to the-mixing of attributes. The development of e true general classification system with
                mutually exclusive,  exhaustive,  and hierarchical categories would fully correct the remaining problem.

                In general,  waate  management capacity is now measured well. However,  the measure of the capacity of cement  kilns
                and aimilar  forms  of incineration was  not sufficiently specific to assure that respondents will  interpret the
                question in  the  same way. If respondents assume either unlimited demand for their product or waste with a low
                heating value, the capacity of  this form of incineration could be significantly overestimated. Some overeatimat ion
                of capacity  is also likely in some versions of this reporting instrument because acme respondents may not have
                considered permit  restrictions  in reporting maximum capacity.

                Finally,  the measures of the extent of waate minimization developed by EPA will not produce valid data on changes
                in waate generation per  unit of production.  The measures do not account for the production of different products
                from one year to the next that may generate unequal amounts of hazardous waate. The results will  be misleading
                because incidental changes in production will be mixed with,  and thus will obscure, actual waste minimization.
                Moreover,  the qualitative measure of toxicity can only show the percentage of caaea in which waate minimization
                toxicity over-time.-In concentration,  not the amount of change in order to correct these problems,. EPA should
                measure the  voluae of waate produced by  each type of product and the concentration of each toxic  constituent.  These
                detailed data could be collected  from  a  sample, which method would be preferable to the larger task of  collecting

-------
  Weakness  (Continued):
                 the information via  a  census.
AA:
                                  Office:
Potential FNFIA
          FT 1990
       Division: All
              Div:
                                                                                                                   Page:    54
                                                                                                                   Date: 09/13/90
                                                                                                     Brand):
           ( 3): We recommend that  the Adninistrator of  EPA direct the Assistant Administrator for Solid Waste and Emergency
                Response  to  assure the use of the mat  appropriate measure of the revelant attributes of hazardous waste generation
                and management.  Specifically, quantitative measures should be used to measure waste characteristics (such as those
                needed  for assessing management capacity or waste minimization), and in addition, a true general classification
                system  should be developed for treatment technologies.
AA:
                                  Office:
              Divs
                                                                                                     Branch:
Report/Audit:   Hazardous Waste: EPA's Generation and Management Data Need Further Improvement
Title

Report/Audit Author: GENERAL ACCOUNTING OFFICE

Publication Date: 02/01/90
weakness ( 4):  Finding 4
AA:
                EPA data collection methods and procedures have improved in important way*. The oust recent national surveys used
                accepted stratified sampling techniques, and the sane data collection instrument was used for each respondent
                sampled. These are basic and sound methods of data collection. However, because of the continued use of different
                data collection instruments among the states, the 1987 RCRA reporting cycle cannot produce complete and valid data.
                Some of the sane problems that characterized previous reporting cycles continue to affect data from states using
                old instruments. In addition, the new information requested on the revised instrument is not fully supported by
                federal regulations.

                Data collection problems will not seriously jeopardize the two types of capacity analyses performed directly by
                EPA. The integrated capacity assessment and the assessments performed to support the land disposal restrictions
                rely entirely on the national surveys, which had minimal data collection problems. However, SARA capacity assurance
                will be seriously impaired because of its reliance on the RCRA reporting system and the fact that data from
                different years and different data collection efforts will be used. Necessary data will be entirely missing in
                states that did not use the revised RCRA reporting system instrument, and previous measurement problems will
                persist. EPA has attempted to compensate for the missing data by providing states with assumptions based on
                engineering judgments. However, EPA acknowledges that these do not reflect actual state conditions. The resultant
                uneven quality of the data will seriously weaken confidence in the SARA capacity assurances. Although state and EPA
                experts we interviewed believed the capacity assessments will be as good as possible given the available data and
                the time frame, state experts indicated that the level of detail will not be sufficient for waste management
                companies to determine whether or where to locate additional capacity.

                Our overall conclusion is that data collection problems will threaten the quality of the data produced by the
                permanent information system. EPA has not supplied the seme 75 percent of the funding for the RCRA reporting system
                that it provides .for other required program activities, nor has it provided effective incentives to the states,
                even though EPA intends the system to be the single routine mechanism for providing regulatory development data.
                Rather than conduct further national surveys, the agency plans to have states collect regulatory development data
                needed by EPA in the Rca reporting system- this despite the fact that the RCRA reporting system (1) has never
                produced valid and complete national data, <2> sample surveys in conjunction with the RCRA reporting system would
                be more efficient and effective,  and (3) the revised instrument Is more detailed than necessary for implementation
                purposes (although less detailed than needed for regulatory development), we believe it is unwise to abandon
                EPA-sponsored national surveys without a proven alterative. In addition, the toxic chemical release inventory
                reporting system has not been designed to complement other data collection mechanisms that provide information on
                hazardous waste generation and management. Moreover, existing federal regulations are inconsistent with EPA
                expectations for state data collection and do not support the collection of new information. Finally, EPA'a ability
                to require states to collect standard data is limited by the authorization procedures established in RCRA. The
                result of the current arrangements is that the federal information system must be pieced together from separate
                state systems rattier than,  as RCRA suggests, having the states add data to a minimum, consistent federal system.

