-------

-------
  em
                             FOREWORD
   UK?
   C 3.
    .!/ EPA has been undergoing a wave of heavy criticism for its
 contracts management practices since February of last year.  In
 response, the Administrator established a Standing Committee on
 Contracts Management to develop ways to eliminate practices that
 leave EPA vulnerable to such criticisms.  In addition, Assistant
 Administrators have established several workgroups, task forces
 and other groups in each Office working towards improving
 contracts management.

      The preparation of this document began last spring in
 response to a request by Office of Water (OW) Work Assignment
 Managers (WAMs)  and Project Officers (POs)  at OW workgroup
 meetings for guidance that focused on the day-to-day activities
 and responsibilities of being a WAM.  The manual was developed by
 six WAMs and POs from OW.  It has been reviewed by OW WAMs and
 POs,  Managers,  the Contracts Management Division in Cincinnati
 the Procurement Contracts Management Division at Headquarters,
 and others.   While it is not meant to be the final answer to
 every difficult question concerning contracts management, it is
 meant to offer some guidance and examples on how to better assure
 that your responsibilities as WAMs are being met.

      We  fully expect this manual to continuously be updated
 and/or revised as the Agency and OW change the way we manage and
 implement contracts.   We do hope,  however,  that this document can
 be  used  by WAMS with confidence knowing that the manual attempts
 to  provide a consistent approach to managing OW contracts.
 Although the manual is intended to provide as much useful
 information as possible,  WANs must recognize that this manual is
 not intended to. be the final word in contract management
 procedures.   WAMs should use this manual only as a guide and
 should work closely with their POs and other contract
 administration officials to ensure proper management of
 contracts.    Part of the responsibilities of a WAM is to be
 responsible for ensuring that the work assignment is administered
 by  EPA and the contractor not only to meet the needs
 substantively,  but also to be legally,  efficiently, and
 economically correct.

      I would like to especially thank Lonnie Finkel,  Susan
 Hancks, Anne Jaffe-Murray,  Beth Kimball and Ed Kramer, from the
 Office of Ground Water and Drinking Water,  and Frances Desselle
 and Patti Morris,  from the Office of Science and Technology for
 all of their time and effort in developing this manual.

       We  hope you find this manual useful and we welcome any
 suggestions  you  have  for improving it.   Please send any comments
 and/or recommendations£o Steve Wilson,  Office of Water,  WH-556.
                        V
  irtha G. Prothro, Acting Assistant Administrator
Office of Water

                                    HEADQUARTERS LIBRARY
                                    ENVIRONMENTAL PROTECTION AGENCY
  SEP   9 1993                       WASHINGTON, D.C. 20460

-------
                         Acknowledgment
The Office of Water would Uke to express its appreciation to the Office of
Emergency and Remedial Response and the Office of Solid Waste for developing
excellent Work Assignment Manager training manuals.   The Office of Water
used the Office of Solid Waste "Nuts and Bolts" and the Office of Emergency
and Remedial Response  "Work Assignment Manager Training Manual" as
models in the development of this manual.
                                                          £681

-------
 Purpose of  This  Manual
 This is not just another training manual nor is ft a replacement of the Contract
 Administration manual. Instead, this manual is meant to answer those unanswered
 questions that many Work Assignment Managers fWAMs) ask themselves - Where
 do I go to learn how to process, manage, and close-out a work assignment; Won't
 anyone help me? Well, the OW Manual "Staying on Course" is just the life preserver
 you need. H's chock full of practical advice and explanations on how to carry out
 your day-to-day responsibilities as a WAM.

 This manual is divided into five major chapters and at the end of each chapter are
 relevant attachments and forms. The five major chapters are:

      Chapter I: The Big Picture - provides common sense rules to keep in mind and
      lists the roles and responsibilities of all the individuals that are Involved in the
      contracting process.

      Chanter II: Charting the Course - discusses areas you should consider when
      planning the work you want the contractor to perform.

      Chapter III: Setting SaS - provides a detailed discussion on who is involved in
      writing  a  Statement of  work, including  examples on how to prepare an
      independent government cost estimate.  This chapter also lists guidelines for
      reviewing the contractor's work plan.

      Chapter IV: At the Helm - discusses the "do's and don 'ts " in managing a work
      assignment, including how to communicate with a contractor, what records to
      maintain, how to review a financial report, and what to do if the contractor's
      performance is unsatisfactory.

      Chapter V: Land Ahoy - indicates the steps  needed to close-out a work
      assignment due to completion, lack of funding, change in program priorities, or
      dissatisfaction with contractor performance.

 This manual also includes an Appendix which contains acronyms (Appendix A) and
glossary of terms (Appendix B) as well as other needed information that you will find
referenced in the manual.

      Happy Sailingl

-------
                                           DISCLAIMER
        in writing this manual,  OW has tried to focus on the major activities and responsibilities of Work
Assignment Managers (WAMs) and methods for making a WAM'sjob more understandable and efficient. Some
of the procedures outlined in this book are based on the rules contained in the Federal Acquisition Regulation
(FAR) and the EPA Acquisition Regulation (EPAAR) that govern the way we conduct our contract business,-
others are standardized practices that EPA has adopted to facilitate contract management, but which are not
required by rule.

        This book tries to distinguish throughout between the binding rules governing WAAf responsibilities and
activities and those which are EPA standardized practices.  OW undertakes to keep this book as current as
possible with frequent updates. However, the WAM must be responsible for ensuring that his or her actions fall
within and meet both the legally binding rules and current EPA practices.

-------
                                Table of Contents
Subject
Chapter     Page
Acknowledgement                                                           i
Purpose of This Manual                                                     ii
Disclaimer                                                                 Hi

Chapter I - The Bie Picture

Introduction                                                  '        II
Regulatory and Administrative Requirements                             I     2
Roles and Responsibilities of Key Personnel                              I     3
       Contract Managers                                              I     3
       Program Managers                                              I     6
       OWRole                                                    ,17
       Contractor                                                     I     7

Chapter II - Charting the Course

Introduction                                                          II     1
lite Basics About Contracts                                            II     1
       Statement of Work                                              II     1
       Contract Period of Performance                                  II     2
       Appropriation                                                  II     2
       Contract Availability                                            II     2
       Type of Contract                                                II     2
       Cost Per Hour                                                 II     2
       Overhead Rates                                                 //     3
Developing a Work Assignment                                         II     3
       What is the Nature of the Work Assignment                        II     3
       Does  Work Assignment Require ADP                              II     4
       Does  Work Assignment Require Government Furnished Property      II     6
       Does  Work Assignment Require Information Collection              II     6
       Is Contractor Required to Handle Confidential Business
           .  Information                                              II     8
       What Constrains Scheduling                                      II     8
       What Reports Do You Want                                      II     10
       Deh'verables,  What and When                                    II     10

-------
 Chapter III - Setting Sail
 Writing A Statement of Work
       Independent Cost Estimate
       Review and Approval of Work Plan

 Chapter IV- At The Helm

 Introduction
 Setting Up A File
 Day to Day Communication and Paper Trail
 Communication With Subcontractors and Consultants
 Communications With Task Managers) and Project Officer
 Contractor Communication and Frequency
 On-Going Activities
 End of Year Activities
 I Need to Make Some Changes
Adding Subcontractors and Consultants
 What to Do If the Inspector General Drops By
 Chapter V - Land Ahov!

 The Close-Out Process

Acronyms
 Glossary of Terms
 EPA Order 1900.1
 EPA Order 1900.2
 WAM Model Performance Standards
Labor Classifications (P-Levels)
Negotiation & Communication
 Confidential Business Information

Exhibit 2-1 Office of Water Contracts
Exhibit 2-2 ADP Form
 Exhibit 2-3 Quick Response Task Form
Exhibit 3-1 Work Assignment Package
Exhibit 3-2 OW Work Assignment Resource Estimating
Exhibit 4-1 Phone Log
Exhibit 4-2 Meeting Record
Exhibit 4-3 Work Assignment Status N otification
Exhibit 4-4 WAM DeUverables Report
Exhibit 4-5 Sub-Contractor/Consultant Approval Form
Exhibit 5-1 OW Work Assignment Close-out Request
Exhibit 5-2 Close-out Evaluation of Contractor
III    1
III    7
III    8
IV
IV
IV
IV
IV
TV
IV
IV
IV
IV
TV
1
1
2
4
S
S
7
11
12
12
14
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H

-------
   CHAPTER I
The  Big Picture

-------

-------
                     Chapter I
                 The Big Picture
INTRODUCTION	  1

REGULATORY AND ADMINISTRATIVE REQUIREMENTS  . .  2

ROLES AND RESPONSIBILITIES OF KEY PERSONNEL	  3
    Contract Managers:	  3
    Work Assignment Manager (WAM)	  3
    Task Manager  	  4
    Project Officer (PO)	  5
    Contracting Officer (CO)  	  6
    Contracts Specialist  (CS)	  6
    Program Managers:  .	  6
    Section or Branch Chiefs	  6

OW Role	  7
    Senior Procurement Official (SPO)	  7
    Senior Procurement Official Assistant (SPOA)	  7

Contractor	  8
    Subcontractor/Consultant . .  .	  9

Figure 1 -1  Rules of the Sea	1
Figure 1-2 Contracts Management Communication Flow	10

-------

-------
Chapter I

The  Big  Picture


INTRODUCTION
This chapter is designed to highlight key areas that you should keep in mind as a Work
Assignment Manager (WAM). The first area is what we like to refer to as the "Rules
of the Sea." If you follow these 12 rules, listed in Figure 1, you should avoid getting
yourself into troubled waters.
                      QIVB and Receive Help

                      Research Wall Before Beginning m work
                      Assignment

                      Specify Dellverables In Work Assignment

                      Do Not Accept Draft SOW* from Contractor

                      Do Not CUve Contractors Dollar Figures

                      Have Frequent Contact with Contractor and Treat
                      Them as You Would Treat Yourself

                      Do Not Personally Direct Contractors or Request
                      Specific Subs or Communicate Dlreetty with Subs

                      Maintain Complete Records end Flies

                      Carefully Review Monthly Progress Reports and
                      Request Additional Information If Needed and
                      Document Your Findings

                      Follow Gtovemment/Aaency Ethical Outdance

                      Be alert for actual or potential Conflicts of Interest
                      (COI), not only in your actions but alao In the
                      Contractor's

                      Ensure that your WA's do not ask Contractors to
                      perform Inherently Governmental Functions or
                      personal services.
Chapter 1
January 13,1993

-------
REGULATORY AND ADMINISTRATIVE  REQUIREMENTS

There are two regulations that dictate whatever we do as WAMS.  These are:

      o  Federal Acquisition Regulation (FAR) - Title 48 CFR Chapter 1: Governs all
      executive Agencies in their acquisition of supplies and services with
      appropriated funds.

      o Environmental Protection Agency Acquisition Regulation (EPARR) - Title 48
      CFR Chapter 15: Implements and supplements the FAR for EPA.

EPA recently issued two orders that provide guidance on use of contractors:

      o EPA Order 1900.1 - Use of Contractor Services: Provides information to EPA
      employees on avoiding personal services arrangements in their contract
      activities and provides principles for managing a contract.

      o EPA Order 19OO.2 - Contracting at EPA: Establishes Agency policy that
      prohibits  contracting  for certain  activities at EPA and implements special
      management and control  measures  when contracting for certain sensitive
      services.

A copy of the FAR and EPAAR may be viewed in the Senior Procurement Official
Assistant's office. EPA Orders 1900.1 and 1900.2 are contained as Appendix C and
D of this manual.

You also need to be aware of the following requirements for all WAMs:

      o  Contract Administration Course - Chapter  7  of the Agencies Contract
      Management Manual requires that an employee may not be a WAM unless
      he/she successfully completes a 3-day course, entitled Contract Administration.
      It is also recommended that a WAM take the Basic Project  Officer Course,
      though not required.

      o Recertification Course - The Agency requires a refresher course for ail active
      WAMs for whom more than three years has elapsed since they completed the
      Contract Administration Course.

      o Performance Standards/Position Descriptions - Chapter 7 of the  Contracts
      Management Manual mandates that the responsibilities for a WAM be contained
      in  both his/her performance standards and position descriptions.  Model
      Performance Standards are included in Appendix E of this manual.
Chapter 1                              2                        January 13,1993

-------
      o OW WAM Training Course - OW requires that WAMs complete a 1/2 day
      training course every two years that is based on this manual. The course is
      specifically geared toward the day-to-day responsibilities of a WAM.

ROLES AND RESPONSIBILITIES  OF KEY PERSONNEL

As a WAM, you need to be aware of not only your roles and responsibilities, but also
those for all the parties involved in the contracting process. This will enable you  to
understand the paperwork and communication flow as well as direct your questions
to the appropriate individuals. The remainder of this chapter discusses the roles and
responsibilities of those involved in the contracting process. Figure 2 on Page 10  of
this Chapter illustrates the communication flow among these individuals.

It is important to recognize that the Contracting Officer, (CO), is the ONLY PERSON
who has the authority to make legal and binding commitments for the Agency. As
WAM, your roles and responsibilities are in technical support of the CO's authority.

Contract Managers:

Work Assignment Manager (WAM)

The WAM is primarily responsible for the following:

a.    Developing the statement of work (SOW) and level of effort estimate for
specific work assignments (WAs).  The SOW must be within the contract's scope  of
work;

b.    Monitoring contractor performance on WAs including timing, costs and product
quality;

c.    Providing technical direction;
      Technical direction includes: 1) Direction to the contractor which assists the
contractor in accomplishing the SOW; and 2) Comments on and approval of reports
or other deliverables. ALL TECHNICAL DIRECTION MUST BE WITHIN THE WA SOW.

d.    Recommending WA amendments to the PO;
e.    Reviewing relevant portions of monthly technical and financial progress reports

Chapter!                             3                        January 13, 1993

-------
      and sending documentation of review to the PO. This includes verifying to the
      PO the "reasonableness" of contractor costs;

f.     Assisting the PO in voucher certification;

g.    Assisting the PO in evaluating the contractor's performance as required (e.g.,
      under Cost Plus Award Fee contracts);

h.    Keeping good files on all WA activity;  {PO and CO will have files, too.  WAM
      is responsible for information  that directly reflects a WAM's activities);

i.     Monitoring work being performed for Task Managers (if applicable);

Task Manager  (Only if applicable)
  . ^ „  ...,., ??       . *   . . *V. ,   ..
The Task Manager is an individual who assists the WAM in overseeing a particular
task or tasks under a WA as follows:

a.    Working with the WAM in planning the task(s) to ensure tasks are free from
      impinging on the sensitive contracting areas as described in EPA ORDERS
      1900.1 and 1900.2;

b.    Working with the WAM to ensure the task(s) are clearly written;

c.    Overseeing the task(s)  to ensure that the contractor completes the assigned
      work in a satisfactory manner;

d.    Maintaining files and documentation required to help the WAM monitor and
      evaluate the contractor's performance  on the task(s) and providing  such
      feedback to the WAM;

e.    Assisting the WAM in evaluating the contractor's performance related to the
      task(s) as appropriate (e.g., under Cost Plus Award Fee contracts);

f.     Providing feedback to the WAM as appropriate on portions of monthly financial
      and progress reports from the contractor related to the task(s) as to whether
      costs appear reasonable;

g.    Assisting WAM in reviewing deliverables from the contractor that are required
      under the  task(s) and notifying the WAM whether the product is acceptable.
Project Officer (PO)


Chapter 1                               4                         January 13, 1993

-------
 The PO is the primary technical representative of the CO authorized by the Office of
 Administration and Resource Management to provide technical oversight and direction
 on contract performance. As such, the PO must be technically proficient in the work
 being performed. The PO is responsible for the proper administration of the contract,
 including the following:
 a.     Monitoring overall contract performance;

 b.     Maintaining a tracking system regarding the source, status and availability of
       funds;

 c.     Monitoring contract administration by WAMs;

 d.     Facilitating interaction between WAM and contractor  (including coordinating
       the resolution of contract-related problems);

 e.     Reviewing technical and financial progress reports (and ensuring WAM review
       of contractor costs);

 f.     Monitoring use of government property;

 g.     Certifying vouchers;

 h.     Funding and forwarding all requests for WAs and contract modifications to the
       CO;

 i.     Receiving, reviewing and recommending approval to CO (with WAMs) all Work
       Plans and revised Work Plans submitted by the contractor;

j.     Maintaining contract files.
Contracting Officer (CO)

Only the CO has the final authority to approve WAs and contractor Work Plans.  The
CO responsibilities include the following:

a.    Signing a contract;

b.    Obligating funds (including reviewing and providing timely final approval of all
Chapter 1
January 13, 1993

-------
      WAs and contractor Work Plans);

c.    Establishing and maintaining communications with POs and contractors;

d.    Modifying contract terms or conditions;

e.    Coordinating resolution of contract-related problems, such as  cost claims,
      conflict of interest (COD, cost overruns, etc.;

f.    Terminating a contract;

g.    Accepting deliverables on behalf of the Agency (unless authority has been
      delegated to the PO and is stated in the  contract).

Contracts Specialist (CS)

The Contracts Specialist (CS) is responsible for:

a.    Serving as the major point of  contact  on the day-to-day activities  of the
      contract with POs and contractors;

b.    Reviewing and making recommendations to the CO on such things as ensuring
      that WAs are within the contract SOW, ensuring that LOE hours and dollar
      ceilings are  adequate and other aspects of WA and Work Plan review and
      approval.

Program Managers:

Section or Branch Chiefs

The Section or Branch Chief may be responsible for:

a.    Developing an annual contracts  management plan for the Section/Branch and
      ensuring this plan is implemented;

b.    Determining that the WAM has properly planned for contractor-supported work;

c.    Ensuring that WAM performance standards contain contract management
      performance criteria;

d.    Ensuring that the WAM has  current certification and securing any required
      training;

e.    Ensuring that the WA requests fit within  the  scope of the Section/Branch

Chapter 1                              6                         January 13, 1993

-------
       program priorities;

 f.    . Ensuring the timely obligation, tasking, and expenditures of funds allocated to
       the Section/Branch for contracts.

    The Section or Branch Chief supports the WAM in the technical management of
 the WA, and assists the  PO with oversight of contract activities in the  Section or
 Branch.

 OW Role:

 Senior Procurement Official (SPO)

 The SPO is the single focal point for procurement authority and accountability within
 each Assistant Administrator's Office and is responsible for:

 a.     Developing a long-term procurement strategy, in  concert with the  Office of
       Administration and Resources Management, that anticipates program needs and
       meets Federal and Agency procurement policy and standards;

 b.     Developing and implementing local action plans to meet program needs,
       fulfilling procurement policy and standards and being responsive to the Standing
       Committee report;

 c.     Reviewing controls over procurement decision and actions; ensuring timely
       identification of issues and prompt resolution at an appropriate level;

 d.     Overseeing  ongoing  procurement  activities  to   ensure   integrity   and
       responsiveness to program needs; ensuring both effectiveness and integrity of
       these activities, including responsible delegations and oversight arrangements.

 Senior Procurement Official Assistant (SPOA)

 The SPOA is the OW individual responsible for assisting  the SPO in the performance
 of the responsibilities identified above. The SPOA carries out such functions as:

 a.     Overseeing and developing OW contract-related training, in particular, WAM
       training;

 b.     Coordinating the gathering and distribution of up-to-date Agency contracts
       information and policy changes to OW Offices;

c.     Providing  guidance to OW POs on contract issues;
Chapter 1                               7                         January 13, 1993

-------
 d.     Updating the OW WAM manual on a regular basis.
 Contractor

 Without attempting to dictate the specific responsibilities of a contractor, in general,
 their role is as follows:

 a.    Evaluating the  WA to see if there is conflict of interest between the work
      specified in the SOW and  other work being performed;

 b.    Developing a work plan which  addresses all of the work to be performed and
      any other requirements stated in the SOW for the WA and including an estimate
      of all of the costs and professional hours involved in performing work;

 c.    Completing work in a timely manner to meet established milestones in an
      approved Work Plan;

 d.    Communicating regularly with  the WAM to ensure that the work performed
      reflects the needs of the WAM and the Agency;

 e.    Responding to changes in the SOW in a timely fashion to prevent additional
      costs to the Agency;

 f.    Managing the work to keep costs at or below the budget of the WA;

 g.    Maintaining accurate and up-to-date records on hours and dollars spent;

 h.    Advising the WAM when 75 percent of funds  and/or hours in a WA have been
      expended;

 i.     Preparing and  submitting periodic  (e.g., monthly)  technical and  financial
      progress reports and invoices as required by the contract;

j.     Reporting to the CO as soon as possible any new activity that may appear or
      present a potential COI to  the Agency;
k.    Maintaining the procurement  management information  required to inform
      office/site managers to ensure an "early warning" capability required to avoid
      contract mismanagement;

1.     Ensuring integrity of responses to audits and other external assessments of
      procurement activities.
Chapter I
8
January 13,1993

-------
Subcontractor/Consultant

      When the contractor does not have the in-house expertise and/or availability of
personnel to conduct work required in the SOW, the contractor may draw from the
subcontractors or consultants which are approved in the contract. Note however that
EPA does not have contractual authority to negotiate or communicate directly with
subcontractors or consultants or to request a specific subcontractor or consultant be
used for a WA. This is the role of the prime contractor.

The subcontractor/consultant is responsible for the following:

a.    Assisting the prime contractor in developing a Work Plan which addresses all
      of the work to be  performed including estimate  of costs and hours and any
      other requirements stated in the SOW for the WA;

b.    Completion of all work in a  timely manner in order to meet all established
      milestones in an approved Work Plan;

c.    Communicating regularly with the prime contractor to ensure that the work
      performed reflects  the needs of the WAM and the Agency;

d.    Responding to changes in the SOW in a timely fashion to prevent additional
      costs to the Agency;

e.    Managing their work to keep costs at or below the budget of the WA;

f.     Working closely with the prime contractor on all phases of the WA, including
      changes in costs, SOW, deliverables, schedule, etc.;

g.    Apprising the prime contractor of any problems in the work being performed
      including a possible conflict of interest to the Agency;

h.    Preparing and submitting information to the prime contractor to be included in
      the periodic technical and financial progress reports and invoices provided to
      EPA.
                                                               Journals, 1993

-------
    Senior
    Procurement
    Officer
    Managers
    Section/
    Branch Chief
        Contracts Management Communication Flow
                         Upper Level
                         Agency
                         Management
    Task
    Manager
SPOA
    \
                             Project
                             Officer
                                              Office of
                                              Aquisrtion
                                              Management

                                              Contract Officer
                            Contract
                            Management
                            Specialist
                             Global nnm and long Iwm ptannttg
Figure 2
Chapter 1
           10
/J,

-------
V
              CHAPTER jl

   Charting the Course

    OR
PLANNING THE WORK ASSIGNMENT

-------

-------
                       Chapter II
                  Table  of Contents
INTRODUCTION	  1

THE BASICS ABOUT CONTRACTS	  1
         Statement of Work (SOW)  	  1
         Contract Period of Performance	  2
         Appropriation	  2
         Contract Availability   	  2
         Type of Contract	 .  2
         Cost Per Hour   	  2
         Overhead Rates    	  3

DEVELOPING A WORK ASSIGNMENT	  3
         What is the nature of the Work Assignment?   	  3
         Which contract would be most appropriate for the job?
         	  4
         How does the Work Assignment break down into tasks?
           		  4
         What products are most  appropriate?	  4
         Is the Statement of Work affordable?	  4
         Does my work assignment require procurement of ADP
         Services?	  4
         Categorizing ADP Services	  5
         Requirements   for   Procurements   Needing  ADP
              Concurrences	  5
         Obtaining OW/OIRM Concurrence  	  6
         Does my WA require the use of Government furnished
         property?	  6
         Will my WA require collection of information?. ... 6
         Is the contractor required to handle Confidential Business
         Information (CBI)?	  8
         What constrains scheduling?   	  8

-------
     But I Need It Now!'!!!		
          Quick Turn-Around	
How often do you want a progress report from your
contractor?	9
When should interim and final deiiverables be planned?

Who should review your interim and final products?
What uses will your WA and  its products have?
Where You Can Go For Help On Various Issues?

Exhibit 2-1  Office of Water Contracts
Exhibit 2-2 ADP Form
Exhibit 2-3 Quick Response Task Form
 9
 9
10
11
10

-------
 Chapter  II
 Charting   the  Course
INTRODUCTION

Contractors cannot begin work before the work assignment (WA) and all the
accompanying documentation have been approved and signed by the Contracting
Officer (CO). Consequently, no matter how brilliant your idea, nor how urgent the
task, you cannot use a contractor's services without having an approved WA in place.
Among the many responsibilities you will assume as a work assignment manager
(WAM), the first, and perhaps the most important, is developing and writing a WA
that clearly and concisely explains to the contractor the type of work you want
completed, the amount of time and money it  should take to complete, and when the
product(s) should be delivered. All WAs you submit to your Project Officer for review
and approval must contain the following documents: (1) cover sheet; (2) WA review
form;  (3) statement of work; (4)  independent  government cost  estimate; (5)
procurement request; (6) WAM designation form 1900.65, when necessary; (7) ADP
concurrence form, when necessary; (8) CBI  Review Form and (9) QA/QC Form, if
necessary. (Forms are covered in Exhibit 1 to Chapter III)

THE BASICS ABOUT CONTRACTS

Before you start developing and writing your WA you should know certain information
about the contract you are going to use to ensure it is the best vehicle for completing
the work you have in mind. The following is a short discussion of these key items.
Each of these items are specific to each contract and can be obtained from the Project
Officer (PO) managing the contract. A list of OW's current contracts, their dollar
values, periods of performance, and respective POs are provided as Exhibit 1 of this
Chapter. The SPOA will also have a copy which you may review.

      Statement of Work (SOW)

      Your WA must fit within the SOW of the contract. Your WA will not be
processed by the PO unless you include a completed WA Review form that cites the
section of the contract SOW under which the scope of your WA falls.  For a copy of
the WA Review form refer to the Exhibits at  the end of Chapter III.

-------
      Contract Period of Performance

      The contract period of performance indicates the life of the contract,  if a
particular contract ends before you expect to complete your WA, you may want to
select another contract to avoid the paperwork involved with moving money from one
contract to  another (i.e. deobligating and  reobligating funds).  Once money is
deobligated, it becomes available to other offices and you run the risk of losing this
money before it can be reobligated  to a new contract.

      Appropriation

      Appropriations are allocated to EPA program offices as one-year money,  two-
year money and no-year money.  If  your appropriation expires before you expect to
complete your WA, you may want to look into another funding source. You cannot
put funds into a WA which has a period of performance which estends beyond the life
of the appropriation.  (You  can  usually tell by the structure  of the number (i.e.
682/30108) is FY 92-FY93 money). If you are not sure, ask your PO.

      Contract Availability

      Prior to completing paperwork for your WA,  you should first check with PO to
ensure that the contract has enough hours and funding left (i.e., below ceiling) for the
contractor to  perform the work. A list of OW Contracts is provided at the end of this
Chapter.

      Type of Contract

      There are two types of contracts in general use in OW: Cost Plus Fixed Fee
(CPFF) and Cost Plus Award Fee (CPAF).  The major difference  between the two is
the method of awarding the contractor's fee, and when that fee is paid.  A CPAF
contract requires you to evaluate the contractor's  performance on each WA you
manage under the contract in addition to the regular monitoring of performance.
Typically, you will have to rate the contractor's performance between 2 and 4 times
per year.  In  contrast, a CPFF contract requires you to evaluate the contractor's
performance only once, when the work is completed.

