540D05001
DRAFT, May 2005                                            OSWER 9355.0-105
     National Strategy to Manage Post Construction Completion (PCC)
       Activities at Superfund Sites Goes Out for Stakeholder Review
The Environmental Protection Agency's (Agency) National Strategy to Manage
Post Construction Completion Activities at Superfund Sites (PCC Strategy) is now
in draft form and is undergoing external stakeholder review. It has been posted
here to make the document available to interested parties while the review is
underway; however, the document is not final and should not be cited or quoted.
The strategy is expected to be finalized in late summer 2005.

The PCC Strategy is a management framework of goals, with recommended
approaches and initiatives, that is designed to provide greater assurance that
remedies put in place under the Comprehensive Environmental Response,
Compensation and Liability Act (CERCLA) remain protective over the long-term.
Through five goals, the PCC  Strategy provides information to regions, federal
agencies and stakeholders regarding the areas that may require continued focus
over the next five years.
Draft, do not cite or quote

-------
DRAFT, May 2005                                                      OSWER 9355.0-105

levels. ,

In the late 1990's, the Superfund program started to group the body of work that occurs after Site
Construction Completion into what is now known as PCC. Since more than 60 percent of the
final and. deleted sites were Construction Complete as of the  end of FY2004, the management of
PCC is becoming increasingly important. The main purpose of PCC generally is to ensure that
response actions continue to provide for the long-term protection of human health and the
environment PCC typically encompasses several activities that may be undertaken at a site
following the construction of a remedy. These activities may include, but are not limited to:

*      Long-Term Response Action (LTRA): Generally applies to the first 10 years of Fund-
       financed ground and surface water restoration.
•      Operation and Maintenance (O&M): Includes the activities required to maintain the
       effectiveness and integrity of the remedy.  Also includes continued operation of ground
       and surface water restoration remedies after LTRA.
•      Five-Year Reviews: Required by statute to assure protectiveness for any remedial action
       that leaves hazardous substances on a site above levels that allow for unlimited use and
       unrestricted exposures.  Five-year reviews are also conducted as a matter of policy in
       other situations.
•      Institutional Controls (1C): Using non-engineered instruments, such as administrative
       and/or legal controls, that typically minimize the potential for human exposure to
       contamination and/or protect the integrity of the remedy by limiting land or resource use.
•      Remedy Optimization: Performing reviews to improve the performance and/or reduce
       the annual operating cost of remedies without compromising protectiveness.
•      NPL Deletion: Removing sites or portions of sites from the NPL because no further
       response action is appropriate (not applicable to SA sites).
•      Reuse: Working with the parties seeking to redevelop Superfund sites to ensure that their
       activities do not adversely affect the implemented remedy.

A complete description of each of these PCC components, along with guidance and fact sheets, is
available at the Agency Superfund web site.4

The remainder of this document describes the five goals in the PCC Strategy and their
recommended implementation.approaches. The goals and implementation approaches are not
listed in any particular priority order, as they are all considered  priorities for the PCC Strategy.
        nttp://www.epa.gov/superfund/action/postconstruction/index.htm

 Draft, do not cite or quote                       -4-

-------
DRAFT. May 2005                                           .            OSWER 9355.0-105

                     Post Construction Completion Strategy by Goal           !!

                                                                             •i
Goal 1        Ensure that remedies remain protective and cost effective.

Section 121(b) of the Comprehensive Environmental Response, Compensation, and Liability Act
(CERCLA) states:                                                             .;

       "The President shall select a remedial action that is protective of human health'and the
       environment, that is cost effective, and that utilizes permanent solutions and alternative
       treatment technologies or resource recovery technologies to the maximum extent
    •s  practicable."                                                           -(

When remedies are selected, the statutory requirements of Section 121  are addressed in part by
applying the nine criteria provided for in the National Oil and Hazardous Substances Pollution
Contingency Plan (NCP).5  At all stages of cleanup, especially the PCC phase after remedies
have been constructed, the focus should be on assuring protectiveness and achieving results in a
cost effective manner, consistent with the statute and the NCP.           .          '

 The PCC phase of an NPL site cleanup typically involves the O&M, including monitoring, of
remedies. Engineered remedies that may require O&M include treatment, such as pump-and-
treat (P&T), bioremediation, air sparging, and soil vapor extraction; and containment, that may
involve vertical barriers (subsurface walls) and caps. To ensure the cost effectiveness and
protectiveness of these remedies often requires ongoing O&M, five-year reviews, monitoring,
periodic repairs, and, sometimes, replacement of remedy components.  Other remedies, such as
monitored natural attenuation (MNA), principally involve monitoring (but can include O&M,
repair, or replacement of monitoring wells). All of these types of remedies may require
managing and evaluating large volumes of monitoring data, and tracking  progress toward well-
defined requirements.  Clear remedy requirements are important in order  to assess ongoing
performance and the need for operational changes. .

