DRAFT SUPPLEMFNTAL ENVIRONMENTAL IMPACT STATEMENT
    Wastewater Treatment Facilities for the Columbus, Ohio Metropolitan Area


                                 Prepared by the
                 United States Environmental Protection  Agency
                                    Region V
                               Chicago, Illinois

                                      and
Science Applications
International Corporation
McLean, Virginia
With
Triad Engineering
Incorporated
Milwaukee, Wisconsin
                                 December 1987
                                                  Approved by:
                                                  Valdas  V.
                                                  Regional Administrator

-------
                              EXECUTIVE SUMMARY

 (X)  Draft Supplemental Environmental  Impact Statement
 (  )  Final Supplemental Environmental  Impact Statement
 U.S. Environmental Protection Agency,  Region V
 230 South Dearborn Street
 Chicago, IL  60604
 1.   NAME OF ACTION
     Administrative (X)
     Legislative    ( )
 2.   LEGAL BASIS FOR ACTION
     The U.S.  Environmental Protection Agency (EPA) is the administering
 agency for a major federal environmental program, provided for by Title II of
 the Clean Water Act, entitled "Grants  for Construction of Treatment Works."
 This program allows the EPA administrator to provide financial aid to any
 state, municipality, intermunicipal  agency, or interstate agency for the
 construction of publicly owned water pollution control facilities.  The
 program encourages reduction of point  sources of water pollution and
 improvement of water quality.

     The EPA's  granting of funds  for  a  water pollution control facility
 requires a review to comply with the National Environmental Policy Act (NEPA)
 and may require an environmental impact statement  (EIS).   Each proposed water
 pollution control facility is evaluated on a case-by-case basis by the
 appropriate EPA regional office  to determine whether the proposed facility is
 expected to have significant environmental effects.  This review is utilized
 in determining whether the proposal  appears to be a cost-effective solution to
 area water quality problems.

     Given that the Columbus project involved; 1) substantial  changes  in the
proposed action and  possible  significant environmental impacts  associated  with
those changes;  and 2) new information which raises substantial concerns not
addressed in the original EIS, it  was reasonable  and prudent  for USEPA to

-------
proceed with the preparation of a supplemental EIS in accordance  with 40 CFR
1502.9(c).

3.   PURPOSE AND NEED FOR PROJECT
     The city of Columbus,  owns and operates two major wastewater treatment
facilities.   The Jackson  Pike  WWTP is located  in  southwest Columbus.   The
Southerly WWTP  is located approximately 8 miles south of downtown Columbus.
Both of these plants discharge to the Scioto River  and will  require upgrading
to ensure compliance with revised National Pollutant  Discharge Elimination
System (NPDES)  permits.

     Original NPDES permits for Jackson Pike  and  Southerly set effluent
limitations of 30 rag/1 (30-day average)  for five-day  carbonaceous biochemical
oxygen demand (CBODj) and total suspended solids (TSS).   In  1985, the NPDES
permits for both plants were  revised.  Tables  1 and 2 present the effluent
standards of the revised  permits.  The limits  vary on a  seasonal  basis.  CUOO^
and TSS limits are more stringent and standards for ammonia  and dissolved
oxygen have been added to the permits.  The plants are required to be in
compliance with these final effluent  limits by July  1, 1988. Until that time,
the Jackson Pike and Southerly plants are operating under interim limits of
25 mg/1 for CBOD5 and 30 mg/1  for TSS.

4.   PROJECT HISTORY
     In 1976, the city of Columbus prepared the Columbus  Metropolitan
Facilities Plan for wastewater management up to the year 1995.  The 1976
facilities plan concluded that the cost-effective  solution to improved
wastewater treatment was rehabilitation and expansion of both the Jackson Pike
and Southerly WWTPs.

     After reviewing the original facilities  plan,  the USEPA initiated
preparation of an EIS on the 1976 facilities plan.  The EIS, when completed in
1979, contained  recommendations for wet stream treatment and solids handling
                                       11

-------
                    TABLE 1.  NPDES FINAL EFFLUENT LIMITS
                              JACKSON PIKE WWTP
                      	 CONCENTRATION
                          SUMMER
PARAMETER

Suspended Solids
 (mg/1)

CBODc
 (mg7D

Ammonia
 (mg/1)

Fecal Coliforra
 (count/100 ml)
The Dissolved Oxygen shall be maintained at a level of not less than 7.0 mg/1
and shall be monitored continuously and the lowest value  reported daily.

The ChlorineResidual shall be maintained at a level not  to exceed 19 ug/l and
shall be monitored continuouly and the highest  value  reported daily  (summer
only).

Source:  OEPA Permit NoT"4PFOTOOO*GD
Summer = June - October
Winter = November - April
SUMMER
(30-day/7-day)
16.0/24.0
8.0/12.0
1.0/1.5
1000/2000
WINTER
(30-day/ 7-day)
30.0/45.0
20.0/30.0
5.0/7.5
____
MAY
(30-day/ 7-day)
26.0/39.0
13.0/19.5
2.5/3.75
«.«.
                                 Ill

-------
                    TABLE 2.  NPDES FINAL EFFLUENT LIMITS
                                SOUTHERLY WWTP
                                            CONCENTRATION
PARAMETER

Suspended Solids
 (rag/1)

CBODc
 (mg/1)

Ammonia
 (tng/1)

Fecal Coliform
 (count/100 ml)
    SUMMER
(30-day/7-day)

  16.0/24.0
   8.0/12.0


   1.0/1.5


  1000/2000
    WINTER
(30-day/7-day)

   30.0/45.0
   25.0/40.0
    5.0/7.5
      MAY
(30-day/7-day)

   26.0/39.0
   13.0/19.5
    2.0/3.0
The Dissolved Oxygen shall be maintained at a level of not less than 7.0 mg/1
and shall be monitored continuously and the lowest value  reported  daily.

The Chlorine Residual shall be maintained at a level not  to exceed 26 ug/1 and
shall be monitored continuouly and the highest value reported daily

Source:OEPAPermit No. 4PF00001*HD
Summer = June - October
Winter = November - April
                                  IV

-------
that differed from the recommendations  of the original facilities plan.  The
differences in wet stream treatment recommendations were due to process
selection, reliability, and design criteria differences.   With regard to
solids handling, the EIS differed from the original facilities plan by
proposing that land application and composting rather than incineration/
landfill be adopted as the primary means  of  solids disposal.

     In order to address the differences in design parameters between the EIS
and the original facilities plan, in the final EIS USEPA  directed  Columbus to
establish a Design Finalization Overview Team (DFOT)  to review and recommend
the final design parameters for both plants.

     The DFOT Report was completed in May of 1984.  On July 9, 1984, the city
submitted a Plan of Study which set the  groundwork for a  facilities  plan
update.   The Plan of Study for the facilities plan update proposed significant
changes from the original facilities plan.  Therefore,  the  DFOT Report  was
never formally reviewed by Ohio EPA or USEPA.

     The Columbus Metropolitan Area Facilities Plan Update (FPU) Report was
submitted to Ohio EPA in December  1984.   The FPU recommended phasing out the
Jackson Pike WWTP and sending all flow to an upgraded and expanded Southerly
WWTP.  Ohio EPA reviewed this document and prepared detailed  comments and
questions for the city.

     In September of 1985, the city submitted the Revised Facilities Plan
Update (RFPU)  as  a  supplement  to the  FPU.   The specific objectives of the RFPU
were:
     •  To revise the recommendations of previous documents based on revised
        design parameters;
     •  To respond to comments by Ohio EPA relative  to the FPU;
     •  To present conclusions and  recommendations of planning analyses
        undertaken since completion of the FPU;  and  to develop treatment
        facilities which would serve the city's  needs though the year 2015.

-------
     The RFFU contained the following basic conclusions and recommendations:

     •  It is cost effective  to  expand  the  existing Southerly WWTP to treat
        all wastewater from  the Columbus service area and to phase out the
        existing Jackson Pike WWTP.

     •  Phasing out the Jackson Pike WWTP will have no significant adverse
        environmental impacts.

     •  The Southerly WWTP expansion will be based upon a design average  flow
        of 178 MGD and a  peak process flow  of  300  MGD.   Peak flows of up  to
        430 MGD may be generated from a CSO control program.  Flow in excess
        of 300 MGD would be settled and chlorinated prior to discharge.

     •  The proposed treatment facilities would utilize a semi-aerobic
        process.

     *  Additional standby incineration capacity beyond that presently under
        construction at Southerly is not recommended since sludge  composting
        and land application  of digested sludge will continue as the preferred
        method of solids disposal.


5.   EIS ISSUES

     During review of the Revised Facility  Plan Update,  a number of

potentially significant environmental impacts  were identified.   These  impacts

were the subject of USEPA's action to issue a Notice of Intent (June 11,  1986)

to prepare a supplemental EIS.   This supplemental EIS addresses  the  following
issues:
     •  The reliability of the semi-aerobic process to effectively meet NPDES
        permit limits.

     •  Water quality impacts resulting from a single  plant  discharge.

     *  The imact on river flow resulting  from the  elimination of Jackson
        Pike's flow.

     •  The impacts expected from the fulfillment of the population projec-
        tions and development for the planning area.

     •  Alternatives for environmentally acceptable sludge treatment and
        disposal.
                                      vl

-------
     *  The induced growth and secondary environmental effects of an expanded
        Southerly WWTP.

     •  The cost-effective treatment of combined sewer overflows as an
        integral part of the system.

     *  The impact of expanding the south end of Interconnector by extending
        the 156-inch gravity sewer to Southerly and placing four 78-inch pipes
        across the Scioto River.

     •  The reliability of the Southerly WWTP as the only plant treating
        sewage in Columbus.

     •  The economic effects of the proposed plan.   What  is the cost-effective
        solution to the wastewater management problems in Columbus7

NOTE:  USEPA has prepared this SEIS based on the conditions as of 1985.


6.   WASTEWATER MANAGEMENT ALTERNATIVES

     In addition to a no action alternative,  three comprehensive  management

alternatives were evaluated in the Supplemental EIS.  They include the

following:


     •  Two-Plant: Upgrade Southerly and Jackson Pike,  provide wet stream
        treatment and solids handling at both plants.

     •  Two-Plant One Solids:  Upgrade Jackson Pike and Southerly, provide all
        solids handling at Southerly.

     •  One-Plant:  Eliminate Jackson Pike,  upgrade and expand Southerly.


     Each comprehensive wastewater management alternative includes the

following components:


     •  Interconnector/Headworks

     •  Biological Process

     •  Sludge Management


     Options for each of these components were also evaluated.  They include

the following:
                                     vii

-------
        Interconnector/Headworks
        -  A/A-1 (additional pumping, force mains, and headworks)
        -  B/B-1 (extension of gravity sewer and separate headworks)
        -  B/B-2 (extension of gravity sewer and entirely new headworks)

        Biological Process
        -  Serai-aerobic
        -  Trickling Filter/Activated Sludge (TF/AS)

        Sludge Management
        -  JP-B (Primary Sludge (PS) Thickening, Waste Activated Sludge (WAS)
           Thickening, Anaerobic Digestion,  Dewatering, Incineration/Landfill,
           Land Application)

        -  JP-C (PS Thickening, WAS Thickening, Anaerobic Digestion, Thermal
           Conditioning, Incineration/Landfill, Land Application)

        -  SO-C (PS Thickening, WAS Thickening, Anaerobic Digestion, Dewatering,
           Incineration/Landfill,  Composting)

        -  SO-D (PS Thickening, WAS Thickening, Anaerobic Digestion, Dewatering,
           Incineration/Landfill,  Composting, Land Application)

        -  SO-F (PS Thickening, WAS Thickening, Dewatering, Incineration/
           Landfill, Composting)
     Table 3 summarizes each wastewater management alternative with its
respective component option.


     Each of the component options were evaluated with respect to technical
criteria consisting of cost, reliability,  flexibility,  implementability, and
operational convenience.   The optimum option to fulfill each component was
selected for both the one-plant and two-plant alternatives.
One-Plant Alternative

     The selected component options for the one-plant alternative include:


     •  Interconnector/Headworks Option B/B-1

     *  Biological Process - Semi-Aerobic

     •  Sludge Management Option SO-D
                                      viii

-------
           TABLE 3  SUMMARY OF  ALTERNATIVES AND OPTIONS
WASTEWATER
MANAGEMENT
ALTERNATIVE
ONE-PLANT
TWO-PLANT
TWO-PLANT ONE SOLIDS
COMPONENT
INTERCONNECTOR/HEADWORKS
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
OPTION *
A/A-1
B/B-1
B/B-2
SEMI-AEROBIC
TF/AS
SO-C
SO-D
SO-F
SEMI-AEROBIC
TF/AS
SO-C
SO-D
SO-F
JP-B
JP-C
SEMI-AEROBIC
TF/AS
SO-C
SO-D
SO-F
* DETAILED DESCRIPTION [N CHAPTER 5

-------
     The Interconnector/headworks option B/B-1 consists of extending the
 156-inch diameter gravity Interconnector Sewer to Southerly,  using four
 parallel 78-inch pipes for the Scioto River crossing, and constructing
 separate headworks at Southerly for the Interconnector flow.   This option was
 selected based on cost and reliability.  Option B/B-1 was approximately the
 same cost as option A/A-1 (force mains) and 15 percent less costly than option
 B/B-2 (gravity sewer and entirely new headworks).  The gravity sewer was
 considered to be more reliable than the force main since there is less chance
 that the gravity sewer will  rupture.  Furthermore, failure of a gravity sewer
 normally results in infiltration to the conduit,  while a rupture of the force
 mains would cause exfiltration  to the environment.   In addition, the gravity
 sewer does not rely on the operation of a pumping facility to perform.

     The semi-aerobic process is a modified form of  the conventional activated
 sludge process which currently exists at the  Southerly WWTP.   It differs from
 conventional activated sludge in that the first 25 percent of the reaction
 basin is not aerated.   Only  mixing is provided.  This maintains that a portion
 of the basin is in an anaerobic or anoxic state,  depending on the level of
 nitrates present.   The process also includes  an internal  mixed liquor recycle
 loop to provide the capability of recycling nitrates  from the last bay of the
 aeration basin back to the first bay to accomplish denitrification.

     The semi-aerobic process was selected over the  trickling filter/activated
 sludge process due to its reliability.   The semi-aerobic process is considered
more reliable due to the fact that more process control flexibility is
 inherent in the process.   Furthermore,  the  trickling  filter process would be
difficult to implement in that it would require major restructuring of the
conduits between the existing primary clarifiers and aeration basins.  The
 trickling filter/activated sludge process would also be subject to an adverse
environmental review due to  its resultant odor and pests.

     The selected sludge management  option for the one-plant alternative,
 SO-D,  includes gravity thickening of PS, centrifuge thickening of WAS,

-------
anaerobic digestion, centrifuge dewatering, composting,  land application, and
incineration/landfill.  This is consistent with the current sludge management
scenario at Southerly, with  the exception of  land  application.  Southerly does
not  land apply sludge at the present time.  However, land application is
employed at Jackson Pike.

     Option SO-D was chosen  over SO-C and  SO-F because it provides more
flexibility and reliability in that it includes three methods of final
disposal.

Two-Plant Alternative
     The two-plant  alternative does not require expansion of the Interconnector
Sewer or additional headworks  at Southerly.  Therefore, selection of an
Interconnector/headworks option was not necessary.  The two-plant alternative
does require new headworks for Jackson Pike located at the plant site.

     The selected component options for the two-plant alternative include:

     *  Biological Process - Semi-Aerobic
     *  Sludge Management Option SO-D
     •  Sludge Management Option JP-B

     The semi-aerobic process was selected over the trickling filter/activated
sludge process for the Jackson  Pike and Southerly WWTPs under  the  two-plant
alternative for the same reasons which were presented for the one-plant
alternative.   These reasons include more reliability with the  semi-aerobic
process due to process flexibility;  and difficulty in implementing the
trickling filter/activated sludge process due  to existing plant configuration
and environmental concerns.   In addition,  the  semi-aerobic process is 20 percent
less costly than the trickling filter/activated sludge process.
                                      XI

-------
     Similar  to  Che one-plant alternative, option SO-D was selected for
Southerly under  the two-plant scenario.  Option SO-D provides more flexibility
and reliability  due to three methods of final disposal:  composting, land
application, and incineration/landfill.

     Option JP-B was selected for Jackson Pike under the two-plant scenario
based on cost and ease of operation.  Option JP-B includes gravity thickening
of PS, centrifuge thickening of WAS, anaerobic digestion, centrifuge
dewatering, incineration/landfill,  and land application.  Option JP-B is
approximately 15 percent less costly than option JP-C which includes thermal
conditioning in addition to the processes included in JP-B.   Thermal
conditioning is difficult and expensive to operate and maintain.  Therefore,
it is recommended that the thermal conditioners be phased out of service when
they reach the end of  their useful  life.

     The two-plant one solids alternative was eliminated from consideration
following the analysis of the one-plant and two-plant solids options.  The
analysis showed  that it was less costly to maintain solids processing at both
Southerly and Jackson Pike if both facilities are providing liquid treatment.

7.   EVALUATION OF COMPREHENSIVE WASTEWATER MANAGEMENT ALTERNATIVES
     The one-plant and  two-plant comprehensive wastewater management
alternatives were evaluated based on the same technical criteria used to
evaluate the component options.   These criteria included present worth cost,
reliability,  flexibility,  impleraentability, and operational convenience.

     In addition to  the technical evaluation, an environmental  evaluation was
performed for the one-plant and two-plant alternatives.  The evaluation
considered physical,  biological,  and human environmental criteria.  Physical
criteria included water, air quality, and prime agricultural land.  Biological
criteria included terrestrial  and  aquatic  biota as well as threatened and
endangered species.   The human or man-made environmental criteria included
land use, noise,  energy, economics,  transportation,  and historic and
                                      Xii

-------
archaeologic resources.  Indirect environmental consequences such as induced
growth were  also  considered.

Technical Evaluation
     Table 4 presents the capital, annual O&M, and total present worth costs
for the one-plant and two-plant alternatives.  The two-plant alternative
exhibits a total present worth cost approximately 7 percent lower than the
one-plant alternative.

     Both the one-plant and two-plant alternatives are equal with respect to
their reliability in meeting the final effluent limits.   However,  the two-
plant is considered more reliable with respect  to shock  loads.  Under the
one-plant alternative, a plant upset at Southerly could result in a
significant loss of biological treatment capacity and may cause a serious
water quality problem.  However, if the shock and/or toxic load can reach only
one of the two plants, the impact may not be  as severe.

     The two-plant alternative is judged  more flexible than the one-plant
alternative.   With both facilities operational,  the city  would have  more
flexibility to adapt to increased  future  flow, to  more stringent effluent
limits, and to address combined sewer overflows.  The  two-plant alternative
would leave more land available at Southerly for expansion.   The two-plant
alternative would improve and upgrade Jackson Pike to provide a solid 100 MGD
treatment capacity.   The two-plant alternative would allow for future
expansion of the Interconnector system to divert more  flow to Southerly while
optimizing the use of the Jackson Pike facility.

     The two-plant alternative is considered easier  to implement since the
majority of the facilities  already exist.  Most  of the construction  would
consist of rehabilitation of existing facilities.  There  would be no
expansion of the conveyance system between the plants under this alternative.
                                     xiii

-------
                      TABLE 4.  ALTERNATIVE COST SUMMARY


                                                                   Total
                                 Capital        Annual O&M     Present Worth

One-Plant [Southerly]          268,711,000      16,849,000      436,911,000

Two-Plant [So. and JP]         217,860,000      19,078,000      407,800,000

Difference From One-Plant      -50,851,000      +2,229,000      -29,111,000

Percent Difference                 -23             +13               -7
NOTE:  These costs are based on a 2008 average flow of 154 MGD and a peak flow
       of 231 MGD.  Present worth costs are in 1988 dollars.
                                        xiv

-------
     The one-plant alternative is considered easier to operate and maintain
since all facilities would be consolidated at one location.

Environmental Evaluation
     The environmental evaluation identified four major impacts which were in
the following areas:

     •  Surface water quality
     •  Surface water flows
     •  Aquatic biota/habitat
     •  Endangered Species

Surface Water Quality
     The principal variable affecting surface water quality under either
alternative is the location of  wastewater discharge.   Comparable levels of
treatment will be provided under either the one-plant or two-plant
alternative} and either alternative  will  protect  stream standards for DO and
ammonia.

     Regardless of the one-plant or two-plant alternative, the treated
effluent will contain a residual  wasteload,  which will be assimilated by the
river,  resulting in a downstream DO sag.   The severity of the sag, and the
extent of the river affected, vary between alternatives.

     Under the no action alternative,  no  improvement in the degraded  water
quality conditions in the Scioto River would occur.   With projected future
growth in the sewered population (and corresponding  increases  in  wastewater
flows),  age-related  deterioration of the  existing  WWTPs and increases in urban
non-point runoff due to continued urban growth,  further deterioraton  in
current water quality conditions would be expected.   Under these conditions,
more frequent water quality standard violations could be expected and the
impacted zone of the Scioto River below Southerly  may be extended to
Circleville, interfering with other point source discharges.
                                      xv

-------
     The two-plant alternative would release the residual effluent DO demand
 to  the Scioto River at two  locations (Jackson Pxke and Southerly).  Two  DO
 sags would  therefore result; however, neither sag would result in contraven-
 tion of water quality standards.   Significant improvements  to  in-stream  DO
 conditions would result from this alternative.  Because significant pollutant
 loads would continue to enter  the Scioto River upsteam of Jackson Pike (from
 urban runoff and CSOs from Whittier Street), the degree of water quality
 improvement below Jackson Pike would be less complete than below the Southerly
 WWTP.  Under certain flow conditions,  DO levels  below the 5.0  mg/1 standard
 could occur below Jackson Pike, related to CSO loadings.  However, the
 presence of Jackson Pike effluent during low flow events could lessen the DO
 impacts of CSOs and upstream urban runoff.

     The impacts of the one-plant alternative would be variable for the  river
 reach between Jackson Pike and Southerly, and depending on background river
 flow conditions at average river flow  levels,  water quality would be  improved
by the elimination of Jackson Pike effluent.  However, under critical low  flow
 conditions,  elimination of the Jackson Pike effluent would reduce Scioto River
 flows by nearly 90 percent,  while a  large background  pollutant load would
 remain in the form of urban runoff and CSO loading.   This  situation would
 result in a significant reduction in the river's wasteload  assimilative
 capacity due to reductions in flow volume, velocity, and reaeration.  Decay of
 pollutants from upstream sources could,  therefore, result  in severe water
quality deterioration in slow,  shallow pools during warm  weather,  low flow
 events.

     Downstream of the Southerly WWTP,  the DO sag resulting from the one-plant
alternative would be more  severe and would affect  a  longer stretch of the
 river, when compared with the  two-plant alternative.  This situation results
 from the release of the entire  residual  wastewater DO demand from Columbus at
 a single point in the river, creating  a  greater  assimilative demand.  In
 addition,  the increased nutrient  release under the one-plant alternative  would
 further stimulate algal biomass below Southerly  which may depress low flow DO
                                     xvi

-------
below  in-streara  standards  due to algal metabolism.  The combination of these
factors results in a possibility that the one-plant  alternative  may impact
the Circleville area, interfering with other point source dischargers near
Circleville.  Based on these considerations,  the two-plant alternative is
considered preferable over the one-plant alternative with regard to water
quality impacts.

Surface Water Flows
     The no action and the two-plant alternatives will have little or no
impact on surface water flows in the Scioto River.  The one-plant alternative
would cause significant reductions in flows in the Scioto River during dry
weather periods in the eight-mile reach between the Jackson Pike  and Southerly
WWTPs.  This reduction in  flow would have negative impacts on water quality,
aquatic biota,  and recreation in that portion of the Scioto River.

Aquatic Biota/Habitat
     The no action alternative would result in continuation of the current low
dissolved oxygen and high residual chlorine condition and related aquatic
habitat degradation in the Scioto River below Columbus.  Pollution intolerant
species would continue to be excluded from the affected areas  of  the Scioto
River,  below the Jackson Pike WWTP and below the Southerly WWTP.

     Under the  two-plant alternative,  water quality should improve which in
turn would have a favorable impact on aquatic biota and habitat.   Sensitive
species that currently inhabit the area should persist and increase in
abundance.   New species may move into the area and increase community
diversity.   However,  more sensitive species may suffer due to  marginal DO
levels  immediately below each of the two  treatment plants.  In addition,  the
continuing negative impacts of general urban  runoff and pollutant  loads  from
the Whittier Street CSO will prevent  free biological recovery in the Central
Scioto.
                                     xvii

-------
     The one-plant alternative would impact aquatic habitat and biota due to
 the elimination of the discharge at Jackson Pike, the increase in discharge at
 Southerly, and the placement of four 78-inch sewer pipes across the Scioto
 River  near Southerly.

     The elimination of the Jackson Pike discharge would decrease the flow in
 the Scioto River between Jackson Pike  and Southerly.  Under critical  low  flow
 conditions,  a significant loss of benthic habitat area  would result.   This
 condition could dissrupt spawning, feeding,  and migratory activities  of the
 fish.   Furthermore, as previously discusssed under  low  flow  conditions the
 loss of the  Jackson Pike discharge  could result in degraded water quality
 conditions which in turn would have negative impacts on aquatic biota.

     Under normal flow conditions,  the elimination of the  Jackson Pike WWTP
discharge would result in improved water quality conditions to the extent that
 this effluent affects  water quality.  These improvements  would result in
 favorable aquatic community responses.

     The increased discharge at the Southerly WWTP would result in an increase
 in the length of the  river affected by the DO  sag.   Degradation of aquatic
communities  can be expected in the vicinity of  the DO sag.

     Construction across the Scioto River would have  localized,  short-term
 impacts on aquatic biota and habitat.  Impacts  will stem primarily from
 increases in sediment  transport and deposition  downstream of  the construction
site.   Fish  would suffer fewer short-term impacts than benthos as they can
avoid the construction site,  but stresses and  mortalities should be expected.
 Increased turbidity would also temporarily damage habitat of  species  which use
pools due to  lowered oxygen levels  caused by organic  loads associated  with
eroded soils.   The  distance affected and the degree of  stress  would depend on
the amounts of sediment  which would be displaced;  however, mitigation
techniques should minimize impacts.
                                    xv ill

-------
Endangered Species
     Terrestrial endangered species should not be affected by the no action
alternative.  However, the aquatic endangered species habitat would suffer due
to continued degradation of water  quality.  Several federal and state
designated endangered and rare fish have been sighted in the Central Scioto
River mains tern within the past five to seven years, and those species would
most likely be disturbed.  The degraded habitat would prevent their
populations from growing in the affected areas.

     Small populations of other endangered or rare fish live in tributaries to
the Scioto River where water  quality  is better.  The Central Scioto River
mainstem potentially could provide habitat for these species if water quality
was improved.   Continued degradation of water quality would decrease the
chances  for these fish to expand their ranges into the Scioto River.

     Endangered aquatic species should benefit from implementation of the two-
plant alternative.   Improvements in water quality should allow the endangered
fish species that have been identified in the Scioto River to increase in
number and allow the species  inhabiting tributaries to expand their ranges.
Specific information on the tolerances of these species to turbidity and
lowered DO is not available,  preventing an assessment of the conditions under
which these species would establish permanent breeding populations.  Increased
habitat for feeding, however,  should benefit  populations.

     Long-term  impacts of the one-plant alternative stem from:  1) modified
water quality below Jackson Pike and Southerly,  and 2) reduction in flow
between the Jackson Pike and Southerly WWTPs.

     Below Jackson Pike, water quality  would  be somewhat improved under most
flow conditions.  These  improvements may encourage rare, threatened, and
endangered aquatic fauna to increase in range and abundance entering the
Scioto  River from tributaries or less  impacted river areas further downstream.
                                     xix

-------
     Under the one-plant alternative, however,  the critical  low flow
conditions will be the limiting factor on re-colonization of the Upper Scioto
River (between Jackson Pike and Southerly) by rare,  threatened,  and endangered
species.  Because  of  the  nearly 90  percent reduction  in river flows during  low
flow conditions, residual DO demands from other upstream sources will result
in degraded water quality in shallow, still pools  during  warm weather.  Under
these conditions,  the sensitive species  will be reduced  or eliminated,
cancelling the benefits to water quality which  will occur under higher flow
conditions.

     The nearly 90 percent reduction in river flows between Jackson Pike and
Southerly under low flow conditions, will exert additional negative impacts on
aquatic fauna due to the physical effects of reduced flows and  diminished
habitat area.   Reduced  velocities associated with  low flow could stress  some
species and possibly limit their range.   Because many of the species feed in
riffles, drying out of  riffles  also could  hinder the movement of these species
into the affected river segment.

       Table 5 summarizes  the  technical and environmental evaluations.

8.   PREFERRED PLAN
     Based on the technical and environmental evaluations, the  two plant
alternative is recommended as the preferred plan.

     Implementation of two-plant alternative requires the following actions:

     o  Upgrade the Jackson Pike WWTP to treat  an  average  flow  of 80 MCD and a
        peak process  flow of 100 MGD.
     o  Upgrade the Southerly WWTP  to treat an average flow of 74 MGD and a
        peak process  flow of 131 MGD.
     o  Complete the north end of the Interconnector Sewer to allow Jackson
        Pike flows to be  diverted to the Southerly WWTP when flows exceed 100
        MGD.
                                      XX

-------
           TABLE 5 ONE PLANT/TWO PLANT COMPARISON
CRITERION
PRESENT WORTH
COSTS
RELIABILITY
FLEXIBILITY
EASE OF
IMPLEMENTATION
EASE OF OPERATION
AND MAINTENANCE
SURFACE WATER
QUALITY
SURFACE WATER
FLOWS
AQUATIC BIOTA
ENDANGERED
SPECIES
ONE-PLANT




X




TWO-PLANT
X
X
X
X

X
X
X
X
X-
PREFERRED ALTERNATIVE
                          XXI

-------
      »   Construct  new  headworks at Jackson Pike rated at a capacity of 100 MGD
         which include  screening,  pumping,  and grit  removal.

      •   Modify the existing aeration basins at  each plant to operate in the
         semi-aerobic mode.

      •   Add  tvo new aeration basins to the existing Center Train at the
         Southerly  WWTP.

      •   Replace  the existing rectangular clarifiers at the Southerly with six
         new  circular clarifiers.

      •   Add  two  new rectangular clarifiers to the B Plant at Jackson Pike.

      •   Construct  chlonnation, dechlorination, and post aeration facilities
         at both  Jackson Pike and  Southerly.

      •   Modify the four existing  decant tanks at Southerly to be utilized as
         gravity thickeners.

      •   Construct  three new gravity  thickeners at Jackson Pxke.

      •   Add one new centrifuge for thickening at both Jackson Pike and
         Southerly.

      •   Rehabilitate the existing anaerobic digesters at both Jackson Pike and
         Southerly.

      •   Add  two  new dewatering centrifuges at Southerly.
     Solids disposal will be accomplished at Southerly in the following
manner:
     •  50 percent of the solids will be  incinerated and the ash landfilled.
        The two most recently installed incinerators will be utilized.  It is
        not recommended that the older incinerators be renovated.

     •  25 percent of the solids  will  be composted at  the  Southwesterly
        Composting Facility.  The compost will be marketed as a soil
        conditioner.

     •  25 percent of the solids will be land applied on nearby farmland.
     Solids disposal will be accomplished at Jackson Pike in the following
manner.
                                     XXli

-------
     •  50 percent of the solids will be incinerated and the ash landfilled.
        The two existing incinerators should be renovated.
     •  50 percent of the solids will be land applied on nearby farmland.

     The preferred plan does  not  incorporate measures to deal with  combined
sewer overflows.  A detailed CSO study LS required to determine a cost-
effective solution to CSO problems within the planning  area.
                                   xxiii

-------

-------
                              TABLE OF CONTENTS


                                                                         Page

EXECUTIVE SUMMARY 	    i

1.   PURPOSE AND NEED FOR ACTION	1-1

     1-1  PROJECT BACKGROUND  	  1-1

     1-2  PURPOSE AND NEED FOR PROJECT	1-6

     1-3  DECISION TO PREPARE A SUPPLEMENTAL EIS	1-7

     1-4  DESCRIPTION OF THE GRANT APPLICANT'S PROPOSED ACTION  ....  1-8

     1-5  ISSUES	1-9

     1-6  EIS PROCESS AND PUBLIC PARTICIPATION  	  1-12

2.   ENVIRONMENTAL SETTING  	  2-1

     2.1  NATURAL ENVIRONMENT 	  2-1

          2.1.1  Atmosphere	2-2
          2.1.2  Water	2-5
          2.1.3  Land	2-18
          2.1.4  Biota	2-23

     2.2  MAN-MADE ENVIRONMENT  	  2-54

          2.2.1  Income	2-55
          2.2.2  Public Service	  2-60
          2.2.3  Public Finance	2-74
          2.2.4  Cultural Resources ......... 	 ....  2-78

3.  EXISTING FACILITIES 	  3-1

     3.1  JACKSON PIKE WASTEWATER TREATMENT PLANT 	  3-1

          3.1.1   Major  Interceptors  	   3-1
          3.1.2  Preliminary Treatment (O.S.I.S.  Flows) 	  3-3
          3.1.3  Major Treatment Processes  ..............  3-3
          3.1.4  System Performance 	  3-5
          3.1.5  Present Condition of Plant 	  3-12
                                     xxiv

-------
                        TABLE OF CONTENTS (Continued)


                                                                         Page

     3.2  SOUTHERLY WASTEWATER TREATMENT PLANT  	  3-13

          3.2.1  Major Interceptors 	  3-13
          3.2.2  Interconnector Pump Station  	  3-14
          3.2.3  Treatment Processes  	  3-14
          3.2.4  System Performance 	  3-19
          3.2.5  Present Condition of Plant 	  3-26

     3.3  COMBINED SEWER OVERFLOWS  	  3-26

     3.4  SOUTHWESTERLY COMPOSTING FACILITY 	  3-30

4.  EVALUATION OF WASTEWATER MANAGEMENT DESIGN FACTORS  	  4-1

     4.1  PLANNING PERIOD	4-2

     4.2  POPULATION	4-2

          4.2.1  Existing Population  	  4-3
          4.2.2  Population Projections 	  4-5

     4.3  LAND USE PATTERNS	4-10

     4.4  WASTEWATER FLOWS AND LOADS	4-17

          4.4.1  Existing Wastewater Flows  	  4-17
          4.4.2  Existing Wastewater Loads	4-29
          4.4.3  Projected Flows and Loads	4-32
          4.4.4  Comparison of EIS and Facility Plan Flows and Loads  .  4-34

     4.5  COMBINED SEWER OVERFLOWS  	  4-37

5.  ALTERNATIVES	5-1

     5.1  COMPREHENSIVE WASTEWATER MANAGEMENT ALTERNATIVES  	  5-7

          5.1.1  No Action Alternative	5-7
          5.1.2  Upgrade Jackson Pike and Southerly, Provide Wet Stream
                 Treatment and Solids Handling at  Both Plants 	  5-8
          5.1.3  Upgrade Jackson Pike and Southerly, Provide All Solids
                 Handling at Southerly  	  5-9
          5.1.4  Eliminate Jackson Pike,  Upgrade and Expand Southerly .  5-9
                                     XXV

-------
                        TABLE OF CONTENTS (Continued)


                                                                         Page

     5.2  INTERCONNECTOR/HEADWORKS OPTIONS  	  5-9

          5.2.1  Interconnector	5-9
          5.2.2  Headworks	5-12

     5.3  BIOLOGICAL PROCESS OPTIONS  	  5-15

          5.3.1  Semi-Aerobic	5-16
          5.3.2  Trickling Filter Processes 	  5-19
          5.3.3  Conventional Activated Sludge  	  5-23

     5.4  SOLIDS HANDLING	5-27

          5.4.1  Sludge Production  	  5-27
          5.4.2  Unit Processes	5-30
          5.4.3  Sludge Management Options  	  5-39

     5.5  SUMMARY OF ALTERNATIVES AND OPTIONS 	  5-57

6.   DETAILED ANALYSIS OF ALTERNATIVES  	  6-1

     6.1  ENGINEERING EVALUATION  	  6-2

          6.1.1  Interconnector/Headworks Component 	  .  6-3
          6.1.2  Biological Process Component 	 .  	  6-6
          6.1.3  Solids Handling	6-10
          6.1.4  One-Plant vs. Two-Plants	6-15
          6.1.5  User Costs	6-28

     6.2  ENVIRONMENTAL CONSEQUENCES - PHYSICAL ENVIRONMENT 	  6-31

          6.2.1  Surface Water Quality  	  6-31
          6.2.2  Surface Water Flow	6-46
          6.2.3  Groundwater	6-50
          6.2.4  Air Quality/Odor	6-54
          6.2.5  Soils/Prime Agricultural Land  	  6-67

     6.3  ENVIRONMENTAL CONSEQUENCES - BIOLOGICAL ENVIRONMENT 	  6-69

          6.3.1  Terrestrial and Wetland Biota/Habitat  	  6-69
          6.3.2  Aquatic Biota/Habitat	6-73
          6.3.3  Endangered Species/Habitat 	  6-79
          6.3.4  Conclusions  	  .....  6-83
                                     XXVI

-------
                        TABLE OF CONTENTS (Continued)
     6.4  ENVIRONMENTAL CONSEQUENCES - HUMAN ENVIRONMENT  	  6-85

          6.4.1  Planning and Land Use	6-85
          6.4.2  Noise	6-86
          6.4.3  Public Health	6-87
          6.4.4  Energy Use	6-88
          6.4.5  Economics and Employment	6-88
          6.4.6  Historic/Archaeologic Resources  	  6-89
          6.4.7  Recreation	6-90
          6.4.8  Transportation	6-91
          6.4.9  Conclusions	6-92

     6.5  ENVIRONMENTAL CONSEQUENCES - SECONDARY IMPACTS/INDUCED GROWTH  6-93

          6.5.1  Secondary Impacts:  Growth and Development 	  6-93
          6.5.2  Secondary Impacts:  Air Quality/Climate  	  6-96
          6.5.3  Secondary Impacts:  Water Quality  	  6-100
          6.5.4  Secondary Impacts:  Community Facilities 	  6-103
          6.5.5  Conclusions	6-111

     6,6  CONCLUSIONS ON ALTERNATIVES	6-112

7.  PREFERRED PLAN	   7-1

     7.1  DETAILED DESCRIPTION OF PREFERRED PLAN	7-1

          7.1.1  Interconnector/Headworks 	  7-1
          7.1.2  Wet  Stream Treatment	7-5
          7.1.3  Sludge Management	  7-6

     7.2  IMPACTS OF  THE PREFERRED PLAN	7-14

          7.2.1  Financial Impacts	7-14
          7.2.2  Environmental Impacts	7-14

     7.3  COMBINED SEWER OVERFLOW 	  7-29
                                    XXVI1

-------
                        TABLE OF CONTENTS (Continued)
INDEX

REFERENCES

APPENDIX A - BRIEFING PAPER NO. 1 - WASTEWATER FLOWS AND LOADS

APPENDIX B - BRIEFING PAPER NO. 2 - SOLIDS HANDLING

APPENDIX C - BRIEFING PAPER NO. 3 - BIOLOGICAL PROCESS SELECTION

APPENDIX D - BRIEFING PAPER NO. 4 - O&M AND CAPITAL COSTS

APPENDIX E - BRIEFING PAPER NO. 5 - COMBINED SEWER OVERFLOWS

APPENDIX F - BRIEFING PAPER NO. 6 - ONE-PLANT VS. TWO-PLANT

APPENDIX G - GRAPHS OF STORET DATA FOR DO, BOD, AND AMMONIA

APPENDIX II - TABLES OF ENDANGERED SPECIES

APPENDIX I - SITES AND STRUCTURES IN THE COLUMBUS AREA LISTED ON
             THE NATIONAL REGISTER OF HISTORIC PLACES

APPENDIX J - ARCHAEOLOGIC BACKGROUND

APPENDIX K - POPULATION PROJECTIONS AND METHODS

APPENDIX L - DRAFT CRITIQUE OF WATER QUALITY MODELING ISSUES

APPENDIX M - USEPA, WATER QUALITY BRANCH, MEMORANDUM ON COLUMBUS
             WATER QUALITY MODEL

APPENDIX N - THE INFRASTRUCTURE PROJECT 1985 - 1986
             FINAL REPORT:  EXECUTIVE SUMMARY

APPENDIX 0 - SEIS DISTRIBUTION LIST
                                    XXV 111

-------
                               LIST OF FIGURES


Figure                                                                  Page

1-1   Planning Area	1-2

2-1   General Soil Map of Franklin County, Ohio	2-21

2-2   Comparison of Segment Mean Composite Index Values of the
      Middle Scioto River Mains tern	2-27

2-3   Composition of the Fish Community by Number in the Central
      Scioto  River  Mainstem	  2-34

2-4   Composition of the Fish Community by Weight in the Central
      Scioto River Mainstem	   2-35

2-5   Longitudinal Trend of the Mean (and Standard Error) Composite
      Index in the Central Scioto River Mainstem   	   2-37

2-6   Longitudinal Trend of the Mean C^SE) Number of Species/Zone
      in the Central Scioto River Mainstem	   2-38

2-7   Comparison of Mean (and Standard Error) Composite Index Values .   2-39

2-8   Number of Benthic Macroinvertebrate Taxa	  2-49

2-9   Columbus Water System  	  .............   2-64

2-10  Sewer Truck Design vs. Industrial Park  Sites 	   2-66

2-11  School District  Boundaries 	   2-71

3-1   Columbus Metropolitan Area Interceptors and Treatment  Facilities   3-2

3-2   North End Interconnector   	3-4

3-3   Jackson Pike WWTP Flow Schematic	3-6

3-4   South End Interconnector	3-15

3-5   Southerly WWTP Flow Schematic	3-16

3-6   Location of Combined Sewer Overflows 	   3-29
                                     xxix

-------
                         LIST OF FIGURES (Continued)






Figure                                                                  Page




4-1   Planning and Service Area Boundaries	4-9




4-2   Water Service Areas  	  4-12




4-3   High Growth Areas	4-16




4-4   Diurnal Flow Variations	4-25




4-5   Diurnal Flow Variations for Dry Weather	  4-27




5-1   South End Interconnected Option A	  5-11




5-2   South End Interconnector Option B  	 .......  5-13




5-3   Semi-Aerobic Process 	  5-17




5-4   Semi-Aerobic Process Modes of Operation  	  5-18




5-5   Trickling Filter/Activated Sludge  	  5-21




5-6   Trickling Filter/Solids Contact  	  5-22




5-7   Single-stage Activated Sludge  	  5-24




5-8   Two-Stage Activated Sludge   	  5-26




5-9   Jackson Pike Existing Sludge Management Schematic  	  5-28




5-10  Southerly Existing Sludge Management Schematic .... 	  5-29




5-11  Jackson Pike Option JP-A Sludge Management Schematic 	  5-41




5-12  Jackson Pike Option JP-B Sludge Management Schematic 	  5-43




5-13  Jackson Pike Option JP-C Sludge Management Schematic 	  5-45




5-14  Southerly Option SO-A Sludge Management Schematic  . 	  5-47




5-15  Southerly Option SO-8 Sludge Management Schematic  	  5-48




5-16  Southerly Option SO-C Sludge Management Schematic  	  5-50




5-17  Southerly Option SO-D Sludge Management Schematic  	  5-52
                                     xxx

-------
                         LIST OF FIGURES (Continued)






Figure                                                                  Page




5-18  Southerly Option SO-E Sludge Management Schematic  	  5-54




5-19  Southerly Option SO-F Sludge Management Schematic  .......  5-56




6-1   Southerly One-Plant Site Layout	6-17




6-2   Southerly Two-Plant Site Layout  	  6-20




6-3   Jackson Pike Two-Plant Site Layout	6-24




6-4   Non-Attainment Areas for Total Suspended Participates  	  6-58




6-5   Locations of Potential Odor Sources in Southern Franklin County   6-62




7-1   Reconmended Plan Flow Schematic	   7-2




7-2   Jackson Pike WWTP Flow Schematic	   7-3




7-3   Southerly WWTP Flow Schematic	   7-4
                                    XXXI

-------
                                LIST OF TABLES


Table                                                                  Page

1     NPDES Final Effluent Limits Jackson Pike WWTP  	   lii

2     NPDES Final Effluent Limits Southerly WWTP 	   iv

3     Summary of Alternatives and Options  	 ...   ix

4     Alternative Cost Summary 	   xiv

5     One-Plant/Two-Plant Comparison 	   xx

2-1   Selected Climatologies! Data for Columbus, Ohio  	   2-3

2-2   USEPA & Ohio EPA Ambient Air Quality Standards	   2-4

2-3   Air Quality Data for the Franklin County Local Area  	   2-6

2-4   Noteworthy Natural Terrestrial Areas 	  . 	   2-23

2-5   Location and Description of the Six River Segments	   2-28

2-6   Overall Composition of the Fish Community in the Central
      Scioto  River Mainstem  	   2-30,  31

2-7   Species Group Designations Used to Assess Community
      Composition Patterns in the Mainstem Scioto River and
      Major Tributaries	   2-32

2-8   Metrics and Numerical Rankings Used in the Index of
      Biotic Integrity 	   2-41

2-9   Index of Biotic Integrity (IBI) Scores for the Scioto River
      Mainstem	   2-42

2-10  Incidence of Lesions, Tumors,  Fin Erosion, and External
      Parasites Among Individual Fish Collected in Six Segments
      of the  Scioto  River  	    2-45

2-11  Industries of Franklin County (1982) 	   2-57

2-12  Columbus MSA Employment (1978-1983) Trends 	   2-58

2-13  Per Capita Income Levels for the Columbus MSA	   2-59

2-14  Per Capita Taxes by County	   2-75
                                   xxxii

-------
                           LIST OF  TABLES  (Continued)


 Table                                                                  Page

 2-15   Columbus  Annexations Since 1986   	   2-76

 3-1    Jackson Pike  Existing Facilities  	   3-7, 8

 3-2    1985 Operating Data  Jackson  Pike  WWTP	   3-9

 3-3    Jackson Pike  WWTP  1985 Performance  Data	   3-10

 3-4    Jackson Pike  WWTP  Nitrification Data -  1985	   3-11

 3-5    Southerly WWTP Existing  Facilities  	   3-17, 18

 3-6    Southerly WWTP 1985  Operating Data	   3-20

 3-7    Southerly WWTP 1985  Performance Data	   3-21

 3-8    Southerly WWTP Nitrification Data - 1985	   3-22

 3-9    Southerly WWTP Flow  Data	   3-25

 3-10   Summary of Bypass  and CSO Locations in  the Columbus
       Planning  Area ...............  	   3-28

 3-11   Southwesterly Compost Facility Operating Data  	   3-33

 4-1    I960 Demographic Profile  for the  Columbus Area	   4-4

 4-2    Population and Per Capita Income  by Political Subdivision  . .   4-6

 4-3    Population Projections for the State of Ohio and the Counties
       in the Columbus Service Area	   4-7

 4-4    Population Projections for Columbus  	   4-8

 4-5    Municipalities and Other Entities that have Sewer Service
       Contracts with Columbus  ...................   4-11

 4-6    Residential Plats by Municipality or Township, 1980-1982,
       Franklin County  	 ..... 	   4-14

4-7    1985 Water Pumpage vs. Wastewater Flow	   4-21

4-8    Industrial and Commercial Flow Estimates 	   4-24
                                    XXXI11

-------
                          LIST OF TABLES (Continued)


Table                                                                  Page

4-9   1985 Estimated Flow	   4-24

4-10  1985 and 1986 BOD and TSS Loads	   4-31

4-11  1985 Flows and Loads	 .   4-32

4-12  1985 Per Capita/Connection Flows and Loads	   4-33

4-13  1988 Projections	   4-35

4-14  2008 Projections	   4-35

4-15  Comparison of Design Flows and Loads 	 ......   4-36

4-16  2008 Recommended Flows and Loads	   4-37

5-1   Solids Analysis	   5-31

5-2   Summary of Alternatives and Options  .............   5-58

6-1   Interconnector/Headworks Costs 	 . 	   6-4

6-2   One-Plant Biological Process Costs 	   6-8

6-3   Two-Plant Biological Process Costs 	   6-9

6-4   Cost Comparison of Sludge Management Options
      (Southerly One-Plant)  	   6-12

6-5   Cost Comparison of Sludge Management Options
      (Southerly Two-Plant)  	   6-13

6-6   Cost Comparison of Sludge Management Options
      (Jackson Pike Two-Plant) 	   6-13

6-7   Southerly One-Plant Required Facilities  	   6-18, 19

6-8   Southerly Two-Plant Required Facilities  	   6-21, 22

6-9   Jackson Pike Two-Plant Required Facilities 	   6-25, 26

6-10  Alternative Cost Summary	   6-23

6-11  Service Charge Estimates 	   6-29
                                   XXXIV

-------
                          LIST OP TABLES (Continued)


Table                                                                  Page

6-12  Median Family Income for the United States,  Ohio,
      Franklin County, and Columbus in 1969 - 1979	    6-30

6-13   Mitigation on Sewer Line (Interconnector)  	    6-42, 43, 44

6-14  Surface Water flows in the Olentangy and Scioto  Rivers at
      Columbus, Ohio	    6-49

6-15a Estimates of Pollutants Generated Per Ton of Sludge
      Incinerated	    6-55

6-L5b Projected Air Pollutant Emissions Associated with  the
      No Action Alternative	    6-55

6-15c Projected Air Pollutant Emissions Associated with  the
      Two-Plant Alternative  	    6-56

6-15d Projected Air Pollutant Emissions Associated with  the
      One-Plant Alternative  	    6-56

6-16  Potential Odor Sources in Southern Franklin  County, Ohio  .  .  *    6-59, 60, 61

6-17  Annexations that have Occurred in Columbus 1984-1986 	    6-97

6-18  Current and Projected Levels  of Total Suspended
      Particulates Due to Population Growth  	    6-98, 99

6-19  Percent Improvements by Site  Category  	    6-99
                                                                           (
6-20  Current Levels of Service  	    6-107

6-21  School District  Information 1985-1987  	   6-109

6-22  One-Plant/Two-Plant Impacts  Comparison 	    6-113,  114, 115

6-23  One-Plant/Two-Plant Comparison 	    6-116

7-1   Jackson Pike Wet Stream Process Design Criteria  .......    7-7, 8

7-2   Southerly Wet Stream Process  Design Criteria .........    7-9, 10

7-3   Jackson Pike Solids Handling  Design Criteria 	    7-12

7-4   Southerly Solids Handling Design Criteria  	    7-13
                                    xxxv

-------
                              LIST OP FRBPARERS

     This Draft Environmental Impact Statement (SEIS) is published by the
Environmental  Impact Unit of the U.S.  Environmental Protection Agency (USEPA),
Region V.  The Draft Environmental Statement (DBS) which forms  the basis of
this SEIS was  prepared under contract  to USEPA by Science Applications
International  Corporation (SAIC), McLean, Virginia, and Triad Engineering
Incorporated,  Milwaukee,  Wisconsin.  Staff from USEPA,  SAIC, and Triad
Engineering involved in preparation of  the DES/DEIS included:
U.S. Environmental Portection Agency
Rita Bair
Dale Luecht
Project Monitor
Chief, Environmental Impact Unit
Science Applications International Corporation
Geoffrey Kay
Carl Mitchell
Hunter Loftin
Candy Bartoldus
Margaret Kerr
Cindy Hughes
Marlene Stern
Dennis Borum
Dorothy LaRusso
David Hair
Teresa Dowd
April Hood
Audrey Knight
Kim Finch
Debbie Ryan
Alena Motyka
Tricia Codd
Project Administrator, Biologist
Planner
Hydrologist
Biologist
Biologist
Editor
Biologist
Bibliographer, Editor
Transportation Analyst
Civil Engineer
Planner, Socioeconomist
Planner, Socioeconomist
Planner, Socioeconoraist
Planner, Socioeconomist
Air Quality Analyst
Information Specialist
Project Coordinator
                                   xxxv i

-------
Triad Engineering Incorporated
Thomas Meinholz
Rick Fulk
Michael Sylvester
£d Manning
Renee Beggan
Mark Miller
Steve Lepak
Tom Robak
Project Manager, Senior Engineer
Senior Engineer
Senior Engineer
Senior Engineer
Project Engineer
Planner, Editor
Project Engineer
Project Engineer
                                   xxxvii

-------
                   CHAPTER 1.  PURPOSE AND NEED FOR ACTION

1.1  PROJECT BACKGROUND
     This Supplement Environmental Impact Statement  (SEIS) addresses plans
submitted by the city of Columbus,  Ohio,  to  meet wastewater treatment needs in
the Columbus Facilities  Planning Area  (FPA).  The planning area includes
essentially all of Franklin County and portions of surrounding counties.   The
planning area boundaries were reconfirmed by the Ohio Environmental Protection
Agency (EPA) in a  letter  to the  city  of Columbus on October 23,  1986.   This
approved planning area is depicted in Figure 1-1.

     The city of Columbus,  owns  and operates two  major wastewater treatment
facilities.   The Jackson Pike Wastewater Treatment Plant (WWTP) in southwest
Columbus was constructed in the late 1930's  with an original hydraulic design
capacity of approximately  115 MGD.  The Southerly WWTP  is  located 8.5  miles
south of downtown Columbus.  The Southerly plant was  constructed  in 1967 with
a hydraulic design capacity of 100 MGD.  Both  of these plants discharge to the
Scioto River.

     Formal facilities planning for the Columbus metropolitan area was
initiated on October 3, 1974,  when  the  city  contracted with Malcolm Pirnie,
Inc.,  for preparation of  a  facilities plan.  On  December 12,  1974,  a Step  1
grant application to request Federal Funds to  conduct planning and a plan  of
study were submitted  to  the Ohio EPA.  The plan of study was subsequently
approved, and a grant was made  to the city by USEPA on September 23, 1975.

     In 1976,  the city of Columbus  prepared  the  Columbus Metropolitan
Facilities Plan for wastewater management up to the year 1995.  The 1976
facilities plan concluded that the  most cost-effective solution to improved
wastewater treatment was rehabilitation and expansion of both Jackson  Pike and
Southerly wastewater treamtent  plants.  Since then, the  following studies  and
reports on the  Columbus,  Ohio, wastewater treatment system have been prepared:
                                     1-1

-------
JACKSON PIKE WWTP

SOUTHERLY WWTP
APPROXIMATE SCALE' 1  INCH - 4.12 MILES
SOUTHWESTERLY COMPOST FACILITY
PLANNING AREA BOUNDARY  -
                          FIGURE 1-1
                          PLANNING  AREA

-------
     •  USEPA Environmental Impact Statement Reports

        - Draft Environmental Impact Statement (EIS) - February 1978

        - Evaluation of the Wastewater Treatment Process Proposed for
          Columbus, Ohio, in the Draft EIS - July 1978

        - Final EIS - June 1979

     •  USEPA - Advanced Waste Treatment Task Force Review - 1979

     •  Columbus Metropolitan Area Facilities Plan Update prepared in the
        following segments:

        Segment 1 - Interim Solids Handling Facilities - 1980
        Segment 2 - Long-term Solids Handling Facilities - 1982
        Segment 4 - Combined Sewer Overflow - 1983
        Segment 5 - Blacklick Interceptor - 1981

     •  Design Finalization Overview Team (DFOT) Review Report - May 1984

     •  Columbus Metropolitan Area Facilities Plan Update Report - December
        1984

     »  Draft Central Scioto River Mainstem Comprehensive Water Quality Report
        August 1983 - (Revised February 1985)

     •  Revised Facilities Plan Update - September 1985

     •  Municipal Compliance Plan -  September 1985


     After reviewing the original facilities plan, the USEPA initiated

preparation of an EIS.  The 1979 Final EIS contained recommendations  for  wet

stream treatment and solids handling that  differed  from the  recommendations of

the original facilities plan.   It  primarily focused on the selection of

additional mainstream treatment and solids handling facilities at Jackson Pike
and Southerly WWTP's  as well as  construction of  separate  sanitary  sewer

interceptors within the Columbus planning area.   The 1979 EIS made the
following recommendations:


     •  Completion of the Interconnector Sewer between the Jackson Pike WWTP
        and Southerly WWTP.
                                     1-3

-------
     •  Installation of facilities for the addition of metal salt coagulant to
        the raw wastewater and  the influent to the clanfiers for phosphorus
        removal  flexibility at  the Southerly  and  Jackson  Pike plants.

     •  Utilization of a two-stage wastewater treatment concept which includes
        trickling filters  followed by activated sludge at the Jackson Pike
        plant.

     •  Continued use of the single-stage activated sludge process at the
        Southerly plant.

     •  Pretreatraent and regulation of brewery flows.

     •  Effluent filters,  that are capable of treating 80 to 85 percent of the
        hydraulic capacity, at  each plant,

     •  Expansion of the chlorine disinfection capacity and addition of post
        aeration and declorination processes at Jackson Pike and Southerly.

     •  Optimum utilization of existing sludge handling facilities,  two
        operable sludge incinerators  at each plant,  and additional  dewatenng
        equipment.

     •  Investigation and  implementation of alternatives to incineration.


     Based on future flexibility considerations and  dissatisfaction with the

performance of the thermal  conditioners, the 1979  EIS included a recommenda-

tion for continued testing  of a  chemical conditioning-belt press system as a

possible alternative for the production of an autogenous sludge  cake.   It was

stated that thermal conditioning could  be abandoned  in favor of  this new

method in the future depending on advances in belt press dewatering

technology.


     The 1979 EIS did not recommend completing  the  sludge line.  Blather, it
was recommended in the EIS  that additional facility planning be  conducted to

evaluate alternative solids handling  options.   The alternatives  suggested by
the EIS included  strip  mine reclamation projects,  composting,  and land

application.   Upon implementation of an alternative disposal technique,
incineration would become  a backup system.
                                      1-4

-------
     The 1979 EIS evaluated 11 subareas for connection to the Columbus sewer
system.  Only 3 (Minerva Park, Blacklick, and Rocky Fork) had a documented
need for sewer service.  The EIS recommended  that additional facility planning
was required in the remaining 8 subareas to establish the need for regional
sewers  during  the  planning period.

     In order to address the differences in design parameters between the
Draft EIS and original facilities plan, USEPA in the Final EIS required that
Columbus establish a Design Finalization Overview Team  (DFOT) "as a separate
but integral part of the  Value Engineering Team  to review and  recommend the
final design parameters  of both plants."  AWARE, Inc.,  was selected as the
DFOT by the city in 1982 and the report was completed in May  1984.  On July 9,
1984, the city submitted a Plan of Study which set the groundwork for a
facilities plan update.   The DFOT Report was not  formally reviewed by USEPA or
OEPA, since significant changes  were proposed in the Plan of Study for a
Facilities Plan Update.

     Approximately 9 years have passed since completion of the original
facilities plan with little implementation of the 1979 EIS recommendations.
Deterioration of the concrete structures and other facilities  at the Jackson
Pike WWTP has occurred during this  time.   (O&M at Jackson Pike  was a concern
in the late 1970's.)  Recently, the city decided  to  reevaluate  the facilities
plan and introduced the Columbus  Metropolitan Area Facilities  Plan Update
Report,  December 1984, as  an update to the original facilities plan.   This
plan represents the first time that a single wastewater  treatment plant
alternative for Columbus  was proposed.

     The Revised Facilities Plan Update Report (RFPU),  September 1985,
supplements the Facilities Plan Update Report (FPU)  and  related facilities
planning documents.  The specific objectives of the RFPU were:  (1) to revise
the recommendations of previous  documents based upon revised design parameters
and NPDES permit limits;  (2) to  present the  conclusions  and  recommendations of
                                      1-5

-------
 planning  analyses undertaken since completion of the FPU; (3) to respond to
 comments by the OEPA relative  to  the  FPU; and (4) to develop treatment
 facilities which would serve the city's needs through the year 2015.

 1.2  PURPOSE AND NEED FOR PROJECT
     As with most major metropolitan  areas, Columbus has experienced a wide
 range of air,  water, and land pollution control  problems.  Columbus is
 increasingly looking toward its natural resources for recreation and an
 improved  quality of  life.  One area of concern to citizens and local officials
 is the resolution of environmental problems relating to  wastewater management.
 The most significant concern centers on water quality.

     The quality of the Scioto River is impacted by the  effluent from the  two
 treatment plants and combined  sewer overflows (CSO).  Currently, the effluent
 from Jackson Pike and Southerly does not meet ammonia and BOD standards set by
 their respective National Pollutant Discharge Elimination System (NPDES)
 permits.  In addition,  during periods  of wet weather (high groundwater
 resulting from rain or snow melt)  clear water enters the sanitary system and
 is conveyed to the treatment plant.  The Jackson Pike and Southerly  WWTPs  are
 unable to treat the increased flow and bypass it directly to the Scioto River.

     In order to reduce the overloading of the system, overflow points were
established in the combined sewer  area where both sanitary and  stormwater  are
collected in the same pipe.  During periods  of wet weather these combined
 sewer overflows discharge untreated wastewater directly to the Scioto River.
According to the 1979 EIS, this can occur up to  SO  times a year.

     Finally,  the most significant need for  action relates to  the Clean Water
Act which currently mandates that  all  wastewater treatment facilities be in
compliance with NPDES permit limits by July  1, 1988.
                                     1-6

-------
1.3  DECISION TO PREPARE A SUPPLEMENTAL EIS
     USEPA is required to prepare a supplemental EIS in accordance with 40 CFR
1502.9(c) which states:

     (c)  Agencies
     (1)  Shall prepare supplements to either draft or final environmental
          impact statements if:
          (i)  The agency makes  substantial changes ^n the proposed action
               that are relevant to environmental concerns;  or
         (li)  There are significant new circumstances or information relevant
               to environmental concerns and bearing on the  proposed action or
               its impacts.
          (2)  May also prepare supplements when the agency  determines that
               the purposes of the Act will be furthered by  doing so.
          (3)  Shall adopt procedures for introducing a supplement into its
               formal administrative record, if such a record exists.
          (4)  Shall prepare,  circulate,  and file a  supplement  in the  same
               fashion (exclusive of scoping)  as a draft  and  final  statement
               unless alternative procedures are approved by the Council.

     Given that the Columbus project involved 1) substantial changes in the
proposed action and possible significant  environmental impacts  associated  with
those changes;  and  2) new  information which raises  substantial  concerns not
addressed in the original EIS,  it was reasonable and prudent for USEPA to
proceed with the preparation of a supplemental EIS.

     Federal funding for wastewater treatment projects is provided under
Title II of the Federal Water Pollution Control Act.  The dispersal of
Federal funds to local applicants or communities is  made via the Municipal
Wastewater Treatment Works Construction Grants Program administered by USEPA.
If a community chooses to construct a wastewater collection  and treatment
system with USEPA grant assistance, the project  must meet all applicable
requirements of the Grants Program.  The Clean Water Act (CWA)  stresses that
the most cost-effective alternative is the  one that will  result  in minimum
                                     1-7

-------
 total resource costs over the life of the project,  as  well as meet federal,
 state, and local requirements.  Nonmonetary costs also must be considered,
 including social and environmental factors.  The analysis for choosing the
 cost-effective alternative is based on both capital costs and operation and
 maintenance costs  for a 20-year period.  Selection  of  the most cost-effective
 alternative must also consider social and environmental implications  of the
 alternative.  An alternative  with higher monetary costs but lesser social and
 environmental impacts may be selected over an alternative that has low
 monetary costs but undesireable environmental impacts.

 1.4  DESCRIPTION OF THE GRANT APPLICANT'S PROPOSED  ACTION
     The proposal by the applicant,  the city of Columbus,  for  wastewater
 treatment was submitted as the 1985 Revised Facilities Plan Update (RFPU) and
 includes the following major elements:

     •  The Jackson Pike Wastewater Treatment Plant (WWTP) would be phased out
        of service by 1993, with  flows transported  to  the  Southerly WWTP
        through the completion of the existing Interconnector Sewer.
     •  The Southerly Wastewater Treatment Plant would be enlarged to treat
        all wastewater flow  from  the service  area  until  the year 2015.
     •  The design average wastewater flow is 178 MGD  with a peak process flow
        of 300 MGD.  Wastewater flows in excess of  300 MGD would be settled
        and chlorinated  prior to discharge.  Peak flow of  up to 430 MGD  may  be
        generated from a CSO control  program.
     •  The proposed treatment facilities would  use a  semi-aerobic process.
     •  The disposal of solids would be through composting and land
        application,  with incineration as back-up.

     The RFPU proposes to divert  wastewater flows from Jackson Pike to
Southerly via completion of  the north end of the  Interconnector  Sewer and
modification at the south end. They  also propose to abandon  the  existing pump
station and force main at the south end of the Interconnector and replace it
with a 156-inch diameter gravity interceptor to the Southerly WWTP.  The
                                      1-8

-------
gravity crossing of the Scioto River would consist of  four 78-inch parallel
lines placed beneath  the  river  bed.

     The 1985 RFPU recommends that the Jackson Pike Wastewater Treatment Plant
would be abandoned in the early 1990's  and wastewater flows be conveyed to an
expanded and upgraded Southerly paint  for treatment  and  discharge.

     The RFPU also states that  combined sewer overflow control is not
warranted based upon water  quality modeling  and sampling results.  As required
in the NPDES Permit, the city intends to continue to monitor overflows.

     The RFPU also proposes abandoning the existing headworks at Southerly and
replacing it with a new headworks designed for a  peak hydraulic  flow of
430 MGD and peak process flow of 300 MGD.

     Composting and land application are proposed  as  the  primary methods of
solids disposal although incineration facilities  would be maintained for
contingency puposes.

1.5  ISSUES
     During the review of the Revised Facilities Plan Update,  a  number of
possible significant environmental impacts were addressed.  These issues were
the subject of USEPA's action to issue a Notice of Intent (June  11,  1986).
The environmental impacts that were identified include:
        Impacts expected from the fulfillment of the population projections
        and development for the planning area.
        The reliability of the Southerly WWTP needs to be evaluated in the EIS
        process.   (The ability of Southerly to meet  its NPDES limits  was a
        major concern in the original EIS due to the unique problems it has
        experienced from the Anheuser-Busch (AB) BOD loadings).   An analysis
        needs to be done to verify the reliability of the currently proposed
        treatment process to effective meet NPDES limits.
                                      1-9

-------
     •  The concerns about the water quality and stream use impacts related to
        a one-plant discharge and other upstream and downstream impacts.

     •  The alternatives for environmentally acceptable sludge treatment  and
        disposal.

     *  The induced growth and secondary environmental effects of an expanded
        Southerly WWTP.

     •  The cost-effective treatment of combined sewer overflow as an integral
        part of the system.


     The RFPU covered a. 30-year planning period (1985-2015),  however, federal

regulations require a LFSEPA review and cost-effective decision based upon a

20-year planning period.  Within the city's  30-year  planning  period,  four
phases were contemplated.


     Phase 1:   Upgrade Jackson Pike and Southerly treatment plants in order to
               meet Clean Water Act requirements of  permit  compliance by
               July 1,  1988.   These  components  are detailed in the  Municipal
               Compliance Plan with a construction schedule.   The  proposed
               improvements were estimated  to  cost  $147,241,718.   A list  of
               these improvements  is provided below.

                    Southerly WWTP                Jackson Pike WWTP

                    Sitework                      Aeration  Tanks
                    Preaeration                   Chlorine  Tanks
                    Primary Settling
                    Aeration Tanks
                    Secondary Settling            Interconnector
                    Effluent Filters*
                    Chlorine Tanks                Interconnector  (North Segment)
                    Dilution Water Pumps
                    Gravity Thickeners
                    Dewatering Centrifuges
                    Sludge Cake Storage
                    Lime Stabilization
                    Primary Electrical Dist.
                    I&C

                    deleted from the plan

     Phase 2:   The improvements required during this phase are needed to  stay in
               compliance.   The city's  recommendation calls  for abandoning Jackson
               Pike with its replacement of capacity at Southerly by 1993.
                                     1-10

-------
     Phase 3:  This phase addresses facilities and sizing to accommodate
               combined sewer overflows.
     Phase 4:  If population projections increase as expected, additional
               capacity and interceptors will be needed at Southerly beginning
               in 2000.  This phase addresses facilities needed for this
               growth.

     USEPA has prepared this SEIS based on  facilities  that existed as of  1985.
This base was used since the completed NEPA  review in 1979 recommends
different conclusions than  the 1985 Revised Facilities Plan Update.   The
planning period used is 1988 - 2008.   The USEPA  review was conducted as  it
would have been had the city sought Federal  review and compliance with NEPA
prior to undertaking the construction in 1986.   Although the  city was required
to attain NPDES permit limits by 1988,  that requirement does not change the
base for analysis under the Construction Grants Program.

     This SEIS will not refer to the Columbus project phases since the city
has not completed facilities planning  for  their  Phases 3 and  4,  but  will
emphasize the facilities required for a 20-year  solution of wastewater
treatment needs.   With this as a given the scope of  this  SEIS was limited to
the 20-year needs of the Columbus FPA without design for CSO capacity of
future interceptors.   USEPA's analysis  determined  the cost-effective
alternative for treating dry weather flows to identify potential grant awards
consistent with the proposed facilities.

     During the development of this SEIS including data gathering on the
facilities plan update,  USEPA has funded two grant  requests which were
consistent with the 1979 EIS.  Both of these actions  were reaffirmations which
determined that those facilities were consistent with the cost-effective
two-plant alternative as identified by  the 1979 EIS.  These actions approved:  1)
construction at Southerly of 3000  feet of  interceptor sewer (north end
Interconnector) between the existing Jackson Pike  and Southerly treatment
plants,  along with construction at Southerly of chlorine contact tanks,
dechlorination, and post aeration facilities (1986); and 2)  rehabilitation at
                                     1-11

-------
Southerly of the existing grit removal and primary settling tanks,  new final
clarifiers, instrumentation and control for both the final clarifiers and
existing aeration tanks,  and  necessary  site  restoration  (1987).

1.6  EIS PROCESS AND PUBLIC PARTICIPATION
     On July 22, 1986,  the USEPA held  two sessions of the Scoping Heeting in
Columbus after the decision to prepare a  supplemental EIS was annouced in the
Notice of Intent of June 11, 1986.   The  Scoping Heeting,  which was  advertised
to the general public and public officials, was held to gather public input in
developing the scope of issues to be addressed in the EIS.  This draft SEIS is
being circulated for public comment (the distribution list for the  draft SEIS
is contained in Appendix 0).  A public hearing is scheduled for USEPA to
receive comments in person on the draft  SEIS.   Following the close  of a 45-day
comment period, the final SEIS will be prepared which will incorporate the
results of public input on the draft SEIS.  The initial mailing lists,  any
additional requestors,  and those who will comment on this SEIS will receive
copies.  After a comment period following the  final SEIS,  USEPA will issue a
Record of Decision (ROD) identifying the  cost-effective,  environmentally
sound alternative for the  Columbus  FPA.   This  ROD will then form the basis for
any funding decisions by  the USEPA.
                                     1-12

-------
                           2.   ENVIRONMENTAL SETTING

     The environmental setting, for purposes of description and analysis, can
be defined as the natural environment and the man-made environment.  The
natural environment includes the land and underlying geologic structure; the
air, water, and mineral resources; and the naturally occurring vegetation and
animal life.  The man-made environment includes the structures man has built
for shelter, transportation, industry, commerce, and recreation.  In
describing the man-made environment certain characteristics are important,
such as:  land use patterns, demographic and economic characteristics, the
exploitation of natural resources, and the degradation of air and water
quality that has been encouraged by technology, urbanization, and an
aggressive attitude toward the natural environment.  The presentation of land
use patterns and demographic characteristics are presented in Chapter 4 as
design criteria.  The following discussions present more of the conditions of
the environment at the onset of this review.

2.1  NATURAL ENVIRONMENT
     Located in central Ohio, the study area includes the city of Columbus,
Ohio; most of the 552 square mile area of Franklin County, including numerous
satellite communities; and a portion of Delaware County near the Hoover
reservoir.  Columbus, the capital of Ohio and a major commercial and
industrial center, is located in the central portion of the county.  This
urban area accounts for 20 percent of Franklin County and contains over
one-half of the Scioto River Basin population.  The remaining, primarily
rural, land is utilized mainly for agriculture, including the grazing of
cattle.

     In this section, the following characteristics are described:

     •  Atmosphere
     •  Water
     •  Land
     •  Biota.
                                     2-1

-------
2.1.1  Atmosphere
2.1.1.1  Climate
     The climate of Franklin County may be characterized as continental.  The
region is subject  to invasions of continental, polar air masses from central
and northwest Canada during winter, and tropical, Gulf air masses in summer
and occasionally in fall and winter.  Precipitation is abundant, about
37 inches, and is distributed rather evenly throughout the year.  The maximum
monthly precipitation total was 10.7 inches and the greatest 24-hour rainfall
rate was 4.8 inches.  The snow season lasts from December through February,
with 5 to 7 inches falling during each of these months.  Annual snowfall
totals average 28 inches, but have varied from 5 to 47 inches.  The maximum
amount to fall in one month was 29 inches.

     Winds, for the most part, are from the south-southwest at 9 mph, with a
high frequency of calms or low wind speeds.  Wind direction frequency varies
considerably throughout the year, as evidenced by the frequently changing
weather patterns.  Damaging winds and local flooding sometimes occur during
thundershowers.  An average of 42 thunderstorms occur during the year, most
frequently during the late spring and summer months.  Additional climate data
is provided in Table 2-1.

2.1.1.2  Air Quality
     The city of Columbus lies within the Metropolitan Columbus Intrastate Air
Quality Control Region (AQCR) as designated by USEPA.  The region is subject
to National Ambient Air Quality Standards (NAAQS) and to standards imposed by
the State of Ohio Environmental Protection Agency (Ohio EPA has designated
standards identical to the NAAQS).  These standards are listed in Table 2-2.

     Areas where the NAAQS are not being attained are designated non-
attainment areas.  In such areas, the State is required to develop permit
requirements which will bring the area into compliance with the NAAQS.
Specifically, new or modified sources locating in these regions must obtain a
high degree of emission control and obtain emission reductions, offsets, or
tradeoffs for problem pollutants.  Currently,  portions of Columbus are
designated non-attainment for total suspended particulates.
                                     2-2

-------
                                 TAKE 2-1.  S1ECIH) aJM&OLOGICAL DKEA R» OOmfflUS, OHIO
Precipitation in Inches
Water Equivalent
Month
(Yrs. in Record)

J
F
M
A
M
J
J
A
S
0
N
D
TR

Normal
(97)
2.87
2.32
3.44
3.71
4.10
4.13
4.21
2.86
2.41
1.89
2.68
2.39
37.01
Maximum
Monthly
(36)
8.29
4.33
9.59
6.36
9.11
9.75
9.46
7.%
6.18
5.24
5.40
5.07
9.75
HJTVjinin
Monthly
(36)
0.53
0.38
0.61
0.67
1.61
1.25
0.48
0.58
0.51
0.11
0.80
0.46
0.11
MaYiniBn
in 24 hrs.
(28)
4.81
2.15
3.40
2.37
2.72
2.93
3.82
3.79
2.02
1.87
2.05
1.63
4.81
Show, Ice Pellets

Normal
(29)
7.0
5.9
5.2
0.8
<0.1
0.0
0.0
0.0
O.I
0.1
2.8
5.9
27.7
MayiiTim
Monthly
(28)
18.4
156
13.5
7.1
<0.1
0.0
0.0
0.0
<0.1
1.3
15.2
17.3
18.4
rt-pn iiijni
in 24 Hrs.
(28)
7.2
8.9
8.6
6.3
<0.1
0.0
0.0
0.0
4D.1
1.3
8.2
8.7
8.9
Wind
MeanVird
Speed M.P.H.
(26)
10.3
10.5
10.8
10.2
8.6
7.5
6.7
6.4
6.8
7.6
9.5
9.8
8.7
Prevailing
Direction
(14)
ssw
NW
SSU
WW
S
SSU
ssv
ttv
S
S
S
V
SSU
# of days
Thunder-
storms
(36)
O.5
1
2
4
7
8
8
6
3
1
1
O.5
42
Notes:

Annual extremes have been exceeded at other sites in the locality as follows:   maximum monthly precipitation 10.71 inches in
January 1937;  minium monthly precipitaion 0.10 inches in October 1924; maximum monthly snowfall 29.2 inches in February 1910.
Information extracted from data compiled by the National Climatic Center.

-------
                   TABLE 2-2.  USEPA AM) OHIO EPA AMBIENT AIR QUALITY SBNMRDS*
  Pollutant
                       Dutation
       Restriction
                                                                           Maxinun Allowable
                                                                            Concentrations**
Primary
Secondary
Total Suspended   Annual geometric
  Particulates    mean
                                          Not to be exceeded
                                75 ve/m3      60 UB/m
                  24-hour concentration   Not to be exceeded more
                                          than once per year

Sulfur Dioxide    Annual arithmetic mean  Not to be exceeded
                                                                         260 vg/m      150 i«/m3
                                                                          80ng/nf
                                                                         (0.03 ppm)
                  24-hour arithmetic
                  mean concentration

                  3-hour arithmetic
                  mean concentartion
Not to be exceeded more
once per year

Not to be exceeded more
than once per year
                                                                         (0.14 ppm)
                                                                                      1300
                                                                                      (0.5 ppm)
Carbon Monoxide

Ozone
Nitrogen Dixoide

Lead

8-hour arithmetic
mean concentration
1-hour mean
concentration
1-hour mean
concentration
Annual arithmetic
mean
3-month arithmetic
mean concentration
Not to be exceeded more
than once per year
Not to be exceeded more
than once per year
Not to be exceeded on more
than one day per year,
average over three years
Not to be exceeded

Not to be exceeded

10 ng/m3
(9.0 ppm)
40mg/m3
(35.0 ppm)
0.12 ppm
(244 IB/HI )
0.53 ppm
100 ng/m3)
1*5 uz/nt

Notes:

Primary standards are established for the protection of public health
Secondary standards are established for the protection of public welfare

  *UEEPA and Ohio EPA Air Quality Standards are identical
 **400 CFR 50.4 - 50.12
***Air Quality Guidelines

Ug/m3 = micrograms per cubic meter
ppm   = parts per million
iqg/m3 = milligrams per cubic meter
                                                2-4

-------
     The Ohio EPA has established numerous air quality monitoring stations
throughout  the State.  Within  the Columbus AQCR, the following pollutants are
monitored:  TSP at 16 sites, PH-10  (particulate matter of less than  10 micron
diameter) at one site, lead at  two  sites, sulfate at one site, sulfur dioxide
at six sites, oxides of nitrogen at one site, carbon dioxide at three sites,
and ozone at three sites.  Data for sites in and around Franklin County are
summarized  in Table 2-3.

2.1.1.3  Odors
     Southern areas of Franklin County have been plagued by ambient  odors for
many years.  The 1979 EIS noted that one positive impact of the proposed
project would be the reduction  of odors that plagued the Jackson Pike and
Southerly WVTPs.  To date, many odor complaints have still been made to local,
State, and  Federal agencies.  It appears that the main cause of odor in the
area is the Southwesterly Composting Facility.

     Southwesterly Composting was first put into service in August 1980.  The
first known registered complaint was filed in January of 1981.  A subsequent
study by Ohio EPA confirmed that "...objectionable odors are frequently
emitted from the facility" (Ohio EPA 1981). In particular, the process of
sludge mixing and breaking of an incompletely composted pile were felt at that
time to be  the operational causes of the objectionable odors.  In addition, it
has been stated by several individuals that the type of odor is easily
distinguishable, e.g., a septic sewage odor is attributed to the primary
clarifiers and/or anaerobic digesters at the Southerly Waste Water Treatment
Plant (WWTP); a burnt ash sewage odor is attributable to the incinerators at
Southerly WWTPj and finally, an earthy sewage odor is attributable to the
Southwesterly Composting Facility (McCarthy 1986).   Similar descriptions have
been offered by Maxwell (1986) and Bonk (1986).

2.1.2  Water
2.1.2.1  Hydrology
     The two wastewater treatment plants (WWTPs) that are the subject of this
environmental review (Jackson Pike and Southerly) are located on the Scioto
                                      2-5

-------
     TABLE 2-3.  AIR QUALITY DATA FOR THE FRANKLIN COUNTY LOCAL AREA
Pollutant
(Units)
Avg . Time
TSP
(ug/m3 )
Annual
TSP
(ug/m3 )
24-Hr
S02
(ug/m3 )
Annual
S02
(ug/m3)
24-Hr
S02
(ug/m3)
3-Hr
CO
(mg/m3)
1-Hr
CO
(mg/in3 )
8-Hr
NOx
(ug/m3)
Annual
OZONE
(ug/m3 )
1-Hr
LEAD
(ug/m3)
3-Mo
Year
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
1985
1984
1983
Columbus
57
71.7
67.9
184
209
229
37.3
64.3
40.4
170
260
224
339
572
828
12.6
16.1
18.4
7.2
10.2
9.8
46.7
44.4
42.8
225
212
231
0.35
0.62
0.57
Franklin Grandview
Co. Heights
34.6 45.8
41.8 48.9
41.1 48.7
93 116
104 127
127 154
20.1
18.1
90
71
190
193





Grove
City
38.6
41 .8
39.8
93
99
120








The maximum values  of  several downtown sites has been reported.
                                 2-6

-------
River.  The Scioto River is a major tributary of the Ohio River, originating
in northwestern Ohio (vest of Kenton) and floving 135 miles southeast to the
Ohio River at Portsmouth.  The river basin drains 6,510 square miles in 31
counties of central and southern Ohio.