      Cost Per Hour

      Each contract has an average cost per hour. This rate should be multiplied by
your estimate of the number of hours required for the WA and then add in an estimate
of Other Direct Costs (ODCs) and travel required by the contractor, to determine  your
estimated total cost.  ODCs are costs other than technical hours (e.g.,  postage,
reproduction, supplies, and equipment).  For estimating purposes use the ODCs
identified by your PO.
Chapter II
January 13,1993

-------
      Overhead Rates

      The overhead rates added on to the cost of hourly labor and ODCs include:

1.    Full and  part time overhead, which  is the cost of the benefits  for the
      contractor's personnel.  These cost are direct percentage of the labor hours
      expended for the month (e.g., 60%).

2.    General and administrative costs (G&A), which are a fixed percentage of most
      direct charges (e.g., 18.5%). These costs are based on projected costs and
      can be changed (upward or downward) when actual costs are incurred.

3.    Fee, which is the contractor's profit. It is fixed for a CPFF contract but subject
      to EPA's evaluation for a CPAF contract.  The fee for either type of contract
      usually does not exceed 9% of the direct labor hours expended for a particular
      period of time.

      These rates are considered confidential business information (CBI) and should
always be secured. See your PO when you are ready to estimate costs for a WA.
Your PO may provide you with an average labor rate already loaded.

Other Material and Information to Get From Your PO

1.    The approximate dates of receipt and turnaround for monthly progress reports.

2.    The cover sheet and all WA forms.

3.    Forms for approving work plans, monthly progress  report, etc.

4.    Criteria for evaluating CPAF contracts, if applicable.


DEVELOPING A WORK ASSIGNMENT

The following will help you think about what should be included in your WA:

      What is the nature of the Work Assignment?

      Is it rulemaking?  Standard setting? Site investigation? Sanitary Survey? Are
there  policy-setting ramifications?  Will the nature of the effort rule out certain
approaches and necessitate  others? What kind of experts are required? Does your
supervisor agree the task should be done?  How quickly should it be completed?



Chapter 11                              3                         January 13,1993

-------
      Which contract would be most appropriate for the job?                  ;

      Review the scope of work of each OW contract to determine the range of skills
and services each one has agreed to deliver. The PO for each contract can assist you.
You must cite in your WA, where it fits in the contract scope of work.

      How does the Work Assignment break down into tasks?

      Sample tasks might include background investigations, data collection, logistics
planning,  on-site  analysis, developing recommendations.   Are any of these task
defined as "inherent government functions"  refer to Chapter 3 and Appendix C & D
for a definition of "inherent government functions." It is always important to define
division of responsibilities among  the  government and  the contractor.   Special
contraols will be necessary for any activities considered "sensitive" or "vulnerable."

      What products are most appropriate?

      Although you may not be certain yet, have some ideas in mind.  Review the
goals stated in the SOW. Who is the audience? Do you want a background research
or testing for a regulation or standard? A report?  A briefing? The type of deliverable
you select will affect the amount, pacing and mix of resources required.

      Is the Statement of Work affordable?

      Determine the full range of resources needed to complete the tasks in your
SOW.  Resist the temptation to start with a projected total cost and fit the activities
to it. Instead, cost out the job the way you think it ought to be performed, estimating
the price of each line item under each task.  This approach will  keep your estimates
"honest" and accurate.

      Be realistic and thorough. How many technical hours do  you estimate will be
      needed to complete the task(s}? How much work do you want completed by
      senior staff? How much work do you want completed by junior staff? Do you
      want  senior  staff  to  provide  Quality Assurance/Quality Control  on all
      deliverables? Do you need specialized technical expertise? It'll cost you. Once
      you make this kind of analysis, add up the  estimated costs to come up with a
      total for professional hours.

      Does my WA require procurement of ADP  Services?

      There are various laws, regulations, and guidelines that must be followed when
you request automated data processing (ADP) services in your WA. The ADP services
may be incidental to the delivery of a non-ADP  product (such  as a report) or may
result in ADP products (such as software or databases).
Chapter II
4
January 13,1993

-------
Categorizing ADP Services

You must always indicate on the WA Review Checklist (Example in Chapter 3, Exhibit
3-1) whether you are requesting the contractor to provide ADP services.  If the
answer is yes, your WA must be accompanied by the ADP Concurrence Form.  (Refer
to Exhibit 2-2 at the end of this chapter for a copy of this form).

The first box on the top of the form contains descriptions of three categories of ADP
services that may be provided by a contractor. Only the last category requires ADP
concurrence.  If your SOW requests a contractor to develop a computer program or
compile a  data  base,  you  must  receive ADP  concurrence  from the Office of
Information Resource Management (OIRM). Just to make sure you understand how
this works, let's review the three categories.

First, a procurement falls in category A if it does not request a contractor to provide
ADP services.  Concurrence is not required.

Second, a procurement falls in category B if the ADP services requested are incidental
to the delivery of  non-ADP products.  Computer programs and/or databases can be
developed, but they cannot be used for subsequent work. Concurrence is not required.
An example of a procurement in category B is a WA that requires the contractor to
conduct a survey  and produce  a report. The contractor may enter the survey data
into a database and create  programs to analyze and report the data.  The final
product, however, is a survey report.  This request falls within category B as long as
the computer programs and databases are not used in any fashion after the report is
complete.

Third, a procurement falls in category C if the WA requests the contractor to develop
an ADP product, or if the databases and programs developed, while incidental to the
completion of non-ADP products, are expected to be used for subsequent work. In
the example discussed above, the WA would fall in category C if you planned to use
the survey  data in another database or as part of a continuing study.

Requirements for  Procurements Needing ADP Concurrences

When your SOW requests a contractor to provide ADP services you must make sure
the work is completed in conformance with EPA policy.  In addition, all software that
is expected to be used by EPA or distributed outside the Agency must undergo testing
by an independent third party.

Obtaining OW/OIRM Concurrence

When your SOW does not request ADP services from a contractor, simply check the
appropriate category and sign the ADP Concurrence form.  No OIRM review will be
   i

Chapter II                              5                         January 13,1993

-------
required. The Contracts Office will accept the certification and will not require any
further ADP concurrences unless the scope of  work  is inconsistent with  the
certification.

         While SOWs that fall into categories A or B will be processed without OIRM
review, there are periodic audits to ensure compliance with this policy. When  your
SOW clearly includes requests for ADP services from a contractor, OW SIRMO and
OIRM  concurrence must be obtained before the WA is submitted to the Contracts
Office. You PO will provide the name of the individual in OIRM who will review the
ADP concurrence form. The Contracts Office will not process the procurement until
all concurrences have been obtained.

       Does  my WA require the use of Government furnished property?

       If the contractor will be required to use government furnished property or
acquire property with contract funds, you  must complete a  "7-Point Justification of
Need" which includes the following:

       1. Identify the specific program and project for which the property is required.

       2. Identify the type, quantity and estimated cost (including any transportation or installation
             costs) of each item of property required.

       3. Explain why the property is necessary for contract performance.

       4. Explain why ft is in the interest of the Government to provide the property rather than to
             require the contractor to provide the property at no direct cost to the contract.

       5. Identify the location of the contractor's facility at which the property will be used, and the
             contractor's personnel responsible for acquisition and management of the property.

       6. For property to be acquired by the contractor at Government expense, include a certification
             that no in-house excess property is available and include the concurrence of the local
             property office.

       7. For equipment to be acquired by the contractor at Government expense (e.g. Purchase of
             a PC), include a lease vs. purchase analysis.
      Will my WA require collection of information?

      Under the Paperwork Reduction Act (PRA), you must prepare an Information
Collection Request (ICR) to obtain Office of Management and Budget (OMB) clearance
for any activity that will  involve collecting substantially the same information items
from ten or more non-Federal respondents in a given year (e.g., owner/operators of
Chapte
January 13, 1993

-------
public water systems, underground injection wells).  You might need to prepare ICRs
for:

1.    Information requirements in a  proposed rule (e.g., monitoring, reporting,
recordkeeping).

2.    Other information collection activities (e.g.,  studies or surveys, application
forms, audits, and similar standardized data collection activities).  OMB regulations
apply to any "collection off information" as broadly defined in 5 CFR  1320.7. The
definition includes:

      a.    Written report forms, application forms, schedules, questionnaires, or
reporting and recordkeeping requirements.

      b.    Other means of collecting information, like rules or regulations, policy
statements,  information requests,  bulletins,  instructions,  contracts,  planning
requirements,  circulars, requests  for  proposals  or   other  procurement, oral
communications, labeling requirements, and telecommunication requests.

      c.    Questions,posed to agencies,  instrumentalities, or employees of the
United States, if the results are to be used for general statistical purposes.
             1.    When you request information from fewer than ten persons in a
      given year, except that:

                  (a)   a collection requirement contained in  a rule of "general
      applicability" is presumed to involve ten or more persons. OMB defines general
      applicability as the potential to affect  ten or more persons; consequently,
      collection requirements  in very few  rules will fall under  the  less than 10
      exemption.

                  (b)   a collection addressed to "all or a substantial majority" of
      an industry is not exempt.

             2.    When undertaken as part of: a criminal investigation; a civil action
      to which the government is party; or an administrative action/investigation of
      specific persons or entities, but only after a "case file," or its  equivalent, is
      opened.

            3.    When it falls under one of the exceptions to the definition of
      "information"  contained  in 1320.7(j), for example:
Chapter II
January 13,1993

-------
                  (a)   Facts  or  opinions submitted  in  response  to general
      solicitations of comments from the public, published in the Federal Register or
      other publications;

                  (b)   Examinations designed to test the aptitude, abilities, or
      knowledge  of the  persons tested and the collection of  information  for
      identification or classification in connection with such examinations; or

                  (c)   Facts  or  opinions obtained through  non-standardized
      follow-up questions designed to clarify responses to approved collections of
      information. •

      If you are still not sure whether you need OMB clearance, contact your PO.

      When your  ICR is approved, you will receive an ICR Number, this number
should be noted in the WA and on any form the contractor may  use to collect the
information.

      Is the contractor required to handle Confidential Business Information (CBI)?

If a WA requires use of  CBI, the contractor shall abide by all EPA requirements and
stipulations. This includes adherence to the  CBI regulations at 40 CFR Part 2. It is
also important for you to ensure that your contractor is authorized access to CBI. The
contractor shall identify in the Work Plan budget all  estimated  costs for CBI
requirements as specified in the contract. Refer to Appendix H  for more detailed
information on CBI.

      What constrains scheduling?

      Identify the internal schedules that delivered products or closeout should meet.
Do the schedules of related efforts conflict with your timetable? Sometime it is useful
to work backwards from the deadline. If no particular date is urgent, decide how long
the WA should reasonably take to finish. (See Figure 2-1 at the end of this chapter).
Many events can affect  your schedule. Some can be controlled, most cannot. It is
impossible to extract rules of thumb on how  long certain types of work should take
to complete;  the variables  involved are just  too  diverse.   Certain "institutional
processes" will delay the progress of your work. The following are some guidelines.

      •     Add 2 weeks for review inside EPA. If the product is going to the
            regions  add 1 more week.
      •     Check the  regulatory schedules to determine the schedule for
            rulemakings or call your lawyer.
      •     Projects demanding public participation should allow  45 days.
Chapter 11                               g                         January 13, 1993

-------
      •     If you want the states to review the document you are producing
            count on it taking at least 1 month.
      •     if you need (or desire) review by other federal agencies add 1
            month to the schedule.
      •     If your project  is to be reviewed during August, or between
            Thanksgiving and New Years, add at least 2 weeks.
      •     Planning  a  large event like a series of workshops or a national
            conference, allow at least 3 to 5 months.
      •     The  contract cycle will  also  affect  how you  schedule the
            completion of various task(s) in your SOW.
      •     If you  are producing  a  document allow 2  to  4  weeks  for
            Government Printing Office or EPA printing, after the camera copy
            is delivered.

      But I Need It Now!!!!!

      Quick Turn-Around

      - In some instances, when an office performs several functions on a continuing
basis, one WA will be written to allow for tasks to be performed as needed.  It is
important that you contact your PO to learn of any specific quick turn-around WAs
and obtain a copy of the scope of work permitted under these WAs.  Requests for
work to be performed should be submitted to the PO using an  OW Quick Response
Task Form.  Refer to Exhibit 3 at the end of this Chapter for a  copy of this form.
      - You will need to supply a clear statement of what you need and a deliverable
schedule for you quick turn-around request. These tasks are usually designed to serve
specific purposes. They may be limited by number of hours and dollars.
       '!./! *j  -F"  S: ' '. \ ' *•.*' I
       eaouf ces, make cot
       ivi«:wXUA*li;--^«i*»i*iti4ii
         '•z,f.t.^ft ;-'•"••"•.-.'& "!•, ;*"« /*••
Chapter II
January 13, 1993

-------
      How often do you want a progress report from your contractor?

      Monthly  progress reports are  obligatory Agency-wide, but you  may have
reasons for wanting more frequent feedback.  Your WA may focus on a currently
"hot" topic or may even be important to senior managers. It may be extremely time-
sensitive. Or you may simply be unfamiliar with the contractor and choose tighter
control until  good performance is  proven.   Remember, requirements like weekly
financial  status reports and bi-monthly meetings have costs associated with  them.
You must decide whether stricter control is worth the hours and dollars it will cost.
It may well be.   Plan and ask for it up front, before the WA is approved by the CO.
Your WA does not become effective, and hence the contractor cannot begin  work,
until the  CO approves and signs it.

      When should interim and final deliverables be planned?

      Schedule them thoughtfully. Planning interim products as well as final ones will
help you  conceptualize the phasing and pacing of the work. At the same time, you
needn't spell out every step the contractor should take. Here's a good rule of thumb:
If an interim product is (1) critical to proper formulation of the final deliverable; (2)
essential to decision-making, or (3) will receive widespread scrutiny, include it in the
WA document.

      Who should review your interim and final products?

      Determine who  has to participate in the review and approval process early on
to determine how long it will take.  Your division may require that you make a formal
request for review and approval.  Even if this is not the case, you should at least
discuss this with your Section or Branch Chief. Be sure to invite colleagues doing
related work (from other offices as well as your own) to review your products.
Regardless of the type of work you hope to accomplish with your WA, the following
may have to be involved in the review and approval process: (see your PO for your
specific Division requirements)

      •     Your Section and/or Branch Chief
      •     Your Division Director
      •     Your Project Officer
      •     Your Contracting Officer

      If your SOW includes computer applications, OIRM must review your WA.  If
      your SOW includes state questionnaires, and the like, the  Office of External
      Affairs and OMB must review your WA in light of ICR requirements (refer back
      to  Page 7).
Chapter II
10
January 13, 1993

-------
      What uses will your WA and its products have?

      Consider how the product of your WA could be put to work within OW.  How
will it strengthen the Office's mission? Be ambitious for your work in the sense of
making it as widely useful as it can be. To what levels should results be elevated?
How can your WA involve and boost the effectiveness of other office projects?

      Where You Can Go For Help On Various Issues?

      Early in the process, the PO of a contract in which you are interested will be
able to assess whether the task you are proposing fits under the scope of work. She
has current information on the contract's scope of work, personnel, and skills, as well
as the contract's financial status, level-of-effort, rates, and staffing mix. Your section
or branch chief can review your WA  for consistency with OW's mission and the
Office's Operating Plan.  Other WAMs  can provide model scopes of work, examples
of delivered products, and other relevant information.  They know what has already
been done.
Chapter II
11
January 13,1993

-------
2-1




2-2



2-3
         Chapter II






          Exhibits





Office of Water Contracts



ADPForm



Quick Response Task Form

-------

-------
                                                                                                EXHIBIT 2-1
    N
                    m
                               CO CD
                                                                      O «
                                                                                         in
                                                                                              (M
i!
                      CO
                                            s
                                            CO
                                              o
s
                                                      CO
              2
8

£
m
                                                                                 CO
s
                                                                                                    CO
                                                                                                      CO
CO
H-

Q

<

rr
         o
         o
         *    8
         m
         c
              ui
o

UJ
O

u.
                                      p
        CO
                                                                 CO
     CO
                                                                                   CO
                                           i
        CO
                                   CO
                                             <%«

                                             i
                                             Eo

                                             i
                                                CO
                                                   CO
CO
                                                         CO
                                                           CO
CO
                                                                 CO
                                                                   CO
                                                                                                           CO
                      09
                                                   CO
                                                      CO
           Ifc


           8
     •b

     8
                                                                           o
                                                                                                      u
                                                                                 111
                                                                                      CO
                                   CO
                                                                                                         8
                             CO

-------
                                              EXHIBIT 2-2
                    Office of Water
              ADP CONCURRENCE FORM
I.  CERTIFICATION

ADP services will be performed as part of this procurement.
Computer programs and/or data bases are products of the effort
OR may be used after completion of this procurement.
WAM Signature                Date    Contract # WA #


II.   ADP CONCURRENCE

Office of Water:


	 Approve  	Disapprove     	Comments Attached
SIRMO, Office of Water                      Date

Office of Information Resources Management:

	Approve  	Disapprove     	Comments Attached
Director, Program Systems Division, OIRM      Date

-------
     Environmental Protection Agency
          Qlfice of Waiter
      Oulok Response (QR) Task
                                               EXHIBIT 2-3
     WANo:
     Task No.
                                   OR Task No:
Labor Hours
     Start Date
Tilk
     End Dale
 Description:
Deliverables
Due Date
Work Assignment Manager
Task Manager	

-------

-------

-------
       CHAPTER III
      Setting  Sail
            or
Writing the Work Assignment
and Approving the Work Plan

-------

-------
                Chapter III
                Table of Contents
INTRODUCTION
1
WRITING A STATEMENT OF WORK	  1
    Suggestions for Writing Your Statement of Work  ...  3
    Completing an Independent OW Cost Estimate	  7
    Review and Approval of Contractor's Work  Plan and
    Budget	  8
    Recommended Contents of a Work Plan	  8
    What to Look for in a Work Plan	  8
    Final Approval of the Work Plan  	  9

    Exhibit 3-1  Work Assignment Package (15 Pages)
    Exhibit 3-2 Work Assignment Resource Estimating Samples

-------

-------
Chapter III

Setting    Sail     or     Writing     the     Work

Assignment and Approving the  Work Plan


INTRODUCTION

One of the most critical jobs a WAM will undertake is the development of a Statement
of Work (SOW). Implementation of a work assignment (WA) begins with the WAM's
preparation of the WA request. This is sent to the Project Officer (PO) who reviews
the package for accuracy and acceptability. If no changes or clarifications are needed,
then it is forwarded to the Contracting Officer (CO) for issuance to the contractor.
*

in preparing the SOW, the WAM must take care to keep the assignment within the
general scope of work of the contract. Assignments must be specific in terms of end
product(s) required, and number and types of reports to be submitted.  Any other
specific requirements involved must also be specified in the WA.  No specific cost
estimates are to be forwarded to the contractor. The contractor must have all the
information necessary to begin work immediately and to prepare a work plan. The
period of performance will generally be from the effective date of the WA (signed by
CO and received by contractor) until the completion date  specified by the WAM.
Performance cannot extend beyond the current contract base or option period (if you
don't know these dates, check with your PO).  The level of effort specified will be
based upon the estimated number of direct labor hours required to perform the task(s).
The contractor should communicate with the WAM and the PO within five days after
receipt of the WA to determine if a meeting is appropriate before final submission of
the Work Plan, (check with your PO for any specifics in the contract you are working
through)


WRITING A  STATEMENT  OF WORK

You may want to use  the following outline when writing your SOW. As you become
more accomplished at developing and writing SOWs you will probably want to tailor
future SOWs to your own specific needs. As you develop more sophisticated ways
of writing SOWs, share them with your colleagues.  In the meantime, feel free to
develop your SOWs with the outline provided below. Remember, writing the SOW
is an inherently governmental function. The contractor is not to participate in any
way in the development of the SOW.
Chapter HI
January 13,1993

-------
 Outline and Format for the SOW                                                         -

 A.     TITLE
        o     Make  H  short,  descriptive  and  the  same  as  on  the WA  Request  cover
              form (Refer to Exhibit 1 at the end of this chapter).
 8.     ESTIMATED PERIOD OF PERFORMANCE
        o     Effective date of WA ICOs Approval) until (insert date).   Cannot extend beyond
              effective contract option period.
 C.     WORK ASSIGNMENT MANAGER
        o     Include the  full  name,  address (including room number and mall code), and
              phone number of the person who wBI be responsible for management of the WA.
 D.     BACKGROUND INFORMATION
        o     Provide a general description of the program and the taskfs) to be completed.
        o     Explain why the task(s) need to be completed.
        o     Explain the  relationship  between this taskfe}  and other tasks being completed
              under the SOW.
        o     Discuss the overall program or project's objectives.
        o     Discuss the specific objectives of this task(s).
 E.      STATEMENT OF WORK
        o   ,  Provide a detailed description of work to be performed.
        o    •• Identify and number the specific taskfs} to be performed by the contractor.
        o     Provide specific direction on any methodologies to be used.
        o ,    Provide information on applicability of specifications and standards,
        o .     Clearly state the  period of performance for each task and  the delh/erables.
        o     identify any contractor travel requirements.
 F.      SPECIAL REPORTING
        o     Contracts routinely require a  work plan  (including  OAK  monthly progress and
              financial reports and a final report for each WA.  Specify any other specific reporting,
              quantities and addresses.
 G.      GOVERNMENT RESPONSIBILITIES
        o     List  if:  fa)  Confidential  Business  Information  (CBI)    is   disclosed  to the
              contractor;   (b)  the  Contractor is  to  use  Government  furnished  property
             . (GFP)  or facilities;  (c)  expert  testimony is expected; Id)  release of information
              and results  of the contractor is restricted; (e)  credentials for right-of-entry as
              required; end (f) other conditions necessary for project  performance.
 H.      RESOURCE ESTIMATES
        o     Identify  EPA's  best estimate  of  the  professional (nonclerical)  direct  labor
              hours  necessary to perform  the  requested work.    Use the  OW estimating
              forms  to develop  an LOE hours  estimate  for all technical work,  computer
              use, and anticipated contractor travel,  (Exhibit 3-2)
        0     Note any special  qualifications needed,
1.      SCHEDULE AND DELIVERABLE
        o     Provide  a  clear,  realistic schedule  for  ihe  completion of each task  and
              deliverable.  Use number of calendar or working days after an event for a due date
              {e.g.,  contractor  shall deliver the final report within ten calendar days of receipt of
              EPA's changes to the draft report).
J.     ATTACHMENTS
       o     You may want to provide a copy of any relevant documents referred to iri the SOW as
	       wall as any specifications  and standards the contractor must follow. -	
Chapter HI
January 13,1993

-------
 Suggestions for Writing Your Statement  of Work

 Now that you are ready to start writing a SOW, keep the following thoughts in mind:

       1.    ^^iSS^ff^SfS&^jf^^ You should realize that your SOW will be
 read, and therefore  have to be interpreted, by persons in  many different fields:
 lawyers,  engineers,  and specialists  in quality assurance, finance,  and contract
 management.  A good SOW precisely defines the product or service desired.  It
 affects administration of the contract because it defines the work to be performed.

       Limit your use of abbreviations to  those in common  usage.  A list of all
 abbreviations and acronyms should appear in the introduction. When a term is cited
 for the first time, spell it out and present the abbreviation or acronym in parentheses.
       2.    Avoid ambiguity, It is most important to gauge the likely effect that the
 specifications, as written, will have on the reader. All obligations of the government
 should be carefully spelled out.  If review or approval actions are to be provided by
 the government, a time limit or  milestones must be set.

       Requirements must be described in sufficient detail to assure clarity, not only
 for legal reasons, but also for practical application. Some details may be overlooked;
 others may be repetitious.   Beware of both.  The term "as necessary" should be
 avoided in any reference to any report or  any immediate action. Rather, it should be
 specified whether the judgment is to be made by the contractor or the government.
 Be aware that these types of contingent  actions may have  an impact on process as
 well as schedule.

       Similarly,  the  phrase  "as directed by the WANT must  be avoided.   Any
 appearance or possible implication of personal services must be avoided. If you do
 not know exactly what product(s) are  needed, write the WA in phases.  Clearly
 identify what the Agency will provide, i.e., existing information or references.
      Finally, avoid ambiguous words such as "prepare"
BE SPECIFIC.
               Do you mean write or type?
      3.
                           Not everyone
will be as familiar with it as you are. For the readers' sake, provide a TOC when your
SOW exceeds four pages in length.
      4.
than "a test should be conducted.
mandatory term "shall" rather the permissive term
"The contractor shall conduct a test" rather
When a firm requirement  is intended, the
           should" is desired.
Chapter HI
January 13,1993

-------
      5.
It is always important to define
 division of responsibilities among the government and the contractor. Always list and
 discuss those  tasks  that cannot  be performed by  a contractor in your SOW.
 Inherently governmental functions are discussed in more detail later in this chapter and
 in EPA Order 1900.1 and 1900.2. (See Appendices C and D).
      6.
                 Expect the
 contractor to follow precisely the wording of the SOW.  If the SOW does not clearly
 state not only the standards by which performance will be judged, but also by whom,
 how, and within what period of time, the contractor may be absolved of responsibility
 for inadequate performance.
      7.
        Previously developed
SOWs can be a valuable resource when used in conjunction with information on the
resulting contract.  Where similar work has been done and the results were good,
portions of that SOW may be used as a guide to the one being  prepared.  Where
problems later developed during performance, the old SOW and the contract file may
provide insight as to where greater detail, correction, or clarification could have been
used to avoid problems.
      8.
               For example,
when immediate decisions cannot be made, it may be possible to include a procedure
for making them (e.g., "as approved by the  CO," or "the contractor shall submit a
report each time required government inputs are not received.")
      9.
             Do you need a
report, a briefing, video? Do you need interim deliverables? Do you have a format in
mind? How many copies will you require?  Do you need a floppy disk? If yes, in
what format. The more information you communicate in your SOW regarding your
deliverables, the more accurate will be both yours and the contractors estimates
regarding the cost of the contract.

The following sections provide additional information as you begin to develop your
SOW.
Chapter 111
January 13,1993

-------
                      Avoid Inherent Government Functions
 EPA has been criticized for its management  of  contractors.   On  a number of
 occasions, the Agency has put contractors in policy and decision-making positions,
 or has placed  contractors  in positions that give  the  appearance that  they are
 formulating policy or making decisions on behalf of the Agency. As a result of these
 past indiscretions, EPA has taken steps to better manage contracts to insure that
 "inherently governmental functions" are carried out by EPA employees.

 The following is a list of inherently Government functions that cannot, under any
 circumstance, be undertaken by a Contractor:

 1.    The actual preparation of congressional testimony.

 2.    The interviewing or hiring of individuals for employment at EPA.

 3.    Developing and writing position descriptions  and performance standards.

 4.    Determining Agency policy.

 5.    Participating as a voting  member on a  performance evaluation  board or
       participating in or  attending award fee meetings.

 6.    Preparing award fee letters, even under typing services contracts.

 7.    The actual preparation of award fee plans.

 8.    The  preparation  of  documents  on EPA  letterhead other  than routine
       administrative correspondence.

 9.    Reviewing Contractor vouchers and invoices for the purposes of determining
       whether cost, hours, and work performed are reasonable.

 10.   The development  of  SOWs, WAs, technical direction documents, delivery
       orders, or any  other  work issuance document  under a contract  that  the
       contractor is performing or may perform.

 11.   Preparing responses  to audit reports for the  Inspector  General, General
       Accounting Office (GAO), or other auditing entities on  behalf of EPA.

 12.   Preparing responses to Congressional correspondence on behalf of EPA.

^Chapter III
 January 13,1993                         5

-------
 13.   The actual preparation of responses to Freedom of information Act requests,
       other than routine, non-judgmental correspondence--in ail cases, EPA must sigh.