Remedies are selected, designed, and constructed based on the best knowledge of site conditions
and technology available at the time. It is expected that most remedies will have a dynamic
nature over time. This can be related to factors such as additional characterization data, changing
site conditions, engineering or operating issues, technological innovation, or regulatory changes
(e.g., regulatory standards such as MCLs). These factors may warrant a reevaluation of previous
documented decisions, such as the remedy, remediation objectives, methods for determining
achievement of objectives, system design and operation, and monitoring frequency or locations.
These decisions are typically documented in the ROD, remedial  design, or Operationsi&
Maintenance (O&M) Plan for the remedy.                                       ;'
       5NCP §300.430(f)(5)(i)
Draft, do not cite or quote                       -5-

-------
DRAFT, May 2005                                                         OSWER 9355.0-105

Existing program guidance allows for remedy changes when appropriate.6 The guidance states
that a Record of Decision (ROD) modification is generally appropriate where significant new
information has become available that supports the need to alter die remedy. Other guidance also
encourages the regions to take a close look at, and modify as appropriate, past remedy decisions
where those decisions are substantially out of date with the current state of knowledge in
remediation science and technology, and, thus, are not as effective from a technical or cost
effectiveness perspective  as they could be.7 Remedy update types could include not only changes
in the remediation technology, but also modification of the remediation objectives, or
modification of the monitoring program. The objective  of Goal 1 is to enable the program to
assess changing conditions over time, and to modify remedy decisions and approaches as needed
to maintain the protectiveness and cost-effectiveness of the remedy.

Recommended Implementation Approach

1.1    Develop approaches for improving remedy O&M, monitoring, performance, and
       tracking.

       To determine if an operating remedy continues to be both protective and cost effective
       may require periodic evaluation of its operation and performance with respect to cleanup
       standards.  To assess progress toward achieving  cleanup standards may require that the
       reliable and necessary data be collected, managed, and analyzed  on a regular basis.
       Current program guidance is focused on five-year reviews8 and a few specific remedies,
       such as monitored natural attenuation (MNA)9 and pump-and-treat10. Five-year reviews
       are designed to assess the protectiveness of a remedy, but not necessarily whether it is
       operating efficiently or making sufficient progress to meet cleanup levels. Detailed
       evaluations (such as remedy optimization evaluations) for large systems may be necessary
       to properly optimize performance for the least cost.
       6"A Guide to Preparing Superfund Proposed Plans, Records of Decision, and Other Remedy Selection
Decision Documents," OSWER 9200.1-23P, EPA 540-R-98-031, July 1999,
http://www.epa.gov/superfund/resources/remedy/rods/index.htm

       7"Superfund Reforms: Updating Remedy Decisions," OSWER 9200.0-22, Sept. 27, 1996,
http://www.epa.gov/superfund/prograras/reforms/reforms/3-2.htm

       ""Comprehensive Five-Year Review Guidance," OSWER 9355.7-03B-P, EPA 540-R-OI-007, June 2001,
http://www.epa.gov/superfund/resources/5year/index.htra

       '"Performance Monitoring of MNA Remedies for VOCs in Ground Water," EPA 600-R-04-027, April
2004, http://www.epa.gov/ada/pubs/reports.html

       """Elements for Effective Management of Operating Pump and Treat Systems," OSWER 9355.4-27FS-A,
December 2002, http://www.epa.gov/superfund/resources/gwdocs/per_eva.htm

Draft, do not cite or quote                        -6-

-------
 DRAFT. May 2005                                                      OSWER 9355.0-105
                                                                             I
       Future efforts may include:                                              :
                                                                             't