     The study area in Franklin and Pickavay Counties, is part of the Central
Scioto River Basin.  This basin is located on a flat glacial till plain with
the mainstern floving from north to south and its tributaries following well-
defined gorges.  The Scioto River enters Columbus from the northwest, joins
with the Olentangy River within the City, and then flows south.  To contain
erosion and flooding, the river channel within Columbus has been modified,
reinforced with concrete, and bounded by levees.

     North of Columbus, the Scioto River is somewhat incised, with a substrate
alternating between exposed limestone bedrock and largely silt/muck deposits.
However, south of the city, the river valley is broad and poorly defined,
flowing over a buried valley filled with glacial outwash material (mostly
coarse sand and gravel).  In this area, the channel is typical of a large
compound river, exhibiting meanders and riffle-pool sequences.  Flooding in
this area covers extensive areas of the floodplain (OEPA 1983).

     There are two major Scioto River tributaries in the study area.  They are
the Olentangy River (543 square miles) entering roughly five miles upstream of
the Jackson Pike VUTP, and Big Valnut Creek (557 square miles) entering about
one mile downstream of the Southerly WTP.

     The major tributaries affecting the water quality of the Scioto River
between Columbus and Circleville are the Olentangy River (confluence at RM
132.2); Big Valnut Creek (confluence at RM 117.2), with its tributaries Alum
Creek and Blacklick Creek; Valnut Creek (confluence at RM 102.1); and Big
Darby Creek (confluence at RM 100.8).  Flow summaries and water quality
characterizations for these Scioto River tributaries are provided in the
following discussions.  These discussions are excerpted from the most recent
305(b) reports (biennial water quality reports prepared by the individual
States).
                                      2-7

-------
*  Qlentangy River

   The Olentangy is crucial to the Scioto River because it provides the
   only guaranteed release below Griggs Reservoir, and thus during
   critical low flow periods may be the only source of dilution to the
   Jackson Pike WVTP.  A minimum flow of 5 cfs is required leaving
   Delaware Reservoir above the town of Delaware, but flow almost always
   exceeds this minimum.  Low flow into the Scioto from the Olentangy
   usually exceeds 19 cfs and almost never drops below 10 cfs.  Effluent
   from the Delaware WVTP enters the Olentangy River, at RH 24.8, and
   affects water quality for a short distance downstream.  However, this
   does not significantly degrade water quality at the confluence with
   the Scioto River.  Nevertheless, water quality in the lower 10 miles
   of the Olentangy is rated FAIR (OEPA 1986b) and the last half-mile
   before entering the Scioto received a POOR rating.  The ratings are
   based on low faunal diversity indices and violations of fecal
   coliform, iron, and lead water quality standards.  Combined sewer
   overflows and urban runoff from Columbus have been noted as the major
   causes of the poor water quality.  Dissolved oxygen usually exceeds
   7.0 mg/1, but the Columbus Consolidated Environmental Information
   Document (URS Dalton 1986) reports violations of DO standards (5.0
   mg/1) during low flow conditions.  Elevated nitrate levels have also
   been reported and may contribute to the DO problem.

•  Big Walnut Creek

   The water quality of the lower segment of this creek, before it enters
   the Scioto, was not rated in the 305(b) report.  The two main
   tributaries into this creek, Blacklick and Alum Creeks, both have
   water quality problems.  Blacklick Creek is given a FAIR rating due to
   serious violations of water quality standards for dissolved oxygen,
   ammonia, and fecal coliform.  Blacklick Estates WVTP is currently the
   major source of degradation, although the Reynoldsburg WVTP also
   discharged into this creek in the past.  Alum Creek is given a GOOD
   rating, but the lower portion (below the two reservoirs) is subject to
   urban point source and nonpoint source pollution, as is Big Walnut
   Creek downstream of the Alum Creek confluence.  Sporadic dissolved
   oxygen and total iron WQS violations have been reported in these
   areas,  but data are insufficient to assess overall water quality.

•  Walnut Creek

   Although the upper reaches of Walnut Creek have exhibited some water
   quality problems,  due to effluents from Crown Zellerbach and the
   Baltimore WWTP, the lower 24.3 mile section leading to the confluence
   with the Scioto River is rated GOOD in the 305(b) report.  Fish and
   macroinvertebrate community indices reflected good water quality, with
   a possible decline reflected in the macroinvertebrates downstream of
   RM 5.5.  This decline may have been due to the effects of organic
   enrichment from nonpoint source runoff from agricultural lands.  The
   CWQR (OEPA 1986a) reports violations of total iron water quality
   standards near the mouth of Walnut Creek,  which could also reflect
   agricultural runoff (iron bound to eroded  soil).   The reported
   dissolved oxygen concentrations always exceeded 5.0 mg/1.
                                2-8

-------
     *  Big Darby Creek

        This tributary is characterized as having exceptional water quality in
        the 30 mile segment upstream of its confluence with the Scioto River
        (OEPA 19865).  Concentrations of nitrogen compounds, total phosphorus,
        and BOD vere relatively low and not indicative of problems.  Heavy
        metals concentrations were indicative of point and nonpoint sources
        but did not reflect severe loadings problems.  Dissolved oxygen
        concentrations generally were high.


     The Olentangy River floodplain is narrow, with an average width of about
1,500 feet.  The river flows through a gorge section, from north of Worthing-
ton upstream to Delaware, Ohio.  It has an average slope of 6.2 feet per mile.


     The river stretch in that portion of the study area north of the Jackson

Pike VVTP is interrupted by two major impoundments, three low head dams on the

Scioto River, and one impoundment on the Olentangy River.  These structures

supply Columbus with drinking water sources, flood control, and recreational

sites.  They are discussed below in upstream-to-downstream order.


     •  0'Shaughnessy Reservoir was built in 1924.  The area of the seven mile
        long pool is 829 acres.  The concrete spillway is 70 feet high and
        1,005 feet long.  The dam is located at RM 148.8.

     •  The Julian Griggs Reservoir was built in 1905 for water supply.  The
        six-mile-long reservoir is also popular for power boating and a park
        and marina exist along the shoreline.  The concrete ogee dam is 33
        feet high and 500 feet long.  It is located at RM 138.8.

     •  The Dublin Road Vater Treatment Plant withdraws water from behind a
        low head dam about 17.7 feet high by 310 feet long.  The dam is at RM
        133.4.

     •  The Delaware Reservoir is located on the Olentangy River.  Completed
        in 1951, the reservoir primarily serves as flood control although the
        conservation pool is operated to provide five cubic feet per second
        during low flow conditions to preserve downstream water supply and
        pollution abatement uses.  The Olentangy River joins the Scioto at RM
        132.3.

     •  The Main Street Dam is a low head dam 15.7 feet high and 545 feet
        wide.  It creates a pool for a downtown park.  The pool is not used to
        control releases downstream.  The dam is at RM 131 (OBPA 1983).

     •  The Greenlawn Avenue Dam, like the Main Street Dam, is not used for
        water conservation.  It is a low head dam 11 feet high, 422 feet wide
        and is located at RM 129.6.
                                     2-9

-------
     The flow regime of the Scioto River can be characterized by river dis-
charge data taken at United States Geological Survey (USGS) gaging stations.
However, in analyzing this data for current river discharges, the period of
record considered roust recognize the effect of flood control and water supply
impoundments, the most recent of which is the Delaware Dam (constructed in
1951).  These impoundments have a moderating effect during flood conditions
reducing peak downstream discharges.  During low flow conditions, water supply
withdrawals have occasionally resulted in no discharge passing the Dublin Dam;
Scioto River flows downstream are then supplied solely by Delaware Dam
releases on the Olentangy River.

     The primary source of river flows is from precipitation with the greatest
amount of precipitation occurring from February to July and the least amount
from August to January.  Previous studies indicate a certain amount of ground-
water inflow to the river during low flow periods (OEPA 1983).

     Of the water bodies in the study area, low flow conditions are the most
critical on the Scioto River.  Columbus is authorized, by a 1913 statute, to
divert all flows of the Scioto River for the purpose of maintaining the public
water supply.  Since the Griggs Reservoir and the Dublin Dam were designed  for
public water supply, this statutory authority has resulted in occasional "no
flow" conditions over the Dublin Dam.  The only assured water sources during
low flow periods are from the Delaware Reservoir and the two WWTPs.

     The Corps of Engineers has guaranteed a minimum release of 5 cfs from  the
Delaware Reservoir, to preserve water supply and water quality uses making  the
Olentangy the principal source of dilution water for the Columbus VWTPs under
extreme low flow conditions.  The Jackson Pike WTP can contribute as much as
98 MGD (85 MGD on average) of discharge to the Scioto River Study area, which
represents 90 to 95 percent of the extreme low flow discharge in the river
stretch between the two WWTPs.  Downstream of Southerly WVTP, Big Walnut Creek
and other tributaries provide additional water inflow.

     According to the Federal Emergency Management Agency's (FEMA) Flood
Insurance Study for Franklin County and the City of Columbus, the floodplain
of the Scioto River can be divided into two fairly distinct topographic
                                     2-10

-------
subdivisions:  a gorge section, with narrow valleys, from the Delaware County
line to approximately Interstate Highway 670 (crossing just north of
Valleyview); and an alluvial section with wide floodplains and rolling
uplands, from the Interstate Highway 670 crossing downstream to the Pickaway
County line.  Floodplain development along the Scioto River is extensive,
varying from residential to industrial.

     The Olentangy River flows south through Franklin County and joins the
Scioto River near the southeasterly corporate limits of Grandview Heights,
within the Columbus metropolitan area.  The land along the Olentangy River
floodplain is mostly open area and farm land in the upper reaches of Franklin
County.  However, the lower several miles of the river, from Worthington to
the mouth, are mainly developed.  Major transportation arteries, with their
associated bridges and interchanges, lie adjacent to the stream.  Many indus-
trial and research facilities, several wholesale and retail distribution
centers and several park areas adjoin the Olentangy in the lower reaches.
Very little land adjacent to the stream along the lower three miles is
available for future development.

     The history of flooding along the Scioto River, and particularly along
the Olentangy River, indicates that a major flood can occur during any season.
However, the majority of floods have occurred during the period from January
to March and have usually been the result of spring rains and/or rapid snow-
melt.  The worst floods of this century occurred on March 25, 1913; in January
1952j and on January 21-22, 1959.

     In response to the flood of 1913, flood protection measures were imple-
mented.  The Scioto River channel improvement project widened the channel,
constructed levees and revetments, and increased bridge spans.  After the 1959
flood, Dry Run levee was raised and strengthened, and a levee was constructed
along Dublin Road.  In 1951, Olentangy River flows were regulated, for the
first time,  by the Delaware Dam and Lake Project.  Although the areas along
the Scioto River protected by levees would probably be safe from minor flood-
ing events,  the extent of major flooding events, such as the 100-year flood,
would be unlimited, as if the levees were not present.
                                     2-11

-------
2.1.2.2  Groundwater
     Groundwater quality analyses are available from the USGS and the Ohio
Department of Health for inorganic chemical characteristics, but organic
analysis data are limited.  In 1985, the Ohio EPA began testing the ground
water quality of four large radial veils used to provide the City of Columbus
with roughly 10 percent of its drinking water supply.  In 1987, a regular
program of testing these four veils is expected to begin (Button 1986).

2.1.2.3  Surface Water Quality
     The Scioto River from O'Shaughnessy Reservoir (RK 148.8) to Chillicothe,
Ohio (RM 70.7) is a moderately polluted, turbid, warm water stream fed by
several tributaries of similar or better quality.  The most significant water
quality impact is observed belov the two Columbus wastewater treatment plants,
at river miles (RM) 127.1 and 118.4.  Previous studies (1980-1982) have
described degraded conditions measured in chemical/physical water quality
parameters and biological indices, below the two treatment plants.  Despite
continued improvement over the past two decades, a substantial part of the
river between Columbus and Circleville does not yet meet the goals of the
Clean Water Act.  Less severe problems occur downstream from Circleville and
upstream from Griggs Dam (RM 138.8) and in the Olentangy and Scioto Rivers
adjacent to Columbus.  The problems in Griggs Reservoir and in the Olentangy
are primarily due to runoff and/or combined sewer overflow (CSO).

     In the Scioto River, low levels of dissolved oxygen have historically
been the greatest problem associated with the two wastewater plant discharges
(Jackson Pike and Southerly).  Improvements made in these treatment facilities
in the last 20 years have contributed to improvements in water quality down-
stream.  The most noted water quality improvement has been increased dissolved
oxygen levels.  Appendix G presents graphs of STORET data for DO, BOD5, and
NH3+NH~-N (ammonia) from 1971 to 1986 at six stations between the Jackson Pike
WWTP and Circleville.  Regressions on each graph (dashed line) indicate a
general trend of improving conditions (increasing DO, decreasing BODS and
decreasing ammonia) over the referenced time period.
                                     2-12

-------
     Flow records from a USGS station just downstream from the Jackson Pike
wastewater treatment plant indicate wide fluctuations in flow, with a minimum
of 47 cfs and a maximum of 68,200 cfs during the period from October, 1920
through September, 1985 (Shindel, et al. 1986).  The impact of wastewater
treatment facilities on water quality is highest during periods of critical
low flow.

     The O'Shaughnessy and Griggs Reservoirs, upstream from Columbus, are a
source of drinking water for the City.  As Columbus is authorized to divert
the entire flow of the Scioto River for public water supply, during periods of
critical low flow there may be little or no water flowing over the dam at the
Dublin Road water treatment plant (RH 133).  Under these flow conditions, the
Scioto River relies upon its confluence with the Olentangy River (RM 132.3) to
replenish its flow, at a minimum of 5 cfs (regulated at Delaware Dam).  During
critical low flow periods, the input from the Olentangy provides the only
upstream dilution to the Jackson Pike UWTP (RM 127.1).

     The Scioto River between Columbus and Circleville is greatly affected by
wastewater discharge from the city of Columbus.  The combined discharge from
the two Columbus wastewater treatment plants (Jackson Pike at RM 127.7 and
Southerly at RM 118.4) constitutes up to 95 percent of the total discharge of
the river during low flow periods.  The effects of point and nonpoint pollu-
tion sources on Scioto River water quality have been demonstrated in the CWQR
(OEPA 1986a), based on instream chemical and physical data from 1980-1982.
The most notable negative impacts occurred downstream from the Jackson Pike
tfWTP.  Dissolved oxygen (DO), BOD5, total Kjeldahl nitrogen (TKN), nitrate
(N03-N), total phosphorus (P-T), and total zinc (Zn-T) concentrations
reflected heavy loadings of domestic and commercial/industrial pollutants.

      Dissolved oxygen (DO) is reported to exhibit the classic decline and
recovery downstream from both the Jackson Pike and Southerly WWTPs (OEPA
1986a).  However, the data presented in the CWQR do not support this observa-
tion.  Instead, these data suggest a steady decline in DO downstream from
Jackson Pike, with recovery beginning at least 10 miles downstream from
Southerly and continuing to Chillicothe (RM 70.9).  At times, DO concentra-
tions drop at Circleville (RM 102.1).  There may be a slight increase in DO at
                                     2-13

-------
RM  115.3,  three miles downstream of the Southerly WWTP, probably reflecting
the input  from Big Walnut Creek at RM 117.2.  Lov dissolved oxygen levels are
considered  the overriding water quality problem in this portion of the Scioto
River, although conditions have improved over the past two decades and are
anticipated  to continue  improving.  This improvement is the result of
increasing DO and decreasing BOD5 loading in the VWTP effluents.  However,
over the past 5 years (1980-1985), the occurrence of WQS violations for DO
(i.e., concentration of  less than 5 mg/1 mean or less than 4 mg/1 minimum) has
not steadily declined, according to a frequency analysis of daytime DO data
(OEPA 1986a).

     Ammonia creates an  oxygen demand, thereby lowering DO concentrations in
receiving waters.  On this basis, the CWQR attributes improved DO conditions
in  the Scioto, in part,  to the significant reduction in ammonia loading from
the two WWTPs over the past two decades.  However, a frequency analysis of
ammonia data between 1980 and 1985 reveals that there was not a substantial
improvement in ammonia levels between 1980 and 1985 (OEPA 1986a).
Concentrations exceeding 2.0 mg/1 were not unusual downstream from the WWTPs
and concentrations exceeding 1.0 mg/1 were common (30-50 percent of the
measurements).

     The major input of  ammonia is from the two WWTPs.  A sharp increase in
ammonia concentrations occurs just downstream of the Jackson Pike WWTP,
followed by a gradual decline to the Southerly WWTP, where a small increase
occurs, and then a progressive decline downstream to Circleville.  Ammonia
concentrations between Jackson Pike and Southerly often exceed 1.0 mg/1 and
annual maxima may exceed 3.0 mg/1.  Downstream of Circleville, concentrations
are usually between 0.2 mg/1 and 1.0 mg/1.

     Upstream of the WWTPs, ammonia concentrations remain less than 1.0 mg/1
and often fall to less than 0.2 mg/1.  The major source of ammonia in that
portion of the river is  runoff and CSO outfalls to the Olentangy and the
Scioto mainsterns.
                                     2-U

-------
     Ammonia is one of several nitrogen species which exert a DO demand.
Total Kjeldahl nitrogen (TKN) is often used as a measure of collective DO
demand due to nitrogen.  TKN concentrations in the Scioto follow the same
general distributional pattern as ammonia, with the tvo WWTPs providing the
major inflow.

     Nitrate nitrogen (N03-N) concentrations reflect both point and nonpoint
sources.  Upstream from Griggs Dam, both the Griggs Reservoir and the
O'Shaughnessy Reservoir are enriched with nitrogen, presumably from agri-
cultural runoff.  Concentrations in excess of 4.0 mg/1 are not uncommon and
violations of the WQS for drinking water (10.0 mg/1) have been reported.
However, much of this water is withdrawn at the Dublin Road water treatment
plant.  Consequently, NO}-N concentrations downstream of the waterworks dam
(RM 133) are reduced due to the diluting effect of water entering from the
Olentangy River, which exhibits lower nitrate levels (N03-N =2.3 mg/1).

     Downstream from Jackson Pike, ambient river nitrate concentrations rise
markedly to concentrations of greater than 5 and even of up to 10 mg/1 during
periods of low flow.  Nitrate concentrations steadily decline downstream from
the initial increase caused by the Jackson Pike WWTP effluent.  Vastewater
input from the Southerly WVTP does not have a marked effect on ambient nitrate
concentrations, although it may retard the rate of decline downstream.
Nitrate contributions from the WWTPs have increased over the past several
years due to improved nitrification practices adopted for the purpose of
reducing ammonia levels in the effluent.

     Total phosphorus (P-T) concentrations are almost exclusively related to
point source input.  The major contribution comes from the Jackson Pike WWTP
where ambient river concentrations rise dramatically, usually in excess of
1.0 mg/1 and often to greater than 2.0 mg/1.  Downstream from the Jackson Pike
WVTP spike, concentrations decline steadily but never drop quite as low as
upstream levels.

     The most commonly found heavy metals in the Scioto are zinc, lead,
copper, and iron.  Cadmium, chromium, and nickel are found less frequently.
Total zinc (Zn-T) concentrations in the river are significant, however, zinc
                                     2-15

-------
rarely exceeds the WQS (300 ug/1).  The Zn-T distribution reflects the impact

of the Jackson Pike WVTP and, to a lesser extent, urban nonpoint sources.

Concentrations are at their maximum near Jackson Pike and decline progres-

sively downstream.


     Total lead (Pb-T) and iron (Fe-T) increase slightly in a downstream

direction through the study area.  Both reflect primarily nonpoint source

input.  Iron is associated with both agricultural and urban runoff and is

strongly bound to suspended solids, while lead is associated primarily with

urban runoff.  WQS violations have been frequently reported for iron, but

violations of the 30 ug/1 WQS for Pb-T have been minimal.  Total copper (Cu-T)

distribution reflects inputs in the Columbus and Circleville areas, but in

general the levels are fairly low.


Vater Quality Ratings of River Segments

     The 305(b) report lists six segments of the Scioto mainstern in the study

area.  They are rated as follows:


     •  O'Shaughnessy Dam to upstream from the Olentangy River confluence (RM
        148.8-132.4) - GOOD:  High nutrient loads but low algal density char-
        acterized this section.  Other physical/chemical water quality param-
        eters were good, and fish and macroinvertebrate indices reflected
        background conditions, although increasing stress was evidenced in
        Griggs Reservoir.

     •  Olentangy River confluence to Prank Road (RM 132.2-127.7) - PAIR:
        Both fish and macroinvertebrate communities reflected structural and
        sublethal stresses due mainly to contributions from urban nonpoint
        sources and combined sewer overflows, and the partially impounded
        nature of this segment causing elevated contaminant levels in trapped
        sediments.

     •  Frank Road to confluence of Walnut Creek (RM 127.7-106.1) - FAIR/GOOD:
        Most extensive chemical/physical and biological water quality degra-
        dation occurred in this segment, but rating has been upgraded from
        POOR to FAIR/GOOD because 1985 sampling revealed full or partial
        attainment of biological potential (based on species diversity
        indices) at several locations.

     •  Confluence of Walnut Creek to confluence of Big Darby Creek (RM 106.1-
        100.8) - GOOD:  Good assemblage of fish and macroinvertebrates
        reflected near complete recovery of upstream impacts, with improve-
        ments continuing through 1985.
                                     2-16

-------
     •  Confluence of Big Darby Creek to near Delano (RM 100.8-78.3) - FAIR:
        Fish and macroinvertebrate communities improved over previous years.
        Slight stresses were still apparent, but diminished downstream.  In
        1981, there was judged to be a potential for impact from complex toxic
        substances downstream from Circleville.  In 1984-1985, almost complete
        recovery of fish and macroinvertebrate communities was reported
        between RM 100.8 and 99.7.
     •  Near Delano to Bridge Street in Chillicothe (RM 78.3-70.7) - GOOD:
        Fish and macroinvertebrates typical of organically enriched warm-water
        river.

     Surveys of fish and macroinvertebrate communities have been used as
indices of water quality (OEPA 1986a; OEPA 1986b; Olive 1971).  Diversity
indices are most commonly used and serve as one basis for classifying water
quality in the 305(b) report (OEPA 1986b).  In both the CWQR (OEPA 1986a) and
the 305(b) reports, improvements in species diversity vere noted as indicative
of improving water quality conditions in the Scioto River between Columbus and
Circleville.  These biotic changes were attributed to overall increases in DO,
due to upgraded water treatment practices.

     It was also noted in the CWQR that improved diversity has been accom-
panied by the reappearance of pollution-intolerant fish species (including
several sport fish).  However, an increase in external anomalies (e.g.,
lesions, fin erosion) has also been recorded.  An attempt has been made to
associate the anomalies with the effects of low oxygen on intolerant species,
and the CWQR predicted that the incidence of anomalies will decrease as DO
continues to increase.  However, this prediction overlooks the potential
effect of chemical contaminants, such as chlorine, heavy metals and various
organic chemicals, to which external and internal anomalies are usually
linked.

     Fecal coliform bacteria are commonly used as raw sewage tracers.  Over
the past decade, there has been a general decline in fecal coliform concen-
trations in the segment of the Scioto River between the Jackson Pike WWTP and
Circleville.  However, this decrease is in large part attributed to increased
chlorination at the VUTPs.  Consequently, the fecal coliform count can no
longer be reliably used as an indicator of raw sewage.  Further, increased
chlorine is a water quality concern which can have an impact on the river
fauna (including, for example, external anomolies).
                                     2-17

-------
2.1.3  Land
2.1.3.1  Topography and Physiography
     The Columbus planning area includes the city of Columbus, Ohio, most of
Franklin County, and small adjacent portions of Delaware, Licking, Fairfield,
and Pickavay Counties.  The topography of the study area is characterized by
level  to rolling relief, with altitudes ranging from 1130 feet above sea level
in the northeast to 665 feet above sea level along the southern border.

     The major stream valleys in the northern portion of Franklin County run
parallel to each other, converging towards the centrally located valley of the
Scioto River,  Tributaries of the Scioto River include the Olentangy River and
Darby, Walnut, Blacklist!, and Alum Creeks.  The Scioto River gradient within
the Facilities Planning Area (FPA) averages about 4.4 feet per mile.

2.1.3.2  Surficial and Bedrock Geology
     The FPA is located within the glaciated till plain of Central Ohio
(Goldthwait et al. 1961).  The Till Plains section of the Central Lowlands
physiographic province constitutes about four-fifths of Franklin County.
Formed when preglacial features were buried by glacial deposits, the Till
Plains are flat except in areas adjacent to streams.  The remaining one-fifth
of Franklin County is occupied by the Appalachian Plateau rising eastward near
Big Valnut Creek from an escarpment of north-south scarps and terraces at an
elevation of 800 feet.  The general area was glaciated during at least two
different glacial periods.  Evidence of Illinoian glaciation has been found in
the form of fine, well-sorted sands in buried valleys beneath the more recent
Wisconsin age glacial till (SCS 1980a).  Dominant soils formed in these
deposits are Eldean, Ockley, Varsawy, and Vea soils.

     The surface deposits in the FPA are mostly ground moraine.  The landscape
has an average of about 50 feet of till over bedrock. There are two distinct
tills within the ground moraine.  The northeastern third of the FPA consists
of a medium-lime clay loam till that contains a high percentage of sandstone
and coarse shale fragments from the underlying bedrock.  The dominant soils
formed here include Bennington, Cardington, and Pevamo soils.  The south-
western two-thirds of the ground moraine consist of a high-lime till that
                                     2-18

-------
contains a high percentage of limestone and coarse dolomite fragments from the
underlying limestone bedrock.  Among the soils formed in this ground moraine
are Kokomo, Celina, and Crosby soils.  There are three end moraines in the
FPA: the London Moraine in the southwest corner, the Pickerington Moraine in
the northeast corner, and the Powell Moraine in the extreme southwest corner.

     The bedrock underlying  the glacial deposits is sedimentary.  It has a
north-south strike and a dip of 20 to 30 feet per mile to the east.  Ages
range from lover Devonian in the west to lower Mississippian in the east of
the FPA.  Lithologies consist of dolomitic limestone, shale, and sandstone.

     The Raisin River Formation, dolomitic limestone exposed in places in the
valleys of Big and Little Darby Creeks, is the oldest member of the Devonian
System in the FPA.  The formations within the Devonian System to the east are
younger and located above the Raisin River.  These include the Columbus and
Delaware Limestones and the Ohio and Olentangy Shales.  The limestone is along
the Scioto River Valley and  the shale is along the northern Olentangy River
Valley.

     The Mississippian System is exposed in the valleys of Big Valnut and
Rocky Fork Creeks.  The formations include, from oldest to youngest, Bedford
Shale, Berea Sandstone, Sunbury Shale, and Cuyahoga Sandstone.  These
formations occur as alternating beds of shale and sandstone.

     The geologic formations that occur near the surface in the Scioto River
Basin are of sedimentary origin.  They are comprised of two general classes:
(1) consolidated layers of sandstone and shale, and (2) unconsolidated
deposits of clay, sand, and gravel.  Sandstone formations may yield sizable
quantities of water; however, the degree of cementation of the individual
grains and the composition of the formation often deter the flow of water
through the formation.  Shale may temporarily store sizable quantities of
water; however, water does not readily pass through it.  Water in the glacial
sand and gravel deposits occurs in the pore spaces; therefore, permeability,
thickness, and regional extent of the water-bearing formation determine the
quantity of water available.
                                     2-19

-------
     Limestone bedrock  is  the principal source of underground vater for the
Mill Creek and Scioto River basins.  The Silurian and Devonian carbonates
underlie  the entire basin  at depths ranging from 1 to more than 220 feet.
Industrial wells developed in these formations have reported yields in excess
of 450 gallons per minute.  The southern glacial outwash deposits of the
Sciota River yield more than 200 gallons per day.  These relatively thick
lenses of sand and gravel  may be recharged by the Scioto River.

2.1.3.3   Soils of the Facilities Planning Area
     Soil characteristics  influence the design and location of septic tank
systems and landfills as veil as the suitability of sites for land application
of sewage sludge.  Soil infiltration rates under different cover conditions,
permeability, land slopes, depth to the bedrock/water table, and the relation
of these  factors to the ground vater system determine the suitability of a
site for  solid or liquid waste disposal.

     The  soils have been mapped in detail for the entire FPA (SCS 1977, 1978,
1979, 1980a, 1980bf 1981,  1982).  The association map (Figure 2-1) is provided
to convey a general concept of soils in the FPA.  The four major soil
associations, covering  75  percent of Franklin County, are described belov.

     The  Bennington-Pewamo association is characterized as deep, nearly level
and gently sloping, somewhat poorly drained, and very poorly drained soils
formed in medium textured  and moderately fine textured glacial till.  This
association covers about 29 percent of Franklin County.  It is found on
relatively broad flats, depressions, low knolls, and ridges.  The soils have
low potential for most  building site development and sanitary facilites.  The
seasonal  wetness, ponding, slow or moderately slow permeability, and low
strength  are the main limitations.

     The  Crosby-Kokomo-Celina association is characterized as deep, nearly
level to  sloping, moderately well drained, somewhat poorly drained, and very
poorly drained soils formed in medium textured and moderately fine textured
glacial till.  This association covers about 12 percent of Franklin County.
                                     2-20

-------


                  7 b-r
        *I*~^I^T^&&EI  •••
          ~EP|£2^j ^W-7^1
            ~%fl£i
                                              U S PCTAMM'NI Of *CfcJCU 4JRC
                                               ,t)H uCih&tffVA (0** St*Vtfc
                                            N TCI HATJRAI wt^ou^crs M* *MJ» OFIAHOSANO vm
                                             IUJl TUN Al ftCSE AHC" ANU Of V t 1 ij»»MIN * Ci N U H
        GENERAL SOIL MAP

       HtANM 1M COUNTY OHIO
                                                SOU LFGLND

                                        tft! I Pf AINLD UOOCRATELY «E^L C*A «f 0 J
                                        Oh I lXK>t> f 4.AW
   j flea «r3 vf ,
   <«ftAEi|i u*,

   e**c»'OvB.l^y-
 • 1 U Ik tb it*J ii "
                                        *£U Of AINFU
                                        VM \ ON UHLAI
                                        wrll r iwc toil* I
                                                      «k.«ra e j « K» « MS* *fc 7 ( «* ir It


                                                      J *>*< fc- a *r jt*it itorji <*rHtffitt*c
                                                      M Wn)u «J {Irt ^ fit *"** >E i. itf t.


                                                 *lLL D1AHED AhL UMf WfAt FOOfLY D4*fa trt«cp nti t> *« HiJ,«rjs «^»4et-U i( >^li
                                            v w jiCBJ •,<• -k T^t *d • IHtWvU * IT flC t. Hj (-1 jlJi Jl Hi
FIGURE 2-1.  GENERAL SOIL MAP OF FRANKLIN COUNTY, OHIO

-------
 It  is  found on  broad  flats with depressions, knolls, and ridges.  The Crosby
 and Kokomo soils  have low potential  for building site development and sanitary
 facilities.  Celina soils have medium potential for these uses.  Seasonal
 wetness,  slow or  moderately slow permeability, and low strength are the major
 land use  limitations.

     The  Crosby-Kokomo association is characterized as deep, nearly level and
 gently sloping, somewhat poorly drained, and very poorly drained soils formed
 mainly in medium  textured and moderately fine textured glacial till.  This
 association covers about 24 percent  of Franklin County.  It is found on broad
 flats with slight rises, low knolls, and depressions.  The soils are mainly
 nearly level and gently sloping with sloping areas along some drainagevays.
 Most areas have low potential for most building site development and sanitary
 facilities.  The seasonal wetness, slow or moderately slow permeability, and
 ponding are the main  limitations to  use.

     The  Kokomo-Crosby-Lewisburg association is characterized as deep, nearly
 level and gently sloping, moderately well drained, somewhat poorly drained,
 and very  poorly drained soils formed in medium textured and moderately fine
 textured  glacial  till.  This association covers about 10 percent of Franklin
 County.   It is  found on broad flats  with depressions, low knolls, and some
 discontinuous ridges.  The Kokomo and Crosby soils have low potential for
 building  site development and sanitary facilities, and the Lewisburg soils
 have medium potential  for these uses.  Soil wetness, slow or moderately slow
 permeability, and erosion hazard on  the Lewisburg and Crosby soils are the
 main limitations.

     Most of the soil associations are described as having low potential for
 building site development and sanitary facilities.  Some of the limitations
can be partially or fully overcome by specially designed facilities.  Building
sites could be landscaped for good surface drainage away from foundations and
 septic tank absorption fields.  In some places artificial drainage can reduce
 the wetness limitation and swell potential if proper design and installation
procedures are used.
                                     2-22

-------
2.1.4  Biota
2.1.4.1  Terrestrial Biota
     The FPA is situated vithin  the Temperate Deciduous Forest Biome.   Once
covered primarily by climax beech  forest, most of  the  land  in Franklin  County
has been cleared for agricultural  use.  Forested areas which currently  cover
only about 5 percent of the county are limited to  relatively small scattered
woods, stream bank areas, and  floodplains.  Table  2-4  identifies several
natural terrestrial areas that have been determined  to have unique natural
vegetation.

     Dominated by agricultural lands, the FPA is characterized by relatively
low wildlife populations and diversity.  With modern agricultural practice, it
is common to plant "fence row  to road ditch," leaving  little year-round
herbaceous cover, undisturbed  breeding habitat, or natural  food for wildlife.
Therefore, the principal wildlife  habitat in the FPA is provided by the avail-
able farm woodlots and vegetation  along streams.   Species which are abundant
in the farm fields include the cottontail rabbit,  the  fox squirrel, the red
fox, and the woodchuck.  For these species, the farm land provides adequate
forage, while nearby woods provide protective cover and nesting sites.
Raccoons, weasels, opossums, muskrats, and minks are found  in wetland areas
and forests associated with streams and ponds.  Species associated with upland
forest habitat, including white-tailed deer, gray squirrels, and gray foxes,
are also found in many parts of  the FPA.

     Each spring and fall millions of bird migrants of several hundred species
pass through Ohio to and from  their breeding grounds.  About one-third of
these nest in the west-central region (Thomson 1983).  This is the region
which contains the FPA.  Once vast forest land, central Ohio is now
predominantly farmland.  Those areas which serve to provide habitat include
remaining forests,  bogs, tree-lined rivers (e.g.  the Scioto River), sewage
treatment ponds, golf courses,  airports, quarries, and landfills.

     The greatest number of migrant and overwintering waterfowl in Ohio can be
found in the Scioto River watershed.  In the northern half of the central
Scioto River basin mallards and black ducks are commonly found nesting, along
                                     2-23

-------
              TABLE 2-4.  NOTEWORTHY NATURAL TERRESTRIAL AREAS
       Area
Location
     Description
       Blacklick Kooas
                   n Park
Southwest of
Reynoldsburg
       Blendon Woods
        Metropolitan Park
       Darby Creek
        Metropolitan Park
Northeast of
Columbus, along
Route 1(1
East side of
Darby Creek, on
Koebel-Suydajn
Road
       riighbanks           Sharon Twp. and
        Metropolitan Park  also Orange Twp.,
                           Delaware County
       Sharon Woods
        Metropolitan Park
        (Spring Hollow)

       flint Ravine
Sharon Twp.
Sharon TWO,
crosses Rt  23
to the Olentangy
River.
       Cahana Woods State  Jefferson Twp.
        Nature Preserve
        (Dehlendorf
         hoods)
       Rocky Fork
        Natural Area
       Scioto River Bank
        at Dublin
       Welch's Beech
        Woods
Gahanna, 1/2 mi
south of Haven
Corners Rd., on
the west side of
of Taylor Station
Road.

Rocky fort Creek
vicinity
One of the finest un-
spoiled woocia-::s ~-i
central Ohio.  A beech-
maple to elff. ash, oan
swamp-forest.  Dedicated
as a State Nature Pre-
serve, April 1973.

An area of rough terrain
and second growth timber,
much kept as wilderness
area   Upland and swamp
forests.

An upland area of pri-
marily oak-hickory forest.
Eroded hillsides along the
creek provide suitable
habitat for prairie spe-
cies vegetation.

Ohio shale bluff and oak
forest along the East bank
of the Olentangy River.
Dedicated as a State
Nature Preserve, April
1973.

A good beech-maple forest
containing large white
oaks.

A terrain rich in fauna
and flora that has been
kept in a wild state.
A beech-maple and ash
forest with mixed mesophy-
tics, and pin oak, silver
maple and buttonbush swamp
in lower regions.  Dedica-
ted January 1974.
A rugged ravine on Kocky
Fork Creek, a tributary
of Big Walnut Creek.
Extends south from  The type locality of
Dublin Bridge and   Trillium nivale,  and also
                    contains-one of the best
                    colonies of Thu^a oeci-
                    dentalis in its native
                    habitat in central Ohio.
                           west of U s  Rt.
                           33 ca 1 mile,
                           including an old
                           limestone quarry
Washington Twp
and Also Concord
Twp ,  Delaware
County
Mature beech woods of
exceptional quality on the
Powell Moraine.
Source:   Malcolm Pirnie, Inc. July 1976.
                                       2-23

-------
with some blue-winged teal.  On  the Scioto River south of Columbus  the wood
duck is the principal breeding species.

     Nesting habitat requirement for the wood duck are water, mature timber
with suitable nesting cavities and brood cover, all within close proximity.
Vhen nest sites are not available near water the wood duck may nest one to two
miles from the nearest body of water.

     Vhen the reservoirs in northern Columbus freeze, many waterfowl fly to
the segment of river below the Jackson Pike WVTP.  The warm effluent keeps the
river from freezing, making it attractive as a source of food and protection
to the migrating and residential flocks (Vatts 1987).

     A diversity of bird fauna has been observed at the Jackson Pike VWTP.
This site has been identified by Thomson (1983) as one of the good birding
sites in Ohio.  Thomson described the small ponds at the entrance of the WVTP
as a noteworthy area for songbirds and also as a possible area to find a great
blue heron or a belted kingfisher.  The sludge pond attracts shorebirds from
April through October.  Rare species that have been seen here include piping,
lesser golden, and black-bellied plovers; whimbrel; willet; ruddy turnstone;
Vilson's and red-necked phalaropes; long-billed dowitcher; red knot; and
western, white-rumped, Baird's stilt, and buff-breasted sandpipers.  The most
commonly seen species during the late summer movement of shorebirds are
greater and lesser yellowlegs, solitary sandpipers, and pectoral sandpipers.
Another pond on the site is attractive to blue-winged teals, wood ducks, and
American coots, and when the water is low, shorebirds feed along the muddy
edges.

2.1.4.2  Aquatic Biota
     The streams within the FPA are classified as "warm water habitat" by the
Ohio EPA.   Vater quality and habitat conditions in the individual streams
affect the species diversity and the abundance of aquatic biota found in each
stream.   The following discussion addresses fisheries,  macroinvertebrates, and
bivalve mollusks as indicators of existing water quality conditions.  The
                                     2-25

-------
 primary  focus  is  the  mains tern  Scioto River, although tributaries are also
 discussed.

      Biological and chemical/physical sampling conducted in the central Scioto
 River mainstem during 1979,  1980, and 1981 clearly illustrated a significant
 impact on  the  area between  the Jackson Pike WWTP and Circleville (OEPA 1986a).
 Both  fish and  macroinvertebrate communities were degraded and biological
 indices were well correlated with the observed pattern of dissolved oxygen
 concentrations.  Fish sampling conducted during 1979-1986 revealed improved
 conditions between Columbus and Circleville, as reflected in Figure 2-2.  The
 cumulative distance of mainstem with low mean composite index values (less
 than  8.0) was  significantly reduced, from 26.9 miles in 1979 to 0.7 miles in
 1985  for that  area between  the Jackson Pike WVTP and Circleville (OEPA 1986a).
 Further improvements  occurred  in 1986 when none of the sampling locations fell
 below 8.0 and  several  rose above 9.5.

 Fisheries:  Mainstem  Scioto River
      Fish can  be one  of the most sensitive indicators of the quality of the
 aquatic environment in that they constitute a conspicuous component of the
 aquatic community (Smith 1971).  The relative abundance and distribution of
 fish  in the central Scioto River were determined, through electrofishing, in
 1979  (Yoder et al. 1981) and 1980-1981 (Ohio EPA 1986a).  The study area
 extended for 74.8 miles between the O'Shaughnessy Dam and Chillicothe.  The
 results of these studies are reported and discussed in detail in the
 Comprehensive Water Quality Report (CWQR) (OEPA 1986a).  Much of the
 information presented  in this  section is derived from the the CVQR, unless
 stated otherwise.

     The study area was divided into six segments based primarily on the
 position of major point sources of wastewater and physical features.  The
 limits of these segments are given in Table 2-5.   River segments 3 and 4 are
situated within the Columbus Facilities Planning Area.
                                     2-26

-------
         e
         in

         §K
         Ul
       -1 -•
** ••»   »
-i -•   e
z •-   10
                                  to
                                  in

10-


0-
J
e-


•
»
f
Is-
J
5-
U — '
Si
\s

1996....
1985 —

1979- 1
1980-*-

igai. J







J


«•






^




<•
MM)


1
<



f c
1 i


*
*
•
	 r 	



,
r



j S
i


»
•
i
»
i


I T
1

I













i
(
i
i
i



«
: 	
* <






1

5? 2
x e
1


V 	 1
1- 	 » 	
I
1
r~T
t
...i 	




                                                                                  10
      130          125          120          115          liO          105          100

                      RIVER                            MILE

      FIGURE 2-2.  COMPARISON OF SEGMENT MEAN COMPOSITE  INDEX  VALUES OF
                           THE MIDDLE SCIOTO RIVER MAINSTEM
NOTE:
Based on electrofishing results  during the period July-September 1979,
1980, 1981, 1985, and  1986  (lines and  arrows indicate direction of
change between each year).  Source:  OEPA 1986a.
                                    2-27

-------
         TABLE  2-5.  LOCATION AND DESCRIPTION OF THE SIX RIVER SEGMENTS
  River Segment    Subsequent

       1               1A


                       IB


       2               2A


                       28
      5


      6
                      4A



                      4B



                      4C
      Location and Description

 RH  145.5-138.7; Downstream from O'Shaugnessy
 dam to Grlggs dam.

 RH  138.6-134.0; Downstream from Grlggs dan to
 Dublin Rd. WTP dam.

 RH  133.9-129.7; Downstream from Dublin Rd.
 WTP dam to Greenlawn dam.

 RH, 129.1-127.2; Downstream from Greenlawn
 dam to upstream from Jackson P1ke MUTP.

 RH  127.1-118.9; Downstream from Jackson P1ke
 UWTP  to upstream Columbus Southerly UWTP 002
 raw wastewater bypass.

 RH 118.8-116.7; Downstream Southerly 002
 bypass to upstream from CSOC-P1cway CGS.

 RH 116.6-108 9; Downstream from CSOE-Plcway
 EGS to RH 108.9.

 RH 108 8-99.7, Downstream from RM 108.9 to
 upstream from Container Corporation of
 America (CCA) 001.

 RH 99.6-89 7. Downstream CCA and C1rc1ev111e
WWTP to upstream from Sdppo Cr. (PPG)

 RH 89 6-70 7; Downstream from Sdppo Cr. to
Bridge St. 1n Chllllcothe
Source:  Ohio EPA 1986a.
                                    2-28

-------
     A cumulative  total of  68  species  and nine hybrids  were  sampled  in the
entire 1979-1981 period.  These  species  are  listed  in Table  2-6.   A  total of
72 species and  10  hybrids were sampled for the 1979-1986  study  period.   The
same cumulative numbers were collected in 1986 as for the entire  period,
indicating an increase in diversity  over time.  General indications  of the
relative  tolerance to pollution  of many  species in  Table  2-6 may  be  derived
from Table 2-7.

     In the  1979 sampling,  common carp,  river carpsucker,  and golden redhorse
dominated catch by weight,  comprising  73, 6, and 3  percent of total  weight,
respectively.   In  1980, common carp, river carpsucker,  and the  smallmouth
buffalo dominated  catch by  weight, comprising 66, 11, and  4  percent  of  total
weight respectively.  In 1981, common  carp,  river carpsucker, and  golden
redhorse again  dominated the catch,  contributing 52, 12,  and 9  percent  of
total weight respectively.  In 1986, the catch was  dominated by the  same  three
species as in 1981, with the common  carp contributing 62  percent of  total
biomass,  the river carpsucker  at 11  percent  and the golden redhorse  at  5  per-
cent.  The golden  redhorse  is  considered to  be less pollution tolerant  than
the common carp, river carpsucker and  small  mouth buffalo, and  its gradual
increase in biomass reflects improved  habitat.  The common carp biomass showed
a decreasing trend over the study period, while the river carpsucker showed an
increasing trend,  suggesting improving habitat conditions  (see  Tables 2-6 and
2-7).

     In terms of numbers of fish caught,  the dominant species show more
variation from year to year.   In 1979, gizzard shad, common  carp, and bluegill
dominated the catch, comprising 16,  16,  and 8 percent of  total  numbers,
respectively.  In  1980, the common carp,  river carpsucker, and  green sunfish
dominated catch, accounting for 18,  11,  and 10 percent of total numbers
caught,  respectively.  The  gizzard shad  decreased to 5 percent  of the catch in
1980.  However,  in  1981,  it was once again the most dominant  fish by number,
comprising 27 percent of the total catch.  Other dominant species for 1981
were the common carp and golden redhorse, accounting for 12  and 10 percent of
catch numbers,  respectively.  In 1986,  the gizzard  shad and  common carp
remained the two most dominant species,  followed by the spotfin shiner.  The
percentages of total numbers caught are gizzard shad:  14;  common carp: 12;
                                     2-29

-------
                             TABLE 2-6.  OVERALL COMPOSITION OF THE FISH COMMUNITY  IN THE
                                                 CENTRAL SCIOTO KIVER MAINSTEM
I
U>
o
4peclet H«e
Short note gir Urpltotteus plttotlcmit)
Inngnose D5l95* (fjihrunia)
4horlhr*d redharte (Hoioitaa* Mcrolepjdoluit)
liter redharte (rloiottani cirlnjlua)
Northern hog tut ler'lfli-fienleTlui nlgrlcint)
UMIe tucker (Citotlonul comerionl)
Spotted iutker'(HTnftrr«i «e1inopt|
Co«on)
Creek chub (Srnatllut ilraxcuUtvi)
Swcttrmouth >1niio« (PhentcoETiil •Iribllts)
[•eritd ihlner (ltolropli~ilnerlnoli)ei)
Stlter thlner (Mo(ropJ_i~pnolojtnli J
RotjUce sMner~(fiotroplJ rubellui)
Rote fin thlner (Mofrojtls »rJens)
Striped thtner (Nofroplt chrjrtocephilut)
Sleelcolar thlner {Notfopjt «M jJpUJ |™
SpolMn thtner (Hotroptt <£tloelerut)
S«nd ihtner |Notrop_U ttri«Inegt$~
Mlalc thlner IRoIroplt tolufellut)
BullKttd •lnno«'(PI»fphilet »ljlli« )
ftthetd ilnnoo (Pluejiha^et £ro**\f\\
Bluntnpte •tnno«~(pUephifet noUtMt)
Central ttoneroller ICtiipottuiit «noitlu«)
Cowan c*rp * Gotd'lth
Chtnnel cttMjh Mclilurui Bunttltut)
lellM butlhttd (icIiTurui niUUt)
Broun bullhetd ( Iclilunit'fttlJuloiut)
BUcI bullhrtd (ItUlurui **1«r"~
flit held cit Mth'tfjrl edict li~oll»»rlt)


Rftn
No/ta
.
0 78
-
-
71.77
.
0 31
0 21
0 97
1 74
6 07
0 14
0 94
1 03
S 96
o tt
0 09
0 71
0 37
0 7B
71 07
7 7)
7 47
0 07
0 09
0 B)
.
0 M
0 0?
0 OB
1 SI
0 9?
7 89
0 42
0 12
.
3 46
0 RB
0 IB
0 90
0 07
0 11
0 09
0 09

Mmber
.
0 70
-
.
It. IB
.
0.7)
0 IS
0.77
0 97
4 SI
0 10
0 70
0.77
4 43
0 49
0.07
0 52
0 78
0 SB
IS 67
1.46
1 BO
0.02
0 07
0.61
_
0 OB
0 07
0 06
1 17
0.48
7 IS
0.3B
0.74
.
2 64
0 6S
0 11
0 67
0 OS
0 OB
0 07
0.07
979
nun
Kg/**
.
0.1)5
-
.
1.277
.
0 84)
0.379
1 600
0.748
4 288
0.06S
0 309
0 S9I
2.374
0 121
0 06S
0 141
0 178
0.777
S7 3S4
0 630
0 239
0.001
0 00)
0 001
_
0 001
0 000
0 000
0 079
0 002
0 006
0.001
0 001
.
0 007
0.010
0 126
0 462
0 009
0 018
0 009
0 099

Height

0.19
.
.
I.JI
„
1 18
0.46
2 21
1 04
S 98
0 09
0 4)
0 82
) 31
0 4S
0 09
0 70
0 18
0.38
73 01
O.B8
0 33
O.OO
0 00
0 00

0 00
0 DO
0.00
0 II
0 00
0 01
0.00
0 00

0 01
0 01
0 IB
0.78
0 01
0 0)
0 01
0.14

Kttn
No/ta

1 07
-
0 07
S 30
0.07
0 19
0.46
7 62
1 1) •
II 71
0 OS
1.30
0 78
6 29
0 49
0 OS
0 32
0 69
0.9S
19 3)
7 46
1 20
0 02
0.02
0 8)

a'u
0.11
0 )6
1.31

0.07
0.02
.74
0.18
0.7$
0 95
0 09
0 16
0.07
0 If

I Ijr
Hiwbtr
.
1.01
-
0 0?
S.04
0 07
0 37
0 4)
2 49
1 07
10 65
0 04
1 7)
0 74
S.98
0 46
0 04
0 11
0 66
0.90
18 36
2 34
1.14
0 02
0.02
0.79

0.11
O.II
0.34
1.24

0.07
0 02
0.70
0 17
0.24
0.91
0.09
0 IS
0.07
•.II
1980
Pe«n

0.471
.
0.005
0 493
0 008
0 7B9
0 647
348
672
03)
OIS
74S
44)
704
0 217
0 OS7
0 076
0 37S
0 469
SO IS4
0 954
0 008
0 000
0 000
0 00)

0 000
0 004
0 002
O.OOS
^
0 000
0 000
0 002
0 002
0 238
0.774
0 OIS
0 02S
0.004
0.167

Ueljht

0 46
.
0 01
0 6S
0 01
1 OS
0 B(
4 44
0 89
10 4S
0 02
0 99
0 49
3 58
0 28
0 07
0 10
0 4)
0 62
66 SO
1.26
0 12
0 00
0 M
0 00

0 00
0 00
0 00
0 01
—
0 00
0 00
0 00
0 00
0 12
1 0)
0 02
0 0)
0.01
022

He»n
Ho/la
0 02
0 70
0 04
0 04
29 74
0 09
0 66
0 11
1 6S
0 97
10 18
0 09
1 16
1 IS
10 44
0 59
0 04
1 I)
0 M
0 47
13 22
0 99
1 49
o it
0 70
0 62
0 16
0 26
0 IS
0 99
4 62
Sol
_
.
I.OS
0 70
0 1)
0.97
.
0 02
.
0 04

UL'.r
0 02
0 64
0 04
a 04
24 91
0.08
0 60
0 30
1 49
0 B8
9 39
0 08
1 OS
1 22
* S)
0 54
0 04
1 02
0 62
0 52
11 97
0 89
I.3S
0.26
0 64
0 46
0.37
0 24
0 14
0 B9
4. IB
0 0*
0 0.'
.
.
0 94
0.18
0 12
0 88 \
.
0.02
.
0 04
1981
~NtM
0 01)
0.492
0 004
0 004
2 S91
0 009
1 177
0 371
2 4S8
0 682
7 1S8
0 042
0 841
0 797
S 241
0 2BI
0 002
0 C6I
0 27)
0 )44
29 S94
0 )67
0 026
0 012
0 002
0 00)
0 002
0 Ml
000)
0 008
0.024
8000
.000
.
.
0 004
0 004
0 140
0.788
.
0 OOS
.
0 032

I If
0.02
0.86
0 01
0 01
4.S)
0 02
2 06
0 64
4 10
1.19
12 87
0 07
1.47
1.39
9 16
0.49
0 09
0.81
0 48
0 60
11 75
0 64
0 OS
0.02
0.00
0 M
0 M
0.00
0 01
0.01
0.04
0 M
0 M
.
_
0 01
0 01
0.24
1.38
.
0 01
.
0.06
         NOTE:   Inclusive of RM 14S.5-70.7 and the lower  sections of three tributaries,
                1979-1981.  (Species are  ranked  phylogenetically).
                Source:  Ohio  EPA I986a.

-------
                   TABLE  2-6.  OVERALL COMPOSITION OF THE FISH COMMUNITY IN THE
                                     CENTRAL SCIOTO RIVER MAINSTEM  (CONT.)
Sprclrt Hi«e
Slontrtt (Nnturul Ditul)
Rrlndltd ••dloM (Nuturut nlurul)
Iroul-prrrh (Pfrcopiii oaUttiiircuj)
• rook ilttrrilil* (I'bldeiinr* jicculm)
Uhlle bill (Horonr chrjlopD""
Hhllr cnpplr JfomoJTj innul»r1s)
Blick cnpplr {Pnmnilt nFJiroJUCul itut)
tori htil (Antitonl Mr? ruprtlfls)
SmllMiuth hiM~|Ml(roptrrui dolcHilrul)
^polled but lHlcroptfrut pontlulTlutJ
lirgrraulh biinHltrgpJr.ru} ulioTd'el)
Virwoutb (Irppnll giilotus)
Grtrn tvnflih (le£Oi>K otntllul)
Blurqlll (Ifpwli •iirocMrui)
Onngrtpotird luiifljh (Irpoalt huallti)
Longnr junltsh tlfgwli «M-g«'loHTT'
Piwpklntrrd ll*PO""U «th»oiuil ^
Rlurglll i PumpHmtrd
Crrrn IvnMth l Blurglll
trrtn lunMth « Punpklnirrd
longrir lunflih • Blurglll
Rlurglll i Ortngtipolted funflsb
Crrrn Sunflih * OrtngrtpottH
PuBpktnirrd i longrtr Sunfljh
Onnjrtpottrd * PuBpklntpH
Stugrr (Stlioitrdlon cintdrnte)
Hiliryr fStliot IrJTon i njjru»)
Crrrnilde dirtrr (ftheottiMt Mrnnloldft)
Rilnbov dirtrr |llhfoito«i CttniTru;]
rr»jh«»trr dru* tAflo^lnolut grunnlent)

Hrtn
No/ta

0 07
0.16
1 25
5 92
1 30
3 00
4.75
0 79
7 78
0 09
8 48
10 57
3 29
6 76
7 81
0 02
0 09
.
0 02
0 18
.
-
.
1 09
0 16
0 65
0 07
0 OS
.
0 86

Nuaber

0.05
0 1?
0 91
4 40
0 97
2 73
3,53
0 71
7 07
0 07
6 30
7 ftf
2 44
4 65
2 09
0 02
0 07
-
0 02
0 11
.
.
.
o ai
0 12
0 48
0 02
0 04
»
0.64
1979
Hrtn
Kg/ta

0 002
0 001
0 102
0 768
0 061
0 278
0,564
0 012
0 818
0 004
0 710
0 456
0 045
0 151
0 121
0 001
0 006
.
0 001
0 005
.
.
.
0 318
0 033
0.009
0 000
0.000
m
0.599

% 8]r
Height

0 00
0.00
0 14
0.37
0 09
0 39
0.79
0.02
1 14
0 01
0 79
' 0 64
0 06
0.21
0.17
0 00
0 01
-
0 00
0.01

-
.
0 44
O.OS
0 01
0 00
0 00
•
0.84
Dlitince Tithed 42 05 ka


Number
Ngaber
or Specltl 58

Nr«n
No/la

.
;
0 It
1 27
7 11
1 49
1 16
0 10
2 08
0.02
10 62
8 90
0 94
4 70
1 50
.
o la
0.74
.
0 OS
0 14
0 02
.
0 52
009
0 02
0.02
0 07
0.02
1.12
1980
HMber Kg/la
• *•
* .
— •
0 II 0 009
1.10 0 119
2 71 0 140
1 12 0 378
3 00 0.118
0 09 0 007
1 97 0 691
0 02 0 001
10 09 0 174
8 46 0 154
0 90 0 024
1.99 0 152
1 42 0 054
. .
0 17 0 009
0.70 0 047
.
0 04 0 001
0 11 0 008
0 02 0 001
. »
0 49 0 182
0 09 0 026
0 02 0 000
0 02 0 000
0 07 0 000
0 02 0 000
1 .06 0.662

I Bjr
"eight

«.
•
0.01
0 16
0.19
0 41
0 45
0.01
0 92
0.00
0 50
0.47
0 01
0.20
0 07
.
0 01
0 06
•
0.00
0 01
0 00
•
0.74
0 01
0.00
0 00
0.00
0 00
O.M
DUUnci ritfcetf 42 91 ta
Number
of Hybrid* S dumber
•f Specie* 57
• f N/fcrMl 6

ieiB I Ijr
Ne/ta Nu-ber
0.02 0.02
•F ^
0.02 0.02
0 04 0 04
0.07 0.06
0 67 0 61
0.55 0 50
2.59
2.90 ,
0.51
1.36
1.14
6.80
0.7?
1.76
0.44
.
0.02
0.09
•
•
O.IS
-
0.04
0.51
0.11
0.09
35
.41
48
21
*84
.15
70
59
40
.
02
.00
•
.
.14
-
.04
.48
.12
.08
• *
0.09 O.OB
. .
0.7} 0.70
1981
MM >i if
tj/fa Might
0 001 0.00
* •
0.000
0.000
0 008
0.050
0 052
0.155
0,152
0.029
0.120
0.128
0.164
0 018
0.054
0022
.
0.001
0.009
•
.
0 Oil
-
0 002
0.222
0 104
0.002
00
.00
01
09
09
.62
62
.05
56
*17
64
07
09
.04
•
00
02
•
-
02
-
00
.39
18
.00
-
0.001 0 00
. .
0.558 O.M
DIlUnc* Flitted 45.25 km
•umber *f Spec let U
Hw*ir »f H/krldl S
                                                     CMiUtUn Sf«l«*  *•
NOTE:  Inclusive of RM  145.5-70.7 and the lower  sections  of three tributaries,
       1979-1981.  (Species are ranked phylogenetxcally).
       Source:  Ohio EPA 1986a.

-------
             TABLE 2-7.  SPECIES GROUP DESIGNATIONS USED TO ASSESS
                 COMMUNITY  COMPOSITION PATTERNS IN THE MAINSTEM
                      SCIOTO RIVER AND MAJOR TRIBUTARIES.
      Group                       Species  of  Genera  Included


        GS       Gizzard  shad  (Dorosoma)t   omnivores,  highly pollution  tolerant

        G        Carp,  goldfish  (Cjrpjrinus,  Carrasius):   omnivores,  highly
                pollution  tolerant

        R        Round-bodied  catostomidea  (Moxostoma,  Hypentelium,  Minytrema,
                Catostomus);  insectivores, moderately to  highly  polluttion
                intolerant

        C        Deep-bodied catostomidea (Carpiodes,  Ictiobus);   mixed
                omnivores and insectivores -  moderately pollution tolerant

        M        Minnows, chubs  (Semotilus, Pimephales,  Hybopsis,  Nocomis,
                Phenacobius,  Campostoma):  insectivores, herbivores,
                generalists - most highly  intolerant  to intolerant  but some
                highly pollution  tolerant

        N        Shiners  (Notropis, Notemigonus);   insectivores -  highly
                pollution intolerant  to moderately pollution  tolerant

        B        Basses,  crappies  (Micropterus, Pomoxis);   top carnivores,
                moderately pollution  intolerant

        S        Sunfishes (Lepomis);   insectivores,  top carnivores, highly
                pollution tolerant to  moderately intolerant

        F        Catfishes, drum (Ictalurus. Pylodictis,  Aplodinotus);   top
                carnivores, insectivores,  one piscivore -highly  to moderately
                pollution tolerant

        V        Sauger, walleye (Stizostedion);  Piscivores

        W        Large River (Horone, Alosa, Hiodon);   piscivores

        L       Gars (Lepisosteus);  piscivores

       0       Other  (rare and uncommon species not included in abovde group
               designations)


NOTE:  Information on feeding preferences and selective level of pollution
        tolerances is included when known.

SOURCE:  Adapted from Ohio EPA 1983a.
                                     2-32

-------
and spotfin shiner: 10.  The most recognizable  trends are  that gizzard shad
fluctuated annually while  the common carp exhibited a gradual decline.  Of the
other species mentioned, the golden redhorse is  the least  pollution  tolerant.

     OEPA used percent similarity and relative  community composition  to assess
changes in the composition of the Scioto River  fish community over the 75 mile
study area.  Similarity matrices shoved a three-year trend of decreasing
faunal organization in the upstream segments and increasing similarity in the
lower reaches.  The Ohio EPA indicated that this data may  reflect increased
stresses upstream  from Columbus and improved conditions downstream.   However,
this postulate is  not entirely consistent with OEPA water quality discussions
(OEPA 1986a and 1986b), which suggest improving water quality conditions in
upstream segments  attributed to improvements in wastewater treatment.

     Notable differences in community composition exist between the six river
segments studied.  In terms of total biomass, the 1980 fish community sampled
from Segment 1 (see Table 2-5 for key to segments) was dominated by carp-
goldfish (G), round-bodied Catostomidae (R), bass-crappie  (B), and sunfish (S)
groups.  (Refer to Table 2-7 for key to lettered species designations.)  The
remaining segments, including the Columbus study area, were each comprised
mainly of carp-goldfish (G) and deep-bodied Catostomidae (C) groups (over
80 percent combined biomass).  The round-bodied Catostomidae (R) and catfish-
drum (P) groups increased in their contribution to total biomass further
downstream in Segment 6.  Numerically, there was a gradual downstream shift
from a sunfish (S), bass-crappie (B), and round-bodied Catostomidae (R) pre-
dominant composition to a carp-goldfish (G) and deep-bodied Catostomidae (C)
community.  Data from 1979 (Yoder et al.  1981) exhibited very similar commun-
ity composition to that found in 1980.

     Compositional differences in fish communities between the six river seg-
ments studied in 1981 are characterized in Figures 2-3 and 2-4.  Comparing the
1980 and 1981 data, a noticeable change occurred in Segment 1 in 1981, with
the round-bodied Catostomidae (R) replacing carp-goldfish (G) as the
predominant group  in terms of total biomass.  Numerical composition in 1981
also differed from that of the previous year.   In Segment 1,  the round-bodied
Catostomidae (R) and gizzard shad (GS) groups were equal in compositional
                                     2-33

-------
                                                     hllllcotM *•«"•" ««•••• T'T>
       FIGURE 2-3.   COMPOSITION OF THE FISH COMMUNITY BY NUMBER IN THE
                             CENTRAL SCIOTO RIVER MAINSTEM
NOTE:  Study area based on numbers during July-October 1981.   Species group
       symbols are those given in Table  2-8.  The  size of  each circle is
       proportional to the mean density  (numbers/km)  of fish in each segment.
       Source:  Ohio EPA 1986a.
                                     2-34

-------
          «.«».* 2 tl»l • UT2I
        FIGURE 2-4.   COMPOSITON OF THE FISH COMMUNITY BY WEIGHT IN THE
                                CENTRAL SCIOTO RIVER MAINSTEM
NOTE:  Study area based on weight during July-October 1981.  Species group
       symbols are those given in Table 2-8.  The size of each circle is
       proportional to the mean biomass (kg/km) of fish in each segment.
       Source:  Ohio EPA 1986a.
                                    2-35

-------
 dominance  to  the  sunfish  (S)  and  bass-crappie  (B) groups.  The  fish community
 from Segment  2  through 5,  including  the Columbus study area, was dominated by
 the  gizzard shad  (GS),  carp-goldfish (G), and  deep-bodied Catostomidae  (C)
 groups.  The  sunfish  (S)  group  was equally  important above the  Jackson  Pike
 WWTP,  in Segment  2.

      Compared to  the  1979 and 1980 data,  the 1981 data showed a predominance
 of the pollution-tolerant groups  (C  and G)  downstream from Columbus.  In
 general, these  results  indicate somewhat  improved conditions in this section
 of the mainstern.

     The composite index  (Gammon  1976), which  incorporates density, biomass,
 and  the Shannon index (a  diversity index),  was used to evaluate the overall
 condition of  the  fish community.  The composite index values were  plotted
 against river mile for  the 1979,  1980, and  1981 results.  The results of this
 comparison are  depicted in Figure 2-5.  The mean number of species per  zone
 was  also plotted  against  river  mile  for this same period.  The  results  of this
 second comparison are depicted  in Figure  2-6.  Downstream from  the Jackson
 Pike WWTP, the  composite  index  values declined.  In 1979-1980,  similar  pat-
 terns  of gradual  decline,  followed by a gradual recovery, occurred downstream
 from the Jackson  Pike WWTP, the Columbus  Southerly WWTP, the Container  Corpor-
 ation  of America, and the  Circleville WWTP.  This pattern was weakly evident
 in 1981.  The mean composite  index values in 1981 were considerably lower than
 in previous years, especially immediately downstream from Greenlawn Dam.

     A comparison of  mean  composite  index scores for 1981, 1985, and 1986 is
 shown  in Figure 2-7.  From 1981 to 1985, all stations improved, particularly
 those  between Southerly and Walnut Creek.   Not only do these stations have
higher overall values, but the decline apparent in 1981 is also less pro-
nounced in 1985.

     The composite index  is used  to assess  structural characteristics of fish
communities,  which are described  in  terms of biomass,  abundance, and
diversity.   The OEPA has also analyzed fish sampling results using the  Index
of Biotic Integrity (IBI)  (Karr 1981, Fausch et al.  1984;  as cited in OEPA
1986a) which  incorporates  both structural and functional characteristics in
                                     2-36

-------
      50     I40    130    120     110     100     90     80     70     60
FIGURE 2-5.   LONGITUDINAL  TREND OF  THE  MEAN  UNO STANDARD ERROR) COMPOSITE
                    INDEX  IN THE CENTRAL SCIOTO RIVER MAINSTEM
NOTE:   Sampling period from 1979 through 1981.  Shaded areas indicate
       boundaries  and  overlap between  biological criteria classes.  (Open
       circles  represent  tributary  location  values).  Source:  OEPA 1986a.

                                   2-37

-------
         (A

         O
I
o

I
o
I
                      *       o
                    60
                    oM »
                    oo £
• a. _
Sto
                     o >
? ;. g   ooo
o Tg * S   « w*
s:if   ^^«
5 «5* "
                             u o a u
                                          ? u
                                         ?o t
                                         £uu
                                                     o
                                                     Ok
                       O
                       a.
   20-
    10
LU

U
yj
a.
co
                                                                     1981
   20-
u.
o

a:
u
03
15-
   ID-
                                                                 1980
   20-
    15-
   10-
    5-
                                                                     1979
       ISO
FIGURE 2-6.
          I40     130    120     110     9O     8O

                                 RIVER MILE
                             70
                                                  60
                                                    50
         LONGITUDINAL TREND OF MEAN C+SE) NUMBER OF SPECIES/ZONE IN THE

                     CENTRAL SCIOTO RIVER MAINSTEM
NOTE:  Study conducted during the  1979 (bottom),  1980  (middle),  and 1981

       (top) sampling periods (open  circles represent  tributary location

       values).   Source:  Ohio EPA 1986a.
                                    2-38

-------
                     *
                                          3 «
                                            u
                                          i! i
                                          i *
                                          ! o
                                          u 5
                                          i	i
                                                                 §
                                                                 C9
               10

                9

                B
            X
            UJ
   10

    9

   '6
w
t  6
Is
                        Exceptional
                                                                      •10

                                                                      9

                                                                      •i
                  >*«teV.  •   .  *. *s v.%tf ^ i^% «V
             Fair
                                                                      •6
                                          ^ A >vuW %v*Wv* %
                                                             ~^SVK»>V*(^K»MI>MM^II9S«%W«  •«.
                                                              Exctptonai
•to
9
                                                            fb/r
      130
                              RIVER                        MILE
 FIGURE 2-7.  COMPARISON OF MEAN (AND STANDARD ERROR) COMPOSITE INDEX VALUES
NOTE:  At sampling locations in the  central  Scioto River  mainstem based on
       sampling conducted in the summers  of 1981, 1985,  and  1986.  (Shaded
       areas separate biological criteria category boundaries).
       Source:  OEPA 1986a.
                                                                             100
                                         2-39

-------
 the assessment of aquatic communities.   The characteristics,  or metrics,  used
 in the IBI,  are listed in Table 2-8.   Each sampling location  is assigned  a
 score of 5 (best), 3,  or 1 (worst) for each metric, based on  the criteria
 shown in Table 2-8.   The scores are then added  and  the total  used to describe
 the fish community at  that particular sampling  location.   The highest possible
 index score  is 60, which would describe a virtually undisturbed habitat  in a
 pristine environment.   Scores above 50 are excellent.   Scores between 20  and
 30 indicate  an impacted community with little structural  and  functional
 integrity.

      Scores  for selected sampling locations are shown  in  Table 2-9.   Scores in
 the 20-30 range were much more common from 1979-1981 than from 1985  to 1986.
 In 1985  and  1986,  most  stations had scores in the 36-44 range,  indicating
 marginally good to good conditions,  but with some problems remaining.  The
 metrics  which  reflected problems in the aquatic community were as follows:
 higher portion of  hybrids,  higher incidence of  external anomalies, higher
 percentage of  omnivores,  and  lower percentage of round-bodied suckers  and/or
 insectivorous  species.

      While all stations improved over time,  some longitudinal trends persisted
 throughout the study period.   The station immediately  below the Whit tier  St.
 CSO  (RH  129.1)  was always higher on both indices than  all stations between
 Jackson  Pike and Southerly (RH 126.4-RM 119.9).  The station  just below South-
 erly  (RH 118.1) always  scored  higher  than the station  just  upstream  from  it
 (RM  119.9).  This  observation  correlates  with modeling information in  the CVQR
 which shows that the dissolved oxygen sag below Jackson Pike  reaches its  low-
 est  point just  above Southerly.

     From RM 118.1 to RM  109.2,  the Index  of  Biotic  Integrity declines in all
years but the delcine was more prounounced  from 1979-1981  than  from  1985-1986.
This  trend is also evident  in  the Composite Index.   According  to  the CWQR,  the
gradual decline in dissolved oxygen concentration below Southerly is primarily
 responsible for the decline in structure  and  function  of  the  fish community
 throughout this segment of  the  river.  These  conditions are probably linked to
 the impacts of  the Southerly VWTP discharge.
                                     2-40

-------
              TABLE 2-8.  METRICS AND NUMERICAL RANKINGS USED IN
                         THE INDEX OF BIOTIC INTEGRITY
Metric
Cumulative Species
Numbers/km*
Sunfish Species
Sucker Species
Intolerant Species
% Round-bodied Catostomids
% Omnivores
% Insectivorous Cyprinidae
& Catostamidae
% Carp/Goldfish
% Top Carnivores
% Hybrids
% Anomalies
5
>35
>350
>6
>8
>9
>40
<25
>30
<5
>10
<0.5
<0.2
3
22-34
175-350
3-6
4-8
5-9
15-40
25-50
10-30
5-20
5-10
0.5-3
0.2-3
1
>22
<175
<3
<4
<5
<15
>50
<10
>20
<5
>3
>3
"less than 50 individuals/km scores 1 in all proportional metrics.

Source:   Adapted from table provided by Yoder,  January 1987a.
                                     2-41

-------
           TABLE 2-9.  INDEX OF BIOTIC INTEGRITY (IBI) SCORES FOR THE
                               SCIOTO RIVER MAINSTEM
River
Nile
129.1
126. 4
122.9*
119.9b
118.1
117.1
m.ec
109.2
108.8
d
104.8
102.0
100.2
1979
32
22
24
26
34
22
6
-
8

10
46
32
1980
34
26
30
22
36
26
26
-
14

36
40
28
1981
26
22
28
26
32
26
24
-
26

32
38
22
1985
34
24
32
32
44
44
36
42
38

44
46
40
1986
36
32
40
34
44
36
36
44
36

44
48
44
 a    RH 123.3 1n 198S and 1986.
 *>    Moved to RH 119.0 \n 1986.
 c    RN 114.0 1n 1979 and RM 113.5 1n 1985 and 1986
 
-------
      The  sampling station below the Whittier  St.  CSO (RM 129.1)  showed  little
 improvement  from 1979  to  1986  on the IBI  scale, although the composite  index
 for  that  station (Figures 2-5,  2-7) and for the segment  including that  station
 (Figure 2-3)  showed  considerable improvement.  This  indicates that  the  commun-
 ity  is more  impacted functionally than structurally.   Improvements  at the
 Vhittier  Street  CSO  site  were  due to increased numbers of  fish and  increased
 diversity, which included an increase in  numbers  of  desirable groups (such as
 sunfish)  and  pollution tolerant species.   Despite this improvement, no  new
 insectivores  moved in  and the  percentage  of ominvores  and  hybrids increased.
 As a result,  the community supports a large number of  individuals and species,
 giving it a high structural rating,  but the species  are  predominantly pollu-
 tion and  silt  tolerant.   Inc dence  of external anomalies and  percentage of
 sunfish hybrids  were consistently high and resulted  in lower  IBI  scores.

      The  IBI  scores  for the sampling station below Jackson Pike  (RM 126.4)
 were lower than  those  below the CSO for all years, but showed  more overall
 improvement from 1979  to  1986.   Composite  index values for this  station were
 also lower than  for  those just  below the CSO.  Effluent  loadings  of BOD, TSS
 and  NH3-N showed increases  or  remained about the  same  over this  time period
 but  loadings  of  chlorine  decreased,  although levels are still  considerably
 high.  Reduction in  chlorine may  account from some of  the  noted  improvement  in
 IBI  scores below Jackson  Pike.

      The  metrics  accounting for improvement at the Jackson Pike station were
 number of species and  number of  fish  per kilometer.  New species which  moved
 into  the area and contributed  to  increased diversity were  sunfish and intoler-
 ant species.  The percentage of  top  carnivores increased and  the percentage of
 omnivores decreased,  which  improved  the community functionally.  Metrics
 indicating continuing  problems  at the station were a substantial increase in
 percentage of anomalies, disproportionately small numbers of  the round-bodied
 catostimid group, and disproportionately large occurrences of hybridization
among species.

     At the station  immediately below Southerly (RM 118.1), metrics reflecting
 improvement included increased density,  and increased numbers of sunfish
species,  intolerant species and sucker species.   A portion of the increase in
                                     2-43

-------
 sucker species was due to increases in numbers of  round-bodied  catostimids,
 which is one of the more sensitive types of suckers.   It  is  noted  that  while
 the percentage of anomalies did not increase on the metric scale,  despite  the
 increase in pollution tolerant  species,  this station  had  a consistently high
 percentage of anomalies in all  years.   The percentage of  anomalies actually
 showed some reduction in percentages from 1979-1986.

      The station at RM 108.8 reflects  the impacts  of  decreasing dissolved
 oxygen downstream from Southerly.   This  station is situated  where  DO
 concentrations whould be near their lowest (i.e.,  near the maximum DO sag).
 Metrics from 1979 reflect this  observation,  being  very low in all  categories
 except percent anomalies,  percent  hybrids,  percent top carnivores  and number
 of  sucker species.   The more sensitive sucker species are not represented.
 From 1979 to 1986,  eight out of eleven categories  improved on the  metric
 scale.   This station is typical of most  stations below Southerly in that it
 showed substantial  improvement  over time.

      In summary,  both indices show that  the fish communities improved over
 time at all  stations.   The greatest improvement occurred  below  Southerly and
 the  least  occurred  between the  Vhittier  St.  CSO and Jackson  Pike.   The  segment
 between Jackson Pike and Southerly showed  moderate improvement.  These  results
 correlate  well with the fact that  reductions  in waste water  loadings were
 greatest  below Southerly in the referenced  time period.

      The  stations in the river  below Southerly  show the greatest increase in
 IBI  scores and  composite index  scores  over  time.   The improvement  is
 attributed to  reductions in loadings of  BOD,  solids,  and  ammonia,  which
 reduced  the  severity of  oxygen  depletion.  The  reductions  were  primarily a
 result of  decreased  bypassing at Southerly.   Loadings  of  chlorine  also
decreased  at Southerly during this  time  period, further reducing stress-
 inducing factors to  the  aquatic environment below  Southerly.

     The frequency of external anomalies among  individual  fish  from  1979-1981
(all species combined) was  assessed in the study area as a possible  indication
of sublethal stress  based on data in Table 2-10.  The  incidence of external
anomalies  ranged from as little as 9 percent  in Segment 1  (1979 and  1980) to
                                     2-44

-------
      TABLE  2-10.   INCIDENCE OF LESIONS, TUMORS,  FIN EROSION,  AND EXTERNAL
                      PARASITES AMONG INDIVIDUAL  FISH COLLECTED IN SIX
                              SEGMENTS  OF THE  SCIOTO RIVER
Segment
Segment 1
{RM 145.5-134.0)
Segment 2
(RM 133.9-127.2)
Segment 3
(RM 127.1-118.9)
Segment 4
(RM 118.8-99.7)
Segment S
(RM 99.6-89.7)
Segment 6
(RM 89.6-70.7)
Olentangy River
(RM 132.3, 0.5)
61g Walnut Cr.
(RM 117.2, 0.5}
Walnut Cr.
(RM 106.1, 0.4)
Number of F1sh Affected/
Total Number of Fish
1979
0/1839
62/1256
3/309
3/709
3/281
4/901
11/261
0/134
1/42
1980
0/1177
29/1005
6/273
38/1075
2/185
3/327
0/179
1/181
7/126
1981
11/991
47/996
4/381
54/1360
3/277
7/608
15/162
9/186
4/33
Percent Affected
1979 1980 1981
0% OX 1.2X
4.9X
1.0%
0.4X
l.OX
0.4X
4.2X
OX
2.4X
2.9X
2.2X
3.5X
1.1X
0.9X
OX
0 6X
5 6X
4.7X
1.1X
4. OX
1.1X
1.2X
9.3X
4.8X
12 IX
Source:  Ohio EPA 1986a.
                                   2-45

-------
 as much as 12.1 percent in the mouth of Valnut  Creek.   Located upstream of the
 Jackson Pike WWTP,  fish in Segment 2 consistently had  high affliction rates
 ranging from 2.9 percent in 1980 to 4.9 percent higher than background in
 1979.   Since this segment is partially impounded,  it has  a tendency to
 exaggerate the impact of intermittent inputs  of heavy  metals,  oxygen demanding
 wastes,  and other detrimental substances.   Segment 4,  which receives loadings
 of oxygen demanding wastes from the Southerly WWTP, had high percentages of
 affected fish in 1980 (3.5 percent) and 1981  (4.0 percent).   These results
 correspond well with the degradation implied  by the composite index.

     OEPA developed a method combining the  composite index and narrative
 biological criteria to evaluate the condition of the central Scioto River
 mainstern based on the 1979-1981 data.   Based  on these  evaluations,  the primary
 cause  of observed negative effects on the mainstem fish community was deter-
 mined  to be the change in water quality attributable to point  sources of
 wastevater.   Less serious effects  were attributed  to urban and possibly
 agricultural nonpoint sources.   Physical factors identified included river
 discharge,  the influence of tributaries and dams,  and  variable habitat
 quality.

     Of  the 38 total active point  sources located  in the  mainstem study area,
 the Jackson Pike  WWTP and the Columbus Southerly WWTP  were identified as
 having the greatest  impact  on the  mainstem  fish communities.   The primary
 impact was from the  discharge of oxygen-demanding  wastes,  which resulted in
 lower  dissolved oxygen concentrations  downstream from  each WWTP.   In
 combination with  elevated concentrations of ammonia and zinc,  the low
 dissolved  oxygen  levels  depressed  fish community diversity and abundance,
 resulting  in a fish  fauna comprised  of predominantly tolerant  species.