                EPA officfels generally agreed with our findings and stated that the agency has already taken steps that at least
                partially address sons of our findings. These steps include increasing the role of limited scope sample surveys,
                planning to begin revision of the federal regulations in the fall of 1989, and creating a more streamlined RCRA
                reporting instrument. Since these actions were taken after we finished our field work, we could not evaluate them
                for this report.
                                 Offices
             Div:
                                                                                                     Branch:
Reconnend ( 4):  we reconnend that the Administrator of EPA direct the Assistant Administrator for Solid Waste and Emergency
                Response tot

                ensure that state data collection and quality control efforts receive fully adequate support and include specific
                indicators related to data collection and verification in the agency's mechanism for monitoring atate performance;
                use probability sampling rather than a census of waste handlers whenever feasible for routine national data

-------
                                                     Potential FNFIA Mrnlmrnts                                    Pages    55
                                                               FT 1WO                                             Dates 09/13/90
                                                            Divlmion: Alt
  Buuamnlntion (Continued):
                 collection and quality control to ensure that EPA obtains the information necessary to develop regulations
                 efficiently and without unnecessary data collection burden;

                 ensure that the toxic chemical release inventory reporting system complements other hazardous waste data collection
                 efforts so that the data it provides on toxic chemical concentrations can be used to their maxima potential; and
                 finally,

                 amend federal recordkeeping and reporting regulations so that states are required to collect and provide standard
                 data eleawits in a disaggregated for* and hazardous waste handlers are required to provide sufficiently detailed
                 data.

 M:                     \         Office:                          Dlv:                              Brandt:

 Report/Audit:    Hazardous Waste: ERA'S Generation and Management Data Need Further Improvement
 Title

.Report/Audit Author: GENERAL ACCOUNTING OFFICE

 Publication Date: 02/01/90

-------
          UNI I fcU J> IM 11^ tM V IKUWMtN I AL. fKO I tc 1 ION AW,feNV.t
                      WASHINGTON, D.C. 20460


                         AIJG  30 IS90

                                                   OFFICE OF
                                          POLICY. PLANNING AND EVALUATION
Honorable John Glenn                        &rr(s
Chairman
Committee on Governmental Affairs
United States Senate
Washington, D.C.  20510

Dear Mr. Chairmant

     On March 19, 1990, the General Accounting Office  (GAO) issued
a final  report on the  Environmental Protection Agency's (EPA's)
system for collecting and producing information  on hazardous waste
generation  and management.   The  report is  entitled "Hazardous
Waste t    EPA's  Generation  and  Management  Data  Need  Further
Improvement* (GAO/PEMD-90-3).  The Agency has reviewed the report
and, pursuant  to Public Law 91-510,  I  am providing the Agency's
official. response to the report's recommendations.

GAP Recommendation

     GAO recommends  that  the Administrator,  EPA, direct that the
Assistant Administrator for Solid Waste and Emergency Response take
appropriate  steps  to enhance its  information system development
process  and  fully  ensure  that data collection efforts complement
each  other and  support  the program mission.    Specifically,  a
comprehensive  data collection plan  should be  developed.   Steps
should be taken to improve the assignment of  responsibilities for
planning  and  directing  the development  of information  system
components by increasing the authority of the  central  coordinating
office to develop data  collection efforts and ensure  consistency.
Finally, the life  cycle  management system  should be refined to
ensure the complete and detailed analysis and documentation of each
stage of the cycle for  major system  components.

EPA Response

     The Office of Solid Waste and Emergency Response  (OSWER) will
undertake the development of a comprehensive data collection plan,
or strategy, beginning in Fiscal Year 1991.  With respect to the
two later  recommendations,  various internal management measures,
such  as stronger  quality  assurance/quality control,  have been
incorporated into  OSWER operating procedures as well as ensuring
that  life  cycle management practices are  incorporated into all
systems development  efforts. OSWER is a  strong  proponent of total
quality  management,  and  this office will continue  to evaluate
practices and  improve  in  these areas.

-------
     OSWER is in the process of revising the Resource Conservation
and  Recovery Act  (RCRA)  biennial  report  requirements  (40  CFR
262.41, 264.75, and 265.75) to ensure that all states collect data
required by EPA on hazardous waste generation and waste management
practices.  This revised requirement will require states to report
data in  a standardized format,  requiring fewer EPA resources to
convert  .state  data to usable  format for national  reporting.
Standardized reporting   will allow  the Agency to  understand more
clearly the demographics of hazardous waste and management.  With
this data, the Agency will be able to report to its constituencies
more effectively and efficiently on  the status and progress of the
RCRA program.

     OSWER is developing data entry  and reporting software for use
by all  states in  collecting and sending EPA  biennial reporting
data.  When states  choose to use their own software,  the Agency has
developed "translator" specifications that will enable these states
to cross-walk  their data elements  into the standardized format.
In developing the software, the Agency has  followed all important
life cycle management procedures.