       A.     Continue to provide tools to review and improve O&M (e.g., capture zone
              guidance and training, O&M check list).                           '
       B.     Continue implementation of the "Action Plan for Ground Water Remedy
              Optimization."11
       C.     Develop and implement tools to manage and analyze monitoring data.
       D.     Clarify and supplement current guidance on establishing intermediate and final
              remedy cleanup levels, ways to measure progress toward cleanup levels, and how
              to verify that they have been achieved (i.e., "exit strategy").          '
       E.     Continue to provide tools to improve the five-year review process.
       F.     Develop and implement tools to ensure that monitoring requirements at sediment
              sites are implemented.                                  '         j1
       G.     Continue implementation of long-term monitoring optimization efforts^for
              monitoring systems.                                             r
       H.     Continue to compile and prepare case studies of remedy cost and performance.
       I.      Provide additional PCC classroom and internet training to regions and states.
       J.      Focus technical support (e.g., Technical Support Centers) for remedial project
              managers on PCC activities.                                      '••
                                                                             it
 1,2    Encourage improved regional management of PCC sites.                  ..

       This effort is intended to help the regions and other federal agencies create processes to
       manage more effectively the increasing number of PCC sites. Regional and state staffs
       are responsible for managing and overseeing multiple complex site cleanups in the PCC
       phase. Effective management of these cleanups may require expertise in data ;
       management, system performance evaluation, system optimization, and innovative
       technologies. Some regional offices already have created special procedures for PCC
       sites.  For example, Region 10 staff members prepare short written updates of the status
       of PCC sites and brief an internal team on progress  and issues. Region 8 has a team of
       staff assigned to manage PCC sites. Region 3 is working with Headquarters to create a
       regional optimization and evaluation team consisting of technical staff, senior managers,
       and others to track and manage LTRA sites.                               •(
                                                                             h
       The activities in PCC may lend themselves to the application of an Environmental
       Management Systems (EMS) approach.12 An EMS  typically involves a continual cycle of
       planning, reviewing and improving the processes and actions that an organization
                                                                             i
       ""Action Plan for Ground Water Remedy Optimization," OSWER 9283.1-25, August 25, 200(4,
        . epa.gov/siaperfund/action/postconstruction/actionjlan.pdf    •
                                                                             >t
        ilttp://www.epa.gov/ems/                            '                   •   '

Draft, do not cite or quote                     . -7-                                P-

-------
DRAFT, May 2005                                                       OSWER 9355.0-105

       undertakes to meet its business and environmental goals.

       Future efforts may include:

       A.     Document regional processes for managing PCC sites.
       B.     Work with any regions that would like assistance to develop new procedures or
              improve their current procedures for managing PCC sites.
       C.     Develop a conceptual model of the PCC process to determine how the EMS
              process may be applied.
       D.     Pilot using an EMS approach for selected PCC sites.

1.3    Ensure proper consideration of PCC requirements in enforceable agreements with
       responsible parties and federal facilities.

       Some of the model documents  associated with Superftmd  may. not have fully anticipated
       issues emerging in PCC. These issues should be contemplated and planned for
       throughout the remedial process, and could include considerations associated with
       financial assurance, O&M, institutional controls, and reuse. The model language may
       need to be revised to include PCC considerations that may not have been included in
       previous versions.

       Future efforts may include:

       A.     Revise model enforcement documents.
       B.     Ensure language addressing operation and maintenance (including any engineered
              and institutional control portion of the remedy) is included in any future Federal
              Facility Agreement.
 Goal 2       Ensure that institutional controls required as part of the remedy are
              implemented and effective.

 The Agency generally defines institutional controls (ICs) as non engineered instruments, such as
 administrative and/or legal controls, that help to minimize the potential for human exposure to
 contamination and to protect the integrity of a remedy by limiting land or resource use.13 ICs are
 frequently used in hazardous waste cleanups to ensure that remedies remain protective over the
 long-term. As the cleanup pipeline has matured, many of the early assumptions about the
 effective identification, evaluation, selection, implementation, monitoring, reporting and
         "Institutional Controls: A Site Manager's Guide to Identifying, Evaluating and Selecting Institutional
 Controls at Superfund and RCRA Corrective Action Cleanups," OSWER 9355.074FS-P, September 2000,
 http://www.epa.gov/superfund/action/ic/guide/index.htm

 Draft, do not cite or quote                       -8-

-------
DRAFT. May 2005                                                       OSWER 9355.0-105

enforcing of ICs have come into question.  This has resulted in significant internal and external
concern about the long-term reliability of certain remedies and associated ICs. The fundamental
challenge presented by ICs is that, although the Agency frequently relies on ICs to ensure
protectiveness, the responsibility for implementation, monitoring, and enforcement is often under
the jurisdiction of other levels of government and private parties.