     OEPA  considers  the  potential  for  the full  recovery of  the central Scioto
River mainstem fish  communities  to be  good, primarily  because  of  the  existence
of the high  number of  relatively undamaged tributaries  (which  provide  a  refuge
 for endemic  species)  and  the  apparent  lack of serious  residual  effects  (i.e.,
habitat modification,  contaminated sediments) in the mainstem.  The main  trib-
utaries expected  to  contribute  to  the  recovery are Big Walnut Creek, Walnut
Creek,  Big Darby Creek, and Deer Creek.  The recovery observed  in the  vicinity
                                     2-46

-------
 of the Columbus Southerly WTP in 1980 and 1981 was considered partially a
 function of the availability of Big Walnut Creek as a refuge and repopulation
 epicenter.   Tributaries undoubtedly played a part in the observed recovery
 upstream from Circleville in 1981.   This location vas in close proximity to
 both Walnut and Big Darby Creeks.   The continued recovery of the mainstern fish
 communities,  however,  is dependent  on efforts aimed at further reducing point
 source loadings of BODS, NH3-N,  suspended solids,  and other  detrimental
 substances  (OEPA 1986a).

 Fisheries:   Tributaries to the Scioto River
      Alum Creek,  near  the Franklin  County line,  supports 51  species of fish.
 Minnows,  including the rosyface shiner,  the bluntnose minnow,  and the  stone-
 roller minnow,  are the most  abundant.   Also found  in large numbers  is  the
 orange-spotted  sunfish.

      Nine of  the  47 species  of fish in Hellbranch  Run are found  along  the
 entire length of  the stream.   Several  of the  species occurring in this stream,
 including shiners and  minnows,  are  characteristic  of prairie streams such as
 Hellbranch  Run.   These streams are  frequently turbid,  rich in  organic  matter,
 and  have  a  lover  gradient  (Phinne 1967).

      Of  the 74  species of  fish that  occur  in  Big Walnut  Creek, six  species,
 including the endangered muskellunge,  are  introduced.  Two other  endangered
 species listed  by the  Ohio Department  of Natural Resources (ODNR)  that  occur
 in Big Valnut are the  blacknose  shiner and  the American  brook  lamprey.  The
 large  population  of  minnows  in the  stream  serves as  a source of  food for  other
 fish  (Cavender and  Crunkilton  1974).

     Due  to its high water quality and diversity of aquatic habitats, Big
Darby Creek supports an  unusually large variety of fish.   One Federally
endangered species  (Scioto madtorn) and several State-endangered species have
been found in Big Darby  Creek  (bigeye  shiner, river redhorse,  tippecanoe
darter, sand darter, and silver lamprey) (Cavender 1982).  During the 1981
Scioto madtorn survey, Cavender (1982) collected 59 species, representing 80
percent of all species recorded for a 10-year period.
                                     2-47

-------
 Hacroinvertebrates
      Benthic macroinvertebrates have been widely  used  in  pollution  studies
 involving flowing waters since they have a number of characteristics  that make
 them useful indicators  of water quality.   They  form permanent  or  semi-
 permanent stream communities,  are  less  transient  than  fish,  are less  sporadic
 in occurrence than microrganisms,  and usually occur in statistically
 significant numbers.  Species  composition and community structure of  benthos
 are determined by environmental factors that have existed throughout  the life
 span of  the organisms.   Consequently, most types  of pollution  can alter the
 existing community structure.

      A number of macroinvertebrate studies have been conducted in the Scioto
 River during the past 15 years (Olive and Smith 1975 cited in  OEPA  1986a).
 The most recent  survey  was conducted by Ohio EPA  in 1981.  A summary  of these
 findings and a detailed comparison to previous studies are contained  in the
 CVQR (OEPA  1986a).

      Figure 2-8  illustrates  the number  of benthic macroinvertebrate taxa
 collected at stations along  the Scioto  River in 1974,  1980,  and 1981.
 Community composition and density  of benthic macroinvertebrates between RM 130
 and  RM 106  reflects considerable variability. In  general, the  numbers of taxa
 are  depressed in a stretch of  the  Scioto  between  Uhittier Street  CSO/Jackson
 Pike WVTP and Southerly,  with  rapid  recovery at the confluence of Big Walnut
 Creek. Below Big Valnut  Creek,  the numbers of taxa remain relatively  constant.
 The  rapid recovery at the confluence of Big Valnut Creek  is  believed  to result
 from benthos  repopulating the  Scioto as "drift" from the higher quality
 aquatic  environment of  Big Valnut  Creek.

      Data from 1980 and  1981 are typified  by the  general pattern  described
above.  Data  from 1974 also reflected the  characteristic decline  from Whittier
Street/Jackson Pike through Southerly; however,  the downstream recovery was
much more gradual, and  the numbers of taxa did not return to the  upstream
levels until  much further  downstream  (below Deer  Creek).  This observation
correlates well with water quality records and other observations which indi-
cate  improved habitat conditions in  the downstream Scioto in recent years.
                                     2-48

-------
            FIGURE 2-8.  NUMBER OF BENTHIC MACROINVERTEBRATE TAXA
NOTE:  Collected from artificial substrata/samplers in the central Scioto
       River raainstera study area  in  1974, 1980, and 1981.
       Source:  Ohio EPA  1986a.
                                      2-49

-------
 Reductions  in  bypassing at  Southerly during low  flow periods in 1981 and
 higher  effluent  qualities are  hypothesized as  influencing  the  improvement  in
 benthos (OEPA  1986a).

      Most recent raacroinvertebrate  data  (1981) reflected strong improvement in
 water quality  compared  to past sampling  efforts, especially these by Olive in
 1969  and OEPA  in 1974.   Stations downstream from the Columbus  WWTP  in  these
 surveys reflected severe water quality degradation while comparable 1981
 stations had consistently higher diversity, larger number  of taxa,  and
 improved species composition.

 Mollusks
      Mollusk populations of  the Scioto River have not been thoroughly  sampled
 and described  since Biggins  (1856).  Fauna below the VVTP  effluent  discharges
 are considered significantly reduced and almost  nonexistent (Stansbury 1986).
 Stansbury indicated that sampling between 1955-1970 revealed some species  of
 mollusks in the  banks of the Big Darby Creek near its confluence with  the
 Scioto  River and  within  the Circleville Riffle,  a mixing zone  of the Scioto
 River and Big  Darby Creek.  Some species were also found in Big Walnut Creek.
 No species of  mollusks were found in the Scioto  River proper.  Stansbury noted
 that relatively good fauna may  be found above and below areas  significantly
 influenced by  WWTP effluent, particularly above  the Jackson Pike WWTP.  The
 potential for  reestablishing a  viable mollusk population through the removal
 of inadequately  treated  WWTP effluent may be good,  although other limiting
 factors  (e.g., pesticides) may  affect the repopulation of  these areas.

 2.1.4.3  Wetlands
     National  Wetland Inventory Haps are not available for the Columbus area;
however, several of the  soil series within the FPA indicate good potential for
wetland habitat.  These  series  include Carlisle,  Condit, Kokomo, Montgomery,
Pewamo,  Sloan, and Westland.  Using these series as an indication of wetland
coverage within the FPA, an estimated 15.7 percent  of Franklin County  could
potentially be comprised of wetlands.   If these lands are used for agricul-
 tural purposes, they may not be designated wetland  areas within State  or
Federal regulatory jurisdiction.  The Scioto River  wetlands appear to have
                                     2-50

-------
been considerably altered, as evidenced by shoreline development, dikes,  and
the presence of large ponded areas adjacent  to  the river, but separated  from
the river by roadfills.  A corridor of forested and emergent floodplain  and
wetland species is present throughout most of the length of the study area.
Further informtion on wetlands is presented  in chapter 6.

2.1.4.4  Endangered and Threatened Species
     Appendix H lists all rare animal and plant species known to occur or with
the potential of being found within the FPA.  Federal and State status of
these species are provided.

Plants
     Several Ohio State threatened plant species have been sighted in the FPA
based on records of the ODNR Natural Heritage Program.  The locations of  these
plants in the FPA is well removed from the Scioto River, so they should not
suffer from direct impacts.  The sighted species are the following:  Narrow-
leaved Toothwort (Dentaria mulfida), Three-birds Orchid (Triphora triantho-
pora), Prarie False Indigo (Baptisia lactea), Spider Milkweed (Asclepias
virdis), and Showy Lady's-slipper (Cypripsadium reginae).

Terrestrial Animals
     Four Federally endangered animal species may be present within the FPA.
These species are the Indiana bat (Myotis sodalis), the bald eagle (Haliaeetus
leucocephalus), the peregrine falcon (Falco peregrinus), and Kirtland's
warbler (Dendroica kirtlandii).

     The Indiana bat was sited in Pickaway County and it is likely that  it may
be found within the FPA (Multerer 1986).  The Indiana bat winters in caves and
is found along streams and adjacent woodlots during summer.   The Indiana  bat
has been found to use loose bark of a dead tree for the nursery roost, but
sometimes the bats temporarily move to the bark crevices of a living shagbark
hickory tree (Humphrey et al. no date).
                                     2-51

-------
      Both the bald eagle and the peregrine falcon have been recorded within
 the FPA (Thomson 1983).   All of the Federally endangered  bird  species migrate
 through the FPA,  but  none of these species has been  known to nest  in Ohio
 (Multerer 1986;   Ohio Department of Natural Resources  1983).

 Hollusks
      None of the Federally endangered bivalve mollusks are expected  to be
 found within the FPA  (Multerer  1986).  However,  13 of  the 16 unionid mollusks
 listed by Ohio as endangered animals have  been recorded from the Scioto River
 below Columbus,  Ohio  (Stansbury 1986).   The endangered unionid mollusks
 recorded below Columbus  are listed in Appendix H.  One of these species,
 Lampsilis orbiculata  (pink mucket pearly mussel),  is also listed as  a
 Federally endangered  species, but has not  been recorded in the area  in the
 recent past.   Based on records  of the ODNR Natural Heritage Program,  only five
 of  the species listed in Appendix H have been sighted  in  the FPA since 1950.
 These species  are:  Simpson's Shell,  Cob Shell,  Club Shell,  Northern Riffle
 Shell,  and Fragile Heelsplitter (Stansbury 1987).

 Fishes
      No  Federally endangered  fish species  are expected to occur within the
 mainstern Scioto River in the  proposed impact  area  (Multerer  1986).   Only one
 Federally endangered  fish,  the  Scioto madtorn  (Noturus  trautmani),  is  found
 within the Facilities Planning  Area.   However,  this  species  is found  only in
 Big Darby Creek.

     The Scioto madtorn (Noturus trautmani)  is  a  fish species endemic  to the
 facilities  planning area which  is FPA listed  as  both Federal and State
 endangered.  This  particular species  is  considered endemic to  Big  Darby Creek.
 Cavender  (1982) conducted  a 1-year  survey  (Nov.  1981-Oct  1982)  on  Big Darby
 Creek  in  an attempt to find  the extant population  of the  Scioto madtorn;  how-
 ever,  this species was not collected  and has not been  collected to date
 (Cavender  1986).  Assuming  the  Scioto madtom  is not  extinct, Cavender (1982)
hypothesized that  it  lives in the lower end of Big Darby Creek,  but  is  so rare
 that in most years it cannot be  sampled by seining.  The other  hypothesis is
 that the  Scioto madtom no longer  lives in Big Darby  Creek  (its  habitat  was
                                     2-52

-------
taken over by other species), but it may live elsewhere in the Scioto River
basin.

     Eight state-listed fish have been sighted in the Columbus study area,
based on ODNR Natural Heritage Program data.  These species are:  blacknose
shiner, Tippecanoe darter, spotted darter, slenderhead darter, northern brook
lamprey, mooneye, river redhorse, and paddlefish.  Two additional species,
lake chubsucker and shortnose gar were reported by OEPA as being sighted in
the study area (OEPA 1986a).

     The river redhorse, mooneye, and shortnose gar were the endangered
species collected in 1985 and 1986 by OEPA during the Scioto River surveys.
These species were also caught during the 1979-1981 surveys of the Scioto
mainstern.  Known populations of blacknose shiner, slenderhead darter, and
spotted darter currently exist on tributaries to the Scioto (Fritz 1986).  The
lake chubsucker was collected in the Scioto by OEPA during the 1981 survey but
not during 1985 and 1986 surveys.  The paddlefish has not been seen on the
Scioto or in the study area since 1976.

     The river redhorse was the state endangered fish most often found during
the fish surveys conducted during 1979-1981 and 1985-1986 by OEPA on the
central mainstern of the Scioto River.  It was captured at several locations
ranging from RM 138.6 to RM 70.7.  The population in the Scioto may be growing
because the numbers caught each year have increased steadily.  In 1986 eight
were caught and prior to that between one and four had been caught per year.

     The river redhorse is generally found on medium sized streams having
gravelly or rocky bottoms and continuous strong flow.  It is highly sensitive
to siltation, turbudity, and intermittent flow.   It feeds in pools on small
mollusks, snails, and insects.   Spawning occurs in spring and is proceeded by
upstream movements.   The spawning fish gather in schools over shallow gravelly
riffles.

     Little information exists on the habits and life history of the mooneye.
In 1986 it was sighted at RH 102 and RM 100.2 in the Scioto.   It is generally
found in larger pools of streams and in open areas of reservoirs.  Its diet
                                     2-53

-------
 consists primarily of insects  and  small  fish  caught near  the waters surface.
 It spawns in spring.

      A population of  Tippecanoe  darters  is believed to exist in Big Darby
 Creek near the  town of Fox and in  Deer Creek.  This darter  is usually  found on
 riffles with slow or  moderate  currents and a  bottom of clean gravel and sand.
 The species  spawns during  spring along fringes or riffles in water three to
 eighteen inches  deep.   The Tippecanoe darter, like most darters is highly
 intolerant of silt.   In winter months it abandons riffles for pools two to
 five feet  deep where  currents  are  sluggish.

      The slenderhead  and spotted darters are  similar  to the Tippecanoe darter
 in  habitat requirements and life cycle.  These darters are  intolerant  of
 turbidity  and spawn in spring  on riffles.  Both darters are commonly found in
 larger  clean  streams  among larger  rocks  in swift currents.  The slenderhead
 exhibits more variability  in habitat selection than the spotted darter.  The
 spotted  darter is  believed to  have a relict distribution pattern in the Ohio
 River basin.

      The lake chubsucker,  shortnose gar, and  paddlefish are not common
 inhabitants of the central mainstern of the Scioto River.  These species are
 most  commonly found in  ponds,  oxbows, or backwaters where currents are
 sluggish.  Waters are  clean and  submerged aquatic vegetation abundant.  Such
 habitat  is apparently not  well developed within the Columbus study area.  Thus
 presence in the  Scioto  is  historically rare.

 2.2   MAN-MADE ENVIRONMENT
     The objective of  this section of the environmental setting chapter is to
 discuss  present  socioeconomic characteristics of the planning area that are
 essential  for identifying  and assessing primary and secondary impacts  of the
 proposed action as presented in  Chapter 6.   Therefore, the description of the
man-made environment focuses on  the following factors:

     o  Income (Economy)
     o  Public Service
        -  Transportation
        -  Water and Sewer Services
                                     2-54

-------
        -  Other Public Utilities
        -  Public Safety
        -  Health Care
        -  Education
        -  Community Services

     o  Public Finance
     o  Cultural Resources.

2.2.1 Income
     There are five aspects of income that are used to indicate the economic
health or stability of an area.  These aspects are listed below:

     o  Unemployment
     o  The number of nev jobs created
     o  The number and type of employers
     o  The number and type of jobs in the area
     o  Personal income levels.

Using these indicators, the Columbus area appears to have a healthy economy
and diverse economic base.

     The area's unemployment rate has remained low, even during recessionary
times.  According to the Ohio Bureau of Employment Services, the area's
unemployment rate peaked at 9.3 percent in the 1982 recession; the State's
rate peaked at 12.5 percent; and the Nation's rate peaked at 9.6 percent.
Franklin County's unemployment rate remained under these levels at 8.8 per-
cent.  This rate dropped to 6.2 percent for the first 6 months of 1985
(Columbus Area Chamber of Commerce 1985).  Franklin County outperformed the
Nation in number of nev jobs created during the period between 1978 to 1984.
Over 42,000 new jobs were added to the Columbus MSA employment base during
that period.  This brought the total number of persons employed in the county
to 557,000.  This figure represents an average increase of 7,000 jobs per year
in Franklin County.  As these figures indicate, the area is not susceptible to
recessionary trends and has a strong growing economy.
                                     2-55

-------
      Columbus weathered the 1982  recession  better  than  expected  for  several
 reasons.   First,  it  is not  an industrial  town.  Columbus has  a service-based
 economy.   The largest  employer is the  State University  followed  by the  State
 government.   Combined,  these two  State institutions  provide 48,000 jobs.
 The Federal  government is  the third  largest employer with  10,533 employees.
 Table 2-11 lists  the number and type of firms  in the Columbus area along with
 the number of employees each industry  employs.  As this table indicates,
 service industries provide  the largest number  of jobs,  over 94,000.
 Table 2-12 lists  the employment trends of these industries.   As  this table
 indicates, the financial and service industries are  the fastest  growing
 sectors of the local economy.   Second, Columbus is the  corporate headquarters
 for two Fortune 500  companies and over 250  firms with sales in excess of
 $10 million.   Some of  these firms include Borden,  Inc.; Bob Evans Farms;
 Nationwide Investing;  Wendy's International; and The Limited  Co.  Finally, the
 city of Columbus  and its Chamber  of  Commerce actively promote economic
 development  in the region.   This  policy has resulted in a  diverse economy  that
 is  able to absorb fluctuation in  the national  economy.

      As a  result  of  this diverse  economy, income levels are higher than
 average in the Columbus area.   The per capita  income in Franklin County is
 higher than  the MSA, State,  and Nation.  The county  per capita income is
 102  percent of the national average  and 106 percent  of  the State average (see
 Table 2-13).   The per  capita incomes for political subdivisions  within
 Franklin County are  shown in Chapter 6.  Several areas  within the county have
 unusually  high income  levels.   These areas  include Bixby,  Dublin, Riverlea,
 Marble Cliff,  Upper  Arlington,  and Uorthington.  Comparing growth rates with
 income levels  indicates  that  the  county is  growing both in the upper income
 and  lower  income  communities.   The growth rate for Dublin, a  community  with an
 average per capita income of  $18,392 was 29.1 percent,  while  the  rate for
 Urbancrest, a  community  with  an average per capita income  of  $5,091  was
 23.4  percent in the  period  between 1980 and 1984.   The  per capita income in
 1984  for Franklin County was  $13,035.  The  county's median family income in
 1980 was $20,970.  This was  104 percent above the  State median family income
and  105 percent above the Nation.   The median family income in the State was
 7.6  percent above the median national  family income in  1969;  this difference
had  decreased  to 5 percent  by 1979.  Furthermore,   the median  family  income in
                                     2-56

-------
                TABLE 2-11.   INDUSTRIES OF  FRANKLIN COUNTY (1982)
Agricultural Services
  Forestry, Fisheries

Mining

Contract Construction

Manufacturing

Transportation and Other
  Public Utilities

Wholesale Trade

Retail Trade

Fire

Services
                           Number of Firms/
                            Establishments
  197

   73

1,353

1,003


  534

1,702

A, 565

2,087

6,354
Annual
Payroll ($000)
$ 25,596
$ 18,899
$ 293,775
$1,375,581
$ 478,871
$ 579,953
$ 802,207
$ 635,173
$1,287,821
Number of
Employees
1,736
984
13,640
63,899
20,581
29,150
80,760
38,289
94,516
Sources:  Bureau of the Census 1983; Columbus Area Chamber of Commerce 1985.
                                    2-57

-------
             TABLE 2-12.   COLUMBUS MSA EMPLOYMENT  (1978-1983) TRENDS
Finance, Insurance,
  and Real Estate

Services

Wholesale/Retail

State and Local
  Government

Transportation
  & Public Utilities

Manufacturing

Mining

Construction
1987
Employment
34.6
92.5
127.5
82.8
23.6
116.2
1.3
22.2
1983
Employment
44.2
110.1
132.9
85.9
23.2
99.2
1.0
17.1
% of Total
1983
Employment
8.5%
21,3%
25.7%
16.6%
4.5%
19.2%
.2%
3.3%
Percent
Change
1978-1983
+27.6
+19.0
+4.2
+3.7
-1.6
-14.6
-19.2
-22.7
Source:  Columbus Area Chamber of Commerce 1985.
                                    2-58

-------
          TABLE 2-13.  PER CAPITA INCOME LEVELS FOR THE COLUMBUS MSA
State of Ohio

MSA

Pelavare

Franklin

Fairfield

Licking

Madison

Union
                  Personal Income
                  Average Annual
                   Growth Rate*
   Per Capita
 Personal Income
1980         1984
Per Capita Income
as a % of National
 Average in 1984
7.48
8.35
9.98
8.11
9.22
8.57
8.77
9.41
$9,401
$9,282
$9,251
$9,577
$8,771
$8,625
$7,696
$8,720
$12,326
$12,609
$12,508
$13,035
$12,025
$11,621
$10,016
$11,479
97
99
98
102
94
91
100
90
Source:  Bureau of Economic Analysis 1986.
                                    2-59

-------
 Franklin County was  2.7  percent  above  the  State  income  in  1969, but was only
 .3 percent  higher in 1979.   By 1979,  the county  income  was 12.7 percent higher
 than the city income level,  up from 8.8 percent  in  1969.   This reflects a
 concentration of higher  income white collar households  in  the suburban areas.
 Median  family income levels  are  also higher for  Franklin County than  the U.S.
 or Ohio.  Median family  income is  discussed further in  chapter 6.

 2-2.2   Public Service
     Local  governments provide a number of essential services.  These include
 fire and  police protection,  water  and  sewer service, local roads, and public
 education.  Public  utilities  provide other services  such as electricity.  Those
 services  that are  required as  part  of  the development process or  require a
 large physical plant  are part  of a  community's infrastructure.  This  infra-
 structure includes water and,sewer  lines, roads  and bridges, and  in some
 communities electric  and gas lines.  Many communities require impact  fees to
 pay  for  these services or require a staged development  plan to limit  the
 impacts of  growth  upon these services.  Although local  planners advocate such
 sound planning practices, these  techniques are not  formally practiced in the
 Columbus  area.   This  rapid and uncontrolled development has placed a  strain on
 many of  the area's essential services.  In most  cases each of these essential
 services  has  been  strained as  a  result of this constant and ever  increasing
 growth.

     The  Development  Committee for  a Greater Columbus is in the process of
 studying  the  area's  infrastructure  needs.  This  committee  is working  with the
 Mid Ohio  Regional  Planning Commission  (MORPC) and other public agencies to set
 criteria  for  funding  availability,  health and safety standards, and minimizing
 the impacts of development on  the local community.  Bridge  repairs, road
 repairs,  increasing the city's water supply, and upgrading  the sewer  system
are the four  areas of most concern  to  this local citizens group.  The
committee recommends a consistent method of financing capital improvement
projects and  increased surtaxes and fees to finance these  improvements
 (Development Committee for a Greater Columbus 1986).  It is  the responsibility
of the State and local government to anticipate necessary  improvements and
incorporate the  funds to provide these improvements in the  budget process.
                                     2-60

-------
      Below  is  a  discussion of  each  of  these  services:

      o  Transportation
      o  Water  and  Sever Services
      o  Other  Public  Utilities
      o  Public Safety
      o  Health Care
      o  Education
      o  Community  Services (Cultural Activities)
      o  Recreation.

 2.2.2.1  Transportation
      Transportation systems, both public and  private, play a vital  role  in  the
 growth and  economy of the  Columbus  Metropolitan Area.  Because of Columbus'
 strategic location, its transportation systems provide easy access  to  the
 markets throughout the  United  States.  As a  result, Columbus is becoming a
 major distribution center.

      The Columbus  Metropolitan Area has a network of more than 200  miles of
 expressways.   This network of  roads consists  of local streets and an inner
 beltway that feeds into the outer beltway at  various junctions.  The following
 roads serve the  city  of Columbus:   1-71, east; 1-70, south; State Road 315,
 west; and 1-670, south.  Interstates 70 and 71 (670 when it is completed) and
 State Road  315 comprise the inner beltway.  1-670 will be completed in the
 early 1990s.  Traffic congestion usually occurs east and north of the downtown
 Columbus area during morning and evening rush hours.  It is expected that
 1-670, when it is  operational, will relieve much of the traffic congestion
 from  1-71.

     The northwestern section  of the Columbus Metropolitan Area is
experiencing severe traffic congestion during morning and evening rush hours
and on weekends.   The roads in this area have exceeded their overall traffic
capacity.   As a  result,  Bethel Road from east of Sawmill Road to Olentangy
River Road  is expanding  to  four lanes.   This project has already been funded
and is under construction.  There is a plan to widen Sawmill Road but it has
                                     2-61

-------
 not  yet been funded.   Road  improvements  for  the Dublin area have not  been
 planned.

      During morning and  evening rush  hours,  traffic  congestion  occurs near and
 around  1-270 access roads.   Projects  that  have been  funded include widening
 Broadway from two  to  five lanes from  Southwest Boulevard  to 1-270, widening
 Cemetery Road from Leap  Road to 1-270, and widening  Cemetary Road from  two to
 four lanes  from  Main  Street  to  Leap Road.

      The  city of Columbus receives financial assistance from the Ohio State
 Department  of Transportation to maintain all roadways (including State  owned)
 for  the Columbus Metropolitan Area.   Developers are  100 percent responsible
 for  repairing and  constructing  roadways  within their areas of construction.
 Through negotiations  with the city or Planning Commission, developers become
 responsible for  offsite  improvements, such as widening a  roadway on the
 outskirt  of their  jurisdiction.

      Four airports located in Franklin County serve  the Columbus Metropolitan
 Area.   Port  Columbus  International Airport is owned  and operated by the city
 of Columbus.   There are  direct  flights from Port Columbus International
 Airport  to  22  major cities,  including New  York, Boston, Washington, Chicago,
 and  Los Angeles.   Port Columbus  International Airport is  not directly
 accessible  from  any of the interstates.  Major traffic congestion usually
 occurs  during  rush hours between the  airport and downtown Columbus.   By the
 early 1990s,  traffic  congestion  should be  reduced when the 1-670 interchange
 is completed.

     Other  airports that serve  the Columbus Metropolitan Area are Don Scott,
 Bolten  Field,  and  Rickenbacker.  Don  Scott, a general aviation  airport, is
 owned and operated by Ohio State University.  It is  the fourth  busiest  airport
 in the  State, and  serves private and  corporate jets.  Don Scott Airport is
 located in  the northwestern  part of Franklin County.  The city  of Columbus
 owns and operates  Bolten Field Airport.  This airport serves only private
 planes.   Rickenbacker Airport is the  largest air-freight hub of the Flying
Tigers Air Cargo Company.  The Columbus Port Authority owns and operates this
airport.
                                     2-62

-------
     Columbus  is a major  rail junction  for  the Chessie, Conrail,  and Norfolk
and Vestern railroad  lines.  Conrail's  new  Buckeye Yards have enabled  local
businesses to  conveniently and  economically transport supplies  and  products in
and out of Central Ohio.

     Over 100  trucking  companies  provide  freight movement  for Columbus
businesses with at least  19 companies transporting goods to any North American
location.

     The Central Ohio Transit Authority (COTA) provides bus transportation
within the Franklin County service area.  COTA is expanding its bus routes to
serve the nonradial travel patterns of  suburban residential and work areas by
use of crosstown route  expansion  and reverse commute planning.

2.2.2.2  Water and Sewer  Services
     The Columbus Division of Water serves  over 200,000 accounts  in the
greater Columbus metropolitan area.  Each year, over 45 billion gallons of
water are treated and pumped to supply  the  industrial, commercial, and
domestic needs of a growing Columbus.   Operating with an annual budget of over
$50 million, the Division maintains 17,000  fire hydrants and over 2,500 miles
of water lines.  The  Scioto River, Big  Walnut Creek, and the South well field
are sources of raw water  for the  Division's three treatment plants.  The
combined supply capacity  of these facilities is over 175 million gallons a
day.

     Figure 2-9 shows the location of city water treatment plants and
reservoirs.   Reservoirs include O'Shaughnessy and Alum Creek located in
Delaware County, Hoover located partly  in Delaware County,  and  Griggs located
in northwestern Franklin County.  A sewer interceptor line runs under the
Griggs reservoir.  This interceptor line is reaching capacity.  If an overflow
occurs,  this water source may be  contaminated.  Water from these sources is
treated at the Dublin Road and Morse Road plants;  the Nelson Road plant serves
as a backup.   The deep well field on Parsons Avenue has been completed.  This
facility is  presently used to supplement the current surface sources as well
as to be the primary source of water to new development in the southern part
of Franklin County.
                                     2-63

-------
          r
      r
   \_
, t
A
1
2
3
*

City of Colwnbui
EjMitinq Wolvr Plonl $ >>m
H0->/tr Jen.
"rc>-!*S ' IOM Do1*-
>*- .t 3,-ar 01 -r
ie t i ;rd Cub
p coo eo Soc - *H



V Ocm
3'**a betwe
1, 'ood Plo
f.eld
SOURCE: 1979 OS
                          2-64
FIGURE 2-9
COLUMBUS  WATER SYSTEM

-------
     The safe yield of water  from  these sources  is  presently  175  MGD;  peak
load is 235 MGD  (City of Columbus  1986c).  This  capacity  is sufficient  to
sustain the present rate of growth until  the year 2000 provided additional
sources are found by 1991  (Development Committee for a Greater Columbus  1986).
 During the summer of 1986, the  city was  forced  to  implement  a dry water
conservation program.  To  meet long-term  demands, however, new sources must be
developed.  One  source under  consideration is  the Upper Darby Creek.
Development of this source is still in the planning stage.

     The city of Columbus  sewer  system consists  of  over 2,780 miles of storm,
sanitary, and combined sewers.   The system receives an average of 149 million
gallons of sewerage per day at the Southerly and Jackson  Pike Treatment
Plants.  Figure  2-10 shows the location of sewer facilities and the existing
service areas.   The system is primarily a gravity system  with minimal pumping
and conforms to  the downstream flow which runs north-south through Franklin
County (City of  Columbus 1986c).

2.2.2.3  Other Public Utilities
     Natural gas, oil, and coal  are all produced in Ohio, with coal the  most
abundant resource.  Ohio ranks fifth among the states in  coal production and
has a supply of  coal that  is  estimated to be enough for about 500 years.  Ohio
has excellent electric generating  capacity, well in excess of demand.  Nearly
96 percent of Ohio's electricity comes from coal-fired boilers.

     The Columbus area is served by Columbus and Southern Ohio Electric
Company, one of  the eight operating companies of the American Electric Power
system.  This system operates in six states and has a generating capacity of
over 22 million kilowatts.  About  85 percent of  this generation is from coal-
fired units.

     The city of Columbus, through the Division of Electricity, provides power
for the city's street lighting and other facilities.  This plant is also a
member of the American Electric Power Grid System.   The Columbus Refuse and
Coal Fired Municipal Electric Plant,  owned and operated by the city of
Columbus,  generates electricity through the burning of refuse.  The plant is
                                     2-65

-------
              r
     \	
             Emting and Planned Industrial,
             Off*. Pcrlc,
      •m^mmmum Exiilmg Trunli line

      •« • • •» '• Planned Trunk line	
      ^   Scwoge Treatment Plant
SOURCE  COLUMBUS, OHIO, DEPARTMENT OF
        DEVELOPMENT DIVISION OF PLANNING
                                       2-66
FIGURE  2-10
SEWER  TRUNK DESIGN  VS
INDUSTRIAL PARK SITES

-------
capable of burning 3,000  tons of refuse per day and has  the  capacity  to
generate 90 megawatts of  electricity  (City of Columbus 1986b).  Columbus  plans
to purchase new collection vehicles and expand its collection area  once the
shredder system is upgraded.

     Columbus Gas of Ohio, Inc. distributes natural gas  throughout  Columbus
and  the surrounding area.  Gas  is  fed  into the city system through  five border
stations located on all sides of the  city.  This gas goes into a high-pressure
loop system which nearly  parallels the outerbelt.  From  this high-pressure
belt, the pressure is reduced to medium pressure (5-50 psig), intermediate
pressure (1-5 psig), and  low pressure  for distribution to the 260,984 residen-
tial, 16,505 commercial,  and 208 industrial customers in the area.

2.2.2.4  Public Safety
     There are 55 different public safety agencies operating at various levels
of government in Franklin County.  Although all of these agencies work hard to
meet the needs of the citizens  they serve, there is an obvious duplication of
services when so many different units are operating in one area.  The problem
is compounded by the city's separate annexation pattern.  There are many
pockets of unincorporated areas nestled within Columbus.  These areas are
served by the Franklin County Police and Fire Departments.  This sporadic
pattern of development forces the rural-oriented County Sheriff's office to
increase its surveillance in urbanized areas.

     In February 1977, MORPC completed a report on fire protection services in
Franklin County.  It describes and analyzes services available in all town-
ships and incorporated areas.  According to the report, Franklin County is
served by a total of 25 fire departments:

     o  15 township departments
     o  5 city departments
     o  3 village departments
     o  2 Federal facilities
     o  1 unincorporated private department.
                                     2-67

-------
 Seven jurisdictions have contract  arrangements  for  fire  services.   Coordina-
 tion of fire services is not  the responsibility of  any single organization.
 Several groups perform various training,  prevention, and coordination
 functions.

      The City Fire Department has  843  employees and the  following  fire
 equipment:   28 stations,  A  heavy rescue vehicles, 28 engine  companies, 4
 paramedics,  10 ladder companies, and 9 squads.  The city plans  to  hire an
 additional 108 recruits in  fiscal  year 1987  (City of Columbus 1986b).

      There are 31  different police forces operating in Franklin County.  These
 units vary from the part-time marshall monitoring a small village  to the city
 of Columbus  police force which includes over 1,500  full-time employees.  The
 County Sheriff patrols  the  entire  county  but has a  special contract for the
 unincorporated areas of Praire,  Hamilton, Norwick,  and Washington  townships.
 The  towns of  Pleasant,  Jackson,  Truro, Jefferson, Cain,  and  Brown  do not have
 a contract for increased  service nor do they have their  own  police force.  The
 County Sheriff has 10 to  12 patrol cars on duty per shift.   There  is one
 deputy per car.

      According to  Chief Kramer,  the Franklin County Sheriff's office is
 understaffed  and is  experiencing an increase in crime as  the county shifts
 from  a rural  area  to a  suburban/urban  economy.  The crowded  roads  have
 decreased the sheriff's response time.  Traffic accidents are more frequent
 and more serious.  In 1985, there  were less  than 10 fatal accidents in the
 county.  In  the first nine  months  of 1986, this number had increased to 23.
 The newly renovated  county  jail  is  at capacity  and  is considering  further
 expansion.

     The sheriff's department keeps a fire radio in all patrol  cars in order
 to keep in constant  touch with the  fire service.  On July 1, 1986,  the county
 expects to implement  911 service from its new communication  center  at the Old
Woman's Work House.  At that  time,   the County Sheriff will be responsible for
dispatching all fire and police equipment (Kramer 1986).
                                     2-68

-------
2.2.2.5  Health Care
     The Columbus area has  12 operating hospitals with 5,565  beds.  This  is
approximately one bed for every  160  persons.  The area has  2,500  physicians,
leaving one physician for every  350  individuals.  In addition,  there  are
90 dentists in the area and 90 clinics serving  the area.  Six of  these  clinics
are  financed by the city of Columbus.  The city also offers a variety of  at
home nursing services.

     Of the 12 hospitals, one (Grant Medical Center) has a Lifeflight
operation  that carries critically  injured patients as far as  125  miles  away to
its emergency care facility.  Childrens Hospital in Columbus, one of  the  three
largest pediatric care facilities  in the nation, will open its expanded
research facility in 1987.  Ohio State University is a leader in  diagnostic
care and is an authorized cancer center.  According to the American Hospital
Association, Columbus health care  costs are lower than the national average
(Columbus Area Chamber of Commerce 1985).

2.2.2.6  Education
     There are 17 different school districts operating 226 public schools in
Franklin County.  In addition, there are 26 private and parochial schools with
over 12,000 students.  There are 13 colleges located in the county with an
enrollment exceeding 75,000 students.  In addition, there are 35  public
libraries:  one main branch, 20 branches in the city of Columbus, and 14
suburban branches (Columbus Area Chamber of Commerce 1986).

     In the public school system,  there are 141,289 students  and  7,804
teachers;  this results in a student teacher ratio of 18 students  per  teacher.
Almost half of these students or 66,158 pupils attend one of  the  city of
Columbus'  130 schools.  The remaining 75,131 students are divided between the
remaining 16 districts.   Since these districts are considerably smaller than
the Columbus school system, the city offers special programs  for  the  learning
disabled or visually or hearing impaired to students outside  the  city's school
district boundaries (Columbus Area Chamber of Commerce 1985).
                                     2-69

-------
      In  1971,  the  Columbus  school  system had a record high enrollment of
 111,000  students.   Enrollment has  declined due to a national decline in birth
 rates and  a  realignment  of  suburban school districts associated with a 1979
 Desegregation  Ruling  by  the U.S. Supreme Court.  In 1985, enrollment leveled
 off.

      The system's  enrollment decreased and the district was forced  to close
 some  schools.  Now that  the birth  rate is increasing and  the overall
 population in  the  city of Columbus is also increasing, the district is
 studying the possibility of reopening six closed schools  for the 1987 school
 year  (Lover 1987).  These schools will be used to help augment the  city's
 alternative school and neighborhood school programs.  The Columbus  area
 population is  well educated in 1980.  Over 73 percent had a high school
 education and  21.2 percent  were college graduates (Bureau of the Census 1983).
 Figure  2-11 shows the various school districts within Franklin County.  The
 smaller  developed  districts such as Bexley, Whitehall, Upper Arlington, and
 Grandview Heights,  have  experienced declining enrollments and have  been forced
 to close some  of their schools.  School districts located in growth areas,
 such  as  Dublin, Worthington, and Billiard, have increasing enrollments and
 plan  to  build  new  facilities.  The Dublin school district is forced to lease
 space  in order to  accommodate its enrollment.  All of these growing suburban
 areas  are overcrowded.

 2.2.2.7  Community  Services
     The Columbus  area has  an adequate number of diverse community services.
There are over 120  neighborhood associations, 88 shopping centers, 69 hotels
and motels with over 10,000 rooms,  over 750 Protestant churches, 54 Catholic
churches, and  11 Jewish synagogues.  Additional services include the
 following:

     City Parks                 141          Major Auditoriums            9
     Metropolitan Parks           7          Museums                      9
     State Parks                  6          Outdoor Movies               6
     Auto Race Tracks             2          Skating Rinks                7
     Ball Fields                120          Swimming Pools              50
     Bowling Facilities          30          Tennis Courts               12
     Country Clubs               15          YMCAs                        8
     Golf Courses                25          YWCAs                        2
     Indoor Movies               25
                                     2-70

-------
NJ
                                                                         Gahanna
                                                                         Jefferson
                                                                         SD
  Reynotdsburq
  SD
                                                                    Groveport -
                                                                    Madison
                                                                    SD
Canal.
Winchester
SD  I
Hamilton
SD
                  * \OJ jf
                                                                                                            • M«yo>
                                                                                                            * rwpiMtwnl i>l 0«
                                                                                                              D"K'01 " -1*"1 H*°°*
                                                                                                            f It I  >\ C' llHI I
                                                                                                     School District
                                                                                                     Boundaries
                                                                                                     August
                               FIGURE 2-11.   SCHOOL DISTRICT BOUNDARIES

-------
      Cultural events  and  activities  include:

      o  The  Columbus  Symphony  Orchestra
      o  The  Ballet  Metropolitan
      o  Music in  the  Air
      o  The  Columbus  Museum  of Art
      o  The  Center  of Science  and Industry
      o  The  Ohio  Historic Center
      o  The  Greater Columbus Arts Festival
      o  A 100-acre  city-owned  zoo
      o  The  Ohio  State Fair.

2.2.2.8  Recreation
      The Scioto River provides opportunities for a variety of active
recreational  uses,  and serves  as a major scenic resource for the Columbus
community.   Access  to the Scioto River is available through scenic easements
and a series  of 21  parks  located along the river in Franklin County.

      The majority of  water-related recreational activity centers around the
O'Shaughnessy and Julian  Griggs Reservoirs in the northern section of the
river.   Boating and fishing  are the major active uses, while picnicking,
hiking,  bicycling,  and sightseeing are the predominant passive uses.  In 1986,
there were 132 boats  registered for primary use on Griggs Reservoir and
143 boats for use on  O'Shaughnessy (Bazler 1987).  There are 243 boat docks
available for rental  at the  two reservoirs through the City of Columbus
Recreation and Parks  Department.  Demand for these docks is high (Slaughter
1987).   Boat  launching ramps are located on each side of the Scioto River for
day-boating use, which is permitted from 7:00 am until 11:00 pm.  No quanti-
tative studies of recreational river use have been undertaken,  but indications
are that it is relatively high in the portions of the Scioto River north of
Jackson  Pike WWTP.
                                     2-72

-------
     Fishing occurs along  the  entire  length of  the  river  in  the  FPA,  but  is
most active north of Greenlavn Dam.   The  latest  creel  survey of  the Scioto
River,  taken between O'Shaughnessy Reservoir and Greenlawn Dam between  April
14 and  October 12, 1986, revealed a total  fishing pressure of 153,080 angler
hours.  Approximately  133,044  fish were caught and  58,470 were kept (Schaefer
1987).

     Swimming or bathing is  prohibited by  city ordinance  at  any  location  along
the Scioto River within the  Columbus  city  limits, in order to protect the
city's  water supply and for  public safety  reasons (Deitz  1987).

     The downtown core of  Columbus, upstream of  the Jackson  Pike site,  hosts a
series  of water-related urban  parks that provide paddleboat  concessions,
pontoon pleasure and shuttle rides, a floating amphitheatre,  scenic overlooks,
fishing piers, waterskiing exhibitions, boat races, and riverfront festivals.

     Limited access and limited recreational quality restrict recreational
activities from Frank Road to  the juncture of Big Walnut  Creek and the  Scioto
River in Harrison County.  Recreation activities along the lower portion  of
the Scioto, south of the Jackson Pike WWTP, consist largely  of duck hunting
and fishing.

     In 1974, a master plan  for the waterways of Columbus was prepared  and
adopted to protect and enhance the water resources  of  the county.  "The
Watercourse Plan for Columbus and Franklin County"  (City  of  Columbus 1974) is
the only land-use master plan adopted by Columbus and Franklin Counties.  The
plan proposes a major park network along the seven watercourses that flow
through the county, including  the Scioto River.  The master  plan identifies
the land along the southern  portion of the Scioto River for  potential
development as parks and scenic open space.

     The northern portion of the river, from the zoo in Delaware County
through downtown Columbus,  is identified for a variety of uses consisting of
urban waterfront parks, open space,  and waterfront development.   The water-
course plan has been used as a guide to development in the area,  although the
corresponding zoning needed  to fully implement the plan is lacking.  The
                                     2-73

-------
 northern section  of the  river  has  developed more or  less according  to  the
 plan.   Currently,  the  city of  Columbus  is  pursuing the purchase of  conser-
 vation and  scenic easements along  the lover Scioto River as opportunities
 arise.

     Even lacking more quantitative  data,  it  is evident that  the  Scioto River
 is  heavily  used as a community resource, and  will experience  additional
 pressure in the future as  a result of projected development in the  Columbus
 area,  and anticipated  demand along the  river's edge.  Currently,  there are
 proposals for a floating restaurant  and a  heliport along the  Scioto River in
 the downtown area;  several of  the  area's incorporated municipalities have park
 projects in the planning stage that  will make use of the river as either an
 active recreational  or aesthetic resource.

 2.2.3   Public Finance
     The study area  includes most  of Franklin County and parts of Fairfield,
 Delaware, and Licking  Counties.  Table  2-14 compares the per  capita property
 taxes  with  the per capita  expenditures  for these four municipalities.  Of
 these  four  counties, Franklin  has  the highest tax rate and the highest
 expenditure level.   This is  due to the  large  number of incorporated areas
 within Franklin County.  Most  of these  incorporated areas have their own
 school districts.  Although  the State makes a large contribution  to school
 district  operations  from the State Foundation Fund, schools are largely
 financed  through the local property  tax.

     The  largest incorporated  area within Franklin County is  the city  of
Columbus.   The city's  fiscal health  is an indicator of the area's economic
vitality.   Columbus has a strong and growing  economy.  The performance of the
 city income tax over the last  3 years reflects this strength.  The  economic
outlook suggests sustained growth  in 1987.   The city continues to increase its
 revenue base through annexation.   Most of the recent annexations have  been for
properties  located within  the municipal boundaries.  Table 2-15 lists  the most
recent annexations.
                                     2-74

-------
                                   TABLE 2-14.  PER CAPITA TAXES BY COUNTY
                                                                  Expenditure Distribution
Property Tax
County per Capita
Ohio
Franklin
Fairfield
Delaware
M Licking
i
•xj
u» Madison
Union
227
217
163
177
200
199
169
Per Capita
Expenditure
729
752
571
502
527
541
527
Education
48.1
47.1
50.2
53.8
57.1
58.2
41.4
Highways
5.8
4.0
7.7
8.5
7.9
10.5
9.8
Public
Welfare
4.7
7.0
2.1
2.6
3.7
4.6
6.4
Health &
Hospitals
7.1
3.1
15.8
3.7
2.3
1.9
22.8
Police
Protection
4.8
6.3
3.1
3.5
3.2
3.4
1.7
Based on 1976-77 Financial Reports



Source:  Bureau of the Census 1983a

-------
                  TABLE 2-15.   COLUMBUS ANNEXATIONS SINCE 1986

 Year                      Fringe Annexation           Infill Annexations
                          Cases       Acres           Cases        Acres
 1980                        7        1,157             15
 1981                        1           365             17
 1982                        1           72             21
 1983                        2           448             12
 1984                        6           288             22
 1985                        11           616             20
 1986  to Present             _4           164             23
   Totals                   32        3,110            130         1,965

      In anticipation of decreased Revenue Sharing  funds, the  city cut its  1987
 budget.  The city increased user charges and regulatory  fees  to compensate for
 this  $10 million loss.  Although cuts vere made, basic services will receive
 full  funding in FY 1987.  Public safety forces are slated to  expand as the
 city  grows.  The police budget includes two classes totaling  65 recruits and a
 police cadet program expected to free up more officers for patrol.  The fire
 budget funds three classes with a total of 108 recruits.  Equipment replace-
 ment, particularly for refuse collection and roadway maintenance, is
 especially critical due to  the age of the fleet.

      In 1986, the city's  long-term credit rating was increased by both
 national rating agencies.  Standard & Poor's Corporation and  Moody's Investors
 Service currently rate Columbus as AA+ and Aa, respectively.  These ratings
 constitute the highest credit quality position in Columbus' history.  The
 city's short-term ratings also reflect Columbus' credit quality, with a
 Standard & Poor's rating  of SPI+ and Moody's rating of MIG-1  and VMIG-1.   The
 1987 Executive Budget combines the city's operating and capital budgets to
allow for a greater understanding of the relationship between capital projects
and operating costs.  It  also provides for dual and simultaneous consideration
of each city division's total operations,  both in the operating arena and  in
 the capital improvements  area.
                                     2-76

-------
     The Division of Planning  prepares  an annual Growth  Potential  report  as
part of an overall Columbus development strategy.  The report  attempts  to
identify the Columbus metropolitan area's future population growth in resi-
dential development, determine the site of such development, and assess the
city's ability  to accommodate  that growth.   Specific capital project proposals
are developed to address  the needs identified  in the Growth Potential report.
The report indicates that growth  is expected on the far  south  side of
Columbus.

     The city of Columbus has  a FY 1987 operating budget of $437.3 million.
The city's general fund generates revenues of  $212.5 million.  These revenues
will fund 49 percent of the FY 1987 operating  budget.  Special revenues,
internal services, and block grants comprise 7.5 percent of the city's
operating budget.  The enterprise fund  comprises the remaining 43.5 percent of
the budget.  The city has four enterprise operations.  These are as follows:

     o  Airports with an  estimated revenue of  $19,815,755 in 1987
     o  Electricity with  an estimated revenue  of $49,738,804 in 1987
     o  Water with an estimated revenue of $74,982,467 in 1987
     o  Sewers with an estimated revenue of  $93,915,047  in 1987.

     The next largest revenue  source for general fund operations is the income
tax.  In 1987, this source is expected  to yield $139.5 million or  64.7 percent
of total general fund revenues.  This estimate exceeds project 1986 receipts
by $8.3 million, or 6.3 percent, and reflects continued economic growth.  The
city of Columbus levies a 2 percent income tax on all wages, salaries, com-
missions,  and other compensation paid by employees and on the net  proceeds of
business operation in the city.  The most recent tax increase,  0.5 percent,
was approved by the voters on November 2, 1982, and became effective on
January 1,  1983.  Pursuant to Columbus City Code,  Section 361.36,  75 percent
of all income tax collections are deposited  in the general fund for general
fund operations, and 25 percent of collections are deposited in a  separate
fund to service debt on capital improvements.
                                     2-77

-------
 2.2.4   Cultural Resources
 2.2.4.1  Historic  Resources
     The  Columbus  area  is  the  second  largest metropolitan area in Ohio, second
 only to Cleveland.   Columbus was  established as the State capital by the Ohio
 General Assembly soon after statehood in 1812 and was named for Christopher
 Columbus.  Columbus  vas made the  seat of Franklin County in 1824.

     Improvements  in transportation corridors spurred growth in the Columbus
 area. During  the 1840s, Columbus  was  linked to the National Road (from
 Maryland) and  to the Ohio and  Erie Canal.  By 1850, the first railroad
 arrived, and by 1900, the population  of Columbus exceeded 100,000 people.  The
 city contained a diversity of  industry and government services important to
 Ohio.   The areas surrounding the  city remained predominantly rural and
 agricultural until after the second world war.  Since World Var II, agri-
 cultural lands have  been converted to subdivisions in a large-lot sprawl
 pattern.  The Columbus  metropolitan area of today covers over 2,000 square
 miles,  making it geographically the largest metropolitan area in Ohio.

     The Ohio Historical Society  (OHS) was established in 1885.  Its
 headquarters are in  Columbus.  The OHS has an inventory of over 3,000
 properties or sites  that may or may not be eligible for inclusion on the
 National Register of Historic  Places  but are, nonetheless, historic under OHS
 criteria.

     The National Register of  Historic Places lists 27 historic sites or
 structures (excluding archaelogical sites) in Delaware County; 34 in Fairfield
 County  (2 additional structures are eligible)f 99 in Franklin County
 (11 additional structures and  sites are eligible,  and 27 are pending inclusion
 on the Register);  39 in Licking County (1 additional is eligible); 6 in
Madison County; and  15  in Pickaway County (1 additional structure is eligible)
 (See Appendix I).

 2.2.4.2  Archaeologic Resources
     Information about archaeologic resources was obtained primarily from the
archaeologic survey report prepared for the Columbus Southerly and Jackson
                                     2-78

-------
Pike Wastevater Treatment Plants, published January 25,  1985,  by John  E.
Black, Ph.D., Department of Anthropology, Cleveland State University.
Archaeologic resources are derived  from a succession of  prehistoric  cultures,
extending back in  time to a period  of 18,000 years B.C., that  made extensive
use of the Scioto  River Valley.

     The archaeologic background analysis of the Blank survey  (see Appendix J)
was used to characterize prehistoric cultural information.  This background
analysis suggests  that prehistoric  manifestations would  occur  on the raised
elevations on both the floodplains  and terraces of the Scioto  River  throughout
the project area.

     According to  William S. Dancey, Ph.D., an Associate Professor of
Anthropology at Ohio State University, in a letter dated January 2,  1987,
"...the valley floor and bluff edges of the rivers in the study area were
preferred locations for human settlement."  Further, he  stated that  "...within
the study area, where intensive surveys have been conducted (e.g., along Big
Darby Creek from Orient to S.R. 40, Alum Creek in the Uesterville vicinity,
and the Scioto River from 1-270 to  Circleville), sites have been found to be
nearly continuous  along the floodplain and on adjacent bluffs."  Dr. Dancey
concluded in his letter that "...development of any kind in the region will
encounter archaeologic sites and because of the poorly known character of the
sequence and structure of prehistoric occupation nearly all sites are
potentially significant by any measure."

     The National Register of Historic Places lists:  1 archaeologic site in
Delaware County; 3 in Pairfield County;  6 in Franklin County; 5 in Licking
County; 1 in Madison County; and 5  in Pickaway County.  The Ohio Historic
Inventory lists those archaeologic sites that may or may not be eligible for
inclusion to the National Register but are,  nonetheless,  important cultural
resources to the State.   The site inventory of the Division of Archaeologic
Services of the Ohio Historic Preservation office includes over 500 sites from
Franklin County and over 330 sites within Pickaway County.
                                     2-79

-------

-------
                       CHAPTER 3.  EXISTING FACILITIES

     This chapter describes the Jackson Pike  and Southerly Wastewater
Treatment Plants, the Combined Sewer Overflow System, and the Southwesterly
Composting  Facility.

     Figure 3-1 shows the  locations of the two treatment plants, the
composting  facility and the area served by combined sewers.  Separation of a
portion of  the combined sewer  area is  currently  underway.  This area is noted
on the map.

     The following sections of this chapter will define the equipment,
influent and effluent characteristics,  and the overall condition of the
facilities.

3.1  JACKSON PIKE WASTEWATER TREATMENT PLANT
     The Jackson Pike Wastewater Treatment Plant began operation in 1937.  The
plant was modernized  and expanded in capacity in the mid-fifties.  Currently
there are two parallel flow trains for  wet stream treatment consisting of
preaeration, primary settling, aeration, and final clarification.  The
original train is called Plant A, and the newer train is called Plant B.  The
two trains  operate relatively independently of each other during liquid
processing but share sludge handling facilities.

3.1.1  Major Interceptors
     Wastewater arrives at the Jackson Pike plant by the 108-inch diameter
Olentangy-Scioto Interceptor Sewer (O.S.I.S.)  and the 72-inch diameter  Big Run
Interceptor Sewer.   The maximum  hydraulic capacity of the Jackson Pike plant
is 100 MGD.  Currently average daily  flows are approximately 84 MGD.  The
plant accepts all of the flow from the Big Run Interceptor but limits the flow
from  the O.S.I.S.  so the hydraulic capacity of  the plant  will not be
exceeded.   The major diversion point for  the O.S.I.S. flows is  at  the  Whittier
Street Storm Standby Tanks.
                                     3-1

-------
JACKSON PIKE WWTP

SOUTHERLY WWTP

SOUTHWESTERLY COMPOST FACILITY


APPROXIMATE SCALE-
   1 INCH = 4.12 MILES
        SEPARATION UNDERWAY OR COMPLETE

        COMBINED SEWERS REMAINING

        MAJOR INTERCEPTOR
FIGURE 3-1
COLUMBUS METROPOLITAN AREA
INTERCEPTORS & TREATMENT FACILITIES
  3-2

-------
     The .major  portion  of a connecting sanitary interceptor sewer (i.e.,  the
Interconnector) is currently in place between the Jackson Pike and Southerly
WWTPs.  Currently the Interconnector consists of approximately 7 miles of 150-
inch and 156-inch diameter sewer.   It begins 3000 feet from the Jackson Pike
WWTP  and  connects with  a pump station on the west side of the Scioto River
near the Southerly WWTP.  In September of 1986, USEPA provided funding for the
construction of the remaining 3,000 feet of the sewer (Figure 3-2),  which will
complete the Interconnector between the two plants.   Included in the north end
construction will be a diversion chamber which will connect the Interconnector
with  the  O.S.I.S. north of Jackson Pike.  When  completed,  the Interconnector
will allow the flow to Jackson Pike to be  controlled  by  diverting excess  flows
to Southerly.

3.1.2  Preliminary Treatment (O.S.I.S. Flows)
     Preliminary treatment  is provided for flows entering Jackson Pike through
the O.S.I.S.  at a facility called the Sewer  Maintenance  Yard which is located
approximately one axle north of Jackson Pike.   These  preliminary treatment
facilities were constructed in 1948.  They  are  rated  at  a capacity of 160 MGD
and provide preliminary  screening and  grit  removal  for  flows in  the  O.S.I.S.
prior to their arrival at Jackson Pike.

3.1.3  Major Treatment Processes
     The Jackson Pike  Wastewater Treatment Plant consists of the following
treatment processes:

     •  Preliminary Treatment
     •  Primary Treatment
     •  Secondary Treatment
     •  Disinfection
     •  Solids Handling
     •  Solids Disposal.
                                      3-3

-------
                                      -f
                                          <0
                                        f
                                       A
 «0
o
PROPOSED
DIVERSION -\
CHAMBER \
f ~ f~ ,-,— ^ ,-,-,- A
/ f an
r fl ° d
fll — Ir*^! I 	 r
malD0


nnnn :
§
/"
/§
/«
g
i ,\
>^

•v
in
J
	 n
^



                        JACKSON PIKE WASTEWATER TREATMENT PLANT
                         PROPOSED 150"
                         INTERCONNECTOR EXTENSION
                         & 8" SLUDGE LINE  EXTENSION
SOURCE REVISED FACILITY PLAN UPDATE
                              3-4
FIGURE 3-2
NORTH END INTERCONNECTOR

-------
     Figure 3-3 shows a  flow  schematic  of  the Jackson Pike WWTP.  Table 3-1
identifies the specific unit processes and their respective facilities.

3.1.4  System Performance
     Wastewater characteristics  and operating performance for the Jackson Pike
plant were assembled from monthly summaries  of  plant operating data.  These
parameters are presented in Tables 3-2  through 3-4.  The following sections
discuss these  tables.

3.1.4.1  Influent Wastewater Characteristics
     Influent wastewater characteristics for 1985 are shown at the top of
Table 3-2.   The average  influent  carbonaceous biochemical oxygen demand
(CBODc) and total  suspended  solids  (TSS) concentrations  of 145 and  185 mg/L
represent low to medium strength domestic  sewage.  Ammonia and phosphorus
concentrations represent a weak domestic sewage.

3.1.4.2  Final Effluent Quality
     The effluent wastewater  characteristics for 1985 are shown at the bottom
of Table 3-2.   The yearly average CBODe,  and TSS  concentrations  are 16 mg/1 and
8 mg/1, respectively.  Table 3-3 shows  the 1985 monthly average raw, settled,
and final concentrations for CBOD^ and TSS.  The annual  average  removal rate
for CBODe  is 90 percent.  The TSS annual average removal rate is 96 percent.
Table 3-4 presents monthly nitrification data for 1985.   Effluent  ammonia
concentrations range from 57  to 90 percent of influent ammonia concentrations.

     Effluent limitations for the Jackson Pike plant are specified in OEPA
Permit No.  4PFOOOOO*HD.   The plant  is  currently  operating under  interim
effluent limitations established by the  permit.   The  interim  limitations
require a 25/30 effluent (i.e.  CBOD/TSS;  30-day  average).  The permit also
sets forth  a compliance schedule  for attainment  of  compliance with final
effluent limitations.  The final limits established by the permit for the
Jackson Pike plant have been previously presented in Table 1-1.   The final
limits are more stringent than the interim limits with respect to CBODc and
                                      3-5

-------
                                                      PLANT  '
                                      PRIMARY
                                    CLARIFICATION
                               AERATION
RAW
INFLUENT
                PUMPING
      SCREENING
PREAERATION
                                      PRIMARY
                                    CLARIFICATION
                             PLANT 'B'
                           PREAERATIDN
                                AERATION
                                              PRIMARY
                                              SLUDGE
                                              HOLDING
                   INCINERATION
          CENTRIFUGE
          DEVATERING
    SECONDARY
   CLARIFICATION
                                                                                  CHLORINATION
    SECONDARY
   CLARIFICATION
                                                       DIGESTED
                                                    SLUDGE HOLDING
 ANAEROBIC
 DIGESTION
                                                         THICKENED RAW SLUDGE
                                                         TO DEWATERING
                                                                                      VAS
                                                                                      HOLDING
                                                            CENTRIFUGE
                                                            THICKENING
                                                            VAS


                                                            THICKENED
                                                            SLUDGE
                                                            BLEND/STORAGE
                        TO
                     LANDFILL
            TO LAND
          APPLICATION
  THERMAL
CONDITIONING
FIGURE 3-3
JACKSON  PIKE  WWTP
FLOW SCHEMATIC

-------
                                    TABLE 3-1.  JACKSON PIKE EXISTING FACILITIES
Process
Screening
Pumping
Preaeration
Blower for Preaeratton and
  Aeration
Primary Clarification
Aeration
Secondary Clarification
Chlorination

Waste Activated Sludge
Holding
Facilities/Condition

Two mechanically cleaned bar screens
with 1-1/2" openings, west screen
replaced in 1983

Two variable speed at 55 MGD (32 ft TDK)
Two constant speed at 27.5 MGD (27.5 ft TDH)
One constant speed at 60 MGD (30 ft TDH)

Plant A - 2 tanks at 180 ft x 26 ft x 15 ft SWD
Plant B - 2 tanks at 113 ft x 26 ft x 15 ft SWD

4 at 21,000 cfm
2 at 15,000 cfm
2 at  3,000 cfm
3 at 12,500 cfm

Plant A - 4 tanks at 150 ft x 80 ft x 10 ft SWD
Plant B - 4 tanks at 150 ft x 80 ft x 10 ft SWD
Twelve sludge pumps at 250 gpm each

Plant A - 8 tanks at 900 ft x 26 ft x 15 ft SWD
Plant B - 4 tanks at 900 ft x 26 ft x 15 ft SWD

Plant A - 8 tanks at 153 ft x 60 ft x 12.5 ft SWD
Plant B - 4 tanks at 153 ft x 60 ft x 12.5 ft SWD
six return sludge pumps; one at 6,944 gpra,
one at 5,555 gpm, one at 5,902 gpm, one at
3,889 gpm, and two at 3,472 gpra each

By direct injection into discharge pipeline

One 78-foot x 14-foot x 8-foot deep basin
(two) standby units
Comments/Sizes/Capacities
165 MGD
1.05 MG total volume
0.66 MG total volume
48,000 SF total surface area
48,000 SF total surface area
21.0 MG total volume
10.5 MG total volume

73,440 SF total surface area
36,720 SF total surface area
0.065 MG of storage

-------
                                     TABLE 3-1.  JACKSON PIKE EXISTING FACILITIES (cont.)
     Process
                              Facilitj.es/CondLtions
Id

OO
     Primary Sludge Holding        One 85-foot dia., 25.25-foot SWD

     Centrifuge Thickening (WAS)   Two solid bowl centrifuges
Anaerobic Digestion




Digested Sludge Holding

Thermal Conditioning


Centrifuge Dewatering



Incineration


Ash Lagoon


Landfill

Land Application

     Sludge Transport and
     Application


     Application Sites
Eight Primary Digesters:
70-foot dia., 27.5-foot SWD
Six Secondary Digesters*
85-foot dia., 23.5-foot SWD

One 85-foot dia., 25.5-foot SWD

Two Reactors installed 1972,
Expanded 1978 to 4 reactors

Six solid bowl centrifuges
Installed 1976
                                   Two multiple-hearth  incinerators
                                   7-hearths,  22.25-foot diameter

                                   Two lagoons
                                    Incinerator ash landfilled on an as-
                                    needed basis through contract operation


                                    Contract Operation
                                   Required Acreage    2,000 Ac/yr
                                   Available Acreage  10,000 Ac
Comments/Sizes/Capacities

1 MG of storage

550 gpm/unit, 400 HP/unit
Feed Solids 1%
Thickened WAS 4%

Volume:  1.6 x 106 CF Total
         6.3 MG Primary
         6.0 MG Secondary


1.0 MG of storage

200 gpm/unit
100 gptn/unit, 100 HP/unit
Feed Solids 31
Dewatered Cake 16-18JS

170 wet tons/day
Feed Solids 16-18%

Total storage capacity 48,000 cy;
Cleaned as needed
                                                    Transport 130-150 tons/day
                                                    Application 70-200 tons/day
                                                    Approximate Unit Cost of $ll/wet ton

                                                    Application 260 days/yr
                                                    Seasonal peaks dependent
                                                    on weather and cropping patterns

-------
  TABLE 3-2.  1985 OPERATING DATA JACKSON PIKE WWTP
Parameter
INFLUENT
Flow, ragd
CBOD5, mg/1
TSS, mg/1
COD, mg/1
Ammonia, mg/1
Nitrite, mg/1
Nitrate, rag/1
TKN, mg/1
Total
Phosphorus, mg/1
EFFLUENT
TSS, mg/1
CBOD5, mg/1
DO, mg/1
COD, mg/1
Ammonia, mg/1
Nitrite, mg/1
Nitrate, mg/1
TKN, mg/1
Total
Phosphorus, mg/1
Fecal Coli form
(count/100 ml)
Average
84.3
145.0
185.0
359.0
U.O
0.17
0.9
20.6
6.4
8.0
16.3
4.6
39.6
3.1
0.58
10.4
4.9
4.4
9.2
Maximum
Monthly
Average
95.1
179.0
235.0
429.0
14.4
0.57
4.8
24.9
7.8
16.0
25.5
6.9
47.9
5.0
1.37
13.3
6.9
6.2
20.0
Minimum
Monthly
Average
74.5
124.0
141.0
275.0
6.3
0.02
0.2
15.1
4.8
5.0
2.03
3.4
30.1
0.6
0.15
8.3
2.2
3.3
3.5
Source:  Plant Operating Reports
                         3-9

-------
            TABLE 3-3.  JACKSON PIKE WWTP 1985 PERFORMANCE DATA

CBOD5
January
February
March
April
May
June
July
August
September
October
November
December
Average
SUSPENDED
January
February
March
April
May
June
July
August
September
October
November
December
Average
Raw (mg/1)

179
159
133
132
135
164
137
141
142
167
125
124
145
SOLIDS
182
173
172
149
186
235
219
190
182
193
192
141
185
% Removal
Raw to
Settled (mg/1) Settling

102
95
100
91
72
98
95
99
101
113
65
69
92

66
98
75
65
61
83
100
86
69
79
55
56
74

43
40
25
31
47
40
31
30
29
32
48
44
37

64
43
56
56
67
65
54
55
62
59
71
60
64
Final (mg/1)

21
18
12
22
13
17
15
2
18
26
7
J_
16

10
9
7
7
7
9
5
8
5
16
9
_6
8
% Removal
Raw to
Final

88
89
91
83
90
90
89
99
87
84
94
94
90

95
95
96
95
96
96
98
96
97
92
95
i6.
96
Source:  Plant Operating Reports
                                     3-10

-------
         1  TABLE 3-4.  JACKSON PIKE WWTP NITRIFICATION DATA - 1985






               Ammonia (mg/l)	Nitrite (mg/1)	Nitrate (mg/1)

January
February
March
April
May
June
July
August
September
October
November
December
Average
Raw
13.4
x
11.5
9.3
10.6
9.8
12.0
10.4
11.5
13.4
14.4
6.3
9.0
11.0
Final
2.8
1.7
1.7
4.2
2.2
4.3
4.4
5.0
5.0
3.8
0.6
1.9
3.1
% Reduction
79
85
82
60
78
64
58
57
63
74
90
Zi
72
Raw
0.05
0.41
0.38
0.14
0.12
0.02
0.02
0.02
0.02
0.02
0.32
0.57
0.17
Final
1.37
0.61
0.35
0.59
0.47
0.50
0.54
0.62
0.60
0.52
0.15
0.68
0.58
Raw
0.4
1.8
1.0
0.4
0.3
0.2
0.2
0.2
0.2
0.2
0.6
4.8
0.9
Final
11.1
13.3
11.7
10.2
11.0
9.9
9.6
8.3
9.1
10.1
10.5
9.6
10.4
Source:  Plant Operating Reports
                                       3-11

-------
TSS, and include discharge limitations on ammonia and establish a minimum

dissolved oxygen concentration which must be maintained in the final effluent.

The compliance  schedule stipulates that construction of wet stream facilities

must be completed prior to May 23, 1988,  and final effluent  limitations  must

be attained  no  later  than July lj  1988.


     Operating data presented in Table 3-2 through 3-4 illustrates that  the

Jackson Pike WWTP is not capable of consistently meeting the final effluent

limitations without upgrading and expansion.  The monthly average CBOD^
concentrations shown in Table 3-3 exceed  the final 30-day  permit  limits  six

months of the year.  The required minimum dissolved oxygen concentration of

7.0 rag/1 was never achieved (Table 3-2).  Ammonia limits were exceeded for the

months of June  through  October (Table  3-4).


3.1.5  Present Condition of Plant

     In August and September of  1985, a detailed survey of the facilities at

the Jackson Pike Wastewater Treatment Plant was conducted.  The purpose  of the

survey was to determine the remaining  useful service life of existing

equipment and structures.   The conclusions  of the survey,  taken from the

General Engineering Report and Basis of Design prepared by URS Dalton (January
1986),  are  listed below:


     •  Tanks                 Visual inspection of the open-air tanks out of
                              service indicates that  the majority of the
                              concrete deterioration has occurred above  the
                              water line,  with the concrete below in good
                              condition.  A  complete  handrail system is  needed
                              around all  the open-air tanks but can only be
                              constructed after concrete restoration.

     •  Buildings             Work is required on all buildings, some of which
                              are in need of more extensive rehabilitation
                              than others.   Those  requiring the most work are
                              either the  oldest or subjected to the most
                              severe environment.  These include  the
                              Incinerator Buildings,  Boiler Building, Sludge
                              Control House No. 2 and the Bar Screen Building.
                                      3-12

-------
        Power System
        Instrumentation
        & Control
        HVAC
        Plumbing

        Wet Stream Process
     •  Solids Handling
The power  system  is generally adequate and in
good condition.  Two transformer substations in
the Aeration Control Building "A" should be
replaced along with the motor control center in
Aeration Control Building "B".   The power
generator system should be abandoned.  Part of
the site is not lighted and should have pole
fixtures installed.

Inadequate.  The  I&C system requires complete
replacement and expansion to meet final NPDES
limitations.

In general, the buildings appear to have
adequate heating and the heating equipment
overall has been kept in good condition.
Buildings that have ventilation equipment
generally have the equipment in operation.  Each
building should be evaluated on an individual
basis to determine heating and ventilation
requirements.

Adequate.   Some renovation required.

There is a significant amount of useful life in
the raw sewage pumps,  the main air blowers, and
the primary sludge pumping system.   However,  the
primary collection mechanisms, air diffusion
equipment and secondary clarifier equipment
need to be replaced.

Adequate,  but requires  renovations  and minor
expansions due to the  need for increased
pollutant removals.
3.2  SOUTHERLY WASTEWATER TREATMENT PLANT

     The Southerly Wastewater Treatment Plant began operation in 1967 with a

single treatment train.  In the  early seventies,  an additional wet  stream

train was constructed.  The original wet stream treatment train is  termed the
Center Section.   The newer train is called the West Section.


3.2.1  Major Interceptors

     Southerly receives approximately 50 to 60 MGD via the Big Walnut Sanitary

Outfall Sewer which  serves the northeast, east, and  southeast portions of

Columbus and Franklin County.  An additional 5 MGD of flow is carried
                                     3-13

-------
 to  Southerly by  the Interconnector Sewer which serves a portion of western
 Columbus.

 3.2.2  Interconnector Pump Station
     The purpose of the Interconnector Pump Station is to pump flows from the
 Interconnector across the Scioto River to the Southerly WWTP.  The
 Interconnfctor Pump Station is located on the south end of the Interconnector
 near Southerly (Figure 3-4).   Flows from the 156-inch Interconnector Sewer
 enter a 58-foot wide by 25-foot long by 16-foot deep chamber to be distributed
 to three channels containing coarse bar racks and mechanically-cleaned bar
 screens.   Each channel is  6 feet  wide by 30 feet  long.   Flows from the
 screening channels enter a 20-foot  wide by  66-foot long by 23-foot high wet
 well and are pumped by two 20 MGD and two 30 MGD extended shaft centrifugal
 pumps through one 36-inch and  one 48-inch  force  main to the Southerly
 headworks.
3.2.3  Treatment Processes
     The Southerly Wastewater Treatment Plant consists of the following
treatment processes:

     •  Preliminary Treatment
     •  Primary Treatment
     •  Secondary Treatment
     •  Disinfection
     •  Solids Handling
     •  Solids Disposal.

     A schematic flow diagram of  the  facilities  is presented  in Figue 3-5.
Table 3-5 identifies the specific unit processes  and  their respective
facilities.
                                      3-14

-------
                            \  \
                                ^
                             \
            EXISTING 156
           I-.-.
t*l
                            ............
                         //
                                \
            INTERCONNECTOR SEWER   I
                                EXISTING PUMPING
                                STATION
                                                                    UJ
                                                                    t
                                                                    CO
                                                                    o
                                                                   I o
                                                                    UJ
                                                                                    \   \
                    \
i
t-»
ui
         /
        /  /
       /  '

      /  '
/I/
 /   /
\   \
                                 EXISTING 48" & 36" FORCE MAINS   /
                                 AND SLUDGE LINE             /
 SCALE: r=500*
 SOURCE. REVISED FACILITY PLAN UPDATE
                                               Y
                                     CU
                     ODO   ,—-      n
                     OnO   '—'
                ^ODO
                c±J CD
                                                       D   D
                                            SOUTHERLY WW.TP
                                                                FIGURE 3-4

                                                                SOUTH END INTERCONNECTOR

-------
                                       CENTER TRAIN
                       PREAERATION
       SCREENING
RAW
INFLUENT
              GRIT REMOVAL
 U)
                       PREAERATION
                      CENTRIFUGE
                      DEWATERING
            PRIMARY
         CLARIFICATION
                                                                 AERATION
                                              SECONDARY
                                            CLARIFICATION
                                                    CHLDRINATION
            PRIMARY
         CLARIFICATION
                     EFFLUENT
VEST  TRAIN
                                                                      SECONDARY
                                                                    CLARIFICATION
     ANAEROBIC
     DIGESTION
     (UNDER REHABILITATION)
CENTRIFUGE
THICKENING
   WAS
DISSOLVED AIR
  FLOTATION
  THICKENING
 (ABANDONED)
                                             DEVATERED
                                             SLUDGE
                                             STORAGE
                      INCINERATION
                  TO
                AMTlCTt I
                  '
               TO
           COMPOSTING
                                                                                          THERMAL
                                                                                        CONDITIONING
                                                                                        (ABANDONED)
           FIGURE 3-5
           SOUTHERLY  WTP
           FT.nW SCHF.MATTO

-------
                                      TABLE 3-5.  SOUTHERLY WWTP EXISTING FACILITIES
  Process

  Screening


  Grit Removal



  Pumping



  Preaeration



i>>
i Primary Clarification
-j


  Aeration



  Secondary Clarification
  Disinfection
   Dissolved Air Flotation
   Thickening  (WAS)
Facilities/Condition

Four bar racks with 5.5-inch openings
Four mechanical bar screens with 1-inch openings

Two aerated grit tanks at 44.5 ft x 20 ft x  13.5  ft SWD
Two aerated grit tanks at 51.2 ft x 20 ft x  13.5  ft SWD
Two variable speed blowers at 960 cfm each

Three variable speed pumps at 35 MOD (38 feet TDK)
Two variable speed pumps at 65 MGD (42 feet  TDU)
One constant speed pump at 35 MGD (38 feet TDH)

Center Train - 4 tanks at 112.7 ft x 26 ft x 15.5  ft  SWD
West Train - 4 tanks at 112.7 ft x 26 ft x 15.5  ft SWD
Three constant speed blowers at 3,400 cfm each

Center Train - 4 tanks at 80 ft x 165 ft x 10 ft  SWD
West Train - 4 tanks at 100 ft x 170 ft x 10 ft  SWD
Twelve sludge pumps at 150 gpra each

Center Train - 4 tanks at 26 ft x 900 ft x 15 ft  SWD
West Train - 6 tanks at 26 ft x 900 ft x 15  ft SWD
Nine blowers at 20,000 cfm each

Center Train - 4 tanks at 89 ft x 170 ft x 12.5  ft SWD
West Train - 4 tanks at 104 ft x 180 ft x 10.5 ft SWD
Return sludge pumps - 4 at 7,000 gpra each,
4 at 10,500 gpm each, 4 at 8,100 gpra each,
4 at 12,000 gpra each
Waste-activated sludge pumps - 8 at 200 gpm  each

Six 2,000 Ib/day chlorinators
Six 8,000 Ib/day evaporators
One chlorine contact basin at 260 ft x 260 ft x  7 ft  SWD

Four units (§ 1,900 SF/unit
(Abandoned 1978 used as
WAS concentration tanks)
Comments/Sizes/Capacitles
0.39 MG total volume
170 MGD
1.36 MG total volume
1.36 MG total volume
52,800 SF total surface area
68,000 SF total surface area
10.5 MG total volume
15.8 MG total volume

-------
                                     TABLE 3-5.   SOUTHERLY WWTP EXISTING FACILITIES (cont.)
  Process

  Centrifuge Thickening
  (WAS)
  Anaerobic Digestion
  Thermal Conditioning
  Centrifuge Dewatering
OJ
i
00
  Dewatered Sludge
  Storage

  Transport to Composting
  Composting


  Compost Disposal


  Incineration



  Ash Lagoon


  Landfill
Fac Hit le s /Cond i t ion

Four solid bowl centrifuges
Pre-Project 88, Contract #19
Mot yet fully operational

Four Primary Digestions;
85-foot dia., 25.25-foot SWD
Two Secondary Digesters;
85-foot dia., 25.25-foot SWD
Construction date 1965

Three Reactors
Installed 1974, Abandoned 1980

Six solid bowl centrifuges
Operational approx. 7 years
Dewatered cake 16-18%

One storage bin.
4-8 trucks @ 25 wet tons
Hrs of operation 56 hrs/wk

Extended aerated static pile system
Product removed by truck
Two existing multiple hearth units;
Two new multiple hearth units
under construction

Two lagoons
 Incinerator ash landfilled on an  as-needed
 basis  through contract operations
Comments/Sizes/Capacities

200 gpra/unit
Feed Solids 1%
Thickened WAS 5%

Volume of 972,000 CF total
          4.8 MG primary
          2.4 MG secondary
200 gpra/unit
100 gpra/unit
Feed solids 3.5%
Volume of 400 cy/300 wet tons
Haul distance of 7 miles roundtrip
120-200 wet tons/day
dependent on sludge and weather

Disposal through bulk sales to
public and private consumers

150 wet tons/day existing
260 wet tons/day new
Total storage capacity 76,000 cy;
Cleaned as needed

-------
     Construction of additional facilities is presently taking place at
Southerly.  These new facilities were not included in Table 3-5.  This
construction phase is called Project 88.  This construction is being
undertaken by the city as part  of their  Municipal Compliance Plan to bring the
treatment facilities into compliance with revised NPDES permit limits by
July 1, 1988.   It includes the following:

     •  4 preaeration tanks
     •  2 primary settling tanks
     •  6 aeration tanks
     •  6 secondary settling tanks
     •  chlorination/dechlorination/post aeration facilities
     •  4 gravity thickeners
     •  4 DPF dewatering presses
     •  sludge cake storage facilities
     •  lime stabilization facilities.

3.2.4  System Performance
     Monthly summaries of wastewater characteristics and operating performance
for the Southerly plant were assembled from plant records and reports.   These
summaries are presented  in Tables 3-6 through 3-8.  The following paragraphs
discuss these tables.

3.2.4.1  Influent Wastewater Characteristics
     Influent wastewater characteristics for 1985 are  shown at the top  of
Table 3-6.   The  average BOD5 and  TSS levels  of  171 mg/1 and 193 mg/1,
respectively,  represent medium strength  domestic wastewater.   The  ammonia and
phosphorus concentrations represent  a weak domestic sewage.