GAP Recommendation

     6AO  recommends  that  the   Administrator,  EPA,  direct  the
Assistant Administrator  for Solid Waste and Emergency Response to
take appropriate and feasible steps to fill remaining information
gaps, including

     (1)   the  volumes   of  waste  located  at   Comprehensive
     Environmental  Resource,  Compensation,  and  Liability  Act
     (CERCLA)  and  corrective action  sites  that will  ultimately
     require management  capacity,

     (2) the volumes of waste that will require management capacity
     under  proposed regulation  (including  the large  volumes of
     waste  expected from the cleaning up of  leaking underground
     storage tanks), and

     (3)  the potential disposal  capacity of salt  domes and other
   '  geological  formations  that  are  capable  of preventing  the
     migration of wastes.

EPA Response

     OSWER  has  added data  elements in the 1989  Biennial Report
forms that will enable those states using EPA forms to respond more
systematically   and  effectively  to  SARA  capacity  reporting
requirements.  In the long-term,  the Agency  plans to integrate the
Biennial  Reporting and  SARA  Capacity  processes,  as appropriate,
since information from the Biennial  Report directly  supports State.

-------
SARA Capacity estimates.
      M
     The Agency will update the regulatory analyses on corrective
action and CERCLA activities,  and EPA will gather more information
on  waste located  at  CERCLA  and  corrective action  sites.   By
amending the  Biennial Report  regulation,  the Agency  is closing
existing gaps in capacity information.

     At this time,  the Agency is unable to respond to the reference.
to salt domes due to a lack of information.

GAP Recommendation

     GAO  recommends  that  the  Administrator,  EPA,  direct  ther
Assistant Administrator for Solid Waste and Emergency Response to
assure the  use  of  the most appropriate measures of  the relevant
attributes  of  hazardous     waste  generation  and  management.
Specifically, quantitative measures should be used to measure waste
characteristics  (such as  those  needed for  assessing  management
capacity or waste  minimization),  and in  addition,  a true general
classification   system  should   be   developed   for   treatment
technologies.

EPA Response

     The Agency recognizes the need to assure the use of the most
appropriate measures or data elements of hazardous waste generation
and management,  including both  capacity and waste minimization.
The Agency will address these  issues in  the revisions  to  the
Biennial Report regulations.

GAO Recommendation
                  i
     GAO  recommends  that  the  Administrator,  EPA,  direct  the
Assistant Administrator for Solid Haste and Emergency Response to

     —  ensure  that  state data  collection and quality control
     efforts receive  fully adequate  support and include specific
     indicators related to data collection  and verification  in the
     agency's mechanism for monitoring state performance;

     —  use probability sampling  rather  than a census  of waste
     handlers   whenever  feasible   for >. routine   national  data
     collection and quality control to ensure'that  EPA obtains the
     information necessary to develop regulation  efficiently and
     without unnecessary data collection burden;

     — ensure that the toxic  chemical release inventory reporting
     system  complements other hazardous  waste data  collection
     efforts  so that the  data  it  provides  on  toxic  chemical
     concentrations  can be used to  their  maximum  potential;  and
     finally,

-------
Finding:   4.   OVERSIGHT COSTS WERE NOT BILLED AND COLLECTED In A TIMELY
             MANNER

         The  Region had not sought to recover  from PRPs costs for cleanup
         oversight as stipulated in settlement documents.   Regional
         management had given only limited attention to enforcing this
         settlement requirement.  In addition, project managers had made
         this a  low priority in their overall  handling of  individual
         sites,  and cost recovery packages were  not adequately or timely
         prepared to document costs claimed.   As a result, the Region had
         not  recovered at least $627,761  for the Superfund Trust Fund that
         could have been invested and earning  interest, thus lessening the
         amount  available for appropriation.   We recommend that the Region
         establish and implement an effective  system for the timely
         recovery of oversight costs involving Superfund cleanup sites.
         We also recommend that the Region initiate action to collect the
         $627,761 in oversight costs identified  in our report.

         A written response to the draft  report  was submitted by the
         Region  on March 27, 1990 (See Appendix  1,  without attachment).
         An exit conference was not held  with  Regional Officials since
         they stated that the written response adequately  presented their
         viewpoint.  We evaluated the Region's comments and revised the
         report  where appropriate.  Where differences still exist,  we have
         summarized the Region's comments and  our response in the ensuing
         paragraphs.  These comments were considered when  finalizing our
         report. The entire response is  available for review upon
         request.

Recommendation(s) :

        We recommend that you:

         1.    Establish and implement an  effective system  for  the timely
              recovery of oversight costs involving Superfund  cleanup
              sites.   Specifically,  require that mandated  settlement
              document itemized cost accountings are sent  to PRPs within
              90 days of the end of each  fiscal year.

         2.    Initiate action to collect  the $627,761 in oversight costs
              identified in our report.
                                        37

-------