ICs normally are used specifically to ensure protection of human health and the environment, as
well as to protect the integrity of the remedy. The most critical aspects of ICs that affect
protection of human health and the environment typically are related to implementation,
monitoring and enforcement. Durable and effective ICs are critical to long-term protectiveness
and may enable more sites to return to productive use sooner.

One key challenge for ICs is ensuring coordination and cooperation outside the Agency. The
Agency,  other federal agencies, states, tribes, local government, and industry need to work
together  to ensure acceptable long-term effectiveness and durability of ICs.

Recommended Implementation Approach

Note that the Agency has separately developed a strategy to ensure institutional control
implementation.14  The approaches described below are consistent with the 1C strategy.1

2.1    Develop and ensure continued effectiveness of a national 1C Tracking System (ICTS).
                                                                               t

       An initial round of preliminary 1C data entry for Agency analysis was completed in the
       summer of 2004 for all of the construction complete sites on the NPL. This initial effort
       likely will be augmented as the tracking system is developed further.         ;

       Future efforts may include:                                               .;

       A.     Establish an approach and appropriate time line for population, continual updates,
              and maintenance of ICTS.                                         •.
       B.     Work further with federal facilities, states, tribes, local agencies and industry to
              establish the exchange of 1C information.

2.2    Ensure the effective implementation of ICs.

       Future efforts may include:

       A.     Use ICTS data and other site information to prioritize further evaluation of ICs at
       ""Strategy to Ensure Institutional Control Implementation at Superfund Sites," OSWER 9355;0-106,
September 29, 2004, http://www.epa.gov/superfund/action/ic/strategy.htm
Draft, do not cite or quote                       -9-

-------
DRAFT. May 2005   •                                                     OSWER 9355.0-105

              applicable sites.
       B.     Develop an approach for ensuring that ICs are successfully implemented at
              applicable sites.
       C.     Evaluate and address 1C issues at applicable sites.
       D.     Develop approaches to update decision documents to reflect selection and
              implementation of ICs.

23    Identify and implement process improvements to increase the reliability of ICs.

       Future efforts may include:

       A.     Improve PCC processes (e.g., remedial design, five-year reviews, O&M plans) to
              better ascertain overall 1C effectiveness.
       B.     Develop policy on how to critically evaluate the effectiveness of ICs both at the
              remedy evaluation stage and post implementation.
       C.     Provide training so that Agency staff, and external partners better understand ICs,
              ICTS, and related topics.
       D.     Educate, inform, and involve additional parties (e.g., local governments,
              communities) to support efforts to identify and resolve 1C issues.

2.4    Undertake other activities targeted at improving the use of ICs.

       Future efforts may include:

       A.     Develop guidance, "A Guide to Preparing Institutional Control Implementation
              Plans and Assurance Plans  at Superfund, Brownfield, Federal Facilities,
              Underground Storage Tanks, and Resource Conservation and Recovery Act
              Cleanups."
       B.     Develop guidance, "Calculating the Full Life-Cycle Costs of ICs."
       C.     Develop guidance on evaluating the effectiveness of ICs.
       D.     Work with Common Ground Alliance or other groups to develop a best practices
              guide for residual contamination, sub-surface remedy components, and excavation
              restrictions.
       E.     Continue to support "one call" demonstration pilots.15
 Goal 3       Assure adequate financing and capability to conduct post construction
              completion activities.
         One call is a state system to notify excavators of the location of underground facilities.  The "one call"
 pilots are designed to study the inclusion of the location of subsurface remedy components and contamination and
 use restrictions to the one call notification system.