3.2.4.2  Final Effluent Quality
     The bottom of Table  3-7  shows average, maximum monthly average, and
minimum monthly  average parameters  for the Southerly plant effluent during
1985.   These values do  not incorporate the flow  that  is bypassed directly to
                                      3-19

-------
   TABLE 3-6.   SOUTHERLY WWTP 1985  OPERATING DATA
Parameter
INFLUENT
Flow, MGD
TSS, mg/1
CBOD5, mg/1
COD, mg/1
Ammonia, rag/1
Nitrite, mg/1
Nitrate, rag/ I
TKN, mg/1
Total
Phosphorus, rag/1
EFFLUENT
TSS, mg/1
CBOD5, mg/1
DO, mg/1
COD, mg/1
Ammonia, mg/1
Nitrite, mg/1
Nitrate, mg/l
TKN, mg/1
Total
Phosphorus, rag/1
Fecal Coliform
(count /100ml)
Average
64.8
193.0
171.0
433.0
12.4
0.04
0.2
24.6
7.5
8.0
11.0
8.1
38.0
3.8
0.63
5.0
5.8
1.4
386.0
Maximum
Monthly
Average
87.2
222.0
238.0
546.0
18.9
0.14
0.3
33.6
9.4
18.0
17.0
8.8
53.0
7.8
1.13
8.6
10.6
2.6
950.0
Minimum
Monthly
Average
51.7
139.0
115.0
328.0
8.2
0.02
0.2
17.7
5.1
5.0
7.0
7.6
27.0
1.2
0.28
2.2
3.2
0.8
119.0
Source:  Plant Operating Reports
                          3-20

-------
               TABLE 3-7.  SOUTHERLY WWTP 1985 PERFORMANCE DATA

CBOD5
January
February
March
April
May
June
July
Augus t
September
October
November
December
Average
SUSPENDED
January
February
March
April
May
June
July
Augus t
September
October
November
December
Average
Raw (mg/1)

183
149
139
160
163
183
171
189
233
238
115
134
171
SOLIDS
198
191
174
193
196
212
210
199
222
210
139
168
193
% Removal
Raw to
Settled (mg/1) Settling

122
109
92
97
123
142
128
132
151
185
88
91
122

85
88
74
79
99
120
96
86
83
120
75
65
89

33
27
34
39
25
22
25
30
35
22
23
32
29

57
54
57
59
49
43
54
57
63
43
46
6.1
54
Final (mg/1)

14
11
10
13
17
15
8
7
8
8
9
_9
11

7
10
13
9
18
7
5
6
7
5
10
_6
8
% Removal
Raw to
Final

92
93
93
92
90
92
95
96
97
97
92
93_
94

96
95
93
95
91
97
98
97
97
98
93
96
96
Source:  Plant Operating Reports
                                     3-21

-------
             TABLE 3-8.  SOUTHERLY WWTP NITRIFICATION DATA - 1985
                Ammonia  (mg/1)
Nitrite (mg/1)
Nitrate (mg/1)

January
February
March
April
May
June
July
August
September
October
November
December
AVERAGE
Raw
12.9
11.0
9.2
11.1
11.6
13.9
11.3
12,3
18.0
18.9
8.2
10.7
12.4
Final
5.0
5.7
2.9
3.3
4.0
4.8
1.8
1.2
3.1
7.8
3.0
2.8
3.8
Z Reduction
61
48
68
70
66
65
84
90
83
59
63
74
69
Raw
0.04
0.05
0.06
0.05
0.02
0.02
0.02
0.02
0.02
0.02
0.14
0.04
0.04
Final
1.13
0.94
0.85
0.52
0.63
0.97
0.55
0.28
0.52
0.56
0.33
0.30
0.63
Raw
0.2
0.3
0.3
0.2
0.2
0.2
0.2
0.2
0.2
0.2
0.3
0.2
0.2
Final
3.1
2.2
2.8
4.7
4.1
4.6
7.1
7.5
8.6
6.3
4.0
4.4
5.0
Source:  Plant Operating Reports
                                     3-22

-------
the Scioto River.  The annual average CBOD^ and TSS concentrations are 11 mg/1
and 8 mg/1, respectively.  Table 3-7 shows the 1985 monthly average raw,
settled, and  final concentrations for CBOD^ and TSS.  The CBOD«j annual average
removal  rate  is  94 percent.  The TSS annual average removal rate is 96
percent.  Table 3-8 presents monthly nitrification data for 1985.  The
effluent ammonia concentrations range from 48 to 90 percent of the influent
ammonia concentrations.

     Similar  to  the Jackson Pike WWTP, the Southerly WWTP is also operating
under interim effluent limits of 25/30 as established in OEPA Permit No.
4PF00001*HD.  This permit also sets forth a compliance schedule for attainment
of compliance with final effluent limitations.  The final  effluent  limits were
presented in  Table 1-2.  The limits are more stringent with regards to CBODc,
TSS, and fecal coliform levels than the interim limits.   The final  limits also
include standards for dissolved oxygen and ammonia which are not included in
the current permit.  The  Southerly  WWTP must attain compliance with the final
limits by July 1, 1988.  Based on the operating data presented in Tables 3-6
through 3-8, the  Southerly WWTP is  not  be capable  of meeting these final
limits on a consistent basis without some  upgrading  or expansion.  The CBODc
limits were exceeded for the months of May  and  June  (Table 3-7), and the
ammonia  limits were  exceeded six months of the year (Table  3-8).

3.2.4.3  Operational  Considerations
     Storm flows periodically cause hydraulic overloading and operational
upsets at Southerly.   In  the past,  when the biological portion of the plant
was threatened by potential flooding, untreated influent was diverted to the
treatment plant bypass.  In 1983,  a cooperative effort by Ohio EPA and the
City to reduce bypassing resulted in another method of resolving this  problem
termed Blending of Flows.

     When incoming flows begin  to increase, the plant increases pumping rates.
When the biological part  of the  plant begins  to  show signs of potential
washout, then flow to the biological part is fixed.   Influent  flows above this
                                      3-23

-------
fixed flow, but less than the capacity of the primary tanks, are bypassed
around the biological portion and blended with the final effluent, thus
receiving only primary  treatment and  chlorination.  Once the primary treatment
facilities are operating at capacity, then influent flow above that rate is
bypassed directly to the Scioto River through a 108-inch diameter pipe
originating in the  screen building.

     In reviewing plant operating data it is difficult to pinpoint the exact
flow rate above which flows must be blended or bypassed.   Blending occurs at
flows as low  as 45  MGD  and  bypassing  occurs at flows as low as 65 MGD.  Table
3-9 gives information on the frequency of bypassing and blending.  The
average flow values in  the  table include treated, blended, and bypassed flows.
The occurrences of blending  and  bypassing  seem to correspond with the level of
precipitation and the time  of year.  The  monthly average precipitation for
1984 through 1986 is 3.0 inches.   The  greatest  frequency of bypassing and
blending occurs when the total monthly precipitation exceeds  this average.
However, during February and March of 1986,  the monthly precipitation totals
are slightly below average  and bypassing and blending occurs in significant
amounts.  This may be due to snowmelt.

     Southerly has also been plagued in the past by bulking problems.  A
bulking sludge exhibits poor settling characteristics and poor compactability.
Filamentous organisms are one of  the  principle causes of bulking due to their
poor floe-forming and settling characteristics.  Excessive organic loads in
the form of carbohydrates in the wastes can cause excessive growths of
filamentous bacteria, which in  turn cause bulking.

     The Anhueser-Busch Brewery contributes a considerable amount of organic
load to the Southerly plant. The brewery  has  a contract with the city dated
August 11,  1981,  which limits their discharge to 45,000 Ibs/day BOO averaged
over a month and 75,000 Ibs/day BOO on a daily basis.   It  is estimated that
the brewery contributes 40  percent of the organic load and 6 percent of the
hydraulic load to the Southerly WWTP.  Thus,  the  brewery loads are suspect as
a significant contributor to the bulking problem.
                                     3-24

-------
                      TABLE 3-9.  SOUTHERLY WWTP PLOW DATA
Month/Year
Flow
Average (MGD)
Blending
Freq. (days)/
Total (MG)
Bypassing
Freq. (days)/
Total (MG)
Precipitation
Total (Inches)
1/84
2/84
3/84
4/84
5/84
6/84
7/84
8/84
9/84
10/84
11/84
12/84
1/85
2/85
3/85
4/85
5/85
6/85
7/85
8/85
9/85
10/85
H/85
12/85
1/86
2/86
3/86
4/86
5/86
6/86
7/86
8/86
9/86
10/87
11/86
12/86
56.7
68.2
78.0
84.5
78.2
57.7
56.7
54.9
53.5
54.5
62.0
64.5
60.6
83.1
77.6
68.2
67.6
56.3
63.5
55.2
51.4
53.5
101.2
73.7
65.1
86.7
80.3
57.7
52.3
64.2
62.8
56.2
58.5
65.0
60.6
75.4
2/ND
10/ND
3/ND
4/ND
0/0
0/0
0/0
0/0
0/0
0/0
0/0
0/0
0/0
8/ND
8/ND
2/ND
10/ND
0/0
0/0
3/1.9
0/0
0/0
16/292
6/41
5/31
15/231
8/95
0/0
2/5.7
12/84
10/65
ND
ND
ND
ND
ND
2/ND
8/ND
9/ND
12/ND
16/ND
0/0
l/ND
0/0
0/0
2/ND
5/ND
3/ND
0/0
6/ND
4/ND
l/ND
2/ND
4/ND
6/ND
2/6.1
0/0
0/0
13/366
3/57
2/7.6
6/207
4/192
0/0
0/0
3/52
4/9.0
0/0
2/0.3
4/81
2/16
4/125
1.04
1.97
3.89
4.10
4.93
0.71
3.15
2.96
1.48
2.91
4.41
2.84
1.31
1.67
3.78
0.56
4.96
1.41
6.88
ND
ND
1.98
10.67
1.81
1.54
2.96
2.61
1.31
2.47
5.53
3.60
1.61
3.44
4.16
3.00
2.81
  Flow includes blended, bypassed, and treated flows.

  Source:  Plant Operating Reports

  ND - No Data Available
                                     3-25

-------
3.2.5 Present Condition ofPlant

     In August and September of 1985 an engineering team surveyed both
Columbus wastewater  treatment plants.  Their purpose was to determine the
remaining useful service life of the existing facilities.   The results of the
Southerly survey, taken from the General Engineering Report and Basis of
Design (January 1986) are listed below:
        Tanks
     •  Buildings
     *  Electrical
     •  HVAC
     •  Plumbing

     •  Instrumentation
        & Control

     •  Wet Stream Process
     *  Solids Handling
Minor concrete rehabilitation is needed.  Many
of the tanks,  walls,  and walkways exhibit
vertical and transverse cracks.

Work is required on practically all of the
buildings to repair cracks in the concrete,  roof
leaks, and damaged handrails.

A new primary  loop is required for future expan-
sion.

The majority of the buildings appear to have
inadequate or no ventilation and  some facilities
have less heat than is required.   The equipment
does not operate or is in poor condition due to
an apparent lack of regularly scheduled preven-
tive maintenance.

Some O&K renovation required.

The I & C system requires renovation and
expansion.

The wet stream process equipment  is well
maintained but it is incapable of effectively
treating its design capacity of 100 MGD.
Sometimes flows are bypassed around the
biological  portion of the plant  and receive  only
primary treatment and chlorinatxon or else they
are directly bypassed to the Scioto River.

All sludge pumps should be replaced.  Digesters
need to be  rehabilitated.   Minor  expansion of
existing facilities is required.
                                    3-26

-------
3.3  COMBINED SEWER OVERFLOW
     The Columbus wastewater collection system includes an area of 10.7
square miles that is served by a combined stormwater and wastewater collection
system (Figure 3-1).  This constitutes approximately 7 percent of the service
areas of the two Columbus wastewater  treatment plants.  Points of combined
sewer overflow  in the City include 21 regulator chambers, 3 overflow
structures and 2 storm tanks.  These  structures detain and  divert  wet  weather
combined sewer flows that would otherwise hydraulically overload the Jackson
Pike and Southerly wastewater treatment  plants.  The locations of CSO are
listed in Table 3-10 and shown  on Figure 3-6.

     Seven of the regulator chambers discharge to the Olentangy River and
eleven overflow to  the Scioto River.  Two of the regulator chambers discharge
overflows to storm sewers.  One of the regulatory chambers  diverts  overflows
to the Old Main Interceptor  while the outfall of the last regulatory chamber
(Sullivant Avenue) has been  bulkheaded causing  local  surcharging during wet
weather periods.

     Two of the overflow structures discharge to the Scioto River through
24-inch and 18-inch pipes.   The  third  overflow  structure  discharges  to Alum
Creek via a 48-inch storm sewer.

     The Whittier Street Storm Detention Tanks, situated south of  Whittier
Street on the east bank of the Scioto River,  were designed  to provide  relief
for wet weather combined  sewage flow in the O.S.I.S.   The three equal  volume,  open,
reinforced concrete tanks provide a total storage capacity of 4,011,000
gallons.   They are capable of acting as  a holding system  for flows until  the
flow in the interceptor subsides and  they can be  bled back  into the  system and
carried to the Jackson Pike WWTP.  If the flows exceed the capacity of the
tanks,  they overflow to the Scioto River. Flows  can also be directly  bypassed
along side the tanks,  through an emergency bypass,  to the Scioto  River.
                                     3-27

-------
TABLE 3-10.  SUMMARY OF BYPASS AND CSO LOCATIONS IN THE COLUMBUS PLANNING AREA
OUTFALL
NUMBER

001
002
003
004
005
006
007
008
009
010
on
012
013
014
015
016
017
018
019
020
021
022
023
025
026
027
028
029
030
031
032
033
034
035
036

001
002
003
004
005
006
007

DECRIPTION - LOCATION
JACKSON PIKE WWTP
Jackson Pike WWTP final effluent
Plant raw sewage bypass
Plant settled sewage bypass
Regulator chamber - Hudson Street
Regulator chamber - Frambes Avenue
Regulator chamber - OSU Water Res.
Regulator chamber - King Avenue
Regulator chamber - Cozzins Street
Regulator chamber - West Street
Regulator chamber - Chestnut Street
Regulator chamber - Spring Street
Regulator chamber - Long Street
Overflow structure - Capital Street
Overflow structure - State Street
Regulator chamber - Town Street
Regulator chamber - Rich Street
Regulator chamber - Broad Street
Storm standby tanks - Win t tier Street
Bypass - Whittier Street standby tank
Regulator chamber - Holer Street
Sluice gate - Mound Street
Overflow - Sewer Maintenance Yard
Overflow - Williams Road pump station
Overflow - Neff Avenue pump station
Overflow - Frank Road - South High Street
Sanitary relief - 3rd Avenue
Regulator chamber - Henry Street
Regulator chamber - Markinson Avenue
Regulator chamber - Whittier Street
Regulator chamber - First Avenue
Regulator chamber - Third Avenue
Regulator chamber - Doe Alley
Regulator chamber - Peter's Run
Regulator chamber - Spring & West Street
Regulator chamber - Sullivant Avenue
COLUMBUS SOUTHERLY WWTP
Southerly WWTP final effluent
Plant raw sewage bypass
Plant settled sewage bypass
Overflow structure - Roads End
Alum Creek storm standby tank
Alum Creek storm standby tank
Ash lagoons
RECEIVING
STREAM

Scioto River
Scioto River
Scioto River
Olentangy River
Olentangy River
Olentangy River
Olentangy River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Scioto River
Kian Run
Kian Run
Olentangy River
Scioto River
Scioto River
Scioto River
Olentangy River
Olentangy River
Olentangy River
Scioto River
Scioto River
Scioto River

Scioto River
Scioto River
Scioto River
Alum Creek
Alum Creek
Alum creek
Scioto River
Source:  Central Scioto River Mainstern CWQR - 1985
                                3-28

-------
                •JACKSON PIKE  WWTP
SOURCE.  CENTRAL SCIOTO RIVER
       MAINSTEM CWQR-1985
• = OVERFLOW STRUCTURE
A = REGULATOR OVERFLOW CHAMBER
• - STORM STAND-BY TANK FACILITY
• = JACKSON PIKE WWTP FiNAL EFFLUENT
    APPROXIMATE SCALE. 1  INCH = 1  MILE
                               FIGURE 3-6
                               LOCATIONS OF COMBINED SEWER OVERFLOW
                                   3-29

-------
     The Alum  Creek  Storm Tank is  situated on the west bank of Alum Creek just
 south of Main  Street.  This covered reinforced tank provides a storage
 capacity of 857,000 gallons before overflows are bypassed to Alum Creek.   A
 sewer separation program  is taking place in the portion of the Southerly
 service area that  is tributary to the Alum Creek Storm Tanks  (Figure 3-1).   It
 is being undertaken  to address localized surface and residential flooding
 problems.  The city expects that the potential for an overflow will be greatly
 reduced; however,  the actual amount of  the reduction has not been quantified.

     An evaluation of all overflow points from October 1977 to October 1978 is
 contained in the Combined  Sewer Overflow Monitoring Report  prepared  by Malcolm
 Pirnie,  Inc.  This  study indicated  that  over 90  percent of  the  overflow volume
 is discharged through the Whittier Street Storm Detention Tanks, 7.5 percent
 is discharged at the Alum Creek Storm Tank, and the remaining 2.5 percent is
discharged through the regulators and other minor points of overflow.
Overflows monitored during the Combined Sewer Overflow Monitoring study
conservatively estimated overflows from the Whittier Street Storm Detention
Tanks,  Alum Creek  Storm Tank, and all other overflow points at 2200, 184, and
 55 million gallons per year, respectively.

     Following completion of the Combined Sewer Overflow Monitoring Report,
OEPA authorized an evaluation of combined sewer  overflow  effects on  the Scioto
River.   This  study, entitled Combined Sewer Overflow Progress Report - July
 1983,  asserts  that during periods of medium to high stream flow,  dissolved
oxygen and BODc concentrations in the Scioto River are largely unaffected by
loadings from combined sewer overflows.  However, during periods of  low river
 flow, the study maintains that the overflow loadings drop the dissolved oxygen
concentration of the river slightly below recommended concentration  (5.0  mg/1)
and cause an increase in stream BODr concentrations.

3.4 SOUTHWESTERLY COMPOSTING FACILITY
     The Southwesterly Compost Facility is located approximately 7 miles  south
of the Jackson  Pike Uastewater Treatment Plant  and  2 miles  due  west  of the
                                      3-30

-------
Southerly Wastewater  Treatment Plant.  Construction began in May  1980.
Composting began on site  in July  1980.

     The plant uses the extended-pile aeration method of composting and was
originally designed to handle 200 wet tons of sludge/day.  It was the first
facility of its type in the midwest  and has attracted considerable attention
from a variety of  interested  groups.

     Dewatered primary and waste  activated  sludge  is trucked to the site and
mixed with a bulking agent,  either previously composted material or woodchips.
The mixture is then placed on a 12-inch deep layer of woodchips,  in which
perforated plastic pipes have been buried.   A pile,  10-feet  high,  250-feet
long,  and 8-feet wide, is generated daily.   An 18-inch layer of previously
composted material is placed  over the pile to provide insulation.  Air is
drawn through the pile by small blowers attached to the buried pipes and
exhausted into a deodorizing pile of woodchips and unscreened compost.  The
composting operation takes approximately 21  days  and  requires a minimum of
three consecutive days with temperatures greater than 55 degrees Centigrade.
Following the composting  period, the piles are torn down and restacked for a
curing period of 30 days.  After this period,  the mixture is screened and the
woodchips recovered for reuse.

     This process creates  one difficulty for Columbus.   Typically,  material
composted by the aerated  static pile  method,  utilizing low aeration rates,
does not dry significantly during the composting or the curing period.
Columbus realized, early in their operation,  that additional drying was
required if they were going to compost 200 wet tons of  sludge per day.

     Additional drying of  compost  may be obtained by either  a passive solar
process or some mechanical method.  Passive solar drying consists of spreading
composted and cured material on a  drying  area and continually stirring it with
a tractor and harrow while it  is dried by the sun and wind.   This  method
requires a large area and  is labor intensive.  This method would  not be
                                      3-31

-------
 sufficient  to handle solids generated at Southwesterly.  Therefore, the city
 chose to implement a mechanical  method  of  drying.

     A mechanized drying  system  was  recently  installed at Southwesterly.  The
 system  consists of reactor bins, conveyor belts, and air handling units in a
 70  foot by  338 foot building.   There are two reactor bins that are 200 feet
 long by 20  feet wide and  10 feet deep.  Front-end loaders carry cured compost
 into the building and dump it  into a bin feeder-hopper.  From there it is
 conveyed onto a 48-inch conveyor  belt which delivers the material to the bins
 utilizing a tripper car and a shuttle conveyor.  The material is placed in the
 bins and will be dried until proper moisture is obtained.  The material is
 turned and  eventually withdrawn  from the bins by a digging machine.  As the
 material is removed from  the bins it is discharged to a conveyor belt,  which
 carries the dried cured compost  into  the next  building for screening.

     The drying bins are aerated from beneath by 4 large air handling units.
The units are completely  self-contained with  integral fans, heat exchangers,
 and monitoring equipment.   They transfer heat  from water to air for drying
compost.  Heat collection for the hot water system is accomplished by a solar
collection  field.   On some occasions only ambient air is used for drying.

     Biological drying can also occur in the compost under the right
conditions.   Biological drying occurs as a  result of the  inherent biological
activity in the composted mass.  Oxygen is required to maintain this
biological activity.  Microorganisms generate  heat which in turn evaporates
moisture in the pile.   This biological drying  can occur in the aerated curing
piles and in the solar drying  building where forced air  is available.

     The mechanized drying system provides an efficient means of drying
compost 365 days a year and permits  Southwesterly  the capability of
processing  their original  design capacity  of 200 wet tons of sludge/day.   The
final product of the composting process, Corn-Til,  is  marketed as a soil
conditioner and top soil  substitute.
                                     3-32

-------
     The city owns approximately 200 acres of land at the Southwesterly
facility,  approximately 15 to 25  percent  of which is being used to process and
store compost.  Table 3-11 shows the quantities of incoming sludge to the
compost facility from January 1984 to September  1986.   A total of 130,560
wet tons of sludge were processed during that period.  This is  approximately
129 tons/day,  or 30 percent of the total  sludge production at Southerly.
                                     3-33

-------
TABLE 3-11.  SOUTHWESTERLY COMPOST FACILITY OPERATING DATA






                                      INCOMING SLUDGE (Wet Tons)

January
February
March
April
Hay
June
July
August
September
October
November
December
TOTAL (Wet Tons)
DAILY AVERAGE (Wet Tons/Day)
PERCENT SOLIDS INCOMING SLUDGE
DAILY AVERAGE (Dry Tons/Day)
1984
3,929
5,056
6,632
5,630
6,091
3,116
4,179
4,970
4,836
6,446
5,502
3,517
59,904
164
15.8
25.9
1985
2,920
3,062
3,622
2,559
3,878
4,233
3,390
3,498
3,626
2,317
3,733
2,454
39,292
108
17.0
18.3
1986
3,142
3,158
1,470
4,197
4,623
3,926
3,473
3,844
3,531
—
—
—
31,364
115
17.3
19.9
   Source:   Plant  Operating Reports
                                3-34

-------
        CHAPTER 4.  EVALUATION OF WASTEWATER MANAGEMENT DESIGN FACTORS

     In the facility planning process, once the objectives have been
established and base line conditions described, the next major task is
identification of reliable design criteria.  The establishment of design
criteria involved reviewing existing regulations and guidelines and projecting
future conditions in the planning area to serve as a base line in evaluating
facility needs and  alternatives.
     The basic design factors described in this chapter are:

     •  Planning Period
     •  Population
     •  Land Use
     •  Wastewater Flows and Loads
     *  Combined Sewer Overflows.

     Existing and projected wastewater  flows and loads are based on a detailed
analysis,  documented in Briefing Paper No.  1 -  Wastewater Flows and Loads,
which is contained in Appendix A.  Data contained in the facility planning
documents was evaluated to develop an accurate picture of existing conditions
and to project future conditions.

     Currently,  the city of Columbus does not have adequate data documenting
the quality and quantity of combined sewer overflows  (CSO).  In the fall  of
1987 the city of Columbus began an extensive study of the CSO problem. The
USEPA conducted an independent study and literature search of the CSO problem.
This study is summarized in  this chapter and is described more fully in
Appendix S entitled Briefing Paper No.  5 -  Combined Sewer Overflows.
                                     4-1

-------
4.1  PLANNING PERIOD
     The USEPA regulations mandate a 20-year planning period.   The planning
period established by USEPA for this SEIS is July 1,  1988, through July 1,
2008.

     In 1985 the city of Columbus published the Revised Facility Plan Update,
which recommended a one-plant approach to meeting Clean Water Act
requirements.  Previously, the city had promoted upgrading the existing
Jackson Pike and Southerly WWTPs.  The planning period selected in the update
report is  30 years  (1985-2015).

     The Clean Water Act requires that wastewater treatment facilities be in
compliance with final NPDES Permit requirements by July 1, 1988.   Construction
is presently underway at both treatment plants to meet the final  NPOES permit
limits.  Currently,  the city is operating under interim  permit limits until
1988.

     This description of the determination of the SEIS planning period takes
precedence in this chapter because it sets the boundaries  for the discussion
of design criteria used in this chapter.  Existing and projected population,
land use,  and wastewater flows and loads are based on a 20-year planning
period which is different from the planning period used in the facility plan.

4.2  POPULATION
     Population is one of the most important parameters used in designing a.
wastewater treatment facility.  Population forcasts are used  to project
wastewater flows  and loads  used  for design.  Approximately 35 percent of the
wastewater flow at Jackson Pike and 47 percent of  the wastewater  flow at
Southerly is estimated to be generated from domestic or residential sources.
As the planning area's  population  increases, wastewater  flows  are also
expected to  increase.
                                     4-2

-------
4.2.1  Existing Population
     In order to project future growth,  it  is necessary  to examine the present
population levels and past trends.  Table 4-1 presents a demographic profile
of the Colunbus area based on  1980  Census data.  It lists 1980 population
levels, median age and income, the  number of housing  units,  household size,
and the change in population and housing units between 1970  and  1980.  This
table indicates that the Columbus Metropolitan Statistical Area  (MSA) is a
high growth area.  The population increased by 25 percent, and the number of
housing units increased by 32 percent from  1970  to 1980.  The  area's average
family income  is higher  than  the  state's.  The bulk of the Columbus area
population is between the child bearing  years of 25 to 35.  Three-quarters of
the area's housing units are single-family  dwellings.

     Table 4-1 also lists the percent of the overall population  for each
county that is included  in the Facility  Planning Area (FPA).   Most of Franklin
County (99 percent)  and  a small pecentage of Delaware (3 percent), FairfieId
(1 percent),  and Licking Counties (3 percent) are included in  the FPA.   All
of the city of Columbus  is included in the  FPA.  Since the city of Columbus
and Franklin County comprise the bulk of the land and population in the FPA,
growth in these two municipalities  are indicative of  growth  levels in the FPA.

     In Franklin County, the population  reached  869,132  in 1980  and 898,345 in
1985.   This represents an increase of 6,000  persons  per  year.   In 1984,  there
were 6,551 building permits issed in Franklin County; 2,875 of which were for
apartments and townhouse units.  The remaining 3,676 were for single family
homes.  On the average,  4,000  dwelling units have been built each year since
1980.
                                     4-3

-------
                                            TABLE 4-1.   1980 DEMDGRAPHIC PROFILE FDR THE COLUMBUS AREA

Percent of
Population
in FPA
State of
Ohio 8
Colunfcus
MSA 75
"T City of
*" Cokrobus 100
FPA Counties
Delaware
County 3
Fairfield
County 1
Franklin
County 99
Licking
County 3
Union
County 0


Total
Persons

10,797,630

1,093,310

564,871


53,8W

93,678

869,132

120,981

29,536


Median
Ase

29.9

29.5

28.1


28.9

30.4

28.1

30.1

29.7

Persons/
House-
hold

2.76

2.82

2.49


2.90

2.92

2.61

2.80

2.87
Percent
Change in
Population
1970-1980

1.3

25.8

25.5


25.5

27.8

14.2

11.6

24.2
1979
Median
Famly
Income

$20,909

23,506

20,882


22,202

20,728

20,970

20,660

19,704


Housing
Units
-
4,108,105

426,426

236,708


18,764

33,530

347,024

44,502

10,619

Percent of
One-Unit
Structures

70.3

76.6

55.0


78.9

83.6

62.4

78.0

80.2

Percent
Owner
Occupied

68

72

48


76

77

57

74

76
Percent
Change
in Units
1970-1980

18.5

32.9

25.5


41.8

36.3

28.0

25.9

32.5


%
Vacar

6

5.6

8.2


6.1

5.2

7

5.2

4.6
The Columbus MSA includes:   Delaware, Fairfield, Licking, Franklin, Madison, Pickaray, and Union Counties.

-------
     Columbus is experiencing, along with  much of  the nation, a decline in
household size.   This trend along with the  growth in population has increased
the demand  for housing.  In  1980,  Franklin County had a household  size of 3.08
persons per household; by  1984 this had decreased to 2.56  persons per
household.  The major component of this decline in household size is the rise
in the number of households  headed by a single person.   In 1970,  17 percent  of
the households in Columbus were  included in this category; by 1985 that number
had increased to 27.9 percent (City  of  Columbus,  1985).

     In the past  25 years,  the population in  the city of Columbus has
increased by 112,406 persons.  The number of  households has  almost doubled in
the period betwen 1960 and 1985.   (The number of households  in 1960 was
142,378;  by 1985, this number had  grown  to 229,804) (City  of Columbus,  1985).
In smaller suburban  communities  (Table 4-2) such as Dublin,  Gahanna,
Westerville, and Worthington, the population  between 1960  and 1980 doubled and
in some cases more  than  tripled  in that 20-year period.   The growth that has
occurred in the Columbus area in the last 25  years generally placed
unanticipated demands on community services.   These services include the local
infrastructure;  that is  roads,  water  and  sewer system as well as  public
services such as  fire and police  protection,  health and community services,
and public education.

4.2.2  Population Projections
     Population projections for the Columbus  area are available from a number
of sources.   These include:

     •  Ohio Data Users Center (ODUC), a  division of the Ohio Department of
        Economic  Development
     *  Ohio Environmental Protection Agency (OEPA)
     •  Mid-Ohio Regional Planning Commission  (MORPC).
                                     4-5

-------
    TABLE 4-2.  POPULATION AND PER CAPITA INCOME BY POLITICAL SUBDIVISION
Columbus
Bexley
Dublin
Gahanna
Grand view Heights
Grove City
Grove port
Milliard
Lockbourne
Marble Cliff
Minerva Park
New Albany
New Rome
Obetz
Reynolds burg
Upper Arlington
Westerville
Whitehall
Worthington
Population
July 1984
566,114
13,588
5,437
20,222
7,945
17,442
3,613
8,647
419
566
1,691
441
68
3,284
22,390
36,067
24,878
22,754
18,721
Population
1980
564,871
13,405
3,855
18,001
7,420
16,793
3,286
8,008
373
630
1,618
409
63
3,095
20,661
35,648
23,414
21,299
15,016
% Change
1980-84
+ 0.2
+ 1.4
+29.1
+63.1
+ 6.6
+ 3.7
+ 9.1
+ 7.4
+11.0
+11.3
+ 4.3
+ 7.3
+ 7.4
+ 6.1
+ 8.4
+ 1.2
+ 6.3
+ 6.8
+24.7
Per Capita
Income 1983
8,800
15,096
18,392
10,444
11,689
9,661
8,438
8,549
7,093
17,815
13,987
10,442
9,095
8,174
10,811
18,711
10,875
9,677
14,622
SOURCE:  Ohio Data Users Center and Columbus Chamber of Commerce.

NOTE:  Shawnee Hills is located in the facility planning area; however, data
       necessary to complete this table were unavailable.
                                     4-6

-------
     However, each agency uses different parameters:  ODUC prepares its
projections only on the county level, OEPA prepares its projections by Sewer
Service Areas, and MORPC prepares its projections by traffic zones.  Although
OEPA and MORPC's projections are prepared for smaller areas than ODUC's,  they
must be certified by the state as agreeing with the most current ODUC
projections.   In 1985,  ODUC updated  its  projections based  on  1980  U.S. Census.
Since MORPC and OEPA agree  that the  1985 ODUC estimates are the best available
projections,  these were used as the  basis of projections used in this EIS.
Table 4-3 lists the ODUC projections for  the area.

       TABLE 4-3.  POPULATION PROJECTIONS FOR THE STATE OF OHIO AND THE
                    COUNTIES IN THE COLUMBUS SERVICE AREA

Ohio
Delaware
Fairfield
Franklin
Licking
1980
10,797,630
53,840
93,678
869,132
120,981
1990
10,681,863
61,709
98,655
924,592
127,390
2000
10,583,083
71,381
104,033
975,013
132,154
2010
10,398,338
81,164
107,577
1,026,008
136,765
Source:  Ohio Data Users Center, 1985.

     Although the population in the state of Ohio is expected to decline in
the future, the population of all of the counties included in the FPA is
expected to increase.  The population of Franklin County is expected to
increase at an average annual rate of six percent for the next 30 years.
These forecasts show the 2010 Franklin County population will exceed 1 million
persons.
                                     4-7

-------
     As mentioned earlier, most:  of Franklin County is included in Che Columbus
Facilities Planning Area (FPA).   The FPA represents  the  geographic area that
could be served by the Columbus  sewer  system.  The FPA  is defined by OEPA.
OEPA assigns each sewer district aa FPA in order to coordinate the planning
activities of various sever authorities.  The FPA includes the potential
service area.  The service area must be located within  the FPA boundary.  The
service area boundary, as shown  on Figure 4-1, represents the area presently
served as well as those areas most likely to be served during the 20-year
planning period or prior  to 2003.

     Population projections were prepared for use in this Supplemental EIS for
both of these areas.   These projections were based on the most recent ODUC
projections and were prepared for  the  20-year planning  period starting in
1988.   Appendix K details the methodology used to disaggregate the county
projections into the 2008 Service Area.  Table 4-4 lists these projections for
the 2008 design year.

               TABLE 4-4.  POPULATION PROJECTIONS FOR COLUMBUS

              Sub-Area               1988         2000         2008
       Planning Area               925,900      982,600      1,018,000
       Total Service Area          888,000      94l,&00        986,000
       Jackson Pike Service Area   499,000      529,200        544,600
       Southerly Service Area      389,000      412,400        441,400
       RFPU Total Service Area     870,427      951,861         995,159
       Forecasts (11/86)

     The above table indicates,  the planning area population will increase by
92,100 individuals during the 1988  to 2008 planning period,  reaching 1,018,000
persons by 2008.   This table also shows the 2008 Service Area population
increasing by 98,000  persons during the same period.   The Service Area
population is shown  as  reaching  986,000 persons by 2008.
                                     4-8

-------
SERVICE AREA BOUNDARY

PLANNING  AREA  BOUNDARY
                 4-9
FIGURE 4-1
PLANNING AND SERVICE
AREA BOUNDARIES

-------
     Preparing population projections for small areas requires a good estimate
of existing land use, the amount of vacant developable land,  and a number of
other economic trends.  Different forecasting techniques can result in slight
variations in small  area population projections.  The projections prepared for
the RFPU vary slightly from those prepared for this Supplemental BIS.  the
RFPU assumed a slower growth rate between 1980 and 1988 and a higher growth
rate between 2000 and 2008 than assumed by ODUC.  This resulted in the RFPU
presenting a lower initial population and a higher population in 2008 than
those shown in Table 4-4.  A detailed  memorandum explaining the methods used
in the RFPU is included as Appendix K.

4.3  LAND USE PATTERN
     Land use in Franklin County is controlled by  local zoning  ordinances.
There are 234  incorporated  areas and  17  towns in Franklin County that guide
growth through zoning.  Some of these incorporated areas also have a master
plan; most do not.   In Franklin County,  eleven of  the  towns have delegated
their zoning powers  to MORPC—- the regional planning agency.

     The largest incorporated area in Franklin County is the city of Columbus.
They are in the process of developing a comprehensive plan to guide growth.
Until a plan is adopted,  the  city will continue to use over 20 different
documents to guide and control growth.  Some of these documents are updated on
a regular basis,  these include  the Growth  and Development Report and the
Capital Improvement  Program.  Others are updated as the need arises, such as
the recently completed plan for the Columbus International Airport.  Due to
its physical size,  large population,  and large employment base, the city's
policies greatly influence  development in the smaller incorporated areas.

     Columbus is the state capital and houses several corporate headquarters
and a major state university.   It has  never been known as an industrial town.
The city has a densely developed inner core with mixed office space and other
                                     4-10

-------
services such as hotels and retail stores.   Low density research and
development and distribution centers have moved from the inner core to the

1-270 corridor.  This redevelopment has  not affected the city's tax base since
many of these newer developments have been  annexed to the city in order to

receive its services.


     The city of Columbus provides sewer and water services to city residents
and by contract to  suburban municipalities.  Twenty communities have contracts

with Columbus.  Table 4-5 lists the municipalities that have sewer service
contracts with the city.  In  the past,  the  city has used water and  sewer

service as an incentive to developers to annex to Columbus.   Figure 4-2
identifies suburban communities with water service contracts.   This service

includes 89 percent of Franklin County.


                TABLE 4-5.  MUNICIPALITIES  AND OTHER ENTITIES
               THAT HAVE SEWER SERVICE CONTRACTS  WITH COLUMBUS
             Bexley                       Valleyview
             Brice                        WesCerville
             Dublin                       Whitehall
             Gahanna                      Worthington
             Grandview Heights            Rickenbacker  Air  Base
             Grove City                   Briarbank  Subdivision
             Groveport                    Brookside  Estates
             Billiard                     Clinton
             Marble Cliff                 Franklin
             Minerva Park                 Hamilton Meadows
             Obetz                        Mifflin
             Reynoldsburg                 New Albany
             Riverlea                     Truro
             Upper Arlington              Worthington Hills
             Urbancrest                   Timberbrook Subdivision

Source:  City of Columbus,  1985,  Division of Sewage  & Drainage
         Operating Report.
                                     4-11

-------
                                                           ~l
L
        i*y of C
       Add i o«ol Af*c
    SOURCE- 1979  EIS
                             4-12
FIGURE  4-2
WATER SERVICE AREAS

-------
     In the Columbus area, growth has been influenced by annexation of various
incorporated areas (school district  boundaries),  highway construction,  and the
availability of public water and sewer.  Suburban growth, particularly in the
northern and western sections of Franklin County is directly related to
completion of the interstate highway system  (1-270 and 1-170).  The  areas most
affected are Dublin, Worthington, Westerville and to a lesser extent Gahanna.
Most of the unincorporated areas are either vacant land or farmland.  Some of
the smaller incorporated areas  mix some industrial  and commercial  uses  with
predominantly residential uses.

     This development has been dominated by the construction of single-family
homes.  Table 4-6 lists subdivisions filed in  the Columbus  area between 1980
and 1932.   This table confirms  that  aside from Grove City most of the area's
residental development is occuring in the northern sectors.  Figure  4-3
presents these high growth areas in a generalized manner.  This figure depicts
growth according to traffic zones.   There are over 800  such zones  in the
service area.   Approximately 30 of  these zones are considered to be  high
growth areas.

     Because there are numerous vacant parcels of land  adjacent to the city of
Columbus and within the service area, it is assumed all  of  the projected
growth can be located within the service area.  These parcels of land were not
developed during the first wave of suburban expansion.  Development  of these
parcels will be part of an infill process and will require resubdivision of
less-attractive parcels.
                                     4-13

-------
TABLE 4-6.  RESIDENTIAL PLATS BY MUNICIPALITY OR TOWNSHIP,
                1980-1932, FRANKLIN COUNTY

                                                New     Total
    Year    Plats  Reaubdivisions   Acreage   Acreage   Lots
Columbus



Dublin



Gahanna



Grandview
Heights


Grove City



Hilliard



Upper*
Arlington


Westerville



1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
1980
1981
1982
TOTAL
31
23
15
69
3
1
2
6
1
4
1
6
1
0
0
1
3
1
1
5
1
0
0
1
1
2
2
5
6
1
3
10
7
6
7
20
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
I
0
0
1
0
1
1
2
0
0
2
2
368.297
275.110
93.193
736.600
41.389
7.447
23.267
72.103
15.980
59.613
7.896
83.489
4.170
0.000
0.000
4.170
48.086
34.182
0.596
82.864
2.074
0.000
0.000
2.074
10.847
8.904
4.006
23.757
77.801
2.115
37.742
117.658
316.359
260.912
70.879
648 . 150
41.389
7.447
23.267
72.103
15.980
59.613
7.896
83.489
4.170
0.000
0.000
4.170
48 .086
34.182
0.596
82.864
0.000
0.000
0.000
0.000
10.847
7.371
2.149
20.367
77.801
2.115
36.119
116.035
1659
965
487
3111
83
1
30
114
45
181
30
256
9
0
0
9
120
92
3
215
10
0
0
10
25
28
9
62
204
11
101
316
New ,
Lots:
                                                                1567
                                                                 901
                                                                 400
                                                                2868

                                                                  83
                                                                   1
                                                                  30
                                                                 114

                                                                  45
                                                                 181
                                                                  30
                                                                 256

                                                                   9
                                                                   0
                                                                   0
                                                                   9

                                                                 120
                                                                  92
                                                                   3
                                                                 215

                                                                   3
                                                                   0
                                                                   0
                                                                   3

                                                                  25
                                                                  27
                                                                   9
                                                                  61

                                                                 204
                                                                  11
                                                                  94
                                                                 309
                           4-14

-------
          TABLE 4-6.  RESIDENTIAL PLATS BY MUNICIPALITY OR TOWNSHIP,
                           1980-1982, FRANKLIN COUNTY (CONT.)
              Year
        Plata  Reaubdi.visi.on3   Acreage
                                  New     Total   New
                                Acreage   Lots    Lots*
Worthington
Bexley
1980
1981
1982
TOTAL

1980
1981
1982
TOTAL
1
2
2
5

0
1
0
1
0
0
1
1

0
1
0
1
 3.250
47.527
 6.601
57.378

 0.000
 1.319
 0.000
 1.319
 3.250
47.527
 5.588
56.365

 0.000
 0.000
 0.000
 0.000
  9
101
 19
129

  0
  3
  0
  3
  9
101
 18
128

  0
  0
  0
  0
Reynoldburg
Townships
Franklin
County
Total
1980
1981
1982
TOTAL

1980
1981
1982
TOTAL
0
2
1
3

3
2
2
7
TOTAL   119
0
0
0
0

0
0
2
2
          29
0.000
13.216
26.252
39.468
0.000
13.216
26.252
39.468
0
88
72
160
68.239
14.914
 6.263
89.416
68.239
14.914
 0.000
83.153
155
 42
 10
207
          1310.296  1206.164   4592
  0
 88
 72
160

155
 42
  3
200
                           4323
 The number of  resubdivisions  is  included  in  the  total  plat count.
 Resubdivision occurs when a large number of undeveloped lots are consolidated
 under one owner and broken into new lots with different acreages and
 locations.
2
 New acreage refer to the total platted acreage minus any resubdivided land.
o
 New lots refers to the total platted lots  minus those lots created by a
 resubdivision where previous  lots existed.  For example, if a resubdivision
 plat of 4 acreas contained 20 lots and the previous plat for the same 4 acres
 contained 16 lots, then the resubdivision resulted in no new acreage and 4 new
 lots.

 Interviews with local officials  indicate  that  less  than 10X of the land in
 the municipalities is available for development.

Source:  City of Columbus, 1983.
                                     4-15

-------
TRAFFIC ZONES  WITH
PROJECTED INCREASES
OF 1,000 PERSONS OR
500 HOMES FROM 1980
TO 2000

SERVICE AREA BOUNDARY
                 4-16
FIGURE 4-3
HIGH GROWTH AREAS

-------
4.4  WASTEWATER FLOWS AND LOADS
     The development of average daily and peak daily flow rates and daily
loadings of total suspended solids (TSS) and biochemical oxygen demand (BOD)
are necessary to evaluate facility planning alternatives.  The following
sections present the existing flows and loads developed for the Columbus WWTPs
from an independent analysis of the 1985 and 1986 plant data, as well as
projected flows and loads for the 2008 design year.   The detailed documenta-
tion for this portion of the report is contained in Appendix A entitled
Briefing Paper No. 1 - Wastewater Flows and Loads.

     An analysis of existing conditions established the current average day
flows.  The average day flow is disaggregated into domestic, infiltration,
industrial, and commercial flows.  Diurnal flows are evaluated, and a diurnal
peaking factor is established.  A process peaking factor is established to
project peak flow rates which will be used for hydraulic sizing of WWTP unit
processes.  Wet weather flows are discussed briefly with a more detailed
discussion included in Section 4.5 - Combined Sewer Overflow.  Due to the lack
of comprehensive combined sewer overflow (CSO) data, projected design flows
were developed independent of CSO.

     The analysis also includes a review of existing influent BOD and TSS
loads.   BOD and TSS loads are used to determine sizings for WWTP unit
processes and to aid in the selection of the treatment processes.

     Wastewater flows and loads are projected for the design year (2008) using
existing per capita flows and loads and 2008 population projections.

4.4.1  Existing Wastewater Flows
     Jackson Pike and Southerly Monthly Operating Reports (MORs) and
precipitation data for the 1985 and 1986 calendar years were used to establish
existing wastewater flows.  The MORs are submitted to Ohio EPA in accordance
with the NPDES permits.
                                     4-17

-------
     The Southerly MORs include data on amounts of raw sewage bypassed and
settled sewage bypassed as well as treated flow.  The Southerly plant has a
method of treatment termed Blending of Flows.  When incoming flows increase to
the point where the biological portion of the plant begins to show signs of
potential washout, the flow to the biological part of the plant is fixed.  The
increase in flow above this fixed flow, but less than the capacity of the
primary tanks, is bypassed around the biological portion and blended with the
final effluent, thus, receiving only primary treatment and chlorination.
These flows are reported on the MORs as settled sewage bypassed.  If the
primary treatment facilities are operating at capacity, then all excess flows
are bypassed directly to the Scioto River through a 108-inch diameter pipe
originating in the screen building.  These flows are reported on the MORs as
raw sewage bypassed.  After August of 1986, no blending of flows was recorded
on the MORs for the Southerly WWTP, however, bypassing was still reported.

     The Jackson Pike MORs provide flow monitoring data for the plant.
Jackson Pike does not blend as Southerly does, nor do they bypass raw sewage.
The major diversion point for Jackson Pike flows occurs at the Whit tier Street
Storm Standby Tanks before the flows reach the plant.  The tanks are capable
of acting as a holding system for the excess flows until the flow in the
interceptor subsides and they can be bled back into the system and carried to
the Jackson Pike plant.  If the flows exceed the capacity of the tanks, they
overflow to the Scioto River.  Flows can also be directly bypassed along side
the tanks, through an emergency bypass, to the Scioto River.

    Flow monitoring did not take place at the Whittier Street Storm Standby
Tanks until November of 1986.  However, hours of operation of the storm tanks
were recorded during 1985 and 1986 on the Monthly Report of Operations.  The
fact that hours of operation were reported does not necessarily mean there was
bypassing or overflowing occurring at the tanks.  It only means that the gates
were open and flows were being diverted into the tanks.  In November of 1986,
the city began monitoring the overflow but not the bypass.  Therefore, the
data is still incomplete with respect to determining the total volume of flow
entering the Scioto River at the Whittier Street facility.
                                     4-18

-------
    Dry weather flows were determined through an analysis of 1985 and 1986
flow data.  However, only 1986 flow data was used to determine wet weather
flows.  An analysis of 1985 MORs showed that data on raw and settled sewage
bypasses at Southerly were not complete.  Up until August of 1985, only a
bypass flow rate (MGD) was reported with no duration specified.  These
bypasses did not always occur 24 hours a day, therefore these rates could not
be converted to the volume bypassed during that day.  In August of 1985,
monitoring of the duration of the bypasses began which provided a more
accurate determination of the volume of the bypasses.  Therefore, the 1986
calendar year data were used to estimate wet weather flows.

     Wet weather total system flow cannot be determined solely based on the
volume of flow arriving at the Jackson Pike and Southerly WWTPs.  There are
numerous points of combined sewer overflow throughout the Columbus Sewer
                                *
System.  The Jackson Pike service area has several regulator chambers and
overflow structures in addition to the Whittier Street Storm Standby Tanks
discussed previously.  The Southerly service area includes an overflow
structure at Roads End and the Alum Creek Storm Standby Tank.  There is no
comprehensive flow monitoring data available for the regulators, overflows,
and storm tanks.  The city began monitoring some of the points of combined
sewer overflow in November of 1986; but according to the MORs, the flow
monitoring equipment malfunctioned frequently providing no data.  Thus, the
only flow data included in the wet weather analysis, other than plant flow
data, was that which was reported for the Whittier Street overflow during
November and December.

     The following paragraphs present the existing average flow, diurnal flow,
peak process flow, and wet weather flow as determined from the analysis of
available data.
                                     4-19

-------
4.4.1.1  Existing Average Plows
     USEPA guidelines require WWTP design flows to be determined based on
existing dry weather flows and non-excessive I/I.  Therefore, the existing
average flow was determined through an analysis of dry weather/no bypass
flows.  The 1985 and 1986 flow record contained 214 dry weather/no bypass
days.  Analysis of these days showed a combined maximum monthly average of
145 MGD for the Jackson Pike and Southerly WWTPs.  This flow was established
as the existing average flow.  Distributed between the two plants, it is
84 MGD for Jackson Pike and 61 MGD for Southerly.

Infiltration
     A current infiltration/inflow report was not available for the Columbus
sewer system; therefore, wastewater flow, water use, and precipitation data
were utilized to estimate infiltration.

     The maximum monthly average dry weather/no bypass flow of 145 MGD
occurred in May of 1985.  The data base consists of two four-day periods of
dry weather/no bypass conditions.  This month, which had 3.92 inches of
precipitation, had the second highest monthly rainfall recorded during 1985.
Therefore, May would represent a high groundwater condition resulting in
increased infiltration. November had the highest precipitation with 10.67
inches, but there were no dry weather/no bypass days during that month.
Therefore, it was not possible to determine infiltration using November data.

     Based on the two years of records evaluated, September of 1985 had the
lowest combined (i.e., total for both WWTPs) monthly average dry weather/no
bypass flow of 124 MGD; and it had 24 dry weather/no bypass days which
occurred in one two-day period and one 22-day period.  Due to the extended dry
weather period, September was used to represent a low groundwater condition.
Water usage vs. wastewater flow data presented in Table 4-7 reinforce May and
September as representing high and low groundwater conditions.  The month of
May has an average water pumpage figure of 120 MGD which is very close to the
annual average of 121 MGD.  However, it has an average dry weather wastewater
                                     4-20

-------
flow figure of 145 MGD which is the highest value reported for 1985.  The
wastewater flow is 20 percent higher than the water pumped suggesting
increased infiltration resulting from a high groundwater condtion.  September,
on the other hand, has the highest water pumpage figure of 142 MGD and the
lowest wastewater flow of 124 MGD.  In this situation the wastewater flow is
15 percent lower than the water pumpage.  This implies that a lot of water is
being used for lawn sprinkling due to the dry weather.

             TABLE 4-7.  1985 WATER PUMPAGE VS. WASTEWATER FLOW
          Month
          January
          February
          March
          April
          May
          June
          July
          August
          September
          October
          November
          December
Average Water
Pumped (MGD)
   111.23
   108.32
   109.65
   115.60
   120.33
   128.53
   127.15
   130.66
   141.74
   124.88
   117.23
   116.46
Average Dry Weather/
No Bypass Flow (MGD)
      132.30
      139.94
      142.55
      140.25
      144.75
      134.03
      138.87
      127.03
      124.02
      124.88
      No Data
      143.16
     The difference of 21 MGD between the high groundwater month (May) and the
low groundwater month (September) represents that portion of the total
infiltration which is attributable to a high groundwater condition.
                                     4-21

-------
     However, this is only a portion of the total amount of infiltration
occurring since there is also some infiltration occurring during low ground-
water conditions.  Therefore, the amount of infiltration occurring during low
groundwater conditions must be determined and added to the 21 MGD in order to
establish a total infiltration rate.

     A common method of estimating total infiltration involves using monthly
water records to establish the domestic, commercial, and industrial portion of
the wastewater flow.  The difference between the water supplied and wastewater
collected under dry weather conditions is then taken to be infiltration.

     Since September 1985 has been established as a low groundwater month,
water usage rates from this month will be used.  As reported in Table 4-8, the
September 1985 water pumpage rate is 141.74 MGD.  Literature states that
approximately 60 to 80 percent of water pumped becomes wastewater.  The 20 to
40 percent which is lost includes water consumed by commercial and manufactur-
ing establishments and water used for street cleaning, lawn sprinkling, and
extinguishing fires.  It also includes water used by residences that are not
connected to the sewer system as well as some leakage from water mains and
service pipes.  If it is assumed that 70 percent of the water becomes
wastewater, then the return flow for September would be 99.22 MGD.  Referring
to Table 4-8, the wastewater flow for September is 124.02 MGD.  The difference
between the actual wastewater flow (124.02) and the expected wastewater flow
(99.22) is 24.80 MGD.  This value is assumed to represent the amount of
infiltration occurring during a low groundwater condition.  Thus, the total
infiltration occurring during high groundwater conditions is obtained by
adding 20.73 MGD to 24.80 MGD.  This total infiltration figure of 45.53 MGD,
converts to 52 gpcd.

     It must be remembered that 52 gpcd is only a rough estimate of
infiltration.  It is not known if all of the water customers are sewer
customers or if all the sewer customers are water customers.  Some sewer
customers may have their own private wells.  In addition, the consumptive use
of the brewery and the other industries is unknown.
                                     4-22

-------
     It is, however, considered to be a non-excessive infiltration rate when
compared to infiltration rates in the USCPA document entitled Facility
Planning - 1981 Construction Grants Programs.  This document states that 2000
to 3000 gpd/inch-diameter mile is considered a non-excessive infiltration rate
for sewer systems with lengths greater than 100,000 feet.  The Columbus Sewer
System has a total length of 9,975,000 feet or an estimated 32,930 inch-
diameter miles.  Multiplying the inch-diameter miles by 2000 gpd/inch-diameter
mile results in 66 MGD or 76 gpcd.  Therefore, 52 gpcd of infiltration would
be considered non-excessive.

     The Revised Facility Plan Update uses a peak infiltration rate of
72 gpcd.  Divided between the two plants, it is 82 gpcd for Jackson Pike and
58 gpcd for Southerly.  Assuming more detailed information was available to
establish this number for the facility plan and considering 72 gpcd is also a
non-excessive infiltration rate according to the USEPA document, it will be
used in this briefing paper as the existing infiltration rate.  It converts to
22 MGD for Southerly and 40 MGD for Jackson Pike, totaling 62 MGD for the
entire Columbus Sewer System.

Industrial and Commercial Flows
     Current information on industrial and commercial wastewater flows was not
available.  Therefore, estimates were made by updating those values presented
in the Columbus Industrial Pretreatment Program Report as prepared by Burgess
and Niple.  The industrial flows presented in the Columbus Industrial
Pretreatment Program Report were updated proportional to the increase in
population from 1980 to 1985 since they were based on 1980 water consumption
records.  The 1985 estimates of industrial and commercial flows are presented
in Table 4-8.
                                     4-23

-------
                 TABLE 4-8,   INDUSTRIAL AND COMMERCIAL FLOW ESTIMATES
                             1980         1980                    1985        1985
                 1980      Industrial   Commercial     1985     Industrial   Commercial
              Population   Flow (MGD)   Flow (MGD)  Population  Flow (MGD)   Flow (MGD)
Jackson Pike
Southerly
TOTAL
472,503
368,228
840,731
8.7
6.7
15.4
4.3
3.1
7.4
489,000
381,000
870,000
9.0
6.9
15.9
4.5
3.2
7.7
Domestic Flows
     Domestic flows were estimated  simply by subtracting infiltration,
industrial, and commercial  flows  from the maximum dry weather/no bypass flow
of 145 MGD.  The Jackson Pike  domestic flow is 30.4 MGD and Southerly is 28.8
MGD.  Table 4-9 presents the breakdown of the existing flow for each plant
and the two plants combined.

                       TABLE 4-9.   1985 ESTIMATED FLOWS

                            Jackson Pike      Southerly        Total
Design Average Flow (MGD)         84              61             145
     •  Infiltration            40.1            22.1            62.2
     •  Industrial              9.0             6.9            15.9
     •  Commercial              4.5             3.2             7.7
     •  Domestic                30.4            28.8            59.2

4.4.1.2  Diurnal Flow
     Just as demand for water  fluctuates on an hourly basis, so do wastewater
flow rates.  Fluctuations observed  in wastewater flow rates tend to follow a
diurnal pattern.  (See Figure  4-4.)  Minimum flow usually occurs in the early
morning hours when water use is low.   The flow rates start to increase at
approximately 6 a.m. when people  are  going to work, and they reach a peak
value around 12 noon.  The  flow rate  usually drops off in the early afternoon,
                                      4-24

-------
 o
 _i
 u.
                TOTAL  FLOW
NJ

Ul
                                                               MAXIMUM
                                                              AVERAGE


                                                              MINIMUM
                   DOMESTIC
                     FLOW
                                              INFILTRATION
     NIGHT-TIME
  DOMESTIC FLOW


INDUSTRIAL
  6PM
  SOuncr  r«lsttft«i Se»er revaluation and Rehnht H tntlon


       Published by the Anerlcao Society of Civil Cntjlnccrj (A5CC) and the JTntcr I'ollutlon Control rcderalloa (»I»CO, 19BJ.
                                                                 FIGURE 4-4
                                                                 DIURNAL  FLOW VARIATIONS

-------
and a second peak occurs in the early evening hours between 6 p.m. and 9 p.m.
In general, where extraneous flows are excluded from the sewer system, the
wastewater flow-rate curves will closely follow water-use curves.  However,
the wastewater curves will be displaced by a time period corresponding to the
travel time in the sewers.

     Diurnal curves are also affected by the size of the community.  Large
communities with more industrial and commercial flows tend to have flatter
curves due to industries that operate on a 24-hour schedule, stores and
restaurants that are open 24 hours a day, and due to the expansiveness of the
collection systems.  These 24-hour operating schedules also result in more
people working second and third shift, thus altering normal flow patterns.
Longer travel times in the collection system dampen peak flows observed at the
WWTP.

     An existing average flow of 145 MGD was determined in Section 4.4.1.
This flow was determined from an analysis of dry weather flows and it is
generally used in the design of wastewater facilities to determine quantities
of chemicals needed, O&M costs, labor, and energy requirements.  However, the
peak hourly flow must be used for hydraulic sizing of pumps.  Therefore, a
diurnal peaking factor must be determined.

     Figure 4-5 presents wastewater flow rate curves for the Jackson Pike and
Southerly plants compiled from September 1985 dry weather/no bypass days.  The
diurnal peaking factor was determined for the Jackson Pike and Southerly WWTPs
through an analysis of hourly wastewater flows for February and September
1985.  These two months represent minimum and maximum water consumption,
respectively for 1985.  The 1985 months were chosen since the existing average
flow occurred in Kay of 1985.  Diurnal peaking factors were calculated by
dividing the maximum hourly flow by the average hourly flow for each dry
weather/no bypass day during February and September.

     The maximum diurnal peaking factor seen at Jackson Pike during this
period was 1.40, and at Southerly it was 1.51.  Jackson Pike's value of 1.40
                                     4-26

-------
   O
   O
   5
   S
   O
.P.  _i
i   "-
tsJ
                            JACKSON PIKr
SOUTHrpIV
-x-
TOTAL AVC
                                                                   FIGURE 4-5
                                                                   DIURNAL  FLOW VARIATIONS
                                                                   FOR DRY WEATHER

-------
occurred several times and was selected as the diurnal peaking factor for
Jackson Pike.  Southerly's maximum value of 1.51, however, was considered to
be excessive.  It occurred, only once, on September 21 when the average hourly
flow was at a low of 45 MGD.  The next peaking factor in the series was 1.37
which is more representative of the maximum diurnal peaking factor seen at the
Southerly plant.  Thus, 1.4 was chosen as a representative diurnal peaking
factor for both plants.

4.4.1.3  Peak Process Flow
     A peak process flow must be developed for use in sizing various
processes.  This flow establishes the maximum process capability of the wet
stream treatment facilities.  Flows greater than the peak process flow will
cause the treatment facilities to operate beyond their intended design
criteria.  Sustained operation above the peak process flow may result in a
violation of permit limits.

     The peak process flow is most reliably established through an analysis of
existing flow.  This approach was not possible in the Columbus system due to
the nature of the flow record.  As discussed in Section 2, the flow records
for the two Columbus plants provided limited information regarding the amount
of sewage bypassed.  As a result, a reliable record of the total flow arriving
is not available.  Furthermore, peak wastewater flows normally include some
combined sewage.  A combined sewage overflow study, which will define a CSO
control strategy, is currently being prepared by the city.  The impact of the
CSO recommendation on the wastewater treatment facilities will be evaluated at
the conclusion of that study.

     In the 1979 EIS, the following empirical formula was utilized to develop
a peak process flow, due to the absence of a comprehensive flow record:

     Peak Process Flow =1.95 (Average Daily Flow) °*9*
                                     4-28

-------
     Lacking flow information which would substantiate a peak process flow,
the 1979 EIS formula provides a reasonable method for developing a peak
process flow.  Based on the 2008 average design flow of 154 MGD, the formula
yields a peak process flow of 233 MGD.  This corresponds to a process peaking
factor of 1.5.

     The 1.5 process peaking factor was evaluated relative to the 1986 flow
data to assess the extent of its range.  The 1986 flow record includes flows
treated at Jackson Pike and Southerly and also the flows which are bypassed at
Southerly.  The flow record does not include flows which were bypassed at
Whit tier Street or any other combined sewer overflows.  The 1986 average flow
of the two plants was 145 MGD.  Applying the 1.5 process peaking factor to
this average flow yields a peak process flow of 218 MGD.  Comparing this flow
with the 1986 record indicated that the daily flow rate of 218 MGD was
exceeded only nine days during the year or approximately 2.5 percent of the
time.  In light of these few exceedances, the 1.5 process peaking factor
established by 1979 EIS provides a reasonable approach to establish a peak
process flow.

4.4.1.4  Wet Weather Flow
     The maximum monitored wet weather flow as determined from 1986 records
is 309.52 MGD.  Note that this maximum wet weather flow only includes flow
that arrives at the treatment plants.  Any flow being bypassed at the various
points of combined sewer overflow is not included.  This flow occurred on
March 14.  It includes 95.57 MGD for the Jackson Pike WWTP and 213.95 MGD for
the Southerly WWTP.  The Southerly flow can be broken down into 78.05 MGD
receiving complete treatment, 30.30 MGD receiving primary treatment and
chlorination, and 105.60 being bypassed directly to the Scioto River.

4.4.2  Existing Wastewater Loads
     Monthly average influent total suspended solids (TSS) and biochemical
oxygen demand (BOD) loads were determined for all weather conditions.
                                     4-29

-------
     The sampling point at Jackson Pike for TSS and BOD concentrations is
located at  the grit chambers on the O.S.I.S.  The O.S.I.S. carries approx-
imately  65  to 70 percent of the flow to Jackson Pike.   The remaining flow
comes through the Big Run Interceptor.   Therefore,  the  samples are  not
representative of the flow from the Big Run Interceptor.    Plant staff
believe  that the flow  arriving  through the  O.S.I.S. contains the  majority of
the industrial flow  in the Jackson Pike service area.   If this is accurate,
then waste loadings established  by evaluating  this data may  overestimate the
actual loadings coming into the Jackson Pike plant. The  Southerly  flow is
sampled between the screens and  the grit chambers.  The samples are
representative of 100 percent of the flow entering the Southerly plant.

     Only 1985 data were used  to determine existing BOD loads  because there
were insufficient data available for 1986.  At Jackson  Pike, BOD  values were
only recorded for 304 days in 1986.   There were 341 days  of  data  for Jackson
Pike in 1985.  Southerly reported BOD values on 362 days  in  1986  and 364 days
in 1985.

     The 1985 annual average BOD  load  for Jackson Pike is 100,702 Ibs/day.
The maximum monthly average load is 118,466  Ibs/day, and  it  occurred in
January.   The ratio of  maximum monthly average to the  annual average results
in a peaking factor of 1.2.

     The 1985 annual average BOD load  for Southerly is  87,258  Ibs/day.   The
maximum  monthly  average  load, which  occurred  in October,  is 105,446 Ibs/day.
The peaking factor, as  determined by dividing  the maximum month average by the
annual average,  is  1.2.

     The 1985 and 1986  data were used  to establish TSS  loads for Jackson Pike
and Southerly.  Jackson Pike had 365 and 363 days  of TSS  data  for 1985 and
1986,  respectively.   There were  364 days of  TSS data reported  for Southerly
for both years.
                                     4-30

-------
     The average TSS load was obtained by computing the average of the annual
averages for 1985 and 1986.  The Southerly 1985 and 1986 average is 97,289
Ibs/day; and Jackson Pike is 126,006 Ibs/day.  Peaking factors were
established for each year in the same manner as was used for BOD loads.  The
peaking factors for Jackson Pike are 1.2 and 1.1 for 1985 and 1986,
respectively.  The higher value of 1.2 was chosen as the Jackson Pike TSS
peaking factor.  The Southerly TSS peaking factors are 1.1 for both 1985 and
1986.  Table 4-10 summarizes the 1985 and 1986 average and peak BOD and TSS
loads.

                 TABLE 4-10.  1985 AND 1986 BOD AND TSS LOADS
BOD LOADS
     *  Average (Ib/day)
     *  Peak (Ib/day)
     *  Peaking Factor
TSS LOADS
     •  Average (Ib/day)
     •  Peak (Ib/day)
     •  Peaking Factor
POPULATION
Jackson Pike
100,702
118,466
1.2
126,006
151,207
1.2
489,000
Southerly
87,258
105,446
1.2
97,289
107,018
1,1
381,000
Total
187,960
223,912
1.1
223,295
251,925
1.1
870,000
     A summary of the 1985 population figures and historic wastewater flows
and loads is presented in Table 4-11.  These quantities were used as a basis
for projecting flows and loads to the design year.
                                     4-31

-------
84
40.1
9.0
4.5
30.4
118,500
151,200
489,000
61
22.1
6.9
3.2
28.8
105,400
107,000
381,000
145
62.2
15.9
7.7
59.2
223,900
258,200
870,000
                       TABLE 4-11.  1985 FLOWS AND LOADS

                                Jackson Pike      Southerly      TOTAL
     Total Flow
     Ave. (MGD)
             •  Infiltration
             •  Industrial
             •  Cotmercial
             •  Domestic
     BOD Load (Ib/day)
     TSS Load (Ib/day)
     Population

4.4.3  Projected Flows and Loads
     Table 4-12 presents the flows of Table 4-11 in per capita/connection
form.  These data support the figures presented in Table 4-11 since they
represent reasonable values in agreement with thfe literature.

     Holding infiltration and industrial flows constant and using the existing
per capita commercial and domestic flows (Table 4-12) and the population
projections for 1988 and 2008, wastewater flows were projected for 1988 and
2008.

     There was insufficient information available to disaggregate the
industrial loads from the total loads.  Therefore, the existing total per
capita BOD and TSS loads from Table 4-12 were multiplied by the population
projections and the respective peaking factors to obtain the 1988 and 2008
projected loads.  In doing so, growth of industrial loads is proportional to
residential growth.
                                     4-32

-------
           TABLE 4-12.  1985 PER CAPITA/CONNECTION FLOWS AND LOADS
Jackson Pike Southerly
Per Capita
Domestic Wastewater Flow (gpcd) 62.2 75.6
Per Capita
Commercial Wastewater Flow (gpcd) 9.2 8.4
Per Capita
Industrial Wastewater Flow (gpcd) 18.4 18.1
Per Capita
Industrial, Commercial, and
Domestic Wastewater Flow (gpcd) 89.8 102.1
Per Capita
Infiltration (gpcd) 82 58
Per Connection
Commercial Wastewater Flows
(gal/connection day) ND ND
Per Connection
Industrial Wastewater Flows
(gal/connection day) ND ND
1985 Per Capita
Water Pumped
Industrial, Commercial, and
Domestic (gpcd) ND ND
1985 (Industrial, Commercial, and
Domestic) Water Pumped to Wastewater
Discharge Factor ND ND
Per Capita
Average BOD Loads (Ib/capita day) 0.206 0.229
Per Capita
Average TSS Loads (Ib/capita day) 0.258 0.255
TOTAL
68.1
8.9
18.2
95.2
72
816.7
62,109
139.1
.976
0.216
0.257
ND = No Data
*
  SOURCE:  City of Columbus, Division of Sewerage and Drainage,  December 1986.
                                     4-33

-------
     Table 4-13 presents the 1988 projected population,  flows, and loads;  and
Table 4-14 presents the projected population and average  flows and loads  for
the 2008 design year.

4.4.4  Comparison of SEIS and Facility Plan Flows and Loads
     This section compares the facility plan flows and loads with  the  flows
and loads developed in  the  preceding  sections of  this SEIS (Table 4-15).   The
facility plan flows and loads have been brought  back to  2008  for purposes  of
comparison, and the loads from  Whittier Street  have been eliminated.

     The SEIS average  flows are  approximately 10 percent  lower than the
facility plan flows, and the SEIS peak process flows are  approximately
20 percent lower than the facility plan  flows.

     There is a difference in the average flows  because  the flow projections
in the SEIS were developed by holding the infiltration and industrial  portions
of the flow constant and increasing only the commercial and domestic flows
proportional to the population increase;  whereas the flow projections  in  the
facility plan were developed by increasing all the flow,  including
infiltration and industrial, proportional to the population increase.

     Projected increases in infiltration do not  appear justified if the
population increase is located within the existing service area.  The  facility
plan does not document why  an increase  in infiltration should be included.
Projected industrial increases should  be based on  documented industrial growth
by existing industries and/or policy decisions by the municipality to  plan for
future undocumented growth.   Furthermore, such industrial growth should be an
identifiable part of the total design flows since capital cost recovery for
the added capacity must be addressed.
                                     4-34

-------
TABLE 4-13.  1988 PROJECTIONS
   Jackson Pike
Southerly
TOTAL
Total Flow
Ave. (MGD)
o Infiltration
o Industrial
o Commercial
o Domestic
BOD Load (Ibs/day)
TSS Load ( Ibs/day)
Population
84.8
40.1
9.0
4.6
31.1
123,400
154,500
499,000
TABLE 4-14. 2008
Total Flow
Ave. (MGD)
o Infiltration
o Industrial
o Commercial
o Domestic
BOD Load (Ibs/day)
TSS load (Ibs/day)
Population
Jackson Pike
87.9
40.1
9.0
5.0
33.8
134,600
168,600
544,600
61.7
22.1
6.9
3.3
29.4
106,900
109,100
389,000
PROJECTIONS
Southerly
66.0
22.1
6.9
3.7
33.3
121,300
123,800
441,400
146.5
62.2
15.9
7.9
60.5
230,300
263,600
888,000

TOTAL
153.9
62.2
15.9
8.7
67.1
255,900
292,400
986,000
        4-35

-------
              TABLE 4-15.  COMPARISON OF DESIGN FLOWS AND LOADS
Design Average Flow (MGD)

     o  Jackson Pike
     o  Southerly
     o  Combined

Peak Process Flows (MGD)

     o  Jackson Pike
     o  Southerly
     o  Combined

Design BOD Load (Ib/day)

     o  Jackson Pike
     o  Southerly
     o  Comb ined

Design TSS Load Clb/day)

     o  Jackson Pike
     o  Southerly
     o  Combined
                                  Facility Plan3  SEIS   Percent Difference
     96
     72
    168
    163
    122
    285
 88
 66
154
132
 99
231
141,600    134,600
126,600    121,300
268,200    255,900
161,600    168,600
121,300    123,800
282,900    292,400
 -8.3
 -8.3
 -8.3
-19.0
•18.9
-18.9
             -4.9
             -4.2
             -4.5
             +4.3
             +2.1
             +3.2
a Adjusted to reflect 20-year planning period ending 2008 and to eliminate
  loads associated with Whit tier Street CSO structure.
                                      4-36

-------
     The difference in the peak process flows is due to the differences in
design average flows and different peaking factors.  The peaking factor is 1.5
for this SEIS and 1.7 for the facility plan.  The 1.5 peaking factor for the
SEIS is consistent with the peaking factor used in the 1979 EIS.  The facility
plan's peaking factor of 1.7 is based on the maximum hydraulic capability of
the conduits between the primary clarifiers and aeration basins in the
existing trains at the Southerly WWTP.  Since CSO is not a component of this
SEIS, it did not seem appropriate to endorse a peaking factor of 1.7.

     As a result of the significant differences in average design and peak
process flows, the flows developed for this SEIS will be used for further
alternative analysis and recommended process sizing.

     The SEIS loads, on the other hand, are all within 5 percent of the
facility plan loads.  Therefore, the 2008 facility plan loads will be accepted
as the SEIS loads, and they will be used for further alternative analysis in
the SEIS.  Table 4-16 summarize* the SEIS recommended flow and loads.

                TABLE 4-16.  2008 RECOMMENDED FLOWS AND LOADS

                               Jackson Pike    Southerly      Total
Average Flow (MGD)                    88            66           154
Peak Process Flow (MGD)              132            99           231
BOD Load (Ib/day)                141,600       126,600       268,200
TSS Load (Ib/day)                161,600       121,300       282,900

4.5  COMBINED SEWER OVERFLOWS
     The Revised Facility Plan Update (RFPU) and the General Engineering
Report and Basis of Design (GERBOD) documents provided a brief analysis of
the CSO problem.  The analysis was conducted on a limited data base not
adequate for planning and design of CSO abatement neasures.  Consequently,  the
city is planning to conduct a detailed CSO study. The SEIS briefly reviewed
                                     4-37

-------
the CSO analysis that was prepared during the facilities plan preparation.
Appendix E entitled Briefing Paper No. 5 - CSO provides a review and critique
of the city's analysis.

     A review of the OEPA Central Scioto River Mainstem Comprehensive Water
Quality Report (CWQR) indicates that combined sewer overflows contribute
significant pollutant loadings to the Scioto River.  The majority of the data
reviewed in the CWQR was collected between 1976 and 1982.  The CWQR states
that "combined sewer overflows, and as previsouly discussed, plant bypasses
also contributed significant loadings of BOD, NH^-N, TSS, and other
substances to the Central Scioto River Mainstem."  In addition, page 317
states "Reductions in the magnitude and frequency of combined sewer overflow
discharges is needed to improve aquatic community function, alleviate
aesthetic problems, and reduce risks to human body contact recreation in the
segment between Greenlawn Dam. and the Jackson Pike WWTP."  The particular
sources of pollutant loadings discussed in the CWQR are the Whittier Street
CSO and the Southerly raw sewage bypass.

     The Whittier Street Storm Standby Tanks provide short-term storage and
some clarification for flows in excess of the Jackson Pike WWTP's hydraulic
capability.  The Jackson Pike WWTP is hydraulically limited to 100 MGD.  As
previously discussed in this chapter, the estimated"peak process flow for the
Jackson Pike Service Area is 132 MGD.  Following completion of the north end
of the Interconnector, 32 MGD can be diverted to the Southerly WWTP for
treatment.  This may alleviate some of the combined sewer overflows occurring
at the Whittier Street facility.

     Some of the combined sewers in the Southerly Service Area have been
separated in recent years.  The entire CSO drainage area has decreased from
18.4 square miles to 10.7 square miles.  This may have reduced the quantity
and frequency of bypasses at the Southerly WWTP and at the overflows within
the Southerly Service Area.
                                     4-38

-------
     In order to assess Che magnitude of the combined sewer overflows at the
present time, a comprehensive study must be performed using current monitoring
data.   This study must include a determination of the inflow problem from the
separate sewer area.   As discussed in the CSO analysis in Appendix E, the
volume of inflow from  the separate sewer area could be greater than the volume
of runoff and inflow  from the combined sewer area.
                                     4-39

-------

-------
                           CHAPTER 5.  ALTERNATIVES

     This chapter presents comprehensive wastewater management alternatives
and options for the components that comprise these comprehensive wastewater
management alternatives.  The comprehensive wastewater management alternatives
include the following:

     *  No action
     •  Upgrade Jackson Pike and Southerly, provide wet stream treatment and
        solids handling at both plants
     •  Upgrade Jackson Pike and Southerly, provide all solids handling at
        Southerly
     •  Eliminate Jackson Pike, upgrade and expand Southerly.

     Each of the comprehensive wastewater management alternatives includes the
following components:

     •  Intercomxector/headworks
     •  Biological process
     •  Sludge management.

     Options for these components will be presented in this chapter.  Options
will not be presented for primary treatment and post treatment.  It is assumed
for all comprehensive wastewater management alternatives that primary
treatment will consist of preaeration and primary settling, and post treatment
will consist of chlonnation and post aeration.

     Numerous studies have been completed since the 1979 Environmental Impact
Statement (EIS) that have influenced the development of the alternatives and
options presented in this chapter.  These major studies include:

     •  1981 -  Segment 2 - Long-Term Solids Hanrtl XP£
     •  1984 -  DPOT Review of the City of Columbus Facilities Plan and EIS
                Reports
                                     5-1

-------
     »  1984 -  Feasibility Study for Wastewater Treatment
     •  1984 -  Facilities Plan Update Report
     •  1985 -  Revised Facilities Plan Update.

     The principal elements of each of these studies, which contribute to the
development of alternatives, are summarized in the following sections.

Segment 2 - Long-Term Solids Handling Report (1981)
     The objective of the Segment 2 report was to evaluate solids processing
and handling at each treatment plant and develop an environmentally acceptable
and cost-effective long-term solution for solids treatment and disposal.

     The Segment 2 study concluded that the solids treatment process at
Jackson Pike and Southerly should include the following components:

     •  Primary sludge:  gravity thickening, anaerobic digestion, centrifuge
        dewatering, land application, or incineration.
     •  Waste activated sludge:  centrifuge thickening, possible anaerobic
        digestion, centrifuge dewatering, composting, or incineration.
     •  Emergency storage for thickened and dewatered sludges, and backup
        stabilization with lime addition.

     A Segment 1 report entitled, "Interim Solids Handling," was also
submitted to the OEPA in 1980.  This report proposed constructing three new
incinerators at Southerly and two new incinerators at Jackson Pike.  It also
proposed increasing composting at Southwesterly from 200 to 400 wet tons per
day.  This solution was intended to solve the immediate problem of solids
disposal until a long term solution could be developed and implemented under
Segment 2.  As a result of these recommendations, Southerly is currently
installing two new incinerators.  These new incinerators have a total capacity
of 520 wet tons per day at 20 percent cake solids.   The two existing
incinerators are rated at 300 wet tons per day at 20 percent cake solids.
                                     5-2

-------
This gives a total incineration capacity of approximately 820 wet tons per

day.


DFOT Report (1984)

     The Design Finalization Overview Team (DFOT) Report, a recommendation of

the 1979 EIS, contains an independent design evaluation of wastewater treat-

ment facility improvements for the Jackson Pike and Southerly treatment

plants.  The primary objective of the DFOT was to review the recommendations

and suggested design criteria presented in the facilities plan with respect to

the 1979 SIS and to reconcile any differences.  The primary recommendations

of the DFOT for the Jackson Pike and Southerly Wastewater Treatment Plants are

summarized below:


     Jackson Pike

     •  Increase primary clarification capacity slightly more than recommended
        in the EIS and original facilities plan.

     •  Adopt facilities plan recommendation for trickling filter capacity.

     •  Provide approximately 50 percent more intermediate clarifier capacity
        than recommended by the EIS and original facilities plan.

     •  Adopt the EIS proposal for activated sludge aeration basin capacity of
        31.5 million gallons.

     •  Increase final settling capacity slightly more than recommended in the
        facilities plan.

     •  Adopt original facilities plan proposal for effluent disinfection but
        add post aeration.

     •  Perform a trial study of thermal conditioning prior to anaerobic
        digestion and incineration.

     •  Design effluent filters and phosphorus removal facilities.  These
        facilities would not be constructed unless their need is verified by
        water quality studies.

     •  Adopt the proposal made by tie Segment 2 - Long-Term Solids Handling
        Report for gravity sludge thickeners and centrifuges.

     •  Use incineration as the preferred means of sludge disposal.
                                     5-3

-------
     Southerly

     •  Use a trickling filter/activated sludge treatment system.

     •  Restrict Anheuser-Busch BOD^ loads to 45,000 Ibs/day.

     •  Increase trickling filter and intermediate clarifier capacity
        approximately 40 percent more than the recommendations of the original
        facilities plan.

     •  Provide activated sludge aeration basin and final clarifier with
        capacities less than those proposed in the original facilities plan
        and EIS.

     •  Adopt effluent disinfection system as proposed in the original
        facilities plan.

     •  Design effluent filters and phosphorus removal facilities.  These
        facilities would not be constructed unless their need was verified by
        water quality studies.

     •  Adopt the proposal made by the Segment 2 - Long-Term Solids Handling
        Report for sludge thickening and digestion.

     •  Use incineration as the prime sludge disposal system until the market
        and dependability of composting and land application alternatives are
        assured.


Feasibility Study for Wastewater Treatment (1984)

     This report presents the findings of a preliminary investigation to

screen treatment plant site alternatives.  The alternatives include various
combinations of new plant construction, plant rehabilitation, and plant

expansion at the Jackson Pike, Southerly, and Southwesterly treatment plant
locations.  The Southwesterly plant would be located near the compost

facility.  The conclusion of this study was that alternatives involving

elimination of Jackson Pike and development of a new plant at the
Southwesterly site were economically feasible and should be more closely
investigated for possible implementation in the Columbus wastewater management
program.
                                      5-4

-------
FacilitiesPlan Update Report (1984Q

     The USEPA asked the city of Columbus to update its facilities plan to

conform to the recommendations of the EtS.  The Facilities Plan Update Report

(FPU) contained a review of numerous combinations of site and treatment

process alternatives.  Some new wet stream treatment process alternatives were

assessed that had not been evaluated in the previous reports.  The city also

looked at the possibility of constructing a new wastewater treatment plant

near the Southwesterly Composting Facility.


The recommendations of the FPU include:
     •  Elimination of the Jackson Pike WWTP, expansion and upgrading of the
        Southerly WWTP to handle all flows.

     •  Construction of a new pump station to transport the flow from the
        Jackson Pike service area.

     »  Implementation of an Anaerobic Anoxic Flocculation (AAF) process for
        biological treatment.