 14.   Any contract which authorizes a contractor to represent itself as EPA to outside
       parties.

 15.   Conducting administrative hearings.

 16.   Reviewing findings concerning the eligibility  of EPA employees for security
       clearance.

 17.   Preparing an office's official budget request.
in addition to those government functions  that contractors are prohibited from
undertaking, there are a number of activities over which the Agency--that means you,
must exercise great control if a contractor is to conduct the work. When you request
a contractor to undertake one of the following tasks, make sure you take an active
role in overseeing the contractor's work and that you are the ultimate decisionmaker.
You must assure that final products are unbiased and represent Agency thinking.
These activities include the following:
      1.    Supporting  preparation of the budget by  doing  workload modeling,
            fact-finding, efficiency studies, should-cost analyses, and the like.

      2.    Reorganization and planning support.

      3.    Conducting analyses, feasibility studies, et cetera that are used by EPA
            to develop policy.

      4.    Supporting regulation development.

      5.    Supporting EPA's evaluation of another contractor's performance.

      6.    Participating in strategic acquisition planning.

      7.    Supporting work to improve contract management.

      8.    Providing specialized expertise in the contract selection process.

      9.    Sharing office space with  EPA personnel.
Chapter HI
January 13,1993
6

-------
      10.   Support in preparing responses to Freedom of Information Act requests.

      11.   Any situation where a contractor has access to CBI or other sensitive
            information.

      12.   Any support involving EPA policy or  regulatory interpretation, such as
            staffing hotlines, attending conferences on behalf of EPA, community
          .  relations efforts, conducting EPA training courses, etc.

      13.   Any situation where it can be assumed that the contractor is an EPA
            employee, without specifically identifying his or herself as a contractor.

      14.   Independently interpreting EPA policies or regulations on EPA's behalf to
            outside parties.


Completing an  Independent OW Cost Estimate

The independent OW cost estimate is an essential  part of your WA. This estimate is
for use by EPA employees only, and should  not be given to the contractor.  Cost
estimate  forms are provided as  Exhibit 3-2 in this  manual to help you complete this
estimate. Along with the SOW  and the WA Request Form, the cost estimate forms,
once they are completed, become part of the permanent record of each WA. Be sure
to see your  PO to  get a copy of the form being used for the contract you will  be
using.

The estimating forms are the basis for establishing the "independent OW estimate"
required for any particular WA. They are developed internally and are for internal use
only. The estimating forms provide a record of how a cost estimate was developed
for a particular WA. These documents provide the basis for negotiating the work plan
with a contractor.  Estimate the P-Levels as required by your PO.  Get the average
hourly rate from your PO and complete the totals. P-Levels are identified in Appendix
F.

Review  and  Approval  of Contractor's  Work  Plan  and
Budget

Once  you have submitted your completed WA along with appropriate forms, to the
PO you must wait for the  contractor  to respond and submit a Work Plan (which
includes a budget) for completing the work you have identified. Your PO will send the
Work  Plan to you for approval along with a WA Cover Sheet which you will sign and
return to  the PO indicating approval of the Work Plan. You will review the Work Plan
to ensure that the contractor's understanding of the task is clear and that the

Chapter 111
January 13,1993                        7

-------
proposed technical approach for accomplishing the work is reasonable. Further, you
must ensure that the proposed level of staffing and  resources are appropriate,
sufficient, and reasonable for performing the work.

Notice of approval/rejection of Contractor's Work Plan is submitted through the PO
to CO for communication to the contractor. If work plans or cost proposals are not
approved, comments or required revisions must accompany the notice of rejection.

Sometimes a Contractor is authorized to begin work  while the Work Plan is under
development or review. The Contract will  specify a point at which work is to stop
if Work Plan approval has not been received, or if the work plan is rejected (a ceiling
of funds to be spent prior to Work Plan Approval can be specified in the WA). Timely
review of the Work Plan is critical to ensure that the work is  completed on time.
Delays on the part of the government can prevent a Contractor, under the terms of
the contract, from continuing performance.

Recommended Contents of a Work Plan

1.    Statement of the Project Goals (Purpose)
2.    Detailed Technical Approach with Action Steps
3.    Description of Each Task/Deliverable with  Schedule for completion
4.    Staffing Plan (with resumes for key  personnel if not previously submitted at
      contract award)
5.    Areas requiring clarification/suggested modifications/anticipated problems
6.    Proposed format(s) for  special progress reports, if required
7.    Proposed use of Subcontractors, with  discussion of how the effort will be
      managed by the Prime Contractor.
8.    Detailed Cost proposal, broken down by task and subtask.

What to Look for in a Work Plan

      o     Does the work plan fit the SOW?
      o     Does the contractor demonstrate complete understanding of all elements
            of the project?
      o     Is the overall schedule appropriate/too generous/too ambitious?
      o     Can the effort be accomplished reasonably within the Level Of Effort?
      o     Is the overall staffing plan appropriate and reasonable (e.g., are there too
            many P-4 hours for Senior Management)? (see Appendix F)
      o     Has the contractor identified any questions or problems which need to
            be resolved?
      o     Is there too much subcontracting? Can the contractor maintain adequate
            control over the project?
Chapter in
January 13, 1993
8

-------
      o     Does the  assignment have the commitment of  the  contractor's
            management?
      o     Costs
                  Are the hours and rates appropriate and reasonable?
                  Is the labor mix close to what was negotiated in the contract?
                  Are  the  indirect cost rates  those  which have  already  been
                  negotiated and are stated in the contract?
                  Is the subcontracted portion of the effort reasonable?
            _     Is the proposed amount of travel acceptable?
                  Did the contractor provide a breakdown on Other Direct Costs? Is
                  each component reasonable?
                  Are proposed subs/consultants already approved?
                  Will approval of the work plan require a ceiling increase of any
                  proposed sub/consultant?
            _     Is any Government Furnished Property involved, and has it been
                  justified in the contract?


 Final  Approval of the Work Plan

 As the WAM, you can approve the Work Plan if it meets the above criteria.  If you are
 not satisfied, you can conditionally approve or reject the Work Plan.  With conditional
 approval, you must clearly identify those areas that the contractor must fix  (e.g.,
 change mix of labor hours, change date of deliverable).  If you reject the work plan,
 you also must provide an explanation  of the deficiencies. The difference between
 conditional  approval and rejection is  that under the former, the contractor may
 continue to work for a specified period of time, while rejection requires immediate
 stop work.  Under both of these scenarios, the contractor must correct deficiencies
 and submit  a revised Work Plan. There is no  limit to the number of times that you
 may conditionally approve or reject a contractor's Work Plan. If the  contractor is
 having difficulty submitting a satisfactory Work Plan you should consider that the
 contractor may not be suited to the task or that your SOW may be unclear.  In either
 case, you should consult with the PO.
Chapter 111
January 13,1993

-------
     Does my WA contain the correct documentation?

     The  WA  you  submit  to  your PO must contain  the
following documents:
         Cover Sheet
         Work Assignment Review Form
         Statement of Work
         Independent Government Cost Estimate
         Procurement Request
         Completed WAM  Designation  Form  1900.65,  if
         necessary
         Completed ADP Concurrence Form, if necessary
         Completed CBI Review Form
         Completed QA/QC Form, if necessary
D
D
D
Q

a
a
a
Chapter 111
January 13, 1993
                      10

-------
3-1



3-2
        Chapter III





          Exhibits






Work Assignment Package (15 Pages)



OW Work Assignment Resource Estimating Form

-------

-------
                                                                              EXHIBIT 3-1
                           WORK  ASSIGNMENT
         ENVIRONMENTAL  PROTECTION  AGENCY
 1.
 2.  CONTRACTOR:
 5.  UA TITLE:  i
                                           3.  UORK ASSIGNMENT NO.:
                                           4.  AMENDMENT NO.:	'
                                                                    bfc O A&»q»ie««««1H>««««««««1»«««ir««*««««««*«««>IK«««««»M
                         LIMITATION OF  FUNDS
                                                              JNO.
 10. TOTAL UA FUNDING CEILING;
                                                                 ••••»•»»•••*»•••«»••••»•••»»»»»
                                      UORK PLAN APPROVAL
 11. CONTRACTOR UP ESTIMATE: COST AND FEES:
12. TOTAL APPROVED FOR CURRENT TERM: COST AND FEES:.
                                                                  LOE
13. DOES UP REQUIRE SUBCONTRACTOR OR CONSULTANT?
   IF YES, HAS SUBCONTRACTOR/CONSULTANT BEEN INCORPORATED
   INTO THE CONTRACT?  (If Subcontractor/Consultant has not
   been incorporated Into the contract. Contractor must
   subnit appropriate docuaentatfon to obtain approval
   prior to use.)

14. DOES WP REQUIRE PURCHASE OR LEASE OF ACCOUNTABLE
   PROPERTY? IF YES, ATTACK JUSTIFICATION.
                                                               C 1 YES
                                                               [] YES
                                                                            94 NO
                                                                            t I NO
                                                                             C 3 NO
 IS.
                                  APPROVALS
  WORK ASSIGNMENT MANAGER:
  Nane:  If V/JUL, /K»^
  Phone No.; (n^yii^f-ff^AZ.   Fax No.; (juaAj/*6-f»nto
                                                             Branch/Ma it Code; NU-fo
                                                             Signature:
                                                             Date:
  PROJECT
  Nam:
  Phana Na. :
                i Ji«»««<•*
                          i«*««««* «••<•»••»•••»•••«•»•»«••«*>••••••>««
                           CONTRACTOR'S REPRESENTATIVE ACKNOWLEDGEMENT
NAME;
TITLE:
SIGNATURE:
DATE:	
CMD-C1 (10-92)

-------

-------
           GtJTDANCB FOR COMPLETING WORK Xfi8T
                                               FORM
NOTE! ITEMS TEAT ARE SELF EXPLANATORY (BE) ARE MOT REPEATED
1.
2.
3.
4.
5.
6.
7.
S.

9.




10.

11.
12.
13.
14.
IS.
SB
8E
SB
SE
SE
CHECK APPLICABLE BOXES (HAT BE MULTIPLE)
INCLUDE TEE FOLLOWING INFORMATION IV THE STATEMENT OF WORK:
    Title
    Purpose of WA/Baekgrouad
    Detailed Tart Descriptions (Specific Tasks/sub-
   '  Tasks/Daliverablea)
    Required Additional Reports (vita specified formats)
    Schedule of Tasks aad Deliverable*
    Suggested Skill Mix
    Required Personnel Qualifications
    Special Requirements or Restrictions
     — Specific Travel Requirement (Bomber of Trips, where,
        when, purpose - must be in direct support of WA)
     — specific Training Requirement (new technology, direct
        benefit to vork assignment, mission)
     — Conflict of interest Issues
     — Q.A Assurance Plan
PERIOD OF PERFORMANCES  Start date may be date contracting
Official  (CO) issues WA or date CO approves TO, depending on
contract WA clause.  Ending, date must not exceed current
contract term UNLESS the WA is severable whereby specific tasks
can be identified as carryover into next term.  If ending? date
exceeds contract maximum expiration date, specific tasks^must
be identified which will be completed by follow-on contractor.
WAS WILL NOT BE ISSUED UNDER THE ASSUMPTION THAT AM EXXEMSIOM
WILL BE GRANTED TO CURRENT CONTRACTOR TO COMPLETE WORK.
INDEPENDENT GOVERNMENT ESTIMATE OF LOBS  This is an estimate
prepared by the Government with no input from contractor.
Zf contractor may start vork at WA issuance,  provide ALL
funding information.  If contractor cannot start_work until WP
is approved, provide all information EXCEPT AMOUNT at WA
issuance.  All information to be provided at  WP approval.
TOTAL WA FUNDING CEILING»  This is TOTAL amount of funding  that
has been provided for the WA during current term.
APPROVED FOR CURRENT TERM (COST/FEES/LOB) S  This includes total
COST/FEES/LOB approved for the current term to date (including
all amendments) obtained from contractor*s  WP.
SB
SB
OTESRs OIRM APPROVAL, QA/QC, SR. Procurement Official,  ETC.

-------
                                    WORT ASSIGNMENT BEVIEU/aEBTIFICATIOl CHECKLIST
 1.
 2.
 S.

 6.
 7.

 8.
CONTRACT MO.;  68 "CO" XX XX
UA NUMBER:	
UA TITLE:
                                                 3.  INDEPENDENT GOVERNMENT COST EST.:  /Otf. j
                                                 4.  INDEPENDENT GOVERNMENT 106 EST.:	L/^Q
                                       :tV»t*,iH<»i
UA falls within scope of work of this contract.
Cite specific section/paragraph(s) of contract SOU:
   Sec^im'^r^ "aajnoLfl/iixph 3
UA Amendment falls witnin scope of original UA.

(a) Total LOE ordered by UAs to date (excluding  this  current  UA):.
(b) Total LOE authorized under current contract  term:
                                                                                           YES
    (c) Current UA requires exercising quantity options.   (Attach  Justification)   t

 9. (a) Funds are in the contract to support UA.                                           Q$
    (b) A funding PR is attached to support this UA.                                        otf
    (e) UA is funded by multiple appropriations.                                           E )
    (d) If °e is yes, FMD approval is attached.                                             ( ]
    (e) FMD approval is not provided, but accounts are  identified  with specific tasks.      t 1

 10.  All work (including deliverables) will be completed during the current contract term,  tf

 11.  The contractor has not been instructed to begin work on
     this UA by anyone in the organization.      .                    .                      j j

 12.  UA does not contemplate improvement to realty (repairs, alterations,
     modifications to real  property).                   •                                   t j

 13.  (a) UA does not require printing.                                                      [ )
     (b) UA does not require duplication exceeding contract limitations.                    t 1

 14.  UA  contemplates development of  software or  ADP equipment/services.                     { ]
     (Attach OIRM clearance or indicate if  this  was obtained at contract award.)

 15.  (a) Program has not  recommended subcontracting/consulting services
         to meet  UA  requirements.
     
-------
                         STATEMENT OF WORK


                             SAMPLE
         (Where Work Assignment Manager is in the Region)
       FEDERAL UNDERGROUND INJECTION CONTROL  (DIG) PROGRAM
              DIRECT IMPLEMENTATION IN EPA REGION II
          NEW YORK, PUERTO RICO, AND THE VIRGIN ISLANDS
     EPA Region II requests that the Contractor provide technical
support services in the areas of activity detailed in the attached
statement of work.  The Contractor, will perform each of the major
activities according to the final work plan, work hours, and cost
estimates agreed upon by EPA and the Contractor. After  approval by
the  Region,  the  detailed work plans will  be submitted  to the
Project Officer in EPA Headquarters and the Contracting  Officer for
review before receiving authorization to proceed.  The initiation
of  these  specific tasks  will be  coordinated by the  Contractor
through the  contract *s Work Assignment  Manager  (WAM), Wilma Ann
Mason in Region II.

Background and Purpose

     Implementation  of  the UXC Program in New York State is the
direct  responsibility  of the Region II  office  of  EPA.    It is
critically important that the UIC needs be  addressed  during the
implementation of the UIC Program  in  western New York State.  In
particular,  the  New York State UIC  Program  requires  oil field
technical expertise and response in a  relatively short time frame.
EPA Region II  needs UIC expertise to witness  and inspect common
Class II  activities in western New  York State.   The Class  II
activities are to be  reported to EPA so a determination  can be made
regarding  compliance with UIC regulations  and/or need  for EPA
follow-up inspections.

     Section 1445 (B) (1)  of the Safe Drinking Water Act provides
the Administrator or  his designated representative the authority to
enter upon and to inspect  any  facility subject  (authorized by rule
or permitted to the  UIC Program requirements.   Additionally, the
provisions of 40 CFR Part 144.51 (i)  specify that the Director or
his authorized representative, upon presentation of documents and
credentials,  may:

     1)    Enter upon the  permittee's premises where a regulated
          facility or activity is located  or conducted,  or where
          records are kept under the conditions of the permit;

     2)    Have access to and copy,  at reasonable times, any records
          that must be kept under the conditions of the permit;

     3)    Inspect at reasonable  times any  facilities,  equipment
          (including monitoring and control equipment), practices
          or  operations regulated  or required under the  permit;
          and,

-------
Background and Purpose  (Continued)

      (4)  Sample or monitor at reasonable times, for the purposes
          or assuring permit compliance or as otherwise authorized
          by the appropriate  Act,  any substance or parameters at
          any location.

     EPA  Region II  requests  that the  Contractor provides UIC
inspection services  as  detailed in this Statement  of  Work.  The
Contractor will  be  responsible  for maintaining  separate  fiscal
accounts  for each  individual  part of this  work assignment.  The
inspection-related work and resulting travel are  limited to New
York State, primarily the western New  York State area of Allegany,
Cattaraugus, Chautauqua,  and  Steuben Counties,  unless otherwise
directed by the WAM.


Period of Performance

     The period of performance for this work assignment is October
1, 1992 through September 30,  1993.
Scope of Work

     The Contractor is requested to provide continued services of
one full-time UIC program inspector equipped with vehicle and basic
inspection gear to work in an assigned geographic area of western
New York State as follows:
     1)   Geographic Responsibility

          The inspector will be primarily responsible for the New
          York counties of Allegany,  Cattaraugus, Chautauqua, and
          Steuben.  The inspector will be expected to be familiar
          with the area.

     2)   Duty Station

          The inspector  will operate  from  his residence.   This
          residency shall be located within 50 miles of the areas
          listed above.

          The highest anticipated workload will be in the vicinity
          of the Olean  ,  NY Region.   This area will be  the area
          most accessible to the current UIC activity.

-------
Scope of Work (Continued)

     3)    Travel and Vehicle

          Under this  contract,  the Contractor will provide  the
          inspector with a four-wheel drive vehicle, which will be
          leased and  insured under this contract.   An  expense
          account for  gasoline, oil, maintenance and certain other
          travel-related expenses will be allowed.  The purpose of
          establishing the  field  locations is  to minimize  long
          distance  travel and overnight  lodging.   Any  overnight
          travel  for  inspection-related  work  must  have  prior
          approval  form the WAN.   The inspector will be authorized
          and is expected to travel to the EPA New York  Region II
          office  for  any training,  reporting,  and enforcement
          casework  as  indicated by the WAH.

    4)    Inspection Equipment

         The Contractor will provide each of  its  inspectors with
         the following equipment:

              hard hat
              safety goggles and safety shoes
              current edition of 40 CFR Parts 100 - 149
              field clipboard (i.e., SNAPAK ISN-8512)
              bound waterproof notebook
              flashlight
              automatic 35mm camera
              appropriate pressure  gauges
              telephone answering machine, beeper, or such device
              500-foot (or  longer)  water level  indicators  (tape
              or mechanical)  (e.g., QED Model  6000)
              other equipment as needed.

        The EPA Region II office will provide the  inspector with
        the following:

             appropriate credentials
        -    sampling containers
             the Region II Quality Assurance  (QA) Project Plan.

        All equipment  purchases charged to the assignment must be
        approved by the Contracting Officer,  in writing, prior to
        the  purchase.    Property  accounts  or  nonexpendable
        equipment,  including information on whether the purchases
        are direct or  indirect costs,  will  be  kept  by  the
        Contractor. A listing of all equipment purchased will be
        furnished to the Property Administrator.

-------
 5)  Duties and Responsibilities

 There are four categories of inspections to be performed
 by  the  inspector:

 Category I - Routine Inspections
                                    •  "    t
 These  inspections are made  to allow EPA to determine
 compliance with  permit or rule requirements.  They may
 require a  review  of  well or other  records,  a visual
 inspection of the sell, a review of well construction/ or
 general housekeeping.  Some  samples of injected fluids
 may be collected and submitted to an approved laboratory
 for analysis.  The sampling procedures and analysis will
 follow  the Regional EPA approved  Assurance  Plan.

 In  addition, the inspector will inspect facilities and
 injection   wells   for   obvious   potential  hazards,
 appropriate   monitoring   equipment    and   recording
 procedures, and  proper operation and  maintenance.   The
 inspector shall  notify the  WAH of any major problems
 encountered at an individual  injection well  or injection
 facility during the course of such an inspection.

 Category II - Construction Verification

 The   inspector   will   be   required   to   observe   the
 construction of  new wells  and modification of existing
 wells and report  to the WAM  so EPA can insure that all
 construction  activities  are  completed  according  to
 approved permit or rule conditions  or guidance.    With
 new facilities,  it is particularly important that a pre-
 operational inspection be made.  An integral element of
 such EPA reviews will be an examination of the compliance
 achieved by  the  owner/operator  in  comparison to  the
 approved corrective action plan.  These inspections may
 be  conducted  either  during  construction,  or  after
 completion,  as warranted.

 The inspector should inspect, review,  and report to the
 WAH, siting and construction data, casing and cementing
procedures,  presence of required monitoring equipment,
 any logs or such tests run during construction,  results
 of  mechanical  integrity  tests,  results of formation
testing,  the   injection   procedure,    and   status   of
 corrective action on the pertinent wells within the area
 of review.

-------
Scope of Work (Continued)

          Category   III   -  Mechanical   Integrity  Test   (MIT)
          Verification

          This category  centers"  on  MIT  activities planned  and
          conducted by the owners/operators in compliance with EPA
          requirements.  The types of MITs conducted will  be  the
          Water-in-Annulus method, used in Regions II and III,a nd
          casing and/or tubing annulus pressure tests.  These tests
          will be  performed on an individual basis  to ensure  the
          use of proper testing procedures and the accuracy of test
          results.  The majority of the MITs performed will  be  the
          Water-in-Annulus method.

          EPA projects that approximately 1,500 existing  active or
          temporarily abandoned Class IIR wells will  be tested  for
         mechanical  integrity  by  the owners/operators.     The
         contract inspector will witness MITs when  instructed by
         the WAN and report results to EPA.

         Category IV -  Plugging and Abandonment (P&A) Verification

         Due  to  the  difficulty  in  determining  the number  of
         closures,  (which  depends   mostly  on   owner/operator
         notification), EPA Region II will require inspections on
         a  case-by-case basis  for  plugging  and  abandonment
         activities.    The  p&A inspections will  rely on proper
         notification by  the owner/operator.  Inspections of this
         type  will be considered a single event, and may entail
         several days  for completion.

         The inspector  will witness the cementing  techniques used
         during the  permanent  closure of a well and compare the
         plugging  activities to  the  EPA  approved  plugging and
         abandonment  plan,  UIC  regulations,  and Region II P&A
         guidelines.  The contract inspector  will notify EPA  on
         owner/operator variance  from the approved  plans.   The
         inspector will submit  a report  to  the WAM outlining
        cementing techniques used during the permanent closure of
        a well.

        All inspection data submitted to EPA by the inspector may
        be used for determination of follow-up EPA inspections or
        initiation of compliance/enforcement  activities.

-------
scope of work (continued)
          6)    Supervision,  Training,  and Guidance

          Inspection  tasks  will  be  scheduled  by   the   WAM.
          Assignments will be issued to the Contractor monthly, and
          also  through  special   requests  as  necessary.     The
          inspector must document completion  of tasks  in a  form
          acceptable to Region  II  (Inspection  Reports,  Compliance
          Reports,  etc.).  The contract inspector will be required
          to   schedule  specific  inspections.     However, names,
          addresses,    and   telephone    numbers   of   company
          representatives will be provided to the Contractor by the
          WAM.    Depending  on  the  inspector's  requirements,
          technical and program guidance, specific  EPA  policies,
          and training  on program objectives will be provided by
          EPA Region II.

          7)    Inspector Qualifications  and  Selection

          Candidates for the position of UIC contract  inspector
          should have  a  combination  of  field  experience   and
          education  that brings  to  the  job   a  comprehensive
          knowledge of  (1)  western New York's State  (Appalachian
          Basin)  oil  and  gas  practices  and  geology  and   (2)
          principles  of  oil  and gas  recovery  and  ground water
          protection.  Emphasis shall  be  placed  on the following:

          A)    New  York State Oil and  Gas Field  Practices

                   drilling and completion
                   well  stimulation
                   geophysical well logging
                    enhanced oil and natural gas  recovery
               -    produced fluids and abandonment practices
               -    casing and cementing  policies

          B)    Principles of Hydrocarbon Recovery and Ground Hater
               Protection

               -    petroleum engineering and geology
                   oil and gas geology in New York State
                   well hydraulics
               -    ground water hydrology/hydrogeology
               -    geochemistry

          In  the event  a replacement  inspector  is required,  the
          Contractor  shall  immediately take all reasonable steps
          necessary  and  appropriate  to  secure  a   qualified
          replacement  in a  timely manner.    The Contractor is
          directed  to  secure  and  evaluate  applications  from
          interested   candidates   according    to   the   above
          requirements.  Screening interviews may be conducted by
          the  Contractor.

-------
  Scope of  Work  (Continued)

           8)   Data Tracking  and Reporting  System

           Data  collected  through   field  inspections  provide an
           essential  element  of  compliance verification  for UIC
           activities in New York State.  For all  inspections  of a
           similar  type,  it is  important that  collected  data be
           consistently recorded.  Consistent inspection reporting
           will  enhance  follow-up   compliance   determination  and
           program enforcement activities.

           Reports  of  inspection  activities shall be  submitted
           within  five  working  days  following  the  inspection.
           Reports shall be submitted  in  a  format consistent with
           the data entry needs of  the  Region II FOCUS  system.
           Specific formats  will be provided to the inspector prior
           to the start of inspection activities. The formats shall
           contain data  elements  directly  related to  the  data
           management system for the UIC activities in EPA Region II
           (FOCUS).   All data  submitted  by the  inspector will be
           reviewed and  put  into the FOCUS system  by the Regional
           UIC staff.  EPA reserves the right to authorize equipment
           purchases  that would  allow the  inspector  to directly
           enter inspector data in FOCUS.
Travel
     The contractor  is  expected to take two long distance trips;
two roundtrip trip between Smethport and New York City for meetings
with the EPA WAH.

-------

-------
 (Shaded areas are for USB ol procurement office only)
Page

US fcnwonmentai Pro
*tCDA Procure
VCr/^ Reauest/
^ffanafun of Originator^ y
Deliver To f/Vo/ecf Mfnagert '
Peter Olson
12.
Financial
Daw


•.Appropriation
682/30108
FMOUse




tact
C2C
m
'0
I
ion Age
(480
ent
>rde
£$7
ncy
r
1 . Name of originator
Wilma Ann Mason
3. Mail Code
2WM-UIC
5^7

4. Telephone Number
(212) 264-XXZZ
2. Date of Requisition
9/1/92
S. Date Item Required
ASAP
7. Recommended Procurement Method
LJ CompMrtJv* LJ Other than full and open competition O Sato source small purchase
a. Address EPA OGWDW/8MES
401 M St. SW Wash. D.C.

