                                         Superfund Post Construction Completion Activities
This Fact Sheet provides an abbreviated, one-page summary of the Superfund Post Construction Completion (PCC) activities.
The goal of these activities is to ensure that Superfund response actions provide for the long-term protection of human health and
the environment.  Readers of this Fact Sheet are encouraged to review "Superfund Post Construction Completion: An Overview"
(OSWER 9355.0-79FS) for more detailed information and a list of key references.

Operation and Maintenance (O&M) is an important component of a Superfund response to ensure that the remedy performs
as intended. Actions range from maintaining engineering containment structures (e.g., landfill covers) to operating ground water
remediation systems. Generally, O&M is the responsibility of the PRPs, States, or other Federal agencies. EPA is responsible
for ensuring that the work is adequately performed. EPA also retains funding and operating responsibility for Fund-financed
ground water restoration systems (called Long Term Response Actions) for up to 10 years prior to transferring these systems
to the States for O&M.  Ground water remedies generally require active management, and site managers should remain involved in
overseeing the performance of these projects during LTRA and O&M, Performance and monitoring data should be maintained to
support analysis and decision-making.

Institutional Controls are used to supplement engineering controls when residual contamination restricts the unimpeded use of
a site or a ground water aquifer. Institutional controls are intended to maintain the integrity of remedies and minimize the potential
exposure to contamination. Examples include easements, zoning restrictions, and deed notices. Institutional controls are
implemented during or immediately following remedy implementation consistent with the requirements of the decision document,
and should be maintained as long as needed to prevent exposure or protect the remedy. Site managers should work closely with
States,  PRPs, other Federal agencies, and local governments, as appropriate, to ensure Institutional controls are implemented,
maintained, and enforced.

Five-year Reviews generally are required by CERCLA or program policy when hazardous substances remain on sites above
levels which allow for unrestricted use and unlimited exposure. Five-year reviews provide an opportunity to evaluate the
implementation and performance of a remedy to determine whether it remains protective of human health and the environment
Generally, reviews are performed five years following the initiation of a CERCLA response action, and are repeated every
succeeding five years so long as future uses remain restricted. Five-year reviews can be performed by EPA or the lead agency for
a site, but EPA retains responsibility for determining the protectiveness of the remedy.

Optimization reviews can be performed to improve the performance and/or reduce the annual operating cost of ground water
remediation systems. Optimization reviews should be performed by an independent team of experts working with the site
manager and operator.  Recommendations can address the extraction well network, the treatment system, or the monitoring
strategy. Optimization studies can be initiated by EPA at Fund-financed sites, or by States, PRPs, or other Federal agencies for
sites under their lead. Recommendations should be reviewed and approved by EPA, in coordination with the State.  Optimization
reviews should be considered prior to transferring  ground water remediation systems to the States for O&M.

Deletion of sites from the National Priorities List (NPL) may occur once all response actions are complete and all cleanup goals
have been achieved. EPA has the responsibility for processing deletions with concurrence from the State. Deleted sites may still
require five-year reviews to assess protectiveness.  Also, if future site conditions warrant, additional response actions can be
taken, using the Trust Fund or by PRPs. Relisting on the NPL is not necessary; however, sites can be restored to the NPL if
extensive response work is required. EPA also has the ability to delete portions of NPL sites.  The Agency may use partial
deletions to designate uncontaminated areas of a site, or when portions of a site are cleaned up and potentially available for
productive use. Requirements for partial deletion are essentially the same as those noted above for a full  deletion.

-------