     •  Effluent polishing by granular media filters, if necessary, to satisfy
        the proposed NPDES permit requirements.  The report recommends that
        construction of these filters should be postponed until operating
        results for the new wet stream treatment facilities are available.

     •  Expansion of existing chlorine feeding equipment and new chlorine
        contact tanks.

     •  Expansion of the effluent pump station.

     •  Sludge processing which consists of thickening, digestion, and
        dewatering.

     •  Ultimate disposal of sludge by incineration, composting, and land
        application.


     The FPU also recommended that the expanded plant be equipped with
distributed automatic monitoring and control systems in each major process

area, linked to a centralized monitoring and control station.  In addition, a
video display terminal should be provided in the Office and Maintenance
Building to enable the plant managers to perform routine monitoring tasks.
                                      5-5

-------
Revised Facilities Plan Update (1985)
     The Revised Facilities Plan Update Report (RFPU)  was developed to
supplement the FPU.  The specific objectives of the document were:   (1) to
revise the recommendations of previous documents based upon revised design
parameters and NPDES permit limits; (2) to present the conclusions  and
recommendations of planning analyses undertaken since completion of the FPU;
(3) to respond to comments by the OEPA relative to the FPU; and (4) develop
treatment facilities which will serve the city's needs through the  year 2015.

The following basic conclusions and recommendations were presented  in the
RFPU:
     •  It is cost effective to expand the existing city of Columbus Southerly
        wastewater treatment facility to treat all wastewater from the
        Columbus service area and to phase out the existing Jackson Pike
        wastewater treatment facility.
     •  Flows should be diverted from Jackson Pike to Southerly via completion
        of the North End and expansion of the South End of the Interconnector
        Sewer.
     •  Biological treatment should be accomplished through a semi-aerobic
        process.
     •  Solids processing consists of gravity and centrifuge thickening,
        anaerobic digestion, dewatering of nondigested sludge for composting,
        and land application of digested sludge.
     •  Maintain current incineration capacity, but land disposal and
        composting are the preferred sludge disposal methods.

     The above paragraphs have summarized the recommendations of previous
studies which have contributed to the development of alternatives in this
report.  The following sections of this chapter provide discussions on options
for plant location, conveyance, headworks, biological treatment processes, and
sludge management alternatives.  These alternatives are subjectively screened
                                      5-6

-------
in this chapter to eliminate the alternatives which are not suitable for the
Columbus facilities.  Those alternatives which advance from the subjective
screening will be evaluated in greater detail in chapter 6.

5.1  COMPREHENSIVE WASTEWATER MANAGEMENT ALTERNATIVES
     The existing wastewater treatment facilities for the Columbus
metropolitan area consist of the Jackson Pike and Southerly Wastewater
Treatment Plants (WWTP) (See Figure 3-1).   Previous planning documents have
evaluated other alternatives for treatment plant location.  These studies have
evaluated continued operation of the existing facilities as well as abandoning
the Jackson Pike WWTP and constructing a new Southwesterly plant to handle
Jackson Pike flows or expanding the Southerly WWTP to handle all the flow from
the Columbus area.  None of the previous studies found it to be cost effective
to build a new facility at a Southwesterly site.   However, the FPU and the
RFPU found that expanding Southerly to handle all flows was cost effective.
Therefore, this study will evaluate the following alternatives:

     •  No action
     •  Upgrade Jackson Pike and Southerly, provide wet stream treatment and
        solids handling at both plants
     •  Upgrade Jackson Pike and Southerly, provide all solids handling at
        Southerly
     *  Eliminate Jackson Pike, upgrade and expand Southerly.

     The following sections discuss these four alternatives and their impacts.

5.1.1.  No Action Alternative
     The development of a no action alternative is consistent with EPA
qutdeLines for preparing an EIS.  A no action alternative cannot be eliminated
during a preliminary screening.
                                     5-7

-------
     Implementation of a no action alternative would involve normal
maintenance but no improvement to the existing facilities.  Failure to
implement procedures to correct wastewater management problems in the Columbus
facilities planning area will result in permit violations for the Columbus
treatment facilities.  The Columbus wastewater treatment plants, without
improvements, cannot meet final NPDES permit limits.  In accordance with the
city's Municipal Compliance Plan, the plants are required to be in compliance
with the final permit limits by July of 1988.  An inability to meet permit
requirements may result in sanctions by OEPA and USEPA that could have adverse
social and economic impacts in the facilities planning area.

     The no action alternative will be retained and used in chapter 6 as a
baseline for comparing and evaluating action alternatives.

5.1*2  UpgradeJackson Pike and Southerly, Provide Wet Stream Treatment and
       Solids Handling at Both Plants
     This alternative will be referred to as the two-plant alternative.  It
was the recommendation of the 1979 Environmental Impact Statement.  In this
alternative the existing treatment plant sites will be maintained.  Each plant
will be rehabilitated and expanded as necessary to provide advanced wastewater
treatment on site for wastewater flows expected through the year 2008.  Due to
site limitations at Jackson Pike, the wet stream treatment capacity cannot be
expanded.  However, the existing facilities could be upgraded to provide
necessary treatment to meet proposed effluent requirements for an average flow
of 80 MGD and a peak flow of 100 MGD.  Any excess flow would be diverted to
Southerly via the Interconnector Sewer.

     The Southerly WWTP would be upgraded and expanded to treat an average
flow of 74 MGD and a peak process flow of 131 MGD.

     This alternative will be retained as it is consistent with existing
operating practice.  It will be evaluated in further detail in chapter 6.
                                      5-8

-------
5.1.3  UpgradeJackson Pike and Southerly, Provide All SolidsHandlingat
       Southerly
     This alternative will be referred to as the two-plant one solids
alternative.  Under this alternative, both plants would be upgraded to provide
wet stream treatment.  All solids handling processes would be provided at
Southerly.  Jackson Pike's solids would be transported to Southerly via sludge
pipelines.  This alternative was developed because an 8-inch sludge pipeline
currently  exists  between the Jackson Pike and Southerly WWTPs.   It will  be
evaluated in further detail in chapter 6.

5.1.4  Eliminate Jackson Pike, Upgrade and Expand Southerly
     This alternative will be referred to as the one-plant alternative.  It
was recommended by the city in the Facilities Plan Update and the Revised
Facilities Plan Update.  Under this alternative, Jackson Pike would be phased
out and all Jackson Pike flows would be diverted to Southerly via the
Interconnector.  The existing facilities at Southerly would be expanded and
upgraded to treat an average flow of 154 MGD and a peak process flow of
231 MGD.  This alternative merits further consideration, and it will be
retained for a more detailed evaluation in chapter 6.

5.2  INTERCONNECTOR/HEADWORKS OPTIONS
     This section discusses the options for the Interconnector/headworks
components under each of the alternatives.

5.2.1  Interconnector
     Each of the comprehensive wastewater management alternatives require
completion of the north end of the Interconnector (Figure 3-3).  The city
maintains that, due to site limitations and existing hydraulic constraints
within the facility, Jackson Pike is not capable of handling more than 100
MGD.  Consequently, the diversion chamber and the Interconnector must be
completed to allow flows in excess of 100 MGD to be diverted from Jackson Pike
to Southerly.
                                      5-9

-------
     The Intercormector Sewer that is being constructed between Jackson Pike
and Southerly is near completion.  It runs in a north-south direction along
the west side of the Scioto River and it crosses the river on the south end to
connect with the Southerly WWTP.

     The main section of the Interconnector has a diameter of 156 inches.  On
the south end it connects with a pumping station.  The South End Pumping
Station, with a capacity of 60 MGD, pumps the flow across the river to
Southerly through a 48-inch force main and a 36-inch force main.  The north
end of the Interconnector is incomplete.  The Municipal Compliance Plan states
that it will be in place by May of 1988.  It will be constructed along the
west and north sides of Jackson Pike (Figure 3-3).  A diversion chamber will
be built to connect the O.S.I.S. with the Interconnector.  This will allow
regulation of flows to Jackson Pike and diversion of flows to Southerly.

     Based on the flows developed in this document, the pump station and force
mains at the south end of the Interconnector are adequate to handle the flow
under both two-plant alternatives.  The maximum potential flow which will be
diverted from Jackson Pike under peak conditions is 32 MGD.  Approximately 10
to 15 MGD currently flows through the Interconnector from a connection at
Grove City.  This total flow of 47 MGD is within the capabilities of the
current pump station and force mains.

     The south end of the Interconnector will require some expansion
under the one-plant alternative.  The sewers must be sized to accommodate
flows through the year 2008.  The projected peak process flow for Jackson Pike
is 132 MGD.  The expanded facilities must accommodate this flow in addition to
the 15 MGD from Grove City.

     The RFPU proposed two options for expansion of the south end of the
Interconnector.  One option (Option A) involves expansion of the existing
Interconnector Pump Station to a capacity of 160 MGD and construction of
additional 36-inch and 48-inch force mains (Figure 5-1).
                                      5-10

-------
                          \
                             \
           EXISTING 156"
           INTER CONNECTOR SEWER
                             \


                                EXISTING PUMPING
                                STATION
                         PROPOSED  PUMPING
                         STATION  EXPANSION
                               y ------
                                              f
'£>'
        PROPOSED ADDITIONAL
        FORCE MAINS
                                             I i
                                             Y-i
                                              «— '
                              Oa°
CD
CD
       D
                           n ODO
                          cLJ EH
                                          SOUTHERLY W.WTP
\
                                                                  o
                                                                  o
                                                                 -
                                                                 X
                                                                 UJ
                                  EXISTING 48" & 36" FORCE MAINS   /
SCALE:  1"
SOURCE- REVISED FACILITY PLAN UPDATE
                                                                                i  t
                                                                                  I
                                                                                i  i

                                                                                ©
                                                                                i — i
                                                                                I  I
                                                                                \  \

                                                                                \ \
                                                                                 \
                                                                                 \
                                                                                 \
                                                                                    \
                                                                                    \

                                                      FIGURE 5-1

                                                      SOUTH END INTERCONNECTOR OPTION A

-------
     The second option (Option B) proposes  abandoning  the  existing  force  mains
and extending the 156-inch gravity Interconnector to Southerly.   Three options
were evaluated for the Scioto River crossing.   Extending the 156-inch pipe
across the river bed would raise the water level of the river by seven feet.
Tunneling the 156-inch pipe beneath the Scioto River was also investigated.
However, the excessive costs associated with the depth of  this pipe and the
increased depth of the Southerly headworks prevented this  option from being
considered economically feasible.  The third option requires the installation
of four 78-inch pipes across the river bed (See Figure 5-2).   This  will raise
the water level approximately three feet and  is  the  option recommended by the
city in the RFPU.

     Each of these Interconnector options must be evaluated in either
conjunction with the headworks option prior to eliminating each of them.
Therefore,  they will be retained for further consideration.   Chapter 6 will
evaluate the Interconnector options in detail  with the headworks options.

5.2.2  Headworks
5.2.2.1  Jackson Pike
     The Jackson Pike headworks are located approximately one mile north of
the treatment plant at the Sewer Maintenance Yard on the west bank of the
Scioto River.  These  remote headworks consist  of bar screens and aerated grit
tanks.   The  bar  screens were originally mechanically cleaned but due to their
age and deteriorated condition,  manual screen cleaning is  now necessary.   Flow
enters the headworks via  the O.S.I.S.  The flow  that enters  the  Jackson Pike
plant comes from  the remote headworks on the O.S.I.S.  and  the Big Run
Interceptor.  The  combined flow  enters a wet well in the pump and blower
building where it is screened and pumped to the  wet  stream treatment
facilities.  Therefore, flows entering Jackson Pike  from the Big Run
Interceptor are not subject to grit removal.
                                      5-12

-------
                              \
                                                                     I  1
                                 \
             EXISTING 156"           *   ,
             INTERCONNECTOR SEWER   /
                                  /
                                /
                                  /
                              /
        /  ,
       ,'  /   ABANDON
       —/	EXISTING PUMPING
              STATION


  s

'     PROPOSED 156"
^^— INTERCONNECTOR
      GRAVITY EXTENSION
    1^1         (4) 78" PIPES
    , £          ACROSS RIVER

   /I/
  /   /

/   /
1    I
\   \

 SCALE- r«500'
 SOURCE. REVISED FACILITY PLAN UPDATE
\ r 	
I
i
I
i
/~\f-i/-\
tJQvJ
*m^ ^M. I
ODO
_n°D°
dJ en
	 -\f
I1'
T]
cn
cu
SOUTHER
                                                   • uj
                                                   I w
                                                   i •«
                                                   . o
                                                                         I  -
                                                                         1  X
                                      EXISTING 48"  k 36" FORCE MAINS
                                     D   D
i
i
i  i
©
i—i
i  \


                                       FIGURE 5-2
                                       SOUTH END  INTERCONNECTOR OPTION B

-------
     Under the one-plant alternative, the headworks at Jackson Pike would only
require necessary maintenance until the plant is phased out in the 1990"s.
The two-plant alternatives would require entirely new headworks consisting of
pumping, screening, and grit removal for Jackson Pike located at the plant,
rather than at the sewer maintenance yard two miles away.

5.2.2.2  Southerly
     The existing headworks at Southerly consist of bar racks, bar screens,
aerated grit tanks, and pumps rated at a capacity of 170 MGD.  Flow enters the
plant from the Interconnector and from the Big Walnut Sanitary Outfall Sewer
which serves the northeast, east, and southeast portions of Columbus and
Franklin County.

     Under both two-plant alternatives, the Southerly WWTP will be required to
treat an average flow of 74 MGD and a peak process flow of 131 MGD.  Since
current headworks are rated at a capacity of 170 MGD, no expansion of these
facilities is required.

     The one-plant alternative requires that Southerly treat an average flow
of 154 MGD and a peak process flow of 231 MGD.  At these flows, the current
headworks are inadequate.  The determination of the optimum headworks option
(i.e., expand the existing or provide new facilities) is related to the
Interconnector option selected.  Interconnector Option A, which involves
expanding the existing pump station and adding additional force mains, would
allow expansion of the existing headworks.  Expansion of the existing
headworks will be called Option A-l.  If Interconnector Option B is selected,
the 156-inch gravity sewer extension would enter the Southerly headworks
approximately eight feet lower than the Big Walnut Interceptor.  This
Interconnector option would require separate headworks (Option B-l) to handle
the flow from the Interconnector or completely new headworks (Option B-2) to
handle the flows from both.
                                      5-14

-------
     Option B-l consists of utilizing the existing 170 MGD headworks at
Southerly for handling the flows from the Big Walnut Interceptor and
constructing a new 150 MGD headworks for handling the Interconnector flows.
The new Interconnector headworks will be located adjacent to the existing
headworks.  They will include coarse bar racks,  raw  pumping, followed by
mechanical screening and aerated grit removal; all designed for 150 MGD.
Mixing of the Interconnector and Big Walnut flow would follow aerated grit
removal.

     Option 8-2 involves constructing completely new headworks which include a
mixing chamber, coarse bar racks, pumping,  and aerated grit chambers.   The
flows from the Big Walnut Interceptor and the Interconnector would  combine  in
a mixing chamber and be conveyed through manually cleaned bar racks.   The
combined flow will then enter a wet well to be pumped to mechanical bar
screens followed by aerated grit chambers.  The new  headworks  will  be designed
for a peak process flow of 231 MGD.

     Based on the subjective screening,  all three headworks options merit
further consideration.  Each of  the  headworks  options  will  be  evaluated in
conjunction with the Interconnector  options in chapter 6.

5.3  BIOLOGICAL PROCESS OPTIONS
     This section presents the options for the biological process component.
The current biological process used at both the  Jackson  Pike and Southerly
WWTP's is conventional single-stage activated sludge.  This  single-stage
activated sludge process  is preceeded in  the wet  stream  treatment process by
preaeration and primary settling and it is followed by chlorination prior to
discharge to the Scioto River.

     Both plants were designed based on NPDES discharge  limitations of 30 mg/1
for BOD and TSS.  These limits have  become  more  stringent and  the plants  can
no longer successfully treat the original design capacity flows.
                                     5-15

-------
     Through the course of the facilities planning process for the Columbus
wastewater treatment system, other process options were proposed and
evaluated.  The 1979 EIS recommended a trickling filter process for the
Jackson Pike plant.  The Facilities Plan Update (FPU) and Revised Facilities
Plan Update (RFPU) recommended semJ-aerobic treatment processes.  In the
following sections the semi-aerobic, trickling filter, and conventional
activated sludge processes including variations are discussed.

5.3.1  Semi-Aerobic
     The semi-aerobic process, being proposed by the city of Columbus, is a
modified form of the activated sludge process.  The process consists of a
non-aerated reaction zone ahead of the aerated activated sludge zone.  These
non-aerated zones may be anoxic (oxygen concentration less than or equal to
0.3 mg/1 and nitrates present),  anaerobic (no oxygen or nitrates present) or
a combination of anoxic and anaerobic zones.  Figure 5-3 provides a schematic
of the semi-aerobic process.  Figure 5-4 shows the process in three different
modes of operation.

     The semi-aerobic process employs a high to low food-to-microorganism
(F:M) gradient and a high oxygen uptake rate to dissolved oxygen ratio
(OUR/DO) in the first two bays of each aeration tank to produce a non-bulking
sludge.  The semi-aerobic process is physically the same as the conventional
activated sludge process with the exception of two additional baffles in the
first bay of each aeration tank and an internal sludge recycle system in each
tank.  The baffles are added to eliminate backmixing.  The sludge recycle
system provides the ability to denitrify by recycling nitrates from Bay 8 back
to Bay I.

     Jet aerators would be installed in the first two bays of each aeration
tank to provide the flexibility for aerating or mixing these bays.  Normal
operation will consist of mixing.  However, air will be employed in Bay 2 and
Bay 1, if necessary, when the ammonia breaks through Bay 6 or Bay 7.  The
                                      5-16

-------
PRIMARY
EFFLUENT

                           AERATION TANKS
                              n      Q
p     p       p      p
                                                  NN
                                 INTERNAL RECYCLE
                                 RECYCLE SLUDGE
           ANOXIC/AN AEROBIC
 AEROBIC
                                                EFFLUENT
                                                                                        CLARIFIER
                                                                                 WASTE SLUDGE
                                                                           FIGURE 5-3
                                                                           SEMI-AEROBIC PROCESS

-------
                         8
Ul
h-
00
AERATION BASIN
EFFLUENT
PRIMARY
EFFLUENT
°x
Ax
Ax
Ax
°x
AN
°X
°X
°X
°x
                    1o    1b     1c             2                   3
                                    SOUTHERLY COLD WEATHER - HIGH N03N RECYCLE
                          8
AERATION BASIN
EFFLUENT
PRIMARY
EFFLUENT
°x
Ax
Ax
AN
°X
AN
°X
°x
°x
°x
1o   Ib    1c            2                  3
                SOUTHERLY WARM WEATHER - LOW N03N RECYCLE
                          8
AERATION BASIN
EFFLUENT
PRIMARY
EFFLUENT
°x
Ax
Ax
Ax
AN
°X
°X
°X
°X
°X
°x
                    1a    1b
           1c
    Ax =ANOXIC
    AN -ANAEROBIC
    Q =OXIC
 2                   3
SOUTHERLY HIGH EFFLUENT NH4N
                                                        FIGURE 5-4
                                                        SEMI-AEROBIC  PROCESS
                                                        MODES OF OPERATION

-------
remaining six bays of each aeration  tank would be equipped with fine bubble
diffusers.  The semi-aerobic process has the ability to control sludge bulking
and to nitrify.  It can easily be incorporated into the existing tankage.
Therefore, it will be retained for further evaluation in chapter 6.

5.3.2  Trickling Filter Processes
     Trickling filter systems are commonly used for secondary treatment of
municipal wastewater.  Primary effluent is uniformly distributed on a bed of
crushed rock, or other media, coated with biological films.

     The microbial film on the filter medium is aerobic to a depth of only 0.1
to 0.2 mm.  The zone next to the medium is anaerobic.  As the wastewater flows
over the microbial film, the soluble organics are rapidly metabolized and the
colloidal organics absorbed into the surface.  Microorganisms near the surface
of the bed, where food concentration is high, are in a rapid growth phase,
while the lower zone of a bed is in a state of endogenous respiration.
Dissolved oxygen extracted from the liquid layer is replenished by reoxygena-
tion from the surrounding air.

     Major components of the trickling filter are the filter media, underdrain
system, and rotary distributor.  The filter media provides a surface for
biological growth and voids for passage of liquid and air.  The underdrain
system carries away the effluent and permits circulation of air through the
bed.  A rotary distributor provides a uniform hydraulic load on the filter
surface.

     Two variations of trickling filters have been presented in previous
studies.  They are:

     •  Trickling filter/activated sludge (TF/AS)
     •  Trickling filter/solids contact (TF/SC).

     The following sections describe each of these processes.
                                     5-19

-------
5.3.2.1  Trickling Filter/Activated Sludge
     This trickling filter process option includes trickling filters coupled
with activated sludge basins.  (See Figure 5-5).  The trickling filter
treatment units are packed with cross flow plastic media.  The filters are
designed for approximately 35 percent BOD removal.  The aeration tanks that
follow the filter remove the remaining BOD^ and provide the required
nitrification.

     The activated sludge tanks are sized for the amount of solids generated
from the trickling filters and activated sludge tanks.  This method utilizes
existing aeration tanks.  The trickling filter provides a selector mechanism
for nonfilamentous bacteria growth in the same manner as the anaerobic zone
operates in the semi-aerobic process.  Slightly reduced aeration tank capacity
and aeration energy is required due to the portion of the BOD^ removed in the
trickling filter process.  This process is capable of controlling sludge
bulking and performing nitrification; therefore, it will be evaluated further
in chapter 6.

5.3.2.2  Trickling Filter/Solids Contact
     In this treatment process, trickling filter units are coupled with a
solids contact channel prior to secondary clarification (See Figure 5-6).  A
portion of the sludge which is settled in the secondary clarifiers is
recirculated to the influent of the solids contact channel.  An aeration time
of approximately one half hour is required in the solids contact channel.  The
contact of the return sludge with the trickling filter effluent in the solids
contact channel enhances the BOD removal and suspended solids removal in the
secondary clarifiers.  Both BODc and ammonia removal are achieved in the
trickling filters prior to the solids contact channel.  The TF/SC process
satisfies the required BOD? removal and nitrification, but it also has some
disadvantages.  An excessive number of trickling filter units are required
(approximately 50 for a one-plant scenario), and only one aeration tank is
required for use as a solids contact channel.  The remaining aeration tanks at
                                      5-20

-------
  PRIMARY

  EFFLUENT
                      1
               A A  A '-' A A A
Y1
N>
                 TRICKLING FILTER
AERATION TANKS
                                                              '/
     RECYCLE SLUDGE
                                                                                               EFFLUENT
                                                                                              CLARIFIER
                                                                                       WASTE SLUDGE
                                                               FIGURE 5-5

                                                               TRICKLING  FILTER/ACTIVATED  SLUDGE

-------
   PRIMARY
   EFFLUENT
                       1
                A A A "-1 A  A A
vrt
                 TRICKLING FILTER
AERATED SOUOS CONTACT CHANNEL
                                                                                                EFFLUENT
                                                              RECYCLE SLUDGE
                                                                                              CLARIFIER
                                                                                       WASTE SLUDGE
                                                                   FIGURE 5-8
                                                                   TRICKLING  FILTER/SOIIDS CONTACT

-------
either treatment: plant would  remain unused.  Due  to  its high capital costs and
the fact that it does not make full use of  existing facilities, this process
alternative is eliminated from further consideration.

5.3.3  Conventional Activated Sludge
     The conventional activated sludge process is the current biological
method used at both the Southerly and Jackson Pike WWTP's.  It consists of
rectangular aeration basins with air diffusers to provide aeration and mixing,
followed by secondary clarifiers.   Settled raw  wastewater and return activated
sludge enter the head of the tank.   The  flow proceeds to  a clarifier where the
solids are settled out.

     The activated sludge process consistently removes 85 to 95 percent of the
BOD and suspended solids.  The amount of  nitrogen and phosphorus removed can
vary considerably depending on the design and operating parameters of the
system.

     Two forms of the activated sludge process are being evaluated in this
report.  They are:

     •  Single-stage activated sludge
     •  Two-stage activated sludge.

     The following sections discuss these two processes.

5.3.3.1  Single-Stage Activated Sludge
     A single-stage activated sludge system consists of an aeration basin
followed by a clarifier (Figure 5-7).  The aeration basin  is typically
operated as a plug-flow system.  Air diffusers  are installed along the length
of the tank to provide aeration and mixing.   One  mode of  operation is to taper
the air flow along the length of the tank to provide a greater amount of
diffused air near the  head where the  rate of biological metabolism and
resultant oxygen demand are the greatest. Another mode of operation,  which is
                                      5-23

-------
    o-
    o-
          )
to
2
<
    L>
                            "

fl

                            "
                            't
                            /
                                                               UJ
                                                               o
                                                               o

                                                               to
                                                               to
                                                                     O
                                                                     P
                                                                     3
                                                                     V)
                                                                     p

                                                                     I

RECYCLE SLUDGE
                                          •
          Q_ UJ
                                      5-24

-------
consistent with the mode of operation  for the  semi-aerobic process, is to
reverse taper the air supply to create an anaerobic/anoxic zone at the head of
the aeration basin.  This anaerobic/anoxic zone acts as a selector mechanism
against filamentous organisms, thus it assists in controlling sludge bulking.

     Since the semi-aerobic process is simply  a modified version of the
single-stage activated sludge process, they can be evaluated as one process
with operational flexibility.  Therefore, the  single-stage activated sludge
process will be eliminated at this point and chapter 6 will evaluate the semi-
aerobic process.

5.3.3.2  Two-Stage Activated Sludge
     With strong domestic wastewaters, staged  treatment may be beneficial and
produce a better effluent than the same reactor volume in a single stage.  In
the first stage, conditions are optimized for carbonaceous removal, while the
second aeration basin is optimized to develop  the maximum nitrifying
population.  The disadvantages for this approach include disposal of more
waste sludge, the cost of intermediate clarification units, as well as those
costs for separating the reactor basins of the two stages and possible costs
for additional lime for pH control.  Controlling the loss of second-stage
solids is also critical.  To maintain sufficient aeration solids for cell
synthesis it is sometimes necessary to bypass a portion of the influent flow
to the second stage, add return sludge from the first stage to the second
stage, or bypass, in part, the intermediate settling basin.  A two-stage
activated sludge system is shown in Figure 5-8.  Due to the additional capital
cost associated with adding intermediate clarifiers and difficulties
associated with process control,  this option does not merit further
evaluation.
                                      5-25

-------
              AERATION TANKS

                   P
PRIMARY
EFFLUENT
  Ni
  O\
           EFFLUENT
                                      WASTE SLUDGE
WASTE SLUDGE
                                                                    FIGURE 5-8

                                                                    TWO-STAGE ACTIVATED SLUDGE

-------
5.4  SOLIDS HANDLING
     Combinations of physical, chemical, and biological processes are  employed
in handling the solids  (sludge) generated during the wastewater  treatment
process.   The objective of processing sludge is to stabilize the organic
material, to extract water from the solids,  and dispose of  the dewatered
residue.   The sequence  of the various processes is critical to the ultimate
performance of the  facility.

     This section will discuss sludge production and available sludge
processing methods and  then present feasible combinations of these methods  for
evaluation as sludge management options.

     Both plants current sludge processes  (Figures 5-9 and 5-10) include
centrifugal thickening  and dewatering.  Jackson Pike also utilizes anaerobic
digestion and heat treatment.  Southerly has digesters, but they are not
currently operational.   Incineration and land application are used at  Jackson
Pike for ultimate disposal.  Southerly disposes of their solids  via incinera-
tion and composting. The solids handling capacity at both  plants  is limited
by either inadequate equipment or  poor performance due  to  aging  equipment.

5.4.1  Sludge Product ion
     The Jackson Pike WWTP currently produces 230  to 250 wet tons per  day of
dewatered sludge at a cake solids  concentration of about 17 percent.   On a dry
weight basis, approximately 50 dry tons per day (dtpd)  of dewatered solids are
produced for ultimate disposal. Based on recent operating  records, approxi-
mately 50 percent of the dewatered sludge is incinerated and 50  percent is
land applied.

     The Southerly WWTP  currently produces 350-400 wet  tons per  day of
dewatered sludge at a cake solids  concentration of about 17 percent.   On a dry
weight basis, approximately 64 dry tons per day (dtpd)  of dewatered solids are
produced for ultimate disposal.  Based on recent operating  records,
                                     5-27

-------
  RAW
  INFLUENT
            PRELIMINARY
             TREATMENT
   PRIMARY
CLARIFICATION
                                                       AERATION
                         SECONDARY
                        CLARIFICATION






•
EFFLUENT

to
CD
                 INCINERATION

                                           PRIMARY
                                           SLUDGE
                                           HOLDING
                                 ANAEROBIC
                                 DIGESTION
   DIGESTED
SLUDGE HOLDING
                                                       THICKENED  RAW SLUDGE
                                                       TO DEWATERING
                                                                                   VAS
                                                                                   HOLDING
                                                  CENTRIFUGE
                                                  THICKENING
                                                  VAS


                                                  THICKENED
                                                  SLUDGE
                                                  BLEND/STORAGE
CENTRIFUGE
DEVATERING
                                                                   THERMAL
                                                                 CONDITIONING
                      TO
                    LANDFILL
    TO LAND
  APPLICATION
                            FIGURE 5-9
                            JACKSON PUCE
                            EXISTING SLUDGE
                            MANAGEMENT SCHEMATIC

-------
            PRELIMINARY
PRIMARY
AERATION
SECONDARY
RAW '*
INFLUENT

c.mnc.

IN i ui-rir

ur XUH

liUP4



UL_rtP

cir iun

uun
EFFLUENT

VJl
                    CENTRIFUGE
                    DEVATERING
                                                                          CENTRIFUGE
                                                                          THICKENING
                                                                             VAS
                                                                         (PROJECT 88)
                                                    DISSOLVED AIR
                                                      FLOTATION
                                                      THICKENING
                                                     (ABANDONED)
       ANAEROBIC
       DIGESTION
       (UNDER REHABILITATION)
                                           DEVATERED
                                           SLUDGE
                                           STORAGE
                     INCINERATION
                                                                                          THERMAL
                                                                                        CONDITIONING
                                                                                        (ABANDONED)
                TO
             LANDFILL
                TO
             COMPOSTING
                     FIGURE 5-10
                     SOUTHERLY
                     EXISTING SLUDGE
                     MANAGEMENT SCHEMATIC

-------
approximately 70 percent of Che dewatered sludge is incinerated and the
remaining 30 percent is composted.

     The anaerobic digestion process is mainly responsible for the  smaller
quantity of dewatered solids at Jackson Pike.   Digestion breaks  down organic
matter in two phases.  In the first phase complex organic substrate is
converted to volatile organic acids.   In this  phase little change occurs  in
the total amount of organic material in the system.  The second phase involves
conversion of the volatile organic acids to methane and carbon dioxide.
Anaerobic digestion results in a decrease in the amount of solids.

     Table 5-1  presents  data on  the amount  of  metals present  in the processed
sludge at Southerly and Jackson Pike.   Zinc, cadmium,  and lead concentrations
are important factors to be considered in evaluating the land application and
composting programs.  Jackson Pike sludge has  significantly higher  metal
concentrations  than Southerly.   This could  impact a one-plant alternative
because the combination of Jackson Pike and Southerly sludge  could  change the
compost classification.

5.4.2  Unit Processes
     The following sections present each of the solids handling processes
being considered in this report.   The  unit  processes are limited to those
alternatives which have been presented in previous Columbus facility planning
studies.    They include:

     •  Sludge  Thickening
     •  Anaerobic Digestion
     •  Thermal Conditioning
     •  Dewatering
     •  Lime Stabilization
     •  Incineration
     •  Composting
     •  Land Application
                                     5-30

-------
                         TABLE  5-1.   SOLIDS ANALYSES
                              METALS  (mg/kg  TS)

                     CADMIUM   CHROMIUM   COPPER
SOUTHERLY*

  1985
September
October
November
December

  1986
January
February
March
April
May
June
July
August

AVERAGE

JACKSON PIKE**

  1985
September
October
November
December

  1936
January
February
March
April
May
June
July
August

AVERAGE

*  To Compost Facility
*« To Land Application
— No Data Available
13
39
                            LEAD   NICKEL  ZINC
16
12
18
18
184
193
153
140
258
233
223
194
218
240
230
162
36
28
27
32
1940
1700
1750
1480
15
14
17
10
6
8
5
111
164
152
149
140
110
119
178
166
197
211
249
258
240
143
202
212
149
168
250
175
31
36
45
31
56
53
53
1400
1086
1167
859
789
843
788
147
219
195
602
625
379
39
151
1255
50
49
38
50
796
820
685
680
686
652
713
613
358
392
398
565
134
162
173
303
5500
5175
4250
3900
36
40
44
32
30
30
26
565
608
577
480
462
478
473
565
539
559
643
640
658
608
315
386
319
332
376
375
358
125
125
147
128
144
113
110
3925
3559
3184
2485
2357
2575
2800
3610
                                     5-31

-------
5.4.2.1  Sludge Thickening
     Thickening is a common practice  for concentrating sludge.  It is  employed
prior to subsequent sludge processes to reduce the volumetric loading  and to
increase the efficiency of the downstream processes.  At present,  there are no
facilities for thickening primary sludge (PS) at the Southerly or  Jackson Pike
treatment plants.  Waste activated sludge (WAS) is thickened at both plants by
centrifuges.   They were installed in recent years to replace the dissolved air
flotation units.   Rehabilitation costs of the dissolved air flotation  units
dissuaded the city from their continued operation.  The following  paragraphs
will discuss gravity, and centrifugal  thickening.

     Gravity thickening is the simplest process for concentrating sludges.
Gravity thickeners are applied principally for thickening of primary sludge,
lime sludges, combinations of primary and waste activated sludges,  and to a
lesser degree, waste activated sludge.  Gravity thickening is a sedimentation
process which is similar to that which  takes  place  in all settling tanks.
Solids settle by gravity to the bottom of the basin forming a sludge blanket
with a clearer liquid (supernatant)  above.   The  supernatant  is  removed from
the basin over weirs located near the top of  the tank.   A scraper  arm  rotates
at the bottom of the tank gently stirring the sludge blanket.  This aids in
compacting the sludge solids and releasing the water from the mass, as well as
scraping the sludge toward a  center  well where it  can be withdrawn by  pumping.
Thickener supernatant is usually returned to either the primary or secondary
treatment process.

     Centrifugal thickening can have substantial maintenance and power costs,
but it is very effective in thickening waste activated sludge.  The centrifuge
is essentially a dewatering device in which the solids-liquid separation is
enhanced by rotating the liquid at high speeds.   The centrate stream is
usually returned to the plant influent.  Centrifuges have been used for both
sludge thickening and dewatering.
                                      5-32

-------
     Conditioning prior to thickening provides improved thickening and solids
 capture.  The thickening process makes primary and waste activated sludge
 difficult to blend together.   Therefore,  a mechanical mixing device is needed
 in  sludge holding  tanks.

     The RFPU recommendation for the  one-plant scenario included gravity
 thickening of PS and centrifugal thickening of WAS.

 5.4.2.2  Anaerobic Digestion
     Biological digestion of sludge from wastewater treatment is widely
 practiced to stabilize and break down  the organic  matter prior to ultimate
 disposal.  Anaerobic  digestion is used in plants employing primary
 clarification followed by either trickling filter or activated sludge
 secondary treatment.  The end products of anaerobic digestion are methane,
 unused organics, and relatively small amounts of cellular protoplasm.
 Anaerobic digestion is basically a destructive process,  although complete
 degradation of the organic matter under anaerobic conditions is not possible.

     The Columbus treatment  facilities currently have primary and secondary
 digesters.   However,  the digesters at Southerly have been out of service since
 1979.  Upgrading and possible expansion at both plants may be required.   The
 areas of contention in previous studies were  whether primary solids,  secondary
 solids, or both should be digested; if post thickening is  necessary;  and what
 the volume requirements should  be.

Anaerobic digestion provides a stabilized solids product that is suitable for
 land application.   Digestion is generally not considered conducive to
 composting.  The reduction in volatile solids would generally reduce the bio-
 activity in the composting piles, which is considered essential to generate
heat in the piles.
                                      5-33

-------
     Centrifuges are presently used to dewater mixtures of primary and waste
activated sludge at the Jackson Pike and Southerly WWTP's.  The RFPU recom-
mended additional centrifuges for dewatering.  A recent report entitled
Preliminary Evalution of Sludge Dewatering recommended replacing the existing
centrifuges with DPF presses.

5.4.2.5  Lime Stabilization
     The addition of lime, in sufficient quantities to maintain a high pH
between  11.0 and 11.5,  stabilizes sludge and destroys pathogenic bacteria.
Lime stabilized sludges dewater well on sandbeds without odor problems if a
high pH is maintained.   Sludge  filterability can be  improved with the use of
lime; however, caution  is required  when sludge  cake disposal to land is
practiced.  Disposal in thick layers could create a  situation where the pH
could fall to near 7 prior to the sludge drying out, causing regrowth of
organisms and resulting in noxious  conditions.  Essentially, no organic
destruction occurs with lime treatment.  The key  factor in assuring a proper
stabilization process is to maintain  the  pH above 11.0.

5.4.2.6  Incineration
     Sludge incineration is usually preceded by sludge thickening and dewater-
ing.   It requires an incinerator feed system, air pollution control devices,
ash handling facilities, and  the related automatic controls.  Two  major
incineration systems employed in the United States are the multiple-hearth
furnace,  the rotary kiln,  and the fluidized-bed reactor.   The  multiple-hearth
unit has received widest adoption because of its simplicity and operational
flexibility.   The Columbus facilities employ these furnaces for incineration,
but they also rely on land application and composting for sludge disposal.

     A primary consideration in the cost-effectiveness of sludge incineration
is the effect of sludge feed composition on auxiliary fuel requirements.   Heat
yield from a given sludge is a function of the relative amounts and elemental
composition of the contained combustible elements.  Primary sludges are higher
                                      5-36

-------
in heating value than biological sludges because of their higher grease
concent.   It  is  more economical to burn undigested solids than digested solids
since digestion significantly reduces the heat content of the  remaining
solids.   Therefore,  critical  design factors  for  any wastewater sludge
incineration system are heating value and moisture content of the sludge,
excess air requirements, and the economics of heat recovery.

     Another significant consideration for incineration is its relative
stability in regard to environmental and aesthetic factors.  The state of  the
art of incineration is such that various controls and  equipment modifications
are possible to meet a variety of possible environmental standards  above and
beyond those currently in place.  These potential modifications are costly,
but at least the basic  advantage exists  that the  ultimate control is within
the facilities operation and not as subject to the variations  in raw sewage
composition as other ultimate disposal processes such  as land  application  and
composting.

5.4.2.7  Composting
     Composting is an aerobic biological process designed to biologically
stabilize organics, destroy pathogenic organisms, and  reduce the volume of
waste.   The Southwesterly Composting Facility in Columbus uses the aerated
static pile method to process unlimed,  raw sludge.  The  final  product  from the
composting process, Corn-Til, is marketed as a soil conditioner.

     The aerated static pile  process  involves mixing dewatered sludge  with a
bulking agent,  such as wood chips, followed by active  composting in specially
constructed piles.   Typically,  both recycled bulking agent and new  bulking
agent are used for mixing.   Induced aeration,  either positive  (blowing) or
negative (suction),  is provided during active composting  and sometimes during
curing and/or drying.

     Temperature and oxygen are monitored during active composting  as  a means
of process control.   The active composting period lasts at least 21 days,
                                     5-37

-------
following which the piles are torn down and restacked for a curing period of
30 days.  After this period,  the mixture  is  screened  and  the wood  chips
recovered for  reuse.

     The issues of concern in composting are the odor problem  and  a market
demand for the final product.  The RFPU recommended composting in  addition  to
land application as the preferred  means of solids disposal with incineration
as a back-up.   The FPU recommended additional incineration due to the  tenuous
nature of composting and land application.

5.4.2.8  Land Application
     Following the recommendations of the original EIS,  the city of Columbus
has developed a program for land application of sludge.   A benefit of the
process results from the nutrient  value of nitrogen and phosphorus in the
sludge, which reduces  the quantities  of chemical fertilizer necessary on the
agricultural land.   The key factors in considering land  application as  an
alternative in sludge  disposal are haul distance,  climate, and availability of
land.   Environmental concerns  regarding land application  include surface water
and groundwater pollution,  contamination of  soil and  crops with toxic
substances,  and transmission of human and animal disease.

     Although nitrogen is a plus in this  process,  it  is  also a limiting factor
in considering the amount of sludge which can be safely applied.  Adding
excess nitrogen to  the  soil  involves  the  risk  of polluting the groundwater
with nitrates.  High nitrate concentrations  are toxic to humans and livestock.

     Cadmium concentrations in sludge are also a limiting factor in the
application rate.   Cadmium is taken up by plants and  enters the human food
chain.   The  primary chronic health effect  of excessive dietary intake of
cadmium is damage  to the kidneys.

     To keep excessive amounts of  cadmium, nitrate, and other  toxic substances
from entering the  soil, monitoring of the  sludge,  soil,  and crops  should be
                                     5-38

-------
done during utilization.   Aquifers should also be monitored for potential
nitrate pollution.

     Only stabilized sludge should be spread on farmland.  Sludge can be
stabilized by aerobic or anaerobic digestion,  lime, or thermal conditioning.
Farmers are usually advised to allow six weeks or more after sludge
application before harvesting crops or allowing animal grazing.   Preferred
vegetation is non-food-chain crops like cotton.   Feed grains  for  animal
consumption are also commonly fertilized by tilling sludge solids into the
soil before planting the crops.

     Sludge can be applied on the surface if local regulations  permit, or it
can be injected into the subsurface.   Subsurface injection is the most
environmentally desirable since it eliminates exposure of the sludge to the
atmosphere.  Surface application can be done by spreading or spraying.
Spraying through irrigation nozzles can only be practiced where insects and
odor are not a problem.

     The continued use of land application as  a preferred means of sludge
disposal is mainly dependent on the available  land for application and the
cost of transporting the sludge.

5.4.3  Sludge Management Options
     Sludge management options were formulated  in  light of several goals and
objectives.   These goals and objectives included the following:
     •  The sludge management options must consist of processing and disposal
        methods that will provide for environmentally sound processing  and
        ultimate disposal of sludge.
     •  The option must provide a reliable means for future processing  and
        disposal.
     •  The options should offer some flexibility allowing the city to  modify
        the processing and disposal  methods to relieve pressures created by
        equipment failures or temporary loss of the ultimate disposal methods.
                                     5-39

-------
     The options developed should consider,  to the extent  possible, optimizing
the reuse of the existing facilities  thus  minimizing implementation costs.

     This preliminary evaluation identified options for the  two-plant
scenario, where Jackson Pike and Southerly would be operated independently;
for the two-plant one solids scenario, where Southerly and Jackson Pike are
upgraded for wet stream treatment and Southerly is expanded  to provide  all  the
solids handling facilities; and for the one-plant scenario,  where Southerly  is
expanded to handle the projected flows and loads and the Jackson Pike  facility
is abandoned.  Under  the  two-plant  two solids scenario, three sludge
management options were  identified for Jackson Pike,  and six sludge management
options were identified  for Southerly.  For  the two-plant one solids and one-
plant scenarios the sludge management options which were identified for the
Southerly two-plant scenario were considered appropriate to evaluate.

5.4.3.1  Jackson Pike Sludge Management Options
     Three potential  sludge management options were identified for the  Jackson
Pike WWTP.  Each option  is discussed separately in the following paragraphs.

Jackson Pike Sludge Management Option JP-A
     Figure 5-11 presents the sludge managment schematic for option JP-A. The
option would involve  the following sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic  digestion
     •  Dewatering.

     Dewatered digested sludge would strictly be land applied in an
agricultural reuse program.
                                     5-40

-------
PRE
RAW TR
INFLUENT

LIMINARY PRIMARY AERATION SECONDARY
EATMENT CLARIFICATION CLARIFICATION










EFFLUENT

V
*>•
                                          GRAVITY
                                          THICKENING
                                          PS
                                 CENTRIFUGE
                                 THICKENING
                                 WAS


                                 THICKENED
                                 SLUDGE
                                 BLEND/STDRAGE
                                  CENTRIFUGE
                                  DEWATERING
   DIGESTED
SLUDGE HOLDING
ANAEROBIC
DIGESTION
                                     t
                                   TD LAND
                                 APPLICATION
                       FIGURE 5-11
                       JACKSON  PIKE
                       OPTION JP-A SLUDGE
                       MANAGEMENT SCHEMATIC

-------
     Based on the subjective review of this  management option,  it  was
eliminated from  further consideration.  Relying strictly on land application,
for ultimate disposal of the projected sludge quantities, lacks the
flexibility critical to maintaining a successful disposal program.  This lack
of flexibility would require an increased degree of conservatism in design and
implementation to ensure plant performance during an interruption of the
disposal process.  Furthermore, the seasonal nature of the agricultural
application program would require  substantial sludge storage facilities.
Normally, such storage facilities experience community relation difficulties
associated with  aesthetics and odors.

Jackson Pike Sludge Management Option JP-B
     Figure 5-12  presents  the sludge management schematic for option JP-B.
This option would consist of the following sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Dewatering
     •  Incineration.

     Dewatered sludge would be disposed of as follows:

     •  50 percent of the dewatered sludge would be incinerated and the ash
        product landfilled.
     •  50 percent of the  dewatered sludge would be land applied.

     The 50:50 ratio  is  approximately consistent with current Jackson Pike
disposal practices.   In  this  brief  analysis,  a comprehensive review of
alternate ratios  to determine an optimum ratio was not performed.   Since land
application is not a limiting factor and the incinerators at Jackson Pike
require some rehabilitation, a split equal to current practices appears
appropriate.
                                     5-42

-------
PRE
RAW
INFLUENT
	 (pi—.

LIMINARY PRIMARY AERATION SECONDARY
EATMENT CLARIFICATION CLARIFICATION










EFFLUENT

                                          GRAVITY
                                          THICKENING
                                          PS
Ul
                 INCINERATION
                                               CENTRIFUGE
                                               THICKENING
                                               WAS


                                               THICKENED
                                               SLUDGE
                                               BLEND/STDRAGE
CENTRIFUGE
DEVATERING
                                                   DIGESTED
                                                SLUDGE HOLDING
ANAEROBIC
DIGESTION
                     TO
                   LANDFILL
  TO LAND
APPLICATION
        FIGURE 5-12
        JACKSON PIKE
        OPTION  JP-B SLUDGE
        MANAGEMENT SCHEMATIC

-------
     Subjective screening of JP-B indicated that the option adequately
addressed the goals and objectives.   Therefore,  it will  go  through  a  more
detailed evaluation in chapter 6.

Jackson Pike Sludge Management Option JP-C
     Figure 5-13 presents the sludge management schematic  for option JP-C.
This option would consist of the following sludge processes.

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Stabilization by thermal conditioning
     •  Dewatering
     •  Incineration.

     Dewatered sludge  would be disposed of as follows:

     •  SO percent of  the dewatered  sludge would be  incinerated  and the ash
        product landfilled.
     •  50 percent of the dewatered  sludge would be  land applied.

     As previously discussed,  the 1)0:50 disposal ratio is consistent  with
current practice.   The stabilization processes  would each handle 50 percent of
the thickened sludges  produced under normal operating conditions.   The
dewatered, thermally conditioned sludge would be incinerated while  the
dewatered, digested sludge would be  land applied.

     Sludge management option JP-C was also determined by the subjective
screening to merit more detailed consideration.   It  will be evaluated further
in chapter 6.
                                     5-44

-------
            PRELIMINARY
 PRIMARY
                     AERATION
SECONDARY
RAW IKCmnC.
INFLUENT 1

\\ i i^unr

;ir i^n

I 1U1^



UL.HT

ur iUM

1 iUIN
EFFLUENT

k
                 INCINERATION

                                           GRAVITY
                                           THICKENING
                                           PS
                                                   DIGESTED
                                                SLUDGE HOLDING
                              ANAEROBIC
                              DIGESTION
                                                      THICKENED RAW SLUDGE
                                                      TO DEWATERING
                                                CENTRIFUGE
                                                THICKENING
                                                WAS


                                                THICKENED
                                                SLUDGE
                                                BLEND/STORAGE
CENTRIFUGE
DEWATERING
                                                                  THERMAL
                                                                CONDITIONING
                     TO
                   LANDFILL
  TO LAND
APPLICATION
                                      FIGURE 5-13
                                      JACKSON PIKE
                                      OPTION  JP-C SLUDGE
                                      MANAGEMENT SCHEMATIC

-------
 5.4.3.2  Southerly Sludge Management Options
     Six potential sludge management options were identified for the Southerly
 WWTP.  Each option is discussed separately in the following paragraphs.

 Southerly Sludge Management Option SO-A
     Southerly sludge management  option  SO-A is graphically depicted by the
 schematic presented in Figure 5-14.   Option  SO-A would utilize the  following
 sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Dewatering
     •  Incineration.

     Oewatered digested sludge would be incinerated and landfilled.

     Option SO-A was eliminated from further consideration for two  basic
reasons.   First,  the  option proposes to abandon the  existing compost
operations.   Such a move would forfeit  the substantial investment the city has
placed in the relatively new facilities and would substitute disposal of all
of the sludge product by landfilling in lieu of the  current practice which
reuses a portion of the sludge as soil  conditioner.   Second, option SO-A lacks
the flexibility needed to allow the  city  to  modify disposal operations subject
to equipment failures or external pressures such as public dissatisfaction or
regulatory requirements.

Southerly Sludge Management Option SO-B
     Figure 5-15 presents the sludge management schematic  for option SO-B.
The option would feature the following sludge processes:

     •  Gravity thickening  of PS
                                     5-46

-------
PRE
RAW TR
INFLUENT

•LJHINARY PRIMARY AERATION SECONDARY
EATMENT CLARIFICATION CLARIFICATION










EFFLUENT

                            GRAVITY
                            THICKENING
                            PS
                            THICKENED
                            SLUDGE
                            BLEND/STORAGE

1
-
- ~m^
CENTRIFUGE
DEWATERING


ANAEROBIC
DIGESTION
  CENTRIFUGE
  THICKENING
     VAS
                            DEVATEREB
                            SLUDGE
                            STORAGE
       INCINERATION
   TO
LANDFILL
FIGURE 5-14
SOUTHERLY
OPTION  SO-A SLUDGE
MANAGEMENT  SCHEMATIC

-------
            PRELIMINARY
              PRIMARY
            CLARIFICATION
AERATION
 SECONDARY
CLARIFICATION
rsnvr
INFLUENT











EFFLUENT

                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STORAGE
                                                    CENTRIFUGE
                                                    THICKENING
                                                       WAS
Ul
k
CENTRIFUGE
DEVATERWG
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                                                   t
                                                   TO
                                                COMPOSTING
                                                   FIGURE 5-15
                                                   SOUTHERLY
                                                   OPTION  SO-B SLUDGE
                                                   MANAGbMJLNT SCHEMATIC

-------
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Dewatering
     •  Composting.

     Ultimate sludge disposal would be accomplished through the marketing and
distribution of compost as a soil conditioner.

     The subjective evaluation eliminated option SO-B from further
consideration.   Flexibility to alter disposal operations was the critical
factor in the evaluation.   Composting the entire volume of dewatered sludge
would mean a 2 to 3 fold increase in compost product over current conditions.
If Southerly were operated in a one-plant scenario,  5 to 6 times the current
compost product would be produced.   An aggressive and  successful  marketing
program would be mandatory to locate and maintain sufficient receptors  for the
compost.  The long-term reliability of an option which relies  solely on
distribution of compost was not considered adequate  to merit more detailed
development and evaluation.

Southerly Sludge Management Option SO-C
     The sludge management schematic  for option SO-C is presented in Figure
5-16.   Southerly sludge management  option SO-C would consist of  the  following
sludge processes:

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened  sludge  storage and blending
     •  Stabilization by  anaerobic  digestion
     •  Dewatering
     •  Composting
     •  Incineration.
                                     5-49

-------
PR£
RAW TR
INFLUENT

:LIMINARY PRIMARY AERATION SECONDARY
EATMENT CLARIFICATION CLARIFICATION










EFFLUENT
	 	 i»
Ui
a
                                         GRAVITY
                                         THICKENING
                                         PS
CENTRIFUGE
DEWATERING
                                          THICKENED
                                          SLUDGE
                                          BLEND/STORAGE
ANAEROBIC
DIGESTION
                                                   CENTRIFUGE
                                                   THICKENING
                                                      WAS
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                     INCINERATION

                TO
              LANDFILL
                              TO
                          COMPOSTING
                             FIGURE 5-16
                             SOUTHERLY
                             OPTION  SO-C  SLUDGE
                             MANAGEMENT SCHEMATIC

-------
     Dewatered sludge would be disposed of as follows:
     •  75 percent of the dewatered sludge would be incinerated,  and the ash
        product would be landfilled.
     •  25 percent of the dewatered sludge would be composted and the compost
        would be distributed as a soil conditioner.
     The 75:25 ratio is approximately consistent with current Southerly
disposal practices.  The digestion facilities  would be sized to process that
portion of the sludge that would be incinerated.  The portion of the sludge
that would be composted would not receive stabilization prior to dewatering.

     Option SO-C represents current practice at Southerly when the digestion
facilities are operational.   Therefore,  subjective screening concluded that
the option merits  more  detailed development and  evaluation  in chapter 6.

Southerly Sludge Management Option SO-D
     Southerly sludge management option SO-D is graphically depicted by the
schematic presented in Figure 5-17.  Option  SO-D  would  utilize  the  following
sludge processes.

     •  Gravity thickening of PS
     •  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     •  Stabilization by anaerobic digestion
     •  Dewatering
     •  Composting
     •  Incineration.

     Ultimate disposal of the sludge would be  accomplished through the
following disposal methods:

     •  25 percent of the sludge would be  dewatered,  composted,  and distri-
        buted as a soil conditioner.
                                     5-51

-------
            PRELIMINARY
PRIMARY
       AERATION
  SECONDARY
RAW
INFLUENT

u.n i ill—









wi_nr

^ir i\,n

                                                                                    EFFLUENT
ro
                     CENTRIFUGE
                     DEVATERING
                 TO
              LANDFILL
                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STORAGE
       ANAEROBIC
       DIGESTION
                                      CENTRIFUGE
                                      THICKENING
                                         VAS
                                          DEVATERED
                                          SLUDGE
                                          STORAGE
                                                   t
    TO
   LAwn
APPLICATION
    TO
COMPOSTING
FIGUEE 5-17
SOUTHERLY
OPTION SO-D SLUDGE
MANAGEMENT SCHEMATIC

-------
     •  25 percent of the sludge would be digested, dewatered, and land
        applied.
     •  50 percent of the sludge would be digested, dewatered, incinerated,
        and landfilled.
     Option SO-0 meets  the  goals  and  objectives  of  the  subjective screening.
The option offers continuation of the existing incineration and composting
processes at Southerly  and  introduces land  application  as  a disposal process.
The city has indicated there is adequate acreage suitable for land application
within an economically  feasible distance of the  plant.  Option SO-D  was
advanced for further development  and  evaluation  in  chapter 6.

Southerly Sludge Management Option SO-E
     Figure 5-13 presents the sludge management  schematic  for Option SO-E.
Southerly sludge management option SO-E would consist of the  following sludge
processes:

     *  Gravity thickening PS
     *  Centrifuge thickening of WAS
     •  Thickened sludge storage and blending
     *  Stabilization by anaerobic digestion
     •  Dewatering
     •  Composting.

     Dewatered sludge would be disposed of  as follows:

     •  50 percent would be composted  and distributed as a soil conditioner.
        Sludge sent to compost would not go through the digestion process.
     •  50 percent would be land applied as a fertilizer to agricultural
        acreage within a reasonable distance from the plant.

     Based on the subjective evaluation option SO-E was  eliminated from
further consideration.   The  reliability of  utilizing only compost distribution
and land application as  ultimate disposal options did not appear reasonable.
                                     5-53

-------
            PRELIMINARY
              PRIMARY
            AERATION
SECONDARY
INFLUENT











EFFLUENT

fc
CENTRIFUGE
DEVATERING
                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STORAGE
ANAEROBIC
DIGESTION
                                                    CENTRIFUGE
                                                    THICKENING
                                                       WAS
                                          BEWATERED
                                          SLUDGE
                                          STORAGE

                                      TO
                                     I AND
                                  APPLICATION
                               TO
                           COMPOSTING
                             FIGURE 5-18
                             SOUTHERLY
                             OPTION SO-E SLUDGE
                             MANAGEMENT SCHEMATIC

-------
The plant currently practices incineration and relies heavily on incineration
and landfilling of the ash for disposal.  Furthermore, it is critical that the
plant have a  disposal  method that is completely within their control, i.e.,
not influenced by sludge quality, weather, market demand, public perception or
other external  pressures.

Southerly Sludge Management Option SO-F
     Figure 5-19 presents the sludge management  schematic  for Option  SO-F.
Ths sludge management  system would consist of the following processes:

     •  Gravity thickening PS
     •  Centrifuge thickening WAS
     •  Thickened sludge storage and blending
     •  Dewatering
     •  Composting
     •  Incineration.

     Ultimate disposal of the sludge would be accomplished through one of the
following disposal methods:

     •  SO percent would be composted and distributed as a soil conditioner.
     •  SO percent would be incinerated and landfilled.

     Option SO-F is similar to option SO-C with  the exception that digestion
is not provided.   The evaluation  of option SO-F was  prompted due to the fact
that digestion prior to incineration has normally not proven to be cost-
effective.  Although digestion diminishes the  amount of  solids  to be handled
in subsequent processes,  the heat content of digested sludge is significantly
reduced.  Furthermore,  digested sludge  tends to be more  difficult to dewater
than combined raw sludges.  These factors cause digested sludge to be  more
difficult,  and consequently more expensive on a unit basis (i.e.  dollars  per
dry ton),  than raw sludges to incinerate.  Since  the Southerly  plant has  a
portion of the required digestion facilities and  adequate incineration
                                     5-55

-------
            PRELIMINARY
            TREATMENT
              PRIMARY
            CLARIFICATION
                                                      AERATION
 SECONDARY
CLARIFICATION
RAW
INFLUENT










i
EFFLUENT

                                          GRAVITY
                                          THICKENING
                                          PS
                                          THICKENED
                                          SLUDGE
                                          BLEND/STORAGE
                                                    CENTRIFUGE
                                                    THICKENING
                                                       WAS
0\
CENTRIFUGE
DEWATERING
                                          DEWATERED
                                          SLUDGE
                                          STORAGE

                 TO
              LANDFILL
                               TO
                           COMPOSTING
 FIGURE 5-19
 SOUTHERLY
 OPTION  SO-F SLUDGE
 MANAGEMENT SCHEMATIC

-------
facilities in place, the cost effectiveness of digestion prior to incineration
is less dependent on capital cost than an evaluation where these facilities

are not  in place.   This option will be  evaluated  further  in  chapter 6.


5.5  SUMMARY OF ALTERNATIVES AND OPTIONS

     Alternatives for comprehensive wastewater management that have advanced

for further evaluation in chapter 6 include the following:


     •  One-plant (all treatment at Southerly)
     •  Two-plant (solids handling at Jackson Pike and Southerly)

     •  Two-plant (all solids handling at Southerly)


     The following  options for treatment plant components have been advanced

for further evaluation in chapter 6.


     •  Interconnector/Headworks
        -  A/A-1 (additional pumping, force mains, and headworks)
        -  B/B-1 (extension of gravity sewer and separate headworks)
        -  S/B-2 (extension of gravity sewer and entirely new headworks)

     •  Biological  Processes
        -  Semi-aerobic
        -  Trickling Filter/Activated Sludge (TF/AS)

     *  Sludge Management
        -  JP-B (PS thickening,  WAS thickening, anaerobic digestion,
           dewatering, land application, and incineration/landfill)

        -  JP-C (PS thickening,  WAS thickening, anaerobic digestion,  thermal
           conditioning!  dewatering, land application, and incineration/
           landfill)

        -  SO-C (PS thickening,  WAS thickening, anaerobic digestion,
           dewatering, composting, and incineration/landfill)

        -  SO-D (PS thickening,  WAS thickening, anaerobic digestion,
           dewatering, composting, land application, and incineration/
           landfill)

        -  SO-F (PS thickening,  WAS thickening, dewatering, composting, and
           incineration/landfill)


     Table 5-2 summarizes each of the wastewater management alternatives with
their  respective component  options.


                                     5-57

-------
TABLE 5-2 SUMMARY OF ALTERNATIVES AND  OPTIONS
WASTEWATER
MANAGEMENT
ALTERNATIVE
ONE-PLANT
TWO-PLANT
TWO-PLANT ONE SOLIDS

COMPONENT
INTERCONNECTOR/HEADWORKS
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
BIOLOGICAL PROCESS
SLUDGE MANAGEMENT
OPTION
A/A-1
B/B-1
B/B-2
SEMI- AEROBIC
TF/AS
SO-C
SO-D
SO-F
SEMI-AEROBIC
TF/AS
SO-C
SO-D
SO-F
JP-B
JP-C
SEMI-AEROBIC
TF/AS
SO-C
SO-D
SO-F
                  5-58

-------
                CHAPTER 6.  DETAILED ANALYSIS OF ALTERNATIVES
     This chapter presents a detailed evaluation of the two comprehensive
wastewater  management alternatives:  the one-plant and two-plant alternatives.
Section 6.1 describes the engineering evaluation, while Sections  6.2 through
6.5 present the environmental  evaluations.  In  Section 6.6, the engineering
and environmental evaluations of the one-plant and two-plant alternatives are
summarized, and a recommended comprehensive alternative is identified.

     Previously in chapter 5 three basic components of the comprehensive
alternatives were identified.  These three components  are:

     •  Interconnector/headworks
     •  Biological process
     •  Solids handling.

     Also in chapter 5, the feasible options that fulfill the components were
identified and subjected to a preliminary screening.   In Section  6.1 -
Engineering Evaluation, the options for the basic components that advanced
from the screening in chapter 5 are evaluated  with respect to technical
criteria consisting of cost, reliability, flexibility,  implementability, and
operational convenience.   The optimum option which fulfills each component is
selected for both the one-plant and two-plant alternatives.  After the  optimum
options for each component are  identified,  the comprehensive one-plant and
two-plant alternatives are defined  and evaluated with  respect to the technical
evaluation criteria.

     The environmental evaluation addresses the  comprehensive system
alternatives.   This  evaluation  considers physical,  biological,  and human
environmental criteria.  These  criteria were derived from the data collection
effort documented in chapter 2.  Physical criteria include:   water,  air
quality,  and prime agricultural land.  Biological criteria include:
terrestrial and aquatic biota as well as threatened and endangered species.
                                       6-1

-------
 The  human or man-made environmental criteria include:   land use, noise,
 energy, economics,  transportation,  and historic and archeologic resources.
 Indirect  environmental  consequences such as  induced growth are  also discussed.

 6.1.  ENGINEERING EVALUATION
     In the  engineering evaluation,  technical criteria are applied to evaluate
 the options  for the components that formulate an alternative,  as well as to
 evaluate  comprehensive  alternatives.  First, the technical evaluation is
 applied to identify the optimum options for the components.   Then,  components
 are assembled  into  the one-plant and two-plant comprehensive alternatives and
 a second  technical evaluation is performed.

     In evaluating planning alternatives,  it is usually necessary to evaluate
 the comprehensive alternatives due to the  interrelationships  between the
 components which formulate  the alternatives.  For example, where options for
 the biological process component produce substantially different quanities of
 sludge,  the  solids handling evaluation must be coupled with the biological
 process evaluation to determine the optimum alternative.   However,  based on
 the options  for the components that have been advanced from chapter 5 such an
evaluation process is not necessary.   Selection of the optimum option for the
 Interconnector/headworks does not influence the subsequent liquid and sludge
 treatment components.  The biological process options  that have been advanced
 will yield approximately the  same  quantity of sludge.   Similarly the solids
handling options remaining under consideration do  not  exhibit  significantly
different impacts on other components.  Consequently,  the individual
components will be evaluated independently and an optimum option for each
component will be identified  for both  the one- and two-plant alternatives.

     The technical  criteria applied in the engineering evaluation are
 identified and defined below.

     *  Cost - The  lowest total present worth cost.
     •  Reliability - Ability  to treat the projected wasteload and continuously
        discharge an effluent  capable of meeting NPDES permit standards.
                                      6-2

-------
     *  Flexibility - Ability to change and meet differing conditions.
     •  Implementability - Ease of implementation.
     *  Operational Convenience - Ease of operation and maintenance.

     Cost is an objective criteria with the differences in total present worth
establishing the ranking of component options and comprehensive alternatives.
The remaining  four criteria are subjective criteria.  A brief narrative
discusses how  the component options and alternatives compare with the
subjective criteria.

6.1.1   Interconnector/Headworks Component
     This section provides an evaluation of the Interconnector and headworks
components of  one-plant and two-plant alternatives.

6.1.1.1  One-Plant
     As discussed in chapter 5,  no work would be required at the Jackson Pike
headworks under the one-plant alternative because  the  plant  would be phased
out of service and the flow tributary to Jackson Pike would be diverted to the
Southerly WWTP via the Interconnector Sewer.   Completion of the north end of
the Interconnector would be required to convey the flows from Jackson Pike to
Southerly.

     The one-plant alternative also requires  that  the capacity of the south
end of the Interconnector Sewer and the Southerly headworks be expanded.
chapter 5 presented two options for expanding the south end of the
Interconnector and three options for expanding the capacity of the Southerly
headworks.  Due to the interrelationship between the headworks and the
Interconnector the headworks options  were developed  based on the
Interconnector options.  Three potential  Interconnector/headworks combinations
are identified and described below.   They include  the  following:
                                       6-3

-------
         Option A/A-l -  Increase the capacity of the south end of the
         Interconnector  from 60 MGD (o 150 MGD by constructing a new pumping
         facility and by  installing one new 48-inch and one new 36-inch force
         main from  the pumping  facility to the Southerly headworks.  Increase
         the  capacity of  the oxisting Southerly headworks from 170 MGD to 231
         MGD  by adding additional  pumps,  screens, and grit chambers.

         Option B/8-1 - Extend the 156-inch gravity Interconnector Sewer to the
         Southerly  WWTP.   Use  four 78-inch pipes for the Scioto River crossing.
         Construct  new 150 MGD headworks  which include pumping, screening, and
         grit removal for the Interconnector  flows.   Use the existing headworks
         for  preliminary treatment of flow from the Dig Walnut Interceptor
         Sewer.

         Option B/B-2 - Extend the 156-inch gravity Interconnector Sewer to the
         Southerly  WWTP.   Use  four 78-inch pipes for the Scioto River crossing.
         Construct  entirely new headworks rated at a capacity of 231 MGD for
         preliminary treatment of flows from the Interconnector Sewer and the
         Big Walnut Interceptor Sewer.   The new headworks will include a mixing
         chamber, screening, pumping, and grit removal.   Demolish the existing
         headworks.
     Table 6-1 presents capital, annual O&M,  and  total  present worth costs for

each of the options.


                  TABLE 6-1.  INTERCONNECTOR/HEADWORKS  COSTS


                             Capital      Annua1  O&M    Total Present Worth

Option A/A-l               $15,239,000    $1,771,000        $31,064,000

Option B/B-1               $19,282,000    $1,289,000        $30,279,000

Option B/B-2               $25,382,000    $1,169,000        $34,928,000


     Option B/8-1 exhibits the lowest present worth cost.  However,

practically speaking the present worth of A/A-l is equal to B/B-1.   The

gravity sewer options (B/B-l and B/B-2)  are more  reliable than the force  main

option (A/A-l) since there is less chance that the gravity sewer will rupture.

Furthermore, failure of the gravity sewer normally results in infiltration to
the conduit, while a rupture of the force mains would cause exfiltration  to
the environment.  In addition,  the gravity sewer  does not rely on the
                                      6-4

-------
operation of a pumping  facility  to  perform.  The pumping facility causes the
force main option to be considered more difficult to operate and maintain and
also somewhat less reliable due  to  the dependency on its pumps.

     With respect to flexibility to adapt to higher flows both the gravity
sewer and the pump station/force main  are considered similar.  Both would be
sized to handle the projected peak  flows  and would require  modifications to
increase capacity.

     The force mains, on the other hand,  will not require as deep of an
excavation as the gravity sewerj and therefore, may be easier to implement.
Also, the force  main option (A/A-1) and  the gravity option (B/B-2) only have
one headworks which would be easier to operate and maintain than the two
separate headworks as proposed under option B/B-1.

     Based on the cost and reliability of the gravity sewer, Option B/B-1 is
the recommended  Interconnector/headworks component for the one-plant
alternative.

6.1.1.2  Two-Plant
     The existing Jackson Pike headworks provide screening and pumping only.
Preliminary screening and grit removal facilities are  located at  the Sewer
Maintenance Yard upstream  of the Jackson Pike headworks on the O.S.I.S.   These
facilities,  however,  provide pretreatment only for flows entering the plant
through the O.S.I.S. Interceptor.

     Due to the fact  that flows  from the Big Run Interceptor are not provided
with grit removal and due to the  age of the  existing equipment,  it is
recommended that entirely new headworks be constructed at Jackson Pike under
the two-plant alternative.   The new headworks would include screening,
pumping, and aerated grit removal,  and they would be located on the Jackson
Pike plantsite.
                                       6-5

-------
      As  discussed  in  chapter  5,  the  peak  flow  to the Jackson Pike WWTP will be
 limited  to 100  MGD.   The 2008 projected peak process flow  tributary to Jackson
 Pike  is  131  MGD.   Therefore,  the north end of  the Interconnector would require
 completion under the  two-plant alternative to  allow flows  in excess of 100 MGD
 to  be transported  to  the Southerly WWTP.

      The pumping station and  force mains  at the south ,end  of the
 Interconnector  Sewer  (i.e.  tributary to Southerly) are rated at a capacity of
 60  MGD.  These facilities are adequate to handle the 2008 flows from the Grove
 City  connection which are  projected  to be 6 MGD as  well  as the 31 MGD that
 would be diverted  from Jackson Pike  under peak conditions.  Therefore, no
 expansion  of  the conveyance system  is  required.

      The existing  Southerly headworks, rated at a capacity of 170 MGD, is
 capable of handling the 31 MGD from  Jackson Pike in addition to Southerly's
 projected peak  flow of 99  MGD.  Therefore, no  expansion is required at the
 Southerly headworks under  the two-plant scenario.

 6.1.2  Biological  Process Component
      This section  provides an evaluation of the serai-aerobic and trickling
 filter/activated sludge biological process options for the Jackson Pike and
 Southerly WWTPs under the  one-plant  and two-plant alternatives.  The detailed
documentation of the biological process evaluation is contained in Appendix C
entitled Briefing  Paper No. 3 - Biological Process  Selection.

6.1.2.1  One-Plant
     The semi-aerobic  and  trickling filter/activated sludge processes were
evaluated for biological treatment at the  Southerly  WWTP under  the one-plant
alternative.
                                      6-6

-------
     The semi-aerobic process  is similar  to  the conventional activated sludge
process which currently exists at the Southerly WWTP.  Existing basins could
be modified  to operate in the semi-aerobic mode by installing two additional
baffles in the first bay of each aeration basin and by installing an internal
mixed  liquor recirculation system  in each basin.  In addition to modifying the
existing basins,  two new basins would be added to the Center Train,  and a new
East Train would be built with nine  basins.

     The trickling filter/activated sludge process would utilize the existing
aeration basins in the West and Center Trains.  Four trickling filters  would
be needed for the  existing West and Center Trains; and  a  new East  Train would
be constructed with two trickling  filters and  four aeration basins.

     Circular clarifiers are  recommended for the Southerly WWTP under either
biological process option due to the  low nitrification rates which require
rapid sludge return to maintain a high mixed liquor suspended solids concen-
tration (MLSS - 3500 mg/1);  and due to the historic rising sludge  observed as
denitrification occurred in the rectangular final clarifiers.   The existing
rectangular clarifiers and associated sludge  removal equipment cannot maintain
the necessary mixed liquor concentrations in the return sludge or  provide the
proper sludge removal rate.   Circular clarifiers  provide  more rapid sludge
removal than rectangular clarifiers,  thereby lessening the potential for
denitrification in the final  clarifier.  New  circular clarifiers would  be
equipped with helical scraper arm sludge removal mechanisms to ensure high
rate sludge removal without denitrification.

     Under the  one-plant alternative,  six  new clarifiers  would be  required for
the existing Center and West  Trains and four new circular clarifiers would be
required for the  new East Train.
                                      6-7

-------
      Table  6-2  provides  the capital, annual O&M, and total present worth costs
 for the  trickling filter/activated sludge and semi-aerobic process options
 under the one-plant scenario.

                TABLE 6-2.  ONE-PLANT BIOLOGICAL PROCESS COSTS

                                                                     Total
                                      Capital      Annual O&M    Present Worth
 Trickling Filter/Activated Sludge   $87,462,000    $2,773,000     $109,571,000
 Semi-Aerobic                        $81,995,000    $3,148,000     $107,958,000

      The semi-aerobic process exhibits  the  lowest  total  present  worth  cost.
 However, practically speaking the present worth cost of the trickling
 filter/activated sludge  process is equal to the present worth cost of the
 semi-aerobic  process.

      From a reliability  standpoint, the semi-aerobic process is more reliable
 than  the trickling  filter/activated sludge process.  Doth processes have the
 ability to select against filamentous organisms which cause bulking and both
 processes are capable of providing nitrification.   However,  the semi-aerobic
 process is considered more reliable due to  the fact that more process control
 flexibility is inherent  in the process.   The ability to maintain the initial
 bays  of an aeration basin in either an anaerobic,  anoxic, or aerobic
 conditions through mixing and aeration and the ability to return mixed liquor
 through a recycle loop enhance the process1  ability to  perform and meet
 effluent limits.

     The trickling filter/activated sludge process would be subject to an
 adverse environmental review due  to its resultant odor and pests.  Trickling
 filters have been cited in odor complaints particularly under conditions of
high organic loadings.   In addition,  fly larvae and flies breed on these
 filter media resulting in nuisance complaints.  Control of odors and flies
 requires covering the trickling filters, installing a positive ventilation
                                      6-8

-------
 system,  and  scrubbing  the  off-gases.  This would add significant capital and
 O&M costs  to the system and may result in reduced efficiency during the summer
 months.

     The trickling  filter/activated  sludge process would  also be very
 difficult  to implement in  that it would require major restructuring of the
 conduits between  the existing  primary clarifiers  and  aeration basins.  There
 is  inadequate area  between these  two processes  for  the  trickling  filters.
 Therefore, they would  have to  be  located some distance  from  the proceeding and
 subsequent treatment process, and primary effluent flows would have to be
 pumped  to  them.

     Due to  the fact that  there is increased reliability with the semi-aerobic
 process and due to the  problems associated  with  implementing the trickling
 filter/activated sludge process, the semi-aerobic process is recommended as
 the  preferred biological process for  the Southerly one-plant alternative.

 6.1.2.2  Two-Plant
     The semi-aerobic  and  trickling  filter/activated sludge processes were
 evaluated  for Southerly and Jackson Pike under the two-plant alternative.
Table 6-3 presents  the capital, O&M, and total present worth costs for these
 processes under the two-plant  alternative.

                TABLE 6-3.  TWO-PLANT BIOLOGICAL PROCESS COSTS
                                                                     Total
                                      Capital     Annual  O&M    Present  Worth
 Southerly
Trickling Filter/Activated Sludge   $38,732,000     $1,491,000     $ 51,034,000
Semi-Aerobic                        $32,805,000     $1,638,000     $ 46,808,000
Jackson-Pike
Trickling Filter/Activated Sludge   $41,140,000     $1,804,000     $ 56,311,000
Semi-Aerobic                        $31,193,000     $1,794,000     $ 46,766,000
                                      6-9

-------
      The semi-aerobic process exhibits  the lowest  total  present worth cost for
 Jackson Pike and  Southerly  under  the  two-plant  scenario.  The cost difference
 between the semi-aerobic process and trickling  filter/activated sludge process
 is approximately  10  percent for  the Southerly plant and  20 percent for the
 Jackson Pike plant.   The evaluation with  respect to the  reliability and
 impleraentatiblity previously discussed  under the one-plant analysis holds true
 in comparing the  options for the  two-plant alternative.

      Since  the semi-aerobic process is  10  to 20 percent  less costly and is
 considered  more reliable than the trickling filter option, the semi-aerobic
 process  is  selected as the optimum biological process option for Jackson Pike
 and Southerly under  the  two-plant alternative.

      Six circular clarifiers are required for the Southerly WWTP under the
 two-plant scenario.   Circular clarifiers are recommended for Southerly under
 the two-plant scenario for  the same reasons that were given for the Southerly
 one-plant scenario.  These  reasons include a high mixed  liquor suspended
 solids concentration, the need to rapidly return activated sludge to
 increase nitrification rates, and the need to maintain a  minimum sludge
 blanket  in  the final  clarifiers to prevent  denitnfixation.

     At  Jackson Pike  the required mixed liquor suspended solids concentration
 is  lower due  to higher observed nitrification rates and overpumping of the
 final clarifiers  is  not  necessary since rising sludge has not been a problem.
 Therefore,  the continued use of the existing rectangular clarifiers is
 recommended along with the  addition of two new rectangular clarifiers for
 final settling.

 6.1.3  Solids Handling
     This section presents an evaluation of the  sludge management options
 developed in chapter 5 for  the one-plant and two-plant alternatives.   Appendix
 B entitled Briefing Paper No. 2 - Solids Handling,  provides detailed
documentation of the  evaluation.
                                      6-10

-------
     The evaluations performed  for the sludge management alternatives in the
following  sections are based on the use of centrifuges for dewatering.  The
Revised Facility Plan Update (RFPU),  prepared  in September of 1985,  recom-
mended  the continued use of centrifuges for dewatering.  Subsequently, in a
document prepared  in December of 1986, entitled Preliminary Design Evaluation
of Sludge Dewatering, the city recommended installing diaphragm plate and
frame presses  (DPF) for dewatering.   Following the review of the planning and
preliminary design documents, an evaluation of sludge dewatering was performed
as part of the SEIS.

     The results of  the SEIS evaluation (Appendix B) concluded that
centrifuges were the cost-effective dewatering  option.  In the SEIS
evaluation, the total present  worth cost of the centrifuge option is 7 percent
lower than the cost of the DPF  option.  The conclusions reached in this
evaluation  differed from those  developed in the planning and preliminary
engineering documents for several reasons.

     •  A higher capacity rating for the centrifuges was utilized.
     *  The operating costs  associated with the  dewatering options and the
        incineration process differed.
     •  A nominal cost for ash disposal was incorporated in the analysis.

     Consequently,  the following evaluation of sludge management options is
based on the continued use of centrifuges  for dewatering.

6.1.3.1   One-Plant
     Under  the one-plant alternative (all  treatment at Southerly) three
options  were retained from chapter 5. They include the following:

     •  SO-C - PS thickening,  WAS thickening,  digestion,  dewatering,
        composting, and incineration/landfill.
     •  SO-D - PS thickening,  WAS thickening,  digestion,  dewatering,
        composting, land application, and incineration/landfill.
                                     6-11

-------
      •   SO-F  - PS  thickening, WAS thickening, dewatering, composting, and
         incineration/land fill.

      Table 6-4 presents  the capital, annual O&M, and total present worth costs
 for  each option.

           TABLE 6-4.  COST COMPARISON OF SLUDGE MANAGEMENT OPTIONS
                            (Southerly One-Plant)

                             Capital      Annual O&M    Total Present Worth
Option SO-C                $45,770,000    $6,080,000        $89,590,000
Option SO-D                $45,770,000    $6,230,000        $90,710,000
Option SO-F                $40,700,000    $7,110,000        $92,440,000

     All options exhibit approximately the same present worth costs, with SO-F
the highest present worth being only 3 percent higher than SO-C which has the
lowest present worth cost.

     Option SO-D with composting, land application, and incineration provides
more flexibility and reliability in final disposal options than SO-C and SO-F.
Option SO-C and SO-D provide more flexibility and reliability than SO-F with
respect to stabilization of the sludge through digestion since option SO-F
does not include digestion.  Based on reliability and flexibility, SO-D is the
recommended option for Southerly under the one-plant alternative.

6.1.3.2  Two-Plant
     The three sludge management options retained from chapter 5 for Southerly
under the two-plant alternatives are the same as those which were retained
under the one-plant alternative.  Table 6-5 provides the capital, annual O&M,
and total present worth costs of SO-C,  SO-D,  and SO-F under the two-plant
alternative.
                                      6-12

-------
            TABLE  6-5.   COST  COMPARISON OF  SLUDGE MANAGEMENT OPTIONS
                             (Southerly Two-Plant)


                              Capital       Annual O&M    To t a1  Pre senEjtforth

 Option  SO-C               $15,220,000    $3,260,000         $39,080,000

 Option  SO-D               $15,220,000    $3,340,000         $39,680,000

 Option  SO-F               $14,570,000    $3,940,000         $42,770,000


      Similar  to the costs  for the one-plant alternative, options SO-C and SO-D

 can  be  considered equal.   However,  SO-F is approximately 9  percent higher than

 SO-C.