O
T
(d




b. Servicing Finance Office Number
22
Document
Control Number
W {6 digits!
Account Number
mno
2BUH40EOOO


1 3. Suggested Source (Name. Xddrexc. 2//> Coda, Phont/Conttct)
XYZ Contractor
305 Forest gate Drive
Washington, D.C. 20469

14. Amount of money
coiiimmad tK
0 Original
D Increase
D Decrease
to. Mail Code
WH550A
1 1 . Telephone Number
(202) 260-XXXY
NOTE: Item 12(d) Document Type — Contract =
Purchase Order « "P"
Class
2505


"C."
Amount (h)
Dollars
108.500


Cent
00


16. For Small Purchases Only: Contracting Office •» autho-
rited to exceed the amount shown m Block 12(h) by 10% or
•100. whichever is less.
Dves DNO
16. Approrate
a. Branch/Office Betsy>franch|, Chief <
UIC EnforcementvneMe. p-Lt/U-^t*-
b. Division/Office Debbie. Datrldot
Enforcement Dix
-------

-------
•&EPA
                       Designation and Appointment of Project Officer/
                      Work Assignment Manager/Delivery Order Officer
                                      (For Other Than Small Purchases)
       Note: This form is not a Contracting Officer warrant. Delivery Order Officers and Administrative Delivery
       Order Officers require a warrant of Contracting Officer authority. Any request for a Delivery Order Officer
       warrant must be accompanied by the additional information required in Chapter 8 of the Contracts Manage-
       ment Manual.
   1 a. Name of Nominee  •

     Wilma  Ann Mason
                                                  b. Title
                                                    Geologist
   c. Organization
     2WH-UIC
                        d. Mail Code
                             2WMD-DGWP
e. Telephone

 (212)  264-XXZZ
f. Years of Contract Experience
   2. The nomination is for:

        LJ Project Officer

        t&J Work Assignment Manager

        I—I Delivery Order Officer

        LJ Administrative Delivery Order Officer

        LJ Delivery Order Project Officer
                                                 3. The Nominee Has:

                                                    a. Completed the basic Project Officer Course

                                                    b. Completed the Contract Administration Course

                                                    c. Incorporated appropriate contract management
                                                      criteria in position description and performance
                                                      standard. (If criteria have not been incorporated.
                                                      they must be incorporated within 30 days of
                                                      appointment. I

                                                    d. If trie nominee has not completed the basic Pro-
                                                      ject Officer Course or the Contract Adminis-
                                                      tration Course, has a waiver or interim
                                                      certification been provided

                                                    If the answer to items a. D. or c is "No." or the
                                                    answer to item d is "No." attach an explanation.)
                                        Yes
                                        B
                                        m
                     No
                     D
                     D

                     D
                                                                                              D    D
            Dollar Amount of Contract. Work Assignment, or Delivery Order
                $108,000
  S. Nomination is for (Check one):


       bu a new contract, work assignment, or delivery order entitled  Federal  UndepgT'Otind Tn jpp.f.i or]

        (UIC)  Direct Implementation  in  Region  II

       I—I a change in the Project Officer. Work Assignment Manager, or Delivery Order Officer on Contract No.  	
       til applicable, the work assignment nondelivery order no. is
                                               Certification
         The undersigned nominee and requesting official certify that the designation of this
         nominee complies with the workload limitations and other requirements set forth in
         Chapter 7 of the Contracts Management Manual.
                                                                                    b. Date
  7a Signature of Requesting Official
  ~   (Division Director or Higher!
                                       b Name and Title
                                                                                c Date
 iignature of Approval Official
(Contracts Organisation/
                                           b Name and Title
                                                                                   : c. Date
  EPA Form 19OO-6S (6-9&\
                                                                                Official Contra

-------

-------
0
              CBI REVIEW OF INDIVIDUAL WORK ASSIGNMENTS/DELIVERS ORDERS
          CONTRACT NO.
WA/DO NO.
          CONTRACTOR NAME:
          PROJECT OFFICER NAME:.
          WAM/DOPO NAME AND SIGNATURE:.
                                                                  YES   NO
          1.  Under this WA/DO, does the contractor or
              subcontractor currently have access to CBI?

          2.  Under this WA/DO, will the contractor or
              subcontractor potentially have access to CBI?

          3.  Is the contractor or subcontractor authorized
              to have access to CBI?

          4.  Did any amendments to this WA/DO preclude
              disclosure of CBI?

          Comments (if applicable):
          NOTE:  If the answers to Questions 1 and 2 are "NO," this action
          presents no problem.  If the answer to Question 3 is "YES," this
          action presents no problem.  In either case, after review by the
          Associate Director or the CMD Director, the form nay be retained
          in a separate file.  If the answer to Questions 1 or 2 is "YES11
          and the answer to Question 3 is "NO," a problem exists.  This
          form requires submission.  If the answer to Question 4 is "YES,1*
          this form requires submission even though no problem exists.
 C

-------

-------
                 QUALITY ASSURANCE REVIEW FOR EXTERNAL PROJECTS
                                   (Contracts)
 I.   GENERAL INFORMATION

     Descriptive Title:

     Sponsoring Program  Office:

     Approximate Dollar  Amount:
             j
     Duration:
 II.   THIS CONTRACT REQUIRES ENVIRONMENTAL MEASUREMENTS  	
      (If yes,  complete form;  If no,  sign form and       Yes       No
      submit with procurement request.)

 III.  QUALITY ASSURANCE REQUIREMENTS                       .	   	
      (Projects Involving  environmental  measurements)       Yes       No

      a.   Submission of a  written quality assurance
          (QA)  program plan (commitment  of the
          offerer's management to meet the QA
          requirements of  the scope of work)  is to
          be included in the contract proposal.

      b.   Submission of a  written QA  project  plan  is
          to be included in the contract proposal.

      c.   A written QA project plan is required as
          a part of the contract.

      d.   Performance on available audit samples or
          devices shall  be required as part of the
          evaluation criteria  (see list  on  page 3-76)

      e.   An  on-site evaluation of proposer's  facili-
          ties will  be  made to ensure that  a QA system
          1s  operational and exhibits the capability
          for successful completion of this project
          (see schedule on  page 3-76).

      f.   QA  reports will  be required (see schedule
          on  page 3-76).

* This form may vary in context depending upon the application
  and originating office.

                           3-75
                                          Second Edition - 4/84
                                          Rev. No. 2-9/30/85

-------
 IV.  DETERMINATION  (Projects  Involving environmental
     measurements)

     Percentage of  technical  evaluation points assigned
     to QA

     Project Officer estimate of percentage of cost
     allocated to environmental measurements
             QC Reference     Split Samples     Required    FREQUENCY
Parameter  Sampling or Device       for          for
Measured      Available	 Cross-Comparison  Preaward  Purina Contract
              (Yes or No)         (Yes or No)    (Yes or No)
QA System Audits are required:  Preaward 	; during contract:

QA Reports are required: with Progress Reports 	; with Final
   Report

The signatures below verify that the QA requirements have been
established.

QA Officer:
      Signature         Date               Signature          Date

After signatures, a copy of this form must be included with the procurement
request and sent to the Contracts Office and a copy placed on file with the
QA Officer
                                3-76
                                              Second Edition - 4/84
                                              Rev. No. 2-9/30/85

-------
                        EXHIBIT3-2
               Work Assignment Resource Worksheet
Task
                68-CO-_ ___ _WA#:

               PLLEVEy      Travei
               HOURS
    WAM:

Photocopy  Postage    DeBvery Sub/Consult
    Y/N      Y/N     Y/N
                        EST HOURS  X   RATE    =   EST COST
    PROF LEVEL 4
    PROF LEVEL 3
    PROF LEVEL 2
    PROF LEVEL 1

        TOTAL DIRECT
LABOR OVERATE
    FRINGE BENEFITS
            sub-total (1) + above
    OVERHEAD       	%

    TOTAL LABOR OVERHEAD
                       RATE   X   BASE
                                                          (1)
                                   (1) ABOVE
                                   ABOVE  $
                      (2)
                  (3)
                                             (SUM OF 1,2&3)

-------

-------
    ER DIRECT COSTS
    WORD PROCESSING/COMPUTER (HOURS)
    PHOTOCOPYING  /^COPIES/PAGES
    POSTAGE/DELIVERY
    MEETING ROOM RENTAL #DAYS/#ROOMS"

    A/V RENTAL
    CONTRACTOR TRAVEL
    TOTAL LABOR/OVERHEAD
       (FROM PAGE 1)
    TOTAL DIRECT COSTS
    AND OVERHEAD (FROM LINE ABOVE)
                                                    (A)
    GENERAL & ADMINISTRATION (	%)
    TOTAL A & B
    FEE(
                                                     (B)
                                                    (D)
    TOTAL WORK ASSIGNMENT COST
A
PWTO:
ACCT:
                                              (SUM C & D)
DCN:

-------

-------
                Work Assignment Resource Worksheet
WORKSHOP   68-C -0000    WA#:
Task
PL LEVEL
HOURS
Travel
Y/N
WAM:

Photocopy  Postage
Y/N      Y/N
PREPARE AMMfHINCPMPMT AfiEMPA 7  94.
Delivery
Y/N
ACQUIRE MEETING SPACE
AV PHI HPIUIFMT	
       24
PREPARE HANDOUTS
    HP PV/AI
       40
TAKE NOTES AT MEETING
       40
PREPARE SUMMARY REPORT
      40
PROJECTED LABOR BUDGET
                        EST HOURS X  RATE   =  EST COST
    PROF LEVEL 4
    PROF LEVEL 3
    PROF LEVEL 2
    PROF LEVEL 1

        TOTAL DIRECT
LABOR OVERATE
      80
      "88"
      24"
      192
    RATE
    FRINGE BENEFITS     35%
            sub-total (1) + above
    OVERHEAD           52%
     OTAL LABOR OVERHEAD
         31.85
        "19.89"
        "13.60"
        "12.44"
            $2,548
            $1,750"
            $  326
    BASE

    (1) ABOVE
  $6,242
                $4,624
                     (1)
                            $1,618
                    (2)
                ABOVE   $3,246
                        (3)
             $9,488
               (SUM OF 1,2&3)

-------

-------
     ER DIRECT COSTS
     WORD PROCESSING/COMPUTER (HOURS)   50 HRS @$5.00/HR $250
     PHOTOCOPYING  ^COPIES/PAGES      2000 @ .10 $200
     POSTAGE/DELIVERY                  $200 _
     MEETING ROOM RENTAL #DAYS/#ROOMS    $3XX)6 - "~
     A/V RENTAL
     CONTRACTOR TRAVEL
                SUBTOTAL   $8,150
                                        $3,000
                                        $1,500"
    TOTAL LABOR/OVERHEAD
        (FROM PAGE 1)
                                        $9,488
TOTAL DIRECT COSTS
AND OVERHEAD (FROM LINE ABOVE)


GENERAL & ADMINISTRATION (18.5%)

TOTAL A & B

FEE (5.25%) C
                                        $17,638
                                        $ 3,263
                                        .$20,901

                                        $ 1,097
                                                     (A)
                                                      .(B)

                                                      (C)
                                                    (D)
    TOTAL WORK ASSIGNMENT COST
A
HBfc):
               ACCT:
                                    $21,998
                                            (SUMC&D)
                                         DCN:

-------

-------
                 INDEPENDENT GOVERNMENT COST ESTIMATE
      (For Internal  Use  Only — Not to Be Included as Part of  the
             Package that is Submitted to the Contractor)
I.   Hours

(Note:
            Refer  to  contract or  PO  for hourly  rates  and labor
            classi f icat ions )

  Labor Classification     Rates per- hr   X    proposed brs. = cost

  PL-4 Project Leader          $54.00               140         $7,350

  PL- 2 Scientist               $32.00             2,080         $66,530

  PL-1 Associate Scientist     $26.00               200         $5,200
  Total
                                                2,420          $79,320
 i
 IX.   other Direct Costs

 (Note:     Includes telephone,  vehicles,  office  supplies,  truck
            repairs, field supplies, copier, and computer)

       Assume 25% of direct labor costs = $19,830


 III.  Travel


 Item                          Quant          Rate           Total

 RT Smethport-NYC              1 Trip       $292.00          $292.03
 Per Diem +  Lodging           5 days       $146.00          $730.00
 Ground Travel                 5 days       $  40.00          $200.00

 RT Boston-NYC                 1 Trip       $128.00          $228.00
 Per Diem + Lodging            5 days       $146.00          $730.03
 Ground Travel                 5 days       $  40.00          $203.00

 Total                                                     $2,280.00


 IV. Total Cost

 Labor                         $79,320
 Other Direct Costs            $19,830
 Travel                        S  2.280
                               $101,430
 Fee (7% of Total Costs)*      $   7,100.10

TOTAL  COST                     $108,530.10

* Refer to contract or Project Officer for fee percentage.

-------

-------
      CHAPTER IV
     At the Helm
           or
Managing the Work Assignment

-------

-------
                      Chapter IV
                   Table of Contents
INTRODUCTION	  1

SETTING UP A FILE	  1

DAY TO DAY COMMUNICATION & PAPER TRAIL .	  1

COMMUNICATION  WITH  SUBCONTRACTORS  AND
    CONSULTANTS 	,	  4

COMMUNICATIONS WITH TASK MANAGER(s) AND POs ......  4

CONTRACTOR COMMUNICATION AND FREQUENCY	  5

ON-GOING ACTIVITIES	9

END OF YEAR ACTIVITIES 	   10

I NEED TO MAKE SOME CHANGES		   11

ADDING SUBCONTRACTORS AND CONSULTANTS 	   11

WHAT TO  DO IF THE INSPECTOR GENERAL DROPS BY	   13

FIGURE 4-1 WORK ASSIGNMENT FILE	2

FIGURE 4-2 MONTHLY FINANCIAL REPORT	 . .8

FIGURE 4-3 MONTHLY TECHNICAL REPORT	10

-------
EXHIBIT 4-1  PHONE LOG



EXHIBIT 4-2  MEETING RECORD




EXHIBIT 4-3  WORK ASSIGNMENT STATUS NOTIFICATION



EXHIBIT 4-4  WAM DELIVERABLES REPORT



EXHIBIT 4-5  SUB-CONTRACTOR/CONSULTANT APPROVAL FORM

-------
Chapter   IV  At   the
Managing      the
Assignment
                                           Helm   or
                                               Work
INTRODUCTION

The next stage in administration of a work assignment (WA) is the actual day-to-day
management of the work detailed in the contractor's work plan. Effective day-to-day
management of a contractor's work requires many different aspects.  For example,
it is essential  that a work assignment manager (WAM) maintain open lines of
communication with contractor's designated point of contact for the WA, monitor
delivery of products, dollars and hours and provide good technical direction (TD) (i.e.
direction which assists contractor in accomplishing statement of work) and provide
comments on and approve reports and deliverables.
                                                            or
Additionally, WAMs are expected to provide comments and input on draft and interim
products in a timely fashion.  Another essential element in the day-to-day
management of contracts is to provide input to the project officer (PO) so that
payments to contractors can be made in accordance with the provisions of the Prompt
Payment Act. Finally, written records of the activities under a particular WA must be
maintained since they serve as your documentation on all aspects of the WA. This
chapter focuses on the activities required to manage a WA from day-to-day.


SETTING UP A FILE

     Now that you have a WA in place with a work plan you should set up a file to
follow through your WA. A guide to setting up a WA file is shown in Figure 4-1.

     For small WAs, files can probably be accommodated in a three ring binder or
accordion folder.  For larger WAs with large deliverables (reports, studies,  etc.) you
may want to set  up in a file drawer cabinet.  This choice is yours based on your
anticipated paperwork.
Chapter IV
                                                   January 13,1993

-------
                                                Close-Out Evaluation
                                            Review Notes on Defverabitt
                                          Dellverables
                                       Evaluation (if Award Fee)
                                   Monthly Financial Reports
                                Monthly Progress Reports fTech)
                              Meeting Notes
                           Phone Log Summaries
                        Contractor Correspondence
                     Internal Correspondence
                  Govt Furnished Property
                Work Plan & Approval
             P Ft's
         Work Assignment Amendments
      Original Work Assign Package
    Work Assignment
    File
Figure 4-1
DAY TO  DAY COMMUIMIC;

      The technical monitoring by the WAM is crucial in assuring that the contractor
understands the work requirements and performs in a manner to produce quality
results within the time required. Throughout the period of performance the WAM will
often need to communicate with the contractor for the purpose of directing the effort
to ensure that the desired results are achieved.  The WAM needs to check with the
PO to assure they have authority to provide TD to the contractor.  TD should always
be in writing with a copy to the PO. (The TD clause allows for verbal TD if confirmed
in writing in 5 days)  Note that WAN's cannot bind the government for additional
services or supplies so be careful not to mislead the contractor. The Government
could be bound to pay the contractor's costs for services rendered ("implied-in-fact"
contractKJL  _____ __ „ „_„ _ „„. „ „„.„„„	„.„„..„..,„„,„
                                                       Remember that TD  is
Chapter IV
January 13,1993

-------
"Direction to the Contractor which essists him in accomplishing the Statement of
Work".

      Following are some do's and don'ts to assist you in communicating with the
contractor.  Good communication ensures that everyone understands the WA and
planned approach.  Communication  can foster team spirit and commitment to the
project, keep a project going smoothly and can get a troubled WA back on track.

      DO	
      o    Keep  a   written  record   of   communications   with   the
           contractor and communicate at least weekly:

                 -  By phone - See Exhibit 1 at end of this Chapter
                 -  By meeting - See Exhibit 2 at end of this Chapter
                 -  By written correspondence

      o    Meet with contract personnel at  specified intervals.   To eliminate
           confusion, miscommunication  and the potential for personal services,
           you should establish at the beginning of the work the individual with
           whom you should be communicating and always communicate with that
           person.  This is usually the WA leader. Confirm any TD evolving from
           communication with the contractor by issuing  a written technical
     	directive and minutes of the meeting.  	

      YOU  ARE PROBABLY  COMMUNICATING  ADEQUATELY  WITH  THE
      CONTRACTOR  IF YOU HAVE  SEEN WRITTEN  OUTPUT OR  DISCUSSED
      PROGRESS OF THE WORK WITHIN THE LAST ONE TO TWO WEEKS, IF YOU
      FEEL UNCOMFORTABLE,  AND  ARE BEGINNING TO WONDER WHAT THE
      CONTRACTOR IS DOING, YOU NEED MORE FREQUENT COMMUNICATION.
o     Evaluate contractor performance throughout WA.

o     Tell the contractor when they have produced a good interim product.

o     Express your position clearly when the contractor has produced an inadequate
      product.

o     Keep written notes to the file and cc the PO.
Chapter IV
January 13,1993

-------
DON'T-—

o     DON'T -Create a Personal Services WA - a personal services WA results when
the Government assumes the right to instruct supervise or control a contractor's
employee in how he/she performs the work.  (It is the contractor's right to hire and
fire, to assign and organize the work.) This is where good negotiation skills come to
play.
o     DON'T-Direct the contractor to subcontract any portion of the work. The
      governments' only direct contractual relationship is with the prime contractor.

o     DO NT--Ask the contractor to do additional work outside the WA scope.

o   .  DONT-Direct  the contractor to perform services  which are "Inherently
      Governmental" in nature. (Refer to EPA Order 1900.1 - Appendix C to this
      manual). This is in direct violation of EPA contracting procedures. If you are
      unsure meet with your PO to review services required.

o     DONT-lncrease or decrease estimated cost of the WA.  This may only  be
      done by the contracting officer (CO) through request of the PO. If you need to
      change the hours see your PO.

o     DON'T-Alter period of performance of WA. This may only be done by the CO.

o     DON'T—Change other express terms & conditions.  EPA Procurement and
      Contracts Management Division requires the contractor to immediately notify
      the (CO) when any government action implies a contract change.
COMMUNICATION  WITH   SUBCONTRACTORS   AND
CONSULTANTS

      o    Never  Direct that any portion of work should be performed by  a
           subcontractor rather than prime contractor.

      o    Never direct the Prime to subcontract with a specific firm.

      o    There is NO DIRECT CONTRACTUAL RELATIONSHIP, (i.e. "Privity of
           Contract") between EPA and any subcontractor. Because there is no
           , "Privity of Contract"  EPA may not communicate directly with its
           subcontractors on contractual  issues. (Whenever  you  are providing
           TD to a sub-contractor, the prime contractor must be involved).

Chapter TV                            4                        January 13,1993

-------
COMMUNICATIONS WITH TASK MANAGER(s) AND POs

TASK MANAGER:

      If you are managing a WA where other individuals are overseeing the technical
aspects of a task, it  is important to communicate at least weekly with these
individuals. It is critical that your task manager(s) review the technical and financial
reports prior to your submitting your approval of costs to the PO. These individuals
have the greatest knowledge regarding the work being conducted under the task.

PO:

      Interaction between the PO and WAM is critical to ensure effective contract
management. The PO is the first point-of-contact if you have any questions regarding
what is allowable under the contract.  The PO can also assist in preparing the SOW.
The PO is also the individual to contact when you are dissatisfied  with contractor
performance; when you need to amend a WA; and when you have carry over of two-
year money.
Monthly Activities

      o    Technical and Financial Progress Report

      Good technical and financial progress reports will give the complete status of
all project elements; highlight the contractor's major accomplishments; point out any
problems or obstacles; propose any changes; discuss work to be performed/completed
during the succeeding month; and compare the level of effort expended to date with
that proposed and agreed to in the work plan. If you are not satisfied or if something
does not look right, discuss it immediately with the contractor.
If you cannot get the information that you need to properly evaluate progress in the
WA, notify the PO. Also notify the PO if you feel charges made are not in line with
work performed. If you don't challenge inaccuracies, they may later be considered
to have been accepted by you as accurate. Specifically you should review to ensure—

o     Who are the individuals who worked on the WA this month? Do I know what
      they did? Are there any unexpected names?
Chapter IV
January 13,1993

-------
o     Were deliverables submitted as scheduled during the performance period?

o     The LOE charged is commensurate with progress (i.e. if they say they worked
      for 40 hours does this seem right?). Does the mix of P-levels seem appropriate
      for the work done?

o     Are travel charges appropriate for the period? If there was a long distance trip
      was it approved in the work plan?

o     Are photocopying charges commensurate  with deliverables received? (Are
      you paying $1,000 for one copy of a 5 page document? Remember contractors
      are not allowed to print and may only xerox 5000 of one page or a multiple of
      25,000 for more than one page.

o     Is computer time commensurate with needs?

o     Is the level  of subcontractor effort charged  commensurate  with the level of
      progress made? (Note subcontractor charges often lag behind and may not be
      included in  the reporting period for which the activity took  place.)

o     Are dollars compatible with work completed for period of performance and to
      date?
      o Subcontractor Financial Report

      The financial information that you get from subcontractors will vary depending
on the type of contract the prime has with the sub.  If the contract is cost-plus you
should receive the same level of information  as from the prime.  If the contract is
fixed-price, the charges will be based on the percentage of work completed, usually
as reflected by hours charged.  You should still be able to get detailed information on
the hours worked and by whom, travel if more than incidental, duplication pages and
charges.

      Your review is important to (1) ensure progress toward your final product, (2)
enable payment for work performed to date, and (3) to  set your project back on
course or make changes as a result of-findings thus  far.
Chapter IV
January 13,1993

-------
A sample technical and financial progress report are shown in Figure 4-2 and 4-3.

o    Invoices

      The PO receives invoices from the National Contract Payments Division in North
Carolina and will review the invoice and recommend payment of the voucher based
on your feedback from review of the technical and financial progress reports.  POs
have a review form for you to sign certifying that costs appear reasonable for work
performed. The Prompt Payment Act necessitates your review/feedback on the date
the PO  requests.

o    Payment of Award Fees

      For cost plus award fee, an award fee plan is included in the contract.  A
performance evaluation board (PEB) is established at the time of award. (PO is usually
Chair)   These individual perform the in-depth review of all  aspects of contractor
performance at periodic intervals (usually every 4 months). They then recommend an
appropriate amount of fee to be awarded to the contractor to the Fee Determination
Official  (who is usually  the Chief of Contracting Office). Usually  WAMs are the
Performance Monitors. Performance Monitors submit reports for each performance
period.  Events are reported on EPA Form 1900-41B.


ON-GOING ACTIVITIES

      0 DELIVERABLES

            The WAM is responsible for continuous monitoring of the  contractor's
efforts in order to ensure satisfactory quality of work performed. This does not mean
taking charge of the contractor's work effort-it does mean:

(1)    Using technical expertise to identify contractor actions or lack of action that
      affect the quality of the work.

(2)    Identifying and calling the contractor's attention to deficiencies.

(3)    Keeping well-informed of what the contractor is doing.

(4)    Working out appropriate action to remedy deficiencies.
Chapter TV                             ^                         January 13,1993

-------
CONTRACTOR: Environmental Associates, me.
CONTRACT NUMBER:  68-C1-9999
PERIOD OF PERFORMANCE: Option I

Work Assignment: 23
Work Performed: July 1-July 31 , 1 992
DIRECT LABOR

Full time Direct Labor
Part Time Direct Labor

TOTAL DIRECT LABOR

OVERHEAD

Full time Direct Labor
Part Time Direct Labor

TOTAL OVERHEAD

OTHER DIRECT COSTS

Equipment Rental
Travel
Copying
Telephone
 Long Distance                50.36
Postage & Delivery
Other Direct Costs
Consultants
Subcontractor
Material Handling
General & Administrative

SUBTOTAL

FEE

TOTAL FEE

TOTAL
                                         4~2
       Total WA LOE: 3000
             Total WA Celling: $165,000
             Per hour cost: $55.00
QUANTITY CAT.
350 HRS
40 HRS
390 HRS
90 % #
45 % #
31 HRS
300 PG

8 %
20 
7A/_
TO
CURRENT
BILLING
6,268.00
660.00
6,928.00
5,641.20
297.00
5,938.20
94.55
1,368.00
24.00
80.56
27.00
191.00
2,200.00
176.00
2.930.26
19,957.57
1,397.03
1.397.03
21.354.60
CUMULATIVE
BILLING
23,618.00
1,320.00
24,938.00
21,256.20
594.00
21,850.20
387.50
2,855.00
168.00
256.13
82.00
568.00
4,586.00
366.88
10,220.97
66,278.68
4,639.51
4,639.51
70,918.18
Chapter TV
8
                                                                    January 4, 1993

-------
 CONTRACTOR: Environmental Associates, Inc.
 CONTRACT NUMBER: 68-C1-9999
 PERIOD OF PERFORMANCE: Option I

 Work Assignment: 23
 Work Performed: July 1-July 31,1992
                       Total WA LOE: 3000
                              Total WA Ceiling: $165,000
                              Per hour cost: $55.00
 COST PER HOUR

 HOURS

 Robespierre
 Jeanne Dixon
 Enrico Fermi
 Malthus
 Emily Dickenson
 Lee Thomas

 TOTAL PRIME LOE

 Consultant

 Subcontractor

 TOTAL LOE
F/PTIME    P LEVEL
                                   52.08
              CURRENT
               47.60

         CUMULATIVE
F
F
F
F
P
F
  4
  3
  2
  2
  2
  1
20
10
160
80
40
80
390
20
80
10
500
300
80
480
1450
40
                                    410
                                  1490
 Travel

 Fermi - DC to Dallas
 Malthus - DC to Dallas
                              TOTAL
      3 da
      3 da
100
100
396.00
396.00
Chapter IV
                                            January 4,1993

-------
                    	Figure 4-3 	

                             Monthly Technical Report

                                   Work Assignment 01
                     Period of Performance June 1,1992 - June 30,1992
                                                        Level of Effort   1000

                                                            Hours Used:     500
       EPAWAM: John Smith

       CONTRACTOR WAM:  Joe Blow

       SUB CONTRACTOR: Waterworks

       Statement of Work:

       Work to be completed under this work assignment includes: a final draft of ...... document;
       continued development of a guide; and preliminary investigations for techninai guidance.

       Summary of Activities:

       Meeting was held with EPA pn June 10. A draft of Chapter 2 and 3 was provided to WAM.
       Literature search was begun for technical guidance.
                                                                       •i

       Planned Activities Next Month:

       Complete Chapters 4 and 5 and send to WAM for review.  Continue literature search.

       Project Status;
       On-going

       Problems:
       None

       Staff Changes:
       Mary Louise win replace Karen Smith.


       The quality of the contractor's output is also dependent upon the competence of its personnel.
In many cases, the best way to ensure quality of work performed is to ensure that personnel with the
necessary capabilities, qualifications and experience are assigned to the work effort. If you are unsure
of the personnel assigned to your WA. ask the PO  if he/she has a resume or any information on past
performance.


functions are  the contractor's, not the Government's." The WAM's role Is one of reviewing and
working with the contractor to remedy any inadequacies.  Exhibit 4-4 may be used to evaluate the
deliverable and should be kept in your files for use during close-out.
Chapter JV
                                           10
January 13,1993

-------
o      What Do I Have?