 Draft, do not cite or quote                       -10-

-------
DRAFT. May 2005'                                                      OSWER 9355.0-105
Obtaining adequate financing for PCC activities at a site can be essential to ensure the] long term
protectiveness at that site.  These activities may include operating and maintaining leachate
collection systems or ground water contamination treatment systems. In other cases, the
activities may be more passive and may simply require adequate financing to be confident that
residual contamination (that is contained or requires land use restrictions) is managed in a way
that ensures the long term effectiveness of the remedy.                             :

With the exception of active restoration of ground and surface water for a 10-year period
(LTRA), the Agency is limited by CERCLA with regard to conducting O&M activities at NPL
sites. Thus, Superfund relies upon state governments, responsible parties, and federal facilities
for ensuring the O&M at sites. Nonetheless, the Agency is keenly interested in making sure that
implementation of the remedy at sites is supported by the community, the state, the federal
facility and responsible parties, and that all these players can be confident that long term
financing will continue to be available to maintain protectiveness at these sites.       '_.
                                                                              i
Two factors may point to the need  to further address financing of long term activities at sites: (1)
the budgetary constraints facing  local, state, and federal governments may affect their capability
to maintain and oversee remedies at sites, and (2) as more sites are entering the PCC phase of
cleanup, the potential scope of O&M costs are increasing.

State governments are required by CERCLA to assure that long term O&M is conducted at Fund-
financed sites. They are not required to provide all required O&M funding from state funds prior
to the start of O&M.  This  statutory feature can complicate long term O&M planning at sites,
since a stable long-term funding source often is needed to continue O&M.  The Agency and its
partners, the state and local governments, have just begun to identify a full complement of
funding mechanisms for financing sites. Innovative approaches and collaborative efforts need to
be explored and developed to promote a variety of ways to achieve reliable long-term O&M
funding.                                                                       ';
       /                                                 ,
Recommended Implementation Approach.-

3.1    Work to assure that Potentially Responsible Parties fulfill their O&M responsibilities.

       Future efforts may include:

       A.    Revise model financial assurance provisions in enforcement agreements and
             orders.
       B.    Develop sample letters of credit, bonds, and trusts.
       C.    Develop approaches to implement different financial assurance mechanisms.

3.2    Help states develop capacity to assure Superfund state cost share and O&M and
       methods to creatively finance both,

Draft, do not cite or quote                      -11-

-------
DRAFT, May 2005                                                       OSWER 9355.0-105
       Future efforts may include:

       A.    With support of states, evaluate current state efforts to develop long-term O&M
             funding. Identify obstacles to funding and share findings.
       B.    Revise model Superfund State Contract to better describe PCC considerations that
             may not have been included in previous versions.
       C.    Identify future O&M workloads for states, and associated funding needs.
       D.    , Collaborate with states on developing new strategies for creatively financing
             O&M.
Goal 4       Support appropriate reuse of sites while assuring remedy reliability.

The Superfund Redevelopment Program is designed to improve consideration of potential reuse
so that communities affected by some of the nation's worst hazardous waste sites can return them
to safe and productive uses. Likewise, other federal agencies envision reusing contaminated
properties and, in some cases, transferring properties outside of the federal government. While
cleaning up sites and making them protective of human health and the environment, the Agency
is working with communities and other partners to consider anticipated future land use in the
cleanup process. The benefits of reuse are most visible during the PCC phase, when remedies
have been constructed to be compatible with expected future use. Through the current
coordinated national effort, the Agency and its partners can better determine what the future use
of a site is likely to be, so that protective remedies are selected consistent with planned reuse,
where practical and feasible.

Recommended Implementation Approach

4.1    Reexamine sites to eliminate barriers to reuse wherever possible.

       Restrictions on site access and use are necessary at some, but not all, of the construction
       complete and deleted NPL sites, hi some cases, fences, warning signs, or other access
       and use controls, may be modified over time as we learn more specifically what is
       necessary to protect the engineered remedy, human health, and the environment.
       Furthermore, at some of these sites, public perception and a misunderstanding of the
       remedy may be precluding productive reuse. Under a new initiative, known as "Return to
       Use,"16 the Agency intends to systematically look at sites where real or perceived barriers
       may exist and work to overcome those barriers.  This can be done by sharing information
       or, when necessary, making modifications to the remedy through the administrative
       process (e.g., ROD Amendment or Explanation of Significant Difference) to change the
       way it is implemented.
         nttp://www .epa.gov/superfund/programs/recycle/rtu/index.htm
Draft, do not cite or quote                       -12-

-------
DRAFT. May 2005                                                       OSWER 9355.0-105
           \
4.2    Implement the Ready for Reuse guidance to answer questions about a site's suitability
       for reuse.                                          ,                    \

       Some Superfimd sites are on prime land. The location of industry and facilities that have
       prompted contamination problems is often at the nexus of transportation, utility and
       employment centers. The locations of these properties often warrant beneficial reuse, and
       such reuse may serve to provide active management of residual wastes over the long
       term. The "Ready for Reuse"17 determination is designed to give possible developers a
       user-friendly report on the environmental status of sites and portions of sites that are
       ready for specified uses. This effort will be accomplished concurrent with or in addition
       to the five-year review and does not require NPL site deletion or partial deletion.