     As with  the  Southerly one-plant alternative, option SO-D  is recommended

 as the  preferred  Southerly two-plant sludge management scheme.  Option SO-D

 provides  three reliable disposal paths  and adequate flexibility.


     Two  options  were retained from chapter 5 for Jackson Pike under the two-

 plant alternative.  They include the following:


     *  JP-B - PS thickening, WAS thickening, anaerobic digestion, dewatering,
        land application,  and incineration/landfill.

     •  JP-C - PS thickening, WAS thickening, anaerobic digestion, thermal
        conditioning, dewatering, land  application, and incineration/landfill.


     Table 6-6 provides the capital, annual O&M, and total  present worth costs
 for these options.


           TABLE 6-6.  COST COMPARISON OF SLODGE MANAGEMENT OPTIONS
                           (Jackson Pike Two-Plant)


                             Capital      Annual O&M    Total Present Worth

Option JP-B                $23,830,000    $3,070,000        $45,930,000

Option JP-C                $25,410,000    $3,770,000        $52,700,000
                                      6-13

-------
      Option  JP-B,  which provides  for  digestion, dewatenng,  and a 50:50 split
 of  sludge  to land  application and incineration/landfill, has the lowest total
 present  worth cost.  This option is approximately 15 percent less costly than
 JP-C  which proposes to  retain the thermal conditioning units for processing a
 portion  of the sludge.

      Option  JP-C provides more  flexibility  in  that  sludge  can be stabilized
 through  digestion  or thermal conditioning.  However, the thermal conditioners
 are more costly and difficult to operate and maintain  than the  digesters.

      Due to the lower present worth cost of option JP-B and the greater ease
 of operation and maintenance of digestion, option JP-B is the recommended
 sludge management  scheme for Jackson  Pike.

 6.1.3.3  Two-Plant Liquid Treatment/One-Plant Solids Treatment
     A third system configuration which was conceptually identified in the
 SEIS  involved  providing liquid  treatment  facilities at two plants (i.e.,
 Southerly  and Jackson Pike) and  consolidating solids processing facilities at
 one-plant  (i.e., Southerly).  Currently, a  single  8-inch sludge transfer
 pipeline links Jackson  Pike and Southerly.   Tins sludge transfer pipeline
 prompted the  identification of the two-plant liquid treatment/one-plant solids
 treatment  alternative.

     The two-plant liquid treatment/one-plant solids treatment alternative was
 eliminated from consideration following the analysis of the one- and  two-plant
 solids options. In the  previously  presented section, the recommended one-
plant solids option,  SO-D,  was shown to have a  present  worth cost of
$90,710,000.   Similarly, the recommended  two-plant solids  options (i.e.,
Southerly SO-D and Jackson Pike  JP-B)  exhibited a  total present  worth cost of
$85,610,000.   Based on these present worth costs,  it is approximately
6 percent less costly to maintain solids processing operations at both
Southerly and Jackson Pike if both facilities are providing liquid treatment.
                                    6-14

-------
     The 6 percent difference is based  strictly on  required  facilities  for
processing and disposal.  This margin would widen if an appropriate  level of
reliability and redundancy in the sludge conveyance system is added  to  the
analysis.  The existing, single 8-inch  pipeline would not be sufficient  to
allow consolidation of sludge processing operations.  At a minimum,  a second
parallel pipeline would be necessary to provide redundancy.  Potentially a
third pipeline may be appropriate, allowing one dedicated pipeline for
transfer of primary sludge, one dedicated pipeline  for transfer of waste
activiated sludge, and one dedicated stand-by pipeline.  Providing the
necessary redundancy in the sludge conveyance system would cause the option
for consolidating sludge processing at Southerly to be from  10 to 15 percent
more costly than maintaining separate facilities at each plant.  As  a result,
the two-plant liquid treatment/one-plant solids treatment alternative was
eliminated from further consideration.

6.1.4  One—P1antvs. Two-P1a n t s
     This section summarizes the recommended component options for the one-
plant and two-plant alternatives based on the evaluations previously
presented.  After defining the recommended components for the one-plant and
two-plant alternatives, a technical evaluation is conducted.

6.1.4.1  Required Facilities
     The previous sections evaluated options for Interconnector/headworks,
biological process,  and solids management components.   Recommendations on
these components were made for each plant alternative based on cost,
reliability,  flexibility,  implementability,  and operational ease.

     The recommendations for the Southerly One-Plant Alternative include the
following:

     •  Complete the north end of the Interconnector Sewer.   Construct a flow
        diversion chamber.
     •  Extend  the 156-inch gravity Interconnector  Sewer  to the Southerly
        WWTP.   Use four 78-inch  pipes for the  Scioto River  crossing.
                                      6-15

-------
     *  Construct new  150 MGD headworks at Southerly to handle Che flows from
        the Interconnector.  Use  the existing 170 MGD headworks for the Big
        Walnut Interceptor flows.

     •  Adopt the semi-aerobic process as the method of biological treatment.

     •  Upgrade and expand the solids handling facilities to include gravity
        thickening of PS, centrifuge thickening of WAS, anaerobic digestion,
        centrifuge dewatenng, incineration/landfill, composting, and  land
        application.


     Figure 6-1 provides a site layout, and Table 6-7 presents the sizes of
the required facilities for the Southerly One-Plant Alternative.


     The recommendations for the Southerly Two-Plant Alternatives include the

following:


     •  Adopt the semi-aerobic process as the method of biological treatment.

     •  Upgrade and expand the solids handling facilities to include gravity
        thickening of PS, centrifuge thickening of WAS, anaerobic digestion,
        centrifuge dewatering, incineration/landfill, composting, and  land
        application.


     Figure 6-2 provides a site layout of the Southerly Two-Plant Alternative,

and Table 6-8 presents the sizes of the required facilities.


     The recommendations for the Jackson Pike Two-Plant Alternative include
the following:


     •  Complete the north end of the Interconnector Sewer.   Construct a flow
        diversion chamber.

     •  Construct new headworks rated at a capacity of 100 MGD which include
        screening,  pumping,  and grit removal.

     •  Adopt the semi-aerobic process  as the method of biological treatment.

     •  Upgrade and  expand  the solids handling facilities to include gravity
        thickening  of PS,  centrifuge thickening  of WAS,  anaerobic digestion,
        incineration/landfill,  and land application.
                                      6-16

-------
                                                                                          ELECTRICAL SWITCHING STATION
          CENTRIFUGAL
               BUILDING

  SLUDGE STORAGE BUILDING
      INCINERATION •
       BUID&IG
ELECTRICAL SNTOWG STATION
              OEWATEKWO
               BULDM6
 I
>-•
•sj
            GRAVITY
           TH OWNERS
v,
    i    i

                                                                       INFLUENT SPUTTER CHAMBER
                                                                                            ' AOWNISTRATION>
                                                                                                BULDINC
                                                                    SCKSM BUILDING
                                      HIGH RATE DIGESTERS
                                                                                                 PRWARYACHAUBER
                                                                                                 •SETTUNGl   \
                                db
                                 PRMARY
                                  SLUDGE
                                 SPUTTER
                                 CHAUBER
                                                                                                      AERATION CONTROL
                                                                                                          BUILDING
                ELECTRICAL SWTCHWG STATION
                                                                               AERATION
                                                                               CON'IROL
                                      EFFUJEKT
                                      CONTROL
                                      BULDtNO
                                                                                                                                   MIXED UQUOR
                                                                                                                                   CONTROL BOX
                                                                                                                                    O£CTRICAL SWflTCHWO
                                                                                                                                         STATION
                                                                                                                                      tflXEO UQUOR
                                                                                                                                    SPUTTER CHAMBER
                                                                                       1~~"1 EXISTING FACILITIES
                                                                                             NEW CONSTRUCTION
                                                                                             ABANDONED FACILITIES

                                                                                       FIGURE  6-1

                                                                                       SOUTHERLY  ONE-PLANT SITE LAYOUT

-------
                                   TABLE 6-7.  SOUTHERLY ONE-PLANT REQUIRED FACILITIES
  Component

  INTERCONNECTOR
  HEAOWORKS
  PREAERATION
a*
t
00 PRIMARY SETTLING
  AERATION
  FINAL SETTLING
  CHLORINATION
  POST AERATION
  EFFLUENT PUMPING
Existing Facilities

7 miles of 150-156 inch gravity sewer.
60 MOD pump station, 48-inch force main, and
30-inch force main connecting the south end
of the gravity sewer to Southerly.
170 MGD screening, pumping, and grit
removal.
Eight tanks at 112.7 ft x 26 ft x 15.5 ft SWD
Four tanks at 80 ft x 165 ft x 10 ft SWD
Four tanks at 100 ft x 170 ft x 10 ft SWD

Ten tanks at 26  ft  x 900  ft  x 15  ft  SWD
Four tanks at 89 ft x 170 ft x 12.5 ft SWD
Four tanks at 104 ft x 180 ft x 10.5 ft SWD

One earthen chlorine contact basin at 260 ft x
260 ft x 7 ft SWD
Effluent control building with pumping capacity
of 170 MGD.
Required Facilities

Complete north end to connect with Jackson
Pike.  Cxtend 156-inch interceptor to
Southerly.  Use four 78-inch pipes for river
crossing.  Abandon existing pump station
and force mains.

Use existing 170 MGD headworks for Big
Walnut flows.  New 150 MGD screening,
pumping, and grit removal for Interconnector
flows.

Four new tanks at 112.7 ft x 26 ft x
15.5 ft SWD; Rehab existing eight tanks.

Four new tanks at 150 ft dia. x 15 ft SWD;
Rehab existing eight tanks.

Eleven new  tanks at 26 ft x 900 ft x
15 ft SWD;  Rehab existing ten tanks.

Ten new tanks at 200 ft dia. x 15 ft SWD;
Demolish existing eight tanks.

Two tanks at 81 ft x 200 ft x 10 ft SWD;
to include  mixers, chlorinators,
evaporators, and sulfinators.
Abandon existing basin.

Final pass  of chlorine contact tanks;
Fine bubble diffusers.

New effluent control building with
pumping capacity of 231 MGD.
Demolish existing building.

-------
                             TABLE 6-7.  SOUTHERLY ONE-PLANT REQUIRED FACILITIES (CONT.)
Component

GRAVITY
  THICKENING PS
Existing Facilities
CENTRIFUGE
  THICKENING WAS        Four at 250 gpm, 1250 Ib/hr

ANAEROBIC DIGESTION     Six 85 ft dia. x 25 ft SWD units


CENTRIFUGE DEWATERING   Six 1000 Ib/hr units
DEWATERED SLUDGE
  STORAGE

COMPOSTING

INCINERATION
One 400 cy bin
Facility - 120 wet ton/day at 20% solids

Two units at 150 wet ton/day each.
Two units at 260 wet ton/day each.
Required Facilities

Two new units at 85 ft dia. x 10 ft SWD;
Modify four decant tanks at 45 ft dia. x
17 ft SWD.

Four new at 250 gpm, 1250 Ib/hr and
utilize four existing units.

Four new units at 85 ft dia. x 25 ft SWDj
Rehab existing six units.

Nine new units at 1000 Ib/hr;
Modify existing six units.

One new a 400 cy bin plus material handling
facilities.  Utilize existing bin.

Utilize existing facility.

Rehab two 150 wet ton/day units.
Utilize two 260 wet ton/day units.

-------
                                                                      INFLUENT SPUTTER CHAMBER
                                                         ELECTRICAL SWTCHING STATION
         CENTRIFUGAL
     THICKENING BUILDING
  SLUDGE STORAGE BUILDING
       INCINERATION
        BUILDING
ELECTRICAL SVWTCKINC STATION
 «•>
 to
 o
                                G"Q
PRIMARY
SLUDGE
SPUTTER
CHAUBER
                   -	OK.
                      ELECTRICAL SWITCHING STATION
                                                                         CHLOR1NE/»»OST
                                                                        AERATION BUILDING
        \
                                                                                                                                   MIXED LIQUOR
                                                                                                                                   CONTROL BOX
                                                                                                                                    ELECTRICAL SWTCHING
                                                                                                                                         STATION
                                                                                                                                           LIQUOR
                                                                                                                                    SPUTTER CHAUBER
                                                             OflSTtNC FACIUTIES
                                                             NEW CONSTRUCTION
                                                             ABANDONED FACILITIES

                                                       FIGURE  6-2
                                                       SOUTHERLY TWO-PLANT  SITE  LAYOUT

-------
                                  TABLE 6-8.   SOUTHERLY TWO-PLANT REQUIRED FACILITIES
Component

INTSRCONNECTOR
HEADWORKS


PRSAERATION

PRIMARY SETTLING


AERATION


FINAL SETTLING
Existing Facilitieg

7 miles of 150-156 inch gravity sewer.
60 MGD pump station, 30-inch force main, and
48-inch force main connecting the south end
of the gravity sewer to Southerly.

170 MGD facility which includes screening,
pumping, and grit removal.

Eight tanks at 112.7 ft x 26 ft x 15.5 ft SWD

Four tanks at 80 ft x 165 ft x 10 ft SWD
Four tanks at 100 ft x 170 ft x 10 ft SWD

Ten tanks at 26  ft x 900  ft x  15  ft  SWD
Four tanks at 89 ft x 170 ft x 12.5 ft SWD
Four tanks at 104 ft x 180 ft x 15.5 ft SWD
Required Facilities

Pump station and force mains have
adequate capacity for the south end.
Existing 170 MGD facility is  adequate.


Rehab existing eight tanks.

Rehab existing eight tanks.
Two new tanks at 26 ft x 900  ft x
 15 ft SWD; Modify existing ten tanks

 Six new at 200 ft dia. x 15  ft SWD;
 Abandon  existing tanks.
CHLORINATIOK
One earthen chlorine contact basin at 260  ft x
260 ft x 7 ft SWD.
POST AERATION
EFFLUENT POMPING
GRAVITY
  THICKENING PS

CENTRIFUGE
  THICKENING WAS
Effluent control building with pumping
capacity of 170 MGD.
Four at 250 gpra, 1250 Ib/hr
Two  tanks at 150 ft x 64 ft x 10 ft SWD
including mixers, chlorinators,
evaporators, and sulfinators.
Abandon existing basin.

Final pass  of chlorine contact  tanks
Fine bubble diffusers

Existing facility is adequate.
 Modify  four 45  ft dia.  x  17  ft  SWD
 decant  tanks.

 Four  existing units.  One  new unit  at
 250 gpm,  1250 Ib/hr

-------
                                TABLE 6-8.  SOUTHERLY TWO-PLANT REQUIRED FACILITIES (CONT.)
  Component               Existing Facilities

  ANAEROBIC DIGESTION     Six 85 ft dia. x 25 ft SWD units

  CENTRIFUGE DEWATERING   Six at 1000 Ib/hr
  DEWATERED SLUDGE
    STORAGE

  COMPOSTING

  INCINERATION
One bin at 400 cy
Facility rated at 120 wet ton/day

Two units rated at 260 wet ton/day each.
Two units rated at 150 wet ton/day each,
Required Facilities

Rehab six existing units.

Two new at 1000 Ib/hr
Modify existing six units.

One new bin at 400 cy plus material
handling.  One existing 400 cy bin.

Utilize existing facility.

Two 260 wet ton/day units.
 t
N»
N>

-------
     Figure 6-3  provides a  site  layout of  the Jackson Pike Two-Plant
Alternative and  Table 6-9 presents  the sizes of  the  required  facilities.

6.1.4.2  Technical Evaluation
     Table 6-10  presents the capital, annual O&M, and total present worth
costs  for the one-plant and two-plant alternatives.  These costs include the
costs  for facilities which  are common to the respective one-plant and two-
plant  alternatives (i.e. preaeration, primary clarification,  chlorination,
post aeration).

                    TABLE 6-10.  ALTERNATIVE COST SUMMARY
                                                                 Total
                                 Capital        Annual_Q&M     Present Worth
One-Plant [Southerly]         268,711,000        16,849,000      436,911,000
Two-Plant [So. and JP]        217,860,000        19,078,000      407,800,000
Difference From  One-Plant     -50,851,000       +2,229,000      -29,111,000
Percent Difference                -23              +13               -7
NOTE:  These costs are based on a 2008 average flow of 154 MGD and a peak flow
       of 231 MGD.  Present worth costs are in 1988 dollars.
     Detailed cost estimates prepared during the facilities planning process
by the Turner Construction Company were utilized in preparing the capital
costs.  These detailed cost estimates were reviewed and considered reasonable
facility planning estimates.  These costs were adjusted in the SEIS evaluation
to account for differences in facility requirements due to different flow
projections and sizing criteria.  Operation and maintenance costs were
developed independent of the analysis presented in the facility plan.  Details
on the development of the costs are included in Appendix D entitled Briefing
Paper No. 4 - O&M and Capital Costs.
                                      6-23

-------
      1SO* t INTERCOHNECTOR EXTENSION
ADMINISTRATION BUILDING
                i   Q  r
                      a/
                10=0
MAINTENANCE U PARTS
  BUILDING  n STORAGE
           BUILDING
                                                        CONTROL MOUSE


                                                          GRAVITY TH1CKUJERS
                     PREAERM1
                      TANKS
 EXISTING 108* OSS


OSIS DIVERSION CHAMBER




PROPOSED REROUTING OF 108" OSIS




   COARSE BAR SCREEN
                                                                                    PUMPING ROOU

                                                                                    MECHANICAL SCREENS

                                                                                    AERATED GRIT CHAMBER
                                                                               PLOW MEASURING DEVICES
                                                                              PREAERATION TANKS
                                                                             RAS ROW SPUTTER
                                                                        HNAl. CLAR1RERS
                                                                                                CHLORINE STORAGE AND
                                                                                                HANDLING BUILDING
                                                               CHLORINE
                                                               CONTACT
                                                                TANKS
EXISTING  FAC1LITES

NEW CONSTRUCTION
                                                                            tm.UEMT
                                                                            CONTROL
                                                                            BUILDING
                                       FIGURE 0-3
                                       JACKSON  PUCE  TWO-PLANT  SITE  LAYOUT

-------
                                 TABLE 6-9.  JACKSON PIKE TWO-PLANT REQUIRED FACILITIES

Component^

INTERCONNECTOR


HEADWORKS


PREAERATION


PRIMARY SETTLING


AERATION


FINAL SETTLING


CHLORINATION



POST AERATION


EFFLUENT PUMPING
GRAVITY
  THICKENING PS

CENTRIFUGE
  THICKENING WAS
                        Exis ting Facilities
                        165 MGD facility which includes screening
                        and pumping.

                        Two tanks at 180 ft x 26 ft x 15 ft SWD
                        Two tanks at 113 ft x 26 ft x 15 ft SWD

                        Four tanks at 150 ft X 80 ft x 10 ft SWD
                        Four tanks at 150 ft x 80 ft x 10 ft SWD

                        Eight tanks at 900 ft x 26  ft x 15 ft SWD
                        Four tanks at 900 ft x 26 ft x 15 ft SWD

                        Twelve tanks at 153 ft x 60 ft x 12.5 ft SWD
Two 500 gpra units
                                                     Required  Facilities

                                                     Complete  north end.
                                                     Construct diversion chamber.

                                                     New  100 MGD  facility which  includes
                                                     screening, pumping, and grit  removal.

                                                     Rehab  existing four tanks.
                                                     Rehab  existing  eight  tanks.
                                                     Rehab  and  modify existing twelve tanks.


                                                     Two  new  tanks  at 153  ft  x 60 ft  x
                                                     12.5 ft  SWD; Rehab existing twelve  tanks.

                                                     Two  new  tanks  at 100  ft  x 75 ft  x
                                                     10 ft  SWD  to include  mixers, chlorinators,
                                                     evaporators, and sulfinators

                                                     Final  pass of  chlorine  contact tanks.
                                                     Fine bubble diffusers.

                                                     New  effluent control  building with  a
                                                     pumping  capacity of 100 MGD.

                                                     Three  new  units  at 65 ft dia. x  10  ft  SWD
                                                                              One  new 500 gpra unit.   Utilize two
                                                                              existing units.

-------
                             TABLE 6-9.   JACKSON PIKE TWO-PLANT REQUIRED FACILITIES (CONT.)
Component

ANAEROBIC DIGESTION


CENTRIFUGE DEWATERING

INCINERATION
Existing Facilities

Six units at 85 ft dia. x 23.5 ft SWD
Four units at 70 it dia. x 27.5 ft SWD

Six at 1200 Ib/hr

Two units at 170 wet tons/day total
Required Facilities

Rehab existing ten units.


Modify existing six units,

Rehab two existing units.

-------
     The two-plant alternative exhibits a total present worth cost
approximately 7 percent lower than the one-plant alternative.

     Both the one-plant and two-plant alternatives are equal with respect to
their reliability in meeting the final effluent  limits.   However,  the two-
plant is considered more reliable with respect  to shock  loads.  Under the
one-plant alternative, a plant upset at Southerly could result in a
significant loss of biological treatment capacity and may cause a serious
water quality problem.  However, if the shock and/or toxic load can reach only
one of the two plants, the impact may not be as severe.

     The two-plant alternative is judged  more flexible than the one-plant
alternative.   With both facilities  operational,  the city  would have  more
flexibility to adapt to increased future flow, to meet more stringent effluent
limits, and to address combined sewer overflows.  The two-plant alternative
would leave more land available at  Southerly for expansion.   The two-plant
alternative would improve and upgrade Jackson Pike to provide a solid 100 MGD
treatment capacity.   The two-plant  alternative would  allow for future
expansion of the Interconnector system to divert more Clow to Southerly while
optimizing the use of the Jackson Pike facility.

     The two-plant alternative is considered easier  to implement since the
majority of the facilities  already  exist.  Most  of the construction  would
consist of rehabilitation of existing facilities.  No expansion of the
conveyance system between the plants is required under this alternative.

     The one-plant alternative is considered easier  to operate and maintain
since all facilities would be consolidated at one location.
                                      6-27

-------
 6.1.5   User  Costs
     The Columbus Department  of  Public Utilities and Aviation owns  and
 operates the Jackson Pike and Southerly WWTPs.  This department  finances most
 of  its  capital  improvement  projects  through  revenue bonds and has the power  to
 assess  user  charges.  User  charges are assessed to finance both  capital
 construction costs and O&M  costs of  operating public facilities.  Columbus has
 operated wastewater facilities for some time and has a  proven financial
 capability.  The city has earned an  AA bond  rating, and has accumulated a
 large cash reserve with established  procedures for assessing and raising
 required revenues.

     Currently, Columbus uses a  combination  of methods  to assess appropriate
 user charges to its customers.  These methods include annual user charges
 (regular fees based on usage)  and permits and connection charges (one-time
 fees).  Annual  service charges for processing standard  strength effluent are
 applied to all users.  Additional service charges for processing extra-
 strength effluent are applied  to industrial users.  Inspection and  permit fees
 are applied  to new and rehabilitated units, both commercial and  residential.
 House connection and front  footage fees are applied primarily to new users.
 System capacity charges are assessed according to either the size of the pipe
 installed for residential users or the size of the structure for commercial
 and industrial users.  System capacity charges are designed to recoup the
 costs of capital construction by assessing an appropriate fee on new users
 (City of Columbus Code, Chapter 1147).  Table 6-11 presents estimated
 additional annual user charges for the one-plant and two-plant alternatives.

     Due to  the uncertainty as to the amount and time of current and future
grants of Federal funds, it is useful to present estimated user costs in a
 range for both alternatives from assuming no Federal funds available vs.
assuming a 55 percent grant for all capital construction.  This approach is
presented in Table 6-11 and shows the full range of possible additional annual
user charges for the one-plant alternative ($42 to $76) and the two-plant
alternative ($41 to $68).
                                     6-28

-------
                   TABLE 6-11.  SERVICE CHARGE ESTIMATES
                                                One-Plant         Two-Plant
                                               Alternative       Alternative

Estimated Capital Costs (Present Worth)
     •  With 55% Federal Funds                 $120,829,950     $ 97,947,000
     •  Without Federal Funds                   268,511,000      217,660,000
Annual Amortized Grant Fundable Capital Costs
     •  With 55% Federal Funds                  $14,192,041      $11,504,818
     •  Without Federal Funds                    31,539,201       25,566,262

Annual Operation & Maintenance (O&M) Costs       16,849,000       19,078,000

Anticipated Annual Revenues from
Sewer Service Hook-up Fee
     •  Residential User                          4,400,000        4,400,000
     *  Commercial & Industrial User                500,000          500,000

Annual Extra-Strength Processing Charge Revenues  4,000,000        4,000,000

Annual Costs to be Recovered through Annual
Service Charge
     •  With 55% Federal Funds                   22,141,641       21,682,818
     •  Without Federal Funds                    39,488,201       35,744,262
Estimated Dwelling Units (DUs)                      370,000          370,000

Equivalent Dwelling Units (EDUs)                    152,576          152,576
  (Coraercial & Industrial Users)

Estimated Number of Users                           522,576          522,576
  (Total DUs and EDUs)
Additional Annual Service
Charges per User for the SEIS Alternatives
• With 55% Federal Funds
• Without Federal Funds
1985 Annual Service Charge Per User
• Residential Users
Projected Annual User Charges


$ 42
76

108
$150-184


$ 41
68

108
$149-176
                                      6-29

-------
     As of the most recent Columbus budget, $117,730,000 has been obligated
 toward construction to meet 1988 water quality limits at the Jackson Pike and
 Southerly WWTPs.  Annual residential user fees in Columbus have been increased
 since 1985 to reflect the obligation of those funds.  For this reason, user
 fees in 1985 are combined with new costs for the alternatives to estimate
 future residential costs.  User fee increases for costs to complete either the
one-plant or two-plant alternatives are estimated to result in future annual
residential user fees of $150 to $184 for the one-plant alternative and $149
to $176 for the two-plant alternative.

     Median family income is often used to assess the affordability of
increases in user charges to average residents.  As shown in Table 6-12,
Franklin County, which includes most of the service area, had median family
incomes over $17,000 in 1979.  Based on EPA guidelines, an annual user charge
of $367 would not be considered excessive for this income category.  Based on
these guidelines, none of the estimated additional user charges will make
total user charges excessive.

           TABLE 6-12.  MEDIAN FAMILY INCOME FOR THE UNITED STATES,
             OHIO, FRANKLIN COUNTY, AND COLUMBUS IN 1969 AND 1979
                                                 Median Income
                                               1969	1979
                                              9,586        19,917
                                             10,309        20,909
                                             10,579        20,970
                                              9,729        18,612
                                             10,282        20,882
              Source:   Bureau of Economic Analysis,  April 1986.
                                     6-30

-------
6.2  ENVIRONMENTAL CONSEQUENCES - PHYSICAL ENVIRONMENT
6.2.1  Surface Water Quality
     The principal variable in the Supplemental Environmental Impact Statement
(SEIS) alternatives, with respect to surface water quality,  is the location of
effluent discharge.  Functionally, only two alternatives exist.

     •  Effluent discharge at two locations (Jackson Pike and Southerly)
     •  Effluent discharge at a single location (Southerly).

     Comparable levels of treatment will be achieved prior to effluent
discharge, with each one-plant or two-plant alternative.

     Raw effluent entering the wastewater treatment plants (or plant) will
receive biological treatment for substantial reduction in the concentration of
biodegradable components of the wastestream, prior to discharge.
Nevertheless, the treated effluent will contain residual amounts of
biodegradable contaminants, which will undergo final decay in the receiving
water.  In this final decay, dissolved oxygen will be consumed, exerting an
oxygen demand in the Scioto River.  The extent of this oxygen demand is a
consequence of the loading rates of oxygen-consuming pollutants in the
effluent, and is expressed as 5-day carbonaceous biological oxygen demand,
CBOD5.  The CBODj loading rates are defined by the National Pollutant
Discharge Elimination System (NPDES) permits.  In addition to CBODc, nitrogen
decay also creates an oxygen demand in the receiving water.  Nitrogen limits
in the NPDES permit are expressed as ammonia nitrogen (NH3-N).

     In the Scioto River, CBOD^ and NH3-N decay will result in a temporary
reduction in dissolved oxygen (DO) downstream of the outfall(s).   The extent
of the DO reduction,  and the length of the river affected, is governed by
physical, chemical, and biological parameters in the receiving water.  These
parameters define the rates at which oxygen-demanding residual constituents in
the effluent are decayed (assimilative capacity).   The NPDES effluent limits
                                     6-31

-------
 established  for  the  Jackson Pike  and/or  Southerly Wastewater Treatment Plants
 (WWTPs)  one- or  two-plant  scenarios  are  intended to preserve a minimum DO
 level  in the receiving water  (5.0 mg/1 mean and 4.0 mg/1 minimum), by
 carefully matching loading rates  of  oxygen-consuming  pollutants with the
 assimilative capacity of the  receiving water.

     To  assist in selecting the appropriate NPDES discharge limits, the Ohio
 Environmental Protection Agency (OEPA) developed an empirical model of the
 Scioto River, which  provides  a mathematical simulation of  the river's
 assimilative capacity.  This  model (QUAL2) was used as the basis  for wasteload
 allocations  and  subsequent effluent  limits in the draft Scioto River
 Comprehensive Water  Quality Report (CWQR) (OEPA 1983).  The original QUAL2
 model was updated by the city of  Columbus.  The updated model (QUAL2E) was
 used by  OEPA as  the  basis  for modihied wasteload allocations and  related
 permit limits as contained in an  amended CWQR (OEPA 1986a).  Although the
 amended  CWQR has not been  approved by the USEPA, the NPDES permit limits have
 been accepted and are the  basis of the facilities planning decisions evaluated
 in this  SEIS.

     In  developing this SEIS, the QUAL2E model was evaluated.  This evaluation
 concluded that a number of technical assumptions used in the model (including
 steady state conditions, benthic  oxygen demand, phytoplankton, organic
 nitrogen demand, and flow/depth/velocity relationships) were questionable.
 Collectively, these assumptions put  in question the reliability of the
 wasteload  allocations, permit limits, and related DO predictions for the
 receiving  water.

     The results of the QUAL2E model evaluation are summarized in Appendix L.
 The USEPA Water Quality Branch has reviewed the QUAL2E model evaluations and
 has concurred that model calibration and verification could be improved.
 However, the USEPA has concluded  that the error margin in the existing QUAL2E
model is acceptable and that  the  permit limits based on this model are
 reliable and would achieve DO and NHo water quality standards.  Based on the
                                      6-32

-------
results of the QUAL2E model and  professional judgement,  the USEPA Region V
Water Quality Branch has "... endorsed  the  two-plant  analysis"  (Fenner, 1987).
The results of the USEPA review  of  the  QUAL2E model evaluations are  included
in Appendix M.  Consequently, the following discussion of water quality
impacts reflects  the conclusion  that proposed permit  limits are sufficient  to
meet minimum water quality standards under either  the one-plant or two-plant
alternative.

     Based on existing data in the  CWQR and as previously discussed  in chapter
2, the biological quality of the mamatem Scioto River is primarily  impacted
by discharges from the two Columbus treatment plants.  This section  of the
river has been well-studied, and the historic data indicate that significant
improvements have occurred in water quality and the fish community structure
during the past decade.  However, water quality continues to be degraded from
the confluence of the Scioto and the Olentangy to just upstream of
Circleville.  The CWQR states that  "the principal chemical/physical  water
quality problem in the central Scioto River mainstream has been, and continues
to be, low dissolved oxygen."  The  low dissolved oxygen conditions are caused
by discharges from Jackson Pike, Southerly, and from the Whittier Street
Combined Sewer Overflow (CSO).

     Effluent monitoring data collected by the city of Columbus at their
Jackson Pike and Southerly WWTPs show that neither facility can consistently
meet its final water-quality-based NPDES permit limitations.  The Jackson Pike
and Southerly WWTPs are required to be  in compliance with these final limits
by July 1, 1988.   Jackson Pike data for 1985 show that the plant usually
exceeded the CBODc and NH -N limits in the summer and occassionally violated
these limits in the winter.  The effluent did not achieve the minimum required
DO concentration of 7 mg/l.  The 1985 performance at Southerly indicates that
this facility could normally achieve the minimum required CBODc limit, but
exceeded final ammonia limits in the summer.
                                      6-33

-------
     The preceding discussion of effluent quality at Jackson Pike and
 Southerly only concerns  flow which  is  treated.  The Southerly plant has a raw
 sewage bypass at  the WWTP and the Jackson Pike plant has the capability to
 bypass flows at Whittier Street.

     During periods of low flow, algal metabolism can influence DO levels in
 the ScLoto River  (OEPA 1986a).  The impact of algal metabolism on DO is
 evident in the data collected by OEPA on July 19-22 and September 1982, for
 water quality modeling of the Scioto between Jackson Pike and Circleville.  DO
 levels below 5 mg/1 are seen along  the entire river reach studied.

     Fecal coliform data from facility self-monitoring reports, the CWQR, and
 EPA's STORET system show elevated counts of bacteria along the Scioto River
 throughout the Columbus area.  Data contained in the CWQR show occasional high
 numbers of fecal coliform bacteria even upstream of the discharge from the
Whittier Street CSO.  According to  the CWQR, 31 percent of the fecal coiiform
 data collected by the OEPA exceed the primary recreation standard of 2,000
 counts/100 ml.  Sixty percent of the data collected by the city of Columbus,
 as part of their cooperative program with the state, exceed the standard.  The
 elevated levels are likely caused by combined sewer overflows and bypasses and
by urban runoff.

 6.2.1.1  No Action Alternative
     The no action alternative assumes no improvements to the existing
 facilities,  although normal maintenance would continue (see Section 5.1.1).
Because the no action alternative does not provide for the rehabilitation or
upgrading of the existing facilities,  violations of the final discharge limits
may occur.   The aquatic environment of the Scioto River in the Facilities
Planning Area (FPA) is degraded, largely as a result of current inadequacies
 in wastewater treatment.   The no action alternative will result in a
perpetuation of the current water quality/aquatic ecology impairments (see
 chapter 2).   Generally, depressed DO conditions and reduced aquatic biota will
exist from Columbus to Circleville.
                                     6-34

-------
     As  the existing  facilities age  and  the wastewater  loads  to  the  exisitng
 facilities increase (through growth  in the sewered  population),  the  frequency
 and duration of permit violations and degree of  impact  on  the receiving water
 is also  expected to increase, under  the  no action alternative.   These
 increases will have two effects.  First, water quality  in  the already  impacted
 section  of the Scioto River will deteriorate, displacing the  less  tolerant of
 the already reduced aquatic species  inhabiting this area.  Second, the zone of
 impact will expand downstream as the length of river needed to assimilate a
 growing  residual effluent wasteload  increases.   Based on currently available
 water quality data, it is probable that  the zone of impact would reach
 Circleville within a number of years.  Under these conditions, the Scioto
 River below Circleville no longer would be capable of fully assimilating the
 residual effluent oxygen demand from the Circleville POTW, and a second zone
 of water quality/aquatic biota impairment would  result.  This scenario could
 result in an inability of the Circleville POTW and industrial NPDES
 dischargers in the Circleville area to meet water quality standards  at current
 treatment levels.

 6.2.1.2  Two-Plant Alternative
     The two-plant alternative will result in signficant water quality
 improvements in the Scioto, particularly in DO levels.  The upgraded Jackson
 Pike and Southerly plants will be capable of consistently meeting final
 limits, and few violations of the DO standard would be expected  in the river.
 However, since only limited nutrient removal would accompany  the plant
 upgrades, algal metabolism would likely continue to affect dissolved oxygen,
 expecially during periods of low flow.

     Effluents from the Jackson Pike and Southerly WWTPs will contain a
 residual DO demand which will be assimilated by  the Scioto River, resulting in
 a DO sag downstream of each plant.   The DO sag below either plant will not
exceed the in-stream DO standards.   The critical point in the sag below
 Southerly will occur approximately 12 miles downstream of the WWTP outfall,
near the confluence of Walnut Creek.
                                      6-35

-------
      Improvements  in riverine DO  levels resulting  from the two-plant
 alternative will be partially masked by continued  discharges  from the Whittier
 Street CSO.  Although  the city  is currently studying the CSO  problem, no CSO
 corrections are included in  the current facilities planning efforts.
 According  to the CWQR, "on an annual basis, the Whittier Street CSO
 contributed nearly as  much BOD^ loading (32.7 percent) in 1982 as did the
 Jackson Pike WWTP (38.8 percent)" (OEPA 1986a).  Although the loadings are
 highest during the spring and winter, some discharge does occur during periods
 of low flow and high temperature when the river is most sensitive to depressed
 DO.

      Field data collected for a report on CSOs by  Malcolm Pirnie, Inc. (1983)
 show  that  the Whittier Street inputs can depress in-stream 00 levels below  the
 standard during periods of low  flow.  Therefore, although the proposed
 discharge  limits will  protect in-stream DO standards based on the Jackson Pike
 and Southerly WWTP effluents, occassional violations of the standards may
 continue to occur resulting  from other sources.  However, the section of the
 Scioto River exhibiting continued depressed DO levels will be reduced
 significantly under the two-plant alternative and will be essentially
 constricted to an area below Whittier Street.  Consequently,  downstream areas
 (near and below Southerly) of the Scioto River will exhibit the greatest
 overall improvement in DO conditions under the two-plant alternative, while
 improvements in upstream areas, closer to Whittier Street and Jackson Pike,
will be reduced.

     Although the two-plant alternative will significantly reduce loadings of
certain oxygen-consuming pollutants (e.g.  BODc), resulting in improvements to
 in-stream DO levels, nitrogen compounds in the effluent will  continue to exert
a DO demand.  The existing modeling does not provide a reliable basis for
evaluating the DO impact of ammonia, nitrite/nitrate, organic nitrogen, and
TK.N.   However, because background sources of these nitrogen compounds tend to
be concentrated in the urban areas of the watershed, nitrogen-related DO
 impacts will be greatest in the area of the Scioto River immediately
downstream of Columbus.
                                      6-36

-------
      Treatment processes at Jackson Pike and Southerly will prevent any
 significant  fecal  coliforro loading to the Scioto River.   However,  fecal
 coliform discharges  will continue from the Whittier Street CSO and other
 urban sources  in the Columbus  metropolitan area.  Although significant fecal
 coliform loading to  the Scioto River does not presently  occur from the two
 WWTPs,  excess  chlorine  discharged from the Jackson Pike  and Southerly plants
 produces a measurable decrease in in-stream fecal coliform levels  below the
 two plants.  Under the  two-plant  alternative, the total  residual chlorine
 limits  in the  discharge permits (JP - 19 ug/1,  SO - 26 ug/1)  will  result in
 little  or no in-stream  fecal coliform kill,  and future fecal  coliform numbers
 may exceed present levels under certain flow conditions.   Because  most
 remaining fecal  coliform sources  (after implementation of the two-plant
 alternative) will  be concentrated in the urbanized  areas  near the  confluence
 of the  Olentangy and Scioto Rivers,  the area of continued water quality
 impairment (relative to fecal  coliforms)  will be concentrated in this  zone.

 6.2.1.3  One-Plant Alternative
      The  one-plant alternative provides for  the complete  elimination of the
 Jackson Pike WWTP  with  all  flows  routed to Southerly.  The Jackson Pike flow
 will  be conveyed to  Southerly  through  the existing  gravity Interconnector
 Sewer.  This Interconnector Sewer will  be extended  to  the  Southerly plant.
 Four  78-inch pipes will  cross  the Scioto  River  in the  alignment of the
 existing  force mains.

     The water quality  impacts  of the one-plant  alternative are similar  to
 those of  the two-plant  alternative  for  many  parameters as  discussed in  the
 preceding section.  Consequently, the following  discussion focuses  only  on
 those impacts that are not  common to the  one-plant and two-plant
alternatives.

     Under the one-plant alternative, critical  low  flows in the upper Scioto
River, between Jackson Pike and Southerly, would be significantly  reduced.
The city of Columbus  is authorized to remove  100 percent of Scioto River
                                      6-37

-------
 flows at the Dublin Dam water intakes.   Consequently,  Scioto River  flows  may
 drop to essentially zero below the Dublin Dam during critical low flow
 periods, at  which time river flow is sustained by Olentangy River discharges.

      Flows in the lower Olentangy River are  regulated by the Delaware Dam
 during low flow  periods.   The guaranteed minimum release is 5 cubic feet  per
 second (cfa)  from the  Delaware Dam.   Although the actual measured minimum is
 11 cfs in the lower Olentangy River, the observed minimum for the 7-day/10-
 day  critical  low flow  period is 13 cfs.    Assuming a 13 cfs low flow discharge
 from the Olentangy River,  a  zero low flow over the Dublin Dam,  a correction
 factor for groundwater recharge which is cited as insignificant (Francis,
 1987a),  seepage  under  or  around the  Dublin Dam,  and miscellaneous industrial
 direct dischargers;  the minimum low  flow immediately above Jackson  Pike is
 estimated at  approximately 20 cfs.

      The average  daily dry weather discharge  at  Jackson Pike is approximately
 78 MGD,  or 121 cfs,  based  on 1985-1986  flow  records.   This effluent flow  is
 six  times the estimated 20 cfs flow  rate in  the  Scioto River, upstream of
 Jackson  Pike, during critical low flow  periods.   Consequently,  removal of
 Jackson  Pike  flows  will reduce present  flows  in  the upper Scioto River,
 between  Jackson Pike and Southerly,  by  as  much as 86 percent during critical
 low  flow periods.   (Current  low flows below Jackson Pike are the sum of 20 cfs
 from upstream flow and  121 cfs from  Jackson Pike.)   This decrease in flows
 will  result  in more  pronounced pooling  and longer riffle areas  between pools.
 The  surface areas  of the riffles  will increase as a function of length, but
 the wetted area will be laterally constricted.

      The  city of Columbus  has  compared  flow versus  depth for Scioto River
 cross  sections between  Jackson Pike  and  Southerly,  comparing the one-plant
 versus two-plant alternatives.  For  nine cross sections  affected by the one-
 plant  alternative,  flow depth  would  be  reduced by an average of 39  percent,
with  a range  of 13  to  72 percent.  In three cross sections  (QUAL2E  stream
 reaches 3, 4, and 8),  flow depth  will be  less  than  1  foot  (0.15  foot,  0.84
 foot,  and 0.35 foot, respectively).  Because  the  flow  calculation component  of
                                      6-38

-------
the available modeling  is  not  considered  reliable,  the  true  nature  of  the  low
flow impact cannot be determined.

     Elimination of  the Jackson Pike  effluent will  remove a  major source of
water quality impact on the  Central Scioto River.   However,  it  is important  to
realize  that other sources (e.g.,  general urban  runoff  and the  Whittier Street
CSO) also exert a major water  quality impact (the calculated BODij loading  from
the Whit tier Street  CSO approximates  the  current loading from Jackson Pike and
has been shown to result in  violations of in-stream DO  standards).
Consequently, the impacts  of the one-plant alternative  will  be  different on
the stretch of the Scioto  between  Jackson Pike and  Southerly and the stretch
between  Southerly and Circleville.  In the following discussion, the stretch
betweeen Jackson Pike and  Southerly is referred  to  as "below Jackson Pike" and
the stretch between  Southerly  and  Circleville is referred to as "below
Southerly".

     Below Jackson Pike, the impacts  of the one plant alternative will be
strongly flow-dependent.   Under most  flow conditions, elimination of the
Jackson Pike effluent loading  will result in improved water  quality
conditions, to the extent  that this effluent affects water quality.  However,
for the one-plant alternative, it  is  possible that  water quality in the upper
Scioto River would deteriorate under  certain flow conditions.

     Under critical  low flow conditions water quality in the Scioto River
below Jackson Pike will be dominated  by wasteload sources not affected by  the
one-plant alternative, including the  Whittier Street CSO and general urban
runoff.  Under these flow conditions, removal of the Jackson Pike effluent may
result in diminished water quality and aquatic biota conditions below Jackson
Pike,  for the following reasons:   1)  the Jackson Pike effluent  represents 86
percent of Scioto River flow under low flow conditions, 2) this effluent would
meet water quality standards, and 3)  the other wasteload sources entering  the
Scioto River near Jackson Pike (CSO and urban runoff) contribute pollutant
loads  equal to or greater than Jackson Pike.   For these reasons, elimination
of the Jackson Pike effluent may remove a beneficial dilution effect which
would be present under the two-plant  alternative.
                                      6-39

-------
      Below the Southerly WWTP,  no change  in river  flows  will  occur as  a  result
 of the one-plant alternative.   Downstream water  quality  conditions are
 expected to generally improve with respect to  DO,  residual  chlorine, and
 CBODr.  However, an oxygen demand will  remain  in the  effluent,  in the  form of
 residual BODc,  nutrients,  and various nitrogen compounds.   This  residual
 demand will result  in a  DO sag  downstream of Southerly.  Although this sag
 would  occur under either the one- or two-plant alternative,  the  severity of
 the  sag and length  of river affected is expected to be greater  under the one-
 plant  alternative.   This is a result of all residual  effluent wasteload  from
 Columbus being released  to the  river at a single location with  no increase in
 river  flows or other parameters affecting assimilative capacity.

 Water  quality  modeling has determined that final effluent limits  for the
 Southerly WWTP  will protect in-stream DO  standards below Southerly, under the
 one-plant alternative (see Appendix M).   While the critical point in the DO
 sag  will occur  at essentially the same  location  under either  the  one-plant or
 two-plant scenario  (approximately 12 miles downstreeam of the Southerly  WWTP),
 the  severity of the sag  is greater under  the one-plant alternative (i.e.,
 downstream  DO  levels are higher under the two-plant alternative)  based on the
 QUAL2E model results.  Although the stream standard will not  be contravened  by
 the  one-plant alternative,  the  DO sag resulting  from  the residual wasteload
 demand of the  Southerly  WWTP effluent will affect a longer  stretch of  the
 river  than  would  occur under the  two-plant alternative and may affect a
 longer stretch  than is impacted by the  present DO sag.   In addition, the
 increased nutrient  release  associated with the one-plant discharge may
 further  impact  downstream  DO due  to increased  algal metabolism, which has
been shown  to have  a  significant  impact on in-stream  DO  levels at low  flow.
Any  increase in  the  length  of river affected by  the expanded  DO sag will  be  in
a downstream direction.  Therefore, the one-plant alternative represents  a
greater  probability of interfering with other  downstream dischargers, because
 the severity and  length  of  the  sag would  be extended  downstream.   The QUAL2E
model  does not extend far enough downstream to assess this possible impact.
                                       6-40

-------
     Under  current  conditions,  the  critical  point  in the  DO sag from Southerly
 is  located  much closer  to Ci.rclevi.lle  than Southerly and  water quality at
 Circleville reflects  residual BODr  from  the  Southerly effluent discharge.
 Under  the one-plant alternative,  the  increased wasteload  discharged  at
 Southerly will result in a  greater  probability that  the DO  sag,  residual
 BODc,  ammonia, and  other pollutants will  impact Circleville.   This impact
 could  impair the ability of the river  to  assimilate  oxygen-consuming wastes
 from existing dischargers in the  Circleville area  of the  Scioto  (e.g.,
 Container Corporation at RM 99.6; Circleville FOTW,  and DuPont at Rm 95.9).
 The existing water  quality  modeling is inadequate  to assess  this potential
 impact, and the OEPA has recommended  that "...all  discharges maintain their
 current NPDES permit  limitations" in  that portion  of the  Scioto  River,  from
 just above  Circleville  (RM  99.2)  to river mile 77.7  "...due  to the
 uncertainty regarding this  segment" (OEPA  1986a).

     Finally, the one-plant  alternative will  require placement of four  78-inch
 gravity sewer pipes across  the Scioto River.  The  crossing will  occur parallel
 to the existing force mains  in the  immediate  vicinity of  the Southerly  plant
 site.  The  pipes will be buried in  the stream bed.   Placement  of the  pipes
will result  in short-term increases in turbidity and  sedimentation downstream
 of the construction area.  The city of Columbus, however, has  proposed  a
variety of mitigating measures, in  the form  of construction  techniques, which
 should minimize the impact.  These  measures  include  timing of  construction in
 the fall when river flows are low;  isolation  of the  in-stream  construction
 zone to prevent river water  from  flowing  through the  disturbed streambed area
during construction, replacement of the natural streambed materials
 following pipe placement; and stabilization of the cut bank areas during and
after construction.  These mitigating measures are described in Table 6-13.

6.2.1.4  Conclusions
     The principle variable affecting surface water  quality under any
alternative  is the location of wastewater discharge.  Comparable levels of
treatment will be provided under either the one-plant or two-plant
                                     6-41

-------
                       TABLE 6-13.  MITIGATION ON SEWER LINE
                                 (Interconnector)
Cons truct ion Act ivi ties

1.   Sewer on Flood Plain

     a.   Pre-clearing
     Attributes
 Existing  Vegetation
     b.   Clearing and Grading    Slight Slopes
                                 Drainageways
     c.   Excavation of Trench    Excavated  Material
     d.   Restoration              Exposed  Topsoil
         (after  final  grading)
        Restoration
    e.  Final Landscaping
Established
Vegetation
Existing Flora
Damage
    Mitigative Measures
 Clearly mark  construction
 easement.  Mark  trees  to
 be  saved and  identify
 stockpile  areas.

 Begin in low  precipitation
 month.

 Staked hay bales and/or
 mesh of jute.

 Stockpiled upslope  from
 trench.  Separate top  soil
 from subsoils.  Cover
 stockpile  with plastic if
 not returned  immediately
 to  trench.  Expose  only
 small lengths of sewer at
 a time.

 Final grade with stock-
 piled topsoil; seed with
 naturally  occurring
 grasses during spring  or
 fall planting season.  Use
 hydroseeding or air-
 seeding at a rate of 3.5
 Ib. of seed/1,000 square
 feet.  Mix fertilizer and
mulch per manufacturer.

Maintain sediment
barriers until vegetation
 is established.

Prune trees as required if
root damage occurred and
replace trees as directed
by owner.
                                      6-42

-------
                       TABLE 6-13.  MITIGATION ON SEWER LINE
                              (Interconnector) (CONT.)
Construction Activities

2.   Sewer on Stream Bank
     (only one bank at a time)

     a.  Pre-clearing
                                     Attributes
                                 Water Quality
                                 and Soil
     b.  Clearing and Grading    Stream and Bank
     c.  Excavation
     d.  Restoration
Stream and Bank
Sloped Area
3.   Sewer in Streambed
     a.  Pre-construction
Aquatic Habitats
and Water Quality
                            Mitigative Measures
                        Low stream flow.
                                                         Establish dry area at
                                                         interface between bank and
                                                         stream and use hay bales
                                                         or steel sheetings to
                                                         catch any sediment.

                                                         Maintain dry area inter-
                                                         face and remove excess
                                                         sediment as required.

                                                         Restore existing grade,
                                                         place rip-rap at water
                                                         line, reseed and cover
                                                         with mesh or jute or net
                                                         to stabilize bank, main-
                                                         tain silt barrier until
                                                         vegetation has been
                                                         established, ground cover
                                                         to be used where shade may
                                                         prevent grass from being
                                                         established or compatible
                                                         with existing vegetation.
                                                         Low flow established
                                                         (timing).   Obtain Army
                                                         Corps of Engineers Section
                                                         10 and 404 permits.
                                                         Establish minimum
                                                         construction easement.
                                                         Keep to permanent easement
                                                         if possible.
                                    6-43

-------
Construction Activities

 3.  Sewer in Strearabed
     (continued)

     b.  Excavation
TABLE 6-13.  MITIGATION ON SEWER LINE
       (Interconnector) (CONT.)

              Attributes
          Aquatic Habitats
          and Water Quality
     c.   Restoration
          Aquatic Habitats
          and Water Quality
    Mitigative Measures
Block only one-half  to
one-third of the stream at
a time.  Remove streambed
and stockpile separate
from sub-bed material.
Keep area dewatered.
Collect discharge water
and separate silt.   Place
all excavated material
upland from stream with
sediment catchbasin  around
stockpile area.  No
material to be placed in
river outside of dry
construction area.

Backfill above sewer with
substream material.  Place
excavated streambed
material to final
elevation.  Fill area with
stream water slowly  to
prevent washout.  Remove
any excess excavated
material to upland
disposal site as shown on
plans.
                                     6-44

-------
 alternatives,  and  either alternative  will  protect  stream standards for DO and
 ammonia.

     Regardless  of the  one-plant  or two-plant  alternative,  the  treated
 effluent will  contain a residual  waste load,  which  will  be assimilated  by the
 river,  resulting in a downstream  DO sag.   The  severity  of the sag,  and the
 extent  of  the  river affected, vary between alternatives.

     Under  the no  action alternative, no improvement  in the degraded water
 quality conditions  in the Scioto  River will  occur.  With  projected  future
 growth  in  the  sewered population  (and corresponding increases in wastewater
 flows), age-related deterioration of  the existing WWTPs and increases  in urban
 non-point  runoff due to  continued urban growth, further deterioration  in
 current water  quality conditions  is expected.  Under  these conditions, more
 frequent water quality  standards  violations  can be expected and the impacted
 zone of the Scioto  River  below Southerly may be extended  to Circleville,
 interferring with other  point source dischargers.

     The two-plant  alternative will release  the residual effluent DO demand
 to the  Scioto  River at  two locations  (Jackson Pike and  Southerly).  Two DO
 sags will therefore  result, however, neither sag will result in contravention
 of water quality standards.  Significant improvements to  in-stream DO
 conditions will  result  from this  alternative.  Because  significant pollutant
 loads will continue to enter the  Scioto River upstream  of Jackson Pike (from
 urban runoff and CSOs from Hhittier Street), the degree of water quality
 improvement below Jackson Pike will be less complete  than below the Southerly
WWTP.  Under certain flow conditions,  DO levels below the 5.0 mg/1 standard
may occur below Jackson Pike, related to CSO loadings.  However, the presence
of Jackson Pike effluent during low flow events may lessen the DO impacts  of
CSOs and upstream urban runoff.

     The impacts of the one-plant alternative are variable for the river reach
between Jackson Pike and Southerly,  depending on background river flow
conditions at average river flow  levels, water quality will be improved by the
                                     6-45

-------
 elimination  of  Jackson Pike  effluent.  However, under  critical  low  flow
 conditions,  elimination of  the  Jackson Pike effluent will  reduce  Scioto River
 flows  by  nearly 90  percent while  a  large background pollutant load  will remain
 in  the form  of  urban  runoff  and CSO loading.  This situation will result  in  a
 significant  reduction in the river's wasteload assimilative capacity due  to
 reductions in flow  volume, velocity, and reaeration.   Decay of  pollutants  from
 upstream  sources could therefore  result in severe water quality deterioration
 in  slow,  shallow pools during warm  weather, low flow events.

     Downstream of  the Southerly  WWTP, the DO sag resulting from  the one-plant
 alternative  will be more  severe and will affect a longer stretch  of the river,
 when compared with  the two-plant  alternative.  This situation results  from the
 release of the  entire  residual  wastewater DO demand from Columbus at a single
 point  in  the river, creating a  greater assimilative demand.  In addition,  the
 increased nutrient release under  the one-plant alternative will further
 stimulate algal biomass below Southerly which may depress  low flow  DO below
 in-stream standards due  to algal  metabolism.  The combination of  these factors
 results in a possibility  that the one-plant alternative may impact  the
 Circleville area, interfering with  other point source dischargers near
 Circleville.

     Based on these considerations, the two-plant alternative is considered
 preferable over the one-plant alternative with regard to water quality
 impacts.

 6.2.2  Surface Water Flow
     Current  construction activities at the Southerly WWTP should have little
or no impact  on the 100-year floodplain.   Construction at the Southerly WWTP
 location includes increasing the plant's  foundation and building berms around
 the facility.  Both of these construction activities would tend to  increase
the flood boundary during a 100-year flood  compared to preconstruction
                                     6-46

-------
conditions.   These  activities  are similar under either system alternative.   To
minimize  potential  flood  increases,  Columbus  was able to have the flood fringe
redefined by  the  Federal  Emergency Management Agency (FEMA)  by guarantee that
portions  of the land  bordering the Scioto River that would be inundated during
the  100-year  flood, and that could feasibly be developed,  would not be
developed.  This  land is  either owned  by  the  city or is  in the process of
being  purchased.  The city's study was reviewed,  approved, and printed for
public release by FEMA.   The new 100-year flood elevation, after redefining
the  flood fringe, is  at roost about one-fourth foot higher  than before.

6.2.2.1   No Action
     By taking no action, no significant  changes  are expected in the flows
observed  in the Scioto River.   The volume of  surface water Columbus  currently
removes from  the  Scioto River  is  about the maximum possible  limit,  especially
during the critical low flow months  of summer  and  fall.  Therefore,  no
future manmade reductions in the  volume of flows  in  the  Scioto River are
expected  around the Columbus area.   Because the stretch  of the Scioto River
affected  by the Jackson Pike WWTP is small, and because  the  river bed is
believed  to be at least partially sealed  by industrial and WWTP sludges,
little or no  impact upon  the groundwater  system by changes in surface water
quality is expected.

6.2.2.2   Two-Plant Alternative
     The  two-plant alternative will discharge  flows  from the  Jackson Pike WWTP
at about  the  same levels as currently  occur.  For this reason,  impacts  from
the two-plant alternative are not  expected to significantly alter the physical
parameters of Scioto River surface water between  the Jackson  Pike and
Southerly WWTPs.

     Another  factor affecting Scioto River flows  is  a new hydroelectric power
plant, built  as part of the O'Shaughnessy Reservoir  Dam, upstream of Columbus.
At present, flows through the O'Shaughnessy Dam are  based on  the downstream
needs of  the Griggs Reservoir and  the Dublin Road Water Treatment Plant
(DRWTP).  Following construction of the new power plant, flows may be
                                      6-47

-------
 released more quickly to the  Griggs  Reservoir,  but  not  above  the  Griggs
 Reservoir capacity (Bell 1987).   However,  the expected  effect of  this  power
 plant  on Scioto River flows  is uncertain.  There may  be an  increase  in the
 number of days when low-flow  conditions  occur.  The latter  condition may
 occur  if the  O'Shaughnessy Reservoir retains more water than  in the  past  to
 provide maximum hydraulic head (maximum  potential water elevation) to  power
 the  hydroelectric  turbines.   Some of the buildup of hydraulic head would  occur
 during periods when the  Scioto River flow  might normally pass the DRWTP.

 6.2.2.3  One-Plant  Alternative
     The Jackson Pike WWTP discharges a  daily mean  flow of  130 cubic feet per
 second (cfs),  or 85 million gallons  per  day (MGD),  into the Scioto River.  The
 USGS surface  water  gauge at Jackson  Pike WWTP (003227500) records a  daily mean
 flow of 1,390 cfs,  as shown in Table 6-14.  The removal  of  Jackson Pike WWTP
 discharges, as  proposed  under the  one-plant alternative, will result in an
 average flow  reduction of less than  10 percent.  This reduction will have a
 negligible effect during average  flow conditions and no  effect  at flood
 conditions.   However, at low-flow  conditions, the effects will  be significant.
 The 7Q10  low-flow used for environmental reasons, as discussed  in chapter 2,
 is 13  cfs.  At  this background flow, removal of Jackson  Pike  WWTP discharge
 will result in  a reduction of Scioto River flows, between the Jackson  Pike and
 Southerly WWTPs, of more than 90 percent.  The  Scioto River flow  regime along
 this stretch will become slower, shallower, and narrower during low-flow
 conditions.  Fools will  receive less mixing (and have an increased flushing
 time), while riffles may have reduced turbulence.   If the discharge  structure
 is designed and  constructed properly, erosion of the river  bed  and banks, the
most potentially deleterious effect, will be prevented.

6.2.2.4  Conclusions
     The no action and two-plant alternatives will have  little or no impact
on surface water flows in the Scioto River.  The one-plant  alternative will
cause  significant reductions in flows in the Scioto River during  low-flow
periods in the eight mile reach between  the Jackson Pike and  Southerly WWTPs.
Impacts of this change are reviewed  in Section 6.2.1,  6.2.3., 6.3 and 6.4.7.
                                     6-48

-------
            TABLE 6-14.  SURFACE WATER  FLOWS*  IN THE  OLENTANGY  AND
                         SCIOTO RIVERS  AT COLUMBUS, OHIO


                                             1                          2
                              Olentangy Flows   in          Scioto  Flows  in
Duration/Recurrence           Cubic Feet per Sec.         Cubic Feet  per  Sec.


7 consecutive  day  mean  low        21.4                       118.0
     7Q10 low                        11.1                        65.8
     3Q10 low                        10.0                        62.4
     1Q10 low                         9.1                        59.6

1 day mean low                       17.4                       102.8
     1Q2 low                         14.9                        95.6
     1Q5 low                         10.6                        70.0

1 day mean high                      4660                       18800
     1Q2 high                        4230                       17300
     1Q5 high                        5150                       25300
     3Q10 high                       5080                       23000
     7Q10 high                       4640                       16400
     1Q50 high                       8610                       41500
     1Q100 high                     10100                       46000
     daily mean                     457.0                        1390


*These values were obtained using a log Pearson type II analysis of USGS
WATSTORE data bases.

1River gauge #003226800 on the Olentangy River below the Delaware Dam.
«
''River gauge #003227500 on the Scioto River at Jackson Pike WWTP.
                                     6-49

-------
 6.2.3  Groundwater
      Beginning in the  early  1980's,  groundwater became  one  of  the  sources of
 raw water  for Columbus'  municipal  drinking  water  system.  Columbus'  growing
 water demands exceeded the available surface water  supplies at the Dublin Road
 Water Treatment  Plant  (DRWTP)  and  the Horse Road  Water  Treatment Plant
 (MRWTP), particularly  during summer  months, leaving groundwater as the  next
 available  water  source.   In  response,  the Parsons Avenue Water Treatment Plant
 (PAWTP) was  constructed  to mine groundwater from  the Teaya  aquifer,  a buried
 glacial braided  river  system in southern Franklin County.

      Data  on bacterial  levels  in Columbus area groundwater  are not available.
 Tests  are  needed  to determine  the  bacterial content of  groundwater taken from
 wells  close  to area streams, since these streams  and buried valley aquifers
 are  usually  hydraulically connected.   Also, the infiltration of Scioto  River
 water, a significant portion of which  is WWTP effluent, could  have a negative
 impact on  the  groundwater quality.   However, groundwater pollution is most
 likely to  occur  in areas using shallow aquifers and in  such recharge sites as
 eskers, Kames, and outwash gravel  terraces.  These  aquifers  lying  close to
 streams or beneath inadequate septic  tanks  are highly susceptible  to
 contamination.

     All public water supplies downstream of Columbus along  the Scioto  River
 and  all private and industrial water consumption  in Columbus relies  on
 groundwater  sources.

     Various  studies of the Teays  aquifer were performed to  determine safe
 yields.  Safe  yield is the volume  of groundwater  that can be withdrawn  from an
 aquifer without exceeding the ability of natural  recharge (from surface water
 and other groundwater sources) to  keep the water  table constant over a  given
 timeframe,  typically 1 year.   The  city of Columbus  contracted with a private
 firm to install radial wells with  a safe design yield of approximately  30 KGD.
Four wells were eventually installed and 7-day, long-term pump  tests were
performed to determine the safe rate of withdrawal  (Francis  1987).   From the
                                    6-50

-------
 available data,  safe  design  yields  for  the  four wells  were  estimated  to range
 from 8.5 to  14.5 MGD,  for  a  total withdrawal  of 46 MGD (Hughes  1987).   The
 PAWTP  is designed  to  handle  roughly  150 MGD (Francis 1987),  allowing  for
 future expansion of the  well system  as needed.

     Because of  the importance  of the Teays aquifer and  the  lack  of available
 data,  the USGS is  currently  studying that portion of the  southern Franklin
 County aquifer that is directly affected by the reach  of  the Scioto River
 between the  Jackson Pike and the Southerly  WWTPs.  This  study is  intended to
 encompass groundwater quality from the Southerly WWTP  to  the PAWTP.  Areas
 under  investigation include  groundwater quality, surface  water  quality,  and
 the impact of Scioto River water on  the aquifer (Shindle  and Childress  1987}«
 This study should  provide  information on surface water impacts  to the
 groundwater,  recharge rates,  safe yields, and the physical parameters
 necessary to predict  the cone of depression created by a  pumping  source, as
 well as the  movement rate and chemical fate of groundwater contaminants.

     A cone  of depression describes  the shape that the water table takes above
 a groundwater pumping source.   The water table is lowered by the  removal of
 groundwater  and  rises back toward the surrounding water  table elevation as
 distance increases from  the  pumping  source.  Several sources observe that the
 Scioto River  recharges the aquifer upstream of the Jackson Pike WWTP,
 especially at some of the reservoirs, but they believe that  the stretch of the
 river between the Jackson Pike  and Southerly WWTPs is  sealed by industrial and
WWTP sludges  so  that little  flow between the Scioto River and the Teays
 aquifer occurs.

     However, a  tracer dye test  along this  stretch of  the river recently
demonstrated  an  outflow  of surface water from the Scioto  River  into the
groundwater.  These are  only  preliminary results, but  the effect  of Scioto
River water upon groundwater  quality and water table elevations may be  greater
 than previously  believed.  Since future increases in Columbus'  water demands
will have to be  met by groundwater pumping, both of these factors are
 important in considering the  one- and two-plant alternatives  for  Columbus'
WWTP options.
                                       6-51

-------
     At  this  point, no  significant  impacts to groundwater resources are
 anticipated from any of the alternatives.  A draw-down of groundwater
 elevations and drinking water wells occurred in 1986 to the town of
 Shadeville, a suburb of Columbus.  This was caused by a dry spell,
 construction  dewatering at the Southerly WHIP, and groundwater pumping from
 the PAWTP.  This caused the water table to drop about 8 feet leaving many of
 Shadeville's  wells inoperational.  To mitigate this problem, Columbus has
 extended water distribution mains to the Shadeville area.

 6.2.3.1  No Action
     The no action alternative, maintaining the status quo in the Columbus
 area, should  have no significant impacts on groundwater.  Even if the USGS
 groundwater study currently underway establishes there is a more direct
 connection between the  Scioto River and area groundwater, current groundwater
 quality at the city's wells remains good, even after several decades of
 potential influence from the Jackson Pike WWTP.

 6.2.3.2  Two-Plant Alternative
     The two-plant alternative is not expected to cause significant impacts to
 area groundwater resources, since WWTP discharge levels and any associated
 impacts will  remain similar to current practices.

 6.2.3.3  One-Plant Alternative
     Under the one-plant alternative,  the Jackson Pike WWTP effluent will be
diverted downstream,  leaving river water elevations during low-flow periods
between the Jackson Pike and Southerly WWTPs drastically lower than under the
 two-plant and no action alternatives.   These low-flow conditions will occur
during dry summer and fall months at the same time that groundwater
elevations are lowered by the reduction in recharge from precipitation
 (surface water infiltration),  other groundwater sources, and surface water
sources (impoundments,  wetlands,  and streams).
                                     6-52

-------
      If  connections between  the  Scioto  River  and  the  Teay  aquifer  are  more
 direct than  currently  believed,  groundwater elevations may become  lower  than
 they  currently  are and they  may  even become critically low during  extended
 drought  conditions,  requiring the PAWTF wells  to be  pumped above  safe design
 yields.  Since  any additional drinking  water  supplies required  to  meet
 Columbus' growing needs will be  drawn from groundwater sources,  long-term
 impacts  on the  radial  well system could include an increase in  capital and
 O&M costs as safe design yields  of individual wells are reduced  during dry
 periods, and additional wells are required to meet demands.

      Groundwater quality was not closely monitored by Columbus until
 groundwater was used as a component of  the municipal drinking water supply.  A
 monitoring system to sample  well water  on a periodic basis  is projected  to be
 in place by 1987 or 1988 (Button 1986).  Raw groundwater quality is superior
 to raw surface water sources used for drinking water purposes in Columbus;
 however, some non-health hazard  problems are present according to  data
 analysis of two PAWTF  well samplings.   Levels of hydrogen  sulfide, iron, and
 manganese are near or  above  water quality standards.  This  is one  reason lime
 soda  ash softening is  required to treat raw water to meet drinking water
 standards.

      Ranney field is located on a parcel of land known as Hartman  Farm.  A
 number of legal agreements have been negotiated between Columbus and the
 affected property owners on  this six hundred acre tract in  order to protect
 the city's drinking water supply (Briegel 1987).  Although  various agencies
 have  recommended land  use controls such as drainage retention basins that
would include a five to twenty-five square mile area surrounding Ranney  field,
 the city of Columbus has not adopted any well head protection laws (Kelly
 1987).

6.2.3.4  Conclusions
     When the USGS groundwater study mentioned above is completed  in 1988,
better data on the groundwater system will be available.   A more definitive
                                      6-53

-------
 evaluation should  then be  possible  of  future  impacts  from the  one-  and  two-
 plant  alternatives.   When  water  quality data  become available  at  the  end  of
 1987 or  in 1988, these data  compared to the USGS  findings will provide  an
 indication of  industrial and Scioto River  water impacts  upon groundwater
 quality.

 6.2.4  Air Quality/Odor
     Air quality impacts do  not  differ  significantly  among the various
 alternatives.  The most significant long-term impact  to  air quality will
 result from the operation  of the incinerators  as  a primary method for ultimate
 solids disposal.  The  current practice,  which  would continue under  the  no
 action alternative, consists of  incineration of approximately  25 dry  tons per day
 (dtpd) of  dewatered solids at Jackson Pike and 45 dtpd at  Southerly.

     Both  the one- and  two-plant alternatives  would result  in  a decrease  in
 the total  amount of solids incinerated  due to  the fact that anaerobic
 digestion  would be practiced and also because  the quantity  of  sludge  land
 applied would increase.  The engineering evaluation developed  the one-plant
 and two-plant alternatives to optimize  utilization of the  sludge reuse
 options.   The Southwesterly  Compost Facility was  assumed  to process 24  dtpd on
 an annual  average under both alterantives.  Under the one-plant alternative,
 25 dtpd would be land applied.   Under the two-plant alternative, 38 dtpd  would
 be land applied, approximately 25 dtpd  from Jackson Pike  and approximately 13
 dtpd from  Southerly.

     The two-plant alternative would decrease  the amount  of solids  incinerated
 at Southerly by about 70 percent  and the level of incineration  at Jackson Pike
would remain approximately the same.  The one-plant alternative will  phase out
 all operations at Jackson Pike and  Southerly incinerators will be used  to
 incinerate about 17 percent more  (to account for  the current amount
 incinerated at Jackson Pike) than current demands.  Current estimates of
 pollutants generated per ton of  sludge  incinerated are listed  in Table  6-15a.
Projected  air pollutant emissions associated with the no action, two-plant,
and one-plant alternatives are listed in Tables 6-15b, c, and d respectively.
                                     6-54

-------
            TABLE 6~15a.  ESTIMATES OF POLLUTANTS GENERATED PER TON
                              OF SLUDGE INCINERATED
                                   Estimated Emission Rate
                                    in lb/tonDry Solids
                                Jackson Pike        Southerly

     Particulate Matter              1.1                1.1
     Oxides of Sulfur                0.102              0.074
     Oxides of Nitrogen              2.18               2.18
     Cadmium                         0.011              0.013
     Lead                            0.037              0.028
     Mercury                         0.0065             0.0087
     Zinc                            0.327              0.24

Emission estimates are based on the  following:

     Particulate matter emissions are  limited to the Ohio EPA standard.  Other
     pollutants are estimated from the difference in the pollutant concen-
     tration in the sludge and ash of Jackson Pike and Southerly incinerators
     prior to emission controls.  However, oxides of nitrogen and sulfur
     oxides rates have been decreased by 80 and 50 percent, respectively, to
     account for the removal efficiency of the wet scrubbers.  Values for
     other heavy metals, organic matter, and pathogenic organisms are not
     available.  Source:  USEPA 1978
          TABLE 6-15b.  PROJECTED AIR POLLUTANT EMISSIONS ASSOCIATED
                               WITH THE NO ACTION ALTERNATIVE

                                  Estimated Emissions (Ib/day)
                                   No Action Alternative
                                Jackson Pike        Southerly
                                                    i
     Particulate Matter            27.5               49.28
     Oxides of Sulfur               2.55               3.3152
     Oxides of Nitrogen            54.5               97.664
     Cadmium                        0.275              0.5824
     Lead                           0.925              1.2544
     Mercury                        0.1625             0.3898
     Zinc                           8.175             10.752

Values are based on current production of 64 dtpd of dewatered solids and 70
percent incineration at Southerly, and 50 dtpd dewatered solids and 50 percent
incineration at Jackson Pike.
                                     6-55

-------
               TABLE  6-15c.  PROJECTED AIR POLLUTANT EMISSIONS ASSOCIATED
                                    WITH THE TWO-PLANT ALTERNATIVE

                                  Estimated Emissions (Ib/day)
                                    Two-Plant Alternative
                            Jackson Pike     Southerly     Total

     Particulate Matter         28.6          15.4        44.0
     Oxides of Sulfur            2.652         1.036       3.688
     Oxides of Nitrogen         56.68         30.52       87.2
     Cadmium                     0.286         0.182       0.468
     Lead                        0.962         0.392       1.354
     Mercury                     0.169         0.1218      0.2908
     Zinc                        8.502         3.36       11.862

Values are based on projected incineration of 26 dtpd of dewatered solids at
Jackson Pike and 14 dtpd of dewatered solids at Southerly.  Values for
Southerly will be higher when handling overflows from Jackson Pike.
          TABLE 6-15d.  PROJECTED AIR POLLUTANT EMISSIONS ASSOCIATED
                               WITH THE ONE-PLANT ALTERNATIVE

                                  Estimated Emissions (Ib/day)
                                   One-Plant Alternative
                            Jackson Pike     Southerly     Total


     Particulate Matter           0            58.3       58,3
     Oxides of Sulfur             0             3.922      3.922
     Oxides of Nitrogen           0           115.54     115.54
     Cadmium                      0             0.689      0.689
     Lead                         0             1.484      1.484
     Mercury                      0             0.4611     0.4611
     Zinc                         0            12.72      12.72

Values are based on the projected incineration of 53 dtpd of dewatered solids
at Southerly.

NOTE:  The one-plant alternative would generate a greater total amount of
       emissions per day than the two-plant alternative due to a greater
       quantity of solids being sent to incineration and a smaller quantity of
       solids being sent to land application.
                                     6-56

-------
      Portions  of Franklin County are designated as non-attainment of the
 National  Ambient Air  Quality  Standards (NAAQS)  for particulate matter.   In
 particular,  the  Jackson Pike  WWTP is located  in an area that  is designated as
 non-attainment of the secondary  standard,  and regions  north of the facility
 are  designated as non-attainment of the  primary standard.  Figure 6-4
 illustrates  the  pattern of NAAQS non-attainment areas.

      All  six incinerators (two operating incinerators  at both Jackson Pike and
 Southerly, and two permitted  incinerators  in  start-up  at Southerly)  are
 equipped  with  wet scrubbers designed to  reduce  particulate matter emissions  to
 meet  the  emission control standards imposed by  the State of Ohio  and  the
 Federal New  Source Performance Standards for  municipal  sludge incinerators.

      Odor problems have  historically plagued  southern Franklin County, with
 frequent  complaints of burnt  ash sewage  odors attributable to the
 incinerators,  earthy  raw sewage  odors  characteristic of Southwesterly
 composting operations, and a  septic sewage odor attributed to the  primary
 clarifiers and/or anaerobic digesters  at the  Southerly WWTP (McCarthy 1986,
 Bonk  1986, and Maxwell  1986).  Based on  the available data, it  appears that
 the Southwesterly Composting  Facility  is the  major cause of the odor  problems
 in Southern  Franklin  County.  Other odors may be due to a variety  of
 industrial and agricultural-related  sources,  as  identifed in  Table 6-16  and
 Figure 6-5.  This  figure  also identifies the  residential areas  that have
 registered the majority  of complaints  to local,  state, or Federal  agencies.

      Several odor  control-related procedures  or design improvements have been
 put into operation at Southwesterly.  However,  complaints are  still received.
Design changes recently  completed at  the Southwesterly composting  facility
 include addition  of a pug mill designed  to achieve  a better mix of wood  chips
and raw sludge and a  solar drying facility to control moisture content.
Additional improvement in the sludge may be seen with the implementation of
 the recommended additions to  the solids handling at the Southerly WWTP.
                                    6-57

-------
     JACKSON PIKE WWTP

     SOUTHERLY WWTP

     SOUTHWESTERLY  COMPOST FACILITY
                                 •—ALL AREAS INSIDE THE INTERSTATE 270 LOOP
                                    ARE DESIGNATED  AS  NON-ATTAINMENT OF THE
                                    SECONDARY STANDARD FOR TOTAL SUSPENDED
                                    PARTICULATES.
—  PLANNING AREA BOUNDARY
pi  DENOTES PRIMARY NON-ATTAINMENT AREA
                                       FIGURE 6-4
                                       NON- ATTAINMENT AREAS FOR
FOR TOTAL SUSPENDED PARTICULATE MATTER   TOTAL SUSPENDED PARTICULATES
                                 6-58

-------
   TABLE  6-16.   POTENTIAL ODOR SOURCES IN SOUTHERN FRANKLIN COUNTY,  OHIO


 1.    Franklin County  Replacement  Landfill:   3851  London-Groveport  Road

      Size:   118  acres
      Types of Waste:  municipal,  commercial,  industrial
      Opened:  August  1985
      Unaware of  any odor  problems

 2.    Model Landfill:  3299 Jackson Pike

      Size:   approximately 100+  acres
      Types of Waste:  municipal,  commercial,  industrial
      Closed:  August  1985.  Adequate cover.
      Odors are noticeable.  Methane gas recovery  is  proposed.

 3.    Jackson Pike Landfill:  2460 Jackson Pike

      Size:  approximately 30-40 acres
      Types of Waste:  municipal,  commercial,  industrial
      Operated from 1969 to 1978.  Adequate cover.
      In 1979 sludge from  the Jackson Pike Sewage Treatment Plant was stored
      on top.  Three to four feet  of sludge remains and is potential source
      of odors.

 4.    Columbus Municipal Refuse Electric Plant - 2500 Jackson Pike

      Six 238 million  BID  input coal or refuse derived fuel steam
      generating boilers.
      Air emissions control equipment include  cyclones with electrostatic
      precipitators.
      Refuse composition varies between summer and winter.
      Short-time storage of refuse may allow odors to become apparent.

 5.    Sloter's Demo Site:   South of Southview Park, East of 1-71.

      Size:  10 acres
     Types of Waste:  demolition
      In operation.
     A potential source of odor as material was dumped into water.

6.   Cowan's Demo Site:   South of Southview Park, East of 1-71.

     Size:  15 acres
     Types of Waste:   demolition
     In operation.
     A potential source of odor as material was dumped into water.
                                6-59

-------
TABLE 6-16.   POTENTIAL ODOR SOURCES IN SOUTHERN FRANKLIN  COUNTY, OHIO (CONT.)


7.   Craig's  Demo Site:  South of Southview Park, East of 1-71.

     Size:  15 acres
     Types of Waste:  demolition
     In operation.
     A potential source of odor as material is being dumped into water.

8.   Scott's  Demo Site:  1377 Harmon Road

     Size:  approximately 100+ acres
     Types of Waste:  demolition
     In operation.
     A potential source of odor as material is being dumped into water.

9.   J & B Mining:  3041 Jackson Pike

     Size:  approximately 20 acres
     Types of Waste:  demolition
     Opened in 1982 and is in operation today.
     Low odor potential.

10.  Loewendick's Demo Site:  715 Frank Road

     Size:  approximately 50+ acres
     Types of Waste:  demolition
     In operation.  Adequate cover.
     Low odor potential.

11.  Southerly Waste Water Treatment Plant - Portsmouth Cols. Road

     2 municipal sludge incinerators
     2 additional incinerators currently under construction
     Incinerators may result in odors.

12.  Southwesterly Composting - East of SR 104, south of SR 665.

     200 wet tons/day steady-state capacity
     300 wet tons/day short-term capacity
     Composting processes may result in odors.

13.  Jackson Pike Waste Water Treatment Plant - Jackson Pike Road

     2 municipal sludge incinerators
     Incinerators and digested sludge used in land application and may
     cause odors.
                                6-60

-------
TABLE 6-16.  POTENTIAL ODOR SOURCES IN SOUTHERN FRANKLIN COUNTY, OHIO  (CONT.)
14.  Inland Products, Inc. Rendering Plant - Frank Road and Scioto River

     Rendering process/product, tallow storage.
     Air emissions control equipment include air evaporator cooler with non-
     condensibles transferred to boilers for incineration, and chlorine
     scrubbing of all fugitive emissions.
     Typical processing time:  3 pm to midnight, 6 days per week.
     Control malfunctions may allow odors to escape.

Other regional potential odor sources include Columbus and S. Ohio Electric
Boilers in Pickaway County, Container Corporation Paper Plant in
Circleville, Mead Paper Plant in Chillicothe, and locations of various
agricultural activities.