             In reviewing a deliverable received from the contractor look for the following:

             o     Are Major ideas expressed with clarity and power?
             o     Does the structure lead the reader sensibly through
                   the arguments?
             o     Is the deliverable in line with the original specifications?
             o     Is analysis sufficiently deep and clear?
             o     Is the material written accurately and clearly?.
             o     Is the tone and level of information appropriate for the target audience?
             o     Is the product technically accurate and valid?
             o     Are the data substantiated to your satisfaction?
             o     Is the design harmonious and pleasing?
             o     Where style and creativity are called  for (videotape,  training,  updates.
                   brochures) are they evident?

       If you have questions, contact the contractor and talk with the PO immediately.  In many
instances a simple phone call will provide the answer.

             o  Know what you are going to ask
             o  Stick to your "agenda"
             o  Use non-confrontational language
             o  Summarize the agreement reached and write it down.

       If you and the contractor can not come to an understanding, get the PO involved. Together
you can decide the best approach which may include a recommendation that the CO issue a stop-work
order or terminate the WA.


END OF YEAR  ACTIVITIES

       All WAs  and work plans must be written for the "contract" year, (or  "option
period")  However, sometimes all dollars are not spent due to many reasons. If this
occurs, you must do a new WA for the dollars which "carry-over." Not all funds can
be carried over (i.e. single year funds), check with your PO early.

Any hours used in the new WA come from the option period for which the WA is
written. You need to make sure that your PO is aware that there will be carry-over
dollars by August  15, since  carry-over  dollars  must  be  moved by  the  CO  in
September.

A WA for carry-over funding requires the same paperwork as an initial WA.  While
carry-over of work is common, it is best to plan your work so that it is completed by
the end of the option year.
Chapter IV                               11                            January 13,1993

-------
 EXAMPLE OF CARRY-OVER FUNDING
• NEED TO MAKE SOME CHANGES	

Amending a WA

      o For Additional Resources

      -  Procedures for adding additional resources as a WA amendment are the
same as writing an initial WA. The only difference being that an amendment usually
contains a much shorter SOW. Therefore in amending a WA you should refer back
to the section on Initiation of Work in this manual. However, a new WA, not an
amendment should be written if the scope is significantly different than originally
anticipated.

      o For More Time at No Cost

      ~ An extension with no change to the estimated cost, requires only a cover
form (see Exhibit 3-1 in Chapter 3) and a new deliverable schedule. What you are
doing is amending the WA to allow the contractor more time to complete the effort
at no additional cost to the government.


ADDING SUBCONTRACTORS  AND CONSULTANTS

      o Subcontractors

      -  The Government's only direct contractual relationship is with the prime
contractor; there is no such relationship between EPA and any subcontractor at any
tier.  What this means is that EPA has no right to deal directly with a subcontractor
on any issue, and the subcontractor has no right to obtain a direct decision of EPA.
The  fact that the  prime  contract requires  advance  Government consent  to  a
subcontract does not remove the subcontractor from the non-privity rule.
Chapter TV
12
January 13,1993

-------
      When a prime  contractor requests approval to add a subcontractor to the
specific WA, you must review the request for technical competence, level of effort,
costs and rates and conflict of interest. (If the subcontractor rate is much higher than
that negotiated for the contract, it may cause the contractor to loose part of his fee
for the year. Both you and the contractor should be aware of this potential problem.)
Exhibit 4-5 is a check list to guide you through this review. If you are satisfied with
the subcontractor selected by the prime you should sign the attached form and submit
it to the PO. Subcontractors are added to the contract by the CO by modification of
the contract. Usually this can be accomplished within 2-3 weeks.  In most contracts,
EPA approval of subcontractors for under $25,000 is not required. However, consult
you PO for the specific terms of the contract you are working under.

      o  Consultants

      -  Often in the performance of EPA contracts  there is a need to bring in a
consultant with a particular expertise to assist in some aspect of the work. However,
hourly or  daily  rates  charged by consultants are often  prohibitive and  not
commensurate with the technical benefits we might derive. Therefore, when the use
of consultants is anticipated as a possibility, the CO will insert a clause in the original
contract requiring the contractor to obtain EPA approval before a consultant is used.
Consultants are not included  in the $25K threshold.

      The technical qualifications  of  the  proposed consultant, the benefits to be
derived from his  or her use,  the amount  of usage, and the rate proposed, are all
reviewed by EPA. Exhibit 4-5 may also be used to perform this review. A contract
modification will be executed by the CO to approve the use of the consultant and it
will usually specify the fixed rate to be charged and set a limit on the number of hours
or days the consultant can be used.

The same rules that apply to  directing subcontractors  apply to  consultant work. In
other words, EPA cannot direct the contractor to hire consultants or influence the
selection of such a consultant in any way.

NOTE:  When the  contractor requests an increase in ceiling for a  consultant or
subcontractor which  has previously been approved.  You must also  complete a
checklist (Exhibit 4-5) and ensure  that hourly rate is  not significantly affected for
overall contract.
Chapter IV
13
January 13,1993

-------
WHAT TO DO IF THE INSPECTOR GENERAL DROPS  BY

      The Inspector General Act of 1978 (P. L. 95-452),  created the Office of
Inspector General (OIG). The OIG's role is to review EPA's financial transactions,
program and administrative activities, investigate allegations or evidence of possible
criminal, civil, and administrative violations and to promote economic, efficient and
effective operations within the Agency.   The OIG is specifically authorized access
to all in-house records, reports, audits, reviews, documents, papers, or other materials
to help with its investigations.

      In carrying-out its mission, representatives of the OIG will initiate independent
and objective audits and investigations which will sometimes require the assistance
of WAMs. When this occurs, WAMs must provide documentation, records and files
and  discuss procedures,  practices and  transactions to  assist the OIG  in its
investigation. In such situations, a WAM must be helpful, cooperative and provide
information requested in a timely and forthright manner.

      The OIG prepares reports based upon its findings. The draft report is reviewed
by the WAM and copies of the WAM's comments are sent with the report to  EPA
management with an independent appraisal of whether desired results and objectives
are  achieved  efficiently, economically and in  accordance with prescribed laws,
regulations, policies and procedures. The results of which are designed to improve
the administration of EPA programs.

      For further information refer to EPA Manual 6500 "Functions and Activities of
the Office of the Inspector General".  Check with the Senior Procurement Official
Assistant on where to view a copy of the manual.

      WAMs who are aware of fraud, waste, or mismanagement in EPA contracting
practices should contact the EPA Inspector General Confidential Hotline (800) 424-
4000. Callers in area code 202 (or on the FTS network) may also use 260-4977.
Chapter IV                            14                        January 13,1993

-------
                    Chapter IV

                     Exhibits

4-1        Phone Log
4-2        Meeting Record
4-3        Work Assignment Status Notification
4-4        WAM Deliverable* Report
4-5        Sub-Contractor/Consultant Approval Form

-------

-------
EXHIBIT 4-1
/
t-
t
u

Name: Date:
Company: Subject of Calf:
Phone Number:
Address:

FoIlowHip
Needed Summary of Conversation






*-














\
..*

























_





-------
                                                    EXHIBIT 4-2
                       MEETING RECORD
                         CONTRACT  NO.
                    CONTRACT:
DATE/TIME:
ATTENDEES;
PURPOSE/DESCRIPTION:
DECISIONS MADE:
NEXT STEPS (EPA, CONTRACTOR)  (Actions to Take. Issues to Resolve):

-------
                                                            EXHIBIT 4-3
                     WORK ASSIGNMENT STATUS NOTIFICATION
  CONTRACT NO:
                                     WORK ASSIGNMENT NO.
  PERFORMANCE PERIOD:
  SUFFICIENT PROGRESS HAS BEEN MADE TO SUPPORT PAYMENT:
  INSUFFICIENT PROGRESS HAS BEEN MAD&
("(•COMMEND WITHHOLDING  CALL)     (PART)  OF PAYMENT FOR THE FOLLOWING
 HiWSOf"
)NS:
                                               Signature  (WAM)
                                                    Date

-------
                                                              EXHIBIT 4-4
                                                             Date:
                    WORK ASSIGNMENT MANAGER'S REPORT
                      ON DELIVERABLES AND PRODUCTS
Work Assignment Manager:
Work Assignment No.:	
Contractor:	
Contract No.:	
Evaluation Period:	
Program Area:	
WA Amount:	
Deliverable:	
                         WORK PLAN REQUIREMENTS
                                                       YES
                                           NO
 Was Work Completed on Time?                         	

 Was Work Within Budget?                               	

                                   Quality

           (Check one of the  following, with  1  being the lowest score)

                                               1234

 Rate the overall quality of the  product         • 	  	  	  —

 Did Product Meet ali Requirements of,          	  ——  	  —
 the Work Assignment?

 Did Product Need Serious Reworking?           ' 	  	  	  —
                                                •
If no  Product for this Quarter, Please Rate       —_  	  	  	
"Contractor's Progress

Please Indicate in Comment Section the Justification for Any Substandard
(i.e., ^ or 2) Score.

Comments:	  	
 CHECK ONE
                  WAM's FILES
                  PO's FILES
                  EPA LIBRARY

                  OTHER
LOCATION  OF PRODUCT

            LOCATION AND FILE NO. (Please Explain)

-------
                                                                                EXHIBIT 4-5
     OMMENDATION FOR APPROVAL OF PROPOSED SUBCONTRACTOR AND/OR CONSULTANT
  WORK ASSIGNMENT NO:
CONTRACT NO:
SOLE SOURCE SOLICITATION:
If sole source dp you agree with the Prime Contractor method and reason for selection?  If not. why?
TECHNICAL:
  Does the attached resume/work plan demonstrate that the proposed consultant-subcontractor has
the expertise in the specific areas needed by the Work Assignment?
  If reasonable, state that technical expertise is the primary criterion for this Work Assignment:
LEVEL OF EFFORT:
  Is the level of effort proposed consistent with the Government's estimate for this Work Assignment.

  Further, wOl approval of this consultant/subcontract adversely impact the cost of the contract In this
term.

  If team subcontractor/consultant, do the hours proposed compare favorably whit hours negotiated at
time of award?


       rate per hour comparable to other consultants and/or subcontractors possessing like expertise.

  How does the rate compare with the rates for the P-X level negotiated in the contract?

  The rates proposed are deemed reasonable based on program need, specialized qualifications, and
availability of the expert to perform services within the required timeframe.

  Does the cost per hour proposed compare favorably with costs negotiated at time of award?
                                        YES
                          NO
CONFLICT OF INTEREST:
 Certification attached from recommended consultant or subcontractor.
 rf no, why?
AGREEMENT:

 A copy of the subcontract or consultant agreement is attached?
 All required prime contract flowdown clauses are referenced in the subcontract agreement.
     on the above, I recommend approval of the proposed subcontractor or     consultant.
     Work Assignment Manager   (Date)
Project Officer
(Date)

-------

-------
   CHAPTER V

  Land Ahoy!

       or
   Closing Out
the Work Assignment

-------

-------
                  Chapter V
              Table of Contents
INTRODUCTION
1
THE CLOSE-OUT PROCESS	  1



EXHIBIT 5-1 OW WORK ASSIGNMENT CLOSE-OUT



EXHIBIT 5-2 CLOSE-OUT EVALUATION OF CONTRACTOR

-------

-------
Chapter V

Land   Ahoy   or  Closing   Out

the  Work Assignment

INTRODUCTION
This chapter contains information on when and how to close-out a completed (or
interrupted) work assignment (WA). Close-out is the formal step assuring that no
further work will be done by the contractor on a particular WA. Note  that little
information currently exists on close-out, therefore, most of the requirements stated
in this chapter are not Agency or OW requirements, but are OW recommendations.
THE CLOSE-OUT PROCESS

The EPA Contracting Officer (CO) is the person authorized to close-out a WA, but it
is the WAM's responsibility to notify the Project Officer (PO) that the WA should be
closed,

A.  Reasons to Close-Out WA's:
    1.   To assure that costs do not continue to be  assessed to your WA.
         Unnecessary charges may include:
         a.    continuation of monthly reports
         b.    computer usage and other indirect costs
         c.    billed hours by contractor
    2.   To recover unexpended funds for use elsewhere;
    3.   To complete your files and (those of the PO and CO);
    4.   So you'll have one less thing to manage (until the next WAI).

B.   When to Notify the PO of Close-Out:
    1.   Within 2 WEEKS of when the work has been completed.
         -OR-
    2.   IMMEDIATELY AFTER a decision to discontinue the project. Examples
         of reasons why this may occur are:
         a.    Lack of funding to complete the project
         b.    Change in program priorities
         c.    Poor quality or excessive costs
Chapter V
January 13,1993

-------
C.    How to Close-Out the WA:

      Confirm by reviewing WA and deliverables that the contractor has met all
requirements (if closing-out because work has been completed).

      If close-out is due  to a  decision to discontinue the project, (6.2 above),
DOCUMENT the decision.

      Verify  with the contractor  (verbally) the  financial information in the  latest
monthly report and indicate your intent to close-out the WA.  If there is a problem
with the information (e.g., charges are excessive) try to resolve with the contractor
as you would other monthly reports.  If problems persist, notify your PO.

Submit to the PO the following:

      a.     Completed OW WA Close-Out Request Form (Exhibit 1 provided at the
            end of this chapter)

            The PO will then submit this form to the CO who in turn will complete
            the Procurement and Contracts Management Division closeout process.
            The CO will provide a copy of the signed form to the PO to show that
            closeout is complete, and the PO will send a copy to you (the WAM) for
            your files.

            Two Things to Remember:

                  1.  Leave some  money  in  the WA for  lagging  charges.
      subcontractor and consultant charges can remain outstanding for months after
      the work is performed. Work with your PO to determine the amount to  leave.

                  2.  If there is leftover money,  indicate on the  "Close-Out Form"
      so that the remaining funds can be transferred back to the contract for  use in
      supporting another WA. By doing this you are helping to ensure that the funds
      and capacity will be available for  other  projects.   Also indicate on  the
      "Close-Out Form" which WA the  funds should be transferred to if you know.

      b.     Completed  Contractor Performance Evaluation  Form (Exhibit  5-2
            provided at the end of this chapter)

      c.     Copies of Final Deliverables


form the location of fmal deMvtrabtes {e^fi.;WA fItes in BM XXX, office library, other).
Chapter V
January 13,1993

-------
Work with the PO in collecting all government furnished property, (GFP). The PO will
provide you with further information on what qualifies as GFP.
      D.    Maintaining Records:

      1.    What to Save and for How Long: WAMs are responsible for record copy
            of documents used for day-to-day technical direction of the contract.
            Documents include  work  plans  and  schedules,  draft  deliverables
            submitted by the contractor, comments provided to the contractor or
            other records of technical direction, contract monitoring logs and
            communication records, meeting records and notes, evaluation forms,
            SOW and level of effort (LOE) documents.  Copies should be kept in the
            office 1 year after contract expiration or termination, then they can be
            transferred to the Federal Records Center (FRC) to be destroyed in 7
            years.

      2.    Retiring Files:  Speak to your PO to arrange to retire your files  1 year
            after the contract expires.  The PO can assist you  in contacting the
            Records Management Staff  for retiring files for storage.

      NOTE: The Information Management and Services Division K>IRM) is in the
process of formulating a draft Agency control schedule on retiring contracts.
Chapter V
January 14,1993

-------

-------
5-7



5-2
         Chapter V





          Exhibits





OW Work Assignment Close-out Request



Close-out Evaluation of Contractor

-------

-------
                                                        EXHIBIT 5-7
          OW WORK ASSIGNMENT CLOSE-OUT REQUEST
3. CONTRACTOR NO:
4. CONTRACTOR:
                              1. WORK ASSIGNMENT NO.:	
                              2. AMENDMENT NO. (if applicable):
5. TITLE:
6. BRIEF DESCRIPTION OF CLOSE OUT:
7. LIST DELIVERABLES RECEIVED:
8. LOCATION OF DELIVERABLES:

9. COMPLETION DATE:
10. UNUSED DOLLARS:
                           APPROVALS
It:  WORK ASSIGNMENT MANAGER:

     Name:	
     Phone:	
     Branch/Mail Code _.	

12:  PROJECT OFFICER:

     Name:	
     Phone:	
     Branch/Mail Code
13:  CONTRACTING OFFICER:
     Name:
     Phone:
     Branch/Mail Code
Signature
                            Signature
                            Signature
Date
              Date
              Date

-------
                                                    EXHIBIT 5-2
        OW CLOSE-OUT EVALUATION  OF CONTRACTOR
^ Contractor: Period Covered:
Contract Numb*" . 	 Work Assignment Number! ^P
Work Assignment Manaaer





Protect Officer:




Ratings: 4-ExceOent 3-Very Good 2-Averaoe 1-Poor 0-1



IM • «•!•< MrftiM4«j
insansfocfory
(Circle one per criterion)
Rate the Following:
1.






II.


^


111.





IV.

%.
" V.
Technical Performance
Level of creative contribution
Effective application of relevant
stotutes/regulations/guideOnes
' Resourcefulness
Adherence to scope of work
Effectiveness of project planning
Comments:
Personnel Assigned
Technical competence appropriate to project
Commitment to the project
Effective interaction, responsiveness
Appropriate mix of professional levels
Comments:
Dellverables/Reporting
Quality of product, thoroughness, adequate
technical detail
Minimal corrections/revisions required
Quality assurance by Contractor
Adherence to schedule
Comments:
Budget
Efforts to keep within budget
Early notification of potential overruns
Notification when 75% of budget expended
Adequacy of Monthly Reports
Comments:
Overall Rating for Work Assignment

4
4
4
4
4


4
, 4
:; 4
-"• ' 4

4

4
4
4

4
4
Yes.
4

4

3
3
3
3
3


3
3
3
3

3

3
3
3

3
3
3

3

2
2
2
2
2


2
2
2
2

2

2
2
2

2
2
2

2








1
1
1
1

1

1
1
1

1
1
No
1

1

0
0
0
0
0


0
o ^
0 A
o W

0

0
0
0

0
0
0
•
0
VI. Miscellaneous Comments:
                                                 October 1992

-------
         APPENDIX
A.   ACRONYMS

B.   GLOSSARY OF TERMS

C.   EPA ORDER 1900.1
D.   EPA ORDER 1900.2

E.   WAM MODEL PERFORMANCE
     STANDARDS

F.   LABOR CLASSIFICATIONS

G.   N EG OTIATION  &
     COMMUNICATION

H.   CONFIDENTIAL  BUSINESS
     INFORMATION

-------

-------
             Appendix A



              Acronyms
Tterisez

-------

-------
APPENDIX A
ACRONYMS
      The following is an  alphabetical list of all acronyms used throughout this
Handbook.  Its purpose is to serve as a quick reference for those who  may be
unfamiliar with the lettered shortcuts that are used commonly to signify terms and
phrases associated with the EPA acquisition/procurement process.

AC&C     Abatement Control and Compliance
ADP       Automated Data Processing
CBI        Confidential Business Information
CFR       Code of Federal Regulations
CO        Contracting Officer
COI        Conflict of Interest
CPAF      Cost-Plus-Award-Fee
CPFF      Cost-Plus-Fixed-Fee
CS        Contract Specialist
DCN       Document Control Number
EPAAR     Environmental Protection Agency Acquisition Regulation
FAR       Federal Acquisition Regulation
FDO       Fee Determination Official                ;
FMD-RTP   Financial Management Division, Research Triangle Park, NC
G&A       General and Administrative
GAO       General Accounting Office
GFP       Government Furnished Property
GPO       Government Printing Office                                     v
GSA       General Services Administration
ICR        Information Collection Request
JOFOC     Justification for Other than Full and Open Competition
LOE       Level of Effort
OARM     Office of Administration and Resource Management
ODCs      Other Direct Costs
OFPP      Office of Federal Procurement Policy
OMB       Office of Management and Budget
OW        Office of Water
P-LEVEL    Professional Level of Contractor Staff
PCMD     Procurement and Contracts Management Division
PEB        Performance Evaluation Board
P.L.        Public Law

-------
PO        Project Officer
PR        Procurement Request/Order
PRA       Paperwork Reduction Act
QA/QC     Quality Assurance/Quality Control

RFP       Request for Proposals
S&E       Salary and Expenses
SF        Standard Form
SOW      Statement of Work
SPO       Senior Procurement Offical
SPOA      Senior Procurement Official Assistant
TD        Technical Direction
TEP       Technical Evaluation Panel
TOC       Table of Contents
WA       Work Assignment
WAM      Work Assignment Manager


-------
   Appendix B



Glossary of Terms

-------

-------
APPENDIX  B
GLOSSARY OF TERMS
Annual Appropriations

      May be obligated only during the fiscal year covered by the Appropriation Act.
Unobligated funds are lost to the Agency (e.g., EPA's S&E appropriation)

Multi-year Appropriations

      May be obligated during a specified period in excess of one year, but may not
be obligated after the life of the funding. (These are usually two-year appropriations
e.g., EPA's R&D and AC&C appropriations. R&D's number is 689/00107.) However,
these funds must be recertified when using a prior year account number.

No-year Appropriations

      Are "on-going" funds and may be obligated until the appropriation is exhausted.
Funds not obligated remain with the Agency and do not lapse back to the Treasury
(e.g., EPA's Superfund appropriation).  However, these funds must be recertified
when using a  prior year account number.

Bona Rde Need Rule

      A fiscal year appropriation may be obligated only to meet a legitimate or bona
fide need arising in the fiscal year for which the appropriation is available.
      Issue: This rule comes into play when you have end of year funds  that you,
either must obligate or lose.

Carryover Funds

      Funds that are not obligated by the end of a fiscal year and which may be
obligated in the next fiscal year. They include unobligated balances in no-year and
two-year appropriations.  Carryover funds may be used in the current fiscal year on
either contract actions brought forward from the  previous year,  or  on new
procurement actions.

Cost-Plus-Fixed-Fee (CPFF)

      This is the most prevalent type of cost-reimbursement contract awarded in this
Agency. Under this arrangement, the contractor is paid a negotiated fee that is fixed
at the inception of the contract. The amount of fee does not vary with actual cost,
but stays fixed unless adjusted as a result of changes in the work to be performed.

-------
 Cost-Plus-Award-Fee {CPAFJ

      A CPAF contract provides for a fee consisting of 1) a fixed base amount, and
 2) an award pool, the amount of which  awarded is based upon a subjective,
 judgmental evaluation by the Government of the contractor's performance.  Areas
 such as quality, timeliness, ingenuity, and cost effectiveness are evaluated by EPA in
 accordance with established criteria. The amount of award fee to be paid is decided
 at stated intervals (usually every quarter or trimester) during contract performance.
 The  overall objective is to motivate the contractor in a positive way to improve poor
 performance or to continue good performance.  This type of contract is considered for
 use  when  the  expected effort is anticipated to exceed $5 million  and a cost-
 reimbursement contract has been selected.  However, it may be used for contracts
 of any dollar value. Most Superfund cleanup contracts are CPAF contracts.

 Commitments

      The reservations of funds for specific projects or services to be procured.  The
 term refers to funds which have been submitted for obligation processing and entered
 in the Financial Management System (FMS) prior to formal obligation.

 Conflicts of Interest

      Organizational conflict of interest (COI) exists when an offerer or contractor for
any of a number of reasons has interests relating to the work to be performed under
an EPA contract which (1) may diminish the impartiality, objectivity, and soundness
of assistance and advice or otherwise bias work product, or (2) result in an unfair
competitive advantage.

      Personal  COI  exists  when an EPA employee's  judgment or actions in
procurement may be improperly influenced or biased in favor of a particular contractor
for reasons such as ownership of stock or relationship to employees of the contractor.

Contracting Officer (CO)

      That individual who because of  business, administrative,  leadership,  and
technical skills and capabilities is assigned by  EPA as responsible for assuring that
contracting is done as authorized by law and regulation. The CO is appointed by the
use of a Contracting Officer's Warrant and is the only one authorized to commit the
U.S.  Government through contracting.

-------
Contracts

      Legal documents between two or more parties which are used to acquire and/or
deliver real property or services.  In EPA, R&D contracts, program contracts, ADP
service contracts, and other contracts and contract modifications processed and
administered  by the Procurement and Contracts Management Division (PCMD) in
Headquarters, and the Contracts Management Divisions in Research Triangle Park
(RTP) and Cincinnati are included under this definition. Purchase orders, construction
contracts under $2,000, delivery orders under the Federal Supply Schedule and other
agencies'contracts, cooperative agreements, grants, interagency agreements, training
and tuition contracts, printing contracts, and other contracts not administered by the
three contracting offices are not covered in this Handbook.

EPA Acquisition Regulation (EPAAR)

      That portion of 48 CFR (Code of Federal Regulations) Chapter 15 that identifies,
by addition and exception, specific EPA implementation of the law and the FAR.

Federal Acquisition Regulation (FAR)

      The primary regulation for use by all Federal agencies in the acquisition of
supplies and services.

Fee Determination Official (FDO)

      That individual assigned responsibility for arriving at determinations regarding
a contractor's entitlement to portions of the award fee pool under a cost-plus-award-
fee contract, such determinations being made at specified times during the period of
contract performance based on evaluation and assessment findings of a performance
evaluation team.

Full and Open Competition

      The standard for use in Government acquisition, full and open competition
means all responsible sources are permitted to compete.

Justification for Other than Full and Open Competition (JOFOC)

      The formal document prepared by the  requiring activity  substantiating and
justifying that a particular procurement should be conducted on a non-competitive or
a limited  competitive basis for certain specified reasons.

-------
 Level of Effort (LOE)

      An expression of the number and type of employee-months or hours that the
 Government is purchasing under a contract.  In a term type contract, the level of
 effort will be based on the period of performance.

 Obligations

      The result of executed contracts or other legal promises to lease, purchase
 and/or deliver real property or services. Obligations occur when contracts or other
 legal documents are signed by the parties involved, and  submitted to financial
 management for recording and official designation of funds in accordance with the
 terms of the contract.  A contract or other document is referred to as  an obligating
 document.

 Procurement and Contracts Management Division (PCMD)

      The organization responsible for EPA contracting, which has operations offices
 in Washington Headquarters, Research Triangle Park, and Cincinnati, Ohio.

 Procurement Request (PR)

      The  document prepared by  a requiring activity containing the information
 necessary to permit contracting. EPA Form 1900-8 (Procurement Request/Order) with
 accompanying instructions.

 Technical Direction

      The exercise of authority by an individual named and specifically authorized by
 the contract to direct the performance of the contractor within the expressed scope
 of work found in the contract, so long as  such direction does not assign additional
 work, constitute changes to  the contract,  increase or decrease agreed-to estimated
 cost or price, or alter the  agreed-to delivery schedule or any other terms  and
 conditions of the contract.

Work Assignment

      Objectives  What you want to have  accomplished  by or through a  Work
Assignment. They are  the first things to be determined.

      Tasks       The steps that the contractor  must take to  accomplish  the
 objectives. Tasks are measured in terms of hours.

      Delh/erables      The products, goods, or  services which the Agency is
buying from the contractor. Many deliverables for the Office of Water (OW) are in the
form of documents.

-------
                Appendix C

         Use of Contractor Services
             EPA Order 1900.1
Septarterim

-------

-------
                Appendix C

         Use of Contractor Services
             EPA Order 1900.1
Sep*rrta1992

-------

-------
Appendix  C


Use  of  Contractor Services

(EPA  Order 1900.1)


        1. Purpose

        As more and more activities require contractor support to be furnished
        on-site at Government facilities, the question of whether these contracted
        actions are personal or nonpersonal in nature continues to arise.  The
        Government is normally required to obtain its employees by hiring
        through personnel channels.  Therefore, the procurement of personal
        servicesbycontractisprohibitedunlessspedficallyauthoiizedbystatute.
        This Order is designed to assist you in avoiding personal services
        arrangements in your contract activities.

        2. Responsibilities

        Contracting Officers, POs, Delivery Order Officers, and all other EPA
        personnel are responsible for ensuring that personal services relationships
        between Government and contractor employees are avoided.