       The Agency will continue its ongoing efforts to delete and partially delete sites; as soon as
       they qualify for deletion.  Sites typically can be fully or partially deleted from the NPL
       after all appropriate response actions have been implemented. It is important to note that
       sites may be "Ready for Reuse" long before NPL deletion.  Ground water restoration
       remedies, for example, may take many years to achieve cleanup levels; however, it may
       be possible to allow for reuse of surface lands once site construction is complete even if
       the site is still on the NPL.
 Goal 5       Improve site records management to better ensure remedy reliability.

 Many records associated with Superfund sites are needed for long into the future;  In those cases
 where wastes are left on site above levels allowing for unrestricted use and unlimited exposure,
 the records generally are critical for ensuring that the presence of these wastes is known. Agency
 strategies for identifying, capturing, managing and providing access electronically are currently
 being designed, and the Superfund Program is playing a leading role. Any electronic systems
 should complement, and in certain cases replace, paper-based processes. The Agency is moving
 toward capturing and preserving records online through the Superfund Document Management
 System (SDMS). SDMS is already in use in all 10 regional offices and will soon become
 available for Headquarters use.

 The Agency is working on a range of options that are designed to foster mutually agreeable data
 exchange formats and procedures between the Agency's and states' information systems. The
 Agency is prepared to address any concerns states may have directly and in an open dialogue to
 achieve results mat do not place undue burdens on those submitting records, or on internal
 systems management. When electronic records are transferred from  one organization to another,
 standardized authentication and chain of custody procedures may need to be established specific
 to digital media.                                                               ,1
       17"Guidance for Preparing Superfund Ready for Reuse Determinations," OSWER 9365.0-33, February 18,
2004, http://www.epa.gov/superfiind/programs/recycle/rfrguidance.pdf
Draft, do not cite or quote                      -13-                                '•

-------
DRAFT, May 2005                                                      OSWER 9355.0-105
Recommended Implementation Approach

5.1    Develop a standard methodology nationwide for record keeping, including electronic
       record keeping, that conforms both to Superfund program needs and the Agency's
       enterprise content management architecture.

       The Agency is embarking on a major information technology investment known as the
       "Enterprise  Content Management System (ECMS)." This is a very significant
       undertaking to electronically manage nearly all Agency information, including records.
       OSRTI is a  key partner in the ECMS project and intends to link SDMS to ECMS.  Most
       Superfund records initially will be captured into SDMS. The aim of the linkage between
       SDMS and  ECMS is to fundamentally transform the manner in which information is
       managed by the Agency. OSRTI is currently working to develop a strategic plan for
       records management. SDMS can already offer much of what will become ECMS.

5.2    Establish effective content "migration " strategies to assure accessibility to records in
       light of rapid and persistent changes in information technologies.

       Among the  challenges facing records production, capture, and management in this age is
       maintaining methods and practices that keep pace with rapidly evolving information
       technologies. When records are captured into digital systems it becomes critical to ensure
       that the content — often irreplaceable ~ is refreshed often enough to preserve its
       accessibility and use. Among the strategies for preserving access is reducing the
       complexity of what must be managed in the first place. For text documents, it is
       generally feasible to save the document  into an Adobe Acrobat Portable Document
       Format (PDF). This single step can greatly ease the task of migrating content from one
       hardware platform, and software version, to the next. Additional standards are pending
       for other records  formats, such as tabular data, geographic information systems outputs,
       web pages,  and audio-visual.  Another effective strategy for reducing file format
       complexity is modifying contract language to submit deliverables in specified formats,
       such as PDF. Guidance is currently being drafted to address both strategies discussed.
       Additional measures will be determined as we move forward toward implementation of
       electronic content in the Agency.
 Draft, do not cite or quote                      -14-

-------