Source:  McCarthy, 1986.
                                 6-61

-------
                                              V\   I1
                                          Fv8 Scott s Demo Site
                                          5^ir
                                                  Jackson Pike Waste Water Treatment Plan)
        & ££?}   "^'      iX
        M  Fnnklin County Reptacement Landfill
        :SX+'\^' \        I
                                                   r-11 Southerly Waste Water Treatment Plant
                                                        \
                                                12 Southwesterly Composting
* SITE OF NUMEROUS ODOR  COMPLAINTS
SEE TABLE 6-16 FOR ADDITIONAL
INFORMATION ON POTENTIAL SOURCES.
                                   6-62
FIGURE 6-5
LOCATIONS  OF  POTENTIAL
ODOR  SOURCES  IN SOUTHERN
FRANKLIN COUNTY

-------
      Recently the city has designated an Odor Control Committee comprised of
 city employees,  chemists,  and local residents.   The Committee has designed an
 odor control  action plan,  which involves the employment of an independent
 consultant to conduct a qualitative study of the problem,  with specific
 efforts aimed at correlating odor complaints with plant operations and
 meteorological conditions.  It is expected that with the results of these and
 other proposed studies,  the odor source(s),  including individual processes
 within a facility,  will be identified.   This knowledge can then be used to
 establish feasible  control measures designed to alleviate  or  substantially
 reduce the odor  levels.  This may be accomplished through  decreasing the
 emissions of  odorants and/or enhancing  the dispersion potential of the
 source.

 6.2.4.1   No Action  Alternative
      The  no action  alternative will result in continued use of both the
 Jackson  Pike  and  Southerly WWTPs,  with  only  normal  maintenance.

      Air  quality impacts of the no action alternative,  excluding odors, are
 essentially neutral  in that they do not degrade present ambient air quality.
 However,  this  alternative  does not provide for  further  progress toward
 achieving compliance  with  ambient  air quality standards for particulate
 matter.   Odor  impacts  from the no  action alternative  would be  represented by  a
 continuation of  current  problems.

 6.2.4.2   Two-Plant Alternative
     Direct air quality  impacts  associated with  the  two-plant  alternative will
 include short-term, adverse  air  quality  impacts  experienced during  the
construction phase of  the  project,  with  the generation  of fugitive  dust  and
 increased vehicular exhaust.   These  impacts will be concentrated  in the  locale
of both the Jackson Pike and Southerly  facilities.  Project specifications
will include provisions  for minimizing  such  impacts  through the  use of
 practical mitigating measures,  such  as watering  of haul roads  and exposed
soil.
                                     6-63

-------
      Operation of the two-plant alternative  is  not  expected  to  result  in  any
 long-term deleterious impacts on air  quality.   Based  on  current operating
 records,  the  operations  at  Southerly  produce approximately 64 dtpd  of
 dewatered solids,  of which  45 dtpd  are  incinerated.   The two-plant  alternative
 substantially decreases  the amount  of solids processed through  the
 incinerators  at Southerly due to the  incorporation  of anaerobic digestion in
 the  processing scheme.   An  approximate  70  percent reduction  in  the  amount of
 dewatered sludge incinerated compared with current  conditions would be
 observed.  Consequently, a  corresponding reduction  in air pollutant emissions
 from the  Southerly incinerators  would result.   The  two-plant alternative  would
 require sludge incineration at  Jackson  Pike  consistent with  current practice
 and  does  not  provide for further progress  toward achieving the  NAAQS for
 particulate matter.   Table  6-15  provides an  estimate  of  emissions from
 incineration  associated with the two-plant alternative as well  as the  one-
 plant and  no  action  alternatives.

     Odor  impacts  will not  occur as a direct impact of the construction phase.
However, operation of the two-plant alternative should result in a  reduction
 in ambient odor  due  to the  reduction  in the  usage of  the incinerators  at
Southerly which  should reduce  to some extent the occurrence  of  nuisance odors,
which are characteristic of burnt sewage odors.  The  25  percent increase  in
 the  amount of  solids composted will result in increasing the odor potential,
which may or may not be offset by process  changes,  renovations,  and  the
 installation of  new  units,  which are  expected to reduce  the  occurrence of
earthy sewage  odors  characteristic of this facility through  the reduction of
moisture and maintenance of  optimum temperature, pH,  and  oxygen content
through improvements to aeration and  dewatermg at  the Southwesterly
Composting.  However, the potential for odorous emissions from  the  operation
of the incinerators  and solids handling facilities  to impact local  residents
is dependent on meteorology.  Therefore, expected impacts of these changes on
the potential  for emissions  from these  facilities to result  in  nuisance odors
cannot be quantified without further  analysis.
                                    6-64

-------
 6.2.4.3  The One-Plant Alternative
     Direct air quality  impacts  associated with  the  one-plant  alternative  will
 include  short-term, adverse  air  quality  impacts  experienced during  the
 construction phase of the project, with  the generation of  fugitive  dust  and
 increased vehicular exhaust.  These  impacts will be  concentrated  in the  locale
 of  the Southerly WWTP and Southwesterly  Composting Facility.   Project
 specifications will include  provisions for minimizing such impacts  through
 the use  of practical mitigating  measures, such as watering of  haul  roads and
 exposed  soil.

     Direct impacts associated with  the  long-term operation of this
 alternative will include a decrease  in pollutant loading similar  to that of
 the two-plant alternative, and a local redistribution of pollutants.  The
 phasing  out of the Jackson Pike  facility and diversion of all  flows to
 Southerly will result in the  following impacts to air quality:

     •   The increased activity at Southerly will result in higher local  levels
         of ambient pollutants due to the increased quantity of sludge
         incinerated The Southerly incinerators would be handling an estimated
         53 dtpd of dewatered  solids  instead of the current value, 45 dtpd.
         This IS percent increase  in  the  volume of sludge incinerated at
         Southerly would result in an increase in air pollutant emissions.
         Likewise, there would be minor increases in emissions  of hydrocarbons,
         carbon monoxide, oxides  of nitrogen, and particulate matter from
         increased vehicular activity.
     •   Local air quality near the Jackson Pike  facility would  improve due to
         the reduction of emissions from  the incinerators.

     Because the Jackson Pike WWTP is located in a more industrial  locale, and
 in a region that exhibits a higher ambient level of particulate matter than
 that of  the Southerly WWTP, it may be concluded  that implementation of the
one-plant alternative may result in a benefit to local air quality  by more
widely distributing the industrial sources of particulates and  providing for
further achievement toward compliance with ambient air quality standards for
particulate matter.  However, without an in-depth modeling analysis, this
cannot be reliably predicted.
                                     6-65

-------
      Ambient odor impacts associated with the long-term operation of the  one-
 plant alternative are not readily discernible.   The  increase in the  quantity
 of sludge incinerated may be associated  with  a  higher  incidence of nuisance
 odors (characteristic of a burnt sewage  odor);  however,  it  is expected  that
 the operation of two new incinerators, which  will  be on-line at Southerly in
 the near  future,  will provide further process control  and  result in  a
 lessening of nuisance odor generation.

      Similarly,  an increase in the amount of  waste composted may be  associated
 with a higher incidence  of nuisance odors;  however,  proposed process changes,
 renovations,  and  the installation of new units  in  conjunction with this
 alternative  should alleviate to some extent the potential  for the generation
 of  nuisance  odors.   In particular,  the reduction of  moisture and maintenance
 of  optimum temperature,  pH,  and oxygen content  through  improvements  to
 aeration  and  dewatering  at the Southwesterly  Composting  Facility will reduce
 the  occurrence of  earthy sewage odors characteristic of  this facility.
 However,  the  potential for odorous  emissions  from  the operation of the
 incinerators  and solids  handling facilities to  impact local  residents is
 dependent  on  meteorology;  therefore,  expected improvements,  or the expected
 decrease  in  the potential  emissions  from these  facilities to result  in
 nuisance odors, cannot be  quantified  without  further analysis.

     At Jackson Pike,  it is  clear  that the  phasing out of operations  will
 result  in  reduced  emissions  of odorous compounds from the incinerators  and
 associated facilities; however,  this  area has not  been associated  with  a
majority of the recorded odor  complaints.

 6.2.4.4  Conclusions
     Air quality impacts do  not  differ significantly between the various
alternatives.  Pollutants  generated through incineration of  sludge will not
cause violations of NAAQS  beyond those currently found in the Columbus  area.
Odor problems should decrease  under either of the  action alternatives and may
increase slightly under no action.
                                     6-66

-------
6.2.5   Soils/Prime  Agricultural  Land
     The  physical and  chemical characteristics  of  local  soils  will  govern the
extent  of impacts from two segments of the  proposed  improvements  to the
Southerly and  Jackson  Pike WWTPs.  First,  the direct impact  of soil
disturbance  during  the construction of new  facilities and  the  removal  of
existing  facilities will  result  in exposure and  accelerated  erosion within the
limits  of the  project  site.   Second,  the  land application  of anaerobically
digested  waste activated  sludge  to agricultural  lands will modify the
composition  of the  existing soils.  The impact of  both segments of  the
project will involve areas that  have  been designated,  based  on soil
classification, as  "prime  agricultural" lands.

     The  land  application  of  anaerobically  digested  waste  activated sludge is
a well-known and accepted  method of solids  management.  Potential adverse
impacts of land application  include heavy metal  contamination, nutrient
overloading, and pathogenic contamination of soils;  however, if properly
regulated and  implemented,  these impacts are minimal  and easily controlled.
Potential benefits  to  the  affected lands include increased productivity  and
enrichment of  existing  soils.  In general,  the benefits greatly outweigh the
adverse effects.

     The OEPA  provides  oversight to the land application program, which
follows the  guidelines  presented in their Land Application of  Sludge Manual
(OEPA 19S5b).  Under this  program, the application rate is based  on both the
concentration of cadmium contained in  the sludge and  the physical and chemical
capacity of a given soil to assimilate this applied volume of  sludge.  The
assimilative capacity is soil specific; thus, it is  impossible to quantify
accurately the acreage of  land required for future land application needs.
The prime agricultural lands involved  in this practice will have  two short-
term restrictions placed on their potential uses.  First,  lac tating dairy
animals should not be grazed on  these  lands for one year.  Second,  vegetable
crops that may be eaten raw should not be grown on these lands for  I year.
                                      6-67

-------
 6.2.5.1  Ho Action Alternative
      This alternative would  involve  the  continuation  of  current  practices.  No
 new construction would occur,  therefore,  no  additional soil  erosion would
 occur due to construction.   The  current  solids management  program at Jackson
 Pike includes land application of  roughly half of  the sludge  produced  (25
 dtpd).   This practice has proven successful,  and no contamination or adverse
 human health problems have been  reported.  None of the sludge produced by  the
 Southerly WWTP is land applied.

 6.2.5.2   Two-Plant Alternative
      Under the two-plant alternative,  there  will be no additional land
 required  for construction of the proposed upgrading of the Southerly WWTP.  At
 the  Jackson  Pike  facility, an  additional  area of approximately 4 acres
 (southeast of  the  existing plant) will be required for new construction.
 This  additional area   is located on an abandoned ash  lagoon,  within the
 confines  of  an existing earthen  dike.  It is now covered by uncultivated
 vegetation and is  not  considered farmland or prime agricultural  land.  The
 area  is relatively flat;  thus,  extensive erosion during construction  should
 not  be a  serious  problem if proper mitigation procedures are  followed.

      Under this alternative, roughly 38 dtpd of sludge will be land applied,
 13 dtpd from Southerly and 25  dtpd from Jackson Pike.  Based  on  1985-1986
 cadmium concentration  figures  and a range of soil assimilative capacities
 typical for  this  region, an application rate of 3.4 to 5.1 dry tons per acre
 per year  can be estimated.  This results  in an annual land requirement of
 2,755 to  4,133 acres per year.   Comments  from OEPA and Columbus  indicate that
 site  lives will be  limited to  16 years because of zinc concentrations.  Based
on the city's  estimate of 200,000 acres available for land application within
40 miles, site availability should not be a problem.   As explained above,
current land application operations have proven successful with no reported
contamination or adverse health effects;  this performance should continue
based on current guidelines.
                                    6-68

-------
6.2.5.3  One-Plant  Alternative
      Under  the  one-plant  alternative,  the  quantity of sludge to be land
applied  is  estimated  at  25  dtpd.   As explained earlier,  based on 1985-1986
cadmium  concentration figures  and  a range  of soil  assimilative capacities
typical  for this  region,  it is estimated  that the  application rate will be
limited  to  3.4  to 5.1 dry tons per acre per  year.   Based on  these  application
rates, the  one-plant  alternative will  require 1,832 to 2,748 acres per year.
Based on the city's estimates  of site  availability and estimated quantity of
solids to land  application, no significant impacts are anticipated.

      No  significant impacts are forecast to  area soils or prime  agriculture
land  under  any  of the alternatives.

6.3   ENVIRONMENTAL  CONSEQUENCES -  BIOLOGICAL ENVIRONMENT
6.3.1 Terrestrial  and Wetland Biota/Habitat
6.3.1.1  No Action
      Implementation of the  no  action alternative and  continued operation  of
the Columbus wastewater facilities  should  not  create  substantial impacts  to
terrestrial biota.  However, some minor impacts may occur on  vegetation along
the Scioto  River  banks.   Nutrient enriched waters  may  support higher growth
rates of plants that  are  flooded periodically  by the  river,  thereby
increasing  the  food supply  of  wildlife feeding on  these  plants.  The Scioto
River is used heavily by  waterfowl, most of which  feed on plants.  These
animals would benefit from  nutrient enriched  waters (Watts 1987).  Waterfowl
also  use Scioto River waters for breeding  and  to escape  predators, and  these
activities  would  not  be affected by degraded  water quality from  the unimproved
treatment facilities  (Watts  1987).   The no action alternative will not impact
wetlands.

6.3.1.2  Two-Plant Alternative
      No impacts to  previously  undisturbed  terrestrial  habitat are  expected
under the two-plant alternative.  The two-plant alternative will not impact
wetlands.
                                     6-69

-------
 6.3.1.3  One-Plant Alternative
      Impacts  to terrestrial  habitat  and  biota  under  the  one-plant  alternative
 will  result  from:   1)  extension  of  the Interconnector  across  the Scioto  River
 and part  of  the flood  plain  and  2) elimination of  the  discharge from  the
 Jackson Pike  WWTP.

      Construction  of the  river crossing  will have  locally  significant impacts
 on terrestrial  biota,  primarily  vegetation.  The local fauna  will  be
 displaced, but  should  be  able to find refuge in similar  habitats nearby.

      The  banks  of  the  Scioto River in the vicinity of  the  river crossing are
 lined with trees indicative  of riparian  habitat.  Observation of the  site in
 January 1987  indicated the dominant  tree species were  red  maple (Acer rubrum),
 box elder (Acer negundo), and poplar (Populus  tremuloides).   Less  common
 species were  sycamore  (Platanus  occidentals)  and hackberry (Celtia
 occidentalis).

     The  stands of  trees on  the  east and west  banks differ in several
 respects.  Trees on the east bank form a swath about 10  feet  wide  bordering
 the river like  a ribbon.  The stand on the west bank is much  wider, extending
 about 400 feet back from the bank at the site of the crossing.  The floodplain
 on the west bank is broad and rises in elevation gradually with distance from
 the river.  The east bank is steep and resembles a levee or the cut bank side
 of a meander.  The  trees on  the east bank are considerably smaller in diameter
 and height than those on the west, and understory growth is denser on the east
 side,  indicating the east stand  is younger than the west.  Aerial photography
of the proposed crossing site, taken April 6, 1976, shows an  absence  of  trees
on the east bank and a fairly dense stand on the west bank.  This confirms the
youth of the east bank stand.

     It is possible that the land near the banks of the Scioto at the site of
 the river crossing could be classified as wetland.   The area  is subject to
 flooding of short duration (primarily from October to June); however, the
                                      6-70

-------
 soils  are not  listed  as  typical  of  those  that  support  wetland plants  or
 animals, in  the Franklin County  Soil  Survey  (Soil  Conservation Service  1980a).
 The west bank  more  strongly  resembles a forested  floodplain than the  east
 because it has larger trees  with little understory growth  or ground cover.
 Evidence of  overbank  flooding  on the  east  bank was apparent during  the  January
 1987 site visit because  the  shrubs  and grasses were uniformly flattened within
 approximately  20  to 60 feet  of the  bank.   The  east bank has been disturbed
 recently by  clearing  and farming and  is possibly  in a  transitional state.
 Areas  to the north  and south of  the east bank  river crossing bear a stronger
 resemblance  to a  typical forested wetland  and  have apparently not been
 disturbed as recently as the crossing zone.

     Based on  soils classifications and direct site  observations, the specific
 areas  to be directly  impacted  by  the  one-plant alternative  are  not considered
 to be wetlands.  Therefore,  the one-plant  alternative, as proposed, will have
 no significant impacts on wetlands.

     Construction on  the west  bank  will destroy trees of substantial age and
 size and disrupt a mature forest habitat.   Regrowth  to the  present state will
 take decades.  Construction on the  east bank will  have a less  severe impact on
habitat because the trees are  younger  and  the  stand  is much  narrower.
Regrowth to the present  state, based  on the aerial  photography mentioned
earlier, should require  approximately  10 years.  However, the east bank is
much steeper than the west and will be subject to  more severe erosion
problems until vegetative cover is  re-established.

     It is advisable  to  retain the maximum amount  of vegetation  possible on
both banks to reduce erosion.  When construction is completed, efforts should
be made to restore the river banks  to  their present slopes.  This will ensure
that a similar forest community will revegetate the area (see Table 6-14 for
additional mitigating measures proposed for the one-plant alternative).

     In addition to crossing the Scioto River,  pipes carrying flows from the
Interconnector sewer will traverse a  field, located to the north  of the
                                     6-71

-------
 Southerly WWTP,  in order to connect with proposed headworks.   The field,
 covering about 120 acres,  is owned by the city of Columbus, Division of
 Sewerage and Drainage,  and is currently leased to a farmer for crop
 production.   The field  is  considered prime agricultural  land,  but was not
 planted during 1986.  A site visit in January 1987 determined  vegetation in
 the field to be  dominated  by rapidly growing grasses and woody shrubs.  The
 condition of vegetation just behind the river bank indicated  the  field
 recently had been flooded.   Vegetation was flattened in  a range of 20 to 60
 feet  from the river bank.   Conversation with Southerly WWTP personnel during
 the site visit indicated flood waters may exceed  that distance during storms
 and that such flooding  was  not uncommon.

      Proposed activities in the field will result in removal of vegetation
 over  the trench  and construction easements.   Because the vegetation is  only 1
 to  2  years old,  it  will be  easily  replaced after  construction  is  completed.
 Similar  fields exist nearby and wildlife  in the area will not  be  forced long
 distances  to find  suitable  habitat.   Tree lines will be  left intact.

      Erosion of  soil poses  a  potential  threat  to  area habitat.  Construction
 should be undertaken during the summer  when rainfall and river flow are
 lowest.  The  field  should be  reseeded before the  weather becomes  too cold to
 prevent  rapid  regrowth  of vegetation.   Clearing the  field in portions would
 be  preferable  to clearing the  entire  field  at  once.   Recommendations  of the
 city  of  Columbus  for roitigative measures  pertaining  to this part  of
 construction are  listed on  page one  of  Table 6-14.

      The impacts on terrestrial habitat and  agricultural  land  from
 Interconnector construction are  considered minimal and can be  easily mitigated
 (see Table 6-14).   Any  additional  localized  impacts  resulting  from headworks
expansion of Southerly  are  also considered minimal and easily  mitigated.
Construction of the new  headworks will occur on the  existing plantsite.

     Elimination of Jackson Pike WWTP may  affect  birds near the plant.  A wide
variety of bird species, including several rare species,  have  been observed  at
                                     6-72

-------
 the  plant and  it  has  been  noted  as  a good  birding site  in Ohio (Thomson
 1983).  Great  Blue Herons  and  Belted Kingfishers  have been known to visit the
 ponds and settling basins  at the Jackson Pike  site and  the brushy edge
 vegetation  surrounding  the ponds provides  habitat for a variety of songbirds.
 The  sludge  ponds  are  visited by  shorebirds from April through  October.   Rare
 shorebirds  sighted here include  the Piping,  Lesser Golden, and Black-bellied
 Plouers, Red-necked Phalaropes,  and the  Long-billed Dowitcher.   A pond
 adjacent to the sludge  pond attracts waterbirds,  including the Blue-winged
 Teal, Wood  Ducks, and American Coots.  This  pond  also attracts shorebirds when
 the  water level is low.

     Effluent  from the  plant also provides river  habitat  for waterfowl  during
 the  winter  months when  the  reservoirs north  of  Columbus become  frozen.   It
 keeps the river water warm, making  it a  source  of food  and protection to
 migrating stocks  (Watts, 1987).   Closing Jackson  Pike would eliminate this
 habitat.  Because the Scioto is  a major  migration route,  the passage of birds
 is not likely  to change; however, their  distribution along the  river probably
 will change.  The distribution probably  will become more  dispersed.  Visits of
 rare birds  to  the area will decrease to  the  extent  that they are  presently
 attracted by open water habitat  provided during the winter.  Depending  on
 habitat requirements  of rare species, they may  find suitable habitat elsewhere
 or suffer mortalities.  The removal  of open water habitat  in the  Scioto River
 during winter, through elimination  of Jackson Pike  effluent, will  diminish
waterfowl visits in general.

 6.3.2   A^uaticJBiqta/Habitrat
 6.3.2.1  No-Action
     Water quality in the Scioto  River, between Columbus and Circleville, is
degraded by point source and general non-point  runoff from the metropolitan
areas.   The key water quality  problem is considered to be  low DO.  Although
 the low DO problem is clearly  related to discharges from  the Jackson Pike and
Southerly WWTPs (degraded fish populations have been associated with the DO
sags resulting from these two  point  sources), other sources contributing  to
the problem include the Whittier  Street CSO and general  urban runoff.
                                      6-73

-------
      Implementation of the no-action alternative  will  result  in  continuation
 of the current DO problems and related  aquatic  habitat degradation  in  the
 Scioto River below Columbus.   Impacts will  be most  severe  in  the summer, as
 the Jackson  Pike  plant is  currently unable  to meet  summer  ammonia limits and
 unable to  consistently meet summer  CBODc  limits.  Under this  alternative,  any
 significant  changes in DO  conditions in the Scioto  River below Columbus will
 be more directly  related to possible changes in the nature and amount  of
 Whittier Street CSO and urban  non-point loadings  (the  other principal  sources
 presently  contributing to  the  current DO  problem).   Because the  city of
 Columbus is  currently  studying the  CSO  problem  with the objective of
 decreasing the CSO related  pollutant loadings to  the Scioto River,  DO
 conditions in  the  Scioto River may  improve  in the future,  due  to factors
 unrelated  to the Jackson Pike  WWTP.   However, improvements in  DO conditions
 related to diminished  CSO  loadings  may  be at least  partially offset by
 increased  urban non-point  loadings  associated with  projected  future population
 growth  in  the  Columbus  area.

     Implementation of  the  no-action alternative will  also result in a
 continuation of the current problems related to the impacts of high residual
 chlorine in  the WWTP effluents  since Jackson Pike and  Southerly  have no
 dechlorination facilities.  In  the  event  that CSO loadings  from  Whittier
 Street  are decreased and DO levels  increase  in  the  Scioto  River  independently
 of  the  treatment plants, the impacts of the  continuing high chlorine loadings
 from Jackson Pike  and Southerly would represent a locally  significant  obstacle
 to  recovery  of the  aquatic habitat.

     Under the no-action alternative, pollution intolerant  species  will
continue to  be excluded from the affected reach of  the  Scioto  River due to
mortality,  lowered  reproductive success, and/or avoidance  (OEPA  1986a).  The
aquatic community will continue to be dominated by  a reduced number of
 tolerant species.    If water quality  conditions deteriorate  further  (as could
result  from  no change in either the  Jackson  Pike WWTP  or Whittier Street CSO,
but a general  increase in the Columbus area  population), pollution  tolerant
                                      6-74

-------
 species will  suffer  a  loss  of  biomass  followed  by a  loss  in density (OEPA
 1986a).  The  more  sensitive of the  tolerant  species  which would  be  lost  first,
 under  a scenario of  deteriorating water  quality conditions,  including the
 round  bodied  catostomidae,  basses,  crappies,  freshwater drum,  and catfishes
 (these species have  increased  their numbers  in  the Central Scioto over the
 past five  to  seven years, reflecting gradually  improving  water quality
 conditions during  this  time period).   Certain pollution tolerant species  may
 increase in biomass  and density with gradual  deterioration of  water quality,
 including  gizzard  shad, carp and  goldfish, and  the deep bodied suckers.
 Increased  hybridization would  also  be  experienced under the  conditions of
 biological stress  resulting from  a  decline in water  quality.   This  effect,
 combined with the  loss  of less tolerant  species  and  an increase  in  tolerant
 species, would be  reflected in a  general decline in  the biotic index.

     The benthic community  will respond  to the  scenarios  of  no change  or
 gradual deterioration  in water quality in patterns similar to  those discussed
 for the fish  community.  Mollusk  species are  extremely sensitive to wastewater
 effluent and  will  not be able  to  recolonize the  affected  segment of the Scioto
 River  under the no-action alternative.

 6.3.2.2  Two-Plant Alternative
     Upgrading both  treatment  plants will result  in  no effluent-related water
 quality violations and  subsequent water  quality  improvements.  Such action
 will have a favorable impact on aquatic  biota and  habitat.   Sensitive  species
 that currently inhabit  the  area should persist and increase  in abundance.  New
 species may move into the area and  increase community diversity.

     Decreased turbidity will  create a more favorable habitat  for turbidity-
 sensitive species.   These species,  such  as darters, which  now  inhabit  Scioto
River  tributaries,  may begin to move into the Scioto mainstream in  greater
numbers.

     Although violations in DO standards will not  occur under  the two-plant
alternative,  residual wasteloads in the  effluents  from both WWTPs will
                                     6-75

-------
 continue to exert a DO demand in the receiving water,  and  a  reduced  DO  sag
 will persist below both treatment plants.   As  a result,  fish communities will
 continue to show some degradation as oxygen levels  are depressed  downstream.
 These effects will be most  noticeable in  the sections  of the river where the
 residual DO sags are most critical (i.e., where DO  levels  approach 5.0  mg/1).
 Effects  of  degradation in fish communities  include  increased numbers of
 omnivorous  fish  relative to insectivorous fish,  increased  hybridization,
 (lowered biotic  index) and  decreased diversity.   In all  fish surveys conducted
 on  the Scioto River from 1979 to 1986,  degradation  of  fish communities
 occurred in the  vicinity of the DO sags associated  with discharges from the
 Jackson  Pike  and Southerly  WWTPs.   Although the structure  of the  benthic
 community will also improve under the two-plant alternative,  benthic
 communities will continue to exhibit decreased  abundance and diversity  in
 areas  experiencing the oxygen sag.

     Over the past 6 years,  the fish community  in the  Central Scioto has
 improved.  The two-plant alternative will result  in a  continuation and
 acceleration  of  this trend.   Although significant improvements will  occur, the
 collective, continuing impacts  of WWTP  effluents, general  urban runoff, and
 the Whittier  Street  CSO will  prevent free biological recovery in  the Central
 Scioto,  when  compared  with  comparatively unimpacted segments  upstream of
 Columbus  and  downstream of  Circlevilie.

 6.3.2.3   One-Plant  Alternative
     Aspects  of  the  one-plant alternative that will  impact aquatic habitat and
 biota  are the  following:  1)  elimination of  Jackson Pike WWTP; 2) upgrading
 and expansion  of  Southerly WWTP;  and  3) construction at Southerly WWTP.

     Between Jackson Pike and Southerly, the impacts of the one-plant
 alternative will be  strongly  flow-dependant.  Under most flow conditions,
elimination of the Jackson Pike effluent loading  will  result  in improved water
quality conditions,  to  the extent  that  this effluent affects water quality.
These improvements will result  in  favorable aquatic community responses, as
discussed under the  two-plant alternative.
                                     6-76

-------
     However,  under  low flow conditions,  pollutant  loadings  from background
 sources  (Whittier  Street CSO and  urban  runoff) will  persist,  while  the
 capacity of  the  river  to assimilate  this  wasteload will  be sharply  diminished,
 through  the  elimination of  nearly 90 percent of  river  flows.  Therefore,  under
 low flow conditions, it is  hypothesized that elimination of  the  Jackson Pike
 effluent will  result in degraded  water  quality conditions (see Section 6.2.1)
 and negative impacts on aquatic biota.  Although these impacts will likely be
 short-term,  dependant  on the length  of  any critical  low  flow conditions during
 summer months, the impacts  could  be  severe.  Because flow will be
 significantly  reduced,  aquatic species  forced to retreat to  pools will be
 especially susceptible  to impaired water  quality conditions which may develop
 at  low flow.

     A significant loss of  benthic habitat area  will result  from the reduction
 in  river flows.  Under  critical low  flow  conditions, riffle areas will be
 reduced, signficant areas of benthic habitat will be exposed  to  drying and
 pools could  become very shallow and  still due to the reductions  in  water
 levels associated with  the  elimination  of Jackson Pike flows  (see Section
 6.2.2).  These conditions could disrupt spawning, feeding, and migratory
 activities of  fish and  water levels.  Depending  on the length of  tune that the
 benthos  is exposed and  on the capability of individual species to withstand
 such impacts,  signficant  reductions  in  benthic productivity could occur in
 selected riffle areas of  the Scioto  River between Jackson Pike and  Southerly
 under the one-plant alternative.

     Downstream of Southerly, the impacts on the one-plant alternative on
 aquatic  fauna are difficult  to assess because expected changes in water
 quality have not been clearly described.  Because the level of wastewater
 treatment will be improved under  this alternative, concentrations in BOD and,
 to a lesser extent, NHo will be lower in the effluent.   However,  by routing
 all flows to Southerly, the entire residual wastewater DO demand  from Columbus
will be released to the river at a single location.   Because reductions in
nutrient concentrations in the effluent (other than ammonia) will be minimal,
                                    6-77

-------
 and because the total  volume  of wastewater  released  at  Southerly will be
 significantly increased,  without any  increase  in  river  flows below  Southerly,
 a proportionate increase  in residual  wastewater DO demand  from Southerly will
 result.  This residual DO demand will be  assimilated by  the river,  and & DO
 sag will be evident  in that portion of the  river  where  the DO demand is
 assimilated.   Although the 5.0  mg/1 DO standard will not be contravened, the
 length of  river affected  by the sag will  be  increased.  Because no  changes
 will occur  in flows, the  area of the  river  affected by  the DO sag will be
 extended in the downstream direction.

     Degradation of  aquatic communities can  be expected  in the vicinity of the
 DO  sag and  in the additional portion  of the  river that will become  exposed to
 a higher level  of water pollution.  Effects  of degradation have been discussed
 under the no  action  alternative and include  reduced diversity, higher
 percentage  of omnivorous  species  relative to insectivorous species, and
 increased hybridization (depressed biotic index).  It is possible that the
 Circleville Riffle will be  exposed Lo  higher levels of pollution.   Currently,
 the aquatic community  in  the vicinity  of  the riffle is considered to be in
 very good condition.   It  supports a high diversity of species.  In  the 1960s
 and 1970s it  was seriously  degraded and has  only  recently  recovered in the
 early 1980s.  These  factors indicate  the community may be  sensitive to habitat
 degradation.  It is  possible that this community  will experience degradation
 under the one-plant  alternative,  reversing the recent trend of improved
 conditions.

     Construction across  the river bed of the Scioto may have a localized,
 short-term but  severe  impact on aquatic habitat and biota.  Impacts will stem
 primarily from  increases  in sediment  transport and deposition downstream of
 the construction site.   Fish will suffer fewer short-term  impacts than benthos
as they can avoid the construction site, but stresses and  mortalities should
be expected.  Localized populations may be reduced if riffles used  for feeding
and spawning become covered with sediment.  Increased turbidity will also
temporarily damage habitat of species which use pools,  due to lowered oxygen
 levels caused by organic  loads associated with eroded soils.   The distance
                                     6-78

-------
affected and  the degree  of  stress  depend  on  the  amounts  of sediment which
will ultimately enter  the water; however, mitigation techniques  proposed  for
this project  alternative (see Table  6-13) should minimize  these  impacts.

     To minimize damage  to  aquatic biota, construction will  be scheduled  when
river  flow  is  low.  Also, construction during  springtime will be  avoided  not
only because  of potential high  flows, but also because most, if not all,  fish
in  the Scioto spawn at that  time (Yoder 1987b).  These and other  mitigative
measures proposed by the city of Columbus as part of the one-plant  alternative
are listed  on pages 2 and 3  of  Table 6-13.

6.3.3   Endangered Species/Habitat
6.3.3.1  Ho Action
     Terrestrial endangered  species  should not be affected by the no action
alternative.  However, the aquatic endangered  species habitat will  suffer due
to  continued  degradation of  water  quality.  Several  federal and state
designated  endangered and rare  fish  have been  sighted in the Central Scioto
River mainstem within the past  5 to  7 years and  those species are most likely
to  be disturbed.  The species are  the river redhorse, mooneye, goldeye, and
Tippecanoe  darter.  Poor water  quality will exclude  them from the affected
portions of the Scioto River through avoidance,  lowered reproductive success,
and/or mortality.  The degraded habitat will prevent  their populations from
growing in  the affected  areas.  The  shortnosed gar,  lake chubsucker, and
paddlefish  have been sighted in the  Central Scioto,  but generally favor a
habitat type not well-developed in the Scioto River.  This species  probably
would not establish a population in  the river even under natural  conditions
(Yoder 1987b).

     Small  populations of other endangered or rare fish live on tributaries  to
the Scioto River where water quality is better.  The Central Scioto River
mainstem potentially could provide habitat for these species, if  water
quality was improved.   Continued degradation of water quality will decrease
the chances for these fish to expand their ranges into the Scioto River.  The
restriction of available habitat will prevent populations  from increasing in
                                     6-79

-------
 numbers.   These species  include  the  bluebreast  darter,  slender  head  darter,
 spotted darter, and  blacknose  shiner.

      The  only  federally  listed endangered  fish  in  the area  is the  Scioto River
 madtom.   The   fish was last  sighted  in Big Darby Creek  in 1957,  although
 efforts to find it   were made as  recently  as  1981.   Implementation of  this
 alternative will probably  not have a direct impact on the fish,  if it  still
 exists in Big Darby  Creek,  but  it will preclude any potential  for the
 expansion of the  present  habitat.

      Several state endangered mollusks may inhabit Big  Darby Creek and the
 Circleville Riffle of the  Scioto  River.  They are native to the  Central Scioto
 River, but are  highly sensitive  to pollution  from WWTP  effluent  (Stansbury
 1986).  Continued degradation of  the Scioto River below the WWTPs  will depress
 the potential for these species  to re-enter their former habitat.  Based on
 surveys conducted from 1955  to 1970, species  that may currently  live in the
 region are the  cob shell,  Simpson's  shell, northern  riffle  shell,  fragile
heelsplitter, and ridged pocketbook  (Stansbury  1986, 1987).  Although  there
have been no recent  surveys  of the Scioto  River, a survey of Big Darby Creek
conducted within the past  3  years identified  the following  species:  smooth
minishell, smooth cob shell, northern club shell, fragile heelsplitter, and
northern  riffle shell.  A  few endangered mollusks have  occasionally been
sighted in the  Scioto River  in earlier surveys.

6.3.3.2   Two-Plant Alternative
     Endangered aquatic species should benefit  from  implementation of  this
alternative.  Improvements in water  quality should allow the fish  species that
have been captured in the  Scioto River (river redhorse, mooneye, gold  eye, and
Tippecanoe darter) to increase in abundance and allow those species inhabiting
tributaries (bluebreast darter, slenderhead darter,  spotted darter, and
blacknose shiner) to expand  their ranges.  Specific  information  on the
tolerances of these species  to turbidity and lowered DO is  not available,
preventing an assessment of  the conditions under which  these species would
establish permanent breeding populations.  Increased habitat for feeding,
                                      6-80

-------
 however,  should benefit populations.   Improved water quality in the Scioto
 River  may increase potential  for the  Scioto raadtora population to expand its
 numbers and  range.

     Mollusk populations should benefit from this alternative because it could
 offer  them an expanded habitat and therefore the  opportunity to increase in
 abundance.   Because they are  sensitive to  WWTP effluent,  they would most
 likely move  into areas further downstream  from outfalls.   As larvae, the
 unionid mollusks are carried  to new environments  on gills of fish.   Little
 information  is available on suitable  fish  species,  but  freshwater drum is
 believed  to  be one such species (Stansbury 1987).   Freshwater drum  is a
 pollution sensitive species.   The  potential  for increased numbers of
 freshwater drum in response to improved water  quality also may play a role in
 the migration of mollusks.

 6.3.3.3   One-Plant Alternative
     Long-term impacts of this alternative stem from:   1)  modified  water
 quality below Jackson Pike  and Southerly,  and  2)  reduction in flow  between the
 Jackson Pike  and Southerly  WWTPs.   Short-term  impacts stem from construction
 at the Southerly WWTP site.

     Below Jackson Pike,  water quality will  be  somewhat improved under  most
 flow conditions.   These  improvements may encourage  rare,  threatened and
 endangered aquatic  fauna to increase in range and abundance,  entering the
 Scioto River  from tributaries  or less  impacted  river areas further  downstream.
 Species most  likely  to migrate  from downstream  areas include  the river
 redhorse, mooneye, goldeye, and Tippecanoe darter.  Species most likely to
move into the  river  from tributaries include the bluebreast slenderhead and
 spotted darters,  and  the  blacknose  shiner.

     Under the one-plant  alternative,  however,  the  critical  low flow condition
will be the limiting  factor on  re-colonization  of the Upper Scioto  River
 (between Jackson Pike  and Southerly) by rare, threatened, and  endangered
species.   Because of  the  nearly 90  percent reduction in river  flows  which will
                                    6-81

-------
 result  from this  alternative  during  low  flow conditions,  residual DO demands
 from other  upstream  sources (urban lunoff  and  the Whittier Street CSO) will
 result  in degraded water  quality  in  shallow, still pools  during warm weather.
 Under these conditions, the sensitive  species  will be  reduced  or eliminated,
 cancelling  the benefits to water  quality which will occur under higher flow
 conditions.

      The nearly 90 percent reduction in river  flows between Jackson Pike and
 Southerly under low  flow  conditions, will  exert additional negative impacts on
 aquatic fauna due to the  physical effects  of reduced flows and diminished
 habitat area.  Of the species mentioned above, the river  redhorse is thought
 to be particularly sensitive  to slow and intermittent  flows.  Reduced
 velocities associated with low flow  could  stress this  species and possibly
 limit its range.  Because many of the  species  feed in  riffles, drying out of
 riffles also could hinder the movement of  these species into the affected
 river segment.  Unionid mollusks  favor riffle  habitats and require shallow to
medium depth, fast flowing water  for feeding.  Should mollusks move into the
 area, a dryout could cause mortalities and stress the  population.
 Reproduction of mollusks  is dependent on swift currents and fertilization
occurs in fall.  It is possible that low flow  conditions  could prevent
 permanent expansion of the mollusk population  into this reach of river.

     Construction at the Southerly WWTP may threaten endangered terrestrial
and aquatic fauna.  The loss of trees along the Scioto's  banks may damage
 potential habitat for the federally  endangered Indiana Bat.  The bat nests in
shaggy barked trees, preferably the  shaggy barked hickory, along river banks
 in summer.   Because the bat has been sited recently in nearby Pickaway County,
precautions should be taken to protect its nesting habitat.  Tree removal
associated  with implementation of the one-plant alternative, if selected,
should be timed to avoid the May  through August (Multerer 1986) nesting
periods.  Because this alternative would result in an  insignificant
incremental reduction in habitat area available to this species throughout its
range, this potential impact is considered minimal.
                                      6-82

-------
     Endangered  fish with  the  greatest  potential  to be effected by
construction  at  Southerly  include  those most  recently  found  in the area:
river  redhorse,  mooneye, and goldeye.   These  species are  all highly sensitive
to  turbidity.  It  is likely that individuals  will  be able to avoid the  area,
but if not, they raay be stressed or  suffer mortalities.   The Tippecanoe
darter may be at risk  if sustantial  quantities of  sediment are carried  as  far
downstream as the  Circleville  Riffle.   However, this darter  has  not been
sighted above Circleville  for  the  past  5  to 7 years.   Should sediment
concentrations increase markedly in  lower Big Walnut Creek,  the  resident
population of slender-head darters might  be disturbed, as  these  darters are
also highly sensitive  to turbidity.  Because  most  of the  endangered fish spawn
in spring, construction should not be scheduled at  this time.  Mitigative
measures outlined  by the city  of Columbus indicate  construction  will proceed
during a low flow  period, which should  not coincide  with  spawning.   The impact
of construction  on fish should be  temporary and should not prevent  these
species from expanding their ranges  and numbers once the habitat recovers
(Yoder 1987b).

     Because no  mollusks are believed to  live in the Scioto  River near  the
Southerly WWTP,  construction should  not be problematic.   In  surveys  conducted
between 1953 and 1970, mollusks were found on the Circleville  Riffle and in
the banks of lower Big Darby Creek.  The riffle is known  to  support
populations of rare, threatened, or  endangered fish  and may  support  some
unionid mollusks (Stansbury 1987).   Should sediment  be transported  down to the
riffle, mollusk  populations may be harmed by  increased turbidity.   Estimates
of sediment transport associated with construction are not available; however,
it is considered unlikely that any signficant impact would be  felt  in the
Circleville Riffle.

6.3.4  Conclusions
     No impacts  to terrestrial and wetlands biota/habitat will occur as a
direct result of either the no action or two-plant alternatives.  Under the
one-plant alternative,  minimal impact will occur for potential habitat  of the
                                     6-83

-------
 Indiana Bat,  an endangered species.   Wetlands  habitat  is  not  impacted  by  any
 alternative.

      The one-plant  alternative will  require  removal  of a  narrow  band of
 forested area on both  sides  of the Interconnector  crossing of the  river.  This
 impact  will remove  mature  trees  on the west  bank and younger  specimens on the
 east  bank.  Although the removal of  forest habitat is  signficant and long term
 locally,  the  increment  is  quite  small regionally and the  overall impact is
 considered minimal.

      Any direct  impacts associated with construction of the one-plant
 alternative are  easily mitigated.  The city  of Columbus has proposed an array
 of mitigation measures which will minimize the potential  impacts of
 construction.

      Elimination of the Jackson  Pike WWTP under the one-plant  alternative will
 remove  a localized  area of attraction to waterbirds, shorebirds, and
 songbirds, including several rare species.   These  birds are presently
 attracted by  the ponds and settling basins,  the brushy  edge vegetation
 habitat,  and  the open water  of the Scioto River, which  is prevented from
 freezing  during  winter by  the warm effluent.  The  Jackson Pike site is popular
 as a  birding  site due to the variety of species which may be observed  at  this
 location.

     No  significant additional changes in aquatic  biota/habitat  will occur
 under the no  action alternative,  although little recovery of the currently
 degraded conditions is expected.

     Under the two-plant alternative, improvements in aquatic biota/habitat
will occur below Jackson Pike and Southerly.  Because of the impacts from
 remaining pollutant sources upstream of Jackson Pike (urban runoff and CSOs),
 the greatest  improvements in aquatic biota/habitat will be realized below
 Southerly.
                                    6-84

-------
      The one-plant alternative will improve water quality below Southerly,
 compared to the no action alternative,  but  to a lesser extent than the two-
 plant alternative.   This  comparatively  reduced beneficial impact results
 from a greater residual wasteload demand  discharged at Southerly under the
 one-plant alternative  and the enlarged  resulting DO sag,  compared to the one-
 plant alternative.   It is possible that this enlarged  sag may extend to
 Circleville and interfere with existing point source dischargers in the
 Circleville area.

      Below Jackson Pike,  water quality  would be improved  under most flow
 conditions,  resulting  in  an  average improvement in aquatic habitat/biota.
 However,  under critical low  flow conditions,  the continuation of extreme low
 river flows,  resulting from  the loss of the Jackson Pike  effluent  and  the
 remaining background loadings  of pollutants (urban runoff and CSOs)  may result
 in short  term but  severe  water quality  stress.   This stress will result in
 critical  impairment of aquatic habitat/biota  and will  be  the  dominating factor
 in the  riverine ecology between Jackson Pike  and Sourtherly during the
 critical  warm weather  season.

      The  reductions in river  flows,  resulting from elimination of  Jackson Pike
 effluent  under the  one-plant alternative, will  further limit  aquatic
 biota/habitat  below Jackson Pike through  removal of physical  habitat.   Because
 critical  low  flow  in the  river below Jackson  Pike will be reduced  by nearly
 90 percent under the one-plant alternative,  aquatic  habitat will be  impaired
 through exposure to drying and reductions in  the volume of remaining aquatic
 habitat.  These  impacts will be  especially  severe in shallow  riffle  areas.

 6.4   ENVIRONMENTAL  CONSEQUENCES  - HUMAN ENVIRONMENT
 6.4.1   Planning and Land Use
 6.4.1.1  No Action  Alternative
     Under this alternative, use of the Jackson Pike and  Southerly WWTPs would
 continue with  only  minor maintenance.  No land  acquisition or  zoning changes
would be necessary  and, therefore, no impact would  be  anticipated.
                                      6-85

-------
 6.4.1.2   Two-Plant Alternative
      No  land  acquisition  or  zoning  changes will be  required under  this
 alternative.  Under  this  alternative, a  smaller portion of the Southerly site
 would be used for wastewater facilities  than under  the one-plant option.  As
 previously explained this  land has  already been purchased and disturbed during
 construction  to meet compliance wil.h water quality  standards by 1988.  In
 addition, there will be some expansion near the southeast corner of  the
 existing Jackson Pike facility.  This land is owned by the city, is  vacant,
 and is not slated for other  development.

 6.4.1.3   One-Plant Alternative
      No  land  acquisition or  zoning  changes will be  required under  this
 alternative.  Under  the one-plant alternative, a larger portion of the
 Southerly site would  be used  for wastewater treatment facilities than under
 the two-plant option.  The land required for these  facilities already has been
 purchased by  the city and was disturbed and graded  as the city pursued
 construction  to meet  compliance by  1988.  The one-plant alternative  will
 require  expansion of the river crossing.  The necessary land is already owned
 by the city and was  previously disturbed.  Upgrading of these facilities may
 disturb  day-to-day farming activities of several farms located on Route 665;
 however,  these effects will  be short-term and minimal.

 6.4.2  Noise
 6.4.2.1  No Action Alternative
     The no action alternative would not involve new construction or its
 associated noise impacts.   Noise from the regular operation of the Jackson
Pike and Southerly WWTPs would continue at current levels.  These are not
considered a nuisance at this time.

6.4.2.2  Two-Plant Alternative
     Ambient noise levels near both treatment plants will increase during
construction activities.  As mentioned above, construction specifications will
                                    6-86

-------
minimize these effects.  Operational noise is not expected  to be a  nuisance.

6.4.2.3  One-Plant Alternative
     Ambient noise levels in the area will increase during  construction.  The
one-plant alternative will result in the concentration of construction
activities at Southerly and therefore increase noise levels at that location.
However, project construction specifications will include provisions for
minimizing these short-term impacts, and, in accordance with standard
practice, all construction activities will be performed during regular working
hours and all vehicles will be equipped with mufflers.  Noise associated with
operation of the improvements to wastewater treatment facilities at the
Southerly WWTP will occur due to the operation of the machinery and traffic
serving the facilities.  These increases are not expected to be a nuisance to
nearby residents.

6.4.3   Public Health
     Adequate disinfection of the effluent from sewage treatment facilities is
critical for the protection of public health.  Untreated effluent can result
in the release of pathogenic microorganisms capable of causing widespread
outbreaks of disease.  Current disinfection practices at both the Southerly
and Jackson Pike WWTPs are successfully controlling the release of pathogenic
microorganisms to the Scioto River, as evidenced by low effluent fecal
coliforra counts.  Treatment levels are expected to improve slightly with the
upgrading of facilities under either the one- or two-plant alternatives.

     Land application of anaerobically digested sludge is a widely practiced
method of sludge disposal.  The primary public health concern regarding this
disposal method is the entrance into the food chain of contaminants contained
in the applied sludge.  The state of Ohio has issued strict guidelines
regulating this practice in order to protect public health interests.
Adherence to these regulations under either the no action, one-plant, or two-
plant alternatives is expected to protect the public from any adverse health
effects.
                                      6-87

-------
6.4.4  Energy Use
     The energy requirements associated with the upgrading of facilities at
Jackson Pike and/or Southerly WWTPs include:

     •  Gasoline and diesel fuel for construction equipment and for hauling of
        solids to landfill, land application, or composting.
     •  Electric power for the operation of pumps, aerators, miscellaneous
        plant equipment, and heating and cooling.
     •  Methane gas (produced by anaerobic digestion) for use as an energy
        supplement within the plants.

     The impact of these energy requirements is not projected to deplete local
reserves significantly.  Current requirements will increase slightly under the
two action alternatives as flows increase.  The one-plant alternative is
estimated to require 10 to 20 percent less energy than the two-plant
alternative due to efficiencies of scale.

6.4.5  Economics and Employment
     Employment levels at the two treatment plants under the no action
alternative would remain constant at approximately 212 persons.  Employment
requirements are estimated at 135 people for the one-plant alternative and 191
people for the two-plant alternative.  The two-plant alternative requires less
personnel than the no-action due to more efficient computerized control
equipment.  Employment requirements are the least under the one-plant option
due to economies of scale.  These differences are reflected in annual
operation and maintenance (O&M) estimates.

     The economic impact in the Columbus area of combined capital and O&M
expenditures would be roughly similar under the one- and two-plant options.
The no action alternative would not provide economic benefits from these
expenditures.  Quantification of indirect economic benefits cannot be
performed at the current level of project planning and financial analysis.
                                     6-88

-------
6.4.6   Historic/Archaeologic Resources
     Neither the no action nor  the  two-plant  system alternatives will  have
direct impacts on known historic resources.   However,  the one-plant option
could impact an archaeologic site at  the point of  the  river crossing.

     Archaeologic surveys were  performed in 1985 by Dr. John Blank in  order  to
evaluate impacts from site work planned by Columbus to meet 1988 compliance
with water quality criteria.  During  Dr. Blank's Phase I and Phase II  survey,
four sites not eligible for the National Register were identified within the
boundaries of the Southerly WWTP site.  Dr. Blank recommended a further (Phase
III) archaeologic survey.  However, at a meeting in March of 1986 the  Ohio
Historic Preservation Officer (OHPO)  approved the initiation of site work
necessary to build improvements to comply with water quality limits at the
Southerly WWTP; this work has since been completed.  Additional construction
under the one-plant alternative may still require a further (Phase IH)
investigation.  The OHPO has been contacted to determine the need for  this
work.  At this time, no significant impacts are expected, since documentation
and recovery of these sites will mitigate potential impacts.

6.4.6.1  No Action
     The no action alternative will not involve new construction at either
WWTP.  No impacts to known or unidentifed archaeologic resources are
anticipated.

6.4.6.2  Two-Plant Alternative
     Impacts to archaeologic resources at the Southerly WWTP under the two-
plant option will be minimal.   During 1985 Dr. Blank,  Professor of Archaeology
at Cleveland State University, surveyed the Jackson Pike WWTP site.  Dr. Blank
estimates that Jackson Pike was built on approximately 20 feet of fill
material, isolating any archaeologic  resources below from disturbance.  For
this reason the two-plant alternative should have no direct impact on
archaeologic resources at Jackson Pike.
                                     6-89

-------
 6.4.6.3  One-Plant Alternative
     Construction at  the Southerly WWTP under this alternative is not expected
 to disturb archeologic resources  identified during surveys in 1985.

     The one-plant alternative  involves extending four 78-inch gravity sewers
 across the Scioto River.  This  may directly impact at least one known
 archaeologic site.  The Ohio State Historic Preservation Officer recommends an
 archaeoLogic survey of the site to determine if this site is eligible for the
 National Register of Historic Places.   Since Dr. Blank's original survey
 uncovered previously unknown sites at the Southerly WWTP site, it is probable
 that construction activities associated with the extension of the gravity
 Interconnector Sewer may also disturb unknown resources in the area.  An
 archaeologic investigation of all potential construction areas, including
 temporary roads and rights-of-way, within the path of the gravity sewer should
 be undertaken to ensure that these activities do not adversely impact unknown
 archaeologic resources since these are predicted to occur frequently in this
 area.

 6.4.7   Recreation
     Direct impacts on recreational use of the Scioto River are expected to be
minimal under either of the system alternatives.  Under the one-plant
 alternative, discharges currently returned to the river at the Jackson Pike
WWTP will be shifted to the Southerly WWTP and discharged downstream.
Watershed models indicate that  this change in discharge location only will
 affect the water elevation of the river during low-flow periods.  The lower
 section of the Scioto is generally shallow, slow-flowing, and lacking in
 aesthetic and other qualities that promote recreational use on the northern
 section of the river.  Minor impacts on water elevation will not change the
current uses of this area.   These include mostly duck hunting and fishing.
Boating in this area is largely limited to infrequent canoeing due to water
depths, which average 3 feet.   None of the alternatives are expected to alter
 these patterns of use significantly.  Fishing on this section of the river,
while not as frequent as in areas north of the Greenlawn Dam, is directed
 toward species adapted to the aquatic ecosystem existing here.  The one-plant
                                      6-90

-------
alternative, while occasionally  lowering  the river elevation minimally,  is not
expected to cause so prolonged or significant an impact as  to alter  the  basic
ecology of the area and thereby  affect recreational use of  the Scioto River.

     Neither of the project alternatives will affect the park acquisition and
conservation easement program, which the city of Columbus is undertaking on
the lower Scioto River in accordance with the "Watercourse Plan for Columbus
and Franklin County.

6.4.8   Transportation
     Direct impacts of the proposed project alternatives on vehicular
transportation in the Columbus area will involve short-terra effects on traffic
flow due to construction.

6.4.8.1  No Action Alternative
     The no action alternative will not produce short- or long-term primary
impacts, leaving circulation patterns in their current status.

6.4.8.2  Two-Plant Alternative
     Under the two-plant alternative, short-term construction impacts can be
expected at both the Southerly and Jackson Pike facilities, related to
construction vehicles and employees.  These effects will be marginally greater
at the Jackson Pike site due to  the more congested traffic patterns in the
downtown area.  In neither case will impacts be significant enough to affect
the level of service in the area.  Under the two-plant alternative, no off-
site construction is anticipated that would impact vehicular flow.

6.4.8.2  One-Plant Alternative
     Transportation impacts of the one-plant alternative will be concentrated
at the Southerly plant during the construction process.  Short-term increases
in traffic may occur, but are unlikely to affect the level of service on State
Route 23, which is currently functioning well.
                                    6-91

-------
     Some disruption of traffic flows along State Route 23 and intersecting
roads may occur as connections are made from the Jackson Pike WWTP to the
Southerly WWTP, but the use of proper traffic management should minimize this
over the affected period.

6.4.9  Conclusions
     None of the alternatives are anticipated to cause significant impacts to
planning or land use.  No land acquisition or zoning changes will be
necessary.  With the one-plant alteinative, the land necessary for a river
crossing is already owned by the city of Columbus.

     Ambient noise levels near the Jackson Pike and Southerly WWTPs will
increase during construction.  The one-plant alternative will result in a
concentration of construction activities and related noise at Southerly.
Operational noise is not expected to be a problem.

     Both the one-plant and two-plant alternatives will provide for the
adequate disinfection of wastewater.  The no action alternative would prove
slightly less reliable than either action alternative.  No significant public
health impacts are expected.

     All alternatives will result in energy usage, however, no alternative is
projected to deplete local reserves signficantly.  Construction equipment will
use gasoline and diesel fuel, while electric power is necessary to operate
plant equipment.  The one-plant alternative should require less energy due to
efficiencies of scale.  However, it is not possible to qualify this at the
facility planning stage.

     The city currently has approximately 212 employees operating its
wastewater treatment plants.  Under the no action alternative, these
employment levels would remain constant.  Employment levels are reduced to 191
employees under the two-plant alternative due to the proposed installation of
computerized control equipment.  The one-plant alternative has the lowest
manpower requirements (135 employees) due to efficiencies of scale.
                                     6-92

-------
     The three system alternatives will  not have  direct  impacts  on known
historic resources.  However,  the one-plant option  could  impact  an
archaeologic site at the  point  of the  river crossing.  Additional  survey work
is suggested for all construction areas  to ensure construction activities do
not disturb archaeologic  resources.

     Direct impacts on recreational use  of the Scioto River are  expected  to be
minimal under a one-plant or two-plant option.  None of  the alternatives  are
expected to alter present patterns of  river use.
                                       t-

     Direct impacts of the proposed project alternatives on vehicular
transportation in the Columbus  area will involve  short-term effects on traffic
flow due to construction.

6.5  ENVIRONMENTAL CONSEQUENCES - SECONDARY IMPACTS/INDUCED GROWTH
6.5.1  Secondary Impacts;  Growth and Development
     Sustained growth in  the Columbus metropolitan  area is projected through
2008.  Upgrading existing wastewater facilities will accommodate this growth.
This discussion centers on secondary impacts projected to occur as part of
forecast growth.  Secondary impacts are defined as  indirect or induced
changes in population and economic growth or land use as well as other
environmental impacts resulting from these changes  (USEFA 1975a; USEPA 1975b).
Secondary impacts from induced growth include: 1) increased demand for public
services; 2) increases in non-point source pollution and erosion and runoff
created by disturbances of stable areas; and 3) increased fiscal outlays
required to mitigate other secondary impacts,  that  is, provide additional
services.

6.5.1.1  No Action Alternative
     Market demand for housing  in the Columbus area, demonstrated by low
vacancy rates,  increased housing and office space costs, as well as a large
number of subdivision and building permit requests  are expected to remain
                                      6-93

-------
high.  This demand for residential, comraerical, and industrial uses is
concentrated  in  the parts of Columbus that already have water and sewer
service.  Local  planners feel that  this demand will continue well into the
future.  Since federal law mandates compliance with provisions of the Clean
Water Act by  1988, the no action alternative is not considered a viable
option.

6.5.1.2  One-Plant and Two-Plant Alternatives
     Although some interceptor sewers in the Columbus area are nearing full
capacity and  future growth could be restricted in some service areas, this BIS
cannot assess the capacity or potential for growth inducement of these lines,
since plans for  suburban interceptor expansion are not yet finalized.
However, some of the growth projected in the northwest section of Franklin
County may not occur if interceptor lines do not improve.

     In general, during past studies of growth inducement, in those areas of
the country where no sewer service existed or expansion of trunk or sewer
interceptor lines increase service areas, the act of providing sewer service,
the location and size of treatment plants, as well as sewer interceptor
routes was found to potentially induce growth or redirect development.
However, since the Columbus area already has sewer service provided by two
major treatment  plants and 3,735 miles of sewer lines, and locations and
sizes of new interceptors are not finalized, the secondary impacts of
upgrading both of the existing treatment plants or phasing out one plant in
order to expand  the other will be limited.  For these reasons, growth
projections, dispersement of the projected population, and the size of the
future service area will not be affected by the one- or two-plant
alternatives.

     Several factors have influenced growth and development in the Columbus
area over the past 20 years.  These include the following growth determinants:

     •  In-place linkages to interstate transportation systems:  railroads,
        highways, and major airports
                                     6-94

-------
     *  Availability of public  facilities, primarily water and sewer
     •  Public policies encouraging economic growth and development
     »  Public policies regarding public land use regulation and  taxation
        (fiscal) policies
     •  Public perception of suburban amenities, such as schools  and parks.

     As long as the Columbus economy is strong and continues to expand, and as
long as vacant land is available, the northern suburbs of Columbus will
continue to grow (see chapter 4).  Developers and local residents find this
section of the county to be most attractive because of its readily available
recreation resources, existing  public services, fine public schools, and close
proximity to the Columbus central business district (CBD).  Although some
infilling has occurred, the city is also expanding its boundaries through
annexation in the northwest sector of the county.  This is an area where the
incorporated areas of Dublin and Milliard are also expanding their boundaries.

     Although State law limits  annexation to contiguous parcels of land (land
adjacent to the established corporate limits of a city or village) the
political boundaries of the city of Columbus are not compact.  The city has a
checkerboard pattern of annexation.  Other incorporated areas in Franklin
County have similar disjointed municipal boundaries.  Most of these
municipalities use annexation to gain the fiscal benefits of new commercial,
industrial, and residential developments.  In the city of Columbus, developers
usually negotiated for water and sewer service.  In these cases, water and
sewer service was withheld until proposed developments were annexed into the
city.

     This reactive method of providing essential services has resulted in an
inefficient pattern of development.  The Office of Strategic Planning
recognizes these inefficiencies and is encouraging infilling.  Infilling is
the process of developing vacant parcels of land that are surrounded by
developed parcels of land.  Most of the growth projected for the planning
                                     6-95

-------
period can be accommodated by these vacant parcels of land located near the
Columbus city limits.  Table 6-17 shows  that this type of infill annexation
has already started  to occur.

     One community most likely to absorb secondary impacts from upgrading of
existing facilities  is New Albany.  This community is inside the future
service area, but outside areas presently served by water and sewer.  As
discussed in chapter 2, strict septic system requirements are limiting growth
in this area to single homes on large lots of approximately 1 acre or more.
Once water and sewer is available, the average residential development in the
area will probably shift to one-quarter acre lots.  This will reduce both
housing and development costs.  Columbus has no plans to extend sewer
interceptor lines into the rural areas adjacent to New Albany (Joyce 1987).

     The most obvious impacts of continued forecast growth will be degradation
in air and water quality and the increased demand for public services
together with the increased taxes and user fees required to finance these
services.  Section 6.5.4 discusses the impacts of growth on community
facilities.  These facilities include transportation, public utilities, police
and fire protection, and public education.

6.5.2  Secondary Impacts:  Air Quality/Climate
     This section presents an assessment of the impact of anticipated
population and related commercial and industrial growth on the ambient air
quality and climate in the Columbus area.

6.5.2.1  Secondary Impacts:  Air Quality
     Since portions of Franklin County have been designated as non-attainment
for total suspended particulates, the impact of projected growth on future
ambient particulate concentrations was assessed.  Overall population increases
in the study area, with or without improved wastewater treatment facilities,
are not forecast to differ significantly.  The analysis presented, therefore,
reflects impacts from overall population growth, rather than any incremental
increases due to the proposed project.
                                     6-96

-------
            TABLE 6-17.  ANNEXATIONS THAT HAVE OCCURRED IN COLUMBUS
                                  1984-1986
 Number of
Annexations
    1
    3
    4
Townships
                                     1984
Franklin TWP
Mifflin
Perry
Norwich
Sharon
Plain
Jackson
Violet, Fairfield Co.
Blendon
Clinton
Praire
              Acres Annexed
              By Townships
                 .98
                8.4
              125.451
                4.260
              212.662
              111.8
               23.157
                4.86
                 .13
                4.9
                2.09
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                      Acres
                                             1984 Total:   493.837 Acres
                                     1985
    1
    4
    2

    3
Perry
Sharon
Franklin
Blendon
Norwich
Praire
Plain
              340.63  Acres
               73.436 Acres
               18.188 Acres
               15.902 Acres
              250.001 Acres
                1.65  Acres
              200.00  Acres

1985 Total:   899.807 or 892.961 Acres
No. of Acres Annexed by TWP
                  1986
    3
    1
    2
    4
Franklin
Sharon
Perry
Clinton

Blendon
Mifflin
Praire
Norwich
Plain
Truro
                6.6   Acres
               12.92  Acres
               40.57  Acres
              983.197 Acres (940.8 Ohio
                       State University)
               12.79  Acres
                      Acres
                5.18
                2.167 Acres
              156.57  Acres
               37.618 Acres
                 .528 Acres

1986 Total:  1256.81  Acres
                                      6-97

-------
     Growth forecasts (see chapter 4) show a 10 percent growth rate for the
period  1988 to 2000, and a 20 percent increase from 1988 to 2015.  This
population growth will be accompanied by increases in particulate generating
activities such as residential and commercial fuel combustion, automotive
exhaust, tire and brake wear, and solid waste burning.  The effect of the
increased particulate loading will depend primarily upon the local
meteorological conditions; however, in order to estimate impacts it may be
assumed that these growth rates would be accompanied by a corresponding
increase in particulate emissions.

     The Ohio EPA (OEPA) operates several monitoring sites for total suspended
particulates throughout Columbus and the metropolitan area.  The monitoring
sites closest to the two wastewater treatment plants are located at Woodrow
Avenue, about 1.5 miles northeast of the Jackson Pike WWTP, and Dennis Lane
in Grove City, about 5 miles west-southwest of Jackson Pike.

     The monitoring locations closest to the high growth areas as outlined in
Figure 4-3 are Maple Canyon in the northeast, South Hamilton Road in the east-
northeast, Dennis Lane, Grove City in the southwest, and Cranston Drive in the
northwest.  Assuming for simplicity that each of these high growth areas will
experience one-fourth of the expected increase in population and an associated
increase in ambient particulate matter levels, and furthermore, that the
Woodrow Avenue area would experience a like increase in particulate matter
levels, yields the following:

TABLE 6-18.  CURRENT AMD PROJECTED LEVELS OF TOTAL SUSPENDED PARTICULATES
                       DUE TO POPULATION GROWTH (ug/m3)
            Monitoring        Avg.        1985      1988      2008
             Station          Time
            Maple Canyon
            So. Hamilton
24-hr
Annual
24-hr
Annual
131
49.3
92
47.0
133
50.0
93
47.7
135
50.7
94
48.3
                                    6-98

-------
24-hr
Annual
24-hr
Annual
24-hr
Annual
74
36.8
93
38.6
132
49.5
75
37.4
94
39.2
134
50.3
76
37.8
96
39.7
136
50.9
TABLE 6-18.  CURRENT AND PROJECTED LEVELS OF TOTAL SUSPENDED PARTICULATES
                     DUE TO POPULATION GROWTH (ug/m3)  (CONT.)
            Monitoring        Avg.        1985      1988      2008
             Station          Time
            Cranston
            Grove City
            Woodrow
                                                                 «i
     All values are well below the secondary standards of 60 ug/m  for the
annual period and 150 ug/m  for the 24-hr average.  Therefore, it is expected
that air quality impacts due to project-related growth will not contribute to
the exceedance of any air quality standards, add to the local non-attainment
areas, or inhibit progress toward achieving ambient air quality standards.
     In reality, however, it is not expected that particulate matter levels
will increase at the rates estimated above.  Data compiled by Ohio EPA (1985a)
for the years 1976 to 1985 have shown a significant reduction in the levels of
suspended participates throughout Ohio.  Percent improvements are shown in
Table 6-19 below.  Data have been grouped according to whether an area is
considered urban or rural, and population- or source-oriented, indicating the
presence or absence of nearby major pollutant sources.

              TABLE 6-19.  PERCENT IMPROVEMENTS BY SITE CATEGORY

       Site Category                                     % Improvement
Urban/Source-Oriented                                          39
Urban/Population-Oriented                                      38
Non-Urban/Source-Oriented                                      36
Non-Urban/Population Oriented                                  31

     Similar levels of improvement have been monitored at sites near the
service area.
                                      6-99

-------
6.5.2.2   Secondary Impacts:  Climate
     Since  the population growth and development are expected to change the
result in 24 hour or annual average air quality only slightly, it  is very
unlikely that growth will contribute to changes in the climate of  the area.

6.5.3  Secondary Impacts;  Water Quality
     To the extent that growth in the Columbus area can be related  to the
proposed project, secondary impacts on water quality in the FPA can be
expected.   However, the project is not projected to change the specific
locations and levels of local growth because the location of new or expanded
interceptors is presently unspecified.

     Based on the current pattern of population distribution and growth
trends, generalized areas within the FPA have been identified where future
growth is probable.  These generalized areas are depicted as "High  Growth
Areas" in Figure 4-3.  These growth areas can be grouped into four  general
zones, based on watersheds, for the purpose of indirect water quality  impacts
discussions.  Moving clockwise around Columbus, the four general  growth
impact zones are the Big Walnut Creek basin, including Blacklick Creek  and
Alum Creek; a small area draining directly to the lower Scioto River,
southeast of Grove City, in Jackson Township; the Big Darby Creek basin; and
the upper Scioto River, including the Olentangy River.

6.5.3.1  Secondary Impacts:  Water Quality - Big Walnut Creek
     Growth projected for this drainage basin occupies the northeastern and
eastern fringes of the Columbus metropolitan area, roughly following the
Route 270 corridor (see Figure 4-3).  This growth will directly affect
the headquarters of Big Walnut Creek, Blacklick Creek, and Alum Creek.  Water
quality impacts will include those typical of urbanization:

     •  Modified hydrograph (higher peak flows, lower base flows) and bank
        erosion
                                      6-100

-------
     *  Elevated turbidity, dissolved solids, and sedimentation
     *  Elevated water temperatures
     •  Increased organic load (higher BOD, COD, TOG, and nutrients) and
        decreased DO
     •  Elevated levels of non-point toxics (pesticides, herbicides, and
        complex organic compounds)
     •  Increased coliform bacterial levels.

     The extent of these impacts will be dependent on the rate and degree of
urbanization actually realized and on the extent to which stream management
practices are integrated with this growth.

     Current information is inadequate to determine either the quantities of
particular pollutants, or the specific impacts of these pollutants.  However,
all three streams comprising the Big Walnut Creek system are already subject
to water quality deterioration due to urban point sources and non-point source
loadings (see Section 2.3.5.2).  The projected growth pattern in this stream
system will aggrevate existing DO, ammonia, and fecal coliform problems.
Although existing water quality degradation in the upper portions of the Big
Walnut Creek system will be exacerbated by projected growth, the lower
sections of this stream system are not projected to experience high growth
rates (Figure 4-3).  Consequently, some water quality improvement will occur
(from natural wasteload assimilative capacity in the stream) before Big
Walnut Creek enters the Scioto River.  The extent of this improvement, and
the degree of possible impacts on the Scioto (resulting from any residual
wasteload in Big Walnut Creek discharge) cannot be quantified with the
currently available data base.

6.5.3.2  Secondary Impacts:  Water Quality - Lower Scioto
     A small area east of Interstate 71, north of Route 665, south of
Interstate 270, and west of the Scioto is projected for high growth
(Figure 4-3).  This area drains directly to the Scioto through a series
of small streams, including Grant Run and other unnamed permanent and
                                    6-101

-------
intermittent drainages.  Although the streams will be severely impacted by the
same generic water quality effects of urbanization cited in the preceding
discussion, these small streams are not known to represent significant aquatic
habitats within the FPA.

     Because of the proximity of this area to the mainstern Scioto, little
natural wasteload assimilation will occur prior to the release of any urban
pollutants to the river; therefore, caution should be exercised during
development of these areas to control non-point runoff.  The current data base
is not adequate to quantify potential impacts on the Scioto from this area.

6.5.3.3  Secondary Impacts: Water Quality - Big Darby Creek
     High growth rates are predicted to occur on the west and southwest
fringes of the Columbus metropolitan area, outside of Interstate 270, north of
Interstate 70, and south of Interstate 40 (see Figure 4-3).  Generic water
quality impacts will be as cited for Big Walnut Creek.

     This growth zone is concentrated in the Hellbranch Run subdrainage basin
of Big Darby Creek.  Hellbranch Run occupies a predominantly north/south
orientation, approximately midway between Interstate 270 and the mainstem of
Big Darby Creek, discharging to Big Darby Creek at the Interstate 71 bridge
(immediately north of the Franklin County/Fickaway County Line), north of
Harrisburg.

     Because most of the growth in this zone will be captured by the
Hellbranch Run subbasin, impacts on Big Darby Creek upstream of the confluence
of Hellbranch Run will be minimal.  However, Hellbranch Run will be directly
impacted by the projected growth in this zone.  Due to the projection of high
growth along much of the stream's length, water quality in Hellbranch Run is
expected to exhibit significant deterioration over time.

     Big Darby Creek currently exhibits "exceptional" water quality (see
Section 2.3.5.2).  Upstream of the confluence of Hellbranch Run, little change
is expected based on the current projection of growth in this zone.  However,
                                      6-102

-------
Big Darby Creek will be impacted by gradually deteriorating water  quality
discharges from Hellbranch Run due to  the  small  flow  from Helibranch Run,  in
comparison with Big Darby Creek, and the high water quality in Big Darby
Creek, the severity of impact should be small.   After  the confluence of
Hellbranch Run, Big Darby Creek flows  more than  25 miles before discharging
to the Scioto River.  Therefore, Big Darby Creek water quality is  expected to
recover from the impacts of future growth  in Hellbranch Run before joining
the Scioto River and little or no impact will be evident in the Scioto
itself.

6.5.3.4  Secondary Impacts:  Water Quality - Scioto/Olentangy Rivers
     High growth is predicted for the  north and  northwest fringes  of the
Columbus metropolitan area along the Scioto and  Olentangy river mainsterns
(Figure 4-3).  General water quality impacts will include those cited
previously for Big Walnut Creek.  Because  this growth  is predicted to occur in
the immediate proximity of the Scioto  and Olentangy mainsterns, urban
pollutants will enter these streams with little  if any attenuation.

     Water quality in the sections of  the Scioto and Olentangy affected by
growth in this zone exhibit some degree of urban pollution; however,
conditions have improved in recent years (see Section  2.3.5.1).  The degree to
which growth impacts will arrest or reverse this trend or the degree to which
water quality impacts will carry to more critical downstream areas in the
Scioto cannot be accurately determined with the  currently available data base.

6.5.4  Secondary Impacts;  Community Facilities
     In rapidly growing metropolitan areas such  as Columbus there  are two
requirements in providing adequate community services.  The first  involves
maintenance of the existing facilities; the second involves expansion of these
services to meet increasing demands.

     There are a number of ways to finance facilities  to meet increased
service needs.  These include:
                                     6-103

-------
     •  Increasing existing  fees and charges
     *  Increasing income and property taxes
     •  Assessing impact fees on developers
     •  Assessing new fees and taxes Cor special districts
     *  Issuing bonds for capital improvements
     »  Coordinating service delivery among local municipalities
     •  Expanding the tax base.

     One of the primary methods used to finance services in the Columbus
region has been expansion of the tax base via annexations.  While expanding
the tax base, new growth in these areas places demands on existing services.
If fees or taxes are inadequately assessed, the supply of community facilities
is adversely affected.  Older facilities and services may not be properly
maintained or supported, and the demand for new facilities and services may
not be provided for in a timely manner.

     In the Columbus area, demand for services has increased as each community
has expanded its boundaries.  Many services are currently at capacity and are
showing signs of deterioration or stress.  The services and resources with the
greatest potential for impacts from sustained growth are listed below:

     •  Public water and sewer
     •  Roads and highways
     •  Public schools
     •  Fire and police protection
     •  Cultural resources.

6.5.4.1  Secondary Impacts:  Community Facilities - Public Water and Sewer
     The city of Columbus provides water and sewer service to most of Franklin
County.  Parts of this system were installed as early as 1935.  The Columbus
Infrastructure Report included in Appendix N lists the location of sewer and
water lines along with associated problems with each system.  Almost 4,000
miles of sewer and water lines must be maintained throughout the Columbus
system.  Although developers usually pay for the installation of sewer
                                    6-104

-------
interceptors, the city must include operation and maintenance charges  in  its
rate structure.  As the system ages and  its size increases, operation  and
maintenance costs also increase.  Projected growth will  increase  the number of
system users.  The impacts of maintaining other operations are discussed  in
the Columbus Infrastructure Report.  This report indicates that each
community will have significant  funding  shortfalls and that new revenue
sources must be tapped in order  to maintain this system.  The report urges an
increase in user charges and assessment  fees to cover operation and
maintenance costs.

     Aside from maintaining a system of  water lines, the city is  also
responsible for maintaining adequate water supply reserves.  Columbus
currently draws 95 percent of its drinking water from surface water supplies.
As mentioned in the water quality section (Section 6.5.3), increased
recreational use and development heightens the potential for runoff into these
waterways.  As described in the  city's watercourse plan, providing a buffer
will limit the impacts of future development.

     A recently completed water  supply study prepared by the State of Ohio for
Columbus (Witlatch & Martin 1985) confirms that the city can meet its water
supply needs through the early 1990*s.   This study recommends, however, that
additional sources be found.  The city has four deep water wells.  In order to
meet growth demands, the city may need to add more wells in the future.

6.5.4.2  Secondary Impacts:  Community Facilities - Transportation
     No secondary impacts on transportation are anticipated as a  result of
this project under any of the alternatives.  As previously described, the
Columbus area is active and growing.  Road capacity problems currently exist
in several areas; some will be addressed under planned and/or programmed
transportation improvements.  Future growth and development will  aggravate
existing traffic capacity problems.  However, none of the proposed
alternatives will result in growth that  is more extensive or earlier than
that currently anticipated.
                                      6-105

-------
     The  level of service provided by the Columbus area highway system appears
 to be adequately meeting current needs of the system, although some roads in
 some communities are approaching capacity.  While data were not available to
 precisely quantify the  levels of service, experts as well as previously
 referenced documents (see chapter 2) indicate that level of service capacity
 has been  reached in some communities and is approaching capacity in others.
 Qualitative conclusions as to level of service are summarized in Table 6-20.

     Table 6-20 identifies a poor level of service for highways in
Westerville.  A major factor contributing to this over-capacity condition is
 limited east/west access to 1-71 from the entire community, resulting in
severe traffic congestion.  This traffic condition is reported to occur even
during non-rush hour periods.  As indicated in Table 6-20, Dublin also is
experiencing traffic congestion.  Dublin is a relatively small community with
a recent history of rapid growth where road systems are not adequate to
handle the increased traffic.  New Albany is projected to experience the same
type of growth as Dublin, and it is reasonable to expect that the same type
of traffic congestion experienced in Dublin will occur in New Albany as
development proceeds.

     In looking at the general results of levels of service estimates, it
seems reasonable to conclude that in many cases highway/road capacity has been
reached without regard to additional growth anticipated in the future.  It is
also clear that growth is anticipated to continue and that the proposed
project is only one factor in determining the magnitude of that growth.  It
does not appear from the available information that the implementation of the
project will increase growth beyond that already projected.

6.5.4.3   Secondary Impacts:  Community Facilities - Public Education
     Franklin County has 17 independent school districts including Columbus.
Each district operates its own schools and raises the funds to finance these
schools through local property taxes.  Most of the schools in high growth
areas such as Dublin, Westerville, Worthington, and Hilliard are at capacity
and will require expansion in the near future.
                                     6-106

-------
                    TABLE 6-20.  CURRENT LEVELS OF SERVICE*
                               Highway  (federal,
Incorporated Area           state, and interstate)         County Road
Dublin                              D - E                      D - E
Westerville                           F                        E - F
New Albany                          C - D                      C - D
Hillard                             D - E                      D - E
Reynoldsburg                        D - E                      D - E
Pickerton                           D - E                        -
Gahanna                             D - E                      D - E
 Levels of Service Definitions:
                                  Definition

A -  Highest quality of service that represents free traffic flow,
     indicates no restrictions on operating speed.

B -  Stable traffic flow with few restrictions on operating speed.

C -  Stable flow with high traffic volume and more restrictions on speed
     and lane changing.

D -  Approaching unstable flow with little freedom to maneuver.

E -  Unstable flow, lower operating speeds than level D, short headway,
     and accident potential high.

F -  Forced flow operations where highway acts as a storage area and
     there are many stoppages.
Source:  Institute of Traffic 1976.
                                     6-107

-------
     These areas may be  forced to  increase their property taxes in order to
pay  for  new schools.  Added  to other public  improvement needs  the tax rate
may  need  to be increased, or  taxpayers may be forced  to decide between school
improvements or roadway  improvements.  One method of  lim ting  educational
costs that is being considered by  the city of Columbus would be to request
that developers dedicate parcels within new  developments for future
neighborhood schools.  Table  6-21  lists the  enrollment figures, existing
capacity, and other parameters for each school district.

6.5.4.4   Secondary Impacts:  Community Facilities - Firt- and Police Protection
     In  1977, MORPC prepared  two reports:  one addressing police protection
and  the other addressing fire protection (Mid-Ohio Regional Planning
Commission 1977b).  Neither of  these studies have been updated.  Both of
these reports indicated  that  providing adequate police and fire protection
for  the Columbus area would   require increased coordinat-on of services and
additional manpower.  These   reports found that the inconsistent pattern of
annexation by Columbus  disrupted the delivery of these Hervices.  The
problems referred to in  these  reports have  not been directly addressed in the
intervening 10 years.