        3. Definition

        Personal services contracts exist when the nature of the relationship
        between the contractor and the Government can be characterized as an
        employer-employee relationship. An employer-employee relationship
        exists when either by the terms of the contract itself, or because of the
        manner in which the contract is managed* contractor personnel are
        subject to the day-todaysupervisionandcontrolofGovemmentpersonnel.

        4. Assessing the Personal Nature of a Contract

        While one of the most important elements to be avoided in a contractual
        relationship is the supervision of contractor employees by Government
        personnel (see f. below), the Federal Acquisition Regulation (FAR
        37.104(d)> provides other descriptive elements which should be used as
        a guide in assessing whether or not a contract is personal in nature. All
        of these elements need not be present to have an improper personal
        services arrangement:


Septen*er1992                                                   C' 1

-------
     a.  Performance on-site.

     b.  Principal tools and equipment furnished by the Government

     c.  Services are applied directly to the integral effort of the Agency or
        an organizational subpart in furtherance of assigned function or
        mission.

     d.  Comparable services, meeting comparable needs, are performed
        in the same or similar agencies using civil service personnel.

     e.  The need for the type of service provided can reasonably be
        expected to last beyond one year.

     f.  The inherent nature of the service, or (he manner in which it is
        provided reasonably requires, directly or indirectly, Government
        direction or supervision of contract employees in order to:
        (1) Adequately protect the Government's interest;
       (2) Retain control of the function involved; or
       (3) Retain full personal responsibilities for the function supported
          by a duly authorized Federal officer or employee.  ' *

 5.  Principles for Managing a Contract

    a. The contracting officer is responsible for  determining prior to
       award, mat the contract does not involve the procurement of
       personal services.  But, even though supervision by Government
       employees is not directly required by the terms of the contract, a
       personal services situation can develop through improper contract
       management

    b. Technical management generally relates to the manner in which
       work direction is given. Interchange of inf orma don of a technical
       nature is not prohibited. In managing the contract, however, the
       following principles should be observed:

       (1) Insofar as possible, let the contract define the job. This can best
          be accomplished when the  contract  contains a definitive
          statement of work.

       (2) When the job scope must be changed, notify the contracting
          officer immediately so that the appropriate contract changes
          may be issued.
__._                                                    -   ___—

-------
               (3) When the job definition requires interpretation of the work
                  description or other direction which is dearly within the
                  project officer's authority, make sure that such direction is
                  issued from the PO to the appropriate contractor contact person
                  in the form of a written technical directive.  Do not give any
                  instructions to individual contractor employees.

               (4) Prepare memorandums for the record of all meetings, trips,
                  and telephone conversations relating to the contract

               (5) Ensure that all contractor and all EPA occupied space is readily
                  identifiable.   Generally, on site contractor employees are
                  physically located in  separate areas  from  Government
                  employees. In isolated cases where a general  area must be
                  occupied or used by both EPA and contractor employees, some
                  sort  of physical separation, identification of space,  and
                  scheduling of equipment usage should be arranged.

               (6) All requests for contractor follow-up or touch-up services
                  should be directed from the PO to the contractor's project
                  manager. Likewise, contractor employees mustoperate through
                  the contractor's supervisor to obtain any information needed to
                  complete the work product  >

               (7) Strictly avoid situations in which one EPA on-site contractor
                  provides support to another EPA on-site contractor, except
                  where the contract requires such support to be furnished (e.g.,
                  janitorial services, security services, etc.).

               (8) Strictly avoid Government intervention with respect to hiring
                  or firing of employees or assigning particular  employees to
                  specific tasks.

         6. Additional Guidance

            a.  A comprehensive paper on the use of contractor services which
               was prepared by the VS. Department of the Navy  follows. This
               paper further illustrates proper use of contractor  services. (See
               Attachment 1)

            b.  As in any contract situation, you are encouraged to contact your
               contracting officer for advice and guidance as required on a case-
               by-case basis.
Septentoer 1992                                                          C- 3

-------

-------
  APPENDIXC
  Attachment  1
         "GUIDE FOR USING CONTRACTOR SERVICES"
         U.S. Department of the Navy

         Basically, we do our work in the Department of the Navy two ways: "in-
         house" with military and civilian personnel, or "out-of-house" by contract.
         Which way it is done is a decision based on policy, practicality, and law.
         Generally speaking, it has been Government policy for a number of years
         to perform commercial or industrial activities by contract unless some
         compelling reason-such as military readiness, security, or economy-
         warrants bringing the job "in-house." Which route to follow is the subject
         of other Office of Management and Budget, Department of Defense, and
         Department of the Navy instructions, and is notatissue here. Our concern
         here is only that, if a decision is made to let a contract involving services,
         we make it properly, and use the services properly.

         The fundamentals are these. It is perfectly proper for the Government to
         purchase by contract what may be  described as a finished product-a
         piece of hardware, a defined piece of research, or a report. Unless
         Congress has passed a  specific statute to authorize something different,
         the Government may not contract out for the services of people who
         receive their assignments from Government personnel, work under the
         direct supervision of Government personnel, and whose relationship to
         the Government is thus no different from that of aGovernmentemployee.
         Where die Government wishes to procure services in this fashion, it must
         hire the people directly, in accordance with the Civil Service Laws.

         A finished product versus personal services-these form the two ends of
         the spectrum.  The one may be procured by contract; die other may not
         In between are situations where the  Government does not want to hire
         people, yet the work  it  needs to have  performed is essentially just
         labor-cleaning, painting, or operating a radar station. In these situations,
         the Government may still obtain the work by contract, providing two
         conditionsaremet:  (1) the contractmustaskfor the finished product only,
         and (2) the contract must be administered in such a way mat control and
         supervision over the work and discretion of the techniques which will be

Septerrter 1992                                                    cTs

-------
 used remain solely with the contractor. Inotherwords,if the Government
 wants a building painted, it defines the job, lets the contractor paint the
 building as he sees fit and then accepts it or rejects it solely on the basis
 of whether die completed job meets the specifications. This would be a
 perfectly legal contract for a finished product. On the other hand, if the
 contractual arrangement with the painting contractor is such that he is
 really only providing us with painters whom we direct and supervise as
 we would our own military or civilian employees, then the contract
 would be for personal services and would be illegal.  In  that case, the
 Government would, in effect be "hiring" employees without regard to
 the Civil Service System. That it may not do, and that is the reason all
 service contracts must provide for a dearly defined task or job.

 The Problem:

 A contract may thus cross over into the forbidden area either because of
 the way it is written or because of the way it is administered. The former
 would not occur very often.  ASPR, Armed Services  Procurement
 Regulations,  provides adequate guidance and procedures which, if
 faithfully pursued, will insure that every contract for services is in fact
 legal on its face. But even the best-written contracts can later be ruled
 illegal if they are not administered properly. Good, intelligent contract
 administration is really the key to avoiding personal services problems.

 In essence, a forbidden personal service  contract results when the
 Government assumes  the  right to  instruct supervise,  or control a
 contractor's employee in how he performs his work. It is one thing, for
 example, to sit down in a restaurant order a steak  medium rare, and
 accept it or reject it when it arrives. It is quite another to insure that it is
 cooked to satisfaction by going out to the kitchen, looking over the chefs
shoulder, and telling him how to adjust the flame, when to turn the steak
over, and how to season it When the Government exercises this sort of
 direct supervision and control over contract personnel, it is using them as
 if they were its own civil service or military personnel Control such as
 this-however well-intentioned-renders the services personal and the
 contract illegal.

How, then, can personal services problems be avoided? The answer must
begin early with contract planning, because these problems are far easier
 to prevent man to cure.

 Pre-Contract Planning:

In planning the contract, the contracting officer must receive a great deal
of willing ccoperationfromall hands-technical personnel, legal personnel,
and especially the users—those with the requirement for the proposed
services. Under ASPR, before the contracting officer may enter into a
C-6
September 1992

-------
          service contract, he must make a written determination that the services
          arenonpersonal. To do so, he mustrely almost completely upon the users
          for the facts he needs, because only they can provide them. As the first
          step, therefore, the contracting officer must learn the whole story-all the
          circumstances of what the services are to be and how they will be used.
          In view of his responsibility for making the procurement he deserves-
          and has every right to receive-the users' fullest assistance and candor.

          Second, the users must provide the contracting officer with a detailed
          description of the job they want done. Since the contract must be couched
          in terms of providing the Government with some sort of finished product
          this is the information that will be nejeded to draft proper specifications,
          task orders, or work assignments. Although it is the job of the contracting
          personnel to reduce this information to contract format, it is the job of the
          users to explain precisely what work they want performed

          Third, mere must be a review of all the collateral circumstances which
          might have a bearing upon whether an illegal personal services contract
          has been created.  Although the key factor is the degree to which the
          Government exercises control and supervision over the performance of
          the contract, the Civil Service Commission's opinion, as well as rulings of
          the Comptroller General, also look to related circumstances which, by
          their very nature,  go hand  in hand with the exercise of Government.
          control over contract performance,  ,.-"'  '

          An example might be a contract under which the contractor is provided
          with articles of Government property.  While it is not unusual for the
          Government to furnish equipment or material for use in performing its
          contracts, what is furnished is usually specialized or otherwise difficult
          for the contractor to provide for himself. If, instead, the Government
          furnishes something ordinary like office equipment, drafting tables, or
          typing paper—the sorts of things any employer ordinarily provides his
          own employees-then, if unexplained, an inference may be drawn mat the
          Government is treating the contractor's employees as its own.

          Similarly, our civilian employees or military personnel generally work
          on-site, whereas a contractor's employees usually do not Thus, providing
          the contractor with office space at a Government location might lend
          weight to an inference that his employees are, in effect Government
          employees. By the same token, the •work should be planned to avoid a mix
          of Government and contractor personnel so that they are not working
         side-by-side under similar conditions and supervision.  It should be
         cautioned, however, that a determination of personal services would still
         be found in cases where these personnel-al though physically separated-
         • were all performing the same work and were otherwise interchangeable.
         The same would be true where succeeding contracts with different firms
September 1992                                                         C-7

-------
                                    . t'lllllttltlttltt - iJtttlll,1,1,1 jft~
 Included provisions for orderly changeover of key personnel, and the
 same contract employees were found doing the same work at the same
 desk year after year; And personal services have even been found, in
 incentive or award fee contracts, where the evaluation of contract
 performance was made, not upon the whole job, but rather upon the
 separate performance of individual contractor employees.

 Factors like these are important because each such piece of circumstantial
 evidence may contribute to a later conclusion that the services concerned
 are personal. All of them pertain to supervision and control; and they are
 weighed according to the  extent of their contributions to actual
 Govemmentcontroloverthe contractor's personnel. Taken together and
 viewed objectively, they may give practical appearance that contract
 employees are being treated as is they were actually Government
 employees.

 In the planning stage, then,  requirements, technical, and contracting
 people should pursue every effort toward eliminating as many such
 factors as they can. None of them alone would necessarily be fatal to the
 contracfslegality,andsomeofuemirughtmdeedbeabsolutelynecessary
 and, therefore, inevitable. It is important to realize, however, that these
 ancillary factors can be critical to the result and  that they can be
 effectivelyprovidedforonlyinadvance.IftheyarecarefuUyconsidered
 during the planning stage, and if mere are good reasons for providing
 me contractor with tools, or working space, or doing anything else which
 might imply Government supervision or control,  then the contract can
 provide for them, and later be administered, in a manner which will be
 proper and will not be susceptible to drawing an inference of personal
 services later on.

The Contract:

The sort of planning described above should provide the contracting
officer and his staff with all they need to know about the actual
requirements,in order toreduce mem to dearly defined work statements.
They must, then, in. dear, understandable language, set forth exactly
what the Government wants to have done.  They must provide in the
contract all the specifications or instruction the contractor needs, both to
undertake and to complete the job. This will insure that the Government
has the right to expect an acceptable end product without the need for
control over the way the contractor goes about his work.

It is not enough, however, to write something like "furnish such assistance
as is or may be necessary to support the overall mission of the activity/'
or "update and revise 40 drawings in accordance with the oral instructions
of me division supervisor or his duly authorized representative." The
contract, or the task orders or work assignments written under it, should

C-8                                                         September 1992

-------
          adequately describe the job to be done so thatfurther informal direction
          is unnecessary.  This, of course, does not mean that they cannot be
          formally modified or amended, if needed.

          Furthermore, the contract must avoid creating in the Government a
          specific or even an implicit power to hire or fire  the contractor's
          employees. It is always permissible to retain the authority to require
          security clearances or other legitimate and relevant administrative
          controls, but it must not go beyond that The contractor, for example,
          may be required to accommodate himself and his working hours to our
          daily business routine if he is working on-base, whereas it would be
          improper to impose such a schedule upon work he performed on his
          own premises. And it goes without saying that the contract must not
          provide for Government supervision or control over the contractor's
          staff.

          Nor will theindmionof artifidalprcxcduresforcontractadministration
          remove the Government from a situation of supervision and control if
          one actually exists. It is no use, for example, to provide art elaborate
          organization in the contract for the transmission of work assignments
          on a supervisory level  if, in practice, it is to be phoned from a
          Government draftsman to his contractor counterpart And even where
          such conduits have actually been used in contract administration, they
          have been viewed as mere camouflage where the alleged supervisors
          or technical directors were so untrained or unskilled as to be incapable
          of direction and were, at best, only figureheads. It may be helpful for
          the contract to make it clear that the contractor is providingmanagement
          or judgment as well as personnel, but only if that is truly the case. To
          repeat what was said earlier, writing a legal contract is not the end of
          the road. The heart of most personal services cases has been contract
          administration—what actually happened-not withstanding the niceties
          of the written contract terms.

          Contract Administration:

          What, then, are the pitfalls of contract administration? Essentially, the
          Government must keep "hands off' the contractor's employees during
          the course of contract operations, in order to avoid sliding into the area
          of supervision and control. Does that mean that, after the contract is
          signed, there can be no further contact with the contractor or his staff?
          The answer to that is obviously *T4o." In the course of almost any
          contract performance, there must be some dialogue between both sides.
          Complete  insulation  from one another is  as  unnecessary  as  it is
         undesirable.

         The  permissible  range  of  dialogue between the  Government's
         representatives and the contractor's representatives is whatever liaison

Sapterrter 1992                                                        C

-------
                                                              mzz
 and discussion or explanation is necessary to carry out the traditional
 processes of contract administration.  We have inspectors and quality
 control personnel, for example, and their work cannot be done in a
 vacuum. Itusuallyrequires contract and communication to be useful, and
 this is entirely proper.  And we usually assign personnel in a liaison
 capacity, not only for surveillance and to keep us apprised of progress, but
 also fora contact through whom the contractor can relay his questions or
 problems. It is a rare contract that does not involve answering questions
 about the Government's specifications, and this, too, is a legitimate liaison
 function.

 In addition, the Government is generally concerned about the contractor's
 delivery scheduie-whether he will have the work performed on time.
 Accordingly, the contract milestones are important, and insuring that
 they are met may demand prodding and reminding of many shapes and
 forms, lake the liaison and inspection mentioned above, mis can be done
 properly as well, because it does not involve the exercise of supervision
 or control over the individual employees. In all proper administration
 functions, Government representatives do not dictate what or how the
 contractor is to perform. The "what"  is set out in the contractor's
 responsibility.  In their contract administration roles, our personnel
 should primarily be policing die written terms of the contract and
 assisting the contractor when necessary to insure that the Government
 receives the job it bargained for on time. Contractadministrationbegins
 to run afoul when our representatives go beyond the terms of the contract
 By telling the contractorwhat to do,they maybe subjecting the Government
 to claims for changes. That is another matter. But by directing how to do
 it, they are crossing the line into a personal services situation. Then they
 are beginning to  exercise supervision or control.  When the inspector,
liaison officer, or any other Government representative  turns from
surveillance to supervision, he begins to use the contractor's employees
as if they were Government employees, and is well on the way to
transfonning the contract into one for personal services. Often, mis arises
from no more man a well-intentioned but overzealous desire upon the
part of lesponsiblaGovernment of ficials to achieve near perfection in the
services obtained^^ock.overzealousness must be restrained.

After aE, it is the contractor's privilege to do the job however he sees fit,
so longas he stays within the terms and conditions of the contract Unless
 the contract legitimately provides  otherwise, it is not our business
whether he  does the work with one computer or 200 men, which
employees work on which assignments, or whether they work nights or
mornings, or whether they do task A before task B, or vice versa. It is the
contractor's right to hire and fire, to assign and organize the work-in
short, to run his own company. The moment the Governmentusurps mat
right and begins to tell his personnel what to do next or how to do it, then

 C* 10                                                       September 1992

-------
                                                            -. t'ttnti 111 tmii^. f
          it has started down the slippery slope towarda personal services situation.
          This illustrates the rule for illegality, but it also must be understood that
          the greater the technical direction to the contractor, the greater  title
          responsibility for successful performance is assumed by the Government
          This situation is  not desirable because it not only compromises  the
          Government's rights to enforcement of the contract's provisions, but it
          also transforms an otherwise proper contract into an illegal one.

          Sometimes it is the actions of the contractor himself which will cause the
          contract to cross over into the forbidden area. By being overzealous in
          attempting to be responsive to the Navy organization with which he is
          working, the contractor may initiate contacts which result in Government
          control or supervision over the work being performed. In other words,
          where thecontractor himself continually asks the Government for direction
          on how to carry out the various tasks required by the contract,  the
          Government may end up, in effect, supervising the performance of the
          work.  This type of situation must be guarded against

          The contractor's employees should always be looking only to their own
          superiors for instructions, and they, in turn, must look back to the written
          terms of the contract. This chain of responsibility must exist throughout
          the performance of every contract, and it reemphasizes the need discussed
          earlier for giving meticulous attention to the contract work statements,
          task orders, or work assignments at the outset. And it further underlines
          the need  for assuring that the  contract preparation is a genuinely
          coordinated effort by everyone  involved-the users, technical staffs,
          contracting staffs, and lawyers-so that, with the input from them, all the
          work to be performed is so dearly and accurately spelled out there will
          be neither need nor temptation to slide into the easy trap of supervising
          any stage of the job.

          Statutory Exception:

          As was mentioned at the beginning, these rules of contracting must be
          followed in every service contract unless there is specific authority from
          Congress to proceed otherwise. There may be situations—and they do
          arise from time to time—when it is desirable for the Government to have
          precisely thatsort of supervision and control which is generally improper,
         'and where the shortdurationof the work dicta tes against hiring employees
          under Civil Service.
September 1992                                                        C-If

-------

-------
   Appendix D

Contracting at EPA
EPA Order 1900.2

-------

-------
 Appendix D
 Contracting at  EPA
 (EPA Order 1900.2)
         1.  Purpose

         This Order establishes Agency policy that (1) prohibits contracting for
         certain activities at EPA and (2) implements special management and
         control measures when contracting for certain sensitive services.


         2.  Background

         EPA relies heavily on contractor support Nearly every EPA employee is
         involved with the contracting community in one way or another. Thus,
         in a very real sense, most EPA employees, including senior management,
         can be considered contract managers.

         Agency responsibility and accountability begin when a decision is made
         to use contract support And, having accepted a final product from a
         contractor, EPA becomes responsible for its content and for how it may
         be used in reaching Agency decisions.

         The extent of the Agency's  contracting, coupled with its  regulatory
         nature, create a strong potential for conflict of interest with members of
         the contracting community. This problem is magnified when a limited
         number of contractors provide support in a variety of potentially sensitive
         areas.  EPA must consider these facts when developing its contract
         requirements. It must be judicious in deciding the most effective ways to
         use its contractors and lookfor ways of reducing the potential for conflicts
         of interest.  And, if contract support has been used, EPA must play a
         proactive role in ensuring a final Agency product that is unbiased and
         represents Agency thinking. The final product provided under a contract
         may assist EPA in reaching a decision; however, a contractor should not
         make the decision for the Agency.

         OMB Circular A-76 defines inherently governmental activities as those
         "being so intimately related to  the public interest  as to mandate
         performance only by Federal employees."   Agency employees must
         ensure that inherently governmental activities  are performed only by
         EPA employees.
September 1992                                                     0- >

-------
            ,1'iintiiftttnti •_-'.
 NOTE:  For purposes of this Order, "active contract managers" are
 denned as POs, Deputy ProjectO£ficers,WAMs,Reinedial Project Officers,
 On-Scene Coordinators, Delivery Order Officers, and Delivery Order
 Project Officers.  "EPA managers" consist of senior management not
 directly involved in contract management

 3. Policy

    a.  EPA will not allow any of the following to be performed under its
       contracts:

       (1) The actual preparation of Congressional testimony.

          Although it is  permissible for a contractor to perform basic
          research and retrieve factual data for the Agency in its
          development of Congressional testimony, it is the ultimate
          responsibility of EPA to develop and issue it The Agency
          spokesperson must present testimony that is free from any
          contractor bias and any real or potential conflicts of interest
          Therefore, even if prelimi-nary research is performed by a
          contractor, itmust be carefully examined by Agency personnel
          for any contractor partiality, favoritism, and conflicts of interest,
          prior to its incorporationinto the testimony. The final document
          must be prepared by Agency personnel to ensure that it fully
          represents the briefing materials to congressional staffers.
          Finally, if workis issued to a contractor for testimony support,
          it is important that the statement of work for the assignment
          reflect that these Agency limitations have been established.

      (2) The interviewing or hiring of individuals for employment at
          EPA.

          Both of these activities are inherently governmental duties
          involving judgment and discretion and a legal commitment
          on the part of the Government They must remain under the
          sole authority of EPA.

      (3) Developing and/or writing  of  Position Descriptions and
          Performance Standards.

          These activities are key to the effective staffing and operation
          of EPA and are supervisory/management responsibilities.
          Outside technical expertise specific to a certain profession

D-2                                                        September 1992

-------
                   may sometimes be necessary but contractors should not write
                   our position descriptions. Similarly, contractors should not be
                   used to determine how the performance of EPA employees
                   should be evaluated.

               (4) The actual determination of Agency policy.

                   This prohibitiondoes not preclude contractors from providing
                   support in the policy development process. However, it does
                   preclude contractors from participating in the final phases of
                   policy development, Le., being involved in the actual decision-
                   making  of what Agency policy will be. Contractors may
                   appropriately be used in the stages of policy development
                   which involve doing background research or  performing
                   options analyses. If such support is provided by a contractor,
                   it must  be carefully examined by Agency personnel for
                   partiality, favoritism, and any contractor conflict of interest In
                   all cases, there should be a clear record that the contractor's
                   work was reviewed and mat final decisions were made by
                   Agency  personnel. Such a record could be demonstrated
                   through notes from reviews of draft and final documents by
                   EPA personnel,  minutes .from progress meetings with
                   contractors, reports from EPA peer and board reviews, etc.(5)
                   Participating as a voting member on a Performance Evaluation
                   Board; participating in and/or attending Award Fee meetings.

                   The assignment of an evaluation  score and the making of
                   recommendations of profit/fee payments by one contractor
                   for another are clearly conflicts of interest  All functions
                   relating to the decisions of  award fees are inherently
                   governmental and should be performed exclusively by Agency
                   staff. However, contractors may provide specialized technical
                   expertise as input to the Board prior to the actual evaluation
                   meeting discussions. The key determining factor is the nature
                   ofthesupport;inallcases/itshouldbecontractor'sperformance.
                   For confidentiality reasons, no contractor may be present
                   during the Board meeting.  Any opinions expressed as the
                   result of a Performance Evaluation Board should be those of
                   the Government   Additionally, due to the subjective and
                   confidential nature of the Board reports, their typing should
                   remain an in-house function.

               (6)  Preparing Award  Fee Letters, even under typing services
                   contracts.
Septerrtoer 1992                                                        D- 3

-------
\'»'tttittitti'ttrit-.t-fifttttt'f'if'•*• ".-
                        i'S'ttttffftftttff.
           Because Award Fee Letters contain significantly sensitive and
           confidential information thatcould possibly ha veadetrimental
           effect on a firm's reputation, it is inappropriate to allow
           outside entities, even those contractors performing typing
           services, access to such information.

       (7)  The actual preparation of Award Fee Plans.

           This is an inherently governmental function that details the
           discretionary and judgmental decisions behind the process
           the Government will be using in its evaluation of a contractor's
           performance. It would be inappropriate for any contractor to
           advise the Agency on whatshouldbe important to it Provided
           that all confidential business information has been removed,
           a contractor may type award fee  plans since  there is  no
          judgment associated with the performance of that task.

       (8) The preparation of documents on EPA letterhead other than
          routine administrative correspondence.

          In this instance, "routine" is synonymous with "non-
          judgmental" or "non-decisional." This prohibition is designed
          to prevent the foUowingsituationfrom occurring. A contractor
          is asked by EPA to perform certain policy analysis tasks. The
          contractor then performs the research and develops a position
          on the policy which it prepares on EPA letterhead. EPA then
          signs it, thereby making it EPA policy. Even though EPA may
          have made the final decision, there is no indication of EPA
          involvement up until that time. The development of inherently
          governmental decision  documents mandates significant
          Agency involvement and mis restriction ensures the Agency's
          participation in the decision process. Records should be kept
          demonstrating EPA's involvement. This prohibition does not
          apply to contracts which are providing typing services,  on
          condition that the contractor providing such typing services
          was not involved in any other capacity in the development of
          the decisional or judgmental document

      (9) Reviewing vouchers and invoices  for the purposes  of
          determining whether costs, hours, and work performed are
          reasonable.

          This prohibition is directed specifically at the PCXs monthly
          review and approval of a contractor's invoice submitted to
          EPA for payment purposes.  Contractors may perform non-
0-4
September 1992

-------
                   judgmental duties,suchascheddLngmamematicsorreviewihg
                   invoices for administrative accuracy, but should not render
                   opinions in lieu of EPA on the reasonableness of professional
                   staffing levels and hours used to perform work. That is an
                   inherently governmental function generally delegated by the
                   Contracting Officer to the PO. This item in no way prohibits
                   the Office of Inspector General from contracting for financial
                   auditing and services, and compliance auditing.

                (10) The preparation of Statements of Work, Work Assignments,
                   Technical Direction Documents, Delivery Orders, or any other
                   work issuance document under a contract that the contractor
                   is performing or may perform.

                   Authorizing a contractor to do any of these activities creates a
                   dear conflict of interest situation since they essentially allow
                   the contractor to assign itself its own work.  Similarly, it is
                   inappropriate for contractors to complete their work issuance
                   forms.  This prohibition does not restrict contractors from
                   preparing work plans which are, in fact, their own
                   responsibility. Additionally; EPA prime contractors should
                   be responsible for preparing the statements of work for their
                   own subcontracts.       >'

                (11) On behalf of EPA, actually preparing responses to audit
                   reports from theInspectorGeneral,General Accounting Office,
                   or other auditing entities

                   and

                (12) On behalf of EPA, preparing responses to Congressional
                   correspondence.

                   Both of these items are analogous to the situation discussed
                   under Item (1), above. Althoughitis permissible for contractors
                   to perform in a research or fact-finding capacity, the final
                   document should be produced by EPA personnel to ensure
                   that it is free from outside bias and that it truly represents
                   Agency thinking.

                (13) The actual preparation of responses to Freedom of Informa don
                   Act  requests, other  than  routine, non-judgmental
                   correspondence—in all cases, EPA must sign it

                   The key work here is "non-judgmental," being synonymous
                   with "non-decisional." We do not want contractors to decide

Septerrtoer 1992                                                         D 5

-------
          what is releasable under FOIA since that is an inherently
          governmentalfunctioninvolvingtheinterpretationofstatutes
          and Agency regulations.  Recognizing that some FOIA work
          is non-judgmental or non-detisional, it is permissible for
          contractors to be used in those areas. For example/ provided
          all conflict of interest, confidential business information (CBI),
          and Privacy Act regulations have been followed, contractors
          may be used to collect data for the Agency as long as they are
          not deciding what data is releasable. Similarly, if conflict of
          interest, CBI, and Privacy Act regulations have been addressed,
          contractors may be used to redact documents provided that
          decisions on what to redact are made exclusively by Agency
          personnel  Questions concerning interpretation of  CBI and
          Privacy Act regulations should be referred to the Office of
          General Counsel. Questions concerning conflicts of interest
          should be  referred to the Procurement and Contracts
          Management Division.