     Some efforts have been made to mitigate problems.  Columbus is currently
recruiting and training  new police and fire  fighters, and has plans to open
four new fire stations in the next three years.  These stations will be
located in  the northern sections of Columbus where most of the new service
demands associated with rapid growth have occurred.  In addition, Franklin
County plans to make 911 service available by the end of 1987.  However, as
these efforts have gone on, new problems have arisen.  In order to cut the
costs of increased service demands, some smaller communities have dropped
their police forces without making contractual arrangements with Franklin
County for protection.  Although this does not leave a community unprotected,
it does change the type of service provided.  A comprehensive community
services plan, sound financial planning, and increased coordination of
services to the various communities would lessen the negative  impacts of such
changes in service.
                                     6-108

-------
TM£6-21.  SCfflX
198WL987
School
Districts
*8exley
Canal Winchester
Cblutbus
1935/86 1986/87
Broil- Etaroli-
|||^ |f- |||i^^
2,072 2,058
954 990
66,823 66,153
4,363 5,181
R>. of
Schools
Currently
at
Capacity
0
0
All 7
Student
Teacher
Ratio
15:1
18:1
20:1
24:1
Opened Naw
Facility
or He-
opened Old
Facility
in 1986
—
0
1-Utfer
Nunber
at leased
Class- New
rooiB Facilities
1986/87 Flamed
-
0
I School
Construction 14 tenp.**
*GEhama-Jeffezson
(kandvieu tfeigits
Qtjveport-tedison
Hamltm
JL Billiard
"^dcenrgtm
Plain
*&synoldsburg

Southwestern
Upper Arlington
Wastemlle


Whitehall
Wbrthmgton


^Currently working
**]n nost cases a t£
5,223 5,306
1,216 1,234
5,969 6,024
2,077 2,127
4,342 4,523
3,513 3,709
882 849
4,445 4,474
-"
16,035 15,931
5,053 5,105
11,034 11,440


3,378 3,400
7,841 8,336


Otl S~fll? M*f^L lOTl S&X
snporacy structure
4
0
0
0
All 9
2
0
All 7

15
2
All 16


0
All 12


lies and/or
is a portal
23:1
15:1
20:1
24:1
19:1
25:1
18:1
22:1

19:1
21:1
25:1


22:1
24:1


projected
-
-
1-Reopened
-
0
-
0
-

-
-
-


-
2N=w


enrollnEnt
-
-
-
-
-
-
0
-

-
-
20 tenp.** 1
3
2
-
2
1

_
0
31988
Bldgs.
-
-
-
-
11988
Bkfc.
0
1 1990
Expansion
-
-
Expansion
Bldg. 1988
Ex. 1987
-
Bldg. 1988
Flaming
Stage
figures developed by SAUC
Recently
Issued or
Under- Pending
ttf-iliaert Bond
Eainlitl6S TsfflP
• _
X
X
X

_
X
-
X
X
— —
X
X

-
X
X


X
X


personal interviews.
tfo. of
ELaiEntary
Schools
3
I
80
5

5
2
6
2

3
1
4

15
4
12


4
8



N3. Of
Muddle
Schools
1
26
1

2
1
2
1

1
1
2

5
2
2


2
3



N>. of
Higi
Schools
1
I
15
1

1
1
2
1

1
1
1

3
1
2


1
1



Vocational
or Special
BicaCLcn
—
8

1
-
1
—

_
-
—

2
—
I


_
1



>le classroom.

-------
 6.5.4.5   Secondary  Impacts:  Community Facilities - Cultural Resources
      Secondary  impacts on historic  resources could occur as a result of
 changes  in  land use and zoning patterns as well as changes in the evolution of
 neighborhoods during the growth process.  Historic resources have been
 inventoried in  the  study area.  Land use changes may affect historic
 properties adversely in numerous ways without stringent zoning codes, zoning
 enforcement, containment of strip commercial and zoning map changes.

     As communities grow and expand outwards from the central core,
 neighborhoods lying between the commercial business core and new suburban
 communities often go through a period of decline.  Many of these older homes,
 particularly in the midwest, are of historic significance.  Examples of
 historically significant communities are areas of American bungalows and
 neighborhoods of turn-of-the-century catalog homes.  During the cycle of
 neighborhood decline there is a tendency for greater absentee ownership,
 and lack of basic maintenance and repair.  Moreover, without stringent zoning
 enforcement, neighborhood integrity can decline as former dwelling units are
 turned into marginal business locations.  In addition, during new suburban
 development, many older estates or  farms are sold to developers.  Without the
 capacity within the local community to inventory significant farms or estates
 of historic interest, many of the original estate/farm homes will be
 demolished to make way for suburban progress.

     To minimize loss of historic resources, Federal Community Development
 Block Grant Funds could be applied  to inventory older neighborhoods of
 indigenous American architecture and draft public policies for preserving
 these resources.  Ohio Historic Inventory Districts that may be impacted the
most by induced growth are districts:  1-4, 8-10, 15-17, 20, and 22.

     As described in chapter 2, archaeologic sites have been found to be
 nearly continuous along the floodplain and on adjacent bluffs along the Scioto
 River in the area of the Southerly WWTP.  Since insufficient data have been
                                     6-110

-------
collected and inventoried, knowledge of prehistoric culture along  the  Scioto
River and within the study area is not complete.

     Increased urban development along the Scioto River  in the vicinity of  the
Southerly plant may increase the disturbance of unknown  sites.  As part of  the
recreation plan for the Scioto River, conservation of the southern Scioto
riverbanks is recommended as a means of mitigating secondary  impacts on these
resources.

6.5.5  Conclusions
     Growth forecasts show a 10 percent growth rate for  the period 1988 to
2000 and a 20 percent overall increase from 1988 to 2015.  This population
growth will be accompanied by increases in particulate generating activities
such as residential and commercial fuel consumption, automotive exhaust, tire
and brake wear, and solid waste incineration.  Calculations were made based on
the project growth rates.  Based on this analysis, it is expected that air
quality impacts due to project related growth will not contribute to the
exceedence of any air quality standards, add to the local non-attainment
areas, or inhibit progress toward achieving ambient air  quality standards.

     Since the population growth and development are not expected to result in
a violation of ambient air quality standards, it is unlikely  that growth will
contribute to changes in the climate of the area.

     Based on the current pattern of population distribution  and growth
trends, four generalized areas have been identified where future growth is
probable.  These growth areas are grouped in four zones based on watersheds
for the purpose of water quality analysis.  Water quality improvement is
anticipated to occur in the Big Walnut Creek before it enters the Scioto.
Little natural wasteload assimilation will occur in the  lower Scioto prior  to
the release of any urban pollutants to the river, therefore,   caution should be
exercised during development of these areas to control non-point runoff.  Big
Darby Creek currently exhibits exceptional water quality upstream of the
confluence of Hellbranch Run and impacts from development in  Hellbranch Run
                                     6-111

-------
will be mitigated prior  to Big Darby joining the Scioto River.  Development
along  the Scioto/Olentangy mainsterns will result in urban pollutants entering
the streams with little  if any attenuation.

     In the Columbus area, demand  for community services has increased as each
community has expanded its boundaries.  Many services are currently at
capacity and are showing signs of  deterioration and stress.  Local reservoirs
must be protected from the negative impacts of increased development and
additional drinking water sources  should be located.  No secondary impacts on
transportation are anticipated as  a result of this project under any of the
alternatives.  Most of the schools in high growth areas such as Dublin,
Westerville, Worthington, and Milliard are at capacity and will require
expansion in the future.  Fire and police protection will continue to face
problems from expanded urban development.

6.6  CONCLUSIONS ON ALTERNATIVES
     The previous sections of this chapter presented evaluations of the one-
plant and two-plant alternatives based on engineering criteria and
environmental impacts.  Table 6-22 provides a comparison of the one-plant and
two-plant alternatives based on the environmental impacts.  Table 6-23
provides a comparison between the  one-plant and two-plant alternatives based
on engineering criteria and major  environmental issues.

     The two-plant alternative is  recommended over the one-plant based on the
following:

     •  The two-plant alternative has a lower present worth cost than the one-
        plant alternative.
     •  The two-plant alternative would be more reliable than the one-plant
        with respect to shock loads of pollutants to the sewer system.
     •  The two-plant alternative would provide more flexibility to adapt to
        increased future flow, to  adapt to more stringent effluent limits, and
        to address combined sewer  overflows.
     •  The two-plant alternative would be easier to implement since the
        majority of the facilities at each plant already exist.
                                     6-112

-------
Criteria
               One-Plant
        •Rao-Plant
Aim. User Costs
Sur. W. Qual.
Air/Odors


Soils/10 Ag


GW


Proj. 88:GW


Surface Flows


Terr. Bio.
Aq. Bio.
       m - $42-76 add'l user charges
           (new total:  $150-184)
           <$500/yr = not excessive

       M - Impaired upstream water quality
       M - WQ unpaired @ normal flow
       M - Enlarged downstream DO sag
       M - Potential for conflicts w/down-
           streara dischargers
       M - Short-term constr. inpacts due
           to river x-ing

       m - Sludge incineration impacts -
           no addtl. violations of standards

       ra - Construction-related erosion -
           easily mitigated

       m - Possible reductions in GW recharge
           along upper Scioto

       M - Vfells dewatered due to constr.
       M - Low flow reduction (86%) in
           upper Scioto

       m - Habitat loss due to constr. at
           Southerly (incl. river x-mg;
           greater on W. bank)

       m - Reduction in open-water habitat
           @ J.P. in winter

       M - Habitat reduction and impairment
           @ If between J.P. and Southerly

       M - Habitat impairment below Southerly
           @ LF

       m - Short-term habitat disruption
           due to river x-ing
   Issue

M = Myor
ra = Minor
   Impact

- = Negative
+ = Positive
o = Neutral
m - $41-68 add'l user charges
    (new total:  $149-176)
    <$500/yr = not excessive

m + minor improvement in WQ at LF
m + WQ improvement at normal flow
m + Downstream DO sag minimized
m + Potential for downstream conflicts
    minimized
m o no impacts
m - [Repeat of one-plant]
m + Construction-related erosion
    minimized - easily mitigated

m o No impacts
M - [repeat of one-plant]
    @ Southerly - mitigated

m o No change in current low flow
    conditions

m o No impact
                                                                  ra o No  impact
m o No change
                                                                  m + Minor habitat improvement below
                                                                      Southerly

                                                                  m o No impact
                                              6-113

-------
 Criteria
               One-Plant
        Ttar-Plant
Endangered Sp.
Plarm./L.U.
Noise



Pub. Health

Energy Use


Econ./Enploy.



Hist./Arch.
Recreation
       m - Impaired habitat belcw J.P. at IF

       ra - Loss of bird habitat at J.P.

       m -~ Reduction in Indiana BAT habitat
           due to river x-ing (greater on
           W side); easily mitigated

       M - Impaired habitat below Southerly

       m - Poten. short-term disruption of
           fanning (easily mitigated)
                     m - Short-term constr. increase/
                         long-term OSM increase:  both
                         easily mitigated
       m + Slightly less (10-20%) energy
           use due to economies of scale

       m + Construction expenditures:
           $269 million
           Annual employment:  135

       ra - Potential disrupt, of 2-3 non-
           eligible sites; can be mitigated
           through recovery (Phase III)

       m - Potential disrupt, of one possibly
           eligible known site and other
           unknown sites @ Scioto River crossing

       m - Water level reductions during IF;
           attenuated by low use levels of
           affected areas during If
m + Minor improvement in habitat at LF

m o No change at J.P.

m o No Impact



m + Minor improvement below Southerly

m o No mpact


m o Expansion of SB comer of J.P.

m - [repeat of one-plant]
                                                                  m - Slightly higher  (10-20%) energy
                                                                       use due to less  economics of scale

                                                                  m + Construction expenditures:
                                                                       $215 million
                                                                       Annual  employment:  191

                                                                  m - [repeat of one-plant]
                                                                  m o No impact
m o No change
   Issue

M = Major
m = Minor
   Impact

- = Negative
+ = Positive
o = Neutral
                                              6-114

-------
Criteria
               One-Plant
        "Rio-Plant
Transportation


2°:Develop.



2°:Air Qual.

2°:«ater Qual.


Pub. Mater/Sew.



Transportation



Pub. Education



Fire/Police Prot.


Cultural Res.
       m - Short-term constr. impacts on roads
           near Southerly

       M o Accomrodates future growth;
           distribution of. growth tied to
           future local development plans
       M - Non-point WQ deterioration (long-
           term); worst in Hellbranch Run

       M - Increased O&M costs/potential
           funding shortfalls in surrounding
           coonunities

       M - Declining levels of service in
           suburban connunities (New Albany,
           Westenalle, Dublin)

       M - Increased crowding in 17 Franklin
           Co. school districts; possible
           property tax increases

       m - Potential service level/coverage
           problems

       m - Potential losses of hist.
           structures and arch, sites due
           to incomplete inventories and
           limited ability to require
           preservation and/or recovery
m - Short-term constr. impacts on
    roads near both WWEPs

M o [repeat of one-plant]
M - [repeat of one-plant]


M - [repeat of one-plant]



M - [repeat of one-plant]



M - [repeat of one-plant]



m - [repeat of one-plant]


m - [repeat of one-plant]
Key;

   Issue

M = Major
ia = Minor
   Impact

- = Negative
+ - Positive
o = Neutral
                                              6-115

-------
            TABLE 6-23 ONE-PLANT/TWO-PLANT  COMPARISON
  CRITERION
                     ONE-PLANT
TWO-PLANT
  PRESENT WORTH
  COSTS
                                               x
  RELIABILITY
                                               x
  FLEXIBILITY
                                               x
  EASE OF
  IMPLEMENTATION
                                               x
  EASE OF OPERATION
  AND MAINTENANCE
                       x
  SURFACE WATER
  QUALITY
                                               x
  SURFACE WATER
  FLOWS
                                               x
  AQUATIC BIOTA
                                               x
  ENDANGERED
  SPECIES
                                               x
\S ^
PREFERRED ALTERNATIVE
                              6-116

-------
The two-plant alternative could result in more positive impacts with
regard to the quality of surface water flows (Scioto River).

The two-plant alternative would not result in any negative impacts
with regard to the volume of surface water flows in the Scioto River
between Jackson Pike and Southerly.

The two-plant alternative would result in more positive impacts on
aquatic biota and endangered species.
                            6-117

-------

-------
                          CHAPTER 7.  PREFERRED PLAN

7.1  DETAILED DESCRIPTION OF PREFERRED PLAN
     Based on the engineering and environmental evaluations presented in
chapter 6, the two-plant alternative is recommended as the preferred
alternative.  This alternative involves upgrading Jackson Pike and Southerly
to provide wastewater treatment  for the Columbus area through 2008.
Figure 7-1 presents a flow diagram  of  the two-plant alternative.  Figures 7-2
and 7-3 present flow schematics of the Jackson Pike and  Southerly WWTPs,
respectively.  The following sections  describe the required facilities.

7.1.1  Interconnector/Headworks
     Under the two-plant alternative, the north end of the Interconnector
(i.e. tributary to Jackson Pike) would  require completion  to allow diversion
of excess Jackson Pike flows to the Southerly WWTP.  The north end of the 150-
inch diameter Interconnector Sewer would be constructed  along  the west and
north sides of the Jackson Pike WWTP.  A diversion chamber would be installed
on the O.S.I.S. ahead of Jackson Pike at  the  intersection of  the O.S.I.S. and
the Interconnector Sewer.

     New headworks are required at the Jackson Pike WWTP.  The new headworks
wouId include:

     •  Four coarse bar racks
     •  Four 35 MGD raw sewage  pumps
     •  Four mechanically cleaned bar screens
     •  Four aerated grit chambers.

     The south end of the Interconnector (i.e.  tributary to  Southerly) would
not require expansion or modification under the two-plant alternative.  The
existing pump station and force mains  are adequate to convey projected flows.
The existing Southerly headworks are also capable of processing projected flows.
                                    7-1

-------
           SOUTHERLY SERVICE AREA
             AVG, FLOW = 66 MGD
             PEAK FLOW = 99 MGD
                                        JACKSON PIKE SERVICE AREA
                                           AVG. FLOW = 88 MGD
                                           PEAK FLOW = 132 MGD
i
N>
                                         INTERCONNECTQR
                                       AVG. FLOW = 8 MGD
                                       PEAK FLOW = 33 MGD
              SOUTHERLY VVTP
             AVG. FLOW = 74 MGD
             PEAK FLOW = 131  MGD
                                            JACKSON PIKE VVTP
                                            AVG. FLOV = 80 MGD
                                           PEAK FLOV = 100  MGD

     VEST TRAIN
 AVG. FLOV = 37 MGD
 PEAK FLOV = 65.5 MGD
    CENTER TRAIN
 AVG. FLOV - 37 MGD
PEAK FLDV = 65.5 MGD
     PLANT 'A'
AVG. FLOV =: 48 MGD
PEAK FLOV = 60 MGD
     PLANT  'B'
AVG. FLOV = 32 MGD
PEAK FLOV = 40 MGD
                                                                              FIGURE 7-1
                                                                              RECOMMENDED  PLAN
                                                                              FLOW SCHEMATIC

-------
                                                      PLANT 'A'

                                           PRIMARY         ,-n*.™,      SECONDARY
                                         CLARIFICATION     AERATION    CLARIFICATION
RAV
INFLUENT
PUMPING
    SCREENING
        GRIT
        REMOVAL
                                PREAERATIDN
                  INCINERATION
                       TO
                    LANDFILL
                                           PRIMARY
                                         CLARIFICATION
                                                     PLANT  'B'
                                                                                               EFFLUENT
 L.S-J
                                                          AERATION
                                                         SECONDARY
                                                       CLARIFICATION

      CHLORINATION/
      DECHLORINATION/
      POST AERATION
                                             PRIMARY
                                             SLUDGE
                                             HOLDING
                                              GRAVITY
                                              THICKENING PS
                       CENTRIFUGE
                       DEWATERING
                                                                                     WAS
                                                                                     HOLDING
  CENTRIFUGE
  THICKENING
  WAS


  THICKENED
  SLUDGE
  BLEND/STORAGE
                                                      DIGESTED      ANAEROBIC
                                                   SLUDGE  HOLDING   DIGESTION
                        TO LAND
                      APPLICATION
FIGUKE 7-2
JACKSON PIKE  VWTP
FLOW SCHEMATIC

-------
                 CENTER TRAIN
PREAERATIQN
   PRIMARY
CLARIFICATION
                                           AERATION
  SECONDARY
CLARIFICATION


CHLORINATION/
•» »> DECHLORINATION
| POST AERATION
SCRLENlNb PUMPING | y

f

RAW PRIMARY AERATION FFFl UFNT
INf- LUiNl CLAkil- 1CA 1 ION
f"DTT DC*Mn\/AI • 	 ~t '
uKi i KLMUVAL. •—- .

PREAERATION WEST TRAIN
GRAVITY
THICKENING PS
r _L
.^ 	 AMArpnnTf
^* rilNtti_l\UUi^
rrNTRTFURF DIGESTION
DEWATERING
\
T1FUATFPFT1
I 	 1 SLUDGE
I STORAGE
TKJHTNFRATTnN
T0 TO LAND 1
LANDFILL APPLICATION COMP
,S ^ _>,
V V
f — —-I SECONDARY
1 	 ri ARTPTrATTriM


],,„ 	 „,...,„„ ^{"MTDTfl \f~f~
ULN 1 K I r Uuc.
_ THICKENING
WAS
THICKENED
SLUDGE
BLEND/STORAGE
FIGURE 7-3
-0 SOUTHERLY WTP
OSTING FLOW SCHEMATIC

-------
7.1.2  Wet StreamTreatment
     The recommended wet stream treatment scheme at both plants would consist
of  the following processes:

     *  Preaeration
     •  Primary Settling
     •  Aeration
     •  Final Settling
     •  Chlorination/Dechlonnation
     •  Post Aeration
     •  Effluent Pumping.

     The existing primary treatment  facilities at both plants, which include
preaeration and primary settling, have adequate capacity to treat the
projected flows.  Some rehabilitation of the existing facilities would be
required.

     The semi-aerobic process is the recommended biological process for both
plants.   The  semi-aerobic process is  a modified form of the conventional
activated sludge process.   It offers  more flexibility to achieve nutrient
removal and control sludge bulking than the conventional activated sludge or
trickling filter/activated sludge processes.   It  differs from the conven-
tional activated sludge process in that the first 25 to 40 percent of the
reaction basin is  not aerated.  Therefore,  this section of each basin is in an
anaerobic or  anoxic state.  To eliminate  backmixing  from the aerated zone to the
anaerobic or  anoxic zone, two baffles would be installed in the first bay of
each aeration basin.   An  internal mixed liquor recycle loop connecting the
effluent end  of the aeration basin with the initial  bay would be necessary.  The
recycle loop  would  be utilized when ammonia bleed through was observed in the
later stages  of the aeration basin.   Recycling the ammonia would provide a
second opportunity  for oxidation to nitrates and nitrites.
                                   7-5

-------
     The semi-aerobic  process would  be  easily  incorporated into the existing
 tankage.  Both plants would utilize  existing aeration basins.  The Southerly
 WWTP would require two new basins, added to the Center Train, to treat the
 projected flows  and  loads.

     Post treatment at  both plants would  include  chlorination, dechlorination,
 and post aeration.  Post aeration would take place in the final pass of the
 chlorine contact  tanks.

     Existing effluent pumping at the Southerly plant is adequate to handle
 the projected flows.  Jackson Pike does  not have  an existing  effluent pumping
 facility.   However, there are two 3.6 MGO effluent pumps on the A train.   In
 the Revised Facility Plan Update  the  city  indicated that  a new 100 MGD
 effluent pumping  facility would  be required at Jackson Pike if the two-plant
 alternative were to be implemented.  In subsequent correspondence the city
 referred to high river levels as the reason a pumping facility would be
 required.   Until further documentation is produced by the city on the
 frequency and duration of high river elevations,  a new effluent pumping
 facility cannot be recommended.   The  cost  estimates include approximately
4.5  million dollars for the facility. This cost  will be subtracted if
 documentation is  not produced.

     Tables 7-1 and 7-2 provide  details  on the  recommended  wet stream treat-
 ment facilities at Jackson Pike and  Southerly, respectively.

 7.1.3  Sludge Management
     The recommended solids handling scheme at both plants includes the
 following processes:

     •  Gravity thickening of PS
     *  Centrifuge thickening of WAS
     •  Anaerobic digestion
     •  Centrifuge dewatering.
                                    7-6

-------
                                   TABLE 7-1.  JACKSON PIKE WET STREAM PROCESS  DESIGN CRITERIA
                                                         Plant "A"
                                                                 Plant "B1
FLOW

•  Average
•  Peak

PREAERATION

•  Tankage
•  Total tank volume
•  Detention time (avg. flow)
•  Detention time (peak flow)
48 MGD
60 MGD
2 existing @ 180 ft x 26 ft x  15  ft  SWD
1.05 MS
31 nun.
25 rain.
                          32 MGD
                          40 MGD
                          2 existing @  113  ft x 26  ft x 15  ft  SWD
                          0.66 MS
                          30 min.
                          24 nun.
PRIMARY SETTLING

•  Tankage
•  Total surface area
•  Surface loading rate (avg. flow)
•  Surface loading rate (peak flow)
4 existing @ 150 ft x
48,000 sq ft
1,000 gpd/sq ft
1,250 gpd/sq ft
80 ft x 10 ft SWD
4 existing @ 150 ft x 80 ft x 10 ft SWD
48,000 sq ft
667 gpd/sq ft
833 gpd/sq ft
AERATION

•  Tankage
•  Total tank volume
•  Detention time (avg. flow)
•  Detention time (peak flow)
6 existing @ 900 ft x 26  ft x  15  ft  SWD
15.75 MG
7.9 hr
6.3 hr
                          4 existing @ 900 ft x  26  ft x  15  ft  SWD
                          10.50 MS
                          7.9 hr
                          6.3 hr

-------
                                    TABLE 7-1.  JACKSON PUCE WET STREAM PROCESS DESIGN CRITERIA (CONT.)
                                                              Plane "A"
     FINAL SETTLING
        Tankage
        Total surface area
        Surface loading rate (avg. flow)
        Surface loading rate (peak flow
        Solids loading rate (avg. flow)
        Solids loading rate (peak flow)
8 existing @ 153 ft x 60
73,440 sq ft
654 gpd/sq ft
817 gpd/sq ft
23 Ib/day/sq ft
29 Ib/day/sq ft
                         ft x  12.5 ft SWD
                                                                Plant "B"
4 existing & 2 new @ 153 ft x 60 ft x 12.5 ft
55,080 sq ft
581 gpd/sq ft
726 gpd/sq ft
21 Ib/day/sq ft
26 Ib/day/sq ft
                                            Plants "A" and "B" Combined
oo
     CHLORINATION/DECHLORINATIOH
        Tankage
        Total tank volume
        Detention time (avg. flow)
        Detention time (peak flow)
        Evaporators
        Chlorinators
        Mixers
        Sulfinators
     POST AERATION

     •  Location
     •  Diffuser system
     •  Desired DO
                    ft x 10 ft SWD
2 new @ 100 ft x 75
1.12 JC
20.2 nan.
16.1 min.
4 <§ 2,000 Ib/day
4 @ 2,000 Ib/day
4 @ 10 HP
4 @ 2,000 Ib/day
Final pass of chlorine contact tanks
Fine bubble
7.0 og/l
     EFFLUENT PUMPING
4 new @ 35 MGD, variable speed

-------
                                     TABLE 7-2.  SOUTHERLY WET STREAM PROCESS DESIGN CRITERIA
FLOW

•  Average
•  Peak
                                                        West Train
                                                                  Center Train
  37 MGD
65.5 MGD
                                                37 MGD
                                              65.5 MGD
PREAERATION

•  Tankage
•  Total tank volume
•  Detention time (avg. flow)
*  Detention time (peak flow)
  A existing @ 25.5 ft x 112.7 ft x 15.5  ft SWD   A existing @ 25.5 ft x 112.7 ft x 15.5 ft SWD
  1.33 MG                                         1.33 MG
  f n	                                          ^A
1.33 MG
52 mm.
29 rain.
                                                   52 mm.
                                                   29 mm.
PRIMARY SETTLING

•  Tankage
•  Total surface area
•  Surface loading rate (avg. flow)
•  Surface loading rate (peak flow)
  A existing @ 100 ft x 170 ft x 10 ft SWD
  68,000 sq ft
  5AA gpd/sq ft
  963 gpd/sq ft
                                                A existing @ 80  ft x 165 ft x 10 ft  SWD
                                                52,800  sq ft
                                                701 gpd/sq ft
                                               1,241 gpd/sq ft
AERATION

•  Tankage
•  Total tank volume
•  Detention time (avg. flow)
•  Detention time (peak flow)
  6 existing @ 26 ft x 900 ft x 15 ft SWD
  15.75 MG
 10.2 hr
  5.8 hr
                                                A existing  &  2  new @  26 ft  x 900 ft x 15 ft SWD
                                                15.75 MG
                                                10.2 hr
                                                5.8 hr

-------
                                   TABLE 7-2.  SOUTHERLY WET STREAM PROCESS DESIGN CRITERIA (CONT.)
                                       West and Center Trains Combined
FINAL SETTLING
   Tankage
   Total surface area
   Surface loading rate (avg. flow)
   Surface loading rate (peak flow)
   Solids loading rate (avg. flow)
   Solids loading rate (peak flow)
6 new @ 190 ft dia
170,000 sq ft
435 gpd/sq ft
771 gpd/sq ft
22 Ib/day/sq ft
38 Ib/day/sq ft
x 15 ft SWD
CHLORINATION/DECHLORINATION
   Tankage
   Total tank volume
   Detention time (avg. flow)
   Detention time (peak flow)
   Evaporators
   Chlonnators
   Mixers
   Sulfinators
2 new @ 150 ft x 64 ft x 10 ft SWD
1.44 MG
28.0 mm.
15.8 min.
5 @ 2,000 Ib/day
5 {? 2,000 Ib/day
4 @ 10 HP
4 @ 2,000 Ib/day
POST AERATION

•  Location
•  Diffuser system
•  Desired DO
Final pass of chlorine contact tanks
Fine bubble
7.0 mg/l
EFFLUENT PUMPING
6 existing @ 35 MGD, variable speed

-------
     Solids disposal of the annual solids production at Jackson Pike would be
accomplished by the following  processes:

     •  50 percent would be incinerated, and the ash product landfilled.
     •  SO percent of the dewatered sludge would be land applied.

     Disposal of the annual solids production at Southerly would be
accomplished by the following  processes:

     •  50 percent of the sludge would be incinerated, and the ash product
        landfilled.
     •  25 percent of the sludge would be composted and distributed as a soil
        conditioner.
     •  25 percent of the sludge would be land applied.

     Redundancy of sludge disposal methods at both plants is provided through
the incineration process.    At  Jackson Pike,  the two existing incinerators are
capable of incinerating approximately 50 percent more sludge than Jackson Pike
will produce.  At  Southerly,  the  two new incinerators constructed in 1986 are
capable of incinerating aproximately 100 percent more sludge than the
Southerly plant is projected to produce under the two-plant alternative.   In
light of the redundancy exhibited by the new Southerly incinerators,
rehabilitation of the older incinerators at  Southerly does not appear
justified.

     Tables 7-3 and 7-4 provide details on the recommended solids handling
facilities at Jackson Pike and Southerly, respectively.

7.2  IMPACTS OF THE PREFERRED PLAN
7.2.1  Financial Impacta
     User charges  are assessed  to finance both capital construction costs and
                                      7-11

-------
           TABLE 7-3.  JACKSON PIKE SOLIDS HANDLING DESIGN CRITERIA
GRAVITY THICKENING PS

     •  Number of units

     •  Total surface area

     •  Solids loading race

     •  Hydraulic loading rate


CENTRIFUGE THICKENING WAS

     •  Number of units

     •  Feed rate


ANAEROBIC DIGESTION

     •  Number of units


     •  Total volume

     •  VSS loading rate

     •  Solids retention time


CENTRIFUGE DEWATERING

     •  Number of units

     •  Feed rate

     •  Polymer dosage


INCINERATION

     •  Number of units

     •  Rated capacity
3 new @ 65 ft dia. x 10 ft SWD

9,955 sq ft

12 Ib/day/sq ft

73 gpd/sq ft




2 existing and 1 new

500 gpm @ 1% solids
6 existing @ 85 ft dia. x 23.5 ft SWD
4 existing @ 70 ft dia. x 27.5 ft SWD

1.2 million cu ft

0.11 Ib VSS/day/cu ft

23.6 days
6 existing and 1 new

1,000 Ib/hr @ 4% solids

12 Ib/dry ton




2 existing 7-hearth @ 22.25 ft dia,

200 wet ton/day @ 20% solids
                                 7-12

-------
            TABLE 7-4.  SOUTHERLY SOLIDS HANDLING DESIGN CRITERIA
GRAVITY THICKENING PS




     •  Number of units




     •  Total surface area




     •  Solids loading rate




     •  Hydraulic loading rate






CENTRIFUGE THICKENING WAS




     •  Number of units




     •  Feed rate






ANAEROBIC DIGESTION




     *  Number of units




     •  Total volume




     *  VSS loading rate




     •  Solids retention time






CENTRIFUGE DEWATERING




     •  Number of units




     •  Feed rate




     •  Polymer dosage






INCINERATION




     •  Number of units




     •  Rated capacity
4 existing @ 45 ft dia. x 17 ft SWD




6,362 sq ft




14 Ib/day/aq ft




86 gpd/sq ft











4 existing and 1 new




250 gpm @ 1% solids











6 existing @ 85 ft dia. x 23.5 ft SWD




0.8 million cu ft




0.08 Ib VSS/day/cu ft




30.7 days










6 existing and 2 new




1,000 Ib/hr <§ 4£ solids




12 Ib/dry ton










2 8-hearth @ 25.75 ft dia.




260 wet ton/day @ 20% solids
                                 7-13

-------
 O&M costs of operating public  facilities.  Due to the uncertainty as to the
 amount and time of current and future grants of Federal funds, it is useful to
 present estimated user costs in  a range from assuming no Federal funds
 available  to  assuming  a 55 percent grant for all capital construction.  This
 approach  shows  the  full range  of possible  additional annual user charges.
 For  the recommended  alternative, this range is $41 to $68.  Added to 1985
 annual  user fees of $108, this range results in total future annual
 residential user fee estimates of $149 to  $176.  These  estimated fees only
 apply to residential users.   Commercial and industrial users pay similar fees,
 and additional charges  for extra strength effluent  are  also levied  on some
 industries.

     Median,  family income often  is used  to assess the affordability of
 increases in user charges to average residents.   Franklin County, which
 includes most of the service area,  had median family incomes over $17,000 in
 1979.  Given EPA guidance, an annual  user charge  of $367  would not  be
 considered excessive for  this income category.  Based on this guidance,
estimated additional user charges for the recommended alternative would not
 make total user charges  excessive.

 7.2.2  Environmenta1 Impacts
 7.2.2.1  Primary Impacts
Surface Water Quality
     The recommended two-plant alternative would protect stream standards for
DO and  ammonia.   However, the treated effluent  would  contain a  minimal
residual wasteload,  which would be assimilated by the river without violating
water quality standards.

     The recommended alternative would release the residual effluent DO demand
to the  Scioto River at  two locations (Jackson  Pike  and  Southerly).   Two DO
 sags would therefore result, however, neither  sag should  result in  contraven-
 tion of water quality standards.  Significant improvements  to  in-stream DO
                                     7-14

-------
conditions would result  from  this  alternative.  Because significant pollutant
loads would continue to enter the Scioto River upstream of Jackson Pike (from
urban runoff and CSOs from Whit tier  Street), the degree of water quality
improvement below  Jackson Pike would be less than below the Southerly WWTP.
Under certain flow conditions, DO  levels below the 5.0 rag/1 standard may occur
below Jackson Pike, related to CSO loadings.  However, the presence of Jackson
Pike effluent during low flow events may lessen the DO impacts of CSOs and
upstream  urban  runoff.

Air Quality/Odor
     The most significant long-terra impact to air quality from the  recommended
alternative would result from the operation of incinerators  as  a primary method
for ultimate solids disposal.   However, the recommended alternative should
result in a decrease in the  total amount of solids incinerated at  Southerly
due to the fact that anaerobic digestion would be practiced and also because a
portion of the solids at Southerly would be land applied.   The level of
incineration at Jackson Pike would remain approximately the same.

     A 25 percent increase in  the amount of  solids composted would  result in
increasing odor potential near the composting facility.  This  increase  may or
may not be offset by process changes, renovations,  and the installation of new
units, which are expected to reduce  the occurrence of earthy sewage odors
characteristic of this facility.   These changes  could reduce odors  through the
reduction of moisture and maintenance of optimum temperature, pH,  and oxygen
content through improvements to aeration and dewatering  at the  Southwesterly
Composting Facility.

Soils/Prime Agricultural Land
     The physical and chemical characteristics of local soils govern the
extent of impacts from proposed improvements to the Southerly and Jackson Pike
WWTPs under the recommended alternative.  First,  the  direct impact  of soils
disturbance during the  construction of  new  facilities and  the  removal of
                                     7-15

-------
 existing  facilities would  result  in  exposure and accelerated erosion within the
 limits of the  project  sites.  Second,  land application of anaerobically
 digested  waste activated sludge to agricultural lands would modify the
 composition of the existing soils.  The impact of both segments of the project
 will involve areas  that have been designated, based on soils classification,
 as  "prime agricultural"  lands.

     Under  the  recommended alternative,  there would be no additional land
 outside the current site required for construction of the proposed upgrading
 of  the Southerly WHIP.  At the Jackson Pike facility, an additional area of
 approximately  four acres (southeast of the existing plant) would be required
 for new construction.  This additional area is located on an abandoned ash
 lagoon, within  the confines of an existing earthen dike.   It is now covered by
 uncultivated vegetation and is not considered farmland or prime agricultural
 land.  The area is relatively flat;  thus, extensive erosion during
 construction should not be a serious problem if proper mitigation procedures
 are  followed.

     Land application of anaerobically digested waste activated sludge is a
 well-known  and accepted method of solids management.   Under the recommended
 alternative, approximately 38 dtpd of sludge will be land applied, 12 dtpd
 from Southerly and 26 dtpd  from Jackson Pike.  Based on 1985-1986  cadmium
 concentration figures and a range of soil assimilative capacities typical for
 this region, an application rate of 3.4 to 5.1 dry  tons per  acre per  year can
be  estimated.  This results in an annual  land requirement of 2,755 to 4,133
acres per year.  Comments from OBPA and Columbus indicate that  a site will be
 limited to  16 years of active life because of zinc concentrations.  Based on
 the city's estimate of 200,000 acres  available for  land application within 40
 miles, site availability should not be a problem.  Current land application
 operations have proven successful  with no reported  contamination or adverse
health effects; this performance  should  continue based on current guidelines.
                                     7-16

-------
     No significant impacts are forecast to area soils or prime agricultural
land under the recommended alternative•

Groundwater
     The recommended alternative  is not expected to cause signficant  impacts
to area groundwater resources through potential  interaction with the  Scioto
River since WWTP discharge levels and any associated impacts will remain
similar to current practices.  Because the stretch of  the Scioto River
affected by the Jackson Pike WWTP  is  small and because the river bed  is
believed to be at least partially sealed by  industrial  and WWTP sludges,
little or no impact on  the groundwater system by  improvements  to surface water
quality is expected.

     A draw-down of groundwater elevations and drinking water  wells occurred
in 1986 to the town of Shadeville, a suburb  of Columbus,  due to a dry spell,
construction dewatering at the Southerly WWTP, and groundwater pumping  for the
city's  Parsons  Avenue Water Treatment Plant.   This  caused  the  water table to
drop about 8 feet leaving many of Shadeville's wells  inoperational.   This
impact was mitigated through the extension of centralized  water service to
Shadeville by the city.  Any  future impacts due to  construction dewatering
should also be  mitigated through  provision of  city  water  by extension of the
city's  centralized  water distribution system.

Surface Water Flows
     The volume of  surface water  Columbus currently removes from the  Scioto
River is about  the  maximum possible limit, especially during the critical low
flow months of summer and  fall.  Therefore,  no future manmade  reductions in  the
volume of flows in the  Scioto River area are expected  around the Columbus area.

     The recommended alternative  would discharge  flows from the Jackson Pike
WWTP at roughly the same levels as currently occur.  Average daily  discharge
will be reduced from 85 to 80 MOD, a decrease of under 6  percent.   For this
reason, impacts from the recommended alternative  are not expected to
                                     7-17

-------
 signficantly alter  the physical parameters of Scioto River surface water
 between  the Jackson Pike and Southerly WWTPs.

 Terrestrial and Wetland Biota/Habitat
     No  impacts to  previously undisturbed wetlands or terrestrial habitat are
 expected under the recommended two-plant alternative.

 Aquatic  Biota/Habitat
     Water quality  in the Scioto River, between Columbus and CirclevilLe, is
 currently degraded by point sources and general non-point runoff for the
 metropolitan area.  The key water quality problem is considered to be low DO.
 Although the low 00 problem is clearly related to discharges from the Jackson
 Pike and Southerly WWTPs (degraded fish populations have been associated with
 the DO sags resulting from these two  point sources), other sources
 contributing to the problem included  the Whittier Street CSO and general
 urban runoff.

     Upgrading both treatment plants would result in water quality improve-
 ments and no water quality violations due to  WWTP effluent.  Nonpoint and CSO
 contributions of pollutants will continue to cause problems.  These changes
 should have a favorable impact on aquatic biota and habitat.  Sensitive
 species that currently inhabit the area should persist and increase in
 abundance.   New species  may move into the area and increase  community
diversity.

     Decreased turbidity should create a more favorable habitat for turbidity
sensitive species.   These species,  such  as darters, which  now inhabit Scioto
River tributaries,  may begin to move into the Scioto  mainstream in greater
numbers.

     Although the  effluent  from the WWTPs should not cause violations in DO
standards under the  recommended alternative,  residual wasteloads in the
                                     7-18

-------
 effluents  from  both  WWTPs would continue to exert  a DO demand in the receiving
 water,  and a reduced DO sag would persist below both treatment plants.  As a
 result, fish communities  would  continue  to show some degradation as oxygen
 levels  are depressed downstream.  These effects would be most noticeable in
 the  sections of the  river where the residual DO sags are most critical (i.e.,
 where DO  levels approach  5.0 mg/1).   Effects of degradation in fish
 communities  include  increased numbers of omnivorous fish relative to
 insectivorous fish,  increased hybridization, (lowered biotic index) and
 decreased  diversity.  Although the structure of the benthic  community would
 also improve under the recommended alternative,  benthic communities would
 continue to exhibit  decreased abundance and diversity in areas experiencing
 the  oxygen sag.

     Over  the past 6 years, the fish community  in  the Central Scioto has
 improved.  The recommended alternative would result in a continuation and
 acceleration of this trend.  Although significant  improvements should occur,
 the collective,  continuing impacts of WWTP effluents, general urban runoff,
 and the Whit tier Street CSO would prevent free biological recovery in the
 Central Scioto,  when compared with comparatively unimpacted  segments upstream
 of Columbus and downstream of Circleville.

     Endangered aquatic species  should benefit  from implementation of this
 alternative.   Improvements in water quality should allow the fish species that
have been captured in the Scioto River (river redhorse,  mooneye,  gold eye,  and
Tippecanoe darter) to increase in abundance  and allow those species inhabiting
 tributaries (bluebreast darter,  slenderhead  darter, spotted  darter,  and
blacknose shiner) to expand their ranges.  Specific information on the
 tolerances of these species to turbidity and lowered  DO is not available,
 preventing a  precise assessment of the conditions  under which these species
would establish permanent breeding populations. Increased habitat for
feeding, however, should benefit populations.   Improved water quality in the
Scioto River  may increase potential  for  the Scioto  madtorn population to expand
its numbers and range.
                                      7-19

-------
     Mollusk  populations  should benefit from  this alternative because it could
offer them an expanded habitat and therefore the opportunity to increase in
abundance.  Because they are sensitive to  WWTP effluent,  they would most
likely move into areas further downstream from outfalls.   As larvae, the
unionid moHusks are carried to new  environments  on gills of fish.  Little
information is available on suitable fish  species, but  freshwater drum is
believed  to be one such species (Stansbury 1987).  Freshwater drum is a
pollution sensitive species.  The  potential for increased numbers of
freshwater drum  in response to improved water  quality also may play a role in
the migration of raollusks.

Planning and Land Use
     No land acquisition or zoning changes should be required under the
recommended alternative.  Under this alternative,  a portion of the current
Southerly site would be used for new wastewater facilities.  This land has
already been purchased and disturbed  during  construction  to meet  compliance
with water quality standards by 198S.  In addition,  there would be some
expansion near the southeast corner of the existing Jackson Pike  facility.
This land is owned by the city, is vacant, and is not slated for  other
development.

Noise
     Ambient noise levels near both treatment plants would increase during
construction activities; however,  construction  specifications would  minimize
these effects.  Operational noise is not expected to be  a nuisance.

Public Health
     Current disinfection practices at both the Southerly and Jackson Pike
WWTPs are successfully controlling the release of  pathogenic  microorganisms to
the Scioto River, as  evidenced by  low effluent fecal coliform counts.
Treatment levels would improve slightly with the upgrading of facilities under
                                     7-20

-------
 the recommended alternative.  The state of Ohio has issued strict guidelines
 regulating land application of sludge in order to protect public health
 interests.  Adherence to these regulations  under  the recommended alternative
 would  protect  the public  from any adverse  health effects.

 Energy Use
     The energy requirements  associated with  the upgrading of facilities at
 Jackson Pike and/or Southerly WWTPs include gasoline and diesel fuel,  electric
 power, and methane  gas.  The  impact of these energy requirements is not
 projected to deplete local reserves significantly.   Current  energy require-
 ments would  increase slightly under the recommended alternative as flows
 increase and higher levels of treatment are achieved.

 Economics and Employment
     Employment  levels under the recommended alternative would drop from
 approximately 212 persons to 191.  The economic impact  in the  Columbus area of
 combined capital and O&M expenditures would be positive, however,
 quantification of indirect economic  benefits cannot  be  performed at the
 current level of project planning and financial analysis.

Historic/Archaeologic Resources
     The recommended alternative would have no direct impacts  on known
historic resources.

     Construction at the Southerly WWTP under  the recommended  alternative is
not expected to disturb archeologic  resources  identified during surveys in
 1985.   Phase I and II archaeologic  surveys  were performed by Dr. John Blank,
Professor of Archaeology at Cleveland State University,  in order to evaluate
 impacts from site work planned by Columbus to  meet  1988 compliance with water
quality criteria.   Four sites  not eligible  for the National Register were
identified during Dr. Blank's  survey  within the boundaries of  the Southerly
WWTP site.  Dr. Blank recommended a further (Phase III) archaeologic survey.
                                     7-21

-------
 However,  at  a meeting in March of 1986 the Ohio Historic Preservation Officer
 (OHPO) approved the initiation of site  work necessary  to  build  improvements to
 comply with  water quality limits at the Southerly WWTP.  This work has since
 been  completed.

     During  1985  Dr.  Blank also  surveyed the Jackson Pike WWTP site.  Dr.
 Blank  estimates that Jackson Pike was built on approximately 20 feet of fill
 material, isolating any archaeologic resources below from disturbance.  For
 this reason,  the recommended alternative should have no direct  impact on
 archaeologic resources at Jackson Pike.

 Recreation
     Direct  impacts on recreational Use of the Scioto  River  would be minimal
 under  the recommended alternative.

 Transportation
     Direct  impacts of the proposed project alternatives  on vehicular
 transportation in the Columbus area would involve  short-term effects on
 traffic flow due  to construction at both the Southerly and Jackson Pike
 facilities.   These effects would be marginally greater at the Jackson Pike
 site due to the more congested traffic patterns in the downtown area.  In
neither case  would impacts be significant enough to affect the  level of
 service in the area.   No  off-site construction is  anticipated that would
 impact vehicular  flow.

 7.2.2.2  Secondary Impacts
Growth and Development
     Sustained growth in  the Columbus metropolitan area is projected through
 2008.   Upgrading existing wastewater facilities under  the recommended
alternative would accommodate this growth.  Secondary impacts projected to
occur as part of forecast growth are evaluated below.   These include:  1)
 increased demand  for public services,  2) increases in non-point source
                                      7-22

-------
 pollution and erosion and  runoff created by disturbances of stable areas, and
 3) increased fiscal outlays required to mitigate other secondary impacts, that
 is,  provide additional  services.

     Although some interceptor sewers  in the Columbus area are nearing
 capacity and future growth could be restricted in some service areas, this EIS
 cannot assess capacity or  potential for growth inducement of  these lines,
 since plans for suburban interceptor expansion are not yet finalized.
 However, some  of  the growth projected  in the northwest section of Franklin
 County may  not occur if sewer service  is not  extended.

     As long as the Columbus  economy is strong and continues  to expand, and as
 long as vacant land is available, the northern suburbs of Columbus should
 continue to grow  (see chapter 4).  Developers and local residents find this
 section of the county to be most attractive because of its recreation
 resources,  existing public services,  and close proximity to  the Columbus
 central business district (CBD).  Although  some  infilling has  occurred,  the
 city is also expanding its boundaries through annexation in the northwest
 sector of the county.   This is an area  where the incorporated areas of Dublin
 and Billiard are also expanding  their  boundaries.

     The most obvious impacts of continued  forecast growth would be
 degradation in air and water  quality, increased demand for public services,
 and increased taxes and user  fees required  to finance these services.

     Since portions of Franklin County  have been designated  as non-attainment
 for total suspended particulates, the impact  of  projected growth on future
 ambient particulate concentrations was assessed.

     Growth forecasts (see chapter  4) show  a  10  percent  growth rate for the
 period 1988 to 2000,  and a 20 percent increase from 1988 to 2015.   This
population growth will be accompanied by increases in particulate generating
activities  such as  residential and  commercial fuel combustion, automotive
                                      7-23

-------
exhaust, tire and brake wear, and solid waste incineration.  An analysis of
changes in emissions due to forecast growth conclude that air quality impacts
due to project-related growth will  not contribute to the exceedance of any air
quality standards, add to the local non-attainment areas, or inhibit progress
toward achieving ambient  air quality  standards.

     Since the population growth and development are not expected to result in
a violation of ambient air quality  standards, it is  unlikely that growth would
contribute to changes in the climate of the area.

     Based on the current pattern of population distribution,  generalized
growth areas within the FPA have been identified in  Figure 4-2.   These growth
areas can be grouped into four general zones, based  on  watersheds, for the
purpose of indirect  water quality impacts  discussions.   Moving clockwise
around Columbus, the four general growth impact zones are the Big Walnut Creek
basin,  including Blacklick Creek and Alum  Creek; a small area draining
directly to the lower Scioto River, southeast of Grove  City, in Jackson
Township; the Big Darby Creek basin; and  the upper Scioto River including the
Olentangy River.

     Water quality impacts in these basins would include those typical of
urbanization:
     •  Modified hydrograph (higher peak flows, lower base flows) and bank
        erosion
     •  Elevated turbidity, dissolved solids, and sedimentation
     •  Elevated water temperatures
     •  Increased organic load (higher BOD,  COD,  TOC,  and nutrients) and
        decreased DO
     •  Elevated levels of non-point toxics  (pesticides,  herbicides,  and
        complex organic compounds)
     •  Increased coliform bacterial levels.
                                      7-24

-------
     The extent of these impacts  would be  dependent  on  the rate and degree of
urbanization actually realized and the extent  to which stream management
practices are integrated with  this growth.

Public Water and Sewer
     The city of Columbus  provides water and sewer service to most of Franklin
County.  Parts of this system were installed as early as 1935.  The Columbus
Infrastructure Report indicates that each of the  communities in the Columbus
area would have significant funding shortfalls in providing  local  sewers and
water  lines and that new revenue  sources should be tapped in order to maintain
this system.  The report urges an increase  in user charges and assessment fees
to cover operation and  maintenance costs.

     Aside from maintaining a system of water and sewer lines, Columbus is
also responsible for maintaining  adequate water supply  reserves.  A recently
completed water supply  study (Witlatch & Martin 1985) confirms that the city
can meet its water supply needs through the early 1990s  and recommends that
additional sources be found.  In order  to meet growth  demands,  new wells
should be located and tested regularly.

Roads and Highways
     The level of service provided by the Columbus area  highway system appears
to be adequately meeting current  needs  of the  system,  although some roads in
some communities are approaching  capacity.   While data were  not available to
precisely quantify the levels of  service,  experts  indicate that the level of
service capacity has been reached in  some communities and is  approaching
capacity in others.   In  many cases highway/road capacity has  been  reached
without regard to additional growth anticipated in the  future.  It is also clear
that growth is anticipated  to continue  and  that the recommended alternative
would represent only one factor in determining the magnitude of that growth.  It
does not appear  from the available information that the  implementation of the
project would increase growth beyond that already projected.
                                    7-25

-------
 Public  Education
     Franklin  County  has  17  independent  school districts  including Columbus.
 Each district operates its own schools and raises the funds to finance these
 schools  through local property taxes.  Most of the schools in high growth
 areas such as Dublin, Westerville, Worthington, and Hilliard are at capacity
 and should require expansion in the near future.

 Fire and Police Protection
     In 1977, MORPC prepared two reports:  one addressing police protection
 and the other addressing  fire protection (Mid-Ohio Regional Planning
 Commission  1977).  Neither of these studies have been updated.  Both of these
 reports indicated that providing adequate police and fire protection for the
 Columbus area would require  increased  coordination of services and additional
 personnel.   These reports found that the inconsistent pattern of annexation by
 Columbus disrupted the delivery  of fire and police services.  The problems
 referred to in these reports have not been directly addressed in the
 intervening 10 years.

Cultural Resources
     Secondary impacts on historic resources could occur  as a result of
changes in land use and zoning patterns as  well as changes in the evolution of
neighborhoods during the growth process.  Historic resources have been
 inventoried in the study area.   The Ohio inventory,  in particular, is
extensive.   Land use changes  may affect historic properties adversely in
numerous ways without stringent zoning codes, zoning enforcement,  containment
of strip coramerical and zoning map changes.

     As described in chapter 2,  archaeologic sites have been found to be
nearly continuous along the floodplain and on adjacent bluffs along the Scioto
River in the area of the Southerly WWTP.  Since insufficient data have been
collected and inventoried, knowledge of prehistoric culture along the Scioto
River and within the study area  is  incomplete.   Increased urban development
                                      7-26

-------
along the Scioto River in the vicinity of the Southerly plant may increase the
disturbance of unknown sites.  As part of the recreation plan for the Scioto
River, conservation of the southern Scioto riverbanks is recommended as a
means of mitigating secondary impacts  on  these  resources.

7.2.2.3  Mitigative Measures
     Direct air quality impacts associated with the recommended alternative
would include short-term, adverse air quality impacts experienced during the
construction phase of the project with the generation of fugitive dust and
increased vehicular exhaust.  These  impacts  would be concentrated in the
locale of both the Jackson Pike and Southerly facilities.   Project
specifications should include provisions for  mitigating  such impacts,  through
such measures as watering of haul roads and  exposed  soil.

     Noise impacts should be minimized by  the following techniques:

     •  Vehicles and motorized equipment should be properly muffled to state
        standards.
     •  Surface construction work should occur only during  normal workday
        hours.
     •  Any activity potentially causing  excessively high  noise levels (e.g.,
        blasting) should  be  carried  out in accordance with  applicable  state
        and local regulations.
     •  Noise barriers should be used around sites where required by the local
        authorities.

     Erosion and sedimentation  impacts should be minimized  by the following
techniques:

     •  Permanent erosion control structures, such as rip-rap or rock fill,
        should be incorporated  into  the site design where appropriate.
     •  The contractor should grade,  fertilize,  seed,  and mulch  areas  as
        called for on the plans  or as directed by the engineer.
                                     7-27

-------
      •  The contractor should provide for temporary seeding or sodding as
        called  for on the plans or as directed by the engineer.

      Well-planned construction phasing  takes into consideration the adverse
effects on construction sites in which work will be left partially completed
while construction continues elsewhere.  A preferred phasing policy would
call  for completion of all necessary construction in a section before
proceeding to the next section.   This will prove more expensive in short-term
costs, but environmentally advantageous in the long-term.

      Finally, growth-related impacts (i.e.,  "secondary  growth")  will occur in
the Columbus area in the future.  Although these impacts are not a direct
consequence of  the proposed project, mitigation should be considered by the
city  where possible in the interest  of sound environmental  management to
control water quality impacts.  Best Management Practices  (BMP) should be
employed including:   construction or farming set-backs  from stream corridors
as well as other erosion control measures discussed above.

      In the area of fiscal and infrastructure planning, greater care should be
directed to anticipating and planning for future infrastructure needs and
development of  longer terra financing options.  Specific opportunities in this
area  are included in the Infrastructure Project Final  Report,  included as
Appendix N.

7.3   FUTURE FACILITIES PLANNING
     This SBIS has evaluated only a  component of a complete waste  treatment
system; therefore, any grant  funds awarded to the city  of Columbus would be
contingent upon EPA approval of  facilities planning for both combined sewer
overflow and future interceptors.  The last  two grant awards  to the city have
included such grant  conditions.

Combined Sewer Overflow (CSO)
     The RFPU stated that the environmental impacts of the  existing combined
                                      7-28

-------
sewer overflows were  insignificant according to documentation in the draft
OEPA Central Scioto River Water Quality Report (CWQR).  However, information
in the CWQR suggests  that the environmental impacts  of  the existing CSOs are
significant.  On page  195 the CWQR states that "combined sewer overflow, and
as previously discussed, plant bypasses also contribute significant loadings
of BOD^, NH-j-N, TSS, and other substances to the Central Scioto River
Mainstream".  Further, page 317 states, "Reductions in the magnitude and
frequency of combined sewer overflow discharges is needed to improve aquatic
community  function, alleviate aesthetic problems, and reduce risks to human
body contact recreation in the segment  between Greenlawn Dam and the Jackson
Pike WWTP".

     Water  quality impacts of CSOs have been identified; however, detailed CSO
data is not available  to assess  the  magnitude  or determine control methods.
Therefore,  completion of facility planning to  produce a CSO study is required
by OEPA to  identify the  magnitude  of CSOs, mitigation measures,  and a cost-
effective,  environmentally sound solution to the CSO problem.  The city is
also required  within the NPDES permit  to  monitor  the  combined sewer overflows
and report  monthly for the permitted discharges.

Future Interceptors
     This SEIS addressed only general  population growth and secondary impacts
associated  with growth.   Since the city has  not  completed planning for future
interceptors,  specially located growth and impacts could not be identified.
The city is also required to  complete  facilities  planning for future
interceptors.
                                     7-29

-------

-------
                                     INDEX

Activated Sludge, 5-16, 5-23
Aeration, 5-16
Aerobic, 5-16
Air Quality, 2-2, 6-54, 6-96
Alternative, No Action, 5-7
Alternative, One-Plant, 5-9, 6-15
Alternative, Two-Plant, 5-8, 6-15
Alternative, Two-Plant One Solids, 5-9, 6-14
Alum Creek Storm Tank, 3-27
Ammonia (NH3), 1-6, 2-14, 6-31
Anaerobic, 5-16
Anaerobic Digestion, 5-33
Anheuser-Busch Brewery, 1-9, 3-24
Annexation, 2-73, 6-97
Anoxic, 5-16
Aquatic Biota, 2-25, 6-73
Aquifer, 6-50
Archeological Resources, 2-78, 6-89
Atmosphere, 2-1
Big Darby Creek, 2-9
Big Run Interceptor, 3-1
Big Walnut Creek, 2-8
Big Walnut Interceptor, 3-13
Biochemical Oxygen Demand (BOD), 1-6, 4-29
Biota, 2-1, 2-23, 6-69
Blending, 3-23
Bypassing, 3-23
Carbonaceous Biochemical Oxygen Demand (CBOD), 1-6, 6-31
Centrifuge Dewatering, 5-35, 6-11
Centrifuge Thickening, 5-32

-------
                               INDEX  (Continued)

Chlonnation, 6-18, 6-21, 6-25,  7-6
Clarification, Primary, 6-18,  6-21j  6-25
Clarification, Secondary, 6-7
Clean Air Act, 1-6, 1-7
Clean Water Act, 1-6, 1-10
Climate, 2-2, 6-96
Combined Sewer Overflow (CSO), 1-6,  1-10, 3-26, 4-37
Commercial Flow, 4-23
Community Service, 2-70
Composting 1-4, 1-8, 5-37
Comprehensive Water Quality Report,  2-14, 4-38, 6-36
Conventional Activated Sludge, 5-23
Costs, Capital, 6-23
Costs, O&M, 6-23
Costs, User, 6-28
Cultural Resources, 2-78, 6-110
Dechlorination, 6-18, 7-6
Denitrification, 5-16, 7-5
Dewatering, 5-35, 6-11
DFOT, 1-5, 5-3
Diaphragm Plate and Frame Presses, 5-35, 6-11
Disinfection, 6-18
Dissolved Oxygen, 2-13
Diurnal Flow, 4-24
Domestic Flow, 4-24
Economic Impacts, 6-88
Education, 2-69, 6-106
Effluent Characteristics, 3-5, 3-19
Effluent Limits, 3-5, 3-23
Effluent Pumping, 7-6

-------
                               INDEX (Continued)

Employment)  6-88
Endangered Species, 2-51, 6-79
Energy, 6-88
Environmental Consequences, 6-31,  6-69, 6-85
Environmental Impact Statement  (EIS)  1-3
Facilities Plan (1976), 1-1
Facilities Plan Update (1984),  1-5, 5-5
Feasibility  Study for Wastewater Treatment, 5-4
Fecal Coliform, 2-17
Five-Day Carbonaceous Biochemical  Oxygen Demand  (CBOD5), 1-6. 3-5, 6-31
Flexibility, 6-3
Floodplains, 6-46
Franklin County, 1-1, 2-1
Future Development 6-93
Geology, 2-18
GERBOD, 3-12, 3-26
Gravity Thickening, 5-32
Grit Removal, 3-3, 3-17
Groundwater, 2-12, 6-50
Headworks, 5-12, 6-3
Health Care, 2-68
Heavy Metals, 2-15
Historical Resources, 2-78,  6-89
Hydrology, 2-5
Implementability, 6-3
Incineration, 1-4, 5-36,  7-11
Industry,  2-56
Income, 2-55, 4-6
Industrial Flow, 4-23

-------
                               INDEX  (Continued)

 Infiltration, 4-20
 Influent Characteristics, 3-5, 3-19
 Influent Pumping, 3-7, 3-17
 Interceptors, 3-1, 3-13
 Interconnector Pump Station, 3-14
 Interconnector Sewer, 1-8, 3-3, 5-9, 6-3, 6-41
 Jackson Pike WWTP, 1-1, 3-1
 Land, 2-1, 2-18
 Land Application 1-4, 1-8, 5-38
 Land Use, 4-10, 6-85
 Long Terra Solids Handling Report, 5-2
 Lime Stabilization, 5-36
 Man-made Environment, 2-54
 Municipal Compliance Plan, 1-10
 National Environmental Policy Act (NEPA), 1-11
 Natural Environment, 2-1
 Nitrification, 5-16
 No Action Alternative, 5-7
 Noise, 6-86
 Notice of Intent, 1-12
 NPDES Permits, 1-5, 1-6, 1-9, 3-5, 5-15, 6-31
 Odors, 2-5, 6-54
Olentangy River, 2-8
Oientangy - Scioto Intercepter Sewer (O.S.I.S.), 3-1
One-Plant Alternative, 5-9, 6-15
Operational Convenience, 6-3

-------
                               INDEX (Continued)
 Option A/A-1,  5-57,  6-4
 Option B/B-1,  5-57,  6-4
 Option JP-A, 5-40
 Option JP-B, 5-42, 6-13
 Option JP-C, 5-43, 6-13
 Option SO-A, 5-46
 Option SO-B, 5-46
 Option SO-C, 5-49, 6-12
 Option SO-D, 5-51, 6-12
 Option SO-E, 5-53
 Option SO-F, 5-55, 6-12
 Peak Process Flow, 4-28
 Phosphorus, 2-15
 Planning Area, 1-1, 4-9
 Planning Period, 1-10, 4-2
 Population, 1-9, 4-2
 Post Aeration, 6-18, 6-21, 6-25, 7-6
 Preaeration, 6-18, 6-21, 6-25, 7-5
 Precipitation, 2-3, 4-20
 Primary Settling, 6-18, 6-21, 6-25
Public Finance, 2-74
 Public Health, 2-69, 6-87
Public Safety, 2-67, 6-108
Public Service 2-60, 6-104
Public Utilities, 2-65
Pumping,  7-1,  7-6

-------
                               INDEX  (Continued)

Record of Decision, 1-12
Recreation, 2-72, 6-90
Reliability, 6-2
Revised Faculties Plan Update, 1-5,  1-8, 5-6
Scioto River, 5-10
Screening, 7-1
Screening of Alternatives, 5-57
Secondary Impacts, 1-10, 6-93
Secondary Settling, 6-7
Semi-Aerobic, 1-8, 5-16, 6-7,  7-5
Service Area, 4-9
Sewer Maintenance Yard, 3-3
Sewer Service, 2-63, 4-11, 6-104
Sewer System, 2-65
Single-stage Activated Sludge, 5-2.1
Sludge Building, 5-16, 7-5
Sludge Line, 1-4, 5-9, 6-14
Sludge, Metals, 5-31
Soils, 2-20, 6-67
Solids Handling Alternatives, 5-39
Solids Disposal, 5-27, 6-10, 7-11
Southerly WWTP, 1-1, 3-13
Southwesterly Composting Facility, 3-30
Supplemental Environmental Impact Statement (SEIS), 1-7
Surface Water Flows, 6-46
Surface Water Quality, 1-6, 1-10, 2-12, 6-31
Suspended Solids, 3-5, 4-29

-------
                               INDEX  (Continued)

Terrestrial Biota, 2-22, 6-69
Thermal Conditioning,  1-4, 5-34, 5-44, 6-14
Thickening, Centrifuge, 5-32,  6-11
Thickening, Gravity, 5-32, 6-11
Threatened and Endangered Species, 2-51, 6-79
Topography, 2-18
Traffic, 6-107
Traffic Zones, 4-16
Transportation, 2-61,  6-91, 6-105
Treatment Plant, Jackson Pike, 1-1, 3-1
Treatment Plant, Southerly, 1-1, 3-13
Trickling Filter/Activated Sludge, 5-20, 6-7
Two-Plant Alternative, 5-8, 6-16, 6-112, 7-1
Two-Stage Activated Sludge, 5-25
User Charges, 6-28, 7-11
Vegetation, 6-69
Walnut Creek, 2-8
Wastewater Flow, 4-17, 4-32
Wastewater Loads, 4-29, 4-32
Water Quality, 6-100
Water Service, 2-63, 4-12,  6-104
Water Use, 2-62, 4-21
Wetlands,  2-50, 6-69
Whit tier Street CSO, 2-42
Whittier Street Storm Standby Tanks,  3-1, 3-27, 4-18
Wildlife,  6-69

-------

-------
                                  REFERENCES


 Bazler,  Fat.   1987.   Personal communiction with Audrey Knight,  SAIC,  re:
      Boat  Use of the Scioto.   State Parks  and Recreation,  Division of
      Watercraft.  Columbus,  Ohio.

 Bell,  Henry.   1987.   Personal communication with Hunter Loftin,  SAIC, re:
      O'Shaughnessy Reservoir water  releases.   City of  Columbus,  January.
      Columbus,  Ohio.

 Bonk,  James.   1986.   Personal communication with Debbie Ryan, SAIC,  re:  Air
      quality  and odor issues.   Ohio EPA    October.   Columbus, Ohio.

 Bureau of  Economic Analysis.   1986.   Personal Income for Counties  and Other
      Municipalities  in Ohio.   Regional Economic Information  System, Report No.
      1840.  April.   Washington,  DC.  7  pp.

 Bureau of  the Census.   1983a.   City and  County Data Book,  1983
      GPO-1984-0-428-476.   November.   Washington,  D.C.   996 pp.

 Bureau of  the Census.   1983b.   1980 Census  of Population and Housing.  Report
      No. PHC-80-2-128.  July.   Washington,  D.C.   550 pp. + Appendix.

 Bureau of  the Census.   1983c.   County Business Patterns, 1982, Ohio.
      Washington,  D.C.

 Button,  Dr. B.   1986.   Personal  communication with  Hunter  Loftin,  SAIC, re:
      Groundwater Quality Testing Program.   Columbus Water  Quality  Research
      Laboratory.   January  9.

 Cavender, T.M.  and R.L. Crunkilton.   1974.  Impact  of  a  Mainstream Impoundment
      on  the Fish Fauna  of  Big  Walnut  Creek, A Scioto River Tributary  in
     Central  Ohio.   Project Completion Report  No. 449.   Prepared   for the U.S.
     Department  of Interior under contract  no.  A-037-OHIO. Columbus,  OH:
     Museum of  Zoology  Ohio State University.   191  pp.

 Cavender, T.M.   1982.   Scioto  Madtom  Survey,  1981-1982,  Report on  the  Status
     of  the Endangered  Species,  Noturus  trautmani.   Prepared for the  U.S. Fish
     and Wildlife  Service  under  contract no.  30181-126T, FY81.  Columbus, OH-
     Museum of  Zoology  Ohio State University.   53 pp.

 Cavender, Ted.   1986.   Personal  communication  with  Candy Bartoldus, SAIC, re:
     Scioto Madtom.  Ohio  State  University, November 19.   Columbus, Ohio.

 City of Columbus.  1974.  Watercourse Plan  for  Columbus  and Franklin  County.
     Columbus Dept. of  Recreation and Labrenz  Riemer Inc , Landscape
     Architects.  Columbus, Ohio.  142 pp.

City of Columbus.  1983.  Growth Potential Report.  Office of Management and
     Budget Strategic Planning.  August.   21 pp. plus Appendix.

City of Columbus.  1985.  The Columbus Development  Strategy.   Growth Potential
     1985-1995.  Columbus Office Management and Budget Strategic Planning.
     December   Columbus,  Ohio.  38 pp.

-------
                            REFERENCES (Continued)


City of Columbus.  1983a.  Consolidated Environmental Information Document
     (EID).  Prepared by URS Dal ton.  March 17.  Columbus, Ohio.  140 pp.

City of Columbus.  1986b.  City of Columbus 1987 Executive Budget.  November
     13.  Columbus, Ohio.  255 pp.

City of Columbus.  1986e.  Operating Report:  1985.  Division of Sewer and
     Drainage.  March 28.  Columbus, Ohio.  46 pp.

Columbus Area Chamber of Commerce.  1985.  The Columbus Fact Pack.  Columbus,
     Ohio.  35 pp.

Columbus Area Chamber of Commerce.  1986.  The New Residents Kit.  Regional
     Information Service.  July.  Columbus, Ohio.  6 separate information
     sheets and maps.

Dancey, William S.  1987.  Letter to Doug Woods, SAIC, re:  Archaeologic
     potential along the Scioto River.  Associate Professor of Anthropology,
     Ohio State University.  January 2.  2 pp.

Deitz, John.  1987.  Personal communication with Teresa Dowd, SAIC, re-
     Scioto River Easement Plan.  Park Planner, Department of Parks and
     Recreation, City of Columbus.  November 4.  Columbus, Ohio.

Development Committee for a Greater Columbus.  1986.  Greater Columbus
     Infrastructure and Financing Strategy.  The Urban Institute.  U.I.
     Project No. 3536-02.  December 5.  Columbus, Ohio.  103 pp. plus
     Appendix.

Federal Emergency Management Agency.  1987.  Flood Insurance Study, Franklin
     County, Ohio.  Vol. 1 of 2.  85 pp.

Federal Emergency Management Agency.  1987.  Flood Insurance Study, City of
     Columbus, Ohio.  Franklin and Fairfield Counties.  69 pp.

Fenner, Kenneth A.  1987.  Memo to Todd A. Cayer, Chief Municipal Facilities
     Branch, re:  Columbus, Ohio Water Quality.  Chief, Water Quality Branch,
     U.S. Environmental Protection Agency, Region V.  September 30.  Chicago,
     Illinois.  2 pp.

Francis, Jerry.   1987a.   Personal communication with Hunter Loftin, SAIC, re:
     Well design capacity,  water table elevations.  Administrator, Division of
     Sewage and Drainage for City of Columbus.  January 20.  Columbus, Ohio.

Francis, Jerry.   1987b.   Personal communication with Teresa Dowd, SAIC, re-
     Secondary impacts of growth and development.  Administrator, Division of
     Sewage and Drainage for City of Columbus.  January 20.  Columbus, Ohio.

Fritz,  Kenneth R.   1986   Letter to Candy Bartoldus, SAIC, re:  Endangered
     wildlife information   Ohio Department of Natural Resources.  December 5.
     Columbus, Ohio.

-------
                            REFERENCES  (Continued)


Gammon,  J.R.  1976.   The fish  populations  of  the  middle 340  kilometers of the
      Wabash River.   Purdue  University Water  Resources  Resources  Center
      Technical  Report  86.   73 pp.

Goldthwait, R.P., G.W.  White,  and  J  L Forsyth.   1961.   Glacial map of Ohio.
      U.S.  Department of Interior,  Geological Survey, Miscellaneous Geological
      Investigations.  Hap 1-316.

Higgins, F.   1858.   A  catalogue of the  shell-bearing species, inhabitating  the
      vicinity of Columbus,  Ohio, with some remarks  thereon.   12th  Annual
      Report Ohio State  Board  of Agriculture  for  1857.   pp.  548-555.

Hughes,  Charles.  1987.  Personal  communication  with Hunter Loftin,  SAIC, re:
      Safe  yields of  wells and current pumping volumes.   Parsons  Avenue Water
      Treatment  Plant.   October 22    Columbus, Ohio.

Humphrey,  S.R., A.R. Richter,  and  J.B Cope.   nd.  Summer habitat and ecology
      of  the endangered  Indiana Bat,  Myotis sodalis.

Institute  of  Traffic Engineers.  1976.  Transportation and  Traffic Engineering
      Handbook.  Prentice-Hall International,  3rd edition, revised.   Englewood
      Cliffs,  New Jersey.  1080 pp.

Kramer,  Chief.  1986.   Personal communication with Teresa Dowd,  SAIC,  re:
      Secondary  impacts  of growth and  development on fire and  police
      protection.  Franklin  County  Sheriff's  office   December 8.   Columbus,
      Ohio.

Lowen, Steve.   1987.  Personal communication with Teresa Dowd, SAIC,  re:
      Secondary  impacts  of growth and  development upon  public  schools.   Teacher
      on  Special Assignment, Columbus  Public  Schools.   January 5.   Columbus,
      Ohio.

McCarthy,  W   L.  1986.  Ohio  Environmental Protection  Agency, Division  of
      Water Pollution Control.  Letter to Mrs. Rachel Lanning.  January  15.
      Columbus, Ohio.

Malcolm  Pirnie, Inc.  1983.   CSO Report (Part I), Columbus, Ohio.  July.
      Columbus, Ohio.

Maxwell, A.F.  1986.  Letter with  Odor Log Attachment  to William McCarthy.
      Ohio  Environmental Protection Agency.   January 30

Mid-Ohio Regional Planning Commission.  1977a.  Technical Report on  Year 2000
      Land  Use and Trip Generation Variables.  May.  Columbus, Ohio.   31  pp.
      plus  Appendix.

Mid-Ohio Regional Planning Commission.  1977b.  Public Services and  Facilities
      Profile:   Police Protection Services, Franklin, Ohio.  August.  Columbus,
     Ohio.   53 pp.

Multerer, Kenneth.    1986.  Personal communication with Candy Bartoldus, SAIC,
     re:   Endangered wildlife.  U.S. Fish and Wildlife Service.   December 2.

-------
                            REFERENCES (Continued)


Ohio Data Users Center.   1985.  ODUC Population Projections.  Ohio Department
     of Economic Development.  September.  Columbus, Ohio.  n.p.

Ohio Department of Natural Resources.  1983.  Rare Species of Native Ohio Wild
     Animals.  Ohio Department of Natural Resources, Division of Natural Areas
     and Preserves.  Columbus, Ohio

Ohio Department of Natural Resources.  1960.  Ohio Water Plan Inventory.  Map
     of the Mill Creek Basin and a Portion of the Middle Scioto River Basin,
     Underground Water Resources.  Ohio Department of Natural Resources,
     Division of Water.   Columbus, Ohio.

Ohio Environmental Protection Agency.  1986a.  Central Scioto River Mainstem
     Comprehensive Water  Quality Report (Final Diaft).  Ohio Environmental
     Protection Agency, Division of Water Pollution Control and Division of
     Water Quality Monitoring and Assessment.  385 pp. plus Appendices.

Ohio Environmental Protection Agency   1986b.  Water Quality Inventory, 1986
     305(b) Report, Volume II.  Division of Water Quality Monitoring and
     Assessment.  Columbus, Ohio.  500 pp. plus Index.

Ohio Environmental Protection Agency.  1985.  Division of Air Pollution
     Control.  Ohio Air Quality Report 1985   Columbus, Ohio.  n.p.

Ohio Environmental Protection Agency   1985b   Land Application of Sludge
     Manual.  Division of Water Pollution Control.  August.  Columbus, Ohio.
     44 pp.

Ohio Environmental Protection Agency.  1983.  Central Scioto River Mainstem
     Comprehensive Water Quality Report.  Division of Wastewater Control.
     416 pp.

Ohio Environmental Protection Agency.  1981.  Director's Final Finding and
     Orders in the Matter of-  City of Columbus Southwesterly Composting
     Facility.  Columbus, Ohio   n.p.

Olive,  J.H.  1971.   A study of biological communities in the Scioto River as
     indices of water quality.  Ohio Biological Survey and Water Resources
     Center, Ohio State University.  U.S.  Department of the Interior.
     Washington, DC.  n.p.

Phinne, G.J.  1967.  An ecological comparison of two streams in central Ohio,
     Ph.D.  Dissertation,  The Ohio State University.   137 pp.

Schaefer,  Ron.  1987.   Personal communication with Audrey Knight, SAIC, re:
     Fish catches in the Scioto River.   District 1 Fish Manager, State
     Department of  Natural Resources, Division of Wildlife.  January 6.
     Columbus, Ohio.

Shindel,  Harold and Callie Childress.  1987.  Personal communication with
     Hunter Loftin, SAIC, re:  Groundwater in Franklin County.   U.S. Geologic
     Survey.  Columbus,  Ohio.  September 28.

-------
                            REFERENCES  (Continued)
Shindel, H.L., J.H. Klingler, J.P. Mangus, and  L.E. Trimble.   1986.   Water
     Resources Data,  Ohio.   Water  Year  1985,  Volume 1,  Ohio River  Basin.  U.S.
     Geological  Survey.   Water-Data  Report OH-85-1.   Columbus,  Ohio.   338 pp.

Slaughter, Rex.   1987.   Personal communication  with Audrey Knight,  SAIC, re:
     Dock  rentals on  the Scioto River.   Permit  Officer, City  of Columbus,
     Department  of Recreation & Parks.   January 12.   Columbus,  Ohio

Smith, P.W,   1971.  Illinois streams: a classification  based  on their fishes
     and an analysis  of  factors responsible for the disappearance  of  native
     species.  Illinois  Natural History Survey,  Biological Notes 76.

Soil Conservation Service   1977.  Licking County, Ohio, Atlas  Sheet  No. 65.
     Happed by R.J. Parkinson November  25, 1977.  U.S.  Department  of
     Agriculture.  Newark, Ohio.

Soil Conservation Service.   1978.  Licking County, Ohio, Atlas  Sheet  No. 56.
     Mapped by M.  Wigginton  June 14, 1978.  U.S. Department of  Agriculture.
     Newark,  Ohio.

Soil Conservation Service.   1979.  Licking County, Ohio, Atlas  Sheet  No. 38.
     Mapped by T.  Sims November 26,  1979.  U.S.  Department of Agriculture.
     Newark,  Ohio.

Soil Conservation Service.   1980a.   Soil Survey of Franklin County, Ohio.
     U.S. Department  of  Agriculture, Soil Conservation  Service, in  cooperation
     with Ohio Department of Natural Resources,  Division of Lands and Soil,
     and Ohio Agricultural Research  and Development Center.  U.S. Department
     of Agriculture.  Washington, DC    188 pp.  and maps.

Soil Conservation Service.   1980b  Soil Survey  of Pickaway County,  Ohio.  U.S.
     Department of Agriculture, Soil Conservation Service in cooperation with
     Ohio Department  of  Natural Resources, Division of  Lands and Soil, and
     Ohio Agricultural Research and Development  Center.  U.S. Department of
     Agriculture.  Washington, DC.   172 pp. and  maps.

Soil Conservation  Service.   1981.  Licking County, Ohio, Atlas  Sheet  No. 73.
     Mapped by R.J. Parkinson December,  1981.    U.S. Department  of Agriculture.
     Newark, Ohio.

Soil Conservation Service.   1982.  Licking County, Ohio, Atlas  Sheet  No. 29.
     Mapped by M. Wigginton April 29, 1982.  U.S. Department of Agriculture.
     Newark, Ohio.

Stansbury.  D.H.   1961.  A century of change in  the naiad population of the
     Scioto River System  in Central Ohio.  Annual Report for 1961 of  the
     American Malacologists Union:  20:22

Stansbury,  David.  1986.   Personal communication with Marlene Stern,  SAIC,  re
     Mollusks in  the Scioto River.   Ohio State University Museum of Zoology.
     November 19.  Columbus,  Ohio.

-------
                               REFERENCES (Continued)


   Stansbury, David.  1987.  Personal communication with Harlene Stern, SAIC, re:
         Endangered unionid mollusks in the Scioto River.  Ohio State University.
         October 30.  Columbus, Ohio.

   Thomson, T.  1983.  Birding in Ohio.  Bloomington, Indiana:  Indiana
        University Press.  256 pp.

   URS Dalton   1986   City of Columbus Consolidated Environmental Information
        Document.  March.  Columbus, Ohio.

   U.S. Environmental Protection Agency.  1978.  Draft Environmental Impact
        Statement Wastewater Treatment Facilities for the Metropolitan Area
        Columbus, Ohio. Chicago, Illinois,  v.p.

   Watts, David.  1987.  Personal communication with Marlene Stern, SAIC,  re:
        Waterfowl along the Scioto River.  U S. Fish and Wildlife Service.
        January.  Columbus, Ohio

   Witlatch, E.E. and M J. Martin.  1985.  Water Use in Central Ohio.  1984 Data
        Base.  Ohio State University Department of Civil Engineering   September
        30.  Columbus, Ohio.  191 pp.

   Yoder, C.O.,  P.  Albeit, and H.A. Smith.  1981.  The distribution and abundance
        of fishes in the mains tern Scioto River as affected by pollutant loadings.
        Ohio EPA Technical Report 81/3.  Ohio Environmental Protection Agency.
        Columbus, Ohio.

   Yoder, Chris.  1987a.  Letter to Marlene Stern, SAIC, re:  Index of biotic
        integrity.   Ohio Environmental Protection Agency.  January.  Columbus,
        Ohio.

   Yoder, Chris.  1987b.  Personal communication with Marlene Stern, SAIC, re:
        Fish communities and data from the Scioto River.  Ohio Environmental
        Protection  Agency.  January.  Columbus, Ohio.
* U a GOVERNMENT PRINTING Of f ICE 1987  542 877

-------