      (14) Any contract which authorizes a contractor to represent itself
          as EPA to outside parties.

          No con tract may contain such an authorization. There may be
          times when contractors are assumed to be EPA personnel, but,
          in those situations, firms must explain that they are Agency
          contractors.

      (15) Conducting administrative hearings.

          Administrative hearings are  primarily conducted by
          Administrative Law Judges (ALJs) who,in accordance with 40
          CFR, Part 22, hear cases involving disputes between EPA and
          other parties regarding regulations, permitting, etc The ALJs
          are EPA employees performing quasijudicial and therefore,
          inherendygovemmentalfunctionssuchasassessingpenalties.
          This  is distinguishable from contracting for professional
          arbiters when the Agency requires outside, independent
          judgment

      (16) Reviewing findings concerning the eligibility  of EPA
          employees for security clearances.

          This has been included as a prohibition because it is inherently
          governmental and may also involve the disclosure of very
          sensitive and personal information regarding EPAemployees.
D-6
September 1992

-------
                (17) The actual preparation of an office's official budget request

                   The prohibition here is very similar to Items (1), (11), and (12).
                   Whereas research and fact-finding of a purely technical nature
                   are permissible assignments under a contract as preliminary
                   steps to  budget development, the responsibilities of
                   establishing Agency priorities or determining how Agency
                   money should be spent may not be delegated to Agency
                   Contractors. These  are inherently  governmental duties
                   involving judgment and discretion and must be performed by
                   Agency staff. Prior to its use, any support work provided by
                   a contractor must be very carefully reviewed by EPA staff to
                   remove any contractor bias and to substantiate the reliability
                   of the data, analyses, etc

             b.  Certain other  activities when performed under contracts may
                place EPA in a vulnerable or sensitive position if adequate controls
                are not implemented.  In those cases, a justification  must be
                prepared by the requesting program office which describes the
                type of work to be performed under the contract, why the work
                cannot be performed internally, and what will be done to ensure
                a final Agency product that is unbiased and represents Agency
                thinking.

                Ifanewcontractawardvaluedat$25,000or greater is contemplated,
                the justification must  be  signed by the cognizant Assistant
                Administrator, Associate Administrator, or Regional
                Administrator. For new contracts valued at less than $25,000; the
                justification must be signed by a program official  at least one
                organizational level above the initiating office but no lower than
                the Branch level, e.g., a document generated at the Section level or
                lower mustbe approved at the Branch level, a document genera ted
                at the Branch level must be approved at the Division level, etc.

               The followingare contract workareas necessitating this justification:

                (1)  Budget preparation support including, but not limited to,
                   workload  modeling,  fact-finding, efficiency studies, and
                   should-cost analyses,

                (2)  Reorganization and planning support

               (3)  Supportservices such as analyses, feasibility studies, etc., to be
                   used by EPA personnel in developing policy,
September 1992                                                         D-7

-------
       (4) Regulation development support,

       (5) Any supportin the in-house evaluation of another contractor's
          performance,

       (6) Involvement in strategic acquisition planning,

       (7) Support on improving contract management

       (8) Providing specialized expertise in the contractor selection
          process/

       (9) Providing specialized  expertise in the development of
          Statements of Work, Work Assignments, and other contract-
          ordered tasks,

       (10) AnysupportinvolvingEPApoUcyorregulatory interpretation,
          such as staffing hotlines, attending conferences on behalf of
          EPA, community relations efforts, conducting EPA training
          courses, etc, and

      (11) Independently providing technical guidance concerning EPA
          policies or regulations on EPA's behalf to outside parties.
                                                     _^ ;
          NOTE: Innoeventshallanycontractrequiring the performance
          of any legal services be entered into without the approval of
          the Office of General Counsel.

      Certain other activities if contracted for, although not sufficiently
      sensitive to require justifications, do necessitate the establishment
      of special EPA control measures.  If a new procurement is
      contemplated involving any of the activities or situations listed
      below, a special discussion detailing control procedures to be
      enforced must be included  within the pre-award procurement
      request  rationale document  This would be required in the
      following instances:

      (1) Situationswherecontractorsshareofficespacewithemployees.

          Control measures must be  established to prevent the
          performance of personal services, to ensure mat contractors
          do not have inappropriate access to privileged or sensitive
          information, etc.

      (2) Support in preparing responses to Freedom of Information
          Act requests.
D-8
September 1992

-------
                    Control measures mustbe established to ensure thatcontractors
                    are in compliance with all regulations involving FOIA, the
                    Privacy Act, and confidential business information.

                (3)  Any situation where a contractor has access to confidential
                    business information and/or any other sensitive information.

                    Controlmeasures mustbe established to ensure thatcontractors
                    do not have inappropriate access to privileged and sensitive
                    information, to  ensure that security systems are in place
                    preventing the  release of sensitive information to non-
                    designated contractor employees, etc

                (4)  Any situation where it can be assumed that the contractor is
                    EPA, without specifically identifying itself as a contractor.

                    Controlmeasures mustbe established to ensure thatcontractor
                    employees are dearly identified through the use of badges,
                    posted signs, etc.

             d.  In determining how best to contract for these sensitive services,
                organizations must  consider ways to reduce the potential for
                conflict of interest. Procurement strategies should be considered
                that break the requirements into smaller components, thereby
                broadening contractor resources available to a particular office. If
                possible, small and  minority business participation should be
                considered, provided these firms do not have conflicts of interest.
                The procurement request rationale document must address;how
                the particular procurement request fits into the requesting office's
                overall procurement strategy.  •

             e.  In order to assure contract accountability at all  levels of the
                Agency, all EPAmanagersmusthave written into their performance
                standards language  emphasizing strong contract  management
                and controls.

             f.  Contract management training classes will be revised to include
                discussions of the  essential elements  of this  EPA Order.
                Additionally, all active contract managers will be required to take
                a one-day refresher course in contract management every three
                years in order to maintain certification.
September 1992                                                         D- 9

-------
4.  Responsibilities
      Hie Procurement and Contracts Management Division (PCMD) is
      responsible for the following:

      (1) Including language within all future contracts to prohibit
          contractor performance of the activities listed in Paragraph
          3.a., above.

      (2) Notifying all current contract holders of those prohibitions
          listed in Paragraph 3.a., above.                ;

      (3) Revising  the  Contracts Management Manual (CMM)  to
          incorporate the provisions of this  Order, specifically
          highlighting:
          (a)  The prohibited activities listed in Paragraph 3a., above.
          (b)  The requirement for justifications for the purchase of any
              of the services listed in Paragraph 3.b., above,
          (c)  The requirement for a control element discussion in the
              procurement request rationale document if any of the
              activities listedinParagraphS.c., above, are contemplated,
          (d)  The requirement for a procurement strategy discussion
              element in the procurement request rationale document,
              and
          (e)  The requirement  to  include in all  EPA managers'
              performance standards  language  emphasizing  strong
              contract management and control            .

      (4)  Reviewing die justifications for the purchases of any of the
          services listed in  Paragraph 3.b., above, and making a
          determination that adequate control measures will be
          employed.
      (5)  Re vising Recurrent contract management training classes to
          include discussions of this order.

      (6)  Institutingaone-daycontractmanagementrefreshercourseto
          be taken every three years by active contract managers in
          order to maintain their  certification.
   b.  EPA offices employing contract support are responsible for
      following:
£M0
September 1992

-------
               (1)  Preparing the justification for the purchase of any of the
                   services listed in Paragraph 3.b., above, and obtaining the
                   signature of the appropriate approving official  on the
                   justification.

               (2)  Including a control elementdiscussion within the procurement
                  - rationale document if any of the activities listed in Paragraph
                   3.c, above, are contemplated.

               (3)  Considering ways  to break up requirements for the
                   procurement of sensitive services into smaller components,
                   thereby reducing the potential for conflicts of interest.

               (4)  Along with the performance standard requirements for active
                   contract managers discussed within the CMM, including in all
                   other EPA managers' performance standards language, as
                   included within the CMM,  emphasizing strong contract
                   management and control

               (5)  maccordancewimguidanceestablishedmmeCMKrequiring
                   active contract managers to attend the contract management
                   refresher course once every three years, in order to maintain
                   their certified status.

            c  All Agency employees are responsible for the following:

               (1)  Being aware of the content of this Order and bringing any
                   suspected violations  to the attention of the cognizant
                   Contracting Officer.            .                   ;-\

               (2)  Ensuring that the "prohibited" activities listed in Paragraph
                   3.a. and the "sensitive" activities listed in Paragraphs 3-b. and
                   3.c. are handled in accordance with the guidance outlined in
                   this Order and the CMM.
September 1992

-------

-------
               Appendix E

      Work Assignment Manager Model
          Performance Standards
SqptamterfSB?

-------

-------
Work Assignment manager
model performance Standards


Critical Job Element:
                                            i
Develops and manages work assignments to ensure effective
compliance with overall contract and completion of the contracted
activities or tasks effectively, in a timely manner, and at the
most cost-effective price.

OMeetive il

To initiate  work assignments by preparing a statement of work
(SOW) and, if necessary, work assignment (wa) amendments that
clearly define essential task components and deliverables and are
within the scope of .the overall contract SOW.

Outstanding

  Consistently prepares sows and WA amendments that are timely,
  carefully  planned, and clearly define the project's objectives,
  task schedules, milestones for each task, deliverables to be
  produced,  and dates of deliverables.  SOWs rarely need
  revision.  Sufficient technical information is provided to
  enable the contractor to respond with a cost-effective work
  plan.  Quantity and quality of work indicate excellent
  attention  to detail and creative problem-solving.  Actively and
  consistently processes WA documents in a timely way so that
  project activities proceed smoothly.

fully Successful

  With some  direction, prepares SOWs and WA amendments that
  demonstrate efficient planning and that are well defined  in
  terms of the project's objectives, task schedules, milestones
  for each task, deliverables to be produced, and dates for
  deliverables.  Generally provides WA documents so that project
  activities can proceed within a reasonable schedule.

Unsatisfactory

  Even with some direction,  WAN prepares SOWs and WA amendments
  that are poorly defined and inefficiently planned in that they
  may not include major tasks and milestones,  period of
  performance,  or deliverables.   Shows little initiative to
  ensure that project activities proceed smoothly; PO must
  request necessary WA documents.

-------
                               -2-

Oblective 12

To manage and monitor technical performance of assigned WAS.

Outstanding

  Carefully examines work plan on receipt to ensure that it
  reflects technical scope, schedule, and budget estimates.
  regularly with contractors, PO, and supervisor to discuss WA
  progress and provides creative and useful solutions to
  problems.  Consistently reviews incurred costs of assigned
  tasks for reasonableness and provides routine feedback to PO or
  supervisor concerning problems that are identified.
  Established routine procedures to ensure that informal
  agreements with contractors are well-documented and that
  contractors' work rarely proceeds under a misunderstanding
  following a meeting.  Reliably maintains precise management
  records to assess information on the status of work; reviews
  and evaluates deliverables and accepts or rejects them promptly
  with well-documented, action-oriented comments; and submits a
  final report to the PO promptly on completion of the project
  that includes a summary of work completed and ensures the
  timely processing of all documentation necessary for con-
  tractors* performance evaluation processing and for WA
  closeout.

Fully successful

  Reviews work plan to ensure that it reflects technical scope,
  schedule, and budget estimates.  Meets periodically with
  contractors, PO, and supervisor to discuss WA progress, and
  solves problems with some assistance from the PO or supervisor.
  Maintains, with minor revisions, management records to assess
  information on the status of work; reviews and evaluates
  deliverables and accepts or rejects them with documented
  comments; and submits a final report to the PO within a
  reasonable time following project completion that includes
  a summary of work completed and ensures the timely processing
  of all documentation necessary for contractors* performance
  •valuation processing and WA eloseout.

unsatisfactory

  Work plans are not timely reviewed, and WAM relies on
  Supervisor or PO to solve problems and ensure that proper
  contracting procedures are complied with.  Meets infrequently
  with contractors, PO, and supervisor and discusses, but often
  does not solve, problems.  Maintains unreliable or inaccessible
  management records to assess information on the status of work;
  inadequately reviews and evaluates deliverables and accepts or
  rejects them with vague and poorly documented comments; and

-------
                                -3-

  submits final report to the PO after substantial delay
  following projsot completion that may not include an accurate
  summary of work completed, thus delaying contractors1
  performance evaluation processing and WA oloseout.

Obiactive §3

To manage and monitor budget and schedule performance on assigned
WAS.

outstanding

   consistently manages WAs efficiently and within budgetary and
   time constraints.  Establishes and maintains precise, timely,
   and appropriate project management records that document
   status of budget and schedule.  Consistently analyses
   financial reports and anticipates problems that may affect
   schedules or deliverables; initiates proper actions to control
   budget and avert budget overruns and to meet changing project
   conditions; and obtains timely clearance for subcontractors
   and consultants.  Regularly communicates with contractors to
   ensure that budget and schedules are being met.  Consistently
   and promptly reviews and evaluates deliverables, and accepts
   or rejects them promptly with well-documented, action-oriented
   comments,  submit final report, including budget and schedule
   summary, to PO promptly at project completion.

Fully Successful

   With some direction, manages WAs within budgetary and time
   constraints.  Maintains, with minor revisions, project        :
   management records that document status of budget and
   schedules,  when requested by the PO, may identify financial
   and other problems that may affect schedules or deliverables;
   with some assistance, takes action control budget, to amend WA
   in sufficient time to avert more than 10 percent overrun, and
   to meet changing project conditions.  Obtain clearance for
   subcontractors and consultants.  Periodically communicates
   with contractors to ensure that budget and schedules are being
   met.  Reviews and evaluates deliverables, and accepts or
   rejects them with documented comments.  Submits final report,
   including a budget and schedule summary, to PO at project
   completion.

unsatisfactory

   Even with some direction, manages WAs with frequent
   adjustments to budget and schedules.  Maintains unreliable or
   inaccessible project management records concerning status of
   budget and schedules.   Often fails to identify financial and
   other problems that may affect schedules or deliverables.
   Often takes inadequate action to modify WA or control budget


-------
                              -4-
and meet changing project conditions.  Often fails to identify
financial and other problems that may affect schedules or
deliverable*.  Often takes inadequate action to modify WA or
control budget and Beet changing project conditions.  Often
fails to obtain clearance for subcontractors and consultants.
Meets infrequently vith contractors, Baking it difficult to
ensure that budget and schedules are being Bet.  Provides late
and vague comments on deliverables.  submits final report to
PO after substantial delay following project completion;
report often does not include accurate budget and schedule
summaries.

-------
APPENDIX F
Definition of Labor
Classification

Listed below are qualifications for each category of professional
services the contractor must provide.

(a) Level XV;  Senior Professional (Management):

   At least eight years of professional experience planning,
   conducting, and participating in short-term studies; the
   design, review and evaluation of management and administrative
   systems; and the provision of management support.  At least
   some of the experience must include scheduling work to meet
   completion dates, estimating manpower needs,  reviewing project
   progress and making changes in methodology where necessary.
   This individual plans, conducts, and supervises projects of
   major significance, necessitating advanced knowledge and the
   ability to originate and apply new and unique methods and
   procedures.  This person supplies technical advice and counsel
   to other professionals and generally operates with wide
   latitude for unreviewed action.  In addition,  must have at
   least a master's degree in business administration,
   management, public administration, or related discipline
   unless the Experience Qualification Substitutions clause is
   satisfied.

(b) Level III:  Mid Professional (Senior Analyst):

   At least three years' professional experience participating in
   short-term studies; the design, review and evaluation of
   management and administrative system; and the provision of
   information management policy support.  Individuals receives
   assignments associated with projects from the senior
   professional translating technical guidance received into
   usable data applicable to the particular assignment.  Work
   assignments are varied and require some originality and
   ingenuity.  In addition,  must have at least a master's degree
   in the social sciences,  management,  business administration,
   public administration, or related discipline unless the
   Experience/Qualification Substitutions clause is satisfied.

(o) Level IX:  Junior Professional (Analyst)

   Less than three years of experience in the areas listed above
   under "Mid Professional  (Senior Analyst)."  Individual gathers
   and correlates basic data and performs routine analyses.
   Person works on less complicated assignments where little
   evaluations required.   In addition,  most have  at least a
   bachelor's degree in the social sciences,  management or
   business,  unless the Experience/Qualifications Substitutions
   clause is  satisfied.

-------

                                — 2 -



 (a) Any combination of additional years of experience in the
    proposed field of expertise plus full tine college level
    study in the particular field totaling four  (4) years will be
    acceptable substitute for a bachelor's degree.

 (b) A bachelor's degree plus any combination of additional years
    of experience and graduate level study in the proposed fields
    of expertise totaling two (2) years will be an acceptable
    substitute for master's degree.

 (c) Additional years of graduate level study in an appropriate
    field will be considered equal to years of experience on a
    two-for-one basis.

Listed below are typical duties, titles and qualifications for
each category of professional service:

PROFESSIONAL

 (1)  Level 4 - Plans, conducts and supervises projects of major
     significance, necessitating advanced knowledge and the
     ability to originate and apply new and unique methods and
     procedures.  Supplies technical advice and counsel to other
     professionals.  Generally operates with wide latitude for
     unreviewed action.

Typical Title:  Project Leader,  Chief Engineer

normal Qualifications:  Ph.D. Degree or equivalent; and

Experience:  10 years or more.

 (2)  Level 3 - Under general supervision of project leader,
     plans, conducts and supervises assignments normally
     involving smaller or less important projects.  Estimates
     and schedules work to meet completion dates.  Directs
     assistance, reviews progress and evaluates results; makes
     changes in methods, design or equipment where necessary.
     Operates with same latitude for unreviewed action or
     decision.

Typical Title:  Engineer, Analyst

Normal Qualifications: B.S. Degree or equivalent; and

Experience:  6-12 years.

-------
                               -3-

(3)  LEVEL 2 - Under supervision of a senior or project leader,
     carries out assignments associated with projects.
     Translates technical guidance received from supervisor into
     usable data applicable to the particular assignment,
     coordinates the activities of juniors or technicians.  Work
     assignments are varied and require some originally and
     ingenuity.

Typical Title:  Engineer, Analyst

Normal Qualifications:  B.S. Degree or equivalent; and

Experiences  3-8 years

(4)  LEVEL 1 - Lowest or entering classification.  Works under
     close supervision of senior or project leader.  Gathers
     and correlates basic data and performs routine analyses.
     Works on less complicated assignments where little
     evaluation is required.

Typical Title:  Junior Associate

Normal Qualifications:  B.S. Degree or equivalent; and

Experience: 0-3 years                     -.


Experience/Qualifications Substitutions:

(1)  Any combination of additional years of experience in the
     proposed field of expertise plus full time college level
     study in the particular field totaling four (4) years will
     be an acceptable substitute for a bachelor's degree.

(2)  A B.S. degree plus any combination of additional years of
     experience and graduate level study in the proposed fields
     of expertise totaling two (2) years will be a acceptable
     substitute for master's degree.

(3)  A B.S.  degree plus any combination of additional years of
     experience and graduate level study in the proposed fields
     of expertise totaling two (4) years or a Master's Degree
     plus two (2)  years of either additional experience or
     graduate level study in the proposed field of expertise will
     be an acceptable substitute for Ph.D.  Degree.

(4)  Additional years of graduate level study in an appropriate
     field will be considered equal to years of experience on a
     two-for-one basis.

-------
                                -4-
 TECHNICAL

 (1)  Level 3 - Performs non-routine  and complex assignments.
     Works under general supervision of a scientist or engineer.
     Performs experiments or tests which may require nonstandard
     procedures and complex instrumentation.  Records, computes
     and analyzes test data, prepares test reports.  May
     supervise lover level technicians.

 Typical Title:  Senior Technician

 Experience:  6 years or more

 (2)  Level 2 - Performs assignments  that are normally
     standardized.  Operates testing or processing equipment of
     moderate complexity.  Hay construct components or
     subassemblies of prototype models.  May troubleshoot
     malfunctioning equipment and make simple repairs.  Extracts
     and processes test data.

Typical Title:  Technician

Experiencet   2-6 years


 (3)  Level 1 - Performs simple and routine 'tasks or tests under
     close supervision.  Records test,data and may prepare simple
     charts or graphs.   Performs routine maintenance and may
     install or set up test equipment.

Typical Title:  Junior Technician, Technician Trainee

Experience:  0-2 years

-------
 /mil

              APPENDIX G
     Negotiations and Communications
September 1992

-------

-------
 APPENDIX  G
 Negotiation and
 Communication
         How to Negotiate with Contractors: Points out where negotiations with
         contractors may be required in the life of a Work Assignment; different
         negotiation techniques; how to distinguish negotiable from non-nego-
         tiable items.

         Effective Communication Is the Key: Being dear about what you want
         and expect; communicating about difficult subjects.

         Ethics for Contractor Management: Summarizes the ethical standards for
         EPA employees who manage contractors andprovides Work Assignment
         Managers with guidance on how to deal with the "gray areas" that
         frequently arise during contractor management
        WHY ARE NEGO-
        TIATION, COMMU-
        NICATION, AND
        ETHICS IMPOR-
        TANT TO GOOD
        MANAGEMENT?

        • Negotiating in
          good faith should
          lead to satisfactory
          agreements.

        • Using noncon-
          frontational tech-
          niques improving
          communications.

        • Good communica-
          tion ensures that
          everyone under-
          stands the Work
          Assignment and
planned approach.

Communication
can foster team
spirit and commit-
ment to the project
and can get a
troubled Work
Assignment back
on track.

Attention to ethics
issues is needed to
ensure that ques-
tions do not arise
about the propriety
of Work Assign-
ment Manager
actions.
 AREA1 How to
 Negotiate with
 Contractors      •:

 A client-contractor
 relationship will
' always have some
 adversarial elements
 to it. Despite efforts
 at effective communi-
 cation and sincere
 attempts on both
 sides to foster a
 positive team spirit,
 there will be those
 times when you and
 the contractor will
 disagree on certain
 aspects of the Work
 Assignment
September 1992

-------
            rvrmiirrmirri
 At these points you
 must negotiate to
 solve these disagree-
 ments. It is possible
 to use negotiation
 techniques to reach
 agreements that will
 satisfy the needs of
 you and your con-
 tractor. This section:

 • Identifies times
   when you  may be
   negotiating with a
   contractor  during
   Work Assignment
   planning and
   implementation;

 * Explains how to
   prepare a negotia-
   tion strategy before
   dealing with the
   contractor; and

 • Provides some
   pointers for con-
   ducting these
   negotiations.

Times When  You
May Be Negotiating
with a Contractor

There are at least
three points in the life
of a Work Assign-
ment when you may
be negotiating with a
contractor

• When the Work
  Plan is initially
  prepared;

• During any mid-
  course correction,
   when it becomes
   apparent that a
   change in the Work
   Assignment's focus
   is needed; and

 • Near Work Assign-
   ment completion/
   when a final prod-
   uct is found to be
   unacceptable.

 There are several
 things that could be
 negotiated during
 Work Plan review,
 including the Work
 Assignment's scope,
 budget, and schedule
 of deliverables. Dur-
 ing these negotia-
 tions/ you will be
 trying to get as much
 work as possible for
 the funds allocated in
 the Work Assign-
 ment/ and the con-
 tractor will be trying
 to make sure that
 there are suf-ficient
 hours in the Plan to
 complete the work.
 These two interests
 do not necessarily
 have to conflict The
 Work Assignment
 manger simply has to
 be creative during the
 negotiations.

 Mid-course correc-
 tions are another
 point in Work As-
 signment implemen-
 tation where you can
become involved in
 negotiations. A shift
 in EPA's program
 policies could result
 in the need to revise
 the focus of the Work
 Assignment. In this
 instance/ negotiations
 would likely center
 around how much of
 the work already
 completed could be
 used for the revised
 Work Assignment
 scope; how much
 additional work will
 have to be under-
 taken; and whether
 this additional work
 can be completed
 given the Work
 Assignment's existing
 budget. By the time a
 Work Assignment is
 half-completed, a
 contractor may be
 very concerned that
 there are not enough
 hours to complete it
 and may be rather
 inflexible about
 revising the scope.

 The final point where
 you may be negotiat-
 ing with a contractor
 is near Work Assign-
 ment completion
 when/ despite exten-
 sive communication
 between you and
 your contractor while
 the work was in
progress, the final
product is unaccept- ;
 able. The contractor..
€-2
                                     September 1992

-------

    may be somewhat
    inflexible about
    revising the docu-
    ment if there are no
    additional funds to
    make the corrections.

    However, this does
    not necessarily mean
    that both of your
   needs cannot be met
   You may be able to
   develop some cre-
   ative solutions to thin
   impasse during
   negotiation sessions
   with the contractor.

   Develop a Negotia-
   tion Strategy
  Before beginning any
  negotiations with a
  contractor, it is help-
  ful if you have a dear
  picture of the issues
  likely to be discussed,
  negotiable and non-
  negotiable items, and
  your "bottom line"
  needs.  Negotiations
  will proceed much
 more smoothly - and
 agreements be
 reached more quickly
 •if you take a little
 time to prepare a
 strategy.

 Five steps are sug-
 gested here for pre-
paring a negotiation
strategy.

1. Identify the Issues
   that you think
       will be raised.

    If your negotiation
    will center around
    provisions in the
    Work Plan, reviewing
    that document should
    provide some indica-
    tion of the issues.
    When reviewing the
    Work Plan, use Ques-
    tion #1 of the Check-
   list to jot down those
   aspects of the plan
   that you believe
   should be changed.
   This, then, gives you
   a preliminary list of
   issues that you can be
   prepared to address.
  If you are negotiating
  for a mid-course
  correction or revi-
  sions to a final prod-
  uct, you will have
  already established a
  working relationship
  with the contractor.
  Based on your famil-
  iarity with the per-
  sonalities at that firm,
  you should be able to
 predict how they may
 respond t proposed
 changes. Here again,
 Question #1 of the
 checklist can help you
 to organize your
 thoughts when trying
 to anticipate potential
 negotiation issues.
2.  Identify your
   "bottom-line"
   needs.
    Successful negotia-
    tions usually require
    that both disputants
    make some conces-
    sions in order to
    reach an agreement
    If you know that-you
    are going to be nego-
    tiating, it is extremely
    helpful to identify
    ahead of time some
    possible negotiable
    items that you could
    discuss. (See Step 4
   below.)  Before iden-
   tifying these items,
   however, it is essen-
   tial that you outline
   your "bottom-line"
   position; that is, the
   minimum you re-
   quire to ensure that
   your needs will be
   met.

  For instance, while
  you may agree to
  extending the sched-
  ule for completing a
  deliverable, your
  bottom-line need
  might be that the
  product must be
  completed in time to
 present it at an up-
 coming conference.
 Question #2 on the
 checklist asks you to
 identify your bottom-
 line needs.

 3.  Identify the non-
    negotiable items.

There are several
potentially non-
                                                           6-3

-------
 negotiable items
 associated with any
 Work Assignment
 There may also be
 limits on the type of
 work that can be
 performed under a
 particular contract

 In addition to con-
 tract limitations, a
 Work Assignment
 may have non-nego-
 tiable budgetary
 constraints.  For
 instance, if a Work
 Assignment is pro-
 posed near the end of
 a mission contract's
 life, there may no
 longer be a "cushion"
 of additional funds
 should the task re-
 quire more hours to
 complete than origi-
 nally scoped. Other
 non-negotiable items
 could include an
 Agency directive or
 an order from your
 supervisor.

 When developing a
 negotiation strategy,
 it is helpful to list all
 of the non-negotiable
items that pertain to.
 the Work Assign-
ment. Question #3 on
 the checklist will help
you in this effort

4. Identify Nego-
   tiable Items.

The most creative
 part of developing a
 negotiation strategy is
 to think of options for
 possible concessions
 mat you could make.
 Because you have
 already identified
 your bottom-line
 needs and your
 negotiation con-
 straints, you should
 be able to come up
 with some focused
 and useful alternative
 suggestions. If pos-
 sible, try to prepare
 one or two options
 for each of die issues
 that your expect to be
 raised.

 These options are
 especially helpful to
 have in the back of
 your mind while
 negotiating.  They
 can help you to reach
 an agreement much
 faster than if you and
 your contractor both
 began negotiating
 "cold." Question#4
 on the checklist
 suggests some pos-
 sible negotiable
 items.
5. List the questions
   that you want to
   ask the contractor.

While considering
possible ways to
assure that you meet
your "bottom-line"
needs (see Step 2,
 above), you may have
 realized that you
 need more informa-
 tion from the contrac-
 tor before you can
 suggest solutions in
 the negotiation ses-
 sion. For example,
 you may have de-
 cided to suggest that
 the contractor reduce
 the ODC costs in a
 given Work Plan.
 There may, however,
 be a good reason for
 these costs that you
 were not aware of. In
 this case, you should
 ask the contractor to
 explain the basis for
 these costs before you
 suggest that they be
 reduced. Question #5
 in the checklist pro-
 vides space for you to
 jot down these ques-
 tions.

 Identifying some key
 questions ahead of
 time has at least two
 advantages. First, it
 can help you identify
 more targeted solu-
 tions to disagree-
 ments in a
 negotiation session.
 Second, a contractor's
 responses to the
 questions you ask in a
 negotiation session
 will give you an
indication of how
cooperative he or she
will be during that
£-4
                                     September 1992

-------
"Hi
 session. If a contrac-
 tor does not answer
 your (questions in a
 straightforward
 manner and seems
 defensive be pre-
 pared that the nego-
 tiations could become
 heated.

 When asking these
 questions of your
 contractor, it is ex-
 tremely important
 mat you pose them in
 a non-confrontational
 way. Even the most
 well-intentioned,
 cooperative contrac-
 tors can become
 defensive if they feel
 like they are being
 grilled. 'Tips of the
 Trade" in the next
 section, "Effective
 Communication is the
 Key," provides some
 examples of how to
 discuss difficult
 situations in a con-
 structive, non-con-
 frontational way.

 What to Do in a
 Negotiation Session

 The negotiation
 strategy you've
 developed gives you
 the tools to conduct
 the negotiations
efficiently and in a
positive manner. The
question is: What do
you do with the
strategy? It is not
 possible to lay out a
 step-by-step ap-
 proach on "how to
 conduct yourself in a
 negotiation." So
 much of it depends
 on reacting to what
 you hear the other
 negotiator say. De-
 veloping a sense of
 the flow of a negotia-
 tion and the timing
 involved - such as
 knowing when to ask
 a question, offer a
 solution, make a
 demand, or raise a
 new issue - just takes
 practice.

 It is possible, how-
 ever, to offer a few
 pointers on how to
 act in a negotiation
session: these are
briefly noted below.

 • Ask questions first
  Begin the session
  by asking the con-
  tractor the question
  that you identified
  on the checklist
  This will ensure
  that you quickly
  gather all of the
  information you
  need to suggest
  options. Again,
  how you ask the
  questions is impor-
  tant - be sure to use
 non-confronta-
  tional language.
 Couple the non-
 negotiable items with
 a positive suggestion.
 During the negotia-
 tions, the contractor is
 likely to request a
 concession that is one
 of those non-nego-
 tiable items you
 identified in the
 checklist. When this
 happens, explain why
 something is non-
 negotiable, and
 suggest a couple of
 areas that can be
 negotiated. For
 example, you might
 respond to a
 contractor's request
 for more money in
 the Work Assignment
 as follows:

 "Unfortunately, all
 remaining funds in
 the contract have  ,.
 already been commit-
 ted so we don't have
 any extra money for
 the Work Assign-
 ment Maybe we can
 talk about reducing
 the scope somewhat,
 or look at some ways
 to reduce costs."

This statement lets
the contractor know
that the request for
ore funds is some-
thing that your are
unable (rather than
unwilling) to pro-
vide. Chances are,
                September 1992
                                                          6-5

-------
 this will not be raised
 again in the negotia-
 tion session. Suggest*
 Ing one or two
 alternatives to con-
 sider lets the contrac-
 tor know that there
 are other ways to
 address the concern
 of "no enough hours
 to complete all of the
 work."

 • Stick to your
   "agenda." If you
   think the negotia-
   tion discussions are
   going off on a
   tangent don't be
   afraid to say, "I
   would like to get
   back to discussing
   ." This will help to
   ensure that you
   have a chance to
   discuss all of your
   concerns.

 •  Use non-confronta-
   tional language.
   This cannot be
   stressed strongly
   enough. The way
   you say something
   often has much
   more of an impact
   than what you are
   saying.

•  Offer your pro-
   posed solutions.
   Be willing to sug-
   gest the possible
   solutions that you
   identified in Ques-
   tion #4 of the
   checklist Suggest-
   ing alternative
   solutions helps to
   reduce the
   adversarial tone of
   a negotiation
   session. Instead/
   the meeting will
   take on a "team
   spirit" where you
   and your con trac-
   tor are jointly
   trying to resolve
   some problems.

 • Ask the contractor
   to suggest solu-
   tions.  If the con-
   tractor keeps
   shooting down
   every suggestion
   you make, without
   offering any alter-
   native, you could
   ask

   "What do you sug-
   gest as an option,,
   given the con-
   straint that no
   additional funds
   are available for
   the Work Assign-
   ment?" This puts
   the responsibility
   back on the con-
   tractor to come up
   with some solu-
   tions, rather than
   just criticizing
   yours.

When asking this
question, make sure
to reiterate the non-
negotiable items.
   Summarize the
   agreements
   reached. At the
   end of the negotia-
   tion session/ take a
   moment to ver-
   bally summarize
   the agreements
   that you and your
   contractor have
   reached. This will
   help to ensure that
   you both have the
   same understand-
   ing about the
   agreement

 AREA 2 Effective
 Communication is
 the Key

 Most people taking
 this course are prob-
 ably thinking "What
 do I need to learn
 about communication
 that I don't already
 knowr At first
 glance/ this seemingly
 simple topic may not
 seem worthy of
 consideration in a
 contractor manage-
 ment training course.
Not true-itis ex-
 tremely important In
face/ poor communi-
cations with a con-
tractor is one of the
main reasons for a
project's final product
not being adequate to
meet your needs.
6-5
                                      September 1992

-------

 Provide Contractors
 with dear Instruc-
 tions

 When giving contrac-
 tors initial instruc-
 tions on the task,
 always keep in mind
 the tree questions/
 "What?", "When?",
 and "How?" If you
 answer them in suffi-
 cient detail, chances
 are that the contractor
 will have a solid
 understanding of the
work that is required.

1.  "What?"-covers
   the activities that
   a contractor is
   being asked to
   undertake and the
   deliverables that
   must be pro-
   duced.  If the final
   product is a
   written docu-
   ment, describe
   your impression
   of that document   2
  in as much detail    '
  as possible. You
  might say, for
  instance, "I envi-
  sion the report
  covering at least
  the following
 items (list them),
 and being be-
 tween 30 and 50
 pages,  with
 tables." If you've
 seen a product
 you'd like to
    emulate, give the
    contractor a copy
    of it. These initial
    impressions may
    change as the
    work proceeds,
    but at least it
    gives the contrac-
    tor a basic idea of
   what you have in
   mind. To some
   extent, the
   "what?" will be
   covered in the
   Work Plan. But,
   any supplemen-
   tary information
   on the details of
   the Work Assign-
   ment will be
   extremely useful
   to the contractor.
  The kickoff meet-
  ing provides an
  excellent opportu-
  nity for discuss-
  ing the details of
  the Work Assign-
  ment
 "When?" - covers
 the dates you
 expect the con-
 tractor to com-
 plete each activity
 and deliverable.
 Here again, this
 will be covered to
 a large extent in
 the Work Plan. In
 addition to the
 deliverable speci-
fied in the Work
Plan, however,
you may also
       request interim,
       less formal
       deliverables, such
       as a preliminary
       outline for a
       report, or a test
       printout from a
       new database.
       You can request
       these informal
       deliverables at the
       Work
       Assignment's
       kickoff meeting.

   3.   "How?" - pro-
      vides the contrac-
      tor with some
      guidance on the
      general approach
      for completing
      the Work Assign-
      ment. Although
      Work Assignment
      Managers are not
      supposed to
      closely direct how
      a contractor
     should complete a
     Work Assign-
     ment, it is per-
     fectly acceptable
     for you to ask mat
     you be briefed
    regularly on the
    approach used.
    Any concerns that
    you have about
    the approach can
    be raised at these
    briefings.

Tips of the Trade:
To promote effective
communications with
contractors:
                                                        6-7

-------
 • Provide contractors
   with dear instruc-
   tions regarding the
   Work Assignment
   to be undertaken.

 • Always try to give
   the contractor
   positive, rather
   than negative,
   motivation.

 « Foster a "team
   spirit/' rather than
   an adversarial
   relationship, with
   the contractor.

 * Communicate with
   the contractor at
   regular intervals
   throughout the
   duration of the
   Work Assignment.

 •  Establish a "com-
   munications proto-
   col" with the
   contractor at the
   beginning of the
   Work Assignment,
   and stick to it

•  Be open to sugges-
   tions and feedback
  from the contractor
  on the specifics of
   the Work Assign-
  ment

* Be responsive to
  contractor's con-
  cerns about how
   the Work Assign-
  ment is progress-
  ing.
 * Document all
   major changes in
   the Work
   Assignment's
   scope or schedule.

 Communicate Lead-
 ership

 In a very true sense,
 you manage the effort
 of your contractor
 team. What are a
 Work Assignment
 Manager's rights and
 responsibilities?
 Whenever a contrac-
 tor is working for
 you, you have a right
 to expect delivery of a
 quality product on
 the date it was prom-
 ised. You are respon-
 sible for assuring the
 contractor staff un-
 derstand their mis-
 sion.

 Some attention to
 motivations is likely
 to get you the best
 product for your
 money.  Contractors
 want to know that
 you, their client, and
 manager, are satisfied
 with their effort. And
 sensitivity to team
spirit can also help
you head off prob-
lems before they start
Here are some ways
to achieve it:

 • Explain the impor-
  tance of the Work
   Assignment and its
   final product, and
   how it fits in with
   OW goals and
   objectives. This
   will give the con-
   tractor a sense of
   contributing to
   these overall pro-
   gram goals. De-
   scribing the
   importance of a
   Work Assignment
   may also help to
   motivate the con-
   tractor to do an
   excellent job in the
   hopes  that his or
   her efforts could
   lead to future
   follow-up.

•  When the contrac-
   tor has produced a
   good interim
   product (e.g., draft
   report, or anno-
   tated outline for
   draft report),
   acknowledge it

• Put some of your
  own creativity into
   the Work Assign-
  ment. If this per-
  mits, join the
  contractor staff at
  one or more brain-
  storming sessions
  about how the
  Work Assignment
  should be devel-
  oped. Participat-
  ing in a session like
  this will also rein-
                                                           September 1992

-------
«
            force to the con-
            tractor that the
            Work Assignment
            is important to
            you.
          Team spirit goes a
          long way toward
          yielding an excellent
          product Meet your
          commitment be fair,
          and offer praise and
          encouragement to the
          contractor. A positive
          relationship from the
          start will smooth the
          way if difficulties
          arise later.

          • Meet your commit-
            ments for the
            agreed-upon
            amount of time for
            EPA review of
            draft products. If
            due to factors
            beyond your con-
            trol you are unable
            to meet these
            deadlines, then
            you and your
            contractor should
            revisit the Work
            Plan and adjust the
            Work Assignment,
            scheduling to
            reflect this length-
            ened EPA review
            time.

          •  Be fair with the
            contractor regard-
            ing tight deadlines.
            Fast turnaround
   "crisis" tasks are a
   fact of life in any
   agency. However,
   you will burn out
   con tractor staff
   very quickly if you
   are constantly
   asking them to
   burn the midnight
   oil to get products
   completed. It is
   important to iden-
   tify what is and
   isn't a real emer-
   gency on a Work
   Assignment and
   only ask for this
   intensive support
   when there is a real
   need.

 • When the contrac-
   tor has produced
   an inadequate
   product or you are
   dissatisfied about a
   staffing issue,
   express your posi-
   tion clearly and
   constructively.
   The next section
   provides some
   ideas on dealing
   with unpleasant
   issues in these
   areas.

Get Tough Reason-
ably

Occasionally, your
contractor is going to
let you down.  Dis-
covering the causes
take patience and
managerial skill, not
 to mention objectiv-
 ity. You may blame
 personality problems,
 poor communication,
 inappropriate staff-
 ing, lack of direction,
 insufficient senior
 attention, or man
 other pitfalls. It is
 important to identify
 the cause so that you
 can keep it from
 happening again.
 Equally important is
 this: How are you
 going to fix the prob-
 lem right now?

 Here are a few sug-
 gestions:

 •  First, identify the
   main problems
   with a product
   This is especially
   useful if the discus-
   sion is going to
   make you uncom-
   fortable: you won't
   overlook a point

 •  Second, be forth-
   right Don't hint
   around. Your
   contractor is pro-
   fessional enough to
   hear both the good
   and bad news. A
  mixed message
  only confuses the
  listener.

• Third, be clear.
  Don't just say
  "This is terrible."
  Let the contractor
September 1992

-------
    know that "We
    have a long way to
    go on this/' or "We
    have quite a bit
 .   more work to do."
    If the product is
    salvageable, iden-
    tify what you like.
    Then dearly say
    what's wrong.
    Describe any
    broader conceptual
    problems first: then
    focus on details.

 •  Fourth,'be willing
    to listen to expla-
   nations and sug-
   gestions on how to
   fix the product.
   Chances are, the
   contractor will
   come up with the
   same changes you
   want anyway. The
   contractor will
   "own" the prob-
   lems and save face
   at the same time.

 •  Fifth, consider the
   history of the
   relationship and
   apply perspective.
   If this is a rare
   disappointment,
   put despair aside
   and focus on trust
   and mutual prob-
   lem-solving. If the
   contractor or the
   staff is new to you,
   this approach is
   clearly more diffi-
   cult to pursue.
  *  Sixth, bring in an
    objective ally. This
    is a good anchor if
    you're very upset
    The more difficult
    a situation is, the
    more clarity it
    needs. The Project
    Officer for the
    contract is a good
    choice.

 •  Seventh, if staffing
    is the problem, ask
    to meet with a
    senior manager in
    the contractor firm.
    He or she can help
    you work out a
   harmonious solu-
    tion. Be careful,
    though: you aren't
   within your rights
   to dictate contrac-
   tor staffing.

 • Eghth, whenever
   possible, use con-
   structive, not
   confrontational
   language, even
   though you may
   feel angry and
   disappointed. The
   immediate need is
   for damage analy-
   sis and control
  Reprimands, if
  necessary, should
  come later.

The "Tips of the
Trade" box on the
following page shows
two ways of express-
ing your concerns in
  the areas of Work
  Plan negotiation,
  mid-course correc-
  tion, product review,
  and staffing. One
  way of expression is
  dearly more produc-
  tive than the other.

  • Incidental trans-
   portation from a
   private organiza-
   tion in connection
   with official duties,

  • Unsolicited adver-
   tising or promo-
   tional material of
   nominal value
   (under $10), such
   as pens, pads, or
   calendars, and

 • Gifts from family
   or friends only if it
   is obvious that the
   personal relation-
   ship, and not the
   business relation-
   ship, is the reason
   for such gifts.

If accepting even a
nominal gift or gratu-
ity would create the
appearance of an im-
propriety, the Work
Assignment Manager
must refuse it

Tips of the Trade:
If s important to
choose the right
words in touchy
situations. Try to
pose questions that
are open-ended and
G-w
                                      September 1992

-------
          use words that are
          not emotionally
          charged.

          Confidential Busi-
          ness Information

          EPA technical person-
          nel often are privy to
          highly confidential
          contractor informa-
          tion, such as profit
          margins, indirect cost
          rates, number and
          kind of employees,
          individual salary
          rates, or amount of
          award fee. The Work
          Assignment Manager
          must be careful not to
          discuss anything
          known about a par-
          ticular contractor
          with anyone (includ-
          ing other EPA em-
          ployees) who does
          not have a "need to
          know." Even casu-
          ally mentioning your
          personal opinion of a
          contractor's perfor-
          mance on a particular
          task is unauthorized.

          Maintaining Impar-
          tiality

         Government employ-
         ees must remain
         objective about a
         contractor's perfor-
         mance. For this
         reason, a professional
         distance must be
         maintained, and
         socializing with
 contractor personnel
 outside of official
 duties is discouraged
 Government
 employee's actions
 should be such that a
 full public disclosure
 would not give rise to
 a question of impro-
 priety.

 Disclosure of Pro-
 curement Informa-
 tion

 All information
 before award of any
 contract modification
 is highly confidential
 Any unauthorized
 disclosure of this
 information could
 lead to one or more
 contractors having a
 competitive advan-
 tage over others,
 which could result in
 a bid protest

 For this reason, it is
 essential that Work
 Assignment Manag-
 ers do not slip inad-
 vertently let slip any
 advance or otherwise
 confidential procure-
 ment information to
 current contractors or
 other firms who
 contact them.

While these stan-
dards of conduct
seem fairly cut and
dried, there are a
number of gray areas
 that require EPA
 Work Assignment
 Managers to make
 judgment calls about
 the ethics of their
 behavior. The most
 frequently faced gray
 area is how to interact
 with former EPA
 colleagues who have
 left the Agency to join
 consulting firms. The
 training course ac-
 companying this
 manual includes a
 discussion forum oh
 how EPA Work
 Assignment Manag-  .
 ers should deal with
 these gray areas.
 In this training
 course, you will
 receive a copy of
 "Ethics in a Nut-
 shell," a booklet
 summarizing ethical
 conduct for EPA  ;
 employees.

 Ask Yourself

 "Does my behavior
 towards a contractor
 have an appearance
 of impropriety?"  If
 the answer is "yes,"
you should modify
your behavior.
September 1992

-------
 Tips of the Trade: It's important to choose the right words in touchy situations. Try
 to pose questions that are open-ended and use words that are not emotionally charged.
       Confrontational Language
       Constructive Language
                     During Work Flan Negotiation
 Why are these ODC costs so high?
 Can't you get this done sooner?
 Your proposed labor mix has too many
 senior staff hours.
 It shouldn't take so many hours to com-
 plete this subtask.
 Tell me more about the basis for these
 ODC costs.

 Is there a way that we could condense the
 schedule?

 You could reduce costs somewhat if you
 moved some of the senior staff hours to
 more junior levels.

 Explain to me all the steps needed to
 complete this subtask.
                     During Mid-Course Correction
 These revisions will have to be covered
 by the existing money in the task.
Your approach seems pretty inefficient.
 Unfortunately, we don't have any addi-
 tional funds for the task. How can we get
 these revisions completed while staying
 within budget?           :

 There may be another approach to com-
 pleting the work which is less time-con-
 suming.
                        During Product Review
This final product is unacceptable; it will
have to be completely redone.
Here are my changes. Have a new draft
ready in two weeks.

You clearly didn't understand my in-
structions.
I would like to discuss some changes to
the final product. They are fairly exten-
sive, but I think they're necessary to make
the product more targeted to our office's
needs.

What are your suggestions for correcting
these ?????

Lefs discuss how this happened so we
can prevent future misunderstandings.
                           On Staffing Issues
Idon't want Joe on this project any longer.

These staff are way too junior to perform
the work.
There seem to be some personality prob-
lems between Joe and me.

This project requires more senior atten-
tion.
G-12
                                Septerrter1992

-------
            APPENDIX H
       Confidential Business
           Information
O

-------

-------
           APPENDIX   H
                           Confidential Business Information
           What Every WAMs Should Know ...


           If a contractor needs access to CBI ...

           »    each individual oust gain clearance by taking  rand passing)
                the CBI test.                                            *'

           If a contractor needs to maintain CBI documents at their office  ...

           *    The EPA Project Officer must request approval for  CBI Access
                On-site for the contractor.

           *    The contractor aust  prepare  and submit a security plan to the
                CBI office for approval.

           -    The contractor must  agree to meet all  requirements set forth
                in the CBI security  manual.

           The requirements of the security manual (which subsequently impact
           on the work assignment management)  include:

           »    Contractor is required  to appoint a Documant Control Officer
                who is responsible for ensuring that all CBI documents on-site
                are secure.

           »    Contractor must submit  a  security plan to the CBI office and
                submit to an on-site facility inspection.

           »    Contractor must submit an annual inventory of  all      CBI
                documents in their possession.

           »    Contractor must return  all      CBI documents to the EPA CBI
                Office at the end of the contract  or when the documents are no
                longer required (whichever occurs first).

           »    Contractor must, return all CBI documents to the EPA CBI Office
                upon request.
c

-------
            Q:
          DISCLOSURE OF  CONFIDENTIAL  BUSINESS INFORMATION
                          TO CONTRACTORS


 This guidance will  address two questions:

 1.  Does the contractor view Confidential Business Information?

 2.  Is the contractor authorized for access to that information?



 1.  Does the contractor view Confidential Business Information?

 Q:  What kind of information is entitled  to confidentiality?

 A:  Generally,  any information  whose  release is  likely to  cause
     harm to the competitive position  of the submitter.   If a
     competitor  could use the information  to the  disadvantage of
     the  submitter, disclosure is  likely to be considered as
     causing "substantial" harm.

    May  I therefore  ignore any information that  I think  will not
    cause competitive harm to the submitter?

A:  No.  EPA confidentiality regulations at 40 CFR Part  2,     .
    Subpart B require that the Agency protect from disclosure
    (except where EPA has made a formal determination otherwise)
    any information where l)  the submitter of the information
    has claimed the information as CBI, or 2) might be expected
    to object to its release (even if a CBI claim has not been
    made).


    This  means that when examining contracts, work assignments,
    and delivery orders to determine whether they involve
    viewing  CBI,  consider not only information which you  think
    is  entitled  to confidentiality,  and not only  information
    which is actually marked as  confidential, but also
    information  for which the submitter might be  expected to
    want  protection (see  the next  question * answer  for guidance
    on types of  information likely to  be at issue).

    In general, any time  a contractor  or subcontractor is
    viewing  information submitted  by a  business,  there is a
    possibility that  some of the information is subject to
    confidentiality claims, and you should  examine that
    information closely.
G

-------
  Q:   Z can't read the mind of a submitter.  Give ne some examples
       of information which night require protection.

  A:   Following is a list of types of information frequently
       claimed as confidential by the submitting company.  This
       list is by no means exhaustive, and should not be used to
       limit investigation.


       -  Trade secret formulas,  devices and identities of chemicals

      -  Identities of pesticide inerts


      -  The fact that a company is manufacturing,  importing,
         processing,  etc.  a particular chemical


      •  Production volumes of chemicals or amount  stored at a
        company  facility


      - Industrial process information


      - ANY financial data regarding a  company (e.g., assets,
        profits, taxes), obtained from  any  source

      - Contractor-supplied information generally, including:

        o  Direct Labor rates

        o  Indirect rates: overhead, general and administrative,
           fringe benefits, etc.
        o  Other contractor charges
        o  Identities of employees and their salaries
        o  Monthly progress reports
        o  Contract m-ono**!-.
  	1 *	^-•—»» 4.1
Contract proposals
Fees
     -  Note that information contained in a document submitted
        by a business does not become non-confidential by
        virtue of being put into an Agency-generated document.
        For example,  source selection documentation generated by
        EPA contains  information obtained from offerers vhich
        may be subject to  confidentiality claims.

2.  Is  the contractor authorized for access  to that information?

Q:  When may  a contractor  be  authorized  to view any information
    claimed as CBI?
                                                                W-3

-------
                                                                    •   .   \
           A:   The Trade  Secrets  Act  prohibits disclosure  of  CBI  to anyone
                outside the Federal Government except where authorized by
                law.  The  environmental  statutes administered  by EPA (e.g.,
                TSCA, FIFRA) contain provisions authorizing the Agency to
                disclose to contractors  information collected pursuant to
                those statutes.  However, information not collected pursuant
                to an environmental statute, e.g., information collected
                from an Agency contractor, may not be disclosed to anyone
               outside the Federal Government,  such as another contractor,
               UNLESS THE SUBMITTER OF THE INFORMATION HAS CONSENTED TO
               SUCH DISCLOSURE.

           Q:   if CBI that the contractor sees  is collected pursuant to an
               environmental  statute,  is my inquiry finished?

           A:   No.  40 CFR (2.301(h)   requires that several steps  be taken
               before CBI  can  be disclosed  to a contractor  or  subcontractor.
               These  include:

               ~ writing  into the contract certain provisions concerning
                 use and  disclosure of  CBI, as spelled out in EPA
                 contract clause  EPAAR  1552.235-71;

              — in the case of data collected under TSCA  or FIFRA,
                 writing  into the contract certain provisions concerning
/                security of CBI  (see EPAAR 1552.235-72); and

              — prior to disclosure,  giving notice to submitters
                 (either by letter of by Federal  Register notice)  of the
                 information  to  be disclosed, the identify of  the
                 contractor or subcontractor, and the purpose  of the
                 disclosure.

             If these steps have  not  been  followed,  then the  contractor
             is not  authorized the view the CBI.

         Q:  If contractor A  is to view CBI from  Contractor B,  (i.e.,
             not submitted under  the  authority of an environmental
             statute), what is necessary to authorize contractor  A  to
             view contractor B's  CBI?





         1  For data collected under EPCRA/SARA Title III, 40 CFR
           {350.23(b) is the applicable regulation.
                                                                          H-4

-------
          A:  The contractor submitting CBX must have given written consent
              for such disclosure, through one of the following methods:

              —  a letter specifically authorizing disclosure to
                  Agency contractors;

              —  a contract provision specifically authorizing disclosure
                  to Agency contractors; or

              --  a provision in an EPA solicitation authorizing disclosure
                  to Agency contractors for audit purposes only.

              Note the following limitations on consent:

              —  When a contractor gives such consent it will generally
                  be very narrow.  That is, it may apply only to
                  information collected pursuant to the administration
                  of one specific contract, only for a specific purpose,
                  to one specific contractor, etc.  Therefore, consent by
                  a contractor to one disclosure cannot necessarily be
                  relied upon for other disclosures to Agency contractors.

              —  A notice published by the Agency in the Federal Register
                  does not constitute consent, even if the submitter reads
                  the notice and does nothing.  Consent must be
                  demonstrated by a positive act of;the submitter.

              In addition, the contractor who will be given access to
              other contractors' CBI must be working under a contract
              which contains contract clause EPAAR 1552.235-71.*

              If these steps have not been followed, then the contractor
              is not authorized to view the CBI.

              It you have questions concerning this guidance, call Don
              SadowsXy of the Office of General Counsel at (202) 260-5469.
o
2  Although the preamble of EPAAR 1552.235.71 contemplates that
this clause be used when providing a contractor with CBI obtained
pursuant, to one of the environmental statutes administered by
EPA, it* provisions are relevant to this discussion of CBI
obtained from an Agency contractor.  Nonetheless, in order to
eliminate any possible ambiguity concerning the scope of this
provision, an additional provision should be added to the
contract stipulating that, for the purposes of this contract,
EPAAR 1552.235-71 shall apply to any Confidential Business
Information provided to the contractor by EPA, whether or not
obtained pursuant to an environmental statute.
                                                                          M-5

-------

-------